Appendix — Cleveland Construction Construction Construction, Inc. v. City of Cincinnati, Ohio (No. 08-601)

Supreme Court brief2008

Ask Donna

What actually matters in this document.

Text

2

A

A

y

'.

’.

é.

S

t

7

9

1

’

la

APPENDIX A

THE SUPREME COURT OF OHIO

No. 2007-0114

[Filed August 6, 2008]

Cleveland Construction, Inc.

We

City of Cincinnati, and Timothy

Riordan, Bernadine Franklin, Nate

Mullaney, Alicia Townsend, Kathi Ranford,

and Valley Interior Systems, Inc.

Nee eee ee”

RECONSIDERATION ENTRY

Hamilton County

It is ordered by the Court that appellee’s motion for

reconsideration and motion to clarify court/decision in

this case are denied.

(Hamilton County Court of Appeals: Nos. C050749,

C050779, and C050888)

ls/

THOMAS J. MOYER

Chief Justice

2a

APPENDIX B

SUPREME COURT OF OHIO

No. 2007-0114

[Filed May 21, 2008]

CLEVELAND CONSTRUCTION, INC.,

APPELLEE,

CITY OF CINCINNATI,

)

)

)

v. )

)

)

APPELLANT, ET AL. )

)

Public contracts — Bidding — Unsuccessful bidder has

no constitutionally protected property interest in public

contract — City properly exercised its discretion in not

awarding contract to bidder who failed to comply with

requirements of invitation to bid.

(No. 2007-0114 — Submitted January 9, 2008 —

Decided May 21, 2008.) APPEAL from the Court of

Appeals for Hamilton County, Nos. C-050749,

C-050779, and C-050888, 2006-Ohio0-6452.

SYLLABUS OF THE COURT

No property interest is created when a city properly

exercises its discretion and does not award a contract

3a

to a party deemed not to have complied with the

requirements of the invitation to bid.

LANZINGER, J.

{fl 1} This discretionary appeal was accepted on the

issues of whether an unsuccessful bidder may have a

constitutionally protected property interest in a public

contract and whether it may assert damages for lost

profits in an action alleging violation of its procedural

due process rights under Section 1983, Title 42,

U.S.Code. We hold that because appellant, city of

Cincinnati, did not abuse its discretion in failing to

award the drywall contract to appellee, Cleveland

Construction, Inc., no property interest in the contract

ever existed; without a property interest, there is no

due process violation.

I. Background

{fl 2} This case arises out of the expansion of the

Cincinnati Convention Center in the early 1990s, a

large-scale public project with an estimated budget of

$145 million. As part of the planning for the expansion

project, the city had planned to set aside 30 percent of

the overall work for small business enterprises

(“SBEs”). To achieve this goal, the city reserved a

varying percentage of work for SBEs in each of the 35

contracts ultimately awarded for the project. All

contract bidders for the project were apprised of this

requirement in the documents accompanying the

formal invitation to bid. The percentage for the

contract to install drywall that was reserved for SBEs

was 35 percent. The documents stated that failure to

4a

satisfy the 35 percent requirement could result ~in

rejection of a bid.

{{_ 3) The drywall contract for the project was bid

twice. None of the bids submitted in the initial round

of bidding fulfilled the SBE requirement, and as a

result, all bids were rejected by the city. A second

round of bidding was held, and three bids were

submitted. Two of those bids, submitted by Valley

Interior Systems, Inc. (“Valley”) and Kite, Inc.,

provided that at least 35 percent of the work would be

performed by SBEs. Cleveland Construction failed to

meet the 35 percent requirement, but did submit the

lowest bid. The city ultimately awarded the contract to

Valley, the lowest bidder who also satisfied the SBE

requirement.

{7 4} Arguing that as the low bidder it had a

protected property interest in the drywall contract,

Cleveland Construction filed suit seeking damages for

lost profits and injunctive relief to prevent Valley from

proceeding on the drywall contract for the project. The

trial court.denied the injunctive relief, but later held

that Cleveland Construction had a constitutionally

protected interest in the drywall contract and that the

city had deprived it of that interest without providing

due process of law. The trial court awarded Cleveland

Construction attorney fees and costs, but granted a

directed verdict in favor of the city on Cleveland

Construction’s claim for lost profits.

{{1 5} Cleveland Construction appealed, and the city

filed a cross-appeal. The First District Court of

Appeals affirmed the trial court’s judgment finding a

protected property interest and awarding attorney

5a

fees, but reversed the lower court’s directed verdict

and remanded the case for trial on damages. We

accepted the city’s discretionary appeal.

II. Legal Analysis

{71 6} Because Cleveland Construction alleges a

violation of procedural due process under Section 1983,

Title 42, U.S.Code, we must consider federal] rather

than state law in this case. “The elements of, and the

defenses to, a federal cause of action are defined by

federal law.” Howlett v. Rose (1990), 496 U.S. 356, 375,

110 S.Ct. 2430, 110 L.Ed.2d 332. Cleveland

Construction must first establish that it had a

constitutionally protected property interest before it

may claim a violation of procedural due process rights.

Bd. of Regents of State Colleges v. Roth (1972), 408

U.S. 564, 569-570, 92 S.Ct. 2701, 33 L.Ed.2d 548.

Although the company alleges that it had such an

interest in the drywall contract, it is well settled that

a constitutionally protected property interest exists

only when a claimant has “more than an abstract need

or desire for it. [The claimant] must have more than a

unilateral expectation of it. [The claimant] must,

instead, have a legitimate claim of entitlement to it.”

Id. at 577, 92 S.Ct. 2701, 33 L.Ed.2d 548.

Furthermore, not all benefits rise to the level of

entitlements; a “benefit is not a protected entitlement

if government officials may grant or deny it in their

discretion.” Town of Castle Rock, Colorado v. Gonzales

(2005), 545 U.S. 748, 756, 125 S.Ct. 2796, 162 L.Ed.2d

658.

{7 7} The Sixth Circuit Court of Appeals has held

that a property interest in a public contract is created

6a

in two situations: one, when a bidder is actually

awarded a contract and then deprived of it; and two,

when a governmental entity has limited discretion in

awarding the contract yet abuses that discretion.

United of Omaha Life Ins. Co. v. Solomon (C.A.6,

1992), 960 F.2d 31, 34. Because Cleveland

Construction was never actually awarded the contract

and then deprived of it, the company has a property

interest only if the city had no discretion to reject

Cleveland Construction’s bid or the city had such

limited discretion that failing to award the contract to

Cleveland Construction amounted to an abuse of

discretion.

{7 8} To determine whether the city had the

discretion to deny Cleveland Construction the drywall

contract, we must look both to the city’s municipal

ordinances and the language of the relevant bid

documents. In awarding contracts, the city retains

broad discretion to accept and reject bids generally.

Cincinnati Municipal Code 321-43 states that “[t]he

City purchasing agent, City manager, or any other

duly authorized contracting officer may reject any bid

for any reason or all bids for no reason if acceptance of

the lowest and best bid is not in the best interests of

the City.” (Emphasis added.)

{f1 9} In this case, the city’s bid package, which

contained the invitation to bid and the bidding

requirements, siinilarly reserved the right of the city

to “reject any and all bids or parts of any bid * * * and

not award a contract” and to “consider all elements

entering into the question of determining the

responsibility of the bidder.” The documents also

stated that “[alny bid which is incomplete * * * or

7a

which contains * * * irregularities of any kind, may be

cause for rejection of [the] bid.” The invitation to bid

also informed potential bidders that they “will be

subject to the provisions of the City of Cincinnati * * *

Small Business Enterprise Program. Failure of a

bidder to comply with these requirements may be

cause for rejection of the bid.”

{91 10} Clearly, the Cincinnati Municipal Code and

the bidding documents are united in emphasizing the

city’s broad discretion to grant or deny contracts. In

fact, the city is not required to award a contract at all

if it is dissatisfied with any of the submitted bids.

{jl 11} In bidding the drywall contract, the city

exercised its considerable discretion to reject the entire

first round of bids because none of the bids conformed

to the SBE requirements. Cleveland Construction’s bid

was among those rejected, and the company did not

challenge the city’s decision.

{{i 12) The First District Court of Appeals held,

however, that the broad discretion granted to the city

in awarding the drywall contract was not unlimited

and that the city had abused its discretion in denying

Cleveland Construction the contract. In so holding, the

court relied upon Cincinnati Municipal Code 321-

37(c)(4). That section states that “[iJn the event that

the selection of the lowest and best bidder is based

primarily upon [SBE requirements], the contract

award may be made subject to the following limitation:

the bid may not exceed an otherwise qualified bid by

ten (10%) percent or Fifty Thousand Dollars

($50,000.00), whichever is lower.”

8a

{% 13} Both the First District and Cleveland

Construction interpret this section to mean that when

the SBE requirements are the deciding factor in

awarding a contract, a qualified bid may still be

rejected if it exceeds the next lowest qualified bid by

ten percent or $50,000, whichever is lower.

{{ 14} The First District’s interpretation is only

one possible interpretation of this section, however.

The other, advanced by the city, is that Cincinnati

Municipal Code 321-37(c)(4) is merely a limitation that

the city may impose upon a contract at its discretion

(“the contract award may be made subject to” a cap).

The cap is not required, according to the city, and it

may impose the cap or not, relying only on its own

judgment. To support its argument, the city cites

Cincinnati Municipal Code 321-1-M, which provides

that “may” is always used as a permissive term. Thus,

when Section 321-37(c)(4) of the code states that an

award may be limited by a cap, the city contends, the

cap must be viewed as discretionary and not

mandatory. Additionally, the cit y code provides that

bids may be rejected for an y reason or for no reason.

Cincinnati Municipal Code 321-43. The city argues

that the First District’s conclusion ignores both of the

above sections and thwarts what is cleacly a theme in

the code and in the bidding documents: that the city

may take into account any number of factors in

considering bids and is in no event required to award

a contract to an y particular bidder.

{9 15} Nevertheless, it is unnecessary for us to

resolve the question of which interpretation is correct

in order to determine whether Cleveland Construction

had a property interest in the drywall contract. Even

9a

if we were to accept the First District’s conclusion that

Cincinnati Municipal Code 321-37(c)(4) limits the city’s

discretion to award a contract to a higher bidder when

the award is made based upon SBE considerations,

that conclusion does not mean that the city must

award the contract to the lowest bidder, which in this

case is Cleveland Construction. Simply because the

city might be prohibited from accepting a specific bid

does not mean that it loses its discretion to reject other

bids for any reason. Even if the city had abused its

discretion by awarding the drywall contract to Valley,

it does not follow that it also abused its discretion by

denying the contract to Cleveland Construction.

{ff 16} The outcome of this case would be different

if the contract and relevant municipal ordinances said

that the contract would be awarded to the “lowest

bidder.” Instead, they said that the contract would be

awarded to the “lowest and best bidder.” (Emphasis

added.) Cincinnati Municipal Code 321-37(a). And

even the lowest and best bid may be rejected if the bid

“is not in the best interests of the city.” Cincinnati

Municipal Code 321-43.

{i 17} Given the extensive discretion of the city in

considering bids, Cleveland Construction had no

property right in the drywall contract at issue in this

case. No property interest is created when a city

properly exercises its discretion and does not award a

contract to a party deemed not to have complied with

the requirements of the invitation to bid. Because the

cit y did not abuse its discretion, no property interest

in the contract ever existed.

10a

III. Conclusion

{7 18} Because we hold that Cleveland

Construction did not have a property interest in the

drywall contract, it is unnecessary for us to address

the remaining proposition of law regarding whether a

disappointed bidder can recover lost profits in an

action under Section 1983, Title 42, U.S.Code. A

property interest is a necessary prerequisite to

maintaining a Section 1983 action for deprivation of

procedural due process. Roth, 408 U.S. at 569-570, 92

S.Ct. 2701, 33 L.Ed.2d 548.

{W% 19} The judgment of the court of appeals is

therefore reversed, and judgment is entered for the

city.

Judgment reversed.

MOYER, C.J., and LUNDBERG STRATTON,

O’CONNOR, O’DONNELL, and CUPP, JJ., concur.

PFEIFER, J., dissents and would affirm the

judgment of the court of appeals.

LUNDBERG STRATTON, J., concurring.

{J 20) I agree that Cleveland Construction, Inc. did

not have a property interest in the drywall contract

awarded by the city of Cincinnati. I write to

emphasize that I reach that conclusion on the narrow

facts of this case. State law mandates only that public

contracts of this magnitude be awarded to the “lowest

and best bidder.” R.C. 735.05. The Cincinnati

Municipal Code also requires the city to select the

lla

“lowest and best bidder,” but provides the city with

broad discretion to “reject any bid for any reason.”

Cincinnati Municipal Code 321-37 and 321-43. In

addition, the city’s bid package gave the city broad

discretion to reject a bid. Based upon these explicit

factors in this case, I must concur with the majority.

However, in cases involving other cities and under

other circumstances, the outcome ma y be different.

{1 21} The Cincinnati City Council, in accordance

with the city code, established the process for

awarding city contracts, and the city of Cincinnati

afforded broad discretion to determine the “lowest and

best bidder” for the city. “Generally, courts in this

state should be reluctant to substitute their judgment

for that of city officials in determining which party is

the ‘lowest and best bidder.” Cedar Bay Constr., Inc.

v. Fremont (1990), 50 Ohio St.3d 19, 21, 552 N.E.2d

202. However, such broad discretion without real

parameters also may give rise to opportunities for

abuse, unfairness, or partiality in the bidding process.

Yet a bidder in such a case faces insurmountable

obstacles in challenging the bid because the discretion

is so broad. Nevertheless, efforts to improve the city’s

bidding procedures must be directed toward the city’s

governing body or to the Genera] Assembly to establish

stricter requirements in the bidding process under

R.C. 735.05. Therefore, I reluctantly concur.

Statman, Harris & Eyrich, L.L.C., W. Kelly

Lundrigan, and Elizabeth L. Hutton, for appellee.

Julia L. McNeil, Cincinnati City Solicitor, and

Richard Ganulin and Mary Frances Clark, Assistant

City Solicitors, for appellant.

12a

Stephen L. Byron, Adam J. Rosplock, and John

Gotherman, urging reversal for amicus curiae Ohio

Municipal League.

Thomas R. Winters, First Assistant Attorney

General, William P. Marshall, Solicitor General, and

Susan M. Sullivan and Ara G. Mekhjian, Assistant

Solicitors, urging reversal for amicus curiae state of

Ohio.

Michael R. Gareau & Associates Co., L.P.A., and

David M. Gareau, urging affirmance for amicus curiae

Pacific Legal Foundation.

Ross, Brittain & Schonburg Co., L.P.A., and Alan

G. Ross, urging affirmance for amicus curiae Northern

Ohio Chapter of Associated Builders and Contractors.

;

;

Pp

l3a

SUPREME COURT OF OHIO

No. 2007-0114

[Filed May 21, 2008]

Cleveland Construction, Inc.,

Vv.

City of Cincinnati, and Timothy Riordan,

Bernadine Franklin, Nate Mullaney,

Alicia Townsend, Kathi Ranford, and

Valley Interior Systems, Inc.

i i a

JUDGMENT ENTRY

APPEAL FROM THE COURT OF APPEALS

This cause, here on appeal from the Court of

Appeals for Hamilton County, was considered in the

manner prescribed by law. On consideration thereof,

the judgment of the court of appeals is reversed, and

judgment is entered for the city, consistent with the

“opinion rendered herein.

It is further ordered that costs are assessed

pursuant to S.Ct.Prac.R XI(5) and that a mandate be

sent to the Court of Common Pleas for Hamilton

County to carry this judgment into execution and that

a copy of this entry be certified to the Clerk of the

Court of Appeals for Hamilton County for entry.

14a

(Hamilton County Court of Appeals: Nos. C050749,

C050779, and C050888)

THOMAS J. MOYER

Chief Justice

l5a

APPENDIX C

SUPREME COURT OF OHIO

No. 2007-0114

[Filed December 12, 2007]

Cleveland Construction, Inc.,

v.

City of Cincinnati, and Timothy Riordan,

Bernadine Franklin, Nate Mullaney,

Alicia Townsend, Kathi Ranford, and

Valley Interior Systems, Inc.

ee i a a

ENTRY

This cause is pending before the Court as an appeal

from the Court of Appeals for Hamilton County. Upon

consideration of appellant’s motion for leave to add

proposition of law to pending appeal and memorandum

in support,

It is ordered by the Court that the motion is denied.

(Hamilton County Court of Appeals; Nos. C050749,

C050779, and C050888)

THOMAS J. MOYER

Chief Justice

17a

APPENDIX D

SUPREME COURT OF OHIO

2007-0114

[Filed May 2, 2007]

Cleveland Construction, Inc.

Appellant/Cross-Appellee,

We

City of Cincinnati, et al

Appellees/Cross-Appellants.

Nee eee eee ee”

Hamilton App. Nos. C-050749, C-050779, and

C-050888, 2006 Ohio 6452, 864 N.E.2d 116.

Cleveland Constr., Inc. v. City of Cincinnati, 2006

Ohio 6452, 864 N.E.2d 116, 2006 Ohio App. LEXIS

6410 (Ohio Ct. App., Hamilton County, 2006)

JUDGES: O’Donnell, J., would accept the appeal.

Lanzinger, J., would accept the appeal. Pfeifer and

Cupp, JJ., dissent.

OPINION:

APPEAL ACCEPTED FOR REVIEW

18a

Discretionary appeal accepted on Proposition of

Law Nos. I and III.

O’Donnell, J., would accept the appeal on Proposition

of Law No. I only. Lanzinger, J., would accept the

appeal on Proposition of Law No. III only. Pfeifer and

Cupp, JJ., dissent.

at iS a el PR i ef kk &

pete Bet Se,

19a

APPENDIX E

IN THE SUPREME COURT OF OHIO

CASE NO. 07-0114

APPEAL NO. C050749, APPEAL NO. C050779

APPEAL NO. C050888

(Consolidated)

[Filed January 22, 2007]

CITY OF CINCINNATI

Defendant-Appellant

Vv.

CLEVELAND CONSTRUCTION, INC.

Plaintiff-Appellee

ee ae ae ee a a a

COURT OF APPEALS

FIRST APPELLATE DISTRICT

CASE NO. A-0402638

MEMORANDUM IN SUPPORT OF

JURISDICTION OF DEFENDANT-

APPELLANT CITY OF CINCINNATI

JULIA L. MCNEIL (0043535)

City Solicitor

20a

RICHARD GANULIN (0025642C)

MARY FRANCES CLARK (0077497)

Assistant City Solicitors

CITY OF CINCINNATI

801 Plum Street, Room 214

Cincinnati, Ohio 45202

Telephone: (513) 352-3329

Facsimile: (513) 352-1515

richard.ganulin @cincinnati-oh.gov

mary.clark @ cincinnati-oh.gov

Attorneys for Defendant-Appellant

City of Cincinnati

W. KELLY LUNDRIGAN (0059211)

GARY E. POWELL (0037546)

MANLEY BURKE

225 West Court Street

Cincinnati, Ohio 45202

Telephone: (513) 721-5525

Facsimile: (513) 721-4268

wkl.@manleyburke.com

gpowell@manleyburke.com

Attorneys for Plaintiff-Appellee

Cleveland Construction, Inc.

eek

IIT.

2la

TABLE OF CONTENTS

EXPLANATION OF WHY THIS CASE ISA

CASE OF PUBLIC AND GREAT GENERAL

I i thee ck so ake eee pean de

STATEMENT OF THE CASE AND FACTS .

ARGUMENT IN SUPPORT OF

PROPOSITIONS OF LAW ..............

Proposition of Law No. I

Under Ohio law, a disappointed bidder for a

City of Cincinnati public contract does not

have a constitutionally protected property

eabonmes Ges Gee Gaeermes 2... wt ee

Proposition w No. 2

To prove a deprivation of its right to

procedural due process, a disappointed

bidder with a constitutionally protected

property interest in a public contract must

establish that the government entity did not

provide sufficient notice and opportunity to

ES Aig iaitl a Oe a's 00a 08s oes ed Oe

Proposition of Law No. 3

A disappointed bidder for a public contract

in Ohio cannot recover lost-profit damages in

a 42 U.S.C. 1983 action alleging a

deprivation of procedural due process ....

i

10

22a

Proposition of Law No. 4

A plaintiff does not have standing to seek an

injunction against file operation of a

municipal corporation unless the plaintiff

pleads and proves a concrete and imminent

TTC TET TEC RE Ore

Proposition of Law No. 5

A subcontracting outreach program is not

impermissibly race-based or gender-based

when all bidders have an equal opportunity

to comply with the subcontracting outreach

program and the program does not create a

~~ PEST YC SEP CRE YT Cenere.

* * eK *

a

23a

APPENDIX F

IN THE COURT OF APPEALS

FIRST APPELLATE DISTRICT OF OHIO

HAMILTON COUNTY, OHIO

APPEAL NO. C-050749, C-050779, C-050888

[Filed January 18, 2007]

CLEVELAND CONSTRUCTION, INC.

Appellant/Cross-Appellee,

VS.

CITY OF CINCINNATI, et al.

)

)

)

)

)

)

Appellees/Cross-Appellants. )

)

ENTRY GRANTING MOTION

TO STRIKE APPLICATION

FOR RECONSIDERATION

This cause came on to be considered upon the

application of the appellees/cross-appellants for

reconsideration, the motion of the appellant/cross-

appellee to strike the application as untimely filed,

and the response of appellees/cross-appellants to the

motion to strike.

24a

The Court finds that the motion to strike the

application for reconsideration is well taken and is

hereby granted.

To The Clerk:

Enter Upon the Journal of the Court on Jan 18 2007

per order of the Court.

By: /s/

Acting Presiding Judge .

(Copies sent to all counsel)

:

:

;

4

25a

APPENDIX G

IN THE COURT OF APPEALS

FIRST APPELLATE DISTRICT OF OHIO

HAMILTON COUNTY, OHIO

APPEAL NOS. C-050749, C-050779, C-050888

TRIAL NO. A-0402638

[Filed December 8, 2006]

CLEVELAND CONSTRUCTION, INC.,

Plaintiff-Appeliant/

Cross-Appellee,

vs.

CITY OF CINCINNATI,

Defendant-Appellee/

Cross-Appellant,

)

)

)

)

)

)

)

)

)

)

and )

)

TIMOTHY RIORDAN, )

)

BERNADINE FRANKLIN, )

)

NATE MULLANEY )

)

ALICIA TOWNSEND, )

)

)

KATHI RANFORD,

26a

and

VALLEY INTERIOR SYSTEMS, INC.,

Defendants-Appellees.

ee a a ee

JUDGMENT ENTRY

This cause was heard upon the appeal, the record,

the briefs, and arguments.

The judgment of the trial court is affirmed in part,

reversed in part, and cause remanded for the reasons

set forth in the Opinion filed this date.

Further, the court holds that there were reasonable

grounds for this appeal, allows no penalty and orders

that costs are taxed under App. R. 24.

The court further orders that 1) a copy of this

Judgment with a copy of the Opinion attached

constitutes the mandate, and a) the mandate be sent

to the trial court for execution under App. R. 27.

To The Clerk:

Enter upon the Journal of the Court on

December 8, 2006 per Order of the Court.

By: /s/Hildebrandt

Presiding Judge

27a

APPENDIX H

IN THE COURT OF APPEALS

FIRST APPELLATE DISTRICT OF OHIO

HAMILTON COUNTY, OHIO

APPEAL NOS. C-050749, C-050779, C-050888

TRIAL NO. A-0402638

[Filed December 8, 2006]

CLEVELAND CONSTRUCTION, INC.,

Plaintiff-Appellant/

Cross-Appellee,

vs.

CITY OF CINCINNATI,

Defendant-Appellee/

Cross-Appellant,

and

TIMOTHY RIORDAN,

BERNADINE FRANKLIN,

NATE MULLANEY,

ALICIA TOWNSEND,

ee ee ee ee ee ee

28a

KATHI RANFORD,

and

VALLEY INTERIOR SYSTEMS, INC.,

Defendants-Appellees.

Nee eee eee ee ee”

Civil Appeals From: Hamilton County Court of

Common Pleas.

Judgment Appealed From Is: Affirmed in Part,

Reversed in Part, and Cause Remanded.

Date of Judgment Entry on Appeal: December 8, 2006

SYLVIA SIEVE HENDON, Judge.

OPINION

{¥1} This case arose from the city of Cincinnati’s

rejection of a bid by Cleveland Construction Co. for

drywall work on the expansion and renovation of the

Cincinnati Convention Center. At the heart of the

dispute was the city’s implementation of its small

business enterprise (SBE) program.

{42} Cincinnati Municipal Code (CMC) 321-37

required the city to award a construction contract to

the lowest and best bidder. The ordinance set forth a

non-exhaustive list of factors that the city purchasing

agent could consider in determining the lowest and

best bid. One of the factors that could be considered

was a contractor’s compliance with the rules and

29a

regulations of the city’s SBE Subcontracting Outreach

Program.’

{J3} Where a lowest-and-best determination was

based primarily on the contractor’s subcontracting-

outreach compliance, the ordinance had a built-in cap.

The contract award could be made, “subject to the

following limitation: the bid could not exceed an

otherwise qualified bid by ten (10%) percent or Fifty

Thousand Dollars ($50,000.00), whichever is lower.”

The cap was apparently intended to strike a balance

between the city’s efforts to include small businesses

in public contracts and the city’s interest in protecting

its taxpayers from excessive costs.

{44} On December 23, 2003, the city issued an

invitation to bid on the Cincinnati Convention Center

Expansion and Renovation Project, entitled “Bid

Package C/TC-09A Drywall.” The city required bidders

to show that they had made a good-faith effort to

obtain the participation of SBEs on the project. For the

drywall-contract bids, the city established a mandatory

SBE-participation goal of 35%. Bidders were notified

that their failure to meet the SBE-participation goal

could cause a bid to be rejected as nonresponsive. The

city received bids until February 5, 2004.

{"¥5} On February 11, 2004, Kathi Ranford, a

contract-compliance officer, reported to Bernadine

Franklin, the city’s purchasing agent, that none of the

* CMC 321-37(c4).

2 CMC 321-37(c).

30a

three bidders for the project’s drywall contract had

complied with the 35% SBE-participation requirement.

According to Ranford, Cleveland had submitted a bid

with 3% SBE participation, Valley Interior Systems

had submitted a bid with 34% SBE participation, and

Kite, Inc., had submitted a bid with no SBE

participation. In that round of bidding, Cleveland’s bid

had been the lowest-dollar bid.

{{6} Because none of the bidders had achieved the

full 35% SBE-participation goal, the city conducted an

emergency rebidding for the drywall contract. On

February 24, 2004, Ranford notified Franklin that

Cleveland had submitted a re-bid for $8,889,000, with

10% SBE participation, and that Valley had submitted

a re-bid for $10,135,022, with 40% SBE participation.

{{7} The city’s office of contract compliance

deemed Cleveland’s bid to be unacceptable due to its

failure to achieve 35% SBE participation. In all other

respects, however, Cleveland’s bid had been found

acceptable according to the city’s purchasing division.

{18} Following a review of the acceptability of the

bids, Franklin issued a recommendation to Timothy

Riordan, an assistant city manager, that the drywall

contract be awarded to Vailey. Franklin’s

recommendation stated, “Pursuant to Section 321-37

of the Municipal Code, the bid submitted by [Valley]

has been determined to be the lowest and best bid.”

{{9} Valley’s new bid exceeded Cleveland’s new

bid by $1,246,022, well over the $50,000 or 10% cap in

CMC 321-37. Nonetheless, on March 3, 2004, the city

awarded the drywall contract to Valley and instructed

3la

Valley to commence work under the terms of the

contract.

Cleveland Files Suit

{10} Three weeks later, on March 30, 2004,

Cleveland brought an action for injunctive relief and

damages against the city, several city employees, and

Valley. Cleveland asked the court to restrain the city

and Valley from proceeding on the drywall contract

and to order the city to award the contract to

Cleveland.

{¥11} In addition, Cleveland sought declarations by

the court that (1) the city’s award of the contract

violated CMC 321-37; (2) the city’s drywall contract

with Valley was void; (3) the city’s SBE program was

unconstitutional and in violation of Section 1983, Title

42, U.S.Code; (4) the city had deprived Cleveland of a

property interest; (5) Cleveland was the lowest and

best bidder; and (6) the city’s delegation of discretion

to its purchasing agent under the SBE subcontracting-

outreach program was void.

{{12} Finally, Cleveland sought compensatory and

punitive damages, as well as attorney fees and costs.

{{13} The trial court denied Cleveland’s motion for

a temporary restraining order. Later, upon motion, the

trial court dismissed the city employees from the

action.

{714} In June 2005, the case proceeded to a jury

trial. At the close of Cleveland’s case, the trial court

directed a verdict in favor of the city and Valley on

32a

Cleveland’s claims for lost profits. Cleveland’s

remaining claims for injunctive and declaratory relief

and attorney fees were tried to the bench, by

agreement of the parties.

{¥15} Atthe conclusion of the trial, the court found

that the city had violated CMC 321-37 by awarding the

drywall contract to Valley rather than to Cleveland. As

a result, the court held, the city had abused its

discretion in a manner that had denied Cleveland the

contract in violation of its federally protected due-

process rights and in violation of Section 1983.

{16} The court held that the city’s SBE program

rules and guidelines created race- and gender-based

classifications that rendered the program facially

unconstitutional. The court further found that the city

had pressured and encouraged bidders. including

Cleveland, to draw upon race- and gender-based

classifications, in violation of Cleveland’s rights under

Section 1983. But the court held that Cleveland had

failed to establish that the denial of the drywall

contract was the result of the race- and gender-based

classifications; rather, it held that the denial had been

the result of the city’s preference for small businesses.

{{17} The court rendered a declaratory judgment

that precludes the city from awarding future contracts

to a bidder that exceeds the cap set forth in CMC 321-

37 if the bid selection is based primarily on the

bidders’ compliance with the SBE subcontracting-

outreach program.

{{18} Thecourt permanently enjoined the city from

maintaining or applying race-or gender-based

33a

classifications in its SBE rules and guidelines, absent

a formal determination that such _ race-based

provisions were narrowly tailored and necessary to

fulfill compelling governmental interests, or that such

gender-based provisions were substantially related to

genuine and important governmental] objectives.

({§19} Finally, the court entered judgment in favor

of Cleveland as the prevailing party, and against the

city, for Cleveland’s reasonable attorney fees and costs

pursuant to Section 1988, Title 42, U.S. Code. The

court also entered judgment in favor of Valley.

{720} On appeal, Cleveland argues that the trial

court erred by (1) directing a verdict in favor of the city

on Cleveland’s damage claims; (2) refusing to declare

Valley’s drywall contract to be void or to prohibit

performance under the contract; (3) ruling that

Cleveland could not elicit testimony from Valley’s

subcontractors with respect to post-contract events; (4)

denying Cleveland’s motion for a new trial; (5)

granting the motions to dismiss individual city

employees; and (6) making findings concerning

causation of damages.

{21} In its cross-appeal, the city argues that the

trial court (1) erred by applying CMC 321-37; (2)

lacked jurisdiction over Cleveland’s claims for

injunctive relief; (3) erred by concluding that the city

had deprived Cleveland of its right to procedural due

process; (4) erred by ruling that portions of the city’s

SBE program created constitutionally impermissible

race- and gender-based classifications; and (5) erred by

awarding attorney fees to Cleveland. We first address

the city’s assignments of error.

34a

The Application of CMC 321-37

{{22} In its first assignment of error, the city

argues that the trial court erred by applying CMC 321-

37 in its analysis of Cleveland’s claims. The city

contends that Franklin had not applied the provisions

of CMC 321-37 in her review of bids for the project

because the ordinance had not been in place at the

time the project’s “procurement process” was planned.

{{23} The record reflects that CMC 321-37 had

been adopted in _ specific contemplation of the

convention center project. By its terms, the ordinance

had been enacted as an emergency measure due to the

city’s “immediate need to proceed with the bidding of

the Convention Center and major development

projects.” The ordinance specifically applied to the

award of construction contracts that exceeded

$100,000. And the ordinance had gone into effect

before the project’s bid solicitation, and well before the

award of the drywall contract. So Franklin’s selection

of the lowest and best bidder was subject to CMC 321-

37.

{424} The city argues that “[e]ven though Valley’s

bid was $1.2 million more than Cleveland’s, the project

was well within the budget.” This argument fails to

take into account that “among the purposes of

competitive bidding legislation are the protection of

the taxpayer [and the] prevention of excessive costs.”*

The fact that the project was under budget was of

* Danis Clarkco Landfill Co. v. Clark Cty. Solid Waste Mgmt Dist.,

73 Ohio St.3d 590, 602, 1995 Ohio 301, 653 N.E.2d 646.

35a

questionable relevance and was certainly not

dispositive of the legality of the bid-selection process.

{{25} The city argues that even if Franklin had

applied CMC 321-37 to the drywall-contract bids, the

ordinance’s cap would not have come into play because

Cleveland’s bid was not an “otherwise qualified” bid.

But the city acknowledges in its brief that “[t)he trial

evidence established that Cleveland lost because its

drywall bid failed to reserve at least 35% of the work

for small business enterprises as the bid documents

required.” In other words, but for its SBE

noncompliance, Cleveland’s bid was qualified. Where

the sole reason that Cleveland’s bid was rejected was

its noncompliance with the SBE subcontracting-

outreach program, Cleveland was an “otherwise

qualified” bidder. Under these circumstances, Valley’s

SBE-comphant bid could not have exceeded

Cleveland’s bid by the $50,000 or 10% cap.

({26} Accordingly, we hold that the trial court

properly considered and applied CMC 321-37. We

overrule the city’s first assignment of error.

Cleveland’s Standing

i(27} In its second assigninent of error, the city

argues that the trial court lacked jurisdiction over

Cleveland’s claims for injunctive relief. The city

contends that the possibility that Cleveland might bid

on a city contract in the future did not create a risk

that it would again be subject to a deprivation of

rights.

36a

{28} In Ohio, it is well established that standing

to challenge the constitutionality of a legislative

enactment exists where a litigant “has suffered or is

threatened with direct and concrete injury in a manner

or degree different from that suffered by the public in

general, that the law in question has caused the

injury, and that the relief requested wil! redress the

injury.” *

{{29} In the context of a constitutional challenge to

a set-aside program, the “injury in fact” is the inability

to compete on an equal footing in the bidding process,

and not necessarily the loss of a contract. So to

establish standing, a party challenging a set-aside

program need only demonstrate that it is able and

ready to bid on contracts and that a discriminatory

policy prevents it from doing so on an equal basis.°

{730} At trial, the city specifically stipulated that

Cleveland intended and was able to bid on future city

construction projects. And the city’s discriminatory

policies would have affected Cleveland’s ability to

compete fairly. So Cleveland had sufficient standing to

seek injunctive relief against the city. We overrule the

city’s second assignment of error.

* State ex rel. Ohio Acad. of Trial Lawyers v. Sheward, 86 Ohio

St.3d 451, 469-470, 1999 Ohio 123, 715 N.E.2d 1062.

° Northeastern Fla. Chapter of Associated Gen. Contractors of Am.

v. Jacksonville (1993), 508 U.S. 656, 666, 113 S. Ct. 2297, 124 L.

Ed. 2d 586.

)

EE ee ee ee

.

37a

Deprivation of a Property Interest

{31} In its third assignment of error, the city

argues that the trial court erred by concluding that the

city had deprived Cleveland of a right to procedural

due process.

{¥32} One of the proscriptions of the Fourteenth

Amendment is the deprivation of a person’s property

interests without due process of law.® In a due-process

challenge based upon such a deprivation, we must first

determine whether a protected property interest was

at stake.

{{33} Property interests “are created and their

dimensions are defined by existing rules or

understandings that stem from an independent source

such as state law-rules or understandings that secure

certain benefits and that support claims of entitlement

to those benefits.”’ A person has a property interest in

a benefit, such as a public contract, if the person has a

legitimate claim of entitlement to it. A person’s

unilateral expectation of a benefit is not enough.?

® Bd. of Regents v. Roth (1972), 408 U.S. 564, 569-570, 92 S. Ct.

2701, 33 L. Ed. 2d 548.

"Id. at 577, 92 S. Ct. 2701.

® Cleveland Constr. v. Ohio Dept. of Admin. Servs., GSA (1997),

121 Ohio App. 3d 372, 394, 700 N.E.2d 54.

® Roth, supra, at 577, 92 S. Ct. 2701.

38a

{34} The Sixth Circuit Court of Appeals has held

that a disappointed bidder may establish a legitimate

claim of entitlement to a public contract in one of two

ways. A bidder can either show that it actually was

awarded the contract and then deprived of it, or that

the government abused its limited discretion in

awarding the contract to another bidder.*®

{{35} Generally, municipalities are vested with

broad discreticn in matters related to public contracts.

But that discretion is not limitless." For example, a

municipality “may by its actions commit itself to follow

rules it has itself established.””* :

{{36} In the context of lowest-and-best-bidder

determinations, Ohio courts are reluctant to substitute

their judgment for that of city officials.’ But where

city officials abuse the discretion vested in them,

courts will intervene.’* An abuse of discretion

“connotes more than an error of law or of judgment; it

implies an unreasonable, arbitrary, or unconscionable

attitude. * * * ‘Arbitrary’ means ‘without adequate

© United of Omaha Life Ins. Co. v. Solomon (C.A.6, 1992), 960

F.2d 31, 34; Enertech Elec. v. Mahoning County Commrs. (C.A.6,

1996), 85 F.3d 257, 260.

" Danis, supra, at 604, 1995 Ohio 301, 653 N.E.2d 646.

2 Id. at 603, 1995 Ohio 301, 653 N.E.2d 646.

'3 See Cedar Bay Constr., Inc. v. Fremont (1990), 50 Ohio St.3d 19,

552 N.E.2d 202.

"* Id. at 21-22, 552 N.E.2d 202.

39a

determining principle; * * * not governed by any fixed

rules or standard.’ * * * ‘Unreasonable’ means

‘irrational.”””*

{737} In this case, the city had established a “fixed

rule” with respect to the award of a contract based

primarily upon the bidder’s subcontracting-outreach

program compliance. In that instance, CMC 321-37

required the city to apply the ordinance’s cap.

{938} But, here, the evidence demonstrated that

the city had arbitrarily ignored the cap in awarding

the contract to Valley. Thus, we agree with the trial

court that the city’s failure to follow the directive of its

own ordinance constituted an abuse of discretion that

resulted in a deprivation of Cleveland’s property

interest in the contract award. We overrule the city’s

third assignment of error.

SBE Program Provisions Were

Facially Unconstitutional

{¥39} In its fourth assignment of error, the city

argues that the trial court erred by ruling that

elements of the rules and guidelines in the city’s SBE

program created constitutionally impermissible race-

and gender-based classifications. The city contends

that the program was a lawful “outreach” program

that encouraged contractors to use “good faith efforts”

to promote opportunities for minorities and females.

'® Dayton, ex rel. Scandrick v. McGee (1981), 67 Ohio St.2d 356,

359, 423 N.E.2d 1095 (emphasis added).

40a

{740} The Fourteenth Amendment requires strict

scrutiny of all race-based action by state and local

governments.” Racial classifications must serve a

compelling government interest and must be narrowly

tailored to further that interest.’’ Gender-based

classifications, by contrast, require an “exceedingly

persuasive” justification.”

{741} At trial, the city did not put forth any

argument or evidence to demonstrate that its SBE

program could withstand such heightened scrutiny.

Instead, the city relied on its assertion that increased

scrutiny should not apply in the first instance because

its SBE program created neither race- nor gender-

based classifications.

(¥42} On appeal, the city acknowledges that it had

predetermined estimates of the availability of

minorities and females for each trade represented in

the convention center project. But the city argues that

its availability estimates were for informational

purposes only, and that bidders were required to do

nothing in response.

{¥43) Racial or gender classifications may arise

- from a regulation’s strict requirements, such as

6 Richmond v. J.A. Croson Co. (1989), 488 U.S. 469, 109 S. Ct.

706, 102 L. Ed. 2d 854.

Adarand Constructors v. Pena (1995), 515 U.S. 200, 235, 115 S.

Ct. 2097, 132 L. Ed. 2d 158.

8 United States v. Virginia (1996), 518 U.S. 515, 533, 116 S. Ct.

2264, 135 L. Ed. 2d 735.

Ce ee ey ee”! Fa? een ae ea” ese

4la

mandated quotas or set-asides. But rigid mandates are

not a prerequisite to a finding of a racial

classification." Where regulations pressure or

encourage contractors to hire minority subcontractors,

courts must apply strict scrutiny.”

{144} For example, in Adarand Constructors v.

Pena,” the United States Supreme Court considered

federal regulations that provided financial incentives

to bidding contractors to hire minority subcontractors.

The regulations did not require contractors to use

minority subcontractors. But contractors would receive

additional compensation if they did so. The court held

that, to the extent that the regulations provided

incentives to contractors to use _ race-based

classifications, the regulations were subject to strict

scrutiny.”

{745} In determining whether strict scrutiny must

be applied to the city’s SBE program, we must look

behind its ostensibly neutral labels such as “outreach

program” and “participation goals.” The program’s

rules and guidelines “are not immunized from scrutiny

because they purport to establish ‘goals’ rather than

—>

'® Bras v. Calif. Pub. Utils. Comm. (C.A.9, 1995), 59 F.3d 869.

2° See Lutheran Church-Missouri Synod v. FCC (C.A.D.C., 1998),

332 U.S. App. D.C. 165, 154 F.3d 487; Monterey Mechanical Co. v.

Wilson (C.A.9 1997), 125 F.3d 702; Safeco Ins. Co. of America v.

White House (C.A.6, 1999), 191 F.3d 675.

" (1995), 515 U.S. 200, 115 S. Ct. 2097, 132 L. Ed. 2d 158.

22 Id. at 224, 115 S. Ct. 2097.

42a

‘quotas.’[Courts] look to the economic realities of the

program rather than the label attached to it.””

{46} Under the city’s SBE rules and guidelines,

all bidders were required to use “good faith efforts” to

promote opportunities for minority- and women-owned

businesses (MBEs and WBEs) to the extent of their

availability as determined by the city. With respect to

the drywall portion of the project, the city estimated

that the availability of MBEs was 13.09%, and that it

was 1.05% for WBEs.

{¥47} Bidders were required to provide detailed

descriptions of the techniques used to obtain

participation of MBEs and WBEs. The city would then

evaluate each bidder’s documented efforts to achieve

participation of MBEs and WBEs. If that review

determined that a bid’s utilization percentage for

MBEs and WBEs was lower than the estimated

availability for those groups, the bid would be flagged

for a discrimination investigation.

{{48} Where the city’s SBE program required

documentation of a bidder’s specific efforts to achieve

the participation of minority subcontractors to the

extent of their availability as predetermined by the

city, the program undeniably pressured bidders to

implement racial preferences.** Therefore, the

program’s rules must be subject to strict scrutiny. To

the extent that the rules pressured bidders to hire

*® Bras, supra, at 874.

* Safeco Inc., supra, at 692, citing Lutheran, supra, at 491.

43a

women-owned subcontractors, the city was required to

demonstrate an “exceedingly persuasive” justification

for the differential treatment.

{149} Given that the city effectively conceded that

it could not justify race- or gender-based classifications

under either standard of heightened scrutiny, the trial

court properly determined that those elements of the

program that caused bidders to use racial- or gender-

based preferences were unconstitutionally

impermissible.

Award of Attorney Fees

{{50} In its fifth assignment of error, the city

argues that the trial court erred by awarding attorney

fees to Cleveland. The city contends that Cleveland

was not entitled to the award because it was not a

prevailing party.

{51} A “prevailing party” is one who “succeed[s]

on any significant issue in litigation which achieves

some of the benefit the parties sought in bringing

suit.”” To be a “prevailing party,” there must have

been “a court-ordered ‘change [in] the legal

relationship” between the parties.” In this regard, a

* Hensley v. Eckerhart (1983), 461 U.S. 424, 433, 103 S. Ct. 1933,

76 L. Ed. 2d 40.

°° Buckhannon Bd. v. W. Va. Dept. of Health & Human Res.

(2001), 532 U.S. 598, 604, 121 S. Ct. 1835, 149 L. Ed. 2d 855.

44a

declaratory judgment may serve as the basis for an

award of attorney fees.”’

{752} But the entry of a declaratory judgment ina

party’s favor does not automatically render that party

a prevailing party under Section 1988.” “In all civil

litigation, the judicial decree is not the end but the

means. At the end of the rainbow lies not a judgment,

but some action (or cessation of action) by the

defendant that the judgment produces-the payment of

damages, or some specific performance, or the

termination of some conduct. Redress is sought

through the court, but from the defendant. This is no

less true of a declaratory judgment suit than of any

other action. The real value of the judicial

pronouncement - what makes it a proper judicial

resolution of a ‘case or controversy’ rather than an

advisory opinion - is in the settling of some dispute

which affects the behavior of the defendant towards the

plaintiff .” (Emphasis in original.)”

{{53} We hold that the trial court did not abuse its

discretion in ordering attorney fees. Cleveland

successfully challenged the unconstitutional race- and

gender-based provisions of the city’s SBE program. As

a result, the city will no longer be permitted to apply

those provisions against Cleveland or other bidders on

*" Hewitt v. Helms (1987), 482 U.S. 755, 761, 107 S. Ct. 2672, 96 L.

Ed. 2d 654.

* Rhodes v. Stewart (1988), 488 U.S. 1, 109 S. Ct. 202, 102 L. Ed.

2d 1.

*® Hewitt, supra, at 761, 107 S. Ct. 2672.

45a

city contracts. In that regard, Cleveland was a

prevailing party because the judgment had a distinct

efiect on the city’s behavior. Accordingly, we overrule

the city’s fifth assignment of error.

Directed Verdict

{954} In its complaint, Cleveland sought damages

for the loss of profits that it would have realized had it

been awarded the drywall contract. Cleveland now

argues in its first assignment of error that the trial

court erred by directing a verdict in favor of the city on

its lost-profits claim.

{155} In considering a motion for a directed

verdict, a trial court must construe the evidence most

strongly in favor of the party against whom the motion

is made.” In doing so, if the court “finds that upon any

determinative issue reasonable minds could come to

but one conclusion upon the evidence submitted and

that conclusion is adverse to such party, the court

shall sustain the motion and direct a verdict for the

moving party as to that issue.”

{{56} “A motion for directed verdict * * * does not

present factual issues, but a question of law, even

though in deciding such a motion, it is necessary to

review and consider the evidence.” Because a

” Civ.R. 50(A)4).

*' Civ.R. 50(AX4).

*? Goodyear Tire & Rubber Co. v. Aetna Cas. & Sur. Co., 95 Ohio

St.3d 512, 2002 Ohio 2842, 769 N.E.2d 835, 94, quoting O’Day v.

46a

question of law is presented, we apply a de novo

standard of review to a directed verdict.”

{{57} Cleveland acknowledges that the Ohio

Supreme Court’s recent decision in Fairlawn uv.

Cementech™ resolves its claim for damages under state

law. In Cementech, the court held that when a

municipality violates competitive-bidding laws in

awarding a competitively bid project, a disappointed

bidder cannot recover its lost profits as damages.

{158} But in addition to its claim for damages

under state law, Cleveland sought damages under

federal law, Section 1983, Title 42, U.S.Code, for the

city’s deprivation of its property interest in the drywall

contract. Under Section 1983, a party who has been

deprived of a federal right under the color of state law

may seek relief through “an action at law, suit in

equity, or other proper proceeding for redress.”

{459} The basic purpose of a Section 1983 damage

award is to compensate persons for injuries caused by

the deprivation of constitutional rights. For this

reason, no compensatory damages may be awarded in

Webb (1972), 29 Ohio St.2d 215, 280 N.E.2d 896, paragraph three

of the syllabus.

33 Cleveland Elec. Illum. Co. v. Pub. Util. Comm., 76 Ohio St.3d

521, 523, 1996 Ohio 298, 668 N.E.2d 889.

* 109 Ohio St.3d 475, 2006 Ohio 2991, 849 N.E.2d 24.

*® Carey v. Piphus (1978), 435 U.S. 247, 253-254, 98S. Ct. 1042, 55

L. Ed. 2d 252.

47a

a Section 1983 suit without proof of actual injury.*

The level of a person’s compensatory damages under

Section 1983 is ordinarily determined according to

principles derived from the common law of torts.”

{960} In Adarand Constructors v. Pena, the

United States Supreme Court considered whether a

rejected bidder had standing to seek injunctive relief

against future application of a minority set-aside

program. In doing so, the Court presumed that the

rejected bidder was entitled to seek damages for the

lost contract:

{61} “Adarand, in addition to its general prayer

for ‘such other and further relief as to the Court seems

just and equitable,’ specifically seeks declaratory and

injunctive relief against any future use of

subcontractor compensation classes. * * * Before

reaching the merits of Adarand’s challenge, we must

consider whether Adarand has standing to seek

forward-looking relief. Adarand’s allegation that it has

lost a contract in the past because of a subcontractor

compensation clause of course entitles it to seek

damages for the loss of that contract [.)” (Emphasis

added.)

*® Memphis Community Sch. Dist. v. Stachura (1986), 477 U.S.

299, 306, 106 S. Ct. 2537, 91 L. Ed. 2d 249.

* Id. at 306-307, 106 S. Ct. 2537.

%6 (1995), 515 U.S. 200, 115 S. Ct. 2097, 132 L. Ed. 2d 158.

48a

{162} Those damages may include a disappointed

bidder’s lost profits.* In W.H. Scott Constr. Co., Inc. v.

Jackson,*° the Fifth Circuit Court of Appeals

considered an equal-protection challenge to a policy

encouraging minority participation in city construction

projects. The court upheld an award of lost profits to a

rejected bidder who had sought damages from the city

under Section 1983.

{{63} Similarly, in Hershell Gill Consulting

Engineers, Inc. v. Miami-Dade Cty., Fla.,*’ the court

held that a county was liable to the plaintiffs under

Section 1983 for any compensatory damages resulting

from its unconstitutional affirmative-action programs.

The court held that the plaintiffs’ damages could

include their lost profits, but that the plaintiffs in that

case had failed to prove that any actual losses had

resulted from the unconstitutional programs.”

{764} In this case, the trial court concluded that

Cleveland’s failure to adduce evidence concerning the

degree of completion of the drywall contract precluded

Cleveland from proceeding on its claim for money

damages. The court reasoned that Cleveland’s

damages were speculative, not due to a failure of proof

as to Cleveland’s anticipated profits, but due to the

3° See Flores v. Pierce (C.A.9, 1980), 617 F.2d 1386, 1392;

Chalmers v. Los Angeles (C.A.9, 1985), 762 F.2d 753.

“(C.A.5, 1999), 199 F.3d 206.

“' (S.D.Fla.2004), 333 F. Supp. 2d 1305.

* Id. at 1339.

49a

court’s misapprehension that Cleveland’s damage

claim was wholly dependent on its claim for injunctive

relief.

{165} Certainly, the status of the drywall project

would have been relevant to a determination of any

injunctive relief the court may have awarded, but that

evidence was not critical to Cleveland’s claim for

Section 1983 damages. In effect, the trial court’s entry

of a directed verdict on the damage claim precluded

Cleveland from seeking redress, even though

Cleveland could have waited to file suit until the

drywall contract had been completed. The issuance of

a directed verdict on the issue of Section 1983 damages

before the contract’s completion had the absurd result

of denying redress because of Cleveland’s diligence in

asserting its claims.

{{66} We recognize that a plaintiff seeking redress

under Section 1983 is required to mitigate its

damages.** But once the plaintiff has presented

evidence of damages, the defendant has the burden of

establishing the plaintiffs failure to properly mitigate

damages.“ So once Cleveland presented evidence of

damages, the burden of proof on the issue of mitigation

was on the city.

{767} Because a jury could have concluded that

Cleveland had established all the elements of its

*® Meyers v. Cincinnati (C.A.6, 1994), 14 F.3d 1115, 1119.

“ Id., citing Rasimas v. Michigan Dept. of Mental Health (C.A.6,

1983), 714 F.2d 614.

50a

Section 1983 claim for damages, we hold that a

directed verdict in favor of the city was unwarranted.

Consequently, we sustain Cleveland’s first assignment

of error in part, reverse the entry of the directed

verdict on the Section 1983 damage claim, and remand

the case for a new trial on the issues of liability and

damages with respect to Cleveland’s lost-profits claim

under Section 1983.

{{68} Because Cleveland’s fourth and_ sixth

assignments of error relate to the trial court’s

dismissal of its damage claims, we address the

assignments out of order. Cleveland argues that the

trial court erred by denying its motion for a new trial,

given the court’s erroneous dismissal of its damage

claim under Section 1983. Cleveland also contends

that the trial court erred by making “a finding that,

essentially, amountled] to a directed verdict on the

issue of proximate causation of Cleveland’s damages in

addition to that given at trial.” For the reasons set

forth in our disposition of Cleveland’s first assignment

of error, we sustain the fourth and sixth assignments

of error.

The Denial of Injunctive Relief

{{69} In its second assignment of error, Cleveland

argues that the trial court erred by refusing to declare

the drywall contract unenforceable and by failing to

enjoin performance of the contract. Cleveland contends

that the trial court should have enjoined performance

of the contract despite the fact that substantial work

had been completed on the project.

5la

{70} An appellate court need not consider an issue

where the court becomes aware of an intervening event

that has rendered the issue moot.*° The duty of an

appellate court is to decide actual controversies

between parties and to render judgments that may be

carried into effect.“° “Thus, when circumstances

prevent an appellate court from granting relief in a

case, the mootness doctrine precludes consideration of

those issues.”*’ For example, in the context of appeals

involving construction projects, Ohio courts have held

that an appeal is rendered moot where the appellant

fails to obtain a stay of execution of the trial court’s

judgment and construction commences.

{{71} In this case, there is no dispute that the

convention center project, which was substantially

completed at the time that the trial court denied the

injunction, is now completed in its entirety. At no point

in the proceedings did Cleveland obtain a stay of the

*’ Cincinnati Gas & Elec. Co. v. PUC of Ohio, 103 Ohio St.3d 398,

2004 Chio 5466, 816 N.E.2d 238, at 715, citing Miner v. Witt

(1910), 82 Ohio St. 237, 238, 92 N.E. 21, 8 Ohio L. Rep. 71.

‘© Miner, supra, at 238, 92 N_E. 21.

*? Schwab v. Lattimore, 166 Ohio App. 3d 12, 2006 Ohio 1372, 848

N.E.2d 912, at 410.

“® Schuster v. Avon Lake, 9" Dist. No. 03CA008271, 2003 Ohio

6587, at 13; Pinkney v. Southwick Invs., L.L.C., 8 Dist. Nos.

85074 and 85075, 2005 Ohio 4167; Bd. of Commrs. v. Saunders,

2™ Dist. No. 18592, 2001 Ohio 1710; Smola v. Legeza, 11" Dist.

No. 2004-A-0038, 2005 Ohio 7059; Redmon v. City Council, 10"

Dist. No. O5AP-466, 2006 Ohio 2199.

52a

trial court’s denial of its request for a temporary

restraining order. In fact, as the trial court pointed

out, Cleveland did not pursue preliminary injunctive

relief for an entire year. Instead, Cleveland acceded to

several continuances. In denying Cleveland’s motion

for a preliminary injunction, the trial court noted the

following:

{¥72} “The court at this time will deny Cleveland’s

motion for injunctive relief pending trial. The parties’

desires with regard to the scheduling of this case have

been solicited on a regular basis. After the action was

removed to and returned from federal court, Cleveland

opted not to seek a prompt hearing on [a] preliminary

injunction, but sought rather to engage in the

extended discovery reflected in the voluminous

materials relating to the summary judgment motions.

Cleveland then waited to the final day of the

dispositive motion period - almost one year after the

action was filed and roughly three months prior to the

scheduled June 20, 2005 trial date - to pursue its

preliminary injunction request.”

{773} At this point, we can not render a judgment

that could be carried into effect with respect to the

performance of the drywall contract. Even if we

concluded (which we expressly do not) that the trial

court had erred in failing to enjoin the contract’s

performance, our opinion would only be advisory in

nature. Consequently, we decline to address the

assignment of error on its merits.

53a

Evidentiary Rulings

{174} In its third assignment of error, Cleveland

argues that the trial court erred by ruling that it could

not elicit testimony from Valley’s subcontractors about

events that had occurred after the city had awarded

the contract to Valley. In support of its argument,

Cleveland directs us to its examination of one of

Valley’s subcontractors, Marti Stouffer-Heis, owner of

MS Construction Consultants.

{{75}) “Relevant evidence” is defined by Evid.R. 401

as “evidence having any tendency to make the

existence of any fact that is of consequence to the

determination of the action more probable or less

probable than it would be without the evidence.”

Evid.R. 402 provides that relevant evidence is

admissible, subject to enumerated exceptions, and that

evidence that is not relevant is not admissible.

Although the terms of Evid.R. 402 are mandatory, a

trial court is vested with broad discretion in

determining whether evidence is relevant.*® A

reviewing court is, therefore, limited to a

determination of whether the trial court abused its

discretion in admitting or excluding the disputed

evidence.”

*° See Cincinnati v. Banks (2001), 143 Ohio App. 3d 272, 287, 757

N.E.2d 1205; Siuda v. Howard, 1" Dist. Nos. C-000656 and C-

000687, 2002 Ohio 2292, 425.

*° See Banks, supra.

54a

{776} Cleveland’s attorney attempted to elicit

testimony from Stouffer-Heis about the city’s post-

award enforcement of its SBE program. Counsel asked

whether Stouffer-Heis had been able to perform her

described “{llogistics, project coordination” tasks at the

construction site, and whether the city had performed

any investigation upon submission of her request to be

certified as an SBE supplier.

{77} The trial court indicated that it would allow

testimony by a subcontractor with respect to the

current status of the uncompleted project. And the

court expressly permitted counsel to question Stouffer-

Heis about whether she had been certified as an SBE

supplier prior to the contract award. But the court

instructed counsel to otherwise restrict his questioning

to matters that had occurred prior to the contract

award to Valley, because Cleveland’s complaint had

been predicated on the rejection of its bid.

{78} We find no abuse of discretion by the trial

court in ruling that testimony related to post-award

program enforcement was irrelevant and inadmissible. -

We overrule Cleveland’s third assignment of error.

Dismissal of City Employees

{779} In its fifth assignment of error, Cleveland

argues that the trial court erred when it granted the

individual defendants’ motion to dismiss. The trial

court dismissed Cleveland’s claims against city

employees Riordan, Franklin, Mullaney, Townsend,

and Ranford in their “personal and individual

capacities,” on the basis of qualified immunity.

Cleveland had also sued the employees in their “official

55a

capacities.” Because the trial court did not explicitly

dismiss the claims against the employees in their

official capacities, we treat the official-capacity claims

as claims against the city.”

{80} The doctrine of qualified immunity generally

shields public officials performing discretionary

functions from liability for civil damages to the extent

that their conduct does not violate clearly established

statutory or constitutional rights of which a reasonable

person would have known.”

{{81} The doctrine recognizes the strong public

interest in protecting public officials from the costs of

defending against claims. A_ public official’s

entitlement to avoid the burdens of litigation “is an

immunity from suit rather than a mere defense to

liability; and like an absolute immunity, it is

effectively lost if a case is erroneously permitted to go

to trial.” To this end, a ruling on the issue of qualified

immunity should be made as early as possible in the

proceedings, before the commencement of discovery.”

°! See Asher Investments, Inc. v. Cincinnati (1997), 122 Ohio App.

3d 126, 137, 701 N.E.2d 400; Norwell v. Cincinnati (1999), 133

Ohio App. 3d 790, 729 N.E.2d 1223.

* Harlow v. Fitzgerald (1982), 457 U.S. 800, 818, 102 S. Ct. 2727,

73 L. Ed. 2d 396.

*° Mitchell v. Forsyth (1985), 472 U.S. 511, 526, 105 S. Ct. 2806, 86

L. Ed. 2d 411.

—

* Id.

;

.

|

a

56a

“[A] quick resolution of a qualified immunity claim is

essential.”™

{{82} “Where a defendant official is entitled to

qualified immunity, the plaintiff must plead facts

which, if true, describe a violation of a clearly

established statutory or constitutional right of which

a reasonable public official, under an objective

standard, would have known. The failure to so plead

precludes a plaintiff from proceeding further, even

from engaging in discovery, since the plaintiff has

failed to allege acts that are outside the scope of the

defendant’s immunity.”

{783} In this case, Cleveland alleged that the city

employees had violated its rights to due process and

equal protection by failing to apply the cap in CMC

321-37 and by rejecting its bid as nonresponsive after

applying provisions of a race-conscious program. These

allegations were insufficient as a matter of law to

describe a violation of a _ clearly established

constitutional right. As demonstrated by the complex

nature of the issues already discussed, the individual

defendants could not have reasonably known that their

actions were unconstitutional. Accordingly, we

overrule Cleveland’s fifth assignment of error.

*° Will v. Hallock (2006), 546 U.S. 345, 126 S. Ct. 952, 960, 163 L.

Ed. 2d 836.

* Sait Lick Bancorp v. FDIC (May 30, 2006), C.A.6 No. 05-5291,

_. F.3d __, 187 Fed. Appx. 428, citing Kennedy v. Cleveland

(C.A.6, 1986), 797 F.2d 297, 299.

57a

Conclusion

In conclusion, we reverse the trial court’s entry of

a directed verdict on Cleveland’s claim for lost profits

under Section 1983. We remand the cause for a new

trial on the issues of liability and damages under

Section 1983. In all other respects, the trial court’s

judgment is affirmed.

Judgment accordingly.

HILDEBRANDT, P.J., and PAINTER, J., concur.

58a

APPENDIX I

COMMON PLEAS COURT

HAMILTON COUNTY, OHIO

CASE NO: A0402638

[Filed October 7, 2005]

Cleveland Construction, Inc.,

Plaintiff,

Vv.

City of Cincinnati, et al.,

Defendants.

ee

ENTRY DENYING PLAINTIFF'S

MOTION FOR A NEW TRIAL

This matter comes before the court on Plaintiffs

motion for a new trial based on Plaintiffs position that

“the Court’s ruling dismissing Cleveland’s damage

remedy [relating to claimed lost profits and uncertain

bid preparation costs] was error....” Plaintiffs motion

for a new trial at 5. Plaintiffs position here clearly is

not precluded by Plaintiff's earlier observation (in the

fee award context) that: “As the Court (and the City)

realize, cases where lost profits have been awarded in

competitive bidding scenarios involving equal

protection challenges are practically nonexistent. Most

59a

cases involving successful equal protection challenges

to programs such as the one at issue here result in

relief of exactly the same nature as that granted here.”

Reply Memorandum in Support of Motion of Plaintiff

for Award of Attorney Fees and Costs (August 22,

2005) at 7. Nonetheless, for reasons already set forth

by the court, including those discussed in the court’s

post-trial entry of July 13, 2005, the court does not

find Plaintiffs argument here well taken. The motion

is denied.

SO ORDERED.

/s/

Judge Nelson, Judge

cc: Kelly Lundrigan, 225 West Court Street,

Cincinnati, OH 45202

Leonard Weakley, Jr., One West Fourth Street,

Suite 900, Cincinnati, OH

David Barth, 537 East Pete Rose Way, Suite

400, Cincinnati, OH 45202

te Oe date Le ee! lai Bee te he et ee ee tie | 9 i ate a

60a

APPENDIX J

COURT OF COMMON PLEAS

HAMILTON COUNTY, OHIO

Case No. A0402638

[Filed August 29, 2005]

Cleveland Construction,

Plaintiff,

Vv.

City of Cincinnati, et al.,

)

)

)

)

)

)

Defendants. )

)

FINAL JUDGMENT ENTRY

This final judgment entry is based on and

incorporates in full the court’s post-trial entry of July

13, 2005.

As set forth in that prior entry, the court finds and

adjudges that:

1) Defendant the City of Cincinnati (“the City”)

violated the requirements of Cincinnati

Municipal Code Section 321-37 (“Bid; Award to

Lowest and Best”) in awarding the Convention

Center drywall contract at issue to Defendant

2)

6la

Valley Interior Systems, Inc. (“Valley”) rather

than to Plaintiff Cleveland Construction, Inc.

(“Cleveland Construction”) when the award was

“based primarily upon” compliance with the

City’s Subcontracting Outreach Program and

Valley’s bid exceeded Cleveland Construction’s

by $1,246,022.00. That additional cost exceeded

the $50,000 cap established by Code Section

321-37, and the City acknowledged that

Cieveland Construction was otherwise qualified

to perform the work. In making its award, the

City abused its discretion in a manner that

harmed the public and denied Cleveland

Construction the contract in violation of

Cleveland Construction’s federally protected.

due process rights and in violation of 42 U.S.C.

Section 1983.

The City’s Small Business Enterprise program

Rules and Guidelines as in effect at the time of

contract award and trial create race and gender

based classifications for which the City claims

no compelling governmental interest and offers

no basis to satisfy any appropriate intermediate

scrutiny review. The program is to that extent

unconstitutional on its face. Further, in the

process of soliciting bids in this matter, the City

did pressure and encourage bidders, including

Plaintiff, to draw upon race and sex-based

classifications that the City concedes could not

withstand the heightened level of review that

the court finds mandated by governing law. The

City in that regard violated Cleveland

Construction’s rights under 42 U.S.C. Section

1983. However, Cleveland Construction failed to

62a

establish that the City’s race and sex based

classifications (as opposed to the City’s small

business preference) resulted in the loss of the

contract at issue.

Further, the court enters a declaratory judgment,

in favor of Cleveland Construction and against the

City, that City Code Section 321-37(c) in its current

form provides, among other things, that where the

City elects to enter into a construction contract on the

basis of the “lowest and best” bid, and where that

selection is based primarily upon the City’s

determination uf the bidders’ relative compliance with

the City’s SBE Subcontracting Outreach Program

rules and regulations, the City may not award the

contract to a bidder whose bid amount exceeds an

otherwise qualified bid by ten percent or fifty thousand

dollars.

The court also enters a declaratory judgment, in

favor of Cleveland Construction and against the City,

that the City’s SBE Rules and Guidelines as of the

date of trial, and as promulgated by the City as official

policy pursuant to City ordinance, contain race and sex

based classifications that violate the equal protection

clause of the United States Constitution.

The court also enters judgment against the City by

permanent injunction prohibiting the City from

maintaining or applying any iteration of the SBE

Rules and Guidelines provisions specified at pages 13-

14 of the court’s July 13, 2005 post-trial entry, or any

substantially comparable provisions making race or

gender based classifications through similar

formulations, absent a formal, public determination by

63a

the City establishing that such provisions are, in the

case of racial classifications, narrowly tailored to

advance a compelling governmental interest, or, in the

case of gender classifications, substantially related to

genuine and important governmental objectives. The

court notes that the City acknowledged during this

litigation that it was not in a position to make such

showings. For the reasons set forth in its July 13, 2005

entry, the court does not enjoin drywall work (well

under progress at this stage) with regard to the

Convention Center project.

The court also enters judgment in favor of

Cleveland Construction, as the prevailing party and

against the City, for its reasonable attorney fees and

costs pursuant to 42 U.S.C. Section 1988, in the

amount of $433,290.00. In arriving at that figure, the

court has declined to award fees for certain

preliminary and post-trial activities and for certain

matters relating to potential expert witness testimony

on matters not directly relevant to the issues

presented to the court. The court has reviewed

Cleveland Construction’s fee application in light of

prevailing standards (see, e.g., Grycza v. Steger [6™

Dist. App. 1994], 97 Ohio App. 3d 82, 84 [“ordinarily a

prevailing plaintiff should recover its attorneys fees”];

Buckhannon Bd. and Care Home, Inc. v. W. Va. Dept

Health and Human Resources {2001], 532 U.S. 598;

Morscott, Inc. v. City of Cleveland [6" Cir. 1991 ], 936

F.2d 271 [absent special circumstances, trial court

“must” award fees to the prevailing plaintiff]), and

with regard for the degree of success obtained through

judicially enforceable remedies that alter the

contemplated future legal relationship of the parties.

The court does not find the City’s memorandum in

64a

opposition to any fee award persuasive (including the

City’s less than full account of its shifting positions on

whether its own Rules and Guidelines even had been

formally promulgated, cf City’s May 11, 2005 brief at

13 arguing that the Rules and Guidelines as attached

to Cleveland Construction’s amended complaint “do

not have the force of law” and are not “official policy” -

a matter of significance to both prongs of Plaintiffs

action).

Court costs as recorded by the Clerk of Courts are

assessed to the Defendants to be shared equally

between them. Although Valley’s legal arguments did

not prevail to the (very considerable) extent that they

mirrored the arguments of the City on those issues as

to which the court awards judgment to Plaintiff

Cleveland Construction against the City, the court

awards no separate relief against Valley and enters

judgment for Valley to that effect for the reasons

stated in the July 13, 2005 post-trial entry.

This is a final order and there is no just cause for

delay. The Clerk of Courts is directed to serve notice of

this final judgment upon the parties in accordance

with the civil rules.

SO ORDERED

/s/

Fred Nelson

Judge

cc: Kelly Lundrigan, 225 West Court Street,

Cincinnati, OH 45202 (fax: 721-4268)

Ie Pye ened his Ls Sgn Areande SEN yt DF Ve AEA TD SE LARS NORD oe ee Give ae ener ie eae, ee ee

65a

4 Leonard Weakley, Jr., One West Fourth Street,

Suite 900, Cincinnati, OH 45202 (fax: 381-9206)

4 David Barth, 537 East Pete Rose Way, Suite 400,

| Cincinnati, OH 45202 (fax: 852-8222)

66a

APPENDIX K

COMMON PLEAS COURT

HAMILTON COUNTY, OHIO

CASE NO: A0402638

[Filed July 13, 2005]

Cleveland Construction, Inc.,

Plaintiff,

We

City of Cincinnati, et al.,

Defendants

ee ee

ENTRY

This matter proceeded to a trial on the merits of

Plaintiffs case combined with an evidentiary hearing

on Plaintiffs Motion for Preliminary Injunction

pursuant to Civil Rule 65(B)(2) and under a schedule

referenced in the court’s May 13, 2005 Entry Denying

Defendants’ Motions for Summary Judgment and

Denying Plaintiffs Motion for Partial Summary

Judgment and [preliminary] Injunctive Relief [SJ

Entry]. That prior entry sets forth in some detail the

legal context of this action, which arises from a dispute

relating to drywall work for the expansion and

renovation of Cincinnati’s Convention Center. A jury

67a

was impaneled to address certain issues in the case,

after the court granted the motion of Defendant, the

City of Cincinnati, for a directed verdict with regard to

Plaintiff, Cleveland Construction, Inc.’s, claim for lost

profits, as referenced below, the parties agreed that

the litigation should proceed as a trial to the court and

the jury was discharged by the consent of all sides (a

matter as to which Plaintiff subsequently took some

issue). The trial now has concluded, and the court has

heard the evidence and counsels’ closing arguments

and also has reviewed the final materials presented in ,

writing.

I. The City violated its Code requirement, that a

determination to award a City contract primarily on

the basis of compliance with the City’s Subcontractor

Outreach Program (designed to favor subcontracting to

small businesses), not cost taxpayers more than

$50,000 .00 beyond the amount submitted in a lower

and otherwise qualified bid.

The evidence is clear and the parties agree that in

the determinative second round of bidding to perform

the drywall work, the bid submitted by Plaintiff

Cleveland Construction, Inc. (“Cleveland,” or

“Plaintiff’) was lower by $1,246,022.00, than the bid

submitted by Defendant, Valley Interior Systems, Inc

(“Valley”) Nonetheless, Defendant City of Cincinnati

(“the City”) awarded the drywall contract to Valley as

the “lowest and best” bidder, because Valley agreed to

subcontract at least 35% of the work to small business

enterprises (“SBEs”) while Cleveland did not.

Defendants have maintained throughout this litigation

that Plaintiff Cleveland was excluded from contract

consideration because it failed to meet the City’s SBE

68a

requirement. The evidence provides no indication of

other infirmities in Cleveland’s bid or capacity to

perform the work, and the City previously had

conceded that Cleveland was otherwise qualified to

perform the work, see SJ Entry at 10. The court finds

that the City’s 35% SBE requirement was the only

reason that the City awarded the contract to Valley

rather than to Cleveland, despite the one and a

quarter million dollar difference between the bids.

The City’s Code section 321-37, “Bid, Award to

Lowest and Best,” provides in part:

“(a) Selection of Lowest and Best in Award of City

Contracts. Except where otherwise provided by

ordinance, the city purchasing agent shall award a

contract to the lowest and best bidder ...

(c) Factors to be Considered Other factors that the

city purchasing agent may consider in determining

the lowest and best bid include, but are not limited

to [prior performance, prevailing wage history,

compliance with nondiscrimination rules, and]

(4) Information concerning compliance with the

‘SBE Subcontracting Outreach Program’ rules and

regulations issued by the city manager pursuant to

section 323-31

In the event that the selection of the lowest and best

bidder is based primarily upon factors 3 or 4 above,

the contract award may be made subject to the

following limitation: the bid may not exceed an

otherwise qualified bid by ten (10%) percent or Fifty

Thousand Dollars ($50,000.00), whichever is lower,”

(emphasis added).

69a

As the court noted in its SJ Entry, the language of

321-37 establishes that “information concerning

compliance” with the Citys SBE Subcontracting

Outreach Program rules and regulations is a “[flactor”

that “may” be considered as the City determines the

lowest and best bid. If the lowest and best bid is indeed

selected “based primarily” on that factor, the City may

proceed to award the contract “subject to the following

limitation: the bid may not exceed an otherwise

qualified bid by ten (10%) percent or Fifty Thousand

Dollars ($50,000.00), whichever is lower,” 321-37(c)(4).

In that context, the phrase “otherwise qualified bid”

can reasonably be read only to mean a bid that is

qualified except that it is not in “compliance” with the

SBE Subcontracting Outreach Program “factor”. The

bid not selected “primarily” because of the SBE

Subcontracting Outreach Program factor must

“otherwise” be qualified in order to trigger the required

calculation with regard to whether the contract award

may be made as selected on that basis. As the court

also observed in its SJ Entry at 15, the City

Administration, through then Assistant City Manager

Rashid Young, advised Cincinnati City Council’s Law

and Public Safety Committee prior to enactment of

this 10%/$50,000.00 cap that, “[w]Jhat this ordinance

allows us to do is be clear about when it is appropriate

to award a bid to a SBE compliant [bidder] if they are

not the lowest. This ordinance would allow us to award

a bid if the bid is $50,000.00 or less difference away

from the lowest bid. We had an example where the

SBE-compliant bidder was some nine hundred

thousand dollars in excess of the lowest bid, and it

doesn’t make a lot of sense to spend nine hundred

thousand dollars more to comply with the regulations

70a

of SBE.” This explanation of a taxpayer protection

rationale for the cap is fully consistent with the Code

language that Cincinnati Council promptly adopted.

The 321-37(c) cap protecting Cincinnati taxpayers

from having to pay more than $50,000.00 extra (extra,

that is, beyond the amount established by a lower and

otherwise qualified bid) for the benefit of SBE

Subcontracting Outreach Program compliance was

adopted in specific contemplation of the Convention

Center project; it took effect only months before the

contract at issue was awarded. See Plaintiffs trial

exhibit 13-A (noting that “this ordinance is an

emergency measure. The reason for the emergency is

the immediate need to proceed with the bidding of the

Convention Center and major development projects,

which may be impacted by Section 321-37 of the

Cincinnati Municipal Code.”)

The court parsed the language of 321-37 at some

length in its SJ Entry (pages 10-23), and incorporates

here that statutory construction. As earlier observed,

the cap applies specifically (and exclusively) to

instances where a higher bid is accepted because of

“information concerning compliance with ‘SBE

Subcontractor Outreach Program rules,’ issued

pursuant to 323-31 [Subcontracting Outreach

Program’]” Code 321-37(c). (The Code’s reference to

program “rules” rather than to the program itself

reflects a rather unusual drafting approach through

which City Council adopted its Subcontracting

Outreach Program simply by reference to a

consultant’s recommendations and _ through

authorization of administratively promulgated rules in

J7la

the absence of any further legislative definition of the

Program Code 323-31.)

Until the eve of trial, the City had maintained that,

despite the clear instruction of Code Section 323-31

requiring that the “City Manager shall issue rules and

regulations to carry out the meaning and purpose of

the Subcontracting Outreach Program,” the City had

not formally promulgated its Small Business

Enterprise Program Rules and Guidelines containing

Subcontracting Outreach Program rules. See, e.z.,

City’s March 11, 2005 Memo Opposing Plaintiffs MSJ

at 13. At trial, however, the City stipulated that the

Small Business Enterprise Program Rules and

Guidelines introduced as Plaintiffs exhibit 17 are

what they purport to be and were, in fact, adopted as

of April 1, 2003. Those Rules and Guidelines set forth

at pages 4-22 the “Components of the [City’s] SBE

Program,” including (at 9-14) the “Subcontracting

Outreach Program”.

As established by the City, the “Subcontracting

Outreach Program applies to City-funded construction

contracts of $100,000.00 or more,” Jd. at 9. Further,

the “Subcontracting Outreach Program requires

bidders to make subcontracting opportunities available

to a broad base of qualified subcontractors and achieve

a minimum of 20% (which may be higher for

construction of buildings) SBE _ subcontractor

participation. To be eligible for award of this project,

the SBE bidder must subcontract a minimum

percentage of its bid to qualified available SBE

subcontractors,” Id. (emphasis added). See also

Plaintiffs trial ex. 5, the “legislative recommendation”

that City Council adopted by reference in establishing

a

72a

the SBE Subcontractor Outreach Program and in

authorizing promulgation of rules and regulations

therefore (“Failure to comply with the City’s

Subcontracting Outreach Program will cause a bid to

be rejected Terms and conditions of this

Subcontracting Outreach Program apply to City-

funded construction projects of $100,000.00 or more”).

Thus, the Subcontracting Outreach Program is a

subset of the City’s broader Smal] Business Enterprise

Program, it applies to all City construction projects

costing $100,000.00 or more, and it incorporates

requirements that a certain “minimum percentage” of

a bid go to qualified SBEs. With regard to covered

projects, the Subcontracting Outreach Program

establishes mechanisms for assuring a more firm

particularized, and project-specific SBE requirement

than the aspirational city-wide annval “goal” of 30%

SBE participation set forth at Section 323-7 of the

Code. See also, e.g., trial testimony of City consultant

Rodney Strong (mandatory aspect of Subcontracting

Outreach Program minimum percentage

requirements).

Having considered all of the evidence adduced, the

court finds by clear and convincing evidence that the

award of the contract at issue here was “based

primarily” upon “information concerning compliance

with the ‘SBE Subcontracting Outreach Program’ rules

and regulations issued pursuant to section 323-31.”

Valley won the contract on re-bid because it exceeded

the 35% SBE participation figure that the City

established for this project under the SBE

Subcontracting Outreach Program, while Cleveland

did not. Plaintiffs trial exhibit 32, for example, is a

City bid document issued to the bidders on this project

73a

and setting forth the applicable “SUBCONTRACTING

OUTREACH PROGRAM SUMMARY.” That program

summary prominently featured the “SBE Goals Per

Trade Contract Cincinnati Convention Center,”

establishing that “All bidders are required to meet the

goal stated for the individual trade contract Drywall

35%.” The Subcontracting Outreach Program, to the

extent of its legislative formulation, was in place at the

time of bid solicitation and the contract award (and

was to be applied to construction contracts of

$100,000.00 or more). See also, e.g., Riordan trial

testimony and Plaintiffs trial ex. 56 (1/21/03 memo

contemplating application to Convention Center

project of legislation containing Subcontracting

Outreach Program authority). In place later, but also

in effect by the time of bid solicitation and award, was

the $50,000.00 taxpayer protection cap on the amount

that the program could cost the City on any one

contract -- and that limitation was part of a package

enacted specifically in contemplation of the Convention

Center project. That the cap was not in place during

initial planning stages of the project does not obviate

its mandate once enacted.

Thus, the court finds that the City did violate a

specific prohibition of its own municipal Code in

awarding the drywall contract to Valley as the “lowest

and best bidder” over Cleveland in order to favor small

business enterprise subcontracting despite the

additional cost to taxpayers of some $1,246,022.00 (an

excess expenditure of $1,196,022.00 beyond what the

321-37 cap permits). Cincinnati’s local rules limit the

discretion of contracting officials in awarding such

contracts where the officials purport to be determining

the “lowest and best” bid. Where the City publicly

T4a

determines that a lowest and best bid is not “in the

best interest of the city,” it may reject such a bid for

that reason, see e.g., Code 321-67, but the law requires

that it do so plainly and openly (and for some

legitimate, non-arbitrary reason, see City of Dayton; ex

rel Scandrick v. McGee {1981], 67 Ohio St 2d 356).

Where no such other rationale exists and the City

purports to award a contract on the basis of the

“lowest and best” bid, it is constrained by the

standards it has established at 321-37, including the

cost cap for awards where the lowest and best

determination is based primarily on Subcontracting

Outreach Program rules.

In determining whether the City abused its

discretion under Ohio law and deprived Plaintiff

Cleveland of a constitutionally protected property

interest without due process of law by awarding the

contract in a manner contrary to governing Code, the

court refers to its discussion of the applicable legal

standards from its SJ Entry: “The meaning of the

term ‘abuse of discretion’ ... connotes more than an

error of law or judgment, it implies an unreasonable,

arbitrary or unconscionable attitude.’ ‘Arbitrary’

means ‘without adequate determining principle, ***

not governed by any fixed rules or standard’.

‘Unreasonable’ means ‘irrational” Cedar Bay

Construction, Inc. v. City of Fremont et al., 50 Ohio St.

3d 19, 22, citations omitted. Moreover, “courts in this

state should be reluctant to substitute their judgment

for that of city officials in determining which party is

7 the ‘lowest and best bidder.’ [IJn the absence of

evidence to the contrary, public officers land]

administrative officers, within the limits of the

jurisdiction conferred by law, will be presumed not to

iil

75a

have acted illegally.” Jd. at 21. Discretion for

determining the lowest and best bid “is not vested in

the courts and the courts cannot interfere in the

exercise of this discretion unless it clearly appears that

the city authorities in whom such discretion has been

vested are abusing the discretion.” Jd. at 21 (citation

omitted). See also, e.g., Greater Cincinnati Plumbing

Contractors’ Association v. City of Blue Ash (1* Dist.

1995), 106 Ohio App. 3d 608, 613-14 (a charter city’s

discretion in accepting lowest and best bid “is similar

to the discretion provided under genera! state law

{citing R.C.735.05], “Competitive bidding provides for

‘open and honest competition in bidding for public

contracts and [saves] the public harmless, as well as

bidders themselves, from any kind of favoritism or

fraud in its varied forms”).

For a property interest in the award of a public

contract to inhere, “one must have more than a

unilateral expectation, rather, one must instead have

a legitimate claim of entitlement to such a contract.”

Cleveland Construction, Inc. v. Ohio Department of

Administrative Services (10" Dist. 1997), 121 Ohio

App. 3d 372, 394. Thus, “a disappointed bidder to a

government contract may establish a legitimate claim

of entitlement protected by due process by showing

that local rules limited the discretion of officials as to

whom the contract should be awarded,” and that

discretion was abused in depriving the bidder of the

award, Id. at 394-95 (no abuse of discretion found), see

also, e.g., Enertech Electrical, Inc. v. Mahoning Co

Commissioners (6™ Cir. 1996), 85 F.3d 257, 260. (“A

constitutionally protected property interest in a

publicly bid contract can be demonstrated [if a bidder

can show] that, under state law, the County had

76a

limited discretion, which it abused, in awarding the

contract’, no abuse of discretion found), Peterson

Enterprises, Inc. v. Ohio Department of Mental

Retardation (6" Cir. 1989), 890 F.2d 416 (“if the board

had limited discretion under local rules as to whom

should be awarded the contract, then Plaintiff might

have a protected property interest in the award if he

were the beneficiary of the state law mandate,” no

property interest where state guidelines were

nonexhaustive), cf. United of Omaha Life Ins. Co. v.

Solomon (6" Cir. 1992), 960 F.2d 31, 34 (“Michigan law

neither requires that the lowest bidder be awarded a

state contract nor creates a property interest in

disappointed bidders on state contracts”), Cementech,

Inc. v. City of Fairlawn (Ohio 9™ Dist. App.), 2005 WL

844948 (disappointed bidder whom jury found had

submitted lowest and best bid may qualify for money

damages when project is already complete), but see,

Miami Valley Contractors, Inc. v. Montgomery Co. (2"4

Dist. App.), 1996 WL 303591 (“as best we can

determine, this jurisdiction has never recognized a

constitutionally protected property interest of a

disappointed bidder on a public works project”), Miami

Valley Contractors, Inc. v. Oak Hill (4" Dist. App.

1996), 108 Ohio App. 3d 745, 752 (no abuse of

discretion found, “we can find no support for the

proposition that a second- or third-place finisher in a

lowest and best bidder determination acquires a

constitutionally protected property right”).

Having heard the evidence at trial, the court finds

that the City did abuse its discretion in a manner that

harmed the public and denied Cleveland the contract

award, and that Cleveland did have a “legitimate

claim of entitlement” sufficiently clear under the Code

T7a

(with its 321-37 cost cap) to establish a due process

violation. The City established a “fixed rule,” in the

language of Cedar Bay, that it then ignored when it

awarded the contract to Valley based primarily on SBE

attainment, despite the City Code’s instruction that

such SBE requirements should not cost the taxpayers

more than $50,000 per contract. Cf. Greater Cincinnati

Plumbing Contractors’ Ass’n. v. City of Blue Ash (1*

Dist. App. 1995), 106 Ohio App. 3d 608, 614

(“Competitive bidding provides ior ‘open and honest

competition in bidding for public contracts and [saves]

the public harmless, as well as bidders themselves,

from any kind of favoritism or fraud in its various

forms’,” quoting Cedar Bay), Scandrick, $7 Ohio St. 2d

at 360. (“While municipal governing bodies are

necessarily vested with wide discretion, such

discretion is neither unlimited not unbridled. The

presence of standards against vhich such discretion

may be tested is essential, otherwise, the term ‘abuse

of discretion’ would be meaningless”), Mechanical

Contractors Ass’n. of Cincinnati v. University of

Cincinnati (10 Dist. App. 2001), 141 Ohio App. 3d

333, 343 (public entitles should not be at liberty “to

violate laws intended to benefit the public” in

contracting), Cementech, 2005 WL 844948.

IT. The City’s Small Business Enterprise Program,

as reviewed in light of its SBE Rules and Guidelines,

contains elements that create race and gender based

classifications for which the City claims no compelling

governmental interest. The program is to that extent

unconstitutional. As applied in this case, however,

those unconstitutional elements did not cause

Cleveland to lose the contract award, rather, Valley

was awarded the contract because of its higher SBE

78a

subcontracting percentage as calculated without regard

to race or gender.

Plaintiff asserts and the City concedes that

Plaintiff intends and is positioned to bid on future City

contracts and that it has standing to mount an equal

protection clause challenge to the City’s SBE program

as that program currently is constituted.

Very significantly to this assessment, the City has

stipulated that it lacks the necessary factual basis to

withstand any “strict scrutiny” review of its SBE

program. If any part of the SBE program must comply

with strict scrutiny standards in order to survive

constitutional challenge, the City agrees that such

elements must be invalidated as unconstitutional at

this time. That is, the City concedes that it is not ina

position to prove any “compelling governmental

interests” that could sustain a racial classification

program no matter how “narrowly tailored.” The City

also has failed to present or argue any significant

evidence showing that its program could satisfy any

“intermediate scrutiny” review.

Justice O’Connor has set forth the determination by

the United States Supreme Court that ...“the

Fourteenth Amendment requires strict scrutiny of all

race-based action by state and local governments,”

Adarand Constructors, Inc. v. Pena (1995), 515 U.S.

200, 222, citing Richmond v J.A. Croson Co. (1989),

488 U.S. 469. “A free people whose restitutions are

founded upon the doctrine of equality’ should tolerate

no retreat from the principle that government may

treat people differently because of their race only for

the most compelling reasons. Accordingly, all racial

;

;

tf

79a

classifications, imposed by whatever federal, state, or

local government actor, must be analyzed by a

reviewing court under strict scrutiny. In other words,

such classifications are constitutional only if they are

narrowly tailored measures that further compelling

governmental interests,” Jd. at 227, see also, e.g.,

Grutter v. Bollinger (2003), 539 U.S. 306, 326 (strict

scrutiny required for all governmentally imposed

racial classifications), Monterey Mech Co. v. Wilson,

125 F.3d 702, 713 (9 Cir. 1997)(“burden of justifying

different treatment by ethnicity or sex is always on the

government”). Given the City’s stipulations on

standing and strict scrutiny, the court is required to

examine whether the City’s SBE program imposes

classifications subject to such heightened review.

Plaintiff points to nothing in the Constitution or

laws of the United States or of the State of Ohio that

creates a heightened standard of judicial review for a

governmental program that simply favors small

business enterprises at the expense of larger

competitors. The issue here is not classification by size,

but rather by race or gender.

Further, the law does not prohibit governmental

entities from recording statistics relating to race or

gender, or from tracking the progress of groups as

identified by such categories, or from seeking to

ascertain whether any impermissible, discriminatory

barriers are hampering the advancement of

individuals within groups as defined by race or gender.

Thus, for example, the fact that the City reviews

statistics relating to contract awards to Minority

Business Enterprises (“MBEs,” as defined at 323-1-M)

or Women’s Business Enterprises (“WBEs,” as defined

80a

at 323-l-W) pursuant to 323-17 (“City Maintained

Records and Reports”) itself does not establish a

requirement of heightened scrutiny. See, e.g., Croson,

488 U.S. at 492 (plurality op. of O’Connor, J.) (“a state

or local subdivision has the authority to eradicate the

effects of private discrimination within its own

legislative jurisdiction ... and can use its spending

powers to remedy private discrimination, if it

identifies that discrimination with the particularity

required by the Fourteenth Amendment”). Even the

identification of specified “MBE/WBE annual

participation goals,” to be used in conjunction with

“monitor[ing], track[ing], and report[ing]” purposes

alone, as set forth in 323-7(a), without further

mechanism to promote or effectuate or encourage

others to meet such goals in any particular context,

may not threaten cognizable injury to this Plaintiff. Cf.

Safeco Ins. Co. v. City of White House, Tenn. (6" Cir.

1999), 191 F.3d 675, 690, 692 (cited in filings made by

both parties and in City’s proposed jury instructions)

(“Outreach efforts may or may not require strict

scrutiny,” citing authority for proposition that such

scrutiny generally does not apply to outreach efforts

targeting particular race).

However, “where ‘outreach’ requirements operate

as a sub rosa racial preference - that is, where their

administration ‘indisputably pressures’ contractors to

hire minority subcontractors — courts must apply

strict scrutiny” Safeco, 191 F.3d at 692. The City’s

Small Business Enterprise Program Rules and

Guidelines, disavowed by the City as unofficial until

the eve of trial and then acknowledged as formally

promulgated as of April 1, 2003, see Plaintiffs trial

exhibit 17, contain a number of such elements when

8la

reviewed as a complete program. The City’s Rules and

Guidelines state, for example, that:

1)

2)

3)

“all bidders are required to use good faith efforts

to promote opportunities for Women and

Business Enterprises to participate in to the

extent of their [governmentally specified]

availability, contracting. Prior to the award of

any contract related to construction services or

professional services, the City shall evaluate

each bidder’s documented efforts to achieve the

participation of minority and women business

enterprise firms.” Rules and Guidelines,

Plaintiffs trial exhibit 17, at 5 (emphasis

added), cf. Virdi v. Dekalb Co School Dist (11

Cir. 2005), 2005 WL 1389942 (nonbinding

“goals” for “minority vendor involvement” linked

to specific notice and advertising outreach

programs are racial classifications subject to

strict scrutiny).

“Upon its successful completion, the Non-

Discrimination Program [component of the SBE

program] will result in utilization of minority

and women owned firms to the extent of their

[governmentally specified] availability.” Rules

and Guidelines at 6 (emphasis added).

“The City will evaluate efforts made by bidders

to promote opportunities for minority and

women owned firms to compete for business as

subcontractors and/or material or equipment

suppliers at the time of bidding. If the

evaluation determines that a bidder has failed

to achieve levels of minority and women

4)

5)

6)

82a

business enterprise participation as might be

reasonable on the basis of objective data

regarding availability and capacity of such

business, the bidder shall be subject to an

inquiry by the Office of Contract Compliance.”

Id. at 6 (emphasis added), cf. MD/DC/DE

Broadcasters Assn. v. Fed. Communications

Com. (D.C. Cir. 2001), 236 F.3d 13 (potential

investigation of recruitment efforts based on

applicant pool numbers is a “powerful threat”

giving rise to strict scrutiny review).

“Bidders [operating under the Subcontracting

Outreach Program] should be able to include

the participation of minority and female firms

at the levels of availability determined in the

City of Cincinnati Disparity Study. “Rules and

Guidelines at 9 (referencing a study that the

City concedes does not reflect a compelling

governmental interest in pursuing a program of

racial classification).

“(Using form 2007,] [ojfferor will provide a

detailed description of the techniques used to

obtain participation of minority and women

owned business enterprise ... “ Jd. at 43.

“Utilizing the bidder’s utilization form (Form

2003) and total bid amount, the actual

utilization percentage is caiculated. This is

accomplished by taking the amount of the

subcontracts awarded to minority and women-

owned businesses and dividing by the total bid

amount If this amount is equal to the estimated

availability, then no further inquiry is needed.

a

-

7)

8)

83a

If the actual utilization is less than the

estimate, then further inquiry is warranted.

The contract administrator must look at the

bidder’s solicitation form and contact the

minority and women-owned businesses listed on

the form to verify that they were contacted by

the bidder and what their response was. The

administrator must also review the good faith

efforts taken by the bidder. The burden is on the

bidder to explain the low utilization percentage.

If the contract administrator determines that

the contractor under-utilized minority and/or

women-owned businesses based on the actual

[government specified] availability percentage,

and that the bidder’s good faith efforts were

inadequate and there is no _ legitimate

explanation for the under-utilization, then the

matter is turned over to the investigative unit

for a discrimination investigation.” Jd. at 46; ¢f.

MD/DC/DE Broadcasters, supra.

[From tl.» “Pre-bid/Outreach Session Script for

Contract Administrator”] “Bidders are required

to show that they’ve made a good faith effort to

get the maximum practical participation of

minority and women-owned businesses on this

project. [I|f it is feasible that the work can be

broken into two or more smaller units, then it

should be done so as to permit maximum

participation, based on the _ availability

estimate.” Rules and Guidelines at 49

(emphasis added).

Every bidder is to submit a “Statement of Good

Faith Efforts” certifying that, “we have utilized

84a

the following methods to obtain the maximum

practicable participation by small, minority and

women-owned business enterprises on this

project.” Id. at Form 2007 (emphasis added).

As constituted, therefore, to include the officially

promulgated Rules and Guidelines authorized and

required by Code 323-5, the City’s Small Business

Enterprise Program contains a variety of elements

through which the City makes classifications by race

and sex and “indisputably pressures” contractors to

recruit and use subcontractors on those terms. This

case is different from many other cases involving

government race and sex classifications in that the

City advances no evidence to suggest that these

elements of its program could withstand the

heightened scrutiny applied under U.S. Supreme

Court precedents. The constitutional inquiry is

foreshortened because the City concedes that it cannot

satisfy any strict scrutiny review of its program. Thus,

the program is unconstitutional on its face to the

extent that the City engages in classification by race or

sex with regard to City contracting in construction

projects. To that extent, as identified above, Plaintiff

prevails on its facial challenge under 42 U.S.C. Section

1983.

With regard to the application of those

unconstitution. 1 program elements to the facts of this

case, the court 10tes that there is no evidence that any

bidder on the contract at issue was privy to the Rules

and Guidelines document itself. The court further

notes, however, that both Cleveland and Valley did, in

fact, (and without protest by Cleveland until after the

contract was awarded to Valley) submit form 2007

85a

(“Statement of Good Faith Efforts”) certifying their

efforts “to obtain the maximum practicable

participation by small, minority and women-owned

business enterprises on this project.” See, e.g.,

Plaintiffs trial ex. 28. Those certifications were made

after all bidders were provided the “Subcontracting

Outreach Program Summary” sheet for the project

that included this directive from the City. “You will

also find on the cover of this bid document an

Availability Determination [of “13.09% Minority

/1.05% Female” for the drywall work, see Availability

Estimation Sheet at Plaintiffs trial ex. 28]. These

figures are percentages based on a review of the City’s

vendor list and certified minority and women-owned

businesses.

Bidders should be able to include minority and

female firms at the level of availability indicated.”

Plaintiffs trial exhibit 32 (emphasis added). The City

also informed bidders through Addendum 3 to the bid

documents that “If the availability estimates are not

met, it does not mean that the bid will be deemed non-

responsive However, we expect the utilization of

SBEs to be reflective of the availability estimates.” See

Plaintiffs trial exhibit 70.

Thus, in the process of soliciting bids, the City did

in those respects pressure and encourage bidders to

draw upon race and sex-based classifications that the

City concedes could not withstand any appropriate

heightened review on the facts to which the City is

privy. The trial elicited no testimony, however, that

the City in fact gave weight to bidders’ compliance

with MBE or WBE availability estimates in making

the contract award with regard to subcontracting

86a

percentages, Plaintiff failed to establish that City

officials looked beyond whether drywall bidders met

the City’s 35% SBE requirement. Indeed, Plaintiffs

own chief estimator on the project did testify that in

seeking to gain the contract award, his focus in this

area was on boosting his company’s small business

enterprise inclusion rate, and not on attaining any

particular MBE or WBE percentages. Valley did not

meet the specified WBE percentage, and no evidence

was presented at trial that the City rejected any

Convention Center bid on the basis of MBE or WBE

availability estimates. The evidence indicates that the

City awarded the contract to Valley, and not to

Cleveland, because Valley’s bid complied with the

City’s requirement that 35 percent of the work go to

small business enterprises and Cleveland’s bid did not.

With regard to the unlawful discrimination

component of the case, therefore, Plaintiff here is

much in the posture of the plaintiff in the case that it

cites of Virdi v. Dekalb County School District (11™

Cir. 2005), 2005 WL 1389942. There, the federal court

of appeals determined that a school district’s

aspirational “goals” for minority involvement in

contracting, coupled with specific mechanisms for

public outreach, created racial classifications that were

not narrowly tailored to meet strict scrutiny review,

“the program is facially unconstitutional.” The court

held that, “[nJevertheless, the District is still entitled

to judgment on Virdi’s intentional discrimination claim

While the [program’s] goals themselves are

unconstitutional, they do not constitute evidence that

Virdi himself was discriminated against. Virdi has

failed to establish a causal connection between the

unconstitutional aspect of the [program] and his

87a

alleged injury. Moreover, there is insufficient other

evidence to impose liability upon the District for

damages to Virdi for intentional discrimination.”

Similarly here, Cleveland has not established that the

City’s race and sex based classifications (as opposed to

the City’s small business preference) resulted in the

loss of the contract award. Cf. Florida General

Contractors v. Jacksonville (1993), 508 U.S. 656

(traceability requirement).

Nor has Plaintiff met its burden of proof to

establish that the City’s stated policy to favor small

businesses (to the extent that the practice does not

cost taxpayers more than $50,000.00 per major

construction contract) is in reality a sham to mask

invidious discrimination. The court notes as an aside

that the City’s policy of encouraging small business

participation well predates the Subcontracting

Outreach Program components of which Plaintiff

complains. Further, the court observes. that

Cincinnati’s City Council, at the urging of the

Administration, has indeed opted to limit application

of Subcontracting Outreach Program small] business

preferences to circumstances in which such

preferences would not add more than $50,000.00 to the

cost of a contract. While that newly enacted taxpayer

protection cap was not observed in this instance, the

evidence does not establish that the provision was

ignored as part of a scheme to further race or sex

based distinctions, and the fact that the cap was

adopted by Code certainly does 1ot further the

intentional discrimination theory. Moreover, for

example, the City’s rejection of all the initial drywall

bids, including Valley’s, does not bolster the theory

that the City’s stated preference for SBEs was used

88a

here as a “sham” to mask improper considerations of

race or sex. Further still, evidence was adduced that

the City did award other contracts on the Convention

Center project to bidders who did not include any MBE

or WBE participation.

In short, Plaintiff has demonstrated that the City’s

SBE program contains certain race and sex based

classifications that cannot pass constitutional muster

as constituted at this time; Plaintiff has not

established, however, that those aspects of the

program caused Plaintiff to lose award of the drywall

contract at issue in this case. Cf. Texas v. Lesage, 528

U.S.18 (1999) (“where a plaintiff challenges a discrete

governmental decision as being based on an

impermissible criterion and it is undisputed that the

government would have made the same decision

regardless, there is no cognizable injury warranting

relief under [Section] 1983” on an ‘as applied’

challenge).

Ill. Having prevailed on its abuse of discretion / due

process Section 1983 claims and on its claim that

specific portions of the City’s SBE Rules and

Guidelines are unconstitutional on their face,

Cleveland is entitled to certain declaratory and

injunctive relief. Cleveland also is entitled to its

reasonable attorney’s fees under 42 U.S.C. Section

1988. Cleveland did not establish, however, that the

court should use its equitable powers to enjoin ongoing

work with regard to the Convention Center project

itself.

The injunctive and declaratory relief sought by

Cleveland involve both the administration of future

89a

City construction contracts and the disposition of the

current Convention Center drywall project.

Plaintiff is entitled to a declaration that City Code

Section 321-37(c) in its current form provides, among

other things, that where the City elects to enter into a

construction contract on the basis of the “lowest and

best” bid, and where that selection is based primarily

upon the City’s determination of bidders’ relative

compliance with the City’s SBE Subcontracting

Outreach Program rules and regulations, the City may

not award the contract to a bidder whose bid amount

exceeds an otherwise qualified bid by ten percent or

Fifty Thousand Dollars. The City Administration

professed to know the meaning of that Code subsection

at the time it was considered by Council; the court

trusts that now that further attention has been drawn

to the existence of the subsection (and to the high cost

to taxpayers of ignoring it), and now that the City has

acknowledged the status of its Subcontracting

Outreach Program rules and regulations, no injunctive

mandate with regard to future contracts is necessary

with regard to that provision of law. Plaintiff

Cleveland further is entitled to a declaration that the

conduct of the City in ignoring the cost cap deprived

Cleveland of a property interest without due process of

law.

Plaintiff also is entitled to a declaration that the

City’s SBE Rules and Guidelines in their current form

contain certain race and sex based classifications as

enumerated above that, in light of the City’s admission

that it cannot now offer a compelling governmental

interest to satisfy “strict scrutiny” review as required

by governing United States Supreme Court precedent,

90a

violate the equal protection clause of the U.S.

Constitution. The court will enjoin the City from

applying those specified Rules and Guidelines

provisions to any City construction project absent a

formal determination and public showing by the City

that such provisions are narrowly tailored to advance

a compelling governmental interest of the sort that the

City concedes it cannot now establish. Now that the

City has acknowledged the status of its Rules and

Guidelines, and now that these particular

classifications have been identified, and the City has

conceded that it is unable to meet any strict scrutiny

review, the City is expected to take prompt steps to

remove all unconstitutional provisions from its Rules

and Guidelines. In this regard, the court is heartened

by the City’s stated commitment in the Rules and

Guidelines (at page 8) to ensure that, “Businesses

awarded City contracts shall prohibit discrimination

against any person or business on the basis of race,

color, sex, religion, disability or national origin. Such

businesses shall develop a policy statement to be

communicated regularly to all persons and entities

involved in the performance of their contracts, and

shall conduct their contracting and purchasing

programs so as to discourage any discrimination and

to resolve all allegations of discrimination.”

In considering Cleveland’s request for injunctive

relief with regard to the Convention Center drywall

contract at issue, the court is mindful that, “A party

seeking a permanent injunction must show [that it has

‘a right to relief under the applicable substantive law,’]

that the injunction is necessary to prevent irreparable

harm and that the party does not have an adequate

remedy at law. [Such] party must ordinarily prove the

9la

required elements by clear and convincing evidence”

Procter & Gamble Co. v. Stoneham (1* Dist. App.

2000), 140 Ohio App. 3d 260, 267. The merits of

Cleveland’s claims, including its showing that the City

abused its discretion in disregarding the $50,000.00

cost cap under Code Section 321-37, have been

discussed above.

Regarding the question of an adequate remedy at

law, the court observes that the Defendants’ consistent

position up to and into trial was that Plaintiff is

limited in this action solely to its requests for

injunctive and declaratory relief, and that money

damages are not an appropriate remedy for Plaintiffs

claims. See, e.g., Citys May 27, 2005 pretrial

statement at 2 (“The City also challenges Cleveland’s

ability to recover its alleged ‘lost profits”), City’s

Motion in Limine to Preclude Plaintiff from Presenting

Evidence of Lost Profits; City’s June 13, 2005 Reply to

Response to the Motion in Limine Regarding Lost

Profits (“Because Cleveland’s only claim is for

injunctive relief, Cleveland also is not entitled to a jury

trial. Cleveland’s constitutional rights, and any claim

for redress, can be handled through an action in equity

by filing and seeking injunctive relief. Not only does an

action for injunctive relief protect Cleveland, but it

also protects the taxpayers from having to pay twice

for a public project”), Citys June 20, 2005

Memorandum Citing Additional Authority on the

Recovery of Lost Profits (“in Ohio lost profits are not

available and only injunctive relief available to the

plaintiff’).

The court agreed with the City that lost profits are

not a remedy available under Ohio law to a

92a

disappointed bidder on a public contract See, e.g.,

O’Rourke Construction Co. v. Cincinnati Metropolitan

Housing Authority (1" Dist. App. 1982), 1982 WL 8613 ©

at n.5 (“We can find no award of damages from public

funds even though the contract was given to another

bidder as the result of abuse of discretion.”); Hardrives

Paving & Constr., Inc. v. Niles (1994), 99 Ohio App. 3d

243, 247-48 (“The fact that injunctive relief is available

generally indicates that a monetary award is not

available for lost profits. [I)}f we were to allow

appellant to receive monetary damages, only the

bidders would be protected because the public would

have to pay the contract price of the successful bidder

plus the lost profits of an aggrieved bidder. However,

if injunction is the sole remedy, both the public and the

bidders themselves are protected.”), Cavanaugh Bldg.

Corp. v. Cuyahoga Cty. Bd. Of Commrs. (8 Dist. App.

2000), 2000 WL 86554. The court disagreed with the

City’s proposition, however, that it “must apply state

law for purposes of defining the scope of damages

under [federal Section] 1983,” cf. City’s June 16, 2005

Motion to Clarify at 2, and concluded that violations of

federal law under Section 1983 can give rise to money

damages including lost profits where injunctive relief

alone would not make a plaintiff whole. See, e.g., Carey

v. Piphus (1978), 435 U.S. 247, 257-58 (“damages

awards under Section 1983 should be governed by the

principle of compensation” as developed by the

common law of torts, where common law does not

provide full compensation, “the task will be the more

difficult one of adapting common-law rules of damages

to provide fair compensation for injuries caused by the

deprivation of a constitutional right.”).

93a

The City’s newly adopted assertion at closing that

project-specific injunctive relief is precluded because

Plaintiff had a complete damages remedy available at

law thus rings a bit hollow The court granted a

directed verdict for the City on the lost profits issue

because Plaintiff - which consistently had sought a

combination of money damages and injunctive relief,

including project-specific injunctive relief, see, e.g.,

Amended Complaint and Plaintiffs May 27, 2005

pretrial statement at 2 (seeking remedies including

damages, declaratory relief, and “injunctive relief

against the City and Valley with regard to the

application of the SBE Program to the award of the

drywall contract at issue”) - failed in its case in chief to

provide any evidence whatsoever with regard to the

drywall project status or the potential availability of

injunctive relief on any balance of the contract, at the

close of Plaintiffs case, therefore, there was no factual

basis on which assess available damage remedies or on

which to instruct the jury to calculate any lost profits

for drywall work already completed. See, e.g., Ohio

cases supra establishing precedence of injunctive relief —

as opposed to money damages in public bid contracts,

see also, e.g., Milwaukee Co. Pavers Assn. v. Fiedler

(W.D. Wisc. 1989), 707 F. Supp. 1016, 1032 (lawsuit

challenging “disadvantaged business” preference in

construction contracts. “Plaintiffs would be entitled to

money damages [for the alleged federal constitutional

violations] only if their motion for a preliminary

injunction were denied, they were to succeed

ultimately on the merits of their claim, and the state

construction projects were to have proceeded so far that

they could not reasonably be re-let under non-

discriminatory bidding conditions,” {emphasis added]).

The court did not rule and does not find that Plaintiff

94a

had available a fully adequate remedy at law. It is true

that no evidence as to the current status of the drywall

work (and as to whether there remains any significant

portion of that drywall project left for potential

injunction) was presented until the City and Valley

put forward proof on that subject as part of their

defense cases; such evidence now is before the court,

however, for any appropriate consideration.

In light of the equitable nature of the remedy

sought, and especially given the public nature of the

project at issue, the court also should consider whether

the public interest would be served or harmed by an

injunction and whether third parties would be unduly

injured by such a remedy. “(CJaution should be

exercised in granting injunctions, and especially so in

cases affecting a public interest where the court is

asked to interfere with or suspend the operation of

important public works or to control the action of

another department of government.” White v. Long (1*

Dist. App. 1967), 12 Ohio App. 2d 136, 140, see also,

e.g., Leaseway Centers v. Dept. of Adm. Serv. (10 Dist.

App. 1988), 49 Ohio App. 3d 99, 106 (quoting White),

Cleveland Construction, Inc. v. Ohio Dep’t. of Adm. *

Serv. (10 Dist. App. 1997), 121 Ohio App. 3d 372, 383

(same).

Certainly there is a powerful public interest in

requiring governmental entities to follow the law.

Courts across this state have found that interest

especially strong in the context of “protecting the

integrity of the [public] bidding process.” Cf.

Cementech, 2005 WL 844948 (9“ Dist. App.) (noting

that where available, “the preferred method of

resolving bidding disputes is injunctive relief, as that

95a

relief would prevent double payment [for the same

project] and better serve the integrity of the bidding

process”), Hardrives Paving, 99 Ohio App. 3d at 247-48

(“if injunction is the sole remedy, both the public and

the bidder themselves are protected”), Cedar Bay, 50

Ohio St. 3d at 21 (“The intent of competitive bidding,

under either the state statutes or a municipal charter,

is ‘to provide for open and honest competition in

bidding for public contracts and to save the public

harmless, as well as bidders themselves, from any kind

of favoritism or fraud in its varied forms.”).

Against such considerations the court weighs the

potential harm to the public that could be caused by

disruption of the ongoing Convention Center work.

Defense witnesses testified that the Convention Center

project as a whole is approximately sixty percent

complete. The drywall work will be roughly 50 percent

done by the end of July and is on a “critical path” in

which delays could significantly affect other parts of

the project. Defendants argue, in effect, that the

savings that the City might obtain if it were ordered to

shift the remaining drywall work from Valley to

Cleveland at Cleveland’s bid price are likely to be

surpassed by additional costs arising fri delay claims

and lost Convention Center business. See, e.g.,

McKillup testimony that potential delay claims could

reach into the millions of dollars). Although

Defendants couple this argument with the contention

that Cleveland delayed unduly in seeking to press its

preliminary injunction claim, thereby allowing the

project to reach a more delicate juncture, the court is

constrained to note that the City seems to have

contributed to any perceived need for extensive and

lengthy discovery by taking positions such as its

96a

longstanding denial, only now abandoned, that it had

not officially promulgated SBE Rules and Guidelines

at all.

Valley is prepared to perform the balance of the

drywall work and, with its subcontractors, would lose

any expected remaining profits if the project is

enjoined. Valley also presented testimony that a

premature end to its contract would mean a loss of

work for certain employees in light of the additional

worker contingent recently added to the endeavor.

Against that very real concern, the court notes that

Valley would not have won the contract or been paid

for any of the work had the contract been awarded in

keeping with the $50,000.00 cost cap, and that Valley

and its subcontractors appear to have been well

compensated for the work they have performed

relative to the significantly lower (and “otherwise

qualified”) bid submitted by Cleveland.

The court finds that equity would not be served by

Cleveland’s proposal that Valley be made to disgorge

money it already has earned for work already done.

Testimony at trial indicates that Valley followed the

rules set forth by the City in bidding on the contract,

and that it has borne substantial contractual risks

associated with its undertaking. The court does not

deem Valley’s contract with the City void ab initio, and

it would be inequitable to strip Valley of the

compensation it has been given for the work it has

undertaken pursuant to contract.

Further, Cleveland provided no _ testimony

whatsoever during its case in chief either with regard

to the current status of the Convention Center project

~~. Fs

|

97a

or with regard to Cleveland’s own current ability to

complete the work without delay and disruption to a

major City undertaking. On rebuttal, Cleveland

offered no testimony to dispute Defendants’ position

that the Convention Center drywall work is on a

“critical path” that is extremely time-sensitive and as

to which disruptions would impede other contractors

and interfere with planned Convention Center events

and broader City interests surrounding the City’s

economic development program. Cleveland did not

offer credible assurances by a witness conversant with

the scope of work and the project’s current status that

Cleveland could take over the job at this stage without

undue and costly disruption. The court continues to

believe that a Plaintiff in an action of this nature is not

entitled to manufacture heightened claims to lost

profits by eschewing serious efforts toward injunctive

relief at any stage in the process.

Considering the testimony that was _ given,

including the rebuttal testimony, the court finds that

an injunction interfering with the ongoing Convention

Center construction work has not been shown to be

appropriate upon examination of all appropriate

equitable considerations. The court reaches this

conclusion reluctantly in light of the course that this

litigation took, but it finds that the public interest is a

weighty factor in this case involving a major public

undertaking, see, e.g., White, 12 Ohio App. 2d 136, and

that the public interest at this juncture is best served

by the combination of declaratory and non-project

specific relief outlined above. The court further finds

that Cleveland is the prevailing party on its Section

1983 due process claim and on its reasonable

98a

attorney’s fee under 42 U.S.C. Section 1988. Costs will

be assessed against Defendants jointly.

The court will ask the parties to confer, if they

wish, on a judgment entry to propose to the court in

very short order reflecting these determinations. The

court also asks the parties to confer on a date for a

hearing on the amount of Cleveland’s attorney’s fee.

/s/_

Judge Nelson

‘

a

|

;

,

99a

APPENDIX L

COMMON PLEAS COURT

HAMILTON COUNTY, OHIO

CASE NO: A0402638

[Filed June 28, 2005]

Cleveland Construction, Inc.,

Plaintiff,

Vv.

City of Cincinnati, et al.,

Defendants.

ee ee ee ee a ee

ENTRY GRANTING DEFENDANT CITY OF

CINCINNAT?S MOTION FOR PARTIAL

DIRECTED VERDICT, DENYING DISMISSAL

OF EQUAL PROTECTION CLAIM,

WITHHOLDING JUDGMENT ON DEFENDANT

VALLEY’S 41(B)(2) MOTION, AND NOTING

STIPULATION THAT REMAINING ISSUES

ARE TO BE DETERMINED BY THE COURT

WITHOUT A JURY

For the reasons expressed on the record of today’s

date, the Court grants Defendant City’s Motion For A

Directed Verdict solely on the issues of lost profit and

bid preparation cost.

:

:

|

:

is a he Es a ee ei en

100a

The Court denies Defendant City’s Motion for

dismissal of Plaintiffs equal protection claim relating

to the administration of the contract at issue in this

case.

The Court defers a ruling on Defendant Valley’s

motion to dismiss under Rule 41(B)(2) and will

withhold judgment on such issues until the close of all

evidence.

All parties having stated that the remaining issues

in this action are appropriate for determination by the

Court alone without jury verdict, the jury is discharged

with the consent of all parties with regard to all issues

remaining in this action. The case will proceed as a

trial to the bench with regard to Plaintiffs claims for

declaratory and injunctive relief and attorney fees.

SO ORDERED.

/s/

Fred Nelson, Judge

101la

APPENDIX M

COMMON PLEAS COURT

HAMILTON COUNTY, OHIO

CASE NO: A0402638

[Filed June 20, 2005]

Cleveland Construction, Inc.,

Plaintiff,

Vv.

City of Cincinnati, et al.,

Defendants.

Nee ee eee

ENTRY

Pursuant to Civil Rule 65(B)(2) and previously

determined with the parties as reflected on the

Amended Case Scheduling Order of October 8, 2004,

the hearing on Plaintiffs request for preliminary

injunctive relief is combined with the trial on the

merits of the case as scheduled to begin on June 20,

2005.

SO ORDERED.

/s/

Judge Nelson

102a

APPENDIX N

COURT OF COMMON PLEAS

HAMILTON COUNTY, OHIO

Case No. A0402638

[Filed May 18, 2005]

Cleveland Construction,

Plaintiff,

vs.

City of Cincinnati, et al.,

)

)

)

)

)

)

Defendants. )

)

ENTRY DENYING DEFENDANTS’ MOTIONS

FOR SUMMARY JUDGMENT AND DENYING

PLAINTIFF’S MOTION FOR PARTIAL

SUMMARY JUDGMENT AND

INJUNCTIVE RELIEF

Introduction

This matter comes before the court on the motion of

Plaintiff Cleveland Construction, Inc. (“Cleveland”) for

partial summary judgment and for injunctive relief,

and countervailing motions for summary judgment by

Defendants the City of Cincinnati (“the City”) and

Valley Interior Systems, Inc. (“Valley,” which has

103a

associated itself with the City’s legal position for

purposes of its motion). The court in keeping with the

requests of the parties conducted a nonevidentiary

hearing on the motions, and has reviewed the

arguments of counsel, the pleadings and briefs, and

the evidence filed of record.

The case involves a dispute related to drywall work

needed for the expansion and renovation of

Cincinnati’s Convention Center. The parties agree that

in a second round of bidding to perform the drywall

work, Cleveland offered to do the job for $8,889,000

and Valley submitted a bid of $10,135,022. Although

Cleveland’s bid was lower than Valley’s by roughly one

and a quarter million dollars, the City awarded the

drywall contract to Valley as the lowest bidder that

met the Citys Small Business Enterprise program

(“SBE”) criteria. The City states that Valley got the

contract because it was prepared to make greater use

of small business subcontractors than could Cleveland.

Cleveland subsequently filed this lawsuit, alleging

among other matters that the City’s SBE program “is

a sham to allow the City to use racial and gender-

based quotas illegally,” and asserting that in awarding

the contract to Valley, the City violated Cleveland’s

equal protection rights and ignored its own municipal

code in violation of due process. After a hearing at

which this court denied Cleveland’s motion for a

temporary restraining order, Defendants removed the

case to federal court; in due course, the action was

remanded here, the court dismissed certain individual

defendants, and the parties engaged in extended

discovery. Cleveland elected not to pursue application

for a preliminary injunction until the filing of the

104a

instant motions, which include the summary judgment

issues to which the court now turns.

Summary Judgment Standard

Summary judgment is appropriate when it is clear

from the facts established in the pleadings and

evidential materials of record, as viewed in the light

most favorable to the party or parties opposing the

motion, that: “(1 ) no genuine issue of fact remains to

be litigated; (2) the moving party is entitled to

judgment as a matter of law; and (3) the evidence

demonstrates that reasonable minds can come to but

one conclusion, and that conclusion is adverse to the

party opposing the motion.” See, e.g., Sauter v. One

Lytle Place (1* Dist. App. 2005), 2005-Ohio-1183, citing

Civil Rule 56(C). Ifa party seeking summary judgment

meets its initial burden of identifying a basis for the

motion together with those parts of the record that

“demonstrate the absence of a genuine issue of

material fact on the essential element(s) of the ...

nonmoving party’s claims ...., the nonmoving party

then has a reciprocal burden ... to set forth specific

facts showing that there is a genuine issue for trial ....”

Dresher v. Burt (1996), 75 Ohio St.3d 280, 293.

Equal Protection Issues

At this stage -in the litigation, Cleveland argues

that the City’s SBE program as designed (to include

certain “Rules and Guidelines”) and as applied here

amounts to a race-conscious awards scheme that the

City cannot justify under prevailing constitutional

norms. (Plaintiff at this point does not argue that the

City has required improper considerations of gender,

105a

perhaps because Valley’s successful bid did not reflect

subcontracting percentages for women-owned firms

that approached the City’s availability estimates.) The

City is frank to respond that it lacks a factual

predicate that could satisfy “strict scrutiny” review of

a race-conscious program, but argues that its SBE

approach as designed and as undertaken here is race-

neutral, rationally based, and _ constitutionally

unexceptionable. The record as presented to date

reflects genuine issues of material fact that preclude

summary judgment for any side on this part of the

dispute.

The City’s municipal code provides’ that

“Cincinnati's Annual Goal for SBE participation shall

be 30% of the city’s total dollars spent for construction

... Services ....” Cincinnati Municipal Code (“Code”) at

323-7(a). The Code defines a Small Business

Enterprise with regard to gross revenues and number

of employees; the SBE definition itself does not include

factors of race or gender. Code 323-1 -S. The record

here may suggest that the City pursues the 30% SBE

goal on a project by project basis, establishing different

percentages for different project components in order

to arrive at the overall 30% figure. The parties agree

that with regard to the drywall element of the

Convention Center project, the goal was that 35% of

subcontracting dollars go to SBEs. See also, e.g., Small

depo. at Ex. 5 (Citys “Subcontracting Outreach

Program Summary” sets Drywall “Goal[ ] For Bid

Package C” at 35%).

Standing alone, that SBE goal does not on its face

implicate any considerations of race or gender, and the

court does not understand Plaintiff to argue that a

106a

program undertaken to ensure participation of small

businesses is subject to heightened scrutiny simply

because it may have the ancillary effect of broadening

participation for people in groups as defined by race or

gender. Plaintiff argues, however, that the program

must be assessed in light of ‘Minority Business

Enterprise/Women’s Business’ Enterprise’

“participation goals of 30% [for] construction

services [,to be] monitored, tracked internally, and

reported annually to city council along with annual

SBE participation rates,” as also established in Code

323-7(a), and in light both of “availability estimates”

provided by the City to reflect percentages of minority

and female controlled subcontractors available for hire

in the region, and of SBE “Rules and Guidelines” that

imply or direct a race-conscious focus for the program.

The City responds that this project, by its terms,

involved only SBE goals; that availability estimates, in

and of themselves, do not establish any particular

hiring requirements; and that the Rules and

Guidelines never were officially promulgated and have

not been applied, at least in full, to this project.

It is undisputed that in the course of the bidding

process, the City was asked why it had provided

prospective bidders with an “Availability Estimation

Sheet ... Subcontractor Outreach Program (CMC 323-

31) noting availability estimates for drywall

subcontractors of “13.09% Minority” and “1.05%

Female.” See Amended Complaint at Ex. B and City’s

MSJ at page 8. The inquiry, disseminated along with

the answer to all prospective bidders, continued: “I

thought this project only deals with SBEs. Please

clarify.” The City responded: “This project does deal

with SBEs. However, the City of Cincinnati’s Disparity

107a

Study found that Minorities and Females were

underutilized in city contracting projects. .... The

minority and female business owner would also have

to be certified with the City as a Small Business

Enterprise. If the availability estimates are not met, it

does not mean that the bid will be deemed non-

responsive. However, we expect the utilization of SBEs

to be reflective of the availability estimates.” Amended

Complaint at Ex. H; City’s MSJ at 8.

The City submits that this arguably rather opaque

answer demonstrates that the drywall bids were

governed exclusively by SBE considerations without

regard to MBE/WBE concerns. The City points, also, to

evidence indicating that a first round of bidding

resulted in no contract award because Valley, while

exceeding the MBE availability estimate, did not

satisfy the 35% SBE goal. The City further notes

testimony of its representatives to the effect that

availability estimates did not factor into its bid

evaluation, and argues that a stated desire to calculate

and track project participation by race does not itself

trigger strict scrutiny under such precedent as Reed v.

Agilent Technologies, 174 F. Supp. 176 (D. Del. 2001).

The City, in short, cites to testimony of its

representatives that Cleveland was disqualified

because it did not meet the 35% SBE goal, and that

considerations of race simply did not enter into the

determination. See, e.g., purchasing agent Franklin

depo. at 46; Ranford at 68 (“when I looked at a bid I

did not look at the availability estimation, all I was

concerned about was Small Business Enterprise”).

Cleveland contends that the City’s answer on the

relevance of availability estimates should not be

108a

construed as advising bidders that the City will not

consider race or gender in evaluating bids. Moreover,

Cleveland points to Valley’s certification of MBE

percentages in its winning Subcontractor Utilization

Plan, to language in the required Statement of Good

Faith Efforts (form 2007, certifying use of any

“methods to obtain the- maximum practicable

participation by small, minority and women-owned

business enterprises”), and to language in the

Subcontracting Program Outreach Summary stating

that “[blidders should be able to include minority and

female firms at the level of availability indicated.” See,

e.g., Strawser depo. ex. 3; Small depo. ex. 5.

Moreover, Cleveland emphasizes a document titled:

“City of Cincinnati/Small Business Division/Office of

Contract Compliance/Small Business Enterprise

Program/Rules and Guidelines.” See Townsend depo.

ex. 19. That document recites, among other things,

that “[iJf ... evaluation determines that a bidder has

failed to achieve levels of minority and women

business enterprise participation as might be

reasonable on the basis of objective data regarding

availability and capacity of such businesses, the bidder

shall be subject to an inquiry by the Office of Contract

Compliance.” Furthermore, the document states, that

Office is to examine bid forms to determine “the

amount of the subcontracts awarded to minority and

women-owned businesses .... If the bidder’s utilization

is the same as or greater than the actual availability

percentage, then the city can accept the bidder’s

utilization as being in compliance with the program.

The burden is on the bidder to explain the low

utilization percentage. If the contract administrator

determines that the contractor under-utilized minority

109a

and/or women-owned businesses based on the actual

availability percentage, and that the bidder’s good

faith efforts were inadequate and there is no

legitimate explanation for the under-utilization, then

the matter is turned over to the investigative unit for

a discrimination investigation.” Townsend depo. ex. 19

at 6, 45-46.

For the purposes of these motions, the City does not

really argue that such provisions in the “Rules and

Guidelines” document are permissible as mechanisms

to prevent intentional discrimination by contractors.

Rather, the City contends that “[tlhe Rules and

Guidelines ... were never signed by the City Manager

and do not have the force of law,” and that “certain

portions of the ‘Rules and Guidelines’ have not been

used” in the bid solicitation and evaluation process.

See City’s memo opposing Plaintiffs MSJ at 13; see

also Lemmie depo; Ranford depo. at 68, 70-73 (City

engaged in no evaluation of MBE participation).

Code section 323-31 instructs the City Manager to

promulgate rules and regulations for the SBE

Subcontracting Outreach Program; the City Manager,

however, has testified that, “I have not promulgated

rules and regulations under this section.” Lemmie

depo. at 10. The City also notes that there is no

evidence in the record that the Rules and Guidclines

document was made available or known to any bidder

prior to the award of the contract at issue; that is, the

current record does not reflect that the document

directly could have caused any bidder to take race into

account in submitting a proposal. The City in effect

disavows any problematic portions of the document by

arguing that those sections never have controlled the

110a

policy of the City or its contractors. On the state of the

record to date, that appears to be a genuine issue of

material fact (although the court does observe that the

City has admitted that the Rules and Guidelines “are

... part of the Small Business Enterprise Program,” see

City’s Response to Interrogatory 17(D) at 6).

Viewing the evidence in the light most favorable to

the non-moving party, and given that the Rules and

Guidelines document was prepared for and available

to City staff, and served to some extent as “working

documents used by staff,” Lemmie depo. at 11 and

Stark depo. ex. 6, (and considering, too, presumptions

of regularity that generally inform review of

governmental! actions), the court cannot conclude for

summary judgment purposes that the principles

embodied in the Rules and Guideline document played

no part in the determinations at issue here. By the

same standard, with all reasonable inferences drawn

in favor of the Defendants in evaluating Cleveland’s

summary judgment motion, the court cannot find as a

matter of undisputed fact that certain sections of the

Rules and Guidelines cited above entered into the

City’s decision. The status of the “Rules and

Guidelines,” and the issue of to what extent and effect,

if any, they were used here or may support other

reasonable inferences regarding Cleveland’s claim that

the SBE program is run as a “sham” to mask a race-

conscious awards program, remain questions of

arguably material fact.

In light of the City’s response to the bidder inquiry

about the relevance of availability estimates, viewed in

conjunction with the bid documents and Code

mandates and the Rules and Guidelines document,

llla

and the testimony of City officials, the court similarly

concludes under the summary judgment standard that

a question of fact remains as to whether the City did

intelligibly and accurately communicate to the bidders

that this drywall project was to be administered under

SBE principles without regard to considerations of

race (as Defendants maintain was the case and which

Plaintiff strongly disputes). Moreover, the court notes

as an aside that the record indicates arguably

conflicting testimony regarding the _ subjective

impressions of the bidders on this score.

In short, whether or not the City has engaged here

in a race-conscious contracting program of the sort

that would require “strict scrutiny” review depends on

a determination of facts that remain at issue when

reasonable inferences are drawn in favor of the non-

moving parties on each of the summary judgment

motions. Cf. Safeco Ins. v. City of White House, Tenn.

(6 Cir. 1999), 191 F.3d 675, 692 (“Outreach efforts

may or may not require strict scrutiny” [citing

authority that such heightened review “is generally

inapplicable’ to outreach efforts that target one race],

“But ... where their administration ‘indisputably

pressures’ contractors to hire minority subcontractors

[,] courts must apply strict scrutiny”).

The City argues, however, that Cleveland lacks

standing to pursue its equal protection claims in any

event because it did not meet the 35% SBE standard

and therefore could not have been awarded the

contract regardless of any other considerations. Cf.

Florida General Contractors v Jacksonville (1993), 508

U.S. 656 (traceability requirement). The court finds

below however, that the City’s Code in some instances

112a

precludes award of a contract based primarily on SBE

Subcontractor Outreach Program considerations where

the winning bid is more than $50,000 higher than the

bid of an otherwise qualified contractor rejected for not

meeting the SBE goal. Under these circumstances,

where the City agreed to pay well more than one

million dollars extra in order to achieve 35%

participation by small businesses in the drywall

project, the undisputed facts do not establish for

summary judgment purposes that Cleveland would

have been out of the running for the award had the

City applied its SBE rules in the context of the Code as

written. Thus, Defendants’ standing argument fails at

this point in the process for reasons even beyond

Cleveland’s contention that the SBE program itself is

wholly a sham to mask impermissible race-conscious

awards.

The court therefore denies the motions for

summary judgment of all three parties with regard to

Cleveland’s equal protection claims.

Due Process Issues

Defendants concede that Cleveland’s bid to perform

the drywall work on the City’s Convention Center

project was $1,246,022.00 lower than Valley’s. City’s

MSJ Memo at 7 (“Valley’s bid was for $10,135,022.00

while Cleveland’s bid totaled $8,889,000.00”); Valley’s

MSJ (adopting “all the same grounds” as City).

Defendants also affirm that “Cleveland’s bid was

excluded from consideration because it failed to meet

the SBE requirements,” City’s MSJ Memo at 7, and

they point to no other infirmities in Cleveland’s bid or

capacity to perform the work. Cf. Franklin depo. at 21-

1122

22, 29, 62, 88 (City purchasing agent believes that all

three bidders met non-SBE bid specifications and that

those bids were acceptable to the purchasing

department; no issues with Cleveland’s prior

performance).

Code section 321-37, “Bid; Award to Lowest and

Best” provides in part:

“(a) Selection of Lowest and Best in Award of City

Contracts: Except where otherwise provided by

ordinance, the city purchasing agent shall award a

contract to the lowest and best bidder. ...

(c) Factors to be Considered: Other factors that the

city purchasing agent may consider in determining

the lowest and best bid include, but are not limited

to: [prior performance; prevailing wage history;

compliance with nondiscrimination rules; and]

(4) Information concerning compliance with the

‘SBE Subcontracting Outreach Program’ rules and

regulations issued by the city manager pursuant to

... section 323-31.

In the event that the selection of the lowest and best

bidder is based primarily upon factors 3 or 4 above,

the contract award may be made subject to the

following limitation: the bid may not exceed an

otherwise qualified bid by ten (10%) percent or Fifty

Thousand Dollars ($50,000.00), whichever is lower.”

(emphasis added)

ll4a

Cleveland contends that in awarding the contract

to Valley despite the fact that Valley’s bid was more

than $50,000 higher than Cleveland’s (by more than

1.2 million dollars), the City abused its discretion and

thereby deprived Cleveland of a constitutionally

protected property interest without due process of law.

Defendants argue that Cleveland was not the lowest

and best bidder because it failed to reach the SBE goal

without regard to Subcontracting Outreach Program

rules. See City’s memo in op. at 22; Valley’s memo in

op. at 10 (“Code section 321-37 does not apply ...

because Cleveland was not an otherwise qualified

bidder eligible for consideration «under 321-37”).

For a property interest in the award of a public

contract to inhere, “one must have more than a

unilateral expectation; rather, one must instead have

a legitimate claim of entitlement to such a contract.”

Cleveland Construction, Inc. v. Ohio Department of

Administrative Services (10™ Dist. 1997), 121 Ohio

App. 3d 372, 394. Thus, “a disappointed bidder to a

government contract may establish a legitimate claim

of entitlement protected by due process by showing

that local rules limited the discretion of ... officials as

to whom the contract should be awarded” and that

discretion was abused in depriving the bidder of the

award. Id. at 394-95 (no abuse of discretion found); see

also, e.g., Enertech Electrical, Inc. v. Mahoning Co.

Commissioners (6 Cir. 1996), 85 F.3d 257, 260 (“A

constitutionally protected property interest in a

publicly bid contract can be demonstrated .... [if a

bidder can show] that, under state law, the County

had limited discretion, which it abused, in awarding

the contract’; no abuse of discretion found); Peterson

Enterprises, Inc. v. Ohio Department of Mental

115a

Retardation (6" Cir. 1989), 890 F.2d 416 (“if the board

had limited discretion under local roles as to whom

should be awarded the contract ..., then Plaintiff might

have a protected property interest in the award if he

were the beneficiary of the state law mandate;” no

property interest where state guidelines were

nonexhaustive); cf. United of Omaha Life Ins. Co. v.

Solomon (6 Cir. 1992), 960 F.2d 31, 34 (“Michigan ...

law neither requires that the lowest bidder be awarded

a state contract nor creates a property interest in

disappointed bidders on state contracts”); Cementech,

Inc. v. City of Fairlawn (Ohio 9™ Dist. App.), 2005 WL

844948 (disappointed bidder whom jury found had

submitted lowest and best bid may qualify for money

damages when project is already complete); but see,

Miami Valley Contractors, Inc. v. Montgomery Co. (2"°

Dist. App.), 1996 WL 303591 (“as best we can

determine, this jurisdiction has never recognized a

constitutionally protected property interest of a

disappointed bidder on a public works project”); Miami

Valley Contractors, Inc. v. Oak Hill (4" Dist. App.

1996), 108 Ohio App. 3d 745, 752 (no abuse of

discretion found; “we can find no support for the

proposition that a second- or third-place finisher in a

lowest and best bidder determination acquires a

constitutionally protected property right”).

“The meaning of the term ‘abuse of discretion’ ...

connotes more than an error of law or judgment; it

implies an unreasonable, arbitrary or unconscionable

attitude’ .... ‘Arbitrary’ means ‘without adequate

determining principle; *** not governed by any fixed

rules or standard.’ .... ‘Unreasonable’ means

‘irrational’.” Cedar Bay Construction, Inc. v. City of

Fremont et al., 50 Ohio St.3d 19, 22, citations omitted.

1l6a

Moreover, “courts in this state should be reluctant to

substitute their judgment for that of city officials in

determining which party is the ‘lowest and best

bidder.’ .... [I[]n the absence of evidence to the contrary,

public officers [and] administrative officers ..., within

the limits of the jurisdiction conferred by law, will be

presumed ... not to have acted illegally.” Id. at 21.

Discretion for determining the lowest and best bid “is

not vested in the courts and the courts cannot interfere

in the exercise of this discretion unless it clearly

appears that the city authorities in whom such

discretion has been vested are abusing the discretion’.”

Id. at 21 (citation omitted). See also, e.g., Greater

Cincinnati Plumbing Contractors’ Association v. City

of Blue Ash (1*Dist. 1995), 106 Ohio App. 3d 608, 613-

14 (a Charter city’s discretion in accepting lowest and

best bid “is similar to the discretion provided under

general state law [citing R.C. 735.05]; “Competitive

bidding provides for ‘open and honest competition in

bidding for public contracts and [saves] the public

harmless, as well as bidders themselves, from any kind

of favoritism or fraud in its varied forms’”).

If the bid in the instant case was awarded in

violation of the explicit $50,000/10% cap established by

321-37(c)(4), the award would be an abuse of discretion

and Cleveland would have a “legitimate claim of

entitlement” sufficiently clear to give rise to a due

process claim. Violation of that precise standard as

established by ordinance would move Cleveland’s

interest in the contract beyond the “mere ‘unilateral

expectation” of receiving the award under a regime in

which the relevant ordinance provides non-exhaustive

guidelines limiting discretion, cf. Peterson Enterprise,

890 F.2d 416; Cleveland Construction, 121 Ohio App.

117a

3d at 394, and into that rare context in which a

disappointed bidder may assert a constitutionally

protected property interest. This is the basis on which

Cleveland advances the second part of its motion for

partial summary judgment. See Motion at 2 (seeking

judgment based on an asserted “property interest in

the contract”). Under the summary judgment

standard, the court thus turns to the question of

whether any genuine issue of material fact exists as to

whether the City breached its 321-37(e)(4) cap.

The language of 321-37 establishes. that

“information concerning compliance” with the City’s

SBE Subcontracting Outreach Program rules and

regulations is a “[flactor” that “may” be considered as

the City determines the lowest and best bid. If the

lowest and best bid is selected “based primarily” on

that factor, the City may proceed to award the contract

“subject to the following limitation: the bid may not

exceed an otherwise qualified bid by ten (10%) percent

or Fifty Thousand Dollars ($50,000.00), whichever is

lower.” 321-37(c)(4).

In that context, the phrase “otherwise qualified bid”

can reasonably be read only to mean a bid that is

qualified except that it is not in “compliance” with the

SBE Subcontracting Outreach Program “factor”. The

bid not selected “primarily” because of the SBE

Subcontracting Outreach Program factor must

“otherwise” be qualified in order to trigger the required

calculation with regard to whether the contract award

may be made as selected on that basis.

Cleveland points to legislative history for 321-37

indicating that the City Administration took the

118a

position and advised Cincinnati’s City Council that the

ten-percent/$50,000.00 cap would apply to any

purchasing contract affected by SBE compliance

issues. Assistant City Manager Rashid Young advised

Council’s Law and Public Safety Committee on

November 25, 2003 that “{w]hat this ordinance allows

us to do is be clear about when it is appropriate to

award a bid to a SBE compliant [bidder] if they are not

the lowest. This ordinance would allow us to award a

bid if the bid is $50,000 or less difference away from

the lowest bid. .... We had an example where the SBE-

compliant bidder was some nine hundred thousand

dollars in excess of the lowest bid and ... it didn’t make

a lot of sense to spend nine hundred thousand dollars

more to comply with the regulations of SBE.” Young

depo. and ex. 1.

By its terms, however, the cap applies specifically

(and exclusively) to instances where a higher bid is

accepted because of “information concerning

compliance with ‘SBE Subcontractor Outreach

Program rules’ ... issued ... pursuant to 323-31.” Code

321-37(c4) (emphasis added). As used in the

legislative text, the reference to an “SBE

Subcontractor Outreach program” does not appear

coextensive with the broader “Small Business

Enterprise Program” itself. Thus, for example: Chapter

323 as a whole is titled “Small Business Enterprise

Program,” while section 323-31 specifically is titled

“Subcontracting Outreach Program;” and Section 323-5

directs the City Manager to “issue and enforce

regulations to carry out the meaning and purpose of

the small business enterprise program authorized by

this chapter,” while Section 323-31 directs the City

Manager to “issue and enforce rules and regulations to

119a

carry out the meaning and purpose of the

Subcontracting Outreach Program, substantially in

conformance with the content of Part II, Section I, the

‘Legislative Recommendation Report To The City of

Cincinnati’ dated December 17, 2002, prepared by

Griffin & Strong, P,C..”

As Cleveland observes: “A basic rule of statutory

construction requires that ‘words in statutes should

not be construed to be redundant, nor should any

words be ignored.’ ... No part lof a statute] should be

treated as superfluous unless that is manifestly

required, and the court should avoid that construction

which renders a provision meaningless or inoperative.”

D.A.B.E., Inc. v. Toledo-Lucas County Board of Health

(2002), 96 Ohio St.3d 250-256 (citations omitted); see

also Cleveland’s MSJ Motion/Memo at 39. Council

enacted 323-31 directing enforcement of regulations

f

This text is long and has been trimmed here. Open the source document for the complete record.

This is a copy of a public record, reproduced as it was published. It is not legal advice, and it may not be the version a court would rely on. Check the official source before you cite it.

A word about cookies

We need a few to keep you signed in and the library working. The rest help us see which pages people use and where they get stuck. They stay off unless you say yes.