Petition for Writ of Certiorari — Virginia v. Browner
Supreme Court brief1997
Ask Donna
What actually matters in this document.
Text
[) FILED
In The
Supreme Court of the United States
October Term, 1996
.
COMMONWEALTH OF VIRGINIA,
Petitioner,
V.
CAROL M. BROWNER, Administrator of the
United States Environmental Protection Agency,
and UNITED STATES ENVIRONMENTAL
PROTECTION AGENCY,
Respondents,
and
AMERICAN LUNG ASSOCIATION OF
NORTHERN VIRGINIA, ET AL.,
Intervenors.
7
On Petition For A Writ Of Certiorari
To The United States Court Of Appeals
For The Fourth Circuit
.
PETITION FOR A WRIT OF CERTIORARI
¢
James S. Giimore, III
Attorney General of Virginia
Davip E. ANDERSON Joun P. Scumrrz, Esquire
Chief Deputy Attorney Grecory S. Wavpen, Esquire
General Tuomas Dicence, Esquire
Mayer, Brown & Ptatt
Joun Paut Woontey, Jr. 2000 Pennsylvania Avenue,
Deputy Attorney General N.W.
Rocer L. CHAFFE Suite 6500
Senior Assistant Attorney Washington, D.C. 20006-1882
General (202) 463-2000
Mary Jo LeuGers Of Counsel
Assistant Attorney General
(Counsel of Record)
900 East Main Street
Richmond, Virginia 23219
(804) 786-2444
oooolh"_e=Seeeeeeeeee——
COCKLE LAW BRIEF PRINTING CO., (800) 225-6964
OR CALL COLLECT (402) 342-2831
QUESTIONS PRESENTED
Whether the Court of Appeals incorrectly deferred to
EPA in accepting that agency's interpretation of
§ 502(b)(6) of the Clean Air Act, thus requiring Vir-
ginia to change its standing law and upsetting a core
function of state sovereignty despite the lack of clear
Congressional intent to do so.
Whether the Title V mandates, sanctions, and enforce-
ment provisions of the Clean Air Act, when viewed
together as a statutory scheme, unconstitutionally
commandeer the legislative processes of the States by
compelling them to enact and administer a federal
regulatory program that, inter alia, requires the States
to waive their sovereign immunity from challenges to
state permitting decisions, in violation of the Tenth
Amendment and the principles embodied in New York
v. United States, 505 U.S. 144 (1992).
Whether the Clean Air Act’s draconian sanction pro-
visions, which continue even after a federal permit
program is imposed, are unconstitutional exercises of
Congress’ Spending Clause and/or Commerce Clause
powers because (a) their sole purpose and effect is to
coerce States into administering a federal regulatory
program, and (b) they are “so coercive as to pass the
point at which pressure turns into compulsion,” South
Dakota v. Dole, 438 U.S. 203 (1987).
ii
LIST OF PARTIES BELOW
In accordance with Rule 14(b) of the Rules of the
United States Supreme Court, the following is a list of the
parties to the proceeding below:
The Petitioner was the Commonwealth of Virginia.
The Respondents were the Administrator of the Envi-
ronmental Protection Agency and the Environmental Pro-
tection Agency itself.
Intervenors were the American Lung Association of
Northern Virginia; the American Lung Association of Vir-
ginia; Audubon Naturalist Society; Clean Water Action;
Friends of the Rivers of Virginia; James River Association;
Mountain Heritage Alliance; Valley Concerned Citizens;
Virginia Chapter of the Sierra Club; Virginia Consortium
for Clean Air; Virginia Council, Trout Unlimited; Envi-
ronmental Defense Fund; Kathleen F. Derricott; Clifton E.
Derricott; Andre L. Brown; Caleata Johnson; and Gwen
Hedgepath.
Amici Curiae were Virginia Manufacturers Associa-
tion; Washington Legal Foundation; Ogden Martin Sys-
tems of Lancaster, Incorporated; Ogden Martin Systems
of Alexandria, Incorporated; National Independent
Energy Producers; Ogden Martin Systems of Fairfax,
Incorporated; and Chesapeake Bay Foundation.
— a
iil
TABLE OF CONTENTS
Page
GUE MEU. COMMU EOD oc vse ccvccnsccnsscnsvcss i
Se Ur OOM MOY occ sccccnincastccvacencce ii
Se IEEE, Oa. cc Uh wspebivdasovececeses iii
ME SE WORT UME MEE SIES oon 5 sccnrcascasccecsesess Vv
I by Gas ewok kh Saks ckecckbeceashesucs 1
POPC EEE oS cuvivecenccces Srey erery. eer rerey 1
CONSTITUTIONAL PROVISIONS AND STATUTES
i ie trka we eh ess) kaha b hon sie ube huhss ie 1
DEALEMENE OF THE CASE ........cccccceccccccss 3
REASONS FOR GRANTING THE WRIT ........... 9
I. The Court of Appeals Improperly Deferred to
EPA’s Interpretation of § 502(b)(6) Even Though
Congressional Intent Is Unclear and That Inter-
pretation Intrudes Upon State Sovereignty In
Violation of Gregory v. Ashcroft................ 10
A. EPA's Interpretation Is an Acknowledged
Administrative Invention ................. 12
B. Gregory Precludes Automatic Deference to EPA
When State Sovereignty Is Threatened....... 12
C. If the Court of Appeals Had Correctly
Applied Gregory to EPA’s Interpretation of
§ 502 (b) (6), the Latter Would Necessarily
ee SS PO MED 0 66 bie ence waaseuensss 15
[l. The Court of Appeals Improperly Applied New
York v. United States by Failing To Analyze the
Mandatory Language of Title V and the Overall
Impact of the Statutory Scheme............... 16
iv
TABLE OF CONTENTS - Continued
Page
A. The Challenged Statutory Scheme Com-
mandeers the Legislative Processes of the
ogres PEETEST ELC ee ee ny a ae 17
B. The Sanctions and Other Coercive Measures
Used To Force State Compliance Violate the
Tenth Amendment and Are Impermissible
Exercises of Congress’ Spending and Com-
merce Clause Powers ..................... 19
Ill. The Court of Appeals Failed to Apply This
Court’s Ruling in South Dakota v. Dole in any
ete atin AER eT Ts ene 23
A. The Highway Sanction as Employed in the
Title V Context Is Coercive............... 24
B. The Condition Imposed on Highway Fund-
ing Under the CAA Is Not Reasonably
Reiated To its Purpose.................... 27
AMEE oy se thcxr cs elaadueihs ee 30
FES OIG 8S SERS CERCA aa ra eee App. 1
Vv
TABLE OF AUTHORITIES
Page
Cases
Association of Community Orgs. for Reform Now v.
Edwards, 81 F.3d 1387 (5th Cir. 1996), petition for
cert. filed, 65 U.S.L.W. 3110 (U.S. July 22, 1996)
PO PEFR krlestcaciveuse igen 18
Atascadero State Hosp. v. Scanlon, 473 U.S. 234
NOE 50s SAN ho wb ks hE Vo nw ndd Hea ta cas 13
Board of Natural Resources v. Brown, 992 F.2d 937
GO eM COMPS Hicks. 4 5 Sane id shoe sabe ceeds es. 18
Chevron, U.S.A. v. Natural Resource Defense Council,
FF SP MT SOME CAs 88 Hon Ck eT AKG aK OR 10, 12
Commonwealth v. Browner, 80 F.3d 869 (4th Cir.
SPP Me Kcektheadenbidévebarkicotweneevbine passim
Commonwealth v. Browner, No. 95-1052, slip op.
a Gs TU SE POO ais. isc peta hak chs 1
Commonwealth of Virginia v. United States, 74 F.3d
WaP N SaA MPPDL eV bps 4k vi das sda kado ed cunkh 20
FERC v. Mississippi, 456 U.S. 742 (1982) ........... 7, 22
Frank v. United States, 78 F.3d 815 (2d Cir. 1996),
petition for cert. filed, 65 U.S.L.W. 3053 (U.S. June
AG, ROO ARO PEE + 5c 9N5 Vices ecbaeRTs dak oks 18
Garcia v. San Antonio Metro. Transit Auth., 469 U.S.
amply ect PEE EEE TET ET ET EPR PROT PRO Su aD revue ae
Gregory v. Ashcroft, 501 U.S. 452 (1991)............. passim
Hodel v. Virginia Surface Min. & Reclam. Ass'n, 452
Sate I SOME 955 8 srk vee ranerivevassenries 17, 20
Koog v. United States, 79 F.3d 452 (5th Cir. 1996),
petition for cert. filed, U.S. v. Gonzalez, 65
U.S.L.W. 3001 (U.S. June 19, 1996) (No. 95-2052) .... 18
vi
TABLE OF AUTHORITIES —- Continued
Page
Nevada v. Skinner, 884 F.2d 445 (9th Cir. 1989), cert.
denied, 493 U.S. 1070 (1990)................ 24, 26, 28
New York v. United States, 505 U.S. 144 (1992) ... passim
Oklahoma v. Schweiker, 655 F.2d 401 (D.C. Cir. 1981) .... 24
Pennsylvania v. EPA, 500 F.2d 246 (3d Cir. 1974)...... 6
Printz v. United States, 66 F.3d 1025 (9th Cir. 1995),
cert. granted, __U.S.__, 116 S.Ct. 2521 (1996)..... 18
South Dakota v. Dole, 483 U.S. 203 (1987) ........ passim
Steward Machine Co. v. Davis, 301 U.S. 548 (1937) .... 24
United States v. Butler, 297 U.S. 1 (1936).......... 26, 28
United States v. Lopez, __U.S.__, 115 S.Ct. 1624
LESOOP sas cn 8WAds ces vaduiee aba keeexe ssn 26, 29
Virginia Dep't of Educ. v. Riley, 86 F.3d 1337 (4th
Cir.), reh'g requested (August 5, 1996)........... 26, 27
UnNiTep STATES CONSTIYUTION
i MMP EOEEEOTEPETT Te TUT ree et ee 4, 12, 14
COMME GARG onc k ci eee inks eks Concise Camas passim
SI GAMUDE. 5560s satis Sones eenbeadestewes passim
FUERTE CT ETE EY PELE ere passim
DOUPORE. ARAINGOR . ~ «ss 90 <a kinnd ccaga st aaenee caer 13
Vii
TABLE OF AUTHORITIES - Continued
Page
FEDERAL STATUTES
42 USC. § 7413 (CAA § 113)............... 3, 6, 20, 21
42 US.C. § 7413(a) (CAA § 113fa))................... 6
42 U.S.C. § 7413(a)(3) (CAA § 113(a)(3)).............. 6
42 U.S.C. § 7413(b) (CAA § 113(b)) .................. 6
42 US.C. § 7509(b) (CAA § 179(b)) .................. 9
42 U.S.C. § 7509(b)(1) (CAA § 179(b)(1)) ........... 4,8
42 U.S.C. § 7509(b)(2) (CAA § 179(b)(2)) ............. 5
42 U.S.C. § 7602(e) (CAA § 302(e))................. 3, 6
42 U.S.C. § 7607(b)(1) (CAA § 307(b){1)) ............. 8
42 U.S.C. § 7661a(b)(6) (CAA § 502(b)(6)) ....... passim
42 U.S.C. § 7661a(d) (CAA § 502(d))................. 3
42 U.S.C. § 7661a(d)(3) (CAA § 502(d)(3))............ 6
Title V of the CAA
(Re UR. BB FOC FOGED ok ccc cceccaceues passim
Cope OF VIRGINIA
i MEME Gaby suva ses ic es bane nadscevi ei cheinkl ya
FEDERAL REGULATIONS
ESR ARR nays aaa
I WO he Lien Pek k Cc ew Kee ee ih cbc Kaus 9
Pe ee ee SUN Uk ks Wa Kehis Abad Feb ckka le Seas 7
nS tet tn cal
PETITION FOR WRIT OF CERTIORARI
TO THE UNITED STATES COURT OF APPEALS
FOR THE FOURTH CIRCUIT
The Commonwealth of Virginia (“Commonwealth”)
hereby petitions this Court for a writ of certiorari to
review the judgment of the United States Court of
Appeals for the Fourth Circuit in this matter.
ia
OPINION BELOW
The opinion of the United States Court of Appeals for
the Fourth Circuit, dated March 26, 1996, is reported at 80
F.3d 869 and is also set forth in the Appendix at App. 1.
The July 12, 1996 order of the Court of Appeals denying
the Commonwealth’s Petition for Rehearing and Sugges-
tion for Rehearing In Banc, with five judges voting to hear
the case in banc, is set forth in the Appendix at App. 33.
Commonwealth of Virginia v. Browner, No. 95-1052, slip op.
(4th Cir. July 12, 1996).
JURISDICTION
The jurisdiction of this Court to issue a writ of cer-
tiorari in this case is grounded upon 28 U.S.C. § 1254(1).
¢
CONSTITUTIONAL PROVISIONS
AND STATUTES INVOLVED
This case involves the Spending and Commerce
Clauses of and the Tenth Amendment to the United Siates
Constitution, various provisions of the federal Clean Air
Act (“CAA”), and § 10.1-1318 of the Code of Virginia
(1950), as amended.
The Spending Clause, Article I § 8 of the United
States Constitution, provides:
The Congress shall have power to lay and col-
lect taxes, duties, imposts and excises, to pay the
debts and provide for the common defense and
general welfare of the United States... .
The Commerce Clause, Article I § 8 of the United
States Constitution, provides:
The Congress shall have power . . . [t]o regulate
commerce with foreign nations, and among the
several states, and with the Indian Tribes .. . .
The Tenth Amendment to the United States Constitu-
tion provides:
The powers not delegated to the United States
by the Constitution, nor prohibited by it to the
states, are reserved to the states respectively, or
to the people.
Title V of the CAA is found at 42 U.S.C. § 7661
through § 7661f, and is set forth in the Appendix at App.
35-67. Section 502(b)(6) of Title V, 42 U.S.C. §& 7661a(b)(6),
is of particular importance here. It requires the Adminis-
trator of the Environmental Protection Agency (“EPA”) to
promulgate regulations establishing the minimum ele-
ments for an approvable state operating permit program,
including:
Adequate, streamlined, and reasonable pro-
cedures . . . for expeditious review of permit
actions . . . including an opportunity for judicial
3
review in State court of the final permit action
by the applicant, any person who participated in
the public comment process, and any other per-
son who could obtain judicial review of that
action under applicable law.
The other CAA provisions involved in this case are
42 US.C. § 7413, 42 U.S.C. § 7509(b), and 42 U.S.C.
§ 7602(e), all of which are set forth in the Appendix at
App. 68-76.
Section 10.1-1318(B) of the Code of Virginia is the
Commonwealth's judicial review law for appeals of state
air pollution permit decisions, which is set forth in the
Appendix at App. 77.
¢
STATEMENT OF THE CASE
As amended by the addition of Title V in 1990, the
CAA mandates a national operating permit program for
facilities that emit air pollution, and requires each State to
run such a program within its borders. CAA § 502(d) (42
U.S.C. § 7661a(d)) (App. 43-45). To this end, Title V orders
States, in no uncertain terms, to legislate and regulate
according to Congressional and EPA directives: Each
State “shall” enact and administer a Title V program. Id.
Title V and its implementing regulations found at 40
C.F.R. Part 70 set forth specific and detailed criteria that
the State programs must meet, and each program must
gain EPA’s approval before it can be implemented. For
approval, § 502(b)(6) of Title V provides that each State
must enact legislation that affords judicial review in state
court of state-issued operating permits to any person who
participated in the public comment period. CAA
§ 502(b)(6) (42 U.S.C. § 7661a(b)(6)) (App. 41-42); 80 F.3d
at 876 (App. 13). Acknowledging that § 502(b)(6) could
not mean literally what it says, EPA interpreted it to
mean that States must, at a minimum, afford standing
consistent with Article III jurisprudence of this Court.
That this direct Congressional command is manda-
tory and intended to commandeer the legislative and
regulatory processes of the States is further evidenced by
the means provided to force compliance. These means
comprise the remainder of the statutory scheme chal-
lenged by the Commonwealth.
Noncomplying States are subjected to coercive pres-
sures and are punished severely and continuously until
they succumb. Specifically, Congress directed EPA to use
several punitive sanctions and authorized it to initiate
civil and criminal enforcement proceedings against the
States and their officials. First, in areas deemed not in
attainment for ozone, non-complying States will lose the
majority of their federal highway construction funds and
be denied federal approvals needed for highway con-
struction projects, even those funded solely with state
monies. CAA § 179(b)(1) (42 U.S.C. § 7509(b)(1)) (App.
74-75). Thus, even if a State wished to forego federal
funding, it could not expend its own funds for any proj-
ect needing federal approval. The Commonwealth esti-
mates that the highway funding ban would result in a
loss of approximately one billion dollars in federal funds
over a three-year period in its three nonattainment areas.'
1 This estimate was made at the time the Commonwealth
filed its Petition for Review with the Court of Appeals.
The highway funding and approval sanctions would crip-
ple the Commonwealth’s highway construction program
in the three most populated areas of Virginia: the North-
ern Virginia, Richmond Metropolitan, and Hampton
Roads areas.
Second, the States would suffer an “offset” sanction
that would require them to impose a 2-for-1 pollution
reduction condition on construction permits (as opposed
to operating permits), which would effectively end indus-
trial development in nonattainment areas.2 CAA
§ 179(b)(2) (42 U.S.C. § 7509(B)(2)) (App. 76). While the
2-for-1 offset requirement would be imposed on industry
and not on the non-complying State, the sanction none-
theless is leveled at the State. For example, if the offset
sanction were imposed in Virginia, it would be done so as
a direct result of the Commonwealth's refusal to conform.
The sanction would coerce the Commonwealth through
economic disruption and pressure exerted on it by those
citizens and industry affected.
In addition, Title V instructs EPA to develop and
enforce a federally run program within the non-comply-
ing State as a temporary measure to fill the “gap” in time
until the overwhelming impact of the sanctions forces the
? For example, for each ton of pollutant a permit applicant
plans to emit, the applicant would have to provide a
corresponding two ton reduction through some other means as
an “offset.” The State would have to include this offset sanction
“condition” in all construction permits issued prior to the
commencement of construction initiated pursuant to other state
regulations. The “condition” would later be memorialized in
each facility’s operating permit that would be issued after
construction is completed.
State to run the program itself. CAA § 502(d)(3) (42 U.S.C.
§ 7661a(d)(3)) (App. 45). In order to keep the pressure on
- for the dual purpose of coercion and punishment — the
highway funding and approval sanctions and the offset
sanction remain in full force even after the federally run
program is in place.
Civil and criminal enforcement under § 113 of the
CAA is the final coercive component of the challenged
statutory scheme that EPA has at its disposal to force
State cooperation. 42 U.S.C. § 7413 (App. 69-70). The CAA
authorizes EPA to issue enforcement orders and to bring
suit for injunctive and penalty relief against “any person”
for any violation of Title V. CAA § 113(a)(3) and § 113(b)
(42 U.S.C. § 7413(a)(3) and § 7413(b)) (App. 69-70). “Per-
son” is defined in the CAA to include States and their
officials. CAA § 302(e) (42 U.S.C. § 7602(e)) (App. 77).
Thus, § 113 would cover any violation by a State of the
requirement to enact an operating permit program. EPA
also can employ § 113(b) to compel a non-complying
State to enforce the federally imposed Title V plan.°
3 The Court of Appeals misapprehended the
Commonwealth’s argument regarding § 113 of the CAA. That
court focused only on subsections (1) and (2) of § 113(a), and did
not consider EPA’s enforcement power found in subsections
(a)(3) and (b) of § 113, 80 F.3d at 881 (App. 25). Furthermore,
neither the Court of Appeals nor EPA ever addressed the
Commonwealth’s additional argument that § 113 can be, and
has been, used to force States to enforce a federally imposed
program. Cf. Pennsylvania v. EPA, 500 F.2d 246, 261 (3d Cir. 1974)
(EPA “acted within the federal commerce power in requiring the
Commonwealth to enforce [EPA's] transportation plan”).
Ait PRAM be ARAL: Beaty Soy sels AP
As a result of the passage of Title V, the Commonwealth
has had to adopt and amend statutes, to promulgate regula-
tions, as well as to spend millions of dollars preparing to
implement the federal Title V program. The Commonwealth
~— along with most other States — has in essence given in to
most of this compulsory federal micromanagement in order
to retain its ability to regulate Virginia industry and protect
its air quality. It has worked hard and in good faith to obtain
EPA approval and to avoid the onerous sanctions awaiting
those States who fail to secure EPA’s approval or who dare to
defy the federal mandates.
The Commonwealth, however, drew the line at the Con-
gressional mandate that it expand the jurisdiction of its
courts to hear challenges to state air permit decisions by any
person who participated in the public comment process.
Primarily because of this refusal, EPA rejected the Common-
wealth’s Title V program on December 5, 1994. 59 Fed. Reg.
62,324.4 In order to obtain its approval, EPA continues to
demand that the Virginia General Assembly alter its stand-
ing statute to open Virginia courts to persons who currently
do not satisfy the state standard.®
4 EPA listed a total of five reasons for disapproving
Virginia’s operating permit program. 59 Fed. Reg. 62,324.
Pursuant to discussions with EPA, all of the remaining
“deficiencies” have been corrected and the Commonwealth
resubmitted its program to EPA for a third time on September
10, 1996.
5 Any such expansion necessarily involves an expanded
waiver of the Commonwealth’s sovereign immunity to allow a
broader range of suits against state agencies in state courts. This
case, therefore, presents the question raised by Justice Powell in his
dissent in FERC v. Mississippi, 456 U.S. 742, 772 (1982) and avoided
by the majority in that case. Id. at 769, n.31 and at 770, n.33 and n.34.
On January 9, 1995, the Commonwealth filed a peti-
tion for review in the Court of Appeals for the Fourth
Circuit, pursuant to § 307(b)(1) of the CAA, 42 U.S.C.
§ 7607(b)(1). The petition challenged EPA’s disapproval
based on its conclusion that the Commonwealth must
expand the jurisdiction of its courts, arguing that EPA's
interpretation of the Title V standing provision was erro-
neous. The Commonwealth also challenged all of the
disapproval reasons on the basis that Title V’s substantive
mandates and the severe sanctions - when viewed
together as a single statutory scheme - unconstitutionally
commandeer the legislative processes of the Common-
wealth to enact and administer a federal regulatory pro-
gram, in violation of the Tenth Amendment to the United
States Constitution and in conflict with this Court's rul-
ing in New York v. United States, 505 U.S. 144 (1992). The
Commonwealth also argued that the highway sanction
itself, as applied in the Title V context, violates the
Spending Clause because it passes the point where finan-
cial inducement turns into compulsion, as prohibited by
this Court in South Dakota v. Dole, 483 U.S. 203, 211 (1987).
On March 26, 1996, the Court of Appeals denied the
Commonwealth's petition, holding that each of the Title
V sanction provisions, standing alone, were constitutional
exercises of Congress’ Spending and Commerce Clause
powers. App. 28-29. On July 12, 1996, the Court of
Appeals denied the Commonwealth’s Petition for Rehear-
ing and Suggestion for Rehearing In Banc, although five
judges - Judges Russell, Widener, Wilkins, Luttig, and
Williams - voted to hear the case in banc. App. 34.
Because the Commonwealth has failed to bend to the
federal will, EPA is now preparing to implement a
= | ere tT
federally run permit program in Virginia.6 Such imple-
mentation, however, will do nothing to alter or delay the
application of the sanctions described above.”
S
REASONS FOR GRANTING THE WRIT
Rule 10(c) of the Rules of this Court provides that a
writ of certiorari will be granted only when there are
compelling reasons for doing so. These include situations
in which a federal court of appeals has decided an impor-
tant federal question (1) which has not been, but should
be, decided by this Court, (2) in a way that conflicts with
relevant decisions of this Court, or (3) in a way that
conflicts with other federal circuit courts.
This case presents several such questions, any one of
which meets the foregoing criteria. Title V represents a
shift in Congress’ approach to regulating air pollution,
and depicts a not-so-subtle move towards outright fed-
eral dictation to and coercion of the States.
In New York v. United States, this Court struck down a
federal statute as violative of the Tenth Amendment and
drew a line beyond which Congress could not go in
“commandeering” state governments to carry out federal
© EPA and the Commonwealth are currently negotiating a
delegation agreement under 40 C.F.R. Part 71 whereby the
Commonwealth would serve as an EPA “contractor” and
operate the federal program for EPA.
? Before imposing sanctions, EPA must issue a rule to
determine which sanction to impose first. CAA § 179(b) (42
U.S.C. § 7509(b)) (App. 74-76). Thus, no sanctions have been
imposed in Virginia yet.
10
programs. The Court of Appeals in the present case has
eliminated and rejected any meaningful application of the
New York decision. By examining the sanctions faced by
the Commonwealth piecemeal instead of stacked together
as they are actually imposed, the Court of Appeals erro-
neously minimized their impact and thereby failed to
apply New York correctly. 80 F.3d at 881 (App. 28-29). By
characterizing the sanctions as “inducements” rather than
coercion, the Court of Appeals also discarded this Court's
most recent Spending Clause jurisprudence reflected in
South Dakota v. Dole. 80 F.3d at 882 (App. 28).
This case squarely presents critical issues regarding
the nature of the federal system. It tests the extent of
constitutional limitations placed by New York and Dole on
the power of the federal government to dictate to the
sovereign States and to force them — under pain of multi-
ple and severe sanctions - to implement federal pro-
grams. This Court’s answer to these questions will
provide pivotal guidance for both Congress and the
States who must work together within the federal frame-
work.
I.
The Court of Appeals Improperly Deferred to EPA’s
Interpretation of § 502(b)(6) Even Though Congres-
sional Intent Is Unclear and That Interpretation
Intrudes Upon State Sovereignty In Violation of Gre-
gory v. Ashcroft
The Court of Appeals treated the statutory issue in
this case as though it were merely a matter of interpreting
§ 502(b)(6) of the CAA and nothing more. Following this
Court’s ruling in Chevron, U.S.A. v. Natural Resources
11
Defense Council, 467 U.S. 837 (1984), it simply deferred to
EPA’s interpretation. 80 F.3d at 878 (App. at 17-18). It thus
overlooked the constitutional ramifications of EPA’s
interpretation and its impact on state sovereignty.
In so doing, the Court of Appeals erroneously deter-
mined that this Court’s more recent and controlling deci-
sion in Gregory v. Ashcroft, 501 U.S. 452 (1991), did not
apply in this case. Where Congressional intent is unclear,
Gregory requires that courts not defer to an agency’s
interpretation if that interpretation would intrude on a
state sovereign prerogative. Because Congressional intent
in this case is not clear and EPA’s interpretation intrudes
on a fundamental state prerogative, the agency's inter-
pretation is not entitled to deference.®
8 In Gregory, this Court was asked to decide whether,
pursuant to the federal Age Discrimination in Employment Act
(“ADEA”), state-appointed judges were protected from a
Missouri State requirement for mandatory retirement at age 70.
Missouri argued that the judges were not included under the
ADEA because they fall with an exception for “appointee[s] on
the policymaking level.” The Court found that the extension of
the ADEA to state employees was a valid exercise of Congress’
Commerce Clause powers, and that all state employees were
covered by the Act except those who fell within one of the
exceptions. 501 U.S. at 467. The Court determined, however,
that the ADEA was ambiguous regarding whether state judges
fell within the exception of an “appointee on the policymaking
level.” Id. Thus, this Court concluded Congress’ intent to cover
state judges in the ADEA was ambiguous. Id. at 470. The Court
held that, “[iJn the face of such ambiguity, we will not attribute
to Congress an intent to intrude on state governmental
functions regardless of whether Congress acted pursuant to its
Commerce Clause powers or § 5 of the Fourteenth
Amendment.” Id.
12
A.
EPA’s Interpretation Is an Acknowledged Administra-
tive Invention
At the outset of this dispute, both EPA and the Com-
monwealth agreed on at least one thing: The words in
§ 502(b)(6) should not be read literally. Under its plain
meaning, the provision requires States to afford standing,
regardless of injury to any person who participated in
any way in the public comment process for the issuance
of a state permit. EPA recognized that even federal judi-
cial standing cannot go so far and is limited by the
requirements of Article III of the United States Constitu-
tion, as interpreted by this Court.
Nonetheless, EPA decided to interpret § 502(b)(6) as
requiring the equivalent of Article III standing without
any basis in either the law itself or its legislative history.
Having done so, EPA determined to force States such as
the Commonwealth to provide such standing for their
Title V programs or face disapproval of those programs.
The Court of Appeals mechanically declared this inter-
pretation reasonable and a “safe harbor,” affording it
Chevron deference. Id.
Gregory Precludes Automatic Deference to EPA When
State Sovereignty Is Threatened
Under different circumstances, EPA’s action might be
entitled to Chevron deference. In many cases involving the
interpretation of a federal statute, there are no implica-
tions for the balance of federal-state power. In those
situations, judicial review is appropriately deferential to
13
the interpretation of the agency charged with implement-
ing the statute. By contrast, where - as here - an inter-
pretation would displace or intrude into some essential
core function of state sovereignty, this Court requires a
clear statement of legislative intent before accepting such
an interpretation. Ambiguity will not do. Gregory, 501
U.S. at 464.9
In Gregory v. Ashcroft, this Court recognized that an
essential component of a healthy federal structure is a
balance of power between federal and state sovereigns. In
addressing issues affecting fundamental aspects of state
sovereignty, therefore, “ ‘it is incumbent upon the federal
courts to be certain of Congress’ intent before finding that
federal law overrides” that balance. 501 U.S. at 460 (quot-
ing Atascadero State Hospital, 473 U.S. at 243). “[I]f Con-
gress intends to alter the usual constitutional balance
between the States and the Federal Government, it must
do so unmistakably clear in the language of the statute.”
501 U.S. at 460 (internal quotations omitted). Where Con-
gressional intent is ambiguous, this Court has instructed
the courts “not [to] attribute to Congress an intent to
intrude on state governmental functions.” 501 U.S. at 470.
° At the time Gregory was decided, this Court in Garcia v.
San Antonio Metro. Transit Auth., 469 U.S. 528 (1985) had
relegated the States’ Tenth Amendment protections essentially
to the political process. The “plain statement rule” was derived
from this Court’s Eleventh Amendment jurisprudence typified
by Atascadero State Hosp. v. Scanlon, 473 U.S. 234 (1985), and was
designed by this Court to protect the rights of the States and to
prevent circumvention of the political process through judicial
(and certainly through administrative) interpretation of
ambiguous legislation.
14
Below, the Court of Appeals addressed the Common-
wealth’s Gregory argument only briefly. It determined
that Gregory did not apply to this case because, unlike the
facts in Gregory, there is no question that the “plain
meaning” of § 502(b)(6) shows that it applies to state
courts. That statement of the obvious begs the question:
Did Congress intend, through the application of
§ 502(b)(6), that States waive their sovereign immunity
and expand their standing laws to hear a broader range
of challenges to state-issued permits in state court than
may be currently authorized by state law?!°
The Commonwealth has never disputed that
§ 502(b)(6) applies to state courts. The provision is undis-
putedly ambiguous, however, regarding Congress’ intent
to force states to adopt a different judicial review stan-
dard, and it is altogether silent on whether the federal
Article III standard should apply.
Furthermore, access to state courts is a core element
of a State’s sovereignty. The Court of Appeals conceded
as much. 80 F.3d at 879 (App. at 19-29). Any expansion of
standing to sue a sovereign in its own courts constitutes a
waiver of that sovereign’s immunity. It is -difficult to
imagine a more essential element of sovereignty than the
ability to control the acts for which the sovereign itself
10 The Court of Appeals’ perfunctory acknowledgment of
Gregory produces an absurd result. Since the plain statement
requirement of Gregory applies only when a federal law
threatens to impact a function of state sovereignty, any statute
examined in light of that ruling must of necessity apply to a
state. The Court of Appeals chose not to apply Gregory to the
very type of situation for which it was designed.
a) yee
15
can be held judicially accountable in its own courts. In
Gregory, the state governmental function at issue
involved the qualifications of state court judges, which
the Court described as “a decision of the most fundamen-
tal sort for a sovereign entity. Through the structure of its
government, and the character of those who exercise
government authority, a State defines itself as a sover-
eign.” 501 U.S. at 460. In the present case, the issue
involves equally fundamental aspects of state sover-
eignty: the jurisdiction of state courts and the States’ right
to decide by whom they may be sued.
Despite this, the Court of Appeals brushed aside
Gregory. In so doing, it allowed EPA, in clear contraven-
tion of Gregory, to administratively interpret § 502(b)(6) in
such a way as to intrude into the core sovereignty of the
Commonwealth.
.
If the Court of Appeals Had Correctly Applied Gregory
to EPA’s Interpretation of § 502(b)(6), the Latter Would
Necessarily Have Been Set Aside
Had the Court of Appeals applied the clear statement
requirement of Gregory correctly, it would have declined
to defer to EPA’s interpretation of § 502(b)(6). Instead it
would have looked for a clear statement of whether the
statute was intended by Congress to apply in the particu-
lar manner claimed by EPA. See Gregory, 501 U.S. at
460-70. Had it done so, it would necessarily have con-
cluded that no such statement of Congressional intent
exists. The Court of Appeals should have ruled that EPA’s
16
interpretation of the statute improperly attributes to Con-
gress the intent to interfere with the usual constitutional
balance by dictating to the Commonwealth who must be
provided access to state courts. Furthermore, the Court of
Appeals should have directed EPA to interpret § 502(b)(6)
consistently with state law. The Commonwealth sug-
gested such a solution, but the Court of Appeals rejected
it. 80 F.3d at 877-78 (App. at 17-18).
EPA’s interpretation improperly creates a constitu-
tional issue rather than avoiding one and thereby violates
the guiding principle of Gregory. Because Congress has
not spoken in unmistakably clear terms on this issue,
EPA’s interpretation is unquestionably arbitrary, capri-
cious, and not in accordance with law. It should have
been and must be set aside.
The Court of Appeals Improperly Applied New York v.
United States by Failing To Analyze the Mandatory
Language of Title V and the Overall) Impact of the
Statutory Scheme
The Court of Appeals evaded the Tenth Amendment
issue in this case by ignoring the mandatory language of
Title V, by divicing the challenged statutory scheme into
discrete provisions, and by examining each without
analyzing the workings of the whole. While other consti-
tutional flaws exist, it is the combined force of these
provisions, which are cumulative and applied simul-
taneously, that most offends the Tenth Amendment. The
Title V mandates and the sanctions and enforcement pro-
visions of the CAA together form an increasingly common
Fle alte te ap a lll mia a i
_
ee ee ee ee ee eee ee eC Ue
a
Statutory scheme that unconstitutionally coerces States
into enacting and administering a federal regulatory pro-
gram. As such, it violates the Tenth Amendment and the
principles embraced by this Court in New York.
A.
The Challenged Statutory Scheme Commandeers the
Legislative Processes of the States
This Court in New York sent a clear message to Con-
gress that its power to require the States to do its bidding
has limits: Congress simply cannot “ ‘commandee[r] the
legislative processes of the States by directly compelling
them to enact and enforce a federal regulatory program.’ ”
New York, 505 U.S. at 161 (quoting Hodel v. Virginia Surface
Min. & Reclam. Ass'n, 452 U.S. 264, 288 (1981)). “{T]he
Constitution has never been understood to confer upon
Congress the ability to require the States to govern accord-
ing to Congress’ instructions.” 505 U.S. at 162.
The Title V scheme of direct commands backed by
severe penalties is exactly the type of Congressional over-
reaching this Court rejected in New York. Title V’s clear
intent is to commandeer the legislative process of the
States to enact and administer a federal operating permit
program. The Court of Appeals, however, failed to recog-
nize this fact because it engaged in virtually no Tenth
Amendment analysis.
In sidestepping the central issue in this case, the
Court of Appeals chose to analyze the sanctions provi-
sions individually and solely under the Spending and
Commerce Clauses - without regard for the CAA’s direct
mandates or for the operation of the statute as a whole -
Cn
18
to determine whether the CAA was constitutional. 80 F.3d
at 880-81. (App. 25-26) (“The CAA is constitutional
because, although its sanctions provisions potentially
burden the states, those sanctions amount to inducement
rather than ‘outright coercion.’ ”). In doing so, the Court
of Appeals erroneously assumed that the direct mandates
would be constitutional so long as each sanction, individ-
ually, was a constitutional exercise of Congress’ powers.
This assumption, however, disregards this Court’s hold-
ing in New York that Congress simply may not order the
States to enact or enforce a federal regulatory program.
See New York, 505 U.S. at 169-70. Several courts of appeals
have relied on New York to strike down federal statutes |
that direct States to adopt and administer federal pro- )
grams. Association of Community Orgs. for Reform Now v. :
Edwards, 81 F.3d 1387 (5th Cir. 1996), petition for cert. filed, |
65 U.S.L.W. 3110 (U.S. July 22, 1996) (No. 96-174) (striking |
down a portion of the Lead Contamination Control Act of .
1988 under the Tenth:Amendment); Koog v. United States, |
79 F.3d 452 (Sth Cir. 1996), petition for cert. filed, United
States v. Gonzalez, 65 U.S.L.W. 3001 (U.S. June 19, 1996) :
(No. 95-2052) (striking down a portion of the Brady Act
under the Tenth Amendment);!! Board of Natural Resources
v. Brown, 992 F.2d 937 (9th Cir. 1993) (striking down a ;
:
:
'! This Court has granted certiorari in two cases
consolidated below in the Ninth Circuit Court of Appeals that
address the constitutionality of the Brady Act. Printz v. United
States, 66 F.3d 1025 (9th Cir. 1995), cert. granted, ___ U.S. __, 116
S. Ct. 2521 (1996). A third petition dealing with this issue was
also filed in 1996. Frank v. United States, 78 F.3d 815 (2d Cir.
1996), petition for cert. filed, 65 U.S.L.W. 3053 (U.S. June 23, 1996)
(No. 95-2006).
19
portion of the Forest Resources Conservation and Short-
age Relief Act under the Tenth Amendment).
As discussed below, the only plausible construction
of the Title V mandates is that it was Congress’ plan to
make the States, and not the federal government, enact
and enforce the federal Title V program. The sanctions
and other coercive measures are the means Congress uses
to force States to do so. Because the Court of Appeals’
decision is inconsistent with this Court’s decision in New
York and the decisions of other federal Circuits in closely
related contexts, the Court should grant certiorari.
The Sanctions and Other Coercive Measures Used To
Force State Compliance Violate the Tenth Amendment
and Are Impermissible Exercises of Congress’ Spending
and Commerce Clause Powers
The Court of Appeals’ analysis was fundamentally
flawed in another way. The court ignored the cumulative
and continuing nature of the CAA sanctions and the
extremely coercive force generated collectively by them.
As a result, the court entirely missed one of the Common-
wealth’s central claims: that the unprecedented stacking
of different sanctions, the effect caused by the interaction
among them, and EPA’s authority to proceed civilly and
criminally against a State - together - inflict impermissi-
bly coercive pressure on the States with the sole purpose
of commandeering State governmental processes, in vio-
lation of the rule of New York.
This Court has identified two “methods . . . by which
Congress may urge a State to adopt a legislative program
sae
20
consistent with federal interests.” See New York, 505 U.S.
at 166. First, the federal government may induce state
action by placing conditions on the State’s receipt of
federal funds, so long as the condition imposed has a
reasonable relationship to the purpose of the expenditure,
and the financial pressure induces rather than coerces.
See, e.g., Dole, 483 U.S. at 211. Second, the federal govern-
ment may offer States the choice between enacting the
federal regulatory scheme or being preempted by federal
regulation. See, e.g., Hodel, 452 U.S. at 282.
In Title V, however, Congress went far beyond these
methods. The CAA mandates State regulation and then
brings all of its various pressures to bear simultaneously
in a finely orchestrated assault designed solely to compel
State compliance. The highway construction funding and
approval sanctions, the offset sanction, and the imposi-
tion of a federally run operating permit program are
mandatory. EPA must impose these sanctions on non-
complying States within certain deadlines, although it
may do so earlier. 80 F.3d at 873, n.2 (App. 6, n.2);
Commonwealth of Virginia v. United States, 74 F.3d 517,
520-21 (4th Cir. 1996). These sanctions operate
cumulatively and, for all practical purposes, simul-
taneously. See id. All are imposed within a matter of a few
months — one being added on top of another. As provided
in § 113 of the CAA, EPA also has the option at the same
time the sanctions are in place to take administrative,
civil, and criminal action against a non-complying State
and its officials.
The layering on of sanctions with federal preemption
creates pressures far more coercive than any of these
measures considered alone, a fact the Court of Appeals
21
failed to recognize. Because of their coordinated and
cumulative coercive effect, a State exercising its Tenth
Amendment right not to enact a federal program is struck
several different ways at once: the simultaneous loss of
federal highway construction funds and the ability to
expend state highway funds, the stagnation of industrial
and economic growth and the dislocation of its citizens’
economic livelihood through the offset sanction, and the
intrusion of a federal regulatory program.!?
The Court of Appeals also grossly underestimated
the coercive nature of the challenged statutory scheme by
dismissing out-of-hand the Commonwealth’s arguments
regarding the offset sanction and § 113. As noted above,
the court analyzed each component of the scheme indi-
vidually, and not as part of the whole. It therefore com-
pletely missed the point that, in concert with the other
sanctions, the offset sanction and § 113 are intended to
coerce States into compliance, thus intensifying the pres-
sure on those States. See Part IV, supra.
Furthermore, the continuation of sanctions after a
federally run program is in place serves only one pur-
pose, which is an illegitimate one: to coerce the States
into foregoing their right not to regulate. This Court in
Hodel and other similar cases has recognized Congress’
12 For example, for failing to enact the federal program, the
Commonwealth will be stopped from building or repairing the
majority of its roads in its three most populated areas. At the
same time, the Commonwealth will itself be required to impose
a permit condition on industry that will greatly inhibit
economic growth in the same areas. Concurrently, EPA will
impose an operating permit program in Virginia.
22
\
authority to pursue substantive federal regulatory inter-
ests through preemption while honoring States’ Tenth
Amendment right to “abandon{] regulation of the field
altogether,” FERC v. Mississippi, 456 U.S. at 766. That
situation does not exist here, however. Assuming
arguendo that the CAA sanctions are needed to control the
increase in pollution caused by a State’s failure to enact a
Title V program, that need would vanish once the federal
government operates a Title V program in that State
because presumably EPA’s program would then control
the increased pollution. At that point, any legitimate fed-
eral interest in controlling air pollution is wholly
exhausted. The only possible interest served by the con-
tinuation of the highway funding and approval sanctions
and the offset sanction is to punish States for not having
themselves enacted the federally dictated scheme - an
interest that the Tenth Amendment condemns as illegiti-
mate and that is an impermissible use of Congress’
Spending and Commerce Clause powers.
Because of the serious impact on federal-state rela-
tions, the principles underlying the New York anti-
coercion rule must apply with heightened force where
sanctions are stackéd and are used to coerce States to
enact and administer a federal program. The coercive
measures used to force State compliance with Title V
violate the Tenth Amendment, and are impermissible
exercises of Congress’ Spending and Commerce Clause
powers. For these reasons, the Court should grant cer-
tiorari.
———-
PP Oe rae eee
23
Ill.
The Court of Appeals Failed to Apply This Court's
Ruling in South Dakota v. Dole in any Meaningful Way
Consistent with the overall pattern that emerges from
the opinion below is the determination not to give signifi-
cant effect to this Court’s most recent ruling on Congress’
exercise of its Spending Clause power. In doing so, the
Court of Appeals avoided any principled analysis of the
limiting language set forth by this Court in Dole. Such
judicial reluctance has resulted in Congress and federal
agencies finding it easier to use the Spending Clause to
circumvent constitutional limitations imposed by the
Tenth Amendment, such as those established in New York.
Congress simply uses its Spending Clause power and, by
threatening to reduce federal funding, coerces States into
doing the federal bidding, thereby accomplishing indi-
rectly what this Court has forbidden to be done directly.
In this case, the cutting off of highway construction
funds is the most draconian element of the challenged
scheme. As used in the Title V context, the funding sanc-
tion serves the sole purpose of forcing States, such as the
Commonwealth, to implement a Title V program
designed and approved by Congress and EPA. This par-
ticular sanction violates two of the Dole requirements: (1)
that the financial penalty for non-compliance not be so
coercive as to turn pressure into compulsion and (2) that
the condition imposed be reasonably related to the pur-
pose of the federal expenditure.
24
A.
The Highway Sanction as Employed in the Title V Con-
text Is Coercive
In Dole, this Court indicated that Congress’ spending
power is not without limit.
[I]n some circumstances the financial induce-
ment offered by Congress might be so coercive
as to pass the point at which “pressure turns
into compulsion.”
483 U.S. at 211 (quoting Steward Machine Co. v. Davis, 301
U.S. 548, 590 (1937)). The Court of Appeals recognized
and even quoted this rule. 80 F.3d at 881 (App. 26). But it
performed only a superficial analysis of the impact of the
highway construction funding sanction on the Common-
wealth, quickly pronouncing it non-coercive. Whatever
standard the court applied is not stated. In essence, it
concluded that because some other courts have upheld
funding restrictions that were “more severe,” the Com-
monwealth’s situation is not serious enough to warrant
further review.!3 80 F.3d at 881-82 (App. 27-28).
13 Dole itself and Nevada v. Skinner, 884 F.2d 445 (9th Cir.
1989), cert. denied, 493 U.S. 1070 (1990), both cited by the Court
of Appeals, involved Congress’ use of the Spending Power to
cut off highway funds to States which refused to change their
laws related to the minimum drinking age and to speed limits,
respectively. Dole itself involved only a small percentage of
highway funds. Oklahoma v. Schweiker, 655 F.2d 401 (D.C. Cir.
1981), another case cited by the Court of Appeals, involved
Medicaid funding. The former two cases are distinguishable
from the present one on their facts and in that they at least deal
with a subject reasonably related to the purpose of the spending
~ highway construction. The last case is totally inapposite.
Participation in the Medicaid program is a voluntary decision
ty ta SS hee het) Fe
DLR 6 LD MBA PORE? A RP nt
te kg
ae
ate!
Panta 31 f eviealbah
ee Wine ees
25
The highway sanction should not have been dis-
missed so lightly. Without placing an exact number on the
potential loss to the Commonwealth and its citizens, the
Court of Appeals could and should have done more. As it
acknowledged, the Commonwealth faces, inter alia, the
loss of major highway funding for non-attainment areas.
While there are exemptions for certain types of projects,
building highways is a long-term, difficult and expensive
process. Loss of highway funding - which means loss of
money paid in the form of federal taxes by citizens of the
Commonwealth - deals a blow to Virginia from which it
may not recover. Highway construction delayed or lost
runs into untold millions of dollars with each passing
year. Plans unmade potentially cannot be remade, cer-
tainly not without increased expense and inordinate ~
delay. Threats to highway safety and inconvenience of
citizens in growing areas of the Commonwealth - those
most directly affected - can reasonably be expected to
result. Moreover, the impact on the economy of the
affected area cannot be readily measured. Such losses
almost certainly are irreparable.
The Court of Appeals disregarded all of these
impacts and justified its conclusion that the highway
sanction is not coercive by stating that the Common-
wealth should have planned better for its anticipated
noncompliance with Title V. 80 F.3d at 882 (App. 27). This
cavalier attitude overlooks the fact that Virginia has been
on the part of each State and failure to do so carries no federal
sanctions. Moreover, Medicaid is a grant program, and the
Commonwealth does not challenge any of the CAA grant
programs.
EE
26
working in good faith for many years with EPA in order
to produce a mutually acceptable Title V program.
Unfortunately, the approach of the Court of Appeals
is not unlike that taken by a number of federal courts
since Nevada v. Skinner that have refused to apply Dole in
any meaningful way. In Skinner, the Ninth Circuit effec-
tively declared that judicial efforts to fashion a test for
coercion as defined in Dole are fruitless.’
It apparently has become somewhat acceptable for
lower federal courts to dismiss a challenge under Dole by
using as partial justification the argument that no federal
court has struck down a federal statute under the Spend-
ing Clause since this Court did so in United States v.
Butler, 297 U.S. 1 (1936). 80 F.3d at 881 (App. 26-27);
Skinner, 884 F.2d at 448; see Virginia Dep't of Educ. v. Riley,
86 F.3d 1337 (4th Cir., 1996), reh’g requested (Aug. 5, 1996).
Where the constitutional balance between federal and
state power is at issue, however, the judiciary must take
on this difficult task. See United States v. Lopez, __ U.S.
__, 115 S.Ct. 1624, 1639 (1995) (Kennedy, J., concurring)
(“[T]he federal balance is too essential a part of. our
14 Because Skinner pre-dates New York, its continuing
validity is questionable. There the Ninth Circuit reasoned that if
Congress has the constitutional authority to force States directly
to comply with a federal directive it should be able to do so
indirectly by withholding funds for failing to comply. 884 F.2d
at 449. Since New York, Congress clearly does not have such
authority.
27
eee ee eee—_e_e_eeeeS ee LL eee
constitutional structure and plays too vital a role in secur-
ing freedom for [the judiciary] to admit inability to inter-
vene when one or the other level of Government has
tipped the scale too far.”)
At least one judge of the Court of Appeals below had
no trouble concluding in another recent case that loss of a
$60 million federal special education grant because of a
dispute involving a handful of students presented a Tenth
Amendment claim of the highest order and met the Dole
test for coercion. See Circuit Judge Luttig dissenting opin-
ion in Riley, 86 F.3d at 1347. Judge Luttig joined the
dissent from the Court of Appeals’ 8-5 refusal to rehear
the present case in banc. App. 34.
The Commonwealth respectfully urges this Court to
revisit the coercion test of Dole and its relation to New
York. If Dole means what it says, then the lower courts
must be directed to apply it consistent with, rather than
in circumvention of, this Court’s other rulings on issues
having implications for relationships among sovereigns
within the federal system. To allow the lower courts, as in
this case, to pay mere lip service to the decision deprives
it of all force and effect and does nothing to guide the
respective sovereigns in attempting to adjust their rela-
tionships within the bounds of the law.
B.
The Condition Imposed on Highway Funding Under the
CAA Is Not Reasonably Related To its Purpose
The Court of Appeals also erred in dismissing out-of-
hand the Commonwealth’s argument that the Spending
Clause is violated where the condition placed on the
28
receipt of federal funds is not related to the federal inter-
est served by the federal spending. See Dole, 483 U.S. at
208. In the Title V context, Congress has directed the
States to enact and enforce a non-voluntary federal regu-
latory program as a condition for receiving federal
monies routinely granted for a purpose unrelated to that
federal program, that purpose being highway construc-
tion.
The condition imposed by the CAA - that States
implement a Title V program for stationary sources of air
pollution — is not reasonably related to the purpose of
highway construction. See Butler, 297 U.S. at 73 (“There is
an obvious difference between a statute stating the condi-
tions upon which moneys shall be expended and one
effective only upon assumption of a contractual obliga-
tion to submit to a regulation which otherwise could not
be enforced.”); Dole, 483 U.S. at 212, 215-18 (O’Connor, J.,
dissenting).
The Court of Appeals simply stated that air quality is
a problem of federal interest and therefore any federal
spending may be conditioned so as not to exacerbate air
pollution. 80 F.3d at 882 (App. 28). As a result, the Court
of Appeals characterized it as “of no consequence that a
highway sanction, which will have the effect of reducing
emissions from mobile pollution sources, is being used to
induce compliance with a portion of the Act designed to
reduce emissions from stationary sources.” Id.15 But it is
1S The Court of Appeals was wrong on all fronts. Factually,
a decrease in highway spending can be demonstrated to increase
emissions from automobiles by reason of increased traffic
congestion. Moreover, Title V is a purely administrative
29
axiomatic that highway construction and the regulation
of industrial air pollution are different program with
different purposes. The pollutants addressed by each are
distinct, with distinct health and environmental conse-
quences, and cannot be interchanged.
More significant, the Court of Appeals ignored the
fact that other portions of the CAA and federal transpor-
tation statutes require that federal highway funds be used
only in conformity with EPA-approved State Implementa-
tion Plans governing mobile pollution sources. Thus, any
federal highway funds returned to the Commonwealth
can be used only on those projects that have received
federal approval from both a transportation and environ-
mental perspective. In short, Congress has tied federal
highway funds to State-adoption of Title V not to further
any federal environmental interest, and not because there
is any relationship between the two programs, but solely
because highway funds represent one of the biggest
weapons in Congress’ arsenal to coerce States into com-
pliance with federal dictates. This approach is even more
troublesome where Congress has the direct power to
implement a federal Title V program in those States that
wish to exercise their Tenth Amendment right not to
regulate on behalf of another sovereign, and, in particu-
lar, not to expand the jurisdiction of their own courts.
The analysis performed by the Court of Appeals
stands in stark contrast to that employed by the
majority of this Court in Lopez, another recent test of
provision of the CAA and will not in itself do anything to reduce
industrial pollution.
30
Congressional power. There this Court rejected the idea
that Congress may assert apparently limitless power
based on sweeping assertions about causal relationships.
Broad assumptions such as these defy careful analysis of
the matter at hand and render the protections afforded to
the States by the Constitution and by decisions such as
Dole and New York illusory.
¢
CONCLUSION
The petition for a writ of certiorari should be
granted.
Respectfully submitted,
COMMONWEALTH OF VIRGINIA
James S. Grimore, III
Attorney General of
Virginia
Davio E. ANDERSON Joun P. Scumrrz, Esquire
Chief Seiad Attorney Grecory S. Wapen, Esquire
Genera THomas Ditence, Esquire
Joun Pau. W , Jn Mayer, Brown & Piatt
Deputy Attorney General 2000 Pennsylvania Avenue,
N.W.
Rocer L. CHAFre Suite 6500
Senior Assistant Attorney Washington, D.C. 20006-1882
General (202) 463-2000
Mary Jo Leucers Of Counsel
Assistant Attorney
General
(Counsel of Record)
900 East Main Street
Richmond, Virginia 23219
(804) 786-2444
App. 1
PUBLISHED
UNITED STATES COURT OF APPEALS
FOR THE FOURTH CIRCUIT
COMMONWEALTH OF VIRGINIA,
Petitioner,
V.
CAROL M. BROWNER,
Administrator, U. S. Environmental
Protection Agency;
ENVIRONMENTAL PROTECTION
AGENCY,
Respondents,
AMERICAN LUNG ASSOCIATION
OF NORTHERN VIRGINIA, AND
AMERICAN LUNG ASSOCIATION
OF VIRGINIA; CLEAN WATER
ACTION; FRIENDS OF THE
RIVERS OF VIRGINIA;
THE JAMES RIVER No. 95-1052
ASSOCIATION; MOUNTAIN
HERITAGE ALLIANCE; VALLEY
CONCERNED CITIZENS;
VIRGINIA CHAPTER OF THE
SIERRA CLUB; VIRGINIA
CITIZEN ACTION; VIRGINIA
CONSORTIUM FOR CLEAN AIR;
VIRGINIA COUNCIL, TROUT
UNLIMITED; ENVIRONMENTAL
DEFENSE FUND,
INCORPORATED; KATHLEEN F.
DERRICOTT; CLIFTON E.
DERRICOTT; ANDRE L. BROWN;
CALEATA JOHNSON; GWEN
HEDGEPATH; AUDUBON
NATURALIST SOCIETY,
Intervenors,
App. 2
VIRGINIA MANUFACTURERS
ASSOCIATION; WASHINGTON
LEGAL FOUNDATION; OGDEN
MARTIN SYSTEMS OF
LANCASTER, INCORPORATED;
OGDEN MARTIN SYSTEMS OF
ALEXANDRIA, INCORPORATED;
NATIONAL INDEPENDENT
ENERGY PRODUCERS; OGDEN
MARTIN SYSTEMS OF
MONTGOMERY, INCORPORATED;
OGDEN MARTIN SYSTEMS OF
FAIRFAX, INCORPORATED;
CHESAPEAKE BAY
FOUNDATION,
Amici Curiae.
On Petition for Review of an Order
of the United States Environmental Protection Agency.
Argued: December 4, 1995
Decided: March 26, 1996
Before MURNAGHAN and MICHAEL, Circuit Judges,
and MICHAEL, Senior United States District Judge for
the Western District of Virginia, sitting by designation.
Petition for review denied by published opinion.
Circuit Judge Michael wrote the opinion, in which
Judge Murnaghan and Senior District Judge Michael
joined.
COUNSEL
ARGUED: Mary Jo Leugers, Assistant Attorney
General, Richmond, Virginia, for Petitioner. David Jay
Kaplan, Environmental Defense Section, Environment
& Natural Resources Division, UNITED STATES
App. 3
DEPARTMENT OF JUSTICE, Washington, D.C., for
Respondents. Katherine E. Slaughter, SOUTHERN
ENVIRONMENTAL LAW CENTER, Charlottesville,
Virginia, for Intervenors. ON BRIEF: James S. Gilmore,
Ill, Attorney General, John Paul Woodley, Jr., Deputy
Attorney General, Roger L. Chaffe, Senior Assistant
Attorney General, John R. Butcher, Assistant Attorney
General, Richmond, Virginia; John P. Schmitz, Thomas
Dilenge, MAYER, BROWN & PLATT, Washington,
D.C., for Petitioner. Lois J. Schiffer, Assistant Attorney
General, Ronald Spritzer, Robin M. Richardson,
Environmental Defense Section, Environment &
Natural Resources Division, UNITED STATES
DEPARTMENT OF JUSTICE, Washington, D.C.;
Michael W. Thrift, Office of General Counsel, UNITED
STATES ENVIRONMENTAL PROTECTION AGENCY,
Washington, D.C.; Cecil A. Rodrigues, Office of
Regional Counsel, UNITED STATES
ENVIRONMENTAL PROTECTION AGENCY,
Philadelphia, Pennsylvania, for Respondents. Deborah
Murray Wassenaar, SOUTHERN ENVIRONMENTAL
LAW CENTER, Charlottesville, Virginia; David S.
Bailey, LAWYERS COMMITTEE FOR CIVIL RIGHTS
UNDER LAW, Washington, D.C., for Intervenors. Carol
C. Raper, Vice President and General Counsel,
VIRGINIA MANUFACTURERS ASSOCIATION,
Richmond, Virginia; George A. Somerville, MAYS &
VALENTINE, Richmond, Virginia, for Amicus Curiae
Virginia Manufacturers Association. Daniel J. Popeo,
David A. Price, WASHINGTON LEGAL
FOUNDATION, Washington, D.C., for Amicus Curiae
Washington Legal Foundation. Deborah E. Jennings,
Michael C. Carter, Norman L. Rave, PIPER &
MARBURY, Baltimore, Maryland, for Amici Curiae
National Independent Energy Producers, et al. Roy A.
Hoagland, Virginia Assistant Director/Staff Attorney,
App. 4
CHESAPEAKE BAY FOUNDATION, INC., Richmond,
Virginia, for Amicus Curiae Chesapeake Bay
Foundation.
OPINION
MICHAEL, Circuit Judge:
The Commonwealth of Virginia petitions for review of
the Environmental Protection Agency’s final action disap-
proving Virginia’s proposed program for issuing air pol-
lution permits. Specifically, Virginia challenges EPA’s
finding that Virginia has failed to comply with Title V of
the 1990 Amendments to the Clean Air Act (sometimes
“CAA” or the “Act”), CAA §§ 501-507, 42 U.S.C.
§§ 7661-7661f, because Virginia’s proposal lacks adequate
provisions for judicial review of the Commonwealth’s
permitting decisions. Virginia also challenges the consti-
tutionality of Title V and its sanctions provisions, CAA
§§ 179(b) & 502(d), 42 U.S.C. §§ 7509(b) & 7661a(d).
According to Virginia, these provisions improperly com-
mandeer the legislative processes of the states, in viola-
tion of the Tenth Amendment and the Spending Clause,
U.S. Const. art. 1 § 8, cl. 1. We have jurisdiction over all of
Virginia’s claims, see CAA § 307(b)(1), 42 U.S.C.
§ 7607(b)(1), and we find them to be without merit.
I.
A.
Because Virginia claims that the EPA has misinterpreted
Title V and that Title V is unconstitutional as well, a brief
discussion of the statute’s structure and purposes is in
order.
App. 5
Title V’s key provision, CAA § 502, 42 U.S.C. § 7661a,
prohibits major stationary sources of air pollution from
operating either without a valid permit or in violation of
the terms of a permit.! The permit is crucial to the imple-
mentation of the Act: it contains, in a single, comprehen-
sive set of documents, all CAA requirements relevant to
the particular polluting source. Clean Air Act Amendments
of 1990: Chafee-Baucus Statement of Senate Managers (Conf.
Rep. No. 952, 101st Cong., 2d Sess.) (“Chafee-Baucus State-
ment”), reprinted in 136 Cong. Rec. $16933, $16983 (daily
ed. Oct. 27, 1990). In a sense, a permit is a source-specific
bible for Clean Air Act compliance.
Title V of the Act contemplates that states will administer
and enforce the permitting program:
[T]he permit program is predicated on the prin-
ciple that the primary responsibility for its day-
to-day administration will rest squarely with
state and local air pollution agencies. While EPA
has an important role of providing guidance and
general oversight, the agency should not unduly
interfere with states’ implementation of the per-
mit program.
Chafee-Baucus Statement at S16983.
States are directed to submit for EPA approval their own
programs for issuing permits. CAA § 502(d)(1), 42 U.S.C.
§ 7661a(d)(1). EPA may not approve a proposed permit
1 A “stationary source” is defined in CAA §§ 112(a)(1),
182(b)(1)(A)(ii)(1), 182(c), 182(d), 182(e), 302(j), & 501(2); 42
U.S.C. §§ 7412(a)(1), 7511a(b)(1)(A)(ii)(), 751 1a(c), 7511a(d),
751la(e), 7602(j), & 7661(2). Stationary sources, such as power
plants and factories, are distinguished from mobile sources,
such as automobiles.
App. 6
program unless it meets certain minimum criteria set out
in CAA § 502(b), 42 U.S.C. § 7661a(b). Among other
things, states must design a standard permit application
form (§ 502(b)(1)), adequately staff and fund the permit
program (§ 502(b)(4)), develop a plan to ensure permit
compliance (§ 502(b)(5)), provide public access to docu-
ments submitted in support of permit applications
(§ 502(b)(8)), and provide for review in state courts of
permitting decisions (§ 502(b)(6)).
If a state fails to submit a permit program, or submits a
permit program that EPA disapproves for failure to com-
ply with CAA § 502(b), the state becomes subject to
sanctions designed to encourage compliance. CAA
§ 502(d), 42 U.S.C. § 7661a(d).2
One sanction deprives states of certain federal highway
funds. CAA § 179(b)(1), 42 U.S.C. § 7509(b)(1). However,
the state loses no funds that would be spent in regions
that are in “attainment” within the meaning of the Act.$
? We discuss the timing of sanctions in greater detail in our
opinion in a related case, Virginia v. United States (Virginia I), No.
95-2229 (4th Cir. Feb. 2, 1996). Sanctions are mandatory, but they
may be imposed earlier than mandated by the statute if EPA
finds, after holding a notice-and-comment rulemaking
proceeding, that early imposition of sanctions is necessary to
encourage compliance. See CAA §§ 502(d) & (i), 42 U.S.C.
§§ 7661a(d) & (i).
° We explain the concepts ot “attainment” and
“nonattainment” in greater detail in Virginia I. In brief, an area is
in nonattainment with respect to a pollutant if levels of that
pollutant in the ambient (breathable) air exceed a threshold
level set by EPA. An ozone nonattainment area, for example, has
what EPA has determined to be a sufficient amount of ozone in
the air to cause health problems.
App. 7
CAA § 179(b)(1)(A), 42 U.S.C. § 7509(b)(1)(A). And, even
within “nonattainment” areas, funds remain available for
highway projects that “resolve a demonstrated safety
problem and likely will result in a significant reduction
in, or avoidance of, accidents.” Id. Finally, federal funds
may be spent on many other types of transportation
projects within nonattainment areas, including:
(i) capital programs for public transit;
(ii) construction or restriction of certain roads
or lanes solely for the use of passenger buses or
high occupancy vehicles;
(iii) planning for requirements for employers
to reduce employee work-trip-related vehicle
emissions;
(iv) highway ramp metering, traffic signaliza-
tion, and related programs that improve traffic
.flow and achieve a net emission reduction;
(v) fringe and transportation corridor parking
facilities serving multiple occupancy vehicle
programs or transit operations;
(vi) programs to limit or restrict vehicle use in
downtown areas or other areas of emission con-
centration particularly during periods of peak
use, through road use charges, tolls, parking
surcharges, or other pricing mechanisms, vehi-
cle restricted zones or periods, or vehicle regis-
tration programs;
(vii) programs for breakdown and accident
scene management, nonrecurring congestion,
and vehicle information systems, to reduce con-
gestion and emissions; and
App. 8
(viii) such other transportation-related pro-
grams as the [EPA] Administrator, in consulta-
tion with the Secretary of Transportation, finds
would improve air quality and would not
encourage single occupancy vehicle capacity. In
considering such measures, the State should
seek to ensure adequate access to downtown,
other commercial, and residential areas, and
avoid increasing or relocating emissions and
congestion rather than reducing them.
CAA § 179(b)(1)(B), 42 U.S.C. § 7509(b)(1)(B).
A second sanction increases the pollution offset require-
ments already imposed on private polluters within ozone
nonattainment areas. Normally, new major stationary
sources of pollution may not be operated within non-
attainment areas (and existing stationary sources may not
be modified if the modification would increase emissions)
unless pollution from other sources is reduced to offset
increased pollution from the new or modified source. In
regions of “marginal” nonattainment with respect to
ozone, 110 tons of old pollution must be eliminated for
every 100 additional tons of new pollution (a ratio of
1.1:1). CAA § 182(a)(4), 42 U.S.C. § 7511a(a)(4). In regions
of “moderate” nonattainment, 115 tons of old pollution
must be eliminated for every additional 100 tons of new
pollution (a ratio of 1.15:1). CAA § 182(b)(5), 42 U.S.C.
§ 751la(b)(5). In regions of “serious,” “severe,” or
“extreme” nonattainment with respect to ozone, 120 tons
of old pollution must be eliminated for every additional
100 tons of new pollution (a ratio of_1.2:1). CAA
§§ 182(c)(10), (d), & (e); 42 U.S.C. § 7511a(c)(10), (d), &
(e). In regions of “severe” and “extreme” nonattainment,
higher ratios are mandated for certain pollutants. See
App. 9
CAA §§ 182(d)(2) & (e)(1); 42 U.S.C. §§ 751la(d)(2) &
(e)(1). The sanction supersedes these normal ratios by
increasing the ratio in all ozone nonattainment areas to
2:1, requiring 200 tons of old pollutants to be eliminated
for every 100 tons of new pollutants allowed. CAA
§ 179(b)(2), 42 U.S.C. § 7509(b)(2). The offset sanction,
therefore, could slow the rate of industrial development
within a noncomplying state.
A third sanction eliminates the state’s ability to manage
its own pollution control regime. If the state does not
gain approval for its permit program, EPA develops and
implements its own Title V permitting program, within
the noncomplying state. CAA § 502(d)(3), 42 U.S.C.
§ 7661a(d)(3). The state is not required to do anything to
assist EPA in this effort; the federal government becomes
wholly responsible.
B.
Virginia submitted a proposed Title V permit program to
EPA on November 12, 1993, and January 14, 1994. EPA
then opened a notice and comment period. EPA pub-
lished notice of its intent to disapprove Virginia’s pro-
posal on June 17, 1994, 59 Fed.Reg. 31183, and Virginia
responded to EPA’s notice. After considering Virginia’s
comments, as well as the comments of others, EPA took
final action disapproving Virginia’s proposed Title V pro-
gram on December 5, 1994. 59 Fed.Reg. 62324.
EPA based its disapproval on five grounds:
(1) the proposed program contained inade-
quate judicial review provisions, in violation of
App. 10
CAA § 502(b)(6) (42 U.S.C. § 7661a(b)(6)) and 40
C.F.R. § 70.4(b)(3)(x) & 70.7(h);
(2) the proposed program would have allowed
certain permits to be issued by default, in viola-
tion of § 505(b)(3) (42 U.S.C. § 7661d(b)(3)) and
40 C.F.R. § 70.8(e);
(3) the regulations that would have imple-
mented the proposed program had expired
without being re-promulgated;
(4) the proposed program did not “require
issuance of permits to the proper universe of
sources required by 40 CFR part 70”; and
(5) the proposed program did not “contain reg-
ulations meeting the requirements of 40 CFR
part 70 to ensure issuance of permits that con-
tain all applicable Federal requirements,” and
did not “correctly delineate provisions only
enforceable by” Virginia.
See id. at 62324-25.
Virginia filed a petition for review in this Court on Janu-
ary 9, 1995.4 Since that date Virginia has revised portions
of its original proposal and now claims that it has cor-
rected defects (2) through (5). EPA has not yet deter-
mined whether those defects have actually been
corrected.
* Virginia simultaneously filed suit, Virginia I, in the district
court for the Eastern District of Virginia. In Virginia I we
affirmed the district court’s decision to dismiss for lack of
subject matter jurisdiction.
App. 11
The claims in Virginia’s petition to us fall into three broad
categories. First, Virginia argues that because it has cor-
rected defects (2) through (5) in its proposed permit
program, we should remand the case to EPA for a new
determination of whether the corrected version complies
with the Act. Second, Virginia argues that EPA’s disap-
proval of the originally proposed permit program was
arbitrary and capricious. Third, Virginia argues that Title
V of the CAA and its sanctions provisions are unconstitu-
tional because the Act represents an attempt by Congress
to coerce Virginia into exercising its sovereign legislative
power. We consider each claim in turn.
Il.
Virginia suggests that we must remand this case to EPA
because four of the five defects in its originally proposed
Title V state permit program have been corrected. We
believe, however, that a remand would be inappropriate.
First, Virginia concedes that EPA properly disapproved
its original submission on the basis of defects (2) through
(5). We may affirm the agency on this basis, and this basis
alone, if the CAA passes constitutional muster. Although
the EPA “Administrator may approve a program [just] to
the extent that the program meets the requirements of”
the Act, she is not required to do so, and she has the
authority to disapprove the entire program on the basis
of one defect. CAA § 502(d)(1), 42 U.S.C. § 7661a(d)(1).
Second, EPA has not yet determined whether Virginia’s
new submission is adequate, because EPA has not com-
pleted the notice and comment rulemaking proceeding
required by CAA § 502(d)(1). And absent any agency
~ App. 12
record, we have no way of knowing whether the new
submission in fact complies with the CAA, as Virginia
claims. See Federal Power Comm'n v. Transcontinental Gas
Pipe Line Corp., 423 U.S. 326, 331-34 (1976) (per curiam);
cf. Virginia Agric. Growers Ass'n v. Donovan, 774 F.2d 89, 92
(4th Cir. 1985) (“the focal point for judicial review should
be the administrative record already in existence, not
some new record made initially in the reviewing court”)
(quoting Camp v. Pitts, 411 U.S. 138, 143 (1973)); Deukme-
jian v. Nuclear Regulatory Comm'n, 751 F.2d 1287, 1325
(D.C. Cir. 1984) (“judicial reliance on an agency’s stated
rationale and findings is central to a harmonious relation-
ship between agency and court”), aff'd in pertinent part
sub. nom. San Luis Obispo Mothers for Peace v. U.S. Nuclear
Regulatory Comm'n, 789 F.2d 26 (D.C. Cir. 1986) (en banc),
cert. denied, 479 U.S. 923 (1986).
A remand would serve no useful purpose here, and
accordingly we reject Virginia’s suggestion.
Il.
Virginia claims that EPA erroneously determined that
Virginia’s permit program contained inadequate judicial
review provisions (defect (1)). EPA’s finding that Virginia
submitted a deficient permit program must be upheld
unless that finding is “arbitrary, capricious, or otherwise
not in accordance with law.” 5 U.S.C. § 706(2)(A). We find
that EPA correctly determined that Virginia’s proposed
judicial review provisions do not comply with the Act.
Therefore, even if EPA had based its disapproval solely
on defect (1), such disapproval would not have been
arbitrary and capricious.
App. 13
A.
CAA § 502(b)(6), 42 U.S.C. § 7661a(b)(6), provides that a
state permit program must contain:
Adequate, streamlined, and reasonable pro-
cedures for expeditiously determining when
applications are complete, for processing such
applications, for public notice, including offer-
ing an opportunity for public comment and a
hearing, and for expeditious review of permit
actions, including applications, renewals, or
revisions, and including an opportunity for judi-
cial review in State court of the final permit action
by the applicant, any person who participated in the
public comment process, and any other person who
could obtain judicial review of that action under
applicable law.
(Emphasis supplied.)
The emphasized portion of this provision is a* ‘ssue here.
A state permit program will be disapproved unless the
state submits a legal opinion stating that the proposed
Title V program allows state court review of permitting
decisions upon the request of “the [permit] applicant, any
person who participated in the public participation pro-
cess ... and any other person who could obtain judicial
review of such actions under State laws.” 40 C.F.R.
§ 70.4(b)(3)(x). EPA interprets the statute and regulation
to require, at a minimum, that states provide judicial
review of permitting decisions to any person who would
have standing under Article III of the United States Con-
stitution. Notice of Proposed Disapproval, 59 Fed. Reg.
31183, 31184 (June 17, 1994).
App. 14
Virginia law grants standing to seek judicial review of
permitting decisions to “[a]ny owner aggrieved by” such
decisions. Va. Code § 10.1-1318(A). This provision satis-
fies CAA § 502(b)(6)’s requirement that the permit “appli-
cant” be allowed to seek judicial review. But § 502(b)(6)
also requires that states grant certain standing rights to
members of the public, and here is where Virginia’s judi-
cial review provision falls short of the mark. Under Vir-
ginia’s provision, a member of the public “who is
aggrieved by a final [permitting decision] who partici-
pated, in person or by submittal of written comments, in
the public comment process” may only seek judicial
review of a permitting decision if he can establish that
(i) [he] has suffered an actual, threatened, or
imminent injury; (ii) such injury is an invasion
of an immediate, legally protected, pecuniary and
substantial interest which is concrete and partic-
ularized; (iii) such injury is fairly traceable to
the [permitting decision] and not the result of
the action of some third party not before the
court; and (iv) such injury will likely be
redressed by a favorable decision of the court.
Va. Code § 10.1-1318(B) (emphasis supplied).
According to EPA, this provision is too restrictive: limit-
ing availability of review to those persons with “pecuni-
ary and substantial” interests violates CAA § 502(b)(6).
We agree with EPA.
App. 15
B.
1.
Virginia argues that the text of CAA § 502(b)(6) does not
require states to slacken their rules of judicial standing at
all.
The critical language to be examined is: “an opportunity
for judicial review in State court of the final permit action
by the applicant, any person who participated in the
public comment process, and any other person who could
obtain judicial review of that action under applicable
law.”
As Virginia reads the statute, the final clause, “who could
obtain judicial review of that action under applicable
[state] law,” modifies all three categories of persons ear-
lier described as being allowed to seek judicial review:
“the applicant,” “any person who participated in the
public comment process,” and “any other person.” Thus,
according to Virginia, § 506(b)(6) requires states to grant
standing to participants in the public comment process
only if those persons would otherwise have standing
under existing state law.
Virginia’s proposed reading is contrary to ordinary prin-
ciples of statutory construction and to the rules of English
usage. The clause, “who could obtain judicial review of
that action under applicable law,” modifies only the
immediately preceding category, “any other person.” An
elementary principle of statutory construction is the “last
antecedent” rule, which holds that ordinarily a clause
modifies only its nearest antecedent. In re Grewe, 4 F.3d
299, 302 (4th Cir. 1993), cert. denied, 114 S. Ct. 1056 (1994).
App. 16
Furthermore, if the last antecedent rule does not apply,
and the clause modifies all three categories, then there
would have been no need for Congress to have included
the first two categories. The statute could have been
written simply to say that standing should be given to
“any person” who complied with state standing rules. A
court should not - and we will not - construe a statute in
a manner that reduces some of its terms to mere sur-
plusage. See Arkansas Best Corp. v. Commissioner, 485 U.S.
212, 218 (1988).
Properly read, the final clause simply allows the states to ,
grant broader standing rights than those otherwise
required under federal law.
This provision ensures that existing provisions
of law governing the availability of review of
final actions on permit applications are in no
way limited, and that interested persons who
arguably are affected by permit decisions are
guaranteed their day in court.
Chafee-Baucus Statement, 136 Cong. Rec. at $169941. In
other words, the clause “who could obtain judicial review
of that action under applicable law” creates a floor of
rights, rather than a ceiling, and ensures that the CAA
does not inadvertently diminish standing rights previ-
ously granted under state laws.
2.
A literal reading of the latter part of § 502(b)(6), then,
would require that a state allow “any person who partici-
pated in the public comment process” to seek judicial
review of permitting decisions. EPA, however, does not
App. 17
require that states go that far in providing for judicial
review. EPA has determined that § 502(b)(6) is satisfied
(and that therefore a state permit program may be
approved) if a state grants standing only to those partici-
pants in the public comment process who would have
Article III standing to sue in federal court.5
This determination is justified by analysis of the opening
portion of § 502(b)(6), which requires that states provide
“[a]dequate, streamlined, and reasonable procedures for
expeditiously” making permitting decisions. The two
parts of the section must be harmonized, and EPA has
done that by creating a safe harbor keyed to Article III
standing.
But Virginia claims that because EPA agrees that
§ 502(b)(6), when read in its entirety, is ambiguous, the
states may propose any Title V program that reasonably
accommodates the statute’s disharmonious provisions.
Virginia claims that because its “pecuniary and substan-
tial interest” requirement is a reasonabie way to resolve
the tension inherent in § 502(b)(6), EPA was arbitrary and
capricious in its decision to reject Virginia’s proposal.
We disagree. EPA’s interpretation, if reasonable, must
take precedence over any interpretation Virginia could
offer or, indeed, even over any alternative interpretation
we could formulate. Chevron, U.S.A., Inc. v. Natural
> For Article III standing purposes, a potential litigant must
show (1) actual or imminent injury that is concrete and
particularized, (2) causal connection between the challenged
conduct and the injury, and (3) likelihood that the injury would
be redressed by favorable judicial action. Lujan v. Defenders of
Wildlife, 112 S. Ct. 2130, 2136 (1992).
App. 18
Resources Defense Council, 467 U.S. 837, 844 (1984). We
defer to EPA’s definition of the bounds of the § 502(b)(6)
safe harbor because “[t]he power of an administrative
agency to administer a congressionally created .. .
program necessarily requires the formulation of policy
and the making of rules to fill any gap left, implicitly or
explicitly, by Congress.” Id. at 843 (quoting Morton v.
Ruiz, 415 U.S. 199, 231 (1974)).
EPA’s interpretation of the judicial review portion of
CAA § 502(b)(6) harmonizes it with the portion that
requires states to provide “[a]dequate, streamlined, and
reasonable procedures.” We find EPA’s importation of
Article III principles to resolve the slight tension within
CAA § 502(b)(6) to be reasonable. The Article III test is
convenient to apply, primarily because a body of national
caselaw interpreting Article III standing requirements
already exists. See, e.g., Sammon v. New Jersey Bd. of Medi-
cal Examiners, 66 F.3d 639, 642 (3d Cir. 1995); Chambers
Medical Technologies v. Bryant, 52 F.3d 1252, 1265 (4th Cir.
1995); Williams v. Lambert, 46 F.3d 1275, 1278 (2d Cir.
1995); Ass’n for Retarded Citizens v. Dallas County Mental
Health & Mental Retardation Ctr. Bd. of Trustees, 19 F.3d
241, 243 (5th Cir. 1994); Adams v. Watson, 10 F.3d 915, 918
(1st Cir. 1993); Banks v. Secretary of Indiana Family and
Social Servs. Admin., 997 F.2d 231, 238 (7th Cir. 1993);
Central Ariz. Water Conservation Dist. v. United States EPA,
990 F.2d 1531, 1537-38 (9th Cir.), cert. denied, 114 S. Ct. 94
(1993). Because EPA’s “answer is based upon a permiss-
ible construction of the statute,” we will follow EPA’s
choice of interpretation. Chevron, 467 U.S. at 843; accord
Monongahela Power Co. v. Reilly, 980 F.2d 272, 278-79 (4th
Cir. 1992).
App. 19
Virginia argues that Chevron deference is inappropriate
because EPA’s area of expertise is the environment, not
jurisdictional rules. See Hi-Craft Clothing Co. v. NLRB, 660
F.2d 910, 914-15 (3d Cir. 1981). Again, we disagree.
“(Cjonsiderable weight should be accorded to an execu-
tive department’s construction of a statutory scheme it is
entrusted to administer.” Chevron, 467 U.S. at 844. Con-
gress has charged EPA with inducing the states to imple-
ment a permitting program that satisfies certain judicial
review requirements, and if Congress has decided that
EPA has sufficient expertise in the area, it is not our place
to say otherwise. See Cass R. Sunstein, Law and Adminis-
tration After Chevron, 90 Colum. L. Rev. 2071, 2097 (1990)
(“an ad hoc inquiry into administrative competence
would be an exceptionally poor way to handle the ques-
tion whether Chevron applies”).
Virginia also claims that Gregory v. Ashcroft, 501 U.S. 452
(1991), mandates a different result. Virginia is again mis-
taken. Gregory simply stands for the proposition that
when congressional intent is unclear, a statute should be
construed to avoid a constitutional question. That princi-
ple has no relevance in this case because here it is mani-
festly clear that Congress specifically intended that the
states conform their judicial standing rules to meet the
§ 502(b)(6) standard. See Association of Community Orgs.
for Reform Now (ACORN) v. Edgar, 56 F.3d 791, 796 (7th
Cir. 1995); United States v. Lot 5, 23 F.3d 359, 362 (11th Cir.
1994), cert. denied, 115 S. Ct. 722 (1995); EEOC v. Massa-
chusetts, 987 F.2d 64, 69 (1st Cir. 1993).
In Gregory the Supreme Court faced the question whether
the Age Discrirnination in Employment Act (ADEA), 29
U.S.C. §§ 621-34, applied to state judges. The ADEA
App. 20
contained no express reference to state courts or judges,
and therefore the Court concluded that the statute did not
apply. If the statute did apply to state judges, the Court
reasoned, then an inquiry into key federalism concerns
would be required. Specifically, could Congress, under
the guise of an antidiscrimination statute, alter the quali-
fications for state judges, or would doing so violate the
Tenth Amendment? The Court held that it would con-
strue the ADEA in a manner that would allow it to avoid
the constitutional question. Because the statute did not
expressly say that it applied to state judges, and because
a difficult constitutional question would have been pre-
sented if the statute did in fact apply to state judges, the
statute was interpreted as not applying to state judges.
The Clean Air Act contains no ambiguity of the kind
present in Gregory. Even if EPA’s interpretation of CAA
§ 502(b)(6) can be said to implicate Tenth Amendment
concerns by intruding upon what Virginia claims to be a
core element of its sovereignty, see IV.A, infra, that inter-
pretation is specifically authorized by the “plain state-
ment” of Congress. Gregory, 501 U.S. at 461. In Gregory,
the question was whether the ADEA applied to the state
judiciary at all. Here, by contrast, Congress intended
CAA § 502(b)(6) to apply to state courts, and Congress
made “its intention unmistakably clear in the language of
the statute.” Atascadero State Hosp. v. Scanlon, 473 U.S. 234,
242 (1985). By its terms, § 502(b)(6) could apply to nothing
but state courts.
Here, EPA resolved the slight tension within § 502(b)(6)
by interpreting the section to require that states, at a
minimum, extend judicial review rights to participants in
App. 21
the state public comment process who satisfy the stan-
dard for Article III standing. This resolution is both
authorized by Congress and reasonable, and therefore we
must reject Virginia’s alternative interpretation.
3.
Virginia also argues that even if the Article III test is
proper, Virginia’s “pecuniary and substantial interest”
requirement satisfies it. Again, we disagree.
A plaintiff need not show “pecuniary” harm to have
Article III standing; injury to health or to aesthetic, envi-
ronmental, or recreational interests will suffice. See, e.g.,
United States v. Students Challenging Regulatory Agency
Procedures (SCRAP), 412 U.S. 669, 686-87 (1973); Sierra
Club v. Morton, 405 U.S. 727, 734 (1972).
In recent cases, Virginia courts have denied standing to
plaintiffs who would have met Article III’s standing
requirements. For example, in Fries v. State Water Control
Bd., 409 S.E.2d 634, 637 (Va. Ct. App. 1991), it was held
that a town lacked standing to seek judicial review of the
decision of the State Water Control Board to grant a
permit, even though the permit allowed a sewage treat-
ment plant to discharge waste directly upstream of the
town. Standing also was denied to individual riparian
landowners. The court held that “an anticipated public
injury” was not “an immediate, pecuniary, and substan-
tial interest” such that standing should be allowed. Id.; see
also Citizens for Clean Air v. Commonwealth, 412 S.E.2d 715,
719-21 (Va. Ct. App. 1991) (because unincorporated asso-
ciation was not an “owner aggrieved” under Virginia law,
association was denied standing to challenge permitting
|
App. 22
decision of State Air Pollution Control Board, even
though association members owned real estate near plant
granted permit, were bothered by foul odors emitted by
plant, and alleged decline in property values); Environ-
mental Defense Fund v. Virginia State Water Control Bd., 404
S.E.2d 728, 731-32 (Va. Ct. App. 1991) (standing denied to
association seeking review of water pollution permit
decision, even though association represented both recre-
ational users of a river and riparian landowners).
Virginia caselaw makes it clear that the “pecuniary and
substantial interest” requirement is more stringent than
Article III’s requirement of concrete and particularized
injury.
4.
Section 502(b)(6)’s requirement of broad availability of
judicial review is necessary to ensure that the required
public comment period serves its proper purpose. The
comment of an ordinary citizen carries more weight if
officials know that the citizen has the power to seek
judicial review of any administrative decision harming
him. EPA recently recognized this principle in another
context:
When citizens are denied the opportunity to
challenge executive decisions in court, their
ability to influence permitting decisions through
other required elements of public participation,
such as through public comments and public
hearings on proposed permits, may be seriously
compromised. If citizens perceive that a state is
not addressing their concerns about [ ] permits
because the citizens have no recourse to an
App. 23
impartial judiciary, that perception also has a
chilling effect on all the remaining- forms of
public participation in the permitting process.
Amendment to Requirements for Authorized State Permit Pro-
grams Under Section 402 of the Clean Water Act, 60 Fed.
Reg. 14588, 14589 (March 17, 1995) (notice of proposed
rulemaking).
a.
Because Virginia’s permit program did not provide the
minimum judicial review rights required under
§ 506(b)(6), it was not arbitrary and capricious for EPA to
disapprove Virginia’s submission.
IV.
Having determined that EPA had a valid reason to disap-
prove Virginia’s permit program, we now examine
whether Title V and its sanctions provisions are constitu-
tional. Virginia claims that Title V and its sanctions provi-
sions are unconstitutional because they impinge upon a
fundamental element of state sovereignty, the state’s right
to articulate its own rules of judicial standing. Even
assuming arguendo the accuracy of Virginia’s assertion
that its standing rules are within the core of its sover-
eignty, we find no constitutional violation because federal
law “may, indeed, be designed to induce state action in
areas that otherwise would be beyond Congress’ regula-
tory authority.” FERC v. Mississippi, 456 U.S. 742, 766
(1982). As we explain below, we believe that if Virginia
chooses to change its rules of judicial standing, it will
App. 24
make the change only because the CAA’s sanctions provi-
sions induce it to do so, not because they coerce it.
A.
We agree that Congress lacks power to impinge upon
“the core of sovereignty retained by the States.” New York
v. United States, 112 S. Ct. 2408, 2419 (1992). We also agree
that an important aspect of a state’s sovereignty is the
administration of its judicial system. See Gregory, 501 U.S.
at 460. Thus, a state cannot be required to create a court
with power to decide federal claims, if no court otherwise
exists. Howlett v. Rose, 496 U.S. 356, 372 (1990). Similarly, a
state may apply neutral venue rules to require that fed-
eral claims be brought in a particular state court. Herb v.
Pitcairn, 324 U.S. 117, 123 (1945), overruled in part on other
grounds by Michigan v. Long, 463 U.S. 1032 (1983). But the
Supremacy Clause compels state judges to apply federal
law, if such law is applicable. U.S. Const. art. VI, cl. 2.
Furthermore, to require an existing state administrative
body to adjudicate a dispute arising under federal law
does not unreasonably interfere with state sovereignty.
FERC, 456 U.S. at 760; see also Testa v. Katt, 330 U.S. 386
(1947) (state court must entertain civil action arising
under federal Emergency Price Control Act); E.A. v. State,
623 P.2d 1210, 1215 n.13 (Alaska, 1981) (state court must
exercise jurisdiction over actions brought pursuant to
federal Indian Child Welfare Act); cf. Mack v. United
States, 66 F.3d 1025, 1029-30 (9th Cir. 1995) (state law
enforcement officials may be required to assist in opera-
tion of federal law enforcement scheme).
App. 25
We need not decide whether judicial standing rules fall
within the core of sovereignty identified in Gregory and
Howlett, supra, because we find that the CAA does not
compel the states to modify their standing rules, it merely
induces them to do so. The CAA is constitutional
because although its sanctions provisions potentially bur-
den the states, those sanctions amount to inducement
rather than “outright coercion.” See New York, 112 S. Ct. at
2423. We examine each sanction separately to explain
how we reach this conclusion. See id. at 2425.
© In its brief and during oral argument Virginia claimed
that CAA § 113, 42 U.S.C. § 7413, exposes the state and its
elected officials to civil and criminal liability for failure to
promulgate a valid state permit program. A careful reading of
this section, however, discloses that it provides for enforcement
of an approved state permit program. Sanctions under § 113 may
not be used to force Virginia to promulgate any state permit
program, and EPA has not proposed invoking § 113 in this case.
Sanctions under this section are available only to redress
“violations of . . . approved permit program under subchapter
[Title] V.” CAA § 113(a)(2), 42 U.S.C. § 7413(a)(2). EPA has not
approved Virginia’s proposed Title V program, so no “approved
permit program” yet exists to trigger any § 113 sanctions against
any Virginia official. In addition, EPA has expressed no
intention to seek § 113 sanctions against Virginia officials in the
future. For these reasons, a constitutional challenge to § 113 is
unripe. Renne v. Geary, 501 U.S. 312, 321-22 (1991). The threat of
such sanctions has not been “felt in a concrete way by” any
Virginia official. Reno v. Catholic Social Servs., Inc., 113 S. Ct.
2485, 2495 (1993) (quoting Abbott Labs. v. Gardner, 387 U.S. 136,
148 (1967)); accord Lujan v. National Wildlife Fed’n, 497 U.S. 871,
891 (1990).
App. 26
B.
Two sources of Congressional power allow use of the
highway sanction. Because the elimination of air pollu-
tion promotes the general welfare, Congress may tie the
award of federal funds to the states’ efforts to eliminate
air pollution. “The Congress shall have Power to lay and
collect Taxes, Duties, Imposts and Excises, to pay the
Debts and provide for the common Defence and general
Welfare of the United States.” U.S. Const. art. I § 8, cl. 1.
Furthermore, the Commerce Clause, U.S. Const. art. I, § 8,
cl. 3, gives Congress the power to regulate “activities
causing air or water pollution, or other environmental
hazards that may have effects in more than one State.”
Hodel v. Virginia Surface Mining & Reclamation Ass’n, 452
U.S. 264, 282 (1981).
Generally, Congress may use the power of the purse to
encourage states to enact particular legislation. New York,
112 S. Ct. at 2423. This power, however, is not limitless.
Exercise of the power to the point of “outright coercion”
violates the Constitution. Id. “[I]n some circumstances the
financial inducement offered by Congress might be so
coercive as to pass the point at which ‘pressure turns into
compulsion.’ ” South Dakota v. Dole, 483 U.S. 203, 211
(1987) (quoting Steward Machine Co. v. Davis, 301 U.S. 548,
590 (1937)).7 Also, it has been suggested that federal
funds may be subject to conditions “only in ways reason-
ably related to the purpose for which the funds are
expended.” South Dakota, 483 U.S. at 213 (O’Connor, J.,
7 In South Dakota the Supreme Court upheld an Act of
Congress that denied a percentage of highway funds to states
that refused to enact a minimum drinking age of 21.
App. 27
dissenting); see also New York, 112 S. Ct. at 2426. No court,
however, has ever struck down a federal statute on
grounds that it exceeded the Spending Power. See Nevada
v. Skinner, 884 F.2d 445, 448 (9th Cir. 1989), cert. denied, 493
U.S. 1070 (1990).
The highway sanction here does not rise to the level of
“outright coercion.” First, a state does not lose any high-
way funds that would be spent in areas of the state that
are in attainment. CAA § 179(b)(1)(A), 42 U.S.C.
§ 7509(b)(1)(A). Second, even within nonattainment areas,
federal highway funds may be spent on projects designed
to promote safety or designed to reduce air pollution.
CAA § 179(b)(1), 42 U.S.C. § 7509(b)(1). More severe
funding restrictions than those at issue here have been
upheld. See, e.g., New York, 112 S. Ct. at 2426-27; Skinner,
supra (virtually all highway funds); Oklahoma v. Schweiker,
655 F.2d 401 (D.C. Cir. 1981) (all Medicaid funds);
Nebraska, Dep’t of Roads v. Tiemann, 510 F.2d 446 (8th Cir.
1975) (broad category of highway funds).
Virginia concedes that it is allowed to spend federal
money on safety projects, on projects that will reduce
pollution, and on projects within areas that are in attain-
ment. The Commonwealth contends, however, that
because it is difficult to shift funds from one transporta-
tion project to another, these exemptions do not reduce
the sanction’s coercive effect. According to Virginia, it
simply lacks the time to reallocate funds away from high-
way projects it has already planned for nonattainment
areas. To this argument we can only say that Title V was
enacted in 1990, and the states have had more than five
years either to comply or to prepare themselves for the
consequences of noncompliance.
App. 28
And contrary to what Virginia claims, the conditions on
spending are reasonably related to the goal of reducing
air pollution. The CAA as a whole is a comprehensive
scheme to cope with the problem of air pollution from all
sources. Congress may ensure that funds it allocates are
not used to exacerbate the overall problem cf air pollu-
tion. It is therefore of no consequence that a highway
sanction, which will have the effect of reducing emissions
from mobile pollution sources, is being used to induce
compliance with a portion of the Act designed to reduce
emissions from stationary sources.
We hold that the highway sanction, CAA § 179(b)(1), is a
valid exercise of the Spending Power. As a valid exercise
of that power, it also comports with the requirements of
the Tenth Amendment. New York, 112 S. Ct. at 2427.
Congress has not overstepped its bounds here.
C.
The offset sanction, CAA § 179(b)(2), 42 U.S.C.
§ 7509(b)(2), which iimits new construction or modifica-
tion of major stationary sources of air pollution, is consti-
tutional because it regulates private pollution sources,
not states.
The burden of the offset sanction falls on private parties.
The more stringent offset requirements will likely make it
more difficult for individual pollution sources (manufac-
turers, utilities, and the like) to upgrade or modify exis-
ting plants and equipment or to open new plants. Thus,
although the sanction may burden some Virginia citizens,
it does not burden Virginia as a governmental unit. For this
reason, the sanction does not violate the principles of
App. 29
federalism embodied in the Tenth Amendment. New York,
112 S. Ct. at 2427 (upholding a sanction because “any
burden caused by a state’s refusal to regulate will fall on”
private citizens); Hodel, 452 U.S. at 288 (harm to citizens
of states does not create Tenth Amendment violation,
absent direct harm to state governmental entities). The
offset sanction is constitutional.
D.
The final sanction, Federal permit program implementa-
tion, CAA § 502(d)(3), 42 U.S.C. § 7661a(d)(3), also is
constitutional. The essence of a Tenth Amendment viola-
tion is that the state is commanded to regulate. Here,
Virginia is not commanded to regulate; the Common-
wealth may choose to do nothing and let the federal
government promulgate and enforce its own permit pro-
gram within Virginia. Because “the full regulatory burden
will be borne by the Federal Government,” the sanction is
constitutional. Hodel, 452 U.S. at 288.
Hodel, in fact, is the mirror image of this case and controls
our decision. In Hodel the federal government first imple-
mented an environmental regulatory regime within each
state but then gave each state the ability to end the
federal program by implementing its own state environ-
mental regulations that met certain criteria. In the present
situation, the federal government gives the states the
chance to enact their own regulations before the federal
plan is imposed. For purposes of constitutional analysis,
we cannot see how it makes a difference whether the
federal plan is imposed first, or whether the states are
given the chance to avoid imposition of the federal plan
App. 30
first. If anything, the CAA’s method - to give the states a
chance first to avoid imposition of any federal plan by
promulgating satisfactory regulations — seems less coer-
cive than the program upheld in Hodel. The CAA simply
“establishes a program of cooperative federalism that
allows the States, within limits established by federal
minimum standards, to enact and administer their own
regulatory programs, structured to meet their own partic-
ular needs.” Id. at 289.
Because Congress may choose to preempt state law com-
pletely, it may also take the less drastic step of allowing
the states the ability to avoid preemption by adopting
and implementing their own plans that sufficiently
address congressional concerns. Id. at 290; Mack, 66 F.3d
at 1029 (“The federal government may offer to preempt
regulation in a given area and permit the states to avoid
preemption if they regulate in a manner acceptable to
Congress.”).
In Maryland v. EPA, 530 F.2d 215 (4th Cir. 1975), vacated
and remanded for consideration of mootness sub nom. EPA v.
Brown, 431 U.S. 99 (1977) (per curiam), this court exam-
ined regulations promulgated under the CAA that on
their face would have directly required Maryland to enact
statutes and to administer an EPA plan. See also District of
Columbia v. Train, 521 F.2d 971, 983 (D.C. Cir. 1975),
vacated and remanded for consideration of mootness sub nom.
EPA v. Brown, 431 U.S. 99 (1977) (per curiam).
The regulations in Maryland provided that “the state of
Maryland shall” establish and implement certain pollu-
tion control programs. 530 F.2d at 219. EPA argued that
the regulations’ use of the word, “shall,” meant that if
a ee eee Se ee
Ie aS ae
PIO ae nee ee
App. 31
Maryland did not comply, EPA could seek to impose civil
and criminal penalties on the state for noncompliance. Id.
at 224. We rejected that proposed interpretation as “aston-
ishing,” id., and said it “would reduce the states to the
puppets of a ventriloquist Congress.” Id. at 226 (quoting
Brown v. EPA, 521 F.2d 827, 839 (9th Cir. 1975), vacated and
remanded for consideration of mootness, 431 U.S. 99 (1977)
(per curiam)). Had we accepted EPA’s proposed inter-
pretation, Maryland’s legislature would have been
directly compelled to regulate, a result that would have
offended the Tenth Amendment. Maryland, 530 F.2d at
224. Instead, we interpreted the regulations as authoriz-
ing EPA to implement a federal pollution control program
directly. Id. at 227-28. This interpretation of the regula-
tions did not offend the Tenth Amendment, even though
Maryland was put under some pressure to pass laws
satisfying federal criteria in order to avoid the Federal
implementation. “Congress may induce a state to act by
offering favors or exacting financial penalties.” Id. at 226.
See also Train, 521 F.2d at 984-85 (this procedure is “quite
unremarkable”). In Maryland we sent Congress and EPA a
signal that they could constitutionally use sanctions such
as those at issue here.
Finally, the CAA’s sanctions provisions maintain unity
between regulation and political accountability. If sanc-
tions are imposed, it will be “the Federal Government
that makes the decision in full view of the public, and it
will be federal officials that suffer the consequences if the
decision turns out to be detrimental or unpopular.” New
York, 112 S. Ct. at 2424. The sanctions provisions are
constitutional.
App. 32
V.
In sum, we conclude (1) that EPA correctly disapproved
Virginia’s proposed State permit program because it did
not satisfy the provisions of the Clean Air Act and (2) that
the sanctions Virginia faces are constitutional. The peti-
tion for review is denied.
DENIED.
3
3
i
App. 33
UNITED STATES COURT OF APPEALS
FOR THE FOURTH CIRCUIT
FILED
July 12, 1996
No. 95-1052
COMMONWEALTH OF VIRGINIA
Petitioner
Vv.
CAROL M. BROWNER, Administrator,
U. S. Environmental Protection Agency;
ENVIRONMENTAL PROTECTION AGENCY;
Respondents
AMERICAN LUNG ASSOCIATION OF NORTHERN
VIRGINIA, AND AMERICAN LUNG ASSOCIATION
OF VIRGINIA; CLEAN WATER ACTION; FRIENDS
OF THE RIVERS OF VIRGINIA; THE JAMES RIVER
ASSOCIATION; MOUNTAIN HERITAGE ALLIANCE;
VALLEY CONCERNED CITIZENS; VIRGINIA CHAPTER
OF THE SIERRA CLUB; VIRGINIA CITIZEN ACTION;
VIRGINIA CONSORTIUM FOR CLEAN AIR; VIRGINIA
COUNCIL, TROUT UNLIMITED; ENVIRONMENTAL
DEFENSE FUND, INCORPORATED; KATHLEEN F.
, DERRICOTT; CLIFTON E. DERRICOTT; ANDRE L.
BROWN; CALEATA JOHNSON; GWEN HEDGEPATH;
AUDUBON NATURALIST SOCIETY
Intervenors
VIRGINIA MANUFACTURERS ASSOCIATION;
WASHINGTON LEGAL FOUNDATION; OGDEN
MARTIN SYSTEMS OF LANCASTER, INCORPORATED;
OGDEN MARTIN SYSTEMS OF ALEXANDRIA,
App. 34
INCORPORATED; NATIONAL INDEPENDENT
ENERGY PRODUCERS; OGDEN MARTIN SYSTEMS
OF MONTGOMERY, INCORPORATED; OGDEN
MARTIN SYSTEMS OF FAIRFAX, INCORPORATED;
CHESAPEAKE BAY FOUNDATION
Amici Curiae
On Petition for Rehearing with Suggestion
for Rehearing In Banc
Petitioner filed a petition for rehearing with sugges-
tion for rehearing in banc.
Judge Murnaghan, Judge Michael, and Judge James
H. Michael, Jr., Senior U. S. District Judge, sitting by
designation, voted to deny the petition for rehearing.
A member of the Court requested a poll on the sug-
gestion for rehearing in banc, and a majority of the judges
voted to deny rehearing in banc. Judges Russell, Widener,
Wilkins, Luttig and Williams voted to rehear the case in
banc, and Chief Judge Wilkinson and Judges Hall, Mur-
naghan, Ervin, Niemeyer, Hamilton, Motz and Michael
voted against rehearing in banc.
The Court denies the petition for rehearing with sug-
gestion for rehearing in banc.
Entered at the direction of Judge Michael for the
Court.
For the Court,
/s/ Bert M. Montague
CLERK
App. 35
TITLE V
42 U.S.C. § 7661 [CAA § 501]
§ 7661. Definitions [CAA § 501]
As used in this subchapter -
(1) Affected source
The term “affected source” shall have the meaning
given such term in subchapter IV-A of this chapter.
(2) Major source
The term “major source” means any stationary source
(or any group of stationary sources located within a
contiguous area and under common control) that is either
of the following:
(A) A major source as defined in section
7412 of this title.
(B) A major stationary source as defined in
section 7602 of this title or part D of subchapter
I of this chapter.
(3) Schedule of compliance
The term “schedule of compliance” means a schedule
of remedial measures, including an enforceable sequence
of actions or operations, leading to compliance with an
applicable implementation plan, emission standard, emis-
sion limitation, or emission prohibition.
App. 36
(4) Permitting authority
The term “permitting authority” means the Adminis-
trator or the air pollution control agency authorized by
the Administrator to carry out a permit program under
this subchapter.
§ 7661a. Permit programs [CAA § 502]
(a) Violations
After the effective date of any permit program
approved or promulgated under this subchapter, it shall
be unlawful for any person to violate any requirement of
a permit issued under this subchapter, or to operate an
affected source (as provided in subchapter IV-A of this
chapter), a major source, any other source (including an
area source) subject to standards or regulations under
section 7411 or 7412 of this title, any other source
required to have a permit under parts C or D of subchap-
ter I of this chapter, or any other stationary source in a
category designated (in whole or in part) by regulations
promulgated by the Administrator (after notice and pub-
lic comment) which shall include a finding setting forth
the basis for such designation, except in compliance with
a permit issued by a permitting authority under this
subchapter. (Nothing in this subsection shall be construed
to alter the applicable requirements of this chapter that a
permit be obtained before construction or modification.)
The Administrator may, in the Administrator’s discretion
and consistent with the applicable provisions of this
RRR MARL BAe: Fae E40
ate
LS AOR OTOL LES ANP ITM SG PRONE Ti
App. 37
chapter, promulgate regulations to exempt one or more
source categories (in whole or in part) from the require-
ments of this subsection if the Administrator finds that
compliance with such requirements is impracticable,
infeasible, or unnecessarily burdensome on such catego-
ries, except that the Administrator may not exempt any
major source from such requirements.
(b) Regulations
The Administrator shall promulgate within 12
months after November 15, 1990 regulations establishing
the minimum elements of a permit program to be admin-
istered by any air pollution control agency. These ele-
ments shall include each of the following:
(1) Requirements for permit applications,
including a standard application form and crite-
ria for determining in a timely fashion the com-
pleteness of applications.
(2) Monitoring and reporting require-
ments.
(3)(A) A requirement under State or local
law or interstate compact that the owner or
operator of all sources subject to the require-
ment to obtain a permit under this subchapter
pay an annual fee, or the equivalent over some
other period, sufficient to cover all reasonable
(direct and indirect) costs required to develop
and administer the permit program require-
ments of this subchapter, including section 7661f
of this title, including the reasonable costs of —
(i) reviewing and acting upon any
application for such a permit,
App. 38
(ii) if the owner or operator receives a
permit for such source, whether before or
after November 15, 1990, implementing and
enforcing the terms and conditions of any
such permit (not including any court costs
or other costs associated with any enforce-
ment action),
(iii) emissions and ambient monitor-
ing,
(iv) preparing generally applicable
regulations, or guidance,
(v) modeling, analyses, and demon-
strations, and
(vi) preparing inventories and _ track-
ing emissions.
(B) The total amount of fees collected by the permit-
ting authority shall conform to the following require-
ments:
(i) The Administrator shall not
approve a program as meeting the require-
ments of this paragraph unless the State
demonstrates that, except as otherwise pro-
vided in subparagraphs (ii) through (v) of
this subparagraph, the program will result
in the collection, in the aggregate, from all
sources subject to subparagraph (A), of an
amount not less than $25 per ton of each
regulated pollutant, or such other amount
as the Administrator may determine ade-
quately reflects the reasonable costs of the
permit program.
(ii) As used in this subparagraph, the
term “regulated pollutant” shall mean (I) a
ee ee
Ne RT Oa So es ee "
SCAT» Sacese Salt ht nthe Sl
App. 39
volatile organic compound; (II) each pollu-
tant regulated under section 7411 or 7412 of
this title; and (III) each pollutant for which a
national primary ambient air quality stan-
dard has been promulgated (except that car-
bon monoxide shall be excluded from this
reference).
(iii) In determining the amiount under
clause (i), the permitting authority is not
required to include any amount of regulated
pollutant emitted by any source in excess of
4,000 tons per year of that regulated pollu-
tant.
(iv) The requirements of clause (i)
shall not apply if the permitting authority
demonstrates that collecting an amount less
than the amount specified under clause (i)
will meet the requirements of subparagraph
(A).
(v) The fee calculated under clause (i)
shall be increased (consistent with the need
to cover the reasonable costs authorized by
subparagraph (A)) in each year beginning
after 1990 by the percentage, if any, by
which the Consumer Price Index for the
most recent calendar year ending before the
beginning of such year exceeds the Con-
sumer Price Index for the calendar year
1989. For purposes of this clause -
(I) the Consumer Price Index for
any calendar year is the average of the
Consumer Price Index for all-urban
consumers published by the Depart-
ment of Labor, as of the close of the 12-
month period ending on August 31 of
each calendar year, and
App. 40
(II) the revision of the Consumer
Price Index which is most consistent
with the Consumer Price Index for cal-
endar year 1989 shall be used.
(C)(i) If the Administrator determines, under sub-
section (d) of this section, that the fee provisions of the
operating permit program do not meet the requirements
of this paragraph, or if the Administrator makes a deter-
mination, under subsection (i) of this section, that the
permitting authority is not adequately administering or
enforcing an approved fee program, the Administrator
may, in addition to taking any other action authorized
under this subchapter, collect reasonable fees from the
sources identified under subparagraph (A). Such fees
shall be designed solely to cover the Administrator’s
costs of administering the provisions of the permit pro-
gram promulgated by the Administrator.
(ii) Any source that fails to pay fees lawfully
imposed by the Administrator under this subparagraph
shall pay a penalty of 50 percent of the fee amount, plus
interest on the fee amount computed in accordance with
section 6621(a)(2) of Title 26 (relating to computation of
interest on underpayment of Federal taxes).
(iii) Any fees, penalties, and interest collected
under this subparagraph shall be deposited in a special
fund in the United States Treasury for licensing and other
services, which thereafter shall be available for appro-
priation, to remain available until expended, subject to
appropriation, to carry out the Agency’s activities for
which the fees were collected. Any fee required to be
collected by a State, local, or interstate agency under this
subsection shall be utilized solely to cover all reasonable
App. 41
(direct and indirect) costs required to support the permit
program as set forth in subparagraph (A).
(4) Requirements for adequate personnel and fund-
ing to administer the program.
(5) A requirement that the permitting authority
have adequate authority to:
(A) issue permits and assure compliance
by all sources required to have a permit under
this title with each applicable standard, regula-
tion or requirement under this Act;
(B) issue permits for a fixed term, not to
exceed 5 years;
(C) assure that upon issuance or renewal
permits incorporate emission limitations and
other requirements in an applicable implemen-
tation plan;
(D) terminate, modify, or revoke and reis-
sue permits for cause;
(E) enforce permits, permit fee require-
ments, and the requirement to obtain a permit,
including authority to recover civil penalties in
a maximum amount of not less than $10,000 per
day for each violation, and provide appropriate
criminal penalties; and
(F) assure that no permit will be issued if
the Administrator objects to its issuance in a
timely manner under this subchapter.
£ (6) Adequate, streamlined, and reasonable pro-
i cedures for expeditiously determining when applications
are complete, for processing such applications, for public
é notice, including offering an opportunity for public com-
E ment and a hearing, and for expeditious review or permit
App. 42
actions, including applications, renewals, or revisions,
and including an opportunity for judicial review in State
court of the final permit action by the applicant, any
person who participated in the public comment process,
and any other person who could obtain judicial review of
that action under applicable law.
(7) To ensure against unreasonable delay by the
permitting authority, adequate authority and procedures
to provide that a failure of such permitting authority to
act on a permit application or permit renewal application
(in accordance with the time periods specified in section
7661b of this title or, as appropriate, subchapter IV-A of
this chapter) shall be treated as a final permit action
solely for purposes of obtaining judicial review in State
court of an action brought by any person referred to in
paragraph (6) to require that action be taken by the
permitting authority on such application without addi-
tional delay. .
(8) Authority, and reasonable procedures consistent
with the need for expeditious action by the permitting
authority on permit applications and related matters, to
make available to the public any permit application, com-
pliance plan, permit, and monitoring or compliance
report under section 7661b(e) of this title, subject to the
provisions of section 7414(c) of this title.
(9) A requirement that the permitting authority, in
the case of permits with a term of 3 or more years for
raajor sources, shall require revisions to the permit to
incorporate applicable standards and regulations promul-
gated under this chapter after the issuance of such per-
mit. Such revisions shall occur as expeditiously as
App. 43
practicable and consistent with the procedures estab-
lished under paragraph (6) but not later than 18 months
after the promulgation of such standards and regulations.
No such revision shall be required if the effective date of
the standards or regulations is a date after the expiration
of the permit term. Such permit revision shall be treated
as a permit renewal if it complies with the requirements
of this subchapter regarding renewals.
(10) Provisions to allow changes within a permitted
facility (or one operating pursuant to section 7661b(d) of
this title) without requiring a permit revision, if the
changes are not modifications under any provision of
subchapter I of this chapter and the changes do not
exceed the emissions allowable under the permit
(whether expressed therein as a rate of emissions or in
terms of total emission: Provided, That the facility pro-
vides the Administrator and the permitting authority
with written notification in advance of the proposed
changes which shall be a minimum of 7 days, unless the
permitting authority provides in its regulations a differ-
ent timeframe for emergencies.
{c) Single permit
A single permit may be issued for a facility with
multiple sources.
(d) Submission and approval
(1) Not later than 3 years after November 15, 1990,
the Governor of each State shall develop and submit to
the Administrator a permit program under State or local
App. 44
law or under an interstate compact meeting the require-
ments of this subchapter. In addition, the Governor shall
submit a legal opinion from the attorney general (or the
attorney for those State air pollution control agencies that
have independent legal counsel), or from the chief legal
officer of an interstate agency, that the laws of the State,
locality, or the interstate compact provide adequate
authority to carry out the program. Not later than 1 year
after receiving a program, and after notice and oppor-
tunity for public comment, the Administrator shall
approve or disapprove such program, in whole or in part.
The Administrator may approve a program to the extent
that the program meets the requirements of this chapter,
including the regulations issued under subsection (b) of
this section. If the program is disapproved, in whole or in
part, the Administrator shall notify the Governor of any
revisions or modifications necessary to obtain approval.
The Governor shall revise and resubmit the program for
review under this section within 180 days after receiving
notification.
(2)(A) If the Governor does not submit a program as
required under paragraph (1) or if the Administrator
disapproves a program submitted by the Governor under
paragraph (1), in whole or in part, the Administrator may,
prior to the expiration of the 18-month period referred to
in subparagraph (B), in the Administrator’s discretion,
apply any of the sanctions specified in section 7509(b) of
this title.
(B) If the Governor does not submit a program as
required under paragraph (1), or if the Administrator
disapproves any such program submitted by the Gover-
nor under paragraph (1), in whole or in part, 18 months
App. 45
after the date required for such submittal or the date of
such disapproval, as the case may be, the Administrator
shall apply sanctions under section 7509(b) of this title in
the same manner and subject to the same deadlines and
other conditions as are applicable in the case of a deter-
mination, disapproval, or finding under section 7509(a) of
this title.
(C) The sanctions under section 7509(b)(2) of this
title shall not apply pursuant to this paragraph in any
area unless the failure to submit or the disapproval
referred to in subparagraph (A) or (B) relates to an air
pollutant for which such area has been designated a
nonattainment area (as defined in part D of subchapter |
of this chapter).
(3) If a program meeting the requirements of this
subchapter has not been approved in whole for any State,
the Administrator shall, 2 years after the date required
for submission of such a program under paragraph (1),
promulgate, administer, and enforce a program under
this subchapter for that State.
(e) Suspension
The Administrator shall suspend the issuance of per-
mits promptly upon publication of notice of approval of a
permit program under this section, but may, in such
notice, retain jurisdiction over permits that have been
federally issued, but for which the administrative or judi-
cial review process is not complete. The Administrator
shall continue to administer and enforce federally issued
permits under this subchapter until they are replaced by
a permit issued by a permitting program. Nothing in this
App. 46
subsection should be construed to limit the Administra-
tor’s ability to enforce permits issued by a State.
(f) Prohibition
No partial permit program shall be approved unless,
at a minimum, it applies, and ensures compliance with,
this subchapter and each of the following:
(1) All requirements established under
subchapter IV-A of this chapter applicable to
“affected sources”.
(2) All requirements established under
section 7412 of this title applicable to “major
sources”, “area sources”, and “new sources”.
(3) All requirements of subchapter I of this
chapter (other than section 7412 of this title)
applicable to sources required to have a permit
under this subchapter. Approval of a partial
program shall not relieve the State of its obliga-
tion to submit a complete program, nor from the
application of any sanctions under this chapter
for failure to submit an approvalable permit
program.
Approval of a partial program shall not relieve the State
of its obligation to submit a complete program, nor from
the application of any sanctions under this chapter for
failure to submit an approvable permit program.
(g) Interim approval
If a program (including a partial permit program)
submitted under this subchapter substantially meets the
App. 47
requirements of this subchapter, but is not fully approv-
able, the Administrator may by rule grant the program
interim approval. In the notice of final rulemaking, the
Administrator shall specify the changes that must be
made before the program can receive full approval. An
interim approval under this subsection shall expire on a
date set by the Administrator not later than 2 years after
such approval, and may not be renewed. For the period
of any such interim approval, the provisions of subsec-
tion (d)(2) of this section, and the obligation of the
Administrator to promulgate a program under this sub-
chapter for the State pursuant to subsection (d)(3) of this
section, shall be suspended. Such provisions and such
obligation of the Administrator shall apply after the expi-
ration of such interim approval.
(h) Effective date
The effective date of a permit program, or partial or
interim program, approved under this subchapter, shall
be the effective date of approval by the Administrator.
The effective date of a permit program, or partial permit
program, promulgated by the Administrator shall be the
date of promulgation.
(i) Administration and enforcement
(1) Whenever the Administrator makes a deter-
mination that a permitting authority is not adequately
administering and enforcing a program, or portion
thereof, in accordance with the requirements of this sub-
chapter, the Administrator shall provide notice to the
State and may, prior to the expiration of the 18-month
App. 48
period referred to in paragraph (2), in the Administra-
tor’s discretion, apply any of the sanctions specified in
section 7509(b) of this title.
(2) Whenever the Administrator makes a determina-
tion that a permitting authority is not adequately adminis-
tering and enforcing a program, or portion thereof, in
accordance with the requirements of this subchapter, 18
months after the date of the notice under paragraph (1),
the Administrator shall apply the sanctions under section
7509(b) of this title in the same manner and subject to the
same deadlines and other conditions as are applicable in
the case of a determination, disapproval, or finding under
section 7509(a) of this title.
(3) The sanctions under section 7509(b)(2) of this
title shall not apply pursuant to this subsection in any
area unless the failure to adequately enforce and adminis-
ter the program relates to an air pollutant for which such
area has been designated a nonattainment area.
(4) Whenever the Administrator has made a finding
under paragraph (1) with respect to any State, unless the
State has corrected such deficiency within 18 months
after the date of such finding, the Administrator shall, 2
years after the date of such finding, promulgate, adminis-
ter, and enforce a program under this subchapter for that
State. Nothing in this paragraph shall be construed to
affect the validity of a program which has been approved
under this subchapter or the authority of any permitting
authority acting under such program until such time as
such program is promulgated by the Administrator under
this paragraph.
App. 49
§ 7661b. Permit applications [CAA § 503]
(a) Applicable date
Any source specified in section 7661a(a) of this title
shall become subject to a permit program, and required to
have a permit, on the later of the following dates -
(1) the effective date of a permit program
or partial or interim permit program applicable
to the source; or
(2) the date such source becomes subject to
section 7661a(a) of this title.
(b) Compliance plan
(1) The regulations required by section 7661a(b) of
this title shall include a requirement that the applicant
submit with the permit application a compliance plan
describing how the source will comply with all applicable
requixcments under this chapter. The compliance plan
shall include a schedule of compliance, and a schedule
under which the permittee will submit progress reports
to the permitting authority no less frequently than every
6 months.
(2) The regulations shall further require the permit-
tee to periodically (but no less frequently than annually)
certify that the facility is in compliance with any applica-
ble requirements of the permit, and to promptly report
any deviations from permit requirements to the permit-
ting authority.
App. 50
(c) Deadline
Any person required to have a permit shall, not later
than 12 months after the date on which the source
becomes subject to a permit program approved or pro-
mulgated under this subchapter, or such earlier date as
the permitting authority may establish, submit to the
permitting authority a compliance plan and an applica-
tion for a permit signed by a responsible official, who
shall certify the accuracy of the information submitted.
The permitting authority shall approve or disapprove a
completed application (consistent with the procedures
established under this subchapter for consideration of
such applications), and shall issue or deny the permit,
within 18 months after the date of receipt thereof, except
that the permitting authority shall establish a phased
schedule for acting on permit applications submitted
within the first full year after the effective date of a
permit program (or a partial or interim program). Any
such schedule shall assure that at least one-third of such
permits will be acted on by such authority annually over
a period of not to exceed 3 years after such effective date.
Such authority shall establish reasonable procedures to
prioritize such approval or disapproval actions in the
case of applications for construction or modification
under the applicable requirements of this chapter.
(d) Timely and complete applications
Except for sources required to have a permit before
construction or modification under the applicable
requirements of this chapter, if an applicant has submit-
ted a timely and complete application for a permit
App. 51
required by this subchapter (including renewals), but
final action has not been taken on such application, the
source’s failure to have a permit shall not be a violation
of this chapter, unless the delay in final action was due to
the failure of the applicant timely to submit information
required or requested to process the application. No
source required to have a permit under this subchapter
shall be in violation of section 7661a(a) of this title before
the date on which the source is required to submit an
application under subsection (c) of this section.
(e) Copies; availability
A copy of each permit application, compliance plan
(including the schedule of compliance), emissions or
compliance monitoring report, certification, and each per-
mit issued under this subchapter, shall be available to the
public. If an applicant or permittee is required to submit
information entitled to protection from disclosure under
section 7414(c) of this title, the applicant or permittee
may submit such information separately. The require-
ments of section 7414(c) of this title shall apply to such
information. The contents of a permit shall not be entitled
to protection under section 7414(c) of this title.
App. 52
§ 7661c. Permit requirements and conditions [CAA
§ 504]
(a) Conditions
Each permit issued under this subchapter shall
include enforceable emission limitations and standards, a
schedule of compliance, a requirement that the permittee
submit to the permitting authority, no less often than
every 6 months, the results of any required monitoring,
and such other conditions as are necessary to assure
compliance with applicable requirements of this chapter,
including the requirements of the applicable implementa-
tion plan.
(b) Monitoring and analysis
The Administrator may by rule prescribe procedures
and methods for determining compliance and for mon-
itoring and analysis of pollutants regulated under this
Act, but continuous emissions monitoring need not be
required if alternative methods are available that provide
sufficiently reliable and timely information for determin-
ing compliance. Nothing in this subsection shall be con-
strued to affect any continuous emissions monitoring
requirement of subchapter IV-A of this chapter, or where
required elsewhere in this chapter.
(c) Inspection, entry, monitoring, certification, and
reporting
Each permit issued under this subchapter shall set
forth inspection, entry, monitoring, compliance certifica-
tion, and reporting requirements to assure compliance
App. 53
with the permit terms and conditions. Such monitoring
and reporting requirements shall conform to any applica-
ble regulation under subsection (b) of this section. Any
report required to be submitted by a permit issued to a
corporation under this subchapter shall be signed by a
responsible corporate official, who shall certify its accu-
racy.
(d) General permits
The permitting authority may, after notice and
opportunity for public hearing, issue a general permit
covering numerous similar sources. Any general permit
shall comply with all requirements applicable to permits
under this subchapter. No source covered by a general
permit shall thereby be relieved from the obligation to
file an application under section 7661b of this title.
(e) Temporary sources
The permitting authority may issue a single permit
authorizing emissions from similar operations at multiple
temporary locations. No such permit shall be issued
unless it includes conditions that will assure compliance
with all the requirements of this chapter at all authorized
locations, including, but not limited to, ambient stan-
dards and compliance with any applicable increment or
visibility requirements under part C of subchapter I of
this chapter. Any such permit shall in addition require
the owner or operator to notify the permitting authority
in advance of each change in location. The permitting
authority may require a separate permit fee for opera-
tions at each location.
App. 54
(f) Permit shield
Compliance with a permit issued in accordance with
this subchapter shall be deemed compliance with section
7661a of this title. Except as otherwise provided by the
Administrator by rule, the permit may also provide the
compliance with the permit shall be deemed compliance
with other applicable provisions of this chapter that
relate to the permittee if -
(1) the permit includes the applicable
requirements of such provisions, or
(2) the permitting authority in acting on
the permit application makes a determination
relating to the permittee that such other provi-
sions (which shall be referred to in such deter-
mination) are not applicable and the permit
includes the determination or a concise sum-
mary thereof.
-—_
Nothing in the preceding sentence shall alter or affect the
provisions of section 7603 of this title, including the
authority of the Administrator under that section.
§ 7661d. Notification to administrator and contiguous
States [CAA § 505]
(a) Transmission and notice
(1) Each permitting authority -
(A) shall transmit to the Administrator a
copy of each permit application (and any appli-
cation for a permit modification or renewal) or
App. 55
such portion thereof, including any compliance
plan, as the Administrator may require to effec-
tively review the application and otherwise to
carry out the Administrator’s responsibilities
under this chapter, and
(B) shall provide to the Administrator a
copy of each permit proposed to be issued and
issued as a final permit.
(2) The permitting authority shall notify all States —
(A) whose air quality may be affected and
that are contiguous to the State in which the
emission originates, or
(B) that are within 50 miles of the source,
of each permit application or proposed permit
forwarded to the Administrator under this sec-
tion, and shall provide an opportunity for such
States to submit written recommendations
respecting the issuance of the permit and its
terms and conditions. If any part of those rec-
ommendations are not accepted by the permit-
ting authority, such authority shall notify the
State submitting the recommendations and the
Administrator in writing of its failure to accept
those recommendations and the reasons there-
for.
(b) Objection by EPA
(1) If any permit contains provisions that are deter-
mined by the administrator as not in compliance with the
applicable requirements of this chapter, including the
requirements of an applicable implementation plan, the
Administrator shall, in accordance with this subsection,
object to its issuance. The permitting authority shall
App. 56
respond in writing if the Administrator (A) within 45
days after receiving a copy of the proposed permit under
subsection (a)(1), or (B) of this section within 45 days
after receiving notification under subsection (a)(2) of this
section, objects in writing to its issuance as not in compli-
ance with such requirements. With the objection, the
Administrator shall provide a statement of the reasons
for the objection. A copy of the objection and statement
shall be provided to the applicant.
(2) If the Administrator does not object in writing to
the issuance of a permit pursuant to paragraph (1), any
person may petition the Administrator within 60 days
after the expiration of the 45-day review period specified
in paragraph (1) to take such action. A copy of such
petition sha!l be provided to the permitting authority and
the applicant by the petitioner. The petition shall be
based only on objections to the permit that were raised
with reasonable specificity during the public comment
period provided by the permitting agency (unless the
petitioner demonstrates in the petition to the Administra-
tor that it was impracticable to raise such objections
within such period or unless the grounds for such objec-
tion arose after such period). The petition shall identify
all such objections. If the permit has been issued by the
permitting agency, such petition shall not postpone the
effectiveness of the permit. The Administrator shall grant
or deny such petition within 60 days after the petition is
filed. The Administrator shall issue an objection within
such period if the petitioner demonstrates to the Admin-
istrator that the permit is not in compliance with the
requirements of this chapter, including the requirements
of the applicable implementation plan. Any denial of
App. 57
such petition shall be subject to judicial review under
section 7607 of this title. The administrator shall include
in regulations under this subchapter provisions to imple-
ment this paragraph. The Administrator may not delegate
the requirements of this paragraph.
(3) Upon receipt of an objection by the Administra-
tor under this subsection, the permitting authority may
not issue the permit unless it is revised and issued in
accordance with subsection (c) of this section. If the per-
mitting authority has issued a permit prior to receipt of
an objection by the Administrator under paragraph (2) of
this subsection, the Administrator shall modify, termi-
nate, or revoke such permit and the permitting authority
may thereafter only issue a revised permit in accordance
with subsection (c) of this section.
(c) Issuance or denial
If the permitting authority fails, within 90 days after
the date of an objection under subsection (b) of this
section, to submit a permit revised to meet the objection,
the Administrator shall issue or deny the permit in accor-
dance with the requirements of this subchapter. No objec-
tion shall be subject to judicial review until the
Administrator takes final action to issue or deny a permit
under this subsection.
(d) Waiver of notification requirements
(1) The Administrator may waive the requirements
of subsections (a) and (b) of this section at the time of
approval of a permit program under this subchapter for
App. 58
any category (including any class, type, or size within
such category) of sources covered by the program other
than major sources.
(2) The Administrator may, by regulation, establish
categories of sources (including any class, type, or size
within such category) to which the requirements of sub-
sections (a) and (b) of this section shall not apply. The
preceding sentence shall not apply to major sources.
(3) The Administrator may exclude from any
waiver under this subsection notification under subsec-
tion (a)(2) of this section. Any waiver granted under this
subsection may be revoked or modified by the Adminis-
trator by rule.
(e) Refusal of permitting authority to terminate, mod-
ify, or revoke and reissue
If the Administrator finds that cause exists to termi-
nate, modify, or revoke and reissue a permit under this
subchapter, the Administrator shall notify the permitting
authority and the source of the Administrator’s finding.
The permitting authority shall, within 90 days after
receipt of such notification, forward to the Administrator
under this section a proposed determination of termina-
tion, modification, or revocation and reissuance, as
appropriate. The Administrator may extend such 90 day
period for an additional 90 days if the Administrator
finds that a new or revised permit application is neces-
sary, or that the permitting authority must require the
permittee to submit additional information. The Adminis-
trator may review such proposed determination under
the provisions of subsections (a) and (b) of this section. If
App. 59
the permitting authority fails to submit the required pro-
posed determination, or if the Administrator objects and
the permitting authority fails to resolve the objection
within 90 days, the administrator may, after notice and in
accordance with fair and reasonable procedures, termi-
nate, modify, or revoke and reissue the permit.
§ 7661e. Other authorities [CAA § 506]
(a) In general
Nothing in this subchapter shall prevent a State, or
interstate permitting authority, from establishing addi-
tional permitting requirements not inconsistent with this
chapter.
(b) Permits implementing acid rain provisions
The provisions of this subchapter, including provi-
sions regarding schedules for submission and approval or
disapproval of permit applications, shall apply to permits
implementing the requirements of subchapter IV-A of this
chapter except as modified by that subchapter.
App. 60
§ 7661f. Small business stationary source technical and
environmental compliance assistance program
[CAA § 507]
(a) Plan revisions
Consistent with sections 7410 and 7412 of this title,
each State shall, after reasonable notice and public hear-
ings, adopt and submit to the Administrator as part of the
State implementation plan for such State or as a revision
to such State implementation plan under section 7410 of
this title, plans for establishing a small business station-
ary source technical and environmental compliance assis-
tance program. Such submission shall be made within 24
months after November 15, 1990. The Administrator shall
approve such program if it includes each of the following:
(1) Adequate mechanisms for developing,
collecting, and coordinating information con-
cerning compliance methods and technologies
for small business stationary sources, and pro-
grams to encourage lawful cooperation among
such sources and other persons to further com-
pliance with this chapter.
(2) Adequate mechanisms for assisting
small business stationary sources with pollution
prevention and accidental release detection and
prevention, including providing information
concerning alternative technologies, process
changes, products, and methods of operation
that help reduce air pollution.
(3) A designated State office within the
relevant State agency to serve as ombudsman
for small business stationary sources in connec-
tion with the implementation of this chapter.
App. 61
(4) A compliance assistance program for
smail business stationary sources which assists
small business stationary sources in determining
applicable requirements and in receiving per-
mits under this chapter in a timely and efficient
manner.
(5) Adequate mechanisms to assure that
small business stationary sources receive notice
of their rights under this Act in such manner
and form as to assure reasonably adequate time
for such sources to evaluate compliance
methods and any relevant or applicable pro-
posed or final regulation or standard issued
under this chapter. -
(6) Adequate mechanisms for informing
small business stationary sources of their obliga-
tions under this chapter, including mechanisms
for referring such sources to qualified auditors
or, at the option of the State, for providing
audits of the operations of such sources to deter-
mine compliance with this chapter.
(7) Procedures for consideration of
requests from a small business stationary source
for modification of -
(A) any work practice or technological
method of compliance, or
(B) the schedule of milestones for
implementing such work practice: or
method of compliance preceding any appli-
cable compliance date,
based on the technological and financial capa-
bility of any such small business stationary
source. No such modification may be granted
unless it is in compliance with the applicable
requirements of this chapter, including the
App. 62
requirements of the applicable implementation
plan. Where such applicable requirements are
set forth in Federal regulations, only modifica-
tions authorized in such regulations may be
allowed.
(b) Program
The Administrator shall establish within 9 months
after November 15, 1990 a small business stationary
source technical and environmental compliance assis-
tance program. Such program shall -
(1) assist the States in the development of
the program required under subsection (a) of
this section (relating to assistance for small busi-
ness stationary sources);
(2) issue guidance for the use of the States
in the implementation of these programs that
includes alternative control technologies and
pollution prevention methods applicable to
small business stationary sources; and
(3) provide for implementation of the pro-
gram provisions required under subsection
(a)(4) of this section in any State that fails to
submit such a program under that subsection.
(c) Eligibility
(1) Except as provided in paragraphs (2) and (3), for
purposes of this section, the term “small business station-
ary source” means a stationary source that -
(A) is owned or operated by a person that
employs 100 or fewer individuals,
App. 63
(B) is a small business concern as defined
in the Small Business Act [42 U.S.C.A. § 631 et
seq.];
(C) is not a major Stationary source;
(D) does not emit 50 tons or more per year
of any regulated pollutant; and
(E) emits less than 75 tons per year of all
regulated pollutants.
(2) Upon petition by a source, the State may, after
notice and opportunity for public comment, include as a
small business stationary source for Purposes of this sec-
tion any stationary source which does not meet the crite-
ria of subparagraphs (C), (D), or (E) of paragraph (1) but
which does not emit more than 100 tons per year of all
regulated pollutants.
(3)(A) The administrator, in consultation with the
Administrator of the Small Business Administration and
after providing notice and Opportunity for public com-
ment, may exclude from the small business stationary
source definition under this section any category or sub-
category of sources that the Administrator determines to
have sufficient technical and financial capabilities to meet
the requirements of this chapter without the application
of this subsection.
(B) The State, in consultation with the Administra-
tor and the Administrator of the Small Business Adminis-
tration and after providing notice and opportunity for
public hearing, may exclude from the small business
Stationary source definition under this section any cate-
gory or subcategory of sources that the State determines
to have sufficient technical and financial capabilities to
App. 64
meet the requirements of this chapter without the appli-
cation of this subsection.
(d) Monitoring
The Administrator shall direct the Agency’s Office of
Small and Disadvantaged Business Utilization through
the Small Business Ombudsman (hereinafter in this sec-
tion referred to as the “Ombudsman”) to monitor the
small business stationary source technical and environ-
mental compliance assistance program under this section.
In carrying out such monitoring activities, the Ombuds-
man shall -
(1) render advisory opinions on the overall
effectiveness of the Small Business Stationary
Source Technical and Environmental Compli-
ance Assistance Program, difficulties encoun-
tered, and degree and severity of enforcement;
(2) make periodic reports to the Congress
on the compliance of the Small Business Station-
ary Source Technical and Environmental Com-
pliance Assistance Program with the
requirements of the Paperwork Reduction Act
[44 U.S.C.A. § 3501 et seq.], the Regulatory Flex-
ibility Act [5 U.S.C.A. § 601 et seq.], and the
Equal Access to Justice Act;
(3) review information to be issued by the
Small Business Stationary Source Technical and
Environmental Compliance Assistance Program
for small business stationary sources to ensure
that the information is understandable by the
layperson; and
App. 65
(4) have the Small Business Stationary
Source Technical and Environmental Compli-
ance Assistance Program serve as the secretariat
for the development and dissemination of such
reports and advisory opinions.
(e) Compliance advisory panel
(1) There shall be created a Compliance Advisory
Panel (hereinafter referred to as the “Panel”) on the State
level of not less than 7 individuals. This Panel shall -
(A) render advisory opinions concerning
the effectiveness of the small business stationary
source technical and environmental compliance
assistance program, difficulties encountered,
and degree and severity of enforcement;
(B) make periodic reports to the Adminis-
trator concerning the compliance of the State
Small Business Stationary Source Technical and
Environmental Compliance Assistance Program
with the requirements of the Paperwork Reduc-
tion Act [44 U.S.C.A. § 3501 et seq.], the Regula-
tory Flexibility Act [5 U.S.C.A. § 601 et seq.],
and the Equal Access to Justice Act;
(C) review information for small business
stationary sources to assure such information is
understandable by the layperson; and
(D) have the Small Business Stationary
Source Technical and Environmental Compli-
ance Assistance Program serve as the secretariat
for the development and dissemination of such
reports and advisory opinions.
App. 66
(2) The Panel shall consist of -
(A) 2 members, who are not owners, or
representatives of owners, of small business sta-
tionary sources, selected by the Governor to
represent the general public;
(B) 2 members selected by the State legis-
lature who are owners, or who represent
owners, of small business stationary sources (1
member each by the majority and minority lead-
ership of the lower house, or in the case of a
unicameral State legislature, 2 members each
shall be selected by the majority leadership and
the minority leadership, respectively, of such
legislature, and subparagraph (C) shall not
apply);
(C) 2 members selected by the State legis-
lature who are owners, or who represent
owners, of small business stationary sources (1
member each by the majority and minority lead-
ership of the upper house, or the equivalent
State entity); and
(D) 1 member selected by the head of the
department or agency of the State responsible
for air pollution permit programs to represent
that agency.
(f) Fees
The State (or the Administrator) may reduce any fee
required under this chapter to take into account the
financial resources of small business stationary sources.
App. 67
(g) Continuous emission monitors
In developing regulations and CTGs under this chap-
ter that contain continuous emission monitoring require-
ments, the Administrator, consistent with the
requirements of this chapter, before applying such
requirements to small business stationary sources, shall
consider the necessity and appropriateness of such
requirements for such sources. Nothing in this subsection
shall affect the applicability of subchapter IV-A of this
chapter provisions relating to continuous emissions mon-
itoring.
(h) Control technique guidelines
The Administrator shall consider, consistent with the
requirements of this chapter, the size, type, and technical
capabilities of small business stationary sources (and
sources which are eligible under subsection (c)(2) of this
section to be treated as small business stationary sources)
in developing CTGs applicable to such sources under this
chapter.
App. 68
§ 7413. Federal enforcement [CAA § 113]
(a) In general
(1) Order to comply with SIP
Whenever, on the basis of any information available
to the Administrator, the Administrator finds that any
person has violated or is in violation of any requirement
or prohibition of an applicable implementation plan or
permit, the Administrator shall notify the person and the
State in which the plan applies of such finding. At any
time after the expiration of 30 days following the date on
which such notice of a violation is issued, the Adminis-
trator may, without regard to the period of violation
(subject to section 2462 of Title 28) -
(A) issue an order requiring such person
to comply with the requirements of prohibitions
of such plan or permit,
(B) issue an administrative penalty order
in accordance with subsection (d) of this section,
or
(C) bring a civil action in accordance with
subsection (b) of this section.
(2) State failure to enforce SIP or permit program
Whenever, on the basis of information available to
the Administrator, the Administrator finds that violations
of an applicable implementation plan or an approved
permit program under subchapter V of this chapter are so
widespread that such violations appear to result from a
failure of the State in which the plan or permit program
applies to enforce the plan or permit program effectively,
the Administrator shall so notify the State. In the case of a
_ App. 69
permit program, the notice shall be made in accordance
with subchapter V of this chapter. If the Administrator
finds such failure extends beyond the 30th day after such
notice (90 days in the case of such permit program), the
Administrator shall give public notice of such finding.
During the period beginning with such public notice and
ending when such State satisfies the Administrator that it
will enforce such plan or permit program (hereafter
referred to in this section as “period of federally assumed
enforcement”), the Administrator may enforce any
requirement or prohibition of such plan or permit pro-
gram with respect to any person by -
(A) issuing an order requiring such person
to comply with such requirement or prohibition,
(B) issuing an administrative penalty
order in accordance with subsection (d) of this
section, or
(C) bringing a civil action in accordance
with subsection (b) of this section.
(3) EPA enforcement of other requirements
Except for a requirement or prohibition enforceable
under the preceding provisions of this subsection, when-
ever, on the basis of any information available to the
Administrator, the Administrator finds that any person
has violated, or is in violation of, any other requirement
or prohibition of this subchapter, section 7603 of this title,
subchapter IV-A of this chapter, subchapter V of this
chapter, or subchapter VI of this chapter, including, but
not limited to, a requirement or prohibition of any rule,
plan, order, waiver, or permit promulgated, issued, or
App. 70
approved under those provisions or titles, or for the
payment of any fee owed to the United States under this
chapter (other than subchapter II of this chapter), the
Administrator may -
(A) issue an administrative penalty order
in accordance with subsectio
This text is long and has been trimmed here. Open the source document for the complete record.
This is a copy of a public record, reproduced as it was published. It is not legal advice, and it may not be the version a court would rely on. Check the official source before you cite it.