Petition for Writ of Certiorari — Port of Tacoma, et al., Petitioners v. Puget Soundkeeper Alliance
Supreme Court briefSep 25, 2024
Ask Donna
What actually matters in this document.
Text
No. ______
In the
Supreme Court of the United States
PORT OF TACOMA; SSA TERMINALS, LLC; AND
SSA TERMINALS (TACOMA), LLC,
Petitioners,
V.
PUGET SOUNDKEEPER ALLIANCE,
Respondent.
ON PETITION FOR A WRIT OF CERTIORARI
TO THE UNITED STATES COURT OF APPEALS
FOR THE NINTH CIRCUIT
PETITION FOR A WRIT OF CERTIORARI
BRADFORD T. DOLL
LYNNE M. COHEE
FOSTER GARVEY PC
1111 Third Avenue
Suite 3000
Seattle, WA 98101
Counsel for Petitioner
Port of Tacoma
BRADLEY B. JONES
DIANNE K. CONWAY
GORDON THOMAS
HONEYWELL LLP
1201 Pacific Avenue
Suite 2100
Tacoma, WA 98402
Counsel for Petitioners
SSA Terminals, LLC, and
SSA Terminals (Tacoma),
LLC
GREGORY G. GARRE
Counsel of Record
ROMAN MARTINEZ
BLAKE E. STAFFORD
CHRISTINA R. GAY
LATHAM & WATKINS LLP
555 Eleventh Street, NW
Suite 1000
Washington, DC 20004
(202) 637-2207
gregory.garre@lw.com
Counsel for Petitioners
Port of Tacoma,
SSA Terminals, LLC, and
SSA Terminals (Tacoma),
LLC
i
QUESTION PRESENTED
Section 505 of the Clean Water Act (“CWA”) grants
federal courts jurisdiction over citizen suits enforcing
“a permit or condition of a permit” if it is “issued
under” Section 402 of the CWA. 33 U.S.C. § 1365(a),
(f). Section 402 of the CWA establishes the National
Pollutant Discharge Elimination System (“NPDES”),
a federal permitting regime that governs the
discharge of pollutants from point sources into
navigable waters. Id. § 1342.
The State of Washington, like many States, issues
general pollutant-discharge permits that regulate
broad sectors of the economy.
These permits
frequently combine federal requirements for point
sources subject to the CWA with additional
requirements authorized by state law. Below, the
Ninth Circuit held that Section 505 authorizes
citizens to enforce in federal court any condition of
Washington’s combined permit for industrialstormwater discharges, even those adopted under
state-law authority that mandate “a greater scope of
coverage” than the CWA. App.13a (citation omitted).
As the Ninth Circuit acknowledged, that rule
“directly conflicts with” Second Circuit precedent on
the authority conferred by the CWA’s citizen-suit
provision. App.13a, 19a (citation omitted).
The question presented is:
Whether Section 505 of the CWA authorizes
citizens to invoke the federal courts to enforce
conditions of state-issued pollutant-discharge permits
adopted under state law that mandate a greater scope
of coverage than required by the CWA.
ii
PARTIES TO THE PROCEEDING
Petitioners Port of Tacoma; SSA Terminals, LLC;
and SSA Terminals (Tacoma), LLC, were defendantsappellees/cross-appellants below. SSA Marine, Inc.,
was a defendant-appellant below and is not
participating in the proceedings before this Court.
APM Terminals Tacoma, LLC, and Don Esterbrook
were named as defendants in the United States
District Court for the Western District of Washington
and are not participating in the proceedings before
this Court.
Respondent Puget Soundkeeper Alliance was
plaintiff-appellant/cross-appellee below.
iii
RELATED PROCEEDINGS
Puget Soundkeeper Alliance v. Port of Tacoma,
Nos. 21-35881, 21-35889, 22-35061, United States
Court of Appeals for the Ninth Circuit, judgment
entered June 10, 2024.
Puget Soundkeeper Alliance v. SSA Terminals,
LLC, No. C17-5016-BHS, United States District
Court for the Western District of Washington,
judgment entered September 16, 2021.
iv
TABLE OF CONTENTS
Page
QUESTION PRESENTED ......................................... i
PARTIES TO THE PROCEEDING ........................... ii
RELATED PROCEEDINGS ..................................... iii
TABLE OF AUTHORITIES .................................... vii
OPINIONS AND ORDERS BELOW ..........................1
JURISDICTION ..........................................................1
STATUTORY
AND
REGULATORY
PROVISIONS INVOLVED .................................1
INTRODUCTION .......................................................2
STATEMENT OF THE CASE ....................................4
A. The Clean Water Act ...................................4
B. Washington’s Industrial Stormwater
General Permit ............................................7
C. West Sitcum Terminal Wharf .....................9
D. Proceedings Below .....................................12
REASONS FOR GRANTING THE WRIT................15
I.
The
Decision
Below
Cements
An
Acknowledged Circuit Conflict Over The
Scope Of The CWA’s Citizen-Suit Provision ....16
II.
The Ninth Circuit’s Decision Is Wrong ............23
III. The Question Presented Is Important And
Warrants This Court’s Review In This Case ...31
v
TABLE OF CONTENTS—Continued
Page
CONCLUSION ..........................................................38
APPENDIX
Opinion of the United States Court of Appeals
for the Ninth Circuit, Port of Tacoma v.
Puget Soundkeeper, 104 F.4th 95 (9th Cir.
2024) ....................................................................1a
Order of the United States District Court of the
Western District of Washington Granting
Port of Tacoma Motion for Partial
Summary Judgment, Puget Soundkeeper
Alliance v. APM Terminals Tacoma, LLC,
No. C17-5016 BHS, 2020 WL 6445825
(W.D. Wash. Nov. 3, 2020) ...............................21a
Order of the United States District Court of the
Western District of Washington Granting
SSA Terminals, LLC, and SSA Terminals
(Tacoma), LLC, Motion for Summary
Judgment, Puget Soundkeeper Alliance v.
SSA Terminals, LLC, 561 F. Supp. 3d 1113
(W.D. Wash. 2021) ............................................48a
Order of the United States District Court of the
Western District of Washington Granting
Defendant’s Motion for Entry of Rule 54(b)
Judgment, Puget Soundkeeper Alliance v.
SSA Terminals, LLC, No. C17-5016 BHS,
2021 WL 4226162 (W.D. Wash. Sept. 16,
2021) ..................................................................70a
vi
TABLE OF CONTENTS—Continued
Page
33 U.S.C. § 1342(a), (p) ...........................................76a
33 U.S.C. § 1365 ......................................................82a
40 C.F.R. § 123.1 .....................................................86a
vii
TABLE OF AUTHORITIES
Page(s)
CASES
Alliance For Environmental Renewal,
Inc. v. Pyramid Crossgates Co.,
436 F.3d 82 (2d Cir. 2006) ...................................17
Ardestani v. INS,
502 U.S. 129 (1991) ..............................................24
Arkansas v. Oklahoma,
503 U.S. 91 (1992) ..................................................4
Askins v. Ohio Department of
Agriculture,
809 F.3d 868 (6th Cir. 2016)................................28
Atlantic States Legal Foundation, Inc.
v. Eastman Kodak Co.,
12 F.3d 353 (2d Cir. 1993), cert.
denied, 513 U.S. 811 (1994) ........... 2, 13, 16, 17, 18
Cape Fear River Watch, Inc. v. Duke
Energy Progress, Inc.,
No. 7:13-cv-200, 2014 WL 10991530
(E.D.N.C. Aug. 1, 2014) .......................................34
Citizens’ Alliance for Property Rights v.
City of Duvall,
No. C12-1093RAJ, 2014 WL
1379575 (W.D. Wash. Apr. 8, 2014),
aff’d, 636 F. App’x 430 (9th Cir.
2016) .....................................................................20
City & County of San Francisco v. EPA,
144 S. Ct. 2578 (2024)..........................................31
viii
TABLE OF AUTHORITIES—Continued
Page(s)
County of Maui v. Hawaii Wildlife
Fund,
139 S. Ct. 196 (2019)............................................31
Covington v. Jefferson County,
358 F.3d 626 (9th Cir. 2004)................................26
Culbertson v. Coats American, Inc.,
913 F. Supp. 1572 (N.D. Ga. 1995) ...............21, 22
Decker v. Northwest Environmental
Defense Center,
567 U.S. 933 (2012) ..............................................31
Decker v. Northwest Environmental
Defense Center,
568 U.S. 597 (2013) ................................................5
DOT v. Association of American
Railroads,
575 U.S. 43 (2015) ................................................30
Florida Department of Revenue v.
Piccadilly Cafeterias, Inc.,
554 U.S. 33 (2008) ................................................24
Friends of the Earth, Inc. v. Laidlaw
Environmental Services (TOC), Inc.,
528 U.S. 167 (2000) ........................................30, 36
Garcia v. Cecos International, Inc.,
761 F.2d 76 (1st Cir. 1985) ..................................30
Gill v. LDI,
19 F. Supp. 2d 1188 (W.D. Wash.
1998) .....................................................................20
ix
TABLE OF AUTHORITIES—Continued
Page(s)
Gwaltney of Smithfield, Ltd. v.
Chesapeake Bay Foundation, Inc.,
484 U.S. 49 (1987) .......................... 7, 27, 28, 30, 36
Harpeth River Watershed Association v.
City of Franklin,
No. 14-1743, 2016 WL 827584 (M.D.
Tenn. Mar. 3, 2016) .............................................22
International Paper Co. v. Ouellette,
479 U.S. 481 (1987) .................................. 24, 25, 27
Jones v. Hendrix,
599 U.S. 465 (2023) ..............................................27
Long Island Soundkeeper Fund, Inc. v.
New York City Department of
Environmental Protection,
27 F. Supp. 2d 380 (E.D.N.Y. 1998) ....................17
Loper Bright Enterprises v. Raimondo,
144 S. Ct. 2244 (2024)..........................................25
Los Angeles County Flood Control
District v. Natural Resources
Defense Council, Inc.,
567 U.S. 933 (2012) ..............................................31
Maryland Department of the
Environment v. Assateague Coastal
Trust,
299 A.3d 619 (Md. 2023) ......................................34
Mesa v. California,
489 U.S. 121 (1989) ..............................................29
x
TABLE OF AUTHORITIES—Continued
Page(s)
Middlesex County Sewerage Authority
v. National Sea Clammers
Association,
453 U.S. 1 (1981) ..................................................28
New Manchester Resort & Golf, LLC v.
Douglasville Development, LLC,
734 F. Supp. 2d 1326 (N.D. Ga.
2010) .....................................................................22
Northwest Environmental Advocates v.
City of Portland,
11 F.3d 900 (9th Cir. 1993)............................18, 19
Northwest Environmental Advocates v.
City of Portland,
56 F.3d 979 (9th Cir. 1995).......... 14, 18, 19, 20, 24
Northwest Environmental Advocates v.
City of Portland,
74 F.3d 945 (9th Cir. 1996)................ 15, 19, 20, 35
Ohio Valley Environmental Coalition,
Inc. v. Marfork Coal Co.,
966 F. Supp. 2d 667 (S.D.W. Va.
2013) .....................................................................22
Ohio Valley Environmental Coalition v.
Fola Coal Co.,
845 F.3d 133 (4th Cir. 2017)................................22
Ohio Valley Environmental Coalition,
Inc. v. Fola Coal Co.,
No. 12-3750, 2013 WL 6709957
(S.D.W. Va. Dec. 19, 2013)...................................22
xi
TABLE OF AUTHORITIES—Continued
Page(s)
Okanogan Highlands Alliance v. Crown
Resources Corp.,
544 F. Supp. 3d 1092 (E.D. Wash.
2021) .....................................................................34
Parker v. Scrap Metal Processors, Inc.,
386 F.3d 993 (11th Cir. 2004)..............................21
Parris v. 3M Co.,
595 F. Supp. 3d 1288 (N.D. Ga.
2022) .....................................................................22
Puget Soundkeeper Alliance v. APM
Terminals Tacoma, LLC,
No. C17-5016 BHS, 2018 WL
2560995 (W.D. Wash. June 4, 2018) ...................12
In re Reissuance of an NPDES/SDS
Permit to United States Steel Corp.,
954 N.W.2d 572 (Minn. 2021)..............................34
Romero v. International Terminal
Operating Co.,
358 U.S. 354 (1959) ..............................................30
Sackett v. EPA,
142 S. Ct. 896 (2022)............................................31
Sackett v. EPA,
598 U.S. 651 (2023) .................................... 7, 28, 35
Saint John’s Organic Farm v. Gem
County Mosquito Abatement District,
574 F.3d 1054 (9th Cir. 2009)..............................34
xii
TABLE OF AUTHORITIES—Continued
Page(s)
Solid Waste Agency of Northern Cook
County v. United States Army Corps
of Engineers,
531 U.S. 159 (2001) ..............................................31
Stephens v. Koch Foods, LLC,
667 F. Supp. 2d 768 (E.D. Tenn.
2009) .....................................................................23
United States Department of Energy v.
Ohio,
503 U.S. 607 (1992) ..............................................17
United States v. Recticel Foam Corp.,
858 F. Supp. 726 (E.D. Tenn. 1993) ....................26
United States ex rel. Polansky v.
Executive Health Resources, Inc.,
599 U.S. 419 (2023) ..............................................31
Verlinden B.V. v. Central Bank of
Nigeria,
461 U.S. 480 (1983) ..............................................29
Yadkin Riverkeeper, Inc. v. Duke
Energy Carolinas, LLC,
141 F. Supp. 3d 428 (M.D.N.C. 2015) .................34
Yates v. United States,
574 U.S. 528 (2015) ..............................................25
CONSTITUTIONAL, STATUTORY AND
REGULATORY PROVISIONS
U.S. Const. art. III, § 2, cl. 1 .....................................29
xiii
TABLE OF AUTHORITIES—Continued
Page(s)
28 U.S.C. § 1254(1)......................................................1
33 U.S.C. § 1251(b).......................................... 4, 28, 35
33 U.S.C. § 1311(a)......................................................4
33 U.S.C. § 1311(b)....................................................18
33 U.S.C. § 1319(a)(3) ...........................................6, 25
33 U.S.C. § 1319(d)......................................................7
33 U.S.C. § 1342 ....................................................5, 24
33 U.S.C. § 1342(a)(2) .................................................5
33 U.S.C. § 1342(b)..................................................6, 7
33 U.S.C. § 1342(p)(1) .................................................5
33 U.S.C. § 1342(p)(2)(B) ............................................5
33 U.S.C. § 1362(12) ....................................................4
33 U.S.C. § 1365 ..........................................................2
33 U.S.C. § 1365(a)................................................7, 23
33 U.S.C. § 1365(a)(1) .................................................6
33 U.S.C. § 1365(d)................................................7, 34
33 U.S.C. § 1365(f) ................................................6, 24
33 U.S.C. § 1365(f)(1)-(7) ..........................................25
42 U.S.C. § 6901 et seq. .............................................26
xiv
TABLE OF AUTHORITIES—Continued
Page(s)
Wash. Rev. Code § 90.48.260 ......................................7
40 C.F.R. § 122.26(a)(1)(ii) ........................................14
40 C.F.R. § 122.26(b)(14) ........................................5, 6
40 C.F.R. § 122.26(b)(14)(i)-(xi) ..................................5
40 C.F.R. § 122.26(b)(14)(viii) .................................6, 8
40 C.F.R. § 122.46(a) ...................................................8
40 C.F.R. § 123.1 .......................................................26
40 C.F.R. § 123.1(d)(1) ................................................7
40 C.F.R. § 123.1(i)(2) ..................................... 2, 17, 26
40 C.F.R. § 271.1 .......................................................26
Wash. Admin. Code § 173-226-010 .............................8
Wash. Admin. Code § 173-226-070 .............................8
OTHER AUTHORITIES
73 Fed. Reg. 70418 (Nov. 20, 2008) ..........................26
Charles S. Abell, Ignoring the Trees for
the Forests: How the Citizen Suit
Provision of the Clean Water Act
Violates the Constitution’s
Separation of Powers Principle, 81
Va. L. Rev. 1957 (1995)........................................30
xv
TABLE OF AUTHORITIES—Continued
Page(s)
David Adelman & Robert Glicksman,
Reevaluating Environmental Citizen
Suits in Theory and Practice, 91
Colo. L. Rev. 386 (2020) .......................................36
Jonathan H. Adler, Stand or Deliver:
Citizen Suits, Standing, and
Environmental Protection, 12 Duke
Env’t L. & Pol’y F. 39 (2001) ...............................32
The American Heritage Dictionary
(1978) ....................................................................24
Frank B. Cross, Rethinking
Environmental Citizen Suits, 8
Temp. Env’t L. & Tech. J. 55 (1989,
Westlaw)...............................................................35
2A Env’t Law Practice Guide (2024) ........................21
Roger Hanshaw, State Courts vs.
Federal Courts: Jurisdictional
Battles over State Water Quality
Standards, 31 Nat. Res. & Env’t 12
(2016) ....................................................................20
Rick W. Jarvis, A City Attorney’s
Citizens’ Suit Survival Guide,
League of California Cities (May
1996), https://www.cacities.org/
UploadedFiles/LeagueInternet/
2a/2a7c5332-7aef-4598-9218c60b795f8119.pdf .................................................32
xvi
TABLE OF AUTHORITIES—Continued
Page(s)
Susan A. Macmanus, The Impact of
Litigation on Municipalities: Total
Cost, Driving Factors, and Cost
Containment Mechanisms, 44
Syracuse L. Rev. 833 (1993) ................................35
1 Linda A. Malone, Env’t Reg. of Land
Use (2024) ............................................................21
James R. May, The Availability of State
Environmental Citizen Suits, 18SPG Nat. Res. & Env’t 53 (2004,
Westlaw)...............................................................35
Memorandum from William A.
Sullivan, Jr., EPA Enforcement of
RCRA-Authorized State Hazardous
Waste Laws and Regulation,
Directive No. 9541.01-82x (Mar. 15,
1982), https://rcrapublic.epa.gov/
files/12046.pdf ......................................................26
Puget Soundkeeper, Clean Water Act
Lawsuits,
https://pugetsoundkeeper.org/
strategy-citizen-lawsuits/ (last
visited Sept. 18, 2024) ...................................33, 37
Marc Robertson, Environmental
Ambulance Chasing: DOJ Urges
Court To Scrutinize Clean Water
Citizen-Suit Settlements, Forbes
(June 26, 2018).....................................................36
xvii
TABLE OF AUTHORITIES—Continued
Page(s)
S. Rep. No. 92-414 (1971), 1971 WL
11307 ......................................................................7
U.S. Gov’t Accountability Off., Clean
Water Act: EPA Needs to Better
Assess and Disclose Quality of
Compliance and Enforcement Data
(July 2021), https://www.gao.gov/
assets/gao-21-290.pdf...........................................33
1
PETITION FOR A WRIT OF CERTIORARI
Petitioners Port of Tacoma; SSA Terminals, LLC;
and SSA Terminals (Tacoma), LLC, respectfully
petition this Court for a writ of certiorari to review the
judgment of the United States Court of Appeals for
the Ninth Circuit in this case.
OPINIONS AND ORDERS BELOW
The opinion of the court of appeals (App.1a-20a) is
reported at 104 F.4th 95. The opinion of the district
court granting SSA Terminals, LLC, and SSA
Terminals (Tacoma), LLC’s motion for summary
judgment (App.48a-69a) is reported at 561 F. Supp.
3d 1113. The opinion of the district court granting the
Port of Tacoma’s motion for partial summary
judgment (App.21a-47a) is available at 2020 WL
6445825. The district court’s order entering Rule
54(b) judgment (App.70a-75a) is available at 2021 WL
4226162.
JURISDICTION
The court of appeals entered its judgment on
June 10, 2024. On September 3, 2024, Justice Kagan
extended the time to file a petition for a writ of
certiorari to September 25, 2024. This Court has
jurisdiction under 28 U.S.C. § 1254(1).
STATUTORY AND REGULATORY
PROVISIONS INVOLVED
Relevant statutory and regulatory provisions are
reproduced in the petition appendix. App.76a-89a.
2
INTRODUCTION
This case presents a fundamental question about
the reach of the citizen-enforcement provision of the
Clean Water Act (“CWA”), 33 U.S.C. § 1365 (“Section
505”). The decision below reaffirmed the Ninth
Circuit’s position that Section 505 authorizes citizens
to bring federal lawsuits that seek to enforce state-law
water-pollution requirements that “mandate ‘a
greater scope of coverage than that required’ by” the
CWA. App.12a-13a. According to the Ninth Circuit,
private citizens can enforce in federal court any
condition of a state-issued pollutant-discharge
permit—including conditions authorized by state law
that go beyond the CWA—as long as some portion of
that permit implements the federal National
Pollutant Discharge Elimination System (“NPDES”)
program.
The Ninth Circuit’s expansive rule on citizen-suit
standing demands this Court’s review. As the Ninth
Circuit itself acknowledged, this rule “directly
conflicts” with the Second Circuit’s decision in
Atlantic States Legal Foundation, Inc. v. Eastman
Kodak Co., 12 F.3d 353 (2d Cir. 1993), cert. denied,
513 U.S. 811 (1994). App.13a (citation omitted). In
Atlantic States, the Second Circuit held that “state
regulations, including the provisions of [state-issued
pollutant-discharge] permits, which mandate ‘a
greater scope of coverage than that required’ by the
federal [Act] and its implementing regulations are not
enforceable through a citizen suit.” 12 F.3d at 359
(quoting 40 C.F.R. § 123.1(i)(2)) (emphasis added).
The Ninth Circuit below held the exact opposite—
while acknowledging the conflict. App.13a.
3
The Ninth Circuit’s rule also is plainly mistaken:
It distorts the CWA’s statutory language, ignores
EPA’s stated limits on the reach of the CWA, produces
several significant and anomalous consequences, and
raises serious constitutional concerns. As Judge
O’Scannlain observed below, the Ninth Circuit’s
position “expand[s] citizen standing in a way
Congress never intended.”
App.18a (specially
concurring). As this case shows, that expansion
eviscerates Congress’ careful drafting of the CWA by
illogically allowing private citizens to enforce in
federal court permit conditions regulating activities
Congress expressly exempted from the CWA’s scope.
The issue is unquestionably important. There are
hundreds of thousands of permits issued under the
NPDES program, many of which combine expansive
state-imposed water-pollution conditions with federal
CWA requirements. As Judge O’Scannlain observed,
the Ninth Circuit’s ruling below paves the way for
costly and unpredictable federal citizen litigation.
App.19a-20a. Because of the CWA’s strict-liability
scheme and attorney’s fees and penalty provisions,
such litigation can impose massive costs on its
targets, including municipalities and other local
government entities, based on even minor violations
of state-authorized permit conditions that go far
beyond the federal requirements.
The Ninth Circuit’s rule also impedes the
sovereign ability of States to decide how to enforce
their own laws, placing authority over such matters
in the hands of a virtually limitless—and entirely
unaccountable—force of private litigants, who lack
the traditional political checks on prosecutorial
actions. This case is just one example. Recognizing
the challenges of compliance with its increasingly
4
complex water laws, Washington—like many
States—has decided not to allow private actions to
enforce violations of its water-pollution requirements.
Yet, under the Ninth Circuit’s rule, citizen groups like
respondent can override Washington’s enforcement
choices, pursuing even minor violations of its widereaching permits. These private enforcement actions
not only burden the federal judicial system, but also
divert attention and taxpayer resources from local
government programs, including those addressing
more pressing environmental issues.
This Court’s review is warranted to resolve the
acknowledged circuit split over this critical question
and ensure that the CWA’s citizen-suit provision
serves its proper, and properly limited, role.
STATEMENT OF THE CASE
A. The Clean Water Act
1. Enacted in 1972, the CWA establishes a
regulatory framework that honors our federal
structure by dividing the authority to regulate water
pollution between the Federal Government and the
States. See Arkansas v. Oklahoma, 503 U.S. 91, 101
(1992). By its own terms, the CWA aims to “protect
the primary responsibilities and rights of States to
prevent, reduce, and eliminate pollution, [and] to plan
the development and use … of land and water
resources,” 33 U.S.C. § 1251(b), while also providing
for direct federal oversight when necessary.
That federal oversight is found principally in the
Act’s prohibition of most discharges of “pollutants”
from “point sources” to “navigable waters.” Id.
§§ 1311(a), 1362(12). Nonexempt discharges from
point sources to navigable waters require a permit,
typically from the EPA or a State with delegated
5
authority. These permits, known as NPDES permits,
are issued under Section 402 of the CWA. See id.
§ 1342. NPDES permits translate the CWA’s general
requirements into specific limitations on the types
and amounts of pollutants a point source can
discharge, and can include monitoring and reporting
requirements to ensure compliance. Id. § 1342(a)(2).
As originally enacted, the CWA regulated
virtually all discharges from point sources into
navigable waters, including stormwater discharges—
rainwater that flows over the ground surface instead
of being absorbed. But in 1987, Congress amended
the Act to exempt “most ‘discharges composed entirely
of stormwater.’” Decker v. Northwest Env’t Def. Ctr.,
568 U.S. 597, 603-04 (2013) (quoting 33 U.S.C.
§ 1342(p)(1)). Congress decided that only certain
categories of stormwater discharges require an
NPDES permit, including discharges “associated with
industrial activity.” 33 U.S.C. § 1342(p)(2)(B).
Congress directed EPA to define stormwater
discharges “associated with industrial activity.”
Decker, 568 U.S. at 603-04 (citation omitted). In
response, EPA defined the term to encompass
discharges from “any conveyance that is used for
collecting and conveying storm water and that is
directly related to manufacturing, processing or raw
materials storage areas at an industrial plant.” 40
C.F.R. § 122.26(b)(14).
EPA specified eleven
categories of facilities meeting those requirements,
including transportation facilities with “vehicle
maintenance shops, equipment cleaning operations,
or airport deicing operations.” Id. § 122.26(b)(14)(i)(xi).
EPA was equally clear that the CWA’s “associated
with industrial activity” term “excludes areas located
6
on plant lands separate from the plant’s industrial
activities, … as long as the drainage from the
excluded areas is not mixed with storm water drained
from” an industrial-activity area. Id. § 122.26(b)(14).
So, for transportation facilities with “vehicle
maintenance shops, equipment cleaning operations,
or airport deicing operations,” “[o]nly those portions
of the facility that are either involved in vehicle
maintenance … , equipment cleaning operations,
airport deicing operations, or which are otherwise
identified under paragraphs (b)(14)(i)-(vii) or (ix)-(xi)
of this section are associated with industrial activity.”
Id. § 122.26(b)(14)(viii). Stormwater drainage from
areas where marine ports do not conduct such
activities—such as parking lots, docks, and wharfs—
are therefore not subject to the federal requirements
for industrial-stormwater discharges.
2. The CWA authorizes enforcement actions by
federal and state regulators. 33 U.S.C. § 1342(b);
see id. § 1319(a)(3) (authorizing EPA to enforce
“condition[s] or limitation[s] … in a permit issued
under section 1342 of this title”). It also contains a
citizen-suit provision authorizing private citizens to
sue in federal court to enforce “an effluent standard
or limitation under [the CWA]” or “an order issued by
[EPA] or a State with respect to such a standard.” Id.
§ 1365(a)(1). Congress defined “effluent standard or
limitation” to include “a permit or condition of a
permit issued under section 1342 of this title that is
in effect under this chapter.” Id. § 1365(f).
Congress intended citizens to play a limited role in
enforcing the CWA. As this Court has recognized,
“[t]he Senate Report [accompanying the bill including
Section 505] noted that ‘[t]he Committee intends the
great volume of enforcement actions [to] be brought
7
by the State,’ and that citizen suits are proper only
‘if the Federal, State, and local agencies fail to
exercise their enforcement responsibility.’” Gwaltney
of Smithfield, Ltd. v. Chesapeake Bay Found., Inc.,
484 U.S. 49, 60 (1987) (quoting S. Rep. No. 92-414, at
64 (1971), 1971 WL 11307). In other words, the
citizen suit was intended to “supplement rather than
to supplant governmental action.” Id.
The CWA’s citizen-suit provision is nevertheless a
potent weapon. Any citizen may invoke it to allege
ongoing violations of the CWA where administrative
authorities have declined to bring suit, in order to
seek injunctive relief as well as civil penalties payable
to the U.S. Treasury. 33 U.S.C. §§ 1319(d), 1365(a).
As this Court has recognized, those penalties—
assessed on a per-day, per-violation basis, even for
completely inadvertent violations—can be “crushing.”
Sackett v. EPA, 598 U.S. 651, 660 (2023). Citizens can
also recover attorney’s fees, expert witness fees, and
other litigation costs. 33 U.S.C. § 1365(d).
B. Washington’s
Industrial
Stormwater
General Permit
The CWA charges EPA with issuing NPDES
permits in the first instance, but most States—
including the State of Washington—are authorized by
EPA to issue NPDES permits themselves. 33 U.S.C.
§ 1342(b); 40 C.F.R. § 123.1(d)(1); Wash. Rev. Code
§ 90.48.260. Exercising its delegated authority, the
State of Washington regulates specific discharge
categories through “general water quality permits”
issued by the Washington State Department of
Ecology (“Ecology”) that apply to categories of
facilities or industries. 2-PortSER-234. Most of these
general permits combine the federal CWA
8
requirements with Washington’s expansive state-law
conditions on the release of stormwater or waste
materials into ground and surface waters. See Wash.
Admin. Code § 173-226-070.
At issue here are the 2010 and 2015 versions of the
Washington Industrial Stormwater General Permit
(“ISGP”), which regulates stormwater discharges
from industrial facilities.1 The ISGP is a combined
permit “designed to satisfy” both “the requirements
for discharge permits under [the CWA] and the state
law governing water pollution control.” Id. § 173-226010. Indeed, the ISGP expressly states that it is both
an “[NPDES] and State Waste Discharge General
Permit” issued “[i]n compliance with the provisions of
The State of Washington Water Pollution Control
Law … and [t]he [CWA].” App.27a.
The ISGP’s scope is staggering. The 2015 version
stretches nearly 70 pages, demanding adherence
to detailed manuals that span hundreds more. 5-ER965–1033.
Through this far-reaching permit,
Washington exerts control over more than 1,200
different facilities. 2-PortSER-265.
Beginning in 2010, Ecology omitted from its ISGP
the terms of the federal regulations confining
regulation of industrial stormwater to “[o]nly those
portions of a [transportation] facility” where vehicle
maintenance, equipment cleaning, airport deicing,
or other activities specifically defined as
industrial take place. App.5a (quoting 40 C.F.R.
§ 122.26(b)(14)(viii)). At the time, however, Ecology
told permittees that the ISGP would apply only to the
portions of transportation facilities “where vehicle
1
The ISGP is reissued every five years. See 40 C.F.R.
§ 122.46(a).
9
and equipment maintenance or equipment cleaning
occurs.” 2-PortSER-358; see 2-PortSER-346–358.
After the deadline to challenge Ecology’s 2010
ISGP passed, Ecology notified two ports that they
needed to expand ISGP compliance to encompass all
port property. App.31a. The ports responded that the
implications of such interpretation would be
“extreme,” explaining that expanding the ISGP’s
scope would have “major ramifications on a port’s
ability to comply” and would “require substantial
efforts and expenditures.” Id.; 4-ER-743.
For example, the ISGP mandates stormwater
runoff sampling and corrective actions such as the
installation of rainfall collection and treatment
systems. 5-ER-988–991, 1005–008. These measures
are infeasible for overwater structures such as docks
or wharfs that support electrified crane operations, as
they are intentionally designed to avoid water
collection for safety reasons.
Notably, federal
regulations contain no similar requirements for
stormwater discharges from docks, wharfs, railroad
lines, and other areas used solely for transportation.
Ecology nonetheless instructed ports that they
needed to take the necessary—and costly—steps to
implement the ISGP’s requirements “as soon as
possible” on “all areas of industrial activity.”
App.31a-32a. But Ecology stated that it would
exercise its “enforcement discretion” to allow time to
comply with those requirements. Id.
C. West Sitcum Terminal Wharf
The Port of Tacoma—one of the largest container
ports in the U.S.—is a deepwater port located on
Commencement Bay in south Puget Sound,
Washington. It is a publicly owned and operated
10
facility. 4-ER-738. Through The Northwest Seaport
Alliance, a marine cargo operating partnership of the
Tacoma and Seattle ports, the Port of Tacoma’s
customers move goods across the world. 4-ER-771–
72.
The West Sitcum Terminal (the “Terminal”) is a
137-acre marine cargo terminal at the Port of Tacoma,
leased and operated by SSA Terminals (Tacoma),
LLC—a privately owned company that provides
stevedoring and marine terminal services. App.3a.
“The Wharf” is a 12.6-acre overwater portion of the
Terminal used only for loading and unloading cargo
containers. Id. No vehicle maintenance, equipment
cleaning, or airport deicing occurs at the Wharf. Id.
The Wharf is graded to avoid receiving stormwater
flows from other portions of the Terminal. 4-ER-772.
The following picture shows the Wharf in yellow,
along with the surrounding area (see App.50a):
11
12
The 2010 and 2015 ISGPs authorized stormwater
discharges from the Terminal. Because the Wharf is
used only to load and unload containers and does not
receive discharges from portions of the Terminal
defined by EPA as “associated with industrial
activity,” discharges from the Wharf are exempted
from federal industrial-stormwater requirements.
App.4a. But the Ninth Circuit concluded below that
such runoff does fall within the state-law-derived
provisions of Washington’s expanded ISGP. App.8a11a.
Accordingly, under the Ninth Circuit’s
interpretation of the combined permit, areas like the
Wharf must meet the State’s requirements for
industrial-stormwater
discharges—even
though
stormwater runoff from the Wharf is exempt from
such requirements under the CWA.
D. Proceedings Below
1. In January 2017, Puget Soundkeeper Alliance
(“Soundkeeper”) initiated this CWA citizen suit
against APM Terminals Tacoma, LLC (“APMT”), the
then-tenant of the West Sitcum Terminal. App.51a.
Among other claims, Soundkeeper contended that
APMT violated the 2010 and 2015 ISGPs by failing to
apply “all known, available, and reasonable methods
of prevention, control and treatment” of pollutants.
Puget Soundkeeper All. v. APM Terminals Tacoma,
LLC, No. C17-5016 BHS, 2018 WL 2560995, at *1
(W.D. Wash. June 4, 2018).
After APMT terminated its operations and SSA
Terminals (Tacoma), LLC, took over as the Terminal’s
tenant, Soundkeeper added the Port and SSA2 as
2
“SSA” refers collectively to petitioners SSA Terminals,
LLC, and SSA Terminals (Tacoma), LLC.
13
defendants, alleging (among other claims) that the
Port and SSA failed to comply with ISGP
requirements on the Wharf—even though no
industrial activities as defined by EPA’s regulations
take place there. App.51a; supra at 10.
As relevant here, the Port and SSA moved for
summary judgment on Soundkeeper’s claims related
to stormwater discharges from the Wharf. They first
argued that the plain language of the ISGP does not
cover discharges from the Wharf. 3-SSA_SER-773;
4-ER-706–11. But they added that, “[e]ven if Ecology
exercised state authority to extend the ISGP to all
portions of a transportation facility,” such broader
coverage “is not federally enforceable” by private
citizens because “stormwater discharges from the
Wharf are exempted from the federal NPDES
program by Congress and the EPA.” 4-ER-801; see
also 3-SSA_SER-771–73. As the Port and SSA
explained, the CWA’s citizen-suit provision does not
authorize suits purporting to enforce state-law
conditions of state-issued permits that mandate a
greater scope of coverage than the CWA. 4-ER-791–
802 (citing Atlantic States, 12 F.3d at 359).
The district court held that the plain terms of the
ISGP do not cover the entire footprint of industrial
facilities and thus do not cover discharges from the
Wharf. App.43a-45a, 65a-66a. The court accordingly
did not reach the alternative argument that, to the
extent the ISGP extended such coverage as a matter
of state law, that expanded scope of coverage could not
be enforced in a CWA citizen suit.
2. The Ninth Circuit reversed. App.1a-20a. The
court disagreed with the district court’s reading of the
2010 and 2015 ISGPs, concluding that those permits
imposed conditions on stormwater discharges from
14
the entire footprint of the Terminal, including the
Wharf. App.8a-11a. The court acknowledged that,
“[i]n this respect, the ISGPs differ from the federal
regulations”—acknowledging that, “[u]nder the
ISGPs, coverage is triggered … when the facility
conducts industrial activity, not when a particular
discharge is ‘associated with industrial activity.’”
App.8a (quoting 40 C.F.R. § 122.26(a)(1)(ii)).
The court then rejected the Port and SSA’s
alternative argument that ISGP conditions
regulating discharges from the Wharf are not
enforceable in a CWA citizen-suit action “because
they exceed the requirements of the federal
regulations.”
App.11a.
Citing Ninth Circuit
precedent, the court held that “all permit conditions”
are enforceable in a CWA citizen suit, App.12a
(quoting Northwest Env’t Advocs. v. City of Portland,
56 F.3d 979, 986 (9th Cir. 1995) (“NWEA II”))—even
if a condition was adopted pursuant to state law and
“prescribe[s] ‘a greater scope of coverage’ than the
federal regulations,” App.12a-13a.
The court
acknowledged that this precedent “directly conflicts
with the Second Circuit’s decision in Atlantic States,”
but stated it was “bound to follow the former.”
App.13a (citation omitted).
Judge O’Scannlain specially concurred. While
acknowledging that the panel opinion “faithfully
follows Ninth Circuit precedent,” Judge O’Scannlain
emphasized that such precedent “created a circuit
split” that remains and is a “source of ongoing
confusion to parties, such as the Port of Tacoma,” that
have invoked the Second Circuit precedent. App.18a19a. Echoing the concerns in an earlier dissent from
the Ninth Circuit’s refusal to rehear NWEA II en
banc, he further explained that the Ninth Circuit’s
15
position “continues to expand citizen standing in a
way Congress never intended.”
Id. (discussing
Northwest Env’t Advocs. v. City of Portland, 74 F.3d
945, 946 (9th Cir. 1996) (“NWEA III”) (O’Scannlain,
J., joined by Hall, T.G. Nelson, and Kleinfeld, JJ.,
dissenting from denial of rehearing en banc)).
Judge O’Scannlain explained that the Ninth
Circuit’s rule not only “upset[s] the delicate balance
envisioned by Congress in its promulgation of the
current enforcement regime for environmental law,”
but
also
invites
“excessive,
costly,
and
counterproductive citizen suits, funded by the
taxpayers, for the enforcement of standards that are
imprecise and astronomically costly to the
municipalities affected.” App.20a (citation omitted).
REASONS FOR GRANTING THE WRIT
This petition readily satisfies all the traditional
criteria for certiorari. First, as the Ninth Circuit
acknowledged, its decision has entrenched a direct
circuit conflict. Second, the Ninth Circuit’s position is
wrong. Text, context, and constitutional principles all
make clear that the CWA’s citizen-suit provision does
not authorize private citizens to bring actions in
federal court to enforce state-law permit conditions
that mandate a greater scope of coverage than
required by federal law. And, third, the question
presented is undeniably important.
The Ninth
Circuit’s decision upsets the delicate balance of state
and federal authority over water-quality matters,
hands enforcement decisions over to private interest
groups or individuals lacking political checks against
prosecutorial abuse, and invites excessive and costly
regulatory litigation. Certiorari is thus warranted.
16
I. The
Decision
Below
Cements
An
Acknowledged Circuit Conflict Over The
Scope Of The CWA’s Citizen-Suit Provision
The Ninth Circuit’s decision reaffirms an
entrenched circuit split over whether citizens can
enforce in federal court conditions authorized by state
law that go beyond the scope of the CWA.
1. As both the panel opinion and special
concurrence acknowledged below, the Ninth Circuit’s
decision “directly conflicts with” the Second Circuit’s
ruling in Atlantic States Legal Foundation, Inc. v.
Eastman Kodak Co., 12 F.3d 353 (2d Cir. 1993).
App.13a; App.19a (O’Scannlain, J., specially
concurring). In Atlantic States, the Second Circuit
held that federal courts lack jurisdiction over citizenenforcement actions alleging violations of permit
conditions authorized by state law that go beyond the
requirements of the CWA. See 12 F.3d at 358-60.
That holding is irreconcilable with the decision below.
The facts of Atlantic States closely resemble those
here.
There, an environmental advocacy group
claimed that Kodak violated a state-issued pollutantdischarge permit that—like the ISGP—was “devised
to implement both the [CWA] and [state] law.” Id. at
355. The group alleged that Kodak breached a permit
condition adopted “pursuant to” New York law, which
allegedly prohibited “the discharge of any pollutant”
not specifically listed. Id. at 359. The Second Circuit
rejected the suit, concluding that, “even if Atlantic
States is right about New York law” and the
interpretation of Kodak’s state-issued permit, the
action would still fail “because New York would be
implementing a regulatory scheme broader than
17
the CWA, … and such broader state schemes are
unenforceable through … citizen suits.” Id. at 359-60.
For support, the Second Circuit quoted an EPA
regulation specifying that, “[i]f an approved State
[NPDES] program has greater scope of coverage than
required by Federal law[,] the additional coverage is
not part of the Federally approved program.”
40 C.F.R. § 123.1(i)(2). It also relied on United States
Department of Energy v. Ohio, which held that
“penalties prescribed by state statutes” for violations
of the CWA do not “arise under federal law” for
purposes of waiving the United States’s sovereign
immunity from liability for citizen suits. 503 U.S.
607, 624-26 (1992). While “States may enact stricter
standards for wastewater effluents than mandated by
the CWA and federal EPA regulations,” the Second
Circuit explained, “private citizens have no standing”
to enforce those standards in federal court under
Section 505 of the CWA. Atlantic States, 12 F.3d at
357-58.
As Judge O’Scannlain recognized, “[t]his circuit
split remains, as the Second Circuit has never
reversed itself.” App.19a. Accordingly, district courts
within the Second Circuit continue to apply Atlantic
States to dismiss citizen suits that, like
Soundkeeper’s here, seek to enforce permit conditions
broader in scope than the CWA’s requirements.3
2. The Ninth Circuit’s decision below squarely
conflicts with Atlantic States. The court held that
Soundkeeper may enforce “all [ISGP] conditions” in
3
See, e.g., Alliance For Env’t Renewal, Inc. v. Pyramid
Crossgates Co., 436 F.3d 82, 84-85 (2d Cir. 2006); Long Island
Soundkeeper Fund, Inc. v. New York City Dep’t of Env’t Prot., 27
F. Supp. 2d 380, 386 (E.D.N.Y. 1998).
18
federal court, including those adopted under statelaw authority that “prescribe ‘a greater scope of
coverage’” than the CWA. App.12a-13a. That is the
exact opposite of what Atlantic States held—that
citizens lack standing under the CWA to enforce
state-law conditions that go beyond the CWA’s
requirements. See 12 F.3d at 358-60. Moreover, in
reaching this holding, the Ninth Circuit reaffirmed its
earlier ruling in NWEA II, which the panel and
concurring opinions below both explicitly recognized
had created a “circuit split” with, and “directly
conflicts” with, Atlantic States. App.13a, 18a-19a.
NWEA II involved a citizen suit brought against
the City of Portland to enforce Oregon’s generic
water-quality standards, which were incorporated
into Portland’s NPDES permit. 56 F.3d at 982. The
CWA does not require permittees to comply with such
standards; rather, it instructs States to use their
water-quality
standards
to
set
“effluent
limitations”—specific restrictions on the amount of
pollutants that can be discharged—and to incorporate
those limitations into NPDES permits. 33 U.S.C.
§ 1311(b). Portland thus argued that the court lacked
jurisdiction over the citizen group’s claims because
they were based on state-law standards that went
beyond the scope of the CWA. 56 F.3d at 986-90.
Initially, the Ninth Circuit panel agreed. In an
opinion by Judge Ingram (a district judge sitting by
designation), the majority highlighted the absence of
“a single case in which a court held that citizen suits
could be used to enforce [state] water quality
standards” in federal court. Northwest Env’t Advocs.
v. City of Portland, 11 F.3d 900, 907-11 (9th Cir.
1993). The majority concluded that such standards
19
should be enforced “in the state courts,” not “by way
of a citizen suit” in federal court. Id. at 911.
Judge Pregerson dissented from that ruling. But
then, the panel granted rehearing and adopted Judge
Pregerson’s position in another divided ruling. In the
revised opinion—authored by Judge Pregerson and
joined by Judge Ingram—the majority concluded that
the citizen-suit provision “authorizes citizens to
enforce all permit conditions” in federal court. NWEA
II, 56 F.3d at 985-90. In so holding, the new majority
leaned heavily on the CWA’s legislative history,
claiming it reflected a concern “about nonenforcement” and an intent to “grant broad authority
for citizen enforcement.” Id. at 986-87. Thus,
according to the majority, the CWA’s citizen-suit
provision allows citizens to enforce permit conditions
based on state standards that “regulate discharges
outside the scope of the [CWA].” Id. at 988-89.
Judge Kleinfeld dissented. He argued that state
water-quality
standards,
while
useful
for
“government enforcement authorities (who decided
not to prosecute this case against the City of
Portland),” are “too uncertain and amorphous” to be
implemented by private citizens and federal courts.
Id. at 992. He emphasized that “citizens’ suits may
produce too much of a good thing with regard to
enforcement,” particularly because the “burdens” on
courts and regulated parties often outweigh the
“improvement” in water quality. Id. at 992-93. He
further warned that “[i]f the private advocacy group”
which brought the action prevailed, it would extract
“a great deal of money from the citizens of Portland.”
Id. at 992.
The full Ninth Circuit declined to rehear the case
en banc, with four judges dissenting. NWEA III,
20
74 F.3d at 946. In an opinion by Judge O’Scannlain,
the dissenters argued that the panel opinion
“significantly reshaped federal environmental law,”
contravened “the plain language of the [CWA],”
“upset the delicate balance envisioned by Congress in
its promulgation of the current enforcement regime
for environmental law,” sanctioned costly federal
suits “at government expense,” imposed potentially
“astronomical[]” costs to municipalities, and created a
circuit split with the Second Circuit. Id.
As Judge O’Scannlain recognized below, “[t]his
circuit split remains.” App.19a. And it is widely
recognized. For example, multiple district courts
within the Ninth Circuit have acknowledged the
conflict between NWEA II and Atlantic States.4 And
practitioners and practice guides have highlighted it
as well. See, e.g., Roger Hanshaw, State Courts vs.
Federal Courts: Jurisdictional Battles over State
Water Quality Standards, 31 Nat. Res. & Env’t 12, 14
(2016) (“Until the Supreme Court advises the
environmental legal community otherwise, Atlantic
States will remain a consideration that every citizen
suit litigant must address when assessing whether
federal jurisdiction exists over an alleged claim under
4
See, e.g., Citizens’ All. for Prop. Rts. v. City of Duvall,
No. C12-1093RAJ, 2014 WL 1379575, at *2 (W.D. Wash. Apr. 8,
2014) (“Although some courts disagree, the Ninth Circuit has
held that citizens may enforce ‘permit conditions based on both
EPA-promulgated effluent limitations and state-established
standards.’” (quoting NWEA II, 56 F.3d at 988 and citing
Atlantic States)), aff’d, 636 F. App’x 430 (9th Cir. 2016); Gill v.
LDI, 19 F. Supp. 2d 1188, 1195 (W.D. Wash. 1998) (explaining
that the Ninth Circuit’s rule in NWEA II conflicts with the
Second Circuit’s from Atlantic States).
21
the [CWA].”).5 This acknowledged circuit conflict
alone warrants this Court’s review.
3. But the split runs deeper than simply the
Second and Ninth Circuits. The Fourth and Eleventh
Circuits, as well as district courts across the country,
have sided with the Ninth Circuit and observed that
citizens can enforce any condition in a state-issued
pollutant-discharge permit—without limitation.
Oftentimes, these courts have acknowledged that
their positions conflict with Atlantic States.
In Parker v. Scrap Metal Processors, Inc., for
example, the Eleventh Circuit expressly rejected the
reasoning of Atlantic States in concluding that
citizens could enforce any “state law standard[]”
embedded in Georgia’s General Storm Water Permits.
386 F.3d 993, 1005-06 (11th Cir. 2004). The Eleventh
Circuit drew on Culbertson v. Coats American, Inc.,
913 F. Supp. 1572 (N.D. Ga. 1995), which explicitly
held that the CWA “authorizes citizen suits for the
enforcement of all conditions of [state-issued
pollutant-discharge] permits,” including those
mandating compliance with all state water laws.
Parker, 386 F.3d at 1008 (emphasis added) (quoting
Culbertson, 913 F. Supp. at 1581).
Post-Parker, district courts within the Eleventh
Circuit have sanctioned citizen suits based on permit
conditions adopted under state law that extend
5
See also 2A Env’t Law Practice Guide § 12A.04 (2024)
(explaining that NWEA II “rejected th[e] view” from Atlantic
States that permit conditions issued under the authority of state
law are not enforceable in federal court); 1 Linda A. Malone,
Env’t Reg. of Land Use § 8:11 n.36 (2024) (discussing the
conflicting holdings in Atlantic States and NWEA II, and listing
these two cases among the four “significant cases” that “have
addressed the scope of citizen suits under” the CWA).
22
beyond the CWA’s scope. See, e.g., New Manchester
Resort & Golf, LLC v. Douglasville Dev., LLC, 734 F.
Supp. 2d 1326, 1337-39 (N.D. Ga. 2010) (citing NWEA
II and Parker in sanctioning a citizen suit based on
“Georgia’s in-stream water quality standards,” which
govern discharges to artificial and subsurface
waters); Parris v. 3M Co., 595 F. Supp. 3d 1288, 1324
(N.D. Ga. 2022) (citizen suit alleging violations of
town’s sewer-use ordinance and State’s water-quality
laws incorporated into a permit).
The Fourth Circuit has likewise held that a permit
holder “must comply with all the terms of its permit”
to avoid citizen suits, including state regulations
“incorporated in” a permit that govern issues other
than the discharge of CWA-regulated pollutants.
Ohio Valley Env’t Coal. v. Fola Coal Co., 845 F.3d 133,
134-36, 143 (4th Cir. 2017). And district courts within
the Fourth Circuit have followed suit, with many
expressly rejecting Atlantic States’s reasoning along
the way. See, e.g., Ohio Valley Env’t Coal., Inc. v. Fola
Coal Co., No. 12-3750, 2013 WL 6709957, at *18
(S.D.W. Va. Dec. 19, 2013) (“reject[ing] [the]
reasoning” of Atlantic States and holding that citizens
can enforce in federal court all “state law standards”
incorporated into a permit); Ohio Valley Env’t Coal.,
Inc. v. Marfork Coal Co., 966 F. Supp. 2d 667, 684-85
(S.D.W. Va. 2013) (holding that citizens can enforce
state-law water-quality standards, even those
pertaining to pollutants for which a permit “did not
establish specific permit effluent limitations”).
Finally, district courts in other circuits have also
blessed citizen suits enforcing state-authorized
permit conditions beyond the scope of CWA’s
requirements, usually acknowledging that doing so
conflicts with Atlantic States. See, e.g., Harpeth River
23
Watershed Ass’n v. City of Franklin, No. 14-1743,
2016 WL 827584, at *3 (M.D. Tenn. Mar. 3, 2016)
(disagreeing with Atlantic States and refusing to
consider whether permit conditions adopted under
state-law authority were “beyond the scope” of the
CWA); Stephens v. Koch Foods, LLC, 667 F. Supp. 2d
768, 783 (E.D. Tenn. 2009) (citing courts holding “that
plaintiffs have standing by alleging a violation of any
NPDES permit condition”).
4. Federal jurisdiction to entertain citizen suits
under the CWA should not vary based on geographic
circumstance. Petitioners strongly believe that the
Ninth Circuit’s position is wrong. But if the Court
disagrees, then there is no basis to deny such
jurisdiction to citizens in the Second Circuit. Either
way, there should be one national rule on this
important and recurring federal question.
The
Court’s intervention is needed to resolve this conflict.
II. The Ninth Circuit’s Decision Is Wrong
This conflict and confusion among the lower courts
is reason enough to grant review. But certiorari is
also warranted because the decision below is wrong.
Interpreting the CWA’s citizen-suit provision to allow
federal lawsuits over permit conditions that exceed
the scope of the CWA distorts the statutory text,
ignores EPA’s own regulations, produces significant
and anomalous consequences, and raises serious
constitutional concerns. The Ninth Circuit’s flawed
interpretation of an important federal statute
demands this Court’s correction.
1. The Ninth Circuit’s rule flouts the CWA’s plain
terms. Section 505 of the CWA authorizes citizen
suits—and grants federal jurisdiction—to enforce an
“effluent standard or limitation” under the CWA. 33
24
U.S.C. § 1365(a). “[E]ffluent standard or limitation,”
in turn, is defined to include “a permit or condition of
a permit” if it is “issued under section 1342 of this
title.” Id. § 1365(f) (emphasis added).
The term “under” means “[w]ith the authorization
of” or “by virtue of.”
The American Heritage
Dictionary 1395 (1978). As a result, permit conditions
are enforceable in citizen suits only if issued
“‘pursuant to,”’ or “‘by reason of the authority of,”’ 33
U.S.C. § 1342. Ardestani v. INS, 502 U.S. 129, 135 &
n.2 (1991) (interpreting “expenses awarded under this
subsection”); see Florida Dep’t of Revenue v. Piccadilly
Cafeterias, Inc., 554 U.S. 33, 52-53 (2008) (“under
Chapter 11” means “pursuant to” Chapter 11). The
“effluent standards or limitations” enforceable in
federal court under Section 505 thus encompass only
those conditions issued under the authority of the
NPDES program. They do not cover any other
possible condition a State might add to a permit under
state-law authority, simply because part of that
permit implements the NPDES program.
The Ninth Circuit effectively rewrote the statute.
It held that an “effluent standard or limitation”
includes any “‘permit or condition thereof …’”—
omitting the crucial qualifying phrase “‘issued under
section [1342].’” NWEA II, 56 F.3d at 986 (ellipsis in
original). Only by excising this language could the
court assert that the CWA allows citizens to sue to
enforce any “permit or condition thereof.” Id.
Courts may not read words out of a statute. That
is especially true for the CWA, a “carefully drawn”
statute in which Congress “carefully addressed” the
“balance of public and private interests” implicated by
the Act. International Paper Co. v. Ouellette, 479 U.S.
481, 494 (1987). Through the CWA, Congress did not
25
grant private citizens a cause of action in federal court
to enforce state pollutant-discharge regulations
broader in scope than the requirements of the CWA.
Instead, Congress carefully defined and limited its
grant of jurisdiction to avoid overburdening federal
courts, while leaving States free to adopt broader
regulations under their own state-law authority.
Rewriting the statute to confer jurisdiction on federal
courts to enforce state-law permit conditions disrupts
the “[careful] balance” Congress struck. Id. at 494-95.
2. Other interpretative tools confirm the statute’s
plain text. For example, the definition of “effluent
standard or limitation” includes seven categories of
enforceable restrictions, including the “permit or
condition thereof” provision.
See 33 U.S.C.
§ 1365(f)(1)-(7). None of the other six categories
includes state-law matters; they all address federal
obligations. Id. Those surrounding categories “cabin
the contextual meaning” of Section 505, Yates v.
United States, 574 U.S. 528, 543 (2015) (plurality
opinion), confirming that it covers only federal, not
state-law, conditions.
EPA’s “contemporaneous[]” understanding of the
CWA—an “especially useful” tool of statutory
construction—cements
this
commonsense
construction. Loper Bright Enters. V. Raimondo, 144
S. Ct. 2244, 2262 (2024). The CWA empowers EPA,
like private citizens, to enforce violations of
“condition[s] or limitation[s] … in a permit issued
under section 1342 of this title.”
33 U.S.C.
§ 1319(a)(3).
Shortly after these enforcement
provisions were enacted, EPA issued a regulation that
clearly delineated the CWA’s limits, cautioning that,
“[i]f an approved State program has greater scope of
coverage than required by Federal law[,] the
26
additional coverage is not part of the Federally
approved program.” 40 C.F.R. § 123.1(i)(2). For
example, EPA noted that, “if a State requires permits
for discharges into publicly owned treatment works,
these permits are not NPDES permits.” Id. § 123.1
second note. This regulation remains in effect today.
And EPA has clarified the obvious implications of it:
“Nor would these State-law requirements be federally
enforceable” by citizens or EPA. 73 Fed. Reg. 70418,
70458 (Nov. 20, 2008) (citing 40 C.F.R. § 123.1(i)(2)).
This longstanding interpretation of the CWA—not
the Ninth Circuit’s—is the correct one.
Moreover, EPA and lower courts have interpreted
the nearly identical enforcement provisions of the
federal Resource Conservation and Recovery Act
(“RCRA”), 42 U.S.C. § 6901 et seq., which governs the
management of solid and hazardous waste, to exclude
state requirements that exceed federal standards.
When EPA adopted comparable regulations for
RCRA, 40 C.F.R. § 271.1, it explained that it “may not
enforce that portion of a state program which is
broader in scope of coverage than the Federal
regulatory program,” Memorandum from William A.
Sullivan, Jr., EPA Enforcement of RCRA-Authorized
State Hazardous Waste Laws and Regulation,
Directive No. 9541.01-82x (Mar. 15, 1982),
https://rcrapublic.epa.gov/files/12046.pdf.
Applying
that guidance, even courts on the Ninth Circuit’s side
of the split have refused to allow federal enforcement
of state-law solid-waste requirements that lack a
counterpart in the federal RCRA program. See, e.g.,
United States v. Recticel Foam Corp., 858 F. Supp.
726, 742 (E.D. Tenn. 1993); Covington v. Jefferson
County, 358 F.3d 626, 642 (9th Cir. 2004). Their
27
contrary position on the nearly identical CWA citizensuit provision is entirely inconsistent.
3. Extending Section 505 to cover permit
conditions beyond the scope of the CWA also leads to
a number of “illogical results”—another red flag.
Jones v. Hendrix, 599 U.S. 465, 480 (2023).
For example, under the Ninth Circuit’s ruling, any
violation of a state-issued permit that incorporates
NPDES requirements would give rise to a citizen
action under the CWA that could result in the
imposition of civil penalties payable to the United
States Treasury and attorney’s fees. See supra at 7.
That makes no sense. Citizen suits exist to ensure
“compliance with the [CWA].” Gwaltney, 484 U.S. at
60 (emphasis added). Congress did not open the
federal courts for the enforcement of all state-law
conditions just because they are included in the same
permit as federal CWA requirements. Nor does it
make sense to impose penalties payable to the U.S.
Treasury for violations of state laws.
The Ninth Circuit went even further here. It held
that Soundkeeper could enforce state-law conditions
on discharges from portions of facilities explicitly
exempted from the CWA’s industrial-stormwater
requirements. See supra at 12-14. But this just puts
the CWA at war with itself, enabling private enforcers
to invoke it to enforce conditions that vitiate
“carefully drawn” federal limits. International Paper
Co., 479 U.S. at 494. Ultimately, the Ninth Circuit’s
rule dismantles the CWA’s precise framework.
Further, under the Ninth Circuit’s rule, one of two
equally untenable outcomes must be true: either
(i) citizens have more enforcement authority in
federal court than EPA; or (ii) EPA has the ability to
28
enforce in federal court state laws incorporated into
NPDES permits. Both scenarios are unacceptable.
As for the first, this Court has repeatedly emphasized
that the citizen-suit provision is only a limited
“supplement[]” to the enforcement powers vested in
EPA. Gwaltney, 484 U.S. at 60; see Middlesex Cnty.
Sewerage Auth. V. National Sea Clammers Ass’n, 453
U.S. 1, 14, 17 n.27 (1981). It would be “paradoxical”
to read the citizen-suit provision as giving citizens
greater enforcement authority than the federal
agency charged with enforcing the statute. Askins v.
Ohio Dep’t of Agric., 809 F.3d 868, 875-76 (6th Cir.
2016) (rejecting interpretation of CWA’s citizen-suit
provision that would “grant citizens greater
enforcement authority than the U.S. EPA”).
As for the second, EPA itself has disavowed
authority to enforce state-law requirements that go
beyond the CWA. Supra at 25-26. And allowing EPA
to enforce matters of state law in federal court would
raise serious federalism concerns. It would encroach
on one of the most fundamental aspects of state
sovereignty—the ability of a State to decide how,
when, and by whom its own laws are enforced—while
undermining the CWA’s express intent to preserve
state primacy in water-quality matters. See 33 U.S.C.
§ 1251(b). An interpretation that leads to this result
cannot be correct either. Indeed, just last year, this
Court rejected an “overly broad interpretation of the
CWA’s reach [that] would impinge on [the States’]
authority” where Congress failed to “‘enact
exceedingly clear language’” expressing a desire to
“‘significantly alter the balance between federal and
state power.’” Sackett v. EPA, 598 U.S. 651, 679-80
(2023).
29
The only outcome that avoids these untenable
results is the one already compelled by the statute’s
plain text and EPA’s implementing regulations: the
CWA’s citizen-suit provision does not extend to
permit requirements adopted under state-law
authority that go beyond the scope of the CWA.
4. The Ninth Circuit’s rule also raises serious
constitutional concerns, making it even more
imperative that the CWA’s citizen-suit provision not
be expanded beyond its terms.
First, the Ninth Circuit’s rule creates Article III
problems. Article III of the Constitution gives the
Judiciary authority to hear cases “arising under”
federal law. U.S. Const. art. III, § 2, cl. 1. Under this
Court’s precedents, Congress cannot simply “grant
jurisdiction over a particular class of cases” to meet
Article III’s “arising under” requirement. Verlinden
B.V. v. Central Bank of Nigeria, 461 U.S. 480, 496
(1983); see Mesa v. California, 489 U.S. 121, 136
(1989) (“[P]ure jurisdictional statute[s] … cannot
support Article III ‘arising under’ jurisdiction.”).
Instead, a case must actually “arise under” federal
law for Congress to confer jurisdiction on federal
courts under Article III to adjudicate it.
The Ninth Circuit’s theory ignores that
constitutional line. Soundkeeper claims a federal
right to enforce permit conditions that regulate far
beyond the federal mandate of the CWA, and that are
implemented pursuant to state-law authority that
does not include citizen enforcement. The Ninth
Circuit’s theory turns Section 505 into a jurisdictional
grant that shoehorns state-law claims into federal
court—precisely what Article III prohibits.
30
Moreover, even if this construction didn’t raise
Article III problems, it still violates this Court’s
admonition to strictly construe—not vastly enlarge—
statutes that confer jurisdiction on the federal courts.
See, e.g., Romero v. International Terminal Operating
Co., 358 U.S. 354, 379 (1959) (explaining the “deeply
felt and traditional reluctance of th[e Supreme] Court
to expand the jurisdiction of the federal courts
through a broad reading of jurisdictional statutes”).
Second, the Ninth Circuit’s rule ignores the need
to narrowly construe statutory provisions that
empower private citizens to enforce the law, given
their potential to “intru[de]” on government
enforcement prerogatives. Gwaltney, 484 U.S. at 6061; see Garcia v. Cecos Int’l, Inc., 761 F.2d 76, 81 (1st
Cir. 1985) (Wisdom, J.) (“The Supreme Court has
demanded strict adherence to statutory provisions for
citizens’ suits in environmental litigation.”).
In the citizen-suit context, a private plaintiff is
“basically
unchecked
to
exercise
executive,
prosecutorial authority as a ‘private attorney
general.’” Charles S. Abell, Ignoring the Trees for the
Forests: How the Citizen Suit Provision of the Clean
Water Act Violates the Constitution’s Separation of
Powers Principle, 81 Va. L. Rev. 1957, 1964 (1995). As
a result, private citizens can launch CWA suits for
reasons entirely unrelated to environmental
protection—be it to target industries they dislike,
attract donor dollars, or simply out of spite.
This unchecked power has led Justices of this
Court to repeatedly question whether the citizen-suit
mechanism violates Article II. See Friends of the
Earth, Inc. v. Laidlaw Env’t Servs. (TOC), Inc., 528
U.S. 167, 197 (2000) (Kennedy, J., concurring); id. at
209 (Scalia, J., joined by Thomas, J., dissenting); DOT
31
v. Association of Am. Railroads, 575 U.S. 43, 62 (2015)
(Alito, J., concurring); see also United States ex rel.
Polansky v. Executive Health Res., Inc., 599 U.S. 419,
442-450 (2023) (Kavanaugh, J., joined by Barrett, J.,
concurring) (recognizing the “substantial arguments”
that qui tam suits violate Article II for similar
reasons). Here, the Ninth Circuit’s rule raises
significant federalism concerns to boot by intruding
on the sovereign ability of States to choose when and
how to enforce their own environmental laws and
conditions. See infra at 35-36.
The Ninth Circuit could, and should, have
“avoid[ed] the significant constitutional and
federalism questions” raised by its overly broad CWA
interpretation. Solid Waste Agency of N. Cook Cnty.
v. United States Army Corps of Eng’rs, 531 U.S. 159,
174 (2001). States that wish to enforce state-law
conditions in pollutant-discharge permits have the
authority and ability to do so under state law. But
Congress did not unleash a force of unchecked private
attorneys general to invoke the jurisdiction of the
federal courts to do so in their stead.
III. The Question Presented Is Important And
Warrants This Court’s Review In This Case
The importance of the question presented
underscores the need for this Court’s intervention.
1. This Court has repeatedly intervened to
enforce the careful balance struck by the CWA and
protect against overregulation. See, e.g., Sackett v.
EPA, 142 S. Ct. 896 (2022) (granting certiorari);
County of Maui v. Hawaii Wildlife Fund, 139 S. Ct.
196 (2019) (same); Decker v. Northwest Env’t Def. Ctr.,
567 U.S. 933 (2012) (same); Los Angeles Cnty. Flood
Control Dist. v. Natural Res. Def. Council, Inc., 567
32
U.S. 933 (2012) (same); see also City & Cnty. of S.F. v.
EPA, 144 S. Ct. 2578 (2024) (same).
The Court’s intervention is likewise needed here.
As Judge O’Scannlain observed, the Ninth Circuit’s
expansive interpretation of the CWA’s citizen-suit
provision upsets the “delicate balance envisioned by
Congress in its promulgation of the current
enforcement regime for environmental law.” App.20a
(citation omitted). Indeed, under the Ninth Circuit’s
rule, citizens—without any of the institutional checks
governing enforcement agencies—can invoke the
jurisdiction of the federal courts and assert even
“technical” violations of state-law conditions that go
beyond the scope of the CWA. Jonathan H. Adler,
Stand or Deliver: Citizen Suits, Standing, and
Environmental Protection, 12 Duke Env’t L. & Pol’y
F. 39, 43, 49-50, 56-57, 62 (2001); see also Rick W.
Jarvis, A City Attorney’s Citizens’ Suit Survival
Guide, League of California Cities (May 1996)
(apprising city attorneys on citizens’ “creative”
theories for bringing federal actions against
municipalities, including by threatening to sue over
violations of California “Discharge Requirements”
that are “far broader than” the CWA’s requirements).6
In practice, this dynamic has created its own
unique breed of professional “citizen suit” plaintiff.
Soundkeeper is a good example. According to its
website, Soundkeeper has filed more than 170 CWA
citizen-suit actions in federal court since 1992—many
of which alleged violations of permit conditions that
6
https://www.cacities.org/UploadedFiles/LeagueInternet/
2a/2a7c5332-7aef-4598-9218-c60b795f8119.pdf.
33
go beyond the CWA.7 Indeed, Soundkeeper has
already brought another lawsuit against SSA alleging
ISGP violations from stormwater runoff at a wharf.8
Imposing the ISGP’s complex—and often infeasible—
permit requirements on overwater, non-industrial
areas like the Wharf makes them an easy target for
citizen suits. The prospect of attorney’s fees only
heightens the appeal of bringing such suits. And the
combination of ever-expanding state-law conditions
and the possibility of lucrative fee awards—without
the traditional checks on prosecutorial overreach or
agency discretion—is a recipe for never-ending
litigation never intended by Congress.
Moreover, these professional “citizen suit”
plaintiffs target an increasingly expanding
community regulated under complex and far-reaching
permits. NPDES permits are ubiquitous: The federal
government estimates that more than 330,000 project
operators nationwide maintained active NPDES
permits in fiscal year 2020. U.S. Gov’t Accountability
Off., Clean Water Act: EPA Needs to Better Assess and
Disclose Quality of Compliance and Enforcement Data
7 (July 2021).9 And forty-seven States issue those
NPDES permits themselves, often incorporating
7
See Puget Soundkeeper, Clean Water Act Lawsuits,
https://pugetsoundkeeper.org/strategy-citizen-lawsuits/
(last
visited Sept. 18, 2024) (“CWA Lawsuits”).
8
See Puget Soundkeeper All. v. SSA Marine, Inc., No. 24cv-00438 (W.D. Wash. filed Apr. 1, 2024); see also, e.g.,
Communities for a Healthy Bay v. Husky Terminal &
Stevedoring, LLC, No. 24-cv-05662-BHS (W.D. Wash. filed Aug.
12, 2024) (another citizen group alleging violations of the ISGP
at a wharf).
9
https://www.gao.gov/assets/gao-21-290.pdf.
34
exclusively state requirements on top of the CWA
requirements.
For example, multiple States have incorporated
into their NPDES permits conditions on discharging
pollutants to groundwater—even though Congress
expressly exempted such discharges from the CWA.10
And citizen-suit plaintiffs have taken note—bringing
federal suits to enforce those broader conditions.11
The consequences of this enforcement regime are
particularly severe for municipalities and public
entities like the Port of Tacoma.
Complex
environmental litigation is increasingly expensive,
particularly given the CWA’s near-mandatory (for
plaintiffs) fee-shifting provision. 33 U.S.C. § 1365(d);
see Saint John’s Organic Farm v. Gem Cnty.
Mosquito Abatement Dist., 574 F.3d 1054, 1063-64
(9th Cir. 2009) (a district court’s discretion to deny a
prevailing citizen fees “is narrow”).
As Judge
O’Scannlain noted, the Ninth Circuit rule “promises
to invite excessive, costly, and counterproductive
10
See, e.g., Maryland Dep’t of the Env’t v. Assateague
Coastal Tr., 299 A.3d 619, 633-34 (Md. 2023); In re Reissuance of
an NPDES/SDS Permit to United States Steel Corp., 954
N.W.2d 572, 577 (Minn. 2021).
11 See, e.g., Yadkin Riverkeeper, Inc. v. Duke Energy
Carolinas, LLC, 141 F. Supp. 3d 428, 448 (M.D.N.C. 2015)
(allowing citizens to enforce permit conditions that applied to
groundwater and surface water and that regulated the safety of
dams); Cape Fear River Watch, Inc. v. Duke Energy Progress,
Inc., No. 7:13-cv-200, 2014 WL 10991530, at *1 (E.D.N.C. Aug.
1, 2014) (holding that a State has the “ability … to regulate
groundwater on its own by imposing NPDES permit conditions”
and a citizen can enforce such provisions); Okanogan Highlands
All. v. Crown Res. Corp., 544 F. Supp. 3d 1092, 1097 (E.D. Wash.
2021) (allowing citizens to enforce conditions of a combined
permit regulating groundwater).
35
citizen suits, funded by the taxpayers, for the
enforcement of standards that are imprecise and
astronomically costly to the municipalities affected.”
NWEA III, 74 F.3d at 946. Given the limited
resources available to government entities, litigation
expenses can divert funds from essential government
programs—costs
that
taxpayers
themselves
ultimately bear. See Susan A. Macmanus, The Impact
of Litigation on Municipalities: Total Cost, Driving
Factors, and Cost Containment Mechanisms, 44
Syracuse L. Rev. 833, 840-41 (1993).
The Ninth Circuit’s rule also harms the States by
undermining “the CWA’s express policy to ‘preserve’
the States’ ‘primary’ authority over land and water
use.” Sackett, 598 U.S. at 680 (quoting 33 U.S.C
§ 1251(b)). Many States, including Washington, have
chosen not to grant their citizens a cause of action to
enforce their water laws. See James R. May, The
Availability of State Environmental Citizen Suits, 18SPG Nat. Res. & Env’t 53, 56 (2004, Westlaw). For
good reason: States often need to rely on their own
enforcement discretion when experimenting with
more stringent regulatory approaches. Allowing
private parties to make their own enforcement
decisions can “frustrate” the very “objective[s] of
environmental protection” by subjecting parties—
especially municipalities—to litigation the State has
chosen not to invite. Frank B. Cross, Rethinking
Environmental Citizen Suits, 8 Temp. Env’t L. &
Tech. J. 55, 64 (1989, Westlaw).
Indeed, in light of the significant costs associated
with obtaining compliance with its industrialstormwater requirements on the entirety of an
industrial facility, Ecology specifically told ports it
would use its “enforcement discretion” to allow time
36
to comply. 4-ER-746. Yet the decision below allows
citizens to override the State’s discretion and enlist
federal courts to enforce Washington’s requirements,
supplanting
(i)
Washington’s
enforcement
prerogatives, (ii) the CWA’s cooperative federalism,
and (iii) this Court’s precedents limiting citizen suits
to a “supplementary role.” Gwaltney, 484 U.S. at 60.
The fact that this case arises from the Ninth
Circuit—the nation’s largest circuit and a magnet for
environmental litigation—amplifies the need for
review. Environmental plaintiffs flock to the Ninth
Circuit to launch their citizen suits, drawn by the
sweeping environmental laws of its States. See, e.g.,
David Adelman & Robert Glicksman, Reevaluating
Environmental Citizen Suits in Theory and Practice,
91 Colo. L. Rev. 386, 430-31, 439-40 (2020). Many of
these suits seek to enforce state-law permit conditions
that are increasingly vague and expansive, extending
well beyond federal requirements. Supra at 32-34.
The Ninth Circuit’s unequivocal reaffirmation of its
overly broad interpretation of the CWA’s citizen-suit
provision will only invite more such actions.
2. This case is an ideal vehicle for resolving the
question presented. Although citizen groups send
hundreds of notices of intent to sue annually, very few
citizen-suit cases make it to the courts of appeals, let
alone this Court, because the costs and burdens of
such litigation often force citizen-suit defendants to
settle, rather than fight. See Friends of the Earth, 528
U.S. at 209-10 (Scalia, J., dissenting) (observing how
citizen plaintiffs’ “massive bargaining power ... is
often used to achieve settlements requiring the
defendant to support environmental projects of the
plaintiffs’ choosing”); Marc Robertson, Environmental
Ambulance Chasing: DOJ Urges Court To Scrutinize
37
Clean Water Citizen-Suit Settlements, Forbes
(June 26, 2018) (describing a Department of Justice
court filing raising concerns about abusive CWA
citizen suits). Indeed, Soundkeeper’s own website
proudly boasts that most of its citizen suits “resolve[]
without going to trial.”12 This Court should not miss
this opportunity to settle a well-entrenched circuit
split over the breadth of the citizen-suit provision.
This case offers an ideal vehicle to do so. The
question presented was dispositive to the judgment
below and pressed at every step of this case. See
App.11a, 6a.
The Ninth Circuit’s rejection of
petitioners’ position on the question presented was its
sole basis for allowing Soundkeeper’s suit against the
Port to proceed once the Ninth Circuit determined
that the ISGPs cover discharges from the Wharf. See
App.11a-13a. And both the panel opinion and Judge
O’Scannlain’s special concurrence fully ventilated
this issue and acknowledged the direct circuit conflict.
In short, the question presented clearly warrants
review and is cleanly presented here.
12
See CWA Lawsuits, supra.
38
CONCLUSION
The petition for a writ of certiorari should be
granted.
Respectfully submitted,
BRADFORD T. DOLL
LYNNE M. COHEE
FOSTER GARVEY PC
1111 Third Avenue
Suite 3000
Seattle, WA 98101
Counsel for Petitioner
Port of Tacoma
BRADLEY B. JONES
DIANNE K. CONWAY
GORDON THOMAS
HONEYWELL LLP
1201 Pacific Avenue
Suite 2100
Tacoma, WA 98402
Counsel for Petitioners
SSA Terminals, LLC, and
SSA Terminals (Tacoma),
LLC
September 25, 2024
GREGORY G. GARRE
Counsel of Record
ROMAN MARTINEZ
BLAKE E. STAFFORD
CHRISTINA R. GAY
LATHAM & WATKINS LLP
555 Eleventh Street, NW
Suite 1000
Washington, DC 20004
(202) 637-2207
gregory.garre@lw.com
Counsel for Petitioners
Port of Tacoma,
SSA Terminals, LLC,
and SSA Terminals
(Tacoma), LLC
APPENDIX
TABLE OF CONTENTS
Page
Opinion of the United States Court of Appeals
for the Ninth Circuit, Port of Tacoma v.
Puget Soundkeeper, 104 F.4th 95 (9th Cir.
2024) ....................................................................1a
Order of the United States District Court of the
Western District of Washington Granting
Port of Tacoma Motion for Partial
Summary Judgment, Puget Soundkeeper
Alliance v. APM Terminals Tacoma, LLC,
No. C17-5016 BHS, 2020 WL 6445825
(W.D. Wash. Nov. 3, 2020) ...............................21a
Order of the United States District Court of the
Western District of Washington Granting
SSA Terminals, LLC, and SSA Terminals
(Tacoma), LLC, Motion for Summary
Judgment, Puget Soundkeeper Alliance v.
SSA Terminals, LLC, 561 F. Supp. 3d 1113
(W.D. Wash. 2021) ............................................48a
Order of the United States District Court of the
Western District of Washington Granting
Defendant’s Motion for Entry of Rule 54(b)
Judgment, Puget Soundkeeper Alliance v.
SSA Terminals, LLC, No. C17-5016 BHS,
2021 WL 4226162 (W.D. Wash. Sept. 16,
2021) ..................................................................70a
33 U.S.C. § 1342(a), (p) ...........................................76a
33 U.S.C. § 1365 ......................................................82a
40 C.F.R. § 123.1 .....................................................86a
1a
UNITED STATES COURT OF APPEALS
FOR THE NINTH CIRCUIT
PUGET SOUNDKEEPER ALLIANCE,
Plaintiff-Appellant,
v.
PORT OF TACOMA; SSA Terminals LLC;
SSA Terminals (Tacoma), LLC, DefendantsAppellees,
and
APM Terminals Tacoma LLC; Don Esterbrook,
Defendants.
Puget Soundkeeper Alliance, PlaintiffAppellee,
v.
Port of Tacoma, Defendant-Appellant,
and
SSA Terminals LLC; SSA Terminals (Tacoma),
LLC; APM Terminals Tacoma LLC; Don
Esterbrook, Defendants.
Puget Soundkeeper Alliance, PlaintiffAppellee,
v.
SSA Terminals LLC; SSA Terminals (Tacoma),
LLC, Defendants-Appellants,
and
Port of Tacoma; APM Terminals Tacoma LLC;
Don Esterbrook, Defendants.
No. 21-35881
No. 21-35899
No. 22-35061
2a
Argued and Submitted December 7, 2022
Submission Withdrawn August 18, 2023
Resubmitted June 10, 2024
Seattle, Washington
Filed June 10, 2024
[104 F.4th 95]
Before: Diarmuid F. O’Scannlain, M. Margaret
McKeown, and Eric D. Miller, Circuit Judges.
Opinion by Judge Miller;
Special Concurrence by Judge O’Scannlain
OPINION
MILLER, Circuit Judge:
Discharges of stormwater are not generally
regulated under the Clean Water Act, but they are
regulated when they result from certain industrial
activities. This case involves a facility that conducts
such activities. The question presented is whether
regulation extends to all discharges from the facility
or only to discharges from the portions of the facility
where the industrial activities occur. We consider
that question in the context of several different
versions
of
Washington
State’s
Industrial
Stormwater General Permit, which implements the
Clean Water Act in Washington. With respect to
those permits that have not been challenged in state
court, we conclude that the plain text of the permits
extends coverage to the entire facility and that the
validity of the permits is not subject to collateral
attack in federal court. We therefore reverse the
district court’s contrary determination. With respect
to the permit that is subject to an ongoing state-court
challenge, we remand to allow the district court to
3a
consider in the first instance the effect of the state
proceedings on this case.
I
The Clean Water Act prohibits “the discharge of
any pollutant by any person” into the waters of the
United States without a National Pollutant Discharge
Elimination System (NPDES) permit. 33 U.S.C.
§ 1311(a); see NRDC v. County of Los Angeles, 725
F.3d 1194, 1198 (9th Cir. 2013). The Environmental
Protection Agency has authority to issue regulations
implementing the Act, 33 U.S.C. § 1361(a), and to
issue NPDES permits, id. § 1342(a).
The West Sitcum Terminal is a 137-acre marine
cargo terminal located on Commencement Bay, an
arm of Puget Sound, in Tacoma, Washington.
It is operated by the Port of Tacoma and by SSA
Terminals,
LLC
and
affiliated
companies
(collectively, the Port). At issue in this case is a 12.6acre portion of the Terminal, commonly referred to as
“the Wharf,” where five large cranes load and unload
container ships.
When rain falls on the Terminal, stormwater
runs into Puget Sound, carrying with it metals
and other pollutants.
But in recognition that
“[p]ractically speaking, rain water will run downhill,
and not even a law passed by the Congress of the
United States can stop that,” the Clean Water Act
does not require an NPDES permit for all discharges
of stormwater. Hughey v. JMS Dev. Corp., 78 F.3d
1523, 1530 (11th Cir. 1996); see 33 U.S.C. § 1342(p)
(defining the scope of stormwater regulation).
Instead, only certain categories of stormwater
discharges require a permit.
4a
One such category is stormwater discharges
“associated with industrial activity.”
33 U.S.C.
§ 1342(p)(2)(B).
EPA’s regulations define that
category to include discharges from “[t]ransportation
facilities” (further defined as facilities that fall within
specified Standard Industrial Classifications) that
house “vehicle maintenance shops, equipment
cleaning operations, or airport deicing operations.” 40
C.F.R. § 122.26(b)(14)(viii). The Terminal is such a
facility, but the regulations do not require it to control
every discharge of stormwater. Rather, they apply to
“[o]nly those portions of the facility that are . . .
involved in vehicle maintenance . . . , equipment
cleaning operations, [or] airport deicing operations.”
Id. (emphasis added). Because such activities do not
occur at the Wharf, discharges from there do not
require NPDES permits.
Although the EPA has the authority to issue
NPDES permits itself, 33 U.S.C. § 1342(a), it can
delegate that responsibility to the States, id.
§ 1342(b); see Southern Cal. All. of Publicly Owned
Treatment Works v. EPA, 8 F.4th 831, 834 (9th Cir.
2021). It has done so in almost every State, including
Washington. 39 Fed. Reg. 26,061 (1974). Exercising
its delegated authority, Washington regulates
industrial stormwater discharges through a “general
permit,” a single NPDES permit that applies to all
facilities conducting industrial activities that
discharge stormwater to a surface water body or a
storm sewer that drains to one. See Alaska Cmty.
Action on Toxics v. Aurora Energy Servs., LLC, 765
F.3d 1169, 1171 (9th Cir. 2014). That permit, the
Industrial Stormwater General Permit (ISGP), is
issued by the Washington State Department of
Ecology (Ecology), which is responsible for Clean
5a
Water Act permitting on behalf of the State. At issue
here are the three editions of the ISGP issued in 2010,
2015, and 2020, each with a term of five years.
The ISGPs purport to define the requirements of
the Clean Water Act: They state that “[a]ny permit
noncompliance constitutes a violation of the Clean
Water Act.” (Many of the words in the ISGPs are
italicized; we omit the italics throughout.) But
beginning in 2010, Ecology omitted the limiting terms
of the federal regulations—that is, the terms
confining regulation of industrial stormwater to
“[o]nly those portions of a facility” where
vehicle maintenance, equipment cleaning, and
airport deicing take place—from the ISGPs
governing discharges from the Port. 40 C.F.R.
§ 122.26(b)(14)(viii). Instead, the 2010 permit states
that it applies to “[t]ransportation facilities”—not
merely portions of such facilities—“which have
vehicle maintenance shops, material handling
facilities, equipment cleaning operations, or airport
deicing operations.” The relevant provisions of the
2015 and 2020 permits are the same.
Puget Soundkeeper Alliance (Soundkeeper) is an
environmental organization concerned with water
quality in Puget Sound. It brought this action under
the citizen-suit provision of the Clean Water Act,
33 U.S.C. § 1365, alleging that the Port had violated
the Act in various respects. In a memorandum
disposition filed concurrently with this opinion, we
address Soundkeeper’s claims about the discharges
from the Terminal that uncontroversially require
some degree of regulation. In this opinion, we confine
ourselves to considering whether stormwater
discharges from the Wharf are subject to regulation.
6a
The district court granted partial summary
judgment to the Port on that issue. The court held
that the ISGPs do not extend coverage to the entire
footprint of facilities that conduct industrial activity.
Although the “Permit Coverage” sections of the ISGPs
omit the limiting terms from the federal regulations,
the court looked to Table 1, which appears just under
the “Permit Coverage” section of the ISGPs, and
which sets out a list of “activities requiring permit
coverage.” In the 2010 ISGP, the definition section
says that “Table 1 lists the 11 categories of industrial
activities identified in 40 CFR 122.26(b)(14)(i-xi) in a
different format.” Accordingly, the court reasoned,
the inclusion of Table 1 in the ISGPs was tantamount
to the incorporation of the federal regulations,
including section 122.26(b)(14)(viii), which limits the
definition of industrial activity—and thus the scope of
regulatory coverage—to include only the portions of
facilities where that activity takes place. Having
determined that the ISGPs do not extend coverage to
the Wharf, the court did not consider the Port’s
alternative argument that, to the extent the ISGPs do
extend coverage to the Wharf, they may not be
enforced in a citizen suit under the Clean Water Act.
The district court subsequently resolved the
remaining claims and entered a final judgment,
which both sides appealed under 28 U.S.C. § 1291.
II
The district court analyzed all three ISGPs—the
2010, 2015, and 2020 editions—together, but as the
case comes before us, the 2020 ISGP presents distinct
issues from the earlier permits.
We begin by
considering the 2010 and 2015 ISGPs before turning
to the 2020 ISGP.
7a
The district court believed that the ISGPs do
not extend coverage to the Wharf. The Port defends
that interpretation and, alternatively, renews
its argument that if the ISGPs do extend coverage
to the Wharf, they may not be enforced in a citizen
suit under the Clean Water Act. We reject both
arguments.
A
At the outset, we must determine the standard of
review that applies to the ISGPs. The district court
reasoned that “NPDES permits are treated like any
other contract.” County of Los Angeles, 725 F.3d at
1204. But that is true only of an individual permit—
that is, a permit authorizing a particular entity to
discharge a pollutant in a specific place. See Alaska
Cmty. Action on Toxics, 765 F.3d at 1172. An ISGP is
a general permit—that is, a permit that authorizes
discharges by an entire class of potential dischargers
across a region. Id. Because such a permit is more
akin to a regulation, we interpret it as we would a
regulation. Id. In either case, however, we must “give
effect to the natural and plain meaning of [the
permit’s] words.” Id. (quoting Bayview Hunters Point
Cmty. Advocates v. Metropolitan Transp. Comm’n,
366 F.3d 692, 698 (9th Cir. 2004)); accord County of
Los Angeles, 725 F.3d at 1204–05 (“If the language of
the permit, considered in light of the structure of the
permit as a whole, ‘is plain and capable of legal
construction, the language alone must determine the
permit’s meaning.’” (quoting Piney Run Pres. Ass’n v.
County Comm’rs of Carroll Cnty., 268 F.3d 255, 270
(4th Cir. 2001))). We review the district court’s
interpretation de novo. Alaska Cmty. Action on
Toxics, 765 F.3d at 1172.
8a
The 2010 and 2015 ISGPs plainly require that a
transportation
facility
conducting
industrial
activities implement stormwater controls across the
entire facility. The first section of the ISGPs, entitled
“S1. Permit Coverage,” begins by stating that “[t]his
statewide permit applies to facilities conducting
industrial activities that discharge stormwater.”
A facility “shall apply for coverage” if it “conduct[s]
industrial activities listed in Table 1.” Table 1 then
lists industrial activities and includes an entry for
“[t]ransportation facilities which have vehicle
maintenance shops, material handling facilities,
equipment cleaning operations, or airport deicing
operations.” In this respect, the ISGPs differ from the
federal regulations. Under the ISGPs, coverage is
triggered—that is, “[t]his statewide permit applies”—
when the facility conducts industrial activity, not
when a particular discharge is “associated with
industrial activity.” 40 C.F.R. § 122.26(a)(1)(ii). The
nature of the facility, not the nature of the discharge,
determines whether there is coverage. See Puget
Soundkeeper Alliance v. Pollution Control Hearings
Bd., ––– Wash.App.2d ––––, ––––, 545 P.3d 333, 345
(2024) (holding that “it is plain that [the 2020 ISGP]
requires coverage for the land and appurtenances at
any transportation facility that conducts vehicle
maintenance, equipment cleaning, or airport deicing
operations—that is, the entire footprint of the
transportation facility”). Because the Terminal is a
facility conducting industrial activities, the permits
apply to the entire facility, including the Wharf.
The Port argues that regardless of whether the
permits writ large apply to the entire facility, the
specific provisions of the permits—prescribing the
actual substance of the permit-holders’ obligations—
9a
are written so as to control only discharges associated
with industrial activity. To the contrary, the permits’
specific obligations encompass the entire facility.
The ISGPs impose a range of obligations on
permit-holders, all of which are derivative, in one way
or another, of two core obligations: the preparation
of a Stormwater Pollution Prevention Plan and
regular sampling of discharges for pollutants. Those
two obligations apply across the entire facility.
In preparing a Stormwater Pollution Prevention
Plan, the permit-holder must identify and implement
“all known, available, and reasonable methods of
prevention, control and treatment . . . of stormwater
pollution.” The permit offers no qualification or
limitation based on where, on site, the stormwater
pollution originates. A permit-holder must update
the plan if it determines that the current plan would
be “ineffective in eliminating . . . pollutants in
stormwater discharges from the site.” (emphasis
added). The plan evidently concerns reduction of
pollution from the site as a whole, not pollution
associated with specific industrial activities.
Likewise, the permit-holder must sample discharges
from the entire site. Specifically, Condition S4
requires sampling of pollutant levels at “each distinct
point of discharge off-site,” not just at discharge
points associated with industrial activity.
Because the obligations to prepare a Stormwater
Pollution Prevention Plan and to sample encompass
discharges from the entire facility, so, too, do the rest
of the permit’s obligations, such as the obligations to
inspect discharges from the facility, to monitor
discharges for exceedances of benchmark levels, to
take corrective actions when pollutant levels in
discharges exceed applicable benchmarks, and
10a
to comply with water quality standards. Consistent
with the opening sentence of the permits, the permits
“appl[y]” to the entire Terminal.
Where the ISGPs limit the scope of their coverage,
they say so clearly by exempting discharges or
applying specific rules to them. For instance, “if any
part of a facility . . . has a stormwater discharge”
containing certain toxic pollutants, the permit-holder
must secure an “individual NPDES” permit for that
discharge. Similarly, the permits explain that “[f]or
sites that discharge to both surface water and ground
water, the terms and conditions of this permit shall
apply to all ground water discharges,” but permittees
“are not required to sample on-site discharges to
ground.” Those carve-outs underscore that, in the
ordinary course, the permits require compliance
across discharges at an entire facility.
In reaching a contrary conclusion, the district
court focused on the permits’ definition of industrial
activity.
In the 2010 ISGP, the definition of
“industrial activity” includes the following sentence:
“Table 1 lists the 11 categories of industrial activities
identified in 40 CFR 122.26(b)(14)(i-xi) in a different
format.” According to the district court, the ISGP
therefore incorporates the federal regulatory
definition of what industrial activities are covered at
a transportation facility.
The 2015 ISGP does not include that sentence in
its definition of “industrial activity,” so that line of
argument is of limited value in interpreting the 2015
ISGP. Regardless, we read both editions of the permit
as requiring stormwater controls across the entirety
of facilities conducting industrial activity. The permit
“applies to facilities conducting industrial activities,”
not to discharges associated with industrial
11a
activity. Even if the ISGPs mirrored 40 C.F.R.
§ 122.26(b)(14)(viii) by directly stipulating that
“[o]nly those portions of the facility” involved in
vehicle maintenance or equipment cleaning “are
associated with industrial activity,” the permits’
coverage would continue to depend on whether the
facility as a whole “conduct[s] industrial activities,”
not on whether specific discharges are associated with
that activity. See Puget Soundkeeper Alliance, 545
P.3d at 345 (concluding that a contrary interpretation
would require “read[ing] language into the definition
and” making parts of the permit “superfluous”).
Because the 2010 and 2015 ISGPs apply to the
entirety of transportation facilities that conduct listed
industrial activity, and because the Terminal is such
a facility, the Port needed to implement appropriate
stormwater controls across the footprint of the
Terminal while the 2010 and 2015 ISGPs were in
effect.
B
The Port argues that even if the ISGPs do regulate
discharges from the Wharf, they are not enforceable
in a citizen suit because they exceed the requirements
of the federal regulations, and “Ecology never sought
EPA approval to expand the scope of the NPDES
program.” The district court did not reach that
argument, but it was preserved below. Because we
may affirm on any ground supported by the record, we
proceed to consider it. Ellis v. Salt River Project
Agric. Improvement & Power Dist., 24 F.4th 1262,
1268 (9th Cir. 2022).
The Port’s argument is foreclosed by the plain
language of the Clean Water Act’s citizen-suit
provision, which states that “any citizen may
12a
commence a civil action . . . against any person . . .
who is alleged to be in violation of . . . an effluent
standard or limitation under this chapter.” 33 U.S.C.
§ 1365(a). The term “effluent standard or limitation
under this chapter” is defined to include “a permit or
condition of a permit issued under section 1342 of
this title that is in effect under this chapter.” Id.
§ 1365(f)(7); see also id. § 1342 (providing the general
authorization for NPDES permitting). Here, there is
no dispute that the ISGP is “a permit issued under
section 1342,” nor that it was “in effect.” It follows
that Soundkeeper may bring a citizen suit to
challenge an alleged violation of the ISGP. And that
is how we have previously read the statute: “The
plain language of [section 1365] authorizes citizens
to enforce all permit conditions.” Northwest Env’t
Advocs. v. City of Portland, 56 F.3d 979, 986 (9th Cir.
1995); accord County of Los Angeles, 725 F.3d at 1204;
Community Ass’n for Restoration of the Env’t v. Henry
Bosma Dairy, 305 F.3d 943, 956 (9th Cir. 2002); see
also Parker v. Scrap Metal Processors, Inc., 386 F.3d
993, 1008 (11th Cir. 2004).
In urging a contrary result, the Port primarily
argues that cases about the enforceability of permit
conditions are inapposite because they involved
“a condition plainly expressed in a permit.” That is
merely a reprise of the Port’s argument that ISGP’s
plain language does not extend coverage to the Wharf,
an argument that we have already rejected. The Port
also invokes Atlantic States Legal Foundation, Inc. v.
Eastman Kodak Co., in which the Second Circuit
concluded that “state regulations, including the
provisions of [state-issued] permits, which mandate
‘a greater scope of coverage than that required’ by the
federal [Act] and its implementing regulations are not
13a
enforceable through a citizen suit.” 12 F.3d 353, 359
(2d Cir. 1993) (quoting 40 C.F.R. § 123.1(i)(2)), as
amended (Feb. 3, 1994). Whether or not the ISGPs
prescribe “a greater scope of coverage” than the
federal regulations in the sense contemplated by the
Second Circuit, we note that “the holding in
[Northwest Environmental Advocates] directly
conflicts with the Second Circuit’s decision in Atlantic
States,” and we are bound to follow the former.
Northwest Env’t Advocs. v. City of Portland, 74 F.3d
945, 948 (9th Cir. 1996) (O’Scannlain, J., dissenting
from denial of rehearing en banc).
The Port further argues that a State cannot issue
NPDES permits that exceed the stringency of federal
stormwater regulations unless the State formally
“determines that the [stormwater] discharge, or
category of discharges within a geographic area,
contributes to a violation of a water quality standard
or is a significant contributor of pollutants to waters
of the United States.” 40 C.F.R. § 122.26(a)(9)(i)(D).
Assuming, without deciding, that Ecology was
required to make such a determination but failed to
do so, we hold that the Port cannot now collaterally
attack the validity of conditions in the 2010 and 2015
ISGPs.
The Clean Water Act “does not contemplate
federal court review of state-issued permits.”
Southern Cal. All. of Publicly Owned Treatment
Works v. EPA, 853 F.3d 1076, 1086 (9th Cir. 2017)
(quoting American Paper Inst., Inc v. EPA, 890 F.2d
869, 875 (7th Cir. 1989)). “[S]tate officials—not the
federal EPA—have the primary responsibility for
reviewing and approving NPDES discharge permits,
albeit with continuing EPA oversight.” Akiak Native
Cmty. v. EPA, 625 F.3d 1162, 1164 (9th Cir. 2010)
14a
(quoting National Ass’n of Home Builders v. Defenders
of Wildlife, 551 U.S. 644, 650, 127 S.Ct. 2518, 168
L.Ed.2d 467 (2007)).
We have previously observed that the Clean Water
Act “make[s] the states, where possible, the primary
regulators of the NPDES system.” Southern Cal. All.
of Publicly Owned Treatment Works, 853 F.3d at 1086
(quoting American Paper Inst., 890 F.2d at 873).
A party may object to the conditions of a state-issued
permit on the basis of federal law, but “state courts
can interpret federal law, and thus can review and
enjoin state authorities from issuing permits that
violate the requirements of the Clean Water Act.”
Southern Cal. All. of Publicly Owned Treatment
Works, 8 F.4th at 839 (quoting Boise Cascade Corp. v.
EPA, 942 F.2d 1427, 1434 (9th Cir. 1991)). Indeed,
parties seeking review of state decisions about
permits are guaranteed judicial review in state courts
“that is the same as that available to obtain judicial
review in federal court of a federally-issued NPDES
permit.” 40 C.F.R. § 123.30.
The principle that federal courts do not reconsider
the validity of state-issued permits helps explain the
settled rule that “[w]here a permittee discharges
pollutants in compliance with the terms of its NPDES
permit, the permit acts to ‘shield’ the permittee from
liability under the CWA.” County of Los Angeles, 725
F.3d at 1204; see also EPA v. California ex rel. State
Water Res. Control Bd., 426 U.S. 200, 205, 96 S.Ct.
2022, 48 L.Ed.2d 578 (1976); Alaska Cmty. Action on
Toxics, 765 F.3d at 1171. That is, if a permit-holder
complies with the terms of its permit, it need not fear
liability under the Clean Water Act. Neither the EPA
nor a citizen can use an enforcement action or a
citizen suit to revisit the validity of permit conditions.
15a
33 U.S.C. § 1342(k). As the Supreme Court has
explained, “[t]he purpose of [section 1342(k)] seems to
be to . . . relieve [permit holders] of having to litigate
in an enforcement action the question whether their
permits are sufficiently strict. In short, [section
1342(k)] serves the purpose of giving permits
finality.” E. I. du Pont de Nemours & Co. v. Train,
430 U.S. 112, 138 n.28, 97 S.Ct. 965, 51 L.Ed.2d 204
(1977).
Accordingly, Soundkeeper could not hold the Port
liable in a citizen suit on the theory that certain
permit conditions in the ISGP were invalid because
they were overly permissive. By the same token,
however, the Port cannot avoid liability by arguing
that certain terms in its permit are invalid because
they are overly restrictive. We will not consider
collateral attacks on the validity of permit conditions
in the course of an enforcement action or citizen suit,
whether those attacks arise offensively or defensively.
See Sierra Club v. Union Oil Co. of Cal., 813 F.2d
1480, 1488 (9th Cir. 1987) (“The state’s method of
adopting a more stringent standard should be subject
to scrutiny only at the permit issuance stage.”),
vacated, 485 U.S. 931, 108 S.Ct. 1102, 99 L.Ed.2d 264
(1988), reinstated as amended, 853 F.2d 667 (9th Cir.
1988).
Our approach is consistent with that of other
courts that have rejected collateral attacks in Clean
Water Act enforcement actions. In General Motors
Corp. v. EPA, a permit-holder sought to defend
against an EPA enforcement action by arguing that
certain terms in a state-issued permit exceeded the
scope of lawful stormwater regulation under the
Clean Water Act. 168 F.3d 1377, 1379 (D.C. Cir.
1999). The District of Columbia Circuit held that the
16a
EPA had reasonably interpreted the Act to bar
a permit-holder from collaterally attacking “the
validity of its state permit in [a] federal enforcement
proceeding.”
Id. at 1383.
Instead, the court
explained, the Act “remit[s] to a state forum any
attack upon the validity of a state permit.” Id.; accord
Public Int. Rsch. Grp. of N.J., Inc. v. Powell Duffryn
Terminals Inc., 913 F.2d 64, 77–78 (3d Cir. 1990).
Likewise, the Port cannot mount a collateral
attack on the validity of stormwater regulations in the
2010 and 2015 ISGPs. Ecology issued ISGPs in 2010
and 2015 providing that “[a]ny permit noncompliance
constitutes a violation of the Clean Water Act.” The
Port now argues that the ISGPs in fact did not comply
with the Act. The Port could have challenged the
permits before the Washington State Pollution
Control Hearings Board. See Wash. Rev. Code.
§ 43.21B.110(1)(c).
Had the Board issued an
unfavorable decision, the Port could have sought
review in state court. See id. § 43.21B.180. As we will
see, the Port availed itself of just that process when it
came to the 2020 ISGP.
But the Port brought no such challenge to the
stormwater regulations in the 2010 and 2015 ISGPs.
And because it did not, it lost “forever the right to do
so.” Public Int. Rsch. Grp. of N.J., Inc., 913 F.2d at 78
(quoting Texas Mun. Power Agency v. Administrator
of U.S. EPA, 836 F.2d 1482, 1484 (5th Cir. 1988)). The
conditions in the 2010 and 2015 ISGPs are valid and
enforceable, and the Port may be liable for discharges
in violation of their terms.
III
Finally, we turn to the 2020 ISGP. Soon after that
permit was issued, several parties, including
17a
Soundkeeper and the Port, appealed it to the
Washington State Pollution Control Hearings Board.
See Puget Soundkeeper All. v. Department of Ecology,
PCHB No. 19-089c, 2021 WL 1163243 (Mar. 23, 2021).
In March 2021, several months after the district
court’s partial summary judgment order, the Board
issued a decision in which it agreed with the Port that
“Ecology’s deletion of the ‘[o]nly those portions of the
facility’ phrase from the federal regulation does not
change the fact that only specified actions are listed
in the permit coverage section” and that “Ecology’s
claim that the 2020 ISGP covers the entire
transportation facility is without support from the
plain language of the permit.” Id. at *9.
We asked the parties to file supplemental briefs
addressing the preclusive effect, if any, of the Board’s
decision. The Port argued that because the decision
“addressed the same legal issue before this Court, it
should be given preclusive effect” as a matter of issue
preclusion. For its part, Soundkeeper argued that the
Port had forfeited any argument for issue preclusion
and that, in any event, because the Board’s decision
was issued after this court assumed jurisdiction over
the appeal, any preclusive effect is barred by the
priority-of-action rule, under which “the court which
first gains jurisdiction of a cause retains the exclusive
authority to deal with the action until the controversy
is resolved.” Sherwin v. Arveson, 96 Wash.2d 77, 633
P.2d 1335, 1337 (1981).
The Board’s decision was not Washington’s last
word on the interpretation of the 2020 ISGP. After
the parties filed their supplemental briefs in this
court, the Washington Court of Appeals reversed the
Board’s decision. Puget Soundkeeper Alliance, 545
P.3d at 333. Paralleling the reasoning we have
18a
employed in construing the 2010 and 2015 permits,
it held that “if a transportation facility requires
coverage under the 2020 permit because it conducts
vehicle maintenance, equipment cleaning, or airport
deicing operations, coverage under the permit applies
to the entire transportation facility, not just limited
areas.” Id. at 346. The Port has petitioned for review
of that decision in the Washington Supreme Court,
and the petition remains pending.
The district court has not had an opportunity to
consider the effect of the decision of the Washington
Court of Appeals, the pending petition before the
Washington Supreme Court, or the outcome of any
potential remand to the Board. Rather than address
those issues in the first instance, we vacate the
district court’s decision insofar as it resolved the scope
of the 2020 ISGP, and we remand for further
consideration. On remand, the district court may, in
its discretion, evaluate how best to address the risk of
piecemeal litigation and conflicting judgments, and it
may consider any arguments that it determines to be
properly presented to it, including arguments based
on issue preclusion or the priority-of-action rule.
VACATED in part, REVERSED in part, and
REMANDED.
O’SCANNLAIN,
Circuit
Judge,
specially
concurring:
While I concur in the Opinion of the Court because
it faithfully follows Ninth Circuit precedent, I write
separately to address my concern, ever since 1996,
that such precedent is flawed, not only because it
created a circuit split at the time, but because it
continues to expand citizen standing in a way
Congress never intended.
19a
The precedent on which the Opinion correctly
relies is Northwest Environmental Advocates v. City
of Portland, 56 F.3d 979 (9th Cir. 1995) (“NWEA II”).
If NWEA II did not apply, private citizens such as
Puget Soundkeeper Alliance would have no standing
to sue as to that portion of the case dealing with
stormwater discharges from the Wharf.
At the time that NWEA II was published, I and
several other colleagues objected to its holding, noting
that “any citizen will now be permitted to bring a
lawsuit at government expense for the enforcement of
state water quality standards that have not been
translated into effluent limitations in federal
permits.” Nw. Envtl. Advocates v. City of Portland, 74
F.3d 945, 946 (9th Cir. 1996) (O’Scannlain, J.,
dissenting from the denial of rehearing en banc)
(“NWEA II En Banc Dissental”).
I wrote that “the holding in NWEA II directly
conflicts with the Second Circuit’s decision in Atlantic
States Legal Foundation v. Eastman Kodak, 12 F.3d
353 (2d Cir. 1993).” NWEA II En Banc Dissental, 74
F.3d at 948. This circuit split remains, as the Second
Circuit has never reversed itself, and may be a source
of ongoing confusion to parties, such as the Port of
Tacoma, which reasonably cited Atlantic States, in
supplemental briefing, for its holding that Congress
authorized states to enact standards on wastewater
effluent stricter than those mandated by the CWA
and federal EPA regulations, but it only authorized
enforcement of those stricter standards by states or
EPA, not citizens.
Indeed, the holding of NWEA II substantially
altered the regulatory enforcement scheme of the
Clean Water Act in a way that was not envisioned by
Congress. As I objected at the time:
20a
“It should go without saying that the
environment faces real and growing dangers
that warrant protective measures and
challenge us to develop innovative solutions.
Nevertheless, by allowing citizens to enforce
standards that Congress specifically allocated
to government agencies to monitor, the court
has upset the delicate balance envisioned by
Congress in its promulgation of the current
enforcement regime for environmental law.
The result promises to invite excessive, costly,
and counterproductive citizen suits, funded by
the taxpayers, for the enforcement of standards
that are imprecise and astronomically costly to
the municipalities affected.”
NWEA II En Banc Dissental, 74 F.3d at 946.
This objection is as strong today as it was in 1996.
While Judge Miller’s Opinion correctly applies NWEA
II in dealing with the citizen-suit standing issue,
I continue to believe that such precedent
unfortunately goes beyond what Congress intended.
21a
[2020 WL 6445825]
UNITED STATES DISTRICT COURT
WESTERN DISTRICT OF WASHINGTON
AT TACOMA
PUGET
SOUNDKEEPER
ALLIANCE,
Plaintiff,
v.
APM TERMINALS
TACOMA, LLC, et al.,
Defendants.
CASE NO. C17-5016
BHS
ORDER GRANTING
DEFENDANT’S
MOTION FOR
PARTIAL SUMMARY
JUDGMENT AND
MOTION TO SEAL,
DENYING WITHOUT
PREJUDICE
DEFENDANT’S
MOTION IN LIMINE,
AND DENYING
DEFENDANT’S
MOTION FOR LEAVE
TO SUPPLEMENT
THE RECORD
This matter comes before the Court on Defendant
Port of Tacoma’s (“Port”) motion for partial summary
judgment, Dkt. 176, motion to seal, Dkt. 281, motion
in limine, Dkt. 283, and motion for leave to
supplement the record, Dkt. 299. The Court has
considered the pleadings filed in support of and in
opposition to the motions and the remainder of the
file and hereby rules as follows:
22a
I. PROCEDURAL HISTORY
On June 13, 2018, Plaintiff Puget Soundkeeper
Alliance (“Soundkeeper”) filed a third amended
complaint bringing a citizen suit under Section 505 of
the Clean Water Act (“CWA”) as amended, 33 U.S.C.
§ 1365, against Defendants APM Terminals Tacoma,
LLC (“APMT”), the Port, SSA Marine, Inc., and SSA
Terminals, LLC. Dkt. 109.
On November 15, 2018, the Port filed a motion for
summary judgment requesting that the Court dismiss
Soundkeeper’s “claims arising from stormwater
discharges to the Wharf.” Dkt. 176 at 18.
On November 30, 2018, the Washington Public
Ports Association (“WPPA”) and the Washington
Maritime Federation (“WMF”) (collectively “Amici”)
filed a motion for leave to file an amici curiae brief.
Dkt. 182.
On December 3, 2018, Soundkeeper and
Defendants SSA Marine, Inc. and SSA Terminals,
LLC (collectively “SSA”) responded to the Port’s
motion for summary judgment. Dkt. 185. On
December 7, 2018, the Port replied. Dkt. 189.
On May 23, 2019, the Court granted WPPA and
WMF’s motion, renoted the pending dispositive
motions, and requested the parties’ positions on
whether the Court should invite an amicus curiae
brief from the Washington Department of Ecology
(“Ecology”). Dkt. 252.
On June 10, 2019, the Court invited Ecology to
submit an amicus brief. Dkt. 259. On August 16,
2019, Ecology filed a brief. Dkt. 269. On August 30,
2019, Soundkeeper, the Port, and SSA responded.
Dkts. 275, 276, 279.
23a
Also on August 30, 2019, the Port filed a motion to
seal, Dkt. 281, and a motion in limine, Dkt. 283.
On September 6, 2019, Ecology, Soundkeeper, the
Port, and SSA replied to the responses to Ecology’s
amicus brief. Dkts. 290, 291, 292, 293.
On September 16, 2019, Soundkeeper responded
to the Port’s motion in limine. Dkt. 296.
On January 28, 2020, the Port notified the Court
of “administrative appeals filed with the State of
Washington Pollution Control Hearings Board
(“Board”) concerning the new Industrial Stormwater
General Permit effective January 1, 2020 (“2020
ISGP”).” Dkt. 298 at 1.
On August 6, 2020, the Port filed a motion to
supplement the record. Dkt. 299. On August 17,
2020, Soundkeeper responded. Dkt. 301. On August
21, 2020, the Port replied. Dkt. 303.
II. FACTUAL BACKGROUND
At issue in this case are industrial stormwater
discharges at a large marine cargo terminal
(“Terminal”) used for ship unloading and cargo
distribution. The Court will address the stormwater
permitting process in general and then the facts of
this case.
A. The Federal Statutes
The CWA is intended to “restore and maintain the
chemical, physical, and biological integrity of the
Nation’s waters.” 33 U.S.C. § 1251(a). To that end,
the CWA makes it unlawful to discharge any
pollutant from a point source to navigable waters
without a permit. Id. §§ 1311(a), 1362(12). The
National Pollutant Discharge Elimination System
(“NPDES”) program is “[a] central provision of the
Act” requiring that “individuals, corporations, and
24a
governments secure [NPDES] permits before
discharging pollution . . . .” Decker v. Nw. Envtl. Def.
Ctr., 568 U.S. 597, 602 (2013).
To achieve these goals, the CWA “anticipates a
partnership between the States and the Federal
Government.” Arkansas v. Oklahoma, 503 U.S. 91,
101 (1992); Aminoil U. S. A., Inc. v. Cal. State Water
Res. Control Bd., 674 F.2d 1227, 1229–30 (9th Cir.
1982) (the CWA created a “scheme of cooperative
federalism” and “a ‘delicate partnership’ between
state and federal agencies” (citation omitted)). Under
this model of cooperative federalism, the
Environmental Protection Agency (“EPA”) sets
requirements for CWA programs, and then delegates
management of those programs to the states.
Aminoil, 674 F.2d at 1229–30. Delegated states may
then issue NPDES permits. 33 U.S.C. § 1342(b).
Subject to federal approval, states can impose
“requirements [that] are more stringent” than
required by EPA. 40 C.F.R. § 123.1(i)(1). However, if
a “State program has greater scope . . . than required
by Federal law the additional coverage is not part of
the Federally approved program.” Id. § 123.1(i)(2).
“For example, if a State requires permits for
discharges into publicly owned treatment works,
these permits are not NPDES permits.” Id.
As originally enacted, the CWA regulated
virtually all discharges, including all stormwater
discharges. Decker, 568 U.S. at 602. For stormwater,
however, EPA quickly found it impracticable to
regulate the “countless owners and operators of point
sources throughout the country.” Id. As one court
observed, EPA was facing “potentially millions of
NPDES permits,” because “[p]ractically speaking,
rain water will run downhill, and not even a law
25a
passed by the Congress of the United States can stop
that.” Hughey v. JMS Dev. Corp., 78 F.3d 1523, 1530
(11th Cir. 1996). Congress, in response to this
problem (and EPA’s refusal to address millions of
stormwater discharges), amended the CWA in 1987 to
“exempt from the NPDES permitting scheme most
‘discharges composed entirely of stormwater.’”
Decker, 568 U.S. at 603 (quoting 33 U.S.C.
§ 1342(p)(1)). Instead, Congress decided that only
certain stormwater discharges require a permit,
including (as relevant here), discharges “associated
with industrial activity.” 33 U.S.C. § 1342(p)(2)(B).
Congress did not define “associated with
industrial activity” and entrusted EPA to do so.
Decker, 568 U.S. at 604; 33 U.S.C. § 1342(p)(4)
(instructing EPA to issue regulations governing
industrial stormwater discharges).
EPA issued
regulations that identified industrial activities by
standard industrial classifications. Relevant here,
EPA included transportation facilities that have
“vehicle maintenance shops, equipment cleaning
operations, or airport deicing operations.” 40 C.F.R.
§ 122.26(b)(14)(viii). EPA’s regulations explain that
“[o]nly those portions of the facility that are either
involved in vehicle maintenance (including vehicle
rehabilitation, mechanical repairs, painting, fueling,
and lubrication), equipment cleaning operations, [or]
airport deicing operations . . . are associated with
industrial activity.” Id.
Congress also included a second phase of
stormwater regulation and gave EPA the discretion to
increase the scope of stormwater discharges that are
regulated under the CWA. 33 U.S.C. § 1342(p)(5)–(6).
EPA was first required to study potential stormwater
sources in consultation with the states.
Id.
26a
§ 1342(p)(5). Congress then authorized EPA (in
consultation with the states) to use the results of that
study to issue regulations governing any additional
stormwater sources that should be regulated under
the CWA. Id. EPA completed that process in 1999,
issuing the “Phase II” rule, “mandating that
discharges from small municipal separate storm
sewer systems and from construction sites between
one and five acres in size be subject to the permitting
requirements of the [NPDES]” and “preserv[ing]
authority to regulate other harmful stormwater
discharges in the future.” Envtl. Def. Ctr., Inc. v. U.S.
EPA, 344 F.3d 832, 840 (9th Cir. 2003).
EPA’s Phase II regulations explain that EPA may
add, on a case-by-case basis, other stormwater
discharges (or categories of discharges) in specific
“geographic areas” based on a determination that the
discharge “contributes to a violation of a water quality
standard or is a significant contributor of pollutants
to waters of the United States.”
40 C.F.R.
§ 122.26(a)(9)(i)(D). In its description of the program,
EPA explains that state regulation (with EPA
approval) of this “reserved category” of discharges
would be considered to be within the “scope” of the
federally approved program. 64 Fed. Reg. 68,722,
68,781 (Dec. 8, 1999). Under this statutory scheme,
Amici assert that, “[a]s of this date, EPA has not
extended the CWA to include other stormwater
discharges on docks and wharfs.” Dkt. 182-4 at 11.
B. Delegation to Washington
In 1974, EPA authorized Ecology to administer the
NPDES program in Washington. See 39 Fed. Reg.
26,061 (July 16, 1974); RCW 90.48.260. Under state
law, Ecology also administers the State Water
Pollution Control Act (RCW Chapter 90.48) which
27a
makes it illegal for “any person” to discharge
pollutants into waters of the state without a permit.
RCW 90.48.080, 90.48.160.
For industrial
stormwater, Ecology decided to enforce both state and
federal requirements using a general permit that
covers a broad range of activities. See WAC 173-226010 (regulations establishing “state general permit
program” and explaining that “[p]ermits issued under
this chapter are designed to satisfy the requirements
for discharge permits under [the CWA] . . . and the
state law governing water pollution control (chapter
90.48 RCW).”).
Ecology’s Industrial Stormwater General Permit
(“ISGP”) reflects this dual state and federal function.
As the ISGP states, it is both a “National Pollution
Discharge Elimination System (NPDES) and State
Waste Discharge General Permit” that was issued
“[i]n compliance with the provisions of The State of
Washington Water Pollution Control Law, Chapter
90.48 Revised Code of Washington and The Federal
Water Pollution Control Act (The Clean Water Act)
Title 33 United States Code, Section 1251 et seq.”
Dkt. 51-1 at 2.
When Ecology issued the ISGP in 2009, it listed
facilities that conducted industrial activities in a
table. Dkt. 270-1 at 7. The last category of activities
requiring permit coverage were “[t]ransportation
facilities which have vehicle maintenance shops,
material handling facilities, equipment cleaning
operations, or airport deicing operations . . . .” Id. at
8. Relevant to the instant dispute, this description
does not include the limiting language of 40 C.F.R.
§ 122.26(b)(14)(viii) that “[o]nly those portions of the
facility that are either involved in vehicle
maintenance (including vehicle rehabilitation,
28a
mechanical
repairs,
painting,
fueling,
and
lubrication), equipment cleaning operations, [or]
airport deicing operations . . . are associated with
industrial activity.” Id. Based on this exclusion of
language, Ecology contends that “once coverage is
triggered at a transportation facility, the ISGP
applies to all areas of industrial activity at the
facility, rather than only those areas where vehicle
maintenance, equipment cleaning, or airport deicing
occur.” Dkt. 269 at 3. The permit defines “facility”
and “industrial activity” as follows:
Facility means any NPDES “point source”
(including land or appurtenances thereto) that
is subject to regulation under the NPDES
program. See 40 CFR 122.2.
Industrial Activity means (1) the 11
categories of industrial activities identified in
40 CFR 122.26(b)(14)(i-xi) that must apply for
either coverage under this permit or no
exposure certification, (2) any facility
conducting any activities described in Table 1,
and (3) identified by Ecology as a significant
contributor of pollutants. Table 1 lists the 11
categories of industrial activities identified in
40 CFR 122.26(b)(14)(i-xi) in a different format.
Dkt. 270-1 at 54.
Ecology issued a companion fact sheet to
summarize changes in the proposed 2010 permit.
Relevant to the instant matter, Ecology stated that
“[s]tormwater may become contaminated by
industrial activities as a result of . . . contact with
materials during loading, unloading or transfer from
one location to another . . . .” Dkt. 270-2 at 10. Under
a section specific to water transportation facilities,
29a
Ecology identified potential sources of additional
pollutants as “loading/unloading areas” and potential
pollutants included “fuels and machinery lubricants,
solvents, paints, heavy metals, and paint stripping
wastes.” Id. at 38.
Furthermore, Ecology issued an ISGP frequently
asked questions (“FAQ”) document. Dkt. 185-1.
Ecology stated that the “document is intended as
guidance only, and does not modify or otherwise
change the permit requirements” and “[i]f there is any
discrepancy between this guidance and the [ISGP],
the permit requirements supersede this guidance.”
Id. at 2. Relevant to the instant dispute, the
document provides a question and answer as follows:
My transportation facility has vehicle
maintenance activity and therefore requires
permit coverage. Does the permit apply to the
entire footprint of the facility, or just to the area
where we conduct vehicle maintenance
activity?
The entire footprint of the industrial facility.
Once a transportation facility has permit
coverage, the permit conditions for sampling,
inspection and stormwater management
practices are required in all areas of industrial
activity, rather than only those areas where
vehicle maintenance, equipment cleaning and
airport de-icing occur.
Id.
On October 21, 2009, Ecology issued a response to
public comments. In the summary section, Ecology
stated that “[t]he most significant changes are
summarized below. The legal and technical basis for
changes related to each public comment is included,
30a
as appropriate.” Dkt. 280-13 at 7. Regarding
Ecology’s decision to exclude language from the table
of facilities that conduct industrial activities, Ecology
provided as follows:
Several commentors requested clarification
on the permit requirements for facilities in the
transportation sector (SIC codes 40XX, 41XX,
42XX, 43XX, 44XX, 45XX, and 5171). Ecology
reviewed the applicable federal regulations,
EPA Multi-Sector General Permit, discussed
the issue with EPA (Region 10 and
Headquarters). Changes have been made to
Table 1 to improve clarity. One of these
changes is to include “material handling
facilities” in the criteria for permit coverage at
transportation facilities [40 CFR 122.26(b)(14)].
Once a transportation facility obtains permit
coverage, the specific areas and stormwater
discharges authorized by the permit become
site specific.
Ecology disagrees with one
commentor’s suggestion that maintenance
activity conducted away from the maintenance
shop is not covered under the permit. The
intent of the ISWGP is to cover all vehicle
maintenance activities at industrial facilities,
not just those performed at the physical
location of the shop. Since this section of the
permit is to specify which type of facilities
require permit coverage, Ecology has decided to
take the approach in EPA’s MSGP and not
include the “only those portions of the facility
that are involved in vehicle maintenance . . .”
statement requested by several commentors.
Ecology also added definitions of “vehicle
31a
maintenance” and “material handling” based
on EPA’s Final Phase I Stormwater Rule.
Id.1
In June of 2010, Ecology permit managers verbally
told two port managers that the presence of a vehicle
maintenance shop anywhere on port property would
trigger ISGP coverage on all port property. Dkt. 1822 at 5. On July 27, 2010, WPPA sent Ecology a letter
stating its concerns regarding the “implementation
and enforcement” of the new ISGPs. Id. The ports
objected to this expansive reading because the
“implications are extreme.” Id. It argued that
expansion would require “implementing best
management practices, including stormwater
treatment, on hundreds or thousands of acres of
property (versus a few areas where maintenance
typically occurs)” and “has major ramifications on a
port’s ability to comply.” Id.
On March 10, 2011, Ecology responded. Id. at 9–
10. Ecology stated that “[o]nce a facility has [ISGP]
permit coverage, the Permit’s sampling, inspection,
and stormwater management practices are required
in all areas of industrial activity - rather than only
those areas where vehicle maintenance, equipment
cleaning, and airport deicing occur.” Id. at 9. Ecology
instructed the ports that they needed to take the
1
The inclusion of “material handling” facilities was
challenged and subsequently removed from the ISGP. Copper
Dev. Assoc., Inc. v. State of Washington, PCHB Nos. 09-135
through 09-141, Order on Summ. J., 2011 WL 62915, *4 (Wash.
Pol. Ctrl. Bd. Jan. 5, 2011) (“The [subsequent] change eliminated
permit coverage requirements for transportation facilities that
have material handling facilities, in order to make the permit
term consistent with the applicable definition in federal
regulations. 40 C.F.R. § 122.26(b)(14)(viii).”).
32a
necessary steps to “implement the Permit
requirements on all areas of industrial activity as
soon as possible” and that Ecology would use its
“enforcement discretion” with respect to the areas
outside vehicle maintenance areas to allow the ports
time to comply. Id. This enforcement discretion
would last until June 1, 2011. Id. Relevant to the
instant dispute, Ecology did not elaborate on the term
“industrial activity” for areas other than vehicle
maintenance, equipment cleaning, and airport
deicing.
On November 6, 2014, Ecology’s Water Quality
Specialist Jeff Killelea (“Killelea”) sent an email to
another Ecology employee discussing the relevant
amendment. Killelea’s explanation was as follows:
• Prior to 2010, the ISGP mirrored the 40 CFR
language regarding transportation facilities,
which stated:
o Only those portions of the facility that are
either involved in vehicle maintenance
(including vehicle rehabilitation, mechanical
repairs, painting, fueling and lubrication),
equipment cleaning operations, airport deicing
operations or which are otherwise identified
under one of the other 11 categories of
industrial activities listed in this appendix are
associated with industrial activity.
o This had the practical effect of excluding
most
material
handling,
storage,
loading/unloading areas from the ISGP’s
sampling and BMP requirements; even though
stormwater from these areas is highly
contaminated with zinc, copper, sediment,
petroleum, etc.
33a
To address this loophole, the “only hose
portions . . .” language was struck from the draft
2010 ISGP. We received public comments from
Ports and consultants requesting that the
language be reinstated.
• WQ PMT and regional stormwater staff
carefully considered the public comments, policy
issues, etc., and decided to issue the final 2010
ISGP without the exclusion language (based on
state authority).
This effectively required
permit coverage at the entire industrial facility
(entire port/rail yard/tank farm, etc.), not just the
maintenance areas.
• WQP management met with the Ports to
discuss this issue in 2010, and provided a follow
up letter that extended “enforcement discretion”
until the end of the year - to allow Ports and their
tenants to update Stormwater Plans, adjust
sampling locations, etc.
Dkt. 280-20 at 3–4 (emphasis added).
On December 3, 2014, Ecology issued a document
summarizing and responding to some public
comments on the proposed 2015 ISGP. Dkt. 185-2.
Relevant to the instant matter, the document
provides as follows:
Summary of the Range of Comments:
• EPA’s definition of industrial activities
associated with “transportation facilities” limits
NPDES coverage to specific portions of a
transportation facility:
o (viii} Transportation facilities classified
as Standard Industrial Classifications 40, 41,
42 except 4221-25}, 43, 44, 45, and 5171 which
have vehicle maintenance shops, equipment
34a
cleaning operations, or airport deicing
operations. Only those portions of the facility
that are either involved in vehicle maintenance
(including vehicle rehabilitation, mechanical
repairs, painting, fueling, and lubrication},
equipment cleaning operations, airport deicing
operations, or which are otherwise identified
under paragraphs (b)(14) (i)-(vii) or (ix)-(xi) of
this section are associated with industrial
activity.
• The Draft 2015 ISGP and Draft 2015 Fact
Sheet continue the omission of the limiting
language in the Table 1 summary of the 11
categories of industrial activities identified in 40
CFR 122.26(b)(14)(i-xi).
• While this omission may seem innocuous
given the ISGP’s directive that Table 1 is merely
40 CFR 122.26(b)(14)(i-xi) in a different format,
the years since the promulgation of the 2010 ISGP
have shown that the omission has led to profound
confusion and significant consequences that were
never identified, analyzed, or subjected to notice
and other required procedures in the context of the
2010 ISGP.
Response to the Range of Comments:
Ecology has considered the comment and
has decided to retain the omission of the
following
statement
from
40
CFR
122.26(b)(14)(viii): “Only those portions of the
facility that are either involved in vehicle
maintenance (including vehicle rehabilitation,
mechanical repairs, painting, fueling, and
lubrication), equipment cleaning operations,
airport deicing operations, or which are
35a
otherwise identified under paragraphs (b)(14)
(i)-(vii) or (ix)-(xi) of this section are associated
with industrial activity.” No change was made
to the final ISGP in response to this comment.
Id. at 78.
C. The Facility
The Port owns the 137-acre Terminal at issue in
this matter. While the majority of the Terminal is not
at issue in this matter, the parties dispute a 12.6-acre
section commonly referred to as the Wharf. Here, five
enormous ship-to-shore cranes load and unload large
shipping containers from docked vessels. See Dkt.
176 at 2–3.
In March 1983, the Port leased the Terminal to
APMT. As part of its operation of the Terminal,
APMT applied for and received an ISGP. Dkt. 51-1.
On October 2, 2017, Ecology terminated APMT’s
coverage under the ISGP and granted the Port
coverage under the permit. Dkt. 82-3. Ecology
informed the Port that it had 30 days to appeal the
general permit’s applicability as to the Port. Id. at 823 at 3. Also, on that date, SSA began its lease with
the Port for the Terminal.
On October 23, 2017, the Port signed Ecology
Agreed Order #15434 (the “Agreed Order”). Dkt.
82-4. The Agreed Order required the Port, subject to
Ecology review, to design, construct, and have
operational a stormwater treatment system. Id. at
§ IV. The Port has prepared, and Ecology approved,
an Engineering Report for a stormwater treatment
system for the Terminal. Dkt. 82-6.
The Port’s Stormwater Pollution Prevention Plan
(“SWPPP”) includes a sampling plan and
documentation regarding areas where the Port does
36a
not collect stormwater samples. Relevant to the
instant matter, the October 2017 SWPPP provides as
follows:
The type of activities that occur along the
wharf are substantially identical to the
activities that occur in the upland drainage
areas associated with [basin] WS1 and [basin]
WS2. In addition, collecting samples from the
wharf discharge points that are representative
of industrial activities in the area would require
access underneath the deck or along the edge of
the wharf, which is considered unsafe due to
tides and/or ship activity and container
offloading activity. As such, discharges from
the deck drains, scuppers, and power trench
and utility vault drains along the wharf are not
sampled since they are substantially identical
to the discharges from their respective upland
drainage areas contributing to WS1 and WS2;
and because the ISGP does not require
sampling in unsafe conditions.
The industrial activities, site conditions,
potential pollutant sources, expected pollutant
concentrations,
and
implemented
best
management practices (BMPs) associated with
the WS1 and WS2 drainage areas are
substantially identical. As such, discharges
from WS2 will not be sampled since they are
substantially identical to WS1 discharges.
Dkt. 87-30 at 4. The Port’s June 2018 SWPPP
provides in relevant part as follows:
Discharges from the deck drains are considered
to be substantially identical to those monitored
from the upland areas of WS2 and are therefore
37a
exempt from monitoring in accordance with
S4.B.2.c requirements.
The deck drain
discharge points are considered to discharge
substantially identical effluent to the WS2
discharge location as activities along the wharf
are similar or less intensive than those
conducted in the upland. Activities in the
upland portion of the basin include hostler
truck traffic, container handling, and mobile
vehicle and equipment maintenance. Activities
in the wharf area of the basin west of the power
trench include hostler truck traffic, container
handling, and crane maintenance. Material
storage and mobile fueling are generally not
performed in the area. As discussed previously,
the hostler trucks that access the wharf area
are exclusively used at the terminal and do not
travel outside Basin B, which should reduce
[total suspended solids] and turbidity in
stormwater discharges relative to the other
Terminal basins subject to over the road traffic
and potentially track-on from offsite.
Dkt. 186-1 at 7. The Port’s October 2018 SWPPP
states that “[n]o activities described in 40 CFR
§ 122.26(b)(14)(viii) are conducted on the wharf and
the wharf does not discharge stormwater associated
with industrial activity, as defined in 40 CFR
§ 122.26(b)(14)(i)-(xi).” Dkt. 178-5 at 9.
38a
III. DISCUSSION
A. Nondispositive Motions
The Port filed a motion to seal and a motion in
limine. First, “[a]ny motion in limine must include a
certification that the movant has in good faith
conferred or attempted to confer with other affected
parties in an effort to resolve which matters really are
in dispute. A good faith effort to confer requires a
face-to-face meeting or a telephone conference.” Local
Rules W.D. Wash. LCR 7(d)(4).
Regarding the motion in limine, Soundkeeper
argues that the Court should deny the Port’s motion
in limine because it failed to file a certificate that it
conferred in good faith to resolve the issue without
Court intervention. Dkt. 296. The Court agrees and
therefore denies the Port’s motion. Soundkeeper also
argues that the Court should preclude the Port from
filing any additional motions in limine because all
motions in limine must be filed in one brief. Id. at 7
(citing Local Rules W.D. Wash. LCR 7(d)(4)). The
Court declines to order such relief, but it informs the
Port that filing another motion without conferring
may result in sanctions.
Regarding the motion to seal, the Port moves to
seal certain exhibits because they may contain
privileged information. Dkt. 281. No party responded
to the Port’s motion. The Court agrees with the Port
to the extent that the documents should be
provisionally sealed pending further rulings on
whether the documents are privileged or relevant.
Therefore, the Court grants the Port’s motion and
provisionally seals the requested documents.
39a
B. Summary Judgment
The Port moves for partial summary judgment
arguing that stormwater discharges from the Wharf
“are not ‘discharges associated with industrial
activities’ pursuant to EPA’s regulations (40 C.F.R.
§ 122.26(b)(14)(viii)) and are therefore not subject to
the federal NPDES program or citizen suit
enforcement of the NPDES program.” Dkt. 176 at 1.
1. Standard
Summary judgment is proper only if the pleadings,
the discovery and disclosure materials on file, and any
affidavits show that there is no genuine issue as to
any material fact and that the movant is entitled to
judgment as a matter of law. Fed. R. Civ. P. 56(a).
The moving party is entitled to judgment as a matter
of law when the nonmoving party fails to make a
sufficient showing on an essential element of a claim
in the case on which the nonmoving party has the
burden of proof. Celotex Corp. v. Catrett, 477 U.S. 317,
323 (1986). There is no genuine issue of fact for trial
where the record, taken as a whole, could not lead a
rational trier of fact to find for the nonmoving party.
Matsushita Elec. Indus. Co. v. Zenith Radio Corp.,
475 U.S. 574, 586 (1986) (nonmoving party must
present specific, significant probative evidence, not
simply “some metaphysical doubt”). Conversely, a
genuine dispute over a material fact exists if there is
sufficient evidence supporting the claimed factual
dispute, requiring a judge or jury to resolve the
differing versions of the truth. Anderson v. Liberty
Lobby, Inc., 477 U.S. 242, 253 (1986); T.W. Elec. Serv.,
Inc. v. Pac. Elec. Contractors Ass’n, 809 F.2d 626, 630
(9th Cir. 1987).
40a
The determination of the existence of a material
fact is often a close question. The Court must consider
the substantive evidentiary burden that the
nonmoving party must meet at trial—e.g., a
preponderance of the evidence in most civil cases.
Anderson, 477 U.S. at 254; T.W. Elec. Serv., Inc., 809
F.2d at 630. The Court must resolve any factual
issues of controversy in favor of the nonmoving party
only when the facts specifically attested by that party
contradict facts specifically attested by the moving
party. The nonmoving party may not merely state
that it will discredit the moving party’s evidence at
trial, in the hopes that evidence can be developed at
trial to support the claim. T.W. Elec. Serv., Inc., 809
F.2d at 630 (relying on Anderson, 477 U.S. at 255).
Conclusory, nonspecific statements in affidavits are
not sufficient, and missing facts will not be presumed.
Lujan v. Nat’l Wildlife Fed’n, 497 U.S. 871, 888–89
(1990).
2. Permit’s Scope
“NPDES permits are treated like any other
contract.” Nat. Res. Def. Council, Inc. v. Cty. of L.A.,
725 F.3d 1194, 1204 (9th Cir. 2013). “If the language
of the permit, considered in light of the structure of
the permit as a whole, ‘is plain and capable of legal
construction, the language alone must determine the
permit’s meaning.’ . . . . If the permit’s language is
ambiguous, we may turn to extrinsic evidence to
interpret its terms.” Id. (quoting Piney Run Pres.
Ass’n v. Cty. Comm’rs of Carroll Cty., Md., 268 F.3d
255, 270 (4th Cir. 2001)).
In this case, the first question is the scope of the
ISGP regarding industrial activities at the Port’s
wharf. The Port moved for summary judgment
arguing that stormwater discharges from the wharf
41a
“are not ‘discharges associated with industrial
activities’ pursuant to 40 C.F.R. § 122.26(b)(14)(viii)
and are therefore not subject to the federal NPDES
program or citizen suit enforcement of the NPDES
program.” Dkt. 176 at 18. The Port recognized that
Ecology may issue regulations beyond the scope of the
federal NPDES program, but there is no private right
of action for violations of such additional regulations.
Id. at 17. SSA also argues that wharf discharges are
beyond the scope of the federal program and that
“even if Ecology had included stormwater sampling in
wharf areas as part of the scope of the ISGP—which
it has not—PSA could not bring a citizen suit
enforcing such a regulation.” Dkt. 184 at 3.
Soundkeeper responds that it may enforce all
conditions of an NPDES permit in an enforcement
proceeding and that the Port and SSA’s arguments
are an untimely and improper collateral attack on the
scope of the permit. Dkt. 185. Soundkeeper relies
primarily on Ecology’s FAQ document and December
2014 summary of comments to support its position
that the ISGP applies to all areas of the Port,
including the wharf. Id. at 8–9.
The Port replies that “it is irrelevant how Ecology
might interpret the ISGP or exercise independent
state authority” to expand the scope of the ISGP. Dkt.
189 at 8. The Port first relies on an EPA final rule
that provides in relevant part that “[i]f a State, Tribe,
or local government were to require a permit for
discharges exempt from the Clean Water Act NPDES
program requirements, those permit requirements
would not be considered part of an NPDES program.
See 40 CFR 123.1(i)(2).” 71 Fed. Reg. 33628-01,
*33635. Regarding the FAQ document, the Port
asserts that the document specifically states that it
42a
does not modify the ISGP and that Ecology’s answer
only states that permit requirements only apply to
areas where “industrial activity” occurs without
further defining that term. Dkt. 189 at 8.
Based on the parties’ dispute regarding the
interpretation of the ISGP, the Court invited Ecology
to file an amicus brief. Dkt. 252. Ecology asserts that
it “exercised its residual Clean Water Act authority
under 33 U.S.C. § 1342(p)(2)(E) when it elected to
extend the scope of ISGP coverage at transportation
facilities that are required to obtain an NPDES
permit under the Clean Water Act.” Dkt. 269 at 2.
Ecology’s claimed extension is that the ISGP applies
to “all areas of industrial activity” at the Port. Id. at
2–4.
The Port responds that Ecology’s position is not
supported by any evidence. Specifically, the Port
argues “Ecology’s amicus brief is unsupported by even
one document or declarant identifying when Ecology
supposedly made a policy decision to exercise such
authority, when it notified the public of this ‘decision’
or any analysis prepared to support such
designation.” Dkt. 279 at 1. For example, the Port
submits Ecology’s economic impact analysis (“EIA”)
for the proposed 2010 ISGP, and Ecology’s alleged
expansion is not described in the “Changes to the
Permit” section. Dkt. 280-5 at 9. Similarly, the Port
submitted Killelea’s 2014 email wherein he stated
that the scope of the permit was expanded “based on
state authority.” Dkt. 280-20 at 3.
SSA contends that Ecology’s position and
Killelea’s supporting declaration “are, at best,
revisionist history.” Dkt. 276 at 2. SSA relies on the
ISGP’s definition of industrial activities that cites and
incorporates the language of 40 CFR 122.26(b)(14)(i-
43a
xi) to conclude that the clear language of the ISGP
contradicts Ecology’s position. Id. at 2–4.
Soundkeeper responds, without much analysis,
and simply provides the conclusion that “the plain
language of the [ISGP] is not ambiguous.” Dkt. 275
at 4.
Ecology replied and clarified that it expanded the
scope of the permit under its residual state authority.
Dkt. 290. Ecology also argued that it properly
delegated this authority to Ecology employees and
that it need not consider certain factors in expanding
the scope of the ISGP with regard to transportation
facilities. Id. at 4–6. Ecology did not address SSA’s
argument regarding the incorporation of the federal
regulatory language in the specific definition of
industrial activity. Soundkeeper likewise ignores this
argument in its reply. Dkt. 293 at 3.
Turning to the law of contract interpretation, “[a]
written contract must be read as a whole and every
part interpreted with reference to the whole, with
preference given to reasonable interpretations.”
Klamath Water Users Protective Ass’n v. Patterson,
204 F.3d 1206, 1210 (9th Cir. 1999), opinion amended
on denial of reh’g, 203 F.3d 1175 (9th Cir. 2000).
“Whenever possible, the plain language of the
contract should be considered first.” Id.
In this case, the plain language of the ISGP
supports the Port and SSA’s positions. Although the
table listing industrial facilities does not include the
federal language, the specific definition of industrial
activities cites and incorporates this language. That
definition “means (1) the 11 categories of industrial
activities identified in 40 CFR 122.26(b)(14)(i-xi) that
must apply for either coverage under this permit” and
44a
“Table 1 lists the 11 categories of industrial activities
identified in 40 CFR 122.26(b)(14)(i-xi) in a different
format.” Dkt. 270-1 at 54. This is clear, unambiguous
language establishing that the ISGP relies on the
federal regulations and its “only those portions”
exclusionary definition as applied to transportation
facilities. Neither Soundkeeper nor Ecology provides
a persuasive argument undermining the ISGP’s
direct reference and incorporation of the federal
language. Therefore, the Court concludes that the
Port’s ISGP defines industrial activity as “[o]nly those
portions of the facility that are either involved in
vehicle maintenance (including vehicle rehabilitation,
mechanical
repairs,
painting,
fueling,
and
lubrication), equipment cleaning operations, airport
deicing operations, or which are otherwise identified
under paragraphs (b)(14) (i)–(vii) or (ix)–(xi) of this
section are associated with industrial activity.”
Although Ecology contends that it intended to
expand the scope of the ISGP, “courts must interpret
contracts, if possible, so as to avoid internal conflict.”
Trident Ctr. v. Conn. Gen. Life Ins. Co., 847 F.2d 564,
566 (9th Cir. 1988). Interpreting the ISGP as Ecology
contends would result in an internal conflict between
the table of industrial activities, Table 1, and the
statement “Table 1 lists the 11 categories of industrial
activities identified in 40 CFR 122.26(b)(14)(i-xi) in a
different format.” Dkt. 270-1 at 54. Ecology, as
drafter of the ISGP and aware of the confusing
conflict from public comments, Dkt. 185-2 at 78, fails
to harmonize its intent with its permit. Thus, the
Court must reject Ecology’s position regarding an
45a
expansive permit and grant the Port’s motion on the
clear language of the ISGP.2
3. Alternative Activities
Soundkeeper argues that even if the Court accepts
the Port’s position on the initial issue, the Port
engages in other industrial activities on the wharf
that
compel
compliance
with
stormwater
management. Dkt. 185 at 18–24. Soundkeeper relies
on section (b)(14)’s preamble that sets forth a nonexhaustive list of industrial activities such as
material handling and rail lines for carrying cargo.
Id. at 19–20. The problem, however, is that this list
of activities may not overcome the exclusionary
language in part (viii) that limits industrial activities
to “only those portions” of transportation facilities.
Ecology recognized this “loophole” and unsuccessfully
attempted to expand the scope of the ISGP by listing
“material handling activities.” The Court likewise
recognizes the controlling and specific limiting
language is set forth in part (viii) and rejects
Soundkeeper’s
argument
that
transportation
facilities are subject to regulation for the nonexhaustive list of activities set forth in the preamble.
Based on this conclusion, the Court also rejects
Ecology’s argument that loading and unloading of
containers at the wharf constitute industrial
activities subject to regulation. Dkt. 269 at 4–5.
Soundkeeper cites Puget Soundkeeper All. v.
Rainier Petroleum Corp., C14-0829JLR, 2015 WL
13655379 (W.D. Wash. Dec. 16, 2015) for the
proposition that this Court held that industrial
2 The Court denies the motion to supplement the record
because the additional evidence is irrelevant to the plain
language of the ISGP.
46a
activities other than vehicle maintenance and/or
equipment cleaning at a marine transportation
facility required stormwater management. Dkt. 185
at 21–22. This case, however, is neither controlling
nor persuasive because the regulated entity was both
a marine transportation facility and a petroleum
storage facility, which significantly expanded the
industrial activities that it had to monitor and
manage.
4. Regulated Activities
The Port moves for summary judgment on any of
Soundkeeper’s claims arising from stormwater
discharges at the wharf. Dkt. 176 at 18. Soundkeeper
responds in part that vehicle maintenance and/or
equipment cleaning occur on the wharf because the
large mechanical cranes are maintained and cleaned
in place on the wharf. Dkt. 185 at 24–25. To support
this argument, Soundkeeper has submitted a report
by Dr. Richard Horner citing grease and gear oil spills
observed during a site visit. Dkt. 187. The Port
counters that Soundkeeper’s reference to the cranes
as “equipment” is dispositive because the ISGP only
regulates “vehicle” maintenance and equipment
cleaning. Dkt. 189 at 2–3. The Court agrees with the
Port because equipment maintenance is not an
industrial activity under 40 C.F.R. 122.26(b)(14)(viii)
or the corresponding ISGP. Therefore, the Court
grants the Port’s motion on Soundkeeper’s claims
regarding discharges from the Port’s wharf.
IV. ORDER
Therefore, it is hereby ORDERED that Port’s
motion for partial summary judgment, Dkt. 176, and
motion to seal, Dkt. 281, are GRANTED, the Port’s
motion in limine, Dkt. 283, is DENIED without
47a
prejudice, and the Port’s motion for leave to
supplement the record, Dkt. 299, is DENIED.
Dated this 3rd day of November, 2020.
s/Benjamin H. Settle
BENJAMIN H. SETTLE
United States District Judge
48a
[561 F. Supp. 3d 1113]
UNITED STATES DISTRICT COURT
WESTERN DISTRICT OF WASHINGTON
AT TACOMA
PUGET
SOUNDKEEPER
ALLIANCE,
Plaintiff,
v.
SSA TERMINALS,
LLC, et al.,
Defendants.
CASE NO. C17-5016
BHS
ORDER GRANTING
DEFENDANTS’
MOTION FOR
SUMMARY
JUDGMENT
This matter comes before the Court on
Defendants SSA Terminals (Tacoma), LLC
(“SSATT”) and SSA Terminals, LLC’s (“SSAT”)
(collectively “SSA”) motion for summary judgment.
Dkt. 317. The Court has considered the briefings
filed in support of and in opposition to the motion and
the remainder of the file and hereby grants the
motion for the reasons stated herein.
I. FACTUAL & PROCEDURAL BACKGROUND
A. Overview
As the parties are familiar with the extensive
history of this case, the Court provides the following
overview. This case is a citizen suit brought under
Section 505 of the Clean Water Act as amended, 33
U.S.C. § 1365. Plaintiff Puget Soundkeeper Alliance
(“Soundkeeper”) seeks, inter alia, a declaratory
judgment and injunctive relief for alleged violations
49a
of the CWA and the National Pollutant Discharge
Elimination System (“NPDES”) permit authorizing
discharges of pollutants from Defendants the Port of
Tacoma and SSA’s facility to navigable waters. Dkt.
254, Fourth Amended Complaint (“FAC”), ¶ 1.
At issue in this case are industrial stormwater
discharges at a large marine cargo terminal
(“Terminal”) used for ship unloading and cargo
distribution. The Port owns the 137-acre Terminal at
issue in this matter. While the majority of the
Terminal is not at issue, the parties dispute a 12.6acre section commonly referred to as the “Wharf.”
Here, five enormous ship-to-shore cranes load and
unload large shipping containers from docked vessels.
The Wharf is depicted below, as provided in the Port’s
motion for partial summary judgment:
50a
Dkt. 176 at 2.
51a
Soundkeeper alleges, in part, that SSA is in
violation of the NPDES permits that authorize
discharges of stormwater associated with industrial
activity and thus are in violation of Section 505 of the
CWA. FAC, ¶ 65.
B. Procedural History
On January 9, 2017, Soundkeeper filed a
complaint against Defendant APM Terminals
Tacoma, LLC (“APMT”) alleging ongoing violations of
APMT’s NPDES permit. Dkt. 1, ¶ 1. APMT was the
lessee of the Terminal at the time of the initial
complaint, and on November 28, 2017, Soundkeeper
filed a second amended complaint adding the Port of
Tacoma as a defendant, stating that the Port owns the
facility and that APMT leases the facility. Dkt. 75.
On June 13, 2018, Soundkeeper filed a third
amended complaint adding the Port’s new tenants,
Defendants SSA Marine, Inc. and SSAT. Dkt. 109.
On June 4, 2019, the Court granted Soundkeeper’s
motion for leave to amend, Dkt. 253, and
Soundkeeper filed its Fourth Amended Complaint,
dropping APMT and SSA Marine, Inc. as parties and
adding SSATT. Dkt. 254. Soundkeeper has settled
all of its claims in this case against APMT via a
consent decree. Dkt. 224.
The Port moved for partial summary judgment as
to Soundkeeper’s claims arising from stormwater
discharges from the Wharf. Dkt. 176. Soundkeeper
then filed a motion for partial summary judgment,
arguing that (1) the Port is liable for APMT’s
violations, (2) the Port is liable for Level 3 corrective
action requirements that occurred in 2013 and 2015,
(3) the Port is liable for failing to monitor discharges
from the Wharf, (4) the Port’s stormwater pollution
52a
prevention plans (“SWPPP”) are inadequate,
(5) Soundkeeper has standing to bring its claims, and
(6) the Court has subject matter jurisdiction over the
alleged violations. Dkt. 196. The Port responded and
filed a cross-motion for summary judgment to dismiss
Soundkeeper’s claim against it in its entirety. Dkt.
210.
SSA joined in the Port’s opposition to
Soundkeeper’s motion. Dkt. 209.
The Court granted the Port’s motion for partial
summary judgment, Dkt. 304, and granted in part
and denied in part the cross-motions for summary
judgment, Dkt. 305.
1. Relevant Court Orders
The Port filed a motion for partial summary
judgment requesting that the Court dismiss
Soundkeeper’s “claims arising from stormwater
discharges to the Wharf.” Dkt. 176 at 18. After
extensive briefing from the parties and amici, the
Court granted the Port’s motion. Dkt. 304. The Port
persuasively argued that stormwater discharges from
the Wharf are not “discharges associated with
industrial activities” pursuant to the Environmental
Protection
Agency’s
regulations
(40
C.F.R.
§ 122.26(b)(14)(viii)) and are therefore not subject to
the federal NPDES program or citizen suit
enforcement of the NPDES program.
EPA has empowered the Washington State
Department of Ecology to administer the NPDES
program in Washington. See 39 Fed. Reg. 26,061
(July 16, 1974); RCW 90.48.260. Under state law,
Ecology also administers the State Water Pollution
Control Act (RCW Chapter 90.48) which makes it
illegal for “any person” to discharge pollutants into
waters of the state without a permit. RCW 90.48.080,
53a
90.48.160.
For industrial stormwater, Ecology
decided to enforce both state and federal
requirements using a general permit that covers a
broad range of activities. See WAC 173-226-010
(regulation establishing “state general permit
program” and explaining that “[p]ermits issued under
this chapter are designed to satisfy the requirements
for discharge permits under [the CWA] . . . and the
state law governing water pollution control (chapter
90.48 RCW)”).
Ecology’s Industrial Stormwater General Permit
(“ISGP”) reflects this dual state and federal function.
As the ISGP states, it is both a “National Pollution
Discharge Elimination System (NPDES) and State
Waste Discharge General Permit” that was issued
“[i]n compliance with the provisions of The State of
Washington Water Pollution Control Law Chapter
90.48 Revised Code of Washington and The Federal
Water Pollution Control Act (The Clean Water Act)
Title 33 United States Code, Section 1251 et seq.”
Dkt. 51-1 at 2.
The Court thus had to determine the scope of the
ISGP issued to the Port regarding industrial activities
at the Wharf. The Court concluded that the ISGP
clearly and unambiguously relied on the federal
regulations, which includes the exclusionary
language in part (viii) that limits industrial activities
to “only those portions” of transportation facilities.
See Dkt. 304 at 20–22.
The Court rejected
Soundkeeper’s
argument
that
transportation
facilities are subject to regulation based upon the
federal regulation’s non-exhaustive preamble and
rejected Ecology’s argument that loading and
unloading of containers at the Wharf constitute
industrial activities subject to regulation.
54a
In sum, the Court agreed with the Port that
“equipment maintenance is not an industrial
activity under 40 C.F.R. 122.26(b)(14)(viii) or the
corresponding ISGP” and granted the Port’s motion
for partial summary judgment regarding claims
involving discharges from the Wharf. Id. at 23.
The Court also agreed with the Port’s cross-motion
for summary judgment, granting the Port’s motion
and dismissing Soundkeeper’s entire claim against
the Port. Dkt 305. While the Court
This text is long and has been trimmed here. Open the source document for the complete record.
This is a copy of a public record, reproduced as it was published. It is not legal advice, and it may not be the version a court would rely on. Check the official source before you cite it.