Amicus Curiae Brief — Environmental Defense v. Duke Energy Corporation
Supreme Court brief2007
Ask Donna
What actually matters in this document.
Text
6
must interpret the statutory term “modification” identically.
There is no question, though, that the regulations are not
uniform. Whereas the NSPS requirements-are triggered only
if there is a post-project increase in the hourly rate of
emissions from a unit, the PSD requirements are triggered
by an increase in a unit’s total annual emissions. By requiring
that the PSD regulations conform with the NSPS regulations,
the Fourth Circuit effectively invalidated those regulations
without jurisdiction to do so.
ARGUMENT
Il. THE FOURTH CIRCUIT’S DECISION CONFLICTS
WITH DECISIONS OF OTHER COURTS OF
APPEALS AND OF THIS COURT ON A MATTER OF
PUBLIC IMPORTANCE.
A. The Fourth Circuit’s Decision Conflicts With New
York v. EPA, tn Which the D.C. Circuit Upheld the
1980 PSD Emissions Test Effectively Invalidated by
the Court Below.
The Fourth Circuit’s decision is directly contrary to the
decision of the D.C. Circuit in New York v. EPA, issued nine
days after the Fourth Circuit ruled.* In rejecting a challenge
by industry (including Duke) to the PSD modification
regulations, the D.C. Circuit likewise rejected industry's
argument that “modification must have the same regulatory
meaning for NSR as prevailed for NSPS in 1977 [because]
Congress, by a cross-reference, used the same language in
both statutory contexts.” 413 F.3d at 19-20. The D.C. Circuit's
4. Although New York was brought to the Fourth Circuit's
attention on petition for rehearing, the court refused to modify its
ruling.
J
decision that EPA is not required to use the NSPS hourly
emission rate test in the PSD regulations cannot be squared with
the Fourth Circuit’s holding that the NSPS and PSD regulations
must have the same test for modifications. This case therefore
presents a conflict between the Fourth Circuit’s decision and
the authoritative decision of the D.C Circuit, which, as explained
below, has exclusive power to review the validity of EPA
regulations under the CAA. See infra Point II.
B. The Fourth Circuit’s Decision Conflicts With the
Decisions of Several Other Courts That Have
Recognized The Differences Between the Emissions
Tests under NSPS and PSD.
The Fourth Circuit’s decision upholding the district court's
interpretation of the PSD emissions test as necessarily identical
to the NSPS emissions test also conflicts with decisions of the
Seventh and First Circuits, recognizing that the tests can and
do differ. In Wisconsin Electric Power Co. v. Reilly, 893 F.2d
901 (7" Cir. 1990), for example, the Seventh Circuit noted that,
[t]o determine whether a physical change constitutes
a modification for purposes of NSPS, the EPA must
determine whether the change increases the facility’s
hourly rate of emission. 40 C.F.R. § 60.14 (1988).
For PSD purposes, current EPA regulations provide
that an increase in the fofal amount of emissions
activates the modification provisions of the
regulations. 40 C.F.R. § 52.21(b)(3) (1988).
893 F.2d at 905; see also id. at 915 (“unlike NSPS, PSD is
concerned with changes in fetal annual emissions, expressed
in tons per year”); Puerto Rican Cement, 889 F.2d at 296-99
(1980 PSD regulations triggered even if hourly rate of emissions
remained the same).
8
The Fourth Circuit’s decision is also contrary to the
_ dectsions of two district courts that have relied on WEPCo
and applied the PSD modification regulations as written, to
require an increase in annual, not hourly, emissions as a
predicate for application of the PSD permitting requirements.
See United States v. Cinergy Corp., 384 F. Supp.2d 1272,
1277 (S.D. Ind. 2005) (“The Court disagrees with ... the
Duke court that the EPA’s definition of ‘actual emissions,’
means that ‘a net emissions increase can result only from an
increase in the hourly rate of emissions.’”);° United States v.
Ohio Edison Co., 276 F. Supp.2d 829, 863-64 (S.D. Ohio
2003) (proposed change must “result in an increase in
emissions, also expressed in tons per year,” to trigger PSD).
These decisions reflect a reality that the Fourth Circuit
chose to ignore: that the divergent purposes of the NSPS
and NSR programs strongly suggest that Congress intended
the use of different emissions increase tests under the two
programs. The NSPS provisions of the CAA are intended to
ensure that new and modified sources use emission controls
that are at least as effective as the “best system of emissions
reduction which ... has been adequately demonstrated.”
42 U.S.C. § 7411(a)(1). This requirement is the same
regardless of the quality of air in the area where the plant is
located or the number of sources located in the area. In
contrast, the NSR provisions are concerned with maintaining
(in the case of PSD) and improving (in the case of NNSR)
air quality in areas where new or modified plants are located.
For example, the PSD provisions require that the effect of a
new or modified source on air quality in the region be
analyzed, 42 U.S.C. § 7475(a), while the NNSR provisions
5. The Seventh Circuit has granted Cinergy’s motion for
interlocutory appeal of this decision.
9
require such a source to obtain emissions offsets so that total
emissions will be sufficiently less after the source begins
operation, 42 U.S.C. § 7503(a)(1). No similar requirements
exist in the NSPS program.
EPA’s regulations simply reflect these differences between
the two programs. Because the NSPS program is primarily
concerned with the efficacy of emission controls, without regard
to the total amount of pollution emitted, the NSPS regulations
require an increase in the hourly emission rate as a prerequisite
for a major modification. See 40 C.F.R. § 60.14(b)(NSPS
emissions test based on rate of emissions “expressed as ky/hr’’).
On the other hand, because NSR is concerned with the total
amount of pollution being emitted, a modification that increases
total annual emissions triggers NSR requirements regardless of
whether the hourly emission rate is increased. See, e.g., 40 C.F.R.
§ 52.21(b)(2)(1), (3)(i), (21)G) (PSD emissions test based on
actual amount of emissions increase expressed in terms of fons
per year), see generally 57 Fed. Reg. 32314, 32316 col. | (July
21, 1992) (different emission increase tests reflect “the
fundamental distinctions between the technology-based
provisions of NSPS and the air quality-based provisions of
NSR”).
C. The Fourth Circuit’s Deeision is Contrary to
Chevron and Alabama Power, Which Allow EPA
to Interpret a Statutorily-Defined CAA Term
Differently in the NSPS and NSR Regulations.
The Fourth Circuit’s holding that EPA must construe a
statutorily-defined term identically in its NSR and NSPS
regulations is also contrary to Chevron U.S.A. Inc. v. NRDC,
467 U.S. 837, 863-64 (1984), and Alabama Power v. Costle,
636 F.2d 323 (D.C. Cir. 1979). In Chevron, this Court upheld
10
EPA’s authority to interpret a single CAA term differently in
its NNSR regulations than it did in its NSPS regulations.
At issue was EPA’s interpretation of the statutory term
“stationary source,” under 42 U.S.C. § 7411(a)(3), CAA
§ 111(a)(3),° as it applies to determining whether a physical
change at a facility results in an emissions increase that
triggers the NNSR modification requirements. EPA
interpreted “stationary source” to include all emissions
sources located at a single facility and allowing the facility
to net (or “bubble”) emissions increases and decreases across
sources. 467 U.S. at 840. Notably, at the time the NNSR
regulations were promulgated, EPA did not allow such netting
under the NSPS regulations,’ in accordance with the D.C.
Circuit’s decision in ASARCO, Inc. v. EPA, 578 F.2d 319
(D.C. Cir. 1978). See 45 Fed. Reg. 5617 (Jan. 23, 1980)
(“revok[ing] the bubble concept as a means of determining
what constitutes a ‘modified’ source for the purpose of
applying new source performance standards”).
On petition for review, the D.C. Circuit set aside the
NNSR regulations, finding that EPA was required to interpret
“stationary source” to preclude netting, as it had done in the
NSPS context. 467 F.2d at 841-42 (citing 685 F.2d 718,
726 (D.C. Cir. 1982)). This Court reversed, emphasizing
6. While the CAA § 111(a)(3) definition of “stationary source”
is not explicitly cross-referenced in the NNSR provisions, the Court
found that “it sheds as much light on the meaning of the word ‘source’
as anything in the statute.” 467 U.S. at 860.
7. As noted above, the NNSR regulations applicable to
modifications are in all relevant respects identical to the
corresponding PSD regulations at issue here. Compare 40 C.F.R.
§ 52.24(1)(5). (6), ({NC10) and (f)(13) with 40 C.F.R.§ $2.21(b)(2),
(b)(3), (b)(21) and (b)(23).
1]
EPA’s authority to define a single CAA term differently
depending on the regulatory program at issue:
Our review of the EPA’s varying interpretations
of the word “source” — both before and after the
1977 Amendments — convinces us that the agency
primarily responsible for administering this
important legislation has consistently interpreted
it flexibly — not in a sterile textual vacuum, but in
the context of implementing policy decisions ina
technical and complex arena. ... Moreover, the
fact that the agency has adopted different
definitions in different contexts adds force to the
argument that the definition itself is flexible,
particularly since Congress has never indicated
any disapproval of a flexible reading of the statute.
467 U.S. at 863-64. Thus, Chevron recognized that the same
language supported an emission increase test based on plant-
wide emissions for modifications under the NNSR
regulations and a dramatically different test prohibiting
“netting” under the NSPS regulations. The term at issue here,
“modification,” is defined in the same section of the CAA
(§ 111) as “stationary source” and must be governed by the
same interpretive rules.
Furthermore, the Fourth Circuit’s decision is contrary
to the D.C. Circuit’s decision in Alabama Power, which
upheld the bubble concept adopted by EPA under the PSD
regulations. 636 F.2d at 400-02. As in Chevron, the D.C.
Circuit’s analysis of the PSD bubble concept determined
“what types of industrial changes will be construed
as ‘modifications’ subject to PSD review requirements.”
Id. at 400. As noted above, the D.C. Circuit had previously
12
held the “bubble” concept to be unlawful under the NSPS
regulations. ASARCO, 578 F.2d at 329. In holding that EPA
was not only allowed but required to implement the PSD
requirements differently from the NSPS requirements, the
court concluded that “a bubble concept would be contrary to
the intent of the NSPS provisions, but such is clearly not the
case with regard to the PSD provisions.” Alabama Power,
436 F.2d at 402. The court explained that, although the
statutory definition of “stationary source” applicable under
PSD is the NSPS statutory definition found in CAA
§ 111(a)(3), id. at 395, EPA must interpret that definition
differently in implementing regulations under the NSPS and
PSD programs due to “differences in the purpose and
structure of the two programs.” /d. at 401-02."
Il. THE PETITION SHOULD BE GRANTED TO
PROMOTE THE INTERESTS IN CERTAINTY AND
UNIFORMITY UNDERLYING CAA SECTION
307(b)(2).
The Fourth Circuit’s decision deprives the States and
the regulated community of certainty about the applicable
PSD requirements, contrary to the purpose of § 307(b)(1).
The CAA forecloses any challenges to EPA’s PSD regulations
— which are “nationally applicable regulations” — except by
petition for review filed in the D.C. Circuit within 60 days
after promulgation of the regulations. CAA § 307(b)(1).
8. The Fourth Circuit erroneously relied on Rowan Cos. v.
United States, 452 U.S. 247 (1981), a case construing the provisions
of the Tax Code. The Rowan decision, however, relied upon the
explicit Congressional concern for “the interest of simplicity and
ease of administration” of the Tax Code, 452 U.S. at 255, which is
inapplicable here because of the different purposes behind the PSD
and NSPS programs.
13
Additionally, if a final EPA action “could have been”
challenged in the D.C. Circuit, such an action “shall not be
subject to judicial review in civil or criminal proceedings
for enforcement.” /d. at § 307(b)(2). The “twin congressional
purposes” in enacting § 307(b) were to “insur[e] that the
substantive provisions of the [regulation] would be uniformly
applied and interpreted and that the circumstances of its
adoption would be quickly reviewed by a single court
intimately familiar with administrative procedures.” Adamo
Wrecking Co. v. United States, 434 U.S. 275, 284 (1978);
see also United States v. Ethyl Corp., 761 F.2d 1153, 1157
(5" Cir. 1985) (“section 307(b)’s clear language and
Congress's manifest intent [was] to avoid protracted and
inconsistent adjudications over the validity” of nationally
applicable EPA regulations), cert. denied sub nom. Firestone
Tire & Rubber Co. v. United States, 474 U.S. 1070 (1986).
The decision below subverts these purposes and leaves
the States unsure of how to fulfill their obligations under
federal environmental statutes. States that have relied on the
validity of EPA’s PSD regulations — including the actual
annual emissions increase test for modifications — now face
uncertainty about the legality of their state implementation
plans (“SIPs”), which incorporate the annual emissions
increase test of the PSD regulations. If the Fourth Circuit's
decision stands, even after the window for judicial review
has closed, the States will no longer be able to rely on the
validity of EPA regulations they are required to enforce.
The result will be administrative confusion and effort wasted
on promulgating state regulations in mistaken reliance on
the validity of the federal programs being implemented.
The decision also guarantees, directly contrary to
Congressional intent, that federal CAA programs will not be
14
implemented uniformly across the fifty states. As discussed
above (pp. 6-12), the Fourth Circuit’s decision conflicts with
the decisions of other courts, which have given effect to the
differences between the NSPS and PSD emissions tests. Now,
though, the PSD requirements applicable in the Fourth Circuit
are different from those applicable in the remaining 45 states.
Nor can this disparity be fixed without this Court’s
intercession. In response to the Fourth Circuit’s decision, EPA
has proposed to change the PSD emissions test to correspond
to the NSPS emissions test in order to cure the serious disparity
and confusion created by the Fourth Circuit’s decision. See 70
Fed. Reg. 61,081, 61,083 col. 2 (Oct. 20, 2005) (“[Duke’s]
holding creates a potential disparity in the way we interpret the
program in the States in the Fourth Circuit compared to States
in other Circuits in the country,” creating need to “establish a[n
emissions] test consistent with the Fourth Circuit's holding”).
EPA’s decision is structurally unsound, for it effectively
supplants the D.C. Circuit’s exclusive authority to review the
validity of nationwide regulations, instead allowing the Fourth
Circuit to dictate the substance of EPA’s PSD regulations.
Furthermore, even EPA’s proposed rule does not satisfy the
Fourth Circuit’s mandate, for it seeks to maintain certain
differences in the NSPS and PSD regulatory definition of
“modification” because “[t]here are differences between the two
programs.” /d. at 61,090 col. 2. Thus, not even EPA’s proposed
rule change will comply with the Fourth Circuit's requirement
that the regulatory definitions be identical.
Nor is the mischief created by the decision below confined
to the Clean Air Act. Numerous other environmental statutes
contain provisions similar to CAA § 307(b), vesting the D.C.
Circuit with exclusive authority to review nationwide
regulations. See, e.g., 33 U.S.C. § § 271 7(a) (Oil Pollution Act):
15
42 U.S.C. § 300)-7(a)(1) (Safe Drinking Water Act); 42 U.S.C.
§ 6976(a)(1) (Resource Conservation and Recovery Act):
42 U.S.C. § 9613(a) (Comprehensive Environmental Response,
Compensation and Liability Act). The need for uniformity and
predictability in the nationwide effort to protect and conserve
environmental resources likewise animates these provisions.
Unless this Court scrutinizes the Fourth Circuit's arrogation to
itself of authority to pass on the validity of environmental
regulations, the uniformity and certainty of nationwide
requirements applicable under these other environmental laws
will also be threatened.
CONCLUSION
For the reasons set forth above and in the petition, the Court
should grant certiorari in this case.
Respectfully submitted,
Peter H. LEHNER E.iot Spitzer
Chief, Environmental Attorney General of the
Protection Bureau State of New York
CaiTutn J. HALLIGAN*
ROBERT ROSENTHAL Solicitor General
J. JaneD SNYDER Danie SMIRLOCK
Assistant Attorneys General Deputy Solicitor General
120 Broadway
New York, NY 1027]
(212) 416-8016
* Counsel of Record
Bitt Lockyer
Attorney General
State of California
CALIFORNIA Dept. or JusTICce
1300 I Street
P.O. Box 944255
Sacramento, CA 94244
RicHARD BLUMENTHAL
Attorney General
State of Connecticut
P.O. Box 120
Hartford, CT 06141
Cart C. DANBERG
Attorney General
State of Delaware
DELAWARE DePpARTMENT
OF JUSTICE
Carvel State Building
820 N. French Street
Wilmington, DE 19801
Lisa MADIGAN
Attorney General of the
State of Illinois
MatTHew DuNN
Chief, Environmental
Enforcement/Asbestos
Litigation Division
ANN ALEXANDER
Assistant Attorney General
and Environmental Counsel
188 West Randolph Strect
Suite 2001
Chicago, IL 60601
(312) 814-3772
G. STEVEN Rowe
Attorney General
State of Maine
6 State House Station
August, ME 04333
J. JosepH CurRAN, JR.
Attorney General
State of Maryland
200 Saint Paul Place
Baltimore, MD 21202
(410) 576-6300
Tuomas F. ReILty
Attorney General
Commonwealth
of Massachusetts
200 Portland Street, 3" Floor
Boston MA 02114
Mike Hatcu
Attorney General
State of Minnesota
MINNESOTA ATTORNEY
GENERAL'S OFFICE
900 Bremer Tower
445 Minnesota Street
St. Paul, MN 55101
Ketty AYoTTE
Attorney General
State of New Hampshire
Orricet oF ATTORNEY GENERAI
33 Capitol Street
Concord, NH 03301
17
ZULIMA V. FARBER Rosert J. SPAGNOLETTI
Attorney General Attorney General
State of New Jersey District of Columbia
Richard J. Hughes The Wilson Building
Justice Complex 1350 Pennsylvania Ave., N.W.
25 Market Street Washington, DC 20004
P.O. Box 80
Rosert A. REILEY
Trenton, NJ 08625 Assistant Counsel,
W.A. Drew EDMONDSON Commonwealth of Pennsylvania,
Attorney General Department of Environmental
State of Oklahoma Protection
2300 N. Lincoln Boulevard — Rachel Carson State
Suite 112 Office Building
Oklahoma City, OK 73105 P.O. Box 8464
Witwiam H. Sorrece Harrisburg, PA 17105
Attorney General
State of Vermont
109 State Street
Montpelier, VT 05609
Attorneys for Amici Curiae
This is a copy of a public record, reproduced as it was published. It is not legal advice, and it may not be the version a court would rely on. Check the official source before you cite it.