Petition for Writ of Certiorari — California Energy Co. v. Public Utilities Commission

Supreme Court brief1991

Ask Donna

What actually matters in this document.

Text

Ou + JUL 17 19%

In the Supreme Cobre OF THE CLERK

OF THE

United States

OCTOBER TERM, i991

CALIFORNIA ENERGY COMPANY, INC.,

Petitioner,

VS.

PUBLIC UTILITIES COMMISSION OF THE STATE OF

CALIFORNIA and SOUTHERN CALIFORNIA EDISON COMPANY,

Respondents.

PETITION FOR WRIT OF CERTIORARI

TO THE CALIFORNIA SUPREME COURT

BAKER & MCKENZIE

JOHN R. SHINER

N. GRANT MARTIN

Thirty-Seventh Floor

777 South Figueroa Street

Los Angeles, California 90017

(213) 892-7300

Attorneys for Petitioner

California Energy Company, Inc.

July 16, 1991

BOWNE OF SAN FRANCISCO. INC. + 190 NINTH ST. + S.F..CA 94103 + (415) 864-2300

QUESTIONS PRESENTED

Whether Respondent California Public Utilities Commission

(“Commission”) denied Petitioner’s constitutional right of due

process, under the 14th Amendment to the United States Consti-

tution, by rescinding, altering or amending its own final orders and

decisions without notice or opportunity to be heard? 28 U.S.C.

§ 1257(a).

PARTIES

The parties to this Petition are listed in the caption. Petitioner,

through its wholly owned subsidiary, Coso Hotspring: _Intermoun-

tain Power, Inc. is a genera! partner in Coso Energy Developers.

The other general partner is Caithness Coso Holdings. Petitoner,

through its wholy owned subsidiary, Coso Technology Corpora-

tion, Inc., is a general partner in Coso Power Developers. The

other general partner is Caithness Navy II Group, L.P. In

addition, the parties who actively participated in the proceedings

below were Southern California Edison Company (“SCE”), Luz

International Ltd. (“LUZ”), the Commission’s Division of Rate-

payer Advocates and the California Energy Commission.

TABLE OF CONTENTS

Page

en...) , orb a.eces arbeure naeeewouere. i

Tee oko a sa ony 66 ib eee deen een eee i

I o's 0.4. 66.9040a eek sede sae eee ii

ND 0 0'0'00856sSnbieinveeee iii

PE sc ccéccvescecedcetdevenedeetel Tete l

PI hoon cceccenedecedudsécerceeneseeraceuee 2

ES oc oududenduynuevawe shane ci 2

os a vis avaeaeueaaenads 3

Reasons For Granting The Writ....................... 10

The Commission’s Failure To Afford Petitioner Notice That

It Intended To, And Could, Alter The 1985 Decision

Denied Petitioner Constitutional Procedural Due Process 11

I

Notwithstanding The Breadth Of Its Perceived Powers, The

Commission Was Compelled By The Fourteenth Amend-

ment To Afford Petitioner Adequate Notice And A

RR ie rrr po yee 13

II

The Notice Afforded Was Inadequate To Apprise Petitioner

Of The Nature Of The Proceedings Below............ 14

A. Petitioner Was On Notice Only That Costs Would

Be Allocated According To The 1985 Decision .... 14

B. Petitioner Prepared For And Participated In The

Proceedings On The Reasonable Assumption That

The 1985 Decision Was Final and Conclusive ..... 17

C. Notwithstanding The Limited Scope Of The Hear-

ing, The Commission Rescinded The Per Se Bulk

Line Rule And Thus Altered The Decision In Viola-

Can Ur Fe 6 eect dvcacedadiciecens 18

III

The Commission’s Rescission Of The Per Se Bulk Line

Rule, Without Adequate Notice To Petitioner, Rendered

Petitioner's Opportunity To Be Heard Meaningless .... . 19

GN as 6p cds hcccseneeveaenee oveseetereetess 20

PO o.o ve cdecddcusetseiesine Le 21

iii

TABLE OF AUTHORITIES

Cases

Boddie v. Connecticut, 401 U.S. 371, 91 S. Ct. 780, 28 L.

cee epee cctnere ews ss

Bowman Transp., Inc. v. Arkansas-Best Freight Sys., Inc.,

419 U.S. 281, 95 S. Ct. 438, 42 L. Ed. 2d 447 (1974), reh.

denied, 420 U.S. 956, 95 S. Ct. 1340, 43 L. Ed. 2d 433

ES ELGG nl eas bakin boa 8d coe nese

California Trucking Assn. v. Public Utilities Com., 19 Cal.

3d 240, 137 Cal. Rptr. 190, 561 P.2d 280 (1977) ......

Cleveland Bd. of Educ. v. Loudermill, 470 U.S. 532, 105 S.

eB ee

Consumers Lobby Agains: Monopolies v. Public Utilities

Com., 25 Cal. 3d 891, 160 Cal. Rptr. 124, 603 P.2d 41

td aacknn wig Kec 0p wie hs bape 0 00

Giaccio v. State of Pennsylvania, 382 U.S. 399, 86 S. Ct.

ee oe

Hannah v. Larche, 363 U.S. 420, 80S. Ct. 1502, 4 L. Ed. 2d

1307, reh. denied, 364 U.S. 855, 81 S. Ct. 33, 5 L. Ed. 2d

is od veacweeeusbeneeis

Hewitt v. Helms, 459 U.S. 460, 103 S. Ct. 864, 74 L. Ed. 2d

etc as ck een weakea ser tsecreraees

Morgan v. United States, 304 U.S. 1, 58 S. Ct. 773, 82 L.

rd Dove cei e cubase shaveuvdess

Mullane v. Central Hanover Bank & Trust Co., 339 U.S.

306, 70 S. Ct. 652, 94 L. Ed. 2d 865 (1950) ..........

Paul v. Davis, 424 U.S. 693, 96 S. Ct. 1155, 47 L. Ed. 2d

405, reh. denied, 425 U.S. 985, 96 S. Ct. 2194, 48 L. Ed.

i I ee

Pennsylvania v. Ritchie, 480 U.S. 39, 107 S. Ct. 989, 94 L.

Tee cel Ls ou Wadkea rae es exe's

Page

16

14

18

13

iV

TABLE OF AUTHORITIES

CASES

Page

People v. Western Air Lines, Inc., 42 Cal. 2d 621, 268 P.2d

723, appeal dism‘d, 348 U.S. 859, 75 S. Ct. 87, 99 L. Ed.

a se Ra ey tol rd a a A 2, 16

Withrow v. Larkin, 421 U.S. 35, 95 S. Ct. 1456, 43 L. Ed. 2d

pp SR ED Se BS Dee Ab eure hye ae a 13

California Public Utilities Commission Decisions:

Decision 84-08-031, 16 CPUC 2d 5 (1984) ........... 4

co AE SS a passim

Decision 87-05-060, 24 CPUC 2d 253 (1987) ......... 6, 15

Constitution, Statutes and Rules

United States Constitution:

Amendment XIV Section] ........................ 3,5

United States Code:

We I OTOL oo ci ccc cccccevscescccees i, 3

ee a i

California Public Utilities Code:

Te ora Sod oy a. oc cae dae ewes even passim

LON so daa kus deus woe ere saree eee passim

PS a 0-65 Ss Sh auoe cote eure een 12

California Public Utilities Commission General Orders:

RY ee Une Ae ager > eee eee 7

No.

In the Supreme Court

OF THE

United States

OCTOBER TERM, 1991

CALIFORNIA ENERGY COMPANY, INC.,

Petitioner,

vs.

PuBLic UTILITIES COMMISSION OF THE STATE OF

CALIFORNIA and SOUTHERN CALIFORNIA EDISON COMPANY,

Respondents.

PETITION FOR WRIT OF CERTIORARI

TO THE CALIFORNIA SUPREME COURT

Petitioner prays that a writ of certiorari issue to review Com-

mission Decision 90-09-059, entered September 12, 1990, and for

which the California Supreme Court denied review on April 18,

1991.

OPINIONS BELOW

The opinion of the Commission (D.90-09-059, the “Decision’’)

has been reported at 37 CPUC 2d 413 (1990). A copy of the

Decision and order denying review by the California Supreme

Court are attached as Appendix A and C, respectively.

2

JURISDICTION

The Decision' of the Commission is dated September 12, 1990.

The Commission’s order denying rehearing and reconsideration is

dated December 19, 1990, and was mailed December 27, 1990.

(Appendix B.) The California Supreme Court denied review on

April 18, 1991.”

The jurisdiction of this Court is invoked under 28 U.S.C.

§ 1257(a).

RELEVANT STATUTES

UNITED STATES CONSTITUTION

Amendment XIV Section 1. Aji persons born or naturalized

in the United States, and subject to the jurisdiction thereof, are

citizens of the United States and of the State wherein they reside.

No State shall make or enforce any law which shall abridge the

privileges or immunities of citizens of the United States; nor shall

any State deprive any person of life, liberty, or property, without

due process of law; nor deny to any person within its jurisdiction

the equal protection of the laws.

‘The Commission acknowledged that Petitioner, “argues that the

Commission cannot alter or rescind the 1985 Decision in this applica-

tion, because to do so would violate the notice and hearing requirements

of PU Code Section 1708 and the Fourteenth Amendment of the U.S.

Constitution.” (Decision at A-24.) Petitioner first raised this argument

in a motion for summary judgment before the proceedings commenced,

and asserted this position at each subsequent stage including in its

Petition to the California Supreme Court.

> A denial of review by the California Supreme Court of a Commis-

sion order, even without an accompanying opinion, constitutes a final

adjudication on the merits. People v. Western Air Lines, Inc., 42 Cal. 2d

621, 630-631, 268 P.2d 723, appeal dism'd, 348 U.S. 859, 75 S. Ct. 87,

99 L. Ed 2d 677 (1954).

3

CALIFORNIA PUBLIC UTILITIES CODE

Section 1708. Modification of orders or decisions by commis-

sion; Effect

The commission may at any time, upon notice to the parties, and

with opportunity to be heard as provided in the case of com-

plaints, rescind, alter, or amend any order or decision made by it.

Any order rescinding, altering, 0: amending a prior order or

decision shall, when served upon the parties, have the same effect

as an original order or decision.

Section 1709. Final orders as conclusive

In all collateral actions or proceedings, the orders and decisions of

the commission which have become final shall be conclusive.

STATEMENT OF THE CASE

Petitioner California Energy Company, Inc. produces electric-

ity from geothermal power plants. SCE is a utility regulated by

the Commission,’ transmitting and distributing both electricity

generated from its own plants and from alternative energy produc-

ers such as Petitioner. Under the Public Utilities and Regulatory

Policies Act of 1978 (“PURPA”), 16 U.S.C. §§ 824a-3, et seq.,

SCE is required to provide for interconnection with Petitioner,

and to compensate Petitioner for the power produced under

standard contracts previously executed between SCE and Peti-

tioner. PURPA describes energy suppliers such as Petitioner as a

“qualifying facility” or “QF.”

On March 20, 1989, SCE filed with the Commission an

Application (A.89-03-026) for a Certificate of Public Conve-

nience and Necessity to obtain permission to construct “a new,

> “The California Public Utilities Commission (CPUC) regulates the

service and rates of more than 25,000 privately-owned utilities and

transportation companies serving California including privately-owned

gas, electric, local and long distance telephone, radio-telephone, water

and steam heat utilities and sewer companies; railroads, buses, trucks,

and vessels transporting freight or passengers; and carloaders and pipe-

line operators.” (1989-90 Commission Annual Report, p. 3.)

4

double circuit, 220 kilovolt (“kV”) electric transmission line

connecting SCE’s Kramer Substation with its Victor Substation

in the Mojave Desert” (“Proposed Line”). (Decision at A-1 )

The Proposed Line was needed, among other reasons, to facilitate

SCE’s acceptance of energy supplied by Petitioner and Luz

International Ltd. (“Luz”), a similarly situated QF. The Com-

mission believed that part of its review process included a deter-

mination of what installation costs, if any, would be allocated to

Petitioner.

The applicable rules for such cost allocation were earlier

announced by the Commission in Decision 85-09-058 (“1985

Decision”), which was an outgrowth of proceedings initiated in

1984 (“1.84-04-077”) to examine limitations on various utilities’

transmission systems (including SCE’s) affecting QF develop-

ment. (Decision at A-19.) Among the issues sought to be

resolved was a methodology for determining what cost responsi-

bility, if any, QFs shouid bear for “bulk transmission line up-

grades.” (Decision 84-08-031, 16 CPUC 2d 5 (1984).)

1.84-04-077 was intended to be a generic proceeding in which

all parties potentially affected might participate in resolving the

issue of cost responsibility for transmission lines. In fact, it

expressly was provided that these issues, “either in the near future

or longer run, affect other California electric utilities and QF

development statewide,” and would have “policy implications”

for all electric utilities subject to the Commission’s jurisdiction.

(1.84-04-077 at p. 1.) The Commission ordered an investigation

“into the potential limitations of the transmission system in

California” for the purpose of determining, inter alia, “[w]hether

an electric corporation or QFs should have sole responsibility to

pay the costs of upgrades... or how such costs should be allo-

cated between them.” (1.84-04-077 at p. 4.)

“Luz and SCE previously had reached agreement regarding what

portion of interconnection costs would be allocated to Luz. Notwith-

standing such agreement, Luz joined Petitioner during the proceedings

below, as did the California Energy Commission, in asserting the

applicability of the prior Commission orders and decisions addressed

herein.

5

In September 1985, the portion of the 1.84-04-077 hearings

bearing on cost allocation was completed and the Commission

issued its findings and conclusions in the 1985 Decision.

The 1985 Decision established the following uncontroverted

rules with respect to cost allocation, which then were published

and thus made applicable to those within the Commission’s

jurisdiction:

“A QF is responsible only for interconnection and other

facilities that have no system-wide benefits and are solely

beneficial to the QF. This approach eliminates the need for a

difficult cost allocation among the various users of a trans-

mission facility.

“... Bulk transmission lines by definition have system-wide

benefits. And nearly all area lines probably have some

system-wide benefits. Thus, QFs will assume cost responsibil-

ity only on the rare occasion that an area line lacks any

perceptible system-wide benefit.

*“... We have not yet adopted consistent energy reliability

criteria for all utilities. The cost of transmission service is

just one piece to the puzzle of properly valuing QF power.

Thus, for the moment, we will allow utilities to follow the

general principle that as long as a transmission facility has

system-wide benefits, the utility's ratepayers are responsible

for the prudent and reasonable cost. The QF is responsible

only for interconnection cost and other special facilities

which have no system-wide benefits. Refinement of this

principal must await for our determination in the long-run

avoided cost proceedings.”

(Emphasis added, Devision at A-20-21.)

On February 20, 1990, Petitioner filed a motion (essentially for

summary judgment) asserting, inter alia, that based upon the

Commission’s earlier orders, it could not be charged with cost

responsibility and that not to follow the prior orders would deprive

Petitioner of its right to procedural due process guaranteed by the

14th Amendment to the United States Constitution. (Decision at

A-4.) Further, it argued, the 1985 Decision made clear that

application of the rules contained therein, “eliminated the need

6

for a difficult cost allocation among the various users of a

transmission facility” (see p. 5, supra), which was precisely what

the proceedings contemplated were designed, in part, to accom-

plish. Petitioner's motion relied primarily upon the applicable

rules of cost allocation announced in the Commission’s earlier

1985 Decision, and sought an order that if the Proposed Line were

a bulk transmission line, no costs could be allocated to Petitioner

in conformity with the 1985 Decision.

Because no “refinement” of the principles adopted in the 1985

Decision has yet taken place,° the “system-wide benefits” ap-

proach, including the per se bulk line rule announced in the 1985

Decision, had been relied upon by Petitioner (both in raising

capital for its projects and during the proceeding below) as the

test in effect for cost allocation of interconnection facilities.

Nevertheless, on March 5, 1990, the Administrative Law Judge

(“ALJ”) assigned to the proceedings denied Petitioner's motion

by summarily concluding that, “[t]he issue of whether or not the

1985 decision controls is for the Commission to decide when it

issues its final decision in the case.... Now, there is still a

lingering, broader question, is this a generic proceeding in which

the Commission will undertake a general study of the cost

allocation ‘ssue in an attempt to craft a formal rule. And I think

we can say with a fair amount of confidence that no, this is not

that type of proceeding.” Petitioner requested the ruling be

certified to the full Commission for an interim appeal, which also

was denied on March 19, 1990 (Decision at A-4), leaving the

parties to proceed without any notice of what standard would be

applied, the precedential effect of the 1985 Decision or the

* Petitioner also relied on a Conclusicn of Law contained in Commis-

sion Decision 87-05-060, a 1987 decision which reaffirmed the 1985

Decision’s cost allocation rules, by providing, “[t]he approach taken in

D.85-09-058 is the best available for allocating cost responsibility to

OFs....

* Indeed, it was incumbent upon the Commission to initiate such

proceedings; until termination of those proceedings, the 1985 and 1987

pronouncements were specified to continue in effect.

7

ultimate conclusions of the Commission reflected for the first

time in the Decision.

Beginning on March 19, 1990, hearings were held to explore,

among other things, issues of public necessity, environmental

impact and cost allocation.

Petitioner reiterated the applicability of the per se bulk line rule

and presented uncontested evidence through its expert witness

that the Proposed Line would be a “bulk” transmission line.

SCE’s expert witness agreed and no evidence was advanced to the

contrary.

Based on this showing, Petitioner argued that the entire cost of

the Proposed Line must be paid by the ratepayers, as dictated by

the 1985 Decision and reaffirmed in 1987. (See footnote 5,

supra.)

Following the March hearings, the ALJ issued a proposed

decision on June 15, 1990, which allocated cost responsibility of

21% (approximately $11 million) to Petitioner, 44.8% to Luz (per

the Luz/SCE agreement, see footnote 4, supra) and 34.2% to the

ratepayers.

The full Commission thereafter considered the entire matter

and, on September 12, 1990, issued the Decision which essen-

tially adopted the results, and much of the reasoning, contained in

the ALJ’s proposed decision.

” In addition to testifying as to the “bulk” rating of the Proposed Line,

substantial evidence pertaining to each of the eight system-wide benefit

criteria articulated in the 1985 Decision was submitted. For example,

Petitioner maintained that simply by satisfying the requirements prereq-

uisite to the issuance of a Certificate of Public Convenience and

Necessity, the Proposed Line, by definition, exhibited system-wide

benefits. The Commission’s General Order No. 131-C provides that a

Certificate is contingent upon:

... this Commission having first found that said facilities are

necessary to promote the safety, health, comfort, and conve-

nience of the public, and that they are required by the public

convenience and necessary.

(Emphasis added. )

8

The Decision itself represents an extraordinary bit of convo-

luted logic, patently designed to release the Commission from the

effect of its 1985 Decision while providing notice to the Petitioner,

for the first time, of how it intended to treat the 1985 Decision.

The Commission began by assuring the parties that it had “no

intention of altering, modifying, or rescinding D.85-09-058 in this

decision” (Decision at A-27),* and that, “[a]lthough we are not

legally bound to apply D.85-09-058 in determining [ Petitioner's }

cost responsibilities, we are left with the question of whether it

nonetheless should form the basis for our decision. The simple

answer is yes.” (Emphasis added, Decision at A-37.)

1. Unlike the Decision, the 1985 Decision had no disclaimer

that, “[a]ny cost allocation which is determined to be reasonable

in this case is based on the facts and circumstances specific to the

parties and testimony in this proceeding and have no further

reaching application.” (Decision at A-27.)

2. Thus, Petitioner assumed that the 1985 Decision would be

“conclusive” as to this or any other collateral proceeding. (€ ali-

fornia Public Utilities Code 1709, see p. 3, supra.)

3. However, the Commission construed Section 1708 as al-

lowing it to reconsider, “its earlier policy positions, so long as

adequate notice and opportunity to be heard is provided to those

who will be affected.” (Decision at A-28.) Those “affected”

would include Petitioner and the entire QF community, none of

whom had prior notice of the Commission’s intent in this regard.

4. In a radical departure from its prior stance, the Commission

continued, “/e]ven if the 1985 decision set forth a clear recipe for

determining who should pay for the proposed project, we would

not be legally bound by that order in this proceeding. None of the

authority cited by the participants in this case stands for the

proposition that this Commission is precluded from reconsidering

its earlier policy positions, so long as adequate notice and opportu-

nity to be heard is provided to those who will be affected. Thus,

we are free to determine that the policy set forth in the 1985

*To do so would require a specific procedure outlined in California

Public Utilities Code § 1708, set forth on p. 3, supra.

9

decision is no longer appropriate as it affects the parties in this

case.”’ (Emphasis added, Decision at A-28.)

5. And finally, buried in the course of some 100 pages, the

Commission states, “[e¢]ither some 220 kV lines are not bulk...

or it simply is not true that all bulk lines have system-wide

benefits” (emphasis added, Decision at A-23), and it “cannot be

legally bound to apply the 1985 decision to the facts at hand.”

(Emphasis added, Decision at A-31.)

6. The effect, of course, was to rescind the 1985 Decision, of

which Petitioner had no notice until after the proceedings were

complete and the Decision issued, notwithstanding the Commis-

sion’s commitment not to do so. The Commission provided no

authority that it could alter its prior decisions, and utterly failed to

apprise the parties prior to commencement of the proceedings

that it claimed to possess such authority and, indeed, might alter

or modify its 1985 Decision.

By this capricious sleight of hand, the Commission wriggled

away from assessing the facts before it within the limitations of

the 1985 Decision. In essence, the Commission was uncomforta-

ble with the result obtained by applying the 1985 Decision, and

simply chose not to follow it. None of this artifice, however, was

imparted to the parties in advance and directly contravened

Sections 1708 and 1709.

Petitioner filed an application for rehearing on October 12,

1990, again arguing that Petitioner’s due process rights had been

violated by the Commission, which was denied December 19,

1990.

The California Supreme Court denied review on April 18,

1991.”

* The Commission now intends to press forward with what has been

identified as “Phase II” of these proceedings, over the objections of

Petitioner. In Phase II, the Commission will allocate additional costs

with respect to ancillary facilities associated with the project. Because

Phase II will be governed by the Decision, the federal questions

presented therein will not be re-examined. Under these circumstances,

10

REASONS FOR GRANTING THE WRIT

Daily throughout the nation, a variety of administrative bodies

act on requests from individuals and, in so doing, grant or deny

rights and obligations frequently with far reaching effect. Those

same tribunals, perhaps because of their number and the fre-

quency with which they adjudicate, operate at every level of a

person’s interaction with government and often with more impact

on the average citizen than the courts. Yet, because of their “lay”

character, they sometimes act arbitrarily, or in the furtherance of

interests never revealed to the participants, and are allowed to

function in a virtually uncontrolled manner knowing that in most

instances their actions will not be reviewed by, or challenged

before, a higher authority.

Administrative agencies, as with the Commission, are often

composed of political appointees who may arrive with a bias or

prejudice which seeps into the ultimate decision making process.

The danger, in such an environment, is that the rights of partici-

pants may be subsumed within the private agendas of those who

rule on matters before them, and who may feel compelled to

sacrifice the parties’ rights to what they believe to be a more

compelling interest. So common is this conduct, and so alarming

the actions outlined in this Petition, that it is critical for the Court

to declare that administrative bodies are not immune from the

Constitution and must act with certainty, not whimsy, insuring

that parties may rely with reasonable predictability upon a set

course.

Indeed, for example, this Court long ago recognized the impor-

tance of due process in administrative proceedings of a quasi-

judicial character, in which:

the liberty and property of the citizen shall be protected by

the rudimentary requirements of fair play. These demand “a

fair and open hearing,” essential alike to the legal validity of

the administrative regulation and to the maintenance of

public confidence in the value and soundness of this impor-

those questions are ripe for review by this Court. See Pennsylvania v.

Ritchie, 480 U.S. 39, 46, 107 S. Ct. 989, 996, 94 L. Ed. 2d 40 (1987).

ll

tant governmental process. Such a hearing has been de-

scribed as an “inexorable safeguard.”

Morgan v. United States, 304 U.S. 1, 14-15, 58 S. Ct. 773, 775, 82

L. Ed. 1129 (1938) (citations omitted). It is precisely, “the

maintenance of public confidence in the value and soundness of

this important governmental process,” which demands swift ac-

tion by this Court.

For this Court not to act, and act with dispatch, will be to

sanction by implication the continued deprivation of due process

within one of the nation’s most active judicial forums—adminis-

trative proceedings.

THE COMMISSION’S FAILURE TO AFFORD PETI-

TIONER NOTICE THAT IT INTENDED TO, AND

COULD, ALTER THE 1985 DECISION DENIED PETI-

TIONER CONSTITUTIONAL PROCEDURAL DUE

PROCESS.

The Commission is allowed by statute to alter its decisions, but

only after application of a procedure which affords notice of its

intention to do so. (California Public Utilities Code § 1708.) The

Commission specifically indicated that was not its intention in the

proceedings below. Thus, with its 1985 Decision in place, the

Petitioner had the right to rely upon it as conclusive. (California

Public Utilities Code § 1709.)

The Commission, however, without ever advising the parties

(and in the absence of any precedent that might have supplied

such notice), maintained:

1. the rules in the 1985 Decision would remain in effect until

a “broader proceeding, with more expansive notice to affected

parties” (Decision at A-27);

2. that although the Commission did not intend to alter the

1985 Decision, it was not legally bound to apply it (Decision at A-

31);

3. it was free to determine that the policy in the 1985

Decision was no longer appropriate (directly contrary to its

statement in the 1985 Decision that the principles cited would

12

remain in effect until further refinement in long-run avoided cost

proceedings) (Decision at A-28); and

4. it may depart from the rules embodied in the 1985 Deci-

sion in this case (despite unconditional language in the 1985

Decision and the California Public Utilities Code which give no

hint that the Commission is free to ignore its promulgated rules

on a case-by-case basis). (Decision at A-31.)

At issue is not some technical analysis of transmission line

interconnection, but whether the Commission, without notifying

those before it, will be allowed to render a decision, specified to be

a controlling rule affecting a multitude of parties, interests and

ratepayers, and then reverse itself by characterizing its earlier

pronouncement simply as “policy” which it is free to alter as

subsequent facts, in its singular view, may warrarit.

The essence of constitutional due process is raised by this

Petition. If administrative bodies are allowed to set standards for

those who may fit within their jurisdiction (and who act in

reliance upon such direction), only later to decree that what was

earlier said can be altered in a subsequent proceeding, there are

absent even the most fundamental of due process guaranties. Yes,

the parties had an opportunity to present their views, however

Petitioner was never advised the Commission would be altering its

earlier rules.

The case presented herein is a classic example of overreaching

and, indeed, is accentuated by the fact Commission action may be

reviewed only by the California Supreme Court,'° and so it is left

with virtually unrestricted license to ignore the constitutional

° California Public Utilities Code § 1759 provides, “[n]o court of this

State, except the Supreme Court to the extent specified in this article,

shall have jurisdiction to review, reverse, correct, or annul any order or

decision of the commission or to suspend or delay the execution or

operation thereof, or to enjoin, restrain, or interfere with the commission

in the performance of its official duties, except that the writ of manda-

mus shall lic from the Supreme Court to the commission in all proper

cases.

13

rights of those who appear before it.'' The California Supreme

Court has demonstrated a general unwillingness to accept matters

on appeal from the Commission, thus leaving the Commission to

act as it wishes.'*

Notwithstanding The Breadth Of Its Perceived Powers, The

Commission \. as Compelled By The Fourteenth Amendment

To Afford Petitioner Adequate Notice And A Meaningful

Hearing.

Not even the Commission can dispute that, “a ‘fair trial in a

fair tribunal is a basic requirement of due process’... [which]

applies to administrative agencies which adjudicate’? as well as to

courts.” Withrow v. Larkin, 421 U.S. 35, 46, 95 S. Ct. 1456, 1464,

43 L. Ed. 2d 712 (1975) (citations omitted). This Court has

consistently recognized that, when governmental agencies such as

the Commission act in a judicial capacity, “it is imperative that

those agencies use the procedures which have traditionally been

associated with the judicial process.” Hannah v. Larche, 363 US.

420, 442, 80 S. Ct. 1502, 1514, 4 L. Ed. 2d 1307, 1321, reh.

denied, 364 U.S. 855, 81 S. Ct. 33, 5 L. Ed. 2d 79 (1960).

'' This although paying lip service to the requirement that it, “must

constantly make its decisions within the constraints and opportunities

provided by the state and federal constitutions and applicable statutory

law but with an eye toward setting the course for the future.” (Decision

at A-30.)

'? Petitioner is informed that between the years 1950-59, 15 petitions

for review of Commission actions were granted by the California

Supreme Court, whereas in the 1980-1989 decade, only 7 such petitions

were granted. Over the past five years, the Commission issued approxi-

mately 900 decisions annually.

'? The Commission functions judicially, as it did in the proceedings

below, when it “acts as trier of fact, applies rules of law to those facts,

and renders a decision adjudicating vested interests in which there are

clear prevailing and losing parties.” Consumers Lobby Against Monopo-

lies v. Public Utilities Com., 25 Cal. 3d 891, 908, 160 Cal. Rptr. 124,

134, 603 P.2d 41 (1979).

14

The “essential requirements of due process” are notice and an

opportunity to be heard. Cleveland Bd. of Educ. v. Loudermill,

470 U.S. 532, 546, 105 S. Ct. 1487, 1495, 84 L. Ed. 2d 494

(1985). The Constitution requires that “notice” be:

reasonably calculated, under all the circumstances, to apprise

interested parties of the pendency of the action and afford

them an opportunity to present their objections.

Mullane v. Central Hanover Bank & Trust Co., 339 U.S. 306,

314, 70 S. Ct. 652, 657, 94 L. Ed. 2d 865 (1950). The Constitu-

tion further provides that the “opportunity to be heard” consists

of:

“an opportunity... granted at a meaningful time and in a

meaningful manner,” . . . “for [a] hearing appropriate to the

nature of the case.”

Boddie v. Connecticut, 401 U.S. 371, 378, 91 S. Ct. 780, 786, 28

L. Ed. 2d 113 (1971) (citations omitted).

The Commission utterly failed to afford Petitioner these “es-

sential requirements of due process” by rescinding the per se bulk

line rule without adequate notice and hearing.

The Notice Afforded Was Inadequate To Apprise Petitioner Of

The Nature Of The Proceedings Below.

Certainly, as the Commission argues, Petitioner was given

notice and a hearing; but that notice, as the Commission con-

cedes, did not apprise Petitioner that the scope of the proceedings

would include the rescission or alteration of the Commission’s

prior orders and decisions promulgating the per se bulk line rule.

As such, the procedures followed by the Commission in depriving

Petitioner of its property rights were constitutionally inadequate.

A. Petitioner Was On Notice Only That Costs Would Be

Allocated According To The 1985 Decision.

Because SCE is required to provide for interconnection with

Petitioner, the Commission believed that part of its review pro-

cess included a determination of what installation costs, if any,

15

would be allocated to Petitioner. The 1985 Decision set forth the

applicable standards for such cost allocation, including the per se

bulk line rule.

Petitioner had an absolute right to expect that the scope of the

hearings, as they related to Petitioner, would be limited to

application of the 1985 Decision (including the per se bulk line

rule) to the facts addressed during the proceedings. Petitioner had

no notice (and could not reasonably have anticipated) that the

scope of the proceedings would be expanded to encompass rescis-

sion or alteration of the 1985 Decision.

First, Petitioner could not reasonably have expected that the

1985 Decision would not be applied, because that Decision, by its

very terms, was made applicable to the cost allocation issues in

the proceedings below:

“Thus, for the moment, ... [t]he QF is responsible only for

interconnection cost and other special facilities which have

no system-wide benefits. Refinement of this principal must

await for our determination in the long-run avoided cost

proceedings.”

(Emphasis added, Decision at p. A-21.) No such determination,

as yet, has been made in the course of any long-run avoided cost

proceedings.

Second, the Commission reaffirmed the applicability of the cost

allocation methodology in 1987. Petitioner, therefore, was entitled

to rely on the applicability of the 1985 Decision in the wake of

that ruling, which stated, “[t]he approach taken in D.85-09-058

is the best available for allocating cost responsibility to QF’s....”

(Decision 87-05-060, Finding of Fact No. 22, 24 CPUC 2d 253

(1987).) The Commission affirmed the applicability of the 1985

Decision’s cost allocation rules. The proceedings in question

began only two years later and nothing occurred in the interim

which served to change the existence or application of the

Commission’s rules for cost allocation.

Third, the State of California has enacted a statutory frame-

work, California Public Utilities Code §§ 1708 and 1709, which

mandates the applicability of the 1985 Decision to the proceed-

16

ings below. Section 1709 applies, on its face, to the 1985 Decision

because that Decision is an order or decision of the Commission

which had become final. Moreover, the proceedings below clearly

were collateral to the 1985 Decision—the 1985 Decision estab-

lished the overall cost methodology applicable to all subsequent

QF interconnections until such time as the Commission could

reconsider the entire matter in the long-run avoided cost proceed-

ings. Under Section 1709, then, the 1985 Decision, including the

per se bulk line rule, was conclusive as to the parties. See People

v. Western Air Lines, Inc., supra, 42 Cal. 2d at 630.

Section 1708 also provides a method by which the Commission

may rescind, alter or amend its prior orders and decisions, “upon

notice to the parties, and with opportunity to be heard as provided

in the case of complaints.” Like Section 1709, Section 1708

applies to the 1985 Decision because that Decision is an “order or

decision made by” the Commission. Indeed, Section 1708 pro-

vides the exclusive method by which the Commission is able to

rescind, alter or amend its prior decisions, including the 1985

Decision. See California Trucking Assn. v. Public Utilities Com.,

19 Cal. 3d 240, 245, 137 Cal. Rptr. 190, 193, 561 P.2d 280

(1977).

Accordingly, Petitioner had a statutory right to rely upon the

applicability of the 1985 Decision, until reevaluated by a pre-

scribed method, and could not have remotely foreseen that the

scope of the proceedings below would be expanded, or essentially

converted, into a Section 1708 procedure allowing for the rescis-

sion or alteration of the per se bulk line rule.

Fourth, the ALJ specifically represented that the 1985 Decision

was applicable and refused to certify the question to the full

Commission for clarification or stay of the proceedings pending

the long-run avoided cost proceedings. The ALJ specifically

stated that, “the 1985 Decision is applicable te our consideration

in this case,” and unequivocally ordered that the scope of the

proceedings would not encompass a generic reevaluation of the

cost allocation issue.

Because the ALJ nevertheless denied Petitioner's summary

judgment motion, Petitioner requested the matter be referred to

17

the Commission on an interim appeal to clarify the Commission’s

position. That request was denied. This, in the face of the ALJ’s

determination that it would be left to the Commission to decide

the application, if any, of the 1985 Decision. Petitioner again

could not possibly have expected that the hearing on the cost

allocation issue would be expanded to include a rescission or

alteration of the 1985 Decision or the per se bulk line rule.

Further, the Commission certainly was free to conduct its long-

run avoided cost proceedings first, resolving whatever ambiguities

it determined to exist in the 1985 Decision, thereafter applying its

conclusions to matters at hand.

Fifth, even the Commission concedes the notice afforded was

insufficient to apprise Petitioner that the scope of the hearings

would include rescission or alteration of the 1985 Decision:

We have no intention of altering, modifying, or rescinding

D.85-09-058 in this decision. While it may be appropriate to

reexamine some of the assumptions behind that decision or

to explore in more detail how it should be implemented,

those questions should be addressed in a broader proceeding,

with more expansive notice to affected parties.

(Emphasis added, Decision at A-27, footnote omitted.)

B. Petitioner Prepared For And Participated In The Proceed-

ings On The Reasonable Assumption That The 1985 Deci-

sion Was Final And Conclusive.

Petitioner, then, was on notice on/y that costs would be allo-

cated in the proceeding below according to the 1985 Decision.

Clearly, Petitioner did not have notice that the scope of the

hearing, which was neither convened nor conducted pursuant to

Section 1708, would involve the rescission or alteration of the per

se bulk line rule. Based on such notice, Petitioner made a simple,

uncontroverted showing at the hearing that the Proposed Line

would be “bulk” in nature and, accordingly, urged the Commis-

sion to allocate the entire cost of the Proposed Line to the

ratepayers in accordance with the 1985 Decision, which the ALJ

stated would apply and which Petitioner had an absolute right to

expect would apply.

,

18

C. Notwithstanding The Limited Scope Of The Hearing, The

Commission Rescinded The Per Se Bulk Line Rule And

Thus Altered The Decision In Violation Of Section 1708.

Instead of applying its previously announced cost allocation

rules, the Commission rescinded the per se bulk line rule ex-

tracting approximately $11 million from Petitioner.

The Commission declared that the per se bulk line rule was too

ambiguous to apply and, therefore, refused to apply it—a de facto

rescission of the rule. (Decision at A-37-38.)'* By refusing to

apply its own rules regarding the cost methodology which the

1985 Decision mandates will be in effect until long-run avoided

cost proceedings are conducted, the Commission effectively re-

scinded those rules without due process of law.

The Commission’s position that it merely was “reconsidering

its earlier policy positions,” rather than rescinding the per se bulk

line rule, is unmistakable mockery. It is well-established that the

Commission’s characterization of its conduct deserves no weight

on review by this Court:

[b]Joth liberty and property are specifically protected by the

Fourteenth Amendment against any state deprivation which

does not meet the standards of due process, and this protec-

tion is not to be avoided by the simple label a State chooses

to fasten upon its conduct or its statute.

Giaccio v. State of Pennsylvania, 382 U.S. 399, 402, 86 S. Ct.

518, 520, 15 L. Ed. 2d 447 (1966). Labeling an established rule

“ambiguous” and refusing on those grounds to apply it, is tanta-

mount to rescission; and a rescission of the per se bulk line rule is

clearly an alteration of the 1985 Decision.

'* Additionally, although the Decision purports to undertake a system-

wide benefits analysis, it also holds that the criteria for that analysis as

set forth in the 1985 Decision are too ambiguous to apply. (Decision at

A-38.)

19

The Commission’s Rescission Of The Per Se Bulk Line Rule,

Without Adequate Notice To Petitioner, Rendered Peti-

tioner’s Opportunity To Be Heard Meaningless.

By expanding the scope of the hearing without providing

adequate notice, the Commission rendered Petitioner’s opportu-

nity to be heard meaningless. Petitioner prepared for and partici-

pated in a hearing that could be reasonably anticipated only to

include the determination of facts and application of the 1985

Decision, including the per se bulk line rule, to those facts. The

Commission, however, changed the rules mid-course and failed to

notify Petitioner. This Court has stated that:

[a] party is entitled, of course, to know the issues on which

[the] decision will turn and to be apprised of the factual

material on which the agency relies for decision so that he

may rebut it.

Bowman Transp., Inc. v. Arkansas-Best Freight Sys., Inc., 419

U.S. 281, 288 n.4, 95 S. Ct. 438, 443 n.4, 42 L. Ed. 2d 447

(1974), reh. denied, 420 U.S. 956, 95 S. Ct. 1340, 43 L. Ed. 2d

433 (1975). Without any knowledge of the theory upon which the

issues would be viewed or evaluated, Petitioner was denied fair

notice of the standard by which its evidence might be judged.’

'* Indeed, Petitioner has a property interest, sufficient to invoke due

process protection, in the Section 1708 procedure because of its

mandatory nature. See Paul v. Davis, 424 U.S. 693, 710-711, 96 S. Ct.

1155, 1165, 47 L. Ed. 2d 405, reh. denied, 425 U.S. 985, 96 S. Ct. 2194,

48 L. Ed. 2d 811 (1976), and Hewitt v. Helms, 459 U.S. 460, 471-472,

103 S. Ct. 864, 871, 74 L. Ed. 2d 675 (1983) (While the “mere fact

[of] a careful procedural structure” does not alone amount to an interest

requiring due process protection under the Fourteenth Amendment, the

mandatory nature of the procedures, coupled with “substantive predi-

cates” or criteria “demands a conclusion that the State has created a

protected ... interest.”) (Citations omitted.)

20

CONCLUSION

1. Our country is increasingly governed by administrative

regulation, a trend of probably long duration.

2. The wisdom or caprice by which such regulation is admin-

istered is of vital importance to the efficacy of government and the

best interests of its citizens.

3. The proceedings below present a vivid example of regula-

tion by sophistry rather than by law, specifically, in the absence of

notice to the parties, the pretense of retroactive conversion of the

agency’s own established rule, specified as definitive and dependa-

ble, to some sort of flexible “policy,” alterable at will.

4. Here then is a distinctive opportunity for the Supreme

Court to speak directly to the thousands of state and federal

agencies concerning the responsibility entrusted to them for

probity and consistency in the enforcement of law.

Dated: July 16, 1991

Respectively submitted,

BAKER & MCKENZIE

JOHN R. SHINER

N. GRANT MARTIN

Attorneys for Petitioner

California Energy Company, Inc.

4’ » wield A

b

Sar OM

i «

> te i * a

\ eae t se 2 * ‘ >

, ; sae ; ae | eer rs ~ rs eS he pe

: +

- ee > vie ; o 5, ' ;

i) > % “5 x my 3 erg SF ”

bs * % rr hay j

¥ r Le ae r po

ee a7

7 4

+ ——— : =

a .

* * a

7

5 .

< . ‘J ’

me f -

* » ¢

. ‘ -

a

i

_ m

.

F-

°

—— ~~

.

é

Appendix A

Decision 90-09-059

September 12, 1990

BEFORE THE PUBLIC UTILITIES COMMISSION

OF THE STATE OF CALIFORNIA

In the Matter of the Application of Southern California Edison

Company (U 338-E) for a Certificate that the Present and Future

Public Convenience and Necessity Requires or Will Require

Edison to Construct and Operate a 220 kV Double-Circuit

Transmission Line Between the Kramer Substation and the

Victor Substation in San Bernadino County, California.

Application 89-03-026

(Filed March 20, 1989)

Richard K. Durant, Carol B. Henningson, James M. Lehrer,

Carol A. Schmid-Frazze, and Michael D. Mackness, Attor-

neys at Law, for Southern California Edison Company,

applicant.

Messrs. Jackson, Tufts, Cole & Black, by William H. Booth,

Joseph S. Faber, and Evelyn K. Elsesser, Attorneys at Law,

for Luz Partnership Management, Inc. and Luz Interna-

tional, Limited; Messrs. Baker & McKenzie, by John R.

Shiner and Gordon F. Dickson, Attorneys at Law, for Cali-

fornia Energy Company, Inc.; Dick Ratliff, by David Mund-

stock, Attorneys at Law, Gary C. Heath and Al McCuen, for

the California Energy Commission; Messrs. Roberts and

Kerner by Douglas K. Kerner, Attorney at Law, for Indepen-

dent Energy Producers’ Association; and Roger Peters,

Douglas A. Oglesby, Kathleen B. Welsh, Attorneys at Law,

and Gary G. Gauthier, for Pacific Gas and Electric Com-

pany; interested parties.

Jason Zeller, Attorney at Law, for the Division of Ratepayer

Advocates and Jo Anna Bullock, for the Commission Advi-

sory and Compliance Division.

; i

Index

Subject Page

ie eek soo oe o.0-6) 64 0a 8 A-l

lL. SW idee een d 60s 64406 $0608 8 n8¥. A-|l

rR ae A-2

Sane RN I ES gg cc ence cccsenes A-5

IV. The Need for a New Transmission Line........ A-7

V. Description of the Proposed Project ........... A-9

VI. Cost Caps and Cost Estimates for the Proposed

ee aes Cewe bao ate anceacns ee ve A-11

Te A-12

ceric cd scccccedseses A-15

VII. Ratepayer Cost Responsibilities ............... A-16

A. The SCE/Luz Agreement ............... A-18

B. Proposals for Allocating the Remainder of the

SE A-18

C. D.85-09-058 and Its Significance.......... A-19

1. Is the Decision Clear on its Face? ..... A-21

2. Is the Decision Binding? ............. A-24

a. Positions of the Parties........... A-24

i a igs bo ono 004006 A-27

3. Cal Energy’s Claims of Reliance on the

ERG A-31

4. Should D.85-09-058 Be Applied In this

SON alae edu eke scenrccens A-37

D. System-Wide Benefits................... A-37

1. The Lack of Clear Criteria ........... A-38

BE te BID. coe cco cccess A-38

3. Providing for Future Growth.......... A-42

4. System Security and Reliability ....... A-43

5. Emergency Support ...............-. A-45

6. Tramsler Capavility ................-. A-46

7. Firm Resources at System Peak Condi-

eee eee Pupeareskseeexks A-47

S. CeO . gn cece cevese A-48

9. QF Generation and Better Air Quality.. A-48

10. Conclusions to be Drawn About System

Ae a a ee A-50

E. Aliocation of Project Costs............... A-52

Subject Page

F. Cal Energy’s Obligation to Pay its Share ... A-56

Viti. Environmental Considerations ................ A-57

A. PUBPUPREON GE GRP EME occ ccc cccuses A-57

DB. Peg occ occteccnccceess A-58

©. ARBRE I vo cass ccs vccccccecss A-59

D. Environmental Impacts.................. A-60

|. Qs obi 66s kasdnaeeaes A-60

2. TRGHORICRD RROSOUICOS.. 0... cc cccc cscs A-60

D. . Sieh as bess ddessscaees A-61

4, FR erpccccccdeneecuces A-62

a — ERE I CR EE A-63

6. Paleontological Resources ............ A-63

1. QR ao pice carscvecccce> A-63

8. Comparison to Alternative Corridors ... A-63

E. Comments on the DEIR................. A-64

F. Mitigation and Mitigation Monitoring ...... A-68

EX. Prem Be tee tees cee ec ess tp cces es A-70

A. Motion of DRA to Admit Additional Evi-

dence Related to Exhibit 48.............. A-70

B. Motion Re Supplemental Brief of Luz Inter-

eR eS ree Pee rr eC eee A-71

C. Motion of SCE to Establish Phase II of A.89-

03-026 to Determine Cost Allocation of In-

terconnection and Integration Facilities Not

dg ke errr A-71

a Og Re ee rs Serr A-72

Cometh OF BAW ois cnceecdeteeee ee A-84

GH distorts seuckudsepee aetna ekahar A-88

a Fe errr ee ete Ra A-91

A-|l

OPINION

I. Summary

In this decision, we grant a Certificate of Public Convenience

and Necessity (CPCN) to the Southern California Edison Com-

pany (SCE or Edison) for the construction of a new, double

circuit, 220 kilovolt (kV) electric transmission line connecting

SCE’s Kramer Substation with its Victor Substation in the

Mojave Desert. The CPCN also includes related facilities at the

Kramer, Victor, and Lugo Substations needed to handle the

power to be transmitted over the new line.

The line is needed to facilitate the delivery into the SCE load

center of electricity from two types of small qualifying facilities

(QFs) located in the Mojave Desert: geothermal power plants

developed by California Energy Company, Inc. (Cal Energy),

and solar thermal power plants developed by Luz International

Limited (Luz). Under state and federal law, SCE is required to

provide for the interconnection of these generating units with the

SCE electric system and to pay the QFs for the power they

produce under the terms of standard contracts offered by SCE

and agreed to by the QFs.

In this decision, we also determine how the costs of the

proposed project will be allocated. Luz’s cost obligations will be

governed by an agreement which it has undertaken with SCE,

under which Luz will be responsible for 44.8% of the project cost.

Cal Energy will be required to pay for 21% of the cost of the

project. The remaining 34.2% of the cost will be borne by SCE’s

ratepayers.

As a condition for the receipt of the CPCN, SCE will be

required to undertake numerous mitigation measures, designed to

limit the impact of otherwise significant and potentially significant

effects which would stem from the construction and operation of

the new facility. In keeping with recent Commission practice,

SCE will be required to pay for a third-party mitigation monitor-

ing program to be managed by the Commission’s Advisory and

Compliance Division (CACD). The mitigation monitoring staff

will oversee SCE’s implementation of the mitigation measures

and other activities required in this decision.

A-2

II. Procedural History

SCE filed its application for a CPCN and the accompanying

Proponent’s Environmental Assessment (PEA) on March 20,

1989. The scheduled operating date for the proposed project is

September |, 1992, with construction planned to begin Septem-

ber 1, 1991.' The application was accepted for filing on April 20,

1990.

A meeting was held in the City of Adelanto on July 26, 1989, to

determine public concerns related to the scope of the Environ-

mental Impact Report (EIR). The alternative transmission route

proposed for this project travel through and around the City of

Adelanto. On August 3, 1989, a prehearing conference was held

in San Francisco. The Draft EIR was distributed to interested

parties and places of public access in the vicinity of the project on

November 30, 1989. The Draft EIR indicated that written com-

ments could be filed no later than January 17, 1990. On that date,

a Public Participation Hearing was held in the City of Adelanto.

The second prehearing conference was held in Adelanto on that

date as well.

In the meantime, other events had occurred which affected the

scope of this proceeding. On November 17, 1989, SCE and Luz

signed an agreement (SCE/Luz Agreement), which is discussed

in greater detail below. Generally, the agreement allocates be-

tween Luz and SCE’s ratepayers costs related to the proposed 220

kV line and other interconnection and integration facilities. Spe-

cifically, Luz agrees to pay 44.8% of the cost of the proposed

project. Cal Energy, the other QF developer seeking use of the

proposed 220 kV line, has not entered into a cost sharing agree-

ment with SCE, although negotiations continued while this case

was pending. SCE asked that the Commission approve the

agreement with Luz as part of its review of the application for a

CPC&N. Both SCE and Luz filed testimony in support of the

agreement.

' Pursuant to the SCE/Luz Agreement signed after the filing of this

application and discussed below, Luz would construct the transmission

line with the goal of having it in operation before the end of 1991.

| ~

Division of Ratepayer Advocates’ (DRA) testimony, released

on December 19, 1989, included a recommendation that the

SCE/Luz Agreement be rejected. The essence of DRA’s position

was that there are no apparent system benefits to be derived from

this line and that under such circumstances the full cost of the

line should be borne by the QFs. On January 8, 1990, SCE and

Luz filed a joint motion asking the Commission to declare that it

could approve the SCE/Luz Agreement without considering the

system benefits issue. The California Energy Commission (CEC)

filed a Staff Prehearing Conference Statement on January 18,

1990, which included comments in support of the motion. DRA

responded to the motion on January 19, 1990 and Luz filed an

additional response on January 22, 1990.

Under the Permit Streamlining Act (Government Code Sec-

tion 65950) the Commission has one year from the date that the

application was filed to approve or disapprove the project. If the

Commission fails to act within that time frame, the project could

be deemed approved (Government Code Section 65956(b)). The

one-year deadline for this project was April 20, 1990. Since the

evidentiary hearings were scheduled to begin on January 22, 1990,

SCE and Luz acknowledged that the pendency of the joint

motion might delay resolution of the application. This is because

SCE and Luz expressed a desire to file rebuttal testimony on the

issue of system benefits, if the motion were to be denied. Govern-

ment Code Section 65957 allows for one extension of the ap-

proval/disapproval deadline for a period of up to 90 days with the

consent of the public agency and the applicant. Since it was likely

that any necessary rebuttal hearings could not be held until

March, SCE requested a 90-day extension. We concur with this

request, which results in a final decision deadline of July 20, 1990.

At the hearing held January 22, 1990, the assigned administra-

tive law judge (ALJ) denied the joint motion. Hearings to

consider evidence relevant to the issue of system benefits were set

to begin March 5, 1990. Luz was given a deadline of February 6,

1990 for the filing of rebuttal testimony on the subject of system

benefits. SCE and DRA were given until March 20, 1990 to file

their rebuttal on that subject. In addition, SCE and Cal Energy

were instructed to notify the Commission by February 6, 1990 as

A-4

to whether or not a cost allocation agreement between those

parties had been achieved. On that date, the parties reported that

no agreement had been reached. The parties were directed to file,

by February 20, 1990, testimony proposing the appropriate alloca-

tion of transmission line costs among SCE and Cal Energy.

On February 20, 1990, in addition to distributing its written

testimony, Cal Energy filed a motion which, in effect, sought

summary judgment on the issues of system benefits and cost

allocation. On February 26, 1990, the CEC filed a Motion for

Declaration of Applicable Law which complemented the Cal

Energy motion. Subsequently, SCE and DRA responded to the

motions in writing.

In addition, Luz raised a discovery matter concerning the

timeliness of SCE’s responses to Luz data requests related to the

system benefits issue. In a telephone conference, the parties

agreed to a schedule for the completion of discovery. Luz indi-

cated that the timing of discovery would make it unable to

prepare for cross-examination in the further hearings set to begin

on March 5, 1990 and requested a delay of the evidentiary

hearings. As a result, hearings on March 5, 1990 were limited to

oral argument of the pending Cal Energy and CEC motions. On

March 5, 1990, both motions were denied. Cal Energy requested

that the March 5 rulings be certified to the full Commission for

interim appeal. On March 19, 1990, that request was denied.

Evidentiary hearings were held on March 19, 20, 21, 22, 26, 27,

and 28, 1990. On the last day of hearings, the proceeding was

submitted, pending receipt of late-filed Exhibit 48 (addressing

business relationships between Luz and SCE and between Cal

Energy and SCE other than those stemming from the standard

offer agreements) and final briefs. The ALJ issued a ruling on

April 18, 1990 which, among other things, admitted Exhibit 48

into evidence. The exhibit is comprised of copies of four contracts

signed by SCE and its affiliates and by either Cal Energy or Luz

with certain portions redacted by SCE under a claim of confiden-

tiality. On April 20, 1990, DRA filed a motion requesting that all

of the redacted portions of the contracts be admitted into evi-

dence and that Exhibit 48 be supplemented with selected materi-

als from Exhibit 87 in Application (A.) 88-02-016. Concurrent

A-5

opening briefs were filed on April 16, 1990 and reply briefs were

filed on May 1, 1990.

Comments on the Proposed Decision were filed by SCE, DRA,

Luz, Cal Energy, and IEP. Some changes have been made to this

decision in response to comments. The CEC moved for accept-

ance of a late filing of its Opening Comments. According to the

motion, the CEC inadvertently neglected to file the comments,

although they were mailed in a timely manner to all parties. DRA

opposes the motion not only because the comments were not filed

in a timely manner, but because they substantially exceeded the

prescribed page limit and consisted largely of reargument, instead

of focusing on factual and legal error. The motion is denied,

primarily due to the CEC’s failure to comply with Rule 77.3 of

the Commission’s Rules of Practice and Procedure which limits

the scope of comments to a proposed decision.

Ill. The CPCN/CEOA Process

Two different regulatory schemes define this Commission’s

responsibilities in reviewing requests for the approval of new

electric transmission projects. Public Utilities (PU) Code Section

1001, et seq. states that a utility must receive a CPCN from the

Commission before it can begin the construction of a new line.

Public Resources (PR) Code Section 21000 et seq. (CEQA)

requires that the CPUC, as lead agency for this type of project,

prepare an EIR assessing the environmental implications of the

proposed project for its use in considering the request for a

CPCN.

The CPCN requirements go beyond a determination that a new

project is necessary. Before granting a CPCN, the Commission

must consider an analysis of the financial impacts of the proposed

project on the utility’s ratepayers and shareholders. The Commis-

sion must review the expected cost of the project and for those

projects estimated to cost more than $50 million, it must set a

cap, Or maximum amount which can be spent by the utility on the

project without seeking further Commission approval. In addition,

the Commission has a statutory obligation, even in the absence of

A-6

CEQA, to give consideration to the following factors as a basis for

granting any CPCN:

1. Community values.

2. Recreational and park areas.

3. Historical and aesthetic values.

4. Influence on the environment.

CEQA requires the preparation of an EIR where there is

substantial evidence that a project may have a significant effect on

the environment. The determination as to whether or not an EIR

must be prepared is to be made by the lead agency, which is also

responsible for the preparation and certification of the EIR. The

lead agency is the governmental body with primary authority over

the proposed project. For transmission lines that would carry

power from a thermal generating facility to the first point of

interconnection with the utility system, the CEC is the lead

agency. For all other transmission lines, such as the one proposed

here, this commission is the lead agency.’

In preparing the EIR, the lead agency must consider the full

range of alternatives to the proposed project, including the alter-

native that there be no new project at all. The lead agency must

identify all significant and potentially significant impacts of the

proposed project, identify the mitigation measures available to

lessen those impacts, and determine whether those measures

would reduce the impacts to an insignificant level. If it is

determined that the project will still have a significant impact on

the environment even after all reasonable mitigation measures are

applied, the CPCN must be accompanied by a statement of

overriding consideration explaining why the project should still be

approved. In any event, the lead agency cannot approve the

CPCN until it has certified that the Final EIR is complete. The

? Although the Commission’s statutory jurisdiction includes all trans-

mission lines that are part of the integrated utility system, the CPUC

has chosen to limit its review to those lines that are designed for

immediate or eventual operation at any voltage in excess of 200 kV. See

General Order 131-C.

ooo oem dill

A-7

permit that is finally issued must be conditioned on completion of

the adopted mitigation measures.

IV. The Need for a New Transmission Line

Cal Energy has constructed its BLM and Navy 2 facilities at

China Lake in the Mojave Desert. They have a combined net

capacity of 150 megawatts (MW). These units are located

approximately 43 miles north of the Kramer Substation. Cal

Energy contracted with an SCE affiliate for the construction cf a

220 kV line to SCE’s Inyokern Substation where the conductor

loops around the substation and is strung on the formerly vacant

side of a series of SCE towers which carry the line down to the

Kramer Substation.

Luz has constructed and brought on line its Solar Energy

Generating Station (SEGS) Unit VIII at its Harper Lake facility

in the Mojave Desert. Each SEGS unit at Harper Lake is

designed to have an installed generating capacity of 80 MW. Luz

plans to bring SEGS IX on-line in September, 1990 and another

unit on-line by the end of each year from 1991 through 1993. In

an agreement with SCE to be discussed in more detail later, Luz

has also committed to sell to the utility another 20 MW of output

from one of its Harper Lake units. Altogether, the SEGS genera-

tion from Harper Lake is expected to have a maximum capacity

of 480 MW. While the other units are all under contract for sales

to SCE, the last unit, SEGS XIII, is under contract to San Diego

Gas and Electric Company (SDG&E). Power from SEGS XIII

would be wheeled across SCE lines for delivery to the SDG&E

service territory if the merger between SCE and SDG&E, which

is the subject of A.88-12-035, is not approved.’ Luz has con-

structed a 12-mile 220 kV transmission line to deliver power from

Harper Lake to the Kramer Substation.

’ As of the date of submission of this case, SCE and Luz had not

entered into an agreement governing the transmission of power from

SEGS XIII.

i

A-8

No one disputes the fact that SCE is required under the federal

Public Utilities Regulatory Policies Act (PURPA)* to intercon-

nect with and purchase power from the QFs developed by Cal

Energy and Luz.’ In addition, all parties appear to agree that SCE

needs to add additional 220 kV transmission capacity in order to

move all of the power from these QFs as far south as the Victor

Substation. It is agreed that if the QF generation is to be

delivered to the Kramer Substation, it will be necessary for the

additional 220 kV transmission line to interconnect at Kramer.

Figure | is a map indicating the location of transmission lines

and substations related to this project.

Cal Energy has lodged Figure | with the Court under separate

cover.

Power moving from the Kramer Substation toward the SCE

load center is delivered to the Lugo Substation, from which it can

be routed on existing 500 kV lines. The Victor Substation is

between Kramer and Lugo. SCE has two 220 kV lines which

currently carry power directly from Kramer to Lugo. James G.

Kritikson, SCE’s Transmission Planning Manager, testified that

these two circuits and the related transformers will be fully loaded

when all existing and previously committed SCE and QF genera-

tion resources come on line. Kritikson’s load flow diagrams

indicate that power is currently imported to Victor from Lugo.

SCE will be able to serve load in the Victor area with power

heading south from Kramer by interconnecting additional trans-

mission capacity at Victor. The remaining power will continue to

flow from Victor toward Lugo on existing lines.

*16 U.S.C. 824a-3; 18 CFR 292.303.

* Throughout this discussion, it should be remembered that SCE is

not under contract to purchase power from SEGS XIII. Nor has it been

specifically asserted that SCE is under any obligation to interconnect

with SEGS XIII. However, since only one point of interconnection will

allow for the transfer of the power anticipated to be delivered by all units

II1V-XIII, we will not repeatedly allude to this distinction. In addition,

no one has argued that the need for new transmission facilities would be

in any way different if SEGS XIII was not part of the consideration.

A-9

Kritikson calculates that if all of the generating sources which

are already committed to use the existing Kramer to Lugo lines

were to operate at full strength, they would fill those lines to 102%

of their capacity. It is evident that the existing Kramer to Lugo

lines cannot be committed to carry the output of any more

generating facilities.

The record indicates that while it is possible to carry more than

100% of capacity on a given line, it is not advisable to do so. Line

losses would be great and the conductors would be in danger of

accelerated deterioration. However, Kritikson testifies that, with-

out the addition of the Cal Energy and Luz facilities, there is very

little danger of ever taxing the existing lines to this extent. First,

to do so would require that all the facilities which are to rely on

these lines be in operation at full strength at the same time. This

is unlikely. Second, as demand grows in the Kramer area, more

power will be diverted to serve local load, leaving less power to be

transmitted to Lugo. At the same time, all parties appear to agree

that there is a need to add more transmission capacity if addi-

tional generating sources are to deliver power through Kramer.

Even if the power from the Cal Energy and Luz facilities that

are the subject of this proceeding was to be delivered not to the

Kramer Substation but directly to Victor or Lugo, there seems to

be agreement among the parties that new transmission lines

would be needed. As will be discussed below, the only other

technically feasible means of delivering this power to the SCE

grid reflected in the record would involve building radial lines

from the China Lake and Harper Lake areas directly to Victor or

Luz. Regardless of the merits of that approach, it clearly would

not obviate the necessity of adding new transmission facilities.

V. Description of the Proposed Project

SCE proposes to construct a new, 38-mile long, double-circuit®

220 kV transmission line connected in the north to the Kramer

° A double circuit line is one which allows for the stringing of two sets

of one circuit conductors on the same towers. One circuit is a set of

3-phase conductors.

on rere

A-10

Substation, located at the small community of Kramer Junction

at the intersection of U.S. Highway 395 and State Highway 58.

The proposed route would be parallel to Highway 395 for the first

22.2 miles. SCE seeks to build this portion of the line immedi-

ately west of the existing transmission lines that are also roughly

parallel to Highway 395. As proposed, the line would continue to

run parallel to one set of existing lines or another all the way to its

southern terminus at the Victor Substation, which is located on

the south side of State Highway 18 near Abode Corners. Along

the way, the proposed route is diverted to avoid running through

the small commercial and civic center which hugs Highway 395

in the town of Adelanto.

As explained in the EIR, to accommodate the new line, the

existing right-of-way between the Kramer and Victor substations

would need to be increased by 75-100 feet, depending on the

specific locations of the transmission towers. Most of the proposed

project would be constructed on conventional double-circuit lat-

tice steel towers. In two areas, however, different towers would be

used. One instance would be where four single circuit towers

would be used to enable the line to cross under an existing 500 kV

line owned by the Los Angeles Department of Water and Power.

The other instance is where single-pole tubular steel towers would

be used to enable the new line to pass within an existing 150 foot

right-of-way through an industrial park in Adelanto. SCE pro-

poses buying and moving two existing homes which sit in the

proposed right-of-way on the northwest side of Adelanto.

The proposed project also includes certain modifications and

additions to the Kramer, Victor, and Lugo substations. At the

Kramer Substation those changes include:

1. the construction of two additional positions in the existing

220 kV switchyard to terminate the new circuits,

2. the installation of one 115 kV capacitor bank, and

3. the installation of necessary protection equipment.

At Victor, those changes include:

1. the construction of four new 220 kV line positions in a new

220 kV switchrack which will form the termination of the new

A-11

transmission line and the two existing Lugo-Victor 220 kV

circuits,

2. the installation of two 220 kV bank positions,

3. the installation of two 220 kV capacitor banks, and

4. the installation of necessary protection equipment.

Finally, additional protection equipment will be required at the

Lugo Substation as a result of increased loading caused by the

proposed project.

VI. Cost Caps and Cost Estimates

for the Proposed Project

In compliance with PU Code Section 1003(C), SCE included

in its application in this proceeding “an appropriate cost estimate”

for the project. The Commission is required by PU Code Section

1005(b) to specify the estimated cost in the certificate which it

issues for the project. Further, for facilities estimated to cost more

than $50 million, PU Code Section 1005.5 requires that the

Commission specify, in the certificate, a maximum cost deter-

mined to be reasonable and prudent for the facility. This cost cap

can be increased by the Commission after the certificate is issued

if the utility applies for an increase and if the Commission finds

both that the project will actually cost more than was initially

anticipated and that the project is necessary and convenient even

at the higher cost.

DRA argues that a limit, or cap should be placed on the

amount that SCE can spend on this project on behalf of its

ratepayers without seeking further Commission approval. SCE

opposes this proposal. In addition, SCE and DRA disagree as to

how much the proposed project should be expected to cost.

A-12

A. Project Cost Estimates

Table 1 provides a comparison of the SCE and DRA cost

estimates:

Table |

Project Cost Estimates

(in $million)

SCE DRA

Pe ho dw bev e dus cvekevereeus 32.225 30

Substation Improvements ................. 18.155 13

po eee 50.38 43

DRA’s transmission cost expert, Ray Valaitis, prepared DRA’s

cost estimate for the new transmission line by using the Bonne-

ville Power Administration’s (BPA) generic cost-per-mile esti-

mates. SCE’s expert, Alexander Mateuchev, tried to develop a

more project-specific forecast by estimating labor and material

needs and applying current costs.

SCE argues that the DRA approach is too imprecise and does

not take into account various peculiarities of the proposed project.

For instance, Mateuchev points out that Valaitis did not add costs

related to the replacement of % mile of existing steel lattice

towers with steel poles through the Adelanto Industrial Park. He

estimates that process to add another $1.3 million to the project

cost.’ In addition, SCE’s estimate for permitting and regulatory

expenses exceeds that of DRA by $644,000. According to

Mateuchev, these regulatory costs include support of the CPCN

process, CPUC application fees, preparation of environmental

studies and reports, and BLM and Edwards Air Force Base

approval. Mateuchev argues that the DRA estimate, which is

based on BPA costs, does not reflect the difference between

regulatory practices in BPA country (Washington and Oregon)

and those in California. Finally, Mateuchev argues that DRA

neglected to include sales tax which would be paid for the

’ The EIR indicates that SCE subsequently proposed to double the

length of the segment that will consist of steel poles. This presumably

would increase the project cost in a manner not reflected in the SCE

estimate.

A-13

construction materials. He estimates those taxes to total

$690,000.

DRA argues that the proposed line is very simple to construct,

the terrain in the area is flat and open, and anticipated mitigation

expenses are relatively low. DRA argues that SCE has provided

virtually no justification as to why costs for this line should exceed

the average. Valaitis acknowledges that SCE’s cost estimating

approach “has the inherent capability of being more precise than

the one the I prepared,” but that SCE’s approach does not always

represent the only reality. DRA agrees that its estimate did not

include the sales tax figures or the added costs resulting from the

removal of % mile of lattice work towers and their replacement

with steel poles. However, DRA argues that its $2 million

contingency provides the cushion necessary to cover these costs.

DRA also points out that SCE may have been able to avoid the

need to replace lattice towers if it had bought a wider right-of-way

through the Adelanto Industrial Park at an earlier date. As for the

estimate of regulatory expenses, DRA argues that SCE has not

demonstrated the existence of any difference between California

regulatory requirements and those in the Pacific Northwest which

would make it more expensive to license a facility in this state.

Finally, DRA argues that SCE was unreasonable in assuming that

overheads would add another 30% to the project costs. DRA says

that, since most of the project will be built by Luz and since Luz

is a smaller organization, it is more realistic to expect that

overheads would add only 20% to the project cost.

In its rebuttal testimony, SCE takes exception to several

aspects of DRA’s estimate of the costs of substation improve-

ments. In preparing its estimate of Kramer Substation costs,

DRA used 1978 cost data which was then escalated to 1991 value.

SCE argued that DRA should have started 1987 cost data and

should have made allowance for the added cost of making

changes on an energized substation such as Kramer. SCE says

that these changed assumptions would have added $1 million to

DRA’s cost estimate. SCE argued that, in considering Victor

Substation costs, DRA failed to use updated 220 kV circuit

breaker costs, failed to include the cost of overhauling and

refurbishing eight system breakers, and omitted the added cost of

A-14

station grounding, site grading, relay equipment, station light and

power, crushed rock, and line and bank conductoring. According

to SCE, these factors account for $5 million in additional ex-

penses. Finally, SCE argues that DRA did not include $245,000

for specific protection improvements for the Lugo Substation,

plans for which were finished after the application for this matter

was filed.

DRA did not respond to each of these concerns, but instead

emphasized that its estimate included a $2 million dollar contin-

gency figure and that SCE used a very high factor for overheads.

We will adopt SCE’s estimate of project costs. While the

provision of a detailed cost estimate does not guarantee accuracy,

it appears that SCE has used a reasonable approach to assembling

its prediction of project costs. We assume that when DRA added

a $2 million contingency amount to its original estimate, it

intended for that amount to be applied to unexpected expenses,

not to be absorbed as a means of covering predictable expenses

that DRA failed to identify. According to SCE, the sales taxes

and lattice tower replacement costs total about $2 million. If the

contingency amount is considered to include these figures, then

there is no contingency left to cover unexpected costs.

The parties simply disagree about the expected regulatory costs

and overheads. SCE has offered us little guidance as to how it

arrived at its estimate of regulatory costs. The DRA has provided

an estimate that can more easily be explained, since it relies on a

cost estimate methodology that is used by the BPA. We are

nonetheless, for the reasons discussed below, willing to adopt

SCE’s estimate for these expenses.

Neither SCE nor DRA has adequately explained its estimate of

overhead expenses. Both parties applied a 30% rate. Nonetheless,

DRA argued that a lower rate is more applicable to a smaller firm

such as Luz, which is expected to construct most of the project.

Unfortunately, DRA offered little support for its assertion that

smaller firms face lower overhead costs.

While the proposed project is relatively straightforward, we are

imposing mitigation requirements and other permit conditions

which may not have been anticipated when SCE made its

be ented Sa

A-15

estimate. The mitigation monitoring program and other condi-

tions placed on the construction of the project may add to

regulatory and other costs.

At the same time, DRA’s cost estimate demonstrates that SCE

has taken a very conservative approach in developing its estimate.

SCE should be able to complete the project within its projected

budget.

In adopting a cost estimate, it should be remembered that this

figure is used for placing the application in a financial context and

does not give SCE license to pass any particular amount of money

on to ratepayers. As is true with ail capital additions, SCE will be

required to demonstrate the reasonableness of all of its expendi-

tures related to this project before ratepayers will bear these costs.

B. Cost Cap

PU Code Section 1005.5(a) states:

“Whenever the commission issues to an electrical or gas

corporation a certificate authorizing the new construction...

of the corporation’s plant estimated to cost greater than fifty

million dollars, the commission shall specify in the certificate

a maximum cost determined to be reasonable and prudent

for the facility...”

If the project later proves to cost more than the amount specified

in the certificate, the utility is required to ask the Commission to

increase the maximum cost (cost cap).

When the Commission considers whether or not to issue a

certificate, it normally must compare the estimated cost of the

facility with the expected benefits and with the cost of other

feasible project alternatives. The cost cap process set forth in PU

Section 1005.5 allows the Commission to ensure that a project

which appeared to be cost-effective when it was certified does not

move forward unchecked if subsequent cost escalation makes

completion of the project economically unwise. The fact that the

Commission is required to establish a cost cap for projects

expected to cost more that $50 million assures that, at a mini-

mum, cost caps will be applied to al! new major projects.

A-16

The estimated cost of this project is slightly more than $50

million. DRA proposes that a cost cap be established, regardless

of estimated cost. SCE argues that since the ratepayers’ share of

the cost is likely to be far less than $50 million, the cost cap

provision of Section 1005.5 does not apply. DRA responds that

Section 1005.5, in establishing the cost cap requirement, is blind

to cost allocation. It simply requires that a cost cap be set

whenever the cost of the project as a whole is expected to exceed

$50 million. We agree. By adopting the highest estimate of

project cost, we have helped to assure that the project can be

completed within the limits of the cost cap. In addition, this is a

short duration project (to be completed before the end of 1991)

which is, therefore, less vulnerable than other projects to severe

inflation of other unexpected cost effects.

In its comments on the Proposed Decision, SCE argues that

the conditions placed on the certificate, outlined below, may add

to the cost of the project. SCE asked for permission to file an

updated cost cap estimate within 90 days of the date at which this

decision becomes final. SCE proposes that its revised estimate

then become the cost cap. The request is denied. Section 1005.5

says that the utility can apply for an increase in the cost cap at any

time after the application is approved. This is approach that SCE

should follow if it determines at any point the the cost of the

project will exceed $50.3 million. Following this approach will

help to assure that SCE properly justifies any request for an

increase in the cap.

VII. Ratepayer Cost Responsibilities

Traditionally, utilities apply for CPCN for new projects which

will be placed into the utility’s rate base, allowing the utility to

earn a rate of return on its investment and to depreciate its capital

investment over a reasonable period of time. It is the ratepayers

who usually pay these costs. The provisions of the PU Code

related to CPCN request the Commission to consider the cost-

effectiveness of a proposed project as a means of meeting a

perceived need before saddling ratepayers with the economic

burden of new investments. PU Code Section 1003(d) requires

that the applicant for a CPCN demonstrate, among other things,

bit ea:

A-17

the financial impact of the new project on the company’s ratepay-

ers. In order to understand the ratepayer impacts, it is necessary

to estimate how much ratepayers will be asked to spend for the

project. This requirement applies regardless of the reasons that

the project is needed. Section 1005(b) states that the certificate

granted by the Commission must specify all of the characteristics

of the plant set forth for the applicant to address in Section 1003.

Thus, in order to grant a certificate for a proposed project, we

must determine, among other things, the portion of the project

cost which will be borne by ratepayers.

In November 1988, SCE signed integration and interconnec-

tion facilities agreements with Luz and Cal Energy. The agree-

ments called for the construction of the proposed project. As an

interim means of carrying Luz and Cal Energy power between

Kramer and Victor, the parties agreed to the rebuilding of an

existing 115 kV line. This strategy was pursued because the 115

kV project could be accomplished without coming to this Com-

mission for a CPCN. It was agreed that Luz and Cal Energy

would split the cost of the rebuild of the 115 kV line. Further, it

was agreed that Luz, Cal Energy, and SCE would evenly share

the cost of the proposed project pending our determination of the

proper cost responsibility for each party.

When it filed its application in March of 1989, SCE indicated

that it was negotiating separately with Luz and Cal Energy in an

effort to agree on a final proposed allocation of the cost of the

proposed project among Luz, Cal Energy, and SCE’s ratepayers.

On November 17, 1989, SCE and Luz signed an agreement

allocating costs for the proposed project and other related facili-

ties between Luz’ and SCE’s ratepayers. SCE has asked us to

approve the SCE/Luz agreement in this application. Initially,

DRA opposed this agreement. It has since removed its opposition

and no one is currently arguing against adoption of the agreement.

SCE and Cal Energy apparently continued to work toward an

allocation agreement until well into this proceeding, but failed to

come to terms. At one point, counsel for Cal Energy asserted that

his client had no interest in negotiating an allocation of the project

costs. SCE has proposed that all project costs not allocated to Luz

under the terms of their agreement be allocated to Cal Energy.

A-18

Cal Energy argued that all such costs should be borne by

ratepayers. The CEC supported Cal Energy’s position. The DRA

proposed a hybrid approach to cost allocation. Before considering

issues related to Cal Energy’s share of the project costs, we will

look in more detail at the SCE/Luz Agreement.

A. The SCE/LUZ Agreement

SCE has asked the Commission to approve its agreement with

Luz under which Luz would bear the following costs:

1. 44.8% of the cost of the proposed project.

2. 100% of the cost of the 220 kV transmission line from

Harper Lake (site of the SEGS VIII-XIII units) to the Kramer

Substation and the cost of the line’s termination at the Kramer

Substation.

3. Ali operation and maintenance (O&M) costs related to the

Kramer Substation termination facilities for the Luz 220 kV line.

4. 52% of the cost of the Kramer-Victor 115 kV transmission

line rebuild which provides an interim means for transmitting Luz

and Cal Energy power.

5. 100% of the cost of metering and telemetering equipment.

The two parties further agreed that while SCE would engineer,

design, and provide equipment specifications for the proposed 220

kV line, ".uz would procure the needed equipment and construct

the line for a fixed cost. Under this arrangement, Luz and SCE

expect that the line can be built as much as a year earlier than

was previously planned. That is because Luz is willing to bear the

risk of planning and procurement costs while the CPCN is

pending. Luz would deed ownership of the line to SCE. SCE

would be fully responsible for planning and constructing the other

facilities included in the proposed project. SCE agreed to pay all

of the cost of upgrading the Lugo substation and all O&M costs

for facilities south of the Kramer Substation.

B. Proposals for Allocating the Remainder of the Project Cost

If the SCE/Luz Agreement were to be approved, it would still

be necessary to determine what portion, if any, of the remaining

55.2% of the project cost should be borne by Cal Energy. SCE

A-19

argues that since the new line is being built exclusively to serve

the new QFs, all costs for the project not paid by Luz should be

paid by Cal Energy. Cal Energy, on the other hands, says that

ratepayers should pay all of the remaining project costs. The CEC

agrees with Cal Energy. The DRA proposes that Cal Energy be

required to pay the same amount as Luz (44.8%) and that the

remainder (10.4%) be paid by SCE’s ratepayers. In support of its

position that all remaining costs should be borne by ratepayers,

Cal Energy has relied almost exclusively on its interpretation of a

1985 decision by this Commission. Because of the weight given

this decision by Cal Energy, we will now explore the decision and

the arguments related to it.

C. D.85-09-058 and Its Significance

In early 1984, the Commission was approached by Pacific Gas

and Electric Company (PG&E) and various QFs about limita-

tions in the near-term availability of transmission capacity in

portions of Northern California. As more and more QF develop-

ers sought to enter into standard offer agreements with PG&E for

the sale of power, it was becoming evident that transmission

limitations could constrain PG&E’s ability to bring new facilities

on line. On April 18, 1984, the Commission issued Order Institut-

ing Investigation (I.) 84-04-077 to examine these alleged trans-

mission constraints. The Commission also wanted to assess the

extent of any limitations in other utilities’ transmission systems

which would affect QF development.

The respondent utilities filed statements of anticipated limita-

tions on their transmission systems over the following ten years

which might affect QF development. In those statements, only

PG&E predicted that it would have significant constraints in its

northern transmission system.

After submission of the utilities’ statements, the Public Staff

Division (now DRA) held several workshops in which an interim

solution was developed to address the PG&E constraints specifi-

cally. In addition, in the workshops, parties formulated a mile-

stone procedure for tracking the development of individual QF

projects and discussed various approaches for allocating costs

related to new transmission projects. Hearings were held in April,

A-20

1985, on three subjects, which included the utilities’ transmission

constraints and cost allocation approaches.

In September of that year, the Commission issued D.85-09-058

which addressed these issues. That decision contained the follow-

ing language, which has been carefully dissected and analyzed by

all of the parties to the current proceeding:

“QF deliveries are a significant part of each utility’s resource

plan. Accordingly, utilities must plan for and otherwise

enable QF facilities to interconnect with their transmission

systems in an expeditious manner. We recognize that both

the diversity and the number of emerging QFs in PG&E’s

system have created new problems for the company’s trans-

mission planners. However, PG&E along with the other

utilities must learn to facilitate the addition of QF power as it

already has learned to accept power deliveries from all other

resources.

“The parties have agreed among themselves that QFs should

not be responsible for the cost of transmission facilities which

serve multiple purposes. The parties find since the ratepayers

in the past have paid for these transmission facilities, the

ratepayers should continue to absorb the cost as long as the

transmission facility has system-wide benefits. A QF is

responsible only for interconnection and other facilities that

have no system-wide benefits and are solely beneficial to the

QF. This approach eliminates the need for a difficult cost

allocation among the various users of a transmission facility.

“System-wide benefits, can mean many things as shown in

SDG&E’s list of factors affecting its transmission planning.

Thus, we believe that nearly all transmission facilities argua-

bly may have some system-wide benefits. Bulk transmission

lines by definition have system-wide benefits. And nearly all

area lines probably have some system-wide benefits. Thus,

QFs will assume cost responsibility only on the rare occasion

that an area line lacks any perceptible system-wide benefit.

“On occasion, a transmission facility’s cost may outweigh its

system-wide benefits. In this event, the QF perhaps should

be responsible for any excessive cost caused by the intercon-

A-21

nection of its facility to the utility’s system. A rigorous cost-

benefit analysis, however, touches upon many as yet unde-

fined criteria. We have yet to determine a long-run avoided

cost methodology for QFs. We have not yet adopted consis-

tent energy reliability criteria for all utilities. The cost of

transmission service is just one piece to the puzzle of

properly valuing QF power. Thus, for the moment, we will

allow utilities to follow the general principle that as long as a

transmission facility, has system-wide benefits, the utility’s

ratepayers are responsible for the prudent and reasonable

cost. The QF is responsible only for interconnection cost and

other special facilities which have no system-wide benefits.

Refinement of this principle must wait for our determination

in the long-run avoided cost proceedings.”

Cal Energy has argued that the above language is clear on its

face, that, as a matter of definition under D.85-09-058, the

proposed project has system-wide benefits, that the Commission

is bound by law to adhere to the principles set forth in that

decision and that Cal Energy relied on its interpretation of the

decision while developing its projects. Cal Energy further argues

that a detailed analysis of the proposed project would demonstrate

that the new line would provide substantial system benefits. For

that reason as well, Cal Energy asserts that we are bound by law

to absolve thie QF from all cost responsibility for this project. The

CEC and Luz agree with Cal Energy’s position. SCE argues that

the 1985 decision allows for a case-by-case examination of the

system-wide benefits question, that the Commission is not bound

by law to adhere to the 1985 decision in any event, and that a

detailed analysis demonstrates that the proposed project has no

system-wide benefits. SCE also argues that Cal Energy’s claimed

reliance on its interpretation of the 1985 decision was unjustified,

was not genuine, and does not prevent the Commission from

reinterpreting the decision. In all significant respects, DRA agrees

with SCE. We will now address each of these arguments in

greater detail.

1. Is the Decision Clear on its Face?

The 1985 decision cited above established a Commission policy

which favors having ratepayers bear the cost of new transmission

ae ere a ee ee

A-22

lines which serve beneficial purposes other than allowing for the

interconnection of QFs. This policy is set forth clearly in the

Conclusions of Law and Ordering Paragraphs of the decision. The

1985 decision provides far less clarity as to how to determine

whether or not those other beneficial purposes exist in a given

instance. Cal Energy and the CEC argue that the 1985 decision

provides no room for misinterpretation; the discussion section

contains the statement that “Bulk transmission lines, by defini-

tion, have system-wide benefits.” This statement is repeated as a

Finding of Fact in the decision. SCE appropriately points out that

this finding is not an element of any of the conclusions which

follow.

The statement about “bulk lines” leaves us little to go on. The

decision does not define the term.* Cal Energy and CEC suggest

that any line of 220 kV or higher voltage is a bulk line and,

therefore, that any line of such a size produces system-wide

benefits by definition. However, it is not logical to suggest that

size alone produces system-wide benefits. For instance, Cal En-

ergy’s witness Lewis stated that, in his opinion not all radial lines

produce system-wide benefits, for reasons that don’t necessarily

relate to the size of the conductors. He drew a distinction between

the line strung by Cal Energy on existing SCE towers which could

at least produce future system-wide benefits if it was intercon-

nected at the Inyokern Substation, and a more typical radial line.

A more typical radial line cannot usually add to system reliability

since it does not contribute redundancy to the transmission

system and usually does not provide excess capacity, since it is

likely to be sized appropriately to carry the anticipated load.

Lewis suggests that the latter type of line does not produce

system-wide benefits. The 220 kV line built by Luz to carry power

from Harper Lake to the Kramer Substation seems to fit the

* Cal Energy argues to the contrary by referring to mimeo pp. 7 and 8

of the decision. However, those pages merely set forth data supplied by

parties to the case and provide little guidance as to how the Commission

intended to use the term “bulk power.” Simply because, some 220 kV or

230 kV lines were referred to as bulk lines doesn’t mean that all such

lines are “bulk” by definition.

287 OR A

A-23

latter description. No party has argued that this line produces

system-wide benefits. To the contrary, as part of its agreement

with SCE, Luz has agreed to pay for the full cost of that line.

Either some 220 kV lines are not bulk lines as the Commission

used that term in 1985, or it simply is not true that all bulk lines

have system-wide benefits. In either event, the 1985 decision is

not as clear as some have argued. Cal Energy argues that all

parties to Commission proceedings understand that all lines over

200 kV are bulk lines. Cal Energy cites a prior SCE statement in

an earlier proceeding as proof. However, PG&E adds that bulk

lines can be distinguished by a number of characteristics other

than voltage rating. In its opening brief, PG&E argues:

“For example, the specific proposed upgrades discussed by

the Commission in D.85-09-058 can be distinguished by

their function. These proposed upgrades had a generalized

function of supporting power transmission throughout the

utility electric system. In contrast despite their voltage rat-

ing, the primary function of the lines that are the subject of

Edison’s application is to gather output from remote QF

projects.

“The developers of these QF projects had their own reasons

for siting them in locations remote from Edison’s load center.

Edison’s ratepayers should not automatically be responsible

for all costs of system upgrades necessary to accept this

power merely because 220 kV lines and associated equip-

ment are involved.”

Finally, SCE offers evidence that the Commission had a

broader definition in mind when it issued its decisions addressing

the allocation of bulk transmission line costs. SCE points out that

D.84-08-031 states that it modified D.83-10-093 to conform to

PG&E’s position, and then argues that PG&E does not distin-

guish between bulk and area lines on the basis of voltage. D.84-

03-092 (issued in the same proceeding as D.83-10-093) quotes a

letter from PG&E’s attorney in which 230 kV lines areas are

described as both bulk and area lines: “Bulk transmission capacity

limitations occur on PG&E’s 230 and 500 kV transmission

system, and area transmission limitations occur on PG&E’s 230,

115 and 60 kV system.” (D.84-03-092, p. 61.) We are left

eee

A-24

without clear guidance from prior Commission decisions as to

what constitutes a bulk line. This is a matter which should be

resolved in a generic proceeding, not in a certification forum with

limited parties.

As will be discussed further below, the 1985 decision also fails

to set forth criteria for iudging the existence of system-wide

benefits. It refers to a list of factors used by SDG&E to assess the

benefits of 2 proposed line, but does not assess the merits of that

list, or suggest that it sets forth the appropriate criteria for SCE or

any other utility to employ. For this reason as well, the 1985

decision does not lend itself to ministerial application.

2. Is the Decision Binding?

a. Positions of the Parties

Cal Energy asserts that D.85-09-058 constitutes the definitive

approach to cost allocation, that the Commission is bound by law

to follow that approach in subsequent proceedings, and that the

Commission is reduced in the current application to the ministe-

rial task of applying the findings from the 1985 decision.

Cal Energy argues that the Commission cannot alter or rescind

the 1985 decision in this application, because to do so would

violate the notice and hearing requirements of PU Code Section

1708 and the Fourteenth Amendment of the U.S. Constitution.

Section 1708 says that the Commission may rescind, alter, or

amend any order or decision upon notice to the parties and with

opportunity to be heard. In support of this argument, Cal Energy

cites California Trucking Association v. PUC, (1977) 19 Cal. 3d

240, a case in which the California Supreme Court held that this

Commission cannot issue an ex parte decision in a matter for

which a formal protest has been filed requesting hearing. SCE

responds that there was an adequate opportunity for the affected

parties in this case (Luz and Cal Energy) to be heard and that

the Commission is not restricted in its ability to depart from the

policy set forth in earlier decisions at least so far as it would affect

these parties. Independent Energy Producers argued that a lim-

ited proceeding such as this should not be used as the forum for

changing the cost allocation policy as it applies to all utilities and

OFs.

ee ee ee es

OO ED LAO ON Ste OF PR Rete oe dale)

YN Ein UR Dated a a, Se

A-25

Cal Energy also argues that because of the existence of D.85-

09-058, the Commission has no interpretative discretion as to how

costs should be allocated in this proceeding. Instead, Cal Energy

claims, the Commission is bound by a ministerial duty to simply

enforce and apply the law. In support of this point, Cal Energy

cites Great Western Savings and Loan Assn. v. City of Los

Angeles, (1973) 31 Cal. App. 3d 403, 413, a case in which a state

appeals court said that a local agency must approve a tract map if

it conforms to state statutes and local ordinances. SCE argues

that there is no such ministerial duty here.

Cal Energy argues that if the Commission applied any interpre-

tive discretion to D.85-09-058, it would necessarily have to

produce inconsistent findings that would render any resulting

order subject to annulment. In support of this assertion, Cal

Energy cites Cal. Portland Cement Company v. PUC, (1957) 49

Cal. 2d 171, 176, a case which said that the Commission cannot

issue a valid decision which contains internally inconsistent find-

ings of fact which go to the principal issue involved in the case.

SCE points out that, in Cal. Portland, the Commission was held

to be at fault for having looked at precisely the same facts and

reached two opposite conclusions within the same decision. SCE

argues that there is no relevant similarity between that fact

pattern and the situation faced in this case.

Finally, Cal Energy argues that while D.85-09-058 was the

result of a quasi-legislative proceeding, a CPCN is a quasi-

judicial proceeding and that the Commission cannot do anything

in a quasi-judicial proceeding which is inconsistent with findings

in an earlier quasi-legislative proceeding.

In its Reply Brief, the CEC emphasized its support of the

quasi-legislative/ quasi-judicial argument and analogized the find-

ings in D.85-09-058 to statutes which an administrative agency is

compelled to uphold. The CEC cited Comite de Padres de

Familia, (1987) 192 Cal. App. 3d 528, 535 in which the State

Department of Education and Board of Education inappropriately

failed to comply with a statutory mandate; and County of Orange

v. Flournoy, (1974) 42 Cal. App. 3d 908, 912, in which an agency

was found at fault for assuring an effective date for new legislation

a

A-26

which was inconsistent with the effective date found applicable as

a result of a plain reading of provisions in the state constitution.

While arguing for the sanctity of D.85-09-058, Luz did not

offer an opinion as to whether or not we are bound in any way by

that earlier decision.

SCE argued that, since no Commission can bind a future

Commission, this Commission is not bound to adhere to the

findings in D.85-09-058. The CEC responded that, while it is true

that a later Commission can alter or reverse the course of an

earlier Commission, it must follow the rules of notice and oppor-

tunity to be heard before doing so. The implication is that the

findings in ihe 1985 decision cannot be altered without prior

notice to all the parties to the underlying proceeding, perhaps with

hearings held under the prior docket. SCE responds that it is

sufficient that the parties to the current proceeding have notice

that their nghts might be affected in a manner inconsistent with

the earlier order. SCE also points out that the finding of fact in

the 1985 decision referring to bulk transmission lines was not

essential to the conclusions of law or ordering paragraphs which

followed, and therefore is fair game for reconsideration in any

subsequent proceeding.

DRA argues that it is valid for the Commission to determine

how or if it will apply the findings of D.85-09-058 in this

proceeding. DRA cites the testimony of SCE’s witness Ronald

Luza ihat in 1986, the amount of potential QF resources that had

signed contract to deliver power in the Kramer-Victor area was

more than double that which had been forecasted in the proceed-

ing underlying the 1985 decision. DRA argues that in the field of

administrative law, the doctrine of changed circumstances has

long been applicable, in recognition of the fact that regulatory

agencies with continual jurisdiction are free to change course and

policies as circumstances change. DRA quoted our D.89-04-081,

in the QF complaint case of Colmac Energy v. SCE in which we

said, “our decisions typically rely more on policy concerns, fair-

ness, and common sense than on a detailed study of pertinent

legal precedent.”

Aastha Schl 5 at at dats a SIE dae AB Nh) ip NPR til ts

ee ae

3

i

4

iM

|

2

§

j

b. Discussion

We have no intention of altering, modifying, or rescinding

D.85-09-058 in this decision. While it may be appropriate to

reexamine some of the assumptions behind that decision or to

explore in more detail how it should be implemented, those

questions should be addressed in a broader proceeding, with more

expansive notice to affected parties.’ Here, we must decide how

the cost of one proposed transmission project should be allocated

among those who serve to benefit from its construction. Consider-

ation of the cost allocation of electric transmission facilities,

generically, is beyond the scope of this instant CPCN proceeding.

Any cost allocation which is determined to be reasonable in this

case is based on the facts and circumstances specific to the parties

and testimony in this proceeding and have no further reaching

application.

This appears to be the first time we have been asked to examine

the policy set forth by the Commission in D.85-09-058 in the

context of a specific application for CPCN. That decision said

that utilities should have their ratepayers pay for new transmis-

sion lines that are built to carry QF power and at the same time

provide other system benefits.'° What that decision did not

explain is how those benefits should be measured. The arguments

outlined above were shaped largely by the debate generated when

Cal Energy filed a motion which, in effect, sought summary

judgment on the questions of system benefits and cost allocation.

Cal Energy asserted that we are bound as a matter of law, by

language in the decision to relieve Cal Energy of all cost responsi-

bility. The ALJ denied that motion and stated that it was for the

full Commission to determine how, if at all, the 1985 decision

should be applied to the facts at hand. We agree with the ALJ.

* The Commission will address transmission line cost allocation in a

new, generic investigation on QF transmission issues. This new investi-

gation will be closely coordinated with the ongoing Biennial Resource

Pian Update (BRPU) proceeding.

'° D.85-09-058 also included the proviso that at some future time, a

means might be developed to limit ratepayer contnbutions in a way

which reflects the benefits being received.

A-28

Cal Energy’s arguments were dependent on the assumption

that a 220 kV line can be nothing but a bulk line. As discussed

earlier, the language concerning bulk lines provides little assis-

tance to us because it is ambiguous.

Even if the 1985 decision set forth a clear recipe for determin-

ing who should pay for the proposed project, we would not be

legally bound by that order in this proceeding. None of the

authority cited by the participants in this case stands for the

proposition that this Commission is precluded from reconsidering

its earlier policy positions, so long as adequate notice and opportu-

nity to be heard is provided to those who will be affected. Thus,

we are free to determine that the policy set forth in the 1985

decision is no longer appropriate as it affects the parties in this

case.

The California Supreme Court’s decision in California Truck-

ing, cited by Cal Energy, does not apply to the current situation.

In that case, the Commission had denied a hearing to a party that

filed a formal protest and requested a hearing. The Supreme

Court held that it was a denial of due process for the Commission

to reach a decision in the absence of the requested hearing. In the

current application, the QFs who will be affected by our decision

had adequate notice and opportunity to be heard. In Great

Western Savings decision, which was also cited by Cal Energy, an

appellate court held that a local agency exceeded its discretion

when it disapproved a tract map which complied with state

statutes and local ordinances. There would be no violation of

applicable state laws if this Commission determined that the cost

of the proposed transmission line should be allocated in a manner

not addressed in D.85-09-058 as long as adequate notice and

opportunity to be heard was provided.

In Cal. Portland Cement, a Commission decision was annulled

because it contained conflicting findings that went to a principal

issue in the case. Cal Energy has attempted to suggest that this

decision would preclude the Commission from issuing apparently

conflicting findings in any two cases. In a regulatory environment

where realities are constantly shifting, it would be unrealistic to

hold the Commission to such a standard.

siiess

tO) pes oti

A-29

The effort by Ca! Energy and the CEC to sort our proceedings

and responsibilities into quasi-legislative and quasi-judicial

cubby-holes is similarly nonpersuasive. Virtually every matter

before the Commission is quasi-legislative to the extent to which

it requires commissioners to draw upon a generalized understand-

ing of the subtleties of regulation and of the industries that we

regulate. With the exception of complaint proceedings, every

matter is quasi-legislative in that each proceeding provides an

opportunity to establish or refine Commission policy. At the same

time, each proceeding is quasi-judicial to the extent to which it

depends on an adjudicatory process (focusing on evidence in a

formal record, with sworn witnesses, etc.) and the narrow applica-

tion of facts to law as the basis for a Commission decision. As

such, the legislative/ judicial labels do not form a meaningful basis

for determining when the Commission must rely on prior deci-

sions and when it can formulate new policy.

The CEC cites two cases in an effort to outline the Commis-

sion’s quasi-judicial responsibilities (Comite de Padres, and

County of Orange). In each instance, an agency decision was

overturned because it was inconsistent with statutory law. A

decision by this Commission would be similarly vulnerable if it

conflicted with provisions of the PU Code. For instance, a

decision in a CPCN proceeding might be overturned if it failed to

meet the requirements of PU Code Section 1001, et seq. How-

ever, neither of these cases suggests that the Commission would

have committed legal error if it questioned or interpreted its

earlier policy in a subsequent proceeding.

In addition, we are not ready to agree with Cal Energy and the

CEC that a CPCN proceeding is “obviously” quasi-judicial in

nature. See, for instance, D.93724, a 1981 proceeding that consid-

ered the availability of attorney’s fees for participation in a CPCN

proceeding. After a lengthy discussion of the attributes of various

parts of a CPCN proceeding, the Commission concluded:

“Our decisionmaking process in certification proceedings

involves more than a narrow application of facts to law in the

classical judicial mode. Once we have made the benchmark

quasi-judicial decision that a proposed project conforms to

the officially adopted forecast, there remain many facts that

A-30

are considered on a quasi-legislative basis. These include the

cost of the project, its likely impact on rates, operating and

reliability factors, safety, and environmental impacts. The

range for exercise of our discretion is very broad. There is no

fixed framework of narrow factual issues which governs the

decision-making process. Our process is quasi-legislative on

these questions.”

What this language demonstrates is that the Commission does not

function with a stoplight that signals the nature of its responsibili-

ties in a given proceeding: green light means one can make

legislative determinations, red light means one cannot. Instead,

the Commission must constantly make its decisions within the

constraints and opportunities provided by the state and federal

constitutions and applicable statutory law but with an eye toward

setting the course for the future.

The flexibility allowed the Commission for these purposes was

set forth in a 1925 California Supreme Court decision with an

oddly relevant fact pattern. Postal Telegraph-Cable Company v.

Railroad Commission of the State of California, (1925) 197 Cal.

426, involved:

review of a portion of an order made by the Railroad

Commission whereby [Postal Telegraph-Cable Company]

was allowed one-half of the cost of relocating a portion of its

telegraph line in certain areas in which it is closely paralleled

by a high power transmission line operated by the Pacific

Gas and Electric Company, in order to prevent induction

interferences to [Postal’s] telegraph line which, by reason of

its close proximity to the power line of Pacific Gas and

Electric Company, renders induction unavoidable.

The Postal telegraph line had been built in 1886. In approxi-

mately 1904, PG&E began building a 50 kV transmission line

which, in some places, closely paralleled the Postal line. Because

surges in the PG&E line interfered with the transmission of

telegraph signals, portions of the telegraph line had to be rebuilt

or relocated. The proceeding before the Commission was a

complaint in which Postal sought to have the full cost of the

changes borne by PG&E.

Me Deda 3

SD te, ae dts abet

ots pret anaatien BEES

4 me nme al

A-31

Up to that time, it was Commission policy to levy all such

charges against the owner of the second line to arrive in the

corridor (in this case, PG&E’s). However, in the Postal com-

plaint, the Commission said:

“The evidence in this proceeding shows that both the power

and communication circuits have been in operation for many

years and long before the question of inductive interference

was given serious consideration. Since that time changes

have been made by both utilities in their circuits. In view of

the history of the lines involved in this matter, it does not

appear that the question of priority of construction should be

given material weight in determining the responsibility of

payment of costs resulting in the mitigation of interference.”

On appeal, Postal asked the Court to nullify the Commission

decision because it was inconsistent with established policy. The

Court said (at p. 436):

“The departure by the Commission from its own precedent

or its failure to observe a rule ordinarily respected by it is

made the subject of criticism, but our reply is that this is not

a matter under the control of this court. We do not perceive

that such a matter either tends to show that the Commission

had not regularly pursued its authority, or that said departure

violated any right of the petitioner guaranteed by the state or

federal constitution. Circumstances peculiar to a given situa-

tion may justify such a departure.”

The need for the Commission to be able to adapt its ordinarily

applicable rules to the peculiarities of a given situation is just as

great today as it was 65 years ago. This is one of the reasons that

the Commission cannot be legally bound to apply the 1985

decision to the facts at hand. Later, we will explore some of the

peculiar circumstances which would justify a departure from the

1985 rule in this case.

3. Cal Energy’s Claims of Reliance on the Decision

Regardless of the Commission’s legal responsibility to adhere

to precedent, there are strong reasons for the Commission to

avoid arbitrary departure from established policy. In no area is

this more true than in the QF market. Those considering the

A-32

development of a QF need assistance that their investment

decisions are made with reasonable knowledge of the conditions

which will apply when the power is brought to market.

Cal Energy presented General Donald M. 0’Shei to testify that

the company relied on its interpretation of D.85-09-58. That

decision was issued in September, 1985. Cal Energy signed its

power purchase agreements with SCE the preceding February.

O’Shei says that Cal Energy relied on what he felt to be the plain

meaning of D.85-09-058 and assumed that Cal Energy would face

no cost related to the improvement of SCE’s transmission system

in order to receive power. He said that it is with this understand-

ing that Cal Energy secured financing for its projects. O’Shei says

that when Cal Energy was informed by SCE that the utility

expected Cal Energy to pay for the additional transmission costs it

was “like a bolt out of the blue.”

SCE argues that the facts do not support Cal Energy’s claims

of reliance on the September, 1985 decision. First, the decision to

site the plants at China Lake was made in 1981. Second, the

power purchase contracts were signed before the 1985 decision

was issued. SCE argues that the 1985 decision could not have

affected the choice of plant location. It only could have affected

the decision to proceed with the projects at the sites previously

selected. However, SCE argues that the facts do not support a

claim that financing decisions were related to D.85-09-058 at all.

Table 2 presents SCE’s chronology of significant events related to

the financing decision.

Table 2

Decision or Activity Date

Cal Energy decides to locate at China

Lake (O’Shei, Tr. 8/526) .......... i981

PPAs signed specifying location at China

MO cane ue veh eCeeee see eeeebers Feb.-June, 1985 (O’Shei,

. Tr. 8/525 and 8/539)

First Method of Service (MOS) pro-

vided to Cal Energy for 115 kV lines Nov., 1985 (Luxa,

Tr. 10/815)

A-33

Decision or Activity

Cal Energy commits “substantial funds”

ag 2 § 2. eee

Cal Energy commits “substantial funds”

8. Bet.)

Second MOS to Cal Energy for two 115

gg NERS Se ot oo aa ee ar

First discussion between Edison and Cal

Energy about interconnection at 220

Dl idsc cutie Genie ca waaene seed

Edison told Cal Energy 220 kV upgrades

south of Kramer would be needed to

accept Cal Energy power at 220 kV

and they would be responsible for

Edison agrees to investigate 220 kV in-

terconnection; told Cal Energy they

would be responsible for costs of any

facilities solely beneficial to QFs ....

MOS proposed by Edison for Proposed

Project at QF’s expense ...........

Execution of IIFAs providing for BLM

and Navy II interconnection at 220

kV—$30-352 committed to Navy 2

—$150 M2 committed to BLM.....

Navy II and BLM projects on-line Total

investment = $380 million .........

Date

Mid-1986 (O’Shei,

Tr. 8/529-530)

Mid-1987 (O’Shei,

Tr. 8/529-530)

Aug., 1987 (Luxa,

Tr. 10/815)

Oct., 1987 (Luxa,

Tr. 10/813, 815-816)

Oct., 1987 (Luxa,

Tr. 10/816)

Dec., 1987 (Luxa,

Tr. 10/813-814)

April, 1988 (Ex. 1,

pp. 10-11)

Dec., 1988

(Luxa, Tr. 10/814)

(O’Shei, Tr. 8/535)

Dec., 1989

(O’Shei, Tr. 8/531)

SCE argues that this chronology shows that prior to October,

1987, SCE had offered Cal Energy Methods of Service (MOS)

which contemplated interconnection and integration using 115 kV

lines. SCE asserts that until October, 1987, Cal Energy had no

A-34

basis for even anticipating that it would interconnect and integrate

its facilities at 220 kV levels. Thus, SCE concludes, Cal Energy

could not have been relying upon its belief that D.85-09-058

would require all bulk line upgrades to be paid for by ratepayers in

making any decision to commit substantial funds before that date.

SCE says that when it learned that Cal Energy wanted to

interconnect at 220 kV, it informed Cal Energy that a 220 kV

upgrade south of Kramer Substation would be needed and that

Cal Energy would be responsible for those costs. SCE says that by

the time a contractual agreement to interconnect was signed in

December, 1988, Cal Energy had already spent approximately

$180 million on the two projects.

It is SCE’s position that only one conclusion can be drawn from

this course of conduct. Cal Energy proceeded with construction of

the BLM and Navy II plants regardless of what the ultimate

interconnection and integration costs would be. SCE argues that

Cal Energy purely and simply assumed the risk for those costs,

and they must now accept that risk.

Cal Energy responded by saying that it not only expected that

ratepayers would pay for all new bulk lines, but that they would

pay for all but the most rare area lines as well. Thus, from Cal

Energy’s perspective, it did not matter what size a new transmis-

sion line might be. The company expected that ratepayers would

pay for it.

O’Shei was asked to explain the significance of any reliance Cal

Energy might have placed on its interpretation of the 1985

decision. He said that that reliance affected the structure of the

financing for the project and that any subsequent assignment of

transmission co.‘ td Cal Energy would reduce the profitability of

the projection: in a manner which the company did not anticipate.

Then, he added:

“T suppose, without getting philosophical, that the Commis-

sion would also be interested in the reliance that the citizenry

in general places on its orders and when its orders are issued,

and if the Commission attempts, and in this case succeeded

in an unusual fashion to make those orders crisp and clear,

and the folks rely upon those orders, I would think that the

A smh ENN Mes mnt sn Liles bin Wile 4 Me obit a ioe

A-35

Utility Commission would take a responsibility for the out-

come of that reliance.”

We could not agree more with General O’Shei’s assertion that

the Commission should carefully communicate its policies and

attempt to develop in the marketplace reasonable expectations as

to the conditions which will apply when projects are brought on

line. However, for several reasons, we are not swayed by Cal

Energy’s claims of reliance on the 1985 decision. First, as SCE

has demonstrated, the need and responsibility for transmission

additions to serve these projects was sufficiently ambiguous at the

crucial decision-making points to make it unlikely that Cal

Energy could have reasonably relied on any particular transmis-

sion cost allocation in deciding to go forward. Second, as dis-

cussed above, we cannot agree that the 1985 decision provided the

clear and crisp allocation method that Cal Energy perceived.

Finally, Cal Energy had no reasonable basis for relying on its

assumption that the ratepayers would pay for the transmission

addition regardless of whether it was a bulk or area line.

Fourteen months prior to the time when Cal Energy signed its

power purchase agreement, the Commission issued D.83-10-93,

which discussed the terms applicable to standard offer contracts

for the purchase of electricity from QFs. In that decision, the

Commission voiced many of the same concerns expressed by

General O’Shei about the need for a solid basis upon which a QF

developer can make its investment decisions. In that decision, the

Commission stated:

“The staff has suggested that the applicable tariff rules in

effect at the time the contract is executed should be included

in the standard offer so that the agreement will not be

affected by future Commission-approved revisions of those

tariffs with the exception of costs of facilities ownership

charges. The reason for this recommendation is clear—to

provide maximum contract certainty and to define from the

outset the QFs and the utility’s responsibilities for intercon-

nection costs throughout the life of the contract. This cer-

tainty could prove vital to a QF’s obtaining financing. While

recognizing that such a requirement could impose an admin-

istrative burden on the utility due to the number of QFs

A-36

which might sign standard offers over the years, we believe

that such a step should be undertaken to preserve the

sanctity and certainty of each contract. We will therefore

direct all of the utilities to append to each standard offer the

applicable tariff rules governing interconnection costs, cost-

sharing and refunds, in the form existing at the time the

contract is signed. By doing so, both the QF and utility will

have reference to the exact rules which will govern their

transaction.”

Ordering Paragraph 22 in D.83-10-93, which addressed the then-

applicable approach to new transmission cost allocation, con-

tained the following language:

“12. The utilities’ tariff rules and standard offer provisions

governing interconnection costs and special facilities agree-

ments shall require the following:

oe

a. The QF shall pay for new or additional line capac-

ity if the upgrade is necessary for the utility to receive the

QF’s power.

“b. The cost of any line upgrade undertaken to serve

additional customers or QFs shall be borne by the utility.

“

c. For two or more QFs seeking to use an existing

line, a first come first served approach shall be used... If

two QFs establish the right of first-in-time simultaneously,

the two QFs shall share the costs of any additional line

upgrade necessary to facilitate their cumulative capacity

requirements. Costs shall be shared based on the relative

proportion capacity each QF will add to the line.”

On January 13, 1984, SCE filed with the Commission its

revision to its Rule 21, which mirrors the language contained in

the ordering paragraph cited above. The revised Rule 21 went into

effect on February 12, 1984 «ad was still in effect when Cal

Energy’s power purchase agreements were signed the following

February.

Ten months later, the Commission issued D.84-08-031, which

resolved an Order to Show Cause which had been issued to

PG&E. Although other utilities and QFs were not parties to the

—— ne ee

A-37

proceeding that led to the 1984 decision, the Commission took

the opportunity offered by the issuance of that decision to modify

Ordering Paragraph 12(a) of D.83-10-093 to read as follows:

“The QF shall apply for new or additional area distribution or

transmission line capacity if the upgrade is necessary for the

utility to receive the QF’s power.”

This modification reaffirmed the notion that ratepayers would pay

for bulk line additions but also left the clear signal that area line

additions prompted by the QFs would be paid for by the QFs.

Whether Cal Energy was paying attention to SCE’s Rule 21 or to

the modification of the 1983 decision in D.84-08-031, it should

have expected to be held responsible for the cost of any new area

lines prompted by its transmission needs. Since it could not have

formed a final opinion as to whether the added line would be a

bulk or area line until after it had formed a strong financial

commitment to completing the project, Cal Energy could not

reasonably have relied on an expectation that ratepayers would

have borne all of the expense of any needed transmission

additions.

4. Should D.85-09-058 Be Applied In This Case?

Although we are not legally bound to apply D.85-09-058 in

determining Cal Energy’s cost responsibilities, we are left with the

question of whether it nonetheless should form the basis for our

decision. The simple answer is yes. The 1985 decision has served

us well, because it has provided balance to the negotiating stance

of QFs and utilities who are attempting to resoive transmission

cost allocation issues. Prior to the current application, parties have

largely been able to work out their differences at the bargaining

table. The universal application of D.85-09-058 and subsequent

decisions which interpret that order is the best way to preserve

that balance.

D. System-Wide Benefits

Because the bulk/area line ambiguity does not provide us with

a very simple way of resolving the cost allocation question, we

have carefully examined issues related to system-wide benefits.

We have encountered two major difficulties. First, D.85-09-058 in

A-38

its current form remains ambiguous as to what criteria should be

applied to define the parameters of system-wide benefits. Second,

even if the criteria offered by parties to the proceeding are

assumed applicable, the record does not clearly demonstrate that

the line would create system-wide benefits.

1. The Lack of Clear Criteria

The lack of established criteria for analyzing system-wide

benefits caused the parties in this proceeding to argue as much

about definition as about the nature of the proposed project. In

D.85-09-058, the Commission referred to a set of criteria on

which SDG&E said it relies in assessing the potential benefits of a

new project. However, the Commission did not adopt these

criteria, or comment on their merits. With few specific parame-

ters or criteria available to sharpen the focus, the parties in this

proceeding attempted to apply the SDG&E criteria. However, it

is not clear that ali of the SDG&E criteria are applicable to the

matter of cost allocation. It is also unclear as to what some of the

criteria may entail.

2. Lowering Line Losses

In its opening brief, the CEC stated:

“The proposed 220 kV line is adding substantiai new trans-

mission Capacity to a system that is constrained and subject

to increasingly heavy loads. All of the energy carried on this

- system, whether QF or utility generated, is being transmitted

to serve SCE load. Line losses, currently high, will continue

to increase as new QF generation is added. Adding the new

220 kV line will unquestionably greatly reduce SCE’s line

losses, with the result that SCE will receive at its load center

significantly more capacity and energy than if it did not build

the line. This may seem simple, but it is also irrefutable

common sense. Logic provides this conclusion without com-

puter analyses and expert witnesses.

“Simple logic and common sense are, of course, the first

casualties when lawyers and engineers meet in administrative

hearings to argue about who should pay. So we leave logic at

A-39

the door and enter the arcane world of transmission planning

and computer modeling.”

While CEC’s argument may be appealing and while we share

CEC’s instinct that logic apply, we are not convinced that the new

line will “unquestionably greatly reduce” SCE’s line losses. It

would be extremely useful for someone to present the simple

calculations which would support this logic. However, none of the

analysts, including CEC’s, has taken such a straightforward

approach."'

In considering whether the proposed line decreases system

transmission losses, as with other possible systemwide benefits, we

must separate the effects of the line from the effects of the QFs.

For example, the additional QF generation may offset oil and gas

generation in the LA Basin, which could reduce NOx emissions

in the Basin. This is the type of societal benefit which justifies the

existence of PURPA and the entire QF program. It is part of the

reason that QFs can receive full avoided cost payments. Nonethe-

less, it is irrelevant to a determination of the benefits created by

adding the new line to transport the QF power.

Major studies of line losses were performed by Luz’s witness,

Rupp, and Edison’s witness Kritikson. In Rupp’s Surrebuttal

Testimony, Exhibit 20, he described an analysis of the reduced

losses from the proposed line based on Edison’s response to DRA

Data Request 2. At DRA’s request, Edison had analyzed the

effects of adding another 220 kV line from Kramer to Lugo, in

lieu of the proposed project. Edison’s response indicated that the

line would reduce losses in the area at a present value of $42

million. (Ex. 20 pp. 10-12.)

'' In their Opening Comments, both Luz and Cal Energy claimed

that their respective experts offered this calculation. However, the

record does not provide assurance that either witness provided the

simple calculation which we describe. Rupp, testifying for Luz, offered

an estimate of line loss savings in the Kramer-Victor area, but did not

explain what comprises that area, or specify its other underlying assump-

tions. Lewis, testifying for Cal Energy, assumed 530 MW of QF

capacity instead of 630 MW) and assumed an average load condition,

instead of considering the maximum expected line losses.

A-40

Rupp stated that Edison’s response to Luz’s Data Request 5

showed that the losses on the existing system should be 129.3

MW, not the 118.9 MW used in Edison’s response to DRA Data

Request 2. (Ex. 20 p. 11.) However, Kritikson testified that

Edison sent a correction to its response to Luz’s Data Request,

explaining that 118.9 MW was the correct figure. (Tr. p. 737.)

Rupp later states that the correct amount of losses on the existing

system is 132.1 MW. (Ex. 20 p. 15.) Kritikson testified that Rupp

appeared to have derived this amount by linear extrapolation

which would be inaccurate because line losses vary exponentially.

(Tr. p. 741.)

Rupp also believed that Edison improperly modeled the gener-

ation at the Coolwater facility. He claimed that Edison improp-

erly increased Coolwater’s generation after the addition of the

proposed project and QF generation. (Ex. 20 p. 17.) Kritikson

argued that if QF production increased, other production would

logically decrease. Kritikson responded that Edison wanted an

equitable comparison of losses in the area. (Tr. p. 745.) Edison

used a 22-24 capacity factor for Coolwater in its models. (Tr. p.

746.)

Rupp also stated that Edison used “unreasonably low” Cool-

water capacity factors in analyzing both the existing and proposed

cases. (Ex. 20 p. 18.) Rupp modeled the Coolwater facilities at

32% capacity, which Kritikson believes is improperly based on

data for another proceeding which did not include the additional

Luz and Cal Energy generation. (Tr. p. 744.) Kritikson also noted

that the Coolwater capacity for the years 1985 through 1988 had

been 7%, less than 2%, 7%, and 27%. (Tr. p. 746.)

Rupp also found fault with Edison’s analysis of reactive power

support. He says that Edison shows Coolwater providing reactive

power even during periods it is not generating power. (Ex. 20 p.

19.) Edison’s Kritikson explained that this representation is a

feature of the modeling technique and does not imply that

Coolwater generates reactive power when off-line. (Tr. p. 747.)

Rupp analyzed two types of loss savings attributable to the new

line. The first is capacity loss savings, which he defines as the

savings created by the reduction in capacity needed due to

A-41

reduced losses at peak load. (Ex. 19 p. 7.) He calculated the

capacity loss savings by adding the 11 MW reduction in losses in

Kramer-Victor area indicated by Edison in its response to DRA’s

Data Request 11.4 and imputing an additional 5 MW for the rest

of the Edison testimony. (Ex. 19 p. 8.) In Rupp’s surrebuttal

testimony he raised the total from 16 to 16.4 MW based on the

flaws he found in Edison’s analysis. (Ex. 20 p. 24.)

According to Rupp, the second loss savings are avoided energy

losses, i.e. energy that is saved because the system has fewer

losses. Again, based on his corrections to Edison’s modeling,

Rupp arrived at annual savings of 92.4 gigawatt-hours (gWh). He

translates the total (energy and capacity savings) into a present

value of $69.3 million. (Ex. 20 p. 24.)

Kritikson disagreed with Rupp about the proper way to evalu-

ate capacity losses. He believed they shouid be evaluated over the

entire peak period. Thus, while at the instantaneous peak this may

be a savings of 11 MW, over the entire peak period, the losses

would actually increase, at a value of $7.1 million. (Ex. 38 p. 7, as

corrected at Tr. p. 715.)

Cal Energy’s witness Lewis testified that the savings would be

approximately 80,000 MWh (90 gWh) per year, using Edison’s

1990 base case generation and loads. (Ex. 23 p. 11.) This was

performed with loads at 80% of peak. The Energy Commission’s

witness McCuen testified that the line appears to offer significant

benefits with respect to reducing line losses. However, he believed

that Edison improperly calculated losses on the proposed project

with the additional generation from Cal Energy and Luz, which

causes line losses to “appear” to increase. (Ex. 35 p. 8.)

Finally, DRA’s witness Flores stated that she could not deter-

mine whether the line would decrease system losses. (Tr. p. 623.)

She noted the sensitivity of the power flow program to the input

assumptions, such as those for Coolwater. (Tr. p. 625.)

The parties disagreed as to whether change in losses should be

measured across the entire SCE network, or on a basis which is

isolated to the Kramer-Victor area. They disagreed as to whether

the analysis should be done with the new QF generation included

or not included. In addition, they disagreed as to whether or not

A-42

the line loss credits included in utility payments to QFs should

influence the analysis in any way.

Some preliminary conclusions can be drawn. It is not logical to

measure the change in losses in the absence of the new QFs. The

construction of the new line has been prompted by the need to

transport electricity generated by the QFs into the system and is a

natura! part of the expanded transmission system. Neither should

the change in losses because of the QF generation displacing

generation closer to Edison’s load center be considered: this is not

a result of the proposed line. It appears that the relevant question

is: How will line losses between Kramer and Lugo be affected by

the addition of the new line and 630 MW of QF power? Since the

existing lines from Kramer to Lugo are heavily loaded, it appears

logical that a new line will cause some of the power on the

Kramer-Lugo lines to flow on the new Kramer-Victor line in-

stead. That should lower losses on the existing lines, but increase

the losses on the new line. What is the net change? No one has

offered that relatively simple calculation.

Finally, SCE’s argument that the line loss credit included in

QF payments may offset some or all of the perceived line loss

benefit must be seriously considered. It might entail double

counting if line loss savings for which QFs are already given credit

are included in an assessment of system-wide benefit of the new

line.

3. Providing for Future Growth

SCE states that the existing transmission system in the

Kramer-Victor area is adequate for the next 20 years. (Ex. 38

p. 5.) Luz believes that the load growth predicted in the Propo-

nent’s Environmental Assessment (PEA)’? for the area will leave

SCE with a load of 400 MW or more which would not be served

if the existing Victor-Lugo line should fail. Luz claims, “the new

line ensures that future load growth will be accommodated within

the guidelines of Edison’s reliability criteria.” Edison counters

'2 The PEA is the environmental documentation which an applicant is

required to submit with a request for a CPCN pursuant to Rule 17.1! of

. the Commissions Rules of Practice and Procedure.

Nid a Caran S

A-43

that Luz has neglected to consider an important element of SCE’s

transmission planning criteria, which states that a major load

cannot be unserved for a “protracted” period. Edison submits that

because of Luz’s omission and the lack of testimony on its Major

Load Criteria there is no support for Luz’s statement.

The CEC argues that the line is needed to carry electricity

from new generating plants it believes will be built in the Mojave

area. McCuen states “It is highly probable that there will eventu-

ally be new generation sources developed by Luz International in

the Mojave. It is also possible, or even likely, that more geother-

mal generation will be developed at the Coso Naval Weapons

Center.” However, the SCE’s Electricity Report 7 (ER7) does

not project any additional QF or other new generation in this area.

This discussion seems to assume that the proposed project

could serve future growth by carrying electricity beyond the 630

MW that is already planned. While the lines would be physically

capable of carrying more power, SCE and Cal Energy seem to

agree that it would be inappropriate to plan for the line to carry

substantial additional generation. In addition, even if the new line

is considered capable of carrying additional power, there is no

benefit unless it is likely to to be used. The CEC’s own planning

documents seem to conflict with McCuen’s prediction that more

Luz and geothermal facilities are likely to be buit. Both Luz and

Cal Energy offered witnesses who could have easily provided that

information if it were true. While it is perfectly conceivable that

more plants will be built in the Mojave, the evidence must be

more solid than that before the ratepayers should be asked to pay

for the line.

4. System Security and Reliability

An addition to an electric transmission system makes that

system more reliable if it enhances the likelihood that the system

will be able to meet the demand of all of its customers. Parties

agree that the new line adds N-1 capability to the Kramer-Lugo

transmission path. N-1 capability is the ability to continue opera-

tions when one line fails. SCE argues that it doesn’t require the

N-1 capability along the Kramer-Lugo path because it has a

generation tripping scheme in place. In the current transmission

i Fe a eee ~~ Serra Oo ae eee ee, ee ee eee ee el ee ee eS eee ee ee” 7 eee ee oe ee ee

A-44

configuration, without a tripping scheme in place, an outage along

one of the Kramer-Lugo lines would cause a severe overload on

the remaining line, causing it to go out of service as well. By

tripping generation to prevent overloading the lines, SCE says

that it can currently serve all its load under N-1 conditions. (Ex.

38 p. 7.) SCE states that the proper way to evaluate the reliability

of a transmission system is in terms of service to the load: “The

ratepayers are not benefited by uninterrupted transmission of the

output from any given generator as long as load continues to be

served.” (Edison Reply Brief p. 44.) Edison’s witness Kritikson

said that if Edison required N-1 capability for serving every

generation sources then Luz and Cal Energy would have been

required to build two new lines to Kramer. (Tr. 756.)

DRA agrees with SCE. Because Kramer is a net generation

area, DRA finds the N-1 capability supplied by the line to be

insignificant. (DRA Reply Brief pp. 12-13.)

Luz asserts that the N-1 capability is “obviously” a system

benefit. (Luz Reply Brief p. 12.) In his testimony, Rupp stated

that “dropping generation to ensure overloads will be avoided is

not an acceptable measure for dealing with an N-1 outage. It

simply does not make sense to invest large amounts of money in

generation resources which would be dropped for ordinary N-|

transmission system failures.” (Ex. 20 p. 5.)

Cal Energy’s witness, Lewis, said that the N-1 capability

provided by the line would improve the firm transfer of energy

from the area. (Ex. 23 p. 12.) However, he also testified that

Edison’s generation tripping scheme is “a perfectly classical way”

of projecting the area. (Tr. p. 474.)

The CEC argues that neither SCE’s transmission reliability

Criteria nor any other utilities’ make a distinction for “net genera-

tion areas.” (Ex. 35 pp. 6-7.) The CEC maintains that, although

one can legitimately argue about its value, the N-1 capability is

desirable and creates a better, more reliable system than one

which relies on generation tripping. (CEC Reply Brief pp. 6-7.)

Just as was the case when considering the line loss question,

there is an attractive logic which applies here. SCE’s overall

electric system should be more reliable whenever it adds a new

ogee en SS ny, Tee eee eee

A-45

transmission line which connects generating sources to the load

center. However, an increase in reliability does not necessarily

provide a tangible benefit. Is there a tangible benefit to providing

N-1 reliability in a net generating area when the absence of N-I

capability does not appear to threaten the utility’s ability to meet

its load? In D.84-10-034, in which the Commission issued

CPCNs for the Devers-Valley, Serrano-Valley, and Serrano-Villa

Park transmission lines, the Commission discussed SCE’s relia-

bility criteria:

“Edison’s transmission reliability criteria basically require

that the outage of a single transmission or substation compo-

nent will not interrupt service to customers nor load compo-

nents in excess of their normal thermal ratings.

“It also requires (“N-2’ standard) that outages of two trans-

mission lines will not (1) cause a protracted interruption of

major load which is defined as 400 MW or more, (2) cause

line loadings on other system components in excess of their

emergency thermal ratings, nor (3) cause uncontrolled cas-

cading outages of additional electrical facilities.” (16 CPUC

2d 310, 324.)

This language suggests that SCE does consistently measure its

system reliability in terms of its ability tc meet load. While the

addition of the proposed project would provide N-! reliability to

Kramer, it is a “benefit” that is invisible to the ratepayers, who

would be no better served during an N-! outage than they are

now.

5. Emergency Support

SCE’s witness defines emergency support as reserve support

provided from other utilities. Because the proposed line does not

connect with another utility, SCE argues that it does not provide

any emergency support. (Tr. p. 785.) The CEC appears to

suggest that a project provides benefit to the electric system if it

improves the utility’s ability to serve load. Based on the testimony

of SCE’s Kritikson, the CEC claims that if the San Onofre

Nuclear Generating Station (SONGS) and Kramer had simulta-

neous failures, Edison could have problems serving load. (Reply

Brief p. 5.) However, in the testimony cited by the CEC,

= LL ee oe. ee eee oe PE ere Te tae ee eS ee ee eee eS Cee ee ee ee

- AP PUA A eS ee ee ee ee? Ree Pe Ue erage ae eee ee eo

A-46

Kritikson says that Edison would have less margin if it lost

Kramer, as indeed it would during any N-1 contingency. The

CEC’s own witness did not submit testimony on this issue.

Cal Energy’s witness, Lewis, states that QF generation is very

well suited to supplying emergency support. The proposed project

would allow all of the Kramer area generation to be available for

an emergency that affected generation in the LA Basin. (Ex. 23

p. 13.)

The definition of emergency support apparently relied upon by

the CEC and Cal Energy seems to make the concept of emer-

gency support virtually indistinguishable from system reliability.

If emergency support comprises a separate potential system-wide

benefit, then it must be somehow distinguishable. Based on the

record before us, we are not in a position to either agree that this

criterion is applicable, or to demand it. However, it is worth

noting that Cal Energy’s position on this issue emphasizes the

benefits of the QF power to be carried on the new line as opposed

to the benefits stemming from the line itself. Since QF benefits

are captured in the avoided cost payment, it would be inappropri-

ate to consider them when determining how to aliocate transmis-

sion costs.

6. Transfer Capability

SCE defines transfer capability as the ability to allow for

economy energy transactions or other support between utilitixs.

Since the Kramer-Lugo system is not interconnected with oth:r

utilities, the proposed project does not enhance transfer capability

of the type described by SCE. Cal Energy claims that Edison’s

definition is too narrow, that one should properly consider the

benefits from intra-utility support, e.g. during a gas curtailment

when nongas generation is increased, as well. (Cal Energy Reply

Brief p. 64.) For example during a recent natural gas curtailment,

Edison asked Kramer QFs to go to maximum generation. (Tr.

p. 382.)

DRA’s position is that transmission lines inherezitly increase

transfer capability and therefore that transfer carability should

not be characterized as a system benefit. (Tr. p. 665.) Cal Energy

says that DRA’s argument fails to recognize that there will be

Sy = Sa ee

So oe lt

capacity on the new line that will not be used by the currently

planned QFs. (Cal Energy Reply Brief p. 65.) DRA responds:

“Given the lack of surplus capacity on the Kramer-Victor line

once the additional QF generation has been added, it is evident

that the proposed project will not ‘by its very nature’ improve the

transfer capability of SCE’s Kramer-area transmission network.”

(DRA Reply Brief p. 40.)

CEC says that the proposed line will increase power transfer

capability from the Mojave area, which it characterizes as the

“area with the greatest generation growth within the SCE sys-

tem.” (Ex. 35 p. 9.) McCuen believes DRA was incorrect to say

that the transfer capability of the project is not a system benefit

because it is a “purpose of a transmission line.” He believes the

transfer capability provided by the line is a system benefit because

the project was built pursuant to a standard offer, the CEC

determined the generation resource was needed and because

DRA, SCE, and the CEC agreed that the increased transfer

capability is necessary to reliably transmit the QF power. (Ex. 35

p. 10.)

With this suggested criterion, as with others, experts disagree

as to what the term means, let alone whether or not a line which

enhances transfer capability would be creating a system-wide

benefit for that reason. Clearly, the proposed project will not

enhance transfers between utilities and will not enhance access to

economy energy. Beyond that, the evidence is insufficient for us to

find the existence of a system-wide benefit related to this

criterion.

7. Firm Resources at System Peak Conditions

Whether the line provides additional firm resources depends on

one’s definition. SCE states: “Firm generation is merely genera-

tion that is counted toward meeting Edison’s load and spinning

reserve requirements. Under contingency conditions, generation

that is iost is replaced by spinning reserves. This does not mean

that any generation which can be lost as a result of an N-1! cannot

be counted as firm.” (Edison Reply Brief p. 47; cf Tr. 759.) The

CEC’s witness, McCuen, defines firm generation as that having a

reasonably reliability, usually N-1. (Ex. 35 p. 11.)

it

A-48

Cal Energy’s Lewis witness describes firm resources as those

that are available with “100 percent reliability.” (Ex. 23 p. 14.)

He goes on to explain that “the implication is that there is no

constraint on maximum generation resources being applied to

meet a system peak condition as a consequence of the loss of a

transmission circuit, (i.e., an N-1 transmission contingency).”

Therefore, he finds that the line provides a benefit by increasing

the firm transfer capability from 500 MW to 1000 MW. (Ex. 23,

pp. 14-15.)

The discussion appears to treat this issue as a question of

system reliability. As such, it is not clear that this criterion adds to

the earlier analysis of reliability.

8. Cost Effectiveness

SCE argues that any analysis of cost-effectiveness must logi-

cally include cost-benefit studies. (Edison Reply Brief pp. 58-59.)

Because SCE believes that losses will increase, it does not find the

line cost-effective. Edison’s witness Kritikson testified that Edison

typically requires a 2:1 benefit to cost ratio for a loss reduction

project. (Tr. 736, 868.) Kritikson found Luz’s witness Rupp’s

calculations of benefit-cost ratios to be incorrect, because Rupp

used a project cost of $27 million instead of $50 million. This

reduces the benefit cost ratio from 2.56:1 to 1.39:1, assuming $69

million in loss savings. (Tr. 750.)

While basically this issue hinges on whether one believes the

line will decrease system losses, it is worth noting that even given

savings of $70 million, the benefit cost ratio is far from Edison’s

2:1 criteria.

Using a different definition of cost-effectiveness, CEC’s witness

McCuen finds the line to be cost-effective because it would be

more expensive if the QFs had to build lines to Edison’s loads.

McCuen also states that the settlement agreement also adds to

the cost-effectiveness of the line. (Ex. 35 p.11.)

9. QF Generation and Better Air Quality

Some parties argued that QF generation is intrinsically “better”

than utility generation and that any transmission line which

delivers QF generation to the load must therefore have system-

——————EEE =

A-49

wide benefits. For example Cal Energy notes that “the availability

and the cost of fossil fuels are uncertain, whereas with solar and

geothermal steam resources there are no such uncertainties, and

utilization is environmentally benign.” (Cal Energy Opening

Brief p. 37.) DRA counters that the Commission should be

technology neutral, as it has been in the past. (DRA Opening

Brief pp. 19-20.) DRA believes the environmental benefits of the

QFs are irrelevant. (DRA Reply Brief p. 7.)

Cal Energy argues that the line is a benefit because geothermal

production has lower incremental cost than conventional thermal

generation. Therefore the line enhances operating economies.

(Cal Energy Opening Brief p. 37; cf Tr. pp. 418-419.)

DRA replies that if it is appropriate to consider QF technology

a benefit, then one should also consider the higher cost of QF

power. (DRA Reply Brief p. 22.) SCE offers a comparison of the

utility’s marginal cost calculated in SO | rates to the higher SO 2

and SO 4 rates Luz and Cal Energy will be paid and notes that

the ratepayers are paying more for the QF generation than they

would for Edison’s. (Edison Opening Brief p. 63.)

In terms of environmental benefits, Cal Energy states that the

new line will improve air quality by providing clean energy to

displace fossil generation in LA Basin. (Ex. 23 p. 15.) The new

line will also reduces losses, also improving air quality. (Ex. 19

pp. 12-13.) The CEC also finds that the reduction in line losses

means less fossil fired generation which means better air quality,

which is a significant benefit. (CEC Reply Brief pp. 11-12.) The

CEC witness also stated that Luz and Cal Energy generation has

significant air quality benefits. (Ex. 22, pp. 9-13.) Kritikson

agreed that generation imported to the LA Basin reduces emis-

sions from plants within the Basin. (Tr. 911.)

Some parties (e.g. Rupp Ex. 19 p. 12) found that the reduction

in line losses means less generation and therefore less air pollu-

tion. Because Edison does not believe there is a loss reduction, it

does not believe there is an associated air quality benefit. (Ex. 38

p. 9.)

As we have mentioned in response to earlier system-wide

benefits arguments, for the purpose of allocating transmission

A-50

costs, benefits inherent in the QFs themselves should not be

considered. The Commission certainly encourages the develop-

ment of QFs which use renewable energy sources and reduce

pollution. That encouragement is in the form of avoided cost

payments. In the Biennial Plan Update (BRPU) proceeding

(1.89-07-004) we are considering whether or not environmental

benefits of potential QFs should be given weight in the bidding

process. However, the question before us here is entirely different.

Obviously, the new line is needed to transmit QF power. The

question affecting cost allocation is whether or not the new line

itself provides system-wide benefits that go beyond the fact that

the power being delivered is generated by QFs.

Air quality benefits from the line itself might be significant. If

the new line reduces overall transmission losses, then less genera-

tion will be needed and less fossil fuel will be burned. Unfortu-

nately, the line loss analysis provided in this record is

inconclusive. Thus, we cannot find that this line will produce

system-wide benefits in the form of air quality improvements.

10. Conclusions to be Drawn About System Benefits

We are left with only a small number of firm conclusions. First,

there is no clear answer as to whether the new line creates

system-wide benefits. Second, the policy set forth in D.85-09-058

may be in need of clarification in a generic proceeding.

There are aspects of this project which militate against a clear

finding of system-wide benefits. First, the cumulative size of the

QFs being developed by these operators is too great to allow us to

simply fal! back on a generalized notion of cost responsibility. We

are not faced, here, with a single facility which wil! occupy a small

fraction of the useful capacity of a transmiss:o: line which can

serve many other purposes. These projects are large enough to

need their own 220 kV transmission system. Although the new

line might prove useful to the SCE system in other ways, those

uses are clearly subordinate to the need to transmit as much as

630 MW of QF generation. SCE ciaims, and Cal Energy seems to

agree, that there will be very little, if any, room for other users on

the new line.

ee — oe a ee a ae ee

A-51

Second, the remoteness of the QFs from the SCE load center

takes much of the system-wide benefits analysis alluded to in the

1985 decision into the realm of conjecture. Will a more substan-

tial localized demand ever develop in the Mojave Desert? Will

more firms try to construct additional QFs in the area? Is there

any chance that SCE will ever seek to interconnect its northern

desert transmission system with other utilities to the east or

north? Transmission lines in this area are not easily categorized

and there is no tidy formula for measuring potential system-wide

benef

This text is long and has been trimmed here. Open the source document for the complete record.

This is a copy of a public record, reproduced as it was published. It is not legal advice, and it may not be the version a court would rely on. Check the official source before you cite it.

A word about cookies

We need a few to keep you signed in and the library working. The rest help us see which pages people use and where they get stuck. They stay off unless you say yes.