Petition for Writ of Certiorari — Servant Health, LLC, Petitioner v. United States
Supreme Court briefApr 15, 2025
Ask Donna
What actually matters in this document.
Text
No. _______
_________________________________________________
IN THE
Supreme Court of the United States
______________
SERVANT HEALTH, LLC,
Petitioner,
v.
UNITED STATES OF AMERICA,
Respondent.
______________
On Petition for Writ of Certiorari to the United
States Court of Appeals for the Federal Circuit
______________
PETITION FOR WRIT OF CERTIORARI
______________
ERIC S. MONTALVO*
CAROL A. THOMPSON
FEDERAL PRACTICE GROUP
801 17TH ST. N.W., SUITE 250
WASHINGTON, DC 20006
(202) 862-4360
emontalvo@fedpractice.com
Counsel for Petitioner
*Counsel of Record
_________________________________________________
LEGAL PRINTERS LLC ! Washington, DC ! 202-747-2400 ! legalprinters.com
i
QUESTIONS PRESENTED
Whether an executive agency contracting officer
may eliminate the requirement to exercise discretion
by inserting contract language that nullifies the
Federal Acquisition Regulation’s excusable delay
protections in a commercial items contract.
Whether a contracting officer’s refusal to consider
delivery delays caused by the Suez Canal blockage—
an archetypal common carrier delay—violates FAR
52.212-4(f) and exceeds the officer’s authority under
41 U.S.C. § 3307.
Whether, under Loper Bright Enterprises v.
Raimondo, courts must invalidate agency actions that
amount to unauthorized legislative rulemaking,
including when a contracting officer unilaterally
rewrites procurement obligations established by
Congress.
ii
PARTIES TO THE PROCEEDING
Petitioner (plaintiff-appellant below) is Servant
Health, LLC. Respondent (defendant-appellee below)
is the United States. Servant Health’s case was
consolidated with three other Plaintiff-Appellant’s:
Transcendence, Inc.; Noble Attorney, LLC; and
American Medical Equipment, Inc. Only Servant
Health, individually, submits this Petition.
iii
CORPORATE DISCLOSURE STATEMENT
Petitioner has no parent corporation, and no
publicly held company owns 10% or more of the
corporation’s stock.
iv
STATEMENT OF RELATED PROCEEDINGS
The following proceedings are directly related to
this case within the meaning of Rule 14.1(b)(iii):
• Servant Health et al., v. United States, No. 222193, 22-2194 (Fed. Cir.), judgment entered on
September 30, 2024;
• Servant Health et al., v. United States, No. 211373C, 21-1456C, 21-1472C (Court of Federal
Claims), judgment entered on August 5, 2022;
• American Medical Equipment, Inc., v. United
States, No. 21-1553C (Court of Federal Claims),
judgment entered on June 30, 2022.
v
TABLE OF CONTENTS
QUESTIONS PRESENTED ........................................ i
PARTIES TO THE PROCEEDING ........................... ii
CORPORATE DISCLOSURE STATEMENT ........... iii
STATEMENT OF RELATED PROCEEDINGS ....... iv
PETITION FOR WRIT OF CERTIORARI ................ 1
OPINIONS BELOW ................................................... 1
JURISDICTION.......................................................... 1
CONSTITUTIONAL PROVISIONS INVOLVED...... 1
STATUTORY PROVISIONS INVOLVED ................. 1
STATEMENT OF THE CASE .................................... 2
A.
Legal Framework. ............................................ 2
B.
Factual Background. ........................................ 5
C.
Procedural Background. .................................. 9
SUMMARY OF THE ARGUMENT ......................... 12
REASONS FOR GRANTING THE PETITION ....... 13
I. The Federal Circuit’s Decision Conflicts with
Loper Bright and Violates the Separation of
Powers................................................................. 13
II. Executive Officials Lack Authority to Rewrite
Statutorily Mandated FAR Clauses .................. 13
III. The Refusal to Consider Excusable Delay
Violated FAR 52.212-4(f).................................... 14
IV. This Case Is an Ideal Vehicle to Clarify the
Scope of Loper Bright and Resolve Post-Chevron
Uncertainty ........................................................ 15
V. Agency Overreach Undermines Prior
Precedent on Separation of Powers ................... 16
vi
VI. Abuse of Discretion and Preservation of the
Issue Below ......................................................... 17
CONCLUSION.......................................................... 18
APPENDICES
APPENDIX A
Opinion, U.S. Court of Appeals for the
Federal Circuit, Servant Health et al., v.
United States, No. 22-2193, 22-2194
(Sept.30,2024)………………………………….
APPENDIX B
Opinion, U.S. Court of Federal Claims for
Servant Health et al., v. United States, No.
21-1373C, 21-1456C, 21-1472C
(Aug.5,2022)………………………………….…
APPENDIX C
Opinion, U.S. Court of Federal Claims for
American Medical Equipment, Inc., v.
United States, No. 21-1553C
(June 30, 2022)…………………………………
APPENDIX D
Order, U.S. Court of Appeals for the
Federal Circuit, American Medical
Equipment, Inc., Petition for Panel
Rehearing, Servant Health et al., v. United
States, No. 22-2193
(Jan. 17, 2025)……………………………….…
APPENDIX E
Order, U.S. Court of Appeals for the
Federal Circuit, Servant Health et al.,
Petition for Panel Rehearing, Servant
Health et al., v. United States, No. 22-2193
(Dec. 6, 2024)……………………..…………….
App 1
App 22
App 95
App 133
App 135
vii
APPENDIX F
Relevant Statutory Provisions
FAR 12.301 (a), (b)(3)………………….……..
FAR 12.302 …………………………………...
FAR 52.212-4 (f) …………………….………..
41 U.S.C. § 3307 (a), (b), (e)(1-2)…………...
App 137
App 138
App 140
App 141
viii
TABLE OF AUTHORITIES
Cases
City of Arlington v. FCC,
569 U.S. 290 (2013) ............................................... 16
FEC v. Cruz,
596 U.S. 289 (2022) ............................................... 14
Kisor v. Wilkie,
588 U.S. 558 (2019) ......................................... 16, 17
Loper Bright Enterprises v. Raimondo,
603 U.S. 369 (2024) ................................... 13, 15, 18
McDonnell Douglas Corp. v. United States,
182 F.3d 1319 (Fed. Cir. 1999) .............................. 17
Servant Health et al., v. United States,
Nos. 22-2193, 22-2194 (Fed. Cir. Sep. 30, 2024) 5, 9
United States v. Brooks-Callaway Co.,
318 U.S. 120 (1943) ............................................... 14
Statutes
28 U.S.C. § 1254(1) ..................................................... 1
28 U.S.C. § 1291 .......................................................... 1
28 U.S.C. § 2101(c) ...................................................... 1
41 U.S.C. § 3307 ...................................... 1, 2, 3, 12, 15
Pub. L. 111–350, § 3, Jan. 4, 2011,
124 Stat. 3754 .......................................................... 2
Regulations
FAR 1.403 .................................................................. 14
FAR 12.301 .................................................................. 3
FAR 12.302 ............................................................ 4, 14
FAR 52.212-4 ............................................ 3, 12, 14, 15
Constitutional Provisions
Art. II, § 1, cl. 1. .......................................................... 1
1
PETITION FOR WRIT OF CERTIORARI
Servant Health respectfully petitions for a writ of
certiorari following judgment by the United States
Court of Appeals for the Federal Circuit.
OPINIONS BELOW
The Federal Circuit’s opinion is not reported in
Fed. Rptr., 2024 WL 4342872 and reproduced at
App.1. The Court of Federal Claims’ opinion is
reported at 161 Fed.Cl. 210 and reproduced at App.21.
JURISDICTION
The final judgment of the court of appeal was
entered on September 30, 2024. The Federal Circuit
denied Petitioner Servant Health’s (as well as coplaintiff’s Transcendence and Noble Attorney)
Petition for Panel Rehearing on December 6, 2024.
The Federal Circuit denied American Medical
Equipment, Inc.’s Petition for Panel Rehearing on
January 17, 2025. The court of appeal’s jurisdiction
rests on 28 U.S.C. § 1291. The jurisdiction of this
Court is invoked under 28 U.S.C. § 1254(1) and §
2101(c).
CONSTITUTIONAL PROVISIONS INVOLVED
Art. II, § 1, cl. 1.
STATUTORY PROVISIONS INVOLVED
Relevant provisions of 41 U.S.C. § 3307 are
reproduced at App.141. Relevant provisions of FAR
12.301, 12.302, and 52.212-4(f) are reproduced at
App.137-140.
2
STATEMENT OF THE CASE
Petitioner Servant Health was terminated for
cause under a contract with the Department of
Veterans Affairs to procure personal protective
equipment (“PPE”) during the height of the COVID-19
pandemic. During contract performance, Petitioner
timely notified the agency of excusable delays caused
by global shipping disruptions, including the Suez
Canal blockage. Rather than evaluate whether
excusable delay was warranted—as required under
FAR 52.212-4(f)—the contracting officer categorically
refused to consider the request. That refusal was
based on a unilaterally imposed contract term stating
that “no extensions will be granted,” which directly
contradicted governing acquisition regulations.
The contracting officer subsequently used the
threat of default to extract discounts and additional
concessions. When Servant Health declined, the
contracting officer proceeded with a termination for
cause. The Court of Federal Claims upheld the
termination, and the Federal Circuit declined to
address whether the contracting officer’s actions
unlawfully eliminated required regulatory discretion.
A. Legal Framework.
In 2011, Congress enacted statutory requirements
to govern executive agency contracting for commercial
items. Pub. L. 111–350, § 3, Jan. 4, 2011, 124 Stat.
3754. This framework is codified at 41 U.S.C. § 3307,
titled “Preference for commercial products and
commercial services.” App.141.
3
Section 3307 mandates that “[t]he Federal
Acquisition Regulation shall provide regulations to
implement this section,” and those regulations “shall
contain a list of contract clauses to be included in
contracts for the acquisition of end items that are
commercial products.” 41 U.S.C. § 3307(e)(2)(B);
App.141. Critically, Congress limited the use of
clauses in such contracts by requiring that, “[t]o the
maximum extent practicable, only the contract
clauses listed pursuant to subparagraph (B) may be
used in a contract.” 41 U.S.C. § 3307(e)(2)(D).
To implement these statutory requirements, the
FAR includes two controlling provisions:
•
•
FAR 52.212-4, 1 “Contract Terms and
Conditions—Commercial
Products
and
Commercial Services,” which provides the
standard commercial items clause; and
FAR 12.301, which directs when and how these
clauses must be used in solicitations and
awards. App.137,140.
FAR 12.301(a)(1)–(2) explicitly restates the
statutory limits under § 3307(e)(2)(B)(i)–(ii),
reinforcing that commercial item contracts must
adhere to standard commercial practices or legal
mandates. App.137,141. Among the mandatory
clauses is the Excusable Delays clause, FAR 52.2124(f), which provides:
The FAR is codified in Title 48 of the Code of Federal
Regulations. For ease of reference and to maintain consistency
with the Federal Circuit’s decision, Petitioner refers to the FAR
without the corresponding C.F.R. citations. App.4.
1
4
The Contractor shall be liable for default
unless nonperformance is caused by an
occurrence beyond the reasonable control of
the Contractor and without its fault or
negligence, such as acts of God or the public
enemy, acts of the Government in either its
sovereign or contractual capacity, fires, floods,
epidemics, quarantine restrictions, strikes,
unusually severe weather, and delays of
common carriers. The Contractor shall notify
the Contracting Officer in writing as soon as it
is
reasonably
possible
after
the
commencement of any excusable delay,
setting forth the full particulars in connection
therewith, shall remedy such occurrence with
all reasonable dispatch, and shall promptly
give written notice to the Contracting Officer
of the cessation of such occurrence.
FAR 52.212-4(f); App.140.
FAR 12.302(c) permits limited tailoring of
standard clauses, but only when the alteration is not
“inconsistent with customary commercial practice.” If
a deviation is necessary, the waiver request must:
•
•
•
identify the relevant commercial practice,
justify the need to deviate from it, and
determine that customary practice is
inconsistent with government needs. App.138.
Additionally, any tailored terms must be
incorporated through an “addenda to the solicitation
and contract.” FAR 12.302(d); App.138.
5
B. Factual Background.
At the height of the COVID-19 pandemic, the
Department of Veterans Affairs (“VA” or
“Department”) developed a solicitation project with
the goal of building and maintaining a stockpile of
PPE (nitrile medical gloves). App.3, 23-25. The VA
had no immediate need at any one facility, nor did it
conduct due diligence in determining how much PPE
the VA (or any one of its facilities) actually required or
by what date the stockpile should be created. App.3. 2
Instead, the VA created a multiple-award solicitation
with an arbitrarily set delivery date. 3 App23-25.
Servant Health was one of 15 contractors who
answered the call. App.25. On February 9, 2021,
Servant Health submitted a quote under Solicitation
36C24921Q0115 for 50 million gloves, and the
Department issued a corresponding award on March
11, 2021, via email, with a delivery date of April 26,
2021. App.6, 40-44.
The awarded contract contained FAR 52.212-4 in
its unaltered state, including its excusable delay
clause under paragraph (f). App.4-5, 28. The award
See also Corrected Br. of Pls.-Appellants at 13-14, Servant
Health et al., v. United States, Nos. 22-2193, 22-2194 (Fed. Cir.
Sep. 30, 2024), ECF No. 23.
2
The Department issued two “substantively identical”
solicitations in three rounds. App.24. The first round had a 30day deadline. App.23-24. The Department realized after the fact
that 30-days was not feasible, as it failed to receive bids. App.2324. The Department then arbitrarily increased the deadline to 45
days. App.24, 41.
3
6
also stated, via the solicitation’s statement of work,
that awarded contracts “will have 45 calendar days
from receipt of order (award date) to deliver the
awarded quantities, or the contract will be terminated
for cause.” App.26. The Department contracting
officer representative later affirmed in his deposition
that “[…] [termination for convenience] was never on
the table based on the decisions that were made
probably during the solicitation phase.” Corrected Br.
of Pls.-Appellants, supra note 3, at 41.
In the body of the email delivering the award the
contracting officer warned that “No extensions will be
granted. This includes but is not limited to delays with
the manufacturer, the supplier, shipping delays,
customs, and the pandemic.” App. 6, 43-44.
As could be expected during this time, Servant
Health faced delays caused by both its supplier, and
canal and port congestion. First, Servant Health’s
supplier informed it could no longer supply the
contracted for gloves; Servant Health then used
another supplier to deliver the same contracted for
gloves from the same original equipment
manufacturer used in its bid for award on the
solicitation. App.47, 52-53. Second, as was
experienced by so many other businesses during this
time, Servant Health’s shipments were disrupted by
the blockage of the Suez Canal and California port
congestions. App.46, 49-51.
Servant Health informed the VA that as of April
16, 2021, the shipment was en route, and would
include 50,000 more gloves than required under the
contract, due to the way the boxes of gloves were
7
packed onto pallets for shipping. App.44-45. One week
later, on April 22, 2021, Servant Health requested a
brief extension of approximately one-week based on
excusable delay——as only approximately 33,017,000
gloves of the contracted-for 50 million gloves could be
delivered within the original timeframe. App.46-47.
Servant Health explained that the March 23, 2021,
Suez Canal blockage and the resulting supply
problems (to include the impact on California ports)
had forced Servant to adjust its shipping method from
transoceanic shipping to air freight. App.6-7, 46-49.
However, the more limited airplane capacity meant
that the full 50 million gloves could not be transported
simultaneously. App.48.
The contracting officer summarily rejected any
notion of excusable delay and refused to even consider
the possibility. Corrected Br. of Pls.-Appellants, supra
note 3, at 20-27. Instead, the contracting officer would
only entertain an extension in return for additional
discounts or free product. App.48. Facing no other
choice, Servant Health offered a $0.10 discount per
remaining gloves, which the contracting officer
rejected out of hand, describing it as a “non-starter”
and choosing instead to press Servant Health for a
larger discount.
On April 25, 2021, the contracting officer again
informed Servant Health that they were in default,
stating:
I am deeply concerned about this
contract. From the beginning, it was
stated that the delivery date of 26 April
8
2021 was for 100% quantity of the
awarded gloves, and no extensions would
be granted due to the pandemic, customs,
etc. […] Also, I do not know what date
Servant Health is requesting the
contract to be extended to or what
consideration is being offered in lieu of
receiving a termination for cause.
App.48, 24-25.
The next day, the contracting officer informed
Servant Health that an extension to May 7 would only
be possible in exchange for a $1.00 discount on over 39
million gloves, reducing the price by $391,370.00, and
the promise of future discounted product. App. 25.
Servant Health counteroffered and requested to
bifurcate the remaining deliveries between May 7 and
May 28, 2021, as agreeing to a reduction of such scale
would cause severe financial harm to Servant Health.
Servant Health also followed up with a detailed
explanation of the excusable delay challenges, and a
renewed counteroffer.
On May 5, 2021, the contracting officer terminated
Servant Health for cause, for allegedly failing to
deliver the gloves on time. App.56-57. The
Termination Letter did not acknowledge Servant
Health’s efforts to mitigate the supply problems, nor
did it address a letter from Servant Health’s first
supplier exculpating Servant for the late deliveries.
Instead, Servant Health was summarily considered to
9
be in default, without
circumstances. App.56-57.
consideration
of
its
In summary, the contracting officer refused to
conduct any examination into whether excusable
delay was warranted, and instead used the threat of
automatic termination for cause as means to extort
unfair concessions from Servant Health.
Of the 15 contracts issued under the Department
of Veterans Affairs stockpile project, ten were
terminated. Nine of those terminated contracts,
including Petitioner’s, were for cause. 4 The tenth
termination was for convenience, but in name only,
because that same contractor held two contracts
under the solicitation and had already received the
for-cause termination on the other contract.
C. Procedural Background.
Servant Health and three other contactors (Noble
Attorney, Transcendence, and American Medical
Equipment) filed appeals with the U.S. Court of
Federal Claims, which were ultimately consolidated
into two cases. Servant Health challenged its forcause termination on the grounds of abuse of
discretion “without observance to the procedure
required by law,” breach of the implied duty of good
faith and fair dealing and duty to cooperate, and the
general failure to grant excusable delay. App.63-64.
4 Pls.’ Resp. to Def.’s Mot. for Summ. J. and Cross Mot. for Summ.
J. at 46, Servant Health et al., v. United States, 161 Fed.Cl. 210
(2022)(Nos. 21-1373C, 21-1456C, 21-1472C), ECF No. 44.
10
From the start, Petitioner challenged the
contract’s inclusion of an automatic termination for
default if the gloves were not delivered within 45 days
of award. Specifically, Servant Health argued that it
negated the language of FAR 52.212-4(f), and
prevented the contracting officer from exercising the
required discretion prior to terminating.
The Court of Federal Claims upheld the
contracting officer’s choice to rewrite the language of
the contract and held that the contracting officer was
permitted to nullify the excusable delay provision. See
App.90 (stating “The contracts did not provide that
extensions of time would be granted” and noting that
extensions were “prohibited.”).
In reaching this decision, the Court of Federal
Claims relied on the 45-day deadline in the
solicitation and on the email submitted with the
award which stated that “[n]o extensions will be
granted.” App.89-91 (finding “the express language of
the contracts—fully supported by the parties’ pre- and
post-award communications—required delivery of the
specific PPE plaintiffs proposed (which the VA vetted
and approved) and required delivery within 45
days[,]” and that, “The contracts further noted that no
extensions would be granted and that plaintiffs’
failure to timely deliver would result in a termination
for cause.”). In other words, the Court of Federal
Claims found that through the combination of the 45day deadline and the “no extensions” rule sent with
the award, the solicitation gave the contracting officer
a suitable basis to find Petitioner and the other
contractors in default without having to consider
whether the delay was “excusable.”
11
On appeal before the Federal Circuit, Servant
Health challenged the rationale of the Court of
Federal Claims, arguing that structuring the
solicitation to remove discretion is not permissible.
Servant Health reiterated its points challenging the
purposeful decision to avoid application of the
excusable delay clause and exercising the requisite
discretion.
The Federal Circuit declined to rule on the issue,
stating:
First, the Appellants contend that the
contracting officer abused his discretion
by structuring the solicitation in a way
that effectively removed any instance of
excusable delay. But they failed to raise
this argument before the Court of
Federal Claims. Instead, the Plaintiffs
argued that there were no performancebased reasons for default termination,
but instead that it was pretextual; the
Court of Federal Claims rejected that
argument.
App.18-19 (internal citations omitted). Moreover, the
Federal Circuit found insufficient evidence to find
excusable delay warranted, and accordingly upheld
the lower court’s ruling.
Servant Health, Transcendence, and Noble
Attorney requested a panel rehearing, noting they had
in fact raised and preserved the issue of purposeful
circumvention of a contracting officer’s discretion by
12
adding in requirements that contradicted the FAR.
Nonetheless, Servant Health’s petition for rehearing
was denied on December 6, 2024. App.132-133. On
December 26, 2024, American Medical Equipment
submitted its own rehearing petition, which was
denied by the merit panel on January 17, 2025.
App.130-131. Servant Health alone elected to seek
certiorari and accordingly submits this petition.
SUMMARY OF THE ARGUMENT
This case presents a clear and troubling example
of an executive agency official exceeding statutory
authority by unilaterally eliminating the requirement
to exercise discretion in assessing excusable delay
under a commercial items contract. The contracting
officer’s insertion of a “no extensions” clause
effectively nullified FAR 52.212-4(f)—a regulatory
provision mandated by Congress through 41 U.S.C. §
3307. This unauthorized override constitutes an
executive intrusion into the legislative domain and
undermines the statutory framework governing
federal procurement.
The refusal to consider delays caused by the Suez
Canal blockage—a textbook example of delay by
common
carriers—further
demonstrates
the
contracting officer’s failure to apply binding
regulatory protections. This action not only violated
federal acquisition rules but also harmed both the
contractor and the government by eliminating
flexibility during a global crisis.
In the wake of this Court’s decision in Loper Bright
Enterprises v. Raimondo, agency actions that
13
effectively legislate in contravention of congressional
mandates must be subject to meaningful judicial
review. This case presents an ideal vehicle for
reinforcing the constitutional separation of powers
and ensuring that executive officials remain within
the limits of their delegated authority.
REASONS FOR GRANTING THE PETITION
I. The Federal Circuit’s Decision Conflicts with
Loper Bright and Violates the Separation of
Powers
The Federal Circuit’s decision conflicts with this
Court’s recent holding in Loper Bright Enterprises v.
Raimondo, 603 U.S. 369 (2024), and infringes on the
structural protections of Article II, Section 1, Clause
1. In Loper Bright, the Court reaffirmed that agencies
may not exercise powers not delegated by Congress.
The decision below permits executive branch
contracting officers to override statutory and
regulatory obligations, effectively allowing them to
legislate through contract drafting—a result squarely
at odds with Loper Bright and the Constitution.
II. Executive Officials Lack Authority
Rewrite Statutorily Mandated FAR Clauses
to
Federal law mandates inclusion of the excusable
delay clause in all commercial item contracts. See 41
U.S.C. § 3307; FAR 52.212-4(f). The clause protects
contractors from default when delays are caused by
unforeseeable events, such as the global shipping
crisis triggered by the Suez Canal blockage. As this
Court noted in United States v. Brooks-Callaway Co.,
14
318 U.S. 120, 122 (1943), the excusable delay clause
serves to “remove uncertainty and needless
litigation.”
Congress mandated the inclusion of only a limited
set of clauses in commercial item contracts and
prescribed a narrow process for their modification. 41
U.S.C. § 3307(e); FAR 12.302; FAR 1.403. Tailoring or
deviation must be specifically justified, documented,
and approved. Here, the contracting officer did none of
that. Instead, he inserted the required clause while
simultaneously nullifying it by declaring that “no
extensions will be granted.”
This action was not a valid tailoring under FAR
12.302, nor a permissible deviation under FAR 1.403.
It was an unauthorized and unilateral modification of
statutory and regulatory language by an executive
official acting without legal authority. As this Court
has held, an agency “literally has no power to act ...
unless and until Congress authorizes it to do so by
statute.” FEC v. Cruz, 596 U.S. 289, 301 (2022).
III. The Refusal to Consider Excusable Delay
Violated FAR 52.212-4(f)
The contracting officer not only wrote around the
excusable delay clause, he refused to consider its
application—a clear violation of FAR 52.212-4(f) and
41 U.S.C. § 3307. The Federal Circuit’s approval of
this conduct legitimizes the executive branch’s
circumvention of congressional mandates.
This conduct implicates the core concerns
addressed in Loper Bright: the unauthorized
15
assumption of legislative power by executive agencies.
As the Court stated, the Administrative Procedure
Act 5 was designed “as a check upon administrators
whose zeal might otherwise have carried them to
excesses.” Loper Bright, 603 U.S. at 371 (quoting
Morton Salt, 338 U.S. 632, 644 (1950)).
The VA’s contracting officer exercised judicial,
executive, and legislative power simultaneously. He
nullified federal regulation, refused to exercise
discretion, and then used the resulting default to
pressure Servant Health into concessions. This is not
merely abuse of discretion—it is an unconstitutional
aggregation of power.
IV. This Case Is an Ideal Vehicle to Clarify the
Scope of Loper Bright and Resolve Post-Chevron
Uncertainty
Servant Health presents a clear and contained
example of executive overreach within the framework
of a single statute and regulation: 41 U.S.C. § 3307
and FAR 52.212-4(f). It allows the Court to clarify the
separation of powers boundaries post-Loper Bright,
particularly with respect to legislative intrusions by
administrative agencies.
As Justice Thomas noted in concurrence, Chevron
deference allowed agencies to perform functions
requiring legislative power. Loper Bright, 603 U.S. at
415 (Thomas, J., concurring). The Court should now
5 While Servant Health was decided under the Contract Disputes
Act, and not the Administrative Procedure Act, the same
standard of review—abuse of discretion—applies in both cases.
16
reinforce that agencies may not alter statutory
requirements simply by inserting contradictory
boilerplate into federal contracts.
The FAR is the cornerstone of procurement law,
directly governing the expenditure of public funds.
Congress has defined its structure and application.
The contracting officer’s circumvention of FAR
provisions to impose strict liability in place of
excusable delay obligations strikes at the heart of
Congress’s procurement regime.
This case also offers a necessary opportunity to
provide guidance on the scope of agency authority in
the post-Chevron era. As the Court observed in Loper
Bright, the Chevron framework created pervasive
uncertainty for judges, agencies, and regulated
parties. Loper Bright, 603 U.S. at 405. Servant Health
provides a concrete context for resolving that
uncertainty within a critical area of public law—
federal contracting.
V. Agency Overreach Undermines
Precedent on Separation of Powers
Prior
The decision below cannot be squared with this
Court’s prior rulings in Kisor v. Wilkie, 588 U.S. 558
(2019) and City of Arlington v. FCC, 569 U.S. 290
(2013), both of which acknowledged the functional
overlap of legislative and judicial forms within agency
practice. While Kisor upheld Auer deference and
emphasized that agency actions must still remain
within the scope of delegated executive authority, it
was grounded in the same Chevron-based
jurisprudence that Loper Bright has now overruled.
17
See Kisor, 588 U.S. at 586 (noting that when agencies
act in “legislative” or “judicial” form, they must
remain exercises of executive power). With Chevron no
longer controlling, the assumptions underpinning
Kisor and Arlington deserve reevaluation.
The Court should take this opportunity to reaffirm
that even when agency action mimics other branches,
it must be confined strictly to the execution of laws as
written—not their modification or disregard.
VI. Abuse of Discretion and Preservation of the
Issue Below
The contracting officer’s conduct constitutes
textbook abuse of discretion. As the Federal Circuit
itself recognized in McDonnell Douglas Corp. v.
United States, 182 F.3d 1319, 1327 (Fed. Cir. 1999),
abuse of discretion arises when contracting officers
eliminate rights established by the FAR. Here, the
officer intentionally precluded consideration of
excusable delay, even when Petitioner’s delay resulted
from a textbook example of common carrier
disruption.
Petitioner preserved this issue from the trial court
onward. At summary judgment, Servant Health
expressly argued that the VA never considered an
extension and had predetermined that excusable
delay would not apply. The Court of Federal Claims
upheld the termination on the basis of the VA’s strict
compliance language (that a failure to deliver within
45 days would automatically result in a termination
for cause, and that delay caused by suppliers and
shipping would not be considered). The Federal
18
Circuit declined to reach the abuse of discretion
issue—a decision that warrants correction.
This case presents a clean legal question involving
a defined statutory and regulatory scheme, a
preserved record, and a critical constitutional issue in
the wake of Loper Bright. Certiorari should be
granted.
CONCLUSION
For the foregoing reasons, the petition for a writ of
certiorari should be granted. This case presents an
urgent and appropriate opportunity to clarify the
limits of agency discretion, enforce Congress’s
procurement mandates, and reinforce the separation
of powers now sharpened by the Court’s decision in
Loper Bright. Without intervention, the Federal
Circuit’s ruling leaves in place a dangerous precedent:
allowing individual executive actors to unilaterally
negate statutory protections and wield contract terms
as instruments of coercion, all without Congressional
or judicial oversight. Allowing executive officials to
nullify congressional mandates through contractual
boilerplate threatens the very foundation of Article I
legislative authority and undermines Congress’s
exclusive power to prescribe procurement law. This
Court’s review is essential to restore constitutional
balance and prevent further erosion of Congress’s
legislative authority in federal procurement.
19
April 15, 2025
Respectfully submitted,
ERIC S. MONTALVO*
CAROL A. THOMPSON
FEDERAL PRACTICE GROUP
801 17TH ST. N.W., SUITE 250
WASHINGTON, DC 20006
(202) 862-4360
emontalvo@fedpractice.com
Counsel for Petitioner
*Counsel of Record
This is a copy of a public record, reproduced as it was published. It is not legal advice, and it may not be the version a court would rely on. Check the official source before you cite it.