Petition — Reliance Insurance v. F & D Electrical Contractors, Inc.
Supreme Court brief1978
Ask Donna
What actually matters in this document.
Text
——U —— —ẽ
IN THE
Supreme Court, U. & *
FILE B
APR 21 1s
MICHAEL RODAK, JR.
Supreme Court of the United States
OctToBER TERM, 1977
No. 7 7 * 1 5 6 9
RELIANCE INSURANCE COMPANY, Petitioner
V.
F & D ELROTRICAL Contractors, Inc.; J. H. COPELAND
& Sons Construction, Inc.; and UNITED STATES
or AMERICA, for the Use and Benefit Of Gray-BaR
ELECTRIC Company, Inc., Respondents
PETITION FOR WRIT OF CERTIORARI TO THE
UNITED STATES COURT OF APPEALS
FOR THE FIFTH CIRCUIT
—
WIIILIAM KNIGHT ZEWADSKI
WILIAM C. FRYE
MicRHAREL C. ADDISON
TRENAM, SIMMONS, KEMKER,
ScHarF, BARKIN, FRYE
& O’NEDLL,
PROFESSIONAL ASSOCIATION
Attorneys for Petitioner
Post Office Box 1102
Tampa, Florida 33601
(813) 223-7474
April 20, 1978
Press or Brno S. ADAMS PRINTING, INC., WASHINGTON, D. C.
6
, CLERK
ON
—
ERMA SSNVTO gos guoo s o JOZOVI}UOOGNS ey} SpuTq Hege pus euere eq
r ee
Step o¢sfoeds—uou fo sneosg eousiczoyaed uopueqe o νj,ᷣ guns e uro)
Prem Sf Jo sousuzoyzed wm s,qns eu perpedut peu sfetep sua yey so outs sd
esneo sen sep orf Ded yotym aon d o duese you pp qus euy enn pus szeps0
mx Suso JO g mse g s sB qusuute nog eg Aq pegus se suUOTSUSyxXe surpꝗ ka pez6ao0o
ATTeFIUeYsqns Sen SfeTep syy egen g fond ed Zupqerdwod ut sffTep jo yMser eB se
PORBIZUCOgGNS B IO YyOReT] [eT eye s pero peu 10,981},U0D yuewUZEAO; s 78U} ZuUTpPTOY
ur Te MOTEQ qm SY} PTq (2) guotyeTdmoo ut step pus Aon UT seBueyo og yoOedsSer
xs nern eupad e Jo seppeusg pus Uf oy} cuxeno? {ns Ts apf eu ey} Jue pXSe Suse
SS. om 0} S7OBIT3QUOO UOTZONA}SUO0D queunzeac’ uo SIOPOBIjUOOGnNS jo sorpenes oan Squ2ta
ey} UIEAOS STI Teiepey WsostuN eB pTNoYs (J) :pezueseid suotjseny
oo | qa0q
| J@AOD og pessesse rsxmfTsedoid Sten sezeuep ey, eue ‘souezTTTp Jo ot syt yo
esneoeq peteyins seZeuep Te og dose. q ur oda ST pus s aepao Suso 0} enp 84800
Tuo rap pps Tĩe o *yoerjzuooqns ey gepun ‘eTQeTT sr eutad eu, euer JO FORT
s Surf ad eꝗꝗ pus 5 .1epi0 eZueyo — ey :A@TOp Jo sesnso Om} eden S.1eq} 2
8 uo aS q TenjoOsrjU09 SA JO yoRerg s ennꝗrsuoo o TeTszeyeU ATIUETOT IIMS ings —
Keep S,eutad eq 2843 UCTSNTOUOD ey, yzoddns oh SoUepTAS quspunqs ST Su- ‘se
| * e, du ed dafrn SdUSEIETIEWUT PTOAR og SB OS n eng duruaogaed pus du tupeuos
UF eg ted 03 ufd eu perpnber 30 uðõ,yöaꝗq pn eu *eouBsutojied uopuege o
a eu) NN de Tetaegen e
IOYOeIjUOOGNS ed u Ha raue srqꝗq a 30 uõ
9 YO) Ho teꝗ Zur Ny—ydoeeig--SpoeT}UoognS—SjoOeajUoD Nö zu
*
3 :Petta drr N
ROTASY TAN Slezang
———
which prevents 43 @overnment caused delays from justifyin: the contractor's
lectrical Contractors,
—
*
—
Insurance Co. v. Fa D
abandonment or withdrawal? (Reliance
4/21/78)
Ins., Sup Ct. 77-1509, petition filed,
TABLE OF CONTENTS
Page
Oprsions BELOW .....---eeeeeeeeerereeseeretettet® 1
Juni roc „„ 2
Oursrioxs PRESENTED nnn 2
Srarutory Provisions INVOL IW... 3
3
STATEMENT OF THE Cas...
REASONS FOR GRANTING THE WRIT
I. The Decision Of The Court Of Ap Should
Have, But Did Not, Enforce A Uniform Federal
Rule Governing The Rights And Remedies Of
Subcontractors On Government Construction
Contracts To The Same Extent That The Fed-
eral Rule Governs The Rights And Remedies
Of A Prime Contractor With Res To
Changes In The Amount Of Work Delays
In The Time Of Completion. The Court Below
Erroneously Decided An Important tion Of
Federal Law Which Has Not Been, But Should
Be, Settled By This Court
Il. The Decision Of The Court Of Appeals, Which
Held That A Subcontractor On Government
Project Which Underwent Significant Govern-
ment-Imposed And Ti Extensions
Could Establish A Material Breach Of The Sub-
contract Which Excused Further Performance
Based On The Mere Existence Of 2 In
Completion Without Establishing IIow ose
Delays Prejudiced His Performance, Conflicts
With Decisions Of The United States Court Of
Claims And Other Courts Of Appeal, And De-
cides An Important Question Of Federal Law
Which Has Not Been, But Should Be, Settled
By This Court..
ii Table of Contents Continued
Page
III. The Decision Court Of Appeals, Which Held
That The Portion Of The ‘‘Disputes’’ Clause
Which gy The Contractor To ‘‘Proceed
Diligently With The Performance Of The Con-
tract’’ In The Event Of A Dispute Over A De-
lay In The Time Of Completion Was Not In-
corporated By Reference Into The Subcontract,
Conflicts With A Decision Of Another Court Of
Appeals And Presents An Important Federal
estion Which Has Not Been, But Should Be,
rer.. ee 13
GGG 16
rale eee be eee e ee 1a
r e 10a
BOE BD c 15a
rr. . 16a
1 Wek 0c 00 eh ewdisians 20a
r cagnebanessteensebosaenast 23a
CasEs :
Bruno Law And Richard Marlink, Trustees In Dis-
solution For Daniel J. Cronin, Inc. v. The United
States, 195 Ct. Cl. 370 (Ct. Cl. 1971) ....... 9, 10, 11
H. W. Caldwell & Son, Inc. v. U.S. For John H. Moon
& Sons, Inc., 407 F.2d 21 (Sth Cir. 1969) ...... 15
Commerce International Company v. United States,
338 F. ad 81 (Ct. Cl. 1964) .............. 9, 10, 11-12
Discount Co., Inc. v. United States, 554 F.2d 435 (Ct.
Cl.), cert denied, —— U.S. ——, 54 L.Ed.2d 298
1 chancbiee e 6
McDaniel v. Ashton-Mardian Company, 357 F. 2d 511
n RR ere Ry 6, 9, 14
F. 1 Co. v. Industrial Lumber Co., 417 U.S. 116
„c sadaieeiin 7
United States v. Citizens & Southern Nat. Bank of
Atlanta, Ga., 367 F.2d 473 (4th Cir. 1966) ...... 9
Table of Contents Continued iii
Page
United States, Etc. v. J. H. Copeland d Sons, 568
F.2d at 1159 (5th Cir. 1978) .......... ae 14
United States v. F Construction Corporation, 423
V EE, BE coc vcccccesccecccescce 15
United States v. Rice, 317 U.S. 61 (1942) ......... 6, 14
STaTUTEs:
r ...t eee 3
r ¶ r.. cisbvedsesaceeoes 1,2
r ᷑ .... 3
IN THE
Supreme Court of the United States
OctoBER TERM, 1977
No.
RELIANCE INSURANCE CoMPANY, Petitioner
V.
F & D ELREOCTYRNCAL Contractors, INC. J. H. CoPELAND
& Sons Construction, INC.; and Unrrep States
or AMERICA, for the Use and Benefit Of Gray-Bar
EvLectric Company, Inc., Respondents
PETITION FOR WRIT OF CERTIORARI TO THE
UNITED STATES COURT OF APPEALS
FOR THE FIFTH CIRCUIT
Petitioner, Reliance Insurance Company, prays that
a Writ of Certiorari be issued under 28 U.S.C. § 1254
(1) to review the opinion and judgment of the United
States Court of Appeals for the Fifth Circuit entered
in this proceeding on March 27, 1978.
The opinion of the Court of Appeals for the Fifth
Circuit is reported at 568 F.2d 1159 and reprinted in
Appendix A. The opinion of the United States District
Court for the Southern District of Florida is not re-
ported and is reprinted in Appendix B.
2
JURISDICTION
The judgment of the Court of Appeals for the Fifth
Circuit was entered on March 27, 1978, and is re-
printed in Appendix C. This Petition for Certiorari
was filed within 90 days of that date.
This Court’s jurisdiction to review the judgment
below is based on 28 U.S.C. § 1254(1).
QUESTIONS PRESENTED
1. Should a uniform federal rule govern the rights
and remedies of subcontractors on government con-
struction contracts to the same extent that the federal
rule governs the rights and remedies of a prime con-
tractor with respect to changes in the amount of work
and delays in the time of completion?
2. Whether the Court below erred in holding that a
government contractor had committed a material
breach of a subcontract as a result of delays in the
completion of the construction project, where the de-
lays were substantially covered by time extensions
granted by the government as a result of government
change orders and where the subcontractor did not at-
tempt to prove which specific delays were caused by
the contractor or that the delays had impaired the
subcontractor’s performance of his portion of the
work?
3. Whether a subcontractor on a government con-
struction project is permitted to abandon his portion
of the construction because of non-specific delays in
the time of completion caused by the contractor when
the subcontract incorporates by reference, and thereby
binds the subcontractor to, a contractual clause which
3
prevents government caused delays from justifying
the contractor’s abandonment or withdrawal!
STATUTORY PROVISIONS INVOLVED
The pertinent portions of the Miller Act (40 U.S. C.
§§ 270a, et seg.) and the Small Business Act (15 US.
C. § 637) are set forth in Appendix D to this petition.
STATEMENT OF THE CASE
The Small Business Administration (SBA) was the
original prime contractor on a government construc-
tion project located in Miami, Florida. The contract
concerned Phase II of the expansion and moderniza-
tion of the Miami air route traffic control center. Pur-
suant to the provisions of Section 8(a) of the Small
Business Act (15 U.S.C. §637(a)), the SBA con-
tracted with a minority contractor, J. H. Copeland &
Sons Construction, Inc. (Copeland), to perform the
actual functions of the general contractor. The con-
struction commenced on January 15, 1973 and was to
be completed in 365 days (January 15, 1974). Cope-
land entered inte a subcontract with F & D Electrical
Contractors, Inc. (F & D), which required that com-
pany to perform the electrical work for that project.
That subcontract was for approximately 25 percent
of the prime contract amount.
The contract between Copeland and the SBA incor-
ported by reference the General Provisions applicable
to government construction projects (Standard Form
23-A). Paragraph 3 of the General Provisions (Ap-
pendix E, p. 20a) obligated the contractor to accept
as binding the change orders issued at any time by the
government Contracting Officer which made any
change in the work within the general scope of the
4
contract, including changes which caused an increase
in the cost of, or time required for, performance of
the work under the contract. Under that clause, if the
contractor did not agree to accept the amount of
money, if any, proffered by the Contracting Officer to
compensate him for the increased cost, the contractor
was entitled to seek an equitable adjustment of the
contract price and time of completion. The contractor
was not free to abandon the contract.
F & D executed a subcontract with Copeland which
incorporated by reference the General Provisions of
Copeland’s contract with the SBA and specifically
provided that F & D shall assume toward the Con-
tractor all of the obligations and responsibilities which
the Contractor, by [the Contract] Documents, assumes
toward the Owner... . (Appendix F, p. 23a).
The work required under the contract was not com-
pleted according to the proposed schedule. Various
change orders expanding the amount of work required
were issued by the Contracting Officer. As of August
8, 1974, the date F & D ceased work and abandoned
the project, various formal contract modifications had
been executed which increased the time allowed for
completion to June 12, 1974, and increased the con-
tract price as well. Although negotiations were still
proceeding with respect to additional time extensions
as of August 8, no decisions had yet been reached to
extend the time for performance beyond the 513 day
periods already allowed.
F & D announced that the failure of the contractor
to receive a formal commitment extending the contract
completion date beyond June 12, 1974, resulted in F
& D no longer having a binding subcontract and there-
a eee Pe
——ͤ— ee
Ce ed
9 ee see at ee 2
——
5
fore F & D abandoned the project on August 8, 1974.
In February of 1975 the government executed an ad-
ditional modification which extended the allowed time
for completion an additional 296 days, which exten-
sion moved the completion deadline well beyond Au-
gust 8, 1974, F & D’s withdrawal date.
Copeland brought in a substitute electrical subcon-
tractor in August of 1974 to complete that portion of
the project left undone by F & D. The completion cost
of the electrical work exceeded the balance of the sub-
contract price, including retainages. F & D, when sued
by one of its suppliers, cross-claimed against Copeland
and Reliance Insurance Company, the Miller Act
Surety, for delay damages allegedly incurred by it
prior to August 8, 1974. Copeland cross-claimed
against F & D for the completion cost on the electrical
work in excess of the remaining contract balance, in-
cluding retainages. The District Court had jurisdic-
tion of the claims pursuant to U.S.C. § 270b(b). The
trial court, after a non-jury trial, ruled that Copeland
had breached the terms of the subcontract by being
the party substantially responsible for some of the
delays in completion, and awarded F & D the delay
damages sought and refused to compensate Copeland
on its counterclaim for completion costs. The United
States Court of Appeals for the Fifth Circuit af-
firmed, holding that it was not necessary to point to
specifie delays, which in turn prevented or impeded
specific items of work, in order for F & D to prove
the existence of a breach of the subcontract and that
Copeland caused nonspecific delays which entitled F
& D to abandon the subcontract. The petition for cer-
tiorari was filed to review that ruling.
6
REASONS FOR GRANTING THE WRIT
I. The Decision of the Court of Appeals Should Have, But Did
Not, Enforce a Uniform Federal Rule Governing the Righis
and Remedies of Subcontractors on Government Construction
Contracts to the Same Extent That the Federal Rule Governs
the Rights and Remedies of a Prime Contractor With Respect
to Changes in the Amount of Work and Delays in the Time
of Completion. The Court Below Erroneously Decided an
Important Question of Federal Law Which Has Not Been. But
Should Be, Settled by This Court.
There is no question that, under the terms of the
contract with the government, the prime contractor
cannot legitimately abandon his performance of the
work if the Contracting Officer, pursuant to the
“Changes’’ provision, increases the amount of work
required of the contractor. This is true even if the
additional work increases the cost of performance or
adds to the time required for completion. See gener-
ally, United States v. Rice, 317 U.S. 61, 65 (1942);
Discount Co., Inc. v. United States, 554 F.2d 435, 440
(Ct. Cl.), cert. denied, —— US. „54 L.Ed.2d 298
(1977); and McDaniel v. Ashton-Mardian Company,
357 F. 2d 551, 514-15 (9th Cir. 1966). Continued per-
formance of the contract is in the publie interest, and
the end result is a uniform rule which in general holds
that government caused delays do not justify aban-
donment of further performance by the contractor.
The Court of Appeals for the Fifth Cireuit has re-
fused to make equally applicable to the subcontractor
this federal rule with respect to delays, and this re-
fusal has occurred despite the fact that the General
Provisions of the prime contract have been clearly
and unequivocally incorporated into the subcontract.
Under the decision of the Court of Appeals, delays
which are the natural and proximate result of govern-
7
ment-imposed change orders can never excuse further
performance by the prime contractor, but those same
delays may serve to excuse further performance by
subcontractors and justify their abandonment of the
project. This ruling clearly frustrates the public in-
terest in continued performance, especially when it is
noted that the bulk of the work required under the
contract in suit was to be performed by the subcon-
tractors on the project. The Contractor is put in an
impossible situation and the parties to the contract
and subcontract are denied the benefits of a uniform
rule which will serve to avoid the pitfalls which re-
sult from an attempt to apply an ad hoc rule. See F.
D. Rich Co. v. Industrial Lumber Co., 417 U.S. 116,
127 (1974). This case presents an important federal
question concerning the interpretation of federal law
as it applies to widely used standard form contracts
and subcontracts for government construction. Peti-
tioner submits that the United States Court of Ap-
peals was in error in refusing to adopt a uniform
rule which will bind both the prime contractor and
the subcontractor to remain on the job and complete
the project even if delays are experienced in the time
for completion.
8
Il. The Decision of the Court of Appeals, Which Held That a
Significant Government-Imposed Changes and Time Exten-
sions Could Establish a Material Breach of the Subcontract
Which Excused Further Performance Based on the Mere
Existence of Delays in Completion Without Establishing How
Courts of Appeal, and Decides an Important Question of
Federal Law Which Has Not Been, But Should Be, Settled
by This Court.
The United States Government, through its various
departments, bureaus and agencies, is involved in bil-
lions of dollars of construction on thousands of pro-
jects throughout the United States every year. In ac-
cordance with standard government contracting pro-
cedure, the general contractor is required to assent to
the General Provisions for Construction Contracts,
Standard Form 23-A, which requires the general con-
tractor to agree to perform changes in, or additions to,
the project at any time during the course of construc-
tion when crdered to do so by the Contracting Officer.
The Contractor is not free to abandon the project or
refuse to perform the required extra work because
his costs or time of performance will be increased.
Paragraph 3 of the General Provisions (App. E, p.
20a) sets forth the procedures by which the con-
tractor will be protected if he can establish that the
required changes have in fact increased his costs of
performance or caused him actual delay in the time of
completion.
The portions of the prime contract which prevent
potentially expected cost increases or completion de-
lays from serving as a predicate for a claimed breach
of contract applied with equal force to the subcontract
9
between Copeland and F & D. Article 11 of the sub-
contract (App. F, p. ——) provided that F & D would
assume toward Copeland all the obligations Copeland
had assumed toward the government. These responsi-
bilities and obligations towards the contractor should
have barred F & D’s argument that a material breach
of the subcontract had occurred which would excuse
further performance based merely on a delay in the
estimated completion date of the project.
Cases arising out of delays in government construc-
tion projects have consistently held that a contractor
which had experienced delays in performing govern-
ment contracts could not establish the existence of a
breach of contract by merely proving government
caused delays—a breach of contract is not proved un-
til the contractor establishes (1) a delay in perform-
ance (2) caused by the government’s failure to per-
form an obligation defined by the contract (3) which
failure was solely responsible for preventing the con-
tractor from performing a specific item, or specific
items, of work under the contract, and (4) thereby
damaged the contractor. See Bruno Law And Richard
Marlink, Trustees in Dissolution for Daniel J. Cronin,
Inc. v. The United States, 195 Ct. Cl. 370, 381-87 (Ct.
Cl. 1971); Commerce International Company v.
United States, 338 F.2d 81, 89-90 (Ct. Cl. 1964);
United States v. Citizens & Southern Nat. Bank of
Atlanta, Ga., 367 F.2d 473, 480-81 (4th Cir. 1966) ; and
McDaniel v. Ashton-Mardian Company, 357 F.2d 511,
514-15 (9th Cir. 1966). Delay in the abstract is mean-
ingless, and proof that the completion of a construc-
tion project was behind schedule proves nothing—it
does not support cancellation of a subcontract; it does
not prove that subcontractor’s obligation to complete
10
his portion of the work has expired; and it does not
prove that the subcontract has been breached in a
manner which would justify abandonment of the
project.
The Court of Appeals rejected this rule and the
cited cases in affirming the judgment awarded to the
subcontractor in this instance. In its opinion the Court
of Appeals acknowledged that the subcontractor had
not attempted to prove which part of the delay, if
any, was the responsibility of Copeland as opposed to
the responsibility of the government. The rationale for
ignoring the rule of Bruno Law, supra, and Com-
merce International, supra, was based on the inter-
pretation that the rule established in those cases was
applicable only to the amount and quality of proof
necessary to allow an award of money damages, and
held that it did not apply to the question of whether
a material breach had in fact occurred. As the Court
of Appeals concluded on this issue:
[Bruno Law and Commerce International] con-
cerned the proof necessary to establish not merely
the fact_of breach of contract but the amount of
damages assessable against the United States as a
result. The exacting rules conditioning the deter-
mination of damages against the sovereign for tts
delay do not prescribe what constitutes a breach
of contract by a private party for purposes of ex-
— further performance. [Emphasis sup-
pli
568 F. 2d at 1161.
The conclusion of the Court of Appeals ignores the
holdings of those cases and, therefore, results in a de-
cision which is in direct conflict with them. A brief
extract from each of those opinions will demonstrate
11
that the amount and specificity of proof required was
necessary to establish the ezistence of a material
breach of the contract, not to determine the amount
of damages which would be recovered if a breach was
otherwise proven. In Bruno Law, 195 Ct. Cl. at 382,
the failure of the plaintiff to establish a breach of con-
tract in the first instance was noted in the following
language:
The evidence, however, demonstrates that many
of the ineidents relied on by plaintiff were iso-
lated and nonsequential, and therefore could not
possibly have caused any significant delay in the
overall progress of the project. Furthermore, with
respect to the great bulk of such incidents, platn-
tiff has failed to prove, or indeed even to attempt
to prove, the crucial fact of the specific extent of
the alleged wrongful delay to the project opera-
tions caused thereby. For the most part, it has
not even attempted a reasonable approximation
based upon some rational theory. Instead, the
plaintiff typically relies on each instance as con-
stituting wrongful action which ‘contributed to
the delayed completion’ of the particular building
or installation ‘and of the project as a whole,
without indicating whether such ‘contribution’
was one day, thirty days, or any reasonably accu-
rate — of time. Plaintiff simply takes the
original and extended completion dates, computes
therefrom the intervening time or overrun, points
to a host of individual delay incidents for which
defendant was allegedly responsible and which
‘contributed’ to the overall extended time, and
then leaps to the conclusion that the entire over-
run time was attributable to defendant. [Empha-
sis supplied].
Similarly, the plaintiff did not prove a material
breach of the contract under consideration in Com-
12
merce International, 338 F.2d at 89, because the delays
which occurred were not shown to have substantially
interfered with the progress of the work required of
the plaintiff :
Causation. Similarly plaintiff has not persuaded
us that the Commissioner was wrong in his alter-
native conclusion that any undue delays on de-
fendant’s part (with respect to the parts) have
not been shown to have interfered with produc-
tion. Plaintiff must admit that, no matter un-
reasonable the Government’s delay, there can be
no recovery without proof that that delay caused
material damage. [Citations omitted]. In the
evidentiary record made in this case there is much
to support the Commissioner’s determination that
such proof has not been made.
The primary lack is plaintiff’s complete failure
to link its accountants’ general survey of the
amounts of time taken by the Government (in the
requisitioning process) with the course of the
plaintiff’s operations.
* * *
Without any specific proof, we are asked to
assume that plaintiff’s serious production diffi-
culties through part shortages were all due to un-
due Government delays—even though other sub-
stantial causes for these difficulties have been ad-
vanced, much of the defendant’s cannot on
any view be deemed unreasonable, there could
not have been any in jurious delay-effect with re-
spect to the large number of — requests
(for parts) which were u . Plaintiff has
contended itself with broad — when spe-
cificity is essential. [Emphasis supplied].
If F & D had been able to prove that specific omis-
sions of Copeland caused it specific, unreasonable de-
13
lays in the performance of the subcontract, compen-
satory damages for the delay would have been avail-
able under the subcontract. Instead of adopting this
recognized legal principle, the Court of Appeals ig-
nored the very real differences betweea delay, breach
of contract, and material breach of contract which
excuses further performance, and help that the sub-
contractor could legally abandon a partially completed
project when the project was, by no substantial fault
of the contractor, delayed beyond the original time
of completion.
Petitioner submits that the decision of the United
States Court of Appeals for the Fifth Circuit on the
standard of proof required to establish a material
breach of a government contract which would serve to
excuse further performance by the subcontractors
conflicts with decisions of the United States Court of
Claims and other Courts of Appeal, and that this
Court should resolve the issue presented.
Ill. The Decision Court of Appeals, Which Held That the Portion
of the “Disputes” Clause, Which Requires the Contractor to
“Proceed Diligenily With the Performance of the Contract
in the Event of a Dispute Over a Delay in the Time of Com-
pletion Was Not Incorporated by Reference Into the Subcon-
tract, Conflicts With a Decision of Another Court of Appeals
and Presents an Important Federal Question Which Has Not
Been. But Should Be, Decided by This Court.
The last sentence of paragraph (a) of the Dis-
putes“ Clause of the General Provisions for construc-
tion contracts (App. E, p. 20a) provides that “the
Contractor shall proceed diligently with the perform-
ance of the contract and in accordance with the Con-
tracting Officer’s decision’’ pending a final decision on
a dispute concerning a question of fact under the con-
14
tract. This clause, in conjunction with the Changes“
provision (App. E, p. 20a), requires a prime con-
tractor to remain and complete his performance under
a government construction project when the Contract-
ing Officer orders work which was not required under
the terms of the original plans and specifications. See
United States v. Rice, 317 U.S. at 65-66. Although the
subcontract between Copeland and F & D specifically
incorporates by reference, and binds the subcontractor
to, the ‘‘Contract Documents between the Owner and
Contractor,” the Court of Appeals ruled as a matter
of law that this portion of the Disputes Clause of the
General Provisions was not incorporated by refer-
ence. See United States, Etc. v. J. H. Copeland &
Sons, 568 F.2d at 1160. Had the Court of Appeals
ruled that F & D was bound by its subcontract to
“proceed diligently with the performance of the con-
tract,” the abandonment of the job by F & D on Au-
gust 8, 1974, would not have been excused and would
in fact amount to a material breach of its obligations
under the subcontract.
The decision of the United States Court of Appeals
for the Fifth Cireuit on this point is in conflict with
the decision in McDaniel v. Ashton-Mardian Com-
pany, 357 F.2d 511 (9th Cir. 1966), which adopted the
language of the District Court in holding that the sub-
contract had sufficiently incorporated the General
Provisions of the government contract to prevent the
subcontractor from relying on delays occasioned by
government-imposed change orders for the recovery
of “anything other than the direct costs of the addi-
tional work and equitable time extensions for any ad-
ditional time required for performance of the
changes.” 357 F.2d at 516.
= >:
fay
The Court of Appeals e cases below relied on
its previous holdings in United States v. Fryd Con-
struction Corporation, 423 F.2d 980 (5th Cir. 1970),
and H. W. Caldwell & Son, Inc. v. U.S. For John H.
Moon & Sons, Inc., 407 F.2d 21 (5th Cir. 1969), to
justify its conclusion that the subcontractor could
justifiably abandon the project if a time delay was ex-
perienced as a result of government change orders is-
sued to the contractor. A review of those cases clearly
establishes that they involve issues completely differ-
ent from those presented in this action and provide
no basis for the conclusion of law reached by the
Court of Appeals. There was no challenge in the case
below to the right of the subcontractor to institute
suit under the Miller Act—what was challenged was
F & D’s right to abandon the project before it was
completed.
Petitioner submits that the decision of the Court of
Appeals, if allowed to stand, will substantially dis-
turb relationships between the contractor and his sub-
contractors on government construction projects, and
the lack of a uniform rule among the circuits on this
issue will raise serious questions about the rights and
liabilities of a contractor who is required to accept
and perform government change orders. This serious
question of federal law should be resolved by this
Court.
16
CONCLUSION
For the reasons set forth above, this Court should
grant this petition for a writ of certiorari.
Respectfully submitted,
WILIA KNIGHT ZEWADSKI
WuLIAM C. Frye
MicHAEL C. ADDISON
TRENAM, SIMMONS, KEMKER,
ScuarF, BaRKIN, FRYE
& O’NEILL,
PROFESSIONAL ASSOCIATION
Post Office Box 1102
Tampa, Florida 33601
(813) 223-7474
Attorneys for Petitioner : A P P E N D 1 X
la
APPENDIX A
UNITED STATES DISTRICT COURT
SOUTHERN DISTRICT OF FLORIDA
No. 75-253-Civ-PF
Unirep States or America for the use and benefit of Gray-
BAR Exectric Company, Inc., a New York Corporation,
Plaintiff,
vs.
J. H. Copetanp & Sons Construction, Ivc., a corporation;
RRLIAN CR Insurance Company, a corporation; and F &
D ELxOTRICAL Contractors, IN., a corporation,
Defendants.
Findings of Fact and Conclusions of Law
(Filed February 23, 1976)
The use-plaintiff, Graysar Exectric Company, Inc.,
(hereinafter referred to as Grayspar) brought this action
under the Miller Act, 40 U.S.C. S 270a-270d, as a supplier
of materials to the subcontractor, F & D Execrricat Con-
Tractors, Inc. (hereinafter referred to as F & D). The
prime contractor on the government construction was the
defendant, J. H. Copetanp & Sons Construction, Inc.
(hereinafter referred to as CopeLanp), and the Miller Act
bond was written by the defendant, Reviance Insurance
Company (hereinafter referred to as Retiance). F & D filed
a crossclaim against CopeLanp and Rewiance for sums al-
legedly due as a result of labor and materials furnished by
F & D to the government project in question. CopELanp, in
turn, filed a crossclaim against F & D for damages occa-
sioned by F & D’s alleged breach of the subcontract between
these parties.
Prior to the non-jury trial of this matter, the claim of
GrayBar against Reviance and CopeLanp was settled and
Graybar recovered the sum of $13,000.00; on the stipulation
2a
of the parties, the claim of GrayBar against F & D was dis-
missed without prejudice. This case, therefore, proceeded
to trial on the crossclaims of the defendants alone.
CopeLanp was the prime contractor on the government
project known as Modernization and Expansion of ARTCC
(Phase II) (hereinafter referred to as the project). F & D
entered into a subcontract with CopeLanp dated January
29, 1973, wherein F & D agreed to furnish electrical work,
including labor and materials, for the project in the initial
base amount of $525,000.00. Article 3 of the subcontract
provided that the work would commence on January 15,
1973 and would be completed on or before January 15, 1974,
with a penalty for delays at $500.00 per day.
Although the subcontract was scheduled for completion
on or before January 15, 1974, the project itself was behind
schedule on that date and, consequently, the subcontract
was not completed. By letter dated January 22, 1974, Copr-
LAND advised F & D that the prime contract had been ex-
tended by and through Modification No. 3 and that the re-
vised completion date for the project was June 8, 1974. F
& D, by its own admission, acceded to Modification No. 3
and remained on the project through June 8 and thereafter
until August 8, 1974.
During those months encompassed by Modification No. 3,
F & D asked Corglaxp to process certain claims through
the government for cost overruns and expenses for delays
which F & D had incurred on account of the extension of
the prime contract. CopeLanp complied with F & D’s re-
quest, and, by letter dated July 18, 1974, informed F & D
that the government had approved funds for the 144 ex-
tension authorized by Modification No. 3.
On July 23, 1974, F & D, Corxrlaxp and representatives
of the SBA held a meeting. At that gathering, F & D an-
nounced that time for performance of its subcontract had
expired; that no new time for completion of that subcon-
tract had been agreed upon; and that F & D had received
3a
no compensation for its extra time on the job. F & D tur-
ther stated that it could not be expected to continue to fur-
nish labor and materials to the project without some con-
tractural arrangement between it and CorRLAxp as to a new
completion date of the subcontract, together with adequate
compensation for labor and materials previously furnished
and to be furnished, should the job continue.
The only concrete result of the July 23 meeting was the
agreement between F & D and Corlaxp that F & D would
supply three men on the job to continue electrical work for
a reasonable time pending negotiations of F & D’s demands.
Two weeks passed, however, without any affirmative action
on the requests of F & D. On August 7, 1974, CopeLanp de-
manded that F & D supply six electricians to the project;
F & D refused. Finally, on August 8, F & D withdrew from
the job.
There is no disagreement among the parties to this law-
suit that the project in question was crippled by lengthy
and costly delays. The parties have differing opinions, how-
ever, as to the responsibility for those delays and the legal
duties of F & D relative to those delays. F & D contends
1) that, on August 8, 1974, the time for completion of the
subcontract, as extended by Modification No. 3, had expired ;
2) that CorxLAxD had materially breached the subcon-
tract by creating lengthy and costly delays; and
3) that F & D was justified, therefore, in abandoning the
subcontract.
CoreLanp counters the arguments of F & D and asserts
1) that the subcontract incorporated by reference the
provisions of the general contract;
2) that, under the incorporated terms of the prime con-
tract, F & D was obligated to perform its electrical work
regardless of any delay which the government might occa-
sion in regard to changes in the“project ;
bone —
4a
3) that the delay of the compietion of the subcontract
beyond January 24, 1974, was caused in substantial part by
the actions of the government and by other forces beyond
CopELanp’s control; and
4) that, therefore, F & D breached its subcontract by
abandoning the project on August 8, 1974.
In order to resolve the legal issues in the case at bar,
this Court must consider two questions. The first question is
whether the subcontract between Cormaxp and F & D in-
corporated, by reference, the provisions of the prime con-
tract between the United States and Copge.anp, specifically
General Provision Three of Standard Form 23-A which
provides:
The Contracting Officer may, at any time, by written
order, and without notice to the sureties, make
changes in the drawings and/or specifications of this
contract if within its general 14 If such changes
cause an increase or decrease in the Contractor’s cost
of, or time required for, performance of the contract,
an equitable adjustment shall be made and the con-
tract modified in writing accordingly.
Having reviewed the various documents and considered
the evidence adduced at trial, this Court is constrained to
answer this first question in the affirmative. Article One of
the subcontract provides that the agreement between the
owner and the contractor, including the general and special
conditions applicable thereto, is incorporated by reference
into the subcontract and, therefore, those provisions become
applicable to the subcontract. As a result of this incorpora-
tion by reference, F & D became obligated to abide by the
terms and conditions of the general contract with respect
to all applicable provisions, except the ‘‘disputes’’ clause
contained in General Provision Six. See H. F. Caldwell &
Son, Inc. v. U.S. for the use of John H. Moon d Son, Inc.,
407 F. 2d 21 (5th Cir. 1969); McDaniel v. Ashton-Merdian
5a
Co., 357 F.2d 511 (9th Cir. 1966). This Court also notes
that, prior to the date that F & D left the project, F & D
asked Cor Lax to process through the government certain
claims for cost overruns and expenses for delay which F &
D had incurred in connection with its performance under
the subcontract. The actions of F & D in this regard con-
stituted an express recognition of the fact that the sub-
contract incorporated, by reference, the provisions of the
prime contract between the United States and CopeLanp.
Having concluded that the general provisions of the
prime contract, with the exception of the ‘‘disputes’’ clause,
were incorporated by reference into the subcontract, this
Court is of the opinion that, on August 8, 1974, it would
have been a breach of the subcontract for F & D to abandon
work if the delays, which F & D now asserts to justify its
actions, were occasioned in substantial part by government-
ordered changes or other factors reasonably beyond Corx-
Laxp's control. If, on the other hand, those delays were
caused in substantial part by CopeLanp and were of a na-
ture that they constituted a material and fundamental
breach of the subcontract, then F & D had a right to aban-
don the subcontract and refuse to complete its electrical
work on the project. The second question which this Court
must resolve, therefore, is who, or what, was substantially
responsible for those delays which prompted F & D on Au-
gust 8, 1974, to completely abandon its contractural obliga-
tions to CopELAND.
If there are two facts which surface from the extensive
evidence and lengthy testimony in the case sub judice, they
are, first, that the project in question was subject to serious
delays before the ink was even dry on the prime contract
and, second, that CoprLanp was, in substantial part, the
cause of those delays. The evidence is clear that CoprLanp
did not get subcontractors signed up for the project until
many weeks after the execution of the prime contract. The
evidence is also clear that CorxlaxD was continuously be-
6a
hind in the general construction areas of the project and,
therefore, that F & D was literally unable to install con-
duits, pull wires, and other work because the buildings and
areas involved were not structurally ready for same. Al-
though some of the delays on the project were beyond the
control of CopeLanp and were recognized as such by the
government, the evidence reveals that most of the delays
were a direct result of CopeLanp’s inability to move con-
struction forward as scheduled, to properly coordinate the
subcontractors, and to provide the type of supervision ne-
cessary for such a project.
Furthermore, the testimony and the evidence show that,
even in the face of CopeLanp’s dehabilitating delays, F & D
‘‘walked the last mile“ in an attempt to reach an agreement
for the completion of electrical work at the project. With
no government extensions in existence, F & D stayed on the
job after the July meeting and maintained three men in the
hope that some decisions would be made as to a final com-
pletion date and as to additional compensation for ‘‘delay
overhead’’. The record reveals that, instead of affirmative
action on its demands, F & D received a telegram on August
7 in which CopeLanp demanded that F & D supply six men
to the project. At that point, this Court is of the opinion
that F & D was justified in abandoning the job; after all,
enough is enough.
In summary, this Court concludes that, even though the
terms of the prime contract were incorporated by reference
into the subcontract, CopeLanp, and not the government,
was substantially responsible for the delays which caused
F & D to abandon its work under the subcontract. This
Court further concludes that the delays occasioned by
CopeLanD were such as to go to the very heart of the sub-
contract and, therefore, were such as to amount to a ma-
terial breach of that subcontract. It is the holding of this
Court, therefore, that CopgLanp materially breached its
subcontract with F & D and that F & D was thereby justified
7a
in abandoning the project on August 8, 1974. Accordingly,
this Court now enters judgment in favor of F & D on both
its crossclaims against CopeLanp and RIAN and on
CopeLann’s crossclaim against F & D.
Turning now to the question of damages, this Court
makes the following awards to F & D on its crossclaim
against CorkLAN D and RELIANCE:
1) The sum of $90.00 a day for the 144 days from the
original date for the completion of the subcontract until
June 8, 1974, or damages in the amount of $12,960.00;
2) The sum of $90.00 a day for the forty-four (44) days
from June 8, 1974, until August 8, 1974, or damages in the
amount of $3,960.00;
3) Retainages in the amount of $47,418.67.
The total award to F & D, therefore, is $64,338.67. F & D
coneedes that this award should be diminished by $13,000.00,
the sum paid by Re.iance to Graysak in settlement of Gray-
BAR’s claim. This court, therefore, computes the total dam-
ages awardable in favor of F & D and against CoPELanp
and Rewiance as $51,338.67.
This Court notes that F & D makes no claim for the un-
paid portion of the base price of the subcontract, or $33,-
512.72. F & D admits that this sum is properly applied
toward CopeLaNp’s expenses in completing the electrical
work on the project. This Court also notes that F & D, in
its post-trial brief, concedes that, under the Miller Act, it
cannot recover its surety bond premium in the amount of
$10,500.00 against Retiance. As to Corax, this Court
holds that, under the provisions of the subcontract, the
surety bond premium was the sole obligation of F & D and,
therefore, F & D cannot recover the cost of that premium
against CopELanp.
Finally, this Court concludes that Corax shall recover
nothing under its crossclaim against F & D. This Court
8a
holds that CopeLanp breached the terms of the subcontract
with F & D and, therefore, is not entitled to set-off the
costs of completing the electrical work on the project
against F & D’s recovery here.
This Court will enter final judgments on the crossclaims
of the respective parties in accordance with the findings of
fact and conclusions of law stated herein.
Done anp Orperep at Miami, Florida, this 19th day of
February, 1976.
/s/ Illegible
UNITED States District Jupon
9a
(Carrion OmitTEepD ix PeintIne)
(Fitep FEBRUAR 23, 1976)
Final Judgment
In accordance with the Findings of Fact and Conclusions
of Law which this Court has entered in this case, this Court
hereby enters a Final Judgment in favor of F & D ELRO-
TRICAL ConTRacToRs on its crossclaim against J. H. Copr-
LAND & Sons Construction, Inc. and Reviance INSURANCE
Company, in the amount of Firry-One THovsanp THREE
Hunprep AND Turrty-E1cnt DoLLARS AND Srxty- Seven
Cents (51,338.67). Further it is—
ORDERED AND Ap upon that J. H. Copetanp & Sons Con-
struction, Inc. shall recover nothing on its crossclaim
against F& D Execrricat Contractors, Inc. Further, it is—
OrpERED that costs in this action shall be taxed at a later
date upon filing of appropriate Bill of Costs.
Done AND Orperep at Miami, Florida this 23rd day of
February, 1976.
/s/ Illegible
UNITED States District Jupon
10a
APPENDIX B
UNITED STATES COURT OF APPEALS, FIFTH CIRCUIT
March 3, 1978
Unrrep Srares of America, for the Use and Benefit of
Gray-Bar Exectric Company, IN., a New York Cor-
poration, Plaintiff,
v.
J. H. CorRLAND & Sons Construction, Inc., a corporation,
et al., Defendants-Cross Defendants-Appellants,
V.
F & D ELxOTRICAL. Contractors, Inc., Defendant-Cross
Plaintiff Appellee.
No. 76-2053.
Appeals from the United States District Court for the
Southern District of Florida.
Before Coteman, HL and Rvusin, Circuit Judges.
Auvin B. Rustin, Circuit Judge.
This appeal challenges the trial court’s conclusion that
J. H. Copeland & Sons Construction, Inc. (‘‘Copeland’’),
a Small Business Act, 15 U.S.C. § 637(a), ‘‘minority’’ con-
tractor, was substantially responsible for delays in the con-
struction of a United States Aviation facility adjacent to
the Miami International Airport and thereby breached its
contract with F & D Electrical Contractors, Inc. (F &
D’’), the electrical subcontractor on the project.’ Finding
that there was substantial evidence to support the factual
conclusions of the trial court, and that the opinion was con-
sonant with the applicable rules of law, we affirm.
The case was tried on the basis of cross-claims between F & D,
Copeland, and Reliance Insurance Company, Copeland’s surety
under the Miller Act, 40 U.S.C. §§ 270a-270d.
lla
I.
Appellant contends that the trial court was clearly er-
roneous in concluding that Copeland materially breached
its contract by reason of the delay. It is contended that the
delay, even if material, does not go to the heart of the con-
tract so as to constitute a breach. See, U.S. for Use and
Benefit of Pickard v. Southern Const. Co., 6 Cir. 1961, 293
F. 2d 493, rev’d in part and remanded on other grounds,
1962, 371 U.S. 57, 83 S.Ct. 108, 9 L.Ed.2d 31.
In an action between private parties, even though the
contract is governed by the Miller Act, it suffices to show
that the contractor caused a substantial delay in perform-
ance, that the contract terms forbade such a delay, and that
the plaintiff was injured as 1 result. See, Steenberg Con-
struction Co. v. Prepakt Concrete Co., 10 Cir. 1967, 381
F. 2d 768; Bruno Law and Richard Marlink v. United States,
Ot. Cl. 1971, 195 Ct. Cl. 370.
The trial court found that the subcontract between Cope-
land and F & D incorporated by reference the terms of the
general contract between Copeland and the government.“
Both the subcontract and the general contract provided
that the work to be completed on or before January 15,
1974. F & D ceased work on August 8, 1974, 188 days after
construction was originally due to be completed, but when
it was still not finished. The trial court concluded that, if
the delay had been occasioned in substantial part by gov-
ernment-ordered changes or other factors reasonably be-
yond Copeland’s control, then F & D had breached the sub-
contract by stopping work. However, the court found that
the delays were caused in substantial part by Copeland, and
that these delays constituted a material breach of the sub-
Only the ‘‘disputes’’ clause, which is not relevant here, was
not incorporated. See, H. W. Caldwell & Son, Inc. v. U. 8. for the
use of John H. Moon & Sons, Inc., 5 Cir. 1969, 407 F.2d 21.
12a
contract, thereby justifying F & D in abandoning the project
on August 8, 1974.
Article 12.10 of the subcontract provides The Contractor
shall cooperate with the Subcontractor in scheduling and
performing his Work to avoid conflicts or interference in
the Subcontractor’s Work.’’ Additionally, it is an implied
condition of every government construction contract that
neither party will hinder the performance of the other.
Bruno Law, supra.
The contract between Copeland and the government was
subject to the vicissitudes endemic to government contracts.
F & D’s subcontract with Copeland explicitly provided and
necessarily implied that F & D would bear with any delays
caused by the government. But neither the contract nor the
nature of the work obliged F & D to suffer the additional
cost that resulted from delay due to Copeland’s inexpert-
ness in performing its work and in discharging its own con-
tractual duties to subcontractors.
There is an abundance of evidence to support the con-
clusion reached by the trial court that Copeland’s delay
was sufficiently material and prejudicial to constitute a
breach of its contractual obligations, and that F & D was
injured as a result. Despite the various time extensions
resulting from the government change orders, which appel-
* The appellant challenges the finding that ‘‘F & D was literally
unable to install conduits, pull wires and other work because the
building and areas involved were not structurally ready for the
same.’’ It is apparent that this conclusion was based upon the testi-
money of Mr. Diaz, F & Dis President. Appellant contends that
this testimony referred only to the UPS building, where delay was
attributable to government change orders. However, although Mr.
Diaz testified about change order problems and cited the UPS area
as an example, he concluded that the problem that areas were not
structurally ready for F & D’s work ‘‘was occurring primarily
throughout the whole job.’’ Trial transcript, February 6, 1976, at
179.
13a
lant contends account for the vast proportion of the delay,
there were no extensions in existence when F & D finally
left the job on August 8, 1974. Moreover, as the trial court
found, ‘‘F & D walked the last mile’’ by continuing work
without any assurance of compensation. See, U.S. for Use
of F. E. Robinson Co. of N. C. Inc. v. Alpha Continental,
D. N. C. 1967, 273 F.Supp. 758, aff’d 4 Cir. 1969, 406 F.2d
561, cert. denied, 1969, 395 U.S. 922, 89 S.Ct. 1774, 23 L.Ed.
2d 239.
Appellant also contends that F & D was required to prove
the specific extent of the alleged wrongful delay caused by
Copeland itself, distinguished from delays occasioned by
the government. However, the cases relied upon, Bruno
Law, supra; Boyajian v. U. S., 1970 191 Ct. Cl. 233, 423 F. 2d
1231; Wunderlich Contracting Co. v. U. S., 1965, 173 Ct. Cl
180, 351 F.2d 956; Commerce International Co. v. U. S.,
1964, 167 Ct. Cl. 529, 338 F.2d 81; and, Great Lakes Con-
struction Co. v. U. S., Ct.Cl. 1942, 95 Ct. CI. 479, all involved
claims by contractors against the United States for dam-
ages sustained as a result of delay caused by the govern-
ment. They concerned the proof necessary to establish not
merely the fact of breach of contract but the amount of
damages assessable against the United States as a result.
The exacting rules conditioning the determination of dam-
ages against the sovereign for its delay do not prescribe
what constitutes a breach of contract by a private party
for purposes of excusing further performance.
Hence, we are unable to find the trial court erred in con-
cluding that Copeland breached its subcontract with F & D,
and that this excused F & D’s failure to continue work
after August 8, 1974.
II.
With respect to the amount of damages suffered, in a suit
between private parties for breach of a construction con-
tract by delay, the party who seeks to collect damages has
the burden of proving the extra costs it incurred as a result
14a
of the breach. United States v. Citizens q Southerns Nat.
Bank of Atlanta, Ga., 4 Cir. 1966, 367 F.2d 473, 480; Lichter
v. Mellon-Stuart Co., 3 Cir. 1962, 305 F.2d 216. If there are
factors for which the defendant is responsible and factors
for which it is not, the plaintiff must provide a reasonable
basis for apportioning the damages. United States v. Citi-
zens & Southerns, supra; Lichter v. Mellon-Stuart Co.,
supra; see also, Wunderlich Contracting Co. v. United
States, supra. However, where the defendant is responsible
for all of the several sources of delay, it would serve no
purpose to require the plaintiff to apportion the amount of
damages caused by each.“
Here, there were only two causes of the delay: the gov-
ernment change-orders and Copeland’s lack of diligence.
Copeland is liable under the subcontract for all additional
costs sustained as a result of government change-orders.'
Copeland is liable in breach of contract for all damage suf-
fered as a result of its own lack of diligence. Hence, regard-
less of the amount of damage attributed to each cause,
Copeland is liable for the whole. The damages were prop-
erly assessed to cover both. Accordingly, the judgment of
the district court is Arrirmep.
*In Wunderlich, supra, there was an equitable adjustment clause,
but a cause for which the government was not legally responsible,
the Korean War, was a major source of delay. Hence, apportion-
ment of damages was required.
* Provision three of the general contract, as incorporated by ref-
erence in the subcontract, provides in relevant part:
The Contracting Officer may, at any time . make any change
in the work within the general scope of the contract .. .
@ e e 8 ® 8
If any change under this clause causes an increase or decrease
in the Contractor’s cost of, or the time required for, the per-
formance of any part of the work . an equitable adjustment
shall be made and the contract modified accordingly. . ..
15a
APPENDIX C
(Caption OmitTTep tn PRintING)
Filed March 29, 1978
Appeals from the United States District Court for the
Southern District of Florida
Before Coteman, Hu and Rusin, Circuit Judges.
Judgment
This cause came on to be heard on the transcript of the
record from the United States District Court for the
Southern District of Florida, and was argued by counsel;
On ConsmperaTiIon Wuereor, It is now here ordered and
adjudged by this Court that the judgment of the said Dis-
trict Court in this cause be, and the same is hereby,
affirmed ;
It is further ordered that appellants pay to appellee, the
costs on appeal to be taxed by the Clerk of this Court.
March 3, 1978.
16a
APPENDIX D
15 U.S.C. § 687
Operation and regulation of companies
Cooperation WTrR Banks AND OTHER FINANCIAL
INSTITUTIONS
(a) Wherever practicable the operations of a small
business investment company, including the generation of
business, may be undertaken in cooperation with banks or
other investors or lenders, incorporated or unincorporated,
and any servicing or initial investigation required for loans
or acquisitions of securities by the company under the pro-
visions of this Act may be handled through such banks or
other investors or lenders on a fee basis. Any small busi-
ness investment company may receive fees for services
rendered to such banks and other investors and lenders.
40 U.S.C. §2270a
Bonds of contractors for public buildings or works; waiver of
bonds covering contract performed in foreign country
(a) Before any contract, exceeding $2,000 in amount,
for the construction, alteration, or repair, of any public
building or public work of the United States is awarded to
any person, such person shall furnish to the United States
the following bonds, which shall become binding upon the
award of the contract to such person, who is hereinafter
designated as ‘‘contractor’’:
(1) A performance bond with a surety or sureties
satisfactory to the officer awarding such contract, and
in such amount as he shall deem adequate, for the pro-
tection of the United States.
(2) A payment bond with a surety or sureties satis-
factory to such officer for the protection of all persons
supplying labor and material in the prosecution of the
17a
work provided for in said contract for the use of each
such person. Whenever the total amount payable by
the terms of the contract shall be not more than $1,000,-
000 the said payment bond shall be in a sum of one-ha!f
the total amount payable by the terms of the contract.
Whenever the total amount payable by the terms of the
contract shall be more than $1,000,000 and not more
than $5,000,000, the said payment bond shall be in a
sum of 40 per centum of the total amount payable by
the terms of the contract. Whenever the total amount
payable by the terms of the contract shall be more than
$5,000,000 the said payment bond shall be in the sum
of $2,500,000.
(b) The contracting officer in respect of any contract
is authorized to waive the requirement of a performance
bond and payment bond for so much of the work under such
contract as is to be performed in a foreign country if he
finds that it is impracticable for the contractor to furnish
such bonds.
(e) Nothing in this section shall be construed to limit
the authority of any contracting officer to require a per-
formance bond or other security in addition to those, or in
cases other than the cases specified in subsection (a) of
this section.
(d) Every performance bond required under this sec-
tion shall specifically provide coverage for taxes imposed
by the United States which are collected, deducted, or with-
held from wages paid by the contractor in carrying out the
contract with respect to which such bond is furnished. How-
ever, the United States shall give the surety or sureties on
such bond written notice, with respect to any such unpaid
taxes attributable to any period, within ninety days after
the date when such contractor files a return for such period,
except that no such notice suall be given more than one
hundred and eighty days from the date when a return for
the period was required to be filed under the Internal Reve-
18a
nue Code of 1954. No suit on such bond for such taxes shall
be commenced by the United States unless notice is given
as provided in the preceding sentence, and no such suit shall
be commenced after the expiration of one year after the day
on which such notice is given.
40 U.S.C. § 270b
Same: rights of persons furnishing labor or material
(a) Every person who has furnished labor or material
in the prosecution of the work provided for in such con-
tract, in respect of which a payment bond is furnished un-
der section 270a of this title and who has not been paid in
full therefor before the expiration of a period of ninety
days after the day on which the last of the labor was done
or performed by him or material was furnished or supplied
by him for which such claim is made, shall have the right
to sue on such payment bond for the amount, or the balance
thereof, unpaid at the time of institution of such suit and
to prosecute said action to final execution and judgment for
the sum or sums justly due him: Provided, however, That
any person having direct contractual relationship with a
subcontractor but no contractual relationship express or
implied with the contractor furnishing said payment bond
shall have a right of action upon the said payment bond
upon giving written notice to said contractor within ninety
days from the date on which such person did or performed
the last of the labor or furnished or supplied the last of the
material for which such claim is made, stating with sub-
stantial accuracy the amount claimed and the name of the
party to whom the material was furnished or supplied or
for whom the labor was done or performed. Such notice
shall be served by mailing the same by registered mail,
postage prepaid, in an envelope addressed to the contractor
at any place he maintains an office or conducts his business,
or his residence, or in any manner in which the United
States marshal of the district in which the public improve-
ment is situated is authorized by law to serve summons.
19a
(b) Every suit instituted under this section shall be
brought in the name of the United States for the use of the
person suing, in the United States District Court for any
district in which the contract was to be performed and exe-
cuted and not elsewhere, irrespective of the amount in con-
troversy in such suit, but no such suit shall be commenced
after the expiration of one year after the day on which the
last of the labor was performed or material was supplied
by him. The United States shall not be liable for the pay-
ment of any costs or expenses of any such suit.
APPENDIX E
General Provisions
(Construction Contract)
3. CHaNcEs
(a) The Contracting Officer may, at any time, without
notice to the sureties, by written order designated or indi-
cated to be a change order, make any change in the work
within the general scope of the contract, including but not
limited to changes:
(i) In the specifications (including drawings and de-
signs) ;
(ii) In the method or manner of performance of the
work;
(ili) In the Government-furnished facilities, equip-
ment, materials, services, or site; or
( * Directing acceleration in the performance of the
wo
(b) Any other written order or an oral order (which
terms as used in this paragraph (b) shall include direction,
instruction, interpretation, or determination) from the Con-
tracting Officer, which causes any such change, shall be
treated as a change order under this clause, provided that
the Contractor gives the Contracting Officer written notice
stating the date, circumstances, and source of the order
22258 —-„HT. cole as 6 Gun
er.
(c) Except as herein provided, no order, statement, or
conduct of the Contracting Officer shall be treated as a
change under this clause or entitle the Contractor to an
equitable adjustment hereunder.
(d) If any change under this clause causes an increase
or decrease in the Contractor’s cost of, or the time required
21a
for, the performance of any part of the work, under this
contract, whether or not changed by any order, an equit-
able adjustment shall be made and the contract modified in
writing accordingly: Provided, however, That except for
claims based on defective specifications, no claim for any
change under (b) above shall be allowed for any costs in-
curred more than 20 days before the Contractor gives writ-
ten notice as therein required: And provided further, That
in the case of defective specifications for which the Govern-
ment is responsible, the equitable adjustment shall include
any increased cost reasonably incurred by the Contractor
in attempting to comply with such defective specifications.
(e) If the Contractor intends to assert a claim for an
equitable adjustment under this clause, he must, within 30
days after receipt of a written change order under (a)
above or the furnishing of a written notice under (b) above,
submit to the Contracting Officer a written statement set-
ting forth the general nature and monetary extent of such
claim, unless this period is extended by the Government.
The statement of claim hereunder may be included in the
notice under (b) above.
(f) No claim by the Contractor for an equitable adjust-
ment hereunder shall be allowed if asserted after final pay-
ment under this contract.
6. Disputes
(a) Except as otherwise provided in this contract, any
dispute concerning a question of fact arising under this
contract which is not disposed of by agreement shall be
decided by the Contracting Officer, who shall reduce his
decision to writing and mail or otherwise furnish a copy
thereof to the Contractor. The decision of the Contracting
Officer shall be final and conclusive unless, within 30 days
from the date of receipt of such copy, the Contractor mails
or otherwise furnishes to the Contracting Officer a written
22a
appeal addressed to the head of the agency involved. The
decision of the head of the agency or his duly authorized
representative for the determination of such appeals shall
be final and conclusive. This provision shall not be pleaded
in any suit involving a question of fact arising under this
contract as limiting judicial review of any such decision to
cases where fraud by such official or his representative or
board is alleged: Provided, however, That any such decision
shall be final and conclusive unless the same is fraudulent
or capricious or arbitrary or so grossly erroneous as neces-
sarily to imply bad faith or is not supported by substantial
evidence. In connection with any appeal proceeding under
this clause, the Contractor shall be afforded an opportunity
to be heard and to offer evidence in support of his appeal.
Pending final decision of a dispute hereunder, the Contrac-
tor shall proceed diligently with the performance of the
contract and in accordance with the Contracting Officer’s
decision.
(b) This Dispute clause does not preclude considera-
tion of questions of law in connection with decisions pro-
vided for in paragraph (a) above. Nothing in this contract,
however, shall be construed as making final the decision of
any administrative official, representative, or board on a
question of law.
23a
APPENDIX F
Article 11
Subeontractor a Reaponsibijities
11.1 The Subcontractor shall be bound to the Contractor
by the terms of this Agreement and of the Contract Docu-
ments between the Owner and Contractor, and shall assume
toward the Contractor all the obligations and responsibili-
ties which the Contractor, by those Documents, assumes to-
ward the Owner, and shall have the benefit of all rights,
remedies and redress against the Contracter whieh the Con-
tractor, by those Documents, has against the Owner, insofar
as applicable to this Subcontract, provided that where any
provision of the Contract Documents between the Owner
and Contractor is inconsistent with any provision of this
Agreement, this Agreement shall govern.
This is a copy of a public record, reproduced as it was published. It is not legal advice, and it may not be the version a court would rely on. Check the official source before you cite it.