Petition — Save The Bay, Inc. v. United States Corps of Engineers
Supreme Court brief1980
Ask Donna
What actually matters in this document.
Text
80-171 JUN 5 1980
IN THE
Supreme Court of the United States
OCTOBER TERM, 1980
SAVE THE BAY, INC.,
Petitioner
V.
U.S. CorPs OF ENGINEERS, et al.,
Respondents
PETITION FOR WRIT OF CERTIORARI TO THE
UNITED STATES COURT OF APPEALS FOR
THE FIFTH CIRCUIT
ROBERT W. SMITH
Attorney for the Petitioner
507 Lameuse Street
Biloxi, Mississippi 39530
(601) 374-1356
EARL L. DENHAM ;
Attorney for the Petitioner
424 Washington Avenue
P.O. Box 596
Ocean Springs, Mississippi 39564
(601) 875-1234
WILSON - EPES PRINTING Co.. INC. - 789-0096 - WASHINGTON, D.C. 20001
QUESTIONS PRESENTED FOR REVIEW
Whether the United States District Court and the
Court of Appeals for the Fifth Circuit erred in ruling
that:
a) The preparation of an Environmental Impact State-
ment is not necessary in this case because
1) An environmental assessment by the district en-
gineer was reasonable and based on substantial evidence;
2) The activity herein is not a major federal action
significantly affecting the quality of the human environ-
ment.
b) In issuing a permit for an outfall pipeline to de-
liver 2,300,000 gallons of pollutants per day from a mas-
sive chemical plant, the Corps of Engineers is not re-
quired to consider the environmental cost of the entire
project but only the effects of the installation and main-
tenance of the outfall line itself.
(i)
TABLE OF CONTENTS
Questions Presented For Review ..................--.:::se0-0000+
Judgment and Opinion Below ......2...............-....-..0c000eee-e-
SEGRE EE
Constitutional Provisions and Statutes Involved ..........
ES ITS I REL
Reasons for Granting The Writ .......................:::seseee-++
I eiispinimisetinaubionecs
Appendix A
Opinion of the United States Court of Appeals for
Ss sesunbelinnionns
TABLE OF AUTHORITIES
CASES:
Citizens for Clean Air, Inc. v. U.S. Corps of Engi-
neers, et al., 349 F. Supp. 696 (S.D.N.Y. 1972)..
Mahelona v. Hawaiian Electric Company, 418 F.
Supp. 1828 (D..Hawaii 1976)...............................
Port of Astoria v. Hodel, 8 ERC 1156, Aff’d, 595
Ss )
STATUTES:
Title 28, USC Section 4882(2) (c) --........22.-222..200-+-
le inccsneiaiendninsennsdasessunarsnsiee
iii
PREVIOUS PAGE WAS BLANK
la
IN THE
Supreme Court of the United States
OCTOBER TERM, 1980
No.
SAVE THE BAY, INC.,
Petitioner
V.
U.S. CoRPS OF ENGINEERS, et al.,
Respondents
PETITION FOR WRIT OF CERTIORARI TO THE
UNITED STATES COURT OF APPEALS FOR
THE FIFTH CIRCUIT
SAVE THE BAY, INC., respectfully petitions for a
Writ of Certiorari to review the Opinion of the United
States Court of Appeals for the Fifth Circuit which
affirmed the judgment of the United States District
Court, Southern District of Mississippi, Southern Divi-
sion, refusing to require the U.S. Corps of Engineers
to prepare an Environmental Impact Statement as pro-
vided under the National Environmental Policy Act with
respect to an outfall pipeline which will discharge
2,000,000 gallons per day of industrial waste water into
a pristine estuarian bay from a massive titanium dioxide
chemical plant being constructed by E. I. DuPont de
Nemours and Co., Inc.
2
JUDGMENT AND OPINION BELOW
The judgment of the United States District Court re-
fusing to require the U.S. Corps of Engineers to prepare
an Environmental Impact Statement and refusing the
injunctive relief requested by Petitioner, was affirmed by
the United States Court of Appeals for the Fifth Circuit
in an Opinion dated January 24, 1980, reported at 610
F.2d 322; Petition for rehearing denied, March 17, 1980.
The opinion and the denial of rehearing are attached
hereto in Appendix A.
JURISDICTION
The Opinion of the United States Court of Appeals
for the Fifth Circuit which is sought to be reviewed was
rendered on January 24, 1980.
The per curiam amendment to the Opinion and denial
rehearing was rendered March 17, 1980.
The jurisdiction of this Supreme Court is based on
28 USC 1245.
CONSTITUTIONAL PROVISIONS AND
STATUTES INVOLVED
1. Title 28, USC Section 4332 (2) (c) °
“The Congress authorizes and directs that to the fullest
extent possible. . .
2. All agencies of the Federal Government shall:
(c) Include in every recommendation or report on
proposals for legislation and other major federal
actions significantly affecting the quality of the
human environment a detailed statement (EIS) by
the responsible official on:
(i) The environmental impact of the proposed
action,
3
(ii) Any adverse and environmental effects
which cannot be avoided should the proposal be
implemented,
(iii) Alternatives to the proposed action,
(iv) The relationship between local short-term
uses of man’s environment and the maintenance
and enhancement of long-term productivity, and
(v) Any irreversible and irretrievable commit-
ments of resources which would be involved in
the proposed action should it be implemented...
2. Counsel of Environmental Quality Regulations 40
CFR 1500.6 (a)
“The statutory clause ‘major Federal actions sig-
nificantly affecting the quality of human environ-
ment’ is to be construed by agencies with a view to
the overall, cumulative impact of the action, proposed
related Federal actions and projects in the area, and
further actions contemplated. Such actions may be
localized in their impact, but if there is potential
that the environment may be significantly affected,
the statement is to be prepared. Proposed major
actions, the environmental impact of which is likely
to be hightly controversial, should be covered in
all cases. In considering what constitutes major
action significantly affecting the environment, agen-
cies should bear in mind that the effect of many
Federal decisions about a project or complex of
projects can be individually limited but cumulatively
considerable. This can occur when one or more agen-
cies over a period of years puts into a project indi-
vidually minor but collectively major resources,
when one decision involving a limited amount of
money is a precedent for action in much larger
cases or represents a decision in principle about a
future major course of action, or when several gov-
ernment agencies individually make decisions about
partial aspects of a major action. In all such cases,
an Environmental Statement shouid be prepared if
4
it is reasonable to anticipate a cumulatively signifi-
cant impact on the environment from Federal action.
The Council, on the basis of a written assessment of
the impacts involved, is available to assist agencies
in determining whether specific actions require im-
pact statement.” 40 CFR 1500.6 (a)
STATEMENT OF THE CASE
The Plaintiff, SAVE THE BAY, INC. is a non-profit
corporation organized under the laws of the State of
Mississippi. Its members consist of full time and part
time residents of Harrison and Hancock Counties in the
State of Mississippi and of the vicinity of the Bay of
St. Louis (Tr. 1158). The Defendant, DuPont, is a pri-
vate corporation incorporated under the laws of the State
of Delaware, the Federal Defendants are the United
States Army, the United States Corps of Engineers, an
agency of the United States Government within the De-
partment of the Army, and Colonel Drake Wilson, for-
merly the District Engineer for the Mobile District of
the Corps. (Tr. 1158). The Defendant, DuPont, is
presently constructing and plans to operate a massive
titanium dioxide manufacturing facility representing an
investment of between one hundred twenty-five and one
hundred thirty million dollars, (Tr. 298, 471) and en-
compassing over two thousand acres of land (Tr. 292,
474), (general exhibits 1-4) in Delisle, Mississippi near
the Bay of St. Louis, in Harrison County, Mississippi.
The plant operation and construction includes waste
emission smoke stacks, deep-well disposal of highly toxic
chemical wastes, and a pipeline to dump chemical wastes
into the Bay of St. Louis as hereafter described. On
November 21, 1974, DuPont sought authorization from
the Defendant U.S. Corps of Engineers, to install a 24
inch diameter effluent line to discharge approximately
two million gallons of industrial pollutants per day (Tr.
505-506) into the Bay of St. Louis. The outfall line
5
itself extends approximately 2,200 feet into the Bay and
is installed by the dredging of a trench resulting in the
removal of 610 cubic yards of dredged material.
From the very beginning, the Corps of Engineers con-
sidered the question as to whether all or part of the pro-
posed construction should be considered as candidate for
an Environmental Impact Statement (Tr. 284), but the
Corps determined that only construction of the 24 inch
effluent line and appurtenant structures were subject to
Corps regulation and thus the Corps limited its assess-
ment, evaluation and evaluation and analysis solely to
that feature of the plant construction (Tr. 285).
On February 3, 1975, the Mississippi Air and Water
Pollution Control Commission, issued a National Pol-
lutant Discharge Elimination Systems permit to DuPont
allowing discharge of the waste water in accordance with
the conditions of the permit.
Following solicitation of comments from federal, state
and local agencies concerning the proposed pipeline con-
struction permit, the Corps of Engineers announced a
public hearing would be held on June 19, 1975, to answer
any questions concerning issuing of the pipeline con-
struction permit. In keeping with the Corps’ prior de-
termination that only the construction of the pipeline was
subject to their regulation, the public notice for the
hearing was limited to the installation of the 24 inch
diameter pipeline and made no mention of consideration
of other aspects of the DuPont Plant in the issuance of
its permit. On June 19, 1975 the hearing was held and
all proponents and opponents were allowed to express
their views. The proponents consisted mostly of govern-
mental or business organizations and generally testified
as to the favorable economic impact the plant would
have. The opponents, consisting mostly of ecological and
recreational organizations, and scientists, testified that
the environmental damage and impact of the DuPont
6
project will reach far beyond deterioration of the water
quality and that potential dangers to the marine and
land environment necessitated the minimal protection of
an environmental impact statement.
The vast majority of the public response and virtually
all the authoritative scientific evidence was unalterably
opposed to the location of the DuPont plant in its se-
lected site; opposed to the granting of the permit for
the outfall pipeline; and overwhelmingly in favor of the
initiation by the Corps of Engineers of a comprehensive
Environmental Impact Statement.
On July 17, 1975, the U.S. Corps of Engineers issued
a statement of Findings allegedly assessing the impact
the proposed activity would have on the environment. The
Corps findings, as was its public notice, was predicated
on the initial determination that the only potential en-
vironmental damages which the Corps would assess would
be those adverse affects caused directly by the construc-
tion of the 220 feet outfall line and excavation of 610
cubic yards of dredged material from the Bay.
The Corps explicitly stated that all other environ-
mental damages caused by the massive DuPont titanium
dioxide plant would not be assessed and were not in-
cluded in the Corps decision to not require an environ-
mental impact statement.
Based on the administrative record, which was replete
with demands for an environmental impact statement
and which evidenced one of the most controversial en-
vironmental issues ever to appear in the State of Mis-
sissippi, the Corps nevertheless directed that the permits
be issued without the protection of an environmental im-
pact statement.
The Plaintiff, SAVE THE BAY, INC. brought suit
pursuant to the National Environmental Policy Act
(NEPA 28 USC 4321 ex seq) against the United States
7
Corps of Engineers, the United States Army, Colonel
Drake Wilson, Mobile District Office of the Corps of
Engineers, and DuPont seeking declaratory and injunc-
tive relief and monetary damages. The case was referred
to the United States Magistrate by the District Judge
and thereafter the Defendant’s Motions for Summary
Judgment were granted and judgment was entered
December 16, 1977 dismissing the complaint with preju-
dice.
Plaintiff, SAVE THE BAY, INC. appealed. On Jan-
uary 24, 1980 the U.S. Court of Appeals for the Fifth
Circuit issued an opinion affirming the District Court’s
opinion and denying Plaintiff the relief requested.
The DuPont plant is now almost in operation. The
construction was begun and has been continuing despite
three years of pleas by Appellant, SAVE THE BAY,
INC. for the very minimal protection of an Environ-
mental Impact Statement.
So far DuPont has obtained or is attempting to obtain
permits from the following agencies:
1. Mississippi Air and Water Pollution Control
Commission,
Mississippi Marine Resources Counsel,
Mississippi Oil and Gas Board,
United States Army Corps of Engineers,
United States Coast Guard, and
The Interstate Commerce Commission.
ee
Not one of these agencies prepared or is attempting to
prepare an Environmental Impact Statement on the
DuPont project.
The perspective of each agency when approached for
a permit has been to consider piecemeal only that part
of the massive project which is directly regulated by
8
that particular agency. The State agencies have studied
only a simulated effluent to be discharged into the Bay
of St. Louis at the rate of 2,000,000 gallons per day.
Those State agencies have further allowed the installa-
tion and use of deep-well disposal of highly toxic chemical
wastes on the DuPont plant site which will one day en-
danger the water supply of the entire Mississippi Gulf
Coast. The United States Coast Guard has issued a
bridge permit to allow construction of a railroad bridge
pursuant to a railroad spur being built to the DuPont
plant. The Interstate Commerce Commission has issued
a permit to allow operation of the same railroad spur.
The United States Corps of Engineers has issued the
outfall construction permit in the instant case as well as
another permit relative to the railroad spur.
The massive DuPont chemical plant could not be built,
could not operate and could not damage the environment
without the issuance of these vital federal permits. The
permits not only allow construction, they allow massive
environmental impact.
The Court of Appeals for the Fifth Circuit has de-
termined that the Corps acted reasonably. The Court
said the Corps was justified in assessing only the environ-
mental damage due to construction aspects of the twenty-
two hundred feet of pipeline and has no duty to consider
the obvious and substantial environmental damages
caused by the massive chemical plant itself.
We strongly dissent.
REASONS FOR GRANTING THE WRIT
The decision of the Court of Appeals that federal per-
mitting agencies, in issuing permits for portions of pri-
vate construction projects must only review the environ-
mental damage of the particular portion of the project
which that federal agency regulates is directly contrary
9
to an explicit regulation of the Council on Environmental
Quality and in conflict with the prior environmental de-
cisions of this Court and other Circuit Courts of Appeal.
In concrete terms for the Petitioner herein the de-
cision will mean that E. I. DuPont can build a $150,000,-
000 titanium dioxide chemical plant with appurtenant
structures for the deep well injection of highly toxic
wastes and for piping 2,000,000 gallons of industrial
waste water a day to dump into a pristine estuarian bay,
and an adjacent thirteen mile railroad spur to ship in
chlorine gas and other chemicals and that all of the
federal permits necessary for this construction can be
issued without the very minimal protection of an En-
vironmental Impact Statement.
L
The Court of Appeals classification of the entire fed-
eral permitting system as “incidental involvement” in
massive private construction projects for the purposes of
NEPA analysis adopts the piecemeal “blinder”’ approach
which has been rejected by every Circuit Court and by
the Council on Environmental Quality (CEQ).
The CEQ Regulation in question, 40 CFR 1500.6(a)
(set forth verbatim at page 3 herein) explicitly states:
“In considering what constitutes major (federal)
action significantly affecting the environment, agen-
cies should bear in mind that the effect of many fed-
eral decisions about a project or complex of projects
can be individually limited but cumulatively con-
siderable. This can occur when one or more agen-
cies over a period of years puts into a project indi-
vidually minor but collectively major resources, when
one decision involving a limited amount of money
is a precedent for action in much larger cases or
represents a decision in principle about a future
major course of action, or when several government
10
agencies individually make decisions about partial
aspects of a major action.
“In all such cases, an EIS should be prepared. . .”
In the case sub judice, the Court of Appeals panel in
oral argument and in its Opinion under the section en-
titled “A Major Federal Action?” took the position that
issuing federal permits was merely “incidental federal
involvement” and did not federalize the massive private
construction. The panel’s position is taken despite the
intimate involvement of four federal agencies in review-
ing and issuing the numerous federal permits necessary
for the massive chemical plant, the deep-well toxic waste
disposal, the railroad constructed to the plant and the
waste-water pipeline constructed to dump 2,000,000 gal-
lons a day of industrial wastes into the Bay of St. Louis.
NEPA was passed specifically to halt the multi-agency,
piecemeal consideration of environmental impact. NEPA’s
whole essence is the comprehensive assessment of en-
vironmental impact in the planning stages of a project.
The decision here is to throwback to pre-NEPA 1969
thinking.
Il.
The second question presented, and as the Court of
Appeals noted, perhaps the point which controls the out-
come of vhe case, is the ruling that the Corps must look
only to the environmental consequences of the pipeline
construction and maintenance instead of considering the
entire DuPont project in its decision on whether or not
to prepare an EIS.
Without the federal permits, including the Corp’s per-
mit for construction of the waste-water pipeline directly
from the massive plant over wet lands to the Bay of St.
Louis, the DuPont project could not have been built and
could not exist.
11
This massive chemical plant is analogous to a living
organism which eats chlorine gas and at the other end
excretes toxic wastes and industrial pollutants at the
rate of over 2,000,000 gallons per day. Without the
permit, there would be no pipeline. Without the pipe-
line, the plant would suffocate in its own waste and the
Bay of St. Louis would live. With the pipeline, the Bay
of St. Louis will die.
To allow the Corps to put on blinders and completely
ignore the environmental ramifications of the federal
permits is the most niggardly, narrow-minded approach
to environmental planning that one can imagine
The cases of Port of Astoria v. Hodel, 8 ERC 1156,
Aff’d 595 F.2d 467 (9th Cir. 1979), Mahelona v. Ha-
watian Electric Company, 418 F. Supp. 13828 (D. Hawaii
1976) and Citizens for Clean Air, Inc. v. U.S. Corps of
Engineers, et al., 349 F. Supp. 696 (S.D.N.Y. 1972) pro-
vide a sound analysis for Petitioner’s position that the
wholg project must be considered and not just 2,200 feet
of pipe. We respectfully disagree with the Court of
Appeals that those cases are distinguishable.
The Corps approach, affirmed by the Opinion of the
Court of Appeals, allows an environmental analysis of
2,200 feet of pipe just as if the pipe was lying out in
the marshes of South Mississippi without a massive
chemical plant at one end and 2,000,000 gallons a day
of industrial waste spewing out the other end. We expect
that type of attitude from the U.S. Corps of Engineers,
but we are keenly disappointed that the attitude also pre-
vails in the Fifth Circuit Court of Appeals.
12
CONCLUSION
This case is the most important environmental law case
ever to come out of the State of Mississippi. A review
of this case by the Supreme Court and a reversal of the
precedent set by the Court of Appeals regarding the
federal permitting system is necessary to the continued
vitality and existence of NEPA in the Fifth Circuit.
The case offers a clear opportunity for this Court to make
a pronouncement concerning the effect of the massive
federal permitting program on environmental law and
environmental impact statements.
We respectfully and urgently ask this Honorable Court
to grant our Petition for Writ of Certiorari.
Respectfully submitted,
SAVE THE BAY, INC.,
PETITIONER
/8/ Robert W. Smith
ROBERT W. SMITH
Attorney at Law
507 Lameuse Street
Biloxi, Mississippi 39530
EARL L. DENHAM
Attorney at Law
42A Washington Avenue
P.O. Box 596
Ocean Springs, Mississippi 39564
13
CERTIFICATE
I, ROBERT W. SMITH, attorney for the Petitioner,
do hereby certify that I have this day mailed a copy
of the Writ of Certiorari, via U.S. Mail, postage pre-
paid to:
Chief Appellate Section
Land and Natural Resources Division
Department of Justice
Washington, D.C. 20520
Attention: Nancy Firestone
L. K. Travis
Assistant U.S. Attorney
P.O. Box 2091
Jackson, Mississippi 39205
David B. Sebree
Legal Department
E. I. du Pont de Nemours & Company
Wilmington, Delaware 19898
Stanford E. Morris
Attorney at Law
P.O. Drawer 100
Gulfport, Mississippi
DONE, this the 2nd day of June, 1980.
/8/ Robert W. Smith
ROBERT W. SMITH
APPENDIX
la
APPENDIX
UNITED STATES COURT OF APPEALS
FIFTH CIRCUIT
No. 79-1482
SAVE THE BAY, INC.,
Plaintiff-Appellant,
V.
THE UNITED STATES CORPS OF ENGINEERS, UNITED
STATES ARMY, COLONEL DRAKE WILSON, and E.I. Du
PONT DE NEMOURS AND COMPANY,
Defendants-Appellees.
Appeal from the United States District Court
for the Southern District of Mississippi
Jan. 24, 1980.
Before BROWN, TJOFLAT and GARZA, Circuit
Judges.
GARZA, Circuit Judge:
Appellant appeals from refusal of the United States
Magistrate, acting on behalf of the District Court by
consent of the parties, to require the United States Corps
of Engineers to prepare an Environmental Impact State-
ment (EIS) as provided for under the National Environ-
mental Policy Act of 1969 (NEPA), 42 U.S.C. § 4821
et seg. Appellants argue the Court below erred in con-
cluding that the environmental assessment by the district
engineer was reasonable and based on substantial evi-
dence, that the activity involved was not a major federal
action significantly affecting the quality of the human
environment, and that the Corps of Engineers was not
required to consider the environmental consequences of
the entire project but only the effects of the installation
2a
and maintenance of a twenty-four inch outfall pipeline.
Appellees argue on appeal that Appellants have no
standing to challenge the actions of the Corps of En-
gineers. For the reasons stated below, we affirm the
ruling of the United States Magistrate.
FACTS
At the time this litigation began, the defendant, E.I.
Du Pont De Nemours & Co., Inc., proposed to construct
and operate a massive titanium dioxide manufacturing
facility in Delisle, Mississippi. Pursuant to this plan,
Du Pont sought necessary authorization and permits
from appropriate state and federal agencies.
On November 21, 1974, Du Pont sought authorization
from the defendant, Army Corps of Engineers, to install
a twenty-four inch diameter effluent line into the marsh-
lands and Bay of St. Louis. The effluent line would
carry approximately two million gallons per day of
industrial wastewater and discharge it into the Bay of
St. Louis. The line would be approximately 2,200 feet
in length extending into the Bay and construction would
require removal of 610 cubic yards of dredged material
from the Bay.
On February 3, 1975, the Mississippi Air and Water
Pollution Control] Commission, acting pursuant to au-
thority delegated to it by the Environmental Protection
Agency, issued a National Pollutant Discharge Elimina-
tion System (NPDES) permit to Du Pont allowing dis-
charge of the wastewater in accordance with the con-
ditions of the permit.
Following solicitation of comments from federal, state
and local agencies concerning the proposed pipeline con-
struction permit, the Corps of Engineers announced a
public hearing would be held on June 19, 1975, to answer
any questions concerning issuing of the pipeline construc-
3a
tion permit. In keeping with the Corps’ prior determina-
tion that only the construction of the pipeline was sub-
ject to their regulation, the public notice for the hearing
was limited to the installation of the twenty-four inch
diameter pipeline and made no mention of consideration
of other aspects of the Du Pont plant in the issuance of
its permit. On June 19, 1975 the hearing was held and
all proponents and opponents were allowed to express
their views. The proponents consisted mostly of govern-
mental or business organizations and generally testified
as to the favorable economic impact the plant would
have. The opponents, consisting’ mostly of ecological and
recreational organizations, testified generally that a po-
tential danger to marine life existed and that an En-
vironmental Impact Statement was necessary.
On July 17, 1975, Colonel Drake Wilson, District
Engineer for the Mobile Corps of Engineers, issued a
Statement of Findings assessing the impact the proposed
activity would have on the environment. The Corps de-
termined there would be no adverse effect on air quality
and that water quality would be only temporarily af-
fected. The findings also noted the issuance of the
NPDES permit and that the Environmental Protection
Agency had no objection to the issuance of the Corps’ per-
mit. The statement, also taking into consideration the
determinations of the Mississippi Marine Resources
Council and the Gulf Coast Research Laboratory, found
there would be no significant adverse effect on land use,
visual aesthetics, wildlife, sealife, vegetation, or historical
interests. Based on the administrative record, Colonel
Wilson directed that the permit be issued. The permit
only authorized building the pipeline and was subject to
several conditions, one of which required that Du Pont
have a proper NPDES permit governing the effluent dis-
charge.
The Plaintiff, Save the Bay, Inc., brought suit pur-
suant to the National Environmental Policy Act (NEPA)
4a
against the United States Army Corps of Engineers,
the United States Army, Colonel Drake Wilson, Mobile
District Office of the Corps of Engineers, and Du Pont
seeking declaratory and injunctive relief and monetary
damages. The case was referred to the United States
Magistrate by the District Judge and thereafter the
defendant’s Motions for Summary Judgment were granted
and judgment was entered December 16, 1977 ne
the complaint with prejudice.
STANDING
Save the Bay’s complaint alleges that it is a nonprofit
corporation organized under the laws of the State of
Mississippi; that its membership is primarily composed
of numerous full-time and part-time residents of Harri-
son and Hancock Counties in the State of Mississippi;
and that its members will be adversely affected econom-
ically, aesthetically and environmentally.
Appellee Du Pont urges on appeal that Save the Bay
has failed to establish standing under § 10 of the Ad-
ministrative Procedures Act, 5 U.S.C. § 702. Specifically,
Du Pont argues that under Sierra Club v. Morton, 405
U.S. 727, 92 S.Ct. 1861, 31 L.Ed.2d 636 (1972) and
United States v. SCRAP, 412 U.S. 669, 93 S.Ct. 2405, 37
L.Ed.2d 254 (1973), Save the Bay must allege that its
members “use” the area and that the proposed federal
action will significantly affect their “use”. Du Pont’s
reliance on Sierra Club v. Morton, supra, is misplaced.
Here, the Plaintiff has alleged economic, aesthetic and
environmental injury to its members and clearly has
gone beyond mere general allegations of grievance on
behalf of the public interest. Du Pont’s argument, that
failure to specifically allege “usage” of the geographic
area is fatal to Plaintiff’s standing, is without merit. An
obvious inference of the English language is that resi-
dents of a geographical area “use” that geographical
5a
area. An allegation of residence coupled with an allega-
tion of injury caused by federal action affecting the area
of that residence clearly demonstrates that the party
seeking review is among those injured. We fail to see.
how the acts of camping, hiking, fishing or sightseeing,
in a particular geographic location, held sufficient for
standing in United States v. SCRAP, supra, can be con-
sidered more relevant for purposes of standing than can
the act of residing in a particular geographic location.
REASONABLENESS OF THE CORPS’ DECISION
The Court below noted that the standard for review
of an agency determination that an Environmental Im-
pact Statement need not be prepared is whether such
determination is reasonable. This standard was set forth
by this Court in Save Our Ten Acres v. Kreger, 472 F.2d
463 (5th Cir. 1973). If the determination is reasonable
and made objectively and in good faith on a reviewable
environmental record, the determination must be upheld.
The Court below found that the environmental assess-
ment prepared by the Corps completely and fully ad-
dressed the possible environmental consequences, that the
assessment was based on substantial evidence, and that
Corps complied with appropriate federal statutes and
regulations. Appellants contend that the Corps’ de-
termination was unreasonable. They argue that the
testimony and evidence offered in opposition to the build-
ing of the pipeline and plant should compel the conclu-
sion that an EIS is required. The Appellants further
argue that the Corps abdicated its responsibilities by
failing to conduct independent studies and by consider-
ing the evaluations of other governmental agencies con-
cerning the pipeline’s potential adverse effects.
We do not agree with Appellant’s contentions. With-
out detailing every point and counter-point of evidence
before the Corps, it is clear that the Corps had testi-
mony, evidence and comments from individuals and gov-
6a
ernmental agencies which could lead it to reasonably
conclude that an EIS would not be necessary. The Corps
received and reviewed comments from several govern-
mental agencies‘ as well as from quasi-governmental and
business organizations. With little exception, all com-
ments from governmental agencies indicated there would
be no significant adverse impact on the environment. We
cannot agree with Appellant that consulting with these
agencies was improper. The National Environmental
Policy Act, 42 U.S.C. § 4332(2)(C) requires that federal
agencies consult with other agencies whose area of ex-
pertise is superior to their own. Of course, this should
not be understood as allowing the Corps to base their
determination solely on the comments of other agencies.
Perhaps the most basic requirement of NEPA is that all
federal agencies make an independent environmental
assessment of the proposed action. The Court below cor-
rectly recognized this in distinguishing this case from
Mahelona v. Hawaiian Electric Company, 418 F.Supp.
1328 (D. Hawaii 1976) wherein the Corps of Engineers
erroneously considered the advisements of the EPA as
determinative and consequently failed to independently
determine whether or not the proposed action would
have a significant impact on the human environment.
For these reasons we hold the Corps’ decision was not
unreasonable.
1 Among those agencies were the following: the Environ-
mental Protection Agency, the Department of Interior, Fish
and Wildlife Service, the Department of Commerce, the Na-
tional Oceanic and Atmospheric Administration, the Missis-
sippi Marine Resources Council, the Mississippi Air and
Water Pollution Control Commission, and the Mississippi
State Clearing House for Federal Programs.
Ta
A MAJOR FEDERAL ACTION?
Appellants contend the court below erred in not finding
the grant of the pipeline construction permit was a
“major Federal action significantly affecting the quality
of the human environment’, under 42 U.S.C. § 4832(2)
(C), and therefore requiring preparation of an EIS. In
furtherance of this contention they argue that granting
almost any Federal permit to this massive multimillion
dollar manufacturing plant should trigger the obliga-
tions of NEPA.
The Court below held that the provisions of NEPA
must be read in context of other language in the Federal
Water Pollution Control Act (FWPCA), 383 U.S.C.
§ 1251 et seq., which places control of water pollution
caused by discharges of effluents in the hands of the
states and the EPA. United States v. SCRAP, supra. The
court went on to hold, citing Sierra Club v. Hodel, 544
F.2d 1036 (9th Cir. 1979) and Port of Astoria v. Hodel,
8 ERC 1156, aff’d 595 F.2d 467 (9th Cir. 1979), that
the issuance of the Corps’ permit was not a sufficient
nexus between the Corps and construction of the Du Pont
plant to make the Corps a partner in such construction
and thereby “federalize” the construction of the Du Pont
plant. In other words, the granting of the pipeline per-
mit by the Corps was not a “major Federal action” within
the meaning of NEPA.
In addition to the Court’s holding, it should also be
noted that FWPCA, 33 U.S.C. § 1871(c) (1),? ordinarily
283 U.S.C. §1871(c)(1) and (2) provides as follows:
(c) (1) Except for the provision of Federal financial assist-
ance for the purpose of assisting the construction of publicly
owned treatment works as authorized by section 1281 of this
title, and the issuance of a permit under section 1342 of this
title for the discharge of any pollutant by a new source as de-
fined in section 1316 of this title, no action of the Adminis-
8a
prohibits the issuance of a NPDES permit from being
deemed a major Federal action significantly affecting the
quality of the human environment within the meaning
of NEPA. Furthermore, § (c) (2) prohibits Federal agen-
cies, under guidance of NEPA, from reviewing any ef-
fluent limitation under a NPDES permit or from im-
posing any effluent limitation as a condition precedent to.
issuance of a license.
The decision of the Court below in no way held that
the Corps was precluded from preparing an EIS because
of FWPCA, but instead held that the Corps’ determina-
tion, of whether or not issuance of the construction per-
mit was a “major Federal action’, was limited to con-
struction and operation of the pipeline itself and correctly
held that the environmental consequences of the effluent
was a factor to be excluded from their consideration.
In reaching our conclusion on this point we are not
unmindful of the impact that building of this massive
manufacturing plant will have on the people of Harrison
trator taken pursuant to this chapter shall be deemed a major
Federal action significantly affecting the quality of the human
environment within the meaning of the National Environ-
mental Policy Act of 1969 (88 Stat. 852); and (2) Nothing
in the National Environmental Policy Act of 1969 (83 Stat.
852) shall be deemed to—
(A) authorize any Federal agency authorized to
license or permit the conduct of any activity which may
result in the discharge of a pollutant into the navigable
waters to review any effluent limitation or other require-
ment established pursuant to this chapter or the ade-
quacy of any certification under section 1341 of this title,
or
(B) authorize any such agency to impose, as a con-
dition precedent to the issuance of any license or permit,
any effluent limitation other than any such limitation
established pursuant to this chapter.
9a
and Hancock Counties, but the requirements of NEPA
do not reach private acts—only “major Federal actions.”
We fail to see how granting of the pipeline construc-
tion permit, after issuance of a valid NPDES permit,
can be considered a major Federal action. An examina-
tion of the guidelines issued by the Council on Environ-
mental Quality, 40 C.F.R. 1500.6(c), indicates that a
private project does not become a “major Federal action”
merely because of some incidental federal involvement.
In this case, the pipeline itself was not a necessity for
operation of the plant. At least one alternative method
of discharge, not requiring any Corps permit, was avail-
able to Du Pont. We are not saying that the requisite
Federal action must be a condition precedent to private
action in order for preparation of an EIS to be required.
But we do hold that in order for there to exist “major
Federal action” some greater involvement, than is
present in the case at hand, must exist.
THE PIPELINE OR THE WHOLE PLANT?
Appellant’s most vigorously argued point on appeal
and perhaps the point which would control the outcome
of this case contests the Corps looking only to the en-
vironmental consequences of the pipeline construction
and maintenance instead of considering the entire Du
Pont project in its decision on whether or not to prepare
an EIS.’ Appellants assert that narrowing the scope of
inquiry to the pipeline construction alone is the “blinder”
approach which should be rejected by this Court. By
analogy they compare the Du Pont facility to a living
organism which at one end eats chlorine gas and at the
other end excretes hydrocloric acid, iron, chromium, zinc,
and other nastiness to the tune of 2,000,000 gallons per
day. Their argument is that but for the permit there
8 We express no opinion as to the proper scope and extent
of coverage of an EIS should one have been necessary.
10a
would be no pipeline; without the pipeline there would
be no excretion; without the ability to excrete the plant
would suffocate in its own waste. They argue that the
permit “enables” the plant to exist and therefore the
entire plant should be taken into consideration in whether
or not the pipeline construction permit should be issued.
In support of this “Enablement Theory”, appellants cite
Port of Astoria v. Hodel, swpra, Mahelona v. Hawaiian
Electric Company, Inc., supra, and Citizens for Clean
Air, Inc. et al. v. United States Army Corps of Engineers
et al., 349 F.Supp. 696 (S.D.N.Y.1972).
Upon review of these cases, this Court does not dis-
agree with their reasoning but the circumstances of those
cases are clearly distinguishable from those before us.
The case of Citizens for Clean Air preceded the FWPCA
Amendments of 1972 and therefore is no longer sup-
portive of the proposition advanced here. In Port of
Astoria there existed a long-term contractual relation-
ship between a Federal agency and a private corporation
in which the proposed private manufacturing plant was
entirely dependent upon electrical power to be supplied
by the Federal agency. In Mahelona the problem was not
that the Corps failed to examine the effects of the electri-
cal generating plant, but rather failed to review the con-
sequences of its own construction permit allowing a
wastewater discharge facility. In short, the results of
these cases do not compel the conclusion which the Ap-
pellants desire. Absent facts or circumstances which are
not present here, we decline to hold that NEPA required
the Corps as a matter of law to consider the entire Du
Pont facility in determining whether or not an EIS was
necessary.
AFFIRMED.
This is a copy of a public record, reproduced as it was published. It is not legal advice, and it may not be the version a court would rely on. Check the official source before you cite it.