Opposition Brief — ASG Solutions Corp., dba American Systems Group, Petitioner v. United States
Supreme Court briefSep 11, 2026
Ask Donna
What actually matters in this document.
Text
No. 25-1372
In the Supreme Court of the United States
ASG SOLUTIONS CORP., DBA AMERICAN SYSTEMS
GROUP, PETITIONER
v.
UNITED STATES OF AMERICA
ON PETITION FOR A WRIT OF CERTIORARI
TO THE UNITED STATES COURT OF APPEALS
FOR THE FEDERAL CIRCUIT
BRIEF FOR THE RESPONDENT IN OPPOSITION
D. JOHN SAUER
Solicitor General
Counsel of Record
BRETT A. SHUMATE
Assistant Attorney General
PATRICIA M. MCCARTHY
MARTIN F. HOCKEY, JR.
SHERYL L. FLOYD
Attorneys
Department of Justice
Washington, D.C. 20530-0001
SupremeCtBriefs@usdoj.gov
(202) 514-2217
QUESTION PRESENTED
Whether the Court of Appeals for the Federal Circuit correctly upheld the government’s decision to terminate a contract for default.
(I)
TABLE OF CONTENTS
Page
Opinions below .............................................................................. 1
Jurisdiction .................................................................................... 1
Statement ...................................................................................... 1
Argument....................................................................................... 6
Conclusion ................................................................................... 11
TABLE OF AUTHORITIES
Cases:
College Point Boat Corp. v. United States,
267 U.S. 12 (1925) ................................................................. 8
DCX, Inc. v. Perry, 79 F.3d 132 (Fed. Cir.),
cert. denied, 519 U.S. 992 (1996) ......................................... 5
Department of Transp. v. Eagle Peak Rock &
Paving, Inc., 69 F.4th 1367 (Fed. Cir. 2023) ...................... 7
Empire Energy Mgmt. Sys., Inc. v. Roche,
362 F.3d 1343 (Fed. Cir. 2004) ............................................. 8
FCC v. Prometheus Radio Project,
592 U.S. 414 (2021)................................................................ 8
Lisbon Contractors, Inc. v. United States,
828 F.2d 759 (Fed. Cir. 1987) ............................................... 4
McDonnell Douglas Corp. v. United States,
182 F.3d 1319 (Fed. Cir. 1999), cert. denied,
529 U.S. 1097 (2000)............................................................ 10
Schlesinger v. United States,
390 F.2d 702 (Ct. Cl. 1968) ............................................. 9, 10
Wilner v. United States,
24 F.3d 1397 (Fed. Cir. 1994) ............................................... 2
Statutes, regulation, and rule:
Administrative Procedure Act, 5 U.S.C. 701 et seq.............. 8
(III)
IV
Statutes, regulation, and rule—Continued:
Page
Contract Disputes Act of 1978,
41 U.S.C. 7101 et seq. ............................................................ 1
41 U.S.C. 7103(a)(1) ........................................................... 2
41 U.S.C. 7103(d) ............................................................... 2
41 U.S.C. 7103(e) ........................................................... 2, 7
41 U.S.C. 7104(b)(1) .......................................................... 2
41 U.S.C. 7104(b)(4) ...................................................... 2, 7
48 C.F.R. 49.402-3(f ) ............................................................... 5
Sup. Ct. R. 10 ......................................................................... 11
In the Supreme Court of the United States
No. 25-1372
ASG SOLUTIONS CORP., DBA AMERICAN SYSTEMS
GROUP, PETITIONER
v.
UNITED STATES OF AMERICA
ON PETITION FOR A WRIT OF CERTIORARI
TO THE UNITED STATES COURT OF APPEALS
FOR THE FEDERAL CIRCUIT
BRIEF FOR THE RESPONDENT IN OPPOSITION
OPINIONS BELOW
The opinion of the court of appeals (Pet. App. 1a-8a)
is available at 2025 WL 3627729. The memorandum opinion and order of the Court of Federal Claims (Pet. App.
9a-62a) is reported at 170 Fed. Cl. 485.
JURISDICTION
The judgment of the court of appeals was entered on
December 15, 2025. A petition for rehearing was denied
on March 3, 2026 (Pet. App. 63a-64a). The petition for
a writ of certiorari was filed on June 1, 2026. The jurisdiction of this Court is invoked under 28 U.S.C. 1254(1).
STATEMENT
1. The Contract Disputes Act of 1978 (CDA), 41
U.S.C. 7101 et seq., provides a comprehensive process
for the resolution of government-contracting disputes.
(1)
2
A contractor must submit a claim against the federal
government relating to a contract to the contracting officer for a decision. 41 U.S.C. 7103(a)(1). The contracting officer must then issue a written decision, which
must “state the reasons for the decision reached” and “inform the contractor of the contractor’s rights.” 41 U.S.C.
7103(e); see 41 U.S.C. 7103(d). The decision need not contain any “[s]pecific findings of fact.” 41 U.S.C. 7103(e). If
such findings are made, they “are not binding in any subsequent proceeding.” Ibid.
Upon receipt of the contracting officer’s decision, a
contractor may appeal to the board of contract appeals
or “bring an action directly on the claim in the United
States Court of Federal Claims.” 41 U.S.C. 7104(b)(1).
Such an action “proceed[s] de novo,” with no deference
to the contracting officer’s determinations. 41 U.S.C.
7104(b)(4). “Thus, once an action is brought following a
contracting officer’s decision, the parties start in court
* * * with a clean slate.” Wilner v. United States, 24
F.3d 1397, 1402 (Fed. Cir. 1994) (en banc).
2. On September 28, 2022, petitioner entered into a
contract with the U.S. Navy “to provide engineering
and program-management services to support design
and construction operations at Naval Air Station Jacksonville.” Pet. App. 2a; see id. at 17a-18a. The contract
identified an “ ‘anticipated staff ’ of 20 professionals as
the ‘base/minimum’ level of service required.” Id. at 12a
(citation omitted). The contract provided that within
five days of its award, petitioner must provide the government with a resume for each team member proposed
to perform work under the contract. Id. at 13a-14a. The
government would review the resumes and approve the
proposed personnel to ensure they possessed the necessary qualifications. Id. at 14a. In the event that peti-
3
tioner did not maintain a full complement of 20 team
members, the contract provided that petitioner must
provide replacements within five days. Id. at 15a. If
petitioner failed to do so, the government was entitled
to a unit-price reduction in payment until the full team
was in place. Ibid.
After petitioner was awarded the contract, “[p]roblems arose almost immediately.” Pet. App. 18a. On the
date petitioner was required to submit the 20 resumes
of its proposed team, it submitted only 2. Ibid. Over
the next month, petitioner submitted 8 additional resumes. Id. at 18a-19a. Of the 10 individuals submitted,
4 were rejected by the government for lacking qualifications, and 4 more “declined [petitioner’s] offer, did
not report to work, or quickly resigned.” Id. at 19a.
On November 1, 2022, the government sent petitioner
a letter of concern, notifying petitioner that it was failing to meet contractual requirements by failing to provide the necessary staff. Pet. App. 20a. Petitioner responded by disputing that it was required to maintain a
staff of 20. Ibid. Instead, petitioner asserted that the
contract entitled it to “choose the precise labor and
staffing mix” to perform assignments under the contract. Ibid. In the days that followed that exchange,
petitioner submitted resumes for 4 more professionals,
3 of which the government approved, but only 1 accepted
petitioner’s offer of employment. Ibid.
On December 5, 2022, the government issued a notice
to cure the performance deficiency. Pet. App. 20a. The
government asserted that petitioner’s failure to perform
could justify termination of the contract for default.
Ibid. Petitioner again took the position that the contract
did not require a 20-person team. Id. at 21a. Petitioner
submitted a few additional resumes over the next month.
4
Ibid. On January 20, 2023, the government issued petitioner a show-cause notice based on the continued failure to comply with the obligation to provide the requisite
team. Ibid. Petitioner again responded by disputing that
it had an obligation to provide a team of 20 professionals.
Id. at 22a.
On April 4, 2023, the government issued a final decision terminating the contract for default. Pet. App. 23a.
In describing the basis for the termination, the final decision stated that petitioner was required to provide the
Navy with a team of 20 professionals, yet had provided
a team of only 5 by the contract’s halfway point. Ibid.
3. Petitioner filed suit in the United States Court of
Federal Claims (CFC), challenging the government’s
termination for default on several grounds. Pet. App.
25a. After briefing, the CFC denied petitioner’s motion
for summary judgment and granted the government’s
cross-motion for summary judgment. Id. at 9a-62a.
The CFC first determined that the government’s interpretation of the contract as requiring petitioner to provide a team of 20 technical experts is “the only reasonable
one.” Pet. App. 35a; see id. at 35a-45a. The CFC further
rejected petitioner’s contention that the contract was an
unlawful personal services contract. Id. at 45a-54a.
The CFC next determined that the government
properly terminated the contract for default. Pet. App.
54a-61a. Under longstanding Federal Circuit precedent,
a termination for default requires “a reasonable belief
on the part of the contracting officer that there was no
reasonable likelihood that the [contractor] could perform the entire contract effort within the time remaining for contract performance.” Id. at 55a (quoting and
adding brackets to Lisbon Contractors, Inc. v. United
States, 828 F.2d 759, 765 (Fed. Cir. 1987)). Applying
5
that standard, the CFC concluded that petitioner had
“materially failed to perform” its contractual obligations,
and that, in light of its “performance halfway through the
contract term, it was reasonable for the contracting officer to determine that insufficient time remained both
for [petitioner] to assemble the required team and for
that team to carry out the tasks [the government]
sought to assign to the team.” Id. at 56a.
The CFC further rejected petitioner’s contention
that the government failed to consider seven factors
identified in the Federal Acquisition Regulation (FAR),
48 C.F.R. 49.402-3(f ), before terminating the contract
for default. Pet. App. 58a-61a. The CFC explained that
“the evaluation of these factors is not a prerequisite to
a valid termination” under Federal Circuit precedent.
Id. at 59a (citing DCX, Inc. v. Perry, 79 F.3d 132, 135
(Fed. Cir.), cert. denied, 519 U.S. 992 (1996)). Rather,
whether an agency considered the factors “may aid a
court in determining whether a particular termination
for default reflects an abuse of the contracting officer’s
discretion.” Id. at 60a. In this case, the CFC determined that a termination for default would not have
been an abuse of discretion regardless of the factors’
applicability because petitioner had “failed to perform
the contract.” Id. at 61a. In any event, the CFC explained that “[t]he record reflects that the contracting
officer considered all seven factors.” Id. at 60a. In support of that conclusion, the CFC cited a document that
was “signed by the contracting officer on March 17,
2023,” in which the contracting officer “outlined and discussed each factor in detail.” Id. at 60a-61a. The CFC
rejected petitioner’s objections to the admission of that
document, which was submitted by the government
along with its reply brief. Id. at 61a n.8. The CFC noted
6
that the date on the document reflects that the contracting officer considered the relevant factors before the
government made the decision to terminate, and that
the court was relying on the document “for that point
only, and not for the substance of its analysis.” Ibid.
4. The court of appeals affirmed in an unpublished,
per curiam opinion. Pet. App. 1a-8a. Like the CFC, the
court of appeals interpreted the contract to require petitioner “to provide at least 20 professionals (or the
equivalent) throughout the contract period,” and it concluded that the contract was not a personal services contract. Id. at 4a; see id. at 5a-6a. The court further determined that petitioner “had defaulted on the contract,
and that the termination for default was not simply a
ruse designed to enable the Navy to escape an improvident contract.” Id. at 7a. The court noted that petitioner had “contend[ed] in passing” that the memorandum from the contracting officer analyzing whether to
terminate the contract for default was inadmissible. Id.
at 8a n.3. The court rejected that contention, noting
that the memorandum “was not considered for the truth
of its contents, but only to show that the contracting officer addressed the [FAR] factors.” Ibid. As for the
“other subsidiary issues” petitioner had raised, the
court rejected each of them, noting that they did not
“affect [the court’s] confidence that the Claims Court’s
summary judgment order was correct.” Id. at 8a.
5. The court of appeals denied a petition for panel
rehearing and rehearing en banc without calling for a
response. Pet. App. 63a-64a.
ARGUMENT
Petitioner contends (Pet. 9-13) that the lower courts
departed from Federal Circuit precedent and failed to
adequately analyze whether the contracting officer con-
7
sidered the factors outlined in the FAR when deciding
whether to terminate the contract. But the lower courts
appropriately reviewed the termination in compliance
with the CDA and circuit precedent. Petitioner separately contends (Pet. 13-15) that the lower courts erred
by accepting the contracting officer’s decision memo into
evidence. That factbound contention is meritless and
does not warrant further review. The petition for a writ
of certiorari should be denied.
1. The lower courts correctly upheld the government’s termination of petitioner’s contract for default.
Contrary to petitioner’s contention, that holding is consistent with longstanding circuit precedent.
a. When a contractor seeks review of a decision terminating a contract for default, the government must establish that the termination for default was justified
based on the facts as they existed at the time of the termination decision. See Department of Transp. v. Eagle
Peak Rock & Paving, Inc., 69 F.4th 1367, 1375 (Fed.
Cir. 2023). Under the CDA, that inquiry “proceed[s] de
novo, based on the evidentiary record * * * and not the
[contracting] officer’s reasoning or findings of fact.”
Ibid.; see 41 U.S.C. 7103(e), 7104(b)(4). Indeed, the contracting officer need not make “[s]pecific findings of fact,”
and “[i]f made, specific findings of fact are not binding in
any subsequent proceeding.” 41 U.S.C. 7103(e). The government “may well present testimony by the contracting officer” about the facts bearing on the termination
decision, but the focus is not on the “contracting officer’s
own reasoning.” Eagle Peak, 69 F.4th at 1375-1376.
That approach is consistent with general contracting
principles. This Court has long recognized that a party
to a contract (including the government) may “justify an
asserted termination * * * of a contract by proving that
8
there was, at the time, an adequate cause, although it
did not become known to him until later.” College Point
Boat Corp. v. United States, 267 U.S. 12, 16 (1925). In
general, “the subjective knowledge of the contracting
officer herself is irrelevant, and the government is not
required to establish that the contracting officer conducted the analysis necessary to sustain a default.” Empire Energy Mgmt. Sys., Inc. v. Roche, 362 F.3d 1343,
1357 (Fed. Cir. 2004).
The lower courts here properly applied the CDA’s de
novo review standard and determined that adequate
cause for terminating the contract for default existed at
the time the contracting officer made the decision. See
Pet. App. 7a, 56a. Based on the summary-judgment record before them, the courts concluded that petitioner
failed to provide the 20 qualified professionals that the
contract required and that petitioner had therefore defaulted on the contract. Ibid.
b. Petitioner nevertheless asserts (Pet. 9-13) that
the lower courts were required to determine whether
the contracting officer adequately assessed seven factors set out in the FAR when determining that the contract should be terminated for default. In doing so, petitioner attempts (Pet. 10) to import concepts of review
of agency decisions under the Administrative Procedure Act (APA), 5 U.S.C. 701 et seq. But APA review
differs from the de novo review mandated by the CDA.
“Judicial review under [the APA] is deferential”; a “court
simply ensures that the agency has * * * reasonably
considered the relevant issues and reasonably explained
the decision.” FCC v. Prometheus Radio Project, 592
U.S. 414, 423 (2021). That type of review is incompatible
with the CDA’s provisions and with the general con-
9
tracting principles it embraces. Petitioner fails to address those incompatibilities.
Instead, petitioner contends (Pet. 9-13) that review
of the contracting officer’s decisionmaking process is
required by the Court of Claims’ pre-CDA decision in
Schlesinger v. United States, 390 F.2d 702 (1968). That
is incorrect. In Schlesinger, the Navy terminated a contract for 50,000 caps on grounds of default when the contractor sought a limited extension of a delivery date.
See id. at 703-706. The court agreed that Schlesinger
was technically in default at the time of the termination
because he had failed to deliver 15,000 of the caps by a
date specified in the contract. Id. at 706-707. Based on
the evidence introduced at trial, however, the court determined that the Navy had in fact terminated the contract because the chairman of a congressional subcommittee had sent the Navy a letter implying that the contract should be canceled for reasons unrelated to the failure to supply the caps on time. See id. at 705, 708 & n.6.
The Court of Claims held that under those circumstances, the termination for default should be treated as
a termination for convenience. See Schlesinger, 390
F.2d at 707-710. The court found that the Navy had not
exercised its discretion to terminate the contract, but
had “simply surrendered its power of choice” in light of
congressional pressure. Id. at 708. The court explained
that the contractor’s “status of technical default served
only as a useful pretext for the taking of action felt to
be necessary on other grounds unrelated to the plaintiff ’s performance.” Id. at 709.
The holding in Schlesinger has no application here.
As the Federal Circuit has observed, “Schlesinger bars
only a termination for default in which there is no considered nexus between the default termination and the
10
contractor’s performance under the contract.” McDonnell Douglas Corp. v. United States, 182 F.3d 1319, 1326
(1999), cert. denied, 529 U.S. 1097 (2000). In this Court,
petitioner does not and could not plausibly contend that
the contract here was terminated for reasons unrelated
to performance. The court of appeals expressly held
“that the termination for default was not simply a ruse
designed to enable the Navy to escape an improvident
contract.” Pet. App. 7a. And the record shows that petitioner’s continuing inability to provide a team of 20
professionals was the impetus for the termination. Ibid.;
see id. at 56a. Nor were petitioner’s failures to satisfy
the contract’s terms merely “technical.” Schlesinger,
390 F.2d at 709. Petitioner proved unable to meet the
contract’s most basic term: assembling a team to carry
out tasks under the contract. Where, as here, termination is premised on performance, a court may uphold
the termination if the default is supported by the record
evidence. McDonnell Douglas, 182 F.3d at 1326-1327.
This case does not, therefore, support petitioner’s
contention (Pet. 13) that the Federal Circuit has “effectively eradicate[d]” its own “Schlesinger line of decisions.”
2. Review is also unwarranted because the record
shows that the contracting officer did consider the FAR
factors that petitioner invokes. Pet. App. 8a & n.3, 60a61a; see id. at 79a-112a. As the CFC explained, the government submitted a document “signed by the contracting officer on March 17, 2023,” which “outline[s] and discusse[s] each factor in detail.” Id. at 60a-61a. Thus,
even if petitioner were correct that courts must assess
whether the FAR factors were considered, that conclusion would have no practical effect in this case.
11
To escape that fact, petitioner asserts that the lower
courts (Pet. 13-15) should not have accepted into evidence the document memorializing the contracting officer’s analysis on the theory that the document is inadmissible hearsay and may be fraudulent. The lower courts
correctly rejected those arguments. Pet. App. 8a & n.3,
61a n.8. With respect to hearsay, the courts did not consider the substance of the document for its truth. And
petitioner’s complaints about the document’s digital signature and formatting do not support the accusation that
the government created it in an attempt to defraud the
court. In any event, petitioner’s objections are merely a
factbound disagreement with the lower courts’ evidentiary rulings, which does not warrant this Court’s review. See Sup. Ct. R. 10 (“A petition for a writ of certiorari is rarely granted when the asserted error consists
of erroneous factual findings or the misapplication of a
properly stated rule of law.”).
CONCLUSION
The petition for a writ of certiorari should be denied.
Respectfully submitted.
D. JOHN SAUER
Solicitor General
BRETT A. SHUMATE
Assistant Attorney General
PATRICIA M. MCCARTHY
MARTIN F. HOCKEY, JR.
SHERYL L. FLOYD
Attorneys
SEPTEMBER 2026
This is a copy of a public record, reproduced as it was published. It is not legal advice, and it may not be the version a court would rely on. Check the official source before you cite it.