Emergency Application — West Virginia, et al., Applicants v. Environmental Protection Agency, et al.

Supreme Court briefJul 23, 2024

Ask Donna

What actually matters in this document.

Text

service requirements of its Montana customers|,|” § 69-3-1204(2)(a)(i),

MCA.

6. The Rule introduces significant economic uncertainty for

important electricity generating units (““EGUs’”) in the portfolio of

electricity resources serving Montana residents and businesses and

underpinning the export of electricity to utilities across the pacific

northwest region of states. The Rule also limits the options for adding

new generation to serve existing and new electricity demand in

Montana. Specifically, the Rule requires major modifications to the

existing Colstrip Units 3 and 4 in Rosebud County, Montana.

7. Colstrip Units 3 and 4 are coal-fired steam generating units,

each with a nameplate generating capacity of 740 megawatts. The units

are operated by Talen Montana and currently serve residential and

commercial customers of NorthWestern Energy in Montana, large

industrial customers of Talen Montana, as well as electricity customers

of utilities with service territories including parts of Idaho, Washington,

and Oregon. The units play an integral role in maintaining operation of

the NorthWestern Balancing Authority in Montana, especially during

peak electricity demand events. NorthWestern Energy, a thirty percent

4

498a

owner of Unit 4 has announced plans to acquire Avista Corporation’s

fifteen percent shares in Units 3 and 4, effective January 1, 2026.

NorthWestern’s depreciation schedule for its current share of Unit 4

runs through 2042.

8. The Rule’s requirement of 90 percent carbon capture has not

been adequately demonstrated as required of the best system of emission

reduction (BSER) in Section 111 of the Clean Air Act. In addition to the

degree of emission limitation available through application of BSER, the

cost of achieving the reduction must be considered. Carbon capture and

sequestration/storage (CCS) has been extremely expensive to implement

and operate. Two examples of failed CCS operations are the Kemper

CCS site in Mississippi (not operating on coal any longer) and the Petra

Nova CCS site in Texas. One site that is still operating is the Boundary

Dam CCS project in Canada which, at best, operates at a 65% carbon

capture and cost $4.2 million per megawatt (MW). If this cost was scaled

to the MW ratings of the Colstrip units, capital costs would be in the

billions of dollars, not to mention the parasitic loads which are required

for capturing the carbon dioxide - most likely in an absorption tower that

requires significant heating and cooling operations.

5

499a

9. A 2016 report from the US Department of Energy (DOE)

predicted as much as $3 billion to retrofit the Colstrip units as a

preliminary cost estimate; scaling the $4.2 million per MW from

Boundary Dam to Colstrip suggests that capital costs could be as high

as $15 billion. Until projects can demonstrate 90% carbon capture,

incorporating this requirement in the Rule is not realistic on a technical

or financial basis.

10. The cost of transportation and storage for CCS is much higher

in Montana’s Powder River Basin than in other states. A study

referenced in the proposed rule reports that the CQO2 pipeline

transportation and storage cost in 2018 was $22/tonne for the Powder

River Basin. The other basins in the study were Illinois ($10/tonne), East

Texas ($11/tonne), and Williston ($15/tonne). Montana questions the

equity of its sites to have the same CCS requirements as other states,

while taking on much greater costs, which are based on reservoir geology

and thereby unavoidable.

11. EPA dismisses the potential impacts to electric system

reliability caused by closure of EGUs that are unable to justify the

economic impact of Rule compliance costs. In dismissing those concerns,

6

500a

EPA does not adequately account for direct impacts of the Rule in

Montana and the NorthWestern Energy Balancing Authority that would

be caused by potential closure of impacted EGUs. Colstrip Units 3 and 4

generated forty one percent of the electricity generated in Montana in

2022, and represented twenty three percent of total installed generating

capacity, see Electricity Statistics Tables, Mont. Department of

Environmental Quality, accessed at

https://deq.mt.gov/files/Energy/Documents/Energy_Statistics/Electricit

y Tables2023-Updated.xlsx. Colstrip’s generating capacity in high load

events varies depending on maintenance schedules, and the availability

and price of other supply resources. However, during the peak of record

setting electricity demand in the NorthWestern Balancing Authority

driven by a severe cold weather event in January 2024, coal fired EGUs

within the balancing authority generated seventy five percent of the

customer electricity demand, see Hourly Electric Grid Monitor, U.S.

Energy Information Administration,

https://www.ela.gov/electricity/gridmonitor/dashboard/electric overview

/balancing authority/NWMT (accessed May 8, 2024). Peak electricity

demand for that event hit on January 138, 2024, a day when

7

501la

temperatures dropped below minus 30 degrees Fahrenheit in major

population centers served by NorthWestern.

12. If the costs of compliance with the Rule prove prohibitively

expensive to undertake, the Rule requires retiring Colstrip Units 3 and

4 prior to January 1, 2032, leaving large industrial customers and utility

owners of the units to replace the generating capacity and energy output

of those EGUs with a mix of resources capable of reliably meeting

comparable energy and capacity requirements, while continuing to meet

the growing demand for electricity in Montana. The requirement to

replace the output of the Colstrip units would come at a time when the

Western Electricity Coordinating Council has assessed that, “(s)upply

chain disruptions, increasing costs, production obstacles, and an

overwhelmed interconnection queue threaten industry timelines to build

new resources,” see 2023 Western Assessment of Resource Adequacy,

Western Electricity Coordinating Council (accessed May 8, 2024),

https://www.wecc.org/Administrative/2023%20Western%20Assessment

%200f%20Resource%20Adequacy.pdf. The uncertainty of adding

replacement generation to adequately meet growing demand threatens

the ability of Montana utilities to meet customer demands in accordance

8

502a

with other legal requirements, such as North American Electric

Reliability Corporation (“NERC”) Standards. See NERC, Reliability

Standards (last visited May 3, 2024),

https://www.nerc.com/pa/Stand/Pages/ReliabilityStandards.aspx.

13. Risks to electricity system reliability, driven in part by

retirement of dispatchable, high-capacity factor thermal EGUs, is a

matter of significant concern. WECC reports that current utility

resource plans in the western interconnect “are not sufficient to meet

future demand over each of the next 10 years,” and that “starting in

2026, the number and magnitude of demand-at-risk hours increase by

orders of magnitude.” WECC attributes the growing risks to reliability

to increasing variability, “driven primarily by the addition of nondispatchable variable energy resources (VER), the retirement of

dispatchable resources, and the increase in load uncertainty due to

extreme weather events,” see 2023 Western Assessment of Resource

Adequacy, Western Electricity Coordinating Council (accessed May 8,

2024),

https://www.wecc.org/Administrative/2023%20Western%20Assessment

%200f%20Resource%20Adequacy.pdf.

9

503a

aw ona Newakeowdfe

SONJA NOWAKOWSKI

Dated: May 10, 2024

10

504a

EXHIBIT 14

505a

DECLARATION OF GAVIN MCCOLLAM

I, Gavin A. McCollam, declare as follows:

1. My name is Gavin A. McCollam. I am the Senior Vice President

and Chief Operating Officer of Basin Electric Power Cooperative (“Basin

Electric”). I am over the age of 18 years, and I am competent to testify

concerning the matters in this declaration. I have personal knowledge of the

facts set forth in this declaration, and if called upon and sworn as a witness,

could and would competently testify to them.

2. Ihave more than 35 years of experience in the electric generation

industry. I have been employed at Basin Electric since 1989. I hold an

associate’s degree from Bismarck (North Dakota) State College, a bachelor’s

degree in mechanical engineering from North Dakota State University, and

a master’s degree in systems management from the University of Southern

California. I am also a registered professional engineer.

3. Basin Electric is a member of the National Rural Electric

Cooperative Association (“NRECA”). This declaration is submitted in

support of NRECA’s and North Dakota’s legal challenges to the rule entitled

506a

New Source Performance Standards for Greenhouse Gas Emissions From New,

Modified, and Reconstructed Fossil Fuel-Fired Electric Generating Units; Emission

Guidelines for Greenhouse Gas Emissions from Existing Fossil Fuel-Fired Electric

Generating Units; and Repeal of the Affordable Clean Energy Rule, 89 Fed. Reg.

39798 (May 9, 2024) (the “Final Rule” or “Rule”).

I. BASIN ELECTRIC

4. I am familiar with how the Final Rule will affect Basin Electric,

the electric markets, and suppliers of electric equipment and services, as well

as Basin Electric’s consumer members.

5. Basin Electric is a not-for-profit generation and transmission

(“G&T”) cooperative incorporated in 1961 to provide supplemental power to

a consortium of rural electric cooperatives. Those member cooperatives— 140

of them—are Basin Electric’s owners. Through them, Basin Electric serves

approximately three million consumer members in an area that covers

roughly 500,000 square miles across nine states: Colorado, lowa, Minnesota,

Montana, Nebraska, New Mexico, North Dakota, South Dakota, and

Wyoming. Basin Electric’s end-use consumer members across these nine

507a

states include residential, farm, commercial, industrial, and irrigation electric

consumers. In 2022, Basin Electric’s farm and residential consumer members

accounted for 29% of its megawatt-hour (“MWh”) sales, while the

commercial and industrial consumer members accounted for 68% of the

MWh sales.

6. As of the end of 2023, Basin Electric had an asset base of $8 billion

and operated 5,219 megawatts (“MW”) of wholesale electric generating

capability and had 8,112 MW of generating capacity within its portfolio.

Those owned electric generation facilities are located in the states of lowa,

Montana, North Dakota, South Dakota, and Wyoming. Basin Electric’s

members provide electric service to 75% of the persistent poverty counties

located within the nine states served, according to the 2023 persistent

poverty data compiled by the U.S. Department of Agriculture Economic

Research Service.

7. In order to provide the reliable electric supply that the member

owners expect, Basin Electric is committed to an “all of the above”

generating strategy which calls for multiple generating units utilizing

508a

diverse fuel types (both fuel-fired and renewable resources) at dispersed

locations. Basin Electric has invested and committed to approximately $7

billion dollars in developing new renewable energy resources, and it

of the end of 2023). The other components of Basin Electric’s portfolio

include coal-fired generation (=2,850 MW), natural gas-fired generation

(1,250 MW), market purchases (=1,350 MW), hydroelectric (=300 MW),

other fossil fuels (175 MW), and recovered energy (50 MW).

8. Basin Electric’s diverse portfolio of electricity generation is a

result of the significant investments that Basin Electric has made in the past

two decades, as the following infographic summarizes:

YEAR

2,839 MW Poses G oF

er Cost Oii/ Diesei Jet Fuei tiydro

2400 MW + 34.6% 120 MW « 4.2% 319 MW - 11.2%

YEAR

Lr

8.112 MW oad “y 4)

—_—— Coal Natural Gas Recovered Energy Market Purchases

2280 MW + 32% 1.266 MW « 15.6% 45 Vw + 0.6%. 1339 MW « 16.5%

OW Diesel Jet Fuel Hydro Wind

T7S MW + 22°, 318 MW - 3.9%. 2,108 MW - 26%

209a

9. Basin Electric has many electric generating units (“EGUs”) that

fall within the scope of the Final Rule (“affected EGUs”) and thus must

comply with the Final Rule’s stringent new standards for coal-fired steam

units. These affected EGUs have remaining useful lives that would be

significantly shortened under the Final Rule absent massive amounts of new

investment to cover all the compliance costs that the Rule creates. These

substantial costs would fall on Basin Electric, and ultimately, on our rural

consumer members. The table below identifies the EGUs that would be

impacted if the Final Rule takes effect. The table also shows the results of

Basin Electric’s preliminary analysis of the approximate capital costs to

comply with the Final Rule.

Affected EGU | State Compliance Strategy = Capital Cost

F 2 billion

mah ork WY _|Long Term: CCS at 90%. $

Station

Antelove Valle Medium Term: Co-fire with

; P ; y ND |natural gas by 2029; retire by |$104 million

Station Unit 1

2038.

Antelope Valley Medium Term: Co-fire with

Station Unit 2 ND _|natural gas by 2029; retire by |$104 million

2038.

510a

Leland Olds ND_ |Applicability exemption; $0

Station Unit 1 retire by 2031.

Leland Olds ND _ |Applicability exemption; $0

Station Unit 2 retire by 2031.

Laramie River WY |Unknown Unknown

Station Unit 1*

Laramie River

; WY |Unknown Unknown

Station Unit 2”

Laramie Kiver WY |Unknown Unknown

Station Unit 3*

Walter Scott Jr.

Energy Center IA |Unknown Unknown

Unit 3**

Walter Scott Jr.

Energy Center IA jUnknown Unknown

Unit 4**

George Neal

South Generating IA jUnknown Unknown

Station Unit 4***

Replacement Unknown Unknown

Generation

*Basin Electric owns an undivided joint interest in Laramie River of

approximately 42%.

** Basin Electric has a power purchase agreement with one of its

members for the output of their ownership interest in Walter Scott Jr.

Energy Center Unit 3 and Unit 4. Through those agreements with its

members, Basin Electric has financial responsibility for approximately

4% of Unit 3 and approximately 6% of Unit 4. Such rights do not

provide the ability to make decisions on these Units.

5lla

*** Basin Electric has two power purchase agreements with two of its

members for the output of their ownership interest in George Neal

South Unit 4. Collectively, Basin Electric has financial responsibility for

approximately 16% of the unit. This percentage does not provide the

ability to make decisions on this unit. MidAmerican Energy Company,

as the majority owner and the operator of the unit, has this right and

responsibility.

10. Basin Electric is currently in the middle of a massive generation

and transmission buildout necessary to address load growth and long-term

grid stability for its growing membership. Basin Electric is constructing an

addition of approximately 580 MW of natural gas simple cycle generation to

the existing Pioneer Generation Station, at a cost of approximately $800

million, that is expected to come online in 2025. Basin Electric is also actively

investigating the need for more than 1,000 MW of dispatchable generation

in western North Dakota by 2030 to address members’ needs. This new

generation will also need to comply with the Final Rule. In addition to these

active generation projects, Basin Electric is also constructing over 300 miles

of high voltage transmission line projects along with several major

substation projects. The transmission line projects include the Roundup-to-

Kummer Ridge 345kV project, the Leland Olds Station-to-Tande 345kV

512a

project, and the Tande and Wheelock-to-Saskatchewan 230kV project. These

projects have a combined cost of more than $700 million.

11. The table and graph below illustrate the projected capital cost

associated with the planned generation expansion without the Final Rule

(“Base Case’), as well as the projected capital cost associated with meeting

load growth and complying with the Final Rule through 2045 (“Final Rule

Case”). The incremental capital cost through 2035 to comply with the Final

Rule is nearly $10 billion. The incremental capital cost through 2045 to

comply with the Final Rule is more than $14 billion. These costs do not

include any costs that would be associated with Final Rule compliance at

Laramie River, Water Scott Jr. Energy Center, or George Neal South

Generating Station.

51l3a

2030-2045 Base Case Final Rule

Total Need (SPP): 3,000 MW 3,500 MW

Total Need (RMPA): 350 MW 450 MW

Total Need (MISO): 45 MW 45 MW

Total Resource Need: 3,395 MW 3,995 MW

Avg Resource Costs: @ ~$2,000/kW @ ~$4,400/kW

Total Cap Costs: $6,790,000,000 $17,578,000,000

Net Incremental Costs to Resource Expansion +$10,788,000,000

NG Conversion +S 208,000,000 +

Carbon Capture on DFS + WLP Resource +S 3,800,000,000

Total incremental Costs =$14,796,000,000+

Resource Installed Costs by Year

$25,000

$29,000

$15,000 u

/ $14,796 MM

* / Ps difference

9,985 iM

difference

aes | aa a oe

mM Che ES pated L i

2030 2031 2032 2033 2034 2035 2036 2037 2038 2033 2040 2041 2042 2045 2044 2045 2046 2047 20428 2049 2050

Millions of Dollars |$)

:

S.,

N

,

)

“,

Game Bose Cese Instolicd Costs wee Firiol Rule Coase Insta led Costs — — Bose Cese GQumulative Costs — — Final Rule Case Curnuletive Costs

Il. OVERVIEW OF THE FINAL RULE

12. The Final Rule sets CO2 emissions limits that States must apply

to existing coal-fired steam electric generating units, under Section 111(d).

dl4da

89 Fed. Reg. 39840. The Rule also sets CO2 emissions limits for new gas-fired

combustion-turbine units, under Section 111(b). Id. 39902. Both types of units

must meet emissions limits equal to what EPA believes 90% carbon-captureand-sequestration can achieve. Existing units that cannot achieve this must

shut down. New units that cannot achieve this must drastically limit their

output of electricity.

13. Existing coal-fired units. The Rule divides existing coal-fired steam

units into three non-overlapping subsets: two are “subcategories” and one is

an “applicability exemption.” Id. 39841. These subsets are defined by

whether a unit has committed to permanently retire, and by the retirement

date that a unit has committed to. See id. For purposes of implementing these

subcategorizations for a particular unit, EPA recognizes only those

retirement commitments that are made “federally enforceable” via inclusion

in a State plan. Id. 40000. State plans are due to EPA in 24 months. Id. 39997.

14. The first (and default) subcategory is for “long-term” units,

which EPA defines as units that “intend to operate past January 1, 2039.” Id.

39801. EPA says that the best system for this subcategory is CCS that

10

515a

captures 90% of the CO2 from a unit. Id. 39845. This system begins with the

design, engineering, and installation of COz capture technology. Id. 39846.

Then the captured COz must be transported (usually via pipeline) to a site

that can permanently sequester it (usually underground). See id. EPA

“assumes” that “work” toward “each component of CCS” will begin in “June

2024.” Id. 39874. And the Rule requires unit operators to complete that work

before January 1, 2032. Id. 39801.

15. The second subcategory is for “medium term” units: those that

commit “to permanently cease operations” sometime “after December 31,

2031” but “before January 1, 2039.” Id. 39841; see id. 39958. EPA says that best

system for this subcategory is “[nJatural gas co-firing at 40 percent.” Id.

39801. That means transforming a coal unit into a unit that combusts both

coal and natural gas. See id. Just “[a]s in the timeline for CCS,” EPA

“assumes” that “work” toward co-firing will begin in June 2024. Id. 39893.

And the Rule requires medium-term unit operators to complete that work

before January 1, 2030. Id. 39845.

11

5l6a

16. Third, the Rule establishes an “applicability exemption” for units

that commit “to permanently cease operation before January 1, 2032.” Id.

39841. These units “are not regulated by” the Rule. Id. 39843. However, if

such a unit then “continues to operate past [that date], then it is no longer

exempt,” id., putting the unit “in violation of” the State plan and the Clean

Air Act, id. 39991.

17. New gas-fired combustion turbine units. For new and modified gasfired combustion turbines, the Rule creates three subcategories. These

subcategories are defined by a unit’s “electric sales (i.e., utilization) relative

to the [unit’s] potential electric output.” Id. 39908. “Low load” units (those

that sell “20 percent or less of their potential electric output”) must comply

with a standard of performance based on “lower-emitting fuels.” Id. 39917.

“Intermediate load” units (those that sell 20-40%) must comply with a

standard based on “high-efficiency simple cycle turbine technology.” Id.

“Base load” units (those sell more than 40%) must comply with a “multiphase standard of performance.” Id. 39923. Phase I is “based on the

performance of a highly efficient combined cycle turbine” and has “an

12

517a

immediate compliance date.” Id. 39903. Phase II is based on 90% CCS and

has “a compliance date of January 1, 2032.” Id.

Ill. IMPACTS TO AFFECTED EGUs

18. Impacts at Dry Fork Station — “Long Term” subcategory. The Dry

Fork Station (“Dry Fork”) consists of one 405 MW affected EGU located in

Gillette, Wyoming. It began operation in 2011, with a construction cost of

$1.35 billion. The station uses pulverized subbituminous coal technology

and the latest generation of pollution control technologies resulting in very

low emissions. As water is a scarce resource in Wyoming, Dry Fork uses air

cooling. The plant location has potential area to site a carbon capture unit.

Dry Fork is home to the Wyoming Integrated Test Center and the Wyoming

CarbonSAFE project, both of which receive funding from the Department of

Energy and the state of Wyoming for research projects that aim to help

develop CCS technology.

19. Dry Fork is a relatively new coal-fired power plant, and its

remaining depreciable life extends into the early 2070s. As a result, Basin

Electric plans to leave Dry Fork within the Final Rule’s default category for

13

518a

“long term” EGUs. That decision requires Basin Electric to achieve 90% CCS

at Dry Fork by the end of 2031. That level of CCS, if it can be achieved at all

and in that time frame, can only be achieved with significant time and at

great expense and risk. Indeed, Basin Electric is not aware of any

manufacturer currently offering to warrant equipment that will achieve 90%

CCS under any conditions, much less under large-scale and high-demand

baseload conditions. Still, to have any hope of meeting the Final Rule’s 2031

deadline for Dry Fork, Basin Electric must immediately begin spending

money across a variety of expense categories.

20. Carbon capture costs. If it is possible to achieve 90% carbon capture

at Dry Fork, it would require the addition of a post-combustion capture

system. The cost for such a system is estimated to total approximately

$2 billion. That astronomical expenditure is more than 150% of what it cost

to construct the Dry Fork in the first place barely a decade ago. Complying

with the Final Rule’s 2031 deadline would require that Basin Electric enter

into engineering, equipment, and other contracts immediately.

14

519a

21. Basin Electric would first need to enter into engineering

contracts, as a great deal of engineering would need to be performed prior

to entering into any equipment contracts. Engineering costs typically

represent approximately five percent of project costs, and are typically more

costly for projects which involve the construction of new technology. In

addition, Basin Electric would also need to hire an engineering firm to

commence modeling work in order to apply for the permits necessary to

begin construction of such a project.

22. Thenext step is ordering equipment. The carbon capture process

equipment alone would cost Basin Electric approximately $400 million and

a down payment of approximately 10% would likely be required.

Engineering and equipment would need to be scheduled and committed to

within the next 12 months. Based on previous experience, approximately 5 —

10% of the total project cost is spent on engineering and design costs. In the

first two years alone, Basin Electric would expect to spend approximately

$20 million on preliminary engineering and design costs that, but for the

Final Rule, would not be expended.

15

520a

23. Carbon transport costs. For CCS to work, once captured, the COz

must be transported to appropriate pore space. At Dry Fork, this would

require approximately 27 miles of pipeline, based on preliminary studies.

Some level of CCS would be feasible at Dry Fork (if at all) only because there

is pore space in the region that could accommodate CO: storage. Still,

constructing a pipeline to transport captured COz from Dry Fork to this

location would cost approximately $4 million per mile. Given high demand

and long lead times for labor and specialized piping—both of which will

only worsen as owners of EGUs across the country simultaneously attempt

to comply with the Final Rule—Basin Electric must begin spending money

immediately for planning, design, engineering, siting, permitting, and

construction of a pipeline to transport captured CO2.

24. Basin Electric’s subsidiary, the Dakota Gasification Company,

recently built a COz pipeline. Based on that project, we estimate the required

pipeline for Dry Fork would cost approximately $108 million and that Basin

Electric would perform the engineering design and procure the equipment

at a cost of approximately $50 million in the first two years.

16

52la

25. Carbon storage costs. Once it is transported, the captured COz

from Dry Fork must be stored. Identifying and contracting for the necessary

pore space is likely as challenging as meeting the 90% carbon capture

requirement. Pore space in Wyoming will be challenging to procure, in light

of the large percentage of federally owned land within the state. There is

potentially suitable geology for CCS near Dry Fork, but geology is only the

first piece of the puzzle. Even once transportation is solved, pore space can

be utilized for storage only after an operator leases the thousands of acres of

pore space and designs, permits, and constructs the storage facility. As with

constructing a pipeline, all of that is outside Basin Electric’s control. Leasing

pore space for storage is both time-consuming and expensive.

26. Operational costs. According to a third-party study that Basin

Electric commissioned several years ago, the annual operating and

maintenance cost for 70% carbon capture at Dry Fork was estimated to be

$56 million (2029). But even implementing that plan would not be sufficient

to comply with the Final Rule, which would instead require Dry Fork to

achieve a 90% CCS by January 1, 2032. Assuming 90% capture could be

17

522a

achieved, that level of CCS would cost even more in annual operating

expenses. The technology for attempting to achieve 90% CCS also demands

significant water usage. Water is a scarce resource in Wyoming and would

only be available at substantial expense. All of these are costs that Basin

Electric must ultimately pass through to its consumer members.

27. Reliability impacts. One further significant cost is that CCS at any

level tends to make an EGU less reliable. This makes unplanned outages

more frequent and more severe. Basin Electric personnel have been to the

Boundary Dam CCS project in Saskatchewan, and Basin Electric is familiar

with the challenges experienced by SaskPower in maintaining and operating

that capture unit, including unplanned outages. Unplanned outages

increase Basin Electric’s overall costs, hurt its relationships with consumer

members, and can even affect its standing with the Regional Transmission

Organization (“RTO”). Therefore, the reliability impacts of CCS are another

significant risk facing Basin Electric.

28. Impacts at Antelope Valley Station — “Medium Term” subcategory.

The Antelope Valley Station (”Antelope Valley”) consists of two affected

18

523a

EGUs located in Beulah, North Dakota. Each EGU is rated at 450 MW.

Antelope Valley is located on a site adjacent to Dakota Gasification

Company’s Great Plains Synfuels Plant. Antelope Valley began operation in

the 1980s, with a construction cost of approximately $1.9 billion. Antelope

Valley is fueled by lignite coal from the adjacent Freedom Mine.

29. Antelope Valley’s remaining depreciable life extends into the

2040s. Yet the Final Rule’s default BSER—90% CCS by the end of 2031—is

not economically feasible at Antelope Valley due to the age of the units and

the short time that would be available to recover the massive investment

necessary for CCS. Basin Electric has engaged in extensive efforts to

participate in CCS research and development, including spending millions

of dollars toward project development to build a demonstration project at

Antelope Valley. That demonstration aimed to capture CO2 emissions from

about one quarter of one of the units at the plant. In other words, even this

state-of-the-art demonstration project would not be sufficient to comply with

the Final Rule. But even with a $100 million grant from the DOE and the

availability of Dakota Gasification Company’s pipeline for transporting the

19

524a

captured CQ2, Basin Electric’s feasibility study determined that the

technology required too large of a parasitic load. Additionally, it came with

an estimated cost of at least $500 million in 2010, would result in a significant

increase in the cost of electricity to Basin Electric’s members, and posed too

great a risk given the technology provider was unwilling to guarantee the

removal rate.

30. Due to these and other factors, Basin Electric plans to

subcategorize Antelope Valley into the Final Rule’s “medium term”

subcategory. That election requires Basin Electric to make a legally binding

commitment (in 2025 or 2026) to shut Antelope Valley down by 2038, and to

achieve 40% natural gas co-firing at Antelope Valley by the end of 2029. To

achieve that, Basin Electric must immediately begin spending money across

a variety of expense categories.

31. Equipment costs. Retrofitting Antelope Valley’s EGUs to co-fire

40% natural gas by the end of 2029 will require Basin Electric to make

immediate capital expenditures. Antelope Valley uses natural gas as a

startup fuel, but the existing equipment only allows for approximately 20%

20

525a

co-firing. Because of that, each EGU’s burner unit must be replaced, at an

approximate total cost of $4 to 5 million. Burners are not “off the shelf”

equipment, but instead must be purchased from a limited number of original

equipment manufacturers, all of whom will simultaneously be facing a

massive increase in demand from other affected EGUs across the country.

32. Transport costs. Basin Electric cannot co-fire natural gas at

Antelope Valley unless there is a way for natural gas to be transported to

those EGUs. Antelope Valley currently receives natural gas for startup fuel

via a pipeline sourced from the Great Plains Synfuels Plant. However, to

have an independent supply of natural gas would require installation of an

approximately 40-mile pipeline connecting Antelope Valley to the closest

interstate gas pipeline, Northern Border Pipeline, and related fuel supply

infrastructure at cost of approximately $160 million (based on the

assumption of $4 million per mile.) Given the long lead times for

construction projects, a pipeline operator must begin design, permitting,

siting, procurement, and construction immediately merely to have a chance

to have natural gas available to Antelope Valley in time for the Final Rule’s

21

526a

end-of-2029 deadline. But no operator is likely to take all those steps without

a substantial, up-front commitment from Basin Electric—either in the form

of a capital contribution to the project, or in the form of a long-term (20-30

year) supply contract. Even if Basin Electric identified an operator and

agreed to such terms, there is no guarantee that such a pipeline could

actually be completed in time. Permitting, engineering construction, rightof-way acquisition, and myriad other factors could block the pipeline or

could delay it beyond the Final Rule’s compliance deadlines. If that

happened, Basin Electric’s investments in equipment costs would be

completely lost, and Antelope Valley would need to shut down.

33. Permitting risks. Converting Antelope Valley to natural gas cofiring will also require Basin Electric to obtain new permits, including a New

Source Review permit and an updated Title V permit. But these permits are

expensive and time consuming, and their issuance is also subject to judicial

review. In order to have proper permitting in place by 2030, Basin Electric

must immediately begin the permitting process for Antelope Valley.

22

527a

[OCR skipped on page(s) 31-108]

[Read from a scan; the first 30 pages.]

This is a copy of a public record, reproduced as it was published. It is not legal advice, and it may not be the version a court would rely on. Check the official source before you cite it.

A word about cookies

We need a few to keep you signed in and the library working. The rest help us see which pages people use and where they get stuck. They stay off unless you say yes.