Amicus Curiae Brief — Seven County Infrastructure Coalition, et al., Petitioners v. Eagle County, Colorado, et al.
Supreme Court briefOct 25, 2024
Ask Donna
What actually matters in this document.
Text
No. 23-975
_________________________________________________
In The Supreme Court of the United States
_________________________________________________
Seven County Infrastructure Coalition, Et Al.,
Petitioners,
v.
Eagle County, Colorado, Et Al.,
Respondents.
_________________________________________________
On Writ of Certiorari to the United States
Court of Appeals for the District of Columbia Circuit
_________________________________________________
BRIEF OF FORMER SENIOR FEDERAL
OFFICIALS AS AMICI CURIAE
SUPPORTING RESPONDENTS
_________________________________________________
James M. Gross
Brenna M. Rosen
FOLEY HOAG LLP
1301 Ave. of the Americas
New York, NY 10019
(212) 812-4000
Beth C. Neitzel
Counsel of Record
Nicole E. Smith
FOLEY HOAG LLP
Seaport West
155 Seaport Blvd.
Boston, MA 02210
(617) 832-1000
bneitzel@foleyhoag.com
Counsel for Amici Curiae
i
TABLE OF CONTENTS
INTEREST OF AMICI CURIAE ................................ 1
INTRODUCTION AND SUMMARY OF
ARGUMENT ............................................................... 2
ARGUMENT ............................................................... 5
I.
NEPA Saves Money, Time, and Lives—Not Just
the Environment. ................................................ 5
A. Projects That Preserve or Restore the
Natural Environment May Also Generate
Enormous Economic Value. .........................7
B. NEPA Makes Economically Advantageous
Projects Even Better. .................................. 12
II.
To The Extent NEPA Should Be (Further)
Revised, Such Work Is Congress’s Domain—And
That Work Is Currently Underway. ................. 24
A. Congress Recently Amended Key Aspects of
NEPA About Which Petitioners
Complain. .................................................... 25
B. Congress Is Considering Legislation That
Would Address Still More of Petitioners’
and Their Amici’s Policy Priorities. ........... 31
CONCLUSION .......................................................... 36
PENDING LEGISLATION APPENDIX
S. 879, 118th Cong. (2023): ....................................... 1a
S. 1449, 118th Cong. (2023) ...................................... 2a
S. 3170, 118th Cong. (2023): ..................................... 8a
H.R. 1, 118th Cong. (2023) ........................................ 9a
ii
H.R. 495, 118th Cong. (2023): ................................. 16a
H.R. 6129, 118th Cong. (2024) ................................ 18a
iii
TABLE OF AUTHORITIES
Cases
Egbert v. Boule,
596 U.S. 482 (2022) .................................... 5, 24, 36
Metro. Edison Co. v. People Against
Nuclear Energy,
460 U.S. 766 (1983) ........................................ 26, 32
Ocean Advocates v. United States Army
Corps of Eng’rs,
402 F.3d 846 (9th Cir. 2004) ................................ 27
Omnicare, Inc. v. Laborers Dist. Council
Constr. Indus. Pension Fund,
575 U.S. 175 (2015) ........................................ 24, 25
SAS Inst., Inc. v. Iancu,
584 U.S. 357 (2018) .................................... 5, 24, 28
Sierra Club v. FHA,
435 F. App’x 368 (5th Cir. 2011).......................... 27
Statutes
42 U.S.C. § 4321 ........................................................ 22
42 U.S.C. § 4331(a) .................................................... 12
42 U.S.C. § 4332 ........................................................ 30
42 U.S.C. § 4332(2)(C) (2022).................................... 26
42 U.S.C. § 4332(2)(C) (2023).................................... 26
42 U.S.C. § 4336(a)(2) ............................................... 29
42 U.S.C. § 4336(b) .................................................... 29
42 U.S.C. § 4336(b)(2) ............................................... 29
42 U.S.C. § 4336a(a)(3) ............................................. 31
42 U.S.C. § 4336a(e) .................................................. 29
iv
42 U.S.C. § 4336a(e)(1) ........................................ 28, 30
42 U.S.C. § 4336a(g) .................................................. 29
42 U.S.C. § 4336a(g)(1)(A) ......................................... 28
42 U.S.C. § 4336a(g)(2).............................................. 28
Fiscal Responsibility Act of 2023, Pub.
L. No. 118-5, Div. C, Title III, § 321,
137 Stat. 38 .......................................................... 25
Grand Canyon National Park. Pub. Law
No. 277, 65 Stat. 1175 (1919) ................................ 7
Water Resources Development Act of
2000, Pub. L. No. 106-541, 114 Stat.
2681 (2000) ............................................................. 8
Rules and Regulations
33 C.F.R. § 385.14 ....................................................... 8
40 C.F.R. § 1500.1(b) ................................................... 2
40 C.F.R. § 1500.1(c) ............................................... 2, 3
40 C.F.R. § 1501.9(a) ................................................. 19
40 C.F.R. § 1502.14(a) ........................................... 6, 12
40 C.F.R. § 1508.1(i)(2).............................................. 27
40 C.F.R. § 1508.1(k) ................................................. 29
Notice of Intent to Prepare an EIS,
64 Fed. Reg. 56306 (Oct. 19, 1999) ...................... 13
Notice of Proposed Rulemaking:
Roadless Area Conservation,
65 Fed. Reg. 30275 (May 10, 2000) ..................... 14
Final Rule and Accord of Decision,
66 Fed. Reg. 3244 (Jan. 12, 2001) ....................... 14
v
Legislative Authorities
H.R. 1, 118th Cong. (2023) ..................... 33, 34, 35, 36
H.R. 495, 118th Cong. (2023) ..................................... 35
The American Resources Act,
H.R. 1335, 118th Cong. (2023-2024)..................... 33
National Environmental Policy Act
Amendments, H.R. 1577, 118th Cong.
(2023-2024) ........................................................... 33
Limit Save Grow Act of 2023,
H.R. 2811, 118th Cong. (2023-2024)..................... 33
H.R. 6129, 118th Cong. (2024) ................................... 35
Countering Communist China Act,
H.R. 7476, 118th Cong. (2023-2024)..................... 33
Lower Energy Costs Act,
S. 947, 118th Cong. (2023-2024) ........................... 33
S. 1449, 118th Cong. (2023) .................... 33, 34, 35, 36
S. 3170, 118th Cong. (2023) ...................................... 36
Other Authorities
2023 National Park Visitor Spending
Effects: Economic Contributions to
Local Communities, States, and the
Nation, National Park Service (Aug.
2024) ....................................................................... 8
A. Masinter, The National
Environmental Policy Act and the
Value of Information, 22 N.Y.U. J.
LEGIS. & PUB. POL’Y 465 (2020) ...................... 12
Bald Mountain Mine Plan of Operations
Amendment Juniper Project, BLM
(Aug. 8, 2024) ....................................................... 30
vi
Commercial Leasing for Wind Power on
the Outer Continental Shelf Offshore
North Carolina – Call for
Information and Nominations,
Docket No. BOEM-2012-0088 (Dec.
13, 2012) ............................................................... 19
Desert Renewable Energy Conservation
Plan, Executive Summary for the
Record of Decision, BLM (Sept. 2016) ........... 15, 16
Desert Renewable Energy Conservation
Plan Proposed Land Use Plan
Amendment and Final EIS, Volume
II (October 2015) .................................................. 15
Douglas H. Strong, Ralph H. Cameron
and the Grand Canyon (Part II),
Arizona and the West, Vol. 20, No. 2
(Spring 1978) .......................................................... 7
Engineering with Nature: An Atlas, U.S.
Army Corps of Engineers (2018) ................... 10, 11
Engineering with Nature: An Atlas, Vol.
2, U.S. Army Corps of Engineers,
(2021). ................................................................... 11
EA for the Proposed Demolition of
Building 330 at Argonne National
Laboratory, DOE/EA-1659 (Aug.
2009) ............................................................... 22, 23
Forest Service Area Conservation: Final
EIS Vol. 1, U.S.D.A., Forest Service
(Nov. 2000) ........................................................... 14
vii
Jeffrey King et. al, Achieving
Sustainable Outcomes Using
Engineering with Nature Principles
and Practices, Integrated
Environmental Assessment and
Management (Aug. 2020) .................................... 11
K. Emerson & E. Baldwin, Effectiveness
in NEPA Decision Making: In Search
of Evidence and Theory, J. ENV.
POL’Y & PLAN. 427 (2019) ............................... 13, 29
L. Caldwell, Beyond NEPA: Future
Significance of the National
Environmental Policy Act, 22 HARV.
ENVTL. L. REV. 203 (1998).................................... 13
Lisa Friedman, Biden Administration
Approves Two Big Solar Projects,
N.Y. Times (Dec. 21, 2021) .................................. 16
Mather Economics, Measuring the
Economic Benefits of America’s
Everglades Restoration (2010) ............................... 9
Michelle Wagner, Kitty Hawk Wants
Offshore Turbines Out of Sight,
Outer Banks Voice (Feb. 13, 2013) ...................... 19
NEPA Success Stories: Celebrating 40
Years of Transparency and Open
Government, The Environmental
Law Institute (Aug. 2010).............................. 17, 18
President Theodore Roosevelt, Remarks
at Grand Canyon, Arizona (May 6,
1903) ....................................................................... 7
viii
Press Release, Dep’t of the Interior,
Biden-Harris Administration
Announces Winners of Carolina
Long Bay Offshore Wind Energy
Auction (May 11, 2022) ........................................ 20
Press Release, Dep’t of the Interior,
BLM Approves Oberon Solar Project,
(Jan. 13, 2022) ...................................................... 16
Press Release, Dep’t of the Interior,
Secretary Jewell Announces
Milestone for Commercial Wind
Energy Development Offshore North
Carolina (Aug. 11, 2014) ..................................... 20
Press Release, Governor DeSantis
Announces $1.5 Billion for
Everglades Restoration and Water
Quality Improvements in Fiscal Year
2024-25 (April 22, 2024) .................................. 9, 10
Press Release, NPS, Timpanogos Cave
National Monument Revisits
Alternatives for Environmental
Assessment (Feb. 1, 2012) ................................... 23
Rob Morris, Energy Agency Moves Wind
Farm Lease Areas Farther Off OBX,
The Outer Banks Voice (Aug. 14,
2004) ............................................................... 19, 20
Sabine Pass to Galveston Bay, Texas
Coastal Storm Risk Management
and Ecosystem Restoration, Final
EIS (2017)............................................................. 18
Statement of Bruce Westerman (RArk.), Chair of House Committee on
Natural Resources (Sept. 11, 2024) ..................... 32
ix
Statement of H. Greczmiel, Former
Associate Director for NEPA
Oversight at CEQ, Oversight
Hearing before the Committee on
Natural Resources, U.S. House of
Representatives (Apr. 25, 2018) .................... 21, 29
Statement of James R. Furnish Before
the United States Senate,
Committee on Energy and Natural
Resources, Subcommittee on Forests
and Public Lands Management (July
26, 2000) ............................................................... 14
STH 26 Final Environmental Impact
Statement (signed June 15, 2005) ....................... 21
The National Academies of Sciences,
Engineering, and Medicine, Progress
Toward Restoring the Everglades:
The Ninth Biennial Review (2022) ........................ 9
Timpanogos Cave National Monument
Long Range Interpretive Plan, NPS,
(Dec. 2010) ............................................................ 23
Timpanogos to Close After Labor Day
for Construction Project, Associated
Press (Aug. 20, 2018) .......................................... 24
U.S. Nuclear Commission, Regulatory
Guide 4.2 (Sept. 2018).......................................... 27
1
INTEREST OF AMICI CURIAE1
Amici are a bipartisan group of former senior
federal officials who interacted frequently with the
National Environmental Policy Act (“NEPA”) while in
office.
Despite divergent political views, amici
agree—based on their extensive experience with
NEPA—that: (I) NEPA makes federal projects better
for all stakeholders and (II) it is Congress’s job, not
this Court’s, to refine NEPA’s framework.
Sally Jewell, Secretary of the Interior, 20132017.
Lynn Scarlett, Deputy Secretary of the
Interior, 2005-2009.
Gregory Jaczko, Chairman of the U.S.
Nuclear Regulatory Commission, 2009-2012.
Jonathan Jarvis, Director of the National
Park Service, 2009-2017.
Dale Hall, Director of the U.S. Fish and
Wildlife Service, 2005-2009.
Jamie Rappaport Clark, Director of the U.S.
Fish and Wildlife Service, 1997-2001.
Thomas L. Tidwell, Chief of the U.S. Forest
Service, 2009-2017.
1 Pursuant to Supreme Court Rule 37.6, counsel represent that
they authored this brief in its entirety and no one else made a
monetary contribution for it.
2
Dave Matsuda, Administrator, 2010-2013,
and Deputy Administrator, 2009-2010, for the
Department
of
Transportation
Maritime
Administration.
Jo-Ellen Darcy, Assistant Secretary of the
Army (Civil Works), 2009-2017.
R. Lyle Laverty, Assistant Secretary of the
Interior for Fish, Wildlife, and Parks, 2007-2009.
Jim Furnish, Deputy Chief of the U.S. Forest
Service, 1999-2002.
INTRODUCTION AND SUMMARY OF
ARGUMENT
NEPA was enacted in 1969 with broad
bipartisan support. Signed into law by President
Nixon, NEPA has been the cornerstone of U.S.
environmental law and federal project management
for more than a half century. It is a procedural law
that seeks to ensure informed and transparent
decision making by federal officials undertaking
major federal actions. To this end, in the small
percentage of federal projects for which NEPA
requires an agency to prepare an Environmental
Assessment (“EA”) or, even more uncommonly, an
Environmental Impact Statement (“EIS”), “[a]ccurate
scientific analysis, expert agency comments, and
public scrutiny” are essential to the process, 40 C.F.R.
§ 1500.1(b). As NEPA’s implementing regulations
make clear, “it is not better documents but better
decisions that count.” Id. at § 1500.1(c). After all,
“NEPA’s purpose is not to generate paperwork—even
3
excellent paperwork—but
action.” Id.
to
foster
excellent
NEPA does not always achieve this aspiration
of excellence. But it does regularly make federal
actions better. One would not know that, however,
from the filings of petitioners and their amici. They
paint NEPA as little more than red tape that foils (or
intractably delays) infrastructure efforts and
economic development generally.
As the undersigned amici can attest, this tale
of wasted time and investment lost is a distorted
one. True, there are real instances of protracted,
years-long EIS review processes. But such cases are
exceedingly rare, corresponding to a tiny fraction of
NEPA reviews. An EIS—the most rigorous NEPA
analysis and the overwhelming target of petitioners’
and
their
amici’s
complaints—is
itself
a
rarity. Among the hundreds of thousands of proposed
federal actions each year, an EIS is prepared for
roughly 200, or less than one percent, of those
projects. See infra p. 29. And in amici’s experience,
the great majority of even EIS processes are vastly
more efficient than petitioners and their amici
suggest.
Similarly off base is petitioners’ fundamental
premise that environmentally informed decision
making
is
anathema
to
economic
development.
History,
amici’s
considerable
experience, and many NEPA reviews reveal that the
environmentally preferable option is sometimes also
the most economically beneficial for taxpayers,
project-developers, and local economies. Even efforts
4
overtly focused on environmental preservation or
restoration
may
yield
enormous
economic
returns. See infra Part I.A.
But NEPA does not expect such symbiosis. And
where it is not possible, NEPA’s function is not to
impede economically or socially advantageous
projects—it is to make them better.
NEPA does so in a variety of ways. In the event
of an EA or EIS, NEPA requires that lead agencies
consider—and take seriously—stakeholder input,
expert analysis, alternative proposals’ costs and
benefits, and, yes, environmental and other
sensitivities. Throughout its process, moreover,
NEPA requires that agencies keep front of mind the
project’s objectives. The result is superior federal
action. Time and again, amici saw NEPA make
projects better for everyone by improving design,
promoting stakeholder interests (including the
interests of those with economic claims), and
deconflicting inter-agency and inter-governmental
concerns. Simply put, NEPA’s process often means
cheaper, safer, more resilient, and even (due to its
deconfliction benefits) faster federal actions. See infra
Part I.B.
Still, amici acknowledge that there is room for
improvement. There are cases—though far fewer
than petitioners suggest—when NEPA does not
achieve its purpose, at least not efficiently. Yet the
job of refining or “right-siz[ing] NEPA” is not for this
Court, as petitioners and their amici would have
it. See, e.g., Brief for the American Exploration &
Mining Association et al. 3. Among other issues, the
5
appropriate scope and duration of NEPA review and
optimal level of interagency consultation are
quintessential policy considerations “properly
addressed to Congress, not this Court.” SAS Inst.,
Inc. v. Iancu, 584 U.S. 357, 369 (2018). The
undersigned amici, based on their extensive NEPA
experience, disagree with many of the policy positions
urged on the other side. But amici recognize that it is
Congress’s prerogative to weigh and resolve such
arguments. See Egbert v. Boule, 596 U.S. 482, 491
(2022).
Besides, Congress is actively doing exactly that,
having substantially amended NEPA just last year.
The revised framework supersedes the version of
NEPA that governed the events and decision below in
this case. Additionally, at least 13 bills to further
revise NEPA are pending at different stages of the
legislative process. If enacted, they would implement
many of the policy changes petitioners and their amici
request. This Court should decline petitioners’
invitation to intrude in this complex and contentious
policy debate, and leave to Congress the work of
shaping NEPA’s future. See infra Part II.
ARGUMENT
I.
NEPA Saves Money, Time, and Lives—
Not Just the Environment.
Petitioners and their amici paint a dismal
picture of NEPA. In their telling, NEPA is a
burdensome waste of money and time that stymies
projects like the proposed railroad tracks at issue
here, the operation of mines, and the building of new
6
roads. Considering a project’s environmental impacts,
they say—whether through “[e]xpanded, wasteful
NEPA analyses” or otherwise—serves only to “hurt
developers, the thousands of employees and
contractors they employ, and the economies they and
their projects support and energize.” Br. of Anschutz
Exploration Corp. 26 (“Anschutz Br.”); see also Petrs.
Br. 50 (describing the decision below as a “threat not
just to the promising project here, but to
infrastructure development in general”). In short,
petitioners and their amici maintain, NEPA’s
requirements benefit only the environment and its
patrons—at the expense of critical infrastructure
needs, industrial development, and local economies.
That argument does not accord with reality.
History, and the experience of the undersigned amici,
are chockful of examples of NEPA improving federal
projects across nearly every metric—enhancing
project design, saving taxpayer and project-developer
dollars, promoting public safety, protecting property
rights, and preserving the natural environment.
NEPA enables agencies to identify superior
proposals and bring them to fruition. In doing so, it
serves not as a barrier to financial gain and economic
development. In fact, NEPA sometimes reveals that
the environmentally preferable option is also the most
profitable. And when that is not the case, or when
such option is incompatible with the project’s aims,
NEPA improves projects by requiring consideration of
stakeholder interests and “reasonable alternatives,”
40 C.F.R. § 1502.14(a). In amici’s experience, that
process frequently yields cheaper, safer, and overall
superior federal actions.
7
A.
Projects That Preserve or Restore
the Natural Environment May Also
Generate
Enormous
Economic
Value.
To begin, contrary to the petitioners’ basic
thesis, it is simply not the case that a project can
result in economic gain or environmental benefit, but
not both. For more than a century, conservation,
restoration, and sustainable infrastructure efforts
have led to enormous positive economic externalities.
Such projects have generated broad bipartisan
support and tremendous economic, social, and
environmental benefits.
1. Take what is now known as Grand Canyon
National Park. When, in 1903, President Theodore
Roosevelt sought to preserve “this great wonder of
nature,” President Theodore Roosevelt, Remarks at
Grand Canyon, Arizona (May 6, 1903),2 some had
other ideas. Those with mining interests fought for
decades to thwart attempts to protect the canyon from
industrial development. See generally Douglas H.
Strong, Ralph H. Cameron and the Grand Canyon
(Part II), Arizona and the West, Vol. 20, No. 2
(Summer 1978). Happily, President Roosevelt’s vision
prevailed when Congress established Grand Canyon
National Park. Pub. Law No. 277, 65 Stat. 1175
(1919). Not only was the Grand Canyon later shown
to possess “no mineral value,” Strong, supra p. 7, at
2 Available at:
https://www.presidency.ucsb.edu/documents/remarks-grandcanyon-arizona.
8
156, it is now widely accepted as one of our country’s
great treasures.
The Park has also proven to be an outstanding
economic investment. According to a peer-reviewed
study, in 2023 alone, more than 4.7 million visitors to
the Grand Canyon brought more than $768 million
dollars in spending to the surrounding economy. 2023
National Park Visitor Spending Effects: Economic
Contributions to Local Communities, States, and the
Nation, National Park Service (“NPS”), at 27 (Aug.
2024).3 That spending, in turn, generated 10,060 jobs,
producing more than $350 million in labor income. Id.
That result is an annual economic output—defined as
the “total estimated value of the production of goods
and services supported by NPS visitor spending”—of
more than $1 billion. Id.
2. Restoration of the Florida Everglades is a
similar story. In 2000, Congress committed more
than $10.5 billion over a 35-year timeline to “restore,
preserve, and protect the south Florida ecosystem”—
an area more than twice the size of New Jersey—
through the Comprehensive Everglades Restoration
Plan (“CERP”). Water Resources Development Act of
2000, Pub. L. No. 106-541, 114 Stat. 2681 (2000). The
plan was an ambitious one, with each phase shaped
by and implemented pursuant to a NEPA analysis.
See 33 C.F.R. § 385.14 (directing the Army Corps of
Engineers to “comply with the requirements of NEPA
3 Available at:
https://www.nps.gov/subjects/socialscience/vse.htm?utm_mediu
m=email&utm_source=govdelivery.
9
and applicable implementing regulations” when
implementing CERP). The restoration work quickly
paid environmental dividends. See generally The
National Academies of Sciences, Engineering, and
Medicine, Progress Toward Restoring the Everglades:
The Ninth Biennial Review (2022). But just as
important are CERP’s economic benefits, owing to the
Everglades’ critical role in desalinating South
Florida’s drinking water and protecting against
damage from hurricane storm surges. According to a
2010 study, every dollar spent on CERP generates an
economic benefit worth four times that amount.
Mather Economics, Measuring the Economic Benefits
of America’s Everglades Restoration, at iii (2010).4
That means that the $10.5 billion allocated pursuant
to CERP “will generate an increase in economic
benefits of approximately $46.5 billion in net present
value,” with benefits potentially as high as “$123.9
billion.” Id.
Given these extraordinary returns, it is
unsurprising that continued investment in CERP has
broad bipartisan support. Earlier this year, Governor
DeSantis committed $1.5 billion for the 2024-25 Fiscal
Year for Everglades restoration, with $614 million
allocated for CERP alone. Press Release, Governor
DeSantis Announces $1.5 Billion for Everglades
Restoration and Water Quality Improvements in
4 Available at:
https://downloads.regulations.gov/FWS-R8NWRS-2016-0063-0811/attachment_9.pdf.
10
Fiscal Year 2024-25 (April 22, 2024).5 As Governor
DeSantis put it: “I am proud to continue making these
investments in Everglades restoration and water
quality that will benefit our state for decades to come.”
Id.
3. The Everglades is hardly the only example
of a natural resource that serves as a protective, and
economically efficient, system. The U.S. Army Corps
of Engineers (“USACE”)—the federal entity tasked
with implementing CERP in accordance with NEPA—
has an entire program devoted to identifying and
implementing
nature-based
solutions
to
infrastructure projects. Known as “Engineering with
Nature,” the program is rooted in modern advances in
engineering and ecology that demonstrate that
environmentally sustainable infrastructure can also
be
the
most
cost-effective
and
socially
beneficial. Through this program, the USACE has,
among many other projects:
x
Restored wetlands in San Pablo Bay,
California, which provide a habitat for
endangered species and improve the quality
of water entering the Bay while also
maintaining
a
buffer
for
flooding.
Engineering with Nature: An Atlas, U.S.
Army Corps of Engineers 68-70 (2018);6
5 Available at:
https://www.flgov.com/2024/04/22/governor-rondesantis-announces-1-5-billion-for-everglades-restoration-andwater-quality-improvements-in-fiscal-year-2024-25/.
6 Available at https://ewn.erdc.dren.mil/atlas-
series/volume/engineering-with-nature-an-atlas-volume-1/.
11
x
Rehabilitated a river in Washington that
provides a migratory and rearing habitat for
salmon
species—important
both
for
ecosystem health and for the region’s
commercial
and
recreational
fishing
industries, id. at 210-12; and
x
Reused dredged sediment from the Buffalo
River to restore wetland vegetation
decimated by decades of industrial
development. The project rehabilitated a
coastal wetland habitat that is home to
threatened wildlife, provided a native seed
bed, and generated “significant cost savings”
by reducing the need for a sediment disposal
facility. Engineering with Nature: An Atlas,
Vol. 2, U.S. Army Corps of Engineers 106
(2021).7
In each instance, the USACE not only “reduce[d]
demands on limited natural resources, and
minimize[d] environmental impacts,” but also
“generat[ed] a diverse array of economic … and social
benefits.” Jeffrey King et. al, Achieving Sustainable
Outcomes Using Engineering with Nature Principles
and Practices, Integrated Environmental Assessment
and Management (Aug. 2020).8
7 Available at:
https://ewn.erdc.dren.mil/atlasseries/volume/engineering-with-nature-an-atlas-volume-2/.
8 Available at:
https://setac.onlinelibrary.wiley.com/doi/10.1002/ieam.4306.
12
B.
NEPA
Makes
Economically
Advantageous Projects Even Better.
Of course, environmental conservation and
restoration do not always go hand-in-hand with
economic gain. And as amici well recognize, there are
times when an infrastructure project or industrial
development effort will benefit the public good, even if
it will harm the environment.
NEPA’s purpose is not to impede such projects.
Rather, its function is to identify the best approach;
i.e., the one that causes the least environmental harm
while also achieving the project’s goals and advancing
stakeholders’ interests—whether they be “social,
economic,” or otherwise. 42 U.S.C. § 4331(a) (NEPA
Congressional Declaration of National Environmental
Policy). Beyond seeking to maintain the environment,
after all, NEPA’s mandate is to help “fulfill the social,
economic, and other requirements of present and
future generations of Americans.” Id.
NEPA accomplishes that goal by requiring
agencies to engage in a reasoned and transparent
decision-making process that accounts for the
interests of all stakeholders. It does so in multiple
ways. By mandating that agencies “[r]igorously
explore and objectively evaluate reasonable
alternatives to the proposed action” when preparing
an EIS, 40 C.F.R. § 1502.14(a), NEPA stands to
“reveal cheaper, more effective, or less damaging
alternatives,”
A.
Masinter,
The
National
Environmental Policy Act and the Value of
Information, 22 N.Y.U. J. LEGIS. & PUB. POL’Y 465,
469 (2020). Likewise, NEPA invites input from
13
parties with vastly divergent perspectives, which
“help[s] to satisfy diverse stakeholders and aid[s] in
avoiding litigation.” K. Emerson & E. Baldwin,
Effectiveness in NEPA Decision Making: In Search of
Evidence and Theory, J. ENV. POL’Y & PLAN. 427, 430
(2019). And, NEPA demands “inter-agency exchange
of information,” as well as “inter-agency cooperation,”
in a setting “where competition and exclusiveness
were once standard practice.” L. Caldwell, Beyond
NEPA: Future Significance of the National
Environmental Policy Act, 22 HARV. ENVTL. L. REV.
203, 207 (1998).
As amici saw time and again while in office, the
result is better overall projects for everyone—
including project developers, taxpayers, property
owners, local communities, and the many individuals
whose safety would have otherwise been jeopardized
by a federal project. The following are just a few
examples of how NEPA has benefitted those groups.
Project Developers and Other Economic
Stakeholders. Some of petitioners’ amici cast NEPA
as a tool used exclusively by “special-interest groups
that oppose oil-and-gas and other mineral
development on public lands.” See, e.g., Anschutz Br.
at 1. Hardly. Project developers, too, have a voice in
the NEPA process.
1. The carve-outs found in the Forest Service’s
“Roadless Rule” are illustrative. In 1999, consistent
with NEPA’s requirements, the Forest Service
initiated rulemaking regarding roadless area
conservation. Notice of Intent to Prepare an EIS, 64
Fed. Reg. 56306 (Oct. 19, 1999). The purpose was to
14
conserve the road-free portions of the National Forest
System by limiting road construction, reconstruction,
and timber harvest within those zones.
See
Statement of James R. Furnish Before the United
States Senate, Committee on Energy and Natural
Resources, Subcommittee on Forests and Public
Lands Management (July 26, 2000).9
As initially proposed, the rule lacked exceptions
for holders of existing mineral leases. See Notice of
Proposed Rulemaking: Roadless Area Conservation,
65 Fed. Reg. 30275 (May 10, 2000).10 During the
NEPA process, however, it became clear that existing
and future holders of such leases required the ability
to construct roads, remove trees, and make other
environmentally impactful changes to extract the
minerals in accordance with their leases. Forest
Service Area Conservation: Final EIS Vol. 1, U.S.D.A.,
Forest Service at 3-259 (Nov. 2000).11 Recognizing the
importance of those interests, the Forest Service
established exceptions for both existing and
prospective mineral leasing activities. See Final Rule
and Accord of Decision, 66 Fed. Reg. 3244, 3256 (Jan.
12, 2001) (allowing “road construction needed in
9 Available at:
https://www.fs.usda.gov/Internet/FSE_DOCUMENTS/stelprdb5
137345.pdf.
10 Available at:
https://www.fs.usda.gov/Internet/FSE_DOCUMENTS/stelprdb5
137342.pdf.
11 Available at:
https://www.fs.usda.gov/Internet/FSE_DOCUMENTS/stelprdb5
057895.pdf.
15
conjunction with the continuation, extension, or
renewal of a mineral lease”).
2. Similarly, as part of the Desert Renewable
Energy Conservation Plan (“DRECP”), lead agencies
delivered significant benefits to project developers
utilizing NEPA’s review process. The DRECP is a
collaborative effort among the U.S. Bureau of Land
Management (“BLM”), the U.S. Fish and Wildlife
Service, and two California state agencies to
“streamline[] permitting of renewable energy
projects” across 22.5 million acres in the Mojave
Desert. DRECP, Executive Summary for the Record
of Decision, BLM, at ES-1 (Sept. 2016).12
In
consultation with federal, state, and local agencies,
tribal governments, and the public, the DRECP
agencies zoned the Mojave Desert to identify
conservation areas, tribal lands, and “development
focus areas”—zones appropriate for utility-scale
renewable energy resource development. Id. at ES-58.
Leveraging the NEPA process, the DRECP
agencies successfully deconflicted the interests of the
many government entities involved, received input
from additional stakeholders, collected all necessary
data, and performed environmental analyses of the
development focus areas—all in advance of receiving
project proposals. See DRECP Proposed Land Use
Plan Amendment and Final EIS, Volume II at II.3-119
12 Available at:
https://eplanning.blm.gov/public_projects/lup/66459/133459/163
123/DRECP_BLM_ROD_Executive_Summary.pdf.
16
(October
2015)13
(highlighting
“interagency
coordination [undertaken] to expedite service and
provide priority processing to [developers]”). This
enabled the DRECP to offer an accelerated approval
process for proposed construction projects within the
focus areas, having already addressed the concerns of
interested parties through NEPA’s framework.
Executive Summary, supra p. 15, at ES-5-6.
BLM has already approved three Mojave
Desert solar projects capable of generating enough
electricity to power nearly 300,000 homes. Lisa
Friedman, Biden Administration Approves Two Big
Solar Projects, N.Y. Times (Dec. 21, 2021);14 Press
Release, Dep’t of the Interior, BLM Approves Oberon
Solar Project (Jan. 13, 2022).15 While beneficial from
an environmental standpoint too, these rapid
approvals were a win for the project developers.
Taxpayers. Taxpayers also gain from NEPA’s
mandate that agencies consider reasonable
alternatives before commencing a project.
1. The Department of Energy’s (“DOE”) shift in
approach to producing tritium—a radioactive gas that
is a key component in nuclear weapons—provides a
dramatic illustration. Because tritium has a decay
13 EISs issued from 2012 onward are available at the following
database: https://cdxapps.epa.gov/cdx-enepaII/public/action/eis/search.
14 Available at:
https://www.nytimes.com/2021/12/21/climate/solar-powerfederal-land-california.htm.
15 Available at:
https://www.blm.gov/press-release/blmapproves-oberon-solar-project.
17
rate of 5.5% per year, it must be continually produced
to maintain nuclear arms. During the Cold War, far
more was needed, so DOE devoted significant
resources to producing and recycling sufficient tritium
to compete in the ever-intensifying arms race. NEPA
Success Stories: Celebrating 40 Years of Transparency
and Open Government, The Environmental Law
Institute, at 33 (Aug. 2010)16. But when the Cold War
ended abruptly, so did DOE’s need for massive
amounts of tritium.
The NEPA process gave DOE the runway it
needed to adapt to the new global order. As thenSecretary of Energy Admiral James Watkins told
Congress in 1992: “Thank God for NEPA because
there were so many pressures to make a selection for
a technology that might have been forced upon us and
that would have been wrong for the country.” Id.
Instead, NEPA ensured that DOE would carefully
evaluate multiple proposals, including those rejected
during the Cold War years because of their inability
to provide then-adequate quantities of tritium. Id.
Taxpayers emerged as the winner. After DOE
cancelled plans to restart an existing production
reactor and prepared EISs on favored alternatives, it
announced that it could meet the nation’s
requirements for tritium production at an existing
nuclear reactor operated by the Tennessee Valley
Authority, combined with processing at the Savannah
River site in South Carolina. Id. That result saved
16 Available at:
https://ceq.doe.gov/docs/getinvolved/NEPA_Success_Stories.pdf.
18
billions of dollars in construction costs and tens of
millions of dollars per year in operation costs, all while
fulfilling the country’s national security needs. Id.
2. Taxpayers are also front of mind for the U.S.
Army Corps of Engineers in carrying out its coastal
initiatives. Many Texas counties have experienced
multiple major coastal storm surge events in recent
years, including from Hurricane Rita in 2005 and
Hurricane Ike in 2008. In response, the USACE
initiated the Sabine Pass to Galveston Bay Coastal
Storm Risk Management Program to reduce
significant human and economic risks from storm
surges. See Sabine Pass to Galveston Bay, Texas
Coastal Storm Risk Management and Ecosystem
Restoration, Final EIS at ES-2, 9-10 (2017). The
Program called for the construction of a new levee
system in Orange County, Texas as well as
improvement projects for existing hurricane flood
protection systems. Id.
Through a NEPA-mandated evaluation of
alternatives, the agency discovered that the
installation of a floodgate—a central component of the
proposed projects—would cost approximately $865
million more than the levee alternative, and would
also include significant operation, maintenance, and
repair costs. Id. ES-5. That cost disparity led USACE
to drop the floodgate from further consideration, once
again saving taxpayers hundreds of millions of
dollars. Id. at ES-27.
Local Communities and Landowners.
NEPA’s implementing regulations require agencies
“to inform the public of an agency’s proposed action,
19
allow for meaningful engagement during the NEPA
process, and ensure decision makers are informed by
the views of the process.” 40 C.F.R. § 1501.9(a). That
public engagement frequently results in project
design changes that address legitimate concerns from
surrounding communities, without jeopardizing the
project’s economic success.
1. NEPA-mandated community engagement
and interagency cooperation played a significant role
in the development of the Kitty Hawk wind farm off
the coast of the Cape Hatteras National Seashore in
North Carolina. In 2012, the Bureau of Ocean Energy
Management (“BOEM”) called for commercial wind
lease proposals that would permit the construction of
wind energy projects on multiple sites along North
Carolina’s coast. See Commercial Leasing for Wind
Power on the Outer Continental Shelf Offshore North
Carolina – Call for Information and Nominations,
Docket No. BOEM-2012-0088 (Dec. 13, 2012).
Not everyone was thrilled—particularly
because BOEM’s initial proposal allowed for leases as
close as six miles from the shore. The town of Kitty
Hawk, for instance, expressed concern over that
proximity. Michelle Wagner, Kitty Hawk Wants
Offshore Turbines Out of Sight, Outer Banks Voice
(Feb. 13, 2013). So did NPS, because turbines within
20 miles of shore would obstruct the views from the
Cape Hatteras National Seashore, including its famed
Bodie Island Lighthouse. Rob Morris, Energy Agency
Moves Wind Farm Lease Areas Farther Off OBX, The
Outer Banks Voice (Aug. 14, 2004).
20
In accordance with NEPA’s public engagement
requirement, however, both the town of Kitty Hawk
and NPS—then led by one of the undersigned amici—
were entitled to express their concerns, and BOEM
was required to listen. Through that engagement,
BOEM agreed to move the proposed lease sites beyond
24 nautical miles off the Kitty Hawk coastline and
33.7 nautical miles off nearby Bodie Island. Id.; see
also Press Release, Dep’t of the Interior, Secretary
Jewell Announces Milestone for Commercial Wind
Energy Development Offshore North Carolina (Aug.
11, 2014) (BOEM “worked with [NPS] to address
concerns regarding potential visual impacts”). That
compromise paved the way for several exceptionally
lucrative, competitively auctioned lease agreements—
with the money again accruing to taxpayers’
benefit. See, e.g., Press Release, Dep’t of the Interior,
Biden-Harris Administration Announces Winners of
Carolina Long Bay Offshore Wind Energy Auction
(May 11, 2022) (“Sale results in $315 million total in
winning bids for two lease areas and a $42 million
investment in domestic supply chain and workforce
training.”).
2. The route occupied by State Highway 26 in
south-central Wisconsin is also illustrative. In 2000,
the Wisconsin Department of Transportation
(“WDOT”) proposed constructing a bypass to address
high rates of traffic congestion along this significant
trucking route. Absent NEPA, the agency would have
done little more than “‘ask[] what the shortest
distance was and buil[d] the road through there.’”
Statement of H. Greczmiel, Former Associate Director
21
for NEPA Oversight at CEQ, Oversight Hearing
before the Committee on Natural Resources, U.S.
House of Representatives, at 31 (Apr. 25, 2018)
(quoting WDOT project manager).17
Instead,
consistent with NEPA’s public engagement mandate,
the agency partnered with members of potentially
affected communities to evaluate a host of “throughtown” and other alternative proposals. See STH 26
Final EIS at 11-5 (signed June 15, 2005) (detailing
public engagement process).18
That process produced a compromise route that
minimized disruption to local communities. The final
route successfully navigated around private lands and
dairy farms, and assuaged communities’ concerns by
avoiding routes through urban centers. Still, the final
route resolved the traffic efficiency concerns that had
sparked the project in the first place. See id. at 11-71
– 11-77 (detailing selected preferred alternative).
According to local residents, such consensus was
possible only because of NEPA.
As one town
supervisor put it: “‘We talked out problems and came
up with solutions that were agreeable to most
participants. The NEPA process has saved us a lot of
money and mitigated many of the externalized
consequences of a freeway expansion project.’”
Greczmiel Statement, supra pp. 20-21, at 31 (quoting
town supervisor).
17 Available at:
https://www.congress.gov/115/chrg/CHRG115hhrg29883/CHRG-115hhrg29883.pdf.
18 Available at:
https://books.google.com/books?id=JA1g7uoPiIkC&pg=RA1PA1&source=gbs_toc_r&cad=2#v=onepage&q&f=false.
22
Public Safety.
When enacting NEPA,
Congress declared that a key purpose of the new law
was to enhance “the health and welfare of man.” 42
U.S.C. § 4321. NEPA achieves that objective in part
by making federal actions safer.
1. NEPA’s process proved critical to the safe
demolition of the former nuclear reactor known as
Chicago Pile 5 at Argonne National Laboratory in
Argonne, Illinois. After the reactor ceased operations,
it was decontaminated and decommissioned following
an EA prepared pursuant to NEPA. See EA for the
Proposed Demolition of Building 330 at Argonne
National Laboratory, DOE/EA-1659 (Aug. 2009) at 2;
see also id. at 1 n.1 (noting initial EA).19 In 2009, the
Department of Energy proposed taking the final step:
demolishing the dormant structure. Id. at 1. That
effort, however, was complicated by the possibility
that demolition would release toxic radionuclides into
the air.
NEPA’s consultation and expert-analysis
requirements ensured that this risk was adequately
addressed to protect the safety of the local community
and on-site workers. Among other mechanisms, the
EA set out steps to ensure compliance with federal
limits on public exposure to radionuclides. Id. at 10.
Those steps included mandating air monitoring at the
building location and site boundaries; the
implementation of airborne contamination controls
such as filters, dust suppression techniques, and the
19 Available at:
https://www.energy.gov/nepa/articles/ea-1659final-environmental-assessment.
23
like; requiring workers to wear personal protective
equipment such as respirators; and providing for postdemolition radiation surveys. Id.
2. NEPA similarly succeeded in protecting the
public in a project at the Timpanogos Cave National
Monument in Utah. In 1991, the Monument’s Visitor
Center burned down, requiring NPS to operate out of
a “temporary” facility for the next two decades. In
2010, NPS approved a new Visitor Center to be built
on essentially the same site as the existing temporary
facility. See Timpanogos Cave National Monument
Long Range Interpretive Plan, NPS, at 6 (Dec. 2010).20
Through the NEPA process, however, NPS
learned that the chosen site posed a much greater risk
of rock falls than NPS initially believed. NPS
announced in 2012 that it had “reevaluated
alternatives for the Environmental Assessment
regarding the construction of a new visitor facility” in
order to “improve visitor and employee safety
from … the rockfall hazard.” Press Release, NPS,
Timpanogos Cave National Monument Revisits
Alternatives for Environmental Assessment (Feb. 1,
2012).21 In the end, NPS decided to build the new
Visitor Center in a new location, thus “put[ting]
visitors out of the path [of] rocks and boulders.”
20 Available at:
https://npshistory.com/publications/tica/lrip-
2010.pdf.
21 Available at:
revisit.htm.
https://www.nps.gov/tica/learn/news/2012-ea-
24
Timpanogos to Close After Labor Day for Construction
Project, Associated Press (Aug. 20, 2018).22
II.
To The Extent NEPA Should Be (Further)
Revised, Such Work Is Congress’s
Domain—And That Work Is Currently
Underway.
None of the above is to say that NEPA is a
perfect law. It is not. And as the briefing in this case
makes clear, reasonable minds disagree on several of
NEPA’s key elements. As this Court has long
recognized, however, such policy considerations are
“properly addressed to Congress, not this Court.” SAS
Inst., Inc. v. Iancu, 584 U.S. 357, 369 (2018);
Omnicare, Inc. v. Laborers Dist. Council Constr.
Indus. Pension Fund, 575 U.S. 175, 193 (2015)
(“Congress gets to make policy, not the courts.”). For
one thing, Congress is “far more competent than the
Judiciary to weigh such policy considerations.” Egbert
v. Boule, 596 U.S. 482, 491 (2022). For another, this
Court’s “authority” to engage in policy making “at all
is, at best, uncertain.” Id.
Bedrock separation-of-powers principles limit
this Court’s role to reviewing whether the D.C.
Circuit’s decision below comports with NEPA’s thenapplicable requirements.
Those principles are
particularly pressing here, where a policy debate
regarding NEPA’s future is currently underway in
Congress.
Just last year, Congress enacted
significant revisions to NEPA that supersede the
NEPA framework in effect during the events at issue
22 Available at:
https://apnews.com/travel-general-news0fd2c794586d4767a08151e5a3757c7e.
25
here. Moreover, at least 13 bills to further amend
NEPA are winding their way through the legislative
process. If enacted, they would implement many of
the policy changes petitioners and their amici
advocate.
In short, were there ever a case for this Court
to tread lightly, this is it. “Congress gets to make
policy, not the courts,” Omnicare, Inc., 575 U.S.
at 193, and here Congress is actively doing just that.
This Court should decline petitioners’ invitation to
intrude in this process.
A.
Congress Recently Amended Key
Aspects of NEPA About Which
Petitioners Complain.
Since the preparation of the EIS underlying
this dispute, Congress overhauled NEPA as part of
the Fiscal Responsibility Act of 2023, Pub. L. No. 1185, Div. C, Title III, § 321, 137 Stat. 38. That overhaul
involved several of the issues underlying petitioners’
challenge here. Specifically, the 2023 amendments:
(1) imposed a standard requiring agencies to evaluate
all “reasonably foreseeable” effects of a proposed
agency action, (2) circumscribed the duration of
environmental reviews and the length of
environmental documents prepared under NEPA, and
(3) reaffirmed the importance of interagency
coordination.
1. Scope of Effects Assessment. Petitioners’
principal objection to the decision below is that NEPA
requires
agencies
to
consider
only
those
environmental effects that the proposed action would
proximately cause—yet, petitioners contend, the D.C.
Circuit required much more. See Petrs.’ Br. 19-30.
26
Petitioners’ chief request is thus for this Court to
clarify that NEPA embodies a proximate causation
standard, “not mere but-for causation.” Petrs. Br. 16.
Since the EIS at issue was drafted, however,
Congress has already amended NEPA to make clear
that agencies need not assess all potential effects
under a but-for causation standard. The previous
iteration of NEPA—which governs this case—
required an agency to consider a proposed action’s
“environmental impact,” as well as “any adverse
environmental effects which cannot be avoided.” 42
U.S.C. § 4332(2)(C) (2022).
The new statutory
language, consistent with longstanding CEQ
regulations, see Br. for the United States 3 (“Gov’t
Br.”), requires agencies to consider “the reasonably
foreseeable environmental effects” and “any
reasonably foreseeable adverse environmental
effects” of a proposed action. 42 U.S.C. § 4332(2)(C)
(2023) (emphasis added).23
Petitioners urge this Court to announce that
NEPA embodies a “more demanding form of
proximate causation,” under which agencies need not
consider effects that are distant in geography or time.
Petrs. Br. 16, 17, 34. But neither NEPA’s pre- nor
post-amendment text supports such a “demanding”
approach. And as amici’s experience confirms, effects
observed many miles from a project’s base or many
23 Although this reasonable foreseeability standard sounds in
proximate causation, NEPA does not employ the same
proximate cause standards as tort law, for the reasons the
government explains. See Gov’t Br. 34-38; see also Metro.
Edison Co. v. People Against Nuclear Energy, 460 U.S. 766, 774
n.7 (1983).
27
years after a project takes place may nonetheless be
“reasonably foreseeable” at the outset.
For starters, any federal action involving the
approval of a mine, dam, power plant, or other facility
with long-term operations will require an agency to
consider and disclose reasonably foreseeable effects
commensurate with those operations—meaning many
years or decades into the future. See, e.g., U.S.
Nuclear Commission, Regulatory Guide 4.2 at ¶ 2.4
(Sept. 2018) (advising that environmental documents
prepared in connection with an application to operate
a nuclear power plant assess long-term effects within
a 50-mile radius of the proposed site).
Yet even a discrete infrastructure project may
have reasonably foreseeable impacts far down the
line. For instance, “[d]evelopment induced by the
construction of a new highway is a secondary effect
that must be considered in the EIS for [a] proposed
highway,” Sierra Club v. FHA, 435 F. App’x 368, 375
(5th Cir. 2011), even if it is difficult to predict exactly
when that development will occur. Likewise, an
agency contemplating the approval of an addition to
an oil refinery dock must evaluate the foreseeable
impact of increased tanker traffic at the dock—and, in
turn, the heightened risk of oil spills. See Ocean
Advocates v. United States Army Corps of Eng’rs, 402
F.3d 846, 868 (9th Cir. 2004). Indeed, there is good
reason that NEPA’s implementing regulations define
“effects” to include “[i]ndirect effects” that are “caused
by the action and are later in time or farther removed
in distance, but are still reasonably foreseeable.” 40
C.F.R. § 1508.1(i)(2) (emphasis added).
In any event, not only has Congress now
incorporated into NEPA a reasonable foreseeability
28
standard, it is contemplating (by way of at least six
separate bills, see infra Part II.B.1) the more
demanding test petitioners urge this Court to
embrace. As those bills reflect, the question whether
NEPA should impose a narrower effects assessment
than reasonable foreseeability involves policy
considerations “properly addressed to Congress, not
this Court,” SAS Inst., 584 U.S. at 369.
2.
Length of NEPA Documents and
Duration of NEPA Review. Petitioners and their
amici complain that lower-court rulings like the
decision below have led to interminable EIS
documents and years-long review processes. Petrs.
Br. 48-51; Anschutz Br. 20-23; Br. of American
Petroleum Institute et al. 25 (“API Br.”). Petitioners
return to this theme time and time again, quipping
that “88 miles of track should not require 3,600 pages
of EIS.” Petrs. Br. 19. Yet in 2023, Congress
responded to this concern, enacting new limits on
NEPA documents and the duration of NEPA review.
The 2023 amendments provide that unless an
EIS is of “extraordinary complexity,” it cannot “exceed
150 pages, not including any citations or appendices.”
42 U.S.C. § 4336a(e)(1). The amendments further
require that an EIS be completed “not later than the
date that is 2 years after the sooner of, as applicable,”
the date the agency determines an EIS is required by
statute, the date the agency notifies an applicant that
an application to establish a right-of-way is complete,
or the date on which the agency “issues a notice of
intent to prepare” the EIS. Id. § 4336a(g)(1)(A).
These deadlines may be extended only “in
consultation with the applicant” and only for “so much
additional time as is necessary to complete” the EIS.
29
Id. § 4336a(g)(2). The revised statute thus addresses
petitioners’ concern that the NEPA process is simply
too long and too burdensome.
To be clear, during amici’s tenure, the EIS
process was far from the morass petitioners suggest.
And having to prepare an EIS, the most
comprehensive
of
NEPA’s
“environmental
documents,” 40 C.F.R. § 1508.1(k); see 42 U.S.C.
§ 4336(b), was (and is) a rare occurrence. The CEQ
estimates that an EIS is required for less than one
percent of all proposed major federal actions.
Greczmiel Statement, supra pp. 20-21, at 20. EAs—
“concise public document[s] … set[ting] forth the basis
of [an] agency’s finding of no significant impact,” 42
U.S.C. § 4336(b)(2)—are more common, accounting
for roughly four percent of proposed major federal
actions. See Greczmiel Statement, supra pp. 20-21, at
20. Still, that leaves 95 percent of proposed projects
requiring neither an EIS nor an EA. Id. In this
overwhelming majority of cases, NEPA requires only
a “categorical exclusion determination,” 40 C.F.R.
§ 1508.1(k), meaning documentation of the agency’s
determination that the proposed action is “excluded
[from NEPA’s EA and EIS review processes] pursuant
to one of the agency’s categorical exclusions [or]
another agency’s categorical exclusions,” 42 U.S.C.
§ 4336(a)(2). In real numbers, this means that tens or
hundreds of thousands of project proposals are
excepted from NEPA review each year via a
categorical exclusion, while only approximately 200
require EIS consideration. K. Emerson, supra p. 13.
Regardless, following the 2023 amendments,
even the seldom-used EIS process has been
significantly streamlined. 42 U.S.C. § 4336a(e), (g).
30
Petitioners’ amici point to one EIS that recently
topped the new 150-page limit, contending that
agencies apparently “view the statutory page limits as
optional,” Anschutz Br. 21-22 & n.9; API Br. 26. But
a single lengthy EIS hardly indicates as much.
Besides, the environmental review for that project
began in 2021—two years before the amendments
were enacted.
Bald Mountain Mine Plan of
Operations Amendment Juniper Project, BLM (Aug.
8, 2024) (noting Feb. 11, 2021 start date).24 Going
forward, an EIS may exceed the cap only in cases of
“extraordinary complexity.” 42 U.S.C. § 4336a(e)(1).
3. Cooperation Between Agencies. Finally,
petitioners urge the Court to announce limits on interagency cooperation based on the so-called “rule of
reason.” Petrs. Br. 45-46. In petitioners’ view,
agencies should consult with one another only with
respect to the particular effects petitioners believe
“the proponent agency is supposed to study under
NEPA.” Id. But here, too, Congress has recently
spoken—just not in the way petitioners and their
amici would have liked.
Although NEPA has long required lead
agencies to “consult with and obtain the comments of
any Federal agency which has jurisdiction by law or
special expertise with respect to any environmental
impact involved,” 42 U.S.C. § 4332 (emphasis added),
Congress recently expanded the consultation
prerogative of lead agencies to encompass non-federal
entities. Following the 2023 amendments, a lead
agency may “designate . . . any Federal, State, Tribal,
24 Available at: https://eplanning.blm.gov/eplanning-
ui/project/2011567/510.
31
or local agency that has jurisdiction by law or special
expertise with respect to any environmental
impact . . . as a cooperating agency.” 42 U.S.C.
§ 4336a(a)(3) (emphasis added).
For the reasons outlined supra pp. 13, 19-20,
amici view inter-agency consultation in the NEPA
process as invaluable. During amici’s time in office,
such cooperation led again and again to critical project
improvements and time-saving inter-agency and
inter-governmental deconfliction. Id. Amici therefore
applaud Congress’s decision to empower lead agencies
to leverage the expertise of a broader array of
government officials—and would disagree with efforts
to limit this authority. But whatever the future policy
determination on this point, amici recognize that it is
just that: a policy choice that rightfully belongs to
Congress.
B.
Congress Is Considering Legislation
That Would Address Still More of
Petitioners’ and Their Amici’s
Policy Priorities.
Other policy preferences that petitioners and
their amici urge this Court to adopt are the subject of
pending legislation in Congress. Proposals that were
not enacted as part of the 2023 amendments are
expected to be reintroduced when the next Congress
convenes.
Indeed, just last month, the House
Committee on Natural Resources held a full
committee legislative hearing on three NEPA-related
bills in an effort to “tak[e] major steps to reform the
NEPA process.” Statement of Bruce Westerman (RArk.), Chair of House Committee on Natural
32
Resources (Sept. 11, 2024).25 According to Chairman
Westerman, additional amendments to NEPA are
needed
to
“streamlin[e]
permitting
for
crucial infrastructure projects and eliminat[e]
bureaucratic
red
tape
that
is
holding
back development of our domestic energy and mineral
resources.” Id.
These bills make clear that petitioners and
their amici are asking this Court to wade into a policy
debate—not simply to apply a since-superseded
version of NEPA to the facts of this case. For their
part, the undersigned amici believe that many of
these bills are misguided and would leave NEPA
unable to deliver its intended benefits. Still, amici
recognize that it is for Congress to evaluate the
proposals’ costs and benefits—and that it is to
Congress that the parties here and their amici must
direct their policy arguments.
The Court should decline petitioners’ invitation
to enter this policy debate. Just as it recognized in
Metropolitan Edison that NEPA is not the place for
policy disputes, 460 U.S. at 777, nor is this Court.
Rather, “[t]he political process … provides the
appropriate forum in which to air policy
disagreements.” Id.
1. Scope of effects. Congress is considering
further refinements to the reasonably foreseeable
standard it adopted in NEPA in 2023. H.R. 1, along
with five bills that contain identical text (collectively,
25 Available at:
https://naturalresources.house.gov/news/documentsingle.aspx?
DocumentID=416501.
33
the “strict causation bills”),26 would limit the effects
an agency must consider to “reasonably foreseeable
environmental effects with a reasonably close causal
relationship to the proposed agency action.” H.R. 1,
118th Cong., § 20202(a) (2023) (emphasis added); see
also S. 1449, 118th Cong., § 2(b) (2023) (limiting the
definition of environmental “effects” to those that
“have a proximate causal relationship”).27
In line with the policy objectives of petitioners
and their amici, see Petrs. Br. 31-39; API Br. 21-22,
the strict causation bills—one of which has passed the
House of Representatives—would also limit the scope
of effects deemed “reasonably foreseeable” by
redefining that term. These bills would define
“reasonably foreseeable” to include only those effects
that are “likely to occur” (1) within “10 years after the
lead agency begins preparing the environmental
document” and (2) within “an area directly affected by
the proposed agency action such that an individual of
ordinary prudence would take such occurrence into
account in reaching a decision,” e.g., H.R. 1, §
20202(b). In addition, the strict causation bills and S.
1449 would limit consideration of environmental
effects to those that “(i) occur on Federal land or (ii)
Additional bills with text identical to H.R. 1 include The
American Resources Act (H.R. 1335), the National
Environmental Policy Act Amendments (H.R. 1577), the Limit
Save Grow Act of 2023 (H.R. 2811), the Countering Communist
China Act (H.R. 7476), and the Lower Energy Costs Act (S. 947).
26
27 To be clear, these bills were pending when Congress enacted
the recent amendments in 2023, so Congress plainly declined to
incorporate the “reasonably close causal relationship” language
into the current iteration of NEPA.
34
are subject to Federal control and responsibility.”
E.g., id.; S. 1449, § 2(g).
2.
Study of effects, risks, or factors
outside an agency’s control. Petitioners and their
amici further object to the decision below because,
they contend, it requires agencies to study alternative
actions that fall outside the agency’s regulatory
jurisdiction. See Petrs. Br. 44-49; Anschutz Br. 11-19;
API Br. 8-20. In this respect, too, Congress is
considering amending NEPA.
Each of the strict causation bills would require
an agency to review only alternatives to a proposed
project that “are within the jurisdiction of the [lead]
agency.” E.g., H.R. 1, § 20202(a). Similarly, S. 1449
would limit agencies to considering “technically
feasible alternatives in the jurisdiction and authority
of the [lead] Federal Agency.” S. 1449, § 2(b). And in
the context of NEPA review for a proposed oil or gas
lease, the strict causation bills would outright
preclude agencies from “consider[ing] downstream,
indirect effects of oil and gas consumption.” E.g., H.R.
1, § 20215.
3. Further shortening the duration of
review. If Congress’s efforts to shorten the window
for NEPA review in the 2023 amendments do not
satisfy petitioners and their amici, see Petrs. Br. 6;
Anschutz Br. 22-23, 29; API Br. 7, 24-25, pending
proposals would tighten the timeframe still more. The
strict causation bills would preclude an agency from
extending a deadline to continue environmental
review unless it first obtained the approval of the
applicant. E.g., H.R. 1, § 20202(b). And if an agency
were to miss a deadline, these bills would require the
agency to pay $100 per day to the applicant for every
35
day past the deadline that NEPA review continues.
E.g., id.; see also S. 1449, § 3(d)(1) (similar).
Proposals to better monitor EIS timelines are
also pending. H.R. 6129, for instance, would require
the CEQ to publish data regarding the time agencies
took to complete environmental reviews during the
previous decade. H.R. 6129, § 2. Such data would
provide Congress additional information relevant to
understanding and refining NEPA’s operation.
4. Containing the costs of NEPA review.
Congress is considering proposals that would curtail
the costs associated with NEPA review—and thus
address another of petitioners’ and their amici’s
concerns. See Petrs. Br. 4-9; Anschutz Br. 26-28. To
monitor the costs of NEPA review, the strict causation
bills and S. 1449 would require agencies to state in
every EIS the estimated total costs of preparing the
document. E.g., H.R. 1, § 20202(b); S. 1449, § 3(d)(1).
Pending legislation would also redistribute certain
costs to states, other non-federal entities, and project
sponsors. See H.R. 495, 118th Cong., § 2 (2023)
(states); H.R. 1, § 20209 (non-federal entities);
S. 1449, § 3(g) (sponsors). And many other proposals
pending in Congress—from those limiting the effects
and risks agencies must consider to those further
constraining the review period, see supra Parts II.B.13—would also decrease the costs of NEPA review.
5.
Limiting judicial review.
Finally,
pending legislation would limit litigation over NEPA’s
requirements. The strict causation bills, for example,
would permit a would-be plaintiff to file suit only if
the plaintiff had submitted comments during the
administrative proceedings that “were sufficiently
detailed to put the lead agency on notice of the issue
36
upon which the party seeks judicial review.” E.g.,
H.R. 1, § 20202(b); see also S. 1449, §§ 3(d)(1), 3(h)
(requiring same and calling for accelerated judicial
review under limited circumstances when review is
permitted); S. 3170, 118th Cong., § 4 (2023)
(eliminating all “judicial right of action” under NEPA
for project approvals following an EA or EIS).
The strict causation bills would also
significantly limit the injunctive relief permitted
under NEPA. They provide that no EA or EIS “shall
be vacated or otherwise limited, delayed, or enjoined
unless a court concludes allowing such proposed
action will pose a risk of an imminent and substantial
environmental harm and there is no other equitable
remedy available as a matter of law.” E.g., H.R. 1,
§ 20202(b).
*
*
*
In sum, petitioners’ arguments and requested
relief intrude on a policy debate that is complex,
fraught, and actively underway right where it
belongs—in Congress. It is for this Court to assess
whether the D.C. Circuit properly applied the prior
version of NEPA to the facts of this case. It is for
Congress to “weigh such policy considerations” as
petitioners and their amici urge here, Egbert, 596 U.S.
at 491, and to decide NEPA’s future.
CONCLUSION
For the foregoing reasons, the Court should
recognize NEPA’s considerable value and leave to
Congress the work of further refining NEPA’s
requirements.
37
Respectfully submitted.
James M. Gross
Brenna M. Rosen
FOLEY HOAG LLP
1301 Ave. of the Americas
New York, NY 10019
(212) 812-4000
Beth C. Neitzel
Counsel of Record
Nicole E. Smith
FOLEY HOAG LLP
Seaport West
155 Seaport Blvd.
Boston, MA 02210
(617) 832-1000
bneitzel@foleyhoag.com
Counsel for Amici Curiae
October 25, 2024
PENDING LEGISLATION APPENDIX
i
TABLE OF CONTENTS
S. 879, 118th Cong. (2023): ....................................... 1a
S. 1449, 118th Cong. (2023) ...................................... 2a
S. 3170, 118th Cong. (2023): ..................................... 8a
H.R. 1, 118th Cong. (2023) ........................................ 9a
H.R. 495, 118th Cong. (2023): ................................. 16a
H.R. 6129, 118th Cong. (2024) ................................ 18a
1a
1. The cited portions of S. 879, 118th Cong. (2023)
provide:
SEC. 106.
IMPACTS.
DOMESTIC
ENVIRONMENTAL
(a) IN GENERAL.—Section 102(2) of the National
Environmental Policy Act of 1969 (42 U.S.C. 4332(2))
is amended—
...
(2) in subparagraph (F), by inserting “in any
proposal or other major Federal action that
involves the funding or development of projects
outside the United States or the exclusive
economic zone of the United States,” before
“recognize”.
....
2a
2. The cited portions of S. 1449, 118th Cong.
(2023) provide:
SEC. 2. MODERNIZING THE NATIONAL
ENVIRONMENTAL POLICY ACT OF 1969.
(a)
EXISTING NEPA REQUIREMENTS.—Section
102(2) of the National Environmental Policy Act of
1969 (42 U.S.C. 4332(2)) is amended—
...
(7) by striking subparagraph (G) (as so redesignated)
and inserting the following:
“(G) consistent with the requirements of this Act,
study, develop, and describe technically feasible
alternatives in the jurisdiction and authority of the
Federal agency;”
...
(b) DEFINITIONS.—The National Environmental
Policy Act of 1969 is amended by inserting after
section 2 (42 U.S.C. 4321) the following:
SEC. 3 DEFINITIONS.
In this Act:
...
(6) EFFECTS.—
(A) IN GENERAL.—The term ‘effects’ means
changes to the human environment as a result of a
proposed agency action or an alternative, as
applicable, to be carried out by a Federal agency
that—
(i) are reasonably foreseeable, including
changes that may occur not later than 10 years
after the date on which the lead agency begins
3a
preparing an environmental document in an
area directly affected by the proposed agency
action or alternative, as applicable, such that
an individual of ordinary prudence would take
such occurrence into account in reaching a
decision; and
(ii) have a proximate causal relationship to the
proposed agency action or an alternative, as
applicable.
(B) REQUIREMENT.—For purposes of subparagraph
(A)(ii), a ‘but for’ causal relationship is insufficient
to establish a proximate causal relationship.
...
(d)
ENVIRONMENTAL
REQUIREMENTS.—
IMPACT
STATEMENT
(1) IN GENERAL.—Title I of the National
Environmental Policy Act of 1969 (42 U.S.C. 4331 et
seq.) (as amended by subsection (c)) is amended by
adding at the end the following:
SEC.
107.
ENVIRONMENTAL
STATEMENT REQUIREMENTS.
IMPACT
...
(b) COVER SHEET.— The cover sheet for an
environmental impact statement shall include a
statement of the estimated total cost of preparing the
environmental impact statement, including the costs
of Federal agency full-time equivalent personnel
hours, contractor costs, and other direct costs.
...
(d) TIMELINE FOR PREPARING AN ENVIRONMENTAL
IMPACT STATEMENT.—
4a
. . . (2) FAILURE TO ACT.—
(A) IN GENERAL.— If a Federal agency fails to
publish a final environmental impact
statement or notice of availability of the final
environmental impact statement in accordance
with the timeline described in paragraph (1),
and the timeline has not been extended in
accordance
with
paragraph
(3),
the
requirements of this title shall be deemed to
have been fulfilled for the major Federal action.
(B) NO JUDICIAL REVIEW.— A major Federal
action deemed to fulfill the requirements of this
title under subparagraph (A) shall not be
subject to judicial review under this title or
subchapter II of chapter 5, and chapter 7, of
title 5, United States Code (commonly known
as the ‘Administrative Procedure Act’).
(3) EXTENSION.—The timeline established under
paragraph (1) may only be extended if—
(A) the extension is requested, in writing, by
the project sponsor; and
(B) the applicable Federal agency concurs, in
writing, with the extension.
(e) SPECIFICITY OF COMMENTS AND INFORMATION.—
...
(3) UNEXHAUSTED AND FORFEITED COMMENTS.—
Comments and objections not provided within a
comment period described in paragraph (1)—
(A) shall be considered unexhausted and
forfeited; and
5a
(B) shall not be grounds for judicial review.
...
(g) EFFICIENT REVIEWS.—Title I of the National
Environmental Policy Act of 1969 (42 U.S.C. 4331 et
seq.) (as amended by subsection (f)) is amended by
adding at the end the following:
SEC. 111. EFFICIENT REVIEWS.
...
(c)
SCOPE OF REVIEW.—In
developing
an
environmental document for a proposed agency
action, the lead agency and any other involved
Federal agencies shall only consider the effects of the
proposed agency action that—
(1) occur on Federal land; or
(2) are subject
responsibility.
to
Federal
control
and
(d) PROJECT SPONSOR PREPARATION.—
(1) IN GENERAL.— A lead agency shall allow a
project sponsor to prepare an environmental
document for a proposed agency action on request
of the project sponsor.
(2) GUIDANCE.— A lead agency may provide a
project sponsor that elects to prepare an
environmental document under paragraph (1)
with appropriate guidance and assistance in the
preparation of that environmental document.
(3) INDEPENDENT VERIFICATION.—A lead agency
shall—
6a
(A) independently evaluate the environmental
document prepared by a project sponsor under
paragraph (1); and
(B) take responsibility for the contents of the
environmental document on adoption.
(h) JUDICIAL REVIEW.—Title I of the National
Environmental Policy Act of 1969 (42 U.S.C. 4331 et
seq.) (as amended by subsection (g)) is amended by
adding at the end the following:
SEC. 112. JUDICIAL REVIEW.
...
(d) DEADLINE FOR RESOLUTION.—A district court of
the United States shall render a final judgment on a
covered cause of action—
(1) as expeditiously as practicable; and
(2) not later than the date that is 180 days after
the date on which the covered cause of action is
filed.
(e) APPELLATE REVIEW.— A court of appeals of the
United States shall render final judgment on a
covered cause of action subject to its original
jurisdiction or an interlocutory order or final
judgment, decree, or order of a district court of the
United States in a covered cause of action—
(1) as expeditiously as practicable; and
(2) not later than the date that is 180 days after
the date on which the applicable interlocutory
order or final judgment, decree, or order of the
district court was issued.
(f) REMANDED ACTIONS.—
7a
(1) IN GENERAL.—If a court of competent
jurisdiction remands a record of decision, a finding
of no significant impact, or an authorization under
this title to a Federal agency, the court shall set a
reasonable schedule and deadline for the Federal
agency to act on remand, which shall not exceed
180 days from the date on which the order of the
court was issued.
(2)
EXPEDITED TREATMENT OF REMANDED
head of the Federal agency to
which a court remands a record of decision, a
finding of no significant impact, or an
authorization under paragraph (1) shall take such
actions as may be necessary to provide for the
expeditious disposition of the action on remand in
accordance with the schedule and deadline set by
the court under that paragraph.
ACTIONS.—The
....
8a
3. The cited portions of S. 3170, 118th Cong.
(2023) provide:
SEC. 4. JUDICIAL STANDING UNDER NEPA.
Title I of the National Environmental Policy Act of
1969 (42 U.S.C. 4331 et seq.) is amended by adding at
the end the following:
SEC. 112. JUDICIAL STANDING.
Nothing in this title, or any environmental review (as
defined in section 2 of the REPAIR Act of 2023) carried
out pursuant to this title, provides a judicial right of
action under this title or subchapter II of chapter 5,
and chapter 7, of title 5, United States Code
(commonly known as the ‘Administrative Procedure
Act’), relating to the approval of an authorization (as
defined in that section) for a project (as defined in that
section) that uses an applicable environmental review
(as so defined).
....
9a
4. The cited portions of H.R. 1, 118th Cong.
(2023) provide:
SEC. 20202. BUILDER ACT.
(a)
PARAGRAPH (2) OF SECTION 102.—Section
102(2) of the National Environmental Policy Act of
1969 (42 U.S.C. 4332(2)) is amended—
...
(3) in subparagraph (C)—
...
(B) by striking clauses (i) through (v) and inserting
the following:
(i) reasonably foreseeable environmental
effects with a reasonably close causal
relationship to the proposed agency action;
(ii) any reasonably foreseeable adverse
environmental effects which cannot be avoided
should the proposal be implemented;
(iii) a reasonable number of alternatives to the
proposed agency action, including an analysis
of any negative environmental impacts of not
implementing the proposed agency action in
the case of a no action alternative, that are
technically and economically feasible, are
within the jurisdiction of the agency, meet the
purpose and need of the proposal, and, where
applicable, meet the goals of the applicant;
(iv) the relationship between local short-term
uses of man's environment and the
maintenance and enhancement of long-term
productivity; and
10a
(v) any irreversible and irretrievable
commitments of Federal resources which would
be involved in the proposed agency action
should it be implemented.
...
(b) NEW SECTIONS.—Title I of the National
Environmental Policy Act of 1969 (42 U.S.C. 4321 et
seq.) is amended by adding at the end the following:
...
SEC. 107. TIMELY AND UNIFIED FEDREAL
REVIEWS.
...
(b) ONE DOCUMENT.—
...
(3) SCOPE OF REVIEW.—In developing an
environmental document for a proposed agency
action, the lead agency and any other involved
Federal agencies shall only consider the effects of
the proposed agency action that—
(A) occur on Federal land; or
(B) are subject
responsibility.
to
Federal
control
and
...
(e) ESTIMATED TOTAL COST.—The cover sheet for each
environmental impact statement shall include a
statement of the estimated total cost of preparing
such environmental impact statement, including the
costs of agency full-time equivalent personnel hours,
contractor costs, and other direct costs.
...
11a
(h) DEADLINES.—
...
(2) DELAY.—A lead agency that determines it is not
able to meet the deadline described in paragraph
(1) may extend such deadline with the approval of
the applicant. If the applicant approves such an
extension, the lead agency shall establish a new
deadline that provides only so much additional
time as is necessary to complete such
environmental impact statement or environmental
assessment.
(3) EXPENDITURES FOR DELAY.— If a lead agency is
unable to meet the deadline described in
paragraph (1) or extended under paragraph (2),
the lead agency must pay $100 per day, to the
extent funding is provided in advance in an
appropriations Act, out of the office of the head of
the department of the lead agency to the applicant
starting on the first day immediately following the
deadline described in paragraph (1) or extended
under paragraph (2) up until the date that an
applicant approves a new deadline. This
paragraph does not apply when the lead agency
misses a deadline solely due to delays caused by
litigation.
...
SEC. 108. JUDICIAL REVIEW.
(a) LIMITATIONS ON CLAIMS.— Notwithstanding any
other provision of law, a claim arising under Federal
law seeking judicial review of compliance with this
Act, of a determination made under this Act, or of
Federal action resulting from a determination made
under this Act, shall be barred unless—
12a
(1) in the case of a claim pertaining to a proposed
agency action for which—
(A) an environmental document was prepared
and an opportunity for comment was provided;
(B) the claim is filed by a party that
participated in the administrative proceedings
regarding such environmental document; and
(C) the claim—
(i) is filed by a party that submitted a
comment during the public comment period
for such administrative proceedings and
such comment was sufficiently detailed to
put the lead agency on notice of the issue
upon which the party seeks judicial review;
and
(ii) is related to such comment;
...
(e) REMAND.—Notwithstanding any other provision
of law, no proposed agency action for which an
environmental document is required shall be vacated
or otherwise limited, delayed, or enjoined unless a
court concludes allowing such proposed action will
pose a risk of an imminent and substantial
environmental harm and there is no other equitable
remedy available as a matter of law.
SEC. 109. DEFINITIONS.
In this title:
...
(13)
REASONABLY
FORESEEABLE.—The
term
‘reasonably foreseeable’ means likely to occur—
13a
(A) not later than 10 years after the lead agency
begins preparing the environmental document;
and
(B) in an area directly affected by the proposed
agency action such that an individual of ordinary
prudence would take such occurrence into account
in reaching a decision.
...
SECTION 20209. FUNDING TO PROCESS
PERMITS AND DEVELOP INFORMATION
TECHNOLOGY.
(a) IN GENERAL.—In fiscal years 2023 through 2025,
the Secretary of Agriculture (acting through the
Forest Service) and the Secretary of the Interior, after
public notice, may accept and expend funds
contributed by non-Federal entities for dedicated
staff, information resource management, and
information technology system development to
expedite the evaluation of permits, biological
opinions, concurrence letters, environmental surveys
and studies, processing of applications, consultations,
and other activities for the leasing, development, or
expansion of an energy facility under the jurisdiction
of the respective Secretaries.
(b) EFFECT ON PERMITTING.—In carrying out this
section, the Secretary of the Interior shall ensure that
the use of funds accepted under subsection (a) will not
impact impartial decision making with respect to
permits, either substantively or procedurally.
(c) STATEMENT FOR FAILURE TO ACCEPT OR EXPEND
FUNDS.— Not later than 60 days after the end of the
applicable fiscal year, if the Secretary of Agriculture
(acting through the Forest Service) or the Secretary of
14a
the Interior does not accept funds contributed under
subsection (a) or accepts but does not expend such
funds, that Secretary shall submit to the Committee
on Natural Resources of the House of Representatives
and the Committee on Energy and Natural Resources
of the Senate a statement explaining why such funds
were not accepted, were not expended, or both, as the
case may be.
(d) PROHIBITION.—Notwithstanding any other
provision of law, the Secretary of Agriculture (acting
through the Forest Service) and the Secretary of the
Interior may not accept contributions, as authorized
by subsection (a), from non-Federal entities owned by
the Communist Party of China (or a person or entity
acting on behalf of the Communist Party of China).
(e) REPORT ON NON-FEDERAL ENTITIES.—Not later
than 60 days after the end of the applicable fiscal year,
the Secretary of Agriculture (acting through the
Forest Service) and the Secretary of the Interior shall
submit to the Committee on Natural Resources of the
House of Representatives and the Committee on
Energy and Natural Resources of the Senate a report
that includes, for each expenditure authorized by
subsection (a)—
(1) the amount of funds accepted; and
(2) the contributing non-Federal entity.
...
SECTION 20215. SCOPE OF ENVIRONMENTAL
REVIEWS FOR OIL AND GAS LEASES.
An environmental review for an oil and gas lease or
permit prepared pursuant to the requirements of the
National Environmental Policy Act of 1969 (42 U.S.C.
4321 et seq.) and its implementing regulations—
15a
(1) shall apply only to areas that are within or
immediately adjacent to the lease plot or plots and
that are directly affected by the proposed action;
and
(2) shall not require consideration of downstream,
indirect effects of oil and gas consumption.
....
16a
5. The cited portions of H.R. 495, 118th Cong.
(2023) provide:
SEC. 2 ASSIGNMENT TO STATES OF FEDERAL
ENVIRONMENTAL
REVIEW
RESPONSIBILITIES.
Title I of the National Environmental Policy Act of
1969 (42 U.S.C. 4331 et seq.) is amended by adding at
the end the following new section:
SEC. 106 ASSIGNMENT TO STATES OF
ENVIRONMENTAL
REVIEW
RESPONSIBILITIES WITH RESPECT TO
CERTAIN PROJECTS IN THE STATE.
(a) Assumption Of Responsibility.—
(1) IN GENERAL.— Subject to the other provisions of
this section, with the written agreement of the
responsible Federal official and a State, which may
be in the form of a memorandum of understanding,
the responsible Federal official may assign, and
the State may assume, the responsibilities of the
responsible Federal official under this Act with
respect to one or more covered Federal projects of
the responsible Federal official within the State.
(2) ADDITIONAL RESPONSIBILITY.— If a State
assumes responsibility under paragraph (1) the
responsible Federal official may assign to the
State, and the State may assume, all or part of the
responsibilities of the responsible Federal official
for environmental review, consultation, or other
action required under any Federal environmental
law pertaining to the review or approval of covered
projects of the responsible Federal official.
17a
(3)
PROCEDURAL
AND
SUBSTANTIVE
REQUIREMENTS.—
A
State
shall
assume
responsibility under this section subject to the
same procedural and substantive requirements as
would apply if that responsibility were carried out
by the responsible Federal official.
(4) FEDERAL RESPONSIBILITY.— Any responsibility
of the responsible Federal official not explicitly
assumed by the State by written agreement under
this section shall remain the responsibility of the
responsible Federal official.
(5) NO EFFECT ON AUTHORITY.— Nothing in this
section preempts or interferes with any power,
jurisdiction, responsibility, or authority of an
agency, other than the agency of the responsible
Federal official for a covered Federal project, under
applicable law (including regulations) with respect
to the project.
....
18a
6. The cited portions of H.R. 6129, 118th Cong.
(2024) provide:
SEC. 2. ANNUAL REPORT ON NEPA’S IMPACT
ON PROJECTS.
Section 201 of the National Environmental Policy Act
of 1969 (42 U.S.C. 4341) is amended to read as follows:
SEC. 201. ANNUAL REPORT
IMPACT ON PROJECTS.
ON
NEPA’S
(a) REPORT REQUIRED.— Beginning July 1, 2024, the
Council on Environmental Quality shall annually
publish on the website of the Council on
Environmental Quality, and submit to Congress, a
report on—
...
(3) the timelines to complete environmental
reviews pursuant to section 102(2)(C) during the
period of 10 years that ends on June 1 of the
current year, which shall include—
(A) with respect to each major Federal action
commenced during such period of 10 years, the
date on which (as applicable)—
(i) the notice of intent to prepare the
environmental impact statement was
published in the Federal Register;
(ii) the draft environmental impact
statement was published in the Federal
Register;
(iii) the final environmental impact
statement was published in the Federal
Register; and
19a
(iv) the record of decision was published in
the Federal Register;
(B) the average and median publication
timelines during such period of 10 years for
each document described in subparagraph (A);
and
(C) a description of trends in completion times
during such period of 10 years for such
documents compared to prior reports published
by the Council on Environmental Quality.
....
This is a copy of a public record, reproduced as it was published. It is not legal advice, and it may not be the version a court would rely on. Check the official source before you cite it.