Opposition Brief — ASG Solutions Corp., dba American Systems Group, Petitioner v. United States

Supreme Court briefSep 11, 2026

Ask Donna

What actually matters in this document.

Text

No. 25-1372

In the Supreme Court of the United States

ASG SOLUTIONS CORP., DBA AMERICAN SYSTEMS

GROUP, PETITIONER

v.

UNITED STATES OF AMERICA

ON PETITION FOR A WRIT OF CERTIORARI

TO THE UNITED STATES COURT OF APPEALS

FOR THE FEDERAL CIRCUIT

BRIEF FOR THE RESPONDENT IN OPPOSITION

D. JOHN SAUER

Solicitor General

Counsel of Record

BRETT A. SHUMATE

Assistant Attorney General

PATRICIA M. MCCARTHY

MARTIN F. HOCKEY, JR.

SHERYL L. FLOYD

Attorneys

Department of Justice

Washington, D.C. 20530-0001

SupremeCtBriefs@usdoj.gov

(202) 514-2217

QUESTION PRESENTED

Whether the Court of Appeals for the Federal Circuit correctly upheld the government’s decision to terminate a contract for default.

(I)

TABLE OF CONTENTS

Page

Opinions below .............................................................................. 1

Jurisdiction .................................................................................... 1

Statement ...................................................................................... 1

Argument....................................................................................... 6

Conclusion ................................................................................... 11

TABLE OF AUTHORITIES

Cases:

College Point Boat Corp. v. United States,

267 U.S. 12 (1925) ................................................................. 8

DCX, Inc. v. Perry, 79 F.3d 132 (Fed. Cir.),

cert. denied, 519 U.S. 992 (1996) ......................................... 5

Department of Transp. v. Eagle Peak Rock &

Paving, Inc., 69 F.4th 1367 (Fed. Cir. 2023) ...................... 7

Empire Energy Mgmt. Sys., Inc. v. Roche,

362 F.3d 1343 (Fed. Cir. 2004) ............................................. 8

FCC v. Prometheus Radio Project,

592 U.S. 414 (2021)................................................................ 8

Lisbon Contractors, Inc. v. United States,

828 F.2d 759 (Fed. Cir. 1987) ............................................... 4

McDonnell Douglas Corp. v. United States,

182 F.3d 1319 (Fed. Cir. 1999), cert. denied,

529 U.S. 1097 (2000)............................................................ 10

Schlesinger v. United States,

390 F.2d 702 (Ct. Cl. 1968) ............................................. 9, 10

Wilner v. United States,

24 F.3d 1397 (Fed. Cir. 1994) ............................................... 2

Statutes, regulation, and rule:

Administrative Procedure Act, 5 U.S.C. 701 et seq.............. 8

(III)

IV

Statutes, regulation, and rule—Continued:

Page

Contract Disputes Act of 1978,

41 U.S.C. 7101 et seq. ............................................................ 1

41 U.S.C. 7103(a)(1) ........................................................... 2

41 U.S.C. 7103(d) ............................................................... 2

41 U.S.C. 7103(e) ........................................................... 2, 7

41 U.S.C. 7104(b)(1) .......................................................... 2

41 U.S.C. 7104(b)(4) ...................................................... 2, 7

48 C.F.R. 49.402-3(f ) ............................................................... 5

Sup. Ct. R. 10 ......................................................................... 11

In the Supreme Court of the United States

No. 25-1372

ASG SOLUTIONS CORP., DBA AMERICAN SYSTEMS

GROUP, PETITIONER

v.

UNITED STATES OF AMERICA

ON PETITION FOR A WRIT OF CERTIORARI

TO THE UNITED STATES COURT OF APPEALS

FOR THE FEDERAL CIRCUIT

BRIEF FOR THE RESPONDENT IN OPPOSITION

OPINIONS BELOW

The opinion of the court of appeals (Pet. App. 1a-8a)

is available at 2025 WL 3627729. The memorandum opinion and order of the Court of Federal Claims (Pet. App.

9a-62a) is reported at 170 Fed. Cl. 485.

JURISDICTION

The judgment of the court of appeals was entered on

December 15, 2025. A petition for rehearing was denied

on March 3, 2026 (Pet. App. 63a-64a). The petition for

a writ of certiorari was filed on June 1, 2026. The jurisdiction of this Court is invoked under 28 U.S.C. 1254(1).

STATEMENT

1. The Contract Disputes Act of 1978 (CDA), 41

U.S.C. 7101 et seq., provides a comprehensive process

for the resolution of government-contracting disputes.

(1)

2

A contractor must submit a claim against the federal

government relating to a contract to the contracting officer for a decision. 41 U.S.C. 7103(a)(1). The contracting officer must then issue a written decision, which

must “state the reasons for the decision reached” and “inform the contractor of the contractor’s rights.” 41 U.S.C.

7103(e); see 41 U.S.C. 7103(d). The decision need not contain any “[s]pecific findings of fact.” 41 U.S.C. 7103(e). If

such findings are made, they “are not binding in any subsequent proceeding.” Ibid.

Upon receipt of the contracting officer’s decision, a

contractor may appeal to the board of contract appeals

or “bring an action directly on the claim in the United

States Court of Federal Claims.” 41 U.S.C. 7104(b)(1).

Such an action “proceed[s] de novo,” with no deference

to the contracting officer’s determinations. 41 U.S.C.

7104(b)(4). “Thus, once an action is brought following a

contracting officer’s decision, the parties start in court

* * * with a clean slate.” Wilner v. United States, 24

F.3d 1397, 1402 (Fed. Cir. 1994) (en banc).

2. On September 28, 2022, petitioner entered into a

contract with the U.S. Navy “to provide engineering

and program-management services to support design

and construction operations at Naval Air Station Jacksonville.” Pet. App. 2a; see id. at 17a-18a. The contract

identified an “ ‘anticipated staff ’ of 20 professionals as

the ‘base/minimum’ level of service required.” Id. at 12a

(citation omitted). The contract provided that within

five days of its award, petitioner must provide the government with a resume for each team member proposed

to perform work under the contract. Id. at 13a-14a. The

government would review the resumes and approve the

proposed personnel to ensure they possessed the necessary qualifications. Id. at 14a. In the event that peti-

3

tioner did not maintain a full complement of 20 team

members, the contract provided that petitioner must

provide replacements within five days. Id. at 15a. If

petitioner failed to do so, the government was entitled

to a unit-price reduction in payment until the full team

was in place. Ibid.

After petitioner was awarded the contract, “[p]roblems arose almost immediately.” Pet. App. 18a. On the

date petitioner was required to submit the 20 resumes

of its proposed team, it submitted only 2. Ibid. Over

the next month, petitioner submitted 8 additional resumes. Id. at 18a-19a. Of the 10 individuals submitted,

4 were rejected by the government for lacking qualifications, and 4 more “declined [petitioner’s] offer, did

not report to work, or quickly resigned.” Id. at 19a.

On November 1, 2022, the government sent petitioner

a letter of concern, notifying petitioner that it was failing to meet contractual requirements by failing to provide the necessary staff. Pet. App. 20a. Petitioner responded by disputing that it was required to maintain a

staff of 20. Ibid. Instead, petitioner asserted that the

contract entitled it to “choose the precise labor and

staffing mix” to perform assignments under the contract. Ibid. In the days that followed that exchange,

petitioner submitted resumes for 4 more professionals,

3 of which the government approved, but only 1 accepted

petitioner’s offer of employment. Ibid.

On December 5, 2022, the government issued a notice

to cure the performance deficiency. Pet. App. 20a. The

government asserted that petitioner’s failure to perform

could justify termination of the contract for default.

Ibid. Petitioner again took the position that the contract

did not require a 20-person team. Id. at 21a. Petitioner

submitted a few additional resumes over the next month.

4

Ibid. On January 20, 2023, the government issued petitioner a show-cause notice based on the continued failure to comply with the obligation to provide the requisite

team. Ibid. Petitioner again responded by disputing that

it had an obligation to provide a team of 20 professionals.

Id. at 22a.

On April 4, 2023, the government issued a final decision terminating the contract for default. Pet. App. 23a.

In describing the basis for the termination, the final decision stated that petitioner was required to provide the

Navy with a team of 20 professionals, yet had provided

a team of only 5 by the contract’s halfway point. Ibid.

3. Petitioner filed suit in the United States Court of

Federal Claims (CFC), challenging the government’s

termination for default on several grounds. Pet. App.

25a. After briefing, the CFC denied petitioner’s motion

for summary judgment and granted the government’s

cross-motion for summary judgment. Id. at 9a-62a.

The CFC first determined that the government’s interpretation of the contract as requiring petitioner to provide a team of 20 technical experts is “the only reasonable

one.” Pet. App. 35a; see id. at 35a-45a. The CFC further

rejected petitioner’s contention that the contract was an

unlawful personal services contract. Id. at 45a-54a.

The CFC next determined that the government

properly terminated the contract for default. Pet. App.

54a-61a. Under longstanding Federal Circuit precedent,

a termination for default requires “a reasonable belief

on the part of the contracting officer that there was no

reasonable likelihood that the [contractor] could perform the entire contract effort within the time remaining for contract performance.” Id. at 55a (quoting and

adding brackets to Lisbon Contractors, Inc. v. United

States, 828 F.2d 759, 765 (Fed. Cir. 1987)). Applying

5

that standard, the CFC concluded that petitioner had

“materially failed to perform” its contractual obligations,

and that, in light of its “performance halfway through the

contract term, it was reasonable for the contracting officer to determine that insufficient time remained both

for [petitioner] to assemble the required team and for

that team to carry out the tasks [the government]

sought to assign to the team.” Id. at 56a.

The CFC further rejected petitioner’s contention

that the government failed to consider seven factors

identified in the Federal Acquisition Regulation (FAR),

48 C.F.R. 49.402-3(f ), before terminating the contract

for default. Pet. App. 58a-61a. The CFC explained that

“the evaluation of these factors is not a prerequisite to

a valid termination” under Federal Circuit precedent.

Id. at 59a (citing DCX, Inc. v. Perry, 79 F.3d 132, 135

(Fed. Cir.), cert. denied, 519 U.S. 992 (1996)). Rather,

whether an agency considered the factors “may aid a

court in determining whether a particular termination

for default reflects an abuse of the contracting officer’s

discretion.” Id. at 60a. In this case, the CFC determined that a termination for default would not have

been an abuse of discretion regardless of the factors’

applicability because petitioner had “failed to perform

the contract.” Id. at 61a. In any event, the CFC explained that “[t]he record reflects that the contracting

officer considered all seven factors.” Id. at 60a. In support of that conclusion, the CFC cited a document that

was “signed by the contracting officer on March 17,

2023,” in which the contracting officer “outlined and discussed each factor in detail.” Id. at 60a-61a. The CFC

rejected petitioner’s objections to the admission of that

document, which was submitted by the government

along with its reply brief. Id. at 61a n.8. The CFC noted

6

that the date on the document reflects that the contracting officer considered the relevant factors before the

government made the decision to terminate, and that

the court was relying on the document “for that point

only, and not for the substance of its analysis.” Ibid.

4. The court of appeals affirmed in an unpublished,

per curiam opinion. Pet. App. 1a-8a. Like the CFC, the

court of appeals interpreted the contract to require petitioner “to provide at least 20 professionals (or the

equivalent) throughout the contract period,” and it concluded that the contract was not a personal services contract. Id. at 4a; see id. at 5a-6a. The court further determined that petitioner “had defaulted on the contract,

and that the termination for default was not simply a

ruse designed to enable the Navy to escape an improvident contract.” Id. at 7a. The court noted that petitioner had “contend[ed] in passing” that the memorandum from the contracting officer analyzing whether to

terminate the contract for default was inadmissible. Id.

at 8a n.3. The court rejected that contention, noting

that the memorandum “was not considered for the truth

of its contents, but only to show that the contracting officer addressed the [FAR] factors.” Ibid. As for the

“other subsidiary issues” petitioner had raised, the

court rejected each of them, noting that they did not

“affect [the court’s] confidence that the Claims Court’s

summary judgment order was correct.” Id. at 8a.

5. The court of appeals denied a petition for panel

rehearing and rehearing en banc without calling for a

response. Pet. App. 63a-64a.

ARGUMENT

Petitioner contends (Pet. 9-13) that the lower courts

departed from Federal Circuit precedent and failed to

adequately analyze whether the contracting officer con-

7

sidered the factors outlined in the FAR when deciding

whether to terminate the contract. But the lower courts

appropriately reviewed the termination in compliance

with the CDA and circuit precedent. Petitioner separately contends (Pet. 13-15) that the lower courts erred

by accepting the contracting officer’s decision memo into

evidence. That factbound contention is meritless and

does not warrant further review. The petition for a writ

of certiorari should be denied.

1. The lower courts correctly upheld the government’s termination of petitioner’s contract for default.

Contrary to petitioner’s contention, that holding is consistent with longstanding circuit precedent.

a. When a contractor seeks review of a decision terminating a contract for default, the government must establish that the termination for default was justified

based on the facts as they existed at the time of the termination decision. See Department of Transp. v. Eagle

Peak Rock & Paving, Inc., 69 F.4th 1367, 1375 (Fed.

Cir. 2023). Under the CDA, that inquiry “proceed[s] de

novo, based on the evidentiary record * * * and not the

[contracting] officer’s reasoning or findings of fact.”

Ibid.; see 41 U.S.C. 7103(e), 7104(b)(4). Indeed, the contracting officer need not make “[s]pecific findings of fact,”

and “[i]f made, specific findings of fact are not binding in

any subsequent proceeding.” 41 U.S.C. 7103(e). The government “may well present testimony by the contracting officer” about the facts bearing on the termination

decision, but the focus is not on the “contracting officer’s

own reasoning.” Eagle Peak, 69 F.4th at 1375-1376.

That approach is consistent with general contracting

principles. This Court has long recognized that a party

to a contract (including the government) may “justify an

asserted termination * * * of a contract by proving that

8

there was, at the time, an adequate cause, although it

did not become known to him until later.” College Point

Boat Corp. v. United States, 267 U.S. 12, 16 (1925). In

general, “the subjective knowledge of the contracting

officer herself is irrelevant, and the government is not

required to establish that the contracting officer conducted the analysis necessary to sustain a default.” Empire Energy Mgmt. Sys., Inc. v. Roche, 362 F.3d 1343,

1357 (Fed. Cir. 2004).

The lower courts here properly applied the CDA’s de

novo review standard and determined that adequate

cause for terminating the contract for default existed at

the time the contracting officer made the decision. See

Pet. App. 7a, 56a. Based on the summary-judgment record before them, the courts concluded that petitioner

failed to provide the 20 qualified professionals that the

contract required and that petitioner had therefore defaulted on the contract. Ibid.

b. Petitioner nevertheless asserts (Pet. 9-13) that

the lower courts were required to determine whether

the contracting officer adequately assessed seven factors set out in the FAR when determining that the contract should be terminated for default. In doing so, petitioner attempts (Pet. 10) to import concepts of review

of agency decisions under the Administrative Procedure Act (APA), 5 U.S.C. 701 et seq. But APA review

differs from the de novo review mandated by the CDA.

“Judicial review under [the APA] is deferential”; a “court

simply ensures that the agency has * * * reasonably

considered the relevant issues and reasonably explained

the decision.” FCC v. Prometheus Radio Project, 592

U.S. 414, 423 (2021). That type of review is incompatible

with the CDA’s provisions and with the general con-

9

tracting principles it embraces. Petitioner fails to address those incompatibilities.

Instead, petitioner contends (Pet. 9-13) that review

of the contracting officer’s decisionmaking process is

required by the Court of Claims’ pre-CDA decision in

Schlesinger v. United States, 390 F.2d 702 (1968). That

is incorrect. In Schlesinger, the Navy terminated a contract for 50,000 caps on grounds of default when the contractor sought a limited extension of a delivery date.

See id. at 703-706. The court agreed that Schlesinger

was technically in default at the time of the termination

because he had failed to deliver 15,000 of the caps by a

date specified in the contract. Id. at 706-707. Based on

the evidence introduced at trial, however, the court determined that the Navy had in fact terminated the contract because the chairman of a congressional subcommittee had sent the Navy a letter implying that the contract should be canceled for reasons unrelated to the failure to supply the caps on time. See id. at 705, 708 & n.6.

The Court of Claims held that under those circumstances, the termination for default should be treated as

a termination for convenience. See Schlesinger, 390

F.2d at 707-710. The court found that the Navy had not

exercised its discretion to terminate the contract, but

had “simply surrendered its power of choice” in light of

congressional pressure. Id. at 708. The court explained

that the contractor’s “status of technical default served

only as a useful pretext for the taking of action felt to

be necessary on other grounds unrelated to the plaintiff ’s performance.” Id. at 709.

The holding in Schlesinger has no application here.

As the Federal Circuit has observed, “Schlesinger bars

only a termination for default in which there is no considered nexus between the default termination and the

10

contractor’s performance under the contract.” McDonnell Douglas Corp. v. United States, 182 F.3d 1319, 1326

(1999), cert. denied, 529 U.S. 1097 (2000). In this Court,

petitioner does not and could not plausibly contend that

the contract here was terminated for reasons unrelated

to performance. The court of appeals expressly held

“that the termination for default was not simply a ruse

designed to enable the Navy to escape an improvident

contract.” Pet. App. 7a. And the record shows that petitioner’s continuing inability to provide a team of 20

professionals was the impetus for the termination. Ibid.;

see id. at 56a. Nor were petitioner’s failures to satisfy

the contract’s terms merely “technical.” Schlesinger,

390 F.2d at 709. Petitioner proved unable to meet the

contract’s most basic term: assembling a team to carry

out tasks under the contract. Where, as here, termination is premised on performance, a court may uphold

the termination if the default is supported by the record

evidence. McDonnell Douglas, 182 F.3d at 1326-1327.

This case does not, therefore, support petitioner’s

contention (Pet. 13) that the Federal Circuit has “effectively eradicate[d]” its own “Schlesinger line of decisions.”

2. Review is also unwarranted because the record

shows that the contracting officer did consider the FAR

factors that petitioner invokes. Pet. App. 8a & n.3, 60a61a; see id. at 79a-112a. As the CFC explained, the government submitted a document “signed by the contracting officer on March 17, 2023,” which “outline[s] and discusse[s] each factor in detail.” Id. at 60a-61a. Thus,

even if petitioner were correct that courts must assess

whether the FAR factors were considered, that conclusion would have no practical effect in this case.

11

To escape that fact, petitioner asserts that the lower

courts (Pet. 13-15) should not have accepted into evidence the document memorializing the contracting officer’s analysis on the theory that the document is inadmissible hearsay and may be fraudulent. The lower courts

correctly rejected those arguments. Pet. App. 8a & n.3,

61a n.8. With respect to hearsay, the courts did not consider the substance of the document for its truth. And

petitioner’s complaints about the document’s digital signature and formatting do not support the accusation that

the government created it in an attempt to defraud the

court. In any event, petitioner’s objections are merely a

factbound disagreement with the lower courts’ evidentiary rulings, which does not warrant this Court’s review. See Sup. Ct. R. 10 (“A petition for a writ of certiorari is rarely granted when the asserted error consists

of erroneous factual findings or the misapplication of a

properly stated rule of law.”).

CONCLUSION

The petition for a writ of certiorari should be denied.

Respectfully submitted.

D. JOHN SAUER

Solicitor General

BRETT A. SHUMATE

Assistant Attorney General

PATRICIA M. MCCARTHY

MARTIN F. HOCKEY, JR.

SHERYL L. FLOYD

Attorneys

SEPTEMBER 2026

This is a copy of a public record, reproduced as it was published. It is not legal advice, and it may not be the version a court would rely on. Check the official source before you cite it.

A word about cookies

We need a few to keep you signed in and the library working. The rest help us see which pages people use and where they get stuck. They stay off unless you say yes.