Petition — United Brotherhood of Carpenters & Joiners of America v. Noranda Aluminum, Inc.
Supreme Court brief1976
Ask Donna
What actually matters in this document.
Text
INTHE |
Supreme Courtof the Wl
OcToBER TERM, 1975
No. 75-1904
Unitrep BRoTHERHOOD OF CARPENTERS AND JOINERS OF
America, AF'L-C1O, anp UNITED BROTHERHOOD OF
CARPENTERS AND JOINERS OF AMERICA, AF'L-CIO,
Loca. 618, Petitioners,
v.
NorAnDA ALUMINUM, Inc., Respondent.
PETITION FOR A WRIT OF CERTIORARI TO THE
UNITED STATES COURT OF APPEALS FOR
THE EIGHTH CIRCUIT
Wim A. McGowan
101 Constitution Avenue, N.W.
Washington, D.C. 20001
Morris J. LEVIN
S. SHELDON WEINHAUS
1125 Arcade Building
812 Olive Street
St. Louis, Missouri 63101
GEORGE KAUFMANN
2101 L Street, N.W.
Washington, D.C. 20037
Attorneys for Petitioners
Press or Brronw S. Apams Parntine, Inc., Wasuinctron, D. C.
SS,
TABLE OF CONTENTS
Page
CERN THUD a dccocccecctinescescntcscesaveaqce 1
Gusathews PUOROMEGS 2.0. ccccccccsccccccevsescecese 2
rr ee wes otbeheeneeeeees 2
er ne, aids pn cnbaneveteeud 3
A. The Factual Background ................see0. 3
SE oe bes I iad dec chee ieanbaeas nee 3
2. The Features of an Aluminum Smelter ..... 4
3. The Strike, Noranda’s Theory of Damages,
and Defendants’ Principal Objections Thereto 5
a. The unacceptability of January 23, 1971 as
a reliable first metal projection .......... 6
b. Labor inefficiency, particularly among the
electricians, and resulting overtime ....... 8
i Te ONIN GOTT occ cccccecescscecces 10
Be ee PO FD nc dec vc cncceccscecncss 10
By Se I IE wckcdbces deve cucdeeuecus 10
ee GO I 6 kk bk cise cbccsicesens 12
Reasons for Granting the Writ .................... 13
I. The Decision Below Subverts the Congressional
Intent in Allowing Only Compensatory Damages
Under the Labor-Management Relations Act and
Ignores Accepted Tort Principles for Measur-
ing Recovery for Injury to Economic Interests
Caused by Violations of Federal Law ........ 13
II. The Decision Below Creates an Unprecedented
and Unsound Exception to the Specificity Re-
quirement of Rule 52(a), F.R.Civ.P. .......... 23
RN a a 28
ii
AUTHORITIES CITED
CASES:
Albemarle Paper Co. v. Moody, 422 U.S. 405 ...... 14,15
Carpenters Local 1273 v. Hill, 398 F.2d 360 (C.A.9) .. 25
Dowagiae Mfg. Co. v. Minnesota Moline Plow Co., 235
Was GE cccvnncesediahsessceuceanwbetes dukes 19, 20
International Wire v. Local 38, 475 F.2d 1078 (C.A.6),
Oars. GEE. Se Wile GE 9 ov ante e004s0keneessss
Labor Board v. Carpenters Union, 365 U.S. 651 ...... 15
Mine Workers v. Gibbs, 383 U.S. 715 ................ 15
Painters District Council 38 v. Edgewood Contracting
oe gg § 8 eS ero rr re 24
Paramount Transport Systems v. Teamsters Local 150,
— £ es § § er re ene es 24
Phelps Dodge Corp. v. Labor Board, 313 U.S.177 .... 15
Plumbers & Fitters, Local 761 v. Matt J. Zaich Const.
oe Fe 8 gt errr re 25
Republic Steel Corp. v. Labor Board, 311 U.S.7...... 15
Sheet Metal Workers Local 223 v. Atlas Sheet Metal
Cis We a ae ee CREED viccdeccediescdvns 12, 22, 25
Sheldon v. Metro-Goldwyn Pictures Corp., 106 F.2d 45
(C.A.2), affirmed, 309 U.S. 390 ...... 15, 18, 19, 20, 22
Story Parchment Co. v. Paterson Parchment Paper
rere 25, 26
Teamsters Union v. Morton, 377 U.S. 252 ....14, 15, 20, 23
Trico Products Corp. v. N.L.R.B., 489 F.2d 347 (C.A.
DD okscccsdcdabinehsoutneessseednenesns 14, 17, 18, 20
Vulean Materials Co. v. United Steel Workers of
America, 430 F.2d 446 (C.A. 5), cert. denied, 401
Wale WUE ve d0d cabecewseetcenecddecontasecwes 24, 25
Westinghouse Electric & Mfg. Co. v. Wagner Electric
ees eS Pere 19, 20
Table of Authorities Continued iii
STaTuUTEs:
Judicial Code, 28 U.S.C. § 1254(1) ........... cece 2
Labor-Management Relations Act of 1947, as amended,
61 Stat. 136, 73 Stat. 519, 29 U.S.C. § 141 et seq.:
DU Séd0cucdbassWediuvsedundwkdes<écane 14, 24
DT bs culvivevtsivecaesvesudeeeds 2, 3, 11
DT. cls eduuhot ulbse bebe eu esaeeaisis cme 14, 15
DUD uibekenseniewne cos 2, 12, 14, 15, 22, 23, 24, 25, 27
EE ie ten oe eed ee ee oe 2,3
DE sedis tu wkersnedes ceuerbeeeeeneeune 3
Federal Rules of Civil Procedure:
EE 6n0hoGdinenedusededeeseecd 2, 3, 23, 25, 27
MISCELLANEOUS:
A.L.I. Restatement of Torts, Second ............ 17, 18, 21
SP CU, TU, Ge CIPD vc cc cece coccccocccsidces 23
wwonnae, Torte COR OF, WAVE) .onccccvccccccccccecs 17, 21
IN THE
Supreme Court of the United States
OcroBER TERM, 1975
No.
Unitrep BRoTHERHOOD OF CARPENTERS AND JOINERS OF
America, AFL-CIO, anp UNrrep BROTHERHOOD OF
CARPENTERS AND JOINERS OF AMERICA, AFL-CIO,
Loca 618, Petitioners,
V.
NorAnDA ALUMINUM, INC., Respondent.
PETITION FOR A WRIT OF CERTIORARI TO THE
UNITED STATES COURT OF APPEALS FOR
THE EIGHTH CIRCUIT
OPINIONS BELOW
The opinion of the Court of Appeals is reported at
528 F.2d 1034 and is reproduced at pp. la-10a, infra.
The findings of fact and conclusions of law of the Dis-
2
trict Court are reported at 382 F.Supp. 1258 and are
reproduced at pp. 13a-25a, infra.
JURISDICTION
The judgment of the Court of Appeals was entered
on January 5, 1976 (p. lla, infra). A timely petition
fur rehearing was denied on February 17, 1976 (p. 12a,
infra). On May 4, 1976 and June 4, 1976 Mr. Justice
Blackmun entered orders extending the time in which
to file a writ of certiorari until June 15, 1976 and June
30, respectively. The jurisdiction of this Court rests
on 28 U.S.C. § 1254(1).
QUESTIONS PRESENTED
1. In a suit to recover damages sustained ‘‘by
reason of any violation of’? §303(a) of the Labor-
Management Relations Act of 1947, must the Court,
where possible, apportion plaintiff’s damages between
harms caused by the defendant’s violation and harms
due to causes for which the defendant is not respon-
sible ?
2. Does the requirement of Rule 52(a), F.R.Civ.P.
that the court ‘‘find the facts specially’’, apply to the
computation of damages in suits under § 303 of the
Labor-Management Relations Act?
STATUTE AND RULE INVOLVED
This case involves §§ 8(b)(4)(D) and 303 of the
Labor-Management Relations Act of 1947, as amended,
(hereafter LMRA) 61 Stat. 136, 73 Stat. 519, 29 U.S.C.
§ 158(b) (4) (D) and § 187. It also involves Rule 52(a)
of the Federal Rules of Civil Pocedure. These pro-
visions are set forth in Appendix F of this Petition,
pp. 27a-28a, infra.
- asec
3
STATEMENT OF THE CASE
A. The Factual Background
1. Introduction
Respondent Noranda Aluminum, Ine. (‘‘Noranda’’)
is a Delaware corporation formed to establish and op-
erate a 200-acre primary aluminum smelter in New
Madrid County, Missouri. Noranda entered into a
contract with Kaiser Engineers, Inc. (‘‘Kaiser’’) to
design and construct the smelter on a cost-plus-fixed
fee basis. Petitioner Local 618 is the labor organiza-
tion which represented the millwrights’ craft at the
Noranda project; petitioner United Brotherhood of
Carpenters and Joiners of America, AFL-CIO, is the
International Union with which Local 618 is affiliated.
(The petitioners will sometimes be referred to jointly
hereinafter as ‘“Carpenters’’ or ‘‘the unions’’).
This action was brought by Noranda under § 303(b)
of the LMRA for losses allegedly sustained by it due
to a strike by Local 618 to protest Kaiser’s assignment
of certain work to another craft in contravention of
Kaiser’s original assignment. Noranda contended, and
the courts below agreed, that the strike was in violation
of § 8(b) (4) (D) and thus of § 303(a) of the Act, and
that both the Local and the International were re-
sponsible therefor. While those liability issues were
vigorously contested below, we do not press them in
this Court. The questions of general public impor-
tance raised by this Petition relate to the propriety
of an award of $914,823.54 as damages sustained by
Noranda by reason of that violation. They concern
the trial court’s failure, in caleulating the award (a)
to make an apportionment between the losses due to
the Carpenters’ strike and those due to other causes
and (b) to find specially, as required by Rule 52(a),
4
F.R.Civ.P., the facts underlying its resolution of con-
tested elements of the damage award.
While the record is lengthy, and the evidence bear-
ing on damages is unusually complex, we shall curtail
our Statement to the minimum necessary to provide
background for these legal issues.
2. The Features of an Aluminum Smelter
In order to render intelligible the terminology used
herein an abbreviated description of the features of
an aluminum smelter is required. The smelter in this
case was designed and constructed to consist of 174
reduction (or electrolytic) cells called ‘‘pots’’ (A. 30,
176-177).’ These 174 ‘‘pots”’ are set up in two pot
rooms with 87 pots in each room; pot room is ‘‘a term
used in the aluminum industry to denote the reduction
ceil arrangement where aluminum oxide is smeltered
into primary aluminum metal’’ (A. 176-177, E. 46).
The two pot rooms are in two separate buildings
joined together at each end constituting a single pot
line (ibid.).
There are two stages in the construction of an
aluminum smelter. One is known as “‘first metal’’.
This is the stage at which the smelter first attains the
eapacity to produce primary aluminum through the
potroom. (A.195). The other is known as total physi-
cal completion of the plant, at which the smelter in its
entirety has been fully constructed; it includes such
matters as painting, road construction, and landscaping,
which are not critical to the start-up production. (A.
198, 242, 358-360. )
1‘* A’? refers to volumes I and II of the Appendix; ‘‘E.’’ re-
fers to volumes II and IV of the Appendix containing the exhibits.
a ee
5
3. The Strike, Noranda’s Theory of Damages, and
Defendants’ Principal Objections Thereto
The millwrights’ strike occurred from July 30 to
August 13, 1970, a period of 11 workdays (A. 72, 138,
337). Most crafts did not work during the strike (E.
143-144, A. 552-553, 246, 416). The theory underlying
most of Noranda’s damage claims was that this strike
had caused a 33-day delay, from January 23 to
February 25, 1971, in reaching ‘‘first metal’’ for
&8 pots. The major component of damages which
Noranda ascribed to that delay was the cost of
excess overtime of employees of Kaiser, Comstock-
Roper, the electrical contractor (a total of $626,361)
and Noranda’s fixed price subcontractors ($66,729).
Certain additional expenses consisting of additional
construction and raw material costs, salaried and utility
overhead payments, rental and depreciation costs of
equipment were also said to stem from this delay.
There were other items, most of them uncontested on
appeal, which were said to flow directly from the strike.
The unions presented two major objections to
Noranda’s theory, and the conclusion it drew there-
from: (1) the time target which was assertedly de-
layed by 33 days was based on a wholly unreliable and
arbitrary projection; (2) accepting the 33-day delay
premise, the unions could be charged with only a frac-
tion (calculated to be at most 35.5%) of the resulting
costs because it was caused also by the strike of an-
other craft, the laborers, and by labor inefficiency,
particularly among the electricians.’
? The claim for overtime to fixed price subcontractors was fur-
ther objected to because Noranda sought the entirety of such
overtime although some was incurred before the millwrights’ strike
and thus could not possibly be caused by it, and some was incurred
after February 25, 1971, the date to which the strike allegedly
delayed the attainment of first metal, and thus was not connected
to the strike even on that theory.
6
We now set forth in summary fashion the evidence
pertaining to these issues.
a. The Unacceptability of January 23, 1971 as a Reliable First
Metal Projection.
The projection of January 23, 1971, for 88 pots was
latest of a series of projections made by Kaiser by
utilizing a planning tool known as critical path method
(or CPM). The various inputs essential to the esti-
mate are programmed into a computer and the net
of these variables emerges as the milestone dates for
completion of particular phases of the work. One
important input is the anticipated efficiency of labor.
Kaiser developed an expected standard of labor effi-
ciency for the Noranda project. This projected stand-
ard which Kaiser estimates it will attain, is quantified
at 100%, and the efficiency actually achieved thereafter
is calculated as a percentage of that 100%. (A. 160-
163, 193, 215, 240, E. 382.)
Kaiser acknowledged, ‘‘All such conclusions . . .
depend on certain numbers of inputs. By varying the
input, of course, you can vary the conclusion’’ (A, 215).
Kaiser’s inputs into its CPM were demonstrably un-
sound based on the immense disparity between projec-
tions made and actually achieved.
Well before the millwrights’ July 30-August 13,
1970 strike, the first metal date had already been twice
revised, resulting in a total delay of two months and
three weeks to the latest date of January 23, 1971.
(A. 193-196, 216-217, E. 48) It is therefore perfectly
clear that there is nothing firm or infallible about
Kaiser’s first metal dates. The January 23, 1971 mile-
stone was of course not reached. First metal was not
attained until February 25, 1971, and then only on a
modified 88-pot basis (33 days late), and first metal on
7
the projected 174-pot basis was not attained until mid-
June 1971 (almost five months late). To ameliorate
the obvious lack of any rational cause-effect relation-
ship between an 11-day strike and a five-month delay,
Noranda ignored the failure to reach first metal on a
174-pot bk .sis until mid-June 1971, and acted instead
as if reaching first metal on an 88-pot basis February
25, 1971 was the achievement of its projected January
23, 1971 milestone. Through this sleight of hand it
reduced the delay to a more reasonable 33-day time
lag, making more palatable ascription of tie shorter
delay to the millwrights’ strike.
The unreliability of Kaiser’s CPM milestones is
further shown by the contrast between projected and
actual physical completion of the project. The June
30, 1970 CPM projected physical completion as of
March 1, 1971 (J 385, 387, A. 392), a four-month delay
(A. 219-220). But this revised date was not achieved.
Instead physical completion did not take place until
October 1, 1971 (E. 385, 387, A. 392). This seven-
month lag in completion could not rationally be as-
scribed to an 11-day strike. Indeed, as of June 30,
1970 (before the strike) completion was 20% behind
schedule; it was still 20% behind schedule as of No-
vember 30, 1970 (after the strike) (A. 219-220, 226-
227).
Yet another measure of the unreliability of the
JPM is the enormous cost overrun in the construction
of the smelter. Originally scheduled to be $85,000,000,
the cost actually came to $107,000,000, an overrun of
$22,000,000 (A. 476, 482). A cost error of this magni-
tude, of which even plaintiff sought to ascribe less
than 5% to the millwrights’ strike, plainly demon-
strates that Kaiser’s estimates of variables were seri-
ously deficient.
8
b. Labor Inefficiency, Parti ilarly Among the Electricians.
and Resulting Overtime.
As already noted, an important input into Kaiser’s
CPM projection is the expected standard of labor
efficiency. Kaiser admitted that the level actually
attained was ‘‘considerably below’’ its projection (A.
216); its progress report for June 1970 succinctly
stated, ‘‘The major portion of this increase in costs
ean be directly traced to the inefficiency of labor’? (A.
843).
Kaiser’s overestimation of labor efficiency was vast.
As of June 30, 1970, it reduced its expected cumulative
attainment of labor efficiency from 100% to 60%, and
later again reduced it to 52% (A. 409, 458-459, 509-
510). But its actual known attainment of cumulative
labor efficiency did not exceed 48.6% (KE. 382).
The cause-effect relationship between labor ineffi-
ciency and recourse to overtime to overcome it can be
concretely pinpointed. For Kaiser’s own reports show
in detail that it was primarily the inefficiency of the
electricians which eventuated in the heavy incurrence
of overtime work. ‘‘... [T]he electrical work in general
was important throughout the plant because this is an
electrolytic plant. Electrical work is a major part of
the total project and the total cost of the project .. .”’
(A. 384). And the electricians were found to be parti-
cularly inefficient (A. 461, see also, A. 228, 239).
For example, in its June 30, 1970 project status
review Kaiser pinpointed the inefficiency of the electri-
cians as a principal source of difficulty:
‘‘At the February meeting we had stressed that
critical control dates could and would be met. The
first of these dates were for the rail unloading
facility, the preparation of cathode blocks, and the
9
mixing of cathode paste for potlining. Their
original schedules were legitimate. We did not
meet them because of delays due primarily to lack
of efficiency on the part of the electricians. For
the same reason the dates are still not achieved.’’
(KE. 821, A. 220, emphasis added).
The problem with the electricians did not abate.
Kaiser’s project status review of October 15, 1970,
particularized the situation as follows (E. 860, A. 222-
223).
‘In our July review we had expected that during
the latter stage of the program, we would be ex-
periencing a gradual improvement in efficiency of
labor; it had been assumed that even though effi-
ciencies were lower at the time, there would be a
sufficient period when productivity would be better,
such that the accumulated average would be 60%
for the entire project.
The following graph portrays that this has not
heen the case. During the months of August and
September, we have only attained 48% and 46%
respectively, much of this due to the extremely low
productivity of the electricians. With the expec-
tation that there will be no improvement, it is now
projected that the accumulated average for the
entire project will be 52%, 8% below the 60%
previously envisioned. (emphasis added).
In October 1970, in an effort to increase the pro-
ductivity of the electricians, the electrical subeontrac-
tor (Comstock-Roper) laid off 100 of its 400 eleetri-
cians, separating those electricians it considered ineffi-
cient (A. 411-412, 430-431). The method chosen to
make up for the production lost by this decrease in the
the force, was recourse to scheduled overtime (FE. 868,
878, A. 412). On November 9, 1970, Kaiser scheduled
the electricians, pipefitters, and supporting crafts to
10
work five 10-hour days per week, ten hours in excess
of the regular 40-hour work week (A. 382, E. 878, 904,
A, 227-228, 241, 245, 385-368) .°
c. The Laborers’ Strike.
The laborers engaged in a three-day strike on July
23, 24, and 27, 1970, which caused a total stoppage of
work on the project for its duration. As reported by
Kaiser on August 12, 1970, the 3-day laborers’ strike
resulted in a loss of 43,464 man-hours, as compared
with the loss of 110,000 man-hours resulting from the
ensuing July 30-August 13, 1970 millwrights’ strike
of eleven working days. (A. 355-356, 404-406, E. 135,
142). The laborers’ strike was thus more intensive in
daily man-hours lost than the millwrights’ strike and
accounted for more than 28.3% of the man-hours lost
in the combined laborers’ and millwrights’ strikes of
14 working days.
B. The Proceedings Below
l. The District Court
The complaint was filed on August 15, 1970 (the day
the strike ended) and was amended as to damages only
on April 10, 1971.4 The case was tried to the court
(Meredith, J.). On December 28, 1973, the Court en-
8 On December 10 or 14 scheduled overtime was extended to all
crafts, but on a reduced basis, all crafts now working a 48-hour
work week. (A. 384-386, 415-416). The scheduled overtime was
again reduced in early January 1971, a 45-hour work week,
(A. 385-386, 415-416), until February 25, 1971, when all crafts
reverted to a 40-hour regular work week, with overtime thereafter
limited to ‘‘some spot overtime’’ (A. 200-201, 386, 416).
4 Both of the complaints caleulated damages on the basis of
injury suffered during the strike; originally Noranda claimed
$30,000 per day (A. 16) which was raised to $167,781 per day in
the amended complaint (A. 19).
11
tered judgment for Noranda against both defendants
in the amount of $914,823.54. In its accompanying
findings of fact and conclusions of law it determined
that the strike violated § 8(b)(4)(D) of the LMRA
and that both defendants were responsible therefor.
The trial court’s findings on the damage issues were
extremely sparse. The court found that Kaiser had
made a pre-strike projection of first metal for 174 pots
as of January 23, 1971, then after the strike, re-
ducing it to 88 pots; but it did not discuss the
unions’ critique of the method by which either
projection was reached. It arrived at the amount
of damages by listing, without further explana-
tion, six categories of injuries which it found the
plaintiff suffered ‘‘as a result of [defendants’ illegal]
conduct”’ (1 21, p. 21a, infra), and totalling them (id.,
p. 22a).° The entire $690,090.10 in increased overtime
payment to the employees of Kaiser, Comstock-Roper
and fixed price subcontractors ‘‘during and as a result
of the strike’? was lumped together in a single sub-
paragraph (id., 1 (c)).° The court’s sole discussion
of the unions’ objection to the damage claim and par-
ticularly to being charged for the entire delay is con-
tained in the following two sentences: ‘They also con-
tend that the damages were partially caused by a three-
day strike of the laborers in July of 1970, that the
premium time of $295,290.00 paid to the electricians
was not caused by the strike. The Court rejects all of
these contentions.’ (p. 22a, infra).
* The court rejected plaintiff’s claims for prejudgment interests,
attorneys’ fees in this suit, and ‘‘loss of cash flow caused by the
strike over a period of twenty-two years in the sum of $551,574.15”’
(23, p. 22a, infra).
* Other categories also subsumed, without even identifyi
1 th
several contested items. a
12
2. The Court of Appeals
The Court of Appeals affirmed. In an opinion by
Mr. Justice Clark, the Court approved the liability
determinations (pp. 5a-6a, infra). The court noted
the uiion’s acquiescence in the allowances of some
items of damages and sustained, as not ‘“‘clearly erro-
neous’? the controverted awards on the items other
than overtime (pp. Ta-8a, infra, nn. 1-3).
The court observed that in suits under § 303 damages
‘cannot be proven with exacting detail and the
proof is therefore quite sufficient where the evi-
dence supports a just and reasonable approxima-
tion. Sheet Metal Workers, Local 223 vy. Atlas
Sheet Metal Co., 384 F.2d 101, 109 (5th Cir.
1967).’’ (p. 9a, infra)
For that reason, although ‘‘it is true that the trial
court did not spell out in meticulous detail each item
of damage’’ (id.), the trial court’s findings were
deemed sufficient. See id., quoted at p. 24, infra.
With respect to the union’s position that plaintiff
was not entitled to recover all the losses resulting from
the delay, because that delay was caused also by the
laborers’ strike and the inefficiency of labor, partic-
ularly the electricians, the Court of Appeals reached
the same result as the District Court, but by its own
line of reasoning. The Court of Appeals determined
that labor inefficiency may have, and the laborers’
strike certainly did contribute to the delay But it
concluded that ‘‘the overall method of calculating
the damages was eminently just and fair to the Unions
and that the total amount allowed was a reasonable
approximation of the amount suffered by Noranda”’
(p. 10a, infra), because the trial court calculated the
ey “9 —_—
13
delay on the basis of 88 pots on January 23, rather
than the prior projection of 174 pots’ on that date:
“Perhaps some of this delay was occasioned by
imefficient labor and certainly some was occasioned
by the 3-day laborers’ strike, but the point is that
the trial judge chose February 25, 1971, as the
cut-off date, when only 88 pots were completed.
If he had chosen the mid-June date, when all pots
were completed, perhaps the items that the Unions
now complain about, as well as some others, would
have some weight in the final calculations. We
believe, however, that the course pursued was cer-
tainly a most reasonable and fair approximation.
Indeed, if a later date had been chosen, making
allowance for the expedition afforded the 88-pot
project, and if the trial judge would have meticu-
lously caleulated the percentages as the Unions
suszest, we ag 4 red = damages would have
otalled a much higher figure.’”’ (Pp. 9a-10 -
phasis added).* . - “ daca
REASONS FOR GRANTING THE WRIT
I. The Decision Below Subverts the Congressional Intent in
Allowing Only Compensatory Damages Under the Labor-
Management Relations Act and Ignores Accepted Tort Prin-
ciples for Measuring Recovery for Injury to Economic In-
terests Caused by Violations of Federal Law.
A. By charging defendant unions for the entire loss
resulting from the delay in reaching 88 pots, although
[perhaps some of this delay was occasioned by in-
efficient labor and certainly some was occasioned by the
* The reference to ‘‘176 pots’’ in the opinion is an inadvertent
error.
®*The Court also rejected Noranda’s cross-appeal. The loss
of cash flow was described as ‘‘reminiscent of the Rube Goldberg
cartoons that graphically transposed speculation into fact by a
series of drawings depicting causes and effects.’’ (p. 10a, infra.)
Pe eee
14
3-day laborers’ strike’’ (p. 9a, fra), the court below
undermined the Congressional determination, given
foree in Teamsters Union vy. Morton, 377 U.S. 252,
that under § 303 of the LMRA a plaintiff may recover
only for damages proximately caused by a violation of
§ 8(b) (4). The decision below is also in square conflict
with a holding of the Second Circuit that in comput-
ing back pay in a ease arising under § 10(c) of the
same Act, which likewise authorizes only compensa-
tory awards, the Labor Board must apportion the em-
ployees’ losses so as to exclude those which they would
have incurred even absent the unfair labor practice.
T'rico Products Corp. v. N.L.R.B., 489 F.2d 347 (C.A, 2,
Friendly, J.). And while the decision’s most immediate
and obvious effect is in the labor field, its principle
necessarily extends to the entire range of federal stat-
utes which allow one party to recover monetary dam-
ages from another for injuries proximately caused by a
statutory violation. For, as this Court observed in
Albemarle Paper Co. v. Moody, 422 U.S. 405, 418-419:
‘** * * where a legal injury is of an economic character,
‘[t]he general rule is, that when a wrong has been
done, and the law gives a remedy, the compensa-
tion shall be equal to the injury. The latter is the
standard by which the former is to be measured.
The injured party is to be placed, as near as may
be, in the situation he would have occupied if the
wrong had not been committed.’ Wicker v. Hop-
pock, 6 Wall. 94, 99 (1867).”’
Viewed in that broader context, the holding below is
contrary to the established principles of the law of
torts, and a series of decisions in which this Court
exhaustively considered the apportionment of dam-
ages. Those decisions avoided, but the court below
15
reached, ‘‘the one certainly unjust course of giving
the plaintiffs everything, because the defendants can-
not with certainty compute their own share’’ (L. Hand,
J., in Sheldon v. Metro-Goldwyn Pictures Corp., 106
F.2d 45, 51 (C.A. 2), affirmed and quoted with ap-
proval, 309 U.S. 390, 398).
B. In Teamsters Union v. Morton, 377 U.S. 252,
this Court unanimously held it to be the Congressional
judgment ‘‘reflected both in the language of the Fed-
eral statute and in its legislative history, that recovery
for an employer’s business losses caused by a union’s
peaceful secondary activities proscribed by § 303 should
be limited to actual, compensatory damages’’ (id. at
260, footnotes omitted). That language, as quoted by
the Court, is: ‘‘[w]hoever shall be injured in his busi-
ness or property ... shall recover the damages by him
sustained. ...”’ (td. at n. 15, this Court’s emphasis).
Thus, Morton “‘permit[s] recovery under § 303 of
damages suffered during a strike characterized by pro-
scribed secondary activity only to the extent that the
damages claimed were the proximate result of such
activity.’”’ Mine Workers v. Gibbs, 383 U.S. 715, 731,
n. 17.
The same ‘‘make-whole”’ principle of relief is estab-
lished by § 10(¢) of the Act which governs the remedial
powers of the Labor Board, see particularly Phelps
Dodge Corp v. Labor Board, 313 U.S 177, 197 and
other cases cited in Albemarle Paper Co. v. Moody, 422
U.S. 405 at 419.° Thus, questions of recovery under
the Labor-Management Relations Act are governed by
the same principles as federal statutes generally (see
® See also e.g., Republic Steel Corp. v. Labor Board, 311 U.S.
7 and Labor Board v. Carpenters Union, 365 U.S. 651, which, like
Morton (377 U.S. at 260-261) expressly reject punitive relief.
16
id. at 418-419 and p. 14 supra). Indeed, the question
raised in this case, of assessing damages proximately
caused by tortious conduct where some of the injury
suffered by the plaintiff is due to causes (be they tor-
tious or nowtortious) for which the defendant is not
legally responsible is familiar to the law of torts, and
that law, as we next show, requires apportionment in
a ease like the present.
In the seetion of his treatise entitled ‘‘Apportion-
ment of Damages’’, Dean Prosser declared:
‘‘Once it is determined that the defendant’s con-
duct has been a cause of some damage suffered by
the plaintiff, a further question may arise as to
the portion of the total damage sustained which
may properly be assigned to the defendant, as dis-
tinguished from other causes. The question is
primarily not one of the fact of causation, but of
the feasibility and practical convenience of split-
ting up the total harm into separate parts which
may be attributed to each of two or more causes.
Where a logical basis can be found for some rough
practical apportionment, which limits a defen-
dant’s liability to that part of the harm which he
has in fact caused, it may be expected that the divi-
sion will be made. Where no such hasis can be
found, and any division must be purely arbitrary,
there is no practical course except to hold the de-
fendant for the entire loss, notwithstanding the
fact that other causes have contributed to it.’’ ”
1° The analysis continues:
‘*The distinction is one between injuries which are reason-
ably capable of being divided, and injuries which are not.
* * * There will be obvious difficulties of proof as to the ap-
portionment of certain elements of damages, such as physical
and mental suffering and medical expenses, but such difficul-
ties are not insuperable, and it is better to attempt some rough
division than to hold one defendant for the wound inflicted
by the other. Upon the same basis, if two defendants each
17
The foregoing views were adopted by the American
Law Institute in Restatement of Torts, Second. See-
tion 433A, entitled ‘‘Apportionment of Harm to
Cuuses’’ provides:
‘*(1) Damages for harm are to be apportioned
among two or more causes where
(a) there are distinct harms, or
(b) there is a reasonable basis for determining
the contribution of each cause to a single harm.
(2) Damages for any other harm cannot be appor-
tioned among two or more causes.”’
The rule stated in § 433A was followed by the See-
ond Cireuit to require apportionment in determining
the amount of back pay due to employees who were
discharged for illegal reasons, but who would have
been laid off in any event in a reduction in force caused
by the employer’s loss of business. Trico Products
Corp. Vv. N.L.R.B., 489 F.2d 347 (C.A. 2). Judge
Friendly, writing for the Court, reasoned:
‘*The Administrative Law Judge was far more
convineing in finding that the unfair labor prac-
tice merely accelerated the layoffs. The situation
is the one, familiar in other contexts, ‘where a
part of the harm caused would clearly have re-
sulted from the innocent conduct of the defendant
himself, and the extent of the harm has been ag-
gravated by his tortious conduct ;’ in such instance
pollute a stream with oil, it is possible to say that each has
interfered to a separate extent with the plaintiff’s rights in
the water, and to make some division of the damages. It is
not possible if the oil is ignited, and burns the plaintiff’s barn.
“In general, it may be said that entire liability will be im-
posed only where there is no reasonable alternative.’’ Prosser,
Torts (4th ed., 1971), pp. 313-314, footnotes omitted, em-
phasis added.
18
the damages should be apportioned as between the
tortious and the innocent conduct. Restatement
of Torts 2d § 433A at 437.”’™
Reversing the Labor Board, the Court of Appeals held
that the discriminatees were entitled to back pay only
up to the date (to be determined on remand) ‘‘when
the employees would have been laid off in the absence
of’’ the protected activity which prompted their dis-
charge. Id. at 354.
Even as the discharge of the employees in Trico
‘‘merely accelerated the lay off’ of the discriminatees,
so the unions’ strike herein only aggravated the delay
which was caused by the laborers’ strike and the fail-
ure of the work force as a whole, and particularly the
electricians, to achieve the projected labor efficiency
standard. And so, even as the employer in Trico was
chargeable with only a portion of the employees’ wage
losses, so the Carpenters here should have been assessed
only for that portion of the excess costs resulting from
the delay which was attributable to the millwrights’
strike. Thus, the Eighth Cireuit’s refusal to require
apportionment of plaintiff’s damages in this case is in
square conflict with the Second Circuit’s decision in
Trico.
This apportionment principle has been uniformly
approved by this Court in a series of decisions arising
under the patent and copyright laws, culminating in
Sheldon v. Metro-Goldwyn Pictures Corp., 309 U.S.
390. There the principal question was stated to be
‘‘whether, in computing an award of profits
against an infringer of a copyright, there may be
an apportionment so as to give to the owner of the
11489 F.2d at 353; Judge Friendly’s quotation is from the
‘‘Comment”’ on § 433A(1) of the Restatement, set forth above.
19
copyright only that part of the profits found to be
attributable to the use of the copyrighted material
as distinguished from what the infringer himself
has supplied,’”’ (Jd. at 396).
Writing for a unanimous Court, Mr. Chief Justice
Hughes answered this question in the affirmative. He
found persuasive the precedents which had held that
where the infringed patent covers only a part of a ma-
chine and creates only a part of the profits, it is only
that portion which the plaintiff-patentee may receive
as damages for the enforcement so that he must, un-
less it is impossible to do so, make an apportionment
between the contribution of his patent and that made
by the defendants. Jd. at 402-405." Chief Justice
Hughes rejected the plaintiff’s reliance on the fact
that the defendants had been ‘‘found guilty of delib-
erate plagiarism’’, perceiving
‘no ground for saying that in awarding profits
to the copyright proprietor as a means of compen-
'? The leading patent cases are Westinghouse Electric & Mfg. Co.
v. Wagner Electric & Mfg. Co., 225 U.S. 604, and Dowagiac Mfg.
Co. v. Minnesota Moline Plow Co., 235 U.S. 641. In the latter case,
the Court held:
‘‘In so far as the profits from the infringing sales were
attributable to the patented improvements they belonged to
the plaintiff, and in so far as they were due to other parts or
features they belonged to the defendants. But as the drills
were sold in completed and operative form the profits result-
ing from the several parts were necessarily commingled. It
was essential therefore that they be separated or apportioned
between what was covered by the patent and what was not
covered by it, for, as was said in Westinghouse Electric & Mfg.
Co. v. Wagner Electric & Mfg. Co., 225 U.S. 615: ‘In such
ease, if plaintiff’s patent only created a part of the profits, he
is only entitled to recover that part of the net gains.’’’ 235
pany at 646, emphasis added, quoted in Sheldon, 309 U.S. at
20
sation, the court may make an award of profits
which have been shown not to be due to the in-
fringement. That would be not to do equity but
to inflict an unauthorized penalty. * * * ’’ (Id. at
405-406 )
So too, in the present case, an award of damages for
the entire loss caused by delay in reaching the 88-pot
target, where only some of that delay was caused by
the Carpenters’ strike, would ‘‘inflict an unauthorized
penalty’’ contrary to the policy of the Labor-Manage-
ment Relations Act, and the express teachings of
Morton, 377 U.S. at 260-261, see p. 15 supra.
In Sheldon and its predecessors apportionment was
required unless ‘‘the act of the defendant had made it
‘not merely difficult but impossible to carry the burden
of apportionment’ ’’ (Sheldon, 309 U.S. at 403, quoting
Westinghouse, 225 U.S. at 618).% This too, is ac-
cepted tort doctrine. As Prosser has written:
“The difficulty of any complete and exact proof
in assessing such separate damages has received
frequent mention in all these cases, but it has not
been regarded as sufficient justification for entire
liability. The emphasis is placed upon the logical
possibility of apportionment, and the distinct and
138 See also 309 U.S. at 404, describing Dowagiac, and id. at 398,
observing that the Court of Appeals had ‘‘fully recognize[d] the
difficulty in finding a satisfactory standard, [but had] decided
that there should be an apportionment and that it could fairly
be made’’.
Likewise, in Trico Products, p. 17 supra, the Labor Board was
directed to make an apportionment even though reconstruction of
when the employees would have been laid off necessarily involved
several ‘‘lines of inquiry’’, some of which Judge Friendly set
forth ‘‘as illustrative and not by way of limitation.’’ 489 F.2d at
354.
;
-
21
separate invasion of the plaintiff’s interests which
may be attributed to each cause.’’ “
This difficulty has been met, not by permitting the
plaintiff to recover from the defendant for all of its
injuries, even though he has not caused them, but by
relaxing the requirements of proof on the issue of
causation, so that ‘‘general evidence as to the propor-
tion in which the causes contributed to the result will
be sufficient to support a verdict.’’
This is but an instance of the rule which permits
‘‘just and reasonable approximation of the actual
amount of damages’’ where the nature of the injury
renders greater certainty impossible. The question
whether to apportion is one of law,"* and the answer,
as we have seen, depends on whether an apportionment
is logically possible. The rule of ‘‘just and reasonable
Prosser, Torts (4th ed., 1971), p. 318. See also id. at 317:
‘‘Evidence may be entirely lacking upon which to apportion
some elements of the damages, such as medical expenses, or
permanent disability, or the plaintiff’s pain and suffering;
but this never has been regarded as sufficient reason to hold
one defendant liable for the damage inflicted by the other.’’
Td. at 318.
*Comment d to § 434 of the Restatement of Torts, Second (p.
448) states:
‘‘The question whether the harm to the plaintiff is capable
of apportionment among two or more causes is a question of
law, and is for the decision of the court in all cases. Once
it is determined that the harm is capable of being apportioned,
the actual apportionment of the damages among the various
causes is a question of fact, which is to be determined by
the jury, unless the evidence is such that reasonable men
could come to only one conclusion.’’
See also the black letter law, particularly §§ 434(1)(b) and (2)
(b), id. p. 447.
22
approximation’? comes into play in resolving ques-
tions of fact—in ascertaining the amount of the plain-
tiff’s total loss, and in apportioning that loss among
causes."
Thus, when the court below invoked that rule to sus-
tain the trial court’s failure to apportion (pp. 9a-10a,
infra), it confused two separate and distinct lines of
analysis. The very case cited by the Court of Appeals
for permitting approximation in calculating damages
recoverable under § 303, Sheet Metal Workers Local
223 vy. Atlas Sheet Metal Co., 384 F.2d 101 (C.A. 5),
demonstrates that the trier is not thereby relieved of
the duty to separate losses which are caused by the
defendants’ violation and those which are not. For
there, the Court laid down ‘‘guidelines to aid the
District Court”’ in a new trial on the issue of damages:
‘‘Sinee section 303 is purely compensatory, all
elements of damages must be directly related to
or eaused by the unlawful secondary activity.
Thus, long distance telephone calls may be recov-
ered only if they are attributable to the picketing,
and salaries of employees who did not refuse to
work may be.recovered only to the extent that
these employees were rendered unproductive as a
result of the picketing.’’ (Jd. at 110.)
This, too, the decisions show. See, e.g., Sheldon, supra, 309
U.S. at 408:
‘*What we said in the Dowagiae Mfg. Co. Case [255 U.S. at
647] is equally true here,—that what is required is not math-
matical exactness but only a reasonable approximation. That,
after all, is a matter of judgment; and the testimony of those
who are informed by observation and experience may be not
only helpful but, as we have said, may be indispensable.
Equity is concerned with making a fair apportionment so that
neither party will have what justly belongs to the other.’
23
Thus, while the Fifth Cireuit did not use the word
‘‘apportionment’’, it made clear that as to each item of
claimed damage the trier may allow recovery only for,
and thus must determine, that portion which is attrib-
utable to the defendants’ tort. It is this method alone
which accords with the tort principles which we have
discussed and which avoids frustration of Congress’
policy that the § 303 remedy was provided ‘‘only to re-
store to people who have lost something because of boy-
cotts and jurisdictional strikes the money they have
lost.”? Sen. Robt. A. Taft, explaining § 393, 93 Cong.
Ree. 4858, quoted and treated as authoritative in Mor-
ton, 377 U.S. at 260, n. 16.
II. The Decision Below Creates an Unprecedented and Un-
sound Exception to éhe Specificity Requirements of Rule
52(a), F.R.Civ.P.
A. As shown in the Statement (p. 11, supra),
the District Court’s findings of fact were wholly
conclusory; the trier simply identified those ele-
ments of plaintiff’s damage claim which it accepted,
without specifying the factual basis for that conclu-
sion or even why it awarded the precise amount
claimed where that was in controversy. The Court’s
findings thus failed to comply with the unequivocal
requirement of Rule 52(a): ‘‘In all actions tried upon
the facts without a jury ... the Court shall find
the facts specially ....’’ Nevertheless, the Court of
Appeals affirmed some of those findings on the basis of
the ‘‘clearly erroneous’’ review standard of that rule.
See pp. Ta-8a, nn. 1, 2 and 3, infra. And it tacitly
accepted, see pp. 9a-10a infra, the Critical Path method-
ology on which all delay claims depended, although
24
the trial court had made no findings with respect to the
unions’ detailed challenge to the validity of that
method. The Court said:
‘‘While is is true that the trial court did not
spell out in meticulous detail each item of damage,
he did clearly find that each item was caused by the
illegal srike and that each was a just and reason-
able approximation of the actual amount of the
damages. The cases on claims of this type require
no more. Vulcan Materials Co. v. United Steel
Workers of America, 430 F.2d 446, 457-58 (5th
Cir. 1970), cert. denied, 401 U.S. 963 (1971).”’
(p. 9a, infra)
The Court of Appeals thereby carved out a special
rule for cases on claims ‘‘of this type’’—that is, suits
for damages under § 303 of the LMRA. This holding
should be reviewed because of its recurring importance
in suits under § 303, and because it is clearly mistaken.
The importance of the question can be readily per-
ceived. The amount of damages caused by a strike in
violation of § 303 will almost invariably be a subject of
controversy in such suits precisely because, as the Court
of Appeals observed, they ‘‘cannot be proven with ex-
acting detail’’ (id. p. 9a, infra), the union is not likely
to take the emplover’s claim on faith. Indeed, since
some Circuits have held that a Labor Board finding
that a violation of §8(b)(4) has been committed is
binding on the defendant in a suit under § 303,” the
amount of damages issue will often be the only matter
in controversy.
18 See Painters District Council 38 vy. Edgewood Contracting Co.,
416 F.2d 1081 (C.A.5); International Wire v. Loval 38, 475 F.2d
1078 (C.A.6), cert. denied, 414 U.S. 867; Paramount Transport
Systems v. Teamsters Local 150, 436 F.2d 1064 (C.A.9).
25
The Court of Appeals’ view that the ordinary re-
quirements of clarity and specificity in findings are
excused in suits under § 303 finds no support in the
single case which ‘it cited, Vulcan Materials Co. v.
United Steel Workers of America, 430 F.2d 446, 457-
458 (C.A. 5), cert. denied, 401 U.S. 963. For while
that case did arise under § 303, the sufficiency of the
findings was nowhere discussed in the Vulcan opinion;
that case was apparently cited because it reaffirmed
and quoted with approval the holding in Sheet Metal
Workers (see p. 22 supra) that damages may be deter-
mined on the basis of a just and reasonable approxi-
ration, following (as the Vulcan court noted) Story
Parchment Co. vy. Paterson Parchment Paper Co., 282
U.S. 255.”
Indeed, the decision below is in direct conflict with
two decisions in the Ninth Circuit which have vacated
damage awards in § 303 suits because the trial court
had not complied with Rule 52(a). Carpenters Local
1273 v. Hill, 398 F.2d 360 (C.A. 9); Plumbers & Fit-
ters, Local 761 v. Matt J. Zaich Const. Co., 418 F.2d
1054 (C.A. 9). As the Court said in the latter case:
‘‘when it is possible to prove damages by definite
caleulation, they should be proved in detail.
Christiansen v. Mechanical Contractors Bid De-
pository, 230 F. Supp. 186, 194 (D. Utah 1964).
Cf. Story Parchment Co v. Paterson Parchment
Paper Co., 282 U.S. 555, 562”’ (Id. at 1059)
This citation of Story leaves no doubt that the Ninth
Cireuit was fully cognizant of the rule that a ‘‘just
The only other damage determinations in Vulcan were that
attorneys’ fees for removing pickets may be recovered and that the
failure to mitigate damages defense was without merit.
26
and reasonable approximation’’ of damages is per-
missible. But that Court correctly declined to treat it
as an excuse for inadequate findings. For that rule
is but an exception—albeit one which is significant
and unquestioned—to the overriding principle that
‘‘damages may not be determined by mere speculation
or guess’’, as the Story opinion shows, 282 U.S. at 562.
Thus, the law does not regard imprecision in the cal-
culation of damages as inherently desirable. Approxi-
mation is permitted solely in order to allow the plaintiff
some recovery even though ‘‘the tort itself is of such
a nature as to preclude the ascertainment of the amount
of damages with certainty’’ (id.). Given the reason
for the rule, the award should be as exact as the cir-
cumstances will allow. Precision in the fact finding
process is essential to that end. If the inherent uncer-
tainty bears at all upon the degree of specificity which
findings should achieve, it call for greater care. For
then the findings perform the indispensable function
of setting the upper and lower limits of the damages
which the evidence can justify; only if that is care-
fully done can a range be determined within which an
approximation will be just and reasonable. Unless
the individual components of the damage award are
carefully examined neither the trier nor the reviewing
court can determine that the total is anything but
speculative, and that the plaintiff’s failure to prove
greater damages is due to uncertainties created by the
defendant rather than the inherent weakness of the
plaintiff’s claim.”
” One example will illustrate our point, and also demonstrate the
prejudice to the defendants in this case:
The Court of Appeals opined that if the trial judge ‘‘had
chosen the mid-June date when all pots were completed’’ rather
than the date when 88 pots were completed ‘‘and if the trial
27
While the importance of this issue for the adjudica-
tion of suits under § 303, and the conflict with the § 203
cases in the Ninth Circuit amply justify certiorari,
the impact of the decision will not readily be confined
to its immediate statutory context. To excuse noncom-
pliance with Rule 52(a) in computing damages because
these are subject to just and reasonable approximation
is to invite error, and to frustrate appellate review
wherever the inherent uncertainty in the amount gives
rise to approximation, most notably in the antitrust
field where Story and its progeny are in fullest flower.
judge would have meticulously calculated the percentages as the
Unions suggest, we dare say the damages would have totalled a
much higher figure’’ (pp. 9a-10a, infra). This is admittedly
surmise (‘‘we dare say’’) and thus impermissible. Moreover, it is
inherently unlikely. The 88-pot theory originated not with the
trial judge, but with Noranda; Noranda presumably would have
presented its claim on the basis of the delay in reaching 174 pots
if it had thought that a larger recovery ould thereby result. In-
deed, one of the Unions’ major objections to the CPM method
was that by stating its claim on the basis that 88 pots should
be reached on January 23, 1971, whereas that day wa. originally
the target for 174 pots, Noranda had camouflaged the utter im-
plausibility of ascribing a five-month delay in completion to an
11-day millwright strike. Neither the trial court nor the Court
of Appeals dealt with this or any of the other objections to the
CPM projection. Thus, the Court of Appeals excused the in-
sufficiency of the findings by assuming the answer to one of the
critical issues which those findings should have addressed—the
validity of the method which was the essential predicate of the
major component of the entire damage award.
28
CONCLUSION
For the foregoing reasons, this Petition for Certio-
rari should be granted.
Respectfully submitted,
WittiamM A. McGowan a
101 Constitution Avenue, N.W.
Washington, D.C. 20001
Morris J. LEVIN
S. SHELDON WEINHAUS
1125 Areade Building
812 Olive Street
St. Louis, Missouri 63101 A P P } ) N D I
GEORGE KAUFMANN ,
2101 L Street, N.W.
Washington, D.C. 20037.
Attorneys for Petitioners
la
APPENDIX A
Opinion of the Court of Appeals
UNITED STATES COURT OF APPEALS
FOR THE EIGHTH CIRCUIT
No. 741467
No. 74-1562
Noranpa ALuminuM, Ivc.,
Appellee and Cross-Appellant,
V.
Unrirep BroTHEerHoop OF CARPENTERS AND JOINERS OF
America, AFL-CIO, and Unirep BrorHernoop or
CARPENTERS AND JoINeRS or America, AFL-CIO,
Locau 618,
Appellants and Cross-Appellees.
Appeal and Cross Appeal from the United States District
Court for the Eastern District of Missouri
Submitted: March 10, 1975
Filed: January 5 1976
Before Gisson, Chief Judge, CLtark, Associate Justice,*
and Lay, Cireuit Judge.
Mr. Justice CLARK.
Appellants and cross-appellees, United Brotherhood of
Carpenters and Joiners of America, Ai'L-CIO (Carpenters’
International) and Local 618 of the United Brotherhood of
Carpenters and Joiners of America, AFL-CIO (Local 618)
appeal from a judgment in the amount of $914,823.34 re-
covered against them by appellee and cross-appellant,
Noranda Aluminum, Ine. (Noranda), a Delaware corpora-
tion. The recovery was based on a jurisdictional strike
* Associate Justice Tom C. Clark, United States Supreme Court,
Retired, sitting by designation.
2a
called and maintained by the Unions at the construction
site of a primary aluminum smelter being built by Noranda
in New Madrid, Missouri, in 1970. Jurisdiction was laid
under § 303(b) of the Labor Management Relations Act of
1947, as amended, 29 U.S.C. § 187, and § 8(b)(4) thereof,
99 U.S.C. § 158(b) (4). The District Court found the strike
to be illegal under § 158(b) (4) (D) for which compensatory
damages were recoverable under § 303(b) but denied pre-
judgment interest, reasonable attorneys’ fees incurred in
the prosecution of the suit, and damages for the loss of
cash flow. We affirm the judgment.
I,
The smelter was being constructed for Noranda under a
contract with Kaiser Engineers, Inc. (Kaiser), during the
period between March, 1969, and February, 1972, on a cost-
plus-fixed-fee basis. Kaiser had collective bargaining agree-
ments on a national basis with the international unions op-
erating in the building trades. Its contract with Carpenters’
International provided, among other things, that Kaiser
would work the hours, pay the wages, and observe the work-
ing conditions established or agreed upon by Carpenters’
International and the recognized bargaining agent in the
locality where the work was performed. The Carpenters’
International further agreed with Kaiser that ‘‘there will
be no stoppage of work or any strike of its members either
collectively or individually until said dispute or misunder-
standing has been referred to the International Office of
the Union and arbitrated between such International Office
of the Union and the Home Office Representative of the
employer.’’ Preparatory to beginning construction, pre-
job conferences and ‘‘mark up’’ meetings were held to de-
termine the jurisdiction of the various unions involved in
the project. Subsequently, Kaiser issued a ‘‘Summary
of Jurisdictional Agreements, Joint Board Decisions, and
Work Assignments,’’ which included a section on work
assignments that were still in dispute. With reference to
3a
the latter, Kaiser assigned the work ‘‘in accordance with
the National Joint Board procedure’’ by utilizing local
and other practices in the trade. Under this section the
pipefitters were assigned ‘‘air lift systems,”’ ‘recovery
systems,’’ and ‘‘air operated gates and valves,’’ while the
millwrights were assigned ‘‘dry material chutes”’ and ‘‘ rack
and pinion gates.’’ However, the cover letter transmitting
this Summary provided that the assignments were subject
to change by agreement between the disputing trades.
The record indicates that a number of jurisdictional dis-
putes arose, of which some were settled by international
representatives, othc:s by business agents and stewards
A list of disputes between the millwrights and the pipe-
fitters was prepared by Kaiser in October, 1969, and in-
cluded such work assignments as ‘‘anode paste equipment od
“dry material chutes,’’ and ‘‘rack and pinion gates.”’ The
pipefitters’ claim to jurisdiction over the latter two areas
arose through an interpretation by the pipefitters of the
“systems”? used in the Kaiser assignment. The pipefitters
aaunes that ‘‘chutes and gates’’ were included within
‘systems’’ and insisted that such work be assigned to them
Kaiser subsequently made such a transfer on the under-
standing that the respective stewards of the disputing
unions had agreed upon a division of the work in dispute
along the line of the ‘‘St. Louis Agreement.’’? This agree-
ment provided that millwrights or pipefitters or both in-
stall equipment depending on the ‘‘system’’ in which the
item functioned, its relation to other equipment and simi-
lar factors. In late June, a jurisdictional dispute arose at
the smelter site despite Kaiser’s claim to have reached
the understanding with the stewards. Both Local 618
and Carpenters’ International deny that they agreed to be
bound by the ‘‘St. Louis’ rules, and all parties conclude
that this is the crux of the controversy.
In an effort to settle the dispute, a meeting was held on
July 8, 1970, among representatives of the Internationals
4a
and the business agents and stewards of the two locals.
No agreement was reached, however, and the controversy
was referred to the ‘‘ Presidents’ Committee.’’ The ‘‘ Presi-
dents’ Committee’’ was established to resolve this type of
controversy. However, no action was taken either by the
Presidents’ Committee or the Joint Board toward the set-
tlement of the controversy. Kaiser, on the contrary, re-
ceived a telegram from the Joint Board, directing it to pro-
ceed immediately with its initial work assignment since
there was no agreement between the trades involved. Kai-
ser advised the Board that ‘‘any changes [it made] were
at the job steward level at the job site.’’ Kaiser insisted
that the dispute be submitted to the Joint Board for deci-
sion on the merits, but appellants refused. Likewise, the
contractor’s suggestions that the parties arbitrate as pro-
vided in the contract between Kaiser and Carpenters’ In-
ternational fell on deaf ears. As the District Court spe-
cifically found, the record shows that the Business Agent
of Carpenters’ Local 618 had his ‘‘instructions’’ from Car-
penters’ International. See Findings 11 and 12.
On July 29, one day before the strike began, Kaiser
agreed to temporarily halt work on the disputed items if
the Business Agent of the Carpenters’ Local 618 would
meet with the Business Agent of the Pipefitters the next
day. Kaiser issued the order and the pipefitters halted
work on the 29th but the millwrights did not. The proposed
meeting between the Business Agents was never held be-
cause the pipefitters’ Business Agent was in an earlier
scheduled business meeting, and the millwrights refused
to wait until that meeting was over. They would not
reschedule the proposed meeting. The pickets came on
the next day, July 30, and continued through August 13,
1970. The object of the strike ‘‘was to force Kaiser to
put millwrights on the rack and pinion gates and chutes
and to remove the pipefitters therefrom.’’ Both Kaiser
and the Joint Board requested the President of the Car-
5a
penter’s International to instruct Carpenters’ Local 618
to remove the picket line but the request was ignored.
IL.
Appellant-Unions’ first claim is that the strike was not
a jurisdictional dispute but on the contrary was caused by
Kaiser’s ‘‘failure to honor his own contractual assignment
of work to which he has committed himself.’’ Cf. Highway
Truckdrivers, Local 107, 134 N.L.R.B. 1320 (1961). Ap-
pellant Unions say that Kaiser’s August 1969 ‘‘Summary’”’
obligated it to assign dry material chutes and pinion gates
to the millwrights. However, the 14-day work stoppage
here was the direct result of the conflicting jurisdictional
claims of the pipefitters and the millwrights over that work.
The situation fits like a glove the prohibition of § 8(b) (4)
(D), regardless of whom the ‘‘Summary”’ favored. The
nature of the conflict was the same and the opposing claims
resulting in the strike were just as intolerable. Hence the
resulting strike is illegal simply because ‘‘both groups
persist in laying claim to the disputed work.’’ Laborers Lo-
cal 116 (E & S Masonry, Inc.), 187 N.L.R.B. 482, 76 LRRM
1052, 1053 (1970). As Mr. Justice Black so well said as
to a similar situation in N.L.R.B. v. Radio & Television
Broadcast Engineers Union, 364 U.S. 573 (1961):
It is true, of course, that employers normally select
and assign their own individual employees according to
their best judgment. But here, as in most situations
where jurisdictional strikes oceur, the employer has
contracted with two unions, both of which represent
employees capable of doing the particular task in-
volved. The result is that the employer is placed in a
situation where the finds it impossible to secure the
benefits of security from either of the contracts, not
because he refuses to satisfy the unions but because the
situation is such that he cannot satisfy them.... We
therefore are not impressed by the Board’s solicitude
for the employer’s right to do that which he has not
been, and most likely will not be, able to do. At 582-
583.
6a
Here, in addition, the contract was ambiguous on the point
which makes it the more imperative that the purpose of
§ 8(b)(4)(D) not be frustrated. International Brother-
hood of Carpenters v. C. J. Montag & Sons, 335 F.2d 216,
220 (9th Cir. 1964), cert denied, 379 U.S. 999. However, we
need not decide the matter on such a basis for here the
trial court judge found against appellant unions deciding
that a local agreement between the stewards of the com-
peting unions had superseded the Kaiser agreement under
the ‘‘Summary.’’ We cannot say on the record here that
this finding is clearly erroneous.
The Carpenters’ International also argues that it cannot
be held liable for the action of Local 618. But the under-
lying facts were decided against the Carpenters’ Inter-
national. The trial judge found that the strike was the
result of the joint effort of the Carpenters’ International
and Local 618. The record also shows that the Carpenters’
International, although kept fully informed of the situa-
tion, did nothing to prevent the strike. On the contrary,
during its progress, the International continually ignored
the pleas of Kaiser and the Joint Board to call it off.
We have made a careful examination of the record and
find that substantial evidence supports the findings, and we
cannot conclude that they are clearly erroneous. See,
Findings 4, 5,6 and 7; N.L.R.B. v. International Longshore-
men’s and Warehousemen’s Union, Local 10, 283 F.2d 558,
565-66 (9th Cir. 1960); International Brotherhood of Car-
penters v. C. J. Montag and Sons, 335 F.2d 216, 221 (9th
Cir. 1964), cert. denied, 379 U.S. 999 (1965) ; Truck Drivers
Local Union 728 v. N.L.R.B., 332 F.2d 693, 697 (5th Cir.
1964) ; International Brotherhood of Electrical Workers
v. N.L.R.B., 181 F.2d 34, 38 (2d Cir. 1950), aff’d, 341 U.S.
694, 704 (1951).
ITI.
Finally, appellant-Unions attack the award of damages
as being totally unconnected to the strike and not caleu-
7a
lated with reason and fairness. They downgrade the
Kaiser estimates. Those estimates were prepared at the
insistence of Noranda and base recovery on a comparative
study between the time the project should have been com-
pleted without the strike and the actual time it took with
the strike [C.P.M.]. They criticize the inclusion of certain
elements in these computations, such as the time to attain
‘*first metal’’ (January 23, 1971), the estimates of labor
efficiency, and the failure of Kaiser to give any weight
whatsoever to other significant events claimed to bear di-
rectly on the delay encountered.
We have carefully considered each of these claims.
Noranda’s final construction cost was $22 million over its
original estimate of $85 million. It employed a task force
of Kaiser professional personnel to determine the damages
suffered because of the carpenters’ strike. The experts
came up with a number of damage items, summarized in
Noranda’s Exhibit 80, wi. .: include: cost directed at
stopping the strike and picketing; railway demurrage, truck
detention, warehousing costs, and rehandling expenses;
construction and office equipment losses; salaries and util-
ity overhead paid to cost-plus-fixed-fee contractors; start-
up losses; and, the largest item, $693,090.10, covering pre-
mium payments of working manhours lost during, or as a
result of, the strike. The court denied recovery of pre-
judgment interest, attorneys’ fees, and loss of cash flow.
A judgment was entered for $914,823.54 covering the other
items above listed.
The appellant-Unions acquiesce in some of the allowances
of the trial judge, including: (a) salary and expense
amounts and ati orneys’ fees directed at stopping the strike;
(b) railway car demurrage, truck detention, warehousing
costs, ete., except for $9055'; (c) rental and depreciation
1 Appellant-Unions contest an item of $9055 of these costs result-
ing from ‘‘the unloading of bus materials on the ground at the
Noranda site.’’ The evidence as to it is not crystal clear.
8a
costs of construction and office equipment, except two items
(office equipment overhead loss, $5345.33, and builders risk
‘nsurance premium, $2719.537; (d) salaries and utilities
overhead paid to cost-plus-fixed-fee contractors; and (e)
35.5 per cent * of construction and raw material costs in-
curred to minimize start-up delay and utility overhead pay-
ments for a trained production staff that was forced to re-
main idle for 33 days.
The Unions dispute item (c) of the trial judge’s findings
on damages which includes increased overtime premium
payments to work manhours lost by the craft construction
employees of Kaiser Engineers, Comstock-Roper, and fixed-
price subcontractors. Appellant-Unions break it down into
two parts: $626,361 ascribed to work performed for Kaiser
and Comstock-Roper, the electrical subcontractor, and over-
time in the sum of $66,729.10 ascribed to work performed
for fixed-price contractors. In essence the appellant-
Unions say that this extra cost is attributable to the in-
efficiency of labor and a three-day strike of laborers which
shut down work on July 23, 24, and 27, 1970. They, there-
fore, acquiesce in only 35.5 per cent of this item on the
same ground as in item (f).
Section 303(b) provides for the recovery of ‘‘damages
sustained and costs of suit’? in cases involving illegal
jurisdictional strikes. This includes all actual compensa-
tory damages. Teamsters Local 20 v. Morton, 377 U.S. 252,
2 Appellant-Unions reduce the ‘‘office equipment overhead loss’’
to the period of 15 days during which the strike lasted. Obviously
the strike caused a longer period of delay than the 14 days it ac-
tually existed, and we cannot say that the 30 days allowed was
clearly erroneous. The same is true as to the builders risk insur-
ance premium.
3 Appellant-Unions say that 64.5 per cent of this item is attrib-
utable to other causes, 7.e., 54.8 per cent to labor in efficiency and
9.7 per cent to a 5-day laborers’ strike. The trial judge found to
the coutrary and on this record we cannot say the finding was
clearly erroneous.
9a
260 (1964). Experience in this field clearly shows that
damages resulting from illegal jurisdictional strikes can-
not be proven with exacting detail and the proof is there-
fore quite sufficient where the evidence supports a just
and reasonable approximation. Sheet Metal Workers, Local
223 v. Atlas Sheet Metal Co., 384 F.2d 101, 109 (5th Cir.
1967). While it is true that the trial court did not spell
out in meticulous detail each item of damage, he did clearly
find that each item was caused by the illegal strike and that
each was a just and reasonable approximation of the actual
amount of the damages. The cases on claims of this type
require no more. Vulcan Materials Co. v. United Steel
Workers of America, 430 F.2d 446, 457-58 (5th Cir. 1970),
cert. denied, 401 U.S. 963 (1971).
The Unions’ major criticism centers on Noranda’s reli-
ance upon Kaiser’s CPM method of computation which pre-
dicted January 23, 1971, as first metal date. In fact it was
not reached until February 25, 1971. But the Unions over-
look entirely the fact that this date was only first metal
date on a modified basis of 88 pots, barely 50 per cent
of the original projection. In calculating the damages the
court accepted this date which only permitted a 33-day
delay time when in fact it would have been much longer
for the entire 176 pots called for in the specifications. In-
deed, ‘‘total metal date’’ was not made until mid-June,
1971, almost five months later than originally projected.
Perhaps some of this delay was occasioned by inefficient
labor and certainly some was occasioned by the 3-day
laborers’ strike, but the point is that the trial judge chose
February 25, 1971, as the cut-off date, when only 88 pots
were completed. If he had chosen the mid-June date, when
all pots were completed, perhaps the items that the Unions
now complain about, as well as some others, would have
some weight in the final calculations. We believe, however,
that the course pursued was certainly a most reasonable
and fair approximation. Indeed, if a later date had been
chosen, making allowance for the expedition afforded the
10a
88-pot project, and if the trial judge would have meticu-
lously calculated the percentages as the Unions suggest,
we dare say the damages would have totalled a much
higher figure. We, therefore, conclude that the overall
method of calculating the damages was eminently just and
fair to the Unions and that the total amount allowed was
a reasonable approximation of the amount suffered by
Noranda.
IV.
On Noranda’s cross-appeal, we find that the trial judge’s
conclusion was also correct. The claimed depiction of cash
flow or profit is reminiscent of the Rube Goldberg cartoons
that graphically transposed speculation into fact by a
series of drawings depicting causes and effects. Likewise,
to award prejudgment interest would have been to run
contra to the prevailing rule. Here the damages were un-
liquidated and could not be ascertained prior to judgment.
It is claimed that a majority of the money expended by
Noranda was paid out by November 1, 1970. However, the
greater part of the damage suffered was in the premium
payments made for overtime which occurred between
November 9 and February 25, 1971.
As to the attorney fees, we do not feel that Noranda
brings itself within the class of exceptional cases warrant-
ing the allowance of fees as a punitive measure or for
reasons of justice. While the action of the Unions was not
in the best tradition of the trades, we feel that it would
be untoward for us to upset the considered judgment of
the trial judge who lived through the matter in all of its
stages.
The judgment is therefore affirmed.
lla
APPENDIX B
Judgment of the Court of Appeals
UNITED STATES COURT OF APPEALS
FOR THE EIGHTH CIL.CUIT
SerTeMBER Term, 1975
No. 74-1467
Noxanpa ALuminum, Inc.,
Appellee,
Vv.
Unitrep BrorHerHoop oF CARPENTERS AND JOINERS OF
America, AFL-CIO, anp Unirep Brotnernoop or Car-
PENTERS AND Jorners or America, AFL-CIO, Locat 618,
Appellants.
No. 74-1562
Noranpa ALuminuM, INc.,
Appellant,
V.
Unitep BrorHerRHoop oF CARPENTERS AND JOINERS OF
America, AFL-CIO, anp Unrrep BrotHEerHoop or Car-
PENTERS AND Jotners Or America, AF'L-CIO, Locat 618,
Appellees.
Appeals from the United States District Court for the
Eastern District of Missouri.
These causes came on to be heard on the record from
the United States District Court for the Eastern District
of Missouri and were argued by counsel.
On Consideration Whereof, it is now here ordered and
adjudged by this Court that the judgment of the said Dis-
trict Court in these causes be and the same is hereby af-
firmed.
January 5, 1976
12a
APPENDIX C
Order Denying Petition for Rehearing
UNITED STATES COURT OF APPEALS
FOR THE EIGHTH CIRCUIT
September Term, 1975
74-1467
Noranpa ALuminuM, INc., Appellee,
v.
Unitrep Brotuernoop or CARPENTERS AND JOINERS OF
America, AFL-CIO, et au., Appellants.
74-1562
Noranpa ALuMINuM, INnc., Appellant,
v.
Unrrep BrotuEernoop or CARPENTERS AND JOINERS OF
America, AFL-CIO, er au., Appellees.
Appeals from the United States District Court
for the Eastern District of Missouri
Petition of appellee-appellant, Noranda Aluminum, for
rehearing filed in this cause having been considered, it is
now here ordered by this Court that the same be, and it is
hereby, denied.
February 17, 1976
13a
APPENDIX D
Findings of Fact and Conclusions of Law of the District Court
UNITED STATES DISTRICT COURT
EASTERN DISTRICT OF MISSOURI
EASTERN DIVISION
No. 72 C 33 (1)
Noranpa ALuminuM, Inc.,
Plaintiff,
Vv.
Unrrep BrorHerHoop or CARPENTERS AND JOINERS OF
America, AFL-CIO, anp Unitep BrorHernoop or Car-
PENTERS AND Jorners OF Amenica, AFL-CIO, Loca.
No. 618,
vefendants.
FINDINGS OF FACT
(Filed in U.S. District Court December 28, 1973)
1. Noranda Aluminum, Inc. (hereinafter referred to as
‘‘Noranda’’), is a domestic wholly-owned subsidiary of
Noranda Mines, Ltd., a foreign corporation (which in the
course of the proceedings herein agreed that all its claims,
if any, against defendants are merged with plaintiff's
claims and that it would be bound by these proceedings
and the findings and judgment of this Court.)
2. Noranda was incorporated in Delaware in 1968 to
establish and operate a 200-acre primary aluminum smelter
in New Madrid County, Missouri.
Noranda entered into a contract with Kaiser Engineers,
Ine. (hereinafter referred to as ‘‘Kaiser’’), for the engi-
neering design and construction of its smelter on a cost-
plus-fixed-fee basis.
l4a
The contract called for the design and construction of a
smelter consisting of 174 reduction cells or ‘‘pots’’ with a
capacity of 70,000 tons per year production of primary
aluminum.
3. Under the contract between Noranda and Kaiser, the
employment of all subcontractors and building and con-
struction trades employees, as well as the work tasks to be
performed by those subcontractors and employees, were
to be and were performed and determined by Kaiser.
In the performance of its contract with Noranda, Kaiser
set up a field construction staff at the site in New Madrid
County, Missouri, to manage, direct, and support direct
construction activities. This construction staff assigned
work to and supervised the work performed by the labor-
ers, pipefitters, painters, teamsters, teamster operators,
operating engineers, surveyors, boilermakers, cement ma-
sons, carpenters, millwrights, and iron workers directly
employed by Kaiser, as well as the electricians employed
by Kaiser’s electrical subcontractor, Comstock-Roper, and
other subcontractors employed from time to time by
Kaiser. .
4. Pursuant to its collective bargaining agreements with
international building and construction trades unions,
Kaiser conducted a pre-job conference at the construction
site in February 1969, before actual construction activities
began. At this meeting, attended by both international
and local representatives of the various trades involved in
the work, Kaiser agreed to observe the terms and condi-
tions of employment established by the various trades in
the Southeast Missouri building trades area.
5. Pursuant to its collective bargaining agreements with
the respective international building and construction
trades unions, Kaiser obtained craft employees using the
local labor organizations of the respective internationals
as a hiring hall source for employment and first construc-
tion activities began in March 1969.
l5a
6. In July 1969, Kaiser held several ‘‘mark-up’’ meet-
ings to review local area and trade practices with respect
to the assignment of work among the trades in the con-
struction of the smelter. At these meetings, attended by
both international and local representatives of the various
building and construction trades, claims to particular work
performance and items of equipment were asserted by the
respective international and local representatives. Fol-
lowing these meetings, and on August 25, 1969, Kaiser
issued a Summary of Work Assignments to the interna-
tional and local union representatives in attendance at the
July 1969 meetings.
7. Kaiser’s August 25, 1969, Summary assigned certain
**systems’’ in the various facilities comprising the alumi-
num smelter to pipefitter members of the United Associa-
tion of the plumbing and pipefitting industry of the United
States and its Local Union No. 562. The Summary as-
signed to millwright members of the United Brotherhood
of Carpenters and Joiners of America and its Local 618
certain equipment items known as dry material handling
rack and pinion gates and dry material handling chutes;
in the case of the latter equipment items, the assignment
was in terms of a local ironworker-millwright agreement.
8. In late June 1970, Carpenters Local 618 representa-
tive, J. D. Morris, complained to Kaiser that pipefitters
were performing work on rack and pinion gates and mate-
rial handling chutes that had been assigned to millwrights
in the August 25, 1969 Summary. On July 8, 1970, inter-
national and local representatives of the millwrights and
pipefitters met with Kaiser to discuss the dispute. Failing
agreement the international representatives involved
agreed and informed Kaiser that the dispute would be
referred for determination by a special joint committee
established by the United Brotherhood of Carpenters and
the United Association to resolve jurisdictional disputes
between the trades without resort to the procedures of the
16a
National Joint Board for the settlement of jurisdictional
disputes. On July 16th, however, the United Brotherhood
also complained to the National Joint Board.
9. In November 1969 and January 1970, Ray Brown, the
millwright steward, informed Kaiser that he and United
Association Local 562 steward, DeWeese, had worked out
an arrangement covering the installation of rack and pin-
ion gates and material handling chutes which would cause
‘‘no problems’’ on the Noranda job. Other such arrange-
ments in the past had been worked out between various
crafts on the job from time to time.
10. The millwrights and pipefitters continued to work on
rack and pinion gates and material handling chutes at the
Green Carbon Plant in the period July 3-July 28, 1970.
11. At some time before July 28, 1970, Carpenters Local
618 business representative Morris, a representative of a
carpenter type of local who did not know or understand
millwright work, contacted Frederick Bull, the General
Executive Board member of the United Brotherhood, who
had been assigned by the United Brotherhood to advise and
assist Morris as the international union’s jurisdictional
expert on millwright work. Morris described to Bull the
work activities, as reported by Brown, being performed by
pipefitters on rack and pinion gates and chutes at the
Green Carbon Plant. On the basis of Morris’ descriptions,
Bull informed Morris that pipefitters were performing
work on gates and chutes at the Green Carbon Plant that
belonged to millwrights under the August 25, 1969, assign-
ments and in accordance with the claims of trade autonomy
contained in the Constitution of the United Brotherhood of
Carpenters.
12. On July 28, 1970, Morris confronted Al Gordon, a
representative of Kaiser’s labor relations department in
charge of the handling of jurisdictional disputes, and
demanded that Kaiser take pipefitters off the work they
17a
were then performing on gates and chutes at the Green
Carbon Plant and place millwright members of the United
Brotherhood of Carpenters and its Local 618 on the work;
Morris stated that he had talked with the International
and had his instructions. At the time of this conversation,
neither Morris nor the United Brotherhood of Carpenters
nor millwright steward Brown, upon whose observations
the demand was based, were aware that millwrights, in fact
were performing final installation work on Green Carbon
Plant gates and chutes or that they had been doing so since
July 3, 1970, along with pipefitters. Morris however, de-
manded the removal of pipefitters from the work and re-
quested Gordon to contact the General Office of the United
Brotherhood of Carpenters concerning Morris’ instructions
Gordon then telephoned the General Office of the United
Brotherhood of Carpenters and talked with Jimmy Jones
the assistant to General President Hutcheson and the
United Brotherhood’s international representative in
charge of its jurisdictional office. Jones, as had General
Executive Board member Bull on several occasions in the
past, demanded that Kaiser take pipefitters off the work
they were then performing on Green Carbon Plant gates
and chutes and replace them with millwrights, threatening
trouble on the job if Kaiser did not comply with Jones’
demand. Jones then instructed Morris, in the hearing of
Gordon, that if Kaiser did not remove pipefitters and re-
place them with millwrights on the disputed work, Morris
had authority to exercise his prerogative, which included a
strike and picket line under the provisions of the United
Brotherhood’s Constitution for job or shop strikes.
13. As of the July 28, 1970, meeting between Gordon
and Morris, Kaiser had not received any determination
of the dispute between the United Association and the
United Brotherhood of Carpenters from the special jur-
isdictional committee of those two internationals to which
the dispute had been referred on July 8, 1970, and had
received no job decision from the National Joint Board
18a
for the settlement of jurisdictional disputes with regard
to the dispute between United Association and the United
Brotherhood. Gordon explained to Morris that in the
absence of any determination from either the special juris-
dictional committee or the National Joint Board, Kaiser
could do nothing to change the way in which work on
rack and pinion gates and chutes was then being per-
formed by both pipefitters and millwrights other than
to direct discontinuance of all work on rack and pinion
gates and chutes at the Green Carbon Plant. Gordon then
informed Morris that United Association Local 562 busi-
ness representative Steska would be at the jobsite for
another jurisdictional meeting on July 29, 1970, and at that
time Gordon would attempt to set up a meeting between
Steska and Morris in an effort to resolve the problem at
the local level. Morris agreed to meet with Steska, which
to that date he had refused to do, because the dispute was
pending before the international’s special jurisdictional
committee. Gordon issued instructions that neither pipe-
fitters nor millwrights were to perform any further work
on rack and pinion gates or chutes at the Green Carbon
Plant until after the proposed meeting between Steska
and Morris on July 29th.
14. Due to a mix-up in schedules, Morris did not meet
with Steska at the jobsite and refused to meet with Steska
at Morris’ home, since Morris had already informed the
other construction trades on the project that a strike and
picket line would oceur on July 30, 1970.
15. At the beginning of the workday on July 30, 1970,
members of the United Brotherhood of Carpenters and
members of the United Brotherhood of Carpenters Local
618 went out on strike and picketed the Noranda construc-
tion project. During the continuance of the strike and
picketing, both Kaiser and the National Joint Board re-
peatedly requested General President Hutcheson to direct
cessation of the strike and picketing and either adjust the
19a
dispute directly with the Uniited Association or by sub-
mission for decision to the National Joint Board. Although
General President Hutcheson could! easily have done so,
neither he nor the United Brotherhow4 of Carpenters at
any time attempted to bring a stop to the’.Stvike and picket-
ing. The picketing ended on August 13, 1979, following the
filing of the lawsuit in this case, and was bought to an
end by the instructions of Carpenters’ General’ Executive
Board member Bull. After the strike and picketing’ ended,
and in October 1970, the dispute over rack and pinion gates
and material handling chutes at the Green Carbon Plant W285
settled by agreement between Carpenters Local 618 repre-
sentative Morris and United Association Local 562 repre-
sentative Steska in a meeting attended by Carpenters’
General Executive Board member Bull, who regularly
attended such meetings in participation with Morris and in
order to advise and assist Morris. The resulting agree-
ment adopted the agreement between the St. Louis District
Council of the United Brotherhood of Carpenters and the
United Association Local 562, and provided that work on
rack and pinion gates and material handling chutes would
be performed by pipefitters and millwrights in exactly the
= way it was performed in the period July 3-July 28,
16. As of July 30, 1970, construction craft manpower,
consisting of the employees of Kaiser, the employees of
Comstock-Roper, and the employees of ten fixed-price sub-
contractors actively at work on the project, was at its peak
of about 1,386, As of this date, with the physical areas of
many of the facilities more than fifty percent complete, con-
struction activities on plant areas critical to first metal and
Noranda’s start-up of production were on schedule for the
first smelting of primary aluminum on January 23, 1971.
Taking into account the twenty-five strike interruptions
which preceded the July 30th strike and the fifty-seven
percent level of productivity of all crafts employed on the
project, the status of construction activities and the sched-
20a
uled manning were timely to the start-up and operation of
174 pots by Noranda on January 23, 1971, and, for these
purposes, Noranda was in the process of training a produc-
tion staff for first operations.
17. When the strike began on July 30th, and through
the date of its discontinuance at the end of the workday on
August 13, 1970, painters, cement masons, carpenters, mill-
wrights, ironworkers, and boilermakers refused to cross the
picket line and perform any work. Following termination
of the strike and picketing on August 13, 1970, the con-
struction work forces were not remobilized and reorganized
to their pre-strike levels until August 27, 1970.
18. Kaiser made a detailed study of the effect of the
strike’s interruption and impact on the construction
schedule and the first metal date of January 23, 1971, which
would have occurred but for the strike interruption of J uly
30th. This study, completed about October 1970, showed
that as a result of the man-hours lost during the period
of the strike and picketing and the remobilization and reor-
ganization following it and the impact of (hose work losses
on schedule, first metal on the basis of the original plan of
174 pots could not be reached until October 1971, a delay
of nine months in Noranda’s start-up.
19. In order to minimize its delay in getting into produc-
tion, Noranda accepted the recommendation of Kaiser to
begin production with 88 pots and without the use of the
planned Green Carbon, Anode Press and Metal Services
Areas.
20. An overtime program implemented following the
July 30-August 13, 1970, strike and picketing succeeding in
limiting the delaying effect of the strike to thirty-three
calendar days for first metal on this modified 88 pot basis
without the Anode Press, Green Carbon and Metal Services
Area.
21. However, by reason of defendants’ wrongful and
2la
illegal conduct in striking and picketing for the objective
of forcing a work assignment, and as a result of such con-
duct, plaintiff suffered injuries in the following amounts:
(a) $13,534.23 incurred and paid in salary and ex-
pense amounts and attorneys’ fees for activities
directed te bringing a stop to the strike and picketing;
(b) $25,147.15 in railway car demurrage, truck de-
tention, warehousing costs, and material rehandling
costs, all as a result of the strike and picketing and the
unavailability of craft labor forces to unload or receive
railway cars and truck trailers;
(c) $693,090.10 in increased overtime premium pay-
ments to work the man-hours lost by the craft construc-
tions employees of Kaiser Engineers, Inc., Comstock-
Roper, and fixed price subcontractors during and as a
result of the strike and in an effort to limit the impact
and effects of the strike and picketing;
(d) $31,752.47 fer the rental and depreciation costs
of construction and office equipment required to be
kept on the job an additional 33 calendar days as a
result of the strike and picketing, which was the last
work interruption on the job;
(e) $57,216.15 in salaried and utilities | overhead
paid to cost-plus-fixed-fee contractors required to be
kept on the job an additional 33 calendar days because
of the strike and picketing, which was the last strike
and picketing or work interruption on the job;
(f) $94,083.44 consisting of $35,566.00 in additional
construction and raw material costs incurred to mini-
mize start-up delay and to limit the impact of the strike
and picketing on production start-up to 33 calendar
days and $58,517.44 in salaried and utility overhead
payments for a trained production staff forced to re-
main idle and non-productive because of the 33 calendar
day delay in start-up caused by the strike and picket-
mg;
22a
The total of these amounts is $914,823.54 and a judgment
will be entered for the plaintiff and against both defendants.
22. Defendants particularly contend that the interna-
tional union should not be held liable for any amount be-
cause they did not call the strike. They also contend that
the damages were partially caused by a three-day strike of
the laborers in July of 1970, that the premium time of
$295,290.00 paid to the electricians was not caused by the
strike. The Court rejects all of these contentions.
23. The plaintiff asks for additional damages of inter-
est on the damages from the time incurred to the date of
judgment; attorneys’ fees on the bringing of this suit in a
reasonable amount; loss of cash flow caused by the strike
over a period of twenty-two years in the sum of $551,574.15.
The Court rejects all of these contentions.
CONCLUSIONS OF LAW
1. The Court has jurisdiction of this cause under section
303 of the Labor Management Relations Act of 1947, as
amended, 29 U.S.C. 187.
2. The plaintiff, Noranda, has standing to bring this law-
suit for injuries to it by reason of violation of section 8(b)
(4)(D) of the Labor Management Relations Act, 29 U.S.C.
158(b)(4)(D).
3. The United Brotherhood of Carpenters and Joiners of
America, AFL-CIO, and the United Brotherhood of Car-
penters and Joiners of America, AFL-CIO, Local No. 618
are labor organizations within the meaning of 29 U.S.C. 152.
4. From the beginning of construction activities by
Kaiser on the Noranda smelter through the completion of
those activities in February 1972, representatives of the
United Brotherhood of Carpenters and Joiners and repre-
sentatives of the United Brotherhood of Carpenters and
Joiners Local 618 acted jointly and in concert with regard
23a
to all matters of work jurisdiction under the collective
bargaining agreement between the United Brotherhood and
Kaiser and the trade autonomy claims of the United
Brotherhood. siuce the International and Local acted in
concert, they are responsible for the conduct not only of
their own agents but of each other’s agents. Vulcan
Materials Co. v. Steelworkers, 430 F.2d 446 (5th Cir. 1970).
5. On July 28, 1970, the assistant to the General Presi-
dent of the United Brotherhood of Carpenters, with full
authority to instruct and require obedience from Carpen-
ters Local 618, threatened Kaiser with trouble on the job if
Kaiser did not remove pipefitter members of the United
Association and United Association Local 562 from work
then being performed on rack and pinion gates and ma-
terial handling chutes on the construction site. At the same
time, the assistant to the General President of the United
Brotherhood of Carpenters, in no uncertain terms, advised
Carpenters Local 618 that if Kaiser did not replace pipe-
fitters with millwright members of the United Brotherhood
of Carpenters and Carpenters Local 618 on the disputed
work, Carpenters Local 618 was authorized to exercise its
prerogative, which included the establishment of a strike
and picket line under the provisions of the Constitution
of the United Brotherhood for job or shop strikes. By thus
provoking and instigating the strike and picketing which be-
gan July 30, 1970, United Brotherhood of Carpenters
through its assistant to the General President, is equally
liable with Carpenters Local 618 for the conduct of this
strike. Longshoremen’s Union v. Juneau Spruce Corp.,
189 F.2d 177 (9th Cir. 1951), aff’d 342 U.S. 237 (1952).
6. The strike and picketing which began July 30th and
lasted through August 13, 1970, was conducted under the
provisions of the Constitution of the United Brotherhood
of Carpenters covering assertions of Carpenters’ trade au-
tonomy and jurisdictional claims and the United Brother-
hood of Carpenters, at no time during the period July 30th
24a
—August 13th, took any of the steps readily available to it
to bring a stop to the strike and picketing. By this silence
and inaction, the United Brotherhood of Carpenters ac-
quiesced in and condoned the activity of Carpenters Local
618 at a time when there was full opportunity to prevent
such activity or bring a halt to its effects. United Brother-
hood of Carpenters is, therefore, liable as a principal actor
along with Carpenters Local 618. Local 984, 1BT v. Humko
Co., 287 F.2d 231 (6th Cir. 1961), cert. denied 366 U.S. 962
(1961).
7. Members of the United Brotherhood of Carpenters who
were not members of Carpenters Local 618 participated in
the strike and picketing activities and during the course of
the strike and picketing United Brotherhood of Carpenters
participated with and encouraged Carpenters Local 618 in
carrying out its strike and picketing activity. The United
Brotherhood, therefore, is liable to the same extent as is
Carpenters Local 618. Carpenters v. C. J. Montag & Sons,
Tnc., 335 F.2d 216 (9th Cir. 1964).
8. As of July 29, 1970, there existed a dispute between the
United Association and its Local 562 dnd the United
Brotherhood of Carpenters and its Local 618 over whether
pipefitter members of the United Association or millwright
members of the United Brotherhood were entitled to per-
form certain work for Kaiser on equipment items known
as rack and pinion gates and dry material chutes. The
United Association and United Association Local 562
claimed certain work on rack and pinion gates and chutes
in piping systems while the United Brotherhood of Carpen-
ters and Carpenters Local 618 claimed all rack and pinion
gates and chutes whether within or without a piping sys-
tem. In order to enforce their claim, the United Brother-
hood of Carpenters and Joiners and Carpenters Local 618,
through their respective officers, agents and stewards, en-
gaged in a strike and picketing from July 30, 1970 through
August 13, 1970, with the objective and purpose of forcing
25a
and requiring Kaiser to assign the work of installing rack
and pinion gates and dry material handling chutes to em-
ployees represented by the United Brotherhood and its
Local 618 rather than to employees working as pipefitter
members of the United Association and its Local 562. This
strike and picketing is an illegal jurisdictional dispute un-
der 29 U.S.C. 158(b)(4)(D) for which compensatory dam-
ages are recoverable under 29 U.S.C. 303. Carpenters v.
C. J. Montag & Sons, Inc., supra.
9. This project was originally scheduled to cost $85,000,-
000.00, but the cost overrun exceeded the scheduled cost by
approximately $22,000,000.00. Most of the overrun was
due to work stoppages and labor inefficiency. The plaintiff
Noranda has shown to a certainty that it sustained dam-
ages by reason of the illegal strike and picketing of the
defendants in violation of the collective bargaining agree-
ment between the United Brotherhood and Kaiser, upon
which agreement the plaintiff specifically relied in author-
izing Kaiser to perform construction activities on its
smelter. The fact that some of the amounts of damages
cannot be ascertained with certainty does not preclude re-
covery as to those amounts since the applicable measure of
' damages in a lawsuit of this kind is that of just and
reasonable approximation. Mason-Rust v. Laborers, Local
42, 435 F.2d 939 (8th Cir. 1970).
Dated this 28th day of December, 1973.
/s/ James H. Merepirn
James H, Meredith
United States District Judge
26a
APPENDIX E
Judgment of the District Court
Judgment
UNITED STATES DISTRICT COURT
EASTERN DISTRICT OF MISSOURI
EASTERN DIVISION
No. 72 C 33 (1)
Noranpa ALuminuy, Ine., Plaintiff,
Vv.
Unirep BrorHERHOOD oF CARPENTERS AND JOINERS OF AMER-
ica, AFL-CIO, ann Unirep BrotHernoop or CaRPEN-
TERS AND Jotners or America, AF'L-CIO, Loca No. 618,
Defendants. |
JUDGMENT
(Filed in U.S. District Court December 25, 1973)
A memorandum dated this day is hereby incorporated in
and made a part of this judgment.
It Is Hereby Ordered, Adjudged, and Decreed that judg-
ment in the amount of $914,823.54 is granted to the plain-
tiff, Noranda Aluminum, Inc., and against both defendants,
United Brotherhood of Carpenters and Joiners of America,
AFL-CIO, and United Brotherhood of Carpenters and Join-
ers of America, AFL-CIO, Local No. 618. Plaintiffs’ costs
are assessed against both defendants.
Dated this 28th day of December, 1973.
/s/ James H. MerepitH
United States District Judge
27a
APPENDIX F
Statute and Rule Involved
Sections 8(b)(4)(D) and 303 of the Labor-Management
Relations Act of 1947, as amended, 61 Stat. 136, 73 Stat.
519, 29 U.S.C. §158(b)(4)(D) and § 187, provides as
follows:
§8(b) It shall be an unfair labor practice for a
labor organization or its agents * * *
(4)(i) to engage in, or induce or encourage any
individual employed by any person engaged in com-
merce or in an industry affecting commerce to en-
gage in, a strike or a refusal in the course of his
employment to use, manufacture, process, transport,
or otherwise, handle or work on any goods, articles,
materials, or commodities or to perform any serv-
ices; or (ii) to threaten, coerce, or restrain any
person engaged in commerce or in an industry af-
fecting commerce, where in either case an object
thereof is— * * *
(D) foreing or requiring any employer to assign
particular work to employees in a particular labor
organization or in a particular trade, craft, or class
rather than to employees in another labor organiza-
tion or in another trade, craft, or class, unless such
employer is failing to conform to an order or certifi-
cation of the Board determining the bargaining repre-
sentative for employees performing such work: * * *
§ 303:
(a) It shall be unlawful, for the purpose of this
section only, in an industry or activity affecting com-
merce, for any labor organization to engage in any
activity or conduct defined as an unfair labor practice
in section 8(b)(4) of this Act.
28a
(b) Whoever shall be injured in his business or
property by reason of any violation of subsection (a)
of this section may sue therefor in any district court
of the United States subject to the limitations and pro-
visions of section 391 of this Act without respect to
the amount in controversy, or in any other court hav-
ing jurisdiction of the parties, and shall recover the
damages by hii sustained and the cost of the suit.
Rule 52(a) of the Federal Rules of Civil Procedure
provides as follows:
52(a) Errecr. In all actions tried upon the facts
without a jury or with an advisory jury, the court
shall find the facts specially and state separately its
conclusions of law thereon * * * Requests for findings
are not necessary for purposes of review. Findings
of fact shall not be set aside unless clearly erroneous,
and due regard shall be given to the opportunity of
the trial court to judge the credibility of the witnesses.
* * * Tf an opinion or memorandum of decision is
filed, it will be sufficient if the findings of the fact and
conclusions of law appear therein. * * *
This is a copy of a public record, reproduced as it was published. It is not legal advice, and it may not be the version a court would rely on. Check the official source before you cite it.