IN THE

Supreme Court of the United | Shaker oon. ie. cure

Octoser Term, 1979

No. 79-1643

MARGARET E. BOSCO,

Petitioner,

US.

ECKARDT C. BECK, Region II Administrator, U. S. ENVIRONMENTAL

PROTECTION AGENCY; DOUGLAS COSTLE, as Administrator,

U. S. ENVIRONMENTAL PROTECTION AGENCY; JERRY F.

ENGLISH, as Commissioner, N. J. DEPARTMENT OF ENVIRON-

MENTAL PROTECTION; PEQUEST RIVER MUNICIPAL UTIL-

iTIES AUTHORITY (WARREN COUNTY) and TOWN OF

BELVIDERE,

Respondents.

On Petition for a Writ of Certiorari to the United States

Court of Appeals for the Third Circuit

BRIEF OF RESPONDENT JERRY F. ENGLISH,

COMMISSIONER, NEW JERSEY DEPARTMENT

OF ENVIRONMENTAL PROTECTION

IN OPPOSITION

JOHN J. DEGNAN,

Attorney General of New Jersey,

Attorney for Jerry F. English, Commissioner,

New Jersey Department of Environmental

Protection,

State House Annex,

Trenton, New Jersey 08625.

ERMINIE L. CONLEY,

Assistant Attorney General,

Counsel.

DENNIS J. KRUMHOLZ,

Deputy Attorney General,

On the Brief.

Adams Press Corp., 5 Commerce Street, Newark, N. J. 07102—(201) 623-8611

TABLE OF CONTENTS

CoUNTER-STATEMENT OF ISSUES PRESENTED .......-..-.--------

CoOUNTER-STATEMENT OF THE CASE .

ArGUMENT—The Supreme Court should deny the

petition for writ of certiorari because the Dis-

trict Court’s decision that the determination of

the Environmental Protection Agency to issue a

Negative Declaration and Environmental Impact

Appraisal was neither arbitrary and capricious nor

unreasonable presents no undecided legal issues

nor factual disputes not correctly decided below

and because the particular facts contained in this

record have no larger significance beyond this case

a nda adeangaenabanaane

Cases Cited

Minnesota Public Interest Research Group v. Butz,

498 F. 2d 1314 (Sth Cir. 1974) 0...

Sierra Club v. Froehlke, 534 F. 2d 1289 (9th Cir.

IE icis.sesesciniiniadenicechsseeecoacacamectigesaisniiteaieanasspharadeeelincees

Statutes Cited

New Jersey Clean Waters Bond Act of 1976 -.............

33 U.S.C. See. 1251 et seg. (Federal Water Pollution

SI BS sieeiiccceniancineeetiiineninintdaainsn

| | Rea ATER SNES ERE a Ee ee

a, SOUR a Beek

li YABLE OF CONTENTS

42 U.S.C. See. 4821 et seq. (National Environmental

Policy Act of 1969) ........

See. 4332(2)(c¢) .....

Regulation Cited

40 C.F.R.:

See. 6.102(e) an

See. 6.204

See. 6.212(b)(2) ..

See. 6.500 et seq.

Sec. 6.512(a) .........

PAGE

bo

1@ 2)

CO —- FH WwW Ww

IN THE

Supreme Court of the United States

OctoserR Term, 1979

No. 79-1643

>.

a

MARGARET E. BOSCO,

Petitioner,

Vv.

ECKARDT C. BECK, Region IT Administrator, U. S.

ENVIRONMENTAL PROTECTION AGENCY ; DOUG-

LAS COSTLE, as Administrator, U. S. ENVIRON-

MENTAL PROTECTION AGENCY; JERRY F.

ENGLISH, as Commissioner, N. J. DEPARTMENT

OF ENVIORNMENTAL PROTECTION; PEQUEST

RIVER MUNICIPAL UTILITIES AUTHORITY

(WARREN COUNTY) and TOWN OF BELVIDERE,

Respondents.

On Petition for a Writ of Certiorari to the United States

Court of Appeals for the Third Circuit

i.

———

BRIEF OF RESPONDENT JERRY F. ENGLISH,

COMMISSIONER, NEW JERSEY DEPARTMENT

OF ENVIRONMENTAL PROTECTION

IN OPPOSITION

Counter-Statement of Issues Presented

Should the Petition for Writ of Certiorari be granted

where the District Court and the Court of Appeals both

upheld the determination of the Environmental Proteec-

tion Agency that no Environmental Impact Statement

was necessary for the approval of a grant for sewerage

collection and treatment facilities where the decisions

below comport with existing federal law and raise no

significant issues of law or fact?

Counter-Statement of the Case

This is an action brought by petitioner Margaret E.

Boseo pursuant to the National Environmental Policy

Act of 1969 (hereinafter “NEPA”), 42 U.S.C. $4821 et

seq., seeking injunctive relief restraining respondents from

building sewerage collection and treatment facilities in

and around Belvidere, New Jersey, without the prepara-

tion of a complete Ervironmental Impact Statement (here-

inafter “EIS”). Petitioner contends that NEPA requires

the filing of an EIS, 42 U.S.C. §4832(2)(e), because the

construction of the sewerage facilities is a major federal

action significantly affecting the quality of the human

environment.

The Federal Water Pollution Control Act, 33 U.S.C.

§1251 et seq., establishes the EPA grant program for the

construction of publicly owned sewerage treatment works

and forms the statutory basis for construction of the

sewerage treatment plant and collection system at issue

in this litigation. 33 U.S.C. §1291(1) and (2). This statute

authorizes EPA to make grants to any state, municipality

or intermunicipal or interstate agency for the planning,

design and construction of wastewater treatment facilities

and collection systems and to provide up to 75% of the

eligible costs of construction. The State of New Jer-

sey, through the New Jersey Clean Waters Bond Act of

1976, has agreed to provide 8% of the funding for the

present projects.

Current EPA regulations require an applicant for a

wastewater treatment works construetion grant to sub-

mit an environmental assessment with the facilities plan

developed under a Step 1 grant. 40 C.F.R. §6.512(a). This

environmental assessment must include a description of

the environmental impacts of the project, a deseription

of the steps taken to minimize any adverse environmental

effects, an evaluation of feasible alternatives, a descrip-

tion of the existing and future environment without the

project and documentation of these findings. 40 C.F.R.

$6.512(a). The EPA then reviews this environmental as-

ssessment and determines whether significant environ-

mental impacts are expected from the proposed action,

whether feasible alternatives can be adopted or changes

made in project design to eliminate adverse impacts and

whether an EIS or a Negative Declaration is to be filed.

40 C.F.R. $6.204.

If EPA determines, as it did in the present action, that

the proposed sewerage collection and treatment facilities

will not have a significant impact upon the environment,

it issues a Negative Declaration together with an Envir-

onmental Impact Appraisal. The Negative Declaration

is a written announcement prepared after EPA’s environ-

mental review stating that the EPA has determined that

an KIS is not required for the proposed project. 40 C.F.R.

§6.102(e). The Environmental Impact Appraisal (here-

inafter “EIA”) is prepared concurrently with the Nega-

tive Declaration and briefly describes the proposed action

and feasible alternatives, environmental impacts of the

4

project, unavoidable adverse impacts of the action, the

relationship between the short-term uses of man’s envir-

onment and the maintenance and enhancement of long-

term productivity, steps to minimize harm to the environ-

ment, irreversible and irretrievable commitments of re-

sources necessary to implement the action, comments and

consultation to the project and reasons for concluding

that the proposed action will not have a significant en-

vironmental impact. 40 C.F.R. §6.212(b) (2).

The Warren County-Pequest River Sewerage Authority

submitted to the DEP in 1975 its proposed plan of study

of the region’s wastewater management options. The

DEP approved and certified this planning application in

April, 1975 and the EPA approved the Authority’s ap-

plication for a Step I grant for the preparation of the

Facilities Plan in July, 1975.

The full Wastewater Facilities Plan for the Pequest

River Drainage Basin was issued preliminarily to EPA,

DEP, the Authority and to the general public for com-

ment in May, 1976. This Plan provides a comprehensive

discussion and analysis of engineering and environmental

concerns relating to wastewater treatment in the Pequest

River drainage basin area and it develops and evaluates

possible alternatives to its proposals. The Facilities Plan

concludes that two regional facilities—one in Oxford

Township and the other in White Township and serving

the Town of Belvidere directly adjacent to this facility

—would provide the most environmentally sound and cost

effective method of sewerage treatment.

A public hearing was held concerning the Facilities Plan

in May, 1976 pursuant to EPA regulations for compliance

with NEPA in the Title Il Wastewater Treatment Works

Construction Grants Program, 40 C.F.R. §6.500 et seq.,

and a subsequent hearing concerning only the Belvidere

collection system was held in August, 1976. The only

questions raised at the initial hearing concerned the claim

that some of the public did not have adequate time in

which to read the Facilities Plan; the Authority fully

responded to written questions posed by interested per-

sons subsequent to the second hearing.

The EPA issued its Negative Declaration and Environ-

mental Impact Appraisal for the Belvidere treatment plant

and collection system on September 8, 1978. it is this deci-

sion by the EPA which petitioner challenges; the Oxford

project is not at issue in the present lawsuit.

No comments or objections were submitted to the HPA

for the consideration within fifteen (15) day comment

period provided upon the issuance of the Negative Decla-

ration and therefore no further hearing was required.

An additional public meeting, not required by law, was

held by the EPA in February, 1979, subsequent to which

the EPA upheld its determination of a Negative Declara-

tion in a nineteen (19) page letter sent to all interested

parties.

On June 12, 1979 petitioner filed a complaint in the

United States District Court for the District of New

Jersey challenging HPA’s issuance of a Negative Declara-

tion and on June 22, 1979 she filed a motion for prelim-

inary injunction. On the return date of August 21, 1979

the Honorable Clarkson S. Fisher, U.S.D.J., with the

consent of all parties, ordered the trial of this action

on the merits to be advanced and consolidated with peti-

tioner’s injunction application. Judge Fisher’s Order and

Judgment in this matter was filed August 30, 1979 deny-

ing petitioner’s application for injunctive relief and dis-

missing her complaint. In his opinion, filed simultane-

ously, Judge Fisher determined that petitioner had failed

to demonstrate that EPA’s decision to file a Negative

6

Declaration and an Environmental Impact Appraisal was

either arbitrary and capricious or unreasonable (Pet. App.

35-72). The Third Circuit affirmed the decision of the

District Court without opinion on January 18, 1980 (Pet.

App. 34).

The Town of Belvidere commenced construction of the

collection system portion of this project on October 15,

1979.

ARGUMENT

The Supreme Court should deny the petition for writ

of certiorari because the District Court’s decision that

the determination of the Environmental Protection

Agency to issue a Negative Declaration and Environ-

mental Impact Appraisal was neither arbitrary and

capricious nor unreasonable presents no undecided

legal issues nor factual disputes not correctly decided

below and because the particular facts contained in this

record have no larger significance beyond this case.

This case presents no undecided legal issues nor any

factual disputes which were not correctly and conclu-

sively decided by the District Court and affirmed without

opinion by the Third Circuit. Petitioner’s assertions of

error in the lower courts are plainly incorrect but, even

assuming them to be true, the decision in this case turns

solely upon the particular facts contained in this record

and has virtually no greater importance beyond this ease.

The initial Question Presented by the petitioner, whether

the decision of the District Court is in error because it

applies the “arbitrary and capricious” standard of re-

view instead of a “reasonableness” test to its review of

the EPA’s decision to issue a Negative Declaration, is

not raised by the decision below. The District Court

reviewed the determination of the HPA not to issue an

EIS under the “arbitrary and capricious” standard (Pet.

53) but it also explicitly examined EPA’s decision under

the more rigorous “reasonableness” test as well (Pet.

App. 67). While petitioner correctly asserts that there

may be some difference among the United States Cireuit

Courts as to which of the foregoing standards of review is

to be applied under NEPA in reviewing the activities of

federal agencies, compare, e. g. Minnesota Public Interest

Research Group v. Butz, 498 F. 2d 1814 (8th Cir. 1974) (en

bane) and Sierra Club v. Froehlke, 534 F. 2d 1289 (9th

Cir. 1976), the District Court’s finding that the Inviron-

mental Impact Assessment issued by the KPA passes

muster under both standards of review eliminates all

ambiguity and potential question of law and necessarily

removes this issue as a basis for granting the petition

for certiorari.

The third and fourth Questions Presented by the peti-

tion for certiorari concern allegations of conflict of inter-

est, undue pressure and political intervention associated

with the sewerage treatment works. The record is totally

devoid of any evidence beyond petitioner’s unsubstan-

tiated assertions at oral argument before the District

Court that there is any conflict of interest whatsoever on

the part of any individual which in any way affects the

decision of the EPA to proceed with the funding and

construction of this project. The District Court correctly

found that petitioner’s allegations were unsubstantiated

by facts and, moreover, that they are irrelevant to the

question presented to the Court (Pet. App. 67).

Petitioner’s assertion as stated in her second Question

Presented, that the District Court’s determination to uphold

8

the EPA decision to issue an Environmental Impact Assess-

ment is not supported by the evidence, finds no support

in the record and is plainly insufficient to warrant the

granting of this petition. The record in this case clearly

reveals that EPA has closely examined the proposed

sewerage collection and treatment facilities and has found

that they will not result in significant environmental im-

pacts. The EIA prepared by EPA and submitted with

the Negative Declaration specifically determined that the

installation of the sewerage system will not contravene

either state or federal air quality standards, that noise

levels due to actual operation of the system will not be

significant and will be contained within the isolated area

of the pumping station, that the construction of the

pumping station will have minimum impacts upon the

natural resources of the area and that the project will

not impact upon any critical areas. The EIA discusses

five alternatives to the present project before conelud

ing that the present plans are most acceptable, it inci-

cates that eleven separate steps to minimize the impact

upon the environment will be taken during construction

and its states that all affected areas will be restored to

a condition at least comparable to what existed prior to

construction. The record demonstrates that each of the

five (5) environmental impacts alleged by petitioner in

the District Court to be “significant” and thus to necessi-

tate the filing of a full EIS, see 42 U.S.C. $4332(2)(e),

including reduction in groundwater recharge, alignment

of the collection system, disruption of the Pophandusing

Brook and increased river turbulence at the treatment

plant outfall, was found by the EPA and upheld by the

District Court to be insignificant and in fact contradicted

by the express findings of the Environmental Impact As-

sessment.

The one specific error of the District Court alleged in

the petition for certiorari, that the District Court’s con-

clusion that a single internal contradiction in the environ-

mental impact assessment concerning the impact of odors

produced by the proposed treatment plant is attributable

to “sloppy draftsmanship” and not an error of fact (Pet.

21-22), is maifestly unsupported in the record. The

District Court found on this issue that EPA had given

“serious consideration” to the odor problem and that the

use of certain devices would render this impact “insig-

nificant” (Pet. App. 63). |

Because the factual issues presented by the record were

all decided correctly below and, in any event, have no

importance beyond the present case, and because this case

presents no undecided legal issues, there is no basis for

the granting of the petition for writ of certiorari.

CONCLUSION

For ‘hese reasons, the petition for writ of certiorari

should be denied.

Respectfully submitted,

JoHN J. DEGNAN,

Attorney General of New Jersey

Attorney for Respondent Jerry

F. English, Commissioner, New

Jersey Department of Envi-

ronmental Protection.

By Erminiz L. Contey,

Assistant Attorney General

Dennis J. KruMHoLz,

Deputy Attorney General,

On the Brief.

This is a copy of a public record, reproduced as it was published. It is not legal advice, and it may not be the version a court would rely on. Check the official source before you cite it.

A word about cookies

We need a few to keep you signed in and the library working. The rest help us see which pages people use and where they get stuck. They stay off unless you say yes.