Petition for Writ of Certiorari — RDFS, LLC, Petitioner v. Federal Energy Regulatory Commission, et al.
Supreme Court briefJun 6, 2025
Ask Donna
What actually matters in this document.
Text
No.
IN THE
Supreme Court of the United States
RDFS, LLC,
Petitioners,
V.
FEDERAL ENERGY REGULATORY COMMISSION, AND
COLUMBIA GAS TRANSMISSION, LLC
Respondents.
On Petition for Writ of Certiorari to the
U.S. Court of Appeals for the Fourth Circuit
PETITION FOR WRIT OF CERTIORARI
Joy D. Llaguno
Counsel of Record
Phillip C. Hook
Matthew R. Miller
Gerald S. Atkins
HOOK & HOOK PLLC
430 East Oakview Dr.
Suite 101
Waynesburg, PA 15370
(724) 824-3302
jllaguno@hooklaw.com
Counsel for Petitioner
i
QUESTIONS PRESENTED
The Natural Gas Act (“NGA”), 15 U.S.C. § 717 et
seq., empowers the Federal Energy Regulatory
Commission (“FERC”) to issue certificates of public
convenience and necessity, which authorize certain
natural gas pipeline operations and grant the power
of eminent domain. FERC, in turn, promulgated
18 C.F.R. § 157.201 et seq., creating the “Blanket
Certificate” mechanism, which grants holders
“automatic authorization” to exercise eminent domain
for certain categories of activities “without further
Commission approval.” Id. §§ 157.203, 157.208. Here,
a private entity used its blanket certificate to
condemn property over forty years after its issuance
against a landowner who had no notice of or
opportunity to oppose the certificate. The Fourth
Circuit held without discussion that it lacked
jurisdiction, deferring to FERC on the question of
FERC’s power to promulgate the regulations which
deprive the judiciary of jurisdiction. The questions
presented are:
1. Whether a court of appeals may defer to FERC
on the threshold question of FERC’s authority to issue
blanket certificates without determining the legality
of the agency’s asserted power?
2. Whether the NGA, 15 U.S.C. § 717 et seq., and
the Constitution permit FERC to issue blanket
certificates under 18 C.F.R. § 157.201 et seq. which
never expire, are unlimited in geographic scope, and—
according to FERC—may not be challenged after the
statutory thirty-day rehearing deadline, irrespective
of future condemnations that may occur decades or
centuries after the date of the original grant?
ii
PARTIES TO THE PROCEEDING AND
CORPORATE DISCLOSURE STATEMENT
The parties to the proceedings in the court of
appeals are:
1. Petitioners (Petitioner below): RDFS, LLC.
2. Respondent (Respondent below):
Energy Regulatory Commission.
Federal
3. Respondent (Intervenor below): Columbia Gas
Transmission, LLC.
Petitioner RDFS, LLC, has no parent corporation.
No publicly held company owns any interest in RDFS,
LLC.
iii
LIST OF RELATED CASES
The related proceedings within the meaning of this
Court’s Rule 14.1(b)(iii) are listed below:
•
RDFS, LLC, v. Federal Energy Regulatory
Commission, et al., No. 24-1530 (4th Cir. Jan. 8,
2025) (judgment entered).
•
Columbia Gas Transmission Corp., 187 FERC
¶ 62,027 (April 11, 2024) (administrative decision
entered).
iv
TABLE OF CONTENTS
Page(s)
QUESTIONS PRESENTED ..............................
i
PARTIES TO THE PROCEEDING AND
CORPORATE DISCLOSURE
STATEMENT ..........................................
ii
LIST OF RELATED CASES ..............................
iii
TABLE OF CONTENTS ....................................
iv
TABLE OF APPENDICES ................................
vii
TABLE OF AUTHORITIES ...............................
viii
PETITION FOR A WRIT OF CERTIORARI ....
1
OPINIONS BELOW ...........................................
1
JURISDICTION .................................................
1
CONSTITUTIONAL, STATUTORY, AND
REGULATORY PROVISIONS
INVOLVED ..............................................
1
STATEMENT OF THE CASE ...........................
2
A.
The Legal Framework of the NGA ....
3
B.
Blanket Certificates ...........................
5
C.
Relevant Facts and Procedural
History ................................................
8
REASONS FOR GRANTING THE PETITION ..
11
I.
The Fourth Circuit Improperly Ceded
Judicial Authority to FERC ....................
11
v
A.
Deference to FERC on the Scope of
Its Own Power Contradicts This
Court’s Clear Precedent .....................
12
The Decision Below Improperly
Insulates Agency Action from
Constitutional Scrutiny .....................
15
FERC’S Blanket Certificate Mechanism
is an Expansion of Executive Power in
Defiance of the Text of the NGA, the
Fifth Amendment, and this Court’s
Precedents ................................................
16
A.
Blanket Certificates Violate Core
Principles of Due Process ...................
16
B.
Blanket Certificates Invoke the
Takings Power Without
Safeguarding the Public Use
Requirement .......................................
18
Blanket Certificates Allow Eminent
Domain to be Exercised in
Perpetuity, Shielded from Judicial
Scrutiny ..............................................
21
B.
II.
C.
vi
III.
The Decision Below Presents a Circuit
Split With Broad Implications for an
Expanding Nationwide Industry, Raises
Significant Constitutional Questions,
and the Issues Presented Are Likely to
Recur in the Absence of this Court’s
Review ......................................................
25
CONCLUSION ...................................................
31
vii
TABLE OF APPENDICES
Page(s)
APPENDIX A — ORDER OF THE UNITED
STATES COURT OF APPEALS FOR
THE FOURTH CIRCUIT, FILED
JANUARY 8, 2025 .............................................. 1a
APPENDIX B — DENIAL OF REHEARING OF
THE FEDERAL ENERGY REGULATORY
COMMISSION, FILED APRIL 11, 2024 ........... 2a
APPENDIX C — REJECTION OF REHEARING
AND DENIAL OF LATE INTERVENTION
OF THE FEDERAL ENERGY REGULATORY
COMMISSION, DATED FEBRUARY 7, 2024 ..... 3a
APPENDIX D — FINDINGS AND ORDER OF
THE FEDERAL ENERGY REGULATORY
COMMISSION, DATED JANUARY 7, 1983 ........ 6a
APPENDIX E — CONSTITUTIONAL AND
STATUTORY PROVISIONS INVOLVED ....... 12a
viii
TABLE OF AUTHORITIES
Page(s)
Cases
Abbott Lab’ys v. Gardner,
387 U.S. 136 (1967) ........................................... 22
Alexander v. Sandoval,
532 U.S. 275 (2001) ........................................... 12
Allegheny Def. Project v. FERC,
964 F.3d 1 (D.C. Cir. 2020) ....................13, 26, 29
Allentown Mack Sales & Serv., Inc. v.
N.L.R.B.,
522 U.S. 359 (1998) ........................................... 15
Armstrong v. Manzo,
380 U.S. 545 (1965), overruled on
other grounds by Daniels v.
Williams, 474 U.S. 327 (1986) .......................... 17
Baldwin v. United States,
140 S. Ct. 690 (2020) ......................................... 30
Bowen v. Mich. Acad. of Fam. Physicians,
476 U.S. 667 (1986) ........................................... 22
Brown v. Gardner,
513 U.S. 115 (1994) ........................................... 12
CTS Corp. v. Waldburger,
573 U.S. 1 (2014) ............................................... 24
Cedar Point Nursery v. Hassid,
594 U.S. 139 (2021) ........................................... 22
Chicago, B. & Q. Ry. Co. v. Illinois,
200 U.S. 561 (1906) ........................................... 20
ix
City of Cincinnati v. Vester,
281 U.S. 439 (1930) ........................................... 19
Columbia Gas Transmission, LLC v.
1.01 Acres, More or Less in Penn Twp.,
768 F.3d 300 (3d Cir. 2014) .......................... 7, 29
Columbia Gas Transmission, LLC v.
10.5068 Acres, More or Less in
York Cnty.,
No. 15-CV-0360, 2015 WL 3831181
(M.D. Pa. June 19, 2015) .................................. 29
Columbia Gas Transmission, LLC v.
RDFS, LLC, No. 23-CV-364 [ECF
No. 1] (N.D.W. Va. Dec. 19, 2023) ...................... 9
Columbia Gas Transmission, LLC v.
RDFS, LLC, No. 23-CV-364, 2024
WL 993093 (N.D.W. Va. Feb. 27, 2024)........6, 10, 24
Corner Post, Inc. v. Bd. of Governors of
Fed. Rsrv. Sys.,
144 S. Ct. 2440 (2024) ..................................24, 25
Covey v. Town of Somers,
351 U.S. 141 (1956) ........................................... 17
Dixon v. United States,
381 U.S. 68 (1965) ........................................12, 14
E. Tennessee Nat. Gas Co. v. Sage,
361 F.3d 808 (4th Cir. 2004) ............................. 29
Eychaner v. City of Chicago,
141 S. Ct. 2422 (2021) ....................................... 20
Fuentes v. Shevin,
407 U.S. 67 (1972) ............................................. 17
x
In re Columbia Gas Transmission Corp.,
No. CP83-76-0008 (Jan. 24, 2024) .................... 10
Kelo v. City of New London,
545 U.S. 469 (2005) ................................18, 19, 22
Koshland v. Helvering,
298 U.S. 441 (1936) ........................................... 12
Leary v. United States,
395 U.S. 6 (1969) ............................................... 12
Loper Bright Enters. v. Raimondo,
603 U.S. 392 (2024) ...................... 2, 11-15, 25, 30
Loretto v. Teleprompter Manhattan
CATV Corp.,
458 U.S. 419 (1982) ........................................... 23
Manhattan Gen. Equip. Co. v.
Comm’r of Internal Revenue,
297 U.S. 129 (1936) ........................................... 12
Marbury v. Madison,
5 U.S. 137 (1803) ............................................... 13
Mennonite Bd. of Missions v. Adams,
462 U.S. 791 (1983) ........................................... 17
Michigan v. E.P.A.,
576 U.S. 743 (2015) ........................................... 20
Miller v. Johnson,
515 U.S. 900 (1995) ........................................... 15
Mullane v. Cent. Hanover Bank & Tr. Co.,
339 U.S. 306 (1950) ........................................... 17
xi
Nat’l R.R. Passenger Corp. v. Bos. &
Maine Corp.,
503 U.S. 407 (1992) ........................................... 20
N. Nat. Gas Co. v. Easement &
Right-of-way Across 33.523 Acres
More or Less,
No. 23-CV-1906, 2023 WL 4936163
(D. Minn. Aug. 2, 2023)..................................... 29
Parratt v. Taylor,
451 U.S. 527 (1981) ........................................... 17
Pavelich v. Nat. Gas Pipeline Co. of Am.,
No. 02 C 3374, 2003 WL 22303140
(N.D. Ill. Oct. 8, 2003) ................................... 6, 21
PennEast Pipeline Co., LLC v. New Jersey,
594 U.S. 482 (2021) ........................................... 28
Peralta v. Heights Med. Ctr., Inc.,
485 U.S. 80 (1988) ............................................. 17
RDFS, LLC v. U.S. Fed. Energy Reg.
Comm’n,
No. 24-1530 [ECF No. 3]
(4th Cir. June 10, 2024) .................................... 10
RDFS, LLC v. Fed. Energy Regul.
Comm’n,
24-1530 [ECF No. 29]
(4th Cir. Jan. 8, 2025) .................. 7, 11, 13, 26, 29
Sabal Trail Transmission, LLC v. +/0.4 Acres of Land in Marion Cnty.,
No. 16-CV-210, 2016 WL 2997672
(M.D. Fla. May 25, 2016) .................................. 29
xii
Seven Cnty. Infrastructure Coal. v.
Eagle Cnty.,
--- S.Ct.--- No. 23-975, 2025 WL
1520964 (U.S. May 29, 2025)............................ 12
Thompson v. Consolidated Gas Corp.,
300 U.S. 55 (1937) ............................................. 18
United States v. Larionoff,
431 U.S. 864 (1977) ........................................... 12
Util. Air Regul. Grp. v. E.P.A.,
573 U.S. 302 (2014) ........................................... 25
W. River Bridge Co. v. Dix,
47 U.S. 507 (1848) ............................................. 19
WBI Energy Transmission, Inc. v.
Easement and Right-of-Way
Across Twp. 2 S.,
No. 14-CV-130, 2017 WL 532281
(D. Mont. Feb. 8, 2017) ..................................... 29
Walker v. City of Hutchinson,
352 U.S. 112 (1956) ........................................... 17
Constitutional Provisions
U.S. Const. amend. V ...............................1, 11, 16, 31
Statutes
5 U.S.C. § 702 .......................................................... 22
5 U.S.C. § 706 .....................................................11, 15
15 U.S.C. § 717 et seq................................................ 3
15 U.S.C. § 717f ......................................................... 1
xiii
15 U.S.C. § 717f(a)..................................................... 6
15 U.S.C. § 717f(c)(1)(A) ............................................ 3
15 U.S.C. § 717f(c)(1)(B) ...................................3, 5, 18
15 U.S.C. § 717f(e) ............................................... 4, 20
15 U.S.C. § 717f(h) ................................................ 3, 5
15 U.S.C. § 717r..........................................1, 7, 13, 26
15 U.S.C. § 717r(a) ......................... 3-7, 13, 14, 23, 24
15 U.S.C. § 717r(b) ...............................4, 5, 23, 24, 26
28 U.S.C. § 1254(1) .................................................... 1
18 C.F.R. § 157.201 et seq. ......................1, 5, 6, 8, 11
18 C.F.R. § 157.203 ..........................................1, 5, 21
18 C.F.R. § 157.203(b) ......................................... 7, 21
18 C.F.R. § 157.204 ............................................... 5, 6
18 C.F.R. § 157.208 ............................................1, 5, 6
18 C.F.R. § 157.208(a) ......................................... 7, 21
Other Authorities
Katy Fleury, Natural gas pipeline
project completions increase
takeaway capacity in producing
regions, U.S. Energy Info. Admin.
(March 17, 2025),
https://www.eia.gov/todayinenergy/
detail.php?id=64744&utm ................................ 27
xiv
Natural Gas Explained, U.S. Energy
Info. Admin. (Mar. 19, 2024),
https://www.eia.gov/energyexplained/
natural-gas/natural-gas-pipelines.php ................. 27
Revisions to Auxiliary Installations,
Replacement Facilities, and Siting
and Maintenance Regulations,
78 Fed. Reg. 72794, 72804, n.78
(Dec. 4, 2013) (to be codified at 18
C.F.R. §§ 157 & 380) ........................................... 5
S. Rep. No. 752, 79th Cong., 1st Sess.,
26 (1945) ............................................................ 22
A. Scalia & B. Garner, Reading Law:
The Interpretation of Legal Texts
56 (2012) ............................................................ 24
Chris Wright, Sec. of Energy, U.S.
Dept. of Energy, Keynote Remarks
at CERAWeek 2025 (Mar. 10, 2025) ................ 27
Victoria Zaretskaya, The United States
remained the world’s largest
natural gas exporter in 2024,
U.S. Energy Info. Admin.
(March 27, 2025),
https://www.eia.gov/todayinenergy/
detail.php?id=64844&utm ................................ 27
PETITION FOR A WRIT OF CERTIORARI
Petitioner RDFS, LLC (“RDFS”) respectfully
petitions for a writ of certiorari to review the
judgment of the United States Court of Appeals for
the Fourth Circuit and clarify the jurisdiction of the
federal courts to review agency interpretations of law
and to vindicate the due process rights set forth in the
Natural Gas Act and the United States Constitution.
OPINIONS BELOW
The order and judgment of the Fourth Circuit are
not reported and are included in the Appendix (“App.”)
at 1a. The Notice Rejecting Request to Intervene and
for Rehearing issued by Respondent Federal Energy
Regulatory Commission is reported at 186 FERC
¶ 62,052, the Commission’s Notice of Denial of
Rehearing is reported at 187 FERC ¶ 62,027, and both
are included in App. 3a–5a and 2a, respectively.
JURISDICTION
The Fourth Circuit entered judgment on January
8, 2025 (App. 1a). On April 1, 2025, Chief Justice
Roberts extended the time to file a petition for writ of
certiorari until June 7, 2025. This Court has
jurisdiction under 28 U.S.C. § 1254(1).
CONSTITUTIONAL, STATUTORY, AND
REGULATORY PROVISIONS INVOLVED
The relevant provisions of the Due Process Clause,
U.S. Const. Amend. V; the Natural Gas Act, 15 U.S.C.
§§ 717f, 717r; and the Commission’s regulations
under the Act, 18 C.F.R. §§ 157.201, 157.203, 157.208,
are reproduced at App. 12a–31a.
2
STATEMENT OF THE CASE
The Federal Energy Regulatory Commission’s
(“FERC”) blanket certificate regulations permit
private pipeline companies to exercise eminent
domain without individualized review, public
necessity findings, or any opportunity for affected
landowners to be heard. Blanket certificates—
creatures of regulation, not statute—never expire and
may authorize takings for decades or centuries, but
FERC nevertheless asserts that the Natural Gas Act’s
(“NGA”) statutory thirty-day rehearing provision for
Commission orders applies. Hence, under this
framework, landowners whose property is condemned
decades after a blanket certificate was issued are
barred from challenging the legality of the taking
unless they sought rehearing within thirty days of the
original certificate—no matter how long ago that was
or how unforeseeable the project, even if they did not
receive notice. FERC has effectively engineered a
regulatory scheme which insulates blanket
certificates and the condemnations they enable from
any form of judicial scrutiny.
Federal courts, in turn, have deferred to FERC.
District courts treat the original blanket certificate as
conclusive proof that FERC has reviewed and
approved each subsequent project, even though FERC
performs no such review. And, in this case, the Fourth
Circuit deferred to FERC’s interpretation of its own
power to issue the blanket certificate without
comment. This deference to FERC contravenes this
Court’s directive that courts—not agencies—must
resolve questions of law. See Loper Bright Enters. v.
Raimondo, 603 U.S. 392 (2024). Had the Fourth
3
Circuit considered the issue, it would have found that
FERC’s interpretation conflicts with the NGA’s text
and subverts constitutional protections.
Unless this Court intervenes, FERC’s regulatory
framework will continue to immunize the perpetual
exercise of eminent domain by private actors with no
meaningful judicial review.
A.
The Legal Framework of the NGA
Congress declared that federal regulation of the
transportation and sale of natural gas is necessary in
the public interest when it enacted the NGA. See 15
U.S.C. § 717 et seq. The NGA states, in relevant part,
that no company shall “undertake the construction or
extension of any facilities [for the transportation or
sale of natural gas], or acquire or operate any such
facilities or extensions thereof, unless there is in force
with respect to such natural gas company a certificate
of public convenience and necessity issued by the
Commission authorizing such acts or operations” (a
“Certificate”). 15 U.S.C. § 717f(c)(1)(A). When a
company applies for a Certificate to authorize
proposed acts or operations, the NGA requires that
FERC “shall set the matter for hearing and shall give
such reasonable notice of the hearing thereon to all
interested persons.” Id. § 717f(c)(1)(B).
The issuance of a Certificate vests the certificate
holder with the extraordinary power to condemn
private property through eminent domain. Id.
§ 717f(h). Accordingly, the NGA requires that parties
aggrieved by an order issuing such a Certificate be
permitted to “apply for a rehearing within thirty days
after the issuance of such order.” Id. § 717r(a).
4
Applying to FERC for rehearing is a prerequisite for
judicial review of the order. Id.
The NGA vests jurisdiction to review FERC’s
orders “in the court of appeals of the United States for
any circuit wherein the natural-gas company to which
the order relates is located or has its principal place of
business, or in the United States Court of Appeals for
the District of Columbia.” 15 U.S.C. § 717r(b). A party
aggrieved by a FERC order invokes the jurisdiction of
the court of appeals “by filing in such court, within
sixty days after the order of the Commission upon the
application for rehearing, a written petition praying
that the order of the Commission be modified or set
aside in whole or in part.” Id. “Upon the filing of such
petition such court shall have jurisdiction, which upon
the filing of the record with it shall be exclusive, to
affirm, modify, or set aside such order in whole or in
part.” Id. The NGA provides that “[n]o objection to the
order of the Commission shall be considered by the
court unless such objection shall have been urged
before the Commission in the application for
rehearing unless there is reasonable ground for
failure so to do.” Id.
Thus, the NGA requires that Certificates be issued
only after notice to interested parties and a hearing.
The purpose of such hearing is to ensure the proposed
acts or operations are “or will be required by the
present or future public convenience and necessity,”
and that the “applicant is able and willing properly to
do the acts and to perform the service proposed and to
conform to the provisions of the [NGA] and the
requirements, rules, and regulations of the
Commission . . . otherwise such application shall be
5
denied.” 15 U.S.C. § 717f(e). The NGA grants the
Commission some discretion in identifying interested
parties who must be notified prior to a hearing on an
application for a Certificate, but envisions that all
persons potentially aggrieved by an order will be able
to petition for rehearing within thirty days and then
to seek judicial review, if necessary. 15 U.S.C.
§§ 717f(c)(1)(B), 717r(a)–(b).
B.
Blanket Certificates
In addition to ordinary Certificates—which are
provided for in the text of the NGA—FERC
promulgated regulations which create “Blanket
Certificates.” 18 C.F.R. § 157.201 et seq. (the “Blanket
Certificate Regulations”). Blanket Certificates grant
holders “[a]utomatic authorization” to engage in
certain activities—including eminent domain—
“without further Commission approval,” provided that
the project cost does not exceed $14.5 million. Id.
§§ 157.203, 157.208; 15 U.S.C. § 717f(h). Under the
regulations, FERC is not obligated to review (or even
be aware of) any given project that a certificate holder
claims is covered by a Blanket Certificate prior to a
condemnation action. FERC’s Blanket Certificate
Regulations do not place any temporal or geographic
limitations on acts which are automatically
authorized. See 18 C.F.R. §§ 157.204, 157.203,
157.208. 1 Blanket Certificates never expire and never
See also Revisions to Auxiliary Installations, Replacement
Facilities, and Siting and Maintenance Regulations, 78 Fed. Reg.
72794, 72804, n.78 (Dec. 4, 2013) (to be codified at 18 C.F.R.
§§ 157 & 380) (noting that “in instances where a pipeline
company . . . constructs auxiliary or replacement facilities . . .
1
6
need to be renewed. See generally 18 C.F.R. § 157.201
et seq. While the certificate holder is prohibited from
“segment[ing] projects in order to meet the cost
limitation[],” there is no mechanism for an aggrieved
party to request enforcement. See generally 18 C.F.R.
§ 157.208. 2
Before a Blanket Certificate is issued, a pipeline
operator must file an application with certain
prescribed contents. 18 C.F.R. § 157.204. FERC is
then obligated to hold a hearing to consider whether
“such action [is] necessary or desirable in the public
interest.” 15 U.S.C. § 717f(a). FERC may then order
that the Blanket Certificate is issued and—according
to FERC—any aggrieved party must file an
application for rehearing within thirty days or further
review is barred. 15 U.S.C. § 717r(a). The thirty-day
deadline for an application for rehearing is a
jurisdictional bar to challenges to FERC orders. Id.
Additionally, FERC orders granting certificates may
not be attacked collaterally. E.g., Columbia Gas
Transmission, LLC v. RDFS, LLC, No. 23-CV-364,
2024 WL 993093, at *2 (N.D.W. Va. Feb. 27, 2024)
(“Collateral attacks on a certificate in federal district
courts are improper.”). As condemnations of private
property for new projects under a Blanket Certificate
can be “authorize[d] . . . without further Commission
approval,” there is no new “order issued by the
Part 157 blanket certificate regulations impose no limitations on
the placement of the facilities”).
2 See also Pavelich v. Nat. Gas Pipeline Co. of Am., No. 02 C
3374, 2003 WL 22303140, at *3 (N.D. Ill. Oct. 8, 2003) (finding
no private right of action to enforce the segmentation limit).
7
Commission” subject to hearing and review. See 15
U.S.C. § 717r; 18 C.F.R. §§ 157.203(b), 157.208(a).
Whether an order granting a Blanket Certificate is
valid for the purposes of the Section 717r(a)
jurisdictional bar appears to be a question of first
impression. Nonetheless, FERC argued below that the
jurisdictional bar applied and the Fourth Circuit
deferred to FERC on the question. See, e.g., 186 FERC
¶ 62,052 (“Because the 30-day rehearing deadline is
statutorily based, it cannot be waived or extended,
and the request for rehearing . . . must be rejected as
untimely.”); RDFS, LLC v. Fed. Energy Regul.
Comm’n, 24-1530 [ECF No. 29] (4th Cir. Jan. 8, 2025)
(summarily dismissing the appeal below for want of
jurisdiction). The upshot is that—according to FERC
and the lower courts—thirty-one days after a Blanket
Certificate is issued it becomes unreviewable, even
though that Blanket Certificate may last decades or
centuries, even though the land condemned by the
holder may be far removed from that originally
contemplated by the Blanket Certificate, and even
though the landowner had no opportunity to object.
In other words, a Blanket Certificate holder
forever has the power to condemn property and, so
long as it spends less than $14.5 million at a time (a
limit which is also unreviewable), it need not make
any individual showing of public necessity and a
landowner has no legal recourse whatsoever. 3
See generally Columbia Gas Transmission, LLC v. 1.01
Acres, More or Less in Penn Twp., 768 F.3d 300, 316 (3d Cir.
3
2014) (Jordan, J., dissenting) (“[FERC’s regulations are] a grant
of limitless authority to natural gas companies . . . to bypass all
8
C.
Relevant Facts and Procedural History
RDFS is a family-owned company formed to own
and manage certain real property interests for
members of the Six family in West Virginia. These
include a certain tract of land located in Wetzel
County, West Virginia, known as tax parcel number
2-8-58 (the “Property”). RDFS’s predecessor in
interest granted an easement and right of way on the
Property to The Manufacturers Light and Heat
Company dated November 3, 1969, recorded in the
office of the County Clerk of Wetzel County, West
Virginia (the “Right of Way”). There is no properly
indexed instrument of record in Wetzel County which
conveys the interest of Manufacturers under the Right
of Way to any party. Today, Columbia Gas
Transmission, LLC (“Columbia”), the IntervenorRespondent below, operates a pipeline across the
Right of Way.
In November 1982, Columbia Gas Transmission
Corporation applied to FERC for a Blanket Certificate
under 18 C.F.R. § 157.201 et seq. RDFS’s predecessors
in interest were not notified as interested parties prior
to FERC’s hearing on the application. On January 7,
1983, FERC granted the Blanket Certificate in its
order styled “Findings and Order after statutory
Hearing Issuing Certificate of Public Convenience and
Necessity Authorizing Routine Activities and
notice-and-hearing requirements by tying its proposed project to
the originally authorized pipeline, even if that authorization was
provided decades ago and in an entirely different location. No
consideration is given to the rights of newly affected parties.
That is fundamentally at odds with regulations requiring notice
and an opportunity to participate in certificate hearings.”).
9
Permitting and Approving Abandonment” at Docket
No. CP83-76-000, 22 FERC ¶ 62,029 (1983)
(“Columbia’s Blanket Certificate”) (App. 6a). In the
intervening decades, the Certificate was transferred
to Columbia.
About forty years later, in 2023, a resource
extraction company began performing longwall coal
mining in the area around and beneath the Property.
Columbia asserted a need to condemn part of the
Property to support its operations to mitigate
potential subsidence damage to its pipeline resulting
from the mining. To that end, Columbia filed and
served a Complaint and Notice of Condemnation upon
RDFS on December 20, 2023, in the United States
District Court for the Northern District of West
Virginia. Columbia Gas Transmission, LLC v. RDFS,
LLC, No. 23-CV-364 [ECF No. 1] (N.D.W. Va. Dec. 19,
2023). At no time prior to Columbia filing suit did
RDFS or its predecessors in interest have notice that
Columbia’s Blanket Certificate—issued in the name of
a defunct corporation and subsequently transferred to
a company which had no record title to natural gas
facilities on the Property—would potentially
authorize takings on the Property.
RDFS attempted to challenge the condemnation of
its property, including whether the proposed
operations complied with the NGA, but the District
Court deferred to FERC and the Fourth Circuit.
Specifically, the District Court stated that “Collateral
attacks on a certificate in federal district courts are
improper. . . . [T]he proper channel to challenge the
FERC certificate is to seek administrative review
under the Natural Gas Act and judicial review is only
10
available in the Court of Appeals.” RDFS, 2024 WL
993093, at *2 (cleaned up).
In parallel, on January 24, 2024, RDFS filed a
motion to intervene and for rehearing on Columbia’s
Blanket Certificate with FERC. In re Columbia Gas
Transmission Corp., No. CP83-76-0008 (Jan. 24,
2024). FERC denied Petitioner’s request on February
7, 2024. 186 FERC ¶ 62,052 (App. 3a). RDFS timely
requested reconsideration but received a Denial of
Rehearing by Operation of Law on April 11, 2024,
when FERC failed to act. 187 FERC ¶ 62,027 (App.
2a).
On June 10, 2024, RDFS timely petitioned the
Fourth Circuit for review of FERC’s decision to deny
RDFS’s motion. RDFS, LLC v. U.S. Fed. Energy Reg.
Comm’n, No. 24-1530 [ECF No. 3] (4th Cir. June 10,
2024). On November 1, 2024, FERC moved the Fourth
Circuit to dismiss RDFS’s petition for want of
jurisdiction. RDFS, No. 24-1530 [ECF No. 20]. FERC
argued that because the NGA requires aggrieved
parties to petition for rehearing within thirty days of
FERC’s order granting the Blanket Certificate (issued
in 1982) RDFS’s application for rehearing was
untimely. Id. at 3–5. FERC further argued that a
timely application for rehearing is a pre-requisite for
seeking judicial review, so the Fourth Circuit lacked
jurisdiction. Id.
On January 8, 2025, the Fourth Circuit entered an
order which simply stated: “Upon consideration of the
submissions relative to respondent’s motion to
dismiss the appeal for lack of jurisdiction and
intervenor’s motion to reply to the motion to dismiss,
11
the court grants the motions.” RDFS, No. 24-1530
[ECF No. 29].
REASONS FOR GRANTING THE PETITION
FERC’s Blanket Certificate Regulations, 18 C.F.R.
§ 157.201 et seq., grant private companies perpetual
authority to exercise eminent domain without the
constitutional safeguards of notice, hearing, or
judicial review. By deferring to FERC’s interpretation
of its own authority, the Fourth Circuit allowed an
agency-created regime to operate beyond the bounds
of the Natural Gas Act and the Fifth Amendment.
This case presents critical questions about the scope
of agency power, access to judicial review, and the
rights of property owners—all of which merit this
Court’s plenary attention.
I.
The Fourth Circuit Improperly Ceded
Judicial Authority to FERC
The Fourth Circuit deferred without discussion to
an agency’s construction of its governing statute that
tramples on the text of that statute and the
constitutional rights of impacted persons. Aside from
being substantively incorrect, the Fourth Circuit’s
deference also runs afoul of this Court’s instruction
that “courts, not agencies, will decide all relevant
questions of law arising on review of agency action.”
Loper Bright, 603 U.S. at 392 (quotation marks
omitted, emphasis in original) (quoting 5 U.S.C.
§ 706).
12
A.
Deference to FERC on the Scope of Its
Own Power Contradicts This Court’s
Clear Precedent
The Fourth Circuit erred by deferring to FERC on
the threshold question of its own authority. It is wellsettled that, where an agency promulgates a
regulation that is “out of harmony with the [enacting]
statute, [it] is a mere nullity.” Dixon v. United States,
381 U.S. 68, 74 (1965) (quoting Manhattan Gen.
Equip. Co. v. Comm’r of Internal Revenue, 297 U.S.
129, 134 (1936)); accord Alexander v. Sandoval, 532
U.S. 275, 291 (2001) (“Agencies may play the
sorcerer’s apprentice but not the sorcerer himself.”).
Accordingly, this Court has a long history of analyzing
regulations for compliance with their enacting
statutes and, if they are in conflict, striking them
down. See, e.g., Alexander, 532 U.S. at 291; United
States v. Larionoff, 431 U.S. 864, 877 (1977); Brown v.
Gardner, 513 U.S. 115, 122 (1994); Leary v. United
States, 395 U.S. 6, 24 (1969); Koshland v. Helvering,
298 U.S. 441, 447 (1936).
To that end, this Court explained just last year
that “[c]ourts must exercise their independent
judgment in deciding whether an agency has acted
within its statutory authority.” Loper Bright, 603 U.S.
at 412. While “the judgment of the Executive Branch
may help inform that inquiry . . . [,] courts need not
and under the APA may not defer to an agency
interpretation of law.” Id. at 413 (emphasis added);
accord Seven Cnty. Infrastructure Coal. v. Eagle
Cnty., --- S.Ct.--- No. 23-975, 2025 WL 1520964, at *6
(U.S. May 29, 2025) (“[W]hen an agency interprets a
statute, judicial review of the agency’s interpretation
13
is de novo.”). At its root, this principle is a recognition
and extension of Chief Justice Marshall’s declaration
that “[i]t is emphatically the province and duty of the
judicial department to say what the law is.” Marbury
v. Madison, 5 U.S. 137, 177 (1803); see Loper Bright,
603 U.S. at 412.
In accordance with this doctrine, about five years
ago the Court of Appeals for the District of Columbia
Circuit considered a similar issue under 15 U.S.C.
§ 717r and held that FERC was not entitled to
deference. There, the court considered “whether
[FERC] had the authority to issue . . . Tolling Order[s]
that . . . prevent the petitioners from seeking judicial
review.” Allegheny Def. Project v. FERC, 964 F.3d 1,
12 (D.C. Cir. 2020) (en banc). FERC argued that it was
entitled to deference because “15 U.S.C.§ 717r(a)
addresses only FERC’s own jurisdiction to entertain
rehearing requests.” Id. (cleaned up). Rejecting this
argument, the court held that:
[D]eference is available only when an
agency interprets a statutory provision
that Congress has charged it with
administering through application of its
expertise. But statutory provisions
addressing the jurisdiction of federal
courts do not fit that mold. Federal
agencies do not administer and have no
relevant expertise in enforcing the
boundaries of the courts’ jurisdiction.
Id. at 11 (citation omitted).
This case presented a similar issue, but the Fourth
Circuit held that it lacked jurisdiction to hear RDFS’s
petition. RDFS, No. 24-1530 [ECF No. 29]. In so doing,
14
it relied on FERC’s one and only argument: that an
order issuing a Blanket Certificate is subject to the
NGA’s thirty-day jurisdictional bar, irrespective of
any future condemnations executed pursuant to that
certificate. 15 U.S.C. § 717r(a). See RDFS, No. 241530 [ECF No. 20]. But the Fourth Circuit’s decision
begs the question: Does FERC have the power to order
the issuance of such a Blanket Certificate in the first
place?
The Fourth Circuit should not have deferred to
FERC on this question. Since portions of the Blanket
Certificate Regulations are at loggerheads with the
NGA, see infra § II(A), (B), there is at least a colorable
claim that they are “a mere nullity.” Dixon, 381 U.S.
at 74 (citation omitted). This is precisely the sort of
question this Court advised the lower courts to take
up (rather than defer on) in Loper Bright. See 603 U.S.
at 401 (“The very point of the traditional tools of
statutory construction—the tools courts use every
day—is to resolve statutory ambiguities. That is no
less true when the ambiguity is about the scope of an
agency’s own power—perhaps the occasion on which
abdication in favor of the agency is least appropriate.”
(emphasis in original)); see also id. at 414 (Thomas, J.,
concurring) (“The judicial power, as originally
understood, requires a court to exercise its
independent
judgment
in
interpreting
and
expounding upon the laws.” (brackets and citation
omitted)); id. at 430 (Gorsuch, J., concurring) (“Th[e]
duty of independent judgment is perhaps the defining
characteristic of Article III judges.” (cleaned up)).
Accordingly, a court of appeals must first determine
whether a regulation that purports to strip it of
15
jurisdiction is lawful before dismissing a petition on
that basis.
B.
The Decision Below Improperly Insulates
Agency Action from Constitutional
Scrutiny
Not only did the Fourth Circuit defer to FERC on
a legal question, it did so despite the obvious
constitutional issues appearing on the face of this
dispute, see infra § II, and which were squarely
presented to it. See, e.g., Miller v. Johnson, 515 U.S.
900, 923 (1995) (“[W]e think it inappropriate for a
court engaged in constitutional scrutiny to accord
deference to the [agency’s] interpretation of the Act.”);
Allentown Mack Sales & Serv., Inc. v. N.L.R.B., 522
U.S. 359, 387 (1998) (Rehnquist, C.J., concurring in
part and dissenting in part) (“We have held that when
an [agency] interpretation raises such constitutional
concerns, the [agency’s] interpretation of the
[enacting statute] is not entitled to deference.”); Loper
Bright, 603 U.S. at 391 (“[W]hen presented, the
reviewing court shall . . . interpret constitutional and
statutory provisions . . . .” (quoting 5 U.S.C. § 706)).
FERC’s regulations allow companies to selfauthorize projects under Blanket Certificates without
FERC making any actual determination as to whether
the takings are in the public interest or in accordance
with the NGA. See infra § II(A), (B). Then, according
to FERC, the NGA bars district courts from
collaterally reviewing whether those takings are for a
lawful purpose. If courts of appeals are permitted to
simply accept FERC’s position that Blanket
Certificates are permanently unreviewable—even as
they continue to authorize new takings decades
16
later—then there is no courtroom left in which
aggrieved landowners may seek recourse.
Based on this Court’s precedent and the principles
of separation of powers, the Fourth Circuit should not
have deferred to FERC on the scope of its powers and
the constitutionality of the Blanket Certificate
Regulations.
II.
FERC’s Blanket Certificate Mechanism is an
Expansion of Executive Power in Defiance of
the Text of the NGA, the Fifth Amendment,
and this Court’s Precedents
FERC’s Blanket Certificate Regulations are
unconstitutional and out of line with this Court’s
precedents. They permit private companies to selfauthorize takings without due process for landowners
or any finding that specific projects serve the public
interest, then shield those actions from judicial
review. This unchecked delegation of power violates
the Fifth Amendment, circumvents the procedural
safeguards in the NGA, and conflicts with this Court’s
precedent on judicial oversight of agency action.
A.
Blanket Certificates Violate
Principles of Due Process
Core
Landowners are stripped of due process under
FERC’s Blanket Certificate regime. The Fifth
Amendment to the United States Constitution
guarantees that “No person shall . . . be deprived of
life, liberty or property, without due process of law.”
U.S. Const. Amend. V. While the requirements of due
process vary by context, “[a]n elementary and
fundamental requirement of the process in any
proceeding which is to be accorded finality is notice
17
reasonably calculated, under all the circumstances, to
apprise interested parties of the pendency of the
action and afford them an opportunity to present their
objections.” Covey v. Town of Somers, 351 U.S. 141,
146 (1956) (quoting Mullane v. Cent. Hanover Bank &
Tr. Co., 339 U.S. 306, 314 (1950)). “Failure to give
notice violates the most rudimentary demands of due
process of law.” Peralta v. Heights Med. Ctr., Inc., 485
U.S. 80, 84 (1988) (quotations and citation omitted));
see Walker v. City of Hutchinson, 352 U.S. 112, 115
(1956) (“[D]ue process requires that an owner whose
property is taken for public use must be given a
hearing . . . [but] [t]he right to a hearing is
meaningless without notice.”); Mennonite Bd. of
Missions v. Adams, 462 U.S. 791, 800 (1983) (“Notice
by mail or other means as certain to ensure actual
notice is a minimum constitutional precondition to a
proceeding which will adversely affect the . . .
property interests of any party . . . .” (emphasis in
original)).
Further, “[t]he right to a prior hearing has long
been recognized by this Court,” which has
“traditionally insisted that, whatever its form,
opportunity for that hearing must be provided before
the deprivation at issue takes effect.” Fuentes v.
Shevin, 407 U.S. 67, 82, (1972). The opportunity to
present objections must be “granted at a meaningful
time and in a meaningful manner.” Parratt v. Taylor,
451 U.S. 527, 540 (1981) (quoting Armstrong v.
Manzo, 380 U.S. 545, 552 (1965)), overruled on other
grounds by Daniels v. Williams, 474 U.S. 327 (1986).
Congress recognized the strictures of due process
in the statutory text of the NGA. Before issuing a
18
Certificate, the statute requires that FERC “shall set
the matter for hearing and shall give such reasonable
notice of the hearing thereon to all interested
persons.” 15 U.S.C. § 717f(c)(1)(B). The statute
conforms to the paradigmatic formulation of due
process: notice and an opportunity to be heard.
Blanket Certificates, however, fall drastically
short of these constitutional and statutory mileposts.
The automatic authorization provisions allow
perpetual, self-implementing takings for future
activities often unforeseen at the time the Blanket
Certificate was issued, making notice to affected
parties impossible. Take the facts of this case as an
example. RDFS would have had to attend FERC’s
hearing on Columbia’s Blanket Certificate in 1982,
forty years before any indication that its property
could be condemned. FERC offers the façade of due
process, not its constitutional guarantee.
B.
Blanket Certificates Invoke the Takings
Power Without Safeguarding the Public
Use Requirement
The Blanket Certificate Regulations also violate
constitutional and statutory safeguards on takings.
The Fifth Amendment’s property protections include
that “one person’s property may not be taken for the
benefit of another private person without a justifying
public purpose, even though compensation be paid.”
Thompson v. Consolidated Gas Corp., 300 U.S. 55, 80
(1937); accord Kelo v. City of New London, 545 U.S.
469, 497 (2005) (O’Connor, J., dissenting) (“[The]
Government may compel an individual to forfeit her
property for the public’s use, but not for the benefit of
19
another private person. This requirement promotes
fairness as well as security.”).
The question of what constitutes a public use
“remains a judicial one.” City of Cincinnati v. Vester,
281 U.S. 439, 446 (1930). Thus, while courts accord
deference to the political branches on whether a
taking serves a “public use,” this Court’s
jurisprudence requires that an agency undertake factspecific analysis, supported by the record, to
demonstrate that each taking is not “under the mere
pretext of a public purpose.” Kelo, 545 U.S. at 478. As
Justice O’Connor recognized in dissent in Kelo:
Where is the line between “public” and
“private” property use? We give
considerable deference to legislatures’
determinations
about
what
governmental activities will advantage
the public. But were the political
branches the sole arbiters of the publicprivate distinction, the Public Use
Clause would amount to little more than
hortatory fluff. An external, judicial
check on how the public use requirement
is interpreted, however limited, is
necessary if this constraint on
government power is to retain any
meaning.
Kelo, 545 U.S. at 497 (O’Connor, J., dissenting). 4
Therefore, for each taking, there must be at least some
See also W. River Bridge Co. v. Dix, 47 U.S. 507, 545 (1848)
(Woodbury, J., concurring) (“[T]he doctrine[] that this right of
eminent domain exists . . . when merely convenient, though not
4
20
opportunity for an aggrieved property owner to
challenge whether “the public has a right to employ
[the power of the Takings Clause].” 5 Eychaner v. City
of Chicago, 141 S. Ct. 2422, 2423 (2021) (Thomas, J.,
dissenting from denial of cert.) (citation omitted);
compare Nat’l R.R. Passenger Corp. v. Bos. & Maine
Corp., 503 U.S. 407, 422 (1992) (“[T]he public use
requirement of the Takings Clause is coterminous
with the regulatory power . . . .”), with Michigan v.
E.P.A., 576 U.S. 743, 750 (2015) (“[A]gency action is
lawful only if it rests on a consideration of the relevant
factors.” (quotation marks and citation omitted)).
Recognizing this constitutional imperative,
Congress embedded its protection in the NGA. FERC
may only grant a Certificate if it concludes that “the
proposed service, sale, operation, construction,
extension, or acquisition . . . is or will be required by
the present or future public convenience and
necessity.” 15 U.S.C. § 717f(e).
The Blanket Certificate Regulations evade these
safeguards on takings. So long as a project does not
necessary, does not seem to me by any means clearly
maintainable. It is too broad, too open to abuse.”).
5 See also Chicago, B. & Q. Ry. Co. v. Illinois, 200 U.S. 561,
593 (1906) (“If, in the execution of any power, no matter what it
is, the government, Federal or state, finds it necessary to take
private property for public use . . . [,] [i]f the means employed
have no real, substantial relation to public objects which
government may legally accomplish,—if they are arbitrary and
unreasonable, beyond the necessities of the case,—the judiciary
will disregard mere forms, and interfere for the protection of
rights injuriously affected by such illegal action. The authority
of the courts to interfere in such cases is beyond all doubt.”
(citations omitted)).
21
exceed $14.5 million, a gas company is automatically
authorized to exercise eminent domain without
regard to geographic or temporal limits. 6 See 18
C.F.R. §§ 157.203(b), 157.208(a). In cases of Blanket
Certificates issued decades before the relevant project
was even conceived, the assertion that the project
complies
with
the
NGA
because
FERC
“automatically” approved it, or that administrative
review is available through FERC, is an
unsustainable fiction. Neither the agency nor the
certificate holder is obligated to make a “public
necessity” finding before condemning property (or
after, for that matter). And landowners are left with
no meaningful avenue to challenge whether their
property is being taken for public use or not. In sum,
the Blanket Certificate Regulations lack any
safeguard against takings for private use. With no
expiration and no oversight, these perpetual
authorizations—wielded entirely at the discretion of
private actors—pose a serious and unchecked risk of
abuse.
C.
Blanket Certificates Allow Eminent
Domain to be Exercised in Perpetuity,
Shielded from Judicial Scrutiny
Not only do the Blanket Certificate Regulations
make it impossible to be heard by FERC, they—
contrary to the text of the NGA—also make judicial
review effectively impossible. When this Court
6 It bears repeating that that this project size limit is
enforced by what amounts to the honor system. See 18 C.F.R.
§ 157.203. A party whose land is being condemned may not
challenge the condemnation on this ground. E.g., Pavelich, 2003
WL 22303140, at *3.
22
reviews a regulation, it “begin[s] with the strong
presumption that Congress intends judicial review of
administrative action.” Bowen v. Mich. Acad. of Fam.
Physicians, 476 U.S. 667, 670 (1986). Thus, “judicial
review of a final agency action by an aggrieved person
will not be cut off unless there is persuasive reason to
believe that such was the purpose of Congress.” Id.
(quoting Abbott Lab’ys v. Gardner, 387 U.S. 136, 140
(1967)). As the Court has recognized, “[i]t has never
been the policy of Congress to prevent the
administration of its own statutes from being
judicially [reviewed, because] . . . statutes would in
effect be blank checks drawn to the credit of some
administrative officer or board.” Id. at 671 (quoting S.
Rep. No. 752, 79th Cong., 1st Sess., 26 (1945)); see
5 U.S.C. § 702 (“A person suffering legal wrong
because of agency action, or adversely affected or
aggrieved by agency action within the meaning of a
relevant statute, is entitled to judicial review
thereof.”). This presumption carries even greater
weight where, as here, judicial review is the only
check on political overreach. See Kelo, 545 U.S. at 497
(O’Connor, J., dissenting) (“[W]ere the political
branches the sole arbiters of the public-private
distinction, the Public Use Clause would amount to
little more than hortatory fluff.”); Cedar Point
Nursery v. Hassid, 594 U.S. 139, 147 (2021)
(“[P]rotection of property rights is necessary to
preserve freedom and empowers persons to shape and
to plan their own destiny in a world where
23
governments are always eager to do so for them.”
(cleaned up)). 7
This fundamental presumption is codified in the
NGA, which explicitly ensures that FERC orders are
subject to judicial review. 15 U.S.C. § 717r(b). Yet,
FERC has crafted a regulatory scheme that renders
this right illusory. FERC points to the jurisdictional
bar in 15 U.S.C. § 717r(a), which states that “[n]o
proceeding to review any order of the Commission
shall be brought by any person unless such person
shall have made application to the Commission for a
rehearing thereon [within thirty days].”
Under this framework, eminent domain exercised
under a Blanket Certificates—which may remain
valid for decades or even centuries without geographic
limitations—is effectively immune from judicial
review. As this case illustrates, notice of
condemnation under a Blanket Certificate (if a
landowner receives any at all) may come decades after
the issuance of that certificate. Yet FERC insists that
any challenge must have been brought within thirty
7 See also Loretto v. Teleprompter Manhattan CATV Corp.,
458 U.S. 419, 436 (1982) (“[A]n owner suffers a special kind of
injury when a stranger directly invades and occupies the owner’s
property. . . . [P]roperty law has long protected an owner’s
expectation that he will be relatively undisturbed at least in the
possession of his property. To require, as well, that the owner
permit another to exercise complete dominion literally adds
insult to injury.
Furthermore, such an occupation is
qualitatively more severe than a regulation of the use of
property, even a regulation that imposes affirmative duties on
the owner, since the owner may have no control over the timing,
extent, or nature of the invasion.” (citations omitted, emphases
in original)).
24
days of the original Blanket Certificate order—no
matter how remote in time or location the eventual
project and condemnation may be. 8 See, e.g., RDFS,
No. 24-1530 [ECF No. 20] (“The application of [15
U.S.C. § 717r(a)] to this case is . . . clear. RDFS did
not apply for agency rehearing within thirty days of
the Certificate Order; it did not even apply within
thirty years of that order. Its tardiness precludes
jurisdiction.”
(emphasis
in
original)).
This
interpretation nullifies the NGA’s guarantees of
judicial review, and leaves landowners with no
meaningful way to challenge the taking of their
property. Allowing FERC to foreclose judicial review
of new takings on previously unaffected properties
under decades old Blanket Certificates, “would
essentially close the courthouse doors on those
unregulated plaintiffs—a radical change to
administrative law that would insulate a broad swath
of agency actions from any judicial review.” Corner
Post, Inc. v. Bd. of Governors of Fed. Rsrv. Sys., 144
S. Ct. 2440, 2463 (2024) (Kavanaugh, J., concurring).
FERC’s strategy of condemnation-by-surprise
should be rejected. Congress clearly intended that
FERC orders be judicially reviewable, which is why it
included Section 717r(b) in the text of the NGA. 15
U.S.C. § 717r(b); see generally CTS Corp. v.
Waldburger, 573 U.S. 1, 12 (2014) (“Congressional
intent is discerned primarily from the statutory
text.”); A. Scalia & B. Garner, Reading Law: The
Interpretation of Legal Texts 56 (2012) (“[Congress’s]
purpose must be derived from the text . . . .”). By
8 And, as described above, a Blanket Certificate may not be
attacked collaterally, either. E.g., RDFS, 2024 WL 993093, at *2.
25
treating issuance of a Blanket Certificate as a single
final “order,” despite its open-ended “automatic
authorizations” of then-unknown future projects,
FERC entirely insulates itself from judicial scrutiny,
defying both the text of the NGA and this Court’s
presumption of judicial review. “[A]n agency
interpretation that is inconsistent with the design and
structure of the statute as a whole” is “impermissible.”
Util. Air Regul. Grp. v. E.P.A., 573 U.S. 302, 321
(2014) (cleaned up)); see Loper Bright, 603 U.S. at 387
(“[T]he supremacy of law demands that there shall be
opportunity to have some court decide whether an
erroneous rule of law was applied.” (citation omitted));
Corner Post, 603 U.S. at 824 (An interpretation
should be disfavored where it means that “only those
fortunate enough to suffer an injury within” a short
time after agency action may seek relief and
“[e]veryone else—no matter how serious the injury or
how illegal the rule—has no recourse.” (cleaned up)).
The decision below is fundamentally at odds with
constitutional guarantees, the NGA’s statutory
framework, and this Court’s established precedent.
Plenary review is warranted.
III. The Decision Below Presents a Circuit Split
With Broad Implications for an Expanding
Nationwide Industry, Raises Significant
Constitutional Questions, and the Issues
Presented Are Likely to Recur in the Absence
of this Court’s Review
The Fourth Circuit’s decision warrants this
Court’s immediate review. It conflicts with the
decision of another Circuit Court of Appeals which is
injecting uncertainty into a growing industry of
26
national importance, it is unlikely to be corrected
without intervention, and it is manifestly contrary to
this Court’s precedents.
First, there is an important split between the
Courts of Appeals for the Fourth Circuit and the
District of Columbia Circuit regarding whether FERC
is entitled to deference in its interpretation and
application of 15 U.S.C. § 717r—the NGA’s section
dealing with jurisdiction. As discussed above, the
Fourth Circuit deferred without comment to FERC’s
interpretation of Section 717r. RDFS, No. 24-1530
[ECF No. 29]. On the other hand, the District of
Columbia Circuit held just five years ago that FERC
was not entitled to deference when interpreting
Section 717r because “Federal agencies do not
administer and have no relevant expertise in
enforcing the boundaries of the courts’ jurisdiction.”
Allegheny Def. Project, 964 F.3d at 11. This case
would have been decided differently if RDFS had
brought it in the District of Columbia Circuit instead
of the Fourth Circuit.
This is not an idle distinction: the split between the
Fourth and District of Columbia Circuits will
encourage forum shopping and undermine the NGA.
The statute authorizes any proceeding by an
aggrieved party to proceed in either “the court of
appeals of the United States for any circuit wherein
the natural-gas company . . . has its principal place of
business, or in the United States Court of Appeals for
the District of Columbia.” 15 U.S.C. § 717r(b)
(emphasis added). In other words, every suit
challenging FERC action can be brought in the
District of Columbia Circuit, and now every plaintiff
27
filing such a suit has an incentive to do so. Contrary
to the NGA, this split will take cases away from the
Fourth Circuit and funnel them into the District of
Columbia Circuit.
Additionally, the eminent domain power granted
to the natural gas industry has wide-reaching
implications. There are about three million miles of
natural gas pipeline in the United States. Natural
Gas Explained, U.S. Energy Info. Admin. (Mar. 19,
2024), https://www. eia.gov/energyexplained/naturalgas/natural-gas-pipelines.php. The United States is
the world’s largest liquefied natural gas exporter,
exporting 11.9 billion cubic feet per day in 2024. 9 New
pipeline projects added 6.5 billion cubic feet of
takeaway capacity in 2024 alone. 10 Natural gas is
responsible for 43% of U.S. electricity, is the largest
source of home heating in the U.S., supplies 25% of
global primary energy, and has been the fastest
growing source of energy over the last 15 years. Chris
Wright, Sec. of Energy, U.S. Dept. of Energy, Keynote
Remarks at CERAWeek 2025 (Mar. 10, 2025).
Accordingly, the Fourth Circuit’s error risks
widespread unconstitutional deprivations of property
across countless affected landowners. At the same
time, the industry is growing; if the Fourth Circuit’s
9 Victoria Zaretskaya, The United States remained the
world’s largest natural gas exporter in 2024, U.S. Energy Info.
Admin.
(March
27,
2025),
https://www.eia.gov/todayinenergy/detail.php?id=64844&utm.
10 Katy Fleury, Natural gas pipeline project completions
increase takeaway capacity in producing regions, U.S. Energy
Info.
Admin.
(March
17,
2025),
https://www.eia.gov/todayinenergy/detail.php?id=64744&utm.
28
deference was improper, and if FERC’s regulations
are unconstitutional, all parties involved would
benefit from this Court’s swift action so that the
infirmities can be rectified as quickly as possible. This
Court has recognized the importance of natural gas
regulations by granting a writ of certiorari in a
natural gas case as recently as 2021. See PennEast
Pipeline Co., LLC v. New Jersey, 594 U.S. 482 (2021).
Moreover, the deprivations occurring under
FERC’s regulations are unlikely to stop absent
intervention of this Court because there is no judicial
review whatsoever of the regulations, so nothing short
of a constitutional attack on the scheme has any
chance of success. Cases involving Blanket
Certificates typically occur after the Certificates have
been issued (and long after the window to challenge
them has closed) in the context of a private natural
gas company condemning land. The natural gas
company typically moves for, and is granted, an early
preliminary injunction for immediate entry, while the
district court reserves on the issue of compensation. 11
See, e.g., the Florida Gas Transmission cases: 707 F. Supp.
3d 1258, 1264 (M.D. Fla. 2023); No. 23-CV-612, 2023 WL
8716597, at *6 (M.D. Fla. Dec. 18, 2023); No. 18-CV-3059, 2019
WL 2613337 (M.D. Fla. Mar. 12, 2019); No. 18-CV-3062, 2019
WL 1371492, at *2 (M.D. Fla. Mar. 11, 2019); the UGI Sunbury
cases: No. 16-CV-00791, 2016 WL 4089126, at *6 (M.D. Pa. Aug.
2, 2016); No. 16-CV-00788, 2016 WL 4089120, at *6 (M.D. Pa.
Aug. 2, 2016); No. 16-CV-00790, 2016 WL 4089124, at *6 (M.D.
Pa. Aug. 2, 2016); No. 16-CV-00793, 2016 WL 3254987, at *6
(M.D. Pa. June 14, 2016); No. 16-CV-00783, 2016 WL 3254986,
at *7 (M.D. Pa. June 14, 2016); No. 16-CV-00801, 2016 WL
3254991, at *9 (M.D. Pa. June 14, 2016); No. 3:16-CV-00798,
2016 WL 3254988, at *9 (M.D. Pa. June 14, 2016); N. Nat. Gas
11
29
These suits typically involve unsophisticated
defendants and concern dollar amounts which,
individually, are far lower than the cost of litigating
and appealing complex constitutional issues. Thus,
these landowners are essentially presented with a fait
accompli, and the prospect of further litigation is
particularly unappetizing. See generally Allegheny
Def. Project, 964 F.3d at 10 (collecting examples
where FERC used administrative hurdles to allow
construction to proceed and moot landowners’ claims).
And where two appeals finally did implicate
constitutional issues, two circuit courts of appeals
declined to reach them. See RDFS, 24-1530 [ECF No.
29] (deferring to FERC without comment); Columbia
Gas, 768 F.3d at 313 (“[T]his constitutional
argument . . . is not properly before us.”). In sum,
there is a confluence of factors here that make it
difficult for any individual to vindicate these rights.
As such, it is a near-certainty that these
constitutional violations will continue in the absence
of this Court’s intervention.
The Fourth Circuit’s opinion was also manifestly
contrary to this Court’s precedents. Specifically, the
Co. v. Easement & Right-of-way Across 33.523 Acres More or
Less, No. 23-CV-1906, 2023 WL 4936163, at *3 (D. Minn. Aug. 2,
2023); WBI Energy Transmission, Inc. v. Easement and Rightof-Way Across Twp. 2 S., No. 14-CV-130, 2017 WL 532281, at *4
(D. Mont. Feb. 8, 2017); Sabal Trail Transmission, LLC v. +/- 0.4
Acres of Land in Marion Cnty., No. 16-CV-210, 2016 WL
2997672, at *5 (M.D. Fla. May 25, 2016); Columbia Gas
Transmission, LLC v. 10.5068 Acres, More or Less in York Cnty.,
No. 15-CV-0360, 2015 WL 3831181, at *1 (M.D. Pa. June 19,
2015); E. Tennessee Nat. Gas Co. v. Sage, 361 F.3d 808, 828 (4th
Cir. 2004).
30
Fourth Circuit gave its imprimatur to an agencycreated scheme which grants to private entities the
virtually unlimited authority to condemn property in
the name of the government, with no regard for due
process or whether such taking is for private or public
use. The Fourth Circuit declined to directly consider
these issues and, instead, simply deferred to FERC’s
interpretation of FERC’s power without discussion.
Thus, the Fourth Circuit’s opinion is directly contrary
not only to this Court’s precedents regarding due
process and takings, but also on the consideration of
agency interpretations of agency power.
At its core, the Fourth Circuit’s error here
undermines the separation of powers between the
executive and judicial branches. Court review of
agency action (or lack thereof) has been a recurring
issue
in
this
Court’s
administrative
law
jurisprudence. See, e.g., Baldwin v. United States, 140
S. Ct. 690, 691–95 (2020) (Thomas, J., dissenting from
denial of cert.) (discussing at length agency deference,
separation of powers, and historical practice); Loper
Bright, 603 U.S. at 415 (Thomas, J., concurring)
(“Because the judicial power requires judges to
exercise their independent judgment, the deference
that Chevron requires contravenes Article III’s
mandate.”). This Court attempted to finally put that
issue to rest last year in Loper Bright. See 603 U.S. at
412. The fact that less than a year later the Fourth
Circuit deferred on an issue that, under Loper Bright,
categorically belongs to the court, shows that there
must be some confusion in the lower courts about
agency deference and the extent of the holding in
Loper Bright.
31
This Court should grant review because Blanket
Certificates are incompatible with the Fifth
Amendment, inject uncertainty into the federal courts
and into an area of national interest, and because the
Fourth Circuit refused to even consider these issues
and instead deferred to an agency.
CONCLUSION
The Court should grant the petition for a writ of
certiorari.
Respectfully submitted,
JOY D. LLAGUNO
Counsel of Record
PHILLIP C. HOOK
MATTHEW R. MILLER
GERALD S. ATKINS
HOOK & HOOK PLLC
430 East Oakview Dr.
Suite 101
Waynesburg, PA 15370
(724) 824-3302
jllaguno@hooklaw.com
June 6, 2025
Counsel for Petitioner
APPENDIX
i
TABLE OF APPENDICES
Page
A PPEN DI X A — OR DER OF T H E
UNITED STATES COURT OF APPEALS
FOR THE FOURTH CIRCUIT, FILED
JANUARY 8, 2025 . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1a
APPENDIX B — DENIAL OF REHEARING
OF THE FEDERA L ENERGY
REGULATORY COMMISSION, FILED
APRIL 11, 2024 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2a
APPENDIX C — REJECTION OF REHEARING
AND DENIAL OF LATE INTERVENTION
OF THE FEDERA L ENERGY
REGULATORY COMMISSION, DATED
FEBRUARY 7, 2024 . . . . . . . . . . . . . . . . . . . . . . . . . . 3a
A PPEN DI X D — FI N DI NG S A N D
ORDER OF THE FEDERA L ENERGY
REGULATORY COMMISSION, DATED
JANUARY 7, 1983 . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6a
APPENDIX E — CONSTITUTIONAL AND
STATUTORY PROVISIONS INVOLVED . . . . . . 12a
1a
Appendix
A UNITED STATES
APPENDIX A — ORDER
OF THE
COURT OF APPEALS FOR THE FOURTH CIRCUIT,
FILED JANUARY 8, 2025
UNITED STATES COURT OF APPEALS
FOR THE FOURTH CIRCUIT
No. 24-1530
(CP83-76-009)
RDFS, LLC,
Petitioner,
v.
FEDERAL ENERGY REGULATORY COMMISSION,
Respondent,
COLUMBIA GAS TRANSMISSION, LLC,
Intervenor.
ORDER
Upon consideration of the submissions relative to
respondent’s motion to dismiss the appeal for lack of
jurisdiction and intervenor’s motion to reply to the motion
to dismiss, the court grants the motions.
Entered at the direction of Judge Gregory with the
concurrence of Judge Thacker and Judge Richardson.
For the Court
/s/ Nwamaka Anowi, Clerk
2a
APPENDIX B —Appendix
DENIALAOF REHEARING
OF THE FEDERAL ENERGY REGULATORY
COMMISSION, FILED APRIL 11, 2024
187 FERC ¶ 62,027
UNITED STATES OF AMERICA
FEDERAL ENERGY REGULATORY COMMISSION
Columbia Gas Transmission Corporation
Docket No. CP83-76-009
NOTICE OF DENIAL OF REHEARING BY
OPERATION OF LAW
(April 11, 2024)
Rehea r ing has been timely requested of the
Commission’s Notice issued on February 7, 2024, in this
proceeding by the Acting Secretary of the Commission’s
Office of the Secretary. Columbia Gas Transmission
Corp., 186 FERC ¶ 62,052 (2024).
In the absence of Commission action on a request
for rehearing within 30 days from the date it is filed, the
request for rehearing may be deemed to have been denied.
15 U.S.C. § 717r(a); 18 C.F.R. § 385.713(f) (2023); Allegheny
Def. Project v. FERC, 964 F.3d 1 (D.C. Cir. 2020) (en banc).
Debbie-Anne A. Reese,
Acting Secretary.
3a
Appendix C OF REHEARING
APPENDIX C — REJECTION
AND DENIAL OF LATE INTERVENTION OF
THE FEDERAL ENERGY REGULATORY
COMMISSION, DATED FEBRUARY 7, 2024
186 FERC ¶ 62,052
UNITED STATES OF AMERICA
FEDERAL ENERGY REGULATORY COMMISSION
Columbia Gas Transmission Corporation
Docket No. CP83-76-008
NOTICE REJECTING REQUEST FOR REHEARING
AND DENYING LATE INTERVENTION
(February 7, 2024)
On January 7, 1983, in Docket No. CP83-76-000,
the Commission issued a blanket certificate of public
convenience and necessity under Part 157 of the
Commission’s regulations to Columbia Gas Transmission
Corporation (Columbia).1 On January 24, 2024, RDFS,
LLC filed a request for rehearing of the Blanket
Certificate Order and a late motion to intervene in Docket
No. CP83-76-000.
Pursuant to section 19(a) of the Natural Gas Act, 2 an
aggrieved party must file a request for rehearing within
30 days after the issuance of a Commission decision, in
1. Columbia Gas Transmission Corp., 22 FERC ¶ 62,029
(1983) (delegated order) (Blanket Certificate Order).
2. 15 U.S.C. § 717r(a).
4a
Appendix C
this case no later than February 7, 1983. 3 Because the 30day rehearing deadline is statutorily based, it cannot be
waived or extended,4 and the request for rehearing filed
by RDFS, LLC must be rejected as untimely.
Additionally, the purpose of inter vening in a
Commission proceeding is to obtain party status, which
entitles the intervenor to file a request for rehearing
of any final order issued in the proceeding and to seek
judicial review of such orders. 5 As the time period to file
a request for rehearing in Docket No. CP83-76-000 has
passed, granting movant intervenor status would gain it
nothing. Accordingly, the motion to intervene is denied.
This notice constitutes final agency action. Requests
for rehearing by the Commission of this notice must be
filed within 30 days of its issuance, pursuant to section
19(a) of the Natural Gas Act, 15 U.S.C. § 717r, and section
3. The Commission’s Rules of Practice and Procedure
provide that, if a filing deadline falls on a Saturday, Sunday,
holiday, or other day when the Commission is not open for business,
the filing deadline does not end until the close of business on the
next business day. 18 C.F.R. § 385.2007(a)(2). Because the end of
the 30-day time period fell on a Sunday (February 6, 1983), the
deadline was the close of business on Monday, February 7, 1983.
4. Jordan Cove Energy Project L.P., 171 FERC ¶ 61,136, at
P 13 (2020) (“Because the 30-day rehearing deadline is a statutory
requirement, it cannot be waived or extended”); Calpine Corp.,
171 FERC ¶ 61,035, at P 6 (2020) (same).
5. See City of Orrville, Ohio v. FERC, 147 F.3d 979, 984 n.3
(D.C. Cir. 1998).
5a
Appendix C
385.713 of the Commission’s regulations, 18 C.F.R.
§ 385.713 (2023).
Debbie-Anne A. Reese,
Acting Secretary.
6a
Appendix D AND ORDER OF
APPENDIX D — FINDINGS
THE FEDERAL ENERGY REGULATORY
COMMISSION, DATED JANUARY 7, 1983
Columbia Gas Transmission Corporation
Docket No. CP83-76-000
FEDERAL ENERGY REGULATORY COMMISSION Office Director
2 2 F.E.R.C. P62 ,029; 1983 FERC LEXIS 1099
Findings and Order After Statutory Hearing Issuing
Certificate of Public Convenience and Necessity
Authorizing Routine Activities and Permitting
and Approving Abandonment
January 7, 1983
CORE TERMS: certificate, abandonment, authorization,
public convenience, Natural Gas Act, blanket, notice,
regulations, budget-type, permission, abandon, time to
time, jurisdictional, conditioned, thereunder, authorize,
effective, surrender, routine, protest, storage
PANEL: [**1]
Kenneth A. Williams, Director, Office of Pipeline and
Producer Regulation.
OPINION: [*63,052]
7a
Appendix D
On November 9, 1982, Columbia Gas Transmission
Corporation (Applicant), n l filed in Docket No. CP83-76000 an application, as supplemented December 1, 1982,
pursuant to Section 7 of the Natural Gas Act to obtain
a blanket certificate of public convenience and necessity
authorizing certain routine activities and permission and
approval to abandon certain service and facilities specified
in Subpart F of Part 157 of the Commission’s Regulations,
as more fully set forth in the application.
n l Applicant, a Delaware corporation having its
principal place of business in Charleston, West Virginia, is
a “natural-gas company” within the meaning of the Natural
Gas Act as heretofore found by order issued March 10,
1971, in Docket No. CP71-132 (45 FPC 398). [*63,053]
Order No. 234 [FERC Statutes and Regulations
P30,368], established a blanket certificate and abandonment
program which permits Applicant to obtain a one-time
certificate of public convenience and necessity to authorize
a variety of jurisdictional activities and permission and
approval to abandon, which would otherwise require
separate certificate or abandonment [**2] authority in
each instance. Under the authorization issued to Applicant
herein, Applicant will be authorized to conduct many
routine activities and abandon facilities and service on
a self-implementing basis without further authorization
by the Commission. n2 For other categories of activities,
n3 which may potentially require more scrutiny and
opportunity for public participation, this authorization is
subject to the notice procedme specified in Section 157.205.
n4 Both categories of activities have been shown to serve
8a
Appendix D
the public interest, and for the reasons stated in Order No.
234, a certificate and abandonment authorization will be
issued to the Applicant to authorize the specified activities,
subject to the procedural and reporting requirements of
that order.
n2 See 18 C.F.R. § 157.203(b).
n3 See 18 C.F.R. § 157.203(c).
n4 Persons having a potential interest in such
transactions are on notice to monitor the Federal Register.
Once a deadline established under Section 157.205(d)
passes without a protest being filed, the proposed activity
is authorized under this order without further action by
the Commission.
Order No. 234 contemplated an orderly transition [**3]
from the Commission’s budget- type certificate program
(18 C.F.R. § 157.7) to the blanket certificate program.
Accordingly, Applicant states that it will surrender the
following certificates and abandonment authorization,
effective upon its acceptance of this certificate:
Docket No.
Date Issued
CP80-114
February 19, 1980
CP82-92-000 February 19, 1982
CP82-93-000 February 25, 1982
Citation
10 FERC P62,141
18 FERC P62,291
18 FERC P62,357
The Commission does not deem the surrender of the
budget-type certificate at the time of acceptance of the
blanket certificate as revocation of the budget-type
9a
Appendix D
authorization for previously undertaken projects. We
note that Applicant must still file a rmal report for the
budget-type certificate, as provided by Section 157.7 of
the Regulations.
Currently, Applicant does not perform a jurisdictional
storage service. Therefore, before Section 157.213 storage
service may be provided by Applicant, applicable rates
must be established.
Applicant also certifies that it will design, install,
inspect, test, construct, operate, replace, and maintain the
facilities authorized under this certificate in accordance
with Federal safety [**4] standards and plans for
maintenance and inspection.
For the reasons discussed in Order No. 234, and in
the Environmental Assessment issued on July 1, 1981, the
activities authorized by this certificate do not constitute
a major Federal action significantly affecting the quality
of the human environment.
After due notice by publication in the Federal Register
on December 9, 1982 (47 Fed. Reg. 55415), no petitions
to intervene, notices of intervention, or protests to the
granting of the application have been filed
At a hearing held on January 7, 1983, there was
received and made a part of the record in this proceeding
all evidence, including the application, submitted in
support of the authorization sought herein, and upon
consideration of the record,
10a
Appendix D
It is found:
(1) Applicant is able and willing properly to do
the acts and to perform the service proposed and to
conform to the provisions of the Natural Gas Act and the
requirements, rules, and regulations of the Commission
thereunder.
(2) The construction, acquisition, and operation of
facilities and the transportation and sale of natural gas
are required by the public convenience and necessity and
a certificate therefor should [**5] be issued as hereinafter
ordered and conditioned.
(3) The abandonment proposed by Applicant is
permitted by the public convenience and necessity and
should be approved as hereinafter ordered.
Pursuant to the authority delegated by 18 C.F.R.
375.307, it is ordered:
(A) Upon the terms and conditions of this order, a
certificate of public convenience and necessity is issued
authorizing Applicant to perform the activities specified
in Subpart F of Part 157 of the Commission’s Regulations,
as amended from time to time.
(B) Upon the terms and conditions of this order,
permission for and approval of the abandonment by
Applicant of service and facilities specified in Subpart F
of Part 157 of the Commission’s Regulations, as amended
from time to time, are granted.
11a
Appendix D
(C) The certificate issued by paragraph (A) above,
the abandonment authorized by paragraph (B) above,
and the rights granted thereunder are conditioned upon
Applicant’s compliance with all applicable Commission
[*63,054] Regulations under the Natural Gas Act and
particularly Section 157.206 and paragraphs (a) and (e)
of Section 157.20 of the such Regulations.
(D) The construction authority included in the
certificates issued in Docket [**6] Nos. CP80-l l 4, CP8292-000, and in CP82-93-000, and abandonment authority
in Docket No. CP82-93-000 are hereby terminated
effective upon the date of Applicant’s acceptance of this
certificate.
12a
E
APPENDIX E —Appendix
CONSTITUTIONAL
AND
STATUTORY PROVISIONS INVOLVED
1.
U.S. Const. Amend. V provides:
No person shall be held to answer for a capital, or
otherwise infamous crime, unless on a presentment or
indictment of a Grand Jury, except in cases arising in
the land or naval forces, or in the Militia, when in actual
service in time of War or public danger; nor shall any
person be subject for the same offence to be twice put
in jeopardy of life or limb; nor shall be compelled in any
criminal case to be a witness against himself, nor be
deprived of life, liberty, or property, without due process
of law; nor shall private property be taken for public use,
without just compensation.
2.
15 U.S.C. § 717f provides:
(a) Extension or improvement of facilities on
order of court; notice and hearing
Whenever the Commission, after notice and opportunity
for hearing, finds such action necessary or desirable in
the public interest, it may by order direct a natural-gas
company to extend or improve its transportation facilities,
to establish physical connection of its transportation
facilities with the facilities of, and sell natural gas to, any
person or municipality engaged or legally authorized to
engage in the local distribution of natural or artificial
gas to the public, and for such purpose to extend its
transportation facilities to communities immediately
adjacent to such facilities or to territory served by such
natural-gas company, if the Commission finds that no
13a
Appendix E
undue burden will be placed upon such natural-gas
company thereby: Provided, That the Commission
shall have no authority to compel the enlargement of
transportation facilities for such purposes, or to compel
such natural-gas company to establish physical connection
or sell natural gas when to do so would impair its ability
to render adequate service to its customers.
(b) Abandonment of facilities or services; approval
of Commission
No natural-gas company shall abandon all or any portion of
its facilities subject to the jurisdiction of the Commission,
or any service rendered by means of such facilities,
without the permission and approval of the Commission
first had and obtained, after due hearing, and a finding by
the Commission that the available supply of natural gas
is depleted to the extent that the continuance of service
is unwarranted, or that the present or future public
convenience or necessity permit such abandonment.
(c)
Certificate of public convenience and necessity
(1)(A) No natural-gas company or person which
will be a natural-gas company upon completion of
any proposed construction or extension shall engage
in the transportation or sale of natural gas, subject
to the jurisdiction of the Commission, or undertake
the construction or extension of any facilities
therefor, or acquire or operate any such facilities
or extensions thereof, unless there is in force with
respect to such natural-gas company a certificate
14a
Appendix E
of public convenience and necessity issued by the
Commission authorizing such acts or operations:
Provided, however, That if any such natural-gas
company or predecessor in interest was bona fide
engaged in transportation or sale of natural gas,
subject to the jurisdiction of the Commission, on
February 7, 1942, over the route or routes or within
the area for which application is made and has so
operated since that time, the Commission shall
issue such certificate without requiring further
proof that public convenience and necessity will
be served by such operation, and without further
proceedings, if application for such certificate is
made to the Commission within ninety days after
February 7, 1942. Pending the determination of any
such application, the continuance of such operation
shall be lawful.
(B) In all other cases the Commission shall set
the matter for hearing and shall give such reasonable
notice of the hearing thereon to all interested persons
as in its judgment may be necessary under rules and
regulations to be prescribed by the Commission;
and the application shall be decided in accordance
with the procedure provided in subsection (e) of
this section and such certificate shall be issued or
denied accordingly: Provided, however, That the
Commission may issue a temporary certificate
in cases of emergency, to assure maintenance of
adequate service or to serve particular customers,
without notice or hearing, pending the determination
of an application for a certificate, and may by
15a
Appendix E
regulation exempt from the requirements of this
section temporary acts or operations for which the
issuance of a certificate will not be required in the
public interest.
(2) The Commission may issue a certificate
of public convenience and necessity to a naturalgas company for the transportation in interstate
commerce of natural gas used by any person for one
or more high-priority uses, as defined, by rule, by the
Commission, in the case of—
(A) natural gas sold by the producer to such
person; and
(B)
natural gas produced by such person.
(d) Application for certificate of public convenience
and necessity
Application for certificates shall be made in writing to
the Commission, be verified under oath, and shall be in
such form, contain such information, and notice thereof
shall be served upon such interested parties and in such
manner as the Commission shall, by regulation, require.
(e) Granting of certificate of public convenience
and necessity
Except in the cases governed by the provisos contained
in subsection (c)(1) of this section, a certificate shall be
issued to any qualified applicant therefor, authorizing
16a
Appendix E
the whole or any part of the operation, sale, service,
construction, extension, or acquisition covered by the
application, if it is found that the applicant is able and
willing properly to do the acts and to perform the service
proposed and to conform to the provisions of this chapter
and the requirements, rules, and regulations of the
Commission thereunder, and that the proposed service,
sale, operation, construction, extension, or acquisition,
to the extent authorized by the certificate, is or will be
required by the present or future public convenience and
necessity; otherwise such application shall be denied. The
Commission shall have the power to attach to the issuance
of the certificate and to the exercise of the rights granted
thereunder such reasonable terms and conditions as the
public convenience and necessity may require.
(f) Determination of service area; jurisdiction of
transportation to ultimate consumers
(1) The Commission, after a hearing had upon
its own motion or upon application, may determine
the service area to which each authorization under
this section is to be limited. Within such service area
as determined by the Commission a natural-gas
company may enlarge or extend its facilities for the
purpose of supplying increased market demands in
such service area without further authorization; and
(2) If the Commission has determined a service
area pursuant to this subsection, transportation
to ultimate consumers in such service area by the
holder of such service area determination, even if
17a
Appendix E
across State lines, shall be subject to the exclusive
jurisdiction of the State commission in the State in
which the gas is consumed. This section shall not
apply to the transportation of natural gas to another
natural gas company.
(g) Certificate of public convenience and necessity
for service of area already being served
Nothing contained in this section shall be construed as
a limitation upon the power of the Commission to grant
certificates of public convenience and necessity for service
of an area already being served by another natural-gas
company.
(h) Right of eminent domain for construction of
pipelines, etc.
When any holder of a certificate of public convenience
and necessity cannot acquire by contract, or is unable to
agree with the owner of property to the compensation
to be paid for, the necessary right-of-way to construct,
operate, and maintain a pipe line or pipe lines for the
transportation of natural gas, and the necessary land or
other property, in addition to right-of-way, for the location
of compressor stations, pressure apparatus, or other
stations or equipment necessary to the proper operation of
such pipe line or pipe lines, it may acquire the same by the
exercise of the right of eminent domain in the district court
of the United States for the district in which such property
may be located, or in the State courts. The practice and
procedure in any action or proceeding for that purpose
in the district court of the United States shall conform
18a
Appendix E
as nearly as may be with the practice and procedure in
similar action or proceeding in the courts of the State
where the property is situated: Provided, That the United
States district courts shall only have jurisdiction of cases
when the amount claimed by the owner of the property to
be condemned exceeds $3,000.
3.
15 U.S.C. § 717r provides:
(a)
Application for rehearing; time
Any person, State, municipality, or State commission
aggrieved by an order issued by the Commission in a
proceeding under this chapter to which such person,
State, municipality, or State commission is a party may
apply for a rehearing within thirty days after the issuance
of such order. The application for rehearing shall set
forth specifically the ground or grounds upon which such
application is based. Upon such application the Commission
shall have power to grant or deny rehearing or to abrogate
or modify its order without further hearing. Unless the
Commission acts upon the application for rehearing
within thirty days after it is filed, such application may
be deemed to have been denied. No proceeding to review
any order of the Commission shall be brought by any
person unless such person shall have made application to
the Commission for a rehearing thereon. Until the record
in a proceeding shall have been filed in a court of appeals,
as provided in subsection (b), the Commission may at any
time, upon reasonable notice and in such manner as it shall
deem proper, modify or set aside, in whole or in part, any
finding or order made or issued by it under the provisions
of this chapter.
19a
Appendix E
(b)
Review of Commission order
Any party to a proceeding under this chapter
aggrieved by an order issued by the Commission in such
proceeding may obtain a review of such order in the court
of appeals of the United States for any circuit wherein the
natural-gas company to which the order relates is located
or has its principal place of business, or in the United
States Court of Appeals for the District of Columbia,
by filing in such court, within sixty days after the order
of the Commission upon the application for rehearing, a
written petition praying that the order of the Commission
be modified or set aside in whole or in part. A copy of such
petition shall forthwith be transmitted by the clerk of the
court to any member of the Commission and thereupon
the Commission shall file with the court the record upon
which the order complained of was entered, as provided
in section 2112 of Title 28. Upon the filing of such petition
such court shall have jurisdiction, which upon the filing
of the record with it shall be exclusive, to affirm, modify,
or set aside such order in whole or in part. No objection
to the order of the Commission shall be considered by
the court unless such objection shall have been urged
before the Commission in the application for rehearing
unless there is reasonable ground for failure so to do. The
finding of the Commission as to the facts, if supported by
substantial evidence, shall be conclusive. If any party shall
apply to the court for leave to adduce additional evidence,
and shall show to the satisfaction of the court that such
additional evidence is material and that there were
reasonable grounds for failure to adduce such evidence
in the proceedings before the Commission, the court may
order such additional evidence to be taken before the
20a
Appendix E
Commission and to be adduced upon the hearing in such
manner and upon such terms and conditions as to the
court may seem proper. The Commission may modify its
findings as to the facts by reason of the additional evidence
so taken, and it shall file with the court such modified or
new findings, which is supported by substantial evidence,
shall be conclusive, and its recommendation, if any, for the
modification or setting aside of the original order. The
judgment and decree of the court, affirming, modifying,
or setting aside, in whole or in part, any such order of
the Commission, shall be final, subject to review by the
Supreme Court of the United States upon certiorari or
certification as provided in section 1254 of Title 28.
(c)
Stay of Commission order
The filing of an application for rehearing under
subsection (a) shall not, unless specifically ordered by the
Commission, operate as a stay of the Commission’s order.
The commencement of proceedings under subsection (b)
of this section shall not, unless specifically ordered by the
court, operate as a stay of the Commission’s order.
(d)
Judicial review
(1)
In general
The United States Court of Appeals for the
circuit in which a facility subject to section 717b
of this title or section 717f of this title is proposed
to be constructed, expanded, or operated shall
have original and exclusive jurisdiction over any
civil action for the review of an order or action of a
21a
Appendix E
Federal agency (other than the Commission) or State
administrative agency acting pursuant to Federal
law to issue, condition, or deny any permit, license,
concurrence, or approval (hereinafter collectively
referred to as “permit”) required under Federal
law, other than the Coastal Zone Management Act
of 1972 (16 U.S.C. 1451 et seq.).
(2)
Agency delay
The United States Court of Appeals for the
District of Columbia shall have original and exclusive
jurisdiction over any civil action for the review of
an alleged failure to act by a Federal agency (other
than the Commission) or State administrative agency
acting pursuant to Federal law to issue, condition,
or deny any permit required under Federal law,
other than the Coastal Zone Management Act of
1972 (16 U.S.C. 1451 et seq.), for a facility subject to
section 717b of this title or section 717f of this title.
The failure of an agency to take action on a permit
required under Federal law, other than the Coastal
Zone Management Act of 1972, in accordance with
the Commission schedule established pursuant
to section 717n(c) of this title shall be considered
inconsistent with Federal law for the purposes of
paragraph (3).
(3)
Court action
If the Court finds that such order or action
is inconsistent with the Federal law governing
22a
Appendix E
such permit and would prevent the construction,
expansion, or operation of the facility subject to
section 717b of this title or section 717f of this title,
the Court shall remand the proceeding to the agency
to take appropriate action consistent with the order
of the Court. If the Court remands the order or action
to the Federal or State agency, the Court shall set
a reasonable schedule and deadline for the agency
to act on remand.
(4)
Commission action
For any action described in this subsection, the
Commission shall file with the Court the consolidated
record of such order or action to which the appeal
hereunder relates.
(5)
Expedited review
The Court shall set any action brought under this
subsection for expedited consideration.
4.
18 C.F.R. § 157.201 provides:
(a) Scope. This subpart establishes a procedure
whereby an interstate pipeline may obtain a blanket
certificate authorizing certain construction and operation
of facilities and certain certificate amendments and
abandonment under section 7 of the Natural Gas Act.
(b) Who may apply. This procedure is only applicable
to interstate pipelines.
23a
Appendix E
(c) Cross-reference. The procedures applicable to
transportation by interstate pipelines under blanket
certificates are set forth in subpart G of part 284 of this
chapter.
(d) Availability of case-specific certificates. Nothing
in this subpart shall preclude an interstate pipeline
from proceeding under any other provision of the
Commission’s regulations to obtain Commission approval
of abandonments or a temporary or permanent certificate
of public convenience and necessity.
5.
18 C.F.R. § 157.203 provides:
(a) Effect. A blanket certificate issued pursuant
to this subpart authorizes the certificate holder, in
accordance with the provisions of this subpart, to engage
in any of the activities specified in § 157.208 through
§ 157.218 (as may be amended from time to time).
(b) Automatic authorization. A blanket certificate
issued pursuant to this subpart authorizes the certificate
holder to engage in transactions described in § 157.208(a),
§ 157.209(a), § 157.211(a)(1), § 157.213(a), § 157.215,
§ 157.216(a), or § 157.218 without further Commission
approval.
(c) Prior notice required. A blanket certificate
issued pursuant to this subpart authorizes the certificate
holder to engage in activities described in § 157.208(b),
§ 157.210, § 157.211(a)(2), § 157.212, § 157.213(b), § 157.214,
or § 157.216(b), if the requirements of § 157.205 have been
fulfilled.
24a
Appendix E
(d)
Landowner notification.
(1) Except as identified in paragraph (d)(3) of
this section, no activity described in paragraph (b) of
this section is authorized unless the company makes
a good faith effort to notify, in writing all affected
landowners, as defined in § 157.6(d)(2), at least 45
days prior to commencing construction or at the
time it initiates easement negotiations, whichever
is earlier. A landowner may waive the 45–day prior
notice requirement in writing as long as the notice
has been provided. For activity required to restore
service in an emergency, the 45–day prior notice
period is satisfied in the event a company obtains all
necessary easements. The notification shall include
at least:
(i) A brief description of the facilities to
be constructed or replaced and the effect the
construction activity will have on the landowner’s
property;
(ii) The name and phone number of a
company representative who is knowledgeable about
the project;
(i i i) A de sc r ipt ion of t he compa ny ’s
environmental complaint resolution procedure that
must:
(A) Provide landowners with clear and
simple directions for identifying and resolving
their environmental mitigation problems and
25a
Appendix E
concerns during construction of the project and
restoration of the right-of way;
(B) Provide a local or toll-free phone
number and a name of a specific person
to be contacted by landow ners and w ith
responsibility for responding to landowner
problems and concerns, and who will indicate
when a landowner should expect a response;
(C) Instruct landowners that if they are
not satisfied with the response, they may call
the company’s Hotline; and
(D) Instruct landowners that, if they
are still not satisfied with the response, they
may contact the Commission’s Landowner
Helpline at the current telephone number and
email address, which is to be provided in the
notification.
(2) For activities described in paragraph (c)
of this section, the company shall make a good faith
effort to notify in writing all affected landowners, as
defined in § 157.6(d)(2), within at least three business
days following the date that a docket number is
assigned to the application or at the time it initiates
easement negotiations, whichever is earlier. The
notice should include at least:
(i) A brief description of the company and
the proposed project, including the facilities to be
26a
Appendix E
constructed or replaced and the location (including
a general location map), the purpose, and the timing
of the project and the effect the construction activity
will have on the landowner’s property;
(ii) A general description of what the
company will need from the landowner if the project
is approved, and how the landowner may contact the
company, including a local or toll-free phone number
and a name of a specific person to contact who is
knowledgeable about the project;
(iii) The docket number (if assigned) for the
company’s application;
(iv) A general description of the blanket
certificate program and procedures, as posted
on the Commission’s Web site at the time the
landowner notification is prepared, and the link to
the information on the Commission’s Web site;
(v) A brief summary of the rights the
landowner has in Commission proceedings and in
proceedings under the relevant eminent domain
rules; and
(vi) The following paragraph: This project is
being proposed under the prior notice requirements
of the blanket certificate program administered
by the Federal Energy Regulatory Commission.
Under the Commission’s regulations, you have the
right to protest this project within 60 days of the
27a
Appendix E
date the Commission issues a notice of the pipeline’s
filing. If you file a protest, you should include the
docket number listed in this letter and provide
the specific reasons for your protest. The protest
should be mailed to the Secretary of the Federal
Energy Regulatory Commission, 888 First St., NE.,
Room 1A, Washington, DC 20426. A copy of the
protest should be mailed to the pipeline at [pipeline
address]. If you have any questions concerning these
procedures you can call the Commission’s Office of
External Affairs at (202) 208–1088; and
(vii) The description of the company’s
environmental complaint resolution procedure as
described in paragraph (d)(1)(iii) of this section.
(3)
Exceptions.
(i) No landowner notice is required for
replacements which would have been done under
§ 2.55 of this chapter but for the fact that the
replacement facilities are not of the same capacity
as long as they meet the location requirements of
§ 2.55(b)(1)(ii) of this chapter and do not cause any
ground disturbance; or any replacement done for
safety, DOT compliance, environmental, or unplanned
maintenance reasons that are not foreseen and that
require immediate attention by the certificate holder.
(ii) No landowner notice is required for
abandonments which involve only the sale or transfer
of the facilities, and the easement will continue to be
used for transportation of natural gas.
28a
Appendix E
(iii) No landowner notice is required if
there is only one landowner and that landowner has
requested the service or facilities.
(iv) No landowner notice is required for
activities that do not involve ground disturbance or
changes to operational air and noise emissions.
(4) If paragraphs (d)(1) or (d)(2) of this section
require an applicant to reveal Critical Energy
Infrastructure Information (CEII), as defined
by § 388.113(c) of this chapter, to any person, the
applicant shall follow the procedures set out in
§ 157.10(d).
6.
18 C.F.R. § 157.208 provides, in relevant part:
(a) Automatic authorization. If the project cost does
not exceed the cost limitations set forth in column 1 of
table 1 to paragraph (d) of this section, or if the project
is required to restore service in an emergency, the
certificate holder is authorized to make miscellaneous
rearrangements of any facility, or acquire, construct,
replace, or operate any eligible facility. The certificate
holder shall not segment projects in order to meet the cost
limitations set forth in column 1 of table 1 to paragraph (d).
(b) Prior notice. If the project cost is greater than
the amount specified in column 1 of table 1 to paragraph
(d) of this section, but less than the amount specified in
column 2 of table 1 to paragraph (d), the certificate holder
is authorized to make miscellaneous rearrangements of
29a
Appendix E
any facility, or acquire, construct, replace, or operate any
eligible facility. The certificate holder shall not segment
projects in order to meet the cost limitations set forth in
column 2 of table 1 to paragraph (d).
(c) Cont ents of request . In add ition t o the
requirements of § 157.205(b), requests filed for activities
described under paragraph (b) of this section shall contain:
(1) A description of the purpose of the proposed
facilities including their relationship to other existing
or planned facilities;
(2) A detailed description of the proposed
facilities specifying length, diameter, wall thickness
and maximum operating pressure for pipeline;
and for compressors, the size, type, and number of
compressor units, horsepower required, horsepower
existing and proposed, volume of fuel gas, suction and
discharge pressure and compression ratio;
(3) A USGS 7 ½ minute series (scale 1:24000)
topographic map (or map of equivalent or greater
detail, as appropriate) showing the location of the
proposed facilities, and indicating the location of any
sensitive environmental areas within one-quarter
mile of project-related construction activities;
(4) A map showing the relationship of the
proposed facilities to the applicant’s existing
facilities;
30a
Appendix E
(5) A f low diagram or comparative study
showing daily design capacity, daily maximum
capacity and operating pressures with and without
the proposed facilities for that portion of the
certificate holder’s system affected by the proposal;
(6) The estimated cost and method of financing
the proposed facilities;
(7) A statement explaining how the public
convenience and necessity requires the approval of
the project;
(8)
For acquisitions of facilities:
(i) A statement referencing the date of
issuance, docket number and title of the proceeding
for any certificate issued by the Commission
authorizing the facilities proposed to be acquired;
and
(ii) The amounts recorded in the accounts
of the vendor (seller or lessor) that apply to
the facilities proposed to be acquired and the
accumulated provisions for depreciation, depletion,
and amortization;
(9) A concise analysis discussing the relevant
issues outlined in § 380.12 of this chapter. The
analysis must identify the existing environmental
conditions and the expected significant impacts that
the proposed action, including proposed mitigation
31a
Appendix E
measures, will cause to the quality of the human
environment, including impact expected to occur to
sensitive environmental areas. When compressor
facilities are proposed, the analysis must also
describe how the proposed action will be made to
comply with applicable State Implementation Plans
developed under the Clean Air Act. The analysis
must also include a description of the contacts made,
reports produced, and results of consultations which
took place to ensure compliance with the Endangered
Species Act, National Historic Preservation Act
and the Coastal Zone Management Act. Include
a copy of the agreements received for compliance
with the Endangered Species Act, National Historic
Preservation Act, and Coastal Zone Management
Act, or if no written concurrence is issued, a
description of how the agency relayed its opinion
to the company. Describe how drilling for wells or
horizontal direction drilling would be designed to
meet the goal of limiting the perceived noise at NSAs
to an Ldn of 55 dBA or what mitigation would be
offered to landowners.
(10) A commitment to having the Environmental
Inspector’s report filed every week.
This is a copy of a public record, reproduced as it was published. It is not legal advice, and it may not be the version a court would rely on. Check the official source before you cite it.