Opposition — Town of Orangetown v. Ruckelshaus
Supreme Court brief1984
Ask Donna
What actually matters in this document.
Text
I 4
“Oitice - Supreme Court, U.S.
ie
pec 20 1965
No. ¥ 2-55 /
; ; ALEXANDER & STEVAS.
CLERXN
I
LED
N THE a
Supreme Court of the United States
OFroper TERM, 1983
—_———> >
TOWN OF ORANGETOWN,
Petitioner,
|
Anne Gorsucn, Individually and as Administrator of the
United States Environmental Protection Agency;
Richarp Dew tine, Individually and as
Regional Administrator of the United States
Environmental Protection Agency; RockKLAND CouNTy SEWER
District No. 1; County of RocKLAND; TOWN OF RAMAPO;
Town or CLarKstowN; New York State DEPARTMENT OF
CLarksTOWN; New York State DEPARTMENT OF
ENVIRONMENTAL CONSERVATION; and RosBert FLACKE,
as Commissioner of the New York State Department of
Environmental Conservation,
Respondents.
ON PETITION FOR WRIT OF CERTIORARI
TO THE UNITED STATES COURT OF APPEALS
FOR THE SECOND CIRCUIT
BRIEF IN OPPOSITION
Perer A. A. BERLE
(Counsel of Record)
Caro. A. BUCKLER
Bere, Butzer, Kass & CASE
Attorneys for Respondents
Rockland County Sewer
District No. 1, County of
Rockland, and Town of Ramapo
45 Rockefeller Plaza
New York, New York 10111
December 19, 1983 (212) 765-1800
(i)
TABLE OF CONTENTS
TABLE OF AUTHORITIES
STATEMENT OF THE CASE
Factual Background
Prior Proceedings
The Opinion Below
POINT I: THE COURT SHOULD NOT
REVIEW THE DECISION
THAT EPA MADE THE
REQUIRED FINDINGS
A. The Court of Appeals Applied
The Appropriate Standard of
Review
1. Informal Agency Action
Is Judged By The "Arbitrary
And Capricious” Standard
2. Formal Findings Were Not
Required
3. Discovery And Testimony Of
Agency Personnel Is Not
Necessary For Judicial Re-
view of This Agency Action
B. EPA Made The Necessary
Determinations
POINT II: THE COURT OF APPEALS
WAS CORRECT IN NOT
REQUIRING WRITTEN
FINDINGS
21
21
25
30
35
36
(ii)
POINT III: THE COURT OF APPEALS
APPLIED THE CORRECT
STANDARD FOR ASSESS-
ING THE LEVEL OF
CONTROVERSY
CONCLUSION
APPENDIX
Finding of No Significant
Impact and Environmental
Assessment
Page
41
47
(iii)
TABLE OF AUTHORITIES
Cases:
Camp v. Pitts, 411 U.S.
138, 93 S.Ct. 1241 (1973)
Citizens to Preserve
Overton Park, Inc., v.
Volpe, 401 U.S. 402
1971)
F.C.C. v. National Citizens
Committee for Broadcasting,
436 U.S. 775 (1978)
Fund For Animals v. Frizzell,
530 F.2d 982 (D.C. Cir. 1975)
Hanly v. Kleindienst, 471
F. 823 (2d Cir. 1972),
cert. denied 412 U.S.
908 (1972)
Motor Vehicle Manufacturers
Association v. State Farm
Mutual Automobile Insurance
Companies, et al., U.S.
__, 103 S.Ct. 2856 (1983)
Rucker v. Willis, 484
F.2q 158 (4th Cir. 1973)
24
46
43,
28,
30,
39,
46
46
(iv)
Page
Scenic Hudson Preservation
Conference v. Federal Power
Commission, 453 F.2d 463
(2d Cir. 1971), cert. denied
407 U.S. 926 (1972) 24
Town of Orangetown v.
Gorsuch et al., Slip Op.
(2d Cir. 1983) Bie aes
28, 34,
36, 37
43, 45
46
Federal Statutes:
Administrative Procedure Act
5 U.S.C. §552 et seq. 21
5 0.8.C. $553 24
5 U.S.C. §554 24
5 U.8.C. $556 24
5 vU.8.C. $557 24
5 U.S.C. §706(2) (A) 22
Clean Water Act
33 U.S.C. §§1251 et seq. 4
33 U.S.C. §1283 20
33 U.S.C. §1284 20
(v)
National Bank Act
12 GomeGe
National Environmental Policy
Act
42 U.S.C.
§26
§§4321 et seq.
Federal Regulations:
40 C.F.R.
40 C.F.R.
40 C.F.R.
40 C.F.R.
40 C.F.R.
270:107
§§35.925 et seq.
§35.925-7
§35.925-8
35.925-13
§1508.27
3,
IN THE
SUPREME COURT OF THE UNITED STATES
OCTOBER TERM, 1983
NO. 83-
TOWN OF ORANGETOWN,
Petitioner,
- against -
ANNE GORSUCH, Individually
and as Administrator of
the United States Environ-
mental Protection Agency;
RICHARD DEWLING, Individual-
ly and as Regional Admini-
strator of the United States
Environmental Protection
Agency; ROCKLAND COUNTY SEWER
DISTRICT NO. 1; COUNTY OF |
ROCKLAND; TOWN OF RAMAPO;
TOWN OF CLARKSTOWN; NEW YORK
STATE DEPARTMENT OF ENVIRON-
MENTAL CONSERVATION; and
ROBERT FLACKE, as Commission-
er of the New York State De-
partment of Environmental
Conservation,
Respondents.
ON PETITION FOR WRIT OF
CERTIORARI TO THE UNITED
STATES COURT OF APPEALS FOR
THE SECOND CIRCUIT
BRIEF IN OPPOSITION
STATEMENT OF THE CASE
Factual Background
The Rockland County Sewer District
No. 1 ("RCSD") is comprised of a number
of municipalities in Rockland County,
New York. It operates a sewage treat-
ment plant which is located in a corner
of Orangetown, New York. The Town of
Orangetown, which is included in Rock=-
land County, refused to be a part of the
sewer district when the district was
formed, but it does have a vote on the
district's governing board of commis-
sioners. Orangetown operates its own
sewage treatment plant, which is located
1,800 feet away from the RCSD plant.
The RCSD plant was built in the
1960's. In the course of time, it has
become outmoded and overloaded. When
flows of untreated effluent to the plant
exceed the plant's treatment capacity,
untreated or partially treated sewage is
discharged to the Hudson River through
the outfall pipe leading from the plant.
In the mid-1970's, in order to address
the need to increase sewage treatment
Capacity within the district and to cope
with a growing threat to groundwater
quality caused by failing septic systems
and antiquated sewers, RCSD sought the
help of the United States Environmental
Protection Agency ("EPA") and the New
York State Department of Environmental
Conservation ("DEC"), pursuant to a
construction grants program for waste-
water treatment plants under the Clean
Water Act, 33 U.S.C. §§1251 et seq.
RCSD, together with the federal and
state agencies, began an extensive fa-
cilities planning process. That pro-
cess involved analysis of present and
future needs for sewage treatment in the
area, analysis of alternative treatment
methods and collection routes and exten-
sive environmental analysis, and extend-
ed over a four-year period. In keeping
EPA finances the construction of
wastewater treatment facilities in three
steps. Step 1 grants finance the devel-
opment of feasibility studies and other
preliminary planning, which results in a
facilities plan which is submitted to
EPA for approval. Step 2 grants finance
the preparation of detailed plans and
design specifications for construction
based on the facilities plan. Step 3
grants finance actual construction,
with the National Environmental Policy
Act, 42 U.S.C. §§4321 et seg. ("NEPA"),
(which requires environmental review of
certain federal actions,) NEPA's imple-
menting regulations, and the Clean Water
Act, extensive public participation also
took place. At practically every public
hearing, Orangetown, the petitioner in
this action, appeared and submitted ex-
tensive criticism of proposals that were
the subject of the facilities planning
process. Ultimately, a facilities plan
was completed. That plan called for the
expansion of the RCSD plant, the upgrad-
ing of certain sewers and collection
systems which transport effluent to the
plant, the installation of extensive
odor control mechanisms and the con-
Struction of facilities to process
sludge -- the by-product of sewage
treatment processing. At the conclusion
of the facilities planning process and
in accordance with the procedures set
forth in the Clean Water Act and its
implementing regulations, RCSD applied
to EPA for a Step 2 grant for develop-
ment of plans and design specifications.
Prior to offering the Step 2 grant
to RCSD in September, 1980, EPA reviewed
the facilities plan, which included
analysis of and response to comments re-
ceived at public hearings, and prepared
a written environmental assessment
("EA"). On the basis of the environmen-
tal review and assessment, EPA issued a
Finding of No Significant Impact
("FONSI"). (The FONSI and EA are re-
produced in the appendix atcached to
this brief.) Upon finding that the pro-
ject would not have a significant impact
on the environment, EPA was not required
to prepare a more detailed environmental
impact statement in accordance with the
National Environmental Policy Act, 42
U.S.C. §4321 et seq, ("NEPA").
Prior Proceedings
After RCSD accepted the Step 2
grant from EPA, Orangetown, having pre-
viously opposed every aspect of the pro-
ject at every opportunity, began this
lawsuit in the United States District
Court for the Southern District of New
York. It sought to enjoin the release
of funds by EPA to RCSD, claiming that
EPA did not comply with certain of its
own regulations relating to the process-
ing and issuance of construction grants.
It also charged that EPA had violated
NEPA because it had not prepared an en-
vironmental impact statement. The
complaint also alleged that DEC had not
met certain requirements of state law.
Finally, Orangetown sought monetary dam-
ages and injunctive relief on the ground
that the operation of the RCSD plant
constituted a nuisance. RCSD asserted a
counterclaim, charging that the opera-
tion of the nearby Orangetown sewage
treatment plant constituted a nuisance.
The District Court dismissed the
Orangetown state law claims on motion.
¢ After
Trial began in October, 1982.
eleven days of trial, the Court dismis-
sed both nuisance claims from the bench
after summation by counsel. After re-
ceiving briefs on the remaining issues,
zat the commencement of trial,
Orangetown amended its complaint to in-
clude the first phase of construction,
Step 3 Phase l.
the Court then dismissed all of Orange-
town's claims, holding that EPA's find-
ing that the project would have no sig-
nificant environmental impact was pro-
per, and that EPA's procedures in issu-
ing the grant complied with applicable
statutory and regulatory law, including
the technical determinations challenged
by Orangetown in its pleadings.
In its complaint, Orangetown
charged that EPA had not made certain
determinations relating to environmental
review, waste treatment technology,
cost-effectiveness and plant capacity,
as required by its regulations. 40
C.F.R. §§35.925-7, 35.925-8 and 35.925=
13. The EPA regulations also specify
that 17 other findings are to be made,
although Orangetown never stated in its
pleadings or during the course of trial,
-10-
that it was challenging findings other
than those required by the three subsec-
tions enumerated in its complaint.
Several weeks after trial, and be-
fore the Court rendered its opinion,
Orangetown moved to amend its complaint
to include a challenge with respect to
the additional 17 findings. The Dis-
trict Court denied the motion in that
the defendants -- both RCSD and EPA --
demonstrated there had been no implied
consent to try these additional ques-
tions, so they had not been contested at
trial; thus it was inappropriate for
Orangetown to attempt to inject a host
of new issues after the close of trial.
Orangetown filed a Notice of Ap-
peal, and the Second Circuit granted
RCSD's motion to have the appeal heard
on an expedited basis. EPA regulations
“l1i-
require that work be commenced within a
specified period after a grant is
awarded. Because of bonding difficul-
ties, RCSD faced the risk of losing the
grant necessary to upgrade its inade-
quate sewage treatment facilities simply
as the result of the pendency of litiga-
tion, even though Orangetown had never
established that a single one of its
claims was meritorious.
In an extensive opinion, the Court
of Appeals affirmed the District Court's
decision to dismiss Orangetown's claims
in all respects. The Court had before
it the aabise administrative record,
which consisted of the nine-volume fa-
cilities plan as well as several addi-
tional boxes of correspondence, analysis
and other written material, all of which
EPA had put in evidence in the proceed-
=12-
ings below. While the Second Circuit
was considering this case, a clerk of
the court apparently contacted the U.S.
Attorney's office seeking information
about the administrative record relating
to the 17 findings which the District
Court had ruled were not in issue when
it denied Orangetown's motion to amend
its pleadings. The U.S. Attorney's of-
fice provided the requested information
in an extensive letter. The Court of
Appeals, however, apparently did not re-
ly on the information submitted. It af-
firmed the denial of Orangetown's post-
trial motion to amend the pleadings to
include a challenge to the remaining 17
EPA determinations. The appellate court
concurred with the District Court's rul-
ing that the only determinations were
-13-
appropriately at issue were those enum-
erated in the pleadings.
Throughout the proceedings, bond
counsel had instructed RCSD that the
pendency of the litigation prevented him
from providing the prerequisite opinions
for the issuance of bonds necessary to
begin the project. In an apparent ef-
fort to continue litigation endlessly,
Orangetown has filed the Petition for a
Writ of Certiorari, which is the subject
of this brief. Orangetown has also
started two new proceedings, one in the
state court and another in the United
States District Court, in which it seeks
to block the issuance of the next phase
of the Step 3 grant, which RCSD has ac-
cepted. That phase will provide for re-
building of the processing facilities
within the RCSD plant. While Orangetown
-14-
pursues every opportunity to litigate
against RCSD and the governmental agen-
cies responsible for administering the
water pollution control program, and
thus delay or prevent the modernization
of the RCSD plant, improperly treated
sewage continues to flow into the Hudson
River and failing septic systems within
the sewer district jeopardize ground-
water supplies within the region.
The Opinion Below
The Court of Appeals, in a unani-
mous, 26-page opinion written by Hon.
Lawrence W. Pierce, affirmed the Dis-
trict Court's dismissal of the action in
every respect. It observed that an en-
vironmental impact statement is not re-
quired for federal actions not "signif-
icant" within the meaning of NEPA, It
found that the EPA's determination of
-15-
"no significant impact” is neither a
rulemaking nor adjudicatory function,
but a factual finding made by the agency
with particular expertise in environmen-
tal matters. Thus, it found that review
was limited to a determination whether
the agency had been arbitrary or capri-
cious.
The Court then proceeded to analyze
every issue that Orangetown asserted
that EPA had given inadequate considera-
tion when it issued the FONSI. In exam-
ining Orangetown's claims with respect
to wetlands,. the Court reviewed the
analysis of wetlands considerations
contained in the administrative record,
EPA's comments to RCSD and DEC about
wetlands during the facilities planning
process, and changes in the project at
EPA's insistence that wetlands impact be
reduced. On the basis of this extensive
-16-
review of the record, the Second Circuit
determined that EPA's decision with re-
gard to wetlands effects was neither
arbitrary or capricious. Similarly, the
Court analyzed the administrative record
with respect to its treatment of flood-
plains impacts, land use impacts, and
sewage treatment plant design. The Sec-
ond Circuit opinion contains several
pages of analysis with respect to each
of the issues that Orangetown raised; in
each instance the Court found that EPA
did not abuse its discretion or act ar-
bitrarily in concluding that the project
would not significantly affect the en-
vironment.
In a separate subsection, the Court
analyzed Orangetown's contention that
this project required an environmental
impact statement on the basis of the
-i17-
claim it was “highly controversial" un-
der the guidelines issued by the Council
on Environmental Quality. See 40 C.F.R.
§1508.27. The Court noted that expan-
Sion of an unpopular sewage treatment
plant can be expected to generate oppo-
sition. It observed that under existing
precedent, a project is "highly contro-
versial" when "a substantial dispute
exists as to the size or effect of the
major federal action rather than to the
existence of opposition to a use.” Town
of Orangetown v. Gorsuch et al., Slip
Op. at 6638 (2d Cir. 1983), Petition at
A-22. The Court found that in light of
the evidence supporting the FONSI, more
than mere speculation that the plant ex-
pansion would increase odor problems
would be necessary before the project
-18<
could be called "highly controversial."
In sum, the Court found that EPA's
finding of no significant impact and its
conclusions with respect to all of the
elements of that finding were supported
by substantial evidence, were not arbi-
trary and capricious, and did not re-
present an abuse of discretion. It
therefore determined that it was not
within the competence of the Court to
overrule the agency's determination.
In considering Orangetown's claims
relating to alleged violations of EPA's
procedural regulations for grant-making,
the Court undertook its own review of
the administrative record. It upheld
the District Court's ruling that the
record revealed that in making certain
technical determinations, EPA complied
-19<
with the terms of the applicable regu-
lations and that the objectives of those
regulations were accomplished.
The Court also reviewed the evi-
dence presented at trial with respect to
the nuisance claims. It found no basis
for overturning the District Court's
ruling that Orangetown's evidence failed
to prove that the County plant operation
resulted in a public nuisance. Finally,
the Court upheld the District Court's
determination in dismissing Orangetown's
Claim that DEC did not comply with New
York State's environmental quality re-
view act.
POINT I
THE COURT SHOULD NOT
REVIEW THE DECISION THAT
EPA MADE THE REQUIRED
FINDINGS
The first question that petitioner
=20-
raises for review by this Court is whe-
ther or not EPA failed to make certain
determinations required under the Clean
Water Act, 33 U.S.C. §§1283 and 1284,
and its implementing regulations, 40
C.F.R. §35.925 et seq. and if 50, whe-
ther such failure rendered the grant at
issue unlawful. The District Court and
the Court of Appeals both conducted re-
views of the extensive record of admin-
istrative action in this case, after
which they both found that the agencies
had complied with that set of regula-
tions, and that the grants were lawful.
Petitioner claims that in spite of the
careful factual review given these is-
sues by the lower courts, they merit re-
view by the Supreme Court because of the
importance of the issue of the enforce-
ability of the statutory and regulatory
requirements. Petitioner suggests that
-2l<-
it is an open question whether or not
the standard to be applied to such an
action, which is neither rulemaking nor
adjudication, should be as rigorous as
that applied by the Administrative Pro-
cedure Act ("APA"), 5 USC §§552 et seg.,
to actions which are either rulemaking
or adjudicatory. There is, however, no
need for the Supreme Court to address
this question anew. It is well settled
by the Supreme Court in prior opinions,
and the decision of the Court of Appeals
fits well within the guidelines thus set
forth. This case presents no issues
which would call into question the es-
tablished law.
A. The Court of Appeals Applied The
Appropriate Standard of Review
1. Informal Agency Action Is
Judged By The “Arbitrary
And Capricious" Standard
In assessing the administrative ac-
-22-
tion here, the Court of Appeals applied
the standard of review set forth in the
Administrative Procedure Act ("APA"),
which provides that agency action may be
overruled by a court only if the action
was “arbitrary, capricious, an abuse of
discretion, or otherwise not in accor-
dance with law." 5 U.S.C. §706 (2) (A)
(1976); Town of Orangetown v. Gorsuch et
al., Slip Op. at 6628-29, Petition at
A-13.
There is no reason, based on the
facts of this case, for this Court to
reconsider the standard of review as ap-
plied. Administering and issuing grants
under the construction grants program of
the Clean Water Act is neither a rule-
making nor an adjudicatory function. In
Citizens to Preserve Overton Park, Inc.
-23-
v. Volpe, 401 U.S. 402 (1971) ("Overton
Park"), at issue was the approval by the
Secretary of Transportation of the con-
struction of an interstate highway
through a public park in Memphis. Such
a construction project, and the neces-
Sary approvals for it, involved neither
rulemaking nor an adjudication. The
Supreme Court had no difficulty in de-
term¥ning that the action was therefore
governed by the arbitrary and capricious
standard of the APA, rather than the
more rigorous requirements applied to
formal, on-the-record actions like for-
mal rulemaking and adjudication. 401
U.S. at 414-15. In the APA, Congress
chose to set higher standards for agen-
cies with regard to record-keeping, pub-
lic statements and due process when they
-24-
were acting in a quasi-judicial or
quasi-legislative function. 5 U.S.C.
§§553, 554, 556, 557. See F.C.C. v.
National Citizens Committee for Broad-
casting, 436 U.S. 775, 802-803 (1978);
Scenic Hudson Preservation Conference v.
Federal Power Commission, 453 F.2d 463,
468 (2€ Cir. 1971), cert. Gen. 487 U.s.
926 (1972). Technical findings made by
agencies in the course of sewage treat-
ment construction grants, as in highway
construction projects, are internal and
preliminary in nature, and result from
the exercise of an expert function,
which is neither legislative nor judi-
cial. The agencies in such actions are
making decisions based on administrative
and technical expertise and are neither
assessing penalties or punishments
-25-
against individuals before them, nor
setting forth prospective regulations to
be followed in the future. This case
presents no reasonable opportunity to
depart from the well-established under-
standing of the Congressional mandate
that a higher standard of review should
be applied to rulemaking and adjudica-
tion than to grant issuance.
2. Formal Findings Were
Not Required
The Court of Appeals was correct in
not requiring formal findings when it
analyzed the agency's record of its ac-
tion in this case. In Overton Park, the
relevant statutes prohibited the Secre-
tary of Transportation from authorizing
the use of federal funds to finance
=26-
construction of a highway routed through
a public park if a feasible”alternative
existed, and further required the Secre-
tary to minimize any harm to the park if
there was no alternative route avail-
able. The Secretary's approvals of the
route and design of the highway were
unaccompanied by a statement of the
Secretary's factual findings on those
points. In reviewing the agency action
in that case, the District Court had re-
lied solely on affidavits prepared for
litigation by both agency representa-
tives and representatives of the chal-
lengers to the action.
The Supreme Court found that al-
though the Secretary did not make formal
findings as to alternatives and the min-
imization of harm, the statutes did not
require formal findings, and therefore
-27<
that failure alone did not mandate re-
mand to the agency. 401 U.S. at 417.
In that case, because the entire admin-
istrative record was not before the
Court, it was unable to determine whe-
ther or not informal findings or other
evidence of the determinations were in-
cluded in the record. The Court there-
fore remanded the case to the District
Court, with instructions that the lower
court review the entire administrative
record to determine the appropriateness
of the Secretary's decision.
The reasoning in Overton Park is
therefore perfectly consistent with the
reasoning of the Court of Appeals in the
case at bar. The difference between the
two cases is that, here, the entire ad-
ministrative record was before the Dis-
trict Court and the Court of Appeals.
-28-
Both courts had the opportunity to re-
view the entire record, and both courts
found evidence to support a finding that
the EPA had complied with the statute
and regulations. The Court of Appeals
stated, "all that is necessary is that a
reviewing court be able to trace from
the written record the path followed by
the agency in deciding to take a partic-
ular action ..." when the statute does
not require formal findings. Town of
Orangetown v. Gorsuch et al., Slip Op.
at 6641, (2d Cir. 1983); Petition at
A25.
This standard is consistent not on-
ly with Overton Park, but with the most
recent Supreme Court decision reviewing
informal agency action, Motor Vehicle
Manufacturers Association v. State Farm
Mutual Automobile Insurance Companies,
et al., U.S. , 103 S.Ct. 2856
-29-
(1983) ("Motor Vehicles"). In that
case, this Court overturned the action
by the Department of Transportation re-
scinding a rule requiring that new motor
vehicles be equipped with passive re-
straints to protect the safety of vehi-
cle occupants in the event of a colli-
sion. The Supreme Court found that the
agency action was arbitrary and capri-
cious because the administrative record
demonstrated that the agency had not
given sufficient consideration to a rel-
evant alternative, and because the re-
cord did not provide the basis for con-
cluding that the rescission was the re-
sult of reasoned decisionmaking. The
Court therefore examined the administra-
tive record compiled by the agency in
the course of taking its action, and
found that record insufficient to jus-
-30-
tify the action. That approach is pre-
cisely the same approach that the Court
of Appeals took in analyzing agency ac-
tion in the case at bar. In this case,
however, unlike Motor Vehicles, the
Court found that the administrative re-
cord did substantiate agency action.
3. Discovery And Testimony Of
Agency Personnel Is Not
Necessary For Judicial
Review Of This Agency Action
The limitations placed by the dis-
trict court on petitioner's delving into
the mental processes of agency person-
nel, either during discovery or trial,
do not strengthen petitioner's argument
that a stricter standard of judicial re-
view should have been applied in this
case. Petitioner seems to argue that
because it asserted during trial that it
failed to understand the administrative
-3l-
record, it therefore was entitled to ob-
tain individual testimony from agency
personnel to explain that record. How-
ever, the cases cited by petitioner do
not support it in that argument. In
Camp v. Pitts, 411 U.S. 138 (1973), an
applicant brought suit to compel the
Comptroller of the Treasury to issue a
bank charter to it. The Comptroller had
twice denied the application. The Court
there found that the statute did not re-
guire the Comptroller to make formal
findings on the record when passing on
applications for new banking authori-
ties. The court cited language from the
National Bank Act, which in fact used
Similar language to that of the Clean
Water Act in referring to the agency
decisionmaking. The National Bank Act
-32-
stated that the Comptroller was to "“as-
certain” certain specific facts with re-
gard to the qualifications of the appli-
cant, in considering the application.
12 U.S.C. $26. Similarly, the Clean
Water Act and regulations state that the
Administrator shall “determine” certain
facts exist. Without more, neither sta-
tute mandates formal findings.
In Camp, the Court went on to find
that the Court of Appeals had been in
error in ordering a de novo hearing. It
stated that the only deficiency suggest-
ed in the agency action was that the
agency inadequately explained its deci-
sion. The Court stated that “such a de-
ficiency was not enough to warrant a de
novo hearing. A trial court should ap-
ply the arbitrary and capricious stan-
dard set forth in the APA and "in apply-
=33-
ing that standard, the focal point for
judicial review should be the adminis-
trative record already in existence, not
some new record made initially in the
reviewing court.” Camp v. Pitts, 411
U.8. at 141.
The Court further held that if
there had been a complete absence of ex-
planation for the administrative action
in the record, then perhaps the court
could obtain from the agency "either
through affidavits or testimony, such
additional explanation of the reasons
for the agency decision as made prove
necessary." Id. at 143. However, the
Comptroller's record provided some ex-
planation of its action. "The explana-
tion may have been curt, but it surely
indicated the determinative reason for
the final action taken ... The validity
=34-
of the controller's final action must,
therefore, stand or fall on the pro-
priety of that finding, judged, of
course, by the appropriate standard of
review.” Id. The agency action in the
case at bar presents the same situation.
While "a clear and concise document out-
lining seriatim”" the required findings
might have been desirable for ease of
review by the Court, the existing form
of the record does not provide peti-
tioner with the opportunity to examine
witnesses from the agency. Town of
Orangetown v. Gorsuch et al., Slip Op.
at 6640 (2d Cir. 1983); Petition at
A-24. The agency action must stand or
fall on the administrative record. Both
lower courts determined that the action
should stand.
-35-
B. EPA Made The Necessary Determinations
The determinations at issue in this
case are those included in 40 C.F.R.
§35.925-7, §35.925-8, and §35.925-13,
which refer to the waste treatment tech-
nology, capacity and cost-effectiveness
of the planned plant and collection sys-
tems, and the environmental review
performed by the agency. The Court of
Appeals found that the administrative
3as discussed above, the Court of
Appeals upheld the District Court's de-
.termination that since the remaining
determinations in 40 C.F.R. §35.925 et
seq were not placed in issue in the
pieadings or during trial, they were not
subject to review in this action. Pe-
titioner's continued post-trial insis-
tence that the other determinations
should receive judicial review cannot
change the fact that petitioner failed
to make known its challenge to those
determinations prior to or during trial.
Further review of the District Court's
ruling on that motion is unwarranted.
-36-
record provided sufficient documentation
of the agency's decision on these is-
sues, and that therefore the agency com-
plied with applicable law in issuing the
grants. Town of Orangetown v. Gorsuch
et al., Slip Op. at 6641 (2d Cir. 1983),
Petition at A-25. The Environmental
Assessment prepared by EPA, which was
promulgated along with the Finding of No
Significant Impact, evidences agency
determinations on all the issues raised
by the relevant regulations. In addi-
tion, the administrative record includes
documents submitted by the grantees
which provide extensively detailed stu-
Gies of those issues.
POINT II
THE COURT OF APPEALS WAS CORRECT
IN NOT REQUIRING WRITTEN FINDINGS
The second reason that petitioner
@37<
sets forth for granting the petition is
related to its first point, and must be
rejected on the same basis. The Court
of Appeals found that the EPA regula-
tions "do not require that the agency's
actions be set down in any particular
order or form, or even that its deter-
mMinations be made in writing." Town of
Orangetown v. Gorsuch et al., Slip Op.
at 6640, (2d Cir. 1983), Petition at A-
24. Petitioner apparently contends that
this Court did not mean what it said in
cases like Overton Park, Camp v. Pitts,
and Motor Vehicle, when it required that
the Court review the administrative re-
cord as a whole when a statute does not
require formal findings. Petitioner
constructs a dichotomy in the petition,
reasoning that if written findings are
not required then the findings must be
either oral or implied. It then states
-38-
that oral findings would require oral
testimony, and that implied findings are
no findings at all. This reasoning, ac-
cording to petitioner, leads neatly back
to the conclusion that discovery of and
testimony by agency personnel should
have been permitted.
The fatal flaw in this reasoning is
that the Supreme Court and lower courts
have consistently permitted examination
of the administrative record for evi-
dence of informal or implied findings.
In Overton Park, the Supreme Court in-
structed the District Court to peruse
the administrative record for such find-
ings on remand. It did not direct the
lower court to take oral testimony, but
allowed the district court some flex-
ibility in determining the necessity for
such testimony after its examination of
-39-
the record. 401 U.S. at 419-20. The
same result prevailed in Camp v. Pitts.
411 U.S. at 143. In both cases, the
Court found that the statute did not re-
quire formal findings, and in neither
case did the Court order that oral tes-
timony must be taken. If the Court did
not believe that implied findings were
acceptable, then it would have ordered
the District Court to take oral testi-
mony, or would have remanded to the
agency for express, formal findings.
Finally, in Motor Vehicle, the Court did
not strike down the agency's rescission
on the basis of a procedural deficiency
in the form of failure to state formal
findings. It found that upon review,
the agency's record proved to be sub-
-40-
Stantively insufficient to justify the
action. 4
As in the cases discussed above,
the Court of Appeals here found that
formal findings were not required; it
examined the administrative record for
evidence of the basis for the adminis-
trative action. On that basis, it up-
held the agency action. Contrary to pe-
titioner's characterization, the Court
did not relieve EPA from its obligation
to comply with the regulations, but
41t is important to note that in
Motor Vehicle, the Supreme Court con-
Sideread it “relevant that Congress re-
quired a record of the rulemaking pro-
ceedings to be compiled and submitted to
a reviewing court, 15 U.S.C. §1394 [mo-
tor vehicle safety standards promulga-
tion], and that agency findings under
the Motor Vehicle Safety Act would be
Supported by 'substantial evidence on
the record considered as a whole.'"
(Citations omitted). 103 S.Ct. at 2856.
-41-
rather found that the agency had com-
plied with the regulations. There is
nothing illogical or inconsistent about
this approach, and thus there is no need
for this Court to review the lower
courts' decisions.
POINT III
THE COURT OF APPEALS APPLIED
THE CORRECT STANDARD FOR
ASSESSING THE LEVEL OF CONTROVERSY
Petitioner asserts a final, un-
founded claim that this Court should
review the ruling by the Court of Ap-
peals that the amount of controversy
surrounding this project did not mandate
an Environmental Impact Statement
("EIS") pursuant to NEPA. The decision
in the Second Circuit is entirely con-
sistent with the prevailing decisions in
-42-
prior cases, and leaves no questions
open for settlement by this Court.
The guidelines of the Council on
Environmental Quality ("CEQ") state that
consideration of environmental impacts
for purposes of deciding whether to re-
quire an EIS, should include an evalua-
tion of "(t]he degree to which the ef-
fects on the quality of the human en-
vironment are likely to be highly con-
troversial.” 40 C.F.R. §1508.27. As
discussed above, after reviewing the
administrative record of this action,
both the District Court and the Court of
Appeals found that EPA had not been ar-
bitrary Or capricious in issuing the
Finding of No Significant Impact, with
respect to every issue raised by peti-
tioner, including that of public con-
troversy. The Court of Appeals found
-43-
that "the record lacks a sufficient
basis to indicate that the opposition to
this project was of such an extraordin-
ary nature as to require an EIS." Town
of Orangetown v. Gorsuch et al., Slip
Op. at 6638 (2d Cir. 1983), Petition at
A22.
Petitioner exaggerates the choice
of of the word "extraordinary" by the
Court of Appeals, contending that with
that one word, the Court intended to set
a new standard for the level of contro-
versy requiring an EIS. To the con-
trary, however, the decision by the
Court of Appeals on this issue is com-
pletely in line with the cases cited by
petitioner. In Hanly v. Kleindienst,
471 F.2d 823, 830 (2d Cir. 1972), cert.
denied 412 U.S. 908 (1972), the Court
Stated that "... the term '‘'controver-
-44-
sial' apparently refers to cases where a
Substantial dispute exists as to the
size, nature or effect of the major fed-
eral action rather than to the existence
of a use ...” In the case at bar, it is
precisely the use of the site as a sew-
age treatment plant, improved or unim-
proved, which is the source of some con-
troversy in the neighborhood, rather
than the environmental effects of the
project. The Petition for Writ of Cer-
tiorari makes this abundantly clear when
it states:
"The [Sewer] District was born
in the controversy inherent in
one community's sending its sew-
age to another. The controversy
deepened through the years as
the County plant emitted massive
odors, reshaping life in the
areas of Orangetown around it.”
Petition at 54-55. Petitioner goes on
to say that the existence of the im-
provement project “deepened and broad-
-45-
ened" the controversy that surrounded
the plant itself. As the Court of Ap-
peals found, in this case the record re-
vealed that the local opposition to the
project's effects grow out of "mere
speculation that the plant expansion
will increase odor problems, rather than
alleviate such problems,” which does not
amount to the sort of controversy with
respect to environmental. impacts that
would mandate an EIS. Town of Orange-
town v. Gorsuch et al., Slip Op. at 6638
(2d Cir. 1983); Petition at A-22.
To rule that any such vocal opposi-~
tion makes the effects of the project
"highly controversial" according to the
terms of the CEQ guidelines, "would re-
quire an impact statement whenever a
threshold determination dispensing with
one is likely to face a court challenge
-46-
fand would] surrender the determination
to opponents of a federal action, no
matter whether [the project is] major or
not, nor how insignificant its environ-
mental effects might be." Rucker v.
Willis, 484 F.2d 158, 162 (4th Cir.
1973). See also Town of Orangetown v.
Gorsuch et al., Slip Op. at 6638 (2d
Cir. 1983); Hanly v. Kleindienst, 471
F.2d at 830 n.9A; Fund for Animals v.
Frizzell, 530 F.2d 982, 988-89 n.15
(D.C. Cir. 1975). The ruling on this
issue by the Court of Appeals is there-
fore grounded in, rather than inconsis-
tent with, relevant case law. The Court
did not establish a new standard for
decision; it simply analyzed the facts
of this case in light of established
standards, and supported the EPA deci-
sion not to require an EIS.
-47-
No issue remains which would demand
the consideration of this Court.
CONCLUSION
On the basis of the foregoing,
the Court should deny the petition for
writ of certiorari.
Respectfully submitted,
PETER A. A. BERLE
Counsel of Record
Carol A. Buckler
Berle, Butzel, Kass & Case
Attorneys for Respondents
Rockland County Sewer
District No. 1; County
of Rockland and Town
of Ramapo
45 Rockefeller Plaza
New York, New York 10111
(212) 765-1800
270:101
_* emt «-<
’ APPENDIX
UNITED STATES ENVIRONMENTAL
PROTECTION AGENCY
Region II
26 Federal Plaza
New York, New York 10278
August 29, 1980
To All Interested Govern-
ment Agencies and Public
Groups:
In accordance with the procedures for
the preparation of environmental impact
statements, an environmental review has
been performed on the proposed agency
action below:
Project Rockland County Sewer
Name: District No. 1 (RCSD No.
1) sewage treatment plant
expansion, sludge hand-
ling facilities and in-
terceptor sewers.
Project C-36-744-03 (Step 2
Grant)
Numbers: RCSD No. 1
C-36-1253-01 (Step 2
Grant)
Town of Ramapo
Purpose of The purpose of this pro-
Project: ject is four fold: to re-
place failing individual
septic systems in Ramapo
with collection sewers;
to provide interceptor
sewers to convey sewage
Project
Location:
Project
Description:
Proposed
Eligible
Project
Costs:
EPA Grant
(75%):
from the Towns of Ramapo
and Clarkstown to the
RCSD No. 1 STP; to expand
the overloaded RCSD No. 1
STP to treat existing and
future flows from the
proposed service area; to
provide facilities to
process sludge from the
RCSD No. 1 STP.
Towns of Ramapo, Clarks-
town and Orangetown, New
York
Preparation of plans and
specifications for con-
struction of collection
sewers, interceptor sew-
ers, pump stations, STP
expansion and sludge
handling facilities as
described in detail in
Section IV of the at-
tached environmental as-
sessment.
$3,758,380 -
RCSD No. 1
$ 674,000 -
Town of Ramapo
RCSD No. 1
$ 506,000 -
Town of Ramapo
Our environmental review of this project
indicates that no significant environ-
mental impacts will result from the pro-
posec action. Consequently, we have
made a preliminary decision not to pre-
pare an environmental impact statement
(EIS) on the project.
This decision is based on a careful re-
view of the engineering report, the en-
vironmental information document, and
other supporting data. All of these
documents, along with the environmental
assessment, are on file at the EPA re-
gional office, where they are available
for public scrutiny upon request. rN
copy of the environmental assessment is
enclosed for your review.
Both the State of New York and the EPA
recognize that this project is located
in an Air Quality Control Region (AQCR).
This fact has been accounted for in our
review.
Comments supporting or disagreeing with
this decision may be submitted to the
EPA for consideration. All comments
must be received within thirty (30) cal-
endar days of the date of this finding
of no significant impacts (FNSI).
Please address your comments to the
Chief, New York and Virgin Islands Sec-
tion, Environmental Impacts Branch, Room
400. After evaluating any comments re-
ceived on the project, the EPA will make
a final decision. However, no adminis-
trative action will be taken on the
project for at least thirty (30) calen-
dar days after the date of this FNSI.
Sincerely yours,
Charles S. Warren
Regional Administrator
Enclosure
Environmental Assessment
rT. Project Identification
Project Name:
Name and
Address of
Applicants:
Project
Numbers:
Project
Location:
II. Description
Rockland County Sew-
er District No. 1
sewage treatment
plant, sludge hand-
ling facilities, and
interceptor sewers
Town of Ramapo col-
lection sewers
Mr. Charles S.
Stewart, Jr., P.E.
Executive Director
Rockland County Sew-
er District No. 1
4 Route 340
Orangeburg, New York
10962
C-36-744-03 (Step 2
Grant), Rockland
County, New York
C-36-1253-01 (Step 2
Grant), Town of
Ramapo, New York
Towns of Ramapo,
Clarkstown and
Orangetown, New York
of Facility Planning
Area
The facility planning area is located in
the Towns of Clarkstown and Ramapo, ap-
proximately 50 kilometers (30 miles)
from New York City (see Figure 1). It
encompasses approximately 190° square
kilometers (75 square miles), represent-
ing the unincorporated parts of the
towns. Although the Rockland County
Sewer District No. 1 sewage treatment
plant (RCSD NO. 1 STP), which receives
flows from Ramapo and Clarkstown, is lo-
cated in Orangetown, Orangetown does not
contribute flows to the RCSD STP and
thus is not included as part of the
planning area.
The facility planning area is character-
ized by gently rolling hills and val-
leys. There are five natural drainage
basins within the area defined by the
names of the respective bodies of water
as follows: Mahwah River, Minisceongo
Creek, Saddle River, Pascack Brook and
Hackensack River. The planning area has
a rich diversity of inland wetlands,
many of which are associated with its
creeks, streams and rivers. As discus-
sed in Section VII-B of this environmen-
tal assessment, grant conditions are be-
ing used to prohibit hook-ups to the
proposed sewer system from future devel-
opment located in wetland and floodplain
areas.
Land use in the planning area is predom-
inantly residential, with industrial and
commercial development along the major
roadways, railroads and waterways. The
population of the planning area is pro-
jected to increase from approximately
160,000 to 201,000 over the 20 year de-
sign period of the proposed sewerage fa-
cilities. The population projections
are based on recent development plans,
zoning, and a constraints analysis which
excluded environmentally sensitive areas
(such as wetlands, floodplains, agricul-
tural lands and steep slopes) from de-
velopment. These projections are lower
than the population projections, pre-
pared by the New York State 208 Water
Quality Management Plan.
Large portions of the planning area are
currently served by collection and
interceptor sewers and pump stations and
forcemains. Unsewered portions of the
planning ares are served by individual
on-site disposal systems. Existing (and
proposed) sewers are tributary to the
existing RCSD No. 1 STP which discharges
treated effluent to the Hudson River.
Some existing sewers also convey waste-
water to the Town of Ramapo, privately
operated treatment plants and to the
Haverstraw Joint Regional Sewerage Board
facilities. Sludge resulting from
wastewater treatment at the STP is cur-
rently disposed of at the Clarkstown
Sanitary landfill.
III. Purpose and Need for Project
The purpose of this project is four
fold: to replace failing individual sep-
tic systems in Ramapo with collection
sewers; to provide interceptor sewers to
convey sewage from the Towns of Ramapo
and Clarkstown to the RCSD No. 1 STP; to
expand the overloaded RCSD No. 1 STP; to
provide facilities to process. sludge
from the RCSD No. 1 STP.
Collection sewers
Existing on-site subsurface disposal
systems in Ramapo are failing because of
impermeable soils, shallow depth to bed-
rock, small lot sizes or seasonal high
water tables. Surface discharges of raw
sewage as a result of these conditions
are causing odor problems, represent a
public health hazard and are degrading
the quality of surface waters in the ar-
ea. Collection sewers are proposed to
replace these failing on-site systems
(see Figures 2, 3, 4, 5, and 6).
Interceptors
Interceptor sewers are required to con-
vey sewage from the proposed collection
areas as well as from eight small public
and private STPs in Ramapo to the RCSD
No. 1 STP (see Figures 7, 8, and 9). In
addition, some of the interceptors will
also facilitate gravity conveyance of
wastewater thereby eliminating existing
pumping stations. Cost-effective analy-
ses found it less expensive to abandon
the eight STPs and treat their flows at
an expanded RCSD No. 1 STP than to up-
grade and expand the small STPs.
RCSD No. 1 STP Expansion
The RCSD No. 1 STP has a design capacity
to treat 3,800 cubic meters (10 million
gallons per day) but present wastewater
flows substantially exceed this quanti-
ty. A large part of the excessive flows
at the plant is due to the infiltration
of groundwater and inflow of stormwater
(I/I) into the interceptor and collec-
tion system. On May 30, 1980, the U.S.
Environmental Protection Agency (EPA)
issued a finding of no significant im-
pact/environmental assessment (FNSI/EA)
for the design and rehabilitation of a
portion of the sewer system where it is
cost-effective to remove I/I rather than
treat it at the STP. As part of th pro-
ject presently being proposed, the RCSD
No. 1 STP will be expanded to 8,500 cu m
(25 mgd) to handle existing and future
sewage flows from the proposed service
area as well as I/I that is cost-effec-
tive to treat rather than remove from
the sewer system (see Figure 11).
Sludge Handling Facilities
The existing sludge handling facilities
at the RCSD No. 1 ST are inadequate to
process the increased sewage flows at
the plant. Under the proposed project,
Sludge will be composted at the Clarks-
town sanitary landfill site and land ap-
plied as a soil conditioner within Rock-
land County (see Figure 12).
IV. Detailed Description of Selected
Plans
Interceptors
The proposed project consists of the
Mahwah River Basin, Minisceongo Creek
Basin, and Phillips Hill Road-Conklin
Road interceptor systems and the Upper
A-10
Main Interceptor. The Mahwah River Ba-
sin is located in the western portion of
the sewer district and encompasses about
one third of the Town of Ramapo. The
Mahwah interceptor system will serve
eleven schools and an existing residen-
tial population of approximately 10,000
people. It will eliminate two existing
pump stations and three existing STPs.
As can be seen in Figure 7, it will con-
sist of seven interceptors: the Mahwah,
Pomona Heights, Wilder Road, Willow Tree
Road, Grandview Avenue, Viola Road and
Montebello Road interceptors. The in-
terceptor system will require seven pump
Stations and consist of 2.5 km (7.5 mi)
of gravity sewer ranging from 20 cmt (8
in) to 75 cm (30 in) in diameter and 0.9
km (2.8 mi) of forcemain.
The Minisceongo Creek Basin is located
in the northeastern portion of the Town
of Ramapo and encompasses two thirds of
the Village of Pomona. The Minisceongo
interceptors will serve eight hospitals
and schools and an existing population
of 2,200. It will provide for a portion
of the village which currently connects
to the Haverstraw STP to tie into the
RCSD No. 1 STP. This system will con-
sist of the Pomona, Mount Ivy North and
Summit Park interceptors (see Figure 8).
It will require three pump stations and
consist of about 9 km (3 mi) of gravity
line ranging from 20 cm (8 in) to 45 cm
(18 in) in diameter and 0.6 km (2 mi) of
force main.
The Phillips Hill Road interceptor will
provide service to a portion of the Town
A-11
of Ramapo and Clarkstown located east of
Palisades Interstate Parkway (see Figure
9). This interceptor will provide capa-
city for an existing population of
1,140. It consists of 1.5 km (0.9 mi)
of gravity sewers and. does not require
any pump stations.
The Conklin interceptor will provide
service to an existing population of 233
in the northeast corner of the Town of
Ramapo and the northwest corner of
Clarkstown (see Figure 9). This inter-
ceptor will require one pump station and
consist of 2.2 km (1.4 mi) of gravity
sewer and 0.6 km (.4 mi) of forcemain,
The Upper Main Interceptor will convey
flows from the western portion of the
sewer district to the RCSD No. 1 STP.
The interceptor is required to augment
the existing upper main interceptor
which, because of groundwater I/I and
future flows from western portions of
the district, will exceed its design ca-
pacity by 1,100 cu m p/d (3 mgd). The
proposed pressure main consists of ap-
proximately 3,050 m (9,350 ft) of 40 cm
(16 in) diameter pressure interceptor.
Collectors
The recommended lateral collection sewer
system projected by the Town of Ramapo
consists of approximately 186,600 ft
(55,890 m) of 20 cm (8 in) gravity sew-
er, three pump stations, 600 m (5,300
ft) of forcemain, 23 grinder pump units
and 960 m (3,200 ft) of lower pressure
main. Of the above 16,500 m (55,060 ft)
A-12
of gravity sewer and 170 m (440 ft) of
forcemain and one pump station have been
found to be ineligible for federal fund-
ing.
RCSD No. 1 STP Expansion
Following is a list of the principal
units which will be added or modified to
expand the capacity of the RCSD No. 1
STP to 8,500 cu m (25 mgd). These units
will be added directly adjacent to the
existing facilities.
1. Main pumping station modified by an
additional larger pump
y Aerated grit chamber
3. Six primary settling tanks
4. Air driven rotating biological con-
tactors (RBC) to provide secondary
treatment. In addition, existing
aeration tanks will be modified to
accept RBCs.
Sludge Handling Facilities
On-site sludge handling at the RCSD
plant will be accomplished by the addi-
tion of the following principle units.
l. Two gravity thickeners to thicken
Sludge from RBCs. The thickeners
will be enclosed to provide odor
control.
2. Conversion of existing secondary
digester to a primary digester.
A-13
30 m (90 ft) diameter unheated di-
gested sludge storage tank.
Containerized methane gas storage
450 kw generator for electricity
generation from methane gas utili-
zation.
Three belt presses for dewatering
sludge and two grit cyclone classi-
fier units for screening and sepa-
ration.
Dewatered sludge will be hauled in water
tight trucks to the Clarkstown landfill
sludge composting facility. The com-
posting site, which will use static-pile
composting, will be designed as follows.
he
Composting operations will occur on
concrete and asphalt pad covering
1.5 ha (3.5 a) of the site.
Landfilled material will be removed
prior to construction of pad.
Pad will be contoured so that
leachate will drain to retention
ponds.
The ponds will be sized to accommo-
date runoff resulting from a ten
year, 24 hour storm.
The ponds will discharge leachate
(via pumping) to 210 m (700 ft)
sewer connecting to RCSD No. 1 STP
for treatment.
A-14
6. Composting operation will be con-
ducted within enclosure with three
walls and roof. Covered compost
facility will have capacity to pro-
vide up to six months storage of
compost.
7 Grayel access road approximately
450 m (1,500 ft) will be construct-
ed.
Composted sludge will be applied as a
soil conditioner to designated lands in
the county. Potential outlets for com-
posted sludge include landscaping and
nursery operations.
Vv. Project Costs
The following are the approximate costs
associated with the design of sewage
collection, conveyance, treatment and
disposal facilities for RCSD No. 1 and
the Town of Ramapo.
Town of Ramapo Collectors:
Total Cost - $1,045,500
Eligible Cost - $689,000
EPA Grant (75%) - $858,630
RCSD No. 1 Interceptors, Pump
Stations, Forcemains, STP
Expansion and Sludge Handling
Facilities:
Total Cost - $4,577,380
Eligible Cost - $3,758,380
EPA Grant (75%) =- $2,858,630
A-15
The following are the estimated total
project costs for contruction of the
proposed facilities including the above
design costs.
Total Eligible
Cost Cost
Collectors $20,600,000 $13,185,000
Interceptors,
Pump Stations,
and Forcemains 31,000,000 30,310,000
STP Expansion
and Sludge
Handling
Facilities 68,389,000 67,101,000
TOTAL: $119,989,000 $110,596,000
The total annual user charges to resi-
dents within the Town of Ramapo is esti-
mated to be $308.00. The total annual
user charge to a resident within the
RCSD No. 1 service area will be approxi-
mately $100.00.
VI. Evaluation of Alternatives
No Action
The "no-action”" alternative consists of
the continued use of individual on-site
treatment systems in Ramapo as well as
the overloaded RCSD No. 1 STP and its
Sludge handling facilities. This alter-
native was rejected due to the existing
need for improvement of water quality
A-16
and alleviation of health hazards in the
service areas.
Collection System
Upgrading of on-site systems was not
considered feasible because of soil con-
ditions, high groundwater and shallow
depth to bedrock. A sewage collection
system is the most cost-effective alter-
native except in three small areas where
adverse topography makes grinder pumps
cost-effective.
Interceptors
Mahwah =- All of the six alternative
routings considered for the Mahwah in-
terceptor consist of a major interceptor
generally paralleling the Mahwah River
with secondary interceptors discharging
into the main interceptor (Mahwah). The
proposed routing was selected because it
minimizes secondary growth impacts by
limiting the service area of the inter-
ceptor as much as possible to those ar-
eas which are in need of sewers and to
which future growth is expected and
planned for. In addition, this alterna-
tive is set back from the Mahwah River
and thus avoids the construction impacts
associated with the other alternatives
that closely parallel the river. It is
also the least expensive of the six al-
ternatives.
Minisceongo - Of the two alternatives
considered to serve this area, the pro-
posed route (alternative 2) was found to
be most cost-effective and environmen-
A-17
tally sound. This alternative will
avoid much of the wetland and flood-
plain, and easements that would be re-
quired with alternative 1.
Phillips Hill Road - The original propo-
sal called for the placement of the in-
terceptor in the cul-de-sac between
Kingsland Drive and Buena Vista Road and
then following Kingsland Drive east.
Under this proposal the interceptor
would cut across a wetland at the end of
Kingsland Drive and connect into. and
follow Phillips Hill Road until Rolling-
wood Drive. The present proposal will
utilize existing laterals in Buena Vista
Road and Kingsland Drive that connect to
the Balter Road pump station. A gravity
interceptor will connect the pump sta-
tion to the Rollingwood Road cul-de-sac.
This route was selected because it
avoids wetlands, eliminates the Balter
Road pump station and was approximately
$60,000 less expensive than the next
least expensive alternative.
Conklin Road - Six alternative routings
were considered to serve the Conklin
Road area in the Town of Ramapo. Four
of the alternatives included placing
sewage lines in or adjacent to Buena
Vista Road in the Town of Clarkstown.
As discussed in Section VIII, residents
of Clarkstown opposed the presence of an
interceptor sewer in Buena Vista Road or
Saw Mill Road because of the potential
secondary impact to the undeveloped land
along these routings. A fifth alterna-
tive consisted of pumping sewage from
the Conklin Road area under the Pali-
A-18
“a
ew
sades Park interceptor. This alterna-
tive was rejected because it required
three additional pump stations and the
residents of Dogwood Lane objected to
the routing. The proposed alternative
which follows a route primarily through
the Town of Ramapo was found to be the
most cost-effective alternative.
Lake DeForest - An interceptor was pro-
posed to serve the Lake DeForest area,
The interceptor was rejected because of
primary and secondary impacts to wet-
lands, streams, active orchards and ag-
ricultural land, water supply, steep
slopes and secondary growth woodland and
because it did not meet EPA requirements
for eligibility. The proposed intercep-
tor is still planned for construction
with local funding.
Upper Pressure Main Interceptor - This
interceptor will parallel the entire
3,050 m (9,350 ft) length of existing
pressure interceptor which is located
adjacent to a railroad right-of-way. As
the right-of-way has been previously
disturbed, there will only be minor im-
pacts from the construction of his in-
terceptor.
RCSD No. 1 STP Expansion
A number of alternative sites were eval-
uated for the expansion of the RCSD No.
1 STP. These alternatives consisted of
the following: locating the expansion
facilities away from the immediate lo-
cation of the STP; building a second STP
at another location; and rearranging the
A-19
expansion facilities at the existing STP
site to minimize impact to wetlands ad-
jacent to the STP. The first two alter-
natives were rejected because of the ex-
tremely high cost, the greater manpower
and unit operations, and the additional
interceptors that would be necessary for
sewage conveyance to a new facility with
the alternatives.
Several alternative arrangements of the
STP expansion at the existing site were
evaluated to minimize impact to the wet-
lands that are located directly north
and south of the STP. Locating the new
secondary treatment unit to the east of
the STP in mixed hardwood area was re-
jected because of the large additional
cost (3.5 million present worth) of
pumping to this upland area. As the
west side of the STP is close to Route
303, expansion in this direction was not
possible. The original proposal of
placing the administrative building and
equipment garage to the north in a
flooded shrub wetland along with an ad-
ditional access road cutting through
steep slopes was rejected in favor of
the present proposal. This involves
placing the administration building, and
equipment garage in the hardwood area to
the east of the STP and eliminating the
additional access road. As with the
original proposals, the new treatment
units are located north of the existing
facilities (see Figures 10 and 1l).
Sludge Handling Facilities
Joint sludge facility with Orangetown
4 A-20
STP.
A detailed cost analysis determined that
cost savings for a RCSD No. 1 =- Town of
Orangetown sludge handling facilities
would not be significant when implemen-
tation schedules for joint and individu-
al alternatives were considered. It was
estimated that a joint facility would
require one additional year for imple-
mentation compared with individual al-
ternatives. Consequently both RCSD No.
1 and Orangetown decided it was in their
best interest to pursue individual
sludge handling alternatives.
Land Application
Land application of digested dewatered
sludge without composting was not conp-
sidered environmentally acceptable as
large quantities of filter cake would
have to be stored during portions of the
year when, for climatic reasons, land
application is not possible. Composting
in conjunction with land application was
selected because the composting opera-
tion can be carried out year round and
because compost can be stored for long
periods without adverse environmental
effects.
Composting Sites
Six composting sites were evaluated (see
Figure 12). The Route 303 industrial
site was rejected because of its proxim-
ity to office buildings, limited amount
of land, high land acquisition cost and
A-21
traffic problems. The site on Route 303
in Orangetown was eliminated because it
would require the loss of a large area
of wooded wetlands. In addition, the
small parcel of land that is not envi-
ronmentally sensitive on the site is
planned for future construction. The
Ramapo incinerator site was rejected be-
cause of the long travel distance to the
site and the proximity to residences.
Although three remaining sites were con-
sidered feasible for composting, the
Clarkstown landfill site was selected
because it represents the site with
least potential adverse impacts. The
Congers Lake site offers ample area to
locate, and is close to RCSD sewer
lines. However, extensive clearing and
a long access road over the Hackensack
River would be required. Under this al-
ternative, the Route 9W site was reject-
ed because it would require clearing a
heavily wooded area and is relatively
near homes and business.
VII. Environmental Consequences of the
Selected Plan
Collection Sewers
Approximately 90 percent of the collec-
tion system will be located in existing
roadways right-of-ways. Limited use of
rights-of-way will be necessary where
topographical constraints preclude road-
way routings and where land will be used
for pump station sites.
A-22
The use of rights-of-ways will avoid
long term impacts and minimize secondary
impacts. Temporary disruption of traf-
fic and noise related to construction
activity will be a short-term nuisance.
All routings through or adjacent to wet-
lands have been eliminated from the pro-
posed project. Where stream crossings
are necessary, the contractor will be
required to comply with New York State
Stream work standards. In addition, the
contractor will be required to follow
environmental specifications concerning
protection and replacement of trees and
erosion and sedimentation control.
Interceptors
Mahwah River Basin
Although a number, of modifications have
been made to the proposed routing, the
Mahwah interceptors will border and
cross wetlands, floodplain and steep
Slopes at various points. Between Bay-
ard Lane and Victory Road, the alignment
of the Mahwah interceptor has been
shifted to the east side of the Mahwah
River to avoid the very steep slopes on
the east side of the river. However,
between Victory Road and Hemion Road,
the interceptor will cross the river
twice and cross and border the wetland
along Route 202.
The Grandview Avenue interceptor will
also border and cross wetlands and
floodplains along Spook Rock Road and
A-23
Grandview Avenue between Carrol Drive
and Wesley Chapel Road.
The Viola Road interceptor will border a
small wetland and cross and floodplain
between Mile Road and Route 202. This
interceptor will cross an area of unde-
veloped land, potentially inducing de-
velopment in this area. No alternative
was available that would avoid these
secondary impacts.
The Montebello Road interceptor travers-
es a wetland between Robin Hood Road and
Nottingham Road. The routing has been
modified to move the alignment away from
the creek, steep slopes and wooded areas
as much as topographical constraints al-
low.
As discussed in Section VII-B, the con-
tractor will be required to follow a
number of special environmental con-
straints to protect wetlands along the
proposed route. As with the collectors,
the contractor will be required to use
construction measures to reduce erosion
and sedimentation, protect and replace
trees, and restore disturbed areas to
their original condition.
In addition, grant conditions are being
used to prohibit hook-ups to the pro-
posed sewer system from future develop-
ment in wetlands and floodplains.
Minisceongo Interceptors - Sewer cross-
ings of the south Minisceongo River will
be required north of the Pomona pumping
station and along M@ute 202 (east of
A-24
Camp Hill Road). The contractor will be
required to follow stream crossing stan-
dards to protect the stream and wetlands
located downstream.
The Pomona interceptor will parallel the
creek along Adele Boulevard between New
Hempstead Road and Scotford Lane. The
routing has been moved to the west side
of the creek to avoid steep slopes and
mixed hardwood on the east side. This
routing will traverse a flat brush area
before cutting to the east side of the
creek at Scotford Lane.
Phillips Hill Area - As discussed under
the alternatives section, the proposed
Phillips Hill interceptor alignment was
selected because it avoids impacts to
wetlands. Although this routing will be
designed to minimize impact to a small
woodland which it traverses, some trees
may have to be removed. The contractor
will be required to follow tree replace-
ment specifications.
Conklin Road Area - The primary impact
associated with the proposed routing is
the secondary impact of crossing a mixed
hardwood forest between the southern end
of Carteret Drive and Buena Vista Road.
Although the interceptor is sized at the
minimum possible diameter 20 cm (8 in),
it will contain sufficient excess capac-
ity to allow development of the wooded
area to hook up to it. Development of
this area is likely with or without sew-
ers as new residential development is
currently making large inroads into the
wooded area. Alternatives to the pro-
A-25
posed alignment which would avoid tra-
versing the wooded area by pdralleling
Buena Vista Road were opposed by the
Town of Clarkstown because of the secon-
dary impacts that such an alignment
would pose to the Buena Vista Road area.
RCSD No. 1 STP Expansion
The expansion of the STP will require
the following loss of wetland to the
north of the STP and mixed hardwood to
the east of the STP (see Figure 10).
Gross Area Area Taken By
(Within Existing STP Construction
Property Boundary)
(hectares) (acres) (hectares) (acres)
Reeds Sean - ae | 1.50 3.60
Flooded
Shrubs 0.58 1.30 0.18 0.43
Flooded
Deciduous
Tree -01 26 0.003 - 43
Wret
Meadow Lean 2.46 --- ---
Mixed
Hardwood 1.83 4.40 ota Leave
Approximately half of the reedgrass wet-
land to be taken by construction has been
disturbed by present construction activ-
ities at the plant site.
The expansion will also require that the
natural wetland drainage channel to the
east of the STP be replaced with a cul-
A-26
vert. As compared to the disturbance of
wetlands by the underground intercep-
tors, the proposed expansion will repre-
sent a permanent loss of wetland habitat
for wildlife in this area. As discussed
in the previous section of this report,
the cost of alternatives that would
avoid impact to wetlands (i.e., con-
structing new STP) were found to be pro-
hibitive. Of the alternative expansion
layouts considered, the proposed ar-
rangement was selected because it mini-
mizes the loss of wetlands.
Construction on the northern side of the
STP will pose potentially severe short-
term impacts to the Sparkill Creek which
traverses the northern edge of the site.
Clearing and grubbing could cause heavy
siltation of rivers and dewatering oper-
ation could seriously reduce the stream-
flow of the creek especially during per-
iods of low flow. As part of the spe-
cial environmental specifications, the
contractor will be required to restrict
clearing and grubbing to the minimum
easement, stay back from creek banks and
recharge the creek with filtered water
from the construction area.
Sludge Handling Facilities
Clarkstown Landfill Site - Composting
The site is located in the Hackensack
River Drainage Basin. The nearest major
tributary is Greenbush Brook, a Class
"C" waterway (suitable for fishing) that
runs north to south along the western
border of the landfill. A connecting
A-27
tributary to the north drains the com-
posting site. This tributary is several
hundred feet from the site and is des-
ignated a Class "D" waterway (suitable
for industrial or cooling uses). The
water assimilates and collects runoff
from the landfill and the urbanized ar-
eas along Route 303.
All effluent from composting operations,
including leachate from composting piles
and washdown water, will be collected in
a water retention pond and discharged to
a sanitary sewer on Greenbush Road. The
retention ponds will be sized to accom-
modate runoff resulting from the once in
10 year, 24 hour storm. Neither water
quality nor uses of adjacent waterways
will be adversely affected by composting
at the site.
The location of the composting facility
at the site will be compatible with the
adjacent use of the site for a sanitary
landfill. Since the area is presently
used as a waste processing area, a com-
posting facility will not alter the ac-
tual or perceived use of the site.
Potential Compost Application Sites
The compost market survey identified a
number of potential compost users in
Rockland County, such as landscapers and
nurseries. In addition, potential com-
post use as a cover material for the
Clarkstown landfill has been proposed.
Currently, no agricultural land is plan-
ned to be used for application of com-
A-28
posted sludge. Should agricultural land
be considered at a later time, sludge
applications would be limited to lands
used to grow field crops and application
rates would be subject to U.S. Depart-
ment of Agriculture guidelines for
Sludge application’ rates. Periodic
groundwater monitoring will be required
to assure that leachate is not contam-
inating the groundwater.
Water Supply
Almost 90 percent of the population of
Rockland County is served by the Spring
Valley Water Company which gets its sup-
ply primarily from Lake DeForest on the
Hackensack River, and a reservoir in
Stony Point and from an extensive
groundwater system. Because of a de-
crease in population projections over
the next 40 years, the water supply
which presently exists in the county
will be ade te into “the foreseeable
future. However, there are alternative
sites that are available for developing
new sources of water supply should the
need arise.
Under the proposed project, water that
has its origin in one of the river ba-
Sins in the sewer district will be
transferred to another basin when it is
treated and discharged. In addition to
household water, groundwater I/I enters
the sewers from all the basins. The ex-
isting and proposed sewer system
discharges the water from these basins
to the Hudson River.
A-29
The present interbasin transfers within
the sewer district have not been shown
to have a negative impact on the envi-
ronment through reductions of flow
streams. The proposed elimination of as
much I/I as is cost-effective will re-
duce such transfers to a minimum, pos-
sibly resulting in an overall reduction
in interbasin transfer even with the
proposed sewer system. Thus, the pro-
posed project will have no adverse im-
pact on water flows in the different
river basins.
Air Quality
The study area is within the New York
State designated Southern Tier East Air
Quality Control Region (AQCR).
At present, only, the National Ambient
Air Quality Standards (NAAQS) for photo-
chemical oxidants are being contravened
within the AQCR. A State Implementation
Plan has been prepared by New York State
which provides for the attainment of the
NAAQS within the AQCR. An analysis has
shown that the proposed project will not
by itself result in contravention of
NAAQS.
There will be localized dust and exhaust
emissions from construction equipment.
These will be mitigated by the proper
construction specifications. Operation
of the facilities should not result in
odors beyond the STP site.
Noise Levels
Noise levels will be high for short-term
A-30
periods (during construction), but will
be localized around construction sites.
The contractors will be respcrsible for
not exceeding the Occupational Safety
and Health Act (OSHA) standards for
noise exposure on a daily basis.
In conformance with the Advisory Council
of Historic Preservation Procedures, the
EPA must investigate the cultural re-
sources located within the project area
that would be affected by construction
of the proposed facilities. A cultural
resource investigation has shown that
there are no resources within the proj-
ect area which are on or eligible for
inclusion on the National Register of
Historic Places which will be affected
by the proposed construction.
Population and STP Design
The population of the planning area is
projected to increase from approximately
160,000 to 201,000 over the 20 year de-
sign period of the proposed sewerage fa-
cilities. The population projections
are based on recent development plans,
zoning, and a constraints analysis which
excluded environmentally sensitive areas
(such as wetlands, floodplains, agricul-
tural lands and steep slopes) from de-
velopment. These projections are
slightly lower than the population pro-
jections, prepared by the New York State
208 Water Quality Management Plan. The
increased capacity of the proposed STP
expansion is based on these population
projections for the service area.
Secondary Impacts
The proposed project may cause an in-
crease in the rate of development. How-
ever, except for the Viola Road inter-
ceptor, which conveys from the northern
portion of the district, the proposed
facilities provide sewers only in those
areas which are either developed or
where there is a strong potential for
development. As discussed under "Popu-
lation" the capacity of the STP is de-
signed only to handle flows from land
that is not environmentally sensitive.
In addition, grant conditions are being
used to prohibit the connections of fu-
ture development in wetlands and flood-
plains to the proposed facilities.
B. Steps to Minimize Adverse Effects
on the Environment
A NYSDEC permit will be require for con-
struction of collection and interceptor
system alignments crossing or parallel
to streams. Where permits are required,
all work in the vicinity of water bodies
must meet the New York State stream work
standards including specifications that
will insure no reduction or disruption
of stream flow which can endanger the
aquatic life or obstruct passage of
fish. Machinery must be operated from
the stream bank, not in the stream. Ex-
cept for stream crossings, all work must
be far enough from the bank that it is
not disturbed.
When the top of excavation is within ten
(10) feet of the top of any stream bank,
A-32
the Contractor shall provide protection
for the stream bank as approved by the
Engineer.
Erosion and Sedimentation Control
The Contractor shall, at the direction
of the engineer, use necessary methods
to minimize erosion from easements and
access roads, especially in stream or
watercourse areas. Right-of-way at sur-
face water crossings or. drainage ways
shall be protected by sandbagging, hay-
baling, mulch, or the use of jute or ex-
celsior blankets, as conditions require.
Methods of preventing erosion shall also
include berms, dikes, and other tempo-
Yary and permanent structures. Erosion
control methods shall be employed during
site clearing, construction of pipe-
lines, and at the time of final restora-
tion.
Air Quality
The major construction impacts will be
dust and exhaust emissions. Dust will
be controlled by water sprinkling and
sweeping of paved areas, and mulching on
unpaved areas. Natural materials, such
as chippings from on-site vegetation,
should be used for mulching whenever
possible. The use of calcium chloride
or petroleum products for dust control
will be prohibited.
Wetland Construction
Where construction must take place in or
A-33
adjacent to wetlands, the contractor
must adhere to the following environmen-
tal specifications.
Re
Prior to the start of construction,
fences and hay bales will be placed
around the edge of the construction
site that borders the wetland.
Metal cyclone fence must be used at
the STP site. All construction ac-
tivity will be limited to the area
behind the fence.
The original grading must be re-
stored in order to maintain the
original vegetation found there.
Manholes, where necessary in the
wetland, should be located as close
as possible to either end of the
wetland to reduce the length and
impact of the permanent access
road.
Impervious barriers should be
placed regularly across the trench
to prevent water flowing down the
slope of the line and draining ar-
ea.
NYSDEC and EPA must be notified at
least 48 hours in advance of con-
struction activity.
The culvert being used to replace
the swale must be of the same ele-
vation as swale to allow continued
wetland drainage pattern.
A-34
Tree and Shrub protection and
Replacement
No trees shall be cut without the per-
mission of the engineer or other des-
ignated authority. Trees not scheduled
for removal shall be carefully protected
from damage to bark by "boxing" with
snow fence of boardings. Where trees
are to be replaced, the replacement size
schedules shall be in accordance with
EPA-NYSDEC specifications.
Whenever excavation is to be performed
within the root zone of trees (normally
about the spread of the limbs), the con-
tractor shall prune damaged roots or
limbs over one inch diameter and prune
the tree to match the undamaged root
system. When the excavation is within
10 feet of trees over 38 cm (15 in) in
diameter, the contractor shall tunnel
under the tree.
The contractor will be responsible up to
and including a one year maintenance pe-
riod for the vegetation that has been
damaged or replaced during construction.
Special Grant Conditions \
To protect environmentally sensitive
areas from development the Federal con-
struction grants for this project will
include the condition prohibiting hook-
ups to the system from new development
located in floodplains and wetlands.
The following grant conditions will be
used:
A-35
The grantee shall submit to EPA and
the NYSDEC an approvable facilities
plan amendment including maps that
clearly delineate all specific va-
cant parcels of land within the 100
year floodplain as defined by the
U.S. Department of Housing and Ur-
ban Development (HUD), or within
wetlands as defined by the U.S.
Fish and Wildlife Service no later
than 45 days after grant accep-
tance. These maps must also show
which parcels had been developed
prior to date of issuance of find-
ing of no significant impact/envi-
ronmental assessment (FNSI/EA).
The grantee agrees that for a peri-
od of 50 years from the date of the
FNSI/EA no sewer hook-up or other
connections to the sewage collec-
tion system included in the scope
of this grant will be allowed or
permitted so as to allow the dis-
charge of wastewater from = any
building, facility or other con-
struction on any parcel of land
within any wetlands or within the
100 year floodplain, which land
parcel as of the date of the
FNSI/EA was undeveloped (i.e., upon
which no building, facility or
other construction had been erected
or placed) unless approved in writ-
ing by the Regional Administrator.
This condition is intended to bene-
fit any persons or private organi-
zation or governmental entity which
may have an interest in the
VIII.
A-36
avoidance of any future development
in the designated areas. Any such
beneficiary (who may otherwise have
standing to seek enforcement and
the right to begin such action in a
court of competent jurisdiction)
may seek to enforce compliance with
this condition in the courts of the
State of New York against the gran-
tees or any non-Federal person, or-
ganization, or entity subject to
this condition if notice of intent
to seek such enforcement is first
given to the EPA Regional Adminis-
trator, New York State Department
of Environmental Conservation, the
grantee and affected governmental
entities and if none of those so
noticed fails to initiate correc-
tive action within ninety days of
such notice.
If the facilities plan amendment
required under a. above delineates
any vacant parcels which will be
affected by this special condition,
the grantee will conduct a public
hearing within 60 days of submis-
sion of the facilities plan amend-
ment. The public hearing must be
preceded by a notice of 45 days,
during which time the facilities
plan amendment will be made avail-
able to the public. The public
hearing record will remain open for
30 days after the hearing to allow
for additional public input.
Coordination of Environmental
Review and Reference Documents
Consulted
A-37
Public Participation Program
Four public information meetings
were held in three locations in the
RCSD No. 1 relative to _ location,
alignment and service area for the
interceptors. One was held in
Orangetown concerning the STP ex-
pansion. As a result of these
meetings, major changes were made
in the alignments or service pro-
vided by the Mahwah River inter-
ceptor and the Conklin Road inter-
ceptor. In response to comments
from the residents of Orangetown
concerning odor control, new treat-
ment processes were reviewed with
respect to elimination of odors.
Review of the proposed plan result-
ed in the requirement that the com-
post facility be completely enclos-
ed for operational and odor control
reasons.
On January 28, 1980, a public hear-
ing was held at 8:00 PM in the
Clarkstown Town Hall Auditorium
concerning proposed RCSD No. 1 fa-
cilities. A number of questions
and objections were raised concern-
ing the proposed project.
The most discussed issue at the
hearing concerned existing and po-
tential odors at the RCSD No. 1
STP. The following is a partial
list of the measures that have been
A-38
and will be taken to deal with odor
control’‘at the STP:
he
2.
10.
Discontinuing use of Zimpro
oxidation unit.
Improved process and sludge
handling equipment and proce-
dures which will minimize sol-
ids recycled in the plant.
Covers over the existing and
proposed primary settling
tanks.
Covered air driven rotating
biological contactors which
will replace the present open
aeration tanks.
Odor control ventilation in
solids handling areas and im-
proved process control and in-
formation systems.
Aerated grit removal.
Covered and ventilated sludce
thickeners,
Prechlorination of influent
sewage.
Covered digestor feedbox and
overflow boxes.
Equipment redundancy will pro-
vide additional safeguards
against process component
failure.
A-39
The Hackensack Water company objec-
ted to the location of the compost-
ing site at the Clarkstown landfill
because of possible contamination
of groundwater or surface water.
As discussed in Section VII, the
composting facilities will be en-
closed on an impervious pad. It
will be contoured to collect runoff
in a water retention pond which
will discharge the runoff back to
the STP for treatment.
The water retention pond will be
sized to collect the runoff from
the entire compost site that would
be produced from a 10 year, 24 hour
storm. In addition, the covered
compost facility provides up to six
months compost storage.
A number of residents asked about
the possible relocation of the STP
and alternatives to expansion. Al-
though portions of the infiltra-
tion/inflow to the RCSD No. 1 STP
are planned to be removed, flows to
the STP due to I/I which it is not
cost-effective to remove and due to
the increased population, still
make expansion of the STP neces-
sary. The use of an alternate
treatment site was precluded by the
enormous cost that a new site (in-
cluding new conveyance facilities
and new outfall to river) would re-
quire.
Two residents questioned the inter-
basin transfer of water that will
A-40
occur with the proposed project.
As discussed in the environmental
assessment, the district is com-
prised primarily of the drainage
basins of three river systems: the
Hackensack River which drains to
the tidal Meadowlands, the Mahwah
which drains toward the southwest
to the Ramapo River and the Minis-
ceongo which drains north and then
east to the Hudson River. Water
that is discharged to the existing
and proposed system has its origin
in more than one river basin and is
used in others. In addition to
household wastewater, I/I enters
the sewers from all three basins.
The existing and proposed system
discharges water from these river
basins to the Hudson River. The
present interbasin transfers within
the sewer district have not been
shown to have a negative impact
through reduction of stream flow.
The proposed elimination of I/I
will reduce such transfers to a
minimum,
Several of the residents complained
that the opportunity to speak at
the public hearing did not occur
until such a late hour that they
had to leave before they had the
opportunity to be heard. In re-
sponse, the sewer district sent a
copy of the responsiveness summary
of the public hearing to all those
who signed up to speak but did not
do so. The sewer district invited
these residents to submit written
A-41
comments or raise questions con-
cerning the issues.
On July 30, 1980 at 8:00 PM a pub-
lic hearing was held in the town of
Ramapo Town Hall concerning the
proposed Ramapo collection sewers.
Several residents requested infor-
mation concerning the proposed sew-
ers that would serve them. No ob-
jections were raised to the proj-
ect.
Federal State and Local Agencies
Consulted
il. Agencies Consulted:
- U.S. Fish and Wildlife
Service
- New York State Department
of Environmental Conser-
vation
- U.S. Environmental Pro-
tection Agency
y Documents Consulted:
- New York State Water
Quality Management Plan
for Rockland County
- Wastewater Facilities
Plans -
a. Rockland County Sew-
er District No. 1
Interceptors, Force
Main and Pump
269:101
A-42
Station, Volumes 1
and 2
Rockland County Sew-
er District No. 1
Sewage Treatment
Plant
Rockland County Sew-
er District No. 1
Sludge Management
Report
Ramapo Extension to
Collection System
A- 43
;
‘
WESTCHESTER COuectt’
LOCATION PLAN
Figure I
A- 44
a
* MOUNT S.-M y :
* > ve mate ~~ ' 3
t - — i tee “hae te eo ! ' *\
b ast vs = { ers 18s -4
’ - . Par ae” €- > FY"
I ens: . ae Agtt | A
i, Cr en Cees
poem -' he ST. Oe j 4 ¢:
4 a8 ae
er
i NAS 7 hae its Mr ivy SOUT. oe lee
aro “ a {|g FORCE mann P
? j ‘
fo, VILLAGE os} Pt
wT wy s6uTa % :
POWONA
eo) TAC oA
4
:
' md
: POMONA... HEIGHTS §
I. 2
pied
iP rc ee , Satay |
b Fb eaerecutt = 35 *\
vf fc rng j ~~ a ' \?- eid hoe 3 Tatar cS? 5.
By Uses “tee Ue \ IS$CCN°
EY Ree ee "4 tet PHOMONA
< jf = % a a h® ne “7! eoeee a7} .¢
Preset Name Mg Sa I ee tg font
<*> 4 “. . wt =
s! , . : '¢ reant rt = 7° -\
ey een : ;
. manne ‘aommnaommnnnanaite mt OS Oe | A .
Fig ye ay EY é
it é! \ i ‘6 t
wens \ any ~ Sovran? @s
= =—- ERS EO
“| | |! _powona -.. :
gunetasou; ~ Son MTERCEFIOR SUNiNZI-
* : Powein af 8
“ 3 FORCE mans! PA
fou = - Pv t
oH og) ott
; hy) :
¢ A o~ ct
. te Ol we L
= Onn. 0ge* t
c _ "facet -/ L
t . be) 4 tc
LEGEND 3A: whe. | é ¢
: py 4 t
Proposed late: cote, - - %
— sewers aT ” see *
_-—-——— Proposed lateral gt ote , i .
sewers ineligible ‘ss '.
===" for federal funding “4:
Tuwts Of Remapo Proposed Collection Sewers
Figure ¢
A- 45
LEGeENd
Proposed latera!
sewers
Proposed lateral
sewers ineligible
for federa) fund)
Town ut Remayo Proposed Collection Sewers
Fi jure 3
A- 46
cs 8, , 7
ee a ; ra 3%
LEGENO
Proposed latera!
a sewers
---——— Proposed lateral
Sewers ineligible
——— = for federal funding |
Tow of Ramapo lrovused SeweqeCol lection System
s
A- 47
reer gat
f f ?
} ( i;
TR eg Jae na oo” LEGEAw
oy, . 7
eee Nf
Proposed laterg)
-ewers
Proposed lateral
Sewers tneligiole
for federal fundi:
m Hlection Sewer
-a% ys Town of Ruma Pr pong Co
— # bigure
A- 48
Y :
wae ¥
“ete aij) rs ls
‘yer rele
q Gip §Onate-.
rel t starcacy
ar}
7 fas Mr hawe (eee the
4 :
“fi
: :
’ )
4 uC
~~ ?
J SMCK LLY OM 1
|
f
u p
7
Towm GAP COUN ‘ Py wea
“ SPOOK ROCK PU ‘ Ors . pt .
U3 SOUTH PUMHING STATION? Panag —P i iy \] 9 x
cj i a I %
te <—e il ¢f
ipiolals alot tT Sag) thee’
“4:
{| ge
Nemes.
AAs?
P
LEGEND
— Proposed later
Sewers
we mmm PPOSed Letor.
SQwers Ineligus
tor fevere) fur
Town of Remepo Propused Cuollention Sewers
r 'gure 5
A- 49
-
}
* - ~~
~ ee
, ~ v "
ye
,
4
a ae |
? voor
/ ] go O19 ht
(yh - sis Ba
, wiv ae To 2 ao Sanp
Se ea >
Weer ey ate teen pion eo :
% “ela tom!
‘ ‘ ~ s ‘ ’
’ ‘ 3 Soe eh t0.400, }
/ bd er
'.. S a 9 ) cantanahd
be “J Ness ‘scer
r feat 2, * 7
) ~ 0Aharg, “ows, ~.
Te ee ee ee oe al - “)-
Ce ee ne ee ee Le AAS A
~~ gr Nee ty Se ty.
” . 1 qsee e
eo? ; < e. Pe ~ ec
gf ' » ‘ px a
%, > ae ease
CAS te EN A as wae i oy
jt t TAS is mel — .
4 ‘Ja
ry
7 4
“4 ’
, 4
< 7
ween te Mee mee Sa am
/ A
“~ P i .
reer . ie *
an) wes ber mre +) ae
fim. +
Vere meer
io
fewmrinn at
sn
mite iE ms
mee
a
\
e
oe ret
woth ae i oie
, 6 et Swe:
Matwalr Basin Interceptor Sewer System
RCSD No. |
Fieure /
A- 50
Bie ESEPIRR wien TREAPIE IS AIT
(TO 3€ Ure TEO)
7 5 00% &
ear wwe MRT .. we
mite «le a aig
_——
—- 20. taiaiasonlal —_- mart) | -
WD ka (C® Bi SA\\ ——
- $8 ue? wreut aff Vie east asece ee ragit
— * S (TC GE SScgt eS EO)
aaa Ah.
l - j ie by oe " tat wy, ‘VE \ Y w bs i
PY Wee —- : LN ory a \ >.
72) row rf -' ee i “Nl tie Ae
rw ii \ NN \"} } ad
‘ ist
| if : = ie" als . ria w/w
: q 2 ‘ie a ee a S = STA —_ , WA
‘ est HAPPY “AL
CF
TREATMENT RANT "19s Pyeee
5 5 tif ae O1SSTANALIES! Le suit
-* —— ee \
;
Siae
(MtERCEP TCA Ae
NN
| sl ebes tev
“5 ExG% SLOTFe aC as 2 85 4 4
{* 4 . re
‘A ee <§ra — rig NE fu q _ aa R 2
wT) = ta d B abe — “at z . { -. =“ ee
err eta as
i
U . s Sud |
Fy 3 Ae are ae Pe
{/> LxisT ‘ve: ts 0 Wid, \l, =
=:: tae = Pi : - oa: ©
ey i wéconnee ES) =f : ee :
4 X : bind “ »> on :-
Rtas a i al :
" ei i . ~~
. ra ae a re a= we
~ i! me me *%. +:
‘ Se ' \ ‘ ;
ae Sais roposed RCSO fo. I Int
mm 8 -— S| Sewers
a ate es ’ Minisceongo Basin Sy
es
a . \
1 eee ‘ . Figure 8
9 ¢ 2
——_——_—
A- 51
CONCKLIN RO.
FORCE MAIN
i"
PrULLIPS Hick
“3 INTERCEPTOR -
6's EXISTING TO
PUMPING ST.
Lae TO BE ABA
Sycamore 8 eB
E TION INTERCEPT.
BUENA VISTA PUMPING \
STATION INTIKCEFTOR —————= #! . E .
BUENA VISTA PS. (FxIST ovate Boy ar srcauone PS
LEGEND MAF (Exist. - orstericr)
——>— EXISTING FACILITES
oome{peeee PROPOSED INTERCLPTORS, STAGE 3 HOCKL AND COUNTY SEWER DIY
— p—— PROPOSED FORCE MAINS , STAGE 3 at eee ee
o PROPOSED PUMPING STATIONS, PHILLIPS HILL RO.-CONCKLIN
STAGE 3 INTERCEPTOR SCWER:
iiiemtehes TOWN PACILINICS Ta ue AcuRES Figure 9
ev Toes Ger len?
ME. 7s oO’
-
——-—
weeTee ~\ a | eererr yy e +4 oastte } 3 a
\ Re acca cok md P ‘
tote F _ "oe » salle « © wal a ‘Ma ii
ln hte be as ob ; . -
4 “S Chae aA, \ Ther a
wn setae H " iethiele: § “te
efits tyne! Meat . — ‘
Ben tese
Mined
Hardwoods
=-
Existing RCSD No. 1 STP and Adjacent Environment
Figure 10
oY
zs
t
ac wo & ;
!
'
—
- -
\
>
-— =, i
“Sh '
>
. ra TS |
. caneammentng Gp 9 ag aoa amen t » |
‘ : CG. el et ee ene 4!
a _- -! . | . Y.
; : : <=.
= eens is t j rt 4 ee
i owe Sion | | ‘ ‘ ae et ~~
a eee. “ower bs \ | ' | \ i
~“ Yt oo - ore —- «+! ! ' i | : i Th ee aco wee —
. , H i .
‘ a ; }
Se ee — ' -
- eal | ts -—---— : ) | | ‘
nantes H . f ' ) ” ' | tower Convene a
° —_— - -
~~ ae ae i ‘ r | | | w 8 joe corerercr et! Bd ow
3 * Spee : eae A ie
——— -* : a ras a H
; : . -—>
ne =a ‘ = =? orn -
* ie ee Sat ee
. aad s ee % ! ' — —
° eo 6 ae > .
~
fae
— =
‘
-
ou m=
® «©
ae’ wh aete
28 Shi Note Mote heniaitinds
o = ————— - -
.
oer
tot’)
BAS°CaswEe hese orr-.° *.5%°
* cre ate
PROPOSED Ye: 37°
Figure Il
Gast Cepy Available
=v
€S
os
A- 54
eee
Alla
RAMAPO ——~ 3
INCINERATOR
SITE
} 202 |
mamard
wu
<—
Gs)
03 INOUSTRIAL |
ETOWN
mms m ees
POTENTIAL COMPOSTING SITES
Figure 12
END OF DOCKET
This is a copy of a public record, reproduced as it was published. It is not legal advice, and it may not be the version a court would rely on. Check the official source before you cite it.