Petition — J. W. Bateson, Inc. v. United States
Supreme Court brief1981
Ask Donna
What actually matters in this document.
Text
=
Office-Supreme Court, U.S.
FILED
80-2113 JUN 5 1981
ALEXANDER L. STEVAS,
CLERY
IN THE SUPREME COURT OF THE UNITED STATES
October Term, 1981
No. A-881
J. W. BATESON, INC., Petitioner
v.
UNITED STATES OF AMERICA
PETITION FOR WRIT OF CERTIORARZ
TO THE SUPREME COURT CF THE
UNITED STATES FROM THE
UNITED STATES COURT OF CLAIMS
J. CARLISLE OVERSTREET
Attorney for Petitioner
P. O. Box 1836
Augusta, Georgia 30903
QUESTIONS PRESENTED
Whether the disputes provisions
of a government contract that forces a
party to the contract through admini-
strative review that does not allow
resolution of all disputes evolving
under the contract is in violation of
the due process provisions of the Con-
stitution; and (2) whether under said
dispute provisions and review the
standard and burden of proof cannot be
met because of intentional and harmful
acts done to the Petitioner and its
records by the Government is a violation
of due process provisions of the Con-
stitution.
Opinions Below . . .« « 6 « © « © « e
Jurisdiction . ..6 «se « «see 2
Question Presented ........ 3
Statute Involved ......++e«s. 4
Statement of Case ....-+-+-e- 6
Reasons for Granting Writ ... .12
Conclusion Me ea ths ea ee ree Maree f
Appendix A
Order of the United States Court
of Claims of December 12, 1980 . .21
Opinion of Trial Judge, United
States Court of Claims, Trial
Division, of May 21, 1980 ... .24
Order Denying Rehearing of the
United States Court of Claims
of Fepruary: 6, 1961 «2.6 6.0.02 62
Order Extending Time to File Petition
for Writ of Certiorari of the Supreme
Court of the United States until
June 6, 1981, of April 30, 1981. .63
i
TABLE OF CASES
Page
Baltimore & O. R. Co. v. United
States, 298 US 349 * ° 7 7 ° . 12
Bowman Transportation, Inc. v.
Arkansas~-Best Freight System,
Inc., U , re en,
420 us 956 . . . * * . . . 7 . 14
First Unitarian Church v. County
of Los Angeles, Be ee
Green v. Georgia, 60 Lawyers
%
Addition 38 99 Supreme
Court: 2150: 1979 Cases .« «6. 16
Jenkins v. McKeithen, 395 US 411. 12
NLRB v. Indiana and M. Electrical
Company, BE ee a ie he ies AT
Speiser v. Randal, 357 US 513, 15
reh den, 358 US 860 .....
United States v. Storer Broad-
Casting Company, 351 US 192 . 17
wad fas
STATUTES
Amendment V, United States
Camegti tution «i. 3
-iii-
MISCELLANEOUS
Page
Disputes Clause of Contract. . 18
-iv-
IN THE SUPREME COURT OF THE UNITED STATES
October Term, 1981
No. A-881
J. W. BATESON, INC., Petitioner
Vv.
UNITED STATES OF AMERICA
PETITION FOR WRIT OF CERTIORARI TO
THE SUPREME COURT OF THE UNITED STATES
To the Honorable, the Chief Justice and
Associate Justices of the Supreme Court
of the United States:
J. W. BATESON, INC., the
petitioner herein, prays that a writ of
certiorari issue to review the judgment
of the United States Court of Claims of
December 12, 1980, of which rehearing was
denied on February 6, 1981, adopting the
Trial Division's Opinion of May 21, 1980.
OPINIONS BELOW
The Order of the United States
Court of Claims of December 12, 1980, is
printed in Appendix A hereto, infra, page
2\. The Trial Division's Opinion in the
United States Court of Claims which was
adopted as the Order of this Court is
printed in Appendix hereto, infra, page Zj.
The Order Denying Rehearing is printed in
Appendix A hereto, infra, page 62.
JURISDICTION
The judgment of the United
States Court of Claims, (Appendix A, infra,
page ,.?/_) was entered on December 12,
1980. The timely petition for rehearing
was denied on February 6, 1981 (Appendix
A, infra, page $62). The jurisdiction of
the Supreme Court is invoked under Title
28 of the USCA§1255,
QUESTIONS PRESENTED
Whether the disputes provisions
of a government contract that forces a
party to the contract through admini-
strative review that does not allow
resolution of all disputes evolving
under the contract is in violation of
the due process provisions of the Con-
stitution; and (2) whether under said
dispute provisions and review the
standard and burden of proof cannot be
met because of intentional and harmful
acts done to the Petitioner and its
records by the Government is a violation
of due process provisions of the Con-
stitution.
CONSTITUTIONAL AND STATUTORY
PROVISIONS INVOLVED
This case involves the fourth
section of the Fifth Amendment to the
Constitution of the United States,
which provides as follows:
No person shall be held to
answer for a capital, or otherwise infa-
mous crime, unless on a presentment or
indictment of a Grand Jury, except in
cases arising in the land or naval
forces, or in the Militia, when in
actual service in time of War or public
danger; nor shall any person be subject
for the same offense to be twice put in
jeopardy of life or limb; nor shai be
compelled in any criminal case to be a
witness against himself, nor be deprived
of life, liberty, or property, without
due process of law; nor shall private
property be taken for public use, with-
out just compensation.
STATEMENT OF CASE
Wrongful and intentional acts
are the basis of this action brought by
J. W. Bateson on behalf of the real party
at interest,*Fidelity Sound, Inc. The
decision of the Armed Services Board of
Contract Appeals 19823 and 22337 were
reviewed by the United States Court of
Claims under the judicial review stan-
dards set forth in the Wunderlich Act
41 USC §321, §322, seeking judicial
review of a breach of contract. The
contract (DACA-21-71-C-0061 for the
construction of the United States Army
Hospital at Fort Gordon, Georgia) was
awarded to Petitioner on April 9, 1971,
and included the requirements for an
*Pidelity Sound, Inc. is a wholly owned
subsidiary of RVA Corporation, a pub-
lically held corporation, with its
principal place of business at 1212 City
National Bank Building, Miami, Florida
33130. 6
audio-nurse call systems which required
facilities for patient communications.
Truland, Fischbach and Moore were
awarded the electrical contract under
Petitioner and Fidelity Sound, the real
party at interest, was a subcontractor
of Truland, Fischbach and Moore. The
contract was awarded on July 12, 1971.
Resulting appeals to the Armed Services
Board of Contract Appeals resulted in
equitable adjustment of $234,536.26 to
Petitioner and a review was made to the
United States Court of Claims by the
Petitioner. Review was limited to
Wunderlich Act provisions even though
Petitioner south review on the basis os
(1) a breach £f contract due to in-
tentional and wrongful acts of an
employee of the Corps of Engineers; and
(2) the standards of proof applied to the
Petitioner in this appeal before the
Board. 7
THE ACTS
Claims relating to the actions
of the United States Corps of Engineers’
employee, Mr. Utermark, was raised in
testimony before the Armed Services
Board of Contract Appeals. The actions
are such that they are indicative of in-
tent to change the specifications to pre-
vent the Petitioner from complying with
them. Mr. Utermark, on several occasions,
attempted to have the specifications
changed so only one special system would
comply. On at least five different
occasions he disapproved the submittals
in total when in fact they have been
found by the Board to meet the speci-
fications required. On at least one
occasion Mr. Utermark wrongfully
attempted to influence the writer of the
specifications. The Petitioner was
required to perform different duties
8
from those in the contract, more partic-
ularly, submitting various submittals for
over a year and finally having to in-
stall a system which the Board found a
"small wonder" that the Petitioner was
able to comply. Mr. Utermark's actions
reflect his intentions. Granted, if the
actions had been totally harmless the
proper relief would have been an equit-
able adjustment, but under these facts
his intentional actions were taken to
prevent the Petitioner from complying
with the contract specifications. The
Armed Services Board of Contract
Appeals has refused to review such
claims for relief.
BURDEN OF PROOF
The Armed Services Board of
Contract Appeals prevented testimony as
to the wrongdoings and intentional acts
9
of the employee of the Corps, Mr. Uter-
mark. Elimination of said testimony
was that the Board had no power to render
any decision that might have related to
those acts. The Corps itself prevented
access to Mr. Utermark by having him
placed in a station in the Middle East
during this litigation.
Also, the process of requiring
numerous submittals; waiting unusual
lengths of time for a @ccision by the
local Contracting Officer; extensive
hearings, both as to entitlement and
as to quantum, totally destroyed the
company as it proceeded through the
administrative process. The damage was
enormous to the real party at interest,
Fidelity Sound, and such a large
financial injury cannot be sustained by
a company of this size. The actual
total destruction was the anticipated
10
result of the delay.
Now, through the application
of burden of proof, the Corps of Engi-
neers and the Armed Services Board of
Contract Appeals demands Petitioner to
prove its case with evidence which has
obviously been destroyed and makes its
demand through the applicable rules of
the Armed Services Board of Contract
Appeals as used in the disputes clause
of the ccutract. The administrative
procedures before the Armed Services
Board of Contract Appeals are of a
quasi-judicial character and the
Petitioner's rights must be protected
by a fair and open hearing. The pro-
ceedings must satisfy pertinent demands
of due process.
The evidence submitted as to
the damages meeting the burden of proof
set forth in the decisions. Records
11
were made available to the Court and the
Court found them too burdensome to
receive. Administrative convenience is
not in and to itself adequate support
for infringement of a constitutional
right. Due process which was not
allowed in this instance requires that
the Board allow Petitioner the oppor-
tunity not only to present the evidence
but also the opportunity to argue said
evidence, which was not done.
REASONS FOR GRANTING WRIT
The right under the due process
clause of the United States Constitution
to a full hearing includes the right of
the party to introduce evidence Balti-
more & O. R. Co. v. United States, 298
US 349. The right to present evidence is
essential to the fair hearing required
by the due process clause. Jenkins v.
12
McKeithen, 395 US 411. The rights under
the due process clause includes the
right to have the judicial findings
based upon the evidence submitted.
Baltimore & O. R. Co. v. United States,
298 US 349. Due process implies the
right to contradict by proof every
material fact which bears on the question
of the right involved. The exclusion
of competent and relevent evidence on
the grounds that the hearing officer is
familiar with the facts surrounding the
relevant evidence is not due process.
At the second hearing as to entitle-
ment before the Armed Services Board of
Contract Appeals, the Board refused to
hear testimony and evidence as to wrong-
ful and intentional acts of the employee
of the Corps of Engineers and in its
opinion in the decision of the Court of
Claims, the Court of Claims totally
13
circumvented the arguments of the
Petitioner that said wrongful and in-
tentional. acts resulted in breach of
contract. The right to present proof
and argument is applicable in admini-
strative proceedings. DeLaRama v.
DeLaRama, 241 US 154. The due process
clause forbids an agency to use evidence
in a way to foreclose an opportunity of
presentation by Petitioner. Bowman
Transportation, Inc. v. Arkansas~Best
Freight System, Inc., 419 US 281, reh
den, 420 US 956.
Also, the rules of evidence as
applied by the Board exceed the bounds
in this case and in most cases of a
reasonable level of scrunity that can be
applied to said presumptions and has,
thus, excluded Petitioner from a fair
hearing. The damages and costs found by
' the first hearing before the Armed
14
Services Board of Contract Appeals to
exist prevented the Petitioner, more
particularly, the Fidelity Sound, Inc.,
the real party at interest, from
sustaining itself through the long
administrative appeal process. The
harmful actions of the Corps of Engineers
resultingly deprived the Petitioner under
the established rules as applied by the
Armed Services Board of Contract Appeals,
under the pretense of regulating evidence
from exhibiting or establishing its
rights. It is within the power of
government to establish the burden of
proof in civil cases provided it is
reasonable. In cases of unreasonable-
ness the courts have not hesitated to
s*+rike down rules or statutes unfairly
shifting the burden of proof. First
Unitarian Church v. County of Los Angeles,
357 US 545; Speiser v. Randal, 357 US 513,
15
reh den, 358 US 860. Also, in this
particular case total destrucion of
Fidelity Sound prevented other reason-
able and practical means of establishing
pertinent facts upon which a decision
could have been reached. Mechanical
applications of the rules of evidence
are not appropriate when used to defeat
the ends of justice, especially when in-
dividuals seek to introduce testimony
which is pertinent but the hearing
officer excludes such testimony and
especially when the testimony is highly
relevant to the critical issues of the
hearing. Green v. Georgia, 60 Lawyers
Addition, 2nd 738,99 Supreme Court 2150
(1979 case). A party's right to protect
itself when involved in quasi-judicial
proceedings includes the right to make
argument; to make proof or introduce
evidence; to meet the claims of opponent,
16
and to deny, explain, controvert or rebut
the claims of the opposing party. United
States v. Storer Broadcasting Company,
351 US 192. Findings cannot be said to
have been fairly reached unless material
evidence which might impeach the
position of the opposing party as well
as evidence that would support the
Claimant, have been heard and waived.
NLRB v. Indiana and M. Electrical
Company, 318 US 9.
CONCLUSION
For the foregoing reasons this
Petition for Writ of Certiorari should
be granted.
ISLE OVERSTREET
Attorney for Petitioner
17
APPENDIX
MISCELLANEOUS
6. DISPUTES (1964 JUN)
(a) Except as otherwise pro-
vided in this contract, any dispute con-
cerning a question of fact arising under
this contract which is not disposed of
by agreement shall be decided by the
Contracting Officer, who shall reduce
his decision to writing and mail or other-
wise furnish a copy thereof to the Con-
tractor. The decision of the Contracting
Officer shall be final and conclusive
unless, within 30 days from the date of
receipt of such copy, the Contractor
mails or otherwise furnishes to the
Contracting Officer a written appeal
addressed to the head of the agency in-
volved. The decision of the head of the
agency or his duly authorized repre-
sentative for the determination of such
appeals shall be final and conclusive.
18
This provision shall not be plead in any
suit involving a question of fact arising
under this contract as limiting judicial
review of any such decision to cases
where fraud by such official or his re-
presentative or board is alleged: Pro-
vides, however, that any such decision
shall be final and conclusive unless the
same is fraudulent or capricious or
arbitrary or so grossly erroneous as
necessarily to imply bad faith or is not
supported by substantial evidence. In
connection with any appeal proceeding
under this clause, the Contractor shall
be afforded an opportunity to be heard
and to offer evidence in support of his
appeal. Pending final decision of a
dispute hivwinaee) the Contractor shall
proceed diligently with the performance
of the contract and in accordance with
the Contracting Officer's decision.
19
(b) This "Disputes" clause
does not preclude consideration of
questions of law in connection with
decisions provided for in paragraph (a)
above. Nothing in this contract, how-
ever, shall be construed as making final
the decision of any administrative
official, representative, or board on a
question of law.
20
IN THE UNITED STATES COURT OF CLAIMS
No. 86-79C
J. W. BATESON, INC. )
v.
THE UNITED STATES
Construction contract; Wunderlich Act
review; constructive change; equitable
adjustment; breach of contract; cardinal
change.
J. Carlisle Overstreet, attorney for
record, for plaintiff.
Robert L. Brombaugh, with whom was
Assistant Attorney General Alice Daniel,
for defendant. Pollie Harris McElroy,
of counsel.
Before FRIEDMAN, Chief Judge, DAVIS and
KUNZIG, Judges.
ORDER
21
This case comes before the court on
plaintiff's request, filed June 25, 1980,
for review by the court of the recommend-
ed decision of Trial Judge James F. Merow,
filed May 21, 1980, pursuant to Rules
54 and 166 on the parties’ cross-motions
for summary judgment, and on plaintiff's
motion for de novo trial, having been
submitted on the briefs and oral argu-
ment of counsel. Upon consideration
thereof, since the court agrees with the
trial judge's recommended decision,
copies of which have been furnished to
the parties, it hereby affirms and
adopts the recommended decision as the
basis for its judgment in this case.
IT IS THEREFORE CONCLUDES AND
ORDERED that the ASBCA decision awarding
Plaintiff and equitable adjustment of
$234,536.26 is entitled to finality
under the judicial review standards of
22
41 U.S.C §§ 321, 322. Accordingly, de-
fendant's motion for summary judgment is
granted, plaintiff's motions for summary
judgment and de novo trial are denied
and plaintiff's petition is dismissed.
BY THE COURT
s/Daniel M. Friedman
Daniel M. Friedman
Chief Judge
DEC 12 1980
23
IN THE UNITED STATES COURT OF
CLAIMS TRIAL DIVISION
NO. 86-79C
(Filed May 21, 1980)
J. W. BATESON, INC. )
v.
THE UNITED STATES
Construction contract; Wunderlich
Act review; constructive change;
equitable adjustment; breach of
contract; cardinal change.
ON CROSS-MOTIONS FOR SUMMARY JUDGMENT
J. Carlisle Overstreet, attorney of
record, for plaintiff.
Pollie Harris McElroy, with whom was
Assistant Attorney General Alice Daniel,
for defendant.
OPINION*
*The opinion and recommended con-
clusion of law are submitted in accordance
with Rules 54 and 166.
24
MEROW, Trial Judge: This matter is
before the court on motions for summary
judgment addressed to the finality of the
Armed Services Board of Contract Appeals
(ASBCA) decision, issued October 27, 1978,
in Appeal No. 22337, under Contract DACA
21-71-C-0061, for the construction of a
United States Army Hospital at Fort
Gordon, Georgia. In addition, plaintiff
seeks a trial de novo in this court.
The Fort Gordon hospital contract
(DACA 21-71-C-0061) was awarded to J. W.
Bateson on April 9, 1971. Included in
the specifications was a requirement for
an audio-visual nurse call system which
required "***facilities for patient
communication, program entertainment,
and TV control." Various subcontractors,
submitted bids to J. W. Bateson for the
nurse call system. After being awarded
the hospital Conrtne as Bateson entered
into a subcontract with Truland, Fisch-
back and Moore (TFM) for the electrical
work on the project and, in turn, on
July 12, 1971 TFM subcontracted the
nurse call system to Fidelity Sound,
Inc. (Fidelity) for $273,000. ASBCA
Appeal No. 22337 and the instand liti-
gation concern the amount that was
awarded on claims submitted by Bateson
to the Government on behalf of the sub-
subcontractor, Fidelity.
As issued, the nurse call specifi-
cations for the Fort Gordon hospital pro-
ject contemplated the use of a standard
product but had been developed by
marrying the specifications of systems
offered by two manufacturers, Executone
and Motorola, in a way so that neither
of these systems could completely meet
the requirements.
26
Fidelity prepared its bid to TFM on
the basis of a nurse call system manu-
factured by Altec-Lansing. To comply
with a requirement that the items to be
installed in the project be approved by
the contracting officer, Fidelity, on
November 15, 1971, submitted a proposal
to install a nurse call system manu-
factured by Picker-Briggs. This was
disapproved on December 7, 1971 and,
after further revision by Fidelity, was
again disapproved on March 15, 1972.
Fidelity then, on May 8, 1972, proposed
the use of the Altec-Lansing system on
which it had based its bid to TFM and
this was cisapproved on May 24, 1972.
Fidelity, on May 25, 1972, contacted the
distributor for the Executone nurse call
system (Righton Distributing Company) and
obtained a quotation of $225,115, in-
cluding $19,921 for supervision of the
27
installation, testing, and a 12-month
guarantee, but did not then submit this
system to the contracting officer.
Rather, on June 27, 1972, a proposal to
use a system manufactured by Dukane was
submitted. This proposal was disapproved
on July 7, 1972. In August 1972 dis-
cussions were held by representatives of
the Government's contracting officer,
TFM, Fidelity and the distributor of
Executone equipment concerning possible
modifications of the nurse call system
as specified and an informal submission
of Executone equipment was provided to
TFM at the request of Fidelity. A for-
mal proposal to utilize the Executone
system was then transmitted to the Govern-
ment by Fidelity and was received and
approved on September 1, 1972. The
specifications for the nurse call system
were modified by the contracting officer
28
on September 6, 1972 (modification No.
51) to somewhat expand the system and en-
large its capacity and capabilities. The
modification noted that "The system sub-
mitted and conditionally approves is
manufactured by Executone." By modi-
fication No. 51, the hospital contract
price was increased by $225,000, subject
to final adjustment.
On December 4, 1973, Fidelity sub-
mitted a claim to TFM to forward to the
contracting officer on the Fort Gordon
hospital contract. Fidelity's claim
stated, in part, as follows:
Fidelity Sound, Inc. (here-
inafter referred to as Claimant)
presents this claim for additional
cost and expenses on the Fort
Gordon Hospital DACA-21-71-C-
0061 (hereinafter referred to as
Project) due to the inter-
pretation and ambiguity of the
specifications resulted in the
proprietary demand for an Executone
system when the specifications
were actually open specifications.
* * * * * * * * *
29
COST DIFFERENTIAL $128,000.00
(1) Warranty Work 12,000.00
{2) Supervision 3,000.00
(3) Salary and Travel
Expenses 31,000.00
(4) Fifteen (15) Months'.
interest on $25,000
at 11.5 % interest
From the day that the
approving authority has forced the
Executone System on Fidelity
Sound, Inc., Fidelity Sound, Inc.
has suffered a net expense of
$177,693.00. Therefore, in
addition to this sum, we are re-
questing the following:
Net Expense $177,693.00
Ten (10%) Percent
Overhead 17,769.00
“$194,862.00
Profit 19,486.00
a .
Cost of Interest on
$194,867.00 [sic] to date
at 11.5% interest
“$236,757.00 : th
* * * * * * *
30
By letter dated September 16, 1974
to the United States Corps of Engineers,
Fidelity amended its claim to $570,030.2/
*
1/ The amended claim consisted of
the following items: $141,440 (total
material cost); $88,853 (total labor
cost); $34,543 (supervision and en-
gineering - 15 percent of labor and
materials); $34,543 (sales expense and
miscellaneous - 15 percent of labor and
materials); $55,270 (general and admini-
strative - 24 percent of labor and
materials); $129,534 (claim expense -
interest of $46,639, executive salary
and travel of $31,000, legal expenses
of $35,000 and general and admini-
strative expense of $16,895 or 15 per-
cent of the total for interest,
executive salary and travel and legal
expense); $48,418 (profit at 10 per-
cent of the total job cost of $484,183);
$37,429 (unilaterial change order).
31
The claim was denied by the contracting
officer and an appeal No. 19823, was
taken to the ASBCA pursuant to the dis-
putes clause in the contract. The pro-
ceedings in Appeal No. 19823 were
limited to the issue of entitlement.
On July 26, 1976 the ASBCA issued
its decision ruling, in relevant part,
as follows:
The Government, of course,
has long-recognized right to in-
sist on the product conforming
to the bid specifications under
contract. But the requirement
for a standard product created
the subtle suggestion of the
commercial availability of a
complying system. It was that
fact coupled with the Govern-
ment's application of its view
of the standard of quality it
thought had been called out
that forced the appellant to
greater expense than it reason-
ably anticipated. Thus, in
applying its criteria of
acceptability the Government
constructively chdnged the
specifications for which the
appellant is entitled to an
equitable adjustment.
32
Following this ASBCA determination
on entitlement, a revised claim of
$2,963,325.83 was submitted by letter
dated February l, 1977.2/ At the request
2 The letter set forth the claim
as follows:
Material - Exhibit A $128,094.48
Labor - Exhibit B 58,973.66
Total Excess Material
& Labor $187,068.14
Associated Charges on Direct
Excess Costs
Supervision - 15% of
Material & Labor $ 28,060.22
Eng. & Estimating -
15% of M& L 28,060.22
Job Coordination -
5% of M&L 9,353.41
$ 65,473.85
(Note: All percentage charged
as previously approved
on change orders.)
33
2/ Cont'd
General & Administrative -
15% of M& L $ 28,060.22
(See Exhibit C)
Extraordinary Costs (See
Exhibit D) $ 98,847.00
Interest Expense (as of 11/30/76)
(See Exhibit E) Per Diem
Interest Cost - $211.17
$236,942.12
TOTAL EXCESS COSTS $616,391.32
Porfit - 10% 61,639.13
Sub-Total $678,030.45
Extraordinary Damages
11/1/73 - 10/31/76
(See Exhibit E) $1,544,714.00
TOTAL COST TO COMPANY $2,222,744.40
Claim Legal Fees 740,581.43
TOTAL CLAIM $2,963,325.83
34
of the Corps of Engineers, the Defense
Contract Audit Agency (DCAA) audited
Fidelity's records and submitted a report
on March 9, 1977, which was made avail-
able to Fidelity. Protracted negoti-
ations did not produce an agreement as
to the amount of the adjustment and on
July 14, 1977 the contracting officer
issued a decision that $228,867 was the
appropriate amount. Again, an appeal
(No. 22337) was taken to the ASBCA.
In the proceedings before the
ASBCA, the appellant presented the
testimony of:
Marvin Pearlman, a Certified Public
Accountant who served as the comptroller
for Fidelity; Frederick J. Fink, an
officer of Fidelity; Charles Byrom, an
officer of Fidelity; and Ronald L. Fine,
an officer of, and major shareholder in
Fidelity.
35
The Government's witnesses before
the ASBCA were:
Gilbert Gechman, a DCAA auditor;
Robert E. Utermark, the representative
of the contracting officer for electrical
matters; Robert A. Rowe, resident
engineer for the Corps of Engineers on
the Fort Gordon hospital project;
Charles A. Baldwin, an electrical
inspector for the Corps of Engineers on
the Fort Gordon hospital project,
Forest H. Cain, vice president, Righton
Distribution Co.; Charles Brown, DCAA
regional supervisory auditor; and
Matthew D. Thomas, assistant district
counsel, Corps of Engineers.
By an opinion issued October 27,
1978, the ASBCA determined that the
appellant was entitled to an equitable
adjustment of $234,536.26 on the nurse
call claim as follows:
36
Material
Claimed 128,094.48
Denied 9,488.48
Sustained 118,606.00
Labor
Claimed 58,973.66
Denied 58,548.66
Sustained 425.00
Total Excess Labor &
Materials
Claimed 187,068.14
Denied 68,037.14
Sustained 119,031.00
Overhead
Claimed 93,514.07
Denied 39,569.22
Sustained 53,944.85
Extraordinary Costs
Claimed 98,847.00
Denied 98,847.00
Sustained 0
Interest Expense (through 10/31)
Claimed 354,727.00
Denied 354,727.00
Sustained 0
Total Excess Costs
Claimed 734,156.21
Denied 561,180.36
Sustained 172,975.85
37
Profit at 10%
Claimed 73,415.62
Denied 56,118.03
Sustained 17,297.59
Subtotal
Claimed 807,571.83
Denied 617,298.03
Sustained 190,273.44
Extraordinary damages
Claimed 1,544,714.00
Denied 1,544,714.00
Sustained 0
Total Cost to Company
Claimed 2,325,285.83
Denied 2,162,012.39
Sustained 190,273.44
Legal Fees
Claimed 740,581.43
Denied 740,581.43
Sustained tics
TOTAL CLAIM
Claimed 3,092,867.26
Denied 2,902,593.82
Sustained 190,273.44
Sales Tas TFM 3,558.18
, .
1/TFM Profit & Over-
head at 10% 19,383.16
’ .
1/3.W.Bateson Profit
& Overhead at 15.5% 21,321.48
334,536.26
38
Previously paid by Government on
Modification P 149 (Parts I & ITI)
228,867.00
/
AMOUNT DUE J. W. BATESON
AND SUBCONTRACTORS 5,669.26
3/ As to the $5,669.26, the sum
which remainded to be paid in addition
to the $228,867 which had been
previously paid by the Government
on the basis of the contracting
officer's decision, the ASBCA con-
cluded that Fidelity's share was
$904.05, TFM's share was $4,004.40
and J. W. Bateson's shares was $760.81.
TFM's share included $3,558.18 in
sales tax expense.
39
On March 8, 1979, plaintiff filed
its petition in this matter, setting
forth a claim against the United States
for $3,600,404.51 as of April 21, 1979,
plus $211.17 per day thereafter until
payment. Plaintiff's petition sought
review of the ASBCA's determinations:
(1) concerning the number of labor hours
for the installation of the equipment;
(2) denying recovery for delay asserted
to be caused by the denial of six sub-
mittals by Fidelity; (3) denying the
interest cost claimed; and (4) denying
the extraordinary cost damages claimed.
Plaintiff's petition also alleges
that:
The amount due to the
Plaintiff was caused by the in-
tentional, arbitrary, and
capricious breach of the contract
in question, causing delays to
plaintiff, through Fidelity,
and resulting in adverse effects
on Fidelity's ability to finance
this contract and other contracts
40
both with defendant and
commercial entities.
Defendant's answer, filed June 6,
1979, set forth the Government's
position that the ASBCA decisions in
Appeals Nos.19823 and 22337 are final
under the judicial review standards as
set forth in the Wunderlich Act, 41
U.S.C. §§ 321, 322.
Plaintiff's motion for summary
judgment, filed August 7, 1979, seeks
judicial review of several of the
determinations made by the ASBCA in
Appeal No. 22337.4/ In its opposition
4/ Plaintiff addresses argument in the
motion only to the ASBCA's determi-
nations:
(1) that the applicable burden rate
was 45.32 percent;
(2) that the use of electricians,
at a higher rate of pay, was not required
in the installation of the nurse call
system;
(3) that 100 hours of excess labor
time was required;
(4) that no amount for additional
time and travel for Fidelity executives
was established.
41
to defendant's cross-motion for summary
judgment filed January 2, 1980, plain-
tiff adds argument in support of the
remaining items of tis claims denied
by the ASBCA and/or seeks a de novo
trial by asserting that the additional
damages claimed are premised upon a
breach of contract asserted to have been
committed by the Government in rejecting
Fidelity's submittals of nurse call
systems prior to the approval of the
Executone equipment on September l,
1972. Plaintiff argues that the
rejections of the submittals made by
Fidelity, other than that for the
Executone system, were made in bad
faith by the contracting officer's re-
presentative for electrical matters, and
that the requirement to install the
Executone system constituted a cardinal
change, one outside of the scope of the
contract. 42
Defendant opposes plaintiff's
assertion of a breach of contract claim
in an opposition brief as not sub-
mitted in accordance with the Rules but
also argues that no valid assertion as
to the existence of a cardinal change
has been made.
It is concluded that plaintiff has
not established any basis upon which it
could be rules that a cardinal change
claims has been asserted in this matter
calling for de novo proceedings in this
court. 2/ The ASBCA has ruled that
5/ Plaintiff's failure to raise the
issue of cardinal change before the ASBCA
could preclude its inital assertion in
plaintiff's opposition brief, filed
January 2, 1980. Conrac Corp. v.
United States, 214 Ct.¢Cl. sor 558 F.2d
957 (1577). However, in view of the
conclusion that a situation within the
cardinal change doctrine has not been
set forth either before the ASBCA or in
the papers filed herein, there exists
no need to rule on this point.
43
plaintiff is entitled to an equitable
adjustment under the contract involved
covering any increased costs reasonably
incurred as a result of the criteria of
acceptability applied by the Government
with respect to the nurse call system
submittals. A "cardinal change" occurs
when the Government effects an altera-
tion in the work so drastic that it
effectively requires the contractor to
perform duties materially different from
those originally bargained for.
Edward R. Marden Corp. v. United States,
194 Ct. Cl. 799, 442 F.2d 364 (1971).
The contract, as bid, specified a nurse
call system and plaintiff, through
Fidelity, installed a nurse call system,
albeit not using the brand of equipment
it originally intended to supply. This
circumstance does not fit the description
of a cardinal change. See Aragona
44
Constr. Co. v. United States, 165 Ct. Cl.
382, 390-91 (1964). If a contractor is
incorrectly required to install some
brand name equipment when other equip-
ment equal thereto would have met the
specifications, this court has recognized
that appropriate relief is provided by
an equitable adjustment under the
changes clause utilized in Government
contracts. Jack Stone Co. v. United
States, 170 Ct. Cl. 281, 344 F.2d 370
(1965).
Plaintiff's assertion of "bad
faith" in connection with the rejection
of equipment other than Executone's
nurse call system in no way demonstrates
"bad faith" directed at Fidelity. If
the asserted bad faith. existed, perhaps
other manufacturers of nurse call
equipment would have grounds to complain,
but Fidelity was not such a manufacturer.
45 .
Plaintiff has alleged no specific
instance of malicious intent or "animus"
directed against Fidelity on the part of
the Government. ;
In this circumstance, general "bad
faith" allegations concerning an asserted
preference for one brand of equipment
do not create a triable issue of fact
such as to convert this matter into a
de novo action for breach of contract.
Kalver Corp. v. United States, 211 Ct.
Cl. 192, 543 F.2d 1298 (1976), cert.
denied, 434 U.S. 830 (1977).
Accordingly, the issue which must
be resolved is limited to whether the
decision of the ASBCA in Appeal No.
22337 is final under the judisical
review standards of the Wunderlich Act,
41 U.S.C. §§ 321, 322.
The changes clause in the contract
for the Fort Gordon Hospital project
provides: 46
* * * * * *
(d) If any change under this
clause causes an increase or
decrease in the contractor's
cost of, or the time required
for, the performance of any
part of the work under this
contract, whether or not changed
by any order, an equitable adjust-
ment shall be made and the
contract modified in writing
accordingly: * * * And provided
further, that in the case of
efective specifications for
which the Government is
responsible, the equitable
adjustment shall include any
increased cost reasonably in-
curred by the contractor in
attempting to comply with such
defective specifications.
The determination of the amount of an
equitable adjustment by a contract
appeals board is generally one of fact,
subject to limited review by this court.
United States v. Callahan Walker Constr.
Co., 317 U.S. 56, 61 (1942); Koppers Co.
v. United States, 186 Ct. Cl. 142, 405
F.2d 554 (1968). The purpose of the
changes provision is to compensate a
47
contractor for the unanticipated and
extra out-of-pocket expenses it incurred
in performing the contract as a result
of a change. Coley Properties Corp. v.
United States, 219 Ct. Cl. , 593 F.2d
380 (1979); Bruce Constr. Corp. v.
United States, 163 Ct. Cl. 97, 100,
324 F.2d 516, 518 (1963). The equitable
adjustment may not properly be used as
an excuse to remedy a loss suffered by a
contractor who has simply underestimated
an item in his bid. S. N. Nielsen Co. v.
United States, 141 Ct. Cl. 793, 796-97
(1958). However, an equitable adjust-
ment must include reimbursement for
those increased costs of performance
which were the direct and necessary
result of the change. Paul Hardeman,
Inc. v. United States, 186 Ct. Cl. 743,
406 F.2d 1357 (1969). When a dispute
arises as to the amount of an equitable
48
adjustment, the party seeking the con-
tract price adjustment has the burden,
before the contract appeals board, of
establishing the existence of the
relevant costs by a preponderance of the
evidence. Teledyne McCormick-Selph v.
United States, 218 Ct. Cl. __, 588 F.2d
808 (1978).
Viewed in accordance with the
principles stated, it is concluded that
the ASBCA's decision in Appeal No. 22337
is final and plaintiff has not establish-
ed any valid basis upon which the deter-
mination could be overturned.
Plaintiff first takes exception
to the finding by the ASBCA that a
burden rate (overhead) of 45.32 percent
should be applied in determining
Fidelity's performance cost. Plaintiff
assets that a determination of 50 percent
should have been made. The record before
49
the ASBCA demonstrates that the 45.32
percent rate is supported by substantial
evidence consisting of the audit con-
ducted by the DCAA and the testimony of
the auditor. No basis has been shown
to overturn the Board's findings.
Plaintiff takes exception to the
decision by the ASBCA that electricians
were not required to install the
Executone equipment such that a portion
of the labor cost Fidelity actually in-
curred in the performance of this work
was not reasonable. The evidence before
the ASBCA established that Fidelity
used a labor rate of $4.25 per hour in
its original bid to TFM when it con-
templated installing the Altec-Lansing
nurse call system. Fidelity had con-
templated installing the system using
technicians who were members of the
50
Communications Workers of Amercia. In
the actual performance of the contract
work, Fidelity arranged for TFM to
provide the labor used to install the
nurse call system, which labor costs
was then billed to Pidelity at the $9.65
hourly rate established for electricians
who were members of the union utilized
by TFM. The beat Senay before the ASBCA
was in conflict as to whether the use
of union electricians at the rate of
$9.65 was caused by increased complexity
of the Executone equipment as compared
to that manufactured by Altec-Lansing,
or whether it was simply necessary to
use electricians from TFM's union
source on this contract such that
Fidelity's original bid estimated was
in error. The Board concluded that
Fidelity did not establish that the use
of union electricians was caused by the
51
actions of the Government in the
approval of the Executone equipment so
that the increase in hourly labor cost
over Fidelity's bid estimate was no
recoverable as a part of the equitable
adjustment. A review of the record
evidence demonstrates that the Board's
finding has adequate record support.
Normally, actual increased costs in-
curred would control. Ford Constr. Co.
v. United States, 202 Ct. Cl. 1133
(1973). However, in the circumstances
where an original bid estimate was in
error, increased cost which occurs as
a result may not be reimbursed by means
of an equitable adjustment. Pacific
Architects and Engineers, Inc. v. United
States, 203 Ct. Cl. 499, 491 F.2d 734
(1974). As plaintiff did not establish
before the ASBCA that the switch to
TFM's union electricians was caused by
52
any Government action, no grounds exist
to overturn the Board's decision denying
recovery of the increased labor cost.
Plaintiff also takes exception to
the findings by the ASBCA, in the nature
of a jury verdict, that 100 extra hours
were expended as a result of the change
at issue. The testimony as to the amount
of extra labor required as a result of
the change was in conflict. Plaintiff
presented only a "total cost" approach,
which the ASBCA rejected because the
amount of excess labor could be deter-
mined by other methods and the total
cost approach did not pinpoint the extra
labor hours attributable to the change
as contrasted with other causes, such
as the alterations made under Modi-
fication 51. The Board's rejection of
plaintiff's total cost method in these
circumstances was correct. Boyajian v.
53
United States, 191 Ct. Cl. 233, 423
F.2d 1231 (1970). Rather than denying
any recovery as to labor cost for
failure of proof, a result which would
have been possible, Joseph Pickard's
Sons Co. v. United States, 209 Ct. Cl.
643, 532 F.2d 739 (1976), the ASBCA
utilized a jury verdict approach to find
that 100 hours of extra labor were
attributable to the change at issue.
This determination is supported by the
testimony of an expert witness for the
Government, although his opinion was that
some 50 to 70 hours of extra labor were
incurred, ©/ and no basis has been shown
6/ Another witness for the Govern-
ment compiled unsubstantiated figures
cited during the trial of this matter
before the Board and then testifed to a
figure of 779 hours of extra labor. The
ASBCA discounted this evidence and this
result is within the province of the
facts on a dispute arising under the
contract.
54
on which the Board's finding on excess
labor hours could be overturned upon
judicial review.
Plaintiff next takes exception to
the ASBCA's findings that no amount of
additional cost was established for the
work time and travel expended by execu-
tives of Fidelity as allocated to the
change at issue. Plaintiff's testimony
was that a certain percentage of execu-
time officer time would normally be
expended on the contract but, because
of the problems on the instance contract,
a substantially greater percentage of
such time was involved. No records or
documentary evidence were introduced
before the Board to support the general
testimony as to the time and travel
expense allocations claimed. The ASBCA
rules that it had no credible evidence
on which to establish a dollar amount as
55
to any additional executive time and
travel attributable to the change at
issue. Upon judicial review, absent
contradictory uncontrovertible docu-
mentary evidence or physical fact, this
court normally defers to the judgment
of the Boards of Contract Appeals on the
credibility of witnesses who have testi-
fied before them. Sternberger v. United
States, 185 Ct. Cl. 528, 401 F.2d 1012
(1968). In the instant situation where
additional overhead of $53,944.85 has’
been awarded for the change (excluding
the overhead and profit amounts of
$19,383.16 for TFM and $21,321.48 for
J. W. Bateson), and additional sums to
be allocated to the change from amounts
expended for corporate officers' salaries
and travel should have been supported by
evidence the ASBCA could deem creditable.
56
No basis has been shown to overturn the
decision of the ASBCA rejecting this
aspect of plaintiff's claim. //
Before the ASBCA, plaintiff's claim
for interest costs, extraordinary damages
and attorneys fees were also denied. In
the motion for summary judgment filed
August 7, 1979, plaintiff does not take
specific exceptions to the ASBCA's deter-
minations in this respect. In the
opposition brief filed January 2, 1980,
plaintiff appears to argue that its
Claims for additional allocations of
7/ As to plaintiff's general
assertion that “delay” must have in-
creased its costs, such as executive
time and travel, no specific delay costs
were claimed before the ASBCA and, more
importantly, because the building had to
be built before the nurse call system
could be installed, no showing was made
before the ASBCA that the installation
work was in any way delayed by reason of
the several submittals of equipment which
were rejected prior to the approval of
the Executone system.
57
executive salaries and travel cost,
interest, extraordinary damages, and
attorneys fees are now asserted as a
part of its cardinal change or breach
of contract claim for which a de novo
trial is sought. Given the conclusion
reached, supra, that no valid breach of
contract claims has been asserted in
this matter, and plaintiff's failure to
contest the rejection of these claims by
the ASBCA, no further discussion as to
these items may be required. However,
in the event that the discussion in
plaintiff's opposition brief is also in-
tended to be addressed to the admini-
strative rejection of these claims, it
is concluded that this rejection must be
sustained.
With respect to the denial of
claimed interest costs, the ASBCA
correctly relied upon the applicable
58
regulation that interest on borrowings
was unallowable in the determination of
the equitable adjustment required. See
Coley Properties Corp. v. United States,
219 Ct. Cl. __, 593, F.2d 380 (1979).
Plaintiff's claim for extraordinary
damages of some $1,500,000 is basically
a “lost profits" claim premised upon
numerous bids Fidelity submitted for
other contracts during the period in-
volved. As such, this lost income claim
in no way consists of out-of-pocket
expenses directly related to the
performance of the nurse call system
contract which can appropriately be
reimbursed as a part of an equitable ad-
justment. Coley Properties Corp. v.
United States, supra. Moreover, beyond
the concept of an equitable adjustment,
damages for lost of future business
prospects are usually considered too
59
remote to be recovered in a breach of
contract suit. See William Green Constr.
Co. v. United States, 201 Ct. Cl. 616,
477 F.2d 930 (1973), cert. denied, 417
U. S. 909 (1974).
As to attorney fees, the record
before the ASBCA makes it clear that the
sums“sought were for prosecution of the
instance claim against the United States
and as such, they may not be recovered
as a part of an equitable adjustment.
Singer Co., Librascope Div. v. United
States, 215 Ct. Cl. 281, 325-28, 568
F.2d 695, 720-71 (1977); 28 U.S.C.
§2412 (1970).
CONCLUSION
As it is concluded that the ASBCA
decision awarding plaintiff an equit-
able adjustment of $234,536.26 is en-
titled to finality under,the judicial
review standards of 41 U.S.C. §§ 321,322,
60
it is recommended that defendant's
motion for summary judgment be granted,
plaintiff's motion for summary judgment
be denied, and plaintiff's petition be
dismissed.
61
IN THE UNITED STATES COURT OF CLAIMS
NO. 86-79C
J. W. BATESON, INC.
V.
THE UNITED STATES
Before FRIEDMAN, Chief Judge, DAVID and
KUNZIG, Judges.
ORDER
This case comes before the court on
plaintiff's motion, filed December 24,
1980, for rehearing pursuant to Rule 151
(b) with reference to the order entered
on December 12, 1980, dismissing the
petition. Upon consideration thereof,
together with the response in opposition
thereto, without oral argument.
IT IS ORDERED that plaintiff's said
motion for rehearing is denied.
FEB 6-1981 — BY THE COURT
S/Daniel M. Friedman
Chief Judge
62
SUPREME COURT OF THE UNITED STATES
NO. A-881
J. W. BATESON, INC.,
Petitioner
v.
UNITED STATES
ORDER EXTENDING TIME TO FILE PETITION FOR
WRIT OF CERTIORARI
UPON CONSIDERATION of the application of
counsel for petitioner. IT IS ORDERED
that the time for filing a petition for
writ of certiorari in the above-entitled
cause be, and the same is hereby,
extended to and including June 6, 1981.
/s/ Warren E. Burger
Chief Justice of the
United States
Dated this 30th day of
April, 1981.
63
CERTIFICATE OF SERVICE
This is to certify that I have,
prior to filing, served three copies
of the within and foregoing Petition
for Writ of Certiorari, on the Solicitor
General, Justice Department, Washington,
D. C. 20530, by depositing conformed
copies of same in the United States
Mail, with the proper postage affixed
thereto.
~h
This the day of June, 1981.
Attorney for Petitioner
64
This is a copy of a public record, reproduced as it was published. It is not legal advice, and it may not be the version a court would rely on. Check the official source before you cite it.