Amicus Curiae Brief — Seven County Infrastructure Coalition, et al., Petitioners v. Eagle County, Colorado, et al.
Supreme Court briefSep 4, 2024
Ask Donna
What actually matters in this document.
Text
No. 23-975
In the Supreme Court of the United States
_____________________
SEVEN COUNTY INFRASTRUCTURE COALITION, ET AL.,
Petitioners,
v.
EAGLE COUNTY, ET AL.,
Respondents.
_____________________
On Writ of Certiorari to the U.S. Court of Appeals
for the D.C. Circuit
______________________
BRIEF OF LAW PROFESSORS AS AMICI CURIAE
IN SUPPORT OF PETITIONERS
______________________
Richard A. Epstein
New York University
16 Thomas Place
Norwalk, CT 06853
James W. Coleman
University of Minnesota
229 19th Ave. South
Minneapolis, MN 55455
Mario A. Loyola
Counsel of Record
Florida International University
11200 SW 8th St.
Miami, FL 33199
(305) 472-2700
mloyola@fiu.edu
i
QUESTION PRESENTED
Whether environmental impacts that are beyond the
scope of an agency’s jurisdiction and expertise can be
among the reasonably foreseeable effects of a major
federal action that must be studied under the
National Environmental Policy Act.
ii
TABLE OF CONTENTS
Page
QUESTION PRESENTED ......................................... i
TABLE OF CONTENTS ............................................ ii
TABLE OF AUTHORITIES...................................... iv
INTEREST OF AMICI CURIAE ............................... 1
SUMMARY OF THE ARGUMENT ........................... 1
ARGUMENT .............................................................. 5
I.
II.
NEPA Does Not Require Agencies to
Study Impacts that Are Beyond the
Scope of their Jurisdiction and
Expertise ....................................................... 6
A.
What Impacts Are “Reasonably
Foreseeable” Depends on the Scope
of Agency Authority .............................. 6
B.
Climate Impacts Are Beyond the
Limited Scope of STB’s Authority ...... 15
The D.C. Circuit Gave STB Little
Deference within the Scope of Its
Authority, While Imposing Vast New
Procedural Requirements On It Outside
the Scope of Its Authority ........................... 18
A.
The D.C. Circuit Failed to Defer to
STB Where Deference Was Due ......... 19
iii
B.
Impacts Outside the Agency’s
Authority May be Noted in an EIS
but Studying Them in Detail
Cannot Be Required............................ 24
III. CEQ Has No Rulemaking Authority
under NEPA and Cannot Create
Judicially Enforceable Obligations ............ 26
CONCLUSION ......................................................... 32
iv
TABLE OF AUTHORITIES
Page(s)
Cases:
Alaska Survival v. Surface Transp. Bd.,
705 F.3d 1073 (9th Cir. 2013) ............................. 15
Atl. Ref. Co. v. Pub. Serv. Comm’n of N.Y.,
360 U.S. 378 (1959) ............................................. 17
Balt. Gas & Elec. Co. v. NRDC,
462 U.S. 87 (1983) ............................7, 8, 18, 23, 24
Calvert Cliff’s Coordinating Committee v.
Atomic Energy Commission,
449 F.2d 1190 (D.C. Cir. 1971) .......................... 31
Center for Biological Diversity, Manasota-88,
Inc. v. United States Army Corps of
Engineers,
941 F.3d 1288 (11th Cir. 2019) ..................... 13, 14
Chambers v. United States,
451 F.2d 1045 (Ct. Cl. 1971) ............................... 30
City of Albuquerque v. U.S. Dep’t of the Interior,
379 F.3d 901 (10th Cir. 2004) ............................. 30
City of Carmel-By-The-Sea v.
U.S. Dep’t of Transportation,
123 F.3d 1142 (9th Cir. 1997) ............................. 30
Cort v. Ash,
422 U.S. 66 (1975) ............................................... 31
Department of Transp. v. Public Citizen,
541 U.S. 752 (2004) .......... 1, 4, 5, 10, 11, 12, 13, 26
v
Facchiano Const. Co., v.
United States Dept. of Labor,
987 F.2d 206 (3d Cir. 1993), cert. denied,
510 U.S. 822 (1993) ............................................. 28
Gonzales v. Oregon,
546 U.S. 243 (2006) ............................................. 19
Haitian Refugee Ctr., Inc. v. Baker,
953 F.2d 1498 (11th Cir.), cert. denied,
502 U.S. 1122 (1992) ........................................... 28
In re Surface Mining Regulation Litig.,
627 F.2d 1346 (D.C. Cir. 1980) ............... 10, 28, 29
Indep. Meat Packers Asso. v. Butz,
526 F.2d 228 (8th Cir. 1975) ................... 28, 30, 31
J. W. Hampton, Jr., & Co. v. United States,
276 U.S. 394 (1928) ......................................... 9, 18
Kentuckians for the Commonwealth v. United
States Army Corps of Eng'rs,
746 F.3d 698 (6th Cir. 2014) ............................... 14
Kisor v. Wilkie,
588 U. S. 558 (2019) .................................. 2, 10, 19
Legal Aid Soc’y of Alameda County v. Brennan,
608 F.2d 1319 (9th Cir. 1979) ............................. 30
Loper Bright Enterprises. v. Raimondo,
144 S. Ct. 2244 (2024) ....................5, 20, 22, 24, 27
Manhattan-Bronx Postal Union v. Gronouski,
350 F.2d 451 (1965), cert. denied,
382 U.S. 978 (1966) ............................................. 29
vi
Metropolitan Edison Company v.
People Against Nuclear Energy,
460 U.S. 766 (1983) ......................3, 7, 9, 11, 12, 14
Michigan v. Thomas,
805 F.2d 176 (6th Cir. 1986) ............................... 28
Motor Vehicle Mfrs. Ass’n v. State Farm Mut.
Auto. Ins. Co.,
463 U.S. 29 (1983) .... 4, 5, 10, 12, 18, 21, 22, 23, 24
Myersville Citizens for a Rural Cmty. v. FERC,
783 F.3d 1301 (D.C. Cir. 2015) ........................... 17
N.J. Dep't of Envtl. Prot. v. United States NRC,
561 F.3d 132 (3d Cir. 2009) ................................ 14
NAACP v. FPC,
425 U.S. 662 (1976) ............................................. 17
Nat’l Broad. Co. v. United States,
319 U.S. 190 (1943) ............................................. 17
New York Cent. Sec. Corp. v. United States,
287 U.S. 12 (1932) ......................................... 16, 18
Ohio Valley Coalition v. Aracoma Coal Co.,
556 F.3d 177 (4th Cir. 2009) ............................... 14
Sierra Club v. FERC,
867 F.3d 1357 (D.C. Cir. 2017) ............4, 12, 13, 14
Sierra Club v. Peterson,
705 F.2d 1475 (9th Cir. 1983) ............................. 30
Skidmore v. Swift,
323 U.S. 134 (1944) ................................... 5, 10, 26
vii
Vermont Yankee Nuclear Power Corp. v.
Natural Resources Defense Council, Inc.,
435 U.S. 519 (1978) ................................... 3, 24, 26
West Virginia v. EPA,
597 U.S. 697 (2022) ................................... 2, 10, 19
Whitman v. Am. Trucking Ass’ns,
531 U.S. 457 (2001) ........................................ 17-18
Wildlands CPR, Inc. v. U.S. Forest Service,
872 F. Supp. 2d 1064 (D. Mont. 2012)................ 30
Youngstown Sheet & Tube Co. v. Sawyer,
343 U.S. 579 (1952) ................................... 9, 26, 28
Statutes & Other Authorities:
5 U.S.C. § 706 ............................................. 1, 9, 10, 18
15 U.S.C. § 717f(e) .................................................... 12
42 U.S.C. § 4321 ..................................................... 1, 5
42 U.S.C. § 4331(a) ................................................... 14
42 U.S.C. § 4332(C) .................................................... 7
42 U.S.C. § 4371 ....................................................... 27
42 U.S.C. § 7411(b)(1)(A) ......................................... 29
42 U.S.C. § 7609 ....................................................... 27
49 U.S.C. § 10101 ............................................... 15, 16
49 U.S.C. § 10101(8) ................................................. 16
49 U.S.C. § 10502 ......................................... 15, 16, 21
49 U.S.C. § 10901 ............................................... 15, 16
viii
49 U.S.C. § 10901I .................................................... 15
40 C.F.R. § 1500 ..................................................... 5, 6
40 C.F.R. § 1500.3 .................................................... 28
40 C.F.R. § 1502.14 .................................................. 26
40 C.F.R. § 1502.22 .................................................. 19
40 C.F.R. § 1508 ....................................................... 26
40 C.F.R. § 1508.1(i)(2) .............................................. 9
39 Fed. Reg. 41501 (November 29, 1974) ................ 30
43 Fed. Reg. 55978 (November 29, 1978) .................. 7
APA § 706 ....................................................... 9, 10, 18
James W. Coleman, Pipelines & Power-lines:
Building the Energy Transport Future, 80
Ohio St. L.J. 263 (2019) ........................................ 3
Richard A. Epstein, Simple Rules for a Complex
World (1995) ........................................................ 14
Richard A. Epstein, Torts, §10.9 Directness and
Foresight (1999) .................................................... 8
Executive Order 11514............................................. 27
Executive Order 11821............................................. 30
Executive Order 11991....................................... 27, 28
Lon L. Fuller, Morality of Law (New Haven:
Yale University Press, rev. ed. 1969) ................. 14
Interstate Commerce Act, § 5(2) .............................. 16
ix
Note, Enforcing Executive Orders: Judicial
Review of Agency Action Under the
Administrative Procedure Act, 55 Geo. Wash.
L. Rev. 659 (1987) ............................................... 29
Section of Administrative Law and Regulatory
Practice, American Bar Association, A Guide
to Judicial and Political Review of Federal
Agencies § 6.024 (John F. Duffy & Michael
Herz eds., 2005) .................................................. 29
Sup. Ct. R. 37.6........................................................... 1
1
INTEREST OF AMICI CURIAE1
Amici are law professors who specialize in
administrative and environmental law, including
the National Environmental Policy Act (NEPA), 42
U.S.C. §§ 4321 et seq., and who have previously
published on, or have interest in, maintaining the
legality and effectiveness of administrative agency
action as originally envisioned in the U.S.
Constitution, the Administrative Procedure Act, and
NEPA. Amici have no personal stake in the outcome
of this case.
SUMMARY OF THE ARGUMENT
In Public Citizen, this Court rightly held that an
environmental impact statement (EIS) is not
required under NEPA when the agency “has no
ability to prevent” those effects “due to its limited
statutory authority.” Department of Transp. v. Public Citizen, 541 U.S. 752, 770 (2004). The Court
likened this limiting principle to the principle of
proximate causation in torts. But the question of
what constitutes a “reasonably foreseeable” environmental impact under NEPA cannot be considered in
legal isolation, for NEPA must be applied
consistently with other sources of law that bear on
the question. Those include the Administrative
Procedure Act’s “arbitrary and capricious” standard,
5 U.S.C. § 706, and the Constitution’s separation of
1 Pursuant to this Court’s Rule 37.6, counsel for amici curiae
states that no counsel for a party authored this brief in whole
or in part, and no party or counsel for a party made a monetary
contribution intended to fund the preparation or submission of
this brief. No person or entity other than amici curiae or its
counsel has made a monetary contribution to the preparation
or submission of this brief.
2
powers—all aspects of the case that the D.C. Circuit
glossed over.
Both the APA and the Constitution create
independent limits of their own on those matters
which agencies may delve into as well as those
which courts may require them to delve into, and
NEPA must be interpreted consistently with those
limits. The question of what is a “reasonably foreseeable” effect of an agency’s action under NEPA
cannot be separated from the question of what
deference the agency is due on matters that lie
within its jurisdiction and expertise, nor from the
related question of how far beyond its jurisdiction
and expertise the agency can stray before its actions
and determinations not only deserve no deference
but must be set aside as arbitrary and capricious.
Hence what this Court said just a few years ago
in West Virginia v. EPA should have been enough to
close the door on decisions like the one below:
“‘When the agency has no comparative expertise’ in
making certain policy judgments, we have said,
‘Congress presumably would not’ task it with doing
so.” 597 U.S. 697, 729 (2022) (quoting Kisor v.
Wilkie, 588 U. S. 558, 578 (2019)).
These issues are also inseparable from the
Constitution’s separation of powers, which require
both intelligible principles for agencies exercising
delegated rulemaking authority and that the
delegations
of
rulemaking
authority
be
unambiguous. Requiring an agency such as the
Surface Transportation Board (STB) to study
climate
impacts
in
connection
with
the
authorization of a short railway line violates all
these requirements.
3
This Court has placed clear boundaries on “the
scope of the agency’s inquiries” under NEPA to
ensure that they fall within “manageable” limits to
accomplish “NEPA’s goal of insuring a fully
informed
and
well-considered
decision.”
Metropolitan Edison Company v. People Against
Nuclear Energy, 460 U.S. 766, 776 (1983) (citing
Vermont Yankee Nuclear Power Corp. v. Natural
Resources Defense Council, Inc., 435 U.S. 519, 558
(1978) (internal citations and punctuation omitted).
Agencies must only consider environmental impacts
that bear a “reasonably close causal relationship” to
the action that the agency is taking, which the
Court, analogizing to the “familiar doctrine of
proximate cause,” has defined as only those impacts
that the agency was legally responsible for.
Metropolitan Edison, 462 U.S. at 774.
In this case, the D.C. Circuit Court of Appeals
vacated a Surface Transportation Board (STB)
approval of a short segment of railroad in Utah
because the court concluded that the agency should
have further analyzed impacts that might occur far
downstream and upstream as a result of authorizing
the railway segment, including increased oil
production in Utah, accidents on distant rail lines,
increased oil refining on the Gulf Coast, further oil
consumption around the world, and all of the
ultimately resulting carbon emissions.
This Court has repeatedly admonished the lower
courts to stop reading the NEPA so expansively. See
James W. Coleman, Pipelines & Power-lines:
Building the Energy Transport Future, 80 Ohio St.
L.J. 263, 299 & n.167 (2019). Had the court below
followed this Court’s admonition to consider the
4
“familiar doctrine of proximate cause,” 541 U.S. at
767, the case would have been easy: the STB’s
approval of a rail line entirely within Utah would
have been largely confined to impacts within Utah,
not hypothetical future impacts due to the
independent actions of other actors around the
world.
Yet the lower courts continue reading this
Court’s opinions narrowly and applying their own
increasingly
baroque
standards
to
require
consideration of more and more hypothetical
impacts, causing more and more delay to important
national infrastructure projects. See, e.g., Sierra
Club v. FERC, 867 F.3d 1357, 1373 (D.C. Cir. 2017)
(distinguishing Public Citizen). To ensure lower
court compliance with this Court’s decisions, the
Court should clearly state that agencies need only
consider impacts, whether direct or indirect, if the
agency is legally responsible for that impact because
it lies within the scope of the agency’s jurisdiction
and expertise.
That the scope of agency authority is the right
place for the “manageable line” between effects the
agency must study and those it need not study is
reinforced by the APA’s deferential “arbitrary and
capricious” standard, which is similarly predicated
on the scope of agency authority—in particular its
statutory jurisdiction and expertise. In State Farm,
this Court confirmed that to survive “arbitrary and
capricious review,” agencies must take a hard look
at all relevant facts. Motor Vehicle Mfrs. Ass'n v.
State Farm Mut. Auto. Ins. Co., 463 U.S. 29, 43
(1983). But “relevant facts” does not mean all facts,
otherwise the agency may have “relied on factors
5
which Congress has not intended the agency to
consider.” Id.
Moreover, while CEQ’s Regulations Implementing the Procedural Provisions of NEPA, 40 C.F.R.
§§ 1500 et seq., (CEQ Regulations) have long been
considered authoritative, NEPA in fact grants CEQ
no rulemaking authority. Hence the CEQ
Regulations may “regulate” agencies for purposes of
presidential administration, but they cannot bind
agencies as a matter of law and can have no impact
on independent agencies like the Federal Energy
Regulatory Commission (FERC). Especially after
this Court’s decision in Loper Bright Enterprises. v.
Raimondo, 144 S. Ct. 2244 (2024), the CEQ
Regulations are at most entitled to deference under
Skidmore v. Swift, 323 U.S. 134 (1944).
By expanding NEPA well beyond its statutory
bounds in disregard of Public Citizen, the decision
below systematically trampled on both the APA’s
deference scheme and the Constitution’s separation
of powers, and should be reversed.
ARGUMENT
All agree that under the National Environmental
Policy Act (NEPA), 42 U.S.C. § 4321 et seq., agencies
need study only those downstream and upstream
impacts that are reasonably foreseeable. But as
interpreted by the D.C. Circuit and courts that
follow it, that standard has become largely
indeterminate. That has introduced several grave
errors into administrative law which this Court now
has a chance to correct.
First, requiring agencies to study impacts beyond
their jurisdiction and expertise makes it nearly
6
impossible in routine cases for agencies to predict
where courts will draw the line between those
impacts that they must study and those they need
not, thereby upsetting the division of regulatory
labor ordained by Congress. Second, this expansive
reading of NEPA contradicts the APA’s sensible
scheme of deference under “arbitrary and
capricious” review, while imposing expansive
environmental review requirements with respect to
matters entirely outside the agency’ jurisdiction and
expertise and as to which the agency should expect
little deference. Third, the D.C. Circuit approach
engenders major separation-of-powers problems,
including a lack of intelligible principles to guide
agencies in climate-based rulemaking and the fact
that CEQ has no rulemaking authority under
NEPA, and therefore its Regulations for
Implementing the Procedural Provisions of NEPA,
40 C.F.R. §§ 1500 et seq., (the CEQ Regulations),
cannot be not judicially enforceable.
I. NEPA Does Not Require Agencies to Study
Impacts that Are Beyond the Scope of their
Jurisdiction and Expertise.
A. What Impacts Are “Reasonably Foreseeable” Depends on the Scope of Agency
Authority.
As originally enacted, NEPA required agencies to
include in any proposal for “major Federal actions
significantly affecting the quality of the human
environment” an environmental impact statement
(EIS) on “the environmental impact of the proposed
action.” It was obvious virtually from the start that
there had to be some limiting principle on the
downstream and upstream impacts that had to be
7
studied,
otherwise
NEPA
would
become
unmanageable for agencies. But in the D.C. Circuit
and courts that follow it, “reasonably foreseeable”
has been transformed into an almost infinitely
elastic
standard.
As
the
decision
below
demonstrates, the only “manageable line” between
effects the agency must study under NEPA and
those which it need not study is one based upon the
scope of the agency’s statutory authority.
The
original
1978
CEQ
Regulations
acknowledged that there must be a limiting
principle on the impacts that must be studied under
NEPA. It defined “Effects” to include both “(a)
Direct effects, which are caused by the action and
occur at the same time and place,” and “(b) Indirect
effects, which are caused by the action and are later
in time or farther removed in distance, but are still
reasonably foreseeable.” 43 Fed. Reg. 55978, 56004
(November 29, 1978) (emphasis added). In 2023, the
Fiscal Responsibility Act codified the reasonably
foreseeable standard. 42 U.S.C. § 4332(C).
This Court first explored what standard should
govern the effects that an agency must study under
NEPA in Metropolitan Edison Company v. People
Against Nuclear Energy. 460 U.S. 766 (1983). The
Nuclear Regulatory Commission (NRC) had
authorized one of the reactors at Three Mile Island
to restart operations. Pursuant to its general safety
procedures (see, Balt. Gas & Elec. Co. v. NRDC, 462
U.S. 87 (1983)), the NRC determined that the action
would have no significant environmental impacts.
Challengers argued that the NRC had failed to
consider the psychological harm to residents in the
vicinity, as well as their relatives elsewhere, that
8
might be caused by the reactor restart as a
cognizable environmental effect within NEPA.
The Court held that the psychological effects of
the reactor restart were not within the scope of
NEPA analysis and adopted a causation test to
determine NEPA's applicability:
Our understanding of the congressional concerns
that led to the enactment of NEPA suggests that
the
terms
“environmental
effect”
and
“environmental impact” in § 102 be read to
include a requirement of a reasonably close
causal relationship between a change in the
physical environment and the effect at issue.
This requirement is like the familiar doctrine of
proximate cause from tort law.
462 U.S. at 774. Thus, to be relevant for NEPA
analysis, an impact has to be proximately caused by
a change in the physical environment entailed in the
proposed agency action. The Court held that the
NRC did not have to take into account the
psychological impacts of the decision to reopen a
reactor. “In the context of both tort law and NEPA,
courts must look to the underlying policies or
legislative intent in order to draw a manageable line
between those causal changes that may make an
actor responsible for an effect and those that do
not.” Id. at 774 n.7. The requirement of proximity
cannot be satisfied given the vast array of actions
that intervene between an agency action and remote
psychological or climate impacts. See Richard A.
Epstein, Torts, §10.9 Directness and Foresight
(1999). The range of consequences that the D.C.
Circuit wishes to add into the analysis are orders of
magnitude greater than those rejected in
9
Metropolitan Edison, such that any “indirect effects”
included in the 1978 CEQ Regulation are subject to
the cautionary limitations of Metropolitan Edison.
Hence the CEQ Regulation risks drawing
agencies onto treacherous waters when it provides
that “[i]ndirect effects may include growth-inducing
effects and other effects related to induced changes
in the pattern of land use, population density or
growth rate, and related effects on air and water
and other natural systems, including ecosystems.”
40 C.F.R. § 1508.1(i)(2). Such effects are still subject
to other limitations, of which the proximate cause of
Metropolitan Edison is only one. There is also the
limitation inherent in APA § 706, which cautions
agencies not to stray far beyond the scope of their
authority and expertise. There is the fact that
beyond the scope of the agency’s expertise, Congress
has almost certainly supplied no intelligible
principle. See J. W. Hampton, Jr., & Co. v. United
States, 276 U.S. 394, 409 (1928) (holding that
precise mechanisms for setting tariff adjustments
prescribed in statute constituted intelligible
principles to guide the agency in its exercise of
delegated rulemaking authority). And there is the
question, which courts have too long ignored, of
exactly what legal effect should be given to the CEQ
Regulation: While a president has inherent
executive authority to add to the agency procedures
that are required by law, the president has no power
to create law. Youngstown Sheet & Tube Co. v.
Sawyer, 343 U.S. 579, 587 (1952). Any command
from the president to federal agencies which claims
to have the force of law must therefore rest on a
delegation of rulemaking authority from Congress,
10
In re Surface Mining Regulation Litig., 627 F.2d
1346, 1357 (D.C. Cir. 1980).
The high deference due to agencies under APA §
706 with respect to issues “which rest[] within the
expertise of [the agency], and upon which a
reviewing court must be most hesitant to intrude,”
See Motor Vehicle Mfrs. Ass’n v. State Farm Mutual
Automobile Ins. Co., 463 U.S. 29, 53 (1983), has as
its corollary that determinations outside the
agency’s sphere of competence are due little
deference beyond the respect of Skidmore. Properly
understood, State Farm implies that agencies
cannot stray too far beyond those issues Congress
has entrusted to them before their very lack of
expertise renders their actions inherently “arbitrary
and capricious” under § 706. And that matters here,
because “‘[w]hen the agency has no comparative
expertise’ in making certain policy judgments […]
Congress presumably would not task it with doing
so.” West Virginia v. EPA, 597 U.S. at 729 (quoting
Kisor v. Wilkie, 588 U. S. 558, 578 (2019) (internal
quotations omitted).
The issue of what acts fall within agency
authority came to the fore with Department of
Transportation v. Public Citizen, 541 U.S. 752
(2004). In that case, the President had decided to lift
a moratorium on Mexican motor carrier certification
following the preparation of new motor carrier
safety regulations required by law. In crafting the
proposed safety regulations, the Federal Motor
Carrier Safety Administration (FMCSA) determined
that it need not consider the environmental impact
of the increased presence of Mexican trucks within
the United States. The Court upheld FMCSA’s
11
determination because FMCSA had no discretion to
prevent the entry of Mexican trucks, where the legal
authority lay with the President, not FMCSA.
The “relevant question,” this Court said, was
whether the environmental impact of an increased
volume of Mexican trucks in the U.S. was an “effect”
of FMCSA’s issuance of safety regulations for those
trucks. 541 U.S. at 764. The Court held that it was
not. “[A] ‘but for’ causal relationship is insufficient
to make an agency responsible for a particular effect
under NEPA. . . . NEPA requires ‘a reasonably close
causal relationship’ between the environmental
effect and the alleged cause.” Id. This Court again
noted a strong analogy to proximate causation in
torts law: “[C]ourts must look to the underlying
policies or legislative intent in order to draw a
manageable line between those causal changes that
may make an actor responsible for an effect and
those that do not.” “Inherent in NEPA . . . is a ‘rule
of reason’ which ensures that agencies determine
whether and to what extent to prepare an EIS based
on the usefulness of any new potential information
to the decisionmaking process.” 541 U.S. at 767.
Public Citizen was an unusual case in that the
statute triggering NEPA was non-discretionary. As
a result, some courts have had a difficult time
applying it to the more usual case, in which the
agency has substantial discretion over the decision.
But Public Citizen merely added to the foundation
established in Metropolitan Edison, the linchpin of
which was the need for a “manageable line” between
the effects an agency is responsible for and those it
is not, given its limited statutory authority. For
even where the agency has discretion over the
12
decision, and therefore can theoretically stop the
impact from happening, no agency has unlimited
statutory authority. The question remains whether
that impact is a “factor which Congress [] intended
[the agency] to consider,” 463 U.S. at 43, and
whether considering it would advance “NEPA’s goal
of insuring a fully informed and well-considered
decision,” See Metropolitan Edison, 460 U.S. at 776
(internal citations and punctuation omitted). Hence
the crucial first question in all of these cases is:
What is the scope of the agency’s authority?
Part of what has led to the circuit split observed
by the petitioners and others is a difference of
opinion over whether NEPA requires agencies to
study impacts beyond their narrow jurisdiction and
expertise and therefore requires agencies to consider
those remote impacts in their decision making.
Answering that question emphatically in the
affirmative, the D.C. Circuit approach ignores
multiple important guardrails inherent in NEPA,
the APA, and the Constitution’s separation of
powers.
Emblematic of this unsound approach is the D.C.
Circuit’s decision in Sierra Club v. FERC, 867 F.3d
1357 (D.C. Cir. 2017) (Sabal Trail), where the court
vacated FERC’s Certificate of Public Convenience
and Necessity for the Sabal Trail pipeline project
under the Natural Gas Act, 15 U.S.C.S. § 717f(e)
(NGA). The court concluded that the agency had
authority under the NGA to consider climate
change, which it failed to do, in the court’s view, by
not estimating carbon emissions from power plants.
Sabal Trail wrongly reads Public Citizen as
turning “not on the question ‘What activities does
13
[the agency] regulate,’” but on the agency’s
unchecked power to block a project that “would be
too harmful to the environment.” 867 F.3d at 1373.
On this view, agencies must consider even those
distant environmental effects that are another
agency’s responsibility: “[T]he existence of permit
requirements overseen by another federal agency or
state permitting authority cannot substitute for a
proper NEPA analysis.” Id. at 1375.
Center for Biological Diversity, Manasota-88, Inc.
v. United States Army Corps of Engineers, 941 F.3d
1288 (11th Cir. 2019) stands for the opposite
position. When the Corps of Engineers was
permitting wetland discharges required for the
expansion of a phosphate mine in Florida, the Corps’
NEPA review addressed the direct and indirect
effects of those discharges. But the Corps did not
study the effects of downstream activities, such as
refining the phosphate ore into fertilizer or storing
phosphogypsum. Relying on Public Citizen, the
Eleventh Circuit upheld the Corps’ decision not to
delve into such downstream issues, noting that
“[t]he Corps has no jurisdiction to regulate or
authorize any of that.” 941 F.3d at 1294. It went on
to note that “EPA and the [Florida Department of
Environmental Protection]—not the Corps—directly
regulate fertilizer plants and phosphogypsum.” Id.
at 1295. “[I]t was sensible,” the court explained, “for
the Corps to draw the line at the reaches of its own
jurisdiction, leaving the effects of phosphogypsum to
phosphogypsum’s regulators” and “respecting the
jurisdictional boundaries set by Congress and
inherent in state-federal cooperation.” Id. at 1295–
96. Any other reading of Public Citizen would turn
the Corps into a “de facto environmental-policy czar”
14
that could deny a permit based on “its dislike of the
applicant’s business or downstream effects not
sufficiently caused by” the activity the Corps was
permitting. Id. at 1296, 1299. The Eleventh Circuit’s
holding was a sharp rebuke of the D.C. Circuit’s
decision in Sabal Trail on a remarkably analogous
set of facts, also involving the jurisdictional
boundary between a federal agency and Florida
regulators.
The Eleventh Circuit is not alone in disagreeing
with the D.C. Circuit. See Kentuckians for the
Commonwealth v. United States Army Corps of
Eng'rs, 746 F.3d 698 (6th Cir. 2014); Ohio Valley
Coalition v. Aracoma Coal Co., 556 F.3d 177 (4th
Cir. 2009); and N.J. Dep't of Envtl. Prot. v. United
States NRC, 561 F.3d 132 (3rd Cir. 2009).
Simply put, the D.C. Circuit approach makes
Metropolitan
Edison’s
“manageable
line”
unmanageable. As interpreted by the D.C. Circuit
and kindred courts, NEPA’s requirements have
mushroomed into a fuzzy and indeterminate mass,
violating the basic principles of any legal system,
such as publicity, clarity, and constancy. See Lon L.
Fuller, Morality of Law (New Haven: Yale
University Press, rev. ed. 1969). Accordingly, the
case-by-case approach does not work. See Richard
A. Epstein, Simple Rules for a Complex World
(1995). By severely restricting the availability of
private
financing
for
infrastructure,
and
necessitating massive public subsidies, that
uncertainty also violates NEPA’s explicit policy of
encouraging man’s productive harmony with his
environment. 42 U.S.C. § 4331(a).
15
B. Climate Impacts Are Beyond the Limited
Scope of STB’s Authority.
The STB has broad discretion to consider the
public interest in granting the authorization at issue
here, but that discretion is not unlimited, and it
does not include the consideration of climate
impacts or climate policy.
The
Interstate
Commerce
Commission
Termination Act of 1995 (the Interstate Commerce
Act), 49 U.S.C. 10101 et seq., provides the STB with
authority to license the construction and operation
of new railroad lines in the interstate rail system.
See Alaska Survival v. Surface Transp. Bd., 705
F.3d 1073, 1078 (9th Cir. 2013). The STB’s
authorization of a new line takes one of two forms.
First, if an applicant submits a full application to
build a new railroad line, the STB must grant the
authorization “unless the STB finds that such
activities are inconsistent with the public
convenience and necessity.” 49 U.S.C. § 10901I.
Second, as in this case, an applicant may request
STB authorization through an “exemption” process
under 49 U.S.C. § 10502.
The STB may grant that exemption when it finds
that (1) a full proceeding under § 10901 “is not
necessary to carry out” the rail transportation policy
in § 10101 of the Interstate Commerce Act, and (2)
either that (a) the transaction is limited in scope, or
(b) the application of § 10901 “is not needed to
protect shippers from the abuse of market power.”
49 U.S.C. § 10502. Market power was no issue here.
In an exemption proceeding, the STB considers the
transportation merits of a project by looking to the
exemption criteria in § 10502, which in turn
16
requires the STB to analyze the rail transportation
policy factors identified in Section 10101. and of the
exemption criterion in Section 10502, only one of a
long list of 15 factors was materially implicated: “(8)
to operate transportation facilities and equipment
without detriment to the public health and safety.”
49 U.S.C. § 10101 (8).
The ICC’s authorizing statute, like the STB’s,
enabled it to approve a rail-line merger if the project
“will be in the public interest.” New York Cent. Sec.
Corp. v. United States, 287 U.S. 12, 20 n.1 (1932)
(quoting Interstate Commerce Act, § 5(2)). This
Court held that the “public interest” did not include
every conceivable public benefit, but was limited by
context to require a “direct relation to adequacy of
transportation service, to its essential conditions of
economy and efficiency, and to appropriate provision
and best use of transportation facilities, questions to
which the Interstate Commerce Commission has
constantly addressed itself in the exercise of the
authority conferred.” Id. at 25. The STB
appropriately concerns itself with the adequacy of
freight rail service, and, consistent with NEPA, the
incidental environmental effects of that service.
Congress
determines
whether
and
how
environmental effects are regulated, and it has not
tasked STB with weighing the merits and demerits
of the oil and gas industry.
The authority to grant a certificate of public
convenience and necessity carries broad discretion,
but that discretion is not unlimited. In the
analogous context of the Natural Gas Act (NGA), the
Supreme Court has held that the NGA’s nearly
identical language on public convenience and
17
necessity requires FERC to evaluate “all factors
bearing on the public interest.” Atl. Ref. Co. v. Pub.
Serv. Comm’n of N.Y., 360 U.S. 378, 391 (1959). The
Court has cautioned, however, that this requirement
is not unlimited in scope and cannot be read in a
vacuum. The term “public interest” in the NGA is
not “a broad license to promote the general public
welfare”—instead, it “take[s] meaning from the
purposes of the regulatory legislation.” NAACP v.
FPC, 425 U.S. 662, 669 (1976) (NAACP), which in
the case of the NGA is “to encourage the orderly
development of plentiful supplies of . . . natural gas
at reasonable prices.”
Id. at 669-70; accord
Myersville Citizens for a Rural Cmty. v. FERC, 783
F.3d 1301, 1307 (D.C. Cir. 2015) (quoting NAACP,
425 U.S. at 669-70).
The Supreme Court has also recognized that the
Commission has authority to consider “other
subsidiary purposes,” such as “conservation,
environmental, and antitrust questions.” NAACP,
425 U.S. at 670 & n.6 (citations omitted). But all
subsidiary purposes are, necessarily, subordinate to
the statute’s primary purpose, and the inquiry must
respect the guardrails provided by other sources of
law.
If the term “public convenience” were as “vague
and indefinite” as the D.C. Circuit suggests, it may
even violate the nondelegation doctrine. Nat’l
Broad. Co. v. United States, 319 U.S. 190, 226
(1943). Under the D.C. Circuit’s reading, STB can
address any foreseeable harm that it chooses. If that
is true, then Congress has failed to give an
“intelligible principle” to guide the STB in its
determination under the statute. Whitman v. Am.
18
Trucking Ass’ns, 531 U.S. 457, 472 (2001) (quoting
J.W. Hampton, Jr., & Co. v. United States, 276 U.S.
394, 409 (1928)).
To avoid any nondelegation problem, “public convenience” must be read through the lens of the
statutory scheme Congress entrusted the STB with
implementing. Cf. New York Cent. Sec. Corp., 287
U.S. at 25 (interpreting the statute while ruling on a
nondelegation challenge). Viewed contextually, it
becomes clear that the environmental effects of oil
production or oil refining do not bear a “direct
relation to the adequacy of transportation service”
that the STB is tasked with promoting.
Finally, both NEPA and the statutory scheme
that
Congress
entrusted
the
STB
with
implementing must be read consistently with other
applicable law, including the APA and the
Constitution’s separation of powers, all of which
constrain the agency’s authorization process in ways
that the D.C. Circuit failed to take into account.
II. The D.C. Circuit Gave STB Little Deference
within the Scope of Its Authority, While
Imposing Vast New Procedural Requirements On It Outside the Scope of Its
Authority
The D.C. Circuit focus on remote environmental
impacts totally outside STB’s jurisdiction and
expertise led it to lose sight of the deference analysis
required by § 706 of the APA. Both State Farm and
Baltimore Gas tolerate agency discretion only on
matters within the scope of an agency’s jurisdiction
and expertise, but demand deference to agencies
within that scope. The D.C. Circuit trampled on
19
both sides of this sensible scheme, finding fault with
the agency’s entirely appropriate refusal to study
impacts well beyond the scope of its jurisdiction and
expertise, while giving no deference to STB
determinations within that scope. It thereby lost
sight of this Court’s observation in West Virginia v.
EPA: “‘When the agency has no comparative
expertise’ in making certain policy judgments, we
have said, ‘Congress presumably would not’ task it
with doing so.” West Virginia v. EPA, 597 U.S. 697,
729 (2022) (quoting Kisor v. Wilkie, 588 U. S. 558,
578 (2019). See also Gonzales v. Oregon, 546 U.S.
243, 266-67 (2006).
A. The D.C. Circuit Failed to Defer to
STB Where Deference Was Due.
The D.C. Circuit agreed with petitioners that
STB had failed to take a “hard look” at the increased
risk of rail accidents downline given the increased
rail traffic resulting from the proposed railway. The
STB used national data to assess the risk of
derailment for the proposed railway, explaining that
“insufficient data” existed to assess whether the
specific commodity to be transported (waxy crude
oil) entailed any particular risks. 82 F.4th at 1182.
The D.C. Circuit pointed to the CEQ Regulation’s
requirement that agencies explain why needed
information is unavailable and what actions the
agency took to address that unavailability. See 40
C.F.R. § 1502.22 (2019). (As explained in Part III of
this brief, this is another “requirement” of the CEQ
Regulation that is not judicially enforceable). The
court concluded that the agency had not taken these
steps, and that in view of “significant opposing
viewpoints” concerning its analysis of rail accidents,
20
it had failed to comply with NEPA, and therefore
also with the APA. The court found the STB’s
derailment-risk assessment arbitrary and capricious
without even suggesting that the STB had erred in
its assessment! Though assessing the risk of
derailment is at the very core of the agency’s
authority and technical expertise, the court gave no
hint of deference.
The court also found arbitrary and capricious the
STB’s assessment of low wildfire risk. The court
explained, “A significant increase in the frequency of
[sic] which existing ignition sources travel this route
equally poses an increased risk of fire.” 82 F.4th at
1184. But the court provides no authority to support
this assertion, and common sense suggests that the
agency was correct to assess a marginal increase in
a “very low risk” as still amounting to a very low
risk. The D.C. Circuit provided no reason why the
STB might be wrong in that assessment, other than
its own disagreement with the assessment. And to
paraphrase Loper Bright, courts have no special
competence in risk assessment. Agencies do. See 144
S. Ct. at 2251.
The court then held that the STB’s analysis of
impacts on downline water resources was faulty
because it did not specifically mention the Colorado
River adjacent to the downline Union Pacific line
that would be carrying increased rail traffic. In its
EIS, STB included a detailed section on potential
impacts to water resources, which the STB said
applied equally well to water resources elsewhere.
The D.C. Circuit found that expert assessment
wanting, too.
21
The D.C. Circuit even vacated the STB’s decision
to grant an exemption for the railway application
under 49 U.S.C. § 10502, even though it could point
to no way in which the exemption failed to comply
with statutory requirements, other than tagging
along with the STB’s other supposed deficiencies.
The D.C. Circuit’s opinion is characterized from
start to finish by an almost astonishing lack of
respect or deference for STB with respect to those
matters that fall within the agency’s jurisdiction
and expertise. What makes the court’s lack of
deference particularly remarkable is its expansive
view of the things STB should have given a “hard
look” to entirely outside its jurisdiction and
expertise. One is left to wonder: If the court gives
virtually no deference to the agency with respect to
the agency’s core competencies, what deference
could the agency expect from the same court with
respect to pure speculation about upstream oil
development or downstream greenhouse gas
emissions, both of which lie outside the agency’s
jurisdiction and expertise, and with respect to which
the agency did not have access to meaningful
information and no means of developing meaningful
information itself?
The question is no mere curiosity. Suppose STB
had spent dozens of pages ruminating on the
problems of global climate change, and on that basis
had denied the authorization for the railway. Would
it not then have been guilty of “rely[ing] on factors
which Congress ha[d] not intended it to consider”
and thereby fail the first test of “hard look” review?
See State Farm, 463 U.S. at 43. It is when agencies
22
are outside their jurisdiction and expertise that
“hard look” review must be the most exacting.
Given the D.C. Circuit’s casual disregard for
STB’s authority and expertise on matters as to
which the APA demands deference, this case may be
an opportune time for this Court to ask whether its
embrace of “hard look” review in State Farm did not
unintentionally
open
the
door
to
courts’
systematically ignoring the deference that is clearly
implied in the APA’s “arbitrary and capricious”
standard. In Loper Bright, this Court finally
signaled a return to the simple and sensible scheme
of the APA, but deference on pure questions of law
was not the only part of that tapestry that has
frayed.
This Court’s concerns about judicial usurpation
of agency expertise, which were so misplaced in
Chevron, would have been fully justified in State
Farm.
Ministerial
fact-finding
in
the
implementation of a statutory scheme is a core
executive function. The court’s inquiry should be
chiefly directed to whether the agency has properly
exercised that function, either as part of delegation
of rulemaking authority, or as an exercise of
inherent executive authority.
On these mixed
questions of law and fact, the agency should
ordinarily receive ample running room as Justice
William Rehnquist pointed out in his short State
Farm dissent. 463 U.S. 57-59.
Alas, in practice, State Farm’s “hard look” review
has created a fog of litigation risk around every
agency action that no amount of diligence can
reliably cut through it. Any court can think of some
point that even the most diligent agency neglected
23
to mention in a rulemaking or EIS hundreds of
pages long. The courts can then quite arbitrarily
and capriciously vacate a vitally necessary agency
action, without any regard to the public interest,
because the agency arguably failed to fulfill some
requirement that it had no way of knowing about
before it got to court. This is the reality facing
agencies engaged in NEPA compliance today. They
often have no idea what the law requires, spend
exorbitant amounts of taxpayer resources trying to
anticipate every possible angle of attack without a
thought
to
NEPA’s
purpose
of
informed
decisionmaking, and then publish their EISs with as
much confidence as the man betting on red at the
roulette table, and with only slightly more success.
When the law becomes so indeterminate that
compliance is almost impossible, there is a problem.
This problem was not created by NEPA, a simple
and modest good-governance statute, but by the
fearsome procedural nettle that activist courts have
turned it into over the years.
State Farm has been cited countless times since
1983, usually by federal courts second-guessing
agency actions they don’t like. However, the earlier
1983 case of Baltimore Gas, 462 U.S. 87 (1983), took
a far better approach to the “arbitrary and
capricious” standard by upholding the Nuclear
Regulatory Commission’s (NRC) “generic” procedure
for nuclear plant approval, emphasizing Congress’s
and agencies’ respective roles in resolving
fundamental policy questions. The alternative is to
insist on hundreds of ad hoc decisions that follow no
rhyme or reason, which slows down these reviews
while leading to indeterminate results that
pointlessly prolong empirical reviews. No business
24
takes such a mindless and wasteful approach.
Government agencies should not either.
Courts have lost sight of the deeper logic of
Vermont Yankee—that courts should not micromanage executive administration. To paraphrase
Loper Bright, courts have no comparative advantage
when it comes to the management of administrative
processes. Agencies do. 144 S. Ct. at 2251. The D.C.
Circuit violated that admonition when it substituted
its preferences on things within STB’s prerogative
for those of the agency.
Applied without rigorous consistency, State
Farm’s “hard look” doctrine often amounts to a
double standard. The grant of any infrastructure
permit can be vacated under “hard look” review, to
great acclaim from environmentalists. But an
agency’s refusal to grant a permit, or its imposition
of vast paperwork burdens, is routinely accorded
sweeping deference that often strikes down the
sensible agency-wide procedures upheld in
Baltimore Gas, helping to make American
infrastructure the costliest, most time-consuming
and riskiest to build in the industrial world.
B. Impacts
Outside
the
Agency’s
Authority May be Noted in an EIS but
Studying Them in Detail Cannot Be
Required.
Federal courts generally pay lip service to the
idea that agencies need only study impacts that are
“reasonably foreseeable.” But without guardrails,
that standard is still too malleable, as shown by the
decision below. The concrete limiting principle that
should guide reasonable foreseeability is right there
25
in the APA: The admonition against agency actions
that are “arbitrary, capricious, or abuse of
discretion” counsels for agencies to stick to their
jurisdiction and expertise. Environmental impacts
that occur outside the agency’s jurisdiction and
expertise of NEPA may be noted in a variety of
ways, such as general statements. But they are not
within the reasonably foreseeable impacts that
NEPA requires careful study of, because NEPA
must be implemented consisted with the APA, and
under the APA agency action that stray too far from
the scope of agency authority risks being set aside
as arbitrary and capricious.
That any given environmental impact is not a
particular agency’s problem does not mean that it is
not the federal government’s problem. The purpose
of NEPA is still served when environmental impacts
within the jurisdiction of other agencies, or of
Congress, are noted for their attention. But there is
no point in an agency such as STB spending time on
climate policy; climate policy is no part of its
statutory mandate or expertise, and nothing that it
says on the subject should be due any deference
under the APA—on the contrary, anything it says
on the subject should be viewed with great
skepticism. The president surely has authority to
make STB part of a national policy effort on climate,
but such a national effort would not be judicially
enforceable against agencies without congressional
action, and there was none here.
26
III.
CEQ Has No Rulemaking Authority
under NEPA and Cannot Create
Judicially Enforceable Obligations.
The inclusion of “cumulative impacts” in the
definition of “effects”, 40 C.F.R. § 1508, and the
directive to examine “reasonable alternatives not
within the jurisdiction of the lead agency”, 40 C.F.R.
§1502.14, are just two familiar examples among
many of the requirements that CEQ invented out of
thin air. As a component of the White House, there
is no doubt that CEQ has authority to promulgate
rules of administration to guide agencies in their
implementation of NEPA’s procedural requirements.
But there is no basis for those rules’ being judicially
enforceable, and the D.C. Circuit’s enforcement of
them was another source of reversible error.
Federal courts’ enforcement of NEPA since
publication of the 1978 CEQ Regulation has lost
sight of the fact that NEPA grants CEQ no
legislative rulemaking authority. The procedural
requirements that the CEQ Regulation adds to
NEPA are binding upon executive agencies in the
same manner as any other presidential directive.
But judicial enforcement of those requirements has
no basis in law, and violates both the basic principle
of Youngstown Steel, that presidents cannot make
law, and that of Vermont Yankee, that courts cannot
add procedural requirements to those provided in a
procedural statute.
In Public Citizen, this Court said, that CEQ was
“established by NEPA with authority to issue
regulations interpreting it.” 541 U.S. at 757. This is
certainly true in the sense that CEQ’s
interpretations of NEPA deserve Skidmore respect,
27
a conviction reinforced by this Court’s recent
decision in Loper Bright. But the inclusion of things
like “cumulative impacts” of other agency actions
and socioeconomic effects of the agency action
within the definition of “environmental impact”
could not follow from any reasonable interpretation
of that statutory term; they are surplusage, which
could only be judicially enforceable if promulgated
pursuant to delegated rulemaking authority. And
neither NEPA nor any other statute grants CEQ
rulemaking authority in the traditional sense.
Federal courts may be forgiven for assuming that
CEQ does have such authority, however, given the
wording of the 1978 CEQ Regulation, which through
a clever sleight-of-hand glossed over the lack of
statutory basis. Section 1500.3 of the 1978 CEQ
Regulation contains the following recitation of
authorities:
These regulations are issued pursuant to NEPA,
the Environmental Quality Improvement Act of
1970, as amended (42 U.S.C. 4371 et seq.),
Section 309 of the Clean Air Act, as amended (42
U.S.C. 7609), and Executive Order 11514,
Protection and Enhancement of Environmental
Quality (March 5, 1970, as amended by
Executive Order 11991, May 24, 1977). […] It is
the Council’s intention that judicial review of
agency compliance with these regulations not
occur before an agency has filed the final
environmental impact statement. . . .
The reference to E.O. 11991 is on firm ground;
the rest of the quoted passage statement is nothing
but smoke and mirrors. There is not a word about
CEQ’s having authority to issue regulations, nor
28
even an intimation to that effect, in any of the
statutes mentioned in § 1500.3. The (Carter-era)
E.O. 11991 is in fact the sole authority for the
(Carter-era) CEQ Regulation, which in fact was
promulgated wholly pursuant to the President’s
vested authority under Article II of the U.S.
Constitution.
It may have been dressed up as a regulation and
adopted through notice-and-comment rulemaking; it
may walk and talk like a regulation; and it may
have fooled lots of people into thinking that it is a
regulation in the legislative sense. But in truth, the
CEQ Regulation of NEPA is nothing more than an
executive order. When the Eighth Circuit refused to
enforce a similar presidential directive, it said,
“Youngstown Sheet & Tube Co. v. Sawyer completely
refutes the claim that the President may act as a
lawmaker in the absence of a delegation of authority
or mandate from Congress.” Indep. Meat Packers
Asso. v. Butz, 526 F.2d 228, 236 (8th Cir. 1975)
(citations omitted).
“Generally, there is no private right of action to
enforce obligations imposed on executive branch
officials by executive orders.” Facchiano Const. Co.,
v. United States Dept. of Labor, 987 F.2d 206, 210
(3d Cir. 1993), cert. denied, 510 U.S. 822 (1993); See
also Haitian Refugee Ctr., Inc. v. Baker, 953 F.2d
1498, 1510-11 (11th Cir.), cert. denied, 502 U.S.
1122 (1992); Michigan v. Thomas, 805 F.2d 176, 187
(6th Cir. 1986). Only when executive orders have
“specific foundation in Congressional action” are
they “judicially enforceable in private civil suits.”
See In re Surface Mining Regulation Litig., 627 F.2d
1346, 1357 (D.C. Cir. 1980).
29
Unless based in delegated rulemaking authority,
presidential directives such as executive orders have
never been considered enforceable de jure and draw
the entirety of their compelling force from the
President’s power to remove agency heads, which
does not extend to independent agencies like FERC.
Section of Administrative Law and Regulatory
Practice, American Bar Association, A Guide to
Judicial and Political Review of Federal Agencies §
6.024 (John F. Duffy & Michael Herz eds., 2005).
Multiple courts of appeals have held that
executive orders without specific foundation in
congressional action are not judicially enforceable in
private civil suits. See Manhattan-Bronx Postal
Union v. Gronouski, 350 F.2d 451, 456-57 (1965),
cert. denied, 382 U.S. 978, (1966) (holding E.O.
10988 not judicially enforceable); In re Surface
Mining Regulation Litig., 627 F.2d 1346, 1357 (D.C.
Cir. 1980) (holding E.O. 11821 and OMB Circular
No. A-107 not judicially enforceable).
Congress knows how to delegate rulemaking
authority. For example, Section 111 of the Clean Air
Act specifically delegates to EPA the authority to
promulgate New Source Performance Standards
with the force of law: “. . . the Administrator shall
publish proposed regulations, establishing Federal
standards of performance for new sources within
such category.” 42 U.S.C. § 7411(b)(1)(A). See Note,
Enforcing Executive Orders: Judicial Review of
Agency Action Under the Administrative Procedure
Act, 55 Geo. Wash. L. Rev. 659, 661-62 (1987). There
is no similar language in NEPA.
Judicial enforcement of the CEQ Regulation is a
glaring exception to the general practice of federal
30
courts, which only enforce executive orders that are
authorized by a statute. See, e.g., City of
Albuquerque v. U.S. Dep’t of the Interior, 379 F.3d
901, 905-06, 913-14 (10th Cir. 2004) (considering a
claim that agency violated executive order in
choosing office space); City of Carmel-By-The-Sea v.
U.S. Dep’t of Transportation, 123 F.3d 1142 (9th Cir.
1997); Sierra Club v. Peterson, 705 F.2d 1475 (9th
Cir. 1983); Legal Aid Soc’y of Alameda County v.
Brennan, 608 F.2d 1319 (9th Cir. 1979); Chambers v.
United States, 451 F.2d 1045, 1050 (Ct. Cl. 1971)
(awarding backpay for the government’s violation of
an executive order regarding nondiscriminatory
employment practices); Wildlands CPR, Inc. v. U.S.
Forest Service, 872 F. Supp. 2d 1064 (D. Mont. 2012)
(finding that EOs governing use of off-road vehicles
on public lands had force and effect of law and were
intended to create a private right of action).
In Independent Meat Packers Association v. Butz,
526 F.2d 228 (8th Cir. 1975), meatpackers challenged an agency action partly on the basis that its
inflation impact statement was deficient and failed
to comply with the requirements of Executive Order
No. 11821, “Inflation Impact Statements,” 39 Fed.
Reg. 41501 (November 29, 1974). The 8th Circuit
Court of Appeals disagreed:
[I]n our view, Executive Order No. 11821 was
intended primarily as a managerial tool for
implementing the President’s personal economic
policies and not as a legal framework enforceable
by private civil action. Even if appellees could
show that the Order has the force and effect of
law, they would still have to demonstrate that it
was intended to create a private right of action.
31
To infer a private right of action here creates a
serious risk that a series of protracted lawsuits
brought by persons with little at stake would
paralyze the rulemaking functions of federal
administrative agencies.
526 F.2d at 234-236. Unfortunately, that describes
eminently well the modern state of NEPA.
Hundreds of federal permits have been vacated
by courts because of agencies’ failure to comply with
supposed NEPA requirements that are not in the
statute and that were invented by CEQ out of thin
air. And not only does NEPA contain no hint of
delegated rulemaking authority for CEQ, it doesn’t
even hint at a private right of action for enforcing
the statute! The D.C. Circuit’s decision in Calvert
Cliff’s Coordinating Committee v. Atomic Energy
Commission, 449 F.2d 1190 (D.C. Cir. 1971), has
stood the test of time, but was arguably contradicted
by this Court’s holding in Cort v. Ash, which held
that these actions should be inferred only when the
plaintiff is “one of a class for whose especial benefit
the statute was enacted.” 422 U.S. 66, 78 (1975)
(emphasis in the original). That test cannot be met
when thousands of individuals and organizations
have standing. Calvert Cliffs, much like the decision
below, wholly distorts the statute, whose procedures
were intended to find middle positions on hard
questions. Allowing a private right action to enforce
NEPA lets extreme opponents prolong litigation and
undermine cooperative solutions. Such rulings have
helped transform the CEQ regulation into fertile
ground for endless litigation where there was
arguably no right of action at all.
32
CONCLUSION
We urge this Court to reverse the decision below.
Respectfully submitted,
Richard A. Epstein
New York University
16 Thomas Place
Norwalk, CT 06853
James W. Coleman
University of Minnesota
229 19th Ave. South
Minneapolis, MN 55455
Mario A. Loyola
Counsel of Record
Florida International University
11200 SW 8th St.
Miami, FL 33199
(305) 472-2700
mloyola@fiu.edu
Amici Curiae
September 5, 2024
This is a copy of a public record, reproduced as it was published. It is not legal advice, and it may not be the version a court would rely on. Check the official source before you cite it.