Emergency Application — North Dakota, et al., Applicants v. Environmental Protection Agency, et al.
Supreme Court briefAug 16, 2024
Ask Donna
What actually matters in this document.
Text
USCA Case #24-1119
Document #2058570
Filed: 06/07/2024
Page 83 of 204
Mercury Emissions: Lignite Coals
60
Mercury Fuel Content (lbs/TBtu)
50
40
30
20
10
0
Coal Lake
Coulee
Kinneman
Creek
Hagel A Coal Hagel B Coal
Seam
Seam
Tavis Coal
Seam
Coyote Quality Coteau DH
Data
Figure 6-1. Mercury Content Variability for Eight North Dakota Lignite Mines
4
3.5
Fuel Sulfur Content (%)
3
2.5
2
1.5
1
0.5
0
Coal Lake
Coulee
Kinneman
Creek
Hagel A Coal Hagel B Coal
Seam
Seam
Tavis Coal
Seam
Coyote Quality Coteau DH
Data
Figure 6-2. Fuel Sulfur Content Variability for Eight North Dakota Lignite Mines
(Page 209 of Total)
23
393a
USCA Case #24-1119
Document #2058570
Filed: 06/07/2024
Page 84 of 204
Mercury Emissions: Lignite Coals
8
7
Aalikalinity Ratio (CA+NA/S)
6
5
Approximate
Range for
PRB Coal
4
3
2
1
0
Coal Lake Coulee Kinneman Creek
Hagel A Coal
Seam
Hagel B Coal
Seam
Tavis Coal Seam
Coyote Quality Coteau DH Data
Figure 6-3. Fuel Alkalinity/Sulfur Ratio for Eight North Dakota Mines
Figure 6-1 compares the Hg content and variability to the fixed value of 7.7-7.8 lbs/TBu,
assumed by EPA as representing North Dakota lignite, as summarized in Table 11 of the Tech
Memo. Figure 6-1 shows – with the exception of the Tavis seam – all mean values of Hg content
exceed EPA’s assumed value that serves as the basis of EPA’s evaluation. More notably, the 75 th
percentile value of Hg for each seam - slightly more than one standard deviation variance from
the mean – in all cases significantly exceeds the value assumed by EPA.
Of note is that the variability of Hg depicted in Figure 6-1 is not necessarily observed only over
extended periods of time – such as months or quarters – it can be witnessed over period of days
or weeks. This is attributable to the sharp contrast in Hg content of seams that are
geographically proximate and thus are mined within an abbreviated time period. Figure 6-4
presents a physical map showing the location of “boreholes” in a lignite field with imbedded text
describing (in addition to the borehole code) the Hg content as ppm. The text boxes report this
Hg content in terms of lbs/TBtu. These example boreholes – separated by typically 660 feet- and
the factor of 3 to 6 variation of Hg content present a meaningful visualization of Hg variability in
a lignite mine, and the consequences for the delivered fuel.
(Page 210 of Total)
24
394a
USCA Case #24-1119
Document #2058570
Filed: 06/07/2024
Page 85 of 204
Mercury Emissions: Lignite Coals
10.70
lbs/TBtu
19.23
lbs/TBtu
2.97 lbs/TBtu
Figure 6-4. Spatial Variation of Hg in a Lignite Mine
Data from Figure 6-1 is summarized in Table 6-1 for units at four stations in North Dakota –
Coal Creek, Antelope Valley, Coyote, and Leland Olds. Both Figures 6-1 and Table 6-1 show
Hg variability exceed that assumed by EPA in their evaluation. Table 6-1 shows that achieving a
1.2 lbs/TBu requires an Hg removal rate of approximately 93-95% for unavoidable instances
where coal Hg content is at the 95th percentile of observed value. The approximate 93-95% Hg
wh
removal requirements well exceed the 85% Hg removal based on the IPM-assigned Hg content.
(Page 211 of Total)
25
395a
(Page 212 of Total)
Coyote Upper Belauh
Kinneman Creek,
Hagel A, Hagel B
Freedom
Coyote
Creek
Freedom
Antelope
Valley
Coyote
Leland
Olds
UTAV, HGB1 and
HGA1/HGA2 (Mostly
Haga A seam)
Freedom Mine Belauh
Seam
Seams
Falkirk
Mine
Coal
Creek
Station
7.81
7.81
7.81
7.81
IPM
Designated
Hg Rate
(lbs/TBtu)
Table 6-1. Hg Variability for Select North Dakota Reference Stations
7.79
7.79
7.76
7.80
Inferred
EIA 2021
Hg Rate
(lbs/TBtu)
23.0
19.2
23.0
Hg Fuel
Content
at 95th
Percentile
(lbs/TBtu)
25.1
94.8
93.8
94.8
95.2
Hg Removal (%)
for 1.2 lbs/TBtu
at
th
95 Percentile
26
Mercury Emissions: Lignite Coals
USCA Case #24-1119
Document #2058570
Filed: 06/07/2024
Page 86 of 204
396a
USCA Case #24-1119
Document #2058570
Filed: 06/07/2024
Page 87 of 204
Mercury Emissions: Lignite Coals
6.2
Texas Gulf Coast Mines and Generating Units
Figures 6-5 to 6-7 present data from Texas and Mississippi lignite mines describing the content
and variability for Hg, sulfur, and the (Ca + Na)/S metric, as delivered to generating units in
Texas. Analogous to the data cited for North Dakota, the “box and whisker” depiction represents
the same metrics.
80
Mercury Fuel Content (lbs/TBtu)
70
60
50
40
30
20
10
0
MS_Mine
TX_Mines
Figure 6-5. Mercury Variability for Two Gulf Coast Sources: Mississippi, Texas
Table 6-2 compares the Hg removal required to meet the proposed 1.2 lbs/TBtu rate considering
the variability of Hg in Texas and Mississippi coals, in
instead of the IPM-assigned Hg coal
content. For three Texas plants that fired 100% lignite – Major Oak Units 1 and 2, Oak Grove
Units 1 and 2, and San Miguel – EPA assigned inlet Hg values from 12.44 to 14.88 lbs/TBtu,
implying Hg removal of 90-92% to achieve 1.2 lbs/TBtu. However, based on the 95th percentile
value of the Texas lignite Hg values from Figure 6-5, the required Hg removal would be 96
96-97
97%.
(Page 213 of Total)
27
397a
USCA Case #24-1119
Document #2058570
Filed: 06/07/2024
Page 88 of 204
Mercury Emissions: Lignite Coals
1.60
1.40
Fuel Sulfur Content (%)
1.20
1.00
0.80
0.60
0.40
0.20
0.00
MS_Mine
TX_Mines
Figure 6-6. Sulfur Variability for Mississippi, Texas Lignite Mines19.1
4.5
4.0
Approximate
Range for
PRB Coal
Aalikalinity Ratio (CA+NA/S)
3.5
3.0
2.5
2.0
1.5
1.0
0.5
0.0
MS_Mine
TX_Mines
Figure 6-7. Fuel Alkalinity/Sulfur Ratio for Mississippi, Texas Lignite Mines
(Page 214 of Total)
28
398a
(Page 215 of Total)
14.88
12.44
14.65
Mines
Calvert
Kosse Strip
Red Hills
San Miguel
Lignite
Major Oak 1,2
Oak Grove 1, 2
Red Hills 1, 2
San Miguel
Station
IPM
Designated
Hg Rate
(lbs/TBtu)
14.65
14.62
12.4
14.6
Inferred
EIA 2021
Hg Rate
(lbs/TBtu)
14.62
Table 6-2. Hg Variability for Select Texas Reference Stations
38.1
67.6
38.12
38.12
Hg Fuel Content
at 95th Percentile
(lbs/TBtu)
96.9
98.2
96.9
96.9
Hg Removal (%) for 1.2
lbs/TBtu at
95th Percentile
29
Mercury Emissions: Lignite Coals
USCA Case #24-1119
Document #2058570
Filed: 06/07/2024
Page 89 of 204
399a
USCA Case #24-1119
Document #2058570
Filed: 06/07/2024
Page 90 of 204
Mercury Emissions: Lignite Coals
6.3 Role of Flue Gas SO3
EPA equates PRB and lignite coal in terms of constituents that affect Hg capture by carbon
sorbent. Data from North Dakota and Gulf Coast mines, displayed in the previous Figures 6-1 to
6-7, show these fuels also contain higher sulfur content than PRB - by a factor or two or more.
This relationship is verified by data acquired from EIA Form 960, as provided by power station
owners. These fuel data, combined with inherent alkalinity, identifies the problematic role of
flue gas SO3 content.
6.3.1 EIA Hg-Sulfur Relationship
Figure 6-8 compares the seam-by
by-seam Hg and sulfur content from various power stations firing
lignite coals, representing approximately 60 lignite mines and 40 PRB mines. Figure 6-8 shows,
even excluding the outlier values of Hg (approximating 50 lbs/TBtu), lignite presents
significantly
ly greater variability in Hg and sulfur than PRB. Moreover, lignite coals have a much
higher sulfur content than PRB and in many instances have twice the Hg content. The higher
sulfur content of lignite equates to greater production rates of sulfur SO 3.
60
Lignite
Subbituminous
Fuel Mercury Content (lbs/TBtu)
50
40
30
20
10
0
0
0.1
0.2
0.3
0.4
0.5
0.6
Fuel Sulfur Content (%)
0.7
0.8
0.9
1
Figure 6-8. Lignite Hg and Sulfur Content Variability: 2021 EIA Submission
An additional factor is the amount of “inherent” alkalinity compared to sulfur – with higher
value surpassing the SO3 content in flue gas. As introduced previously, one metric of this feature
is the ratio of Na and Ca to sulfur – on a mole basis.
(Page 216 of Total)
30
400a
USCA Case #24-1119
Document #2058570
Filed: 06/07/2024
Page 91 of 204
Mercury Emissions: Lignite Coals
Figures 6-3 and 6-7 show North Dakota and Gulf Coast lignite present a similar ratio of
alkalinity to sulfur content as does PRB – approximating a value of 2. By this metric, lignite
fuels in Figure 6-3 present similar means to “buffer” SO 3 as PRB. Notably, Texas lignite in
Figure 6-7 is disadvantaged in this metric as the alkalinity to sulfur ratio is half that of PRB –
reducing the buffering” effect of inherent ash.
Consequently, the higher sulfur content of lignite combined with equal or lower total alkali
relative to sulfur allows measurable levels of SO 3 in lignite-generated flue gas, as evidenced by
field measurements. EPA does not recognize this distinguishing difference, and states the
following regarding lignite and subbituminous coal: 30
As mentioned earlier, EGUs firing subbituminous coal in 2021 emitted Hg at an average annual
rate of 0.6 lb Hg/TBtu with measured values as low as 0.1 lb/TBtu. Clearly EGUs firing
subbituminous coal have found control options to demonstrate compliance with the 1.2 lb/TBtu
emission standard despite the challenges presented by the low natural halogen content of the
coal and production of difficult-to-control elemental Hg vapor in the flue gas stream.
This passage contains two major flaws – that the effectiveness of Hg removal techniques with
PRB-generated flue gas can be replicated with lignite, and that average annual Hg emission rates
are the metric for comparison. EPA fails to recognize that Hg removal in PRB is in the presence
of very little (essentially unmeasurable) SO3, and 30-day rolling averages exhibit variability not
captured by the annual average.
6.3.2 SO3: Inhibitor to Hg Removal
The ability of SO3 to interfere with sorbent Hg removal is well-known. 31 Most notably, EPA’s
contractor for the technology assessments used in the IPM 32 – Sargent & Lundy –for EPA issued
assessment on Hg control technology. This document states33
With flue gas SO3 concentrations greater than 5 - 7 ppmv, the sorbent feed rate may be
increased significantly to meet a high Hg removal and 90% or greater mercury removal may not
be feasible in some cases. Based on commercial testing, capacity of activated carbon can be cut
by as much as one half with an SO3 increase from just 5 ppmv to 10 ppmv.
This passage from the S&L technology assessment – funded by EPA to support the IPM model describes that Hg absorption capacity of carbon can be cut in half by an increase in SO 3 from 5
to 10 ppm. In addition, the presence of SO3 asserts a secondary role in terms of gas temperature
– units with measurable SO3 are designed with higher gas temperature at the air heater exit –
typically where sorbent is injected – to avoid corrosion. Special-purpose tests on a fabric filter
30
Tech Memo page 21
Sjostrom 2019. See graphics 21-25
32
Documentation for EPA’s Power Sector Modeling Platform v6: Using the Integrated Planning Model,
May 2018.
33
IPM Model – Updates to Cost and Performance for APC Technologies: Mercury Control Cost
Development Methodology, Prepared by Sargent & Lundy, Project 12847-002, March 2013.
31
(Page 217 of Total)
31
401a
USCA Case #24-1119
Document #2058570
Filed: 06/07/2024
Page 92 of 204
Mercury Emissions: Lignite Coals
pilot plant showed an increase in gas temperature from 310ºF to 340ºF lowered sorbent Hg
removal from 81% to 68%.34 Th
The role of SO3 is not considered in assumed carbon injection rates
for EPA’s economic analysis in Tables 12 and 13 of the Tech Memo.
Publicly available field test data demonstrate the role of SO3 on carbon sorbent effectiveness.
Figure 6-9 presents results from a lignite-fired plant describing Hg removal across the ESP with
sorbent injection.35 This 900 MW unit is reported to fire a higher sulfur lignite in which more
than 20 ppm of SO3 in flue gas is observed preceding the air heater, subsequently decreasing to
10 ppm SO3 existing the air heater.
Figure 6-9. Sorbent Hg Removal in ESP in Lignite-Fired Unit: Effect of Injection Location
Data in Figure 6-9 show the role of SO3 in compromising sorbent performance - highest Hg
removal is attained with lower SO3 (downstream APH) with 60-68% Hg removal achieved (at an
injection rate corresponding to 0.6 lbs/MACF).
Attaining a total system 92% Hg removal – the target as described by EPA – is likely not
achievable given the trajectory of the curves as shown in Figure 6-9.
6.4 EPA Cost Calculations Ignore FGD
EPA ignores the major role of wet or dry FGD in removing Hg – a fundamental flaw in their
analysis. EPA’s premise that sorbent addition is the sole compliance technology is incorrect – 18
of 22 units in the lignite fleet listed in Table 9 of the RTR Tech Memo are equipped with FGD.
34
Sjostrom 2016. See graphic 16.
Satterfield, J., Optimizing ACI Usage to Reduce Costs, Increase Fly Ash Quality, and Avoid Corrosion,
presentation to the Powerplant Pollutant and Effluent Control Mega Symposium, August, 2018.
35
(Page 218 of Total)
32
402a
USCA Case #24-1119
Document #2058570
Filed: 06/07/2024
Page 93 of 204
Mercury Emissions: Lignite Coals
Of these 18 units, 4 are equipped with dry FGD and 14 with wet FGD. This process equipment
asserts a major role in Hg removal as discussed in the next section.
The calculation of cost-effectiveness for the model plant as presented in Section (e)(i) of the
RTR Tech memo addresses only sorbent addition, thus does not reflect the Hg compliance
strategy of 18 units in the lignite fleet. EPA assumes (a) upgrade of sorbent from “conventional”
activated carbon to the halogenated form, and (b) increasing sorbent injection from 2.5 to 5.0
lbs/MAFH elevates Hg reduction from 73% to 92%.36 This assumption is not relevant – at least
in this specific form – to 18 of 22 units in the lignite fleet, as wet or dry FGD will contribute to
Hg removal. EPA’s approach could underestimate the cost per ton incurred, as tons of Hg
removed by the FGD could be credited to sorbent injection (the denominator of the $/ton
calculation is larger than it should be).
The variable of FGD Hg removal cannot be ignored, and undermines the legitimacy of the cost
estimates as Hg removed by FGD cannot be ascribed to sorbent injection. Thus, depending on
how or if the sorbent injection rate changes, costs could increase beyond EPA’s estimate (as the
denominator in the $/ton calculation is reduced.
6.5
Conclusions
•
EPA’s proposal that Hg emissions of 1.2 lbs/TBtu can be attained for lignite-fired units
by increasing sorbent injection rate and adding halogens (to compensate for loss of
refined coal) is incorrect, as it assumes sorbent injection Hg removal observed with PRB
is achievable on lignite.
•
Flue gas generated from lignite exhibits measurable SO3 in quantities that– as
summarized by EPA’s contractor for IPM model inputs - reduce the effectiveness of
sorbent by 50% and in some cases presents a barrier to 90% Hg removal.
•
Accounting for the variability of Hg content in lignite for most North Dakota and Texas
lignite fuels, more than 90% Hg removal is required to meet 1.2 lbs/MBtu, exceeding the
nominally 80% removal estimated by EPA, and over a 30-day rolling average basis is
unlikely to be attained.
•
EPA’s calculation of cost–effectiveness for lignite fuels ignores the role of FGD, present
in 18 of the 22 reference stations, in removing Hg. The result of this erroneous
assumption could be an under-estimation of the cost for additional Hg removal.
36
EPA uses the incorrect constant in the calculation of gas flow rate to translate sorbent injection from a
mass per time basis (lb//hr) to mass per unit volume of gas (lbs/MACF). The calculation on page 24 uses
the value of 9,860 scf/MBtu to quantify flue gas generated from lignite coal. Per EPA-454/R-95-015
(Procedure for Preparing Emission Factor Documents, OAQPS, November 1997) this value reflects the
dry volume of gas produced from lignite coal, per MBtu. The flue gas rate that is processed by the
environmental controls is the authentic “wet” basis and about 20% higher per MBtu (12,000 scf/MBtu).
Use of the correct, latter constant lowers the value of sorbent per MACF by the same magnitude.
(Page 219 of Total)
33
403a
USCA Case #24-1119
Document #2058570
Filed: 06/07/2024
Page 94 of 204
Mercury Emissions: Non-Low Rank Coals
7. Mercury Emissions: Non-Low Rank Fuels
Section 7 addresses EPA’s proposal to retain the present Hg limit of 1.2 lbs/TBtu for units firing
bituminous and subbituminous coals.
EPA recognizes that Hg emission rates - as determined on an annual average basis - have
decreased significantly since the initial MATS rule was issued, with bituminous–fired units
averaging 0.4 lbs/TBtu (and ranging between 0.2 and 1.2 lbs/TBtu) and subbituminous-fired
units averaging 0.6 lbs/TBtu (ranging between 0.1 to 1.2 lbs/TBtu).37 EPA states these Hg
emission rates represent between a 77 and 98% Hg removal from an assumed Hg inlet value of
5.5 lbs/TBtu. EPA notes they did not acquire detailed information on compliance steps such as
the type of sorbent injected, the rate of sorbent injection, and the role of SCR NOx control and
wet FGD and the myriad factors that determine Hg removal “co-benefits.”
This section addresses the reported Hg removal and basis for EPA’s position.
7.1 Hg Removal
EPA’s discussion of the annual average of Hg removal does not consider the 30-day rolling
average, the more challenging metric to attain – and the metric mandated for compliance. The
30-day rolling average reflects variability in Hg coal content and process conditions, both of
which can experience daily or hourly changes, which obviously is not captured in annual
averages.
Figures 7-1 and 7-2 report two metrics of Hg emission rate variability. 38 Figure 7-1 presents the
mean and standard deviation of Hg annual average emissions for eleven categories of control
technology and fuel rank. For six of these eleven categories, the sum of the mean and the
standard deviation approach the Hg limit of 1.2 lbs/TBtu.
Figure 7-2 describes for six categories of control technology and 2 or 3 fuel ranks (depending on
the technology) the number of units that for at least one operating day exceed 1.2 lbs/TBtu on a
30-day rolling average. Figure 7-2 shows for all categories of control technology and fuel rank
experience 10% to 20% of units exceed this 30-day average.
In summary, EPA’s report of annual Hg emission rate - significantly reduced compared from
2012 – does not provide a basis for further reductions as annual data does not account for
variability.
37
Prepublication Version, page 85
Cichanowicz, J. E. et. al., Mercury Emissions Rate: The Evolution of Control Technology
Effectiveness, Presented at the Power Plant Pollutant and Effluent Control MEGA Symposium: Best
Practices and Trends, August 20-23, 2018, Baltimore, MD.
38
(Page 220 of Total)
34
404a
USCA Case #24-1119
Document #2058570
Filed: 06/07/2024
Page 95 of 204
Mercury Emissions: Non-Low Rank Coals
1.40
Mean
Standard Deviation
Hg Emission Rate (lbs/TBtu)
1.20
1.00
0.80
0.60
0.40
0.20
0.00
Figure 7-1. Mean, Standard Deviation of Annual Hg Emissions: 2018
18
N=151
Bituminous
Units with >= 1 30-Day
30
Variance
16
14
Subbituminous
Lignite
N=76
12
N=63
10
N=28
8
N=31
N=35
6
4
N=41
N=33
N=6
2
N=2
N=0
N=12
N=10
N=6
N=3
N=5
N=0
N=3
0
ESP Only
FF Only
Dry FGD
Dry FGD /
SCR
Wet FGD
Wet FGD /
SCR
Figure 7-2. Mean, Standard Deviation of Annual Hg Emissions: 2018
(Page 221 of Total)
35
405a
USCA Case #24-1119
Document #2058570
Filed: 06/07/2024
Page 96 of 204
Mercury Emissions: Non-Low Rank Coals
7.2 Role of Fuel Composition and Process Conditions
Hg emissions are defined by variability in coal composition and process conditions, the latter
including sorbent type, and injection rate, and the “co-benefit” Hg removal imparted by SCR
NOx control and wet or dry FGD.
Although EPA did not elicit detailed process information from owners via Section 114, several
key insights are presented in a 2018 survey conducted by ADA.39
7.2.1 Coal Variability
EPA cites observing for Hg emissions “a control range of 98 to 77 percent (assuming an average
inlet concentration of 5.5 lb/TBtu).”40 It is not clear if EPA assigns the average Hg content value
of 5.5 lbs/TBtu to both bituminous and subbituminous coal, or solely the latter.
Figure 7-3 shows an average value of 5.5 lbs/TBtu does not represent either coal rank well.
Figure 7-3 presents – on an annual average basis – data from more than 70 units reporting Hg
content to the EIA. Numerous units report up to 10 lbs/TBtu - almost twice the average value
EPA assigns, with 10 additional units reporting Hg content exceeding 10 lbs/TBtu. Northern
Appalachian bituminous coals appear to contain higher Hg content than coals from other regions.
Figure 7-3. Annual Average of Fuel Hg, Sulfur Content in Coal
39
40
Sjostrom, S. et. al., Mercury Control in the U.S.: 2018 Year in Review
RTR Tech Memo, page 19.
(Page 222 of Total)
36
406a
USCA Case #24-1119
Document #2058570
Filed: 06/07/2024
Page 97 of 204
Mercury Emissions: Non-Low Rank Coals
Consequently, EPA’s calculation of 98 to 77% Hg removal is likely inaccurate as the assumed
coal Hg content is too low.
7.2.2 Process Conditions
The process conditions for Hg removal: sorbent composition, sorbent injection rate, and the “cobenefits” of SCR NOx control and wet FGD are highly variable, due to a combination of factors.
The following provides several examples.
Refined Coal. The absence of Refined Coal – no longer a viable option - complicates projecting
future Hg emissions. A survey of Hg compliance activities for 2018 reported Refined Coal as a
compliance step;41 EIA fuel records show this trend persisted through 2021. EPA’s assumption
that adding halogens to the fuel or flue gas compensates for the unavailability of Refined Coal is
speculative and without basis. Without assurances of the benefits from the halogen content of
Refined Coal, it is not possible to assess the viability of lowering Hg emissions.
Sorbent Injection. Sorbent injection is a key compliance step for 70% of subbituminous-fired
units, for some augmented with coal additives and Refined Coal. For bituminous-fired units,
18% of coal use is treated by some combination of sorbent injection and coal additives.
As described by EPA, increasing the rate of sorbent injection increases Hg removal – but with
diminishing returns as sorbent mass is added. An example of this relationship is provided by fullscale tests at Ameren’s PRB-fired Labadie Unit 3. These tests explored the effectiveness of both
conventional and brominated activated carbon. These tests, purposely conducted in PRBgenerated flue gas to define sorbent performance in the absence of SO 3, show Hg removal of
90% or more is feasible and that halogen addition can lower sorbent rate. 42
This relationship is complicated by the role of Refined Coal, coal additives, and (as described
below) the contribution of “co-benefits”. Devising a reasoned prediction of Hg removal under
variable conditions, including coal composition and the impact of changing sorbents is not
possible with current available information.
SCR, FGD Co-Benefits. The capture of Hg by wet FGD – in many cases prompted by the role
of SCR catalysts to oxidize elemental Hg – can be a primary mean for Hg capture. However,
such co-benefits are highly variable, and depend on the ratio of elemental to oxidized Hg in the
flue gas, and the consequential Hg “re-emission” by a wet FGD. There are means to remedy this
variability in some instances, but broad success cannot be assured. Without the specifics of FGD
design and operation, Hg removal via wet FGD cannot be predicted.
41
Sjostrom, S. et. al., Mercury Control in the U.S.: 2018 Year in Review. Hereafter Sjostrom 2019.
Senior, C. et. al., Reducing Operating Costs and Risks of Hg Control with Fuel Additives, Presentation
to the Power Plant Pollutant Control and Carbon Management Mega Symposium, August 16-18, 2016.
42
(Page 223 of Total)
37
407a
USCA Case #24-1119
Document #2058570
Filed: 06/07/2024
Page 98 of 204
Mercury Emissions: Non-Low Rank Coals
Hg Re-Emission. The fate of Hg entering a wet FGD is uncertain. 43 If in the oxidized state, Hg
upon entering the FGD solution can (a) remain in solution and be discharged with the FGDcleansing step of “blowdown” (b) precipitate as a solid and be removed with the byproduct
(typically gypsum), or (c) be reduced from the oxidized to the elemental state, thus re-emitted in
the flue gas. Several means to minimize Hg re-emission exist, including injection of sulfite and
controlling the scrubber liquor oxidation/reduction potential (ORP). These means can limit Hg
remission but are additional process steps that are superimposed upon the task of achieving high
efficiency SO2 removal. The extent these means can be universally applied without
compromising SO2 removal is uncertain.
Role of Variability Due to Load Changes. An in-plant study showed that increasing load for a
wet FGD-equipped unit can elevate Hg re-emission, eventually exceeding 1.2 lbs/TBtu. 44 This
observation can be due to loss of the control over the ORP, defined in the previous paragraph as
a key factor in FGD Hg removal. Chemical additives can adjust ORP but complete and
autonomous control may not be available. For example, in a systematic evaluation of FGD
operating variables conducted at a commercial power station, factors such as limestone
composition and the extent to which units must operate in zero-water discharge – as perhaps
mandated by the pending Effluent Limitation Guideline – can affect ORP and thus Hg-reemission.45
Upsets in wet FGD process conditions can prompt Hg re-emission. Specifically, one observer
noted two units that “….experienced a scrubber reemission event causing the mercury stack
emissions to increase dramatically above the MATS limit and significantly higher than the
incoming mercury in the coal and the event lasting for several days.” 46 This high Hg event was
eventually remedied over the short-term operation, but long-term performance is not available.
7.3 Conclusions: Mercury Emissions - Non-Low Rank Coals
There is inadequate basis to further lower the Hg emissions rate below the present limit of 1.2
lbs/TBtu, as variability in fuel and process operations outside the control of the operator can
elevate emissions to approach or in some cases exceed that rate.
43
Gadgil, M., 20 Years of Mercury Re-emission – What do we Know?, Presentation to the Power Plant
Pollutant Control and Carbon Management Mega Symposium, August 16-18, 2016.
44
Blythe, G. et. al., Maximizing Co-Benefit Mercury Capture for MATS Compliance on Multiple CoalFired Units, Presentation to the Power Plant Pollutant Control and Carbon Management Conference Mega
Symposium, August 16-18, 2016.
45
Blyte, G. et. al., Investigation of Toxics Control by Wet FGD Systems, Presentation to the Power Plant
Pollutant Control and Carbon Management Conference Mega Symposium, August 16-18, 2016.
46
Pavlisch, J. et. al., Managing Mercury Reemission and Managing MATS compliance Using a sorbent
Approach, Presentation to the Power Plant Pollutant Control and Carbon Management Conference Mega
Symposium, August 16-18, 2016.
(Page 224 of Total)
38
408a
USCA Case #24-1119
Document #2058570
Filed: 06/07/2024
Page 99 of 204
EPA IPM Results: Evaluation and Critique
8.
EPA IPM RESULTS: EVALUATION AND CRITIQUE
EPA used the Integrated Planning Model (IPM) to establish a Baseline Scenario from which to
measure compliance impacts of the proposed rule. This Baseline Scenario is premised upon
IPM’s Post-IRA 2022 Reference Case. In this Post-IRA simulation, IPM evaluated a number of
tax credit provisions of the Inflation Reduction Act of 2022 (IRA), which address application of
Carbon Capture and Storage (CCS) and other means to mitigate carbon dioxide (CO 2). These are
the (i) New Clean Electricity Production Tax Credit (45Y); (ii) New Clean Electricity Investment
Credit (48E); Manufacturing Production Credit (45X); CCS Credit (45Q); Nuclear Production
Credit (45U); and Production of Clean Hydrogen (45V). Also, the Post-IRA 2022 Reference
Case includes compliance with the proposed Good Neighbor Policy (Transport Rule). 47
A critique of EPA’s methodology and findings is described subsequently.
8.1 IPM 2030 Post-IRA 2022 Reference Case: A Flawed Baseline
The IPM Post-IRA 2022 Reference Case for the years 2028 and 2030 comprises a flawed
baseline to measure compliance impacts of the proposed rule. This flawed baseline centers
around IPM projected coal retirements in both 2028 and 2030 as well as units projected to deploy
CCS in 2030. Specifically, IPM has erroneously retired numerous coal units expected to operate
beyond 2028 and 2030 based upon current announced retirement plans; consequently, these units
are subject to the proposed rule beginning in 2028. There are numerous challenges and
limitations to deploying CCS as EPA has projected on 27 coal units in 2030. These units would
also be subject to the proposed. Consequently, IPM’s compliance impacts of the proposed rule is
likely understated.
8.1.1 Analytical Approach
This analysis identifies those units IPM modeled as coal retirements, CCS retrofits and coal to
gas (C2G) conversions in both 2028 and 2030, and compares them to announced plans for unit
retirements, technology retrofits and C2G conversions. To identify errors for 2028, the parsed
file for the 2028 Post-IRA 2022 Reference Case was used. Since EPA did not provide a parsed
47
In addition to the IRA and GNP, the Post-IRA 2022 Reference Case takes into account compliance
with the following: (i) Revised Cross-State Air Pollution Rule (CSAPR) Update Rule; (ii) Standards of
Performance for Greenhouse Gas Emissions from New, Modified and Reconstructed Stationary Sources:
Electric Utility Generating Units; (iii) MATS Rule which was finalized in 2011; (iv) Various current and
existing state regulations; (v) Current and existing RPS and Current Energy Standards; (vi) Regional
Haze Regulations and Guidelines for Best Available Retrofit Technology (BART); and, (vii) Platform
reflects California AB 32 and RGGI. Three non-air federal rules affecting EGUs: (i) Cooling Water
Intakes (316(b) Rule; (ii) Coal Combustion Residuals (CCR), which reflects EPA’s July 29, 2020 position
on retrofitting or closure of surface impoundments; and, (iii) Effluent Limitation Guidelines, which
includes the 2020 Steam Electric Reconsideration Rule (cost adders were applied starting in 2025).
(Page 225 of Total)
39
409a
USCA Case #24-1119
Document #2058570
Filed: 06/07/2024
Page 100 of 204
EPA IPM Results: Evaluation and Critique
file of the 2030 Post-IRA 2022 Reference Case, an abbreviated parsed file was created using four
different IPM files. These are: (i) 2028 parsed file of the Post-IRA 2022 Reference Case; (ii)
Post-IRA 2022 Reference Case RPE File for the year 2030; (iii) Post-IRA 2022 Reference Case
RPT Capacity Retrofits File for the year 2030; and, (iv) National Electrical Energy Data System
(NEEDS) file for the Post-IRA 2022 Reference Case. These parsed files allow identifying IPM
modeled retirements in 2028 and 2030, CCS retrofits in 2030 and C2G in both 2028 and 2030.
These modeled retirements and conversions were compared to announced information in the
James Marchetti Inc ZEEMS Data Base.
8.1.2 Coal Retirements
The 2028 IPM modeling run retired 112 coal units (53.6 GW) from 2023 to 2028. In the 2030
analysis, IPM retired an additional 52 coal units (25.5 GW). The total number of retirements for
the two modeling run years is 164 coal units (79.1 GW).
Table 8-1 summarizes the IPM retirement errors in the 2028 and 2030 modeling runs.
Specifically, IPM incorrectly retired 29 coal units (14.0 GW) by 2028 and an additional 23 coal
units (14.1 GW) in 2030. In addition, there are 3 coal units (1.6 GW) that EPA listed in the
NEEDS file as being retired before 2028 that will operate beyond 2030. In total, there are 55
coal units that IPM erroneously retired in the 2028 and 2030 modeling runs that will be operating
and subject to some aspect of the proposed rule beginning in 2028.
Table 8-1. Coal Retirement Errors
Year
2028
2030
2030
Total
Description
Retiring after 2028
Retiring after 2030
NEEDS retirements that should be in the 2030 modeling
platform
Number
29
23
3
55
Tables 8-2 to 8-6 lists each of the coal units IPM has incorrectly retired, incorrectly deployed
CCS, or switched to natural gas.
(Page 226 of Total)
40
410a
No.
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
RegionName
WECC_Arizona
SPP West
MISO_Arkansas
MISO_Arkansas
SERC_Central_TVA
SERC_Central_TVA
SERC_Central_TVA
SERC_Central_TVA
SERC_Central_TVA
SERC_Central_TVA
SERC_Central_TVA
MISO_Minn/Wisconsin
MISO_Missouri
MISO_Missouri
MISO_Missouri
MISO_Missouri
MISO_Missouri
MISO_Missouri
SERC_VACAR
SERC_VACAR
ERCOT_Rest
ERCOT_Rest
WECC_Utah
WECC_Utah
PJM_Dominion
PJM_Dominion
PJM_AP
PJM_AP
WECC_Wyoming
StateName
Arizona
Arkansas
Arkansas
Arkansas
Kentucky
Kentucky
Kentucky
Kentucky
Kentucky
Kentucky
Kentucky
Minnesota
Missouri
Missouri
Missouri
Missouri
Missouri
Missouri
North Carolina
North Carolina
Texas
Texas
Utah
Utah
Virginia
Virginia
West Virginia
West Virginia
Wyoming
ORISCode
6177
6138
6641
6641
1379
1379
1379
1379
1379
1379
1379
6090
2103
2103
2103
2103
2107
2107
2712
2712
298
298
7790
8069
7213
7213
3943
3943
6101
UnitID
U1B
1
1
2
2
3
5
6
7
8
9
3
1
2
3
4
1
2
3A.3B
4A, 4B
LIM1
LIM2
1-1
2
1
2
1
2
BW91
PlantName
Coronado
Flint Creek
Independence
Independence
Shawnee
Shawnee
Shawnee
Shawnee
Shawnee
Shawnee
Shawnee
Sherburne County
Labadie
Labadie
Labadie
Labadie
Sioux
Sioux
Roxboro
Roxboro
Limestone
Limestone
Bonanza
Huntington
Clover
Clover
Fort Martin
Fort Martin
Wyodak
Capacity
380
528
809
842
134
134
134
134
134
134
134
876
593
593
593
593
487
487
694
698
831
858
458
450
440
437
552
546
332
(Page 227 of Total)
41
Document #2058570
EIA 860 has retirement December 2029
EIA 860 has retirement December 2029
Unit is planned to retire in 2030,
Retire in 2032 - 2023 IRP (3/31/23)
Dominion 2023 IRP - Retirement Date 2040 (5/1/23)
Dominion 2023 IRP - Retirement Date 2040 (5/1/23)
EPA Settlement on wastewater upgrades (8/9/22). 2020 IRP through 2035
EPA Settlement on wastewater upgrades (8/9/22). 2020 IRP through 2036
Retire in 2039 - IRP (3/31/23)
2022 Carbon Reduction Plan per PSC retirement Jan. 1, 2028-34 (12/30/22).
2023 Carbon Reduction Plan per PSC retirement Jan. 1, 2028-34 (12/30/22).
Observation
To be retired by 2032 and continued seasonal curtailemts,
Retire January 1, 2039 - Entergy LL 2023 IRP (March 31, 2023).
Agreement with Sierra Club and NPCA to cease coal by Dec 31, 2030.
Agreement with Sierra Club and NPCA to cease coal by Dec 31, 2030.
TVA planning assumption retirement (5/21) - December 31, 2033
TVA planning assumption retirement (5/21) - December 31, 2033
TVA planning assumption retirement (5/21) - December 31, 2033
TVA planning assumption retirement (5/21) - December 31, 2033
TVA planning assumption retirement (5/21) - December 31, 2033
TVA planning assumption retirement (5/21) - December 31, 2033
TVA planning assumption retirement (5/21) - December 31, 2033
PSC approved closure (2/8/22). Upper Midwest Resource Plan (6/25/21) for 2030.
2022 IRP Update retire in 2042 (6/24/22).
2022 IRP Update retire in 2042 (6/24/22).
2022 IRP Update (6/24/22) retirement in 2036
2022 IRP Update (6/24/22) retirement in 2036
2022 IRP Update (6/24/22) - To be retired in 2030
2022 IRP Update (6/24/22) - To be retired in 2030
Table 8-2. IPM Coal Retirement Errors: 2028 Post-IRA 2022 Reference Case Run
EPA IPM Results: Evaluation and Critique
USCA Case #24-1119
Filed: 06/07/2024
Page 101 of 204
411a
(Page 228 of Total)
RegionName
1 WECC_Arizona
2 FRCC
3 FRCC
4 SERC_Southeastern
5 SERC_Southeastern
6 PJM West
7 MISO_Iowa
8 SPP North
9 SPP North
10 SERC_Central_Kentucky
11 SERC_Central_Kentucky
12 SERC_Central_Kentucky
13 SPP North
14 SPP North
15 SERC_VACAR
16 SERC_VACAR
17 SERC_VACAR
18 SERC_VACAR
19 MISO_MT, SD, ND
20 SERC_VACAR
21 SERC_VACAR
22 SERC_VACAR
23 SERC_VACAR
24 PJM West
25 PJM West
26 PJM_AP
27 PJM_AP
StateName
Arizona
Florida
Florida
Georgia
Georgia
Indiana
Iowa
Kansas
Kansas
Kentucky
Kentucky
Kentucky
Missouri
Missouri
North Carolina
North Carolina
North Carolina
North Carolina
North Dakota
South Carolina
South Carolina
South Carolina
South Carolina
West Virginia
West Virginia
West Virginia
West Virginia
ORISCode
6177
628
628
6257
6257
1040
1167
6068
1241
1356
1356
1356
6065
6195
8042
8042
2727
2727
8222
6249
6249
6249
6249
3935
3935
3954
3954
UnitID
U2B
4
5
1
2
1
9
1
2
1
3
4
1
1
1
2
3
4
B1
1
2
3
4
1
2
1
2
Region Name
1 SPP_N
2 MIS_LA
3 WECC_WY
State Name
Kansas
Louisiana
Wyoming
ORIS
Plant
1241
6190
4158
Unit ID
1
3-1, 3-2
BW44
Plant Name
La Cygne
Brame Energy Center
Dave Johnston
Capacit
y (MW)
736
626
330
NEEDS
Retirement
2025
2027
2027
Year
Retire in 2039 - 2023 IRP (3/31/23).
Observations
2022 IRP Update to be retired in 2032
No plans to retire. Evaluating CCS
42
Capacity Observations
382
To be retired by 2032 and contined seasonal curtailments
To be retired in 2034 (2020 Sustainability Report)
712
710
To be retired in 2034 (2020 Sustainability Report)
860
ELG Compliance - Wastewater Treatment - No Announced Retirement
860
ELG Compliance - Wastewater Treatment - No Announced Retirement
Biased to peak load duty. 2020 IRP Base Case has retirement May 31, 2034
35
163
ELG compliance options for FGDW and BATW, possible 2028 retirement
To be retired at the end of 2039 (2021 IRP)
728
662
To be retired at the end of 2039 (2021 IRP)
474
To be retired 2034
485
To be retired 2037.
465
To be retired 2037.
700
To be retired at the end of 2039 (2021 IRP)
184
Beyond 2030 retirement date - new 2022 IRP
1110
1/1/2036 retirement per 2022 Carbon Reduction Plan
1110
1/1/2036 retirement per 2022 Carbon Reduction Plan
658
2022 Carbon Reduction Plan accepted by PSC retirement Jan. 1, 2033 (12/30/22)
660
2022 Carbon Reduction Plan accepted by PSC retirement Jan. 1, 2033 (12/30/22)
429
Active perl reliablity concerns in MISO. End of depreciable life - 2041
275
2023 IRP: operate unit through 2030 for reliability (4/19/23)
285
2024 IRP: operate unit through 2030 for reliability (4/19/23)
285
2025 IRP: operate unit through 2030 for reliability (4/19/23)
285
2026 IRP: operate unit through 2030 for reliability (4/19/23)
800
Approved ELG upgrades to keep plant open until 2040.
800
Approved ELG upgrades to keep plant open until 2040.
554
Dominion 2023 IRP - Retirement Date 2044 (5/1/23)
555
Dominion 2023 IRP - Retirement Date 2044 (5/1/23)
Filed: 06/07/2024
No.
PlantName
Coronado
Crystal River
Crystal River
Scherer
Scherer
Whitewater Valley
Muscatine Plant #1
Jeffrey Energy Center
La Cygne
Ghent
Ghent
Ghent
Iatan
John Twitty
Belews Creek
Belews Creek
Marshall (NC)
Marshall (NC)
Coyote
Winyah
Winyah
Winyah
Winyah
John E Amos
John E Amos
Mt Storm
Mt Storm
Document #2058570
Table 8-4 Units in the NEEDS to Be Operating in 2028
No.
Table 8-3. IPM Coal Retirement Errors: 2030 Post IRA 2022 Reference Case Modeling Run
EPA IPM Results: Evaluation and Critique
USCA Case #24-1119
Page 102 of 204
412a
(Page 229 of Total)
Region Name
1 ERCOT_Rest
2 ERCOT_Rest
3 ERCOT_Rest
4 ERCOT_Rest
5 ERCOT_Rest
6 FRCC
7 MISO_Indiana
8 PJM West
9 PJM West
10 PJM West
11 SERC_Southeastern
12 SPP_WAUE
13 SPP_WAUE
14 SPP_WAUE
15 WECC_Arizona
16 WECC_Arizona
17 WECC_Colorado
18 WECC_Colorado
19 WECC_Utah
20 WECC_Utah
21 WECC_Utah
22 WECC_Utah
23 WECC_Wyoming
24 WECC_Wyoming
25 WECC_Wyoming
26 WECC_Wyoming
27 WECC_Wyoming
StateName
Texas
Texas
Texas
Texas
Texas
Florida
Indiana
Kentucky
West Virginia
West Virginia
Alabama
North Dakota
North Dakota
North Dakota
Arizona
Arizona
Colorado
Colorado
Utah
Utah
Utah
Utah
Wyoming
Wyoming
Wyoming
Wyoming
Wyoming
ORISCode
6179
7097
6180
6180
6183
645
6113
6018
3948
3948
6002
6469
6469
2817
8223
8223
470
6021
6165
6165
6165
8069
8066
8066
6204
6204
6204
UnitID
3
BLR2
1
2
SM-1
BB04
1
2
1
2
4
B1
B2
2
3
4
3
C3
1
2
3
1
BW73
BW74
1
2
3
Laramie River Station
Laramie River Station
Comanche (CO)
Craig (CO)
Hunter
Hunter
Hunter
Huntington
Jim Bridger
Jim Bridger
Laramie River Station
Springerville
Springerville
East Bend
Mitchell (WV)
Mitchell (WV)
James H Miller Jr
Antelope Valley
Antelope Valley
Leland Olds
Gibson
PlantName
Fayette Power Project
J K Spruce
Oak Grove (TX)
Oak Grove (TX)
San Miguel
Big Bend
RegionName
StateName ORISCode
SPP West (Oklahoma, Arkansas
Arkansas, Louisiana)
56564
PJM West
Kentucky 6041
ERCOT_Rest
Texas
56611
UnitID
1
2
S01
PlantName
John W Turk Jr Power Plant
H L Spurlock
Sandy Creek Energy Station
Year
2030
2028
2030
Capacity Observations
609 Retire Jan 1, 2068 - SWEPCO 2023 IRP (March 29, 2023)
510 No announced C2G or co-firing
933 No announced conversion
Convert to natural gas in 2030 - 2023 IRP (3/31/23)
Convert to natural gas in 2030 - 2023 IRP (3/31/23)
Retire in 2032 - 2023 IRP (3/31/23).
Retire in 2032 - 2023 IRP (3/31/23).
Retire in 2032 - 2023 IRP (3/31/23).
To be retired Dec 31 2030 (10/31/22)
To be retired Dec 2029 - Electric Resource Plan (12/1/20)
Retire in 2031- 2023 IRP (3/31/23)
Board voted to convert to natural gas by 2027 (1/23/23)
Observations
43
Filed: 06/07/2024
No.
1
2
3
Capacity
286.05
537.93
572.77
570.97
237.74
292.27
594.24
399.00
537.77
537.77
477.05
289.22
288.38
279.16
281.05
281.05
501.15
305.66
319.80
292.44
314.06
311.54
354.02
349.78
385.22
382.92
383.45
Document #2058570
Table 8-6 Units IPM Erroneously Predicts Switch to Natural Gas
No.
Table 8-5 Units IPM Predicts CCS By 2030
EPA IPM Results: Evaluation and Critique
USCA Case #24-1119
Page 103 of 204
413a
USCA Case #24-1119
Document #2058570
Filed: 06/07/2024
Page 104 of 204
EPA IPM Results: Evaluation and Critique
8.1.3 Coal CCS
Table 8-5 identifies the 27 units IPM projected to retrofit CCS by 2030; none of these have been
involved in any Front-End Engineering and Design (FEED) Studies. However, 9 of the units
identified by IPM will be either be retired or converted to natural gas in and around 2030. There
are major questions addressing infrastructure and project implementation that present challenges
to IPM’s CCS projection for 2030. Indeed, it is next to impossible for these units to be in
position to retrofit CCS by 2030.
8.1.4 Coal to Gas Conversions (C2G)
The 2028 IPM modeling run converted 36 coal units to gas (14.3 GW). In the 2030 IPM
modeling run an additional 2 coal units (1.5 GW) were converted to gas (Turk and Sandy Creek).
As shown in Table 8.6, three of these units have no announced plans to convert to gas by 2028 or
2030 and will be subject to the proposed rule.
8.2 Summary
The major issues associated with EPA’s IPM modeling of the 2028 and 2030 Post-IRA 2022
Reference Case are summarized as follows:
•
•
•
•
The 2028 and 2030 Baseline (Post-IRA 2022 Reference Case) used to measure the
compliance impacts of proposed rule is flawed and needs to be revised
Most notably, IPM erred in retiring 55 coal units that will be subject to the proposed rule
beginning in 2028.
IPM retrofitted 27 units with CCS in 2030, 19 of which will be subject to the proposed
rule. It is next to impossible for these units to retrofit CCS by 2030.
The IPM modeled compliance impacts for the proposed rule in 2028 and 2030 is very
likely understated.
(Page 230 of Total)
44
414a
(Page 231 of Total)
Colstrip 3
Labadie 2
Labadie 1
Labadie 4
Labadie 3
Note: Colstrip costs reflect EPA's approch of retrofitting a fabric
filter, as an ESP is not installed at that site.
Colstrip 4
D B Wilson Martin Lake Mt Storm 3 Martin Lake Walter Scott Mt Storm 1,
1
3
Jr Energy
2
45
Filed: 06/07/2024
-
20
40
Appendix A
Document #2058570
60
80
100
120
140
160
Figure A-1.. Unit ESP Investment (per EPA’s Cost Assumptions):
Assumptions) PM of 0.010 lbs/MBtu
Appendix A: Additional Cost Study Data
Potential Investment for 0.010 lbs/MBtu, $M
USCA Case #24-1119
Page 105 of 204
415a
(Page 232 of Total)
ESP Typical
East Bend
General James M Gavin
Gibson
Martin Lake 2
Milton R Young
Mt Storm
Mt Storm
ESP Minor
Alcoa/Warrick
Big Bend
Coronado
Coronado
Crystal River
Crystal River
Jeffrey Energy Center
Laramie River Station
Martin Lake
San Miguel
Seminole
Labadie
Labadie
Labadie
Labadie
Martin Lake 1
ESP Major Upgrade
D B Wilson
Clover Power Project
Ghent
Gilberton Power/John B Rich
H L Spurlock
Iatan
Marion
Mt Carmel Cogen
St Nicholas Cogen Project
Walter Scott Jr Energy Center
WPS Westwood Generation LLC
FF Cleaning
Boswell Energy Center
Table A-1. Technology Assignment for 0.010 lbs/MBtu PM Rate: Industry Study
FF Retrofit
Colstrip 3, 4
46
Appendix A
USCA Case #24-1119
Document #2058570
Filed: 06/07/2024
Page 106 of 204
416a
USCA Case #24-1119
Document #2058570
Filed: 06/07/2024
Page 107 of 204
Appendix A
Table A-2 Technology Assignment for 0.006 lbs/MBtu PM Rate: Industry Study
FF O&M Enhancement
Antelope Valley
Bonanza
FF Retrofit
Alcoa/Warrick
Belews Creek
FF Retrofit
Laramie River Station
Leland Olds 1, 2
Boswell Energy Center Clay Boswell
Clover Power Project
Comanche
Ghent
Gilberton Power/John B Rich
H L Spurlock
Huntington
Iatan
Louisa
Marion
Mt Carmel Cogen
Oak Grove 1
Sandy Creek Energy Station
Scrubgrass Generating 1, 2
St Nicholas Cogen Project
Twin Oaks Power 1, 2
Walter Scott Jr Energy Center
Weston
WPS Westwood Generation LLC
Big Bend
Cardinal
Colstrip 3, 4
Coronado 1, 2
Crystal River 4, 5
D B Wilson
East Bend
General James M Gavin
Gibson 1, 3
Gibson
Independence
IPL - AES Petersburg
James H Miller Jr
Jeffrey Energy Center 1, 2, 3
Jim Bridger 3, 4
Labadie 1 -4
Martin Lake 1-3
Merrimack
Milton R Young
Monroe 1, 2
Mt Storm 1, 2
Naughton
Nebraska City
R D Green
R S Nelson
Sam Seymour Fayette 1, 2
San Miguel
Schiller
Seminole
Trimble County
Whelan Energy Center
White Bluff 1, 2
(Page 233 of Total)
47
417a
USCA Case #24-1119
Document #2058570
Filed: 06/07/2024
Page 108 of 204
Appendix B
Appendix B: Example Data Chart
Appendix A presents additional examples of units for which EPA’s PM sampling and evaluation
approach distorted results. These charts contain both mean and 99 th percentile data. Data is
presented for the following units, for which observations are offered as follows:
•
TVA Gallatin Unit 1. EPA selected 0.0030 lbs/MBtu as the reference PM rate, using Q4
of 2019. Few of the 16 quarters that report lower PM emissions.
•
TVA Gallatin Unit 2. EPA selected 0.0031 lbs/MBtu as the reference PM rate, also using
Q4 of 2019. Few of the 16 quarters that report lower PM, similar to Unit 1.
•
TVA Gallatin Unit 3. EPA selected 0.0016 lbs/MBtu as the reference PM rate, again
using Q4 of 2019. Only one quarter (Q3 of 2019) reports lower PM rate.
•
TVA Gallatin Unit 4. EPA selected 0.0022 lbs/MBtu as the reference PM rate, using Q1
of 2021. Of the 14 quarters reporting data, two quarters report PM rates equal to this rate,
while two are below this rate.
•
LG&E/KU Ghent 1. EPA selected 0.005 lbs/MBtu as the reference PM rate, using Q2 of
2019. This PM rate represents that reported in previous quarters, but with one exception
all subsequent quarters through 2021 report higher PM.
•
LG&E/KU Mill Creek Unit 4. EPA selected 0.0035 lbs/MBtu as the reference PM rate,
using Q4 of 2021. With the exception of the previous quarter, this value is the lowest of
any reported since 2017 by a significant margin.
•
Alabama Power Gaston Unit 5. EPA selected 0.005 lbs/MBtu as the reference PM rate,
using Q1 of 2021. Data for this unit is displayed from Q1 2017 through Q4 2022. Of the
24 reporting quarters (1Q 2017 through 4QW 2022) only 6 quarters have lower PM rates.
•
Alabama Power Miller Unit 1. EPA selected 0.004 lbs/MBtu as the reference PM rate,
using Q3 of 2017. Data for this unit is displayed from Q1 2017 through Q4 2022. The
designated rate represents a significant reduction from approximately half of the
reporting quarters since Q1 2020.
(Page 234 of Total)
48
418a
USCA Case #24-1119
Document #2058570
Filed: 06/07/2024
Page 109 of 204
Appendix B
PM Emission Rate, Mean and 99th Percentile (lbs/MBtu)
0.018
TVA Gallatin Unit 1
Mean PM Rate
99th Percentile Rate
0.016
0.014
0.012
0.010
0.008
EPA Reference
Quarter
0.006
0.004
0.002
0.000
18 Q1 18 Q2 18 Q3
1 Q4
19 Q1 19 Q2 19 Q3 19 Q4 20 Q1 20 Q2 20 Q3 20 Q4 21 Q1 21 Q2 21 Q3 21 Q4
2018
2019
2020
2021
PM Emission Rate, Mean and 99th Percentile (lbs/MBtu)
0.018
TVA Gallatin Unit 2
Mean PM Rate
99th Percentile Rate
0.016
0.014
0.012
0.010
0.008
EPA Reference
Quarter
0.006
0.004
0.002
0.000
18 Q1 18 Q2 18 Q3
2018
(Page 235 of Total)
1 Q4
19 Q1 19 Q2 19 Q3 19 Q4 20 Q1 20 Q2 20 Q3 20 Q4 21 Q1 21 Q2 21 Q3 21 Q4
2019
2020
2021
49
419a
USCA Case #24-1119
Document #2058570
Filed: 06/07/2024
Page 110 of 204
Appendix B
PM Emission Rate, Mean and 99th Percentile (lbs/MBtu)
0.012
TVA Gallatin Unit 3
Mean PM Rate
99th Percentile Rate
0.010
0.008
0.006
EPA Reference
Quarter
0.004
0.002
0.000
18 Q1 18 Q2 18 Q3
1 Q4
19 Q1 19 Q2 19 Q3 19 Q4 20 Q1 20 Q2 20 Q3 20 Q4 21 Q1 21 Q2 21 Q3 21 Q4
2019
2018
2020
2021
PM Emission Rate, Mean and 99th Percentile (lbs/MBtu)
0.012
TVA Gallatin Unit 3
Mean PM Rate
99th Percentile Rate
0.010
0.008
0.006
EPA Reference
Quarter
0.004
0.002
0.000
18 Q1 18 Q2 18 Q3
2018
(Page 236 of Total)
1 Q4
19 Q1 19 Q2 19 Q3 19 Q4 20 Q1 20 Q2 20 Q3 20 Q4 21 Q1 21 Q2 21 Q3 21 Q4
2019
2020
2021
50
420a
USCA Case #24-1119
Document #2058570
Filed: 06/07/2024
Page 111 of 204
Appendix B
PM Emission Rate, Mean and 99th Percentile (lbs/MBtu)
0.020
Mean PM Rate
99th Percentile Rate
Ghent Unit 1
0.015
0.010
EPA Reference
Quarter
0.005
0.000
PM Emission Rate, Mean and 99th Percentile (lbs/MBtu)
0.030
Mean PM Rate
99th Percentile Rate
Mill Creek Unit 4
0.025
0.020
0.015
0.010
EPA Reference
Quarter
0.005
0.000
(Page 237 of Total)
51
421a
USCA Case #24-1119
Document #2058570
Filed: 06/07/2024
Page 112 of 204
Appendix B
0.025
Mean PM Rate
99th Percentile Rate
Gaston Unit 5
PM Emission Rate (lbs/MBtu)
0.020
0.015
EPA Reference
Quarter
0.010
0.005
0.000
0.025
Mean PM Rate
99th Percentile Rate
Miller Unit 1
PM Emission Rate (lbs/MBtu)
0.020
0.015
0.010
EPA Reference
Quarter
0.005
0.000
(Page 238 of Total)
52
422a
USCA Case #24-1119
Document #2058570
Filed: 06/07/2024
Page 113 of 204
Appendix B
0.035
Mean
PM Emission Rate (lbs/MBtu)
0.030
Trimble County 1
99th
0.025
0.020
0.015
0.010
EPA Reference
Quarter
0.005
0.000
(Page 239 of Total)
53
423a
USCA Case #24-1119
Document #2058570
Filed: 06/07/2024
Page 114 of 204
ATTACHMENT C
(Page 240 of Total)
424a
USCA Case #24-1119
Document #2058570
Filed: 06/07/2024
Page 115 of 204
MEMORANDUM
Date:
December 16, 2011
Subject:
Emission Reduction Costs for Beyond-the-floor Mercury Rate for Existing Units
Designed to Burn Low Rank Virgin Coal
From:
Kevin Culligan, SPPD/OAQPS
To:
EPA-HQ-OAR-2009-0234
For the final rule, EPA has recalculated the beyond the floor control costs for existing
units designed to burn low rank virgin coal using a methodology similar to that used in the IPM
analysis done for the MATS proposal. In the final rule, we have not recalculated control costs
based on the other methodology used in the proposal which used ACI capital and operating costs
provided in the ICR. We have not used that approach because it was based upon an assumption
that all units would need to have a baghouse (also known as a fabric filter – FF – either existing
or newly installed) in order to meet the MACT PM standard and that the ACI would be used with
the baghouse. EPA has considered and used additional information demonstrating that high
levels of mercury removal can be achieved with injection of brominated activated carbon and the
addition of a FF is not necessary. Furthermore, based on additional analysis related to the PM
standard, EPA believes that most lignite units will not need to install new FF, therefore, EPA
believes a costing methodology based on this assumption would be inappropriate.
For this analysis, EPA calculated beyond-the-floor costs for mercury controls by
assuming injection of brominated activated carbon at a rate of 3.0 lb/MACF for units with ESPs
and injection rates of 2.0 lb/MACF for units with baghouses (also known as fabric filters). The
rate of 2.0 lb/MACF for fabric filters is consistent with the rate assumed in all other IPM
analyses for this rule. The rate of 3.0 lb/MACF for units with ESPs is lower than the rate of 5.0
lb/MACF assumed in the IPM analysis. EPA believes that this rate is appropriate, because a
higher rate would likely result in reductions beyond those needed to meet the BTF standard of
4.0 lb/TBtu. Figure 1 in "Activated Carbon Injection for Mercury: Overview" 1 suggests that >
90% control can be achieved at lignite-fired units at a < 2.0 lb/MACF injection rate for units with
installed FF and using treated (i.e., brominated) AC. The figure also suggests that > 90% Hg
control can be achieved at lignite-fired units at < 3.0 lb/MACF injection rate for units with
installed ESPs and using treated AC. As Table 1 below shows, based on the IPM analysis, all
units would need to achieve reductions of less than 90%, therefore lower assumed injection rates
are appropriate.
1
Fuel Processing Technology 89 (2010) 1310
(Page 241 of Total)
425a
USCA Case #24-1119
Document #2058570
Filed: 06/07/2024
Page 116 of 204
Table 1 – Emission Reduction Rates Required to Meet Standard of 4 lb/TBtu.
Plant Name
Big Brown
Big Brown
Lewis & Clark
Martin Lake
Martin Lake
Martin Lake
Monticello
R M Heskett
R M Heskett
Leland Olds
Leland Olds
Milton R Young
Milton R Young
Stanton
Stanton
Limestone
Limestone
Dolet Hills
Coal Creek
Coal Creek
Laramie River Station
Laramie River Station
Antelope Valley
Antelope Valley
Twin Oaks Power One
Twin Oaks Power One
Pirkey
Coyote
Great River Energy Spiritwood Station
Unit ID Hg Controls Existing Controls
1
ACI
Cold-side ESP + Fabric Filter + SNCR
2
ACI
Cold-side ESP + Fabric Filter + SNCR
B1
ACI
Wet Scrubber
1
ACI
Cold-side ESP + Wet Scrubber
2
ACI
Cold-side ESP + Wet Scrubber
3
ACI
Cold-side ESP + Wet Scrubber
3
ACI
Cold-side ESP + SNCR + Wet Scrubber
B1
Cold-side ESP
B2
Cold-side ESP + Cyclone
1
Cold-side ESP
2
Cold-side ESP
B1
Cold-side ESP + SCR + Wet Scrubber
B2
Cold-side ESP + SCR + Wet Scrubber
1
Cold-side ESP
10
Fabric Filter + Dry Scrubber
LIM1
Cold-side ESP + Wet Scrubber
LIM2
Cold-side ESP + Wet Scrubber
1
Cold-side ESP + Wet Scrubber
1
Cold-side ESP + Wet Scrubber
2
Cold-side ESP + Wet Scrubber
1
Cold-side ESP + Wet Scrubber
2
Cold-side ESP + Wet Scrubber
B1
Fabric Filter + Dry Scrubber
B2
Fabric Filter + Dry Scrubber
U1
Fabric Filter
U2
Fabric Filter
1
Cold-side ESP + Wet Scrubber
B1
Fabric Filter + Dry Scrubber
1
Cold-side ESP + Fabric Filter + SNCR + Dry Scrubber
Base
Reduction
Policy
Hg lbs/Tbtu Required, % Hg lbs/Tbtu
9.09
55.98
1.01
9.09
55.98
1.01
7.68
47.92
0.75
5.41
26.09
0.56
5.41
26.09
0.56
5.41
26.09
0.56
6.30
36.53
0.96
7.81
48.77
0.45
4.76
16.00
0.75
7.68
47.93
0.77
7.81
48.77
0.78
4.21
4.93
0.75
4.21
4.93
0.75
7.81
48.77
0.78
7.51
46.76
0.75
6.75
40.76
1.13
6.75
40.76
1.13
8.33
51.98
1.35
4.21
5.07
0.76
4.21
5.07
0.76
5.31
24.71
0.56
5.31
24.71
0.56
7.51
46.76
0.75
7.51
46.76
0.75
5.82
31.33
1.35
5.82
31.33
1.35
7.59
47.27
1.35
7.64
47.66
0.75
7.68
47.92
0.75
EPA also assumed a disposal cost of $25/ton for ash comingled with activated carbon.
This cost is consistent with a range of studies. DOE/NETL, in a recent study examining the
costs of ACI, assumed total disposal costs of $17/ton for non-hazardous fly ash. They assumed
$35/ton for fly ash that would have otherwise been sold for beneficial reuse (lost revenue of
$18/ton plus disposal costs of $17/ton for non-hazardous fly ash). 2 In an EPA study, $25 - $30
per ton were assumed as total disposal costs.3
EPA recently modeled site-specific disposal costs for the RIA 4 for the proposed rule
regulating coal combustion residuals (CCRs), including fly ash. Those costs were examined for
units burning low rank virgin coal. The disposal costs varied by state/region. For Texas the
incremental costs attributable to Hg control were $18.13/ton, while for North Dakota and
Montana, the incremental costs attributable to Hg control were $32.31/ton.
2
Environmental Sci. Technol. 2007, 41, 1365].
Environmental Sci. Technol. 2006, 1385
4
Regulatory Impact Analysis For EPA’s Proposed RCRA Regulation Of Coal Combustion Residues (CCR)
Generated by the Electric Utility Industry. Prepared by US Environmental Protection Agency Office of Resource
Conservation & Recovery (ORCR) (formerly Office of Solid Waste) 1200 Pennsylvania Avenue NW (Mailstop
5305P) Washington DC, 20460 USA. Available at http://www.regulations.gov/ docket number EPA-HQ-RCRA2009-0640-0003, Appendix H.
3
(Page 242 of Total)
426a
USCA Case #24-1119
Document #2058570
Filed: 06/07/2024
Page 117 of 204
Based on these key assumptions, EPA projects an average reduction cost of $27,017 per
pound of Hg removed. Unit by unit costs are provided in Table 2.
Table 2 – Unit by unit cost estimates for achieving an emission rate of 4 lb/TBtu Hg
Plant Name
Unit ID
Capacity
(MW)
Heat Rate Existing PM
(Btu/kWh) Controls
Big Brown
1
575
11001
Big Brown
2
575
10931
Lewis & Clark
B1
52.3
13787
Martin Lake
1
750
11512
Martin Lake
2
750
11202
Martin Lake
3
750
10784
Monticello
3
750
11246
R M Heskett
B1
29.37
11985
R M Heskett
B2
75.5
11386
Leland Olds
Leland Olds
1
2
221
448
11404
11021
Milton R Young
B1
250
10661
Milton R Young
B2
455
10661
Stanton
1
130.3472 10990
Stanton
10
57.35278 10320
Limestone
LIM1
831
10102
Limestone
LIM2
858
10108
(Page 243 of Total)
Cold-side ESP +
Fabric Filter +
SNCR
Cold-side ESP +
Fabric Filter +
SNCR
Wet Scrubber
Cold-side ESP +
Wet Scrubber
Cold-side ESP +
Wet Scrubber
Cold-side ESP +
Wet Scrubber
Cold-side ESP +
SNCR + Wet
Scrubber
Cold-side ESP
Cold-side ESP +
Cyclone
Cold-side ESP
Cold-side ESP
Cold-side ESP +
SCR + Wet
Scrubber
Cold-side ESP +
SCR + Wet
Scrubber
Cold-side ESP
Fabric Filter +
Dry Scrubber
Cold-side ESP +
Wet Scrubber
Cold-side ESP +
(Base to
Policy) Hg
remv'd (lbm)
(2007$) unit
S/lbm Hg
Total
Cost
-396
3954
1565723
-393
3980
1565723
-31
22920
704682
-332
32175
10671737
-323
32174
10383770
-311
32309
10038209
-359
29249
10487787
-17
38871
652353
-22
53992
1206545
-109
-217
25792
23822
2812406
5176973
-64
51542
3272935
-116
49018
5665257
-77
26601
2050240
-31
30538
935770.1
-372
29034
10797351
-384
28982
11134608
427a
USCA Case #24-1119
Document #2058570
Coal Creek
1
554
11219
Coal Creek
2
560.3
10818
1
565
11312
2
570
10953
Antelope Valley
B1
450
10988
Antelope Valley
B2
450
11206
U1
152
9497
U2
153
10364
Coyote
B1
427
11639
Pirkey
1
675
10693
Laramie River
Station
Laramie River
Station
Twin Oaks Power
One
Twin Oaks Power
One
Filed: 06/07/2024
Wet Scrubber
Cold-side ESP +
Wet Scrubber
Cold-side ESP +
Wet Scrubber
Cold-side ESP +
Wet Scrubber
Cold-side ESP +
Wet Scrubber
Fabric Filter +
Dry Scrubber
Fabric Filter +
Dry Scrubber
-162
48056
7781365
-158
47982
7576786
-235
34742
8170580
-230
34737
7980115
-264
22315
5888636
-269
22269
5993120
Fabric Filter
-50
38215
1900963
Fabric Filter
-55
37778
2064287
-228
22122
5043515
-349
26185
9140141
-46
11694
535381.6
-351
27064
9500464
Fabric Filter +
Dry Scrubber
Cold-side ESP +
Wet Scrubber
Great River Energy
Spiritwood Station
1
99
8937
Cold-side ESP +
Fabric Filter +
SNCR + Dry
Scrubber
Dolet Hills
1
650
10674
Cold-side ESP +
Wet Scrubber
Total
Average
(Page 244 of Total)
Page 118 of 204
-5948
1.61E+08
27016
428a
USCA Case #24-1119
Document #2058570
Filed: 06/07/2024
Page 119 of 204
ATTACHMENT D
(Page 245 of Total)
429a
USCA Case #24-1119
(Page 246 of Total)
Document #2058570
Filed: 06/07/2024
Page 120 of 204
430a
USCA Case #24-1119
(Page 247 of Total)
Document #2058570
Filed: 06/07/2024
Page 121 of 204
431a
USCA Case #24-1119
(Page 248 of Total)
Document #2058570
Filed: 06/07/2024
Page 122 of 204
432a
USCA Case #24-1119
Document #2058570
Filed: 06/07/2024
Page 123 of 204
ATTACHMENT E
(Page 249 of Total)
433a
USCA Case #24-1119
Document #2058570
Filed: 06/07/2024
Page 124 of 204
Minnkota Power Cooperative, Inc.
Milton R. Young Station Unit 2
Particulate & Mercury Control
Technology Evaluation & Risk
Assessment for Proposed MATS Rule
Final
June 23, 2023
Project No.: A14559.010
S&L Nuclear QA Program Applicable:
Yes
No
55 East Monroe Street
Chicago, IL 60603-5780 USA
312-269-2000
www.sargentlundy.com
(Page 250 of Total)
434a
Minnkota Power Cooperative, Inc.
USCA
Case #24-1119
Document #2058570
Milton R. Young Station Unit 2
Filed: 06/07/2024
PageRev.
125
204
No.:of
Final
June 23, 2023
A14559.010
1.INTRODUCTION
1.1. PURPOSE
Sa
Sargent
& Lundy (S&L) was retained by Minnkota Power Cooperative, Inc. (Minnkota) to evaluate potential
filterable particulate matter (PM) and mercury (Hg) emissions reductions in response to the proposed rule to
amend the National Emission Standards for Hazardous Air Pollutants (NESHAP) for Coal-and Oil-Fired
Electric Utility Steam Generating Units (EGUs), commonly known as Mercury and Air Toxics Standards
(MATS) published on April 24, 2023 that would require additional filterable PM and Hg emissions reductions
on the Milton R. Young (MRY) Station Unit 2. These proposed revisions are the result of EPA’s review of the
residual risk and technology review (RTR) from May 22, 2020. Based on the proposed rule, EPA is planning
to revise the filterable PM standards from 0.030 lb/MMBtu to 0.010 lb/MMBtu and is soliciting comments to
consider even more stringent standard of 0.006 lb/MMBtu or lower. For lignite-fired units, EPA is also
proposing to revise and tighten mercury emission standard from 4.0 lb/TBtu to 1.2 lb/TBtu to make it same as
other units firing bituminous and subbituminous coal.
S&L reviewed the existing MRY Unit 2 PM and Hg control technologies to determine potential optimizations
that could achieve incremental emission reductions as well as consider new PM and Hg control technologies.
S&L prepared an evaluation of available control technologies including technical feasibility and effectiveness,
and costs based on the current emissions from the unit. S&L’s evaluation was completed based on past
experience on similar projects, as well as input from established original equipment manufacturers (OEMs)
regarding predicted performance for the lignite application at MRY Unit 2.
1.2. FACILITY BACKGROUND
The MRY station is located approximately seven (7) miles southeast of Center, North Dakota or forty (40)
miles northwest of Bismarck, North Dakota on ND Highway 25 at 3401 24th Street SW, Center, North Dakota
58530. MRY station provides energy to the Midcontinent Independent System Operator (MISO) system. MRY
station consists of two (2) units. Both MRY units are lignite-fired Babcock and Wilcox (B&W) cyclone boilers.
The Unit 1 single wall cyclone boiler was placed into service in 1970 and has a typical output capacity rating
of 257 MWg (gross). The Unit 2 opposed wall cyclone boiler (Carolina type, radiant pump assisted natural
circulation) was placed into service in 1977 and has a typical output capacity rating of 470 MWg (gross). Both
boilers fire North Dakota lignite coal supplied from BNI Coal, Ltd.’s Center Mine located in close proximity to
the plant. Both units utilize selective non-catalytic reduction (SNCR) and separated overfire air (SOFA)
systems for NOx control, fuel additive (halide injection) system and non-halogenated powdered activated
carbon (PAC) for Hg control, dry electrostatic precipitators (ESP) for PM emissions control, and wet flue gas
desulfurization (WFGD) systems for sulfur dioxide (SO2) control.
1.3. DIFFERENCES IN MRY UNIT 1 AND 2 DESIGN & OPERATION
MRY Unit 1 and 2 have the same air pollution control equipment in series; however, the design of the
equipment differ in ways other than unit MWg size. Of particular note, the Unit 2 ESP design attributes are
superior to Unit 1, with use of a wider plate spacing (12 vs. 9 inches), and a higher specific collection area
(375 ft2/1000 actual cubic feet per minute (acfm) vs. 288 ft2/1000 acfm). However, the Unit 2 ESP design
consists of the first 2 fields' specific corona power = 160 W/1000 acfm and the last 2 fields = 240 W/1000 acfm,
Particulate & Mercury Control Technology Evaluation & Risk Assessment
for Proposed MATS Rule
(Page 251 of Total)
1
435a
Minnkota Power Cooperative, Inc.
USCA
Case #24-1119
Document #2058570
Milton R. Young Station Unit 2
Filed: 06/07/2024
PageRev.
126
204
No.:of
Final
June 23, 2023
A14559.010
which is consistent with historic ESP designs where transformer-rectifier (T/R) sets were typically selected to
provide lower current density at the inlet sections, where the dust concentration will tend to suppress the
corona current, and to provide higher current density at the outlet sections, where there is a greater percentage
of fine particles. In comparison, the Unit 1 ESP design does not follow this approach, with all fields’ specific
corona power = 493 W/1000 acfm and is currently achieving significantly lower PM emissions than Unit 2. The
single Unit 1 WFGD vessel has four (4) slurry recycle pumps (SRPs). Each of the two (2) WFGD vessels on
Unit 2 have five (5) SRPs.
Furthermore, manual cleaning of the boiler on Unit 1 is also able to include air preheater (APH) cleaning,
whereas the large hoppers below the Unit 2 APH prevent APH washes from being completed during shortterm boiler cleaning outages. The Unit 1 offline cleaning occurs on average every 110-115 days and requires
the unit to be offline typically for three (3) days. The Unit 2 offline cleaning (only including APH tube rodding)
occurs on average every 85-90 days and requires the unit to be offline typically for four (4) days.
s.
1.4. CU
CURRENT BASELINE EMISSIONS
Minnkota provided the past five (5) years of emissions to establish baseline emissions used for this evaluation.
The baseline emissions were developed using data submitted by Minnkota to the EPA between January 01,
2018 through December 31, 2022 as part of emissions reporting requirements. For PM emissions, a 30-boiler
operating day rolling average was selected as the baseline PM emission calculation methodology to be in-line
with the permit reporting requirements. For Hg emissions, the maximum 30-boiler operating day experienced
during the evaluation period was selected as the baseline Hg emission.
Table 1-1 — Baseline Unit 2 PM & Hg Emissions
Parameter
Units
Unit 2
PM Emissions
lb/MMBtu
0.015
Hg Emissions
lb/TBtu
3.90
3.
Particulate & Mercury Control Technology Evaluation & Risk Assessment
for Proposed MATS Rule
(Page 252 of Total)
2
436a
Minnkota Power Cooperative, Inc.
USCA
Case #24-1119
Document #2058570
Milton R. Young Station Unit 2
A14559.010
Filed: 06/07/2024
PageRev.
127
204
No.:of
Final
June 23, 2023
2.PARTICULATE TECHNOLOGY EVALUATION
As part of this evaluation, PM control technologies were evaluated based on achieving post-upgrade emissions
limits in accordance with the proposed emissions included in the April 24, 2023, MATS proposed rule, 0.010
lb/MMBtu and potentially 0.006 lb/MMBtu. The description and assessment of each control option are
discussed in the sections below.
2.1. OP
OPTIONS TO REACH 0.010 LB/MMBTU
2.1.1.Increased Boiler Cleaning Outages
When manual cleaning of the boiler occurs, the following unit operation indicates reduced economizer outlet
temperatures and subsequently APH outlet temperatures. The fly ash resistivity is reduced at lower
temperatures making it easier to capture in the ESP. The decrease in temperature would also slightly reduce
the volumetric flow through the ESP, which may also allow for improved flow and velocity through the ESP,
subsequently improving the ESP overall performance. Although scheduling short term outages to complete
cleaning of the boiler on a regular basis (regardless of near-term long-term outages) has shown the ability to
maintain emissions below the baseline emissions, a PM emission of 0.010 lb/MMBtu likely cannot be achieved
and therefore this option was not considered further.
2.1.2.Flow & Distribution Devices
Uniform gas and dust distribution to each ESP casing will allow for uniform treatment/conditions of each casing
to facilitate optimal performance of each. Concentrated flow and/or dust to a casing will require that casing to
work harder than the others, ultimately contributing to and/or causing other operating inefficiencies within the
ESP to reduce its PM removal capabilities. Replacement of existing inlet and outlet flow & dust distribution
devices to achieve the latest standards of the Institute of Clean Air Companies (ICAC) Publication No. EP-7
will improve the ESP overall performance. Implementation of other flow correction devices to minimize
sneakage between cells and/or around collecting fields as well as to minimize particle re-entrainment from
hoppers and collecting surfaces when rapped can also be implemented, as required, to meet best industry
practices, if not already implemented as part of ESP designs.
A detailed assessment including computational flow dynamic (CFD) analysis and physical flow model studies
would be performed to determine the design and placement of all flow and dust distribution devices. New
designs of perforated plates (with rappers) would be implemented to allow for the easy removal of fly ash into
the first field hopper to minimize the potential fly ash accumulation in the inlet plenum. Although PM emissions
reductions are expected to be achieved with this option, a PM emission of 0.010 lb/MMBtu likely cannot be
achieved and therefore this option was not considered further.
2.1.3.Increased Power Supply
In an ESP, the collection efficiency is proportional to the amount of corona power supplied to the unit, assuming
the corona power is applied effectively (maintains a good sparking rate). The resulting corona current charges
the PM in the flue gas which are then attracted to the grounded, oppositely charged collecting plates. For a
given flow rate, the collection efficiency will increase as the corona power is increased. To achieve a high
collection efficiency, corona power is usually between 100 and 500 W/1000 acfm, but newer ESP installations
Particulate & Mercury Control Technology Evaluation & Risk Assessment
for Proposed MATS Rule
(Page 253 of Total)
3
437a
Minnkota Power Cooperative, Inc.
USCA
Case #24-1119
Document #2058570
Milton R. Young Station Unit 2
A14559.010
Filed: 06/07/2024
PageRev.
128
204
No.:of
Final
June 23, 2023
have been designed for as much as 800-900 W/1000 acfm.
Increasing the power delivered into the ESP casing for this option would be done by replacing the T/R sets
with higher rated power supplies, e.g. switch mode power supplies (SMPS), also referred as high frequency
T/R sets, or 3-phase power supplies. Replacement of the T/R sets will require new cables, as the existing
cables for 2-phase will need to be upgraded to accommodate 3-phase; cables are assumed to be able to be
pulled while the unit continues to operate. Further assessment would be required to determine all electrical
infrastructure modifications required, including the ability to reuse the existing MCC and T/R set controls.
Although PM emissions reductions are expected to be achieved with this option, a PM emission limit of 0.010
lb/MMBtu with adequate operating margin likely cannot be achieved and therefore this option was not
considered further.
2.1.4.Additional ESP Field
As ESP performance does depend on the number of fields in the direction of flue gas flow, the addition of
another field will increase the amount of power that can be supplied to the ESP and provide incremental
removal of the filterable PM. As approximately 80% of the ash is expected to be collected in the first field, with
decreasing degrees of particulate removal in the following fields, the last field in the ESP casing is expected
to have the least amount of fly ash removed. This option can be implemented by either increasing the
sectionalization of the last field (adding a T/R set) or potentially by utilizing the ESP outlet nozzle to retrofit
another independently operated ESP field.
Sectionalization in the direction of gas flow is not feasible without a rebuild of the fields to be sectionalized as
the current high voltage frames span the entire length of the field. Therefore, this option is only feasible if a
new field is added at either the inlet or outlet of the existing ESP casing (assuming space available). However,
the retrofit implications of this option would be considered to be a large capital retrofit project in lieu of an
equipment optimization. This option is not anticipated to provide significant enough cost savings compared to
the other large capital retrofit options that will be evaluated later in this evaluation. Therefore, this option is not
considered further.
2.1.5.Additional ESP Casing
Installation of additional ESP casings in parallel to the existing Unit 2 ESP casings would increase the specific
collecting area (SCA) and improve the velocity and treatment time of the existing ESP casings. The smaller
wing ESP casings would be installed adjacent to the existing ESP casings, one added to north of Casing A
and one added to the south of Casing B. The new wing casings will utilize a separate support structure and
new power supplies to be independent, stand-alone structures. It is anticipated that modifications to the inlet
and outlet ductwork would be required to evenly balance the flow to the new casings. The hoppers of the new
ESP casings would be tied into the existing fly ash handling system. Although PM emissions reductions are
expected to be achieved with this option, a PM emission limit of 0.010 lb/MMBtu with adequate operating
margin likely cannot be achieved and therefore this option was not considered further.
2.1.6.ESP Rebuild
Rebuilding the existing Unit 2 ESP would involve replacement of all internals, while only reusing the outer
shell/walls, hoppers, support structures, and ash conveying system. To accomplish the rebuild of the ESP
Particulate & Mercury Control Technology Evaluation & Risk Assessment
for Proposed MATS Rule
(Page 254 of Total)
4
438a
Minnkota Power Cooperative, Inc.
USCA
Case #24-1119
Document #2058570
Milton R. Young Station Unit 2
A14559.010
Filed: 06/07/2024
PageRev.
129
204
No.:of
Final
June 23, 2023
casings, the roof, T/R sets, high voltage bus ducts, top end frames, intermediate roof beams, the top section
of the inlet and outlet nozzles and all internal components of the existing ESPs will be removed, and replaced
with new equipment. The flow distribution and correction devices in the inlet and outlet plenums would be
replaced to optimize the flue gas and fly ash distribution to the casings. The hot and cold roofs would also be
replaced as well to accommodate construction activities.
Before moving forward with rebuild, a structural integrity and thickness study should be completed on the
entire structure to ensure that the steel has not thinned as a result of normal long-term option. The design of
the support structure (casing, structural members, and determination of ESP loads to steel), support steel and
foundation will need to be reviewed to verify if acceptable for reuse or if modifications are required for the
weight change in the ESP casings as a result of the rebuild, which may result in additional reinforcement
required. The existing ash handling systems would be reused without requiring any modifications for the
incremental increase in the amount of ash collected. It would be assumed that the complete rebuild of the ESP
casings and optimization of the flow distribution/collection devices in the inlet and outlet nozzles should be
capable of achieving no net increase in the current pressure drop across the ESP and therefore would not
require modifications or replacement of the existing ID fans.
The level of rebuild and repair to the existing ESP casings will require a longer construction outage, most likely
requiring a twelve (12) week outage, if not longer. Limited access to the Unit 2 casings will also limit the
construction sequence, and may cause delays, further extending the outage. Winter weather conditions
experienced at the site could also prolong the construction process. Additional construction personnel would
likely be required to complete work in multiple areas in an effort to reduce the outage duration.
With this option, the PM emissions are estimated to potentially achieve an emission rate of 0.008 lb/MMBtu.
However, vendors would likely have to complete a more detailed qualitative study in order to provide a
guarantee and would require baseline testing to qualify ESP inlet and outlet emissions.
2.2. OPTIONS TO REACH 0.006 LB/MMBTU
To achieve PM emissions that would allow for compliance with the more stringent proposed standard, a
baghouse would be required. It should be noted that a baghouse will likely not provide sufficient operating
margin to achieve the proposed 0.006 lb/MM
MMBtu emission rate. It will likely be challenging to obtain a guarantee
below 0.006 lb/MMBtu from baghouse OEMs. However, a baghouse is not considered to be economically
feasible 1 and is therefore not evaluated further. The baghouse installation options that could be considered,
described below, and the expected timeline for implementation of this control option, described in Table 2-2,
are included for reference only.
•
•
Conversion of ESP to Baghouse:
o The existing ESP casings would be reused and ESP internals and all roof mounted equipment
would be removed. A vertical partition wall, running in the direction of gas flow from the hopper
bend line to the tube sheet, would be constructed in the center of each ESP casing.
Polishing Baghouse (Downstream of ESP):
o The existing ESP would continue to operate. Due to the reduced inlet ash loading, a polishing
1
A high-level estimation of the cost effectiveness of a baghouse retrofit on MRY Unit 2 is approximately $162k/ton,
based on the annualized capital and O&M costs ($/yr) divided by the annual reduction in annual emissions (ton/yr).
Particulate & Mercury Control Technology Evaluation & Risk Assessment
for Proposed MATS Rule
(Page 255 of Total)
5
439a
Minnkota Power Cooperative, Inc.
USCA
Case #24-1119
Document #2058570
Milton R. Young Station Unit 2
Filed: 06/07/2024
PageRev.
130
204
No.:of
Final
June 23, 2023
A14559.010
•
baghouse can be designed using a 6.0 air-to
to-cloth (AC
AC) ratio, which allows for a reduced
footprint compared to a 4.0 AC ratio sized to handle the entire unit fly ash loading.
o There is not adequate space available adjacent to the existing ESP casings for placement of
a baghouse. Therefore, long tie-in ductwork will be required to route flue gas to an open area
where the baghouse can be constructed. As such, the reduced size of the polishing baghouse
is not anticipated to provide significant enough cost savings when compared to a baghouse
that utilizes a 4.0 AC ratio.
Baghouse (Primary PM Collection):
o The existing ESP would be abandoned in place (could be demolished at a later date). As
mentioned previously, long tie-in ductwork will be required to route flue gas to an open area
where the baghouse can be constructed while the unit continues to operate in order to
minimize the tie-in outage duration.
A baghouse is expected to have a pressure drop of 8 in. w.c., but could be higher depending on the location
of the baghouse in relation to the tie-in to the existing flue gas path. The current axial fans are already operated
very close to their stall curve, and do not have any pressure drop operating margin. Therefore, either
replacement of the existing ID fans or installation of new booster fans would be required to accommodate the
additional pressure drop through the baghouse.
2.3. PARTICULATE EMISSIONS SUMMARY
Table 2-1 below provides a summary of the post-upgrade achievable emission rate for the feasible PM control
option evaluated to achieve a proposed PM emission limit of 0.010 lb/MMBtu. The estimated emission rates
included in the following tables are considered to be representative of an average emission rate that could be
achieved under normal operating conditions. The emission rates provided should not be construed to
represent an enforceable regulatory or proposed permit limit. Corresponding regulatory and/or permit limits
must be evaluated on a control system-specific basis taking into consideration normal operating variability
(i.e., a minimum additional 20% margin would likely be needed to account for operating margin).
Table 2-1 — Unit 2 PM Emissions Summary
Parameter
Baseline (Dry ESP)
ESP Rebuild
Control
Efficiency Note 1
Projected
Emissions Note 2
(lb/MMBtu)
Expected Emissions
(ton/year)
--
0.015
254
46.7%
0.008
135
Note 1 – Control efficiency is based on incremental improvement achieved with the option in addition to baseline dry ESP
operation (e.g. not to be misconstrued as a total percent removal from uncontrolled PM emissions).
Note 2 – No compliance margin is included in these estimates. The emissions rate projections should not be used as an
achievable limit for these upgrades.
2.4. TIMELINE FOR INSTALLATION
A high-level implementation schedule that outlines the time needed for the project steps necessary for the
implementation of the feasible control options are summarized below. It should be noted that although a
baghouse is not considered to be economically feasible, the control option is included in the summary below
for reference on the expected timeline required for implementation of this control option. Other project-related
Particulate & Mercury Control Technology Evaluation & Risk Assessment
for Proposed MATS Rule
(Page 256 of Total)
6
440a
Minnkota Power Cooperative, Inc.
USCA
Case #24-1119
Document #2058570
Milton R. Young Station Unit 2
Filed: 06/07/2024
PageRev.
131
204
No.:of
Final
June 23, 2023
A14559.010
activities, such as the time needed to obtain internal project approval, financing or permitting, if required, are
not included. It should be noted that these time frames are separate from the regulatory time frames for EPA
to take final action on the Proposed MATS RTR.
Lead times of equipment that would be used in these types of retrofits have been observed to be double or
triple the lead times typically provided by suppliers before the COVID pandemic, with longer durations
observed for electrical and instrumentation and control equipment. With continued supply-chain issues, it is
anticipated that longer and longer lead times may be required that are difficult to quant
ntify at this time.
Therefore, timelines represented are estimated based on past project durations and not reflective of postpandemic market delays nor the limited number of experienced OEMs capable of providing the equipment.
Table 2-2 — PM Control Implementation Schedule
Design/
Specification/
Procurement
Detail Design/
Fabrication
Construction/
Commissioning/
Startup
Minimum
Total
(months)
(months)
(months)
(months)
ESP Rebuild
8
16
12
36
Baghouse
10
20
18
48
PM Control Option
Particulate & Mercury Control Technology Evaluation & Risk Assessment
for Proposed MATS Rule
(Page 257 of Total)
7
441a
Minnkota Power Cooperative, Inc.
USCA
Case #24-1119
Document #2058570
Milton R. Young Station Unit 2
Filed: 06/07/2024
PageRev.
132
204
No.:of
Final
A14559.010
June 23, 2023
3.MERCURY TECHNOLOGY EVALUATION
3.1. MERCURY EMISSIONS BACKGROUND
3.1.1.Mercury Speciation
Mercury (Hg) is contained in varying concentrations in different coal supplies. During combustion, Hg is
released in the form of elemental Hg in the high temperature combustion zone of a boiler. As the combustion
gases cool, a portion of the elemental Hg transforms or oxidizes to ionic Hg
Hg. However, the amount of elemental
Hg that oxidizes is dependent on the cooling rate of the gas and the presence of halogens in the flue gas.
Ultimately, there are three possible forms of Hg
Hg:
•
•
•
Elemental (Hg0):
o The conversion of elemental Hg to the other forms depends upon several factors including
cooling rate of the gas, presence of halogens or sulfur trioxide (SO 3) in the flue gas, amount
and composition of fly ash, presence of unburned carbon, and the installed APC equipment.
o Hg0 is insoluble in water and therefore removal requires injected sorbents or must be
converted to another form to be captured, depending on the installed APC equipment.
Ionic or Oxidized (Hg
Hg++ or Hg2+):
o In contrast to elemental Hg
Hg, ionic Hg is highly water soluble, allowing for collection in water
streams that may be utilized in certain APC equipment and subsequently leave the process
with the solid by-product or as a constituent in the purge water.
Particulate-bound:
o Particulate-bound Hg typically is bound to fly ash or unburned carbon. Particulate-bound Hg
is efficiently removed from the flue gas by the particulate control device, making it desirable
to convert as much Hg as possible to particulate-bound Hg
Hg.
o High SO3 levels have been shown to inhibit the binding of ionic Hg to fly ash or Hg sorbents.
The addition of halogens increase the conversion of elemental and ionic Hg to particulatebound Hg
Hg.
The proportion of the various Hg forms is referred to as Hg speciation. As such, Hg speciation testing has
indicated that the distribution of Hg species varies with coal type. The effectiveness of post-combustion Hg
control technologies is highly influenced by the Hg speciation in the flue gas, with gaseous oxidized (or ionic)
Hg compounds (i.e. HgCl2) being easier to capture by downstream APC equipment.
3.1.2.Lignite Coal Variability
Industry experience has shown that lignite coal deposits vary significantly in quality, including fuel combustion
performance, mineral content, and Hg content, resulting in a coal that can change on a day-to
to-day basis
depending on the coal seam being mined at the time. For example, during the 2005 Energy & Environmental
Research Center (EERC) sixty (60) day testing on MRY Unit 2, 2 the coal samples analyzed ranged from 6.22
2
Refer to the EERC “Large-Scale Mercury Control Technology Testing for Lignite-Fired Utilities - Oxidation Systems for
Wet FGD” report (Cooperative Agreement No. DE-FC26-03NT41991) dated March 2007 for further details on the testing
completed from March 15, 2005 to May 15, 2005 on MRY Unit 2.
Particulate & Mercury Control Technology Evaluation & Risk Assessment
for Proposed MATS Rule
(Page 258 of Total)
8
442a
Minnkota Power Cooperative, Inc.
USCA
Case #24-1119
Document #2058570
Filed: 06/07/2024
Milton R. Young Station Unit 2
PageRev.
133
204
No.:of
Final
June 23, 2023
A14559.010
lb/TBtu to 10.9 lb/TBtu (Hg content varied from 0.05 to 0.25 ppm, and averaged 0.112 ± 0.014 ppm on a dry
coal basis). As such, units firing lignite coal with lower heating values have to accommodate frequently
changing coal quality and require a wide range of flexibility to account for instances of firing high Hg seams of
coal to consistently achieve adequate operating margin below the required Hg emission limit. 3
The variability of the projected lignite coal quality received from the Center Mine from 2025 through 2036 is
shown in Table 3-1.
Table 3-1 — Center Mine Ultimate Coal Analyses (As-Received)
Fuel Parameter
Units
Average
Minimum
Maximum
Carbon
wt.%
40.53
39.73
41.24
Hydrogen (fuel-based)
wt.%
2.78
2.71
2.82
Nitrogen
wt.%
0.30
0.26
0.34
Sulfur
wt.%
0.86
0.68
1.07
Oxygen (by difference)
wt.%
9.97
9.47
10.83
Moisture
wt.%
38.83
38.53
39.25
Ash
wt.%
6.73
6.00
7.87
Higher Heating Value (HHV)
Btu/lb
6,625
6,489
6,739
Mercury Content
ppm
0.091
91
0.053
0.184
Estimated Hg Emission
lb/TBtu
8.41
4.79
17.42
3.1.3.Hg
Hg Removal with ESPs
For ACI on ESP applications, 80% of Hg capture occurs in the flue gas, and 20% occurs on the dust within
the ESP (as the dust on the collecting plates are consistently removed as part of the process). Therefore, for
ESP applications, achieving ideal mixing and residence time to allow for elemental Hg to oxidize to ionic Hg
and for Hg to be adsorbed on the carbon particles (of the PAC or unburned carbon content in the fly ash) is
critical. It should be noted that this ratio is the exact opposite for baghouse applications, i.e. 20% capture induct and 80% capture on the dust of the filter cake accumulated in the baghouse. For this reason, fabric filters
can result in extremely high Hg capture and can improve the capture with any Hg sorbent.
3.1.4.Existing System Limitations
Documented evidence of a lignite unit achieving 1.2 lb/TBtu or below has not been found/reviewed at the time
of this report. Minnkota personnel recently completed short-term parametric testing in May 2023 to determine
the Hg emissions that could be achieved by maximizing the existing fuel additive and PAC injection. Even
when maximizing the fuel additive rate in addition to maximizing the non-halogenated ACI addition, an
emission rate of 1.2 lb/TBtu was not able to be achieved. Due to the variability of the coal, a longer period of
testing would be required to gauge the Hg emissions that could be achieved just using the capacity within the
existing equipment.
3
Based on Response of Minnkota Power Cooperative Clean Air Act Section 114 Request, dated July 29, 2022.
Particulate & Mercury Control Technology Evaluation & Risk Assessment
for Proposed MATS Rule
(Page 259 of Total)
9
443a
Minnkota Power Cooperative, Inc.
USCA
Case #24-1119
Document #2058570
Milton R. Young Station Unit 2
Filed: 06/07/2024
A14559.010
PageRev.
134
204
No.:of
Final
June 23, 2023
3.2. INCREMENTAL HG CONTROL ON A LIGNITE UNIT
As mentioned previously, S&L is not aware of any documented evidence of a lignite unit achieving 1.2 lb/TBtu
or below. As such, the following sections describe issues that need to be resolved/tested to establish if it is
feasible to achieve a 1.2 lb/TBtu Hg emission rate with sufficient operating margin on a lignite unit and if so,
develop an overall Hg compliance approach that likely would consist of a suite of control approaches. It should
be noted that any achievable Hg emission should not be construed to represent an enforceable regulatory or
proposed permit limit. Corresponding regulatory and/or permit limits must be evaluated on a control systemspecific basis taking into consideration normal operating and coal variability (i.e., a minimum additional 20%
margin or higher would likely be needed
ed to account for coal fluctuations and operating margin).
3.2.1.Increased Oxidation of Elemental Hg
Recent 2011 Hg speciation data measured at the Unit 2 stack, with no control technologies, indicated the Hg
emissions consisted of approximately 98.3% elemental Hg
Hg, 0.8% oxidized Hg
Hg, and 0.9% particulate Hg
Hg.
Recent operating data from a retired Hg process monitor indicates that the Unit 2 Hg emissions, with the
currently installed Hg control technologies, consisted of approximately 86% elemental Hg
Hg, and 14% oxidized
Hg. Because the current Hg emissions are made up mostly of elemental Hg, the unit emissions would benefit
Hg
from an increased amount of halogen in an attempt to oxidize the elemental Hg in the flue gas. The additional
halogen (chlorine, iodine, and bromine) can be added to the PAC, to the coal, or both.
The current fuel additive injection could be increased and/or replaced with a different halogen-based additive.
In addition, the current non-halogenated PAC would be replaced with a more expensive halogenated PAC.
The increased amount of halogen present is expected to increase the amount of elemental Hg that is oxidized
to be more easily captured on the surface area of the PAC and in downstream APC. 4
3.2.2.Increased PAC
It is anticipated that additional halogenated PAC (i.e. more than the current capabilities of the existing
equipment) will need to be injected for the increased amount of oxidized Hg to be efficiently captured. However,
preliminary feedback received from PAC suppliers have indicated that demonstration testing would be required
to determine a PAC dosage rate and the emissions rate that can be achieved when considering the Hg content
variability of the lignite. Therefore, additional modifications that may be required cannot be concluded at this
time; however, it is likely that the existing lances and transport piping would need to be replaced to
accommodate a higher injection rate. As the existing PAC storage silo is shared by Units 1 and 2, it is likely
that a separate silo would be required for Unit 2 to ensure adequate supply, turndown flexibility, and reliability
is achieved to maintain compliance with a defined Hg emission limit.
The degree of increased PAC injection rates can have an impact on the ESP performance as the increased
amount of carbon particles that have low resistivity will decrease the overall resistivity of the fly ash (can cause
particles to rapidly lose their charge on arrival at the collecting plate and become re-entrained). If/when
4
It should be noted that the existing PAC silo is not currently compatible to store halogenated PAC due to the material of
construction of the fluidizing air nozzles and may also require an internal coating of the silo to prevent corrosion.
Additional assessment will be required to determine modifications required to reuse the existing silo, and may be subject
to the brominated PAC utilized.
Particulate & Mercury Control Technology Evaluation & Risk Assessment
for Proposed MATS Rule
(Page 260 of Total)
10
444a
Minnkota Power Cooperative, Inc.
USCA
Case #24-1119
Document #2058570
Milton R. Young Station Unit 2
A14559.010
Filed: 06/07/2024
PageRev.
135
204
No.:of
Final
June 23, 2023
additional testing is completed to determine the supplier recommended brominated PAC injection rate, PM
emissions should also be closely monitored to confirm no longer term impacts are caused by the increased
ACI rate. In order to mitigate potential increases or deviations for the current PM emissions, it would be
reasonable to anticipate some ESP upgrades (operational changes and/or equipment optimizations) to be
required to ensure the ESP maintains its current performance.
3.2.3.Increased Contact
Increasing the degree of flue gas and PAC mixing can optimize the sorbent utilization to ensure adequate
mixing of the oxidized Hg and PAC is achieved, which potentially could result in the use of less PAC to achieve
the same Hg emission rate. Similarly, additional testing and evaluation would be required to determine the
beneficial incremental Hg removal improvement that could be achieved. Additional mixing could be
implemented by either adding static mixers into the flue gas path and/or using a more advanced injection lance
design to increase sorbent dispersion relative to a straight lance design to optimize sorbent usage.
Increased contact time could also be achieved by relocating the injection lances upstream of the APH. 5 Hg
reduction effectiveness with PAC has been shown to be temperature limited, as the absorption capacity of the
carbon is reduced at temperatures above approximately 350°F. Although flue gas temperatures downstream
of the APH are more ideal for capture, temperatures upstream of the APH are within an ideal zone for mercuric
halogens to be formed, taking advantage of the additional halogen introduced with the PAC. Furthermore, for
applications with SO3 concentrations above 5 ppm in the flue gas (as-is on the MRY units), carbon active sites
may be preferentially occupied by SO3. Although adsorption rates slow down above 350°F, injection upstream
of the APH is sometimes considered to lower the impact of SO3 competition. Furthermore, tubular APH designs
will not offer as much mixing compared to Ljungstrom type APHs; therefore, relocating the injection lances
upstream of the APH will likely only achieve added residence time for adsorption to occur in lieu of additional
mixing. Therefore, the high temperature environment and resulting residence time for injection at the APH inlet
would need to be evaluated further.
3.2.4.WFGD Re-Emission Control
Oxidized Hg is highly water soluble and exists in vapor phase at back-end equipment flue gas temperatures.
WFGDs readily capture approximately 90% of oxidized Hg because it is highly soluble, but will not remove
elemental Hg. However, re-emission of Hg is possible in some circumstances when Hg precipitates out in
scrubber solids (mercuric sulfide or equivalent) and the scrubber slurry converts some of the oxidized Hg back
into elemental form. Re
Re-emission of elemental Hg can be mitigated through the use of a sulfide-donating liquid
reagent additive that enhances the Hg capture within
in the WFGD by decreasing soluble Hg in the WFGD slurry.
Testing would be required to determine the amount of re
re-emission currently occurring based on recent
operating conditions.
3.3. MERCURY EMISSIONS SUMMARY
Presently, there is not any publicly available information to determine if improvements to any of the above
categories (individually or in combination) can achieve a Hg emission of 1.2 lb/TBtu or below on a lignite unit.
5
It should be noted that this approach is patented by Alstom, and use of this approach would need to consider
intellectual property implications.
Particulate & Mercury Control Technology Evaluation & Risk Assessment
for Proposed MATS Rule
(Page 261 of Total)
11
445a
Minnkota Power Cooperative, Inc.
USCA
Case #24-1119
Document #2058570
Milton R. Young Station Unit 2
Filed: 06/07/2024
A14559.010
PageRev.
136
204
No.:of
Final
June 23, 2023
Therefore, additional testing would be required to establish if it is feasible to achieve a 1.2 lb/TBtu Hg emission
rate with sufficient operating margin on a lignite unit and if so, develop an overall Hg compliance approach
that likely would consist of a suite of control approaches to achieve th
this rate on MRY Unit 2.
In summary, additional testing would include, but not be limited to, the following:
•
•
•
•
Hg speciation data upstream of the ESP, upstream of the WFGD and at the stack (with no controls,
current operation and maximum capacity of existing Hg control equipment, and test conditions for
other listed items)
Performance with increased concentrations of current fuel additive system, including additional
injection locations, as well as potentially testing other halogen-based fuel additives than what is
currently used.
Performance with halogenated PAC, considering capabilities of existing Hg control equipment and
increased injection rates (while also considering other test conditions for other listed items). Note that
due to the limitations of the existing equipment, a separate test skid will be required to facilitate this
testing campaign.
If WFGD re-emission is determined to be occurring based on Hg speciation upstream and downstream
of the WFGD, the performance of a re-emission additive can also be tested.
As mentioned previously, PAC suppliers have indicated that testing would be required in order to obtain any
guaranteed performance. Therefore, recommended consumption and/or injection rates to determine the
modifications and/or new systems required are not available at this time to develop the subsequent cost of the
suite of Hg controls needed to achieve adequate operating margin below a 1.2 lb/TBtu Hg emission limit on
MRY Unit 2.
Particulate & Mercury Control Technology Evaluation & Risk Assessment
for Proposed MATS Rule
(Page 262 of Total)
12
446a
Minnkota Power Cooperative, Inc.
USCA
Case #24-1119
Document #2058570
Milton R. Young Station Unit 2
Filed: 06/07/2024
PageRev.
137
204
No.:of
Final
June 23, 2023
A14559.010
4.SUMMARY
The existing MRY Unit 2 PM and Hg control technologies were found to not be capable of achieving the
proposed emissions included in the April 24, 2023, MATS rule: filterable PM emissions limit of 0.010 lb/MMBtu
and potentially 0.006 lb/MMBtu and Hg emissions limit of 1.2 lb/TBtu.
The evaluation of available PM control technologies found that an ESP rebuild would be required to achieve
the proposed PM emission limit of 0.010 lb/MMBtu considering the need for adequate operating margin.
However, testing to determine the baseline ESP inlet flow profile, ESP inlet and outlet emissions, and amount
of PM removal occurring across the WFGD will likely be required in order for a vendor to complete a detailed
qualitative study required to provide a PM emission guarantee. A baghouse will likely not provide sufficient
operating margin for compliance with the more stringent 0.006 lb/MMBtu proposed emission limit; furthermore,
this alternative was not considered to be economically feasible, and OEMs may not offer a PM emission
guarantee with sufficient operating margin. A significant outage will be required to complete an ESP rebuild
on MRY Unit 2, likely requiring the unit to be offline 12 weeks or longer as part the retrofit. Due to current postpandemic market delays and the limited number of experienced OEMs capable of completing an ESP rebuild,
it is highly likely that the implementation of this large-scale capital project will take longer than the estimated
36-month implementation schedule.
36
At the time of this evaluation, no evidence or examples demonstrating that an operating lignite unit could
achieve the proposed Hg emission limit of 1.2 lb/TBtu were found. As the Hg content of the lignite coal fired at
MRY Unit 2 can range from as low as 4.8 lb/TBtu to as high as 17.4 lb/TBtu, a wide range of flexibility in Hg
control to account for instances of firing high Hg seams of coal to consistently achieve adequate operating
margin below the proposed Hg emission limit will be required. Additional testing will also be required to
navigate the challenges of Hg speciation, flue gas temperature, flow profile/mixing, residence time, and coal
variability for application on a lignite fired unit to establish if it is feasible to achieve a 1.2 lb/TBtu Hg emission
rate with sufficient operating margin. Furthermore, PAC suppliers have indicated that testing would be required
in order to obtain any guaranteed performance. Once testing is completed, recommended
consumption/injection rates, required flexibility of the suite of Hg control approaches and the subsequent costs
of the modifications and/or new systems required to achieve adequate operating margin below a 1.2 lb/TBtu
Hg emission limit on MRY Unit 2 can be developed.
Particulate & Mercury Control Technology Evaluation & Risk Assessment
for Proposed MATS Rule
(Page 263 of Total)
13
447a
USCA Case #24-1119
Document #2058570
Filed: 06/07/2024
Page 138 of 204
ATTACHMENT F
(Page 264 of Total)
448a
USCA Case #24-1119
Document #2058570
Filed: 06/07/2024
Page 139 of 204
Analysis of
Proposed EPA MATS Residual Risk and Technology Review and
Potential Effects on Grid Reliability in North Dakota
Claire Vigesaa
aa, Director
North Dakota Transmission Authority
April 3, 2024
Assisted by:
Isaac Orr and Mitch Rolling
Center of the American Experiment
(Page 265 of Total)
449a
USCA Case #24-1119
Document #2058570
Filed: 06/07/2024
Page 140 of 204
Contents
Executive Summary....................................................................................................... 3
Section A: North Dakota’s Power Environment .............................................................................. 4
Generation Adequacy, Transmission Capacity & Load Forecast Studies......................... 5
Current North Dakota Generation Resources ............................................................... 6
Electric Generation Market & Utilization ...................................................................... 8
Grid Resource Adequacy and Threats to Growth Opportunities ..................................... 9
Grid Reliability Is Already Vulnerable ......................................................................... 10
NERC’s 2023 Reliability Risk Assessment .................................................................. 11
MISO’s Response to the Reliability Imperative (2024) ................................................. 12
Conclusion: The Long Term Reliability of the MISO Grid is Already Precarious .............. 14
Generating Units ......................................................................................................... 14
The Proposed MATS Rule Eliminates the Lignite Subcategory for Mercury Emissions .... 15
The Proposed MATS Rule Will Not Provide Meaningful Human Health or Environmental
.................................................................................................................. 16
The Administrative Record Indicates the Mercury Standard of 1.2 lb./TBtu is Technically
Unachievable for EGUs using North Dakota Lignite Coal ............................................. 20
The Administrative Record Indicates the Lower PM Standard May Also Not Be Technically
Feasible .................................................................................................................. 23
Section C: Impact of MATS Regulations- Power Plant Economics and Grid Reliability ....... 24
Power Plant Economic Impacts ................................................................................ 24
Grid Reliability Impacts ............................................................................................ 27
Section D: Modeling Results ........................................................................................ 31
Summary ................................................................................................................ 31
Modeling the Reliability and Cost of the MISO Generating Fleet Under Three Scenarios 32
Reliability in each scenario ....................................................................................... 33
Extent of the Capacity Shortfalls ........................................................................... 34
Unserved MWh in Each Scenario ........................................................................... 37
The Social Cost of Blackouts Using the Value of Lost Load (VoLL) ............................ 37
1
(Page 266 of Total)
450a
USCA Case #24-1119
Document #2058570
Filed: 06/07/2024
Page 141 of 204
Hours of Capacity Shortfalls ................................................................................. 39
Cost of replacement generation................................................................................ 39
Conclusion: ................................................................................................................ 48
Appendix 1: Modeling Assumptions .............................................................................. 49
Appendix 2: Capacity Retirements and Additions in Each Scenario ............................. 53
Appendix 3: Replacement Capacity Based on EPA Methodology for Resource Adequacy
.............................................................................................................................. 58
Appendix 4: Resource Adequacy in Each Scenario ..................................................... 59
2
(Page 267 of Total)
451a
USCA Case #24-1119
Document #2058570
Filed: 06/07/2024
Page 142 of 204
Executive Summary
On behalf of the North Dakota Transmission Authority (NDTA), the Center of the American
Experiment prepared this study to analyze the potential impacts of EPA’s proposed revisions to the
Mercury and Air Toxics Standards (MATS) Rule on North Dakota’s power generation and power
grid reliability.
Our primary finding, which is drawn substantially from the Rule’s administrative record, is that
the proposed changes are likely not technologically feasible for lignite-based power generation
facilities, will foreseeably result in the retirement of lignite power generation units, and will
negatively impact consumers of electricity in the Midcontinent Independent Systems Operator
(MISO) system by reducing the reliability of the electric grid and increasing costs for ratepayers.
Our analysis builds upon grid reliability data and forecasts from the Federal Energy Regulatory
Commission (FERC) and the North American Electric Reliability Corporation (NERC), and it
assesses what is likely to happen to grid reliability if the MATS Rule forces some or all of North
Dakota’s lignite power generation units to retire. We determined that the closure of lignite-fired
powered power plants in the MISO footprint would increase the severity of projected future
capacity shortfalls, i.e. rolling blackouts, in the MISO system even if these resources are replaced
with wind, solar, battery storage, and natural gas plants. In reaching that determination, we have
accepted EPA’s estimates for capacity values of intermittent and thermal resources.
Moreover, building such replacement resources would come at a great cost to MISO ratepayers.
The existing lignite facilities are largely depreciated assets that generate large quantities of
dispatchable, low-cost electricity. Replacing these lignite facilities with new wind, solar, natural
gas, and battery storage facilities would cost an additional $1.9 billion to $3.8 billion through 2035,
compared to operating the current lignite facilities under status quo conditions.
MISO residents would also suffer economic damages from the increased severity of rolling
blackouts. Accounting for projected increases in demand for electricity, we assess that if the MATS
Rule goes into effect in the near future, by 2035, the MISO grid will experience up to an additional
73,699 megawatt hours (MWh) of unserved load, with an economic cost of up to $1.05 billion
based on the Value of Lost Load (VoLL) criteria, which can be thought of as the Social Cost of
Blackouts.
3
(Page 268 of Total)
452a
USCA Case #24-1119
Document #2058570
Filed: 06/07/2024
Page 143 of 204
Section A: North Dakota’s Power Environment
North Dakota Transmission Authority (NDTA)
The North Dakota Transmission Authority (NDTA) was established in 2005 by the North Dakota
Legislative Assembly at the behest of the North Dakota Industrial Commission. Its primary
mandate is to facilitate the growth of transmission infrastructure in North Dakota. The Authority
serves as a pivotal force in encouraging new investments in transmission by aiding in facilitation,
financing, development, and acquisition of transmission assets necessary to support the expansion
of both lignite and wind energy projects in the state.
Operating as a 'builder of last resort,' the NDTA intervenes when private enterprises are unable or
unwilling to undertake transmission projects on their own. Its membership, as stipulated by statute,
comprises the members of the North Dakota Industrial Commission, including Governor, Attorney
General, and Agriculture Commissioner.
Statutory authority for the North Dakota Transmission Authority (NDTA) is enshrined in Chapter
17-05 of the North Dakota Century Code. Specifically, Section 17-05-05 N.D.C.C. outlines the
powers vested in the Authority, which include:
1. Granting or loaning money.
2. Issuing revenue bonds, with an upper limit of $800 million.
3. Entering into lease-sale contracts.
4. Owning, leasing, renting, and disposing of transmission facilities.
5. Entering contracts for the construction, maintenance, and operation of transmission
facilities.
6. Conducting investigations, planning, prioritizing, and proposing transmission corridors.
7. Participating in regional transmission organizations.
In both project development and legislative initiatives, the North Dakota Transmission Authority
(NDTA) plays an active role in enhancing the state's energy export capabilities and expanding
transmission infrastructure to meet growing demand within North Dakota. Key to its success is a
deep understanding of the technical and political complexities associated with energy transmission
from generation sources to end-users. The Authority conducts outreach to existing transmission
system owners, operators, and potential developers to grasp the intricacies of successful
transmission infrastructure development. Additionally, collaboration with state and federal
officials is essential to ensure that legislation and public policies support the efficient movement
of electricity generated from North Dakota's abundant energy resources to local, regional, and
national markets.
As the energy landscape evolves with a greater emphasis on intermittent generation resources,
transmission planning becomes increasingly intricate. Changes in the generation mix and the
redistribution of generation resource locations impose strains on existing transmission networks,
4
(Page 269 of Total)
453a
USCA Case #24-1119
Document #2058570
Filed: 06/07/2024
Page 144 of 204
potentially altering flow directions within the network. A significant aspect of the Authority's
responsibilities involves closely monitoring regional transmission planning efforts. This includes
observing the activities of regional transmission organizations (RTOs) recognized by the Federal
Energy Regulatory Commission (FERC), which oversee the efficient and reliable operation of the
transmission grid. While RTOs do not own transmission assets, they facilitate non-discriminatory
access to the electric grid, manage congestion, ensure reliability, and oversee planning, expansion,
and interregional coordination of electric transmission.
Many North Dakota service providers are participants in the Midcontinent Independent System
Operator (MISO), covering the territories of several utilities and transmission developers.
Additionally, some entities are part of the Southwest Power Pool (SPP), broadening the scope of
transmission planning. Together, North Dakota utilities and transmission developers contribute to
a complex system overseeing the transmission of over 200,000 megawatts of electricity across
100,000 miles of transmission lines, serving homes and businesses in multiple states.
MISO and SPP also operate power markets within their respective territories, managing pricing
for electricity sales and purchases. This process determines which generating units supply
electricity and provide ancillary services to maintain voltage and reliability. Overall, the NDTA's
involvement in regional transmission planning and coordination is crucial for ensuring the
reliability, efficiency, and affordability of electricity transmission across North Dakota and beyond.
FERC-Recognized Regional Transmission Organizations and Independent System Operators
(www.ferc.gov)
Generation Adequacy, Transmission Capacity & Load Forecast Studies
The North Dakota Transmission Authority (NDTA) conducts periodic independent evaluations to
assess the adequacy of transmission infrastructure in the state. In 2023, the NDTA commissioned
two generation resource adequacy studies, one for the Midcontinent Independent System Operator
(MISO) and another for the Southwest Power Pool (SPP). Additionally, the NDTA recently
completed a generation resource adequacy study examining the impact of the EPA's proposed
Mercury and Air Toxics Standards (MATS) Rule. A transmission capacity study commissioned by
the NDTA is scheduled for completion in the summer of 2024.
Regular load forecast studies are also commissioned by the NDTA, with the most recent study
5
(Page 270 of Total)
454a
USCA Case #24-1119
Document #2058570
Filed: 06/07/2024
Page 145 of 204
completed in 2021. This study, conducted by Barr Engineering, provided an update to the Power
Forecast 2019, projecting energy demand growth over the next 20 years. The 2021 update
incorporates factors such as industries expressing interest in locating in North Dakota, abundant
natural gas availability from the Bakken wells, and the potential for carbon capture and
sequestration from various sources. The 2021 update and the full study can be obtained from the
North Dakota Industrial Commission website: Power Forecast Study – 2021 Update,
https://www.ndic.nd.gov/sites/www/files/documents/Transmission-Authority/Publications/taannualreport-21.pdf
The Power Forecast 2021 Update projects a 10,000 GWhr increase in energy demand over the next
two decades under the consensus scenario, requiring approximately 2200 to 2500 MW of
additional capacity to meet demand. These projections are closely tied to industrial development
forecasts and are coordinated with forecasts used by the North Dakota Pipeline Authority. These
projections were highly dependent on industrial development and are premised on new federal
regulations not forcing the early retirement of even more electric generation units.
Meeting this growing demand poses significant challenges for utilities responsible for providing
reliable service. While there is considerable interest in increasing wind and solar generation,
natural gas generation is also essential to provide stability to weather-dependent renewable
sources. Importantly, load growth across the United States is driven by the electrification of
transportation, heating/cooling systems, data centers, and manufacturing initiatives.
Studies consistently highlight the critical importance of maintaining existing dispatchable
generation to prevent grid reliability failures. Ensuring uninterrupted power supply is paramount
for national security, public safety, food supply, and overall economic stability. The NDTA's
ongoing assessments and proactive planning are crucial for meeting the evolving energy needs of
North Dakota while maintaining grid reliability and resilience.
The timing and implementation of resources to meet this growing demand is a significant challenge
for the utilities. Importantly, electric demand growth across the United States over the next several
decades is projected to be dramatic due to the electrification of transportation, home
heating/conditioning, data center and artificial intelligence centers, as well as the effort to bring
manufacturing back to the USA. Studies by NDTA and others all point to the critical need to keep
all existing dispatchable generation online to avoid catastrophic grid reliability failures, and have
been warning that the push to force the retirement of reliable, dispatchable fossil fuel generation
units is occurring before it is projected there will be sufficient intermittent units in place to cover
the anticipated increase in demand. And when demand for electricity exceeds the dispatchable
supply, the foreseeable result will be blackouts or energy rationing.
Current North Dakota Generation Resources
Here is the current breakdown of North Dakota's generation resources:
1. Renewable Generation:
• Wind Generation: North Dakota has 4,250 MW of wind generation capacity in
service, making it a significant contributor to the state's renewable energy portfolio.
The average capacity factor for these generating facilities is 40% to 42%.
• The 4,000 MW of wind generation receives a reduced capacity accreditation in the
ISO of approximately 600 MW since it is intermittent. This is representative of the
6
(Page 271 of Total)
455a
USCA Case #24-1119
2.
3.
4.
5.
Document #2058570
Filed: 06/07/2024
Page 146 of 204
amount that is estimated to be available for the peak demand in the summer.
• Solar Generation: Although North Dakota currently lacks utility-scale solar
generation facilities in operation, some projects are in the queues of regional
transmission organizations like MISO and SPP, indicating potential future
development in this area.
Thermal Coal Generation:
• North Dakota currently operates thermal coal generation at six locations,
comprising a total of 10 generating units with a combined capacity of
approximately 4,048 MW.
• The average capacity factor for these generating plants ranged from 65% to 91% in
2021, excluding the retired Heskett Station.
• Rainbow Energy operates the Coal Creek Station and the DC transmission line that
transports ND produced energy to the Minneapolis region. Rainbow Energy is
assessing a CO2 capture project for the facility. In addition, approximately 400
MW of wind generation is planned for that area of McLean County to utilize the
capacity on the DC line.
Hydro Generation:
• North Dakota has one hydro generation site equipped with 5 units, boasting a total
capacity of 614 MW.
• However, the average capacity factor declined to approximately 43% in 2021 due
to limitations imposed by water flow in the river, particularly during drought years.
Natural Gas Generation:
• North Dakota operates three sites for electric generation utilizing natural gas,
comprising 21 generating units with a total capacity of 596.3 MW.
• These units include reciprocating engines and gas turbines, with variation in
summer capacity influenced by the performance of gas generators in hot weather.
• Total natural gas generation in North Dakota remained steady from 2019 through
2021, amounting to 1.445 GWhr in 2021.
Total Generation:
• The combined total capacity of all types of utility-scale generation in North Dakota
is approximately 8,863 MW.
• Wind generation receives a reduced capacity accreditation in the ISO of
approximately 600 MW due to its intermittent nature, down from 4,250MW of
installed capacity, representing the estimated amount available during peak summer
demand. However, newer installations have demonstrated slightly higher capacity
for accreditation.
This comprehensive overview underscores the diverse mix of generation resources in North
Dakota, with significant contributions from wind, coal, hydro, and natural gas. Continued
assessment and adaptation to evolving energy needs and market dynamics are essential for
ensuring a reliable and sustainable energy future for the state.
7
(Page 272 of Total)
456a
USCA Case #24-1119
Document #2058570
Filed: 06/07/2024
Page 147 of 204
Electric Generation Market & Utilization
In recent decades, North Dakota has emerged as a significant exporter of electricity, primarily
fueled by the development of thermal lignite generation in the western part of the state since the
1960s. Concurrently, transmission infrastructure has been expanded to facilitate the export of
electricity to markets predominantly situated to the east. Moreover, North Dakota has garnered
recognition as an excellent source of wind generation, leading to additional transmission
development to accommodate the transmission of this renewable energy to markets.
According to data from the Energy Information Administration, in 2020, North Dakota generated
a total of 42,705 MWh of electricity from all sources, with 46% of this total being exported beyond
the state's borders over two large high voltage direct current lines (HVDC), which serve load in
the neighboring state of Minnesota and multiple 345kv and 230kv alternating current (AC)
transmission lines serving surrounding states. Wind generation accounted for 31% of North
Dakota's total electricity generation in 2020, highlighting the growing significance of renewable
8
(Page 273 of Total)
457a
USCA Case #24-1119
Document #2058570
Filed: 06/07/2024
Page 148 of 204
energy in the state's energy portfolio. Notably, industrial demand in North Dakota experienced
substantial growth, expanding by nearly 11% in 2020.
While demand for electricity in markets outside of North Dakota, and in most areas within the
state, has remained relatively stable in recent years, the Bakken region has witnessed notable
demand growth. Over the past 16 years, total electricity generation in North Dakota has increased
from 29,936 MWh to 42,705 MWh, with retail sales climbing from 10,516 MWh to 22,975 MWh.
This growth is primarily attributed to the burgeoning development of the Bakken oil fields.
Industrial consumption in North Dakota also witnessed a robust increase of over 11% in 2020,
with power forecasts projecting a continued upward trajectory in demand.
Generation by Type in North Dakota
35000
30000
Thousand MWh
25000
20000
15000
10000
5000
0
2001 2002 2003 2004 2005 2006 2007 2008 2009 2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021
Coal
Natural Gas
Hydroelectric
Wind
Grid Resource Adequacy and Threats to Growth Opportunities
In 2023, both the MISO and SPP grid operators issued warnings about the adequacy of generation
resources to meet peak demand situations. This highlights a growing concern that the desired pace
of change towards a more sustainable energy future is outpacing the achievable pace of
transformation. This concern is underscored by the stark increase in grid events necessitating the
activation of emergency procedures. For instance, prior to 2016, MISO had no instances
requiring the use of emergency procedures, but since then, there have been 48 Maximum
Generation events.
Many experts in the industry project that, despite ambitious goals, realistic scenarios still foresee
a substantial dependence on fossil fuel energy—potentially up to 50%—even by 2050. While
efforts to decarbonize fossil fuel resources are underway, achieving complete carbon neutrality or
a fully renewable energy grid by 2050 appears increasingly unlikely. The scalability and
9
(Page 274 of Total)
458a
USCA Case #24-1119
Document #2058570
Filed: 06/07/2024
Page 149 of 204
affordability of storage technology, particularly for renewable energy sources, remain significant
challenges.
In response to these challenges, Governor Burgum has issued a visionary goal for North Dakota
to achieve carbon neutrality in its combined energy and agriculture sectors by 2030. Governor
Burgum's approach emphasizes innovation over mandates, aiming to attract industries and
technologies that support this goal to the state. The initiative seeks to leverage advancements in
carbon capture and sequestration technologies to retain conventional generation in North Dakota
while also promoting sustainable agricultural practices and other innovative solutions, such as CO2
sequestration from ethanol production and enhanced oil recovery. These efforts demonstrate a
commitment to proactive and pragmatic solutions to address the complexities of achieving carbon
neutrality in the energy and agriculture sectors.
The state's vision for a decarbonized energy generation future faces significant challenges due to
the individual and cumulative impact of expansive federal rulemakings. These regulations would
curtail the flexibility to achieve the 2030 goal through the deployment of carbon capture and
sequestration (CCS) technologies. Furthermore, they would impose financial burdens on electric
cooperatives and utilities with limited resources, diverting investment away from future growth
options toward retrofitting existing facilities with costly emissions technologies to comply with
new federal requirements.
This regulatory burden not only impedes progress towards decarbonization but also introduces
opportunity costs for utilities and cooperatives. The funds that would otherwise be allocated for
future growth and innovation in clean energy solutions are instead diverted to compliance
measures, hindering the state's ability to transition to a more sustainable energy future efficiently
and effectively.
Ultimately, the restrictive nature of these federal rulemakings poses a significant obstacle to North
Dakota's efforts to achieve its decarbonization goals and undermines the state's vision for a cleaner
and more sustainable energy generation landscape. It highlights the need for a balanced approach
to regulation that supports innovation and investment in carbon reduction technologies while also
allowing for continued economic growth and development in the energy sector.
Grid Reliability Is Already Vulnerable
The fragility of grid reliability is already evident as warnings have been issued due to the declining
ratio of dispatchable and intermittent generation supplies. This concerning trend poses significant
threats to public safety, economic stability, and national security. Grid reliability is vital for
ensuring continuous access to essential services, such as food production and military operations.
Dispatchable reliable generation forms the backbone of grid stability, enabling the balancing of
supply and demand fluctuations. Failure to address these reliability concerns will compromise
critical infrastructure and expose society to substantial risks. Urgent action is required to safeguard
grid reliability and mitigate the potential consequences for public safety and national security.
10
(Page 275 of Total)
459a
USCA Case #24-1119
Document #2058570
Filed: 06/07/2024
Page 150 of 204
NERC’s 2023 Reliability Risk Assessment
The North American Electric Reliability Council’s 2023 Reliability Risk Assessment 1 are
concerning as demonstrated in the slides below. The electrification of the US economy, data & AI
center growth and the build it at home initiatives will substantially increase the demand for
electricity generation and transmission.
NERC’s 2023 Summer Reliability Assessment warns that two-thirds of North America is at risk
of energy shortfalls this summer during periods of extreme demand. While there are no high-risk
areas in this year’s assessment, the number of areas identified as being at elevated risk has
increased. The assessment finds that, while resources are adequate for normal summer peak
demand, if summer temperatures spike, seven areas — the U.S. West, SPP and MISO, ERCOT,
SERC Central, New England and Ontario — may face supply shortages during higher demand
levels.
“Increased, rapid deployment of wind, solar and batteries have made a positive impact,” said Mark
Olson, NERC’s manager of Reliability Assessments. “However, generator retirements continue to
increase the risks associated with extreme summer temperatures, which factors into potential
supply shortages in the western two-thirds of North America if summer temperatures spike.”
The North American Electric Reliability Corporation (NERC) recently released its 2023 LongTerm Reliability Assessment (LTRA), which found MISO is the region most at risk of capacity
shortfalls in the years spanning from 2024 to 2028 due to the retirement of thermal resources with
inadequate reliable generation coming online to replace them. 2
1
NERC. "North American Reliability Assessment." North American Electric Reliability Corporation, May 2023,
https://www.nerc.com/news/Headlines%20DL/Summer%20Reliability%20Assessment%20Announcement%20May
%202023.pdf.
2
North American Electric Reliability Corporation, “2023 Long-Term Reliability Assessment,” December, 2023,
https://www.nerc.com/pa/RAPA/ra/Reliability%20Assessments%20DL/NERC_LTRA_2023.pdf.
11
(Page 276 of Total)
460a
USCA Case #24-1119
Document #2058570
Filed: 06/07/2024
Page 151 of 204
MISO is the region most at risk of rolling blackouts in the near future.
In 2028, MISO is projected to have a 4.7 GW capacity shortfall if expected generator retirements
occur despite the addition of new resources that total over 12 GW, leaving MISO at risk of load
shedding during normal peak conditions. This is because the new wind and solar resources that are
being built have significantly lower accreditation values than the older coal, natural gas, and
nuclear resources that are retiring. 3
MISO’s Response to the Reliability Imperative (2024)
On February 26, 2024, the Midcontinent Independent System Operator (MISO) released “MISO’s
Response to the Reliability Imperative 4,” a report which is updated periodically to reflect changing
conditions in the 15-state MISO region that extends through the middle of the U.S. and into
Canada. MISO’s new report explains the disturbing outlook for electric reliability in its footprint
unless urgent action is taken. The main reasons for this warning are the pace of premature
un
retirements of dispatchable fossil generation and the resulting loss of accredited capacity and
reliability attributes.
From 2014 to 2024, surplus reserve margins in MISO have been exhausted through load growth
and unit retirements. Since 2022, MISO has been operating near the level of minimum reserve
3
Midcontinent Independent Systems Operator, “MISO’s Response to the Reliability Imperative,” February, 2024,
https://cdn.misoenergy.org/2024%20Reliability%20Imperative%20report%20Feb.%2021%20Final504018.pdf?v=20
240221104216.
4
MISO. "MISO’S Response to the Reliability Imperative Updated February 2024." MISO, February 2024,
https://cdn.misoenergy.org/2024%20Reliability%20Imperative%20report%20Feb.%2021%20Final504018.pdf?v=20
240221104216.
12
(Page 277 of Total)
461a
USCA Case #24-1119
Document #2058570
Filed: 06/07/2024
Page 152 of 204
margin requirements. 5
According to the Reliability Imperative, MISO uses an annual planning tool called the OMS-MISO
Survey to compile information about new resources utilities and states plan to build and older
assets they intend to retire. The 2023 survey shows the region’s level of “committed” resources
declining going forward, with a potential shortfall of 2.1 GW occurring as soon as 2025 and
growing larger over time.
MISO lists U.S. Environmental Protection Agency (EPA) regulations that prompt existing coal and
gas resources to retire sooner than they otherwise would as a compounding reason for growing
challenges to grid reliability. From the report, there is a section titled, “EPA Regulations Could
Accelerate Retirements of Dispatchable Resources,” which states:
“While MISO is fuel- and technology-neutral, MISO does have a responsibility to inform
state and federal regulations that could jeopardize electric reliability. In the view of MISO,
several other grid operators, and numerous utilities and states, the U.S. Environmental
Protection Agency (EPA) has issued a number of regulations that could threaten
reliability in the MISO region and beyond.
In May 2023, for example, EPA proposed a rule to regulate carbon emissions from all
existing coal plants, certain existing gas plants and all new gas plants. As proposed, the
rule would require existing coal and gas resources to either retire by certain dates or else
retrofit with costly, emerging technologies such as carbon-capture and storage (CCS) or
co-firing with low-carbon hydrogen.
MISO and many other industry entities believe that while CCS and hydrogen co-firing
technologies show promise, they are not yet viable at grid scale — and there are no
assurances they will become available on EPA’s optimistic timeline. If EPA’s proposed rule
drives coal and gas resources to retire before enough replacement capacity is built with
the critical attributes the system needs, grid reliability will be compromised. The proposed
rule may also have a chilling effect on attracting the capital investment needed to build
new dispatchable resources.”
Despite these reliability warnings issued by MISO, EPA did not consider the reliability impacts of
the proposed MATS rules required emission control upgrades and additions to units. It is likely
that many units that would have to incur millions of dollars to retrofit emissions controls to comply
with this proposal would not do so. 6
In light of these shortcomings, the NDTA contracted with Center of the American Experiment to
model the impacts of the MATS rules on resource adequacy, reliability, and cost of electricity to
consumers. The findings of this analysis are detailed in Section D.
5
Midcontinent Independent Systems Operator, “MISO’s Response to the Reliability Imperative,” February, 2024,
https://cdn.misoenergy.org/2024%20Reliability%20Imperative%20report%20Feb.%2021%20Final504018.pdf?v=20
240221104216.
6
Rae E. Cronmiller, “Comments on Proposed National Emission Standards for Hazardous Air Pollution: Coal-and
Oil-Fired Electric Utility Steam Generating Units Review of the Residual Risk and Technology Review,” The National
Rural Electric Cooperative Association, June 23, 2023, Attention Docket ID NO. EPA-HQ-OAR-2018-0794.
13
(Page 278 of Total)
462a
USCA Case #24-1119
Document #2058570
Filed: 06/07/2024
Page 153 of 204
Conclusion: The Long Term Reliability of the MISO Grid is Already
Precarious
As the state agency responsible for the strategic buildout and framework of electricity distribution,
the North Dakota Transmission Authority (NDTA) is deeply concerned about the potential impact
of federal rulemakings on the generation fleet in North Dakota and the ability to support future
growth initiatives. The current strain on the electric transmission system due to load growth is
already posing significant challenges to grid reliability, particularly in areas facing transmission
constraints and limited access to dispatchable generation.
The escalating frequency of grid events requiring emergency procedures, such as the 48 Maximum
Generation events in MISO since 2016 and the increasing number of alerts issued by SPP, over
194 alerts issued in 2022, underscores the urgency of addressing transmission congestion and
bolstering reliable generation capacity. The economic growth and security of North Dakota are
directly tied to the timely development of new transmission facilities in tandem with dependable
dispatchable electric generation.
The impacts of grid strain extend beyond the energy sector, affecting multiple industries,
ratepayers, and overall economic stability. Volatile wholesale prices and transmission congestion
undermine business operations and investment confidence, hindering economic growth and
prosperity. Moreover, reliable electricity supply is critical for essential services, including
Department of Defense facilities, underscoring the broader implications of grid reliability issues.
Achieving a balanced generation portfolio requires careful consideration of reliability and
resilience under all weather conditions, especially amidst the electrification of America and the
imperative to safeguard public welfare and security.
Additionally, over 50% of the electricity generated in North Dakota is exported to neighboring
states, magnifying the ripple effects of any regulations impacting dispatchable electricity
generation resources. By responsibly managing the generation portfolio and prioritizing generation
adequacy, North Dakota and the nation can seize significant opportunities for economic growth,
innovation, and sustainable development.
Section B: The Proposed MATS Rule Will Dramatically
Lignite Electric Generating Units
The revised MATS Rule includes a proposal to eliminate the “low rank coal” subcategory
established for lignite-powered facilities by requiring these facilities to comply with the same
mercury emission limitation that currently applies to Electric Generating Units (EGUs)
combusting bituminous and subbituminous coals, which is 1.2 pounds per trillion British thermal
units of heat input (lb/TBtu). EPA’s proposal is a substantial lowering of the current mercury
14
(Page 279 of Total)
463a
USCA Case #24-1119
Document #2058570
Filed: 06/07/2024
Page 154 of 204
limitation for lignite fired EGUs, which is 4.0 lb/TBtu. 7,8 The proposal also includes a significant
reduction in the particulate matter standard applicable to all existing units from 0.03 lb/mmBtu to
0.01 lb/mmBtu. Because North Dakota is somewhat unique to the degree in which its power
generation relies upon lignite coal, the compliance costs for this Rule, while likely to substantial
for coal plants all around the country, will be most acutely inflicted upon North Dakota’s lignitebased power generation facilities.
Numerous comments in the administrative record, including from the regulated facilities in North
Dakota and the North Dakota Department of Environmental Quality, provided EPA with notice
that the new emission standards are not technologically feasible, will impose crippling compliance
costs that may require facility retirement, and will result in a significant portion of the dispatchable
power provided by coal-generation facilities being taken off the grid. This report will summarize
some of those concerns in the section that follows, however, a full study of the technological
feasibility of complying with the new emissions standards is beyond the scope of this report. For
purposes of this report, we assume the regulated facilities and state regulator were forthright in
their concerns about the feasibility of lignite-based facilities meeting the new standards.
The Proposed MATS Rule Eliminates the Lignite Subcategory for Mercury
Emissions
Although the Proposed Rule affects all coal electrical generating utilities (EGUs), reducing the
lignite emissions standards to levels of other coal ranks effectively eliminates the lignite subcategory and would have drastic consequences for North Dakota's lignite EGU industry. 9 EPA
original decision to regulate separately a subcategory of lignite units was well-supported with
documented information and a thorough analysis. In its comments filed in this Docket, on June
22, 2023, the North Dakota Department of Environmental Quality (hereafter DEQ) encouraged
EPA to review that prior determination and reaffirm the need for a lignite subcategory and the
associated emissions standards. 10
Specifically, DEQ summarized the original MATS proposal in 2011 and final MATS rule in 2012,
in which EPA presented a body of evidence in support of the lignite category. For example, the
EPA wrote:
“For Hg emissions from coal-fired units, we have determined that different emission
limits for the two subcategories are warranted. There were no EGUs designed to burn
a non-agglomerating virgin coal having a calorific value (moist, mineral matter free
7
Jason Bohrer, “Comments on National Emission Standards for Hazardous Air Pollutants: Coal- and Oil-Fired
Electric Utility Steam Generating Units Review of the Residual Risk and Technology Review, 88 Fed. Reg. 24854
(Apr. 24, 2023), June 23, 2024.
8 8
J. Cichanowicz et al., Technical Comments on National Emission Standards for Hazardous Air Pollutants: Coaland Oil-fired Electric Utility Steam Generating Units Review of Residual Risk and Technology, (June 2, 2023)
(“Cichanowicz Report”).
9
EPA characterizes lignite as "low rank virgin coal". 88 Fed. Reg. 24,854, 24,875. For this comment letter, lignite
will be used in place of low rank virgin coal.
10
David Glatt, P.E., “Comments on the Proposed Rulemaking Titled "National Emission Standards for Hazardous Air
Pollutants: Coal- and Oil-Fired Electric Utility Steam Generating Units Review of the Residual Risk and Technology
Review" (Docket ID No. EPA-HQOAR-2018-0794),” On Behalf of the North Dakota Department of Environmental
Quality, June 22, 2023.
15
(Page 280 of Total)
464a
USCA Case #24-1119
Document #2058570
Filed: 06/07/2024
Page 155 of 204
basis) of 19,305 kJ/kg (8,300 Btu/lb) or less in an EGU with a height-to-depth ratio
of 3.82 or greater among the top performing 12 percent of sources for Hg emissions,
indicating a difference in the emissions for this HAP from these types of units.
The boiler of a coal-fired EGU designed to burn coal with that heat value is larger
than a boiler designed to burn coals with higher heat values to account for the larger
volume of coal that must be combusted to generate the desired level of electricity.
Because the emissions of Hg are different between these two subcategories, we are
proposing to establish different Hg emission limits for the two coal-fired
subcategories.”
As explained by DEQ, EPA has not provided any scientific justification to support abandoning the
lignite subcategory and requiring those facilities to comply with the emission standards applicable
to other coal types. The most EPA identified in support of its proposal was a reference to
information nearly 30 years old, which predated EPA’s original determination.
The Proposed MATS Rule Will Not Provide Meaningful Human Health or
Environmental B
Section 112(f)(2) of the CAA directs EPA to assess the remaining residual public health and
environmental risks posed by hazardous air pollutants (HAPs) emitted from the EGU source
category. 11 Further regulation under MATS is required only if that residual risk assessment
demonstrates that a tightening of the current HAP emission limitations is necessary to protect
public health with an ample margin of safety or protect against adverse environmental effects.
When reviewing whether to revise the MATS Rule, EPA determined that further regulation of
mercury and other HAPs would be unnecessary to address any remaining residual risk from any
affected EGU within the source category. The stringent standards based on state-of-the-art control
technologies that are currently imposed on coal-fired EGUs have already achieved significant
reductions in HAP emissions. As EPA itself noted, the MATS rule has achieved steep reductions
in HAP emission levels since 2010, including a 90 percent reduction in mercury, 96 percent
reduction in acid gas HAPs, and an 81 percent reduction in non-mercury metal HAPs. 12
Data from EPA and the U.N Global Mercury Assessment show mercury emissions from U.S.
power plants are now so low they accounted for only 0.12 percent of global mercury emissions in
2022, assuming all other sources remained constant at 2018 levels. 13 These data demonstrate that
11
J. Cichanowicz et al., Technical Comments on National Emission Standards for Hazardous Air Pollutants: Coaland Oil-fired Electric Utility Steam Generating Units Review of Residual Risk and Technology, at 29, Figure 6-7 (June
2, 2023) (“Cichanowicz Report”).
12
Fact Sheet, EPA’s Proposal to Strengthen and Update the Mercury and Air Toxics Standards for Power Plants,
https://www.epa.gov/system/files/documents/2023-04/Fact%20Sheet_MATS%20RTR%20Proposed%20Rule.pdf
13
United Nations, “Global Mercury Assessment 2018,” UN Environment Programme, August 21, 2019,
https://wedocs.unep.org/bitstream/handle/20.500.11822/27579/GMA2018.pdf?sequence=1&isAllowed=y
16
(Page 281 of Total)
465a
USCA Case #24-1119
Document #2058570
Filed: 06/07/2024
Page 156 of 204
US mercury emissions from power plants are lower than global cremation emissions, and North
Dakota coal facilities emitted 9.25 times less mercury in 2021 than global cremations in 2018. 14
As the above chart indicates: the annual mercury emissions from global cremations (where the
mercury primarily comes from individuals with dental fillings) exceed the mercury annually
emitted by all coal-fired EGUs in the United States combined, and is orders of magnitude more
than the mercury emissions from all coal-fired EGUs in North Dakota. 15
Moreover, the Administrative Record indicates EPA has performed a comprehensive and detailed
risk assessment that clearly documents the negligible remaining residual risks posed by the very
low amount of HAPs now being emitted by coal-fired EGUs. EPA first performed that risk
assessment in 2020, which concluded that “both the actual and allowable inhalation cancer risks
to the individual most exposed were below 100-in
in-1 million, which is the presumptive limit of
14
ERM Sustainability Initiative, “Benchmarking Air Emissions of the 100 Largest Power Producers in the United
States,” Interactive Tool, accessed February 29, 2024, https://www.sustainability.com/thinking/benchmarking-airemissions-100-largest-us
us-power-producers/
15
UN Environmental Programme. (2018). Global Mercury Report 2018, Technical Background Report to the Global
Mercury Assessment. https://www.unenvironment.org/resources/publication/global-mercury-assessment-technicalbackground-report
17
(Page 282 of Total)
466a
USCA Case #24-1119
Document #2058570
Filed: 06/07/2024
Page 157 of 204
acceptability” for protecting public health with an adequate margin of safety. 16 Similarly, EPA’s
risk assessment supports the conclusion that residual risks of HAP emissions from the EGU source
category are “acceptable” for other potential public health effects, including both chronic and acute
non-cancer effects. 17
These conclusions have been confirmed by the detailed reevaluation of the 2020 risk assessment
that the Agency is now completing as part of the current rule-making action. That EPA
reevaluation clearly demonstrates that the 2020 risk assessment did not contain any significant
methodological or factual errors that could call into question the results and conclusions reached
in the 2020 risk assessment. Most notably, EPA used well-accepted approaches and methodologies
for performing a residual risk analysis that adhere to the requirements of the statute and are
consistent with prior residual risk assessments performed by EPA over the years for other industry
sectors. 18
The results from both residual risk assessments can lead to only one rational conclusion: the current
MATS limitations provide an ample margin of safety to protect public health in accordance with
CAA section 112.
The DEQ filed comments addressing these points and asking EPA to provide a better health benefit
justification than the rationale currently included in the Regulatory Impacts Analysis (RIA). 19 In
particular, DEQ noted that EPA cannot rely on non-HAPs' co-benefits to justify the Proposed Rule,
and EPA has not identified any HAP-related benefits that would be sufficient to justify the
Proposed Rule. The agency also voiced skepticism over what it called EPA' s suspect
characterization of the health benefits that it identified, which is quoted below:
While the screening analysis that EPA completed suggests that exposures
associated with mercury emitted from EGUs, including lignite-fired EGUs, are
below levels of concern from a public health standpoint, further reductions in these
emissions should further decrease fish burden and exposure through fish
consumption including exposures to subsistence fishers. 20
DEQ’s well-founded concern is that EPA’s admission that current exposure associated with
mercury is below levels of concern is directly inconsistent with, not support of, EPA’s proposal
for a lower standard.
DEQ commented that this theme, unfortunately, is consistent across the entire "Benefits Analysis"
section of the RIA, citing another example of this inconsistency, which is quoted below:
“Regarding the potential benefits of the rule from projected HAP reductions,
we note that these are discussed only qualitatively and not quantitatively
16
88 Fed. Reg. at 24,865.
Id. at 24,865-66.
18
88 Fed. Reg. at 24,865.
19
Regulatory Impact Analysis for the Proposed National Emission Standards for Hazardous Air Pollutants: Coal- and
Oil-Fired Electric Utility Steam Generating Units Review of the Residual Risk and Technology Review (Apr. 2023),
Docket ID: EPA-HQ-OAR-2018-0794-5837.
20
Id. At p. 0-8.
17
18
(Page 283 of Total)
467a
USCA Case #24-1119
Document #2058570
Filed: 06/07/2024
Page 158 of 204
....Overall, the uncertainty associated with modeling potential of benefits of
mercury reduction for fish consumers would be sufficiently large as to
compromise the utility of those benefit estimates-though importantly such
uncertainty does not decrease our confidence that reductions in emissions
should result in reduced exposures of HAP to the general population,
including methylmercury exposures to subsistence fishers located near these
facilities. Further, estimated risks from exposure to non-mercury metal HAP
were not expected to exceed acceptable levels, although we note that these
emissions reductions should result in decreased exposure to HAP for
individuals living near these facilities.” 21
Comments filed by the Lignite Energy Council (LEC) further emphasize the point. LEC stated
that according to the risk review EPA conducted in 2020, which EPA has proposed to reaffirm, the
risks from current emissions of hazardous air pollutants (HAP) emitted by coal-fired power plants
are several orders of magnitude below what EPA deems sufficient to satisfy the Clean Air Act. 22
LEC points out that EPA has for decades found risks to be acceptable with an ample margin of
safety if maximum individual excess cancer risks presented by any single facility is less than “100in-1 million.” In comparison, EPA’s analysis of the coal- and oil-fired electric utility source
category recognizes the risk it presents is now at one tenth of that acceptable level, with a
maximum risk from any individual facility of “9-in-1 million.”
However, even that value vastly overstates the risk associated with coal-fired power plants. The
“9-in-1 million” risk level identified by EPA is only associated with a single, uncontrolled, residual
oil-fired facility located in Puerto Rico. 23 What EPA’s discussion of risk fails to recognize, but its
analysis clearly shows, is that the highest level of risk presented by any coal-fired power plant is
actually “0.3-in-1 million,” more than 300 times lower than the threshold EPA deems acceptable. 24
The level of risk presented by North Dakota lignite-powered plants is lower still. According to
EPA’s risk review, the maximum risks presented by any North Dakota lignite-fired power plant is
“0.08-in-1 million,” yet another order of magnitude lower than the highest risk from any coal-fired
plant, and more than three orders of magnitude lower than EPA’s “acceptable” level of risk with
an “ample margin of safety.”
21
Id. at pp. 4-1 - 4-2.
Jason Bohrer, “Comments on National Emission Standards for Hazardous Air Pollutants: Coal- and Oil-Fired
Electric Utility Steam Generating Units Review of the Residual Risk and Technology Review, 88 Fed. Reg. 24854
(Apr. 24, 2023), June 23, 2024.
23
Residual Risk Assessment for the Coal- and Oil-Fired EGU Source Category in Support of the 2020 Risk and
Technology Review Final Rule, Docket ID No. EPA-HQ-OAR-2018-0794-4553, App. 10, Tbls. 1 & 2a (Sept. 2019)
(“Risk Assessment”) (note that Table 2a is printed upside down in the final September 2019 version of the Residual
Risk Assessment posted at www.regulations.gov, which may interfere with search commands; a searchable version of
the same table is available in the December 2018 draft version, Docket ID No. ). See also 84 Fed. Reg. at 2699 (“There
are only 4 facilities in the source category with cancer risk at or above 1-in-1 million, and all of them are located in
Puerto Rico.”).
24
Jason Bohrer, “Comments on National Emission Standards for Hazardous Air Pollutants: Coal- and Oil-Fired
Electric Utility Steam Generating Units Review of the Residual Risk and Technology Review, 88 Fed. Reg. 24854
(Apr. 24, 2023), June 23, 2024.
22
19
(Page 284 of Total)
468a
USCA Case #24-1119
Document #2058570
Filed: 06/07/2024
Page 159 of 204
The risks from North Dakota lignite are so low that they are more easily expressed, not in a million,
but in a billion—EPA has determined that the excess cancer risks from all North Dakota lignite
plants fall between 5- and 80-in-1 billion. 25 Moreover, EPA’s analysis indicates that those
maximum risks are not associated with mercury. 26
In fact, EPA’s own analysis confirms the risks from North Dakota lignite-powered plants are so
low they are little more than a rounding error that does not even qualify as a significant digit. In
its analysis of the still low but relatively higher risk from the Puerto Rican oil-fired plants, EPA
determined that one of those facilities presented a risk no greater than “1-in-1 million,” even
though EPA’s modeling actually returned a risk level of “1.09-in-1 million.”6 EPA discarded the
extra “.09,” apparently finding it too small to matter. However, that extra “.09” risk equates to “90in-1 billion,” and it is therefore higher than the entire risk identified for any North Dakota lignite
plant.
The Administrative Record Indicates the Mercury Standard of 1.2 lb./TBtu
is Technically Unachievable for EGUs using North Dakota Lignite Coal
The Administrative Record for the proposed rule suggests EPA made numerous critical mistakes
in assuming lignite fired EGUs can achieve a 1.2 Hg/lb limit with 90% Hg removal. As detailed in
the Cichanowicz Report, Section 6, EPA assumed the characteristics of lignite and subbituminous
coals are similar such that the Hg removal by emission controls capabilities is similar. In this light,
EPA did not consider that the high presence of sulfur trioxide (SO3) in lignite coal combustion flue
gas that significantly limits the Hg emissions reduction potential of emissions controls. 27
Similarly, as noted by LEC, EPA’s proposal references data obtained via an information collection
request as indicative of the level of performance achievable at North Dakota lignite facilities, but
that data only reflects relatively short-term testing that does not fully capture the significant
variability of lignite coals. Also, unlike other types of facilities that may be able to blend coals to
achieve greater consistency in the character of their fuel, all North Dakota lignite units are located
at mine-mouth facilities without access to other coal types, and therefore depend entirely on the
fuel extracted from the neighboring mine. As a result, changes in constituents between seams of
lignite coal can result in a high level of variability in the emission rates that result from use of the
coal as it is mined over time. 28
While LEC agreed with EPA that the injection of activated carbon is the most effective means of
reducing mercury emissions from lignite-powered units, LEC also criticized EPA for ignoring the
well-known diminishing returns of injecting more carbon. With each marginal increase in carbon
25
Risk Assessment, Tbl. 2a (indicating cancer risks of 8.07e-08, 3.09e-08, 1.31e-08, 1.21e-08, and 5.12e-09 for
Facility NEI IDs 380578086511, 380578086311, 380558011011, 380578086511, 380578086611 (Milton R. Young,
Leland Olds, Coal Creek, Antelope Valley, and Coyote).
26
Id., at Tbl. 2a (indicating the target organ of the risk associated with the plants identified in note 5 is “respiratory”).
27
J. Cichanowicz et al., Technical Comments on National Emission Standards for Hazardous Air Pollutants: Coaland Oil-fired Electric Utility Steam Generating Units Review of Residual Risk and Technology, at 29, Figure 6-7 (June
2, 2023) (“Cichanowicz Report”).
28
Jason Bohrer, “Comments on National Emission Standards for Hazardous Air Pollutants: Coal- and Oil-Fired
Electric Utility Steam Generating Units Review of the Residual Risk and Technology Review, 88 Fed. Reg. 24854
(Apr. 24, 2023), June 23, 2024.
20
(Page 285 of Total)
469a
USCA Case #24-1119
Document #2058570
Filed: 06/07/2024
Page 160 of 204
injection, the incremental increase in emission reduction capability falls. Thus, injecting more and
more carbon will not necessarily result in greater emission reductions beyond a certain injection
level. LEC asked EPA to evaluate the effect of diminishing returns on its conclusion that North
Dakota lignite-powered facilities can achieve the standard designed for all other units of 1.2
lb/TBtu.
EPA does not appear to have taken the above concerns into account in claiming lignite- powered
facilities can achieve the performance levels achieved at subbituminous plants. As a result, EPA
has significantly underestimated the level of control needed to achieve the proposed standard of
1.2 lb/TBtu. Contrary to the analysis EPA relies upon to justify lowering
This text is long and has been trimmed here. Open the source document for the complete record.
This is a copy of a public record, reproduced as it was published. It is not legal advice, and it may not be the version a court would rely on. Check the official source before you cite it.