Amicus Curiae Brief — Percipient.ai, Inc., Petitioner v. United States, et al.
Supreme Court briefNov 7, 2025
Ask Donna
What actually matters in this document.
Text
No. 25-428
In the
Supreme Court of the United States
PERCIPIENT.AI, INC.,
Petitioner,
v.
UNITED STATES, et al.,
Respondents.
On Petition for a Writ of Certiorari to the
United States Court of Appeals for the Federal Circuit
BRIEF AMICI CURIAE OF FOUNDATION
FOR AMERICAN INNOVATION, THE ALLIANCE
FOR COMMERCIAL TECHNOLOGY IN
GOVERNMENT, SHIELD CAPITAL,
SNOWFLAKE INC., AND COMMERCIAL
SUPPLIERS IN SUPPORT OF PETITIONER
Erika Payne
Snowflake Inc.
125 Constitution Drive
Menlo Park, CA 94025
Counsel for Snowflake, Inc.
and Sridhar Ramaswamy
Tim Hwang
Counsel of Record
Foundation for
American Innovation
2443 Fillmore Street,
#380-3386
San Francisco, CA 94115
(973) 960-4955
tim.hwang@thefai.org
Counsel for Amici Curiae
131670
A
(800) 274-3321 • (800) 359-6859
i
TABLE OF CONTENTS
Page
TABLE OF CONTENTS . . . . . . . . . . . . . . . . . . . . . . . . . . i
TABLE OF CITED AUTHORITIES . . . . . . . . . . . . . . iii
INTEREST OF AMICI CURIAE . . . . . . . . . . . . . . . . . 1
SUMMARY OF ARGUMENT . . . . . . . . . . . . . . . . . . . . 2
ARGUMENT . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 4
I.
FORTY YEARS OF CONGRESSIONAL
REFORM HAVE FAILED DUE TO A
SYSTEMIC ENFORCEMENT GAP THAT
THREATENS NATIONAL SECURITY . . . . . 4
A. Congress Envisioned a Procurement
Revolution That Would Harness
Commercial Innovation for National
Defense . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5
B. Agencies Gutted That Vision Through
Reinterpretation And Regulatory
Accretion . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 8
C. The Section 809 Panel Documented How
Far Agencies Had Strayed From The
Text . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 10
D. The Empir ical Consequences Of
Nonenforcement Have Been Stark . . . . . . 12
ii
Table of Contents
Page
D1. S k ipp i n g M a rket R e s e a r c h
Adds Years of Delay and Billions
in Cost . . . . . . . . . . . . . . . . . . . . . . . . . . . 12
D2. Uncontrolled Clause Proliferation
Drove Out Thousands of Vendors . . . . 16
E. The En Banc Holding Would Remove the
Last Available Brake on Nonenforcement . . 18
II. THE SUPREME COURT SHOULD
GRANT CERTIORARI TO ADDRESS
ERROR ON AN IMPORTANT FEDERAL
QUESTION . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .21
A. Textual Canons Strongly Suggest
Differential Standing for Prong 3
Challenges . . . . . . . . . . . . . . . . . . . . . . . . . . . 21
B. “Floodgate” Concerns Are Speculative . . 24
C. The Issues at Stake Implicate Critical
Federal Questions . . . . . . . . . . . . . . . . . . . . 26
CONCLUSION . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 27
APPENDIX — LIST OF AMICI CURIAE . . . . . . . 1a
iii
TABLE OF CITED AUTHORITIES
Page
Cases
Analytical Graphics, Inc. v. United States,
135 Fed. Cl. 378 (2017) . . . . . . . . . . . . . . . . . . . . . . . . 12
Conn. Nat’l Bank v. Germain,
503 U.S. 249 (1992) . . . . . . . . . . . . . . . . . . . . . . . . . . . 23
Kingdomware Techs., Inc. v. United States,
579 U.S. 162 (2016) . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6
Palantir USG, Inc v. United States,
904 F.3d 980 (Fed. Cir. 2018) . . . . . . . . . . . . . . . . . 8, 19
United States v. Gonzales,
520 U.S. 1 (1997) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 23
Statutes and Rules
10 U.S.C. § 2377 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6, 12
10 U.S.C. § 3453 . . . . . . . . . . . . . . . . . . . . . . . . . 6, 7, 17, 20
10 U.S.C. § 3453(a) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6
10 U.S.C. § 3453(b) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6
10 U.S.C. § 3453(b)(2) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6
10 U.S.C. § 3453(c) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6
iv
Cited Authorities
Page
10 U.S.C. § 3453(c)(5) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6
10 U.S.C. § 3705(a) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 9
28 U.S.C. § 1491(b) . . . . . . . . . . . . . . . . . . . . . . 1, 19, 20, 22
28 U.S.C. § 1491(b)(1) . . . . . . . . . . . . . . . . . . . . . . . . . . . . 22
38 U.S.C. § 8127(d) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6
41 U.S.C. § 103(1)(A)–(B) . . . . . . . . . . . . . . . . . . . . . . . . . . 9
41 U.S.C. § 3503 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 8
48 C.F.R. § 2.101 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 9
48 C.F.R. § 15.403-1(b)(3) . . . . . . . . . . . . . . . . . . . . . . . . . . 8
48 C.F.R. § 212.102(a)(1)(C) . . . . . . . . . . . . . . . . . . . . . . . . 9
48 C.F.R. § 252.204-7012(b)(2) . . . . . . . . . . . . . . . . . . . . 10
48 C.F.R. § 252.204-7012(c)(1)(ii) . . . . . . . . . . . . . . . . . . 10
74 Fed. Reg. 34,270 (July 15, 2009) . . . . . . . . . . . . . . . . . . 7
Pub. L. No. 98-369, Div. B, Title VII, §§ 2701–2753,
98 Stat. 1175 (1984) . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5
Pub. L. No. 114-92 § 844(a), 129 Stat. 915 (2015) . . . . . . 7
Pub. L. No. 114-328 § 871, 130 Stat. 2307 (2016) . . . . . . 7
v
Cited Authorities
Page
Pub. L. No. 115-232 § 836(d)(3), 132 Stat. 1866 (2018) . 7
Pub. L. No. 116-92 § 818(a), 133 Stat. 1488 (2019) . . . . . 7
Pub. L. No. 116-283 § 1821, 134 Stat. 4195 (2021) . . . . . 7
Pub. L. No. 118-159 § 834, 138 Stat. 1986 (2024) . . . . . . 7
Administrative Dispute Resolution Act . . . . . . . . . . . . .26
Competition in Contracting Act . . . . . . . . . . . . . . . . . 5, 22
National Defense Authorization Act . . . . . . . . . . . . . . . . 7
Sup. Ct. R. 10 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 26
Tucker Act . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 23, 25
Other Authorities
Advisory Panel on Streamlining & Codifying
Acquisition Regulations (Section 809 Panel),
Report of the Advisory Panel on Streamlining
and Codifying Acquisition Regulations,
vol. 1 of 3 (Jan. 2018), https://discover.dtic.
mil /w p -content /uploads/809 -Panel-2019/
Volume1/Sec809Panel_Vol1-Report_Jan2018.pdf . . 11
Ben, Complete DJI Drone History & Release
Date Timeline (2013–2025), Gadgets N Tech
(Oct. 14, 2025), https://gadgets-n-tech.com/
complete-dji-drone-histor y-releasedatetimeline/ . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 13
vi
Cited Authorities
Page
Alec C. Blivas, Brenen Tidwell & Morgan Dwyer,
Cycle Times and Cycles of Acquisition
Refo r m , C SI S Br ie fs (A ug. 5 , 2 0 2 0),
https://w w w.csis.org/analysis/cycle-timesand-cycles-acquisition-reform . . . . . . . . . . . . . . . . . . 12
Tajha Chappel let -La n ier, Ar my, Defense
Inn o va ti o n Unit Mo ve Fo r war d With
Surveillance Drone Project, FedScoop (Apr.
29, 2019), https://fedscoop.com/army-diushort-range-reconnaissance-drones-award/
(reporting DIU solicitation issued Nov. 2018) . . . . . 13
Coalition for Gov’t Procurement, Market Report: The
State of the Federal Market (May 2024), https://the
cgp.org/images/2024/06/23-Market-Report-2.pdf . . . 21
Cong. Research Serv., F-35 Joint Strike Fighter (JSF)
Program: Background and Issues for Congress
(Dec. 22, 2009), https://www.everycrsreport.com/
files/20091222_RL30563_4e4c38f6c1371c17b92
fa2c7cc25a9c2aeae8df6.pdf . . . . . . . . . . . . . . . . . . . . 15
Ctr. for Strategic & Int’l Stud., How Ukraine
Rebuilt Its Military Acquisition System
Around Commercial Technology (Jan. 2025),
https://csis-website-prod.s3.amazonaws.
com/s3fs-public/2025 - 01/250113_Bondar_
Ukraine_Acquisition.pdf . . . . . . . . . . . . . . . . . . . . . . 16
vii
Cited Authorities
Page
Defense Acquisition Regulations Sys., Defense
Federal Acquisition Regulation Supplement;
Limitation on Procurements on Behalf
of the Dep’t of Def., 74 Fed. Reg. 34,270
(July 15, 2009), https://w w w.govinfo.gov/
content/pkg/FR-2009-07-15/pdf/E9-16668.pdf . . . . . 7
Defense Contract Mgmt. Agency, DCMA CIG
In d u s t r y D a y ( Fe b. 2 0 , 2 0 2 0) (s l i de
deck), https://w w w.dcma.mil / Portals/31/
D o c u ment s /CIG / D CM A%2 0 CIG %2 0
I n d u s t r y % 2 0 D ay % 2 0 s l i d e s % 2 0 2 0 % 2 0
February%202020.pdf . . . . . . . . . . . . . . . . . . . . . . . . . 9
Dep’t of Def., Class Deviation 2024-O0013
(May 2, 2024) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 10
DFARS 212.102 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 9
DFARS 252.204-7012 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 9
Yuliia Dysa & Olena Harmash, Zelenskiy Woos
US Businesses, Seeks to Grow Ukraine’s Drone
Industry, Reuters (Sept. 25, 2025), https://
www.reuters.com/business/zelenskiy-woosus-businesses-seeks-grow-ukraines-droneindustry-2025-09-25/ . . . . . . . . . . . . . . . . . . . . . . . . . 16
viii
Cited Authorities
Page
Exec. Order No. 14,271, 90 Fed. Reg. 16,433
(Apr. 18, 2025) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 7
Federal Acquisition Regulation; Acquisition
of Commercial Items, 60 Fed. Reg. 48,231
(Sept. 18, 1995), https://w w w.govinfo.gov/
content/pkg/FR-1995-09-18/pdf/95-22778.
pdf . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6
Federa l Acqu isit ion Reg u lat ion; Pa r t 15
R ew r it e — Cont r a c t i ng by Negot i at ion
& Competitive Range Determination, 62
Fed. Reg. 51,224 (Sept. 30, 1997), https://
w w w.gov i n fo.gov/cont ent /pkg / FR-19 9709-30/pdf/97-25666.pdf . . . . . . . . . . . . . . . . . . . . . . . 8-9
Grace Commission Recommendations: Hearing
Before the S. Comm. on Finance, 98th Cong.,
S. Hrg. No. 98‑744 (1984), https://www.finance.
senate.gov/imo/media/doc/HRG98-744.pdf . . . . . . . . 5
J o h n E . Ja c k s o n , T h e $ 4 3 6 H a m m e r :
A Laughing Matter?, Proceedings (U.S.
Nava l Inst .) (Dec. 19 8 5), https: // w w w.
u sn i .or g / m a g a z i ne s / pr o c e e d i ng s / 19 8 5 /
december/4 36 -ha m mer -laugh i ngmatter. U.S. Naval Institute . . . . . . . . . . . . . . . . . . . . 5
ix
Cited Authorities
Page
List of Starlink and Starshield launches,
Wikipedia (last v isited Oct. 31,
2 0 2 5 ), ht t p s : //e n .w i k i p e d i a . o r g / w i k i /
List_of_Starlink_and_Starshield_launches . . . 13, 14
Adam Mazmanian, DoD Plans $1.4B SoleSource Extension for Leidos on Health
Ca re Record, Ne x tgov/ FC W (Oc t . 2 3 ,
2024), https://www.nextgov.com/acquisition/
2 0 2 4 / 10 /d o d - p l a n s -14 b - s o l e - s o u r c e extension-leidos-health-care-record/400501/ . . . . . 15
Nor t h rop Gr u m ma n, U. S . Nav y Aw ar d s
$1.16 Billi o n BA MS UA S Co ntr a c t t o
No r th r o p G r u m m a n (A pr. 2 2 , 2 0 0 8),
https://investor.nor thropg r umman.com /
news-releases /news-release - det a i ls /usnavy-awards-116-billion-bams-uas-contractnorthrop-grumman (last visited Nov. 4, 2025) . . . . 13
OECD, OECD Main Science and Technology
Indicators: Highlights from the March
2024 Edition (Mar. 2024), https://www.oecd.
org /cont ent /dam /oecd /en /data /datasets /
main-science-and-technolog y-indicators/
msti-highlights-march-2024.pdf . . . . . . . . . . . . . . . . 17
Shyam Sankar, The Defence Reformation: 18
Theses for the Resurrection of the American
Industrial Base, 18Theses.com (Oct. 31, 2024),
https://www.18theses.com . . . . . . . . . . . . . . . . . . . . . 26
x
Cited Authorities
Page
Section 809 Panel, Vol. 1 Report (Jan. 2018),
discover,dtic.mil . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 11
Jared Serbu, Section 809 panel’s final report
prescribes “revolutionary” changes to DoD
buying, Federal News Network (Jan. 15, 2019),
https://federalnewsnetwork.com/acquisitionpolicy/2 019/01/section- 8 0 9 -panels-f inalreport-prescribes-revolutionary-changes-todod-buying/ . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 11
Antonin Scalia & Bryan A. Garner, Reading Law:
The Interpretation of Legal Texts (Thomson/
West 2012) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 22
Triad Isotopes, Inc., B-411360, 2015 CPD ¶ 220
(Comp. Gen. July 16, 2015) . . . . . . . . . . . . . . . . . . . . . 19
Sa rah T reuha f t et a l., Fewer and Fewer
Small Businesses A re Getting Federal
Contracts, National Equity Atlas (Sept.
28, 2021), https://nationalequityatlas.org/
federalcontracts . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 17
U.S. Army, New Short Range Reconnaissance
Capability Begins Fielding to Soldiers
(O c t . 1 2 , 2 0 2 2 ) , h t t p s : / / w w w. a r m y.
m i l /a r t i c l e / 2 6 10 6 3 / n e w_ s ho r t _ r a n g e _
reconnaissance_capability_begins_fielding_to_
soldiers (last visited Nov. 4, 2025) . . . . . . . . . . . . . . . 13
xi
Cited Authorities
Page
U.S. Dep’t of Def., Performance and Accountability
Report, Fiscal Year 2003 (Dec. 23, 2003), https://
comptroller.war.gov/Portals/45/Documents/afr/
QQfy2003/00_Entire_Document.pdf . . . . . . . . . . . . 14
U. S. Dep’t of Def., State of Competition
within the Defense Industrial Base (Feb.
2 0 2 2), ht tp s: //med i a .defense.gov/ 2 0 2 2 /
feb/15/2002939087/-1/-1/1/state-of-competitionwithin-the-defense-industrial-base.pdf . . . . . . . . . . 17
U. S . G ov ’t Accou nt abi l ity Of f., Co ntr a c t
Management: Minimal Compliance with
New Safeguards for Time‑and‑Materials
Contracts for Commercial Services and
Safeguards Have Not Been Applied to GSA
Schedules Program, GAO‑ 09‑579 (2009),
https://www.gao.gov/assets/gao-09-579.pdf . . . . . . . 10
U.S. Gov’t Accountability Off ice, Defense
Acquisition Reform: Persistent Challenges
Require New Iterative Approaches to Delivering
Capability with Speed (June 11, 2025),
https://www.gao.gov/assets/880/879068.pdf . . . . . . 14
U. S . G o v ’ t A c c o u nt a b i l i t y O f f i c e , F- 3 5
Joint Strike Fighter: Actions Needed to
Ad dress Late Deliver ies an d Imp ro ve
Future Devel o p m ent (S ept . 2 0 2 5),
https://www.gao.gov/assets/gao-25-107632.pdf . . . . 15
xii
Cited Authorities
Page
U.S. Gov’t Accountability Off., Market Research:
Better Documentation Needed to Inform Future
Procurements at Selected Agencies, GAO‑15‑8
(2014), https://www.gao.gov/assets/gao-15-8.pdf . . 10
U.S. Gov’t Accountability Office, Military
A c q u i s i t i o n s : D OD Is Ta k i n g S t e p s
to Address Challenges Faced by Certain
Companies (July 2017), https://www.gao.gov/
assets/gao-17-644.pdf . . . . . . . . . . . . . . . . . . . . . . . 17-18
U.S. Gov’t Accountability Office, Small Business
Contracting: Actions Needed to Implement
and Monitor DOD’s Small Business Strategy
(Oct. 2021), https://www.gao. https://www.gao.
gov/assets/gao-22-104621.pdf . . . . . . . . . . . . . . . . . 16-17
U.S. Navy, NAS Sigonella Welcomes First
MQ-4C Triton (Apr. 1, 2024) (noting VUP19 achieved initial operational capability in
Sept. 2023), https://w w w.navy.mil/ PressOffice/News-Stories/Article/3725909/nassigonella-welcomes-first-mq-4c-triton/ . . . . . . . . . . 13
U. S . Pa c . F leet , F- 35C Achi eves Initi a l
Operational Capability (Feb. 28, 2019),
ht t p s : // w w w. c p f . n a v y. m i l / Ne w s r o o m /
Ne w s /A r t ic le / 2 6 6 4 4 0 5 / f- 3 5 c - a c h ie ve s initial-operational-capability/ . . . . . . . . . . . . . . . . . . 15
xiii
Cited Authorities
Page
Frank Wolfe, Updated Sentinel Acquisition
Strategy in Works; EMD Approval Goal
Early to Mid-2027, Defense Daily (Sept. 23,
2025), https://www.defensedaily.com/updatedsentinel-acquisition-strategy-in-works-emdapproval-goal-early-to-mid-2027/air-force/ . . . . . 14-15
David Wright & Cameron Tracy, Hypersonic
Weapons Are Mediocre. It’s Time to Stop
Wasting Money on Them., Bulletin of the Atomic
Scientists (Mar. 12, 2024), https://thebulletin.
org/2024/03/hypersonic-weapons-are-mediocreits-time-to-stop-wasting-money-on-them/ . . . . . . . . 18
1
INTEREST OF AMICI CURIAE1
Amici are commercial technology suppliers and policy
organizations who study federal procurement. Their work
directly addresses the commercial-item enforcement gap
this case presents. Amici have compiled and submit empirical
evidence that quantifies the prevalence and economic impact
of noncompliance with commercial-item mandates and
demonstrates the importance of this Court’s review.
The Foundation for American Innovation is a think
tank whose mission is to develop technology, talent, and
ideas that support a better, freer, and more abundant
future. Its policy team focuses on issues at the intersection
of innovation, governance, and national security, including
regulatory barriers that prevent cutting-edge technology
from serving government needs.
T he A l l iance for Commercia l Technolog y i n
Government represents commercial technology companies
seeking to supply the Department of Defense. The Alliance
advocates for acquisition regulation changes that enable
commercial suppliers to compete on commercial terms.
Snowf lake, ASTi, Makpar Corporation, Foxtrot
Professional Services, Gallatin AI, and NEXA are
commercial suppliers facing the barriers this case
addresses. Snowflake Inc. is a large, publicly traded
(NYSE: SNOW) cloud-based AI and data company. ASTi
1. No counsel for any party authored this brief in whole or in
part. No party, counsel, or person other than Amici and their counsel
contributed money to fund the preparation and submission of this
brief. Timely notice of the intent to file this amicus brief was provided
to all parties by October 24 via email.
2
has supplied commercial-off-the-shelf communications
and sound systems to military training for 36 years but
faces explicit exclusion from larger DoD deployments
despite evidence its solutions could save hundreds of
millions of taxpayer dollars. Makpar has delivered federal
IT solutions since 2008, earning recognition including Inc.
5000 and federal program awards for cloud engineering,
cybersecurity, and data analytics work. Foxtrot provides
data platform implementations to federal agencies.
Gallatin AI develops AI-native logistics decision-support
software for defense customers. NEXA supplies missiongrade mobile devices plus end-to-end device lifecycle and
managed services to defense customers. All six compete
for government contracts where agencies may impose
requirements that violate commercial-item mandates and
remove their opportunity to fairly compete.
Shield Capital is a venture capital firm investing
across artificial intelligence, autonomy, cybersecurity,
and space. SHIELD supports entrepreneurs addressing
the convergence of commercial technology and national
security.
Amici file this brief because the issues presented
affect their ability to serve the national defense and
because commercial procurement reform is central to
maintaining America’s technological advantage.
SUMMARY OF ARGUMENT
This case asks whether 28 U.S.C. § 1491(b)(1)—which
authorizes suit by an “interested party” over “any alleged
violation of statute or regulation in connection with a
procurement or a proposed procurement”—permits
3
challenges to post-award statutory violations by all parties
with a provable harm derived therefrom. The Federal
Circuit held that it does not, limiting such standing to
actual or prospective bidders, regardless of the fact
that the language of the statute itself contains no such
limitation. This holding should be overturned.
Reviewing the question is critical because of the
widespread noncompliance with Congress’s commercialprocurement mandates. This noncompliance occurs chiefly
after contract award, when the lower court’s holding now
bars most standing. Two common failures show the effects
of noncompliance: first, agencies under-research the market
and default to custom development instead of buying
existing commercial items, adding years to procurement
cycles; second, agencies reimpose government-unique
clauses on purportedly commercial purchases, deterring
entry and causing an exodus among defense suppliers.
Under the lower court’s ruling, these post-award violations
have no private enforcement mechanism.
The legal theory is straightforward and rooted in
text and structure. Congress used “any” and modified the
object with “in connection with a procurement,” language
that reaches the procurement lifecycle—not just the
moment of award. The third prong’s separate reference to
“a procurement” would be surplusage if suits were limited
to bidders contesting a specific award. And Congress
chose “interested party,” not “bidder” or “offeror,” terms
it uses elsewhere when it means to confine standing. The
familiar limits still apply: Article III’s injury, causation,
and redressability; the zone-of-interests test; and the
requirement to plead a concrete statutory violation,
such as inadequate market research or improper clause
4
imposition. Recognizing prong-three standing preserves
those brakes and channels litigation to parties with direct
economic injury who can supply record-based proof.
Certiorari is warranted. The en banc court split
7–4 on a recurring topic central to federal procurement
performance. The Federal Circuit’s exclusive jurisdiction
prevents percolation; in the absence of review, it is the
last word. The issue carries existential consequences for
commercial defense contractors and presents a clean legal
question of statutory interpretation that this Court can
resolve within established standing doctrines. The Court
should grant the petition.
ARGUMENT
I.
FORT Y Y EA R S OF CONGRES SIONA L
REFORM HAVE FAILED DUE TO A SYSTEMIC
ENFORCEMENT GAP THAT THREATENS
NATIONAL SECURITY
The Federal Circuit’s ruling in Percipient.ai, Inc.
v. United States caps off decades of court and agency
decisions undermining Congress’s attempts to bring
commercial vendors into federal procurement. No. 23-1970,
2025 U.S. App. LEXIS 22128 (Fed. Cir. Aug. 28, 2025) (en
banc). For forty years, Congress has commanded agencies
to buy commercial products. For forty years, agencies
have evaded that command. The consequences have been
dire: tens of billions of dollars in waste, thousands of
exited suppliers, and an almost twelve-year major project
acquisition timeline. Now, the Federal Circuit’s opinion is
set to make enforcing these commands nearly impossible
by nontextually limiting prong three standing to those
least likely to challenge violations.
5
A.
Congress Envisioned a Procurement Revolution
That Would Harness Commercial Innovation
for National Defense
Congress launched its first effort at commercialprocurement reform in 1984. The impetus was clear:
government acquisition had become a spectacle of
waste, particularly at the Department of Defense (DoD).
A Navy hammer cost $436; an Air Force plastic cap,
$1100; and a single diode—available elsewhere for four
cents—$110. 2 The 1982 Grace Commission calculated
that DoD procurement savings over only 3 years could
be $7.33 billion. 3 In response to the commission, in July
1984, Congress passed the Competition in Contracting Act
(CICA), with a stated goal of ensuring that government
contracts were awarded “using full and open competition.”
Pub. L. No. 98-369, Div. B, Title VII, §§ 2701–2753, 98
Stat. 1175 (1984).
Despite the passage of CICA, waste continued to
pile up. So, in 1994, Congress passed the most ambitious
procurement reform in modern history, the Federal
Acquisition Streamlining Act. FASA had a simple
premise: the government would buy from the same
companies that serve commercial markets, using the
same streamlined practices that make those markets
2. John E. Jackson, The $436 Hammer: A Laughing Matter?,
Proceedings (U.S. Naval Inst.) (Dec. 1985), https://www.usni.org/
magazines/proceedings/1985/december/436-hammer-laughingmatter. U.S. Naval Institute.
3. Grace Commission Recommendations: Hearing Before the
S. Comm. on Finance, 98th Cong., S. Hrg. No. 98‑744, at 46 (1984),
https://www.finance.senate.gov/imo/media/doc/HRG98-744.pdf.
6
efficient. No longer would commercial companies need
to maintain separate production lines, quality systems,
or accounting structures to serve federal buyers. To
achieve this goal, Congress created a parallel acquisition
pathway—Federal Acquisition Regulation Part 12—that
exempted commercial purchases from over thirty unique
government requirements.4
FASA included a detailed statutory scheme for
ensuring adherence. It created mandatory commercialitem preferences codified at 10 U.S.C. § 3453 (formerly
10 U.S.C. § 2377), which used the word “shall” ten times.
See Kingdomware Techs., Inc. v. United States, 579 U.S.
162, 171 (2016) (rejecting the VA’s “may” construction
and holding that Congress’s use of “shall” in 38 U.S.C.
§ 8127(d) imposes a mandatory, non-discretionary duty).
It also requires agencies to: (1) conduct market research
before developing requirements (§ 3453(c)); (2) define
requirements to permit commercial solutions (§ 3453(a));
(3) acquire commercial items “to the maximum extent
practicable” (§ 3453(b)); (4) “require” prime contractors
to incorporate commercial components (§ 3453(b)(2)); and
(5) “ensure” primes conduct market research for contracts
exceeding $5 million (§ 3453(c)(5)).
The statutory scheme recognized a specific market
failure: prime contractors managing large integrated
procurements lack incentive to seek commercial
components that would displace their own profitable
development work. Subsections (b)(2) and (c)(5) thus
4. Federal Acquisition Regulation; Acquisition of Commercial
Items, 60 Fed. Reg. 48,231, at 48,246–47 (Sept. 18, 1995), https://
www.govinfo.gov/content/pkg/FR-1995-09-18/pdf/95-22778.pdf.
7
impose post-award obligations—agencies must ensure
primes research and use commercial alternatives even
after contract award. This obligation targets the precise
moment when agency oversight weakens and contractor
self-interest peaks.
Congress reinforced these mandates repeatedly
in national security contexts. The National Defense
Authorization Act for Fiscal Year 2009 required defense
agencies to “identify and evaluate opportunities for the
use of commercial computer software” at “all stages
of the acquisition process.”5 Multiple NDAAs further
strengthened § 3453—adding training (FY2016), pricing
market-research (FY2017), terminology and conforming
changes (FY2019), clarifications (FY2020), recodification
(FY2021), and, most recently, a directive to reward riskinformed decisions maximizing commercial acquisition
(FY2025). 10 U.S.C. § 3453; Pub. L. 114-92 § 844(a), 129
Stat. 915 (2015); Pub. L. 114-328 § 871, 130 Stat. 2307
(2016); Pub. L. 115-232 § 836(d)(3), 132 Stat. 1866, 1868
(2018); Pub. L. 116-92 § 818(a), 133 Stat. 1488 (2019); Pub.
L. 116-283 § 1821, 134 Stat. 4195 (2021); Pub. L. 118-159
§ 834, 138 Stat. 1986 (2024). Additionally, an Executive
Order in 2025 mandated removal of regulatory barriers
to commercial suppliers.6 The statutory text, legislative
history, and subsequent enactments make clear Congress’s
intent: commercial items first, development only when
commercial solutions are genuinely unavailable.
5. Defense Acquisition Regulations Sys., Defense Federal
Acquisition Regulation Supplement; Limitation on Procurements
on Behalf of the Dep’t of Def., 74 Fed. Reg. 34,270, at 34,270 (July
15, 2009), https://www.govinfo.gov/content/pkg/FR-2009-07-15/pdf/
E9-16668.pdf.
6. Exec. Order No. 14,271, 90 Fed. Reg. 16,433 (Apr. 18, 2025).
8
B. Agencies Gutted That Vision Th rough
Reinterpretation And Regulatory Accretion
Agencies quickly got to work overriding Congress’s
intent in order to preserve the status quo. The pattern
was consistent. Congress exempted commercial purchases
from government-unique requirements, so agencies
created parallel procedures to restore those requirements
under different names. Congress expanded the scope of
what counted as commercial items, so agencies imposed
procedural barriers that ensured this expansion would
be rarely applied. Today, nominally commercial contracts
bear enormous compliance burdens that Congress
had explicitly eliminated; and agencies treat statutory
commands as suggestions subject to their discretion.
The cost-data exemption illustrates the pattern
pa r ticula rly well. Cong ress explicitly exempted
commercial acquisitions from Truth in Negotiations Act
requirements—the “certified cost or pricing data” that
forced vendors to maintain government-unique accounting
systems. 41 U.S.C. § 3503 . The FAR mirrored that
command: contracting officers “shall not require certified
cost or pricing data” for commercial purchases. 48 C.F.R.
§ 15.403-1(b)(3).
But agencies built a workaround. The 1997 FAR Part
15 rewrite, led by the agencies themselves, authorized
contracting officers to demand “data other than” certified
cost or pricing data to establish price reasonableness—cost
breakdowns, sales records, internal estimates, etc.7 The
7. Federal Acquisition Reg ulation; Part 15 Rew r ite —
Contracting by Negotiation & Competitive Range Determination,
9
category was blessed by Congress to ensure procurement
at a “fair and reasonable price”, but the details were not.
10 U.S.C. § 3705(a). In fact, the information burden the
agencies created was functionally identical to the certified
cost packages Congress had prohibited. As 48 C.F.R.
§ 2.101 points out, in some cases the similarity has become
more than functional, stating explicitly that “[s]uch data
may include the identical types of data as certified cost
or pricing data.”
The DoD has been particularly effective at stymieing
Cong ressional mandates. For example, Cong ress
broadened the commercial-item definition to include items
“of a type” customarily used commercially and items
“offered” but not yet sold. 41 U.S.C. § 103(1)(A)–(B). The
DoD implemented this definition through DFARS 212.102,
which requires extra approval—“one level above the
contracting officer”—whenever determinations rely on a
category in the broader definition. 48 C.F.R. § 212.102(a)(1)
(C). Acquiring this approval is procedurally burdensome,
leading to commentary stating “documenting [commercial
items] has become so burdensome and fraught with risk, it
discourages contractors from buying commercial items or
treating commercial items as such.”8 Some requirements
have no commercial analogue whatsoever. DFARS
252.204-7012 mandates implementation of 110 NIST
cybersecurity controls and seventy-two-hour incident
62 Fed. Reg. 51,224, at 51,251 (Sept. 30, 1997), https://www.govinfo.
gov/content/pkg/FR-1997-09-30/pdf/97-25666.pdf.
8. Defense Contract Mgmt. Agency, DCMA CIG Industry
Day (Feb. 20, 2020) (slide deck), https://www.dcma.mil/Portals/31/
Documents/CIG/DCMA%20CIG%20Industry%20Day%20slides%20
20%20February%202020.pdf.
10
reporting—requirements vastly more burdensome than
those commercial customers demand. 48 C.F.R. § 252.2047012(b)(2); 48 C.F.R. § 252.204-7012(c)(1)(ii); Dep’t of Def.,
Class Deviation 2024-O0013 (May 2, 2024).
On their own, each of the above changes could
potentially be justified as policy, if not on textual grounds.
The needs for pricing accuracy, quality assurance,
and security are pressing. But Congress has spoken.
Commerciality is to be the goal, and, cumulatively, these
additions have buried it. If “to the maximum extent
practicable” is to hold any meaning at all, then it must
take priority over other considerations.
C.
The Section 809 Panel Documented How Far
Agencies Had Strayed From The Text
By 2016, Congress could no longer ignore the size
of the gap between statutory text and actual practice. A
2009 GAO review had found nearly 19% of commercial
contracts were in fact not commercial at all.9 A further
2014 study found that half of contracts had inadequate
market research documentation.10 To get to the bottom
of this gap, Congress chartered the Section 809 Panel to
9. U.S. Gov’t Accountability Off., Contract Management:
Minimal Compliance with New Safeguards for Time‑and‑Materials
Contracts for Commercial Services and Safeguards Have Not Been
Applied to GSA Schedules Program, GAO‑09‑579, at 28 (2009),
https://www.gao.gov/assets/gao-09-579.pdf.
10. U.S. Gov’t Accountability Off., Market Research: Better
Documentation Needed to Inform Future Procurements at Selected
Agencies, GAO‑15‑8, at 14 (2014), https://www.gao.gov/assets/gao15-8.pdf.
11
document how commercial procurement had failed at the
DoD. Over three years, the Panel produced nearly 2,000
pages documenting the extent of the non-compliance.
The Panel identified 109 clauses—54 in FAR, 55 in
DFARS—that the DoD was imposing on commercial
contracts in direct violation of FASA’s statutory criteria
for when government-unique terms could be added.11
109 clauses out of a total of 165. Nearly two thirds of the
clauses included in commercial defense procurement
contracts were illicitly added.
Expert commentary on the panel found that the
processes for determining whether a procurement
should be commercial had become “so unwieldy that they
sometimes consume even more time and paperwork than
the traditional development contracts that are designed
for military-unique systems.”12 The Panel “recommended
the [109] clauses…be removed” to restore commercial item
contracting to the original intent—laid out in FASA.13 As
of 2025, the status quo has prevailed and most remain.
11. Advisory Panel on Streamlining & Codifying Acquisition
Regulations (Section 809 Panel), Report of the Advisory Panel on
Streamlining and Codifying Acquisition Regulations, vol. 1 of 3, at
A‑41 (Jan. 2018), https://discover.dtic.mil/wp-content/uploads/809Panel-2019/Volume1/Sec809Panel_Vol1-Report_Jan2018.pdf.
12. Jared Serbu, Section 809 panel’s final report prescribes
“revolutionary” changes to DoD buying, Federal News Network (Jan.
15, 2019), https://federalnewsnetwork.com/acquisition-policy/2019/01/
section-809-panels-final-report-prescribes-revolutionary-changesto-dod-buying/.
13. Section 809 Panel, Vol. 1 Report, at A‑41 (Jan. 2018).
discover.dtic.mil
12
Despite these documented violations spanning
thousands of contracts and billions of dollars of waste,
“the application of 10 U.S.C. § 2377 has not often been
addressed…in the context of a bid protest.” Analytical
Graphics, Inc. v. United States, 135 Fed. Cl. 378, 424 (2017).
Standing doctrine ensures that there is no mechanism
to challenge violations post-award where incentives are
weakest, so enforcement is effectively nonexistent. The
statute had teeth in theory. In practice, it has none.
D.
The Empirical Consequences Of
Nonenforcement Have Been Stark
Decades of this nonenforcement have taken a toll on the
defense ecosystem. Agencies’ evasion of commercial-item
mandates has produced twelve-year delivery timelines,
billions in waste, and an exodus of small businesses from
the defense market. With the en banc court’s decision in
Percipient.ai set to further foreclose review, these harms
will accelerate unchecked.
D1. Skipping Market Research Adds Years of
Delay and Billions in Cost
As previously stated, GAO has repeatedly found that
agencies provide inconsistent or inadequate marketresearch documentation. Without such documentation,
which informs the agency about the scope of offerings
and modifications available, agencies cannot determine
whether feasible commercial alternatives exist. Without
that determination, agencies cannot satisfy the “maximum
extent practicable” standard. Instead, they acquire blindly
and default to custom development. The consequences for
delivery timelines have been predictably bad:
13
Product14 Commercial DoD Custom
Cycle
Development
Delay
Added
Vehicles
2 years
4.6 years
~2.5 years
Drones
~1 year15
3.8–15.3 years16
~3–14 years
Satellite
1.5-3 years17 8.8 years
~6–7 years
14. Unless otherwise cited, all data on the chart is from Alec C.
Blivas, Brenen Tidwell & Morgan Dwyer, Cycle Times and Cycles
of Acquisition Reform, CSIS Briefs (Aug. 5, 2020), https://www.csis.
org/analysis/cycle-times-and-cycles-acqu isition-reform.
15. Ben, Complete DJI Drone History & Release Date Timeline
(2013–2025), Gadgets N Tech (Oct. 14, 2025), https://gadgets-n-tech.
com/complete-dji-drone-history-release-dat e-timeline/.
16. On the low end, RQ-28A Short-Range Reconnaissance drone
at 3.8 years (Nov 2018 - Sep 2022), at the high-end, there is MQ-4C
Triton at 15.3 years.
Tajha Chappellet-Lanier, Army, Defense Innovation Unit
Move Forward With Surveillance Drone Project, FedScoop
(Apr. 29, 2019), https://fedscoop.com /army-diu-short-rangereconnaissance-drones-award / (repor ting DIU solicitation
issued Nov. 2018); U.S. Army, New Short Range Reconnaissance
Capability Begins Fielding to Soldiers (Oct. 12, 2022), https://
www.army.mil/article/261063/new_short_range_reconnaissance_
capability_begins_fielding_to_soldiers (last visited Nov. 4, 2025).
U.S. Navy, NAS Sigonella Welcomes First MQ-4C Triton (Apr. 1, 2024)
(noting VUP-19 achieved initial operational capability in Sept. 2023),
https://www.navy.mil/Press-Office/News-Stories/Article/3725909/nassigonella-welcomes-first-mq-4c-triton/; Northrop Grumman, U.S. Navy
Awards $1.16 Billion BAMS UAS Contract to Northrop Grumman
(Apr. 22, 2008), https://investor.northropgrumman.com/news-releases/
news-release-details/us-navy-awards-116-billion-bams-uas-contractnorthrop-grumman (last visited Nov. 4, 2025).
17. All SpaceX major satellite model refreshes, v1 Nov 2019,
v1.5 Sep 2021, v2 Feb 2023, v3 exp. early 2026, List of Starlink and
14
These multi-year custom development projects lead
to skyrocketing costs and technological obsolescence by
delivery. And that development has itself elongated over
time. From the turn of the millennium to today, GAO has
reported an increase in time-to-deployment of over 40
months—from 103 to 144 months.18 From 2024 to 2025,
the cost of thirty major defense acquisition programs
reviewed by the GAO increased by $49.3 billion.19 That is
an increase of nearly $50 billion in one year attributable
to less than half of the 79 total programs. 20 The method
of failure is simple. The DoD grants a large contract to a
prime, who—safe in the knowledge that standing doctrine
protects them from relevant complaints—prioritizes
internal development while blowing past the original
deadline and racking up billions in extra costs.
Examples abound. Development on the Sentinel ICBM
started in 2020 with a targeted 2029 deployment but
delivery has already been pushed to 2033—a four year
slip in five years. 21 The F-35 fighter started in 1996, with
Starshield launches, Wikipedia (last visited Oct. 31, 2025), https://
en.wikipedia.org/wiki/List_of_Starlink_and_Starshield_launches.
18. U.S. Dep’t of Def., Performance and Accountability Report,
Fiscal Year 2003, at 36 (Dec. 23, 2003), https://comptroller.war.gov/
Portals/45/Documents/afr/fy2003/00_Entire_Document.pdf.
19. U.S. Gov’t Accountability Office, Defense Acquisition
Reform: Persistent Challenges Require New Iterative Approaches
to Delivering Capability with Speed, at 5 (June 11, 2025), https://
www.gao.gov/assets/880/879068.pdf.
20. Id. at 2.
21. Frank Wolfe, Updated Sentinel Acquisition Strategy in
Works; EMD Approval Goal Early to Mid-2027, Defense Daily
15
initial deployment to be spread between 2012-2015. 22 In
reality, rollout did not conclude until 2019. 23 Even now,
its Block 4 modernization is five years late and billions
over budget. 24 MHS GENESIS, DoD’s electronic health
record system, started in 2015 and took nearly a decade
to reach enterprise rollout. 25 By comparison, commercial
electronic health records typically deploy in eighteen to
twenty-four months. 26
Experience in Ukraine has shown that Congress’s
mandates can work if allowed. Prior to Russia’s 2022
invasion, Ukraine had a custom-development focused
(Sept. 23, 2025), https://www.defensedaily.com/updated-sentinelacquisition-strateg y-in-works- emd-approval-goal- early-to mid-2027/air-force/.
22. Cong. Research Serv., F-35 Joint Strike Fighter (JSF)
Program: Background and Issues for Congress, at 8 (Dec. 22, 2009),
https://www.everycrsreport.com/files/20091222_RL30563_4e4c38f
6c1371c17b92fa2c7cc25a9c2aeae8df6.pdf.
23. U.S. Pac. Fleet, F-35C Achieves Initial Operational
Capability (Feb. 28, 2019), https://www.cpf.navy.mil/Newsroom/
News/Article/2664405/f-35c-achieves-initial-operational-capability/.
24. U.S. Gov’t Accountability Office, F-35 Joint Strike Fighter:
Actions Needed to Address Late Deliveries and Improve Future
Development, at 1 (Sept. 2025), https://www.gao.gov/assets/gao25-107632.pdf.
25. Adam Mazmanian, DoD Plans $1.4B Sole-Source Extension
for Leidos on Health Care Record, Nextgov/FCW (Oct. 23, 2024),
https://www.nextgov.com/acquisition/2024/10/dod-plans-14b-solesource-extension-leidos-health-care-record/400501/.
26. David Pumphrey, Tick‑Tock: How to Perfect Your EMR
Implementation Timeline, RiverAxe (Apr. 30, 2025), https://riveraxe.
com/emr-implementation-timeline/.
16
procurement system like our own. However, when faced
with mortal danger, they quickly pivoted to a commercialfirst system. Reports state that with this new commercial
focus, Ukraine has “reduce[d] timelines from years to
months—even weeks.” 27 Drone companies have scaled
from dozens to hundreds in two years, and electronicwarfare countermeasures are deployed within weeks of
new Russian threats. 28 The United States, by contrast,
averages nearly twelve years to deployment and delivers
obsolete technology.
D2. Uncontrolled Clause Proliferation Drove
Out Thousands of Vendors
Through their actions, agencies drove out tens of
thousands of vendors between FY2011 and FY2021—a
43 percent decline from 42,723 to 24,296. 29 First-time
27. Ctr. for Strategic & Int’l Stud., How Ukraine Rebuilt Its
Military Acquisition System Around Commercial Technology, at
2 (Jan. 2025), https://csis-website-prod.s3.amazonaws.com/s3fspublic/2025-01/250113_Bondar_Ukraine_Acquisition.pdf.
28. Compare Pavel Polityuk & Olena Harmash, Ukraine to
Produce One Million Drones Next Year, Reuters (Dec. 19, 2023),
https://w w w.reuters.com/world/europe/ukraine-produce-onemillion-drones-next-year-zelenskiy-says-2023-12-19/, with Yuliia
Dysa & Olena Harmash, Zelenskiy Woos US Businesses, Seeks
to Grow Ukraine’s Drone Industry, Reuters (Sept. 25, 2025),
https://www.reuters.com/business/zelenskiy-woos-us-businessesseeks-grow-ukraines-drone-industry-2025-09-25/, and Aosheng
Pusztaszeri & Emily Harding, Technological Evolution on the
Battlefield, Ctr. for Strategic & Int’l Stud. (Sept. 16, 2025), https://
www.csis.org/analysis/chapter-9-technological-evolution-battlefield.
29. U. S. Gov’t Accountability Off ice, Small Business
Contracting: Actions Needed to Implement and Monitor DOD’s
17
contractors across all agencies dropped 59 percent during
the same period.30 Defense prime contractors consolidated
from 51 in the 1990s to 5 today—a 90 percent contraction.31
Suppliers have exited precisely as AI, autonomy, cyber,
and advanced computing shifted to commercial leadership.
Roughly three-quarters of global R&D now occurs in the
commercial sector, but U.S. acquisition barriers impede
DoD access to that know-how. 32
Adding dozens of clauses to commercial contracts
since 1995 has raised regulatory burdens to uneconomical
levels, driving commercial firms from defense markets
and violating Congress’s mandate to utilize commercial
suppliers under § 3453. Reports support this thesis, with
the Section 809 Panel labelling these clauses as “barriers”
and a 2017 GAO survey where eleven of twelve companies
cited “government specific contract terms and conditions”
as a key challenge in supplying the defense market. 33
Small Business Strategy, at 8 (Oct. 2021), https://www.gao.gov/
assets/gao-22-104621.pdf.
30. Sarah Treuhaft et al., Fewer and Fewer Small Businesses
Are Getting Federal Contracts, National Equity Atlas (Sept. 28,
2021), https://nationalequityatlas.org/federalcontracts.
31. U.S. Dep’t of Def., State of Competition within the Defense
Industrial Base, at 1 (Feb. 2022), https://media.defense.gov/2022/
feb/15/2002939087/-1/-1/1/state-of-competition-within-the-defenseindustrial-base.pdf.
32. OECD, OECD Main Science and Technology Indicators:
Highlights from the March 2024 Edition, at 1 (Mar. 2024), https://
www.oecd.org/content/dam/oecd/en/data/datasets/main-scienceand-technology-indicators/msti-highlights-march-2024.pdf.
33. U.S. Gov’t Accountability Office, Military Acquisitions:
DOD Is Taking Steps to Address Challenges Faced by Certain
18
Comparisons with our rivals are stark. Senior
acquisition leaders have testified that China achieves
similar capability at a fraction of U.S. costs. Notably,
China has fielded multiple hypersonic systems while the
United States spent over $10 billion without a fielded
system during the same period. 34 Even the former head
of Air Force procurement is on record stating “China is…
about five to six times faster than us in acquisition.” China
is able to take full advantage of its commercial business
ecosystem, but due to enforcement failures, we cannot.
E. The En Banc Holding Would Remove the Last
Available Brake on Nonenforcement
The Federal Circuit’s en banc holding threatens
to eliminate standing for the only party incentivized
to remedy these commercial item violations. If left
untouched, it will ensure that only prospective prime
bidders retain standing—yet they have the least incentive
to enforce commercial requirements. This mismatch will
make the commercial item preference a dead letter.
The Federal Circuit has already ruled in Palantir
USG, Inc v. United States, 904 F.3d 980 (Fed. Cir. 2018),
that prospective commercial offerors who can meet
the requirements of a solicitation have standing under
Companies, at 9 (July 2017), https://www.gao.gov/assets/gao-17-644.
pdf.
34. David Wright & Cameron Tracy, Hypersonic Weapons Are
Mediocre. It’s Time to Stop Wasting Money on Them., Bulletin of the
Atomic Scientists (Mar. 12, 2024), https://thebulletin.org/2024/03/
hypersonic-weapons-are-mediocre-its-time-to-stop-wasting-moneyon-them/.
19
§ 1491(b). In that case, Palantir filed a pre-award bid
protest challenging the army’s solicitation, before it had
awarded the contract. It is also well-established that a
prospective bidder may lodge a pre-award GAO protest
on the grounds that a solicitation failed to conduct the
required market research. See Triad Isotopes, Inc.,
B-411360, 2015 CPD ¶ 220 (Comp. Gen. July 16, 2015) (preaward; sustained—set-aside based on inadequate market
research). So it is true that failure to properly adhere to
commercial item requirement duties creates standing for
those otherwise able to bid—at least pre-award.
When the duty completes prior to the award, as in
Palantir, this standing is sufficient. In that circumstance,
the prospective bidder can point directly to the failure
causing the harm before the award is granted. However,
any commercial offeror that can only fulfill a future
portion of the contract—even though equally supported
by the statutory language—is out of luck.
Because of their contract-then-subsequent-task-order
structure, indefinite delivery, indefinite quantity (IDIQ)
contracts such as the one in Percipient.ai provide a
particularly clear illustration of the problem. When these
contracts are awarded, the task specifics are not often
clear (hence, “indefinite”). Scope, quantities, and delivery
schedules are examples of categories often left for the
future. Nonetheless, Congress structured commercial-item
duties to be ongoing, continuing after the contract award,
even after the government issues each individual task order.
In theory then, commercial offerors simply need to wait for
these details to be released and then compete. But by that
point they can’t enforce their rights.
20
Traditionally, pre-award challenges to ongoing duties
do not have standing, as the prospective failure of duty
only exists in the future. But under the en banc court’s
opinion, post-failure challenges also have no standing.
This is because the commercial duty exists in the present,
but the court applies the “actual or prospective offeror”
standing test—which adheres to the contract awarded
in the past. To meet this bar would require the offeror
to be not just prospective, but clairvoyant. As a result,
§ 1491(b) standing requirements under the lower court’s
opinion may reasonably be stated as: If an agency
specifies exactly how a contract should be undertaken,
pre-award protests are available to commercial offerors;
but if the agency does not provide specifics, no protest
is available at all. This standard rewards agencies for
misbehavior and leaves potential plaintiffs like Percipient
fully standing-barred—regardless of whether they can
prove harm.
Under this holding, the only parties left with standing
to enforce the duty will be prospective prime bidders
on base contracts, the very people who § 3453 foists
commercial item preferences onto. But prime bidders
benefit from non-compliance. Custom development
delivers higher margins, creates vendor lock-in, and
eliminates competition. Non-compliance serves their
economic interests, and without standing, no outside party
is available to force compliance.
Commercial item vendors have the opposite incentives.
They suffer direct economic injury when agencies ignore
commerciality mandates. They lose sales, face improper
technical data requirements, and watch procurement
timelines stretch beyond their planning horizons. These
vendors would enforce the statute.
21
The parties who would enforce cannot sue. The parties
who can sue will not. The documented failures—109 noncompliant clauses, 50% inadequate market research, 40%
supplier exit, twelve-year timelines—persist because
doctrine creates an enforcement vacuum. As agency use
of IDIQ contracts continues to grow beyond 50% of all
government procurement dollars, these problems are set
to get worse. 35 If the en banc holding stands, forty years
of congressional reform will fall.
II. THE SUPREME COURT SHOULD GRA NT
CERTIORARI TO ADDRESS ERROR ON AN
IMPORTANT FEDERAL QUESTION
By itself, the erosion of America’s defense-industrial
base would not justify the grant of certiorari. What makes
it appropriate in this case is that the Federal Circuit’s
opinion is grounded in a serious error of statutory
interpretation, which fails to give proper consideration
to the plain meaning of the language in the Tucker Act.
A.
Textual Canons Strongly Suggest Differential
Standing for Prong 3 Challenges
The procedural history of this litigation is complex,
but the core legal task is a simple and familiar textual
exercise: statutory interpretation. Who is an “interested
party” in the context of the Tucker Act? To wit:
Both the United States Court of Federal Claims
and the district courts of the United States
35. Coalition for Gov’t Procurement, Market Report: The
State of the Federal Market, at 4 (May 2024), https://thecgp.org/
images/2024/06/23-Market-Report-2.pdf.
22
shall have jurisdiction to render judgment
on an action by an interested party objecting
to a solicitation by a Federal agency for bids
or proposals for a proposed contract or to a
proposed award or the award of a contract or
any alleged violation of statute or regulation
in connection with a procurement or a
proposed procurement. (emphasis added, note
district court authority has sunset). 28 U.S.C.
§ 1491(b)(1)
Established textual canons make clear that the
Federal Circuit erred in its limitation of “interested
party” to actual and prospective bidders, and support
the broader interpretation that anyone with “a ‘direct
economic interest [that] would be affected by the
[challenged §1491(b)(1) action]’” has standing under the
law. Percipient.ai, Inc. v. United States, No. 23-1970, 2025
U.S. App. LEXIS 22128, at 48 (Fed. Cir. Aug. 28, 2025)
(Stoll, J., dissenting).
Three principles form the basis for this conclusion.
First, the “text must be construed as a whole…Context is
a primary determinant of meaning.”36 The Federal Circuit
departs from this principle in its review, instead importing
an “interested party” definition from an entirely separate
statute – the Competition in Contracting Act (CICA). This
is then dogmatically applied to the three prongs of the
Tucker Act with little regard to the context of the prongs
themselves. Indeed, to justify this transplantation, the
36. Antonin Scalia & Bryan A. Garner, Reading Law: The
Interpretation of Legal Texts 167 (Thomson/West 2012).
23
Federal Circuit opinion spends fourteen pages recounting
a dense legislative history before ever examining the text
of the statute itself.
This exercise is unnecessary. “We have stated time
and again that courts must presume that a legislature says
in a statute what it means and means in a statute what it
says there…When the words of a statute are unambiguous,
then…‘judicial inquiry is complete.’” Conn. Nat’l Bank
v. Germain, 503 U.S. 249, 253–54 (1992). The words of
the Tucker Act are clear. The context of “an interested
party” shows it to simply mean a potential plaintiff with
a harm derived from “any alleged violation of statute or
regulation in connection with a procurement or proposed
procurement.” No limitation is express or implied.
Second, the plain language of the Tucker Act suggests
an expansive reading. The statute grants standing to “an
interested party objecting to…any alleged violation of
statute or regulation in connection with a procurement
or a proposed procurement (emphasis added)”. “Any”
statute or regulation is necessarily broad, and implies
a broader scope of parties than those that are actual or
prospective bidders. See United States v. Gonzales, 520
U.S. 1, 5 (1997) (“Read naturally, the word ‘any’ has an
expansive meaning.”). It stretches believability to think
that Congress expressly calls out such a wide scope of
violations only to silently limit such a rule to bidders.
Third, the presumption against surplusage also makes
the meaning of “interested party” clear. The third prong
of the Tucker Act makes explicit that it is intended to allow
interested parties to challenge violations related to “a
procurement or proposed procurement”. If we are to “give
24
effect, if possible, to every clause and word of a statute”
then it is unclear why Congress would have specifically
called out procurements where it earlier references
awards and proposed awards in prong 2. “Procurement”
refers to the entire lifecycle of the process for acquiring
goods and services for the government – identifying needs,
scoping requirements, establishing budgets, soliciting
for bids, awarding contracts, and all other steps from
beginning to end.
The plain language supports the conclusion that
litigants like Percipient have standing. At the very least,
the sharp 7-4 division within the Federal Circuit in its en
banc review indicates the need for clarification, one that
only the Supreme Court can provide.
B. “Floodgate” Concerns Are Speculative
The Government has offered the concern that a finding
that litigants have standing to bring Prong 3 challenges
if they are “someone with a ‘direct economic interest
[that] would be affected by the [challenged §1491(b)(1)
action]’” will open the floodgates to costly and frivolous
litigation. “Permitting unrelated third parties who had no
involvement in the competitive process to interfere with
the performance of ongoing contracts under the guise of
bid protest review would threaten to destabilize every
Government contract.” Br. of Def.-Appellee United States
at 35–6, No. 23-1970 (Fed. Cir. Apr. 4, 2025).
We would challenge this premise. For one, a party
seeking to challenge a procurement or proposed
procurement must still show an actual competition injury
25
stemming from a specific ongoing duty. Similarly, plaintiffs
must offer facts indicating that the statutory violation was
the cause of such injury. For example, showing how the
inadequate market research harmed their ability to bid.
It is worth noting that, to date, these evidentiary burdens
appear to have limited the number of bona fide litigants
under the Tucker Act significantly: there are a minuscule
number of prong 3 cases which have been brought to
challenge procurements or proposed procurements.
Second, courts continue to apply the standard
machinery of justiciability requirements in allowing a
litigant to pursue a claim against the Government. The
analysis of redressability, ripeness, mootness all continue
to be important considerations, and the decision in this
case does not fundamentally change these Article III and
prudential limits.
Third, providing plaintiffs the standing that they are
intended to have under the Tucker Act does not allow
any party with a grievance to challenge a procurement.
“Direct economic interest” is itself a standard cabined by
the typical zone-of-interests tests. Plaintiffs must show
that their interests align with the statutory purposes
at issue, and remote or tangential interests remain
excluded.
Finally, given the limited universe of applicable
statutes, the primary material outcome of a finding of
standing in this case is that plaintiffs offering actual
commercial products meeting the statutory definition can
object to violations of statutes or regulations in connection
with a procurement or a proposed procurement.
26
C.
The Issues at Stake Implicate Critical Federal
Questions
The grant of certiorari is appropriate when a case
implicates “questions of general importance beyond the
particular facts”. Sup. Ct. R. 10. This is the situation
presented by this case. Ultimately, whether the Supreme
Court grants certiorari in this case will determine the
economic shape of our defense-industrial base, and in
connection our national security.
The involvement of the Court is particularly urgent
in this area since it is one where no split between the
Circuits will be forthcoming. The exclusive jurisdiction of
the Federal Circuit conferred by Administrative Dispute
Resolution Act means that it will serve as the last word
in the absence of review by this Court.
American power has always relied on the dynamism
of its defense industry. This dynamism has in turn relied
on the ability for our nation to draw on a vibrant, highly
competitive commercial ecosystem. For decades, Chrysler,
Ford, and even General Mills were commercial businesses
manufacturing cars and cereal at the same time they
produced missiles, satellites, and guidance systems for
the U.S. military. 37
37. Shyam Sankar, The Defence Reformation: 18 Theses for the
Resurrection of the American Industrial Base, 18Theses.com (Oct.
31, 2024), https://www.18theses.com/.
27
CONCLUSION
The historical record reviewed above in Part I shows
how agency and judicial decisionmaking in past decades
have systematically undermined this dynamism and
given rise to a slow-moving, sclerotic sector resistant to
new entrants. The decision of the Federal Circuit in this
case only compounds this problem by leaving commercial
players with little redress under the law when they are
excluded in violation of the law.
The legal error presented by this case therefore
implicates not just billions of dollars of federal funding
but also offers the question of whether the U.S. shall have
the powerful defense industry it needs in the coming,
dangerous decades. Ensuring that it does begins with the
simple act of guaranteeing that the government complies
with existing law and allows real competition back into
defense procurement. For these reasons, we urge the
Court to grant certiorari in this case.
November 6, 2025
Respectfully submitted,
Erika Payne
Snowflake Inc.
125 Constitution Drive
Menlo Park, CA 94025
Tim Hwang
Counsel of Record
Foundation for
American Innovation
2443 Fillmore Street,
#380-3386
San Francisco, CA 94115
(973) 960-4955
tim.hwang@thefai.org
Counsel for Snowflake, Inc.
and Sridhar Ramaswamy
Counsel for Amici Curiae
APPENDIX
1a
Appendix
APPENDIX — LIST
OF AMICI CURIAE
Warren K atz
Chairman of the Board
The A lliance for Commercial
Technology in Government
Jim Norton
Chairman of the Board
ASTI
K aamil Khan
President and General Counsel
Makpar Corporation
Christine Williams
Co-CEO
Foxtrot Professional Services
Woody Glier
CEO
Gallatin AI
A li Webster
Chief Business Officer
NEXA
Raj Shah
Managing Partner
Shield Capital
This is a copy of a public record, reproduced as it was published. It is not legal advice, and it may not be the version a court would rely on. Check the official source before you cite it.