Appendix — City of Cincinnati, Ohio v. Cleveland Construction Construction Construction, Inc. (No. 07-113)

Supreme Court brief2007

Ask Donna

What actually matters in this document.

Text

APPENDIX A

SUPREME COURT OF OHIO

2007-0114

[Filed May 2, 2007]

Cleveland Construction, Inc.

Appellant/Cross-Appellee,

V.

City of Cincinnati, et al

Appellees/Cross-Appellants.

)

)

)

)

)

)

)

)

Hamilton App. Nos. C-050749, C-050779, and C-050888,

2006 Ohio 6452, 864 N.E.2d 116. Cleveland Constr., Inc.

v. City of Cincinnati, 2006 Ohio 6452, 864 N.E.2d 116,

2006 Ohio App. LEXIS 6410 (Ohio Ct. App., Hamilton

County, 2006)

JUDGES: O’Donnell, J., would accept the appeal.

Lanzinger, J., would accept the appeal. Pfeifer and Cupp, JJ.,

dissent.

OPINION:

APPEAL ACCEPTED FOR REVIEW

2a

Discretionary appeal accepted on Proposition of Law Nos.

J and Ill.

O’Donnell, J., would accept the appeal on Proposition of Law

No. I only. Lanzinger, J., would accept the appeal on

Proposition of Law No. III only. Pfeifer and Cupp, JJ.,

dissent.

APPENDIX B

IN THE SUPREME COURT OF OHIO

CASE NO. 07-0114

APPEAL NO. C050749, APPEAL NO. C050779

APPEAL NO. C050888

(Consolidated)

[Filed January 22, 2007]

CITY OF CINCINNATI

Defendant-Appellant

Vv.

CLEVELAND CONSTRUCTION, INC.

Plaintiff-Appellee

i i i i i ed

COURT OF APPEALS

FIRST APPELLATE DISTRICT

CASE NO. A-0402638

MEMORANDUM IN SUPPORT OF JURISDICTION OF

DEFENDANT-APPELLANT CITY OF CINCINNATI

4a

JULIA L. MCNEIL (0043535)

City Solicitor

RICHARD GANULIN (0025642C)

MARY FRANCES CLARK (0077497)

Assistant City Solicitors

CITY OF CINCINNATI

801 Plum Street, Room 214

Cincinnati, Ohio 45202

Telephone: (513) 352-3329

Facsimile: (513) 352-1515

richard.ganulin @cincinnati-oh.gov

mary .clark @ cincinnati-oh.gov

Attorneys for Defendant-Appellant

City of Cincinnati

W. KELLY LUNDRIGAN (0059211)

GARY E. POWELL (0037546)

MANLEY BURKE

225 West Court Street

Cincinnati, Ohio 45202

Telephone: (513) 721-5525

Facsimile: (513) 721-4268

wk].@manleyburke.com

gpowell@manleyburke.com

Attorneys for Plaintiff-Appellee

Cleveland Construction, Inc.

kok ok &

TABLE OF CONTENTS

EXPLANATION OF WHY THIS CASE IS A

CASE OF PUBLIC AND GREAT

GENERAL INTEREST

STATEMENT OF THE CASE AND FACTS ..

ARGUMENT IN SUPPORT OF PROPOSITIONS

OF LAW

Proposition of Law No. I

Under Ohio law, a disappointed bidder for a City

of Cincinnati public contract does not have a

constitutionally protected property interest in that

contract

Proposition of Law No. 2

To prove a deprivation of its right to procedural

due process, a disappointed bidder with a

constitutionally protected property interest in a

public contract must establish that the government

entity did not provide sufficient notice and

opportunity to be heard

Proposition of Law No. 3

A disappointed bidder for a public contract in

Ohio cannot recover lost-profit damages in a 42

U.S.C. 1983 action alleging a deprivation of

procedural due process

6a

Proposition of Law No. 4

A plaintiff does not have standing to seek an

injunction against file operation of a municipal

corporation unless the plaintiff pleads and proves

a concrete and imminent injury in fact

Proposition of Law No. 5

A subcontracting outreach program is not

impermissibly race-based or gender-based when

all bidders have an equal opportunity to comply

with the subcontracting outreach program and the

program does not create a preference

* KK KK

APPENDIX C

IN THE COURT OF APPEALS

FIRST APPELLATE DISTRICT OF OHIO

HAMILTON COUNTY, OHIO

APPEAL NO. C-050749, C-050779, C-050888

[Filed January 18, 2007]

CLEVELAND CONSTRUCTION, INC.

Appellant/Cross-Appellee,

CITY OF CINCINNATI, et al.

Appellees/Cross-Appellants.

)

)

)

VS. )

)

)

)

)

ENTRY GRANTING MOTION

TO STRIKE APPLICATION

FOR RECONSIDERATION

This cause came on to be considered upon the application

of the appellees/cross-appellants for reconsideration, the

motion of the appellant/cross-appellee to strike the application

as untimely filed, and the response of appellees/cross-

appellants to the motion to strike.

The Court finds that the motion to strike the application

for reconsideration is well taken and is hereby granted.

To The Clerk:

Enter Upon the Journal of the Court on Jan 18 2007_ per

order of the Court.

By: /s/ (Copies sent to all counsel)

Acting Presiding Judge

APPENDIX D

IN THE COURT OF APPEALS

FIRST APPELLATE DISTRICT OF OHIO

HAMILTON COUNTY, OHIO

APPEAL NOS. C-050749, C-050779, C-050888

TRIAL NO. A-0402638

[Filed December 8, 2006]

CLEVELAND CONSTRUCTION, INC.,

Plaintiff-Appellant/

Cross-Appellee,

VS.

CITY OF CINCINNATI,

Defendant-Appellee/

Cross-Appellant,

and

TIMOTHY RIORDAN,

BERNADINE FRANKLIN,

NATE MULLANEY

ALICIA TOWNSEND,

KATHI RANFORD,

and

VALLEY INTERIOR SYSTEMS, INC.,

Defendants-Appellees.

JUDGMENT ENTRY

This cause was heard upon the appeal, the record, the

briefs, and arguments.

The judgment of the trial court is affirmed in part,

reversed in part, and cause remanded for the reasons set forth

in the Opinion filed this date.

Further, the court holds that there were reasonable

grounds for this appeal, allows no penalty and orders that

costs are taxed under App. R. 24.

The court further orders that 1) a copy of this Judgment

with a copy of the Opinion attached constitutes the mandate,

and a) the mandate be sent to the trial court for execution

under App. R. 27.

To The Clerk:

Enter upon the Journal of the Court on December 8, 2006

per Order of the Court.

By: /s/Hildebrandt

Presiding Judge

APPENDIX E

IN THE COURT OF APPEALS

FIRST APPELLATE DISTRICT OF OHIO

HAMILTON COUNTY, OHIO

APPEAL NOS. C-050749, C-050779, C-050888

TRIAL NO. A-0402638

[Filed December 8, 2006]

CLEVELAND CONSTRUCTION, INC.,

Plaintiff-Appellant/

Cross-Appellee,

vs.

CITY OF CINCINNATI,

Defendant-Appellee/

Cross-Appellant,

and

TIMOTHY RIORDAN,

BERNADINE FRANKLIN,

NATE MULLANEY,

ALICIA TOWNSEND,

KATHI RANFORD,

and

VALLEY INTERIOR SYSTEMS, INC.,

Defendants-Appellees.

——

Civil Appeals From: Hamilton County Court of Common

Pleas.

Judgment Appealed From Is: Affirmed in Part, Reversed in

Part, and Cause Remanded.

Date of Judgment Entry on Appeal: December 8, 2006

SYLVIA SIEVE HENDON, Judge.

OPINION

{41} This case arose from the city of Cincinnati’s

rejection of a bid by Cleveland Construction Co. for drywall

work on the expansion and renovation of the Cincinnati

Convention Center. At the heart of the dispute was the city’s

implementation of its small business enterprise (SBE)

program.

{€2} Cincinnati Municipal Code (CMC) 321-37 required

the city to award a construction contract to the lowest and best

bidder. The ordinance set forth a non-exhaustive list of factors

that the city purchasing agent could consider in determining

the lowest and best bid. One of the factors that could be

considered was a contractor’s compliance with the rules and

13a

regulations of the city’s SBE Subcontracting Outreach

Program.’

{43} Where a lowest-and-best determination was based

primarily on the contractor’s subcontracting-outreach

compliance, the ordinance had a built-in cap. The contract

award could be made, “subject to the following limitation: the

bid could not exceed an otherwise qualified bid by ten (10%)

percent or Fifty Thousand Dollars ($50,000.00), whichever

is lower.” The cap was apparently intended to strike a

balance between the city’s efforts to include small businesses

in public contracts and the city’s interest in protecting its

taxpayers from excessive costs.

{44} On December 23, 2003, the city issued an

invitation to bid on the Cincinnati Convention Center

Expansion and Renovation Project, entitled “Bid Package

C/TC-09A Drywall.” The city required bidders to show that

they had made a good-faith effort to obtain the participation

of SBEs on the project. For the drywall-contract bids, the city

established a mandatory SBE-participation goal of 35%.

Bidders were notified that their failure to meet the SBE-

participation goal could cause a bid to be rejected as

nonresponsive. The city received bids until February 5, 2004.

{(5} On February 11, 2004, Kathi Ranford, a contract

compliance officer, reported to Bernadine Franklin, the city’s

purchasing agent, that none of the three bidders for the

project’s drywall contract had complied with the 35% SBE-

participation requirement. According to Ranford, Cleveland

' CMC 321-37(c)(4).

? CMC 321-37(c).

l4a

had submitted a bid with 3% SBE participation, Valley

Interior Systems had submitted a bid with 34% SBE

participation, and Kite, Inc. , had submitted a bid with no SBE

participation. In that round of bidding, Cleveland’s bid had

been the lowest-dollar bid.

{{6} Because none of the bidders had achieved the full

35% SBE-participation goal, the city conducted an emergency

rebidding for the drywall contract. On February 24, 2004,

Ranford notified Franklin that Cleveland had submitted a re-

bid for $8,889,000, with 10% SBE participation, and that

Valley had submitted a re-bid for $10,135,022, with 40%

SBE participation.

{€7} The city’s office of contract compliance deemed

Cleveland’s bid to be unacceptable due to its failure to

achieve 35% SBE participation. In all other respects,

however, Cleveland’s bid had been found acceptable

according to the city’s purchasing division.

{48} Following a review of the acceptability of the bids,

Franklin issued a recommendation to Timothy Riordan, an

assistant city manager, that the drywall contract be awarded

to Valley. Franklin’s recommendation stated, “Pursuant to

Section 321-37 of the Municipal Code, the bid submitted by

[Valley] has been determined to be the lowest and best bid.”

{€9} Valley’s new bid exceeded Cleveland’s new bid by

$1,246,022, well over the $50,000 or 10% cap in CMC 321-

37. Nonetheless, on March 3, 2004, the city awarded the

drywall contract to Valley and instructed Valley to commence

work under the terms of the contract.

15a

Cleveland Files Suit

{410} Three weeks later, on March 30, 2004, Cleveland

brought an action for injunctive relief and damages against the

city, several city employees, and Valley. Cleveland asked the

court to restrain the city and Valley from proceeding on the

drywall contract and to order the city to award the contract to

Cleveland.

{411} In addition, Cleveland sought declarations by the

court that (1) the city’s award of the contract violated CMC

321-37; (2) the city’s drywall contract with Valley was void;

(3) the city’s SBE program was unconstitutional and in

violation of Section 1983, Title 42, U.S.Code; (4) the city

had deprived Cleveland of a property interest; (5) Cleveland

was the lowest and best bidder; and (6) the city’s delegation

of discretion to its purchasing agent under the SBE

subcontracting-outreach program was void.

{412} Finally, Cleveland sought compensatory and

punitive damages, as well as attorney fees and costs.

{413} The trial court denied Cleveland’s motion for a

temporary restraining order. Later, upon moiion, the trial

court dismissed the city employees from the action.

{414} In June 2005, the case proceeded to a jury trial. At

the close of Cleveland’s case, the trial court directed a verdict

in favor of the city and Valley on Cleveland’s claims for lost

profits. Cleveland’s remaining claims for injunctive and

declaratory relief and attorney fees were tried to the bench,

by agreement of the parties.

{415} At the conclusion of the trial, the court found that

the city had violated CMC 321-37 by awarding the drywall

16a

contract to Valley rather than to Cleveland. As a result, the

court held, the city had abused its discretion in a manner that

had denied Cleveland the contract in violation of its federally

protected due-process rights and in violation of Section 1983.

{416} The court held that the city’s SBE program rules

and guidelines created race- and gender-based classifications

that rendered the program facially unconstitutional. The court

further found that the city had pressured and encouraged

bidders, including Cleveland, to draw upon race- and gender-

based classifications, in violation of Cleveland’s rights under

Section 1983. But the court held that Cleveland had failed to

establish that the denial of the drywall contract was the result

of the race- and gender-based classifications; rather, it held

that the denial had been the result of the city’s preference for

small businesses.

{417} The court rendered a declaratory judgment that

precludes the city from awarding future contracts to a bidder

that exceeds the cap set forth in CMC 321-37 if the bid

selection is based primarily on the bidders’ compliance with

the SBE subcontracting-outreach program.

{418} The court permanently enjoined the city from

maintaining or applying race-or gender-based classifications

in its SBE rules and guidelines, absent a formal determination

that such race-based provisions were narrowly tailored and

necessary to fulfill compelling governmental interests, or that

such gender-based provisions were substantially related to

genuine and important governmental objectives.

{419} Finally, the court entered judgment in favor of

Cleveland as the prevailing party, and against the city, for

Cleveland’s reasonable attorney fees and costs pursuant to

17a

Section 1988, Title 42, U.S. Code. The court also entered

judgment in favor of Valley.

{420} On appeal, Cleveland argues that the trial court

erred by (J) directing a verdict in favor of the city on

Cleveland’s damage claims; (2) refusing to declare Valley’s

drywall contract to be void or to prohibit performance under

the contract; (3) ruling that Cleveland could not elicit

testimony from Valley’s subcontractors with respect to post-

contract events; (4) denying Cleveland’s motion for a new

trial; (5) granting the motions to dismiss individual city

employees; and (6) making findings concerning causation of

damages.

{21} In its cross-appeal, the city argues that the trial

court (1) erred by applying CMC 321-37; (2) lacked

jurisdiction over Cleveland’s claims for injunctive relief; (3)

erred by concluding that the city had deprived Cleveland of

its right to procedural due process; (4) erred by ruling that

portions of the city’s SBE program created constitutionally

impermissible race- and gender-based classifications; and (5)

erred by awarding attorney fees to Cleveland. We first

address the city’s assignments of error.

The Application of CMC 321-37

{422} In its first assignment of error, the city argues that

the trial court erred by applying CMC 321-37 in its analysis

of Cleveland’s claims. The city contends that Franklin had not

applied the provisions of CMC 321-37 in her review of bids

for the project because the ordinance had not been in place at

the time the project’s “procurement process” was planned.

{423} The record reflects that CMC 321-37 had been

adopted in specific contemplation of the convention center

18a

project. By its terms, the ordinance had been enacted as an

emergency measure due to the city’s “immediate need to

proceed with the bidding of the Convention Center and major

development projects.” The ordinance specifically applied to

the award of construction contracts that exceeded $100,000.

And the ordinance had gone into effect before the project’s

bid solicitation, and well before the award of the drywall

contract. So Franklin’s selection of the lowest and best bidder

was subject to CMC 321-37.

{924} The city argues that “[e]ven though Valley’s bid

was $1.2 million more than Cleveland’s, the project was well

within the budget.” This argument fails to take into account

that “among the purposes of competitive bidding legislation

are the protection of the taxpayer [and the] prevention of

excessive costs.”* The fact that the project was under budget

was of questionable relevance and was certainly not

dispositive of the legality of the bid-selection process.

{425} The city argues that even if Franklin had applied

CMC 321-37 to the drywall-contract bids, the ordinance’s cap

would not have come into play because Cleveland’s bid was

not an “otherwise qualified” bid. But the city acknowledges

in its brief that “[t}he trial evidence established that Cleveland

lost because its ¢rywall bid failed to reserve at least 35% of

the work for small business enterprises as the bid documents

required.” In other words, but for its SBE noncompliance,

Cleveland’s bid was qualified. Where the sole reason that

Cleveland’s bid was rejected was its noncompliance with the

SBE subcontracting-outreach program, Cleveland was an

“otherwise qualified” bidder. Under these circumstances,

* Danis Clarkco Landfill Co. v. Clark Cty. Solid Waste Mgmt Dist.,

73 Ohio St.3d 590, 602, 1995 Ohio 301, 653 N.E.2d 646.

19a

Valley’s SBE-compliant bid could not have exceeded

Cleveland’s bid by the $50,000 or 10% cap.

{426} Accordingly, we hold that the trial court properly

considered and applied CMC 321-37. We overrule the city’s

first assignment of error.

Cleveland’s Standing

{427} In its second assignment of error, the city argues

that the trial court lacked jurisdiction over Cleveland’s claims

for injunctive relief. The city contends that the possibility that

Cleveland might bid on a city contract in the future did not

create a risk that it would again be subject to a deprivation of

rights.

{428} In Ohio, it is well established that standing to

challenge the constitutionality of a legislative enactment exists

where a litigant “has suffered or is threatened with direct and

concrete injury in a manner or degree different from that

suffered by the public in general, that the law in question has

caused the injury, and that the relief requested will redress the

injury.” *

{429} In the context of a constitutional challenge to a set-

aside program, the “injury in fact” is the inability to compete

on an equal footing in the bidding process, and not necessarily

the loss of a contract. So to establish standing, a party

challenging a set-aside program need only demonstrate that it

* State ex rel. Ohio Acad. of Trial Lawyers v. Sheward, 86 Ohio

Si.3d 451, 469-470, 1999 Ohio 123, 715 N.E.2d 1062.

20a

is able and ready to bid on contracts and that a discriminatory

policy prevents it from doing so on an equal basis.”

{430} At trial, the city specifically stipulated that

Cleveland intended and was able to bid on future city

construction projects. And the city’s discriminatory policies

would have affected Cleveland’s ability to compete fairly. So

Cleveland had sufficient standing to seek injunctive relief

against the city. We overrule the city’s second assignment of

error.

Deprivation of a Property Interest

{431} Inits third assignment of error, the city argues that

the trial court erred by concluding that the city had deprived

Cleveland of a right to procedural due process.

{€32} One of the proscriptions of the Fourteenth

Amendment is the deprivation of a person’s property interests

without due process of law.° In a due-process challenge based

upon such a deprivation, we must first determine whether a

protected property interest was at stake.

{933} Property interests “are created and their

dimensions are defined by existing rules or understandings

that stem from an independent source such as state law-rules

or understandings that secure certain benefits and that support

> Northeastern Fla. Chapter of Associated Gen. Contractors of Am.

v. Jacksonville (1993), 508 U.S. 656, 666, 113 S. Ct. 2297, 124 L.

Ed. 2d 586.

° Bd. of Regents v. Roth (1972), 408 U.S. 564, 569-570, 92 S. Ct.

270i, 33 L. Ed. 2d 548.

2la

claims of entitlement to those benefits.”’ A person has a

property interest in a benefit, such as a public contract, if the

person has a legitimate claim of entitlement to it.* A person’s

unilateral expectation of a benefit is not enough.’

{434} The Sixth Circuit Court of Appeals has held that a

disappointed bidder may establish a legitimate claim of

entitlement to a public contract in one of two ways. A bidder

can either show that it actually was awarded the contract and

then deprived of it, or that the government abused its limited

discretion in awarding the contract to another bidder.’

{435} Generally, municipalities are vested with broad

discretion in matters related to public contracts. But that

discretion is not limitless.'' For example, a municipality “may

by its actions commit itself to follow rules it has itself

established.” !”

{436} In the context of lowest-and-best-bidder

determinations, Ohio courts are reluctant to substitute their

” Id. at 577, 92 S. Ct. 2701.

® Cleveland Constr. v. Ohio Dept. of Admin. Servs., GSA (1997),

121 Ohio App. 3d 372, 394, 700 N.E.2d 54.

° Roth, supra, at 577, 92 S. Ct. 2701.

'© United of Omaha Life Ins. Co. v. Solomon (C.A.6, 1992), 960

F.2d 31, 34; Enertech Elec. v. Mahoning County Commrs. (C.A.6,

1996), 85 F.3d 257, 260.

'' Danis, supra, at 604, 1995 Ohio 301, 653 N.E.2d 646.

'2 Id. at 603, 1995 Ohio 301, 653 N.E.2d 646.

22a

judgment for that of city officials.’? But where city officials

abuse the discretion vested in them, courts will intervene.”

An abuse of discretion “connotes more than an error of law

or of judgment; it implies an unreasonable, arbitrary, or

unconscionable attitude. * * * ‘Arbitrary’ means ‘without

adequate determining principle; * * * not governed by any

fixed rules or standard .’ * * * ‘Unreasonable’ means

‘irrational.’”!

{437} In this case, the city had established a “fixed rule”

with respect to the award of a contract based primarily upon

the bidder’s subcontracting-outreach program compliance. In

that instance, CMC 321-37 required the city to apply the

ordinance’s cap.

{9438} But, here, the evidence demonstrated that the city

had arbitrarily ignored the cap in awarding the contract to

Valley. Thus, we agree with the trial court that the city’s

failure to follow the directive of its own ordinance constituted

an abuse of discretion that resulted in a deprivation of

Cleveland’s property interest in the contract award. We

overrule the city’s third assignment of error.

SBE Program Provisions Were Facially Unconstitutional

{439} In its fourth assignment of error, the city argues

that the trial court erred by ruling that elements of the rules

'5 See Cedar Bay Constr., Inc. vy. Fremont (1990), 50 Ohio St.3d

19, 552 N.E.2d 202.

'* Id. at 21-22, 552 N.E.2d 202.

'? Dayton, ex rel. Scandrick v. McGee (1981), 67 Ohio St.2d 356,

359, 423 N.E.2d 1095 (emphasis added).

23a

and guidelines in the city’s SBE program created

constitutionally impermissible race- and gender-based

classifications. The city contends that the program was a

lawful “outreach” program that encouraged contractors to use

“good faith efforts” to promote opportunities for minorities

and females.

{440} The Fourteenth Amendment requires strict scrutiny

of all race-based action by state and local governments."°

Racial classifications must serve a compelling government

interest and must be narrowly tailored to further that

interest.'’ Gender-based classifications, by contrast, require

an “exceedingly persuasive” justification.”

{441} At trial, the city did not put forth any argument or

evidence to demonstrate that its SBE program could withstand

such heightened scrutiny. Instead, the city relied on its

assertion that increased scrutiny should not apply in the first

instance because its SBE program created neither race- nor

gender-based classifications.

{442} On appeal, the city acknowledges that it had

predetermined estimates of the availability of minorities and

females for each trade represented in the convention center

project. But the city argues that its availability estimates were

'© Richmond v. J.A. Croson Co. (1989), 488 U.S. 469, 109 S. Ct.

706, 102 L.. Ed. 2d 854.

'7 Adarand Constructors v. Pena (1995), 515 U.S. 200, 235, 115

S. Ct. 2097, 132 L. Ed. 2d 158.

'§ United States v. Virginia (1996), 518 U.S. 515, 533, 116 S. Ct.

2264, 135 L. Ed. 2d 735:

24a

for informational purposes only, and that bidders were

required to do nothing in response.

{443} Racial or gender classifications may arise from a

regulation’s strict requirements, such as mandated quotas or

set-asides. But rigid mandates are not a prerequisite to a

finding of a racial classification. '? Where regulations pressure

or encourage contractors to hire minority subcontractors,

courts must apply strict scrutiny.”

{944} For example, in Adarand Constructors v. Pena,”’

the United States Supreme Court considered federal

regulations that provided financial incentives to bidding

contractors to hire minority subcontractors. The regulations

did not require contractors to use minority subcontractors. But

contractors would receive additional compensation if they did

so. The court held that, to the extent that the regulations

provided incentives to contractors to use race-based

classifications, the regulations were subject to strict scrutiny.”

{445} In determining whether strict scrutiny must be

applied to the city’s SBE program, we must look behind its

ostensibly neutral labels such as “outreach program” and

“participation goals.” The program’s rules and guidelines

'° Bras v. Calif. Pub. Utils. Comm. (C.A.9, 1995), 59 F.3d 869.

0 See Lutheran Church-Missouri Synod v. FCC (C.A.D.C., 1998),

332 U.S. App. D.C. 165, 154 F.3d 487; Monterey Mechanical Co.

v. Wilson (C.A.9, 1997), 125 F.3d 702; Safeco Ins. Co. of America

v. White House (C.A.6, 1999), 191 F.3d 675.

71 (1995), 515 U.S. 200, 115 S. Ct. 2097, 132 L. Ed. 2d 158.

? Id. at 224, 115 S. Ct. 2097.

25a

“are not immunized from scrutiny because they purport to

establish ‘goals’ rather than “quotas.’[Courts] look to the

economic realities of the program rather than the label

attached to it.”

{446} Under the city’s SBE rules and guidelines, all

bidders were required to use “good faith efforts” to promote

opportunities for minority- and women-owned businesses

(MBEs and WBEs) to the extent of their availability as

determined by the city. With respect to the drywall portion of

the project, the city estimated that the availability of MBEs

was 13.09%, and that it was 1.05% for WBEs.

{447} Bidders were required to provide detailed

descriptions of the techniques used to obtain participation of

MBEs and WBEs. The city would then evaluate each bidder’s

documented efforts to achieve participation of MBEs and

WBEs. If that review determined that a bid’s utilization

percentage for MBEs and WBEs was lower than the estimated

availability for those groups, the bid would be flagged for a

discrimination investigation.

{448} Where the city’s SBE program required

documentation of a bidder’s specific efforts to achieve the

participation of minority subcontractors to the extent of their

availability as predetermined by the city, the program

undeniably pressured bidders to implement racial

preferences.’ Therefore, the program’s rules must be subject

to strict scrutiny. To the extent that the rules pressured

bidders to hire women-owned subcontractors, the city was

> Bras, supra, at 874.

** Safeco Inc., supra, at 692, citing Lutheran, supra, at 491.

26a

required to demonstrate an “exceedingly persuasive”

justification for the differential treatment.

{449} Given that the city effectively conceded that it

could not justify race- or gender-based classifications under

either standard of heightened scrutiny, the trial court properly

determined that those elements of the program that caused

bidders to use racial- or gender-based preferences were

unconstitutionally impermissible.

Award of Attorney Fees

{450} In its fifth assignment of error, the city argues that

the trial court erred by awarding attorney fees to Cleveland.

The city contends that Cleveland was not entitled to the award

because it was not a prevailing party.

{4513} A “prevailing party” is one who “succeed[s] on

any significant issue in litigation which achieves some of the

benefit the parties sought in bringing suit.” To be a

“prevailing party,” there must have been “a court-ordered

‘change [in] the legal relationship’” between the parties.”° In

this regard, a declaratory judgment may serve as the basis for

an award of attorney fees.”

> Hensley v. Eckerhart (1983), 461 U.S. 424, 433, 103 S. Ct.

1933, 76 L. Ed. 2d 40.

6 Buckhannon Bd. v. W. Va. Dept. of Health & Human Res.

(2001), 532 U.S. 598, 604, 121 S. Ct. 1835, 149 L. Ed. 2d 855.

2? Hewitt v. Helms (1987), 482 U.S. 755, 761, 107 S. Ct. 2672, 96

L. Ed. 2d 654.

27a

{452} But the entry of a declaratory judgment in a party’s

favor does not automatically render that party a prevailing

party under Section 1988.”* “In all civil litigation, the judicial

decree is not the end but the means. At the end of the rainbow

lies not a judgment, but some action (or cessation of action)

by the defendant that the judgment produces-the payment of

damages, or some specific performance, or the termination of

some conduct. Redress is sought through the court, but from

the defendant. This is no less true of a declaratory judgment

suit than of any other action. The real value of the judicial

pronouncement - what makes it a proper judicial resolution of

a ‘case or controversy’ rather than an advisory opinion - is in

the settling of some dispute which affects the behavior of the

defendant towards the plaintiff .” (Emphasis in original.)”

{453} We hold that the trial court did not abuse its

discretion in ordering attorney fees. Cleveland successfully

challenged the unconstitutional race- and gender-based

provisions of the city’s SBE program. As a result, the city

will no longer be permitted to apply those provisions against

Cleveland or other bidders on city contracts. In that regard,

Cleveland was a prevailing party because the judgment had a.

distinct effect on the city’s behavior. Accordingly, we

overrule the city’s fifth assignment of error.

Directed Verdict

{954} In its complaint, Cleveland sought damages for the

loss of profits that it would have realized had it been awarded

*8 Rhodes v. Stewart (1988), 488 U.S. 1, 109 S. Ct 202, 102 L.

Ed. 2d 1.

*? Hewitt, supra, at 761, 107 S. Ct. 2672

28a

the drywall contract. Cleveland now argues in its first

assignment of error that the trial court erred by directing a

verdict in favor of the city on its lost-profits claim.

{455} In considering a motion for a directed verdict, a

trial court must construe the evidence most strongly in favor

of the party against whom the motion is made.” In doing so,

if the court “finds that upon any determinative issue

reasonable minds could come to but one conclusion upon the

evidence submitted and that conclusion is adverse to such

party, the court shall sustain the motion and direct a verdict

for the moving party as to that issue.”*

{456} “A motion for directed verdict * * * does not

present factual issues, but a question of law, even though in

deciding such a motion, it is necessary to review and consider

the evidence.”*” Because a question of law is presented, we

apply a de novo standard of review to a directed verdict.®

{457} Cleveland acknowledges that the Ohio Supreme

Court’s recent decision in Fairlawn v. Cementech™ resolves

*® Civ.R. 5O(A)(4).

3! Civ.R. SO(A)(4).

Goodyear Tire & Rubber Co. v. Aetna Cas. & Sur. Co., 95 Ohio

St.3d 512, 2002 Ohio 2842, 769 N.E.2d 835, “4, quoting O’Day

v. Webb (1972), 29 Ohio St.2d 215, 280 N.E.2d 896, paragraph

three of the syllabus.

3 Cleveland Elec. Illum. Co. v. Pub. Util. Comm., 76 Ohio St.3d

521, 523, 1996 Ohio 298, 668 N.E.2d 889.

* 109 Ohio St.3d 475, 2006 Ohio 2991, 849 N.E.2d 24.

29a

its claim for damages under state law. In Cementech, the

court held that when a municipality violates competitive-

bidding laws in awarding a competitively bid project, a

disappointed bidder cannot recover its lost profits as damages.

{458} But in addition to its claim for damages under state

law, Cleveland sought damages under federal law, Section

1983, Title 42, U.S.Code, for the city’s deprivation of its

property interest in the drywall contract. Under Section 1983,

a party who has been deprived of a federal right under the

color of state law may seek relief through “an action at law,

Suit in equity, or other proper proceeding for redress.”

{459} The basic purpose of a Section 1983 damage award

is to compensate persons for injuries caused by the

deprivation of constitutional rights.” For this reason, no

compensatory damages may be awarded in a Section 1983 suit

without proof of actual injury. The level of a person’s

compensatory damages under Section 1983 is ordinarily

determined according to principles derived from the common

law of torts.*’

{460} In Adarand Constructors v. Pena,*® the United

States Supreme Court considered whether a rejected bidder

had standing to seek injunctive relief against future application

*® Carey v. Piphus (1978), 435 U.S. 247, 253-254, 98 S. Ct. 1042,

55 L. Ed. 2d 252.

°° Memphis Community Sch. Dist. v. Stachura (1986), 477 U.S.

299, 306, 106 S. Ct. 2537, 91 L. Ed. 2d 249.

*” Id. at 306-307, 106 S. Ct. 2537.

** (1995), 515 U.S. 200, 115 S. Ct. 2097, 132 L. Ed. 2d 158.

30a

of a minority set-aside program. In doing so, the Court

presumed that the rejected bidder was entitled to seek

damages for the lost contract:

{461} “Adarand, in addition to its general prayer for

‘such other and further relief as to the Court seems just and

equitable,’ specifically seeks declaratory and injunctive relief

against any future use of subcontractor compensation classes.

* * * Before reaching the merits of Adarand’s challenge, we

must consider whether Adarand has standing to seek forward-

looking relief. Adarand’s allegation that it has lost a contract

in the past because of a subcontractor compensation clause of

course entitles it to seek damages for the loss of that contract

[.]” (Emphasis added.)

{462} Those damages may include a disappointed

bidder’s lost profits.” In W.H. Scott Constr. Co., Inc. v.

Jackson,“ the Fifth Circuit Court of Appeals considered an

equal-protection challenge to a policy encouraging minority

participation in city construction projects. The court upheld an

award of lost profits to a rejected bidder who had sought

damages from the city under Section 1983.

{463} Similarly, in Hershell Gill Consulting Engineers,

Inc. v. Miami-Dade Cty., Fla.,*' the court held that a county

was liable to the plaintiffs under Section 1983 for any

compensatory damages resulting from its unconstitutional

affirmative-action programs. The court held that the plaintiffs’

9 See Flores v. Pierce (C.A.9, 1980), 617 F.2d 1386, 1392;

Chalmers v. Los Angeles (C.A.9, 1985), 762 F.2d 753.

“” (C.A.5, 1999), 199 F.3d 206.

“ (S.D.Fla.2004), 333 F. Supp. 2d 1305.

3la

damages could include their lost profits, but that the plaintiffs

in that case had failed to prove that any actual losses had

resulted from the unconstitutional programs.*

{464} In this case, the trial court concluded that

Cleveland’s failure to adduce evidence concerning the degree

of completion of the drywall contract precluded Cleveland

from proceeding on its claim for money damages. The court

reasoned that Cleveland’s damages were speculative, not due

to a failure of proof as to Cleveland’s anticipated profits, but

due to the court’s misapprehension that Cleveland’s damage

claim was wholly dependent on its claim for injunctive relief.

{465} Certainly, the status of the drywall project would

have been relevant to a determination of any injunctive relief

the court may have awarded, but that evidence was not

critical to Cleveland’s claim for Section 1983 damages. In

effect, the trial court’s entry of a directed verdict on the

damage claim precluded Cleveland from seeking redress,

even though Cleveland could have waited to file suit until the

drywall contract had been completed. The issuance of a

directed verdict on the issue of Section 1983 damages before

the contract’s completion had the absurd result of denying

redress because of Cleveland’s diligence in asserting its

claims.

{466} We recognize that a plaintiff seeking redress under

Section 1983 is required to mitigate its damages.*’ But once

the plaintiff has presented evidence of damages, the

defendant has the burden of establishing the plaintiffs failure

** Id. at 1339.

* Meyers v. Cincinnati (C.A.6, 1994), 14 F.3d 1115, 1119.

32a

to properly mitigate damages.“ So once Cleveland presented

evidence of damages, the burden of proof on the issue of

mitigation was on the city.

{467} Because a jury could have concluded that

Cleveland had established all the elements of its Section 1983

claim for damages, we hold that a directed verdict in favor of

the city was unwarranted. Consequently, we sustain

Cleveland’s first assignment of error in part, reverse the entry

of the directed verdict on the Section 1983 damage claim, and

remand the case for a new trial on the issues of liability and

damages with respect to Cleveland’s lost-profits claim under

Section 1983.

{468} Because Cleveland’s fourth and sixth assignments

of error relate to the trial court’s dismissal of its damage

claims, we address the assignments out of order. Cleveland

argues that the trial court erred by denying its motion for a

new trial, given the court’s erroneous dismissal of its damage

claim under Section 1983. Cleveland also contends that the

trial court erred by making “a finding that, essentially,

amount[ed] to a directed verdict on the issue of proximate

causation of Cleveland’s damages in addition to that given at

trial.” For the reasons set forth in our disposition of

Cleveland’s first assignment of error, we sustain the fourth

and sixth assignments of error.

The Denial of Injunctive Relief

{469} In its second assignment of error, Cleveland argues

that the trial court erred by refusing to declare the drywall

* Id., citing Rasimas v. Michigan Dept. of Mental Health (C.A.6,

1983), 714 F.2d 614.

33a

contract unenforceable and by failing to enjoin performance

of the contract. Cleveland contends that the trial court should

have enjoined performance of the contract despite the fact that

substantial work had been completed on the project.

{470} An appellate court need not consider an issue

where the court becomes aware of an intervening event that

has rendered the issue moot.* The duty of an appellate court

is to decide actual controversies between parties and to render

judgments that may be carried into effect.“ “Thus, when

circumstances prevent an appellate court from granting relief

in a case, the mootness doctrine precludes consideration of

those issues.”*’ For example, in the context of appeals

involving construction projects, Ohio courts have held that an

appeal is rendered moot where the appellant fails to obtain a

stay of execution of the trial court’s judgment and

construction commences.“

{{71} In this case, there is no dispute that the convention

center project, which was substantially completed at the time

*° Cincinnati Gas & Elec. Co. v. PUC of Ohio, 103 Ohio St.3d

398, 2004 Ohio 5466, 816 N.E.2d 238, at 415, citing Miner v. Witt

(1910), 82 Ohio St. 237, 238, 92 N.E. 21, 8 Ohio L. Rep. 71.

“© Miner, supra, at 238, 92 N.E. 21.

*’ Schwab v. Lattimore, 166 Ohio App. 3d 12, 2006 Ohio 1372,

848 N.E.2d 912, at 410.

** Schuster v. Avon Lake, 9" Dist. No. 03CA008271, 2003 Ohio

6587, at 43; Pinkney v. Southwick Invs., L.L.C., 8" Dist. Nos.

85074 and 85075, 2005 Ohio 4167; Bd. of Commrs. v. Saunders,

2” Dist. No. 18592, 2001 Ohio 1710; Smola v. Legeza, 11" Dist.

No. 2004-A-0038, 2005 Ohio 7059; Redmon v. City Council, 10"

Dist. No. OSAP-466, 2006 Ohio 2199.

34a

that the trial court denied the injunction, is now completed in

its entirety. At no point in the proceedings did Cleveland

obtain a stay of the trial court’s denial of its request for a

temporary restraining order. In fact, as the trial court pointed

out, Cleveland did not pursue preliminary injunctive relief for

an entire year. Instead, Cleveland acceded to several

continuances. In denying Cleveland’s motion for a

preliminary injunction, the trial court noted the following:

{472} “The court at this time will deny Cleveland’s

motion for injunctive relief pending trial. The parties’ desires

with regard to the scheduling of this case have been solicited

on a regular basis. After the action was removed to and

returned from federal court, Cleveland opted not to seek a

prompt hearing on [a] preliminary injunction, but sought

rather to engage in the extended discovery reflected in the

voluminous materials relating to the summary judgment

motions. Cleveland then waited to the final day of the

dispositive motion period - almost one year after the action

was filed and roughly three months prior to the scheduled

June 20, 2005 trial date - to pursue its preliminary injunction

request.”

{473} At this point, we can not render a judgment that

could be carried into effect with respect to the performance of

the drywall contract. Even if we concluded (which we

expressly do not) that the trial court had erred in failing to

enjoin the contract’s performance, our opinion would only be

advisory in nature. Consequently, we decline to address the

assignment of error on its merits.

Evidentiary Rulings

{974} In its third assignment of error, Cleveland argues

that the trial court erred by ruling that it could not elicit

35a

testimony from Valley’s subcontractors about events that had

occurred after the city had awarded the contract to Valley. In

support of its argument, Cleveland directs us to its

examination of one of Valley’s subcontractors, Marti

Stouffer-Heis, owner of MS Construction Consultants.

{{75} “Relevant evidence” is defined by Evid.R. 401 as

“evidence having any tendency to make the existence of any

fact that is of consequence to the determination of the action

more probable or less probable than it would be without the

evidence.” Evid.R. 402 provides that relevant evidence is

admissible, subject to enumerated exceptions, and that

evidence that is not relevant is not admissible. Although the

terms of Evid.R. 402 are mandatory, a trial court is vested

with broad discretion in determining whether evidence is

relevant.” A reviewing court is, therefore, limited to a

determination of whether the trial court abused its discretion

in admitting or excluding the disputed evidence.”

{476} Cleveland’s attorney attempted to elicit testimony

from Stouffer-Heis about the city’s post-award enforcement

of its SBE program. Counsel asked whether Stouffer-Heis had

been able to perform trer described “[ljogistics, project

coordination” tasks at the construction site, and whether the

city had performed amy imvestigation upon submission of her

request to be certified as an SBE supplier.

{477} The trial court indicated that it would allow

testimony by a subcontractor with respect co the current status

® See Cincinnati v. Banks (2001), 143 Ohio App. 3d 272, 287, 757

N.E.2d 1205: Siuda v. Howard, i“ Dist. Nos. C-000656 and C-

000687, 2002 Ohio 2292, €25.

© See Banks, supra.

36a

of the uncompleted project. And the court expressly permitted

counsel to question Stouffer-Heis about whether she had been

certified as an SBE supplier prior to the contract award. But

the court instructed counsel to otherwise restrict his

questioning to matters that had occurred prior to the contract

award to Valley, because Cleveland’s complaint had been

predicated on the rejection of its bid.

{478} We find no abuse of discretion by the trial court in

ruling that testimony related to post-award program

enforcement was irrelevant and inadmissible. We overrule

Cleveland’s third assignment of error.

Dismissal of City Employees

{479} In its fifth assignment of error, Cleveland argues

that the trial court erred when it granted the individual

defendants’ motion to dismiss. The trial court dismissed

Cleveland’s claims against city employees Riordan, Franklin,

Mullaney, Townsend, and Ranford in their “personal and

individual capacities,” on the basis of qualified immunity.

Cleveland had also sued the employees in their “official

capacities.” Because the trial court did not explicitly dismiss

the claims against the employees in their official capacities,

we treat the official-capacity claims as claims against the

city.”

{480} The doctrine of qualified immunity generally

shields public officials performing discretionary functions

from liability for civil damages to the extent that their conduct

>' See Asher Investments, inc. v. Cincinnati (1997), 122 Ohio App.

3d 126, 137, 701 N.E.2¢ 400; Norwell v. Cincinnati (1999), 133

Ohio App. 3d 790, 729 N.E.2d 1223.

37a

does not violate clearly established statutory or constitutional

rights of which a reasonable person would have known.”

{481} The doctrine recognizes the strong public interest

in protecting public officials from the costs of defending

against claims. A public official’s entitlement to avoid the

burdens of litigation “is an immunity from suit rather than a

mere defense to liability; and like an absolute immunity, it is

effectively lost if a case is erroneously permitted to go to

trial.”°? To this end, a ruling on the issue of qualified

immunity should be made as early as possible in the

proceedings, before the commencement of discovery.” “[A]

quick resolution of a qualified immunity claim is essential.”

{{82} “Where a defendant official is entitled to qualified

immunity, the plaintiff must plead facts which, if true,

describe a violation of a clearly established statutory or

constitutional right of which a reasonable public official,

under an objective standard, would have known. The failure

to so plead precludes a plaintiff from proceeding further, even

from engaging in discovery, since the plaintiff has failed to

* Harlow v. Fitzgerald (1982), 457 U.S. 800, 818, 102 S. Ct.

2727, 73 L. Ed. 2d 396.

3 Mitchell v. Forsyth (1985), 472 U.S. 511, 526, 105 S. Ct. 2806,

86 L. Ed. 2d 411.

4 Id.

** Will v. Hallock (2006), 546 U.S. 345, 126 S. Ct. 952, 960, 163

L. Ed. 2d 836.

38a

allege acts that are outside the scope of the defendant’s

immunity.”*°

{483} In this case, Cleveland alleged that the city

employees had violated its rights to due process and equal

protection by failing to apply the cap in CMC 321-37 and by

rejecting its bid as nonresponsive after applying provisions of

a race-conscious program. These allegations were insufficient

as a matter of law to describe a violation of a clearly

established constitutional right. As demonstrated by the

complex nature of the issues already discussed, the individual

defendants could not have reasonably known that their actions

were unconstitutional. Accordingly, we overrule Cleveland’s

fifth assignment of error.

Conclusion

In conclusion, we reverse the trial court’s entry of a

directed verdict on Cleveland’s claim for lost profits under

Section 1983. We remand the cause for a new trial on the

issues of liability and damages under Section 1983. In all

other respects, the trial court’s judgment is affirmed.

Judgment accordingly.

HILDEBRANDT, P.J., and PAINTER, J., concur.

*© Salt Lick Bancorp v. FDIC (May 30, 2006), C.A.6 Ne. 05-5291,

__ F.3d ___, 187 Fed. Appx. 428, citing Kennedy v. Cleveland

(C.A.6, 1986), 797 F.2d 297, 299.

APPENDIX F

COMMON PLEAS COURT

HAMILTON COUNTY, OHIO

CASE NO: A0402638

[October 7, 2005]

Cleveland Construction, Inc.,

Plaintiff,

City of Cincinnati, et al.,

Defendants.

)

)

)

)

)

)

)

)

ENTRY DENYING PLAINTIFF’S MOTION

FOR A NEW TRIAL

This matter comes before the court on Plaintiff's motion

for a new trial based on Plaintiff's position that “the Court’s

ruling dismissing Cleveland’s damage remedy [relating to

claimed lost profits and uncertain bid preparation costs] was

error....” Plaintiff's motion for a new trial at 5. Plaintiff's

position here clearly is not precluded by Plaintiff's earlier

observation (in the fee award context) that: “As the Court

(and the City) realize, cases where lost profits have been

awarded in competitive bidding scenarios involving equal

protection challenges are practically nonexistent. Most cases

involving successful equal protection challenges to programs

40a

such as the one at issue here result in relief of exactly the

same nature as that granted here.” Reply Memorandum in

Support of Motion of Plaintiff for Award of Attorney Fees

and Costs (August 22, 2005) at 7. Nonetheless, for reasons

already set forth by the court, including those discussed in the

court’s post-trial entry of July 13, 2005, the court does not

find Plaintiff's argument here well taken. The motion is

denied.

SO ORDERED.

Judge Nelson, Judge

Kelly Lundrigan, 225 West Court Street, Cincinnati,

OH 45202

Leonard Weakley, Jr., One West Fourth Street, Suite

900, Cincinnati, OH

David Barth, 537 East Pete Rose Way, Suite 400,

Cincinnati, OH 45202

APPENDIX G

COURT OF COMMON PLEAS

HAMILTON COUNTY, OHIO

Case No. A0402638

[Filed August 29, 2005]

Cleveland Construction,

Plaintiff,

City of Cincinnati, et al.,

Defendants.

)

)

)

)

)

)

)

)

FINAL JUDGMENT ENTRY

This final judgment entry is based on and incorporates in

full the court’s post-trial entry of July 13, 2005.

As set forth in that prior entry, the court finds and

adjudges that:

1) Defendant the City of Cincinnati (“the City”) violated

the requirements of Cincinnati Municipal Code

Section 321-37 (“Bid; Award to Lowest and Best”) in

awarding the Convention Center drywall contract at

issue to Defendant Valley Interior Systems, Inc.

(“Valley”) rather than to Plaintiff Cleveland

42a

Construction, Inc. (“Cleveland Construction”) when

the award was “based primarily upon” compliance

with the City’s Subcontracting Outreach Program and

Valley’s bid exceeded Cleveland Construction’s by

$1,246,022.00. That additional cost exceeded the

$50,000 cap established by Code Section 321-37, and

the City acknowledged that Cleveland Construction

was otherwise qualified to perform the work. In

making its award, the City abused its discretion in a

manner that harmed the public and denied Cleveland

Construction the contract in violation of Cleveland

Construction’s federally protected due process rights

and in violation of 42 U.S.C. Section 1983.

The City’s Small Business Enterprise program Rules

and Guidelines as in effect at the time of contract

award and trial create race and gender based

classifications for which the City claims no compelling

governmental! interest and offers no basis to satisfy

any appropriate intermediate scrutiny review. The

program is to that extent unconstitutional on its face.

Further, in the process of soliciting bids in this matter,

the City did pressure and encourage bidders, including

Plaintiff, to draw upon race and sex-based

classifications that the City concedes could not

withstand the heightened level of review that the court

finds mandated by governing law. The City in that

regard violated Cleveland Construction’s rights under

42 U.S.C. Section 1983. However, Cleveland

Construction failed to establish that the City’s race and

sex based classifications (as opposed to the City’s

small business preference) resulted in the loss of the

contract at issuc.

43a

Further, the court enters a declaratory judgment, in favor

of Cleveland Construction and against the City, that City

Code Section 321-37(c) in its current form provides, among

other things, that where the City elects to enter into a

construction contract on the basis of the “lowest and best”

bid, and where that selection is based primarily upon the

City’s determination of the bidders’ relative compliance with

the City’s SBE Subcontracting Outreach Program rules and

regulations, the City may not award the contract to a bidder

whose bid amount exceeds an otherwise qualified bid by ten

percent or fifty thousand dollars.

The court also enters a declaratory judgment, in favor of

Cleveland Construction and against the City, that the City’s

SBE Rules and Guidelines as of the date of trial, and as

promulgated by the City as official policy pursuant to City

ordinance, contain race and sex based classifications that

violate the equal protection clause of the United States

Constitution.

The court also enters judginent against the City by

permanent injunction prohibiting the City from maintaining or

applying any iteration of the SBE Rules and Guidelines

provisions specified at pages 13-14 of the court’s July 13,

2005 post-trial entry, or any substantially comparable

provisions making race or gender based classifications

through similar formulations, absent a formal, public

determination by the City establishing that such provisions

are, in the case of racial classifications, narrowly tailored to

advance a compelling goverrtmental interest, or, in the case

of gender classifications, substantially related to genuine and

important governmental objectives. The court notes that the

City acknowledged during this litigation that it was not in a

position to make such showings. For the reasons set forth in

its July 13, 2005 entry, the court does not enjoin drywall

44a

work (well under progress at this stage) with regard to the

Convention Center project.

The court also enters judgment in favor of Cleveland

Construction, as the prevailing party and against the City, for

its reasonable attorney fees and costs pursuant to 42 U.S.C.

Section 1988, in the amount of $433,290.00. In arriving at

that figure, the court has declined to award fees for certain

preliminary and post-trial activities and for certain matters

relating to potential expert witness testimony on matters not

directly relevant to the issues presented to the court. The

court has reviewed Cleveland Construction’s fee application

in light of prevailing standards (see, e.g., Grycza v. Steger

[6" Dist. App. 1994], 97 Ohio App. 3d 82, 84 [“ordinarily a

prevailing plaintiff should recover its attorneys fees”];

Buckhannon Bd. and Care Home, Inc. v. W. Va. Dept Health

and Human Resources [2001], 532 U.S. 598; Morscott, Inc.

v. City of Cleveland [6" Cir. 1991 ], 936 F.2d 271 [absent

special circumstances, trial court “’must’” award fees to the

prevailing plaintiff]), and with regard for the degree of

success obtained through judicially enforceable remedies that

alter the contemplated future legal relationship of the parties.

The court does not find the City’s memorandum in opposition

to any fee award persuasive (including the City’s less than full

account of its shifting positions on whether its own Rules and

Guidelines even had been formally promulgated, cf. City’s

May 11, 2005 brief at 13 arguing that the Rules and

Guidelines as attached to Cleveland Construction’s amended

complaint “do not have the force of law” and are not “official

policy” - a matter of significance to both prongs of Plaintiff's

action).

Cow costs as recorded by the Clerk of Courts are

asses. te the Defendants to be shared equally between them.

Although Valley’s legal arguments did not prevail to the (very

45a

considerable) extent that they mirrored the arguments of the

City on those issues as to which the court awards judgment to

Plaintiff Cleveland Construction against the City, the court

awards no separate relief against Valley and enters judgment

for Valley to that effect for the reasons stated in the July 13,

2005 post-trial entry.

This is a final order and there is no just cause for delay.

The Clerk of Courts is directed to serve notice of this final

judgment upon the parties in accordance with the civil rules.

SO ORDERED

/s/

Fred Nelson

Judge

cc: Kelly Lundrigan, 225 West Court Street, Cincinnati, OH

45202 (fax: 721-4268)

Leonard Weakley, Jr., One West Fourth Street, Suite

900, Cincinnati, OH 45202 (fax: 381-9206)

David Barth, 537 East Pete Rose Way, Suite 400,

Cincinnati, OH 45202 (fax: 852-8222)

46a

APPENDIX H

COURT OF COMMON PLEAS

HAMILTON COUNTY, OHIO

CASE NO.: A040263

[Filed August 19, 2005]

CLEVELAND CONSTRUCTION, INC.,

Plaintiff,

-:

CITY OF CINCINNATI, et al.,

Defendants.

AGREED ENTRY

It is agreed by counsel for the City and Cleveland

Construction Company that the hearing scheduled for August

19, 2005 at 1:30 p.m. for Cleveland’s Motion for legal fees

is hereby moved to a report hearing on August 26, 2005 at

2:30 p.m. as counsel has agreed to submit the issue on briefs

to the Court. All other agreements and prior Orders or Entries

stay in effect. Counsel for Cleveland Construction Company

will submit its Reply Brief on or before August 22, 2005.

/s/

Judge Nelson

HAVE SEEN:

Julia L. McNeil, Esq. #0043535

City Solicitor

/s/

Leonard A. Weakley, Jr., Esq. #0000152

Christopher J. Aluotto, Esq. #0059555

Attorneys for the City of Cincinnati

RENDIGS, FRY, KIELY AND DENNIS LLP

One West Fourth Street, Suite 900

Cincinnati, Ohio 45202

Phone: 513-381-9269 / Fax: 513-381-9206

E-mail: lweakley@rendigs.com

cja@rendigs.com

and

Julie F. Bissinger, Esq. #0012055

Chief Counsel

Trial Attorneys for the City of Cincinnati

Assistant City Solicitor

Room 214, City Hall

801 Pium Street

Cincinnati, Ohio 45202

Phone: 513-352-3346

/s/

[Per Telephone Authorization of 8/19/05}

Kelly M. Lundrigan, Esq.

Manley Burke

225 West Court Street

Cincinnati, Ohie 45202-1098

Copies Sent to:

Kelly M. Lundrigan, Esq.

Manley Burke

225 West Court Street

Cincinnati, Ohio 45202-1098

Julie F. Bissinger, Esq.

Chief Counsel

Room 214, City Hall

801 Plum Street

Cincinnati, Ohio 45202

Julia LaRita McNeil, Esq.

Assistant City Solicitor

Room 214, City Hall

801 Plum Street

Cincinnati, Ohio 45202

Fred A. Ungerman, Jr., Esq.

Coolidge Wall Womsley & Lombard

33 W. First Street

Suite 600

Dayton, Ohio 45402

David L. Barth, Esq.

Cors & Bassett, LLC

537 East Pete Rose Way, Suite 400

Cincinnati, Ohio 45202

APPENDIX I

IN THE COURT OF COMMON PLEAS

HAMILTON COUNTY, OHIO

Case No. A0402638

[Filed August 11, 2005]

Cleveland Construction, Inc.,

Plaintiff,

V.

City of Cincinnati, et al,

Defendants.

)

)

)

)

)

)

)

)

ENTRY

The Plaintiff issued a subpoena to Rendigs, Fry, Kiely &

Dennis, L.L.P for billing records related to this litigation.

The City of Cincinnati filed a Motion to Quash the subpoena.

The Court, after carefully considering the matter, and after

hearing arguments from counsel, made on August 4, 2005,

grants the City of Cincinnati’s Motion to Quash as expressed

on the record of the hearing.

| /s/

Date Judge Nelson

HAVE SEEN:

Robert E. Manley (0000849)

W. Kelly Lundrigan (0059211)

Gary E. Powell (0037546)

MANLEY BURKE

A LEGAL PROFESSIONAL ASSOCIATION

225 W. Court Street

Cincinnati, Ohio 45202

Attorneys for Cleveland Construction, Inc.

Leonard A. Weakley, Jr. (0000152)

Rendigs, Fry, Kiely & Dennis, L.L.P.

One West Fourth Street, Suite 900

Cincinnati, Ohio 45202

Attorney for City of Cincinnati

APPENDIX J

COURT OF COMMON PLEAS

HAMILTON COUNTY, OHIO

Case No. A0402638

[Filed July 20, 2005]

Cleveland Construction, Inc.,

Plaintiff,

City of Cincinnati, et al,

Defendants.

)

)

)

¥. )

)

)

)

)

ENTRY

By agreement of the parties, a hearing on attorneys fees

in this matter is established for August 9, 2005 at 3:00 p.m..

The parties request and agree that a final judgment entry be

deferred until a result is reached on fees after that hearing.

Plaintiff will file its Application for fees and costs by July 29,

2005, and serve Defendants in person or by telefax by that

date. The City agrees to observe and abide by the injunctive

restraint indicated in the Court’s post-trial entry of July 13,

2005 pending final judgment entry. The fee hearing relates to

a determination of Plaintiff's fees to be paid by the City.

52a

/s/

Judge Fred Nelson

Attorney (0059211)

/s/Leonard A. Weakley, Jr. atty for the City of Cincinnati

Attorney

/s/David L. Barth tty for Defendant Valley Interior

Systems, Inc.

APPENDIX K

COMMON PLEAS COURT

HAMILTON COUNTY, OHIO

CASE NO: A0402638

[Filed July 13, 2005]

Cleveland Construction, Inc.,

Plaintiff,

V.

City of Cincinnati, et al.,

Defendants

)

)

)

)

)

)

)

)

ENTRY

This matter proceeded to a trial on the merits of Plaintiff's

case combined with an evidentiary hearing on Plaintiffs

Motion for Preliminary Injunction pursuant to Civil Rule

65(B)(2) and under a schedule referenced in the court’s May

13, 2005 Entry Denying Defendants’ Motions for Summary

Judgment and Denying Plaintiff's Motion for Partial Summary

Judgment and [preliminary] Injunctive Relief {SJ Entry}. That

prior entry sets forth in some detail the legal context of this

action, which arises from a dispute relating to drywall work

for the expansion and renovation of Cincinnati’s Convention

Center. A jury was impaneled to address certain issues in the

case. after the court granted the motion of Defendant, the City

54a

of Cincinnati, for a directed verdict with regard to Plaintiff,

Cleveland Construction, Inc.’s, claim for lost profits, as

referenced below, the parties agreed that the litigation should

proceed as a trial to the court and the jury was discharged by

the consent of all sides (a matter as to which Plaintiff

subsequently took some issue). The trial now has concluded,

and the court has heard the evidence and counsels’ closing

arguments and also has reviewed the final materials presented

in writing.

I. The City violated its Code requirement, that a

determination to award a City contract primarily on the basis

of compliance with the City’s Subcontractor Outreach

Program (designed to favor subcontracting to small

businesses), not cost taxpayers more than $50,000 .00 beyond

the amount submitted in a lower and otherwise qualified bid.

The evidence is clear and the parties agree that in the

determinative second round of bidding to perform the drywall

work, the bid submitted by Plaintiff Cleveland Construction,

Inc. (“Cleveland,” or “Plaintiff’) was lower by

$1,246,022.00, than the bid submitted by Defendant, Valley

Interior Systems, Inc (“Valley”) Nonetheless, Defendant

City of Cincinnati (“the City”) awarded the drywall contract

to Valley as the “lowest and best” bidder, because Valley

agreed to subcontract at least 35% of the work to small

business enterprises (“SBEs”) while Cleveland did not.

Defendants have maintained throughout this litigation that

Plaintiff Cleveland was excluded from contract consideration

because it failed to meet the City’s SBE requirement. The

evidence provides no indication of other infirmities in

Cleveland’s bid or capacity to perform the work, and the City

previously had conceded that Cleveland was otherwise

qualified to perform the work, see SJ Entry at 10. The court

finds that the City’s 35% SBE requirement was the only

55a

reason that the City awarded the contract to Valley rather than

to Cleveland, despite the one and a quarter million dollar

difference between the bids.

The City’s Code section 321-37, “Bid, Award to Lowest

and Best,” provides in part:

“(a) Selection of Lowest and Best in Award of City

Contracts. Except where otherwise provided by

ordinance, the city purchasing agent shall award a

contract to the lowest and best bidder ...

(c) Factors to be Considered Other factors that the city

purchasing agent may consider in determining the lowest

and best bid include, but are not limited to [prior

performance, prevailing wage history, compliance with

nondiscrimination rules, and]

(4) Information concerning compliance with the ‘SBE

Subcontracting Outreach Program’ rules and regulations

issued by the city manager pursuant to section 323-31

In the event that the selection of the lowest and best bidder

is based primarily upon factors 3 or 4 above, the contract

award may be made subject to the following limitation: the

bid may not exceed an otherwise qualified bid by ten

(10%) percent or Fifty Thousand Dollars ($50,000.00),

whichever is lower,” (emphasis added).

As the court noted in its SJ Entry, the language of 321-37

establishes that “information concerning compliance” with the

City’s SBE Subcontracting Outreach Program rules and

regulations is a “[f]actor” that “may” be considered as the

City determines the lowest and best bid. If the lowest and best

bid is indeed selected “based primarily” on that factor, the

City may proceed to award the contract “subject to the

56a

following limitation: the bid may not exceed an otherwise

qualified bid by ten (10%) percent or Fifty Thousand Dollars

($50,000.00), whichever is lower,” 321-37(c)(4).

In that context, the phrase “otherwise qualified bid” can

reasonably be read only to mean a bid that is qualified except

that it is not in “compliance” with the SBE Subcontracting

Outreach Program “factor”. The bid not selected “primarily”

because of the SBE Subcontracting Outreach Program factor

must “otherwise” be qualified in order to trigger the required

calculation with regard to whether the contract award may be

made as selected on that basis. As the court also observed in

its SJ Entry at 15, the City Administration, through then

Assistant City Manager Rashid Young, advised Cincinnati

City Council’s Law and Public Safety Committee prior to

enactment of this 10%/$50,000.00 cap that, “[w]hat this

ordinance allows us to do is be clear about when it is

appropriate to award a bid to a SBE compliant [bidder] if they

are not the lowest. This ordinance would allow us to award a

bid if the bid is $50,000.00 or less difference away from the

lowest bid. We had an example where the SBE-compliant

bidder was some nine hundred thousand dollars in excess of

the lowest bid, and it doesn’t make a lot of sense to spend

nine hundred thousand dollars more to comply with the

regulations of SBE.” This explanation of a taxpayer

protection rationale for the cap is fully consistent with the

Code language that Cincinnati Council promptly adopted.

The 321-37(c) cap protecting Cincinnati taxpayers from

having to pay more than $50,000.00 extra (extra, that is,

beyond the amount established by a lower and otherwise

qualified bid) for the benefit of SBE Subcontracting Outreach

Program compliance was adopted in specific contemplation of

the Convention Center project; it took effect only months

before the contract at issue was awarded. See Plaintiff's trial

S7a

exhibit 13-A (noting that “this ordinance is an emergency

measure. The reason for the emergency is the immediate need

to proceed with the bidding of the Convention Center and

major development projects, which may be impacted by

Section 321-37 of the Cincinnati Municipal Code.”)

The court parsed the language of 321-37 at some length in

its SJ Entry (pages 10-23), and incorporates here that

Statutory construction. As earlier observed, the cap applies

specifically (and exclusively) to instances where a higher bid

is accepted because of “information concerning compliance

with ‘SBE Subcontractor Outreach Program rules,’ issued

pursuant to 323-31 [‘Subcontracting Outreach Program’}”

Code 321-37(c). (The Code’s reference to program “rules”

rather than to the program itself reflects a rather unusual

drafting approach through which City Council adopted its

Subcontracting Outreach Program simply by reference to a

consultant’s recommendations and through authorization of

administratively promulgated rules in the absence of any

further legislative definition of the Program Code 323-31.)

Until the eve of trial, the City had maintained that, despite

the clear instruction of Code Section 323-31 requiring that the

“City Manager shall issue rules and regulations to carry out

the meaning and purpose of the Subcontracting Outreach

Program,” the City had not formally promulgated its Small

Business Enterprise Program Rules and Guidelines containing

Subcontracting Outreach Program rules. See, e.g., City’s

March 11, 2005 Memo Opposing Plaintiff's MSJ at 13. At

trial, however, the City stipulated that the Small Business

Enterprise Program Rules and Guidelines introduced as

Plaintiffs exhibit 17 are what they purport to be and were, in

fact, adopted as of April 1, 2003. Those Rules and Guidelines

set forth at pages 4-22 the “Components of the [City’s] SBE

58a

Program,” including (at 9-14) the “Subcontracting Outreach

Program”.

As established by the City, the “Subcontracting Outreach

Program applies to City-funded construction contracts of

$100,000.00 or more,” /d. at 9. Further, the “Subcontracting

Outreach Program requires bidders to make subcontracting

opportunities available to a broad base of qualified

subcontractors and achieve a minimum of 20% (which may be

higher for construction of buildings) SBE subcontractor

participation. 7o be eligible for award of this project, the SBE

bidder must subcontract a minimum percentage of its bid to

qualified available SBE subcontractors,” Id. (emphasis

added). See also Plaintiffs trial ex. 5, the “legislative

recommendation” that City Council adopted by reference in

establishing the SBE Subcontractor Outreach Program and in

authorizing promulgation of rules and regulations therefore

(“Failure to comply with the City’s Subcontracting Outreach

Program will cause a bid to be rejected Terms and conditions

of this Subcontracting Outreach Program apply to City-funded

construction projects of $100,000.00 or more”). Thus, the

Subcontracting Outreach Program is a subset of the City’s

broader Smail Business Enterprise Program, it applies to all

City construction projects costing $100,000.00 or more, and

it incorporates requirements that a certain “minimum

percentage” of a bid go to qualified SBEs. With regard to

covered projects, the Subcontracting Outreach Program

establishes mechanisms for assuring a more firm

particularized, and project-specific SBE requirement than the

aspirational city-wide annual “goal” of 30% SBE participation

set forth at Section 323-7 of the Code. See also, e.g., trial

testimony of City consultant Rodney Strong (mandatory

aspect of Subcontracting Outreach Program minimum

percentage requirements).

59a

Having considered all of the evidence adduced, the court

finds by clear and convincing evidence that the award of the

contract at issue here was “based primarily” upon

“information concerning compliance with the ‘SBE

Subcontracting Outreach Program’ rules and regulations

issued pursuant to section 323-31.” Valley won the contract

on re-bid because it exceeded the 35% SBE participation

figure that the City established for this project under the SBE

Subcontracting Outreach Program, while Cleveland did not.

Plaintiff's trial exhibit 32, for example, is a City bid

document issued to the bidders on this projeci and setting

forth the applicable “SUBCONTRACTING OUTREACH

PROGRAM SUMMARY.” That program summary

prominently featured the “SBE Goals Per Trade Contract

Cincinnati Convention Center,” establishing that “All bidders

are required to meet the goal stated for the individual trade

contract Drywall 35%.” The Subcontracting Outreach

Program, to the extent of its legislative formulation, was in

place at the time of bid solicitation and the contract award

(and was to be applied to construction contracts of

$100,000.00 or more). See also, e.g., Riordan trial testimony

and Plaintiff's trial ex. 56 (1/21/03 memo contemplating

application to Convention Center project of legislation

containing Subcontracting Outreach Program authority). In

place later, but also in effect by the time of bid solicitation

and award, was the $50,000.00 taxpayer protection cap on the

amount that the program could cost the City on any one

contract -- and that limitation was part of a package enacted

specifically in contemplation of the Convention Center

project. That the cap was not in place during initial planning

stages of the project does not obviate iis mandate once

enacted.

Thus, the court finds that the City did violate a specific

prohibition of its own municipal Code in awarding the drywall

60a

contract to Valley as the “lowest and best bidder” over

Cleveland in order to favor small business enterprise

subcontracting despite the additional cost to taxpayers of some

$1,246,022.00 (an excess expenditure of $1,196,022.00

beyond what the 321-37 cap permits). Cincinnati’s local rules

limit the discretion of contracting officials in awarding such

contracts where the officials purport to be determining the

“lowest and best” bid. Where the City publicly determines

that a lowest and best bid is not “in the best interest of the

city,” it may reject such a bid for that reason, see e.g., Code

321-67, but the law requires that it do so plainly and openly

(and for some legitimate, non-arbitrary reason, see City of

Dayton, ex rel Scandrick v. McGee [1981], 67 Ohio St 2d

356). Where no such other rationale exists and the City

purports to award a contract on the basis of the “lowest and

best” bid, it is constrained by the standards it has established

at 321-37, including the cost cap for awards where the lowest

and best determination is based primarily on Subcontracting

Outreach Program rules.

In determining whether the City abused its discretion

under Ohio law and deprived Plaintiff Cleveland of a

constitutionally protected property interest without due

process of law by awarding the contract in a manner contrary

to governing Code, the court refers to its discussion of the

applicable legal standards from its SJ Entry: “‘The meaning

of the term ‘abuse of discretion’ ... connotes more than an

error of law or judgment, it implies an unreasonable,

arbitrary or unconscionable attitude.’ ‘Arbitrary’ means

‘without adequate determining principle, *** not governed by

any fixed rules or standard’. ‘Unreasonable’ means

‘irrational’” Cedar Bay Construction, Inc. v. City of Fremont

et al., 50 Ohio St. 3d 19, 22, citations omitted. Moreover,

“courts in this state should be reluctant to substitute their

judgment for that of city officials in determining which party

6la

is the ‘lowest and best bidder.’ [I]n the absence of evidence

to the contrary, public officers {and] administrative officers,

within the limits of the jurisdiction conferred by law, will be

presumed not to have acted illegally.” /d. at 21. Discretion

for determining the lowest and best bid “‘is not vested in the

courts and the courts cannot interfere in the exercise of this

discretion unless it clearly appears that the city authorities in

whom such discretion has been vested are abusing the

discretion.’” Jd. at 21 (citation omitted). See also, e.g.,

Greater Cincinnati Plumbing Contractors’ Association v. City

of Blue Ash (1* Dist. 1995), 106 Ohio App. 3d 608, 613-14

(a charter city’s discretion in accepting lowest and best bid “is

similar to the discretion provided under general state law

{citing R.C.735.05], “Competitive bidding provides for ‘open

and honest competition in bidding for public contracts and

[saves] the public harmless, as well as bidders themselves,

from any kind of favoritism or fraud in its varied forms’”).

For a property interest in the award of a public contract to

inhere, “one must have more than a unilateral expectation,

rather, one must instead have a legitimate claim of entitlement

to such a contract.” Cleveland Construction, Inc. v. Ohio

Department of Administrative Services (10" Dist. 1997), 121

Ohio App. 3d 372, 394. Thus, “a disappointed bidder to a

government contract may establish a legitimate claim of.

entitlement protected by due process by showing that local

rules limited the discretion of officials as to whom the

contract should be awarded,” and that discretion was abused

in depriving the bidder of the award, /d. at 394-95 (no abuse

of discretion found), see also, e.g., Enertech Electrical, Inc.

v. Mahoning Co Commissioners (6" Cir. 1996), 85 F.3d 257,

260. (“A constitutionally protected property interest in a

publicly bid contract can be demonstrated [if a bidder can

show] that, under state law, the County had limited

discretion, which it abused, in awarding the contract’, no

62a

abuse of discretion found), Peterson Enterprises, Inc. v. Ohio

Department of Mental Retardation (6" Cir. 1989), 890 F.2d

416 (“if the board had limited discretion under local rules as

to whom should be awarded the contract, then Plaintiff might

have a protected property interest in the award if he were the

beneficiary of the state law mandate,” no property interest

where state guidelines were nonexhaustive), cf. United of

Omaha Life Ins. Co. v. Solomon (6" Cir. 1992), 960 F.2d 31,

34 (“Michigan law neither requires that the lowest bidder be

awarded a state contract nor creates a property interest in

disappointed bidders on state contracts”), Cementech, Inc. v.

City of Fairlawn (Ohio 9" Dist. App.), 2005 WL 844948

(disappointed bidder whom jury found had submitted lowest

and best bid may qualify for money damages when project is

already complete), but see, Miami Valley Contractors, Inc.

v. Montgomery Co. (2™ Dist. App.), 1996 WL 303591(“as

best we can determine, this jurisdiction has never recognized

a constitutionally protected property interest of a disappointed

bidder on a public works project”), Miami Valley

Contractors, Inc. v. Oak Hill (4" Dist. App. 1996), 108 Chio

App. 3d 745, 752 (no abuse of discretion found, “we can find

no suppce’ for the proposition that a second- or third-place

finisher in a lowest and best bidder determination acquires a

constitutionally protected property right”).

Having heard the evidence at trial, the court finds that the

City did abuse its discretion in a manner that harmed the

public and denied Cleveland the contract award, and that

Cleveland did have a “legitimate claim of entitlement”

sufficiently clear under the Code (with its 321-37 cost cap) to

establish a due process violation. The City established a

“fixed rule,” in the language of Cedar Bay, that it then

ignored when it awarded the contract to Valley based

primarily on SBE attainment, despite the City Code’s

instruction that such SBE requirements should not cost the

63a

taxpayers more than $50,000 per contract. Cf. Greater

Cincinnati Plumbing Contractors’ Ass'n. v. City of Blue Ash

(i* Dist. App. 1995), 106 Oh» App. 3d 608, 614

(“Competitive bidding provides ior ‘open and honest

competition in bidding for public contracts and [saves] the

public harmless, as well as bidders themselves, from any kind

of favoritism or fraud in its various forms’,” quoting Cedar

Bay), »<andrick, 67 Ohio St. 2d at 360. (“While municipal

governing bodies are necessarily vested with wide discretion,

such discretion is neither unlimited not unbridled. The

presence of standards against which such discretion may be

tested is essential, otherwise, the term ‘abuse of discretion’

would be meaningless”), Mechanical Contractors Ass'n. of

Cincinnati v. University of Cincinnati (10" Dist. App. 2001),

141 Ohio App. 3d 333, 343 (public entitles should not be at

liberty “to violate laws intended to benefit the public” in

contracting), Cementech, 2005 WL 844948.

Il, The City’s Small Business Enterprise Program, as

reviewed in light of its SBE Rules and Guidelines, contains

elements that create race and gender based classifications for

which the City claims no compelling governmental interest.

The program is to that extent unconstitutional. As applied in

this case, however, those unconstitutional elements did not

cause Cleveland to lose the contract award, rather, Valley

was awarded the contract because of its higher SBE

subcontracting percentage as calculated without regard to

race or gender.

Plaintiff asserts and the City concedes that Plaintiff intends

and is positioned to bid on future City contracts and that it has

standing to mount an equal protection clause challenge to the

City’s SBE program as that program currently is constituted.

64a

Very significantly to this assessment, the City has

stipulated that it lacks the necessary factual basis to withstand

any “strict scrutiny” review of its SBE program. If any part

of the SBE program must comply with strict scrutiny

standards in order to survive constitutional challenge, the City

agrees that such elements must be invalidated as

unconstitutional at this time. That is, the City concedes that it

is not in a position to prove any “compelling governmental

interests” that could sustain a racial classification program no

matter how “narrowly tailored.” The City also has failed to

present or argue any significant evidence showing that its

program could satisfy any “intermediate scrutiny” review.

Justice O’Connor has set forth the determination by the

United States Supreme Court that ...“the Fourteenth

Amendment requires strict scrutiny of all race-based action by

state and local governments,” Adarand Constructors, Inc. v.

Pena (1995), 515 U.S. 200, 222, citing Richmond v J.A.

Croson Co. (1989), 488 U.S. 469. “‘A free people whose

restitutions are founded upon the doctrine of equality’ should

tolerate no retreat from the principle that government may

treat people differently because of their race only for the most

compelling reasons. Accordingly, all racial classifications,

imposed by whatever federal, state, or local government

actor, must be analyzed by a reviewing court under strict

scrutiny. In other words, such classifications are constitutional!

only if they are narrowly tailored measures that further

compelling governmental interests,” /d. a’ 227, see also,

e.g., Grutter v. Bollinger (2003), 539 U.S. 506, 326 (strict

scrutiny required for all governmentally imposed racial

classifications), Monterey Mech Co. v. Wilson, 125 F.3d 702,

713 (9" Cir. 1997)(“burden of justifying different treatment

by ethnicity or sex is always on the government”). Given the

City’s stipulations on standing and strict scrutiny, the court is

65a

required to examine whether the City’s SBE program imposes

classifications subject to such heightened review.

Plaintiff points to nothing in the Constitution or laws of

the United States or of the State of Ohio that creates a

heightened standard of judicial review for a governmental

program that simply favors small business enterprises at the

expense of larger competitors. The issue here is not

classification by size, but rather by race or gender.

Further, the law does not prohibit governmental entities

from recording statistics relating to race or gender, or from

tracking the progress of groups as identified by such

categories, or from seeking to ascertain whether any

imperinissible, discriminatory barriers are hampering the

advancement of individuals within groups as defined by race

or gender. Thus, for example, the fact that the City reviews

Statistics relating to contract awards to Minority Business

Enterprises (“MBEs,” as defined at 323-1-M) or Women’s

Business Enterprises (“WBEs,” as defined at 323-l-W)

pursuant to 323-17 (“City Maintained Records and Reports”)

itself does not establish a requirement of heightened scrutiny.

See, e.g., Croson, 488 U.S. at 492 (plurality op. of

O’Connor, J.) (“a state or local subdivision has the authority

to eradicate the effects of private discrimination within its

own legislative jurisdiction ... and can use its spending

powers to remedy private discrimination, if it identifies that

discrimination with the particularity required by the

Fourteenth Amendment”). Even the identification of specified

“MBE/WBE annual participation goals,” to be used in

conjunction with “monitor[ing], track[ing], and report[ing]”

purposes alone, as set forth in 323-7(a), without further

mechanism to promote or effectuate or encourage others to

meet such goals in any particular context, may not threaten

cognizable injury to this Plaintiff. Cf. Safeco Ins. Co. v. City

66a

of White House, Tenn. (6" Cir. 1999), 191 F.3d 675, 690,

692 (cited in filings made by both parties and in City’s

proposed jury instructions) (“Outreach efforts may or may not

require strict scrutiny,” citing authority for proposition that

such scrutiny generally does not apply to outreach efforts

targeting particular race).

However, “where ‘outreach’ requirements operate as a

sub rosa racial preference - that is, where their administration

‘indisputably pressures’ contractors to hire minority

subcontractors — courts must apply strict scrutiny” Safeco,

191 F.3d at 692. The City’s Small Business Enterprise

Program Rules and Guidelines, disavowed by the City as

unofficial until the eve of trial and then acknowledged as

formally promulgated as of April 1, 2003, see Plaintiff's trial

exhibit 17, contain a number of such elements when reviewed

as a complete program. The City’s Rules and Guidelines

state, for example, that:

1) “all bidders are required to use good faith efforts to

promote opportunities for Women and Business

Enterprises to participate in to the extent of their

[governmentally specified] availability, contracting.

Prior to the award of any contract related to

construction services or professional services, the City

shall evaluate each bidder’s documented efforts to

achieve the participation of minority and women

business enterprise firms.” Rules and Guidelines,

Plaintiff's trial exhibit 17, at 5 (emphasis added), cf.

Virdi v. Dekalb Co School Dist (11"Cir. 2005), 2005

WL 1389942 (nonbinding “goals” for “minority

vendor involvement” linked to specific notice and

advertising outreach programs are racial classifications

subject to strict scrutiny).

67a

2) “Upon its successful completion, the Non-

Discrimination Program [component of the SBE

program] will result in utilization of minority and

women owned firms to the extent of their

[governmentally specified] availability.” Rules and

Guidelines at 6 (emphasis added).

“The City will evaluate efforts made by bidders to

promote opportunities for minority and women owned

firms to compete for business as subcontractors and/or

material or equipment suppliers at the time of bidding.

If the evaluation determines that a bidder has failed to

achieve levels of minority and women business

enterprise participation as might be reasonable on the

basis of objective data regarding availability and

capacity of such business, the bidder shall be subject

to an inquiry by the Office of Contract Compliance.”

Id. at 6 (emphasis added), cf MD/DC/DE

Broadcasters Assn. v. Fed. Communications Com.

(D.C. Cir. 2001), 236 F.3d 13 (potential investigation

of recruitment efforts based on applicant pool numbers

is a “powerful threat” giving rise to strict scrutiny

review).

“Bidders [operating under the Subcontracting

Outreach Program] should be able to include the

participation of minority and female firms at the levels

of availability determined in the City of Cincinnati

Disparity Study. “Rules and Guidelines at 9

(referencing a study that the City concedes does not

reflect a compelling governmental interest in pursuing

a program of racial classification).

“(Using form 2007,] [o]fferor will provide a detailed

description of the techniques used to obtain

68a

participation of minority and women owned business

enterprise ... “ /d. at 43.

“Utilizing the bidder’s utilization form (Form 2003)

and total bid amount, the actual utilization percentage

is calculated. This is accomplished by taking the

amount of the subcontracts awarded to minority and

women-owned businesses and dividing by the total bid

amount If this amount is equal to the estimated

availability, then no further inquiry is needed. If the

actual utilization is less than the estimate, then further

inquiry is warranted. The contract administrator must

look at the bidder’s solicitation form and contact the

minority and women-owned businesses listed on the

form to verify that they were contacted by the bidder

and what their response was. The administrator must

also review the good faith efforts taken by the bidder.

The burden is on the bidder to explain the low

utilization percentage. If the contract administrator

determines that the contractor under-utilized minority

and/or women-owned businesses based on the actual

[government specified] availability percentage, and

that the bidder’s good faith efforts were inadequate

and there is no legitimate explanation for the under-

utilization, then the matter is turned over to the

investigative unit for a discrimination investigation.”

Id. at 46; cf. MD/DC/DE Broadcasters, supra.

[From the “Pre-bid/Outreach Session Script for

Contract Administrator”] “Bidders are required to

show that they’ve made a good faith effort to get the

maximum practical participation of minority and

women-owned businesses on this project. [I]f it is

feasible that the work can be broken into two or more

smaller units, then it should be done so as to permit

69a

maximum participation, based on the availability

estimate.” Rules and Guidelines at 49 (emphasis

added).

Every bidder is to submit a “Statement of Good Faith

Efforts” certifying that, “we have utilized the

following methods to obtain the maximum practicable

participation by small, minority and women-owned

business enterprises on this project.” /d. at Form 2007

(emphasis added).

As constituted, therefore, to include the officially

promulgated Rules and Guidelines authorized and required by

Code 323-5, the City’s Small Business Enterprise Program

contains a variety of elements through which the City makes

Classifications by race and sex and “indisputably pressures”

contractors to recruit and use subcontractors on those terms.

This case is different from many other cases involving

government race and sex classifications in that the City

advances no evidence to suggest that these elements of its

program could withstand the heightened scrutiny applied

under U.S. Supreme Court precedents. The constitutional

inquiry is foreshortened because the City concedes that it

cannot satisfy any strict scrutiny review of its program. Thus,

the program is unconstitutional on its face to the extent that

the City engages in classification by race or sex with regard

to City contracting in construction projects. To that extent, as

identified above, Plaintiff prevails on its facial challenge

under 42 U.S.C. Section 1983.

With regard to the application of those unconstitutional

program elements to the facts of this case, the court notes that

there is no evidence that any bidder on the contract at issue

was privy to the Rules and Guidelines document itself. The

court further notes, however, that both Cleveland and Valley

70a

did, in fact, (and without protest by Cleveland until after the

contract was awarded to Valley) submit form 2007

(“Statement of Good Faith Efforts”) certifying their efforts

“to obtain the maximum practicable participation by small,

minority and women-owned business enterprises on this

project.” See, e.g., Plaintiff's trial ex. 28. Those

certifications were made after all bidders were provided the

“Subcontracting Outreach Program Summary” sheet for the

project that included this directive from the City. “You will

also find on the cover of this bid document an Availability

Determination [of “13.09% Minority /1.05% Female” for the

drywall work, see Availability Estimation Sheet at Plaintiff's

trial ex. 28]. These figures are percentages based on a review

of the City’s vendor list and certified minority and women-

owned businesses.

Bidders should be able to include minority and female

firms at the level of availability indicated.” Plaintiff's trial

exhibit 32 (emphasis added). The City also informed bidders

through Addendum 3 to the bid documents that “If the

availability estimates are not met, it does not mean that the

bid will be deemed non-responsive However, we expect the

utilization of SBEs to be reflective of the availability

estimates.” See Plaintiff's trial exhibit 70.

Thus, in the process of soliciting bids, the City did in

those respects pressure and encourage bidders to draw upon

race and sex-based classifications that the City concedes could

not withstand any appropriate heightened review on the facts

to which the City is privy. The trial elicited no testimony,

however, that the City in fact gave weight to bidders’

compliance with MBE or WBE availability estimates in

making the contract award with regard to subcontracting

percentages, Plaintiff failed to establish that City officials

looked beyond whether drywall bidders met the City’s 35%

Tila

SBE requirement. Indeed, Plaintiff's own chief estimator on

the project did testify that in seeking to gain the contract

award, his focus in this area was on boosting his company’s

small business enterprise inclusion rate, and not on attaining

any particular MBE or WBE percentages. Valley did not meet

the specified WBE percentage, and no evidence was presented

at trial that the City rejected any Convention Center bid on

the basis of MBE or WBE availability estimates. The evidence

indicates that the City awarded the contract to Valley, and not

to Cleveland, because Valley’s bid complied with the City’s

requirement that 35 percent of the work go to small business

enterprises and Cleveland’s bid did not.

With regard to the unlawful discrimination component of

the case, therefore, Plaintiff here is much in the posture of the

plaintiff in the case that it cites of Virdi v. Dekalb County

School District (11" Cir. 2005), 2005 WL 1389942. There,

the federal court of appeals determined that a school district’s

aspirational “goals” for minority involvement in contracting,

coupled with specific mechanisms for public outreach, created

racial classifications that were not narrowly tailored to meet

strict scrutiny review, “the program is facially

unconstitutional.” The court held that, “[nJevertheless, the

District is still entitled to judgment on Virdi’s intentional

discrimination claim While the [program’s] goals themselves

are unconstitutional, they do not constitute evidence that Virdi

himself was discriminated against. Virdi has failed to establish

a causal connection between the unconstitutional aspect of the

[program] and his alleged injury. Moreover, there is

insufficient other evidence to impose liability upon the District

for damages to Virdi for intentional discrimination.”

Similarly here, Cleveland has not established that the City’s

race and sex based classifications (as opposed to the City’s

small business preference) resulted in the loss of the contract

72a

award. Cf. Florida General Contractors v. Jacksonville

(1993), 508 U.S. 656 (traceability requirement).

Nor has Plaintiff met its burden of proof to establish that

the City’s stated policy to favor small bus.nesses (to the extent

that the practice does not cost taxpayers more than

$50,000.00 per major construction contract) is in reality a

sham to mask invidious discrimination. The court notes as an

aside that the City’s policy of encouraging small business

participation well predates the Subcontracting Outreach

Program components of which Plaintiff complains. Further,

the court observes that Cincinnati’s City Council, at the

urging of the Administration, has indeed opted to limit

application of Subcontracting Outreach Program small

business preferences to circumstances in which such

preferences would not add more than $50,000.00 to the cost

‘of a contract. While that newly enacted taxpayer protection

cap was not observed in this instance, the evidence does not

establish that the provision was ignored as part of a scheme to

further race or sex based distinctions, and the fact that the cap

was adopted by Code certainly does not further the intentional

discrimination theory. Moreover, for example, the City’s

rejection of all the initial drywall bids, including Valley’s,

does not bolster the theory that the City’s stated preference

for SBEs was used here as a “sham” to mask improper

considerations of race or sex. Further still, evidence was

adduced that the City did award other contracts on the

Convention Center project to bidders who did not include any

MBE or WBE participation.

In short, Plaintiff has demonstrated that the City’s SBE

program contains certain race and sex based classifications

that cannot pass constitutional muster as constituted at this

time; Plaintiff has not established, however, that those aspects

of the program caused Plaintiff to lose award of the drywall

73a

contract at issue in this case. Cf. Texas v. Lesage, 528 U.S.18

(1999) (“where a plaintiff challenges a discrete governmental

decision as being based on an impermissible criterion and it

is undisputed that the government would have made the same

decision regardless, there is no cognizable injury warranting

relief under [Section] 1983” on an ‘as applied’ challenge).

Ill. Having prevailed on its abuse of discretion/due

process Section 1983 claims and on its claim that specific

portions of the City’s SBE Rules and Guidelines are

unconstitutional on their face, Cleveland is entitled to certain

declaratory and injunctive relief. Cleveland also is entitled to

its reasonable attorney’s fees under 42 U.S.C. Section 1988.

Cleveland did not establish, however, that the court should

use its equitable powers to enjoin ongoing work with regard

to the Convention Center project itself.

The injunctive and declaratory relief sought by Cleveland

involve both the administration of future City construction

contracts and the disposition of the current Convention Center

drywall project.

Plaintiff is entitled to a declaration that City Code Section

321-37(c) in its current form provides, among other things,

that where the City elects to enter into a construction contract

on the basis of the “lowest and best” bid, and where that

selection is based primarily upon the City’s determination of

bidders’ relative compliance with the City’s SBE

Subcontracting Outreach Program rules and regulations, the

City may not award the contract to a bidder whose bid amount

exceeds an otherwise qualified bid by ten percent or Fifty

Thousand Dollars. The City Administration professed to

know the meaning of that Code subsection at the time it was

considered by Council; the court trusts that now that further

attention has been drawn to the existence of the subsection

74a

(and to the high cost to taxpayers of ignoring it), and now that

the City has acknowledged the status of its Subcontracting

Outreach Program rules and regulations, no injunctive

mandate with regard to future contracts is necessary with

regard to that provision of law. Plaintiff Cleveland further is

entitled to a declaration that the conduct of the City in

ignoring the cost cap de rived Cleveland of a property

interest without due process of law.

Plaintiff also is entitled to a declaration that the City’s

SBE Rules and Guidelines in their current form contain

certain race and sex based classifications as enumerated above

that, in light of the City’s admission that it cannot now offer

a compelling governmental interest to satisfy “strict scrutiny”

review as required by governing United States Supreme Court

precedent, violate the equal protection clause of the U.S.

Constitution. The court will enjoin the City from applying

those specified Rules and Guidelines provisions to any City

construction project absent a formal determination and public

showing by the City that such provisions are narrowly tailored

to advance a compelling governmental interest of the sort that

the City concedes it cannot now establish. Now that the City

has acknowledged the status of its Rules and Guidelines, and

now that these particular classifications have been identified,

and the City has conceded that it is unable to meet any strict

scrutiny review, the City is expected to take prompt steps to

remove all unconstitutional provisions from its Rules and

Guidelines. In this regard, the court is heartened by the City’s

stated commitment in the Rules and Guidelines (at page 8) to

ensure that, “Businesses awarded City contracts shall prohibit

discrimination against any person or business on the basis of

race, color, sex, religion, disability or national origin. Such

businesses shall develop a policy statement to be

communicated regularly to all persons and entities involved in

the performance of their contracts, and shall conduct their

75a

contracting and purchasing programs so as to discourage aiiy

discrimination and to resolve all allegations of

discrimination.”

In considering Cleveland’s request for injunctive relief

with regard to the Convention Center drywall contract at

issue, the court is mindful that, “A party seeking a permanent

injunction must show [that it has ‘a right to relief under the

applicable substantive law,’] that the injunction is necessary

to prevent irreparable harm and that the party does not have

an adequate remedy at law. [Such] party must ordinarily

prove the required elements by clear and convincing

evidence” Procter & Gamble Co. v. Stoneham (1" Dist. App.

2000), 140 Ohio App. 3d 260, 267. The merits of Cleveland’s

claims, including its showing that the City abused its

discretion in disregarding the $50,000.00 cost cap under Code

Section 321-37, have been discussed above.

Regarding the question of an adequate remedy at law, the

court observes that the Defendants’ consistent position up to

and into trial was that Plaintiff is limited in this action solely

to its requests for injunctive and declaratory relief, and that

money damages are not an appropriate remedy for Plaintiff's

claims. See, e.g., City’s May 27, 2005 pretrial statement at

2 (“The City also challenges Cleveland’s ability to recover its

alleged ‘lost profits’”), City’s Motion in Limine to Preclude

Plaintiff from Presenting Evidence of Lost Profits; City’s June

13, 2005 Reply to Response to the Motion in Limine

Regarding Lost Profits (“Because Cleveland’s only claim is

for injunctive relief, Cleveland also is not entitled to a jury

trial. Cleveland’s constitutional rights, and any claim for

redress, can be handled through an action in equity by filing

and seeking injunctive relief. Not only does an action for

injunctive relief protect Cleveland, but it also protects the

taxpayers from having to pay twice for a public project”),

16a

City’s June 20, 2005 Memorandum Citing Additional

Authority on the Recovery of Lost Profits (“in Ohio lost

profits are not available and only injunctive relief available to

the plaintiff”).

The court agreed with the City that lost profits are not a

remedy available under Ohio law to a disappointed bidder on

a public contract See, e.g., O’Rourke Construction Co. v.

Cincinnati Metropolitan Housing Authority (1* Dist. App.

1982), 1982 WL 8613 at n.5 (“We can find no award of

damages from public funds even though the contract was

given to another bidder as the result of abuse of discretion.”);

Hardrives Paving & Constr., Inc. v. Niles (1994), 99 Ohio

App. 3d 243, 247-48 (“The fact that injunctive relief is

available generally indicates that a monetary award is not

available for lost profits. [I]f we were to allow appellant to

receive monetary damages, only the bidders would be

protected because the public would have to pay the contract

price of the successful bidder plus the lost profits of an

aggrieved bidder. However, if injunction is the sole remedy,

both the public and the bidders themselves are protected.”),

Cavanaugh Bldg. Corp. v. Cuyahoga Cty. Bd. Of Commrs.

(8 Dist. App. 2000), 2000 WL 86554. The court disagreed

with the City’s proposition, however, that it “must apply state

law for purposes of defining the scope of damages under

[federal Section] 1983,” cf. City’s June 16, 2005 Motion to

Clarify at 2, and concluded that violations of federal law

under Section 1983 can give rise to money damages including

lost profits where injunctive relief alone would not make a

plaintiff whole. See, e.g., Carey v. Piphus (1978), 435 U.S.

247, 257-58 (“damages awards under Section 1983 should be

governed by the principle of compensation” as developed by

the common law of torts, where common law does not

provide full compensation, “the task will be the more difficult

one of adapting common-law rules of damages to provide fair

77a

compensation for injuries caused by the deprivation of a

constitutional right.”).

The City’s newly adopted assertion at closing that project-

specific injunctive relief is precluded because Plaintiff had a

complete damages remedy available at law thus rings a bit

hollow The court granted a directed verdict for the City on

the lost profits issue because Plaintiff - which consistently had

sought a combination of money damages and injunctive

relief, including project-specific injunctive relief, see, e.g.,

Amended Complaint and Plaintiff's May 27, 2005 pretrial

Statement at 2 (seeking remedies including damages,

declaratory relief, and “injunctive relief against the City and

Valley with regard to the application of the SBE Program to

the award of the drywall contract at issue”) - failed in its case

in chief to provide any evidence whatsoever with regard to

the drywall project status or the potential availability of

injunctive relief on any balance of the contract, at the close of

Plaintiff's case, therefore, there was no factual basis on which

assess available damage remedies or on which to instruct the

jury to calculate any lost profits for drywall work already

completed. See, e.g., Ohio cases supra establishing

precedence of injunctive relief as opposed to money damages

in public bid contracts, see also, e.g., Milwaukee Co. Pavers

Assn. v. Fiedler (W.D. Wisc. 1989), 707 F. Supp. 1016,

1032 (lawsuit challenging “disadvantaged business”

preference in construction contracts. “Plaintiffs would be

entitled to money damages [for the alleged federal

constitutional violations] only if their motion for a preliminary

injunction were denied, they were to succeed ultimately on

the merits of their claim, and the state construction projects

were to have proceeded so far that they could not reasonably

be re-let under non-discriminatory bidding conditions,”

{emphasis added]). The court did not rule and does not find

that Plaintiff had available a fully adequate remedy at law. It

78a

is true that no evidence as to the current status of the drywall

work (and as to whether there remains any significant portion

of that drywall project left for potential injunction) was

presented until the City and Valley put forward proof on that

subject as part of their defense cases; such evidence now is

before the court, however, for any appropriate consideration.

In light of the equitable nature of the remedy sought, and

especially given the public nature of the project at issue, the

court also should consider whether the public interest would

be served or harmed by an injunction and whether third

parties would be unduly injured by such a remedy. “(C]aution

should be exercised in granting injunctions, and especially so

in cases affecting a public interest where the court is asked to

interfere with or suspend the operation of important public

works or to control the action of another department of

government.” White v. Long (1° Dist. App. 1967), 12 Ohio

App. 2d 136, 140, see also, e.g., Leaseway Centers v. Dept.

of Adm. Serv. (10" Dist. App. 1988), 49 Ohio App. 3d 99,

106 (quoting White), Cleveland Construction, Inc. v. Ohio

Dep't. of Adm. Serv. (10" Dist. App. 1997), 121 Ohio App.

3d 372, 383 (same).

Certainly there is a powerful public interest in requiring

governmental entities to follow the law. Courts across this

state have found that interest especially strong in the context

of “protecting the integrity of the [public] bidding process.”

Cf. Cementech, 2005 WL 844948 (9" Dist. App.) (noting that

where available, “the preferred method of resolving bidding

disputes is injunctive relief, as that relief would prevent

double payment [for the same project] and better serve the

integrity of the bidding process”), Hardrives Paving, 99 Ohio

App. 3d at 247-48 (“if injunction is the sole remedy, both the

public and the bidder themselves are protected”), Cedar Bay,

50 Ohio St. 3d at 21 (“The intent of competitive bidding,

79a

under either the state statutes or a municipal charter, is ‘to

provide for open and honest competition in bidding for public

contracts and to save the public harmless, as well as bidders

themselves, from any kind of favoritism or fraud in its varied

forms.”).

Against such considerations the court weighs the potential

harm to the public that could be caused by disruption of the

ongoing Convention Center work. Defense witnesses testified

that the Convention Center project as a whole is

approximately sixty percent complete. The drywall work will

be roughly 50 percent done by the end of July and is on a

“critical path” in which delays could significantly affect other

parts of the project. Defendants argue, in effect, that the

savings that the City might obtain if it were ordered to shift

the remaining drywall work from Valley to Cleveland at

Cleveland’s bid price are likely to be surpassed by additional

costs arising from delay claims and lost Convention Center

business. See, e.g., McKillup testimony that potential delay

claims could reach into the millions of dollars). Although

Defendants couple this argument with the contention that

Cleveland delayed unduly in seeking to press its preliminary

injunction claim, thereby allowing the project to reach a more

delicate juncture, the court is constrained to note that the City

seems to have contributed to any perceived need for extensive

and lengthy discovery by taking positions such as its

longstanding denial, only now abandoned, that it had not

officially promulgated SBE Rules and Guidelines at all.

Valley is prepared to perform the balance of the drywall

work and, with its subcontractors, would lose any expected

remaining profits if the project is enjoined. Valley also

presented testimony that a premature end to its contract would

mean a loss of work for certain employees in light of the

additional worker contingent recently added to the endeavor.

80a

Against that very real concern, the court notes that Valley

would not have won the contract or been paid for any of the

work had the contract been awarded in keeping with the

$50,000.00 cost cap, and that Valley and its subcontractors

appear to have been well compensated for the work they have

performed relative to the significantly lower (and “otherwise

qualified”) bid submitted by Cleveland.

The court finds that equity would not be served by

Cleveland’s proposal that Valley be made to disgorge money

it already has earned for work already done. Testimony at

trial indicates that Valley followed the rules set forth by the

City in bidding on the contract, and that it has borne

substantial contractual risks associated with its undertaking.

The court does not deem Valley’s contract with the City void

ab initio, and it would be inequitable to strip Valley of the

compensation it has been given for the work it has undertaken

pursuant to contract.

Further, Cleveland provided no testimony whatsoever

during its case in chief either with regard to the current status

of the Convention Center project or with regard to

Cleveland’s own current ability to complete the work without

delay and disruption to a major City undertaking. On rebuttal,

Cleveland offered no testimony to dispute Defendants’

position that the Convention Center drywall work is on a

“critical path” that is extremely time-sensitive and as to which

disruptions would impede other contractors and interfere with

planned Convention Center events and broader City interests

surrounding the City’s economic development program.

Cleveland did not offer credible assurances by a witness

conversant with the scope of work and the project’s current

status that Cleveland could take over the job at this stage

without undue and costly disruption. The court continues to

believe that a Plaintiff in an action of this nature is not entitled

Sla

to manufacture heightened claims to lost profits by eschewing

serious efforts toward injunctive relief at any stage in the

process.

Considering the testimony that was given, including the

rebuttal testimony, the court finds that an injunction

interfering with the ongoing Convention Center construction

work has not been shown to be appropriate upon examination

of all appropriate equitable considerations. The court reaches

this conclusion reluctantly in light of the course that this

litigation took, but it finds that the public interest is a weighty

factor in this case involving a major public undertaking, see,

e.g., White, 12 Ohio App. 2d 136, and that the public interest

at this juncture is best served by the combination of

declaratory and non-project specific relief outlined above. The

court further finds that Cleveland is the prevailing party on its

Section 1983 due process claim and on its reasonable

attorney’s fee under 42 U.S.C. Section 1988. Costs will be

assessed against Defendants jointly.

The court will ask the parties to confer, if they wish, on

a judgment entry to propose to the court in very short order

reflecting these determinations. The court also asks the parties

to confer on a date for a hearing on the amount of Cleveland’s

attorney’s fee.

/s/

Judge Nelson

APPENDIX L

COMMON PLEAS COURT

HAMILTON COUNTY, OHIO

CASE NO: A0402638

[Filed June 28, 2005]

Cleveland Construction, Inc.,

Plaintiff,

City of Cincinnati, et al.,

Defendants.

)

)

)

V. )

)

)

)

)

ENTRY GRANTING DEFENDANT CITY OF

CINCINNATY’S MOTION FOR PARTIAL DIRECTED

VERDICT, DENYING DISMISSAL OF EQUAL

PROTECTION CLAIM, WITHHOLDING

JUDGMENT ON DEFENDANT VALLEY’S 41(B)(2)

MOTION, AND NOTING STIPULATION THAT

REMAINING ISSUES ARE TO BE DETERMINED BY

THE COURT WITHOUT A JURY

For the reasons expressed on the record of today’s date,

the Court grants Defendant City’s Motion For A Directed

Verdict solely on the issues of lost profit and bid preparation

cost.

83a

The Court denies Defendant City’s Motion for dismissal

of Plaintiff's equal protection claim relating to the

administration of the contract at issue in this case.

The Court defers a ruling on Defendant Valley’s motion

to dismiss under Rule 41(B)(2) and will withhold judgment on

such issues until the close of all evidence.

All parties having stated that the remaining issues in this

action are appropriate for determination by the Court alone

without jury verdict, the jury is discharged with the consent

of all parties with regard to all issues remaining in this action.

The case will proceed as a trial to the bench with regard to

Plaintiff's claims for declaratory and injunctive relief and

attorney fees.

SO ORDERED.

/s/

Fred Nelson, Judge

APPENDIX M

COMMON PLEAS COURT

HAMILTON COUNTY, OHIO

CASE NO: A0402638

[Filed June 20, 2005]

Cleveland Construction, Inc.,

Plaintiff,

V.

City of Cincinnati, et al.,

Defendants.

)

)

)

)

)

)

)

)

ENTRY

Pursuant to Civil Rule 65(B)(2) and previously determined

with the parties as reflected on the Amended Case Scheduling

Order of October 8, 2004, the hearing on Plaintiff's request

for preliminary injunctive relief is combined with the trial on

the merits of the case as scheduled to begin on June 20, 2005.

SO ORDERED.

/s/

Judge Nelson

APPENDIX N

COURT OF COMMON PLEAS

HAMILTON COUNTY, OHIO

Case No. A0402638

[Filed May 13, 2005]

Cleveland Construction,

Plaintiff,

City of Cincinnati, et al.,

Defendants.

)

)

)

VS. )

)

)

)

)

ENTRY DENYING DEFENDANTS’ MOTIONS FOR

SUMMARY JUDGMENT AND DENYING

PLAINTIFF’S MOTION FOR PARTIAL SUMMARY

JUDGMENT AND INJUNCTIVE RELIEF

Introduction

This matter comes before the court on the motion of

Plaintiff Cleveland Construction, Inc. (“Cleveland”) for

partial summary judgment and for injunctive relief, and

countervailing motions for summary judgment by Defendants

the City of Cincinnati (“the City”) and Valley Interior

Systems, Inc. (“Valley,” which has associated itself with the

City’s legal position for purposes of its motion). The court in

86a

keeping with the requests of the parties conducted a

nonevidentiary hearing on the motions, and has reviewed the

arguments of counsel, the pleadings and briefs, and the

evidence filed of record.

The case involves a dispute related to drywall work

needed for the expansion and renovation of Cincinnati’s

Convention Center. The parties agree that in a second round

of bidding to perform the drywall work, Cleveland offered to

do the job for $8,889,000 and Valley submitted a bid of

$10,135,022. Although Cleveland’s bid was lower than

Valley’s by roughly one and a quarter million dollars, the

City awarded the drywail contract to Valley as the lowest

bidder that met the City’s Small Business Enterprise program

(“SBE”) criteria. The City states that Valley got the contract

because it was prepared to make greater use of small business

subcontractors than could Cleveland.

Cleveland subsequently filed this lawsuit, alleging among

other matters that the City’s SBE program “is a sham to allow

the City to use racial and gender-based quotas illegally,” and

asserting that in awarding the contract to Valley, the City

violated Cleveland’s equal protection rights and ignored its

own municipal code in violation of due process. After a

hearing at which this court denied Cleveland’s motion for a

tempcrary restraining order, Defendants removed the case to

federal court; in due course, the action was remanded here,

the court dismissed certain individual defendants, and the

parties engaged in extended discovery. Cleveland elected not

to pursue application for a preliminary injunction until the

filing of the instant motions, which include the summary

judgment issues to which the court now turns.

87a

Summary Judgment Standard

Summary judgment is appropriate when it is clear from

the facts established in the pleadings and evidential materials

of record, as viewed in the light most favorable to the party

Or parties opposing the motion, that: “(1 ) no genuine issue of

fact remains to be litigated; (2) the moving party is entitled to

judgment as a matter of law; and (3) the evidence

demonstrates that reasonable minds can come to but one

conclusion, and that conclusion is adverse to the party

opposing the motion.” See, e.g., Sauter v. One Lytle Place

(1* Dist. App. 2005), 2005-Ohio-1183, citing Civil Rule

56(C). If a party seeking summary judgment meets its initial

burden of identifying a basis for the motion together with

those parts of the record that “demonstrate the absence of a

genuine issue of material fact on the essential element(s) of

the ... nonmoving party’s claims ...., the nonmoving party

then has a reciprocal burden ... to set forth specific facts

showing that there is a genuine issue for trial ....” Dresher v.

Burt (1996), 75 Ohio St.3d 280, 293.

Equal Protection Issues

At this stage in the litigation, Cleveland argues that the

City’s SBE program as designed (to include certain “Rules

and Guidelines”) and as applied here amounts to a race-

conscious awards scheme that the City cannot justify under

prevailing constitutional norms. (Plaintiff at this point does

not argue that the City has required improper considerations

of gender, perhaps because Valley’s successful bid did not

reflect subcontracting percentages for women-owned firms

that approached the City’s availability estimates.) The City is

frank to respond that it lacks a factual predicate that could

satisfy “strict scrutiny” review of a race-conscious program,

but argues that its SBE approach as designed and as

88a

undertaken here is race-neutral, rationally based, and

constitutionally unexceptionable. The record as presented to

date reflects genuine issues of material fact that preclude

summary judgment for any side on this part of the dispute.

The City’s municipal code provides that “Cincinnati’s

Annual Goal for SBE participation shall be 30% of the city’s

total dollars spent for construction ... services ....” Cincinnati

Municipal Code (“Code”) at 323-7(a). The Code defines a

Small Business Enterprise with regard to gross revenues and

number of employees; the SBE definition itself does not

include factors of race or gender. Code 323-1 -S. The record

here may suggest that the City pursues the 30% SBE goal on

a project by project basis, establishing different percentages

for different project components in order to arrive at the

overall 30% figure. The parties agree that with regard to the

drywall element of the Convention Center project, the goal

was that 35% of subcontracting dollars go to SBEs. See also,

e.g., Small depo. at Ex. 5 (City’s “Subcontracting Outreach

Program Summary” sets Drywall “Goal[ ] For Bid Package

C” at 35%).

Standing alone, that SBE goal does not on its face

implicate any considerations of race or gender, and the court

does not understand Plaintiff to argue that a program

undertaken to ensure participation of small businesses is

subject to heightened scrutiny simply because it may have the

ancillary effect of broadening participation for people in

groups as defined by race or gender. Plaintiff argues,

however, that the program must be assessed in light of

‘Minority Business Enterprise/Women’s Business Enterprise’

“participation goals of 30% [for] construction ... services [,to

be] monitored, tracked internally, and reported annually to

city council along with annual SBE participation rates,” as

also established in Code 323-7(a), and in light both of

89a

“availability estimates” provided by the City to reflect

percentages of minority and female controlled subcontractors

available for hire in the region, and of SBE “Rules and

Guidelines” that imply or direct a race-conscious focus for the

program. The City responds that this project, by its terms,

involved only SBE goals; that availability estimates, in and of

themselves, do not establish any particular hiring

requirements; and that the Rules and Guidelines never were

officially promulgated and have not been applied, at least in

full, to this project.

It is undisputed that in the course of the bidding process,

the City was asked why it had provided prospective bidders

with an “Availability Estimation Sheet ... Subcontractor

Outreach Program (CMC 323-31) noting availability estimates

for drywall subcontractors of “13.09% Minority” and

“1.05% Female.” See Amended Complaint at Ex. B and

City’s MSJ at page 8. The inquiry, disseminated along with

the answer to all prospective bidders, continued: “I thought

this project only deals with SBEs. Please clarify.” The City

responded: “This project does deal with SBEs. However, the

City of Cincinnati’s Disparity Study found that Minorities and

Females were underutilized in city contracting projects. ....

The minority and female business owner would also have to

be certified with the City as a Small Business Enterprise. If

the availability estimates are not met, it does not mean that the

bid will be deemed non-responsive. However, we expect the

utilization of SBEs to be reflective of the availability

estimates.” Amended Complaint at Ex. H; City’s MSJ at 8.

The City submits that this arguably rather opaque answer

demonstrates that the drywall bids were governed exclusively

by SBE considerations without regard to MBE/WBE

concerns. The City points, also, to evidence indicating that a

first round of bidding resulted in no contract award because

90a

Valley, while exceeding the MBE availability estimate, did

not satisfy the 35% SBE goal. The City further notes

testimony of its representatives to the effect that availability

estimates did not factor into its bid evaluation, and argues that

a stated desire to calculate and track project participation by

race does not itself trigger strict scrutiny under such precedent

as Reed v. Agilent Technologies, 174 F. Supp. 176 (D. Del.

2001). The City, in short, cites to testimony of its

representatives that Cleveland was disqualified because it did

not meet the 35% SBE goal, and that considerations of race

simply did not enter into the determination. See, e.g.,

purchasing agent Franklin depo. at 46; Ranford at 68 (“when

I looked at a bid I did not look at the availability estimation,

all 1 was concerned about was Small Business Enterprise”).

Cleveland contends that the City’s answer on the

relevance of availability estimates should not be construed as

advising bidders that the City will not consider race or gender

in evaluating bids. Moreover, Cleveland points to Valley’s

certification of MBE percentages in its winning Subcontractor

Utilization Plan, to language in the required Statement of

Good Faith Efforts (form 2007, certifying use of any

“methods to obtain the maximum practicable participation by

small, minority and women-owned business enterprises”), and

to language in the Subcontracting Program Outreach

Summary stating that “[blidders should be able to include

minority and female firms at the level of availability

indicated.” See, e.g., Strawser depo. ex. 3; Small depo. ex.

5.

Moreover, Cleveland emphasizes a document titled: “City

of Cincinnati/Small Business Division/Office of Contract

Compliance/Small Business Enterprise Program/Rules and

Guidelines.” See Townsend depo. ex. 19. That document

recites, among other things, that “[ijf ... evaluation

9la

determines that a bidder has failed to achieve levels of

minority and women business enterprise participation as might

be reasonable on the basis of objective data regarding

availability and capacity of such businesses, the bidder shall

be subject to an inquiry by the Office of Contract

Compliance.” Furthermore, the document states, that Office

is to examine bid forms to determine “the amount of the

subcontracts awarded to minority and women-owned

businesses .... If the bidder’s utilization is the same as or

greater than the actual availability percentage, then the city

can accept the bidder’s utilization as being in compliance with

the program. The burden is on the bidder to explain the low

utilization percentage. If the contract administrator determines

that the contractor under-utilized minority and/or women-

owned businesses based on the actual availability percentage,

and thai the bidder’s good faith efforts were inadequate and

ihere is no legitimate explanation for the under-utilization,

then the matter is turned over to the investigative unit for a

discrimination investigation.” Townsend depo. ex. 19 at 6,

45-46.

For the purposes of these motions, the City does not really

argue that such provisions in the “Rules and Guidelines”

document are permissible as mechanisms to prevent

intentional discrimination by contractors. Rather, the City

contends that “[t]he Rules and Guidelines ... were never

signed by the City Manager and do not have the force of

law,” and that “certain portions of the ‘Rules and Guidelines’

have not been used” in the bid solicitation and evaluation

process. See City’s memo opposing Plaintiff's MSJ at 13; see

also Lemmie depo; Ranford depo. at 68, 70-73 (City engaged

in no evaluation of MBE participation).

Code section 323-31 instructs the City Manager to

promulgate rules and regulations for the SBE Subcontracting

92a

Outreach Program; the City Manager, however, has testified

that, “I have not promulgated rules and regulations under this

section.” Lemmie depo. at 10. The City also notes that there

is no evidence in the record that the Rules and Guidelines

document was made available or known to any bidder prior

to the award of the contract at issue; that is, the current

record does not reflect that the document directly could have

caused any bidder to take race into account in submitting a

proposal. The City in effect disavows any problematic

portions of the document by arguing that those sections never

have controlled the policy of the City or its contractors. On

the state of the record to date, that appears to be a genuine

issue of material fact (although the court does observe that the

City has admitted that the Rules and Guidelines “are ... part

of the Small Business Enterprise Program,” see City’s

Response to Interrogatory 17(D) at 6).

Viewing the evidence in the light most favorable to the

non-moving party, and given that the Rules and Guidelines

document was prepared for and available to City staff, and

served to some extent as “working documents used by staff,”

Lemmie depo. at 11 and Stark depo. ex. 6, (and considering,

too, presumptions of regularity that generally inform review

of governmental actions), the court cannot conclude for

summary judgment purposes that the principles embodied in

the Rules and Guideline document played no part in the

determinations at issue here. By the same standard, with all

reasonable inferences drawn in favor of the Defendants in

evaluating Cleveland’s summary judgment motion, the court

cannot find as a matter of undisputed fact that certain sections

of the Rules and Guidelines cited above entered into the City’s

decision. The status of the “Rules and Guidelines,” and the

issue of to what extent and effect, if any, they were used here

Or may support other reasonable inferences regarding

Cleveland’s claim that the SBE program is run as a “sham”

93a

to mask a race-conscious awards program, remain questions

of arguably material fact.

In light of the City’s response to the bidder inquiry about

the relevance of availability estimates, viewed in conjunction

with the bid documents and Code mandates and the Rules and

Guidelines document, and the testimony of City officials, the

court similarly concludes under the summary judgment

standard that a question of fact remains as to whether the City

did intelligibly and accurately communicate to the bidders that

this drywall project was to be administered under SBE

principles without regard to considerations of race (as

Defendants maintain was the case and which Plaintiff strongly

disputes). Moreover, the court notes as an aside that the

record indicates arguably conflicting testimony regarding the

subjective impressions of the bidders on this score.

In short, whether or not the City has engaged here in a

race-conscious contracting program of the sort that would

require “strict scrutiny” review depends on a determination

of facts that remain at issue when reasonable inferences are

drawn in favor of the non-moving parties on each of the

summary judgment motions. Cf. Safeco Ins. v. City of White

House, Tenn. (6" Cir. 1999), 191 F.3d 675, 692 (“Outreach

efforts may or may not require strict scrutiny” [citing

authority that such heightened review “’is generally

inapplicable’ to outreach efforts that target one race], “But ...

where their administration ‘indisputably pressures’ contractors

to hire minority subcontractors [,] courts must apply strict

scrutiny”).

The City argues, however, that Cleveland lacks standing

to pursue its equal protection claims in any event because it

did not meet the 35% SBE standard and therefore could not

have been awarded the contract regardless of any other

94a

considerations. Cf. Florida General Contractors v

Jacksonville (1993), 508 U.S. 656 (traceability requirement).

The court finds below however, that the City’s Code in some

instances precludes award of a contract based primarily on

SBE Subcontractor Outreach Program considerations where

the winning bid is more than $50,000 higher than the bid of

an otherwise qualified contractor rejected for not meeting the

SBE goal. Under these circumstances, where the City agreed

to pay well more than one million dollars extra in order to

achieve 35% participation by small businesses in the drywall

project, the undisputed facts do not establish for summary

judgment purposes that Cleveland would have been out of the

running for the award had the City applied its SBE rules in

the context of the Code as written. Thus, Defendants’

standing argument fails at this point in the process for reasons

even beyond Cleveland’s contention that the SBE program

itself is wholly a sham to mask impermissible race-conscious

awards.

The court therefore denies the motions for summary

judgment of all three parties with regard to Cleveland’s equal

protection claims.

Due Process Issues

Defendants concede that Cleveland’s bid to perform the

drywall work on the City’s Convention Center project was

$1,246,022.00 lower than Valley’s. City’s MSJ Memo at 7

(“Valley’s bid was for $10, 135,022.00 while Cleveland’s bid

totaled $8,889,000.00”); Valley’s MSJ (adopting “all the

same grounds” as City). Defendants also affirm that

“Cleveland’s bid was excluded from consideration because it

failed to meet the SBE requirements,” City’s MSJ Memo at

7, and they point to no other infirmities in Cleveland’s bid or

Capacity to perform the work. Cf. Franklin depo. at 21-22,

95a

29, 62, 88 (City purchasing agent believes that all three

bidders met non-SBE bid specifications and that those bids

were acceptable to the purchasing department; no issues with

Cleveland’s prior performance).

Code section 321-37, “Bid; Award to Lowest and Best”

provides in part:

“(a) Selection of Lowest and Best in Award of City

Contracts: Except where otherwise provided by

ordinance, the city purchasing agent shall award a

contract to the lowest and best bidder. ...

(c) Factors to be Considered: Other factors that the city

purchasing agent may consider in determining the lowest

and best bid include, but are not limited to: [prior

performance; prevailing wage history; compliance with

nondiscrimination rules; and}

(4) Information concerning compliance with the ‘SBE

Subcontracting Outreach Program’ rules and regulations

issued by the city manager pursuant to ... section 323-31.

In the event that the selection of the lowest and best bidder

is based primarily upon factors 3 or 4 above, the contract

award may be made subject to the following limitation: the

bid may not exceed an otherwise qualified bid by ten

(10%) percent or Fifty Thousand Dollars ($50,000.00),

whichever is lower.”

(emphasis added)

Cleveland contends that in awarding the contract to Valley

despite the fact that Valley’s bid was more than $50,000

higher than Cleveland’s (by more than 1.2 million dollars),

96a

the City abused its discretion and thereby deprived Cleveland

of a constitutionally protected property interest without due

process of law. Defendants argue that Cleveland was not the

lowest and best bidder because it failed to reach the SBE goal

without regard to Subcontracting Outreach Program rules. See

City’s memo in op. at 22; Valley’s memo in op. at 10 (“Code

section 321-37 does not apply ... because Cleveland was not

an otherwise qualified bidder eligible for consideration under

321-37”).

For a property interest in the award of a public contract to

inhere, “one must have more than a unilateral expectation;

rather, one must instead have a legitimate claim of entitlement

to such a contract.” Cleveland Construction, Inc. v. Ohio

Department of Administrative Services (10" Dist. 1997), 121

Ohio App. 3d 372, 394. Thus, “a disappointed bidder to a

government contract may establish a legitimate claim of

entitlement protected by due process by showing that local

rules limited the discretion of ... officials as to whom the

contract should be awarded” and that discretion was abused

in depriving the bidder of the award. Jd. at 394-95 (no abuse

of discretion found); see also, e.g., Enertech Electrical, Inc.

v. Mahoning Co. Commissioners (6" Cir. 1996), 85 F.3d 257,

260 (“A constitutionally protected property interest in a

publicly bid contract can be demonstrated .... [if a bidder can

show] that, under state law, the County had limited

discretion, which it abused, in awarding the contract’; no

abuse of discretion found); Peterson Enterprises, Inc. v. Ohio

Department of Mental Retardation (6" Cir. 1989), 890 F.2d

416 (“if the board had limited discretion under local roles as

to whom should be awarded the contract ..., then Plaintiff

might have a protected property interest in the award if he

were the beneficiary of the state law mandate;” no property

interest where state guidelines were nonexhaustive); cf.

United of Omaha Life Ins. Co. v. Solomon (6" Cir. 1992),

97a

960 F.2d 31, 34 (“Michigan ... law neither requires that the

lowest bidder be awarded a state contract nor creates a

property interest in disappointed bidders on state contracts”);

Cementech, Inc. v. City of Fairlawn (Ohio 9" Dist. App.),

2005 WL 844948 (disappointed bidder whom jury found had

submitted lowest and best bid may qualify for money damages

when project is already complete); but see, Miami Valley

Contractors, Inc. v. Montgomery Co. (2™ Dist. App.), 1996

WL 303591 (“as best we can determine, this jurisdiction has

never recognized a constitutionally protected property interest

of a disappointed bidder on a public works project”); Miami

Valley Contractors, Inc. v. Oak Hill (4" Dist. App. 1996),

108 Ohio App. 3d 745, 752 (no abuse of discretion found;

“we can find no support for the proposition that a second- or

third-place finisher in a lowest and best bidder determination

acquires a constitutionally protected property right”).

“*The meaning of the term ‘abuse of discretion’ ...

connotes more than an error of law or judgment; it implies an

unreasonable, arbitrary or unconscionable attitude’

‘Arbitrary’ means ‘without adequate determining principle;

*** not governed by any fixed rules or standard.’ ....

‘Unreasonable’ means ‘irrational’.” Cedar Bay Construction,

Inc. v. City of Fremont et al., 50 Ohio St.3d 19, 22, citations

omitted. Moreover, “courts in this state should be reluctant to

substitute their judgment for that of city officials in

determining which party is the ‘lowest and best bidder.’ ....

[iJn the absence of evidence to the contrary, public officers

{and} administrative officers ..., within the limits of the

jurisdiction conferred by law, will be presumed ... not to have

acted illegally.” /d. at 21. Discretion for determining the

lowest and best bid “’is not vested in the courts and the courts

cannot interfere in the exercise of this discretion unless it

Clearly appears that the city authorities in whom such

discretion has been vested are abusing the discretion’.” /d. at

98a

21 (citation omitted). See also, e.g., Greater Cincinnati

Plumbing Contractors’ Association yv. City of Blue Ash (1*

Dist. 1995), 106 Ohio App. 3d 608, 613-14 (a Charter city’s

discretion in accepting lowest and best bid “is similar to the

discretion provided under general state law [citing R.C.

735.05]; “Competitive bidding provides for ‘open and honest

competition in bidding for public contracts and [saves] the

public harmless, as well as bidders themselves, from any kind

of favoritism or fraud in its varied forms’”).

If the bid in the instant case was awarded in violation of

the explicit $50,000/10% cap established by 321-37(c)(4), the

award would be an abuse of discretion and Cleveland would

have a “legitimate claim of entitlement” sufficiently clear to

give rise to a due process claim. Violation of that precise

standard as established by ordinance would move Cleveland’s

interest in the contract beyond the “mere ‘unilateral

expectation’” of receiving the award under a regime in which

the relevant ordinance provides non-exhaustive guidelines

limiting discretion, cf. Peterson Enterprise, 890 F.2d 416;

Cleveland Construction, 121 Ohio App. 3d at 394, and into

that rare context in which a disappointed bidder may assert a

constitutionally protected property interest. This is the basis

on which Cleveland advances the secoud part of its motion for

partial summary judgment. See Motion at 2 (seeking judgment

based on an asserted “property interest in the contract”).

Under the summary judgment standard, the court thus turns

to the question of whether any genuine issue of material fact

exists as to whether the City breached its 321-37(e)(4) cap.

The language of 321-37 establishes that “information

concerning compliance” with the City’s SBE Subcontracting

Outreach Program rules 2nd regulations is a “[flactor” that

“may” be considered as the City determines the lowest and

best bid. If the lowest and best bid is selected “based

99a

primarily” on that factor, the City may proceed to award the

contract “subject to the following limitation: the bid may not

exceed an otherwise qualified bid by ten (10%) percent or

Fifty Thousand Dollars ($50,000.00), whichever is lower.”

321-37(c)(4).

In that context, the phrase “otherwise qualified bid” can

reasonably be read only to mean a bid that is qualified except

that it is not in “compliance” with the SBE Subcontracting

Outreach Program “factor”. The bid not selected “primarily”

because of the SBE Subcontracting Outreach Program factor

must “otherwise” be qualified in order to trigger the required

calculation with regard to whether the contract award may be

made as selected on that basis.

Cleveland points to legislative history for 321-37

indicating that the City Administration took the position and

advised Cincinnati’s City Council that the ten-

percent/$50,000.00 cap would apply to any purchasing

contract affected by SBE compliance issues. Assistant City

Manager Rashid Young advised Council’s Law and Public

Safety Committee on November 25, 2003 that “[w]hat this

ordinance allows us to do is be clear about when it is

appropriate to award a bid to a SBE compliant [bidder] if they

are not the lowest. This ordinance would allow us to award a

bid if the bid is $50,000 or less difference away from the

lowest bid. .... We had an example where the SBE-compliant

bidder was some nine hundred thousand dollars in excess of

the lowest bid and ... it didn’t make a lot of sense to spend

nine hundred thousand dollars more to comply with the

regulations of SBE.” Young depo. and ex. 1.

By its terms, however, the cap applies specifically (and

exclusively) to instances where a higher bid is accepted

because of “information concerning compliance with ‘SBE

100a

Subcontractor Outreach Program rules’... issued ... pursuant

to 323-31.” Code 321-37(c)(4) (emphasis added). As used in

the legislative text, the reference to an “SBE Subcontractor

Outreach program” does not appear coextensive with the

broader “Small Business Enterprise Program” itself. Thus,

for example: Chapter 323 as a whole is titled “Small Business

Enterprise Program,” while section 323-31 specifically is

titled “Subcontracting Outreach Program;” and Section 323-5

directs the City Manager to “issue and enforce regulations to

carry out the meaning and purpose of the small business

enterprise program authorized by this chapter,’” while

Section 323-31 directs the City Manager to “issue and enforce

rules and regulations to carry out the meaning and purpose of

the Subcontracting Outreach Program, substantially in

conformance with the content of Part IJ, Section I, the

‘Legislative Recommendation Report To The City of

Cincinnati’ dated December 17, 2002, prepared by Griffin &

Strong, P,C..”

As Cleveland observes: “A basic rule of statutory

construction requires that ‘words in statutes should not be

construed to be redundant, nor should any words be ignored.’

... No part [of a statute] should be treated as superfluous

unless that is manifestly required, and the court should avoid

that construction which renders a provision meaningless or

inoperative.” D.A.B.E., Inc. v. Toledo-Lucas County Board

of Health (2002), 96 Ohio St.3d 250-256 (citations omitted);

see also Cleveland’s MSJ Motion/Memo at 39. Council

enacted 323-31 directing enforcement of regulations for the

“SBE Subcontracting Outreach Program” in 2003, while

leaving in place the separate 323-5 directive as enacted in

1999 to enforce regulations for the SBE program itself. If the

Subcontracting Outreach Program and the overall SBE

program were identical, a double instruction on enforcement

would be unnecessary and redundant. The specific reference

1Ola

in 321-37(c)(4) to the SBE Subcontracting Outreach Program

thus appears to comprehend something less than the SBE

program as a whole (a conclusion strengthened by the

structure of Chapter 323).

The distinction between the “SBE Subcontractor Outreach

Program” and the overall SBE program may not be terribly

complex. The Griffin & Strong Report referenced and to

some extent incorporated by Code section 323-31

(“Subcontracting Outreach Program”) itself makes clear that

“(t]he Subcontracting Outreach Program applies to City-

funded construction contracts of $100,000 or more,” except

where the City “in advance” specifically waives such

requirements. Lemmie Depo. Ex. 2 (December 17, 2002

Griffin & Strong Report at 3, 5). That is also the deposition

testimony offered by City representatives. See, e.g., Ranford

depo, at 78 (“Those are for contracts that are in excess of

$100,000”). That distinction, applying the Subcontracting

Outreach Program to contracts in excess of $100,000, both

would explain the implication in the Code that the SBE

Subcontracting Outreach Program is only a subset of the SBE

program overall, and could vindicate the City

Administration’s representation to Council through Mr.

Young that 323-31 would preclude the City from paying, for

example, “nine hundred thousand dollars more to comply

with the regulations of SBE”: it gives a widely applicable

meaning to the $50,000/10% cap, while also making clear

that the cap applies only to relatively large contracts.

The record before the court further reflects that at least

some elements of the SBE Subcontractor Outreach Program

were applied to the bids at issue. As City contract compliance

officer Ranford has testified: “The Subcontracting Outreach

Program was applied to convention center bids. If you have

any of those bid documents, you will see the Subcontracting

102a

Outreach Program. Those are for contracts that are in excess

of $100,000.” Ranford depo. at 78; see also id. at 60 (“we

had the Subcontracting Outreach Program on all convention

center projects and they were in excess of $100,000. So we

followed how that worked, the goals. The goals were set.”),

83 (“The Subcontracting Outreach Program was used for

convention center”), 100 (“Q: “There’s a listing of the forms

that you reviewed ... for the bidders in this case? A: These

were the same documents that were the Subcontracting

Outreach Program, yes.”).

The record now before the court also reflects that the very

bid requirement document that specified the 35% SBE

participation figure was headed in all capital letters:

“SUBCONTRACTING OUTREACH PROGRAM

SUMMARY/CONVENTION CENTER PROJECT.” See,

e.g., Small depo. ex. 5; Butler depo. ex. 1, tab 4, p.7. That

document continued, in part: “SBE GOALS PER TRADE

CONTRACT ..., BID PACKAGE C: All bidders are required

to meet the goal stated .... Drywall .... 35%.” The Outreach

Program Summary also stated that the “SBE bidder must

clearly indicate on Form 2003 the percentage of work that

represents their SBE participation percentage as a Prime

related to the completion of the scope of work.”

Substantial evidence in the record suggests, too, that the

City treated that 35% figure as a mandatory requirement. See,

e.g, Townsend depo. at 83 (“You’re determined not to be in

compliance if you did not meet the goal, yes”), 106. Indeed,

the City bases its Motion with respect to Cleveland’s equal

protection claims on the assertion that the SBE goal was

mandatory, although Cleveland takes somewhat of a contrary

positaon, cf. Cleveland’s Reply Memo in support of MSJ at

2, citing prior Townsend testimony. Whereas the rest of the

Code relating to SBE matters speaks in terms of goals not

103a

expressed as inflexible threshold requirements, the

Subcontracting Outreach Program as referenced in 321-37 and

323-31 “requires bidders to ... achieve a minimum of 20%

(which may [be] higher for construction of buildings) SBE

subcontractor participation.” December 17, 2002 Griffin &

Strong Report 7 (noting elsewhere that City can waive

requirement in advance under the program). Significantly, at

the same time that the Code was amended to include the

Subcontracting Outreach Program language (including the

cost cap), Council also deleted Code language otherwise

requiring bidders to submit (less rigorous) “written assurance

of commercially useful SBE participation in their bids” and to

make “good faith” efforts to meet SBE participation levels.

See former Code sections 323-27 and 323-29, as repealed by

the same ordinance that established 232-31 incorporating the

more mandatory regime of the Griffin & Strong report.

That mandatory approach also is largely consistent with

the “Subcontracting Outreach Program” section of the Small

Business Enterprise Prograr; Rules and Guidelines that,

although not signed by the City Manager, nonetheless

provided guidance to City employees in certain respects. See,

e.g., Townsend depo. ex. 19 (“Rules and Guidelines”) at 9

(“Subcontracting Outreach Program, CMC 323-31: The

Subcontracting Outreach Program applies to City-funded

construction contracts of $100,000 or more. At the City’s sole

discretion, these requirements may be waived in advance ....

The Subcontracting Outreach Program requires bidders to ...

achieve a minimum of 20% [which may be higher for

construction of buildings] SBE subcontractor participation. To

be eligible for award of this project, the SBE bidder must

subcontract a minimum percentage of its bid to ... SBE

subcontractors”); see also Lemmie depo. at 11 (“Rules and

Guidelines” were “working documents used by staff in the

office”); Ranford depo. at 78, 80 and ex. 34 and G (“Rules

104a

and Guidelines” page 10, Subcontracting Outreach Program

with regard to coverage of projects over $100,000 and

mandatory nature of SBE figures was used for contract

compliance review in convention center program, whereas

Nondiscrimination MBE sections of Rules and Guidelines

were not). The court observes, however, that Cleveland’s

position that “the City has ... decided that good faith efforts

[to achieve SBE compliance] do not matter and does not look

at them,” Cleveland’s MSJ Memo at 33, argues that certain

elements of the Subcontracting Outreach section of the Rules

and Guidelines were disregarded in pursuit of higher SBE

figures, see Ranford depo. ex. G at 11 (good faith

exceptions).

The City Manager’s failure formally to promulgate rules

and regulations for the Subcontracting Outreach Program

under 323-37, of course, can provide no justification for any

failure to abide by the $50,000/10% cost cap established by

321-37. Code 323-31 requires the issuance of such rules:

“The City Manager shall issue roles and regulations to carry

out the meaning and purpose of the Subcontracting Outreach

Program....” Failure to provide required regulations may

compound an abuse of discretion; it does not mitigate such an

abuse. See, e.g., City of Dayton, ex rel. Scandrick v. McGee,

67 Ohio St.2d 356, 360 (1981) (“The presence of standards

against which such discretion may be tested is essential;

otherwise, the term ‘abuse of discretion’ would be

meaningless”); cf. Lemmie depo. at 11 (“[a]t this time we

have no plans” to issue any SBE rules and regulations other

than those cited above as “working documents used by

staff.”).

Similarly, the City’s perhaps unusual approach to

legislative drafting - codifying the Subcontractor Outreach

Program through statutory references to a consultant’s report,

105a

rather than by direct recitation of standards and requirements

- cannot permit the City to ignore the cost cap that Council

did specifically enact in 321-37. Had the legislative

recommendations concerning the Subcontractor Outreach

Program as set forth in Part II, Section I of the Griffin &

Strong report referenced in 323-31 been adopted in a more

Straightforward fashion, the connection between the

Subcontractor Outreach Program and a generally required

SBE figure of 20% or higher would be more publicly visible.

That connection is not nullified simply because it may be

obscured by the indirect approach of the Code.

Code section 321-37(c)(4) envisions that “[i]nformation

concerning compliance” with the SBE Subcontracting

Outreach Program may be the primary basis for the selection

of the lowest and best bidder (in which event, the cost cap

applies). Defendants do not dispute that award of the contract

to Valley was “based primarily” on “compliance” with the

35% SBE figure set forth in the SUBCONTRACTING

OUTREACH PROGRAM SUMMARY. See, e.g., Franklin

depo. at 28-29 (“Q: ... do you remember any factor other

than SBE compliance that was a primary factor in deciding

who got the bid award in this situation? A: No. ....Q: ... do

you recall there being any factor that made a difference

primarily one way or the other other than the SBE number?

A: No.”). Although the title of that bid requirements

document may not be dispositive, it does not appear to weigh

in Defendants’ favor.

Defendants plainly have not established that they are

entitled to summary judgment on Cleveland’s due process

claim or on the remaining elements of Cleveland’s Amended

Complaint.

106a

The closer issue is whether Cleveland is entitled to

judgment on the due process portion of its motion. When the

evidence is reviewed in the light most favorable to

Defendants, as the summary judgment standard requires for

this evaluation, the court cannot find that reasonable minds

could come only to the conclusion that Cleveland had been

divested of a property right in violation of due process of law.

A question remains for the finder of fact as to whether the

City legitimately designated Valley as the lowest and best

bidder based on factors other than information concerning

compliance with the Subcontracting Outreach Program. That

is, an arguable question of fact remains as to whether the 35%

SBE figure invoked by the City derived from the

Subcontracting Outreach Program itself (with its generally

mandatory 20% SBE threshold) or from efforts by the City on

top of the Subcontractor Outreach Program to approach the

overall 30% SBE goal contained elsewhere in the Code.

The City’s 30% SBE goal was created prior to the

Subcontractor Outreach Program and continues in effect today

in a Code section separate from that containing the

Subcontractor Outreach Program. Code 323-7 (“The city of

Cincinnati’s Annual Goal for SBE participation shall be 30%

of the city’s total dollars spent for construction ...”). The

parties have not specifically identified in their briefing the

particular genesis of the 35% drywall SBE figure that was

used for Convention Center bids, and the court does not find

the facts on that matter established beyond peradventure. That

the Subcontracting Outreach Program applies to contracts

over $100,000 and generally requires at least 20% SBE

participation need not necessarily mean to a finder of fact that

the higher goal of 30% SBE participation stated elsewhere in

the Code could not have provided a sufficiently distinct basis

for the City’s evaluation.

107a

The facts do make clear that the City insisted upon a re-

bid after the initial bidding round in which Valley came very

close to but did not meet the 35% figure (while very

considerably exceeding the 20%-level designated by the

Subcontracting Outreach Program); in the end, Valley

achieved 40% SBE participation to Cleveland’s 10% -- a

difference of 400%. The record also includes testimony that

the Convention Center project is the only recent City project

for which SBE goals were set at higher than the 20%

Subcontractor Outreach figure. See Ranford depo. at 84.

The City has broad discretion to determine what

constitutes the lowest and best bid. See 321-37; 321-65

(award to the “most advantageous” offeror, “taking into

consideration price and evaluation factors set forth in the

request for proposals”; here the contract was awarded on

“lowest and best” basis); cf. Cedar Bay Construction, 50 Ohio

St.3d at 21. Construing all the facts in the light most

favorable to the Defendants for summary judgment purposes,

the court determines that a reasonable finder of fact could

decide that the cost cap provision is not triggered because the

City arrived at its award for reasons substantially enough

beyond the Subcontracting Outreach Program as to make

“information concerning compliance” with that program

something less than the primary basis for the award. That is

an issue for trial next month.

The court therefore denies all motions for summary

judgment in this matter.

108a

Cleveland's Motion for Injunctive Relief

The court at this time will deny Cleveland’s motion for

injunctive relief pending trial. The parties’ desires with regard

to the scheduling of this case have been solicited on a regular

basis. After the action was removed to and returned from

federal court, Cleveland opted not to seek a prompt hearing

on preliminary injunction, but sought rather to engage in the

extended discovery reflected in the voluminous materials

relating to the summary judgment motions. Cleveland then

waited to the final day of the dispositive motion period --

almost one year after the action was filed and roughly three

months prior to the scheduled June 20, 2005 trial date—to

pursue its preliminary injunction request.

Moreover, Cleveland has provided no evidence

whatsoever to meet its burden of proving (by clear and

convincing evidence) various elements required to win

injunctive relief. For example, the court has been presented

with no evidence, apart from the McKillip affidavit provided

by the City, as to the current status of the Convention Center

drywall project, the equitable balance of harms among the

parties, and important factors affecting the public interest.

The trial date now is not much more than one month away;

the evidence adduced there surely will help inform any

decisions with regard to injunctive relief. The court in the

exercise of its equitable powers will await that necessary

information as presented by the parties in an orderly manner

at trial.

SO ORDERED

/s/

Fred Nelson,

Judge

109a

Kelly Lundrigan, 225 West Court Street, Cincinnati,

OH 45202 (fax: 721-4268)

Leonard Weakley, Jr., One West Fourth Street, Suite

900, Cincinnati, OH 45202 (fax: 381-9206)

David Barth, 537 East Pete Rose Way, Suite 400,

Cincinnati, OH 45202 (fax: 852-8222)

APPENDIX O

C

This text is long and has been trimmed here. Open the source document for the complete record.

This is a copy of a public record, reproduced as it was published. It is not legal advice, and it may not be the version a court would rely on. Check the official source before you cite it.

A word about cookies

We need a few to keep you signed in and the library working. The rest help us see which pages people use and where they get stuck. They stay off unless you say yes.