Petition for Writ of Certiorari — Sheffield Korte Joint Venture, Petitioner v. Daniel P. Driscoll, Secretary of the Army
Supreme Court briefNov 5, 2025
Ask Donna
What actually matters in this document.
Text
No. ___________
.
In the Supreme Court of the United States
__________________
SHEFFIELD KORTE JOINT VENTURE,
Petitioner,
v.
SECRETARY OF THE ARMY,
Respondent.
___________________________________________
ON PETITION FOR WRIT OF CERTIORARI
TO THE UNITED STATES COURT OF APPEALS
FOR THE FEDERAL CIRCUIT
___________________________________________
APPENDIX
___________________________________________
Michael E. Wilson, Esq.
Counsel of Record
UB GREENSFELDER LLP
10 S Broadway Ste 2000
St. Louis, MO 63102
mwilson@ubglaw.com
(314) 516-2680
Counsel for Petitioner
Fifth day of November, MMXXV
United States Commercial Printing Company • www.uscpc.us • (202) 866-8558
App-i
APPENDIX
TABLE OF CONTENTS
Appendix A
Judgment
[summary
judgment
affirmed], United States Court of
Appeals for the Federal Circuit,
Sheffield Korte Joint Venture v.
Secretary of the Army,
No. 2024-1134 (May 22, 2025) ................... App-1
Appendix B
Opinion [summary judgment affirmed],
United States Court of Appeals for the
Federal Circuit, Sheffield Korte Joint
Venture v. Secretary of the Army,
No. 2024-1134 (May 22, 2025) ................... App-3
Appendix C
Order [rehearing denied], United States
Court of Appeals for the Federal Circuit,
Sheffield Korte Joint Venture v.
Secretary of the Army,
No. 2024-1134 (Aug. 7, 2025) .................. App-10
Appendix D
Armed Services Board of Contract
Appeals, Appeals of Sheffield Korte
App-ii
Joint Venture, Under Contract No.
W912QR-15-C-0027,
Nos. 62972, 62973 (Aug. 11, 2023) .......... App-12
Appendix E
Appx 1511 - Drawing C-101
(May 13, 2014) ……………………………. App-53
Appendix F
Appx 1831 - Specification Excerpt
(May 13, 2014) ……………………………. App-54
Appendix G
Appx 1835 - Specification Excerpt
(May 13, 2014) ……………………………. App-57
Appendix H
Appx 2107 - Specification Excerpt
(May 13, 2014) ……………………………. App-60
Appendix I
Appx 1939 - Specification Excerpt
(May 13, 2014) ……………………………. App-61
App-1
Appendix A
[Filed: May 22, 2025]
United States Court of Appeals
for the Federal Circuit
___________________
SHEFFIELD KORTE JOINT VENTURE,
Appellant
v.
SECRETARY OF THE ARMY,
Appellee
___________________
2024-1134
___________________
Appeal from the Armed Services Board of
Contract
Appeals
in
Nos.
62972,
62973,
Administrative
Judge
Richard
Shackleford,
Administrative Judge Stephanie Cates-Harman,
Administrative Judge J. Reid Prouty.
___________________
JUDGMENT
___________________
THIS CAUSE having been considered, it is
ORDERED AND ADJUDGED:
AFFIRMED
App-2
FOR THE COURT
May 22, 2025
Date
Jarrett B. Perlow
Clerk of Court
App-3
Appendix B
[Filed: May 22, 2025]
NOTE: This disposition is nonprecedential.
United States Court of Appeals
for the Federal Circuit
_____________________
SHEFFIELD KORTE JOINT VENTURE,
Appellant
v.
SECRETARY OF THE ARMY,
Appellee
_____________________
2024-1134
_____________________
Appeal from the Armed Services Board of
Contract
Appeals
in
Nos.
62972,
62973,
Administrative Judge J. Reid Prouty, Administrative
Judge Richard Shackleford, Administrative Judge
Stephanie Cates-Harman.
_____________________
Decided: May 22, 2025
_____________________
MICHAEL WILSON, UB Greensfelder, LLP,
Saint Louis, MO, argued for appellant.
App-4
BRYAN MICHAEL BYRD, Commercial Litigation
Branch, Civil Division, United States Department of
Justice, Washington, DC, argued for appellee. Also
represented by BRIAN M. BOYNTON, STEVEN JOHN
GILLINGHAM, PATRICIA M. MCCARTHY.
_____________________
Before MOORE, Chief Judge, CHEN and CUNNINGHAM,
Circuit Judges.
MOORE, Chief Judge.
Sheffield Korte Joint Venture (Sheffield)
appeals from a summary judgment decision of the
Armed Services Board of Contract Appeals (Board),
which denied Sheffield’s request for an equitable
adjustment and granted the U.S. Army Corps of
Engineers’ (Corps) request for repayment of
improperly issued funds. We affirm.
BACKGROUND
The Corps solicited bids for a fixed-price
design-build contract to construct an Army Reserve
Center in Charles County, Maryland. J.A 2 ¶¶ 1–2.
The solicitation documents contained a specification
describing general project requirements and
conceptual drawings depicting major features of the
project. J.A. 1825–59 (specification); J.A. 1441
(drawing). One major feature was a stormwater
management system. J.A. 1441 (denoted by keynote
30).
App-5
Sheffield submitted a bid for the project that
included a design for a centralized 1 stormwater
management system. See J.A. 3278–81. In August
2015, the Corps accepted the bid and awarded
Sheffield the contract for $21,427,802. J.A. 2 ¶¶ 1–2.
In September 2016, Sheffield sent the Corps a letter
explaining the stormwater management system
depicted in the solicitation documents differed from
that required by the State of Maryland. J.A. 3278–81.
Sheffield noted the conceptual drawings included a
centralized system but that local requirements
mandated a decentralized system. Id. The Corps
disagreed that the requirements in the solicitation
documents differed from those imposed by local
officials. J.A. 3282.
In April 2017, Sheffield submitted a request
for an equitable adjustment of $1.8 million based on
changes to the stormwater management system. J.A.
3292–301. The Corps denied Sheffield’s request. J.A.
3370–71 (non-final decision). The Corps did, however,
issue a series of unilateral contract modifications
increasing the contract price by $418,406 to
compensate Sheffield for expenses incurred in
meeting local requirements. J.A. 7–14 ¶¶ 22–43.
In November 2020, Sheffield certified its
request for an equitable adjustment. J.A. 3402. In
April 2021, the Corps denied Sheffield’s request and
A centralized system collects stormwater in a single feature
like a pond, whereas a decentralized system uses multiple,
small-scale features to control stormwater and is intended to
replicate natural hydrology. J.A. 3294–95.
1
App-6
asked Sheffield to repay the $418,406, which the
Corps claimed was issued in error. J.A. 3403–37
(final decision). Sheffield appealed to the Board. On
summary judgment, the Board denied Sheffield’s
request for an equitable adjustment and ordered it to
repay the Corps. J.A 16–21 (citing United States v.
Spearin, 248 U.S. 132 (1918)). Central to the Board’s
analysis was its conclusion the Spearin implied
warranty does not apply to the contract between
Sheffield and the Corps. Sheffield appeals. We have
jurisdiction pursuant to 41 U.S.C. § 7107(a)(1)(A)
and 28 U.S.C. § 1295(a)(10).
DISCUSSION
We review the Board’s legal conclusions de
novo. Kellogg Brown & Root Servs., Inc. v. Sec’y of the
Army, 973 F.3d 1366, 1370 (Fed. Cir. 2020). The
Board’s decision to grant or deny summary judgment
is a legal conclusion. Cessna Aircraft Co. v. Dalton,
126 F.3d 1442, 1446 (Fed. Cir. 1997). So too is its
interpretation of contracts, Triple Canopy, Inc. v.
Sec’y of the Air Force, 14 F.4th 1332, 1338 (Fed. Cir.
2021), including deciding whether the Spearin
implied warranty applies, Blake Const. Co. v. United
States, 987 F.2d 743, 746 (Fed. Cir. 1993).
When the government provides a contractor
with a defective design specification, the government
is deemed to have breached the Spearin implied
warranty that satisfactory contract performance will
result from adherence to the specification. Rick’s
Mushroom Serv., Inc. v. United States, 521 F.3d 1338,
1344–45 (Fed. Cir. 2008); see also Spearin, 248 U.S.
App-7
at 135–36. Such a breach entitles the contractor to
recover all costs proximately flowing from the breach.
Rick’s, 521 F.3d at 1344–45. The Spearin implied
warranty, however, does not attach to performance
specifications. Id. at 1344. Unlike design
specifications, which “explicitly state how the
contract is to be performed and permit no
deviations,” performance specifications “specify the
results to be obtained, and leave it to the contractor
to determine how to achieve those results.”
Stuyvesant Dredging Co. v. United States, 834 F.2d
1576, 1582 (Fed. Cir. 1987). A key factor in
distinguishing a design specification from a
performance specification is the amount of discretion
given to the contractor in implementation. Blake, 987
F.2d at 746–47.
Sheffield argues the Board legally erred by
concluding the Spearin implied warranty does not
apply to its contract with the Corps. Appellant Br.
39–75. Specifically, Sheffield argues the solicitation
documents (i.e., the specification and conceptual
drawings)
show
a
centralized
stormwater
management system is a design requirement to
which the Spearin implied warranty applies. We do
not agree.
While the conceptual drawings depict a
“stormwater management facility” in the northern
portion of the site, they do not specify the type of
stormwater management system. J.A. 1441; J.A.
1511. The drawings do, however, state the
stormwater management system depicted is only an
approximation, and the contractor is responsible for
App-8
determining the “actual size and location” of the
system. J.A. 1441 (keynote 30); J.A. 1511 (keynote
30). Regardless, even if these drawings appear to
depict a centralized system, the specification makes
clear it is not a design requirement.
The specification shows Sheffield was required
to design the stormwater management system in
accordance with local requirements, was responsible
for obtaining all necessary permits, and had
discretion to refine the conceptual design accordingly.
See, e.g., J.A. 1831 §§ 1.2.4.2–3, 1833 § 1.3.1, 1852 §
3.1.8.2 The specification also provides that federal,
state, and local regulations are “considered the
minimum design criteria” for designing “stormwater
management systems” and that “[l]ow impact
development strategies” can be used to restore “the
natural hydrologic functions of a site.” J.A. 1859 §
3.4.5. Moreover, the specification incorporates the
2010 Maryland Stormwater Management Guidelines,
J.A. 1843 § 2.2.1, which explain environmental site
design3 for stormwater management is required to
the “maximum extent practicable,” J.A. 747–62.
Because Sheffield had significant discretion to design
and build the stormwater management system in
accordance with local regulations and the
The contract between the parties also includes a “permits and
responsibilities” clause that makes Sheffield “responsible for
obtaining any necessary licenses and permits, and for
complying with any Federal, State, and municipal laws, codes,
and regulations applicable to the performance of the work.” J.A.
1692.
3 Environmental site design is a design for decentralized
stormwater management systems. J.A. 754 ¶ 14; J.A. 3278–81.
2
App-9
specification did not require a centralized
stormwater management system, this is a
performance specification to which the Spearin
implied warranty does not apply. Stuyvesant, 834
F.2d at 1582.
CONCLUSION
We have considered Sheffield’s remaining
arguments and find them without merit. For the
foregoing reasons, we affirm.
AFFIRMED
App-10
Appendix C
[Filed: Aug. 7, 2025]
NOTE: This order is nonprecedential.
United States Court of Appeals
for the Federal Circuit
___________________
SHEFFIELD KORTE JOINT VENTURE,
Appellant
v.
SECRETARY OF THE ARMY,
Appellee
___________________
2024-1134
___________________
Appeal from the Armed Services Board of
Contract
Appeals
in
Nos.
62972,
62973,
Administrative Judge J. Reid Prouty, Administrative
Judge Richard Shackleford, Administrative Judge
Stephanie Cates-Harman.
___________________
ON PETITION FOR PANEL REHEARING AND
REHEARING EN BANC
___________________
App-11
Before MOORE, Chief Judge, LOURIE, DYK, PROST,
REYNA, TARANTO, CHEN, HUGHES, STOLL,
CUNNINGHAM, and STARK, Circuit Judges.1
PER CURIAM.
ORDER
Sheffield Korte Joint Venture filed a combined
petition for panel rehearing and rehearing en banc.
The petition was referred to the panel that heard the
appeal, and thereafter the petition for rehearing en
banc was referred to the circuit judges who are in
regular active service.
Upon consideration thereof,
IT IS ORDERED THAT:
The petition for panel rehearing is denied.
The petition for rehearing en banc is denied.
FOR THE COURT
August 7, 2025
Date
1
Jarrett B. Perlow
Clerk of Court
Circuit Judge Newman did not participate.
App-12
Appendix D
[Filed: Aug. 11, 2023]
ARMED SERVICES BOARD OF CONTRACT
APPEALS
Appeals of –
Sheffield Korte Joint Venture
Under Contract No. W912QR15-C-0027
)
)
) ASBCA
) Nos. 62972, 62973
)
)
APPEARANCE FOR
THE APPELLANT:
Michael E. Wilson, Esq.
Greensfelder, Hemker &
Gale, P.C.
St. Louis, MO
APPEARANCES FOR
THE GOVERNMENT:
Michael P. Goodman, Esq.
Engineer Chief Trial
Attorney
R. Lauren Horner, Esq.
James M. Inman, Esq.
Engineer Trial
Attorneys
U.S. Army Engineer
District, Louisville
OPINION BY ADMINISTRATIVE JUDGE CATESHARMAN ON THE GOVERNMENT’S MOTION
FOR SUMMARY JUDGMENT AND APPELLANT’S
CROSS-MOTION FOR PARTIAL SUMMARY
JUDGMENT
App-13
These appeals involve a contract for design
and construction of a new 600-member Army
Reserve Center near Waldorf, Charles County,
Maryland. Sheffield Korte Joint Venture (SKJV)
seeks additional compensation from the United
States Army Corps of Engineers (USACE) to meet
permitting requirements imposed on this project.
SKJV also appeals the contracting officer’s (CO)
decision to rescind a series of five unilateral
modifications issued by USACE providing additional
compensation to SKJV for difficulties it encountered
in obtaining sewer, water, and access permits from
Charles County and the Maryland State Highway
Administration (MDSHA).
USACE moves for summary judgment on the
grounds that Federal Acquisition Regulation (FAR)
52.236-7, PERMITS AND RESPONSIBILITIES
(NOV 1991) and other contract provisions required
SKJV to obtain licenses and permits necessary for
project completion without additional expense to the
government. USACE also seeks summary judgment
of its affirmative claim for recoupment of the
amounts paid under the unilateral modifications.
SKJV moves for partial summary judgment on the
grounds that USACE constructively changed the
contract by providing defective specifications and by
misrepresenting the project’s requirements. SKJV
also challenges the credit sought by the government
in the amount of $418,406 arguing that there was
accord and satisfaction between SKJV and USACE
regarding the five unilateral modifications. USACE
responds that there was no accord and satisfaction
App-14
regarding the five unilateral modifications as
appellant contends. For the reasons identified below,
we grant USACE’s motion and deny SKJV’s motion.
STATEMENT OF FACTS (SOF) FOR THE
PURPOSE OF THE MOTIONS
1. On August 28, 2015, USACE awarded
Contract No. W912QR-15-C-0027 to SKJV for
“Design and Construction of a New 600-Member
Bowie Army Reserve Center Project located near
Waldorf, Charles County, Maryland” (R4, tab 11A at
720, 722;1 tab 11B at 733).
2. The total contract price was $21,427,802,
including base work and all exercised options at time
of award (R4, tab 11A at 720; tab 11B at 734).
3. The as-awarded project also included design
and construction of an organizational maintenance
shop, an unheated storage building, and military
equipment parking (R4, tab 11B at 739-41).
4. The contract’s statement of work (SOW)
included specification Part 1, entitled “Design
Objectives, and Functional and Area Requirements”
(R4, tab 11C at 1017). Section 1.1.2 of Part 1
provided: “This project shall consist of the design and
construction of an Army Reserve Center complete
with
required
utilities,
storm
drainage,
communications,
electric,
HVAC,
fire
The government R4 page numbers begin with “GovR4-000”
and are omitted here.
1
App-15
protection/alarm systems, IDS, force protection
measures, paving, walks, curbs, parking, access
roads, exterior lighting, site improvements, grading
and landscaping on Government-owned land” (id.).
5. Section 1.2.4 of Part 1, “Design Freedom,”
provided:
Requirements stated in this RFP
are
minimums.
Innovative,
creative, or cost-saving proposals,
which meet or exceed these
requirements are encouraged, and
will be considered more favorably.
....
1.2.4.2 The conceptual design
Drawings, this Statement of
Work, and the Outline Technical
Specifications, along with the
other
information
and
requirements in this RFP, serve
as requirements for Contractor
building design and construction
completion, along with other code,
regulatory
and
professional
practice requirements. The extent
of development of these RFP
documents in no way relieves the
successful
offeror
from
responsibility for completing the
design,
construction
documentation, and construction
App-16
of
the facility in conformance with
Applicable Criteria and codes.
1.2.4.3 The conceptual design
illustrates
desired
general
arrangements, orientation, and
adjacencies,
and
provides
examples of exterior images which
is acceptable to the Government –
it is not intended to dictate the
final layout and image for the
project.
The
Contractor’s
designers shall develop and refine
the conceptual site and building
design in their completion of the
design
and
construction
documents. Such development
shall be consistent with the
criteria and acceptable to the
Government.
(R4, tab 11C at 1018) (emphasis added)
6. Section
1.3
of
Part
1,
“Contractor
Responsibility,” provided: “The Contractor shall
provide all labor, materials, equipment, supplies,
permits, fees, and consultant services to design and
construct this Training Center complex” (R4, tab 11C
at 1020) (emphasis added).
7. Section 1.7 of Part 1, “Site,” provided, in part:
App-17
Site work includes all design and
construction of site features
necessary to meet the intent of
the RFP, including but not
limited
to,
site
planning,
demolition, clearing, grading,
erosion control, site drainage,
utility
systems,
pavements,
pedestrian
and
vehicular
circulation systems, signage, site
lighting, landscaping, physical
security
measures,
fencing,
permitting, and site furnishings.
(R4, tab 11C at 1023) (emphasis added)
8. Section 1.7.8 of
Compliance,” provided:
Part
1,
“Regulatory
The Contractor shall assure that
the site development complies
with all applicable local, State
and Federal regulations. A list of
known regulations is located in
the
Attachments
to
this
Statement of Work. Timely
acquisition of the necessary
design and construction related
permits shall be the responsibility
of the Contractor. The Contractor,
upon notice to proceed, shall
immediately begin working on
the permits so as not to delay
completion of the project. The
App-18
Contractor shall prepare permits,
associated
drawings,
public
notices,
and
other
related
documentation as necessary to
successfully meet permit approval
status. The Contractor shall pay
for associated permit fees.
(R4, tab 11C at 1026) (emphasis added)
9. The SOW included specification Part 2,
entitled “Applicable Criteria and Coordination With
Local Authorities” (R4, tab 11C at 1029). Section 2.2,
“Local and State Codes or Standards,” provided:
The
following
specifications,
codes, standards, bulletins and
handbooks form a part of this
RFP.
2.2.1 State and Local
Maryland State Highway
Administration - Standard
Specifications for Construction
and Materials
Maryland State Highway
Administration – State Highway
Access Manual Engineering
Access Permits Division
January 2004
Maryland State Highway
Administration – Highway
Drainage Manual
App-19
Maryland Department of the
Environment - 2011
Maryland Standards and
Specifications for Soil Erosion
and Sediment Control
Maryland Department of the
Environment – 2000
Maryland Stormwater Design
Manual
Maryland Department of the
Environment - Erosion and
Sediment Control Guidelines
Maryland Department of the
Environment - Stormwater
Management Guidelines for State
and Federal Projects, April 15,
2010
Maryland Forest Conservation
Act
Charles County Department of
Planning and Growth
Management – Water and Sewer
Ordinance, September 2011 or
current edition
Charles County Department of
Planning and Growth
Management – Plan Preparation
Package, June 2012 or current
edition
(Id. at 1030-31)
10. Section 2.6 of Part 2, “Permits and
Coordination With Local Authorities,” provided:
App-20
The Contractor is responsible for
making all applications and
obtaining required municipal,
utility, and regulatory agency
coordination, reviews, permits,
inspections and approvals, and is
responsible for payment of any
associated fees or charges. If
Government
information,
signatures, names or addresses
are required for applications,
approvals
or
permits,
the
Contractor is responsible for
obtaining same. This is a Federal
Government project; therefore,
some
reviews,
permits,
inspections and approvals are not
required. The Contractor is
responsible for identifying such
requirements for a commercial
project and verifying with the
Government which of these will
be waived. Permit requirements
which have been identified are
listed below. This list is not allinclusive, and Contractor is
responsible for verifying that
information
below
remains
accurate.
(Id. at 1037) (emphasis added)
App-21
11. The contract incorporated FAR 52.236-7,
PERMITS AND RESPONSIBILITIES (NOV 1991)
(the Permits and Responsibilities Clause), which
provided:
The Contractor shall, without
additional
expense
to
the
Government, be responsible for
obtaining any necessary licenses
and permits, and for complying
with any Federal, State, and
municipal laws, codes, and
regulations applicable to the
performance of the work. The
Contractor
shall
also
be
responsible for all damages to
persons or property that occur as
a result of the Contractor's fault
or negligence. The Contractor
shall also be responsible for all
materials delivered and work
performed until completion and
acceptance of the entire work,
except for any completed unit of
work which may have been
accepted under the contract.
(R4, tab 11B at 879) (emphasis added)
12. The project was located in Charles County,
Maryland (R4, tab 11B at 733), at the corner of an
access road called Fox Tail Place and a state highway
App-22
called Marshall Corner Road (R4, tab 11E at 2434;
JSUMF2 ¶6).
13. MDE is the State of Maryland governmental
authority that exercises jurisdiction over stormwater
management (JSUMF ¶ 7; see also gov’t mot. ¶¶ 3,
41).
14. MDSHA is the State of Maryland
government authority that exercises jurisdiction over
state highways (JSUMF ¶ 8; see also gov’t mot. ¶¶ 5,
41).
15. Charles County is the State of Maryland
authority that exercises jurisdiction over sewer and
water line access within Charles County (JSUMF ¶ 9;
see also gov’t mot. ¶¶ 4, 41).
16. Michael Baker International (formerly
known as Michael Baker, Jr., Inc.) is an architectural
and engineering firm retained by USACE that
participated in developing the project’s request for
proposal (RFP), including the preparation of
conceptual drawings (R4, tab 6; Higgins dep. at 38-39;
JSUMF ¶ 10).
17. Frankford Short Bruza Associates, P.C.
(FSB), the designer of record hired by SKJV, was
responsible for overall design of the project. Mott
McDonald is a civil engineering firm retained by FSB
The parties provided a Joint Stipulation of Undisputed
Material Facts (JSUMF) for the purposes of the motions.
2
App-23
responsible for the civil engineering portion of the
project’s design. (JSUMF ¶ 11; see also app. mot. ¶ 2)
18. USACE issued its notice to proceed on
October 7, 2015 (R4, tab 12).
19. Between June 27, 2016 and May 17, 2017,
SKJV and its design subcontractors engaged in
several rounds of submission to the MDE involving
changes and additions to design drawings and review
and comment by the MDE. MDE granted the early
mass
grading,
demolition,
and
foundation
construction permit, effective August 1, 2016. (R4,
tabs 13-15, 18-21, 24; JSUMF ¶ 20)
20. SKJV sent a letter dated September 22, 2016
to USACE identified as a “Request for Change on
Behalf of FSB/Mott MacDonald” (R4, tab 16 at 2464).
Attached to this letter was another letter, dated
September 20, 2016, from Mott MacDonald with the
subject, “Bowie ARC Stormwater Management Basis
of Bid Versus Design” (id. at 2465-68). This letter
purported that the requirements imposed by MDE
differed from the RFP’s requirements for the project
(id.).
21. By letter dated October 13, 2016, USACE
informed SKJV that it disagreed with SKJV’s
contention that the requirements imposed by MDE
differed from those in the RFP (R4, tab 17).
22. On or before January 19, 2017, the Charles
County Department of Planning and Growth
Management informed SKJV that a development
App-24
services permit and a separate stormwater permit
from Charles County would also be required for the
work relating to the Fox Tail Place access road. The
requirement to obtain these permits was not listed in
the permit matrix found in the contract documents.
(JSUMF ¶ 31; see also R4, tab 11C at 1631)
23. The parties stipulate that Charles County
and MDSHA required changes to SKJV’s assubmitted design in furtherance of obtaining
relevant permits (JSUMF ¶ 30).
24. On January 19, 2017, USACE issued and
approved a Basic Change Document for the Charles
County and MDSHA required changes to SKJV’s assubmitted design, identified as Mod Serial No. AA-1.
This document authorized $20,000 to be paid to
SKJV for additional Charles County-required design
work:
1) Prepare and submit required design
documents to Charles County for the
VSS plans (VSS-160028) for the Access
Road area not on Government Parcel.
2) Prepare and submit required design
documents to Charles County for the
application of Development Services
Permit for the Access Road Area not on
Government Parcel.
3) Complete a design that separates the
access road storm features from the
Government Parcel.
App-25
(App. mot., ex. A)
25. In March 2017, USACE issued a Price
Negotiation Memorandum denoted as “Case AA-1 –
Charles County Requirements.” This memorandum
provided in part:
1. Necessity for Change: The
Design-Build RFP requires the
contractor to pay permit fees to
Charles County to obtain the
necessary permits for conduct
earthwork activities for Erosion and
Sediment
control.
During
the
permitting process, the Department
of
Planning
and
Growth
Management of Charles County, MD
confirmed that in order to obtain the
necessary erosion and sediment
control permit, a design that
separates the storm water features
from the existing access road and the
project site must be included in the
permit application. Adding this
design requirement in order to
obtain the permit for Charles County
will require a change to the contract.
2. [ ] The RFP does not include the
requirement
for
providing
an
approved design with the permit
application.
App-26
(App. mot., ex. B)
26. By letter dated April 12, 2017, SKJV filed a
request for equitable adjustment seeking $1,800,000,
as a result of alleged changed conditions associated
with its attempts to obtain state permits, increasing
the cost of site design and construction costs of the
project. (R4, tab 21 at 2479-88).
27. On April 18, 2017, USACE issued Unilateral
Modification No. A00002 to the contract for Change
Case AA (Charles County requirements), identical to
the scope described in Basic Change Document AA-1
on January 19, 2017. This modification authorized
expenditures not to exceed $20,000, thereby
increasing the contract’s price by $20,000.
Modification No. A00002 was designated Part 1 of
Change Case AA and granted no additional time. (R4,
tab 22; app. mot., ex. B)
28. By letter dated May 9, 2017, SKJV informed
USACE that delays in the permitting process were
causing SKJV to incur a “rough order of magnitude
of construction costs” in the amount of $773,700,
excluding “permit work” (R4, tab 23).
29. By letter dated May 17, 2017, MDE advised
USACE that it had approved the final stormwater
management and sediment control plans (R4, tab 24).
By letter dated June 2, 2017, MDE advised USACE
that it had approved the sequence of construction
and the erosion and sediment controls (R4, tab 25).
App-27
30. On or about September 22, 2017, USACE
issued a Basic Change Document identified as Mod
Serial No. AA-2. This document authorized an
additional $30,000 to be paid to SKJV for additional
Charles County-required design work involving the
same three categories as Mod Serial No. AA-1:
1) Prepare and submit required design
documents to Charles County for the
VSS plans (VSS-160028) for the Access
Road area not on Government Parcel.
2) Prepare and submit required design
documents to Charles County for the
application of Development Services
Permit for the Access Road Area not on
Government Parcel.
3) Complete a design that separates the
access road storm features from the
Government Parcel.
(App. mot., ex. F)
31. On November 14, 2017, USACE issued
Unilateral Modification No. A00005 to the contract
supplementing the amounts previously added for
Change Case AA (Charles County requirements).
The modification authorized expenditures not to
exceed $30,000, thereby providing a total maximum
increase of $50,000 in amounts obligated relating to
Change Case AA. Modification No. A00005 was
designated Part 2 of Change Case AA and granted no
additional time. (R4, tab 26)
App-28
32. On November 14, 2017, Ms. Jane Kiefer, a
USACE regional construction project manager, and
Mr. Hans Probst, a USACE administrative
contracting officer, signed a Price Negotiation
Memorandum dated October 17, 2017. Part 1 of the
memorandum, “Necessity for Change,” stated:
While
the
contractor’s
designer
continued with design requirements for
Charles County permit, their cost has
increased significantly. Therefore a
supplement to the Part 1 NTP
modification of the same title is
necessary.
Part 3, “Price Negotiation Memorandum,” stated:
It is anticipated that the final
price agreement will be reached
within 60 days of comment
resolution from Charles County.
The contractor has stated that
the
designer
has
already
expended more than $30k for the
design work and Charles County
comments have increased design
effort even more. Once a
negotiated settlement has been
reached,
a
Part
2
Final
modification will be executed
with appropriate time extension.
App-29
Part 4, “Justification for Unpriced Notice to Proceed,”
stated:
On 7 February 2017, the contractor’s
[project manager] notified USACE
during the weekly telephone conference
that an additional design stormwater
design was required by Charles County,
MD in order to obtain the required
stormwater management permit.
(App. mot., ex. G)
33. By letter dated December 15, 2017, USACE
denied SKJV’s April 12, 2017 REA (R4, tab 27).
34. By letter dated January 26, 2018, USACE
addressed SKJV’s stated position that it was entitled
to additional compensation for difficulties meeting
Charles County’s permitting requirements. The
letter denied six of SKJV’s eight grievances but
found merit with respect to the other two issues—
design work due to a discrepancy between MDE’s
and Charles County’s requirements for the type of
inlets for drain storage and additional costs relating
to polymer concrete to be used for transition
manholes. The amount of these additional costs was
not stated. (R4, tab 28)
35. On or about February 13, 2018, USACE
issued a Basic Change Document identified as Mod
Serial No. AA-3. Seven items were added in the Basic
Change Document under “Necessity for Change”:
App-30
1. Type K Inlets
This is a Charles County storm
water requirement. The design of
the storm water on Charles
County property was not included
in the contract.
2. Polymer Concrete Manhole
Charles [C]ounty has made this
request and the Government has
agreed to provide. Charles
[C]ounty
storm
water
requirements were not in the
contract.
3. Fire Hydrants
The contract was required to
meet
the
Charles
County
requirements which is fire
hydrants every 300 feet, but the
RFP drawings show fire hydrants
spaced every 400 feet.
4. Entrance Road Turn Around
Charles County is requiring a
turn around at the end of the
entrance road that was not
identified in the NTP.
5. State Highway Authority –
Increase Entrance Radius
The State Highway Authority has
requested that the radius of the
entrance road be increased for
App-31
safety reasons. This should have
been coordinated with the SHA
during preparation of the RFP.
6. Wash Rack Enclosure
Charles County is requiring the
contractor to enclose the north
side of the wash rack. This
requirement was unknown at the
time of RFP preparation.
[7.] Additional Permit Fees
The permit fees have increased
since time of award.
(App. mot., ex. H)
36. On February 15, 2018, USACE issued
Unilateral Modification No. A00009 to the contract
supplementing the amounts previously added for
Change Case AA (Charles County requirements) not
to exceed $75,000. This modification was designated
Part 3 of Change Case AA and granted no additional
time. (R4, tab 29)
37. By letter dated March 1, 2018, USACE
requested that SKJV provide pricing and
justification for the seven items identified in
Modification No. A00009. The letter also reiterated
that the not-to-exceed price of the modifications at
that time was $75,000. (R4, tab 30)
38. SKJV responded by email dated May 2, 2018.
This email included several attachments, including
App-32
information about the dollar amounts SKJV sought
for each of the seven items. SKJV requested
$739,614.78 in total. The email also noted that
“Subcontractors/Vendors are going thru our contract
for compensation from the USACE. I do not believe
this should be included in the above items but if you
would like us to include please let me know (should
be roughly one month now to accumulate these
costs).” (App. mot., ex. I)
39. On June 27, 2018, USACE issued a Price
Negotiation Memorandum identified as “Case No.
AA-4 ‘Charles County Requirements’, Part 1,
Supplement 3.” Part 1, “Necessity for Change,” read:
This is an in scope modification
due to a design omission. Section
01 02 00.00 48 Paragraph 3.1.8 in
the Design-Build RFP required
the DB contractor to pay fees to
obtain the earthwork permit for
Charles County. The DB RFP did
not include a requirement to
provide a design to Charles
County during the permitting
process that separates the storm
water features of the existing
access road from the project site.
Without this design, Charles
County will not issue permits
required to start construction on
the access road and site work. In
order to include this design in the
App-33
permit submission, a modification
to the contract is required.
Part 1 Supplement 3 – While the
contractor’s designer continued
with design requirements for
Charles County permit, their cost
has
increased
significantly.
Charles County has identified
additional requirements to meet
their storm water ordnance.
Therefore
an
additional
supplement to the Part 1 NTP
modification of the same title is
necessary.
This project is located in Charles
County, MD. A storm water
management fee was established
in April 2012, affecting nine
counties and the City of
Baltimore in order to meet the
requirements of the federal Clean
Water Act as it concerns the
Chesapeake Bay watershed. The
law was passed in response to a
decree by the Environmental
Protection
Agency
and
aggressively sought to reduce
sediment
loading
to
the
Chesapeake Bay. The contract, as
issued, failed to incorporate these
stringent
permitting
requirements.
App-34
(App. mot., ex. J at 1) The memorandum continues:
A not to exceed price in the
amount
of
$20,000
was
established in the Part 1 NTP; an
additional
$30,000
was
established
in
Part
1,
Supplement 1; an additional
$75,000 was established in Part 1,
Supplement 2; and an additional
$224,814.063 is being established
by Part 1, Supplement 3. The
Government
has
already
recognized $418,406 of validated
costs associated with this change.
(Id. at 2)
40. On June 28, 2018, USACE issued Unilateral
Modification No. A00011 to the contract increasing
the total not-to-exceed price to a lump sum amount of
$224,814. The aggregate obligated amount under
Change Case AA (Charles County requirements) was
increased to $349,814. The modification was issued
“for the purpose of making interim payment to the
Contractor pending negotiation and issuance of the
final adjustment modification.” Modification No.
A00011 was designated Part 4 of Change Case AA
A note below the paragraph clarified the strikethrough: “The
amount of $224,814.06 is hereby corrected to read ‘$224,814.00’”
(app. mot., ex. J at 2).
3
App-35
and granted no time extension. (R4, tab 31; JSUMF
¶ 46)
41. On or about July 25, 2018, USACE executed
a Price Negotiation Memorandum identifying the
“Change Request Number and Title” as “Change AA4 – REA for Charles County Requirements” (R4, tab
31A). This memorandum listed the same seven items
previously identified in Mod Serial No. AA-3 and
conceded liability for them. According to the
memorandum, price negotiations took place between
February 11, 2018 and July 16, 2018, but SKJV and
USACE failed to agree to a proposed price change.
(Id. at 2572-74) By June 2018, USACE had
determined that SKJV had support for $293,496
relating to Change AA. The memorandum stated
that the balance that USACE determined was
supported—$66,682—was included in an offer to
SKJV, but SKJV never responded to the offer. (Id. at
2574) The memorandum concluded:
Since no response has been
received to date, it is believed
that the Government and the
Contractor are not in agreement
that the balance of $66,682 from
the offered amount of $293,496
with zero calendar days of
contract time extension, is fair
and reasonable. Therefore, it is
recommended that a unilateral
modification for this amount be
executed.
App-36
(Id. at 2574-75)
42. On August 8, 2018, USACE issued
Unilateral Modification No. A00013 to the contract
for “Case AA-5: Charles County Requirements.” This
modification increased the final amount under
Change AA (Charles County requirements) by
$68,592. The modification reads in part: “Full and
final payment to provide labor, materials, equipment
and supervision to comply with Charles County
requirements.” The contract price was increased by
$81,592,4 for a total increase of $418,406 in obligated
amounts relating to Case AA. Modification No.
A00013 was designated Part 5 of Change Case AA
and granted no additional time. (R4, tab 32; JSUMF
¶ 47)
43. SKJV never signed Modification No. A00013
(JSUMF ¶ 48).
44. By letter dated January 3, 2020, SKJV
submitted an uncertified request for a contracting
officer’s final decision (COFD), which incorporated
SKJV’s April 12, 2017 REA by reference as its claim.
A letter from Mott MacDonald dated January 3, 2023,
was attached to SKJV’s claim. (R4, tab 1B)
45. By letters dated February 27 and June 30,
2020, the CO informed SKJV that its claim was
Modification No. A00013 included the sum of $13,000 under
Case AK for an unrelated differing site condition. SKJV’s
entitlement to the $13,000 is not in dispute and is not included
in the amount that the government seeks to recoup. (JSUMF
¶47, 49).
4
App-37
missing the required certification under the Contract
Disputes Act (R4, tabs 34, 36).
46. By letter dated November 10, 2020, SKJV
resubmitted its claim with a proper certification to
the CO, incorporating by reference its April 12, 2017
and January 3, 2020 correspondences as comprising
the claim (R4, tabs 1C, 37).
47. On April 2, 2021, the CO denied SKJV’s
claim (R4, tab 1D). Additionally, the CO issued an
affirmative claim to recoup the $418,406 paid to
SKJV under Modification Nos. A00002, A00005,
A00009, A00011, and A00013 on the grounds that
the Permits and Responsibilities Clause precluded
entitlement to additional compensation and that
there was no evidence of accord and satisfaction
regarding the unilateral modifications (id. at 110).
48. By letter dated June 20, 2021, SKJV
requested reconsideration, arguing that USACE had
erred in claiming the $418,406 credit (R4, tab 45).
49. On June 28, 2021, SKJV timely appealed the
COFD to the Board.
DECISION
The Parties’ Contentions
SKJV argues that USACE constructively
changed the contract by breaching the implied
warranty that its provided drawings and
specifications would be adequate for the project (app.
App-38
opp’n at 60-84, 91-97), and that USACE is liable for
changes to the contract due to its misrepresentation
of the project (id. at 89-90). SKJV also maintains
that the parties reached an accord and satisfaction
on the five unilateral modifications awarding
amounts totaling $418,406 (id. at 98-101). USACE
contends it is entitled to summary judgment because
any changes to the project were directed by third
parties (gov’t mot. at 37-42), that SKJV cannot
demonstrate that the project’s specifications were
defective (id. at 42-44), that the contract
unambiguously placed the responsibility of meeting
local permitting requirements on SKJV (id. at 44-47),
and that there was no accord and satisfaction
regarding the unilateral modifications to the contract
(id. at 51-53).
Standard of Review
Summary judgment is proper when there are
no genuine issues of material fact and the movant is
entitled to judgment as a matter of law. Celotex Corp.
v. Catrett, 477 U.S. 317, 322 (1986); Mingus
Constructors, Inc. v. United States, 812 F.2d 1387,
1390 (Fed. Cir. 1987). A fact is material if it may
affect the outcome of the decision. Anderson v.
Liberty Lobby, Inc., 477 U.S. 242, 248-49 (1986). The
movant bears the burden of establishing the absence
of any genuine issue of material fact. Celotex, 477
U.S. at 323.
Regardless of the type of claim being raised, the
applicable substantive law determines which facts
are material and thus preclude an entry of summary
App-39
judgment. Liberty Lobby, 477 U.S. at 248. Such facts
must be viewed in the light most favorable to the
non-moving party. Id. at 255; C. Sanchez and Son,
Inc. v. United States, 6 F.3d 1539, 1541 (Fed. Cir.
1993). However, the non-movant must set forth
specific facts demonstrating the existence of a
genuine issue of material fact; mere conclusory
statements and bare assertions are inadequate.
Mingus, 812 F.2d at 1390-91; Liberty Lobby, 477 U.S.
at 252 (“The mere existence of a scintilla of evidence
in support of the [non-movant]’s position will be
insufficient . . . .”). Our responsibility is not “‘to
weigh the evidence and determine the truth of the
matter,’ but rather to ascertain whether material
facts are disputed and whether there exists any
genuine issue for trial.” Holmes & Narver
Constructors, Inc., ASBCA Nos. 52429, 52551, 02-1
BCA ¶ 31,849 at 157,393 (quoting Liberty Lobby, 477
U.S. at 249). “Contract interpretation is a question of
law generally amenable to summary judgment.”
Varilease Tech. Grp., Inc. v. United States, 289 F.3d
795, 798 (Fed. Cir. 2002) (citing Textron Def. Sys. v.
Widnall, 143 F.3d 1465, 1468 (Fed. Cir. 1998)); see
also NVT Technologies, Inc. 370 F.3d 1153, 1159 (Fed.
Cir. 2004). However, if the Board determines that it
cannot resolve the dispute without reviewing
extrinsic evidence, it should not grant summary
judgment and instead allow the parties to conduct
discovery. See Korte-Fusco Joint Venture, ASBCA No.
59767, 15-1 BCA ¶ 36,158 at 176,456. When deciding
cross-motions for summary judgment, the Board
“‘evaluate[s] each motion on its own merits, taking
care in each instance to view the evidence in favor of
the non-moving party.’” ‘Martin Aeronautics Co.,
App-40
ASBCA No. 62209, 22-1 BCA ¶38,112 at 185,120
(quoting Almanza v. United States, 935 F.3d 1332,
1337 (Fed. Cir. 2019). Thus, with respect to each
motion, the non-movant “‘receiv[es] the benefit of
favorable inferences.’” Id. (quoting Chevron U.S.A.,
Inc. v. Mobil Producing Tex. & N.M., 281 F.3d 1249,
1253 (Fed. Cir. 2002)).
SKJV is Not Entitled to an Increase in Contract Price
as a Matter of Law
SKJV claims that USACE constructively
changed the contract by requiring it to perform
additional design services and construction work
beyond that which was specified in the project’s
conceptual documents and other contract documents
in order to comply with MDE, Charles County, and
MDSHA permitting requirements (app. opp’n at 6084). To demonstrate a constructive change to the
contract, SKJV must show that (1) it performed work
beyond the contract’s requirements, and (2) that the
government, expressly or impliedly, ordered the
additional work. Bell/Heery v. United States, 739
F.3d 1324, 1335 (Fed. Cir. 2014) (citing The Redland
Co. v. United States, 97 Fed. Cl. 736, 755-56 (2011)).
SKJV fails to meet either of these requirements.
First, the contract unambiguously placed all
responsibility and risk of obtaining permits
necessary for completion of the project on SKJV. The
Permits and Responsibilities Clause provides:
The Contractor shall, without
additional
expense
to
the
Government, be responsible for
App-41
obtaining any necessary licenses
and permits, and for complying
with any Federal, State, and
municipal laws, codes, and
regulations applicable to the
performance of the work. The
Contractor
shall
also
be
responsible for all damages to
persons or property that occur as
a result of the Contractor's fault
or negligence. The Contractor
shall also be responsible for all
materials delivered and work
performed until completion and
acceptance of the entire work,
except for any completed unit of
work which may have been
accepted under the contract.
(SOF ¶ 11) This obligation is reiterated in several of
the SOW’s provisions (see SOF ¶¶ 4-10). The Permits
and Responsibilities clause unambiguously imposes
upon the contractor the responsibility to determine
and comply with both State and local permitting
requirements without further cost to the government.
See Bell/Heery, 739 F.3d at 1335; ACC Constr. Co.,
ASBCA Nos. 62265, 62937, 22-1 BCA ¶ 38,194;
AMEC Environment & Infrastructure, Inc., ASBCA
No. 58948, 15-1 BCA ¶ 35,924 at 175,593. The
numerous other provisions within the contract
merely reinforce what is already made clear in the
Permits and Responsibilities clause. SKJV fails to
provide any basis for ignoring its contractual
responsibility to obtain permits or to perform work
App-42
on the project necessary to obtain those permits. See
ACC Constr. Co., 22-1 BCA ¶ 38,194 at 185,478 (“The
contract could not have been clearer that [appellant]
was solely responsible for ascertaining and
complying with the state’s requirements and for
obtaining all necessary state and local permits for
the project, whatever they might be.”).
SKJV asserts that USACE is nevertheless
responsible for the alleged changes to the contract
under the Spearin doctrine (app. opp’n at 60-71, 9197; app. reply at 14- 25). Specifically, SKJV alleges
that the conceptual drawings and other contract
documents USACE provided for the project were
defective because they did not comply with all of the
relevant permitting requirements (app. opp’n at 6061). The Spearin doctrine provides that “if the
contractor is bound to build according to plans and
specifications prepared by the owner, the contractor
will not be responsible for the consequences of
defects in the plans and specifications.” United States
v. Spearin, 248 U.S. 132, 136 (1918). The
government’s detailed design specifications contain
an implied warranty that if they are followed, a
satisfactory result will be produced. Id at 136-37;
Stuyvesant Dredging Co. v. United States, 834 F.2d
1576, 1582 (Fed. Cir. 1987). Accordingly, when a
contractor’s adherence to the government’s detailed
specifications results in unsatisfactory performance,
the design is considered defective, the government is
deemed to have breached this implied warranty, and
“the contractor is entitled to recover all of the costs
proximately flowing from the breach.” Essex Electro
Eng’rs, Inc. v. Danzig, 224 F.3d 1283, 1289 (Fed. Cir.
App-43
2000) (citations omitted); see Spearin, 248 U.S. at
138. In such cases, the government is liable for “any
damages incurred by a contractor as a result of
defects in such plans and specifications” and “all
delay
caused
by
defective
or
inadequate
specifications is per se unreasonable and hence
compensable.” Turner Constr. Co., ASBCA No. 25447
et al., 90-2 BCA ¶ 22,649 at 113,806 (citing Chaney
and James Constr. Co., Inc., v. United States, 421
F.2d 728, 731-32 (Ct. Cl. 1970); see also Essex, 224
F.3d at 1289 (“The compensable costs include those
attributable to any period of delay that results from
the defective specifications.”).
Specifications fall into two categories—design
specifications
and performance
specifications.
“Design specifications explicitly state how the
contract is to be performed and permit no
deviations.” Stuyvesant, 834 F.2d at 1582.
Conversely, performance specifications specify the
results to be obtained, but leave it to the contractor’s
discretion as to how to achieve those results. Id.
(citing J.L. Simmons Co. v. United States, 412 F.2d
1360, 1362 (Ct. Cl. 1969)); see also P.R. Burke Corp. v.
United States, 277 F.3d 1346, 1356 (Fed. Cir. 2002)
(explaining Federal Circuit precedent “[p]erformance
specifications ‘set forth an objective or standard to be
achieved, and the successful bidder is expected to
exercise his ingenuity in achieving that objective or
standard of performance, selecting the means and
assuming a corresponding responsibility for that
selection.’”) (quoting Blake Constr. Co. v. United
States, 987 F.2d 743, 745 (Fed. Cir. 1993) (emphasis
in original). The implied warranty that the
App-44
government’s specifications are free from design
defects attaches only to design specifications—it
“does not accompany performance specifications that
merely set forth an objective without specifying the
method of obtaining the objective.” White v. Edsall
Constr. Co., 296 F.3d 1081, 1084 (Fed. Cir. 2002).
These specifications did not specify how the
project was to be designed, but merely obligated
SKJV to meet USACE’s objectives for the project
while also complying with requirements and
guidelines of both the State of Maryland and Charles
County to obtain permits, paying both the applicable
fees and costs necessary to meet the requirements.
The contract’s provisions repeatedly emphasized that
this responsibility rested solely with SKJV. (SOF ¶¶
4-11) Section 1.2.4 of Part 1 of the SOW, “Design
Freedom,” provided:
Requirements stated in this RFP
are
minimums.
Innovative,
creative, or cost-saving proposals,
which meet or exceed these
requirements are encouraged, and
will be considered more favorably.
...
1.2.4.2 The conceptual design
Drawings, this Statement of
Work, and the Outline Technical
Specifications, along with the
other
information
and
requirements in this RFP, serve
App-45
as requirements for Contractor
building design and construction
completion, along with other code,
regulatory
and
professional
practice requirements. The extent
of development of these RFP
documents in no way relieves the
successful
offeror
from
responsibility for completing the
design,
construction
documentation, and construction
of
the facility in conformance with
Applicable Criteria and codes.
1.2.4.3 The conceptual design
illustrates
desired
general
arrangements, orientation, and
adjacencies,
and
provides
examples of exterior images which
is acceptable to the Government –
it is not intended to dictate the
final layout and image for the
project.
The
Contractor’s
designers shall develop and refine
the conceptual site and building
design in their completion of the
design
and
construction
documents. Such development
shall be consistent with the
criteria and acceptable to the
Government.
App-46
(SOF ¶ 5) Since these specifications left discretion for
the project’s overall design to SKJV, we find that
they were performance specifications. Stuyvesant,
834 F.2d at 1582. Consequently, the Spearin doctrine
is inapplicable here. Edsall, 296 F.3d at 1084.
Likewise, SKJV cannot shift the unexpected
increase in costs to the government under a
constructive change theory as it cannot meet the
essential element that there was additional work
ordered, expressly or impliedly, by the government.
Bell/Heery, 739 F.3d at 1335. It is undisputed that
the alleged changes to the contract were directed by
MDE, Charles County, and MDSHA, not USACE
(SOF ¶¶ 19, 22-23). The government cannot be held
responsible for determinations made by another
sovereign government. ACC Constr. Co., 22-1 BCA ¶
38,194 at 185,478 (citing Kellogg Brown & Root
Servs., 20-1 BCA ¶ 37,656 at 182,826); see also Zafer
Taahhut Insaat ve Ticaret A.S. v. United States, 833
F.3d 1356, 1364 (Fed. Cir. 2016) (holding the
government is not responsible for the sovereign acts
of a foreign nation). “[T]he doctrine of constructive
change cannot be invoked against the [g]overnment
because it did not itself effect an alteration in the
work to be performed, much less an alteration ‘so
drastic that it effectively’ resulted in a cardinal
change ‘requir[ing] the contractor to perform duties
materially different from those originally bargained
for.’” Bell/Heery, 739 F.3d at 1335 (quoting Krygoski
Constr. Co. v. United States, 94 F.3d 1537, 1543 (Fed.
Cir. 1996)). Under these facts, SKJV cannot recover
for a constructive change.
App-47
SKJV’s Misrepresentation Claim
Additionally, SKJV argues that USACE is
liable for changes to the contract due to its alleged
misrepresentation of the project (app. opp’n at 89-90).
To prevail, SKJV must demonstrate that USACE
“made an erroneous representation of material fact
that [SKJV] honestly and reasonably relied on to [its]
detriment.” T. Brown Constructors, Inc. v. Pena, 132
F.3d 724, 728-29 (Fed. Cir. 1997). SKJV fails to
identify
any
specific
facts
supporting
its
misrepresentation claim. Ashcroft v. Iqbal, 556 U.S.
662, 678 (2009) (A pleading that merely offers
conclusions or a “‘formulaic recitation of the elements
of a cause of action’” without identifying any specific
facts is inadequate to support a claim. (quoting Bell
Atlantic Corp. v. Twombly, 550 U.S. 544, 555 (2007))).
Moreover, as discussed above, the contract made
clear that SKJV would be responsible for obtaining
any permits necessary for the project (SOF ¶¶ 4-11).
In fact, while § 2.6 of Part 2 of the SOW listed
various permits that would be required for the
project, it also stipulated that “[t]his list is not allinclusive, and Contractor is responsible for verifying
that information below remains accurate” (SOF ¶ 10).
Accordingly, SKJV either knew or should have
known of the possibility that permits additional to
those enumerated in the contract may have been
necessary and was responsible for researching these
requirements. There are simply no facts presented by
appellant that could support a finding of
misrepresentation.
App-48
As a Matter of Law, USACE is Entitled to Recoup the
$418,406 That it Paid as a Result for Mistakenly
Issuing Unilateral Modification Nos. A00002, A00005,
A00009, A00011, and A00013
SKJV asserts that USACE’s affirmative claim
for $418,406 associated with Modification Nos.
A00002, A00005, A00009, A00011, and A00013 was
improper because USACE constructively changed the
contract, alleging that Charles County and MDSHA
permitting requirements were beyond the scope of
the contract documents (app. opp’n at 91-97). As
discussed above, the Permits and Responsibilities
Clause and several of the SOW’s provisions placed
the obligations to acquire any permits necessary for
the project and to perform work necessary to obtain
such permits solely on SKJV (SOF ¶¶ 4-11). SKJV
once again relies on Spearin in its attempt to
circumvent this responsibility (app. opp’n at 91-97).
However, as discussed above, Spearin is inapplicable
to these circumstances. The contract’s specifications
did not specify how the project was to be designed,
but merely stipulated that SKJV meet USACE’s
demands for the project while complying with state
and local permitting requirements and left discretion
for the project’s overall design to SKJV (see SOF ¶¶
4-11).
Accordingly,
they
were
performance
specifications, and SKJV’s reliance on Spearin is
misplaced. Stuyvesant, 834 F.2d at 1582.
SKJV challenges USACE attempts to recover
the $418,406 arguing that the parties reached an
accord and satisfaction as it relates to the five
unilateral modifications. (App. opp’n at 98-101). “To
App-49
reach an accord and satisfaction, there must be
mutual agreement between the parties with the
intention clearly stated and known” to the parties.
Coastal Gov’t Servs., Inc., ASBCA No. 50283, 99-1
BCA ¶ 30,348 at 150,088 (citing Metric Constructors,
Inc., ASBCA No. 46279, 94-1 BCA ¶ 26,532 at
132,058). “To prove accord and satisfaction, [SKJV]
must demonstrate ‘(1) proper subject matter; (2)
competent parties; (3) a meeting of the minds
[between SKJV and USACE]; and (4) consideration.’”
Whiting-Turner Contracting Co., ASBCA No. 56319,
10-1 BCA ¶ 34,436 at 169,951 (quoting Bell BCI Co. v.
United States, 570 F.3d 1337, 1341 (Fed. Cir. 2009)).
The unilateral modifications germane to this
appeal were essentially settlement offers that SKJV
was free to accept or decline. See Zinger Constr. Co.,
ASBCA Nos. 28788, 32424, 87-3 BCA ¶ 20,196 at
102,284. The undisputed facts show that SKJV never
accepted the terms of any of these offers—there was
no
“meeting
of
the
minds.”
Numerous
communications between the parties and documents
issued by USACE indicate that SKJV did not accept
nor agree to the five unilateral modifications (see
SOF ¶¶ 27, 31, 36, 40-42). SKJV repeatedly sought
amounts exceeding those awarded via the unilateral
modifications (see SOF ¶¶ 38, 41). Furthermore,
SKJV never signed Modification No. A00013—the
fifth and final modification (SOF ¶ 43). Accordingly,
we find that there was no “mutual agreement” 5
Indeed, what SKJV is asking us to do is to enforce this
agreement against the government, but be free of any
5
App-50
between USACE and SKJV regarding the unilateral
modifications, and therefore no accord and
satisfaction. Coastal Gov’t Servs., 99-1 BCA ¶ 30,348
at 150,088.
The Contracting Officer’s final decision seeks
to recover the amounts paid to SKJV under the five
modifications it contends were erroneously issued
(Mod. Nos. A00002 - $20,000; A00005 - $30,000;
A00009 - $75,000; A00011 - $224,814; A00013 $68,5926) for a total sum of $418,406. (SOF ¶¶ 27, 31,
36-37, 40, 42-43, 47). We have jurisdiction to consider
the government’s affirmative claim of recoupment.
Nova Group, Inc., ASBCA No. 55408, 10-2 BCA ¶
34,533 at 170,331. Having found that the additional
work performed by SKJV to meet Charles County
and MDSHA permitting requirements, was work
required by the contract, there was no constructive
change and no basis for the government’s paying
increased costs to SKJV. As such, we find that the
five unilateral modifications were, as the CO
contended, mistakenly issued and that the
government thus incorrectly paid $418,406 for costs
associated with the Charles County and MDSHA
requirements for water, sewer, and access permits.
As we established above, SKJV cannot rely upon the
defense of accord and satisfaction. SKJV’s challenge
to the government’s affirmative claim for the
repayment of $418,406 is rejected. The USACE is
obligation to comply with it, itself. That is not how contracts
work.
6 The sum of $13,000 paid under Modification No. A00013 for
an unrelated differing site condition remains unaffected.
App-51
entitled to recoup the funds incorrectly paid to the
contractor and is entitled to judgment in the amount
of $418,406.
CONCLUSION
For the foregoing reasons, we grant USACE’s
motion for summary judgment and deny SKJV’s
motion for partial summary judgment. The appeals
are denied.
Dated: August 11, 2023
(Signatures
continued)
STEPHANIE CATES-HARMAN
Administrative Judge
Armed Services Board
of Contract Appeals
I concur
I concur
RICHARD SHACKLEFORD
Administrative Judge
Acting Chairman
Armed Services Board
of Contract Appeals
J. REID PROUTY
Administrative Judge
Vice Chairman
Armed Services Board
of Contract Appeals
I certify that the foregoing is a true copy of the
Opinion and Decision of the Armed Services Board of
Contract Appeals in ASBCA Nos. 62972, 62973,
App-52
Appeals of Sheffield-Korte Joint Venture, rendered
in conformance with the Board’s Charter.
Dated: August 11, 2023
PAULLA K. GATES-LEWIS
Recorder, Armed Services
Board of Contract Appeals
App-53
Appendix E
[Filed: May 13, 2024]
Appx 1511 - Drawing C-101
App-54
Appendix F
[Filed: May 13, 2024]
As Awarded 28 August 2015
W912QR-15-C-0027
W912QR-14-R-0034
*** SAFETY PAYS ***
Army Reserve Center
W912QR-14-R-0034
Bowie, MD
Amendment 0009
1.2.1.2
Where manufacturer or vendor names
are called out, the intention is generally to provide
guidance on desired quality and features for the
system or material. Unless the manufacturer or
vendor is identified as “sole-source,” or with similar
language, the Contractor may provide the equivalent
or better system or material of another vendor or
manufacturer.
1.2.1.3
The project shall be designed and
constructed using English (inch-pound) units of
measurement.
1.2.2
Primary Consideration. The primary
consideration of this solicitation is to obtain a
Training Center within funds available, and to
maximize design quality. Offerors are encouraged to
review the RFP to familiarize themselves with all
RFP requirements.
1.2.3
Design Quality. Design quality is
achieved through the optimization of interior
planning, integration of the buildings with the site,
App-55
sustainability, selection of building materials and
systems for low-cost maintenance and operation, and
an overall balance of esthetics and functionality. The
Army Reserve encourages a project design of awardwinning caliber.
1.2.4
Design Freedom. Requirements stated
in this RFP are minimums. Innovative, creative, or
cost-saving proposals, which meet or exceed these
requirements are encouraged, and will be considered
more favorably.
1.2.4.1
The project conceptual design was
developed by the Army Reserve, the Corps of
Engineers, and an A/E design team; this conceptual
design is accepted by the Government.
1.2.4.2
The conceptual design Drawings, this
Statement of Work, and the Outline Technical
Specifications, along with the other information and
requirements in this RFP, serve as requirements for
Contractor building design and construction
completion, along with other code, regulatory and
professional practice requirements. The extent of
development of these RFP documents in no way
relieves the successful offeror from responsibility for
completing the design, construction documentation,
and construction of the facility in conformance with
Applicable Criteria and codes.
1.2.4.3
The conceptual design illustrates
desired general arrangements, orientation, and
adjacencies, and provides examples of exterior
images which is acceptable to the Government – it is
App-56
not intended to dictate the final layout and image for
the project. The Contractor’s designers shall develop
and refine the conceptual site and building design in
their completion of the design and construction
documents. Such development shall be consistent
with the criteria and acceptable to the Government.
1.2.4.3.1
Examples of exterior images acceptable
to the AR are included in the Attachments to this
Section.
1.2.4.3.2
Design building(s) to enhance or
complement the visual environment of the
neighborhood. The design shall reflect a human scale,
and primary entrances shall be architecturally
designed for easy visibility. Exterior materials, roof
forms, and detailing shall be compatible with
surrounding development and adjacent buildings,
and shall follow established architectural themes.
Exterior colors shall conform to the 99th Regional
01 02 00.00 48
Part 1 - 2 of 12
Appx1831
App-57
Appendix G
[Filed: May 13, 2024]
As Awarded 28 August 2015
W912QR-15-C-0027
W912QR-14-R-0034
*** SAFETY PAYS ***
Army Reserve Center
W912QR-14-R-0034
Bowie, MD
Amendment 0009
1.4
SURVEY
INFORMATION.
AND
GEOTECHNICAL
1.4.1
A survey was performed by a licensed
surveyor and is provided in these documents. The
Contractor shall, at its own expense, obtain any
additional information required to provide a
complete and useable design. Do not contact the
surveyor during the preparation of proposals for the
solicitation.
1.4.2
A
preliminary
Subsurface
Characterization report has been performed by a
professional engineer, and is provided in the
Attachments to this Statement of Work. Do not
contact the engineer during the preparation of
proposals for the solicitation. The Contractor shall
perform its own geotechnical investigation to
establish soil characteristics for site earthwork,
foundation, paving and cathodic protection design
and construction.
App-58
1.5
RFP DRAWINGS. The conceptual
drawings are included as a part of this RFP to
provide information and criteria for the Contractor’s
completion of the design.
1.6
SPECIFICATIONS.
1.6.1
The Outline Technical Specifications
are provided primarily in outline format. They shall
be utilized as design and submittal criteria, and
minimum
standards
for
the
corresponding
construction work, and shall be met or exceeded
unless Contractor obtains specific Government
approval for proposed reductions. These outline
specifications shall not be considered complete and
suitable for final construction specifications.
Contractor’s designers shall expand the outline
specifications to provide comprehensive, three-part,
CSI-format Specifications and shall edit the
Specifications to indicate actual products to be used
in the construction. Final specifications shall include
as a minimum, a description of the technical
requirements, criteria for determining whether the
criteria are met, and quality control requirements
and procedures. The standards referenced in the
outline
specifications
establish
minimum
requirements for the final construction specifications.
1.6.2
All Outline Technical Specification
sections provided in this RFP may not be required for
this project, and designers shall provide additional
Specification Sections or items if necessitated by
their final design or RFP requirements.
App-59
1.6.3
Some Outline Technical Specification
Sections are more detailed and extensive than the
majority; these represent the Government’s required
specification approach to this project. Contractor’s
designers must still take complete responsibility for
the design and specification of the project, and shall
satisfy themselves that these Sections are complete
and suitable for the final design. Most of the outline
specification sections are adapted from typical
Government Unified Facility Guides Specifications
(UFGS) and reflect Army Reserve-approved
approaches and products. The outline specification
requirements shall be used as the basis for selection
of construction materials, products, and systems.
Contractor’s final specifications may be developed
from UFGS, one of the industry prototype
specifications (such as MasterSpec), or Contractor’s
designers’ company specification system. Use of
UFGS is not required.
01 02 00.00 48
Part 1 - 6 of 12
Appx1835
App-60
Appendix H
[Filed: May 13, 2024]
App-61
Appendix I
[Filed: May 13, 2024]
As Awarded 28 August 2015
W912QR-15-C-0027
W912QR-14-R-0034
Report of
Bowie MD – Army
Geotechnical Data
Reserve Center
May 1, 2014
GTA Project No. 140171
on the order of 6 to 8 kips per linear foot (klf).
Construction of an Unheated Storage Building
(UHS), and an Organization Maintenance
Shop (OMS) in the northern portion of the site.
GTA has assumed that these buildings will be
relatively lightly loaded, one-story buildings
with slabs-on-grade.
Approximately 75,000 square feet of Military
Equipment Parking (MEP) in the northeastern
portion of the site near the OMS and UHS. A
Privately Owned Vehicle (POV) lot is also
planned in the southern portion of the site
outside of the fenced-in facility. GTA
understands
that
relatively
heavy
equipment/vehicles will utilize the MEP lot,
and the POV parking area will be primarily
limited to passenger cars or similar vehicles.
Construction of a Stormwater Management
(SWM) facility in the northern portion of the
site. The plans indicate that this facility will
consist of a pond with an excavated basin and
a partially filled earthen embankment.
Several drainage swales are planned
throughout the site. The swales will drain to
App-62
this SWM facility. GTA understands that the
proposed SWM facilities may incorporate
infiltration techniques if feasible based on the
subsurface conditions. Additional specific
details of this facility were not available at the
time of the preparation of this report
Access to the proposed Army Reserve Center
(ARC) will be provided from the south via Marshall
Corner Road by an access road extending along the
general alignment of the existing Foxtail Place. A
gated entry is planned near the terminus of this
roadway. Subsurface utilities will consist of public
water, sewer, and gas utilities. Additional
communications and electrical utilities are also
planned. The available grading plans indicate that
cuts and fills on the order of 5 to 9 feet will be
required to establish the proposed grades across the
project site. Deeper excavations may be required
locally, on the existing knoll, or for deep utilities that
drain by gravity (i.e. sanitary sewer).
SITE GEOLOGY
According to the Geologic Map of Maryland
(1968), published by the Maryland Geological Survey,
the site vicinity is situated within the Coastal Plain
Physiographic
Province,
which
is
generally
characterized by interlayered sedimentary deposits
from historic marine and estuarine environments.
More specifically, the Geologic Map of Charles
County, Maryland (1989) indicates
3
Appx1939