Petition — United States ex rel. Johnston v. General Insurance Co. of America
Supreme Court brief1977
Ask Donna
What actually matters in this document.
Text
Sup me Count y. — |
™- FILER .
| ANG 24 1977 |
| |
aK, JR., CLERK
IN THE
Supreme Court of the United States
OCTOBER TERM, 1977 {
)
mm F9-307
THE UNITED STATES OF AMERICA for the use of
JOHNSTON, L. R. d/b/a L. R. JOHNSTON COMPANY.
Petitioner.
versus
GENERAL INSURANCE COMPANY OF AMERICA,
a corporation,
Respondent,
versus
BECKMAN CONSTRUCTION COMPANY, a corporation,
Respondent.
PETITION FOR A WRIT OF CERTIORARI TO THE
| UNITED STATES COURT OF APPEALS
; FOR THE FIFTH CIRCUIT
MAURICE A. DOWNING
Counsel for Petitioner
Of Counsel
MOORE AND DOWNING
920 DAUPHIN STREET
P. O. BOX 1261
MOBILE, ALABAMA 36601
SCOFIELDS’ QUALITY PRINTERS. P O BOX 53096.N 0. LA 70153 504 822 1611
o>
FCR ; Aberthnar hea tdatieeee taketh en sii u
BRIEF
the=prisc-cowerecter® (3) Whether the sutcontractor would be entitled to
damages for the injury to machinery caused by the negligence of the prime contrac
| recovery
=. CMe? aE eS. ee ee
SSG To Sie OR SS Es Og ee RR tor when ‘kmcmom is provided for in the subcontract? (4) Whether the subcontractor
, a eT :
Supreme Court Review would be entitled to attorneys' fees when the daily worksheets submitted by the
subcontractor and sidgfd by the prime state that the prime agrees to pay attorneys?
fees in the even! of default in payment of the amounts shown and where State lew
cae | | provides for attorneys' fees in similar contracts with the State? Se ee
Petition Filed Relwkemlte (U.S. f£/u/o Johnston, L.R., v. General Insurance °o. of “nerica,
Sup. Ct. No. 77-307, 8/24/77)
\ Subcontract Milder _Actr—Rul.ing Below ( CA 5; 3/23/77):_/
Sctanutaiianiaatittnsial epee furnishing the labor and
A
materials for construction of a well under a Government prime contract who,
after the first well had stopped producing water, was directed by the prime
contractor to #x drill a second one isn't entitled to payment under the Miller
Act for work performed on the second well since the Government refused to. pay for
the work and the ‘subcontract aia not obligate the prime to pay for any work until , | REST COPY AVAILABLE
the prime had been paid themedie&e by the Government. Further, the sub's request
were
for damage s to its aquiguan, claimed to have been caused by the negligence of the
prime is one for extraordinary damages by reason of tortious conduct, rather than
a claim for materials or labor » and therefore demx is not appropriate in a Miller
Act suit.
Questions presented: (1) Is the subcontractor entitled to be paid under the
Miller Act by the prime contract) for verk anf lebor done unter oréers/of the prin
where the Corps of Engineers had not issued a change order of the contract for
additional sums to pay for such work and labor? (2) Under the Miller Act, is a sub
entitled to be paid for drilling esastional well not called for in the prime
contract when the subcontract calls for $40 per how for work and labor and machinery
end
furnished, when the failure of the first well was due to the negligence of the prime 2
Sater
An tutitig to supply—eiectpiece:—peies—tothe—tinest—well—tfer—more—than one yesr fag~-
tne —tme —the—ori pine weT I
OSES ERAN — eager
Page
Citations .......... Siedse Wid dewhecwresndeasantees ii
i .-..6knd beens Od eeeenne og genseceyes 2
REET Bcc ee aE 8 Ge 2
eS vcd ct vd dunddheud men dhe da giee T0605 3
ere ene ee ene 3
DE SiN cabacade ee nneeneoute Osc esaeeeseécesse 4
ee EE CEE ccc ecanscevesecucesesecene 8
cite chiens cape edbeasoeeotesvesetes is eds 12
ing Kad dv ddeh vnEs eww bes comedies ceces 13
Appendix
A — Memorandum Opinion and Judgment
ED cnn bdo ads cdamdueewesdediced la
B — Appeal to United States Court of
Appeals for the Fifth Circuit ............. lla
C — Court of Appeals Rehearing .............. 12a
D — Supreme Court Extension of time ........ 12a
E — Kenneth MclIntyre’s letter ................ 13a
Fe ee ED TP da Was cdwEd baw cases veces 15a
G — 40 U.S.C. 270(a), (b), (c), (d) ............... 18a
ii
CITATIONS
CASES:
Arnold vs. United States for the use of Bow-
man, 470 F. 2d. 343, (1972) 2... cccccccccces
Title 50, Section 16, Code of Alabama, 1940, as
Recompiled 1958 (Appendix F) ............
United States of America for the use and
benefit of Weyerhaeuser Company vs.
Bucom Construction Company and
Traveler’s Indemnity Company, 430 F. 2d.
GRD, (2GTE) oc cccccccccccesesenesucesesucweel
United States Fidelity and Guaranty Com-
pany vs. Hendry Corporation, 391 F. 2d. 13
United States vs. F. D. Rich Company, 434
DP. 28. GSB, (2BVE) c ccccccccssobevscssuseuenen
STATUTES:
40 U.S.C. § 270 (a), 270 (b), 270 (c) and 270 (d)
ON gd ee eee
SB UO.BG. OSBRS oc ccvscccsvscanesseneeesneae
ADMINISTRATIVE HEARING
Corps of Engineers, Beckman Construction
Company, Ruling on appeal 30 July 1976,
ON SS Sa.
Page
IN THE
SUPREME COURT OF THE UNITED STATES
OCTOBER TERM, 1977
No.
THE UNITED STATES OF AMERICA for the use of
JOHNSTON, L. R. d/b/a L. R. JOHNSTON
COMPANY,
Petitioner,
versus
GENERAL INSURANCE COMPANY OF AMERICA,
a corporation,
Respondent,
versus
BECKMAN CONSTRUCTION COMPANY,
a corporation,
Respondent.
PETITION FOR A WRIT OF CERTIORARI TO THE
UNITED STATES COURT OF APPEALS
FOR THE FIFTH CIRCUIT
Petitioner, THE UNITED STATES OF AMERICA
for the use of JOHNSTON, L. R. d/b/a L. R.
JOHNSTON COMPANY, prays that a Writ of Cer-
2
tiorari issue to review a judgment of the United States
Court of Appeals for the Fifth Circuit, affirming a
judgment rendered by the United States District Court
for the Middle District of Alabama against your
Petitioner. ™~
OPINIONS BELOW
District Court entered a judgment on the 17th day of
June, 1976 (R. 49) in favor of the Defendant, General! In-
surance Company of America, a corporation, and
Third-Party Defendant, Beckman Construction Com-
pany, a corporation, wherein the Court ruled in its
opinion that “Plaintiff take nothing by his complaint
herein, and that the above-styled cause be, and the
same is hereby, dismissed with costs taxed against the
Plaintiff’. (Appendix A) In a summary judgment, un-
der Local Rule 21, without opinion, the United States
Court of Appeals for the Fifth Circuit (case no. 76-3033)
affirmed the District Court on March 23, 1977. (Appen-
dix B) On April 27, 1977, an Order was entered by the
United States Court of Appeals for the Fifth Circuit
(case no. 76-3033) denying the petition for rehearing.
This is not reported. (Appendix C).
The Supreme Court by Order dated the 19th day of
July, 1977, extended the time to file Petition for Writ of
Certiorari to and including August 25, 1977. (Appen-
dix D)
JURISDICTION
The jurisdiction of this Court is invoked under 28
U.S.C., § 1254. The basis for federal jurisdiction in the
Court of first instance, United States District Court for
3
the Middle District of Alabama, is that this is a case
under the “Miller Act”, Title 40, U.S.C., Section 270 (a),
(b), (c), and (d).
STATUTES INVOLVED
The statute involved is 40 U.S.C., § 270 (a), 270 (b), 270
(c) and 270 (d). This statute is printed in Appendix G
hereto (pp. 18a-22a).
QUESTIONS PRESENTED
1. Is the sub-contractor entitled to be paid under 40
U.S.C., § 270 (a), (b), (c) and (d) by the prime contractor,
for work and labor done under orders of the prime con-
tractor where the Corps of Engineers had not issued a
change order or modification of the contract for ad-
ditional sums to pay for such work and labor?
2. Under the “Miller Act”, 40 U.S.C. § 270 (a), (b), (c),
and (d), is a sub-contractor entitled to be paid for the
drilling of additional water well not called for in the
general contract when the contract between the prime
contractor and the sub-contractor calls for $40.00 per
hour for work and labor and machinery furnished,
when the failure of the first well was due to the negli-
gence of the prime contractor in failing to supply elec-
trical power to the first well for more than one year
from time original well was drilled and accepted by
Corps of Engineers and prime contractor?
3. Whether under asub-contract the sub-contractor
would be entitled to damages for the injury to
machinery caused by the negligence of the prime con-
tractor when same is provided for in the sub-contract?
4
4. Whether the sub-contractor would be entitled to
attorney fees when on the daily tickets or worksheets
submitted by sub-contractor and signed by the super-
intendent of the prime contractor it is stated that the
prime contractor agrees to pay attorney fees in the
event of default in the payment of the amounts shown
on the work sheets and where State law provides for
attorney fees in like contracts with the State?
5. Does the sub-contractor have to wait until the
Corps of Engineers agrees to a change order or
modification of the original contract before being paid
for work and labor performed and machinery fur-
nished where the prime contractor authorized the sub-
contractor to do the work?
STATEMENT
The basis of federal jurisdiction in the court of first
instance, the United States District Court for the Mid-
dle District of Alabama is 40 U.S.C., § 270 (a), 270 (b).
270 (c) and 270 (d) dealing with a federal contract for
the building of recreation facilities at Jones Bluff,
Autauga County, Alabama. On the 25th day of July,
1975, the Plaintiff, United States for the use of L. R.
Johnston, doing business as L. R. Johnston Company,
filed a suit against the Defendant, General Insurance
Company cf America, as surety on the bond of
Beckman Construction Company, general contractor,
for work and labor performed under a sub-contract, for
damages caused by the prime contractor by negligent-
ly causing injury to machinery of the Plaintiff,
Johnston Company, and for attorney fees. Ail of said
damages being sustained under a sub-contract with
the Corps of Engineers for the erection or building ofa
5
recreation center at Jones Bluff, Autauga County,
Alabama. The Plaintiff, hereinafter called Johnston,
claims that he entered into an agreement with the
prime contractor, Beckman Construction Company,
Third-Party Defendant, hereinafter called Beckman, a
copy of which sub-contract is attached to the original
complaint and is also Plaintiff's Exhibit 6 (R. 370); that
under said contract Johnston agreed to furnish all the
labor, tools, machinery, taxes and insurance to drilla
water well and to drill and place grout piling and
Beckman was to furnish the materials and super-
vision. Under Section 4 (R. 371) of the contract,
Beckman agreed to pay Johnston $40.00 per hour for
actual working time and the same rate for travel time,
and that payments partial or final were to be made on
the same basis that the owner, U. S. Corps of Engi-
neers, hereinafter called the Corps, pays Beckman;
that under the contract Corps agreed to pay Beckman
each month for work completed or at more frequent in-
tervals as determined by the contracting officer (see
Section 7 (b), last page of Plaintiff's Exhibit 7 (R. 386);
that under said contract Johnston did furnish the
labor, tools and machinery and insurance as agreed,
did drill two wells and place grout piling and that
Beckman failed to pay the Plaintiff $17,003.00 due him
under said sub-contract. The Plaintiff also claims at-
torney fees in the amount of $3,400.00. Work tickets or
order tickets were issued by Johnston and signed by
Beckman Company each day. (Plaintiff's Exhibits 1
and 4) (R. 310 and 348) The Plaintiff filed his claim
against General Insurance Company of America, a
corporation, as surety on Beckman’s payment bond
and the surety, with leave of the Court, brought in
Beckman as Third Party Defendant.
On pre-trial hearing, the Defendant (surety) admit-
ted that its principal (Beckman) entered into the con-
tract sued on, admitted that it was subject to the
provisions of Title 40, U.S.C., § 270 (a), et seq. and ad-
mitted that General Insurance Company was surety
for Beckman Construction Company under the federal
construction project referred to in the contract.
The defenses were:
1. The general issue.
2. That the contract provided that payment would
not be made to Johnston until the progress on work
done and services furnished was satisfactory to
Beckman and that said work was not satisfactory.
3. That Johnston failed to perform work and com-
plete all work covered by the sub-contract to the satis-
faction of Beckman as provided in the contract and -
failed to secure and protect his work as required.
4. That Johnston was to be paid on the same basis
as Beckman was paid by the Corps and that Johnston
has been paid on this basis and that Beckman has no
further obligation to make payment to Johnston.
5. That Johnston agreed tocomply with the general
contract between Beckman and the Corps of Engi-
neers and failed to do so.
6. That the amount claimed by Johnston was the
amount incurred in drilling a well which the Defen-
dant and Corps of Engineers claimed were defective
and that Plaintiff drilled another well which was ap-
proved and paid for after the first well had been
declared defective.
7
7. Beckman claims that Johnston agreed to per-
form his work in a workmanlike manner which would
be satisfactory to the contracting officer of the Corps
of Engineers, but that the first well was not accepted
by the Corps of Engineers, who refused to pay
Beckman for Johnston’s work done and hence
Johnston is not entitled to recover.
8. Defendant says that attorney fees are not
recoverable in this action.
9. That Defendant (surety) is entitled to judgment
over against Beckman for any amount for which it
may have to pay under its bond.
The case came on to be heard at a formal hearing
before the Honorable Robert L. Varner, United States
District Judge for the Middle District of Alabama,
Northern Division, and all parties were represented
by counsel and were given full opportunity to be
heard, and a Memorandum Opinion and Judgment was
rendered by the Court on the 17th day of June, 1976, by
which Judgment the Court dismissed the complaint of
the Plaintiff with costs taxed against Plaintiff.
The Plaintiff filed timely notice of appeal to the Unit-
ed States Court of Appeals, Fifth Circuit, pursuant to
the rules of appellate procedure.
The United States Court of Appeals for the Fifth Cir-
cuit, in case no. 76-3033, Summary Calendar, without
opinion, affirmed the lower court on March 23, 1977.
Said judgment was not published.
On the 27th day of April, 1977, a petition for rehear-
ing was denied by the United States Court of Appeals
for the Fifth Circuit.
8
REASONS FOR ISSUING WRIT
During the entire course of the trial in the Court of
first instance, the United States District Court for the
Middle District of Alabama, the defense of Beckman
Construction Company, Defendant, and General In-
surance Company of America, Defendant, was, that
since the Defendant, Beckman Construction Com-
pany, was not paid by the Corps of Engineers for the
second well drilled by the Petitioner, Johnston Com-
pany, that the prime contractor, Beckman Construc-
tion Company, did not have to pay Johnston for the
work done on the second well. In fact, the Court stated
(R. 125) as follows:
“THE COURT: I think your defense has not
been an itemized defense. Your defense up to
this point has been that you simply weren't
paid by the engineers, therefore you don’t owe
him.
MR. MILLING: Yes, sir.”
Section 4 of the sub-contract (R. 371) between
Appellant, Johnston and Beckman Company sets out
that Johnston, the sub-contractor, was to be paid $40.00
per hour for men, machinery, work and insurance, and
under Section 2 of the sub-contract (R. 370), Johnston
was to drill a water well and to drill holes for piling, all
of which he did in a workmanlike manner.
Also, in Section 4, the following will be found:
“Payments, partial and final, will be made on
the same basis that the owner pays Beckman
Construction Company. The sub-contractor
will submit an estimate of its completed work
each month before the 20th of the month. If not
received, Beckman Construction Company
will make an estimate for this sub-
contractor.” (R. 371)
The entire contention of Beckman Construction
Company is that the Corps of Engineers did not pay for
the second well, therefore, under said paragraph of the
sub-contract, Beckman was not obligated to pay the
sub-contractor for doing the work.
At paragraph 7 of the prime contract with the Corps
of Engineers, (R. 390) the following will be found:
“7. (b) The government will pay progress
payments monthly as the work proceeds or at
more frequent intervals as determined by the
contracting officer on estimates approved by
the contracting officer.” .
Therefore, considering both paragraphs, that in the
prime contract and that in the sub-contract, it is ob-
vious that what was meant in the sub-contract is that
the prime contractor would pay the sub-contractor as
the government or owner paid him which was on a
monthly basis on estimates of work submitted. It does
not mean that if there is extra work done by the sub-
contractor and the Corps of Engineers fails to issue
change orders for the extra work done by the sub-
contractor, then the prime contractor is not obligated
to pay the sub-contractor. | do not believe that the par-
ties understood this to be the case when they entered
10
into the contract. In addition, since the trial] in the Dis-
trict Court of the Middle District of Alabama, the
Corps of Engineers on appeal by Beckman ruled as
follows:
“I find that you let the well sit idle for over one
year. Therefore, I find that you did not develop
the well properly.” (Appendix E)
_So, it is plain that the engineers have ruled both at
the Mobile level and at the Appellate level that the
prime contractor, Beckman, was at fault in allowing a
well to sit idle without electrical power and no way to
activate a pump to keep said well clean for over a year,
thereby allowing the well to clog and corrode and be
inoperable.
The District Court held in its order or memorandum
opinion that there was no order slips or daily work
slips signed for the $3,600.00 for work and labor done
and the use of machinery in trying to revive the first
well (R. 42). Daily work slip #6770, dated 1/10/75,
shows. the costs and hours worked on washing and
blowing the well and at the bottom states, “Cost work-
ing on well #1 $3,600.00” (R. 360). This ticket was
signed by John Morgan, who was superintendent for
Beckman.
As for the charge of $1,100.00 for damages negligent-
ly done by Beckman to Johnston’s machinery, I refer
the court to Section 21, of the sub-contract wherein it
states that, “the sub-contractor shall effectually
secure and protect his material and work and shall
bear and be liable for all loss and/or damages of any
kind in connection therewith at any time prior to the
11
final completion and acceptance thereof, unless said
loss or damage is caused by direct negligence of the
company’. (R. 408)
As to attorney fees in ‘“‘Miller Act” cases, there are
many cases throughout the United States which hold
that said fees are collectable. In the case of Arnold vs.
United States for the use of Bowman, 470 F.2d. 243,
(1972) the Court stated:
“There is substantial authority for a trial
court to award attorney fees in Miller Act
cases if such fees are allowable by state law.”
Title 50, Section 16, Code of Alabama, 1940, Recom-
piled 1958, provides for payment bonds on state public
work projects which carries with it a provision for at-
torney fees (Appendix F).
In the case of United States of America for the use
and benefit of Weyerhaeuser Company vs. Bucom
Construction Company and Traveler’s Indemnity
Company, 430 F. 2d. 420, (1970) the Fifth Circuit _—
of Appeals ruled as follows:
“In accordance with our holding in a United
States Fidelity and Guaranty Company vs.
Hendry Corporation, 5th Circuit, 391 F. 2d. 13,
we grant the Appellee’s unopposed motion for
attorney fees on this appeal pursuant to Flori-
da statute 627.0127, as amended in 1967, E.S.A.
The clerk is directed to fix saff fee in the
amount of $2,112.08 in taxing costs upon this
appeal.”
12
In the case of United States vs. F. D. Rich Company,
434 F. 2d. 855, (1970) the Court stated:
“It was held that allowance of attorney fees
against prime contractor and its surety in ac-
tion under Miller Act by sub-contractor with
respect to construction project in Alaska was
not improper.”
Therefore, we submit to the Court that attorney fees
in this case is proper and should be awarded to
petitioner.
Every allegation of the complaint as originally
filed, which was admitted to be in good form and prop-
erly before the trial court, was proved by the Plaintiff
through written exhibits and testimony and the only
defense was that Beckman would pay Johnston when
the Corps paid Beckman, which the Corps refused to
do because Beckman was negligent in allowing the
well to sit idle for more than one year (Appendix E).
CONCLUSION
For the foregoing reasons, it is respectfully sub-
mitted that this Petition for a Writ of Certiorari should
be granted and that the judgments of the United States
District Court of the Middle District of Alabama and
the United States Court of Appeals for the Fifth Circuit
of Alabama should be reversed.
Respectfully submitted,
Maurice A. Downing
Counsel for Petitioner
13
Of Counsel:
MOORE AND DOWNING
920 Dauphin Street
P. O. Box 1261
Mobile. Alabama 36601
PROOF OF SERVICE
I, Maurice A. Downing, the attorney for the
Petitioner herein and a member of the Bar of the
Supreme Court of the United States, hereby certify
that on the ____ day of August, 1977, I served a copy of
the foregoing Petition for Writ of Certiorari to the
United States Fifth Circuit Court of Appeals on
General Insurance Company of America, a corpora-
tion, and Beckman Construction Company, acorpora-
tion, Respondents herein, by mailing a copy of the
same in a duly addressed envelope, with first class
postage prepaid to Harry Cole and John M. Milling, Jr.
of the firm of Hill, Carter, Franco, Cole and Black, at
Post Office Box 116, Montgomery, Alabama 36101, At-
; torneys for Respondents.
Maurice A. Downing
Counsel for Petitioner
920 Dauphin Street
P. O. Box 1261
Mobile, Alabama 36601
la
APPENDIX A
MEMORANDUM OPINION
Filed: Jun 17, 1976
In the United States District Court for
The Middle District of Alabama
Northern Division
THE UNITED STATES OF AMERICA, Etc.,
Plaintiff,
versus CA NO. 75-356-N
GENERAL INSURANCE COMPANY OF AMERICA,
A Corporation,
Defendant and
Third-Party Plaintiff,
versus
BECKMAN CONSTRUCTION COMPANY,
A Corporation,
Third-Party Defendant.
This cause being submitted for final judgment on the
pleadings, evidence submitted in open Court, and
briefs filed by the parties, the Court now enters the
following findings of fact and conclusions of law.
FINDINGS OF FACT
This is an action by a subcontractor [Johnston]
proceeding against the surety [General Insurance] of
a general contractor [Beckman] on a federal construc-
tion project in this district. Plaintiff seeks recovery of
$20,503.00 from Defendant General Insurance, which
sum, according to the evidence herein, consists of $15.-
903.00 claimed for work done pursuant to Johnston's
contract with Beckman, $1,100.00 damages to
Johnston's equipment allegedly due to Beckman’s
negligence, and $3,500.00 attorneys’ fees.
The Court finds that Johnston knowingly entered
into the contract herein attached to the complaint and
that General Insurance entered into the suretyship
agreement also attached to the said complaint. The
Court notes that, although some of Johnston's
testimony apparently attempts to suggest that he did
not believe himself to be operating under the said con-
tract, the pleadings show clearly that he is now suing
solely upon that agreement as secured by the sur-
etyship agreement. Each party has admitted the
proper execution of the same.
The Court finds that sometime in 1973 Plaintiff com-
menced drilling a water well at the project site as
called for in the aforesaid contract. On September 6,
1973, Plaintiff turned over to Beckman a producing
well from which acceptable drinking water was flow-
ing. Sometime during the following month, the Army
Corps of Engineers paid Beckman for the well, and
Beckman, in turn, paid Plaintiff for the same well. At
some time subsequent to the payment to Plaintiff for
the well, it stopped producing water in significant
quantity. The evidence presented to the Court is in
conflict as to the cause of this cessation of flow. Plain-
tiff contends it was caused by Beckman’s failure to
continue pumping the well after Plaintiff's departure
from the job site, while Defendant claims that the well
was negligently dug. For reasons stated below, the
Court finds it unnecessary to decide the issue of the
cause of the cessation of flow.
3a
The Court finds that, regardless of when Plaintiff
was first informed of the failure of the well, he was not
asked to return to the job site until late November or
December, 1974. After attempting without success to
revive the flow of water from the well, Plaintiff in-
formed Beckman that it would be necessary to partial-
ly destroy a concrete house erected by Beckman over
the well, in order to perform further operations on the
well. Beckman refused this plan and proposed instead
that Plaintiff dig a new well. Plaintiff accepted this
plan and set to work, completing the second well in
1975.
The Court finds that the contract herein calls for
Plaintiff's work to be compensated at the rate of $40.00
per hour and that a practice was followed at the job site
whereby during the digging of both wells Plaintiff's
agent presented a ticket setting out each day’s work
time and charges at the end of the day, the same being
accepted by Beckman through its on-the-job agent,
who was supposed to sign the ticket. Plaintiff produc-
ed a series of such tickets signed by an agent of Beck-
man and dated from December 17, 1974, amounting toa
total charge of $5,760.00. Plaintiff also claims $3,600.00
for work performed in an effort to resuscitate the first
well, as to which he has produced no signed tickets
and, indeed, no tickets at all. The remaining $6,543.00
of Plaintiff's claim consists of-miscellaneous ex-
penses and “rig rent” incurred at various times from
December 16, 1974, until April 4, 1975, all of which the
Court finds to be referrable to the drilling of the second
well. None of the expenditures, except the time
charges during digging of the second well, are sub-
stantiated by work tickets.
4a
The Court finds that, at the time of the decision to
drill the second well, no written authorization was ob-
tained by Plaintiff before proceeding with the work,
although, as aforesaid, Plaintiff did obtain signed
work tickets each day after completion of the day’s
work. The Court also finds that Beckman told Plaintiff
that Beckman would apply for a change order on the
original contract to allow for this second well but that
the Corps of Engineers rejected the application.
CONCLUSIONS OF LAW
In resolving Plaintiffs claims, the Court is mindful
both that “[t]he Miller Act provides a federal cause of
action, and the scope of the remedy as well as the sub-
stance of the rights created is a matter of federal not
state law,” F.D. Rich Co., Inc. v. United States for the
use of Industrial Lumber Co., 417 U.S. 116, 127 (1974),
and that the Act, being “highly remedial’, should be
given a liberal construction so as to give effect to the
intention of Congress to give security to those who
furnish materials or labor on government construc-
tion projects. Clifford F. MacEvoy Co. v. United States,
322 U.S. 102 (1944); Glassell-Taylor Co. v. Magnolia
Petroleum Co., 153 F.2d 527 (5th Cir. 1945); Coffee v.
United States ex rel Gordon, 157 F.2d 968 (5th Cir.
1946). In order for Plaintiff to recover, however, he
must prove that the charges he seeks to enforce come
within the terms of the Act; the charges must be for
“labor or material done or performed by him” or “fur-
nished or supplied by him in the prosecution of the
work provided for in such contract.’”’ 40 U.S.C.
§ 270b(a). It is particularly to be noted that the “such
contract” referred to is manifestly the prime contract
between the United States and the prime contractor
(Beckman).
—
5a
Referring to the terms of Genera] Insurance's sur-
etyship agreement, we find that it provides that:
“* ** if the Principal shall promptly make
payment to all persons supplying labor and
materials in the prosecution of the work
provided for in said contract, and any and all
duly authorized modifications of said contract
that may hereafter be made, notice of which
modifications to the Surety(ies) being hereby
waived, then the above obligation shall be
void and of no effect.”’
Nowhere in the suretyship is any contract referred to
other than the prime contract, which carried the
numerical designation DACW01-73-C-0099. The Corps
of Engineers explicitly declined to alter that contract
to provide for the drilling of a second well. It follows,
therefore, that the terms of the subcontract between
Beckman and Plaintiff could not be controlling unless
the charges Plaintiff seeks to recover were properly
incurred under the subcontract as originally entered
into or as modified.
Eleven Hundred Dollars of the sum claimed by
Plaintiff is for damage to Plaintiff's equipment claim-
ed to have been caused by the negligence or fault of
Beckman. It is clear that this claim is not one for in-
cidental damage or ordinary wear and tear. Instead, it
is a claim for extraordinary damage alleged to have
occurred by reason of tortious conduct by Beckman.
Such aclaim is not one for materials or labor, even un-
der the most expansive reading of these terms and has
no place in a Miller Act suit. United States ex rel Gib-
son v. Harmon, 192 F.2d 999 (4th Cir. 1951); United
6a
States ex rel Spencer v. Massachusetts Bonding & Ins.
Co., 18 F.2d 203 (6th Cir. 1927).!
As to Plaintiff's claim of $3,600.00 for work done in
an attempt to revive the first well, it is this Court's
opinion that the parties’ rights are determinable under
§ 20 of the subcontract which provides as follows:
“The Subcontractor shall promptly amend
or make good any defective materials and/or
workmanship to the entire approval and
acceptance of the Owner and/or Architect or
their authorized representatives. Should the
Subcontractor refuse or neglect to proceed at
once with the correction of rejected or defec-
tive materials and/or workmanship after
receiving notice to do so, it is agreed that the
Company shall have the right and power to
have the defects remedied or changes made at
the expense of the Subcontractor, and the Sub-
contractor agrees to pay to the Company on
demand any and all loss and/or expense paid
or incurred by the Company in remedying
such defects and/or making such changes,
together with interest thereon at the rate of 6%
per annum until paid.”
1 The Court expresses no opinion as to the effect of § 21 of
Beckman’s subcontract with Plaintiff, as follows:
“* * * Subcontractor shall effectually secure and protect
his material, and shall bear and be liable for all loss and/or
damage to any kind [sic] in connection therewith * * * un-
less said loss or damage is caused by direct negligence of
the company.”
Whatever this may mean and to whatever extent this language
would affect Plaintiff's right to recover in tort, it does not affect
this suit. Even if this language did create a breach of contract
claim in Plaintiff, which it manifestly does not, it still would not
support a Miller Act recovery. United States ex re] Edward E.
Morgan Co. v. Maryland Casualty Co., 147 F.2d 423 (5th Cir. 1945).
7a
't is the opinion of the Court that both Beckman and
Plaintiff understood that the repairs charged herein to
the value of $3,600.00 were being undertaken pursuant
to this provision. There is no evidence before the Court
suggesting that there was any agreement, oral or
written, for the payment for repairs to the first well
that would amount to a modification of the contract or
the formation of a new contract, either implied or ex-
press. Particularly significant is the failure of Plain-
tiff to secure work tickets for this remedial work, con-
trasted with his careful accumulation of such tickets
for work on the second well. The Court finds that
Plaintiff has not met his burden of proof of es-
tablishing that these repair activities were expen-
ditures chargeable to Beckman. Since General In-
surance is surety only for Beckman, Plaintiff cannot
recover these charges.
It appears to the Court that the situation with
respect to charges for digging the second well may be
somewhat different. The Court has found that Plaintiff
and Beckman entered into an agreement for the dig-
ging and that this agreement was occasioned by
Beckman’s unwillingness to allow Plaintiff to proceed
with repairs as required of Plaintiff by the subcon-
tract. The Court, however, is not at liberty to award a
judgment to Plaintiff herein againgt the surety on the
basis of any new, oral contract that may have been
formed or on any theory of quantum meruit. The only
way in which Plaintiff can recover in this suit is ona
theory that this work was called for by a binding
modification of the subcontract. The Court finds it un-
necessary to determine whether the agreement, in
fact, created such a modification of the original sub-
contract for the reason that recovery on such a
modified contract is clearly barred by the simple
language of § 4 of the subcontract:
8a
“However, [Beckman] shall be under no
obligation to pay Subcontractor for any work
done hereunder, until [Beckman] has been
paid therefor by [the Corps].”’ (Bracketed ex-
pressions added)
Although Plaintiff testified that this language,
which the Court notes is slightly ambiguous, meant
only that payment would be made on a certain
schedule, the Court finds that this contention must be
rejected in view of language of § 4 and of the Court’s
finding that Beckman informed Plaintiff that he would
seek a change order to allow for the additional work.
The Court is of the opinion that the preponderance of
the evidence supports the conclusion that, under the
contract, Plaintiff's payment was conditional on
Beckman’s being paid. No evidence of any modifica-
tion of § 4 was introduced.
Of course, if the failure of the Corps to pay for the
second well resulted from Beckman’s own intentional
or negligent act or failure to act, ordinary contract
principles may foreclose Defendant’s attempt to de-
fend herein on the basis of the Corps’ failure to pay.?
Evidence was introduced at trial on this question,
relating to the alleged failure of Beckman to transmit
data concerning the first well test bore and water
analysis, as required by § 2 of the subcontract. The
Court, however, finds that Plaintiff has failed to meet
his burden of proof as to his allegation that Beckman
was the cause of the Corps’ adverse decision. Plain-
tiffs Exhibit 7, a copy of the decision of the ap-
propriate officer of the Corps relative to the additional
2 There may be a question whether that matter was adequately
pleaded.
claim, does not support Plaintiff's contention. While
the officer does state that Beckman “failed to promptly
notify the Contracting Officer in writing of an alleged-
ly differing site condition,” there is no evidence that
Beckman was aware of such a condition. Pages 2 and3
of the decision would appear to implicate Plaintiff, not
Beckman, as the party at fault.
The Court concludes that the terms of the written
subcontract, to which Plaintiff has expressly chosen
by counsel to confine this suit, do not authorize
recovery of charges for the second well even if, as the
Court need not decide, a valid modification of the con-
tract ever came into existence.’
Since the Court has concluded that Plaintiff may not
recover on any of his contract claims, it need not con-
sider Plaintiff's claim for attorneys’ fees. Such fees
would be barred by the holding in F. D. Rich Co., supra,
at 127-131.
Judgment will enter accordingly.
DONE this 17th day of June, 1976.
/s/ R. E. VARNER
UNITED STATES
DISTRICT JUDGE
3 See United States for the use of H. O. Kilsby v. George, 243 F.2d
82 (5th Cir. 1957). While in Kilsby there was “no contract hy * as to
[the] ‘extras’,” the fact that such a contract (i.e., a binding oral
modification) may exist herein does not distinguish the present
case, since the agreement, if any, contained a condition, namely
that Beckman be paid, that requires the same holding as in Kilsby,
that is that the subcontractor is barred by his agreement to be
bound by the determination of the Government on the prime con-
tract.
108
JUDGMENT
(Number and Title Omitted)
Filed: Jun 17, 1976
In accordance with the Memorandum Opinion
entered by the Court in the above-styled cause on the
17th day of June, 1976, it is
ORDERED, ADJUDGED and DECREED by the
Court that Plaintiff take nothing by his complaint
herein and that the above-styled cause be, and the
same is hereby, dismissed with costs taxed against the
Plaintiff.
DONE this 17th day of June, 1976.
/s/ R. E. VARNER
UNITED STATES DISTRICT
JUDGE
lla
APPENDIX B
IN THE UNITED STATES COURT OF APPEALS
FOR THE FIFTH CIRCUIT
No. 76-3033
Summary Calendar*
—
THE UNITED STATES OF AMERICA for the use of
JOHNSTON L.R., d/b/aL.R. JOHNSTON COMPANY,
Plaintiff-Appellant,
versus
GENERAL INSURANCE COMPANY OF AMERICA,
a Corporation,
Defendant-Third Party
Plaintiff Appellee,
versus
BECKMAN CONSTRUCTION COMPANY,
a Corporation,
Third Party Defendant.
Appeal from the United States District Court for the
Middle District of Alabama
(March 23, 1977)
BEFORE GOLDBERG, CLARK and FAY, Circuit
Judges.
PER CURIAM: AFFIRMED. See Local Rule 21.!
* Rule 18, 5 Cir.; See Isbell Enterprises, Inc. v. Citizens Casualty
Co. of New York, et al., 5 Cir. 1970, 431 F.2d 409. Part I.
1 See N.L.R.B. v. Amalgamated Clothing Workers of America, 5
Cir., 1970. 430 F.2d 966.
12a
APPENDIX C
ON PETITION FOR REHEARING
(Number and Title Omitted)
Filed: Apr 27, 1977
Before GOLDBERG, CLARK and FAY, Circuit
Judges.
PER CURIAM:
IT IS ORDERED that the petition for rehearing filed
in the above entitled and numbered cause be and the
same is hereby DENIED.
ENTERED FOR THE COURT:
/s/ IRVING L. GOLDBERG
United States Circuit Judge
APPENDIX D
ORDER EXTENDING TIME TOFILE PETITION FOR
WRIT OF CERTIORARI
Supreme Court of the United States
No. A-50
UNITED STATES FOR THE USE OF JOHNSTON,
L.R. d/b/a L.R. JOHNSTON COMPANY,
Petitioner,
versus
GENERAL INSURANCE COMPANY OF AMERICA,
ET AL.
13a
UPON CONSIDERATION of the application of
counsel for petitioner(s),
IT IS ORDERED thatthe time for filing a petition for
writ of certiorari in the above-entitled cause be, and
the same is hereby, extended to and including August
25, 1977.
/s/ LEWIS F. POWELL
Associate Justice of. the
Dated this 19th day Supreme Court of the United
of July, 1977. States
APPENDIX E
Department of the Army
South Atlantic Division, Corps of Engineers
310 Title Building, 30 Pryor Street, N.W.
Atlanta, Goorgia 30303
30 July, 1976
Beckman Construction Company
7201 West Vickery
Fort Worth, Texas 76116
Re: Appeal of Beckman Construction Com-
pany, Contract No. DACW01-73-C-0099,
Jones Bluff Lock and Dam, Alabama,
ENG BCA 3751
Gentlemen:
I have reviewed your appeal for an alleged en-
countering of a Differing Site Condition in the in-
stallation of a water well.
14a
From the present record, I find no proof of a condition
which wouid entitle you to an equitable adjustment in
the contract price. In addition, I find that you let the
well sit idle for over one year. Therefore, I find that you
did not develop the well properly.
Since I have found no basis for reversing the Find-
ings of Fact and decision of the Contracting Officer, it
is suggested that the appeal be submitted to the Board
of Contract Appeals. However, if you have additional
facts or arguments which you care to present to me, I
will be pleased to hear them at a mutually agreeable
date.
If I do not hear from you in 20 days, I will assume you
wish to have the appeal forwarded to the Board.
Sincerely yours,
/s/ KENNETH E. McINTYRE
KENNETH E. McINTYRE
Brigadier General, USA
Division Engineer
Copy furnished:
District Engineer, Mobile
(SAMOC)
I hereby certify that the foregoing is a true and correct
copy of the original letter signed by BG Kenneth E.
McIntyre. The underscoring has been added subse-
quent to signature.
/s/ LAURA R. SEAL
Notary Public, Georgia, State At
Large
15a
APPENDIX F
Tit. 50, § 16
CHAPTER 2.
Bonds of Contractors.
Sec.
16. Bonds required; suits thereon,
etc.
§ 16. Bonds required; suits thereon, etc. — Any per-
son, firm or corporation entering into a contract with
the state or any county or municipal corporation or
subdivision thereof in this state for the repair, con-
struction or prosecution of any public buildings or
public work, highways or bridges, shall be required,
before commencing such work, to execute a perfor-
mance bond, with penalty equal to fifty percent of the
amount of the contract price, and in addition thereto,
another bond with good and sufficient surety, payable
to the state, county or municipal corporation or sub-
division, letting the contract, in an amount not less
than fifty percent of the contract price, with the obliga-
tion that such contractor or contractors shall prompt-
ly make payments to all persons supplying him or
them with labor, materials, feedstuffs or supplies for
or in the prosecution of the work prc vided for in such
contract, and for ‘he payment of reasonable attorneys’
fees, incurred by successful claimants or plaintiffs in
suits on said bond; and any person, firm or corporation
that has furnished labor, materials, feed-stuffs or sup-
plies for or in the prosecution or repair of any public
building or public work, highways or bridges, and
payment for which has not been made, shall be
authorized to institute an action upon said bond in his
or their name or names and to have their rights and
claims adjudicated in such action and judgment
No
16a
rendered thereon; provided, however, that no suit
shall be instituted on said bond until after forty-five
days’ written notice to the surety thereon of the
amount claimed to be due and of the nature of the
claim. Such suit shall be commenced not later than
one year from the date of final settlement of said con-
tract. The giving of said notice by registered mail,
postage prepaid, addressed to the surety at any of its
piaces of business or offices shall be deemed sufficient
hereunder. In the event the surety or contractor fails to
pay such claim in full within forty-five days from the
mailing of such notice, then such person or persons
shall be entitled to recover of the contractor and sure-
ty, in addition to the amount of said claim, a
reasonable attorney’s fee, together with interest on
such claim from the date of such notice. Every person
or persons having a right of action on said last
described bond as herein provided shall, upon written
application to the authority under the direction of
whom such work has been prosecuted, setting out that
labor, material, feed-stuffs or supplies for such work
has been supplied by him or them and that payment
therefor has not been made, be promptly furnished a
certified copy of said additional bond and contract.
Such claimant shall be authorized to bring suit on said
bond in the county in which the work provided for in
said contract is to be performed, or in any county
where the contractor or his surety does business, for
his or their use and benefit against said contractor and
his surety or either of them. In addition to any other
legal mode of service, service of summons and other
process in suits brought in the county where the work
is let or done may be had on the contractor or the sure-
ty on the last described bond, by leaving a copy of the
summons and complaint or other pleading or process,
17a
with the director of the highway department if the con-
tract be a state highway contract or with the executive
officer of the city, town, board, commission or authori-
ty letting the contract, or charged with the payment of
the contract price, if the contract be not a state
highway contract. The bond last described shall have
a provision binding the principal contractor and sure-
ty to the mode of service above described; and consent-
ing that such service shal] be the same as personal
service on the contractor or surety. Immediately on
service being made on the director of the highway
department or executive office of a city, town, board,
commission or authority, it will be the duty of such
director or executive officer to immediately mail a
copy of such process to the contractor and surety, at
the address given in the bond.
This section shall nct require the taking of bond to
secure contracts of less than one thousand dollars in
amount.
The contractor shall immediately after the comple-
tion of the contract give notice of said completion by
an advertisement in some newspaper of general cir-
culation published within the city or county wherein
the work has been done for a period of four successive
weeks. In no instance shall a final settlement be made
upon the contract until the expiration of thirty days
after the completion of same. Proof of publication of
said notice shall be made by the contractor to the
authority by whom the contract was made, by affidavit
of the publisher and a printed copy of the notice
published. If no newspaper is published in the county
where the work is done, the notice may be given by
posting at the court house for thirty days and proof of
same shall be made by the probate judge or sheriff and
the contractor. (1927, p. 37; 1935, p. 70.)
18a
APPENDIX G
Title 40, Section 270(a), United States Code, page 397:
“(a) Before any contract, exceeding $2,000 in
amount, for the construction, alteration, or
repair of any public building or public work of
the United States is awarded to any person,
such person shall furnish to the United States
the following bonds, which shall become bind-
ing upon the award of the contract to such per-
son, who is hereinafter designated as “‘con-
tractor”’:
(1) A performance bond with a surety or
sureties satisfactory to the officer award-
ing such contract, and in such amount as
he shall deem adequate, for the protection
of the United States.
(2) A payment bond with a surety or sur-
eties satisfactory to such officer for the
protection of all persons supplying labor
and material in the prosecution of the
work provided for in said contract for the
use of each such person. Whenever the
total amount payable by the terms of the
contract shall be not more than $1,000,000
the said payment bond shall be in asumof
one-half the total amount payable by the
terms of the contract. Whenever the total
amount payable by the terms of the con-
tract shall be more than $1,000,000 and not
more than $5,000,000, the said payment
bond shall be in a sum of 40 per centum of
the total amount payable by the terms of
the contract. Whenever the total amount
payable by the terms of the contract shall
19a
be more than $5,000,000 the said payment
bond shall be in the sum of $2,500,000.
(b) The contracting officer in respect of any
contract is authorized to waive the require-
ment of a performance bond and payment bond
for so much of the work under such contract as
is to be performed in a foreign country if he
finds that it is impracticable for the contractor
to furnish such bonds.
(c) Nothing in this section shall be construed
to limit the authority of any contracting of-
ficer to require a performance bond or other
security in addition to those, or in cases other
than the cases specified in subsection (a) of
this section.
(d) Every performance bond required under
this section shall specifically provide
coverage for taxes imposed by the United
States which are collected, deducted, or
withheld from wages paid by the contractor in
carrying out the contract with respect to
which such bond is furnished. However, the
United States shall give the surety or sureties
on such bond written notice, with respect to
any such unpaid taxes attributable to any
period, within ninety days after the date when
such contractor files a return for such period,
except that no such notice shall be given more
than one hundred and eighty days from the
date when a return for the period was required
to be filed under the Internal Revenue Code of
1954. No suit on such bond for such taxes shall
be commenced by the United States unless
notice is given as provided in the preceding
20a
sentence, and no such suit shall be commenced
after the expiratign of one year after the day on
which such notice is given.”
Title 40, Section 270(b), United States Code, page 461:
“(a) Every person who has furnished labor
or material in the prosecution of the work pro-
vided for in such contract, in respect of which
a payment bond is furnished under Section 270
a of this title and who has not been paid
in full therefor before the expiration of a
period of ninety days after the day on which
the last of the labor was done or performed by
him or material was furnished or supplied by
him for which such claim is made, shall have
the right to sue on such payment bond for the
amount, or the balance thereof, unpaid at the
time of institution of such suit and to
prosecute said action to final execution and
judgment for the sum or sums justly due him:
Provided, however, That any person having
direct contractual relationship with a subcon-
tractor but no contractual relationship ex-
press or implied with the contractor furnish-
ing said payment bond shall have aright of ac-
tion upon the said payment bond upon giving
written notice to said contractor within ninety
days from the date on which such person did or
performed the last of the labor or furnished or
supplied the last of the material for which
such claim is made, stating with substantial
accuracy the amount claimed and the name of
the party to whom the material was furnished
or supplied or for whom the labor was done or
Zia
performed. Such notice shall be served by
mailing the same by registered mail, postage
prepaid, in an envelope addressed to the con-
tractor at any place he maintains an office or
conducts his business, or his residence, or in
any manner in which the United States
marshal of the district in which the public im-
provement is situated is authorized by law to
serve summons.
(b) Every suit instituted under this section
shall be brought in the name of the United
States for the use of the person suing, in the
United States District Court for any district in
which the contract was to be performed and
executed and not elsewhere, irrespective of
the amount in controversy in such suit, but no
such suit shall be commenced after the expira-
tion of one year after the day on which the last
of the labor was performed or material was
supplied by him. The United States shall not
be liable for the payment of any costs or ex-
penses of any such suit.”
Title 40, Section 270(c), United States Code, page 619.
“The Comptroller General is authorized and
directed to furnish, to any person making
application therefor who submits an affidavit
that he has supplied labor or materials for
such work and payment therefor has not been
made or that he is being sued on any such
bond, acertified copy of such bond and the con-
tract for which it was given, which copy shall
be prima facie evidence of the contents, execu-
tion and delivery of the original. Applicants
22a
shall pay for such certified copies such fees as
the Comptroller General fixed to cover the
cost of preparation thereof.”
Title 40, Section 270(d), United States Code, page 622:
“The term “person” and the masculine
pronouns as used in sections 270a-270c of this
title shall include all persons whether in-
dividuals, associations, copartnerships or
corporations.”
This is a copy of a public record, reproduced as it was published. It is not legal advice, and it may not be the version a court would rely on. Check the official source before you cite it.