Petition — Baltimore County v. Raymond International Builders, Inc.
Supreme Court brief1980
Ask Donna
What actually matters in this document.
Text
oo } |. Supreme Court, U.S.
FILED
80-512 SEP 30 1980
tea RODAK, JR., CLERK
NO.
IN THE
Supreme Court of the United States
OCTOBER TERM, 1980
BALTIMORE COUNTY, MARYLAND,
Petitioner,
Vv.
RAYMOND INTERNATIONAL BUILDERS, INC.,
and
J. E. GREINER, INC.,
Respondents.
PETITION FOR WRIT OF CERTIORARI TO THE
COURT OF SPECIAL APPEALS OF MARYLAND
LEONARD S. JACOBSON,
HARRY S. SHAPIRO
Baltimore County,
Office of Law,
Court House
Towson, Maryland 21204
(301) 494-3 146 :
Attorneys for Petitioner
———————————S—_ ———————————————————_—_
THE PAUL M. HARROD COMPANY, BALTIMORE, MARYLAND 21234
i
To the Honorable, the Chief Justice and Associate Justices
of the Supreme Court of the United States:
Baltimore County, Maryland, the Petitioner prays that a
Writ of Certiorari be issued to review the judgment of the Court
of Special Appeals of Maryland entered in the above-entitlted
case on April 11, 1980, and the order dated July 3, 1980, of
the Court of Appeals of Maryland which denied a Petition for
Writ of Certiorari relating to said case.
QUESTIONS PRESENTED
1. Was the Court of Special Appeals correct when it
held thai, following Hollerbach v. United States, 233 U.S. 165
(1914), Baltimore County was liable to a contractor for cost
overruns on a bridge repair contract, where the contractor
allegedly relied on data provided by the county, even though
the contractor was warned the data was forty years old and
should not be relied upon?
2. Was the Court of Special Appeals correct when it
remanded the case to the trial court for damages alone, and
against the Petitioner alone, when the Respondent, J. E. Greiner,
Inc., was also an original Defendant and had prepared the
contract documents upon which the allegations of misrepre-
sentations had been made?
3. Did the failure on the part of the State Court to
apply your Petitioner’s defenses of sovereign immunity and the
statute of limitations deprive your Petitioner of its rights of due
process under the Constitution of the United States?
PARTIES
The Petitioner herein, Baltimore County, Maryland, was
a Defendant before the Trial Court, and was an Appellee before
ii
the Court of Special Appeals of Maryland. The Respondent
herein, Raymond International Builders, Inc., was the Plaintiff
before the Trial Court, and was the Appellant before the Court
of Special Appeals. The Respondent herein, J. E. Greiner,
Inc., was a Defendant before the Trial Court in the action
brought by Raymond International Builders, Inc., and was a
Cross-Defendant in the Trial Court proceedings in a Cross-
Claim filed against such party by Baltimore County, Maryland,
before the Trial Court.
TABLE OF CONTENTS
Page
ob yy es ne Pore re ey sere i
PUNE <vsa - Kean Coun ¥ scene Ukecks eee reese Rees i
Bo gS er er rere rer er er Ts |
| ESTEE UTR CURR TTL ROPER LTT 2
CONSTITUTIONAL PROVISIONS AND STATUTES....... 3
SEAR TE TIE FEE WON 66 65h S Ra ee Ned FOS SS eed 4
REASONS FOR GRANTING THE WRIT................. 7
COE oct cous ese eh ewan beeen et obeeeeGeren 14
TABLE OF CITATIONS
Cases
Accord, Alpert v. Commonwealth,
250 Fi de Fae COs BOTs ooo 6 eens Dab erens a
Accord, Dravo Corp. v. Municipality of Metropolitan
Seattle, 79 Wash. 2d 214, 494 P.2d 399
Ca OE es STs ate eid on ie eek babes dates 10
Archie and Allen Spiers, Inc. v. United States,
296 F 26 Ta? Cott OE Com, PIED oc cc cc ces oes 8
Branna Construction Corp. v. West Allegheny
Joint School Authority, 430 Pa. 214,
DES A280 DO Oe is CE hh ewes 6 dceeass 9,10
ry
iv
Page
Condun-Cunningham, Inc. v. Day, 258 N.E.2d 264
(Ct. of Common Pleas of Ohio,
Ce ME Sve ce dees escbesionses 11
Detroit and I. R. Co. v. Guthrie,
pea ey 8 eS "re eee 10
Elkan v. Sebastian Bridge District,
BO oe bg vik dk oo desde ewasees 9
Gevyn Construction Corp. v. United States,
og Re ge | | Se 1]
Hollerbach v. United States,
ae ae Pe Es weeseeceecces i,2,6,7,8,9,10,11,13
MacArthur Brothers Co. v. United States,
oe le il 6 wd wi aé'b'g 0 kb o.o 0 66 « asia 7
Robert E. McKee, Inc. v. City of Atlanta,
rr PT CEs BP oe Site cue eecn sve’ 9
Penn Central Transportation Co. v. United States,
as, CRUE I BOT ED 65.5 c's Se cee dlecde ween 11
Pitt Construction Co. v. City of Alliance,
Re ee a es BOD, bn ob ok oe hoe sc acaewee ee 10
Transbay Construction Co. v. City and County
of San Francisco,
Pe es Te Crees COE, BOOED cc ccc chs ceecccews 10
Wunderlich v. State, 56 Cal. Rptr. 473,
ff Ta gk oy) 10
Constitutiv::<! Provisions and Statutes
Annotated Code of Maryland, Article 25A, Section 1A ... 3,13
Constitution of the United States,
Fourteenth Amendment................... 2,3,12,13
INDEX TO APPENDIX
Appendix A—Opinion of the Court of
Special Appeals of Maryland.............sceee0. A. 1
NO.
IN THE
Supreme Court of the United States
OCTOBER TERM, 1980
BALTIMORE COUNTY, MARYLAND,
Petitioner,
v.
RAYMOND INTERNATIONAL BUILDERS, INC.,
and
J. E. GREINER, INC.,
Respondents.
PETITION FOR WRIT OF CERTIORARI TO THE
COURT OF SPECIAL APPEALS OF MARYLAND
OPINIONS BELOW
The opinion of the Court of Special Appeals of Maryland
whose judgment is herein sought to be reviewed is reported at
412 A.2d 1296. By its order dated July 3, 1980, the Court of
Appeals of Maryland denied Petitioner’s Petition for Writ of
Certiorari.
2
JURISDICTION
The jurisdiction of this Court is invoked pursuant to 28
U.S.C., Section 1257, as the Petitioner herein is alleging that its
rights and privileges under the Fourteenth Amendment to the
Constitution have been violated by the State Court decision.
Additionally, the principal issue in the case relates to the State
Court construction and application under the Supreme Court
of the United States case of Hollerbach v. United States, 233
U. S. 165 (1914), and your Petitioner is alleging that the State
Court erroneously construed and applied such 1914 case and
overlooked a more recent Supreme Court and other federal
decisions relating to the issue in Hollerbach. Under Rule 19
of the Rules of the Supreme Court, the Supreme Court may
consider the application of the decisions of the Supreme Court
in order to clarify in a uniform way such application. Addition-
ally, under Rule 20 of the Rules of the Supreme Court, the
Supreme Court may give consideration to the imperative public
importance of the matter, and the Petitioner is alleging that the
application by the State Court in the case at bar could detri-
mentally affect municipal and state contracts throughout the
United States contrary to the public interest and not in accord-
ance with the current view of the Supreme Court of the United
States.
Although the element of damages in this case was remanded
to the trial court for further consideration as to the Respond-
ent, Raymond International Builders, Inc., the case was fully
and finally determined as to the Respondent, J. E. Greiner,
Inc. Additionally, the case was fully and finally determined
as to the defenses of sovereign immunity and statute of limita-
tions raised by the Petitioner.
Therefore, it is the Petitioner’s belief that this case is in
a posture of finality for review by this Honorable Court with
reference to some or all of the issues.
3
CONSTITUTIONAL PROVISIONS AND STATUTES
Fourteenth Amendment to the Constitution of the United
States:
“All persons born or naturalized in the United States
and subject to the jurisdiction thereof, are citizens of
the United States and of the State wherein they
reside. No State shall make or enforce any law which
shall abridge the privileges or immunities of citizens
of the United States; nor shall any State deprive any
person of life, liberty, or property, without due
process of law; nor deny to any person within its
jurisdiction the equal protection of the laws.”
Article 25A, Section 1A of the Annotated Code of Maryland
“Article 25A—Chartered Counties of Maryland 1A.
(A) Unless otherwise specifically provided by the
laws of Maryland, a chartered county, and every
officer, department, agency, board, commission or
other unit of county government may not raise the
defense of sovereign immunity in the courts of this
state in an action in contract based upon a written
contract executed on behalf of the county, or its
department, agency, board commission, or unit by
an official or employee acting within the scope of
his authority... .
SECTION 7. AND BEIT FURTHER ENACTED,
That this Act shall take effect July 1, 1976.
Approved May 4, 1976.”
4
STATEMENT OF THE CASE
On July 17, 1972, the Respondent, Raymond International,
Inc. (hereinafter referred to as “Raymond”) and Petitioner,
Baltimore County, Maryland, entered into a written contract
relating to underwater repairs to the Wise Avenue Bridge in
Baltimore County. The bridge was in excess of forty years old.
The contract documents in this case were made up of
various documents which included an invitation to bid, speci-
fications, proposal, agreement, special provisions and various
documents. Section 5 of the Special Provisions states:
“Original construction data has not been verified by
actual field measurements and the conditions observed
during the underwater inspections and tests may have
changed since the date on which furnished to the con-
tractor for general information purposes only and do
not purport to represent existing field conditions. It
shall be the contractor’s sole responsibility to verify
by actual field measurements, inspections and tests
and data which may be of significance to him in tz
preparation of his bid.”
The contract document specifically states that “Special
Provisions shall govern over specifications, supplemental speci-
fications and plans.” In addition the invitation to bid states at
page 1-03 that:
“Bidders must examine the drawings and specifica-
tions carefully and must make a personal examination
of the location and nature of the proposed work.”
Sheet “X” of the contract documents states in the notes:
5
“Note 2—contractor to verify all dimensions in field.
Note 5—dimensions shown taken from as built plans
and have not been verified by actual measurement.
The contractor shall verify any and all dimensions as
may be required to complete satisfactorily all work
under this contract.”
The Proposal, which is a part of the contract, clearly states
that:
“The undersigned hereby declare that they have care-
fully examined the Form of Contract Specifications,
Special Provisions and Drawings forming a part of the
same and have their satisfaction examined the locality
of the proposed work... .”
Substantial testimony was produced at trial showing that
Raymond could have determined the underwater conditions,
prior to its submitting its bid for the repair job, through the use
of soundings, observations and underwater probes. Raymond
should have foreseen the underwater conditions which existed
because of the age of the bridge (over forty years old) and the
repeated statements in the plans and specifications that the
drawings and measurements were original construction data
and had not been verified. The contract had clear and unam-
biguous statements to the effect that the data was old, was
given for general information purposes only and did not purport
to represent existing field conditions. In addition the contract
stated that it was Raymond’s responsibility to verify any data
which might be of significance in the preparation of its bid.
The original contract price for the repair job was $213,000.
Immediately after the contract was awarded to them, Raymond
decided that it did not have enough profit in the job and
attempted to persuade the county to change the plans and
specifications in order to create more profit. After repairs
6
began, Raymond alleges that it discovered that specifications
provided by the county were inaccurate. The testimony also
revealed that in September of 1972, Raymond was fully aware
of the underwater conditions, and could have taken any legal
action it sought fit to rescind the contract, or other legal
measures that might have been designed to protect any legal
interest it might have had in this matter. However, Raymond
took no such action.
Notwithstanding the fact that Raymond took no action in
September of 1972 or soon thereafter, it later alleged that it
had to perform unforeseeable work at an increase in cost in
excess of one million dollars. Raymond did not institute any
action against Baltimore County until May 26, 1976; more, the
documents clearly stated that the bidder should not rely on the
information given in preparing its bid.
Respondent then institutec an appeal in the Court of
Special Appeals of Maryland. Relying heavily on this Court’s
holding in Hollerbach v. United States, 233 U.S. 165 (1914),
the Court of Special Appeals held that the Trial Court had erred
in holding that the Raymond was not justified in relying upon
the data provided. The Court of Special Appeals further held
that Raymond was entitled to compensation for the unforeseen
or negligently misrepresented conditions which they encountered
in the performance of the contract. However, the Court of
Special Appeals determined that the Respondent, J. E. Greiner,
Inc., the independent contractor who prepared the specifica-
tions for the bid, was not responsible in any way despite the
fact that the proceedings contained a cross-claim brought by
your Petitioner against said Greiner. The Court of Appeals
of Maryland denied, without opinion, Baltimore County’s
Petition for Writ of Certiorari.
7
REASONS FOR GRANTING THE WRIT
Certiorari should be granted in this case because there is
an urgent need for clarification and guidance from the Supreme
Court as to when municipal corporations and states will be
held liable for the accuracy of information provided to pros-
pective bidders and when exculpatory clauses will be upheld.
In Hollerbach v. United States, 233 U.S. 165 (1914), the
Court held that where the government has made a positive
representation upon which the contractor has justifiably relied,
the government will be held liable for increased costs if the
representations prove to be inaccurate. In MacArthur Brothers
Co. v. United States, 258 U.S. 6 (1922), the Court held that
where there has been no positive assertion there can be no
liability.
“To hold the government liable under such circum-
stances would make it an insurer of the uniformity of
all work, and cast upon it responsibility for all of the
conditions which a contractor might encounter, and
make the cost of its projects always an unknown
quantity.” Jd. at 13.
There is a need for the Supreme Court to provide guidance
for the gray area between Hollerbach and MacArthur. In the
sixty-six years since the Court handed down its decision in
Hollerbach, the Courts have differed widely in applying it.
There is great confusion in the federal and state courts as to
when there has been a positive assertion upon which the con-
tractor is justified in relying. Some courts have even used
Hollerbach to hold the government absolutely liable for infor-
mation provided to contractor, even where the contractor has
clearly been warned that the data may be inaccurate and should
not be relied upon. Raymond International, Inc. v. Baltimore
County is a good example of such an erroneous application of
F*
8
Hollerbach. Raymond was clearly warned that the information
provided to it was from original construction drawings, which
were more than forty years old, and that data should not be
relied upon unless the contractor verified it for itseif. The
Court of Special Appeals of Maryland held that following
Hollerbach the Court was liable when the information allegedly
proved to be inaccurate. The Court of Special Appeals of Mary-
land and other courts have effectively interpreted Hollerbach as
holding governments absolutely liable for information provided
to contractors. Clearly the Court did not intend this to be the
effect of its decisions in Hollerbach and MacArthur.
The confusion existing in the federal and state courts can
be clearly seen by examining cases where the fact situations
were similar but the court’s decisions were vastly different. In
Archie and Allen Spiers, Inc. v. United States, 296 F.2d 757
(Court of Claims, 1961), the court was faced with a situation
similar to that in Raymond International. The Navy had
requested bids on a contract to refurbish and repair its pipe-
lines on several piers. The proposal contained a clause telling
bidders to
“inspect carefully the work in place and satisfy them-
selves as to the character and amount of work to be
removed, re ewed, or replaced... .”
The contract drawings contained statements that the “contrac-
tor shall verify all dimensions and conditions at the site.” The
contractor failed to verify the data on the drawings before sub-
mitting his bid. The data was inaccurate and the contractor
brought suit for the cost overruns which resulted. The court
held that the government was not liable for the overruns. The
court recognized Hollerbach but held that it did not remove all
cautioning and exculpatory clauses from contracts. The con-
tractor was not justified in relying upon the data supplied by
the government.
9
In Elkan v. Sebastian Bridge District, 291 F. 532 (8th
Cir., 1923), the court held that the government was not liable
where representations made in construction plans were inaccur-
ate. The construction plans for a bridge contained a profile of
test borings from the bridge site. The contract contained a
clause stating that:
“data furnished to bidders. . .are to be considered as
approximate and bidders must assume the risk of
having to carry the foundations to a greater or less
depth without altering their prices.”
The contractor used the government’s data to determine how
much work was required. When the foundations had to be dug
deeper, he filed suit to recover his cost overruns. The court
held that Hollerbach did not require the government to be held
liable under these circumstances.
In Robert E. McKee, Inc. v. City of Atlanta, 414 F. Supp.
957 (N.D.Ga. 1976), the court stated that if a contract clearly
places the risk of uncertainty on one of the parties then that
party must absorb the losses from unexpected conditions. The
court found that following Hollerbach two conditions must be
met to void an exculpatory clause. It must be unrealistic to
expect the bidders to uncover error on their own and the mis-
representation must be material. According to the court, the
state is not liable when it has done little more than represent
the results of an investigation and the bidder knew or should
have known of the factual basis of these representations. The
government does not become an insurer merely by providing
information to contractors.
The federal courts are not alone in holding that Hollerbach
does not require governments to pay cost overruns when they
provide data to a contractor. In Branna Construction Corp. v.
10
West Allegheny Joint School Authority, 430 Pa. 214, 242
A.2d 244 (S.C. of Pa., 1968), the prospective bidders were
provided with test boring information. The contract stated:
“No responsibility is assumed by the owner or archi-
tect for subsurface conditions, such information is
given for guidance only. Bidders shall not rely on
data, bidders shall make their own investigation.”
The Pennsylvania Supreme Court recognized Hollerbach but
‘held that the exculpatory clause was a sufficient manifestation
of the intent of the government that the contractor should not
rely upon subsurface conditions as represented by plans and
specifications. In accord, Dravo Corp. v. Municipality of
Metropolitan Seattle, 79 Wash. 2d 214, 494 P.2d 399 (S.C. of
Wash. 1971); Wunderlich v. State, 56 Cal. Rptr. 473, 423 P.2d
545 (S.C. of Cal., 1967); Detroit and I. R. Co. v. Guthrie, 72
F.2d 126 (6th Cir., 1934).
As stated previously, the courts are not in agreement on
their interpretation and application of Hollerbach. In Pitt
Construction Co. v. City of Alliance, 12 F.2d 28 (6th Cir.,
1926), the contract contained an exculpatory clause to the
effect that the bidders are required to examine the site and
inform themselves of the magnitude of the work involved and
the conditions and difficulties which would be encountered in
performing the work. The depths of existing excavations shown
on blueprints were stated as being ‘‘about.””» The Depths were
inaccurate and the contractor brought suit for his cost overruns.
The court held that the contractor was entitled to accept and
rely upon the data provided by the city government, despite the
exculpatory clause.
In Transbay Construction Co. v. City and County of San
Francisco, 35 F. Supp. 433 (N.D. Cal., 1950), the bid invitation
for a dam construction project stated that the quantities stated
1]
in the contract were estimates only and the bidders were to
make careful, personal examinations of the proposed work.
Citing Hollerbach the court held that where the estimates
proved incorrect the contractor could recover his cost overruns.
The Court of Special Appeals of Maryland is not the only
state court which has followed this line of rasoning. In Condun-
Cunningham, Inc. v. Day, 258 N.E.2d 264 (Ct. of Common
Pleas of Ohio, Cuyahoga County, 1979) the county had made
available to the bidders soil and foundation investigation
reports. The reports stated that they were not part of the con-
struction plans and were merely a source of supplementary
information. The contract also stated that the bidder was
required to examine the site and the contractor warranted that
he had fully investigated the project and was aware of all the
characteristics of the work. The court held that where the
county makes tests results available to a bidder, the bidder is
justified in relying upon the data and the county warrants that
the information is accurate. In accord, Alpert v. Common-
wealth, 258 N.E.2d 755 (Mass., 1970); Penn Central Trans-
portation Co. v. United States, 366 F. Supp. 1161 (Del., 1973);
Gevyn Construction Corp. v. United States, 357 F. Supp.
18 (S.D.N.Y., 1972).
In the sixty-six years since Hollerbach, the size and num-
ber of government construction contracts has increased tre-
mendously, as has the involvement of the federal government
in funding construction projects. The integrity of federal,
state and municipal contracts is in jeopardy unless the Court
makes a clear and definitive statement as to when a govern-
ment will be held liable for information provided to contractors
and when exculpatory clauses will be upheld. If contractors
dealing with state and municipal governments have a free hand
in claims for overruns, the taxpayers shall have to bear the
brunt of the inevitable financial burden. If government cannot
budget expenses for capital improvement projects and make
12
contracts accordingly, the fiscal affairs of our governments will
become chaotic. Raymond International, Inc. v. Baltimore
County presents the Court with a clear opportunity to make a
definitive ruling in this confused and chaotic area.
The proceedings before the Trial Court involved five or
six weeks of testimony and the consideration of numerous
exhibits by the Trial Court. The hearing before the Court of
Special Appeals of Maryland was intended to test the validity
of various legal principles applied to the case at bar by the
Trial Court. However, as indicated by the opinion of the Court
of Special Appeals, the said Appellate Court made numerous
findings of fact without having the benefit of hearing the testi-
mony and examining the exhibits in the light of such testimony.
lt is your Petitioner’s belief that such a factual determina-
tion by said Appellate Court constitutes a violation of the
due process rights of your Petitioner under the Fourteenth
Amendment to the Constitution of the United States. The
determination of said Appellate Court further excluded factual
issues relating to proximate cause and the obligations of the
Respondent, J. E. Greiner, Inc., to your Petitioner in accordance
with contracts between said parties, which contracts were filed
as evidence in the Trial Court. At the very least, your Petitioner
believes and avers that the entire case should have been remanded
to the Trial Court for further proceedings relating to liability
and damages with the legal! direction of the said Appellate Court
relating to the legal principles to be applied by the Trial Court
to the facts and evidence presented.
The failure on the part of the Special Court of Appeals to
remand the entire case to the Trial Court constituted a final
deiermination as to the issue of liability involving your Peti-
tioner and Raymond International Builders, Inc., and involved
a determination as to all issues between your Petitioner and
J. E. Greiner, Inc., which your Petitioner believes to be an
13
erroneous conclusion in the light of the due process rights of
your Petitioner and in the light of an appropriate application
of the Supreme Court cases cited herein.
In addition to the substantial and important issues relating
to Hollerbach and the Fourteenth Amendment to the Constitu-
tion of the United States, this Honorable Court should consider
the defenses of sovereign immunity and the statute of limitations
as presented by your Petitioner in the State Court. The Peti-
tioner believes that the failure to apply such defenses by the
State Court violated the rights of due process of your Petitioner.
Until July 1, 1976, when Article 25A, Section 1A of the
Annotated Code of Maryland was changed, the county had the
benefit of the defense of sovereign immunity in contract actions
(Chapter 450 of the Laws of Maryland, 1976).
The claims of Raymond International in this proceeding
originated prior to July 1, 1976, which made sovereign immun-
ity applicable to the claims asserted against your Petitioner.
When the Court of Special Appeals of Maryland remanded the
proceeding to the Trial Court for damages, it failed to apply
the defenses of sovereign immunity which were legally raised
in the State Court.
With reference to the statute of limitations defenses, the
testimony indicated that Raymond was fully aware of under-
water conditions in September of 1972, but did not file any
action until 1976 which was long after the three-year statute
of limitations applicable had run. Petitioner believes and avers
that the failure of the State Court to apply the defense of
Statute of limitations detrimentally affected the rights of due
process of your Petitioner in the State Court proceeding.
14
CONCLUSION
Wherefore, Petitioner respectfully prays that a Writ of
Certiorari be granted.
Respectfully submitted,
LEONARD S. JACOBSON
County Solicitor
HARRY S. SHAPIRO
Chief Assistant County
Solicitor
Baltimore County Office of Law
Courthouse
Towson, Maryland 21204
Attorneys for Petitioner
A. 1
APPENDIX A
REPORTED
IN THE COURT OF SPECIAL APPEALS OF MARYLAND
No. 714
September Term, 1979
RAYMOND INTERNATIONAL, INC.
v.
BALTIMORE COUNTY, MARYLAND, et al.
Gilbert, C.J.
Thompson
Liss,
JJ.
Opinion by Liss, J.
Filed: April 11, 1980
A. 2
This appeal by appellant, Raymond International, Inc.,
arises out of a judgment rendered in a non-jury trial in the
Circuit Court for Baltimore County in which the presiding judge
ruled that Baltimore County, one of the appellees, was indebted
to the appellant in the amount of $18,431.98. At the same
time, the trial judge entered a verdict for costs in favor of the
remaining appellee, J. E. Greiner, Inc. Appellant filed the
within appeal from these judgments.
By invitation to bid in May of 1972, Baltimore County
solicited bids for underwater repairs to the bascule piers of the
Wise Avenue Bridge over Bear Creek. Bidders were supplied
with plans and specifications prepared for the County by
Greiner. The proposed repairs consisted of the removal of
deteriorated concrete from the bases of the piers and the place-
ment of aggregate concrete in lieu of the deteriorated material.
The bridge was originally built about thirty years ago. It was of
the bascule type with two main piers which encompassed the
channel of the river. The piers were of concrete resting on piles
driven into the river bottom. Their reconstruction was contem-
plated to be accomplished by driving additional piles into the
river bottom and encircling the piling with a cofferdam consist-
ing of interlocking sheet piling driven into the bottom of the
river and extending out of the water thus forming a boxlike
structure. The cofferdam is erected and sealed in order to per-
mit the water to be removed from the interior of the structure.
The sealing of the cofferdam is accomplished by placing in its
bottom a mass of concrete heavy enough to act as a plug and
sufficient to counteract the pressure of the water. The place-
ment of this mass of concrete is achieved by the “‘tremie”
method which requires a tube to be lowered into the water
through which concrete flows that settles on the bottom of
the cofferdam. Subsequent to this operation, the water in the
cofferdam is removed and work on the bridge pier may be
completed free of the water. The mass of concrete in the
bottom of the cofferdam is known as “‘tremie concrete,” and
A.3
when construction or repair of the bridge pier is completed,
the sheet piling of the cofferdam is removed and the “tremie”
is abandoned by being left in place.
Over the years after the original construction of the bridge,
Greiner conducted regular inspections of the bridge including
the piers. In 1971, Greiner reported deterioration of the bridge
piers below the waterline. This deterioration was determined
to be of a progressive nature. Based on the data gathered includ-
ing test borings and inspection by divers, Greiner came to the
conclusion that the piers needed immediate repairs. Greiner
communicated with Raymond which had some expertise in the
making of underwater repairs. Raymond’s representatives
recommended a repair procedure which contemplated a jacket-
ing of the piers with preplaced aggregate concrete. This pro-
cedure is a construction technique used in underwater work by
which stones are placed in a form with a cementitious material
(grout) pumped into the form displacing the water and forming
concrete.
At the request of the County, Greiner prepared contract
documents for the recommended repairs in order that the
County could solicit bids. The documents included specifica-
tions, drawings, informational drawings, an addenda, an invita-
tion to bid and other general provisions. Bids were solicited
from a limited group of bidders who were thought to have the
specialized abilities to perform the work. The group included
Raymond which ultimately submitted a bid substantially below
the bid of the next lowest bidder. Raymond and the County
entered into an agreement by the terms of which Raymond was
to finish the work in 100 days. Failure to do so made the
contractor liable for liquidated damages under the contract.
The County promised to obtain for Raymond a necessary right
of way. Raymond was to be paid on a unit price basis the
approximate sum of $213,000 based on the 230 cubic yard
quantity estimated by Greiner and the County to be the amount
A.4
of aggregate concrete required to complete the job. The work
to be performed consisted primarily of cleaning around Piers
Nos. 3 and 4 of the bridge, forming and pouring preplaced
aggregate concrete around the deteriorated faces of the piers,
and making repairs to the submarine cables.
After the repairs began, Raymond contends it discovered
that Greiner’s specifications were inaccurate. It produced
witnesses who stated that: (1) the material surrounding the
piers was not soft as represented, but contained large pieces of
concrete, pile butts, old timbers and steel; (2) the tremie was
irregular with variations up to 1.5 feet; (3) no tremie existed
in some areas; (4) only an average of two inches of deteriorated
concrete could be chipped away, rather than the six inches
represented in the plans and specifications which resulted in the
projected total of 230 cubic yards of concrete not being able to
be placed; and (5) the tremie was so weak in places that the
form could not be anchored. Raymond contended below and
contends here that as a result of the inaccuracy of Greiner’s
specifications it was required to perform unforeseeable increased
work. Raymond also complained particularly that instead of
the 230 cubic yards of aggregate concrete estimated to be used,
it utilized and was paid for only 114 cubic yards. Raymond
urges that its unit price as bid was computed by spreading its
fixed costs over the 230 cubic yards stated in the plans and
specifications and that the County paid for only 114 yards
which deprived Raymond of more than half of its computed
contract price. Raymond advised the County in a summary
of claim filed on January 30, 1976, that while its original
bid was $213,000, as a result of the misrepresentations included
in the plans and specifications and the unforeseeable conditions
arising out of the misrepresentations, its actual expenditure to
complete the project amounted to $1,095,804.30. This calcu-
lation is apparently not disputed. Baltimore County rejected
the claim and refused any adjustment in its contract with
Raymond.
A.5
Suit was then filed by Raymond against Greiner and the
County. The declaration was based on alleged fraud, negligent
misrepresentation, breach of warranty and breach of contract.
Raymond sought compensation for the additional costs incurred
as a result of the unforeseen conditions of the piers, the return
of liquidated damages retained by the County, and an award
for punitive damages. During the course of the bench trial
which lasted for many weeks, the trial judge granted Greiner’s
motion to dismiss at the conclusion of Raymond’s case. At the
conclusion of the entire case, the court awarded Raymond $900
representing rental payments made by the appellant for rights
of way and $17,531 being the compensation withheld by the
County which was due Raymond. The appellant, unsatisfied
with the judgment of the trial judge, thereupon filed this appeal.
The issues to be decided are:
I. Whether the trial judge erred in holding that the
plaintiff was not entitled to rely on the conditions,
quantities and representations contained in the
contract?
II. Whether the trial court erred in holding that the
plaintiff was not entitled to compensation for the
unforeseen or misrepresented conditions encountered
in the performance of the contract?
Ill. Whether Greiner’s motion to dismiss at the close of
Greiner’s case was improperly granted?
IV. Whether the County’s motion raising preliminary
objection was improperly granted on the issue of
sovereign immunity?
A. 6
V. Whether the trial judge erred in denying plaintiff's
claim for an equitable adjustment in time and com-
pensation due to a 50.1% underrun in preplaced
aggregate?
I,1I,V
One of the principal issues at trial was whether Raymond
was justified in relying on the conditions, quantities and repre-
sentations contained in the contract documents. Baltimore
County in its defense relied principally on the contract docu-
ments which were filed as exhibits in this case. These documents
included the invitation to bid, specifications, the proposal, the
agreement, special provisions and various drawings. Included in
the contract documents was the following which appeared in
Section 5 of the special provisions:
Original construction data has not been verified
by actual field measurements and the conditions
observed during the underwater inspections and tests
may have changed since the date on which they were
made. Therefore, the above described data are fur-
nished to the Contractor for general informational
purposes only and do not purport to represent exist-
ing field conditions. It shall be the Contractor’s sole
responsibility to verify by actual field measurements
inspections and tests and data which may be of sig-
nificance to him in the preparation of his bid.
The contract documents specifically stated that: “Special
provisions shall govern over specifications, supplemental speci-
fications and plans.” The County points out that the invitation
to bid at page 1-03 states: ‘Bidders must examine the drawings
and specifications carefully and must make a personal examina-
tion of the location and nature of the proposed work.”
A.7
In addition, the proposal which was made a part of the
contract documents required the bidders to agree as follows: ©
The undersigned hereby declare that they have
carefully examined the Form of Contract, Specifica-
tions, Special Provisions and Drawings forming a part
of the same and have to their satisfaction examined
the locality of the proposed work and agreed to fur-
nish all labor, tools, materials, machinery, equipment
and other means of construction called for in the
manner provided in the Contract, Specifications,
Special Provisions and Drawings thereto and require-
ments under them of the Engineer... .
Sheet “X”’ which also was made a part of the contract
documents provided:
Note 2—contractor to verify all dimensions in
field.
Note 5—dimensions shown taken from as built
plans and have not been verified by actual measure-
ment. The contractor shall verify any and all dimen-
sions as may be required to complete satisfactorily all
work under this contract.
Relying on these provisions, the County urgently contends
that the trial judge was correct when he held that there was no
“justifiable reliance” by the appellant on the conditions stated
to exist at the Wise Avenue bridge by the County’s engineer,
Greiner, and that the trial judge committed no error when he
held that: “[T] he contract documents that finally formed the
contract clearly placed the burden to the Plaintiff to make a
reasonable inspection to determine if these conditions were as
depicted as in the contract documents.”
A.8
The legal issue boils down to a question of whether Ray-
mond was required to verify independently the information
upon which it based its bid, or whether Raymond was justified
in relying on the information supplied by the County and its
engineer as to the plans and specifications for the project.
The seminal case on the subject is Hollerbach vy. United
States, 233 U.S. 165, 34 S.Ct. 553, 58 L.Ed. 898, which was
decided by the Supreme Court in 1914. That controversy
involved a contract between the appellant Hollerbach and the
United States Government for the repair of a dam. In its speci-
fications for the contract, the Government stated that the dam
was backed with broken stone and sediment. As the contractor
proceeded with the work of removing the material, it was
discovered that the backing of the dam was composed of a soft,
slushy sediment and that the required excavation of the dam
was substantially greater than that stated in the contract docu-
ments. The contract contained several exculpatory clauses
which were stated as follows:
It is understood and agreed that the quantities
given are approximate only, and that no claim shall
be made against the United States on account of any
excess or deficiency, absolute or relative, in the same.
Bidders, or their authorized agents, are expected to
examine the maps and drawings in this office, which
are open to their inspection, to visit the locality of
the work, and to make their own estimates of the
facilities and difficulties attending the execution of
the proposed contract, including local conditions,
uncertainty of weather, and all other contingencies.
It is expected that each bidder will visit the site
of this work, the office of the lockmaster, and the
A.9
office of the local engineer and ascertain the nature
of the work, the general character of the river as to
floods and low water, and obtain the information
necessary to enable him to make an intelligent
proposal. [233 U.S. at 167-68, 34 S.Ct. at 554.]
In spite of the Government’s attempt to make the contrac-
tor responsible for his own inspection,the investigation of the
site and the work to be done under the contract, the Supreme
Court held:
{T]he specifications assured them of the character of
the material, a matter concerning which the Govern-
ment might be presumed to speak with knowledge
and authority. We think this positive statement of
the specifications must be taken as true and binding
upon the Government, and that upon it rather than
upon the claimants must fall the loss resuiting from
such mistaken representations. We think it would be
going quite too far to interpret the general language
of the other paragraphs as requiring independent
investigation of facts which the specifications fur-
nished by the Government as a basis of the contract
left in no doubt. If the Government wished to leave
the matter open to the independent investigation of
the claimants it might easily have omitted the speci-
fication as to the character of the filling back of the
dam. In its positive assertion of the nature of this
much of the work it made a representation upon
which the claimants had a right to rely without an
investigation to prove its falsity. See United States
v. Stage Co., 199 U.S. 414, 424. [233 US. at 172,
34 S.Ct. at 556.]!
‘See also United States v. Spearin, 248 U.S. 132, 39 S.Ct. 59, 63
L.Ed. 166 (1918); Christie v. United States, 237 U.S. 234, 35 S.Ct. 565,
59 L.Ed. 933 (1915).
-
A. 10
Appellant also cites Robert E. McKee, Inc. v. City of
Atlanta, 414 F. Supp. 957 (N.D. Ga. 1976). In that case, the
results of test borings were gratuitously provided to bidders
along with specifications and other contract documents. The
contract contained a clause in which the owner disclaimed any
responsibility for the accuracy of the test results or for any
conclusions drawn from them. The contract specifically pro-
vided that the test boring data were not to be considered a
part of the contract. The contractor sued for misrepresenta-
tion because it discovered the level of rock was substantially
higher than had been represented by the test boring.
The District Court in McKee, supra, at 959, held that it is
clear “the government does not become an insurer merely by
providing certain information” to the contractor. That Court,
in determining whether the Government was liable for mis-
information which it furnished to the bidder, posed two ques-
tions which must be examined: (1) “whether the contractor
could have discovered the true facts through reasonable investi-
gation[?]” and: (2) what “is the materiality of [the] misrepre-
sentation itself[?]’’ Jd. at 960.
Condon-Cunningham vy. Day, 22 Ohio Misc. 71, 258
N.E.2d 264 (1969) involved a suit in which damages were
allowed to a highway contractor as a result of misleading soil
tests even though the contract provided that the test results
were not part of the contract and that the contractors were
obliged to make their own inspection. In examining the issue
whether the contractor could have discovered the true facts
for itself, the Court said: ©
What were the bidders to do? Was each bidder to run
these tremendously expensive core boring tests not
knowing whether or not he would get the contract?
Under defendant’s contention there would be practic-
ally no bidders. A bidder wouid be faced with this
A. 11
dilemma. Shall I bid on what is presented to be and
run the risk of loss if the information is not correct
or shall I run core boring tests at great expense,
amounting to thousands of dollars, which expense I
must bear on my own if I do not secure the contract?
[258 N.E.2d at 274-75.]
See also Michigan Wisconsin Pipeline Co. v. Williams-Mc Williams
Co. v. United States, 551 F.2d 945 (Sth Cir. 1977); Foster Con-
struction C. A. & Williams Bros. Co. v. United States, 435 F.2d
837 (1970); Alpert v. Commonwealth, 357 Mass. 306, 258
N.E.2d 755 (1970).
There is one case from the Court of Appeals in which a
similar controversy was addressed. That case is Linz v. Schuck,
106 Md. 220, 67 A. 286 (1907), in which a contractor was
hired to excavate a cellar under appellant’s property. Before
submitting a price, the contractor inquired about the nature of
the soil whereupon he was taken by the owner to a property
across the street from the subject property and shown a cellar
which the owner stated had been constructed without any dif-
ficulty. When the contractor began the work, however, it was
ascertained that the building stood on a three-foot crust of hard
ground under which were muddy, swamp-like conditions. It
was conceded that the contractor could have ascertained the
condition of the earth under the house by digging a test hole.
However, the contractor relied on the owner’s representations
without performing any tests. Suit for additional compensation
due to substantial and unforeseen difficulty was brought by the
contractor. In affirming a judgment for the contractor, the
Court of Appeals said:
When two parties make a contract based on supposed
facts which they afterwards ascertain to be incorrect;
and which would not have been entered into by the
one party if he had known the actual conditions
A. 12
which the contract required him to meet, not only
Courts of justice but all right thinking people must
believe that the fair course for the other party to the
contract to pursue is either to relieve the contractor
of going on with his contract or to pay him additional
compensation. [106 Md. at 230.]
We have very carefully reviewed the record extract in order
to determine whether the trial court was clearly erroneous in
its conclusions as to the law and the facts. The record extract
establishes that the specifications as prepared by Greiner on
behalf of Baltimore County were materially wrong and sub-
stantially inaccurate. The evidence disclosed no substantial
dispute that the conditions as found by Greiner and reported to
the County and to the bidders were substantially different from
those encountered by Raymond when it began to perform the
work required by the contract. Greiner and the County knew or
should have known the representations regarding the deteriora-
tion of the piers and the quantities of concrete necessary for
the repairs were inaccurate as Greiner had been engaged by the
County over a period of years to inspect the underwater por-
tions of the bascule piers. Greiner actually had thirteen con-
tracts with the County between 1968 and 1972 which required
Greiner to make underwater inspections of the bascule piers,
tremies and piles, and field supervision of the piers.
Greiner, as agent for the County, submitted to Raymond
information and plans which represented an average surface
deterioration depth of six inchesin spite of the fact that Greiner
had reports from its divers that indicated the average depth of
deterioration was only two inches. Therefore, in its bid proposal,
Greiner required a computation based on quantities and infor-
mation which Greiner knew or should have known was incorrect.
To suggest that Raymond, who had been solicited to bid on
the job by the County and Greiner, should have conducted
diving tests in order to verify the information given it in the
A. 13
plans and specifications prepared by Greiner seems to us to
place an undue burden on Raymond. Entirely apart from the
substantial cost of any such verification, it is obvious that
Greiner required a period of almost four years and innumerable
test divings to compile the information necessary to prepare the
plans, specifications and bid proposals, and that even in view of
that lengthy time frame the information it had was incorrect.
We conclude that Raymond was not reasonably able to discover
the true facts for itself and was, therefore, entitled to rely on
the representations made by the County and Greiner.
As to the materiality of the representations, there can also
be no dispute. Raymond established that its bid was conditioned
upon the erroneous representation in the contract documents
that a total of 230 cubic yards of aggregate concrete would be
required to perform the contract. The actual amount required
was approximately 114 cubic yards. The bid was based on a
unit price per square yard, and because the County paid only
for the actual amount used, the appellant was deprived of over
half its contract price. In addition, because of the incorrect
information supplied to Raymond, the contractor was required
to perform additional work in connection with the use of the
prefabricated forming system and to utilize new methods for
sealing and anchoring the form bottoms. As a direct result of
the variations from the conditions as represented in the plans
and specifications, Raymond was unable to complete the
project within the 100 days provided in the contract. As
Raymond failed to perform within the time specified, the
County withheld the sum of $37,000 notwithstanding that
performance was impossible within the 100 days required by
the contract.
Appellee Baltimore County relies on Trionfo v. Board of
Education of Harford County, 41 Md. App. 103, 395 A.2d
1207 (1979), in which Judge Thompson of this Court exhaus-
tively discussed the law of a contractor’s right to recover on a
A. 14
theory of misrepresentation. There we held, as we hold here,
that the plaintiff must establish a right to rely on the misrepre-
sentation. In Trionfo, we found no right to rely because the
test boring data furnished to contract bidders were supplied
only in exchange for a written release from the bidders
designed to absolve the board from any responsibility for the
accuracy or completeness of the information and to protect
the board from assessments for additional work performed
pursuant to assumptions made based on the supplied data.
No such release provision exists in this contract. We, there-
fore, find Trionfo inapplicable to the present case. We con-
clude that the trial court erred in holding that the appellant
was not entitled to rely on the conditions, quantities and
representations contained in the contract. We further hold
that the trial court erred in its finding that the appellant was
not entitled to compensation for the unforeseen or negligently
misrepresented conditions encountered in the performance of
the contract.
We perceive an additional error in the trial court’s rulings.
The contract documents expressly incorporated the specifica-
tions of the State of Maryland with the contract between
Raymond and the County. Section 10.09-3 of those specifi-
cations expressly provides for an equitable adjustment for
major discrepancies in quantities as follows:
Whenever a final quantity for any Major Con-
tract Item shows that either the Proposal Quantity
of said item, or the quantity specified therefor in
any Supplemental Agreement has been actually over-
run or underrun by more than 25 percent; the Con-
tractor and Commission shall then be allowed an
equitable adjustment in time and/or compensation
as though said overrun or underrun had been antici-
pated by the Engineer and ordered, under the pro-
visions of Section 10.04-3.
A. 15
The term “major contract item” is defined in the State
specifications as follows:
Major Contract Items shall be the original Contract
item of greatest cost, computed from the original
Contract price and estimated quantity, or lump sum
price and such other original Contract items next in
sequence of lower cost, computed in like manner,
necessary to show a total cost at original prices and
quantities of not less than 60 per cent of the original
Contract cost and all other Contract items shall be
considered as minor items.
The record extract, we think, clearly establishes that the
major contract items in this contract were the preplaced aggre-
gate contract amount of $115,000 and the removal of the
fender systems amounting to $34,000 and totaling more than
60 percent of the original contract price. The evidence is undis-
puted that the quantity of preplaced concrete used amounted
to a 50 percent underrun of the prescribed quantities set forth
in the contract. Under these circumstances, Raymond was
entitled to an equitable adjustment in time or compensation.
The trial court initially came to the same conclusion, but
inexplicably without reliance on either the law or the facts
changed that opinion and concluded that Baltimore County
was entitled to a favorable verdict on the issues of the failure
to renegotiate and on the issue of an equitable adjustment. The
lower court said:
The other three issues were the failure to renegotiate
an equitable adjustment. At one point in the trial,
I think I indicated to counsel, that I was really some-
what impressed that this is an issue that the plaintiff
has a right to a particular equitable adjustment. I
was very impressed by the testimony of Mr. Morris
A. 16
on this issue. He dwelled at length, but after review-
ing the contract documents and listening to argu-
ments of counsel, I’ve come to the conclusion that
the defendant is correct that this is just not called
for under the contract documents, and I could not,
without breaking the rules of the law, allow that
amount and I find that I would have to find for the
defendant, Baltimore County, on those issues failing
to renegotiate, and on the equitable adjustment.
We find nothing in the record extract on the basis of the facts
or the law which supports that conclusion.
III
We find no error in the trial court’s granting of Greiner's
motion to dismiss Raymond’s suit against Greiner on the
grounds of misrepresentation at the conclusion of Raymond’s
case. Raymond contends that Greiner waived its right to file
such a motion to dismiss because it offered testimony before
the conclusion of the plaintiff’s case and that this amounted
to a clear violation of Maryland Rule 535. We do not agree.
The record discloses that Greiner’s counsel read into the record
a short portion of the deposition of one of Greiner’s executives,
the major portion of which had been put into the record by
Raymond’s counsel. The clearly expressed purpose of the
reading of the short excerpt of the deposition was for clarifica-
tion of the witnesses’ testimony. We do not find that this
amounted to such a violation of either the letter or the spirit
of Rule 535 as to make Greiner’s motion to dismiss a “nuga-
city.” See Smith v. State Roads Comm., 240 Md. 525, 214
A.2d 792 (1965).
It would serve no useful purpose to again restate the five
prerequisites of proof required to sustain an action for mis-
representation or deceit. It is sufficient to state that the appel-
lant failed to produce evidence from which could be found or
A. 17
inferred that Greiner intended to defraud by reason of the
allegedly incorrect information it furnished to Raymond.
Even assuming that Greiner was negligent in preparing the
information it furnished to the bidders, that would not be
sufficient to satisfy the plaintiff’s burden as a misrepresentation
induced by negligence or ignorance will not sustain an action
for fraud. Peurifoy v. Congressional Motors, Inc., 254 Md. 501,
255 A.2d 332 (1969). There was no testimony establishing
clear and convincing evidence that Greiner’s representations in
this case were made for the specific purpose of defrauding the
plaintiff. This is particularly so when we note that at the time
the information was supplied to the prospective bidders no one
had any knowledge as to who the successful bidder would be.
It is not contended in appeal that the trial court was otherwise
in error with respect to Greiner’s motion.
IV
The trial court was correct in its ruling on the County’s
motion raising preliminary objection on the ground of sovereign
immunity as to the first and second counts of Raymond’s
declaration which were founded on the torts of fraud and negli-
gent misrepresentation. See Jekofsky v, State Roads Comm.,
264 Md. 471, 287 A.2d 40 (1972); Godwin v. County Commis-
sioners of St. Mary’s County, 256 Md. 326, 260 A.2d 295
(1970),
JUDGMENT REVERSED AS TO BALTI-
MORE COUNTY; REMANDED FOR NEW
TRIAL AS TO DAMAGES ONLY. JUDG-
MENT AFFIRMED AS TO GREINER.
COSTS TO BE PAID BY BALTIMORE
COUNTY.
This is a copy of a public record, reproduced as it was published. It is not legal advice, and it may not be the version a court would rely on. Check the official source before you cite it.