Respondents Brief — Ohio, ex rel. Dave Yost, Attorney General of Ohio, Petitioner v. Rover Pipeline, LLC, et al.
Supreme Court briefJun 30, 2025
Ask Donna
What actually matters in this document.
Text
No. 24-1120
In the Supreme Court of the United States
OHIO, EX REL. DAVE YOST,
ATTORNEY GENERAL OF OHIO,
Petitioner,
v.
ROVER PIPELINE, LLC, ET AL.,
Respondents.
ON PETITION FOR A WRIT OF CERTIORARI
TO THE COURT OF APPEALS OF OHIO, STARK COUNTY
BRIEF IN OPPOSITION
BENJAMIN C. SASSÉ
TUCKER ELLIS LLP
950 Main Ave.
Suite 1100
Cleveland, OH 44113
(216) 696-3213
benjamin.sasse
@tuckerellis.com
Counsel for Respondent
Pretec Directional
Drilling, LLC
WILLIAM S. SCHERMAN
Counsel of Record
JASON J. FLEISCHER
MATTHEW X. ETCHEMENDY
VINSON & ELKINS LLP
2200 Pennsylvania Ave.,
NW, Suite 500 West
Washington, DC 20037
(202) 639-6550
wscherman@velaw.com
Counsel for Respondent
Rover Pipeline, LLC
QUESTIONS PRESENTED
1. Section 401(a) of the Clean Water Act provides
that if a State “fails or refuses to act on a request” for a
water-quality certification “within a reasonable period
of time (which shall not exceed one year) after receipt of
such request, the certification requirement[] * * * shall
be waived.” 33 U.S.C. § 1341(a)(1). The first question
presented is whether § 401’s one-year deadline for state
action begins to run when a State receives a request for
a water-quality certification, or only begins to run once
the State deems the request “complete.”
2. Section 401(d) of the Clean Water Act provides
that States “shall” impose any “condition[s]” on a waterquality certification that are “necessary to assure” that
the applicant “will comply” with “any * * * appropriate
requirement of State law.” 33 U.S.C. § 1341(d). For its
part, the Natural Gas Act preempts state regulation of
interstate natural gas pipeline construction, with a narrow exception that preserves “the rights of States under” the Clean Water Act. 15 U.S.C. § 717b(d). The second question presented is whether Ohio, having waived
its ability to issue a water-quality certification for
Rover’s interstate pipeline project, could nonetheless initiate subsequent litigation to enforce state water-quality laws on which it could have conditioned, but failed
to condition, a timely § 401 certification.
(I)
II
RULE 29.6 STATEMENT
Respondent Rover Pipeline, LLC (“Rover”) is a Delaware limited liability company that is owned 65% by ET
Rover Pipeline LLC, 20% by Traverse Rover LLC, and
15% by Traverse Rover II LLC. ET Rover Pipeline LLC
is owned 50.1% by Energy Transfer Interstate Holdings,
LLC, a wholly owned subsidiary of Energy Transfer LP,
and 49.9% by BCP Renaissance L.L.C. Other than Energy Transfer LP (NYSE: ET) and Blackstone Inc.
(NYSE: BX), no publicly held company owns 10% or
more of Rover’s stock.
Respondent Pretec Directional Drilling, LLC is a
Florida limited liability company that is owned 100% by
MP Drilling Holdings, LLC, a Florida limited liability
company. MP Drilling Holdings, LLC is owned 100% by
Precision Pipeline, LLC, a Wisconsin limited liability
company. Precision Pipeline, LLC is 100% owned by
Precision Acquisition, LLC, a Wisconsin limited liability
company. Precision Acquisition, LLC is 100% owned by
MasTec, Inc., a Florida corporation which is publicly
traded on the New York Stock Exchange (NYSE: MTZ).
III
TABLE OF CONTENTS
Page
Questions Presented ..................................................... I
Rule 29.6 Statement ................................................... II
Table of Authorities ..................................................... V
Introduction ................................................................. 1
Statement .................................................................... 4
I.
Legal Background ................................................. 4
A. The Natural Gas Act ...................................... 4
B. The Clean Water Act ...................................... 5
II. Factual and Procedural Background.................. 10
Reasons for Denying the Petition ............................. 15
I.
There Is No Split of Authority Among Lower
Courts. ................................................................. 15
II. This Case Does Not Present Important or
Recurring Questions, and Is a Poor Vehicle. ..... 19
A. The First Question Presented Does Not
Warrant Review. .......................................... 20
B. The Second Question Presented Does
Not Warrant Review. ................................... 25
C. This Case Also Presents Threshold
Jurisdictional Issues That Further Cut
Against Review. ............................................ 28
III. The Decision Below Is Correct............................ 30
A. The Ohio Supreme Court Correctly
Resolved the First Question Presented. ...... 30
IV
B. The Fifth District Correctly Resolved the
Second Question Presented. ........................ 33
Conclusion.................................................................. 36
V
TABLE OF AUTHORITIES
Cases:
Page(s)
Adams v. Robertson,
520 U.S. 83 (1997) .................................................... 24
AES Sparrows Point LNG, LLC v. Wilson,
589 F.3d 721 (4th Cir. 2009) ............................... 15-17
California Trout v. Hoopa Valley Tribe,
140 S. Ct. 650 (2019) .................................................. 8
Chem. Mfrs. Ass’n v. NRDC,
470 U.S. 116 (1985) .................................................... 8
City of Tacoma v. Taxpayers of Tacoma,
357 U.S. 320 (1958) .................................................. 28
Del. Riverkeeper Network v. Sec’y Pa. Dept. of
Env’t Prot., 833 F.3d 360 (3d Cir. 2016) ............. 4-5, 8
EEOC v. Abercrombie & Fitch Stores, Inc.,
575 U.S. 768 (2015) .................................................. 31
Hoopa Valley Tribe v. FERC,
913 F.3d 1099 (D.C. Cir. 2019) ............................ 8, 26
Huber v. N.J. Dep’t of Env’t Prot.,
131 S. Ct. 1308 (2011) .............................................. 25
In re Clean Water Act Rulemaking,
568 F. Supp. 3d 1013 (N.D. Cal. 2021) ...................... 8
In re Clean Water Act Rulemaking,
60 F.4th 583 (9th Cir. 2023) ...................................... 9
Islander E. Pipeline Co. v. Conn. Dept. of Env’t
Prot., 482 F.3d 79 (2d Cir. 2006) ............................ 4-5
Johnson v. California,
541 U.S. 428 (2004) .................................................. 24
VI
Cases—Continued:
Page(s)
Louisiana v. American Rivers,
142 S. Ct. 1347 (2022) ................................................ 9
Maslenjak v. United States,
137 S. Ct. 1918 (2017) .............................................. 25
Monsalvo v. Bondi,
145 S. Ct. 1232 (2025) .............................................. 30
N.C. Dep’t of Env’t Quality v. FERC,
3 F.4th 655 (4th Cir. 2021) ...................................... 20
N.Y. State Dep’t of Env’t Conservation v. FERC,
884 F.3d 450 (2d Cir. 2018) ................ 8, 15, 18, 20-21
Nat’l Ass’n of Mfrs. v. Dep’t of Def.,
583 U.S. 109 (2018) .................................................. 33
PennEast Pipeline Co., LLC v. New Jersey,
141 S. Ct. 2244 (2021) .............................................. 30
Pennsylvania v. Wheeling & Belmont Bridge Co.,
54 U.S. 518 (1851) ...................................................... 6
PUD No. 1 of Jefferson Cnty. v. Wash. Dept. of
Ecology, 511 U.S. 700 (1994) ................................... 27
S.D. Warren Co. v. Me. Bd. of Env’t Prot.,
547 U.S. 370 (2006) ................................................. 5-7
Schneidewind v. ANR Pipeline Co.,
485 U.S. 293 (1988) .................................................... 4
Seven Cnty. Infrastructure Coal. v. Eagle Cnty.,
Colo., 145 S. Ct. 1497 (2025) ................................... 35
Sierra Club v. State Water Control Bd.,
898 F.3d 383 (4th Cir. 2018) ...................................... 7
Sosa v. Alvarez-Machain,
542 U.S. 692 (2004) .................................................. 32
VII
Cases—Continued:
Page(s)
Sperry v. State of Fla. ex rel. Fla. Bar,
373 U.S. 379 (1963) .................................................... 6
State v. Davis,
894 N.E.2d 1221(Ohio 2008).................................... 25
Street v. New York,
394 U.S. 576 (1969) .................................................. 23
Turkiye Halk Bankasi A.S. v. United States,
143 S. Ct. 940 (2023) ................................................ 31
Williams Nat. Gas Co. v. Oklahoma City,
890 F.2d 255 (10th Cir. 1989) .................................. 29
Statutes:
15 U.S.C. § 717b(d) .................................................. 5, 33
15 U.S.C. § 717b(d)(3) .................................................. 33
15 U.S.C. § 717f(e) ..................................................... 4, 8
15 U.S.C. § 717n(b)(1).................................................... 4
15 U.S.C. § 717o ............................................................. 4
15 U.S.C. § 717r(b)................................................... 5, 28
15 U.S.C. § 717s(a) ........................................................ 4
15 U.S.C. § 717t-1 .......................................................... 4
20 U.S.C. § 6364(f)(4)................................................... 32
22 U.S.C. § 8753(d) ...................................................... 32
33 U.S.C. § 1251(d) ........................................................ 8
33 U.S.C. § 1311 ......................................................... 5-6
33 U.S.C. § 1313 ............................................................ 6
33 U.S.C. § 1341(a) .................................................. 6, 24
33 U.S.C. § 1341(a)(1) ..................................... 6-7, 21, 30
VIII
Statutes—Continued:
Page(s)
33 U.S.C. § 1341(d) ........................................................ 7
33 U.S.C. § 1342(a) ........................................................ 6
33 U.S.C. § 1344 .......................................................... 16
33 U.S.C. § 1344(a) ...................................................... 32
42 U.S.C. § 505(f)(1)..................................................... 32
42 U.S.C. § 7651g(c)(2) ................................................ 32
42 U.S.C. § 7661b(c)..................................................... 32
Ohio Rev. Code § 6111.30(C) ....................................... 21
Ohio Rev. Code § 6111.30(G) ....................................... 24
Ohio Rev. Code § 6111.30(D). ...................................... 21
Regulations:
33 C.F.R. § 325.2(b)(1)(ii) (2008) ............................ 16-17
40 C.F.R. § 121.5(b) (2020) .......................................... 22
40 C.F.R. § 121.5(c) (2020) .......................................... 22
Statutory History:
H.R. Rep. 91-940 (1970) (Conf.) .................................... 8
Rules:
Ohio Sup. Ct. Rep. Op. R. 4.1 ...................................... 25
S. Ct. R. 14.1(g)(1) .................................................. 23-24
Administrative Materials:
Clean Water Act Section 401 Certification Rule,
85 Fed. Reg. 42,210 (July 13, 2020) ..... 8-9, 20, 22, 24
IX
Administrative Materials—Continued:
Page(s)
Clean Water Act Section 401 Water Quality
Certification Improvement Rule, 88 Fed.
Reg. 66,558 (Sept. 27, 2023) ................................ 9, 22
Comments of Louisiana et al., Docket No. EPAHQ-OW-2022-0128-0123 (Aug. 8, 2022),
https://perma.cc/N33H-S7CW ................................. 32
Millennium Pipeline Co., L.L.C.,
161 FERC ¶ 61,186 (2017) ....................................... 18
Other Authorities:
Black’s Law Dictionary (4th ed. 1968) ........................ 30
Letter from Stephen A. Ryba, Chief, Regulatory
Branch, Army Corps, to Ron Happach, CEO,
Millenium Pipeline Company, LLC (Oct. 16,
2017), FERC Accession No. 20171026-5163
attach. 2, https://tinyurl.com/4xuz925j .............. 18-19
Letter from Terry Turpin, Director, Off. of Energy
Projects, FERC, to Kelly Allen, Regul. Affairs
Dep’t Manager, Rover Pipeline, LLC (Sept. 18,
2017), FERC Accession No. 20170918-3075,
https://tinyurl.com/ydr2tf6v .................................... 11
Memorandum from Peggy S. Browne, Acting
Assistant Administrator, Off. of Water, EPA
(May 21, 2025), https://perma.cc/KC9M-WU2F........ 9
Mot. to Hold Matter in Abeyance, Louisiana v.
EPA, No. 23-cv-1714 (W.D. La. Feb. 7, 2025),
ECF No. 154 ............................................................... 9
Webster’s Third New International Dictionary
(1971) ........................................................................ 30
INTRODUCTION
Upon reading Ohio’s petition, an uninitiated
reader might be surprised to learn that it concerns the
regulation of an interstate natural gas pipeline—a
unique area subject to comprehensive regulation and
oversight by the Federal Energy Regulatory Commission (“FERC”), pursuant to a federal statute, the Natural Gas Act (“NGA”), that broadly preempts state environmental regulation in this field, subject only to
narrow exceptions of Congress’s own making. The petition—which is merely the latest chapter in Ohio’s
stubborn effort to undo the consequences of its own decisions—papers over that reality. So too does it ignore
the fact that Ohio easily could have avoided those consequences merely by taking timely action on permit
applications.
In early 2015, Rover sought authorization from
FERC to build an interstate natural gas pipeline running through Michigan, Ohio, Pennsylvania, and West
Virginia. Because of FERC’s comprehensive regulatory role under the NGA, any state regulation of this
interstate pipeline project would ordinarily be
preempted. However, under § 401 of the Clean Water
Act (“CWA”), Ohio had a one-year window to impose
state water-quality requirements on the project, in advance of construction. Thus, Congress gave Ohio an
option—if it wished—to jointly regulate a project that
would otherwise be subject solely to federal control.
But the State chose not to exercise that congressionally conferred option. Instead, it allowed its federally imposed one-year deadline to expire, waiving its
CWA authority. Then, following an extensive federal
environmental review, FERC approved the pipeline
(1)
2
and authorized its construction under the NGA, subject to extensive FERC-imposed environmental conditions.
The State later filed suit against Rover, asserting
violations of claimed state-law requirements that Ohio
could have, but did not, impose earlier through a
timely § 401 certification. After Ohio’s claims were
dismissed as inconsistent with the CWA and the background rule of preemption the NGA establishes for interstate pipeline construction, the State embarked on
a years-long unsuccessful series of state-court appeals.
The last of these was so ill-conceived the Ohio Supreme Court refused discretionary review. The State
now seeks this Court’s review, in a final effort to revive
the arguments the Ohio state courts soundly rejected.
This case is profoundly unworthy of this Court’s review. There is no split of authority on Ohio’s second
question presented (regarding the effect of its waiver),
and the State never contends otherwise. As for the
first question presented—regarding when the oneyear waiver clock begins under CWA § 401—the best
the State can muster is a supposed conflict with language in a 15-year-old Fourth Circuit decision that
was not even interpreting the text of § 401 itself.
There is accordingly no split of authority to address.
But even if Ohio’s assertion of a thin and stale circuit tension could be credited, the issue would still be
unworthy of review for multiple reasons. Most notably, the timing question Ohio’s petition presents,
which relates to when an application is considered “received” for purposes of beginning the one-year clock,
has subsequently been addressed administratively in
3
Environmental Protection Agency (“EPA”) rulemakings postdating the operative facts here. Ohio offers no persuasive reason for this Court to reach ten
years back in time, prior to EPA’s current (and quite
recent) rules addressing this, and adjudicate the timeliness of the State’s actions prior to those rules taking
effect. Indeed, this case is an almost uniquely bad candidate for review. If this Court’s review of the issues
Ohio raises were ever warranted (which is doubtful),
it would be in a case arising after the promulgation of
the most recent administrative rules on the subject.
In any event, the questions presented have rarely
been litigated and will rarely (if ever) be litigated in
the future, because States can easily avoid waiver under § 401 simply by taking timely action on certification requests. In an effort to make up for this lack of
practical importance, the State offers rhetoric about
purported threats to its sovereignty. But the State’s
quasi-constitutional puffery cannot withstand scrutiny. When Congress enacted the NGA in 1938, it occupied the field of interstate natural gas pipeline construction, subjecting the approval and construction of
such interstate projects to exclusive federal regulation.
And Congress would have been well within its constitutional authority to leave things there. As it happens, Congress later chose to give States a limited role
in regulating interstate natural gas pipeline construction via CWA § 401—albeit subject to § 401’s limits, including its express waiver provision. Ohio may be dissatisfied with the scope of its federally delegated statutory role in this congressionally crafted cooperativefederalism regime. But the State’s constitutional overtures are pure nonsense, intended to obscure the fact
4
that this case presents only splitless, infrequently
arising issues that States can easily avoid by diligently
acting on certification requests, and that EPA has issued subsequent rules to clarify. The petition should
be denied.
STATEMENT
I. Legal Background
A.
The Natural Gas Act
The NGA provides a “comprehensive scheme of federal regulation” for interstate natural gas transportation, including interstate natural gas pipelines.
Schneidewind v. ANR Pipeline Co., 485 U.S. 293, 300
(1988) (citation omitted); see 15 U.S.C. § 717f(e).
Pursuant to its “exclusive jurisdiction” in this field,
FERC leads a coordinated effort to review and approve
applications for the construction of such interstate
pipelines. Schneidewind, 485 U.S. at 300-301, 308; see
Islander E. Pipeline Co. v. Conn. Dept. of Env’t Prot.,
482 F.3d 79, 84 (2d Cir. 2006); 15 U.S.C. §§ 717f(e),
717n(b)(1). If FERC determines that a proposed pipeline is required by the “public convenience and necessity,” then it “shall” issue a certificate authorizing the
pipeline. Id. § 717f(e); see Del. Riverkeeper Network v.
Sec’y Pa. Dept. of Env’t Prot., 833 F.3d 360, 367 (3d Cir.
2016). The NGA empowers FERC to monitor compliance with any conditions imposed in its certificates, to
ensure continued compliance via stop-work orders and
penalties, and to impose additional conditions if unforeseen circumstances arise. See 15 U.S.C. §§ 717o,
717t-1, 717s(a). Any party “aggrieved” by a FERC order issued under the NGA “may obtain a review of
such order” in an appropriate “court of appeals of the
5
United States.” Id. § 717r(b). And “[u]pon the filing of
such petition such court shall have jurisdiction, which
upon the filing of the record with it shall be exclusive,
to affirm, modify, or set aside such order in whole or in
part.” Ibid.
A provision of the NGA known as the “savings
clause” preserves “the rights of States under” the CWA
(as well as the Coastal Zone Management Act and the
Clean Air Act). 15 U.S.C. § 717b(d). Outside of the
federally delegated “rights” referenced in the savings
clause, States have no power to regulate the
construction of interstate natural gas pipelines. That
is because the NGA “wholly preempt[s] and completely
federalize[s] the area of [interstate] natural gas
regulation,” Islander E., 482 F.3d at 90, including
“state environmental regulation of interstate natural
gas facilities,” Del. Riverkeeper, 833 F.3d at 368.
B.
The Clean Water Act
1. The CWA establishes a comprehensive framework for regulating discharges of pollutants into waters of the United States. See S.D. Warren Co. v. Me.
Bd. of Env’t Prot., 547 U.S. 370, 385 (2006). When
crafting the CWA, Congress balanced the traditional
power of States to regulate water resources with the
need for comprehensive federal policy governing water
quality, as well as long-standing principles of federal
supremacy when licensing interstate projects. The result was a scheme of “cooperative federalism” under
which States and the federal government each have
defined roles. The CWA prohibits all discharges of pollutants into navigable waters without a permit, 33
U.S.C. § 1311, and then divides between federal agen-
6
cies and the States the authority to permit certain discharges, see id. §§ 1311, 1313, 1341(a), 1342(a).
While the CWA contemplates a limited role for
States, it does not alter the basic rule that, under longfamiliar preemption principles, “[n]o State law can
hinder or obstruct the free use of a license granted under an act of Congress.” Pennsylvania v. Wheeling &
Belmont Bridge Co., 54 U.S. 518, 566 (1851); see
Sperry v. State of Fla. ex rel. Fla. Bar, 373 U.S. 379,
385 (1963) (similar). Thus, Congress recognized that,
absent federal-law provisions creating a mechanism
for States to regulate the water-quality impacts of federally permitted projects, developers could rely on “a
Federal license or permit” to “excuse * * * a violation
of [state] water quality standard[s].” S.D. Warren, 547
U.S. at 386 (citation omitted).
2. Congress enacted CWA § 401 as the sole mechanism for States to participate in regulating federally
permitted projects’ water-quality impacts. Under
§ 401, an applicant for a federal permit “to conduct any
activity” that “may result in any discharge into the
navigable waters” must seek a certification from the
“State in which the discharge * * * will originate” that
the discharge will comply with state and federal water-quality laws. 33 U.S.C. § 1341(a)(1). Without such
a certification, the federal permit cannot be granted.
Ibid. Crucially, however, Section 401 provides that, if
the State “fails or refuses to act on a request for certification, within a reasonable period of time (which
shall not exceed one year) after receipt of such request,
the certification requirements of this subsection shall
be waived with respect to such Federal application.”
Ibid.
7
A State has four options when presented with an
application for a § 401 certification: (1) grant the certification outright, (2) grant the certification with conditions, (3) deny the certification, or (4) waive its certification authority. See Pet. App. 92a; Sierra Club v.
State Water Control Bd., 898 F.3d 383, 388 (4th Cir.
2018).
If the State elects the first option (grant outright),
then § 401 is satisfied and the federal permit requested by the applicant may be granted. If the State
elects the second option (grant with conditions), then
§ 401(d) specifies that the State “shall” include the
conditions “necessary to assure” that the applicant’s
activities will comply with certain listed provisions of
the CWA “and with any other appropriate requirement of State law”; once specified, the State’s conditions then become enforceable conditions on the federal permit. 33 U.S.C. § 1341(d). If the State elects
the third option (deny), then it can block the federal
project, unless its denial is successfully challenged in
court. See 33 U.S.C. § 1341(a)(1).
This case is largely about the fourth option available to States presented with a certification request
(waiver). Section 401 makes clear that, if a State fails
to act on a certification request within “one year * * *
after receipt of such request,” then the “certification
requirements of [§ 401] shall be waived with respect to
such Federal application.” 33 U.S.C. § 1341(a)(1). The
federal permit may then be issued, allowing the project to go forward without further restriction by the
State. Section 401 therefore operates to “preserve
state authority to address” water pollution, S.D. Warren, 547 U.S. at 386, while simultaneously imposing a
8
one-year deadline to prevent States from engaging in
“dalliance or unreasonable delay” when exercising
that authority, Hoopa Valley Tribe v. FERC, 913 F.3d
1099, 1104 (D.C. Cir.) (quotation omitted), cert. denied, 140 S. Ct. 650 (2019); see H.R. Rep. 91-940, at 55
(1970) (Conf.) (waiver provision intended to ensure
that “inactivity by the State * * * will not frustrate the
Federal application”). In the event of waiver, the
State’s limited grant of federal authority to impose
conditions for the relevant project dissipates and reverts back to the federal licensing agency. See Del.
Riverkeeper, 833 F.3d at 376; 15 U.S.C. § 717f(e).
3. The EPA oversees implementation of the CWA.
See 33 U.S.C. § 1251(d); Chem. Mfrs. Ass’n v. NRDC,
470 U.S. 116, 125 (1985). EPA has issued several implementing regulations for § 401 in recent years, and
is currently contemplating another revision to its
rules.
In 2020, EPA issued its first implementing rule for
§ 401 since 1971. See Clean Water Act Section 401
Certification Rule, 85 Fed. Reg. 42,210 (July 13, 2020)
(“2020 Rule”). The 2020 Rule expressly confirmed that
the one-year clock in § 401 “starts after ‘receipt of such
request’ by the certifying authority” and not “when a
State determines that a request for certification is
‘complete.’” Id. at 42,223-24 (quoting N.Y. State Dep’t
of Env’t Conservation v. FERC, 884 F.3d 450, 455-56
(2d Cir. 2018) (“NYSDEC”)); see id. at 42,243-48 (similar). A federal district court in California vacated the
2020 Rule, but this Court stayed that vacatur, and the
Ninth Circuit later reversed the district court. In re
Clean Water Act Rulemaking, 568 F. Supp. 3d 1013
(N.D. Cal. 2021), stay granted sub nom. Louisiana v.
9
American Rivers, 142 S. Ct. 1347 (2022), rev’d and remanded, 60 F.4th 583 (9th Cir. 2023).
In 2023, EPA issued a new regulation. Clean Water Act Section 401 Water Quality Certification Improvement Rule, 88 Fed. Reg. 66,558 (Sept. 27, 2023)
(“2023 Rule”). Over the objection of various States, the
2023 Rule backtracked in certain respects from the
2020 Rule, including by suggesting that States may establish “requirements for a request for certification
that starts the reasonable period of time.” Id. at
66,577. EPA nonetheless clarified that, even under
the new rule, the one-year clock would not be tethered
to the time “when a state deems [a request for certification] ‘complete.’” Id. at 66,576.
A consortium of eleven States and three industry
groups brought suit against EPA to challenge the 2023
Rule, and that litigation is currently pending in the
U.S. District Court for the Western District of Louisiana. In February 2025, that court placed the litigation
into abeyance after EPA represented that “new EPA
leadership” was “review[ing] the rule” to confirm that
EPA’s positions “reflect the views of current Agency
leadership.” Mot. to Hold Matter in Abeyance at 1-2,
Louisiana v. EPA, No. 23-cv-1714 (W.D. La. Feb. 7,
2025), ECF No. 154. And, in May 2025, EPA published
a memorandum announcing that it “will use a forthcoming Federal Register Notice and recommendations
docket” to consider changes to the 2023 Rule. Memorandum from Peggy S. Browne at 2, Acting Assistant
Administrator, Off. of Water, EPA (May 21, 2025),
https://perma.cc/KC9M-WU2F.
10
II. Factual and Procedural Background
1. In February 2015, Rover applied to FERC for a
certificate to construct and operate a 713-mile interstate pipeline through Michigan, Ohio, Pennsylvania,
and West Virginia. See Pet. App. 4a. With input from
Ohio, FERC developed an environmental impact statement (“EIS”) that fully considered the project’s potential environmental impacts. Id. at 17a. In February
2017, FERC issued a certificate to Rover. No party
sought judicial review of FERC’s certificate order.
Pipeline construction ended in 2020 and the project
entered service the same year.
2. In November 2015, Rover submitted a request
to Ohio for a § 401 certification. Pet. App. 4a. Ohio
did not act on that request within one year. Ibid.
Instead, Ohio informed Rover of perceived
insufficiencies in its request without taking any
formal action on the application, and ultimately
demanded that Rover “resubmit its request” for a
§ 401 certification. Pet. App 105a. Rover made its
revised request for certification on February 23, 2017.
See ibid. The next day (some 15 months after Rover
had first submitted its application), Ohio “granted the
revised request * * * without ever acting on the initial
request filed” in November 2015. Ibid.; see Pet. App.
89a (“undisputed” that Ohio “failed to act on Rover’s
original certification request within one year”).
In May 2017, Ohio asked FERC to halt construction of the project based on the same concerns that
later formed the factual predicates for this case—i.e.,
alleged “inadvertent returns” during drilling and “failure[s] to adequately control storm water runoff.” Pet.
11
App. 4a.1 FERC stopped work at some construction
sites until Rover implemented various protective
measures. See ibid. For the next several months,
Rover worked with FERC and Ohio to address the
State’s concerns.
In September 2017, FERC issued a letter order
that (1) allowed Rover to resume certain construction
activities and (2) rejected Ohio’s request that Rover be
required to meet Ohio’s new permitting demands (the
“September 2017 Order”).2 See Pet. App. 4a. Ohio did
not seek judicial review of the September 2017 Order.
From the time its FERC certificate became final to
the present, Rover has been subject to FERC’s expansive enforcement authorities. FERC is currently pursuing an enforcement action against Rover with respect to the same discharges that form this lawsuit’s
factual predicate. See Pet. App. 4a, 23a.
3. Unable to convince FERC to impose additional
conditions on Rover, Ohio attempted to impose them
de facto in November 2017 by bringing state-court litigation seeking penalties and other relief. Specifically,
Ohio’s complaint against Rover and its contractor alleged various state-law violations during the project’s
construction.
1 In the pipeline industry, the phrase “inadvertent returns” re-
fers to situations in which the drill used to bore through the
ground encounters natural fissures or other features that allow
drilling fluid to reach the surface. See Pet. App. 17a, 34a.
2 Letter from Terry Turpin, Director, Off. of Energy Projects,
FERC, to Kelly Allen, Regul. Affairs Dep’t Manager, Rover
Pipeline, LLC (Sept. 18, 2017), FERC Accession No. 201709183075, https://tinyurl.com/ydr2tf6v.
12
The defendants moved to dismiss on various
grounds, including waiver under CWA § 401 and
preemption under the NGA. In March 2019, the Ohio
Stark County Court of Common Pleas dismissed the
State’s lawsuit in full, reasoning that the State waived
all of the powers it now sought to exercise through litigation. Pet. App. 96a-108a. Ohio appealed to the
Ohio Fifth District Court of Appeals, which unanimously affirmed. Pet. App. 79a-95a.
4. The State then appealed to the Ohio Supreme
Court. In its memorandum in support of jurisdiction,
Ohio argued for the first time that the one-year clock
in § 401 does not begin to run until a State deems a
certification application to be “complete.”3 The State
also argued that even if it did waive its § 401 authority, it retained power to bring claims concerning matters outside “the scope of the certification it declined
to act on.” State’s Ohio S. Ct. Br. 18 (June 19, 2020),
2020 WL 3440352. But it conceded that it could not
“use state law to stop or remediate pollution within the
3 Ohio’s arguments at earlier stages of the litigation were much
different. In opposing the motions to dismiss at the trial court,
Ohio suggested that its February 2017 certification was timely
under a so-called “revise-and-resubmit” scheme—i.e., that Ohio
had supposedly “timely issued the 401 certification, one day after
* * * Rover reapplied,” with “364 days to spare.” Ohio Trial Ct.
MTD Opp. 24-25 (Oct. 12, 2018). As the Fifth District explained,
Ohio “abandoned” that argument on appeal. Pet. App. 89a. In
lieu of arguing that its February 2017 certification was timely,
Ohio instead insisted in its Fifth District briefs that, “even if the
State waived,” its waiver “does not preclude the[] claims” that are
supposedly “outside the scope of the Section 401 certification.”
Ohio 5th Dist. Appellant Br. 1, 16 (June 13, 2019).
13
scope of the certification it declined to act on.” Ibid.
(emphasis added); accord Pet. App. 67a.
In March 2022, the Ohio Supreme Court issued its
decision. Pet. App. 61a-78a. All seven Justices agreed
that the one-year clock in § 401 begins when the request for a certification is received, rather than when
that certification is deemed “complete” by the State.
Id. at 66a (majority), 70a (Fischer, J., concurring in
part and dissenting in part). Applying that rule to
these facts, the Ohio Supreme Court “conclude[d] that
the state waived” under § 401 and thus was prohibited
from asserting any claims within the “contours of the
Section 401 certification.” Id. at 68a-69a (majority).
However, the Court remanded on grounds that, before
dismissing the suit on the basis of waiver, the lower
court would need to determine whether Ohio’s lawsuit
(1) “assert[ed] rights related to th[e] certification” (in
which case waiver would bar the State’s claims), or instead (2) asserted rights “outside the contours of the
Section 401 certification” (in which case Ohio’s waiver
would not, in the Ohio Supreme Court’s view, bar
Ohio’s claims). Id. at 69a.4
5. On remand, and with Ohio’s agreement, the trial
court allowed the defendants to file motions to dismiss
addressing issues not resolved in the prior appeal to
the Ohio Supreme Court, including whether the NGA
preempted Ohio’s claims. See Pet. App. 6a, 40a. The
4 In his partial concurrence, Justice Fischer—joined by Justices
Kennedy and DeWine—explained that there was “no reason to
remand this case” because the record was already clear that Ohio
had “waived its ability * * * to enforce any state laws regarding
any discharges resulting from the activity of constructing the
pipeline.” Pet. App. 74a, 77a.
14
defendants explained that waiver and preemption operated together to eliminate any source of authority
the State could rely upon to maintain its lawsuit. The
Ohio trial court granted the motions to dismiss. See
id. at 37a-60a.
6. The Fifth District again unanimously affirmed.
Pet. App. 2a-36a. After first expressing frustration
with “the fluctuating arguments by [Ohio] at the various stages in these proceedings,” id. at 13a, the Fifth
District explained that, “during the permitting process, states can exercise their CWA permitting authority” through conditions in a § 401 certification, id. at
25a. However, “once the state waives this authority,
state law is preempted by federal law.” Id. at 25a-26a.
In other words, the “rights of States” protected from
preemption under the NGA’s savings clause are the
same federally delegated rights under the CWA that
are waived if the State decides not to act in a timely
manner on a § 401 certification request. More particularly, in the specific context of interstate natural gas
pipeline construction, the NGA preempts any remaining state powers (e.g., the traditional sovereign authority to regulate waters within the State’s jurisdiction). See id. at 34a-35a.
7. Ohio sought discretionary review of the Fifth
District’s 2024 opinion in the Ohio Supreme Court.
The Ohio Supreme Court declined to grant review.
Pet. App. 1a.
15
REASONS FOR DENYING THE PETITION
I. There Is No Split of Authority Among Lower
Courts.
First, this case does not warrant review because
there is no split of authority. Ohio does not contend
that there is any division of authority on its second
question presented. Rather, the State’s only asserted
split concerns the first question presented. However,
the State’s asserted split is illusory.
1. The State argues that the Ohio Supreme Court’s
unanimous decision on the question of whether
Rover’s November 2015 application triggered § 401’s
one-year clock deepened a purported split between the
Second and Fourth Circuits. Compare NYSDEC, 884
F.3d at 455-456 (2d Cir. 2018), with AES Sparrows
Point LNG, LLC v. Wilson, 589 F.3d 721, 729 (4th Cir.
2009). The State admits that the Second Circuit’s decision in NYSDEC is consistent with the Ohio Supreme Court’s decision here, see Pet. 18, so it is forced
to hang its entire argument for certiorari on the
Fourth Circuit’s 15-year-old decision in AES Sparrows. Ohio characterizes the Fourth Circuit’s decision
in AES Sparrows as having held that a “valid request”
for certification is necessary to trigger the one-year
clock. Pet. 17-18.
But AES Sparrows did not supply any interpretation of § 401 itself. Instead, as Ohio concedes, the
panel found that § 401 was “ambiguous” and granted
Chevron deference to an interpretation set forth in a
regulation of the U.S. Army Corps of Engineers
(“Army Corps”). AES Sparrows, 589 F.3d at 729. Because the Fourth Circuit did no textual analysis at
16
Chevron step one and did not deliver any holding
about the meaning of § 401, there is no conflict between AES Sparrows and NYSDEC. Indeed, as Ohio
itself conceded below, AES Sparrows at most “suggested” that Ohio’s position in this case might be correct. State’s Ohio S. Ct. Juris. Memo 3 (Jan. 17, 2020),
2020 WL 422473 (emphasis added). A “suggestion”
does not make a circuit split.
Moreover, AES Sparrows turned entirely on the
meaning of a regulation that does not even apply in
this case. See Pet. App. 65a. The regulation AES
Sparrows interpreted is an Army Corps implementing
rule for CWA § 404, 33 U.S.C. § 1344, under which the
Army Corps may grant permits for certain discharges
into navigable waters. The Army Corps regulation at
issue in AES Sparrows provided that no § 404 permit
“will be granted” by the Army Corps “until [a § 401]
certification has been obtained or has been waived,”
and that, “[i]n determining whether * * * waiver has
occurred, the [Army Corps’] district engineer will verify that the certifying agency has received a valid request for certification.” 33 C.F.R. § 325.2(b)(1)(ii).
In AES Sparrows, the Army Corps’ district engineer issued a public notice on April 25, 2008 stating
that Maryland had one year from that date to act on
the applicant’s request for a water quality certification. 589 F.3d at 729. Applying § 325.2(b), the Fourth
Circuit held that the one-year clock began to run on
the date of the 2008 notice, rather than in 2007, when
Maryland had first received the request. Ibid.
Whatever the merits of that holding, it has no application here. Rover sought a § 401 certification in
connection with its application to FERC for an NGA
17
§ 7 certificate, not in connection with an application to
the Army Corps for a CWA § 404 permit. The Army
Corps’ implementing regulations are therefore irrelevant.
In addition, the Army Corps regulation at issue in
AES Sparrows said only that the engineer should verify that “the certifying agency has received a valid request for certification.” 33 C.F.R. § 325.2(b)(1)(ii)
(2008). The regulation did not say what it meant for a
certification to be “valid,” or that the certifying State
(rather than EPA) was legally empowered to set criteria for “valid[ity].” Ohio apparently interprets AES
Sparrows to mean that, as a matter of federal law,
States must be permitted to decide whether an application for a § 401 certification is “complete.” See Pet.
9-10, 18. Ohio neglects to mention that AES Sparrows
itself rejected this interpretation, reasoning that it
would be “inconsistent with the plain language of 33
C.F.R. § 325.2(b)(1)(ii)” to suggest that “the state has
the responsibility to determine if it has received a
valid request for a § 401(a)(1) water quality certification.” AES Sparrows, 589 F.3d at 730 n.3 (citation
omitted).
In short, Ohio can marshal no case from any court
in any jurisdiction that has interpreted the actual text
of § 401 as it prefers. There is accordingly no split of
authority for this Court to resolve.
3. What’s more, the Army Corps itself has declined
to defend the interpretation of its regulation offered in
AES Sparrows. During FERC proceedings concerning
the Millenium pipeline in New York State, the parties
had the same dispute that now exists here: The pipeline developer argued to FERC that New York had
18
waived its § 401 authority by taking longer than one
year to act on its request for a certification, and New
York argued that it had not waived because the clock
did not begin running until the application was “complete.” The Army Corps wrote a letter (the “Ryba Letter”) indicating that it “does not endorse the position
taken by either side of this dispute” and that, should a
“Federal Court resolve this legal question, the Corps
would abide by [that] determination.”5
FERC ultimately agreed with the developer that
New York had waived, reasoning that the “plain
meaning” of § 401 is that the one-year clock begins
running “the day the agency receives a certification
application, rather than when the agency considers
the application to be complete.” Millennium Pipeline,
161 FERC ¶ 61,186, P 38. In so holding, FERC correctly noted that its case was “distinguishable from
AES Sparrow[s] ” because the “Corps’ interpretation of
the CWA is not at issue in this proceeding.” Id. P 31.
The Second Circuit then unanimously agreed with
FERC’s waiver ruling in Millenium Pipeline. Reviewing FERC’s orders without Chevron deference, the Second Circuit rejected New York’s argument that the
one-year timeline “applies only for ‘complete’ applications.” NYSDEC, 884 F.3d at 455-456. As noted, the
5 Letter from Stephen A. Ryba, Chief, Regulatory Branch, Army
Corps, to Ron Happach, CEO, Millenium Pipeline Company, LLC
(Oct. 16, 2017), FERC Accession No. 20171026-5163 attach. 2,
https://tinyurl.com/4xuz925j; see Millennium Pipeline Co.,
L.L.C., 161 FERC ¶ 61,186, P 31 & n.54 (2017) (discussing Ryba
Letter).
19
Army Corps itself has promised to “abide by [that] determination” rather than AES Sparrows. Ryba Letter
at 1.
4. Perhaps recognizing that it cannot credibly rely
on its flimsy alleged circuit split, Ohio asserts that
“federal regulations also conflict in reading Section
401.” Pet. 19. But this Court does not grant review to
resolve “splits” between federal regulations. Nor does
Ohio explain why supposedly different interpretations
of § 401 offered by FERC and the Army Corps would
warrant this Court’s review, given that neither of
those agencies (as opposed to EPA) has authority to
interpret § 401 itself. 6 As Ohio later sheepishly admits, Congress instead delegated that authority solely
to EPA, which has issued rulemakings on the subject
(postdating the operative facts of this case) and is continuing to examine the question. See Pet. 8; see also
pp. 8-9, supra.
II. This Case Does Not Present Important or
Recurring Questions, and Is a Poor Vehicle.
Regardless, even if the State’s assertions regarding
a supposed circuit tension could be credited, the questions presented do not warrant review—and this case
would also be an extraordinarily bad vehicle for addressing them.
6 If Ohio believes that there is a tension between EPA’s current
regulations and those of FERC, the solution is to petition FERC
to revise its rule.
20
A.
The First Question Presented Does Not
Warrant Review.
1. The question of when a certification request has
been received, thereby triggering the one-year waiver
clock, is rarely litigated. Although § 401 has existed
for more than fifty years, the petition identifies only
two other cases that have even arguably addressed the
subject. And one of those two cases—AES Sparrows—
was decided more than 15 years ago, has not been followed by any court since, and has been read narrowly
by the Fourth Circuit itself. See N.C. Dep’t of Envt.
Quality v. FERC, 3 F.4th 655, 667 n.4 (4th Cir. 2021)
(“Sparrows Point has no application” in cases that “involve withdrawn and resubmitted applications” for
§ 401 certifications).
2. There is a reason why the first question presented is so seldom litigated. As the Ohio Supreme
Court correctly recognized, if a State believes that an
application for a § 401 certification is incomplete, it
can simply deny the application within one year of receiving it. See Pet. App. 66a; accord NYSDEC, 884
F.3d at 456 (“If a state deems an application incomplete, it can simply deny the application without prejudice—which would constitute ‘acting’ on the request
under the language of Section 401.”); 2020 Rule, 85
Fed. Reg. at 42,250, 42,265 (similar). Ohio could have
timely denied Rover’s November 2015 application due
to supposed “incompleteness,” as many other States often do. The only reason this case arose is because Ohio
elected not to take that simple step. Thus, Ohio’s suggestion that the decision below threatens its “sovereignty over [its] own waters” is hyperbolic and inaccurate. Pet. 19. All a State in Ohio’s position must do to
21
fully protect its powers over waters within its borders
is to deny an application it believes is incomplete.
There is no reason to grant review to address an issue
States can avoid ever even arising simply by acting
with minimal diligence.
Ohio claims that it would prefer not to deny incomplete applications, supposedly because “that approach
would make the certification process far more adversarial” and would “prematurely trigger public notice
obligations * * * and hearing obligations.” Pet. 27-28.
But the procedural obligations Ohio discusses are all
creatures of state law. See 33 U.S.C. § 1341(a)(1) (the
“State * * * shall establish procedures for public notice” and “public hearings”); Pet. 28 (discussing rules
for hearings and comment periods under Ohio Rev.
Code §§ 6111.30(C)-(D)). If Ohio is truly concerned
about the risk of “confusing” or “duplicative” proceedings over applications it regards as incomplete, ibid.,
then it can change its procedures to address those concerns. Cf. NYSDEC, 884 F.3d at 456. Nor does Ohio
explain why denying an incomplete application without prejudice would be particularly “adversarial.”
3. Equally significant to the unworthiness of this
case for review is that EPA has addressed the timing
issue in rulemakings that postdate the operative
events in this case. See pp. 8-9, supra. It would be a
profound waste of this Court’s resources to ignore a
decade of intervening agency rulemaking on § 401 and
take up a case whose facts long predate all those
rules—especially given that the operative rules may
soon change again.
The Ohio Supreme Court issued its ruling on the
first question presented while EPA’s 2020 Rule was in
22
effect. That alone is a serious vehicle problem, given
that the regulations in place when this case was decided differ from those in place now. To make matters
worse, Ohio now seeks to draw support from the 2023
Rule, which postdates the relevant opinion below by
more than a year. But the 2023 Rule arguably allows
Ohio to implement its preferred rule on a prospective
basis—rendering it wholly pointless to grant review
here, save as an exercise in fact-specific case review
unworthy of this Court’s attention. See 2023 Rule, 88
Fed. Reg. at 66,577-78. Moreover, both the 2020 Rule
and the 2023 Rule provided that there would be certain minimum requirements for certification requests.
Thus, federal agency rulemaking has already foreclosed the State’s strained hypotheticals about
whether it would be enough to submit a certification
request via “handwritten note” or “a shout across the
street,” answering them in the negative. Cf. Pet. 23.7
And even if the first question warranted review,
that review would be premature. Litigation concerning the 2023 Rule remains ongoing, and the current
Administration has signaled that it may soon revisit
7 The 2020 Rule defined the term “certification request” and
listed certain “documents and information that must be included
in a certification request.” 85 Fed. Reg. at 42,243; see id. at
42,286 (40 C.F.R. §§ 121.5(b), (c) (2020)). Ohio’s petition does not
claim that Rover’s November 2015 certification request would be
materially incomplete under the 2020 definition of “certification
request,” which in any case postdated Rover’s November 2015
request by almost five years. Tellingly, the components that Ohio
insists were supposedly missing from Rover’s 2015 request (e.g.,
a “jurisdictional determination from the Army Corps,” Pet. 12)
were not required by EPA’s 2020 definition of “certification
request.”
23
that rule. See p. 9, supra. Granting review would
short-circuit an ongoing administrative process for no
good reason. The better approach is to let EPA’s process play out on its own terms. Ohio can participate
in that process, as other States are doing and have
done. And, should some party ultimately ask this
Court to review the validity of the 2023 Rule (or whatever new rule EPA may soon propose), this Court can
grant review at that time, if appropriate.
4. Review of the first question presented would also
be inequitable and unwarranted because Ohio did not
present its current argument concerning “complete”
applications to the trial court or the Fifth District. See
p. 12 n.3, supra. It debuted that argument at the Ohio
Supreme Court, apparently because a number of other
courts had rejected its prior “revise-and-resubmit” theory during the period after this case was filed but before it reached the Ohio Supreme Court. Even assuming that this Court could properly review the first
question despite the fact that it indisputably was not
presented at each stage of the state-court proceedings,8 the record is bereft of information that would be
8 Rover raised this preservation objection at the Ohio Supreme
Court, see Rover Ohio S. Ct. Br. 3, 40-41 (Aug. 7, 2020), 2020 WL
4677970, and that Court ultimately decided the case without
explicitly passing judgment on the preservation issue. But “[t]he
issue whether a federal question was sufficiently and properly
raised in the state courts is itself ultimately a federal question,
as to which this Court is not bound by the decision of the state
courts.” Street v. New York, 394 U.S. 576, 583 (1969).
Moreover, the petition violates this Court’s Rule 14.1, which
provides that, when “review of a state-court judgment is sought,”
the petitioner must specify “the stage in the proceedings, both in
24
critical for this Court to properly review the question.
Notably, Rover’s November 2015 certification application—the critical document on which Ohio’s entire
case now turns, see Pet. 26—is not even in the record
for this proceeding.
5. Finally, even if Ohio were correct on its first
question presented, it would not change the ultimate
result in this case. Although § 401 provides that the
maximum time to act on an application is one year, it
also makes clear that States ultimately must act
within a “reasonable period of time,” 33 U.S.C.
§ 1341(a). Many States have implemented laws interpreting the “reasonable period” to be less than one
year. See 2020 Rule, 85 Fed. Reg. at 42,235. Ohio is
one such State: Its statutes require the Ohio Department of Environmental Protection to “issue or deny” a
certification within 180 days after receipt of a “complete application.” Ohio Rev. Code § 6111.30(G). Ohio
admits that “Rover submitted a completed application” by July 2016, meaning that the deadline for State
action was January 2017. State’s Ohio S. Ct. Br. 37;
cf. Pet. 12. Thus, even if Ohio were correct that the
clock does not begin to run until an application is complete, its February 2017 certification was still too late.
the court of first instance and in the appellate courts, when the
federal questions sought to be reviewed were raised.” S. Ct. R.
14.1(g)(1) (emphasis added). The petition makes no such
disclosure. Cf. Adams v. Robertson, 520 U.S. 83, 92 n.5 (1997)
(noting non-compliance with Rule 14.1(g) before dismissing writ
of certiorari as improvidently granted); Johnson v. California,
541 U.S. 428, 431 (2004) (similar).
25
B.
The Second Question Presented Does
Not Warrant Review.
1. As to the second question presented—concerning the consequences of Ohio’s waiver for its claims in
this litigation—Ohio concedes that it seeks review of
an intermediate state appellate court decision. That
decision is binding solely in one of twelve intermediate
appellate districts in Ohio. And in the (unlikely) event
the issue ever arises in a future case, the Ohio Supreme Court is free to revisit the Fifth District’s legal
holdings. This Court rarely grants review in such circumstances. Cf. Huber v. N.J. Dep’t of Env’t Prot., 131
S. Ct. 1308, 1308 (2011) (statement of Alito, J., respecting denial of certiorari).9
The absence of any decisions from other courts addressing the second question presented—much less
decisions of federal appellate courts or state courts of
last resort—cuts sharply against review. This Court
does not customarily grant review of legal issues that
have not been addressed by any court except a single
intermediate state appellate court. Cf. Maslenjak v.
United States, 137 S. Ct. 1918, 1932 (2017) (Gorsuch,
J., concurring in part and concurring in the judgment)
(“This Court often speaks most wisely when it speaks
last.”).
The absence of other decisions addressing the
question is, moreover, entirely unsurprising. For
9 The Ohio Supreme Court’s decision not to grant discretionary
review does not constitute “a statement of opinion as to the merits
of the law stated by” the Fifth District. Ohio Sup. Ct. Rep. Op. R.
4.1; accord State v. Davis, 894 N.E.2d 1221, 1225 (Ohio 2008).
26
starters, the second question presented—properly construed—concerns only the effect of Ohio’s waiver on its
specific claims in this case. The State conceded in the
Ohio Supreme Court that waiver would prevent it
from “later us[ing] state law to stop or remediate pollution within the scope of the certification it declined
to act on”—in other words, that waiver would extinguish the State’s authority to regulate “the activity for
which a permit is sought.” State’s Ohio S. Ct. Br. 18;
cf. Pet. 12 (Ohio Supreme Court citing that concession). The Ohio Supreme Court agreed with that framing, see Pet. App. 68a-70a, and the Fifth District
simply found that Ohio lost even under that approach.
The fact that that narrow question presents no split of
legal authority (and never will) is hardly surprising.
To the extent Ohio seeks to frame its second question
presented more broadly—in terms of unspecified
“other” rights it might retain despite its waiver, and
despite the NGA’s preemptive scope, Pet. i—it forfeited any such arguments long ago.
In any event, questions about the effect of a
waiver on subsequent efforts to regulate federally permitted projects rarely arise because States seldom
waive under § 401 without intending to do so, much
less waive and then come back later seeking to use litigation to enforce environmental conditions they could
have, but did not, include in a timely § 401 certification.10 In addition, all States have to do to avoid the
situation in which Ohio found itself is either (1) deny
10 Such waivers are even less common after the D.C. Circuit’s
Hoopa Valley decision and its progeny, which clarified the
relationship between waivers under § 401 and revise-andresubmit schemes. See Hoopa Valley, 913 F.3d at 1104.
27
the application; or (2) grant the application with conditions pursuant to CWA § 401(d)—which can include
state-law water-quality-related conditions like the
ones at issue here, see PUD No. 1 of Jefferson Cnty. v.
Wash. Dept. of Ecology, 511 U.S. 700, 713 (1994). Ohio
took neither step, and now seeks discretionary relief
from a problem of its own making. But no State will
ever face the same problem if it acts diligently to deny
or conditionally grant certification requests.
2. In an effort to paper over the manifest unimportance of the second question, Ohio offers constitutional puffery—going so far as to frame the decision
below as a threat to its sovereignty. But the State’s
constitutional overtures are empty. Ohio complains
about being forced to choose between participating in
the § 401 process and having its ability to regulate interstate natural gas pipeline construction preempted.
See Pet. 31. But Congress occupied the field of interstate natural gas pipeline construction when it enacted the NGA in 1938—something it plainly had constitutional authority to do. Although Congress later
gave States a limited role in the process via § 401 and
the NGA’s savings clause, it was not constitutionally
required to give States any such role. Questions about
the scope of the NGA’s savings clause and the consequences of the CWA’s waiver provision thus have no
constitutional implications whatsoever.
3. Nor does the second question presented implicate any concerns about adequate environmental regulation of FERC-permitted infrastructure projects.
The Fifth District’s decision simply held that, due to
the combined effect of Ohio’s waiver against the back-
28
drop of preemption under the NGA, regulatory authority reverted to exclusive federal oversight. And that
federal oversight was fully exercised here. FERC
paused construction of the Rover project at Ohio’s urging to address the same concerns at issue in this case,
and millions of dollars were spent on remediation, satisfying FERC that Ohio’s environment would be adequately protected on a prospective basis. As for retrospective sanctions, FERC is pursuing an enforcement
action against Rover with respect to the same discharges that form the predicate of this suit. See p. 11,
supra.
C.
This Case Also Presents Threshold
Jurisdictional Issues That Further Cut
Against Review.
The procedural posture of the case also raises serious questions about statutory jurisdiction that could
prevent the Court from reaching the merits of most of
Ohio’s current claims. That is because, as the defendants argued below, those claims are improper collateral attacks on long-final FERC orders, which were required to be brought (if at all) in challenges to those
orders in federal appellate court.
Section 19(b) of the NGA grants the federal courts
of appeals “exclusive” jurisdiction “to affirm, modify,
or set aside” FERC’s orders. 15 U.S.C. § 717r(b). That
statute “preclude[s] de novo litigation between the
parties of all issues inhering in [a] controversy” before
FERC. City of Tacoma v. Taxpayers of Tacoma, 357
U.S. 320, 336 (1958). Thus, Ohio’s current claims are
precluded to the extent they relate to issues on which
the State lost at FERC, or could have raised at FERC
and elected not to.
29
Ohio’s claims fit that description to a tee. For example, the claims regarding drilling fluid in Counts 1,
3, and 5 are improper collateral attacks on both
FERC’s September 2017 Order (which rejected Ohio’s
arguments concerning fluid releases and allowed construction to resume over the State’s objection) and
FERC’s EIS and certificate order (which approved the
construction method Rover used and acknowledged
the eventuality of the releases to which Ohio later objected). See Pet. App. 4a, 17a, 92a. And the claims
regarding stormwater releases in Counts 2 and 5 are
improper collateral attacks on both FERC’s certificate
order (which anticipated stormwater discharges and
included conditions regulating them) and FERC’s September 2017 Order (which allowed construction to resume despite Ohio’s objection that Rover needed to obtain certain stormwater permits). See ibid.
Ohio’s sole mechanism for litigating these claims
was to raise them at FERC and then seek review of
FERC’s orders by filing a petition for review in an appropriate federal court of appeals. Cf. Pet. App. 22a.
The fact that Ohio never pursued such a petition is irrelevant, because a State cannot “circumvent the
scheme of judicial review under § 19 simply by choosing not to file a petition for review.” Williams Nat. Gas
Co. v. Oklahoma City, 890 F.2d 255, 262 n.8 (10th Cir.
1989).
This jurisdictional issue was extensively briefed
during the state-court litigation. Because the Ohio
courts resolved this case on other grounds (which were
subject-matter-jurisdictional under Ohio state law,
see Pet. App. 8a, 108a), they never reached this question. But if this Court granted review, it would need
30
to decide whether Ohio was required to litigate its current claims in the federal courts of appeals, or whether
the state courts below lacked subject-matter jurisdiction. Cf. PennEast Pipeline Co., LLC v. New Jersey,
141 S. Ct. 2244, 2254 (2021). Litigation of these
threshold jurisdictional issues would crowd out the
merits of the questions on which Ohio seeks review.
Cf. Monsalvo v. Bondi, 145 S. Ct. 1232, 1245 (2025)
(Thomas, J., dissenting) (expressing frustration that
“[t]his Court granted certiorari to decide” underlying
merits issues, but “briefing revealed a serious, novel
jurisdictional objection” concerning the lower court’s
statutory jurisdiction “that may bar our review”). If
this Court wants to review the questions presented, it
can do so in a future case free of lurking jurisdictional
problems—e.g., an appeal of challenges to an EPA implementing rule.
III. The Decision Below Is Correct.
A.
The Ohio Supreme Court Correctly
Resolved the First Question Presented.
1. As to the first question presented, Section 401
provides that the one-year clock starts upon “receipt”
of a “request for certification,” 33 U.S.C. § 1341(a)(1)—
not that it starts when the request for certification is
“complete.” Dictionaries and ordinary speakers of
English understand the word “request” to mean any
instance of asking for something. See Black’s Law Dictionary 1468 (4th ed. 1968) (noun “request” means
“[a]n asking” or “the expression of a desire to some person for something to be granted”); Webster’s Third
New International Dictionary 1929 (1971) (“request”
means “an instance of asking for something”).
31
All agree that the application Ohio received from
Rover in November 2015 asked for a § 401 certification
to be granted. That application was therefore a “request” within the ordinary meaning of that term. Ohio
nonetheless implies that the application was not “formal” enough to qualify under its atextual definition of
“request.” Pet. 23. But the November 2015 application was presented on a standard form made available
by the Ohio Environmental Protection Agency, and it
was accompanied by detailed tables, schematics,
maps, design parameters, economic and environmental analyses, and mitigation plans that together
spanned more than 1,700 pages. See Rover Ohio S. Ct.
Br. 44 & n.14. Ohio’s suggestion that Rover’s request
was akin to a “quick email” or a “handwritten note”
blinks reality. Pet. 23.
2. Ohio now insists that the term “request” actually means “complete request,” supposedly because
that meaning is evident from the “broader context” of
the statute. Pet. 23. Wrong. Congress did not use the
word “complete” in § 401, and no court may “add words
to [a] law to produce what is thought to be a desirable
result.” EEOC v. Abercrombie & Fitch Stores, Inc., 575
U.S. 768, 774 (2015); see Turkiye Halk Bankasi A.S. v.
United States, 143 S. Ct. 940, 945 (2023) (court cannot
“graft an atextual limitation” into a federal statute).
In any case, statutory context confirms that, when
Congress intended to qualify the term “application”
with the modifier “complete,” it did so. For example,
CWA § 404 provides that certain notice requirements
for permits under that Section are tethered to the
“date an applicant submits all the information required to complete an application for a permit.” 33
32
U.S.C. § 1344(a) (emphasis added)).11 That Congress
said “complete” elsewhere in the CWA, but not in
§ 401, confirms that all “requests” for certification—
not just “complete” ones—start the waiver clock under
§ 401. See Sosa v. Alvarez-Machain, 542 U.S. 692, 711
n.9 (2004) (“[W]hen the legislature uses certain language in one part of the statute and different language
in another, the court assumes different meanings were
intended.”).
3. Congress’s textual decision also dovetails with
sound policy. Ohio’s rule would defeat the purpose of
the statute by allowing States to indefinitely delay
much-needed projects via determinations that the application is not “complete” due to their own subjective
interpretations of vague and ever-shifting state laws.
As thirteen States explained in a recent letter to EPA,
crediting Ohio’s theory in this case will “enable States
to * * * frustrate infrastructure development” and
“us[e] bureaucratic games to effectively veto a project
that has significant economic effects across an entire
region.” Comments of Louisiana et al. at 7-8, Docket
No. EPA-HQ-OW-2022-0128-0123 (Aug. 8, 2022),
https://perma.cc/N33H-S7CW. This risk is particu-
11 Myriad other statutes confirm that Congress plainly knows
how to refer to a “complete” application when it wants to. See,
e.g., 42 U.S.C. § 7661b(c) (provision of Clean Air Act requiring
action on “a completed application” within “18 months after * * *
receipt thereof”); 22 U.S.C. § 8753(d) (“License determinations for
complete requests * * * shall be made not later than 90 days after
receipt”); 42 U.S.C. § 505(f)(1) (“within 30 days after receipt of a
complete application”); 42 U.S.C. § 7651g(c)(2) (“within 6 months
after receipt of a complete submission”); 20 U.S.C. § 6364(f)(4)
(“90 days after receipt of the complete application”).
33
larly dangerous in the context of interstate gas pipelines, where the applicant often must obtain 401 certifications from multiple States that have multiple
standards. Requiring States to act promptly on certification requests—rather than bogging down project
development in debates or litigation about whether
applications are “complete” enough to satisfy a particular State—is the only way to ensure such projects can
move forward.
B.
The Fifth District Correctly Resolved
the Second Question Presented.
As to the second question presented, the decision
below rested on a straightforward application of wellaccepted preemption principles against the backdrop
of Ohio’s waiver. The NGA preempts all state environmental regulation of interstate natural gas pipeline
construction except to the extent covered by its savings
clause. See pp. 4-5, supra. Thus, Ohio had no authority to regulate Rover’s construction activities except
insofar as it was exercising “rights * * * under” the
CWA. 15 U.S.C. § 717b(d). That disposes of any effort
by the State to assert its traditional (non-federally-delegated) regulatory powers in this unique context.12
And all of Ohio’s rights under the CWA were
waived. Ohio conceded below that “a State necessarily
waives its right to participate in the permitting pro-
12 Ohio halfheartedly argues otherwise, see Pet. 32-33, but the
most natural reading is that the phrase “rights * * * under” the
CWA, 15 U.S.C. § 717b(d)(3), means rights that exist “by reason
of the authority” of the CWA, Nat’l Ass’n of Mfrs. v. Dep’t of Def.,
583 U.S. 109, 124 (2018).
34
cess, and thus waives its right to enforce state pollution laws in response to pollution that is within the
federal permit’s scope, if it fails timely to act on a certification request,” State’s Ohio S. Ct. Br. 4, and it has
now forfeited any broader argument. Moreover, as
Rover explained below, all of Ohio’s claims fall within
the scope of the federal permit, because they all pertain to Rover’s pipeline construction, and all of the requirements it sought to assert were requirements it
could have placed in § 401(d) conditions.
Thus, all of Ohio’s claims, whether nominally
granted in federally conferred rights under the CWA
or Ohio’s traditional regulatory authority, are either
waived or preempted. That narrow, case-specific decision of an intermediate state court is plainly unworthy
of review. And, once again, the decision below accords
not only with the text of the statute and with familiar
preemption principles; it accords as well with sound
policy. Through the NGA and CWA, Congress balanced the federal interest in a FERC-centered interstate pipeline development process with the States’ interest in regulating waters by creating a defined process for States to participate in pipeline regulation:
§ 401 certification. As participants in that process,
States have a time-limited opportunity to impose regulatory requirements. That process gives federal authorities timely notice of the requirements the State
seeks to impose on a project, before construction commences. But if a State chooses not to participate, it
must stand aside and cede to exclusive federal authority. A State cannot fail to participate according to the
process Congress specified, then later change its mind
and decide it wishes to impose requirements after all.
35
A contrary approach would “hamstring new infrastructure and construction projects,” Seven Cnty. Infrastructure Coal. v. Eagle Cnty., Colo., 145 S. Ct.
1497, 1514 (2025), by rendering the one-year deadline
a nullity and preventing both federal authorities and
project developers from knowing what regulatory requirements their federally permitted projects will be
subject to in a timely manner.
36
CONCLUSION
The petition should be denied.
Respectfully submitted.
WILLIAM S. SCHERMAN
Counsel of Record
JASON J. FLEISCHER
MATTHEW X. ETCHEMENDY
VINSON & ELKINS LLP
2200 Pennsylvania Ave.,
NW, Suite 500 West
Washington, DC 20037
(202) 639-6550
wscherman@velaw.com
Counsel for Respondent
Rover Pipeline, LLC
BENJAMIN C. SASSÉ
TUCKER ELLIS LLP
950 Main Ave., Suite 1100
Cleveland, OH 44113
(216) 696-3213
benjamin.sasse
@tuckerellis.com
Counsel for Respondent
Pretec Directional
Drilling, LLC
JUNE 2025
This is a copy of a public record, reproduced as it was published. It is not legal advice, and it may not be the version a court would rely on. Check the official source before you cite it.