Petition for Writ of Certiorari — ASG Solutions Corp., dba American Systems Group, Petitioner v. United States
Supreme Court briefJun 1, 2026
Ask Donna
What actually matters in this document.
Text
APPENDIX TABLE OF CONTENTS
Appendix A: United States Court of Appeals
for the Federal Circuit, Opinion, December 15,
2025. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1a
Appendix B: United States Court of Federal
Claims, Memorandum Opinion, March 29,
2024. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 9a
Appendix C: United States Court of Appeals
for the Federal Circuit, Order Denying Rehearing,
March 3, 2026 . . . . . . . . . . . . . . . . . . . . . . . . . . . . 63a
Appendix D: Department of the Navy, Notice
of Termination to Prime Contractor, October 30,
2024. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 65a
Appendix E: Department of the Navy, Request
to Terminate for Default . . . . . . . . . . . . . . . . . . . 79a
Appendix F: Statutory and Regulatory
Provisions . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 113a
APPENDIX A
NOTE: This disposition is nonprecedential.
UNITED STATES COURT OF APPEALS
FOR THE FEDERAL CIRCUIT
ASG SOLUTIONS CORP., DBA AMERICAN
SYSTEMS GROUP,
Plaintiff-Appellant
v.
UNITED STATES,
Defendant-Appellee
2024-1755
Appeal from the United States Court of Federal
Claims in No. 1:23-cv-01029-RAH,
Judge Richard A. Hertling.
Decided: December 15, 2025
DAVID DEMIAN, Finch, Thornton & Baird, LLP,
San Diego, CA, argued for plaintiff-appellant.
SHERYL L. FLOYD, Commercial Litigation
Branch, Civil Division, United States Department of
Justice, Washington, DC, argued for defendantappellee. Also represented by MARTIN F. HOCKEY,
JR., PATRICIA M. MCCARTHY, BRETT SHUMATE.
1a
Before CHEN, BRYSON, and CUNNINGHAM, Circuit
Judges.
PER CURIAM.
This case arises from a contract between a private
contractor and the United States Department of the
Navy (Navy). The contractor complains that the
Navy improperly terminated the contract for default
and raises a number of claims of improper conduct by
the Navy that led to that termination.
The contractor sought review of the termination
in the Court of Federal Claims (the Claims Court),
which granted summary judgment for the government
in a thorough opinion that addressed each of the
claims raised by the contractor. See ASG Sols. Corp. v.
United States, 170 Fed. Cl. 485 (2024). We agree with
the Claims Courts analysis and accordingly affirm.
I
The contract in this case was an Indefinite
Delivery Indefinite Quantity task order contract under
which the contractor, ASG Solutions Corporation,
doing business as American Systems Group (ASG)
agreed to provide engineering and programmanagement services to support design and
construction operations at Naval Air Station
Jacksonville. Id. at 489; J.A. 29573022. The
government interpreted the task order as requiring the
contractor to assemble a multi-disciplinary team of at
least 20 professionals who would provide technical
support services on demand relating to design and
2a
construction work at the Naval Air Station.
Despite the terms of the agreement, ASG never
succeeded in assembling a team of 20 or more
professionals who met the qualifications set forth in
the contract. For that reason, the Navy terminated the
contract for default halfway through the one-year
contract period, over ASGs strong objection. J.A.
455661.
In its challenge to the termination, ASG raises a
number of issues, the principal ones of which are (1)
that the Navy misconstrued the contract by
interpreting it to require ASG to assemble and
maintain a group of at least 20 professionals even at
times when the Navy had no tasks for the group to
perform; (2) that the contract was invalid because it
was an unlawful personal services contract, prohibited
by section 37.104 of the Federal Acquisition Regulation
(FAR); and (3) that the default termination was
unjustified and was merely a pretext by which the
Navy sought to rid itself of ASG as a contractor.
II
A
The government argues that the plain terms of
the contract required ASG to provide the Navy with a
team of 20 facilities technical experts to advise and
assist on projects at the Naval Air Station as they
arose, and that ASG never approached having that
number of technical experts available to perform
services for the Navy. ASG, on the other hand, argues
3a
that the contract did not require it to have a certain
number of professionals on staff, but only required it
to assemble a qualified team to perform each task after
the Navy assigned it a specific project under the
contract.
The Claims Court found the governments
interpretation of the contract to be more reasonable, as
do we. See ASG, 170 Fed. Cl. at 498502. Although the
contract gave ASG the right to determine the precise
labor and staffing mix among professionals selected to
provide the contractual services, the contract required
ASG to provide at least 20 professionals (or the
equivalent) throughout the contract period, not simply
to make professionals available when and as needed
for the tasks assigned from time to time under the
contract. J.A. 2966. Section A.2 of the solicitation
states that [t]he staff of twenty (20) professionals is
base/minimum level of service, J.A. 2959; and section
H.8 states that any time there is a vacancy within the
Contractors team (i.e. all twenty (20) positions are not
filled), the Government will be entitled to immediate
replacement . . . or to a unit price reduction in
payment, J.A. 2988.
Other evidence in the case is consistent with the
requirement that the contractor have an assembled
team of 20 professionals at all times. That evidence
included ASGs bid, which referred to [o]ur proposed
20 FTE All-Senior Team and outlined the
backgrounds of the 20 team members. J.A. 3027; see
also J.A. 2999 (Attachment 2 to section J of the task
order outlining the proposed back grounds of 20 team
members). ASG subsequently confirmed that it
4a
understood that it would be bound by the
representations found in its bid. J.A. 317374. In
addition, section M of the solicitation provided that for
the evaluation of proposals, [t]he team must be
composed of twenty (20) professionals including two
supervisors. J.A. 3074.
We agree with the Claims Courts conclusion that
the governments interpretation of the contract is
clearly more reasonable than ASGs. For that reason,
we reject ASGs reliance on the doctrine of contra
proferentem, which calls for construing ambiguous
contract terms against the drafterhere, the
government.
B
The Claims Court rejected ASGs argument that
the contract was an impermissible personal services
contract. ASG, 170 Fed. Cl. at 50405. While the
contract required ASG to make a number of
professionals available to perform tasks for the Navy,
it clearly left the responsibility for hiring and
supervising those professionals with ASG.
The FAR provision governing personal services
contracts defines nonpersonal services contracts as
those in which the personnel rendering the services in
question are not subject to the supervision and control
usually prevailing in relationships between the
Government and its employees. 48 C.F.R. § 37.101;
see 48 C.F.R. § 37.104. The contract made clear that
the 20 professionals that ASG was committed to
making available to do government work would be
5a
employees of ASG, not of the government; the contract
specifically provided that [t]he contractor supervises
its own team to ensure compliance with this
[Performance Work Statement]. J.A. 2968. While the
government had the right to review resumes and
specify the level of expertise required of those
employees, it was not responsible for hiring and firing
them or otherwise managing their employment on a
day-to-day basis. See J.A. 2970 (Contractor employees
performing services under this order will be controlled,
directed and supervised at all times by management
personnel of the contractor.); see also J.A. 2975,
297980, 303132. The Claims Court was thus clearly
correct that the contract was not a personal services
contract.
C
ASG argues that it provided the services for
which the government contracted because it stood
ready to supply professionals to do whatever tasks the
Navy asked it to perform, and that the termination for
default was therefore unjustified. The Claims Court
rejected that argument on the ground that it was
inconsistent with the obligations imposed on ASG by
the contract. ASG, 170 Fed. Cl. at 505 08. In section
F.4 of the contract, ASG agreed that within five days
of the contract award it would provide a [r]esume for
each position proposed to accomplish the tasks falling
within the scope of the contract. J.A. 297475. ASG
failed to deliver those resumes. See ASG, 170 Fed. Cl.
at 49293. The contract did not contemplate that ASG
would arrange to hire and provide professionals
whenever the Navy had a particular task for ASG to
6a
perform.
The summary judgment record showed that
throughout the contract period, ASG never retained as
many as 20 qualified professionals, and for most of
that period, it had far fewer.1 Moreover, on several
occasions the Navy notified ASG that it was not
complying with its responsibilities under the contract,
but ASG never brought itself into compliance with the
contracts requirements.2
We agree with the Claims Court that the
government reasonably concluded that ASG had
defaulted on the contract, and that the termination for
default was not simply a ruse designed to enable the
Navy to escape an improvident contract. Based on that
conclusion, the Claims Court properly determined that
the government had not breached its covenant of good
faith and fair dealing through its actions and
communications with ASG. See ASG, 170 Fed. Cl. 505,
508.
1
The Claims Court held that ASG materially failed to
perform. It did not provide the required services of assembling a
fully staffed team . . . . As of March 2023, halfway through the
contract period, ASG had retained only four employees who
reported to work at NAS Jacksonville. ASG, 170 Fed. Cl. at 506.
2
The Claims Court noted that the Navy sent ASG a
letter of concern on November 1, 2022; a cure notice on
December 5, 2022; and a notice to show cause on January 20,
2023, based on ASGs failure to comply with its obligations to
propose team members meeting the qualifications required by the
contract. ASG, 170 Fed. Cl. at 493.
7a
ASG has raised several other subsidiary issues in
its brief, which the Claims Court addressed in its
comprehensive opinion.3 None of those issues,
however, affect our confidence that the Claims Courts
summary judgment order was correct.
AFFIRMED
3
ASG contends in passing that the memorandum in
which the contracting officer considered seven factors to
determine whether to terminate the contract for default (J.A.
473244) was inadmissible as hearsay. Appellants Br. 5053. The
memorandum, however, was not considered for the truth of its
contents, but only to show that the contracting officer addressed
the factors required by 48 C.F.R. § 49.402-3(f) to be considered
before terminating a contract for default. ASG, 170 Fed. Cl. at
50708 & n.8.
8a
APPENDIX B
IN THE UNITED STATES COURT OF
FEDERAL CLAIMS
No. 23-1029
Filed: March 29, 2024
FOR PUBLICATION
ASG SOLUTIONS CORPORATION DBA
AMERICAN SYSTEMS GROUP,
Plaintiff,
v.
UNITED STATES,
Defendant.
David S. Demian, Finch, Thornton, & Baird LLP, San
Diego, CA, for the plaintiff.
Sheryl L. Floyd, Commercial Litigation Branch, Civil
Division, U.S. Department of Justice, Washington,
D.C., for the defendant.
MEMORANDUM OPINION
HERTLING, Judge
The plaintiff, ASG Solutions Corp., dba American
Systems Group (ASG), was awarded an Indefinite
Delivery Indefinite Quantity (IDIQ) task order by the
defendant, acting through the United States
9a
Department of the Navy (Navy), to provide
engineering and program-management support
services to the Naval Facilities Engineering Systems
Command Southeast (NAVFAC SE) to support the
operations of the Design and Construction Business
Line (DCBL) at Naval Air Station (NAS)
Jacksonville in Jacksonville, Florida. Ultimately, the
Navy terminated ASGs task order for default. ASG
filed claims with the contracting officer and, after
those claims were largely rejected, filed this action
under the Contract Disputes Act (CDA), 41 U.S.C. §
7101 et seq. The plaintiff alleges that the termination
for default was in error and that the Navy breached
the contract and the covenant of good faith and fair
dealing. The plaintiff has moved for judgment on the
pleadings and for summary judgment. The defendant
has cross-moved for summary judgment.
The defendants interpretation of the task order
as requiring the contractor to assemble a 20-person,
multidisciplinary team of professionals aligns with the
plain language of the task order, reads all its
provisions in harmony, and makes sense given the
task orders purpose. This reading does not render the
task order a personal services contract in violation of
Federal Acquisition Regulation (FAR) 37.104 because
the task order made clear that, throughout
performance, the contractor retained control of its
team.
Given that the task order requires a 20-person
team, the evidence submitted by the parties
demonstrates that the plaintiff failed to perform the
contract, and termination for default was justified
10a
under FAR 52.249-8 and 49.402-3(f). The plaintiffs
motions for judgment on the pleadings and summary
judgment are denied, and the defendants motion for
summary judgment is granted.
I.
FACTUAL BACKGROUND
ASG is a provider of professional-support services
for federal agencies. In 2019, the Navy awarded ASG,
along with more than 2,400 other entities, the Seaport
Next Generation Multiple Award, IDIQ Contract, No.
N0017819D7175 (Seaport NxG Contract). (ECF 23 at
3.) Under the Seaport NxG Contract, various Navy
commands procure a variety of professionalsupport
services, including for technical fields such as
architecture and engineering.
A.
Solicitation and Task Order
On August 25, 2022, ASG submitted a proposal in
response to a solicitation for task order No.
N6945022F3005 under the Seaport NxG Contract.1
(ECF 23 at 15; 23-2 at 67.) Under the task order, the
contractor would provide technical-support services at
1
ASG is a party to two agreements involved in this
matter. First, it is a member of the Seaport NxG contract. Second,
pursuant to that contract, it was awarded the NAVFAC SE task
order at Jacksonville NAS. The parties sometimes refer to this
latter contract as the Jacksonville contract, but this opinion will
refer to it as the task order, or the Jacksonville task order. The
assignments issued to ASG by the Navy pursuant to the
Jacksonville task order will be referred to as sub-task orders or
assignments rather than tasks or task orders to avoid
confusion.
11a
NAS Jacksonville for NAVFAC SEs DCBL. The task
order was to begin in October 2023. (ECF 23-2 at 70.)
The Navy apparently opted to proceed with the
solicitation when it found itself unable to fill vacancies
in the ranks of its own DCBL workforce.
Sections A through J of the solicitation mirror the
content of the task order ultimately awarded to ASG.
Section A.2 describes the service requirements under
the task order. (ECF 17- 3 at 95.) Offerors were to
assemble a team to provide expert advice and
assistance services on various NAVFAC SE-supported
projects. (Id.) With respect to this team, Section A.2 of
the solicitation noted that:
[a]t the time of initial contract award, the
Government anticipates a staff of four (4)
Architects, four (4) Mechanical Engineers,
four (4) Electrical Engineers, two (2) Civil
Engineers, two (2) Structural Engineers, one
(1) Fire Protection Engineer, one (1) Cost
Engineer, and two (2) Supervisors.
(Id.)
Section A.2 identified this anticipated staff of 20
professionals as the base/minimum level of service
required under the task order. (Id.)
Section B provided a list of supplies and services
to be provided under the task order for which offerors
were to provide pricing. (Id. at 98.) The first line item
is the base requirement, which is [t]echnical
[s]upport [s]ervices at NAS Jacksonville in accordance
12a
with [the performance work statement]. (Id.) The
quantity and unit columns provide that the Navy
will acquire these services for 12 months. (Id.) The
second line item required offerors to provide pricing for
an additional, [o]ptional level of service, through
which NAVFAC SE could award additional
architectural and engineering technical expert support
services. (Id.) This item also stated a quantity and
unit of 12 months. (Id.)
Section C of the solicitation included the
performance work statement (PWS). (ECF 17-3 at
103.) The PWS required the awardee to provide,
manage, and supervise a team of facilities technical
experts to help[ ] NAVFAC SE achieve its mission and
ensure compliance with the Department of Defense
(DoD) Unified Facilities Criteria and other applicable
standards related to the design, construction,
sustainment, and demolition of naval facilities. (Id.)
The PWS noted that the contractor would choose[ ]
the precise labor and staffing mix to meet the PWS,
as long as the team possessed the requisite expert
knowledge and experience. (Id.) The PWS was silent
about the size and composition of the team and failed
to reiterate the obligation specified in Section A.2
regarding the base/minimum level of service under
the task order.
Section F.4 of the solicitation outlined the
deliverables due under the task order. (Id. at 111-12.)
Among the deliverables specified in Section F.4, the
awardee would be required, within five days of
receiving the task-order award, to provide resumes to
the contracting officer for each team member proposed
13a
by offerors to perform work under the task order. (Id.
at 112.) Each resume had to be in accordance with
[the offerors] proposal and the PWS. (Id.)
Section G.5 of the solicitation outlined the task
orders quality-assurance plan and detailed NAVFAC
SEs review of contractor personnel. (Id. at 118.) In
relevant part, the quality-assurance plan explained
that the contracting officers representative would
review and approve prospective contractor personnel
to ensure that they met the required qualifications,
including certification and licensure, whenever
personnel were added to the task order.2 (Id. at 118.)
Section G.6 reiterated this requirement by confirming
that the awardee would submit to the Navy the
resumes of all proposed employees working on the task
order in accordance with Section F.4. (Id.) The
awardee would have to demonstrate that its personnel
held certificates, licenses, physical requirements or
other expertise required to fulfill the requirements of
the [PWS]. (Id.) In submitting the resume of each
prospective employee, the awardee also had to certify
that . . . the qualified individual[ ] has agreed to accept
the position upon acceptance by the [g]overnment.
(Id.)
Section H.8 of the solicitation provided for
deductions to the firm, fixed price the Navy had to pay
2
The solicitation was amended twice. The final version
of the solicitation included an amendment intended to strengthen
the resume requirements. The summary of changes accompanying
the final solicitation explained that Section G was amended, in
part, to clarify resume certification. (ECF 17-3 at 95.)
14a
the awardee in the event the awardee did not maintain
a team of 20 employees. Specifically, Section H.8
provided that if, at any time there [was] a vacancy
within the [c]ontractors team (i.e. all twenty (20)
positions are not filled), the contractor had to provide
a replacement within five days. (Id. at 124.) If the
contractor failed to provide a replacement to restore
the team to a complement of 20 members within five
days, NAVFAC SE would subject the contractor to a
unit price reduction in payment in accordance with
FAR 52.246-4 until the qualified technical expert(s)
[was] in place.3 (Id.)
Section J of the solicitation included various
attachments that offerors had to submit with their
proposals. (Id. at 128.) Attachment 4 provided a
worksheet for offerors to demonstrate the
qualifications of the team they would provide under
the task order. (Id.)
In Section M of the solicitation, NAVFAC SE
outlined three factors it would use to evaluate
proposals. (Id. at 134.) The second factor, Staffing
Approach, required offerors to propose a team of 20
professionals to accomplish the work required under
the task order. (Id. at 136.) The solicitation noted:
The non-price proposal presented by the
3
FAR 52.246-4 governs fixed-price service contracts.
Section (e) provides that if the services provided do not conform
with the contracts requirements, the government may reduce the
contract price to reflect the reduced value of the services to be
performed. FAR 52.246- 4(e)(2).
15a
offeror to whom the award is made will be
incorporated into the task order at time of
award. Post-award, the offeror will be held
to any proposed licenses certifications,
qualifications, expertise, etc. of the technical
support personnel that exceed the minimum
requirements of the solicitation and/or PWS.
(Id.)
Section M also specified that each team member
must possess an education level suitable to meet the
requirements of the PWS. Section M noted that
offerors proposing teams with education, training, or
seniority beyond the minimum requirements may be
rated higher. (Id.)
During the Navys development of the solicitation,
a NAVFAC SE contracting official had analyzed
whether the task order would constitute a personal
services contract, because the task order required
offerors to propose teams of qualified personnel to
assist the Navy in performing its functions. (ECF 23-2
at 76.) FAR 37.104 forbids agencies from awarding
personal services contracts unless they are authorized
by law to do so. The Navy contracting official
determined and certified that the task order would not
result in an impermissible personal services contract
because the awardee, rather than the Navy, would
control and manage its own employees working on the
task order. (Id.)
To reflect this determination, Section C.8 of the
solicitation incorporated a Non- Personal Service
16a
Statement. In this provision, the Navy certified that
all contractor personnel would be controlled, directed
and supervised at all times by management personnel
of the contractor. . . . The [g]overnment will control
access to the facility and will perform the inspection
and acceptance of the completed work. (ECF 17-3 at
107.) Thus, under the task order, the Navy would
assign projects to the contractor; the contractor was
then responsible for tasking out the assignment to its
personnel, who would be supervised exclusively by the
contractor in the performance of their tasks.
As part of its proposal, ASG submitted in
Attachment 4 of Section J a proposed 20-member team
consisting entirely of senior-level, accredited
professionals with advanced degrees. Although the list
included the specific qualifications of the individuals,
it did not include the name of any of the individuals
proposed. (Id. at 71.) ASG accompanied its proposed
team with the proposed cost associated with employing
each team member. (ECF 23-2 at 64.) When NAVFAC
SE incorporated Attachment 4 into the final contract
as the solicitation provided, this list of costs also
became ASGs monthly rate: $281,870.00. (ECF 17 at
30; ECF 17-3 at 57.)
On September 15, 2022, the contracting officer
contacted ASG about its proposal, requesting that ASG
confirm that [it] underst[ood] the technical experts
submitted after award must meet the additional
requirements proposed in ASGs Attachment 4. (ECF
17-3 at 539.) ASG responded simply, [y]es. (Id.)
On September 28, 2022, ASG was awarded the
17a
task order, which incorporated the provisions of the
solicitation outlined above, except for Section M, which
described the awardevaluation criteria. Attachment 4
of Section J of the solicitation was incorporated into
the task order as Attachment 2 to Section J.
The task order does not contain an order of
precedence clause to resolve disputes in the event of
conflicting provisions. The Seaport NxG contract does,
however, incorporate by reference FAR 52.215-8,
which provides the order of precedence in the Uniform
Contract Format. FAR 52.215-8 provides that
inconsistencies between provisions shall be resolved by
giving precedence to: (a) the schedule; (b)
representations and other instructions; (c) contract
clauses; (d) other documents, exhibits, and
attachments; and (e) the specifications, in that order.
B.
ASGs Performance of the Task Order
Problems arose almost immediately. After being
awarded the task order, ASG struggled to assemble its
team of professionals. On October 3, 2022, the date by
which, under Section F.4 of the task order, ASG had to
submit resumes for its 20 team members, ASG
submitted only two resumes. (ECF 23 at 19.) ASGs
owner and president emailed the contracting officers
representative that day noting that so far I have been
able to obtain 2 of the 20 have [sic] signed [letters of
intent]. (ECF 17-3 at 392.) After identifying the two
individuals, ASGs president continued I will continue
this process till all 20 are filled. (ECF 23 at 393.)
Between October 6, 2022, and November 9, 2022,
18a
ASG submitted eight additional resumes. (Id. at 1923.) Of the 10 resumes submitted by November 9,
2022, four were rejected by NAVFAC SE because the
professionals lacked required licenses or possessed
inadequate experience in comparison to the seniorlevel team members proposed by ASG on Attachment
2 of the contract. (Id.) Six resumes were accepted, but
four of these six professionals declined ASGs offer, did
not report to work, or quickly resigned. (Id.) As of
November 9, 2022, ASG only had two professionals
available to work under the task order. (Id. at 23.)
Email communications between ASG and
NAVFAC SE revealed growing disagreement between
the parties pertaining to the submitted resumes and
the qualifications necessary for ASGs team members.
ASG asserted that because the task order was not a
personal services contract, it was free to hire personnel
that it believed could deliver services consistent with
the requirements of the PWS. (ECF 23-2 at 260.) It
asserted that NAVFAC SEs failure to issue
assignments for ASG contractors to complete under
the task order prevented ASG from assembling an
appropriate team; ASG could not recruit employees
unless it knew what type of work they would need to
do. (Id. at 477-81.) NAVFAC SE, in turn, explained to
ASG that its employees had to meet the experience
levels described in Attachment 2 to the task order
(Attachment 4 of ASGs proposal) and insisted that it
had the right to reject resumes of proposed ASG
employees who did not reflect the qualifications for
prospective employees initially offered by ASG in its
proposal. (Id. at 259.)
19a
On November 1, 2022, the contracting officer sent
ASG a letter of concern, notifying ASG that it was
failing to meet the minimum staffing requirement
identified in Section A.2 of the task order by failing to
provide a staff of at least 20 professionals. (Id. at 458459.) The letter expressed further concern that ASG
was not meeting the requirement of Section F.4 by
failing to deliver adequate and timely resumes. (Id.)
On November 17, 2022, counsel for ASG
responded to the letter of concern. (ECF 23-2 at 46064.) ASG asserted that it was not required to maintain
a staff of 20 professionals under the task order and
that, pursuant to Section C, the PWS, ASG retained
the authority to choose the precise labor and staffing
mix to perform under the task order. (Id.)
Between November 18 and November 20, 2022,
ASG submitted four additional resumes to NAVFAC
SE. (ECF 23 at 24-25.) NAVFAC SE rejected one
resume because the proposed employee lacked the
credentials described in Attachment 2. (Id. at 25.)
NAVFAC SE accepted the other three resumes, but
ASG successfully retained only one of these
professionals. (Id. at 24-25.)
On December 5, 2022, NAVFAC SE issued a cure
notice to ASG. NAVFAC SE asserted that ASGs
inability to meet its obligations under Attachment 2
endangered performance of the task order and could
justify termination for default. (ECF 23-2 at 527-28.)
Specifically, NAVFAC SE noted that ASG had
submitted only nine resumes that met the level of
employee qualifications required under Attachment 2.
20a
(Id.) NAVFAC SE informed ASG that unless it cured
this failure within 10 calendar days, NAVFAC SE
could terminate the task order for default under FAR
52.249-8. (Id.)
On December 14, 2022, ASG responded to the
cure notice and asserted that it was not required to
provide 20 professionals to meet its obligations under
the task order because Attachment 2 was not a
contractual obligation. (Id. at 532-34.) ASG further
responded that because the Navy had not provided to
ASG any then-pending specific assignments to perform
under the task order, ASG was not yet obligated to
provide a team of professionals. (Id. at 531- 32.) ASG
reasoned that because it was to choose the precise
labor and staffing mix to perform assignments under
the task order, it could not put together an appropriate
team until NAVFAC SE gave it specific assignments to
fulfill. (Id. at 530.)
On January 13, 2023, ASG provided an additional
resume, which NAVFAC SE accepted. (ECF 23 at 26.)
On January 20, 2023, ASG provided two more
resumes. (Id. at 27-28.) NAVFAC SE accepted one and
rejected the other based on lack of experience. Finally,
on March 10, 2023, ASG submitted an additional
resume, and NAVFAC SE accepted it. (Id. at 28.) Of
this group of three prospective employees whose
resumes NAVFAC SE accepted, ASG retained two
professionals. (Id.)
On January 20, 2023, NAVFAC SE issued ASG a
show cause notice based on ASGs failure to comply
with its obligations to propose team members meeting
21a
the qualifications of the team members proposed in
Attachment 2. (ECF 23-2 at 672.) The notice
referenced a meeting held at NAS Jacksonville on
January 5, 2023, at which ASGs president allegedly
acknowledged that ASG cannot meet Attachment 4.
(Id.) This statement, the notice explained, constituted
an anticipatory repudiation and abandonment of
ASGs contractual obligations. (Id.) The notice
provided ASG the opportunity to explain why its
failure to perform arose from causes beyond [its]
control and without fault of or negligence by ASG.
(Id.)
On February 10, 2023, ASG responded to
NAVFAC SEs show cause notice. (Id. at 674- 86.) ASG
continued to assert that it had no obligation to provide
20 professionals under the task order. Rather, ASG
insisted that it was only obligated to provide
professionals once NAVFAC SE issued specific
assignments for work under the task order. (Id. at
675.) ASG disputed the notices characterization of
ASG presidents statement at the January 5, 2023
meeting as a repudiation or abandonment of the
contract. (Id. at 676.) Instead, ASG explained that its
president had attended the January 5th meeting to
ensure that the onboarding of ASGs employees would
proceed smoothly. (Id. at 680.) Regarding the shortage
of resumes it had provided by that date, ASG asserted
that post-pandemic labor-market conditions beyond its
control prevented it from providing a team of 20
professionals. (Id. at 674.) ASG also explained that it
was unable to perform because the Navy had not yet
paid ASGs monthly invoices, as required by the task
order. At that point, ASG had provided services for a
22a
few minor assignments under the task order. (Id. at
675-76.)
On April 4, 2023, NAVFAC SE issued a final
decision terminating the task order for default. (Id. at
1600-1605). In its decision, the contracting officer
identified that ASG was required as a minimum level
of service under the task order to provide the Navy
with a team of 20 professionals, and ASG had failed to
supply such a team. (Id. at 1600.) NAVFAC SE
justified its decision to terminate for default on ASG
having provided at the halfway point of the task order
a team of only five of the 20 required professionals. (Id.
at 1602.) NAVFAC SE asserted that ASGs position
that unforeseen labor-market conditions prevented it
from recruiting professionals was unavailing, because
ASG either knew or should have known of postpandemic labor-market conditions prior to submitting
its proposal. (Id. at 1603.)
C.
Payment Invoices and CDA Claims
ASG submitted six monthly invoices to NAVFAC
SE during performance of the task order. (ECF 17-3 at
1492-1501.) The invoices were for Base Requirement
for Base Period services provided between October
2022 and April 2023. (Id.) Each invoice was for the full
monthly amount stated in the task order, $281,870.00
(aside from the last invoice which did not cover a full,
month-long period). (Id.) The amounts invoiced were
the same as the estimated, monthly cost of employing
the 20-person team ASG had provided in Attachment
4 to its proposal, included in the task order as
Attachment 2.
23a
ASG submitted three certified claims to the
contracting officer seeking payments for the full
amounts of its fixed monthly prices, in accordance with
its monthly invoices. On January 9, 2023, ASG
submitted its first certified claim, seeking the
combined amount of its October and November 2022
invoices. (Id. at 1509-12.) It submitted a second claim
on March 8, 2023, seeking the combined amount of its
December 2022, January 2023, and February 2023
invoices. (Id. at 1743.) On April 18, 2023, the
contracting officer notified ASG that he had not made
a final decision on the claim submitted in January
2023 but would do so by June 30, 2023. (Id. at 1699.)
The contracting officer noted that the task order had
been terminated for default on April 4, 2023, and
NAVFAC SEs re-procurement with another contractor
could result in liability for ASG. (Id.) On May 4, 2023,
ASG submitted a third claim which sought the
combined total of its invoices from March 2023 to April
5, 2023. (Id. at 2239-41.)
The contracting officer issued the first decision on
any of ASGs claims in a June 28, 2023 decision which
addressed the March and May claims. The decision on
the March claim explained that ASG had already been
paid $156,396.80 for services rendered, and the
contracting officer denied the rest of the claim. (Id. at
2238.) The decision on the May claim explained that
ASG had been paid $77,812.85 for services rendered,
and the contracting officer denied the remainder. (Id.
at 2373.) In both cases, the contracting officer justified
the partial payments on Section H.8 of the task order,
which provides for a deduction in pay if there is a
vacancy within the [c]ontractors team. (Id. at 2372;
24a
see also 2237.) The contracting officer did not
correspond further with ASG about its original
January claim until August 18, 2023, when the
contracting officer informed ASG that it could expect
a final decision by December 15, 2023. (Id. at 1700.)
This decision arrived on December 1, 2023, when the
contracting officer denied the claim in its entirety
because ASG had failed to deliver the 20 [facilities
technical experts] required by the task order.4 (Id. at
1741.)
II.
PROCEDURAL HISTORY
After NAVFAC SE terminated ASGs contract for
default, ASG filed this suit in July 2023. (ECF 1.) The
complaint alleges first that NAVFAC SE improperly
terminated the task order for default. (ECF 1 at 34.)
The termination, the complaint alleges, entitles ASG
to damages or, in the alternative, a conversion to a
termination for convenience. (Id. at 35.) Second, the
complaint alleges that NAVFAC SE breached the
Jacksonville task order by failing to pay ASG under
the firm fixed-price contract. (Id.) Third, it alleges that
NAVFAC SE breached the implied covenant of good
faith and fair dealing by hindering ASGs performance
of the task order. (Id.) In support of this third claim,
the complaint alleges that NAVFAC SEs failure to
approve resumes in a timely manner, issue
4
The decision also addresses a July 18, 2023, claim for
anticipatory lost profits. (ECF 17- 3 at 1709.) No copy of this
claim appears among the records submitted by either party. In
any event, the contracting officer denied the claim. (Id.)
25a
assignments for ASG to perform, inform ASG of
upcoming assignments, provide site access to ASG
personnel, and require ASG to provide a team of 20
professionals at all times prevented ASG from
performing. (Id. at 36.)
The plaintiff moved for judgment on the pleadings
in November 2023 (ECF 15), and for summary
judgment in December 2023 (ECF 17). The defendant
responded to the motion for judgment on the pleadings
and cross-moved for summary judgment in February
2024. (ECF 23.) Both parties responded to the crossmotions. (ECF 24; ECF 25.) Oral argument was held
on March 12, 2024. At the close of oral argument, the
parties were encouraged to try to settle the case and
were allowed two weeks within which to do so; any
settlement discussions that may have taken place
apparently failed.
III. JURISDICTION
The Tucker Act, 28 U.S.C. § 1491(a), vests in the
Court of Federal Claims jurisdiction over claims for
money damages against the United States:
The United States Court of Federal Claims
shall have jurisdiction to render judgment
upon any claim against the United States
founded either upon the Constitution, or any
Act of Congress or any regulation of an
executive department, or upon any express
or implied contract with the United States,
or for liquidated or unliquidated damages in
cases not sounding in tort.
26a
28 U.S.C. § 1491(a)(1).
The Court of Federal Claims has jurisdiction over
claims for breach of contract founded upon an express
contract with the United States. Hercules Inc. v.
United States, 516 U.S. 417, 422 (1996). Here, the
plaintiffs claim is founded on an express contract with
a federal agency.
ASGs claims are founded on the CDA. 41 U.S.C.
§ 7104(b)(1). The court may hear a claim under the
CDA only if that claim has been submitted to the
relevant contracting officer, and the contracting
officer has issued a final decision on that claim. KCon Bldg. Systems, Inc. v. United States, 778 F.3d
1000, 1005 (Fed. Cir. 2015). A claim submitted to a
contracting officer must provide a clear and
unequivocal statement that gives the contract officer
adequate notice of the basis and amount of the claim.
Id. (quoting Contract Cleaning Maint., Inc. v. United
States, 811 F.2d 586, 592 (Fed. Cir. 1987)).
ASG submitted its claims to the contracting
officer in January, March, and May 2023, and the
contracting officer has issued final decisions on those
claims. The defendant does not dispute that
jurisdiction under the CDA over ASGs claims is
appropriate.
IV. STANDARDS OF REVIEW
The plaintiff has moved for judgment on the
pleadings pursuant to Rule 12(c) of the Rules of the
Court of Federal Claims (RCFC). To decide a motion
27a
for judgment on the pleadings, a court assumes that
all of the nonmovant's allegations are true and
indulges all reasonable inferences in favor of the
nonmoving party. Gummer v. United States, 40 Fed.
Cl. 812, 814 (1998). Judgment on the pleadings is
appropriate where there are no material facts in
dispute and the party is entitled to judgment as a
matter of law. Forest Laboratories, Inc. v. United
States, 476 F.3d 877, 881 (Fed. Cir. 2007).
Both parties have also cross-moved for summary
judgment. Under RCFC 56(a), a court shall grant
summary judgment if the movant shows that there is
no genuine dispute as to any material fact and the
movant is entitled to judgment as a matter of law.
Credibility determinations, the weighing of the
evidence, and the drawing of legitimate inferences
from the facts are inappropriate at the summaryjudgment stage. See Anderson v. Liberty Lobby, Inc.,
477 U.S. 242, 255 (1986). An issue is genuine only if
it may reasonably be resolved in favor of either
party, and a fact is material if it might affect the
outcome of the suit under the governing law. Id. at
248-50. Contract interpretation involves questions of
law and is therefore generally amenable to summary
judgment. Premier Office Complex of Parma, LLC v.
United States, 916 F.3d 1006, 1011 (Fed. Cir. 2019).
V.
DISCUSSION
The parties offer conflicting and inconsistent
interpretations of the task order.
The plaintiff argues that the terms of the PWS
28a
control; when other provisions of the task order conflict
with the PWS, the plaintiff argues the terms of the
PWS should prevail. Under the PWS, ASG chooses the
labor mix required to meet the assignments given by
the Navy. Thus, until the Navy gives ASG an
assignment to perform, ASG need not provide any
team members because it cannot know what the right
mix of professional skills would be to perform an
assignment until it receives one. ASG argues that a
reading of the task order requiring ASG to provide and
maintain a specific number of team members would
convert the task order into either a personal services
contract, which is prohibited by FAR 37.104, or a time
and materials contract, which must comply with FAR
16.601 to be valid. ASG therefore argues that its
reading is the only legally permissible one.
The defendant argues the opposite. The Navy
asserts that it was indeed procuring a team of 20
professionals, and the various provisions of the task
order make that clear. The Navy argues that its
reading of the task order is the only one that gives
effect to all the task orders terms, including the
requirement that the contractor supply a team of 20
professionals or face a reduction in payment if its team
endures a vacancy among the 20 positions for more
than five days. The defendant argues that because the
contractor would maintain total control over its
employees by assigning work and supervising team
members without interference by the Navy, the
contract contains safeguards adequate to avoid a
prohibited personal services contract.
ASG also argues that even if the Navys
29a
interpretation of the contract is correct, the Navy
failed to terminate the contract for default in the
manner required by FAR 52.249-8 and FAR 49.4023(f).
A.
Contract Interpretation
The central issue of contract interpretation in this
case is whether the task order requires the contractor
to compose and maintain a team of 20 professionals to
assist NAVFAC SE in performing the work of the
DCBL and whether these professionals had to meet
the qualifications described in Attachment 4 of ASGs
proposal, incorporated into the task order as
Attachment 2.
Contract interpretation must begin with the
plain language of the contract. Foley Co. v. United
States, 11 F.3d 1032, 1034 (Fed. Cir. 1993). In reading
that language, a court should interpret the contract in
a manner that gives meaning to all of its provisions
and makes sense. McAbee Const. Inc. v. United States,
97 F.3d 1431, 1435 (Fed. Cir. 1996) (citing Hughes
Communications Galaxy, Inc. v. United States, 998
F.2d 953, 958 (Fed. Cir. 1993)). Interpretations should
effectuate [the] spirit and purpose of the contract.
Hercules, 292 F.3d at 1381. Although a contract is
ambiguous if it is susceptible to more than one
reasonable meaning, Barron Bancshares, Inc. v.
United States, 366 F.3d 1360, 1375 (Fed. Cir. 2004),
the fact that each party can advance conflicting
interpretations of a contract does not on its own render
the contract ambiguous. Metric Constrs., Inc. v. Natl
Aeronautics & Space Admin., 169 F.3d 747, 751 (Fed.
30a
Cir. 1999).
This task order is a standard service contract as
defined in FAR Part 37. (ECF 17-3 at 55.) A service
contract under the FAR is a contract that directly
engages the time and effort of a contractor whose
primary purpose is to perform an identifiable task
rather than to furnish an end item of supply. FAR
37.101. Examples of service contracts provided in the
FAR include advisory and assistance services. Id.
1.
The plaintiffs interpretation
The plaintiff argues that the task orders PWS
empowers ASG to determine the make-up of its team
in response to assignments from NAVFAC SE. (ECF
17 at 25.) According to the plaintiff, the task order is
a service contract whose primary purpose is the
performance by ASG of identifiable tasks as assigned.
(Id. at 26 (quoting FAR 37.101).) This interpretation is
reinforced, the plaintiff argues, by the provision of the
PWS specifying that the contractor chooses the
precise labor mix necessary to complete the
assignment. (ECF 17-3 at 62.) As an example, the
plaintiff supposes that NAVFAC SE assigns ASG a
project exclusively seeking architectural services. In
that case, it reasons, ASG would need to bring in as
many architects as necessary to fulfill the tasks. (ECF
17 at 26.) If the next project assigned by NAVFAC SE
requires a team of civil engineers, ASG would then
replace the architects with as many civil engineers as
necessary. (Id.) This reading, the plaintiff argues, is
the only one that enables ASG to complete the full
range of assignments contemplated within the PWS as
31a
incorporated into Section C. (Id. at 27.)
Under the plaintiffs reading, the task order
requires the contractor to assemble rapidly a highly
qualified team suited to each assignment once
NAVFAC SE assigns a specific project. Sections like
A.2 specifying the makeup of the team that NAVFAC
SE anticipate[d] the awardee would need served to
put offerors on notice of the types of professionals the
Navy could require them to provide. (Id. at 33
(discussing Section A.2, ECF 17-3 at 55).) ASG read
this provision as a sensible warning, because under a
firm-fixed-price contract, the contractor would need to
provide the requested individuals no matter the cost.
Given the structure of a firm-fixedprice contract, the
plaintiff explains, it makes sense to establish a
base/minimum level of service for the contractor to
expect to have to provide. (ECF 17 at 34.) When the
language about a team of 20 professionals appeared as
an evaluation criterion in Section M of the solicitation,
ASG understood it to require offerors to demonstrate
they could provide 20 professionals with a variety of
skills; this criterion, ASG argues, did not suggest that
providing a team of 20 professionals was an obligation
under the task order and a prerequisite to completing
any assignments under the task order. (See id. at 37.)
ASG argues that a reading of the task order
requiring it to hire and maintain a team of 20 facilities
technical experts outside of any specific assignments
would render the PWS meaningless, potentially
impossible, and illegal. (Id.) First, it asserts that the
PWS would be meaningless because if the task order
only obligates ASG to provide a team of 20
32a
professionals, then the scope of work so carefully
detailed in the PWS is superfluous and absurd. (Id.)
Second, performing the assignments contemplated by
the PWS would be impossible. If ASG is always bound
to maintain the slate of professionals proposed in
Attachment 2, it very likely will not be able to
perform assignments requiring, for example, only
architects. (Id.) Third, requiring ASG to maintain and
complete assignments with a team of 20
predetermined professionals would strip ASG of its
right to determine the how of performance. (Id. at
28.) As a result, NAVFAC SE would have control over
performance of the task order in violation of FAR
37.104(d). (Id.)
Under the plaintiffs interpretation, the PWS is
central. That section sets forth ASGs performance
obligations under the [task order]. (ECF 24 at 11.)
Each section of the task order that references the
contractors performance, the plaintiff notes, points the
reader to the PWS. (Id.) ASG interprets the
deliverables section, F.4, to list 8 types of deliverables
of work-product anticipated to be performed based on
PWS tasks. (ECF 17 at 28-29.) It argues that the
representative team ASG proposed in Attachment 4 of
the solicitation, while incorporated into the contract,
is not an irrevocable promise to deliver these
personnel in a manner unmoored from the rest of the
contract. (ECF 24 at 18.)
2.
The defendants interpretation
In the defendants interpretation, the task orders
central purpose is to provide NAVFAC SE with a team
33a
of 20 facilities technical experts to advise on projects at
NAS Jacksonville as they arise. Its reading starts from
the text of Section A, in which the task order notes
that a team of 20 professionals is the base/minimum
level of service. (ECF 23-2 at 3.) This requirement has
been clear, the defendant argues, since the solicitation,
which noted in its evaluation criteriaSection
Mthat offerors shall submit a team that reflected
the requirements specified in Section A.2, i.e., a team
of 20 professionals. (Id. at 118.)
In addition to these express requirements of the
solicitation and task order, the solicitation made clear
that the team proposed by each offeror on Attachment
4 of its proposal would be incorporated into the task
order at the time of award. (ECF 23-3 at 118.) ASG
confirmed its understanding of this fact when, in reply
to the contracting officers pre-award email, its
president acknowledged that ASG was aware that, if
awarded the task order, it would be obligated to
provide a team whose qualifications matched those it
had listed in Attachment 4 of its proposal. (ECF 23-3
at 217.)
Because the purpose of the task order is to
provide a team of 20 professionals to advise NAVFAC
SE at NAS Jacksonville, the defendant argues that the
task order permits NAVFAC SE to review the resumes
of prospective team members. (ECF 23 at 47.) The first
deliverable due according to the schedule provided in
Section F.4 required ASG to submit resumes of the 20
prospective team members within five days of task
order award. (Id.) The defendant argues that neither
this requirement, nor NAVFAC SEs ability to accept
34a
the resumes in accordance with Section G.6, violates
FAR 37.104s prohibition on personal service contracts.
(Id. at 49, 14.) During drafting, a contracting officer
implemented safeguards to avoid a personal services
contract and formally certified this fact before
publication of the task order. (Id. at 49.) The task
order is not a personal services contract, the defendant
argues, and NAVFAC SE did not create one by trying
to enforce the contract terms and reviewing ASGs
deliverables. (Id.)
3.
The defendants interpretation is
the only reasonable one
The fact that the task order is a firm-fixed-price
contract is not itself dispositive. A firm-fixed-price
contract is not subject to any adjustment on the basis
of the contractors cost experience in performing the
contract. FAR 16.202-1. Such a contract does not,
however, necessarily entitle the contractor to the full
amount of compensation when it does not perform the
contract in full. See Pacific Coast Community Services
v. United States, 858 Fed. Appx. 346, 349 (Fed. Cir.
2021) ([A] firm-fixed-price contract requires the
contractor to charge the government a fixed price for
services but does not provide that the government
must pay that price when the contractor does not
deliver the services.). Section H.8 provides for a price
reduction if the contractors team membership falls
below 20 people. (ECF 17-3 at 84.) Here, the monthly
rate NAVFAC SE was to pay ASG was the total cost of
employing each of the 20 professionals, $218,870.00.
(ECF 17-3 at 89 (showing the monthly cost of each
employee); ECF 17 at 30 (stating the monthly cost,
35a
which reflects the sum of each employees monthly
rate).) Following the structure of a firm-fixed-price
contract, ASG requested this monthly amount in each
of its certified claims to the contracting officer. (ECF
17-3 at 1509-12, 1743, 2239-41.)
ASG argues, however, that the provisions of the
task order specifying a team of 20 reflect the Navys
best estimate of how many employees, and their
respective qualifications, would be required to fulfill
the requirements of the task order. ASG relies on the
word anticipates in Section A. (ECF 23-2 at 3
(emphasis added) (at the time of initial contract
award, the [g]overnment anticipates a staff of 20
experts).) ASG explains that the provisions reflecting
a team of 20 were designed to allow offerors, and the
eventual awardee, to price their offers appropriately,
because under a firm-fixed-price contract, the awardee
would bear the financial risk if it ultimately required
more resources to fulfill the assignments NAVFAC SE
gave it. The parties have provided conflicting readings
of the task order, but no party has suggested that
provisions of the task order itself are internally
inconsistent such that the Seaport NxG contracts
order of precedence clause would apply to resolve the
conflict. Overall, the defendants interpretation best
harmonizes all the task orders provisions and is most
consistent with its purpose. The first section of the
task order makes a team of 20 technical experts a
requirement from the outset. Section A.2 opens with
the proviso, relied on by ASG, that at the time of
initial contract award, the [g]overnment anticipate[d]
that a staff of 20 experts across specified disciplines
would be required, and that the team would be
36a
subject to change. (Id.) In the next sentence,
however, Section A.2 specified that the staff of twenty
(20) professionals is the base/minimum level of
service. (Id. (emphasis added).)
Later sections comport with or do not conflict with
Section As language. Section B supports the
defendants reading. Under Section B, the Navy
retained the option to increase the number of
employees working for the contractor on the task
order. If the contractor retained the full discretion to
determine appropriate staffing for any assignment,
there would be no need for the Navy to have retained
the option of awarding the contractor additional funds
to increase the size of the team.
The PWS, Section C, requires the contractor to
provide, manage, and supervise a multidisciplinary
team of facilities technical experts. (Id. at 10.) The
PWS provides that the contractor chooses the precise
labor and staffing mix to fulfill assignments. (Id.) The
PWS is silent on the size or composition of the staffing
mix. The PWS is the heart of the task order. A
contractor would expect this central part of the
contract to specify in detail what tasks will be
performed; other provisions often reflect boilerplate
language to guide the parties execution of those tasks.
In this case, however, it is the PWS that is almost
perfunctory, and the surrounding sections more
specific. In this regard, the task order is written
inside-out.
Although not expressed as clearly as it should
have been, the PWS implicitly requires the contractor
37a
to provide a team ready to advise on any projects
NAVFAC SE assigns to it. As part of its supervisory
role over its employees under the task order, ASG had
to provide NAVFAC SE with a weekly report setting
out, among other items, active projects for each
[facilities technical expert]; ASG was not required to
report each week on the progress of each assigned
project. (Id. at 12.) This requirement contemplates a
standing team ready to take on projects as they are
assigned so that the Navy can track the work of the
team members, rather than track the staffing of
discrete assignments.
In Section F.4, the calendar of deliverables
assumes a team of 20 professionals.5 The calendar
5
Section F.4 contains the following deliverables:
1.
Design Drawings & Specifications. Date of Submission:
At project milestones (ex: 35%, 65%, 100%).
2.
Requests for Proposals (RFP). Date of Submission: 100%
Pre-Final.
3.
Design Review Comments. Date of Submission: At
project milestones (ex: 35%, 65%, 100%).
4.
Quantity Takeoffs for Cost Estimates. Date of
Submission: At project milestones (ex: 35%, 65%, 100%).
5.
Construction Cost Estimates. Date of Submission: At
project milestones (ex: 35%, 65%, 100%).
6.
Project Status Report for Assigned Projects. Date of
Submission: Weekly.
38a
required that, [w]ithin five days of award of task
order, the awardee was required to submit a resume
for each position proposed in accordance with the
[c]ontractors proposal and the PWS. (Id. at 19.) The
parties dispute what task order means in this
context. The plaintiff contends that the term refers to
individual project assignments issued under the
Jacksonville task order. (ECF 17 at 35.) Only after
NAVFAC SE issues an assignment (which the plaintiff
refers to as a task), would ASG be obligated to
submit resumes for that assignment within five days.
(Id.) The defendant interprets task order to refer to
the Jacksonville task order. (ECF 23 at 47.) This
interpretation requires that the 20 resumes of the
members of ASGs prospective team would have been
due by October 3, 2022, five days after award of the
Jacksonville task order. (See ECF 23-2 at 19.)
The defendants interpretation of the table of
deliverables is the better reading of the task order. The
term task order is singular and does not contemplate
multiple submissions. On the other hand, other
deliverables listed on the table contemplate multiple
submissions, with various due dates at project
milestones or weekly. (Id.) These plural project
milestones contrast with the singular reference to
7.
Work Schedule. Date of Submission: Monthly (due by
the 5th working day of the month).
8.
Resume for each position proposed in accordance with
the Contractors proposal and the PWS. Date of
Submission: Within five days of award of task order.
(ECF 23-2 at 19.)
39a
task order, suggesting that deliverables regarding
assignments under the Jacksonville task order would
occur repeatedly. In this context, the one-time,
singular reference to task order most logically refers
to the Jacksonville task order, and not the recurring
assignments within it. If ASG were required to submit
resumes at the outset of each assignment under the
Jacksonville task order, the deliverable table would
use language reflecting those repeated submissions,
just like the project milestones and weekly report
deliverables. Unless context requires otherwise, a term
should be read consistently throughout at least the
same provision of a contract. See Imation Corp. v.
Koninklijke Philips Elecs. N.V., 586 F.3d 980, 990
(Fed. Cir. 2009) (cleaned up) (A proper interpretation
of a contract generally assumes consistent usage of
terms throughout the [a]greement.).
Further, a task order is defined as an order for
services placed against an established contract or with
government sources. FAR 2.101. Interpreting task
order to mean the Jacksonville task order comports
with this definition in the FAR, because the
Jacksonville task order was issued pursuant to an
established government contract: the Seaport NxG
Contract. The Jacksonville task order also expressly
identifies itself as a task order in Section A.1. Section
A.1 notes that the Jacksonville task order is a Firm
Fixed Price (FFP) task order. (ECF 17-3 at 55.)
The singular word award in Section F.4 also
suggests the full slate of resumes was due on October
2, 2022, and not five days after NAVFAC SE issues
each assignment. Assignments given to ASG under the
40a
task order would not be awarded to it; once ASG was
awarded the Jacksonville task order, there would be
no competition for further assignments under that
task order. Therefore, it is implausible to interpret the
phrase award of the task order as referring to the
order of each assignment given to ASG by NAVFAC
SE under the Jacksonville task order.
Section G of the task order provides further
support for the defendants interpretation that the
task order requires a fulltime team of 20 professionals
as the baseline of performance under the contract.
Section G contains a section titled Submission and
Substitutions of Key Personnel. (ECF 23-2 at 25.) In
explaining the resume requirement, Section G.6 notes
that all resumes for proposed individuals will be
submitted after award in accordance with Section F.4.
(Id. 25.) Again, the term award in the singular is best
read refer to the award of the Jacksonville task order,
because assignments given to the contractor under
that task order would not be awarded. In addition,
the term appears again in the singular. Under the
contract, the Navy expected to make multiple
assignments to the contractor; use of the singular
award is best construed as applying to the one award
of the governing Jacksonville task order.
Upon submitting resumes for its 20 team
members, the contractor had to certify that the
proposed individuals had agreed to accept the position
upon acceptance by the [g]overnment. (Id.) This
language again suggests that the Navys goal under
the contract was to hire a vetted team of
41a
professionals.6
Finally, interpreting Section A.2s language
according to its ordinary usage gives meaning to
Section H.8, which describes what would happen when
the contractors team experiences a labor shortage.
Section H.8 provides that [i]f at any time there is a
vacancy within the [c]ontractors team (i.e. all twenty
(20) positions are not filled), the contractor must fill
the vacancy within five days, or the Navy would reduce
payments to the contractor otherwise due for that
vacant position until another professional joins the
team. (Id. at 32.) This clause is meaningless if the
contract does not require ASG to provide and maintain
a team of 20 professionals.
Essentially, the plaintiff treats the PWS as the
6
In his first submission of resumes to the Navy, ASGs
president seemed to share this interpretation. As noted in Section
I.B, above at 5-6, he wrote to the contracting officers
representative on October 3, 2022, that he had been able to
obtain 2 of the 20 and would continue to submit resumes until
all 20 [were] filled. (ECF 23-2 at 223.) This interpretation
changed gradually, beginning with an October 6, 2022, email in
which ASGs president pushed back against NAVFAC SEs
request that future resumes comply with the labor mix ASG had
provided in Attachment 2 of the task order. He noted there that
it was up to ASG to [ ] hire who it has reasons to believe in good
faith can deliver services per Section C. (Id. at 230.) He began to
protest the Navys interpretation of the number of professionals
required under the task order in an October 13, 2022, email,
writing that ASG has the prerogative to change the labor mix
and quantity as [ASG] deem[s] fit to execute the work. (Id. at
269.)
42a
central and governing portion of the contract. Under
ASGs reading, the other sections of the task order are
important in providing the obligations and limits of the
parties contractual relationship, but only the PWS
establishes the contractors obligations under the task
order. A PWS is the statement of work . . . that
describes the required results in clear, specific and
objective terms with measurable outcomes. FAR
2.101. As previously noted, it is hard to conceive or
explain why the PWS does not include any reference to
what the defendant now insists is the contracts
central purpose, i.e., to provide the Navy with a team
of 20 professionals. Perhaps the Navy thought that by
placing the requirement for a team of 20 professionals
in Section A.2, it was highlighting the primary purpose
of the task order for offerors; if that is what the Navy
thought it was doing, its effort was ineffective.
Contractors generally look to the PWS to ascertain
exactly what goods or services they will be obligated to
provide or perform under a contract. The provisions
that surround the PWS typically support it by
providing boilerplate mechanisms to guide the parties
execution of the contract. Here, however, it is the PWS
that describes the advisory work of the contractors
team in broad, generic language, while the
surrounding provisions more clearly require a team of
20. A simple reference to the hiring of 20 professionals
when the PWS already mentions the contractors
team could have avoided this entire dispute, both
preserving ASGs standing as a reputable government
contractor and the Navys progress on its essential
projects.
A court must read all provisions of a contract
43a
together and give effect to each of them. The provisions
of the Jacksonville task order are best harmonized if
Section A.2 is taken at face value: while the Navy
could only anticipate its precise needs, the awardeesupplied team of 20 interdisciplinary professionals was
the base/minimum level of service. Section C
describes the assignments the contractors
interdisciplinary team will be given to accomplish;
Section F requires the contractor to submit resumes of
its prospective team members within five days of
award of task order; Section G describes the required
content of the resumes and explains that the
prospective employees must agree to work upon
acceptance by the government; and Section H
mandates that the contractor maintain its staff of 20
at all times or face a payment reduction. The plaintiffs
interpretation requiring only a to-be-determined team
of an unspecified makeup corresponding to specific
assignments is inconsistent with the language of
Section A.2 and requires strained interpretations of
the other provisions of the contract.
The logistical processes involved in performance
of the task order also support the defendants
interpretation that a team of 20 professionals was a
central requirement of the task order. The contractors
authority to choose a staffing mix in the PWS does not
mean that the Navy expected the contractor to
overhaul the makeup of its team in response to each
individual assignment. Both parties address the
onboarding process all the professionals had to
undergo before they could report to work. The
defendant explained that the security and background
screenings for each proposed ASG employee could take
44a
up to two months before that employee could access
NAS Jacksonville to perform the assignment. (ECF 23
at 13.) Emails submitted by the plaintiff convey ASGs
frustration that the onboarding process was moving
more slowly than expected. (See, e.g., ECF 17-3 at 361,
374.) The existence of these administrative hurdles
further strains ASGs reading of what the task order
required. These mandatory processes are also
antithetical to the one-year term of the task order.
NAVFAC SE would need to have ASG assemble a team
as soon as it awarded the task order so that the team
could provide advice and technical assistance to the
Navys projects at NAS Jacksonville, as the task order
required. (ECF 23-2 at 10.) A workflow in which
NAVFAC SE assigns a project to ASG, ASG then
recruits and hires qualified personnel, the personnel
then undergo screening and onboarding for two
months, and only then can provide the services needed
by the Navy is impracticable. A reading that requires
this result, as the plaintiffs does, is therefore
implausible and should be avoided. The defendants
reading of the task order is consistent with the plain
meaning of the task order language, best harmonizes
all provisions of the task order, and is the reasonable
interpretation, given the task orders purpose. The
plaintiffs interpretation does not produce a reading of
the task order that gives meaning to all of its parts to
effect the Navys purpose: to have ASG provide a team
of 20 professionals who satisfied the qualifications
described in ASGs proposal.
B.
Personal Services Contract
Given that the defendants interpretation of the
45a
task order is the only reasonable one, the next step is
to analyze whether, under that interpretation, the task
order becomes a personal services contract that would
violate FAR 37.104 or an improperly executed time
and materials contract under FAR 16.601.
The plaintiffs primary argument in advocating
for its interpretation of the task order is that under the
governments reading the task order is an illegal
personal services contract. An interpretation that
renders a contract illegal cannot be a reasonable
interpretation. See Bay Co., FL v. United States, 112
Fed. Cl. 195, 202 (2015); Cray Research, Inc. v. United
States, 44 Fed. Cl. 327, 333 (1999) (quoting Hobbs v.
McLean, 117 U.S. 567, 576 (1886)) (where a contract
is fairly open to two constructions, by one of which it
would be lawful and the other unlawful, the former
must be adopted). Here, the defendants
interpretation of the task order is the reasonable
construction, so it must be determined whether that
interpretation renders the contract illegal. The
difference between a de facto personal services
contract and a nonpersonal services contract often
means the difference between an unlawful and a
lawful services contract. Off. of Fed. Contract
Compliance Progs. v. Florida Hosp. of Orlando, 2013
WL 3981196, at *17 (U.S. Dept of Labor Adm. Rev.
Bd. Jul. 22, 2013) (en banc).
FAR 37.104(a) defines a personal services
contract as one characterized by the employeremployee relationship it creates between the
[g]overnment and the contractors personnel. Such a
contract is illegal because it circumvents laws that
46a
govern the procedures for hiring federal employees. Id.
In assessing a contract, the key question is whether
the government will exercise relatively continuous
supervision and control over the contractor personnel
performing the contract. FAR 37.104(c). The FAR lists
six factors that guide an assessment of whether a
personal services contract exists:
1.
Performance on site.
2.
Principal tools and equipment furnished by
the Government.
3.
Services are applied directly to the integral
effort of agencies or an organizational
subpart in furtherance of assigned function
or mission.
4.
Comparable services, meeting comparable
needs, are performed in the same or similar
agencies using civil service personnel.
5.
The need for the type of service provided can
reasonably be expected to last beyond 1 year.
6.
The inherent nature of the service, or the
manner in which it is provided, reasonably
requires directly or indirectly, Government
direction or supervision of contractor
employees.
FAR 37.104(d).
Of these factors, the last one aligns most closely
47a
with the FARs key question underlying whether an
employer-employee relationship between a contractors
staff and the government has been created.
Caselaw closely adheres to the FARs designation
of the governments degree of supervision over
contractor personnel as the key question in
determining whether a contract is impermissibly for
personal services. As the Federal Circuit has noted,
the principal ground on which a contract will be found
to be a personal services contract . . . is the degree of
supervision to which the contracting employees were
subject under the contract. Seh Ahn Lee v. United
States, 895 F.3d 1363, 1371 (Fed. Cir. 2018). The fact
that some of the factors listed in FAR 37.104(d) are
met under a contract does not per se render[ ] the
contract a personal services contract; instead, such
factors are merely to be used as indicia of continuous
supervision and control of contractor personnel by the
government. John Douglas Burke v. Dept. Health &
Human Services, CBCA 7492, 23-1 B.C.A. ¶ 38304
(Mar. 10, 2023) (quoting W.B. Jolley, B- 234146, 89-1
CPD ¶ 339 (Comp. Gen. Mar. 31, 1989)).
Before issuing the solicitation, the Navy analyzed
whether the task order would constitute an illegal
personal services contract. The contracting officer
determined that five of the six factors listed in FAR
37.104(d) would be met under the contract. After this
finding, the Navy implemented additional safeguards
in the task order. It added language to clarify that the
contractor [would] choose[ ] the precise labor and
staffing mix and to require the contractor to provide,
manage, and supervise the team. (ECF 23-2 at 10.)
48a
With these provisions, even though ASGs employees
were working onsite and with government-provided
tools, ASG would assign and control the daily activities
of its employees performing work under the task order.
The lack of Navy control over ASGs employees would
prevent the creation of an employer-employee
relationship between the government and ASG
personnel. (ECF 23 at 49; see also ECF 23-2 at 10.)
The fact that several of the factors of FAR
37.104(d) would be met does not necessarily mean that
the task order violates the FAR. In Seh Ahn Lee v.
United States, the Federal Circuit explained that the
FAR 37.104(d) factors are far from definitive. 895
F.3d at 1371. Indeed, meeting several of FAR
37.104(d)s analysis criteria does not dictate that an
executed contract will be deemed void. Id. at 1372.
Instead, the controlling question, which assumes
greater importance as more of the other factors listed
in 37.104(d) are met, is whether the language of the
task order or the manner of its administration gives
the agency control over the work of the contractors
employees.
The task order specifically left the control of
ASGs employees to ASG. The Navy would assign work
to ASG. ASG would then select which members of the
20-person team were appropriate to execute the work;
ASG would control the daily activities of the team. The
Navy was allowed to inspect the completed work to
ensure it was satisfactory. Otherwise, from the
assignment of the work to its completion and review by
the Navy, ASG was in control of its team. Because
ASG, not the Navy, assigned work to its employees
49a
and managed their daily activities, the Navys
determination that the task order would not create a
personal services contract was correct.
Although the task order did not create a personal
services contract, the inquiry is not ended. A personal
services contract may arise either by the contracts
terms or the manner of its administration during
performance. FAR 37.104(c)(1). ASG argues that
NAVFAC SEs insistence on reviewing and retaining
approval rights over the hiring of ASGs employees
created a personal services contract. The defendants
interpretation of Section G.6 as allowing NAVFAC SE
to approve resumes would lead, the plaintiff argues, to
an absurd result of NAVFAC SE controlling the labor
mix as if this were a personal services contract. (ECF
24 at 15.) By reviewing resumes to ensure they meet
the qualifications promised by ASG in Attachment 4 of
its proposal (and incorporated into the task order as
Attachment 2), the plaintiff argues, NAVFAC SE
stripped [ASG] of its right to determine the how of
performance. (Id. at 27.) Beyond violating the FAR,
the plaintiff contends that the Navys actions also
violated the PWS, which grants the contractor the
right to choose the labor mix needed to complete an
assignment. (Id. at 39-40.) It does not argue why this
labor mix could not refer to a selection of
professionals drawn from the contractors existing
team of 20. Once the Navy approves the contractors
team, the task order gives the contractor freedom to
select which individuals to use on any given
assignment.
When examining performance, an order for a
50a
specific article or services, with the right to reject the
finished product or result, is not the type of
supervision or control that converts . . . an
independent contractor (such as a contractor
employee) into a [g]overnment employee. FAR
37.104(c).
While no federal court has addressed FAR
37.104(d) in a factually similar case, decisions of the
Comptroller General have found that agencies may
review contractor personnel without creating a
personal services contract. See The Endmark Corp., B278139 (Comp. Gen. Dec. 31, 1997) (quoting FAR
37.104(c)(1)) (an agencys evaluation of a key
employees performance . . . does not establish or
evidence an employer-employee relationship marked
by relatively continuous supervision and control [of
the non-government employee] by a [g]overnment
officer or employee, as required to constitute an
improper personal services contract). Agencies have
discretion to determine [their] needs and the best
method to accommodate them, and a partys
disagreement with the agencys determination about
its needs does not establish that the agencys
judgment is unreasonable. Matter of: Ronald L. Glass,
B-417855 (Comp. Gen. Nov. 21, 2019).
The plaintiffs argument that NAVFAC SEs
administration of the task order created an illegal
personal services contract rests on the Navys
insistence on reviewing the resumes and approving the
hiring of ASGs prospective employees. The plaintiff
neither alleges nor argues that other statements or
actions by NAVFAC SE resulted in an employer51a
employee relationship between ASGs personnel and
the Navy. The plaintiff also does not allege that
NAVFAC SE attempted to supervise or interfere with
ASGs employees performance of their jobs at all; its
argument pertains only to allegations that NAVFAC
SE attempted to supervise ASGs recruitment of those
employees. Once on site, neither the task order nor
NAVFAC SEs actions reflect that the agency had any
supervisory involvement with ASGs team members.
The Navys insistence on reviewing and approving
resumes, on its own, is not sufficient to demonstrate
that NAVFAC SE administered the task order in a
manner that created a personal services contract. The
delivery by ASG of resumes matching the
qualifications of the contractors proposal was a
specific deliverable under Section F.4 of the task order.
The right of NAVFAC SE to review and accept the
resumes of proposed ASG team members before the
team member could work at NAS Jacksonville is not
the type of supervision or control that converts a
contractor into a government employee. FAR
37.104(c)(1). Once it is established that the task order
calls for an interdisciplinary team of 20 professionals,
it is within NAVFAC SEs discretion to screen resumes
of prospective contractor employees. Agencies have
discretion to determine their needs and the best way
to meet them. See Ronald L. Glass, B-417855. This
limited involvement by the Navy of reviewing resumes
to ensure they met the qualifications proposed by ASG
in its response to the solicitation does not create a
personal services contract; rather the submission of
the resumes of its prospective employees was a
deliverable under the contract. The Navys review and
52a
approval of resumes did not involve any governmental
supervision of ASGs employees, and none of these
actions interfered with ASGs performance of the task
order in violation of the covenant of good faith and fair
dealing.
Following
the
defendants
reasonable
interpretation of the task order does not render the
task order an illegal personal services contract in
violation of FAR 37.104. The plaintiff has not shown
that the defendants interpretation of the task order
could render it an improperly executed time and
materials contract. The FAR mandates that time and
materials contracts be used only when it is not
possible . . . to estimate accurately the extent or
duration of the work or to anticipate costs with any
reasonable degree of confidence. FAR 16.601(c). In
such a case, the contracting officer must prepare and
submit for agency approval a determination and
findings that no other contract type is suitable. FAR
16.601(d)(1). The defendants interpretation of the task
order is the most reasonable, and under that reading
the task order is a one-year contract which requires
the contractor to provide a team of 20 advisory
professionals. The duration is established and
undisputed by the plaintiff. Moreover, the firmfixedprice structure of the task order means that the costs
are established beyond a reasonable degree of
certainty. ASG provided the cost of employing each
team member in its proposal, and those rates added
together became the contract price. Nothing in the
record indicates that these variables were ever in
doubt by ASG or NAVFAC SE, and no evidence
suggests that NAVFAC SE ever contemplated
53a
implementing a time and materials pricing structure.
C.
Termination for Default
The defendant correctly interprets the task order
to require the contractor to provide a multidisciplinary
team of 20 professionals, and such an interpretation
does not create a personal services contract in violation
of FAR 37.104. Even so, the evidence must also
demonstrate that NAVFAC SE correctly effected the
termination in accordance with the requirements of
FAR 52.249-8 and FAR 49.402-3.
1.
FAR 52.249-8
Pursuant to FAR 49.504(a)(1), the provisions of
FAR 52.249-8 were included in the contract. Under
FAR 52.249-8(a)(1), an agency may terminate a
contract for default if the contractor fails to (i)
[d]eliver the supplies or to perform the services within
the time specified in th[e] contract or any extension;
(ii) [m]ake progress, so as to endanger performance of
th[e] contract . . . ; or (iii) [p]erform any of the other
provisions of th[e] contract. An agencys right to
terminate a contract for default pursuant to
subparagraphs (ii) and (iii) requires that it first
provide the contractor notice and offer the contractor
a 10-day window to cure the failure. FAR 52.2498(a)(2).
The Federal Circuit provided the standard for
evaluating an agencys decision to terminate a contract
for default in Lisbon Contractors, Inc. v. United States.
828 F.2d 759 (Fed. Cir. 1987). A termination for
54a
default require[s] a reasonable belief on the part of
the contracting officer that there was no reasonable
likelihood that the [contractor] could perform the
entire contract effort within the time remaining for
contract performance. Id. at 765 (cleaned up).
The plaintiff argues that there is no allegation
and no evidence of any failure to perform services
requested by NAVFAC SE. (ECF 24 at 23.) It explains
that ASG performed every task NAVFAC SE assigned
it. Despite ASGs successful performance of each
assigned task, the Navy insisted that ASGs
performance was inadequate because ASG did not hire
or provide resumes for the number of facilities
technical experts required under the task order. (Id.)
As a result, the plaintiff argues, NAVFAC SE wrongly
claimed that it could not assign ASG all the projects it
anticipated accomplishing through the task order. (Id.)
The plaintiffs argument turns on its reading,
already rejected, of what the task order required.
Under the plaintiffs reading of the task order, the
Navy assigns projects to ASG, and only then does ASG
assemble the appropriate team; because ASG
performed each sub-task the Navy assigned, it did not
fail to perform any work required by the task order.
(Id. at 23-24.) The defendant argues that because the
point of the task order was to appoint a team of 20
facilities technical experts, the plaintiffs failure to do
so clearly justifies a termination for default. (ECF 25
at 23.) The defendant has offered the better reading of
the contract. Under this reading, ASG failed to
perform.
55a
Given that the defendants reading of the task
order is the better one, the plaintiffs argument (ECF
24 at 25) that it did not fail to perform as required
under the task order is rejected. See 52.249-8(a)(1)(i).
ASG had to submit 20 resumes to the Navy within five
days of the award of the task order, which was October
3, 2022. ASG did not do so by that date. Indeed, ASG
never did so.
The plaintiffs analyses of the termination
according to FAR 52.249-8(a)(1) factors (ii) and (iii)
follow the same logic and must be rejected for the same
reason: they rest on ASGs flawed reading of the
requirements of the task order.
ASG materially failed to perform. It did not
provide the required services of assembling a fully
staffed team. This failure in turn limited the projects
that NAVFAC SE could assign. ASG never made
sufficient progress toward assembling the team. As of
March 2023, halfway through the contract period, ASG
had retained only four employees who reported to work
at NAS Jacksonville. (ECF 25-1 at 71-72 (decl. of the
contracting officer).) Given ASGs performance halfway
through the contract term, it was reasonable for the
contracting officer to determine that insufficient time
remained both for ASG to assemble the required team
and for that team to carry out the tasks NAVFAC SE
sought to assign to the team.7
7
The contracting officer also supported the default
termination decision by asserting that ASG had repudiated the
task order. According to the defendant, repudiation occurred
56a
While meeting any one factor of FAR 52.2498(a)(1) can justify termination for default, ASGs
performance met all three of them.
ASG also argues that even if its performance
provided proper grounds to terminate the task order
pursuant to FAR 52.249-8, the termination is
nevertheless invalid because ASG did not receive a
notice to cure as required by FAR 52.249-8(a)(2). (ECF
24 at 26.) ASG argues that although it received a cure
notice letter and a show cause notice on December 5,
2022, and January 20, 2023, respectively, these notices
did not provide ASG with the opportunity to cure. It
could only cure, the plaintiff reasons, by performing
assignments. ASG repeatedly requested information
on projects to perform and was denied that
information. (Id.) This alleged denial prevented ASG
from having a meaningful opportunity to cure. (Id.)
The plaintiffs argument, again, relies on its
during a meeting on January 5, 2023. (ECF 23-2 at 672.) During
that meeting ASGs president allegedly stated that ASG cannot
meet Attachment 4 (referring to Attachment 2 of the task order).
(Id.) NAVFAC SE viewed this statement as anticipatory
repudiation. (Id.) ASG has repeatedly denied that it repudiated
the task order. In an email to a NAVFAC SE representative,
ASGs president wrote, at no time did I repudiate [ ]or state for
the record that I cannot meet Attachment 4 but did articulate the
challenges as I have consistently done. (ECF 23-2 at 1520.) On
the evidence provided by the parties, ASGs alleged repudiation of
the task order is a factual dispute unfit for resolution on summary
judgment. Because the termination for default was appropriate
regardless of whether repudiation occurred, the factual dispute
over this issue does not preclude summary judgment.
57a
faulty reading of the task order, already rejected. It
received and responded to the December 5, 2022 and
January 20, 2023 notices. (ECF 23-2 at 532-34, 67486.) Rather than hire a team of 20 in response to either
notice, ASG continued to insist that it was not
required to do so. On their face, the notices provided to
ASG reflect that the Navy had advised ASG of its
failures to perform and gave ASG the opportunity to
comply with the terms of the task order. ASG never
did. The Navy effected the termination in compliance
with FAR 52.249-8.
2.
NAVFAC SEs Consideration of the
FAR 49.402-3(f) factors
When an agency is contemplating a termination
for default, FAR 49.402-3(f) outlines seven factors that
the contracting officer shall consider:
(1) The terms of the contract and applicable
laws and regulations.
(2) The specific failure of the contractor and
the excuses for the failure.
(3) The availability of the supplies or
services from other sources.
(4) The urgency of the need for the supplies
or services and the period of time required to
obtain them from other sources, as compared
with the time delivery could be obtained
from the delinquent contractor.
58a
(5) The degree of essentiality of the
contractor in the Government acquisition
program and the effect of a termination for
default upon the contractors capability as a
supplier under other contracts.
(6) The effect of a termination for default on
the ability of the contractor to liquidate
guaranteed loans, progress payments, or
advance payments.
(7) Any other
circumstances.
pertinent
facts
and
The plaintiff argues that NAVFAC SE failed to
satisfy the requirements of FAR 49.402-3(f) when
terminating ASG for default. The plaintiff asserts that
consideration of the seven factors found in FAR
49.402-3(f) is mandatory, and that the contracting
officer failed to consider any of them. (ECF 17 at 47-48;
ECF 24 at 30-33.) As a result, the plaintiff contends,
the contracting officer failed to exercise his discretion
as required to terminate ASG for default, thereby
undercutting the validity of the termination. (ECF 24
at 30-31.) The defendant argues that the seven factors
identified in FAR 49.402-3(f) are irrelevant because
ASG failed to perform under the task order and
repudiated. (ECF 23 at 55.)
Although FAR 49.402-3(f) requires contracting
officers to consider the seven factors in deciding to
terminate a contract for default, the evaluation of
these factors is not a prerequisite to a valid
termination. DCX, Inc. v. Perry, 79 F.3d 132, 135 (Fed.
59a
Cir. 1996). The provision of the FAR setting out these
factors does not confer any enforcement rights on a
defaulting contractor. Id.; see also Minelli v. United
States, 1995 WL 424858, at *4 (Fed. Cir. July 18,
1995). Accordingly, a contracting officers failure to
consider one or more of the factors does not require
that a termination for default be converted into a
termination for convenience. DCX, Inc., 79 F.3d at 135.
While the factors outlined in FAR 49.402-3(f) are
not mandatory, an agencys compliance or
noncompliance with them may aid a court in
determining whether a particular termination for
default reflects an abuse of the contracting officers
discretion. See Darwin Constr. Co. v. United States,
811 F.2d 593, 598-599 (Fed.Cir.1987); DCX, Inc., 79
F.3d at 135; PCL Const. Servs., Inc. v. United States,
47 Fed. Cl. 745, 781 (2000) (contracting officers
decision to terminate contract for default was
reasonable despite no written analysis of enumerated
consideration of FAR 49.402-3(f) factors when the
contractor had repudiated the contract); Alutiiq Mfg.
Contractors, LLC v. United States, 143 Fed. Cl. 689,
698 (2019) (termination for default was improper when
contracting officer only considered the first two FAR
49.402-3(f) factors).
The record reflects that the contracting officer
considered all seven factors. In a document titled
Request to Terminate for Default, signed by the
contracting officer on March 17, 2023, the contracting
60a
officer outlined and discussed each factor in detail.8
(ECF 25-1 at 62-63.) The evidence is sufficient to
demonstrate that the contracting officer considered the
factors required by the FAR, and the contracting
officers analysis of those factors does not reflect an
abuse of discretion. Indeed, given the correct reading
of the task order, even without the Navys analysis of
the FAR 49.403-3(f) factors, the termination for default
would not be an abuse of the Navys discretion because
ASG failed to perform the contract.
VI. CONCLUSION
The plaintiff is not entitled to judgment on the
8
At oral argument, the plaintiff objected to the admission
of this document, which was made part of the record only with the
defendants reply brief filed five days before the argument.
Because caselaw reflects that the plaintiff does not have an
affirmative right to receive an agencys analysis of each factor, the
time at which the plaintiff became aware of this document does
not affect the validity of the termination analysis. See DCX, Inc.,
79 F.3d at 135. The date of the contracting officers signature on
the request, March 17, 2023, reflects that the contracting officer
considered the relevant factors before NAVFAC SE made the
decision to terminate for default. The document is relied on for
that point only, and not for the substance of its analysis.
Regardless, a court retains discretion to consider untimely
submissions when there is no undue prejudice to the opposing
party. See Aventis Pharma S.A. v. Hospira, Inc., 675 F.3d 1324,
1333 (Fed. Cir. 2012) (finding that the district court did not abuse
its discretion in allowing a party to make late amendments to its
pleadings in part because the non-moving party was not unduly
prejudiced by the amendment). Considering the timing and
limited use of this document in resolving its claims, ASG has not
been unduly prejudiced by its introduction.
61a
pleadings or summary judgment. Although ASG has
presented a possible reading of the task order, the
defendants reading is the reasonable one. The
defendants reading of the task order does not convert
it into an illegal contract for personal services or an
improperly executed time and materials contract. ASG
was properly notified of the deficiencies in its
performance and received an opportunity to cure. It
did not cure, and the contracting officers decision to
terminate the task order for default complied with the
FAR and was not an abuse of discretion.
The plaintiffs motions for judgment on the
pleadings and summary judgment are denied. The
defendants motion for summary judgment is granted.
A separate order will be filed concurrently with this
opinion directing the Clerk to enter judgment.
s/ Richard A. Hertling
Richard A. Hertling
Judge
62a
APPENDIX C
ITNOTE: This order is nonprecedential.
UNITED STATES COURT OF APPEALS
FOR THE FEDERAL CIRCUIT
ASG SOLUTIONS CORP., DBA AMERICAN
SYSTEMS GROUP,
Plaintiff-Appellant
v.
UNITED STATES,
Defendant-Appellee
2024-1755
Appeal from the United States Court of Federal
Claims in No. 1:23-cv-01029-RAH, Judge Richard A.
Hertling.
ON PETITION FOR PANEL REHEARING AND
REHEARING EN BANC
Before MOORE, Chief Judge, LOURIE, BRYSON1,
DYK, PROST, REYNA, TARANTO, CHEN,
HUGHES, STOLL, CUNNINGHAM, and STARK,
1
Circuit Judge Bryson participated only in the decision
on the petition for panel rehearing.
63a
Circuit Judges.2
PER CURIAM.
ORDER
ASG Solutions Corp filed a combined petition for
panel rehearing and rehearing en banc. The petition
was first referred to the panel that heard the appeal,
and thereafter the petition was referred to the circuit
judges who are in regular active service.
Upon consideration thereof,
IT IS ORDERED THAT:
The petition for panel rehearing is denied.
The petition for rehearing en banc is denied.
March 3, 2026
Date
FOR THE COURT
Jarrett B. Perlow
Clerk of Court
2
Circuit Judge Newman did not participate.
64a
APPENDIX D
[DEPARTMENT OF THE NAVY LETTERHEAD]
4330
Ser CON24/23-046
4 April 2023
TRANSMITTED VIA EMAIL: rito@asgscorp.com
ACKNOWLEDGEMENT OF RECEIPT REQUIRED
Mr. Ritobrata Banerjee
ASG Solutions Corporation American Systems Group
3990 Old Town Ave, STE B107
San Diego, CA 92110-2967
Dear Mr. Banerjee:
SUBJECT:
NOTICE OF TERMINATION TO
PRIME CONTRACTOR FOR
CONTRACT N00178-19-D-7175, TASK
ORDER N6945022F3005, TECHNICAL
SUPPORT SERVICES FOR THE
ENGINEERING AND DESIGN
DIVISION FOR THE DESIGN AND
CONSTRUCTION BUSINESS LINE
This letter is to notify ASG Solutions Corporation
American Systems Group ("ASG") that effective
immediately, the subject task order is hereby
terminated in its entirety for default of the contractor.
As detailed in the Letter of Concern dated November
1, 2022, the Cure Notice dated December 5, 2022 and
65a
the Show Cause letter of January 20, 2023, ASG has
breached its contractual duty by failing to perform in
accordance with the terms and conditions of the
contract and has repeatedly reiterated its refusal to
comply with the contract or to provide any reasonable
assurance to the Navy that the performance will be
improved in time to meet mission requirements.
Background
The subject task order was awarded by Naval
Facilities Engineering Systems Command (NAVFAC)
Southeast to ASG on September 28, 2022, in the total
amount of $3,836,152.00 for the one-year base period.
The contract called for a self-sufficient and
self-supervised multidisciplinary support team
consisting of at least twenty (20) professionals to
provide professional support services in the form of
advisory and assistance services to NAVFAC
Southeast's Engineering and Design Division, Design
and Construction Business Line (DCBL). In
accordance with CLIN 1000, the services were
required to be performed on-site at Naval Air Station,
Jacksonville, Florida.
Task Order Section A.2 Service Requirements
specifies: "the staff of twenty (20) professionals is
base minimum level of service." In order to enforce this
requirement, Section H.8 - Schedule of Deductions states: "If at any time there is a vacancy within the
Contractor's team (i.e., all twenty (20) positions are not
filled) the Government will be entitled to immediate
replacement (within 5 days of loss of personnel), or to
a unit price reduction in payment, in accordance with
66a
FAR 52-246-4 until the qualified technical expert(s) is
in place. The daily unit price will [be] determined by
the Unit Price per Month proposed in the Optional
Levels of Service CLIN, as applicable." Further
underscoring the essentiality of this requirement,
Section G.6 - Submission and Substitutions of Key
Personnel - provides that: "The offeror shall certify
that as of the date of submission of the resume, the
qualified individual(s) has agreed to accept the
position upon acceptance by the Government, pending
any unforeseen circumstances."
ASG explicitly acknowledged its understanding of
these contractual requirements. On August 24, 2022,
ASG submitted its proposal, which contained
Attachment 4 Proposed Labor Mix, listing twenty
(20) highly qualified professionals from a variety of
technical disciplines. The proposed labor mix included
very specific qualifications over and above the
minimum requirements set forth in the solicitation, to
include Masters Degrees, Professional Licensing, and
extensive DoD experience.
The solicitation clearly states: "The non-price
proposal presented by the offeror to whom the award
is made will be incorporated into the task order at time
of award." This was so important that, prior to award
of the task order, on September 15, 2022, NAVFAC
Southeast issued a clarification notice to confirm
ASG's proposal. The clarification notice required ASG
to expressly acknowledge that ASG understood that
any personnel proposed after award would need to
meet the qualifications of the personnel that ASG
proposed in its Attachment 4. Specifically, the
67a
contracting officer asked: "Please confirm that you
understand the technical experts submitted after
award must meet the additional requirements
proposed that are contained within your non-price
proposal, Attachment 4. On the same date, ASG
provided written confirmation, acknowledging the
requirement, and affirming it with an unequivocal
"Yes."
Therefore, due to the highly skilled labor mix
proposed and confirmed by ASG, NAVFAC Southeast
selected ASG for award as the best value offeror.
ASG's Attachment 4 was incorporated in the task
order award in Section J as Attachment 2 Labor
Mix.
Contract Schedule
ASG's task order was awarded on 28 September
2022, with a completion date of September 27, 2023.
Section F.4 Deliverables - required the contractor to
submit "to the contracting officer" "within five days of
award of task order" a "resume for each position
proposed in accordance with the Contractor's proposal
and the PWS." Approximately halfway through the
one-year period of performance, ASG has provided only
five (5) of the twenty (20) professionals required by the
task order and that were expressly proposed and
confirmed by ASG in Attachment 4 of its proposal.
ASG has failed to provide the personnel to
perform the technical support services required by the
contract, which has had, and continues to have, an
adverse impact on NAVFAC Southeast's mission
68a
accomplishment. This has been explained to ASG on
several occasions, but ASG has failed and/or refused to
take sufficient corrective actions.
Contractor Performance Issues
From the beginning of the contract, ASG's
performance has never been satisfactory. The task
order required the contractor to submit resumes of
qualified candidates within five (5) days of contract
award to the Contracting Officer for review and
approval as stated in Section F.4 Deliverables of the
Task Order.
In the first twelve (12) days of the period of
performance, ASG submitted five (5) resumes to the
Contracting Officer's Representative (COR), but of
those five resumes two failed to meet the
requirements, and a third individual has not
completed his security forms to date. On October 17,
2022, at the kickoff meeting, ASG began to assert that
it would not comply with certain requirements of the
task order. According to ASG, due to the
performance-based elements within the performance
work statement (PWS), ASG could unilaterally decide
whether or not to comply with the personnel
requirements of the task order and with the personnel
qualifications that ASG proposed in its proposal
Attachment 4 incorporated into the task order as
Attachment 2.
To date, approximately six months into the base
period of performance, ASG has provided only five (5)
of the twenty (20) professionals that are required by
69a
the task order and that were expressly proposed and
confirmed by ASG in Attachment 4 of its proposal.
Throughout the entire six months, ASG has provided
a total of eighteen (18) resumes to the contracting
officer. NAVFAC Southeast rejected six (6) of the
resumes because they did not meet the proposed
qualifications listed in ASG's Attachment 4; and
approved twelve (12) candidates, five (5) of which did
not accept employment with ASG, the other seven (7)
accepted employment with ASG. One of the approved
candidates terminated employment with ASG nine (9)
days after approval. Another approved candidate has
yet to complete the security process. An additional
candidate was recently approved in early March 2023.
In summary, approximately halfway through the
one-year period of performance, ASG has provided only
twenty-five percent (25%) of the number of qualified
professionals required by the task order and as
expressly proposed and confirmed by ASG in
Attachment 4 of its proposal. Out of these five (5)
professionals, only four (4) have performed
professional support services under the task order to
date.
ASG insists that it is bound neither by the terms
of the task order nor by the terms of its proposal
incorporated into the contract. ASG insists that it can
unilaterally interpret the task order PWS according to
its own unilateral convenience. Moreover, ASG claims
entitlement to full compensation under the task order.
ASG submits and certifies monthly invoices in the full
amount of $281,870.00 each, regardless of the
positions filled or services rendered.
70a
On 1 November 2022, NAVFAC Southeast issued
a Letter of Concern explaining that ASG was failing to
meet the task order requirements. In response to the
Letter of Concern, ASG took the position that even
though it proposed and confirmed twenty (20) qualified
personnel sought by the Government, it is not bound
to providing the number, the qualifications, or the onsite services that it proposed.
On December 5, 2022, NAVFAC SE issued a Cure
Notice, informing ASG that the Government
considered ASG' s repudiation of its proposal,
specifically its Attachment 4, a condition that was
endangering performance of the task order and that
could result in a termination for default. ASG
responded to the Cure Notice on December 14, 2022.
According to ASG, the labor mix required by the task
order and proposed by ASG is irrelevant, and only
ASG's self-serving interpretation of select portions of
the performance work statement are controlling. ASG
has continuously argued that it is not required to
provide twenty (20) professionals that meet the
qualifications of its proposal. According to ASG, it is
allowed to provide whatever staffing it deems
appropriate, working from whatever location, and with
whatever qualifications, regardless of the terms and
conditions of the task order and ASG's proposal.
Additionally, ASG accuses NAVFC Southeast of
wanting to enforce a prohibited personal services
contract, ignoring the fact that management,
supervision, and oversight of personnel remained at all
times within the control of ASG (not NAVFAC
Southeast). In fact, Section 8 of the task order, entitled
71a
Non-Personal Service Statement, provides: "Contractor
employees will perform independent of and without
the supervision of any Government official."
On January 5, 2023, at a meeting with NAVFAC
SE's Contracting Officer's Representative (COR), ASG
stated that it "cannot meet Attachment 4," citing labor
market conditions. On one hand, ASG admits that it
has defaulted under the contract, blaming labor
market conditions. On the other hand, ASG argues
that it is not bound by the contract, and that it can
unilaterally interpret and administer select portions of
the contract to its advantage and profit. NAVFAC
Southeast believes that ASG either knew or should
have known the state of the labor market prior to
making its proposal. NAVFAC Southeast believes that
ASG submitted a potentially false or fraudulent
proposal that ASG either knew or should have known
that it could not achieve. NAVFAC Southeast believes
that ASG's invoices requesting full payment for less
than full services may constitute a potential false
claim against the government.
Termination
On January 20, 2023, NAVFAC Southeast issued
a Show Cause Notice, which notified ASG that the
Government was considering termination of the
contract for default. The Show Cause Notice provided
an opportunity for ASG to submit a response detailing
any facts bearing on the reason ASG has failed to
perform in accordance with the contract with regard
to: (1) failure to comply with its proposal, specifically
Attachment 4, which expressly proposed a multi72a
disciplinary mix of twenty (20) qualified personnel
meeting specific qualifications and credentials; and (2)
ASG's anticipatory repudiation of the contract
performance by informing the COR that ASG "cannot
meet Attachment 4."
On January 22, 2023, ASG requested a time
extension to respond, and an opportunity to meet in
person with NAVFAC Southeast personnel. On
January 31, 2023, NAVFAC Southeast issued an
extension notice that also included confirmation of the
in-person meeting to be held on February 1, 2023 that
had previously been scheduled. On February 1, 2023,
NAVFAC Southeast representatives met with ASG
representatives. ASG reasserted its position that
NAVFAC Southeast should not enforce the terms of
the contract that ASG cannot meet. According to ASG,
it should be allowed to perform DCBL support tasks
with less personnel (four or five) working primarily
remotely (online rather than on-site). In sum, ASG
essentially requested a total reformation or
modification of the task order. NAVFAC Southeast
cannot grant ASG's request. For one, allowing ASG to
potentially exercise a bait and switch scheme of this
magnitude may constitute fraud. Moreover, the
mission needs of DCBL for this particular task order
called for a multidisciplinary and qualified team of at
least twenty (20) professionals providing on-site
support to DCBL operations. ASG's failure to provide
the required team, hindered DCBL's ability to assign
meaningful support tasks under the contract. ASG has
asserted that without receiving meaningful tasks it
cannot hire a qualified team. However, the task order
required providing the qualified team first to be able to
73a
receive tasks based on the composition and capabilities
of the support staff team. In a meeting on February 1,
2023, the ASG was asked if it would consider a
reduction in quantity of required personnel for a
reduction in total price. ASG did not propose any sort
of reduction in their response dated February 10, 2023
to the Show Cause notice. Rather, ASG has insisted on
full pay for its minimal or non-existent performance.
On February 10, 2023, ASG responded to the
Show Cause Notice. ASG did not fully address the
failures identified in the Show Cause Notice. ASG did
not accept any responsibility. ASG did not provide any
acceptable recovery plan. Rather, ASG reiterated its
stance that: (i) ASG is not required to have a minimum
number of 20 professionals; (ii) ASG is entitled to staff
the contract with any individuals of ASG's choosing
without regard to the qualifications; (iii) the
contractual requirement for the professionals to work
on-site at Naval Air Station Jacksonville is impossible
to meet, and ASG employees should be able to work
remotely from anywhere; and (iv) ASG is entitled to
full payment under the contract regardless of level of
performance.
Decision
After due consideration of all of the information
above, I fmd and determine that ASG is in default,
without any valid excuse. ASG is hereby notified that
the Government, by this written notice, terminates
Contract N00178-19-D-7175, Task Order
N6945022F3005 including ASG's right to proceed with
performance, in its entirety and for default in
74a
accordance with FAR 52.249-8 Default (Fixed-Price
Supply & Service) (April 1984). This termination for
default shall be effective upon ASG's receipt of this
notice. ASG shall cease work under this task order
immediately. No further work shall be assigned to
ASG. Any current work assigned to ASG shall cease
immediately. ASG personnel shall return any
Government Furnished Equipment, to include but not
limited to, Government Furnished Laptops, Common
Access Cards, and any other computer related
equipment as scheduled with the Contracting Officers
Representative (COR) on-site in building 903 on board
Naval Air Station Jacksonville, on 5 April 2023.
The Government reserves its right to re-procure
the contract. ASG may be found liable for applicable
re-procurement costs under the Termination for
Default clause cited above. The Government reserves
the rights and remedies provided by law and under the
contract.
This notice of termination for default constitutes
the Final Decision of the Contracting Officer. ASG has
the right to appeal this final decision pursuant to the
Disputes Clause, FAR 52.233-1 (May 2014), of the
contract. This decision may be appealed to the Armed
Services Board of Contract Appeals, which is the
authorized representative of the Secretary for hearing
and determining contract disputes. If you decide to
appeal this decision, written notice thereof must be
mailed or otherwise furnished to the Armed Services
Board of Contract Appeals, Skyline Six, 5109 Leesburg
Pike, 7th Floor, Falls Church, VA 22041, within 90 days
from the date you receive this decision. A copy shall
75a
also be furnished to the Contracting Officer from
whose decision the appeal is taken at the following
address:
Naval Facilities Engineering Systems Command
Southeast
Attn: Renee Comfort, Chief of Contracting Office
Naval Air Station Jacksonville
P.O. Box 30A BLDG 903 Contracting SL
Jacksonville, FL 32212-0030
The notice should indicate that an appeal is
intended, should reference this decision, identify the
contract by number, and state the amount in dispute.
The rules of procedures of the Armed Services Board
of Contract Appeals are in the Department of Defense
Federal Acquisition Regulation Supplement, Appendix
A, Part Two. Optional Accelerated Procedures are
available in appeals involving $100,000 or less and
Small Claims (expedited) procedures are available in
appeals involving $50,000 or less or, in the case of a
small business concern (as defined in the Small
Business Act and regulations under that Act),
$150,000 or less. In lieu of appealing to the Board of
Contract Appeals, you may bring action directly in the
Court of Federal Claims* within 12 months of the date
you receive this decision (*except as provided in
Section 4 of the Contract Disputes Act (Maritime
Contracts)).
Sincerely,
COMFORT.RENE
E.M.1082580375
76a
Digitally signed by COMFORT.RENEE.
M.1082580375
Date: 2023.04.04 11:59:05 -04'00'
RENEE M. COMFORT
Chief of Contracting Office
Terminating Contracting Officer
Copy to:
Administrating Contracting Office
Contracting Officers Representative
Planning Design and Construction Division
NAVFAC SE, Office of Small Business
Small Business Association Regional Office
77a
Acknowledgment of Notice
The undersigned acknowledges receipt of a signed copy
of this notice on ________, 2023. Two signed copies of
this notice are returned.
ASG Solutions Corporation DBA American Systems
Group
By _______________________ (Name)
___________________________(Title)
(End of notice)
78a
APPENDIX E
Request to Terminate for Default
From:
To:
Via:
Cory Iselin, Supervisory Contract Specialist,
NAVFAC Southeast (SE)
Renee Comfort, Chief of Contracts, NAVFAC
SE
Rebecca Jones, FSC Division Director,
NAVFAC SE
Subj:
RECOMMENDATION TO TERMINATE
FOR DEFAULT CONTRACT NUMBER
N 69 4 50 - 1 9- D -7 1 75 T AS K O RD ER
N6945022F3005 ENTITLED DESIGN AND
CONSTRUCTION BUSINESS LINE
(DCBL) TECHNICAL SUPPORT SERVICES
Ref:
(a) FAR Part 49
(b) DFAR Part 49
(c) NPGI 49.4
Encl:
(1) N69450-19-D-7175 -N6945022F3005
ASG Systems Corporation DBA American
Systems Group (ASG) Proposal
(2) Letter of Concern dated 11/1/22
Evidence of Receipt to Letter of Concern
dated 11/1/22
ASG Response to Letter of Concern dated
12/14/22
Cure Notice dated 12/5/22
79a
Evidence of Receipt to Cure Notice dated
12/5/22
ASG response to Cure Notice dated 12/14/22
Government response to ASG response
dated 12/22/22
Show Cause dated 1/20/23
Evidence of Receipt to Show Cause dated
1/22/23
ASG response to Show Cause dated 2/10/23
(3) Government Estimate (time and money)
to complete
1. In accordance with references (a) (c), it is
recommended that the subject contract be terminated
for default. Enclosures (l) (2) provide the supporting
background information necessary to assist in making
this determination.
2. Background Information:
a.
Contract
number
and title:
N69450-19-D-7175-N6945022F3005 Design
and Construction Business Line (DCBL)
technical support services
b.
Date of Award: 9/28/2022
c.
Value of contract at time of award:
$3,836,152.00 (Funded At Time of Award) &
$17,381,838 (Total potential value)
d.
Original contract completion date: 9/29/2023
80a
(End of Base Period)
e.
Contractors name and address:
ASG Systems Corporation DBA American
Systems Group (ASG)
3990 Old Town Ave, Suite B-107
San Diego, CA, 92110
f.
Suretys name and address: NA
g.
Modifications: No modifications
h.
Amount paid to date: $0
i.
Balance of funds remaining: $3,836,152.00
j.
Contractors unpaid earnings for work
through date of this document $1,409,350.
The contractor may be entitled to
approximately $207,615.81 for personnel
proposed and approved during the first five
months of the task order.
k.
Assignee (if applicable): NA
l.
Trustee in bankruptcy (if applicable): NA
m.
Inventory (List all work in place): NA
n.
Percentage of completion (Describe the areas
and extent of work performed):
Approximately 8%. Time wise, 42% (5
months divided by 12 months of the base
81a
period) has elapsed. Performance wise, 20%
(4 qualified professionals out of a minimum
of 20 required for a compliant
multidisciplinary team) has been provided.
Since 20% of 42% is 8.4%, it can be said that
completion percentage is 8% at this time.
In terms of assigned projects, NAVFAC SE
assigned to ASG the following DCBL
professional support projects:
- Whiting Field P286 65% Review
Completed
- Kessler New Cyber Processing Facility
65% Review Completed
- Kingsville B4766 Replace HVAC Pre-Final
Review Completed
- Indoor SAUSR Range,
Pre-Final Review In process
Charleston
- Mayport Triton Maintenance Trainer Final
Review In process
o.
List any corrective action required: The
contract called for a base minimum of 20
qualified professionals, with resumes to be
provided to the Contracting Officer within 5
business days of award. To date the
contractor has provided a total of 17 resumes
to the contracting officer. NAVFAC SE
rejected six (6) resumes because the
82a
personnel did not meet the professional
qualifications proposed by ASG. NAVFAC
SE approved eleven (11) personnel that met
the qualifications proposed by ASG.
However, ASG has retained only four (4)
employees on board. The remaining seven (7)
are not on board for the reasons listed below.
1.
Approved Architect Once approved,
the candidate did not accept the job
from ASG.
2.
Approved Electrical Engineer This
candidate was approved on 18 Oct
2022. ASG and the employee have not
completed the Security documentation
and the candidate has had two
Eletronic Questionnaires for
Investigations Processing (EQIPs)
expire.
3.
Approved Civil Engineer NAVFAC SE
approved this candidate on 21 Nov
2022. The candidate resigned on 8 Dec
2022 prior to completing the security
review process.
4.
Approved Structural Engineer
NAVFAC SE approved this candidate,
the candidate did not accept the job
from ASG because the candidates wife
did not meet the qualifications for
structural engineer and was not
approved for the task order.
83a
5.
First Approved Supervisor NAVFAC
SE approved the first supervisor on 17
Oct 2022. A few days later, the
supervisor notified NAVFAC SE that
they (the supervisor) had terminated
their employment with ASG effective
on 26 Oct 2022. The first supervisor did
not finish the security review process.
6.
Second
Approved
Supervisor
NAVFAC SE approved the second
proposed supervisor, but this
supervisor did not accept the job offer
made by ASG.
7.
Third Approved Supervisor NAVFAC
SE approved the third proposed
supervisor, ASG was unable to hire or
employ the individual.
p.
List of paid materials and supplies at site:
NA
q.
List of unpaid materials and supplies at site:
NA
r.
Pending change orders, percentage of
completion of the changed work, status and
recommended disposition of pending change
orders: NA
s.
Whether termination will result in a
reduction in employment of 100 of more
contractor employees: No
84a
t.
Any other applicable data/information:
i.
u.
1.
Invoices Five monthly invoices were
submitted in the amount of $281,870.00
each, for a total of $1,409,350.00. The
first two invoices have been rejected
because the vendor did not have
billable employees in place, and did not
provide the timesheets required to
verify the costs being billed. The three
remaining invoices are pending a
determination on how they may be
partially processed, if at all, without
timesheets because the contractor
refuses to submit timesheets.
Point of contact if additional information is
necessary: Cory Iselin, cory.s.iselin.civ@
us.navy.mil
DISCUSSION
Chronology of events:
a.
On 29 July 2022, NAVFAC SE issued
Solicitation N6945022R3005. The scope of
work consisted of providing a
multidisciplinary professional support staff
with the minimum personal allocation: four
(4) architects, four (4) mechanical engineers,
four (4) electrical engineers, two (2) civil
engineers, two (2) structural engineers, one
(1) fire protection engineer, one (1) cost
engineer, and two (2) Supervisors. This could
85a
b.
c.
change based upon the successful offerors
proposed technical approach. A staff of
twenty (20) professionals was the
base/minimum level of service. See
additional scope information in Encl. 1 at
page 9.
On 24 August 2022, ASG submitted a
proposal offering an impressive labor mix of
20 highly qualified professionals. Each
technical professional was listed as Senior,
having a minimm of 12 years to 35+ years of
experience, decades of DoD experience, a
degree from a specifically named
college/university (18 of the 20 listed
Masters degrees), and a relevant
professional certificate and/or license. On 15
September 2022, NAVFAC SE issued a
clarification notice to confirm ASGs offer.
The clarification notice required ASG to
expressly acknowledge that ASG understood
that the personnel proposed after award
would need to meet the qualifications of the
personnel proposed in Attachment 4 of
ASGs proposal. On the same date (15
September 2022), ASG confirmed in the
affirmative that ASG would be held to the
standards as proposed in ASGs proposal
Attachment 4.
On 28 September 2022, NAVFAC SE
selected ASG for award as the best value
offeror due to the highly skilled labor mix of
20 highly qualified professionals proposed
and confirmed by ASG in Attachment 4 of its
86a
proposal. ASGs Attachment 4 was
incorporated in the task order award as
Attachment 2. Consequently, NAVFAC SE
incorporated ASGs proposed labor mix into
the task order award in Section J as
Attachment 2 Labor Mix.
d.
On 18 October 2022, ASG began to assert
that it could unilaterally decide whether to
comply or not with the qualifications
proposed in Attachment 4 of its proposal.
Additionally, ASG began disputing the task
order requirements of providing a staff of
twenty (20) professionals as the
base/minimum level of service, and to do so
by providing resumes of qualified candidates
within 5 days of contract award to the
Contracting Officer for review and approval
by the Government (so the Government
could verify that proposed employees met
ASGs proposed minimum qualifications).
e.
On 1 November 2022, NAVFAC SE issued a
Letter of Concern explaining that ASG was
failing to meet the task order requirements.
ASG did not change its stance. On 5
December 2022, NAVFAC SE issued a Cure
Notice, informing ASG that the Government
considered ASGs repudiation of its proposal,
specifically its proposal Attachment 4
Labor Mix, which was incorporated into the
task order at the time of award, a condition
that was endangering performance of the
task order and that could result in a
87a
termination for default. The task orders
period of performance had started on 30
September 22, however, as of the date of
Cure Notice, ASG had submitted only 18
resumes, out of which only twelve (12) met
the qualifications ASG proposed, and only
six (6) accepted employment with ASG, with
one (1) terminating their employment nine
(9) days after approval, and one (1)
additional employee (to the date of this
request) has yet to finish the security
process. In summary, at approximately
halfway through the one-year period of
performance, ASG has provided only five (5)
(one was just accepted in early March and
has yet to finish security process) of the
twenty professionals by the contract.
f.
On 05 January 2023 Mr. Ritobrata Banerjee
(owner of ASG) visited NAVFAC SE for a
meeting with Mr. Douglas Szilagyi,
Contracting Officers Representative (COR).
During that meeting, Mr. Banerjee stated
that he cannot meet Attachment 4.
g.
On 20 January 2023, NAVFAC SE issued a
Show Cause Notice asking ASG to Show
Cause why the task order should not be
terminated for default. The Show Cause
Notice informed ASG that it had failed to
cure t he condit ions endangering
performance. Specifically, ASG had failed to
comply with Attachment 4 of its proposal,
which expressly proposed personnel meeting
88a
specific qualifications and credentials. On 22
January 2023, Mr. Banerjee requested an
in-person meeting to discuss the Show Cause
Notice. On 1 Feb 2023, ASG representatives
Mr. Banerjee and Mr. Marcy met with
NAVFAC SE representatives Ms. Renee
Comfort (Chief of Contracts), Mr. Cory Iselin
(Contracting Officer), Ms. Rebecca Jones
(Public Works Contracts Division Director),
Mr. Doug Szilagyi (Contracting Officers
Representative), and Mr. John Bazylewicz
(Assistant Deputy Director for Small
Business). During the meeting the intent
and terms of the contract were discussed.
Mr. Banerjee continued to assert that his
belief was that the Government was wrong
and that the Government should allow him
to staff the contract with whomever he
deemed necessary. He stated that should he
be required to respond to the Show Cause
Notice that he would propose a 2% reduction
in price in order for the ability to provide
whomever he deemed qualified for the
contract, whether they met the terms of his
proposal or not. Mr. Banerjee continued to
assert that his proposal was simply just that,
a proposal and that he did not need to
adhere to or provide what he proposed. The
Government continually pointed back to the
contract language stating the base/minimum
level of service and remind Mr. Banerjee
that he responded during clarifications that
he was aware that he would be held to his
proposal. At the conclusion of the meeting,
89a
Ms. Comfort informed Mr. Banerjee that
ASG was still required to submit a formal
response to the Show Cause Notice.
h.
On 10 February 2023, ASG responded to the
Show Cause Notice. In Summary, ASG
continued to categorically deny the
Governments assertions made in the Show
Cause and all prior notices. ASG essentially
contended that it was not obligated to adhere
to the Governments requirements or its
proposals, but only to ASGs unilateral
interpretation of certain portions of the task
order. ASG continued to claim that the
Government is operating this contract as a
Personal Services contract and that the
Government is ignoring contract language
and the needs and mission of the
Government. ASG stated that the
Government has shown zero regard for the
impracticability and absurdity of staffing 20
elite professionals to show up in Jacksonville
and do nothing. ASG closed its response by
stating that the Government has presented
ASG with two equally untenable options:
1) conspire with the Government and its
agents to unlawfully treat this contract as a
personal services contract and perform the
extra-contractual task, which to date is
impossible based on market conditions, of
delivering 20 professionals of the
Governments choosing with no work to be
done... or 2) Face the full wrath of the
90a
Governments unlimited legal budge in bet
the company litigation at the Court of
Federal Claims, which all the costs and
waste associated with the endeavor. ASG
requested that the Government avoid
litigation by ceasing baseless attacks,
paying ASG (full price), and consider
Alternative Dispute Resolution. The
government team discussed and considered
the request for ADR as suggested by ASG,
and by Mr. John Bazylewicz (NAVFAC
Assistant Deputy Director for Small
Business), however the team believed that
the entirety of this situation does not lend
itself to reaching a successful ADR
agreement, and as such the Government
determined ADR not to be the best path
forward.
Past and present performance of the
contractor, including deficiencies and
difficulties together with a statement of
any efforts made to improve
performance:
The contractor has refused to perform in
accordance with this task order since it start
date of 30 September 2022. ASG has not
been able to meet its proposal as outlined in
Attachment 4 Labor Mix. ASG has been
unable to provide twenty (20) professionals
as the base/minimum level service
requirement. ASG is very combative and
argumentative, insisting in its own
91a
interpretation of the contract and completely
disregarding the fact that it expressly
proposed a specific labor mix of 20 qualified
professionals to work at NAVFAC SE in
Jacksonville, FL. NAVFAC SE requires a
multidisciplinary team composed of specific
specialties to deliver on-site professional
support services for the Design and
Construction Business Line. ASG insists
that provided that it can perform DCBL
work remotely and with personnel of any
number and qualification of its choosing, it
would meet the performance requirements of
the contract. ASG insists on a partial and
selective contract interpretation that would
render meaningless the requirement to
provide a specific labor mix for a
multidisciplinary team providing seamless
on-site professional support services to
DCBL in Jacksonville, Florida. ASG only
wants to read the contract sections that
support its particular interpretation of the
contract, negating other sections of the
contract, and negating its proposal. ASG also
demands to be paid in full for the contract
even if its performance is partial and only
meeting specific sections or portions of the
task order rather than the task order as a
whole. ASGs position is that it should be
paid the full amount of $281,870.00 per
month regardless of their level of effort. In
support of this argument, ASG points to the
fact that the CLIN is firm-fixed price.
However, the deductions clause of the
92a
contract clearly sets forth the mechanism by
which the firm-fixed price may be reduced if
the contractor fails to keep a minimum staff
of 20 professionals. Almost halfway through
the performance period, ASG has never
achieved this requirement.
ASG has made minimal efforts to
correct/improve their performance. They
have continued to occasionally submit new
resumes; since Show Cause was issued, they
have submitted an additional resume, for an
individual whom the government approved
and whom has yet to finish his security
processing. The Government has done its
best to work with ASG in reviewing resumes
on time (providing feedback in less than 48
hours in every case since the Kickoff
meeting, even though this is not a
requirement of the contract). They have
provided detailed notes on resumes when
individuals have not been approved to help
better direct ASG towards acceptable
candidates that meet the ASG proposed
specifications for their team members.
Present factual position, contentions,
representations, or promised
performance by the contractor (Review
contractors response to Cure
Notice/Show Cause letter and answer
each allegation).
ASG response to Letter of Concern: ASGs
93a
response contained embellishments and
conflations of opposing issues/topics/laws/etc.
making the response difficult to understand.
Overall, ASG argues that the Government is
misinterpreting the task order whereas ASG
is allegedly interpreting it correctly.
According to ASG, even though it proposed
the 20 qualified personnel sought by the
Government, it is not bound to provide the
proposed team. The Government disagrees.
The intent of the task order was clearly to
obtain the onsite professional support of a
multidisciplinary team composed of at least
20 qualified personnel. It is evident that
ASG understood the Government
requirement exactly as required in the
Solicitation. The evidence is that ASG
proposed the 20 qualified personnel required
by the Government in the Solicitation.
Moreover, ASG confirmed in writing that it
could and would provide the required
personnel that it proposed. The statement of
work is clear that notwithstanding the
performance-based nature of the work, the
performance is to be rendered on-site by a
professional staff of at least 20 professionals
physically located at NAVFAC SE in
provided administrative office spaces. The
task order even specifies that if there is a
vacancy in the 20 professionals, ASG would
have to replace the vacancy within 5 days of
loss of personnel.
ASG asserts that Section A.2 provides no
94a
support for the Governments position. The
Government disagrees. Section A-2 provides
the Services Requirements for the task
order, specifying the multidisciplinary team
of at least 20 professionals as the
base/minimum level of professional support
service consistent with FAR 37.101. ASG
argued that the Government was trying to
change the contract into a cost reimbursable
time and materials (T&M) personal services
contract. The Government disagrees. Section
H.8 clearly advises ASG that vacancies
below the minimum of 20 personnel would
need to be filled, or that price deductions
would be applicable. ASG asserts that
Section F.4 provides no support for the
Governments position. ASG states that the
Government does not have a right to review
resumes to ensure potential employees meet
the requirement proposed by ASG in its
Attachment 4 (labor mix). The Government
disagrees. It is implicit in the Governments
right and discretion to properly administer
the contract to review resumes and approve
personnel to be on board a military
installation providing professional support
services in accordance with FAR Part 37. It
is reasonable to review resumes and
personnel on board for many reasons,
including contract administration, oversight,
and avoidance of an improper or fraudulent
bait and switch against the Government
and as a waste of public funding. ASGs
response to the Cure Notice set forth a
95a
narrative of their efforts to hire individuals
to perform the services (albeit not meeting
the specifications of their proposal).
However, ASG states that it is impossible.
Additionally, ASGs position is that it has
performed all work that it has been given,
has delivered ahead of schedule, stating,
The Government has not requested any
task order that ASG has not performed.
Moreover, ASG believes that it deserves a
CPARS of Very Good/Exceptional. The
Government disagrees. While it is true that
ASG has submitted the work assigned, the
Government has been unable to assign the
complexity of the projects intended for this
contract, and only been able to assign small
review based projects that require minimal
staff due to the lack of a complete team, and
scarcity of ASGs approved staffing.
NAVFAC has assigned ASG small
professional support projects that ASG could
handle with the staffing level on hand. As
stated previously, the task order was
envisioned to have a robust professional
support to DCBL by a fully staffed
multidisciplinary team of highly qualified
professionals. Lacking the full staff has
hindered the ability to meet the customers
mission as was intended by issuance of this
contract.
ASG response to Cure Notice:
As
before,
ASGs
96a
response
contained
embellishments and conflations of opposing
issues/topics/laws/etc. that made the
response difficult to understand and follow.
In addition to the same arguments raised
before, ASG asserted that it cannot endanger
performance of a task order where there is
no work to perform. The Government
disagrees. ASG pretends to interpret the
task order in a self-serving manner where
only the requirements that ASG likes or can
meet are valid while all other requirements
can be ignored, disregarded, and waived at
Governments expense.
ASG decided to interpret the task order as
only requiring performance regardless of the
composition, location, and qualification of
the team. According to ASG, provided that it
can perform with any personnel it wants and
from wherever it wants, it is complying with
the contract. In other words, ASG wants to
invalidate the contractual requirement for a
multidisciplinary team of a minimum
composition providing onsite professional
support to DCBL at NAVFAC SE in
Jacksonville, Florida. That is neither what
the Government procured nor what ASG
offered. Somehow, however, ASG wants to
unilaterally reform and change the contract
to its own selfserving interests without
consideration and at Governments and
taxpayers expense. The task order sought a
multidisciplinary team for onsite
professional support. ASG understood the
97a
requirement, and expressly proposed to meet
it. After contract award, and after displacing
competitors with a potentially false proposal,
ASG pretends to change the contract to its
sole and self-serving advantage. This is
borderline fraud and false claim conduct that
cannot be reasonably accepted or condoned.
The task order calls for the vendor to provide
a staff of twenty (20) professionals who
would provide professional support on-site at
NAVFAC SE. However, since ASG failed to
provide the required staff, the task order
never took off as planned. Rather the
Government received no services for the first
three (3) months of the period of
performance until ASG provided its first
qualified, approved and cleared through
security employees on 3 January 2023. At
such time, the Government began to assign
tasks to ASG. The Government attempted to
help prevent no performance by assigning
smaller review type work that could be
completed by the disciplines of the three (3)
approved employees now on board, rather
than assigning work that required a fully
multi-disciplinary team.
Once again, ASG asserted that its proposed
labor mix spreadsheet is not a contract
obligation. The Government disagrees. The
staff was confirmed before award, and ASGs
offer was accepted and incorporated into the
task order. ASG made reference to
Non-personal Services Contract Provisions.
98a
It is difficult to understand the actual
argument being made, but to the extent that
it implies that the task order is an
impermissible personal services contract, the
Government disagrees. The task order
requires a multidisciplinary team to provide
professional support services on-site under
the supervision and management of ASG
(not the Government).
ASG asserted that the Government has a
duty to exercise discretion in connection with
a termination for default. The Government
agrees and has given ASG plenty of
opportunities to honor its proposal and
position its company to perform. However,
ASG insists on its legal arguments to negate
portions of the task order and accuse the
Government of breach.
ASG states that the Cure Notice which may
lead to a termination is not justifiable. This
is incorrect, ASG has been unresponsive to
the Governments requests to provide the
services required in the task order. As such,
one remedy available to the Government is
to issue a Cure Notice to the contractor so it
may cure the deficient performance.
ASG asserted that its performance was
satisfactory and that it would continue with
its action plan based on its own
interpretation of the requirements. The
Government disagrees. ASG has continually,
99a
since the first meeting after award of this
task order (Kickoff 17 October 2022),
disagreed with the Government on the
requirements of the task order and has been
combative in asserting that the Government
is wrong and does not understand the
contract. As such, ASG refused to
acknowledge the requirement to provide the
twenty (20) professionals for the base period.
ASG response to Show Cause Notice:
As before, ASGs response contained
embellishments and conflations of opposing
issues/topics/laws/etc. that made the
response difficult to understand. ASGs
response contained condescending language,
and accused the Government of bullying
ASG. ASG reiterated that its interpretation
of the task order is correct.
ASG stated that, .... market conditions
outside the control of ASG have made it
impossible as of the date of this letter for
ASG to recruit 20 full time professionals of
the Governments choosing to show up in
Jacksonville to do nothing, which is
apparently what the Government believes
ASG is required to do per this contract. ASG
implicitly acknowledged that it has tried to
recruit the 20 qualified personnel offered,
but has failed to do so due to market
conditions. The market conditions are
complicated, but not drastically different
100a
today than five or six months ago when ASG
submitted its proposal and confirmed its
offer of 20 qualified personnel. Whether ASG
was negligent, fraudulent, or both in
preparation of its proposal is yet to be
discovered. Regardless, it seems that ASG
acknowledges the duty to provide 20
qualified professionals to perform the
required services on site at Jacksonville,
Florida. That is, ASG finally acknowledged
that the task order calls for 20 professionals
to work at NAVFAC SE (Jacksonville), but
ASG cannot satisfy the requirement due to
market conditions.
ASG accuses the Government of trying to
run this contract as a Personal Services
Contract under FAR 37.104. The
Government disagrees. As stated above, the
professionals would be on-site providing
professional support, but would be managed
and supervised at all times by ASG (not by
the Government). That is precisely why the
multidisciplinary team must include
qualified supervisors employed by ASG.
Requiring ASG to submit potential employee
resumes for review (as required by the task
order), so the Government can verify they
meet ASGs proposed qualifications does not
make this a Personal Services contract. That
is simply reasonable and proper government
contract administration and oversight, it is
not management or supervision of employee
performance. Finally, requiring ASG to
101a
submit timesheets for employees (required
per the task order), so the Government can
verify ASG is submitting accurate invoices to
the Government for payment does not make
this a Personal Services contract. This is a
reasonable contract administration and
oversight process to ensure adequate
disposition of Government funds.
ASG argued that if the Government holds
ASG to the task order terms, the
Government is trying to treat the contract
like a Personal Services contract. The
Government disagrees. Again, while the
Government is providing overall contract
administration and oversight, the actual
supervision and management of contractor
employees would be performed by ASG (not
the Government). Holding a contractor to
contract terms and conditions does not make
a contract a Personal Services contract. At
one point in their response, ASG stated that
the task order does not require a staff 20
professionals at NAVFAC SE that ASG
proposed, but if it did it would be impractical
and absurd. ASG stated that 20
professionals at NAVFAC SE would be doing
nothing, just sitting there. Also, AGS stated
that 20 professionals who meet ASGs
proposed qualifications cannot be
manufactured, because ...who will be
actually willing to work at NAVFAC SE
Facility in this post-pandemic world... The
Government disagrees. This is precisely
102a
what AG proposed. The fact that ASG has
failed to perform to its proposal does not
make the task order requirements
unenforceable or reflect negatively on
NAVFAC in any way. On the other hand,
allowing ASG to negligently or fraudulently
run a bait and switch would reflect
negatively on NAVFAC SE and the
Government.
ASG also argued that Section C, the
Performance Work Statement, takes
precedence over its proposed labor mix. The
Government disagrees. The proposed labor
mix incorporated into the task order takes
precedence over Section C. FAR 52.215-8
Order of Precedence-Uniform Contract
Format clearly states that attachments have
precedence over the specifications. ASG goes
on to continually state or admit that it
cannot meet its proposed labor mix
requirements due to market conditions, but
at the same time maintains that it does not
need to meet its proposed labor mix
requirements. Unfortunately, these excuses
and contradictory statements do not shield
ASG from liability and responsibility to
comply with the terms and conditions of the
task order. All terms and conditions were
part of the Solicitation under which ASG
prepared its competitive proposal. ASG had
the opportunity to ask any questions
pertaining to these terms and conditions
during the pre-proposal phase of this
103a
procurement. ASG did not submit any
questions, Instead, ASG proposed and
confirmed what now appears to be a
negligent, and potentially false or fraudulent
proposal.
a.
Position of the Surety concerning the
proposed default action and whether it
has expressed an interest in completing
the contracting by a contractor of its
choosing or by Takeover Agreement: NA
b.
Additional contract time extensions
claimed or likely to be claimed: NA
c.
Pending claims
(date of claim,
description, amount (money and time),
date of certification, status,
recommended disposition):
ASG
submitted a claim on 9 January 2023 for two
invoices that were rejected because the
vendor did not provide timecards of
employees so the Government could verify
the hours being billed. The vendor was asked
to provide time sheets so the Government
could verify the invoice amounts, the vendor
refused to so, but instead filled a claim:
(1)
Invoiced Amount - $281,870.00 - Invoice
Number - N6945022F30051022 - Period
of Performance 09/30/2022
10/29/2022 - Month of October 2022
Invoice; and
104a
(2)
Invoiced Amount - $281,870.00 - Invoice
Number - N6945022F30051122 - Period
of Performance 10/30/2022
11/29/2022 - Month of November 2022
Invoice.
The claim has been sent to the claims
department for processing. During the first
two months of performance, for which these
claims are for, the vendor had very few, if
any, employees hired to work on task order
N6945022F3005, so most, if not all, of the
money being billed is erroneous. It could be
considered fraudulent billing to the US
Government
d.
Labor violations: NA
e.
Special military or other urgency
concerning the project: NA
f.
Government estimate (time and money)
to complete the work: NA
g.
Funds available (in addition to funds
remaining under the contract) to
complete the work: NA
h.
Project reprocurement date (explain
what needs to be done prior to
reprocurement and the estimated date
for award of the completion contract
and for completion of the defaulted
work). Determination as to whether or not
105a
to re-procure these services remains to be
made, however, Re-procurement of these
services is not advised utilizing the FY22
funds on contract. As there is only an
additional maximum of 6-months remaining
to utilize these funds, there is not a
reasonable expectation that DCBL would
receive beneficial services in a timely
manner prior to the end of the Fiscal Year.
2.
FACTORS CONSIDERED IN DETERMINING
WHETHER CONTRACT SHOULD BE
TERMINATED FOR DEFAULT (reference FAR
49.402-3(f)):
a.
Terms of contract, applicable laws and
regulations: FAR Clause 52.249-8 Default
(Fixed-Price Supply and Service).
b.
Specific failure of contractor and the
excuses for failure:
ASG has failed to provide the self-sufficient
and self-supervised multidisciplinary
professional support team required by the
task order. The task order solicitation
required a team of at least 20 professionals
to provide professional support on site to
NAVFAC SE DCBL in Jacksonville, Florida.
ASG did not question the solicitation
requirements. Instead, offered 20 highly
qualified professionals to lure the
Government to award the task order to ASG.
Immediately after task order award, ASG
106a
began to fail on its promise, and began to
attack the Government for trying to enforce
the bargain of the parties under the terms
and conditions of the task order. ASG has
failed to provide the required self-sufficient
and self-supervised multidisciplinary team
for professional support performance on-site
at Jacksonville, Florida. Instead of accepting
failure and trying to negotiate an equitable
price reduction, ASG claims entitlement to
full compensation, arguing that it is not
require to provide the required and proposed
personnel and that the Government wants to
convert the contract into a prohibited
personal service contract. ASG argues that it
is not required to provide 20 professionals to
work at NAVFAC SE. ASG argues that it
can provide whatever staffing it deems
appropriate, from whatever location, and
with whatever qualifications regardless of
the terms and conditions of the task order
and ASGs proposal.
c.
The availability of the supplies or
services from other sources: The services
are available from other sources. There was
a total of 6 proposals (inclusive of ASG)
received in response to the solicitation issued
that led to the award of N6945022F3005.
d.
Urgency
of
the
need
for the
supplies/services and the period of time
required to obtain them from other
sources, as compared with the time
107a
delivery could be obtained from the
delinquent contractor: To be determined
based on the mission needs of DCBL.
e.
The degree of essentiality of the
contractor in the Government
acquisition program and the effect of a
termination for default upon the
contractors capability as a supplier
under other contracts: ASG is one of
many staffing companies in the United
States, and not essential to the Government
acquisition program. The termination for
default should not affect ASGs ability to
provide staffing under pre-existing contracts,
but may affect ASGs ability to obtain similar
contracts in the near future. The termination
for default may help other agencies avoid
similar negligent or fraudulent bait and
switch schemes under professional support
contracts.
f.
The effect of a termination for default
on the ability of the contractor to
liquidate guaranteed loans, progress
payments, or advance payments:
Unknown
g.
Any other pertinent facts and circumstances
(i.e. any Government vulnerability, etc.
explain):
The Government has been too lenient with
ASG, prolonging a default that was evident
108a
within the first five days of the contract into
five months of difficult contract
administration efforts. It is likely that ASG
will appeal the termination for default to
convert it into a termination for convenience.
ASG will argue that the task order is 100%
performance based and that the Government
should have allowed to perform with
whatever staffing, from whatever location,
a n d w i t h w h a t e v e r p r o f e s s i on a l
qualifications. As with all litigation, there
will be hefty expenses and time consuming
duties plus risk of an adverse judicial
decision.
3.
RECOMMENDATIONS:
a.
Based on the foregoing, termination for
default is in the Governments best interest
for the following reasons:
1.
The contractor is unwilling and/or
unable to provide the self-sufficient and
self-supervised multidisciplinary
professional support team required in
the task order. The requirements were
for professional support services
provided by a minimum of twenty (20)
qualified professionals as clearly
understood and expressly proposed by
ASG. However, ASG now argues that
due to market conditions it cannot
fulfill its proposal. Instead of
negotiating an equitable reduction of
109a
the contract price for reduced
performance, ASG insists that it can
reform the contract based on its own
self-serving contract interpretation and
a myriad of accusations against the
Government, demanding full payment
regardless of its lack of performance.
The Government cannot pay full price
for services that have not been
performed.
2.
To continue this contract would harm
and impede the mission of the United
States Navy. The contractor has
expressly stated that it is impossible for
it to obtain the multidisciplinary on-site
team (as was proposed) to provide the
required professional support to the
mission of NAVFAC SEs DCBL. If the
Government were to fully assign DCBL
professional support projects to ASG in
accordance with the contractual level of
service of a multi-disciplinary team of
at least twenty (20) professional, ASG,
having only five (5) qualified
professionals on its staff, would
certainly fail and negatively impact the
mission.
3.
The contractor appears to be involved in
a classic bait and switch operation with
regard to this task order. The vendor
proposed highly qualified individuals in
order to win the award. Upon winning
110a
the award, the vendor changed its
posture arguing that it does not have to
comply with portions of the task order
or portions of its proposal.
b.
Recommended re-procurement method: To
be determined upon discussions with DCBL
and assessment of command needs for
professional support services.
Prepared by:
ISELIN.CORY.
S.1100847996
Digitally signed by ISELIN.CORY.S.11
1100847996
Cory Iselin
CONTRACTING OFFICER/CONTRACT SPECIALIST
3/17/23
DATE
I have reviewed the above for form and legality:
GONZALEZ.JAVI
ER.E.1258530140
Digitally signed by GONZALEZ.JAVIER.E.
1258530140
Date 2023.03.21 09:27:15 -04'00'
3/21/23
DATE
Termination
Contracting
111a
Officer
or
Level
III
Contracting Officer approval:
/s/
Renee Comfort
Terminating Contracting Officer
4/4/2023
DATE
112a
APPENDIX F
STATUTORY AND REGULATORY
PROVISIONS
49.402-3 Procedure for Default
[48 C.F.R. § 49.402-3]
...
(d) Subdivisions (a)(1)(ii) and (a)(1)(iii) of the Default
clause cover situations when the contractor fails to
perform some of the other provisions of the contract
(such as not furnishing a required performance bond)
or so fails to make progress as to endanger
performance of the contract. If the termination is
predicated upon this type of failure, the contracting
officer shall give the contractor written notice
specifying the failure and providing a period of 10 days
(or longer period as necessary) in which to cure the
failure. When appropriate, this notice may be made a
part of the notice described in subparagraph (e)(1)
below. Upon expiration of the 10 days (or longer
period), the contracting officer may issue a notice of
termination for default unless it is determined that the
failure to perform has been cured. A format for a cure
notice is in 49.607.
(e) (1) If termination for default appears appropriate,
the contracting officer should, if practicable,
notify the contractor in writing of the possibility
of the termination. This notice shall call the
contractors attention to the contractual liabilities
113a
if the contract is terminated for default, and
request the contractor to show cause why the
contract should not be terminated for default. The
notice may further state that failure of the
contractor to present an explanation may be
taken as an admission that no valid explanation
exists. When appropriate, the notice may invite
the contractor to discuss the matter at a
conference. A format for a show cause notice is in
49.607.
(2) When a termination for default appears
imminent, the contracting officer shall provide a
written notification to the surety. If the contractor
is subsequently terminated for default, a copy of
the notice of default shall be sent to the surety.
(3) If requested by the surety, and agreed to by
the contractor and any assignees, arrangements
may be made to have future checks mailed to the
contractor in care of the surety. In this case, the
contractor must forward a written request to the
designated disbursing officer specifically directing
a change in address for mailing checks.
(4) If the contractor is a small business firm, the
contracting officer shall immediately provide a
copy of any cure notice or show cause notice to the
contracting offices small business specialist and
the Small Business Administration Area Office
nearest the contractor. The contracting officer
should, whenever practicable, consult with the
small business specialist before proceeding with
a default termination (see also 49.402-4).
114a
(f) The contracting officer shall consider the following
factors in determining whether to terminate a contract
for default:
(1) The terms of the contract and applicable laws
and regulations.
(2) The specific failure of the contractor and the
excuses for the failure.
(3) The availability of the supplies or services
from other sources.
(4) The urgency of the need for the supplies or
services and the period of time required to obtain
them from other sources, as compared with the
time delivery could be obtained from the
delinquent contractor.
(5) The degree of essentiality of the contractor in
the Government acquisition program and the
effect of a termination for default upon the
contractors capability as a supplier under other
contracts.
(6) The effect of a termination for default on the
ability of the contractor to liquidate guaranteed
loans, progress payments, or advance payments.
(7) Any other pertinent facts and circumstances.
...
(j) If the contracting officer determines before issuing
115a
the termination notice that the failure to perform is
excusable, the contract shall not be terminated for
default. If termination is in the Governments interest,
the contracting officer may terminate the contract for
the convenience of the Government.
52.249-8 Default (Fixed-Price
Service)
[48 C.F.R. § 52.249-8]
Supply
and
As prescribed in 49.504(a)(1), insert the following
clause:
Default (Fixed-Price Supply and Service) (Apr 1984)
(a) (1) The Government may, subject to paragraphs (c)
and (d) of this clause, by written notice of default to the
Contractor, terminate this contract in whole or in part
if the Contractor fails to(i) Deliver the supplies or to perform the services
within the time specified in this contract or any
extension;
(ii) Make progress, so as to endanger performance
of this contract (but see paragraph (a)(2) of this
clause); or
(iii) Perform any of the other provisions of this
contract (but see paragraph (a)(2) of this clause).
...
(f) The Government shall pay contract price for
116a
completed supplies delivered and accepted. The
Contractor and Contracting Officer shall agree on the
amount of payment for manufacturing materials
delivered and accepted and for the protection and
preservation of the property. Failure to agree will be a
dispute under the Disputes clause. The Government
may withhold from these amounts any sum the
Contracting Officer determines to be necessary to
protect the Government against loss because of
outstanding liens or claims of former lien holders.
(g) If, after termination, it is determined that the
Contractor was not in default, or that the default was
excusable, the rights and obligations of the parties
shall be the same as if the termination had been issued
for the convenience of the Government.
...
117a
This is a copy of a public record, reproduced as it was published. It is not legal advice, and it may not be the version a court would rely on. Check the official source before you cite it.