Petition for Writ of Certiorari — Bianchi v. Perry

Supreme Court brief1996

Ask Donna

What actually matters in this document.

Text

or ae

Supreme Court,

U.S,

D

No. NOV 29 1995

CLERK

IN THE ;

SUPREME COURT OF THE UNITED STATES

OCTOBER TERM, 1995

M. BIANCHI OF CALIFORNIA,

PETITIONER

Vv.

WILLIAM J. PERRY, SECRETARY OF DEFENSE,

RESPONDENT.

PETITION FOR WRIT OF CERTIORARI

TO THE UNITED STATES COURT

OF APPEALS FOR THE FEDERAL CIRCUIT

PETITION FOR WRIT OF CERTIORARI

Robert A. Brunette

4443 Chevy Chase Drive

La Canada Flintridge, CA 91011

(818) 790-0956

Attorney for Petitioner

M. BIANCHI OF CALIFORNIA

QUESTIONS PRESENTED FOR REVIEW

1. Whether it is in the public interest to strongly incentivize future

defense contractors to submit cost saving Value Engineering Change Proposals

(VECPs) under future contracts, by paying a fair, contractually agreed to

portion of initial cost savings to Petitioner from his military garment

fabrication suggestions which have saved the government over $1.5 billion

to date (as uncontested to by the sovernment at trial).

2. Whether the U.S. government-drafted contract Value Engineering

Incentive (VEI) clause should be liberally interpreted to carry out the mutual

intent of the parties, as testified to under oath, that the government would

share cost savings 50-50 (over a three year royalty period) with the Petitioner

on all future affected end-item procurements which used his VECP

suggestions.

3. Whether these important and farreaching questions of federal law

concerning the standard VEI clause used in every Government contract should

be settled by the Supreme Court rather than the U.S. Court of Appeals for the

Federal Circuit, which recently held (contrary to the language of the clause)

to severely limit VECP royalties to future purchases of the same end items as

purchased in the contract under which the VECP was submitted.

Opinions Below ..---- +++ 7°" bes v deed ae br eeeeenrnnpees*" ]

ceannenaits Oh PUMNOD «ous cen 0 8 FON EETR PSST |

Government Regulations TE OS ei ds, lah aia l

secniamnanih af GSEs ca Uo ete die U9 CON 2

Reasons For Granting den Pe. isn soo ndaw CROMER Ee IE 7

1.

Conclusion

The Value Engineering Incentive (VEI) Clause Will No Longer Provide

Contractors With An Incentive To Submit VECPs To The Government

If It Is Interpreted So Narrowly As To Negate The Government Stated

Purposes Of The Clause And A Reasonable Reading Of The Royalty

Sharing Provisions Of The Clause... ccscccccceresesneeere’ 8

A Liberal Interpretation of the VEI Clause’s Royalty Sharing Provisions

Will Benefit The Government And Makes Sense..----+s+0 7°" 10

The Supply Contract VEI Clause Literally Contemplates Royalties For

“Concurrent” and “Future” Contracts Which Occur After Performance

Of The “Instant” Contract Has Been Completed, And Should Be Treated

Differently Than The Construction Contract VEI Clause..------ 11

Under the Cardinal Rule of Contract Interpretation a Contractor's

VEI Clause Should Be Uniformly Interpreted To Carry Out The

Mutual Intent Of The Parties. The MBOC Interlining Decision

Threatens That Principle For Government Contractors ------: 12

MBOC Submitted Uncontradicted And Overwhelming Proof Into

Evidence At The Trial That VECP No. 2181 Was Accepted By The

Government, The Specification Was Changed To Incorporate

MBOC’s VECP Non-Woven Fusible Interlining Suggestion, And

That Other Contractors Did, In Fact, Implement MBOC’s Suggestion

On “Future” COMMCts. ..-.scccresernnereer ces e8E o 14

eee Se ene nn aa

Appendix: Page

A. Opinion of U.S. Court of Appeals for the Federal Circuit

B. Opinion of the U.S. Armed Services Board of Contract Appeals 24

C. Order On Rehearing, U.S. Court of Appeals, Federal Circuit .. 6]

D. Judgment, U.S. Court of Appeals, Federal Circuit

E. Armed Services Procurement IS Sa eee 66

F. Memorandum of U.S. Army R&D Center (Natick, MA), Oct.26,1979

(Roy Roth, Chief Fiber & Fabric Technology Branch) ....... 78

TABLE OF AUTHORITIES

Cases: Page

AID Request for Decision, B-210103, 83-2 CPD 9116 (1983) ........-- 12

BE Goodrich Co. v. United States, 398 F.2d 843 (Ct.Cl. 1968) .......-. 11

Gulf Apparel Corp., ASBCA No. 27784, 89-2 BCA $21,735 (1989)... 8,11

John J. Kirlin, Inc. v. United States, 827 F.2d 1538 (Fed. Cir. 1987). . 2,8,9,11

Julius Goldman's Egg City v. United States, 697 F.2d 1051

(Fed. Cir. 1983) 0... .. 2 cece cere cece cece eee cece eeeeerenesees 12,13

M. Bianchi of California, ASBCA No. 36518, 93-2 BCA §25,801 (1993),

aff'd mem. CAFC No. 93-1402 (Feb. 16, 1994)......--.ee eee eeeee 3,5,8

M. Bianchi of California, ASBCA Nos. 37029 and 37071, 93-1 BCA $25,309

(July 31, 1992) vacated 31 F.3d 1163 (Fed. Cir. 1994) .......--.---: 2,3,8

M. Bianchi of California, ASBCA Nos.37395 et al., 94-1 BCA 926,417

(Sept. 30, 1993), affirmed 61 F.3d 920 (Fed. Cir. 1995) .....-.----- 1,3,5,8

Northeastern Mfg. & Sales, Inc., ASBCA No. 38307, 90-1 BCA

922,562 (1990)... 0. ee ere ccceecccccerecscreerecerererscesers 11

Philco-Ford Corp., ASBCA No. 16197, 73-1 BCA 49917 (1973) ....-.. 1]

Randolph Engineering Co., ASBCA No. 4872, 58-2 BCA 92053 (1958) ..... 12

State of Arizona v. United States, 575 F.2d 855 (Ct.Cl. EE a kawyevs oes 12

Thanet Corp. v. United States, 591 F.2d 629 ee, er 12

Umpqua River Navigation Co., ENGBCA No. 3881, 78-1 BCA

913,051 (1978)... cece cere ccc cccecccvcncccseeecressceeceees 1]

W.R. Johnson, Inc., ASBCA Nos. 40251 et al., 91-3 BCA

WDA 1T2 CIDP). wo cc cccccccncvrevenccccavecsessserenssaveres 1]

Statutes: Page

28 U.S.C. § 1254(1) Courts of Appeal; Certiorari: Certified Question ..... l

41 U.S.C. § 605 Decision by Contracting Officers; Review ............. 3

41 U.S.C. § 606 Contractor's Right of Appeal to Boards of Contract Appeal .... 3

41 U.S.C. § 607 Agency Boards of Contract PE Cen dbcanetearieoe. 3

Regulations:

ASPR § 1-1703.1 Acquisition Savings ............................. l

ASPR § 1-1706 VEI Sharing Arrangements ...................... 1,1]

Pir | FARA VET NR ani 5 5 hiss Sook Be cee l

ASPR § 7-602.50 Value Engineering Incentive - Construction .......... 1]

Secondary Authorities:

J. Gabig & C. Cook, A Guide To Interpreting Contracts, 23 NCMA Journal, No.

bb cecneah MELE ET ee Oa nD 13

S. Williston, A Treatise on the Law of Contracts, § 618 (3d ed je 12

D. Fulghum, Aviation Week & Space Technology 76 (November 6, 1995) .. 7

BRIEFING PAPERS (January 1994) .............................. 8

2 Steiger, Federal Contract Management, DE ey ee 1]

Il Nash & Cibinic, Federal Procurement Law 1194 (3d ed.1980) ...... 2,11

CCH, Government Contract Reports, Jom Dl: Sen ee 1]

36 The Government Contractor, eee ee eee 9

R. Nash, VALUE ENGINEERING: Another Illusory Promise?, 9 THE NASH

& CIBINIC REPORT, No. 3 §20 (March ET OT a OOO Rae eae 10

M. Clancy & V. Antonocci, view: i

ircui ions, 24 Public Contract Law Journal,

areca hes, SR ES OI EE Ch SD ROT Hie 9

IN THE

SUPREME COURT OF THE UNITED STATES

OCTOBER TERM, 1995

M. BIANCHI OF CALIFORNIA,

PETITIONER

v

WILLIAM J. PERRY, SECRETARY OF DEFENSE,

RESPONDENT.

PETITION FOR WRIT OF CERTIORARI

TO THE UNITED STATES COURT

OF APPEALS FOR THE FEDERAL CIRCUIT

M. BIANCHI OF CALIFORNIA, the Petitioner herein, respectfully prays

that a writ of certiorari issue to review the judgment of the United States

Court of Appeals for the Federal Circuit, entered in the above-entitled case

on July 21, 1995.

OPINIONS BELOW |

The July 21, 1995 opinion of the U.S. Court of Appeals for the Federal

Circuit, whose judgment is herein sought to be reviewed, is unpublished

(except as to notice of affirmance at 61 F.3d 920), and is reprinted in the

attached Appendix A to this Petition, at p. 17. The prior opinion of the U.S.

Armed Services Board of Contract Appeals, entered September 30, 1993, is

reported at 94-1 BCA 926,417, at page 131,405; and is reprinted in the

attached Appendix B to this Petition, at p. 24.

STATEMENT OF JURISDICTION

The judgment of the Court of Appeals was entered on July 21, 1995.

The jurisdiction of this Court is invoked pursuant to title 28, U.S.C. § 1254(1).

GOVERNMENT REGULATIONS INVOLVED

This case involves the following, government Value Engineering Incentive

(VEI) regulations in the Armed Services Procurement Regulation (ASPR),

as superseded by the Defense Acquisition Regulation (DAR), and currently

the Federal Acquisition Regulation (FAR): ASPR § 1-1703.1 and .2 (entitled

“Acquisition Savings” and “Collateral Savings”, respectively); ASPR Clause

7-104.44, subparagraph (e) (entitled “Sharing”); and ASPR 1-1706,

promulgated by Defense Acquisition Circular (DAC) #76-26, which identifies

the “Sharing Arrangements” for all affected end items for supply and services

contracts and for construction contracts. These regulations are reprinted in

pertinent part in Appendix E, at p. 66.

l

eae

VX

STATEMENT OF THE CASE

1. Background

The Value Engineering Incentive (VEI) clause is a provision common to

all government contracts. The Department of Defense (DoD) pioneered value

engineering in 1961 through regulatory policy and clauses, which were revised

in 1964, 1967, 1974 and 1977.' The DoD attempted to provide sufficient

incentive to induce supply and services contractors to submit cost savings

ideas, called Value Engineering Change Proposals (VECPs), to the DoD by

promising to pay the contractor 50% of the government's cost savings (for an

initial 3 year royalty period) for its use of essentially the same item (i.e., the

VECP suggestion) in all “affected” end items in instant, concurrent and future

contracts of the procuring activity. The government keeps all cost savings

beyond the 3 year royalty period. Engineering development or low rate initial

production contracts (such as a “production test” or “limited production”

contract), use a future royalty cost sharing period which is the highest 36

consecutive months of planned government production when the VECP is

accepted.

The VEI Clause was quite literally intended to strongly incentivize

contractors to submit cost savings ideas to the DoD. However, when it comes

to actually compensating the submitter of a VECP Suggestion once its

received, the government is often tempted to hold down awards by setting up

two hurdles which tend to prevent the submitter from receiving a reasonable

reward...or any reward at all, as in this case.

First, the government agency can simply hold up review or approval or

implementation of the VECP until after the submitter’s “instant” contract is

fully paid for and closed out...and the contractual relationship has ended.?

Secondly, even if the VECP is accepted and implemented into the instant

contract, the procuring agency (or the Federal courts) can narrowly interpret the

language of the VEI Clause so as to only allow VECP royalties on concurrent or

future contracts for the “the same” military garment as initially supplied by the

submitter. They deny any reward for hundreds of thousands of other “affected

end-item” garments purchased by the government on future contracts which utilize

the very same VECP idea.

The “net” result is an extremely disenchanted and disincentivized

contractor who is not about to submit another cost savings idea to the DoD.

This results in exactly the opposite result than the drafters of the VEI Clause

intended.

' II Nash & Cibinic, Federal Procurement Law 1194 (3d ed. 1980)

* John J. Kirlin, Ine, v. United States, 827 F.2d 1538,1541 (Fed.Cir.1987); and M. Bianchi

of California v, Perry, 31 F.3d 1163, 1167-68 (Fed.Cir.1994).

2

ee

The Federal Circuit has recently established this narrow interpretation,

which is contrary to the weight of lower court ASBCA case precedents which

urge a liberal interpretation favoring contractors so as to maximize future

VECP submissions. This is an important question of first impression which

the Supreme Court has never addressed, and is too important to leave with

the Federal Circuit.

2. The Bianchi VECPs

M. BIANCHI OF CALIFORNIA (MBOC), is a sole proprietorship. In

1979 and 1980 MBOC was competitively awarded three contracts by the

DLA’s Defense Personnel Support Center, in Philadelphia, PA (DPSC) for

the production of U.S. military garments in various amounts. MBOC’s first

contract was for 43,000 Navy enlisted men’s raincoats, the second contract

was for a production “test” run of 26,250 Air Force women’s pantsuit coats,

and the third contract was for “limited” production of 125,240 Army men’s

all weather coats.

MBOC was informed by the DPSC of their VEI Program even before he

bid on these contracts, and each contract contained the VE] clause (identified

in their Master Contract Terms as the JO9 Clause). He subsequently submitted

eight VECP’s, five of which are the subject of this appeal, all of which were

denied any sharing of cost savings by the DPSC. MBOC submitted claims

for all of these VECPs which DPSC failed to respond to, such that in 1988

MBOC appealed them to the Armed Services Board of Contract Appeals

(ASBCA) under the jurisdiction of 41 U.S.C., § § 605(b), 606, and 607. The

ASBCA severed the appeals into three VECP categories for hearings:

(a) The Stitching claim (VECP 8680), for about $6 million, which eventually

resulted in an ASBCA award of $58,613.03, plus interest.’

(b) The Boxes claims (VECPs | 180 and 8780), for about $30 million, for

which the ASBCA denied any award, and which the Federal Circuit vacated

and remanded to the ASBCA*‘; and

(c) The Interlining. Gimp Thread and Label claims (VECPs 1280, 1380,

2181, 2880, and 3380) for about $207 million, for which the ASBCA denied

any award, and the Federal Circuit affirmed’, and is the subject of this Petition.

This appeal involves the third category of VECP claims. Three of the

VECPs (3380, 1280 and 2181) suggested changing expensive woven, fusible

interlining (in collars, cuffs, etc.) of military garments for a new European

style Pellon #SG4 13/#8325 series nonwoven fusible interlining, which could

> M_ Bianchi of Califomia, ASBCA No. 36518, 93-2 BCA 25,801 (Feb.10,1993),

aff'd mem CAFC No. 93-1402 (Feb.16, 1994)

‘ M Bianchi of California, ASBCA Nos. 37029 & 37071, 93-1 BCA $25,309 (July

31,1992), vacated 31 F.3d 1163 (Aug.10,1994)

SM _ Bianchi of California, ASBCA Nos. 37395 et al., 94-1 BCA {26,417

(September.30, 1993), affirmed 61 F.3d 920(July 21,1995)

3 ,

be fused to the military garment via Pellon’s new “point seal” process, saving

substantial labor and material costs per garment, as well as collateral storage

and handling costs.

This suggestion was repeatedly submitted by MBOC (on all three

contracts) at a time when the government's fusible interlining program was

at an absolute “standstill” (on October 26, 1979). Appendix F, at p.78, contains

a government memorandum that confirms this fact.

Samples of Mr. Bianchi’s new Pellon interlining fabric were tested at

the U.S. Army Research & Development Center, Natick, MA from July 1979

(on the Navy garment contract) through written acceptance of the same Pellon

interlining suggestion (VECP 2181) on March 31,1981, and incorporation

into the third MBOC contract as a change to the manufacturing interlining

component specification for the Army’s all weather coat.

At the ASBCA Hearing on April 20-23,1992 MBOC submitted 41

changed U.S. military garment specifications into evidence (without

government objection, or subsequent contradiction), 28 of which now require

“mandatory use” of nonwoven fusible interlining components (i.e., Pellon

SG#413/#8325 or equivalent), and 13 which allow nonwoven fusible

interlinings as an alternate component.

Another idea (VECP 1380) suggested substituting inexpensive cotton

V-T-280 button thread for silk thread around the gimp of buttonholes for the

Air Force’s pantsuit coats. This VECP was also expressly accepted by DPSC

on May 20, 1980 and November 3, 1980 in contract changes to the garment

specification. At the ASBCA Hearing on April 20-23,1992 MBOC submitted

32 changed U.S. military garment specifications into evidence (again without

government objection, or subsequent contradiction) all of which now require

cotton V-T-280 button thread as a “mandatory requirement”.

A third idea (VECP 2880) suggested substituting one garment label which

combined size and identification information (previously included on two

labels) on the Air Force’s garment. This suggestion was denied by the DPSC

onApril 2, 1980. However, the DPSC constructively accepted this suggestion.

At the ASBCA Hearing during April 20-23,1992 MBOC submitted 13

changed U.S. military garment specifications into evidence (without

government objection, or subsequent contradiction), 7 of which require

“mandatory” use of MBOC’s suggestion.

MBOC asked the ASBCA for concurrent and future contract “acquisition”

savings and “collateral” savings on all affected U.S. military end-items

wherever the VECPs were used on buttonholes and interlinings, and wherever

separate labels were combined, and that required the above changed

specifications. During the ASBCA Hearing on April 21-23,1992 the cost

quantum savings were demonstrated by MBOC via uncontradicted testimony

of three expert witnesses who authenticated one hundred (100) separate

4

volumes of evidence concerning DPSC’s future contract procurements and

cost savings data, calculations and reports, which in total cumulated to be

about 15 feet thick. The government was simply overwhelmed and did not,

in fact, contest any of MBOC’s quantum evidence, it simply contested

MBOC’s entitlement to any cost savings under its interpretation of the

language of the contracts’ JO9 Value Engineering Clause. That is a fact.

Government counsel even stated that they would beat MBOC on the

entitlement issue, not the quantum of damages issue.

MBOC experts testified as to engineering, labor savings and extended

life cycles for each “affected” end-item specification. MBOC also submitted

uncontradicted evidence of the procurement history of each “affected” end-

item garment (and its underlying specification) over the applicable royalty

period. This evidence included voluminous back-up documentation obtained

by government computer data analysis of two databases (called “Haystack”)

which provided MBOC’s experts with information on DLA military garment

contracts for each “affected” end-item specification from as far back as 1980

through the Hearing in 1992. The ASBCA had previously found this database

analysis to be a completely satisfactory, and a fair method for MBOC to

identify quantities of “affected” end-item specifications in his first Hearing

on the Stitching appeal.°

Uncontradicted proof submitted into evidence by MBOC at the ASBCA

Hearing demonstrated that BIANCHI’s interlining VECP suggestion alone

generated over $350 Million in acquisition and collateral savings over the

initial 3 year royalty period. This resulted in an uncontested interlining

quantum claim of $176,825,130.00.’ The subsequent 10 year period has

been “royalty free” to the government, and should have generated an additional

$1.1 Billion or more of additional savings...a little over $1.5 Billion of total

savings to date.

At the ASBCA Hearing the government introduced two witnesses which

strongly supported MBOC on his entitlement to these royalties. Mr. Bruce

A. Snigger, Senior Textile Technologist at the Natick, MA test lab, testified

on April 28,1992 that the government tested MBOC’s new Pellon nonwoven

fusible interlining samples and that they exhibited “unique properties...that

would perform as [DPSC] wanted it to”, and he wouldn't have accepted VECP

2181 otherwise.

Further, Ms. Susan Lynn Caso, DPSC’s Value Engineering Specialist

(who was present as the government’s consultant during the entire 9 day

trial) testified on April 27, 1992 that when a component...such as “buttons,

threads, cloth, zippers, slide fasteners...” were changed as a part of an accepted

* M._ Bianchi of California, supra note 3, at pages 128,403 and 129,405

’ M. Bianchi of California, supra note 5, at page 131,417.

5

VECP and it is used in an affected end-item garment (other than in the instant

contract), then the contractor would receive royalties on the use of his VECP

“component specification” in all affected “end-item specifications”.

This testimony was in harmonious agreement with Mr. Bianchi’s trial

testimony concerning DPSC’s Standard JO9 VEI Clause...i.e., that MBOC

would be compensated for its interlining and thread component VECP

Suggestions, once approved by the DPSC, which are used in all affected end-

item garments procured by DPSC on future contracts within the royalty period.

This was also identical to Ms. Caso’s testimony on March 1, 1991 in the

earlier ASBCA Hearing in MBOC’s Stitching claim.

Nevertheless, the ASBCA rejected MBOC’s claims. holding as a matter

of law that the doctrine of constructive acceptance does not apply to three

VECP claims (3380, 1280, 2880), and that even though VECP 2181 was

accepted by the DPSC it wasn’t “implemented” in the instant contract SO as

to have a unit cost reduction (under the instant contract) to apply to concurrent

or future contract savings. Therefore, the ASBCA erroneously concluded

that there is no legal basis for MBOC to recover future contract Savings

(contrary to the language of the VEI clause).

Further, the ASBCA rejected the fact that MBOC had submitted “new”

interlining suggestions (VECPs 1280, 3380 and 2181), even though internal

DPSC and the Natick, MA laboratory documents and government testimony

conclusively established otherwise. DPSC had “accepted” VECP 2181 asa change

to the interlining specification because it was new, unique and it worked.

Incredibly, the ASBCA also held that the record shows “no evidence” of

any changed military specifications, nor cost savings... regardless of MBOC’s

unchallenged submission of days of expert testimony and 100 volumes of

cost data, analysis and reports that proved to the contrary.

The U.S. Court of Appeals for the Federal Circuit affirmed the ASBCA

on July 21, 1995, stating that there was no constructive acceptance by DPSC

of VECPs 3380, 1280 and 2880. It also narrowly interpreted the JO9 VEI

Clause to mean that MBOC could only recover for the use of the VECP 2181

nonwoven, fusible interlining on future DPSC contracts purchasing essentially

the same [end] item garment (ie., the same Army all weather coats)...but that

since no contractor ever implemented VECP 2181 on future contracts, no

royalties were due MBOC. This finding was incorrect, and the entire record

proved it.

The Federal Circuit declined to address MBOC’s VECP 1380 (cotton

gimp) appeal by completely ignoring it in its July 21st Decision.

REASONS FOR GRANTING THE PETITION

Petitioner MBOC was a seasoned commercial garment manufacturer in

1979. He was recruited by his local Long Beach, CA Congressman to enter

into the government arena after Mr. Bianchi made a speech to local

businessmen and government personnel. He was told that DPSC had no

major supplier for uniforms West of the Mississippi River. He brought with

him a competitive eagerness, and a certain sense of patriotism...plus valuable

ideas from his commercial experience.

He quickly visited DPSC in Philadeiphia and was informed of their VEI

Program. They told him if he submitted VECPs, and they were used by the

Government that he would share in the cost savings. DPSC used examples.

If he suggested a new inexpensive type of uniform “button” then, MBOC

would share in all savings from its use on all types of uniforms that DPSC

buys. Another example was “black dye”. If MBOC submitted a better, cheaper

dye, then wherever it was used he'd share in cost savings. A strong incentive

to submit VECPs to be sure. :

MBOC took the government’s words to heart. He bid, and won, a DLA

contract for a Navy enlisted men’s raincoats in rather quick fashion in the

summer of 1979. MBOC immediately applied for a VECP suggestion for

replacing the specification’s collar, sleeve and facings with a new Pellon

SG#413 nonwoven, fusible “interlining” that used a point seal fusing process

developed and patented for the commercial industry by the Pellon Corporation

in West Germany. It had never been used anywhere in the United States. He

submitted Pellon fabric samples for testing with the VECP.

He submitted the same suggestion four more times over the next 15

months on his initial Navy garment contract, and also on two additional

competitively awarded DLA contracts for Air Force and Army garments.

DPSC thoroughly tested the new interlining at its Natick, MA laboratory

during that period and finally approved his fifth interlining VECP (No. 2181)

on March 31, 1981...over 20 months after the suggestion was first submitted

by MBOC.

That exceptional nonwoven, fusible interlining suggestion has reaped a

phenomenal cost savings for the U.S. Government since it was formally

implemented by DPSC into MBOC’s contract. The government saved over

$350 million in the first 3 year (royalty) use period...and over $1.5 billion to

date. This is the equivalent to eight new C-17 airlifter aircraft.

Wasn’t this precisely what the VEI Program was intended for?

However, there is a dark side of the MBOC story. MBOC hasn’t been

paid for his suggestion.

* — D. Fulghum, Aviation Week & Space Technology 76 (Nov.6, 1995)

7

As surely as I write this Petition, and as you read it, the outcome of

MBOC’s 15 year quest for a reasonable reward will have an important impact

on the VEI Program for the entire defense industry and all government cost

savings incentive programs.

The MBOC trilogy’ of VEI cases are being closely followed by the defense

industry in periodical articles and timely commentary. The Federal Circuit first

established a restrictive case precedent on the VEI Clause in 1987.° Its three

subsequent MBOC decisions (in 1994 and 1995) have, I believe, eroded away

any remaining credibility in the VEI Program that the DoD may have left.

This Court has never before been asked to decide how it would stimulate

defense contractors via the VEI clause. The ASBCA has generally ruled that a

liberal interpretation favoring royalty compensation should be encouraged in order

to achieve maximum savings ideas for the Government! The incorrect interpretation

of the Court of Appeals misreads the language of the clause and will effect a

contrary result. Defense contractors are extremely concerned about it. There are

special and important public reasons for this Court to hear the issue before its

impact is felt throughout the government's cost savings incentive programs.

1. The Value Engineering Incentive (VET) Clause Will No Longer Provide

Contractors With An Incentive To Submit VECPs To The Government

If It Is Interpreted So Narrowly As To Negate The Government Stated

Purposes Of The Clause And A Reasonable Reading Of The Royalty

Sharing Provisions Of The Clause Itself

It is fair to say that the Bianchi trilogy'*of VEI clause cases are being

closely followed by the defense industry. To date notable legal commentators

on MBOC’s cases have universally lamented that this is no way to incentivize

contractors! Recent 1994-95 published comments on the Bianchi decisions

have intoned (and I quote verbatim):

“As a matter of policy, the Government should find some way (by

amendment to regulations or endorsement of the implied contract theory)

to pay contractors when the Government utilizes the ideas in a value

engineering proposal on subsequent contracts. The Government’s policy

is to encourage value engineering. It is difficult to find a way more

calculated to discourage value engineering proposal preparation and

submission than to let the Government ‘appropriate’ contractor’s ideas

without payment.”?

* — M. Bianchi of California, supra notes 3, 4 and 5

John J. Kirlin v. United States, supra note 2

Gulf Apparel Corp., ASBCA No. 27784, 89-2 BCA 421,735 (1989), at p. 109,266

M. Bianchi of California, supra notes 3, 4 and 5

BRIEFING PAPERS. (January 1994), pp. 32-34.

8

“Indeed, if the Government as a policy matter really wants to encourage

contractors to generate cost savings (as many senior policy making

officials have often stated), one would have thought it could have achieved

the same result by being receptive to a more liberal interpretation of the

current VEI’ clause language than it seems to have been in cases like

Bianchi. having resisted that approach, however, it may well be that the

value engineering program unless it is willing to revise the VEI’ clause

to eliminate language that can be interpreted to discourage contractors

from spending the money needed to generate the ideas the Government

says it wants.”'* (emphasis added)

“Although the court’s decision ultimately offered Bianchi another limited

chance to prove its case, the inherent unfaimess in the court’s reliance

on Kirlin will not promote contractors’ faith in the VECP process... While

the general concept that contract completion extinguishes the

Government's right to accept a VECP is a simple, bright-line rule for the

Government, contractors and reviewing tribunals to follow, it ignores

the inequities that exist when the Government simply reject a VECP,

waits until the termination of the contractual relationship, and accepts

the same proposal offered by another contractor or independently initiates

the change on its own, allowing the Government to avoid compensating

the original developer of the savings ‘concept’.”

“The court did not discuss Bianchi’s Value Engineering clause in detail;

however, the clause’s unambiguous statement that acceptance of the VECP

could occur ‘within a reasonable time after performance has been

completed under this contract’ could have provided the necessary

springboard for undoing what appeared to be an injustice to Bianchi- ed

(emphasis added)

“One of our earliest criticisms of a decision of the U. S. Court of Appeals

for the Federal Circuit was in

Value Engineering: The Federal Circuit

Kicks a Wounded Dog, 1 THE NASH & CIBINIC REPORT, Para. 93.

We took offense at the holding in John J. Kirlin, Inc. v. ULS., 827 F.2d

1538 (Fed.Cir.1987),...that Government use of the idea in a value

engineering change proposal was not compensable if it occurred after

‘completion’ of the contract. We concluded that this was poor value

‘* 36 The Government Contractor, (Sept.21,1994)

‘SM. Clancy & V. Antonacci,

1994 Year In Review: Analysis of Significant Federal Circuit

Government Contracts Decisions, 24 Public Contract Law Journal, No. 2 (Winter 1995),

pp. 201-202

9

contract clauses were not operative after completion. The latter

assumption is clearly ridiculous and would wreak havoc if applied

generally. For example, what would it do to the Government’s rights

under the ‘Patent Rights’ or ‘Rights in Technical Data’ clauses? Where

would it leave the Disputes’ clause? Need we go on?” (emphasis added)

“It_ seems to us that this is a case of winning a battle but losing the

war...Government wins by making arguments that work against its best

interest. The Bianchi decision greatly reduces the incentive of concurrent

and future savings that the “Value Engineering” clauses give to contractors

to induce them to submit VECPs. This is particularly true in the case of

agencies that do not process VECPs promptly - where almost the only

incentive is concurrent and future savings. a ane ee nee re

willi tt Vv *'6 (emphasis added)

Mr. Ralph Nash, a highly respected legal educator, author, and consultant

to government and industry, puts the issue in the proper perspective...the

government has won the battle but will surely lose the war.

If this Court orders that Mr. Bianchi should be paid for the actual use of

his interlining VECPs in all “affected” military end-item garments the

beneficial result to the government would be dramatic. When word of a

positive Decision is announced to the defense contracting community it is

reasonable to expect a flood of cost savings suggestions.

This issue is of exceptional importance to the defense community, the

public and the government, particularly as the fallout from decades of deficit

budgets and deficit spending critically impacts our ability to fund essential

government programs. The government needs every cost savings idea now

more than any time in recent history.

2. A Liberal Interpretation of The VEI Clause’s Royalty Sharing

Provisions Will Benefit The Government And Makes Sense

The principle that when in doubt “liberally” interpret all VEI Clauses in

favor of royalty compensation should be encouraged. In an earlier case before

the ASBCA the DPSC was specifically advised that its VECP program

requires “open handed and ever generous administration” if it is to achieve

maximum savings ideas for the government, stating:

“If the sharing provisions were to be interpreted and administered strictly

with an eye to holding down rewards, the incentive to propose or urge

© R. Nash, VALUE ENGINEERING: Another Illusory Promise?, 9 THE NASH &

CIBINIC REPORT, No. 3 420 (March 1995), pp. 42-43

10

adoption of money-saving devices and procedures would be eliminated,

the flow of suggestions would dry up, and the program would die.”"’

This principle goes back almost 30 years at the ASBCA. Industry

comments on the Bianchi cases (quoted above) are strongly in favor of liberal

interpretation as the way to positively encourage VECPs. It is in the public

interest for this Court to consider the benefit of such a liberal policy before

the Court of Appeals conclusively establishes the latest Bianchi decision as

a major roadblock...which may fatally undercut that common sense public

policy and the intent of the current clause.

3. The Supply Contract VEI Clause Literally Contemplates Royalties

For “Concurrent” and “Future” Contracts Which Occur After

Performance Of The “Instant” Contract Has Been Completed, And

Should Be Treated Differently Than The Construction Contract VEI

Clause

The Federal Circuit applied its holding in John _J. Kirlin Inc. v. United

States, 827 F.2d 1538 (Fed.Cir.1987), a “construction” contract case, to the

VEI clause contained in MBOC’s three “supply” contracts. Although the

Kirlin opinion doesn’t otherwise identify the clause, the standard construction

contract VEI clause does not allow any cost sharing for acquisition savings

other than on the “instant contract”."*

Further, the December 15, 1980 DAC #76-7% -ersion of the VEI clause

explicitly states in ASPR § 1--706.1(b) that °(s,"aring on construction

contracts applies only to savings on the instant contract.” [see Appendix E}

In Kirlin, from the onset, the defense contractor never had any legitimate

“expectation” of future or concurrent or collateral savings if a VECP was

submitted. Conversely, MBOC’s “supply” contracts contained a different

VEI clause. Under the sharing provision of MBOC’s JO9 (VEI) clause, the

government explicitly provided for not only instant savings, but for future

and concurrent savings as well.

The Federal Circuit’s reassertion of the Kirlin holding in the latter two

Bianchi cases works an extremely harsh result.

‘7 Gulf Apparel Corp., ASBCA 27784, 89-2 BCA 421, 735 (1989) at 109,266. See also

Philco-Ford Corp., ASBCA No. 16197 BCA 49917 (1973), at 46,493; Northeastern

Manufacturing and Sales, Inc., ASBCA No. 38307, 90-1 BCA 422,562, (1980), at

113,229; W.R. Johnson, Inc,, ASBCA Nos. 40251 et al., 91-3 BCA 924,172 (1991).

at 120,913; and B.F, Goodrich Company v. United States, 398 F.3d 843,848

(Ct.C1.1968).

ASPR § 7-602.50 (entitled “Value Engineering Incentive-Construction”); If Nash &

Cibinic, Federal Procurement Law 1194 (3d ed. 1980); cf. 2 Steiger, Federal Contract

Management, $8.05[3}[a], note 5(19993); CCH Government Contract Reports,

£21,700 at p.10,401 (Feb.2,1992); accord Umpqua River Navigation Co,, ENGBCA

No. 3381, 78-1 BCA $13,051 (1978), at p, 63,740

1]

adele Radaetiins. Sine Mena

ot Gl at EH IFN MN el

The net effect of the Boxes VECP Decision last August 1994 coupled

with the instant Interlining VECP Decision is to kill “constructive acceptance”

possibilities for supply and service contractors. As indicated by several

defense industry commentators, this could perpetuate poor value engineering

policy and poor government contracting policy because it actually discourages

contractors from submitting VECPs. The public has to important an interest

in this concept not to have a hearing, and this Court’s reconsideration of the

negative implications of this precedent.

4. Under the Cardinal Rule of Contract Interpretation a Contractor’s

VEI Clause Should Be Uniformly Interpreted To Carry Out The Mutual

Intent Of The Parties. The MBOC Interlining Decision Threatens That

Principle for Government Contractors.

Hearing testimony by the government’s VECP expert witness, Susan

Caso, on April 27, 1992, and Mr. Bianchi himself earlier in the trial, indicate

that they both interpreted the DPSC’s Standard JO9 Clause in harmonious

agreement...i.e., that MBOC’s Pellon nonwoven, fusible interlining and cotton

thread component VECP suggestions, once approved by the DPSC, would

be compensated for all end-item garments procured by the DPSC on future

contracts which have incorporated his VECP suggestions within the royalty

period. Further, Ms. Caso’s testimony was identical one year earlier in the

MBOC Boxes VECP claim Hearing.

This interpretation was not only mutually understood by both parties,

but it gives a fair and reasonable interpretation to all parts of the JO9 Clause.

including that language concerning cost sharings royalties for “all affected

end-items”, which language was completely ignored by the Federal Circuit

in its July 21, 1995 opinion (and its earlier Boxes opinion onAugust 10,1994).

Prior case law in the Federal Circuit indicates that contract language

should be interpreted as a whole so as to harmonize and give meaning to all

of its provisions and the parties understanding of the clause as shown by

their conduct before the controversy. Under the cardinal rule of contract

interpretation the contract must be interpreted to carry out the mutual intent

of the parties."

In the Julius Goldman's Egg City v. United States” the Federal Circuit

interpreted the party’s mutual intent, via the entire contract, stating:

19 . e .

v. Uni , 6997 F.2d 1051,1057 (Fed.Cir.1983);

Thanet Corp. v, United States, 591 F.2d 629,633 (C1.C1.1979): Randolph Engineering

Co,, ASBCA No. 4872, 58-2 BCA $1053 (1958), at p.867; izona v. Uni

States, 575 F.2d 855,863 (Ct.Cl.1978); AID Request for Decision, B-210103. 83-2

CPD 4116 (1983), citing S. Williston, A Treatise on the Law of Contracts, (3d ed

1961) § 618; and J. Gabig & C. Cook, A Guide To Interpreting Contracts, 23 NCMA

Journal, No.1 (1989) p.1.

y. Uni , Supra note 19.

12

“Contract interpretation has been consistently viewed as a harmonizing

process in which the various parts of a disputed contract are to be

construed as a whole to give meaning to all of its provisions. In State of

Arizona v. United States, 575 F. 2d 855,863 (1978), the Court of Claims

held that: “[w]e follow the established general rules that provisions of a

contract must be so construed as to effectuate its spirit and purpose, that

' a

iV visions, and that an interpretation which

gives a reasonable meaning to all parts will be preferred to one which

leaves a portion of it useless, inexplicable, inoperative, void, insignificant,

meaningless, superfluous, or achieves a weird and whimsical result.”*'

(emphasis added)

Two Air Force officers recently wrote an excellent article on the law of

government contract interpretation.” They state, “the cardinal rule is the

highest rule of contract interpretation”, and that a judge must ascertain the

mutual intent of the parties as manifested in the contract, including evidence

of oral testimony.”

Ms. Susan Caso, the Government’s Value Engineering Specialist (the

Government's expert consultant during the entire 9 day trial) testified under

oath on April 27, 1992 that when a VECP suggestion for new component

items such as “buttons, threads, cloth, zippers and slide fasteners” are used

by the Government in an “end item” (other than on the instant contract) then

the contractor would share in cost savings for the use of his “component

specification” in all “affected” end item specifications.

In the Boxes VECP claim Hearing, on March 1, 1991 Ms. Caso similarly

testified while under direct examination by Government counsel:

“BY MS. ZIMMT-MACK:

Q.

Q. Under what circumstances?

A.

J wirement.

Q. As in your discussion of the webbing, is that correct?

A. That’s correct.” (emphasis added) ASBCA No. 36518 Transcript page

5-42.

21 ld.

2 See Generally, J. Gab & C. Cook. A Guide To Interpreting Contracts, 23 NCMA

Journal, Issue No. 1, page 55.

3 Id, note 4.

13

ye

oF Sa a ae (I te el ll

i ae et ee

9 AREY SE

yes

—————————

Ms. Caso had testified earlier in the day that a change in the construction

of “webbing” would be an example of a component VECP suggestion that

automatically resulted in its incorporation into other end items for royalty

purposes:

“Q. Would you explain a value engineered component?

A. Well, a value engineered component indicates that at the time that

the approval is loaded into the contracting tech data file, that one

action taken to incorporate it into the file resulted automatically in

the incorporation of a valued engineered component in other items.

Wells, explain what the component would be?

An example of a component would be if a contractor were to

ti webbing, if he

recommended using a shutteless loom construction in lieu of a shuttle

machine to make the webbing. When the change is loaded into the

contracting technical data file, it is loaded in for the webbing. By

loading those changes in for the webbing, anywhere that webbing is

a referenced document in some end item --

In other words, anywhere the webbing is used to make the end item?

Exactly. Anywhere that one action resulted in the incorporation of this

VE into other items, because it was listed as a component.” (emphasis

added) ASBCA Nol 36518 Transcript, pages 5-13 and 5-14.

MBOC’s VECP 2181 interlining suggestion is a component VECP

Suggestion (like webbing). The Government’s above-quoted interpretation

in that circumstance would allow him royalties when that new component

was used “for items other than the end-item which he ori ginally had a contract

for”. That was the mutual intent of the parties. This interpretation gives

reasonable meaning to all parts of the JO9 Clause.

This Court of Appeal’s finding interpreted only the words “essentially

the same items”. It ignored the words “all affected end items” in Clause JO9

and, thereby, rendered them wholly imperative, meaningless and superfluous.

That result will no doubt be confusing to the defense contractor community.

Contractors won't believe what the VEI clause Says even if its rewritten

by DoD if the courts continue to misconstrue it in order to the limit recovery

of royalties. Again, this Court has the opportunity to correct this farreaching

interpretation which undercuts the VE] Program.

5. MBOC Submitted Uncontradicted And Overwhelming Proof Into

Evidence At The Trial That VECP No. 2181 Was Accepted By The

Government, The Specification Was Changed To Incorporate MBOC’s VECP

Non-Woven Fusible Interlining Suggestion, And That Other Contractors

Did, In Fact, Implement MBOC’s Suggestion On “Future” Contracts.

At theApril 1992 ASBCA Hearing MBOC’s expert witnesses authenticated

100 thick volumes of MBOC’s Trial Exhibits of applicable garment contracts,

14

> O

» O

specifications calculations and analysis regarding “future” Government

contracts. This evidence was almost 15 feet in width. Three expert witnesses,

in addition to Mr. Bianchi, testified over 3 days at the Hearing and introduced

these one hundred Trial Exhibits into evidence without Government objection:

Wi Date Trial Exhibi

James W, Sutherland,Ph.D. 04/21/92 Nos. 1000-1039

Nos. 1049-1073

Nos. 1080-1092

George Davidson 04/22/92 No. 1094

Peter Elliott, CPA 04/23/92 Nos. 1040-1042

No.1074

No. 1093

MBOC thoroughly briefed the Court of Appeals concerning these

Exhibits, but did not include all the 100 volumes supporting cost savings

evidence into the Joint Appendix on appeal before the Federal Circuit because

it would have overloaded the Court Clerk. Nevertheless, under Fed.R. App.

P., Rule 30 (a) this evidence is a part of the Court’s record even though

they’re not phycially included in the Appendix on appeal.

As to Mr. Davidson, MBOC included his entire 233 page report in the

Appendix on appeal. As to Mr, Elliott, MBOC included only Trial Exhibit No.

1042 (concerning VECP 2181 calculations) which itself was 154 pages long.

Each of Mr. Elliott’s 4 other supporting Trial Exhibits were just as lengthy.

As to Dr. Sutherland, MBOC introduced into evidence no less than

ninety-four (94) separate and distinct Trial Exhibits...one for each military

specification for each of five VECPs that implemented MBOC’s VECP

suggestions. Due to the sheer number of these 94 volumes we could not

include them in the Joint Appendix on appeal; and we told the Federal Circuit

this. MBOC briefs contained a 4 page list of these 94 Trial Exhibits.

In particular, Trial Exhibit 1029 details government contracts for the

“identical” Army allweather coat that implemented MIL-C-44030 changes

due to MBOC’s VECP 2181 (i.e., non-woven fusible interlining) suggestion.

Trial Exhibit 1029 contains 217 pages of very detailed evidence on

specific “future” contracts for the identical item by contractor name, DLA

contract number, quantity, price, dates, SRC and DD numeration. MBOC’s

VECP 2181 was implemented in identical Army coat contracts, at a cost

savings alone of almost $30 million.

There is no competent evidence to support the ASBCA’s contrary findings on

this damages issue, nor the Federal Circuit's endorsement of this erroneous fact.

The Government submitted no contrary evidence whatsoever during the

April 21-28, 1992 ASBCA Hearing. It consciously chose to ignore the

15

quantum of damages. The Government also did not dispute this fact in its

brief before the Federal Circuit.

What level of VECP proof will ever satisfy a federal court? Is the court

system simply stuck on the “size” of MBOC’s potential royalties, rather than the

phenomenal size of the cost savings to date? MBOC’s royalties (if compensated

in full) would only equate to about eleven percent (1 1%) of the total cost savings

benefit realized by the government as of today. Again, defense contractors will

be frustrated and disincentivized when they learn about the level of proof that

MBOC entered into evidence only to be denied any recovery.

CONCLUSION

WHEREFORE, Petitioner respectfully prays that writ of certiorari be

granted for the Supreme Court to consider and decide this important federal

question.

S/

Robert A. Brunette

4443 Chevy Chase Drive

La Cafiada Flintridge, CA 91011

(818) 790-0956

Attorney for Petitioner

M. BIANCHI OF CALIFORNIA

APPENDIX A

OPINIONS BELOW:

U.S. COURT OF APPEALS FOR THE FEDERAL CIRCUIT

ON JULY 21, 1995

17

a

Poy —————— .

* AG omg eer

aT a ee COC PCCCCOERE DER O RCO ERO RO OH CbeCeCe

4 NOTE: Pursuant to Fed. Cir. R. 47.6, this disposition is not citable as z

¢ precedent. It isa public record. The disposition will appear intables ¢

$ published periodically. bs

a

United States Court of Appeals for the Federal Circuit

94-1166

M. BIANCHI OF CALIFORNIA,

Appellant,

v.

William J. Perry

DEPARTMENT OF DEFENSE,

Appellee.

DECIDED: July 21, 1995

Before RICH, NEWMAN, AND RADER, Circuit Judges.

RICH, Circuit Judge.

DECISION

M. Bianchi of California (MBOC) appeals the September 20, 1993 decision

of the Armed Services Board of Contract Appeals (ASBCA or board) in

ASBCA Nos. 37395, 37798, 42243, 42244, and 42416 (consolidated), denying

MBOC royalties based on five Value Engineering Change Proposals (VECPs),

We affirm.

18

DISCUSSION

MBOC is a government contractor for military garments. This appeal

involves three contracts and five VECPs. Three of the VECPs suggest

changing the interlining in specific military garments from a woven material

to PELLON, a nonwoven fusible material. Of the other two VECPs, one

Suggests changing the type of thread around button holes, and the second

suggests combining size labels in specific garments.

MBOC submitted five claims to the Contracting Officer. A final decision

was never issued, and MBOC took five separate appeals to the board where

they were consolidated. Before the board, MBOC asked for concurrent,

collateral, and future contract savings on all items with button holes, wherever

nonwoven fusible interlining is used, and wherever separate labels are

combined claiming that they all meet “essentially the same items” clauses of

the contracts. MBOC seeks royalties, from 1988 to 1990, of approximately

$180,000,000 for these suggestions.

The board unanimously rejected MBOC’s claims holding as a matter of

law that the doctrine of constructive acceptance does not apply to MBOC’s

claims, that no instant or concurrent savings were created by MBOC’s VECPs,

and that the Value Engineering Incentive (VEI) clause does not provide for

collateral savings. Below is a table relating the contracts, the VECPs, and

the board’s findings.

Contact # Description | VECP No. |Description | ASBCA Findings

DLA-100-79-C-| Navy 3380 Change a) rejected by

2894 raincoats: interlining _| gov.

ordered from fusible

43,000 with woven b) not

option for material to | implemented

21,500; PELLON on

delivered men’s NAVY | c) none of the

43,952; raincoats. future

contract contracts

terminated were for

for default “essentially

on 10/29/81. the same

items”

19

Contact # Description | VECP No.| Description |ASBCA Findings

DLA-100-80-C-| Air Force Change a) rejected by

2290 women’s interlining —_{ gov.

pantsuit from hair,

Coat: wool, rayon, |b) not

ordered or cotton to | implemented

26,250; gov. fusible

considered PELLON on |c) none of the

performance women’s Air | future contracts

complete on Force were for

12/9/80. pantsuit “essentially

coats. the same items”

Change a) none of the

thread for | future contracts

buttonhole _| were for

gimp on “essentially the

women’s Air |same items”

Force pantsuit

coats from

silk to

polyester.

2880 Combine a) rejected by

separate gov.

size labels

on women’s |b) not

Air Force implemented

pantsuit.

Cc) none of the

future contracts

were for

“essentially

the same items”

Ne Te

Contact # Description | VECP No. |Description ASBCA Findings

DLA-100-80-C-| Army men’s | 2181 Change a) accepted by

2972 all weather interlining | gov.

coat: ordered from fusible

125,240, woven b) not

delivered material to | implemented,

25,903; PELLON on | therefore no

contract men’s Army | future

terminated all weather | contract

for default coat. royalties

in late *81.

c)contract

MIL-C-44030

was for

“essentially

the same

items,”

however no

suppliers used

the suggestion

within the

available

window,

therefore no

royalties are

available

The Contracts Disputes Act (CDA) states the standard for this court’s

review of decisions from agency contract appeals boards as follows: |

(T]he decision of the agency board on any question of law shall not

be final or conclusive, but the decision on any question of fact shall

be final and conclusive and shall not be set aside unless the decision

is fraudulent, or arbitrary, or capricious, or so grossly erroneous as

to necessarily imply bad faith, or if such decision is not supported by

substantial evidence.

41 U.S.C. § 609(b) (1988); See Federal Data Corp. v. United States, 911 F.2d

699, 702 (Fed. Cir. 1990).

Although MBOC enumerates sixteen issues on appeal, we find it

necessary to address only those issues that are dispositive.

2!

—————————

(ct pe Fee Te

ive alae VeRO Rei . lend Br EA Lah es

Nee Nie eh Rete ee We

In its opinion, the board thoroughly evaluated the legal and factual basis

for its determinations, which provide several alternative grounds for

nonallowance of all the VECPs at issue.

All three contracts at issue include the same VEI clause. Its pertinent

language is as follows:

If the VECP accepted under this contract is used on future purchases

of essentially the same items by the purchasing office, or its successor,

the Contractor shall share in the savings .... (emphasis added).

From the above language, it is clear that the VECP must be accepted

under the contract for allowance of royalties thereunder. As noted in the

table above, the board found that three of the VECPs had been rejected by

the agency, Nos. 1280, 2880, and 3380. MBOC, however, asserts that VECP

Nos. 1280, 2181, 2880, and 3380 were “constructively accepted” by the

agency when it allegedly implemented the “concepts” of these proposals in

future contracts and therefore, it is entitled to future royalties. The government

argues that MBOC’s theory of constructive acceptance was properly rejected

by the board.

The provisions of the VEI clause limit a contractor’s recovery of cost

savings arising from the agency’s adoption of a VECP to instances where the

VECP 1) is accepted by the agency, 2) is implemented on the instant contract,

and 3) requires the issuance of a change to the contract. See John J. Kirlin v.

United States, 827 F.2d 1538 (Fed. Cir. 1987). The board, in applying Kirlin,

found that VECP Nos. 1280, 2880, and 3880 were specifically rejected by

the agency and thus constructive acceptance was not a viable theory for

entitlement. Subsequent to the board’s findings, this court reaffirmed the

board’s application of the reasoning in Kirlin, which limits constructive

acceptance to cases where the contractual relationship has not ended. M.

Bianchi of California v. United States, 31 F.3d 1163, 1167 (Fed. Cir. 1994)

(“If the government rejects the proposal in good faith and the contract

terminates, the VECP terminates with the contract.”). We affirm the board’s

decision,holding that the agency rejected VECP Nos. 3380, 1280, and 2880

without bad faith before termination, as supported by substantial evidence

and based on proper application of the legal requirements for constructive

acceptance. Although the board found that VECP No. 2181 had been accepted

by the agency, it concluded that MBOC had not established entitlement to

royalties on the basis discussed below.

MBOC’s claim for future royalties also requires interpretation of the

“essentially the same items” language in the VEI clause. MBOC argues that

the “essentially the same items” language means the “components” in the

military clothing, such as thread, interlining, and labels for use on any military

items having such components, and not the particular garment that is the

subject of the contract. This court, however, has recently interpreted this

22

(lla ig

same language from one of the contracts at issue here to mean “[t]he ‘items’

referred to in the contract are the ones manufactured and shipped pursuant to

the contract.” M. Bianchi of Cal. at 1168. The “essentially the same items”

language refers to the items purchased under the contract and not to the

component parts thereof. Because the board’s interpretation in the instant

appeal is consistent with this court’s precedent, we affirm.

After careful review of the record, we hold that there is substantial

evidence to support the board’s findings that either none of the future contracts

were for “essentially the same items” or, in the case of VECP No. 2181, no

contractor ever implemented the suggestion. Therefore, MBOC is not entitled

to royalties on any future contracts.

23

Seti ena itch Tne bile

APPENDIX B

OTHER OPINIONS:

ARMED SERVICES BOARD OF CONTRACT APPEALS

ON SEPTEMBER 30, 1993

ARMED SERVICES BOARD OF CONTRACT APPEALS

Appeals of -- )

)

M. Bianchi of California )

) ASBCANos. 37395 37798 42243

) 42244 42416

Under Contract Nos. )

DLA100-80-C-2290)

DLA100-80-C-2972)

DLA100-79-C-2894)

APPEARANCE(S) FOR THEAPPELLANT: Michael A. Hordell, Esq.

Laurel A. Heneghan, Esq.

Petrillo & Hordell

Washington, DC

APPEARANCE(S) FOR THE GOVERNMENT: Thomas Hornak, Esq.

Chief Trial Attorney

John M. Logue, Esq.

Patricia A. Papas, Esq.

Trial Attorneys

Defense Personnel

Support Center (DLA)

Philadelphia, PA

N N Vv

After being awarded three contracts for the production of articles of

clothing for the military services, appellant submitted five value engineering

change proposals (VECP’s) thereunder which it contends the Government

accepted directly or constructively and for which it now seeks royalties of

approximately $180 million, as follows:

25

ASBCANo, VECPNo, Contract Description of VECP

37395 1380 DLA100- — Change thread for

80-C-2290 _ buttonhole gimp on

women’s pantsuit coats

from silk to polyester’

37798 1280 DLA100- Change interlining of

80-C-2290 women’s pantsuit coats

from hairwool, rayon, or

cotton to Pellon

non-woven material

42243 2181 DLA100- Change interlining of

80-C-2972 men’s all weather coats

from fusible woven

material to Pellon fusible

non-woven material

42244 3380 DLA100- — Change interlining of

79-C-2894 enlisted men’s raincoats

from fusible woven

material to Pellon fusible

non-woven material

42416 2880 DLA100- — Change from separate size

80-C-2290 and identification labels

for women’s pantsuit

coats to one combined

label

Quantum, as well as entitlement, is at issue in each of the appeals.

VECP 1380 also contained a proposed change to use Oncore or cotton

thread for all body construction of the coats instead of polyester and

silk thread (finding 23, infra). However, appellant declared at the hear-

ing of these appeals and thereafter that it was no longer pursuing its

claim with regard to that proposed change (tr. 1/17-18; app. posthearing .

br. at 79, 312).

26

I. The Contracts

A. Contract No. DLA100-7-C-2894

1. On 13 July 1979, the Defense Personnel Support Center (DPSC) of

Philadelphia, Pennsylvania, Defense Logistics Agency (DLA), awarded

appellant Contract No. DLA100-79-C-2894 for the manufacture and delivery

of 43,000 Navy men’s single-breasted polyester/cotton, poplin blue shade

3346 raincoats in accordance with military specification MIL-R-82290B(SA)

for a unit price of $19.20 and a total contract price of $825,600 (R4, ASBCA

No. 42244, tabs 1-4).

2. The contract also provided for an optional quantity of 21,500 units,

which the Government ordered by Modification POOOO7 on 22 February

1980, at a unit price of $21.64, raising the contract quantity to 64,500 and

increasing the contract price to $1,290,860 (ibid., tab 5).

3. Appellant delivered 43,952 units, but the remaining quantity of 20,548

units was terminated for default by Modification POOO11 dated 29 October

1981 (ibid.).

B. Contract No. DLA100-80-C-2290

4. On 7 November 1979, DPSC awarded appellant Contract No.

DLA100-80-C-2290 for the manufacture and delivery of 26,250 polyester/

wool, tropical 10-ounce, blue shade 1578 Air Force women’s pantsuit coats

in accordance with Purchase Description ENEU 78-7 (subsequently

superseded by MIL-C-87160) for a unit price of $34.37 and a total contract

price of $902,212.50 (R4, ASBCA No. 37395, tab 1). The contract stated

that it was a production test procurement for the purpose of determining

whether the item described in ENEU 78-7 “can be manufactured in quantity

production in accordance with accepted production practices” (ibid., tab 3 at

63; tr. 1/89).

5. Appellant delivered 25,903 units which the Government paid for and

regarded as contract completion on 9 December 1980 (tr. 9/62-63; exh. G-

193).

27

C. Contract No, DLA100-80-C-2972

6. On 23 June 1980, DPSC awarded appellant Contract No. DLA100-

80-C-2972 for the manufacture and delivery of 125,240 Army men’s black

cotton and polyester poplin cloth all weather coats with removable liners at a

unit price of $31.92 and a total contract price of $3,997,366.40. The coats

were to be manufactured in accordance with Limited Purchase Description

12-77 (DES 12-77A) dated 1 November 1978 (subsequently replaced by

MIL-C-44030, dated 24 July 1980) using patterns dated 21 September 1979

issued by the United States Army Natick Research and Development

Laboratory (Natick) and were to be delivered between 4 January and 3 June

1981 (R4, ASBCA No. 42243, tabs 3, 5; tr. 1/156).

7. Appellant delivered 38,146 coats under the contract, and the

remaining 87,094 were terminated for default in late 1981 (R4, ASBCA No.

42243, tab 6).

D. Value Engineering Incentive Clause

8. All three of appellant’s contracts contained the following value

engineering incentive clause (R4, ASBCA No. 37395, tab 4; R4, ASBCA

No. 42243, tab 1; R4, ASBCA No. 42244, tab 2):

JO9 VALUE ENGINEERING INCENTIVE (DPSC 1978 Jan)

(a) Application. This clause applies to a Contractor developed and

documented Value Engineering Change Proposal (VECP) which:

(i) requires a change to this contract to implement the VECP, and

(11) reduces the overall costs to the cognizant Military Department

without impairing essential functions of characteristics, provided that

it is not based:

(A) solely on a change in deliverable end item quantities, or

(B) a change in R&D end item or test quantities due solely

to results of previous testing under this contract, or

(C) solely on a change to the contract type.

(b) Documentation. As a minimum, the following information shall

be submitted by the Contractor with each VECP.

(i) a description of the difference between the existing contract

requirement and the proposed change, and the comparative

advantages and disadvantages of each, justification when a function

or characteristic of an item is being altered, and the effect of the

change on the performance of the end item;

28

(ii) an analysis and itemization of the requirements of the

contract which must be changed if the VECP is accepted and a

recommendation as to how to make each change (¢.g., a suggested

specification revision):

(iii) a separate detailed cost estimate for both the existing

contract requirement and the proposed change to provide an estimate

of the reduction in costs, if any, that will result from acceptance of

the VECP, taking into account the costs of development and

implementation by the Contractor (including any amount attributable

to subcontracts in accordance with paragraph (h) below);

(iv) a prediction of any effects the proposed change would

have on collateral costs to the Military Department such as

Government-furnished property costs, costs of related items, and costs

of maintenance and operation.

(v) a statement of the time by which a contract modification

accepting the VECP must be issued so as to obtain the maximum

cost reduction, noting any effect on the contract completion time or

delivery schedule, and

(vi) identification of any previous submission of the VECP,

including the dates submitted, the agencies involved, the numbers of

the Government contracts involve’ and the previous actions by the

Government, if known.

(c) Submission. VECPs shall be submitted to the Procuring

Contracting Officer (PCO). When the contract is administered by

other than the purchasing office, a copy of the VECP shall be

submitted simultaneously to the Administrative Contracting Officer

(ACO). VECPs shall be processed expeditiously, however, the

Government shall not be liable for any delay in acting upon any VECP

submitted pursuant to this clause. The Contractor has the right to

withdraw, in whole or in part, any VECP not accepted by the

Government within the period specified in the VECP.

(d) Acceptance. The Contracting Officer may accept, in whole

or in part, by contract modification either before or within a reasonable

time after performance has been completed under this contract any

VECP submitted pursuant to this clause. Until a contract modification

applies a VECP to this contract, the Contractor shall remain obligated

to perform in accordance with the terms of the existing contract.

Contract modification made pursuant to this clause will so state. The

decision of the Contracting Officer as to the acceptance of any VECP

under this contract (including the decision as to which clause is

29

licabl ' Lif thi ‘ns both a “V

Engineering Incentive” aah Solel ectneatien boesoens

Requirement” clause) shall be final and shall not be subject to the

“Disputes” clause of this contract.

(e) Sharing. If a VECP submitted by the Contractor pursuant

to this clause is accepted, the Contractor shall share in savings realized

by the Government in accordance with the following provisions:

(1) Instant Contract.

(i) Definitions:

(A) Instant contract savings to the Contractor (ICS)

is the unit cost reduction times the number of units affected in the

instant contract. The proposed unit cost reduction includes estimated

allowable Contractor development and implementation costs (CC).

The Contractor’s development and implementation costs include any

subcontractor development and implementation costs and

subcontractor incentive payments (see (h) below). For purposes of

this clause, Contractor development costs are those costs incurred

after the Contractor has identified a specific VE project and prior to

acceptance by the Government.

(B) Government Costs (GC) are those DOD costs

which directly result from development and implementation of the

VECP, such as test and evaluation of the VECP, and any increased

cost in DoD operations, maintenance, and logistics support.

**e

(2) Concurrent Contracts.

(i) If the VECP accepted under this contract is also used

on concurrent contracts of the purchasing office for essentially the

same items, the Contractor shall be paid a share of any savings as

calculated in (ii) below.

(ii) Calculations

(A) Determine the reduction in the price of each

concurrent contract(s) as a result of incorporating the VECP.

(B) Subtract from the total amount in (A) any

Government costs (GC) not yet offset (if GC was greater than ICS)

in (e) (1) (ii) (C) or (D) above, and any increase in the instant contract

price, 1.e., if ICS was negative in (e) (1) (ii) (D), if the resulting

number is positive, multiply it by 50% (25% if this is a VEPRC).

Add this amount to the instant contract price.

30

(3) Future Contracts.

(i) Definition. The term unit cost reduction for future

contract sharing shall be the unit cost reduction under this instant

contract without deducting any cost of development or impletion

[sic].

(ii) If the VECP accepted under this contract is used on

future purchases of essentially the same item by the purchasing office,

or its successor, the Contractor shall share in the savings on all affected

end items scheduled for delivery not later than 3 years after acceptance

of the first item incorporating the VECP, or until the originally

scheduled delivery date of the last affected end item under the instant

contract, whichever is later. When sharing on future contracts is

expected, the Contractor shall be responsible for the following:

(A) Maintaining records adequate to support

identification of the first delivered unit to which the VECP applies.

These records are considered an integral part of contract

documentation and shall be maintained for a period of three years

after final payment on the contract under which the VECP was

accepted.

(B)Annotating the DD-250, Material Inspection and

Receiving Report, which applies to the initial unit covered by the

VECP with the following statement:

“This is the initial unit delivered which incorporates VECP NO. ,

Contract Modification No. , dated ,

(iii) Calculations. At the time each eligible future

contract is awarded:

(A) Determine the number of units scheduled to be

delivered prior to expiration of the Contractor sharing period

determined in (ii) above. Multiply this by the unit cost reduction as

defined in (e) (3) (1).

(B) Subtract from the total amount in (A) any

Government costs or instant contract increases not yet offset in (e)

(1) (11) (C) or (D), or in (e) (2) (ii) (B), or in other contracts awarded

since acceptance of the VECP. If the resulting number is positive

multiply it by 50% (25% if this is a VEPRC) and add the result to the

instant contract price.

(f) Payment. The Contractor’s concurrent and future

contract shares should be paid upon modification of concurrent

contracts or future contract award, or within six (6) month thereafter.

However, any such payments are subject to the condition that to the

extent the Government does not receive delivery and accept all items

31

.

on which the share is paid, the Contractor shall reimburse the

Government the proportionate share of the payments. If this clause

is modified to provide for lump sum payments, such payments shall

be made upon modification of the instant contract.

II. ’s Vi Vv ,

A. VECP 1280 (ASBCA No, 37798)

9. In a letter to DPSC dated 3 December 1979 (R4, ASBCA No.

37798, tab 6), appellant submitted several VECP’s under Contract 2290,

including the following proposal which the Government subsequently

designated as VECP 1280 (ibid., tab 10):

1. Change From:

MIL-C-297F Cloth Interlining, Cotton Wrap and Spun Hairwoo!

or Rayon Filling 12-1-79: $4.50 per yard 72" wide for Coat Fronts.

Change To:

Pellon Corp. fusible [sic] #3633, Color White, 45" wide at $.60

per yard.

Hair-Wool .286 yards per garment

72 x 36 equals 2592 square inches

Cost per square inch = .001736

658 square inch x .001736

= $1.14 per coat.

Pellon 45" x 36" long = 1620 square inches.

Cost per square inch = .000373

658 square inch x .000373 =

$.25 per coat.

Savings of $.89 per coat

10. An interlining is a piece of fabric that is sewn or fused between two

other layers of fabric in parts of a garment, such as collars, cuffs, and pocket

flaps, to give them body and stiffen them (tr. 5/1 87-88, 8/52).

11. Garment interlining material is either woven -- that is, resulting from

the weaving of yarns vertically and horizontally on a loom like the hairwool

32

|, aaa ii

prescribed in Contract 2290 -- or non-woven -- that is, resulting from the

pressing together of fibers with some sort of resin or by heat to cause them to

bond into a papery type configuration like the Pellon Corp. #3633 material

proposed by appellant (tr. 1/23, 82, 131-32, 141-43, 156-57, 5/188, 6/83-84).

12. Both woven and non-woven interlinings can be sewn or fused into a

garment (tr. 1/134, 5/188). A fabric like Pellon #3633, is fusible when an

adhesive is applied to it and is joined to other material by a process of time,

temperature, and pressure which melts the adhesive (tr. 3/17, 5/189-90, 8/28-

29).

13. Non-woven fusibles were developed by Freudenberg, the parent

company of Pellon Corp., in Germany in or before the 1960's and became

generally accepted in the garment industry by the mid-1980’s (tr. 3/64). DPSC

began testing fusibles in the late 1960’s to determine how they could be used

in military clothing (tr. 6/133); and the Army Research and Development

Center at Natick, Massachusetts, engaged in a continuous research,

development, and experimentation program concerning the use of fusible

fabrics for components of garments, including interlinings, from 1971 to

1983 and thereafter (tr. 5/170, 175-76, 193-94, 6/5-6, 16-17, 93-96, 136,

138, 192-200, 7/49, 9/115-21; exh. G-139, -143). All of the military services

participated in the Natick program, including the Marine Corps (tr. 2/58, 6/

13, 16-18, 133-34, 7/49, 116) which wrote the MIL-C-29365 (MC)

specification, entitled “CLOTH, NONWOVEN: INTERLINING, FUSIBLE,

NYLON AND POLYESTER, POLYAMID,” around a Pellon product in

February 1978 (exh. G-116, -139; tr. 6/19, 35); and the military departments

were fusing interlinings on approximately 15 items such as dress shirts,

raincoats, service caps, and optional PX-type uniform coats in the mid to late

1970's (tr. 5/199-200; exh. G-125). Although the Government had tested

250 uniform coats in 1975-76 to determine the feasibility of fusible interlinings

therein (tr. 6/5-6, 21, 133-34; exh. G-128) and had met with Pellon personnel

at its factory in New England in the mid-1970’s (tr. 6/17), it was not convinced

in late 1979 that the desired quality of dress coats could be maintained with

fusible interlinings (tr. 5/198-99, 6/57, 94-95). As stated by Mr. Bruce Snigger

of the Fabric and Fabric Technology Division of Natick, in a 14 January

1980 memorandum to the chief of that division (exh. G-128):

2. A meeting was held on 7 December 1979 with Mr. D. Cerow,

AUPO, to review the present status of the use of fusible interlinings

and discuss where new uses can be introduced as presented in

reference 1. Present from F&FT Branch, TR&ED were B. Snigger,

E. Frederick, and R. Roth.

33

2

*

3

:

a

-

7

2

7

3. From the items identified in reference 1 as potential candidates

for fusibles, it was agreed that the items listed in the attached table

should be investigated and priorities were assigned as indicated.

4. The following comments are made concerning the categories

selected for investigation:

a. Coats (items 1-3) - A wear test was performed in 1975/1976

with 250 fused polyester/wool coats. Although 68 percent of the test

subjects reporting to NARADCOM indicated preference of the fused

coats, some of the test items exhibited delamination of fused areas.

The number of faulty coats generated a reluctance to introduce

fusibles into dress items at that time. However, with the growing

popularity in commercial items, and with the experience gained in-

house and by outside contractors, a program has been initiated to

evaluate improved fusibles in 25 men’s coats in a small scale, closely

monitored wear test which could include Army Uniform Board

personnel. The coats will be made under “ideal” conditions

(temperature, pressure and dwell time) with the fusing being done in

the fusible supplier’s laboratory. Crown Textile Co. has offered to

furnish the fusibles and to assist in the fabrication of the coats.

b. Shirts and Overblouses (items 4-7) - The question was raised

as to whether fusing of the flaps would magnify the puckering of the

pocket stitching because of the flaps’ relative smoothness.

Approximately six (6) shirts will be made with fused collars, cuffs,

flaps and shoulder loops to determine what aesthetic differences result

before and after laundering.

¢. Raincoats (items 8-10) - A document modification will be

sent through AUPO to EPMO which will implement the fusing of

raincoat collar stands as an alternate to the sewn-in marquisette.

Fusing of the raincoat front with a suitable nonwoven fabric was

also determined to be worthy of investigation. Sample coats will

tentatively be made up at the Pellon Corporation Studio in New York

and evaluated.

d. Women's Uniforms (items 11 & 12) - These items are

scheduled to be phased out. AUPO has indicated that changes to

these items would not be feasible since they could be out of the system

before any modifications were implemented.

34

e. Coat, Men’s, Woven Twill, Textured Polyester, AG 434 - UQC

S-2-75 (item 13) - Since this item already utilizes fusible interlinings,

a document change is being prepared for the UQC Office through

AUPO to include fusing of the cuff wigans. This will be completed

in January 1980.

5. Total funding over a two year period should be approximately

$60,000. Action is being taken to transfer funds from AUPO to

establish a TR&ED task.

14. Delamination is the separation of a fusible interlining from the fabric

to which it is fused (tr. 1/131, 3/17, 43-44, 8/27).

15. At the time appellant submitted VECP 1280, it was aware that the

Marine Corps had prescribed fusible, non-woven interlinings in MIL-C-29365

(MC) in 1978 (tr. 2/58). Appellant itself had had no prior experience with

Pellon non-woven fabrics (tr. 2/114, 126).

16. By letter dated 28 February 1980, while the Government was

evaluating VECP 1280 (R4, ASBCA No. 37798, tabs 8-11), appellant

proposed the following Pellon products for the Government’s consideration

as “additional alternate” products to be used for interlinings on the Air Force

women’s pantsuit coats “for this procurement and all like procurements” (ibid.,

tab 12):

Pellon #SG413 36” Non-woven Fusible $1.09 1/2 per yard White

Pellon #SG413 36" Non-woven Fusible $1.16 1/2 per yard Black

.

(or, a lighter version)

Pellon #SG313 36" Non-woven Fusible $0.85 per yard White

Pellon #SG313 36" Non-woven Fusible $0.91 per yard Grey

17. In a letter dated 12 March 1980 (ibid., tab 14), appellant informed

DPSC:

Cost estimated for the difference between hairwool and fusible

interlining, as referenced in letter to DPSC dated 03Dec79, is

incorrect. Depending on the type fusible interlining used, the savings

is not $.89 but, from $1.36 for SG413 to $1.62 with Pellon #3633,

$G313 savings would be $1.49.

35

Estimated labor savings by fusing are as follows.

Labor cost deleted

Hand Operations

A. Operation 4 (E) Press undercollar .046

B. Operation 4 (T)3 Baste collar 1/4" 092

from edge to edge

C. Operation | (A) Baste interlining to front .092

D. Operation 14(A) Press fronts .092

E. Operation 14(B) Trim front interlining .092

F. Operation 21(C) Baste diagonal rows 198

across lapels

er

A. Operation 4 (A) Blindstitch collar lining 055

B. Operation 4 (H) Stitch top and side edges 055

of collar

C. Operation 13(A) Blindstitch 6 rows on lapel A]

D. Operation 14(DD) Stitch interlining from | A

armhole to shoulder seam

E. Operation 21(F) Blindstitch back of front .22

facing to interlining

F. Operation 27(C) Sew shoulder loop interlining .11

to edge

Labor cost added

Fusing of parts 20

Total labor savings are: Deleted operations $1.272

Minus added cost 22

Savings $1.052

18. After evaluation by DPSC and the Air Force specification preparing

activity and in accordance with their recommendation (ibid., tabs 13, 16-18),

the contracting officer, by letter dated 18 April 1980, disapproved VECP

1280, stating (ibid., tab 19):

36

VECP 1280 - Proposal to use Pellon fusible in lieu of cotton

warp and spun haircloth or rayon filling interlining material is not

approved. We concur in the concept of using fusible interlining

materials wherever applicable. However, one of the problems to be

resolved before any action can be taken is to have test methods that

yield reproducible data on which requirements can be based. Also,

compatibility of the Pellon material and the base cloth to which it

will be fused must first be determined. Detailed manufacturing

procedures to insure control of time, temperature, and pressure during

the fusing operation is of primary importance.

19.On 13 and 16 June 1980, appellant resubmitted VECP 1280,

proposing respectively that Pellon #3633 and Pellon #SG413 be used in the

manufacture of the pantsuit coats instead of hairwool or hair-rayon, and further

stating that the proposal contemplated a reduction in cost on all like garments

as well as the contract item (ibid., tabs 20, 21; tr. 1/126-27).

20. The Government took no action on the resubmitted VECP, and

appellant, through counsel, submitted a claim concerning VECP 1280, in the

amount of $1,023,999.86, on 4 August 1988 (exh. A-1165).

21. On 17 October 1988, the appeal in ASBCA No. 37798 was initiated

by appellant after failure of the contracting officer to issue a final decision on

its claim.

B. VECP 1380 (ASBCA No. 37395)

22. Appellant’s 3 December 1979 letter to DPSC (finding 9) also

contained the following proposal under Contract 2290 which the Government

subsequently designated as VECP 1380 (R4, ASBCA No. 37395, tabs 6, 7):

2. Change From:

V-T-301D Thread Silk 4/22/71 AM, 2 - 4-19-73 - $50.60

1750 yards per pound/Omit Completely.

Change To:

V-T-285 D Polyester -- 1750 yards $.65

Savings : $49.95 per pound

37

23. On 25 January 1980, appellant amended its proposal in the following

letter to DPSC (ibid., tab 8):

Please refer to our Valued [sic] Engineering

Recommendations dated 03 December 1979, Change #2.

The information given to us by Gudebrod, Inc. regarding 1750 yards

per pound, silk thread, is incorrect. We recommend the following

change which will reflect the pounds as being accurate according to

the management of Gudebrod, Inc.:

Change From:

V-T-301D Thread Silk 4/22/71 AM 2, 4-19-73 $50.60 per pound

Yield as follows: Type A 15,200 per pound

Type B 12,480 per pound

Type C 9,920 yards per pound

(Gimp)

Change To:

Threads, Inc,

Oncore 50 MIL-T-43548 7.02 per pound

(To be used for all body construction including topstitching)

Yield as follows: 11,000 yards per pound

Cotton A-3 V-T-276 6.30 per pound

(To be used for button hole sewing)

Yield as follows: 9,600 per pound

Cotton #8 V-T-280 5.86 per pound

(Gimp to be used for button holes)

Yield as follows: 11,000 yards per pound

Omit V-T-295D Thread Nylon 2-33-77 $28.50 per pound.

This can be utilized with Threads, Inc., as listed above:

38

Silkk: A $50.60 Threads, Inc. $ 7.02

B 50.60 Threads, Inc. 6.30

G 50.60 Threads, Inc. 5.86

$151.80 $19.18

Savings : $132.62 per three (3) pounds

24. After evaluation, the Government disapproved VECP 1380, except

the proposal to use V-T 280 cotton thread for button hole gimps

(reinforcements) which it accepted, in Modification POOOO6, dated 20 May

1980, as an alternative to the ENEU 78-7 requirement for silk thread for

gimps (tr. 1/98, 9/54-55; R4, ASBCA No. 37395, tabs 9, 10).

25. The allowance of V-T cotton thread as an alternative material for

gimps was confirmed in Modification POOO10 which was executed by

appellant on 30 October 1980 and by the contracting officer on 3 November

1980 and contained the following provisions (ibid., tab 11):

1. Pursuant to Clause JO9 entitled Value Engineering Incentive

Clause the following changes are made to the specification

requirements:

VECP #1380 - para. 3.1.15 Gimp - At the end of the paragraph

add “or the Gimp may be cotton type II, size 8 of V-T-280.”

2. The contractor and the Government hereby agree that savings as

a result of VECP #1380 will be $.0395 per unit for future contracts

utilizing this change.

3. Itis agreed that the contractor is entitled to 50% of the unit savings

or $.01975 per unit for all items utilizing this change during the royalty

period.

26. Appellant did not use the alternative V-T-280 cotton thread for gimps on

the 25,903 units which it delivered under Contract 2290 between 24 September

and 9 December 1980 (exh. A-1074, G-194; finding 5; app. posthearing br. at 78).

27. There were no concurrent contracts for the item which was the subject

of Contract 2290, and no other contractors which manufactured women’s Air

Force pantsuit coats for the Government after appellant’s submission of VECP

1380 elected to utilize the alternative V-T-280 cotton thread for gimps (tr. 4/

26-27, 35, 9/57-58).

39

28. Appellant received no royalties or other compensation for VECP 1380

(tr. 1/120).

29. In a letter dated 27 May 1988, appellant filed a claim in this matter,

through counsel, in the amount of $1,036.88 for instant contract savings and

indicated that the claim would be supplemented as it obtained further

information concerning the implementation of VECP 1380 by the Government

(exh. A-1166).

30. Appellant subsequently appealed from a failure of the contracting

officer to issue a final decision on VECP 1380.

C. VECP 2181 (ASBCA No, 42243)

31. By letter dated 31 October 1980 (R4, ASBCA No. 42243, tab 7),

appellant submitted to DPSC the following VECP under Contract 2972, which

was subsequently designated as VECP 2181 (ibid., tabs 8, 9):

Regarding clause J O9 Value Engineering, MBOC recommends the

following change:

Change From

100 percent cotton plain weave cloth which has a uniformly

distributed dot system of a polyvinyl chloride/polyvinyl acetate

type fusible adhesive applied to one side. (Per paragraph 3.2.9.1

of LP/P DES 12-77A)

Change To

Pellon product SG413 (#8325) non-woven fusible interlining.

Note: Pellon Corporation has notified MBOC that # SG413 and

#8325 applies to the same product. A decision is being

finalized by Pellon Corporation management as to which

number will pertain to the product.

Please refer to DLA100-79-C-2894 correspondence on VECP

#3380 and DLA100-80-C-2290 correspondence on VECP #1380

from DLA which contains all current data and testing

accomplished by the Department of Defense.

40

Cost savings can only be determined upon future evaluating by

audit. MBOC will supply this information upon request in

compliance [sic] with Clause J O9.

32. After technical review and evaluation of appellant’s proposal, the

Army Natick Research and Development Laboratories determined that the

interlining material proposed in VECP 2181 was acceptable as an alternative

to the interlining material prescribed in the contract, and it recommended the

approval of that VECP (ibid., tab 8; tr. 6/24, 43, 51).

33. Natick’s recommendation was adopted by the Government in

unilateral Modification POOOOS to the contract dated 31 March 1981, which

provided (R4, ASBCA No. 42243, tab 6):

5. In addition, VECP #2181 has also been approved. The following

changes are incorporated into the contract to MIL-C-C-44030:

CHANGES TO MIL-C-44030, 24 July 1980

a. Page 1, paragraph 2.1, under Military Specifications, add:

“MIL-C-29365 - Cloth, Nonwoven, Interlining, Fusible, Nylon and

Polyester, Polyamid.”

b. Page 4, paragraph 3.2.9.1, at the end of the paragraph add:

“As an alternative a nonwoven fusible fabric conforming to class 3

material of MIL-C-29365 may be used as a fusible interlining. Testing

for the nonwoven fusible shall be as specified in MIL-C-29365 (The

woven fusible requirements contained herein for colorfastness,

3.2.9.3; fusing conditions, 3.2.9.4; bond strength, 3.2.9.5, and

shrinkage, 3.2.9.6, shall not apply).

6. The contractor shall be entitled to 50% of the unit savings or

[sic] any unit incorporating VECP #2181. Unit savings has not yet

been determined for this VECP; modification will be issued to

definitize the savings at a later date.

7. Contractor is obligated to annotate the DD Form 250 which

applies to the initial unit covered by the VECP #2181.

34.A cost analysis of the proposed change, conducted by DPSC’s

Directorate of Manufacturing in late March 1981 disclosed that the change

in interlining material proposed in VECP 2181 would effect neither an increase

nor a decrease in production costs (tr. 5/81, 6/152-56; exh. G-140).

41

35. VECP 2181 was not implemented under Contract 2972, and appellant

received no payments for VECP 218] (tr. 1/162; exh. A-1042; app. posthearing

br. at 289-90, 384, 443-44).

36. Appellant submitted its present claim in this matter, for an unspecified

amount, on 3 August 1990 (R4, ASBCA No. 42243, tab 12) and subsequently

appealed from a failure of the contracting officer to issue a final decision

thereon (ibid., tab 14).

D. VECP 2880 (ASBCA No. 42416)

37.On 22 January 1980, appellant submitted to DPSC a VECP,

subsequently designated as VECP 2880, under Contract 2290, proposing that

two labels prescribed in the contract for attachment to the pantsuit coats, one

for size and one for contractor and personnel identification (tr. 1/165, 199, 5/

114-15), be combined as suggested in a 10 December 1979 letter from its

subcontractor, Star Printing Company, which stated (R4, ASBCA No. 42416,

tabs 6, 7, 10):

We enclose herewith 100 each of the labels required for your contract

2290 and can quote as follows for the labels as submitted:

1. 27,000 3" x 3" Type I Classes 1 & 10 Labels @$16.50M

2. 27,000 Asst. 1 1/2 x 1 1/4 Type 1 Class 2 @$5.25M

labels plus 31 size changes @ $1.50 each

27,000 Asst. 3 1/2 x 1 5/8 “paper” bag

insert” labels @$4.50M

plus 31 size changes @ $1.50 each

Maury, if it is possible for you to combine label #1 and label #2 with

1/4" sew in on four sides only, combination Type I Classes 1, 2 and

10 label, the price for 27,000 assorted 2 5/8" x 2 3/8" labels would

be at $12.50 per thousand plus 31 size changes at $1.50 each. These

labels would take the place of both 3" x 3" and the 1 1/2" x 1 1/4"

label if you are able to convince the inspector that there is a cost

saving by combining the two labels.

We will hold up processing the balance of your order and would

appreciate hearing form you at your earliest convenience how you

want to handle the balance of this order.

42

38. After consideration and evaluation of VECP 2880, the Air Force

Clothing and Textile Office, of Philadelphia, Pennsylvania, the specification

preparing activity, reported that it did not concur in the proposal because the

“size label is required to be placed so that it will be visible for both storage &

issue purposes” (ibid., tab 11).

39. By letter dated 2 April 1980 (ibid., tab 12), the contracting officer

informed appellant that VECP 2880 was not adopted for the reason stated by

the specification preparing activity in its report.

40. VECP 2880 was not implemented on the subject contract, and

appellant received no payment therefor (tr. 1/168, 171).

41. Appellant submitted its present claim, in an unspecified amount, for

alleged constructive acceptance of VECP 2880 on 30 October 1990 and revised

the claim on 26 November 1990 to an amount less than $50,000; and it has

appealed from the failure of the contracting officer to issue a final decision

thereon.

E. VECP 3380 (ASBCA No, 42244)

42. On 28 February 1980, appellant sent the following VECP to DPSC

under Contract 2894, which was subsequently designated as VECP 3880

(R4, ASBCA No. 42244, tabs 6, 7).

MBOC recommends the following change:

Change From

Samuel Habers, QST, style #961/Facemate style #2320

Fusible Interlining Woven. $1.05

Change to

Pellon Corp., 36 inch SG413 Fusible $1.09 1/2

White

Non-Woven 1.16 1/2

Black

This product has been proven to be highly successful in raincoats

and all like garments for all outer-wear use.

43

This product is especially good for garments that are exposed to rain

or heavy water use. We have found that when the outer-shell becomes

saturated, the SG413 does not defuse itself from the base fabric as

easily as woven fusible facings. Its porus [sic] construction factors

and its fusible properties are of a hi gher quality than woven products

we have experienced in the past.

43. By letter to DPSC dated 7 April 1980, appellant amended VECP

3380 after learning that the Government intended to revise the provisions of

MIL-R-82290B to replace the woven fusible interlinings with sewn-in

hairwool woven cloth interlinings meeting the requirements of MIL-C-297,

as follows (ibid., tabs 8, 9, 15):

... it has been brought to MBOC’s attention that Woven Fusibles

would be changed to a loose coat front, flap, collar and stand

interlining.

MBOC received a bid (DLA! 00-80-B-0542) that indicates MIL-

C-297F Cloth, Interlining Cotton Warp and Hairwool. This

product is $4.50 per yard (72 inches wide). The Hairwool will

require hand trimming; added cost as follows:

1 Collar 025

1 Stand 025

2 Flaps @.02 each 04

2Coat Fronts @.06 each 12

A total cost for hand trimming of .21c.

Machine setting time cost will increase as follows:

1 Collar 015

| Stand O15

2 Flaps @.015 each .03

2Coat Fronts @.03 each .06

A total increase cost of .12¢ per coat. ‘

The above does not reflect arm flaps or epaulets. A cost increase

can not be evaluated.

The percentage of shrinkage is flexible [sic] in the MIL-C-297F

Cloth Interlining Cotton Warp and Hairwool. Patterns must be

graded with an over-allowance to accommodate. This over-

allowance can only be determined by the Pattern Maker and

Engineering Department in the Government. Additional material

of course will be necessary for the Hairwool Interlining.

The fabric cost difference is as follows:

a) Facemate Woven Style #2320 45 inches wide $1.06 per yard

b) MIL-C-297F Cloth Hairwool/Cotton Warp

72 inches wide 4.50 per yard

c) MBOC recommends:

Felton Corp SG a Non-woven, White 1.09 per yard

” Black 1.16 1/2 per yard

(or) Pellon Corp SG 313 Non-woven, White .85 per yard

. Grey 36 inches wide .91 per yard

The selection between SG 413 and SG 313 will determine the

Savings in this cost area.

Pellon SG 413 is heavier than SG 313. It is MBOC’s opinion

that SG 313 will accomplish an end product of quality finish and

desired stiffness. It is also MBOC’s position that bubbling will

not occur because of the open weave construction of either SG

413 or SG 313. MBOC strongly suggests an indepth laboratory

test on this product for all weather garments.

MBOC has made contact with the Pellon Corp to assume proper

fusing. All fusing can be arranged if contractors do not have the

proper fusing equipment.

This Valued Engineering Recommendation is for all like

garments.

44. VECP 3380 was considered by the Navy Clothing and Textile

Research Facility at Natick, Massachusetts, whose evaluation and

recommendation (ibid., tab 9) were adopted by the contracting officer and

reflected in the latter’s 14 October 1980 letter to appellant, as follows (ibid.

tab 10).

45

Your Value Engineering Change Proposal 3380, recommending a

nonwoven fusible interlining for man’s raincoat under MIL-R-

82290(SA) has been evaluated and final approval is still pending.

Currently, the Navy, with other military services, DCAS and DPSC

are conducting a Fusible Interlining Development Program. The

intent of this program is to develop a Government wide fool proof

method of specifying fusibles, their requirements, application and

testing in specifications.

Since problems occurred with fusibles in raincoats in the past and

since a program is currently underway, the Navy is withholding any

adoption of fusible into the subject specification until the fusible

interlining committee can agree on the adoption of specification

verbage [sic] that is considered to be the best method of selecting,

applying and testing the fusible.

In view of the above, your VECP cannot be adopted at this time. We

will inform you periodically regarding the progress of the fusible

program.

45. By letter dated 15 October 1980 (ibid., tab 11), appellant informed

the contracting officer, with reference to VECP’s 3380 and 1280:

We have been advised by the Pellon Company that the progress for

all branches of service has been verbally accepted and it is a matter

of the time of processing the proper paper work to formalize the

governments [sic] acceptance of the changes in the above reference

[sic] VECP numbers.

I would also like to advise you that for bookkeeping purposes, the

numbers only are being changed by the Pellon Company to an 8,000

number series. SG313 is now 8313 and SG413 is now 8325. The

fabric itself has not changed.

The Value Engineering, as previously stated, is to cover all branches

of service and all applicable garments.

Cost calculation of saving can only be determined upon audit and

evaluation in accordance with Value Engineering Clause [sic] JO9

DPSC Jan.

46

46. The specification for the Navy enlisted man’s raincoat, which was

the subject of Contract 2894, was never changed to include non-woven fusible

interlinings or other components, and the raincoat was “phased out” as an

authorized item starting in May 1985, and replaced by an all weather coat

(ibid., tabs 13, 15, 17; tr. 7/160).

47. VECP 3380 was not implemented on the subject contract, and

appellant received no payment therefor (tr. 1/149-50, 153).

48. Appellant submitted its present claim, in an unspecified amount,

concerning VECP 3380 on 3 August 1990 (R4, ASBCA No. 42244, tab 12)

and has appealed from a failure of the contracting officer to render a final

decision thereon (ibid., tab 14).

II. Appellant’s Claims

A. VECP’s 1280, 2181, and 3380

49. Appellant contends that its suggested changes to non-woven fusible

interlinings in VECP’s 1280, 2181, and 3380 were constructively accepted

by the Government when the latter implemented the concepts in those

proposed changes on subsequent specifications; that the Government

confirmed the constructive acceptance of VECP’s 1280 and 3380 when it

accepted VECP 2181; that it had introduced the Government, through DPSC,

to the non-woven fusible manufactured by Pellon Corp. or its functional

equivalent; that it is entitled to royalties for future contracts of the Government

for “essentially the same” items, which it defines, as it applies to VECP’s

1280, 2181, and 3380, as “any item which contains (or would contain ‘but

for’ MBOC’s VECPs) an unsatisfactory interlining requirement that can be

replaced with a nonwoven fusible, resulting in lower production or life-cycle

costs, without a diminution of the changed item's essential functions or

characteristics”; that it is also entitled to royalties for collateral savings which

the Government realized as a consequence of its constructive acceptance of

those VECP’s; and that the Government acted in bad faith in denying that its

VECP’s, particularly VECP 2181, resulted in contractor savings (app.

posthearing br. at 63-65, 310-12, 316-458).

50. Since the changes recommended in appellant’s VECP’s were not

implemented under its contracts, appellant is claiming no instant contract

savings therefor (ibid., at 289-90, 384, 443-44).

47

51. Nor is appellant claiming any royalties for concurrent contracts since

it could find no information to show that its VECP’s were used on any such

contracts (tr. 4/44; exh. B of exh. A-1040, -1041, -1042).

52.In accordance with its definition of “essentially the same item,”

appellant seeks royalties for alleged Government Savings On many contracts

awarded by the Government embracing the following military specifications

(exh. A-1, -1000 through -1042, -1094: tr. 1/1 36-37, 149-50, 159, 3/41; app.

posthearing br., vol III):

MIL-SPEC DESCRIPTION

B-29407 Belt for Man’s All Weather Coat

B-29408 Belt for Woman’s All Weather Coat

C-15507 Woman’s Garrison Cap

C-24921 Woman’s All Weather Coat With Removable Liner

C-43972 Woman’s All Weather Coat, Black, With Removable

Liner

C-44030 Man’s All Weather Coat, Black, With Removable

Liner

C-87110 Man’s All Weather Coat, Black, With Convertible

Collar and Removable Liner

C-87170 Woman's All Weather Coat, Black, With Removable

Liner

C-87230 Flyer’s Coveralls

J-88382 Man’s Flyer Jacket, Summer

C-82189 Man’s Full Dress Coat, Summer and Winter

J-83388 Flyer’s Jacket, Cold Weather

J-29451 Man’s Marine Corps Jacket, Intermediate Weight

R-24918 Man’s Double-Breasted Raincoat, Coast Guard, With

Removal Liner

R-24919 Woman’s Raincoat, Coast Guard, With Removal

Liner

R-43518 Man’s Quarpel-Treated Double-Breasted Raincoat

S-21087 Woman’s Skirt, Wool, Polyester Wool

S-29122 Woman’s Dress Skirt

S-87053 Woman’s Belted Skirt

S-87054 Woman’s Belted Slacks

S-87055 Woman’s Dress Shirt, White

C-24920 Man’s All Weather Coat, With Epaulets, and

Removable Liner

C-27438 Man’s Service Coat

48

C-44048

Combat Coat, Camouflage Pattern

C-44211 Man’s Coat, Tropical and Serge, Polyester Wool

C-44379 Woman’s Combat Coat, Polyester Wool

C-87215 Woman’s Air Force Garrison Cap

J-87250 Man’s Light Weight Jacket, With Removable Liner

J-87251 Woman’s Light Weight Jacket, With Removable

Liner

J-293964*+— Woman’s Dress Jacket, Scarlet

S-24948 Woman’s Slacks

S-29394 Woman’s Marine Corps Band Evening Dress Skirt

S-29429 Woman’s Skirt

S-44039 Man’s Long Sleeve Shirt, Polyester/Cotton, Army

Green

S-44041 Man’s Short Sleeve Shirt, Army Green

S-44090 Woman’s Short Sleeve Shirt, Polyester/Cotton, Army

Green

$-44093 Woman’s Long Sleeve Shirt, Polyester/Cotton, Army

Green

S-44299 Man’s Hospital Duty Uniforms Smock

S-83234 Woman’s Blue Skirt

S-82126 Woman’s Marine Corps Dress Skirt

T-44047 Combat Trousers, Camouflage Pattern

53. Appellant selected the foregoing military specifications and the

Government contracts referring to them after examination of the histories

and specifications of several thousand contracts (tr. 1/99-100, 104-13).

“Employing consultants with expertise in engineering, computers, apparel

manufacturing, methods-time-measurement with regard to clothing

manufacture, and cost and pricing data (tr. 2/149-54, 3/9-15, 4/11-19, 23),

appellant completed the formulation and quantification of its claims in late

March 1992 in reports prepared by the Peter Elliott Accountancy Corporation

(exh. A-1040, -1041, -1042; tr. 3/18-58, 105-61, 4/23--120) which contained

cost figures for the following:

a. Appellant’s estimate of labor and material savings by the

Government on future contracts.

b. Indirect Expense savings.

c. Profit.

49

d. Extended life savings -- i.e., estimated savings on quantities

that would have been scheduled for delivery but for implementation

of the VECP’s

e. Maintenance savings.

f. Interest, both before and after the filing of appellant’s claims.

g. Collateral savings and interest thereon.

h. Escalation -- i.e., the adjustment of material costs to the

midpoint period of performance (tr. 4/31-33).

i. Re-engineered costs for VECP 1280 reflecting an alternate

royalty period of the highest three years of planned production

because Contract 2290 was a production test contract (tr, 4/38-4] ).

54. The total amounts of appellant’s claims for its three non-woven fusible

interlining VECP’s, as constructed by the Elliott Corporation, were (exh. A-

1040, -1041, -1042):

VECP 1280 $68,629,052

VECP 2181 91,182,891

VECP 3380 17,013,187

Total $176,825,130

B. VECP 1380

55. Appellant contends that its suggestion in VECP 1380 that cotton gimp

be used for button hole sewing was implemented by the Government in future

contracts for approximately 32 “essentially the same” items as that purchased

under Contract 2290, defining “essentially the same item” as “any item which

contained (or would have contained) buttonholes prior to MBOC’s VECP” (app.

posthearing br. at 76, 287, 415; exh A-1049 through -1074; tr/ 1/99, 1 18).

56. Appellant seeks no collateral or concurrent Savings in its claim for

this VECP (tr. 1/18; exh. A-1074).

57. Appellant does not seek any instant contract savin gs since “Contract

DLA100-80-C-2290 was modified to incorporate VECP 1380, however, the

change was not implemented on that contract” (exh. A-1074 at A2, p. 1;

finding 26; tr. 3/74; app. posthearing br. at 78).

50

58. The future contracts for which appellant seeks royalties for VECP

1380 embraced the following military specifications (exh. A-1, -1049 through

-1074; tr. 1/107-12):

MIL-SPEC DESCRIPTION

T-44094 Trousers, Night Camouflage, Desert

C-24920 Man’s All Weather Coat with Removable Liner

C-24921 Woman’s All Weather Coat with Removal Liner

C-27438 Man’s Service Coat

C-44101 Woman’s Classic Design Coat, Polyester/Wool

C-44107 Ground Troops Parachutist’s Helmet Cover

C-44111 Woman’s Maternity Work Uniform Coat

C-44211 Man’s Tropical Serge Coat, Army Green

C-44379 Woman’s Classic Design Coat, Army Green

J-24949 Woman’s White Jumper

J-87250 Man’s Light Weight Jacket with Removable Liner

J-87251 Woman’s Light Weight Jacket with Removable Liner

O0-24905 Man’s Coast Guard Reefer Overcoat

O0-24906 Woman’s Coast Guard Reefer Overcoat

O0-24926 Enlisted Woman’s Overcoat

R-24918 Man’s Coast Guard Raincoat

R-24919 Woman’s Coast Guard Raincoat with Removable

Liner

S-29429 Woman’s Skirt

S-44110 Woman’s Maternity Work Uniform Skirt

S-87005 Woman’s Coast Guard Dress Skirt

S-87169 Woman’s Utility Durable Press Shirt

S-87171 Woman’s Durable Press Utility Slacks

T-29452 Man’s Polyester Wool Trousers

C-29391 Woman’s Wool Gabardine Dress Ceremony Coat

C-29393 Woman’s Marine Full Dress Coat

J-29396 Woman’s Marine Band Full Dress Jacket

J-29397 Woman’s Marine Band Full Dress Jacket

J-2945]1 Man’s Intermediate Weight Jacket, Polyester Wool

O0-29390 Woman’s Wool Gabardine Overcoat

S-29392 Woman’s Wool Gabardine Skirt

S-29394 Woman’s Marine Band Evening Dress Skirt

S-29395 Woman’s Musician Slacks

S-24902 Woman’s Polyester and Cotton Slacks

T-44291 Man’s Hospital Duty Uniform Trousers

V-29389 Man’s Scariet Dress Vest

51

59. Appellant selected the foregoing military specifications and the

Government contracts referring to them and prepared its claim for VECP

1380 in the same manner and with the same elements as for VECP’s 1280,

2181 and 3380 (finding 53; tr. 1/99-100, 104-15, 4/23-42, 45; exh A-1074),

except that the Peter Elliott report for VECP 1380 contained no collateral

Savings or re-engineered costs (tr. 4/39; exh. A-1074).

C. VECP 2880

60. Appellant contends that VECP 2880, which suggested the combining

of labels for pantsuit coats, was denied by the contracting officer “in bad

faith and without a rational basis” (app. posthearing br. at 88) and that it was

constructively accepted by the Government’s utilizing the change in contracts

involving the following 13 specifications for essentially the same item, which

appellant defines as “any place that the Government is going to use the

combination label” without restriction to any particular garment (ibid.; tr. 1/

32, 168-71; exh. A-1, -1080 through -1092):

MIL-SPEC DESCRIPTION

C-85700 Flyer’s Summer Coveralls

T-44213 Physical Fitness Trunks

C-87230 Flyer’s Cold Weather Coveralls

0-24905 Man’s Coast Guard Reefer Overcoat

0-24906 Woman’s Coast Guard Reefer Overcoat

P-44087 Night Camouflage Desert Parka

P-44188 Extended Cold Weather Camouflage Parka

S-29415 Wool Service Sweater

S-37951 Man’s Medical Assistant Polyester/Cotton Smock

S-44092 Woman’s Classic Design Polyester/Wool Slacks

S-44212 Hooded Physical Fitness Uniform Sweat Shirt

T=44094 Night Camouflage Desert Trousers

T-44189 Extended Cold Weather Camouflage Trousers

61. Appellant further contends that the first unit which incorporated

VECP 2880 was delivered to the Government on 28 February 1984 and that

therefore the royalty period for the VECP is from February 1984 to February

1987 (exh. G-308; app. posthearing br. at 89); that since Contract 2290 was a

production test contract, with a low rate of production, a second, alternative

royalty period, based on the highest 36 months of actual production, from

April 1989 toApril 1992, is applicable (ibid.); and that it is entitled to royalties

for future contract savings totalling $250,575 (ibid. at vol III, attachment 1).

$2

62. Appellant seeks no instant contract savings royalties since its proposed

change was not implemented under Contract 2290 (exh. A-1093); tr. 1/168).

63. Nor does appellant seek any concurrent contract savings royalties or

collateral savings costs (exh. A-1093).

64. Appellant prepared its claim for VECP 2880 in the same manner and

with the same elements as for its other VECP’s (findings 53, 59; exh. A-

1093; tr. 4/63-67).

[V. Pertinent Regulations

A. Collateral Savings

65. Armed Services Procurement Regulation (ASPR) 1-1073.2 (1 July

1976), in effect at the time of award of the subject contracts, provided that

the paragraph in the standard JO9 Value Engineering Incentive clause entitling

a contractor to share in collateral savings “may be excluded from a contract

or class of contracts when the HPA [Head of the Procuring Activity] determines

that the cost of computing and tracking collateral savings will exceed benefits

to be derived.” ;

66. Pursuant to that regulation, the paragraph in the standard JO9 clause

entitling a contractor to share in collateral savings was excluded from all of

the contracts involved in these appeals (finding 8) as well as for subsequent

DPSC contracts for the acquisition of clothing and textiles (tr. 9/103-07; exh.

G-165, -166, -167, -171).

B. Profit

67. ASPR 1-1703.1 (d), in effect at the time of award of the subject

contracts, provided:

On instant and future contracts the contractor’s profit or fee shall be excluded

when calculating the net savings.

C. Altemative Royalty Period

68. Appellant contends that because Contracts 2290 and 2894 were

production test contracts, it is entitled to future contract royalties for the time

period prescribed in Defense Acquisition Circular (DAC) #76-26, dated 15

December 1980, which was in effect prior to the actual acceptance of VECP’s

53

1380 and 2181 and the constructive acceptance of VECP’s 1280, 2880, and

3380, as an alternative to the royalty period specified in the JO9 clause of the

contract (app. posthearing br. at 18). DAC #76-26 provided (exh. A-1146):

(4) Concurrent and Future Contract Savings.

a... . If the instant contract is for low rate initial

production or an earlier life-cycle phase, the future sharing period

shall encompass scheduled deliveries, equal in number to the quantity

required by the highest 36 consecutive months of planned production,

based on the Five Year Defense Program (FYDP) or other planning

documentation at the time the VECP is accepted.

V. Additional Findi 1 Conclusi

A. VECP’s 1280, 2181, and 3380

69. In VECP 1280, appellant had proposed to change only the fronts of

pantsuit coats and not other coat parts for which it seeks royalties (finding 9;

tr. 6/140, 7/13, 9/22-23).

70. The fronts of women’s pantsuit coats were never changed in military

specifications to include non-woven fusible interlinings (tr. 6/139-40, 143-

44, 147-48).

71. The change proposed in VECP 3380, from woven fusible interlining

to Pellon non-woven fusible interlining, would not have produced any savings,

but rather it would have increased the cost of the Navy enlisted man’s polyester

cotton raincoat since the proposed Pellon material cost ($1.095 per yard for

white and $1.165 per yard for black) was greater that the cost of the woven

material prescribed in the contract ($1.05 per yard) (finding 42; tr. 1/141,

146, 6/84-85, 156-58).

72. The raincoat which was the subject of Contract 2894 and VECP 3380

was phased out of the Government procurement system in 1985 (tr. 7/160).

73. The change in material proposed in VECP 2181, from woven to Pellon

non-woven interlining in the Army man’s polyester cotton all weather coat,

which the Government accepted as an alternative (findings 32, 33), would

have produced no cost savings since the cost of the Pellon material was the

same as that for the interlining material prescribed in the contract (tr. 1/162,

5/81, 6/83, 86, 152, 155-56; exhs. G-140, -141).

54

74. Contrary to appellant’s contention (finding 49), it did not introduce

the Government to the non-woven fusible manufactured by appellant. Before

appellant had submitted its VECP’s concerning Pellon products or otherwise

suggested their use by the Government, the Government had met with Pellon

personnel at the latter’s factory, had written a specification, MIL-C-29365,

around a Pellon product, and fully considered Pellon’s non-woven fusible

interlinings as part of its continuous research, development, and

experimentation program concerning the use of fusible fabrics for garment

components for all of the military services (findings 13, 15).

75. Non-woven fusibles had not been sufficiently developed by late 1979

to eliminate the likelihood of delamination and shrinkage during manufacture,

particularly during fusing, and subsequently during laundering and dry

cleaning processes (tr. 5/198-201, 6/57, 94-95, 135-36, 7/99, 122, 8/35-37;

finding 13).

76. In the 1980's, improvements in technology, particularly with regard to

fusion machines and resin-based adhesives developed for the fusion process, led

the Government, as well as the textile industry, to make more extensive use of

non-woven fusibles in the fabrication of wearing apparel and other textile products

(tr. 3/63-64, 71, 161, 5/198-202, 6/81-82, 145, 8/16-17, 43-46). :

77.Four days before appellant had submitted VECP 2181, the

Government had completed a study of a Pellon non-woven fusible and had

begun to draft changes to military specifications for all weather coats, as

indicated in the following memorandum for the record dated 27 October

1980 by Natick’s fusing program project officer (tr. 6/23, 38; exh. G-151):

1. A study of Pellon Corporation Style 8325 has been completed

by the Seams Engineering Laboratory. The nonwoven style is

compatible with the water repellent treated fabric used in the men’s,

women’s and Jr. ROTC all-weather coats. No delamination of any

samples was found, and the fused fabrics look outstanding, in my

opinion, after laundering or dry cleaning.

2. In view of the above, I am drafting the necessary changes to the

all-weather coat specifications (MIL-R-87110, MIL-R-43972 and

MIL-R-439624A) to allow the nonwoven as an alternate to the present

(woven) fusible. This decision was based on our testing, Pellon test

results and acceptance by the Marine Corps and commercial

manufacturers. In addition, a minimal cost savings should result

when the nonwoven is used.

55

78. On the record before us, we are convinced that none of the military

specifications for which appellant seeks future contract royalties (finding

52) was changed because of appellant’s VECP’s 1280, 2181, and 3380 (tr. 6/

158-71, 177-78, 183-84, 7/9-43, 8/24-30, 43-47, 50). In fact, those working

on the fusible program and garment specifications at Natick in the 1980's

had never even heard of appellant (tr. 8/46).

79. Nor are we persuaded that the Government realized any Cost savings

on any future contracts involving those military specifications because non-

woven fusibles, as opposed to other materials, were prescribed therein (tr. 6/

151-53, 155-58, 169-71, 194). In this regard, we deem it highly significant

that appellant produced no cost records of any contractor under any of those

contracts to disclose how its manufacturing costs were affected by its use of

non-woven fusibles.

80. We further conclude, after examination of the military specifications

upon which appellant bases its claims for future contract royalties (finding

52), that none of those specifications dealt with an item which was essentially

the same as the Air Force woman’s pantsuit coat prescribed in Contract 2290

with regard to design, construction, purposes, and functions, that none of

those specifications dealt with an item which was essentially the same as the

man’s cotton and polyester poplin cloth all weather coat prescribed in Contract

2972 with regard to design, construction, purposes and functions, with the

exception of MIL-C-44030; and that none of those specifications dealt with

an item which was essentially the same as the Navy enlisted man’s single-

breasted raincoat prescribed in Contract 2894 with regard to design,

construction, purposes, and functions (exh. A-1000 through -1042; tr. 2/101-

03, 3/23, 5/196, 8/31-34). Most of those specifications, such as those for

belts, caps, coveralls, skirts, slacks, shirts, and combat wear, were not even

for remotely similar items (tr. 5/196, 8/32-34; exh. A-1000 through -1042).

81. The revision to MIL-C-44030, which appellant alleges constituted

implementation of its VECP 2181, only affected items delivered after 18

September 1984 (exh. A-1, -1029), more than three years after 14 May 198]

when appellant ceased operations on all Government contracts (exh. A-1042,

attachment 5 at 2, 21).

82. We find in the record before us no evidence to persuade us that any

future contractors for the production of garments in accordance with MIL-C-

44030 elected to use the alternative non-woven fusible fabric for interlinings in

accordance with the July 1980 amendment to that specification (finding 33) or, if

they did, thereby effected any cost savings for themselves or the Government.

56

B. VECP 1380

83. None of the military specifications upon which appellant bases its

claim for future contract royalties (finding 58) dealt with an item which was

essentially the same as the Air Force woman’s pantsuit coat prescribed in

Contract 2290 with regard to design, construction, purposes, and functions;

and most of them, such as those for trousers, helmet covers, jumpers, raincoats,

skirts, shirts, slacks, and vests, were for items which were not even remotely

similar to the pantsuit coat (exh. A-1049 through -1074; tr. 2/101-03, 3/23, 5/

196, 8-31-34, 61-62).

C. VECP 2880

84. None of the military specifications upon which appellant bases its

claim for future contract royalties (finding 60) dealt with an item which was

essentially the same as the Air Force woman’s pantsuit coat prescribed in

Contract 2290 with regard to design, construction, purposes, and functions;

and most of them, such as those for coveralls, trunks, parkas, sweaters, smocks,

shirts, slacks, and trousers, were for items which were not even remotely

similar to the pantsuit coat (exh. A-1080 through -1092; tr. 2/101-03, 3/23, 5/

196, 8/31-34, 61-62).

D. All of the VECP’s

85. The Clothing and Textile Directorate of DPSC has never awarded a

low rate initial production contract, and all of its contracts have always been

firm fixed price contracts (tr. 9/63-64).

86. We find no evidence in the record of these appeals to establish that

any of the subject contracts was, or was intended to be, a low rate initial

production contract within the meaning of DAC #76-26 (finding 68) or that

the items procured in any of the subject contracts were involved in any Five

Year Defense Program or other planning documentation at the time any of

appellant’s VECP’s were accepted.

87. Although appellant alleges in its posthearing brief that the

Government acted in bad faith and without a rational basis in actions which

it took concerning the VECP’s which are the subjects of these appeals (findings

49, 60), we find no evidence in the recordd before us which supports that

allegation, and we conclude that the Government’s representatives acted in

good faith and with good and rational cause in all of their actions with regard

to those VECP’s.

$7

DECISION

Although appellant has expended years of effort, culminating in the many

volumes of documentary evidence and the extensive testimony which it has

presented to us in support of its claims in these appeals totalling approximately

$180 million, we find those claims to be wholly without merit.

It is appellant's position that it is entitled to royalties because four of its

five VECP’s 1280, 2181, 2880, and 3380, were constructively accepted by

the Government when the latter implemented the concepts in those proposed

changes on subsequent, or future, contracts (findings 49, 60).

That position, however, is invalid as to three of those VECP’s since there

car.no compensable constructive acceptance of a VECP under future contracts

if a VECP was rejected without bad faith for the contract under which it was

submitted. John J. Kirlin v. United States, 827 F.2d 1538, 1541 (1987): M.

Bianchi of California, ASBCA Nos. 37029 and 37071, 93-1 BCA para. 25,309,

at 126,089; appeal docketed, M. Bianchi of California v. Cheney, No. 93-

1087 (Fed. Cir. 2 Dec. 1992).

Since VECP’s 1280, 2880, and 3380 were rejected under appellant’s

contracts without bad faith on the part of the Government (findings 18, 39,

44, 47, 87), appellant could therefore, as a matter of law, not recover future

contract royalties for those VECP’s even if they had been implemented on

future contracts.

Although VECP 2181 was accepted under Contract 2972 as an alternative

provision, it was not implemented thereunder by appellant (findings 32, °

Consequently, there was no unit cost reduction for that VECP under Contract

2972; and without such instant contract unit cost reduction, there can be no

future contract royalties under the terms of the JO9 clause of the contract

(finding 8), since the basis of future contract royalties is clearly stated in that

clause, at (e)(3)(i) and (iii)(A), to be “the unit cost reduction under this instant

contract.”

Thus, there is no legal basis for appellant to recover future contract

royalties for VECP 2181 even though it had been accepted.

All of these appeals must be denied as to collateral savings since neither

the JO9 clause nor any other clauses in the subject contracts allow the

contractor any compensation therefor (findings 8, 65, 66).

58

Furthermore, none of appellant’s claims are supported by the facts

surrounding them.

Three of these appeals, ASBCA Nos. 37798, 42243, and 42244, deal

with VECP’s (1280, 2181, and 3380) proposing contract changes to permit

the use of Pellon fusible non-woven interlinings in various types of coats.

However, it has been clearly established that at the time appellant submitted

those VECP’s the Government was engaged -- and had been for many years

-- in a research, development, and experimentation program concerning the

use of fusible fabrics, including Pellon non-woven fusibles, for interlinings

and other garment components; that appellant was aware of that program;

that the Government had already used fusible non-woven interlinings in some

garments; and that the Government had even written a specification for non-

woven fusible interlinings around a Pellon product (findings 13, 15, 74, 77).

The record before us compels the conclusion that not a single military

specification for which appellant seeks future contract royalties was changed

because of any of appellant’s interlining VECP’s (finding 78).

Furthermore, we have found no evidence to persuade us that the use of

non-woven fusible interlinings in any contracts involving the military specifications

cited by appellant resulted in any cost savings to the Government (finding 79).

Appellant’s claims for VECP’s 1280, 2181, and 3380 are also unallowable

because none of the future contracts for which it seeks royalties were for

essentially the same items as those purchased in appellant’s contracts, except

those embracing MIL-C-44030 (finding 80), and we find no evidence to establish

that any contractors who produced garments in accordance with MIL-C-44030

elected to use non-woven fusible fabric as an alternative material for interlinings

or delivered any items to the Government within the three-year royalty period

prescribed in the JO9 clause of the contracts (findings 81, 82).

Likewise, ASBCA Nos. 37395 and 42416, dealing respectively with

VECP’s 1380 and 2880, cannot be sustained because none of the future

contracts for which appellant seeks royalties in those appeals was for essentially

the same item as that purchased in Contract 2290 (findings 83, 84).

The claim for VECP 1380 in ASBCA No. 37395 must also be rejected

because no contractors which manufactured women’s Air Force pantsuit coats

after the submission of that VECP elected to utilize the V-T-280 cot:on thread

for gimps which was allowed as an alternative pursuant to the VECP (findings

24, 25, 27).

59

For the foregoing reasons, all of the subject appeals are denied.

Dated: 30 September 1993

/s/

JOSEPH B. AXELMAN

Administrative Judge

Armed Services Board

of Contract Appeals

I concur I concur

/s/ /s/

WILLIAM J. RUBERRY V. JOHN RIISMANDEL

Administrative Judge Administrative Judge

Acting Chairman, Armed Services Vice Chairman, Armed Services

Board of Contract Appeals Board of Contract Appeals

I certify that the foregoing is a true copy of the Opinion and Decision of

the Armed Services Board of Contract Appeals in ASBCA Nos. 37395, 37798,

42243, 42244, and 42416, Appeals of M. Bianchi of California, rendered in

conformance with the Board’s Charter.

Dated: 06 Oct. 1993

/s/

EDWARD S. ADAMKEWICZ

Recorder, Armed Services

Board of Contract Appeals

60

APPENDIX C

ORDER ON REHEARING:

U.S. COURT OF APPEALS FOR THE FEDERAL CIRCUIT

ON AUGUST 31, 1995

61

94-1166

M. BIANCHI OF CALIFORNIA, INC.,

Appellant,

V.

William Perry,

SECRETARY OF DEFENSE.

Appellee.

ORDER

62

United States Court of Appeals for the Federal Circuit

ORDER

A combined petition for rehearing and suggestion for rehearing in

banc having been filed by the APPELLANT, and the petition for rehearing

having been referred to the panel that heard the appeal, and thereafter

the suggestion for rehearing in banc having been referred to the circuit

judges who are in regular active service,

UPON CONSIDERATION THEREOF, it is

ORDERED that the petition for rehearing be, and the same hereby is,

DENIED and it is further

ORDERED that the suggestion for rehearing in banc be, and the same

hereby is, DECLINED.

The mandate of the court will issue on September 11, 1995 unless another

time becomes appropriate under Rule 41.

FOR THE COURT,

FRANCIS X. GINDHART, CLERK

Dated: August 31, 1995

By /s/

Diane M. Frye

Chief Deputy Clerk

cc: ROBERT A. BRUNETTE

GEOFFREY C. COOK

M. BIANCHI OF CALIFORNIA V DEFENSE, 94-1166

(BCA - 37395, 37798)

CeCe OSES SHHHHHSESHSHHSSHSSSSHSSHHESESESES®S

® Note: Pursuant to Fed. Cir. R. 47.6, this order is not citable as °

e _ precedent. It is a public record. :

63

) ~-

EE

APPENDIX D

JUDGMENT SOUGHT TO BE REVIEWED:

U.S. COURT OF APPEALS FOR THE FEDERAL CIRCUIT

ON JULY 21, 1995

64

United States Court of Appeals for the Federal Circuit

94-1166

M. BIANCHI OF CALIFORNIA,

Appellant,

We

William J. Perry

DEPARTMENT OF DEFENSE,

Appellee.

Judgment

ON APPEAL from the Armed Services Board of Contract Appeals in CASE

NO(S). 37395, 37798, 42243, 42244 and 42416 (consolidated) This CAUSE

having been heard and considered, it is

ORDERED and ADJUDGED:

AFFIRMED

ENTERED BY ORDER OF THE COURT

DATED JULY 21, 1995 /s/

Francis X. Gindhart, Clerk

ISSUED AS A MANDATE: September 11, 1995

65

APPENDIX E

ARMED SERVICES PROCUREMENT REGULATIONS (ASPR):

ASPR 1-703.1 and .2 (entitled “Acquisition Savings” and “Collateral

Savings”, respectively), DPC #76-9, dated August 30, 1979;

ASPR Clause 1-704.44 (entitled “Value Engineering Incentive (1977

SEP)”), DPC #76-10, dated September 26, 1977; and

ASPR 1-1706. (entitled “Sharing Arrangements”), DAC #76-26, dated

December 15, 1980.

DPC # 76-9 30 AUG. 1977 1:203

GENERAL PROVISIONS

1-1703.1 Acquisition Savings are those which accrue from the application

of value engineering change proposals to contracts for supplies or services.

Acquisition savings include instant, concurrent, and future contract savings

(see paragraph (e) “Sharing” of the clause in 7-104.44(a)(1))..

(a) Instant contract savings are those measurable net cost reductions on

the contract under which the value engineering change proposal was submitted

by the contractor and accepted by the Government. In the case of requirements

or other indefinite delivery type contracts, basic ordering agreements, multi-

year contracts, fixed-price contracts providing for prospective price

redetermination, or contracts in which supplemental agreements or other

modifications increase the quantity of items or add items to the contract, see

paragraph (j) of the clause in 7-104.44(a)(1) for the appropriate definition of

“instant contract”.

(b) Concurrent contract savings are those measurable net reductions in

the price of a concurrent contract. For purposes of Value Engineering, a

concurrent contract is a contract which has been let by the same procuring

activity for essentially the same item but which is other than the contract

under which the VECP was accepted by the Government.

(c) Future contract savings are either (i) those measurable net reductions

in the price of a future contract (other than the contract under which the

value engineering change proposal was accepted) let by the same procuring

activity for essentially the same item or (ii) a lump sum payment paid to the

contractor at the time the value engineering change proposal is accepted and

based upon estimated future applications of the accepted VECP in future

contracts let by the same procuring activity for essentially the same item.

Such savings are generally computed based upon the unit cost reduction under

the Instant contract without deducting any cost of development or

implementation. -

(d) On instant and future contracts, the contractor's profit/ fee shall be

excluded when calculating the net savings.

1-703.2 Collateral Savings are those measurable net reductions in the

cognizant Military Department’s overall, documentable projected costs of

operation, maintenance, logistic support, or Government-furnished property,

when such savings result from the VECP submitted by the contractor, whether —

or not there is any change in the acquisition cost (see paragraph (e)(4) of the

clause in 7-104.44(a)(1)). This paragraph (e)(4) may be excluded from a

contract or class of contracts when the HPA determines that the cost of

computing and tracking collateral savings will exceed benefits to be derived.

67

DPC #76-10 26 Sep. 1977 7:94

CONTRACT CLAUSES AND SOLICITATION PROVISIONS

7-104.44 Value Engineering (VE).

(a) Value Engineering Incentive Clause.

(1) In accordance with 1-702.1 and 1-1707, insert the following

clause in firm fixed-price contracts, fixed-price contracts with

economic price adjustment or fixed-price contracts providing

for prospective price redetermination:

VALUE ENGINEERING INCENTIVE (1977 SEP)

(a) Application. This clause applies to a contractor developed

and documented Value Engineering Change Proposal

(VECP) which:

(i) requires a change to this contract to implement the VECP.

and

(ii) reduces the overall costs to the cognizant Military

Department without impairing essential functions or

characteristics, provided that it is not based:

(A) solely on a change in deliverable end item quantities:

or

(B) a change in R&D end item or test quantities due

solely to results of previous testing under this

contract; or

(C) solely on a change to the contract type.

(b) Documentation. As a minimum, the following information

shall be submitted by the Contractor with each VECP:

(i) a description of the difference between the existing

contract requirement and the proposed change, and the

comparative advantages and disadvantages of each,

justification when a function or characteristic of an item

is being altered, and the effect of the change on the

performance of the end item;

(ii) an analysis and itemization of the requirements of the

contract which must be changed if the VECP is accepted

and a recommendation as to how to make each such

change (e.g. a suggested specification revision);

(iii) a separate detailed cost estimate for both the existing

contract requirement and the proposed change to provide

an estimate of the reduction in costs, if any, that will

result from acceptance of the VECP, taking into account

the costs of development and implementation by the

68

Contractor (including any amount attributable to

subcontracts in accordance with paragraph (h) below);

(iv) a prediction of any effects the proposed change would

have on collateral costs to the Military Department such

as Government- furnished property costs, costs of related

items, and costs of maintenance and operation;

(v) a statement of the time by which a contract modification

accepting the VECP must be issued so as to obtain the

maximum cost reduction, noting any effect on the

contract completion time or delivery schedule; and

(vi) identification of any previous submission of the VECP,

including the dates submitted, the agencies involved, the

numbers of the Government contracts involved, and the

previous actions by the Government, if known.

(c) Submission. VECPs shall be submitted to the Procuring Contracting

Officer (PCO). When the contract is administered by other than the purchasing

office, a copy of the VECP shall be submitted simultaneously to the

Administrative Contracting Officer (ACO). VECPs shali be processed

expeditiously; however, the Government shall not be liable for any delay in

acting upon any VECP submitted pursuant to this clause. If the evaluation

period is likely to exceed forty-five (45) calendar days, the PCO shall promptly

notify the Contractor of the estimated decision date and provide the reasons

for the additional time required. The Contractor has the right to withdraw, in

whole or in part, any VECP not accepted by the Government within the period

specified in the VECP.

(d) Acceptance. The Contracting Officer may accept, in whole or in

part, by contract modification either before or within a reasonable time after

performance has been completed under this contract, any VECP submitted

pursuant to this clause. Until a contract modification applies a VECP to this

contract, the Contractor shall remain obligated to perform in accordance with

the terms of the existing contract. Contract modifications made pursuant to

this clause will so state. The decision of the Contracting Officer as to the

acceptance of any VECP under this contract (including the decision as to

which clause is applicable to the proposal if this contract contains both a

“Value Engineering Incentive” and a “Value Engineering Program

Requirement” clause) shall be final and shall not be subject to the “Disputes”

clause of this contract.

(e) Sharing. If a VECP submitted by the Contractor pursuant to this

clause is accepted, the Contractor shall share in savings realized by the

Government in accordance with the following provisions:

69

(1) Instant Contract.

(i) Definitions.

(A) Instant contract savings to the Contractor (ICS) is the

unit cost reduction times the number of units affected in

the instant contract. The proposed unit cost reduction

includes estimated allowable contractor development and

implementation costs (CC). The Contractor's

development and implementation costs include any

subcontractor development and implementation costs and

any subcontractor incentive payments (see (h) below).

For purposes o£ this clause, contractor development costs

are those costs incurred after the Contractor has identified

a specific VE project and prior to acceptance by the

Government.

(B) Government Costs (GC) are those DoD costs which

directly result from development and implementation of

the VECP, such as test and evaluation of the VECP. and

any increased ¢ 9sts in DoD operations, maintenance. and

logistic support.

(ii) Calculations and Actions:

(A) Calculate GC and ICS.

(B) If ICS exceeds GC, calculate fifty percent (50%)

(Government share) of the sum of ICS and GC. i. e.,(5

(ICS plus GC)), unless this is a VE Program Requirement

Change (VEPRC), in which case calculate (.75 ICS plus

.25 GC). In either case, subtract the result from the

contract price.

(C) If GC exceeds ICS, but acceptance of the VECP is still

desirable due to concurrent or future savings, reduce the

instazt contract price by the amount of ICS and offset

the amount by which GC exceeds ICS against concurrent

or future savings.

(D) If the Contractor's cost of developing and implementing

the VECP would result in an increase in the instant contract

price, but the VECP is still desirable due to concurrent or

future savings, equitably adjust the instant contract price in

accordance with the “Changes” clause. In addition, offset

the increase in the instant contract price and any GC against

concurrent or future contract savings.

(E) See (e)(3)(ii) for those actions to be taken when a future

contract is expected.

70

(2) Concurrent Contracts.

(i) If the VECP accepted under this contract is also used on

concurrent contracts of the purchasing office for essentially

the same items, the Contractor shall be paid a share of any

savings as calculated in (ii) below.

(ii) Calculations:

(A) Determine the reduction in the price of each concurrent

contract(s) as a result of incorporating the VECP.

(B) Subtract from the total amount in (A) any government

costs (GC) not yet offset (if GC was greater than ICS) in

(e)(1 (1iKC) or (D) above, any increase in the instant

contract price, i.e., if ICS was negative in (e)(1 (ii)(D).

If the resulting number is positive, multiply it by fifty

percent (50%) (25% if this isaVEPRC). Add this amount

to the instant contract price.

(3) Future Contracts.

(i) Definition. The term unit cost reduction for future contract

sharing shall be the unit cost reduction under this instant

contract without deducting any cost of development or

implementation.

(ii) If the VECP accepted under this contract is used on future

purchases of essentially the same item by the purchasing

office, or its successor, the Contractor shall share in the

savings on all affected end items scheduled for delivery not

later than three (3) years after the acceptance of the first

item incorporating the VECP, or until the originally scheduled

delivery date of the last affected end item under the instant

contract, whichever is later. When sharing on future contracts

is expected, the Contractor shall be responsible for the

following:

(A) Maintaining records adequate to support identification

of the first delivered unit to which the VECP applies.

These records are considered an integral part of contract

documentation and shall be maintained for a period of

three years after final payment on the contract under

which the VECP was accepted.

(B) Annotating the DD Form 250, Material Inspection and

Receiving Report, which applies to the initial unit

covered by the VECP with the following statement:

“This is the initial unit delivered which incorporates

VECP No , Contract Modification

No. , dated My

71

(iii) Calculations. At the time each eligible future contract is awarded:

(A) Determine the number of units scheduled to be delivered

prior to expiration of the contractor sharing period

determined in (ii) above. Multiply this by the unit cost

reduction as defined in (e)(3)(i).

(B) Subtract from the total amount in (A) any Government

costs or instant contract increases not yet offset in

(e)(1)(ii(C) or (D), or in (e)(2)ii)(B), or in other

contracts awarded since acceptance of the VECP. If the

resulting number is positive, multiply it by fifty percent

(50%) (25% if this isa VEPRC) and add the result to th

instant contract price.

(4) Collateral Savings. If an accepted VECP results in a measurable net

reduction in the cognizant Military Department's overall documentable

projected costs of maintenance, operation, logistic support or

Government-furnished property, which exceeds any increase in costs

attributable to incorporation of such VECP, including acquisition costs,

the contract shall be increased by twenty percent (20%) of the projected

net reduction in ascertainable collateral costs (i.e., savings determined to

be realized during an average year of use of the item in which the change

is incorporated) and, if applicable, of the actual savings accruing from a

change or reduction of Government-furnished property under the instant

contract. However, such increase representing the Contractor's share of

collateral savings shall, in no event exceed the price of this contract of

$100,000, whichever is greater. The determination of the amount of

collateral savings, if any, will be made solely by the Government and

shall not be subject to the “Disputes” clause of this contract. In all cases.

degradation of performance, service life, or capability shall be a

consideration in the determination of actual savings to the Military

Department.

(f) Payment. The Contractor's concurrent and future contract

shares should be paid upon modification of concurrent contracts or

future contract award, or within six (6) months thereafter. However,

any such payments are subject to the condition that to the extent the

Government does not receive delivery of and accept all items on

which the share is paid, the contractor shall reimburse the Government

the proportionate share of the payments. If this clause is modified to

provide for lump sum payments, such payments shall be made upon

modification of the instant contract.

(g) Operation and Maintenance Contracts. If this is a contract for

overhaul or maintenance (including repair, alteration, modification or

modernization), the Contractor will be paid a share of future contract savings

72

realized by the Government only on overhaul and maintenance of the

designated items accomplished by purchase, under contract, by the designated

purchasing office. Only collateral savings will be paid on application of

accepted VECPs to overhaul and maintenance of items within Government

resources.

(h) Subcontracts. The Contractor shall include appropriate VE

arrangements in any subcontract of $100,000 or greater, and may include

such arrangements in contracts of lesser value. To compute any adjustment

in the contract price under paragraph (e)(1) above, the Contractor’s cost of

development and implementation costs of a subcontractor and any VE

incentive payments to a subcontractor, which clearly pertain to such VECP.

However, no such payment or accrual to a subcontractor will be permitted,

either as a part of the contractor's development or implementation costs or

otherwise, to reduce the Government's share on collateral savings or additional

purchases as contemplated by paragraphs (e)(2), (3) or (4) of this clause.

(i) Data. The Contractor may restrict the Government's right to use any

sheet of a VECP or of the supporting data, submitted pursuant to this clause, in

accordance with the terms of following legend if it is marked on such sheet:

“This data furnished pursuant to the Value Engineering clause of

contract ____ shall not be disclosed outside the Government, or

duplicated, used, or disclosed, in whole or in part, for any purpose

other than to evaluate a VECP submitted under said clause. This

restriction does not limit the Government's right to use

information contained in this data if it is or has been obtained, or

is otherwise available, from the Contractor or from another source,

without limitations.”

In the event of acceptance of a VECP, the Contractor hereby grants to the

Government unlimited rights, as defined in the clause of ASPR 7-104.9(a),

in the VECP and supporting data, except that, with respect to data which

qualifies as and is submitted as limited rights technical data in accordance

with the clause of ASPR 7-104.9(a), the Government shall have the rights

specified in the contract modification referred to in paragraph (d) hereof and

the data shall be appropriately marked.

(j) Miscellaneous Provisions

(1) For purposes of sharing under paragraph (e)(1) above, the

term “instant contract” shall not include any modifications of the instant

contract, executed after acceptance of the particular VECP, by which the

Government increases the quantity of any item or adds any item, nor shall it

include any extension of the instant contract through exercise of an option

provided under this contract after acceptance of the VECP. Such modifications

and extensions shall be considered “future contracts” within the provisions

of paragraph (e)(3) of this clause.

73

(2) If this is an indefinite delivery type contract, the term “instant

contract” for purposes of sharing under paragraph (e)(1) above shall include

only those orders actually placed by the Government up to the time the

particular VECP is accepted. All orders placed subsequent to the acceptance

of the particular VECP shall be considered “future contracts” within the

provisions of paragraph (e)(3) of this clause.

(3) If this clause is included in a basic ordering agreement, the

term “instant contract”, for purposes of sharing under paragraph (e)(1) above,

shall be the order under which the particular VECP is approved. Other orders

under the same agreement shall be considered either “concurrent contracts”

(if awarded prior to acceptance of the VECP) or ‘future contracts’ (if awarded

after acceptance of the VECP), within the provisions of paragraph (e)(2) or

(e)(3) of this clause respectively.

(4) Ifthis clause is included in a multi-year contract, the term “instant

contract” for the purpose of sharing under paragraph (e)(1) above, shall be the

funded contract at the time the VECP is approved, and items purchased under

subsequent funding under this contract shall be treated under the future contract

VE sharing provisions in paragraph (e)(3) of this clause. The sharing period

shall be the entire life of the multi-year contract, or three (3) years after delivery

of the first item incorporating the VECP, whichever is longer.

(5) If this clause is included in a fixed-price contract providing for

prospective price redetermination, the term “instant contract” for purposes of

sharing under paragraph (e)(1) above shall be that period for which firm prices

have been established. The remaining periods under this contract shall be treated

under the future contract VE sharing provisions in paragraph (e)(3) of this clause.

(6) The Contracting Officer may require the Contractor to provide written

notification prior to undertaking significant expenditures for VECP effort.

(k) Relation To Other Incentives. Those benefits of an approved VECP

which are not rewardable under performance, design to cost (production unit

cost, operating and support (O&S) costs, reliability and maintainability

(R&M) or similar incentives of the contract shall be rewarded under

subparagraph (e) of this clause. The targets of such incentives affected by

the VECP shall not be adjusted because of the acceptance of the VECP. If the

contract does not provide such incentives to better specified targets, the VE

sharing shall apply only to the amount of achievement better than target.

(End of clause)

7-104.44

ARMED SERVICES PROCUREMENT REGULATION

74

DAC # 76-26 15 DECEMBER 1980 1:201

GENERAL PROVISIONS

Part 17 - Value Engineering

1-1700 Value Engineering (VE).

1-1706 Sharing Arrangements. The two types of savings shared by the

Government and the contractor as a result of accepted VECPs are acquisition

savings and collateral savings.

1-1706.1 Sharing of Acquisition Savings.

(a) The sharing base for acquisition savings is the number of affected

end items on contracts of the contracting office approving the VECP. The

Head of the Contracting Activity (HCA) may extend the sharing base from

the contracting office throughout the activity if the HCA determines in writing

that it would be more equitable or would significantly increase the contractor's

incentive. The sharing base may be further expanded by the Secretary

concerned. The sharing rates (Government/contractor) for acquisition savings

for supplies and services are based on the type of contract, the Value

Engineering clause, and the type of savings as follows:

Incentive Program Requirement

(Voluntary) (Mandatory)

TYPE OF Concurrent Concurrent

CONTRACT Instant and Future Instant and Future

Fixed-Price 50/50 50/50 75/25 75/25

(Other than

Incentive)

Incentive ° 50/50 . 75/25

(Fixed-Price

or Cost)

Cost - 75/25 75/25 ? 85/15 —s 85/15

Reimbursement**

(Other than

Incentive)

* Same ratio as the contract’s cost incentive ratio.

** Includes cost-plus-award-fee contracts.

75

aaa

(b) Sharing on construction contracts applies only to savings on the

instant contract. The sharing rates (Government/contractor) are as follows:

Fixed-Price* 45/55

Cost- 75/25

Reimbursement*

*Other than incentive

(c) The contractor shall share in the savings on all affected units

until the originally scheduled delivery date of the last affected unit under the

instant contract or for 3 years after acceptance of the first unit incorporating

the VECP, whichever is longer. For engineering development and low rate

initial production contracts, the future sharing period shall encompass

scheduled deliveries, equal in number to the quantity required over the highest

36 consecutive months of planned production, based on the Five Year Defense

Program (FY DP) or other planning documentation at the time the VECP is

accepted. Savings are paid through the contract under which the VECP was

accepted. Within 9 months after concurrent contracts have been modified to

reflect price reductions attributable to use of the VECP, the contracting officer

shall modify the instant contract to provide the contractor’s share of savings.

On incentive contracts, the contractor’s share of concurrent, future, and

collateral savings shall be paid as a separate firm fixed-price contract line

item on the instant contract. The contractor shall be responsible for

maintaining, for 3 years after final payment on the contract under which the

VECP was accepted, records adequately identifying the first delivered unit

incorporating the applicable VECP.

(d) The contractor’s share of future contract savings may be paid as

subsequent contracts are awarded or in a lump-sum payment at the time the

VECP is accepted. The contracting officer ordinarily shall make calculations

as future contracts are awarded and, with 3 months after their award, modify

the instant contract to provide the contractor’s share of savings. Use of the

lump-sum method must be agreed to by thé contractor. For future acquisition

savings calculated under the optional lump-sum method, the sharing base is

an estimate of the aumber of items which will be purchased by the contracting

office during the sharing period. In deciding to use to more convenient lump-

sum method for an individual VECP, the contracting officer shall consider:

76

(i) the accuracy with which the number of items to be purchased

during the sharing period can be estimated and the probability

of actual production of the projected quantity;

(ii) the availability of funds for a lump-sum payment; and

(iii) the administrative expense of otherwise amending the

instant contract as future contracts are awarded.

(e) The contractor’s profit or fee shall be excluded when calculating the

net savings on instant and future contracts.

(f) Departments shall establish procedures for funding and payment of

the contractor’s share of future savings.

1-1706.2 Sharing of Collateral Savings. The contractor’s share of

collateral savings is 20% of the estimated savings to be realized during an

average year of use but shall not exceed (i) the contract’s firm fixed-price,

target price, target cost, or estimated cost at the time the VECP is accepted;

or (ii) $100,000, whichever is greater.

77

APPENDIX F

MEMORANDUM dated October 26, 1979 of Roy W. Roth, Chief of Fiber

& Fabric Technology Branch of the U.S. Army Research & Development

Center, Natick, MA (“NATICK”)

78

DRDNA-VTF Fusible Interlinings

C, Tech Sec C, F&FT Br 26 October 79

/mb/2634

1. Reference DF dtd 19 Oct 79 to C, TR&ED from Dir, CEMEL.

2. Reference Memo dtd 24 Oct 79 to C, F&FT Br from B. Snigger.

3. My own experiences with the manufacture and use of fusible interlinings

support the conclusions in | and 2 that acceptable garments can be and are

being made in Industry with fusible interlinings. Technology has advanced

within the last few years to allow numerous items to be so manufactured.

4. Despite the advances in Industry, military procurements incorporating

fusible interlinings seem to be at a standstill. Unfortunately, results from the

250 test coats made in 1975 with fusible interlinings are not available. D.

Cerow tells me that his Office had not received adequate results from the

field to constitute a report. This test, therefore, has to be considered

inconclusive.

5. I would like to see a stepwise test program formulated, identifying where

fusible interlinings should be possible, i.e., specific items, what savings could

be realized with each item (estimated labor and material savings) and a

recommended R&D effort to evaluate fusible interlinings in selected apparel-

detailing items, timing and estimated man-hour effort involved. Also, items

available within other services using fusible interlinings should be identified

where they exist.

6. Do we have any market research reports identifying where fusible

interlinings are used and are likely to be used?

7. A response to para. 5. is requested by 15 Nov.

ROY W. ROTH ;

Chief, Fiber & Fabric

Technology Branch

CF: C, TR&ED

79

CERTIFICATE OF SERVICE

I hereby certify that three (3) copies of each of the foregoing PETITION

FOR WRIT OF CERTIORARI of Petitioner M. BBANCHI OF CALIFORNIA

were served on the following parties by Certified United States Mail, return

receipt requested this 28th day of November 1995:

The Honorable William J. Perry Frank W. Hunger, Esq.

Office of the Secretary of Defense David M. Cohen, Esq.

The Pentagon Jeanne E. Davidson, Esq.

Room 3E880 Jeri Kaylene Somers, Esq.

Washington, D.C. 20301 John K. Lapiana, Esq.

Thomas W. Peterson, Esq.

Geoffrey C. Cook, Esq.

Drew S. Days, III, Esq. John M. Logue, Esq.

Department of Justice Department of Justice

Office of the Solicitor General Civil Division

10th & Constitution Ave., N.W. Room 10104, Todd Building

Room 5143 550-1 1th Street, N.W.

Washington, D.C. 20530 Washington, D.C. 20530

Francis X. Gindhart

Clerk of the Court

Court of Appeals for the Federal Circuit

717 Madison Place, N.W.

Washington, D.C. 20439

Dated: November 28, 1995 Is/

Robert A. Brunette, Esq.

4443 Chevy Chase Drive

La Cafiada Flintridge, CA 91011

(818) 790-0956

Attorney for Petitioner

M. BIANCHI OF CALIFORNIA

80