Appendix — Massachusetts v. United States Nuclear Regulatory Commission
Supreme Court brief1991
Ask Donna
What actually matters in this document.
Text
EDITOR S NOTE:
THE FOLLOWING PAGES WERE POOR HARD COPY
AT THE TIME OF FILMING. IF AND WHEN A
BETTER COPY CAN BE OBTAINED, A NEW FICHE
WILL BE ISSUxD.
a“ OZ, Beets Caw UST
60-1657 if FILBD
In the i APR 25 1981
Supreme Court of the United’Statesy® currk |
October Term, 1990
COMMONWEALTH OF MASSACHUSETTS
SEACOAST ANTI POLLUTION LEAGUE,
NEW ENGLAND COALITION ON
NUCLEAR POLLUTION, TOWN OF HAMPTON
Petitioners,
V.
NUCLEAR REGULATORY COMMISSION, et al.
Respondents.
Appendix to Petition
for a Wnit of Certiorari to the
United States Court of Appeals for
the District of Columbia Circuit
Volume I
Scott Harshbarger
Attorney General
of Massachusetts
Matthew T. Brock
Leslie Greer
*James R. Milkey
Assistant Attorneys General
One Ashburton Place
Boston, Massachusetts 02108
*Counsel of Record (617)727-2200
(Counsel for the co-petitioners are listed on the
inside of the front cover.)
COUNSEL FOR CO-PETITIONERS
ROBERT BACKUS
Seacoast Anti Pollution
League
DIANE CURRAN, ESQ.
New England Coalition On
Nuclear Pollution
PAUL MCEACHERN, ESQ.
Town Of Hampton
COMMONWEALTH OF
MASSACHUSETTS, et
al., Petitioners,
-
UNITED STATES NUCLEAR REGULATORY
COMMISSION and the United States of
America, Respondents,
Public Service Company of New Hampshire,
Towns or Cities of Ashburnham, et al.,
Intervenors.
Nos. 89-1306, 90-1132 and 90-1218.
United States Court of Appeals,
District of Columbia Circuit.
Argued Sept. 18, 1990.
Decided Jan. 25, 1991.
Petitions for review of Nuclear
Regulatory Commission's (NRC) licensing
of nuclear power plant were
consolidated. The Court of Appeals,
Buckley, Circuit Judge, held that: (1)
NRC's interpretation of emergency
response plan was not plainly
inconsistent with regulatory language;
(2) agency interpretation was not
contrary to mandate of Authorization
Act; and (3) remand was required for
determination of whether appeal board
properly considered potential
materiality of allegations concerning
on-site weaknesses identified in full
participation exercise.
Petitions denied in part and granted
in part.
Before BUCKLEY, WILLIAMS and
RANDOLPH, Circuit Judges.
Opinion for the Court filed by
Circuit Judge BUCKLEY.
+ a
BUCKLEY, Circuit Judge:
This action consolidates three
petitions for review of the Nuclear
Regulatory Commission's licensing of
Seabrook Nuclear Power Station.
Petitioners are the Commonwealth of
Massachusetts, the Seacoast
Anti-Pollution League ("SAPL"), and the
New England Coalition on Nuclear
Pollution ("NECNP"), all intervenors in
the agency's licensing proceedings.
Public Service Company of New Hampshire
("PSNH") has intervened here as leader
of the consortium of utilities that owns
and operates Seabrook. '
In No. 90-1132, petitioners raise
three issues concerning the Commission's
authorization of the plant's full power
license. They challenge the
Commission's decision to allow
authorization of the full power license
despite a prior agency ruling requiring
further consideration of Seabrook's
offsite emergency response plans. They
also challenge a ruling excluding from
the licensing record evidence about the
potential consequences of hypothetical
radiological emergencies at Seabrook.
Finally, they challenge the Commission's
denial of a waiver of regulations
exempting PSNH, as a regulated utility,
from the requirement of demonstrating
financial qualifications.
In No. 89-1306, petitioners raise
two issues relating to the plant's low
power licensing. They claim the
Commission misconstrued the scope of a
contention they had filed concerning the
possible fouling of Seabrook's cooling
System, and they claim the Commission
improperly authorized the low power
license without conducting an
adjudicatory hearing on potential flaws
in Seabrook's onsite emergency plan,
allegedly revealed in a June 1988
emergency exercise. The third
consolidated petition, No. 90-1218, was
filed as a precaution to preserve
petitioner's opportunity for appellate
review of the full power issues; it
Simply duplicates No. 90-1132.
We deny in their entirety the
petitions in Nos. 90-1132 and 90-1218
for review of the full power license
issues. In No. 89-1306, we deny the
petition for review of the’ Commission's
action concerning the coolinc system
contention; we grant review, however, of
the decision concerning the exercise
contention, and we remand to the agency
oo
for further explanation of its reasoning
on this issue. In the interim, we will
allow the operating licenses for
Seabrook to remain effective.
I. BACKGROUND
A. Regulatory Overview
Under section 182(a) of the Atomic
Energy Act of 1954 ("AEA"), as amended,
42 U.S.C. §§ 2011-2296 (1988), the
Nuclear Regulatory CommisSBion ("NRC: or
"Commission") is authorized to approve
the operation of nuclear power plants
that the agency finds “will provide
adequate protection to the health and
safety of the public." 42 U.S.C.
§ 2232(a). See also 10 C.F.R.
§ 50.57(a)(3) (1990). In accordance
with the notice and hearing requirements
of section 189 of the AEA, 42 U.S.C.
§§ 2239, the procedural requirements of
_ =
the Administrative Procedure Act, 5
U.S.C. §§ 551-559, and the procedures
set forth in its own regulations, 10
C.F.R. Part 2, the NRC conducts formal
adjudicatory hearings on all contested
issues, called “contentions,” that are
raised by interested parties in response
to applications for a nuclear plant
operating license. Licensing hearings
are conducted by a three-member Atomic
Safety and Licensing Board ("Licensing
-Board") whose duties are to admit and
decide contentions and, if the
contentions are resolved in the
applicant's favor, to authorize the
requested license. See 10 C.F.R.
§§ 2.750, 2.772. Appeals from Licensing
Board decisions are heard by a panel of
the Atomic Safety and Licensing Appeal
Board ("Appeal Board"), id. §§ 2.785,
2.787, and the Commission may, in its
discretion, undertake further review,
id. § 2.786.
A Licensing Board authorization of a
low power testing license, which permits
operation of a plant at up to five
percent of rated power, becomes
immediately effective notwithstanding
any appeals taken within the NRC. Id. §
2.764(a),(£). Such authorizations are
subject to motions for stay, and the
Commission reserves the power to step in
at any time. Id. § 2.764(£)(2).
Authorization of an operating license
that permits more than five percent
power operations does not become
effective until the Commission itself
has conducted an “immediate
effectiveness” review of the Licensing
Board's initial decision.
Id. § 2.764¢(£)(2)(i), (ii). After a
positive immediate effectiveness review,
the authorization becomes effective
without prejudice to any
==
pending administrative appeal of the
Licensing Board's dec.sion or any
further motions or formal adjudication.
Id. § 2.764(g).
An applicant for a nuclear plant
operating license must provide detailed
plans for coping with radiological
emergencies on the plant site and for
ensuring offsite emergency
preparedness. See id. § 50.34(b)(6)(v);
id. Part 50, Appendix E.III, .IV. The
NRC requires the applicant to submit
emergency response plans prepared by
state and local governments whose
jurisdictions lie within designated
emergency planning zones ("“EPZs")
Surrounding the plant. Id. § 50.33(g).
The “plume exposure pathway” EPZ is
generally a circular zone with a radius
of approximately ten miles; the
ate
“ingestion pathway” EPZ is a larger
circle measuring approximately fifty
miles in radius. The exact
configurations of the EPZs depend on the
particular characteristics of each
site. Id. §§ 50.33(9g), 50.47(c)(2).
Offsite planning primarily focuses on
protective measures for people within
the plume exposure pathway. EPZ. See,
e.g., id. § 50.47(b)(5), (10). In the
ingestion pathway EPZ, the focus is on
protecting the food sources from
fallout. See id. §§ 50.33(9),
50.47(c)(2).
The NRC will not authorize an
operating license unless it finds
“reasonable assurance that adequate
protective measures can and will be
taken in the event of a radiological
emergency.” Id. § 50.47(a)(1). The
«tin
EEE eee eee aa raeaQQ
NRC's findings on the adequacy of
protective measures are based on a
determination by the Federal Emergency
Management Agency ("FEMA") that the
state and local response er for the
offsite EPZs are adequate and can be
implemented, and on an NRC assessment of
the adequacy and implementability of the
Id.
applicant's onsite emergency plans.
§ 50.47(a)(2). A FEMA finding
constitutes a rebuttable presumption on
the adequacy of an offsite plan. Id.
Low power licensing requires the
approval of an onsite emergency plan but
does not require any assessment of
offsite emergency preparedness. Id.
§ 50.47(d).
Paragraph (b) of the emergency
planning regulation sets forth sixteen
specific standards that response plans
tia
must meet. Id. § 50.47(b) .7/6
Yaragraphs (a) and (b) of the
uergency planning regulation set out in
their entirety in the accompanying
Appendix.
U
Failuie to meet these standards “may
result in the Commission[s] declining to
issue an operating license,” but the
applicant will have the opportunity to
demonstrate that the license should
still issue where, inter alia,
“deficiencies in the plans are not
significant for the plant in question.”
Id. § 50.47(c)(1). Further detailed
guidance fot emergency planning 1s
contained in 10 C.F.R. Part 50, Appendix
E.IV ("Content of Emergency Plans” ) one
De te
in emergency preparedness gu eline
developed and published jointly by FEMA
and the NRC, NRC & FEMA, Criteria for
Preparation and Evaluation of
Radiological Emergency Response Plans
{
nas
and Preparedness in Support of Nuclear
Power Plants, NUREG-0654/FEMA-REP- 1
(rev. 1 Nov. 1980) (NUREG-0654") . Where
state or local} governments in the EPZsS
refuse to participate in emergency
planning, the applicant must substitute
‘ts own offsite response plan, and such
a “utility plen” is also evaluated
against the paragraph (b) standards. 10
C.F ek. 3 50.47(c) (1) (111).
B. Full Power Licensing proceedings
The full power licensing issues
before the court pt incipally involve the
Licensing Board's approval of Seabrook’s
offsite emergency P lans. The New
Hampshire radiological Emergency
Response Plan Revision 2 ("NH Plan”) is
a state plan covering the New Hampshire
communities within the plume exposure
pathway EPZ. The Seabrook Plan for
«i
Massachusetts Communities ("Utilities
plan”) 1S 84 plan that was developed by
PSNH and the other owner-utilities
pursuant to 10 C.F.R. § 50.47(c) after
Massachusetts and the Massachusetts
communities within the EPZ declined to
participate in emergency planning.
During adjudicatory hearings on the
adequacy of the NH Plan, petitioner
Massachusetts proffered evidence of
potential radiation doses that would
result from specific hypothetical
accidents at Seabrook. The evidence was
intended to support petitioners’
contentions that the NH Plan could not
adequately protect the large numbers of
persons who visit the ocean beaches neal
Seabrook on summer weekends. The
evidence consisted of written testimony
from four expert witnesses: Steven Cc.
atte
Sholly, Dr. Jan Beyea, DI. Gordon
Thompson, and Dr. Jennifer Leaning
(collectively "Sholly/Beyes
testimony”). Joint Appendix (*JA*) at
160. (Unless jndicated otherwise,
202
citations to the joint appendix refer to
case no. 90- 1132.
Mr. Sholly’s testimony was offered
to explain that the generic emergency
ss guidelines on which section
fr
2a
preparedne
69.47 rests were developed on the bas15
of dose-distance aspessments performed
for a range ot accident scenarios. JA
at 171. Dr. Beyed would then predict
the level of protection the NH Plan
would actually provide to the peak® ye
summertime beach population in terms of
the potential radiation doses that could
result from various accident scenalivs.
id. at 172. Or. Thompson's testimony
elSe-
proposed to address the likelihood and
characteristics of a catastrophic
atmospheric release of radiation at
Seabrook. Id. at 174. Finally, Dr.
Learning was to describe the health
effects that such accidents would have
on the beach population. Id. The stated
premise of these experts’ testimony was
that a site-specific examination of the
potential dose consequences of various
accidents would illuminate the
effectiveness of the offsite emergency
measures planned. Id. at 187.
The Licensing Board refused to admit
the Sholly/Beyea testimony on the ground
that such evidence is novwieltevant: to
the review of emergency response plans
under section 50.47. JA at 144-59. On
interlocutory appeal, the Appeal Board
certified to the Commission the question
whether the evidence should be admitted
in light of a prior Commission opinion,
ofitin
{
Long Island Lighting Co. (Shoreham
Nuclear Power Station, Unit 1),
CLI-86-13, 24 N.R.C. 22, 30 (1986)
("Shoreham") in which the Commission had
stayed that a goal of emergency planning
is “reasonable and feasible dose
reduction under the circumstances." See
Public Service Co. of New Hampshire
(Seabrook Station, Units 1 and 2,
ALAB-922, 30 N.R.C. 247, 255-59 (1989).
In the meantime, on December 30,
1988, the Licensing Board issued a
l4l-page partial initial decision
approving the NH Plan. Public Service
Co. of New Hampshire (Seabrook Station,
Units 1 and 2), LBP-88-32, 26°N.R.C. 667
(1988).*6
Each of the NRC rulings related to
Seabrook bears the caption “Public
Service Co. of New Hampshire (Seabrook
Station, Units 1] and 2)," fullowed by
its respective decision number, with the
prefix “LBP” denoting the Licensing
~~
Board, “ALAB,” the Appeal Board, and
"CLI," the Commission. For ease and
clarity, we will simply refer to all of
the Seabrook rulings by their decision
numbers.
U
The Board made findings on twenty-six
litigated contentions relating to eight
general aspects of the plan. See id. at
669-70. While the Board found it
necessary to make four specific
revisions of the plan and to retain
Jurisdiction over a subissue relating to
one of those revisions, it concluded
that, subject to later verification that
the necessary revisions had been made,
the plan met the requirements of 10
C.F.R. § 50.47(b) and Part 50, Appendix
E, and reasonably assured that“adequate
protective measures were available for
the New Hampshire portion of the EPZ.
See 28 N.R.C. at 804-05.
nit.
Petitioners appealed this decision
while hearings continued on other
segments of offsite emergency planning.
On November 7, 1989, the Appeal Board
handed down an opinion reviewing four of
the eight categories of issues resolved
in LBP-88-32. ALAB-924, 30 N.R.C. 331
(1989). The Appeal Board generally
affirmed the Licensing Board's findings
and conclusions but reversed and
remanded four issues “for further action
consistent with this opinion.” Id. at
373. The remanded issues involved the
possible need for letters of agreement
with school personnel involved in
evacuating schoolchildrenwmehe aécuracy
of a survey intended to identify persons
with special transportation needs; the
accuracy of evacuation time assumptions
for advanced life support patients in
-~19-
hospitals, nursing homes, and other
special facilities; and the need for
further implementing details in the plan
for emergencies which sheltering would
be preferred protective action for the
beach population. Id. The Appeal Board
did not specify that its opinion
precluded issuance of a full power
license but did note that the lack of
implementing details fo beach sheltering
"is a deficiency that must be remedied."
Id. at 372 n. 194
Two days afvYer ALAB-924, on November
9, 1989, the Zicensing Board issued a
28l-page partial initial decision. The
decision addressed sixty-twotlét igated
contentions proferred by petitioners
relating to the Utilities ilan and a
1988 FEMA-graded, full participation
exercise of Seabrook's emergency plans
=
BEST AVAIL
(such an exercise being a prerequisite
to full power licensing under 10 C.F.R.
Part 50, Appendix E.IV.F.1). See
LBP-89-32, 30 N.R.C. 375, 380-84
(1989). The Board concluded that the
1988 graded exercise was adequate in
scope and revealed no fundamental flaw
in the Utilities Plan or the NH Plan;
that the 1988 exercise demonstrated that
the NH Plan was adequate and
implementable; and that the Utilities
Plan satisfied the requirements of
section 50.47(b) and Appendix E, and
reasonably assured that adequate
protective measures would be available
for the Massachusetts por PPOT MED 2: ae
See 30 N.R.C. at 650. Having thus
resolved all remaining licesening issues
in the applicant's favor (other than the
four remanded by the Appeal
ABLE COPY
the Licensing Board authorized a
Id. at
Board),
fi:ll power license for Seabrook.
651. The Board took note of the four
remanded issues and promised to provide
a supplemental decision explaining why
ALAB-924 did not preclude the immediate
issuance of an operating license. Id.
at 651 & n. 87.
Petitioners moved the Appeal Board
to vacate authorization of the full
power license, but the Appeal Board
refused to act before receiving the
Licensing Board's supplemental opinion.
JA at 1048. Subsequently, the
Commission decided sua sponte to assume
jurisdiction over peti Cionegy QOtion to
‘ rpaetash r
Wire. D
vacate; the Commission. reasoned that
because it was already scheduled to
decide the immediate effectiveness of
LBP-89-32 and the Sholly/Beyea
=>
evidentiary question, its resolution of
the motion to vacate would serve the
interests of etficiency. JA at 1051.
Thereafter, in its supplemental decision
of November 20, 1989, the Licensing
board analyzed the four remanded issues
in light of its familiarity with the
extensive factual record and concluded
that none of the deficiencies was
sufficiently significant to preclude
licensing and that any further action
concerning such issues could be
conducted through post-licensing
hearings. LBP-89-33, 30 N.R.C. 656
(1989).
On March 1, 1990, thes Commission
handed down its decision on the
certified question concerning the
Sholly/Beyea testimony. CLI-90-2, 21
wuim.G. 297 €i9Se?.« The Commission
a«23-
upheld the Licensing Board's ruling that
the testimony was inadmissible, holding
that “judgments on the adequacy of
emergency planning are to be based on
conformity with the sixteen planning
standards set forth in 10 C.F.R. §
50.47.(b)" Id. at 213. Relying on its
own guidelines and rulemaking statements
supporting section 50.47 and on prior
adjudicatory decisions, including its
Shoreham opinion, the Commission
reasoned that
consideration of specific accident
sequences and their potential dose
consequences has been rendered
unnecessary by the promulgation of
generic guidance that incorporates
and synthesizes data on a range of
accidents and their consequences.
Thus the seeming anomaly of
excluding proferred evidence on dose
consequences, where the objective of
the inquiry is to reduce dose
consequences, is in fact no anomaly
at all. For it is by applying the
generic guidance of the regulation's
~—) =
sixteen standards to the review of
individual emergency plans - not by
attempting to predict the effects of
particular hypothetical accidents
occurring under particular
hypothetical conditions of weather,
time of year, and time of day-that
the NRC satisfies itself that the
goal of achieving dose reductions is
met.
Id. 8st 215.
On the same day it decided this
evidentiary question, the Commission
issued a ruling denying petitioners’
motion to vacate and allowing the
immediate effectiveness and the
Licensing Board's decisions. CLI-90-3,
sa Bie. 240. €S5eer On the motion to
vacate, the Commission concluded that
the Licensing Board had not violated any
"clear, nondiscretionary duty” in
authorizing the license. Id. at
229-31. The Commission reasoned that
"nothing in ALAB-924 by its terms
precludes a full power authorization";
~~ =
that no NRC rule or decision “suggests
{a} duty on the part of the
Licensing Board to delay full power
authorization pending completion of
remand proceedings”; and that, "most
important for this case," the Licensing
Board's authority to act despite a
remand from the Appeal Board was
properly supported by 10 C.F.R. §
50.47(c)(1). 31 N.R.C. at 230. While
agreeing that the temanded issues were
remanded probative of compliance with
section 50.47(b), and thus would be
relevant to licensing, the Commission
noted that they were “not necessarily
materia] to license issuance because,
under § 50.47(c) [some] compliance
issues may not be significant and
therefore need not be resolved prior to
——
license
=) =
issuance.” Id. at 230-31 (emphasis
added).
In its immediate effectiveness
review, the Commission found that the
Licensing Board had acted reasonably in
determining that the remanded issues
were not significant and that this
determination did not preclude the
immediate issuance of a license. See
id. at 232-48. The Commission further
held that_the Licensing Board's findings
and conclusions in LBP-89-32 on the
adequacy of the Utilities Plan and the
FEMA-graded exercise not yet reviewed by
the Appeal Board, also met the immediate
effectiveness criteria set forth in 10
C.F.R. § 2.764(£)(2). See id. at
248-54. As a result, the Commission
allowed the full power license to take
effect, "with , however, the recognition
that administrative appeal processes (in
which later review of the Licensing
Board's decision[s] will take place)
will continue." Id. at 225.
On March 15, 1990, the full power
license issued. JA at 752. This court
denied a stay pending appeal, and
Seabrook thereafter began its ascension
to full power. Administrative appeals
and further adjudication before the
Licensing Board are ongoing.
The last NRC action petitioners ask
us to review in connection with the full
power proceedings is the Commission's
denial of their request for a waiver of
the financial qualification regulation.
CLI-89-20, 30 N.R.C. 231 (1989). The
NRC exempts regulated electric
utilities, like PSNH, from its general
rule requiring license applicants to
demonstrate financial qualification. 10
C.F.R. §§ 50.33(f£), 50.40(b). The
rationale for the exemption is that a
regulated utility usually can recover
through its rate base the costs of
safely operating a nuclear facility. 49
Fed. Reg. 35,747, 35,748 (1984).
Massachusetts and SAPL argued that a
waiver was justified pursuant to 10
C.F.R. § 2.758(b) because the rationale
for the exemption had been undercut by
"special circumstances," namely, the
fact that PSNH had filed bankruptcy. JA
at 397-537. The Licensing Board ruled
that petitioners failed to make a prima
facie showing for a waiver, LBP-89-10 29
N.R.C. 297 (1989), but the Appeal Board
certified the issue to the Commission,
ALAB-920, 30 W.R.C. 121 (1989).
«29.
Petitioners relied on a prior
Opinion rendered during Seabrook's low
power proceedings in which the
Commission had found that the purpose of
the exemption was undermined by the
combination of PSNH's bankruptcy and New
Hampshire's “antiCWIP" statute (which
prohibits a utility from increasing
customers’ rates to recover the costs of
construction work in progress). See
CLI-88-10, 28 N.R.C. 573, 592-98
(1988). In denying the later petition,
the Commission held that its low power
decision did not support a waiver of the
financial qualification exemption during
full power operations because "[nJothing
in the anti-CWIP law. . . prohibits
including Seabrook's operating costs in
the rate base when the plant is
operating to serve the public, as it
-30-
will be fully authorized to do if it
receives its full power license." 30
N.R.C. at 241 (emphasis in original).
The Commission also held that the
exemption would not be undercut by a
normal delay in cost recovery imposed by
the New Hampshire ratesetting process,
id., and that even if the rule were
undercut by exceptional circumstances,
petitioners had failed to show that a
Significant safety problem would result,
id. at 243-44.
C. Low Power Licensing Proceedings
A low power license permits an
applicant to initial fuel loading and
low-level testing before ascension to
full power operation. Because certain
requirements for full power licensing,
such as adequate offsite emergency
plans, are not relevant to low power
att.
operation, the NRC may, upon motion by
the applicant, issue a low power testing
license prior to the authorization of a
full power license, provided that all
contested issues material to low power
operations have been resolved in the
applicant's favor. See 10 C.F.R. §
50.57(c). The Licensing Board assigned
the adjudication of Seabrook's licensing
issues to two panels; one of them held
hearings on the offsite emergency
planning contentions discussed above,
and the second adjudicated all
contentions relevant to low power
licensing, including all onsite safety
and emergency planning issues. See
LBP-87-10, 25 N.R.C. 177, 181 (1987).
Petitioners seek review of the NRC's
action concerning two issues raised in
the low power proceedings.
|
In June 1982, petitioner NECNP
submitted a contention suggesting that
Seabrook's ocean-water cooling system
could fail because of the "accumulation
of mollusks, other aquatic organisms,
and debris.” JA, No. 89-1306, at 1. As
its basis for the contention, NECNP
pointed to an NRC notice in the Federal
Register discussing the problem of
cooling system blockage from sea animals
like clams and mussels. Id. at 2-3; see
47 Fed.Reg. 21,653 (1982). The
Licensing Board refused to admit the
contention. Several years later,
however, the Appeal Board reversed and
remanded the contention. ALAB-875, 26
N.R.C. 251, 261-63 (1987).
During the course of subsequent
proceedings, NECNP sought to compel
discovery of Seabrook's ability to
«B%o
detect and control "“microbiologically
induced coreanaes in its cooling
system. The Licensing Board denied
NECNP's motion to compel, ruling that
NECNP's cooling system contention was
limited to the accumulation of marine
Organisms and debris and did not
encompass the side-effects of
microbiological activity. JA, No.
89-1306, at 472-79. NECNP sought
reconsideration, submitting an expert
affidavit expressing the view that
microbiologically induced corrosion was
within the scope of the 1982
contention. Id. at 90. The Licensing
Board denied the motion to reconsider on
the ground that expert opinions were not
relevant to the question. Id. at
491-96. NECNP thereafter informed the
Board that it no longer wished to
«%@«
litigate the issue of blockage by
"“macro"-organisms, id. at 158-59, and
the contention was subsequently
dismissed as abandoned, id. at 499-501.
The Appeal Board accepted an
untimely appeal of the Licensing Board's
ruling on the scope of the cooling
system contention, ALAB-894, 27 N.R.C.
632 (1988), and later affirmed the
ruling, ALAB-899, 28 N.R.C. 93 (1988).
Based on the terms and the stated basis
of contention, the Appeal Board
concluded that the contention addressed
"blockage" of coolant flow to safety-
related systems, not “leakage” caused by
corrosion. 28 N.R.C. at 96-99. The
Appeal Board observed that instead of
raising this new issue within the terms
of the old contention, NECNP should have
proffered a late-filed contention. ld.
=i
at 99. The Commission denied review,
and the Appeal Board's decision became
final agency action.
The second low power issue raised by
petitioners relates to the June 1988
full participation exercise of
Seabrook's emergency plans. The NRC
inspection team overseeing the onsite
portion of the exercise issued a report
on July 6, 1988, which concluded that
"[n]o violations were identified"
during the drill and that the “response
actions were adequate to provide
protective measures for the health and
safety of the public." JA, No. 89-1306,
at 220. The report detailed various
strengths observed in the exercise and
also discussed some “weaknesses,”
including certain actions of onsite
plant personnel. Jd. at 223-24. In the
oY
opinion of the inspection team, five
weaknesses indicated that the plant's
Technical Support Center ("TSC") and
Emergency Operations Faciltiy ("EOF")
staffs displayed questionable
engineering judgment or failed to
recognized or address technical concerns:
Neither the EOF [nJjor TSC
staff questioned a release of
greater than 7000 curies per
second with only clad damage
and no core recovery;
Efforts continued to restore
the Emergency Feedwater Pump
after a large break LOCA
[Loss of Coolant Accident];
A questionable fix for the
Containment Building Spray
system;
A lack of effort to locate
and isolate the release path;
and
No effort was noted to
blowdown Steam Generators to
lessen the heat load in the
containment.
On September 16, 1988, petitioners
filed a motion requesting that the Board
~
i_
~
_——
admit a new contention, or in the
alternative reopen the record, based on
their allegation that the June exercise
had revealed fundamental deficencies in
the onsite emergency plan. Id. at 241.
On September 28, the NRC staff issued a
follow-up inspection report based on
further investigation, which concluded
that the actions of the plant personnel
had been acceptable after all and that
the matter of the weaknesses was
"considered closed." Id. at 274, 286-88.
The Licensing Board denied
petitioners’ motion on the grounds that
petitioners had failed to satisfy the
requirements for a late-filed
contention, set forth in 10 C.F.R. §
2.714(a)(1), and that the motion did not
meet the criteria for reopening a closed
hearing record, id. § 2.734. LBP-89-4,
=
29 N.R.C. 62, 68-86 (1989). The Appeal
Board affirmed, first, on the ground
that the Licensing Board did not abuse
its discretion in determining that the
motion failed to meet the late-filed
contention requirements; and, second, on
the “independent basis" that even if the
motion met those criteria, the proposed
exercise contention must be rejected
under Commission case law because it did
not involve a "fundamental flaw" in the
emergency plan. ALAB-918, 29 N.R.C.
473, 480-86 (1989). The Appeal Board
dic not reach the issue of whether the
motion satisfied the criteria for
reopening a closed record. Id. at 485.
The Commission declined further review;
thus the Appeal Board's ruling became
final agency action.
After various delays, the Commission
ultimately granted a low power testing
license for Seabrook in December 1988,
with two conditions: The applicants had
entn
to provide reasonable assurance that
sucficient funds would be available to
cover the costs of decommissioning the
plant should a full power license be
denied, and petitioners' then-pending
motion to litigate the onsite exercise
contention had to be resolved. See
CLI-88-10, 28 N.R.C. 573 (1988). With
the fulfillment of these conditions, the
Commission lifted its stay of the
license in May 1989. CLI-89-8 29 N.R.C.
399 (1989). After this court refused to
petitioners’ subsequent request for a
Stay, Seabrook began low power
operations.
ee DISCUSSION
A. Jurisdiction
[1,2] At the outset, we must sort
out the reviewability of the various
agency decisions implicated in these
-40-
petitions. This court has jurisdiction
over all final orders of the NRC that
are made reviewable by section 189 of
the AEA. 28 U.S.C. § 2342. Section 189
provides for judicial review of "[a]ny
final order entered in any proceeding,”
inter alia, “for the granting,
suspending, revoking, or amending of any
license." 42 U.S.C. § 2239(a)(b).
Generally, under these statutes, an NRC
order is final if it disposes of all
issues as to all parties in the
licensing proceeding, that is, if it
consummates the agency's decision-making
process and results in granting,
denying, suspending, revoking, or
amending a license. See NRDC, Inc. v.
NRC, 680 F.2d 810, 815 (D.C.Cir. 1982).
According to this strict rule of
finality, we plainly have jurisdiction
to review the low power issues raised in
é@t<
No. 89-1306 because the Commission has
issued a final order, CLI-88-10,
granting the low power testing license.
The full power petitions, however, are
another matter.
(3,4) In our opinion, the
Commission's immediate effectiveness
ruling, CLI-90-3, represents a final
agency order that is reviewable by this
court. As shown by our decision in
Oystershell Alliance v. NRC, 800 F.2d
1201 (D.C.Cir.1986), we will review an
immediate effectiveness decison even
though, under the procedures set forth
in 10 C.F.R. § 2.764, the Commission's
decision is not a final adjudication on
the merits and is without prejudice to
any pending administrative appeal or
Subsequent adjudication. See 800 F.2d
at 1206-07.
ait.
Such review is appropriate because it
will not disrupt the orderly process of
adjudication within the agency and
because significant legal consequences
flow from the Commission's action. See
Port of Boston Marine Terminal Ass'n v.
Rederiaktiebolaget Transatlantic, 400
0.8. 62, Fi, Di S.Ct. 2035 209. 27
L.Ed.2d 203 (1970). We also believe it
appropriate in this case to review that
portion of CLI-90-3 in which the
Commission refused to vacate the
Licensing Board's authorization of the
full power license, 31 N.R.C. at 225-31,
because that ruling was a necessary
predicate to immediate effectiveness.
[5] Of course, our examination of
CLI-90-3 is exceedingly limited. In an
immediate effectiveness review, the
Commission determines whether it is in
ai Dm
the public interest to lift the
administrative stay thet automatically
attaches to an initial authorization of
a full power license. This
determination is based on a weighing of
equitable considerations: “gravity of
the substantive issue, the likelihood
that it has been resolved incorrectly
below, the degree to which correct
resolution by the issue would be
prejudiced by operation pending review,
and other relevant public interest
factors.” 10 C.F.R. § 2.764(£)(2)(i).
Thus, our review of CLI-90-3 is akin to
the review of a district court's grant
of a preliminary injunction, see, e.g.,
Nationa] Wildlife Fed'n v. Burford, 835
F.2d 305, 319 (D.C.Cir.1987), and is
properly confined to determining whether
the Commission abused its discretion,
~44-
see Qystershell Alliance, 800 F.2d at
1206.
[6] We reject petioners' argument
that immediate effectiveness renders the
Licensing Board's decisions and all
related “intermediate, procedural or
preliminary non-final actions or
rulings" of the NRC reviewable by this
court under 5 U.S.C. § 704.
Petitioner's Motion Seeking Clarifaction
of Appellate Jurisdiction, filed Apr.
30, 1990, at 10. We already decided in
a related petition that LBP-89-32 is not
reviewable even after CLI-90-3. Order,
Massachusetts v. NRC, No. 89-1743 (D.C.
Cir. filed Mar. 7, 1990) (per curiam).
Furthermore, while section 704
authorizes judicial review of
preliminary or intermediate rulings “on
the review of the final agency action,"
s6t-
5 U.S.C. § 704, it does not give us
plenary jurisdiction over the entire
seabrook licensing litigation. The only
"final agency action” at issue here is
an order allowing the plant to operate
at full power pending the Commission's
further review of the licensing issues.
This order is not a "final decision" by
the Commission pursuant to 10 C.F.R. §
2.770. Section 704 authorizes us to
review only those preliminary,
intermediate, or procedural rulings that
relate to the final agency action
presently before the court.
Accordingly, we will consider the NRC's
full power rulings only to the extent
necessary to review the Commission's
exercise of discretion in allowing
immediate effectiveness.
ait.
[7] In particular, the Commission's
denial of a financial qualification
waiver, CLI-89-20 is interlocutory in
nature and is not independently
reviewable. We so held in dismissing an
earlier petition for review of
CLI-89-20, Order, Massachusetts v. NRC,
No. 89-1648 (D.C.Cir. filed Dec. 26,
1989) (per curiam), and we see nothing
in the immediate effectiveness decision
to alter than conclusion. Therefore, we
again decline to review CLI-80-20.
[8] Intervenor PSNH maintains that
the Commission's evidentiary ruling on
the Sholly/Beyea testimony in CLI-90-2
is also not a final licensing order
subject to our review. Brief for PSNH
at 22-23; see NRDC, Inc. v. NRC, 680
F.2d at 816 (ordinarily, agency's
evidentiary ruling is not a final
order).
~~
In Our Opinion, however, the peculiar
relationship between CLI-90-2 and the
commission's immediate effectiveness
decision of the same date, CLI-90-3,
makes the decision to exlude the
testimony properly reviewable. In
allowing immediate effectiveness, the
Commission observed that CLI-90-2 "forms
an important part of conclusions
regarding emergency planning for
Seabrook." CLI-90-3, 31 N.R.C. at 225.
Indeed, the Licensing Board believed
that its initial ruling on the relevance
of the Sholly/Beyea testimony “would
have the potential to affect the basic
Structure of the case in a pervasive
way,: JA at 144, and in certifying the
question of the Commission, the Appeal
Board stated that “this issue is
Cardinal to the resolution of a number
-~-48-
of matters in this proceeding.”
ALAB-922, 30 N.R.C. at 249. In sum,
there is little doubt that if its
decision on the relevance of the
testimony had gone in petitioners’
favor, the Commission would not have
allowed the immediate effectiveness of
the full power authorization. This
close link between the two decisions
renders our review ot CLI-90-2
appropriate.
B. Interpretation of Emergency Planning
Regulation.
In the NRC's view, an emergency
response plan provides “reasonable
assurance” of “adequate protective
measures” under 10 C.F.R. § 50.47(a)(1)
if it adequately satisfies the sixteen
paragraph(b) criteria in a way that is
implementable; the plan need not achieve
any minimum radiation dose savings 0!
~49-
minimum evacuation time in the event of
a specific accident. See CLI-90-2, 31l
N.R.C. at 208, 216-17. This approach is
thought most likely to produce a
flexible plan that offers the best
feasible means for minimizing harm to
the public from unpredictable accidents,
given the particular characteristics of
the plant site and the surrounding EPZ.
See id. at 215-17. If any interested
party believes that satisfaction of the
Sixteen standards alone will not produce
an adequate and implementable plan in a
particular case, the party may petition
the NRC uner 10 C.F.R. § 2.758 for a
waiver of section 50.47 to allow the
imposition of more stringent planning
requirements. See 1d. at 217.
Petitioners challenge this
interpretation of the emergency planning
regulation and the Commission's
consequent decision to exclude
Sholly/Beyea testimony.
Petitioners’ view of emergency
planning fundamentally differs from the
NRC's. It is their position that
section 50.47(a)(1l) requires the
Commission to judge an emergency plan in
terms of the actual dose of radiation
received by a particular EPZ population
in a hypothetical accident scenario.
The inference to be drawn from their
position is that a nuclear power plant
may not be licensed for full power
operation where the demography and
physical constraints of the planning
area are such that no feasible response
plan can provide substantial protection
under particular conditions. See Brief
for Petitioners at 13, 43-46; Brief for
ain
a
SAPL at 2-8. Because of the absence of
sufficient protective sheltering near
the beaches and the length of time
potentially required for a complete
evacuation of the beach population
during periods of peak use, they contend
that Seabrook is such a plant. See Oral
Argument of Robert A. Backus, counsel
for petitioner SAPL, Sept. 18, 1990:
QUESTION: Would you agree that
adequate sheltering is simply not
available on the beaches for the
beach population?
MR. BACKUS: Essentially, we agree
with that, Your Honor.
QUESTION: Then is it your position
that if there cannot be protection,
a license may not issue?
MR. BACKUS: That is our position.
QUESTION: That this is a
aS%s
characteristic inherent in the
choice of the site?
MR. BACKUS: That's correct, Your
HONOr.
This basic, irreconcilable conflict
fuels petitioner's challenge to the full
power licensing of Seabrook. For that
reason, we will address CLI-90-2 before
turning to the immediate effectiveness
ruling. As discussed below, we decline
to disturb the Commission's application
of section 50.47.
Our standard of review on this
question is necessarily deferential. We
will not overturn the Commission's
interpretation of its own emergency
planning rule “unless that
interpretation is plainly inconsistent
with the language of the regulation[].”"
San Luis Obispo Mothers for Peace v.
=.
NRC, 789 F.2d 26, 30 (D.C.Cir.) (en
banc) ("Mothers for Peace JI"), cert.
denied, 479 U.S. 923, 107 S.Ct. 330, 93
L.Ed.2d 302 (1986). If its reading of
section 50.47 satisfies that standard,
the Commission's application of the
regulation to exclude petitioners’
expert testimony may be set aside only
if it was arbitrary, capricious, an
abuse of discretion, or otherwise
contrary to law. See 5 U.S.C.
§ 706(2)(A) (1988). Moreover, the
Commission's licensing decisions are
generally entitled to the highest
judicial deference because of the
unusually broad authority that Congress
delegated to the agency under the Atomic
Energy Act. Carstens v, NRC, 742 F.2d
386, 1551 (D.C.Caic. 19646), cert.
denied, 471 U.S. 1136, 105 S.Ct. 2675,
86 L.Ed.2d 694 (1985).
Petitioners argue “hat we should not
defer to the Commission's interpretation
of section 50.47 or the decision to
exclude the Sholly/Beyea testimony on
the ground that the NRC lacks expertise
in the area of emergency planning. They
contend that Congress recognized this
supposed lack of expertise when it
required the NRC to develop and
implement mandatory offsite planning
standards in consultation with an agency
more specialized in emergency response,
FEMA, see 1980 NRC Authorization Act,
Pub.L. No. 96-295, § 109, 94 Stat. 780,
783-85 (1980), thereby indicating
dissatisfaction with the failure of the
"checklist" approach to offisite
planning that the NRC employed prior to
the Three Mile Island ("TMI") accident
=-55-—
in 1979.
Petitioners have confused the
judicial deference that is given when
the NRC makes “predictions, within its
area of special expertise, at the
frontiers of science," Baltimore Gas &
Elec. Co. v, NRDC, 462 U.S. 87, 103, 103
S.Ct. 2246, 2255, 76 L.Ed.2d 437 (1983),
with the deference presumptively owed an
agency's interpretation of its own
regulations and with the heightened
deference for NRC licensing decisions
that flows from its broad statutory
mandate. The latter two bases for
judicial deference fully apply here.
In particular, the 1980
Authorization Act, an expired fiscal
appropriations of law, was not in effect
when CLI-90-2 was decided and therefore
did not limit the licensing discretion
~ ?
otherwise conferred on the Commission by
Congress. Moreover, petitioners’
argument that the NRC lacks expertise in
offsite emergency planning was expressly
rejected in Massachusetts v. United
States, 856 F.2d 378 (lst Cir. 1988),
where the court held that "[t]Jhe
substantive area in which an agency is
deemed to be expert is determined by
statute; here, under the relevant
congressional enactments .. . , the NRC
is specifically authorized and directed
to determine whether emergency plans
adequately protect the public.” Id. at
382. We agree with the First Circuit.
Accordingly, we see no reason to depart
from the highly deferential standard of
review outlined above.
Our analysis must begin with the
wording of section 50.47.
me, %
Petitioners argue that the Commission's
interpretation violates the plain
language of the regulation because
protective measures cannot possibly be
judged “adequate,” as required by
section 50.47(a)(1), without
consideration of their actual
effectiveness in protecting the public.
That conclusion, however, is not
compelled by a straightforward reading
of the rule.
The Commission observed that
"“{[nJothing in the regulation contains
any suggestion that calculations of dose
consequences are intended to play a role
in the evaluation of a plan's
adequacy.” CLI-90-2, 31 N.R.C. at 214.
We cannot say that this judgment is
flatly contradicted by the language or
Structure of section 590.47. As we have
tin
previously noted in determining that a
response plan need not consider a
particular emergency event like an
earthquake, section 50.47 "“make[s] no
reference to specific conditions or
accident sequences." Mothers for Peace
II, 789 F.2d at 43. Paragraph (a)
appears to state the general goal of the
regulatory scheme for emergency
planning. As we earlier observed,
paragraph (a) “does not address any
particular emergency . . .; rather, it
sets forth a general standard that
envisions judgment and implies
Ganmcrecson.” id. st 31. Paragraph (b)
then enumerates specific standards that
a response plan “must meet,” presumably
for the purpose of achieving the goals
of adequacy and implementability. 10
C.F.R. § 50.47(b). None of these
at}.
specific standards requires the
Commission to measure a plan against
particular hypothetical scenarios.
Other provisions in the regulation
indicate that the core of the
Commission's inquiry is compliance with
the generic standards of paragraph (b).
Paragraph (a)(2) provides that FEMA's
determination supporting the “reasonable
assurance" finding "will primarily be
based on a review of the plans," 10
C.F.R. § 50.47(a)(2), which will
necessarily focus on the contents
required by paragraph (b) and Part 50,
Appendix E.IV. Paragraph (c)(1)
provides, inter alia, that “[fJailure to
meet the applicable standards set forth
in paragraph (b) of this section may
result in the Commission['s] declining
to issue an operating license," unless
-60-
the applicant for the license can
demonstrate to the Commission's
satisfaction that deficiencies in the
plan are not significant for the plant
in question, that interim measures will
compensate for the deficiencies, or that
there are other compelling reasons to
permit licensing. io. S 30.47(e) (i).
In the event the applicant must
develop its own response plan as a
result of a refusal by state and local
governments to participate in emergency
planning, the regulation provides that
the “utility plan will be evaluated
against the same planning standards
applicable to a state or local plan, as
listed in paragraph (b) of this
section,” with certain allowances for
the lack of governmental participation.
Id. § 50.47(c)(1)(iii). Under paragraph
«ft.
(d), the NRC's evaulation of onsite
emergency planning for purposes of low
power licensing requires a similar
finidng of reasonable assurance of
adequate protective measures, which will
be based on the NRC's “assessment of the
applicant's onsite emergency plans
against the pertinent standards in
paragraph (b) of this section and
Appendix E." Id. § 50.47(d).'
All of these provisions bolster the
Commission's conclusion that “adequacy
is to be judged by conformity with the
planning standards." CLI-90-2, 31
N.R.C. at 214. These sixteen standards
were derived from assessments of a
spectrum of possible radiological
accidents, and the NRC has concluded
that they provide an appropriate basis
for arriving at a plan that will be
=).
comprehensive and flexible. See id. at
215-17. Petitioners’ construction of
paragraph (a) is certainly plausible,
perhaps even desirable as a matter of
policy, but it not the only reasonable
reading of the regulation. We conclude
that the Commission's interpretation is
not plainly inconsistent with any
language in section 50.47.
Petitioners further argue that the
agency interpretation is contrary to the
mandate of the 1980 Authorization Act,
in which Congress directed the NRC tx
establish and enforce standards for
N
+
offsite emergency plans. See Pub.
96-295, § 109, 94 Stat. at 783-84.
Section 109 of the NRC Authorizatior
Act 1S reprinted in the Appendix
following this opinion.
Uj
They point to language in the
Authorization Act indicating that a
response plan was to “provide[]
reasonable assurance that public health
and safety is not endangered," id. §
109(b)(1)(B)(i)(II); that the NRC was
required to “assess the adequacy” of
existing plans, id. § 109(b)(3); and
that the agency was directed to report
t Congress n the emergency response
Capabilities available for plants with
existing construction permits (which
Seabrook) and to determine “the
Maximum zone in tne vicinity of each
sucn facility for which evacuation of
individuals is feasible at various
different times corresponding to the
representative warning times for variou:
different types of accidents,” id.
§ 109(c). Petitioners contend that
rnese
provisions required the NRC to judge the
effectiveness of a particular plan's
protective measures vased on “the degree
to which the public is actually
protected by those measures. Brief for
Petitioners at 27.
We do not agree that the
Authorization Act required the NRC to
develop standards for evaluating each
emergency plan in terms of an actual
reduction in potential radiation
exposure. The Act directed the agency
to promulgate planning standards by rule
and to require as a condition of
licensing that for each plant there
exist either a plan that complies with
the NRC's regulatory’s standards for
responding to a radiological emergency,
or in the alternnative, a plan that
offers reasonable assurance that public
=¢5-
health and safety will not be
endangered. Pub.L. No. 96-295,
§ 109(b)(1). This congressional mandate
left to the NRC's discretion the |
specific requirements of emergency
planning. The alternative structure of
section 109(b) reflects Congress's
assumption that the NRC could develop
generic standards that would reasonably
assure the public safety without having
to examine the specific safety
consequences of each emergency plan for
each plant.
Petitioners do not contend that the
agency failed to comply with section
109(c) cf the Act, which simply required
the NRC to report to Congress on the
emergency response capabilities of each
plant then under construction and to
include in that report a description of
oli o.
the maximum feasible emergency planning
zone for such plant. See id. § 109(c).
The fact that Congress directed the NRC
to identify enlarged EPZ's for all new
facilities with reference to feasible
evacuation times does not signify that a
response plan could only be approved if
it would achieve some minimum safe
evacuation time for persons in the EPZ.
This provision did not constrain the
NRC's discretion to define generic
standards for such protective measures.
See H.R.Rep. No. 1070, 96th Cong., 2d
Sess. 27 (1980) (conference report)
(while designation of EPZ should
consider capability to implement
protective measures such as evacuation
and sheltering quickly and safely,
minimum requirements for planning
standards left to NRC discretion.)
a?
[13] Petitioners offer a second
statutory basis for their contention
that the adequacy of emergency planning
must be measured by the actual]
mitigation of harmful consequences. As
a result of the TMI accident, they
argue, the NRC came to realize that
emergency planning is an essential
“first tier" safety requirement, along
with siting and design engineering, for
achieving “adequate protection to the
health and safety of the public,” the
goal of licensing under section 182(a)
of the AEA, 42 U.S.C. § 2232(a). See 44
Fed. Reg. 75,167, 75,169 (1979)
(rationale for promulgation of section
50.47). They conclude from this that
the 1980 Authorization Act required that
the same standards be applied in
determining the adequacy of offsite
-~68-
lil
emergency planning as are applied in
determining the adequacy of site
selection and plant design.
From this premise, petitioners
reason that each emergency response plan
must be judged to provide effective
protection for the public from
hypotehtical accidents that surpass the
containment capabilities of engineered
safety features and onsite precautions.
The only possible measure of such
effectiveness they claim is dose
consequences.
Petitioners contend that in its 1980
rulemaking proceedings on emergency
planning, the NRC embraced this concept
and, in response to the Authorization
Act, rejected the pre-TMI practice of
relying on a checklist to guide state
and local authorities in the development
of emergency plans because that approach
-69-
was insufficient to achieve “adequate
protection." Petitioners argue that the
Commission's current intrepretation of
section 50.47 represents a throwback to
the pre-Authorization Act practice
because the paragraph (b) catalog of
standards is almost identical to the
earlier checklist used by the NRC. Cf.
NRC, Guide and Checklist for the
Development and Evaluation of State and
Local Government Radiological Emergency
Response Plans in Support of Fixed
Nuclear Facilities, NUREG-75/111 (1974).
In CLI-90-2, the Commission agreed
that emergency planning under section
50.47 is a “first-tier" safety
requirement designed to implement the
“adequate protection” standard of
section 182(a) of the AEA. 31 N.R.C. at
210-13. But the Commission did not
«78
believe this fact was material to
whether evidence like the Sholly/Beyea
testimony is properly considered in the
review of an emergency plan. Id. at
210. According to the Commission, even
though offsite planning is an essential
element of adequate public protection,
it is not necessarily of equal safety
significance with other protective
requirements:
[A]dequate emergency planning is
"essential," just as adequate
lifeboats are essential for a liner
Carrying passengers at sea. But
it's only common sense to
acknowledge that emergency plans,
like lifeboats, are a backstop, a
second or third line of defense that
comes into play only in the
extremely rare circumstance that
engineered design features and human
Capacity to take corrective action
have both failed to avert a serious
mishap.
Id. at 213.
For initial siting approval, the NRC
requires the applicant to establish
«tt.
_
around the proposed plant an “exclusion
area" and "low population zone" ("LPZ"),
the sizes of which must be determined on
the basis of specific maximum safe
radiation exposure levels for the public
assuming a fission product release from
the reactor core. See 10 C.F.R.
§ 100.11(a)(1)(2). The siting
regulations also require the
determination of a “population center
distance," measuring the distance to the
nearest area of dense population, which
must be at least one and one-third times
the radius of the LPZ. See id.
§ 100.11(a)(3). Thus, the shorter the
population distance, the greater the
design-engineered safeguards required in
order to have an LPZ with an outer
boundary of no more than three-fourths
the distance to the nearest population
center. In emergency
a
planning, by contrast, the goal of
mitigating dose consequences in the
larger EPZs is to be attained through
the application of generalized planning
standards without consideration of
actual levels of dose savings. See
Shoreham, 24 N.R.C. at 30.
Our limited task on this point is to
determine whether, given its recognition
that emergency planning is "first-tier,"
the NRC's generalized approach to dose
mitigation in offsite planning is a
reasonable exercise of the agency's
discretion under section 182(a). We
believe it is. Section 182(a) does not
expressly require that “adequate
protection” be judged by a single
standard for different categories of
safety features. In fact, we have
repeatedly emphasized the broad
x, :
ae
discretion available to the agency in
devising appropriate standards and have
held that “adequate protection" permits
the acceptance of some level of risk.
See Union of Concerned Scientists v.
NRC, 824 F.2d 108, 117-18 (D.C.Cir.
1987). It is for the NRC to determine
whether a level of, or approach to, risk
reduction is acceptable for offsite
planning that may not be adequate for
plant siting and design engineering.
Contrary to petitioner's contention,
the Commission's July 23, 1980,
rulemaking proceedings do not clearly
establish that section 50.47 was
intended to achieve a measurable level
of effective protection in specific
cases. In choosing the word “adequate”
over “appropriate” for paragraph (a),
certain members of the Commission voiced
Pew
the opinion that “adequacy” would
connote reasonabe assurance of effective
dose reductions, whereas “appropriate"
might be satisfied by a less demanding
best-efforts standard that could leave
the public in danger. See Transcript of
NRC Rulemaking Session, July 23, 1980,
at 22-28, 34-43, reprinted in JA at
25-31, 37-46. Petitioners argue that
these statements contemplate a
case-by-case effectiveness assessment.
We are not convinced. At most, the
1980 rulemaking proceedings establish
that the overall goal of emergency
planning is reasonable and feasible dose
reductions under the circumstances, a
proposition reiterated in the
Commission's ruling, see CLI-90-2, 31
N.R.C. at 216-17. In the same hearing
cited by the petitioners, one
commissioner stated:
[T]he whole thrust of the rule as I
perceive it is what we do things
with plant design and operation to
try to keep things from happening.
Then you can say if something does
happen it seems sensible .. . to
have pre-existing plans and
notification means so that we can
take whatever measures are practicle
; to reduce the radiological
hazard.
JA at 38. Another commissioner noted
that a plan need not
be found inadequate just because you
know that there are going to be some
periods of time when you can't do
that which you would really like to
be able to do . . . because of the
conditions of the accident or the
conditions of the weather.
Id. at 41-42. While the adequacy of a
plan is necessarily determined on a
case-by-case basis, the rulemaking
record does not contradict the
Commission's decision that the
minimization of harm to the public in
each case may be inferred from
Satisfaction of the sixteen planning
att<
standards, regardless of whether the
plan will actually protect the entire
EPZ under all conditions if one of the
particular accidents assessed in the
underlying guidelines should occur.
Nor do we accept the claim that
under the Commission's interpretation,
section 50.47 amounts to little more
than a pre-TMI reliance on a pro forma
"checklist." Before 1980, the Commission
did not require an NRC-approved offsite
emergency plan as a condition of
licensing. The checklist provided state
and local governments with criteria for
the development of plans for responding
to radiological emergencies and
facilitated their coordination with
those of the licensee. See NRC,
Emergency Planning for Nuclear Power
Plants, Regulatory Guide 1.101 (rev.
“| =
|
Mar. 1977). The regulatory scheme for
emergency planning deveoped by the NR‘
in response to TMI and the 1980
Authorization Act is markedly more
demanding than the prior practice, even
though the parargraph (b) planning
standards are largely drawn from the
earlier criteria. See generally 45
Fed.Reg. 55-401, 55-402-08 (1980).
After 1980, satisfaction of these
standards became for the first time a
condition of licensing that required the
finding of adequacy by FEMA and the
NRC. Id. at 55,403. The new scheme
provided that where significant
deficiencies in a plan would preclude
the finding of adequacy, the plant could
be shut down if the deficiencies were
not corrected within four months. Id.
The geographical area for offsite
planning
~~ =
was substantially expanded from the LPZ
to two laruver zones, the ten-mile radius
plume exposure pathway EPZ and the
fifty-mile radius ingestion pathway
EPZ. See id. at 55,406; 44 Fed. Reg.
61,123 (1979); see also Seacoast
Anti-Pollution League v. NRC, 690 F.2d
i025, 1028-29 & nn.10 & 12 (D.C.Cir.
1982) Also, the new scheme required
detailed implementing procedures and
more stringent public notification
Capabilities. See 45 Fed. Reg. at
55,403, 55,407. Finally, emergency
plans must comply with the detailed
requirements of Appendix E. These
enhanced safety requirements plainly
represent something more than a
checklist review.
Furthermore, we do not take it from
the Commission's ruling in CLI-90-2 that
~ | -
paragraph (a) has no meaning independent
of paragraph (b). As we understand the
NRC's application of the regulation,
paregraph (a) requires the agency to
determine that compliance with the
sixteen planning standards is more than
pro forma. The NRC must assure itself,
based on FEMA's review, that the plan
addresses each of the individual
requirements in a mannner that is
adequate and implementable. There is
ample indication in the administrative
record that the Licensing Board employed
this approach in its approval of the NH
Plan for Seabrook.
For example, the planning standard
in section 50.47(b)(10) is satisfied if
the response plan demonstrates that "[a]
range of protective actions [has] been
developed .. . for emergency workers
80.
Ba
and the public.” 10 C.F.R.
§ 50.47(b)(10). Petitioners argued
before the Licensing Board
that the NH
Plan did not satisfy (b)(10) because it
did not contain adequate provisions for
sheltering the beach population. See
CLI-90-3, 31 N.R.C. at 244.
Commission
guidance makes clear, however, that
(b)(10) does not require sheltering as
an option but does require
of the expected advantages
under loca] circumstances.
NUREG-0654, Criterion 11l.J.
Pursuant to this guidance,
Board set out to determine
State of New Hampshire has
and adequate consideration
as a protective action" in
an evaluation
of sheltering
Id. (citing
10m).
the Licensing
“whether the
given careful
to sheltering
the NH Plan.
LBP-88-32, 28 N.R.C. at 771; see
CLI-90-3, 31 N.R.C. at 244.
afi.
The Board found that the State had
Satisfied this Standard. In response to
comments f rom FEMA, the State had
Provided detailed explanations of its
approach to the use of Sheltering for
the beach population. 28 woe. C. ot
758. Under almost al] Circumstances,
earlysbeact ciosure Or evacuation would
be preferred action for the beach areas
because of the lack Of beachside
Structures that would offer substantia]
Protection. Id. at 758, 766. The plan
included a description of the very
low-probability conditions under which
emergency planners would Choose genera]
Sheltering for the beach population.
Id. at 758-59, 775.
Sheltering would be more readily
utilized for the estimated two percent
cf beachgoers without their own
a>.
transportation, and the plan identified
specific shelters for these -persons and
provided for sufficient bus
transportation along the beach routes
Id. at 759, 76l. In addition, the Board
found that credible surveys established
that sheltering providing a dose
reduction of at least ten percent
existed for the entire peak or near peak
transient summer beach crowd in the very
limited circumstances in which
sheltering would be preferred option.
a, OC F80~ta2, FFD. FEMA agreed with
the technical bases for the State's
approach to sheltering and concluded
that the NH Plan, with its primary
ny
\v
‘
Lad
‘2
a 2
\
reliance on evacuation, satisfi
requirement for a range of protective
measures. a.) Se 767.
Cc
Pi
-8
Based on these and other findings,
the Licensing Board ruled that adequate
consideration had been given in the NH
plan to the protective action of
Sheltering Seabrook's beach population.
Id. at 776. On review, the Appeal
Board's conclusions on the limited
nature of the Sheltering option but went
even further on the question of
implementability, requiring that the NH
Plan include more detailed implementing
instructions for those very low
Probability situations when general
Sheltering of the transient beach
population would be the preferred
Option. See ALAB-924, 30 N.R.C. at
362-73.
Far from applying an uncritical
Checklist methodology, the Licensing and
Appeal Boards exhibited a reasoned
-~84-
evaluation of the adequacy and
implementability of the plan's
compliance with the paragraph
standards. That is the approach
interpret the Commission to
under section
soe
(discussing reasonableness of
Board's treatment of shelt ing
option). Indeed, in ruling on ¢t
Of t
=
n
ry
immediate effectiveness
power authorization, the Com
agreed with the Appeal Board
should include further
—
J
a
<
_—
plan
detail if general beach she]
To
a)
-
.
‘
an
+>
Ww
¢
ae
be an option. Id.
agreed with the Lic
1
bad
<
DS)
that the lack of such detail
¢
significant,
with
concurrence
requl
ng
(hb)
Wwe
jcensing
}e
mw
need for further implementing measures
reinforces our conclusion that the NRC
requires fulfillment of the individual
paragraph (b) standards in an adequate
and implementable manner.
{14] Having determined that the
Commission's interpretation of its
emergency planning regulation is
consistent with the language of the
regulation and is not otherwise contrary
to law, we have little difficulty
concluding that the Commission's
exclusion of the Sholly/Beyea testimony
was not improper.
Given the fact that the Licensing
Board's task under section 50.47 is
limited to a review of the plan's
conformity with the paragraph (b)
standards and that this review does not
entail consideration of the dose
-86-
consequences that might result from
various hypothetical accidents, the
Commission had a reasonable basis for
concluding that the proffered evidence
was not relevant to the proceedings
because it would not make the finding of
an adequate and implementable plan
within the meaning of the regulation
more or less likely. Cf.Fed.Re.Evid.
401. To allow litigation of specific
dose consequences would be inconsistent
with a methodology that was derived from
generic guidelines and was designed to
eliminate the need for an examination of
hypothetical dose savings. See
CLI-90-2, 31 N.R.C. at 215-17. This
determination is within the NRC's “great
discretion to decide what matters are
relevant to its licensing decision.”
Union of Concerned Scientists v. NRC,
|
735 F.2d 1437, 1446 (D.C. Cir. 1984)
("UCS I"), cert denied, 469 U.S. 1132,
105 S.Ct. 815, 83 L.Ed.2d 808 (1985).
At bottom, petitioners' contention
is that the Sholly/Beyea testimony is
probative of their belief that the
effective emergency planning at Seabrook
is inherently impossible because the
plant is located so near the crowded
ocean beaches, a fact that was described
by SAPL counsel at oral argument as an
“Operating license blocker.” They point
to post-TMI rules that require
applicants for nuclear facility
construction permits to file preliminary
emergency plans, see 10 C.F.R.
§50.34(a)(10), Appendix E.II
("Preliminary Safety Analysis Report"),
and they suggest that this requirement
means that after 1980 the feasibility of
-~88-
emergency planning was meant to
influence site selection. The
implication apparently is that inherent
planning difficulties created by the
siting of a facility may block section
50.47 approval where the plant received
its construction permit, as did
Seabrook, prior to TMI.
The problem is that, as discussed
above, neither the AEA nor section 50,47
as interpreted by the Commission leads
to this implication. The Commission has
given no indication that preliminary
emergency plans under section
20.34(a)(10) will be used as “site
blockers" any more than final emergency
plans under section 50.47.
Finally, we note that although the
Commission held the Sholly/Beyea
testimony inadmissibie for purposes of
-~89-
the section 50.47 proceeding, the
Commission did suggest a possible use
for such evidence. See CLI-90-2, 31
N.R.C. at 217. It noted that when the
Licensing Board refused to admit the
evidence, petitioners could have filed a
petition for a waiver of or exception to
the normal application of section 50.47,
requesting more stringent planning
requirements for Seabrook on the ground
that “special circumstances with respect
to the subject matter of the particular
proceeding are such that application of
the rule or regulation . . . would not
serve the purposes for which the rule or
regulation was adopted." 10 C.F.R.
§2.758(b). With their application for a
waiver, petitioners could then have
submitted the Sholly/Beyea testimony to
the Licensing Board in the form of
-90-
supporting affidavits “set[ting] forth
with particularity the special]
circumstances alleged to justify the
waiver or exception.” Id. Petitioners
failed to avail themselves of this
opportunity.
a Immediate Effectiveness Review
Petitioners argue that the Appeal]
Board's ruling in ALAB-924 mandated that
the Licensing Board hold further
hearings on beach sheltering and on the
otner remanded issues prior to
authorizing a full power license for
Seabrook, and that, therefore, the
Commission acted unlawfully in refusing
to vacate authorization of the license
and in allowing the Licensing Board's
decisions to become immediately
effective. They also contend that the
Commission's action in CLI-90-3 violated
their statutory right to‘a hearing under
section 189(a).
{15] The NRC's rules of practice do
not specifically provide fer the
“mandatory relief" petitioners were
seeking in their motion to vacate. See
CLI-90-3, 31 N.R.C. at 229. As a
practical matter, no order was necessary
because an initial decision authorizing
a full power license is automatically
stayed pending the immediate
effectiveness review. See 10 C.F.R.
§2.764(£)(3)(iii). Nevertheless, the
Commission chose to entertain
petitioners’ motion, and, borrowing from
the law of judicial mandamus, decided
that such extraordinary relief would
only be appropriate if the Licensing
Board had breached “a clear,
nondiscretionary duty to withold
win
authorization." CLI-90-3, 31 N.R.C. at
229-30 (citing Ganem v. Heckler, 746
F.2d 844, 852 (D.C.cir. 1984)). The
decision to adopt this approach was
peculiarly within the Commission's
discretion.
[16] We cannot say that the
Commission acted arbitrarily or
Capriciously in concluding that the
Licensing Board had not violated such a
duty. As the Commission observed, no
NRC rules preclude the authorization of
a license while remand proceedings are
pending, and there is precedent for such
authorizations. CLI-90-3, 31 N.R.C at
230; see, e.g., Long Island Lighting Co.
(Shoreham Nuclear Power Station, Unit
1), LBP-84-53, 20 N.R.C 1531, 1542-48
(1984). Indeed, 10 C.F.R. §50.47(c) (1)
expressly contemplates that deficiencies
wit.
Ee
rn oan emergency plan that are “not
significant for the plant in question”
ay be resolved by the Licensing Boerd
atter license issuance. 31 N.R.C. at
230.
The Appeal Board did not state that
the deficiencies it identified in the
LBP-88-32 partial initial decision
precluded authorization. It expressly
affirmed the Licensing Board's decision
in all respects other than the four
specific items and said only that these
items required “appropriate corrective
action.” ALAB-924, 30 N.R.C. at 373.
ALAB-924 did make it clear that so long
the NH Plan was to include sheltering as
a possible protective option for the
general transient beach population,
implementing details would have to be
included in it, id. at 368, 372 n. 194;
-94-
but the Appeal KHoatd's directives Jid
not rule out a finding by the Licensing
Board that the planning deficiencies
were not significant under section
50.47(c). %In fact, the Appeal Board
deferred any action on petitioners’
motion to vacate in order to give the
Licensing Board an opportunity to
provide “some explanation of the
relevance of 10 C.F.R. §50.47(c)(1)-"
JA at 1049. And, as the Licensing Board
pointed out in its supplemental opinion,
LBP-89-33, 30 N.R.C. at 657 & n.2, only
one week prior to the issuance of
ALAB-924, the Appeal Board had denied 32
motion by petitioners for an order
directing the Licensing Board to
withhold its impending decision in
LBP-89-32, even though the Commission
had made it known that LBP-89-32 “would
-95-
—— << ttt”
have the potential to authorize issuance
of the full-power license,” CLI-89-19,
30 N.R.C. 171, 173 (1989).
[17] We do not agree that the
Commission's application of section
50.47(c) is inconsistent with
petitioners’ right to 4a hearing under
section 189 of the AEA. Section 189(a)
provides that in any licensing
proceeding, the Commission shall grant 4
hearing upon the request of any person
whose interest may be affected.” 42
u.s.C. §2239(a)(1)- we have held that
section 189(a) guarantees an opportunity
for a hearing on issues that the NRC
considers material coguigensingssy See
ucS I, 735 F. 2d at 1443, 1447-48.
Section 50.47(c) (1) indicates that the
NRC does not consider all issues
relating to deficiencies in 4a particular
~96-
response plan to be material to the
basic findings required for license
authorization under sections 50.47(a) (1)
and 50-57(a)(3). Thus, consistent with
the AEA, the Licensing Board could
choose to address the remanded issues in
post-licensing hearings upon finding
that the issues were not significant for
emergency planning at Seabrook. See
CLI-90-3, 31 N.R.C. at 230-31. In
addition, it is established NRC practice
that, where appropriate, that Licensing
Board may refer minor safety matters not
pertinent to its basic findings to the
NRC staff for post-hearing resolution,
and may make predictive findings
regarding emergency planning that are
subject to post-hearing verification.
Id. at 231 Nn. ee
my
Turning to its immediate
effectiveness review, the Commission
examined the reasonableness of the
Licensing Board's supplemental opinion
explaining why the four remanded issues
were not significant for the adequacy of
emergency planning. On the issue of
letters of agreement with school
personnel, the Commission believed that
the Licensing Board's further
explanation of its original finding
might well satisfy the Appeal Board's
concerns; at any rate, there was support
for the finding that sufficient school
personnel would accompany children 1” an
emergency and no indication thet
evacuation would be delayed even if the
personnel did not participate. Id. at
234-35. The Commission found reasonable
the Licensing Board's opinion that the
_
second remanded issue - the accuracy of
the special-needs survey - was 4
question more of fine-tuning an
acceptable methodology than of
developing a different methodology, and
that any uncertainty about the size of
the special-needs population was
probably not large enough to require
additional transportation resources. Id.
at 239-40. The accuracy of the
evacuation time estimates for advanced
life support patients remained
unresolved, in the Commission's opinion,
but the error was not large enough to
cause authorities to recommend
sheltering over evacuation BND COMA se oete: puna
easily be corrected, given that such
patients were found at only two
locations in the EPZ. Id. at 243.
-99-
Finally, on the lack of implementing
details for beach sheltering, the
Commission believed that correcting this
deficiency would not be difficult
because a comprehensive survey of
available beachside shelters had been
prepared, and the Appeal Board's mandate
Simply required that the NH Plan
designate which shelters on the survey
list would be suitable and available for
use. Jd. at 248 & n.45. Moreover, the
Commission concurred with the Licensing
Board that the sheltering issue was not
Significant. Evacuation would be the
primary protective action for the beach
and the record showed that the
protection afforded by the structures at
the beach was “trivial,” as further
evidenced by the fact that the Utilities
Flan, which the Licensing Board had
-100-
found adequate, did not include
sheltering as an option for the
Massachusetts beaches. Id. at 248. In
this regard, we note that in later
proceedings, New Hampshire revised its
plan to omit any provision for
sheltering the general beach population
other than a “shelter in place” option,
and the Licensing Board therefore
concluded that this issue was resolved.
LBP-90-20, 31 N.R.C. 581, 585 (1990).
It 185 evident that the Commission
eS
did not abuse 1* discretion in
concluding that the Licensing Board's
findings on these matters were
reasonable. See Oystershell
B00 F.2d at 1206. Hence, we also deny
the petitions for review as to this full
power issue.
-10i-
LD. Low Power Licensing Issues (No.
89-1306)
[18] We need not devote much
analysis to petitioners’ arguments
concerning the Appeal Board's
interpretation of the cooling system
contention in the low power
proceedings. See background discussion
at pages 13-14 above. On this issue,
petitioners direct most of their effort
toward relitigating the question of
whether microbiologically induced
corrosion is within the four corners of
NECNP's 1982 contention. This court,
however, is limited to deciding whether
the Appeal Board's ruling in ALAB-899
was arbitrary or Capricious, or
Otherwise contrary to law. See 5 U.S.C
§706(2)(A). Petitioners have not shown
that it was.
-102-
They argue only that the Appeal
Board acted arbitrarily by ignoring
certain terms in the contention that
could conceivably be read to encompass
the build-up of microscopic aquatic
organisms, and that the Board had no
reasonable grounds for disregarding the
opinion of NECNP's expert concerning the
technical interpretation of these
terms. We think the Appeal Board's
construction was reasonable because it
took into account the entire context of
the contention, whose heading and stated
basis focus solely on the blockage of
cooling systems due to the accumulation
of marine life and debris... SES gy
ALAB-899, 28 N.R.C. at 96-97. One
important purpose of the NRC's pleading
requirements in 10 C.F.R. §2.714(b) (2)
r
is to put all parties reasonably on
w
-103-
notice about what issues may be raised.
28 N.R.C. at 97. Therefore, it was
sensible for the Board to approach the
matter as a straightforward question of
linguistic construction and not as a
matter of technical interpretation
requiring a battle of experts. We deny
the petition as to this issue.
{19]) The second low power issue in
No. 89-1306, however, does raise
questions that justify granting this
petition. Petitioners argue that the
NRC violated their statutory right to a
hearing by rejecting the contention
concerning the onsite weaknesses |
identified in the 1988. Saadae
participation exercise. See background
discussion at pages 15-16. Because we
are unable to determine whether the
Appeal Board properly considered the
-104-
LE COPY
potential materiality of the allegations
involved, we must remand this issue for
further explanation,
The Appeal Board's ruling in
ALAB-918 is the final agency action on
the exercise contention and is the only
opinion hefore us. Petitioners
challenge the Appeal Board's
application, in ALAB-918, of the
late-filed contention criteria of 10
C.F.R. §2.714(a)(1) on the ground that
use of these criteria cannot be squared
with our decisions in UCS J] and San Luis
Obispo Mothers for Peace v. NRC, 751
{
F.2d 1287 (D.C. Cir. 1984) ("Mothers for
Peace I").,| vacated in party@60 F.2d
1320 (D.C.@Gir.1985) (en banc), and
aff'd, 789 .20 26 (D.C.Cir.) (en banc),
cert denied) 479 U.S. 923, 107 S.Ct.
330, 93 L.Edk2d 302 (1986).
-105-
NN _C ==" il
Under the NRC's rules, intervenors
ir liceagsing proceedings must file their
proposed contentions at least fifteen
days prior to the Licensing Board's
prehearing conference. 10 C.F.R.
§2.714(b)(1)..The Board may grant
additional time for the filing of
contentions based upon a balancing of
the factors set forth in section
2.714(a)(1) governing nontimely
petitions for intervention. Jd. Those
factors are:
(1) Good cause, if any, for failure
to file on time. |
(11) The availability of other means
whereby the petitioner's interest will
be protected.
(i111) The extent to which the
petitioner's participation may
-106-
reasonable be expected to assist in
developing a sound record.
(iv) The extent to which the
petitioner's interest will be
represented by existing parties.
(v) The extent to which the
petitioner's participation will broaden
the issues or delay the proceeding.
Id. §2.714(a)(1).
Because of the requirement, under
section 2.714(b)(1l), that contentions be
filed prior to the prehearing
conference, it would appear that almost
any contention based on the results of a
plant's full participation exercise
would be subject to a balancing of these
factors, under NRC rules, the exercise
must take place less than two years
prior to full power licensing, id. Part
50, Appendix E.IV.F.1, a period that
qeunerally falls well after the
prehearing conference, The full
participation exercise for Seabrook, for
example, occurred in June 1988, more
then six years after the prehearing
conterence on the low power licensing
issues.
{20, 21] Under YCS ], the NRC may
not eliminate from the licensing
proceedings consideration of evidence
that is relevant to material licensing
issues, such as issues raised by
emergency preparedness exercises. 735
F.2d at 1443-48; see Union of Concerned
Scientists v, NRC, 920 F.2d 50, 55
(D.C.Cir.1990) (ree I to require
a hearing on all natertet “issues”, as
distinct from all “evidence” or
“information” that comes to light afte:
the time of the initial application).
-108-
At the same time, we fully recognize
that the NRC has “wide discretion to
structure its licensing hearings in the
interests of speed and efficiency.” 735
F.2d at 1448. This discretion may
include, for example, rules on the
admissibility of evidence, enhanced
pleading requirements in support of
contentions, and procedures for summary
disposition of claims not meeting the
agency's criteria. See jd. In short,
we allow for a balancing between the
public's right to a hearing under
section 189 and the NRC’s discretion to
St.ucture efficient licensing
proceedings. See id. at 1446-49.
We are not willing to say Nhe
sensitive balance outlined in UCS I] is
upset whenever the NRC applies the
late-filed contention factors to
-109-
submissions based on deficiencies
revealed in exercises occurring after
the prehearing cut off. The unfettered
ability to file a late contention may
Significantly undermine the efficiency
of a proceeding even if the contention
is based on newly discovered
information. The NRC should retain
discretion to impose enhanced procedural
requirements on such filings so long as
the use of that discretion is consistent
with section 189.
On their face, the five factors
listed in section 2.714(a)(1) as
justifying intervention are not well
Suited to the question of whether a
late-filed contention a neers be
considered where based on deficiencies
found in a subsequent exercise, and we
think it odd that the NRC would choose
-110-
to apply them in this context. An
exercises contention *‘ill in practice
almost always be fiied out of time, so
the question of “good cause” seems less
central. Two of the other factors also
do not make much sense here. (Factor
(iv) does not seem relevant because
there will almost never be other parties
already litigating the issues raised by
the new contention. And factor (v) 1s
potentially inconsistent with YCS I's
holding that emergency preparedness
exercises are material] to licensing: it
should not be a strike against admitting
the cortention that it will “broaden the
issues” to include mates ps guest ions
Pers
about the adequacy of preparedness.
Nevertheless, in practice the NRC's
boards have attempted to compensate
somewhat for the problematic nature of
-lll-
these factors, and we will look to the
manner in which they have been applied
in the particular case before us.
[22] We think the Appeal Board's
application of factor (1) to
petitioners’ exercise contention is
reasonable and consistent with section
189. In considering “good cause” fol a
late filing, the adjudicatory boards
insist that “a late-filed contention
must be tendered promptly upon the
discovery of the information upon which
it is based.” ALAB-918, 29 N.R.C. at
482 (citing Duke Power Co, (Catawba
Nuclear Station, Units 1 and 2),
CLI-83-19, 17 N.R.C. 1041, 1048
(1983)). This prompt-filing aii) Hombrit
is in line with the agency’s broad
discretion to structure efficient
proceedings. Moreover, we have been
-ll2-
presented with no argument for rejecting
the Board's view that factor (1) 1s the
“most crucial” in the analysis. See 29
wick. - Se See:
Applied in this fashion, the first
factor is not contrary to Mothers for
Peace I which held that under section
189(a), the NRC may not unjustifiably
require that a material contention
satisfy the heightened evidentiary
standards for reopening a closed
record. See 75] F.2d at 1316. Mothers
for Peace I does not constrain the NRC’Ss
discretion to impose reasonét'’e limits
on the untimely presentation of claims
including claims based on late-breaking
developments that are not promptly = «
filed. We do not express an opinion
here about whether the NRC may
€ r)
justifiably apply these five factors
-113-
contentions that are tendered promptly
upon discovery of newly revealed
information. The Appeal Board made it
clear that that would be the agency's
practice in such cases. See 29 N.R.C.
at 480.
In the present case, the Appeal
Board did not act arbitrarily in
upholding the finding that petitioners
lacked good cause for their faiiure to
tender the exercise contention
promptly. The Appeal Board agreed with
the Licensing Board that petitioners had
no convincing justification for waiting
until September 16, 1988, to present
their contention when all of the
essential information on,which it was
based was available in the July 6
inspection report, which was received by
petitioners no later than July 15. ld,
~ §802«
at 482-83. Although this period of
approximately two months does not strike
uS aS an exceptional delay, we are not
willing to interpose our judgment. The
low power proceedings had advanced to a
stage when promptness might have been
especially important. Indeed, the
Licensing Board had renewed its
authorization of a low power license
when petitioners moved to admit their
contention. See jd. at 475-76.
The problem with the Appeal Board's
reasoning relates to its application of
the remaining four factors. The NRC
reguires a “compelling” showing on these
factors to overcome a lack of good cause
under (1). Jd. at 484. In this
counterbalancing, the greatest emphasis
seems to be on factor (i1ii)-the ability
of the petitioning party to assist in
developing a sound record. See id. at
483-85. The Appeal Board stated that
petitioners “had an obligation in
addressing the third criterion to set
out with as much particularity as
possible the precise issues they plan to
cover, the identity of their prospective
witnesses, and a summary of their
proposed testimony.” Jd. at 483. Here
the Appeal Board upheld the finding that
this significant factor weighed against
admitting the contention because
petitioners, who were “experience
litigants,” had failed in their motion
papers “to furnish the required
information in the prescribed form.”
Id. at 483-84. . Cee
{23} Our concern is that in
focusing on whether petitioners’ papers
Satisfied these formal “particularity”
- 116 -
requirements, the Appeal Board may have
lost sight of the potential materiality
of the issues raised by the contention
and thus may have strayed from the line
laid down in YUCS J]. We think section
189 required the Appeal Board to provide
an affirmative explanation as to whether
petitioners’ allegations raised any
material issue and, if they did, how
that materiality was to be weighed
against petitioners delay in promptly
filing the contentiun. We note, for
example, that petitioners offered an
expert atriddvit alleging that the July
6 inspection report showed fundamental
deficiencies in Seabrook'‘s onsite
emergency preparedness. See Affidavit
of Robert D. Pollard, Sept. 16, 1988.
Petitioners specifically contended that
the deficiencies in the onsite plan
ILABLE COPY
“BF -
precluded a finding of compliance with
paragraphs (b)(2), (b)(14), and (b)(15)
of the section 50.47 planning
guidelines. JA, No. 89-1306, at 253-54.
The Appeal Board failed to consider |
these allegation in analyzing whether,
on balance, it was proper to reject
petitioner's late-filed claims. The
Licensing Board did engage in an
extended discussion of the safety
Significance of the exercise issues in
the context of its ruling on
petitioners‘ motion to reopen the
record, see LBP-89-4, 29 N.R.C. 62,
74-86 (1989), but the Appeal Board
declined to address that portion of the
Licensing Board's decision, ALAB-918, 29
N.R.C. at 485. Thus, we cannot impute
this reasoning to the higher board.
The Appeal Board provided a second,
independent basis for its opinion,
namely, that no hearing was required on
petitioner's exercise contention because
the contention did not involved a
“fundamental flaw" in the onsite plan.
Id. at 485. Under the NRC precedent, a
fundamental flaw is a deficiency that
precludes the finding of reasonable
assurance under 50.47(a)(1), and is
confined to deficiencies that reflect a
failure of an essential element of the
plan that can be remedied only through a
Significant revision of the plan. Ssee
Long Island Lighting Co, (Shoreham
Nuclear Power Station, Unit 1),
ALAB-903, 28 N.R.C. 4994504 305).01988 )
("LILCO"). We acknowledge this concept
in UCS I, and stated that our gloss on
section 189 does not restrict the NRC's
authority to adopt this substantive
hicensing standard, 735 F.2d at 1448.
We nevertheless recognized that even the
best of plans may be so poorly
implemented that it would be fvolhardy
to license the plant until fundamental
deficiencies detected in an exercise,
such as serious shortcomings in staff
training, were substantially corrected.
Ct, 10 C.F.R. § 50.47(b)(15) (requiring
plan to provide for adequate training of
emergency personnel). Thus we noted
that the agency would still be subject
to challenge for applying the standard
arbitrarily or capriciously. See 735
F.2d at 1448 n. 20.
Here, we are unable coMetermine
from the Appeal Board's terse
explanation whether it acted properly in
applying the fundamental flaw concept.
- 120 -
The Board simply stated the conclusion
that the purported we knesses in the
training of Technical Support Center and
Fnergency Operations Facility staff
could be readily corrected through minor
modifications in operating procedures or
Supplemental training and would not
require any revision in the onsite
Plan. ALAB-918, 29 N.R.C. at 485-664.
Once again, this judgment does not meet
the allegations set out in petitioners’
contention and in the Pollard Affidavit
concerning adequate ccmpliance with
specific planning standards. Moreover,
in a second affidavit, filed in response
to the NRC's September. 28 fodlow-up
inspection report, petitioners presented
further evidence to support their claim
that the alleged deficiencies had not
been adequately addressed. See Second
- l2l -
Attidavit of Robert D. Pollard, Nov. 8&8,
1988.
We fail to see how the Appeal Board
could reasonably determine the
materiality of this contention under the
fundamental flaw rubric without
considering the supporting allegations.
The LILCO opinion relied on by the
Appeal Board draws a distinction between
fundamental flaws and “(mJinor or
isolated problems on the day of the
exercise” that can be "“readiiy
corrected.” ALAB-903, 28 N.R.C. at 505,
506, cited in ALAB-918, 29 N.R.C. at
485. There would appear to be a
substantial varianée*betweenmaucn™
nonfundamental deficiencies and the
serious shortcomings in staff competency
alleged in the Pollard Affidavit.
- 122 -
Netariinety, we must grant the
petition for review of this issue and
remand ALAB-918 to the Appeal Board for
further consideration of the materiality
of petitioners’ exercise contention.
As is apparent, we disagree with the
NRC and PSNH that this issue was mooted
by the September 1989 exercise of
Seabrook's onsite plan. Appendix E of
the emergency planning regulations calls
for a prelicense onsite drill if the
full participation exercise occurs more
than a year before full power
licensing. 10C.F.R. Part 50, Appendix
E.IV.F.1. We do not believe that such
an onsite exercise is intended to “ete
supersede the full participation drill,
and thus we reject the NRC's contention
that the onsite exercise becomes the
"legal underpinning” for approval of the
- 123 -
—-
full power license. Supplemental Brief
f' r Respondents at 6. The Licensing
Board essentially rejected the view now
adopted by staff counsel when it
described the purpose of the more
limited onsite drill: “to ensure that
emergency response personnel retain
sufficient knowledge and expertise to
actuate an emergency [plan] already
determined through a reasonably current
adequate and without fundamental
flaws." LBP-89-38, 30 N.R.C. 725,
744-45 (1989) (emphasis added).
[24,25] In granting the petition
for review of ALAB= 918 apg. do not vacate
; ES 25 ATS L
the authorization of Seabrook's
operating licenses. In appropriate
cases, we will remand without vacating
an agency's order where the reason for
, - 124 -
i
the remand is a lack of reasoned
decisionmaking. E.G., International
Uni UMW v._ Mi oatuty K taslt
Admin., 920 F.2d 960, 967 (D.C. Cir.
1990). “Relevant to the choice are the
seriousness of the order's deficiencies
(and thus the extent of doubt whether
the agency chose correctly) and the
disruptive consequences of an interim
Change that may itself be changed.” J[d.
On the ee before us, only the
allegations and affidavits offered by
petitioners provide a basis for concern
about the adequacy of onsite
preparedness. Although we are unwilling
to conclude that the September 1989
onsite exercise fully tested«eBlaspects
of emergency planning potentially
implicated by petitioners’ contention,
we see nothing in the results of that
- 125 -
exercise to indicate any- ongoing flaws
in staff competency. Most important, we
note that Seabrook was scheduled for a
second full participation exercise in
December 1990. A clean record in that
exercise will likely moot this issue.
Hence, we decide against imposing an
immensely disruptive interim status quo
that may itself be displaced by the
Appeal Board's subsequent reasoning or
by the more recent full participation
exercise.
We therefore leave it to the Appeal
Board to determine whether our opinion
suggests any reason for altering the
plant‘s licensing status. In
particular, we have received from
oe
petitioners no guidance as to how, if at
all, the Appeal Board‘s ruling in
ALAB-918 may bear on the Commission's
- 126 -
decision to allow the authorization of
full power operations. Because the full
power license necessarily depends upon
the resolution of all issues material to
low power licensing, including the
adequacy of the onsite emergency plan,
this question merits the agency's
consideration.
III. CONCLUSION
We deny the petitions for review of
Seabrook's full power license in Nos.
90-1132 and 90-1218. The Commission's
interpretation of its emergency planning
regulation does nut do violence to the
language of the rule and is..within the
agency's statutory discretion, and the
related decision to exclude the
Sholly/Beyea testimony was not arbitrary
- 127 -
Or Capricious or otherwise unlawtul.
Furthermore, the Commission did not
abuse its discretion in allowing the
imnediate effectiveness of the full
authorization. The decision
power
denying a waiver of the agency's
financial qualification exemption is not
a tinal order, and petitioners'
challenge to that ruling is not properly
before us.
The low power licensing petition in
No. 89-1306 is denied in part and
gQranted in part. The Appeal Board acted
reasonably in interpreting the scope of
petitioners’ cooling system contention,
and we deny review of ALAB-899. We are,
however, unable to conclude that the
Appeal Board properly considered
petitioners’ rights under section 189
when it rejected their onsite exercise
- 128 -
>
i
contention. For that reason, we grant
the petition for review of ALAB-918 and
remand this ruling for reasoned
decisionmaking. This conclusion,
however, does not give us reason to
Jisturb Seabrook's operating licenses.
oy vLdered.
Z29U31E
UNITED STATES OF AMERICA
NUCLEAR REGULATORY COMMISSION
COMMISSIONERS:
Kenneth M. Carr, Chairman
Thomas M. Roberts
Kenneth C. Rogers
James R. Curtiss
Forrest J. Remick
)
In the Matter of )
) Docket Nos.
PUBLIC SERVICE COMPANY ) 50-443-O0L
OF NEW HAMPSHIRE, ET AL.) 50-444-OL
)
) Offsite
(Seabrook Station, Units) Emergency
I, and 2) ) Planning
)
MEMORANDUM AND ORDER
CLI-90=- 02
I. Introduction
In ALAB~922 9.3.0.NRC
October 11, 1989, the Appeal Board
» issued on
*
certified a question to the Commission
for resolution, pursuant to 10 CFR /
2.785(d), under which the Appeal Board
may "certify to the Commission for its
- 430 =
determination major or novel questions
of policy, law or procedure." The
question certified was the following:
"Whether the MassAG‘’s
(Massachusetts Attorney
General’s) testimony, which
seeks to address the dose
reductions/dose consequences
that will arise under the
NHRERP [New Hampshire
Radiological Emergency
Response Plan), is admissible
as relevant to a determination
of whether, in accordance with
the Commission’s Shoreham
guidance, the NHRERP will
achieve reasonable and
feasible’ dose reduction under
the circumstances so as to
provide ’reasonable assurance
that adequate protective
measures can and will be
taken’ in accordance with 10
C.F.R. § 50.47(a)."
30 NRC at 259 «gps Bs
For the reasons which follow, we
. Pe had 5 et
have determined that the testimony
proffered by the Massachusetts Attorney
General was admissible neither for the
purpose mentioned by the Appeal Board
» 433.
nor for any other. To explain the basis
of our decision requires us to set forth
in some detail the context in which the
admissibility of the proffered testimony
was considered by the two Boards.
II. Proceedings before the Licensing
Board
The Massachusetts Attorney General,
in a contention first offered in 1983
and resubmitted in 1986, charged that
the New Hampshire plan did not, as
required by 10 CFR § 50.47(a), provide
"reasonable assurance that adequate
protective measures can and will be
taken" in an emergency, because on a
summer weekend, with the nearby iaaahes
densely populated by transients,
evacuation would fail to protect persons
on the beach under many plausible
meterological conditions, and inadequate
- dae ¢
provisions had been made for sheltering
these persons. The applicants objected
to this contention on the grounds,
first, that the NRC’s emergency planning
regulations were not intended to
guarantee absolute protection or a given
level of protection, and second, that to
litigate the contention would in effect
be to relitigate the decision to site
the plant at Seabrook. The staff
opposed the contention to the extent it
could be interpreted as seeking to
litigate the dose consequences of any
specific accident or as asserting that
emergency planning must achieve a
particular level of dose protection to
the public, but wouldhave allowed its
admission to the extent it constituted a
challenge to the adequacy of the
- i233
sheltering provided for the beach
population.
‘The Licensing Board rejected the
proposed contention on April 29, 1986.
The Commission’s rules, it said, did not
require a zero risk standard, but rather
the development of emergency plans with
the flexibility to ensure response to a
wide spectrum of accidents. The
Massachusetts Attorney General, said the
Licensing Board, was seeking to have
each of the responses within the range
of protective responses provide absolute
assurance, whereas the intent of the
rules was to assure that any one or a
combination of responses would provide
the requisite reliccnshie naaeeeee The
Licensing Board agreed with the staff
that particular postulated accidents
were inappropriate for litigation, and
- 134 =
that the regulations did not require
that any particular level of
radiological does reductions be achieved.
The Massachusetts Attorney General
sought review by the Appeal Board, but
the Appeal Board, in ALAB-838, 23 NRC
585 (1986), held the appeal to be
interlocutory, since Massachusetts could
continue to participate in the
proceeding as an interested state. As
an intéexested state, therefore, the
MassAG trNed again in September 1987,
offering tesNmony as to the technical
basis for the NRC’s emergency planning
rules; radiation doses to the public
which would result from anaccident at
Seabrook; the potential for an
atmospheric release; and the probable
health consequences of the foregoing.
ABLE COPY
The MassAG argued that this
testimony was germane, since it
illuminated the actual level of
protection afforded the public, a
necessary part of a “reasonable
assurance" finding. The regulations,
said the MassAG, called for a range of
protective measures, but here, the plan
did not provide for sheltering. The
MassAG urged that while the Board was
not required to make specific dose
savings findings, or to calculate the
number of people who would be injured in
an accident, it was nevertheless
required to accept evidence on those
issues in order to determine the
adequacy of the protective measures
provided by the emergency plan.
Applicants objected to the offer of
proof, arguing that it was an effort to
- i236 =
reintroduce the contention rejected
earlier, and that the evidence was
irrelevant, since it purported to show
dose savings and consequences in
absolute terms, whereas the regulation
only required a showing that the
emergency plan "is designed to achieve
reasonable and feasible dose savings
given the circumstances of the site in
question." The staff agreed with the
applicant.
In a bench ruling on November 17,
1987, the Licensing Board determined
that the proposed testimony was outside
the scope of the Commission’s emergency
planning requirements, as outlined in
three Commission pronouncements on
emergency planning. TR 5594. First, the
Licensing Board said, the 1983 San
Onofre decision (Southern California
- 137 -
Edison, San Onofre Nuclear Generating
Station, Units 2 and 3, CLI-83-10, 17
NRC 528, 533), had emphasized that with
regard to emergency planning,
The emphasis is on prudent risk
reduction measures. The regulation
does not require dedication of
resources to handle every possible
accident that can be imagined. The
concept of the regulation is that
there should be core planning, with
sufficient planning flexibility to
develop a reasonable ad hoc
response to those very serious
low-probability accidents which
could affect the general public.
Second, the Licensing Board looked
to the Commission’s 1986 decision in
Long Island Lighting (Shoreham Nuclear
Power Station, Unit 1), CLI-86-13, 24
NRC 22, where the Commission said:
The root question becomes whether
the LILCO plan can provide for
"adequate protective measures in
the event of a radiological
emergency." [Footnote omitted. )
This root question cannot be
answered without some discussion of
what is meant by "adequate
protective measures." Our emergency
= i238 -
planning regulations are an
important part of the regulatory
framework for p~ otecting the public
health and safety. But they differ
in character from most of our
siting and engineering design
requirements which are directed at
achieving or maintaining a minimum
level of public safety protection.
See, e.g., 10 C.F.R. § 100.11. Our
emergency planning requirements do
not require that an adequate plan
achieve a preset minimum radiation
dose saving or a minimum evacuation
time for the plume exposure pathway
emergency planning zone in the
event of a serious accident.
Rather, they attempt to achieve
reasonable and feasible dose
reduction under the circumstances.
Finally, the Licensing Board cited
the then newly issued final rule in the
1987 rulemaking on emergency planning,
where the Commission said:
The final rule makes clear that
every Emergency Plan has to be
evaluated for adequacy on its own
merits, without reference to the
specific dose reductions which
might be accomplished under the
plan, or to the capabilities of any
other plan. 52 Federal Register
42078, 42084 (November 3, 1987).
- i139 =
The Licensing Board concluded that
the proffered testimony, despite sincere
efforts to argue otherwise, involved
“specific assumptions of doses, dose
consequences, health effects, and the
entire array that the Commission stated
is not part of consideration." TR 5608.
B. Proceedings before the Appeal
Board
The issue of the exclusion of the
proffered testimony came before the
Appeal Board on its review of the
Licensing Board’s December 31, 1988
Partial Initial Decision on the New
Hamphsire emergency plan. In ALAB-922,
issued on October 11, 1989, the Appeal
Board provided a different analysis of
the issue from that of the Licensing
Board. It declared that the focal point
of the dispute was where the emergency
planning regulations, with their
- 449 =
requirement of "reasonable assurance,"
fit into the two-tiered regulatory
scheme of the Atomic Energy Act. The
Appeal Board explained that the
Commission’s safety regulations are
either standards necessary to provide
first-tier “adequate protection" (as
authorized by Section 182(a) of the
Atomic Energy Act) or are second-tier
“extra-adequate protection" (measures
over and above what is needed for
adequate protectior) as authorized by
Sections 161(b) and (i) of the Atomic
Energy Act. The distinction between the
two was recognized, said the Appeal
Board, in UCS v. NRC (UCS 1), 824 F.2d
108 (D.c. Cir. 1987).
The intervenors, said the Appeal
Board, claimed that 10 CFR § 50.47 was a
first-tier “adequate protection"
- 446i =
standard, and that the Commission could
not determine whether “adequate
protection" was provided without
evaluating the degree to which the
emergency plan still left the public at
risk. This argument, said the Appeal
Board, was “promptly dispelled" by an
examination of the 1980 rulemaking that
promulgated 10 CFR § 50.47. In that
rulemaking, the Commission cited as its
authority Sections 161(b),-(i), and (0)
of the Atomic Energy Act. In the Appeal
Board’s words, "it is hard to imagine a
more compelling indication that ...
emergency planning requirements are
intended to be second-tier, AEA section
161 safety provisions rather than a
first-tier, ‘adequate protection’
requirement under AEA Section 182." 30
NRC at 256-57. Thus the Appeal Board
- 362 *
had "no difficulty" rejecting the
intervenors’ argument that the proffered
testimony was admissible to show that
even with the New Hampshire emergency
plan in place, operation of the plant
presented such risks as to fail the
“adequate protection" test. 30 NRC at
257-58.
The Appeal Board found “more
compelling" the argument that the
evidence should be admitted to show (in
accordance with Shoreham’s guidance that
emergency plans should seek to achieve
"reasonable and feasible dose
reductions") whether the dose reductions
achievable by the New Hampshire plan
were "reasonable." Clearly, said the
Appeal Board, the reductions would be
"feasible," since the plan had been
prepared by state officials; but a “more
- 143 -
compelling case" was presented by the
argument that those dose reductions
would not be "reasonable." if, as
contenced by the Massachusetts Attorney
General, they would result in little
realistic dose reduction and lead to
doses with serious health consequences.
To this, the Appeal Board noted,
applicants and staff answered that all
information on dose consequences and
dose reductions was beside the point,
since the Commission had made clear in
Shoreham that no preset dose reductions
or evacuation times were called for, and
the 1987 rule had declared that plans
were to be evaluated for adequacy
"without reference to the specific dose
reductions which might be accomplished
under the plan." 30 NRC at 258, citing
52 Fed. Reg. 42,078, 42,084 (1987).
- 466 <
The Appeal Board thus found itself
pulled between what it considered to be
cwo contradictory lines of analysis:
Shoreham’s emphasis on "reasonable" dose
reductions and the "perhaps superseding"
guidance of the 1987 rule, in which the
determination of ‘specific dose
reductions" was ruled out. The latter
approach, the Appeal Board said,
suggested that "given the
‘extra-adequate protection’ status of
emergency planning requirements," review
of emergency plans should concentrate
not on a subjective judgment of whether
the protection afforded to the public is
"adequate," but rather on conformance
with the requirements of the regulation
and the pertinent NRC/FEMA criteria.
Accordingly, the Appeal Board certified
to the Commission the question of
=» 463 °
whether the MassAG’s testimony was
admissible as relevant to a
determination of whether the New
Hampshire plan would achieve “reasonable
and feasible dose reduction under the
circumstances" so as to provide
"reasonable assurance that adequate
protective measures can and will be
taken." 30 NRC at 259.
On October 20, 1989, the
Massachusetts Attorney General asked the
Appeal Board to reconsider its decision
that emergency planning regulations
represented a "second-tier" or
"“extra-adequate" level of protection
under Section 161 of the Atomic Energy
Act rather than "first-tier" protection
under AEA Section 182. The petition
urged that the transcript of the 1980
Commission meeting at which the language
- 146 =
of the emergency planning rule was
crafted was evidence that the Appeal
Board erred on this central point. The
Massachusetts Attorney General argued
that the citation to Section 161 in the
1980 rulemaking was without
Significance, and it noted that the
Commission’s fire protection rule by the
NRC’s own account a first-tier "adequate
protection" standard had been issued
under Section 161. The petition also
noted that the two-tier theory had not
been articulated until years after the
1980 rulemaking on emergency planning.
Massachusetts offered a different
explanation of the citation to Sections
161(b), (i), and (0): to assure that
criminal sanctions set forth in 42
U.S.C. Section 2273 would apply. A
- 147 -
similar petition was filed by the
Seacoast Anti-Pollution League.
On October 23, the Appeal Board
summarily denied the petitions for
reconsideration, on the grounds that the
issues raised in them were so linked to
those involved in the question certified
to the Commission for decision that they
should be resolved by the Commission
rather than the Appeal Board.
III. Filings of the Parties
In response to a briefing schedule
issued by the Commission on October 13
(modified by an extension of time
granted to the NRC staff), the parties
filed their briefs between October 27
and November 13, 1989. The positions of
the parties may be sunnarized as follows.
- 448 <-
1. Intervenors
Intervenors asscct that the Appeal
Board erred when it held, based on the
citation to Section 161 of the Atomic
Energy Act in the 1980 emergency
planning rulemaking, that emergency
planning was a second tier,
‘extra-adequate" safety measure. The
transcript of the 1980 Commission
meeting that preceded adoption of the
rule makes clear that the key phrase
“adequate protective measures" in the
regulation was specifically intended to
track the phrase “adequate protection"
in Section 182 of the AEA. The choice
of words was designed to assure that
“best efforts’ would not be enough, and
that energency planning measures would
also have to be effective in protecting
the public. In recognition that the
- 149 <=
discussion was crucial to a correct
understanding of the Commission’s
intent, the Commissioners directed that
the transcript be included in the
rulemaking record.
According to the intervenors, the.
Appeal Board, in relying on the citation
to Sections 161(b), (i), and (0) -- an
issue which the Appeal Board itself
raised, none of the parties having done
so -- ignored the 1980 Authorization Act
in which Congress directed the NRC to
develop emergency planning regulations.
Although the Commission’s final rule in
1980 included a statement that the rule
was consistent with the Authorization
Act, that Act did not appear in the list
of authorities. Thus the list is
incomplete on its face. Furthermore,
the Commission has named Section 161 as
- ioe +
the sole basis of such safety-based
rules as the fire protection rule, cited
by the Commission in an appellate brief
as an example of a first-tier "adequate
protection" backfit. In reality, the
citations to Sections 161(b), (i), and
(Oo) simply designate regulations to
which criminal penalties under 42 U.S.C.
2273 are intended to apply. Any doubt
is eliminated when it is recognized that
in the 1980 version of 10 CFR, the
General Design Criteria of 10 CFR Part
50, Appendix A, were not described as
based on Section 182.
Intervenors claim that the Appeal
Board’s quotation from the Commission’s
1986 Shoreham decision was misplaced.
Although some of the quoted language
might suggest that emergency planning
was not designed to achieve or maintain
- i394 °
a regulatory minimum of protection, the
1980 rulemaking was unambiguous on that
point, and it is controlling. Indeed,
in 1983 the Commission, in response to a
Congressional question, made clear that
it saw emergency planning as a matter of
adequate protection, not -- as in the
days before the TMI accident -- a
"Secondary but additional measure to be
exercised in the unlikely event that an
accident would happen."
Likewise, say the intervenors, the
Appeal Board should have given no weight
to the Commission’s statements in the
1987 rulemaking that suggested emergency
planning was of second-rank importance.
First, the context in which the 1980
Commission spoke of emergency planning
as needed to "bolster" other safety
measures was one which (as described
- ine *
above) contrasted the pre-TMI and
post-TMI approaches. Moreover, even the
Commission in 1987 conceded that it was
not possible to resolve the issue of the
intended significance of emergency
planning through "microscopic" analysis
of the 1980 language. As for the
120-day clock, that provision did not
reveal a differerice between emergency
planning and other safety regulations,
but rather a resemblance, in that other
types of regulations also do not require
automatic shutdown. Moreover, the 1980
regulation reflected a compror,,ise,
with new and existing plants handled
differently. For new plants such as
Seabrook, an adequate emergency plan was
essential to operation. In fact, the
reason tor the 120-day clock was not a
casual view of emergency planning, but
- 150 =
rather a recognition that the NRC did
not have the power to compel the
cooperation of state and local
governments.
In the intervenors’ view, the
phrase "adequate protective measures’ in
Section 50.47(a)(1) has a plain meaning
that must be acknowledged. The Appeal
Board never addressed the intervenors’
argument that whatever the Commission
thought about emergency planning in
1987, it still considered emergency
planning to be part of the first-tier
adequate protection framework. The
Commission would never have countenanced
the huge sums that utilities have spent
on emergency planning since 1980 if
those requirements were not viewed as
necessary for adequate protection. The
Appeal Board did not deal with the 1980
- 154 -
Authorization Act, in which Congress
made clear that emergency planning was
designed to prevent "public
endangerment," ie., first tier. In
statements to the Congress,
Commissioners made clear that they
shared Congress’ view that emergency
planning regulations were in place to
assure “adequate protection."
Once it is recognized, say the
intervenors, that emergency planning is
a first tier safety standard, then there
are three different approaches under
which the Massachusetts Attorney
General’s proffered testimony is
admissible: (1) to contribute to a
case-by-case evaluation of whether the
risk posed by operation of Seabrook is
acceptable; (2) for a determination of
whether a "range of protective
* i233 =
measures," as required by the planning
standards of Section 50.47(b), have been
provided; and (3) to judge whether the
plan achieves "reasonable and feasible
dose reductions under the
circumstances," to quote the
Commission’s 1986 Shoreham decision.
The phrase "under the circumstances"
should be understood to refer simply to
the case-by-case nature of the inquiry,
not to suggest that a "bést efforts"
showing is all that is needed. The
Commission’s November 1987 final
emergency planning rule rejected a "best
efforts" approach.
Finally, intervenors argue, there
is no "exclusionary rule" in NRC
proceedings that would bar testimony on
dose consequences. The evidence on dose
reductions and dose consequences that
- 435 ©
the Massachusetts Attorney General has
sought to introduce is plainly relevant
to the adequacy of the emergency plan.
The only way that such obviously
relevant evidence could be excluded is
the existence of some policy barring its
admission. Such an intent might account
for the statement in the Commission’s
November 1987 rule that “every emergency
plans is to be evaluated for adequacy on
its own merits, without reference to the
specific dose reductions which might be
accomplished under the plan." It would
be irrational, however, for the
Commission, without ever having
articulated a rational basis for doing
so, to say in one breath that it will
evaluate a plan’s adequacy and in the
next that it will not look at evidence
plainly relevant to the plan’s
- ior =
adequacy. The NRC has expertise in
evaluating dose consequences, which it
routinely estimates in a variety of
contexts.
For these reasons, intervenors
urge, the Commission should reverse the
Appeal Board’s "second tier" findino and
direct the Appeal Board to proceed with
its review of LBP-88-32 accordingly.
Alternatively, it should go further and
indicate that the proffered testimony
was relevant and material and should
have been admitted.
2. Applicants
The precise question posed by the
Appeal Board, say the applicants, was
whether the reference in Shoreham to the
objective of achieving "reasonable and
feasible dose reduction" meant that
evidence on dose savings and dose
- ine. =
consequences should be admitted. In the
context in which the Commission used
that phrase, ‘’reasonable" referred to
dose savings achievatle without
disproportionate cost. This position is
consistent with San Onofre, CLI-83-10,
17 NRC 528, which said that the
emergency planning rules emphasized
"prudent" risk reduction measures, not
extraordinary measures such as
construction of new hospitals. The 1987
amendments to the Commission’s emergency
planning rules lay to rest any
suggestion that the profferred testimony
could be admissible. The proposed rule
emphasized that the emergency planning
rules were flexible, not aimed at
achieving preestablished minimum dose
savings. The final rule made the same
point, declaring that findings as to
° i998 >
precise dose reductions “are never a
requirement in the evaluation of
emergency plans," and that emergency
plans were to be evaluated individually,
"without reference to the specific dose
reductions which might be accomplished
under the plan...... The foregoing
demonstrates that the evidence proffered
by the intervenors was irrelevant, since
all that must be shown to satisfy the
NRC’s requirements is that the emergency
plan is "designed to achieve reasonable
and feasible dose savings given the
circumstances of the site in question."
Once that is shown, it is irrelevant
"whether these dose savings will be high
or low in absolute terms at a particular
site in the circumstances of a given
accident or class of accidents."
- i160 =
The Appeal Board was correct,
applicants argue, in finding that the
NRC’s emergency planning rules, having
been promulgated under Section 161 of
the Atomic Energy Act, constitute
"second tier" protection under the
two-tier formula described in UCS I.
Citations of authority are required by
the Administrative Procedure Act, and
are not merely some afterthought to
which the agency may or may not give
consideration. The 1980 Commission
transcript on which intervenors rely is
at best inconclusive. It does not
remove the ambiguity as to the meaning
of “adequate protective measures" in the
regulation, but it does make clear that
the emergency planning rules were not
intended as a "site blocking"
regulation. Moreover, the 1987
= 463 -
emergency planning rules commented on
che “inconsistency” in the Comnission’s
1980 pronouncements on emergency
planning.
According to applicants, the
intervenors may be correct in saying
that a reference to Section 161 does not
necessarily designate a rule as "second
tier," but in the case of the emergency
planning rules, it is clear that the
Commission intended second tier status.
The fire protection rule, cited by
intervenors as an “obvious example" of a
first tier safety regulation which was
issued under Section 161, actually
demonstrates the opposite. In the list
of authorities for Part 50 found at 52
Federal Register 41294, Section 161(b)
is cited as authority for Section 50.48,
for purposes of 42 U.S.C. Section 2273
- iG2a -
(establishing criminal sanctions for
violations). Sections 161 and 182 are
both cited as authority, for Part 50.
Thus the reference in the rulemaking to
Section 161(b) was intended to identify
§ 50.48 as a regulation to which
criminal sanctions would apply. With
regard to § 50.47, however, the list of
authorities for Part 50 does not mention
§ 50.47 specifically. However, the
rulemaking listed Sections 161(b),
161(i), and 161(0). This fact, coupled
with the absence of a statement that
criminal sanctions would apply to the
regulation, demonstrates that the
Commission could only have intended §
50.47 to be a second tier regulation.
In the applicants’ view, reference
to statements made to the Congress by
individual Commissioners deserve little
= 163 -
or no weight in determining whether the
regulation is first or second tier.
More to the point is the distinction
which the Commission drew in Shorehan,
CLI-86-13, between emergency planning
regulations and siting and engineering
design requirements "which are directed
at achieving or maintaining a minimum
level of public safety protection." such
as 10 CFR § 100.11, which establishes
the exclusion area and low population
zone in terms of doses to individuals.
This language clearly shows emergency
planning regulations to be second tier.
Finally, say the applicants, the
discussion in the Comission’s 1987
proposed rulemaking makes clear that any
ambiguity was to be resolved in favor of
calling emergency planning rules second
tier. ‘Yhe final rule made the further
- 164 -
point that the 120-day clock in the 1980
rule showed the second tier status of
emergency planning requirements.
3. NRC Staff
According to the NRC staff, the
Commission’s regulations -- the plain
wording of Section, 50.47(a)(1), the
pertinent administrative history, and
prior Commission interpretations -- all
demonstrate that the Licensing Board was
correct in excluding the proferred
testimony. The regulation calls for
determinations by FEMA on the adequacy
and implementability of offsite plans,
in accordance with planning standards of
Section 50.47(b). The regulation does
not provide for a dose reduction/dose
consequences analysis, but rather for a
review of the plans against the
standards to see if they are adequate
» 392 °
~
and implementable. The Statement of
Considerations of the 1980 rule did not
indicate that there was to be any
examination of radiological doses and
consequences. The Commission there
recognized that FEMA was best suited to
assess offsite emergency preparedness.
The NRC final rule restated, and cited,
the guidance of NUREG-0654/FEMA-REP-1,
which states that the planning basis for
the standards was a spectrum of
accidents, independent of specific
accident sequences. Thus the Commission
intended that individual licensing cases
look at conformance with the standards,
not at particular accident sequences or
their consequences.
The NRC staff asserts that in San
Onofre, CLI-83-10, 17 NRC 528 (1983),
the Commission refuted the concept that
- i166 =
dose reduction calcula‘ ions are needed
or relevant. In Shoreham, the
Commission focused on "reasonable and
feasible dose reductions under the
circumstances," not on achieving "a
preset minimum radiation dose saving or
a minimum evacuation time." This was a
plain indication that there was to be no
consideration of absolute dose reduction
Or consequences at particular sites.
While Shoreham could be read in the
manner outlined by the Appeal board to
allow dose savings and cor. equences to
be litigated as part of determining
-whether dose reductions achieved by a
plan are "reasonable," the decision,
when read in context, emphasizes that
plans are to be judged against
"standards" rather than on the basis of
dose and risk calculations. That point
- 167 -
was reiterated several times in the 1987
final rule on emergency planning. That
Same rule made clear that plans were to
be judged without reference to the
specific dose reductions that might be
accomplished under a particular plan.
It is immaterial, says the NRC
staff, whether emergency planning is a
first tier or second tier regulation,
for in either case, the proffered
testimony was irrelevant. Intervenors’
emphasis on emergency planning as a
first tier, adequate protection standard
seens to be based on the misconception
that if the regulation is first tier,
dose calculations are required to
determine the adequacy of emergency
plans. In fact, whether the regulation
was adopted under Section 161 of the AEA
(as these were) or Section 182, the
- 468 =
Commission’s regulations do not call for
dose calculations, but rather for
conformity with standards set out in the
regulations. In this regard they are
like many of the Comiasion*s most basic
safety regulations, such as emergency
core cooling standards and quality
assurance requirements. If the
intervenors wished to challenge the
adequacy of the rule, they could have
petitioned for a rule change, and they
could have asked for a waiver of the
rule in this case. Instead, they are
attempting to engraft onto the rule
requirements over and above those
established by the Commission.
To answer the certified question
directly, the NRC staff maintains, the
phrase “reasonable and feasible dose
reductions under the circumstances" in
- 169 =
Shoreham envisioned testimony not on
dose projections and dose consequences,
but on reasonable and feasible methods
of dose reduction for a particular site
under the circumstances existing there.
The Licensing Board received such
testimony and concluded, as had FEMA,
that the New Hampshire emergency plan
provided "for a range of protective
actions."
IV. Discussion
1. "First Tier" vs. "Second Tier"
In approaching the issues presented
by the certified question, it may be
useful to begin by addressing, as a
threshold matter, the Appeal Board’s
finding that emergency planning is a
second-tier, “extra-adequate’ protection
requirement. We do so for the sake of
Clarifying this area of the Commission’s
- 170 -
regulations, not because it is necessary
to our decision. We agree with the NRC
Staff that for the purpose of deciding
whether the Massachusetts Attorney
General’s proffered testimony should
have been admitted, it is immaterial
whether the emergency planning
regulations are considered first tier or
second tier.
The issue of what the Commission
intended when it put the emergency
planning rule in place was discussed
extensively in the proposed and final
1987 emergency planning rules and their
Statements of Considerations. In the
March 1987 proposed rule (52 Fed. Reg.
6980), the Commission commented on the
inconsistency between some of the
language of the 1980 rulemaking and the
regulatory scheme that it actually put
- 171 -
in place. Writing after the
promulgation of the backfit rule, the
Commission in its March 1987 notice also
squarely posed the question whether
emergency planning should be considered
first tier or second tier protection:
On the one hand, the Commission
stated that the new requirements,
as well as proper siting and
engineered safety features, were
needed to protect public health and
safety. Taken in isolation, these
statements can be read as
evidencing a CommiSsion decision
that emergency planning and
preparedness as provided in those
revised rules were to be treated as
matters essential to safe operation
of nuclear facilities and therefore
to be imposed rigorously without
regard to equity or cost.
On the other hand, the Commission
rejected an option in the
rulemaking that could have led to
automatic plant shutdown if
adequate plans were not filed
because of commenters’ concerns
about "unnecessarily harsh economic
and social consequences to State
and local governments, utilities,
and the public." Operating plants
were given very substantial grace
periods .... These provisions are
- 172 -
not consistent with the concept
that emergency planning and
preparedness are as important to
safety as such engineered
safeguards as reactor containments
or emergency core cooling systems.
Rather, these provisions
reflect a different concept -- that
adequate emergency planning and
preparedness are needed and
important, but that they represent
an additional level of public
protection that comes into play
only after all of the other safely
requirements for plant design,
quality construction, and careful,
disciplined operation have been
considered, and that therefore some
regulatory flexibility is warranted
and the costs associated with
alternative approaches may be taken
into account.
The Commission’s notice asked for
comment on which of the two
approaches should be followed:
a relatively inflexible one,
that will require adequate
planning and prtparedness with
little or no concern for
fairness or cost; or a more
flexible one that focuses on
what kind of accident
riitigation (dose reduction to
the public in the event of an
- 173 -
accident) can be reasonably
and feasibly accomplished,
considering all of the
circumstances. If sound
safety reg-uration requires
the former, then no rule
change is warranted. If the
latter, then a change would be
in order.... ,in other words,
the Comnission’s March 1987
proposed rule recognized
explicitly that to move from
an "adequate protection"
standard to a "second tier" or
backfit standard, a rule
change would be needed.
The Commission’s November 1987 final
rule, 52 Fed. Reg. 42078, disavoy,ed
any interit xo move from the fornier to
the latter approach. The Commission
began its answer to the question, "Is
emergency planning as important to
safety as proper plant design and
operation?", by declaring:
First of all, this issue does
not have to be addressed in
the context of the final rule
announced in this notice,
since the present rule
- 375 =
involves no redrawing by NRC
of the balance between
emergency planning and other
provisions for the protection
of health and safety.
The Commision then went on to
discuss the words used in the 1980 rule,
noting that in places, emergency
planning was desibribed as "essential"
and "needed," whereas elsewhere
emergency planning was described as
"bolstering" the protection offered by
engineered design features. The issue,
said the Commission, could not be
resolved definitively by "microscopic
analysis" of the language of the 1980
notice. More relevant, said the
Commission, was the regulatory structure
put in place, in particular the "120-day
clock":
In 10 CFR 50.54(s) (2) (ii), the
Commission provided that if it
"finds that the state of
emergency preparedness does
- 175 -
not provide reasonable
assurance that adequate
protective measures can and
will be taken in the event of
a radiological emergency .
and if the deficiencies . .
are not corrected within four
months of that finding, the
Commission will determine
whether the reactor shall be
shut down until such
deficiencies are remedied or
whether other enforcement
action is appropriate. In
other words, a plant
ordinarily may operate for at
least four months with
deficiencies in emergency
planning before the NRC is
required even to decide
whether remedial action should
be taken. .. . at the time
that the Commission created
the so-called "120-day clock"
for deficiencies in emergency
planning, it was settled
Commission law (and remains so
today) that the NRc must issue
an order directing a license
to show cause why its license
should not be modified,
revoked, or suspended whenever
it concludes that "substantial
health or safety issues ha[ve)]
been raised about the
activities authorized by the
license. .. . in the
context of that standard, the
120-day clock provision for
emergency planning
- 176 -
deficiencies amounts to a
Commission f.nding that, at
least for *ne first 120 days,
even a major deficiency in
emergency planning does not
automatically raise a
“substantial health or safety
issue" with regard to plant
operation. By contrast, a
major safety deficiency
relating to emergency
conditions -- for example, the
availability of the emergency
core cooling system -- would
warrant inirtiediate shutdown.
In sum, despite language
indicating that emergency
planning was "essential," the
Commission in 1980 created a
regulatory structure in which
emergency planning was treated
somewhat differently, in terms
of the corrective actions to
be taken when deficiencies are
identified from the engineered
safety features ("hardware")
that would be relied on in an
emergency.
The foregoing discussion from the
1987 final rule helps to clarify the
real nature of the issue in dispute.
The relevant consideration is not
whether emergency, planning as a general
- 177 -
matter is a part of "adequate
protection" or of "extra-adequate
protection." The Commission’s
rulemakings of 1980 and 1987 establish
that it is the former. (We do not share
the Appeal Board’s view of the
significance of the citation to Section
161 in the 1980 rulemaking.) To frame
the issue in terms of a simple choice
between "adequate" and "extra-adequate"
protection is to lose sight of the
reality that when the Commission
enumerates the many individual safety
issues which must be resolved in order
to find "adequate protection," it is not
thereby declaring that all those
component issues are of equal safety
Significance, or that the same standards
for demonstrating compliance are
applicable to all.
- 178 -
For illustration, one need only
consider the gamut of issues presented
in 10 CFR 50.34(b), dealing with the
Final Safety Analysis Report. These
include: a description of the reactor
coolant system, instrumentation and
control systems, electrical systems,
containment system, and other engineered
safety features (50.34(b)(2)(i)); the
applicant’s organizational structure and
personnel qualifications requirements
(50.34(b) (6) (1i))? plans for conduct of
normal operations, including
maintenance, surveillance, and periodic
testing of structures, systems, and
components (50.34(b)(6)(iv))?; plans for
coping with emergencies
(50.34(b) (6) (v))7 a description of the
operator requalification program
(50.34(b)(8))?7 a description of
* Fe =
protection provided against pressurized
enermal shock events, including
erosected values of the reference
termperature for reactor vessel beltline
materials (50.34(b)(9)); plans for
physical security at the facility
(50.34(c)); and safeguards contingency
plans for dealing with threats, thefts,
and sabotage (50.34(d)). Plainly, each
of these component determinations has
safety significance, and since none can
be dispensed with, all can be called
"essential"; but no one would claim that
each is of identical weight in
contributing to public protection. ‘Nor
would anyone assert that the same type
of analysis is appropriate for each.
Necessarily, the kind of highly
technical inquiry appropriate to
determining the adequacy of the plant’s
- 460 =
hardware will not resemble either the
"human factors" analysis applied to the
utility’s operator requalification
program, or the predictive judgments
required for a decision on safeguards
contingency plans.
The real issue, therefore, is not a
judgment in the abstract about the place
of emergency planning in the hierarchy
of safety standards, or an exercise in
semantics about the meaning of the word
"essential." (So that there may be no
misuriderstanding, let us make clear
that adequate emergency planning is
"essential," just as adequate lifeboats
are essential for a liner carrying
passengers at sea. But it is only
common sense to acknowledge that
emergency plans, like lifeboats, are a
backstop, a second or third line of
=~ jon *
defense that comes into play only in the
extremely rare circumstance that
engineered design features and human
capacity to take corrective action have
both failed to avert a serious mishap.)
For our purposes today, the real issue
is a much more straightforward question:
what is the nature of the inquiry that
the Commission, in recognition of the
fact that emergency planning involves
predicting the ability to respond to the
unpredictable, has put in place for
determining whether "adequacy," i.e.,
compliance with the Commission’s
emergency planning regulations, has been
established?
= 233 °
2. How Adequacy is Determined
The Commission’s emergency planning
requirements are not obscure. In the
text of the regulations, in rulemakings
on the subject of emergency planning,
and in adjudicatory decisions
interpreting those regulations, the
Commission has made clear that judgments
on the adequacy of emergency planning
are to be based on conformity with the
16 planning standards set forth in 10
CFR / 50.47(b). [Footnote in original]
110 CFR § 50.47(b) provides:
The onsite and, except as provided
in paragraph (d) of this section,
off-site emergency response plans for
nuclear power reactors must meet the
following standards:
(1) Primary responsibilities
for emergency response by the
nuclear facility licensee and by
State and local organizations
within the Emergency Planning Zones
have been assigned, the emergency
responsibilities of the various
~ 263 «
supporting organizations have been
specifically established, and each
principal response organization has
staff to respond and to augment its
initial response on a continuous
basis.
(2) On-shift facility
licensee responsibilities for
emergency response are
unambiguously defined, adequate
staffing to provide initial
facility accident response in key
functional areas is maintained at
all times, timely augmentation of
response capabilities is available
and the interfaces among various
onsite response activities and
offsite support and response
activities are specified.
(3) Arrangements for
requesting and effectively using
assistance resources have been
made, arrangements to accommodate
State and local staff at the
licensee’s near-site Emergency
Operations Facility have been made,
and other organizations capable of
augmenting the planned response
have been identified.
(4) A standard emergency
classification and action level
scheme, the bases of which include
facility system and effluent
parameters, is in use by the
nuclear facility licensee, and
State and local response plans call
for reliance on information
- 184 -
provided by facility licensees for
determinations of minimum initial
offsite response measures.
(5) Procedures have been
established for notification, by
the licensee, of state and local
response organizations and for
notification of emergency persornel
by all organizations; the content
of initial and followup messages to
response organizations and the
public has been established; and
means to provide early notification
and clear instruction to the
populace within the plume exposure
pathway Emergency Planning Zone
have been established.
(6) Provisions exist for
prompt communications among
principal response organizations to
emergency personnel and to the
public.
(7) Information is made
available to the public ona
periodic basis on how they will be
notified and what their initial
actions should be in an emergency
(e g., listening to a local
broadcast station and remaining
indoors), the principal points of
contact with the news media for
dissemination of information during
an emergency (including the
physical location or locations) are
established in advance, and
procedures for coordinated
= too =
dissemination of information to the
public are established.
(8) Adequate emergency
facilities and equipment to support
the emergency response are provided
and maintained.
(9) Adequate methods,
systems, and equipment for
assessing and monitoring actual or
potential offsite consequences of a
radiological emergency condition
are in use.
(10) A range of protective
actions have been developed for the
plume exposure pathway EPZ for
emergency workers and the public.
Guidelines for the choice of
protective actions during an
emergency, consistent with Federal
guidance, are developed and in
place, and protective actions for
the ingestion exposure pathway EPZ
appropriate to the locale have been
developed.
(11) Means for controlling
radiological exposures, in an
emergency, are established for
emergency workers. The means for
controlling radiological exposures
shall include exposure guidelines
consistent with EPA Emergency
Worker and Lifesaving Activity
Protective Action Guides.
- 496 «
(12) Arrangements are made for
medical services for contaminated
injured individuals.
(13) General plans for
recovery and reentry are developed.
(14) Periodic exercises are
(will be) conducted to evaluate
major portions of emergency
response capabilities, periodic
drills are (will be) conducted to
develop and maintain key skills,
and deficiencies identified as a
result of exercises or drills are
(will be) corrected.
(15) Radiological emergency
response training is provided to
those who n)ay be called on to
assist in an emergency.
(16) Responsibilities for plan
developr,*nt and review and for
distribution of emergency plans are
established, and planners are
properly trained.
For offsite planning, the regulations
provide that the Federal Emergency
Management Agency (FEMA) shall make
"findinas and determinations as to
whether State and local emergency plans
are adequate and whether there is
- 187 -
reasonable assurance that they can be
implemented." 10 CFR / 50.47(a) (2). This
FEMA finding "will primarily be based on
a review of the plans." Id. The same
regulation also provides that "[{iJn any
NRC licensing proceeding, a FEMA finding
will constitute a rebuttable presumption
on questions of adequacy and
implementation capability." 10 CFR §
50.47(c), which states that the
Commission may decline to issue an
operating license in case of "[(f]Jailure
to meet the applicable standards set
forth in paragraph (b) of this section,"
reinforces the point that adequacy is to
be judged by conformity with the
planning standards. Nothing in the
regulation contains any suggestion that
calculations of dose consequences are
intended to play a role in the
- 188 -
evaluation of a plan’s adequacy.
As the NRC staff pointed out in its
brief, the 1980 rulemaking was in part a
restatement of the guidance developed
jointly by NRC and FEMA in
NUREG-0654/FEF,A-REP-1, "Criteria for
Preparation and Evaluation of
Radiological Emergency Response Plans
and Preparedness in Support of Nuclear
Power Plants." That document, frequently
quoted and relied upon in the 1980
rulemaking, states in part:
The overall objective of
emergency response plans is to
provide dose savings (and in
some cases immediate life
saving) for a spectrum of
accidents that could produce
offsite doses in excess of
Protective Action Cuides
(PAGS). No single specific
accident sequence should be
isolated as the one for which
to plan because each accident
could have different
consequences, both in nature
and degree. Further, the
range of possible
* i393 *
selection for a planning basis
is very large, starting with a
zero point of requiring no
planning at all because
significant offsite
radiological accident
consequences are unlikely to
occur, to planning for the
worst possible accident,
regardless of its extremely
low likelihood. The NRC/EPA
Task Force did not attempt to
define a single accident
sequence or even a limited
number of sequences. Rather,
it identified the bounds of
the parameters for which
planning is recommended, based
upon Knowledge of the
potential consequences,
timing, and release
characteristics of a spectrum
of accidents. Although the
selected planning basis is
independent of specific
accident sequences, a number
of accident descriptions were
considered in the development
of the guidance, including the
core melt accident release
categories of the Reactor
Safety Study. At 6-7
(footnotes omitted).
In other words, consideration of
specific accident sequences and their
potential dose consequences has been
- 100 =
rendered unnecessary by the promulgation
of generic guidance that incorporates
and synthesizes data on a range of
accidents and their consequences. Thus
the seeming anomaly of excluding
proffered evidence on dose consequences,
where the objective of the inquiry is to
reduce dose consequences, is in fact no
anomaly at all. For it is by applying
the generic guidance of the regulation’s
16 standards to the review of individual
emergency plans -- not by attempting to
predict the effects of particular
hypothetical accidents occurring under
particular hypothetical conditions of
weather, time of year, and time of day
-- that the NRC satisfies itself that
the goal of achieving dose reductions is
met.
- i393 =
The Commission interpreted and
explained its emergency planning
requirements in the 1983 San Onofre
decision, where it said:
Since a range of
accidents with widely
differing consequences
can be postulated, the
regulation does not
depend on the assumption
that a particular type of
accident may or will
occur. In fact, no
specific accident
sequences should be
specified because each
accident could have
different consequences
both in nature and
degree. Although the
emergency planning basis
is independent of
specific accident
sequences, a number of
accident descriptions
were considered in
development of the
Commission’s regulations,
including the core melt
accident release
categories of the Reactor
Satety Study
(WASH-1400). (Footnote
omitted. )
- £338 =
Southern California Edison Co.,
(San Onofre Nuclear Generating
Station,
Units 2 and 3), CLI-83-10, 17 NRC
528, 533 (1983).
The Comission further
explained:
It was never the intent
of the regulation to
require directly or
indirectly that state and
local governments adopt
extraordinary measures,
such as construction of
additional hospitals or
recruitment of
substantial additional
medical personnel, just
to deal with nuclear
plant accidents. The
emphasis is on prudent
risk reduction measures.
The regulation does not
require dedication of
resources to handle every
possible accident that
can be imagined. The
concept of the regulation
is that there should be
core planning with
sufficient planning
flexibility to develop a
reasonable ad hoc
response to those very
serious low
probability-accidents
which could affect the
general public.
» {33 =
In the 1986 Shoreham hedtaten.
CLI-86-13, 24 NRC 22, the Commission
discussed the emergency planning
regulations in language which appears to
have left the Appeal Board with some
uncertainty as to the nature of the
inquiry called for. Among other things,
the Commission said:
Our emergency planning
requirements do not require
that an adequate plan achieve
a preset minium radiation dose
saving or a minimum evacuation
time for the plume exposure
pathway emergency planning
zone in the event of a serious
accident. Rather, they
attempt to achieve reasonable
and feasible dose reduction
under the
circumstances; what may be
reasonable or feasible for one
site may not be for another.24
NRC 22, 30.
Referring to the fact that State
and local governments were not
participating in emergency planning
for Shoreham, the Commission
continued:
- 194 =
But what should we regard as
reasonable «nd feasible for
Shoreham, where the
governments refuse to
cooperate? ... We could
conceivably define what is
reasonable and feasible dose
reduction for Shoreham solely
in terms of what LILCO itself
can reasonably and feasibly
achieve, but we are not
prepared to do so. Rather, we
might look favorably on the
LILCO plan if there was
reasonable assurance that it
was capable of achieving dose
reductions in the event of an
accident that are generally
comparable to what miaht be
accomplished with government
cooperation. ... In sum, we
conclude that LILCO’s plan
should be measured against a
standard that would require
protective measures that are
generaily couparable to what
might be accomplished with
governmental cooperation.
24 NRC 22, 30, 32.
Recognizing that the language just
quoted lent itself to the interpretation
that findings on dose reductions are a
part of the emergency planning inquiry,
the Commission soon provided a
clarification. In the final emergency
planning rule, 52 Federal Register 42078
(November 3, 1987), the Commission
stated:
~ 195 =
The Commission currently
believes that the
planning standards of 10
CFR 50.47(b), which are
used to evaluate a state
or local plan, also
provide an appropriate
framework to evaluate a
utility plan. Therefore
coe @ WEALECY BLBH ...
will be evaluated for
adequacy against the sane
standards used to
evaluate a state or local
plan.
The approach reflected in
this rule amplifies and
clarifies the guidance
provided in the
Commission’s decision in
Lonq Island Lighting Co.,
(Shoreham, Nuclear Power
Station, Unit--I),
CLI-BE-13, 24 NRC 22
(1986). ... That decision
included larguage
which could be
interpreted as
envisioning that the NRC
must estimate the
radiological dose
reductions which a
utility plan would
achieve, compare them
with the radiological
dose reductions which
would be achieved if
there were a state or
local plan with full
- 136 =<
state and local
participation in
emergency planning, and
permit licensing only if
the dose reductions are
literally comparable."
Such an interpretation
would be contrary to NRC
practice, under which
emergency plans are
evaluated for adequacy
without reference to
numerical dose reductions
which would be
accomplished and without
comparing them to other
emergency plans, real or
hypothetical. The final
rule makes clear that
every emergency plan is
to be evaluated for
adequacy on its own
merits, without rererence
to the specific dose
reductions which might be
accomplpished under the
plan or to the
capabilities of any other
plan. It further makes
clear that a finding of
adequacy for any plan is
to be considered
generally comparable to a
finding of adequacy for
any other plan.
(Emphasis added.)
52 Federal Register 42078, 42084-85.
Thus to the extent that Shoreham
suggested that evidence might be taken
on dose consequences, the guidance in
the 1987 final rule superseded it
completely. The final rule should have
left little room for doubt as to the
Commission’s intent, which may be
summarized as follows: Emergency plans
are to be evaluated on-their own merits,
against the 16 planning standards of 10
CFR 50.47(b), with presumptive validity
accorded to FEMA’s expert judgments on
offsite planning; that the evaluation
does not entail consideration of the
dose consequences that might be
calculated under various hypothetical
circumstances; and that a plan judged
adequate against these planning
standards is considered generally
comparable to any other plan that has
been found adequate.
~ 198 «
Consistent with that guidance, we
find that the Licensing Board acted
correctly in excluding the proffered
testimony. The Appeal Board, in
suggesting that the testimony might be
admissible for the purpose of
determining whether "reasonable and
feasible" dose reductions are
accomplished by a plan, may have
confused the objective of the emergency
planning inquiry with the means used to
accomplish the objective. The
objective, plainly, is the achievement
of reasonable and feasible dose
reductions in the event of an accident.
But the means which the Commmission has
determined to use is an evaluation of
emergency plans against the 16 planning
standards developed by NRC and FEMA.
- 4199 =-
That determination, made by rule,
is not for individual adjudicatory
boards to alter. Parties dissatisfied
with that approach may petition to
change the rule, or they may attempt, by
requesting a waiver of the rule, to show
why it should not be applied to a
particular case. The parties before us
have chosen reeither of those courses of
action. Accordingly, we find that there
was no purpose for which the proffered
testimony was admissible.
In concluding, we wish to make
clear that this opinion does not decide
whether emergency planning at Seabrook
is adequate, nor whether that facility
should receive a license to operate at
full power. Rather, it provides, in
accordance with our procedures for
directed certification, guidance as to
- 4200 =
how, under the Commission’s rules,
determinations on the adequacy of
emergency planning are to be made.
It is so ORDERED.
- 429i =
This is a copy of a public record, reproduced as it was published. It is not legal advice, and it may not be the version a court would rely on. Check the official source before you cite it.