Petition for Writ of Certiorari — United States v. Urban Plumbing & Heating Co.
Supreme Court brief1970
Ask Donna
What actually matters in this document.
Text
INDEX
one ions presented bbe hia ey ha aduk wn ao Masts Cae tke
"i te involyed EE RHEE SOS ays Toe * 6
CITATIONS
Woy Products Corporation v. United Siates,
Me. 0 GOB. sb. socks ews cen
Automatic Radio Mfg. Hazeltine Re-
ee, 176 F. 2d op, “aiceed. 339 U.S.
E pal United States, 404 F. 2d 975______-_-
Bennett v. Mahon, 180 F. 2d 224, certiorari
denied, 339 U.S. 980___......-----_.-_--
Bolander v. United States, 186 Ct. Cl. 398_-__-
Centre Manufacturing Co. v. United States, 183
Ch 0: 116, 302 F.9d 220... 2-222. 225.
D. & L. Construction Co. v. United States, 185
Ct. Cl. 736, 402 F. 2d 990____..-...._--
Dean Construction Co. v. United States, Ct.
Cl. No. 95-67 (decided June 20, 1969) ____
Gill v. S.H.B. Corporation, 322 Mich. 700, 34
Te BO. bb Gonwe ccc tncedsudoeeua
— Mill v. United States, 271 U. .
ce Hellenis Lines Lid v. Louis Dreyfus Corp., 372
PE TD. <nmawcnaakundunmnweadbuewzusbwale
“Aircraft Associates v. United States, 357 F.
22, 23
18
13
11, 13
14
0
Cases—Continued i
J. D. Hedin Construction Co. v. United States,
408 F. 2d 424
ts
King Construction Co. v. W.M. Smith Blears
Co., 350 S.W. 2d 940 (Tex. Civ. App.)
‘Kraus v. United States, 366 F. 2d 975_______
L. W. Foster Sportswear Co. v. United States,
405 F. 2d 1285
22,
Portland Hotel Corp. v. Fidelity Storage Corp.,
134 F.. 2d 57
22
16, 20, 21,2 |
United States v. Bethlehem Steel Corp., 315
U.S. 289
BLEED THROUGH POOR COPY
So SO BS SBS HBO SB SE SF SS
m
Cases--Continued
United States v. Utah Construction & Mining _ Paee
Re i cn 16, 21, 22
United States v. Wunderlich, 342 U.S. 98_---- 16
Urban Plumbing and Heating Co. v. United
Se Ff eee 22, 23
Val-Rich Corporation v. Tole Electric Co., 196
i CEE: ci nactckeidedeenguaknennniims 13
Vines v. General Outdoor Advertising Co., 171
PO is cuen shoe cucbaaagioeieaes 13
WRB Corp. v. United States, 183 Ct. Cl., 409. 18
Oo vivicnpiddvccanioadcbbinnmenddamone 13
Williamson v. Bendix Corp., 289 F. 2d 389- -- 13
Woodcrest Construction Co. v. United States,
BE Fe Gi. Hib ki ee 17, 21, 22, 23
Statute:
The Wunderlich Act, Act of May 11, 1954,
c. 199, 68 Stat. 81, 41 U.S.C. 321____---- 2, 3,15
Miscellaneous:
Gamer, After Two Years: Cases in the Court of
Claims Since Utah and Grace, Public Contract
Newsletter, vol. 3, No. 3 (July, 1968) - - - -- 23
5 Williston, Contracts (rev. ed. 1937):
ee rn 14
Se eee 12, 14
: aa ee 14
DE tasccenndimecasacanenasaemnsee 14
COPY BOUND CLOSE IN CENTER
A
BLEED THROUGH POOR COPY
§n the Supreme Court of the Wnited States
OcToBER TERM, 1969
No. ——
UntrTep States oF AMERICA, PETITIONER
v.
Ursan Pirumsina & HeEatine Co.
PETITION FOR A WRIT OF CERTIORARI TO THE UNIVED
STATES COURT OF CLAIMS
The Solicitor General, on behalf of the United
States, petitions for a writ of certiorari to review the
opinion and order of the United States Court of
Claims entered in this case on March 14, 1969.*
OPINION BELOW
The opinion and order of the Court of Claims
(App. 25-44) is reported at 408 F. 2d 382. The opinion
and findings of the Armed Services Board of Con-
tract Appeals (App. 45ff.) are reported at 66-2 BCA
{ 6062, ASBCA No. 9831.
Although the decision of the Court of Claims is interlocu-
tory in the sense that it does not finally grant or deny relief,
but simply remands for computation of the amount of recov-
ery, this Court has jurisdiction under 28 U.S.C. 1255(1).
United States v. Caltex, Inc., 344 U.S. 149; United States v.
Central Eureka Mining Co., 357 U.S. 155; United States v.
Acme Process Equipment Co., 385 U.S. 138.
COPY BOUND CLOSE IN CENTER
2
JURISDICTION
The opinion and order of the Court of Claims wag
entered on March 14, 1969. By an order of June 4, 1969,
the Chief Justice extended the time for filing a peti.
tion for a writ of certiorari to July 27, 1969. The ju-
risdiction of this Court is invoked under 28 U.S.C.
1255(1). S,
QUESTIONS PRESENTED
1. Whether an amendment to a government cop-
tract is voidable for duress merely because it was
agreed to after a government agent threatened cancel-
lation for default in circumstances ultimately found
not to have constituted culpable default, there being
no proof either of bad faith on the agent’s part or of
incapacitating financial weakness on the part of the
contractor.
2. Whether the Court of Claims exceeded the scope
of review permitted it by the Wunderlich Act on re
view of factual findings of government boards of
contract appeals.
STATUTE INVOLVED
The Wunderlich Act, Act of May 11, 1954, c. 199,
68 Stat. 81, 41 U.S.C. 321, provides in relevant part:
Limitation on pleading contract-provisions re-
lating to finality ; standards of review.
No provision of any contract entered into by
the United States, relating to the finality or
conclusiveness of any decision of the head of
any department or agency or his duly author-
ized representatives or board in a dispute in-
volving a question arising under such contract,
shall be pleaded in any suit now filed or to be
=<. aseeen eee 6am 4886 6 4ee 8 SS Te. eT. eo
3
filed as limiting judicial review of any such
decision to cases where fraud by such official
or his said representative or board is alleged:
Provided, however, That any such decision shall
be final and conclusive unless the same is fraudu-
lent or capricious or arbitrary or so grossly
erroneous as necessarily to imply bad faith,
or is not supported by substantial evidence.
STATEMENT
In June, 1961, the Urban Plumbing and Heating
Company was awarded a fixed-price contract, as
low bidder, for the modification of the central heat-
ing and power plant at Eielson Air Force Base,
Alaska. The contract specified that the work was to
be completed within 120 days after the notice to pro-
ceed. That notice was issued on June 30, 1961, there-
by fixing the completion date as October 28, 1961.
Compliance with the specified completion date was
important because the contract work involved shut-
ting down a portion of the Base heating plant, which
could not be done during the Alaskan winter.
Among the contract requirements was the instal-
lation of three sorts of furnace appliances—coal scales,
combustion air coils, and ash removal equipment. The
specifications for these appliances were fully described,
and the contract required the contractor to submit draw-
ings of the equipment he proposzd to install for ap-
proval. (Contract Sec. 5-04; App. 48). Equipment
other than that specified would be approved only if
4
“equal” to the specified equipment;* and, it was pro.
vided, ‘‘[n]o extension of contract time will regu}
from submission of material and equipment dat,
which does not fulfill the requirements.” Ibid, Th
contract also provided for a procedure by which ¢op.
formity to the specifications would be measured—gyb.
mission of the specifications of substitute equipment
to a designated architect-engineer.
On July 11 and 13, 1961, two weeks after the notice
to proceed had been given, the contractor submitted
initial data as to each of the three items of equip.
ment (Pl. Ex. 41,° Govt. Exs. E, G, H; App. 47).
On July 17, although he had not yet formally been
retained (Tr. 476-481),* the Architect-Engineer in.
formed the contractor orally that he would reject the
* As to the coal scales, the contract provided :
The coal scale shall be of the stationary, automatic, dus-
proof, batch type, Model 46, manufactured by Stock Equip-
ment Company, or approved equal.
(Sec. 5-09; App. 49)
As to the combustion air coils, the contract provided:
Equipment differing from that specified may be pro-
posed, provided the Contractor clearly states such differ.
ences and provided all essential requirements of the
specifications are met. If the equipment offered under this
provision is, in the opinion of the Contracting Officer, equal
or better than that specified, it will be given consideration
(Sec. 7-02B; App. 51)
As to the ash removal equipment, the contract provided:
It is the intent of the drawings and specifications that
equipment for this contract shall be as manufactured by
the United Conveyor Corporation, or approved equal.
(Sec. 8-04; App. 52)
*The exhibits were in the proceedings before the Armed
Services Board of Contract Appeals (“Board”).
*“Tr.” designates the transcript of proceedings before the
Board.
Ri cecn THROIGH POOR COPY
5
proposed coal scales and combustion air coils, and the
contractor promptly cancelled his orders for that
equipment (Pl. Exs. 3, 5; App. 56).’ Regarding the
ash removal equipment, the Architect-Engineer told
the contractor that the data was insufficient to permit
review (Pl. Ex. 3; App. 55); additional data was
submitted August 8, 1961 and he disapproved the
equipment on August 29, 1961, in a letter received by
the contractor September 5, 1961. (Pl. Exs. 14, 23, 31,,.
33; App. 57).
Partly as a result of these disapprovals, the con-
tract was not completed by October 28, 1961. During
September, when it became apparent that this would
happen, negotiations towards an extension of the
deadline were begun. The contractor first requested a
90-day extension; when he was offered 30 days, he
returned with a request for 120. (Rule 4 File * Doc. 9,
11, 13; App. 59). At this point, the deadline had
expired, and the contracting officer offered a 69-day
extension, corresponding to the total time elapsed be-
tween the June 30 notice to proceed and the Septem-
ber 5 disapproval of the ash removal equipment.’ Ibid.
This offer thus made no adjustment to reflect the insuf-
ficiency of the initial data, the time then taken to submit
additional data, or a reasonable period of time the Archi-
tect-Engineer might have taken to pass on the submis-
*The formal letters of rejection for these items were received
August 7, 1961 (Pl. Exs. 20,21; App. 56).
*The “Rule 4 File” is the official file of documents pertaining
to the contract, placed in the administrative record pursuant to
Rule 4 of the Armed Services Board of Contract Appeals Rules.
"Here the contracting officer made an arithmetical error; the
time elapsed between June 30 and September 5 is 67 days.
ree ns ee ee ee
6
sion.’ As an alternative—since at least some of the work
on the heating plant would not have been possible during
the Alaskan winter—the contracting officer offered a
Supplemental Agreement extending the completion date
to June 30, 1962, subject to the proviso that the extension
“neither increases or decreases contract costs.’’ (App
59.) The officer stated that he would terminate the con-
tract for default if the contractor rejected both al-
ternatives (App. 60),° and insisted that a choice be
made “within a very few days, two or three days any-
way.” (Tr. 83). After securing a change of language
from ‘‘no increase in cost” to “no increase in price,”
* At the Board hearing the contracting officer testified that
the offer of 69 days was made on the assumption that “the
Government takes « flat zero for approval of data which I think
is maybe a little unrealistic on the Government's side, I think
we are entitled to more than that in our normal approval chan-
nel up there, it was from 15 to 30 days, but I wanted to give
him the benefit of the doubt since my job is not only to protect
the Government, but also to protect the company, or the con-
tractor.” (Tr. 131; see also Tr. 220).
*The contract provided that “the right of the Contractor to
proceed shall not be terminated [for default] * * * because of
any delays in the completion of the work due to unforeseeable
causes beyond the control and without the fault or negligence
of the Contractor, including * * * acts of the Government,
either its sovereign or contractual capacity * * * and unusually
severe weather” (App. 34), The contracting officer’s threat to ter-
minate for default thus necessarily asserted that the delay which
had occurred, and the concomitant difficulties introduced by the ap-
proach of the Alaskan winter, were not entirely due to acts of
the Government. Although the Supplemental Agreement as signed
states that the delay was granted due to “adverse weather condi-
tions and Government delay in approval of data,” (App. 28), that
agreement is a compromise of the conflicting claims of the parties.
BLEED THROUGH POOR COPY
Re
BRZPRREFE “sQV TFrPP SST we
Si Sek Fas
29
BE eB
7
the contractor signed the Supplemental Agreement on
November 16, 1961 (Tr. 84-85, 104-107; App. 28).”
Urban completed the contract by June 30, 1962, and
then made a claim for the costs it had incurred as a
result of the delay past the original contract deadline.
The Armed Services Board of Contract Appeals
denied that claim, after hearing, on the ground that it
was barred by the Supplemental Agreement (App.
45). Relying on the testimony of the Architect-
Engineer that the equipment the contractor submitted
for approval in July and August had significantly
deviated from the contract specifications (App. 18-19),
it found that the contractor was partially responsible
for the delay in delivery of the equipment and therefore
“was not entitled to a time extension adequate to permit
completion of the work’’ (App. 64). It followed that the
extension permitted by the Supplemental Agreement
was valuable consideration, sufficient to support it. Ibid.
Moreover, the Board concluded, that agreement was not
invalid for duress:
Where the contracting officer threatens default
termination, and the contractor is actually in
default, the contracting officer was threatening
°The contracting officer proposed the Supplemental Agree-
ment to Mr. Brewer, the contractor’s Alaska Superintendent.
Although Brewer had authority to sign the Agreement, he told |
the officer that he wished first to speak with Mr. Urban, the
president of the contractor. He called Mr. Urban, who told
him to sign the Agreement provided that the “no increase in
cost” language was changed to “no increase in price.” Brewer
then went back to the contracting officer and advised him that
he would refuse to sign unless this change was made. The con-
tracting officer agreed to the change, and the Supplemental
Agreement was signed. (Tr. 81, 84-85, 104-105, 107, Gov't Ex. 4;
App. 60).
Palait~-,"an-le bt :ates na’ — al *2.!s*..
8
to do only what he had the right to do. This ig
not duress. [Citation]. In the instant case the
appellant was in default for the completion date
was 18 days past when the modification was
signed. At least as to the coal thaw shed only
3 days of the delay was excusable.” The con-
tracting officer offered 69 days time extension
because of the delay in approvals. This would
not have permitted completion, but we cannot
find that it was not as much as was due for ex-
cusable cause.
Ibid.
Urban then brought this action in the Court of
Claims. That court rejected the Board’s finding that
the contractor was partially responsible for the delay
“because it offered equipment which did not meet
the contractual requirements * * *.’’ Ibid. The court
considered that the specifications should have been con-
strued to permit any equipment which would function
as well as the specified equipment, and concluded that
“the Board never found, and there is no proof,”’ that the
equipment offered by the contractor deviated from the
specifications as so construed. (App. 30, n. 3).
Having found therefore that the government was
solely responsible for the delay which prevented com-
11 The coal thaw shed was a portion of the project which the
Air Force urgently wished to complete as quickly as possible,
since in its present condition it was a major fire hazard. (Tr.
266, 268; App. 58). The work on the coal thaw shed did
not involve any of the equipment disapproved by the archi-
tect engineer (Tr. 45-52, 58-68). The three days delay which
the Board found to be excusable was caused by an error in the
contract drawings. (App. 59).
BLEED THROUGH POOR COPY
9
pletion by the original contract deadline, the court
held that
* * * under the circumstances of this case, the
contracting officer had no right to terminate
the contract, except for the convenience of the
Government, and when he threatened to do so
to force the plaintiff to sign the supplemental
agreement, he was guilty of coercion and duress
against the contractor.
(App. 35). Accordingly, the court held that the
Supplemental Agreement was invalid, and thus did
not constitute a bar to recovery of the contractor’s
costs in excess of the contract price. It remanded the
ease to the Board for determination of the amounts
cs REASONS FOR GRANTING THE WRIT
1. The holding of the court below, permitting the
contractor to recover its delay-related costs, over-
head, and profit in excess of the fixed contract price
on the theory that the contracting officer’s threat to
cancel for default constituted duress invalidating the
Supplemental Agreement, is not only unsound but
conflicts with the decisions of this Court in Hartsville
Mill v. United States, 271 U.S. 438, and of the United
States Court of Appeals for the District of Columbia
Circuit in Board of Trustees v. O. D. Wilson Co., 133
F, 2d 399. It extends the concept of duress and
thereby substantially undercuts the government’s abil-
ity to defend its interests in contract renegotiations by
making compromise agreements unenforceable by the
government whenever its negotiators have asserted
contract rights later held unfounded, without regard
10
to good faith, the financial strength of the contractor,
or other relevant circumstances.
The opinion of the Court of Claims recites that
“[w]hether or not duress exists in a particular case,
depepds on the facts in the case’”’ (App. 35). But the
sole fact on which the Court of Claims relied to show
duress was the contracting officer’s threat to terminate
for default in a situation held after the fact not to in-
volve culpable default. There was no evidence, and no
finding by the Board or the court, that the contracting
officer acted in bad faith or with knowledge that he had
no right to terminate for default. In light of the Board’s
finding that the contractor was in default and the sub-
stantial evidence supporting that finding, it would be
impossible to conclude that the contracting officer go
acted. There was also neither evidence * nor any find-
ing » that the contractor was in such bad financial condi-
tion that it could not insist in its rights and bring suit in
**The only remotely relevant evidence as to financial condi-
tion was a notation in a memorandum written by the contract-
ing officer, stating: “In discussion with Mr. Brewer [Urban’s
Alaska Superintendent] he has indicated that his company has
had considerable bad luck on several construction projects this
year. They have had approximately $3,000,000 worth of busi-
ness and it seems as tho all other projects have gone sour.
had some flooding conditions oa a city project.” (Govt. Ex. A),
This notation does not show that Urban was in such bad condition
as to be unable to insist on its rights.
**The Board stated in its opinion that “from [the contrac-
tor’s] viewpoint, default termination was unthinkable” (App.
60), but did not suggest that this was because of financial
inability to insist on its rights. Such termination would be
unthinkable, for example, to a contractor who realized he was
likely to lose any such litigation as having in fact been in
material default.
BLEED THROUGH POOR COPY
11
event of termination, rather than sign a supplemental
ent it did not wish to sign. Indeed, both the ex-
tended period of negotiations over the delay as a
whole and Urban’s successful insistence upon a change
of language in the contract suggest that the Supple-
mental Agreement was freely entered.
Under the existing case law, two facts must be
shown for a threat of contract cancellation to consti-
tute duress invalidating a contract amendment: (1)
that the threat was made in bad faith, with knowledge
that the other party was not in default; and (2) that
the other party was not in financial condition to stand
on its rights rather than accept the contract amend-
ment. The leading case is Hartsville Mill v. United
States, 271 U.S. 43. There the government made a
threat to “disregard the admitted obligations of its
contracts unless those entitled to the performance of
them would yield to its demands.’’ 271 U.S. at 48-49.
Characterizing this threat as ‘‘discreditable”’, Mr.
Justice Stone nevertheless held for the unanimous
Court that the contract amendment which resulted
from the threat was not invalid for duress (271 U.S.
at 49):
But a threat to break a contract does not in
itself constitute duress. Hefore the coercive ef-
fect of the threatened action can be inferred,
there must be evidence of some probable conse-
quences of it to person or property for which
the remedy afforded by the courts is inade-
quate. ** *
Since such consequences had not been shown, the
Court concluded that duress could not be found. 271
COPY BOUND CLOSE IN CENTER
12
U.S. at 47-48. See also United States v. Bethlehem
Steel Corp., 315 U.S. 289, 300-305.
The Court of Appeals for the District of Columbia
Circuit, in a similar case, held that a government con.
tract was not void for duress when made under the
government’s threat to forfeit the contractor’s bid
bond, even though the bid bond may have been re-
scindable for an error in the bid:
[The contractor] contends that it made the con-
tract under duress, since [the government]
threatened to forfeit the bid bond if it refused
to contract in accordance with the bid. But if
[the contractor] had, as it insists, a right to
rescind, [the government] had no power to
make good its threat. Its denial of the right to
rescind did not conclude the question. [The
contractor] could litigate it. * * * [The con-
tractor] simply chose to contract and perform
rather than have its right to rescind judicially
determined. It is bound by the contract and
cannot recover in this action.
Board of Trustees, etc. v. O. D. Wilson Co., 133 F.
2d 399, 400. The court restated its position in a case
between private litigants shortly thereafter, in the
following terms:
[A]ppellees were entitled to litigate, or
threaten to litigate, the question whether appel-
lants’ failure to make improvements ended their
rights under the lease. Where there is a genuine
controversy, a threat to sue is not duress. * * *
Portland Hotel Corp. v. Fidelity Storage Corp., 134
F. 2d 57. Accord: 5 Williston, Contracts § 1606, pp.
4501-4502 (rev. ed. 1937). State authorities agree
BLEED THROUGH POOR COPY
13
that a threat to eancel a contract not in fact
subject to cancellation is not duress per se; there must
be proof that the threat was made in bad faith, and that
the other party was not in a position to have obtained
an adequate remedy by suing for damages if the
threat were carried out. The facts of cases previously
decided against the government on duress grounds
in the Court of Claims also bring them within these
principles.”
We recognize, of course, that what was found not
to constitute duress in Hartsville Mill, supra, might
be found to be so today.
[T]he modern tendency * * * is to regard any
transaction as voidable which the party seeking
to avoid was not bound to enter into and which
was coerced by fear of a wrongful act by the
other party to the transaction.
4 Williamson v. Bendix Corp., 289 F. 2d 389, 392-393 (C.A.
7) (applying Ind, law); W. 2. Grimshaw Co. v. Nevil 0. With-
rom Co. 248 F. 2d 896, 903-905 (C.A. 8), certiorari denied,
356 U.S. 912 (applying Ark. law). Bennett v. Mahon, 180 F.
9d 294, 231 (C.A. 8) (applying Mo. law), certiorari denied,
339 U.S. 980; Vines v. General Outdoor Advertising Co., 171
F. 9d 487 (C.A. 2) (applying N.Y. law); 7'ri-State Roofing
Co. of Uniontown v. Simon, 187 Pa. Super. 17, 142 A. 2d 333; Gill
v. S.H.B. Corporation, 322 Mich. 700, 34 N.W. 2d 526; Val-Rich
Corporation v. Tole Electric Co., 196 So. 2d 486 (Fla. App.).
Whero contract amendments have been voided for duress, both bad
faith and lack of an adequate legal remedy was clear. King Con-
struction Co. v. W. M. Smith Electric Co., 350 S.W. 2d 940 (Tex.
Civ. App.) ; cf. Ross Systems v. Linden Dari-Delite, Inc., 35 N.J.
329, 173 A. 2d 258.
% Fg. Aircraft Associates v. United States, 357 F. 2d 373;
WRB Corp. v. United States, 183 Ct. Cl. 409, 468-469 ; Shewan &
Sons v. United States, 73 Ct. Cl. 49, 79-95; compare Alloy Prod-
ucts Corporation v. United States, 302 F. 2d 528, 530.
358-025—69 2
COPY BOUND CLOSE IN CENTER
14
5 Williston, Contracts § 1603, p. 4495; Hellenic Lines,
Ltd. v. Lowis Dreyfus Corp., 372 F. 2d 753, 756-758
(C.A. 2). And the existence of a remedy at law—such as
the contractor here would have had under the Cour
of Claims’ view that he was blameless—is not neces.
sarily a conclusive answer where the contractor’s f-
nancial position or some other factor renders it in.
adequate. 5 Williston, Contracts § 1620, pp. 4529-4533,
But the Court of Claims’ holding in this case was made
in the absence of information about the contractor’s
financial situation; and the only wrongfulaess in the
contracting officer’s assertion that he would invoke the
contractual remedy of default was in his judgment,
ultimately found to have been erroneous, that he was
entitled to do so. ‘“‘[A] threat * * * to resort to reme-
dies given by the contract is not * * * duress * * * even
though there is no legal right to enforce the claim,
provided the threat is made in good faith; that is, in
the belief that a possible cause of action exists.” 5
Williston, Contracts § 1606, pp. 4501-4502; and see id,
at § 1607, p. 4504; Automatic Radio Mfg. Co., v. Ha-
zeltine Research, 176 F. 2d 799, 804-805 (C.A. 1), af-
firmed, 339 U.S. 827. None of the authorities suggests
that a threat to cancel a contract not actually subject to
cancellation is duress per se.
The question is important. By in effect adopting
a per se rule, the Court of Claims has severely limited
the government’s ability to engage in the negotiations
which are frequently required in the administration
of government contracts. Often, contracts cannot be
completed on time or delay or other factors create
a cost overrun; there is very often a dispute as to
BLEED THROUGH POOR COPY
15
gho is responsible for the problem. Negotiations on
revised contract terms, looking toward avoidance of
the drastic steps of litigation or default, are the usual
and desirable first step in the resolution of these
disputes. Since the allocation of responsibility for the
delays and/or overruns will bear heavily on the terms
of the revisions made, each side can be expected
to press forcefully its views on that issue and the
contract remedies therefore available to it. But under
the Court of Claims’ opinion, the government’s nego-
tiator is subjected to an unequal burden of accuracy ;
if despite his good faith belief that default has oc-
curred the court later concludes that it did not, his
representations will be construed as duress if they in-
dude or can be interpreted as a threat to cancel. The
holding thus imposes an unwarranted limitation on
the ability of contracting officers to negotiate and
settle disputes in the performance of government
contracts.
9. The previous discussion assumes that the Court
of Claims correctly found the contractor not to have
heen in default. But the Board of Contract Appeals
had found that it was at fault for the delay—both
with respect to the coal thaw shed, where none of the
challenged equipment was required, and with respect
to the equipment, because it failed to meet the con-
tractual requirements (App. 64). In rejecting the
Board’s findings and in effect entering its own con-
trary findings, the court exceeded its power under the
Wunderlich Act, 41 U.S.C. 321, which confines it to
substantial evidence review of administrative findings.
CORY BROLIN) CIrOsEe IN COA TKD
16
As is set out at length in this Court’s opinion in
United States v. Carlo Bianchi & Co., 373 Us,
709, the rationale of the Wunderlich Act, enacted in
1954, was to relieve certain restrictions on Court of
Claims review of the findings of government contra¢t
boards operating under the “disputes” clause of goy-
ernment contracts. These restrictions had last been
stated in this Court’s decision in United States y,
Wunderlich, 342 U.S. 98, 100. The dominant purpose
of the Act was to permit the Court of Claims to act
essentially as any other court reviewing the findings of
an administrative agency. 373 U.S. at 713-718. The
history of the Act in this Court shows, however, that
the Court of Claims has tended to assume authority
above and beyond that which reviewing courts gen-
erally exercise over administrative agencies; the gov-
ernment has come to this Court on three occasions in
order to protect that finality of administrative findings
which the Act does require. Thus, in Bianchi, supra,
this Court dealt with the practice of holding de novo
trials to determine whether administrative findings
were supported by substantial evidence. In United
States v. Utah Construction & Mining Co., 384 US.
394, this Court rejected the position of the Court of
Claims that in ruling on claims outside the scope of the
disputes clause it could ignore administrative findings
made under that clause in related claims under the
same contract. And in United States v. Anthony Grace
& Sons, Inc., 384 U.S. 424, this Court rejected the
assumption of authority to hold a de novo trial and
make findings where an administrative board had
erroneously failed to make them, and required the
BLEED THROUGH POOR COPY
17
gurt, in effect, to remand to the Board for such
proceedings.
In the present case, the court has avoided its obli-
gation to accord finality to administrative findings
by purporting to apply the substantial evidence rule,
but then ignoring substantial evidence in the record
supporting the findings. A decision involving applica-
tion of the substantial evidence rule to a particular
set of facts would not normally warrant review by
this Court. There has, however, been a pattern of sim-
lar decisions having the cumulative effect of a re-
assumption by the Court of Claims of a large measure
of the de novo review power which it lost when this
Court put an end to its practice of taking new evi-
dence. This case and Woodcrest Construction Co. V.
United States, 408 F. 2d. 406 (Ct. Cl.), in which the
government is filing a petition for certiorari together
with the present petition, are the latest in this series of
decisions. The approach taken in these cases should be
reviewed by this Court with a view to restoring the
proper balance between the Court of Claims and the
administrative contract boards in government contract
cases,
In the present case, the court overturned the admin-
istrative finding (that the contractor was partially at
fault for the delay “because it offered equipment
which did not meet the contractual requirements”
(App. 64)) by simply ignoring the evidence on
which it was based. In a footnote, the court brushed
this finding aside, stating that “[t]here is no showing
that plaintiff was responsible for any substantial
part of the delay” and that there is “no proof” that
COPY BOUND CLOSE IN CENTER
18
the equipment proffered by the contractor failed tp
meet the requirement of functional equality with the
equipment required by the specifications, (App.
30-31).”* It then proceeded to decide the case on the basis
of what was in effect its own finding that the contractor
was without fault. Establishment of such a new factual
premise was, however, beyond the authority of a review.
ing court in light of the facts supporting the Board’;
findings.
The Architect-Engineer, who disapproved the equip-
ment offered by the contractor, testified before the
Board that the equipment differed from the contract
0. 96-67 (June 20, 1969) (formal findings of con-
tracting officer “constitute a strong presumption or an evidentiary
admission of the extent of the government's liability [but] are
always subject to rebuttal”.).
Nor could the Court of Claims rationally conclude that the
Board found the government to be solely responsible for any
particular period of delay, in view of the Board’s finding that
the parties were “jointly responsible” and that it was “unable
to apportion the causes of delay.” (App. 64).
BLEED THROUGH POOR COPY
19
‘eoations in several respects having an important
pearing on the operation and maintenance of the Base
heating plant. Regarding the ash removal equipment,
he noted that the proposed equipment had not met
reliability requirements which seemed particularly
important in view of Alaska’s remoteness and the
harshness of its winters, and that it embodied a fea-
ture which—unlike complying equipment—would have
required replacement of parts every three or four
weeks (Tr. 482-483, 488, 524; Pl. Exs. 31, 33; App.
52-55). The coal scales submitted, unlike those specified,
had only a slight gradient between coal bunker and fur-
nace ,which would make it hard to feed in frozen coal
(Tr. 495-497, 499, 502-503), and used a type of conveyor
belt which could be repaired only by technicians who
would have to come from Seattle (Tr. 499). The combus-
tion air coils submitted would have presented a mainte-
nance problem during the coldest weather—the most
critical time—which the specified coils would not present
(Tr. 508), and were conceded not to meet the specifi-
cations by a representative of the manufacturer (Tr.
506-507). Although there was contrary testimony and
evidence tending to show that the equipment did con-
form to the specifications (Tr. 463-464; Pl. Exs. 6,
17, 19, 37, 39; Govt. Ex. E), the Board’s finding
accepted the Architect-Engineer’s testimony (App.
48-55). Moreover, the Board also found that the con-
tractor was in default in its work on the coal shed, where
the challenged equipment was not involved and only
three days’ delay was excusable (n. 11, supra; App.
58-59, 64). The court simply ignored this finding in
COPY BOUND CLOSE IN CENTER
20
concluding that the contractor was not culpably in
default when the contracting officer threatened
termination.
We do not contend that the court was required to
affirm the Board’s opinion, since certain portions of it
are confusing and might be read to indicate that the
Board was adopting an erroneous legal standard,”
But the proper remedy in such a case, where there is
substantial evidence to support the Board’s findings
under a proper legal approach, is to remand the case
for reconsideration under a correct standard; the
Court of Claims may not make its own findings on
conflicting evidence in the administrative record. See
United States v. Anthony Grace & Sons, Inc., 384
U.S. 424, 433, n. 10. In making such findings, the court
"The first two paragraphs of the Board's opinion have
some language which appears to ignore the “or equal” clauses
of the specifications (see n. 1, supra), which the Court of
Claims reads to require acceptance of equipment that is fune-
tionally equivalent to the equipment described in the specifica-
tions. See Jack Stone Co. v. United States, 170 Ct. Cl. 281,
344 F. 2d 370. However, the opinion does state: “Many of the
specified details may have been unnecessary. Others were clearly
desirable for this particular application, and some of these
details were not met by the offered equipment” (App. 62,
emphasis added). Moreover, Board Findings 7a and 7b are
clearly addressed to functional differences between the speci-
fied equipment and the equipment offered by the contractor
(App. 50).
The last paragraph of the Board’s opinion might be read to
indicate that any failure to meet the completion date would be
a default by the contractor, regardless of who was responsible
for the delay (App. 64). This would be an erroneous view of
the law, as the Court of Claims pointed out (App. 34).
BLEED THROUGH POOR COPY
21
dearly exceeded its review powers under the Wunder-
jich Act.”
There are disturbing indications that the decisions
of the Court of Claims here and in Woodcrest Con-
struction Co., supra, are not isolated examples. Since
this Court’s decisions in United States v. Anthony
Grace & Sons, Inc., 384 U.S. 424, and United
States v. Utah Construction & Mining Co., 384
US. 394, finally precluded the Court of Claims
from taking new evidence on questions within the
contract boards’ jurisdiction under the disputes clause,
that court has assumed a large measure of de novo
review power by simply reweighing evidence in ad-
ministrative records. A review of the reported de-
cisions of the Court of Claims between the date of
the Grace and Utah decisions (June, 1966) and the
current decisions (March, 1969) shows that of the
87 government contract cases in which decisions of
administrative contract boards were under review on
the basis of the administrative record, 35 cases (40%
%The court would have had authority under the Act to
interpret the contract in the light of the Board’s findings. But
it would have been unjustified in holding under the contract
that the government had no right to terminate the contract
in November, 1961 despite the contractor’s culpable default
because it, too, was responsible for some delay. Section 5-04 of
the contract specifications provided that “[n]o extension of
contract time will result from submission of material and
equipment data which does not fulfill the requirements.” Sec-
tion 5 of the contract provided that “(t]he right of the Con-
tractor to proceed shall not be terminated * * * because of any
delays in the completion of the work due to unforeseeable
causes beyond the control and without the fault or negligence
of the Contractor * * *.” (App 34).
= mine + BA ASS ee,emhlC KM FlhlCO Me oO hUCr KC lL ee eo oe eee
iemmeindnaaaie
22
of the total) were reversed in whole or part. It is
difficult to tell how many of the reversals were based
on a reweighing of evidence in the administrative
record, since the court’s opinions, as here, do not al-
ways reveal the extent of the evidence supporting the
administrative decision, and frequently treat as ques-
tions of law (not subject to Wunderlich Act finality)
issues which involve a large factual element.” How-
ever, the court has clearly reviewed the evidence and
rejected administrative factual findings in at least
13 cases (15% of the total cases decided, and 37%
of the reversals) ;” of these 13, 6 were decided in the
last 6 months of the period surveyed, representing
40% of the 15 cases decided in those months (October
1 For example, the court so treated the issue of duress here
(App. 35). In some cases, it goes so far as to enter formal or
additional findings of fact. Kraus v. United States, 366 F. 2d
975; Bolander v. United States, 186 Ct. Cl. 398; KECO Indus-
tries v. United States, 364 F. 2d 838. Making such findings of
fact in the course of reviewing an administrative record is
inconsistent with the limitations on the court’s role underlined
in Utah and Grace.
2° United Contractors v. United States, 177 Ct. Cl. 151,
368 F. 2d 585; Johnson & Sons, Inc. v. United States, 180 Ct.
Cl. 969; Loral Electronics Corp. v. United States, 181 Ct. Cl.
822; S. S. Mullen Inc. v. United States, 182 Ct. Cl. 1, 389
F. 2d 390; Sundstrand Turbo v. United States, 182 Ct. Cl. 31,
389 F. 2d 406; Centre Manufacturing Co. v. United States, 183
Ct. Cl. 115, 392 F. 2d 229; Morrison-Knudsen Co. vy. United
States, 184 Ct. Cl. 661; D & L Construction Co. vy. United
States, 185 Ct. Cl. 736, 402 F. 2d 990; Bell v. United States, 404
F. 2d 975; L. W. Foster Sportswear Co. vy. United States, 405
F, 2d 1285; J. D. Hedin Construction Co. v. United States, 408
F. 2d 424; Woodcrest Construction Co. vy. United States, 408
F. 2d 406; Urban Plumbing and Heating Co. v. United States,
408 F. 2d 382.
BLEED THROUGH POOR COPY
23
1968 through March 1969)." While it would unduly
jengthen the petition were we here to discuss the
merits of each of these cases, we believe they bear
out our concern that, as shown by the opinions in
Woodcrest Construction Co. and the present case, the
Court of Claims is not heeding the limitations in-
herent in the substantial-evidence standard of review
prescribed by the Wunderlich Act.” The effect is to
transfer to the Court of Claims the administrative
fact-finding function.
CONCLUSION
The petition for a writ of certiorari should be
granted.
Respectfully submitted.
ErwIn N. GRISWOLD,
Solicitor General.
WituiaM D. RUCKELSHAUS,
Assistant Attorney General.
Rosert V. ZENER, Attorney.
Juty 1969.
1D & L Construction Co. v. United States, supra; Bellv. United
States, supra; L. W. Foster Sportswear Co. v. United States,
supra; J. D, Hedin Construction Co. v. United States, supra;
Woodcrest Construction Co. v. United States, supra; Urban
Plumbing and Heating Co. v. United States, supra.
2Gamer, After Two Years: Cases in the Court of Claims
Since Utah and Grace, Public Contract Newsletter, vol. 3, No.
3 (July, 1968), surveys the post-Grace and Utah decisons of
the Court of Claims as of April, 1968. Commissioner Gamer
concludes: “I found that the Boards were sustained in whole
or in part in 41 cases * * * and that they were reversed in
whole or in part in 23 cases. * * * Of the 23, six were reversed
for lack of substantial evidence.” Since Commissioner Gamer’s
survey, the trend of factual reversals seems to have accelerated.
COPY BOUND CLOSE iN CENTER
BLEED THROUGH POOR COPY
APPENDIX A
§n the Bnited States Court of Claims
No. 70-67
(Decided March 14, 1969)
URBAN PLUMBING & HEATING CO., AN OREGON
CORPORATION v. THE UNITED STATES
Warde H. Erwin, attorney of record for plaintiff.
James A. Pemberton, Jr., with whom was Assistant At-
torney General Edwin L. Weisl, Jr., for defendant.
Before Cowen, Chief Judge, Laramorr, Durree, Davis,
Coutins, SKELTON, and Nicnors, Judges.
ON PLAINTIFF'S MOTION AND DEFENDANT'S CROSS-MOTION FOR
SUMMARY JUDGMENT
Sxz.ton, Judge, delivered the opinion of the court:
The plaintiff, Urban Plumbing & Heating Company, is
an Oregon Corporation. Jc entered into a contract with the
Department of Defense, Alaska Air Command, of the United
States on June 23, 1961, in which it agreed to make certain
modifications in the centval heating and power plant at
Eielson Air Force Base, Alaska, for the sum of $487,775."
The contract required the work to be completed within 120
days after June 30, 1961, the day that notice to proceed was
given. Performance was to commence about July 1, 1961, and
the project was to be completed by October 28, 1961, well in
advance of the usual beginning of severe winter weather in
1 Contract No. AF 65(508)-1505.
CADDY BTIinnt CTMce 8) CoarTree
26
Alaska. In fact, the expected winter weather made it neces.
sary for the project to be completed by October 28, 1961,
because much of the work had to be done inside the central]
heating and power plant, and, while the work was going
on, the plant had to be shut down. Since the plant supplied
the heat and power for the air base, it could not be shut down
during the severe Alaskan winter season. Under these circum.
stances, time was of the essence, because after the winter
weather set in, it would be impossible for the plaintiff to work
effectively on the project, either inside or outside of the plant,
The contract required the plaintiff to submit to the archi.
tect-engineer (hereinafter called AE) of defendant for ap.
proval or rejection the products it proposed to use in the
project. The contract specified certain named brands, “or
equal,” of the items to be supplied by the contractor. The
contractor was given the right to submit materials and equip-
ment it proposed to use other than the named brands, but
which it considered equal to those named. Of course, this
arrangement required the defendant to promptly name or
appoint an AE, otherwise the contractor would not have any-
one to whom it could submit its products for approval.
The defendant delayed the appointment of the AE for a
period of time. The defendant says the delay in the appoint-
ment was 18 days, but plaintiff contends it was 38 days and
that it did not have notice of the appointment for 4 more
days. We do not have to resolve this time dispute between
the parties. However, we do take note of the fact that there
was a substantial delay by defendant in appointing the AE.
In our opinion, this delay materially affected the progress
of the work, but, as will be seen below, it was not the only
delay on the part of the defendant that the contractor
encountered.
After the AE was appointed, the contractor submitted to
him for approval samples of the products it proposed to use,
as required by the contract. The contractor says these prod-
ucts were equal to or better than the named brands set forth
in the contract. The AE delayed approval or rejection of the
submitted items. In the meantime, plaintiff had tentative
arrangements with suppliers of the products to furnish the
Pt Set FLIF IIL OUD MmMbD rma DY
—
27
items for the project, but the suppliers would not manufac-
ture them until they were approved. Time was passing and
both parties were getting nervous about the progress of the
project. After a substantial delay, the AE rejected the prod-
ucts submitted by plaintiff as not meeting the specifications
of the contract. There is a dispute between the parties as to
how long the AE delayed making his decision, but it appears
to be undisputed that he did wait an unreasonable length of
time to make a decision and that this delayed the contractor
in the performance of the work. The contractor was required
to order the named brands of items listed in the contract
after the AE rejected others submitted by it, and this required
more time.
On August 30, 1961, the contracting officer notified plain-
tiff in writing that the Government considered plaintiff's
progress @ condition that was endangering the performance
of the contract, and that unless the condition was cured
within 10 days, the Government “may terminate subject con-
tract for default.” The plaintiff answered by its letter of
September 7, 1961, in which it excepted to the Government’s
notice and pointed out the delays that had been caused by the
Government. It asked for a time extension of 90 days because
of these delays. The contracting officer answered this request
in writing by letter of September 26, 1961, in which he ad-
mitted “since some time delay was caused by disapproval of
material an extension of 30 days is considered fair and reason-
able to cover the delay involved.”
The contractor rejected the offer of a 30-day extension by
its letter of October 18, 1961. It again detailed the delays
caused by the Government and requested a time extension of
120 days.
The contracting officer answered this request in writing on
November 13, 1961, in which he said, among other things:
However, since the time required by the Government
to approve or pape, data submitted was over 30
days and in part is beyond the control of the contractor,
a reasonable time extension is considered in order. In
accordance with General Provision Clause 5(c) a time
extension of 69 days (58+11) is considered the time
delay which was beyond the control of the contractor.
28
As an alternative, the contracting officer offered an amend.
ment to the contract which would give the contractor », 245
day extension (to June 30,1962) provided it followed the,
work schedule prescribed by the Government and agreed to
the following clause in the amendment ; !
This supplemental agreement neither increases or {sic
darcendastcamraas y
This extension would give the contractor 120 days after the
winter was over to finish the project. This was equal to the
ing statement :
The above extension of time is granted due to adverse
weather conditions and Government delay in approval
of data.
The contractor finished the work within the 245 day time
extension granted in the supplemental agreement. However,
its costs in doing so were $79,905.22 more than the original
contract price. An audit by the Air Force confirmed the cor-
rectness of this figure. The contractor presented his claim of
$79,905.22 in extra costs, plus overhead of 15 percent of the
total contract cost of $567,680.22 amounting to $85,152.03,
plus profit of 10 percent on the total cost and overhead
($652,832.25) amounting to $65,283.25, plus cost of its bond
(01 percent of $718,115.47) in the sum of $7,181.15, plus taxes
in the sum of $1,795.38, making its total claim $239,316.98
(the difference between the original contract price of $487,-
775 and the final costs, plus overhead, profit, cost of bond and
taxes as set forth above in the total sum of $727,091.98).
29
The contracting officer rejected plaintiff's claim and it
ed to the Armed Services Board of Contract Ap-
peals (hereinafter called the Board), which also refused
plaintiff’s claim in its entirety in an opinion dated Decem-
ber 30, 1966, 66-2 BCA 96062. Its motion for reconsideration
was denied by the Board on February 8, 1967. The plain-
tiff filed suit in this court on March 13, 1967, and asserts the
same claim that he made to the contracting officer and to the
Board. The defendant filed an answer contesting plaintiff's
claim. Both parties have filed motions for summary judg-
ment which we will now consider. __
- The contract involved here contained the standard Sus-
pension of Work clause. Therefore, plaintiff's delay claim is
redressable at the administrative level. United States v.
Anthony Grace & Sons, Inc., 384 U.S. 424 (1966). The
plaintiff has exhausted his administrative remedies, except
for the amount of his damages, and the case is now before us
for review. The defendant insists that since this case falls
within the purview of the Wunderlich Act, we are bound by
the decision of the Board. It contends that the decision of the
Board is supported by substantial evidence, is neither arbi-
trary, capricious, nor grossly erroneous, and that its deter-
minations of questions of law are correct. The plaintiff, on
the other hand, takes the opposite position on all of these
points. It especially urges that the » sion of the Board on
questions of law is erroneous.
Both plaintiff and defendant have devoted most of their
briefs to the question of whether or not there was an accord
and satisfaction of all claims of the parties, past, present,
and future, by their signing the supplemental agreement on
November 16, 1961, wherein the plaintiff was given a time
extension of 245 days to complete the contract and wherein
it was stated that “This Supplemental Agreement neither
increases or [sic] decreases contract price.” The plaintiff says
that the word “costs” was changed to “price” at its request
and that it understood the meaning of the provision as
changed to be that it would be entitled to collect additional
costa if any were sustained by reason of the time extension.
*ASBCA No. 9881, appeal of Urban Plumbing & Heating Company, under
Contract No. AF 65(503)-—1505.
358-025—69—-3
— ; —
30
Consequently, plaintiff says there was no accord and gatis.
faction of anything.
The defendant says that plaintiff was in default at the tims
the amendment was signed and it did not have to grant the
time extension but could have defaulted the plaintiff; thet
the giving of the time extension was consideration for, and aa
accord and satisfaction of, all of plaintiff's claims, and that
this was the plain meaning of the word “price” in the amend-
ment. The Board agreed with the defendant.
It is our opinion that it is not necessary to reach the accord
and satisfaction question in disposing of this case.
We start with the threshold question of whether or not the
Government delayed the contractor, and, if so, how much
and what were the consequences of such delay. The first part
of this question is easily answered, because it is undisputed
that the Government did delay the contractor. The contract-
ing officer admitted this delay in his letters of September 26
and November 13, 1961, mentioned above. The amendment
(Supplemental Agreement) signed by the parties on Novem-
ber 16, 1961, acknowledged such delay on the part of the
Government when it provided that the time extension was
granted “due to adverse weather conditions and Government
delay in approval of data.” Also, the Board found that the
Government delayed the contractor. It stated in its opinion,
“The respondent did unreasonably delay acting upon these
submittals. * * * there is no reasonable excuse for de-
laying official action on the Durabilt submittal until
29 August * * *.” Again, the Board said: “The parties were
* There is no showing that plaintiff was responsible for any substantial
of the delay. As indicated in the quotation from its opinion set
mediately above in the text, the Board erroneously assumed that the
part
H
Fz,
g
Pie
|
g
s
i
E
ae
eccount of the contractor’s express right under the contract to propese for
approval other materials and equipment which it considered equal to the
brands specified. These “or equal” provisions did not mean that
substitutes had to comply with every detail of the specifications (which
il
—
How much delay was caused by the Government is more
difficult to determine, but it seems clear that it was at least
69 days. In the contracting officer’s letter of November 153,
1961, to the contractor, he said that the records of his office
showed, “81 days government delay on disapproval of
Richardson Scales & Combustion Coils” and “58 days gov:
ernment delay on disapproval of Durabilt Equipment.” In
the same letter he said “* * * a time extension of 69 days
(58+11) is considered the time delay which was beyond the
control of the contractor.” The Board, in commenting on the
69 days offered by the contracting officer as a time extension
said, “This was apparently computed as the total lapsed time
between the notice to proceed and appellant’s receipt of the
rejection of the Durabilt ash removal equipment.” The Board
went on to say: “The contracting officer offered 69 days time
extension because of the delay in approvals. * * * we can-
not find that it was not as much as was due for excusable
cause.” We regard this as a finding by the Board that the
Government did delay the contractor 69 days. If it could be
said that the Board did not so find, then we conclude that
the evidence on the matter was such that as a matter of law
the Board could have made only one finding of fact with
respect to it. Under these circumstances, we are authorized to
make the finding on the question. Maxwell Dynamometer Co.
v. United States, 181 Ct. Cl. 607, 631, 386 F. 2d 855, 870
(1967). Accordingly, we find that the contractor was delayed
69 days by the Government. -
We now consider what effect this 69 day delay had on the
performance of the contract by the contractor. We agree with
the contractor that under the conditions existing in Alaska,
there is a vast difference between 69 days in the summer and
fall when working conditions are favorable and 69 days in
based on particular brands, without naming them). The “or equal” clauses
were designed to establish a “standard of equality” and meant only that the
proffered “deviation” had to function as well as the specified equipment. See
Jack Btone Co. v. United States, 170 Ct. Ci. 281, 844 F. 24 870 (1965). The
Board found that the plaintiff's proposals did not meet every single detail of
the specifications, but the Board never found, and there is no proof, that these
proposals failed to meet the “or equal” standard in the broader sense in which
it should have been construed, On the record, therefore, the plaintiff cannot
be held responsible for offering “equipment which did not meet the contractual
requirements.”
the wintertime when little, if any, work can be done. This wag
particularly true in this case, because the facts show that
most of the work had to be done inside the heating and power
plant. This plant bad to be shut down in order for the plain.
tiff to work in it. The Government could not allow it to te
shut down in winter, because it supplied heat and power for
the air base. If the plaintiff worked at all inside the plant
while it was in operation, there was danger of an explosion
of the combustible coal dust found inside. For all these rea.
sons, the plaintiff could not work inside of the plant
the winter months. It could not work outside the plant in
the winter because of the extreme cohd, snow, and ice
in that area. The record shows that the winter of 1961-49
was a severe one in Alaska, with temperatures below zero
much of the time. By the time the amendment to the contrac
was signed on November 16, 1961, the temperature had been
as low as 20 degrees below zero and bitter cold prevailed
most of the time.
The parties intended that the project be completed by
October 28, 1961, before the onset of the Alaskan winter. The
plaintiff did not contract to work under conditions which
exist during the winter in Alaska. The Government delayed
the work of the contractor 69 days, which prevented its com-
pletion of the project before winter. In other words, the de-
lay caused by the Government would have required the con-
season was impossible. Even the Board said: “The 69 days
would have been useless * * *.” It is obvious that the Gov-
ernment realized the situation when it asked the contractor
to accept a 245 day time extension, which would extend the
time of performance through the winter and allow it 120 days
theres fter to finish the project.
It is clear that at the time the Government made the three
alternative propositions to the plaintiff on November 16, 1961,
it had delayed the plaintiff until the date for the completion
of the contract (October 28, 1961) had passed, through no
fault of the contractor. The offer of a 69 day extension at
that time meant nothing whatsoever, because even if it had
been granted and accepted, the Government would not have
BLEED THROUGH POOR COPY
weather.
time of year was an
as far as the contractor was
left of the alternatives was the demand of
34
mination, the contractor is entitled to an equitable adjust.
ment in accordance with the Termination for Convenience
clause of the contract (paragraph 31). See Litchfield Mfg,
Corp. v. United States, 167 Ct. Cl. 604, 613, 388 F. 2d 94, 95
(1964) ; Bailey Specialieed Buildings, Ino. v. United States,
Ct. Cl. No. 90-67, decided December 13, 1968.
The contract, itself, prohibits termination for default by
the Government under the circumstances of this case, except
for the convenience of the Government. Paragraph 5 of the
contract provides:
5. TERMINATION FOR DEFAULT—DAMAGES
7 oe eerie
(c) The ne right of the Contractor t shall not
be termi fet Oo rate treet (a). nor
the Contractor charged with liqui ahd
ages, as provided in paragraph ghey = because of
any delays in the completion of the work due to unfore-
seeable causes beyond the control and without the fault
or negligence of the Contractor, incl » but not re-
stricted to, * * *, acts of the G orn om ater
sovereign or contractual capacity, unusually
severe weather, * * *. [Emphasis supplied)
time specific! in this contract, or any extension thereof, or falls to complete
said work within auch time, the Government may, by written notice
BLEED THROUGH POOR COPY
es
The Board decided that the contractor was in default and
thst in threatening to terminate the contract for default, the
contracting officer was threatening to do only what he had a
scht to do. We agree in part and disagree in part with this
decision. These are questions of law and we are not bound by
the decision of the Board with respect to them. T.C. Bateson
Constr. Oo. v. United States, 162 Ct. Cl. 145, 187, 319 F. 2d
135, 160 (1963). We agree that the Board correctly decided
that the contractor was in default on November 16, 1961,
any clear-cut definition, and the courts have stated that
its application must of necessity “pene upon the cip.
cumstances of each individual case. Morrill v, Amoskeag
Sav. Bank, 9 Atl. 2d (N.H.) 519, 524. An examination of
the cases, however, makes it clear that three elements are
common to all situations where duress has been
to exist. These are: (1) that one side involuntarily ac.
cepted the terms of another; (2) that circumstances
permitted no other alternative; and (3) that said circum.
a ee ~ result - omaha 3 the spa
- United States v. Bethlehem
B80, 301; French Schoemaker, 14 Wall. (US) 34
332. In order to substantiate the al ation of eco
duress or business compulsion, the plaintiff must go be.
ond the mere showing of a reluctance to accept and of
ial embarrassment. There must be a showi of acts
on the part of the defendant which produced these
factors. The assertion of duress must be proven to have
been the result of the defendant's conduct and not by the
plaintiff’s necessities, * * *
We think the three elements common to the duress cases
quoted above are present in the instant case.
The Board found that no duress existed, citing v.
United States, 67 Ct. Cl. 348, 381 (1929) for the proposition
that in order to constitute duress there must be something
present other than threatened financial disaster. While it is
true that the court in that case indicated by dicta that the
fact that a contractor is in a bad financial condition for which
the Government is in no way responsible, at the time an agree-
ment is signed, is not enough to constitute duress, this is
not the situation here. The Board cites Commonwealth Engi-
neering Co. of Ohio v. United States, 148 Ct. Cl. 330, 180 F.
Supp. 396 (1969), cert. denied, 364 U.S. 820, in supPport of its
holding “where the contracting officer threatens default ter-
mination, and the contractor is actually in default, the con-
tracting officer was threatening to do only what he had a right
to do. This is not duress.” It is at once apparent that this is
not the situation here. The cases cited by the Board are clearly
distinguishable from our case and are not controlling. We
are not bound by this decision of the Board on questions of
law.
On the question of duress, the instant case is governed by
the principles announced in the decisions in Aircraft As-
BLEED THROUGH POOR COPY
37
sciates & Mfg. Oo. v. United States, 174 Ct, Cl. 886, 357 F. 2d
373 (1966) ; James Shewan & Sons, Ine. v. United States, 73
Ct. Cl. 49 (1981); Universal Sportswear, Ine. v. United
States, 145 Ct. Cl. 209, 180 F. Supp 391 (1959) ; Struck
Constr. Co. v. United States, 96 Ct. Cl. 186 (1942), and simi-
lar cases.
In Aircraft Associates & Mfg. Co. v. United States, supra,
the plaintiff bid on the purchase of a number of discarded
airplanes from the Government for the purpose of salvaging
aluminum from them. After plaintiff made its bid and before
the planes were delivered to it as the successful bidder, the
Government removed large quantities of aluminum parts
from the planes. When the plaintiff learned of this and com-
plained, the contracting officer refused to allow the plaintiff
to continue with the contract, locked the gates to the air base
to keep plaintiff's workmen out, and threatened to terminate
the contract for default unless plaintiff signed an agreement
releasing his claims for the missing parts. At that point, the
plaintiff was behind in its payments to the Government, be-
cause the Government had denied it access to the planes, so
that it was unable to sell the parts it had salvaged, and, ac-
cordingly, it was in technical default through no fault of its
own. In this situation, the plaintiff signed the release, finished
the contract, and then sued the Government for the value of
the missing parts, contending that it signed the release be-
cause of duress and coercion by the Government. We held
that the facts showed that the contracting officer was guilty
of duress and coercion, and we entered judgment for the
plaintiff saying:
When all of the facts recited above are coupled with
the exclusion of plaintiff and its workmen from the base
= oe paca rere of the Ky 4 r) ity plaintiff
n vernment, we con-
clude that t the paar carp SF men by the Kind of duress
which renders the release invalid and not binding upon
the plaintiff. James Shewan & Sons v. United States,
73 Ct. CL 49 (1931) and Struck Construction Company
v. United States, 96 Ct. Cl. 186 (1942). As the court
stated in the Shewan case at page 93 :
In cases of this kind the defendant should not be
permitted to take advantage of its own failure to
358-025—69—_4
38
rm & oe © contract obligation in order to
exact from the other — wpe wee
render of rights which he would not otherwise be
compelled to give up.
In that decision the court pointed out that settlements
and payments exacted by officials of the Government
without lawful authority and in arbitrary Rp oe to
Ww. ve to financial disaster
ioe box aaee ee senaeween Gnenitinas ter the Su-
preme Court. Thus, in Robertson v. Frank Brothers Co,
132 US. 17, 23 (1889), the Supreme Court stated :
When the duress has been exerted by one clothed
with official authority, or exercising a public em-
loyment, less evidence of compulsion or pressure
Gretel an Wines tn dba exacts 1 z
or ® common carrier excessive charges. But the
— is applicable in all cases according to the
re and exigency of each. /d. at 898.
The contractor was awarded a contract by the Government
in the case of James Shewan & Sons, Inc. v. United States,
supra, to repair and dry-dock ships belonging to the Gov-
ernment. The contract specified that the contractor would be
paid monthly, but the Government did not make the payments
on time and many of them were long overdue. The Govern-
ment suddenly terminated the contract while the work was
in progress. A year and seven months later, the Government
offered to pay the contractor $850,427.10 on the long overdue
bills, on condition that the contractor sign a full release of all
other claims. The contractor protested because the amount
offered was far below what it was entitled to receive. Much
of the amount due was for actual outlay of labor and ma-
terials on the part of the contractor, all of which was known
to the Government. There was at least $250,000 in pending
claims over and above the amount the Government offered.
The contractor owed the bank and its income tax, which it
could have paid but for the delinquency of the Government.
Also, the Government threatened to turn the money appro-
priated by Congress for this work back to the Treasury if the
contractor did not sign the release, which would require the
contractor to procure the passage of a special act of Congress
for it to get its money. In this situation, and faced with these
threats, the contractor signed the release under protest. It
BLEED THROUGH POOR COPY
—_—
39
Jater sued for the balance of the money due it. We held that
the release was procured by duress and awarded the plaintiff
a judgment, We said in that case:
* * © The rule as to duress, indicated by the trend of
authorities, has receded from its ancient strictness and
has been accepted in numerous instances wherein it ap-
that the parties were not on equal terms and no
alternative existed except to submit to an illegal exaction
or suffer irreparable injury to business.
The Supreme Court in Swift hm v. United
States, 111 U.S. 22, 28-29, a case invo wey Bowe illegal
exaction by officials of the Internal Revenue Department,
used this significant language:
“The jes were not on equal terms. The appellant
had no choice. The only alternative was to submit to an
illegal exaction or discontinue its business. It was in
the power of the officers of the law and could only do as
they required. nom, | paid or other value tome with,
under such pressure, has never been regarded as a volun-
tary act within the meaning of the maximim, volenti non
fit mjuria.” Id, at 83-84.
* * : et * *
* * * The contract provided that the Navy Deportes
should pay for the work done within thirty ays. The
defendant did not comply with this provision and it was
only because of this, which resulted in the plaintiff being
faced with financial disaster and irreparable loss, that
the defendant was able by its failure to fulfill its _
ment to exact from the plaintiff an unconscionable re-
lease of all claims ess of their merit. But for the
failure of the defendent to fulfill its definite and clear
romises under the contract, plaintiff could very well
ve refused to sign the release. In cases of this kind the
defendant should not be permitted to take advantage of
its own failure to perform a solemn contract obligation
in order to exact fom the other parties to the contract
a surrender of rights which he would not otherwise be
compelled to give up. Jd. at 93.
+ * *
* * * It was the department’s duty under the contract
to make final payments for work Parte when the
work was completed on each vessel designated and take a
release as to that vessel, and if the department had ex-
hibited the same degree of zeal in making settlements, as
the contract required, as it did exhibit in procuring the
final release involved, this plaintiff would not have bone
40
brought to the brink of bankruptcy and compelled by a
chain of circumstances, not of its own making, to do
what it did. Jd. at 95.
We hold that the facts in the instant case show that the
plaintiff signed the supplemental agreement because of the
duress and coercion on the part of the Government. Conse-
quently, the agreement is not binding on the plaintiff.
We conclude that the rights of the parties must be deter.
mined without regard to the supplemental agreement. This
being true, the Suspension of Work clause (paragraph SP
1-12) of the contract becomes important.* This clause pro-
vides that the contractor shall be entitled to an equitable
adjustment in the contract price if a suspension is for an
unreasonable length of time not due to the fault or negligence
of the contractor and causes additional expense or loss to the
contractor. It is our opinion that under the facts and cir-
cumstances of this case the delay was for an unreasonable
length of time, was not due to the fault or negligence of the
contractor, was for the convenience of the Government, and
caused additional expense or loss to the contractor. All of the
prerequisites for the issuance of a suspension of work order
by the contracting officer were present. We think it should
have been issued.
The situation here is much like that in the case of 7. 0.
Bateson Constr. Co. v. United States, supra. There the Gov-
ernment delayed the contractor 38 days by causing a strike
when it required the contractor to use non-union employees.
The contractor sued for delay damages, claiming that the
Government should have issued a suspension of work order
and made an equitable adjustment of the contract price. We
said in that case:
*SP 1-12 SUSPENSION OF WORK
The Contracting Officer may order the Contractor to suspend all or any
part of the work for such period of time as may be determined by him to be
necessary or desirable for the convenience of the Government. Unless such
suspension unreasonably delays the progress of the work and causes addi-
tional expense or loss to the Contractor, no increase in contract price will be
allowed. In the case of suspension of all or any part of the work for an un-
reasonable length of time, causing additional expense or loss, not due to the
fault or negligence of the Contractor, the Contracting Officer shall make an
equitable adjustment in the contract price and modify the contract
accordingly.
BLEED THROUGH POOR COPY
—
41
In this posture of the case, our opinion is that the
rovisions of Article GC-11 [suspension of work clause]
are brought into — The Government’s action
demonstrates that, knowing all the consequences, its
determination to use civil service employees which
caused the strike could only be for the convenience of the
Government. Under these circumstances, when it did
cause delay and additional expense and since it was not
the fault of the contractor, we think the contracting
officer should have suspended the work and an equitable
adjustment of the contract price should have been made
under Article GC-11. Failing in this, we think the Gov-
ernment is liable. /d. at 187.
We reach the same conclusion here that we did in that case.
The contracting officer should have issued a suspension of
work order and made an equitable adjustment of the contract
price with the contractor. Since this was not done, the Gov-
ernment is liable.
The liability of the Government here where no suspension
of work was issued, but should have been, is the same as it
would have been if it had been issued. A case that illustrates
the latter situation is the case of Morrison-Knudsen Co. v.
United States, 184 Ct. Cl. 661, 397 F. 2d 826 (1968). That
case, like the one before us, involved a contract for work on
a project in Alaska, The contractor was required to do the
grading, drainage, and related construction work on a 45
mile segment of an existing roadway. The eontract required
the work to be completed by November 15, 1954, before the
onset of severe winter weather in that part of Alaska. Dur-
ing the progress of the work, the Government made various
changes in the contract which delayed the contractor. On Oc-
tober 26, 1954, the Government issued a suspension of work
order on the project until further notice because of severe
weather conditions which had frozen the subgrade and had
produced six inches of snow on the roadway. The work was
resumed the following spring and finished in about three
weeks. The contractor contended that he could have com-
pleted the contract on time if the Government had not de-
layed him. He sued for damages resulting from the delay
and suspension of work. We held in that case:
* * * Completion of the contract having thus been
delayed through fault of the defendant, it is liable for
42
damages incurred by plaintiff as a result of
tion of the work info the 1955 ceaakroction wttan
eg Jefferson Construction Co, v. United States, 183 Ct,
Cl. 720, 392 F. 2d aed gl George A. Fuller Oo. vy,
United States, 108 Ct. Cl. 70, 94, 69 F. Supp. 409, 411
1947) ; Donald M. Drake Co. v. United States, 158 Ct,
433, 440 (1961); S Delays-Damages on Gov-
ernment Contracts, 26 G.W.L. Rev. 505, 518 et seq.
We think these principles are applicable to the case before
us even though the Government did not stop the work of the
contractor by a suspension of work order as authorized by
the contract. It accomplished the same purpose for its own
convenience by forcing the contractor to agree to the supple.
mental agreement by the coercion and duress discussed above,
The plaintiff is entitled to recover whatever damages it suf-
fered by reason of such delay.
We come now to consider the question of equitable adjust-
ment or damages claimed by the contractor. It has presented
its claim on the basis of the total cost theory." In this connec-
tion, it shows that it spent $79,905.22 more than the original
contract price of $487,775 because of the delay aforesaid. It
contends that it is entitled to recover this amount, plus over-
head and profit, on the original contract price, as well as on
the additional costs, plus the cost of its bond and taxes, all
in the total sum of $239,316.98 over and above the original
contract price of $487,775. The defendant admits that an Air
Force audit shows that plaintiff spent $79,905.22 more than
the contract price of $487,775, but says these are only total
cost figures and denies that plaintiff is entitled to recover that
much even if it is entitled to a recovery in some amount. It
points out that the Board made no determination as to the
amount of plaintiff’s damages and that under the Wunderlich
Act, damages must be found in the first instance by the Board.
We agzee with the defendant. The amount of an equitable
adjustment is a pure question of fact. United States v. Calla-
han Walker Constr. Co., 317 U.S. 56, 61 (1942). The total
cost theory has never been favored by this court if there is
any other way to determine the amount of the equitable ad-
7 See Rubin, The Total Cost Method of Computing An Equitable Adjustment-
An Analysis, 26 Fed. B.J. 308 (1966).
BLEED THROUGH POOR COPY
43
j t. We said in Phillips Constr. Co. v. United States,
194.Ct. Cl. 249, 894 F’, 2d 884 (1968) :.
* * * [T]his method is not preferred by the court and.
will be used only in an extreme case. The reasons for its
reluctance to apply the total cost approach are explained
by the court in a much-quoted excerpt from its opinion
in F. H. McGraw & Oo. v. United States, 131 Ct. Cl. 501,
130 F. Supp. 894 (1955). The court said: :
This method of proving is by no means satis-
factory, because, among other it assumes plain-
tiff’s costs were reasonable and that plaintiff was not
responsible for any increases in cost, and because it as-
sumes plaintiff’s bid was accurately computed, which is
not always the case, by any means.
Our opinion in Great Dredge & Dock Co. v.
United States, supra, [119 Ct. Cl. 504, 96 F. Supp. 923
(1951), cert. dened, 342 U.S. 953 (1952 ] was not in-
tended to give approval to this method of proving dam-
age, in an extreme case and under proper safe-
guards, 131 Ct. Cl. 511, 180 F. Supp. 400. Jd. at 260-61.
Again, we held in WRB Corporation v. United States, 188
Ct. Cl. 409 (1968) :
For claims 22 and 26, acer submission is the
“total cost” standard (the difference between actual ex-
and bid or estimated costs). This theory has never
favored by the court and been tolerated onl
when no other mode was available and when the reliabil-
ity of the supporting evidence was fully substantiated.
See 7'wv Ine. v. United States, 180 Ct. Cl. 1010
1025-26, 389 I. 2d 1007, 1015 (1967) ; J. D. Hedin Con-
struction Co. v. United States, 171 Ct. Cl. 70, 86-87, 347
F. 2d 235, 246-47 (1965) ; River Construction Corp. v.
United States, su 159 Ct. Cl. at aes 270-71;
Oliver-Finnie Co. v. United States, 150 189, 200,
979 F. 9d 498, 505-06 (1960); F. H. McGraw & Co. v.
United States, 181 Ct. Cl. 801, 510-12, 180 F. Supp. 394,
on proof that (1) the nature of the particular losses
make it impossible or highly impracticable to determine
them with a reasonable degree of accuracy; (2) the
plaintiff's bid or estimate was realistic; (3) its actual
for the added expenses. See J. D. Hedin Construction Co.
v. United States, supra, 171 Ct. Cl. at p 86-87, 347
F. 2d at pages 246-47 ; Oliver-Finnie Co, v. United
44
States, su; 150 Ct. Cl. at pages 197, 200, 279 F.
at pages 05-06; F. H. McGrew a Co. v. United States
su 131 Ct. Ci. at page 511, 130 F. Supp. at page 400,
Id. at 426.
It is clear that we cannot make initial findings of fact on
the amount of plaintiff’s recovery. The case must be returned
to the Board so that it may make this determination. United
States v. Anthony Grace & Sons, Inc., 384 U.S. 424, 480-31
(1966).
Accordingly, we hold that plaintiff is entitled to recover
on its claim for delay damages and judgment is entered for
plaintiff thereon, and to that extent its motion for summary
judgment is granted, the amount of recovery to be deter-
mined in the first instance by the Armed Services Board of
Contract Appeals. Proceedings in the case in this court are
hereby suspended for a period of 120 days from this date for
such Board determination, and the case is returned to the
Board for this purpose. The plaintiff will comply with Rule
100 and the appropriate provisions of the General Order of
the court of April 1, 1968, implementing it. Upon the con-
clusion of the proceedings of the Board, the plaintiff will
report the result to the court and the parties will take further
action for the final disposition of the case in this court. The
motion for summary judgment of defendant is denied.
APPENDIX B
ARMED SERVICES Boarp oF CoNTRACT APPEALS
WASHINGTON, D.C.
ASBCA No. 9831
Appeal of
Ursan PLuMBING AND HeEatinG Co.
Under Contract No. AF 65(503)-1505
Appearances for the Appellant: Warde H. Erwin,
Esq., Portland, Oregon.
Appearances for the Respondent: Colonel David C.
Yeoman, USAF, Chief Trial Attorney, Major Eugene
M. Solimine, USAF Trial Attorney.
OPINION BY Mr. ANDREWS
The appellant contends that its work was delayed,
extended, and interfered with as the result of the
respondent’s tardy review of submittals and improper
rejection of equipment offered under the contract. The
claim is in the amount of $239,316.90, which is com-
puted by adding to its total direct costs of perform-
ance, assumed percentage mark-ups for overhead,
profit, bond premiums, and Alaska business tax, and
subtracting therefrom the contract price.
Findings of Fact
1. The contract was awarded to the appellant on
23 June 1961 for modification of the central heating
and power plant at Eielson Air Force Base, Alaska,
(45)
46
at a price of $485,704.00. It specified that the
ent must issue the notice to proceed by 30 June 196],
and appellant must complete the work within 120 cal.
endar days thereafter. The notice to proceed was
actually issued on 30 June 1961, thus fixing the com.
pletion date as 28 October 1961.
2. There were several major features of the work,
A system was to be installed whereby outside air could
be taken into the power plant and heated as combus.
tion air for the boilers. A new handling system was
to be installed for removal of ashes from the boilers,
A concrete floor, new heaters, and other miscellaneous
work was to be performed in the coal thaw shed ad.
jacent to the powerhouse. A centralized vacuum clean-
ing system was to be installed in the powerhouse, And
finally new coal handling equipment was to be in-
stalled to modify the existing system.
3. This plant furnished most of the heat and elec.
tricity for the operations buildings and quarters at
Eielson AFB. Some of the installation work would
require that operation of portions of the plant's
equipment be shut down. Obviously operation of the
plant could not he completely stopped, and the speci-
fications provided as follows:
1-04 COORDINATION WITH USING AGENCY: The
r shall execute all work with a mini-
mum of interference with the using :
Any work which will cause a disruption of
normal operations of facilities will first be
cleared in writing with the Contracting Officer
or his authorized representative.
1-06 INSPECTION oF sITE: The Contractor
shall thoroughly examine the site prior to sub-
— a bid and become thoroughly familiar
with all conditions that might affect the cost of
the mane The Contractor shall also notify
the Contracting Officer of any discrepancies be-
47
tween the contract drawings and actual field
conditions.
+
1-09 rnTeRFERENCES: The Contractor shall
store all materials and schedule all work so
as to provide a minimum of interference to
the normal operations of the Power Plant.
In extremely cold winter weather it became neces-
sary to place into operation 5 of the 6 boilers in the
, and to hold the remaining one on stand-
by. Thus, that part of the work which required the
cessation (of a part) of the plant’s operation could
not be accomplished at all in winter. The short per-
formance period was designed to assure completion
before the onset of winter weather.
4. Appellant was required to make a site inspection
prior to bidding and did so. It thus, presumably, be-
came familiar with the powerplant and the nature of
the work.
5. The specifications directed that the contractor
submit to the contracting officer, for his approval, a
listing of the equipment to be furnished, and such
descriptive information as would permit a review to
determine whether or not such equipment met the re-
quirements of the snecifications. Such submittal was
required within 10 days of contract award on the coal
handling and ash removal equipments and within 30
days after award for the ash removal equipment.
While there were numerous items of equipment to
be supplied, those involved in this appeal were the
coal scales, the combustion air coils, and the ash re-
moval equipment. Some drawings on these equipments
were delivered on 5 or 6 July 1961. Formal submittals
were made to the contracting officer on 11 July and
13 July 1961. The respondent made no immediate
review of these submittals, for it had not been decided
whether such review would be made by the architect-
ee
48
engineer (hereinafter AE) or by the Base iy)
Engineer.
6. Section 5 of the specifications described the coal
handling equipment. Relevant portions are as follows:
5-04 MATERIAL AND EQUIPMENT SCHEDULE:
A. As soon as practicable and within 10 days
after the date of award of contract and before
commencement of installation of any materials
or equipment, a complete schedule of the mate.
rials and equipment proposed for installation
xs ha ee en a Aig oe assem, teeta
include catalogs, cuts, di ms, i
and such other descriptive data as may be re.
quired. In the event any items of materials or
uipment contained in the schedule fail to com-
ply with the specifications or the requirements
of the drawings, such items will be rejected. In
case of rejection, similar data on other ma-
terials or equipment shall be immediately sub-
mitted until they shall comply with the i
ments. No extension of contract time will result
from submission of material and equipment
data which does not fulfill the requirements,
[Emphasis supplied]
B. The manufacturer’s drawings shall be re.
viewed to determine that the equipment to be
furnished will fit into the available space and
will cause no structural interference. * * *
* . o * * * .
5-06 EXISTING SYSTEMS:
A. Coal Bunker to Boiler: The existing coal
bunker to boiler system conveys coal through
the coal bunkers to the stoker feeder hoppers
through a three-way gate valve at the di
of the coal bunkers, thence through a chute into
a circular downspout and into conical spreaders
on Boilers 1, 2, 3, & 4. On Boilers 5 & 6, the
three-way gate valve discharges through a
chute into coal scales at elevation 581’-2’’, from
which the working parts have been removed.
28
aS? KFRSPSTR SHS es Frag
Se ste Saad sE&.
The discharge from the coal scales drops into
spreaders to the stoker feeder hop-
existing three-way gate valves are
Designed to direct coal either to the chutes lead-
ing to the spreaders or to an_under-bunker
conveyor which has been partially removed.
« * + * * * .
5-09 DESCRIPTION & CAPACITY OF NEW EQUIP-
MENT:
D. Coal Scale:
The coal seale shall be of the stationary, auto-
matic, dust-proof, hatch type, Model 46, manu-
factured by Stock >< t Company, or ap-
proved equal. Scale have a rated capacity
of 10 tons per hour and a hopper capacity of
200 pounds. Distance between center line of in-
let and center line of outlet is to be 2’-8’’.
1. The coal seale shall be a complete unit in-
eluding the body, belt feeder, feeder drive,
bypass, weighing mechanism, weigh hopper,
controls, counter, circuit breaker, control trans-
former and all other items requied to make a
completely automatic coal scale.
The remaining portions of paragraph 5-09 give a
fairly detailed listing of the mechanical requirements
of the coal scales.
7. The coal scales offered by appellant were a stand-
ard model manufactured by Richardson Scale Com-
pany. From its own correspondence, Richardson is
the largest manufacturer of such equipment in the
country. The evidence is uncontradicted that this firm
enjoys an excellent reputation and its products are of
good quality. Admittedly, however, the equipment of-
fered did not meet many of the required mechanical
features set out in the specifications, which actually
deseribed the ‘‘brand name”’ Stock Equipment Com-
pany seales in considerable detail. We mention only
a few of the differences which the AE considered
important.
50
a. Richardson scales had been installed on boilers
5 and 6 when these boilers had been added to the
powerhouse. It was found that the configuration of
the Richardson scales was not compatible with the
location of the boilers. The firing aisle in this power
plant is unusually wide, while in the Richardson
equipment the distance from the bottom of the coal
hoppers to the scale itself is relatively short. As the
result, the chute does not have sufficient slope s
that the coal would flow through it by gravity. The
working parts had been removed from the scales
on boilers 5 and 6, as stated in paragraph 5-06,
quoted above, and these scales were to be replaced as a
part of the contract work.
b. The specifications contained a requirement for
an endless rubber feed belt without splice. The Rich-
ardson equipment contained a laced belt. The nearest
belt lacers to Fairbanks, Alaska, are in Seattle, Wash-
ington. An untenable delay could be encountered in
the event a belt broke.
e. A solenoid counter was specified while the Rich-
ardson equipment offered a mechanical counter.
8. Relevant provisions of Section 7 of the specifica-
tions, describing the combustion air system are as
follows:
7-02 GENERAL: The applicable drawings indi-
cate the extent and general arrangement of
the installation. If any departures from these
drawings are deemed necessary by the Con-
tractor, details of such departures and the rea-
sons therefor shall be submitted as soon as
practicable to the Contracting Officer for
proval. No such departures shall be made wi
out the prior written approval of the Contract-
ing Officer.
A. Standard Products: The equipment to be
furnished under this specification shall be es-
sentially the standard product of the manv-
BLEED THROUGH POOR COPY
ee ee |
51
facturer. Where two or more units of the same
class of equipment are required, these units
shall be products of a single manufacturer;
however, the component parts of the system
need not be the products of the same manu-
facturer.
B. Material and Equipment Schedule: As
soon as practicable and within 30 days after
the date of award of contract and before com-
mencement of installation of any materials and
equipment, a complete schedule of the materials
and equipment proposed for installation shall
be submitted for approval of the Contracting
Officer. * * * Equipment differing from that
specified may be proposed, provided the Con-
tractor clearly states such differences and
rovided all essential requirements of the spec-
ification are met. If the equipment offered
under this provision is, in the opinion of the
Contracting Officer, equal or better than that
specified, it will be given consideration. * * *
+ + . ” .
D. Manufacturer: Mechanical equipment to
be furnished under this specification shall be
the product of a reputable manufacturer who
shall have had not less than five years experi-
ence in the design and construction of equip-
ment for the purpose and service intended for
this system and of a capacity equal or greater
than specified which shall have been proven in
suecessful operation for at least five years,
under like or more severe conditions. Required
accessories sha!l also be of proven design and
the product of experienced and reputable
manufacturers.
In addition paragraph 7-07 of the specifications gives
many required mechanical features of the combustion
air coils. While no brand name is given, it appears
from the testimony that combustion air coils manu-
factured by L. J. Wing Co. was used as a model in
writing the specifications. Appellant’s proposal offered
: 52 |
Pace combustion air coils to be furnished by Brod
and McClung. These coils differed from the specifica-
tion requirements in a number of particulars; notably,
the coils would have steel tubing while non-ferroys
metal was specified, and the connection to the headers
was different from that specified. No proof was fur-
nished that the manufacturer of this equipment had
the experience qualifications detailed in specification
paragraph 7-02D.
9. Section 8 of the specifications describes the ash
removal equipment, in relevant part as follows:
8-04 GENERAL: The contract drawings indicate
the extent and general arrangement of ash
removal equipment to be replaced. It is the
intent of these specifications and drawings to
obtain an ash conveyor installation which will
eliminate the excessive maintenance and poor
operational functions of the system now being
used on Boilers 1, 2, 3, and 4. The newer sys-
tem used on Boilers 5 and 6 is quite satis-
factory from a maintenance and operational
standpoint. It has therefore been decided to
extend the system used on Boilers 5 and 6 to
Boilers 1 thru 4, and replace the ash handling
equipment on these boilers.
It is the intent of the drawings and speci-
fications that equipment for this contract shall
be as manufactured by the United Conveyor
Corporation, or approved equal. If any depar-
ture from the contract drawings are deemed
necessary by the Contractor, details of such
departures and the reasons therefor shall be
submitted as soon as practicable to the Con-
tracting Officer for approval. No such depar-
tures shall be made without the written ap-
proval of the Contracting Officer.
+ + - + * * *
B. Standard Products: The equipment fur-
nished under this section of the specifications
shall be essentially the standard products of
BLEED THROUGH POOR COPY
sacar
manufacturers regularly engaged in the produc-
tion of these types of equipment and shall be
the types, sizes, and capacities and for the kinds
of service specified. Each item of equipment
shall be of the most recent type which has been
roven in successful commercial operation for
at least three (3) years without major changes
in design. The air washers and receivers and
other items of equipment where two or more
units of the same class are required, shall be
products of the same manufacturer; however,
the cumponent parts of the equipment need not
be the products of the same manufacturer.
C. Manufacturer’s Lists, Drawings & Refer-
ences: Within ten (10) days after award of con-
tract, the Contractor shall submit to the
Contracting Officer for approval a tabular list,
in triplicate, of all the different individual
items, listing opposite each item the manufac-
turer's name, address, and identifying number
together with any drawings or specifications
pertinent to the equipment selected. Within
thirty (30) days after award of contract, the
Contractor shall submit detailed drawings show-
ing equipment location, foundation details, and
connections to existing ash conveying piping, to
the Contracting Officer for approval. Further,
the Contractor shall submit to the Contracting
Officer the addresses of five installations of com-
parable size with air washers operating under
vacuum in conjunction with mechanical ex-
hausters where the manufacturer of the major
items of equipment selected (blowers, air
washers, receiver) has furnished similar-
designed equipment with satisfactory perform-
ance. No materials of an untried nature will
be acceptable.
There followed detailed mechanical requirements for
the equipment.
10. The ash removal equipment proposed by the
appellant was to be manufactured by the Durabilt
358-025—69-——5
CORY BOTINT) CTOSE IN CONTE SP
54
Conveying Systems Division of Chicago Fire Brick
Company. No proof was offered that this equipment
met the experience requirements of the contract, In
addition, the AE reported to the contracting officer a
variation from the mechanical requirements of the
specifications, by letter of 29 August 1961, as follows.
4. The equipment presented does not include a
weighted, nonvibrating relief valve to provide
pressure control, plus overload protection for
the blower as required under Specification Sec.
tion 8-06A(1) entitled Equipment Design.
5. Equipment submittal arrangement of the
Durabilt drawings No’s. AHE-3-593-2 and
AHE-3-593-3 indicate the blower motor as-
sembly foundation as 41%4’’ high to accomodate
[sic] the air washer top outlet. The contract
drawings specifically show on sheet 38 of 42 a
foundation three feet high.
6. Specification Section 8-06B, Equipment De-
sign, specifically calls for an air washer of the
impact type capable of successfully operating
under full 14’ Hg vacuum with satisfactory
water operation. The air washer submittal is of
the centrifugal type which does not meet the
specifications. The above data is shown on sub-
mittal drawing No. AHA-1-5983.
7. Specification Section 8-06C, Equipment
Design, indicates the receiver and secondary
separator be constructed of not less than 34”
thick hard alloy cast plate with 2” thick wear
plates. Drawing AHA-1-5299 does not indicate
this requirement, nor does this submittal indi-
cate utilization of existing openings and anchor
pi aga removal of existing equipment is
possible.
Drawing No. AHA-3-513 by Durabilt does
not show a swing gate nor a removable wear
plate as called for under this section of the
specifications.
—
55
8, Durabilt Drawing No. AHE-1-593 does
not satisfactory indicate the wear and abrasive
resistant pipe required at each change indirec-
tion as called for under Section 8-06G.
9. Durabilt Drawing No. AHA-2-5993, Ro-
tary Slide Gate, does not show or indicate dust
seal rings as called for under Specification Sec-
tion 8-061.
10. Durabilt Drawing No. SK-5757 indicates
plain end ash pipe will be utilized, however lo-
eation of such ash line is not shown on the
drawings.
11. Pressure and temperature rating of the
8’’ steam exhauster shown on Durabilt Draw-
ing No. AHA-1-507 is not shown.
In addition to the above, no information is
rovided for vacuum cleaning system interlock
y ash conveyor control, exhauster interlock,
control panel, and other equipment details.
The above basic factors are in direct con-
flict with the detailed specifications either by
non-availability of information, or equipment
that does not meet the specified equipment de-
sign. This establishes that the submittal pre-
sented is unacceptable.
That such variations did exist is not controverted in
the record. 3
11. Following the submittal of the data on this
equipment, one of appellant’s engineers traveled to
Fairbanks where, on 17 July 1961, he conferred with
the AE and the contracting officer. While the AE had
not actually yet been retained to review the proposals,
he informed appellant’s engineers that he would not
approve the Brod and McClung Combustion Air Coils
or the Richardson Scales, and that the information
submitted on the Durabilt Ash Removal Equipment
was not in sufficient detail to permit review. Testi-
mony is conflicting as to actually what was said at the
—
meeting. In any event appellant’s engineer gained
the impression that only Stock Seales, Wing Coils,
and United Conveyor Ash Removal Equipment would
be approved. On the same day as the conference, he
wrote a memorandum to his purchasing department
to cancel the orders which had been placed for the
offered equipment and to place orders for that named
last above. Appellant did send cancellation notices to
the suppliers of rejected equipment on 19 July 1961,
12. Upon receipt of the notice of cancellation, Brod
and McClung discussed their equipment with the AE,
agreed that it did not meet the requirements of the
specifications, and accepted the cancellation. While
appellant did not receive formal rejection of the Brod
and McClung Coils until 7 August 1961, the informal
rejection was effective. Appellant actually ordered
the Wing Combustion Coils immediately after the 17
July meeting. The order was confirmed by the jobber,
on 26 July 1961, with the statement that the three
weeks delay in placing the order resulted in a prom-
ised shipping date of 11 September 1961.
13. Richardson refused to accept the cancellation of
appellant’s order for its scales. It insisted to both the
appellant and the AE by telephone calls and letter of
24 July that, while its equipment did not meet the de-
tailed requirements of the specifications, it was equal
in utility to the “named brand,” and demanded to
know the reasons for the rejection. The AE for-
warded a formal rejection of the Richardson Scales
to the contracting officer on 26 July 1961. This was re-
ceived by the appellant on 7 August 1961. In response
to repeated arguments, the AE gave detailed reasons
for rejection of this equipment in a letter of 17 Au-
gust 1961.
14. Appellant had placed an order for Stock Equip-
ment Company Scales on 20 July 1961. The order was
56
ae
confirmed 25 July 1961, with tentative delivery in Oc-
tober. Delays resulted because of the arguments with
Richardson, and incomplete data submission by Stock.
Appellant received final approval of the shop draw-
ings on 5 September 1961. The equipment was shipped
on 3 December 1961 and arrived at the job site 18
January 1962.
15. Chicago Fire Brick Co. also initially refused
to accept cancellation of appellant’s order for the
Durabilt ash handling equipment. The AE then ad-
vised appellant that he had not received any data on
this equipment. Durabilt submitted such data to ap-
pellant on 4 August and it was received by the AE
on 8 August 1961. It was disapproved by him on
29 August, for the reasons stated in finding 10, above.
16. Appellant placed an order for United Conveyor
ash handling equipment on 29 July 1961 but, in view
of the Chicago Fire Brick Co. protest, considered it
wise to place a verbal stop on the order. United Con-
veyor Corporation submitted data on its equipment to
appellant on 24 July 1961. This data was mailed to
the contracting officer on 6 September and approved
by the AE on 15 September 1961. All of this equip-
ment, except the control panel, was shipped on 24
November 1961 and arrived at the job site 9 January
1962. The control panel was shipped 30 December
1961 and received 31 January 1962.
17. The specifications required that work be started
and completed as established by a schedule of work
prepared and approved by the contracting officer
before any work was commenced. The progress sched-
ule submitted and approved contemplated that work
would first be started in the coal thaw shed, and that
this part of the work would be completed by 31 Au-
gust 1961. The operational parts of the shed consisted
of railroad tracks on ties, surrounded by gravel,
57
58
running through the shed, and a crusher called a
“‘grizzly’’ into which the coal was dumped. The eoa]
was then conveyed from the grizzly into the power-
house. Appellant was to remove the tracks, lay a con-
crete floor, and replace the tracks. Some concrete wag
to be replaced around the grizzly. A car puller was to
be installed. Heaters were also to be installed.
18. The respondent considered this work to he
urgent, for the shed in its existing condition was a
severe safety hazard. A large part of the combustion
air for the existing powerplant was drawn through
open doors. As the outside temperature reached ex-
treme cold of —30° and below, it became necessary
to close the doors to prevent freezing of lines and in-
struments. The boilers then generated negative air
pressure in the plant. Coal dust, which had permeated
the gravel floor, was then drawn into the plant from
the coal thaw shed and from the bunkers, creating a
dangerous, explosive, condition. The concrete floor
would permit the coal thaw shed to be kept clean.
19. In anticipation of the work, the respondent had
placed a stockpile of coal by an outside crusher and
conveyor. When appellant commenced work in the
coal thaw shed, respondent stopped using it. The work
in the coal thaw shed was not completed in accordance
with the progress schedule. In fact the work, other
than installation of heaters, was not completed until
approximately 20 November 1961. The heaters were
installed in the spring of 1962. The concrete work,
and setting the rails in the coal thaw shed was com-
pleted the first week in October 1961, concurrently
with arrival of the first deep snowfall. It was then
necessary for the respondent to commence using the
coal thaw shed to feed the boilers. The respondent
confined its use of the shed to night hours as much as
possible, but could not do so entirely because the
BLEED THROUGH POOR COPY
59
heaters had not been installed. The respondent’s use
of the shed naturally interfered with appellant’s work.
When coal was hauled in and dumped only at night,
appellant’s workmen must put away their tools and
materials so as not to obstruct the tracks. Cars stand-
ing in the shed reduced working space. Extra precau-
tions in welding were necessary and a fire watch was
required. When coal was being dumped and welding
was in progress, the doors were opened to disperse
coal dust and prevent explosion. The extreme cold
then reduced efficiency.
90. The work was delayed about 3 days due to an
error in elevations. No other delaying factor can be
attributed to the respondent as preventing completion
of work in the coal thaw shed within the scheduled
time. A tractor did damage anchor bolts for the car
puller, but the evidence shows they were in the wrong
locations, thus could not have been used anyway.
921. On 7 September 1961 appellant requested 90
days time extension for delays in procuring the ash
handling equipment. The contracting officer offered
to extend the time 30 days by letter of 26 September.
The appellant then, on 18 October 1961, requested
120 days time extension. The contracting officer, on
12 November 1961, replied that he would grant 69
days time extension for delay in approvals. This was
apparently computed as the total lapsed time between
the notice to proceed and appellant’s receipt of the
rejection of the Durabilt ash removal equipment. As
an alternative the contracting officer offered a con-
tract amendment which would delay the start and
completion of certain items of the work, and establish
the final completion date as 30 June 1962. The draft
supplemental agreement contained the following:
This Supplemental Agreement neither increases
or [sie] decreases contract costs. [Emphasis
supplied ]
COPY BOUND CLOSE IN CENTER
This offer was motivated by the fact that the power
plant could not be shut down for work in the
and the contemplated time extension would allow th.
appellant 120 days, equal to the entire contract per.
formance time, after winter would be over.
22. Appellant’s Alaska Representative met with the
contracting officer on 16 November. The appellant was
given the alternatives of accepting the 69 days time
extension, signing the proposed modification, or hay.
ing the contract terminated for default. The 69 days
would have been useless and, from appellant's view.
point, default termination was unthinkable. Appel-
lant objected to the statement in the draft agreement
that there would be no change in costs. Its represents.
tives knew extra costs would be incurred by
the performance period. The local representative con.
tacted one of appellant’s principal officers and was
told to sign the agreement provided the word “costs”
be changed to “price.” The parties then signed Sup-
plemental Agreement No. 1, which reads in substan.
tial part as follows:
gine eve mmmmered contract is modified as
_ Pursuant to Clause 5 entitled “Time Exten-
sion”’
1. extendi ormance period as follows:
rx Coal +d pemes heatiog apetens extended
to 20 November 1961, except for insulation of
pipe to be completed by 27 November and
SY Bad maar agee prior to 30 June 1962,
(b) ion air system modification and
ash removal equipment and auxiliaries shall be
completed by 15 May 1962 and prior to installa-
tion and modification of coal scales.
(ce) Installation and modification of coal
scales shall be completed 45 days after comple-
tion of the combustion air system modification
vy CE vae Vas ee Pea aS” Vow a
>. FF eee Pe eee ce —
>
ditions mt said contract as
remain unchanged and in full force and effect.
This Supplemental Agreement is entered into
pursuant to the authority of basic contract.
23. Appellant continued to work through the winter,
with attendant problems. There were interferences
from the severe weather and the operation of the
. While there was some rearrangement
of the interim schedules, the work was substantially
completed on 30 June 1962.
%4. An audit conducted by the Air Force after com-
pletion shows a cost to the appellant of $567,680.22.
This is $79,905.22 in excess of the final contract price.
25. The original claims consisted of the allegations
of delay and interference detailed in the foregoing
findings, and several smaller claims founded on par-
ticular alleged changes. Several of the smaller claims
were abandoned at the hearing, and none of the others
were supported by adequate proof to warrant specific
findings.
OPpixion
The first question presented is whether or not the
coal seales, combustion air coils, and ash removal
equipment initially offered by the appellant was im-
properly rejected by the respondent. Appellant argues
——_
that this equipment met the “intent” if not the de
tailed requirements of the specifications. It says thet
the details of fabrication and operation given wer
unduly restrictive and in violation of the provisions
of the Armed Services Procurement Regulation 1.
lating to description by “‘brand name or equal.” }j
says that respondent would accept only the named
brands, thus should have specified them alone. We cay
assume that every allegation made by the appellant
is correct, but still find that the equipment was prop.
erly rejected.
Prior to award of a contract, prospective bidders,
suppliers, or even interested taxpayers may object to
restrictive specifications which unnecessarily restriet
competition. These objections may be, and frequently
are, made to the contracting officer, his superiors, or
to the General Accounting Office. When the restric.
tions are found to be more stringent than the needs
of the service dictate, the specifications are amended.
But a bidder may not remain silent during the bid.
ding period, then after receipt of award of the
contract contend that he has the right to furnish some
thing less expensive and not meeting the requirements
of the specifications. To allow such would be equally
damaging to the competitive bidding system with u-
duly restrictive specifications. Many of the specified
details may have been unnecessary. Others were
clearly desirable for this particular application, and
some of these details were not met by the offered
equipment. The Richardson Scales, Brod and Me
Clung Coils and the Durabilt equipment clearly did
not meet the requirements of the contract and were
properly rejected.
The appellant was the innocent victim of represen-
ae ee, ee a ee tn F&F ewe TE S&H T
i
tations by its prospective suppliers that their equip-
ments would meet the specified requirements. We
have no reason to believe they were not acting in good
faith. But this would not entitle appellant to recover
its losses from the Government. Under the most lib-
eral view it could, at most, receive a time extension,
and this the appellant got.
The respondent did unreasonably delay acting upon
these submittals. The contract gave appellant only 10
tion on the Durabilt submittal until 29 August, par-
ticularly since it had already been decided to reject it.
Appellant argues that by insisting upon changing
the word “costs” to the word “price” in Supplemental
Agreement No. 1, it avoided agreeing that the contract
consideration would not be increased as the result of
the extended contract performance time. This is not a
reasonable construction of the provision which states,
“This Supplemental Agreement neither increases or
[sie] decreases contract price.” The other provisions
of the agreement reschedule performance. We think
it clear that the quoted sentence stated an agreement
that the contract price would not be changed by
reason of performance under the new schedule. The
appellant’s losses were directly attributable to such
performance.
The appellant next contends that the supplemental
agreement was without consideration, thus not bind-
64
ing upon it. The appellant was actually in default at
the time the supplemental agreement was made, The
parties were jointly responsible for the delay in de
livery of the equipment, the appellant because it of.
fered equipment which did not meet the contractual
requirements, and the respondent because it delayed
too long in rejecting it. We are unable to apportion
the causes of delay for the evidence is directed to.
ward the time lapse between submittal and action
thereon. A time extension is properly computed upon
how long the work is delayed, not how long the de.
laying causes continue in existence. We know when
the approved equipment was delivered, but not when
it would have been delivered but for the respondent's
delay in rejecting the unsuitable equipment. In any
event, the appellant was not entitled to a time exten.
sion adequate to permit completion of the work,
The receipt of such time in the modification was a
valuable consideration.
Appellant’s final argument is that the supplemental
agreement was signed by it under duress. In order
to constitute economic duress, there must be something
present other than threatened financial disaster.
DuPuy v. United States, 67 Ct. Cl. 348, 381 (1929).
Where the contracting officer threatens default termi-
nation, and the contractor is actually in default, the
contracting officer was threatening to do only what he
had the right to do. This is not duress. Commonwealth
Engineering Company of Ohio v. United States, 48
Ct. Cl. 330 (1960), cert. denied 364 U.S, 820. In the
instant case the appellant was in default for the com-
pletion date was 18 days past when the modification
was signed. At least as to the coal thaw shed only 3
days of the delay was excusable. The contracting of-
ficer offered 69 days time extension because of the
delay in approvals. This would not have permitted
BLEED THROUGH POOR COPY
or Tra wr iB SPS SET SB ABP SS SB
~o we | © OH oe 8 Ts SF Oo
65
completion, but we cannot find that it was not as
much as was due for excusable cause.
The appeal is denied.
Dated: 30 December 1966.
Harris J. ANDREWS, Jr.,
Member of Division No. 3,
Armed Services Board of Contract Appeals.
I concur.
Hvuou B. ArcHer,
Acting Vice Chairman, Armed Services Board
of Contract Appeals, and Member of Division
No. 3.
Rosert J. O’Connor,
Member of Division No. 3, Armed Services
Board of Contract Appeals, did not par-
ticipate.
Armep Services Boarp or Contract APPEALS
ASBCA No. 9831
Appeal of
Ursan PLUMBING AND HeEatine Co.
Under Contract No. AF 65(503)-1505
Appearances for the Appellant: Warde H. Erwin,
Esq., Portland, Oregon.
Appearances for the Respondent: Colonel David C.
Yeoman, USAF, Chief Trial Attorney; Major Eugene
M. Solimine, USAF, Trial Attorney.
On Morton For RECONSIDERATION
The appellant has moved for rehearing and redeter-
mination of certain of the Board’s findings set out in
COPY BOUND CLOGE IN CENTER
66
its opinion of 30 December 1966, which denied the
appeal.
The first allegation of error is that the member of
the Board who conducted a portion of the hearing dig
not participate in the decision. This member retired
soon after the hearing, and was not a member of the
Board at the time this case was ready for decision,
The Board has held many times that preparation of
the opinion by a member who did not preside at the
hearing is not error. Buckeye Union Casualty Co,
ASBCA No. 6770 (On Reconsideration), 1962 BCA
P 3309, and cases cited therein. See also Racine Screw
Company v. United States, 156 Ct. Cls. 256 (1962).
The remaining allegations of error present nothing
which was not fully considered by the Board in reach-
ing its decision.
The Motion for Reconsideration is denied.
Dated 8 February 1967.
Harris J. ANDREWS, JR.,
Member of Division No. 3,
Armed Services Board of Contract Appeals.
I concur:
Huou B. ARcHER,
Acting Vice Chairman, Armed Services Board of
Contract Appeals and Member of Division No.
3.
Wu11aM T. Grirrirn,
Lt. Colonel, USAF, Member of Division No. 3,
Armed Services Board of Contract Appeals,
did not participate in the determination of this
decision.
I certify that the foregoing is a true copy of the de-
cision and opinion of the Armed Services Board of
Contract Appeals in ASBCA No. 9831, Appeal of
Urban Plumbing and Heating Co., On Motion for
BLEED THROUGH POOR COPY
67
Reconsideration, rendered in conformance with the
Board’s Charter.
Dated
GerorceE L. HAWKES,
Recorder, Armed Services Board of
Contract Appeals.
U.S. GOVERNMENT PRINTING OFFICE: 1969
This is a copy of a public record, reproduced as it was published. It is not legal advice, and it may not be the version a court would rely on. Check the official source before you cite it.