Petition for Writ of Certiorari — Bay Area Laundry and Dry Cleaning Pension Trust Fund v. Ferbar Corp. of Cal.
Supreme Court brief1997
Ask Donna
What actually matters in this document.
Text
/g@ 370 SEP | 0 9%
IN THE
Supreme Court of the United States
OCTOBER TERM, 1996
BOARD OF TRUSTEES, BAY AREA LAUNDRY AND
Dry CLEANING PENSION TRUST FUND,
. Petitioner,
FERBAR CORPORATION OF CALIFORNIA, INC.;
STEPHEN BARNES,
Respondents.
Petition for Writ of Certiorari to the
United States Court of Appeals
for the Ninth Circuit
PETITION FOR WRIT OF CERTIORARI
MARSHA S. BERZON *
LOWELL FINLEY
177 Post Street
Suite 300
San Francisco, CA 94108
(415) 421-7151
GEOFFREY V. WHITE
351 California Street
Suite 650
San Francisco, CA 94104
(415) 362-5658
Counsel for Petitioner
* Counsel of Record
WILSON - Eras PRINTING Co., INC. - 789-0096 - WASHINGTON, D.C. 20001
oS ~
QUESTION PRESENTED
Whether a cause of action for recovery of withdrawal
liability under the Multiemployer Pension Plan Amend-
ments Act, 29 U.S.C. § 1451, arises: (a) on the date an
employer withdraws from the plan; (b) on the date the
first payment becomes overdue; (c) for each payment
due, on the date that payment becomes overdue, unless the
plan sponsor elects to invoke the statutory provision per-
mitting acceleration of the entire withdrawal liability debt
after default; or (d) on some other date.
(i)
- ee
TABLE OF CONTENTS
Page
EE i
TABLE OF AUTHORITIOG ..............:20....<-000-................ iv
PETITION FOR A WRIT OF CERTIORARI ............ 1
EEE a 1
EE SE 2
EE 2
STATEMENT OF THE CASE .................-0......0cccc000000--2-- 2
TD 2
_ ees mm 4
EE 5
REASONS FOR GRANTING THE PETITION ........ 7
a aenesseusenesoconons 19
(iii)
iv
TABLE OF AUTHORITIES
Cases Page
Board of Trustees of the Constr. Laborers Pension
Trust v. Thibodo, 34 F.3d 914 (9th Cir. 1994),
cert. denied, 115 S. Ct. 1861 (1995) —.............. 6, 13
Board of Trustees of the Dist. No. 15, Machinists
Pension Fund v. Kahle Eng’g. Corp., 43 F.3d
FRET ee passim
Carriers Container Council, Inc. v. Mobile S.S.
Ass’n., Inc., 948 F.2d 1219 (11th Cir. 1991)... 18
Central States, Southeast & Southwest Areas Pen-
sion Fund v. Navco, 3 F.3d 167 (7th Cir. 1993),
cert. denied, 510 U.S. 1115 (1994) passim
Concrete Pipe & Prods. v. Construction Laborers
Pension Trust, 508 U.S. 602 (1993) . nen 3,9
Giroux Bros. Transp. v. New England Teamsters
& Trucking Indus. Pension Fund, 73 F.3d 1 (1st
SS ti TS 8, 13, 15
Joyce v. Clyde Sandoz Masonry, 871 F.2d 1119
(D.C. Cir.), cert. denied, 493 U.S. 918 (1989)... passim
Milwaukee Brewery Workers v. Jos. Schlitz Brew-
ing Co., —— U.S. ——, 115 S.Ct. 981 (1995)... passim
Pilot Life Ina. Co. v. Dedeauzx, 481 U.S. 41 (1987). x
Shaw v. Delta Air Lines, Inc., 463 U.S. 85 (1983) .. s
Trustees of the Plumbers and Pipefitters National
Pension Fund v. Mar-Len, Inc., 30 F.3d 621 (5th
Statutes
oe Ie RE eS AT Pim 8 PE 16
28 U.S.C. § 1254(1) -............. isieaisiaiadeiatcentiaaiaieciatinaiiataa 2
29 U.S.C. § 1001 et seq. oon. ae 3
§ 1145 _... cE ES eee 14, 16
Ee ce nee mae Ee 2, 6,9
tt EN CAL: Ae ee " 9
§ 1883 (b) (2) (B) (ii) —........................ 12
ES. Pee ere 9
SERS Eee eee ee 9
§ 1383 (e) 13
§ 1399 (b) (1) oo OC ene eee SS ye 2, 10, 13
§ 1891 (b) (1) (C) -................. iaidelebiaiidtniaaabaciias 11
- 2 ee ee
v
TABL ~ OF AUTHORITIES—Continued
Page
§ 1399(b) (2) (A) (T) 3
| eA SR ee 16
ie APE TE lags 16
“ws Oe 3, 10, 16
5 SSE SARI ea 14
; at es sunsnnassnconssstnatetanesasees 16
5 ELLE eae meee 11,1
eT ne Reet iain: air
en Ras BI es 8 a 10
Fe I a SES 3,14
NA” passim
ANSI ae SP eZ 3, 10, 15
§1451(b) Sneincineitaeteinmarinniinetidiesiati es 16
; aa ro idstosnassunearsnsuncsenstnemenetheeensessadannieesmesss 14
a ee nS passim
I i ites cS us passim
ED eee eee ate 2 3, 5, 6
In THE
Supreme Court of the United States
OcTOBER TERM, 1996
No. 96- ——
BOARD OF TRUSTEES, BAY AREA LAUNDRY AND
Dry CLEANING PENSION TRUST FUND,
7 Petitioner,
FERBAR CORPORATION OF CALIFORNIA, INC.;:
STEPHEN BARNES,
Respondents.
Petition for Writ of Certiorari to the
United States Court of Appeals
for the Ninth Circult
PETITION FOR WRIT OF CERTIORARI
The Board of Trustees of the Bay Area Laundry and
Dry Cleaning Pension Trust Fund (“Trustees”), the
plaintiff in the district court and the appellant in the
Court of Appeals, respectfully petitions for a writ of cer-
tiorari to review the judgment of the United States Court
of Appeals for the Ninth Circuit in this case.
OPINION BELOW
The opinion of the United States Court of Appeals for
the Ninth Circuit is reported at 73 F.3d 971 and is re-
appears as Appendix B, at App. 6a-19a.
printed as Appendix A to this Petition (App.), at App.
la-Sa. The opinion of the United States District Court
for the Northern District of California is unreported and
2
JURISDICTION
The Court of Appeals for the Ninth Circuit entered an
order denying a petition for rehearing on May 13, 1996.
App. 20a. On August 1, 1996, Justice O'Connor ex-
tended the time within which to file the petition for writ
of certiorari to and including September 10, 1996.
The jurisdiction of this Court is invoked under 28 U.S.C.
§ 1254(1).
STATUTES INVOLVED
The statutes and regulations involved are set forth in
Appendix E to the Petition, App. 30a-49a.
STATEMENT OF THE CASE
1. The Statutory Scheme
The Employee Retirement Income Security Act of
1974, (“ERISA”), 29 U.S.C. § 1001 ef seq.,' as amended
by the Multiemployer Pension Plan Amendments Act of
1980, requires an employer withdrawing from a multi-
employer pension plan to pay its share of any unfunded
vested pension obligations. § 1399(b)(1). An employer
ordinarily completely withdraws from a multiemployer
plan when it permanently ceases to have an obligation to
contribute under the plan or permanently ceases all cov-
ered operations under the plan. § 1383(a).° The amor-
tized withdrawal liability payments are calculated by the
fund and assessed to the withdrawing employer accord-
ing to a schedule set up by the fund but in large part
dictated by the statute, with payments to begin
within sixty days after the fund demands payment.
§ 1399(c)(2).°
1 All subsequent statutory citations are to Title 29 of the United
States Code unless otherwise indicated. “
2 There are special complete withdrawal provisions covering cer-
tain industries and circumstances. See n.6 and p. 12, infra.
8 The multiple and complex calculations that must be performed
by the plan’s actuary in order to assess withdrawal liability are
5
Ae ere
—_
ete 5
3
Within 90 days after 1:eceiving the plan sponsor's notice
of withdrawal liability, the employer may ask the plan
sponsor to review the determination of liability or the
schedule of payments, or both. § 1399(b)(2)(A)(i).
After this review, any dispute concerning the demand is
subject to arbitration (§ 1401(a)(1)): Within 60 days
after (a) the plan sponsor’s response to the employer's
request for review or (b) 120 days after the employer's
request for review, whichever is earlier, the employer may
initiate arbitration. § 1401(a)(1). While the arbitra-
tion proceeds, the employer must make periodic interim
payments according to the schedule set forth by the plan
sponsor. §§ 1399(c)(2), 1401(d).
If the employer does not meet its withdrawal liability
obligations, the statute provides a cause of action by the
plan trustees:
A plan fiduciary, employer, plan participant, or
beneficiary, who is adversely affected by the act or
omission of any party under this subtitle with respect
to a multiemployer plan . . . may bring an action
for appropriate legal or equitable relief, or both.
[$ 1451(a)(1)]
As to the limitations question, the critical statutory sec-
tion provides:
(f) An action under this section may not be brought
after the later of —
(1) 6 years after the date on which the cause
of action arose, or
(2) 3 years after the earliest date on which the
plaintiff acquired or should have acquired actual
knowledge of the existence of such cause of
action; except that in case of fraud or conceal-
ment, such action may be brought not later than
6 years after the date of discovery of the exist-
ence of such cause of action. [§ 1451(f)]
described in Concrete Pipe & Prods. v. Construction Laborers Pen-
sion Trust, 508 U.S. 602, 609-10 (1993).
4
The issue in this case is when the statute of limitations
established by § 1451(f) begins to run on a cause of
action for failure to make withdrawal liability payments.
2. Facts
Ferbar Corporation (“Ferbar” or “the employer”)
contributed to the Bay Area Laundry and Dry Cleaning
Pension Fund (“Trustees” or “Fund”) for several years
for three business locations, but ceased all contributions
on or about March 1, 1985. CR. 13 at 1-2."
On December 12, 1986, the Fund assessed withdrawal
liability against Superior French Laundry, one of the three
laundries operated by Ferbar, in the amount of
$45,580.80. CR. 13 at 2. The assessment notice gave
Ferbar a choice between a single lump-sum payment of
the total withdrawal liability by February 10, 1987, and
monthly installment payments of $345.50 commencing
February |, 1987. The notice also stated that the em-
ployer would be deemed in “default” if any delinquency
were not cured within 60 days after notice of delinquency,
and that Ferbar was required by law to make the pay-
ments as scheduled notwithstanding any request for re-
view or appeal. CR 15, Exh. 1.
By letter dated February 27, 1987, Ferbar exercised
its right to request review of the assessment by the
Trustees. CR. 16, Exh. 2. During the pendency of the
review, Ferbar made no payments on its withdrawal
liability. CR. 13 at 3.
Having received no withdrawal liability payments, the
Fund, on April 14, 1987, notified Ferbar of the delin-
quency. CR. 16, Exh. 3. The delinquency notice stated
that Ferbar had sixty days to cure the delinquency, or it
would be in “default,” in which case liability for the full
amount of outstanding withdrawal liability could be accel-
4These facts were accepted as true for purposes of summary
judsgrment.
ee Se
5
erated. And the notice of delinquency notified Ferbar
once again that ERISA required it to make the scheduled
payments notwithstanding any request Ferbar might make
for review or appeal of the Fund’s determination.
Ferbar did not cure its delinquency after receiving the
delinquency notice, but did, on July 8, 1987, request arbi-
tration of its disputed withdrawal liability. CR 16, Exh.
4. Ferbar made no payments of withdrawal liability at
any time.
3. Proceedings
The Trustees filed their complaint for collection of un-
paid withdrawal liability on February 9, 1993, eight days
more than six years after the first withdrawal liability pay-
ment was due under the assessment but less than six years
after any other payment of the withdrawal liability was
due, and less than six years after the entire amount of the
withdrawal liability could have been demanded under the
assessment or the statute. CR. 1. Ferbar answered on
March 23, 1993. CR. 3. Thereafter, Ferbar filed a Mo-
tion for Summary Judgment based solely on failure to
meet the appiicable statute of limitations, and the Trustees
filed a cross-motion for suiuumary judgment. CR. 10, 14.
. The District Court held that the Trustees’ action was
time-barred under the three-year “discovery” statute of
limitations set forth in § 1451(f)(2), notwithstanding the
express language in the statute providing that the appli-
cable limitations period is “the later of” the three-year
discovery period in § 1451(f)(2) or the six-year accrual
period in § 1451(f)(1). Alternatively, the District Court
held that the Trustees’ action was also time-barred under
the six-year limitations period in § 1451(f)(1), conclud-
ing that the Trustees’ cause of action arose, and the limita-
tions period on the entire amount of the withdrawal lia-
bility began to run, on February 1, 1987, when Ferbar
failed to make the first installment payment on the date
scheduled by the Fund.
6
On appeal, the Ninth Circuit held that the District
Court had erred by applying the three-year discovery limi-
tations period in § 1451(f)(2). The Ninth Circuit af-
rirmed the judgment, however, holding that the action was
time-barred under the six-year limitations period of § 1451
(f)(1).
Unlike the District Court, which had viewed the cause
of action as arising on the date of the first missed payment,
the Ninth Circuit ruled that a cause of action under
§ 1383(a) accrues, and the limitations period of § 1451
(f)(1) begins to run, on the date on which an employer
completely withdraws from a plan. In so holding, the
court relied upon its own decision in Board of Trustees
of the Constr. Laborers Pension Trust v. Thibodo, 34
F.3d 914 (9th Cir. 1994), a case construing the relation-
ship between a different withdrawal liability subsection of
the statute, § 1383(b), and the statute of limitations pro-
vision, § 1451(f).° Because Ferbar had effected a com-
plete withdrawal from the Fund more than six years
before the Trustees’ action was filed, the Ninth Circuit
affirmed the summary judgment for Ferbar. App. Sa.
Judge Trott concurred reluctantly, stating that he was
compelled to join in the judgment by the court’s previous
decision in Thibodo. In his concurrence, Judge Trott,
noting that the D.C. Circuit had, in Joyce v. Clyde Sandoz
Masonry, 871 F.2d 1119 (D.C. Cir.); cert. denied, 493
U.S. 918 (1989) decided the same statute of limita-
tions issue differently than the Ninth Circuit did in this
case, expressed the view that Joyce “does a better job of
answering the questions raised by these issues... .”
App. 5a.
5 The Thibodo opinion appears in Appendix D to this Petition,
at App. 21a.
A te ee
en a mn Mmm
7
REASONS FOR GRANTING THE PETITION
This case presents the Court with an opportunity to
resolve a serious and multifaceted disagreement among the
circuits on the application of the statute of limitations
governing actions by multiemployer pension benefit plans
to recover ERISA withdrawal liability payments.
The Ninth Circuit held that the § 1451(f)(1) limita-
tions period begins to run on the date that the employer
completely withdraws from a multiemployer pension fund.
It so held even though, as this Court recognized last year
in Milwaukee Brewery Workers v. Jos. Schlitz Brewing
Co., US. , 115 S.Ct. 981 (1995), the statute
does not impose any obligation on the employer to make
any payment on the date of withdrawal. Instead, the
statute simply uses that date in assessing the amount and
number of payments due to be paid by the employer con-
siderably later, after the plan calculates the total amount
due, sets out the required payment schedule, and makes
a demand for payment. 115 S.Ct. at 988. Thus, accord-
ing to the Ninth Circuit, the statute of limitations on a
suit to collect withdrawal liability begins to run well before
the plan trustees can file such a suit.
The four other circuits that have ruled on the limita-
tions period applicable to collection of withdrawal liability
all disagree with the Ninth Circuit on this point. Those
circuits hold instead that the statute of limitations begins
to run from the date when the plan trustees first can bring
suit on the claims, not months or years before that. Since,
under the complex statutory system for assessing and col-
lecting withdrawal liability reviewed in Schlitz, the right
to file a collection action arises only after withdrawal lia-
bility has been assessed and payment is due, all four of
the other circuits hold that the statute of limitations under
§ 1451(f)(1) begins to run only then. Joyce v. Clyde
Sandoz Masonry, 871 F.2d at 1123-24, Central States,
Southeast & Southwest Areas Pension Fund v. Navco, 3
F.3d 167, 172 (7th Cir. 1993), cert. denied, 510 US.
1115 (1994): Board of Trustees of the Dist. No. 15,
8
Machinists Pension Fund v. Kahle Eng’g. Corp., 43 F.3d
852, 859-61 (3d Cir. 1994); Giroux Bros. Transp. v.
New England Teamsters & Trucking Indus. Pension
Fund, 73 F.3d 1, 3-4 (1st Cir. 1996).
At the same time, those circuits are in discord among
themselves as to precisely how the limitations period ap-
plies once there has been the requisite statutory demand
for payment: The Seventh and Third Circuits are directly
at odds concerning whether, as the district court in this
case held, the limitations period for the entire amount of
withdrawal liability runs from the first missed payment or
whether, instead, there is a separate limitations period
running from each missed payment unless and until the
multiemployer plan exercises its statutory option to accel-
erate the withdrawal payment obligation because of de-
fault. Compare Navco, supra (single limitations period
for entire amount), with Kahle Engineering Corp., supra
(separate period for each missed payment unless the pay-
ment obligation is accelerated after default ).
The various interpretations of the statutory limitations
period adopted by the circuits yield widely varying results
on the same facts. In this case, for example, the action
for collection of withdrawal liability is timely under the
District of Columbia Circuit’s interpretation of § 1451
(f)(1) adopted in Joyce v. Clyde Sandoz Masonry and
the Third Circuit’s interpretation adopted in Kahle Engi-
neering Corp., but is untimely under the Ninth Circuit's
rule in this case and under the very different statutory
interpretation reached by the Seventh Circuit in Navco.
As Congress recognized in enacting ERISA, many funds
operate in broad geographical areas and are hampered
in their operations if subject to varying rules with regard
to such basic functions as the collection of funds necessary
to assure fund solvency. For that reason, assuring uni-
formity in the rules governing employee benefit plans is
a central purpose of ERISA. Pilot Life Ins. Co. v.
Dedeaux, 481 U.S. 41, 56 (1987); Shaw v. Delta Air
Lines, Inc., 463 U.S. 85, 98-100 (1983).
ee ee
9
Because of the current disarray on the MPPAA with-
drawal liability limitations issue among the circuits, the
many pension plans that operate within the jurisdiction of
more than one of the five circuits which have spoken to
this issue must have administrative systems in the various
circuits operating under different time lines for the pur-
pose of assessing and collecting withdrawal liability. To
eliminate this disruptive disparity in the application of
§ 1451(f), this Court should grant certiorari and, as it
has in two other recent cases raising issues concerning the
assessment and collection of withdrawal liability under
the MPPAA (Schlitz, supra and Concrete Pipe & Prods.
v. Construction Laborers Pension Trust, 508 U.S. 602
(1993)), announce a uniform rule applicable to all multi-
employer pension plans wherever they operate.
1. The Ninth Circuit, alone of the five circuits that
have addressed the issue, holds that for purposes of the
time limitations governing actions for recovery of with-
drawal liability, a Fund’s cause of action arises under that
section on the day the employer permanently withdraws
from the plan. App. Sa. As the other four circuits that
have addressed the question have recognized, this result
simply cannot be squared with the statutory scheme as a
whole.
A. As Schlitz explained, the MPPAA “imposed a with-
drawal charge on all employers withdrawing from an
underfunded plan . . . [aJ]nd set forth a detailed set of
rules for determining, and collecting, that charge.” 115
S.Ct. at 985. The calculation of that charge is triggered
once there has been a “complete withdrawal from a multi-
employer plan,” which occurs ordinarily when an employer
“permanently ceases to have an obligation to contribute
under the plan, or . . . permanently ceases all covered
operations under the plan.” 29 U.S.C. § 1383(a); Con-
crete Pipe, 508 U.S. at 610.°
® There are special provisions for determining complete with-
drawal in certain industries. § 1383(b), (c), (d) and (f); see
p. 12, infra.
10
No obligation to pay wtihdrawal liability arises, how-
ever, on the date the withdrawal is deemed to occur.
Rather, as this Court noted in Schlitz, while “[t]he statute
.. . might make the withdrawing employer pay (or begin
payment) on the date the employer actually withdraws
.. . it does not do so.” 115 S.Ct. at 987. Instead, the
language in § 1399(b)(1) and (c)(2) “makes clear that
the withdrawing employer owes nothing until its plan
demands payment... .” /d. at 988; see also id. at 987
(noting that “[t}he statute says that a plan must draw
up a schedule for payment and ‘demand payment’ as
‘soon as practicable’ after withdrawal . . . [and] adds
that ‘[w]ithdrawal liability shall be payable . . . no more
than 60 days after the date of the demand.’ 29 U.S.C.
§ 1399(c)(2).”)*
It is only once the withdrawal liability payments are
“due and owing on the schedule set forth by the plan
sponsor” that “[t]he plan sponsor may bring an action
in a State or Federal court of competent jurisdiction for
collection.” § 1401(b)(1). Section 1451, in turn, pro-
vides that a plan fiduciary “adversely affected by the act
or omission of any party . . . with respect to a multi-
employer plan . . . may bring an action . . . six years
after the date on which the cause of action arose.” 29
U.S.C. § 1451(a)(1) and (f)(1).
7 As Schlitz also explains, the statute requires that the plan
permit the withdrawal liability to be paid either in a lump sum
or in equal installments, and prescribes the method according to
which the amount of each installment and the number of install-
ments is to be calculated. Then, to be more precise than the Court
had reason to be in Schlitz, the statute provides that “{w]ithdrawal
liability shall be payable in accord with the schedule set forth by
the plan .. . beginning no later than 60 days after the date of
the demand.” 29 U.S.C. § 1399(c)(2). As we explain later, the
employer has no obligation to pay the total amount of the with-
drawal liability any sooner than the mandatory installment plan
payment schedule provides, unless the plan elects to accelerate the
payment schedule to demand full payment because of payment
default. See pp. 15-19, infra.
11
Given this statutory scheme, it is clear that “[t)he stat-
ute carefully distinguishes between the circumstances that
define complete withdrawal and those which give rise to a
cause of action.” Joyce v. Clyde Sandoz Masonry, supra,
871 F.2d at 1123. The function of delineating the date
of complete withdrawal is simply “to demarcate or to
allow calculation of the employer's share, if any, of the
plan’s unfunded vested liability.” Jd. No “cause of action”
“arises” on the date that complete withdrawal occurs be-
cause no employer payment obligation of any kind,
capable of being breached, exists until well after that
date."
Instead, as the D.C. Circuit went on to explain in
Joyce:
The statute itself . . . indicates that the plan is
“adversely affected” (and thus that a “cause of ac-
tion” arises) when the plan has not received pay-
ments which are due and owing. The language of
the statute (including the terms of section 145!
itself) points firmly in the direction of the conclu-
sion that [the employer's} uncured failure to pay
the sum demanded adversely affect{s] the plan, thus
giving rise to a cause of action. See 29 U.S.C.
$§ 1399(c)(5), 1401(b). .. . Withdrawal, in itself,
does not visit any adverse effect upon the plan that
gives rise to the cause of action. [871 F.2d at 1122-
23, footnotes and citations omitted. ]}
In short, the Court of Appeals’ analysis in this case
fails because, »nlike the D.C. Circuit's reasoning in Joyce,
the Ninth Cir uit ignored critical statutory language per-
mitting plans to bring suit for withdrawal liability only
after payments are “due and owing.”
® Indeed, on the date of complete withdrawal, neither the plan
sponsor nor the employer knows the amount of withdrawal! lia-
bility or even whether the employer will owe anything. See
§ 1391(b) (1) (employer’s proportional share of the plan’s unfunded
vested benefits may be “zero.”)
12
B. This statutory language and structure analysis is
more than sufficient to demonstrate why the D.C. Cir-
cuit was right ard the Ninth Circuit wrong on the
question here presented. Additionally, the D.C. Circuit's
application of § 1451 in Joyce yields a result that ac-
counts for the pertinent practical considerations, while
the Ninth Circuit’s statute of limitations theory is based
on practical concerns that ae fully met by statutory pro-
visions quite separate from the limitations section.
On the one hand, the Joyce approach takes account, as
the Ninth Circuit interpretation does not, of the fact that
it is sometimes impossible to determine whether a com-
plete withdrawal has occurred until years after the fact,
as in cases of plant shutdowns or bargaining impasse.
“This determination cannot necessarily be made upon
complete withdrawal; rather it requires a post hoc deter-
mination of when a particular cessation of covered opera-
tions, for example, actually signaled a permanent halt to
(rather than a lull in) operations.” Joyce v. Clyde Sandoz
Masonry, 871 F.2d at 1123.
In the building and construction industry, the uncer-
tainty is exacerbated. The MPPAA provides that com-
plete withdrawal occurs on the date such an employer
“ceases to have an obligation to contribute under the
plan,” but only if the employer “resumes such work within
5 years after the date on which the obligation to con-
tribute under the plan ceases, and does not renew the
obligation at the time of the resumption.” § 1383(b)(2)
(B) (ii). As a result,
the plan sponsor (or any other party) may not be
able to establish that the building or construction
industry employer has completely withdrawn until
as much as five years after what the parties eventually
determine to have been the date of complete with-
drawal. To conclude that an event requiring such
a post hoc (and belated) determination triggers the
limitations bar would create, at the least, an un-
13
wieldy statutory collection mechanism. [Joyce v.
Clyde Sandoz Masonry, 871 F.2d at 1123-24.]°
On the other hand, while the Ninth Circuit thought that
its construction of § 1451 was necessary to assure that
pension plan trustees promptly assess and collect with-
drawal liability (App. 27a), MPPAA provisions entirely
apart from the running of the statute of limitations pro-
vide powerful incentives for plan sponsors to expedite the
process of assessing withdrawal liability.
Section 1399(b)(1) requires the plan sponsor to as-
sess, schedule and demand withdrawal liability payment
“fa]s soon as practicable after an employer’s complete
or partial withdrawal.” § 1399(b)(1). An employer may
defend in arbitration against paying withdrawal liability
on the ground that the plan sponsor failed to satisfy
the “as soon as practicable” requirement. Giroux Bros.
Transportation, Inc. v. New England Teamsters & Truck-
ing Industry Pension Fund, 73 F.3d at 2, 4; see Joyce v.
Clyde Sandoz Masonry, 871 F.2d at 1126-27. Thus, a
* The Ninth Circuit purported to avoid this problem in Thibodo
by holding that the statute of limitations runs not from the date
defined by the statute as the “date of complete withdrawal” —
namely, the “date of the cessation of the obligation to contribute or
the cessation of covered operations” (§ 1383(e))—but, instead,
from “the date on which the conditions for complete withdrawal!
... have been met”—that is, in the case of a construction industry
employer who returns to the jurisdiction within five years, the
date of that return. 34 F.3d at 917. In this case, however, the
Ninth Circuit lost sight of that distinction, and instead construed
and applied Thibodo as holding that “[i)n other words, the limita-
tions period begins to run from the date of complete withdrawal.”
App. 4a.
If anything, Thibodo adds to the disarray in the courts of appeals
in determining when a cause of action arises within the meaning
of § 1451(f) (1), by suggesting that sometimes a cause of action
arises after the date on which complete withdrawal is deemed to
occur under the statute but still before the
14
plan that is dilatory in assessing the withdrawal liability
and demanding payment risks losing the right to collect
the amount due.
Moreover, “(t]he plan sponsor that unduly delays in
taking appropriate action . . . may invite a claim for
breach of fiduciary duty.” Joyce, 871 F.2d at 1126.
Putting off the assessment and collection of withdrawal
liability causes the plan to lose the investment value of
money due to it, and may threaten the solvency of the
fund.” Plan beneficiaries therefore could sue procrastinat-
ing trustees under ERISA, seeking to recover for the
fund the earnings the withdrawal funds could have gener-
ated for the beneficiaries had those funds been timely
assessed, collected and invested. See §§ 1145, 1399
(c)(3), 1401(d), 1451(d).
Because other provisions of ERISA adequately assure
timely assessment of and demand for withdrawal liability,
there is no reason to contort the provisions governing the
statutory limitations period on filing collection lawsuits,
as the Ninth Circuit did here, in order to serve ends for
which those provisions were not intended.
2. While disagreeing uniformly with the Ninth Cir-
cuit’s erroneous interpretation of § 1451(f)(1), other cir-
cuits have adopted at least two other inconsistent and
incompatible interpretations of that provision:
The Seventh Circuit holds that once there is the requi-
site demand for payment of withdrawal liability and the
employer fails to make a single installment payment under
the schedule set out by the plan sponsor, the limitations
period on the entire withdrawal liability begins to run.
According to the Seventh Circuit, unless the plan sues for
” The amount of the amortization interest built into the pay-
ment schedule is fixed by the statute no matter when collection
actually occurs. Schlitz, 115 S.Ct. at 990. Consequently, if the
plan trustees do not promptly assess withdrawal liability, the plan
will not collect interest for the period of the delay.
15
the entire amount within the statutory limitations period
as figured from the first missed payment, it loses the right
to sue for any of the installments due later. Central
States Pension Fund v. Navco, supra, 3 F.3d at 172.
The Third Circuit, in Dist. 15, Machinists Pension
Fund v. Kahle Engineering Corp., supra, expressly re-
jected the Navco approach as “unpersuasive.” 43 F.3d
at 858. Kahle holds instead that, unless the plan chooses
to accelerate the entire debt after a missed payment
under § 1399(c)(5), as it “may” do, the limitations
period runs from each missed installment payment, with
respect to collection of that payment."'
On the facts of this case, the difference between the
Third and Seventh Circuit positions is determinative. The
collection suit in this case was filed more than six years
(by eight days) after the first missed payment was due,
but less than six years after every other installment pay-
ment (as well as the alternative, lump sum payment) was
due, and less than six years before the plan could have
insisted on accelerating payment of the entire debt under
the statute had it wished to.” Under the Seventh Cir-
'! Neither the D.C. Circuit in Clyde Sandoz Masonry nor the
First Circuit in Giroux squarely addressed the question on which
the Naveco and Kahle Engineering opinions are in conflict. The
reasoning of Clyde Sandoz Masonry, however, favors the Kahle
Engineering approach. 871 F.2d at 1124 (the cause of action arises
“based on the adverse effect on the plan of failure to receive
demanded payment,” and the plan may, but need not, make demand
for “the entire amount of withdrawal liability,” but only after
default on a payment); see Kahle Engineering, 43 F.3d at 860
(reading Clyde Sandoz Masonry as supporting the Kahle Engineer-
ing interpretation).
12 Under the statute and implementing regulations, the plan may
not accelerate the payment schedule and demand payment in full!
during the period allowed for appeals and arbitration challenging
the liability assessed. § 1451(a)(1); Kahle Engineering Corp.,
43 F.3d at 855 (“[i]f an employer misses a scheduled [interim]
payment, the fund may seek to collect by filing a collection action
16
cuit’s Navco interpretation of the statute, the suit is barred
(as the District Court in this case alternatively held);
under the Third Circuit’s Kahle Engineering analysis, the
only possible impact of § 1451(f)(1) would be to bar
collection of the first unpaid installment payment.
The Kahle Engineering analysis is faithful to the statu-
tory scheme, as a whole, while that of the Seventh Circuit
in Navco is not.
The premise of the Navco holding is that “[a]lthough a
fund may permit an employer to amortize [withdrawal
liability] over twenty years . . . the whole amount is pre-
sumptively due at the outset.” 3 F.3d at 172 (emphasis
supplied). That premise is simply wrong.
As this Court made clear in Schlitz, the statute itself
establishes the installment payment option for employers,
the amount of each annual payment, and the number of
such annual payments that may be required. 115 S.Ct.
at 986; § 1399(c)(1). Under the statute, the only statu-
tory obligation of the employer at the time of the first
missed payment was to pay that installment. The plan
therefore could not sue at that juncture, even if it wished
to, for more than that single payment. See &§ 1399(c)
(1)(A), (2), and (4) (obligation is to pay acvording to
the installment schedule); 1451(b) (in an action to com-
pel payment of withdrawal liability, “any failure of the
employer to make any withdrawal liability payment shall
be treated in the same manner as a delinquent contribu-
tion (within the meaning of section 1145 of this title).”)
It is true, of course, that the MPPAA ailows, but does
not require, a plan sponsor faced with the default of a
withdrawing employer on one or more scheduled pay-
but it may not accelerate the balance during that protected arbitra-
tion period.”) See also Trustees of the Plumbers and Pipefitters
National Pension Fund v. Mar-Len, Inc., 30 F.3d 621, 624 (5th
Cir. 1994).
: 17
ments to accelerate the employer's obligation to pay the
full amount of withdrawal liability." Such default and
acceleration “provide[] the predicate for a plan sponsor's
suit” for the full amount of withdrawal liability (Joyce v.
Clyde Sandoz Masonry, 871 F.2d at 1123), but only
if the plan sponsor elects to accelerate."
By insisting that “the whole sum becomes due and the
whole claim accrues when the first payment is missed”
Navco “in effect imposes a compulsory acceleration
clause,” although the statute in terms provides a discre-
tionary one, and one that can be invoked necessarily only
after the first payment is due under the plan’s demand.
Kahle Engineering, 43 F.3d at 859. The Navco holding
is therefore at odds with the statute’s plain language.
The Kahle Engineering analysis, in contrast, gives effect
to both the obligation to permit installment payments
18 Section 1399(c) (5) provides:
In the event of a default, a plan sponsor may require imme-
diate payment of the outstanding amount of an employer's
withdrawal liability, plus accrued interest on the total ovt-
standing liability of the employer from the due date of the
first payment which was not timely made. For purposes of this
section, the term “default” means— -
(A) the failure of the employer to make, when due, any
payment under this section, if the failure is not cured
within 60 days after the employer receives written notifi-
cation from the plan sponsor of such failure, and
(B) any other event defined in rules adopted by the plan
which indicates a substantial likelihood that ar employer
will be unable to pay its withdrawal liability.
14 The analysis in the text is intentionally simplified to apply to
any missed payment. We reiterate, however, that at the outset
of the payment schedule the Seventh Circuit’s interpretation is
particularly untenable, since the option the plan otherwise has to
accelerate the entire debt if it wishes to and demand payment of
all of the withdrawal liability does not come into existence until
after the period for demanding arbitration has passed—which it
had not as of February 1, 1987 in this case. See n.12, supra.
18
and the optional nature of debt acceleration when one of
the payments is missed. As the Third Circuit explained:
the employer’s obligation to make the scheduled
payments is akin to the obligation to make install-
ment payments. In an installment payment contract,
a new cause of action arises from the date each
payment is missed. [43 F.3d at 857].
See also Carriers Container Council, Inc. v. Mobile S.S.
Ass'n., Inc., 948 F.2d 1219, 1223 (11th Cir. 1991)
(“with respect to each withdrawal liability installment, the
right to sue [under 29 U.S.C. § 1451] is triggered by the
failure to pay the installment within the prescribed time,”
i.e., at the due date of each installment).
The Kahle interpretation is not only more consistent
with the statutory language and structure but also avoids
“perverse incentives” that the Navco rule creates. Kahle
Engineering, 43 F.3d at 859. Maintaining the flexibility
of the plan not to accelerate the debt when a payment is
missed “[en]courages amicable resolution of disputes and
. . reentry into the fund as a contributing employer.”
Id. To force acceleration of the debt when the first missed
payment occurs would preclude an accommodating fund
from suing on any payment missed more than six years
after the first, and could require a plan to sue for the
'’ As Kahle went on to note, where there is an installment sales
contract, the statute of limitations begins to run separately against
each installment when that installment becomes due, whether or
not the debtor has the option to pay the entire indebtedness at
any time and whether or not the creditor has “ ‘the right upon
certain contingencies to declare the whole sum due... unless the
creditor exercises his option to declare the whole indebtedness due,
in which case the statute begins to run from the date of the exercise
of his option.’” Kahle Engineering, 43 F.3d at 857, quoting 51
Am.Jur.2d: Limitations of Actions § 133; see Carriers Container
Council, Inc. v. Mobile S.S. Asa’n., Inc., 948 F.2d at 1222-24.
This Court in Schlitz confirmed that the method of paying with-
drawal liability under the statute is akin to contractual installment
payments. 115 S.Ct. at 988.
19
entire amount rather than for the past overdue payments
alone even where doing so would make the employer in-
solvent (and therefore unable to make the later payments
as they become due). Insisting upon draconian enforce-
ment of the obligation to pay withdrawal liability does
not benefit any of the potentially affected parties—the
employer, the plan, or the plan beneficiaries.
CONCLUSION
The question presented here—when a cause of action
for an employer’s failure to fulfill its withdrawal liability
obligation arises—affects employers, pension plans, and
employees throughout the nation. The Courts of Appeals
are in disarray on these issues, taking several inconsistent
and incompatible positions. This case is well-suited for
a definitive decision by this Court, because the facts of the
case raise every one of the various interpretive permuta-
tions adopted by the courts of appeals. This Court should
therefore grant this petition for writ of certiorari to the
Court of Appeals for the Ninth Circuit.
Respectfully submitted,
MARSHA S. BERZON *
LOWELL FINLEY
177 Post Street
Suite 300
San Francisco, CA 94108
(415) 421-7151
GEOFFREY V. WHITE
351 California Street
Suite 650
San Francisco, CA 94104
(415) 362-5658
Counsel for Petitioner
* Counsel of Record
_ APPENDICES
la
APPENDIX A
UNITED STATES COURT OF APPEALS
NINTH CIRCUIT
No. 94-15976
Bay AREA LAUNDRY & Dry CLEANING PENSION
TRUST FUND,
Plaintiff-A ppellant,
Vv.
FERBAR CORPORATION OF CALIFORNIA, INC., a California
Corporation; FERREIRA FARMS, INc., a California
corporation; STEPHEN J. BARNES, and RosBerRT J.
FERREIRA,
Defendants-A ppellees.
Appeal from the United States District Court
for the Northern District of California
Argued and Submitted Nov. 16, 1995
Decided Jan. 17, 1996
Before: NORRIS, BEEZER, and TROTT, Circuit
Judges.
PER CURIAM:
This case arises from an action filed on February 9,
1993, by the Bay Area Laundry and Dry Cleaning Pen-
sion Trust Fund against Ferbar Corp. and Stephen J.
Barnes (“Ferbar”) to collect withdrawal liability under
29 U.S.C. §§ 1381-1461, the Multi-Employer Pension
2a
Plan Amendments Act of the Employee Retirement In-
come Security Act. The district court granted summary
judgment for Ferbar on the ground that the Fund’s suit
for withdrawal liability was barred by the applicable
statute of limitations set forth in 29 U.S.C. § 1451(f).
This statute provides in relevant part:
§ 1451. Civil Actions...
(f) Time limitations. An action under this section
may not be brought after the later of—
(1) 6 years after the date on which the cause
of action arose, or
(2) 3 years after the earliest date on which
the plaintiff acquired or should have acquired
actual knowledge of the existence of such cause
of action;....
29 U.S.C. § 1451(f). The district court applied the
three-year statute of limitations set forth in § 1451(f)(2),
but in the alternative held that the action would never-
theless be barred under the six-year statute of limitations
set forth in § 1451(f)(1), reasoning that the cause of
action arose on the date that Ferbar missed its first with-
drawal liability installment payment. On appeal the par-
ties contest, first, whether the three-year or the six-year
period applies, and second, the date on which the limita-
tions period began to run.
I
BACKGROUND
In March, 1985, Ferbar effected a complete withdrawal
from the Fund. On December 12, 1986, the Fund sent
Ferbar a notice assessing a withdrawal liability obligation
of $45,580.80. The notice provided that Ferbar could
pay off its withdrawal liability in one of two ways: (1)
it could either make a single lump-sum payment of the
total liability no later than 60 days after receipt of the
demand, or (2) it could begin making installment pay-
3a
-ments according to a schedule established by the Fund,
with the first payment due on February |, 1987. Ferbar
did not pay the first installment, but rather on February
27, 1987, exercised its right to request review of the
assessment by the Board of Trustees. On April 14, 1987,
the Fund notified Ferbar that Ferbar’s first payment was
delinquent, and informed Ferbar that it had 60 days from
the notice to cure the delinquency, or it would be con-
sidered in default. Ferbar did not cure its delinquency.
APPLICABLE LIMITATIONS PERIOD
The district court held that the Fund’s action was time-
barred because it was filed more than three years after the
Fund acquired knowledge of the cause of action, citing
§ 1451(f)(2). The Fund argues that the action could
not be time-barred until six years after the cause of action
arose.
We agree with the Fund. The district court misread
the plain language of § 1451(f), which clearly directs
courts to apply “the later of” the two periods of limita-
tions. On the facts of this case, “the later of” the two
periods is six years from the date the cause of action
arose. We now turn to the question when the cause of
action arose.
Ill
WHEN THE CAUSE OF ACTION AROSE
In its alternative holding, the district court determined
that the cause of action arose on February 1, 1987, the
date on which Ferbar missed its first installment payment
for the assessed withdrawal liability. The Fund argues
that the cause of action arose on June 14, 1987, the date
of default.’ Ferbar argues that the cause of action arose
1 Default occurs when the employer has received notice that it
has missed a payment and has failed to cure the delinquency within
60 days. See 29 U.S.C. § 1899(c) (5) (defining “default’’).
4a
in March, 1985, the date of complete withdrawal, or
alternatively on the date of the first missed payment.
Our court has recently spoken dispositively on this
issue. In Board of Trustees of the Constr. Laborers Pen-
sion Trust v. Thibodo, 34 F.3d 914 (9th Cir.1994), we
held that “for actions to recover withdrawal liability in-
curred as a result of complete withdrawal under 29 U.S.C.
§ 1383(b), the limitations period begins to run from the
date that the conditions for withdrawal specified under
that section are met.” /d. at 916-17. In other words, the
limitations period begins to run from the date of complete
withdrawal—in this case, March 1985.
It is true that Thibodo by its terms applies only to ac-
tions arising under 29 U.S.C. § 1383(b), which defines
the conditions for complete withdrawal only in the build-
ing and construction industry.*. The conditions for com-
plete withdrawal in most other industries are defined by
2 § 1383 (b) provides:
§ 1383. Complete Withdrawal...
(b) Building and construction industry.
(1) Notwithstanding subsection (a) of this section, in the
case of an employer that has an obligation to contribute under
a plan for work performed in the building and construction
industry...
(2) A withdrawal occurs under this paragraph if—
(A) an employer ceases to have an obligation to contribute
under the plan, and
(B) the employer—
(i) continues to perform work in the jurisdiction of the
collective bargaining agreement of the type for which con-
tributions were previously required, or
(ii) resumes such work within 5 years after the date on
which the obligation to contribute under the plan ceases,
and does not renew the obligation at the time of the
resumption.
29 U.S.C. § 1383 (b).
Sa
§ 1383(a), which governs the present action.* However,
we see no basis for distinguishing an action brought under
§ 1383(a) from one brought under § 1383(b) for the
purpose of applying the statute of limitations set forth in
§ 1451(f). Indeed, the Fund makes no attempt to dis-
tinguish Thibodo from the present action for statute of
limitations purposes. Accordingly, we hold that Thibodo
controls actions arising under § 1383(a) as well as ac-
tions arising under § 1383(b).
Under Thibodo, the period of limitations began running
in March, 1985, when Ferbar effected a complete with-
drawal from the Fund.* Because the Fund filed the
present action on February 9, 1993, more than six years
later, we AFFIRM the summary judgment for Ferbar on
the ground that the action is time-barred.
TROTT, Circuit Judge, concurring.
I concur in Judge Norris’s opinion because I believe
Thibodo compels this result. I believe, however, that
Joyce v. Clyde Sandoz Masonry, 871 F.2d 1119 (D.C.
Cir.) does a better job of answering the questions raised
by these issues, but we do not have authority to ignore
our own decisions.
% § 1383 (a) provides:
(a) Determinative factors.
For purposes of this part, a complete withdrawal from a multi-
employer plan occurs when an employer—
(1) permanently ceases to have an obligation to contribute
under the plan, or
(2) permanently ceases all covered operations under the
plan.
29 U.S.C. § 13883 (a).
*Ferbar never agreed to the installment plan proposed by the
Fund and made no installment payments. As a result, it appears
that no new contract to pay off the withdrawal liability could have
been formed. See 1A Arthur L. Corbin, Corbin on Contracts § 211
(1963). Had such a contract been formed, the Fund might have a
separate claim, with its own statute of limitations, for breach of
that contract.
6a
APPENDIX B
[Filed May 9, 1994]
No. C-93-0489 DLJ
BOARD OF TRUSTEES, BAY AREA LAUNDRY AND _
Dry CLEANING PENSION TRUST FUND,
Plaintiffs,
v.
FERBAR CorP., FERREIRA FARMS, INC., DIABLO
CLEANERS, INC., STEPHE*. BARNES and
ROBERT FERREIRA,
Defendants.
ORDER
Following oral argument and the submission of supple-
mental briefing on December 22, 1993, the parties’ cross-
motions for summary judgment in this matter were before
the Court. Geoffrey White represented plaintiffs; defend-
ants Ferbar Corporation and Stephen Barnes were repre-
sented by William Terheyden of Littler, Mendelson,
Fastiff, Tichy & Mathiason. Having considered the papers
submitted and the applicable law, the Court now finds
the applicable statute of limitations has lapsed, and grants
summary judgment in favor of defendants Ferbar and
Barnes. :
BACKGROUND
I. Factual Background and Procedural History
Plaintiffs bring this action under 29 U.S.C. §§ 1381-
1461, ERISA’s Multi-Employer Pension Plan Amend-
ments Act. It is defendants’ position that they were not
obligated under a collective bargaining agreement to con-
tribute to an employee trust fund. For purposes of this
7a
summary adjudication, however, defendants acknowledge
making contributions for several years to a Fund for the
benefit of three business locations—Superior French
-Laundry, One Hour Martinizing and Diablo Cleaners.
These contributions were discontinued to Diablo Cleaners
in February of 1983, at which time Ferbar no longer
owned Diablo Cleaners. Defendants’ Mot. for Sum.
J. at 2.
In March of 1985, Ferbar ceased altogether to make
contributions to the remaining locations, following sub-
mission of a petition by a majority of the employees work-
ing at Superior French Laundry and One Hour Martiniz-
ing which indicated they no longer wanted union repre-
sentation. Plaintiffs’ Opp’n Mot. at 2; Defendants’ Mot.
for Sum. J. at 2.
On December 12, 1986, plaintiffs sent a notice to Su-
perior French Laundry, asserting a withdrawal liability
obligation of $45,580.80. Plaintiffs’ Opp’n Mot. at 2.
That notice provided that Superior French would be able
to satisfy this debt in one of two ways: Superior French
could (1) make a single lump-sum payment of the total
withdrawal liability no later than sixty days after the
demand; or (2) begin making installment payments of
withdrawal liability pursuant to a schedule set forth by
the Trust Fund, with the first monthly payment due on
February |, 1987. Plaintiffs’ Opp’n Mot. at 2.
Defendants since then have made no payments on the
withdrawal liability. On February 27, 1987, Ferbar re-
quested a review of the plaintiffs’ assessment. Plaintiffs’
Opp’n Mot. at 2. By letter dated April 14, 1987, the
Fund notified Ferbar it was delinquent, and that Ferbar
had sixty days from the date of notice to cure the de-
linquency, or it would be considered in default. /d. Plain-
tiffs filed this lawsuit on February 9, 1993.
Il. Legal Standard
The Federal Rules of Civil Procedure provide for sum-
mary adjudication where “the pleadings, depositions, an-
swers to interrogatories, and admissions on file, together
with the affidavits, if any, show that there is no genuine
issue as to any material fact and that the party is entitled
to a judgment as a matter of law.” Fed. R. Civ. P. 56(e).
In a motion for summary judgment, “[i]f the party
moving for summary judgment meets its initial burden of
identifying for the court those portions of the materials
on file that it believes demonstrate the absence of any
genuine issues of material fact,” the burden of production
then shifts so that “the nonmoving party must set forth,
by affidavit or as otherwise provided in Rule 56, ‘specific
facts showing that there is a genuine issue for trial.’ ”
T.W. Electric Service, Inc. v. Pacific Elec. Contractors
Ass'n, 809 F.2d 626, 630 (9th Cir. 1987) (citing Celotex
Corp. v. Catrett, 106 §. Ct. 2548, 2553 (1983)).
In contrast to a plaintiff's motion for summary judg-
ment, a defendant's motion for summary judgment faces
a lighter burden. Because the defendant does not bear
the burden of proof at trial, the defendant need only
point to the insufficiency of the plaintiff's evidence to shift
the burden to the plaintiff to raise genuine issues of fact
as to each claim by substantial evidence. T.W. Electric
at 630, citing Celotex at 2553. If plaintiff fails to raise
a genuine issue of fact, then summary adjudication in
favor of the defendant will be granted.
DISCUSSION
The Court’s decision in this matter depends on an in-
terpretation of 29 U.S.C. § 1451, that portion of the
Multi-Employer Pension Plan Amendment Act defining
the relevant statute of limitations. That section provides:
(f) An action under this section may not be brought
after the later of —
9a
(1) 6 years after the date on which the cause
of action arose, or
(2) 3 years after the earliest date on which the
plaintiff acquired or should have acquired actual
knowledge of the existence of such cause of
action; except that in the case of fraud or con-
cealment, such action may be brought not later
than 6 vears after the date Of discovery of the
existence of such cause of action.
A. The Applicability of 29 U.S.C. § 1451(f)(2)'s Three-
Year Statute of Limitations
Defendants argue that the shorter of the two statutes
of limitations applies—and acts as a bar—to the present
action. This shorter, three year statute of limitations, see
§ 1451(f)(2), applies to instances in which the plaintiff
has actual or constructive knowledge of the accrual of a
cause of action. Notwithstanding the scarcity of case law
invoking § 1451(f)(2) with respect to cases involving
withdrawal liability, it is the conclusion of the Court that
this section applies in the present instance.
It is a canon of statutory construction that, where pos-
sible, a statute be interpreted to give effect to all its com-
ponent parts. Reiter v. Sonotone Corp., 99 S. Ct. 2326,
2331 (1979). To give such meaning to § 1451(f), a
three-year statute is interposed in those instances where
a plaintiff does or should know of the existence of a cause
of action, except in instances of fraud or concealment.
The immediate problem with plaintiffs’ attempt to ap-
ply a six year statute to all aspects of the present action
is reflected in their assertion that the six year statute is
triggered only after their knowledge of defendants’ de-
fault. Specifically, plaintiffs argue that the statute cannot
be found to run until defendants failed to make payment_
following sixty days after they received notice of the de-
linquency. Plaintiffs’ Opp’n at 8. On its face, this argu-
ment twists the very premises of § 1451(f) by combining
10a _
the six year provision of § 1451(f)(1) with the knowl-
edge component of § 1451(f)(2). The argument is, ac-
cordingly, flawed since the six year statute cannot corre-
spond to instances in which such knowledge is conceded.
Plaintiffs attempt variously to justify their assertion of
the inapplicability of the three year statute of limitations
to the present case. Initially, plaintiffs argue § 1451(f) (2)
can be given effect since the section applies to other cases
not involving withdrawal liability. Such application, ac-
cording to plaintiffs, proves that the three year statute is
not rendered meaningless since it would continue to apply
to other causes of action under Subtitle E of Title IV
of ERISA, e.g. reorganizations, mergers, transfers of as-
sets, insolvency and termination. See Plaintiffs’ Sup. Mot.
at 10-11; see also Joyce v. Clyde Sandoz Masonry, 871
F.2d 1119, 1125 (D.C. Cir.), cert. denied, 110 S. Ct. 280
(1989). “The fact that one prong of the general statute
of limitations contained at 29 U.S.C. § 1451(f) may not
have applicability to one particular provision in the sub-
title does not mean that it is surplusage with respect to all
other provisions.” /d.
Plaintiffs further argue that “the ‘discovery’ prong of the
limitations period can also apply directly to some aspects
of collection of withdrawal liability.” Plaintiffs’ Sup. Mot.
at 11. For example, plaintiffs argue that § 1451(f)(2) is
given effect in instances where an employer's inability to
make further payments of withdrawal liability constitutes
a default under Plan regulations allowing acceleration of
withdrawal liability. /d.; see also Joyce, 871 F.2d at 1125.
These arguments are unavailing, for the reason that
plaintiffs have elicited no statutory or case law, nor any
indicia of Congressional intent, supporting such a reading.
While plaintiffs have presented the Court with scenarios in
which the three year statute might alternatively be applied,
and therefore given meaning, plaintiffs have neglected to
proffer any sufficient reasons why § 1451(f)(2) should
lla
be so limited. In the absence of such support, the Court
must assume that Congress meant what it said in deeming
the three year statute in § 1451(f)(2) applicable to all of
Subtitle E of Title IV of ERISA. See § 1451(a)(1).
The three year statute of § 1451(f)(2) thus applies to
the present action. As plaintiffs knew a cause of action
existed no later than 1987, see Defendants’ Sup. Mot. at
4 n.1, 5, yet filed their complaint in excess of three years
of that time, the present action is barred by the applicable
statute of limitations.
B. Even Were the Six Year Statute of Limitations
Deemed Applicable, the Present Case Would Still be
Barred Since the Statute Begins Running at the Date
of the First Omitted Payment
Applying the six year statute of limitations urged by
plaintiffs would not, in any event, affect the Court’s con-
clusion that the present action is statutorily time-barred.
In making the argument, whether primarily or alterna-
tively, that the six year statute applies, the point of dispute
among the parties centers upon the date the statue is
deemed triggered. Defendants argue the statute begins to
run from the moment an employer withdraws from a fund;
plaintiffs argue the statute begins to run once an employer
misses on contribution payments and then fails to cure
that failure following receipt of notice of default.
It is the conclusion of this Court that the answer falls
between these two suggestions. Although the Ninth Circuit
has not answered the question, the running of the six-
year statute is appropriately found to begin at the date
that an employer first fails to make a payment pursuant
to the governing schedule.
This outcome follows a sensible application of the stat-
ute, and the direction of applicable case law. Title 29
U.S.C. § 1399(c)(2) provides:
12a
Withdrawal liability shall be payable in accordance
with the schedule set forth by the pian’s sponsor under
subsection (b)(1) of this section beginning no later
than 60 days after the date of demand notwithstand-
ing any request for review or appeal of determinations
of the amount of such liability or of the schedule.
Here, plaintiffs had set forth a schedule under which
payment was due, at the latest, February 1, 1987. Though
defendants failed to meet that schedule, plaintiffs argue
such non-payment alone cannot give rise to a cause of
action, since the non-payment could subsequently have
been cured.’ It is the opinion of the Court, however, that
there has been sufficient adverse action at the very moment
a payment becomes overdue to trigger the statute of
limitations.
The applicable PBGC regulations distinguish between
the term “overdue” and the term “default.” Title 29
C.F.R. § 2644.2(a) provides that withdrawal liability is
“overdue” if unpaid at the date set forth in the applicable
schedule. “Default,” by contrast, is defined as occurring
sixty days after the employer receives written notification
from the plan’s sponsor that the payment is overdue. See
29 C.F.R. § 2544.2(b)(i). It is when a payment is
overdue, and not in default, that a cognizable injury occurs
which triggers the statute of limitations.
The facts of the present case well illustrate that, upon
the first payment becoming overdue, there was adverse
action. In their December 12, 1986 letter to defendants,
plaintiffs wrote that defendants would be incurring inter-
? Plaintiffs also argue that “the Plan must allow a minimum of
sixty days after the date of the demand for the employer to com-
mence making installment payments of withdrawal liability under
29 U.S.C. § 1399(c) (2).” Plaintiffs’ Sup. Mot. at 4-5. Plaintiffs
concede the absence of any supporting case law for this position.
Further, § 1399 merely provides that “[w]ithdrawal liability shall
be payable . . . no later than 60 days after the date of demand... .”
29 U.S.C. § 1399(c) (2) (emphasis added).
13a
est charges if they failed to timely make the first monthly
payment. See Defendants’ Sup. Mot. at 8-9. Further,
the letter stated that defendants might “incur liability for
liquidated damages and other sums assessed in other delin-
quency provisions of the Plan’s Trust agreement; and your
obligation may be subject to such additional steps as the
Trustees may require in accordance with the law.” /d. at
9: Barnes Decl. at Exh. A. Thus, plaintiffs were adversely
affected when the first monthly payment was not made by
the February 1 date. At that time, then, plaintiffs’ cause
of action arose and, concomitantly, the statute of limita-
tions began running.
This holding is in accord with the holdings of those
decisions involving the issue in question. In Joyce, supra,
the District of Columbia Circuit held that a cause of action
arose not on the date of the employer’s withdrawal from a
fund, but from the time a plan demanded payment and
the employer refused to comply with the demand.
When, and only when, the employer fails to meet that
demanded schedule of payments (and fails to cure
that failure) has the plan been harmed (and thus
becomes entitled to maintain its claim against the
employer ).
871 F.2d at 1124. See also ILGWU National Retirement
Fund v. Smart Modes of Calif., Inc., 735 F. Supp. 103
(S.D.N.Y. 1990) (characterizing Joyce as a “well-reasoned
and thorough opinion”). Similarly, in Chicago Truck
Drivers Pension Fund v. Van Vorst Indus., 800 F. Supp.
587 (N.D. Ill. 1992), aff'd, Central States, Southeast &
Southwest Areas Pension Fund v. Navco, 3 F.3d 167 (7th
Cir. 1993), the court concluded that the claim accrued
at the time the first payment was due. Numerous unpub-
lished opinions are also in accord. See Debreceni v. West-
fair Transport Corp., 1988 U.S. Dist. LEXIS 9527 (D.
Mass. 1988); Central States, Southeast & Southwest Areas
l4a
Pension Fund v. Cherry Branch Properties, 1991 U.S. Dist.
LEXIS 14350 (N.D. Ill. 1991).*
Plaintiffs argue the accrual of a cause of action cannot
be designated as the date of the first missed payment,
since such a decision would “create serious impediments
va because of minor delinquencies during the administra-
tive process.” Plaintiffs’ Sup. Mot. at 8. Plaintiffs pose
the specter of an employer who misses his first installment
payment, then timely pays installments for the next six
years, and thereafter stops all further payments. See id.
Plaintiffs argue that if the first missed payment triggers
the statute of limitations, then the fund would be barred
from attempting to collect the succeeding, owed payments.
This concern is unfounded, however. While the first,
missed payment in the hypothetical would be time-barred,
a new cause of action would have arisen from the time
the payments were stopped.
. The parties suggest the Court adopt other alternatives
in determining the appropriate trigger for withdrawal lia-
bility. The breadth of these proffered solutions stems
largely from a dictum in a Ninth Circuit opinion, which
inaccurately depicts the degree of difference among courts
addressing the very question now considered. In Brent-
wood Financial v. Teamsters Pension Trust Fund, 902
F.2d 1456 (9th Cir. 1990) (declining to adopt a theory
when the statute of limitations was triggered for with-
drawal liability actions), the Court wrote:
Although this court has not considered the question
of when the six-year statute of limitations begins to
run, other courts have addressed and split on this
issue. The Seventh Circuit concluded that the limita-
tions period begins to run when a ‘complete with-
* Few decisions appear to hold to the contrary. But see, €.9.,
Connors v. Peles, 724 F. Supp. 1588, 1578-79 (W.D. Pa. 1989)
(finding, without analysis, that “Plaintiffs’ cause of action accrued
on... the date at which [defendant] no longer became obligated
to contribute to the Pension Fund.”).
15a
drawal’ occurs. See Trustees of Ironworkers Local
473 Pension Trust v. Allied Products Corp., 872
F.2d 208, 213 (7th Cir.), cert. denied, 110 S.Ct.
143 (1989). The District of Columbia Circuit held,
however, that the limitation period begins to run
from the time the employer first fails to make the
withdrawal payment demanded by the Plan. See
Joyce v. Clyde Sandoz Masonry, 871 F.2d 1119,
1122 (D.C.Cir.), cert. denied, 110 S. Ct. 280
(1989).
Defendants wield this language in arguing that the
statute of limitations began running when defendants
withdrew from the Fund. Plaintiffs, however, argue cor-
rectly that the Ninth Circuit wrongly framed the issue by
inaccurately citing a Seventh Circuit case for the proposi-
tion that the limitations period begins to run when a
“complete withdrawal” occurs. Plaintiffs’ Opp’n Mot. at
7. That referenced opinion, /ron Workers, supra, does
not once cite section 1451(f) or contain any discussion
of a statute of limitations; instead, the opinion examines
an employer’s date of withdrawal from a fund only in
order to ascertain the amount of withdrawal liability in-
curred. Cf. Cherry Branch Properties, supra, 1991 U.S.
Dist. LEXIS 14350 (unpublished) (“Jronworkers . . .
does not confront the issue. . . . Thus we find the Ninth
Circuit’s recent discussion of the two cases unenlightening
[since] its recitation of the Seventh Circuit’s conclusion
.. . is flatly wrong.”). Other than the unelaborated asser-
tion “that how the Ninth Circuit reads Ironworkers Local
473 Pension Trust controls the parties in the instant case”,
Reply at 2, defendants do not defend the accuracy of the
Ninth Circuit’s characterization of Jron Workers.
Apart from the lack of supporting case law, it is clear
that the date of withdrawal would be an inappropriate
point at which to begin the running of the statute of limi-
tations for withdrawal liability cases. Defendants argue
that “{if] the statute of limitations is not deemed to run
l6a
from the time of withdrawal. . ., there is no incentive for
a trust fund to make its calculations and attempt to ob-
tain payment. It could take as long as it wants to impose
the liability if the period of limitations does not begin to
run until the imposition is made and the payment not
made .. . and a company that withdrew may be hit with
withdrawal liability many years after withdrawal and after
relying on the fact that it owed no withdrawal liability as
it never heard from the trust fund.” Defendants’ Sup.
Mot. at 6.
This argument is unpersuasive. Most important, de-
fendants have failed to cite any evidence that Congress
actually intended that the statute of limitations would
be triggered at the moment of withdrawal. Further, de-
fendants’ recitation of the evil effects which would ensue
from setting the trigger date after the time of withdrawal
is suspect, as there is not an incentive for a trustee to
postpone making a claim of withdrawal liability. To the
contrary, it is a trustee’s statutory duty to timely protect
the interests of the Plan. See § 1399(b)(1) (providing
that a fund, [a]s soon as practicable after an employer's
complete . . . withdrawal” (1) calculate the employer's
withdrawal liability, (2) set forth a schedule of payments,
and (3) demand that the employer make payments pur-
suant to that schedule). Moreover, there is obvious risk
involved in the event a trustee delays collection, and nec-
essary cost incurred by collecting later rather than sooner.
Finally, to the extent an employer is concerned about
determining the existence or extent of future withdrawal
liability, then that employer may at his own behest make
such inquiry at the onset of his withdrawal. Defendants’
concerns are thus unfounded that, if the statute is not
triggered at the moment of withdrawal, a trustee will delay
collection of payment in order to extend the statute of
limitations.
Plaintiffs’ argument as to when the statute of limitations
should be deemed triggered is similarly unpersuasive.
Plaintiffs suggest that failure to make the payment triggers
17a
liability only with respect to interest charges, but that no
default can occur until an employer fails to make pay-
ment and, after receiving notice of the delinquency, fails
to cure that delinquency within a specified period of time.
Pleintiffs’ Opp’n at 8. As applied to the present case,
plaintiffs argue that a cause of action by a fund to collect
withdrawal liability does not begin until (1) the fund has
assessed liability against the employer; (2) the employer
has failed to make a payment due on the schedule; and
(3) the employer has failed to cure its delinquency within
60 days after notice by the fund. /d. Under this theory,
since plaintiffs did not give notice to defendant of its
delinquency until a letter dated April 14, 1987, defend-
ants still had 60 days from that date to cure their failure
to pay, thereby placing the expiration date of the statute
of limitations on June 14 1993. Plaintiffs’ Opp’n at 1.
Plaintiffs argue that “the text of the Assessment plainly
states, even though the monthly payments are to begin on
February 1, failure to make the payment triggers liability
for interest charges, but no ‘default’ can occur until the
Defendants fail to make payment following 60 days after
receiving notice of the delinquency.” Plaintiffs’ Opp’n at
8.
Plaintiffs’ interpretation is unavailing for various rea-
sons. First, it is unsupported by case law. Plaintiffs latch
on to language in Joyce that “[the] uncured failure to
pay the sum demanded [gives] rise to the cause of action.”
871 F.2d at 1122 (emphasis added). There, however, the
District of Columbia Circuit continued that “the plan
sponsor’s demand for payment triggers the employer's
obligation to pay, and the employer’s failure to make the
scheduled payment in turn provides the predicate for a
plan sponsor’s suit. That is to say, the failure to pay
gives rise to a cause of action.” /d. at 1122-23. Most
significantly, the holding of that case does not postpone
the trigger for the statute of limitations in the manner
sought by plaintiffs.
18a
Similarly, Navco, supra, is also unsupportive of plain-
tiffs’ position. Plaintiffs cite the language of Navco that
“[aJs soon as the 60-day grace period provided by
§ 1399(c)(2) expired, the funds could have commenced
suit. They had been injured. That is the standard defini-
-tion of the ‘accrual’ of a claim.” 3 F.3d at 171. The
Court continued, however, that “the claim accrues as soon
as payment becomes overdue.” /d. at 172. Moreover,
there, too, the court did not in its holding expressly post-
pone the triggering of the statute of limitations.
No case has been cited to the Court in which a court
held the staute of limitations of § 1451(f) was tolled
until after default and subsequent expiration of a desig-
nated time period. This absence is understandable, since
the predictability sought by implementation of a statute of
limitation would be undercut by such an interpretation.
Allowing the grace period suggested would enable an
injured fund to toll a statute of limitations by virtue -of
having neglected to formally notify an employer of a
forthcoming default, though an owing payment was al-
ready overdue. The absence of case law supporting plain-
tiffs’ position is also understandable since, whether set
_ at three or six years, the governing statute of limitations
is a lengthy one, for which resort to extenuating methods-
of tolling has proved seldom necessary.
In conclusion, then, even were the six year statute to
apply, the present action would be barred. Defendants
were obligated—and failed—to make the first required
withdrawal liability payment on February 1, 1987, a date
preceding the filing of the lawsuit by more than six years.
See Defendants’ Mot. for Sum. J. at 7; Plaintiffs’ Opp’n
at 8. Accordingly, the present action is time-barred, and
summary judgment is appropriately granted in favor of
defendant Ferbar Corporation and defendant Stephen
Barnes.
CONCLUSION
For the foregoing reasons, the Court Orders as follows:
The motion for summary judgment submitted on behalf
19a
of defendants Ferbar Corporation and Stephen Barnes is
GRANTED. Partial judgment shall be entered accord-
ingly. A status conference shali occur among the re-
maining parties to this action on May 25, 1994 at 8:30
a.m.; all other dates currently scheduled are hereby
vacated.
IT IS SO ORDERED.
Dated: May 9, 1994.
/s/ D. Lowell Jensen
D. LOWELL JENSEN
United States District Judge
20a
APPENDIX C
NOT FOR PUBLICATION
[Filed May 13, 1996]
UNITED STATES COURT OF APPEALS
FOR THE NINTH CIRCUIT
No. 94-15976
D.C. No. CV-93-00489-DLJ
Bay AREA LAUNDRY & Dry CLEANING PENSION
Trust FunD,
Plaintiff-A ppellant,
Vv.
FERBAR CORPORATION OF CALIFORNIA, INC., a California
Corporation; FERREIRA Farms, INc., a California
corporation; STEPHEN J. Barnes, end Rosert J.
FERREIRA Defendants-A ppellees.
ORDER
Before: NORRIS, BEEZER, and TROTT, Circuit Judges
The panel, as constituted above, has voted unanimously
to deny the petition for rehearing. Judges Beezer and
Trott have voted to reject the suggestion for a rehearing
en banc, and Judge Norris has recommended the same.
The full court has been advised of the suggestion for
en banc rehearing and no judge of the court has requested
a vote on the suggestion for rehearing en banc. Fed. R.
App. P. 35(b).
The petition for rehearing is DENIED, and the sugges-
tion for a rehearing en banc is REJECTED.
2la
APPENDIX D
UNITED STATES COURT OF APPEALS
NINTH CIRCUIT
Nos. 93-55079, 93-55080
BOARD OF TRUSTEES OF THE CONSTRUCTION LABORERS
PENSION TRUST FOR SOUTHERN CALIFORNIA,
Plaintiff-Appellant,
Vv.
RuSSELL L. TurBpopo; Gary R. THiBopo;
THIBODO CONSTRUCTION Co. INC.;
DRAINAGE CONSTRUCTION Co.,
Defendants-A ppellees.
BOARD OF TRUSTEES OF THE CONSTRUCTION LABORERS
PENSION TRUST FOR SOUTHERN CALIFORNIA,
Plaintiff-A ppellant-A ppellee,
Vv.
RUSSELL L. THIBODO; THIBODO CONSTRUCTION Co. INC.,
Defendants-A ppellees-A ppellants.
Appeals from the United States District Court
for the Central District of California
Argued and Submitted June 8, 1994
Decided Sept. 12, 1994
Before: FLETCHER, CANBY and HALL, Circuit
Judges.
CANBY, Circuit Judge:
The Board of Trustees of the Construction Laborers’
Pension Trust for Southern California appeals the district
22a
court’s dismissal of this action in which the Trustees
sought to enforce an arbitration award. The arbitrator
had determined that Russell Thibodo was personally liable
to the Trust for ERISA withdrawal liability incurred as a
result of his construction company’s complete withdrawal
from the Construction Laborers Pension Plan in 1983.
The district court, however, held that the Trustees’ action
was barred by ERISA’s six-year statute of limitations.
We reverse and remand to the district court.’
STATUTORY BACKGROUND
ERISA, as modified by the Multiemployer Pension
Plan Amendments Act of 1980 (MPPAA), is designed to
ensure the financial integrity of multiemployer pension
funds. See generally Joyce v. Clyde Sandoz Masonry, 871
F.2d 1119 (D.C.Cir.), cert. denied, 493 U.S. 918, 110
S.Ct. 280, 107 L.Ed.2d 260 (1989) One mechanism for
attaining this goal is the Act’s requirement that employers
who withdraw from multiemployer plans remain liable
for a statutory share of the plan’s “unfunded vested bene-
fits.” See 29 U.S.C. $§ 1381, 1399; Joyce, 871 F.2d at
1120.
Much of the confusion surrounding this case is due to
the fact that, at least with regard to the construction in-
dustry, when “complete withdrawal” occurs is determined
differently under two different sections. The first deter-
mination under 29 U.S.C. § 1383(b)(2) is for the
purpose of establishing whether the employer has, in
fact, withdrawn and liability for continuing contribu-
tions has ended. The second determination is for the
purpose of establishing the amount of withdrawal lia-
bility. The former determination is made under sections
1383(b)(2)(A) and (B). An employer is deemed to
have completely withdrawn from the plan if:
1 Thibodo cross-appeals the district court’s denial of his motion
for attorneys’ fees. In light of our disposition, we dismiss the
cross-appeal as moot.
23a
(A) [the] employer ceases to have an obligation to
contribute under the plan, and
(B) the employer—
(i) continues to perform work in the jurisdic-
tion of the collective bargaining agreement of
the type for which contributions were previously
required, or
(ii) resumes such work within 5 years after the
date on which the obligation to contribute under
the plan ceases, and does not renew the obliga-
tion at the time of the resumption,
29 U.S.C. §§ 1383(b)(2)(A), (B). It may readily be
seen that conditions (A) and (B) may not be met for
up to 5 years after an employer’s duty to make regular
contributions to the fund has ceased, Indeed, as we will
see, the employer in the present case did not effectuate
“complete withdrawal” until two years after it ceased
contributions to the plan.
Different statutory provisions, however, determine the
“date of complete withdrawal” for purposes of calculating
the amount of withdrawal liability. For that purpose, the
date of “complete withdrawal” is deemed to be the “date
of the cessation of the obligation to contribute.” 29
U.S.C. § 1383(e). This date, or, more accurately, the
year in which this date falls, is instrumental in determin-
ing the amount of the employer’s withdrawal liability. See
29 U.S.C. § 1391(b)(2) (amount of unfunded vested
benefits that existed on the last date of the plan year pre-
ceding the year in which the employer withdrew is the
amount for which the employer owes a contribution).
Civil actions to collect unpaid withdrawal liability
amounts may not be brought after the later off: (1) six
years after the date on which the cause of action arose;
or (2) three years after the earliest date on which the
plaintiff acquired or should have acquired actual knowl-
edge of the existence of such cause of action, with one
—
24a
exception not relevant to this case. See 29 U.S.C.
§ 1451(f).
FACTUAL BACKGROUND
The Trust is the plan sponsor for the Construction
Laborers Pension Plan (the Plan). Thibodo Construc-
tion Co., Inc. contributed to the Plan pursuant to its col-
lective bargaining agreement (CBA) with the Laborers
Union until June 15, 1983, the date upon which the CBA
expired. In early 1984, the Trustees believed that the
company had withdrawn from the Plan and therefore
owed withdrawal liability as provided in ERISA under
the MPPAA. They sent the company an assessment notif-
ication and payment schedule. The company disputed the
assessment, however, and in July 1984 the Trustees
agreed that the assessment was erroneous because the
company had not employed any laborers since the ex-
piration of its CBA with the union. See 29 U.S.C.
§ 1383(b)(2)(B). The Trustees warned, however, that
the company would owe withdrawal liability if it resumed
hiring laborers.
In the Spring of 1985, the company resumed hiring
laborers to perform work within the jurisdiction of the
Plan. When the Trustees became aware of this resump-
tion, they reinstated the company’s withdrawal liability
assessment, but the company made no payments to the
Plan in response to the assessment. Nothing more tran-
spired until April 1986, when the Trustees notified the
company that it must begin making payments on the as-
sessment within 60 days. Having received no payments
from the company, the Trustees initiated this lawsuit in
the district court on June 20, 1989, six years and five
days after the expiration of the company’s CBA.
The district court agreed to stay its proceedings so that
the parties could submit the following issues for arbitra-
tion: (1) whether the company had completely with-
drawn from the plan in 1983; and (2) whether Thibodo,
25a
the company’s sole shareholder, was personally and indi-
vidually liable for the company’s withdrawal liability.
The arbitrator concluded that the company had with-
drawn from the plan on June 15, 1983,” and that Thibodo
was personally liable for the company’s withdrawal
liability.*
After the arbitrator’s decision, the Trustees moved the
district court to enforce the arbitration award. In opposi-
tion, Thibodo asserted that the Trustees’ district court
action had been filed beyond the limitations period pro-
vided in ERISA. The district court agreed with Thibodo
and dismissed the action.
DISCUSSION
We must decide when the statute of limitations begins
to run for actions to recover withdrawal liability payments
under ERISA and the MPPAA. We hold that, for actions
to recover withdrawal liability incurred as a result of com-
2 The Trustees dispute this determination by arguing that Thibodo
had a legal obligation to continue payments to the plan for a short
time beyond the CBA’s expiration on June 15, 1983. See 29 U.S.C.
§ 1383(e) (date of complete withdrawal is the date that the em-
ployer ceased to have an obligation to contribute to the plan).
Thus, they argue, the “date of complete withdrawal” was later
than June 20, 1983. If this argument were accepted, then the
Trustees’ action would be timely regardless of whether the limita-
tions period began to run on the “date of complete withdrawal”
as defined in § 1383 (e).
We need not address the question of when Thibodo’s obligation
to contribute ceased because we conclude that the limitations period
does not run from the date of complete withdrawal as defined in
§ 1383(e). For the same reason we need not address the parties’
contentions pertaining to: (1) whether the arbitrator improperly
decided an issue not before it when it determined an exact date
on which Thibodo withdrew; and (2) whether the district court
should have deferred to the arbitrator’s determination of the date
of complete withdrawal.
We express no opinion regarding the correctness of this
determination.
26a
plete withdrawal under 29 U.S.C. § 1383(b), the limita-
tions period begins to run from the date that the conditions
for withdrawal specified under that section are met. In this
case, that date fell sometime in the Spring of 1985, when
the company resumed work of the type for which contribu-
tions were previously requirea.
The district court concluded that the limitations period
begai running on June 15, 1983, which the arbitrator
determined to be the “date of complete withdrawal” as de-
fined in § 1383(e).* We repudiate that conclusion be-
cause, under the district court’s approach, the limitations
period was running against the Trustees before they ac-
quired a cause of action against Thibodo. For purposes of
limitations, Thibodo’s complete withdrawal from the Plan
occurred in the Spring of 1985 when his company resumed
employing laborers, because only then were the statutory
conditions for complete withdrawal met. 29 U.S.C.
§ 1383(b)(2). Before that time, the Trustees had no
right to assess or receive withdrawal liability payments
from Thibodo. Indeed, the Trustees realized as much in
1984 when they withdrew their original assessment. It is
anomalous to conclude that the limitations period of
§ 1451(f) was running against the Trustees before they
had a right to sue.
For the purpose of calculating the amount of withdrawal
liability under § 1391, it is useful to fix the “date of com-
*We note that Thibodo has been unable to cite to any federal
court opinion in which this approach has been adopted. His asser-
tion that the Seventh Circuit adopted this approach in Trustees of
Iron Workers Local 473 Pension Trust v. Allied Prods. Corp., 872
F.2d 208 (7th Cir.), cert. denied, 493 U.S. 847, 110 S.Ct. 143, 107
L.Ed.2d 102 (1989), is erroneous. That case says nothing about
when the limitations period for withdrawal liability actions begins
to run. Our statement to the contrary in Brentwood Financial
Corp. v. Western Conference of Teamsters Pension Trust Fund,
902 F.2d 1456, 1459 (9th Cir.1990), was incorrect. See Central
States, Southeast and Southwest Areas Pension Fund v. Navco,
3 F.3d 167, 170-71 (7th Cir.1998), cert. denied —— US. ——,
114 S.Ct. 1062, 127 L.Ed.2d 382 (1994).
27a
plete withdrawal” as the date when the duty of regular
contribution ceased. See 29 U.S.C. § 1383(e); Joyce,
871 F.2d at 1123. But in the case of a withdrawal in the
construction industry, selection of such a date may involve
a considerable period of relation back, as it does in the
present case. The fact that it is useful to relate back for
purposes of calculation of liability, however, does not
mean that it is useful to relate back for purposes of the
Statute of limitations. Limitations run from “the date on
which the cause of action arose.” 29 U.S.C. § 1451(f)(1).
We conclude, therefore, that the limitations period of
§ 1451(f) begins to run from the date on which the condi-
tions for complete withdrawal specified in § 1383(b)(2)
have been met—in this case, the Spring of 1985. Be-
cause the Trustees’ action was initiated within six years
of the Company’s resumption of covered work, their action
is timely and the district court erred in dismissing it.
We recognize that our approach differs from that taken
by the D.C. Circuit. In Joyce, that Circuit concluded that
the limitations period does not begin to run until the plan
makes a demand upon the employer for withdrawal liabil-
ity payments and the employer refuses that demand.’
Joyce, 871 F.2d at 1124; see also ILGWU Nat'l Retire-
ment Fund v. Smart Modes of Cal., Inc., 735 F.Supp.
103, 106 (S.D.N.Y.1990) (adopting Joyce approach in
§ 1383(a) withdrawal liability action). In our view, that
approach improperly places the running of the limitations
period in the control of the plaintiff.
In deciding that the limitations period does not begin to
run until a demand for payments goes unmet, the District
of Columbia Circuit was influenced by the difficulty of
determining when an employer had “permanently” ceased
to have an obligation to contribute or “permanently”
5 The District of Columbia Circuit’s approach would not aid
Thibodo, of course, because it selects a date even later than the
one we choose.
28a
ceased all covered operations, within the meaning of
§ 1383(a). Joyce, 871 F.2d at 4123-24. Whatever the
difficulties might be under that subsection, we conclude
that the construction industry provisions of § 1383(b) do
not lead to debilitating uncertainty concerning whether an
employer has completely withdrawn. Determining whether
an employer continues to perform work of the type for
which contributions were required, or resumes such work
within 5 years is relatively straightforward. See 29 U.S.C.
1383(b)(2)(B).° We see no reason, therefore, to choose
a date of limitations that is in the control of the plaintiff
and, theoretically at least, might not be triggered for many
years." We also consider our rule to involve a more nat-
ural construction of § 1451(f), which sets the limitation
as “6 years after the date on which the cause of action
arose, or 3 years after the earliest date on which the
plaintiff acquired or should have acquired knowledge of
the existence of such cause of action.” There is little
reason for the second clause if the cause of action does not
come into existence until demand for payment is made
and refused.
For these reasons, we decline to adopt the D.C. Circuit’s
approach—at least with respect to § 1383(b) withdraw-
als—and hold that for actions to collect withdrawal liabil-
ity incurred under 29 U.S.C. § 1383(b), the limitations
period found in 29 U.S.C. § 1451(f) begins to run on
the date that the statutory conditions for withdrawal are
© We do not decide whether the potential difficulties of determin-
ing when an employer has “permanently” ceased covered operations
under § 1383(a) warrants adoption of the D.C. Circuit’s approach
in suits seeking recovery of withdrawal liability incurred under
that section.
7 The District of Columbia Circuit opined that there were several
incentives for plan sponsors to act promptly in demanding payment
of withdrawal liability. Joyce, 871 F.2d at 1126-27. There may be,
but contro] still remains with the plaintiff.
29a
met. Because the Trustees brought this action well within
six years after that date, it is not time-barred.
No. 93-55079 REVERSED and REMANDED.
No. 93-55080 DISMISSED.
30a
APPENDIX E
STATUTES AND REGULATIONS INVOLVED
The Employee Retirement Income Security Act of 1974
(ERISA), as amended by the Multiemployer Pension
Plan Amendments Act of 1980 (MPPAA), provides in
relevant part as follows:
§ 1132. Civil enforcement
(a) Persons empowered to bring a civil action
A civil action may be brought—
(3) by a participant, beneficiary, or fiduciary
(A) to enjoin any act or practice which
violates any provision of this subchapter or
the terms of the plan, or
(B) to obtain other appropriate equitable
relief
(i) to redress such violations or
(ii) to enforce any provisions of this
subchapter or the terms of the plan;
(g) Attorney’s fees and costs; awards in actions in-
volving delinquent contributions
(1) In any action under this subchapter (other
than an action described in paragraph (2)) by
a participant, beneficiary, or fiduciary, the court
in its discretion may allow a reasonable attor-
ney’s fee and costs of action to either party.
(2) In any action under this subchapter by a
fiduciary for or on behalf of a plan to enforce
section 1145 of this title in which a judgment in
3la
favor of the plan is awarded, the court shall
award the plan—
(A) the unpaid contributions,
(B) interest on the unpaid contributions,
(C) an amount equal to the greater of—
(i) interest on the unpaid contribu-
tions, or
(ii) liquidated damages provided for
under the plan in an amount not in
excess of 20 percent (or such higher
percentage as may be permitted under
Federal or-State law) of the amount
determined by the court under sub-
paragraph (A),
(D) reasonable attorney's fees and costs of
the action, to be paid by the defendant, and
(E) such other legal or equitable relief as
the court deems appropriate. For purposes
of this paragraph, interest on unpaid con-
tributions shall be determined by using the
rate provided under the plan, or, if none,
the rate prescribed under section 6621 of
title 26.
§ 1381. Withdrawal liability established; criteria and
definitions
(a) If an employer withdraws from a multiem-
ployer plan in a complete withdrawal or a partial
withdrawal, then the employer is liable to the plan
in the amount determined under this part to be the
withdrawal liability.
32a
§ 1383. Complete withdrawal
(a)
Determinative factors
For purposes of this part, a complete withdrawal from
a multiemployer plan occurs when an employer—
(b)
(1) permanently ceases to have an obligation
to contribute under the plan, or
(2) permanently ceases all covered operations
under the plan.
Building and construction industry
(1) Notwithstanding subsection (a) of this sec-
tion, in the case of an employer that has an
obligation to contribute under a plan for work
performed in the building and construction in-
dustry, a complete withdrawal occurs only as
described in paragraph (2), if—
(A) substantially all the employees with
respect to whom the employer has an obli-
gation to contribute under the plan perform
work in the building and construction in-
dustry, and
(B) the plan—
(i) primarily covers employees in the
building and construction industry, or
(ii) is amended to provide that this
subsection applies to employers de-
scribed in this paragraph.
(2) A withdrawal occurs under this paragraph
if-—
(A) an employer ceases to have an obliga-
tion to contribute under the plan, and
(B) the employer—
33a
(i) continues to perform work in the
jurisdiction of the collective bargain-
ing agreement of the type for which
contributions were previously re-
quired, or
(ii) resumes such work within 5 years
after the date on which the obligation
to contribute under the plan ceases,
and does not renew the obligation at
the time of the resumption.
(3) In the case of a plan terminated by mass
withdrawal (within the meaning of section
1341a(a)(2) of this title), paragraph (2) shall
be applied by substituting “3 years” for “5
years” in subparagraph (B) (ii).
(c) Entertainment industry
(1) Notwithstanding subsection (a) of this sec-
tion, in the case of an employer that has an
obligation to contribute under a plan for work
performed in the entertainment industry, pri-
marily on a temporary or project-by-project
basis, if the plan primarily covers employees in
the entertainment industry, a complete with-
drawal occurs only as described in subsection
(b)(2) of this section applied by substituting
“plan” for “collective bargaining agreement” in
subparagraph (B) (i) thereof.
(2) For purposes of this subsection, the term
“entertainment industry” means—
(A) theater, motion picture (except to the
extent provided in regulations prescribed
by the corporation), radio, television,
sound or visual recording, music, and
dance, and
34a
(B) such other entertainment activities as
the corporation may determine to be ap-
propriate.
(3) The corporation may by regulation exclude
a group or class of employers described in the
preceding sentence from the application of this
subsection if the corporation determines that
such exclusion is necessary—
(A) to protect the interest of the plan’s
participants and beneficiaries, or
(B) to prevent a significant risk of loss to
the corporation with respect to the plan.
(4) A plan may be amended to provide that
this subsection shall not apply to a group or
class of employers under the plan.
(d) Other determinative factors
(1) Notwithstanding subsection (a) of this sec-
tion, in the case of an employer who—
(A) has an obligation to contribute under
a plan described in paragraph (2) primar-
ily for work described in such paragraph,
and
(B) does not continue to perform work
within the jurisdiction of the plan,
a complete withdrawal occurs only as de-
scribed in paragraph (3).
(2) A plan is described in this paragraph if
substantially all of the contributions required
under the plan are made by employers primar-
ily engaged in the long and short haul trucking
industry, the household goods moving industry,
or the public warehousing industry.
(3) A withdrawal occurs under this paragraph
if—
35a
(A) an employer permanently ceases to
have an obligation to contribute under the
plan or permanently ceases all covered
operations under the plan, and
(B) either—
(i) the corporation determines that
the plan has suffered substantial dam-
age to its contribution base as a re-
sult of such cessation, or
(ii) the employer fails to furnish a
bond issued by a corporate surety com-
pany that is an acceptable surety for
purposes of section 1112 of this title,
or an amount held in escrow by a
bank or similar financial institution
satisfactory to the plan, in an amount
equal to 50 percent of the withdrawal
liability of the employer.
(4) If, after an employer furnishes a bond or
escrow to a plan under paragraph (3)(B) (ii),
the corporation determines that the cessation of
the employer’s obligation to contribute under
the plan (considered together with any cessa-
tions by other employers), or cessation of cov-
ered operations under the plan, has resulted in
substantial damage to the contribution base of
the plan, the employer shall be treated as hav-
ing withdrawn from the plan on the date on
which the obligation to contribute or covered
operations ceased, and such bond or escrow shall
be paid to the plan. The corporation shall
not make a determination under this paragraph
more than 60 months after the date on which
such obligation to contribute or covered opera-
tions ceased.
(5) If the corporation determines that the em-
ployer has no further liability under the plan
either—
36a
(A) because it determines that the con-
tribution base of the plan has not suffered
substantial damage as a result of the ces-
sation of the employer’s obligation to con-
tribute or cessation of covered operations
(considered together with any cessation of
contribution obligation, or of covered op-
erations, with respect to other employers),
or
(B) because it may not make a determina-
tion under paragraph (4) because of the
last sentence thereof,
then the bond shall be cancelled or the escrow
refunded.
(6) Nothing in this subsection shall be con-
strued as a limitation on the amount of the
withdrawal liability of any employer.
(e) Date of complete withdrawal
For purposes of this part, the date of a complete
withdrawal is the date of the cessation of the obliga-
tion to contribute or the cessation of covered opera-
tions.
(f) Special liability withdrawal rules for industries
other than construction and entertainment industries;
procedures applicable to amend plans
(1) The corporation may prescribe regulations
under which plans in industries other than the
construction or entertainment industries may be
amended to provide for special withdrawal lia-
bility rules similar to the rules described in
subsections (b) and (c) of this section.
(2) Regulations under paragraph (1) shall per-
mit use of special withdrawal liability rules—
(A) only in industries (or portions there-
of) in which, as determined by the cor-
37a
poration, the characteristics that would
make use of such rules appropriate are
clearly shown, and
(B) only if the corporation determines, in
each instance in which special withdrawal
liability rules are permitted, that use of
such rules will not pose a significant risk to
the corporation under this subchapter.
§ 1391. Methods for computing withdrawal liability
(a) Determination of amount of unfunded vested
benefits allocable to employer withdrawn from plan
The amount of the unfunded vested benefits allocable
to an employer that withdraws from a plan shall be
determined in accordance with subsection (b), (c),
or (d) of this section.
(b) Factors determining computation of amount of
unfunded vested benefits allocable to employer with-
drawn from plan
(1) Except as provided in subsections (c) and
(d) of this section, the amount of unfunded
vested benefits allocable to an employer that
withdraws is the sum of—
(A) the employer’s proportional share of
the unamortized amount of the change in
the plan’s unfunded vested benefits for plan
years ending after September 25, 1980,
as determined under paragraph (2),
(B) the employer’s proportional share, if
any, of the unamortized amount of the
plan’s unfunded vested benefits at the end
of the plan year ending before September
ahi 1980, as determined under paragraph
(3); and
38a
(C) the employer’s proportional share of
the unamortized amounts of the reallocated
unfunded vested benefits (if any) as de-
termined under paragraph (4).
If the sums of the amounts determined with
respect to an employer under paragraphs (2),
(3), and (4) is negative, the unfunded vested
benefits allocable to the employer shall be zero.
(2)(A) An employer’s proportional share of
the unamortized amount of the change in the
plan’s unfunded vested benefits for plan years
ending after September 25, 1980, is the sum
of the employer’s proportional shares of the
unamortized amount of the cha-ge in unfunded
vested benefits for each plan year in which the
employer has an obligation to contribute under
the plan ending—
(i) after such date, and
(ii) before the plan year in which the with-
drawal of the employer occurs.
(B) The change in a plan’s unfunded vested
benefits for a plan year is the amount by
which—
(i) the unfunded vested benefits at the end
of the plan year; exceeds
(ii) the sum of—
(1) the unamortized amount of the
unfunded vested benefits for the last
plan year ending before September 26,
1980, a d
(Il) the sum of the unamortized
amounts of the change in unfunded
vested benefits for each plan year end-
ing after September 25, 1980, and
preceding the plan year for which the
change is determined.
39a
(C) The unamortized amount of the change in
a plan’s unfunded vested benefits with respect
to a plan year is the change in unfunded vested
benefits for the plan year, reduced by 5 percent
of such change for each succeeding plan year.
(D) The unamortized amount of the unfunded
vested benefits for the last plan year ending
before September 26, 1980, is the amount of
the unfunded vested benefits as of the end of
that plan year reduced by 5 percent of such
amount for each succeeding plan year.
(E) An employer’s proportional share of the
unamortized amount of a change in unfunded
vested benefits is the product of—
(i) the unamortized amount of such
change (as of the end of the plan year
preceding the plan year in which the em-
ployer withdraws); multiplied by
(ii) a fraction—
(1) the numerator of which is the sum
of the contributions required to be
made under the plan by the employer
for the year in which such change
arose and for the 4 preceding plan
years, and
(II) the denominator of which is the
sum for the plan year in which such
“change arose and the 4 preceding
plan years of all contributions made
by employers who had an obligation
to contribute under the plan for the
plan year in which such change arose
reduced by the contributions made in
such years by employers who had
40a
withdrawn from the plan in the year
in which the change arose.
(3) An employer’s proportional share of the
unamortized amount of the plan’s unfunded
vested benefits for the last plan year ending be-
fore September 26, 1980, is the product of —
(A) such unamortized amount; multiplied
by—
(B) a fraction—
(i) the numerator of which is the
sum of all contributions required to
be made by the employer under the
plan for the most recent 5 plan years
ending before September 26, 1980,
and
(ii) the denominator of which is the
sum of all contributions made for the
most recent 5 plan years ending be-
fore September 26, 1980, by all em-
ployers—
(I) who had an obligation to
contribute under the plan for the
first plan year ending on or after
such date, and
(II) who had not withdrawn
from the plan before such date.
(4)(A) An employer’s proportional share of
the unamortized amount of the reallocated un-
funded vested benefits is the sum of the em-
ployer’s proportional shares of the unamortized
amount of the reallocated unfunded vested ben-
efits for each plan year ending before the plan
year in which the employer withdrew from
the plan.
4la
(B) Except as otherwise provided in regula-
tions prescribed by the corporation, the reailo-
cated unfunded vested benefits for a plan year
is the sum of—
(i) any amount which the plan sponsor
determines in that plan year to be uncol-
lectible for reasons arising out of cases or
proceedings urder Title 11, or similar
proceedings.
(ii) any amount which the plan sponsor
determines in that plan year will not be
assessed as a result of the operation of sec-
tion 1389, 1399(c)(1)(B), or section
1405 of this title against an employer to
whom a notice described in section 1399
of this title has been sent, and
(iii) any amount which the plan sponsor
determines to be uncollectible or unassess-
able in that plan year for other reasons
under standards not inconsistent with regu-
lations prescribed by the corporation.
(C) The unamortized amount of the reallocated
unfunded vested benefits with respect to a plan
year is the reallocated unfunded vested benefits
for the plan year, reduced by 5 percent of such
réallocated unfunded vested benefits for each
succeeding plan year.
(D) An employer’s proportional share of the
unamortized amount of the reallocated unfunded
vested benefits with respect to a plan year ‘s
the product of— a
(i) the unamortized amount of the reallo-
cated unfunded vested benefits (as of the
end of the plan year preceding the plan
_
42a
year in which the employer withdraws);
multiplied by
(ii) the fraction defined in paragraph
(2) (E) (ii).
§ 1399. Notice, collection, etc., of withdrawal lia-
bility
(a) Furnishing of information by employer to plan
sponsor
An employer shall, within 30 days after a written
request from the plan sponsor, furnish such informa-
tion as the plan sponsor reasonably determines to be
necessary to enable the plan sponsor to comply with
the requirements of this part.
(b) Notification, demand for payment, and review
upon complete withdrawal by employer
(1) As soon as practicable after an employer's
complete or partial withdrawal, the plan sponsor
shall— :
(A) notify the employer of—
(i) the amount of the liability, and
(ii) the schedule for liability pay-
ments, and
(B) demand payment in accordance with
the schedule. Fi
(2)(A) No © ver than 90 days after the em-
ployer receives the notice described in paragraph
(1), the employer—
(i) may ask the plan sponsor to review
_any specific matter relating to the determi-
nation of the employer’s liability and the
schedule of payments,
(c)
43a
(ii) may identify any inaccuracy in the
determination of the amount of the un-
funded vested benefits allocable to the
employer, and
(iii) may furnish any additional relevant
information to the plan sponsor.
(B) After a reasonable review of any matter
raised, the plan sponsor shall notify the em-
ployer of—
(i) the plan sponsor’s decision,
(ii) the basis for the decision, and
. (ili) the reason for any change in the de-
termination of the employer’s liability or
schedule of liability payments.
Payment requirements; amount, etc.
(2) Withdrawal liability shall be payable in
accordance with the schedule set forth by the
plan sponsor under subsection (b)(1) of this
section beginning no later than 60 days after
the date of the demand notwithstanding any
request for review or appeal of determinations
of the amount of such liability or of the
schedule.
(3) Each annual payment determined under
paragraph (1)(C) shall be payable in 4 equal
installments due quarterly, or at other intervals
specified by plan rules. If a payment is not
made when due, interest on the payment shall
accrue from the due date until the date on
which the payment is made.
(4) The employer shall be entitled to prepay
the outstanding amount of the unpaid annual
withdrawal liability payments determined under
44a j
paragraph (1)(C), plus accrued interest, if any,
in whole or in part, without penalty... .
(5) In the event of a default, a plan sponsot
may require immediate payment of the out
standing amount of an employer’s withdrawal
liability, plus accrued interest on the total out
standing liability from the due date of the first
payment which was not timely made. For put
poses of this section, “default” means—
(A) the failure of an employer to make,
when due, any payment under this sectior,
if the failure is not cured within 60 days
after the employer receives written notifica-
tion from the plan sponsor of such failure,
and
(B) any other event defined in rules
adopted by the plan which indicates a sul
stantial likelihood that an employer will be
unable to pay its withdrawal liability.
§ 1401. Resolution of disputes
(a) Arbitration proceedings; matters subject to at
bitration, procedures applicable, etc.
(1) Any dispute between an employer and ‘he
plan sponsor of a multiemployer plan corcern-
ing a determination made under sections 1381
through 1399 of this title shall be resolved
through arbitration. Either party May mitiate
the ‘arbitration proceeding within a 60-day
period after the earlier of—
(A) the date of netification to the em-
ployer under section 1399(b)(2)(B) of
this title, or
(B) 120 days after the date of the
employer’ request under section
1399(b)(2)(A) of this title.
45a
The parties may jointly initiate arbitration
within the 180-day period after the date of the
plan sponsor’s demand under section 1399(b)
(1) of this title.
(b) Alternative collection proceedings; civil action
subsequent to arbitration award; conduct of arbitra-
iton proceedings
(1) If no arbitration proceeding has been ini-
tiated pursuant to subsection (a) of this section,
the amounts demanded by the plan sponsor
under section 1399(b)(1) of this title shall be
due and owing on the schedule set forth by the
plan sponsor. The plan sponsor may bring an
action in a State or Federal court of competent
jurisdiction for collection.
(d) Payments by employer prior to determination
by arbitrator; adjustments; failure of employer to
make payments
Payments shall be made by an employer in accord-
ance with the determinations made under this part
until the arbitrator issues a final decision with respect
to the determination submitted for arbitration, with
any necessary adjustments in subsequent payments
for overpayments or underpayments arising out of
the decision of the arbitrator with respect to the
determination. If the employer fails to make timely
payment in accordance with such final decision, the
employer shall be treated as being delinquent in the
making of a contribution required under the plan
(within the meaning of seciion 1145 of this title).
§ 1451. Civil actions
(a) Persons entitled to maintain actions
(1) A plan fiduciary, employer, plan partici-
pant, or beneficiary, who is adversely affected
46a
by the act or omission of any party under this
subtitle with respect to a multiemployer plan,
or an employee organization which represents
such a plan participant or beneficiary for pur-
poses of collective bargaining, may bring an
action for appropriate legal or equitable relief,
or both.
(b) Failure of employer to make timely withdrawal
liability payment within prescribed time.
In any action under this section to compel an
employer to pay withdrawal liability, any failure of
the employer to make any withdrawal liability pay-
ment within the prescribed time shall be treated in
the same manner as a delinquent contribution (within
the meaning of section 1145 of this title).
(f) Time limitations
An action under this section may not be brought
after the later of —
(1) 6 years after the date on which the cause
of action arose, or
(2) 3 years after the earliest date on which the
plaintiff acquired or should have acquired ac-
tual knowledge of the existence of such cause
of action; except that in case of fraud or con-
cealment, such action may be brought not later
than 6 years after the date of discovery of the
existence of such cause of action.
29 C.F.R. § 2644.2 Overdue and defaulted with-
drawal liability; overpayment
(a) Overdue withdrawal liability payment. Except
as otherwise provided in rules adopted by the plan
in accordance with Sec. 2644.4, a withdrawal liabil-
47a
ity payment is overdue if it is not paid on the date
set forth in the schedule of payments established by
the plan sponsor.
(b) Default.
(1) Except as provided in paragraph (c)(1), ‘de-
fault’ means—
(i) The failure of an employer to pay any overdue
withdrawal liability payment within 60 days after
plan sponsor that the payment is overdue; and
(ii) Any other event described in rules adopted by
the plan which indicates a substantial likelihood that
an employer will be unable to pay its withdrawal
liability.
(2) In the event of a default, a plan sponsor may
require immediate payment of all or a portion of the
outstanding amount of an employer's withdrawal li-
ability, plus interest. In the event that the plan spon-
(i) Expiration of
48a
(ii) If the employer requests review under section
4219(b)(2)(A) of the Act of the plan’s withdrawal
liability determination or the schedule of payments
established by the plan, expiration of the period
described in section 4221(a)(1) of the Act for init-
iation of arbitration; or
(iii) If arbitration is timely initiated either by the
plan, the employer or both, issuance of the arbitra-
tor’s decision. i
(2) Any amounts due before the expiration of the
period described in paragraph (c)(1) shall be paid
in accordance with the schedule established by the
plan sponsor. If a payment is not made when due
under the schedule, the payment is overdue and inter-
est shall accrue in accordance with the rules and at
the same rate set forth in Sec. 2644.3.
(d) Overpayments. If the plan sponsor or an arbi-
trator determines that payments made in accordance
with the schedule of payments established by the plan
sponsor have resulted in an overpayment of with-
drawal liability, the plan sponsor shall refund the
overpayment, with interest, in a lump sum. The plan
sponsor shall credit interest on the overpayment from
the date of the overpayment to the date on which the
overpayment is refunded to the employer at the same
rate as the rate for overdue withdrawal liability pay-
ments, as established under Sec. 2644.3 or by the
plan pursuant to Sec. 2644.4.
29 C.F.R. § 2644.3 Interest on overdue, defaulted
(a) Interest assessed. The plan sponsor of a multi-
employer plan—
(1) Shall assess interest on overdue withdrawal lia-
bility payments from the due date, as defined in
paragraph (d) of this section, until the date paid, as
defined in paragraph (e); and
\
49a
(2) In the event of a default, may assess interest on
any accelerated portion of the outstanding with-
drawal liability from the due date, as defined in
paragraph (d) of this section, until the date paid, as
defined in paragraph (e).
(4) Due date. Except as otherwise provided in rules
adopted by the plan, the due date from which interest
accrues shall be, for an overdue withdrawal liability
payment and for an amount of withdrawal liability
in default, the date of the missed payment that gave
rise to the delinquency or the default.
(e) Date paid. Any payment of withdrawal liability
shall be deemed to have been paid on the date on
which it is received.
This is a copy of a public record, reproduced as it was published. It is not legal advice, and it may not be the version a court would rely on. Check the official source before you cite it.