Opposition Brief — Utility Water Water Act Group Group v. Riverkeeper, Inc. (Nos. 07-597, 07-588, 07-589)
Supreme Court brief2009
Ask Donna
What actually matters in this document.
Text
4
Nos. Om 07-589 & 0
In The SUPREME COURT, us
Supreme Court of the Anited States
ENTERGY CORPORATION,
Petitioner,
Vv.
ENVIRONMENTAL PROTECTION AGENCY, ET AL.,
Respondents.
PSEG Fossit LLC snp PSEG Nuc ear LLC,
Petitioners,
v.
RIVERKEEPER, INC., ET AL.,
| | - Respondents.
Utitity WATER Act GROUP,
Petitioner,
Vv.
RIVERKEEPER, INC., ETAL.,
Respondents.
On Petitions for Writ of Certiorari to the United
States Court of Appeals for the Second Circuit
— — ——
BRIEF FOR RIVERKEEPER, INC., ET AL. IN OPPOSITION
P. Kent CORRELL Reep W. Surer
300 PaRK AVENUE Counsel of Record
17TH FLOOR LAW OFFICE OF REED W. SuPER
New York, NY 10022 116 JOHN STREET, SUITE 3100
(212) 475-3070 New York, NY 10038
(212) 791-1881
Counsel for Respondents Riverkeeper, Inc., et al.
February 29, 2008
Becker Gallagher - Cincinnati, OH - Washington, D.C. ~ 800.890.5001
COUNTER STATEMENT OF
QUESTIONS PRESENTED
1. Whether the court of appeals properly remanded
the Environmental Protection Agency’s Phase II
cooling water intake structure regulations for further
rulemaking because of uncertainty as to whether EPA
based its determination of “best technology available”
(“BTA”) on cost-benefit analysis rather than on
economic availability, cost-effectiveness, or other
considerations permissible under the plain language of
Clean Water Act section 316(b). (07-588 Q3; 07-589
Q1; 07-597 Q1)
2. Whether the court of appeals correctly followed
its Phase I decision and remanded a provision in EPA’s
Phase II cooling water intake structure regulations
that would have allowed compliance with section
316(b) through “restoration measures.” (07-589 Q2;
07-597 Q2)
3. Whether section 316(b) of the Clean Water Act
applies to both new and existing facilities, as its plain
language makes clear and as the courts and EPA have
consistently recognized since the statutory provision
was enacted in 1972. (07-588 Qs1&2)
il
CORPORATE DISCLOSURE STATEMENT
Respondents Riverkeeper, Inc., Natural Resources
Defense Council, Waterkeeper Alliance, Soundkeeper,
Inc., Scenic Hudson, Inc., Save the Bay—People for
Narragansett Bay, Friends of Casco Bay, American
Littoral Society, Delaware Riverkeeper Network,
Hackensack Riverkeeper, Inc., New York/New Jersey
Baykeeper, Santa Monica Baykeeper, San Diego
Baykeeper, California Coastkeeper, Columbia
Riverkeeper, Conservation Law Foundation, and
Surfrider Foundation have no parent corporations, and
no publicly owned company owns stock in them.
lit
TABLE OF CONTENTS
Page
PRESENTED -..-sesscssvestsseessseevecseed
CORPORATE DISCLOSURE STATEMENT ..... ii
TABLE OF AUTHORITIES .................. iv
COUNTER STATEMENT OF THE CASE ...... 1
Cooling Water Intake Structures ......... 2
EPA Rulemaking under Section 316(b).... 3
REASONS FOR DENYING THE PETITIONS ... 9
I. THERE IS NO VALID REASON FOR
REVIEW NOW, WHILE REMAND
PROCEEDINGS ARE PENDING........ 10
Il. THEREIS NOCIRCUIT SPLIT ........ 15
A. Cost Considerations ............. 16
B. Restoration Measures ........... 20
C. Existing Facilities .............. 22
Ill. THE DECISION BELOW IS CORRECT... 24
A. Cost Considerations ............. 24
B. Restoration Measures ........... 27
C. Existing Facilities .............. 29
| TRUE TTC CT CTI TUTE TT TTT Tee 30
iv
TABLE OF AUTHORITIES
Cases
American Petroleum Institute v. EPA,
661 F.2d 340 (5th Cir. 1981) .............. 25
American Textile Manufacturers
Institute, Inc. v. Donovan,
452 U.S. 490 (1981) ............... 24, 25, 26
Appalachian Power Co. v. Train,
566 F.2d 451 (4th Cir. 1977) ............ 3,15
BP Exploration & Oil, Inc. v. EPA,
66 F.3d 784 (6th Cir. 1995) ............... 19
Chevron U.S.A., Inc. v. Natural
Resources Defense Council,
eee passim
Clingman v. Beaver,
nce eens ccpoceesees 23
ConocoPhillips Co., et al. v. EPA,
5th Cir. Dkt. No. 06-60662 ................ 9
E.I. du Pont de Nemours & Co. v. Train,
EE MID neg 0 4 60. 0. 6-0 G0. 0.0.6.% 66 65058 29
EPA v. National Crushed Stone Ass’n,
ed od wanda ek shee ae 19
Natural Resources Defense Council v. EPA,
859 F.2d 156 (D.C. Cir. 1988) ............. 23
Riverkeeper, Inc. v. EPA,
358 F.3d 174 (2d Cir. 2004) ............ passim
Riverkeeper, Inc. v. EPA,
475 F.3d 83 (2d Cir. 2007) ............. passim
v
TABLE OF AUTHORITIES
-continued-
Page(s)
Seacoast Anti-Pollution League
v. Costle
597 F.2d 306 (1st Cir. 1979) ..... 15, 16, 17, 21
United States Steel Corp. v. Train,
556 F.2d 822 (7th Cir. 1977) ........ 15, 18, 22
Virginia Electric & Power Co. v. Costle,
66 F.2d 446 (4th Cir. 1977) .............. 22
Walters v. Metropolitan Education
Enterprises, Inc., }
ee , EOD bin vo vcs cee céaus seseen 28
Weyerhaeuser Co. v. Costle,
590 F.2d 1011 (D.C. Cir. 1978) ............ 19
Whitman v. American Trucking Ass’ns,
ke ff , eaerneiireiy sess 25, 26
Statutes and Regulations
ft eR EE rng rer 26
Roe FoR B.S | rer a 19
3Oo U.B.C. & BBEBIBMAMA) .. nw ccc cccccccccces 26
ats oe ef 00Ul) ee oe 26
(Bis Foe 8) Ul ee 26
33 UBC. 6 SEROMA) .. nw cc ccccccvecsveces 19
Se See, ED 0 0 4 0-0 éccnedee cee eee 21
oR ee passim
vi
TABLE OF AUTHORITIES
-continued-
Page(s)
33 U.S.C. § 1342(aX 1A) ..........-. 2 eee 30
42 U.S.C. § 300g-1(bX3(C)\MUIV) .......--.... 26
42 U.S.C. § 7545(cM2KB) .... 2... cee eee eee 26
ss eo. see eknbeeseeeees 26
Ce Gs | ee eee eee 4
es LD onc ccc cc cccccccncs 4,13
to sath eeniceceeseonee 4,13
ek A RF) ee rere 4,13
40 C.F. § 126.90 et eq. ... 1. ccc cece 5
eh SR re 5
40 C.F.R. § 125.94(aM5Xii) .. 2... eee eee eee 5
ee ka ee Sec eke eases ces 5
Ee 5
Other Authorities
41 Fed. Reg. 17,387 (Apr. 26, 1976) ............ 3
44 Fed. Reg. 32,853 (June 7, 1979) ............. 3
66 Fed. Reg. 28,853 (May 25, 2001) ............ 2
66 Fed. Reg. 65,255 (Dec. 18, 2001) ......... 3, 20
67 Fed. Reg. 17,121 (Apr. 9, 2002) ....... 5, 12, 13
vil
TABLE OF AUTHORITIES
-continued-
Page(s)
69 Fed. Reg. 41,575 (July 9, 2004) ........... 2,5
69 Fed. Reg. 68,443 (Nov. 24, 2004) ........... 28
71 Fed. Reg. 35,005 (June 16, 2006)............ 8
72 Fed. Reg. 37,107 (July 9, 2007) .......... 8, 10
Berea Caetene Bieta Bs oe ccc ccc cccccesas 10
1
COUNTER STATEMENT OF THE CASE
In language not repeated elsewhere in the Act or in
any other federal statute, section 316(b) of the Clean
Water Act (“CWA”) provides that “[a]ny standard
established pursuant to section 301 or section 306 of
this Act and applicable to a point source shall require
that the location, design, construction, and capacity of
cooling water intake structures reflect the best
technology available [‘BTA’] for minimizing adverse
environmental impact.” 33 U.S.C § 1326(b). Section
316(b) is the only provision in the statute that
regulates water withdrawals, as opposed to discharges.
In this case, which presents questions of first
impression concerning the application of this unique
statutory language to a novel Environmental
Protection Agency (EPA) rulemaking, the Second
Circuit unanimously remanded EPA’s rule for further
explanation and possible revision. Riverkeeper, Inc. v.
EPA (“Riverkeeper IT’), 475 F.3d 83 (2d Cir. 2007);
App. la-86a.' Significantly, EPA has not sought
review by this Court and is reconsidering its rule on
remand. Only industry parties have filed petitions for
certiorari.
The petitions should be denied for three reasons.
First, the further administrative proceedings on
remand make review premature, and petitioners’
exaggerated claims about the purportedly devastating
impact of the court’s ruling ignore the indisputable fact
that the effect of that ruling has yet to be determined.
Second, there are no circuit splits. Third, the court’s
decision is correct on the merits, and there is no
* Citations to “App.” refer to petitioner PSEG’s appendix.
2
compelling reason for this Court to review the court of
appeals’ fact-specific application of this unique
statutory language to EPA’s rulemaking.
Cooling Water Intake Structures
Section 316(b) directs EPA to regulate cooling
water intake structures, through which power plants
and other heavy industrial facilities withdraw cooling
water from natural waterbodies. Such structures “kill
or injure billions of aquatic organisms every year” by
trapping (or “impinging”) them against grills or
screens or drawing them into the cooling system
(“entraining” them). Riverkeeper II, App. 2a; see also
Riverkeeper, Inc. v. EPA (“Riverkeeper I”), 358 F.3d
174, 181 (2d Cir. 2004) (“A single power plant might
impinge a million adult fish in just a three-week
period, or entrain some 3 to 4 billion smaller fish and
shellfish in a year, destabilizing wildlife populations in
the surrounding ecosystem.”). Intake structures affect
the full spectrum of aquatic organisms, from plankton
to sea turties, including threatened and endangered
species. 69 Fed. Reg. 41,575, 41,586-87 (July 9, 2004).
Available technology can dramatically reduce this
environmental damage. Some plants are “dry-cooled”
by air instead of water, and many others employ
“closed-cycle” water cooling systems that reduce
withdrawals and aquatic mortality by 70 to 96 percent
compared to the relatively primitive “once-through”
cooling systems used by older plants. Virtually all gas-
fired power plants and two-thirds of coal-fired plants
built in the last 25 years use closed-cycle cooling. 66
Fed. Reg. 28,853, 28,856 (May 25, 2001); see also NEI
Amicus Br. 16 (about 40 percent of nuclear plants are
closed-cycle). Other technologies, such as fine-mesh
3
screens, barrier nets, and fish diversion or return
systems, are designed to exclude organisms from
intakes or return them to waterways.
EPA Rulemaking under Section 316(b)
The 1976 Regulations. In 1976, EPA promul-
gated section 316(b) regulations,” but the regulations
were remanded by the Fourth Circuit because of a
notice-and-comment violation, Appalachian Power Co.
v. Train, 566 F.2d 451, 457 (4th Cir. 1977), and with-
drawn. 44 Fed. Reg. 32,853, 32,956 (June 7, 1979).
EPA issued no new section 316(b) regulations in the
1980s or 1990s. Absent regulations, permits for intake
structures were issued during that time by EPA and
state agencies on a case-by-case, “best professional
judgment” basis.
Between 1995 and 2002, EPA agreed to a series of
consent decrees requiring it to conduct rulemaking
under section 316(b), amd ultimately decided to pursue
the rulemaking in three phases: (1) Phase I (new
facilities); (2) Phase II (large existing power plants);
and (3) Phase III (small existing power plants and all
other existing facilities). App. 4a-5a.
Phase I. In 2001, EPA promulgated its Phase I
Rule covering cooling water intake structures at new
facilities. 66 Fed. Reg. 65,255 (Dec. 18, 2001). The
Phase I Rule requires larger new facilities to use
* At that time, EPA refused to determine BTA based on cost-
benefit analysis, explaining that “[t]he statute directs the Agency
to ... select the most effective means of minimizing (i.e., ‘reducing
to the smailest possible amount or degree’) th[e] adverse effects.”
41 Fed. Reg. 17,387, 17,388 (Apr. 26, 1976).
4
cooling water intakes that withdraw no more water
than a closed-cycle system. 40 C.F.R. § 125.84(b)(1).
The Phase I Rule also includes a second compliance
track under which a facility can escape limits on
intake flows if it uses other technologies that achieve
comparable reductions of adverse environmental
impacts, see 40 C.F.R. §§ 125.84(d)(1), 125.86(c)(2), and
a “variance” provision if compliance at a particular
facility would be excessively costly or have adverse
impacts on air or water quality or energy markets. 40
C.F.R. § 125.85. In addition, the Phase I Rule would
have allowed compliance solely through habitat
“restoration measures” designed to offset the adverse
impact of cooling water withdrawals. 66 Fed. Reg. at
65,280-81. Like the remanded 1976 regulations, the
Phase I requirements were not based on cost-benefit
analysis. Instead, EPA “selected best technology
available for minimizing adverse environmental
impact on the basis of what it determined to be an
economically practicable cost for the industry as a
whole.” 66 Fed. Reg. at 65,309. EPA gave three
reasons, including “cost-effectiveness,” for rejecting
standards based on dry cooling. 66 Fed. Reg. at
65,282-84.
In consolidated challenges by environmentalists
and industry, the Second Circuit upheld most of the
Phase I Rule, Riverkeeper I, 358 F.3d at 181, but
remanded the “restoration measures” provision “as
plainly inconsistent with the statute’s text” because
they did not involve the “location, design, construction,
and capacity” of intake structures, id. at 189, and did
not meet the statutory requirement of “minimizing the
adverse environmental impact” of those structures. Id.
5
at 190. No party sought certiorari, and the
Riverkeeper I decision is final.
Phase II. In 2004, EPA promulgated the Phase II
Rule at issue here, applicable to large existing power
plants. 69 Fed. Reg. 41,575 (July 9, 2004), codified at
40 C.F.R. § 125.90 et seg. The Phase II Rule set
performance standards requiring a 60-90 percent
reduction in entrainment and a 80-95 percent
reduction in impingement, to be achieved through any
technologies. 40 C.F.R. § 125.94(b). EPA based these
standards on a suite of technologies.
The Phase II Rule included alternative compliance
options allowing facilities to elect a less stringent
determination of BTA based on either cost-cost
analysis (comparison of a facility's costs to those
considered by EPA) or cost-benefit analysis. 40 C.F.R.
§ 125.94(a)(5)(i), (ii). Like the Phase I Rule, the Phase
II Rule also allowed compliance through “restoration
measures.” 40 C.F.R. § 125.94(c).
The Phase II Rule rejected stricter requirements
based on closed-cycle cooling. One alternative EPA
considered but rejected was a flow limit commensurate
with closed-cycle cooling for 51 facilities — less than ten
percent of the facilities covered by the rule — with
extremely large withdrawals from waterbodies
containing essential habitat and nursery areas. 67
Fed. Reg. 17,121, 17,155-58 (Apr. 9, 2002).
Both environmentalists and industry challenged
the Phase II Rule in consolidated petitions. In the
unanimous decision below, the Second Circuit rejected
Entergy’s claim that section 316(b) applies only to new
facilities and remanded eight aspects of the rule to
6
EPA for further rulemaking because it found they were
“inadequately explained or inconsistent with the
statute, or because the EPA fa led to give adequate
notice of its rulemaking.” App. sa.
In the holding to which petitioners primarily object,
the court of appeals stated: “If the EPA construed the
statute to permit cost-benefit analysis, its action was
not ‘based on a permissible construction of the
statute.” Id. at 33a (quoting Chevron U.S.A., Inc. v.
Natural Res. Def. Council, 467 U.S. 837, 843 (1984)).
Significantly, the court of appeals did not construe
section 316(b) as barring cost considerations entirely.
Rather, it held that the “statutory language suggests
that the EPA may consider costs in determining BTA,
in that a technology that cannot not be reasonably
borne by the industry is not ‘available’ in any
meaningful sense,” but that “cost-benefit analysis is
not similarly supported by the language or purpose of
the statute.” Jd. at 21a. The court further explained
that, in determining BTA, EPA must “first determine
what is the most effective technology” and “whether
the industry as a whole can reasonably bear the cost of
the adoption of the technology,” id. at 23a, and that
“EPA may then consider other factors, including cost-
effectiveness, to choose a less expensive technology
that achieves essentially the same results as the
benchmark.” Jd. at 23a-24a. Finally, the court
explained that EPA “may also depart from this
performance benchmark because of other permissible
considerations aside from cost, for instance, energy
efficiency or environmental impact.” Jd. at 24a n.12
(citing Riverkeeper I, 358 F.3d at 195-96).
7
Notably, the court’s ruling concerning the
appropriate role of costs under section 316(b) did not
lead it to reject EPA’s BTA determination definitively.
Although the court said that cost-benefit analysis
“appears to have played some role” in EPA’s BTA
determination, id. at 29a, the court found it “unclear
whether the Agency improperly weighed the benefits
and the costs.” Id. (emphasis added); see also id. at
32a (“[I]t is impossible to tell whether the EPA based
its decision on permissible cost-effectiveness analysis
or exceeded its authority by relying impermissibly
upon a cost-benefit analysis.”) (emphasis added). Asa
result, the court concluded that “[i]t may also be that
the EPA misunderstood or misapplied cost-
effectiveness analysis” or “may have simply failed
either to perform the required analysis or to explain
adequately a decision that was within its authority to
make.” Id. at 33a. Accordingly, the court “remand|ed!
to the EPA the provision establishing BTA so that it
may provide either a reasoned explanation of its
decision or a new determination of BTA based on
permissible considerations.” Id. at 85a. Importantly,
the court required only “clarification of the basis for
the Agencys action and possibly ... a new
determination of BTA.” Jd. at 33a (emphasis added).
The court also remanded several other provisions that
were based on the same considerations as, or closely
interrelated with, the BTA determination.
With respect to restoration measures, the court
followed its decision in Riverkeeper I in finding that, by
allowing compuance through restoration measures,
EPA had impermissibly construed section 316(b). Jd.
at 85a.
8
Finally, the court rejected Entergy’s claim that
section 316(b) applies only to new facilities, id. at 65a-
70a, holding that the plain language of section 316(b),
and in particular its reference to section 301, which
applies to existing point sources, indicates that the
section applies to existing facilities, and that even if
the language were ambiguous, EPA’s reasonable and
longstanding interpretation of it as applying to
existing facilities was entitled to Chevron deference.
EPA did not seek rehearing, and petitioners’
rehearing requests were denied with no judge voting
for rehearing. Anp. 88a-89a. Upon remand, the
agency suspended virtually the entire Phase II Rule,
72 Fed. Reg. 37,107 (July 9, 2007), and commenced
further rulemaking proceedings. Until EPA prom-
ulgates a new final Phase II Rule, “{plermit —
requirements for cooling water intake structures at
Phase II facilities should be established on a case-by-
case best professional judgment (BPJ) basis.” Id. at
37,108. EPA’s suspension of the rule thus restored the
status quo ante with respect to permitting of power
plant cooling water intakes that has been in effect for
35 years.
Phase III. In 2006, EPA promulgated Phase III
regulations applicable to new offshore oil rigs, that
were not based on cost-benefit analysis. 71 Fed. Reg.
35,005 (June 16, 2006). Simultaneously, EPA decided,
on the basis of an explicit cost-benefit analysis, not to
promulgate section 316(b) regulations for existing
manufacturing facilities. Jd. at 35,016-17. In
consolidated petitions pending before the United
States Court of Appeals for the Fifth Circuit, industry
contends that EPA should have conducted a cost-
9
benefit analysis, while the environmental petitioners
challenge EPA’s explicit reliance on cost-benefit
analysis. ConocoPhillips Co., et al. v. EPA, 5th Cir.
Dkt. No. 06-60662 (and consolidated cases). Thus, the
Fifth Circuit is currently considering “precisely the
same issue” the Second Circuit decided below —
whether EPA has authority to rely on cost-benefit
considerations under section 316(b). UWAG Pet. 18;
see also PSEG Pet. 13-14.
REASONS FOR DENYING THE PETITIONS
The decision below involves issues of statutory
interpretation whose impact on the regulation at issue
remains undetermined because of the court’s remand
to EPA for clarification of the basis of its decision.
Moreover, the Second Circuit’s conclusions that section
316(b) applies to existing facilities and that Congress
intended EPA to implement that section without
engaging in cost-benefit analysis or allowing
compliance through “restoration” measures reflect
application of standard principles of statutory
construction to unique statutory language, applied to
a single regulation, and do not conflict with decisions
of any other court of appeals. Should a conflict
eventually arise, there will be ample opportunity for
this Court to address it either in the Phase III case
that is still pending or in further judicial review
proceedings once EPA completes its reconsideration of
the Phase II Rule. Meanwhile, particularly in light of
the correctness of each of the Second Circuit’s rulings,
review by this Court is not warranted.
10
I. THERE IS NO VALID REASON FOR
REVIEW NOW, WHILE REMAND
PROCEEDINGS ARE PENDING
The Second Circuit’s decision remanded the Phase
II Rule for further explanation and possible revision in
light of the court’s opinion. The court noted that “EPA
in reconsidering its selection of BTA on remand may
alter the suite of technologies it originally selected,”
App. 34a, but the court did not say such alteration was
required, much less foreordain the exact features of a
properly explained and justified rule.
EPA has not sought review of the court’s ruling,*
but instead has suspended the Phase II Rule almost
entirely “while the Agency considers bv to address
the remanded issues.” 72 Fed. Reg. at 37,108. As
directed by the remand, EPA is reconsidering the core
provisions of the Phase II Rule, including the BTA
determination, the establishment of requirements
reflecting BTA, and the various options for complying
with or obtaining variances from those requirements.
Whatever the result of its reevaluation, EPA must
notice a new proposed Phase II Rule in the Federal
Register for public comment and then, after
considering and responding to those comments, issue
a new Phase II Rule. Only when the regulatory
process is complete will the practical impact of the
Second Circuit’s ruling become clear. Moreover,
because major parts of the rule were also remanded on
* Although we have no way of knowing what EPA may say in
response to the petitions, we note that the non-extendable time in
which EPA may file a response supporting the petitions under this
Court’s Rule 12.6 has long since passed.
11
grounds as to which petitioners have not sought this
Court’s review, further rulemaking would be required
even if this Court were to grant the petitions and then
agree with petitioners that EPA’s BTA determination
was proper. Thus, no action by this Court would
reinstate the Phase II Rule as promulgated.
When it does promulgate a new Phase II Rule, EPA
may change its BTA determination substantially,
modestly, or not at all. Another round of judicial
review is virtually inevitable, but whether it will be
the industry petitioners or environmental groups that
are aggrieved by how EPA carries out the remand
remains to be seen. In any event, any further review
will be based on a complete record, following proper
notice and comment. The Second Circuit will then
determine whether EPA’s reexamination of its actions
is consistent with section 316(b), supported by the
record, and not arbitrary and capricious. In the event
that, at the end of the day, the industry petitioners are
dissatisfied by some feature of the final rule that is
attributable to one of the aspects of the Second
Circuit’s holding that they now challenge, the
petitioners could seek review of the issue by this Court
at that time. The effectively interlocutory posture of
the proceedings below thus counsels strongly against
granting the petitions.
Meanwhile, the parade of economic and energy-
related horribles petitioners and amici conjure up to
justify review is, at this point, completely unfounded.
Their forecasts of exorbitant compliance costs, facility
closures, and grid failure are all premised on the
hypothetical presupposition that EPA will promulgate
a new rule that compels substantially all 550 Phase II
12
facilities to retrofit to closed-cycle cooling. See PSEG
Pet. 32-36, UWAG Pet. 36-39. But petitioners them-
selves concede that the decision below does not
mandate such a result. See, eg., UWAG Pet. 37
(““UWAG does not believe that retrofitting closed-cycle
cooling can be justified even after Riverkeeper II...”).
Indeed, petitioners and amici admit that their true
concern is not with the decision itself, but with what
they consider to be the “implication[s] of the Second
Circuit’s opinion,” PSEG Pet. 33, or what they predict
EPA or others will contend those implications are.
See, e.g., NEI Amicus Br. 9 (respondents “will no doubt
argue that the court’s reasoning requires that result”);
see also id. at 2 (“court’s reasoning may require the
EPA to mandate” retrofits). But until the admin-
istrative process is complete, predictions about what
EPA may do, or what others may argue it should do, do
not justify this Court’s intervention.*
Moreover, although predicting what EPA might
ultimately include in a revised Phase II Rule is
speculative, the BTA option EPA rejected on the basis
of what appeared to the court of appeals to »nclude
improper considerations would not have established a
flow limit based on closed-cycle cooling for all facilities,
but only for the 51 largest plants (less than ten percent
of those covered by th® rule) located “on sensitive
waterbodies.” Riverkeeper II App. 29a; 67 Fed. Reg. at
‘If any permits are issued on a case-by-case basis while EPA
is reconsidering the rule, permittees and other interested parties
will have ample opportunities to challenge any permit provisions
they consider to be improperly based on the “implications” of the
Second Circuit's opinion.
13
17,156-58. EPA concluded that adverse economic and
environmental effects of this alternative would be
minimal and compliance costs low. Id.
Further, that EPA may base its BTA determination
on a particular technology does not mean that all
facilities will necessarily install that technology and
incur the associated costs. For example, the Phase I
Rule included both a second compliance track and a
variance provision applicable if compliance would
impose excessive costs or involve other adverse
impacts. 40 C.F.R. §§ 125.84(d)(1), 125.86(c)(2),
125.85. Both alternative compliance provisions were
upheld by the Second Circuit. Riverkeeper I, 358 F.3d
at 187-89, 192-94.
PSEG’s claim that the decision below “blithely
accepts the bankruptcy or closure of numerous
electricity generating facilities, without considering
impacts to the U.S. electric supply,” PSEG Pet. 34
(emphasis added), and numerous other similar claims
regarding the court’s alleged indifference to economic
and technological burdens, facility closures, or energy
impacts, are simply incorrect. As in Riverkeeper I, in
the decision below the court recognized that a
technology is not “available” unless its costs can be
reasonably borne by the industry. Riverkeeper II, App.
21a; Riverkeeper I, 358 F.3d at 195. Cost-effectiveness
may also be considered. Riverkeeper II, App. 23a.
Moreover, the Second Circuit stated that other
“permissible considerations” include “energy efficiency
and production concerns.” Riverkeeper II, App. 24a
n.12 (citing Riverkeeper I, 358 F.3d at 195-96).
Accordingly, EPA will, no doubt, consider economics,
facility closures, and any energy impacts on remand,
14
and if the agency does not do so to petitioners’ liking,
they will surely challenge its decision once it is final.
Similarly unwarranted are the assertions by
petitioners and amici that the decision below “will
significantly affect our Nation’s environmental
priorities” by increasing fossil fuel consumption with
its associated air pollution and greenhouse gases. See,
e.g., PSEG Pet. 32, 35; UWAG Pet. 38-39; NEI Amicus
Br. 18-20. As petitioner UWAG admits, the decision
below “acknowledges EPA’s right to consider” such
environmental effects. UWAG Pet. at 39. Again, EPA
will doubtlessly consider them on remand, and if it
does not, petitioners will surely challenge the revised
rule on that basis.
Also unavailing are petitioners’ claims of absurd
results, such as the expenditure of billions of dollars to
save “a single fish larvae.” Entergy Pet. 3, 4; see also
CWISC Amicus at 6 (“one additional fish”). To the
contrary, the Phase II Rule applies only to facilities
withdrawing large volumes of water, at least 50
million gallons per day, and, as EPA found, these large
power plants kill aquatic organisms in enormous
numbers. See supra at 2. Unless and until the course
of actual rulemaking substantiates petitioners’
purported fear that the agency will require extreme
measures to save a single fish, their hyperbole
provides no basis for review.
In short, even if petitioners’ legal positions were
arguably meritorious, which they are not, now is not
the time for the Court to address them, particularly in
light of the federal government’s determination not to
seek certiorari despite EPA’s strong disagreement with
aspects of the Second Circuit’s ruling.
15
II. THERE IS NO CIRCUIT SPLIT
There are no conflicts among the circuits over the
issues decided by the court of appeals. The absence of
conflict is hardly surprising because section 316(b) is
a singular provision rarely before construed, in part
because of EPA’s lengthy failure to promulgate cooling
water intake standards. Indeed, until the Second
Circuit’s 2004 decision in Riverkeeper I, no court ever
had occasion to review the substance of a section
316(b) regulation. Although Congress enacted section
316(b) in 1972, the only regulations EPA issued under
that section — before its current, three-part rulemaking
— were the 1976 regulations remanded by the Fourth
Circuit on purely procedural grounds. Appalachian
Power Co. v. Train, 566 F.2d 451, 457 (4th Cir. 1977).
Only two other court of appeals decisions have
construed section 316(b), both in the 1970s and in the
context of permits issued by EPA on a case-by-case
basis in the absence of national regulations. U.S. Steel
Corp. v. Train, 556 F.2d 822 (7th Cir. 1977); Seacoast
Anti-Pollution League v. Costle, 597 F.2d 306 (1st Cir.
1979).
Riverkeeper II is perfectly consistent with the very
limited section 316(b) authority that preceded it —
Riverkeeper I and the two 1970s permitting cases.
There is no reason to abandon this Court’s usual
practice of awaiting a conflict among the circuits
before accepting review. As petitioners themselves
note, in reviewing EPA’s Phase III rule the Fifth
Circuit is currently considering “precisely the same
issue” that the Second Circuit decided below as to
whether EPA may rely on cost-benefit considerations
under section 316(b). UWAG Pet. 18. If the Fifth
16
Circuit disagrees with the Second, and a conflict does
materialize, there will be ample opportunity for EPA,
petitioners, or any party aggrieved by either circuit’s
decision to seek this Court’s review. Not only could
Riverkeeper or the other environmental petitioners in
the Phase III case file a petition for a writ of certiorari
to the Fifth Circuit, but, in addition, once the Second
Circuit reviews the revised Phase II Rule that EPA
will issue on remand, any aggrieved parties could file
a new petition for certiorari (assuming they were in
fact injured by features of the revised rule attributable
to the court’s holding that the statute does not permit
cost-benefit analysis). Review now, before a conflict
has arisen, is unwarranted and unnecessary.
A. Cost Considerations
1. The decision below does not conflict with the
First Circuit’s 1979 decision in Seacoast. There, in
approving a permit for New Hampshire’s Seabrook
power plant, the court did not hold that EPA may base
section 316(b) determinations on _ cost-benefit
considerations. 597 F.2d at 311. Indeed, in the single
paragraph of the opinion that discussed costs, that
court did not even consider that issue, nor was it asked
to. Rather, noting that petitioners’ challenge was “not
a model of clarity” and understanding them only to
“suggest that cost of delay is an improper
consideration,” the First Circuit denied their claim
(without deciding whether considering such costs
would be improper) because it was based on a
misreading of the record. Jd. (“Apparently petitioners
read the cost figure ... as including the estimated costs
of delay and reengineering as well as additional
17
tunnelling. ... The record is clear, however, that $20
million is the cost of the tunnelling alone.”).
The First Circuit explicitly stated that the Seacoast
petitioners “d[id] not argue that the cost may not be
considered.” Jd. (emphasis added). The court’s
observation that “cost” — not cost-benefit analysis —
“[is] an acceptable consideration in determining
whether the intake design ‘reflect(s) the best
technology available,” id., is fully consistent with
Riverkeeper I and Riverkeeper II, which found both
economic availability and cost-effectiveness to be
proper considerations. Indeed, we readily acknow-
ledge that consideration of compliance costs (as
opposed to cost-benefit analysis) is proper under
section 316(b).
To be sure, the First Circuit also noted that the
EPA “Administrator decided that moving the intake
further offshore might further minimize _ the
entrainment of some plankton, but only slightly, and
that the costs would be ‘wholly disproportionate to any
environmental benefit.” Jd. But that decision was
apparently based on cost-effectiveness (because the two
intake locations had essentially the same benefit),
rather than cost-benefit. See Riverkeeper II, App. 20a-
21a (comparing the two types of analyses). Certainly,
nothing in the First Circuit’s opinion addresses the
distinction drawn below between cost-effectiveness and
cost-benefit analysis, let alone sets forth a holding on
the point that conflicts with the Second Circuit’s.
Thus, contrary to PSEQG’s argument, it is not at all
“clear [that] the First Circuit would have decided this
case differently.” PSEG at 25.
18
2. Nor are there any other conflicting appellate
decisions.” PSEG’s speculation that “the Sixth and
D.C. Circuits ... would have decided this case
differently,” PSEG Pet. 21, is unfounded because those
circuits have never construed section 316(b). The host
of cases PSEG and the other petitioners cite construed
the language of other sections of the Clean Water Act,
such as sections 301, 304 and 306, or other environ-
mental laws entirely. See PSEG Pet. 19-21; UWAG
Pet. 27-28; Entergy Pet. 31-33. Thus, none of them is,
or could be, in direct conflict because the heart of this
case is section 316(b)’s distinctive text.
As petitioners themselves recognize, section
316(b)’s standard is “unique,” PSEG Pet. 11; see also
Entergy Pet. 4, and, as the Second Circuit has ex-
plained, “cooling water intake structures are suorum
generum.” Riverkeeper I, 358 F.3d at 186. That the
court of appeals looked for “guidance” to other courts’
interpretations of other CWA provisions, and observed
that they support its construction of 316(b), does not
* This Court need not consider UWAG’s citation to a single
sentence of dicta from United States Steel v. Train, 556 F.2d 822
(7th Cir. 1977), UWAG Pet. 21, because UWAG itself concedes
there is no actual conflict with the Seventh Circuit on this point.
See id. at 19 (arguing that First Circuit is “only other circuit that
has decided the § 316(b) issue presented here”). In fact, U.S. Steel
rejected, as premature, the argument that EPA must do a cost-
benefit analysis, and it is unclear from the dicta UWAG cites to
what extent that court’s expectation of how EPA would take costs
into account would differ from the cost-effectiveness analysis that
the Second Circuit's decision permits. 556 F.2d at 850.
19
establish a conflict.° Thus, there is no merit to
petitioners’ and amici’s claims that the decision below
should be reviewed because it “may also sweep far
broader than §316(b)” and affect other CWA provisions
or other laws, or “invite[ ] a rash of challenges to
NPDES permits.” PSEG Pet. 36; see also Entergy Pet.
31; CWISC Amicus Br. 16-17. In short, the Second
Circuit interpreted only section 316(b) and did not
purport to issue holdings concerning any other
statutes.
PSEG’s claim that “until this case, no court has
ever held that EPA is prohibited from considering costs
in relation to benefits,” PSEG Pet. 20, merely reflects
the fact that, before appearing to do so in promul-
gating its Phase II Rule, EPA never relied on cost-
benefit analysis in promulgating BTA standards for
® Petitioners’ attempt to manufacture a conflict is also based
on their incorrect suggestion that EPA may rely on cost-benefit
analysis in establishing effluent limitations based on “best
available technology” (“BAT”) under sections 301 and 304. Their
argument is irreconcilable with the language of the statute, 33
U.S.C. §§ 1311(bX 2A), 1314(b)(2)(B), and with EPA v. National
Crushed Stone Ass’n, 449 U.S. 64 (1980), which recognized that “in
assessing BAT total cost is no longer to be considered in
comparison to effluent reduction benefits.” Jd. at 71. Petitioners
also mischaracterize Weyerhaeuser Co. v. Costle, 590 F.2d 1011
(D.C. Cir. 1978) and BP Exploration & Oil, Inc. v. EPA, 66 F.3d
784 (6th Cir. 1995). In neither case had EPA used cost-benefit
analysis to establish BAT, and thus neither court held such
analysis proper. Rather, the Sixth Circuit decision cited the
earlier D.C. Circuit decision, which was discussing the 1977 “best
practicable control technology,” or “BPT,” standards, not the 1983
BAT standards. Id. at 796 (citing Weyerhaeuser, 590 F.2d at
1045).
20
intake structures under section 316(b) (or, for that
matter, in promulgating BAT effluent limitations
under sections 301 and 304). Petitioners acknowledge,
as they must, that “numerous circuits have recognized
that EPA is not required to consider costs and benefits
when setting BAT,” PSEG Pet. 20, but fail to identify
any case where EPA did use cost-benefit analysis to
set such standards, let alone a case where such a
decision was upheld in court.
Finally, PSEG’s argument that the decision below
is “hard to reconcile” with Riverkeeper I not only fails
to provide a basis for granting certiorari (after all, the
Second Circuit is responsible for maintaining consis-
tency of its own precedents, and no judge of that court
favored rehearing en banc), but also relies on the
mistaken contention that EPA’s rejection of dry-cooling
technology in its Phase I Rule was supported by “cost-
benefit considerations.” PSEG Pet. 21 n.2. In fact, the
preamble to the Phase I Rule makes clear that “EPA
has not selected the best technology available on a
cost-benefit basis,” and that EPA instead based that
Phase I decision on “cost-effectiveness.” 66 Fed. Reg.
at 65,284, 65,309. EPA’s reliance on cost-effectiveness
in Phase I also rebuts Entergy’s assertion that the
court of appeals “made up” a “novel ‘cost-effectiveness’
test” in Riverkeeper II. Entergy Pet. at 25, 11.
B. Restoration Measures
In Riverkeeper I, the Second Circuit remanded the
Phase I Rule’s “restoration measures” provision as
“plainly inconsistent with the statute’s text and
Congress’s intent in passing the 1972 amendments,”
358 F.3d at 189, and no party sought this Court’s
review of that decision. In the decision below, a
21
different panel reaffirmed that holding and remanded
the Phase IT Rule’s nearly identical provision, stating:
“our holding in Riverkeeper I was and remains clear:
restoration measures contradict the unambiguous
language of section 316(b).” App. 43a. The court’s
straightforward application of section 316(b) to the
regulations at issue does not conflict with any other
decision and does not warrant this Court’s review.
Other than the Riverkeeper I and Riverkeeper II
decisions, no court of appeals has ever had occasion to
consider the issue of restoration under section 316(b).
The First Circuit’s 1979 Seacoast decision had nothing
to do with restoration measures, which were not at
issue in that case. Nor was the First Circuit there
asked to consider whether “adverse environmental
impact” under section 316(b) should be defined with
respect to fish populations, individual fish, or both.
While the court generally discussed the New
Hampshire power plant’s effect on individual fish as
well as populations, 597 F.2d at 309-11, that discuss-
ion has no bearing on how that court would have
viewed restoration measures.’ Seacoast thus is
manifestly not in conflict. Moreover, the rest of the
decisions petitioners cite did not consider section
316(b) at all, but involved completely different
statutes. See PSEG Pet. 30-31 (citing cases under the
National Environmental Policy Act, among others);
UWAG Pet. 34-36 (same).
’ Population effects were clearly relevant in that case under
CWA section 316(a), 33 U.S.C. § 1326(a), which sets forth a very
different standard than section 316(b), see Riverkeeper 11, App.
53a & n.27 (explaining that “wildlife levels” can be considered
under section 316(a), not section 316(b)).
22
C. Existing Facilities
Entergy alone contends that section 316(b) excludes
existing facilities, but fails to offer even a plausible
rationale for this Court’s review of that issue. No
court of appeals ~— and, indeed, to respondents’
knowledge, no federal or state tribunal or agency at
any level — has ever concluded that section 316(b)
applies only to new facilities. Five years after the
CWA was enacted, the Seventh Circuit upheld a
NPDES permit imposing section 316(b) requirements
on an existing facility. U.S. Steel Corp. v. Train, 556
F.2d 822, 850 (7th Cir. 1977) (holding that EPA’s
construction of section 316(b) “to apply to ali point
sources ... comports with its plain meaning”)
(emphasis added). That holding has stood for over 30
years and Entergy does not cite any decisional
authority that even suggests that the law is or should
be otherwise, despite EPA’s consistent application of
section 316(b) to existing facilities over the last 35
years.
As Entergy acknowledges, see Entergy Pet. 20 &
n.4, United States Steel not only held section 316(b)
applicable to existing facilities, but also expressly
affirmed EPA’s authority to use NPDES permits to
impose section 316(b) requirements. 556 F.2d at 850.
Of the two decisions Entergy contends are in conflict
on that point, neither even hinted that NPDES
permits could not be so used. In Virginia Electric &
Power Co. v. Costle “VEPC@”), 566 F.2d 446 (4th Cir.
1977), the Fourth Circuit held only that original
jurisdiction to review EPA’s section 316(b) regulations
lies in the court of appeals. Jd. at 447. The Fourth
Circuit’s statement that section 316(b) regulations are
23
“other limitations” under sections 301 and 306, 566
F.2d at 450, accords with the decision below because
NPDES permits include both effluent limitations and
other limitations.
The other case Entergy cites, Natural Resources
Defense Council v. EPA, 859 F.2d 156 (D.C. Cir. 1988),
had nothing to do with section 316(b). There, the court
held that EPA may not use NPDES permits to
implement an entirely different statute, the National
Environmental Policy Act (“NEPA”). Id. at 169. The
court did not imply that NPDES permits may not be
conditioned on compliance with relevant requirements
of the CWA itself.
Finally, Entergy’s additional request that this
Court grant certiorari to resolve a claimed conflict over
whether Chevron deference should be accorded
agencies’ interpretation of their own jurisdiction,
Entergy Pet. 22-25, does not warrant serious consider-
ation. Entergy did not raise this issue (or even
characterize EPA’s determination as “jurisdictional”)
below® and cannot now raise it here. See Clingman v.
Beaver, 544 U.S. 581, 598 (2005) (“We ordinarily do not
consider claims neither raised nor decided below.”).
Further, the court of appeals did not simply defer to
EPA’s interpretation on this point; it based its decision
on Chevron step one, holding “that section 316(b), on
its face, applies to existing facilities” and “Congress
intended the requirements of section 316(b) to apply in
® See Brief of Petitioner Entergy Corp., July 5, 2005, at 14-35
in Riverkeeper II, Dkt. No, 04-6692-ag(L). Moreover, none of the
other parties briefed the issue and the court of appeals did not
discuss it sua sponte.
24
tandem with the effluent limitations established
pursuant to sections 301 and 306.” Riverkeeper II,
App. 68a, 70a. The court’s reference to Chevron step
two was merely an alternative holding. Id. at 65a
(“[A]t the very least, the EPA permissibly interpreted
the statute...”). It is hard to imagine a case more
poorly suited for review of the jurisdictional deference
issue than this one, where the issue was not developed
below and is not outcome-determinative.
Il THE DECISION BELOW IS CORRECT
A. Cost Considerations
Correctly employing traditional tools of statutory
construction established by this Court, the Second
Circuit based its conclusion that cost-benefit analysis
would be inappropriate under section 316(b) on the
plain meaning of the statutory text. By requiring in
section 316(b) the “best technology available for
minimizing adverse environmental impact” (emphasis
added), Congress directed EPA to mandate the most
protective technology feasible. The court thus recog-
nized that section 316(b) leaves no room for weighing
of costs and benefits: “the language of section 316(b)
itself plainly indicates that facilities must adopt the
best technology available and that cost-benefit analysis
cannot be justified in light of Congress’s directive.”
Riverkeeper II, App. 21a.
Put another way, “the statute therefore precludes
cost-benefit analysis because ‘Congress itself defined
the basic relationship between costs and benefits.” Jd.
at 22a (quoting Am. Textile Mfrs. Inst., Inc. v.
Donovan, 452 U.S. 490, 509, (1981)). The Second
Circuit’s reading of the statute to exclude cost-benefit
25
analysis is fully consistent with this Court’s decision in
American Textile Manufacturers excluding cost-benefit
considerations under the Occupational Safety and
Heaith Act, as well as Whitman v. American Trucking
Ass’ns, 531 U.S. 457 (2001), where cost considerations
were precluded by the “most natural of readings” of the
Clean Air Act provision at issue there. Jd. at 465.
Petitioners mistakenly criticize the Second Circuit’s
reliance on American Textile, arguing that that “every
court of appeals that has addressed American Textile’s
impact on cost-benefit analysis has held that the case
is limited to whether cost-benefit analysis is required
by statute.” PSEG Pet. 26 (citing cases); see also
UWAG Pet. 24-25; Entergy Pet. 33-34. On the
contrary, the Fifth Circuit has recognized that the
“rather broad holding” of that case “rejected any
implication of cost-benefit analysis.” Am. Petroleum
Inst. v. EPA, 661 F.2d 340, 355 n.36 (5th Cir. 1981)
(emphasis added). As this Court observed in American
Textile, imposing a cost-benefit criterion onto a statute
meant to be governed by feasibility would be
“inconsistent” with the balance struck by Congress and
“would eviscerate” the congressional scheme. 452 U.S.
at 509, 513.9
The court of appeals was also correct to attach
significance to Congress’s failure to authorize cost-
benefit analysis expressly in section 316(b), in contrast
* Entergy disparages American Textile as a “pre-Chevron
decision.” Entergy Pet. 12. In fact, American Textile is a textbook
example of what later came to be called step one of Chevron; it
employed traditional tools of statutory analysis to discern the
intent of Congress.
26
to other environmental statutes — and, in particular,
other sections of the CWA — that explicitly call for cost-
benefit balancing.’*° Because Congress has repeatedly
demonstrated that it knows how to authorize cost-
benefit considerations when it so chooses, the absence
of any such authority in section 316(b) is evidence that
it did not intend such considerations to govern here.
“When Congress has intended that an agency engage
in cost-benefit analysis, it has clearly indicated such
intent on the face of the statute.” Am. Textile, 452
U.S. at 510; see also Whitman, 531 U.S. at 467 (“We
have therefore refused to find implicit in ambiguous
sections of the CAA an authorization to consider costs
that has elsewhere, and so often, been expressly
granted.”).
In giving weight to Congress’s conspicuous failure
to authorize cost-benefit analysis in section 316(b), the
Second Circuit did not, as PSEG asserts, hand down a
“new clear statement rule barring cost-benefit analysis
whenever a statute is silent on the issue.” PSEG Pet.
36. Rather, the court merely quoted this Court’s own
observation in American Textile about the significance
of Congress’s failure to authorize cost-benefit analysis
explicitly. See Riverkeeper II, App. 22a-23a (quoting
Am. Textile, 452 F.3d at 510). <A lower court’s
quotation from one of this Court’s decisions provides
no basis for review by the Court.
© See, e.g., 33 U.S.C. §§ 1312(b\2A), 1314(b)(1)(B),
1314(bX4B). Other statutes expressly authorizing cost-benefit
analysis include the Safe Drinking Water Act, 42 U.S.C. § 300g-
1(bM3KCXiXMIV), the fuel additive provision of the Clean Air Act,
42 U.S.C. § 7545(cK2)(B), the Outer Continental Shelf Lands Act,
43 U.S.C. § 1347(b), and the Flood Control Act, 33 U.S.C. § 701a.
27
B. Restoration Measures
With respect to restoration, the court of appeals
construed the specific language of section 316(b),
including the statutory mandates that EPA regulate
(1) the “location, design, construction, and capacity of
cooling water intake structures” (2) to “minimiz[e)”
their “adverse environmental impact,” and found that
EPA’s restoration provision contradicted the statute in
both respects. Off-site ecological improvement activi-
ties “have nothing to do with the location, design,
construction, or capacity of cooling water intake
structures.” App. 41a (quoting Riverkeeper I, 358
F.3d at 189). Moreover, attempts to “correct for the
adverse environmental impacts of impingement and
entrainment ... do not minimize those impacts in the
first place.” Id.
The court of appeals recognized that “a rule
permitting compliance with the statute through
restoration measures allows facilities to avoid adopting
any cooling water intake structure technology at all, in
contravention of the Act’s clear language as well as its
technology-forcing principle.” App. 44a; see also
Riverkeeper I, 358 F.3d at 190 (referring to “Congress’s
intent that the ‘design’ of intake structures be
‘' Petitioners argue that barrier nets and closed-cycle cooling
systems are no more a part of the “location,” “design,”
“construction,” or “capacity” of intake structures than restoration
measures. PSEG Pet. 30; UWAC Pet. 31-32. In fact, barrier nets
are part of the “design” of the intake because they are placed in
front of it to exclude fish. Similarly, a requirement, such as EPA’s
Phase I Rule, that intakes be designed to withdraw no :nore water
than a closed-cycle system, clearly regulates the “design” and
“capacity” of an intake structure.
28
regulated directly, based on the best technology
available”).
Petitioners argue that the word “reflect” in section
316(b) authorizes EPA to require no protective tech-
nology at intake structures if off-site ecological
improvement activities are successful. PSEG Pet. 30.
But if Congress had so intended it would not have
needed to use the words “location, design, construction,
and capacity of cooling water intake structures” at all.
It could have simply directed EPA to ensure suitable
populations of fish. Instead, consistent with the
principle that technology standards regulate pollution
at its source, Congress mandated best technology for
four specific aspects of cooling water intake structures.
Of course, “[s]tatutes must be interpreted, if possible,
to give each word some operative effect.” Walters v.
Metro. Educ. Enters., Inc., 519 U.S. 202, 209 (1997).
In addition, as the court observed in Riverkeeper I,
“EPA’s own findings reveal that restoration measures
are inconsistent with Congress’s intent.” 358 F.3d at
190. Since at least 1977, EPA has consistently defined
“adverse environmental impact” under section 316(b)
to include impingement and entrainment. In the
Phase II rulemaking, as in Phases I and III, EPA
“interpret[ed] adverse environmental impact as the
loss of aquatic organisms due to impingement and
entrainment.” 69 Fed. Reg at 41,612; see also 69 Fed.
Reg. 68,443, 68,473 (Nov. 24, 2004). Restoration
measures contradict EPA’s determination because they
do not minimize or even limit “how many organisms a
facility entrains or impinges.” 358 F.3d at 189.
Restoration measures therefore cannot satisfy section
29
316(b)’s command to “minimizele] adverse environ-
mental impact.”
Petitioners also vastly overstate the prior use of
restoration measures by power plants. In the briefing
below, industry was able to offer examples of only six
of more than 500 existing power plants that had ever
used restoration measures to compensate for fish kills,
and none of the cited permits allowed restoration as a
complete substitute for available intake structure
technology. Instead, restoration measures have only
been allowed as a partial, supplemental measure or
under regulatory authority other than section 316(b).””
Cc. Existing Facilities
As the court of appeals recognized, “section 316(b),
on its face, applies to existing facilities” and “the cross-
reference in section 316(b) to section 301 provides a
clear textual basis for that conclusion.” Riverkeeper II,
App. 68a-69a. Section 316(b) commands that “la]ny
standard” promulgated by EPA for point sources under
CWA section 301 “shall require” BTA for cooling water
intake structures. 33 U.S.C. § 1326(b). The
“standards” promulgated under section 301 are the
discharge standards for existing point sources. E.J. du
Pont de Nemours & Co. v. Train, 430 U.S. 112, 121
(1977) (“Section 301(b) defines the effluent limitations
that shall be achieved by existing point sources....”)
(emphasis added); see also Entergy Pet. 5 (Section
'? For example, the permitting agency clearly stated that the
restoration measures undertaken by PSEG at the Salem nuclear
plant, see PSEG Pet. 4-5, were not utilized to fulfill BTA
requirements under section 316(b). Joint Appendix 254.
30
301(e) requires EPA to establish limitations applicable
to “all point sources’ ... whether existing or new”).
The court of appeals also correctly found that by
applying section 316(b) to four particular aspects of
cooling water intake structures — their “location,
design, construction, and capacity” — Congress did not
signal an intention to exclude existing facilities, as an
existing facility's intake location, design, construction
and capacity can be regulated just as readily as a new
facility's. Riverkeeper II, App. 67a-68a & n.32. If
Congress had wanted to limit section 316(b)’s
application to new facilities, it could have done so
expressly, “which would have been a simple task to
do.” Id. at 68a.
Finally, the Second Circuit properly rejected
Entergy’s back-up argument that CWA section 402
does not authorize EPA to use NPDES permits to
impose section 316(b) requirements. Section 316(b)
states that standards applicable to point sources under
sections 301 and 306 shall include BTA requirements
for cooling-water intakes, and section 402(a)(1)(A), 33
U.S.C. § 1342(a)(1)(A), in turn provides that NPDES
permits shall require compliance with “all applicable
requirements under sections [301 and 306]” (emphasis
added). See Riverkeeper II, App. 68a-69a. The statute
thus provides ample authority for EPA to incorporate
the BTA requirements into NPDES permits, and
Entergy’s contrary argument would render section
316(b) meaningless by depriving EPA of a mechanism
for imposing its requirements.
CONCLUSION
The petitions for writ of certiorari should be denied.
31
Respectfully submitted,
P. KENT CORRELL REED W. SUPER
300 Park Avenue, Counsel of Record
17th Floor LAW OFFICE OF REED W. SUPER
New York, NY 10022 116 John Street, Suite 3100
(212) 475-3070 New York, NY 10038
(212) 791-1881
Counsel for Respondents Riverkeeper, Inc., et al.
February 29, 2008
This is a copy of a public record, reproduced as it was published. It is not legal advice, and it may not be the version a court would rely on. Check the official source before you cite it.