Opposition Brief — Adler Construction Co. v. United States
Supreme Court brief1971
Ask Donna
What actually matters in this document.
Text
:
INDEX
Pio 4
TER es eS eR ]
EER ae as are See oan ]
EEO RAT l
re eas anne 2 '
ee Lande acakdeesncanecuennas 8
re ae ile a mie bwines 11 .
CITATIONS
Cases: | :
Aircraft Associates & Mfg. Co. v. United
States, 174 Ct. Cl. 886, 357 F. 2d 373__ _ ___- 9 :
Barnette v. Wells Fargo Nevada Nat. Bank, 270
of Qa eee a Se SA S :
Gallen v. Lloyd-Thomas Co., 264 F. 2d 821__- ~~ 8
Grymes v. Sanders, 93 U.S. 55. -------------- 8 ;
H.L.C. & Associates Constr. Co. v. United
States, 176 Ct. Cl. 285, 367 F. 2d 586__.___- )
Lewis v. Lowry, 322 F. 2d 453, certiorari
EE OP oc dncncnaseeatue 8
Lichter v. Goss, 232 F. 2d 715._.-..-.-.------- S |
Robertson v. Franks Bros. Cv., 182 U.ts. 17__2 g
United States v. William Cramp & Sons, Inc.,
iy EA ES ep np ea 9,10
Vann v. United States, 420 F. 2d 968_______- 9
Watts Construction Co. v. United States, 161
Rls Os is OE Es BE DO inncnancenaavoenan G
Winn-Senter Construction Co. v. United
States, 110 Ct. Cl. 34, 75 F. Supp. 255_--___- 10
(I)
410-274—70——-1
Statutes:
28 U.S.C. 1491
Miscellaneous:
5 Williston, Contracts, Rev. Ed. §§ 1580, 1594,
Ue ee
Gu the Supreme Court of the Gnited States
OcToBER TERM, 1970
No. 829
ADLER CONSTRUCTION COMPANY, PETITIONER
a ‘sae
THE UNITED StaTEs
ON PETITION FOR A WRIT OF CERTIORARI TO THE. UNITED
STATES COURT OF CLAIMS
BRIEF FOR THE UNITED STATES IN OPPOSITION
OPINION BELOW .
“The opinion of the Court of Claims (Pet. App.
A-1—A-8) is reported at 423 F. 2d 1362.
ee JURISDICTION
The judgment of the Court of Claims was entered
on April 17, 1970, and a motion for rehearing was
denied on July 15, 1970. The petition for a writ of
certiorari was filed on October 9, 1970. The jurisdie-
tion of this Court is invoked under 28 U.S.C. 1255(1).
QUESTION PRESENTED
Whether a release signed by a government contrac-
tor bars him from presenting certain claims against
the United ean
(1)
2
STATEMENT
This is a suit based on certain claims arising out of
a 1952 government contract for construction of a dam.
The Court of Claims found that these claims were
barred by a valid release petitioner had signed.
A. THE EVIDENCE
In August 1952 the. Bureau of Reclamation issued
an invitation for bids on the construction of the earth-
filled Pactola Dam in South Dakota’ Congress ap-
proved the project for immediate construction in
order to make available a much needed water supply
for an air base (Pet. App. A-20—A-21). Since the
work was of ‘fa highly urgent’ nature,” it was im-
portant that construction begin before the onset of
winter weather in 1952; otherwise a full season’s delay
would result, Id.
Prior to bidding, Adler thoroughly explored the
entire project: t-site (Pet. App. A-10). He then sub-
mitted a bid of $3,761,115, some 23 per cent under
the second low bid of $4,878,476 (Pet. App. A-11).
The invitation to bid specified that a bidder would
not have any right to secure relief ‘ton the plea of
error in the bid’’ or of negligence in making the bid
(Pet. App. A-10).
On September 30, 1952, the bids were opened. The
Board considering the bids believed that ‘‘the low
hidder could not complete the work at his bid prices
without considerable strain on his financial resources”
(Pet. App. A-11). However, it recommended accep-
tance because “he is known as a conscientious and skill-
3
ful contractor, and unquestionably would prosecute
the work vigorously and in full compliance with the
terms of the specifications” (Pet. App. A-11—A-12).
Later that day, when Adler learned of the disparity
in his bid, he expressed shock, but because of his in-,
volvement in litigation, he did not confer with gov-
ernment representatives until October 7, 1952 (Pet.
App. A-12). At that time, he told the government
officials that “he may have made a mistake” and wrote
to the Chief Engineer, requesting that the awarding
‘of the contract be delayed (Pet. App. A-12—A-13),
On October 11, the Chief Engineer informed him that
the Government would “withhold making the award
a reasonable length of time,” but that it was necessary
to start the project as soon as possible (Pet. App.
A-13),
On October 14, the Bureau of Reclamation awarded
the contract to Adler, at which time Bureau officials
_ advised him to submit an affidavit explaining his errors,
which would be transmitted to the Comptroller General
for advice as to bid revision, award to the next low bid-
der, or contract readvertising (Pet. App. A-14). Adler
was told that any correction would have to be effec-
tuated by the Comptroller General because the Bureau's
officials lacked such authority (Pet. App. A-14—A-15).
The contracting officer forwarded the statement to the
Commissioner of the Bureau of Reclamation along with
the recommendation that the Comptroller General be
asked to permit an appropriate reformation of the
contract (Pet. App. A-16). The Bureau. accepted the
D>
Dat matt whe SRN nln FA ED SRY AN ett AR
recommendation, which was forwarded to the Comp-
troller General for a decision (Pet. App. A-16).’
On November 14 the Comptroller General deter-
mined that “[ujnder all the cireumstances, this Office
will not be required to object to the correction of the
bid’? (Pet. App. A-20—A-21) and three days lates
Adler met with Bureau of Reclamation representatives
in Denver to reform the contraet.?
The Bureau was apparently concerned that Adler's
corrected prices for certain items were more than the
government's prebid estimates or the bids of other
contractors regarding the same items (Pet. App. A=
17). Consequently, the Bureauy representatives in-
formed Adler they would not allow corrections that
exceeded these amounts. They also emphasized that no
further delay would be permitted, that Adler would
have to sign the contract documents immediately, and
that a notice to proceed would be issued that day (Vet.
App. A-17). Adler then signed an amendatory Agree-
ment * which increased the contract price by $485,265,
an amount $136,240 less than the increase of $621,005
Adler had sought (Pet. App. A-19).' In a letter to
the Senate Judiciary Committee in 1960, when peti-
' Adler was not advised of these favorable recommendations by
the contractiny officer and the Bureau (Pet. App. A-16—A-17).
*A text of the Comptroller's decision was not yet available
(Pet. App. A-17).
“= At thé same time he signed the basic contract (Pet. App.
A-20).
‘From the contract, as amended, Adler could have e: xpec ‘ted
to earn a profit of $557,696 (according to the government's in-
terpretation), or S271,083 (according to Adler's interpretation)
(Pet. App. A-21).
ee
5 |
tioner had a private bill for relief pending, the Under-
secretary of the Interior stated that the proposal’
embodied in the amendatory agreement “in good con-
science * * * should never have been made”’ because,
even if the full increase had been allowed, the gov-
ernment would have ‘had the advantage of an ex-
ceedingly low bid’’ (Pet. App. A-23—A-24).
| After the signing of the agreement, Adler com-
menced work, with an initial completion date of June
25, 1955 (Pet. App. A-24). However, as work pro-
gressed, he encountered subsurface or latent condi-
tions at the site of the main dam foundation mater-
ially different from those shown in the drawings and
specifications, which made excavation and refill work
much more difficult and costly (Pet. App. A-25—A-
34). At the urging of the Bureau of Reclamation (Pet.
App. A-46), Adler continued working during the
winter of 1955-1956 under severe weather conditions
in order to minimize delays (Pet. App. A-49).
Early in July, 1956, the parties held a conference
to determine how far the contract completion date
should be extended ® and to agree upon extra costs of
performance. The Bureau of Reclamation, which had
originally proposed an extension to April 27, 1956,
agreed to extend the time to August 15, 1956. The Bu-
reau also agreed with Adler to allow him $43,314 for 11
specified items of «changed conditions. At the con-
clusion of the conference, Adler signed a letter con-
firming this agreement. The letter stated that ‘‘the
* Adler had requested such an extension in mid-1955 (Pet.
App. A-44, A-45).
6
payment by the Bureau of Reclamation of the sum
of $43,314.39 * * * for extras and changes * * * will
be accepted as settlement in full of all claims for
additional compensation under the contract arising
out of work performed to date,’’ and that ‘‘no new
claims for additional compensation will be made on
the basis of anything occurring prior to July 6, 1956”’
(Pet. App. A-51—A-52).
On August 15, 1956, the project was substantially
completed (Pet. App. A-54). As contemplated by the
basie contract,’ Adler on November 20, 1956, executed
a release which provided that in consideration of the
payment by the United States to him of the amount
then due under the contract, $213,562.60, he ** releases
and forever discharges the United States of and
from all manner of debts, dues, sums or sums of»
money, accounts, claims and demands whatsoever, in
law or in equity, under or by virtue of the said con-
tract, except contract items and quantities as listed
on the reverse side hereof’* (Pet. App. A-54—A-55;
Def. Exh. 30). On the reverse side of this release
Adler listed 13 exceptions totalling $198,633.20 (Pet.
App. A-55).
*The basic contract provided that upon completion of the
project “the amount due the contractor under this contract
will be paid upon the presentation of a properly executed
and duly certified voucher therefore, after the contractor’ shall
have furnished the Government with a release, if required, of
all claims against the Government arising under and by virtue of
this contract, other than such claims, if any, as may be
specifically excepted by the contractor from the operation of
the release in stated amounts to be set forth therein” (Def.
Exh. 1, Art. 16; Pet. App. A-55).
t— +
7
Following his signing of this release and his receiv-
ing the $213,562, Adler administratively asserted
claims for extra payment. On the basis of the claims
that he had excepted from the November 20, 1957, re-
lease, Adler received $14,089 additional compensation
(Pet. App. A-63) ; he was not, however, given’ any-
thing on claims not excepted from that release (Pet.
App. A-62—A-64).
B. THE COURT OF CLAIMS DECISION
This proceeding began in 1960 by a Congressional
reference to the Court of Claims. In July 1964, the
Court of Claims held that it could not aecept jurisdic-
tion as a Congressional reference ease, but that it had
jurisdiction under 28 U.S.C. 1491. Petitioner’s prin-
cipal claims related to the government’s failure fully
to correct the mistakes in Adler’s bid, unanticipated
subsurface conditions, excavation overruns, disputed
excavation classification, work acceleration, and col-
lateral matters (Pet. App. A-9). He sought recovery
in excess of $800,000.
The Court of Claims, adopting the trial commis-
sioner’s decision, ruled that Adler was not entitled
to recover (Pet. App. A-1—A-64). It held that “none
of the claims constituting the present action were ex-
cepted from” the release Adler signed on November
20, 1956, in which he released the United States from
all claims arising out of the contract, with 13 specified
exceptions (Pet. App. A-3). The court concluded that
the release was valid, notwithstanding Adler’s claim
that he had been economically coerced into signing
sto
POON Ls ee eaten NN Oe Ral CART | ome Bree “ Lt OS A TER crate, oo olen 4
it. The court stated: “[N]o conceivable economic coer-
cion could invalidate a release where, as here, there is
no evidence that plaintiff was restricted in the scope of
his exceptions to the release” (Pet. App. A-4).
ARGUMENT
1. The release of November 20, 1956, was in ae-
cordance with the contract of November 17, 1952,
which stated that upon completion and acceptance
of the work, the amount due the contractor will be
paid upon presentation of a voucher “after the con-
tractor shall have furnished the Government with a
release, if required, of all claims against the Govern-
ment arising under and by virtue of this contract,
other than such claims, if any, as may be specifically
excepted by the contractor from the operation of
the release” (Def. Exh. 1, Art. 16; Pet. App. A-55).
Adler challenges the contract on the ground that
it was obtained through duress and the government’s
taking advantage of his mistaken bid. However, where
a party desires to rescind a contract upon grounds
such as duress or mistake, he must assert his right
to rescind without delay, and he waives his right to
rescission by electing to perform under the contract.
See, e.g.. Grymes v. Sanders, 93 U.S, 55, 62; Barnette
v. Wells Fargo Nevada Nat. Bank, 270 U.S. 488;
Lichter vy. Goss, 232 F. 2d 715 (CAM 7); Lewis v.
Lowry, 322 F. 2d 453 (C.A. 4), certiorari denied, 368
U.S. 977; Gallen vy. Lloyd-Thomas Co., 264 F. 2d 821
(C.A. 8); 5 Williston, Contracts, Rev. Ed., §§ 1580,
1594, 1626. Adler, having elected to perform under
9
the basie contract and receive payment under it, is
hound by its terms—including the requirement that
he execute a release upon completion of the work.
2. A release such as Adler signed in November 1956
hars the assertion of any claim not specifically ex-
cepted therefrom. E.g., United States v. William Cramp
ad} Sons, Inc., 206 U.S. 118: H. L. C. & Associates
Coustr. Co. v. United States, 176 Ct. Cl. 285, 367 F. 2d
586 ; Watts Construction Co. v. United States, 161 Ct. Cl.
801, 355 F. 2d 573. See also Vann ¥. United States,
420 F. 2d 968, 972 (Ct. Cl.). While the release itself
may he avoided if it was obtained by duress, e.g.,
Aircraft Associates & Mfy. Co. v. United States, 174
Ct. Cl. 886, 357 F. 2d 373,° ample evidence supports
the finding of the Court of Claims that the release was
hot so obtained. When Adler signed it. he was free to
except any claims he wished, and he listed 13 excep-
tions totalling $198,633.20 (Pet. App. A-55).
Adler contends that he did not list his present
claims among the exceptions because. he thought he
Was barred from doing so by the earlier release, dated
July 6, 1956 (Pet. 18).* But the difficulty with this con-
tention is that the claims petitioner did except also
related to work performed prior to July 6, 1956, the
date of the first release (Pet. App. A-52). This is
simply further support for the Court of Claims’ find-
‘See also Robertson v. Frank Bros, Co. 132 U.S. 17, 23.
*'This release was a letter providing that all pending claims
arising up to July 6, 1956, were withdrawn and “no new claims
for additional compensation will be made on the basis of any-
thing oceurring prior to July 6, 1956" (Pet. App. A-51—A-52).
ome MPEG
<P Ry rn Pe
ee a ee
POOLE POEM
10
ing that the government, by presenting the second re-
lease to petitioner with the opportunity for him to
note exceptions, waived the first release (Pet. App.
A-3).°
Thus, there is no justification for Adler’s failure to
list the claims involved here along with the 13 excep-
tions to the November release.” As the Court of Claims
found, Adler was exercising “his own free choice’’ in
listing 13—and only 13—exceptions to the release (Pet.
App. A-4). Adler signed the November release free
*The government by its subsequent conduct can waive pro-
visions of a release which are in its favor. See Winn-Senter
Construction Co, v. United States, 110 Ct. Cl. 34, 65-66, 75 F.
Supp. 255, 260.
© Adler contends that at the time of the signing of the Novem-
ber release he lacked certain relevant information which the
government had, such as a revised drawing of the main dam
foundation and knowledge that the Bureau had recommended
to the Comptroller General full correction for Adler’s mistaken
bid (Pet. 13). The Court of Claims properly answered that his
lack of this information does not excuse his failure to state his
exceptions covering his present claims in general terms, which
would have preserved his right to pursue them (Pet. App. A-+).
11
from duress, and there can be no question of its
validity.”
CONCLUSION
For the foregoing reasons, the petition for a writ of
certiorari should be denied.
Respectfully submitted.
ERWIN N. GRISWOLD,
Solicitor General.
WituiamM D, RucKELsHAUS,
Assistant Attorney General.
Rosert V. ZENER,
Rosert FE. Kopp,
Attorneys.
N OVEMBER 1970.
‘'Petitioner argues (Pet. 20-21) that recovery may be on a quan-
tim meruit. basis even if no recovery is permitted on the contract.
However, the November 20, 1965, release releases the United States
“from all manner of debts, dues, sums or sums of money, accounts
claims, and demands whatsoever, in law or equity, under or by
virtue he the said contract” except for the listed exceptions (Pet.
App. A-55). Such language bars a quantum meruit claim, which
uvises by virtue of the contract. See United States y. William
Cramp & Sons, Inc., supra, at 206 U.S. 127-128.
Petitioner also contends (Pet 13-14) ‘thet the Bureau of Recla-
mation, in allowing only partial correction of the bid instead
of full correction, acted contrary to a decision of the Comp-
troller General. The decision of the Comptroller General, however,
was simply that “[u]nder all the circumstances, this Office will
not be required to object” to full correction of the bid (Pet. App.
A-20—A-21).
U.S. GOVERNMENT PRINTING OFFICE: 1970
This is a copy of a public record, reproduced as it was published. It is not legal advice, and it may not be the version a court would rely on. Check the official source before you cite it.