Appendix — Tennessee Gas Pipeline Co. v. Federal Energy Regulatory Commission

Supreme Court brief1980

Ask Donna

What actually matters in this document.

Text

‘Gupreme Court, U. &,

EILED

DEC 19 1979

“BICHABL ROBAK, JR., CLERR.

IN THE

Supreme Cowt of the United States

OcToBER TERM, 1979

_79-962*

No.

TENNESSEE GAS PIPELINE COMPANY,

a Division of Tenneco Ince.,

Petitioner,

v.

FEDERAL ENERGY REGULATORY COMMISSION,

Respondent.

APPENDIX TO

PETITION FOR A WRIT OF CERTIORARI TO THE

UNITED STATES COURT OF APPEALS FOR THE

DISTRICT OF COLUMBIA CIRCUIT

MELVIN RICHTER

Harowp L. TALISMAN

DALE A. WrIGHT

LitTMAN, RICHTER, WRIGHT

& TALISMAN, P.C.

1050 17th Street, N.W., Suite 600

Washington, D.C. 20036

MICHAEL R. WALLER

General Counsel

P.O. Box 2511

Houston, Texas 77001

Attorneys for

Tennessee Gas Pipeline Company,

a Division of Tenneco, Inc.

Press or Byron S. ADAMS PRINTING, INC., WASHINGTON, D. C.

jew a Se etree Nana te

APPENDIX

APPENDIX

APPENDIX

APPENDIX

APPENDIX

INDEX TO APPENDIX

co taeda

SRA Sea I Ne 6 Fe nnn

APPENDIX A

Muited States Court of Appeals

FOR THE DISTRICT OF COLUMBIA CIRCUIT

No. 77-1496

TENNESSEE GAS PIPELINE COMPANY,

a division of Tenneco Inc., PETITIONER

Vi

FEDERAL ENERGY REGULATORY COMMISSION, RESPONDENT

PUBLIC SERVICE COMMISSION OF THE STATE OF NEw YorRK

ENTEX, INC.

COLUMBIA GAS TRANSMISSION COMPANY

PUBLIC SERVICE ELECTRIC AND GAS COMPANY

NORTHERN ILLLINOIS GAS COMPANY

NEW ENGLAND CUSTOMER GROUP (BAY STATE GAs Co.),

INTERVENORS

No. 77-1498

PUBLIC SERVICE COMMISSION OF THE STATE OF NEW YorK,

PETITIONER

V.

FEDERAL ENERGY REGULATORY COMMISSION, RESPONDENT

la

2a

TENNESSEE GAS PIPELINE COMPANY

COLUMBIA GAS TRANSMISSION CORPORATION

NEW ENGLAND CUSTOMER GROUP, ET AL.

NORTHERN ILLINOIS GAs Co.

PUBLIC SERVICE ELECTRIC AND GAS CO., INTERVENORS

No. 77-1653

INTERSTATE NATURAL GAS ASSOCIATION OF AMERICA,

PETITIONER

Vv.

FEDERAL ENERGY REGULATORY COMMISSION, RESPONDENT

COLUMBIA GAS TRANSMISSION CORP.

TENNESSEE GAS PIPELINE Co.

PUBLIC SERVICE ELECTRIC AND GAS Co.

PUBLIC SERVICE COMMISSION OF THE STATE OF NEW YORK,

INTERVENORS

No. 77-1712

TRANSCONTINENTAL GAS PIPE LINE CORPORATION,

PETITIONER

Ve

FEDERAL ENERGY REGULATORY COMMISSION, RESPONDENT

COLUMBIA GAS TRANSMISSION CORP.

UNITED CITIES GAS COMPANY

PUBLIC SERVICE ELECTRIC & GAS COMPANY

TENNESSEE GAS PIPELINE Co.

PUBLIC SERVICE COMMISSION OF THE STATE OF NEW YORK,

INTERVENORS

- a eed

bo ia al CAE aS ANS NANA tle dere oy na eee Ne EA) tee - SOK, NeAdscndlen ett —

jay NO re pet

3a

No. 77-1719

MICHIGAN WISCONSIN PIPE LINE COMPANY, PETITIONER

Vv.

FEDERAL ENERGY REGULATORY COMMISSION » RESPONDENT

WISCONSIN NATURAL GAS Co.

ASSOCIATED NATURAL GAS Co.

MICHIGAN GAS UTILITIES CO., INTERVENORS

Petitions for Review of Orders of the

Federal Energy Regulatory Commission

Argued September 29, 1978

Decided June 20, 1979

Harold L. Talisman with whom Melvin Richter, Dale

A. Wright, Patricia A. Curran, Terence J. Collins, Greg-

ory Grady and Lilyan G. Sibert were on the brief, for

Tennessee Gas Pipeline Company, petitioner in No. 77-

1496, intervenor in Nos. 77-1498, 77-1658 and 77-1712

and amicus curiae in No. 77-1719.

Richard J. Flynn with whom Frederic G. Berner, Jr.

and Charles V. Shannon were on the brief, for Michigan

Wisconsin Pipe Line Company, petitioner in No. 77-1719

and amicus curiae in No. 77-1496.

Thomas F. Ryan, Jr. with whom Robert G. Hardy

was on the brief, for Transcontinental Gas Pipe Line

Corporation, petitioner in No. 77-1712.

Edward W. Hengerer and Norman A. Pedersen, At-

torneys, Federal Energy Regulatory Commission, with

whom Howard E. Shapiro, Solicitor, and Philip R. Tel-

arm

4a

leen, Attorney, Federal Energy Regulatory Commission,

were on the brief, for respondents.

Richard A. Solomon with whom Peter H. Schiff and

Sheila S. Hollis were on the brief, for Public Service

Commission of the State of New York, petitioner in No.

77-1498 and intervenor in Nos. 77-1496 and 77-1712.

Jerome J. McGrath, John H. Cheatham, III and J.

Evans Attwell were on the brief, for petitioner Inter-

state Natural Gas Association of America in No. 77-

1653.

John D. Daly and Giles D. H. Snyder and Stephen J.

Small were on the brief for intervenor Columbia Gas

Transmission Corporation in Nos. 77-1496, 77-1498, 77-

16538 and 77-1712.

Robert H. Gorske was on the brief, for intervenor

Wisconsin Natural Gas Company in No. 77-1719.

Irving Jacob Golub, Stephen A. Wakefield, William B.

Cassin and Phillip D. Endom were on the brief, for

amicus curiae United Gas Pipe Line Company in Nos.

77-1496, 77-1498 and 77-1653.

Also Allan Abbot Tuttle, Robert W. Purdue and Dennis

Lane, Attorneys, Federal Energy Regulatory Commission,

entered appearances for respondent.

Also Paul W. Fox and John W. Glendening, Jr. for

intervenor New England Customer Group in Nos. 77-

1496 and 77-1498.

Also J. Stanley Stroud entered an appearance for in-

tervenor Northern Illinois Gas Company in Nos. 77-

1496 and 77-1498.

Also Carl W. Ulrich, William R. Duff, Edward S.

Kirby and James R. Lacey entered appearances for in-

tervenor Public Service Electric and Gas Company in

Nos. 77-1496, 77-1498, 77-1653 and 77-1712.

ee int het hae ba ais saa

of 5a

Also Michael J. Manning and Patrick J. Keeley en-

tered appearances for intervenor Entex, Inc. in No. 77-

1496..

Also Jack M. Irion entered an appearance for inter-

venor United Cities Gas Company in No. 77-1712.

Also Richard M. Merriman, J. Richard Tiano and

Richard T. Witt entered appearances for intervenors

Associated Natural Gas Company and Michigan Gas

Utilities Company in No. 77-1719.

Before: LEVENTHAL and WILKEY, Circuit Judges, and

HAROLD GREENE,” District Judge, United

States District Court for the District of

Columbia.

Opinion for the Court filed by Circuit Judge LEVEN-

THAL, in which Circuit Judge WILKEY and District Judge

GREENE join.

Concurring opinion filed by Circuit Judge WILKEY.

LEVENTHAL, Circuit Judge: We consider petitions of

natural gas pipeline companies’ for review of Federal

Power Commission? rate making orders. The common

* Sitting by designation pursuant to 28 U.S.C. § 292(a)

(1976).

1 In addition to the principal pipeline petitioners, Tennessee

Gas Pipeline Company (No. 77-1496) (“Tennessee”), Trans-

continental Gas Pipe Line Corporation (No. 177-1712).

(“Transco”), Michigan Wisconsin Pipe Line Company (No.

77-1719) (“Michigan-Wisconsin’”’), there are petitions by the

Interstate Natural Gas Association of America (No. 77-1653)

(“INGAA”), Columbia Gas Transmission Corporation (In-

tervenor in No. 77-1496 et al.) (“Columbia”), and the Public

Service Commission of the State of New York (No. 77-1498)

(“PSC”). There also have been various cross-interventions

by the parties.

2 The Federal Power Commission went out of existence in

the fall of 1977. The Department of Energy Reorganization

Act of 1977, P.L. 95-91, 91 Stat. 565, codified at 42 U.S.C.

§§ 7107 ea seq. (1978), transferred most of the FPC’s func-

6a

element in these companion cases is the treatment of “ad-

vance payments,” pre-payments for future deliveries of

natural gas made by the pipelines in the context of an

experimental “advance payment program,” which was

designed to facilitate capital formation by producers to

finance development and production of additional gas

supplies, thus helping to alleviate the natural gas short-

_ age. In formulating “just and reasonable” pipeline rates

in each case, the Commission denied rate base treatment

for various expenditures. It deferred inclusion in rate

base for advance payments made during the test period

and not appropriately expended by the recipient produ-

cers within 30-days of the close of that period. We find

that the Commission failed to administer the advance

payment program with the required flexibility and thus

remand the treatment of advance payments for further

consideration. In certain respects, as will be noted, we

affirm the Commission’s other determinations.

I. FRONT-END ADVANCE PAYMENTS TO

DOMESTIC PRODUCERS

A. General Background

The unhappy saga of the advance payment pregram

has been detailed by this court on other occasions.* Con-

tions, including its rate making authority under both the

Federal Power Act and the Natural Gas Act, to the newly

created Federal Energy Regulatory Commission (FERC). 42

U.S.C.A. §§ 7172(a) (1) (B), (C) (1977). This change in

administration has no effect on the instant litigation, save for

the appropriate substitution of parties.

3 See The Second National Natural Gas Rate Cases, 186

U.S.App.D.C. 23, 59-64, 567 F.2d 1016, 1052-57 (1977), cert.

denied, 435 U.S. 907 (1978); United Gas Pipe Line Co. v.

FPC, 179 U.S.App.D.C. 274, 276, 551 F.2d 460, 462 (1977) ;

Michigan Wisconsin Gas Pipe Line Co. v. FPC, 171 U.S.App.

D.C. 352, 353-54, 520 F.2d 84, 85-86 (1975); Public Service

Com’n, State of N.Y. v. FPC, 167 U.S.App.D.C. 100, 511 F.2d

338 (1975) [hereafter cited as “PSC (Advance Payments)

NG itl AY RAT RIE Sit Nihal Ss cairn, eae

ee eet re

Ta

ceived as one method of alleviating the impending natural

gas shortage, the program was initiated in 1970 and

was governed successively by a series of five “advance

payment orders” until its termination at the end of

1975.‘ As originally formulated and approved by this

court, the program was designed to facilitate capital

formation by producers to finance development and pro-

duction of new gas supplies.’ It was contemplated that

pipelines would provide production capital in the form

II’’]; Public Service Com’n, State of N.Y. v. FPC, 151 U.S.

App.D.C. 307, 467 F.2d 361 (1972) [hereafter cited as “PSC

(Advance Payments) I’’].

Order No. 410, Accounting and Rate Treatment of Ad-

vance Payments to Suppliers for Gas and Amending F.P.C.

Form No. 2, Docket No. R-380, 44 FPC 1142 (1970) (gov-

erning advances made pursuant to contracts entered after

October 2, 1970) [hereafter cited as “Order No. 410”] ; Order

No. 410-A, Accounting and Rate Treatment of Advance Pay-

ments to Suppliers for Gas, and Amending F.P.C. Form No.

2, Docket No. R-380, 45 FPC 135 (1971) (amending the treat-

ment of advance payments governed by Order No. 410) [here-

after cited as “Order No. 410-A”’] ; Order No. 441, Accounting

and Rate Treatment of Advance Payments to Suppliers for

Exploration and Lease Acquisition of Gas Producing Proper-

ties, Docket No. 4-411, 46 FPC 1178 (1971) (governing ad-

vance payments contracts executed between November 10,

1971 and December 31, 1972) [hereafter cited as “Order No.

441”]; Order No. 465, Accounting and Rate Treatment of

Advance Payments Included in Account 166, Advance Pay-.

ments for Gas Development and Production, Docket No.

R-411, 48 FPC 1550 (1972) (governing contracts executed

between January 1, 1973 and December 31, 1973) [hereafter

cited as “Order No. 465”]; Order No. 499, Accounting and

Rate Treatment of Advances Included in Account No. 166, Ad-

vances for Gas Exploration, Development and Production,

Docket No. RM74-4, 50 FPC 2111 (1973) (governing con-

tracts executed between January 1, 1974 and December 31,

1975) [hereafter cited as “Order No. 499’’].

5 PSC (Advance Payments) I, supra note 3, 151 U.S.App.

D.C. at 309, 467 F.2d at 363.

8a

of pre-payments to producers (advance payments) for

future deliveries of natural gas. The order launching

the program provided that such payments could be capi-

talized and included in the pipeline’s rate base subject

to qualifications, including the requirement that advances

must be “reasonable and appropriate.” * The orders also

specified those producer expenditures permissible under

the program (“qualifying expenditures”). Producers

could be expected to seek advance payments because the

advances would provide them with a source of interest-

free capital.’ It was anticipated that pipeline participa-

tion in the program also would be assured if pipeline

rates could reflect a return on qualifying advance pay-

ments.* Current purchasers from the pipeline would

shoulder, in the rates they paid, the “carrying charges”

on these interest-free loans to producers, though the

benefits from expansion of natural gas supplies would

6 Order No. 410, supra note 4, 44 FPC at 1144. Advance pay-

ments were to be drawn down and removed from Account 166,

Advance Payments for Gas, as gas deliveries commenced or

as the pipeline was reimbursed in consideration other than

gas. The significant express qualifications governing advances

under the various orders are described in note 34 infra.

7 See Order No. 465, supra note 4, 48 FPC at 1554.

8 The “cost” to the pipeline of an advance payment was

the cost of financing the amount advanced, a factor prin-

cipally determined by interest rates in the bond market. The

“cost” to rate payers was determined by the rate of return

allowed on the pipeline’s rate base. A differential between

the allowed rate of return and the prevailing interest rate

in capital markets provided some opportunity for successful

arbitrage, but as interest rates rose during the relevant period

this incentive was minimized. The principal incentive for

pipeline participation lay in their ability to secure gas reserves

for the future while transferring to the rate payer the added

cost of making pre-payments (advance payments) for the

gas.

9a

flow to future, not current, rate payers.’ This departure

from the usual rule of public utility regulation (that

current rates should reflect the cost of supplying service

to current rate payers) was thought justified by the

“public interest in enlarging the field supply of natural

gas, needed for existing facilities and contracts.”

The program was conditionally approved by this court

in Public Service Commission, State of New York v.

FPC [PSC (Advance Payments) I[]," as a “justifiable

experiment in the continuing search for solutions to our

nation’s critical shortage of natural gas.” Resolving

doubts in favor of the program, we stressed its experi-

® Qualifying advance payments had to be made prior to de-

liveries under the advance payment contract. See, e.g., Order

No. 465, supra note 4, 48 FPC at 1556. Substantial lag times

were inevitable between the date of the advance and its full

repayment in gas, especially if the advance were made to fund

exploration or other pre-production producer expenditures.

See id. at 1553 (FPC assumption that all pre-Order No. 441

advances are fully recovered on the average in five years, with

a one-year lag between the advance and commencement of

recoupment). Where “front-end” advances were involved, the

time between the date of advance and its full repayment in

gas was considerably extended. For example, most of the

advance payments excluded for a period from Tennessee’s

rate base, though advanced in 1973, were not even fully

utilized by the recipient producers until 1975, and the weighted

average lag time between the end of the applicable test period

and the date when Tennessee’s producers would require the

advance to cover costs was calculated to be 22.8 months. JA in

No. 77-1496, et al. at 254, 256 (testimony of Staff witness

Robert H. Benna, unrebutted by petitioners in this respect) ;

see FERC Br. in No. 77-1496, et al. at 36.

10 PSC (Advance Payments) I, supra note 3, at 316, 467

F.2d at 370.

11151 U.S.App.D.C. 307, 467 F.2d 361 (1972).

12 Id. at 317, 467 F.2d at 371 (on petition for rehearing).

10a

mental character and the need for flexibility and re:

evaluation as it evolved. We perceived the three ad-

vance payment orders that had been issued as of that

time * “as an on-going effort by the FPC to determine

experimentally the proper solution with regard to ad-

vance payments to help alleviate the gas shortage,” and

we were “impressed with the fact that the FPC [had]

demonstrated a willingness to assimilate criticism .. .

and adjust its treatment of advance payments to con-

form with the realities of the natural gas market.’ ™

We emphasized that the agency, in reaching “an accom-

modation of conflicting interests,’ was “making policy

decisions of the type it was created to make.” But

this judicial approval was predicated on the Commission’s

willingness to continue to respond to “the realities of the

natural gas market” and to modify the program in light

of accumulated experience. We reiterated these concerns

in our response to New York Public Service Commis-

sion’s petition for rehearing.’®

18 Orders No. 410, No. 410-A, and No. 441, supra note 4.

14 PSC (Advance Payments) I, supra note 3, 151 U.S.App.

D.C. at 3138, 467 F.2d at 367.

15 Id.

16 Jd. at 317, 467 F.2d at 371:

One of the important factors in reaching our decision

was the temporary character of the FPC order under

review (Order 441 remains in effect only through 31

December 1972), and our belief that it represented a

justifiable experiment in the continuing search for solu-

tions to our nation’s critical shortage of natural gas... .

Fundamental to the concept of any experiment is the

assumption that the data developed from the experience

thereunder will be subjected to meaningful review,

analysis, and evaluation before the expcrimental prac-

tice is allowed to continue or to become institutionalized

as a more permanent procedure. . . . We would accord-

ingly expect that the FPC will not continue, or extend

oe ——

1 la

The advance payment order approved by our March

1972 ruling in PSC (Advance Payments) I expired at

the end of that year. It was replaced in turn by the

two orders pertinent to the instant cases, Order No. 465,"

governing advance payments made during 1973, and

Order No. 499,'* governing the 1974-75 period. When

the program again came before this court in Public

Service Commission, State of New York v. FPC [PSC

(Advance Payments) II],’* we ruled that the Commis-

sion had failed in its obligation “to engage in ‘meaning-

ful review, analysis and evaluation’ of the experience

under the advance payments program” * and to “adjust

its treatment of advance payments to conform with the

realities of the natural gas market.’ *! In our view,

“(t]he data presented by the Commission as a justifica-

tion of its repeated extensions of the advance payments

program provide[d| an inadequate basis from which ‘to

determine whether its justifying objectives [were] being

satisfactorily met at an acceptable level of ultimate eco-

nomic cost to the nation’s gas consumers.’” ** Accord-

ingly, we remanded the record for further evidence and

the effective date of, the practices authorized by Order

441 without further proceedings in which New York and

all other interested parties will be given the opportunity

to demonstrate the effectiveness or the futility of this

experiment.

17 See note 4 supra.

18 See id.

19 167 U.S.App.D.C. 100, 511 F.2d 338 (1975).

20 Jd. at 104, 511 F.2d at 342 (quoting from PSC (Advance

Payments) I statement on petition for rehearing, note 16

supra).

21 Td. at 105, 511 F.2d at 343.

22 Id. at 104, 511 F.2d at 342 (quoting from PSC (Advance

Payments) I statement on petition for rehearing, note 16

supra).

12a

consideration by the FPC. In light of its subsequent

reevaluation, the agency allowed the program to expire

upon termination of Order No. 499 on December 31,

1975.8

Although the program has been terminated, existing

advance payment contracts retain their vitality,” and

continued administration is required as pipelines file with

the FERC for jurisdictional rate increases. In such rate-

making proceedings the Commission has been called upon

to determine whether specific advance payments qualify

for rate base treatment under the terms of the applicable

advance payment orders. This is the posture of the cases

here under review.

B. Nature of Front-end Advance Payments

The central controversy in these cases involves the

temporary exclusion from rate base of certain “front-

end advance payments” made in the United States.”

23 See Advances for Gas Exploration, Development and Pro-

duction, Docket Nos. R-411 & RM74-4 (orders issued Dec. 31,

1975 and Feb. 27, 1976).

24 Td.

25 The first of the two advance payment orders pertinent to

these cases restricted its coverage to advances made to pro-

ducers within the lower 48 states. Order No. 465, supra note

4, 50 FPC at 1555. The second pertinent order made accom-

modation for advances to producers in Alaska. Order No. 499,

supra riote 4, 50 FPC at 2116.

One of these cases, No. 77-1496 et al., also involves exclu-

sion from rate base of advances made to Canadian producers,

but the Commission’s decision was controlled by different

considerations since advances to producers on the North

American continent outside the United States were eligible

for rate base treatment but only on a case-by-case basis.

Advances to Suppliers for Gas Outside Continental United

States, Docket No. R-466, 38 Fed. Reg. 1055-56 (1973)

(notice of rulemaking). This issue is treated in section II-A

infra.

13a

These are a particular class of “advance payments.” In

general, the program provided for “advance payments”

in the sense that the payments were authorized to be

made in advance of the delivery of gas supplies. The

focus of concern in these cases is the so-called “front-

end advance payment,” which identifies a transfer to the

producer not only prior to gas deliveries, but also prior

to any producer expenditures associated with ultimate

production of the gas.

An advance payment has two aspects, and provides a

dual benefit to the recipient producer. First, it is a

source of capital, which supplements the funds available

to producers for development and production expendi-

tures. It is a loan, but one shaped as a pre-payment to

be credited against the purchase price of gas that will

flow from successful development efforts. Second, it is

an interest-free loan. When an advance payment sub-

stitutes for capital raised in financial markets, it re-

lieves the producer of financing costs. There is an extra

benefit to the producer in that the rate set for the pro-

ducer by the Commission incorporates an allowance for

financing cost, and no reduction in that rate is required

on account of the fact that part of the producer’s financ-

ing is cost-free.** Thus, advance payments provide a

26 See, e.g., JA in No. 77-1712 at 148-49, Transcontinental

Gas Pipe Line Corporation, Docket Nos. RP74-48 and PR75-3,

Presiding Administrative Law Judge’s Initial Decision on

Reserved Issues 31-32 (Dec. 22, 1975) [hereafter cited as

“Transcontinental Initial Decision’”] (“{T]he producer has

interest-free use of the funds until the day they must be spent

on eliciting gas, and this is a substantial bonus added to the

price he will receive for the gas from the pipeline. The pipe-

line receives no discount upon that pric2 because its funds

financed the producer’s venture. And the full price, commonly

the highest price permissible under FPC regulations, is ulti-

mately paid by the pipeline’s customers.”) ; JA in No. 77-1719

at 111, Michigan Wisconsin Pipe Line Co., Docket No. CP70-

14a

“bonus” to producers in the amount of the interest factor,

an amount which is never refunded.

In the Commission’s view, the objective of the advance

payment program was to expedite the development of

gas supply through the mechanism of providing pro-

ducers an additional source of capital. In theory, the

increased availability of capital would encourage invest-

ment, which in turn would yield additional gas supply.

The interest factor, and the “bonus” which it provided

to producers, has been construed as a subsidiary element

designed to provide incentive for producer participation,

a necessary cost to achieve the desired benefit.”

The Commission has come to focus on front-end ad-

vance payments as providing a still further bonus to the

producer—not only the interest-free availability of funds

during use for gas development, but their availability for

some period prior to the time of “qualifying expenditure”

by the producer. The Commission has recognized that

capital formation and the pertinent qualifying expendi-

ture may be facilitated by the transfer of an advance

to the producer a “reasonable time” prior to the expendi-

ture. However, the Commission has endeavored through

administration of the program to protect rate payers

from the cost of advance payments held by producers

for any “unreasonable” front-end period. Advance pay-

ments that were made (in the Commission’s view) an

“ynreasonable” time prior to their appropriate expendi-

22, Initial Decision Upon Inclusion of Advance Payments in

Rate Base 7 (Feb. 27, 1976) [hereafter cited as “Michigan-

Wisconsin Initia! Decision’’], JA in No. 77-1719 at 111 (“The

use of money for a period of time is itself worth money. The

advance payments at issue in this proceeding necessarily in-

volve the payment of substantial additional compensation to

the producers above and beyond the established price for gas

that they may discover and sell to the pipeline.’’).

27 See Order No. 465, supra note 4, 48 FPC at 1554.

15a

ture have been labeled “extravagant” by the agency. Since

the term “extravagant” begs the question, these pay-

ments will be referred to in this opinion as “extended

front-end advance payments” or “extended front-end

advances.”

C. The Critical Timing Requirement

Distilled to its essence, this case involves two ques-

tions: (1) whether the rate base treatment contemplated

by the program was inherently limited to advance pay-

ments made no more than a “reasonable time” prior to

their appropriate expenditure; and, (2) whether, if such

a limitation existed, the Commission acted within its

discretion in defining the permissible interval solely in

terms of traditional line-of-credit financing practices.

The timing element has assumed paramount impor-

tance due to the response of both pipelines and producers

to the realities of the natural gas market in the context

of the advance payment program. In an unregulated

economic environment, a period of supply shortage may be

expected to stimulate a rise in price until supply and

demand are once again in equilibrium. But on sales

of natural gas within FERC jurisdiction, both producers

and pipelines are foreclosed from an unencumbered re-

sponse to economic forces. Unless specifically excepted, |

producers must sell gas, and pipelines must buy it, at

regulated rates that may fall well below a “free-market”

price.” Further, the law imposes on the pipelines an

28 Section 4(a) of the Natural Gas Act, 15 U.S.C. § 717¢(a)

(1976), provides that “[a]ll rates and charges made, de-

manded, or received . . . shall be just and reasonable, and any

such rate or charge that is not just and reasonable is declared

to be unlawful.” Section 5, 15 U.S.C. § 717d (1976), authorizes

the Commission to review rates and set them at just and

reasonable levels. Section 7(c), 15 U.S.C. §717f(c) (1976),

16a

enforceable obligation to resist any temptation to ac-

quiesce in unlawful producer demands and to bid against

each other for available supplies of gas by offering higher

prices or their equivalents.” Still, the sanctions available

to the FERC have their limitations, and even in the

regulatory context market pressures retain some vital-

ity.

requires that new gas be sold under certificates of “public

convenience and necessity.” The Commission’s power to ex-

empt producers and pipelines from the regime of just and

reasonable rate regulation is limited. See generally FPC v.

Texaco Inc., 417 U.S. 380 (1974) ; Consumer Federation of

America v. FPC, 169 U.S.App.D.C. 116, 515 F.2d 347, cert.

denied, 423 U.S. 906 (1975).

29 See Natural Gas Act, §§ 20, 21, 15 U.S.C. §§ 717s, 717t

(1976).

30 Pursuant to section 4(e) of the Natural Gas Act, 15

U.S.C. §717c(e) (1976), the Commission may suspend a

filing for a jurisdictional rate for up to five months. At the

end of the suspension period, the rate may go into effect, sub-

ject to refund. Pipeline expenditures for the purchase of gas

beyond just and reasonable prices may be denied reimburse-

ment (i.e., ordered for refund) and the pipeline’s investors,

rather than its rate payers, mcy have to bear the disallowed

cost. Section 20 of the Act, 15 U.S.C. § 717s (1976), allows

the Commission to seek an injunction from a district court to

restrain on-going or prospective violations of the Act’s pro-

visions. Section 21, 15 U.S.C. § 717t (1976), subjects to crim-

inal penalties “{a]ny person who willfully and knowingly

does or causes or suffers to be done any act, matter, or thing

in this chapter prohibited or declared to be unlawful,” and

subjects to modest per diem fines “[a]ny person who willfully

and knowingly violates any rule, regulation, restriction, con-

dition, or order made or imposed by the Commission under

authority of this chapter.” Despite these deterrents to the

knowing payment of higher than just and reasonable prices

for natural gas, the Commission cannot take the ill-gotten gas

away from the offending pipeline once it has flowed to its

customers. One may anticipate circumstances where a pipe-

line’s investors might determine in their sound business

17a

The advance payment orders did not specify the per-

missible interval between the advance and its appropriate

expenditure. Perhaps emboldened by this indefiniteness,

producers pressed their bargaining advantage, inducing

pipelines to make advances long before the funds were

used for qualifying expenditures. These advances, cer-

tain of which the Commission has labeled “extravagant,”

and which we refer to as “extended front-end advances,”

gave producers valuable interest-free funds for their un-

restricted use during the interim period. By this mecha-

nism the price of natural gas effectively was raised above

the regulatory ceiling.** Competition for needed gas sup-

plies motivated pipelines to acquiesce in exorbitant pro-

ducer demands. The belief (or hope) that the Commis-

sion would permit rate-base treatment of extended front-

end advances, thus passing on the competitive cost to the

rate payers, may have contributed to the pipelines’

weakened resistance. Whatever the causes, extended

front-end advance payments emerged in the market and

are referred to in the testimony of witnesses for the

pipelines as a “term of trade” arising during the period

relevant to these cases.*?

The Commission has administered the advance pay-

ment program to defer inclusion in rate base of a pipe-

line’s front-end advances until the test period in which

those advances were used by the recipient producers for

appropriate purposes. The Commission has relied on its —

construction of the general objectives of the program

and on the administrative discretion inherent in an an-

nounced general policy that it would include in the rate

judgment to take the risks associated with obtaining needed

gas supplies, at least where there is a colorable legal argument

that questionable expenditures are permissible.

81 See note 26 supra.

32 See, e.g., Opinion No. 769-A, Tennessee Gas Pipeline Com-

pany, Docket No. RP73-113, Opinion and Order Denying

Rehearing 3 (May 31, 1977) [hereafter cited as “Opinion

No. 769-A”’], JA in No. 77-1496 et al. at 394.

18a

base only those advances found “reasonable and ap-

propriate.”

The initial advance payment order established Account

166, Advance Payments for Gas, and provided that “ad-

vance payments for gas would be recorded as prepay-

ments and unrecovered advance payments would be in-

cluded in the rate base as part of working capital.” *

Various express conditions limited the advance payments

that would be considered for inclusion in rate base. Some

of these conditions were modified in the subsequent ad-

vance payment orders.** Each. of the orders stated that

83 Order No. 410, supra note 4, 44 FPC at 1143.

34 Order No. 410 encompassed advance payments to inde-

pendent or affiliated producers for exploration, lease acquisi-

tion, development, or production of natural gas, “when such

advance payments are to be repaid by delivery of gas. Id.

at 1146. Advances had to be fully recovered within a “reason-

able period of time following commencement of deliveries,

and in any case “within a 5-year period.” Jd. The rate base

account had to be credited by the amount of non-recoverable

advances. Id.

Order No. 410-A, supra note 4, suspended rate-base treat-

ment for advances to affiliated producers for exploration and

lease acquisition costs. 45 FPC 135 (1971). Order No. 441,

supra note 4, limited the program to the period ending Dec. 31,

1972, and denied rate-base treatment to all advances for ex-

ploration and lease acquisition, as well as payments to both

affiliated and independent producers which resulted in a

working interest. 46 FPC at 1180-81. Where economic inter-

ests other than a working interest were received by a pipeline

as a result of an advance payment properly includable in the

rate base, any realization therefrom was to be treated so as to

reduce the pipeline’s most of service. Jd. at 1181. Advance

payments might be repaid by delivery of natural gas or by

other consideration, and full repayment was required within

five years from the date gas deliveries commenced or the date

it was determined that recovery would be in other than gas.

Id. at 1180.

Order No. 465, supra note 4. extended the program for one

year and reallowed rate-base treatment of advances for ex-

19a

“the Commission plans to consider those amounts re-

corded in Account 166, Advance Payments for Gas, as

rate base items, where found reasonable and appropri-

ate.” ** Thus, properly recording an advance in Account

166 was a necessary, but not a sufficient, condition for

inclusion in the rate base. The Commission also had to

be satisfied that the advance was “reasonable and appro-

priate.”

There has been no dispute that the advance payments

at issue in these cases complied with the express condi-

tions in the pertinent advance payment orders. What is

ploration while. continuing to deny it for lease acquisition

costs. 48 FPC at 1554. Advances by a pipeline to an affili-

ated producer were eligible for rate base treatment, even if

the affiliate obtained a working interest. Jd. at 1154-55. Ad-

vances had to be fully repaid within five years of the date

deliveries commenced, or the date it was determined that

repayment would be in other than gas; and the delivery-

commencement or alternative-determination date had to be

within five years from the date of the advance. Jd. at 1153-

54. A refund to customers was required if an advance re-

sulted in the finding of proven reserves, gas deliveries

commenced, but no gas flowed to the advancing pipelines. /d.

at 1554. |

Order No. 499, supra note 4, extended the program for

another two years and expanded its coverage to include

Alaskan advances made under future contracts (previously

only advances in the lower 48 states where eligible for rate

base treatment). 50 FPC at 2115. Advances to independent

producers resulting in the acquisition of a working interest

were permissible, and economic benefits derived from working

interest advances need not be credited against the pipeline’s

cost of service. Jd. at 2114.

3° Order No. 410, supra note 4, 44 FPC at 1144; Order No.

410-A, supra note 4, 45 FPC at 185 (by incorporation of Order

No. 410); Order No. 441, supra note 4, 45 FPC at 1181;

Order No. 465, supra note 4, 48 FPC at 1555, Order No. 499,

supra note 4, 50 FPC at 2115.

20a

contested is the Commission’s discretion to interpret and

administer the “reasonable and appropriate” guideline.

Two orders govern the advance payments in these

eases. Order No. 465, issued December 20, 1972, gov-

erns advance payment contacts made during 1973.

It contains an unelaborated statement of the reason-

able and appropriate standard.** On December 28, 1973,

the Commission issued Order No. 499, which governs

advance payment contracts made during 1974-75. In

that order, responding to public comments raising the

critical timing issue, the Commission emphasized the

applicability of the “reasonable and appropriate” stand-

ard to that issue. It did not adopt a strict timing rule,

but instead stated that as a “general policy” advances

must be appropriately expended by the producer within

a “reasonable time.” *

36 The Order provided: “Consistent with the amendments

to Section 154.62 of the Regulations under the Natural Gas

Act adopted herein, the Commission plans to consider those

amounts allowed in Account 166, as rate base items, where

found reasonable and appropriate.” Order No. 465, supra

note 4, 48 FPC at 1555.

8750 FPC 2111, 2115 (1973):

[A]s a general policy we shall not consider amounts ad-

vanced to be “‘reasonable and appropriate” for inclusion

in rate base where such amounts are in excess of costs for

exploration, development and production incurred by the

producer within a reasonable time from the date such

amounts advanced are included in the pipeline’s rate base.

The Commission declined to formulate specific timing stand-

ards, determining instead to “examine each advance on a case

by case basis.” Accounting and Rate Treatment of Advances

Included in Account No. 166, Advance for Gas Exploration,

Development and Production, Docket Ne. RM74-4, Order

Denying Rehearing of Order No. 499, 51 FPC 818, 819 (1974).

2la

Huge sums in extended front-end advances were trans-

ferred to producers under contracts subject to Order

No. 465. Despite the Commission’s signal in Order No.

499 that it intended to focus on the critical timing re-

quirement, the flood did not abate.*®

D. The Administrative Proceedings

The administrative proceedings commenced with sep-

arate filings by petitioners for jurisdictional rate in-

creases pursuant to section 4 of the Natural Gas Act.*®

Each filing was initially suspended, then became effective

subject to refund.*°

In the ensuing hearings the pipelines proposed that

all advance payments made during the test period that

complied with the express conditions of the relevant ad-

38 A report prepared on the basis of Commission files cal-

culated that a total of $5.5 billion had been committed in

advance payments as of February 1, 1976. Of that total it

would appear that little more than 1% was advanced on a 30-

day line-of-credit basis. INGAA Br. in No. 77-1496, e¢ al. at 5

n.3; JA in No. 77-1496, et al. at 370. Of this total, more than

$4.2 billion in front-end advance payments were reportedly

committed between August, 1973 and February, 1976. JA in:

No. 77-1496 et al. at 370.

3° 15 U.S.C. 717c (1976).

40 Filing by Tennessee Gas Pipeline Co. (No. 77-1496 et

al.) occurred on June 15, 1973, was accepted and suspended

on August 1, and became effective subject to refund on Janu-

ary 1, 1974. JA in No. 77-1496 et al. at 321.

Transcontinental Gas Pipeline Corp. (No. 77-1212) made

its pertinent filing on July 16, 1974. It was accepted and

suspended by the Commission on Aug. 31, 1974, with the rates

becoming effective subject to refund on Feb. 1, 1975. JA in

No. 77-1712 at 165-66.

Michigan Wisconsin Pipeline Co. (No. 77-1719) filed for

its rate increase on November 15, 1974. The rates became

effective subject to refund on January 1, 1975. JA in No.

77-1719 at 104.

22a

vance payment order should be included in the rate base.

The Commission Staff argued that a reasonable timing

element was inherent in the reasonable and appropriate

standard and that the payment of advances could only

be justified as necessary to provide producers a line of

credit for current obligations. The Staff relied on the

testimony of Robert H. Benna, who stated in part: “*

Based on my experience with Shell, I understand

that producers are normally allowed 30 days from

the date of billing to pay for contract work and

materials. Thus, from the producers’ standpoint,

receipt of an advance one month prior to the date

the related payment is due should allow ample time

to pay the bill. The important factor, to the pro-

ducer, is that he has a commitment by a financially

stable pipeline to make advances in amounts and

at the time necessary to cover exploration and de-

velopment costs.

In the Staff’s view, an advance was not reasonable

and appropriate for inclusion in the rate base unless it

was appropriately expended by the producer within 30

days of receipt. It was argued that the pipelines’ stock-

holders, rather than their rate payers, should bear ti-

carrying charges on front-end advances paid more than

30 days prior to their expenditure. Adapting this stand-

ard to the test-period methodology employed in rate

making, the Staff proposed to disallow inclusion of ex-

tended front-end advance payments made during the

test period but not appropriately expended within 30

days of its close.** The Staff would have allowed an

41 JA in No. 77-1712 at 64; JA in No. 77-1719 at 42-43;

see JA in No. 77-1496 et al. at 6-7.

42 JA in No. 77-1496 et al. at 309; JA in No. 77-1712 at

145-46; JA in No. 77-1719 at 108-11. It may be noted that

this approach allowed certain advances to be included in

rate base even if they were expended more than 30 days after

23a

exception to this rule when it was demonstrated that a

financial savings to the rate payer would result from

the terms of a particular advance payment contract that

— the added cost of deviation from the 30-day

rule.

In response, the pipelines submitted extensive evidence

of the competitive circumstances obtaining during the

period in which the challenged advance payments were

made. The pipelines argued that, in this environment,

refusal to bid competitively for gas reserves by offering

extended front-end advances would have left any hesitant

pipeline without gas to meet its commitments, and that

such a refusal would have been irresponsible in light of

the pipeline’s obligations to its customers.“* Thus, it

receipt. Though an advance made on the last day of a one year

test period would have to have been expended within 30 days

to qualify, advances made on the first day of that test period

would qualify if expended anytime within the subsequent

13 months. Thus it might be argued that the effective timing

reqirement (i.e., the average permissible front-end lag time)

was considerably in excess of 30 days.

*8 JA in No. 77-1712 at 145; JA in No. 77-1719 at 116.

** See Opinion No. 769, Tennessee Gas Pipeline Company,

Docket No. RP73-113, Opinion and Order Affirming in Part

and Reversing in Part Initial Decision Establishing Just and

Reasonable Pipeline Rates (July 9, 1976) (hereafter cited as —

“Opinion No. 769”) (opinion of Commissioner Holloman,

dissenting at 2) (“A pipeline such as Tennessee faced with

this competitive climate would be remiss in its attempts to

attach new supplies of gas on behalf of itself and its cus-

tomers if it did not use this tool to enter into new gas supply

contracts.”) JA in No. 77-1496, et al. at 359; Opinion No.

769-A, note 32 supra (opinion of Commissioner Holloman,

dissenting, at 1) (“For the plain fact is this program was

thrust upon the pipeline companies, leaving them little choice

but to negotiate for these arrangements or abandon the field

to competing pipelines. Obviously, considered in the context

of growing curtailments and deteriorating gas supply, the

24a

was argued, an advance made in good faith response to

competitive conditions was both reasonable and appro-

priate and should be fully included in the rate base.

The administrative law judges in the proceeding be-

fore us, while diverging somewhat in particular results,

were congruent with each other in critical aspects.”

latter course would have evidenced a willful disregard of

Tennessee’s responsibilities to its customers bordering on

negligence.”), JA in No. 77-1496 et al. at 406.

** Tennessee sought inclusion in rate base of nearly $197

million in advance payments to domestic producers, all gov-

erned by Order No. 465. JA in No. 77-1496 et al. at 313. The

administrative law judge rejected Staff’s 30-day rule as “un-

duly restricted and arbitrary.” Jd. at 311. In general, the pipe-

line’s unchallenged good faith and business judgment was

found to qualify advances as reasonable and appropriate. /d.

at 310-11. However, the ALJ perceived an important differ-

ence with respect to $59 million of the total, comprising ad-

vances to affiliated producers. He found that these advances

did not constitute an “arm’s length transaction” since the un-

earmarked affiliate funds were advanced near the close of the

test period and were available for uses unrelated to gas de-

velopment. Approximately $28 million in unexpended intra-

corporate domestic advances were excluded from rate base. /d.

at 314-15.

Transco’s advances, totaling approximately $15 million,

were governea in part by Order No. 465 and in part by Order

No. 499. The pipelines’ business judgment rule was accepted

with respect to the Order No. 465 advances. JA in No. 77-

1712 at 147. However, the ALJ viewed the articulation in

Order No. 499 of a reasonable timing requirement as a sharp

change in Commission policy. All Order No. 499 advances

not expended at the close of the test period were excluded

from rate base. Jd. at 152-54.

Approximately $11.5 million in advance payments, governed

by Order No. 499, are involved in the Michigan-Wisconsin

proceeding. The ALJ found that all the front-end advances,

including those made to an affiliated producer, satisfied the

reasonable timing requirement even though they did not

comply with Staff’s 30-day rule. JA in No. 77-1719 at 112-14.

25a

Each was receptive to the competitive conditions justifica-

tion proffered by the pipelines. Each perceived the ex-

press mention in Order No. 499 of the timing require-

ment as a shift in Commission policy. By and large,

each rejected the Staff’s 30-day rule.

The Commission overruled the initial decisions, adopt-

ing the Staff’s position that a reasonable timing require-

ment was inherent in the reasonable and appropriate

standard of both Order No. 465 and Order No. 499. In

its view, the advance payment program was designed to

benefit rate payers by providing capital to finance ex-

ploration and development of additional gas supplies and

to expedite development of existing reserves. It was not

intended to provide a license for pipelines to bid against

each other for available gas. The Commission concluded

that there was no inherent justification in terms of the

purposes of the program for advances made prior to the

time they were reesonably required to facilitate qualify-

ing producer expenditures. While these extended front-

end advances provided a benefit to producers, no public

service benefit could be discerned. In the Commission’s

view, only one consideration was relevant in determining

whether a timing relationship satisfied the reasonable

and appropriate standard: the financial requirements of

the transaction, i.e., the lag time required to allow a

smooth transfer and expenditure of funds. The Com-

mission regarded the Staff’s 30-day line-of-credit rule

as a well-pleaded presumption, subject to rebuttal, as to

producer needs and pipeline abilities. Since there had

been no showing by the pipelines that producers re-

quired funds more than 30 days prior to appropriate

expenditure, nor that pipelines needed more time to

finance advances, the Staff’s rule was applied to de-

termine inclusion in the rate base.“® The Commission

** Opinion No. 769, supra note 44, at 29-84, JA in No. 77-

1496, et al., at 348-51; Opinion No. 769-A, supra note 82, at

26a

stated: * '

[While we do not find that a maximum time lag of

thirty days between advance and expenditure is

necessarily the only reasonable and appropriaic

standard, it was well pleaded and completely un-

rebutted. ...

The Commission adopted the Staff’s proposal that any

advances failing to satisfy the 30-day test would be

included in rate base only if the terms of the particular

advance payment contract would “save the ratepayer

more in advance payment carrying charges than would

be saved by insisting upon Staff’s 30 day installment

rule.” *® The Commission did not consider that its ex-

press reference to the timing requirement in Order No.

499 represented a dramatic shift in policy from its

earlier orders. Rather, the reference merely highlighted

4-10, JA in No. 77-1496 et al. at 395-401; Opinion No. 801

Transcontinental Gas Pipe Line Corp., Docket Nos. RP74-48

& RP75-3, Opinion and Order Affirming in Part and Reversing

Initial Decision on Reserved Issues and Establishing Just and

Reasonable Pipeline Rates 21-23 (May 31, 1977) [hereafter

cited as “Opinion No. 801”], JA in No. 77-1212 at 185-87;

Michigan Wisconsin Pipe Line Co., Docket No. CP70-22, et al.,

Order Reversing Initial Decision 2-4 (June 3, 1977) [hereafter

cited as ‘““Michigan-Wisconsin Order”’], JA in No. 77-1719 at

116-20. The Commission declined to differentiate between

advances to affiliated and to non-affiliated producers, thus

differing from the reasoning of the ALJ in the Tennessee

proceeding. But the same result was achieved—exclusion of

unexpended intracorporate advances from the rate base—on

the basis of the 30-day standard.

‘7 Opinion No. 769-A, supra note 82, at 5, JA in No. 77-1496,

et al. at 396; Michigan-Wisconsin Order, supra note 46, at 4,

JA in No. 77-1719 at 119.

‘8 Opinion No. 801, supra note 46, at 22, JA in No. 77-1712

at 186; see Opinion No. 769, supra note 44, at 32, JA in No.

77-1496, et al. at 351; Michigan-Wisconsin Order, supra

note 46 at 3, JA in No. 77-1719 at 118.

27a

one element of the reasonable and appropriate standard.

Thus, the same criteria were applied to both Order No.

465 and Order No. 499 advances.

The net effect of the Commission’s advance payment

determinations was the temporary exclusion from the

rate base of advances not satisfying the timing re-

quirement. It is important to note that this was a de-

ferral, not a disqualification. Subsequent filings for rate

increases would entail new test periods; ultimately, when

the expenditure was in fact made during a test period

or within 30 days after its close, the deferred advances

would be included in the appropriate rate base. This

deferral aspect must be distinguished from outright

disqualification resulting when advances failed to satisfy

one or more of the express conditions stated in the ad-

vance payment orders. Nevertheless, substantial sums

were involved and deferral has resulted in considerable

losses for the pipelines’ stockholders.

KE. Interpretation of the Advance Payment Orders

The pipelines assert that the advance payment orders

contemplated the use of extended front-end advance pay-

ments as a mode of competition for available supplies of

gas. From this it is argued that the Commission’s cur-

rent interpretation constitutes retroactive rule making.

The pipelines rely principally on various excerpts from

the text of the orders, and draw additional support from

language in previous administrative decisions. Moreover,

it is asserted that to the extent the Commission’s cur-

rent interpretation might at one time have been a reason-

able and legally supportable construction, that approach

has been foreclosed by the Commission’s repeated re-

newal of the program without appropriate modification

in the face of actual and constructive notice that ex-

tended front-end advances had become a term of trade.

The express mention of a reasonable timing standard in

28a

Order No. 499 is viewed as an inadequate reaction to a

crying need. Indeed, the generality of the Commission’s

response to specific comments is cast as further evi-

dence that the Commission did not intend at the time to

curtail extended front-end advances. Finally, as to the

Commission’s use of Staff’s 30-day rule as a presumption

subject to rebuttal, petitioners challenge its evidentiary

basis, and more fundamentally its premise that the only

factor relevant to application of the reasonable and ap-

propriate standard was the financial requirements of the

transaction.

The essence of petitioner’s arguments is this: multiple

factors encouraged extended front-end advances, and no

specific Commission direction restricted their use. As-

serting that each pipeline’s good faith business judgment

should prevail over the Commission’s present interpreta-

tion, petitioners propose this clear-cut rule: “the sole test

for determining whether the advance payments made

under these orders were to be included in rate base as

‘reasonable and appropriate’ [should have been] whether

they were made in order to obtain commitments for addi-

. tional gas supplies.” *

We find that petitioners’ arguments in support of their

interpretation are undercut by consideration of the char-

acter of the advance payment program as an experimen-

tal departure from well accepted and understood prin-

ciples of regulatory law. The Commission has correctly

construed the underlying purposes of the program as it

was understood by this court in PSC (Advance Pay-

ments) I & II and has not abused its discretion in

discerning a reasonable timing requirement and in re-

jecting petitioners’ “business judgment rule” as the “sole

*® Tennessee Br. in No. 77-1496, et al. at 15 (emphasis

deleted).

29a

test” for the program’s administration.*” Compictely sep-

arate, however, is the question whether the Commission,

in choosing a manner of administering the reasonable

timing requirement, gave due consideration to all perti-

nent factors. As discussed in section I-F infra, we con-

clude that it did not, and remand. But first we turn

to those considerations that support rejection of peti-

tioners’ business judgment rule.

1, Petitioners have the burden of demonstrating an

affirmative authorization for extended front-end advances.

In Smyth v. Ames," the Supreme Court articulated the

guiding principle that “the basis of all calculations as

to the reasonableness of rates to be charged by a | pub-

lic utility] must be the fair value of the property being

used by it for the convenience of the public.” Although

methods for determining values of rate base items have

evolved since Smyth v. Ames," the precept endures that

an item may be included in a rate base only when it is

°° Although we employ the term “business judgment rule”

to characterize the pipelines’ suggested approach, we do not

intend to import the extensive jurisprudence that has de-

veloped in connection with use of the term as a standard

for measuring the duty of corporate directors and other

fiduciaries.

*' 169 U.S. 466, 546 (1898) (emphasis supplied).

"2 See FPC v. Hope National Gas Co., 320 U.S. 591, 605

(1944) ; FPC v. Natural Gas Pipeline Co., 315 U.S. 575, 599-

608 (1942) (concurring opinion of Black, Douglas and

Murphy, JJ.) ; Driscoll v. Edison Light & Power Co., 307 U.S.

104, 122-24 (1939) (Frankfurter, J., concurring) ; McCart v.

Indianapolis Water Co., 302 U.S. 419, 423-41 (1988) (Black,

J., dissenting) ; Missouri ex rel. Southwestern Bell Tel. Co. v.

Public Service Com’n., 262 U.S. 276, 289-312 (1928) (opinion

of Brandeis, J.) ; City of Detroit v. Panhandle Eastern Pipe

Line Co., 3 FPC 273, 278-80 (1942) ; Chicago District Elec-

tric Generating Corp., 2 FPC 412, 416-20 (1941).

30a

“used and useful” in providing service. In other words,

current rate payers should bear only legitimate costs of

providing service to them. The FPC early adopted the

“used and useful” standard and has not departed from it

without careful consideration of the wisdom of requir-

ing current rate payers to bear costs of providing future

service.*®

533 F.g., Mississippi River Fuel Corp., 4 FPC 340, 344 (1945)

(“It has been the general practice of this Commission to deter-

mine the rate base bv ascertaining the net investment in the

gas plant used and useful in rendering service, and adding ;

reasonable allowance for working capital.”’) ; Chicago Distric

Electric Generating Corp., 2 FPC 412, 420 (1941). The “used

and useful” standard was expressly incorporated into the de-

preciation provisions of section 9 of the Natural Gas Act, 15

U.S.C. §717h (1976), which provide in part: The eee

mission may from time to time ascertain and determine, an

by order fix, the proper and adequate rates of depreciation

and amortization of the several classes of property of each

natural-gas company used and useful in the production, trans-

portation or sale of natural gas.”

Compare Cities Service Gas Co., 3 FPC 459, 490 (1943)

(‘While a strict interpretation of rate making principles

might require no allowance for return and depreciation on

the Hugoton [pipeline] project u. ‘il it is completed and in

service, we believe that, because of use urgent necessity for

relieving the gas transportation shortage during the war

emergency, it is in the public interest presently to make

such an allowance in connection with the interim reduction of

rates ordered in this pruceeding.”) ; General Policy and Inter-

pretations, Inclusion of Construction Work in Progress in

Rate Base, 41 Fed. Reg. 51392, 51393 ( 1976) (“The ques-

tion of the proper treatment for ratemaking purposes of

capital expenditures which have not yet been placed in service

is one which is subject to a play of conflicting principles. On

the one hand, public utility regulation has generally adhered

to the principle that a rate base should only include items

which are ‘used and useful.’ On the other hand, regulation

has also always recognized that the expense of financing con-

struction to serve customers is itself a legitimate expense

which must ultimately be borne by the ratepayers.’’) ; Order

3la

One such departure was the advance payment program.

At the very least it contemplated that current rate pay-

ers would shoulder the costs (i.¢., the financing charges)

of qualifying advance payments. This was intended to

expedite the development of additional gas reserves by

providing supplemental sources of capital, which would

be used to provide service for future rate payers. Such

a modification of the “used and useful” principle was

thought justified in view of the discouraging supply

forecasts and the general correspondence between ciasses

of current and future rate payers. Consumers would

eventually have to bear the costs of developing needed gas

supplies. In theory, the advance payment program

promised to provide that gas at the lowest ultimate cost.”

The Commission has taken the position that any de-

parture from such a well-rooted regulatory principle

must be affirmatively authorized and that an authorized

departure must be presumed limited to its express terms.

We agree with the analysis that agency silence in these

circumstances must be construed to mean that tradi-

tional principles retain their vitality.» We are not so

clear that authorization for a departure from settled

principles must be expressly set forth in an order (as

contrasted with what is fairly discernible as the intent

No. 566, Changes in Accounting and Rate Treatment for Re-

search, Development and Demonstration Expenditur ., Docket

No. RM76-12 (June 3, 1977). Regulations permitting rate-

base treatment of R & D expenditures, with certain qualifica-

tions, are codified at 18 CFR 201(108) (1978).

** PSC (Advance Payments) I, supra note 3, 151 U.S.App.

D.C. at 316, 467 F.2d at 370.

°5 See NLRB v. Majestic Weaving Co., 355 F.2d 854, 860 (2d

Cir. 1966) ; NLRB v. International Bhd. of Teamsters, 225

F.2d 343, 348 (8th Cir. 1955). See Standard Oil Co. v. Dept.

of Energy, No. 6-18, slip op. at 20-56 (Temp. Emer. Ct. App.

12/13/78) (reaching a different result where there existed

no previously well-settled rule).

32a

of an order), but it must be established with reference

to the order.

This conclusion allows us to by-pass petitioners’ factual

assertions that, during the pendency of the program, the

Commission had actual and constructive notice that it

was widely understood within the industry to be acquiesc-

ing in extended front-end advances. It is urged that the

Commission’s failure expressly to restrict extended front-

end advances gave such payments an affirmative blessing,

or—what is the same thing—estops the Commission from

now asserting an interpretation contrary to that held by

the pipelines. We accept arguendo petitioners’ factual

assertions of notice, and reject their proffered conclu-

sion. Though a belief that the agency was cognizant of

widespread employment of extended front-end advances

may have further encouraged their use, the Commission’s

inaction cannot be construed to change existing law

where the Commission resists such a change and has

given no indication that it intended a wholesale abandon-

ment of traditional principles. Any modification of tradi-

tional principles broad enough to permit extended front-

end advances must be derived from the advance payment

orders themselves, not from Commission inaction. Fur-

ther, since the Commission relies on well-established

principles of public utility law, it is not sufficient for

petitioners to come forward with some conceivable inter-

pretation of language in the advance payment orders

that supports their view. At the very least, the burden

must fall on petitioners to demonstrate that a preponder-

ance of the interpretative evidence is favorable to their

position.

2. The program was intended to provide additional

sources of capital to expedite development of gas sup-

plies, not to give license for competition among pipelines.

Petitioners attempt to carry their burden of showing an

affirmative authorization for extended front-end advances

33a

by citing specialized provisions of the advance payment

orders, which they construe to support their position. The

first problem is that the cited passages, often less than

clear, are subject to conflicting interpretations.** But a

more fundamental difficulty with petitioners’ approach is

the premise that the underlying purposes of the program

5° For example, petitioners place substantial reliance on the

statement in Order No. 441, supra note 4, that: “Advances

may be recorded in Account 166 and shall be included in rate

base where such payments are reasonable, necessary and

appropriate in order to contract for gas supplies by agree-

ment executed not later than December 31, 1972.” 46 FPC at

1180 (emphasis supplied). Petitioners focus our attention on

the facially directory langauge. It may be noted first that fol-

lowing this statement, the order iterates, “the Commission

plans to consider those amounts recorded in Account 166, Ad-

vance Payments for Gas, as rate base items, where found

reasonable and appropriate.” Jd. at 1181. An harmonious

construction of these two sentences is that need “‘to contract

for gas supplies” is a necessary, but not a sufficient condition

for inclusion in rate base. We may note secondly that the key

ingredient added to the order by the relied-upon sentence is

specification of the order’s termination date as December 31,

1972. Concentration on the sentence’s primary purpose may

have caused the Commission to overlook careless drafting.

Insofar as petitioners’ argument is premised on a justifiable

reliance on the directory language, it is undercut by the Com-

mission’s paraphrase of the critical sentence in the Order of

Clarification and Denial of Rehearing or Modification, 47

FPC 57, 58 (1972):

Tennessee is uncertain as to whether a return will be

allowed on the unamortized balances of non-recoverable

advances. It is our stated position in the fourth para-

graph of page 1180 of Order No. 441, that advances re-

corded in Account 166 may be included in rate base

where such payments are reasonable, necessary and ap-

propriate in order to contract for gas supplies by agree-

ment executed not later than December 31, 1972. There

is no provision for the inclusion in rate base of amounts

that must be eliminated from Account 166.

(Emphasis supplied.)

34a

were sufficiently ambiguous to admit of an interpretation

favorable to extended front-end advances. We find over-

whelming the Commission’s evidence as to the purposes

of the program, as intended by the Commission and as

understood by this court in PSC (Advanced Payments) I.

Thus we need not pause to consider in depth the particu-

lars of petitioners’ references (and the Commission’s

strenuous rebutta!s) but may proceed to consider the

evidence supporting the Commission’s narrower view.

In the introductory paragraphs to Order No. 441, the

advance payment order conditionally approved in PSC

(Advance Payments) I, the Commission stated: °7

In our area rate opinions for Southern Louisiana

and Texas Gulf Coast (Opinion Nos. 598, 46 FPC 86,

and 595, 45 FPC 674), we recognized that it is the

function of a just and reasonable rate for inde-

pendent producers to elicit requisite gas supply, and

that costs, in economic terms, reflects the required

level of capital formation to elicit that level. In

other words, the just and reasonable area rate in

these recent opinions did not consider “non-cost”

items. Having acknowledged, as we do, that provi-

sions for special rate treatment of advance payments

by pipelines have been justified in the past on the

basis of providing additional incentives in this ex-

perimental undertaking, we nevertheless seek to

hy separate, non-price incentives as much as pos-

sible.

A critical shortage of gas exists in the United

States; capital formation for gas development is

difficult. The objectives of providing capital to ac-

celerate the addition of new gas supplies supports

our continuation for the limited period of the rate

treatment of advance payments provided herein. We

recognize that the just and reasonable area rates

5? Order No. 441, supra note 4, 46 FPC at 1179-80.

35a

for independent producers will hopefully alleviate

this gas supply shortage over the long-run; however,

for the immediate term, (namely through 1972) our

advance payments policy has been designed to in-

crease directly the funds available for the necessary

exploration and developmental effort. It is our in-

tention that rate base treatments for advances in-

cluded in Account 166 be terminated for advances

resulting from contracts executed after December

31, 1972, unless otherwise ordered.

The Commission’s starting point was its recognition

of the role of just and reasonable area rates for pro-

ducers in “elicit{ing] requisite gas supply.” For the

long-run, the articulated policy was to incorporate in the

certificated rate all required incentives to assure requisite

supply; ‘“‘non-price incentives” were to be avoided “as

much as possible.” Contrary to this long-term policy, ad-

vance payments embodied a “non-price incentive” in the

“bonus” inherent in the interest-free loan of capital.

Nevertheless, since the Commission recognized that a

“critical shortage of gas exist[ed]” and “capital forma-

tion for gas development was difficult,” the “objective

of providing capital to accelerate the addition of new gas

supplies” justified continuation “for the immediate

term” of a policy “designed to increase directly the

funds available for the necessary exploration and develop-

mental effort.” It was apparent on the face of the order

that the purpose of an advance payment was to provide

“reasonable and appropriate” developmental capital for

“qualifying expenditures.” Yet, the pipelines argue that

the orders approve] all extended front-end advances, con-

tary to the Commission’s view that for the extended

period between receipt and expenditure many of these

advances made no such contribution of developmental

capital while providing producers with a non-rrice incen-

tive of the type the program explicitly sought to avoid

“as much as possible.” In the face of such a clear ex-

36a

pression of limited purpose, we find untenable the argu-

ment of the pipelines for carte blanche authority to

make advances.

One of petitioners’ arguments that figures prominently

in any defense of the pipelines’ behavior asserts that the

advance payment program contemplated competition

among pipelines for available gas through the use of

extended front-end advance payments, which would ef-

fectively raise the price of natural gas and thus inevita-

bly contribute, in an indirect way, to the alleviation of

the natural gas shortage. The fatal weakness in this

argument is that it confuses an incentive with a justifi-

cation. Certainly the Commission contemplated that the

prospect of obtaining additional gas reserves for an in-

dividual gas distribution system would encourage a pipe-

line to offer advance payments. But the mere fact that

an advance payment made good business sense to the

advancing pipeline was not alone sufficient to authorize

its use. Advance payments were not an end in them-

selves. They were legitimate only insofar as and to the

extent that they provided producers with a source of

developmental capital for use in qualifying expenditures.

In the passage from Order No. 441 quoted above, the

stimulating effect on gas supply of the price-incentive

aspect of advance payments was expressly excluded by

the Commission as an objective of the advance payment

program; rather, the price-incentive aspect was tolerated

as a necessary and subsidiary adjunct to the capital-

formation objective. .

The conclusion that the Commission had no intention

of encouraging internecine bidding among gas-starved

pipelines is fortified by the pervasive tone of the advance

payment orders, exemplified by the above-quoted pas-

sage, that the overall goal in both the long-run and the

58 See note 8 supra.

37a

immediate-term was to elicit requisite gas supply for the

nation as a whole, not for any particular pipeline system

at the expense of others.

In another provision of Order No. 441, the Commis-

sion showed a particularized concern that advances should

not be used for competitive purposes but rather should be

cost-justified in terms of the consumer benefit derived

from furtherance of the program’s objectives :*

Our review of the various comments and available

data has persuaded us that advances for explora-

tion and lease’ acquisition have not [been] shown

to be an effective vehicle for stimulating the wide-

spread participation in natural gas production for

which their encouragement was intended. Moreover,

there is some indication that the availability of ad-

vances for such purposes by creating competition

among pipelines to make such advances may be hav-

ing the effect of increasing the amounts expended

on lease acquisition without a proportionate improve-

ment in gas supply.

The Commission excluded from the category of “qualify-

ing expenditures” advance payments for exploration and

lease acquisition since they could be identified as an entire

category that did not further the justifying objectives

of the program, but were instead fostering undesirable

competition among pipelines without an offsetting con-

sumer benefit. When this court affirmed the program in

PSC (Advanced Payments) I, we highlighted this ad-

justment as an example of the Commission’s flexibility

and willingness to modify the program, which we con-

sidered a prerequisite to sound administration.”

5° Order No. 441, supra note 4, 46 FPC at 1180 (emphasis

supplied).

%° PSC (Advance Payments) I, supra note 3, 151 U.S.App.

D.C. at 313, 467 F.2d at 367.

38a

In PSC (Advance Payments) 1, we unambiguously un-

derstood the program’s objective to be the creation of an

additional source of capital to facilitate the natural gas

development and production necessary to alleviate the

gas shortage. In one illustrative passage, we noted:®

The rationale behind this decision is that the ad-

vance payments will help to give the gas producers

the necessary investment capital to finance the de-

velopment and production needed to alleviate the

gas shortage, and the pipelines will be encouraged

to make such advance payments if they are allowed

to include the payments in their rate base, thus

virtually simultaneously shifting the cost of the ad-

vance payments to the pipelines’ customers, the nat-

ural gas consumers.

There was no hint in PSC (Advance Payments) I that a

justifying objective of the program was the encourage-

ment of competition among pipelines for scarce supplies

of gas. On the contrary, by consistently referring to

“producers,” “pipelines” and “consumers” throughout the

opinion, we evidenced our conviction that the revelant

interests were nationwide in scope, not those of any par-

ticular pipeline or its customers.

It is a crucial aspect of this case, refuting the pipe-

lines’ basic retroactive rule making contention, that the

limited purposes of the advance payment program were

unambiguously articulated, in both Order No. 441 and

in the affirming opinion of this court, well prior to the

date of any advance payment contract involved in these

cases.

In PSC (Advance Payments) I we had made clear that

continued approval of the program was dependent. on the

Commission’s ongoing modification and evaluation to as-

1 Jd, at 809, 467 F.2d at 363. See also id. at 317, 467 F.2d

at 871 (on petition for rehearing).

39a

sure that the program was accomplishing its ultimate

purposes—alleviation of the gas shortage—at an ac-

ceptable cost to the natural gas consumer. This process

was undertaken in both Order No. 465 and Order No.

499. In the opening sentence of each, the Commission

stated that the focus of its inquiry was “to determine

whether the advance payment program [was] stimulat-

ing activity toward increasing the supply of natural gas

sufficiently to justify the extension of rate base treat-

ment of advances.” In Order No. 465 the Commission

concluded: “in view of our analysis of all the responses

. and our review of the program of advances in gen-

eral, we find that rate base treatment of advances to

producers has ‘represented a justifiable experiment in

the continuing search for solutions to our nation’s critical

shortage of natural gas.’” [Quoting from PSC (Ad-

vance Payments) [| In Order No. 499 the Commis-

sion stated: “review of the data... indicates that the

advance payment program has continued to meet its

objectives of bringing additienal gas supplies into the

interstate market at an acceptable cost to the nation’s

gas consumers,” and “that pipeline advances have con-

tinued to accelerate the capita: formation which led to

the exploration, development and dedication of 10.27 Tef

of proven reserves of natural gas as well as 9.57 Tef of

potential reserves of natural gas to the interstate mar-

ket.” Neither Order No. 465 nor Order No. 499 severed

the tie between the objective of capital formation and the

authorized use of advance payments. Each Order con-

tinued to assess the program in terms of nationwide gas

supply, not improvement for some pipeline systems at the

62 Order No. 465, supra note 4, 48 FPC at 1550; Order No.

499, supra note 4, 50 FPC at 2111.

*3 48 FPC at 1553.

50 FPC at 2112-13.

40a

expense of others. Again, there was direct evidence that

competition among pipelines was not a desirable nor in-

tended effect of the program.” Although we found the

Commission’s review of the data inadequate in PSC

(Advance Payments) II, we found no inconsistency of

purpose in the Commission’s orders and reiterated our

understanding of the program as expressed in PSC (Ad-

vance Payments) I and in the previous orders.”

The Commission consistently referred. to the purpose

of capital formation to accelerate improvement in overall

gas supply as the purpose of the program and never put

forward the purpose of facilitating for its own sake the

enhancement of producer prices through competition

among pipelines for available gas supplies. Had the Com-

mission advocated such an objective, we discern no basis

on which we would have approved it as permissible under

the Natural Gas Act.

8. Leyul infirmity of a program approving all front-

end advances, The Natural Gas Act requires the Com-

mission to anchor its regulation of producers in the main-

tenance of just and reasonable rates. In T'exaco,"’ which

issued at a time when the strain of natural gas shortage

* In Order No. 465, supra note 4, the Commission stated:

It is clear then that advances for exploration and lease

acquisition have resulted in significant production activ-

ity. However, the comments indicate that advances for

lease acquisition may have been a contributing factor in

bidding up of the price of leases. Therefore we shall

henceforth allow advances for exploration in rate base

while continuing to exclude advances for lease acquisition

from rate base.

48 FPC at 1554 (1972).

PSC (Advance Payments) II, supra note 3, 167 U.S.App.

D.C. at 103-04, 111-18, 511 F.2d at 341-42, 349-51.

* FPC v. Texaco Inc., 417 U.S. 380 (1974).

4la

was acute, the Supreme Court held that the Commission

had acted impermissibly in exempting small producers

from direct rate regulation and rejected as inadequate the

Commission’s contention that it was sufficient to regulate

small producers indirectly, by reason of the consequences

of regulation of pipelines and of large producers. Indirect

regulation was permissible, but only when and if the

Commission developed safeguards to ensure that the rates

paid by pipelines, and ultimately borne by consumers,

remained just and reasonable."*

In Consumer Federation of America v. FPC,” we dis-

approved a program in which the Commission attempted

to authorize competitive bidding for needed gas supplies

by pipelines experiencing critical short-term supply diffi-

culties. That program granted producers 180-day exemp-

tions from rate limitations and permitted them to enter

into contracts with eligible pipelines without risk of re-

fund. The order provided that gas costs “shown to have

been required by the public interest” were to be passed on

to consumers." We invalidated the program, even though

it was proffered as an experiment responding to a supply

crisis, since it failed to provide adequate assurance that

just and reasonable rates would be maintained. We con-

cluded :*'

[T]he Commission has exceeded its authority under |

the Act. In essence, it has attempted to remedy the

shortfall of supply in the interstate market by au-

"* Td, at 401.

169 U.S.App.D.C. 116, 515 F.2d 347 (1975).

Order No. 491-B, 50 FPC 1463, 1470 (1978). The pro-

gram reviewed in Consumer Fedcration was governed by

Order No. 491, 50 FPC 742 (1973); Order No. 491-A, 50

FPC 848 (1973); Order No. 491-B, supra; and Order No.

491-C, 50 FPC 1684 (19738).

169 U.S.App.D.C. at 129, 515 F.2d at 360, quoting PSC

(Advance Payments) I, supra note 8, 167 U.S.App.D.C. at

116, 511 F.2d at 354.

42a

thorizing a supplemental injection of large quanti-

ties of gas through sales freed from the constraints

of meaningful regulation. We reject the FPC’s

claim that § 7(c) [of the National Gas Act] sup-

ports this substantial, partial deregulation, and find

that the Commission has neglected its rate control

responsibilities under the Act. Congress has yet to

embrace proposals for deregulation of new gas sup-

plies. Until it acts to alter the present “system of

regulation by an agency subject to court review, the

courts may not abandon their responsibility by ac-

quiescing in a charade or a rubber stamping of non-

regulation in agency trappings.”

To adopt petitioners’ contention, which would validate

any “timing” arrangement that a pipeline found justified

as a matter of business judgment were it to compete

successfully for gas supply in a shortage crisis, would be

nothing more nor less than acceptance of a deregula-

tory approach, a ruling that cannot be reconciled with the

teaching of Texaco and Consumer Federation. A _pro-

ducer receiving an extended front-end advance, to use

without restriction for a significant period prior to ex-

penditure, is in effect given a sum of money. There is no

meaningful distinction between receipt of unrestricted

funds for a period and receipt of a sum equivalent to the

“return” (at a minimum, interest) procurable from use

of the funds. In both circumstances producers will be

compensated in excess of certificated rates. The business-

judgment rule would permit pure competitive bidding by

pipelines using the device of extended front-end advance

payments.

Had the Commission articulated the approach now

advanced by the petitioners as an interpretation, we

would have disapproved it as an abdication of the agency’s

regulatory responsibilities. This is not to say that the

deployment of funds must be instantaneous. What is

43a

inappropriate is unrestricted transfer for more than a

reasonable period—a concept to which we shall return.

Any permission to transfer advances prior to gas de-

livery (even as to funds used immediately or in a reason-

able time for qualifying developmental expenditures)

entailed some variance from the previous situation, in

terms of benefit to producer and of cost to pipeline and

customer. However, the ultimate cost to the consumer

was projected to remain within the just and reasonable

range because of the compensating benefit of expedited

gas development, and the maintenance of restrictions

relating the cost to the benefit.** This justification, and

these safeguards, were lacking as to the extended front-

end advances made without restriction other than the

competitive “business-judgment rule.”

4. Claim of retroactive rule making. The foregoing

analysis undercuts petitioners’ contention that a reason-

able timing requirement amounted to retroactive rule

making. The pipelines had fair notice both of traditional

regulatory principles and that the advance payment pro-

gram exception was put forward and affirmed on a basis

that did not encompass the departure asserted by peti-

tioners.

In Natural Gas Pipeline Co. v. FERC, the Seventh

Circuit recently ruled that the Commission’s interpreta-

tion of the reasonable and appropriate standard to im-

pose a relatively inflexible “30-day rule” constituted im-

** These restrictions include the maximum allowable pay-

back period (see note 34 supra), economic motivations for

producers to proceed expeditiously with development once ad-

vances have been “sunk” in qualifying expenditures, and the

continued supervision of all aspects of timing and amount of

advance payments under the reasonable and appropriate

standard.

590 F.2d 664 (7th Cir. 1979).

44a

permissible retroactive rule making. It viewed the case

as falling within a doctrine, articulated in Bell Aerospace

Co. v. NLRB," whereby an agency’s broad discretion to

announce policy in adjudication is subject to an exception

in a case of severe impact and justifiable reliance on coli-

trary agency pronouncements.** It stated: *°

The consequences to the appellant of denying rate

base treatment to the advances are very severe. It

would mean the imposition of a large liability with

regard to the advances in the present case. Further-

more, the appellant’s entering into these agreements,

under these terms, was in reliance upon the prior

orders of the Commission, and the policies reflected

in those orders, specifically the policies encouraging

the advance payment program, with few restrictions,

and the promulgation of a flexible standard with re-

gard to the advance-expenditure time relationship.

We believe that the aforementioned facts require that

the Commission’s discretion to proceed by adjudi-

cation as opposed to by rulemaking be restricted so

as to prevent the imposition of a “30 day rule” in

this proceeding.

We differ from the Seventh Circuit in that, in our ap-

praisal, the Commission’s current interpretation of the

limited purpose of the' advance payment orders does. not

reverse a policy that had been the subject of reasonabie

reliance.

The Commission’s rulings on appeal are rooted in basic

principles of regulation and in petitioners’ notice of the

limited purpose of the advance payment exception. We ao

4 416 U.S. 267 (1974).

75 Jd, at 295.

76 590 F.2d at 669.

45a

not discern the substantial claim of justifiable reliance

that is needed to invoke the Bell Aerospace exceptions.”

In support of its rulin oretnaneas

NEG g the Seventh Circuit

decision in Consumer Federation: 78 cited our

While the factual pattern of Consumer Federa-

tion of America, supra, is not identical to the pres-

ent case, the opinion does demonstrate an effort be-

ing made to protect the pipeline companies from the

Squeeze which results if the pipeline incurs expenses

for emergency gas which is not refundable. A very

similar type of problem to that discussed in Con-

sumer Federation of America, supra, is present in

this case. Through Order No. 499, and the four

previous orders, the Commission encouraged a pro-

gram of advances by interstate pipelines to pro-

ducers to secure commitments of natural gas. Furth-

™ The limitations on permissible retroactivity m i

cerned from SEC v. Chenery Corp., 332 U.S. 194 oer wae

NLRB v. Majestic Weaving Co., 355 F.2d 854 (2d Cir. 1966)

(Friendly, J.). The relevant factors include the degree of

retroactivity, the need for administrative flexibility, and the

hardship on the affected parties. With respect to advance

payments, the Commission has not changed an explicit past

policy (Majestic Weaving) but rather has reaffirmed eal.

established regulatory principles. The need for flexibility is

evident in a case, such as this, where “the agency may ger

have had sufficient experience with a particular problem to

sein: gine es tentative judgment into a hard and

ule. enery, 332 U.S. at 202. Th issi

cifically noted the need for a case-by-case ee

timing question. See note 37 supra. Hardship to the pipelines

is mitigated by two factors. First, the Commission merel

has deferred rate-base treatment, not forever disqualified

extended front-end advances from inclusion in rate base

Second, even during the deferral period, the pipelines have

the assurance that their rates will remain at compensato

levels. FPC v. Texaco, 417 U.S. 380, 391-92 (1974) : FPC e

Natural Gas Pipeline Co., 315 U.S. 575, 585 (1942). S

78 590 F.2d at 670.

eee eg eg ee

46a

ermore, inherent within the Commission’s orders

was an attitude of experimentation and flexibility

as reflected in the “reasonable time” standard which

the Commission chose to include in Order No. 499.

Nevertheless, in electing to utilize a “reasonable

time” standard, by itself, the Commission failed to

furnish the pipelines with any sort of guidelines

which might be followed in contracting with pro-

ducers for commitments of gas reserves. Then

after the agreements are entered into and the ad-

vances made, the Commission wants a “reasonable

time” to be defined as “30 days”, with the obvious

effect of such action being that the pipeline would

be forced to absorb huge costs which are not capable

of being reflected in its rate base. To follow the

course set forth by the Commission would be to con-

travene the policy expressed by the court in Con-

sumer Federation of America, supra.

The Seventh Circuit’s citation of our opinion in Con-

sumers Federation is a subsidiary point in its approach,

dependent on its major premise of justified reliance. In any

event, we did not intend Consumers Federation to express

a general solicitude for all pipelines caught in a “squeeze”

to obtain gas. In that case there was a wholesale deregu-

lation of producers, and we found that the indefinite indi-

cation that pipelines would be held to a “public interest”

limit on prices paid was not enough to assure mainte-

nance of just and reasonable rates. In the present case,

there was a continuing regulation, not a deregulation, and

the advance payment order that was judicially approved

articulated a reasonable and appropriate standard which

the Commission, and this court, find was not discarded,

as to the matter of timing of payments, in favor of a

competitive business judgment rule.

While we differ from the Seventh Circuit both on the

issue of justifiable reliance and on the meaning of Con-

sumers Federation, we agree with that court in its dis-

47a

approval of the Commission’s relatively rigid “30-day

rule.” We concur in its view that “inherent within the

Commission’s orders was an attitude of experimentation

and flexibility,” * which in turn involves flexibility in

administration. We develop our views in the next section

of this opinion, but interpolate at this point that the

remand which we order can be implemented by the Com-

mission with results that do not violate the remand by

the Seventh Circuit.

F. Improper FERC Administration of the Advance Pay-

ment Program

We have concluded that the Commission acted within

its discretion in rejecting both the pipelines’ interpreta-

tion of the advance payment orders and their proposed

competitive business judgment rule for administration of

the “reasonable and appropriate” standard. We now turn

to a consideration of the Commission’s administration of

the “reasonable timing requirement,” which in light of

the program’s justifying objectives was implicit in the

reasonable and appropriate standard.

We recognize the limited scope of our review function.

Although a court may not supplant the Commission’s

well-reasoned judgments with those more nearly to its

liking, it must assure itself that “the Commission has

given reasoned consideration to each of the pertinent fac-

tors.” Permian Basin Area Rate Cases, 390 U.S. 747, 792

(1968).

1. Defining the reasonable timing requirement. In

evaluating the timing relationship between an advance

payment and its qualifying expenditure, the Commission

focused solely on the timing requirements of conventional

financing transactions.” It relied on the testimony of its

? Id.

89 See text accompanying note 46 supra.

48a

staff engineer Robert H. Benna set forth earlier in this

opinion.** His testimony, based on his earlier employment

by Shell, was submitted as evidence that producers could

satisfactorily arrange for payment of contract and ma-

terials costs on the basis of a continuing commitment and

specific payments thirty days in advance of due date.

From this the Commission evolved a 30-day line-of-credit

approach, which it established as a presumption subject

to rebuttal. It found that in the cases before it the rule

was unrebutted by evidence of financial inability on the

part of either producer or pipeline to arrange for pay-

ments due under advance payment contracts to be trans-

ferred on a line-of-credit basis. We find the Commission’s

approach unduly restrictive in that it failed to take ac-

count of all factors relevant to the “reasonable timing”

inquiry.

We agree with the Commission that its advance pay-

ment orders do not imply either a competitive business

judgment rule as the sole standard for timing of ad-

vances, or authority for the extravagant costs of extended

front-end advances not accompanied by reasonable con-

trols on the timing of expenditures. However this does

not mean that its orders disclosed a requirement that the

pipelines adopt the “tight” timing practices of conven-

tional financing transactions employed by producers like

Shell in their arrangements with contractors. No strict

line-of-credit requirement could fairly be implied from

the terms of the advance payment orders. By so restrict-

ing the scope of its “reasonable timing” inquiry, the Com-

mission failed to evaluate fully and fairly the reasonable-

ness of the protective mechanisms adopted by particular

pipelines to fulfill their obligation of vigilance in the con-

sumers’ interest.”

81 See text accompanying note 41 supra.

82 Had the Commission considered all pertinent factors, we

would ot lightly overturn its result merely because of severe

49a

The advance payment program was accepted by all

concerned aS an experimental and unconventional method

of financing producer expenditures. The program em-

bodied an important element of flexibility. This was a

key feature both of our approval of the program in PSC

(Advance Payments) I, and of our subsequent remand in

PSC (Advance Payments) II. Nothing in the advance

payment orders, not even in Order No. 499 with its

express reasonable timing requirement, hinted that the

pipelines were limited to line-of-credit or other conven-

tional banking practices in the development of practical

financing packages that would facilitate capital forma-

tion by producers while adequately protecting consumer

interests, thus keeping advances within the confines of

the program. Order No. 499 provided that as a general

policy an advance should be appropriately expended

within a reasonable time from “the date such amounts

advanced are included in the pipeline’s rate base.” * The

language of the order is instinct with latitude.

The Commission’s failure to take into account the in-

herent flexibility of the advance payment program was

the basis for our ruling in United Gas Pipe Line Co. v

FPC." In that case, involving latitude of choice of ian

cing methods, we vacated the Commission’s summary re-

hardship for pipeline investors. As recent]

Pennzoil Producing Co., 99 S.Ct. 765 (1979), pein

Court has suggested that the Commission’s discretion to with-

hold relief from harsh application of familiar regulatory

principles is not abused unless rate levels border on the con-

fiscatory. Id. at 772. That case involved the Commission’s

equitable discretion, not the review of a determination, as in

this case, of applicable legal standards arising in the context

of an experimental, conditionally approved program.

83 See note 37 supra.

** 179 U.S.App.D.C. 274, 551 F.2d 460 (1977).

ee

50a

jection of rate-base treatment for United’s complex finan-

cing arrangement, which entailed an interest-reimburse-

ment scheme rather than the lump-sum transfer of capital

more typical of advance payment contracts. The arrange-

ment contemplated that United would assist the pro-

ducer to locate sources of developmental capital, and then

reimburse the producer’s financing costs. In our opinion

for remand we noted that we found nothing in the ad-

vance payment orders precluding this method of facili-

tating capital formation.

In the pending case involving Transcontinental Gas

Pipeline Corporation (Transco) ,® the advance payment

contracts “provided for payment by Transco on January

10 and July 10 of each year of the estimated expendi-

tures for the subsequent six months, with adjustments

semi-annually and annually to ref&ct overexpenditures,

or underexpenditures, respectively.” ** The Commission

did not say one way or the other whether the pipeline

acted reasonably in fashioning this procedure as a tech-

nique for controlling producer expenditures. Instead, it

applied its line-of-credit rationale to exclude from rate

base all advances not expended within 30 days of the close

of the test period. It appears that Transco’s approach of

periodic accounting and adjustment, with a semi-annual

review of expenditures, constituted a prima facie

showing of an effort to tie payments to “qualifying

expenditures.” We agree with the position of the Public

Service Commission of the State of New York, intervenor

in the Transco proceeding, that in such a case “the shoe

is on the other foot” and it is incumbent upon the Com-

mission to articulate why this attempt to protect the

85 No. 77-1712.

8 Transco Br. in No. 77-1712 at 17-18.

5la

consumers’ interest falls outside the zone of reasonable-

ness contemplated by the advance payment orders.”

We remand the cases before us for a more extensive

and flexible inquiry by the Commission into the reason-

ableness of attempts to protect the rate payers from ex-

cessive costs. If it concludes that contracts such as those

presented by Transco did provide for reasonable timing

protections, the Commission would have latitude as a mat-

ter of equitable discretion to conclude that the kind of

interval found reasonable in a case such as Transco’s

could be accepted as a general bench mark, even as to

contracts that did not contain precisely the same pro-

visions. On the other hand, based on the circumstances

of a particular case, the Commission may determine that

a much shorter timing interval was reasonable. For ex-

ample, we note that in the proceeding involving Tennessee

Gas Pipeline Co.,* Tennessee transferred $59 million in

domestic advance payments to an affiliated producer.

These advances were effected within the last 35 days of

the test period, involved a mere bookeeping transfer with-

out restrictions on the timing or nature of expenditures,

and to the greater extent were not put to use in qualify-

ing expenditures for many months.® The ALJ disallowed

the unexpended portion of these advances because in his

judgment they did not constitute an arm’s length trans-

action. The Commission reached the same result on a

different rationale, deferring rate-base treatment on the

basis of the 30-day rule. On remand, the Commission

may determine that such advances to affiliated producers

present one example of unjustifiable misuse of the advance

payment program.”

87 PSC Br. in No. 77-1712 at 4.

88 No. 77-1496 et al.

89 JA in No. 77-1496 et al. at 318-14.

°° We construe the pertinent advance payment orders as

permitting advances to affiliated producers to be included in

52a

It is evident that a broad range of financing practices

were employed under the advance payment program.

Some may have evidenced a reasonable attempt to protect

rate payers from excessive costs; others, perhaps, did not.

We do not prejudge the result in any particular case;

such determinations are for the Commission in the first

instance.

In sum, we remand these cases because the Commission

failed to apply the proper legal criteria when it ad-

minstered the “reasonable timing” aspect of the “reason-

able and appropriate” standard. The advance payment

orders did not require adherence to strict line-of-credit

or other conventional banking practices, but rather were

- instinct with the attitude of flexibility and experimenta-

tion that motivated the advance payment program. The

Commission correctly determined both that good faith

response to competitive pressures was an inadequate

justification for advance payments and that the pipelines

had a responsibility to protect their rate payers from

excessive costs, ¢.g., to take reasonable steps to ensure

that the timing of advances was tied to that of “qualify-

ing expenditures.” But the advance payment orders al-

lowed a certain discretion to the pipelines and encouraged

them to develop practical financing packages that would

facilitate capital formation by producers while adequately

protecting consumer interests, thus keeping advances

within the confines of the program. Application of the

correct legal standard on remand requires consideration

of the various factors pertinent to a determination of the

reasonableness vel non of the pipelines’ efforts in ‘this

- direction.

Account 166 on the same basis as advances to non-affiliated

producers. However, there is no limitation in the orders re-

stricting the Commission’s ability to consider the affiliate re-

lationship as one factor pertinent to application of the reason-

able and appropriate standard in determining which advances

included in Account 166 qualify for rate base-treatment.

53a

2. Latitude on remand. The Commission has latitude

under its statute to use its equitable discretion and to

choose alternative procedures or mechanisms to formulate

and io effectuate its judgment; * the result need not re-

quire a painstaking readjustment of rate base in each

case.

The Public Service Commission of the State of New

York, an active and helpful participant in all phases of

the development, administration, and review of the ad-

vance payment program, cails our attention to the inter-

relationship between the Commission’s ruling on the ad-

vance payment question and its determination on rate-of-

return. In the Tennessee proceeding,*? the Commission

readjusted upwards the return on rate base allowed by

the administrative law judge, on the basis of a revised

assessment of the risks faced by the industry in these

times of acute supply shortages. In the Commission’s

view, the “pendulum has definitely swung in a direction

substantially contrary to the interests of the investor. A

time of adjustment is clearly called for.” ** One of the

risks incurred by the pipelines has been the “regulatory

risk” that an experimental program such as advance pay-

ments might miscarry, and that administrative readjust-

ment would not prevent substantial adverse impact. Com-

missioner Smith, whose vote in Tennessee was necessary

te form the majority, expressly premised his conecurrenc2

on the 1ink between treatment of advance payments and

rate of return.“ On remand the Commission will have

"' FCC v. Pottsville Broadcasting Co., 309 U.S. 134 (1940) :

Vermont Yankee Nuclear Power Corp. v. NRDC, 435 U.S. 519

(1978).

92 No. 77-1496 et al.

*§ Opinion No. 769, supra note 44, at 22; JA at No. 77-

496 ec? al. at 341.

4 Id., Commissioner Smith, concurring, at 4; JA in No. 77-

1496 ec al. at 357 (“The overai: result [on rate of return] is

54a

discretion to consider this interrelationship in reaching

a just result. In the other two cases before us, the rate-

of-return issue was settled prior to determination of the

advance payment question. If the Commission prefers to

use rate of return as the vehicle for adjustment, it may

consider whether it should reopen these settlement agree-

ments.* Another mechanism for effecting the final just

and equitable result is the ordering of only partial re-

funds, rather than the readjustment of rate base. The

Commission retains a broad discretion in such matters.”

One other significant factor that the Commission may

consider in exercising its latitude on remand is the im-

pact on the industry of the entire course of Commission

action in the development and administration of the

advance payment program.”

supportable only because of the treatment given advance pay-

ments.’’).

% By purporting to “settle” rate of return yet leaving open

the treatment of advance payments, such settlements may

have been rooted in an erronecus premise that these issues

could be put in separate analytic compartments and resolved

independently.

% As noted in Niagara Mohawk Corp. v. FPC, 126 US.

App.D.C. 376, 382, 379 F.2d 153, 159 (1967), “the breadth of

agency discretion is, if anything, at zenith when the action ...

relates primarily not to the issue of ascertaining whether con-

duct violates the statute, or regulations, but rather to the

fashioning of policies, remedies and sanctions.”

7 In another context, we approved the Commission’s deter-

mination to ignore the varied impact on producers of the ad-

vance payment program, and to make a “clean start” in its

prescription of a national rate. The Second National Natural

Gas Rate Cases, 186 U.S.App.D.C. 23, 59-64, 567 F.2d 1016,

1052-57 (1977), cert. denied, 485 U.S. 907 (1978). But that

situation involved allocation among producers of uneven gains,

and prescription of rates for the future. The pipelines are in

a different posture. The Commission has latitude to consider

whether the pipelines were caught between a rock and a hard

55a

It is appropriate to conclude our discussion of Latitude

on Remand, before going on to subsidiary issues, to em-

phasize that while the court has identified a number of

factors for consideration by the Commission, it is aware

that the appraisal and weighing of these factors is the

function of the agency and not of the court. It is not an

encroachment on the agency’s ultimate discretion either

that the court has identified a number of factors for

consideration, or that Judge Wilkey has indicated that

in his view a particuiar emphasis should be given to

certain factors. The court’s role, permitting intervention

for error of law or arbitrary action, still leaves the agency

place and took actions which they reasonably believe were in

the best interests of their customers. This appears to be the

thinking of the Public Service Commission of the State of

New York. PSC Br. in No. 77-1498 at 14.

There is the further consideration that the ambiguity of the

advance payment orders on the timing question may have

served the producers as a kind of legal lever to overcome pipe-

line resistance. In the context of an exception to settled prin-

ciple, which permitted some “advance” payments, the combi-

nation of FERC indefiniteness in the first instance and inac-

tion later on may have given momentum to extended front-end

advances. If the FERC takes the view that the ability of the

pipelines to resist untoward advances was materially weakened

by the agency’s handling of the issue, it has latitude to take

this into account. In this regard it would be appropriate for

the Commission to consider the contrast between Order No.

465, with its absence of any explicit reference to the timing

issue, and the notice provided to both pipelines and producers

in Order No. 499 that advances must be appropriately ex-

pended by the producer within a “‘reasonable time.”

The impact on the natural gas industry of the advance pay-

ment program has been likened to the mark left on a land-

scape by the wreckage from an airplane disaster. The Second

National Natural Gas Rate Cases, supra, 186 U.S.App.D.C.

at 64, 567 F.2d at 57. The Commission has latitude in the

circumstances to fashion an equitable allocation of burdens

between the rate payers and the vipeline investors.

56a

with a function broader in scope than the court’s.”

Although our ruling pertains to the rate-base es

nations raised by the petitions before us, the Commission

has flexibility to consolidate these with other cases, to

engage in rule making, or to adopt other procedures. In

the end, the Commission may choose to adopt a simplify-

ing formula in the interests of feasible administration ;

but such a resolution must reflect a reasoned considera-

tion of all the pertinent factors, demonstrating the flexi-

bility that always has been inherent in the advance pay-

ment program.

II. OTHER ISSUES IN No. 77-1496, e¢ al.,

Tennessee Gas Pipeline Co. v. FERC

We turn to two subsidiary questions raised by the

petitions for review.

A. Canadian Advance Payments

The first question is whether the Commission properly

excluded from Tennessee’s rate base advance payments

made to a Canadian producer. We approve the Commis-

sion’s determination.

The Commission affirmed the ALJ’s decision to exclude

from rate base $37.5 million in advance payments made

by Tennessee to an affiliated Canadian producer, for use

in exploration and development activities in the Canadian

Artic Islands, a remote area in the northern reaches of

Canada.” We discern that the principal basis of the

% The vitality of these principles appears from their early

statement, e.g., FCC v. Pottsville Broadcasting Co., 309 U.S.

134 (1940), and their recent reiteration, e.g., FERC v. Penn-

zoil Producing Co., 99 S.Ct. 765 (1979), discussed in note 81

supra.

Opinion No. 769, supra note 44, at 33-34, JA in No. 77-

1436, et al. at 352-53; Opinion No. 769-A, supra note 32, at

10-18, JA in No. 77-1496, et al. at 401-04. See JA in No. 77-

1496, et al. at 297 (map).

57a

Commission’s determination was Tennessee’s failure to

demonstrate “that receipt by the appropriate American

consumers of the Canadian gas . . . will most likely

occur.” '°

The advance payment orders were expressly limited to

domestic advances.'*' The Commission stated that “[t]he

sole basis for even considering Canadian advance pay-

ments is our prior statement that pending a Canadian

advance payment rulemaking such advances ‘shall be

treated on a case by case basis.’” '°* The Canadian ad-

vances were made in 1973 and Tennessee sought to have

them charged to the contemporaneous rate payers, though

it concedes that no gas will be forthcoming until the mid-

1980’s.'"* These advances were not “used and useful” for

providing service to then current rate payers, and tradi-

tional rate making principles would call for exclusion

from rate base.’* The Commission’s analysis seems to

contemplate an exception from traditional principles,

permitting rate base inclusion on a showing that a par-

ticular advance payment served the same purposes, and

promised an equivalent benefit to rate payers, as those

envisioned for domestic advances complying with the

advance payment orders.

The fundamental objective of the advance payment

program was to help elicit requisite gas supply by pro-

viding capital for expedited development and production

during the interim period until an upward revision in

100 Opinion No. 769-A at 12, JA in No. 77-1496, et al. at 408.

101 See note 25 supra.

102 Opinion No. 769-A at 11, JA in No. 77-1496, et al. at 402,

quoting Notice of Rulemaking, supra note 25, 38 Fed. Reg. at

1056.

103 Td. at 138, JA in No. 77-1496 et al. at 404; Tennessee Br.

in No. 77-1496, et al. at 66.

104 See text accompanying notes 51-55 supra.

58a

producer rates would accomplish this objective.’ The

ends of the program could not be furthered unless the

investments that were precipitated by advance payments

inured to the benefit of jurisdictional rate payers. For

this reason the program expressly assured that rate pay-

ers would not be charged for advances that did not pro-

duce gas, or that produced gas which did not flow to the

advancing pipeline.’ Similarly, as to Canadian ad-

vances, the Commission here required that the gas result-

ing from such advances must be shown “most likely” to

flow to the advancing pipeline’s domestic rate payers.

This general approach was well within the Commission’s

broad discretion and consistent with that taken in previ-

ous adjudications.'”

More specifically, the Commission concluded that Ten-

nessee had not carried its burden of showing that Arctic

Islands gas would “most likely” flow to rate payers in the

United States. Several uncertainties remained, e.g.: (1)

whether reserves in the Arctic Islands region were suf-

ficient to justify construction of a pipeline; (2) whether,

at the time this gas would become available for market,

Canada’s total reserve situation would justify granting of

the necessary export authorizations by the National Ener-

gy Board of Canada (NEB); and, (3) whether, assum-

ing the existence of adequate reserves, the NEB would

grant the required authorizations, rather than authoriz-

ing additional exports from other gas-producing regions,

or otherwise modifying Canadian energy policy. As we

recently have had occasion to note, in the present era of

uncertainty for natural gas supply any attempt to pre-

105 See text accompanying notes 56-66 supra.

106 See note 34 supra.

107 F’.g., Opinions No. 672 & 672A, Texas Eastern Transmis-

sion Corp., Docket No. RP70-29, et al., 50 FPC 1419 (1973),

51 FPC 258 (1974), aff'd, 171 U.S.App.D.C. 25, 517 F.2d 1299

(1975).

59a

dict NEB export policy is highly speculative.‘°* The very

existence in this case of a genuine dispute over the in-

terpretation of a series of inconsistent and conflicting

NEB reports is sufficient to support the Commission’s

judgment that the issue is not free from substantial

doubt. We will not disturb the Commission’s informed

judgment when it acts as here, within an area of its

special expertise and discretion.

B. Rate of Return

The second subsidiary issue is whether the Commission

erred in allowing Tennessee a 13.75% return on equity.

In proceedings before the administrative law judge,

Tennessee argued for a 13.35% rate of return on equity;

Staff proposed an 11.6% return. The ALJ concluded that

a return of 12.5% on equity was “reasonably in line with

earnings of enterprises with comparable degrees of risk,

and which have similar ratios of common equity capi-

tal.” *°° The Commission set aside this determination and

adopted a return of 13.75%. In the Commission’s view,

the “pendulum [had] definitely swung in a direction sub-

stantially contrary to the interests of the investor. A

time of adjustment [was] clearly called for.” 1°

108 Midwestern Gas Transmission Corp. v. FERC, —— U.S.

App.D.C. ——, 589 F.2d 603 (1978) (ruling, inter alia, that

certain of petitioner’s claims were not ripe for review since

they depended on the speculative effect on future NEB export

policy of FERC action regarding the Alaska Natural Gas

Transportation System). See id. at 622 n.107.

109 Initial Decision in No. 77-1496 et al. at 23, JA in No. 77-

1496, et al. at 307. This ruling would have resulted in overall

return on rate base of 8.787%. Id.

0 Opinion No. 769-A at 22, JA in No. 77-1496, et al. at 341.

This ruling resulted in an overall return on rate base on

9.25%. Id. at 23, JA in No. 77-1496 et al. at 342.

bi

:

4

60a

New York Public Service Commission argues that the

Commission’s ruling on rate of return was inextricably

bound to its advance payments determination.""' PSC

also challenges the reasonableness of the allowed return

on equity. We have suggested that on remand for recon-

sideration of the advance payments determination, the

Commission should again evaluate the rate of return

' question, which it would have full authority to do even

if the allowed return were valid in all respects, FCC v.

Pottsville Broadcasting Co., 309 U.S. 1384 (1940). We

think it appropriate to refrain from entering a ruling at

this time on this issue, pending further consideration on

remand.

III. OTHER ISSUES IN No. 77-1712,

Transcontinental Gas Pipe Line Corp. v. FERC

Two subsidiary issues are raised by Transco’s petition

for review: (1) whether the Commission erred in ex-

cluding from Transco’s rate base expenditures for un-

successful alternative gas supply projects; and, (2)

whether the Commission properly rejected an offer of

settlement. We affirm the Commission’s rulings.

A. Expenditures for Alternative Gas Supply Projects

The Commission affirmed the ALJ’s exclusion from

rate base of over $22 million expended by Transco in

four unsuccessful projects related to the production of

synthetic natural gas (SNG).' The pipeline argued

111 See text accompanying hotes 92-95 supra.

112 Expenditures of $10.1 million related to a study of the

technical and economic viability of converting Middle Eastern

crude oil into synthetic natural gas of pipeline quality. Over

$9.8 million was devoted to a project for conversion of naptha

feedstock into SNG. A study of a program to use natural gas

reserves located overseas by converting the gas to crude

methanol at its source, transporting the methanol by conven-

tional tankers to the United States, and converting the meth-

6la

that these amounts should be included in rate base to

be amortized as expense items for inclusion in cost of

service. Thus Transco sought both a return on, and the

return of its investments. The Commission found that

the expenditures were not “used and useful” in providing

service and should not be charged to the rate payers.'"®

Since the projects did not produce any jurisdictional gas,

this ruling clearly was a proper exercise of discretion.

We find without merit the claim that the Commission

had established a policy, relied on by Transco, creating

an exception from the traditional “used and useful”

principle with respect to expenditures for SNG develop-

ment."* The Commission had established such an excep-

tion for research and development costs, but the Transco

projects failed to qualify for special R & D treatment.?"*

anol into natural gas cost $1.4 million. Over $920.000 was

spent on a project to produce methane from coal. Initial Deci-

sion in No. 77-1712, supra note 26, at 5-7, JA in No. 77-1712

at 122-24.

113 Opinion No. 801-A, supra note 46, at 2-8, JA in No. 77-

1712 at 202-03.

114 See text accompanying notes 51-55 supra.

115 The Commission had previously demonstrated its reliance

on this principle in Tennessee Gas Pipeline Co., Opinion No.

624, 48 FPC 149 (1972), aff'd, 159 U.S.App.D.C. 318, 487

F.2d 1189 (1973) (grant of a certificate to construct liquified

natural gas facilities conditioned to prevent rate-base treat-

ment of costs if the project proved unsuccessful). In addition,

the Commission’s uniform System of Accounts for Natural

Gas Companies, 18 CFR 201 (1978), provided clear notice

that pipeline investors must absorb costs of abandoned projects

involving “preliminary survey plans, investigations, etc. made

for the purpose of determining the feasibility of utility proj-

ects under contemplation . . . to provide a future supply of

natural gas.” See PSC Br. in No. 77-1712 at 11.

116 See 18 CFR 201(103) (1978) (requiring, inter alia, use

of experimental technology and prior Commission approval—

62a

These expenditures were prudent investments, argues

Transco; however, for rate base inclusion expenditures

must satisfy not only the necessary condition of prudent

investment but.also must be “used and useful” in provid-

ing service. The Commission did not abuse its discretion

when it applied a policy “that SNG expenditures which

do not qualify as R & D can be recovered, if at all, only

through the price paid for actual SNG production sold

in interstate commerce.” ’

B. Rejection of Transco’s Settlement Offer

On the basis of the above reasoning, we affirm the

Commission’s concise rejection of a settlement offer that

proposed to exclude these project costs from rate base,

yet to amortize most of them over a five-year period for

inclusion in cost of service, thus allowing Transco to

recover its unsuccessful investments.**

Affirmed In Part; Remanded In

Part For Further Consideration.

both absent from Transco’s projects) ; Opinion No. 801-A at

3, JA in No. 77-1712 at 203.

117 Opinion No. 801-A at 4, JA in No. 77-1712 at 204.

118 See Opinion No. 801 at 8, JA in No. 77-1712 at 172.

63a

WILKEY, Circuit Judge concurring: I concur in Judge

Leventhal’s carefully reasoned and skillfully crafted opin-

ion for the court. I add this note as a concurrence-for-

emphasis.'

In Judge Leventhal’s opinion for the court the Com-

mission has properly been allowed wide discretion in fash-

ioning a new and more flexible rule on remand. The

point I wish chiefly to emphasize is that the Commission

on remand must give careful consideration to arguments

raised by petitioning pipelines concerning market pres-

sures, the ambiguity of the Commission’s orders on timing

of payments, and the contribution of advance payments

to capital development by producers and to enhancement

of gas supply. Thus I believe the court’s opinion must be

read as not allowing the Commission discretion to institute

a new rule that is little more forthcoming in its allow-

ances for advance payments than the now-void thirty-

day rule.

As we have noted, the advance payment program

constituted a significant and recognized departure from

traditional regulatory principles.2 This departure was

deemed necessary to serve the important public purpose

of “facilitat{ing] capital formation by [natural gas]

1 See Citizens to Save Spencer County v. United States En-

vironmental Protection Agency, No. 78-1002 et al. (D.C. Cir.

27 March 1979) (Leventhal, J., concurring).

2 See, e.g., slip op. at 9 (advance payment program was a

recognized “departure from the usual rule of public utility

regulation . . . that current rates should reflect the cost of

supplying service to current rate payers .. .”); id. at $1

(describing advance payment program as a clear “departure”

from, and “modification” of the “used and useful” principle) ;

id. at 43 (“Any permission to transfer advances prior to gas

delivery . . . entailed some variance from the. . . [regulatory]

situation [prior to the commencement of the advance pay-

ments program], in terms of benefit to producer and of cost

to pipeline and customer.’’).

\+ ay a2 a

64a

producers to finance development and production of new

. . . supplies” in order to “alleviat[e] the impending

natural gas shortage.”* The program aimed to stimulate

the process of capital formation by allowing the transfer

from pipelines to producers of interest-free sums reason-

ably targeted for purchase or expenditures for produc-

tion of identified gas supplies.‘ Natural gas producers

were thus relieved of financing costs ordinarily associated

with the accumulation of capital for exploration and

development of new supplies.

With such significant advantages to be gained from

advance payments, it is certainly correct, as Judge Leven-

thal has pointed out, that producers could be “expected”

to bargain with the pipelines for advance payments to be

made.® Likewise, producers could be expected to press

the pipelines for advances to be made on the most favor-

able terms possible—i.e., as long as possible in advance of

their eventual “qualifying” expenditure.* This pressure

for what we have termed “extended front-end” advances *

was increased because the availability to producers of

interest-free advance payments became one of the few

8 See id. at 7. See also id. at 14 (“theory” of the program

was that “increased availability of capital would encourage

investment, which in turn would yield additional gas

supply”).

4 See id. at 42 (“A producer receiving an extended front-end

advance, to use without restriction for a significant period

prior to expenditure, is in effect given a sum of money.”).

5 See id. at 8.

6 The court’s opinion has employed the term “qualifying

expenditure” to identify “those producer expenses permissible

under the [advance payments] program.” See id. at 8.

7 The court has devised the novel and useful term “extended

front-end advance” to describe those advance payments barred

from current rate base treatment by Commission orders here

under review. See id. at 14.

65a

negotiable terms of gas supply contracts in the other-

wise closely regulated natural gas market.

As a result of tight gas supplies during the years of

the program at issue here,* bargaining attempts of the

producing companies met with particular success as pipe-

lines scrambled to secure supplies of gas for customers.

Since it was in order to relieve this plight of tight supply

that the program was initiated, however, this superior

bargaining position of the producers and their conse-

quent bargaining success should have come as no sur-

prise to the Commission.

Furthermore, no evidence on the record suggests that

contracts providing for advance payments were negotiated

covertly. Instead, all available information suggests that

the high degree of administrative, judicial, and public

scrutiny afforded the advance payment program made

the terms of the vast majority of advance payment con-

tracts well known to outside parties, and certainly to the

responsible regulators.

It is thus particularly astonishing that, as noted in

the court’s opinion, “[t]he advance payment orders [is-

sued by the Commission during the program] did not

specify the permissible interval between the advance and

its appropriate expenditure.” * Order No. 465 contained

what has properly been described as a totally “unelabo-

rated statement” that advance payments would be al-

lowed only where “reasonable and appropriate,” with no

specific reference to the critical issue of how long in ad-

vance of designated use such payments could be made.”®

Subsequently, Order No. 499 made a completely unim-

pressive advance toward specificity by declaring that

8 These years were 1973, governed by FERC Order No. 465,

and 1974-75, governed by FERC Order No. 499. See id. at 11.

® See id. at 17.

10 See id. at 20.

66a

only those advances made within a “reasonable time” of

eventual expenditure would be allowed."' Until long after

the expiration of the advance payment program, there-

fore, the Commission through its applicable Orders pro-

vided only the most cryptic and ambiguous guidelines

concerning the issue central to the present litigation.”

It thus was practically inevitable that the “flood” of

advance payments propelled by Order No. 465 did not

abate during the time between the two advance payment

orders, or thereafter.'* The Commission bears much re-

sponsibility for this situation, for the opacity of the Com-

mission’s orders on the issue of permissible timing could

only have contributed to the disruptive effect of

advance payment bargaining on the otherwise tightly

metered minuet of producers, pipelines, consumers, and

regulators."

11 See id.

12 The Commission order barring current rate base treat-

ment to certain “extended front-end advances’ made by

Tennessee Gas Pipeline Company, for example, was issued on

9 July 1976, see FPC Docket No. RP73-113, Opinion No. 769,

more than six months subsequent to the expiration of the ad-

vance payment program on 31 December 1975.

18 See slip op. at 21 (“Despite the Commission’s signal in

Order No. 499 that it intended to focus on the critical timing

requirement, the flood [of advance payments] did not abate.’’)

14 As noted in the court’s opinion, producers may have

been “emboldened by ... [the] indefiniteness [of the advance

payment orders on timing]” and therefore the “producers

pressed their bargaining advantage, inducing pipelines to

make advances long before the funds were used for qualifying

expenditures.” Jd. at 17. See also id. (pipelines’ “weakened

resistance” to competitive pressures was materially aided by

“(t]he belief (or hope) that the Commission would permit

rate-base treatment of extended front-end advances ... .”).

Though the court’s opinion in other language has not ac-

cepted petitioners’ argument that the Commission must be

67a

The court’s opinion has bent over backward to em-

phasize that the lack of clear regulatory guidance weak-

ened the resistance of pipelines to the “untoward ad-

vances” of producers in eliciting extended front-end pay-

ments by pipelines.'"*> We have been somewhat less defi-

“estopped” from denyirg current rate base to advance pay-

ments because the Commission was on notice of the payments

and the pipelines relied justifiably on agency silence, see id.

at 44-47, the court’s view on this issue is perhaps best summed

up in its exceedingly cautious statement that “agency silence

. .. [with regard to the scope of a departure from a well-

rooted regulatory principle] must be construed to mean that

traditional [regulatory] principles retain their vitality.” Jd.

at 31. This modest statement, however, must be placed side

by side with the court’s repeated observation that the ad-

vance payment program constituted an express departure

from recognized regulatory principles. See id. at 9, 31 & 43.

Thus it is certainly consistent with the court’s position to

argue that the “vitality” of the Commission’s regulatory

principles has been diminished at least to the extent that the

Commission itself has backed away from those principles.

It would be insupportable for the Commission to bind an in-

dustry to regulatory principles from which the Commission

has itself departed; thus I believe it is only with some diffi-

culty that we conclude that “agency silence” on the issue of

timing of advance payments did not convey a tacit and irre-

versible assurance that advance payments would be upheld if

made in full view of the Commission and in arguable compli-

ance with the Commission’s ambiguous regulations.

15 We have suggested, for example, that the Commission

on remand has “latitude to take . . . into account . . . the

view that the ability of the pipelines to resist untoward ad-

vances was materially weakened by the agency’s handling

of the issue ... ,” id. at 55 n.98, and “whether the pipelines

were caught between a rock and a hard place and took actions

which they reasonably believe were in the best interests of

their customers,” id. at 54-65 n.97. The Commission also has

been urged to take into consideration more generally the “sig-

nificant factor” of “the impact on the industry of the entire

course of Commission action in the development and admin-

istration of the advance payment program.” Id. at 54.

68a

nite, however, in suggesting the extent of the relief that

should be afforded the pipelines on remand. We have

noted that the objective of the advance payment program

was to facilitate the development of capital by producers

in order to enhance gas supply,’* and that advance pay-

ments by definition involve the transfer of capital from

pipelines to producers.” We have also noted the argu-

ment of the pipelines that all advance payments must be

sustained fu ' reason of such a capital contribution, and

the contrary argument of the Commission that no allow-

ance should be made for many payments that “for the

extended period between receipt [by the producers] and

expenditure . . . made no. . . contribution of develop-

mental capital [for ‘qualifying expenditures’] while pro-

viding producers with a non-price incentive of the type

the program explicitly sought to avoid ‘as much as pos-

sible.’ ” *®

The opinion of the court, however, adopts a middle

position. While rejecting the pipeline’s argument for

carte blanche authority to make advances,’® we have also

rejected the Commission’s overly narrow view of the role

of advance payments in enhancing capital formation and

gas supply. Any front-end advance payment, according

to this court’s definition, is one made prior to its use

for “qualifying expenditures.” 7° Also we have noted that

only a sub-class of front-end advance payments may

properly be disallowed current rate base treatment. This

16 See, e.g., id. at 6-7 & 14.

17 See id. at 138 (an advance payment, as an interest-free

loan, “substitutes for capital raised in financial markets’) ;

id. at 42 (“A producer receiving an extended front-end ad-

vance... is in effect given a sum of money.”)

18 See id. at 35.

19 See id. at 35-36.

20 See id. at 18.

69a

class of payments on remand will necessarily be smaller

than that excluded by the Commission according to the

thirty-day rule. Thus we have not determined that every

advance is insupportable for the simple reason of its pay-

ment prior to expenditure; instead, we urge strict scru-

tiny only of those payments that may have been “extrava-

gant” because they were made too long in advance of

qualifying expenditures.

We reach this conclusion, I believe, in part because pay-

ments made at any interval (whether thirty days or

much longer) in advance of qualifying expenditures in-

evitably enhanced the formation of capital in the hands

of producers, and, unless diverted eventually for other

non-“qualifying” purposes, may have facilitated the de-

velopment of new gas supplies by reenforcing the capital

foundation of the producing firms and freeing other

funds for immediate productive use. It will be the task

of the Commission on remand to define with some spe-

cificity and with greater latitude than previously those

advance payments that were, and those that were not,

“reasonable and appropriate” in conforming to the stated

objectives of the program in thus aiding capital develop-

ment for the purpose of enhancing gas supplies.

I have some difficulty, however, with the court’s dis-

cussion of the undesirable consequences of competition

among pipelines for supplies of gas. Though bidding

among pipelines for gas by offering advance payments

inevitably had the effect of raising prices, it cannot lightly

be assumed that an increase in prices did not lead to a

corresponding increase in supply. As a general matter,

only in a situation of total inelasticity of supply can an

increase in prices not be expected to lead to a correspond-

ing increase in supply. No such situation of total inelas-

ticity has been demonstrated here, and as Judge Leven-

thal notes, “Even in the regulatory context, market

, al oe

70a

pressures retain some vitality.” *' Thus it is clearly with-

in the purview of our decision for the Commission to

give close consideration to the extent to which bidding for

gas supplies had the effect of raising prices and thus

enhancing natural gas supply, in keeping with the overall

goals of the advance payment program. I believe that

the burden of proof rests with the Commission to demon-

strate that the new rule it derives on remand distin-

guishes effectively between those advance payments that

reasonably could, and those that reasonably could not

lead to an increase in supply commensurate with any

increase in price.

The Commission on remand will also want to take

careful note of the losses incurred by the pipelines as

a result of the Commission’s rate base ruling. Though

Judge Leventhal has noted for the court that the Com-

mission’s action to date has been to defer, rather than

indefinitely to disqualify certain advance payments for

rate base, he has also noted that “substantial sums were

involved” and that “deferral has resulted in considerable

losses for the pipelines’ stockholders” because of interest

lost during the period of deferral.?? Such losses are not

to be taken lightly, and clearly a very close question is

presented as to whether these losses are substantial

enough to bar the admittedly retroactive clarification by

the Commission of the ambiguous language of its earlier

orders on the issue of timing.”*

The Commission will also wish to consider the equities

in specific cases of a denial of current rate base to pipe-

line companies that may have exercised reasonable judg-

21 See id. at 16.

22 See id. at 27.

23 See cases cited in id. at 45 n.77 (hardship on the

affected parties a factor to consider in evaluating limitations

on retroactivity of agency action).

$

a

Tla

ment in making advance payments in the context of tight

gas supplies and ambiguous regulatory guidance. The

pipelines have made out a convincing case that their re-

sponsibility to obtain adequate supplies for consumers

during a period of scarce supply compelled them to “bid

competitively for gas reserves by offering extended front-

end advances.” *“* Though we have not endorsed applica-

tion of any “competitive business judgment” rule in this

case, we have noted that circumstances may be “antici-

pate[d] ... where a pipeline’s investors might determine

in their sound business judgment that they should take

the risks associated with obtaining needed gas supplies,

at least where there is a colorable legal argument that

... [the] expenditures are permissible.” *°

I believe that under the circumstances of this case

there was at least a “colorable legal argument” that many

of the advance payments made would subsequently be

approved by the Commission, and that any exercise of

sound judgment by pipeline companies in weighing fac-

tors of consumer demand, scarce supply, and ambiguous

regulation must not be lightly rebuffed by the Commission

on the basis of an imputed greater wisdom of hindsight.

All of the considerations discussed above I understand

to be subsumed within the court’s instruction that the

Commission on remand devise a new and more flexible

24 See id. at 23-24; id. at n.44 (quoting dissenting view of

Commissioner Holloman that, inter alia, “A pipeline... faced

with... [the] competitive climate [in the natural gas market]

would be remiss in its attempts to attach new supplies of gas

on behalf of itself and its customers if it did not use... [the]

tool [of offering extended front-end advances] to enter into

gas supply contracts.’’)

25 Jd. at 16-17 n.30. We have also noted that at least one

administrative law judge ruling on this case found that a pipe-

line company’s “unchallenged good faith and business judg-

ment... qualif[ied] advances as reasonable and appropriate.”

Id. at 24 n.45.

72a

rule concerning advance payments. As noted in the

court’s opinion, “The advance payment orders . . . were

instinct with the attitude of flexibility and experimenta-

tion” and “allowed a certain discretion to the pipelines

and encouraged them to develop practical financing pack-

ages....” *° Though the pipelines have erred in arguing

for an overbroad and overgenerous rule of universal al-

lowances,”’ they certainly have not erred in resisting the

Commission’s correspondingly narrow and _ excessively

rigid thirty-day rule. As has been made amply clear in

the court’s opinion, there is nothing pernicious about

advance payments per se; ** instead, I believe, only those

advance payments that overstrain the bounds of reason-

ableness may be denied current rate base treatment by

the Commission. Having failed once, a serious burden

rests with the Commission to buttress its new rule with

reasoned support.

26 Td. at 52.

*7 As noted in the court’s opinion, pipelines have argued

that “the sole test for determining whether the advance

payments made . . . were to be included in rate base...

[should have been] whether they were made in order to obtain

commitments for additional gas supplies.” Jd. at 28.

28 See, e.g., id. at 14.

73a

APPENDIX B

UNITED STATES OF AMERICA

FEDERAL POWER COMMISSION

Before Commissioners: Richard L. Dunham, Chairman;

Don S. Smith, John H. Holloman III, and James G.

Watt.

TENNESSEE Gas Pireting CoMPANy

(A Division of Tenneco, Inc.)

Docket No. RP73-113

Oprtnion No. 769

OPINION AND ORDER AFFIRMING IN PART AND

REVERSING IN PART INITIAL DECISION ESTAB-

LISHING JUST AND REASONABLE PIPELINE RATES

(Issued July 9, 1976)

This proceeding arises under Section 4 of the Natural

Gas Act and concerns the justness, reasonableness and law-

fulness of increased rates and charges proposed by Ten-

nessee Gas Pipeline Company.

PROCEDURAL HISTORY

On June 15, 1973, Tennessee Gas Pipeline Company (Ten-

nessee) filed revised PC Gas Tariff Sheets incorporating

a proposed annual rate increase from jurisdictional sales of

$150,194,754. Then on August 1, 1973, the Commission ac-

cepted these revised tariff sheets for filing, suspended the

proposed rates for the full five month statutory period, to

become effective subject to refund on J anuary 1, 1974, and

set the matter for hearing. It did, however, state that Ten-

nessee must file revised tariff sheets to eliminate any facili-

ties which had not been certificated by January 1, 1974

Beck

74a

(the Commission had noted that Tennessee included in rate

base for its June 15, 1973, filing over $18 million of non-

certificated facilities). In response to this Commission di-

rective Tennessee filed on November 30, 1973, further

revised tariff sheets in which the annual jurisdictional rate

increase had been reduced to $141,719,530.

Hearings were held intermittently from March 26, 1974

through October 29, 1974, before Administrative Law Judge

Samuel Kanell, who thereafter on February 3, 1975, issued

an initial decision resolving all of the issues presented by

the parties. Briefson exception to this initial decision were

filed by Tennessee, Staff, Columbia Gas Transmission Cor-

poration and Consolidated Gas Supply Corporation (Co-

lumbia and Consolidated), Berkshire Gas Company, et al.

(Berkshire), the Public Service Commission of New York

State (New York), and Trunkline Gas Company (Trunk-

line). Briefs opposing these exceptions were thereafter

filed by Tennessee, Staff, Berkshire, New York, Columbia

and Consolidated, Northern Illinois Gas Company (North-

ern Illinois), East Tennessee Natural Gas Company (Kast

Tennessee), and Northern Indiana Public Service Company

and Peoples Gas Light and Coke Company (Northern

Indiana).

SUMMARY

We find that the following findings in the initial decision

should be affirmed: (1) Tennessee Gas Pipeline Company’s

(Tennessee) composite depreciation rate should be in-

creased from 3.6% to 4% as Staff recommended, not to

5.75% as Tennessee filed. (2) Tennessee’s Canadian and

Non-Canadian unexpended intracorporate advance pay-

ments should be disallowed, as Staff recommended. (3)

Tennessee’s rate base should be reduced because Staff’s

larger DDA reserve should be utilized. (4) Tennessee’s rate

base should further be reduced to account for the disal-

lowance of minimum bank balances from working capital.

75a

(5) Tennessee’s rate base should also be reduced to reflect

use of Staff’s larger reserve for accumulated deferred Fed-

eral income taxes. (6) Tennessee’s cost of service should

be reduced to reflect the amortized portion of the Bastian

Bay deferred revenue fund being credited to Bastian Bay

expenses. (7) Tennessee’s cost of service should also be

reduced to account for the tax allowance deduction of inter-

est on short-term debt. (8) Tennessee’s cost of service

should moreover not be reduced by the deduction from tax

allowance of geological and geophysical expenses, as rec-

ommended by Staff. (9) Tennessee’s cost of service should,

however, be reduced to reflect lower ad valorem taxes, but

not to the full extent sought by Staff. (10) Finally, Ten-

nessee’s cost of service should be reduced to reflect Staff’s

franchise tax figure. (11) Tennessee’s method of cost classi-

fication, allocation, and rate design, with minor exception,

should be accepted, and all the specific customer proposed

alterations rejected, except for Staff’s change to the SO-4

rate.

We also find, however, that the following findings in the

initial decision should be reversed: (1) The composite de-

preciation rate increase to 4% should not permit a corre-

sponding income tax allowance. (2) Front-end advance pay-

ments unexpended by January 1, 1974, should not be dis-

allowed from Tennessee’s rate base. (3) Tennessee’s cost

of service should not be reduced as Staff sought to reflect

greater hydrostatic testing expenses and greater research

and development expenses.

FACTUAL BACKGROUND

The major elements of Tennessee’s proposed rate in-

crease are a depreciation rate increase from 3.6% to

9.75%, inclusion of substantial additional advance payments,

and an increased overall rate of return of 9.25%. Numerous

other cost of service and rate base increases were also pro-

posed by Tennessee.

76a

Staff alone presented evidence and argument against

Tennessee’s cost of service as it took the position that only

$15,696,391 out of the $141,719,530 proposed annual rev-

enue increase should be authorized by the Commission, leav-

ing a $126 million differential between Tennessee and Staff.

Tennessee’s filing is based upon a test year ended February

28, 1973, adjusted for known and measurable changes

through November 30, 1973.

The other parties to the proceeding, mainly wholesale

customers or state commissions, took an active role in this

proceeding only in regard to the issues of cost classifica-

tion, allocation and rate design.

DISCUSSION AND RESOLUTION OF ISSUES

I. Depreciation

Tennessee’s annual depreciation rate had been 3.6% as

a result of the last rate settlement, but it sought an increase

to 5.75% for an initial five year period based on declining

gas production. Staff, on the other hand, would have in-

creased the rate to 4%. Tennessee’s rate would result in

$33,326,358 more depreciation expense than Staff’s rate

would, and both Staff and Tennessee'estimated $65,186,870

of additional revenues needed to provide the 5.75% rate,

of which $32,095,207 represents the associated effect upon

the income tax allowance in the cost of service.

The Administrative Law Judge adopted Staff’s 4% rate

and its straight-line depreciation method, rejecting Ten-

nessee’s use of the accelerated unit of production method.

He found that Staff and Tennessee both basically agreed

upon an annual average depreciation rate of 4% but that

they disagreed as to the method. He viewed Tennessee’s

unit of production method as being based on the growing

gas shortage, the anticipated reduced plant service life, and

an avoidance of excessive future depreciation charges per

unit of gas delivered. While he noted prior Commission

77a

approval of accelerated depreciation,’ he distinguished it

because Tennessee has adequate depreciation accruals for

prior years.

The Administrative Law Judge found Tennessee’s meth-

od to be arbitrary in that it unwarrantedly assumes no

additional future supplies and charges more depreciation

expense to present seryice. This method was also rejected

for Tennessee employs it on a system-wide basis, not relat-

ing specific gas reserves to useful life of specific plant.

In authorizing a depreciation rate increase to 4%, how-

ever, he conditioned it so as not to include a corresponding

increase in Federal income tax liability for no Internal Rev-

enue Service approval of this depreciation methodology

change had been received.

Staff only excepts to the tax portion of this ruling, argu-

ing that Tennessee should be allowed to realize the in-

creased depreciation allowance after taxes have been paid.

Tennessee’s exception to the initial decision is multi-

farious: It first of all asserts that the unit of production

method * is appropriate in cases of supply instability, such

as natural gas, and points to various record evidence of its

declining supplies * to stress the declining usefulness of its

*United Gas Pipe Line Company, Opinion No. 645, 49 FPC

141 (1973).

*The unit of production method (depletion accounting) estab-

lishes a rate of depreciation by using the total units of gas to be

sold during a given time period. Unlike the straight-line method

in which time is the basis and the useful life of plant is the cen-

tral focus, with the unit of production method the difference be-

tween original cost and net salvage value is distributed by the

ratio of annual production of gas to the remaining recoverable gas

reserves.

*The nationwide reserve-life index has declined to 9.7 years

by 1973, Tennessee’s reserve-life index being 10.8 years for the

same period. Also new reserves are being far outstripped by

present deliveries, Present Tennessee curtailment is also noted.

78a

system, quite apart from the traditional service life under

straight-line depreciation. It moreover asserts that the unit

of production method should be used because it fairly and

evenly apportions its remaining investment between present

and future consumers. In addition Tennessee contends that

its method does assume additional future supplies‘ and

that the five year review provision protects the consumer

if its gas supplies increase more than already estimated.

It also contests the finding that Tennessee’s unit cost of

depreciation would decline from 7.5¢ per Mef for the first

ten years to 4¢ for the last ten years, pointing to the impact

of increasing interim retirements, which the Judge did not

consider. Tennessee furthermore would depreciate the dis-

tinction made in the initial decision between its case and

‘nited, supra note 1, arguing first of all that the inade-

quacy of past depreciation charges is not controlling for

it should be forward-looking, and secondly that its system

is newer than United’s and therefore has more undepre-

ciated investment to recoup.

Tennessee attacks Staff’s method which includes all esti-

mated future additions as present supplies, an allegedly

faulty assumption in light of the failure of SNG and LNG

projects: If forecasted supplies do not materialize, Staff’s

method would result in either inadequate depreciation

accrual or substantially increased unit cost of depreciation

for future consumers at a time when the cost of gas supply

will also be much higher.’ It also questions Staff’s failure

to include the plant investment necessary to attach all the

supply additions Staff assumes will result, as well as

*One of Tennessee’s studies (Table 2, Exhibit 1) shows 8 Tcf

addition over 20 years from traditional supply areas, and the

other (Table 3, Exhibit 1) shows this same 8 Tef, as well as

another 14 Tef from non-traditional sources.

5Such eventualities resulting from a deferral of depreciation

recovery to the future under Staff’s method are asserted to vio-

late the Commission’s statutory obligation to establish ‘‘ proper

and adequate rates of depreciation’’ under Section 9 of the Natural

Gas Act.

79a

Staff’s interim retirements figure. Tennessee also reads

Staff’s study to require a 5.15% depreciation rate, thereby

rendering the holding of 4% devoid of record. evidence

support. It attributes this discrepancy to Staff only using

three of the twenty years covered by the study. It also

controverts the Judge’s conciusion that Tennessee’s study

also renders a 4% average annual rate, arguing that it is

error to extrapolate the 20 year study to 25 years for major

retirements were not considered in the study.

Finally Tennessee excepts to the tax impact finding. It

alleges that its depreciation rate for taxes has always been

higher than for book or ratemaking purposes, and it argues

that, since in its prior rate cases this excess tax deduction

was used to reduce its cost of service, it would be incorrect

to now require use of the same rate for book and tax pur-

poses. Also Tennessee cites prior Commission orders in

which the book and tax depreciation rates were not identical.

We find that the initial decision should be affirmed as

to the increase in depreciation rate to 4%. Therefore, Ten-

nessee’s depreciation expense for cost of service should be

reduced from $116,602,993 to Staff’s proposed depreciation

charge of $83,276,635. Tennessee did not meet its burden of

proof to justify its substantial depreciation rate increase:

Its evidence (Exh. 1, T-1, T-10, T-19, 65-69) is primarily

a recitation of various reserve-life indices and the focus

of its rationale echoes Opinion No. 645, which is no longer

viable.” While the Court in Memphis recognized that the

Commission can take into account the exhaustion of natural

resources in establishing depreciation rates for a natural

gas company, it held that the Commission must first of all

find that such exhaustion of natural resources has in fact

caused the useful life of the company’s property to be

° Staff’s study employed a .2% interim retirement rate instead

of Tennessee’s .5% interim retirement rate.

* United, supra note 1, rev’d sub nom, Memphis Light Gas and

Water Division v. F.P.C., 504 F.2d 225 (D.C. Cir. 1974).

80a

reduced to the extent that depreciation based solely on

physical life is inadequate. The Court continued by stating

that, although evidence of a declining reserve life index

increases the risk of a shortened useful life, it was ‘‘not

satisfied with a record that contains only a recitation of

the decline of the reserve life index.’’* Tennessee’s evi-

dentiary presentation would not satisfy the Court and does

not satisfy the Commission.

Staff if the only other party to introduce evidence con-

cerning an increase in the depreciation rate. (Exh. 39, 40,

41, 42, 42A, 43, 43A, 44, 45, 46, 47, 48, S-6, S-7, S-8, and

S-9). Is proposed increase to 4% as adopted in the initial

decision, should be approved. We completely endorse Staff’s

methodology which is discussed below; however, we note

that since the time Staff prepared its evidence the alter-

nate sources of supply relied upon by Staff (SNG, LNG,

Canadian natural gas) have not been realized to the extent

advanced by Staff. Accordingly, this 4% depreciation rate

could well be inadequate, but we are constrained to adopt

this 4% rate: Tennessee failed to satisfy its burden of

proof, and the record upon which we must rely does not

afford us the opportunity to sua sponte forge a different de- |

preciation rate.

It should first of all be explained, however, that, unlike

Tennessee’s system-wide approach, Staff classified its de-

preciable property and assigned separate depreciation rates

to each property class ® which resulted in a composite rate

of 4%.

. Memphis, supra note 7, 504 F.2d at 235.

®* Property Classification Annual Depreciation Rate

Offshore Gathering 6.00

Products Extraction 2.71

Underground Storage 2.42

Transmission 3.83

General 4.00

(Exh. 8-9, p. 7).

8la

Staff then used the unit of production method, supra

note 2 to establish the 6% depreciation rate for gathering

plant since its useful life is related to the useful life of the

gas reserves supplying it. Such a limited application of the

unit of production method is reasonable since the useful

life of gathering plant is necessarily defined by the ascer-

tainable present and future reserves. (xh. S-9, p. 9).

The depreciation rates for the other classes of plant were

developed using the straight-line remaining life method.

This was also a reasonable approach since Staff recognized

that possible changing gas flow patterns would have an im-

pact upon the useful lives of extraction, storage and trans-

mission plant. (Exh. 8-9, p. 10).

The Court in Memphis specifically directed Commission

consideration of ‘‘current Commission policies designed to

increase or sustain industry-wide gas supply,’’ as well as

‘‘the probable extent and location of reserves which United

might utilize at some future date.’’ Supra note 7, 504 F.2d

at 235. Staff introduced evidence in this regard (Exh. S-9,

pp. 11-22): Alaskan reserves, reserves in the lower 48

states, coal gasification, liquified natural gas from Alaska

and overseas, and importation of natural gas from Canada.

Staff related these factors to both industry-wide activities

and also specifically to Tennessee, concluding that ‘‘we are

fast approaching a change-over from almost complete re-

liance upon our own natural gas resources to diversified .

sources international in scope.’’ Staff then applied these

changing gas supply patterns to the various portions of

Tennessee’s plant to ascertain the proper service life, look-

ing specifically for possible resulting material under-utiliza-

tion of plant (major retirements). Staff assigned a 28 year

average remaining service life to storage plant and that

portion of transmission plant which could utilize imported

LNG, Midwestern SNG and Canadian gas. It then assigned

an 18 year average remaining service life to the remainder

of Tennessee’s transmission plant and its extraction plant,

82a

that which can only rely on Tennessee’s historic southwest

gas supply.

From the perspective of the 1972 and 1973 adjusted test

period Staff made the ‘‘reasoned estimate”’ of the useful

life of Tennessee’s plant as required in Memphis, and Staff

is moreover correct in rejecting use of Tennessee’s unit of

production method other than for gathering plant because

the total number of units to be transported cannot be as-

certained with any degree of certainty. The future prospects

of LNG importation, SNG and importation of Canadian gas

appear dimmer than when Staff prepared its evidence, but

based upon the record in this docket, the nature of the Com-

mission’s depreciation rate inquiry under Section 9 of the

Natural Gas Act (the Commission must make a ‘‘reasoned

estimate’’ of the useful life of plant, and its conclusion

must fall within a ‘‘zone of reasonableness’’) warrants

continued cognizance of the potential impact of such event-

ualities upon Tennessee’s gas supply patterns.

We do find, however, that the income tax condition placed

in the initial decision should be removed. Even with this

increase in the book depreciation rate from 3.6% to 4%,

there will be no need to change the tax depreciation rate

since it has been 4.55%. The income tax component of cost

of service is the proper forum in which to consider the

tax impact.

II. Rate of Return

There are two contested issues with respect to the ap-

propriate rate of return to be allowed Tennessee in this

proceeding, viz., the proper earnings level for equity funds

devoted to natural gas transmission operations, and the fair

treatment of discounts arising from the reacquisition of

previously issued debt securities. We turn first to rate of

return to be allowed on the equity portion of Tennessee’s

overall rate of return.

83a

Evidence on rate of return was introduced by our Staff

and Tennessee, although other parties argued the issues on

brief. Evidence on behalf of our Staff was introduced

through the Chief, Division of Finance and Statistics, Ms.

Georgia LeDakis; and that for Tennessee by a private con-

sultant, Mr. W. R. Field, supplemented as to the need for

additional financing by the President of Tenneco, Inc., Mr.

R. EK. McGee. Ms. LeDakis found the then current cost of

equity to Tennessee to be 11.6%, while the evaluation by

Mr. Field yields a range between 13.5% and 14%. The

Administrative Law Judge determined the appropriate al-

lowance to be 12.5% to which both Tennessee, the Staff as

well as other parties except.

Witness LeDakis presented testimony discussing the vari-

ous analytical approaches toward financing cost evaluation

—with particular emphasis on the cost of equity—followed

by a description of the general economic condition of the

country, the pipeline industry, Tennessee and other com-

panies found to be comparable to Tennessee.

Much in Witness LeDakis’ testimony and supporting ex-

hibits is not subject to serious challenge by any party on

cross examination, rebuttal testimony or on brief—nor could

it be, having been based on sound regulatory principles and

economic analysis. We shall therefore utilize Ms. LeDakis’

testimony to set forth several principles which must serve

as the foundation upon which to construct a sound rate of

return judgment in this proceeding.

We begin with the fundamental legal precepts required

in a rate of return calculation. Ms. LeDakis correctly states

at page 24 of her direct testimony: ~

As established by judicial precedent, the prescribed

rate of return under the Comparable Earnings Test

must be:

(a) sufficient to assure confidence in the financial

integrity of the enterprise so as to maintain its

credit standing and to attract capital;

ry eniern erento eameemaneneny

i te aa

84a

(b) it must be commensurate with returns on in-

vestment in other enterprises with corresponding

risk; and

(c) it must recognize the necessity of maintaining

a balance between the interests of investors and

consumers alike.

As indicated above there appears to be little q

This text is long and has been trimmed here. Open the source document for the complete record.

This is a copy of a public record, reproduced as it was published. It is not legal advice, and it may not be the version a court would rely on. Check the official source before you cite it.

A word about cookies

We need a few to keep you signed in and the library working. The rest help us see which pages people use and where they get stuck. They stay off unless you say yes.

Appendix — Tennessee Gas Pipeline Co. v. Federal Energy Regulatory Commission · 445 U.S. 920 | Frix