Respondents Brief — Alaska Dept. of Environmental Conservation v. EPA
Supreme Court brief2004
Ask Donna
What actually matters in this document.
Text
JUL | 6 208
No. 02-658
In the Supreme Court of the United States
ALASKA DEPARTMENT OF ENVIRONMENTAL
CONSERVATION, PETITIONER
U.
ENVIRONMENTAL PROTECTION AGENCY, ET AL.
ON WRIT OF CERTIORARI
TO THE UNITED STATES COURT OF APPEALS
FOR THE NINTH CIRCUIT
BRIEF FOR RESPONDENTS
THEODORE B. OLSON
Solicitor General
Counsel of Record
KELLY A. JOHNSON
Acting Assistant Attorney
General
EDWIN S. KNEEDLER
Deputy Solicitor General
ROBERT E. FABRICANT
General Counsel
CAROL S. HOLMES
JULIANE R.B. MATTHEWS
Attorneys
Environmental Protection JAMES A. FELDMAN
Agency Assistant to the Solicitor
Washington, D.C. 20460 General
ANDREW J. DOYLE
Attorney
Department of Justice
Washington, D.C. 20530-0001
(202) 514-2217
QUESTIONS PRESENTED
1. Whether the court of appeals had jurisdiction over this
pre-enforcement challenge to the Environmental Protection
Agency’s administrative orders.
2, Whether, if the Environmental Protection Agency
(EPA) finds that a state permitting authority has not made a
reasonable determination of the best available control tech-
nology as required by Section 165 of the Clean Air Act, 42
U.S.C. 7475(a)(4), the EPA has authority under Sections
113(a)(5) and 167 of the Act, 42 U.S.C. 7413(a)(5) and 7477, to
issue a finding of noncompliance and administrative orders
to prevent construction of a major emitting source.
(I)
TABLE OF CONTENTS
The court of appeals had jurisdiction in this
The Clean Air Act authorizes EPA to issue a stop-
construction order if a States PSD permit is
based on an arbitrary or unreasoned determina-
A. Under the plain language of Sections 113(a)(5)
and 167, EPA has authority to prevent con-
struction of a facility under a permit that does
not comply with requirements of the Clean
——¼dn——
. A permitting authority that has not reasonably
determined the maximum degree of reduction
in pollution achievable for a facility has not
complied with the Act’s BACT requirement
. Petitioner’s remaining arguments that a
BACT determination is an entirely subjective
or discretionary decision that is not subject to
review are mistaken
D. The Court should defer to EPA's interpreta-
tion that it is a “requirement” of the Clean
Air Act that States make reasonable BACT
determinations
(IID)
uuu’
12
16
21
IV
TABLE OF CONTENTS—Continued: Page
III. The court of appeals correctly sustained EPA's
conclusion that petitioner made an unreasonable
BACT determination 44
Conclusion 50
Appendix la
TABLE OF AUTHORITIES
Cases: Page
Air Line Pilots Ass'n v. O'Neill, 499 U.S. 65
(1991) 40
Alabama Power Co. v. Costle, 636 F.2d 323 (D.C.
Cir. 1979) 3, 29, 37
Allsteel, Inc. v. EPA, 25 F.3d 312 (6th Cir. 1994)... 17, 20, 30
Amoco Oil Co. v. EPA, 959 F. Supp. 1318 (D. Colo.
1997) 21
Arkansas v. Oklahoma, 503 U.S. 91 (1992) 33
Asbestec Constr. Servs., Inc. v. EPA, 849 F.2d 765
(2d Cir. 1988) 17
Barnhart v. Walton, 122 S. Ct. 1265 42, 43
Bennett v. Spear, 520 U.S. 154 (1997) 10, 16, 17
Cameron v. United States, 252 U.S. 450 (1920) 20
Chevron U.S.A., Inc. v. NDRC, 467 U.S. 837 (1984) — . 15, 41
Christensen v. Harris County, 529 U.S. 576
(2000) 41
Citizens for Clean Air v. EPA, 959 F 2d 839 (9th Cir.
1992) 35
Citizens to Preserve Overton Park v. Volpe, 401
U.S. 402 (1971) 24
FTC v. Standard Oil Co., 449 U.S. 232 (1980) 16
General Motors Corp. v. United States, 496 U.S.
530 (1990) 2
Gonzaga Univ. v. Doe, 536 U.S. 273 (2002) 28
„
*
Cases—Continued: Page
Good Samaritan Hosp. v. Shalala, 508 U.S. 402
(1993) 42
Harrison v. PPG Indus., Inc., 446 U.S. 578
(1980) 16, 20, 44
Heckler v. Chaney, 470 U.S. 821 (1985) 35
Hoffman Group, Inc. v. EPA, 902 F 2d 567 (7th
Cir. 1990) 21
Lezecon, Inc. v. Milberg Weiss Bershad Hynes &
Lerach, 523 U.S. 26 (1998) 45
Lloyd A. Fry Roofing Co. v. EPA, 554 F 2d 885
(8th Cir. 1977) 21
Motor Vehicle Mfrs. Ass'n v. State Farm Mut. Ins.
Co., 463 U.S. 29 (1983) 50
New York v. United States, 505 U.S. 144 (1992 38
Northern Plains Res. Council v. EPA, 645 F.2d
1349 (9th Cir. 1981) 29, 35
Pennsauken Solid Waste Mgmt. Auth., In re, 569 A.2d
826 N. J. Super. Ct. App. Div. 1990) 35
Plumbers & Steamfitters, Local 52 v. Alabama
Dep't of Envtl. Mgmt., 647 So. 2d 793 (Ala. Civ.
App. 1994) 35
Ross Incineration Servs. v. Browner, 118 F. Supp. 2d
837 (N.D. Ohio 2000) 21
Skidmore v. Swift & Co., 323 U.S. 134 (1944) 44
Solar Turbines, Inc. v. Seif, 879 F 2d 1073 (3d Cir.
1989) 18, 30
Southern Ohio Coal Co. v. Office of Surface Mining,
Reclamation & Enforcement, 20 F.3d 1418 (6th
Cir. 1994) 21
Southern Pines Assocs. v. United States, 912 F 2d
713 (4th Cir. 1990) 21
Stone v. INS, 514 U.S. 386 (1995) 32
Sur Contra La Contaminacion v. EPA, 202 F.3d
443 (Ist Cir. 2000) 35
TVA v. Whitman, No. 00-15936, 2003 WL 21452521
(11th Cir. June 24, 2003) 18, 19
Cases—Continued:
Train v. NRDC, 421 U.S. 60 (1975)
United States Dep't of Treasury v. Fabe, 508
U.S. 491 (1993)
United States v. Mead Corp., 533 U.S. 218 (2001)
United States v. Murphy Oil USA, Inc., 155
F. Supp.2d 1117 (W.D. Wis. 2001)
Vermont Yankee Nuclear Power Corp. v. NRDC,
435 U.S. 519 (1978)
Whitman v. American Trucking Ass us, 531 U.S.
457 (2001)
Wilder v. Virginia Hosp. Ass'n, 496 U.S. 498
(1990)
U.S. Const., Due Process Clause, Amend. V
Administrative Procedure Act 5 U.S.C. 551 et seg
5 U.S.C. 701(aX1)
5 U.S. C. 701(aX2)
Clean Air Act, 42 U.S.C. §§ 7401 et seg.
§ 160-169, 42 U.S.C. 7470-7492
107(a), 42 U.S.C. 7407(a)
110, 42 U.S.C. 7410
Loa DD, U.S.C. 7410(aX2) (DiX1D)........
1104), 42 U.S.C. 74100
111(aX(4), 42 U.S.C. 7411
113(aX(5), 42 U.S.C. 74145)
113(b), 42 U.S.C. 7413(b)
113(b)(2), 42 U.S.C. 74130)
113(c), 42 U.S.C. 7413(c)
160(3), 42 U.S.C. 7470(3)
160(4), 42 U.S.C. 7470(4)
161, 42 U.S.C. 7471
163, 42 U.S.C. 7473
165, 42 U.S.C. 7475
165(aX(1), 42 U.S.C. 7475(a\(1)
165(a)(3), 42 U.S.C. 7475(aX3)
17
Vil
Statutes and regulation—Continued:
§ 165(aX4), 42 U.S.C. 7475(aX4) 3, 13, 23, 36
§ 165(aX8), 42 U.S.C. 7475(aX8)
§ 165(dX1), 42 U.S.C. 7475(dX(1)
§ 167, 42 U.S.C. 7477
§ 16%1), 42 U.S.C. 74791)
§ 16%3), 42 U.S.C. 747943)
§ 307(b\(1), 42 U.S.C. 7607(b\1)
§ 307(b\2), 42 U.S.C. 7607(b\2)
$§ 501-507, 42 U.S.C. 7661-7661f
Clean Water Act, 33 U.S.C. 1251 et seg.
Comprehensive Environmental Response, Compen-
sation, and Liability Act, 42 U.S.C. 9601 et seg. ...............
Resource Conservation and Recovery Act, 42
U.S.C. 6901 et seq.
18 U.S.C. 3661
42 U.S.C. 1983
40 C. F. R. 51.168
Miscellaneous:
EPA, New Source Review Workshop Manual
(Draft 1990)
57 Fed. Reg. 28,095 (1992)
58 Fed. Reg. 10,961 (1993)
63 Fed. Reg. 13,796 (1998)
65 Fed. Reg. 35,430 (2000)
H.R. Conf. Rep. No. 564, 95th Cong., Ist Sess.
(1977)
H.R. Rep. No. 294, 95th Cong., Ist Sess. (1977
H.R. Rep. No. 490, 101st Cong., 2d Sess. Pt. 1 (1990) ........
S. Rep. No. 127, 95th Cong., Ist Sess. (1977)
United States Sentencing Guidelines § 1B1.4
„ 2
In the Supreme Court of the United States
No. 02-658
ALASKA DEPARTMENT OF ENVIRONMENTAL
CONSERVATION, PETITIONER
V.
ENVIRONMENTAL PROTECTION AGENCY, ET AL.
ON WRIT OF CERTIORARI
TO THE UNITED STATES COURT OF APPEALS
FOR THE NINTH CIRCUIT
BRIEF FOR RESPONDENTS
OPINIONS BELOW
The opinion of the court of appeals (Pet. App. la-16a) is
reported at 298 F.3d 814. A prior order of the court of ap-
peals addressing its subject matter jurisdiction (Pet. App.
17a-23a) is reported at 244 F.3d 748.
JURISDICTION
The judgment of the court of appeals was entered on July
30, 2002. The petition for a writ of certiorari was filed on Oc-
tober 25, 2002, and was granted on February 24, 2003. This
Court’s jurisdiction is invoked under 28 U.S.C. 1254(1).
STATUTORY PROVISIONS INVOLVED
Pertinent statutory and regulatory provisions are set
forth at App., infra, la-18a.
(1)
2
STATEMENT
1. Under the Clean Air Act, “the States and the Federal
Government [are] partners in the struggle against air pollu-
tion.” General Motors Corp. v. United States, 496 U.S. 530,
532 (1990). The Environmental Protection Agency (EPA),
for example, establishes national ambient air quality stan-
dards (NAAQS) for certain air pollutants, and States play a
“statutory role as primary implementers of the NAAQS.”
Whitman v. American Trucking Ass’ns, 531 U.S. 457, 470
(2001); see 42 U.S.C. 7408, 7409. Each State must draft and
submit to EPA for approval a state implementation plan
(SIP) that, inter alia, provides for the attainment and main-
tenance of the NAAQS. See 42 U.S.C. 7407(a), 7410; see
Train v. NRDC, 421 U.S. 60, 93-94 n.28 (1975).
This case involves particular provisions of the Act appli-
cable to construction of major facilities in areas that are
designated as “attainment” or “unclassifiable,” i. e., areas of
the country—such as much of Alaska—where the NAAQS
for a given pollutant are satisfied or for which insufficient
data exist to know whether they have been satisfied. See
Pet. App. 3a. The key goal of the Act in such areas is to pre-
serve existing air quality, and a State’s SIP therefore must
“contain emission limitations and such other measures as
may be necessary * * * to prevent significant deterioration
of air quality” in those areas. 42 U.S.C. 7471; see 42 U.S.C.
7410(a)(2)(D)(i)(II). Under the Act’s prevention-of-signifi-
cant-deterioration—or PSD—program, no “major emitting
facility“ —i. e., no facility that would emit substantial quanti-
ties of pollutants, see 42 U.S.C. 7479(1)—may be constructed
in a clean air area unless it satisfies certain statutory re-
quirements. 42 U.S.C. 7475.
Before such a facility may be constructed, its operator
must secure a PSD permit “setting forth emission limitations
for such facility which conform to the requirements” of the
Act. 42 U.S.C. 7475(a)(1). One substantive requirement that
—— m
— — — —
- — — — — —L—ͤ — =
3
must be reflected in the PSD permit is that the new facility
must not “cause, or contribute to * * * air pollution” in ex-
cess of certain “maximum allowable increase[s]”—or incre-
ments—in the levels of particular pollutants in clean air ar-
eas. 42 U.S.C. 7475(a)(3) (permit requirement), 7473 (defini-
tion of increment). Another requirement is that the facility
must not cause or contribute to air pollution exceeding any
NAAQS or other “applicable emission standard or standard
of performance” under the Act. 42 U.S.C. 7475(a)(3).
To prevent significant deterioration of air quality in a
clean air area, a facility also may not “be constructed * * *
unless * * * the proposed facility is subject to the best
available control technology [BACT] for each pollutant sub-
ject to regulation under [the Act] emitted from, or which re-
sults from, such facility.” 42 U.S.C. 7475(a)(4); see Alabama
Power Co. v. Costle, 636 F.2d 823, 407 (D.C. Cir. 1979).
BACT is defined under the Act, in pertinent part, as
an emission limitation based on the maximunr degree of
reduction of each pollutant * * * emitted from * *
any major emitting facility, which the permitting
authority, on a case-by-case basis, taking into account
energy, environmental, and economic impacts and other
costs, determines is achievable for such facility.
42 U.S.C. 7479(3). Thus, BACT is an “emission limitation”
that must be “based on the maximum degree of reduction
* * * achievable” for the facility, as determined by the
permitting agency and taking into account the specified fac-
tors.
In determining what is BACT for a given source, permit-
ting authorities commonly follow the “top-down” approach.
Pet. App. 13a (citing EPA, New Source Review Workshop
Manual (Draft 1990)). Under that approach, “the applicant
ranks all available control technologies in descending order
of control effectiveness. The most stringent technology is
BACT unless the applicant can show that it is not technically
1
feasible, or if energy, environmental, or economic impacts
justify a conclusion that it is not achievable.” Pet. App. 13a.
The Act directs state permitting authorities to keep EP.
informed of every PSD permit application and “of every ac-
tion related to the consideration of such permit.” 42 U.S.C.
7475(d)(1). Although EPA often offers comments to state
permitting authorities on permit applications, EPA does not
become more formally involved in PSD permit decisions in
the vast majority of instances. Two provisions of the Act,
however, authorize EPA to enforce the statutory PSD re-
quirements. Section 113(a)(5) provides that if EPA “finds
that a State is not acting in compliance with any requirement
or prohibition” of the Act “relating to the construction of
new sources or the modification of existing sources,” 42
U.S.C. 7413(a)(5), EPA may (A) “issue an order prohibiting
the construction or modification of any major stationary
source in any area to which such requirement applies,” (B)
issue an administrative penalty order,” or (C) “bring a civil
action” in federal district court for an injunction or other re-
lief. 42 U.S.C. 7413(a)(5). Section 167, which is directed
solely to the PSD program applicable to new sources in clean
air areas, provides that EPA “shall * * * take such meas-
ures, including issuance of an order, or seeking injunctive
relief, as necessary to prevent the construction or modifica-
tion of a major emitting facility which does not conform to
the requirements of” the Act specifically intended to pre-
vent significant deterioration. 42 U.S.C. 7477.
2. Teck Cominco Alaska, Inc. operates the “Red Dog
Mine” in northwest Alaska, which is the largest producer of
zine concentrates in the world. Pet. App. 3a. Many workers
are housed within its boundaries, and native Alaskans reside
in the nearby villages of Kivalina and Noatak. Id. at 4a; J. A.
166; R. 36-018, 46-001. Cominco first obtained a PSD permit
from petitioner for the mine in 1988. Pet. App. 4a; J.A. 166.
The mine produces its own electricity. In order to ensure
—
— 1 ae a
er ee
5
that emissions of nitrogen oxides (NOx) from its power gen-
erators remained within permissible limits, that permit, as
later amended, included restrictions that limited the opera-
tions of the mine’s five original diesel-fired power generators
(designated MG-1 through MG-5) and one generator added
later (designated MG-6). J.A. 78-79, 166-167, 194-195.
In 1996, Cominco initiated an expansion project to in-
crease zinc production by 40%. Pet. App. 4a; R. 85-007; J.A.
167. The State of Alaska provided just under half of the
funding. R. 85-007. The project was to increase the mine’s
workforce from 406 to 476. Ibid. Because the expansion
would significantly increase emissions of air pollutants
(including up to 1,100 additional tons per year of NOx) from
the power generators, Cominco was required to apply for a
new PSD permit. Cominco submitted its application in June
1998. Pet. App. 4a; J.A. 167-169. As amended in 1999,
Cominco’s application sought permission to build a new gen-
erator (designated MG-17) to add to the six existing ones.
Pet. App. 4a; J.A. 167, 196. Cominco argued that petitioner
should determine that BACT for that generator is a technol-
ogy known as “Low NOx.” Pet. App. 4a; J. A. 84.
1 BACT review is required if modification of a particular facility would
lead to a specified increase in emissions. See R. 33-016 (Table 2.3-1 show-
ing Alaska PSD permit needed if NOx emissions will be increased by 40
tons per year or greater); 40 C.F.R. 51.166(b)(23)(i) (state SIPs must have
40-ton-per-year threshold for NOx increase). Initially, as a result of
Cominco’s planned increases in electricity generation from those
generators that would lead to increased emissions, there was
disagreement about the content of a BACT determination for MG-5 and
the need for a BACT determination for MG-1, MG-3, and MG-4. See J.A.
128-129. In October 1999, Cominco revised its proposal to install Low
NOx on those generators and thereby increase electricity production
while not increasing emissions. See J.A. 149. The revision required
Cominco to abide by the emission limitations in the pre-existing permits
for those generators. See p. 9, infra. The case now concerns only the
BACT limitation on the new generator, MG-17.
6
Petitioner’s staff initially disagreed with Cominco’s BACT
proposal, concluding that a different and more stringent
technology, selective catalytic reduction (SCR), should be
required as BACT. J.A. 108, 196; Pet. App. 4a. SCR is
similar to the catalytic converter technology used in auto-
mobiles. See, e.g., 65 Fed. Reg. 35,430, 35,470 nn.100-101
(2000). In May 1999, however, petitioner released a draft
PSD permit decision granting Cominco permission to build
MG-17 with Low NOx—rather than SCR—installed on it.
See Pet. App. 4a; J.A. 55-95. Purporting to follow the “top-
down” approach (see pp. 3-4, supra), petitioner acknowl-
edged that SCR would provide the most stringent level of
control, while also being “technically and economically
feasible” on MG-17. J.A. 61-62, 65, 83-84, 283-284. In
particular, petitioner noted that the costs of SCR (variously
estimated at that time to be between $1586 and $5643 per
ton of NOx removed) were “well within what [petitioner]
and EPA considerſ] economically feasible.” J. A. 84. Never-
theless, petitioner proposed to select the less effective Low
NOx as BACT for MG-17 due solely to “other considera-
tions.” J. A. 65 n. I. Those “other considerations” consisted of
Cominco’s proposal to retrofit some of its existing genera-
tors with Low NOx as well. See note 1, supra; J.A. 87-88;
Pet. App. 4a.
In July 1999, EPA, following up on comments submitted
by the National Park Service (NPS), which was concerned
about the effect of increased NOx emissions on air quality
and vegetation at Cape Krusenstern National Monument
and Noatak National Preserve, raised concerns with peti-
tioner about its draft permit decision. Pet. App. 4a-5a; J.A.
96-98, 257, 284-285. EPA pointed out that petitioner itself
had found that SCR offered “the most stringent level of con-
trol” and was “economically and technologically feasible.”
J.A. 96. And EPA reminded petitioner that “the PSD pro-
gram does not-allow the imposition of a limit that is less
7
stringent than BACT” on MG-17, “even if equivalent emis-
sion reductions are obtained by imposing new controls on
other emission units.” J.A. 97; see Pet. App. 5a.
After receiving EPA’s comments, petitioner issued a re-
vised draft permit decision dated September 1999. Peti-
tioner again found SCR to offer the most stringent level of
control, to be technologically feasible, and not to be elimi-
nated by consideration of environmental and energy impacts.
J.A. 107, 287. The revised decision also acknowledged that
“the emission reductions achieved by the applicant’s pro-
posal to retrofit the existing, unmodified engines * * *
cannot be used to temper the stringency of BACT” on MG-
17—.e., that BACT had to be determined for MG-17 alone,
without regard to controls petitioner might choose to place
on other generators. J.A. 111-112, 286.
The revised draft decision nonetheless continued to state
that Low NOx qualified as BACT for MG-17, purporting to
base that determination on the costs of SCR, which it now
found to be only $2100 per ton of NOx removed. Pet. App.
5a, 14a-15a; J.A. 113, 117, 286-288. The revised draft as-
serted that the costs of SCR were “significantly higher” than
those associated with “recent BACT decision(s] for similar
installations,” although petitioner acknowledged that it had
imposed BACT costs of up to “$7,000 per ton of NOx re-
moved” on other sources. J.A. 115-116; R. 29-052. The re-
vised draft hypothesized that Cominco “would probably buy
power from a rural Alaskan utility” if it did not generate its
own power and stated that the cost increase of SCR would
be “a disproportionate cost increase when viewed as an elec-
tric utility.” J.A. 116. Petitioner concluded its analysis:
Another perhaps better way to determine if the cost of
BACT is excessive, is for the applicant to present de-
tailed financial information showing its effect on the op-
eration. However, the applicant did not present this in-
formation. Therefore, no judgment can be made as to the
8
impact of [the costs of SCR] on the operation, profitabil-
ity, and competitiveness of the Red Dog Mine.
J.A. 116 (emphasis added).
EPA again submitted detailed comments to petitioner.
See J.A. 118-130, 288-291. EPA’s view was that petitioner’s
BACT determination for MG-17 was “clearly erroneous” and
‘not “supported by * * * available information.” J.A. 129.
EPA emphasized, for example, the complete absence of facts
establishing that “requiring Cominco to install and operate
the more effective control strategies would have any adverse
economic impacts upon Cominco specifically.” J.A. 127.
In October 1999, the parties met to discuss the pending
PSD permit. Pet. App. 5a; J.A. 292. Many outstanding is-
sues were ultimately resolved. J.A. 294. For example,
Cominco now “agreed to restrict the emission increases as-
sociated with MG-5 to avoid modification and BACT review”
of that generator. J.A. 197. Although only the validity of
petitioner’s determination of BACT for the MG-17 generator
remained in dispute, it was an issue of significance. With
SCR, the MG-17 generator would emit only 53 tons of NOx
per year. With Low NOx, MG-17 would emit 531 tons of NOx
per year—a 10-fold difference. J.A. 100, 198.
After further correspondence and discussions, see J.A.
136-140, 292-294, EPA issued a “Finding of Noncompliance
and Order” to petitioner. Pet. App. 5a, 26a-37a; J.A. 294-296.
Invoking Section 113(a)(5) of the Clean Air Act, EPA found
that petitioner would violate the requirements of the Act
and the Alaska SIP if it issued the permit as then drafted.
Pet. App. 35a; J.A. 295-296. In a cover letter, EPA explained
that petitioner’s “record simply does not support its decision
that BACT for * * * MG-17 is low NOx controls.” J. A. 150.
EPA noted that petitioner’s own analysis “indicates that
SCR is technically feasible.” J. A. 149. EPA also “d[id] not
believe that the cost-effectiveness analysis in the final tech-
nical analysis report demonstrates that the installation of
9
SCR is economically infeasible” and noted that the costs of
SCR “are well within the range of costs EPA has seen per-
mitting authorities nationwide accept as economically feasi-
ble for NOx control, except where there are compelling site-
specific factors that indicate otherwise.” J.A. 150. EPA
stated, however, that it remained “available to review and
consider any additional information or analyses * * * to
support a determination that SCR is not BACT.” J.A. 150,
296-297. Similarly, pursuant to Section 167 of the Act,
EPA’s order directed petitioner not to permit construction
of Cominco’s MG-17 generator “unless [petitioner] satisfacto-
rily documents why SCR is not BACT.” Pet. App. 36a.
Later that same day, and notwithstanding EPA's order,
petitioner issued a PSD permit with an emission limit on
MG-17 based on a determination that Low NOx constituted
BACT. Pet. App. 5a; J.A. 254, 297-298. Under the permit,
the pre-existing emission limitations for the existing genera-
tors MG-1 through MG-6 were “retained” unchanged. J.A.
232; see J.A. 156 (2259 tons combined total for MG-1, MG-3,
MG-4, and MG-5), 233 (limits for MG-2 and MG-6). The per-
mit included no requirement that petitioner install Low NOx
on any of those generators, although petitioner had the right
both before and after the permit decision to do so to remain
within the pre-existing emission limitations while producing
more electricity. See J.A. 139.
There was one other significant departure from the Sep-
tember 1999 revised draft permit. Compare J.A. 194-211
with R. 29-042 to 29-055. Cominco still had not submitted
any information on, and petitioner by its own admission
therefore could make “no judgment” about, SCR’s impact
“on the operation, profitability, and competitiveness of the
Red Dog Mine.” J.A. 207, 299. Nonetheless, petitioner’s
analysis purported to find “the foremost consideration to
judge economic impacts of SCR” to be “the direct cost of
SCR technology and its relationship to retaining the Mine’s
10
world competitiveness.” J.A. 208. Petitioner concluded that
It jo support Cominco’s Red Dog Mine Production Rate In-
crease Project, and its contributions to the region, [peti-
tioner] has rejected [SCR] controls based on excessive eco-
nomic cost—$2.9 million capital cost, with annualized costs
approaching $635,000.” J.A. 208; see J.A. 298-299.
In early February 2000, EPA issued a finding of noncom-
pliance based on petitioner’s final December 1999 permit and
BACT determination. Pet. App. 5a; J.A. 256-258, 299-300.
On the same day, invoking Sections 113(a)(5) and 167 of the
Act, EPA issued an “Administrative Order” to Cominco not
to commence construction of MG-17 until it obtained a valid
PSD permit. See Pet. App. 38a-50a; J.A. 301. In March
2000, EPA issued an “Amended Administrative Order” ac-
commodating Cominco’s request to conduct some limited,
weather-sensitive construction. See Pet. App. 5la-64a; J.A.
302. In April 2000, EPA withdrew the original December 10,
1999, Order on the ground that “after [petitioner] issued the
permit prohibited by the Order, the Order did not impose
any continuing prohibitions or obligations applicable to [peti-
tioner].“ Pet. App. 19a; J.A. 300. EPA did not, however,
withdraw the orders that generally prohibited Cominco from
doing construction work on MG-17.
3. Petitioner and Cominco filed petitions for review of
EPA’s findings of noncompliance and orders. The Ninth Cir-
cuit held that the EPA’s orders were final and that it there-
fore had jurisdiction under 42 U.S.C. 7607(b)(1). Pet. App.
18a-23a. Applying the test for finality in this Court’s deci-
sion in Bennett v. Spear, 520 U.S. 154 (1997), the court held
that EPA’s orders were its “last word” on whether Low
NOx is BACT for MG-17 and that “rights or obligations” of
the parties were determined by the orders because It he
effect of the February 8 Order [to Cominco] is to halt
construction at Cominco’s Red Dog Mine facility at a
considerable cost of both time and money to Cominco.” Pet.
11
App. 20a. The court also noted that legal consequences
[would] flow” if Cominco chose to continue construction
despite the orders because, if EPA instituted proceedings to
enforce its orders in district court, “Cominco and its
employees would be subject to criminal and civil penalties
for the violation of its Orders, as well as for the violation of
the [Clean Air Act].“ Id. at 21a.
On the merits, the court denied the petitions. Pet. App.
la-16a. The court noted that the enforcement powers EPA
relied upon depend on EPA’s finding either that the State is
“not acting in compliance with any requirement” of the Clean
Air Act under Section 113(a)(5) or that a proposed facility
“does not conform to the requirements of” the Act under
Section 167. Id. at 7a-8a (emphasis added) (quoting 42
U.S.C. 7413(a)(5) and 7477). The court observed that, under
the Act, a State may issue a PSD permit to construct a new
facility only if the proposed facility is “subject to the best
available control technology for each pollutant.” Id. at 8a.
The court concluded that BACT is therefore a “requirement”
of the Clean Air Act under both Section 113(a)(5) and See-
tion 167 and that EPA’s finding that petitioner had failed to
subject MG-17 to BACT authorized EPA to issue orders un-
der those Sections. Id. at 8a-9a.
Petitioner argued that the Act grants it discretion in de-
termining what constitutes BACT, because the Act defines
BACT as a limitation “based on the maximum degree of re-
duction of each pollutant * * * which the permitting
authority, on a case-by-case basis, taking into account en-
ergy, environmental, and economic impacts and other costs,
determines is achievable for [the] facility.” Pet. App. 9a
(emphasis added) (quoting 42 U.S.C. 7479(3)). The court
agreed that “the state has discretion to make BACT deter-
minations as the permitting authority.” Jd. at 10a. But it
explained that “neither Section 113(a)(5) nor Section 167
contains any exemption for [Clean Air Act] requirements
12
that involve the state’s exercise of discretion.” Id. at Ila.
The court concluded that “(i]t does not follow from the
placement of initial responsibility with the state permitting
authority that its decision is thereby insulated from the
oversight and enforcement authority assigned to the EPA in
other sections of the statute.” Ibid.
The court also rejected the argument that, even if EPA
has authority to reject a state BACT determination, EPA
acted arbitrarily and capriciously in this case. See Pet. App.
13a-16a. The court found that the administrative re-
cord—which “all the parties effectively agreed * * * was
adequate to resolve the issues on appeal”—supported EPA’s
finding of noncompliance. Id. at 7a. The court held that peti-
tioner’s own permit record “shows that (1) Cominco failed to
meet its burden of demonstrating that SCR was economi-
cally infeasible; and (2) [petitioner] failed to provide a rea-
soned justification for its elimination of SCR as a control op-
tion.” Id. at 16a. The court noted that petitioner’s “apparent
motivation for the elimination of SCR— appreciation for
Cominco’s contribution to the local economy”—is “uncom-
fortably reminiscent of one of the very reasons Congress
granted EPA enforcement authority—to protect states from
industry pressure to issue ill-advised permits.” Ibid.
SUMMARY OF ARGUMENT
I. The court of appeals rejected EPA’s argument that it
did not have jurisdiction in this case because EPA’s orders
were not “final action” and therefore were not subject to re-
view under 42 U.S.C. 7607(b)(1). Upon further considera-
tion, the government now believes that the court of appeals
did have jurisdiction. EPA’s orders embodied EPA's consid-
ered and final judgment on whether petitioner had ade-
quately justified its conclusion that Low NOx was the best
available control technology for the MG-17 generator. The
orders also determined legal rights and obligations, because
they in effect invalidated petitioner’s permit, pursuant to
13
which Cominco could have otherwise begun construction of
the MG-17 generator.
II. A. On the merits, EPA’s orders were based on
authority granted to EPA in Sections 113(a)(5) and 167 of
the Clean Air Act, 42 U.S.C. 7413(a)(5) and 7477, to prohibit
construction of a new source when a State has failed to com-
ply with a “requirement”—or the new source would not con-
form to a “requirement”—of the PSD program. The statu-
tory BACT provisions constitute such a requirement. They
mandate that permits for specified new sources (which in-
clude Cominco’s MG-17) require use of the “best available
control technology,” 42 U.S.C. 7475(a)(4), which in turn is
defined as “an emission limitation based on the maximum
degree of reduction of each pollutant” that the “permitting
authority * * * determines is achievable” for the facility,
“taking into account energy, environmental, and economic
impacts and other costs.” 42 U.S.C. 7479(3).
B. Petitioner’s core argument is that a State complies
with the BACT provisions so long as it makes a determina-
tion—any determination—of emission levels under the ru-
bric of BACT. That contention is inconsistent with the
statutory terms, which do not merely allow a state permit-
ting authority to determine whatever limit on emissions it
wants, but instead require it to determine the “maximum
degree of reduction in each pollutant * * * achievable” for
the facility, taking into account specified factors. 42 U.S.C.
747903). If a State has not actually determined the maxi-
mum reduction” that is “achievable,” or if a State has em-
ployed an arbitrary methodology or relied on unsupported
factual premises, the State has not complied with the BACT
requirement. Although a State has substantial scope for ex-
ercising judgment and weighing competing considerations in
making a BACT determination, that scope is not unlimited.
If a State acts outside the scope of permissible judgment,
14
EPA may exercise the authority Congress granted it to is-
sue a stop-construction order.
Petitioner’s argument that a State has sole discretion to
determine BACT would also undermine the statutory
scheme. Congress vested EPA with enforcement authority
in order to protect national interests in ensuring compliance
with Clean Air Act requirements—interests that transcend
state boundaries. Clean Air Act requirements were imposed
in order to protect not only residents of the State that
houses a new facility, but also residents of neighboring
States into which the air pollution from that facility may mi-
grate. Moreover, Congress wanted to limit the substantial
competitive disadvantage that States that imposed reason-
able BACT and other requirements would face if other
States could adopt unreasonably permissive standards.
C. Petitioner’s other arguments that it has absolute dis-
cretion to make whatever BACT determinations it wants are
unsound. Although petitioner holds out the prospect of
state-court review of its permitting decisions, Congress in
Sections 113(a)(5) and 167 of the Act deliberately gave EPA
its own independent authority to protect the multistate in-
terests in preventing the significant deterioration of air
quality in clean-air areas. In any event, petitioner’s conces-
sion that BACT requirements in its permits are subject to
state-court review is inconsistent with its core argument
that such requirements are solely a matter of discretion for
the state permitting authority. Petitioner is also mistaken in
contending that EPA enforcement of the BACT requirement
is unnecessary because new sources must not exceed the al-
lowable increases in emission (increments) under the Clean
Air Act. Although the increment requirement sets a maxi-
mum level of pollution from new facilities in the aggregate,
the separate BACT requirement was included specifically to
ensure that emissions from each new facility are reduced to
the maximum extent achievable for the facility.
15
EPA review is also consistent with the statutory scheme
of cooperative federalism. Under the PSD program, state
permitting authorities have substantial latitude to exercise
their own judgment about what constitutes BACT. Con-
gress also, however, gave EPA substantive authority to en-
sure compliance with the BACT requirement where a State
acts outside that area of reasonable judgment and discretion.
It is petitioner’s view, which would deprive EPA of any sig-
nificant role in the BACT process, that violates the princi-
ples of cooperative federalism.
D. If there is any doubt about the meaning of the Clean
Air Act in this case, EPA’s construction of the Act to require
permitting authorities to make reasonable BACT determina-
tions is entitled to deference under Chevron U.S.A, Inc. v.
NRDC, 467 U.S. 837 (1984). In conferring authority on the
EPA to make findings and issue orders to ensure compliance
with the Act’s requirements, Congress ne. -ssarily conferred
authority on EPA to construe and apply the Act. EPA’s
longstanding view that the Act requires BACT determina-
tions to be reasonable was embodied in its orders and the
administrative record in this case, as well as in notice-and-
comment rulemaking and guidance to the States over the
years.
III. Petitioner argues that, if EPA does have statutory
authority to act on the basis of a State’s unreasonable BACT
determination, EPA nonetheless erred in finding that peti-
tioner’s BACT determination in this case was unreasonable.
That factbound issue falls outside the question of statutory
authority presented in the certiorari petition.
In any event, EPA correctly concluded that petitioner un-
reasonably determined that Low NOx was BACT was un-
reasonable. It is not disputed that the use of SCR on MG-17
would result in much lower emissions than would the use of
Low NOx. Petitioner conceded that SCR was feasible based
on energy and environmental impacts. Although petitioner
16
purported to rely on the greater costs of SCR in rejecting it
as BACT, petitioner also acknowledged that it had been pro-
vided with no information concerning the effects of those
greater costs on Cominco’s mining operation, and that ac-
cordingly “no judgment can be made as to the impact of [the
costs of SCR] on the operation, profitability, and competi-
tiveness” of the mine. J.A. 207. EPA correctly found that
petitioner’s decision to base its BACT determination on a
bare desire to save money for Cominco, unsupported by any
evidence that doing so would in turn substantially affect
Cominco’s operations at the mine or the neighboring com-
munities, was unreasonable.
ARGUMENT
I. THE COURT OF APPEALS HAD JURISDICTION IN
THIS CASE
The court of appeals held that EPA’s orders in this case
were “final action” and thus reviewable under 42 U.S.C.
7607(b)(1). See generally Harrison v. PPG Indus., Inc., 446
U.S. 578 (1980). The court rejected EPA’s arguments that
the orders were non-final. Upon further consideration, the
government now believes that the court of appeals correctly
found that it had jurisdiction in this case.
1. It is well-settled that myriad “pragmatic considera-
tions” are involved in a finality determination. See, e.g., FTC
v. Standard Oil Co., 449 U.S. 232, 239-243 (1980). The finality
of EPA’s Orders turns on two factors that were highlighted
in Bennett v. Spear, supra. Under Bennett, [a]s a general
matter,” a final agency action (1) must be one that “mark(s]
the ‘consummation’ of the agency’s decisionmaking process,”
rather than one that is “merely tentative or interlocutory
in] nature,” and (2) it “must be one by which ‘rights or obli-
gations have been determined,’ or from which ‘legal conse-
quences will flow.“ 520 U.S. at 177-178. See Whitman, 531
U.S. 477-479.
— —
— — — . —
——
17
The first of the Bennett conditions is satisfied here, as the
Ninth Circuit concluded. Pet. App. 20a. The second Bennett
condition is also satisfied given the nature of the orders in
this case. The Act required Cominco to obtain a permit and
be subject to BACT prior to construction. 42 U.S.C.
7475(a)(1). Absent EPA’s orders, petitioner’s permit would
have removed those obstacles to Cominco’s construction of
the MG-17 generator. The orders, however, “effectively in-
validated” the state permit. Pet. App. 18a. They precluded
Cominco from constructing the generator and from asserting
its compliance with the state permit as a defense in any en-
forcement proceeding. Moreover, as the court of appeals
noted,-once EPA issued its stop-construction orders,
Cominco was faced with the threat of penalties for their vio-
lation. Id. at 21a; see 42 U.S.C. 7413(b)(2) (civil penalties
possible for violations of a “requirement or prohibition of any
* * * order * issued * * under” the Act), 7413(c)
(criminal penalties possible for knowing violation of “any or-
der under [Section 113(a)]” or “an order under section
[167}”). Accordingly, the orders alterſed] the legal regime,”
Bennett, 520 U.S. at 178, and they constituted “final action of
the Administrator” under 42 U.S.C. 7607(b)(1).
2. The court of appeals’ jurisdictional conclusion is con-
sistent with the Sixth Circuit’s conclusion involving a similar
order in Allsteel, Inc. v. EPA, 25 F.3d 312, 315 (6th Cir.
1994) (noting that EPA’s order “directed Allsteel to stop all
construction—a new obligation, not one directly imposed by
statute”). Compare Acker v. EPA, 290 F.3d 892 (7th Cir.
2002) (order that identified past violations and directed com-
pany to comply with law in the future not final action); As-
bestec Constr. Servs., Inc. v. EPA, 849 F.2d 765 (2d Cir.
1988) (order that identified past violations of the Act, di-
2 Although the Sixth Circuit’s opinion does not specify the nature of
the federal-state dispute, the briefs in Allsteel reveal that it included the
validity of Tennessee’s BACT determination.
18
rected the recipient to provide certain information, and re-
quired compliance with regulations in the future not final ac-
tion); but cf. Solar Turbines, Inc. v. Seif, 879 F.2d 1073 (3d
Cir. 1989) (holding, prior to 1990 expansion of civil penalties
to cover violations of orders under 167, that pre-enforcement
review of stop-construction order was unavailable).
After the court of appeals decided this case and this Court
granted certiorari, the Eleventh Circuit in TVA v. Whitman,
No. 00-15936, 2003 WL 21452521 (June 24, 2003), expressly
disagreed with the Ninth Circuit’s jurisdictional holding in
this case. See id. at *16. The Eleventh Circuit did not
disagree with the Ninth Circuit’s conclusion that, as a
statutory matter, Section 307(b)(1), 42 U.S.C. 7607(b)(1),
would authorize pre-enforcement review of a stop-construc-
tion order such as that at issue here. The court held,
however, that the Act “is unconstitutional to the extent that
mere noncompliance with the terms of [an EPA order] can
be the sole basis for the imposition of severe civil and crimi-
nal penalties.” 2003 WL 21452521, at *19. In the court’s
view, the statutory scheme “deprives the regulated party of
a ‘reasonable opportunity to be heard and present evidence’
on the two most crucial issues: (a) whether the conduct
underlying the issuance of the [order] actually took place and
(b) whether the alleged conduct amounts to a [Clean Air Act]
violation.” Jd. at *18. The Eleventh Circuit rejected the
contention that EPA could remedy any procedural deficiency
“by voluntarily undertaking an adjudication prior to the
issuance of an [order],” finding that “there is simply no room
for administrative discretion on this [procedural] point” in
the Act. Ibid. The Eleventh Circuit concluded that EPA
orders “lack finality because they do not meet prong two of
the Bennett test.” Id. at *19.
The Eleventh Circuit’s holding is mistaken, for at least
two reasons. First, contrary to the Eleventh Circuit’s ap-
parent conclusion, see, e.g., 2003 WL 21452521, at *4, the un-
19
derlying merits of an EPA order are always subject to judi-
cial review—either on petition for review, as in this case or,
if not, in a subsequent action brought by EPA to enforce the
order. See 42 U.S.C. 7607(b)(2) (“Action of the Administra-
tor with respect to which review could have been obtained
under [42 U.S.C. 7607(b)(1)] shall not be subject to judicial
review in civil or criminal proceedings for enforcement.”).
The Act’s authorization of penalties for violation of EPA
“orders” is naturally read to refer only to valid orders. In
any event, such a narrowing construction would certainly be
appropriate to avoid holding a portion of the Act unconstitu-
tional.“
Second, the Eleventh Cireuit erred in holding that EPA
cannot provide for administrative procedures that would
remedy any constitutional deficiency. The mere fact that
Congress has failed to specify what procedures must be fol-
lowed before EPA may issue an order does not preclude
EPA from adopting procedures that are constitutionally
adequate. The Due Process Clause does not require that
Congress specify adequate procedures every time it entrusts
to an agency the responsibility to make a determination; the
Clause requires only that, in each case, adequate procedures
are provided. This Court has long held that an agency has
8 The Eleventh Circuit noted that EPA may issue orders under
Section 113(a)(5) “on the basis of any available information,” 42 U.S.C.
7413(a)(5), and the court appears to have believed that that language man-
dated an exceptionally lax standard of judicial review of EPA orders. See
2003 WL 2145251, at *5, *16, *18. The “any available information” clause,
however, does not alter the standard of review when EPA’s orders are
challenged; it simply means that EPA need not apply judicial rules of
evidence in determining whether there has been a violation of the Act that
warrants issuance of an order. Cf. 18 U.S.C. 3661 (“No limitation shall be
placed on the information concerning the background, character, and
conduct of a person convicted of an offense which a court of the United
States may receive and consider for purposes of imposing an appropriate
sentence.”); Sentencing Guidelines § 1B1.4 (similar).
20
general authority to provide appropriate process, even when
a statute does not specify that that process must be used.
See, e.g., Vermont Yankee Nuclear Power Corp. v. NRDC,
435 U.S. 519, 544 (1978) (noting “the very basic tenet of ad-
ministrative law that agencies should be free to fashion their
own rules of procedure”); Cameron v. United States, 252
U.S. 450, 460-463 (1920). The Eleventh Circuit erred in re-
jecting that principle. Moreover, neither the Due Process
Clause nor the Administrative Procedure Act requires a
formal evidentiary hearing in all circumstances, and Con-
gress contemplated that many EPA orders under the Clean
Air Act would be issued in less formal proceedings. See
PPG Indus., Inc. 446 U.S. at 587-589.
3. The Eleventh Circuit’s sole reason for holding that the
EPA order in that case was nonfinal and thus unreviewable
was that the Act’s provision for such orders to be backed by
civil and criminal penalties was unconstitutional. For the
reasons given above, the Act’s provisions for EPA orders do
not violate the Due Process Clause. Accordingly, the
Eleventh Circuit’s finality conclusion was erroneous, and the
court of appeals in this case correctly held that the EPA
orders were reviewable under Section 307(b)(1).°
4 Petitioner has not presented any question in this case about the ade-
quacy of EPA’s procedures under the Due Process Clause or the APA.
5 The Clean Air Act itself vests courts of appeals with original
jurisdiction to review certain enumerated actions of EPA and “any other
final action” it takes. 42 U.S.C. 7607(b)(1). Thus, apart from constitutional
or prudential limitations such as standing, “finality” is the only juris-
dictional inquiry under the Act. See Allsteel, 25 F.3d at 314. Other en-
vironmental statutes, such as the Clean Water Act, 33 U.S. 1251 et seq.,
and the Resource Conservation and Recovery Act, 42 U.S.C. 6901 et seq.,
generally do not comprehensively provide for judicial review, and review
accordingly often takes place in district courts pursuant to the APA. The
APA provides that an agency action may be “final” yet still statutorily
unreviewable on other grounds, such as if the statute under which the
agency acts preeludeſs] judicial review.” 5 U.S.C. 701(a)(1). Courts have
— — . eS
21
II. THE CLEAN AIR ACT AUTHORIZES EPA TO IS-
SUE A STOP-CONSTRUCTION ORDER IF A
STATE’S PSD PERMIT IS BASED ON AN ARBI-
TRARY OR UNREASONED DETERMINATION OF
BEST AVAILABLE CONTROL TECHNOLOGY
Sections 113(a)(5) and 167 of the Clean Air Act, 42 U.S.C.
7413(a)(5) and 7477, both grant EPA authority to issue stop-
construction orders to enforce a “requirement” of the Act.
Both parties agree that it is a requirement of the Act that a
permitting authority determine the best available control
technology for a proposed facility and include corresponding
emission limitations in its PSD permit. EPA rested its
Orders in this case on the premise that a State fails to
conform to that requirement if it bases emission limitations
in a permit on an unreasonable BACT determination. That
conclusion is correct, and petitioner’s arguments for a
contrary interpretation—under which the Act requires per-
mitting authorities to make a BACT determination but does
not require them to do so reasonably—are mistaken.
generally found that pre-enforcement review of EPA orders under those
other environmental statutes is precluded within the meaning of the APA.
See, e. g., Southern Ohio Coal Co. v. Office of Surface Mining, Reclama-
tion & Enforcement, 20 F.3d 1418, 1426 (6th Cir. 1994); Southern Pines
Assocs. v. United States, 912 F.2d 713, 716 (4th Cir. 1990); Hoffman
Group, Inc. v. EPA, 902 F.2d 567, 568 (7th Cir. 1990); Ross Incineration
Servs. v. Browner, 118 F. Supp. 2d 837, 843-845, 847 (N.D. Ohio 2000);
Amoco Oil Co. v. EPA, 959 F. Supp. 1318, 1323-1324 (D. Colo. 1997). The
Comprehensive Environmental Response, Compensation, and Liability
Act, 42 U.S.C. 9601 et geg., contains an express bar to pre-enforcement re-
view. Cf. Lloyd A. Fry Roofing Co. v. EPA, 554 F.2d 885 (8th Cir. 1977)
(finding pre-enforcement review under the Clean Air Act precluded prior
to the 1977 addition of the “any other final agency action” language to
Section 7607(b)(1)).
22
A. Under The Plain Language Of Sections 113(a)(5) And
167, EPA Has Authority To Prevent Construction Of A
Facility Under A Permit That Does Not Comply With
Requirements Of The Clean Air Act
“(T]he starting point in a case involving construction * *
* of a statute, is the language of the statute itself.” United
States Dep’t of Treasury v. Fabe, 508 U.S. 491, 500 (1993).
Two provisions of the Clean Air Act expressly authorized
EPA’s orders in this case.
1. Under Section 113(a)(5), “[wJhenever * * * the Ad-
ministrator finds that a State is not acting in compliance
with any requirement or prohibition of the chapter relating
to the construction of new sources or the modification of ex-
isting sources, the Administrator may * issue an order
prohibiting the construction or modification of any major
stationary source in any area to which such requirement ap-
plies.” 42 U.S.C. 7413(a)(5) (emphasis added); see 42 U.S.C.
7411(a)(4) (defining “modification”). Under that provision,
even when a State rather than EPA has authority to issue
PSD permits—and even though the State’s decision to grant
a PSD permit would be subject to judicial review in state
court—Congress granted EPA itself a substantive role in
overseeing state implementation. Cf. Pet. Br. 23 (“There are
many ‘requirements’ in the Act, including in the PSD provi-
sions, that the EPA may enforce pursuant to Sections
113(a)(5) or 167.”). Indeed, Congress expanded EPA’s over-
sight role under Section 113(a)(5) in 1990 specifically to in-
clude enforcement of the Act’s PSD requirements. See p. 32,
infra. Thus, if EPA finds that a State decision to issue a
permit does not comply with a requirement of the PSD
provisions of the Act, EPA may issue a stop-construction
order under Section 113(a)(5).
2. EPA's authority under Section 167 rests on a similar
foundation. Under Section 167, “[tJhe Administrator shall
* * * take such measures, including issuance of an order,
* * * as necessary to prevent the construction or modifica-
tion of a major emitting facility which does not conform to
the requirements of this part” of the Act. 42 U.S.C. 7477
(emphasis added). The term “this part” refers to the provi-
sions of the Act concerning prevention of significant deterio-
ration of air quality in clean air areas. See 42 U.S.C. 7470-
7492. Section 167 thus specifically gives to EPA—in addition
to the States that have permitting authority under the
Act—a substantive enforcement role with respect to con-
struction or modification of facilities in clean air areas.
B. A Permitting Authority That Has Not Reasonably De-
termined The Maximum Degree Of Reduction In Pollu-
tion Achievable For A Facility Has Not Complied With
The Act's BACT Requirement
EPA's ability to act in this case thus turns (under Section
113(a)(5)) on whether the Alaska permitting authority has
complied with the Clean Air Act’s “requirements” and (un-
der Section 167) on whether Cominco’s proposed facility
would conform to the Act’s “requirements.” Section
165(a)(4) provides that Injo major emitting facility * * *
may be constructed” in a clean air area “unless * * * the
proposed facility is subject to the best available control
technology.” 42 U.S.C. 7475(a)(4). Petitioner concedes (Br.
22) that that provision imposes a “BACT requirement” that
“a stat. issued PSD permit contain a BACT limitation.”
EPA's order to stop construction therefore was authorized
under Section 113(a)(5) if the State was “not acting in
compliance with” the statutory BACT requirement when it
issued the PSD permit, and EPA’s order was authorized
under Section 167 if Cominco’s construction of its MG-17
generator with Low NOx would “not conform to” that
requirement.
The core disagreement in this case concerns the nature of
the BACT requirement. Both parties agree that a state
permitting authority has the responsibility in the first in-
24
stance to determine what is the best available control tech-
nology for a given proposed facility. The government’s
submission is that the Act requires the state permitting
authority to make its BACT determination reasonably
within the parameters the statutory standards, and that,
when the state author / fails to do so, EPA may enforce the
Act’s requirements under Sections 113(a)(5) and 167.
Petitioner’s view is that the state permitting authority has
“sole discretion” to impose whatever emission limitations it
wants under the BACT label (Br. 27) and that EPA’s
authority under Sections 113(a)(5) and 167 therefore does
not include any substantive review of whether the State’s
BACT determination is reasonable or justifiable. Peti-
tioner’s position is mistaken.
1. The BACT requirement is fleshed out in a statutory
definitional provision. That provision does not merely re-
quire that a State determine the “best” emission limitation,
without further specification—a standard that, even had it
been employed, still would not necessarily mean that peti-
tioner had unreviewable discretion. See Citizens to Preserve
Overton Park v. Volpe, 401 U.S. 402, 411-413 (1971) (grant of
authority to administrator to determine “prudent” alterna-
tive to highway route does not grant unlimited discretion).
Rather, BACT is defined in pertinent part as
an emission limitation based on the maximum degree of
reduction of each pollutant * * *, which the permitting
authority, on a case-by-case basis, taking into account
energy, environmental, and economic impacts and other
costs, determines is achievable for [the] facility through
application of production processes and available meth-
ods, systems, and techniques * * * for control of each
such pollutant.
42 U.S.C. 747903). Thus, a PSD permit satisfies the BACT
requirement if it provides for the “maximum degree of re-
duction of each pollutant” that “is achievable for [the] facil-
ity” through specific measures “for control of each such pol-
lutant.” That determination must “tak[e] into account en-
ergy, environmental, and economic impacts and other costs.”
The “permitting authority”—in this case, petitioner—is the
entity that must make that determination, just as it must
make all other determinations necessary to deciding whether
a proposed PSD permit would comply with the Act.
2. Petitioner’s core argument is that the statutory BACT
requirement is satisfied so long as the permitting authority
takes into account the specified factors and makes some de-
termination about emission limitations, no matter how im-
plausible. See Pet. Br. 22 (“The only ‘BACT requirement’
pertinent here is that a state-issued PSD permit contain a
BACT limitation, determined by the State ‘on a case-by-case
basis, taking into account energy, environmental, and eco-
nomie impacts and other costs.’”); id. at 27 (Congress
vestſed] the States with sole discretion to decide what con-
stitutes BACT.”) (emphasis added). In petitioner’s view,
EPA may invoke Sections 113(a)(5) and 167 only to enforce
the requirement that the state permitting authority recite
that it is determining the best available control technology
and “tak{ing] into account” the specified factors. In peti-
tioner’s view, that is all a state permitting authority must do
to satisfy the statutory BACT requirement.
Petitioner’s argument is inconsistent with the plain lan-
guage of the BACT definition. Under that definition, there
are at least two ways in which a permitting agency might
recite that it is determining BACT and taking into account
the specified factors while still failing to satisfy the statutory
BACT requirement.
a. First, the Act does not require merely that a permit-
ting agency make some determination of indeterminate con-
tent regarding desirable emission reductions. Rather, the
agency must make a determination of the “maximum degree
of reduction of each pollutant * * * achievable” by the
facility. Despite a permitting agency’s incantation of the
statutory BACT definition, the agency’s decision might
make clear that it has not actually determined the “maxi-
mum degree of reduction * * * achievable” by a facility. In
such a case, although the permitting agency has made some
determination, it has not made a determination of BACT.
For example, the permitting authority’s reasoning may
demonstrate that it applied some lower standard than the
“maximum degree of reduction * * * achievable”—perhaps
seeking only a degree of reduction that requires no new
equipment installation, the least expensive reduction in
emissions, or the like. Applying such a standard would vio-
late the statutory BACT requirement regardless of whether
the permitting agency designated it as a BACT determina-
tion.
Similarly, the state agency’s decision may make clear that
it was based on a desire to provide economic support to a
particular company or facility by relieving it of the need to
lower its emissions. Providing economic support through
expenditure of state funds or exemption from purely state-
law regulations may be a worthwhile state goal in a given
case, but a State’s decision that it wants to support an em-
ployer is not a determination of the “maximum degree of re-
duction” of pollutants “achievable” for the facility.
As is spelled out in additional detail below, see pp. 44-50,
infra, EPA objected to the permit in this case because peti-
tioner made the very kinds of errors outlined above. Peti-
tioner did find that SCR is more expensive than Low NOx.
But petitioner also acknowledged that, because Cominco
“did not present” detailed financial information about the
effect of the costs of SCR on its operations, “no judgement
can be made as to the impact [of those costs] on the opera-
tion, profitability, and competitiveness of the Red Dog
Mine.” J.A. 207. Petitioner thus had no evidence concerning
the effect of the costs of SCR on Cominco’s operations or on
— — — ñ te
27
the local community. Indeed, petitioner pointed to no evi-
dence supporting a conclusion that the higher costs would
have any adverse effect. As a result, petitioner was not in a
position to determine that SCR—which concededly would
assure the “maximum degree of reduction” of NOx as a
technological matter—would not be “achievable” for the MG-
17 generator. At most, petitioner could determine that it
wanted to provide additional economic “support” to the Red
Dog mine. J.A. 208. But a State may not simply choose to
support a local facility by relieving it of the requirement to
use the best available control technology to reduce pollution.
If it does so, EPA has authority under Sections 113(a)(5) and
167 to prohibit construction of the facility.
b. In addition, the permitting agency does not satisfy the
Act’s requirement that it make a genuine BACT determina-
tion based on the “maximum degree of reduction * * *
achievable” merely by reciting a finding that a particular
technology satisfies that standard, no matter how arbitrary
or unreasoned that finding is. Congress’s grant of authority
to make a BACT determination was directed toward a par-
ticular purpose of fundamental importance under the
Act preventing significant deterioration of air quality in
clean-air areas within the State and in other neighboring
States. See 42 U.S.C. 7470(3) and (4). That purpose would
not be advanced by a BACT determination that arbitrarily
evaluated the evidence before the permitting authority or
applied the statutory criteria in an arbitrary manner that
excused the applicant from installing meaningful pollution
controls. Accordingly, Congress’s grant of authority to make
BACT determinations is limited to the authority to make
reasonable BACT determinations.
This Court reached an analogous conclusion in Wilder v.
Virginia Hosp. Ass n, 496 U.S. 498 (1990). In that case,
medical care providers brought suit under 42 U.S.C. 1983 to
challenge Medicaid reimbursement rates set by a State, on
the ground that the rates violated a federal statute requiring
States to provide for payment for medicaid services “though
the use of rates * which the State finds * are rea-
sonable and adequate” to meet certain costs. 496 U.S. at
503. The Court rejected the argument that the only right
granted by the statute that was enforceable under 42 U.S.C.
1983 was “the right to compel compliance with theſ] bare
procedural requirement{]” that the State recite a finding
that its rates are reasonable. 496 U.S. at 513. Noting that
such a construction “would render the statutory require-
ment(] of findings essentially meaningless,” the Court
explained that “[ijt would make little sense for Congress to
require a State to make findings without requiring those
findings to be correct.” Id. at 514. Accordingly, the statute
imposed a meaningful requirement that could be enforced
under federal law.
Similarly here, it would make little sense to require a
state permitting agency to “determine” the best available
control technology if the agency could do so without concern
for the accuracy or statutory legitimacy of its analysis. If a
permitting agency used an arbitrary methodology or disre-
garded clear evidence of actual costs in determining what is
BACT, then the agency has not made a reasonable BACT
determination and it has not complied with the statutory
BACT requirement. That would be the case, for example, if
a permitting agency simply decided that any technology that
® The result in this case follows a fortiori from Wilder. Wilder
involved the question whether the members of a particular class were
intended to be beneficiaries of a right under a federal statute such that
they could sue to enforce that right under Section 1983. As the Court con-
cluded in Gonzaga University v. Doe, 536 U.S. 273, 283 (2002), the de-
manding standards governing implication of private rights of action under
federal statutes apply to such uses of Section 1983 by private plaintiffs.
No such demanding standard applies to the construction of EPA’s express
authority under Sections 113(a)(5) and 167 to enforce the requirements of
the PSD provisions of the Clean Air Act.
imposes any economic cost—even one additional dollar—is
not “achievable” for a facility, even though the facility is pro-
jected to be profitable and plainly could afford a modest ad-
ditional cost for pollution control. Where, as in this case, a
permitting authority has not made a reasonable determina-
tion of what is the best available control technology under
the statutory standards, it has failed to comply with the
statutory BACT requirement, and EPA has authority under
Sections 113(a)(5) and 167 to issue a stop-construction order.
e. That does not mean that a permitting authority has no
ability to exercise judgment and to weigh competing consid-
erations when it makes a BACT determination. EPA itself
has consistently recognized that the Clean Air Act gives
state permitting authorities considerable latitude in making
such determinations.’ EPA has long taken the position that
a State with an approved SIP “assumes primary responsi-
bility for administering the PSD program,” J.A. 268 (1983
EPA guidance document), and that “permitting decisions in-
volve the exercise of judgment,” J.A. 273 (1988 EPA guid-
ance document). EPA also has recognized that “it is the state
that must make the final decision on all issues relating to the
specific permit” and that It here is no suggestion in the
Act’s * * * provisions that EPA has authority to second-
guess the state on matters that are a lawful and rational ex-
ercise of discretion properly conferred upon the state.” J.A.
281 (quoting 1993 EPA guidance document).
7 See also, e., Pet. App. 10a (“state has discretion to make BACT
determinations”); Northern Plains Res. Council v. EPA, 645 F.2d 1349,
1358-1362 (9th Cir. 1981) (affirming BACT determination because per-
mitting authority “exercised reasoned discretion”); Alabama Power, 636
F.2d at 409 (“permitting authority * may exercise reasonable dis-
cretion” in determining BACT).
8 EPA recognized that scope of state authority in this case by making
clear, for example, that petitioner could come into compliance by “satis-
factorily document{ing] why SCR is not BACT for the Wartsila diesel
generator.” Pet. App. 36a, 48a, 6la. See also J.A. 150 (EPA is “available
30
Nonetheless, EPA too has enforcement responsibility un-
der Sections 113(a)(5) and 167. Accordingly, EPA has con-
sistently informed the States that it will exercise its author-
ity under those provisions if a State’s “BACT determination
lis] not based on a reasoned analysis.“ J. A. 274 (1988 EPA
guidance document). See also J. A. 282 (quoting 1993 EPA
guidance document) (EPA may take action if a State has not
“met all procedural norms, considered all available control
technologies, and given a reasoned justification for the basis
of its decision.”); J.A. 281 (EPA may act “to ensure that the
state exercises its discretion within the bounds of the law.”).
It has proven to be relatively rare that a state agency has
put EPA in the position of having to exercise that authority.’
But, if it does so, EPA may exercise its authority under Sec-
tions 113(a)(5) and 167 to remedy the failure.
3. a. Petitioner’s argument that EPA has no authority to
examine the substance of a State’s BACT determination is
also inconsistent with the structure and purposes of the
Clean Air Act and, in particular, with its PSD provisions.
Congress added those provisions in 1977. Under the 1977
amendments, as the Senate Report explained,
[t]he Administrator’s role is one of monitoring State ac-
tions. States have authority to issue construction per-
mits to new major emitting facilities in clean air areas.
The Administrator thus could go to court to stop a per-
mit for activities which would exceed the increments of
pollution or which otherwise did not comply with the re-
to review and consider any additional information or analyses * * * to
support a determination that SCR is not BACT”).
There are only two other reported judicial decisions that involve
stop-construction orders because of faulty BACT determinations. See
Allsteel, supra (recital only that there was faulty PSD permit, but record
reveals that fault was in part in BACT determination); Solar Turbines,
supra.
31
quirements of this section, including use of best avail-
able control technology.
S. Rep. No. 127, 95th Cong., Ist Sess. 12 (1977) (emphasis
added). As is evident, legislators expressly contemplated,
without qualification, that the BACT requirement would fall
within EPA’s responsibility to “monitor[] State actions.”
Ibid. The Report even explains how EPA should exercise its
oversight role: At he Administrator should tell the States
the basis for his review. When asked, he should become in-
volved at an early date in particularly difficult permit appli-
cations so that the States and localities will know of any po-
tential differences.” Ibid. See also H.R. Conf. Rep. No.
564, 95th Cong., Ist Sess. 153 (1977) (“The Administrator
shall isswe orders and seek other action to prevent issuance
of an improper permit.”) (emphasis added).
10 Although the passage quoted in the text identifies one measure
(goling! to court”) that EPA may take under 42 U.S.C. 7477 to prevent
construction of a non-conforming facility, Section 7477 more generally
authorizes EPA to “take such measures” as are necessary, specifically
“including issuance of an order, or seeking injunctive relief.”
11 The record here shows that EPA followed this roadmap by com-
municating its concerns about Cominco’s amended application. EPA’s
prompt actions here also belie predictions by petitioner and its amici that
affirming the judgment below would necessarily allow EPA enforcement
action initiated long after construction is completed. See, e.g., Pet. Br. 35;
Nat’l Envtl. Dev. Ass'n, et al. Br. 10; N. D., et al. Br. 15. This case, which
involves pre-construction orders issued by EPA, furnishes no occasion to
consider the circumstances under which EPA might appropriately act
post-construction. Cf., ¢.g., United States v. Murphy Oil USA, Inc., 155 F.
Supp. 2d 1117, 1123 (W. D. Wis. 2001) (rejecting source operator’s reliance
on state-issued PSD permit because operator failed to submit relevant
information to permitting authority). As a matter of policy, EPA takes
account of equitable concerns in issuing orders. See J.A. 273. District
courts also may consider the equities in fashioning “appropriate relief,” 42
U.S.C. 7413(b), and EPA’s failure to act in a timely manner would in many
cases be an important equitable factor for the court to consider. 42 U.S.C.
7413(b).
32
The legislative history of the 1990 amendments further
confirms that Congress intended to give EPA a limited, but
nonetheless substantive and source-specific role under the
Clean Air Act. Contra Pet. Br. 33-34. Prior to 1990, EPA’s
authority under Section 113(a)(5) was limited to actions to
remedy a State’s noncompliance with a “plan provision” or
other specified provisions of the Clean Air Act, and only in
nonattainment areas. 42 U.S.C. 7413(a)(5) (1988). Under the
1990 amendments, Congress broadened Section 113(a)(5) to
encompass a State’s noncompliance with “any requirement”
pertaining to new or modified major sources, including those
located in clean air areas and therefore subject to PSD per-
mits. H.R. Rep. No. 490, 101st Cong., 2d Sess. Pt. 1, at 391
(1990). Petitioner’s restrictive construction would contradict
Congress’s purposeful expansion of EPA’s authority. See
Stone v. INS, 514 U.S. 386, 397 (1995) (“When Congress acts
to amend a statute, we presume it intends its amendment to
have real and substantial effect.”).”
b. Congress had good reason to give EPA such enforce-
ment authority. First, Congress has always recognized that,
because air pollution moves easily across state lines, the
Clean Air Act implicates interests that surpass those of any
particular State. Indeed, Congress declared in a statutory
finding that one of the purposes of preventing significant de-
terioration of air quality even in clean air areas was “to as-
sure that emissions from any source in any State will not in-
terfere with any portion of the applicable implementation
plan to prevent significant deterioration of air quality for
any other State.” 42 U.S.C. 7470(4) (emphasis added). The
House Report on the 1977 amendments that added the PSD
program discussed the extensive evidence that “{a]ir is no
respecter of political boundaries” and explained that “while
12 Also in 1990, Congress enacted an operating-permit program under
which EPA has even greater source-specific responsibilities than under
the preconstruction programs. See 42 U.S.C. 7661-7661f.
33
emissions may not be ‘significant’ in the area of origin, when
transported to another area and combined with pollutants
from other areas, air quality may be drastically degraded.”
H.R. Rep. No. 294, 95th Cong., Ist Sess. 135 (1977). Ac-
cordingly, Ja] policy of prevention of significant deteriora-
tion which controls a new source’s emissions to the mayimum
extent practicable will help minimize the transport and
buildup of pollutants from one area to another.” Ibid. To
accomplish that goal, Congress did not give each individual
State carte blanche to include whatever emissions limita-
tions it wished in PSD permits, but instead required those
limitations to be based on the “maximum degree of reduc-
tion in each pollutant” that is “achievable,” 42 U.S.C. 717903)
(emphasis added). And it gave EPA enforcement authority
in Sections 113(a)(5) and 167 to protect the national interests
that extend beyond those of any particular State. Compare
Arkansas v. Oklahoma, 503 U.S. 91, 105-107 (1992).
Second, Congress intended that there be a level piaying
field among the States. The House Report on the 1977
amendments explained that “[t]here exists a strong incen-
tive * * * for industry to ‘shop around’ for States or locali-
ties with large clean air resources and weak pollution control
standards.” H.R. Rep. No. 294, supra, at 133. An important
congressional purpose in enacting the PSD pro-
gram—including its BACT requirement—was to limit the
“substantial competitive disadvantage” that could be faced
by other States:
Without national guidelines for the prevention of signifi-
cant deterioration a State deciding to protect its clean air
resources will face a double threat. The prospect is very
real that such a State would lose existing industrial
plants to more permissive States. But additionaliy the
State will likely become the target of ‘economic-envi-
ronmental blackmail’ from new industrial plants that will
play one State off against another with threats to locate
34
in whichever State adopts the most permissive pollution
controls. In other words, without national guidance on
prevention of significant deterioration, the very States
demonstrating a concern for preserving existing clean air
seriously risk having their economic base undermined.
Id. at 134. Congress therefore granted EPA authority to en-
sure that BACT decisions were justifiable.
C. Fetitioner’s Remaining Arguments That A BACT De-
termination Is An Entirely Subjective Or Discretionary
Decision That Is Not Subject To Review Are Mistaken
1. Petitioner argues that its selection of BACT cannot be
reviewed by EPA because Idletermining the ‘best’ control
technclogy is like asking different people to pick the ‘best’
car,” and “[sJubstituting one decisionmaker for another may
yield a different result, but not in any sense a more ‘correct’
one.” Pet. Br. 24. In petitioner’s view, “[bJecause there is no
‘correct’ BACT determination for any particular source, the
EPA cannot conclude that a State failed to include the ‘cor-
rect’ BACT limitation in a PSD permit.” Id. at 24-25.
Petitioner’s claim that there is no “correct” BACT deter-
mination for a particular source may or may not be right, de-
pending on the facts. In this case, for example, it appears
that both petitioner and EPA would agree that there are no
more than two genuine candidates for BACT—Low NOx
and SCR. Depending on the technology involved, there will
likely be cases in which there is only one possibility and
other cases in which there are several more.
In any event, insofar as petitioner’s submission is that a
state agency’s BACT determination can never be said to be
correc: or incorrect, petitioner's own argument that its
BACT determination is subject to review in state court con-
tradicts that submission. According to petitioner (Br. 35),
EPA or any other person could, “if it believed that the State
had failed to adequately justify its final permit decision,
challenge that decision through the State’s [judicial] review
35
process.” Indeed, petitioner argues that “the need [for EPA]
to correct ‘unreasoned’ state determinations * is hardly
compelling, given the availability of state administrative and
judicial review addressed to just that possibility.” Jd. at 36.
Petitioner’s insistence that there could be state-court re-
view of a BACT determination is at war with its core conten-
tion that the determination of the best available control
technology is no more ascertainable than an individual’s per-
sonal taste for one car over another. If a BACT determina-
tion contains the degree of unfettered discretion that peti-
tioner asserts, then state-court review of the determination
would also be doomed. Cf. Heckler v. Chaney, 470 U.S. 821,
830 (1985) (“[I]f no judicially manageable standards are
available for judging how and when an agency should exer-
cise its discretion, then it is impossible to evaluate agency
action for ‘abuse of discretion.’”). The prospect of state judi-
cial review that petitioner holds out would be a chimera. In
fact, however, a number of federal and state courts have re-
viewed BACT determinations that were made by EPA as
permitting authority and by state agencies, and none has
ever suggested that the matter was altogether committed to
the permitting authority’s discretion by law and therefore
unreviewable. Cf. 5 U.S.C. 701(a)(2)."
Thus, petitioner is correct when it argues that a BACT
determination can be arbitrary or otherwise contrary to law
and hence subject to review by another body (state court,
federal court, or EPA), and petitioner is incorrect when it
13 See Northern Plains, 645 F.2d at 1350-1352, 1358-1362 (EPA-issued
permit); Sur Contra La Contaminacion v. EPA, 202 F.3d 443, 418 (Ist
Cir. 2000) (EPA as permitting authority); Citizens for Clean Air v. EPA,
959 F.2d 839 (9th Cir. 1992) (EPA as permitting authority, with State
agency as delegatee); Plumbers & Steamfitters, Local 52 v. Alabama
Dep't of Envtl. Mgmt., 647 So. 2d 793 (Ala. Civ. App. 1994) (state
permitting authority); In re Pennsauken Solid Waste Mgmt. Auth., 569
A.2d 826 (N.J. Super. Ct. App. Div. 1990) (EPA as permitting autnority,
with state agency having been delegated some authority).
36
argues to the contrary that the determination of BACT is so
subjective, discretionary, or indeterminate that it can never
be said to be correct or incorrect. Congress anchored the
BACT requirement in terms—“best available,” “maximum
degree of reduction * * * achievable,” “production proc-
esses” and “techniques * * * for control,” etc.—that impose
substantive limitations on a permitting authority. If a state
permitting authority applies those terms in an unjustifiable
fashion, EPA may invoke-Sections 113(a)(5) and 167.
2. Petitioner’s claim that a determination of BACT is en-
tirely subjective or discretionary is also based on a faulty
understanding of the relationship among the various re-
quirements of the PSD program. To obtain a PSD permit,
the owner of a proposed facility must demonstrate that its
emissions will not “cause, or contribute to” emissions in ex-
cess of an “increment”—a “maximum allowable increase or
maximum allowable concentration for any pollutant.” 42
U.S.C. 7475(a)(3). That “increment” requirement is inde-
pendent of the requirement that the facility be “subject to
the best available control technology for each pollutant.” 42
U.S.C. 7475(a)(4). Accordingly, even if a proposed facility
will not cause emissions in excess of the increments—indeed,
even if all new facilities in the State will indisputably not
cause emissions in excess of the increments—the state
agency must still determine what is the “maximum degree of
reduction of each pollutant * * * achievable” for each indi-
vidual facility and limit its emissions accordingly.
The increment provisions of the Act do place an overall
limit on the number and types of permits a State can grant in
the aggregate. But, contrary to petitioner’s argument that a
State may determine BACT simply by dividing up the allow-
able increments among facilities as it sees fit, see Pet. Br. 17,
24, compliance with the overall increment limitations does
37
not establish that the State has satisfied the separate BAC T
requirement for each facility.“
3. Similarly unsupportive of petitioner’s restrictive
reading of EPA’s oversight authority is Section 165(a)(8) of
the Clean Air Act. See Pet. Br. 25. That provision contains
another PSD permit requirement, one with limited ay plica-
bility to “a source which proposes to construct in a class III
area”—a classification that no State has ever used. 42
U.S.C. 7475(a)(8). That Congress required EPA affirma-
tively to “approve[] the determination” of BACT in a permit
for that discrete subset of new sources (i. e., sources in Class
III areas that pollute in excess of the applicable increment
for Class II areas) before the permit becomes effective does
not mean it intended to bar EPA oversight of BACT
determinations affecting all other clean air areas. Rather, it
was logical for Congress to provide EPA with a general
oversight role with respect to PSD permits while at the
same time to increase the level of oversight, through a
requirement of prior approval, in the special circumstances
in Section 165(a)(8).
4. Petitioner contends (Br. 27) that precluding any sub-
stantive EPA review of a State’s BACT determination
would carry through the “basic division of responsibilities”
between the federal and state governments that this Court
4 Petitioner errs in arguing that BACT determinations are
categorically different from “objective” decisions about whether a facility
will satisfy the increments. Nearly every part of a PSD permit decision
involves the exercise of sometimes complex judgment on the part of the
permitting authority, such as the determination of whether emissions
from the new source would “cause, or contribute” to pollution in excess of
the applicable increment. 42 U.S.C. 7475(a)(3); see 42 U.S.C. 74100)
(owner of facility must show “to the satisfaction of the permitting
authority” that facility will satisfy performance standards, including
increments). Yet it is uncontested that “EPA has authority under the
[Act] to prevent or to correct a violation of the increments.” Alabama
Power, 636 F. ad at 361; Pet. Br. 25.
recognized in Train. That case concerned the limits on a
State’s authority under the Clean Air Act to fashion an im-
plementation plan (SIP) to reach the national ambient air
quality standards that EPA had set. The Court explained
that t he Act gives the [EPA] no authority to question the
wisdom of a State’s choices of emission limitations [in a SIP]
if they are part of a plan which satisfies the [Act’s] stan-
dards.” 421 U.S. at 79. Petitioner argues that a similar prin-
ciple should grant States “sole discretion” (Br. 27) to deter-
mine BACT for a facility.
Even on its own terms, Train does not support peti-
tioner’s argument. Train recognized that, although States
have a primary role in determining how to satisfy national
ambient air quality standards, the EPA retains “a secondary
role in the process of determining and enforcing the specific,
source-by-source emission limitations which are necessary if
the national standards it has set are to be met.” 421 U.S. at
79. It is just such a secondary, backstop role that EPA has
played in this case. Cf. id. at 93-94 n.28 (noting that Con-
gress “charged [EPA] with the administration of the Act{]
and made [it] ultimately responsible for the attainment and
maintenance of the national standards”). That scheme is in
keeping with the plan of “cooperative federalism,” New York
v. United States, 505 U.S. 144, 167-168 (1992), that Congress
put in place in the Clean Air Act. Indeed, it is petitioner’s
view, which would deprive EPA of any significant role in the
BACT process, that violates the principles of cooperative
federalism embodied in the Act.
In any event, Train addressed the provisions of the Act
concerning state plans for implementing national ambient air
quality standards set by EPA and EPA’s ability to review
such plans. See 42 U.S.C. 7410(a)(2). In that context, Con-
gress gave the States substantial discretion to develop their
own mix of emission limitations to meet the EPA-specified
national standards in light of the States’ own “particular
situation{s],” 421 U.S. at 79, while at the same time granting
EPA authority to reject a state plan if the State has acted
outside the range of discretion accorded it by proposing a
plan that does not meet the national standards. This case
concerns entirely different, source-specific requirements of
the Act that were added in 1977, after Train, and bear no
similarity in wording, structure, or context to the provisions
at issue in Train. Nonetheless, the principles of cooperative
federalism play out here as well. In the PSD program,
Congress granted the States substantial latitude to exercise
the judgment necessary to determine BACT under the
governing standards in the Act, while also vesting EPA with
authority in Section 113(a)(5) and Section 167 (which was
especially directed toward the PSD program) to enforce the
BACT requirement in the unusual case in which a State acts
outside the range of permissible judgments. r
5. Finally, petitioner argues (Br. 36) that EPA’s exercise
of authority in this case would “improperly shiftſ] the burden
of persuasion from the EPA to the States,” because federal-
court review of whether EPA’s action is supportable will re-
place state-court review of whether petitioner’s decision was
supportable. Petitioner’s quarrel, however, is not with
EPA’s authority in this case, but with Congress’s decision to
enact Sections 113(a)(5) and 167, and thereby to vest EPA
with oversight authority in cases in which a State has failed
to comply with the Act’s requirements. It naturally follows
from those provisions that there will be at least some cases
in which a state permitting authority’s failure to comply with
the requirements of the Act will be potentially subject to
several alternative avenues of review: (a) review in state
court, (b) exercise by EPA of its authority under Sections
113(a)(5) and 167 to issue a stop-construction order, followed
by federal court review of EPA’s action, or (e) an EPA suit
for injunctive relief directly in federal court under those
same provisions. Congress’s enactment of Sections 113(a)(5)
40
and 167 demonstrates that it specifically intended the latter
two forms of review, and petitioner’s complaints about those
features of the Act should be addressed to Congress.
Petitioner itself acknowledges that such parallel avenues
of review properly may take place under Sections 113(a)(5)
and 167. Petitioner notes that there are “many [Clean Air
Act] requirements, including in the PSD provisions, that the
EPA may enforce pursuant to Sections 113(a)(5) or 167.”
Pet. Br. 23. It is common ground that EPA may act, for ex-
ample, if “the State issued a permit allowing emissions to ex-
ceed available increments,” see Pet. Br. 25, even though de-
cisions about whether a facility will exceed the increments
may involve complex and controversial judgment calls. Peti-
tioner thus acknowledges that in such a case, the state per-
mitting agency’s permit would be reviewable, as here, in al-
ternative ways: either by judicial review in state court, or by
EPA’s exercise of its independent enforcement responsibil-
ity. If such a scheme is workable in the case of a state per-
mit that allows emissions in excess of the allowable incre-
ments, it is equally workable here. Nor is it difficult for a
federal court, reviewing an EPA order, to take into account
that the state permitting authority retains discretion and
that EPA’s action may be sustained only if its determination
that the state agency acted outside its zone of reasonable
discretion is supported. See Pet. App. 10a; cf. Air Line Pi-
lots Ass’n v. ONeill, 499 U.S. 65, 78 (1991) (courts must rec-
ognize “wide range of reasonableness” within which unions
act in evaluating certain duty of fair representation claims).
D. The Court Should Defer To EPA's Interpretation That
It Is A “Requirement” Of The Clean Air Act That States
Make Reasonable BACT Determinations
If there is any doubt about the meaning of the Clean Air
Act in this case, EPA’s construction of the Act to require
permitting authorities to make reasonable BACT determina-
41
tions is entitled to deference under Chevron U.S.A, Inc. v.
NR DC, 467 U.S. 837 (1984). .
1. This Court has “recognized a very good indicator of
delegation meriting Chevron treatment in express congres-
sional authorizations to engage in the process of * * . adju-
dication that produces regulations or rulings for which def-
erence is claimed.” United States v. Mead Corp., 533 U.S.
218, 229 (2001). Just such a delegation is at issue here. EPA
acted in this case pursuant to the express conferral of
authority in Sections 113(a)(5) and 167 to make findings and
issue orders when a State fails to “act[] in compliance with
any requirement” of the Act, 42 U.S.C. 7413(a)(5), or a facil-
ity fails to “conform to the requirements of” the PSD pro-
gram, 42 U.S.C. 7477. Indeed, Congress provided that
States must transmit copies of PSD permit applicaticns to
EPA “and provide notice to [EPA] of every action related to
the consideration of such permit,” 42 U.S.C. 7475(d)(1), in
part so that EPA may effectively exercise its authorit y un-
der Sections 113(a)(5) and 167. Congress necessarily in-
tended that EPA would have to construe and apply the
Clean Air Act in taking action under those express delega-
tions, and EPA’s construction of the Clean Air Act underly-
ing the orders is therefore entitled to Chevron deference.
Moreover, as explained above, see pp. 16-17, supra, EPA's
orders in this case have “the force of law,” a factor that this
Court has found to support Chevron deference for agency
interpretations. Christensen v. Harris County, 529 U.S. 576,
587 (2000); see Mead, 533 U.S. at 230. Those orders are not
analogous to “interpretations contained in policy a en
agency manuals, and enforcement guidelines” that “are be-
yond the Chevron pale.” Mead, 533 U.S. at 234. .
2. EPA’s construction of the Clean Air Act to require
permitting authorities not merely to make some BACT de-
termination, but also to make reasonable BACT determina-
tions, was embodied in the orders in this case. In those or-
42
ders, EPA invoked Sections 113(a)(5) and 167 as the sources
of its authority,” and the orders were based on the premise
that a State’s BACT determination must be reasonable and
supported by the record. See J.A. 150 ( Petitioner's] record
simply does not support its decision that BACT for * * *
MG-17 is low NOx controls rather than SCR.”). Addition-
ally, the administrative record here is replete with EPA’s
interpretation of the scope of Sections 113(a)(5) and 167 as
granting EPA authority to enforce the statutory BACT re-
quirement when state permitting authorities make arbitrary
or unreasoned BACT determinations. J.A. 137, 148-149, 261-
262, 292-293, 295-296, 302. Accordingly, EPA’s construction
of the Act in these orders to require that BACT determina-
tions be reasonable is entitled to Chevron deference.
3. Other factors that this Court has discussed in deciding
whether an agency’s interpretation of a statute is entitled to
Chevron deference are also present here. EPA’s position is
“longstanding” and reflects a “careful consideration * * *
over a long period of time,” Barnhart v. Walton, 122 S. Ct.
1265, 1270, 1272 (2002), and it has remained “consistent{],”
Good Samaritan Hosp. v. Shalala, 508 U.S. 402, 417 (1998).
EPA guidance documents dating from as long ago as 1983
reflect. the same basic interpretation as the Agency em-
ployed here. See p. 29, supra. Moreover, EPA has pre-
sented that same interpretation in notice-and-comment
rulemaking proceedings approving various States’ PSD pro-
grams. See 57 Fed. Reg. 28,095 (1992); 58 Fed. Reg. 10,961
(1993); 63 Fed. Reg. 13,796 (1998). For example, in re-
sponding to comments that Virginia should not receive
EPA’s approval to run a PSD program, EPA assured the
public that “it has a responsibility to insure that all States
properly implement their preconstruction permitting pro-
1 Pet. App. 26a, 29a-30a, 35a-36a (J 1-2, 19-20, 46-47); id. at 38a, 41a-
42a, 47a, 49a ( 1-2, 18-19, 42, 48-50); id. at 5 la, 54a-55a, 60a, 62a (TF 1-2,
18-19, 42, 48, 51-52).
43
grams.” Id. at 13,796. At the same time, however, EPA re-
iterated the need to accord appropriate deference to the
States: “EPA may not intrude upon the significant discretion
granted to states * * * and will not ‘second guess’ state de-
cisions.” Id. at 13,797. As EPA noted, it “will review the
process followed by the permitting authority in determining
[BACT] * * * toensure * * * any determination * * *
was made on reasonable grounds properly supported on the
record.” Ibid.
4. Finally, the Agency’s interpretation addresses an is-
sue within its expertise and one with “importance * * * to
administration of the statute.” Barnhart, 122 S. Ct. at 1272.
The question whether a State’s determinations of the best
available control technology for new facilities are subject to
EPA oversight is not only of great importance to residents
of the State itself. It also is of substantial importance to
residents of neighboring States that may suffer from in-
creased air pollution, and still other States that must com-
pete for new facilities with a State that has adopted an arbi-
trarily lenient standard for BACT. If there is any doubt
whether the Clean Air Act requires that a State make its
BACT determination reasonably, EPA’s construction of the
Act to encompass that requirement should be eonelusive.“
16 This Court has made clear that development of an agency’s views in
a formal rulemaking proceeding is not necessary for Chevron deference.
See, e., Edelman v. Lynchburg Coll., 122 8. Ct. 1145, 1150 (2002); Mead,
533 U.S. at 231. Nor, in the absence of rulemaking, is a formal adjudica-
tion a prerequisite to Chevron deference. See id. at 231-232 & n. 18
(discussing Nations Bank v. Variable Annuity Life Ins. Co., 513 U S. 251,
256-257 (1995). Formal adjudication under 5 U.S.C. 554 and 556 is de-
signed to guarantee certain procedures for the determination of f1cts in
particular types of cases; it does not have a direct bearing on how an
agency interprets applicable law. See also Martin v. OSHRC, 499 U.S.
144, 156-157 (1991) (according deference to interpretation reflected in
administrative complaint). Under the Clean Air Act, Congress has con-
templated that EPA will render decisions on numerous issues without a
44
III. THE COURT OF APPEALS CORRECTLY SUS-
TAINED EPA’S CONCLUSION THAT PETITIONER
— 4 AN UNREASONABLE BAC T DETERMINA-
A. Petitioner argues (Br. 39-48) that even if EPA has
statutory authority to issue a stop-construction order based
on a state permit’s failure to comply with BACT, it erred in
doing so in this case. That issue falls outside the question of
og construction presented in the certiorari petition
et. i):
Whether the Ninth Circuit erred in upholding the EPA’s
assertion of authority to second-guess a permitting deci-
sion made by the State of Alaska—which had been dele-
gated permitting authority under the Clean Air Act, 42
U S.C. §§ 7401 et seg.—in conflict with decisions of this
Court and other federal courts of appeals establishing
the division of federal-state jurisdiction under the Act
and similar statutory programs.
The petition fairly poses the question whether EPA has
statutory authority under Sections 113(a)(5) and 167 to re-
view the substance of state BACT determinations and to act
accordingly. The petition does not, however, present any
question concerning whether, if EPA does have such
authority, it was properly exercised in this case. Although
the petition later, in a single sentence in the “Statement,”
mentions that the court of appeals “went on to hold that the
EPA’s issuance of the orders [in this case] was not arbitrary
or capricious,” Pet. 12, it contains no further mention of that
point. Moreover, it could not fairly be said that EPA’s
analysis of the particular factual record in this case is “in
formal adjudication. See PPG Indus., 446 U.S. at 587-589. But even if
EPA’s interpretation were ineligible for Chevron-level deference, it has
the “power to persuade” under Skidmore v. Swift & Co., 323 U.S. 134, 140
(1944), because of the Agency’s “thoroughness,” “validity of * * * rea-
soning,” and “consistency.”
— — ͤ —œZàqWà242⏑ĩ᷑—
45
conflict with decisions of this Court and other federal courts
of appeals establishing the division of federal-state jurisdic-
tion under the Act and similar statutory programs.” Pet. i.
Accordingly, the question whether EPA’s orders in this par-
ticular case were adequately supported by the record is not
fairly included in the question presented and should not be
addressed by this Court. Lexecon, Inc. v. Milberg Weiss
Bershad Hynes & Lerach, 523 U.S. 26, 42 n.5 (1998).
B. In any event, EPA properly found that petitioner had
not reasonably justified its determination that Low NOx was
the best available control technology for MG-17. See Pet.
App. 18a-16a.
1. The record is uncontradicted that SCR “is the most
stringent control technology available for large diesel-fired
generators,” J.A. 80, and requiring it would result in “the
maximum degree of reduction of” nitrogen oxide. 42 U.S.C.
74793). With SCR, MG-17 would emit only 53 tons of NOx
per year. J. A. 198. It would emit 10 times that level—531
tons per year—under a permit that allowed Low NOx. Ibid.
Petitioner asserts that, “because Cominco had agreed to
install Low NOx on all its generators,” petitioner’s “permit
decision was expected to result in lower overall NOx emis-
sions than would occur if SCR * * * were installed on only
the MG-17 generator.” Pet. Br. 13; see also id. at 4, 42 n.12;
Cominco Br. 4; North Dakota, et al. Amicus Br. 14. That
contention is mistaken, and it is inconsistent with the con-
clusions that petitioner itself reached in issuing the permit.
First, petitioner concluded in its Final Technical Report
that, Jolf the Wartsila generators at the Red Dog Mine, only
unit MG-17 requires BACT,” J.A. 232, and whatever low
emission parts Cominco may install on “existing, unmodified
engines * * * is not a consideration of the BACT review.”
J.A. 199 (emphasis added); see also J.A. 111-112 (same).
That conclusion was correct. The plain terms of the Clean
Air Act require that a State determine and apply the best
46
available control technology for each “major emitting facil-
ity” that is “constructed,” 42 U.S.C. 7475(a)(1). Neither a fa-
cility owner nor a State may avoid the BACT requirement
for a new facility by arguing that some other control tech-
nology will be used on some other facility.
Second, the permit issued by petitioner plainly allows
much greater emissions of nitrogen oxide than a permit re-
quiring the use of SCR on the MG-17 generator. The permit
“retain(ed}” the limit on nitrogen oxide emissions from the
pre-existing generators that had already been imposed in
the operating permits for those generators. J.A. 239. In-
deed, those pre-existing limits had to be retained, without
regard to any BACT determination for any generator, old or
new, so that the facility would not exceed the applicable in-
crements—a requirement that petitioner concedes to be
binding on the States and enforceable by EPA. J. A. 237.
Therefore, Cominco must ensure that the existing genera-
tors remain within the pre-existing limits, regardless of what
pollution control device—Low NOx or SCR—is required on
MG-17. Cominco may of course choose to install Low NOx
on the existing generators in order to increase electricity
production without exceeding the pre-existing limits on
emissions of nitrogen oxide. Nothing in the permit, how-
ever, requires Cominco to do so, much less to reduce their
overall emissions to offset added emissions from MG-17. As
a result, petitioner’s determination that Cominco may use
Low NOx rather than SCR on MG-17 plainly allows sub-
stantially greater emissions from the Red Dog Mine.
2. There is no suggestion in the record that petitioner
should have rejected SCR on account of “energy” or “envi-
ronmental * * impacts.“ 42 U.S.C. 7479(8). See, e. g., J. A.
200-203 (rejecting Cominco’s arguments concerning such im-
pacts); see also Pet. Br. 40 (“ADEC discounted Cominco’s
claim that energy or environmental impacts warranted
eliminating SCR.”). In fact, petitioner specifically rejected
47
Cominco’s efforts to “reduce the stringency of BACT” by re-
liance on the mine’s compliance with other air quality stan-
dards, J.A. 200, and even found that “it is likely that the NOx
emission reductions resulting from [SCR] will improve
workplace conditions.” J.A. 201.
3. Nor does the record on which petitioner’s decision was
based reveal any reasoned basis to conclude that a limitation
based on SCR was not “achievable for such facility” due to
“economic impacts and other costs.” 42 U.S.C. 7479(8).
Petitioner and its engineer initially concluded that SCR was
“economically feasible” for MG-17. J.A. 65. Further evincing
SCR’s economic feasibility is the world-wide pervasiveness
of that technology. See, eg., J.A. 102 (“SCR has been
installed on similar diesel-fired engines throughout the
world.”); J.A. 234 (“The Department has permitted projects
{in Alaska] requiring SCR.”); J. A. 289-291."
Petitioner asserts that its BACT determination was cor-
rect because the cost of SCR—approximately $2,100 per ton
of NOx removed, see J.A. 204—was higher than the cost of
controls in recent BACT determinations it had made of $0 to
$936 per ton of NOx removed. Pet. Br. 40. See J.A. 205-206.
Not even Cominco, however, had placed reliance on those
“installations,” see R. 44- 011, 45-034, 45-043, and petitioner
itself commented that “[t]he cited examples of engines per-
mitted in Alaska without requiring SCR are not valid exam-
17 Because SCR is so pervasive, including in cold climates, petitioner’s
selected excerpts (see Br. 44-45) from EPA’s New Source Review
Workshop Manual do not help its cause. A fair reading of the cited
portion of the guidance is that the more a “control alternative” is “effec-
tively employed in the same source category,” the harder it is generally to
eliminate that level of control on the basis of an “economic impact.” R. 71-
115. That reading is confirmed by petitioner’s own acknowledgment that
Cominco bore the burden of showing “compelling and atypical energy,
environmental, or economic * * * circumstances specific to a facility
that] constrain it from using I] the most effective technology a burden
that Cominco failed to discharge. J.A. 178.
48
ples as they either took place over 18 months ago or were
not used for similar purposes.” J.A. 233-234; see also R. 21-
018 (None of the decisions cited by Cominco are similar to
the case at hand.”).
Moreover, even if the “recent BACT decisions” cited by
petitioner had any instructive value,” the record does not
support petitioner’s dismissal of higher-cost examples within
the State. J.A. 115, 205. As petitioner itself noted with re-
spect to a prior permit decision, “the Yukon Pacific Corpora-
tion permit included a gas/diesel-fired boiler and heaters
with costs at $2,900 and $7,000, respectively, per ton of NOx
removed,” and the estimated cost of SCR for Cominco falls
well below either figure. R. 21-019."
Ultimately, petitioner rested its BACT analysis on an
analogy to rural electric utilities in Alaska. Petitioner stated
that “[iJf [Cominco] did not have a powerhouse, it would
probably buy power from a rural Alaska utility.” J.A. 206.
Petitioner reasoned that, because what it termed a “cursory
review” revealed that the average cost of electricity for such
rural utilities is 15 cents per kilowatt hour and the use of
SCR would increase that by 3 cents, SCR “would be equiva-
lent to a 20% increase in the electric rate of the facility.”
J.A. 206. Petitioner concluded that “this is a disproportion-
ate cost increase when viewed as an electric utility.” J.A.
206 (emphasis added). Cominco, however, is not a rural util-
18 Because the record does not reveal the dates of those BACT
decisions, it is not clear whether they have any precedential relevance.
See R. 22-031 to 22-033. As petitioner itself noted, “18 months is the time-
frame over which BACT decisions are rendered stale under both state and
federal PSD regulations.” R. 21-014. Relying on other BACT decisions
standing alone is also problematic because, as both EPA and petitioner
pointed out, cost-effectiveness is not always calculated or published. See
J. A. 127, 205.
10 While this analysis is from an internal memorandum, petitioner
incorporated that analysis by reference into its final response to com-
ments. See J.A. 236 n.31.
49
ity and it does not compete with rural utilities. Moreover,
the economic impact of a requirement that a rural Alaska
utility use SCR on a new generator could be far different
than the economic impact of a requirement that Cominco do
so on the new generator at its mine. Indeed, no facts exist to
suggest that the “economic impact[]” of the incrementally
higher cost of SCR on the world’s largest producer of zinc
concentrates would be anything like its impact on a rural,
non-profit utility that must pass costs on to a small base of
individual consumers. 42 U.S.C. 7479(8); J. A. 116, 207.
4. The best demonstration that petitioner unreasonably
selected Low NOx over SCR for MG-17 is found in its own
final BACT determination:
The Red Dog Mine plays a unique and continuing impact
on the economic diversity of this region. Therefore, the
Department has chosen to consider the direct cost of
SCR technology and its relationship to retaining the
Mine’s world competitiveness as it relates to community
socioeconomic impacts for the foremost consideration to
judge economic impacts of SCR. To support Cominco’s
Red Dog Mine Production Rate Increase Project, and its
contributions to the region, the Department has rejected
Selective Catalytic Reduction controls based on exces-
sive economic cost * * *.
J.A. 208. Assuming that “retaining the Mine’s world com-
petitiveness as it relates to community socioeconomic im-
pacts” could properly be the “foremost consideration” in pe-
titioner’s BACT determination, the record provides nc sup-
port whatever for the proposition that requiring the use of
SCR would either affect the “Mine’s world competitiveness”
or have significant “community socioeconomic impacts.” Pe-
titioner acknowledged that, although the “better way to de-
termine if the cost of BACT is excessive” would be “for the
applicant to present detailed financial information showing
its effect on the operation,” Cominco “did not present this
50
information.” J.A. 207. Petitioner therefore acknowledged
that “no judgment can be made as to the impact of [the costs
of SCR] on the operation, profitability, and competitiveness
of the Red Dog Mine.” J.A. 207.” If it was impossible to
make a judgment about the effect of requiring SCR on the
“operation, profitability, and competitiveness” of the mine, it
was also impossible to make a resulting judgment about its
effect on the mine’s “world competitiveness” or local “socio-
economic impact(].” J. A. 207. Petitioner could not possibly
have articulated a “rational connection between the facts
found and the choice made” because Cominco did not provide
the requisite “facts” to depart from the “maximum degree of
[NOx] reduction.” 42 U.S.C. 7479(3); Motor Vehicle Mfrs.
Ass’n v. State Farm Mut. Ins. Co., 463 U.S. 29, 43 (1983) (ei-
tation omitted).
As the court of appeals appropriately observed, peti-
tioner’s BACT decision underscores one of the reasons why
Congress intended EPA to have oversight authority-—“to
protect states from industry pressure to issue ill-advised
permits.” Pet. App. 16a. Based on this “available informa-
tion” from the record, 42 U.S.C. 7413(a)(5), EPA acted rea-
sonably in issuing the finding of noncompliance to petitioner
and the administrative orders to Cominco to prevent the
construction of a major new source of air pollution.
CONCLUSION
The judgment of the court of appeals should be affirmed.
Respectfully submitted.
2 Petitioner cannot now suggest that it considered Cominco’s bare
assertion of an impact to be sufficient (Pet. Br. 41); it contemporaneously
stressed an inability “to verify [the] claim.” R. 22-002. Additionally, while
the Red Dog Mine is an important employer in the region (Pet. Br. 9, 10,
46), there is no record evidence that requiring SCR would compromise
even a single job.
ROBERT E. FABRICANT
General Counsel
CAROL S. HOLMES
JULIANE R.B. MATTHEWS
Attorneys
Environmental Protection
Agency
JULY 2003
THEODORE B. OLSON
Solicitor General
KELLY A. JOHNSON
Acting Assistant Attorney
General
EDWIN S. KNEEDLER
Deputy Solicitor Generul
JAMES A. FELDMAN
Assistant to the Solicitor
General
ANDREW J. DOYLE
Attorney
1. Section 101 of the Clean Air Act, 42 U.S.C. 7401,
provides in relevant part:
§ 7401. Congressional findings and declaration of
purpose
(a) Findings
The Congress finds—
(3) that air pollution prevention (that is, the
reduction or elimination, through any measures, of the
amount of pollutants produced or created at the source)
and air pollution control at its source is the primary
responsibility of States and local governments; and
(4) that Federal financial assistance and leadership is
essential for the development of cooperative Federal,
State, regional, and local programs to prevent and ccntrol
air pollution.
(b) Declaration
The purposes of this subchapter are—
(1) to protect and enhance the quality of the Nation’s
air resources so as to promote the public health and
welfare and the productive capacity of its population;
* * * * *
(c) Pollution prevention
A primary goal of this chapter is to encourage or
otherwise promote reasonable Federal, State, and local
governmental actions, consistent with the provisions of this
chapter, for pollution prevention.
(la)
2a
2. Section 107 of the Clean Air Act, 42 U.S.C. 7407,
provides in relevant part:
§ 7407. Air quality control regions
(a) Responsibility of each State for air quality;
submission of implementation plan
Each State shall have the primary responsibility for
assuring air quality within the entire geographic area
comprising such State by submitting an implementation plan
for such State which will specify the manner in which
national primary and secondary ambient air quality
standards will be achieved and maintained within each air
quality control region in each State.
(d) Designations
(1) Designations generally
(A) Submission by Governors of initial designa-
tions following promulgation of new or re-
vised standards
By such date as the Administrator may reasonably
require, * * * the Governor of each State shall (and at
any other time the Governor of a State deems appropri-
ate the Governor may) submit to the Administrator a
list of all areas (or portions thereof) in the State,
designating as—
(i) nonattainment, any area that does not
meet (or that contributes to ambient air quality in
a nearby area that does not meet) the national
primary or secondary ambient air quality stan-
dard for the pollutant,
(ii) attainment, any area (other than an area
identified in clause (i)) that meets the national
3a
primary or secondary ambient air quality
standards for the pollutant, or
(iii) unclassifiable, any area that cannot be
classified on the basis of available information as
meeting or not meeting the national primary or
secondary ambient air quality standard for the
pollutant.
* * * * *
(B) Promulgation by EPA of designations
() * * [Tze Administrator shall promul-
gate the designations of all areas (or portions
thereof) submitted under subparagraph (A) as
expeditiously as practicable * * * *
(ii) In making the promulgations required
under clause (i), the Administrator may make
such modifications as the Administrator deems
necessary to the designations of the areas (or
portions thereof) submitted under subparagraph
(A) (including to the boundaries of such areas or
portions thereof). * * * *
8 Section 110 of the Clean Air Act, 42 U.S.C. 7410,
provides in relevant part:
§ 7410. State implementation plans for national pri-
mary and secondary ambient air quality stan-
dards
(a) Adoption of plan by State; submission to —
strator; content of plan; revision; new sources;
indirect source review program; supplemental or
intermittent control systems
(1) Each State shall * * * adopt and submit to the
Administrator * * * a plan which provides for imple-
da
mentation, maintenance, and enforcement of such primary
standard in each air quality control region (or portion
thereof) within such State. In addition, such State shall
adopt and submit to the Administrator * * * a plan which
provides for implementation, maintenance, and enforcement
of such secondary standard in each air quality control region
(or portion thereof) within such State. * * * *
(2) * * * * Each such plan shall —
(A) include enforceable emission limitations and other
control measures, means, or techniques as may be
necessary or appropriate to meet the applicable
requirements of this chapter; * * *
(C) include a program to provide for the enforcement
of the measures described in subparagraph (A), and
regulation of the modification and construction of any
stationary source within the areas covered by the plan as
necessary to assure that national ambient air quality
standards are achieved, including a permit program as
required in parts C and D of this subchapter; * * * *
* * * * *
(c) Preparation and publication by Administrator of
proposed regulations setting forth implementa-
tion plan; transportation regulations study and
report; parking surcharge; suspension authority;
plan implementation
(1) The Administrator shall promulgate a Federal
implementation plan at any time within 2 years after the
Administrator —
(A) finds that a State has failed to make a required
submission or finds that the plan or plan revision
submitted by the State does not satisfy the minimum
5a
criteria established under subsection (k)1)(A) of this
section, or
(B) disapproves a State implementation plan sub-
mission in whole or in part,
unless the State corrects the deficiency, and the Admini-
strator approves the plan or plan revision, before the Ad-
ministrator promulgates such Federal implementation plan.
* * * * *
(j) Technological systems of continuous emission
reduction on new or modified stationary sources;
compliance with performance standards
As a condition for issuance of any permit required under
this subchapter, the owner or operator of each new or
modified stationary source which is required to obtain such a
permit must show to the satisfaction of the permitting
authority that the technological system of continuous emis-
sion reduction which is to be used will enable such source to
comply with the standards of performance which are to
apply to such source and that the construction or modifi-
cation and operation of such source will be in compliance
with all other requirements of this chapter.
4. Section 113 of the Clean Air Act, 42 U.S.C. 7413,
provides in relevant part:
§ 7413. Federal Enforcement
(a) In general
(1) Order to comply with SIP
Whenever, on the basis of any information available to
the Administrator, the Administrator finds that any person
has violated or is in violation of any requirement or pro-
hibition of an applicable implementation plan or permit, the
Administrator shall notify the person and the State in which
6a
the plan applies of such finding. At any time after the
expiration of 30 days following the date on which such notice
of a violation is issued, the Administrator may * * *
(A) issue an order requiring such person to
comply with the requirements or prohibitions of such
plan or permit,
(B) issue an administrative penalty order in
accordance with subsection (d) of this section, or
(C) bring a civil action in accordance with sub-
section (b) of this section.
(2) State failure to enforce SIP or permit program
Whenever, on the basis of information available to the
Administrator, the Administrator finds that violations of an
applicable implementation plan or an approved permit
program under subchapter V of this chapter are so wide-
spread that such violations appear to result from a failure of
the State in which the plan or permit program applies to
enforce the plan or permit program effectively, the
Administrator shall so notify the State. * During the
period beginning with such public notice and ending when
such State satisfies the Administrator that it will enforce
such plan or permit program (hereafter referred to in this
section as “period of federally assumed enforcement”), the
Administrator may enforce any requirement or prohibition
— such plan or permit program with respect to any person
—
(A) issuing an order requiring such person to
comply with such requirement or prohibition,
(B) issuing an administrative penalty order in
accordance with subsection (d) of this section, or
7a
(C) bringing a civil action in accordance with
subsection (b) of this section.
(3) EPA enforcement of other requirements
Except for a requirement or prohibition enforceable
under the preceding provisions of this subsection, whenever,
on the basis of any information available to the Admini-
strator, the Administrator finds that any person has
violated, or is in violation of, any other requirement or pro-
hibition of this subchapter, section 7603 of this title, sub-
chapter IV-A, subchapter V, or subchapter VI of this
chapter, including, but not limited to, a requirement or pro-
hibition of any rule, plan, order, waiver, or permit pro-
mgulated, issued, or approved under those provisions or
subchapters, * * * the Administrator may—
(A) issue an administrative penalty or‘er in accor-
dance with subsection (d) of this section,
(B) issue an order requiring such person to comply
with such requirement or prohibition,
(C) bring a civil action in accordance with subsection
(b) of this section or section 7605 of this title, or
(D) request the Attorney General to commence a
criminal action in accordance with subsection (c) of this
section.
(4) Requirements for orders
An order issued under this subsection * * * shall not
take effect until the person to whom it is issued has had an
opportunity to confer with the Administrator concerning the
alleged violation. A copy of any order issued under this
subsection shall be sent to the State air pollution control
agency of any State in which the violation occurs. Any order
issued under this subsection shall state with reasonable
8a
specificity the nature of the violation and specify a time for
compliance which the Administrator determines is reason-
able, taking into account the seriousness of the violation and
any good faith efforts to comply with applicable require-
ments. * * * * No order issued under this subsection shall
prevent the State or the Administrator from assessing any
penalties nor otherwise affect or limit the State’s or the
United States authority to enforce under other provisions of
this chapter, nor affect any person’s obligations to comply
with any section of this chapter or with a term or condition
of any permit or applicable implementation plan promul-
gated or approved under this chapter.
(5) Failure to comply with new source requirements
Whenever, on the basis of any available information, the
Administrator finds that a State is not acting in compliance
with any requirement or prohibition of the chapter relating
to the construction of new sources or the modification of
existing sources, the Administrator may-
(A) issue an order prohibiting the construction or
modification of any major stationary source in any area to
which such requirement applies;
(B) issue an administrative penalty order in accor-
dance with subsection (d) of this section, or
(C) bring a civil action under subsection (b) of this
section.
Nothing in this subsection shall preclude the United States
from commencing a criminal action under subsection (c) of
this section at any time for any such violation.
(b) Civil judicial enforcement
The Administrator shall, as appropriate, in the case of
any person that is the owner or operator of an affected
9a
source, a major emitting facility, or a major stationary
source, and may, in the case of any other person, commence a
civil action for a permanent or temporary injunction, or to
assess and recover a civil penalty or not more than $25,000
per day for each violation, or both, in any of the following
instances:
(1) Whenever such person has violated, or is in vio-
lation of, any requirement or prohibition of an applicable
implementation plan or permit. * * * *
(2) Whenever such person has violated, or is in
violation of, any other requirement or prohibition of this
subchapter * * * including, but not limited to, a
requirement or prohibition of any rule, order, waiver, or
permit promulgated, issued, or approved under this
chapter * * * *
(3) Whenever such person attempts to construct or
modify a major stationary source in any area with repect
to which a finding under subsection (a)(5) of this section
has been made.
Any action under this subsection may be brought in the
district court of the United States for the district in which
the violation is alleged to have occurred, or is occurring, or i
which the defendant resides, or where the defendant’s
principal place of business is located, and such court shall
have jurisdiction to restrain such violation, to require
compliance, to assess such civil penalty, * * * and to award
any other appropriate relief. Notice of the commencement of
such action shall be given to the appropriate State air
pollution control agency. * * * *
* * * * *
10a
(e) Penalty assessment criteria
(1) In determining the amount of any penalty to be
assessed under this section or section 7604(a) of this title, the
Administrator or the court, as appropriate, shall take into
consideration (in addition to such other factors as justice
may require) the size of the business, the economic impact of
the penalty on the business, the violator’s full compliance
history and good faith efforts to comply, the duration of the
violation as established by any credible evidence * * *,
payment by the violator of penalties previously assessed for
the same violation, the economic benefit of noncompliance,
and the seriousness of the violation. * * * *
5. Section 116 of the Clean Air Act, 42 U.S.C. 7416,
provides:
§ 7416. Retention of State authority.
Except as otherwise provided in sections 1857c-10(c), (e),
and (f) (as in effect before August 7, 1977), 7543, 7545(c)(4),
and 7573 of this title (preempting certain State regulation of
moving sources) nothing in this chapter shall preclude or
deny the right of any State or political subdivision thereof to
adopt or enforce (1) any standard or limitation respecting
emissions of air pollutants or (2) any requirement respecting
control or abatement of air pollution; except that if an
emission standard or limitation is in effect under an
applicable implementation plan or under section 7411 or
section 7412 of this title, such State or political subdivision
may not adopt or enforce any emission standard or limitation
which is less stringent than the standard or limitation under
such plan or section.
lla
6. Section 160 of the Clean Air Act, 42 U.S.C. 7470,
provides:
§ 7470. Congressional declaration of purpose
The purposes of this part [Part C—Prevention of
Significant Deterioration of Air Quality] are as follows:
(1) to protect public health and welfare from any actual or
potential adverse effect which in the Administrator’s
judgment may reasonably be anticipate [sic] to occur from
air pollution or from exposures to pollutants in other media,
which pollutants originate as emissions to the ambient air{],
notwithstanding attainment and maintenance of all national
ambient air quality standards;
(2) preserve, protect, and enhance the air quality in
national parks, national wilderness areas, national monu-
ments, national seashores, and other areas of special national
or regional natural, recreational, scenic , or historic value;
(3) to insure that economic growth will occur in a manner
consistent with the preservation of existing clean air re-
sources;
(4) to assure that emissions from any source in any State
will not interfere with any portion of the applicable imple-
mentation plan to prevent significant deterioration of air
quality for any other State; and
(5) to assure that any decision to permit increased air
pollution in any area to which this section applies is made
only after careful evaluation of all the consequences of such a
decision and after adequate procedural opportunities for
informed public participation in the decisionmaking process.
12a
7. Section 161 of the Clean Air Act, 42 U.S.C. 7471,
provides:
§ 7471. Plan requirements
In accordance with the policy of section 7401(b)(1) of this
title, each applicable implementation plan shall contain
emission limitations and such other measures as may be
necessary, as determined under regulations promulgated
under this part, to prevent significant deterioration of air
quality in each region (or portion thereof) designated
pursuant to section 7407 of this title as attainment or
unclassifiable.
8. Section 162 of the Clean Air Act, 42 U.S.C. 7472,
provides in relevant part:
§ 7472. Initial classifications
* * * * *
(b) Areas designated as class II
All areas in such State designated pursuant to section
7407(d) of this title as attainment or unclassifiable which are
not established as class I under subsection (a) of this section
shall be class II areas unless redesignated under section 7474
of this title.
9. Section 165 of the Clean Air Act, 42 U.S.C. 7475(a),
provides in relevant part:
§ 7475. Preconstruction requirements
(a) Major emitting facilities on which construction is
commenced
No major emitting facility * * * may be constructed in
any area to which this part applies unless-
(1) a permit has been issued for such proposed
facility in accordance with this part setting forth emission
13a
limitations for such facility which conform to the
requirements of this part;
(2) the proposed permit has been subject to a
review in accordance with this section, the required
analysis has been conducted in accordance with
regulations promulgated by the Administrator, and a
public hearing has been held with opportunity for
interested persons including representatives of the
Administrator to appear and submit written or oral
presentations on the air quality impact of such source,
alternatives thereto, control technology requirements,
and other appropriate considerations;
(3) the owner or operator of such facility demon-
strates, as required pursuant to section 7410(j) of this
title, that emissions from construction or operation of such
facility will not cause, or contribute to, air pollution in
excess from construction or operation of such facility will
not cause, or contribute to, air pollution in excess of any
(A) maximum allowable increase or maximum allowable
concentration for any pollutant in any area to which this
part applies more than one time per year, (B) national
ambient air quality standard in any air quality control
region, or (C) any other applicable emission standard or
standard of performance under this chapter;
(4) the proposed facility is subject to the best
available control technology for each pollutant subject to
regulation under this chapter emitted from, or which
results from, such facility;
(5) the provisions of subjection (d) of this section
with respect to protection of class I areas have been
complied with for such facility;
14a
. (6) there has been an analysis of any air quality
impacts projected for the area as a result of growth
associated with such facility;
(7) the person who owns or operates, or proposes to
own or operate, a major emitting facility for which a
permit is required under this part agrees to conduct such
monitoring as may be necessary to determine the effect
which emissions from any such facility may have, or is
having, on air quality in any area which may be affected
by emissions from such source; and
(8) in the case of a source which proposes to
construct in a class III area, emissions from which would
cause or contribute to exceeding the maximum allowable
increments applicable in a class II area and where no
standard under section 7411 of this title has been
promulgated subsequent to August 7, 1977, for such
source category, the Administrative has approved the
determination of best available control technology as set
forth in the permit.
(c) Permit applications
Any completed permit application under section 7410 of
this title for a major emitting facility in any area to which
this part applies shall be granted or denied not later than one
year after the date of filing of such completed application.
(d) Action taken on permit applications; notice;
adverse impact on air quality related values;
variance; emission limitations
(1) Each State shall transmit to the Administrator a
copy of each permit application relating to a major emitting
facility received by such State and provide notice to the
— ——
15a
Administrator of every action related to the consideration of
such permit.
(2(A) The Administrator shall provide notice of the
permit application to the Federal Land Manager and the
Federal official charged with direct responsibility for
management of any lands within a class I areas which may
be affected by emissions from the proposed facility.
(B) The Federal Land Manager and the Federal official
charged with direct responsibility for management of such
lands shall have an affirmative responsibility to protect the
air quality related values (including visibility) of such lands
within a class I area and to consider, in consultation with the
Administrator, whether a proposed major emitting facility
will have an adverse impact on such values.
(Cy i) In any case where the Federal official charged with
direct responsibility for management of any lands within a
class I area or the Federal Land Manager of such lands, or
the Administrator, or the Governor of an adjacent State
containing such a class I area files a notice alleging that
emissions from a proposed major emitting facility may cause
or contribute to a change in the air quality in such area and
identifying the potential adverse impact of such change, a
permit shall not be issued unless the owner or operator of
such facility demonstrates that emissions of particular
matter and sulfur dioxide will not cause or contribute to con-
centrations which exceed the maximum allowable increases
for a class I area.
(ii) In any case where the Federal Land Manager
demonstrates to the satisfaction of the State that the emis-
sions from such facility will have an adverse impact on the
air quality-related values (including visibility) of such lands,
notwithstanding: the face that the change in air quality
resulting from emissions from such facility will not cause or
16a
contribute to concentrations which exceed the maximum
allowable increases for a class I area, a permit shall not be
issued.
(iii) In any case where the owner or operator of such
facility demonstrates to the satisfaction of the Federal Land
Manager, and the Federal Land Manager so certifies, that
the emissions from such facility will have no adverse impact
on the air quality-related values of such lands (including
visibility), notwithstanding the fact that the change in air
quality resulting from emissions from such facility will cause
or contribute to concentrations which exceed the maximum
allowable increases for class I areas, the State may issue a
permit.
10. Section 167 of the Clean Air Act, 42 U.S.C. 7477,
provides:
§ 7477. Enforcement
The Administrator shall, and a State may, take such
measures, including issuance of an order, or seeking
injunctive relief, as necessary to prevent the construction or
modification of a major emitting facility which does not
conform to the requirements of this part, or which is
proposed to be constructed in any area designated pursuant
to section 7407(d) of this title as attainment or unclassifiable
and which is not subject to an implementation plan which
meets the requirements of this part.
11. Section 169 of the Clean Air Act, 42 U.S.C. 7479,
provides in relevant part:
§ 7479. Definitions
-For purposes of this part —
17a
(3) the term “best available control technology” means an
emission limitation based on the maximum degree of
reduction of each pollutant subject to regulation under this
chapter emitted from or which results from any major
emitting facility, which the permitting authority, on a case-
by-case basis, taking into account energy, environmental,
and economic impacts and other costs, determines is achiev-
able for such facility through application of production
processes and available methods, systems, and techniques,
including fuel cleaning, clean fuels, or treatment or innova-
tive fuel combustion techniques for control of each such
pollutant. In no event shall application of “best available
control technology” result in emissions of any pollutants
which will exceed the emissions allowed by any applicable
standard established pursuant to section 7411 or 7412 of this
title. Emissions from any source utilizing clean fuels, or any
other means, to comply with this paragraph shall not be
allowed to increase above levels that would have been
required under this paragraph as it existed prior to enact-
ment of the Clean Air Amendments of 1990.
12. Section 7607(b) of the Clean Air Act, 42 U.S.C.
7607(b), provides in pertinent part:
(b) Judicial review
(1) * * * A petition for review of the Administrator’s
action in approving or promulgating any implementation
plan under section 7410 of this title or section 7411(d) of this
title, any order under section 7411(j) of this title, under
section 7412 of this title, under section 7419 of this title, or
under section 7419 of this title, or under section 7420 of this
title, or his action under section 1857c-10(c)(2)(A), (B), or (C)
of this title (as in effect before August 7, 1977) or under
regulations thereunder, or revising regulations for enhanced
monitoring and compliance certification programs under
section 7414(a)(3) of this title, or any other final action of the
18a
Administrator under this chapter (including any denial or
disapproval by the Administrator under subchapter I of this
chapter) which is locally or regionally applicable may be filed
only in the United States Court of Appeals for the
appropriate circuit.* * *
(2) Action of the Administrator with respect to which
review could have been obtained under paragraph (1) shall
not be subject to judicial review in civil or criminal pro-
ceedings for enforcement. * * *
This is a copy of a public record, reproduced as it was published. It is not legal advice, and it may not be the version a court would rely on. Check the official source before you cite it.