Petition for Writ of Certiorari — Alaska Dept. of Environmental Conservation v. EPA
Supreme Court brief2004
Ask Donna
What actually matters in this document.
Text
Supreme Court. US
FILED
No. 02- 02 658 ocr 25 2002
OFFICE OF THE CLERK
IN THE
Supreme Court of the Gnited States
STATE OF ALASKA, DEPARTMENT OF ENVIRONMENTAL
CONSERVATION,
Petitioner,
v.
UNITED STATES ENVIRONMENTAL PROTECTION AGENCY, ef al.,
Respondents.
Petition for a Writ of Certiorari to the
United States Court of Appeals
for the Ninth Circuit
PETITION FOR A WRIT OF CERTIORARI
BRUCE M. BOTELHO JOHN G. ROBERTS, JR.*
Attorney General LORANE F. HEBERT
STATE OF ALASKA HOGAN & HARTSON L.L.P.
Department of Law 555 Thirteenth Street, N.W.
P.O. Box 110300 Washington, D.C. 20004
Juneau, Alaska 99811 (202) 637-5810
(907) 465-3600
CAMERON M. LEONARD
Assistant Attorney General
STATE OF ALASKA
Department of Law
100 Cushman Street, Suite 400
Fairbanks, Alaska 99701
(907) 451-2811
* Counsel of Record Counsel for Petitioner
WILSON-EPES PRINTING CO., INC. — (202) 789-0096 -— WASHINGTON, D. C. 20001
a
QUESTION PRESENTED
Whether the Ninth Circuit erred in upholding the EPA’s
assertion of authority to second-guess a permitting decision
made by the State of Alaska—which had been delegated
permitting authority under the Clean Air Act, 42 U.S.C.
§§ 7401 et seqg.—in conflict with decisions of this Court and
other federal courts of appeals establishing the division of
federal-state jurisdiction under the Act and similar statutory
programs.
(i)
li
PARTIES TO THE PROCEEDING
_ The State of Alaska, Department of Environmental Con-
servation, and Teck Cominco Alaska, Inc. were petitioners in
the Ninth Circuit below. The United States Environmental
Protection Agency (“EPA”), and Carol M. Browner and
Chuck Clarke in their official capacities as Administrator of
the EPA and Regional Administrator of the EPA’s Region
10, respectively, were originally named as respondents
below. Ms. Browner and Mr. Clarke have since been suc-
ceeded by Christie Whitman and L. John Iani, respectively.
ill
TABLE OF CONTENTS
QUESTION PRESENTED ...........ccccsscseeseeseeeserseeeseneenes
PARTIES TO THE PROCEEDING .............ccccececeeeeeeees
TABLE OF AUTHORITIEG............ccccccccesseeseeeeeeeeneeneees
REASONS FOR GRANTING THE WRIT..................-..
I. THE NINTH CIRCUIT’S DECISION
CONFLICTS WITH DECISIONS OF THIS
COURT AND OTHER FEDERAL
COURTS OF APPEALS ON THE
ALLOCATION OF FEDERAL-STATE
II. THE CONFLICT OVER FEDERAL -
STATE AUTHORITY IS A RECURRING
ISSUE OF NATIONAL IMPORTANCE ...........
IY cesencesenscnssscnenseccscrsseevssnsessensceseesssesssecosseees
Page
iV
TABLE OF CONTENTS—Continued
APPENDICES
Appendix A:
Appendix B:
Opinion of the United States
Court of Appeals for the Ninth
Circuit (July 30, 2002)...........0000000
Opinion of the United States
Court of Appeals for the Ninth
Circuit (Mar. 27, 2001)...........0cce00e0
: Order of the United States Court
of Appeals for the Ninth Circuit
Oe
: EPA Finding of Noncompliance
and Order (Dec. 10, 1999)................
Page
v
TABLE OF AUTHORITIES
Page
CASES:
Alabama Power Co. v. Costle, 636 F.2d 323
IEE ME TE ccnsseneneennsniiennenemmmeneemenn 16, 17, 19-20
American Corn Growers Ass'n v. EPA, 291
soo, 4 | 15, 16
Bethlehem Steel Corp. v. Gorsuch, 742 F.2d
0. De 18, 19
Florida Power & Light Co. v. Costle, 650 F.2d
een 17, 18, 19
General Motors Corp. v. United States, 496
ee 4-5
Michigan v. EPA, 268 F.3d 1075 (D.C. Cir.
ee Eee 3
New York v. United States, 505 U.S. 144 (1992).......... 22
Russello v. United States, 464 U.S. 16 (1983)............. 14
Train v. Natural Resources Defense Council,
Rig Ge Ces Gi acter, passim
Union Elec. Co. v. EPA, 427 U.S. 246 (1976)............. 15
United States v. AM General Corp., 34 F.3d 472
eR 19
Virginia v. EPA, 108 F.3d 1397 (D.C. Cir.),
modified, 116 F.3d 499 (1997) ........ccccccccseeeesneeeees 16, 17
Whitman v. American Trucking Ass ‘ns, 531 U.S.
SF Ge cccrcmenntmmenineeinemmnts 11
vi
TABLE OF AUTHORITIES—Continued
Page
STATUTES:
16 U.S.C. §§ 3101 ef SG. ..ccccccccssssscccsssssssesessssssceseeeeee 22
8 ERIS AC ee 2
29 U.S.C. §§ 651 ef 8G. cccccccsccssscsssssssssssvessseesesssssseceees 22
33 U.S.C. §§ 1251 ef 8G. coccccccssscccsssssssssssesssesssssssseceees 22
re 22
42 U.S.C. §§ 7401 ef $€q. .ccccsccccsssccvsssssssscesssssssecesseeee 2
42 U.S.C. § 7401 (a)(3) .aassccccccccsssssssssvcvssesseesesessssssssee 5
FEE Ee a 5
42 U.S.C. § 7407(d)(1(A)(Gi) -cccccscccccccecsccccsssssseceeeeceen 5
iar iar tities 5
TES eae Ee 5
42 U.S.C. § 7410(a)(2)(C).ecccccccscssvvccecescsscessssssseeceecenes 5
EN Aa a ce 5
42 U.S.C. § 7410(C)(3) voccccccccsccosssssvsssseesesseessssssueeeeeeene 5
i iiitticntinceictntitecs 14
cr 10
a ne eR 5
TEE AT ANE Seed 5
irs ciincicncatniiidaiioeneneainanees 5
42 U.S.C. § 7475(a)ccccccccccccessssssssssssssssssseesseesessssssuvcceee 5
42 U.S.C. § 7475(a)(2) cevvecccccvvcesccssvessessssessessseesessnecesen 19
vii
TABLE OF AUTHORITIES—Continued
Page
STATUTES:
42 U.S.C. § 7475(a)(3) .cccvececccsccesccsscesssssucsessuecessneesesness 13
42 U.S.C. § 7475(a)(4) .ccccccccccvecsscsssessssssecsessseeeessees 2, 3, 6, 11
ee Oe Pr airerrcrerncnisnernsnemnenssnmmntnenmesine 14
ee Oe BN tniisineteneininnicenensenennnmennenmnennnnes 10
a ae passim
42 U.S.C. § T491(D) 2A) .....cececccscseceesesceseeeeneeneeeenees 15, 21
Se ae 0 eR ccrcceneRreninnmncmetinmmnnnnion 15, 21
Se Oe He itetetncnntinmmniinnmens 21
i 0 Se citcternccinicenenscncncmincientenenmeenensen 21
42 U.S.C. § T6O7(D)(1) .cscccecccsscesscsssvecsscsssecsssssueessssvecen 2,15
BULB, 6 FEI ccccccscccnccscsscesesccnsssescssssscssees 21
es Oe Pe PD cirrrecerinicnsensccrenenineinnesmmntiioanes 6
Alaska Stat. § 46.14.200............. euiusienapusenstonenenseninitettsions 19
18 Alaska Admin. Code § 50.310(d)(3) .............cccc000 6
18 Alaska Admin. Code § 50.315 .........cccccccccceseeeeseenees 19
LEGISLATIVE MATERIAL:
a eS CPO entnenereneenaniennnnmennnens passim
IN THE
Supreme Court of the Anited States
No. 02-
STATE OF ALASKA, DEPARTMENT OF ENVIRONMENTAL
CONSERVATION,
Petitioner,
Vv.
UNITED STATES ENVIRONMENTAL PROTECTION AGENCY, ef al.,
Respondents.
Petition for a Writ of Certiorari to the
United States Court of Ay peals
for the Ninth Circuit
PETITION FOR A WRIT OF CERTIORARI
Petitioner State of Alaska, Department of Environmental
Conservation (“ADEC”) respectfully petitions this Court for
a writ of certiorari to review the judgment of the United
States Court of Appeals for the Ninth Circuit in this case.
OPINIONS BELOW
The opinion of the Ninth Circuit is reported at 298 F.3d
814 and reproduced in the appendix hereto (“App.”) at la.
The Ninth Circuit’s prior opinion concluding that it had
jurisdiction over this case is reported at 244 F.3d 748 and
reproduced at App. 17a. The Ninth Circuit’s order request-
2
ing supplemental briefing is reproduced at App. 24a. The
orders of the United States Environmental Protection Agency
(“EPA”) are reproduced at App. 26a, 38a, and 51a.
JURISDICTION
The judgment of the Ninth Circuit was entered on July 30,
2002. App. la. The jurisdiction of the Ninth Circuit was
based on 42 U.S.C. § 7607(b)(1). The jurisdiction of this
Court is invoked under 28 U.S.C. § 1254(1).
STATUTORY PROVISIONS INVOLVED
Section 165(a)(4) of the Clean Air Act (“CAA”), 42 U.S.C.
§§ 7401 et seq., provides, in pertinent part:
(a) Major emitting facilities on which construction is
commenced. No major emitting facility on which con-
struction is commenced after August 7, 1977, may be
constructed in any area to which this part applies
unless—
(4) the proposed facility is subject to the best avail-
able control technology for each pollutant subject to
regulation under this Act emitted from, or which results
from, such facility * * *. [42 U.S.C. § 7475(a)(4).]
Section 169(3) of the CAA provides, in pertinent part:
(3) The term “best available control technology” means
an emission limitation based on the maximum degree of
reduction of each pollutant subject to regulation under
[the Act] emitted from or which results from any major
emitting facility, which the permitting authority, on a
case-by-case basis, taking into account energy, envi-
ronmental, and economic impacts and other costs, de-
termines is achievable for such facility * * *. [42
U.S.C. § 7479(3).]
3
INTRODUCTION
This case raises important and recurring issues concerning
the ability of the States to exercise their statutory authority
under the Clear Air Act (“CAA”)—one of the Nation’s most
significant and far-reaching environmental statutes. De-
scribed as an “experiment in federalism,” Michigan v. EPA,
268 F.3d 1075, 1078 (D.C. Cir. 2001) (quotation omitted),
the CAA assigns to the States an important—indeed pri-
mary—tole in air pollution prevention and control. One of
the States’ principal responsibilities under the Act is to
prevent the degradation of air quality in those areas where
national clean air standards have been attained. To this end,
the CAA prohibits the construction or modification of a
“major emitting facility” in any “clean air” area unless the
facility is subject to the “best available control technology,”
or “BACT.” 42 U.S.C. § 7475(a)(4). BACT is defined in the
CAA as “an emission limitation * * * which the permitting
authority, on a case-by-case basis, taking into account
energy, environmental, and economic impacts and other
costs, determines is achievable for such facility * * *.” Jd.
§ 7479(3) (emphasis added). The “permitting authority” in
this case—and in most cases arising under this provision—is
the State. See App. 3a.
The CAA thus by its terms gives the States the authority to
determine BACT for a particular source, and allows the
States broad discretion in making that determination. This is
confirmed by the Act’s legislative history: “The decision
regarding the actual implementation of best available tech-
nology is a key one, and the committee places this responsi-
bility with the State, to be determined in a case-by-case
judgment. It is recognized that the phrase has broad flexibil-
ity in how it should and can be interpreted, depending on
site.” S. Rep. No. 95-127, at 31 (1977) (emphases added).
In 1999, the State of Alaska issued a permit for the con-
struction of a new electric generator at the Red Dog Mine in
—_—
4
Northwest Alaska, 100 miles north of the Arctic Circle. In
accordance with the CAA and the State’s own regulations,
the State determined that a particular technology—“Low
NOx”—was BACT to control nitrogen oxide emissions from
the new generator. In making that determination, the State
expressly took into consideration “energy, environmental,
and economic impacts and other costs.” 42 U.S.C.
§ 7479(3).
Under the guise of exercising its enforcement authority
under the CAA, the EPA issued a series of orders prohibiting
the construction of the generator because the federal agency
disagreed with the State’s determination that Low NOx was
BACT for the new generator. In seeking to override the
State’s BACT determination in this manner, the EPA usurped
authority that the CAA clearly delegates to the States,
upsetting the balance of power that Congress carefully sought
to create under the Act. In conflict with decisions of this
Court and other federal courts of appeals, the Ninth Circuit
sanctioned that result.
The Ninth Circuit’s decision poses a grave threat to the
ability of the States to exercise the statutory authority vested
in them by Congress to make BACT and other important
discretionary decisions under the Act. The question pre-
sented is a recurring one of national importance, arising not
only under the CAA but a broad range of other federal
-Statutes with similar shared authority between the States and
federal government. This Court should grant certiorari to
resolve the conflict engendered by the Ninth Circuit’s
decision, and to preserve the delicate balance of power that
Congress established under the CAA and similar statutes.
STATEMENT OF THE CASE
Statutory and Regulatory Background. The CAA estab-
lishes “a comprehensive national program that ma{kes] the
States and the Federal Government partners in the struggle
against air pollution.” General Motors Corp. v. United
5
States, 496 U.S. 530, 532 (1990). At the same time, the
CAA recognizes that “air pollution prevention * * * and air
pollution control at its source is the primary responsibility of
States and local governments.” 42 U.S.C. § 7401(a)(3)
(emphasis added); see also id. § 7407 (“Each State shall have
the primary responsibility for assuring air quality within the
entire geographic area comprising such State”). Thus, while
the CAA assigns to the EPA the responsibility for establish-
ing national ambient air quality standards (“NAAQS”), see
id. § 7409, the Act gives the States the responsibility for
implementing those standards. See id. §§ 7407, 7410.
To this end, the CAA requires the States to adopt and sub-
mit for the EPA’s approval a state implementation plan
(“SIP”) that provides for attainment and maintenance of the
NAAQS. See id. § 7410. If a State does not have an ap-
proved SIP in place, the Act requires the EPA to adopt and
implement a federal implementation plan. See id. § 7410(c).
The EPA may delegate to a State the authority to implement
and enforce any part of such a plan. Jd. § 7410(c)(3).
The CAA requires that each SIP contain emission limita-
tions and such other provisions as may be necessary “to
prevent significant deterioration of air quality” in “attain-
ment” areas. Jd. § 7471. An “attainment”—or “clean air”—
area is one “that meets the [NAAQS] for [a given] pollutant.”
Id. § 7407(d)(1)(A)ii). The Act establishes maximum
allowable increases (or increments) of certain pollutants in
clean air areas. Jd. § 7473. To ensure that such increments
are not exceeded, the Act also establishes a preconstruction
review process that must be followed before the construction
or modification of a “major emitting facility” in a clean air
area. Id. § 7475. As part of that process, the Act requires
that each SIP contain a Prevention of Significant Deteriora-
tion (“PSD”) permit program, and provides that no major
emitting facility may be constructed in a clean air area
without a PSD permit. Jd. §§ 7410(a)(2)(C), 7475(a).
6
The Act also provides that no major emitting facility may
be constructed or modified unless “the proposed facility is
subject to the best available control technology [or “BACT”]
for each pollutant subject to regulation under [the Act]
emitted from, or which results from, such facility.” /d.
§ 7475(a)(4). BACT is defined as
an emission limitation based on the maximum degree of
reduction of each pollutant subject to regulation under
[the Act] emitted from or which results from any major
emitting facility, which the permitting authority, on a
case-by-case basis, taking into account energy, environ-
mental, and economic impacts and other costs, deter-
mines is achievable for such facility * * *. [Jd. § 7479(3)
(emphasis added). }
Factual Background. The State of Alaska is a clean air
area with respect to nitrogen dioxide, a regulated pollutant
under the Act. Under Alaska’s SIP, approved by the EPA in
1983, the State operates a PSD permit program through its
Department of Environmental Conservation (“ADEC”).
Before a PSD permit will be issued for the construction of a
new source within the State, the Alaska SIP requires “a
demonstration that [a] proposed limitation represents the best
available control technology for each air contaminant and for
[the] source.” 18 Alaska Admin. Code § 50.310(d)(3).
The Red Dog Mine, the world’s largest source of zinc
concentrate, is located in the harsh landscape of Northwest
Alaska, about 100 miles north of the Arctic Circle. The mine
is operated by Teck Cominco Alaska, Inc. (“Cominco”) in
partnership with the Northwest Arctic Native Association
(“NANA”)! on lands owned by NANA. Operating 365 days
' NANA is a regional corporation established by Congress
pursuant to the Alaska Native Claims Settlement Act, 43 U.S.C.
§§ 1601 et seg. NANA is the regional corporation organized for
the benefit of the Inupiat Eskimos residing in Northwest Alaska.
7
a year, the mine is the largest private employer in the North-
west Arctic Borough, a vast and isolated area with an histori-
cally high unemployment rate. Due to its remote location,
the mine requires an independent, on-site power source. The
mine is currently powered by six diesel-fired electric genera-
tors, designated “MG-1’ through “MG-6,” which were
constructed pursuant to PSD permits issued by ADEC in
1988 and 1994.
In April 1996, Cominco initiated a project to boost the
mine’s output—and in the process create nearly 100 new
jobs. Because the project required the use of more electric-
ity, Cominco in June 1998 submitted an application to ADEC
for a new PSD permit, requesting permission to increase the
amount of nitrogen oxide (“NOx”), a precursor to nitrogen
dioxide, from its MG-5 generator. Cominco’s application
proposed the use of “Low NOx”—a process that reduces the
amount of NOx that would otherwise be released into the
environment—as BACT for the MG-5 generator. In April
1999, Cominco amended its application, proposing to install
Low NOx on all six of its existing generators—including the
five not subject to a new BACT determination—as well as on
a proposed new generator, “MG-17,” which—like MG-5—
was also subject to BACT.
In May 1999, ADEC issued a draft PSD Permit and a pre-
liminary Technical Analysis Report (“TAR”) in which it
accepted Cominco’s amended proposal because it would
reduce total NOx emissions from the Red Dog Mine to a
level comparable to or lower than that which would result
were another control alternative evaluated during ADEC’s
review process—Selective Catalytic Reduction (“SCR”)}—
installed on only the MG-5 and MG-17 generators. See App.
4a. ADEC published the draft PSD Permit and preliminary
TAR for public comment and review.
In July 1999, after the close of the public comment period,
the EPA commented on Cominco’s application for the first
8
time, expressing its view that SCR was BACT for the MG-5
and MG-17 generators—even though SCR had never before
been determined to be BACT to reduce NOx emissions from
a similar diesel-fired electric generator. In September 1999,
after considering all public comment—including the EPA’s
belated input—ADEC issued a final draft permit and a final
draft TAR concluding that Low NOx was BACT for the MG-
5 and MG-17 generators. In response to the EPA’s continu-
ing objections, ADEC worked with the federal agency in an
effort to resolve their differences. Although the dispute over
BACT for the MG-S5 generator was resolved when Cominco
decided to restrict emission increases from the generator to
avoid BACT review, the parties could not agree on BACT
for the proposed new generator, MG-17.
After a period of unsuccessful negotiations, ADEC on
December 10, 1999 issued the PSD Permit and a final TAR,
in which ADEC spent nearly ten pages explaining the basis
of its carefully considered determination that Low NOx was
BACT for the MG-17 generator. See PER 044-053.2 In
making that determination, ADEC considered the “energy,
environmental, and economic impacts and other costs”
associated with other technologies, including SCR. 42
U.S.C. § 7479(3). Moreover, although not required to do so,
ADEC followed the EPA’s “top-down” approach—used by
the EPA when it acts as the PSD permitting authority in those
circumstances where a State does not have a PSD program—
in determining BACT.2 Under that approach, ADEC
(1) identified all NOx control technologies; (2) identified
which technologies were technically feasible; (3) ranked the
feasible control technologies in order of effectiveness; (4)
considered the energy, environmental, and economic impacts
of the feasible technologies and determined which to elimi-
2 Petitioners’ Combined Excerpts of Record below are cited as
“PER.”
> As the EPA acknowledges, “top-down analysis is not a man-
datory methodology.” EPA 9th Cir. Br. 12 (quotation omitted).
9
nate based on such impacts; and (5) selected Low NOx as the
most effective technology not eliminated.
In considering the “energy, environmental, and economic
impacts and other costs” associated with SCR, ADEC
discounted Cominco’s contention that requiring SCR would
have adverse environmental and energy impacts. ADEC
concluded, however, that SCR would have an adverse
economic impact because, among other things, the “exces-
sive economic cost” of SCR—$2.9 million in capital costs
and annual operating costs approaching $635,000—could
adversely affect the mine’s “world competitiveness,” with
attendant adverse consequences for the precarious economy
of the Northwest Arctic Borough. PER 051. Accordingly,
ADEC determined that SCR was not economically feasible.
Yet because Cominco had agreed to install Low NOx on ail
its generators—not just the MG-17 generator subject to
ADEC’s BACT determination—ADEC’s permit decision
was expected to reduce NOx emissions to a level comparable
to or Jower than that which would result if SCR were in-
stalled on only the MG-17 generator. See App. 4a.
The EPA’s Orders. In an attempt to prevent ADEC from
issuing the PSD Permit to Cominco, the EPA on December
10, 1999 issued a Finding of Noncompliance and Order to
ADE. App. 26a. According to the EPA, ADEC’s issuance
of the final draft permit would not be in compliance with the
requirements of the CAA or Alaska’s SIP relating to the
construction or modification of new or existing sources.
App. 36a. The EPA thus ordered ADEC to withhold issu-
ance of Cominco’s permit designating Low NOx as BACT
until ADEC demonstrated to the EPA’s satisfaction that SCR
was not BACT for the MG-17 generator or that the issuance
of the permit was otherwise in compliance with the CAA and
Alaska’s SIP. /d.
The EPA purported to issue its Finding and Order under
Section 113(a)(5) of the CAA, which provides that whenever
10
the Administrator “finds that a State is not acting in compli-
ance with any requirement or prohibition of the [Act] relating
to the construction of new sources or the modification of
existing sources,” the Administrator “may issue an order
prohibiting the constructicn «r modification of any major
stationary source in any ava to which such requirement
applies.” 42 U.S.C. § 7413(a)(5). The EPA also relied on
Section 167 of the CAA, which provides that the Administra-
tor “shall * * * take such measures, including issuance of an
order, or seeking injunctive relief, as necessary to prevent the
construction or modification of a major emitting facility
which does not conform to the requirements of [the CAA’s
PSD program].” Jd. § 7477. The Finding and Order did not
identify the specific “requirement” of the Act with which
ADEC supposedly had failed to comply, and the Act itself
specifies that “the permitting authority, on a case-by-case
basis,” is to determine what constitutes BACT for a particular
facility. Id. § 7479(3).
Because ADEC had already issued Cominco’s permit, the
EPA—on February 8, 2000— issued an Administrative Order
to Cominco prohibiting the construction of the MG-17
generator until Cominco “demonstrated to the EPA’s satis-
faction compliance with [the CAA]” and obtained a “valid”
PSD permit from ADEC for the MG-17 generator that
complied with the CAA and the EPA’s December 10, 1999
Finding and Order. App. 49a. Subsequently, on March 7,
2000, the EPA amended its February 8, 2000 order to allow
Cominco to perform certain construction activities during the
short Alaska summer. App. 62a-63a. The Amended Admin-
istrative Order reiterated that Cominco was otherwise prohib-
ned ftom commencing construction of the MG-17 generator.
App. 62a.
Proceedings Below. ADEC and Cuntans subsequently
filed petitions for review in the Ninth Circuit challenging the
EPA's authority to issue the December 10, 1999 Finding of
Noncompliance and Order, the February 8, 2000 Administra-
11
tive Order, and the March 7, 2000 Amended Administrative
Order. App. la. ADEC and Cominco argued that the EPA
had no authority to issue the orders under either Section
113(aX(5) or Section 167 because ADEC had not failed to
comply with a “requirement” of the Act. To the contrary,
they explained, ADEC had properly exercised its authority
under the Act to make BACT determinations on a “case-by-
case basis.” 42 U.S.C. § 7479(3).
Before issuing its decision, the Ninth Circuit twice sought
supplemental briefing from the parties. Shortly after oral
argument, after initially rejecting the EPA’s contention that
the court lacked jurisdiction to consider the petitions because
the EPA’s orders did not constitute “final agency action,” the
Ninth Circuit requested further briefing “assessing the
impact, if any,” of this Court’s recent decision in Whitman v.
American Trucking Ass'ns, 531 U.S. 457 (2001). App. 23a.
Later, the court requested additional briefing on “whether it
is the state of Alaska (through ADEC) or the EPA that bears
the ultimate legal authority and responsibility under the
Clean Air Act to determine whether an individual [PSD]
permit issued by Alaska pursuant to its State Implementation
Plan (SIP) meets the requirements of the Clean Air Act or the
SIP.” App. 25a.
In the end, the Ninth Circuit upheld the EPA’s orders. The
court observed that applicants for PSD permits “must fulfill
the ‘preconstruction requirement’ that a ‘proposed facility
[be] subject to the best available control technology for each
pollutant subject to regulation."” App. 8a (quoting 42
U.S.C. § 7475(a)(4)) (alteration in original). Thus, the court
concluded, “subjecting a facility to BACT is both a ‘require-
ment * * * of the chapter relating to the construction of new
sources or the modification of existing sources,’ under
Section 113(a)(5), and a ‘requirement{] of this part’ under
Section 167.” /d. (alterations in original). “Because the EPA
based its orders on the finding that ADEC had not complied
with the BACT requirement,” the court held, “the orders
12
were authorized by the plain language of Section 113(a)(5),
as ‘order[s] prohibiting the construction or modification of
any major stationary source in any area to which such
requirement applies,’ and of Section 167, as orders ‘neces-
sary to prevent the construction or modification of a major
emitting facility which does not conform to the requirements
of this part.” App. 9a.
The Ninth Circuit further held that the CAA’s legislative
history also compelled the conclusion that “the EPA has the
ultimate authority to decide whether the state has complied
with the BACT requirements of the Act and the state SIP.”
App. 10a-1la. As support for that conclusion, the court cited
the 1970 amendment of the Act authorizing the EPA to
publish NAAQs and delegating to the States the responsibil-
ity for implementing those standards; the 1977 amendment of
the Act adding the Aci’s PSD provisions; and the 1990
amendment of Section 113(a)(5) allowing the EPA to take
action when a State fails to comply with “any requirement or
prohibition” relating to new or modified sources. See App.
9a-10a. The Ninth Circuit did not address the legislative
history most directly on point—that making clear that “{tJhe
decision regarding the actual implementation of best avail-
able technology is a key one, and the committee places this
responsibility with the State, to be determined in a case-by-
case judgment.” S. Rep. No. 95-127, at 31 (1977) (emphasis
added). See ADEC 9th Cir Br. 34 (citing legislative history).
Addressing ADEC and Cominco’s contention that the EPA
lacked the authority to veto ADEC’s discretionary judgment
based on its difference of opinion as to which technology was
BACT, the Ninth Circuit stated that “neither Section
113(aX5) nor Section 167 contains any exemption for
requirements that involve the state’s exercise of discretion,”
and that “[njothing in the BACT definition of Section 169(3)
limits the EPA’s authority.” App. lla. The court then went
on to hold that the EPA’s issuance of the orders was not
arbitrary or capricious.
13
REASONS FOR GRANTING THE WRIT
I. THE NINTH CIRCUIT’S DECISION CONFLICTS
WITH DECISIONS OF THIS COURT AND
OTHER FEDERAL COURTS OF APPEALS ON
THE ALLOCATION OF FEDERAL-STATE AU-
THORITY.
The Ninth Circuit held in this case that “the EPA has the
ultimate authority to decide whether [a] state has complied
with the BACT requirements of the Act.” App. 10a-1la.
The CAA, however, squarely places the responsibility for
determining BACT with the States, and gives them broad
discretion to do so. See 42 U.S.C. § 7479(3) (defining BACT
as “an emission limitation * * * which the permitting author-
ity, on a case-by-case basis, taking into account energy,
environmental, and economic impacts and other costs,
determines is achievable for such facility”) (emphasis
added); see also S. Rep. No. 95-127, at 31 (“The weight
assigned to such factors is to be determined by the State.”).
Because a BACT determination is a discretionary judgment,
involving the case-by-case weighing of a variety of factors,
there is no single, objectively “correct” BACT determination
for any particular source. The fact that a State weighs the
pertinent factors differently than the EPA in any particular
case does not mean that the State has in any sense violated a
requirement of the Act, authorizing the EPA io intervene and
overturn the State’s judgment.
The CAA does provide that a facility’s emissions may not
exceed the NAAQS or PSD allowable increments, see 42
U.S.C. § 7475(a)(3), and that the application of BACT may
not result in emissions that exceed other standards estab-
lished under the Act, see id. § 7479(3). As long as a State
observes those statutory parameters—and it is undisputed
that Alaska did so here—the only BACT “requirement”
imposed by the Act is that a State take into account “energy,
environmental, and economic impacts and other costs” in
14
determining BACT. If a State takes such factors into consid-
eration—as Alaska plainly did here—the EPA has no author-
ity to override a BACT determination with which it may
disagree.‘ The Ninth Circuit’s holding to the contrary is thus
not only deeply flawed, but fails to square with decisions of
this Court and other federal courts of appeals that have
recognized and respected the balance of power between the
States and the federal government that Congress established
under the Act.
1. More than twenty-five years ago, this Court recog-
nized the CAA’s “division of responsibilities” between the
States and the federal government in Train v. Natural
Resources Defense Council, Inc., 421 U.S. 60, 79 (1975). In
Train, the Court observed that the EPA “is plainly charged
by the Act with the responsibility for setting the national
ambient air standards.” But “{jjust as plainly,” the Court
emphasized, the EPA “is relegated by the Act to a secondary
role in the process of determining and enforcing the specific,
source-by-source emission limitations which are necessary if
the national standards it has set are to be met.” Jd. (emphasis
added). As the Court explained, “[t]he Act gives the [EPA]
4 The only circumstance—not applicable here—in which the
EPA’s approval of BACT is required is “in the case of a source
which proposes to construct in a class [II area, emissions from
which would cause or contribute to exceeding the maximum
allowable increments applicable in a class II area and where no
standard under section 7411 of this title [42 U.S.C. § 7411] has
been promulgated subsequent to August 7, 1977, for such source
category.” 42 U.S.C. § 7475(a)(8). This narrow exception proves
the rule—that Congress otherwise did not intend the EPA to be the
“ultimate authority” with respect to a State’s BACT determination.
App. lla. See Russello v. United States, 464 U.S. 16, 23 (1983)
(where “Congress includes particular language in one section of a
statute but omits it in another section of the same Act, it is gener-
ally presumed that Congress acts intentionally and purposely in the
disparate inclusion or exclusion”).
15
no authority to question the wisdom of a State’s choices of
emission limitations if they are part of a plan which satisfies
the [Act’s] standards.” Jd. (emphasis added). “(S]o long as
the ultimate effect of a State’s choice of emission limitations
is compliance with the national standards for ambient air, the
State is at liberty to adopt whatever mix of emission limita-
tions it deems best suited to its particular situation.” /d. See
also Union Elec. Co. v. EPA, 427 U.S. 246, 269 (1976)
(“Congress plainly left with the States, so long as the national
standards were met, the power to determine which sources
would be burdened by regulation and to what extent”).
2. Unlike the Ninth Circuit below, other federal courts
of appeals have respected the “division of responsibilities”
set out in the CAA and have firmly rebuffed attempts by the
EPA to usurp authority that Congress has clearly reserved for
the States. Not surprisingly, the Ninth Circuit’s decision
conflicts in this regard with numerous decisions of the D.C.
Circuit—the court vested with exclusive jurisdiction over
petitions for review of the EPA’s promulgation of national
standards, rules, and regulations under the CAA. See 42
U.S.C. § 7607(b)\(1).
For instance, the Ninth Circuit’s decision conflicts with the
D.C. Circuit’s recent decision in American Corn Growers
Ass'n v. EPA, 291 F.3d 1 (D.C. Cir. 2002), a case involving
the States’ authority to make determinations very much like
the BACT determination at issue here. American Corn
Growers involved the States’ authority to determine the best
available retrofit technology (“BART”) for certain stationary
sources under the Act. The Act requires the States to deter-
mine BART for particular sources and provides that in
determining BART each State “shall” take into consideration
five enumerated statutory factors. See 42 U.S.C.
§§ 7491(b)(2)(A), (gX(2). The EPA promulgated a rule
requiring the States to consider one of the factors on a
regional, rather than source-by-source, basis. See 291 F.3d at
6. The D.C. Circuit invalidated the rule, holding that it was
16
“inconsistent with the Act’s provisions giving the states
broad authority over BART determinations.” /d. at 8. By
dictating that the States make BART determinations in a
particular manner, the EPA had impermissibly “constrain[ed]
authority Congress conferred on the states.” /d. at 9.
Just so here. The CAA gives the States broad authority to
make BACT determinations for particular sources. By
substituting its judgment for the State of Alaska’s in this
case, the EPA plainly “infringe[d] on [the State’s] authority
under the Act.” /d. at 9. The Ninth Circuit’s decision
sanctioning that result cannot be reconciled with American
Corn Growers.
The Ninth Circuit’s decision also conflicts with the D.C.
Circuit’s decision in Alabama Power Co. v. Costle, 636 F.2d
323 (D.C. Cir. 1980), the seminal case addressing the CAA’s
PSD provisions. Amid various challenges to the EPA’s
initial regulations implementing those provisions, the court
addressed the contention that the EPA should be required to
promulgate guidelines “detailing the manner in which States
may permit consumption of the available increments” of
certain pollutants in clean air areas. Jd. at 363-364. The
court made clear that although the EPA may prevent or
correct violations of the increment limitations under the Act,
“the agency is without authority to dictate to the States their
policy for management of the consumption of allowable
increments.” Jd. at 361. Those limitations must be observed,
the Court held, “but assuming such compliance, growth-
management decisions were left by Congress for resolution
by the states.” Jd. at 364.
: In the same vein is the D.C. Circuit’s more recent decision
in Virginia v. EPA, 108 F.3d 1397 (D.C. Cir.), modified on
other grounds, 116 F.3d 499 (1997). There, the D.C. Circuit
invalidated an EPA regulation requiring certain States to
adopt particular motor vehicle emissions standards. Relying
on this Court’s decision in Train, the D.C. Circuit held that
17
“Congress did not give EPA authority to choose the control
measures or mix of measures states would put in their
implementation plans.” Jd. at 1410. In sharp contrast to the
D.C. Circuit’s decisions in Alabama Power and Virginia v.
EPA, the Ninth Circuit’s decision permits the EPA to “dictate
to the States” a matter plainly within their discretion—what
constitutes BACT with respect to a particular facility.
3. The conflict between the decision below and the
decisions of the D.C. Circuit alone provides a compelling
basis for review. But the conflict created by the decision
below is by no means limited to the D.C. Circuit. For
instance, in Florida Power & Light Co. v. Costle, 650 F.2d
579 (1981), the Fifth Circuit rebuffed the EPA’s attempt to
require the State of Florida to include a particular provision
in its SIP. Florida had submitted a proposed SIP revision to
the EPA to allow a particular source to increase its emissions
limitations beyond those in Florida’s EPA-approved SIP.
The EPA approved the SIP revision, but imposed a two-year
limit on the increase. Relying on 7rain, the Fifth Circuit held
that the EPA’s action was clearly “beyond the Congressional
mandate.” /d. at 589. Under the CAA, the court explained,
States “‘imay obtain approval of their developing policy
choices as to the most practicable and desirable methods of
restricting total emissions to a level which is consistent with
the national ambient air standards.’” Jd. at 587 (quoting
Train, 421 U.S. at 80). “The great flexibility accorded the
states,” the court went on, “is further illustrated by the
sharply contrasting, narrow role to be played by EPA.” Id.
So long as a proposed SIP revision meets the criteria set out
in the Act, the EPA has no authority to “ ‘assume control of a
State’s emission limitations mix once its initial plan is
approved.’” Jd. (quoting Train, 421 U.S. at 80). By at-
tempting to do just that, the EPA had “usurp[ed] state initia-
tive in the environmental realm,” thereby “disrupt[ing] the
balance of state and federal responsibilities that undergird the
efficacy of the Clean Air Act.” Jd. at 589.
18
The Seventh Circuit’s decision in Bethlehem Steel Corp. v.
Gorsuch, 742 F.2d 1028 (7th Cir. 1984) (Posner, J.), is to the
same effect. There, too, the court refused to allow the EPA
to tread upon the States’ authority under the CAA and upset
the Act’s “division of responsibilities.” Train, 421 U.S. at
79. The EPA had issued an order partially approving a
proposed SIP revision submitted by the State of Michigan.
The effect of the “partial approval,” however, was to render
the proposed SIP revision more stringent than it was as
submitted. The Seventh Circuit held that the EPA could not,
“in the guise of partial approval,” make Michigan’s SIP
stricter than the State intended. /d. at 1036. If the EPA
wished to impose tougher standards, it was required to follow
the Act’s procedures for doing so—namely by promulgating
its own regulation in accordance with the Act’s criteria. See
id. at 1035. Under the CAA, the court explained, “{t}he
federal government through the EPA determines the ends—
the standards of air quality—but Congress has given the
States the initiative and a broad responsibility regarding the
means to achieve those ends.” Jd. at 1036. In short, the
CAA “creates a partnership between the states and the
federal government,” and the EPA “may not run roughshod
over the procedural prerogatives that the Act has reserved to
the states.” Jd.
The Ninth Circuit’s decision allowing the EPA to “usurp
state initiative in the environmental realm,” Florida Power &
Light Co., 650 F.2d at 589, is squarely at odds with these
decisions. Moreover, as the Seventh Circuit’s decision in
Bethlehem Steel makes clear, when the EPA prefers that a
State take a particular action, the EPA must follow proper
procedures. As ADEC explained below, the proper recourse
for the EPA in this case was not to veto the State’s discre-
tionary judgment by regulatory fiat, but rather to participate
in the public comment process on Cominco’s draft permit
and then, if it still disagreed with the State’s action after that
process, challenge ADEC’s BACT determination through the
19
State’s administrative review process. See ADEC 9th Cir.
Br. 53-56; PER 390-391. See also 42 U.S.C. § 7475(a)(2)
(requiring opportunity for interested persons “including
representatives of the Administrator” to submit comments on
“control technology requirements” before PSD permit may
be issued). Alaska’s laws and SIP permit any party that
participated in the public comment process to pursue an
administrative appeal of a permit decision, followed by
judicial review. See 18 Alaska Admin. Code § 50.315;
Alaska Stat. § 46.14.200. |
Contrary to Bethlehem Steel, the Ninth Circuit permitted
the EPA to bypass those channels and “run roughshod” over
the State’s prerogatives under the Act. 742 F.2d at 1036.
The Ninth Circuit’s decision is particularly intolerable as it
essentially gives the EPA free rein to invalidate a BACT
determination at any time—months, even years, after a
permit has been issued and a source has invested in the
technology approved by the State. Cf United States v. AM
General Corp., 34 F.3d 472, 474-475 (7th Cir. 1994) (hold-
ing that the EPA could not “mount a collateral attack” on a
permit as many as five years after it was issued where the
EPA had the “alternative remedy” of a state administrative
appeal followed by judicial review). The conflict between
the decision below and Bethlehem Steel in this regard further
underscores the need for this Court’s review.
Il. THE CONFLICT OVER FEDERAL-STATE
AUTHORITY IS A RECURRING ISSUE OF
NATIONAL IMPORTANCE.
Although the conflict engendered by the Ninth Circuit’s
decision alone warrants certiorari, the need for this Court’s
review is heightened by the important and recurring nature of
the question presented. Congress gave the States “great
flexibility” to achieve the goals of the CAA, Florida Power
& Light, 650 F.2d at 587, including the preservation of air
quality in clean air areas. As the D.C. Circuit explained in
20
Alabama Power, “[i]n the allocation of responsibilities made
by Congress” with respect to preventing the significant
deterioration of air quality, “maximum limitations have been
set.” 636 F.2d 364. “These must be observed by the states,
but assuming such compliance, growth-management deci-
sions were left by Congress for resolution by the states.” /d.
A State’s authority to determine BACT for a particular
source is “key” to its ability to “manage [its] allowed internal
growth” under the CAA. /d. at 364. The “flexible approach”
chosen by Congress “enables [a] State to consider the size of
the plant, the increment of air quality which will be absorbed
by any particular major emitting facility, and such other
considerations as anticipated and desired economic growth
for the area.” S. Rep. No. 95-127, at 31 (emphasis added).
Congress’s decision to make BACT “strictly a State and local
decision,” id., makes sense, as it is the States—not the
EPA—that are most sensitive to particular local needs and
concerns. .
The Act’s requirement that BACT be determined on a
“case-by-case,” facility-specific basis, 42 U.S.C. § 7479(3),
highlights the importance of such local considerations. In
this case, for instance, the State of Alaska, taking into
account the requisite statutory factors, made a permitting
decision that would not only result in cleaner air, but more
jobs for a struggling community situated 100 miles north of
the Arctic Circle, where geography and the harsh environ-
ment pose unique employment challenges and offer few
employment alternatives. In reaching its decision, the State
considered various site-specific conditions, as well as “the
importance of the mine to the regional economy of the
Northwest Arctic Borough.” PER 387. See id. 386-387.
The Ninth Circuit, based more than 2000 miles away in
California, was “uncomfortabl[{e]” with the State’s considera-
tion of the mine’s importance to the local economy. App.
16a. But the statute specifically directs that the States
21
consider “economic impacts” in determining BACT. 42
U.S.C. § 7479(3). See S. Rep. No. 95-127, at 31. Allowing
the EPA to dictate BACT to the States means allowing the
EPA to “assume control” of the States’ “developing policy
choices as to the most practicable and desirable methods of
restricting total emissions to a level consistent with” the
limitations set out in the Act. Train, 421 U.S. at 80. It also
means longer delays in the permitting process while the EPA
wrangles with the States over their decisions. That is plainly
not what Congress intended. See S. Rep. No. 95-127, at 32
(“Nothing could be more detrimental to the intent of [the
PSD] section and the integrity of [the] act than to have the
process encumbered by bureaucratic delay.”’).
The Ninth Circuit’s decision not only vitiates the States’
authority to determine BACT under the CAA, but also -
threatens the ability of the States to make numerous similar
kinds of discretionary decisions under the Act. As noted
above, for instance, the Act authorizes the States to deter-
mine the best available retrofit technology (“BART”) for
particular sources by weighing various statutory factors. See
42 U.S.C. § 7491(b)(2)(A); id. § 7491(g)(2). The Act also
authorizes the States, in consultation with the EPA, to
exclude from the definition of “small business stationary
sources” under the Act’s operating permit provisions any
category of sources that “the State determines to have
sufficient technical and financial capabilities to meet the
requirements of [the] Act.” Jd. § 7661f(c)(3)(B). In non-
attainment areas, the Act authorizes the States to determine
the lowest achievable emissions rate (“LAER”) for new and
modified major stationary sources. See id. §§ 7501(3),
7503(a)(2). Under the Ninth Circuit’s holding, the EPA
would be free to override these sorts of determinations any
time it disagrees with a State’s decision.
The potential effect of the Ninth Circuit decision is even
more far-reaching. In addition to the CAA, numerous other
statutes embody the principle of “cooperative federalism.”
22
See, e.g., New York v. United States, 505 U.S. 144, 167-168
(1992) (noting “numerous federal statutory schemes” of this
nature, including the Clean Water Act, 33 U.S.C. §§ 1251 et
seq., the Occupational Safety and Health Act, 29 U.S.C.
§§ 651 et seg., the Resource Conservation and Recovery Act,
42 U.S.C. §§ 6901 et seq., and the Alaska National Interest
Lands Conservation Act, 16 U.S.C. §§ 3101 et seqg.). Those
statutes also establish regulatory regimes based on shared
federal-state responsibility, whereby the federal government
sets standards and the States—if they opt to undertake the
responsibility—are given broad flexibility in implementing
those standards. Such programs “offer States the choice of
regulating * * * activity according to federal standards,”
which promotes underlying values of federalism because
“state governments remain responsive to the local elector-
ate’s preferences; state officials remain accountable to the
people.” New York v. United States, 50S U.S. at 167-168.
The Ninth Circuit decision, by transferring from the State to
the EPA core discretionary authority under one of the leading
“cooperative federalism” statutory regimes, threatens to
undermine the balance of power struck by Congress and
accepted by the States when they assumed the responsibilities
offered under the Act. This Court should not allow such a
troubling decision to stand unreviewed.
23
CONCLUSION
For the foregoing reasons, the petition for a writ of certio-
rari should be granted, and the judgment reversed.
Respectfully submitted,
BRUCE M. BOTELHO JOHN G. ROBERTS, JR.*
Attorney General LORANE F. HEBERT
STATE OF ALASKA HOGAN & HARTSON L.L.P.
+t of Law 555 Thirteenth Street, N.W.
P.O. Box 110300 Washington, D.C. 20004
Juneau, Alaska 99811 (202) 637-5810
(907) 465-3600
CAMERON M. LEONARD
Assistant Attorney General
STATE OF ALASKA
oe of Law ~-
100 Cushman Street, Suite 400
Fairbanks, Alaska 99701
(907) 451-2811
* Counsel of Record Counsel for Petitioner
APPENDICES
la
APPENDIX A
UNITED STATES COURT OF APPEALS
FOR THE NINTH CIRCUIT
Nos. 00-70166, 00-70169, 00-70175 and 00-70301.
STATE OF ALASKA, DEPARTMENT OF ENVIRONMENTAL
CONSERVATION,
Petitioner,
Vv.
UNITED STATES ENVIRONMENTAL PROTECTION AGENCY,
Respondent.
TECK COMINCO ALASKA INCORPORATED,
Petiti
Vv.
UNITED STATES ENVIRONMENTAL PROTECTION AGENCY,
Respondent.
TECK COMINCO ALASKA INCORPORATED,
Petitioner,
Vv.
——
UNITED STATES ENVIRONMENTAL PROTECTION AGENCY,
Respondent.
2a
TECK COMINCO ALASKA INCORPORATED,
Petitioner,
Vv.
UNITED STATES ENVIRONMENTAL PROTECTION AGENCY,
CAROL M. BROWNER, ADMINISTRATOR, AND CHUCK
CLARKE, REGIONAL ADMINISTRATOR, REGION 10, OF THE
UNITED STATES ENVIRONMENTAL PROTECTION AGENCY,
Respondents.
Argued and Submitted Feb. 13, 2001.
Submission Vacated March 27, 2001.
Resubmitted July 30, 2002.
- Filed July 30, 2002.
Before: REINHARDT, WARDLAW, and GOULD, Circuit
Judges.
WARDLAW, Circuit Judge.
The Alaska Department of Environmental Conservation
(“ADEC”) and Teck Cominco Alaska, Inc. (“Cominco”)
petition for review of three enforcement orders entered by the
United States Environmental Protection Agency (“EPA”),
which effectively invalidated a Prevention of Significant
Deterioration (“PSD”) permit issued by ADEC to Cominco.
Petitioners challenge the EPA’s authority to issue these
orders, and that the EPA abused its discretion in
ing that "ADE *s Best Available Control Technology
(“BACT”) determination did not comply with the require-
ments of the Clean Air Act and Alaska’s State Implementa-
tion Plan (“SIP”). We find that the EPA acted within its
authority and, further, that it did not abuse its discretion.
3a
I. Background
The Clean Air Act (“the Act”), 42 U.S.C. §§ 7401-76714q,
establishes a program for controlling and improving the
nation’s air —_ through a system of shared federal and
state responsibility. The Act requires states to submit for the
EPA’s approval a state implementation plan that provides for
attainment and maintenance of the national ambient air
quality standards (“NAAQS”) promulgated by the EPA. 42
U.S.C. § 7410.
The Act’s Prevention of Significant Deterioration program
controls the level of degradation in “clean air areas” of the
nation by requiring a pollutant-emitting source to obtain a
it before construction. See 42 U.S.C. §§ 7470-7492. In
implementing the PSD program and permitting process,
States can either operate within the federal PSD program, in
which the EPA is the PSD permit issuer, or include a PSD
program within their own EPA-approved state implementa-
tion plan. 42 U.S.C. §§ 7410(a)(2)(C), 7471.
Alaska is a “clean air area” under the Act-——that is, its air
quality regions are cleaner than the national standards with
respect to ozone and nitrogen dioxide. Under Alaska’s State
Implementation Plan, which the EPA accepted as meeting the
Act’s requirements in 1983, Alaska, through the Alaska
Department of Environmental Conservation, is the PSD
permit issuer. See Approval and Promulgation of
Implementation Plans; Alaska, 48 Fed. Reg. 30623 (July 5,
1983), as amended at 56 Fed. Reg. 19284 (April 26, 1991).
For new and modified sources, the Alaska SIP requires “a
demonstration that the proposed [emissions control]
limitation represents the best available control technology”
before ADEC will issue a permit. Alaska Admin. Code tit.
18, § 50.310(d)(3) (1997).
Cominco operates the Red Dog Mine facility (“the Mine”),
a major producer of zinc concentrates, in partnership with the
Northwest Arctic Native Association, an Alaska corporation.
The Mine is approximately 100 miles north of the Arctic
Circle and about five miles west of the Noatak National
4a
Preserve. The closest residential communities are the native
villages of Kivalina and Noatak.
- Due to its remote location, the Mine requires an independ-
ent, on-site power source. The current power supply for the
Mine consists of six diesel-fired Wartsila 5000-watt genera-
tors, labeled “MG-1” through “MG-6,” which were con-
structed under a 1988 PSD permit. In April 1996, Cominco
began its Production Rate Increase (“PRI”) project to boost
the Mine’s output of zinc and zinc concentrates. Cominco
determined it needed more electricity at the Mine to power
the additional mining equipment.
In June 1998, Cominco submitted an application to ADEC
for a new PSD permit, requesting permission to increase the
amount of nitrogen oxides (“NOx”), a regulated air pollutant,
from its MG-5 generator. Cominco’s application proposed
the use of “Low NOx” as BACT for MG-5. Low NOx is a
process that uses high-combustion air temperatures to better
atomize toxic particles, thereby reducing the amount of NOx
released into the environment. A review by ADEC, however,
reached the contrary conclusion that Selective Catalytic
Reduction (“SCR”), a process in which exhaust is injected
with ammonia or urea and then combined with a catalyst,
was BACT for MG-S.
Cominco responded by amending its application in April
1999. As an alternative to installing SCR on MG-5,
Cominco volunteered to install the less costly Low NOx
technology on all six of its existing generators, including
those not subject to BACT standards, and on a proposed
seventh generator, “MG-17.”
In its May 4, 1999 Preliminary Technical Analysis Report,
ADEC accepted Cominco’s proposal because it would reduce
the total NOx output from the Mine to a level comparable to
that which would result were SCR installed in only the MG-5
and MG-17 generators.
In July 1999, the EPA entered the discussion over
Cominco’s application at the urging of the National Park
Service, which had expressed concern that the “[n]itrogen
Sa
oxide emissions . . . could affect vegetation at Cape Krusen-
stern National Monument and Noatak National Preserve.”” In
a letter to ADEC, the EPA stated that SCR was tlic best
available control technology for the MG-5 and MG-17
generators, and that “the PSD program does not allow the
imposition of a limit that is less stringent than BACT even if
the equivalent emission reductions are obtained by imposing
new controls on other emission units.”
On September 3, 1999, ADEC issued a Final Technical
Analysis Report and permit decision, concluding that SCR
was not economically feasible and that Low NOx was instead
BACT. The EPA responded with a review of ADEC’s
report, asserting that ADEC’s cost-effectiveness estimate for
SCR was “well within the range that the EPA considers
reasonable,” and that Cominco had not adequately demon-
strated why SCR was economically infeasible.
ADEC, Cominco, and the EPA met to discuss the pending
PSD permit, agreeing to install Low NOx on MG-1, MG-3,
MG-4, and MG-5, but without agreeing on BACT for MG-
17.
After further unsuccessful negotiations, the EPA issued a
“Finding of Noncompliance Order” on December 10, 1999,
stating that ADEC’s authorization of Cominco’s construction
and installation of new equipment was not in compliance
with the Clean Air Act and the Alaska SIP. Pursuant to
Sections 113(a)(5) and 167 of the Act, 42 U.S.C. §§
7413(a)(S5) and 7477, the EPA ordered ADEC to withhold
issuance of Cominco’s PSD permit.
Later that same day, however, in disregard of the EPA’s
order, ADEC issued the PSD permit along with a second
Final Technical Analysis Report.
On February 8, 2000, the EPA sent a letter to ADEC with a
formal finding that the December 10, 1999 report and PSD
permit failed to comply with federal and state PSD require-
ments. On the same day, the EPA issued a second order to
Cominco preventing the company from beginning construc-
tion on the MG-17 generator until Cominco had demon-
6a
strated to the EP,’,’s satisfaction compliance with the Act and
the SIP.
The EPA’s third order, dated March 7, 2000, modified the
February 8, 2000 order to allow Cominco to engage in
summer-dependent construction activities.
On April 25, 2000, the EPA withdrew its December 10,
1999 order prohibiting ADEC from issuing the permit. In an
accompanying letter, however, the EPA emphasized that its
findings of noncompliance in the December 10, 1999 and
February 8, 2000 orders remained unchanged.
ADEC and Cominco petition this court for review of the
December 10, 1999 Finding of Noncompliance and Order;
the February 8, 2000 Administrative Order; and the March 7,
2000 Amended Administrative Order. Petitioners claim that
the EPA exceeded its authority by issuing enforcement orders
invalidating ADEC’s issuance of Cominco’s PSD permit,
and that ADEC acted within its discretion when making its
BACT determination.
II. Procedural History on Appeal and Jurisdiction
_ The EPA initially challenged our subject matter jurisdiction
in a motion to dismiss, which we denied without prejudice,
and again in conjunction with the merits of the appeal. In an
order dated March 27, 2001, Alaska v. United States EPA,
244 F.3d 748 (9th Cir. 2001), we determined that we have
jurisdiction pursuant to Section 307(b)(1) of the Clean Air
Act because the EPA’s Administrative Orders to ADEC and
Cominco constitute final agency action. 42 U.S.C. §
7607(b)(1) (granting jurisdiction to review final actions of
the Administrator). Applying the test in Bennett v. Spear,
520 U.S. 154 (1997), we held that the EPA’s actions were
final for the purposes of llate review because the EPA’s
findings represented its “ position on the factual circum-
stances,” the orders had determined the rights and obligations
of the parties, and legal consequences would follow if
Cominco chose to disregard the orders and commence
construction. Alaska, 244 F.3d at 750.
Ta
To address Petitioners’ contention that the record was
incomplete, we also directed the EPA to submit a complete
administrative record, withdraw its orders, or file an action in
district court. The EPA submitted a declaration that the
record was, in fact, complete. On August 3, 2001, we
directed Petitioners to respond to the EPA’s declaration. In
their responses, all the parties effectively agreed that the
record as it stood was adequate to resolve the issues on
appeal.
On February 28, 2002, in light of the parties’ agreement as
to the completeness of the record, we requested supplemental
briefing on the question of the EPA’s authority to issue the
orders. Having resolved these preliminary disputes, we now
turn to the merits of the appeal.
III. Authority of the EPA
We agree with the EPA that the plain text, structure, and
history of the Act compel the conclusion that the administra-
tive orders fell within the EPA’s enforcement and oversight
authority.
Under the traditional method of statutory construction, the
interpretation of a statute “begin{s] with the plain meaning of
its language.” Jn re Bonner Mall Partnership, 2 F.3d 899,
908 (9th Cir. 1993). “Our task is to give effect to the will of
Congress, and where its will has been expressed in reasona-
bly plain terms, that language must ordinarily be regarded as
conclusive.” Griffin v. Oceanic Contractors, Inc., 458 U.S.
564, 570 (1982) (internal quotation marks omitted).
The EPA’s enforcement powers are outlined in Section
113(aX(5), 42 U.S.C. § 7413(a)(5), and Section 167, 42
U.S.C. § 7477, of the Act.
Section 113(a)(5) provides:
Whenever, on the basis of any available information, the
Administrator finds that a State is not acting in compliance
with any requirement or prohibition of the chapter relating
to the construction of new sources or the modification of
existing sources, the Administrator may—
8a
(A) issue an order prohibiting the construction or modi-
fication of any major stationary source in any area to
which such requirement applies;
(B) issue an administrative penalty order in accordance
with [42 U.S.C. § 7413(d)], or
(C) bring a civil action under [42 U.S.C. § 7413(b)].
42 U.S.C. § 7413(a)(5). The referenced “chapter” includes
the PSD permit program in “Part C—Prevention of Signifi-
cant Deterioration of Air Quality.” See 42 U.S.C. § 7475;
H.R. Rep. No. 101-490(I), pt. 10, at 391 (1990) (Section
113(a)(5) “authorizes enforcement actions where a State is
not acting in compliance with any requirement of Part C or
Part D of Title I.”).
Under Section 167, the Administrator “shall ... take such
measures, including issuance of an order, or seeking injunc-
tive relief, as necessary to prevent the construction or modifi-
cation of a major emitting facility which does not conform to
the requirements of this part... .” 42 U.S.C. § 7477. “This
part” refers to Part C, which establishes the PSD program.
The PSD program is implemented through a permitting
system for new and modified “major emitting facilities” in
clean air areas. 42 U.S.C. §§ 7475, 7479(1). To receive a
permit, the applicant must fulfill the “preconstruction re-
quirement” that a “proposed facility [be] subject to the best
available control technology for each pollutant subject to
regulation. ...” 42 U.S.C. § 7475(a)(4). Thus, subjecting a
facility to BACT is both a “requirement... of the chapter
relating to the construction of new sources or the modifica-
tion of existing sources” under Section 113(a)(5), and a
“requirement{[ ] of this part” under Section 167. See S. Rep.
No. 95-127, at 12 (1977), reprinted in 3 A Legislative History
of the Clean Air Act Amendments of 1977, at 1386 (Comm.
Print 1978) (“[T]here is a national requirement that each new
major facility to be located in a clean air area install the best
available control technology.”’).
BACT is defined in Section 169(3) as
9a
an emission limitation based on the maximum degree of
reduction of each pollutant subject to regulation under this
chapter emitted from or which results from any major
emitting facility, which the permitting authority, on a case-
by-case basis, taking into account energy, environmental,
and economic impacts and other costs, determines is
achievable for such facility. . . .
42 U.S.C. § 7479(3). Here, ADEC, as the “permitting
authority,” made the initial BACT decision. Because the
EPA based its orders on the finding that ADEC had not
complied with the BACT requirement, the orders were
authorized by the plain language of Section 113(a)(5), as
“order[s] prohibiting the construction or modification of any
major stationary source in any area to which such require-
ment applies,” and of Section 167, as orders “necessary to
prevent the construction or modification of a major emitting
facility which does not conform to the requirements of this
part.”
The structure and legislative history of the Act further
support the EPA’s authority to issue the enforcement orders.
Since the original Clean Air Act of 1963, state and local
governments have had “primary responsibility” for “the
prevention and control of air pollution at its source.” Train v.
NRDC, 421 U.S. 60, 64 (1975); 42 U.S.C. § 7401(a)(3).
Following disappointing state response to air pollution
concerns, Congress has consistently increased over time
federal authority in pollution control.
In 1970, Congress amended the Act, Pub. L. 91-604, 84
Stat. 1676, “in order to assure that the requirements of the act
would be met if the State failed to adopt, implement, or
enforce the necessary measures.” S. Rep. No. 95-127, at 326
(1977), reprinted in 1977 U.S.C.C.A.N. 1077, 1405; see
Train, 421 U.S. at 64. Fundamentally restructuring the Act
“to create an aggressive federally-orchestrated program for
air pollution control,” the amendments directed the EPA to
publish NAAQS and the states to develop implementation
plans to meet them. William V. Luneburg, Clean Air Act
Implementation and the Impact of Whitman v. American
——
10a
Trucking Associations, Inc., 63 U. Pitt. L. Rev. 1, 5 (2001);
42 U.S.C. § 7410(a)(1).
In 1977, when it became clear that many areas of the coun-
try would not attain the NAAQS by the 1970 Amendments’
statutory deadline, Congress extended the deadline and
amended the Act, dividing the country into nonattainment
areas and clean air areas, and establishing the Prevention of
Significant Deterioration program to prescribe allowable
levels of air quality degradation in clean air areas. Douglas
R. Williams, Cooperative Federalism and the Clean Air Act:
A Defense of Minimum Federal Standards, 20 St. Louis U.
Pub. L. Rev. 67, 76 (2001). Congress recognized that the
states experienced internal industry “pressure... to relax
their standards with the threat of industrial relocation in
other, more permissive States.” S. Rep. No. 95-127, at 136-
37 (1977), reprinted in 1977 U.S.C.C.A.N. 1077, 1215.
Overarching federal leadership provided “protection for
States exercising their right to maintain clean air.” Jd.
The 1990 Amendments strengthened the EPA’s enforce-
ment authority in cases where states fail to enforce SIPs or
permit requirements. See H.R. Rep. No. 101-952, at 348,
358 (1990), reprinted in 1990 U.S.C.C.A.N. 3385, 3731,
3741. Amendments to Section 113(a)(5) extended enforce-
ment authority to include not only failure to comply with
state implementation plan provisions, but also a state’s
failure to comply with “any requirement or prohibition” of
the Act relating to new or modified sources. H.R. Rep. No.
10t-490(1), pt. 10, at 391.
Thus, although the state has discretion to make BACT
determinations as the permitting authority, the Act provides
for EPA enforcement when the state issues a permit based on
an improper determination. See H.R. Rep. 95-564, at 152
(1977), reprinted in 3 A Legislative History of the Clean Air
Act Amendments of 1977, at 533 (Comm. Print 1978) (“The
Administrator shall issue orders and seek other action to
prevent the issuance of an improper permit.”). Therefore,
based upon the plain language and the legislative history of
the Act and amendments to it, we hold that the EPA has the
lla
ultimate authority to decide whether the state has complied
with the BACT requirements of the Act and the state SIP.
ADEC and Cominco contend that the EPA exceeded its
authority in issuing the three administrative orders predicated
on a finding that ADEC’s BACT determination was inade-
quately justified. They argue that because Section 169(3)
gives ADEC, the “permitting authority,” discretion to deter-
mine BACT, the EPA lacked authority to veto ADEC’s
judgment based on a mere difference of opinion as to which
technology was BACT.
This argument is without merit because neither Section
113(a)(5) nor Section 167 contains any exemption for
requirements that involve the state’s exercise of discretion.
Nothing in the BACT definition of Section 169(3) limits the
EPA’s authority. It does not follow from the placement of
initial responsibility with the state permitting authority that
its decision is thereby insulated from the oversight and
enforcement authority assigned to the EPA in other sections
of the statute.
Petitioners further contend that the EPA’s authority extends
only to determining whether ADEC satisfied what they term
“objective requirements” listed in the Act and the SIP.
However, it is not clear what Petitioners mean by “objective
requirements,” as opposed to, presumably, discretionary
requirements. Instead of defining such requirements, Peti-
tioners offer a non-exhaustive list, including: the require-
ment of a PSD permit, the inclusion of a BACT determina-
tion in the permit, compliance with federally set limits on
emissions, and consideration of energy, environmental,
economic, and other costs. Whereas failure to comply with
any of the foregoing objective requirements would justify the
EPA’s issuance of enforcement orders under Sections
113(a)(5) and 167, Petitioners argue, the state’s BACT
determination itself is not subject to EPA approval or veto.
In support of this distinction, Petitioners cite United States
v. Solar Turbines, Inc., 732 F. Supp. 535 (M.D. Pa. 1989), in
which the district court analyzed whether a source’s actions
constituted a violation of the Act:
eee eee
l2a
[A] violation is to be assessed against objective stan-
dards, namely the source’s failure to apply for a permit or
receive a permit prior to construction; failure to supply
information requested of it by the issuing authority, or
failure to comply with specific quantifiable air quality
standards or restrictions on emission levels.
Id. 539. However, this case sheds no light on Petitioners’
argument because it examined the requirements that a source
must meet under the Act. Here, the question presented is
what requirements the state must meet.
In a move that seems to undermine their position, Petition-
ers also quote a Legal Opinion by the EPA’s Office of
General Counsel to define what they mean by “objective
requirements:”
[I}n the case of a decision applying best available control
technology (BACT) under Section 165(a)(4) for PSD, if a
state has met all procedural norms, considered all avail-
able control technologies, and given a reasoned justifica-
tion of the basis for its decision, EPA has no grounds on _
which to challenge a final substantive state decision that
does not violate such objective standards.
(emphasis added).
As the emphasized portion demonstrates, this Opinion
actually supports the EPA’s authority to determine the
reasonableness or adequacy of the state’s justification for its
decision, which is exactly what the EPA did here. The cover
letter to the December 10, 1999 Finding of Noncompliance
and Order stated the EPA’s belief that:
ADEC’s own analysis supports the determination that
BACT is selective catalytic reduction (SCR)... ADEC’s
decision in the proposed permit therefore is both arbitrary
and erroneous.... [T]he State’s record reflects that the
cost-effectiveness and the collateral issues of energy, en-
vironmental, or economic impacts, and other costs, do not
justify failure to select SCR as BACT in this case.
l3a
Whatever Petitioners mean by “objective requirements,” they
must concede that the provision of a reasoned justification is
one of them. We conclude, therefore, that the EPA had the
authority to issue findings and orders on the ground that the
State failed to provide an adequate justification for its BACT
decision.
IV. Validity of the Orders
Petitioners alternatively argue that the EPA erred in finding
that ADEC was not in compliance because ADEC’s BACT
determination fulfilled all requirements of the Act. The EPA
maintains that ADEC’s determination that Low NOx was
BACT was “nothing short of incomprehensible, unreasoned,
Under the Act, we may reverse a final action by the EPA if
it is “arbitrary, capricious, an abuse of discretion, or other-
wise not in accordance with law.” 42 USC. §
7607(d)(9)(A); Exxon Mobil Corp. v. United States EPA, 217
F.3d 1246, 1248 (9th Cir. 2000). Upon review of the admin-
istrative record, we conclude that EPA did not act arbi-
trarily or iciously in issuing its Findings of Noncompli-
ance and prohibiting construction of the MG-17
generator until ADEC produced a valid PSD permit.
A common approach to determining BACT is the “top-
down” method, which ADEC to apply. Under this
method, as detailed in the EPA’s New Source Review Work-
shop Manual (1990), the applicant ranks all available control
technologies in descending order of control effectiveness.
The most stringent technology is BACT unless the applicant
can show that it is not technically feasible, or if y,
environmental, or economic i ts justify a conclusion
it is not achievable. Citizens for Clean Air v. United States
EPA, 959 F.2d 839, 845-46 (9th Cir. 1992). If the top choice
is eliminated, then the next most stringent alternative is
considered, and so on. The most effective control option not
eliminated is BACT. /d.
Although the top-down h is not mandated by the
Act, if a state purports to follow this method, it should do so
Pe
l4a
in a reasoned and justified manner. ADEC’s December 10
Technical Analysis Report rejected SCR because it would
have adverse economic impacts on the Red Dog Mine. The
report states that there are several situations in which a
permitting authority can reject a control option for economic
considerations: (1) when the applicant, i.e., Cominco, shows
that the costs of the control are disproportionately high
compared to the cost of control in recent permit decisions; (2)
when the cost-effectiveness of the control is outside the range
of costs being borne by similar sources in recent BACT
determinations; and (3) when the applicant shows the cost of
ee option will cause adverse economic impact to the
acility.
ADEC’s report demonstrates, however, that none of these
situations were present. As to the first situation, the report
reveals that there were no recent permit decisions involving
BACT determinations for diesel engines used as primary
power generators.
As to the second, the cost-effectiveness of recent NOx
control BACT decisions ranged from $0 to $7,000 per ton of
NOx removed. According to ADEC’s estimate, the cost-
effectiveness of SCR was $2,100 per ton of NOx removed, a
cost well within the applicable range.
Finally, ADEC attempted to determine whether the costs of
SCR would be excessive by analogizing the costs of the MG-
17 generator to the costs of other electric utilities. ADEC
began with the assumption that SCR for MG-17 would cost 3
cents per kilowatt-hour. It reasoned that if Cominco “did not
have a powerhouse, it would probably buy power from a
rural Alaska utility. From a cursory review, it appears that
the average cost of electricity in rural-Alaska is approxi-
mately 15¢ per kilowatt hour.” Because a 3¢ increase would
“be equivalent to a 20% increase in the electric rate of the
facility,” ADEC concluded that “this is a disproportionate
cost increase when viewed as an electric utility.
This rationale is unfounded, however, because Cominco
does not, in fact, buy power from an electric utility. There-
fore, the use of the 15¢ figure is not justified. ADEC itself
1Sa
acknowledges the flimsiness of its own hypothetical in the
report:
Another perhaps better way to determine if the cost of
BACT is excessive, is for the applicant to present detailed
financial information showing its effect on the operation.
However, the applicant did not present this information.
Therefore, no judgment can be made as to the impact of a
$2.1 million control cost on the operation, profitability,
and competitiveness of the Red Dog Mine.
ADEC’s report demonstrates that Cominco failed to show
that any of the situations in which a control option can be
rejected for cost considerations was applicable. Rather than
concluding, logically, that Cominco had failed to show that
SCR could be eliminated, ADEC instead invented its own
reason for the economic infeasibility of SCR. ADEC de-
scribed the Mine’s “dramatic” reversal of unemployment
rates in its borough:
Before the Mine opened in 1990, borough wages were
well below state average wages. ... The Mine now pro-
vides high paying year round employment. .
Cominco’s contractors, vendors, and wages have boosted
the borough’s private sector economy. ... With govern-
ment support and endorsement of Cominco’s operations,
including the Production Rate Increase Project, the Red
Dog Mine will continue to influence and benefit the resi-
dents and economy of this region.
ADEC concluded that it had chosen, as the “foremost
consideration to judge economic impacts of SCR,” the
“direct cost of SCR technology and its relationship to
retaining the Mine’s world competitiveness as it relates to
community socioeconomic impacts.” To “support
Cominco’s [PRI Project]... and its contributions to the
region,” ADEC rejected SCR “based on excessive economic
cost—$2.9 million capital cost, with annualized costs
approaching $635,000.” The report fails to explain how the
costs of SCR would affect the Mine’s world competitiveness
or why the capital cost is excessive.
l6a
ADEC’s apparent motivation for the elimination of SCR—
appreciation for Cominco’s contribution to the local econ-
omy—is not an accepted justification in the top-down
approach. Worse still, it is uncomfortably reminiscent of one
of the very reasons Congress granted EPA enforcement
authority—to protect states from industry pressure to issue
ill-advised permits. See S. Rep. No. 95-127, at 136.
Because ADEC’s report shows that (1) Cominco failed to
meet its burden of demonstrating that SCR was economically
infeasible; and (2) ADEC failed to provide a reasoned
justification for its elimination of SCR as a control option,
the EPA did not act arbitrarily and capriciously in concluding
that ADEC abused its discretion by making an internally
inconsistent and unreasonable BACT determination. The
petition for review is therefore
DENIED.
17a
APPENDIX B
UNITED STATES COURT OF APPEALS
FOR THE NINTH CIRCUIT
Nos. 00-70166, 00-70301, 00-70169, 00-70175.
STATE OF ALASKA, DEPARTMENT OF ENVIRONMENTAL
CONSERVATION, COMINCO ALASKA, INC., AN ALASKA
CORPORATION,
Petitioner,
Vv.
UNITED STATES ENVIRONMENTAL PROTECTION AGENCY,
CHRISTIE WHITMAN,” ITS ADMINISTRATOR, AND CHUCK
CLARKE, REGIONAL ADMINISTRATOR, REGION 10, OF THE
UNITED STATES ENVIRONMENTAL PROTECTION AGENCY,
Responients.
STATE OF ALASKA, DEPARTMENT OF ENVIRONMENTAL
CONSERVATION, COMINCO ALASKA, INC., AN ALASKA
CORPORATION,
Petitioner,
Vv.
UNITED STATES ENVIRONMENTAL PROTECTION AGENCY,
CHRISTIE WHITMAN, ITS ADMINISTRATOR, AND CHUCK
CLARKE, REGIONAL ADMINISTRATOR, REGION 10, OF THE
UNITED STATES ENVIRONMENTAL PROTECTION AGENCY,
Respondents.
* Pursuant to Fed. R. App. P. 43(c), Christie Whitman is auto-
matically substituted as a party respondent for Carol Browner.
De a OO ee
18a
Argued and Submitted Feb. 13, 2001
Filed March 27, 2001
Before: REINHARDT, WARDLAW and GOULD, Circuit
Judges.
ORDER
The Alaska Department of Environmental Conservation
(“ADEC”) and Cominco Alaska, Inc. (“Cominco”) petition
this Court for review of three enforcement orders (the
“Orders”) entered by the United States Environmental
Protection Agency (“EPA”), which effectively invalidated an
air quality construction permit issued by ADEC for the
construction of a power generator at Cominco’s Alaskan
mining facility located about 100 miles above the Arctic
Circle. Petitioners challenge the EPA’s authority to invali-
date the permit under federal and state law. The EPA asserts
that it has the authority to regulate such construction under
the Clean Air Act (“CAA” or the “Act”’) and further claims
that this Court lacks subject matter jurisdiction to consider
ADEC’s and Cominco’s petitions because the Orders are not
“final agency action” subject to review in the United States
Courts of Appeal.
We first consider the question of our jurisdiction to review
the Orders. The parties agree that we have jurisdiction, if at
all, pursuant to section 307(b)(1) of the CAA, 42 U.S.C. §
7607(b)(1), which gives the Court jurisdiction over “any...
final action taken, by the Administrator.” The EPA argues
that none of the Orders constitutes final agency action and
thus none is reviewable.
Each of the Orders is predicated on the EPA’s position that
the Best Available Control Technology (“BACT”) for the
proposed new Wartsila generator MG-17 at Cominco’s Red
Dog Mine facility is Selective Catalytic Reduction as op-
19a
posed to Low NOx emission reduction, a less costly technol-
ogy proposed by Cominco and approved by ADEC. In its
“Finding of Noncompliance and Order” dated December 10,
1999, the EPA found that the Low NOx emission control for
MG-17 does not comply with the CAA or the Alaska State
Implementation Plan (“SIP”) for the CAA. Pursuant to 42
U.S.C. §§ 7413(a)(S) and 7477, the EPA ordered ADEC to
withhold issuance of its proposed Prevention of Significant
Deterioration (“PSD”) permit for Cominco. Concluding that
Low NOx was the appropriate BACT for the MG-17 genera-
tor, ADEC, shortly after receiving the December 10, 1999
Order, issued the final PSD permit. In a second order
directed to Cominco dated February 8, 2000, finding it
“necessary to prevent any further construction or modifica-
tion at the Red Dog mine facility,” the EPA prohibited
Cominco from commencing any and all construction or
modification activities at the Red Dog Mine facility associ-
ated with the Wartsila generator MG-17. The EPA’s third
order, dated March 7, 2000, modified the February 8, 2000
Order to accommodate the unique weather-related construc-
tion limitations present at the Red Dog Mine site and allowed
certain preliminary summer construction activities. On April
25, 2000, the EPA withdrew its December 10, 1999 Order
directed to ADEC, in light of ADEC’s issuance of the
construction permit after it received the order, noting that
“the Order does not impose any continuing prohibitions or
obligations to ADEC.” In an accompanying letter, however,
the EPA Deputy Regional Administrator stated:
EPA still believes that the final PSD permit issued to
Cominco is not in compliance with th~ Clean Air Act or
the Alaska SIP. Region 10 is withdrawing only the Order
portion of the December 10, 1999 document. Thus, the
December 10, 1999 and February 8, 2000 Findings under
Section [7413(a)(5)] remain unchanged, as does the
March 7, 2000 Order issued to Cominco.
ADEC and Cominco petitioned for review of the Orders.
Respondents, the EPA, Christie Whitman, and Chuck Clarke,
Regional Administrator, Region 10, move to dismiss the
petitions for lack of subject matter jurisdiction. The EPA
20a
asserts that the Administrative Orders issued to Cominco and
ADEC do not constitute the “final action of the Administra-
tor.” In Bennett v. Spear, 520 U.S. 154 (1997), recently
reaffirmed in Whitman v. American Trucking Ass‘ns, Inc.,
531 U.S. 457 (2001), the Supreme Court explained that two
conditions must be satisfied in order for agency action to be
“final” for purposes of appellate review: the action must
mark the “consummation” of the agency’s decision-making
process, and it must “be one by which rights or obligations
have been determined, or from which legal consequences
will flow.” Bennett, 520 U.S. at 177-78 (citation and quota-
tions omitted).
Like the Supreme Court in Bennett and American Trucking,
we have little trouble concluding, especially in light of the
representations as to the EPA’s position made in oral argu-
ment by its counsel, that both Bennett conditions are met
here. The EPA argues that the Orders are not a “final ac-
tion,” although the findings in the Orders are its “last word”
on its position as to Selective Catalytic Reduction as BACT
for MG-17 and Cominco is in legal jeopardy if it fails to
comply with the Orders. The EPA contends that because it
has not actually commenced an enforcement action, the
Orders are not subject to review. There is, however, no
question that the EPA asserted its final position on the factual
circumstances upon which the Orders are predicated: It is
EPA’s position that if Cominco builds the MG-17 generator
using Low NOx it would be in violation of the Act, the
Alaskan SIP, and its Orders. The EPA’s position is unalter-
able; according to counsel, it would change only if the
circumstances surrounding the construction of MG-17
change.
The “rights or obligations” of the parties have been deter-
mined by these Orders. As paragraph No. 49 of the Findings
of Fact in the February 8 Order states, the EPA found it
“necessary” to issue the Order to “prevent any further
construction or modification at the Red Dog mine facility.”
The EPA is right: The effect of the February 8 Order is to
halt construction at Cominco’s Red Dog Mine facility at a
considerable cost of both time and money to Cominco.
2la
Moreover, “legal consequences will flow,” if Cominco
chooses to disregard the Order and go forward with construc-
tion. As the EPA wrote in its Motion to Dismiss the Petition
for Lack of Subject Matter Jurisdiction, “EPA could ask, and
the district court could assess, penalties both for Cominco’s
alleged violation of the Act’s PSD requirements and for any
alleged violation of the order.” At argument EPA counsel
explained that the language “could” referred only to its
decision to seek enforcement of its Orders and a district
court’s decision to enforce them. Thus the “could” language
did not refer to a tentative conclusion as to the merits by the
EPA, or to any ongoing EPA proceedings in that regard; it
referred simply to whether the EPA would commence
judicial proceedings to remedy what it views irretrievably as
a violation of the Act. Under EPA’s construction of its
Orders, if it decides to institute such proceedings, Cominco
and its employees would be subject to criminal and civil
penalties for the violation of its Orders, as well as for the
violation of the CAA.
Finally, our review will not benefit from further factual
development of the record, as the principal issue before us is
a legal question—whether it is the state, through ADEC, or
the EPA which bears the ultimate responsibility and authority
to decide what emissions reductions will be required from
which sources, see 42 U.S.C. §§ 7410(a), 7411, and whether
the EPA acted in an arbitrary and capricious manner in
issuing the Orders based on the record before it at the time it
made its decision that the use of Low NOx on MG-17 would
violate the Act and the PSD provisions of the SIP.
Having determined that the Orders are final and that we
have jurisdiction, we do not consider the merits at this time
because in order to do so we require, as explained below, the
submission of an appropriate administrative record as well as
further briefing. Also, because the EPA argued to this Court
that the Orders were not “final” and that it had not yet
determined whether to seek enforcement in the district court,
it seems appropriate to provide the Agency with a fair
opportunity either to commence such an enforcement pro-
ceeding, as contemplated by 42 U.S.C. § 7413(b), or to
22a
withdraw the Orders, before we proceed further with the
petition for review. Thus, we express no view as to (a)
whether the EPA has the authority under the CAA to invali-
date the ADEC permit, or (b) if so, whether the EPA acted
arbitrarily and capriciously in issuing the Orders. Accord-
ingly, we order as follows:
Within 60 days of this order, the EPA may either (1) sub-
mit a complete administrative record which will allow this
Court to review the justifications for the EPA’s decisions to
issue the Orders before us; (2) withdraw the Orders that are
the subjects of these petitions; or (3) file an enforcement
action, pursuant to 42 U.S.C. § 7413(b), in the appropriate
United States District Court.'
With respect to the first option, the record we would be
called upon to review, should we decide that the EPA has the
authority to overrule ADEC, is that upon which the EPA
relied in its determination that Selective Catalytic Reduction,
and not Low NOx, is the BACT for the MG-17. See 5
U.S.C. § 706; Ober v. EPA, 84 F.3d 304, 313-15 (9th Cir.
1996); see also Florida Power & Light. Co. v. Lorion, 470
U.S. 729, 743-44 (1985) (“The task of the reviewing court is
to apply the appropriate APA standard of review, 5 U.S.C. §
706, to the agency decision based on the record the agency
presents to the reviewing court.”); Harrison v. PPG Indus.,
Inc., 446 U.S. 578, 597 (1980) (requiring a “meaningful
record to review,” which “fully comports with the traditional
role of appellate courts in reviewing agency decisions that
are based on development of factual issues by means of an
administrative record”). To the extent necessary to provide a
full and complete administrative record of the basis for the
agency’s final decision and the Orders, the EPA must _
duce not only documentary evidence but also affidavits of the
Administrator or her delegates as needed to permit review.
See Camp v. Pitts, 411 U.S. 138, 142-43 (1973); Citizens to
' An enforcement action in the appropriate United States Dis-
trict Court in our view may ge a preferable means of resolv-
ng the issues in this case, for the parties in that context will be
able to develop a full record on pertinent issues.
23a
Preserve Overton Park, Inc. v. Volpe, 401 U.S. 402, 420-21
(1971) (holding that “since the bare record may not disclose
the factors that were considered or the Secretary’s construc-
tion of the evidence it may be necessary . . . to require some
explanation in order to determine if the Secretary acted
within the scope of his authority and if the Secretary’s action
was justifiable under the applicable standard”), overruled on
unrelated grounds by Califano v. Sanders, 430 U.S. 99, 105
1977). Communications setting forth and evaluating alterna-
tives to the Orders must also be included.
Should the EPA opt to submit the administrative record
rather than to pursue an enforcement action or to withdraw its
Orders, petitioners and respondents are ordered to file, within
21 days of such submission, supplemental briefs, not to
exceed 15 pages, assessing the impact, if any, of Whitman v.
American Trucking Ass‘ns, Inc., 531 U.S. 457 (2001), on the
question whether it is the EPA or ADEC which has the
ultimate authority to make BACT determinations.
The parties shall provide notice of the status of these pro-
ceedings to this Court within 60 days hereof. Submission of
this matter is hereby vacated until further notice by this
Court.
IT IS SO ORDERED.
Re 8 oe BOOS ek
24a
APPENDIX C
UNITED STATES COURT OF APPEALS
FOR THE NINTH CIRCUIT
Nos. 00-70166, 00-70169, 00-70175 and 00-70301
STATE OF ALASKA, DEPARTMENT OF ENVIRONMENTAL
CONSERVATION,
Petitioner,
Vv.
UNITED STATES ENVIRONMENTAL PROTECTION AGENCY,
Respondent.
COMINCO ALASKA INC .» AN ALASKA CORPORATION,
Petitioner,
Vv.
UNITED STATES ENVIRONMENTAL PROTECTION AGENCY,
Respondent.
COMINCO ALASKA INC., AN ALASKA CORPORATION,
Petitioner,
Vv.
UNITED STATES ENVIRONMENTAL PROTECTION AGENCY,
Respondent.
25a
COMINCO ALASKA INC., AN ALASKA CORPORATION,
Petitioner,
Vv.
UNITED STATES ENVIRONMENTAL PROTECTION AGENCY;
CAROL M. BROWNER, ADMINISTRATOR, AND CHUCK
CLARKE, REGIONAL ADMINISTRATOR, REGION 10, OF THE
UNITED STATES ENVIRONMENTAL PROTECTION AGENCY,
Respondents.
Filed Feb. 28, 2002
A. ey REINHARDT, WARDLAW and GOULD, Circuit
Judges.
ORDER
Having considered the recent submissions of the ies
agreeing to the factual record on appeal and the briefs filed
beginning in June 2000 (almost two years ago), we have
determined that supplemental briefing would be of assistance
in the determination of the cause. Therefore, it is ORDERED
that each side file a supplemental brief not to exceed twenty-
five pages within twenty-eight days of the date hereof on the
following question: whether it is the state of Alaska (through
ADEC) or the EPA that bears the ultimate legal authority and
responsibility under the Clean Air Act to determine whether
an individual Prevention of Significant Deterioration permit
issued by Alaska pursuant to its State Implementation Plan
(SIP) meets the requirements of the Clean Air Act or the SIP.
If any pay desires additional oral argument in this matter,
it file a request, along with a brief statement of the
reasons it believes additional argument is necessary.
It is so ( RDERED.
26a
APPENDIX D
UNITED STATES
ENVIRONMENTAL PROTECTION AGENCY
In the Matter of: )
)
State of Alaska Department ) Docket No. CAA-10-99-0263
of Environmental )
Conservation, ) FINDING OF
NONCOMPLIANCE and
ORDER
113(a)(5) and 167 of the
Clean Air Act.
)
)
Proceeding under Sections )
) (42U.S.C. §§ 7413 and 7477)
)
)
I. FINDING OF NONCOMPLIANCE and ORDER
1. This Finding of Noncompliance and Order is issued by
the Regional Administrator, Region 10, United States Envi-
ronmental Protection Agency (EPA), to the State of Alaska,
Department of Environmental Conservation (ADEC),
pursuant to Sections 1 13(a)(5) and 167 of the Clean Air Act
(CAA or Act), 42 U.S.C. §§ 7413(a)(5) and 7477.
ant The oy of the Administrator of EPA to issue
ena to Section 1 13(a)(5) and Section
167 of the Anat 42 C. §§ 7413(a)(5) and 7477, has been
delegated to the Regional Administrator. The Regional
Administrator has consulted with the Assistant Administrator
for the Office of Enforcement and Compliance Assurance
RS Se ES ey See ie Ae.
Il. STATUTORY AND REGULATORY AUTHORITY
3. The Administrator of EPA, t to Section 109 of
the Act, 42 U.S.C. § 7409, promulgated National Primary
and Secondary Ambient Air Quality Standards (NAAQS) for
LE LI ET ELL EE IL LE CT I a A Ut tReet tac Mle YER! ee gr
SO rm | am
27a
certain criteria pollutants, including nitrogen dioxide (NO2).
40 C.F.R. §§ 50.4 to 50.12.
4. Pursuant to Section 107(d) of the Act, 42 U.S.C. §
7407(d), the Administrator promulgates lists of attainment
status designations _= each air quality control region
(AQCR) in ev These lists contain the attainment
status of each A R for each of the criteria pollutants. The
attainment status desi for the Alaska AQCRs appear
at 40 C.F.R. § 81.302.
5. Cominco Alaska, Inc. (Cominco) owns and operates
the Red Dog mine facility, a surface zinc and lead ore mining
operation, which is located in the Northern Alaska Interstate
AQCR and is in an area that is in attainment or unclassifiable
with respect to the NAAQS. 40 C.F.R. § 81.302.
6. Part C of the Act, 42 U.S.C. §§ 7470-7492, requires
the Administrator to promulgate regulations for prevention of
significant deterioration (PSD) of air quality in areas desig-
nated in accordance with Section 107(d) of the Act, 42
U.S.C. § 7407(d), as in attainment or unclassifiable.
7. Pursuant to Sections 110 and 165(e)(3) of the Act, 42
U.S.C. hae awe 7410 and 7471(e)(3), EPA promulgated two sets of
largely identical regulations for preventing the significant
of air quality in areas where the existing air
cular isteneraetaaieaiameate In States without
a PSD program and in those States where EPA has de
authority to administer the federal PSD program to the State
the federal PSD regulations at 40 C.F.R. § 51.21 have been
into the various State Implementation Plans
(SIPs) of such States. in the remaining Sas, © EPA has
approved as part of the SIP a State imple-
mented directly by the State, as meeting de toaniemnenth of
Part C of the Act and the PSD regulations at 40 CFR §
51.166.
8. EPA has approved 18 AAC 50.020, 50.021, 50.300,
50.400, 50.510, 50.520, 50.530, 50.600, 50.620, and 50.900,
as in effect on June 2, 1988, as a revision to the Alaska SIP
and as meeting the requirements of Part C of the Act and the
ee a ere
28a
PSD regulations at 40 C.F.R. § 51.166 for preventing the
significant deterioration of air quality. See 40 C.F.R. §
52.96(a). (48 Fed. Reg. 30626, July 5, 1983, and subsequent
amendments.) References in this document to Alaska
statutory or regulatory provisions are to the current SIP-
approved versions of the statute or regulation.
9. Section 165 of the Act, 42 U.S.C. § 7475, prohibits the
construction of a major emitting facility in any area subject to
the requirements of Part C of the Act and the PSD regula-
tions unless, among other things, a permit has been issued for
the proposed facility in accordance with Part C of the Act
which sets forth emission limitations that a | to the
requirements of Part C, and the facility is sub - to
best available control technology (BACT) for each po fhutent
subject to regulation under Title I of the Act that is emitted
from or which results from such facility.
10. “Ambient air” is defined at Alaska Statutes
46.14.99(2)( 1993) as “that portion of the atmosphere, exter-
nal to buildings, to which the general public has access.”
11. “Actual emissions” as defined in 18 AAC
50.900(1)(1991) means “for each air contaminant, the™
average rate in tons per year that a facility actually emitted
the most recent two years of normal operation; the
during
department will, in its discretion, consider facility-specific
allowable emissions to be actual emissions of an air contami-
nant.”
12. “Construct” as defined in 18 AAC 50.900(13)(1991)
means “to make a change or a series of changes in operation
or any physical changes or additions to a source which
increase the actual emissions of an air pollutant.”
13. “Allowable emissions” as defined in 18 AAC
50.900(4)1991) means “the calculated emission rate of a
source or facility using the maximum rated capacity and
enforceable limitations and conditions on emissions and
operations.”
14. “Modify” as defined in 18 AAC 50.900(28)(1991)
means “to make a change or a series of changes in operation
29a
or any physical changes or additions to a source which
increase the actual emissions of an air pollutant.”
15. 18 AAC 50.300(a)(1991) states that no person may
construct, modify, reconstruct, operate, or cause the opera-
tion of a facility meeting the criteria in that subsection
without a hry from ADEC. The list of facilities covered
by 18 AAC 50.300(a) includes a facility which has allowable
emissions of more than 250 tons per of a lated air
contaminant and which is modified hee i August 7, 1980, or
after the date of the most recent permit issued to the facility
under 18 AAC 50.400(c)(3), causing an increase in actual
emissions equal to or exceeding any of the thresholds identi-
fied in that subsection.
16. A permit application for a facility subject to 18 AAC
50.300(a)(5) or (6) must include, among other things, a
detailed demonstration that the expected maximum emissions
from the facility will not cause or contribute to a violation of
an ambient air standard or allowable increment in 18 AAC
50.020(b).
17. 18 AAC 50.400(c)\(3)(A)(1991) states that ADEC will
issue a permit only if the applicant shows that, for a facility
subject to 18 AAC 50.300(a)(5) or (6), BACT for controlling
emissions of each regulated pollutant will be installed for
each new or modified source.
18. 18 AAC 50.900(9)(1991) defines “best available con-
trol technology” as an emission limitation which represents
the maximum reduction achievable for each regulated air
pollutant taking into account energy, environmental, and
19. Section 113(a\(5) of the Act, 42 U.S.C. § 7413(a)(5)
provides:
Whenever, on the basis of ary-available information, the
Administrator finds that a State is not acting in compli-
ance with any requirement or prohibition of the [Act] re-
lating to the construction of new sources or the modifica-
tion of existing sources, the Administrator may—
ew se eee
=
30a
(A) issue an order prohibiting the construction or
modification of any major stationary source in any area to
which such requirement applies;
(B) issue an administrative penalty order in accor-
dance with subsection (d) of this section; or
(C) bring a civil action under subsection (b) of this
section.
Nothing in this subsection shall preclude the United
States from commencing a criminal action under subsec-
tion (c) of this section at any time for any such violation.
20. Section 167 of the Act, 42 U.S.C. § 7477, provides
that the Administrator shall take such measures, including
issuance of an order, as necessary to prevent the construction
or modification of a major emitting facility which does not
conform to the requirements of Part C of the Act.
21. Section 169(1) of the Act, 42 U.S.C. § 7479(1), de-
fines a major emitting facility, in pertinent part, as a station-
ary source which emits or has the potential to emit 250 tons
per year or more of any air pollutant.
22. A State does not conform to the requirements of Part C
of the Act if, among other things, it allows a major emitting
facility to commence construction or modification prior to
receipt of a PSD permit or issues a PSD permit to a facility
without subjecting the facility to BACT for each pollutant
subject to regulation under Title I of the Act that is emitted
from or which results from such facility.
23. A major emitting facility does not conform to the
requirements of Part C if, among other things, it commences
construction or modification prior to receipt of a PSD it
or if the facility is not subject to BACT for each pollutant
subject to + under Title I of the Act that is emitted
from or which results from such facility.
Ill. FINDINGS OF FACT
24. On June 17, 1988, ADEC issued a PSD permit, Permit
No. 8732-AA001;-that authorized the construction of the Red
a ee
3la
Dog mine facility, including the installation of five Wartsila
diesel generators (MG-1, MG-2, MG-3, MG-4, and MG-5).
25. ADEC revised and replaced the June 1988 PSD permit
on several occasions, including a revision dated July 27,
1994, Permit No. 9332-AA003, which: (a) removed from the
permit a NOx BACT limit of 750 parts per million volume
dried (ppmvd) that applied to the five Wartsila diesel genera-
tors, and substituted a limit of 109,660,000 kilowatt hours
per continuous 365-day period (kW-hr/yr) for MG-1, MG-3,
MG-4, and MG-5, (b) removed the stand-by limits on MG-2
and permitted it to full-time, and (c) authoriz~d the
installation and full-time operation of a sixth Wartsila diesel
generator (MG-6).
26. The Red Dog mine facility currently operates under
the terms and conditions of Permit No. 9332-AA003, as
amended December 4, 1996.
27. On March 27, 1996, prior to receiving an amended
PSD permit, Cominco requested that ADEC allow Cominco
to make on-site preparations for changes to the facility that
would allow for production increases. On April 2, 1996,
ADEC granted Cominco a waiver to allow the company to
conduct specified procurement and construction activities on
the condition that Cominco prepare and submit a request for
a permit amendment concurrent with the activities.
28. Between April 1996 and May 1998, Cominco con-
structed a new gyratory crusher at the Red Dog mine facility
without a permit.
29. On June 29, 1998, Cominco submitted a PSD permit
application to ADEC for what it referred to as a “production
rate increase project” that was expected to increase the
mine’s ore ing rate from approximately 2,200,000
tons per year to 3,500,900 tons per year and to increase the
production of zinc and lead concentrate from 854,000 tons
per year to 1,400,000 tons per year. Cominco submitted a
supplement to the application to ADEC on April 6, 1999. As
part of the production rate increase project, Cominco re-
quested that ADEC, among other things, remove the air
32a
quality operating restrictions on the four Wartsila diesel
generators that were installed in 1988 and which still had
operational limits on them (MG-1, MG-3, MG-4, MG-5),
“add” a seventh Wartsila diesel generator (MG-17), “add”
the new gyratory crusher that Cominco had already installed,
and approve the addition of other equipment and changes
necessary to support the production rate increase project.
30. On May 4, 1999, ADEC issued a preliminary PSD
permit (preliminary draft PSD permit) for the production rate
increase project for review and public comment. The pre-
liminary draft PSD permit proposed to remove the opera-
tional cap of 109,660,000 kW-hr/year that applied to Wartsila
diesel generators MG-1, MG-3, MG-4, and MG-S, to “add”
the seventh Wartsila diesel generator (MG-17), to “add” the
new gyrator crusher, and to approve the addition of other
equipment and changes that Cominco requested in its PSD
permit application for the production rate increase project.
31. ADEC prepared a preliminary technical analysis report
(Preliminary Technical Report) to accompany the prelimi-
nary draft PSD permit. The Preliminary Technical Report
stated that the production rate increase project is expected to
increase actual NOx emissions by up to 1,100 tons per year;
carbon monoxide (CO) emissions by 90 tons per year;
particulate matter (PM) emissions by 35 tons per year, PM
emissions less than 10 micrometers in diameter Yoo) 10) by
35 tons per year; volatile organic compound ( emis-
sions by 59 tons per year; and lead (Pb) emissions by 0.046
tons per year. The proposed production rate increase project
is expected to reduce sulfur dioxide (SO2) emissions by 37
tons per year.
32. In the preliminary draft PSD permit and Preliminary
Technical Report, ADEC concluded that, of the seven
Wartsila diesel generators, only MG-5 and MG-17 were
subject to PSD requirements and therefore required BACT.
EPA regulations require that technical and economic feasibil-
ity be considered when determining BACT. In the Prelimi-
nary Technical Report ADEC determined that Selective
Catalytic Reduction (SCR) is a technically and economically
feasible emission control technology for the Wartsila genera-
A
!
7
i
7
)
:
:
:
-
7
:
:
33a
tors and that SCR could result in reductions of 712 tons per
year of NOx for each Wartsila diesel generator. The Pre-
liminary Technical Report also concluded that installation of
low NOx controls would result in reductions of only 273 tons
per year of NOx for each Wartsila diesel generator. The
Preliminary Technical Report then concluded that BACT for
MG-5 _ MG-17 was an emission hunt based on low NOx
controls.
33. The Red Dog mine facility was at the time of construc-
tion and continues to be a “major emitting facility” under
Section 169(1) of the Act, 42 U.S.C. § 7479(1).
34. The Red Dog mine facility was at the time of construc-
tion and continues to be a facility with allowable emissions,
as defined in 18 AAC 50.900(4), of at least 250 tons per year
of a regulated air contaminant. The Red Dog mine facility 1s
therefore a “facility,” as listed in 18 AAC 50.300(a)(6).
35. The production rate increase project will “modify,” as
that term is defined in 18 AAC 50.900(28), the Red Dog
mine facility.
36. The production rate inci.ase project will increase
actual emissions of NOx, PM, PM-10, and VOC from the
Red Dog mine facility by more than the thresholds identified
in 18 AAC 50.300(a)(6)(C) and will occur after 1980 and
after the date of the most recent permit issued for the Red
Dog mine under 18 AAC 50.400(c)(3). The Red Dog mine
facility and production rate increase project are therefore a
“facility,” as listed in 18 AAC 50.300(a)(6)(C).
37. The public comment period on the preliminary draft
PSD permit for the production rate increase project ended on
June 2, 1999.
38. On June 2, 1999, the United States Department of the
Interior, National Park Service (NPS), submitted comments
on the preliminary draft PSD permit for the production rate
increase project. The NPS comments raised several concerns
with the preliminary draft PSD permit, including the follow-
ing:
34a
a. ADEC failed to subject four of the Wartsila diesel
generators (MG-1 and MG-3 through MG-5) to PSD, includ-
ing BACT. These generators are part of the production rate
increase project because the preliminary draft PSD permit
would remove an operating restriction on these generators.
b. ADEC failed to require SCR on the two Wartsila die-
sel generators which ADEC acknowledges are subject to
BACT (MG-5 and MG-1I7). SCR is BACT for the Wartsila
diesel generators.
39. By letter dated July 29, 1999, EPA informed ADEC
that it agreed with NPS’s comments and had concluded that:
a. The Wartsila diesel generators MG-1 and MG-3
through MG-S5 are subject to PSD, including BACT, because
these generators are part of the production rate increase
project since the preliminary draft PSD permit would remove
the existing operating restriction on these generators.
b. Based on ADEC’s preliminary Technical Report that
accompanied the preliminary draft PSD permit, SCR is
BACT for the Wartsila diesel generators MG-1, MG-3,
MG-4, MG-5, and MG-17.
40. On September 3, 1999, ADEC provided to EPA a final
draft permit No. 9932-AC005 for the Cominco Red Dog
mine facility. The final draft permit was accompanied by a
Final Technical Analysis Report (Final Technical Report)
and Response to Comment document.
41. The Final Technical Report concluded that an emis-
sion rate achievable with low NOx controls to be BACT on
Wartsila diesel generators MG-5 and MG-17. The final draft
PSD permit includes an emission rate limit of 121.3 Ib/hour
on MG-5 and MG-17 based on low NOx controls.
42. The final draft PSD permit does not require the instal-
lation of BACT on MG-1, MG-3, and MG-4, but instead only
proposes to reinstate the same limit on total annual emissions
from MG-1, MG-3, and MG-4 which previously applied to
total annual emissions from MG-1 through MG-S5. This limit
is listed in the final draft PSD permit as:
35a
P ©. 2259 tons NOx/year from MG-1, MG-3, and MG-
(2) 750 ppm NOx corrected to 7% oxygen from each
unit.
43. Neither the Final Technical Report nor the final draft
PSD permit clearly identify or delineate the ambient air
boundary for the Cominco Red Dog mine facility.
44. The Public Control Access Plan in final draft PSD
permit Section 19 provides that public access to the mine site
ambient air boundary is limited by sign postings placed along
corridors of potential public access, specifically, at the main
entrance to the operation on the southern boundary along the
haul road, along Red Dog Creek, and at three sites around the
boundary where the terrain may possibly accommodate
public access.
45. On September 15, 1999, EPA notified ADEC by letter
that the final draft PSD permit was deficient and that issu-
ance of the permit as proposed in the September 3,1999, final
draft PSD permit would not comply with the Clean Air Act
or the Alaska SIP requirements relating to the construction or
modification of new sources or modification of existing
sources, if issued as drafted.
IV. FINDING OF NONCOMPLIANCE
46. Based on investigation and analysis of all relevant
facts and documentation provided by Cominco and ADEC,
pursuant to Section 113(a)(5) of the Clean Air Act, 42 U.S.C.
§ 7413(a)(5), EPA finds that:
a. The April 2, 1996, ADEC authorization of Cominco’s
construction and installation of new equipment, including the
new gyratory crusher, at the Red Dog mine facility prior to
Cominco’s receipt of a PSD permit allowing construction of
such equipment did not comply with the requirements or
prohibitions of the Clean Air Act and/or the Alaska SIP
relating to the construction or modification of new sources or
the modification of existing sources.
36a
b. Neither the preliminary draft PSD permit nor the final
draft PSD permit complies with the requirements or prohibi-
tions of the Clean Air Act or the Alaska SIP relating to the
construction or modification of new sources or the modifica-
tion of existing sources. Furthermore, issuance of a final
PSD permit as proposed in the preliminary draft PSD permit
or final draft PSD permit would not be in compliance with
requirements or prohibitions of the Clean Air Act and/or the
Alaska SIP relating to the construction or modification of
new sources or the modification of existing sources.
c. The construction or major modification of the Red
Dog mine facility without a valid PSD permit violates
Section 165(a) of the Act, 42 U.S.C. § 7475(a). Conse-
quently, the issuance of this Order, pursuant to Section 167
of the Act, 42 U.S.C. § 7477, is necessary to prevent any
further construction or modification at the Red Dog mine
facility.
V. ORDER
47. Based on investigation and analysis of all relevant
facts, including any good faith efforts to comply, and pursu-
ant to Section 167 of the Act, 42 U.S.C. § 7477, effective
immediately upon issuance:
a. ADEC is prohibited from issuing a PSD permit to
Cominco’s Red Dog mine facility allowing the construction
or modification of the facility and designating low NOx
controls (or less effective controls) as BACT for Wartsila
diesel generator MG-17, unless ADEC satisfactorily docu-
ments why SCR is not BACT for the Wartsila diesel genera-
tor at the Red Dog mine facility, or ADEC has demonstrated
that the PSD permit is in compliance with the prevention of
significant deterioration provisions of Part C of the Act, 42
U.S.C. §§ 7470-7492, and the Alaska SIP relating to the
construction or modification of new sources or the modifica-
tion of existing sources. In either case, ADEC must first
obtain EPA’s written concurrence on this determination.
b. Prior to issuance of a PSD permit to Cominco for
Wartsila diesel generators MG-1, MG-3, MG-4, or MG-5,
37a
ADEC is ordered to either include emission limits for MG-1,
MG-3, MG-4, and MG-S that reflect the previous “bubble”
limits and result in no increase in actual or allowable emis-
sions from these engines, include NOx emission limits based
on SCR, or satisfactorily document why SCR is not BACT
for the Wartsila diesel generators at tne Red Dog mine
facility and to obtain EPA’s written concurrence of this
determination.
c. In the event ADEC has already issued or released the
permit, ADEC is ordered to retract or render it ineffective
until such time as EPA provides written concurrence that the
permit is in compliance with the prevention of significant
deterioration provisions of Part C of the Act, 42 U.S.C.
§§ 7470-7492, and the Alaska SIP relating to the construc-
tion or modification of new sources or the modification of
existing sources.
48. Such documentation shall be submitted by certified
mail with return receipt requested to:
Douglas E. Hardesty
Office of Air Quality
U.S. Environmental Protection Agency
1200 Sixth Ave, OAQ-107
Seattle, WA 98101
Issued this 10 day of Dec , 1999.
/s/
Chuck Clarke
Regional Administrator
Region 10
38a
APPENDIX E
UNITED STATES
ENVIRONMENTAL PROTECTION AGENCY
In the Matter of: )
Cominco Alaska, Inc., ) Docket No. CAA-10-2000-0035
)
Proceeding under Sections ) ADMINISTRATIVE ORDER
113(a)(5) and 167 of the )
Clean Air Act. ) (42 U.S.C. §§ 7413(aXS)
) and 7477)
I. MINISTRATIV
1. This Administrative Order is issued by the Regional
Administrator, Region 10, United States Environmental
Protection Agency (EPA), to Cominco Alaska, Inc.,
(Cominco) pursuant to Sections 113(a(5) and 167 of the
Clean Air Act (CAA or Act), 42 U.S.C. §§ 7413(a)(5S) and
7477.
2. The authority of the Administrator of EPA to issue
orders pursuant to Sections 113(a)(5) and 167 of the Act, 42
U.S.C. §§ 7413(a)(5) and 7477, has been delegated to the
Regional Administrator. The Regional Administrator con-
sulted with the Assistant Administrator for the Office of
Enforcement and Compliance Assurance or his designee
pursuant to the delegation of authority from the Administra-
tor prior to issuing this Administrative Order.
Il. STATUTORY AND REGULATORY AUTHORITY
3. The Administrator of EPA, pursuant to Section 109 of
the Act, 42 U.S.C. § 7409, National Primary
and Secondary Ambient Air Quality S (NAAQS) for
certain criteria pollutants, including nitrogen dioxide (NO2).
40 C.F.R. §§ 50.4 to 50.12.
39a
4. Pursuant to Section 107(d) of the Act, 42 U.S.C. §
7407(d), the Administrator promulgates lists of attainment
Status designations for each air quality control region
(AQCR) in every State. These lists contain the attainment
status of each AQCR for each of the criteria pollutants. The
attainment status designations for the Alaska AQCRs appear
at 40 C.F.R. § 81.302.
5. Cominco Alaska, Inc. (Cominco) owns and operates
the Red Dog mine facility, a surface zinc and lead ore mining
operation, which is located in the Northern Alaska Interstate
AQCR which has been designated as in attainment or unclas-
sifiable with respect to the NAAQS. 40 C.F.R. § 81.302.
6. Part C of the Act, 42 U.S.C. §§ 7470-7492, requires
the Administrator to promulgate regulations for prevention of
significant deterioration (PSD) of air quality in areas desig-
nated in accordance with Section 107(d) of the Act, 42
U.S.C. § 7407(d), as in attainment or unclassifiable.
7. Pursuant to Sections 110 and 165(e)(3) of the Act, 42
U.S.C. §§ 7410 and 7471(e)(3), EPA promulgated two sets of
largely identical regulations for preventing the significant
ion of air quality in areas where the existing air
quality is better than the ambient standards. In States without
a PSD program and in those States where EPA has delegated
authority to administer the federal PSD program to the State,
the federal PSD regulations at 40 C.F.R. § 51.21 have been
incorporated into the various State Implementation Plans
(SIPs) of such States. In the remaining States, EPA has
approved, as part of the SIP, a State PSD program as meeting
the requirements of Part C of the Act and the PSD regula-
tions at 40 C.F.R. § 51.166.
8. EPA has approved 18 AAC 50.020, 50.021, 50.300,
50.400, 50.510, 50.520, 50.530, 50.600, 50.620, and 50.900,
as in effect on June 2, 1988, as a revision to the Alaska SIP
and as meeting the requirements of Part C of the Act and the
PSD regulations at 40 C.F.R. § 51.166 for preventing the
significant deterioration of air quality. See 40 C.F.R. §
52.96(a). (48 Fed. Reg. 30626, July 5, 1983, and subsequent
amendments.) References in this document to Alaska
40a
statutory or regulatory provisions are to the current SIP-
approved versions of the statute or regulation.
9. Section 165 of the Act, 42 U.S.C. § 7475, prohibits the
construction of a major emitting facility in any area subject to
the requirements of Part C of the Act and the PSD regula-
tions unless, among other things, a permit has been issued for
the proposed facility in accordance with Part C of the Act
which sets forth emission limitations that conform to the
requirements of Part C, and the facility is subject to
best available control techno (BACT) for each pollutant
subject to lation under Title I of the Act that is emitted
from or which results from such facility.
10. “Actual emissions” as defined in 18 AAC
$0.900(1)( 1991) means “for each air contaminant, the average
rate in tons per year that a facility actually emitted during the
most recent two years of operation; the department
will, in its discretion, consider facility-specific allowable
emissions to be actual emissions of an air contaminant.”
11. “Construct” as defined in 18 AAC 50.900(13\(1991)
means “to make a change or a series of changes in operation
or any physical changes or additions to a source which
increase the actual emissions of an air pollutant.”
12. “Allowable emissions” as defined in 18 AAC
50.900(4)(1991) means “the calculated emission rate of a
source or facility using the maximum rated capacity and
enforceable limitations and conditions on emissions and
operations.”
13. “Modify” as defined in 18 AAC 50.900(28\1991)
means “to make a change or a series of changes in operation
14. “Best available control technology” is defined in 18
AAC 5$0.900(9\ 1991) as an emission limitation which
represents the maximum reduction achievable for each
regulated air pollutant taking into account energy, environ-
mental, and economic impact, and other costs.
4la
15. 18 AAC 50.300(a1991) states that no person may
construct, modify, reconstruct, operate, or cause the opera-
tion of a facility meeting the criteria in that subsection
without a permit from the State of Alaska Department of
Environmental Conservation (ADEC). The list of facilities
covered by 18 AAC 50.300(a) includes a facility which has
allowable emissions of more than 250 tons year of a
segulated sir contaminant and which is modified after Av-
gust 7, 1980, or after the date of the most recent permit
issued to the facility under 18 AAC 50.400(c)(3), causing an
increase in actual emissions equal to or exceeding any of the
thresholds identified in that subsection. —
16. A permit application for a facility subject to 18 AAC
50.300(a)(S) or (6) must include, among other things, a
detailed demonstration that the expected maximum emissions
from the facility will not cause or contribute to a violation of
ee ee 18 AAC
_ 17. 18 AAC 50.400(cK3A)(1991) states that ADEC will
issue a permit only if the applicant shows that, for a facility
subject to 18 AAC 50.300(a)(S) or (6), BACT for controlling
emissions of each regulated pollutant will be installed for
each new or modified source.
18. Section 113(aX5) of the Act, 42 U.S.C. § 7
a t, § 7413(aX(5)
Whenever, on the basis of any available information, the
Administrator finds that a State is not acting in compli-
ance with any requirement or prohibition of the [Act] re-
lating to the construction of new sources or the modi
tion of existing sources, the Administrator may—
Lo eng pater aapene- phen mypencenyd
oe on
fication < y major stationary source in any area to
(B) issue an administrative penalty order i ordanc
with subsection (d) of this section; or — '
42a
(C) bring a civil action under subsection (b) of this sec-
tion. -
Nothing in this subsection shall preclude the United
States from commencing a criminal action under subsec-
tion (c) of this section at any time for any such violation.
19. Section 167 of the Act, 42 U.S.C. § 7477, provides
that the Administrator shall take such measures, including
issuance of an order, as necessary to prevent the construction
or modification of a major emitting facility which does not
conform to the requirements of Part C of the Act.
20. Section 169(1) of the Act, 42 U.S.C. § 7479(1), de-
fines a major emitting facility, in pertinent part, as a station-
ary source which emits or has the potential to emit 250 tons
per year or more of any air pollutant.
21. A State does not conform to the requirements of Part C
of the Act if, among other things, it allows a major emitting
facility to commence construction or modification prior to
receipt of a PSD permit or issues a PSD permit to a fz -ility
without subjecting the facility to BACT for each poll. iant
subject to regulation under Title I of the Act that is emitted
from or which results from such facility.
22. A major emitting facility does no~ conform-to the
requirements of Part C if, among other things, it commences
construction or modification prior to receipt of a PSD permit
that subjects the facility to BACT for each pollutant subject
to regulation under Title I of the Act that is emitted from or
which results from such facility.
Ill. FINDINGS OF FACT
23. On June 17, 1988, ADEC issued a PSD permit, Permit
No. 8732-AA001, that authorized the construction of the Red
Dog mine facility, including the installation of five Wartsila
diesel generators (MG-1, MG-2, MG-3, MG-4, and MG-S5).
24. ADEC revised and replaced the June 1988 PSD permit
on several occasions, including a revision dated July 27,
1994, Permit No. 9332-AA003, which: (a) removed from the
43a
permit a NOx BACT limit of 750 parts per million volume
dried (ppmvd) that applied to the five Wartsila diesel genera-
tors, and substituted a limit of 109,660,000 kilowatt hours
per continuous 365-day period (kW-hr/yr) for MG-1, MG-3,
MG-4, and MG-S, (b) removed the stand-by limits on MG-2
and permitted it to operate full-time, and (c) authorized the
installation and full-time operation of a sixth Wartsila diesel
generator (MG-6).
25. On March 27, 1996, prior to receiving an amended
PSD permit, Cominco requested that ADEC allow Cominco
to make on-site preparations for changes to the facility that
would allow for production increases. On April 2, 1996,
ADEC granted Cominco a waiver to allow the company to
conduct specified procurement and construction activities on
the condition that Cominco prepare and submit a request for
a permit amendment concurrent with the activities.
26. Between April 1996 and May 1998, Cominco con-
structed a new gyratory crusher at the Red Dog mine facility
without authorization under a valid PSD permit.
27. On June 29, 1998, Cominco submitted a PSD permit
application to ADEC for what it referred to as a “production
rate increase project” that was expected to increase the
mine’s ore processing rate from approximately 2,200,000
tons per year to 3,500,000 tons per year and to increase the
ion of zinc and lead concentrate from 854,000 tons
per year to 1,400,000 tons per year. Cominco submitted a
supplement to the application to ADEC on April 6, 1999. As
part of the production rate increase project, Cominco re-
quested that ADEC, among other things, remove the air
quality operating restrictions on the four Wartsila diesel
generators that were installed in 1988 and which still had
operational limits on them (MG-1, MG-3, MG-4, MG-5),
“add” a seventh Wartsila diesel generator (MG-17), “add”
the new gyratory crusher that Cominco had already installed,
and approve the addition of other equipment and changes
necessary to support the production rate increase project.
28. On May 4, 1999, ADEC issued a preliminary PSD
permit (preliminary draft PSD permit) for the production rate
44a
increase project for review and public comment. The pre-
liminary draft PSD permit proposed to remove the opera-
tional cap of 109,660,000 kW-hr/year that applied to Wartsila
diesel generators MG-1, MG-3, MG-4, MG-5, to “add”
the seventh Wartsila diesel generator (MG-17), to “add” the
new gyrator crusher, and to approve the addition of other
equipment and changes that Cominco requested in its PSD
permit application for the production rate increase project.
29. ADEC prepared a preliminary technical analysis report
(Preliminary Technical — to accompany the prelimi-
nary draft PSD permit. Preliminary Technical Report
stated that the production rate increase project is expected to
increase actual NOx emissions by up to 1,100 tons per year;
carbon monoxide (CO) emissions by 90 tons per year;
particulate matter (PM) emissions by 35 tons per year; PM
emissions less than 10 micrometers in diameter (PM-10) by
35 tons per year; volatile organic compound (VOC) emis-
sions by 59 tons per year; and lead (Pb) emissions by 0.046
tons per year. The proposed production rate increase project
is expected to reduce sulfur dioxide (SO2) emissions by 37
tons per year.
30. In the preliminary draft PSD permit and Preliminary
Technical Report, ADEC concluded that of the seven Wart-
sila diesel generators, only MG-5 and MG-17 were subject to
PSD requirements and therefore required BACT. EPA
regulations require that technical and economic feasibility be
considered when determining BACT. In the Preliminary
Technical Report ADEC determined that Selective Catalytic
Reduction (SCR) is a technically and economically feasible
emission control technology for the Wartsila generators and
that SCR could result in Seductions of 712 tens per your of
NOx for each Wartsila diesel generator. The Preliminary
Technical also concluded that installation of low NOx
controls w result in reductions of only 273 tons per year
of NOx for each Wartsila diesel generator. The Preliminary
Technical Report then concluded that BACT for MG-5 and
MG-17 was an emission limit based on low NOx controls.
45a
_31. The Red Dog mine facility was at the time of construc-
tion and continues to be a “major emitting facility” under
Section 169(1) of the Act, 42 U.S.C. § 7479(1).
_32. The Red Dog mine facility was at the time of construc-
tion and continues to be a facility with allowable emissions,
as defined in 18 AAC 50.900(4), of at least 250 tons per year
of a regulated air contaminant. The Red Dog mine facility is
therefore a “facility,” as that term is defined in 18 AAC
50.300(a)(6).
33. The production rate increase project will “modify,” as
that term is defined in 18 AAC 50.900(28), the Red Dog
mine facility.
34. The production rate increase project will increase
actual emissions of NOx, PM, PM-10, and VOC from the
Red Dog mine facility by more than the thresholds identified
in 18 AAC 50.300(a)(6)(C) and will occur after 1980 and
after the date of the most recent valid permit issued for the
Red Dog mine under 18 AAC 50.400(c)(3). Therefore the
Red Dog mine facility is a “facility,” as listed in 18 AAC
50.300(a)(6)(C).
35. The public comment period on the preliminary draft
Soe Ee one preennanen cane RD gD ene Om
une 2,
36. On June 2, 1999, the United States Department of the
Interior, National Park Service (NPS), submitted comments
on the prelimi draft PSD permit for the production rate
with the preliminary draft PSD permit, including the follow-
ing:
a. ADEC failed to subject four of the Wartsila diesel
(MG-1 and MG-3 through MG-5) to PSD, includ-
ing BACT. These generators are part of the production rate
increase project because the preliminary draft PSD permit
would remove an operating restriction on these generators.
b. ADEC failed to require SCR on the two Wartsila die-
sel generators which ADEC acknowledged are subject to
46a
BACT (MG-5 and MG-17). SCR is BACT for the Wartsila
diesel generators.
37. By letter dated July 29, 1999, EPA informed ADEC
that it agreed with NPS’s comments and had concluded that:
a. The Wartsila diesel generators MG-1 and MG-3
through MG-S are subject to PSD, including BACT, because
these generators are part of the production rate increase
project since the preliminary draft PSD permit would remove
the existing operating restriction on these generators.
b. Based on ADEC’s preliminary Technical Report that
accompanied the preliminary draft PSD permit, SCR is
BACT for the Wartsila diesel generators MG-1, MG-3, MG-
4, MG-S, and MG-17.
38. On September 3, 1999, ADEC provided to EPA a final
draft permit No. 9932-AC005 for the Cominco Red Dog
mine facility. The final draft permit was accompanied by a
Final Technical Analysis Report (Final Technical Report)
and Response to Comment document.
39. The Final Technical Report concluded that an emis-
sion rate achievable with low NOx controls to be BACT on
Wartsila diesel generators MG-5 and MG-17. The final draft
PSD permit included an emission rate limit of 121.3 Ib/hour
on MG-5 and MG-17 based on low NOx controls.
40. The final draft PSD permit did not require the installa-
tion of BACT on MG-1, MG-3, and MG-4, but instead only
proposed to reinstate the same limit on total annual emissions
from MG-1, MG-3, and MG-4 which previously applied to
total annual emissions from MG-1! through MG-5. This limit
was listed in the final draft PSD permit as:
(1) 2259 tons NOx/year from MG-1, MG-3, and MG-
4; and
(2) 750 ppm NOx corrected to 7% oxygen from each
unit.
41. On September 15, 1999, EPA notified ADEC by letter
that the final draft PSD permit was deficient and that issu-
Sen
47a
ance of the permit as proposed in the September 3, 1999,
final draft PSD permit would not comply with the Clean Air
Act or the Alaska SIP requirements relating to the construc-
tion or modification of new sources or modification of
existing sources, if issued as drafted. Additional letters were
sent to ADEC on September 28, 1999, and November 10,
1999, further explaining EPA’s concerns with the final draft
permit.
42. On December 10, 1999, pursuant to the authority of
Sections 113(a)(5) and 167 of the Act, 42 US.C. §§
7413(a)(5) and 7477, EPA issued a Finding of Noncompli-
ance and Order, Docket No. CAA-10-99-0263, to ADEC
(ADEC 113/167 Order). On the same day, the ADEC
113/167 Order was sent by fax and overnight certified mail
return receipt requested to Michele Brown, ADEC Commis-
sioner, and faxed to Tom Chapple, ADEC, Director, Division
of Air and Water Quality. A copy of the ADEC 113/167
Order was faxed to Doug Horswill, Vice President for
Environmental and Corporate Affairs, Cominco, and sent
overnight certified mail return receipt requested to John
Keys, General Manager, Cominco.
43. The ADEC 113/167 Order provides at paragraph 46a
that:
The Apnl 2, 1996, ADEC authorization of Cominco’s
construction and installation of new equipment, including
the new gyratory crusher, at the Red Dog mine facility
prior to Cominco’s receipt of a PSD permit allowing con-
struction of such equipment did not comply with the re-
quirements or prohibitions of the Clean Air Act and/or
the Alaska SIP relating to the construction or modifica-
tion of new sources or the modification of existing
sources.
44. The ADEC 113/167 Order provides, in part, at para-
graph 47 that “effective immediately upon issuance:
a. ADEC is prohibited from issuing a PSD permit to
Cominco’s Red Dog mine facility allowing the construction
or modification of the facility and designating low NOx
48a
controls (or less effective controls) as BACT for Wartsila
diesel generator MG-17, unless ADEC satisfactorily docu-
ments why SCR is not BACT for the Wartsila diesel genera-
tor at the Red Dog mine facility, or ADEC has demonstrated
that the PSD permit is in compliance with the prevention of
significant deterioration provisions of Part C of the Act, 42
U.S.C. §§ 7470-7492, and the Alaska SIP relating to the
construction or modification of new sources or the modifica-
tion of existing sources. In either case, ADEC must first
obtain EPA’s written concurrence on this determination.
c. In the event ADEC has already issued or released the
permit, ADEC is ordered to retract or render it ineffective
until such time as EPA provides written concurrence that the
permit is in compliance with the prevention of significant
deterioration provisions of Part C of the Act, 42 U.S.C. §§
7470-7492, and the Alaska SIP relating to the construction or
modification of new sources or the modification of existing
sources.
45. Shortly after receiving the ADEC 113/167 Order,
ADEC issued Air Quality Construction Permit No. 9932-
AC005 for the Cominco Red Dog Mine on December 10,
1999 (final permit). The final permit was accompanied by a
Final Technical Analysis Report dated December 10, 1999
(12/10/99 Technical Report).
46. The 12/10/99 Technical Report states at page 49 that
“The Department [ADEC] finds an emission limit achievable
with low NOx controls to be BACT on diesel generator MG-
17. A vendor-guaranteed emission rate of 121.3 Ib/hour is
representative of the NOx reduction expected of the Low
NOx controls selected as BACT.”
47. Section 4, Best Available Control Technology (BACT)
for Oxides of Nitrogen (NOx), Condition 20.1 of the final
permit requires Wartsila diesel generator MG-17 to limit
NOx emissions to no greater than 121.3 Ib/hour averaged
over any three hours.
49a
48. On February 8, 2000, EPA notified ADEC pursuant to
Section 113(a)(S) of the Act, 42 U.S.C. § 7413(a)(5) that
Permit No. 9932-AC005, issued to Cominco on December
10, 1999, fails to comply with Pact C of the Act, 42 U.S.C. §
7470-7492, the implementing regulations and Alaska SIP,
and that the State is not in compliance with Part C of the Act.
49. The issuance of this Order, pursuant to Sections
113(ay(5) and 167 of the Act, 42 U.S.C. §§ 7413(a)(5) and
7477, is necessary to prevent any further construction or
modification at the Red Dog mine facility.
V. ORDER
50. Based on investigation and analysis of relevant facts,
and pursuant to Sections 113(a)(5) and 167 of the Act, 42
U.S.C. §§ 7413(a)(5) and 7477:
a. Cominco is prohibited from commencing any and all
construction or modification activities at the Red Dog mine
facility associated with the Wartsila diesel generator MG-17
until Cominco has demonstrated to EPA’s satisfaction
compliance with Part C of the Act and 40 C.F.R. Part 51, and
obtains a valid PSD permit from ADEC for the Wartsila
generator MG-17 that complies with the Act and with the
December 10, 1999 Finding and Order.
__ b. Cominco is specifically allowed to continue construc-
tion or operation of other portions of the Red Dog mine
facility as authorized by ADEC Permit No. 9932-AC005.
c. Cominco shall submit, no later than five (5) days after
the effective date of this Order, certification that Cominco
has complied with the prohibition in the paragraph 50a above
and will continue to comply with paragraph 50a of this Order
will Cominco demonstrates to EPA’s satisfaction compliance
with Part C of the Act and 40 C.F.R. Part 51, Subpart I and
the Alaska SIP. Such certification shall be submitted by
certified mail with return receipt requested to:
50a
Douglas E. Hardesty
Office of Air Quality
U.S. Environmental Protection Agency
1200 Sixth Ave, OAQ-107
Seattle, WA 98101
50. Cominco has the opportunity to confer with EPA
concerning this Order. Any request for a conference should
be made to Mr. Hardesty, Chief, Federal and Delegated Aur
Programs Unit, within 10 days of issuance of this Order. He
may be reached at (206) 553-6641. Such a conference shall
occur no later than March 16, 2000.
Issued this 8th day of Feb. , 2000.
/s/
Chuck Findley ae
Deputy Regional Administrator
Sla
APPENDIX F
UNITED STATES
ENVIRONMENTAL PROTECTION AGENCY
In the Matter of: ) AMENDED
Cominco Alaska, Inc., ) ADMINISTRATIVE ORDER
)
Proceeding under Sections ) Docket No. CAA-10-2000-0035
113(aX(5) and 167 ofthe )
Clean Air Act. ) (42 U.S.C. §§ 7413(a)(5)
) and 7477)
I. AMENDED ADMINISTRATIVE ORDER
1. This Amended Administrative Order is issued by the
Regional Administrator, Region 10, United States Environ-
mental Protection Agency (EPA), to Cominco Alaska, Inc.,
(Cominco) pursuant to Sections 113(a)(5) and 167 of the
Clean Air Act (CAA or Act), 42 U.S.C. §§ 7413(a)(5) and
7477.
2. The authority of the Administrator of EPA to issue
orders pursuant to Sections 113(a)(5) and 167 of the Act, 42
U.S.C. §§ 7413(a)(5) and 7477, has been delegated to the
Regional Administrator. The Regional Administrator con-
sulted with the Assistant Administrator for the Office of
Enforcement and Compliance Assurance or his designee
pursuant to the delegation of authority from the Administra-
tor prior to issuing this Amended Administrative Order.
Il. STATUTORY AND REGULATORY AUTHORITY
3. The Administrator of EPA, pursuant to Section 109 of
the Act, 42 U.S.C. § 7409, promulgated National Primary
and Secondary Ambient Air Quality Standards (NAAQS) for
certain criteria pollutants, including nitrogen dioxide (NO2).
40 C.F.R. §§ 50.4 to 50.12.
52a
4. Pursuant to Section 107(d) of the Act, 42 U.S.C. §
7407(d), the Administrator promulgates lists of attainment
status designations for each quality control region (AQCR) in
every State. These lists contain the attainment status of each
AQCR for each of the criteria pollutants. The attainment
status designations for the Alaska AQCRs appear at 40
C.F.R. § 81.302.
5. Cominco Alaska, Inc. (Cominco) owns and operates
the Red Dog mine facility, a surface zinc and lead ore mining
operation, which is located in the Northern Alaska Interstate
AQCR which has been designated as in attainment or unclas-
sifiable with respect to the NAAQS. 40 C.F.R § 81.302.
6. Part C of the Act, 42 U.S.C. §§ 7470-7492, requires
the Administrator to promulgate regulations for prevention of
significant deterioration (PSD) of air quality in areas desig-
nated in accordance with Section 107(d) of the Act, 42
U.S.C. § 7407(d), as in attainment or unclassifiable.
7. Pursuant to Sections 110 and 165(e)(3) of the Act, 42
U.S.C. §§ 7410 and 7471(e)(3), EPA promulgated two sets of
largely identical regulations for preventing the significant
deterioration of air quality in areas where the existing air
quality is better than the ambient standards. In States without
a PSD program and in those States where EPA has delegated
authority to administer the federal PSD program to the State,
the federal PSD regulations at 40 C.F.R. § 51.21 have been
incorporated into the various State Implementation Plans
(SIPs) of such States. In the remaining States, EPA has
approved, as part of the SIP, a State PSD program as meeting
the requirements of Part C of the Act and the PSD regula-
tions at 40 C.F.R. § 51.166.
8. EPA has approved 18 AAC 50.020, 50.021, 50.300,
50.400, 50.510, 50.520, 50.530, 50.600, 50.620, and 50.900,
as in effect on June 2, 1988, as a revision to the Alaska SIP
and as meeting the requirements of Part C of the Act and the
PSD regulations at 40 C.F.R. § 51.166 for preventing the
significant deterioration of air quality. See 40 C.F.R §
52.96(a). (48 Fed. Reg. 30626, July 5, 1983, and subsequent
amendments.) References in this document to Alaska
53a
Statutory or regulatory provisions are to the current SIP-
approved versions of the statute or regulation.
9. Section 165 of the Act, 42 U.S.C. § 7475, prohibits the
construction of a major emitting facility in any area subject to
the requirements of Part C of the Act and the PSD regula-
tions unless, among other things, a permit has been issued for
the proposed facility in accordance with Part C of the Act
which sets forth emission limitations that conform to the
requirements of Part C, and the proposed facility is subject to
best available control technology (BACT) for each pollutant
subject to regulation under Title I of the Act that is emitted
from or which results from such facility.
10. “Actual emissions” as defined in 18 AAC
50.900(1)(1991) means “for each air contaminant, the
average rate in tons per year that a facility actually emitted
during the most recent two years of normal operation; the
department will, in its discretion, consider facility-specific
allowable emissions to be actual emissions of an air contami-
nant.”
11. “Construct” as defined in 18 AAC 50.900(13)(1991)
means “to make a change or a series of changes in operation
or any physical changes or additions to a source which
increase the actual emissions of an air pollutant.”
12. “Allowable emissions” as defined in 18 AAC
50.900(4)(1991) means “the calculated emission rate of a
source or facility using the maximum rated capacity and
enforceable limitations and conditions on emissions and
operations.”
13. “Modify” as defined in 18 AAC 50.900(28)(1991)
means “to make a change or a series of changes in operation
or any physical changes or additions to a source which
increase the actual emissions of an air pollutant.”
14. “Best available control technology” is defined in 18
AAC 50.900(9\1991) as an emission limitation which
the maximum reduction achievable for each
regulated air pollutant taking into account energy, environ-
mental, and economic impacts, and other costs.
54a
15. 18 AAC 50.300(a)(1991) states that no person may
construct, modify, reconstruct, operate, or cause the opera-
tion of a facility meeting the criteria in that subsection
without a permit from the State of Alaska, Department of
Environmental Conservation (ADEC). The list of facilities
covered by 18 AAC 50.300(a) includes a facility which has
allowable emissions of more than 250 tons per year of a
regulated air contaminant and which is modified after August
7, 1980, or after the date of the most recent permit issued to
the facility under 18 AAC 50.400(c)(3), causing an increase
in actual emissions equal to or exceeding any of the thresh-
olds identified in that subsection.
16. A permit application for a facility subject to 18 AAC
50.300(a)(5) or (6) must include, among other things, a
detailed demonstration that the expected maximum emissions
from the facility will not cause or contribute to a violation of
an ambient air standard or allowable increment in 18 AAC
50.020(b).
17. 18 AAC 50.400(c\(3A)(1991) states that ADEC will
issue a permit only if the applicant shows that, for a facility
subject to 18 AAC 50.300(a)(5) or (6), BACT for controlling
emissions of each regulated pollutant will be installed for
each new or modified source.
18. Section 113(a)(5) of the Act, 42 U.S.C. § 7413(a)(5)
provides:
Whenever, on the basis of any available information, the
Administrator finds that a State is not acting in compli-
ance with any requirement or prohibition of the [Act] re-
lating to the construction of new sources or the modifica-
tion of existing sources, the Administrator may—
(A) issue an order prohibiting the construction or
modification of any major stationary source in any area to
which such requirement applies;
(B) issue an administrative penalty order in accor-
dance with subsection (d) of this section; or
55a
(C) bring a civil action under subsection (b) of this
section.
Nothing in this subsection shall preclude the United
States commencing a criminal action under subsec-
tion (c) of this section at any time for any such violation.
19. Section 167 of the Act, 42 U.S.C. § 7477, provides
that the Administrator shall take such measures, including
issuance of an order, as necessary to prevent the construction
or modification of a major emitting facility which does not
conform to the requirements of Part C of the Act.
20. Section 169(1) of the Act, 42 U.S.C. § 7479(1), de-
fines a major emitting facility, in pertinent part, as a station-
ary source which emits or has the potential to emit 250 tons
per year or more of any air pollutant.
21. A State does not conform to the requirements of Part C
of the Act if, among other things, it allows a major emitting
facility to commence construction or modification prior to
receipt of a PSD permit or issues a PSD permit to a facility
without subjecting the facility to BACT for each pollutant
subject to ation under Title I of the Act that is emitted
from or which results from such facility.
22. A major emitting facility does not conform to the
requirements of Part C if, among other things, it commences
construction or modification prior to receipt of a PSD permit
that subjects the facility to BACT for each pollutant subject
to ation under Title I of the Act that is emitted from or
which results from such facility.
Ill. FINDINGS OF FACT
23. On June 17, 1988, ADEC issued a PSD permit, Permit
No. 8732-AA001, that authorized the construction of the Red
Dog mine facility, including the installation of five Wartsila
diesel generators (MG-1, MG-2, MG-3, MG-4, and MG-5).
24. ADEC revised and replaced the June 1988 PSD permit
on several occasions, including a revision dated July 27,
1994, Permit No. 9332-AA003, which: (a) removed from the
56a
permit a NOx BACT limit of 750 parts per million volume
dried (ppmvd) that applied to the five Wartsila diesel genera-
tors, and substituted a limit of 109,660,000 kilowatt hours
per continuous 365-day period (kW-hr/yr) for MG-1, MG-3,
MG-4, and MG-S5, (b) removed the stand-by limits on MG-2
and permitted it to operate full-time, and (c) authorized the
installation and full-time operation of a sixth Wartsila diesel
generator (MG-6).
25. On March 27, 1996, prior to receiving an amended
PSD permit, Cominco requested that ADEC allow Cominco
to make on-site preparations for changes to the facility that
would allow for production increases. On April 2, 1996,
ADEC granted Cominco a waiver to allow the company to
conduct specified procurement and construction activities on
the condition that Cominco prepare and submit a request for
a permit amendment concurrent with the activities.
26. Between April 1996 and May 1998, Cominco con-
structed a new gyratory crusher at the Red Dog mine facility
without authorization under a valid PSD permit.
27. On June 29, 1998, Cominco submitted a PSD permit
application to ADEC for what it referred to as a “production
rate increase project” that was expected to increase the
mine’s ore processing rate from approximately 2,200,000
tons per year to 3,500,000 tons per year and to increase the
production of zinc and lead concentrate from 854,000 tons
per year to 1,400,000 tons per year. Cominco submitted a
supplement to the application to ADEC on April 6, 1999. As
part of the production rate increase project, Cominco re-
quested that ADEC, among other things, remove the air
quality operating restrictions on the four Wartsila diesel
generators that were installed in 1988 and which still had
operational limits on them (MG-1, MG-3, MG-4, MG-5),
“add” a seventh Wartsila diesel generator (MG-17), “add”
the new gyratory crusher that Cominco had already installed,
and approve the addition of other equipment and changes
necessary to support the production rate increase project.
28. On May 4, 1999, ADEC issued a preliminary PSD
permit (preliminary draft PSD permit) for the production raie
S7a
increase project for review and public comment. The pre-
liminary draft PSD permit proposed to remove the opera-
tional cap of 109,660,000 kW-hr/year that applied to Wartsila
diesel generators MG-1, MG-3, MG-4, MG-S5, to “add”
the seventh Wartsila diesel generator (MG-17), to “add” the
new gyrator crusher, and to approve the addition of other
equipment and changes that Cominco requested in its PSD
permit application for the production rate increase project.
29. ADEC prepared a preliminary technical analysis report
(Preliminary Technical Report) to accompany the prelimi-
nary draft PSD permit. The Preliminary Technical Report
stated that the production rate increase project is expected to
increase actual NOx emissions by up to 1,100 tons per year;
carbon monoxide (CO) emissions by 90 tons per year;
particulate matter (PM) emissions by 35 tons per year; PM
emissions less than 10 micrometers in diameter (PM-10) by
35 tons per year; volatile organic compound (VOC) emis-
sions by 59 tons per year; and lead (Pb) emissions by 0.046
tons per year. The proposed production rate increase project
is expected to reduce sulfur dioxide (SO2) emissions by 37
tons per year.
30. In the preliminary draft PSD permit and Preliminary
Technical Report, ADEC concluded that, of the seven
Wartsila diesel generators, only MG-5 and MG-17 were
subject to PSD requirements and therefore required BACT.
EPA regulations require that technical and economic feasibil-
ity be considered when determining BACT. In the Prelimi-
nary Technical Report ADEC determined that Selective
Catalytic Reduction (SCR) is a technically and economically
feasible emission control technology for the Wartsila genera-
tors and that SCR could result in reductions of 712 tons per
year of NOx for each Wartsila diesel generator. The Pre-
liminary Technical Report also concluded that installation of
low NOx controls would result in reductions of only 273 tons
per year of NOx for each Wartsila diesel generator. The
Preliminary Technical Report then concluded that BACT for
MG-5 = MG-17 was an emission limit based on low NOx
controls.
58a
31. The Red Dog mine facility was at the time of construc-
tion and continues to be a “major emitting facility” under
Section 169(1) of the Act, 42 U.S.C. § 7479(1).
32. The Red Dog mine facility was at the time of construc-
tion and continues to be a facility with allowable emissions,
as defined in 18 AAC 50.900(4), of at least 250 tons per year
of a regulated air contaminant. The Red Dog mine facility is
therefore a “facility,” as that term is defined in 18 AAC
50.300(a)(6).
33. The production rate increase project will “modify,” as
that term is defined in 18 AAC 50.900(28), the Red Dog
mine facility.
34. The production rate increase project will increase
actual emissions of NOx, PM, PM-10, and VOC from the
Red Dog mine facility by more than the thresholds identified
in 18 AAC 50.300(a)(6)(C) and will occur after 1980 and
after the date of the most recent valid permit issued for the
Red Dog mine under 18 AAC 50.400(c)(3). Therefore the
Red Dog mine facility is a “facility,” as listed in 18 AAC
50.300(a)(6)(C).
35. The public comment period on the preliminary draft
PSD permit for the production rate increase project ended on
June 2, 1999.
36. On June 2, 1999, the United States Department of the
Interior, National Park Service (NPS), submitted comments
on the preliminary draft PSD permit for the production rate
increase project. The NPS comments raised several concerns
with the preliminary draft PSD permit, including the follow-
ing:
a. ADEC failed to subject four of the Wartsila diesel
(MG-1 and MG-3 through MG-5) to PSD, includ-
ing BACT. These generators are part of the production rate
increase project because the preliminary draft PSD permit
would remove an operating restriction on these generators.
b. ADEC failed to require SCR on the two Wartsila die-
sel generators which ADEC acknowledged are subject to
59a
BACT (MG-S5 and MG-17). SCR is BACT for the Wartsila
diesel generators.
37. By letter dated July 29, 1999, EPA informed ADEC
that it agreed with NPS’s comments and had concluded that:
a. The Wartsila diese! generators MG-1 and MG-3
through MG-S are subject to PSD, including BACT, because
these generators are part of the production rate increase
project since the preliminary draft PSD permit would remove
the existing operating restriction on these generators.
b. Based on ADEC’s preliminary Technical Report that
accompanied the preliminary draft PSD permit, SCR is
BACT for the Wartsila diesel generators MG-1, MG-3, MG-
4, MG-S, and MG-17.
38. On September 3, 1999, ADEC provided to EPA a final
draft permit No. 9932-AC005 for the Cominco Red Dog
mine facility. The final draft permit was accompanied by a
Final Technical Analysis Report (Final Technical Report)
and Response to Comment document.
39. The Final Technical Report concluded that an emis-
sion rate achievable with low NOx controls to be BACT on
Wartsila diesel rs MG-5 and MG-17. The final draft
PSD permit included an emission rate limit of 121.3 lb/hour
on MG-5 and MG-17 based on low NOx controls.
40. The final draft PSD permit did not require the installa-
tion of BACT on MG-1, MG-3, and MG-4, but instead only
proposed to reinstate the same limit on total annual emissions
from MG-1, MG-3, and MG-4 which previously applied to
total annual emissions from MG-1 through MG-S. This limit
was listed in the final draft PSD permit as:
(1) 2259 tons NOx/year from MG-1, MG-3, and MG-
4; and
(2) 750 ppm NOx corrected to 7% oxygen from each
unit.
41. On September 15, 1999, EPA notified ADEC by letier
that the final draft PSD permit was deficient and that issu-
60a
ance of the permit as proposed in the September 3, 1999,
final draft PSD permit would not comply with the Clean Air
‘Act or the Alaska SIP requirements relating to the construc-
tion or modification of new sources or modification of
existing sources, if issued as drafted. Additional letters were
sent to ADEC on September 28, 1999, and November 10,
1999, further explaining EPA’s concerns with the final draft
permit.
42. On December 10, 1999, pursuant to the authority of
Sections 113(a)(5) and 167 of the Act, 42 U.S.C. §§
7413(a)(S) and 7477, EPA issued a Finding of Noncompli-
ance and Order, Docket No. CAA-10-99-0263, to ADEC
(ADEC 113/167 Order). On the same day, the ADEC
113/167 Order was sent by fax and overnight certified mail
return receipt requested to Michele Brown, ADEC Commis-
sioner, and faxed to Tom Chapple, ADEC, Director, Division
of Air and Water Quality. A copy of the ADEC 113/167
Order was faxed to Doug Horswill, Vice President for
Environmental and Corporate Affairs, Cominco, and sent
overnight certified mail return receipt requested to John
Keys, General Manager, Cominco.
43. The ADEC 113/167 Order provides at paragraph 46a
that:
The April 2, 1996, ADEC authorization of Cominco’s
construction and installation of new equipment, including
the new gyratory crusher, at the Red Dog mine facility
prior to Cominco’s receipt of a PSD permit allowing con-
struction of such equipment did not comply with the re-
quirements or prohibitions of the Clean Air Act and/or
the Alaska SIP relating to the construction or modifica-
tion of new sources or the modification of existing
sources.
44. The ADEC 113/167 Order provides, in part, at para-
graph 47 that “effective immediately upon issuance:
a. ADEC is prohibited from issuing a PSD permit to
Cominco’s Red Dog mine facility allowing the construction
or modification of the facility and designating low NOx
6la
controls (or less effective controls) as BACT for Wartsila
diesel generator MG-17, unless ADEC satisfactorily docu-
ments why SCR is not BACT for the Wartsila diesel genera-
tor at the Red Dog mine faciiity, or ADEC has demonstrated
that the PSD permit is in compliance with the prevention of
significant deterioration provisions of Part C of the Act,
42 U.S.C. §§ 7470-7492, and the Alaska SIP relating to the
construction or modification of new sources or the modifica-
tion of existing sources. In either case, ADEC must first
obtain EPA’s written concurrence on this determination.
* * *
c. In the event ADEC has already issued or released the
permit, ADEC is ordered to retract or render it ineffective
until such time as EPA provides written concurrence that the
permit is in compliance with the prevention of significant
deterioration provisions of Part C of the Act, 42 U.S.C. §§
7470-7492, and the Alaska SIP relating to the construction or
modification of new sources or the modification of existing
sources.
45. Shortly after receiving the ADEC 113/167 Order,
ADEC issued Air Quality- Construction Permit No. 9932-
AC005 for the Cominco Red Dog Mine on December 10,
1999 (final permit). The final permit was accompanied by a
Final Technical Analysis Report dated December 10, 1999
(12/10/99 Technical Report).
46. The 12/10/99 Technical Report states at page 49 that
“The Department [ADEC] finds an emission limit achievable
with low NOx controls to be BACT on diesel generator
MG-17. A vendor-guaranteed emission rate of 121.3 lb/hour
is representative of the NOx reduction expected of the Low
NOx controls selected as BACT.”
47. Section 4, Best Available Control Technology (BACT)
for Oxides of Nitrogen (NOx), Condition 20.1 of the final
permit requires Wartsila diesel generator MG-17 to limit
NOx emissions to no greater than 121.3 lb/hour averaged
over any three hours.
62a
48. On February 8, 2000, EPA notified ADEC pursuant to
Section 113(a)(5) of the Act, 42 U.S.C. § 7413(a)(5) that
Permit No. 9932-AC005, issued to Cominco on December
10, 1999, fails to comply with Part C of the Act, 42 U.S.C. §
7470-7492,
This text is long and has been trimmed here. Open the source document for the complete record.
This is a copy of a public record, reproduced as it was published. It is not legal advice, and it may not be the version a court would rely on. Check the official source before you cite it.