Petition for Writ of Certiorari — Shannon Poe, Petitioner v. Idaho Conservation League

Supreme Court briefMar 15, 2024

Ask Donna

What actually matters in this document.

Text

No. __________

In The Supreme Court of the United States

____________________

SHANNON POE,

v.

Petitioner,

IDAHO CONSERVATION LEAGUE,

____________________

Respondent.

On Petition for Writ of Certiorari

to the United States Court of Appeals

for the Ninth Circuit

____________________

PETITION FOR WRIT OF CERTIORARI

____________________

DAMIEN M. SCHIFF

Pacific Legal Foundation

555 Capitol Mall,

Suite 1290

Sacramento, CA 95814

DANIELLE R. BETTENCOURT

Fairfield and Woods P.C.

1801 California St.,

Suite 2600

Denver, CO 80202-2645

FRANK D. GARRISON

Counsel of Record

Pacific Legal Foundation

3100 Clarendon Blvd.,

Suite 1000

Arlington, VA 22201

Telephone: (202) 888-6881

FGarrison@pacificlegal.org

Counsel for Petitioner Shannon Poe

i

QUESTION PRESENTED

The Clean Water Act forbids the unpermitted

“discharge of any pollutant” into “navigable waters.”

33 U.S.C. §§ 1311(a), 1362(11). The Act defines

“discharge of a pollutant” as “any addition of any

pollutant to navigable waters[.]” Id. § 1362(12). This

Court has twice held that, as a matter of ordinary

meaning, there can be no “addition of any pollutant”

unless there is an increase of pollutants to a

waterbody. S. Florida Water Mgmt. Dist. v.

Miccosukee Tribe of Indians, 541 U.S. 95, 109–12

(2004); Los Angeles Cnty. Flood Control Dist. v.

Natural Res. Def. Council, Inc., 568 U.S. 78, 82–84

(2013). In conflict with these decisions, as well as

rulings from several courts of appeals, the Ninth

Circuit below found “addition” ambiguous, applied

Chevron deference, and held that Petitioner’s smallscale suction dredge mining added pollutants to an

Idaho river—even though his mining just temporarily

resuspended material in the water column that was

already present within the waterbody.

The question presented is:

Whether there is a “discharge of a pollutant”

under the Clean Water Act when material already

within a regulated waterbody is merely moved or

resuspended within that waterbody?

ii

PARTIES TO THE PROCEEDING

Petitioner is Shannon Poe. Respondent is the

Idaho Conservation League.

STATEMENT OF RELATED CASES

These proceedings are directly related to the

above-captioned case under Rule 14.1(b)(iii):

Idaho Conservation League v. Poe, No. 2235978, 86 F.4th 1243 (9th Cir.), judgment

entered on November 20, 2023;

Idaho Conservation League v. Poe, No. 1:18cv-353-REB, 2021 WL 2316158 (D. Idaho),

judgment entered on June 4, 2021;

Idaho Conservation League v. Poe, No. 1:18cv-353-REB, 2022 WL 4536465 (D. Idaho),

judgment entered on September 28, 2022.

iii

TABLE OF CONTENTS

QUESTION PRESENTED .......................................... i

PARTIES TO THE PROCEEDING ........................... ii

STATEMENT OF RELATED CASES ....................... ii

TABLE OF AUTHORITIES ....................................... v

PETITION FOR A WRIT OF CERTIORARI ............. 1

OPINIONS BELOW ................................................... 1

JURISDICTION.......................................................... 1

STATUTORY PROVISIONS AT ISSUE.................... 1

INTRODUCTION ....................................................... 3

STATEMENT OF THE CASE .................................... 7

A. The Clean Water Act ................................. 7

B. Factual and Procedural Background ........ 9

REASONS FOR GRANTING THE PETITION ....... 14

I.

The Ninth Circuit’s decision conflicts with this

Court’s precedents construing the Clean Water

Act ................................................................... 14

A. The Ninth Circuit’s decision conflicts with

this Court’s decisions in Miccosukee Tribe

and L.A. County ....................................... 14

B. The Ninth Circuit’s decision conflicts with

this Court’s application of clear statement

rules in Sackett ........................................ 19

iv

II. The Ninth Circuit’s decision deepens an

already entrenched conflict over the meaning of

“addition” under the Clean Water Act .......... 21

III. This case is a good vehicle for the Court to

clarify an exceptionally important issue of

statutory interpretation under the Clean Water

Act ................................................................... 25

CONCLUSION.......................................................... 30

APPENDIX

Opinion, U.S. Court of Appeals for the Ninth Circuit,

filed November 20, 2023 ...................................... 1a

Memorandum Decision and Order Re: Plaintiff Idaho

Conservation League’s Motion for Remedies, U.S.

District Court, District of Idaho, filed

September 28, 2022 ........................................... 21a

Memorandum Decision and Order Re: Idaho

Conservation League’s Motion for Summary

Judgment on Liability and Shannon Poe’s Motion

for Summary Judgment, U.S. District Court,

District of Idaho, filed June 4, 2021 ................. 61a

Order (denying petition for rehearing en banc), U.S.

Court of Appeals for the Ninth Circuit, filed

January 11, 2024 ............................................... 97a

v

TABLE OF AUTHORITIES

Cases

Avoyelles Sportsmen’s League, Inc. v. Marsh,

715 F.2d 897 (5th Cir. 1983) ................... 13, 22, 24

Borden Ranch Partnership v.

U.S. Army Corps of Engineers,

261 F.3d 810 (9th Cir. 2001),

aff’d, 537 U.S. 99 (2002) ...........7, 11, 13, 16, 22, 24

Catskill Mountains Chapter of Trout

Unlimited v. City of New York,

273 F.3d 481 (2d Cir. 2001) ......................... 3–4, 23

Chevron v. NRDC,

467 U.S. 837 (1984) ............................................. 13

Cnty. of Maui v. Hawaii Wildlife Fund,

140 S. Ct. 1462 (2020) ......................................... 27

Comm. to Save Mokelumne River v.

East Bay Mun. Util. Dist.,

13 F.3d 305 (9th Cir. 1993) ................................... 8

Friends of the Earth, Inc. v.

Laidlaw Env’t Servs. (TOC), Inc.,

528 U.S. 167 (2000) ............................................. 28

Gutierrez-Brizuela v. Lynch,

834 F.3d 1142 (10th Cir. 2016) ........................... 26

Lawrence on Behalf of Lawrence v. Chater,

516 U.S. 163 (1996) ............................................. 26

Loper Bright Enterprises v. Raimondo,

143 S. Ct. 2429 (2023),

cert. granted in part May 1, 2023........................ 26

vi

Los Angeles Cnty. Flood Control Dist. v.

Natural Res. Def. Council, Inc.,

568 U.S. 78 (2013) ..........................3, 14–15, 17, 25

Michigan v. EPA,

576 U.S. 743 (2015) ............................................. 26

Nat’l Mining Ass’n v. U.S. Army Corps of Eng’rs,

145 F.3d 1399 (D.C. Cir. 1998) ..................... 22–23

Nat’l Wildlife Fed’n v. Consumers Power Co.,

862 F.2d 580 (6th Cir. 1988) ......................... 22–23

Nat’l Wildlife Fed’n v. Gorsuch,

693 F.2d 156 (D.C. Cir. 1982) ......................... 8, 22

North Carolina Coastal Fisheries

Reform Group v. Capt. Gaston LLC,

76 F.4th 291 (4th Cir. 2023) ...................... 5, 24–25

Pereira v. Sessions,

585 U.S. 198 (2018) ............................................. 26

Perez v. Mortgage Bankers Ass’n,

575 U.S. 92 (2015) ............................................... 26

Rapanos v. United States,

547 U.S. 715 (2006) ......................................... 9, 18

Rybachek v. EPA,

904 F.2d 1276 (9th Cir. 1990) ......11–13, 16, 22, 24

S. Florida Water Mgmt. Dist. v.

Miccosukee Tribe of Indians,

541 U.S. 95 (2004) ........................................... 3, 14

S.D. Warren Co. v. Maine Bd. of Env’t Prot.,

547 U.S. 370 (2006) ............................................. 15

Sackett v. EPA,

598 U.S. 651 (2023) ......................5, 6, 9, 18–21, 27

vii

Skilling v. United States,

561 U.S. 358 (2010) ............................................. 21

United States v. Deaton,

209 F.3d 331 (4th Cir. 2000) ............................... 23

United States v. Law,

979 F.2d 977 (4th Cir. 1992) ............................... 23

United States v. M.C.C. of Florida, Inc.,

772 F.2d 1501 (11th Cir. 1985) ............... 13, 22, 24

United States v. Moses,

496 F.3d 984 (9th Cir. 2007) ............................... 18

Statutes

28 U.S.C. § 1254(1) ..................................................... 1

33 U.S.C. § 1251(a) ..................................................... 7

33 U.S.C. § 1311(a) ............................................. 1, 3, 7

33 U.S.C. § 1319(a)–(d) ............................................... 9

33 U.S.C. § 1319(b) ..................................................... 9

33 U.S.C. § 1319(d) ..................................................... 9

33 U.S.C. § 1342 .......................................................... 3

33 U.S.C. § 1342(a) ..................................................... 8

33 U.S.C. § 1342(a)(1) ............................................. 1–2

33 U.S.C. § 1342(b) ..................................................... 8

33 U.S.C. § 1344 ................................................ 3, 8, 11

33 U.S.C. § 1344(g) ..................................................... 8

33 U.S.C. § 1362(3) ..................................................... 8

33 U.S.C. § 1362(6) ................................................. 2, 7

33 U.S.C. § 1362(12) ....................................... 2, 15, 29

viii

33 U.S.C. § 1362(12)(A) .......................................... 3, 8

33 U.S.C. § 1365 .......................................................... 4

33 U.S.C. § 1365(a) ..................................................... 8

33 U.S.C. § 1365(b)(1)(A) .......................................... 10

33 U.S.C. § 1365(d) ..................................................... 9

33 U.S.C. § 1377(e)...................................................... 8

Regulations

40 C.F.R. § 19.4 tbl.1 .................................................. 9

40 C.F.R. § 440.140(b)............................................... 12

Other Authorities

Bernell, David et al., Inst. For Natural

Resources, Or. State Univ., Recreational

Placer Mining in the Oregon Scenic

Waterways System (2003),

https://bit.ly/34W5AcW ....................................... 17

Bishop, Timothy S. et al.,

Counting the Hands on Borden Ranch,

34 Envtl. L. Rep.

(Envtl. L. Inst.) 10,040 (2004) ............................. 28

Cal. State Water Resources Control Bd.,

Mercury Losses and Recovery During

a Suction Dredge Test in the South

Fork of the American River (2005) ...................... 10

Coon, Arthur F., Is Plowing a Point Source

Discharge? The Aftermath of Borden Ranch,

18-SUM Nat. Resources & Env’t 6

(Summer 2003) .................................................... 28

ix

Dahab, Nadia H., Note, Muddying the

Waters of Clean Water Act Permitting:

NEDC Reconsidered,

90 Or. L. Rev. 335 (2011)............................. 4, 9–10

EPA, NPDES General Permit for Small Suction

Dredge Placer Miners in Idaho,

https://www.epa.gov/npdes-permits/idahonpdes-program-authorization ............................... 8

Gerber, Adam, Casenote, Borden Ranch

Partnership v. U.S. Army Corps of

Engineers: A Barge in a Bucket? May

Isolated Wetlands Be Considered

“Navigable Waters” Under the CWA?,

15 Vill. Envtl. L.J. 415 (2004) ............................. 28

Kavanaugh, Brett M.,

Fixing Statutory Interpretation,

129 Harv. L. Rev. 2118 (2016) ............................ 26

Miller, Jeffrey G., Plain Meaning, Precedent,

and Metaphysics: Interpreting the “Addition”

Element of the Clean Water Act Offense,

44 Envtl. L. Rep. News &

Analysis 10770 (2014) ............................. 19, 27–28

Robertson, Marc, Environmental Ambulance

Chasing: DOJ Urges Court To Scrutinize

Clean Water Citizen-Suit Settlements,

Forbes (June 26, 2018),

https://bit.ly/3R0xFIW ................................... 28–29

Webster’s Third New International

Dictionary (2002) ................................................. 15

1

PETITION FOR A WRIT OF CERTIORARI

Petitioner Shannon Poe respectfully petitions for

a writ of certiorari to review the judgment of the

United States Court of Appeals for the Ninth Circuit.

OPINIONS BELOW

The Ninth Circuit’s panel opinion is reported at 86

F.4th 1243 and is reproduced in the Appendix

beginning at 1a. The United States District Court for

the District of Idaho’s opinion on remedies is

unreported but is available at 2022 WL 4536465 and

is reproduced in the Appendix beginning at 21a. The

United States District Court for the District of Idaho’s

opinion on liability is unreported but is available at

2021 WL 2316158 and is reproduced in the Appendix

beginning at 61a. The Ninth Circuit’s denial of

rehearing en banc is unreported but is reproduced in

the Appendix beginning at 97a.

JURISDICTION

The Ninth Circuit issued its opinion on

November 20, 2023, and denied rehearing en banc on

January 11, 2024. This Court has jurisdiction under

28 U.S.C. § 1254(1).

STATUTORY PROVISIONS AT ISSUE

The Clean Water Act provides:

Except as in compliance with this section

and sections 1312, 1316, 1317, 1328,

1342, and 1344 of this title, the discharge

of any pollutant by any person shall be

unlawful. 33 U.S.C. § 1311(a);

Except as provided in sections 1328 and

1344 of this title, the Administrator may,

2

after opportunity for public hearing issue

a permit for the discharge of any

pollutant, or combination of pollutants,

notwithstanding section 1311(a) of this

title, upon condition that such discharge

will meet either (A) all applicable

requirements under sections 1311, 1312,

1316, 1317, 1318, and 1343 of this title,

or (B) prior to the taking of necessary

implementing actions relating to all such

requirements, such conditions as the

Administrator determines are necessary

to carry out the provisions of this

chapter. 33 U.S.C. § 1342(a)(1);

The term “pollutant” means dredged

spoil, solid waste, incinerator residue,

sewage,

garbage,

sewage

sludge,

munitions, chemical wastes, biological

materials, radioactive materials, heat,

wrecked or discarded equipment, rock,

sand, cellar dirt and industrial,

municipal, and agricultural waste

discharged into water. 33 U.S.C.

§ 1362(6);

The term “discharge of a pollutant” and

the term “discharge of pollutants” each

means (A) any addition of any pollutant

to navigable waters from any point

source, (B) any addition of any pollutant

to the waters of the contiguous zone or

the ocean from any point source other

than a vessel or other floating craft. 33

U.S.C. § 1362(12).

3

INTRODUCTION

This case presents an intractable conflict among

the lower courts, as well as between those courts and

this Court, over an important issue of statutory

interpretation. The Clean Water Act generally

prohibits “the discharge of any pollutant” without

obtaining a permit from the Environmental Protection

Agency or the Army Corps of Engineers. 33 U.S.C.

§§ 1311(a), 1342, 1344. The Act defines “discharge of

a pollutant” as “any addition of any pollutant to

navigable waters from any point source.” Id.

§ 1362(12)(A). Thus, under the statute’s text, if a

person does not add pollutants to a “navigable water,”

then that person has not discharged a pollutant and

need not obtain a federal permit before engaging in an

activity within that jurisdictional water.

This Court has twice construed “addition” using

the traditional tools of statutory construction, found

no ambiguity, and held that there is no discharge of a

pollutant when water containing suspended

pollutants is moved between different parts of the

same waterbody. S. Florida Water Mgmt. Dist. v.

Miccosukee Tribe of Indians, 541 U.S. 95, 109–12

(2004), and Los Angeles Cnty. Flood Control Dist. v.

Natural Res. Def. Council, Inc., 568 U.S. 78, 82–84

(2013). This is because there can be no “addition” of a

pollutant unless there is an increase in pollutants to

the waterbody. Id. at 82. Or, as the Court colorfully

put it in both cases, “[i]f one takes a ladle of soup from

a pot, lifts it above the pot, and pours it back into the

pot, one has not ‘added’ soup or anything else to the

pot.” Miccosukee Tribe, 541 U.S. at 110; L.A. County,

568 U.S. at 82–83 (both quoting Catskill Mountains

4

Chapter of Trout Unlimited v. City of New York, 273

F.3d 481, 492 (2d Cir. 2001)).

Despite the Clean Water Act’s and this Court’s

clear direction, the Ninth Circuit below followed a

different course, creating a conflict with this Court

and deepening a conflict among the courts of appeals

over the statute’s meaning.

Respondent Idaho Conservation League (ICL)

sued Petitioner Shannon Poe under the Act’s citizen

suit provision, 33 U.S.C. § 1365, alleging that his

instream mining activities in an Idaho river resulted

in the unlawful discharge of pollutants. Mr. Poe

practices a form of placer mining.1 Instream miners

like Mr. Poe use an engine-powered hose to dredge

streambed materials—rocks, sand, gravel, or other

minerals or metals within a waterbody’s streambed—

and then run those materials through a sluice box.

Dredgers separate and trap the dense gold (and

similarly heavy metals, such as mercury) from other

streambed materials, remove and keep the heavy

metals, and let the remaining materials fall back to

the streambed, thus decreasing material within the

waterbody.

The Ninth Circuit nevertheless upheld summary

judgment for ICL. But the panel did not apply this

Court’s precedents in Miccosukee Tribe and L.A.

County—which established, under the Clean Water

Act’s ordinary meaning, that before there is an

1 Placer mining is, broadly speaking, the extraction of valuable

minerals from sediment. See Nadia H. Dahab, Note, Muddying

the Waters of Clean Water Act Permitting: NEDC Reconsidered,

90 Or. L. Rev. 335, 338 (2011). The specific type of placer mining

in this case is small-scale suction dredge mining.

5

“addition” of a pollutant, there must be an increase in

pollutants to a waterbody. The panel instead relied on

lower court precedents predating Miccosukee Tribe

and L.A. County, found the term “addition”

ambiguous, and applied Chevron deference to hold

that merely “resuspending” pollutants (here, the

riverbed materials) within a waterbody “may be

interpreted to be an addition of a pollutant under the

Act.” App. 8a–10a (citation omitted).

More still, this Court made it plain last Term that

when construing the Clean Water Act, not only should

courts start “with the text,” they should also consider

background clear statement principles grounded in

federalism and due process before blessing an

agency’s interpretation. Sackett v. EPA, 598 U.S. 651,

671, 679–81 (2023). Yet here, the Ninth Circuit turned

those principles on their head: not only is there no

clear statement in the Act supporting the Ninth

Circuit’s judgment, but the court’s ruling also directly

contradicts the ordinary meaning of the Act’s text.

In diverging from this Court’s precedents, the

panel also deepened a conflict among the courts of

appeals. After briefing was completed below, Mr. Poe

alerted the panel to North Carolina Coastal Fisheries

Reform Group v. Capt. Gaston LLC, 76 F.4th 291 (4th

Cir. 2023). In Gaston, a unanimous Fourth Circuit

panel cited L.A. County’s holding and applied the

ordinary meaning of “addition” to hold that there was

no “discharge of a pollutant” when fishing nets

“disturb[ed] the [Pamlico] Sound’s floor, causing

sediment [rocks and sand] to temporarily suspend in

the water.” Id. at 302. Put differently, there was no

“addition” of a pollutant when pollutants (ocean-bed

materials) were moved within and resuspended in a

6

single waterbody. That holding directly conflicts with

not only the Ninth Circuit’s ruling below, but also with

the decisions of other circuits finding “addition”

ambiguous.

It is important that this Court resolve these

conflicts and provide ordinary citizens with the

uniformity and clarity they are entitled to under the

law. Time and again, this Court has reaffirmed that

lower courts must apply the traditional tools of

statutory construction before deferring to the

executive branch’s legal interpretations. Indeed, even

in the age of Chevron deference, federal agencies are

bound by the law as written by Congress—and lower

courts must not reflexively defer to an agency’s view

of a statute’s meaning. When courts do so, they

abdicate their judicial duty, flout the Constitution’s

separation of powers, and deprive litigants of due

process.

And nowhere are these first principles more

critical than when courts construe the Clean Water

Act. The Act is a “potent weapon” imposing “crushing

consequences.” Sackett, 598 U.S. at 660, 671 (citation

omitted). Yet since the Act’s inception, lower courts

have often failed to provide meaningful judicial review

over the statute’s terms. This in turn has exposed

ordinary citizens to evolving, expanding, and

uncertain legal rules, the violation of which can lead

to ruinous citizen suits, crushing civil penalties, and

even criminal prosecution for engaging in everyday

conduct.

For these reasons, this Court has consistently

taken cases to enforce the Act’s textual boundaries,

including in Miccosukee Tribe, L.A. County, and

Sackett. It is also why this Court granted certiorari

7

over the “addition” issue in Borden Ranch Partnership

v. U.S. Army Corps of Engineers, 261 F.3d 810, 814–

15 (9th Cir. 2001), aff’d, 537 U.S. 99 (2002)

(affirmance by an equally divided Court)—a precedent

relied on by the Ninth Circuit below, App. 9a–10a. In

Borden Ranch the Ninth Circuit found “addition”

ambiguous and held that a farmer added pollutants to

a “navigable water” because he “redeposited” soil by

plowing his field. As Borden Ranch shows, and this

case confirms, the extra-textual rule adopted below

and followed by several other circuits—that the Act’s

“addition of any pollutant” element is ambiguous and

can be satisfied by the mere movement, resuspension,

or redeposit of material within a regulated

waterbody—captures

various

ordinary

and

environmentally benign activities.

Because of Justice Kennedy’s recusal in Borden

Ranch, this Court did not resolve the question

presented. This case is a good vehicle for the Court to

finally do so, provide the regulated public with clarity,

and ensure that the lower courts apply the law as

written by Congress. Certiorari should be granted.

STATEMENT OF THE CASE

A. The Clean Water Act

1. Congress enacted the Clean Water Act to

“restore and maintain the chemical, physical, and

biological integrity of the Nation’s waters.” 33 U.S.C.

§ 1251(a). To do so, the Act makes illegal, unless

otherwise permitted, the “discharge of any pollutant

by any person.” Id. § 1311(a). The statute defines

“pollutant” as, among other things, “dredged spoil,”

“rock,” “sand,” and “cellar dirt” that is “discharged into

water.” Id. § 1362(6). The Act then defines “discharge

8

of a pollutant” as “any addition of any pollutant to

navigable waters from any point source,” id.

§ 1362(12)(A), but it does not define “addition.”

The statute divides regulatory authority among

federal agencies and the states. Nonexempt

discharges to regulated waters (other than those of

dredged or fill material, which the Army Corps of

Engineers regulates, see id. § 1344) require a permit

from EPA (commonly called a National Pollutant

Discharge Elimination System (NPDES) permit). Id.

§ 1342(a). This permitting authority may be delegated

to the states, territories, and Indian tribes.2 See 33

U.S.C. §§ 1342(b), 1344(g), 1362(3), 1377(e). The Act

also delegates enforcement authority to private

parties: “any citizen” may bring a civil action against

any person who is alleged “to be in violation” of

specified provisions of the Act, including its NPDES

permitting requirement. See id. § 1365(a).

2. To prove a violation of the Act, would-be

enforcers have the burden to establish five elements:

(1) a “pollutant” must be (2) “discharged—there must

be an addition of a pollutant—(3) to “navigable

waters” (4) from (5) a “point source.” See Comm. to

Save Mokelumne River v. East Bay Mun. Util. Dist.,

13 F.3d 305, 308 (9th Cir. 1993) (citing Nat’l Wildlife

Fed’n v. Gorsuch, 693 F.2d 156, 165 (D.C. Cir. 1982)).

2 At the time of the alleged violations at issue here, EPA had not

delegated federal NPDES permitting power over suction dredge

mining to Idaho but has since done so. See EPA, NPDES General

Permit for Small Suction Dredge Placer Miners in Idaho,

https://www.epa.gov/npdes-permits/idaho-npdes-programauthorization.

9

If these elements are not met, then a person is not

subject to the Act.

3. If a person subject to the Act discharges

pollutants without a required permit or violates

permit conditions, he risks cease-and-desist orders,

compliance

orders,

administrative

penalties,

significant civil penalties and injunctions, and

criminal liability for even negligent violations. See 33

U.S.C. § 1319(a)–(d); 40 C.F.R. § 19.4 tbl.1 (allowing

for civil penalties of over $60,000 per day per

violation); Sackett, 598 U.S. at 660 (persons who

“negligently discharge ‘pollutants’ into covered waters

may face severe criminal penalties including

imprisonment”); Rapanos v. United States, 547 U.S.

715, 721 (2006) (“[T]he Clean Water Act imposes

criminal liability, as well as steep civil fines, on a

broad range of ordinary industrial and commercial

activities.”) (cleaned up).

Private enforcers can seek injunctive relief and

civil penalties payable to the United States Treasury.

33 U.S.C. § 1319(b), (d). They can also recover

attorney fees, expert witness fees, and other litigation

costs for successful suits. Id. § 1365(d).

B. Factual and Procedural Background

1. Petitioner Shannon Poe is a gold miner who

engages in instream suction dredge mining—a form of

placer mining.3 Rather than pan for gold, Mr. Poe uses

Particularly in comparison to larger types of placer mining,

suction dredge mining’s environmental impact is limited. See

Dahab, Muddying, supra, at 339 (“[S]mall suction dredging is

more similar, at least with respect to the magnitude of its impact,

to hand panning than it is to large placer mining: with small

3

10

a suction dredge, a small engine-powered hose that

vacuums materials from the streambed. The

suctioned material is made to pass through a floating

sluice box, which separates and traps gold and other

heavy metals. The miner then removes and keeps the

gold while depositing the dangerous mercury at

proper disposal sites.4 The rest of the suctioned

material—the left-over rocks, sand, and other

material—then falls back into the water, ultimately

settling again on its native streambed.

2. In 2018, ICL sued Mr. Poe in the U.S. District

Court for the District of Idaho under the Clean Water

Act’s citizen suit provision.5 ICL alleged that Mr. Poe’s

suction dredge mining illegally discharged pollutants

into Idaho’s South Fork Clear Water River, a

navigable-in-fact water, in 2014, 2015, and 2018. App.

6a. It was undisputed below that Mr. Poe mined in the

river between 2014 and 2018. App. 22a. It was also

suction-dredging, the streambed volume disturbed is relatively

limited, as is the ancillary effect on sediment upstream and

downstream of the mining location.”).

Indeed, suction dredge mining often benefits the aquatic

environment because miners remove dangerous heavy metals,

such as mercury, found within streambeds. See Cal. State Water

Resources Control Bd., Mercury Losses and Recovery During a

Suction Dredge Test in the South Fork of the American River 7

(2005) (“The test showed that a typical suction dredge set up to

recover gold recovered about 98 percent of the mercury in the

high-mercury, test sediment sample.”).

4

5 Initially, Mr. Poe moved to dismiss the case for lack of subject

matter jurisdiction because ICL’s required notice of intent to sue

under the Clean Water Act’s citizen suit provision was defective,

see 33 U.S.C. § 1365(b)(1)(A), and because ICL lacked standing.

The motion was denied, and Mr. Poe did not appeal these issues.

See App. 6a–7a.

11

undisputed that the State of Idaho allowed instream

suction dredge mining in the river and that Mr. Poe

always obtained a permit from the Idaho Department

of Water Resources before mining. App. 49a. But on

advice from his attorney at the time, Mr. Poe never

sought an NPDES permit from EPA. App. 52a.6

On cross-motions for summary judgment, Mr. Poe

argued that under the ordinary meaning of

“addition”—as this Court had established in

Miccosukee Tribe and L.A. County—his dredging did

not add pollutants to the river. And he was thus not

required to obtain an NPDES permit. This is because

suction dredging does not result in the increase of any

material within a waterbody. App. 66a–67a. The

district court rejected that argument, holding instead

that, despite Miccosukee Tribe and L.A. County,

“addition” remains ambiguous, as the Ninth Circuit

had held in Rybachek v. EPA, 904 F.2d 1276, 1285 (9th

Cir. 1990), and Borden Ranch, 261 F.3d at 814–15.

App. 67a–69a. And based on those precedents, Mr.

Poe’s suction dredge mining resulted in the “addition”

of a pollutant. Id.7

After granting ICL summary judgment, the court

issued a separate opinion and order over remedies,

6 In 2014, EPA sent Mr. Poe a notice of violation. Through his

attorney, Mr. Poe disputed the notice, and he never heard back

from the agency. App. 52a–53a.

7 Below, Mr. Poe also argued that, even if his dredging added

pollutants to the river, those pollutants are “dredged or fill

material” regulated exclusively by the Corps, see 33 U.S.C.

§ 1344, so his mining still did not require a permit from EPA. The

district court rejected that argument and the Ninth Circuit

affirmed. App. 95a, 17a. Petitioner does not seek certiorari on

this issue.

12

enjoining Mr. Poe from suction dredge mining in the

river and ordering him to pay $150,000 to the United

States Treasury. App. 60a.8

3. On appeal, Mr. Poe renewed his argument that

Miccosukee Tribe and L.A. County clarified the

statutory meaning of “addition” and that they control

over Rybacheck and Borden Ranch.

Responding to that point, the panel started off on

the right foot by acknowledging that “[i]t is well

settled that the starting point for interpreting a

statute is the language of the statute itself,” and

“[w]hen interpreting a statute, [courts] use the

‘traditional tools of statutory construction,’ to

determine whether Congress directly addressed the

‘precise question at issue.’” App. 7a–8a (citations

omitted). But then the panel inexplicably ignored the

statutory text and skipped right to the Ninth Circuit’s

decisions in Rybachek and Borden Ranch.

Rybachek addressed, among other things, a facial

challenge to an EPA regulation that broadly sought to

regulate pollution from larger “placer mining”

activities under the NPDES permitting regime. 904

F.2d 1276.9 The challengers argued, among other

things, that instream placer mining did not result in

8 After the district court issued its remedies opinion and order,

ICL filed a motion for attorneys’ fees, costs, and other litigation

expenses totaling nearly $200,000. ECF Dkt. # 69. Though the

district court stayed that motion and held it in abeyance, ECF

Dkt. # 75, ICL has now filed a renewed motion for attorneys’ fees

in the amount of $264,440.25. See ECF Dkt. # 81.

9 The pollution limits set in these regulations do not apply to

Mr. Poe’s small-scale suction dredge mining. See 40 C.F.R.

§ 440.140(b) (exempting “dredges which process less than 50,000

cu yd of ore per year”).

13

the “addition” of pollutants to regulated waters, and

thus EPA could not regulate the activity. Id. at 1285.

The Ninth Circuit rejected this argument in a single

paragraph—with no textual analysis—and held that

“if the material discharged originally comes from the

streambed itself, such resuspension may be

interpreted to be an addition of a pollutant under the

Act.” Id.10 And so the court “defer[ed] to the EPA’s

interpretation of the word ‘addition.’” Id. at 1286.

(citing Chevron v. NRDC, 467 U.S. 837, 844 (1984)).

Borden Ranch, in turn, relied on Rybachek to hold that

deep plowing in regulated wetlands results in the

“addition” of pollutants even though it does not

“involve the introduction of material brought in from

somewhere else” and even though “no new material

has been ‘added . . . .’” 261 F.3d 814–15. Because

“addition” is ambiguous under these precedents, the

panel below concluded that the resuspension of rocks

and sands from Mr. Poe’s suction dredge mining

qualifies as the “addition of any pollutant” even

though those materials came from the bed of the

stream itself. App. 67a.

As for Miccosukee Tribe and L.A. County, the

panel distinguished those cases because they involved

“polluted water [] transferred from one location to

another within the same waterbody,” and Mr. Poe’s

dredge mining involves “excavat[ing] rocks, gravel,

The opinion relied on Avoyelles Sportsmen’s League, Inc. v.

Marsh, 715 F.2d 897, 923 (5th Cir. 1983), and United States v.

M.C.C. of Florida, Inc., 772 F.2d 1501, 1506 (11th Cir. 1985).

Both decisions, in turn, applied broad deference to the EPA’s

view that “redeposit”—in contexts the Rybachek court found

similar to placer mining—may be considered an “addition” of a

pollutant. Rybachek, 904 F.2d at 1285–86.

10

14

sand, sediment, and silt from the riverbed,” which are

then discharged into the same waterbody. App. 10a–

11a. Yet the panel left unexplained why the precise

location of pollutants within a regulated waterbody

should make a legal difference.

Mr. Poe also argued that, even if “addition” is

ambiguous, Rybachek’s reliance on Chevron conflicts

with this Court’s recent decision in Sackett, which

precludes deference under supposedly ambiguous

statutes that impose significant civil liability and

criminal sanctions for ordinary, everyday conduct.

App. 10a–13a. Yet the panel did not cite Sackett, much

less address Mr. Poe’s argument based on that ruling.

Mr. Poe then moved for rehearing en banc, which

was denied. App. 97a.

REASONS FOR GRANTING THE PETITION

I.

The Ninth Circuit’s decision conflicts with

this Court’s precedents construing the

Clean Water Act.

A. The Ninth Circuit’s decision conflicts

with this Court’s decisions in Miccosukee

Tribe and L.A. County.

Under the ordinary meaning of “addition,” a

person does not discharge pollutants under the Clean

Water Act unless he increases the amount of

pollutants in a jurisdictional water. The Court

confirmed this commonsense interpretation of the

statute in both Miccosukee Tribe, 541 U.S. at 109–12,

and L.A. County, 568 U.S. at 82–84.

In neither case did this Court find “addition”

ambiguous; it simply employed traditional tools of

statutory construction and then applied the resulting

15

legal rule—the ordinary meaning of the term. Indeed,

the Court held in Miccosukee Tribe that “the transfer

of polluted water between ‘two parts of the same water

body’ does not constitute a discharge of pollutants

under the CWA.” L.A. County, 568 U.S. at 82 (citation

omitted). The Court “derived that determination from

the CWA’s text, which defines the term ‘discharge of a

pollutant’ to mean ‘any addition of any pollutant to

navigable waters from any point source.’” Id. (citing

33 U.S.C. § 1362(12)). And “[u]nder a common

understanding of the meaning of the word “add,” no

pollutants are “added” to a water body when water is

merely transferred between different portions of that

water body.” Id. (citing Webster’s Third New

International Dictionary 24 (2002) (“add” means “to

join, annex, or unite (as one thing to another) so as to

bring about an increase (as in number, size, or

importance) or so as to form one aggregate”)

(emphasis added)).11 Neither the Ninth Circuit’s

decision below nor the precedents it relies on can be

squared with this Court’s rulings.

First, in Rybachek, the Ninth Circuit reflexively

deferred to the EPA’s view that “resuspension” could

be the “addition” of a pollutant. Rybachek was a broad

challenge to a regulation of many forms of placer

mining, including mining that takes place both on

11 This Court’s construction of “addition” is bolstered by statutory

context, which shows that Congress wanted to cabin the statute’s

scope by including “addition” as a term of limitation. Cf. S.D.

Warren Co. v. Maine Bd. of Env’t Prot., 547 U.S. 370, 380–81

(2006) (“The triggering statutory term” under NPDES permitting

“is not the word ‘discharge’ alone, but ‘discharge of a pollutant,’

a phrase made narrower by its specific definition requiring an

‘addition’ of a pollutant to the water.”) (emphasis added).

16

shore and instream.12 Reasonably enough, the court

held that “if the material discharged is not from the

streambed itself, but from the bank alongside, this is

clearly the discharge into navigable waters of a

pollutant under the Act.” 904 F.2d at 1285. And

“[b]ecause, under this scenario, the material

discharged is coming not from the streambed itself,

but from outside it, this clearly constitutes an

‘addition.’” Id.

Yet Rybachek did not stop there. In a single

paragraph—without employing the traditional tools of

statutory construction—it then found, applying

Chevron deference, that “even if the material

discharged originally comes from the streambed itself,

such resuspension may be interpreted to be an

addition of a pollutant under the Act.” Id. (emphasis

added). This statutory analysis applying broad and

reflexive deference, which the panel below relied on,

conflicts with this Court’s decisions in Miccosukee

Tribe and L.A. County applying the ordinary meaning

of “addition” under the Clean Water Act.

Nor can Borden Ranch be reconciled with this

Court’s precedents. Indeed, the Ninth Circuit’s

holding—that the plowing of wet farm fields results in

the “addition” of pollutants because dirt is moved

around within those fields—makes no sense under the

ordinary meaning of “addition.” As Judge Gould

observed in dissent, “the return of soil in place after

deep plowing is not a ‘discharge of a pollutant.’” 261

F.3d at 819 (Gould, J., dissenting). Although through

plowing “the hydrological regime is modified,” any

12 Noticeably absent from 40 C.F.R. § 440.140 is any attempt by

EPA to define “addition” of a pollutant.

17

such ecological impact is irrelevant, because

“Congress spoke in terms of discharge or addition of

pollutants, not in terms of change of the hydrological

nature of the soil.” Id. at 820. And just as the plowing

in Borden Ranch involved no movement of

“process[e]d” material “to a substantially different

location,” see id., the same is true of suction dredge

mining, which entails merely the passing of gravel

and sand through a floating sluice box. See David

Bernell et al., Inst. For Natural Resources, Or. State

Univ., Recreational Placer Mining in the Oregon

Scenic Waterways System 44 (2003) (“There is no

discharge of pollutants into the waterways, [and]

there are no chemical components being used in the

mining process . . . .”).13

Second, the panel’s attempt to distinguish

Rybachek from this Court’s precedents was also

misplaced because there is no legal difference between

Rybachek’s ultimate judgment and this Court’s

holdings in Miccosukee Tribe and L.A. County. See

App. 10a–11a. In both cases, the Court did not hold

that “simply transferring water,” id. at 11a, between

two parts of the same waterbody was not an “addition”

of a pollutant. Those cases held that transferring

water—which contained pollutants—between parts of

the same waterbody was not an addition of a

pollutant. See L.A. County, 568 U.S. at 80.

To be sure, Miccosukee Tribe and L.A. County both

concerned the movement of polluted “water”—and

suction dredge mining “[p]ick[s] up the bed material,”

including “rock and sand,” from the streambed. App.

11a. But this distinction makes no legal difference,

13 Available at https://bit.ly/34W5AcW.

18

and the Ninth Circuit did not even attempt to explain

any legal difference. This is for a good reason: as far

as Mr. Poe is aware, no court has ever held that a

regulated water’s streambed and the material on or

within it are not part of the “navigable water” itself.

See United States v. Moses, 496 F.3d 984, 991 (9th Cir.

2007) (“[A]s the Supreme Court has recognized,

regardless of any other disagreements, ‘no one

contends that federal jurisdiction appears and

evaporates along with the water in such regularly dry

channels.’”) (quoting Rapanos, 547 U.S. at 733 n.6).

That should not be surprising—were the rule

otherwise, a person would be free to flout all the Clean

Water Act’s provisions by simply discharging

pollutants when a “navigable water” is dry. But see

Sackett, 598 U.S. at 671 (adopting the Rapanos

plurality’s view that the Clean Water Act’s “use of

‘waters’

encompasses

‘only

those

relatively

permanent, standing or continuously flowing bodies of

water’”); Rapanos, 547 U.S. at 732 n.5 (“By describing

‘waters’ as ‘relatively permanent,’ we do not

necessarily exclude streams, rivers, or lakes that

might dry up in extraordinary circumstances, such as

drought. We also do not necessarily exclude seasonal

rivers, which contain continuous flow during some

months of the year but no flow during dry months[.]”).

To put a slightly different spin on the analogy the

Court used in Miccosukee Tribe and L.A. County,

imagine if soup contained vegetables that are ladled

from the bottom of a pot, then the soup with the same

vegetables is returned to the pot. No one would think

someone increased the amount of vegetables in, or

added different vegetables to, the soup or the pot. But

if someone then added, say meat to the soup from a

19

different pot, then there would be an “addition” of

materials (or pollutants).14

At bottom, this Court’s decisions in Miccosukee

Tribe and L.A. County should have controlled the legal

analysis below where an instream suction dredge

miner takes materials (the soup) from the waterbody

(the pot) and moves those materials through his

dredge (the ladle) and then returns some of those

same materials back to the waterbody (the pot). In

both instances, no new materials are added to the

“navigable waters”—thus there can be no increase of

pollutants. The Ninth Circuit’s judgment, applying

Rybachek’s holding that deference is owed to EPA’s

view that resuspending pollutants within a

waterbody, sharply departs from this Court’s

precedents and the Clean Water Act’s ordinary

meaning.

B. The Ninth Circuit’s decision conflicts

with this Court’s application of clear

statement rules in Sackett.

Mr. Poe argued below that Chevron deference was

precluded by this Court’s recent decision in Sackett,

which explained that “background principles of

construction” require EPA to “provide clear evidence

that it is authorized to regulate in the manner it

proposes.” 598 U.S. at 679. Yet the panel simply

ignored Mr. Poe’s argument and did not address

14 See

Jeffrey G. Miller, Plain Meaning, Precedent, and

Metaphysics: Interpreting the “Addition” Element of the Clean

Water Act Offense, 44 Envtl. L. Rep. News & Analysis 10770,

10800 (2014) (arguing that Miccosukee Tribe rejected the

argument that redepositing pollutants from the same regulated

water could add new or different pollutants).

20

Sackett at all in its opinion. The Court should

therefore take this case and clarify that Sackett means

what it says: lower courts should not defer to executive

branch agencies’ statutory interpretations under the

Clean Water Act.

First, background principles of construction

“require Congress to enact exceedingly clear language

if it wishes to significantly alter the balance between

federal and state power[.]” Id. (citation omitted). This

is because “[r]egulation of land and water use lies at

the core of traditional state authority” and an “overly

broad interpretation of the [Act’s] reach would

impinge on this authority.” Id. at 679–80. Here, EPA’s

overbroad view of “addition” has expanded the Clean

Water Act’s reach to normal productive activities like

instream mining (this case) and farming (see Borden

Ranch) with no clear statement for that authority.

Worse still, the Ninth Circuit’s blessing of this flawed

view of the statute has allowed private enforcers to

infringe on the states’ (and even the federal

government’s) enforcement authority with no clear

statement. Indeed, in Mr. Poe’s case, he annually

obtained a permit from the State of Idaho before

suction dredge mining, App. 49a, with EPA being fully

aware of his activity, yet he is now facing ruinous fines

in federal court through a citizen suit based on a

supposedly “reasonable” view of the statute.

Second, fair notice and “[d]ue process require[]

Congress to define penal statutes with sufficient

definiteness that ordinary people can understand

what conduct is prohibited and in a manner that does

not encourage arbitrary and discriminatory enforcement.” Id. at 680 (cleaned up). And “[w]here a penal

statute could sweep so broadly as to render criminal a

21

host of what might otherwise be considered ordinary

activities, we have been wary about going beyond

what ‘Congress certainly intended the statute to

cover.’” Id. at 681 (quoting Skilling v. United States,

561 U.S. 358, 404 (2010)). Under the Ninth Circuit’s

judgment, whenever materials are removed from a

riverbed and resuspended within a regulated water,

there is a regulable “addition” of pollutants. That rule

contains little to no limiting principle for what conduct

could be illegal. For example, imagine if someone

scooped sand (pollutants) from the riverbed with a

shovel (a point source), picked out the aesthetically

pleasing rocks, and “resuspended” (added) the leftover materials back into the water. Federal criminal?

Simply put, after Sackett, a clear statement is

required from Congress before courts can

mechanically accept agencies’ interpretations of the

Clean Water Act. And these clear statement rules

enunciated in Sackett mean here that any ambiguity

in “addition” should be resolved in favor of the

regulated party. Yet the Ninth Circuit’s decision

below, by effectively creating ambiguity and resolving

that ambiguity against the regulated party, did not

just fail to follow these principles; it turned them on

their head. Certiorari is warranted.

II. The Ninth Circuit’s decision deepens an

already entrenched conflict over the

meaning of “addition” under the Clean

Water Act.

Besides conflicting with decisions of this Court,

the Ninth Circuit’s decision below deepens an already

entrenched split among lower courts over the

statutory meaning of “addition of any pollutant.” For

many years after the Act’s passage—but before this

22

Court provided guidance over the meaning of

“addition”—the various circuit courts often found the

term ambiguous, gave broad deference to the

executive branch, and issued conflicting decisions over

the Act’s scope.15 This Court should grant certiorari

and provide clarity and uniformity to the law.

Some courts of appeals, although in a few

instances applying broad deference, ultimately issued

decisions consistent with the statute’s ordinary

meaning and this Court’s precedent in Miccosukee

Tribe and L.A. County: moving or resuspending

pollutants within a navigable water is not the

“addition” of pollutants. See, e.g.,

Gorsuch, 693 F.2d at 174–75 (giving deference

to EPA’s position about dams as point

sources—and that the “addition from a point

source occurs only if the point source itself

physically introduces a pollutant into water

from the outside world”);

Nat’l Mining Ass’n v. U.S. Army Corps of

Eng’rs, 145 F.3d 1399, 1404 (D.C. Cir. 1998)

(“[T]he straightforward statutory term

‘addition’ cannot reasonably be said to

encompass the situation in which material is

15 Indeed,

most if not all circuit court decisions construing

“addition” and deferring to EPA or the Corps’ view predated this

Court’s decisions in Miccosukee Tribe and L.A. County. See Nat’l

Wildlife Fed’n v. Gorsuch, 693 F.2d 156, 174–75 (D.C. Cir. 1982);

Avoyelles Sportsmen’s League v. Marsh, 715 F.2d 897, 922–25

(5th Cir. 1983); United States v. M.C.C. of Florida, Inc., 772 F.2d

1501, 1506 (11th Cir. 1985); Nat’l Wildlife Fed’n v. Consumers

Power Co., 862 F.2d 580, 585 (6th Cir. 1988); Rybachek v. EPA,

904 F.2d 1276, 1285 (9th Cir. 1990); Borden Ranch P’ship v. U.S.

Army Corps of Eng’rs, 261 F.3d 810, 814–15 (9th Cir. 2001).

23

removed from the waters of the United States

and a small portion of it happens to fall

back.”);

Nat’l Wildlife Fed’n v. Consumers Power Co.,

862 F.2d 580, 585 (6th Cir. 1988) (following

Gorsuch to hold that “manipulation of water

by [a point source that] changes the form of

the pollutant from live fish to a mixture of live

and dead fish in the process of generating

electricity . . . does not mean that the [point

source] ‘adds’ a pollutant to Lake Michigan”);

Catskill Mountains, 273 F.3d at 492 (“The

Gorsuch and Consumers Power decisions

comport with the plain meaning of ‘addition’

. . . .”);

United States v. Law, 979 F.2d 977, 979 (4th

Cir. 1992) (“[W]here ‘pollutants’ exist[] . . . in

the waters of the United States before contact

with [point sources], the mere diversion in the

flow of the waters [does] not constitute

‘additions’ of pollutants to the waters.”).

Other courts of appeals decisions—including the

Ninth Circuit’s precedent relied on below—often

applied broad deference and ultimately came to a

decision not reflecting the statute’s ordinary meaning

or consistent with this Court’s precedent. See, e.g.,

United States v. Deaton, 209 F.3d 331, 335

(4th Cir. 2000) (“The idea that there could be

an addition of a pollutant without an addition

of material seems to us entirely unremarkable

. . . .”);

24

Rybachek, 904 F.2d at 1285–86 (“[E]ven if the

material discharged originally comes from the

streambed itself, such resuspension may be

interpreted to be an addition of a pollutant

under the Act.”);

Borden Ranch, 261 F.3d at 814–15 (deep

plowing of vernal pool wetlands to plant

orchards and vineyards results in the addition

of a pollutant (soil) even though “no new

material has been ‘added’”);

Ayoyelles Sportsmen’s League, 715 F.2d at 923

(“The word ‘addition,’ as used in the definition

of the term ‘discharge,’ may reasonably be

understood to include ‘redeposit.’”);

United States v. M.C.C. of Florida, Inc., 772

F.2d 1501, 1506 (11th Cir. 1985) (a tugboat

propeller’s stirring up of sediment onto

submerged sea grass beds was an “addition”

of “dredged spoil” pollution).

Most recently, the Fourth Circuit in Gaston

applied this Court’s precedent in L.A. County and the

ordinary meaning of the Act’s text. Gaston concerned

a private enforcement action under the Clean Water

Act’s citizen suit provision. The suit alleged that the

owners of certain shrimp trawlers violated the Clean

Water Act because they discharged pollutants into a

jurisdictional water without a NPDES permit. 76

F.4th at 302–04. The private-party enforcers in that

case argued that the shrimp trawlers’ nets “disturb

the Sound’s floor, causing sediment [i.e., rocks and

sand] to temporarily suspend in the water.” Id. at 302.

And thus, the shrimp trawlers added pollutants to the

Pamlico Sound. Id. But a unanimous Fourth Circuit

25

panel rejected that claim because the “rocks and sand”

allegedly “discharged” from the Sound’s floor (the bed

of the navigable water) were not added—those

materials were already “present in the body of

water[.]” Id. at 304. “[M]oving that pollutant around

inside that same body of water is not discharging it—

nothing is added.” Id. (citing L.A. County, 568 U.S. at

82–83).

Gaston directly conflicts with not only the Ninth

Circuit’s decision here, but many decisions cited

above. Indeed, the panel’s decision below (and thus

Rybachek) conflicts with Gaston in two ways. First,

the Fourth Circuit did not find “addition”

ambiguous—it followed this Court’s precedent in L.A.

County and applied the term’s ordinary meaning. 76

F.4th at 304. Second, the Fourth Circuit found that

materials suspended in the water coming from the

ocean floor did not “add” any pollutants because the

materials were “already present in the body of water.”

Id. That holding conflicts with the panel’s purported

distinction below that Mr. Poe added materials to the

river because they came from the riverbed.

This Court should grant certiorari and resolve

these conflicts to bring uniformity to the Clean Water

Act.

III. This case is a good vehicle for the Court to

clarify an exceptionally important issue of

statutory interpretation under the Clean

Water Act.

1. As this Court’s rulings in Miccosukee Tribe and

L.A. County show, the Ninth Circuit’s application of

Chevron deference flouts the Clean Water Act’s text.

And as many members of this Court have explained,

26

reflexively granting executive branch agencies broad

deference (or any deference at all) is incompatible

with the separation of powers and due process of

law.16 That is the primary reason why this Court is

now considering whether to overrule or limit Chevron.

See Loper Bright Enterprises v. Raimondo, 143 S. Ct.

2429 (2023) (No. 22-451), cert. granted in part May 1,

2023. If this Court does so, then there will be no basis

in law for the Ninth Circuit’s judgment.17 And in any

event, even under Chevron, courts should begin with

a statute’s text and end there if the meaning is clear.

Brett M. Kavanaugh, Fixing Statutory Interpretation,

129 Harv. L. Rev. 2118, 2153 n.175 (2016) (“Chevron

told us explicitly that we should employ all the

‘traditional tools of statutory construction’ to resolve

any statutory ambiguity before we defer to an

agency. . . . [I]n those cases, we would not have to

defer to the agency at all.”). The Ninth Circuit failed

to follow these instructions below and it is important,

regardless of Chevron’s fate, that the lower courts be

See, e.g., Pereira v. Sessions, 585 U.S. 198, 219–21 (2018)

(Kennedy, J., concurring); Michigan v. EPA, 576 U.S. 743, 760–

64 (2015) (Thomas, J., concurring); Perez v. Mortgage Bankers

Ass’n, 575 U.S. 92, 109–10 (2015) (Scalia, J., concurring in the

judgment); Gutierrez-Brizuela v. Lynch, 834 F.3d 1142, 1149–58

(10th Cir. 2016) (Gorsuch, J., concurring); Kavanaugh, Fixing,

supra, at 2150–54.

16

17 The Court may wish to hold this Petition until Loper Bright is

resolved and, if appropriate, grant, vacate, and remand. If this

Court overrules Chevron—or even if it modifies Chevron

deference without overruling the doctrine—it will directly affect

the Ninth Circuit’s opinion and judgment below. See Lawrence

on Behalf of Lawrence v. Chater, 516 U.S. 163, 166 (1996) (per

curiam) (“[This Court has] GVR’d in light of a wide range of

developments, including our own decisions[.]”).

27

prevented from skirting their duty to interpret

statutes fully and faithfully.

2. Ensuring that lower courts employ the

traditional tools of statutory construction is also vital

when the Clean Water Act is at issue. Indeed, because

the Act’s reach is often unclear, it is unfortunately all

too easy for citizens acting in good faith to violate the

Act’s “regime of strict liability.” Cnty. of Maui v.

Hawaii Wildlife Fund, 140 S. Ct. 1462, 1489 (2020)

(Alito, J., dissenting). And the decision below aids this

regime by significantly expanding the Act’s nonlegislative scope, a trend over which this Court has

repeatedly expressed concern. See, e.g., Sackett, 598

U.S. at 660–61 (noting how the Act’s “expansive

interpretations” combined with its civil and criminal

penalties can be “crushing” and citing as an example

Borden Ranch’s adoption of EPA’s argument that each

of 348 passes of a plow by a farmer was a separate

offense).

This Court found the “addition” issue cert-worthy

in Borden Ranch, but the Ninth Circuit’s judgment

was affirmed by an equally divided Court because of

Justice Kennedy’s recusal. Yet the reasons for this

Court’s review now are just as, if not more, strong

than they were then. Indeed, commentators have

continuously underscored the need for this Court’s

intervention to narrow how the lower courts have

interpreted “addition.” See, e.g., Miller, “Addition,”

supra, at 10773, 10803 (advocating for construing

“addition” to mean “the act of a person adding a

pollutant to navigable waters from a point source,

when that pollutant would not otherwise be in those

navigable waters” and observing that the contrary

28

“redeposit” decisions “push ‘addition’ to its outer

limit”).18

3. The question presented is also important

because ordinary citizens ought to have the benefit of

clarity in the law because they are often subject to

private enforcement of extra-textual interpretations

of the Act. And the Ninth Circuit’s decision below

further entrenches the ability of private groups to sue

in federal court for often innocent violations, collect

money for the United States Treasury, and obtain

attorneys’ fees for doing so. See Friends of the Earth,

Inc. v. Laidlaw Env’t Servs. (TOC), Inc., 528 U.S. 167,

209–10 (2000) (Scalia, J., dissenting) (observing how

citizen plaintiffs’ “massive bargaining power . . . is

often used to achieve settlements requiring the

defendant to support environmental projects of the

plaintiffs’ choosing”). See also Marc Robertson,

Environmental Ambulance Chasing: DOJ Urges Court

18 See also, Adam Gerber, Casenote, Borden Ranch Partnership

v. U.S. Army Corps of Engineers: A Barge in a Bucket? May

Isolated Wetlands Be Considered “Navigable Waters” Under the

CWA?, 15 Vill. Envtl. L.J. 415, 433 (2004) (noting that the rule

in cases like Borden Ranch “could impose severe regulatory

burdens”); Arthur F. Coon, Is Plowing a Point Source Discharge?

The Aftermath of Borden Ranch, 18-SUM Nat. Resources & Env’t

6, 7 (Summer 2003) (arguing that “the Ninth Circuit’s holding in

Borden Ranch is wrong on the law, and should ultimately be

overruled by the U.S. Supreme Court if the same issues arise

again in another case”). Cf. Timothy S. Bishop et al., Counting

the Hands on Borden Ranch, 34 Envtl. L. Rep. (Envtl. L. Inst.)

10,040 (2004) (noting the parallel between the argument that

“moving water around within a single water body cannot amount

to an ‘addition’ of a pollutant” and the Borden Ranch petitioners’

position that “moving soil around within a wetland cannot be the

‘addition’ of a pollutant because it adds nothing new to the

wetland”).

29

To Scrutinize Clean Water Citizen-Suit Settlements,

Forbes (June 26, 2018) (describing a Department of

Justice court filing raising concerns about a law firm’s

abusive use of Clean Water Act citizen suits).19

Mr. Poe’s plight is a fitting example. He did not

seek an NPDES permit because, on advice from his

attorney, he believed that he need only obtain a

permit from the State of Idaho. App. 52a. That

reasonable position, see Miccosukee Tribe and L.A.

County, has him now facing financially ruinous civil

penalties and attorneys’ fees under the Act’s private

enforcement provision.

4. This case is a good vehicle to resolve the

conflicts over the Clean Water Act’s meaning and

scope. The pertinent conflicts are squarely presented,

and the Ninth Circuit issued a published decision

expressly holding: (1) “addition” is ambiguous and

merits Chevron deference, and (2) the mere movement

or resuspension of materials or pollutants within a

waterbody can be considered the “discharge of a

pollutant” under the Act, 33 U.S.C. § 1362(12). App

7a–13a. Now is also the right time for the Court to

resolve the conflict. This Court decided Miccosukee

Tribe in 2004 and L.A. County in 2013, yet the conflict

among the circuits has persisted. There is no need for

awaiting further percolation.

At bottom, whether the activity is small-scale

mining, normal farming practices, or shrimp trawling,

the legal issue raised here concerns thousands of

citizens across the nation and merits this Court’s

review.

19 Available at https://bit.ly/3R0xFIW.

30

CONCLUSION

The Clean Water Act is among the most

complicated statutes in the federal code. But as this

Court’s precedents show, its terms and scope can be

discerned by applying the traditional tools of statutory

construction. Yet lower courts continue to reflexively

and broadly defer to the executive branch’s view of the

statute—which can lead to severe civil penalties and

other life altering consequences. This enforcement

action and the Ninth Circuit’s decision below are

prime examples of this backwards regime. But this

case gives the Court a chance to remedy these ills by

clarifying (once again) the meaning of “addition” and

properly limiting EPA’s authority over everyday

productive activity—and the private enforcement of

that authority. The Petition for Writ of Certiorari

should be granted.

DATED: March 2024.

Respectfully submitted,

DAMIEN M. SCHIFF

Pacific Legal Foundation

555 Capitol Mall,

Suite 1290

Sacramento, CA 95814

DANIELLE R. BETTENCOURT

Fairfield and Woods P.C.

1801 California St.,

Suite 2600

Denver, CO 80202-2645

FRANK D. GARRISON

Counsel of Record

Pacific Legal Foundation

3100 Clarendon Blvd.,

Suite 1000

Arlington, VA 22201

Telephone: (202) 888-6881

FGarrison@pacificlegal.org

Counsel for Petitioner Shannon Poe

APPENDIX

i

Appendix

Table of Contents

Opinion, U.S. Court of Appeals for the Ninth

Circuit, filed November 20, 2023 ........................ 1a

Memorandum Decision and Order Re:

Plaintiff Idaho Conservation League’s

Motion for Remedies, U.S. District Court,

District of Idaho, filed September 28, 2022 ...... 21a

Memorandum Decision and Order Re:

Idaho Conservation League’s Motion for

Summary Judgment on Liability and

Shannon Poe’s Motion for Summary

Judgment, U.S. District Court,

District of Idaho, filed June 4, 2021 ................. 61a

Order (denying petition for rehearing en banc),

U.S. Court of Appeals for the Ninth

Circuit, filed January 11, 2024 ......................... 97a

1a

FOR PUBLICATION

UNITED STATES COURT OF APPEALS

FOR THE NINTH CIRCUIT

IDAHO CONSERVATION

LEAGUE,

Plaintiff-Appellee,

No. 22-35978

D.C. No. 1:18-cv00353-REP

v.

SHANNON POE,

OPINION

Defendant-Appellant.

Appeal from the United States District Court

for the District of Idaho

Raymond Edward Patricco, Jr.,

Magistrate Judge, Presiding

Argued and Submitted October 5, 2023

Seattle, Washington

Filed November 20, 2023

Before: KIM McLANE WARDLAW and MILAN D.

SMITH, JR., Circuit Judges, and ROBERT L.

HINKLE,* District Judge.

Opinion by Judge Milan D. Smith, Jr.

_________________________________________________

* The Honorable Robert L. Hinkle, United States District Judge

for the Northern District of Florida, sitting by designation.

2a

SUMMARY**

_________________________________________________

Environmental Law

The panel affirmed the district court’s grant of

summary judgment in favor of the Idaho Conservation

League in the League’s action under the Clean Water

Act against Shannon Poe, who engaged in instream

suction dredge mining, a method of placer mining, in

Idaho’s South Fork Clearwater River without a

National Pollutant Discharge Eliminating System

permit.

The panel held that to establish a violation of the

Clean Water Act’s NPDES requirements, also referred

to as Section 402 permitting, a plaintiff must prove

that the defendant (1) discharged, i.e., added (2) a

pollutant (3) to navigable waters (4) from (5) a point

source. As to the first element, the panel held that

Poe’s suction dredge mining “added” a pollutant to the

South Fork. The panel followed Rybachek v. EPA, 904

F.2d 1276 (9th Cir. 1990), which upheld

Environmental Protection Agency regulations

interpreting the Clean Water Act as prohibiting

discharges from placer mining sluice boxes unless

done in compliance with a Section 402 permit. In two

subsequent cases, S. Fla Water Mgmt. Dist. v.

Miccosukee Tribe of Indians, 541 U.S. 95 (2004), and

L.A. Cnty. Flood Control Dist. V. Nat. Res. Def.

Council, Inc., 568 U.S. 78 (2013), the Supreme Court

held that the transfer of polluted water from one

location to another within the same waterbody did not

** This summary constitutes no part of the opinion of the court.

It has been prepared by court staff for the convenience of the

reader.

3a

constitute an “addition” of pollutants. Here, by

contrast, Poe excavated from the riverbed materials

that were not already suspended in the water. The

panel concluded that Rybachek was not “clearly

irreconcilable” with L.A. County or Miccosukee Tribe’s

holdings, and it therefore was still good law.

The panel further held that the processed material

discharged from Poe’s suction dredge mining was a

pollutant, not dredged or fill material, and therefore

required an NPDES permit under Section 402 of the

Clean Water Act, rather than a permit from the Army

Corps of Engineers under Section 404. Because the

meaning of the Act and its implementing regulations

was ambiguous, the panel deferred to the official joint

conclusion of the EPA and the Corps.

_________________________________________________

COUNSEL

Frank D. Garrison IV (argued), Pacific Legal

Foundation, Arlington, Virginia; Damien M. Schiff,

Pacific Legal Foundation, Sacramento, California;

Danielle Bettencourt, Fairfield and Woods PC,

Denver, Colorado; for Defendant-Appellant.

Bryan Hurlbutt (argued) and Laurence J. Lucas,

Advocates for the West, Boise, Idaho, for PlaintiffAppellee.

_________________________________________________

OPINION

M. SMITH, Circuit Judge:

This appeal raises questions of statutory

interpretation concerning the Clean Water Act

(CWA), 33 U.S.C. § 1311(a). For several years,

Shannon Poe engaged in instream suction dredge

4a

mining in Idaho’s South Fork Clearwater River (the

South Fork) without a National Pollutant Discharge

Eliminating System (NPDES) permit. Plaintiff Idaho

Conservation League (ICL) sued Poe, arguing that he

violated the CWA each time he operated a suction

dredge on the South Fork without an NPDES permit.

Poe countered that (1) his suction dredge mining did

not add pollutants to the South Fork and therefore did

not require an NPDES permit, and (2) even if his

suction dredge mining did add pollutants, those

pollutants are “dredged” or “fill” material regulated

exclusively pursuant to Section 404, not Section 402,

of the CWA. The district court granted summary

judgment to ICL. Poe appeals the judgment as to

liability. We affirm.

STATUTORY AND

REGULATORY BACKGROUND

Congress enacted the CWA “to restore and

maintain the chemical, physical, and biological

integrity of the Nation’s waters.” 33 U.S.C. § 1251(a).

The CWA “categorically prohibits any discharge of a

pollutant from a point source without a permit.”

Comm. to Save Mokelumne River v. E. Bay Mun. Util.

Dist., 13 F.3d 305, 309 (9th Cir. 1993). “[D]ischarge of

a pollutant” is defined as the “addition of any

pollutant to navigable waters from any point source

. . . .” 33 U.S.C. § 1362(12). The CWA defines

“pollutant” broadly to include “dredged spoil,” “solid

waste,” “rock,” “sand,” and “industrial . . . waste

discharged into water.” 33 U.S.C. § 1362(6). A point

source is “any discernible, confined and discrete

conveyance . . . .” 33 U.S.C. § 1362(14). Navigable

waters are defined as “the waters of the United States

. . . .” 33 U.S.C. § 1362(7). The CWA does not define

5a

what constitutes the “addition” of a pollutant. See 33

U.S.C. § 1362.

Before discharging any pollutant, one must obtain

a permit from either the Environmental Protection

Agency (the EPA) or the Army Corps of Engineers (the

Corps). See 33 U.S.C. §§ 1311(a), 1342, 1344. The

NPDES permitting program (also referred to as

Section 402 permitting) authorizes the EPA to issue

permits “for the discharge of any pollutant, or

combination of pollutants,” on the condition that the

discharge will otherwise comply with the CWA. 33

U.S.C. § 1342(a)(1). Section 404 of the CWA

authorizes the Corps to issue permits “for the

discharge of dredged or fill material . . . .” 33 U.S.C.

§ 1344(a). When a discharge requires a Section 404

permit, it does not require a Section 402 permit. See

33 U.S.C. § 1342(a)(1); 40 C.F.R. § 122.3(b). The CWA

does not define “discharge of dredged material” or

“dredged material.” See 33 U.S.C. §§ 1342, 1362.

FACTUAL AND PROCEDURAL BACKGROUND

Suction dredge mining is a method of placer

mining that uses a floating watercraft device with a

pump to suck water, riverbed sands, and minerals

through a nozzle. The water and riverbed material are

run through a “sluice box,” where gold and other

heavy metals are separated out. Water, sand, and

minerals are then discharged back into the river,

along with sediments and other pollutants. Dredging

creates tailing piles behind the dredge, where larger

and heavier processed riverbed materials are

discarded and settle to the river bottom nearby.

Tailing piles can rise to the surface level of the river

and can span most of the river’s width.

6a

Dredging overburden and bedrock involves

dismantling the riverbed by dislodging and moving

rocks and boulders, and breaking up tightly bound

sediments using the miner’s hands, the dredge nozzle,

and other tools, like crowbars. The resulting holes can

be several feet deep under the riverbed.

During the 2014, 2015, and 2018 dredge seasons,

Poe suction dredge mined forty-two days on the South

Fork, a navigable water located in north-central

Idaho. Poe never obtained an NPDES permit

pursuant to Section 402 of the CWA.

On August 10, 2018, ICL sued Poe, alleging that

Poe was violating the CWA by failing to obtain an

NPDES permit while dredging and discharging

sediment and other pollutants in the South Fork. On

December 21, 2018, Poe filed a motion to dismiss

arguing that (1) the district court lacked subject

matter jurisdiction because, in part, ICL’s 2017 and

2018 notice letters were not sent via certified mail as

required by the CWA and its implementing

regulations; and (2) ICL lacked standing to the bring

the suit in the first instance. The district court denied

the motion.

ICL then moved for summary judgment on

liability. Poe cross-moved for summary judgment. On

June 4, 2021, the district court granted summary

judgment to ICL, concluding that (1) Poe’s suction

dredge mining added pollutants to the South Fork,

thereby requiring an NPDES permit under Section

402 of the CWA; and (2) the processed material

discharged from Poe’s suction dredge mining was a

pollutant, not dredged or fill material, requiring an

NPDES permit under Section 402 of the CWA rather

than a permit under Section 404. The court thereafter

7a

enjoined Poe from suction dredge mining in the South

Fork without a valid CWA Section 402 permit and

imposed a $150,000 civil penalty. Poe appeals the

judgment as to liability.

JURISDICTION AND STANDARD OF REVIEW

We have jurisdiction pursuant to 28 U.S.C. § 1291.

We review de novo a district court’s decision to grant

summary judgment. Lopez v. Smith, 203 F.3d 1122,

1131 (9th Cir. 2000) (en banc). We “must determine

whether, viewing the evidence in the light most

favorable to the nonmoving party, there are any

genuine issues of material fact and whether the

district court correctly applied the relevant

substantive law.” Id. Summary judgment is

appropriate where “there is no genuine dispute as to

any material fact and the movant is entitled to

judgment as a matter of law.” Fed. R. Civ. P. 56(a).

ANALYSIS

I. Dumping Suction Dredge Mining Waste into

the South Fork Is an “Addition” of Pollutants

Pursuant to the CWA.

To establish a violation of the CWA’s NPDES

requirements, “a plaintiff must prove that defendant[]

(1) discharged, i.e., added (2) a pollutant (3) to

navigable waters (4) from (5) a point source.” Comm.

to Save Mokelumne River, 13 F.3d at 308. The parties

dispute the first element—whether Poe’s suction

dredge mining “added” a pollutant to the South Fork.

What amounts to the “addition” of a pollutant is

not defined under the CWA. “It is well settled that the

starting point for interpreting a statute is the

language of the statute itself.” Olympic Forest Coal. v.

Coast Seafoods Co., 884 F.3d 901, 905 (9th Cir. 2018)

8a

(quoting Gwaltney of Smithfield, Ltd. v. Chesapeake

Bay Found., Inc., 484 U.S. 49, 56 (1987)). “When

interpreting a statute, we first use the ‘traditional

tools of statutory construction,’ to determine whether

Congress directly addressed the ‘precise question at

issue.’” Id. (quoting Chevron, U.S.A., Inc. v. Nat. Res.

Def. Council, Inc., 467 U.S. 837, 843 n.9 (1984)). “If the

precise question at issue is addressed, then the

‘unambiguously expressed intent of Congress

controls.’” Id. (quoting Chevron, 467 U.S. at 843).

Where a statute is ambiguous, courts defer to the

reasonable interpretation of the agency charged with

administering that statute. See Chevron, 467 U.S. at

844.

Since the 1970s, the EPA has interpreted the CWA

as prohibiting discharges from placer mining sluice

boxes unless done in compliance with a Section 402

permit. See Trustees for Alaska v. EPA, 749 F.2d 549,

552–53 (9th Cir. 1984) (reviewing the EPA’s issuance

of Section 402 permits to gold placer miners in 1976

and 1977). In 1988, the EPA adopted industry-wide

regulations setting effluent limitations for Section 402

permits for gold placer miners, including gold mining

from floating dredges. See 40 C.F.R. § 440.140.

In Rybachek v. EPA, 904 F.2d 1276 (9th Cir. 1990),

miners challenged these regulations, arguing that

placer mining does not cause the “addition” of a

pollutant. We rejected that argument. We noted that

“resuspension” of streambed materials “may be

interpreted to be an addition of a pollutant under the

Act,” and we deferred to the EPA’s reasonable

interpretation that such activity constitutes the

“addition” of a pollutant under the CWA. Id. at 1285–

86 (first citing Avoyelles Sportsmen’s League, Inc. v.

9a

Marsh, 715 F.2d 897, 923 (5th Cir. 1983) (stating that

“[t]he word ‘addition,’ as used in the definition of the

term ‘discharge,’ may reasonably be understood to

include ‘redeposit’”); and then citing United States v.

M.C.C. of Florida, Inc., 772 F.2d 1501, 1506 (11th Cir.

1985) (action of digging up sediment and redepositing

it on sea bottom by boat propellers constitutes an

addition of pollutants), vacated and remanded on

other grounds, 481 U.S. 1034 (1987)). We further

explained: “Because the EPA has been charged with

administering the [CWA], we must show great

deference to the Agency’s interpretation of the Act. We

especially defer where the Agency’s decision on the

meaning or reach of the [CWA] involves reconciling

conflicting policies committed to the Agency’s care and

expertise under the Act.” Id. at 1284 (citation

omitted).

Poe’s mining activities fall squarely within the

scope of Rybachek. Undisputed evidence in the record,

including photos and descriptions of Poe’s dredge

operating on the South Fork, shows that he

“excavate[d] the dirt and gravel” in the river using a

high-pressure blaster nozzle, “extract[ed] any gold”

and other heavy metals, and “discharge[d] the dirt

and other non-[heavy metal] materials into the

water.” See id. at 1285. That is, Poe engaged in placer

mining “subject to regulation under the [CWA].” Id.

Poe, therefore, “added” pollutants to the South Fork.

See id. (“[W]e will not strike down the EPA’s finding

that placer mining discharges pollutants within the

meaning of the Act.”); see also Borden Ranch P’ship v.

U.S. Army Corps of Engineers, 261 F.3d 810, 814 (9th

Cir. 2001) (reaffirming Rybachek, which “held that

removing material from a stream bed, sifting out the

gold, and returning the material to the stream bed

10a

was an ‘addition’ of a pollutant’”), aff’d, 537 U.S. 99

(2002).

In response, Poe argues that (1) Rybachek is no

longer good law in light of subsequent Supreme Court

decisions or, in the alternative, (2) the court should

not apply Chevron deference and overrule Rybachek.

Neither argument is persuasive.

Poe suggests that the Supreme Court has, since

Rybachek, twice confirmed the “commonsense

interpretation” of the CWA—i.e., that a person does

not illegally discharge a pollutant unless he or she

adds new material from the outside world. See S. Fla.

Water Mgmt. Dist. v. Miccosukee Tribe of Indians, 541

U.S. 95 (2004); L.A. Cnty. Flood Control Dist. v. Nat.

Res. Def. Council, Inc., 568 U.S. 78 (2013). That is,

according to Poe, Miccosukee Tribe and L.A. County

eviscerate the logic of Rybachek. But these cases are

both distinguishable from Rybachek and inapposite

here. In Miccosukee Tribe, polluted water was

removed from a canal, transported through a pump

station, and deposited into a reservoir a short distance

away. See 541 U.S. at 98–99. The Court held that

pumping polluted water from, and back into, the same

body of water, without more, “cannot constitute an

‘addition’ of pollutants.” Id. at 109–10 (“As the Second

Circuit put it in Trout Unlimited, if one takes a ladle

of soup from a pot, lifts it above the pot, and pours it

back into the pot, one has not ‘added’ soup or anything

else to the pot.” (citing Catskill Mountains Chapter of

Trout Unlimited, Inc. v. City of N.Y., 273 F.3d 481, 492

(2d Cir. 2001) (cleaned up)). In L.A. County, the Court

held that “the flow of water from an improved portion

of a navigable waterway into an unimproved portion

of the very same waterway does not qualify as a

11a

discharge of pollutants under the CWA.” 568 U.S. at

83. In both cases, polluted water was transferred from

one location to another within the same waterbody.

Here, by contrast, Poe excavated rocks, gravel,

sand, sediment, and silt from the riverbed. Poe

punched holes in the riverbed by excavating through

layers of riverbed down to the bedrock. Poe then

processed the materials by running them through the

sluice on his dredge, and then discarded the waste

material into the water. This added a plume of turbid

wastewater to the South Fork. These materials were

not already suspended in the water; they were

previously deposited in the riverbed. Poe’s dredging

was therefore not simple water transfer.

As the district court correctly observed,

Poe’s reliance on [L.A. County and

Miccosukee Tribe] misses the point. Suction

dredge mining does not simply transfer

water (what the above cases address); to the

contrary, it excavates rock, gravel, sand,

and sediment from the riverbed and then

adds those materials back to the river—this

time, in suspended form.

See also EPA, 2018 Response to Comments Idaho

Small Suction Dredge General Permit (GP) (“If,

during suction dredging, only water was picked up

and placed back within the same waterbody . . . , no

permit would be necessary. However, in suction

dredging, bed material is also picked up with water.

Picking up the bed material is in fact the very purpose

of suction dredging—the bed material is processed to

produce gold. This process is an intervening use that

causes the addition of pollutants [rock and sand, see

12a

CWA § 502(6)] to be discharged to waters of the

United States. As a result . . . an NPDES permit is

required for the discharge from this activity.”

(alteration in original) (citation omitted)). Thus,

Miccosukee Tribe and L.A. County do not disturb our

holding in Rybachek, which remains good law.

In addition, or in the alternative, Poe asks us not

to apply Chevron deference and to overrule Rybachek.

Specifically, Poe argues that (1) the ordinary meaning

of “addition” under the CWA is clear, making Chevron

deference inappropriate, (2) Chevron should not be

applied where a statute may subject individuals to

criminal penalties, and (3) Chevron should not be

applied where the EPA has taken inconsistent

positions on the meaning of “addition” under the

CWA. Adopting any of these theories would require us

to depart from our ruling in Rybachek. A three-judge

panel may depart from controlling circuit precedent

only if “our prior circuit authority is clearly

irreconcilable with the reasoning or theory of

intervening higher authority.” Miller v. Gammie, 335

F.3d 889, 893 (9th Cir. 2003) (en banc). “[T]he ‘clearly

irreconcilable’ requirement ‘is a high standard.’” Fed.

Trade Comm’n v. Consumer Def., LLC, 926 F.3d 1208,

1213 (9th Cir. 2019) (quoting Rodriguez v. AT&T

Mobility Servs. LLC, 728 F.3d 975, 979 (9th Cir.

2013)). “[I]f we can apply our precedent consistently

with that of the higher authority, we must do so.” Id.

As explained above, Rybachek’s holding regarding

placer mining is not irreconcilable, let alone “clearly

irreconcilable,” with L.A. County or Miccosukee Tribe’s

holdings regarding the transfer of water within a

single waterbody. We therefore follow Rybachek on

the issues raised by Poe and hold that Poe’s instream

13a

suction dredge mining constitutes the “addition” of a

pollutant under the CWA.

II. The Processed Material Discharged from

Instream Suction Dredge Mining is a

Pollutant that Requires a Section 402 Permit.

Poe also argues that, even if his suction dredge

mining adds pollutants to the South Fork, the waste

discharged from his operation constitutes “dredged” or

“fill material” over which the Corps has exclusive

permitting authority.1 Poe makes this argument

pursuant to (1) the ordinary meaning of “dredged

material” under the CWA and (2) the ordinary

meaning of the Corps’ own regulatory definition of

“dredged material.” Neither argument is persuasive.

Under the CWA, pollution discharges require a

Section 402 permit from the EPA, unless the

discharge is “dredged or fill material” requiring a

Section 404 permit from the Corps. See 33 U.S.C.

§§ 1342, 1344; 40 C.F.R. § 122.3; Coeur Alaska, Inc. v.

Se. Alaska Conservation Council, 557 U.S. 261, 274

(2009). The terms “dredged material” and “discharge

of dredged material” are not defined under the CWA.

See 33 U.S.C. § 1362; Olympic Forest Coal., 884 F.3d

at 905 (“It is well settled that the starting point for

interpreting a statute is the language of the statute

itself.”). Nor does the statute define whether material

1 The Oregon Supreme Court recently addressed this issue. See

E. Or. Mining Ass’n v. Dep’t of Env’t Quality, 445 P.3d 251, 274

(2019) (EOMA) (deferring to the “EPA’s and the Corps’

reasonable conclusion that the EPA (or its state delegate) has the

authority to issue a permit under section 402 for all the processed

waste discharged as a result of suction dredge mining”). We find

EOMA well-reasoned and persuasive and substantially follow its

analysis, as did the district court.

14a

that is dredged from navigable water remains

“dredged material” after it has been processed. That

is, nothing in the CWA says that once a material has

been dredged, it remains a dredged material forever.

If, as the district court explained (citing EOMA, 445

P.3d 251, 257 (2019)), processing dredged material

can change its character, the text of the statute does

not identify the point at which the processed material

becomes a pollutant other than dredged material that

is subject to the EPA’s rather than the Corps’

permitting authority. The CWA therefore does not, in

plain terms, address the question presented here.

We next look to the regulations promulgated to

implement the Act. See Coeur Alaska, 557 U.S. at

277–78 (explaining that, if the text of the CWA is

ambiguous, courts look to the agencies’ implementing

regulations and, if those regulations are ambiguous,

to the agencies’ interpretation and application of their

regulations to determine what the CWA means)). The

CWA regulations define “dredged material” as

“material that is excavated and dredged from waters

of the United States,” but offer no further explanation

of the term. See 33 C.F.R. § 323.2(c). Like the CWA,

the regulations do not specifically address the

question of which agency has the authority to permit

the discharge of dredged material that has been

processed, such as the leftover waste material that is

discharged during suction dredge mining.

Absent clear direction from either the CWA or the

regulations promulgated thereunder, we look to the

agencies’ interpretation and application of those

regulations. See Coeur Alaska, 557 U.S. at 277–78;

Kisor v. Wilkie, 139 S. Ct. 2400, 2415–18 (2019). The

EPA and Corps have long agreed that when materials

15a

are dredged from a waterbody and are subsequently

processed, they are no longer dredged materials and

have become industrial waste, rock, sand, or other

CWA pollutants regulated under Section 402.2 For

example, in their 1986 memorandum of agreement,

the EPA and the Corps agreed that “placer mining

wastes” were the type of “pollutant” discharged in

“liquid, semi-liquid, or suspended form” subject to

Section 402, not Section 404. Memorandum of

Agreement Concerning Regulation of Discharge of

Solid Waste Under the Clean Water Act, 51 Fed. Reg.

8871, 8872 (March 14, 1986). A 1990 Regulatory

Guidance Letter from the Corps states that once

“dredged material” is “subsequently processed to

remove desired elements, its nature has been

changed” and “it is no longer dredged material”

regulated under Section 404. U.S. Army Corps of

Engineers, Regulation of Waste Disposal from InStream Place Mining, Regulatory Guidance Letter 8810 (July 28, 1990), https://usace.contentdm.oclc.org/u

tils/getfile/collection/p16021coll9/id/1386; see also

U.S. Army Corps of Engineers, Regulatory Guidance

Letters, https://www.usace.army.mil/Missions/CivilWorks/Regulatory-Program-and-Permits/GuidanceLetters (noting that, “unless superseded by specific

provisions of subsequently issued regulations or

guidance, the content provided in [Regulatory

Guidance Letters] generally remains valid after the

expiration date”). The Corps explained: “The raw

materials associated with placer mining operations

are not being excavated simply to change their

locations as in a normal dredging operation, but

The district court included a more detailed account of the

regulatory history, which Poe does not contest on appeal.

2

16a

rather to obtain materials for processing, and the

residue of this processing should be considered waste.”

As the district court noted, “whatever patchwork of

permitting authority has existed over time, from at

least 2013 (via the general permitting process,

initiated in 2010 and after notice and comment), it is

the EPA that has required a Section 402 permit for

suction dredge mining.” “This fact, coupled with the

overall approach to and assignment and acceptance of

responsibilities under the EPA’s and the Corps’

interpretation of the applicable regulations to suction

dredge mining . . . , confirms that the agencies have

taken an official position and made a fair and

considered judgment, based on its substantive

expertise, that the operation of a suction dredge

results in the discharge of processed wastes, thus

requiring Section 402 permits.” We therefore defer to

the agencies’ reasonable interpretation of the CWA

and implementing regulations that the processed

material discharged from Poe’s suction dredge mining

is a pollutant, not a dredged or fill material, and

requires an NPDES permit under Section 402 of the

CWA. See Kisor, 139 S. Ct. 2400.

Poe’s arguments to the contrary are unavailing.

Principally, citing the dissent in EOMA, Poe argues

that (1) the text of Section 404 itself is enough to settle

the case: suction dredge mining does “dredge”

material, and, in a literal sense, that material is then

“discharged” into the water, and (2) the Corps’

regulation defining “dredged material” is not

genuinely ambiguous as to the question over whether

instream suction dredge mining is regulated under

Section 404 once ordinary interpretive methods have

been applied. However, as explained above, even if the

17a

material starts as dredged material, that fact does not

settle the issue of whether material that was dredged

remains “dredged material” after it has been

processed. Poe processed the materials dredged from

the riverbed when he ran them through the sluice on

his dredge, extracted heavy metals and other

materials, and discharged the remaining waste and

sediments into the South Fork.

In any event, the meaning of the CWA and

implementing regulations remains sufficiently

ambiguous that deference to the agencies’ official joint

conclusion is appropriate. See Coeur Alaska, 557 U.S.

at 277–78. As the Oregon Supreme Court noted,

“[b]oth the statutes and the regulations are genuinely

ambiguous on [this] question.” EOMA, 445 P.3d at

270. The concern here “is not with the navigability of

the water body, a concern that falls within the Corps’

expertise; rather, the concern is with the health of the

water body, a concern that lies at the heart of the

EPA’s expertise. The Corps and the EPA reasonably

could conclude that the EPA was better suited than

the Corps to make th[e]se types of water quality

decisions.” Id. at 272.

CONCLUSION

For the foregoing reasons, the district court’s grant

of summary judgment to ICL is AFFIRMED.

18a

[cited in Idaho Conservation League v. Shannon Poe

No. 22-35978 archived on November 16, 2023]

INFORMATIONAL COPY ONLY

Regulatory Guidance Letter 88-10

SUBJECT: Regulation of Waste Disposal from

In-Stream Placer Mining

DATE: July 28, 1990

EXPIRES: December 31, 1990

Paragraph B.5. in the Army’s 23 Jan 86

Memorandum of Agreement (MDA) with EPA,

concerning the regulation of solid waste discharges

under the Clean Water Act, states that discharges

that result from in-stream mining activities are

subject to regulation under Section 402 and not under

Section 404.

Dredged material is that material which is

excavated from the waters of the United States.

However, if this material is subsequently processed to

remove desired elements, its nature has been

changed; it is no longer dredged material. The raw

materials associated with placer mining operations

are not being excavated simply to change their

location as in a normal dredging operation, but rather

to obtain materials for processing, and the residue of

this processing should be considered waste. Therefore,

placer mining waste is no longer dredged material

once it has been processed, and its discharge cannot

be considered to be a “discharge of dredged material”

subject to regulation under Section 404.

This guidance expires 31 Dec 90 unless sooner

revised or rescinded.

19a

[cited in Idaho Conservation League v. Shannon Poe

No. 22-35978 archived on November 16, 2023]

US Army Corps of Engineers Headquarters Website

Regulatory Guidance Letters

Regulatory Guidance Letters (RGLs) were

developed by the Corps as a system to organize and

track written guidance issued to its field agencies.

RGL’s are normally issued as a result of evolving

policy; judicial decisions and changes to the Corps

regulations or another agency’s regulations which

affect the permit program. RGL’s are used only to

interpret or clarify Regulatory Program policy, but do

not provide mandatory guidance to the Corps district

offices. RGL’s are sequentially numbered and expire

on a specific date. However, unless superseded by

specific provisions of subsequently issued regulations

or guidance, the content provided in RGL’s generally

remains valid after the expiration date. The Corps

incorporates most of the guidance provided by RGL’s

whenever it revises its permit regulations.

Archive

Collapse All Expand All

⊞ 2019

⊞ 2018

⊞ 2016

⊞ 2008

⊞ 2007

⊞ 2006

⊞ 2005

⊞ 2002

20a

[cited in Idaho Conservation League v. Shannon Poe

No. 22-35978 archived on November 16, 2023]

⊞ 2001

⊞ 1996

⊞ 1995

⊞ 1994

⊞ 1993

⊞ 1992

⊞ 1991

⊞ 1990

⊞ 1989

⊞ 1988

⊞ 1987

⊞ 1986

⊞ 1985

⊞ 1984

⊞ 1983

⊞ 1982

⊞ 1981

21a

Filed September 28, 2022

UNITED STATES DISTRICT COURT

DISTRICT OF IDAHO

IDAHO

CONSERVATION

LEAGUE,

Plaintiff,

vs.

SHANNON POE,

Defendant.

Case No.: 1:18-cv-353-REP

MEMORANDUM

DECISION AND

ORDER RE:

PLAINTIFF IDAHO

CONSERVATION

LEAGUE’S MOTION

FOR REMEDIES

(Dkt. 59)

Pending before the Court is Plaintiff Idaho

Conservation League’s Motion for Remedies (Dkt. 59).

Having carefully reviewed the record and the parties’

briefs, the Court finds that the facts and legal

arguments are adequately presented. Accordingly, in

the interest of avoiding further delay, and because the

Court finds that the decisional process would not be

significantly aided by oral argument, the Court will

decide the Motion without oral argument. Dist. Idaho

Loc. Civ. R. 7.1(d)(1)(B).1 For the reasons that follow,

the Motion is granted insofar as the Court will issue

injunctive relief and assess civil penalties against

Defendant Shannon Poe in the amount of $150,000.

1 Through correspondence with the Court, the parties confirmed

that their briefing did not request oral argument and neither

party was otherwise requesting one.

22a

I. RELEVANT BACKGROUND

The circumstances giving rise to this citizen-suit

enforcement action are largely undisputed:2 Mr. Poe

suction dredge mined 42 days on the SFCR during the

2014, 2015, and 2018 dredge seasons (running from

July 15 to August 15 each year) without ever

obtaining an NPDES permit under Section 402 of the

CWA.

Through this action, ICL argued that Mr. Poe

violated the CWA each of the 42 times he operated a

suction dredge on the SFCR without an NPDES

permit. Mr. Poe countered that (i) his suction dredge

mining did not actually add pollutants to the SFCR

and therefore did not require an NPDES permit (or

any other CWA permit) in the first place; and even if

his suction dredge mining did add pollutants,

(ii) those pollutants are “dredged” or “fill” material

regulated exclusively under Section 404 (not Section

402) of the CWA and therefore did not require an

NPDES permit, and (iii) any discharges of dredged or

In denying Defendant Shannon Poe’s Motion to Dismiss on

September 30, 2019, the Court generally discussed the

characteristics of the South Fork Clearwater River (“SFCR”);

recreational suction dredge mining and National Pollutant

Discharge Elimination System (“NPDES”) permit requirements

under the Clean Water Act (“CWA”); Idaho’s permitting

requirements for suction dredge mining; Mr. Poe’s suction dredge

mining activities on the SFCR without an NPDES permit in

2014, 2015, and 2018; and Plaintiff Idaho Conservation League’s

(“ICL”) correspondence to Mr. Poe in 2016, 2017, and 2018,

advising him of its intention to initiate a CWA citizen suit

against him if he continued to suction dredge mine in Idaho

without an NPDES permit. Idaho Conservation League v. Poe,

421 F. Supp. 3d 983, 986–90 (D. Idaho 2019). This backdrop,

while important for perspective, will not be repeated in depth

here.

2

23a

fill material from his suction dredge mining are only

“incidental fallback,” making them exempt under

Section 404 of the CWA anyway. The parties agreed

to bifurcate the case into two separate phases: a

liability phase decided on the parties’ cross-motions

for summary judgment, followed by a remedial phase

as necessary.

On June 4, 2021, the Court granted summary

judgment in ICL’s favor. Idaho Conservation League

v. Poe, 2021 WL 2316158 (D. Idaho 2021). At that

time, U.S. Magistrate Judge Ronald E. Bush

concluded that (i) Mr. Poe’s suction dredge mining

added pollutants to the SFCR, thus requiring an

NPDES permit under Section 402 of the CWA; and

(ii) the processed material discharged from Mr. Poe’s

at-issue suction dredge mining is a pollutant, not

dredged or fill material, and required an NPDES

permit under Section 402 of the CWA. Id. at *2–12.3

With the liability phase now complete, the action

shifts to the remedial phase, framed by ICL’s pending

Motion for Remedies. ICL requests that, owing to

Mr. Poe’s CWA violations, the Court order (i) an

injunction barring Mr. Poe from suction dredge

mining in Idaho unless he obtains and complies with

an NPDES permit under the CWA, and (ii) civil

penalties against Mr. Poe of at least $564,924. Mem.

ISO Mot. for Remedies at 3, 7–22 (Dkt. 59-1). Mr. Poe

responds that an injunction is unnecessary and moot

because there are no longer any illegal discharges to

enjoin and that, regardless, a $60,924 civil penalty is

The undersigned inherited this case from Judge Bush on

June 11, 2021. Before then, Judge Bush presided over the action

and issued rulings on multiple aspects of the case, including the

liability phase.

3

24a

more in line with the environmental impacts of such

dredge mining and will sufficiently deter him from

ever suction dredge mining on the SFCR without an

NPDES permit again. Resp. to Mot. for Remedies at 5,

9–24 (Dkt. 63). These arguments are taken up below.

II. DISCUSSION

A. Legal Standards

The CWA authorizes courts “to order that relief it

considers necessary to secure prompt compliance with

the Act,” including an “order of immediate cessation.”

Weinberger v. Romero-Barcelo, 456 U.S. 305, 320

(1982); see also 33 U.S.C. §§ 1319(b),(d) & 1365(a).

Discretion is vested in the court to either grant or deny

a request for injunctive relief depending upon its view

of the range of public interests at issue. Weinberger,

456 U.S. at 320. If a court chooses to grant an

injunction, however, it must meet the requirements of

Federal Rule of Civil Procedure 65(d), which requires

that every injunction (i) state the reasons why it was

issued, (ii) state its terms specifically, and

(iii) describe in reasonable detail—without reference

to the complaint or other document—the act or acts

restrained or required. Fed. R. Civ. P. 65(d); see also

Reno Air Racing Ass’n. Inc. v. McCord, 452 F.3d 1126,

1132 (9th Cir. 2006).

The CWA additionally permits courts “to apply any

appropriate civil penalties.” 33 U.S.C. § 1365(a). Civil

penalties are mandated for CWA violations. 33 U.S.C.

§ 1319(d) (any person who violates the CWA “shall be

subject to a civil penalty not to exceed $25,000 per day

for each violation.”) (emphasis added); see also

Natural Res. Def. Council. v. Sw. Marine, Inc., 236

F.3d 985, 1001 (9th Cir. 2000) (holding that penalties

25a

are mandatory if violation of CWA is found). The

maximum daily penalty has increased periodically to

account for inflation. Relevant here, for violations that

occurred between December 6, 2013 and November 2,

2015, the maximum penalty is $37,500 per violation;

for violations that occurred after November 2, 2015

(where penalties are assessed after January 12, 2022),

the maximum penalty is $59,973. 40 C.F.R. § 19.4 at

Tables 1 & 2. Unlike damages in other civil cases,

these penalties do not inure to the citizen plaintiffs,

but are payable to the United States Treasury. See

Friends of the Earth v. Laidlaw Envtl. Servs., Inc., 528

U.S. 167, 173 (2000).

As between injunctive relief and civil penalties,

“the district court has discretion to determine which

form of relief is best suited, in the particular case, to

abate current violations and deter future ones.” Id. at

192.

B. Injunctive Relief Is Appropriate to Ensure

Compliance With the CWA

ICL requests a permanent injunction barring

Mr. Poe from suction dredge mining in Idaho unless

he obtains and complies with an NPDES permit under

Section 402 of the CWA. Mem. ISO Mot. for Remedies

at 7 (Dkt. 59-1).

The standard for a permanent injunction is

essentially the same as for a preliminary injunction

with the exception that the plaintiff need not show a

likelihood of success on the merits because actual

success has already been achieved. Amoco Prod. Co. v.

Gambell, 480 U.S. 531, 546 n.12 (1987). Therefore, to

demonstrate that a permanent injunction should

issue, the plaintiff must establish the following:

26a

“(i) that it has suffered an irreparable injury; (ii) that

remedies available at law, such as monetary damages,

are inadequate to compensate for that injury;

(iii) that, considering the balance of hardships

between the plaintiff and defendant, a remedy in

equity is warranted; and (iv) that the public interest

would not be disserved by a permanent injunction.”

Monsanto Co. v. Geertson Seed Farms, 561 U.S. 139,

156-57 (2010).

This traditional balancing of harms applies in the

environmental context. The Lands Council v. McNair,

537 F.3d 981, 1005 (9th Cir. 2008) (“Our law does not

. . . allow us to abandon a balance of harms analysis

just because a potential environmental injury is at

issue.”). However, injunctive relief “is not

mechanically obligated . . . for every violation of law.”

Weinberger, 456 U.S. at 313. Courts have broad

latitude when determining the scope of an injunction

and must balance the equities between the parties

and give due regard to the public interest. Geertson

Seed Farms v. Johanns, 570 F.3d 1130, 1136 (9th Cir.

2009). If proper, any injunctive relief should be framed

“no broader than required by the precise facts.”

Schlesinger v. Reservists Comm. to Stop the War, 418

U.S. 208, 222 (1974); see also Stormans, Inc. v.

Selecky, 586 F.3d 1109, 1140 (9th Cir. 2009)

(“‘Injunctive relief . . . must be tailored to remedy the

specific harm alleged.’ ‘An overbroad injunction is an

abuse of discretion.’”) (quoting Lamb-Weston v.

McCain Foods, Ltd., 941 F.2d 970, 974 (9th Cir.

1991)).

ICL argues that the elements comprising a

permanent injunction are met and thereby justify the

requested injunctive relief. Mem. ISO Mot. for

27a

Remedies at 3, 8–12 (Dkt. 59-1). Mr. Poe disagrees—

not because any of the elemental prerequisites for a

permanent injunction do not exist per se, but because

a permanent injunction is unnecessary and moot since

he is no longer suction dredge mining in Idaho and

civil penalties are available to deter future CWA

violations. Resp. to Mot. for Remedies at 13–16 (Dkt.

63). Though sensible on their face, Mr. Poe’s

arguments are ultimately unpersuasive here. An

injunction is warranted.

1. An Injunction Prevents Irreparable Injury

“Environmental injury, by its nature . . . is often

permanent or at least of long duration, i.e.,

irreparable. If such injury is sufficiently likely,

therefore, the balance of harms will usually favor the

issuance of an injunction to protect the environment.”

Amoco Prod., 480 U.S. at 545 (emphasis added).

During the earlier liability phase, the Court concluded

as a matter of law that Mr. Poe’s suction dredge

mining added pollutants to the SFCR, stating in

relevant part:

A Section 402/NPDES permit is required if

a person (i) discharged, i.e., added (ii) a

pollutant (iii) to navigable waters (iv) from

(v) a point source. There is no dispute that

rock and sand passing through a suction

dredge is a pollutant; that the [SFCR] is a

navigable water; and that a suction dredge

is a point source. In turn, this reveals a

lynchpin issue of the case: whether

Mr. Poe’s suction dredge mining involves

the “discharge” or “addition” of a pollutant

to the [SFCR]. ICL says it does. Mr. Poe says

it does not.

28a

....

Suction dredge mining does not simply

transfer water . . . ; to the contrary, it

excavates rock, gravel, sand, and sediment

from the riverbed and then adds those

materials back to the river—this time, in

suspended form. If Mr. Poe’s suction dredge

just sucked up river water from—and back

into—the [SFCR] (along with any pollutants

already in the water), he would be

transferring water and not adding any

pollutants . . . . but that is neither suction

dredge mining nor what Mr. Poe did on the

[SFCR] during the 2014, 2015, and 2018

dredging seasons.

In sum, the very nature of Mr. Poe’s suction

dredge mining added pollutants to the

[SFCR] [and] require[s] an NPDES permit

under Section 402 of the CWA.

Poe, 2021 WL 2316158, at *3, 6–7 (emphasis in

original, internal quotation marks and citations

omitted). But ICL cannot obtain injunctive relief

merely because the Court has made a finding of

liability under the CWA; it still must connect the legal

dots between Mr. Poe’s suction dredge mining and

corresponding irreparable injury.

ICL does this by juxtaposing the SFCR’s pristine

ecosystem with suction dredge mining activity

generally. It points out how, on the one hand, the

SFCR is a “State Protected River”; is eligible as a

federal wild and scenic river; and is a vital fishery,

inhabited by many native fish species, including those

listed as “threatened” under the Endangered Species

29a

Act (“ESA”) (steelhead trout, fall Chinook salmon, and

bull trout). Mem. ISO Mot. for Remedies at 5–6, 9

(Dkt. 59-1) (citing Ex. 7 to Poe MTD at 45 (Dkt. 17-3);4

Ex. 8 to Poe MTD at 3–83 (Dkt. 17-4); Ex. V to 2nd

Hurlbutt Decl. at 1 (Dkt. 38-13)). Yet, on the other

hand, it emphasizes how the SFCR is still listed as an

“impaired” water body because it fails to meet CWA

standards for sediment and temperature pollution;

how the rock, sand, sediment, and silt discharged from

suction dredge mining degrades water quality and

impedes river habitat restoration; and how the

sediment and fine silt discharged by a suction dredge

reduces oxygen levels, aquatic cover, forage, and

invertebrate production, which impact the survival of

fish eggs and alevins, the growth in older and juvenile

fish, and ultimately fish migrations and spawning

seasons. Mem. ISO Mot. for Remedies at 6, 9 (Dkt. 591) (citing ICL SOF at ¶¶ 3, 10 (Dkt. 38-1); Ex. U to 2nd

Hurlbutt Decl. at 1–2 (Dkt. 38-12)).

More specific to Mr. Poe’s suction dredge mining on

the SFCR, ICL highlights the opinions of its expert,

Dan Kenney.5 Mr. Kenney discusses basic stream

Though listed as a “State Protected River,” the SFCR has

exemptions for recreational suction dredge mining. Ex. 7 to Poe

MTD at 45 (Dkt. 17-3). Even so, this acknowledgment exists

within the “Fact Sheet” to an EPA proposal to reissue an NPDES

General Permit to small suction dredgers operating in Idaho. Id.

at 1.

4

5 Mr. Kenney is a former Forest Service fisheries biologist with

extensive experience monitoring and assessing suction dredge

mining and its impacts in the Clearwater River watershed,

including the SFCR. Kenney Rpt., attached as Ex. G to 4th

Hurlbutt Decl. at 1–3 (Dkt. 59-9). In addition to scientific papers

and state and federal agency studies and reports on suction

30a

morphology and biology, suction dredge mining in

relation to the SFCR stream morphology in particular,

and Mr. Poe’s site-specific suction dredge mining in

2014, 2015, and 2018, before summarizing the

physical and biological effects of those same dredging

activities on the SFCR. Kenney Rpt. attached as Ex.

G to 4th Hurlbutt Decl. at 3–24 (Dkt. 59-9). On that

last point, Mr. Kenney notes the following:

• There is ample evidence that Mr. Poe’s 2014,

2015, and 2018 activities on the SFCR affected

algae, invertebrates, and fish. As described

above, a total of up to about 3,400 square feet of

surface substrate, predominately algae-covered

rocks (gravel and larger), was removed from the

SFCR during the 3 dredging seasons and some

were either overturned or dropped into the

dredge holes, while a separate but at least

equal-sized area of the SFCR surface substrate

was covered with tailings piles or fine sediment

by Mr. Poe’s activities.

• Given that the SFCR is already considered

“impaired” due to too much fine sediment, some

of the dredged and otherwise modified areas

likely had too-thick of a layer of fine sediment

pre-dredging to allow algae to grow, and so the

total amount of attached algae harmed by

Mr. Poe may be somewhat less than 3,400

square feet. Attached algae is a food source for

many aquatic invertebrates, so, at least locally

dredge mining and its impacts, Mr. Kenney’s opinions are based

on photos, videos, and reports of Mr. Poe’s suction dredge mining

on the SFCR in 2014, 2015, and 2018. Mr. Poe challenges aspects

of Mr. Kenney’s opinions but not his qualifications.

31a

and temporarily, the primary production of the

SFCR was reduced.

• The same surface substrate modified by 2014,

2015, and 2018 dredging by Mr. Poe was

habitat for aquatic invertebrates, as was at

least a portion of the hyporheic zone, and so the

manipulation of the substrate in the dredging

process caused an unknown number of

individuals to be loosed into the water column,

and another unknown number of individuals to

be covered by or have their interstitial habitat

infiltrated by sand and smaller fines. . . . [I]t

seems likely that hundreds of thousands of

aquatic insects were displaced, harmed, or

killed by Mr. Poe’s dredging activities.

• The fine sediment brought to the substrate

surface or suspended in the water column by

Mr. Poe’s dredges would have been mostly

scoured away from the substrate surface in

direct vicinity of the dredging sites within a few

months—these fines did not disappear from the

river,

however,

but

did

contribute

incrementally to degraded aquatic habitat

locally for miles downstream on the SFCR and

eventually to the mainstem Clearwater River.

• I cannot say with certainty that Mr. Poe’s

activities would have directly injure or killed

any individuals of special status species,

however, stream margins are often important

habitat for juvenile steelhead and other

salmonids and my October 7, 2015 notes for the

upper unauthorized dredging site state that the

“(b)ank undercut by dredger for length of hole.”

The downstream Poe dredge hole at the 2018 #1

32a

site was at the stream edge, as were Sites #2

and #3 that year. The Poe primary dredging

area in 2014 was in mid-channel, however, and

I don’t know where Mr. Poe dredged at the

downstream (Moose Creek) site.

• I think it likely that direct and indirect adverse

effects to aquatic insect growth, survival, and

abundance (even if incremental, localized, or

temporary) were caused by Mr. Poe’s suction

dredging in each year he dredged on the SFCR.

In regard to 2018 SFCR suction dredging, a

report commissioned by IDWR [(Idaho

Department of Water Resources)] concluded

that “(a)ll disturbed areas will experience a

reduction in invertebrate production from fine

sediment, leading to a reduction in foraging

opportunities for anadromous and resident fish

species.”

• While some small fish are apparently not

repelled by suction dredging operations, it is

possible that some SFCR fish were physically

or behaviorally excluded from rearing, holding,

and migratory habitat by the Poe operations.

. . . . [W]hile noise, activity, and turbidity

definitely can modify adult fish behavior, the

degree to which the Poe operations did so is

unknown, but likely minor compared with

effects on habitat.

• When Mr. Poe and his assistants suctioned

substrate at depth, they were also bringing

gravel and finer rock particles to the surface to

cover the existing substrate surface in the

SFCR channel. These particles, as noted above

regarding aquatic invertebrates, infiltrated

33a

interstitial spaces in some portions of the

dredging reach. Juvenile and subadult

salmonids, including bull trout, often seek out

interstitial habitat (especially that among

cobbles and boulders) during diel feeding

periods (or winter in general). The

rearrangement and addition of fine sediment to

the stream channel during Mr. Poe’s suction

dredging activities is likely to have reduced the

local quantity or quality of such habitat, even

considering that some of these fines would have

been scoured from the dredging sites by

subsequent high flow events and deposited

downstream. The effects of the addition of

previously-unmobilized fine sediment from the

Poe dredging likely incrementally reduced

interstitial hiding cover for fish in the SFCR

channel for miles downstream.

• Based on my experience in delineating NPCNF

[(Nez Perce-Clearwater National Forest)]approved dredging reaches, the areas that

Mr. Poe dredged and covered with tailings and

fines in each relevant year do not appear to be

spawning habitat for any special status fish

species, and so there was a low likelihood that

his activities directly affected salmonid redds,

eggs, or pre-emergent fry. On the other hand,

there are areas with suitable spawning habitat

for steelhead (and to a lesser extent, spring and

fall Chinook salmon) within a few hundred feet

downstream of at least the Sasquatch 2 sites for

each year, and I think that is reasonable to

assume that this habitat was incrementally

degraded by the excavation of previously

immobile fine sediment.

34a

• Excavation and dispersion of previouslysequestered fines by dredging operations can

contribute to the pollution in the SFCR that the

EPA is attempting to control through the

TMDL [(Total Maximum Daily Load)] and the

NPDES permitting process which Mr. Poe has

defied and encouraged others to defy.

• The effects of suction dredging on water

quality, stream channel conditions, and stream

biota are real and some of these effects are

similar to the effects of natural phenomena

such as flooding and erosion.

• Even if the adverse effects of Mr. Poe’s dredging

were entirely erased each year by high

streamflows (and many are not), these effect

would still be manifest for days, weeks, or

months. These periods constitute a substantial

part of a lifetime to many or most aquatic

organisms. Similarly, and particularly in 2015

and 2018, even if the adverse effects of each of

Mr. Poe’s dredging operations are considered as

insignificant in isolation (and many are not),

Mr. Poe set up his operations nearby other

dredgers in a relatively short river reach, such

that the cumulative effects of these activities

were most likely to be exacerbated.

• The goal of a suction dredge miner is to find

gold through the dismantling of a portion of the

physical structure of a stream. Because most

placer gold will find its way to or near the

bedrock surface, typically at least several feet

below the substrate surface, this dismantling is

essentially an overturning and redistribution of

the existing structure of the stream at the

35a

dredging site. Because flowing water, both

concurrently with and subsequent to dredging,

transmits these physical effects downstream,

the effects of the dredging are not confined to

the immediate dredge mining area.

• Mr. Poe’s dredging operations on the SFCR in

2014, 2015, and 2018 had demonstrable

immediate and enduring effects on SFCR water

quality and stream channel morphology. Based

on my training, experience, and my review of

the scientific literature, I believe that these

physical effects were harmful to individual

aquatic organisms in the SFCR. The degree and

duration of Mr. Poe’s dredging operations’ harm

to populations of these organisms or the SFCR

biological community cannot be known with

certainty but I believe that incremental and

cumulate adverse effects should be considered

plausible and likely.

Id. at 24–29, 30–31 (internal citations omitted).

Mr. Poe takes issue with certain of Mr. Kenney’s

opinions, offering up an expert of his own: Andréa

Rabe.6 Ms. Rabe contends that, while suction dredge

Ms. Rabe has a bachelors in genetics and anthropology, a

masters in botany, and is a certified professional wetlands

scientist. Rabe Rpt., attached as Ex. 1 to Resp. to Mot. for

Remedies at 15 (Dkt. 63-2). Ms. Rabe has over 23 years’

experience conducting water quality monitoring, stream surveys,

habitat assessments, and wetlands delineations; preparing

water quality monitoring plans; and preparing and

implementing restoration plans. Id. Ms. Rabe reviewed

Mr. Kenney’s report and the documents he relied on, as well as

additional photos and videos of Mr. Poe’s dredging operations,

state and federal permit requirements, and the Forest Service

6

36a

mining may impact water quality, stream channel

conditions, and stream biota due to the movement and

release of fine sediments, small-scale suction dredge

mining (like Mr. Poe’s) does not (or at least can be

conducted in a manner to reduce and eliminate such

impacts). Rabe Rpt., attached as Ex. 1 to Resp. to Mot.

for Remedies at 3, 11–12 (Dkt. 63-2). She more

directly opines that Mr. Poe’s suction dredge mining

on the dates in question mostly7 followed permitting

authorities’

operating

procedures

and

how

Mr. Kenney’s claims do not unequivocally establish

injury to the SFCR. Id. at 3–11, 15. Importantly, she

does not ultimately disagree that there are likely

impacts from Mr. Poe’s dredging operations, just that

any such impacts are not occurring to the extent

expressed by Mr. Kenney given Mr. Poe’s adherence

to these operating procedures—even without having

ever obtained an NPDES permit. Id. at 12, 15 (“This

reduction and elimination of impacts will occur

whether the operating procedures are implemented as

permit conditions or as best management practices by

a suction dredge operator. . . . Mr. Poe employed most

of these best management practices in his operations

during the dredging seasons in 2014, 2015, and 2018,

thereby reducing the impacts from his small-scale

and Bureau of Land Management’s Decision Record for SmallScale Dredging in Orogrande and French Creeks and South Fork

Clearwater River.

7 Suction dredge operations should not discharge within 800 feet

of another suction dredge operation discharge that is occurring

at the same time. Rabe Rpt., attached as Ex. 1 to Resp. to Mot.

for Remedies at 5 (Dkt. 63-2). Ms. Rabe acknowledges that

Mr. Poe was not always at least 800 feet from the next dredge

operation, but he did add spacing to maintain lower levels of

turbidity. Id.

37a

suction dredging operation on water quality, stream

channel conditions, and stream biota.”) (emphasis

added).8

From this, it is clear that suction dredge mining

(even small-scale, recreational suction dredge mining)

disturbs a riverbed’s substrate and discharges

sediment into the water column, causing aesthetic

and environmental harm. This is especially the case

in a sensitive environment like the SFCR—a critical

habitat for ESA-listed species and an alreadyimpaired river due to the failure to meet state water

quality standards for sediment and temperature.

Fortunately, steps can be taken to mitigate these

harms, including a permitting process that outlines a

specific suction dredge mining season and strict

operational protocols.

Here, however, Mr. Poe never secured an NPDES

permit before suction dredge mining 42 days on the

SFCR. These repeated failures constitute CWA

violations because his dredging activities added

pollutants to the waterway and caused environmental

harm. Environmental harm in this sense amounts to

irreparable injury. Amoco, 480 U.S. at 545

(environmental injury, “by its nature,” is irreparable).

That Mr. Poe may have obtained other permits with

overlapping protections does not upend this

conclusion. Otherwise, there would be no purpose to

the CWA’s application in this setting. The CWA

regime exists alongside state permitting requirements

8 To be clear, Mr. Poe does not offer Ms. Rabe’s opinions to contest

ICL’s argument that his suction dredge mining on the SFCR

caused irreparable injury. Rather, these opinions support his

argument that any harm was de minimis and that any civil

penalties should reflect that reality. See infra.

38a

and applies across all users as a whole, not just

Mr. Poe. A contrary position is not supported in the

law and the Court will not stake that ground now.

This is particularly the case given CWA’s

straightforward objective: “to restore and maintain

the integrity of the chemical, physical, and biological

integrity of the Nation’s waters.” 33 U.S.C. § 1251(a);

see also Decker v. Nw. Envtl. Def. Ctr., 568 U.S. 597,

602 (2013) (“A central provision of the [CWA] is its

requirement that individuals, corporations, and

governments secure [NPDES] permits before

discharging pollution from any point source into the

navigable waters of the United States.”).

With irreparable injury established, case law hints

that the remaining factors favor injunctive relief to

protect the environment. Amoco, 480 U.S. at 545 (“If

such [irreparable] injury is sufficiently likely,

therefore, the balance of harms will usually favor the

issuance of an injunction to protect the environment.”)

(emphasis added); but see Earth Island Inst. v.

Carlton, 626 F.3d 462, 474 (9th Cir. 2010) (declining

“to adopt a rule that any potential environmental

injury automatically merits an injunction.”)

(emphasis in original, internal quotation marks and

citation omitted). The Court briefly addresses these

factors below for completeness’ sake.

2. Legal Remedies Are Inadequate

The Supreme Court has recognized that, in most

instances, environmental harms are not readily

compensable by money damages. Amoco, 480 U.S. at

545 (“Environmental injury, by its nature, can seldom

be adequately remedied by money damages and is

often permanent or at least of long duration, i.e.

irreparable.”) (emphasis added). Moreover, money

39a

damages are not even available to ICL. The only relief

available in a CWA citizen-suit enforcement action is

the enforcement of standards, limitations, and orders,

or the application of civil penalties paid to the United

States Treasury. 33 U.S.C. § 1365(a). As a result, legal

remedies are plainly inadequate.

3. The Balance of Hardships Favors an

Injunction

Even where environmental injury is established,

courts must still engage in the traditional balancing

of harms test before entering an injunction. This

includes a consideration of all of the competing

interests at stake including potential economic harm.

Carlton, 626 F.3d at 475. Here, there is no

counterweight to the irreparable injury caused by

Mr. Poe’s permitless suction dredge mining on the

SFCR. That is, any burden in complying with the

CWA by securing the legallynecessary NPDES

permit—what the requested injunctive relief

requires—is not a hardship, let alone one that would

eclipse the above-stated environmental harms. See

Idaho Conservation League v. Atlanta Gold Corp., 879

F. Supp. 2d 1148, 1161 (D. Idaho 2012) (“Harm to

environment outweighs a defendant’s financial

interests, particularly where violations are of a

longstanding and continual nature.”).

4. An Injunction Is in the Public Interest

Courts have recognized that ensuring protection of

the environment serves an important public interest.

McNair, 537 F.3d at 1005 (“[P]reserving environmental resources is certainly in the public’s interest.”);

Earth Island Inst., 442 F.3d at 1177 (“The

preservation of our environment . . . is clearly in the

40a

public interest.”). Recognizing the public interest in

protecting the environment, it is likewise very much

in the public interest to expect compliance with the

CWA. See U.S. v. Akers, 785 F.2d 814, 823 (9th Cir.

1986) (“[C]ourts have noted that the public interest

requires strict enforcement of the [CWA] to effectuate

its purpose of protecting sensitive aquatic environments.”); Atlanta Gold Corp., 879 F. Supp. 2d at 1162

(“Water is the West’s most precious resource. Keeping

Idaho’s waters sufficiently clear of toxic elements so

that they can support all the beneficial uses for which

the State has designated them is a critical public

interest . . . .”). Mr. Poe does not argue otherwise.

5. Other Factors Do Not Undermine the Need for

an Injunction

Beyond the customary factors that inform the

propriety of an injunction, Mr. Poe’s arguments

against one take a more practical, big-picture

approach. He claims that an injunction is simply

(i) unnecessary to secure his compliance with the

CWA because he is not currently suction dredge

mining in Idaho (and has not done so since 2018) and

(ii) moot given the availability of civil penalties. Resp.

to Mot. for Remedies at 13–16 (Dkt. 63). These

arguments are without merit.

First, it is misleading to suggest that Mr. Poe

complied with the CWA once ICL brought this action.

See id. at 14 (Mr. Poe stating: “[I]f a defendant comes

into compliance with the CWA after a complaint is

filed, then the principles of mootness prevent

maintenance of a suit for injunctive relief . . . .”). It

may be true that he has not technically violated the

CWA since then, but that is only because he has not

suction dredge mined in Idaho and therefore never

41a

needed to pull an NPDES permit. This is not because

he has proactively secured an NPDES permit before

again suction dredge mining in the state. The

distinction is important when understanding that the

mere cessation of a challenged practice in response to

pending litigation “does not moot a case unless the

party alleging mootness can show that the ‘allegedly

wrongful behavior could not reasonably be expected to

recur.’” Nat. Res. Def. Council v. Cnty. of Los Angeles,

840 F.3d 1098, 1104 (9th Cir. 2016) (quoting Laidlaw,

528 U.S. at 189) (emphasis added); see also Idaho

Rural Council v. Bosma, 143 F. Supp. 2d 1169, 1177

(D. Idaho 2001) (recognizing “a presumption of future

injury” when a defendant has voluntarily ceased

illegal activity in response to litigation, even if the

cessation occurs before a complaint is filed.”). Without

the exception, “‘courts would be compelled to leave

[t]he defendant . . . free to return to his old ways.’”

Porter v. Bowen, 496 F.3d 1009, 1017 (9th Cir. 2007)

(quoting U.S. v. Concentrated Phosphate Exp. Ass’n,

393 U.S. 199, 203 (1968)).

The standard for determining whether a case has

been mooted by a defendant’s voluntary conduct is

“stringent.” Laidlaw, 528 U.S. at 189; Concentrated

Phosphate, 393 U.S. at 203 (“A case might become

moot if subsequent events made it absolutely clear

that the allegedly wrongful behavior could not

reasonably be expected to recur.”) (emphasis added).

“The ‘heavy burden of persua[ding]’ the court that the

challenged conduct cannot reasonably be expected to

start up again lies with the party asserting mootness.”

Laidlaw, 528 U.S. at 189 (quoting Concentrated

Phosphate, 393 U.S. at 203). This burden “protects

plaintiffs from defendants who seek to evade sanction

by predictable protestations of repentance and

42a

reform.” Gwaltney of Smithfield v. Chesapeake Bay

Found., 484 U.S. 49, 67 (1987).

The Court previously touched on this issue in

relation to Mr. Poe’s efforts to dismiss the action at its

outset. At that time, Mr. Poe argued that the Court

did not have subject matter jurisdiction because ICL

failed to meet the CWA’s notice requirements.

Specifically, Mr. Poe argued that ICL’s 2016 notice

letter advising him that it intended to initiate a

citizen-suit enforcement action relied on wholly past

violations, not prospective ones. Poe, 421 F. Supp. 3d

at 991. The Court disagreed, stating:

Mr. Poe properly acknowledges that [ICL]

must have a good faith allegation of

continuing or intermittent violations for a

court to have jurisdiction over a suit. . . .

Here, ICL made good faith allegations of

continuing/ intermittent CWA violations

based not only on Mr. Poe’s history of

suction dredging on the [SFCR], but also his

public statements about his past dredging,

about his ongoing dredging, and about his

plans for dredging in future years (including

statements about defying the EPA and the

CWA). Indeed, it could reasonably be said

that Mr. Poe was intentionally advertising

to the world not just the fact of his prior

suction dredging activities but also the fact

of his intended future suction dredging

activities. That Mr. Poe ultimately resumed

suction dredging activities on the [SFCR] in

2018

without

any

NPDES

permit

substantiates

ICL’s

concerns

about

43a

Mr. Poe’s “continuing”

violations back in 2016.

and

“ongoing”

Id. at 993 (citing Sierra Club v. Union Oil Co. of Cal.,

853 F.2d 667, 671 (9th Cir. 1988) (agreeing that risk

of ongoing violations must be “completely eradicated”

for citizen suit to be precluded, holding: “Intermittent

or sporadic violations do not cease to be ongoing until

the date when there is no real likelihood of

repetition.”)).

A similar rationale applies now. Yes, Mr. Poe

properly stresses how he has not suction dredge mined

in Idaho since 2018. And while that fact may suggest

he does not intend to pick back up where he left off, it

does not satisfy his burden to establish compliance

with the CWA in the future. To be sure, in the past,

Mr. Poe has simply indicated that he “do[es] not

intend to dredge in future years without the

appropriate permits.” Ex. C to Oppenheimer Decl.

(Dkt. 20-19) (emphasis added). It is unclear what this

commitment means or ever meant. Critically, Mr. Poe

suction dredge mined on the SFCR in 2018 without an

NPDES permit precisely because he does not believe

an NPDES permit is required to do so. Cf. Resp. to

Mot. for Remedies at 15 (Dkt. 63) (Mr. Poe

acknowledging that “he never stated that he would

not mine without first obtaining an NPDES permit.”).

Alas, that is what this entire case has been about.

At bottom, Mr. Poe must show that there is “no

reasonable expectation that the wrong will be

repeated” and that it is “absolutely clear that the

allegedly wrongful behavior would not reasonably be

expected to recur.” Gwaltney, 484 U.S. at 66. Despite

no known CWA violations since 2018, Mr. Poe has not

met that high burden here. See Atlanta Gold, 879 F.

44a

Supp. 2d at 1162 (fact that violations were “of a

continual, and long-standing nature” and that

defendant “passed up opportunities to fix the problem,

strongly suggests that the added impetus of an

injunction is necessary.”). An injunction is neither

unnecessary nor moot.

Second, civil penalties—even considerable ones—

do not preclude injunctive relief. These remedies are

not mutually exclusive. In fact, the CWA authorizes

courts to impose one, the other, or even both. Supra;

see also Idaho Conservation League v. Magar, 2015

WL 632367, at *9 (D. Idaho 2015) (“[T]he Court finds

both a substantial civil penalty and an injunction are

necessary to remedy Magar’s violations of the CWA.”);

Atlanta Gold, 879 F. Supp. 2d at 1171 (“To

summarize, the longstanding and serious nature of

the violations in this case require injunctive relief. A

substantial civil penalty is also necessary in order to

have a deterrent effect on future pollution . . . .”);

Bosma, 143 F. Supp. 2d at 1177 (“[A]n injunction

against the Bosmas and their dairy operation will

redress, at least in part, the injury of which the IRC

complains. Additionally, the civil penalties sought by

IRC will likely deter the Bosmas and other NPDES

permit violators from polluting the affected waters in

the future.”). Simply put, whether civil penalties are

imposed here (or the amount of such penalties) is

immaterial;

the

factors

discussed

herein

independently support injunctive relief.

6. The Injunction is Limited to the SFCR

As an extraordinary remedy, an injunction’s scope

must be narrowly and specifically tailored to fit the

dispute that gives rise to its issuance, and not more.

Stormans, Inc. v. Selecky, 586 F.3d 1109, 1140 (9th

45a

Cir. 2009) (“‘Injunctive relief . . . must be tailored to

remedy the specific harm alleged.’ ‘An overbroad

injunction is an abuse of discretion.’”) (quoting LambWeston v. McCain Foods, Ltd., 941 F.2d 970, 974 (9th

Cir. 1991)).

ICL seeks to enjoin Mr. Poe from suction dredge

mining throughout Idaho unless he obtains and

complies with an NPDES permit under the CWA.

Mem. ISO Mot. for Remedies at 3, 5, (Dkt. 59-1). But

this action is tied only to Mr. Poe’s suction dredge

mining on the SFCR. There is no evidence in the

record concerning what Mr. Poe did (or did not do)

elsewhere in the state and ICL makes no claims

relating to any such conduct. So, a state-wide

injunction is not justified.

Mr. Poe counters that no injunction is warranted

at all. He complains that one would amount to a

disfavored “obey the law” injunction and is

“excessively intrusive” because it would require the

Court’s continual supervision. Resp. to Mot. for

Remedies at 13–14 (Dkt. 63). Not so. The injunction is

not vague but rather sufficiently specific. It requires

Mr. Poe to secure and comply with an NPDES permit

before suction dredge mining on the SFCR in the

future. These simple and straightforward terms are

enough. Further, no judicial oversight is warranted

here. Once this action is closed, ICL can move to reopen the case and pursue contempt proceedings as

necessary. See, e.g., Idaho Conservation League v.

Atlanta Gold Corp., 2017 WL 4099815 at *1 (D. Idaho

2017) (“This decision resolves a Motion for Civil

Contempt . . . . This is a re-opened Clean Water Act

case, first filed in 2011.”).

46a

Consequently, an injunction will be issued barring

Mr. Poe from suction dredge mining on the SFCR

unless he obtains and complies in good faith with an

NPDES permit under the CWA.

C. Civil Penalties in the Amount of $150,000

Are Warranted

ICL asks the Court to impose a civil penalty of at

least $564,924 for Mr. Poe’s 42 CWA violations. Mem.

ISO Mot. for Remedies at 14–22 (Dkt. 59-1). Mr. Poe

argues the Court should reject ICL’s request as

excessive and unduly burdensome, proposing that a

$60,924 penalty more accurately addresses his

conduct and the surrounding circumstances. Resp. to

Mot. for Remedies at 16–24 (Dkt. 63).

Congress has vested courts with the authority to

determine an appropriate civil penalty for CWA

violations. Tull v. U.S., 481 U.S. 412, 427 (1987). Like

other penalties, the purpose of a penalty under the

CWA is to provide restitution, punish the violator, and

deter similar conduct by the violator and others. Id. at

422. “A penalty must be high enough so that the

discharger cannot ‘write it off’ as an acceptable

environmental trade-off for doing business.” Hawaii’s

Thousand Friends v. City and Cnty. of Honolulu, 821

F. Supp. 1368, 1394 (D. Haw. 1993).

Civil penalties in CWA cases involve “highly

discretionary calculations that take into account

multiple factors.” Tull, 481 U.S. at 427. The factors

courts must consider are: (i) the seriousness of the

violations; (ii) the economic benefit, if any, resulting

from the violations; (iii) any history of such violations;

(iv) any good faith efforts to comply with the

applicable requirements; (v) the economic impact of

47a

the penalty on the violator; and (vi) any other matters

as justice may require. 33 U.S.C. § 1319(d).

When considering these statutorily-enumerated

factors, courts generally employ either a “top-down” or

“bottom-up” approach. Atlanta Gold, 879 F. Supp. 2d

at 1165 (comparing Sierra Club v. Cedar Point Oil Co.,

73 F.3d 546, 573–74 (5th Cir. 1996) (employing topdown approach), with U.S. v. Smithfield Foods, Inc.,

191 F.3d 516, 528–29 (4th Cir. 1999) (taking bottomup approach)). The top-down approach requires the

court to first calculate the maximum penalty, and

then, if necessary, to adjust the penalty downward in

consideration of the six statutory factors. Cedar Point,

73 F.3d at 573. The bottom-up method begins with

calculating the economic benefit realized by the

defendant as a result of his non-compliance, and then

adjusts that amount upward or downward based on

the court’s evaluation of the remaining factors.

Smithfield Foods, 191 F.3d at 528.

ICL does not insist on either a top-down or bottomup approach to calculating the proper civil penalties

here. It references a $1,957,041 maximum penalty.9 It

settles on a proposed penalty of at least $564,924.

ICL’s figure is guided in large part by the $6,600

penalty imposed in a similar EPA civil enforcement

action (Erlanson (discussed infra)) relating to a single

day of unpermitted suction dredge mining on the

SFCR in 2015. Here, citing Mr. Poe’s flagrant

violations and need for deterrence, the ICL doubled

the per-violation penalty to $13,200 and added

Mr. Poe’s $10,524 economic gain to the total penalty.

9 This represents a total of 25 violations in 2014 and 2015 at

$37,500 per violation ($937,500) and 17 violations in 2018 at

$59,973 per violation ($1,019,541).

48a

Mem. ISO Mot. for Remedies at 13–16 (Dkt. 59-1).

Mr. Poe favors a bottom-up approach because,

according to him, it better reflects the minimal

environmental harm caused by his suction dredge

mining. Resp. to Mot. for Remedies at 17 (Dkt. 63).

The Court will employ the bottom-up approach as

the most practical to these facts. This case is unique

in that Mr. Poe did not outright ignore the need for an

NPDES permit in the typical sense. His decision not

to secure an NPDES permit was informed, at least in

part, by advice from his attorney, coupled with their

correspondence with the EPA about whether he even

needed an NPDES permit in the first instance. See

infra. Also, it is not exactly clear how Mr. Poe’s suction

dredge mining violated NPDES permit standards

(aside from not securing an NPDES permit in and of

itself). Id. These considerations favor a bottom-up

approach rather than beginning with a nearly

$2 million maximum civil penalty and working down.

See Atlanta Gold, 879 F. Supp. 2d at 1166 (describing

bottom-up approach as “more practical in this

scenario, as arsenic and iron differ greatly in terms of

the degree of the environmental harm they cause.”).

With that, the Court turns to the above-referenced

statutory factors for calculating CWA-related

penalties.

1. The Economic Benefit From Mr. Poe’s CWA

Violations

Mr. Poe’s most obvious economic benefit in suction

dredge mining on the SFCR without an NPDES

permit is the value of mineral resources (gold)

extracted therefrom. Remedial phase discovery

revealed that Mr. Poe mined up to six ounces of gold

across 2014, 2015, and 2018. Mem. ISO Mot. for

49a

Remedies at 18 (Dkt. 59-1). At an estimated value of

$1,754 per ounce, the value of Mr. Poe’s unpermitted

haul amounts to at least $10,524. Id. Mr. Poe does not

disagree; he folds this exact amount into his own civil

penalty proposal. Resp. to Mot. for Remedies at 17, 24

(Dkt. 63). The civil penalty therefore begins at $10,524

and is subject to adjustment in light of the remaining

factors.

2. The Seriousness and History of Mr. Poe’s CWA

Violations

Congress flatly prohibited “the discharge of any

pollutant by any person” except as in compliance with

the CWA. 33 U.S.C. § 1311(a). There is no dispute that

Mr. Poe violated this prohibition time and again when

he suction dredge mined on the SFCR without an

NPDES permit in 2014, 2015, and 2018. These

violations are unquestionably serious. They not only

violated the law, but also caused environmental harm

by lowering water quality. See supra.

But in assessing the “seriousness” of these

violations, it is important to keep in mind that suction

dredge mining is allowed on the SFCR. In other words,

this is not a case of Mr. Poe suction dredge mining at

a time and place where it was not lawfully permitted.

His problem is that he repeatedly suction dredge

mined without an NPDES permit (even if he did have

a state IDWR permit with some—though not

completely—overlapping best management practices).

See, e.g., Poe, 421 F. Supp. 3d at 998, n.6 (in denying

Mr. Poe’s earlier Motion to Dismiss, Judge Bush

explaining that “the IDWR and NPDES permits are

not identical, as there is some overlap but also

numerous differences.”). Still, Mr. Poe argues that

ICL has not claimed that he violated either his IDWR

50a

permit or any actual NPDES permit requirements

(except for the 800-foot separation requirement (see

supra)). Resp. to Mot. for Remedies at 12, 17–20 (Dkt.

63); but see Reply ISO Mot. for Remedies at 11, n.4

(Dkt. 64) (ICL identifying instances where Mr. Poe

violated IDWR permit and reporting requirements

attached to NPDES permits). If so, how do the

environmental impacts of Mr. Poe’s unpermitted

suction dredge mining stack up against another’s

permitted suction dredge mining? If they are

comparable, how “serious” are Mr. Poe’s CWA

violations when evaluating a commensurate civil

penalty? See, e.g., Magar, 2015 WL 632367, at *5

(difficulty in attributing water quality problems to

illegal discharges “neither compel nor preclude a

reduction to the maximum civil penalty”); but cf.

Atlanta Gold, 879 F. Supp. 2d at 1168 (finding

discharges of arsenic and iron in excess of effluent

limitations over three-year period sufficient to justify

significant upward adjustment of total civil penalty).

The record does not neatly confront these

questions except to underscore the spectrum of

possible CWA violations and corresponding levels of

impact (seriousness). What is clear, however, is that

Mr. Poe violated the CWA when he suction dredge

mined 42 days on the SFCR without the required

NPDES permit and that these activities added

pollutants to the river and caused environmental

harm. Supra. Any similarities between properlypermitted mining activities and Mr. Poe’s

unpermitted (but nonetheless allegedly compliant)

mining activities largely miss the point and represent

a false equivalence. Mr. Poe should not have been

suction dredge mining without an NPDES permit at

all. The liability phase confirmed as much. Had he not,

51a

he never would have discharged pollutants into the

waterway, even if his activities otherwise complied

with a hypothetical NPDES permit (that may not have

even been issued). Each of the 42 times he did this

represents a serious CWA violation that, together,

warrant an upward adjustment of the civil penalty

amount.

3. Mr. Poe’s Good Faith Efforts to Comply With

the CWA

Good faith efforts to comply with applicable

requirements may reduce civil penalties. This factor

turns on whether Mr. Poe “took any actions to

decrease the number of violations or made efforts to

mitigate the impact of [his] violations on the

environment.” U.S. v. Smithfield Foods, Inc., 972 F.

Supp. 338, 349–50 (E.D. Va. 1997).

ICL argues that Mr. Poe took no steps to comply

with the CWA or to mitigate the effects of his suction

dredge mining. Mem. ISO Mot. for Remedies at 20

(Dkt. 59-1) (“Poe’s compliance efforts could hardly be

less vigorous. In fact, non-compliance has often been

Poe’s stated intention . . . .”) (emphasis in original). In

response, Mr. Poe does not walk back his belief that

suction dredge mining does not require an NPDES

permit or that he has openly suction dredge mined in

opposition to the EPA. Resp. to Mot. for Remedies at

21 (Dkt. 63). He instead claims that his opinions are

protected by the First Amendment, while noting his

consistent

compliance

with

IDWR

permit

requirements to show that he “still respected the

conditions that are in place to minimize and eliminate

the environmental impacts of his operations.” Id.

52a

Whatever protections exist via the First

Amendment, they do not excuse violations of the law

and certainly do not amount to good faith efforts to

comply with the CWA. Just the opposite. And while

observing state permitting requirements is better

than the alternative, its attendant “no harm no foul”

logic comes up short when assessing Mr. Poe’s good

faith efforts to respect a different, albeit parallel,

permitting standard that may have applied to

preclude his suction dredge mining on the SFCR and

foreclosed its environmental impacts altogether.

Supra. In short, these aspects of Mr. Poe’s

counterarguments are misplaced.

Despite all this, it is noteworthy that Mr. Poe’s

insistence against an NPDES permit did not seem to

be a knee-jerk reaction to an inconvenient legal

requirement getting in the way of his gold mining

pursuits. He was told this by his own attorneys before

he first suction dredge mined in Idaho in 2014. Poe

Dep., attached as Ex. B to 2nd Hurlbutt Decl. at 13:8–

20 (Dkt. 38-5) (“Q: When you went to Idaho, did you

have an NPDES permit for suction dredging in Idaho

in 2014? A: No. Q: Had you applied for one? A: No. Q:

And why didn’t you have one, Mr. Poe? A: At the

advice of my attorney, I didn’t. I was informed that I

did not need one.”); see also Poe Decl. ISO MSJ at ¶12

(Dkt. 39-4) (“I did not obtain an NPDES permit from

the Environmental Protection Agency (EPA) [in 2014]

because I was informed by my attorney that one was

not required.”). What’s more, after receiving notice

from the EPA in October 2014 about violating the

CWA for suction dredge mining on the SFCR without

an NPDES permit, Mr. Poe’s counsel wrote back and

explained why the EPA’s position was wrong. Exs. A

& B to Poe Decl. ISO Mot. to Dismiss (Dkt. 17-2). The

53a

EPA never responded, never contacted Mr. Poe or his

attorney again, and never took any further action. It

was thus no real surprise when Mr. Poe suction

dredge mined in Idaho in 2015 and 2018 without an

NPDES permit, even after receiving ICL’s “intent to

sue” notices in 2016, 2017, and 2018. Poe Decl. ISO

MSJ at ¶ 15 (Dkt. 39-4) (“I did not obtain an NPDES

permit from the EPA [in 2015] because, according to

counsel, the IDWR permit was the only permit I was

legally required to get.”); id. at ¶ 19 (same for 2018).

It is therefore possible to argue that this is not a

situation where Mr. Poe obviously knew better but

acted on his impulses and misguided convictions

anyway. His attorney told him that an NPDES permit

was not required and this advice aligned with his own

subjective view on the matter.10 That said, it does not

establish a good faith effort to comply with the CWA

(even if it may countenance against a finding of

outright bad faith) or render him legally blameless.

Short of actually securing the required NPDES permit

before suction dredge mining, the proper course of

action in this instance was to administratively engage

to resolution or proactively seek relief from the courts.

Mr. Poe purposely chose not to, ignored violation

notices, and proceeded to repeatedly suction dredge

mine on the SFCR without a permit. He ultimately did

so to his own detriment. Accordingly, an upward

adjustment of the civil penalty amount is in order.

10 In this way, ICL’s reliance on Erlanson is undercut. There,

Mr. Erlanson submitted an NPDES permit application to the

EPA but was denied. In re Dale Erlanson, Sr., Docket No. CWA10-2016-0109 (U.S. Environmental Protection Agency) at 7,

attached as Ex. D to 4th Hurlbutt Decl. (Dkt. 59-6). He suction

dredge mined anyway.

54a

4. The Economic Impact on Mr. Poe

Courts may reduce the civil penalty against a party

if the maximum statutory penalty would work an

undue hardship. Atlantic States Legal Found. v.

Universal Tool & Stamping Co., 786 F. Supp. 743,

753–54 (N.D. Ind. 1992). This factor will not reduce

the amount of the penalty unless the violator can show

that the penalty will have a “ruinous effect.” Magar,

2015 WL 632367, at *7 (citing U.S. v. Gulf Park Water

Co., 14 F. Supp. 2d 854, 868 (S.D. Miss. 1998)).

ICL argues that a penalty of at least $564,924

(already reduced from the $1,957,041 maximum

penalty) is warranted and will not impose an undue

burden on Mr. Poe given his personal assets and close

affiliation with AMRA.11 Mem. ISO Mot. for Remedies

at 21–22 (Dkt. 59-1). Mr. Poe insists that ICL

overstates his financial association with AMRA and

that ICL’s proposed penalty “places a significant

burden” on him individually. Resp. to Mot. for

Remedies at 21–23 (Dkt. 63). He submits that a

$60,924 penalty is more appropriate. Id. at 24.

Mr. Poe is an individual professional miner and

claims to have limited annual income and only a

limited number of assets. Id. at 23. To that end, he

states that his main source of income over the last few

years comes from his mining operations, a previouslyowned rental property, and the small consulting fees

received from AMRA. Id. He goes on to identify $3,000

in savings, a 2007 truck worth $5,000–$8,000, a 1985

11 AMRA is a 501(c)(3) non-profit that provides “mining education

and assist[s] small miners and public land users with issues that

arise when mining on state and federal lands.” Poe Decl. ISO

MSJ at ¶ 2 (Dkt. 39-4). “AMRA focuses on regulatory initiatives

that directly affect small miners.” Id.

55a

mobile home worth about $15,000, roughly 16 ounces

of gold valued at $28,064, and $75,000 in proceeds

from a recent sale of a 10-acre parcel of land. Id.12 ICL

does not dispute these figures or argue that Mr. Poe is

capable of paying its proposed civil penalty from these

rather modest income sources and assets; its

argument centers on Mr. Poe’s alleged access to

AMRA’s significant financial resources. Reply ISO

Mot. for Remedies at 111–12 (Dkt. 64). The economic

impact that a penalty will have on Mr. Poe

consequently rises and falls with the contours of this

relationship.

To begin, Mr. Poe is a founder and the President of

AMRA. Resp. to Mot. for Remedies at 5–6 (Dkt. 63).

He submits posts and uploads videos to AMRA’s

webpage about proposed federal and state legislation,

general mining activity, and issues impacting water

rights. He promotes AMRA during his mining trips.

He submits his mining activities as content on

AMRA’s webpage. Id. at 6. Despite this administrative

involvement with AMRA, the record reveals that all of

Mr. Poe’s suction dredge mining on the SFCR in 2014,

2015, and 2018 was done at his own expense, under

his own personal IDWR permits, and for his own

personal economic benefit—not AMRA’s. Id. at 6 & 23.

In this context, there is no basis to conclude that

Mr. Poe and AMRA are effectively one-and-the-same.

This action bears that out, with ICL asserting

12 In comparison, the plaintiff in Magar had $11,914.36 deposited

in various bank accounts, $3 million in unencumbered assets,

and $45,974.58 in monthly income. Magar, 2015 WL 632367, at

*7 (“Given evidence that Magar has substantial income and

unencumbered assets, the Court is not persuaded that a

substantial civil penalty would lead Magar to financial ruin.”).

Mr. Poe does not have these same resources.

56a

claims only against Mr. Poe individually, not AMRA

institutionally.

At the same time, Mr. Poe concedes that AMRA

provides monetary support to miners, including

himself, that are dealing with legal issues. Id. at 6; see

also Ex. C. to Hurlbutt Decl. (Dkt. 20-4) (AMRA

fundraising posting: “We could use some new

members, we have legal bills to pay . . . . You can

support AMRA with a $5 monthly donation.

Remember, this goes to fight for your mining rights

. . . .”); Ex. B to 4th Hurlbutt Decl. (Dkt. 59-4) (“We

will be doing many outings, fundraisers, dinners and

even yes . . . another Walk for Liberty to raise money

for this legal fight. . . . If you’d like to make a donation

or join AMRA, clink the link below.”) (emphasis

added); id. at Ex. C (Dkt. 59-5) (“[W]e need to spend a

large amount of money to get [this case] to appeal. We

are looking to raise $150,000 to get there folks. . . .

Want to make a cash donation, click the link below.”).

The true extent of this support, however, and whether

it would apply to a civil monetary penalty, is

unknown. At the end of the day, the mere possibility

of Mr. Poe’s access to AMRA’s legal defense fund

definitely generates “smoke” but not enough “fire” to

legitimize ICL’s matter-of-fact statement that, owing

to his ties to AMRA, “[Mr.] Poe has significant funds

to pay a penalty” of at least $564,924. Mem. ISO Mot.

for Remedies at 22 (Dkt. 59-1). The record is simply

too underdeveloped for such a broad legal conclusion.

All in all, the Court is satisfied that imposing a

civil penalty of at least $564,924 would have a more

drastic effect on Mr. Poe than is needed to account for

his CWA violations and ensure future compliance.

This does not mean that Mr. Poe’s suggested $60,924

57a

penalty prevails by default either. To the contrary,

Mr. Poe fails to explain the basis for this significantly

lower amount13 or how a higher penalty would be

ruinous to him. Because Mr. Poe failed to meet this

burden, the Court is not limited to the $60,924 penalty

he proposes.

5. Other Considerations

It is not unusual to try and determine whether a

civil penalty is equitable by drawing comparisons to

analogous cases. See U.S. v. Righter, 2010 WL

4977046, at *4 (M.D. Pa. 2010) (performing side-byside comparison of two cases to fashion equitable

penalty). Both ICL and Mr. Poe attempt to do this.

Compare Mem. ISO Mot. for Remedies at 14–16 (Dkt.

59-1), with Resp. to Mot. for Remedies at 23–24 (Dkt.

63). These exercises are helpful in the abstract, but

rarely supply an “apples to apples” comparison that

uncovers an obvious answer. Cases may deal with

different facts, different party statuses (individual vs.

corporate), different legal proceedings (court vs.

administrative), different manners of resolution

(settlement vs. finding of liability), or just different

methods of calculation (high per violation penalties in

low volume cases vs. low per violation penalties in

high volume cases) that frustrate comparison. Id. The

following chart incorporates the parties’ cases and

confirms as much:

13 More specifically, Mr. Poe has not supplied the basis for his

suggested $1,200 per day violation of the CWA. This figure,

multiplied by Mr. Poe’s 42 CWA violations, and then added to his

$10,524 economic benefit, amounts to $60,924.

C

I

I

I

I

I

C

Atlanta Gold

Magar

Erlanson

Rice

Grissom

Rogue

Riverkeeper

Poe

$1,957,041

$99,525,000

$203,256

$16,000

$16,000

$187,500

$75,150,500

Max Penalty

??

$96,150 (~1%)

$24,000 (~12%)

$3,600 (~23%)

$6,600 (~41%)

$100,000 (~53%)

$2 million (~3%)

Imposed Penalty

42

2,654

9

1

1

5

2,000

Violations

??

$37.50/per

$2,667/per

$3,600/per

$6,600/per

$20,000/per

$1,000/per

Per

violation

14 ICL cites to Atlanta Gold, Magar, and Erlanson; Mr. Poe cites to Rice, Grissom, and Rogue Riverkeeper.

Status

Case14

58a

59a

Of note, Erlanson, Rice, and Grissom dealt with

suction dredge mining on the SFCR without an

NPDES permit which the Court considers relevant

when evaluating the seriousness of Mr. Poe’s CWA

violations. However, only Erlanson included a finding

of liability (albeit administratively); the Rice and

Grissom penalties resulted from settlements with the

EPA. In all, the cases are difficult to reconcile and

fact-dependent. Accordingly, they provide only limited

comparative guidance.

Suffice it to say, and mindful of the complexities

inherent in cases like this, the Court exercises its

discretion and assesses a total civil penalty of

$150,000 for Mr. Poe’s 42 CWA violations. This

amount includes (i) the $10,524 direct economic

benefit that Mr. Poe received from his CWA violations

and (ii) $139,476 ($3,320.86 per violation) following

the Court’s evaluation of the remaining § 1319(d)

factors. Supra.

This penalty represents less than 8% of the

maximum possible penalty, yet can still be read

consistently with the penalties imposed in analogous

cases. It recognizes on the one hand the serious nature

of Mr. Poe’s 42 violations over three years; on the

other hand, it does not ignore the fact that suction

dredge mining is allowed on the SFCR (when properly

permitted) and that Mr. Poe is an individual suction

dredge miner, mines for his own personal benefit, and

has limited resources (though receives financial

support—to some degree—from AMRA). With these

overarching considerations in mind, the Court is

satisfied that this penalty accounts for the harm

involved, deters future violations, and represents an

equitable application of the law.

60a

III. ORDER

Based on the foregoing, IT IS HEREBY ORDERED

that ICL’s Motion for Remedies (Dkt. 59) is

GRANTED as follows:

1. An

injunction

consistent

with

this

Memorandum Decision and Order shall issue as part

of a separate judgment.

2. Defendant Shannon Poe shall pay a civil

penalty of $150,000 to the United States Treasury.

3. Within 14 days of this Memorandum Decision

and Order, the parties are instructed to submit a joint

proposal to the Court, addressing (i) the terms of the

injunction and (ii) a deadline for the $150,000

payment

and

any

corresponding

payment

schedule/logistics.

DATED: September 28, 2022

/s/ Raymond F. Patricco

Honorable Raymond E. Patricco

Chief U.S. Magistrate Judge

61a

Filed June 4, 2021

UNITED STATES DISTRICT COURT

DISTRICT OF IDAHO

IDAHO

CONSERVATION

LEAGUE,

Plaintiff,

vs.

SHANNON POE,

Defendant.

Case No.: 1:18-cv-353-REB

MEMORANDUM

DECISION AND

ORDER RE:

IDAHO

CONSERVATION

LEAGUE’S MOTION

FOR SUMMARY

JUDGMENT ON

LIABILITY

(Dkt. 38)

SHANNON POE’S

MOTION FOR

SUMMARY JUDGMENT

(Dkt. 39)

Pending before the Court is Plaintiff Idaho

Conservation League’s Motion for Summary

Judgment on Liability (Dkt. 38) and Defendant

Shannon Poe’s Motion for Summary Judgment (Dkt.

39). Having carefully considered the record,

participated in oral argument, and otherwise being

fully advised, the Court enters the following

Memorandum Decision and Order:

I. RELEVANT BACKGROUND

The pertinent facts that now frame the legal issues

involved in this case (and as presented in the parties’

cross-motions for summary judgment) are largely

62a

undisputed1—namely, that Mr. Poe suction dredge

mined 42 days on the South Fork Clearwater River

during the 2014, 2015, and 2018 dredge seasons

(running from July 15 to August 15 each year),

without ever obtaining an NPDES permit under

Section 402 of the CWA. ICL argues that Mr. Poe

violated the CWA each time he operated a suction

dredge on the South Fork Clearwater River without

an NPDES permit. Mr. Poe disagrees, countering that

(1) his suction dredge mining did not add pollutants to

the South Fork Clearwater River and therefore did

not require an NPDES permit (or any other CWA

permit) in the first instance; and (2) even if his suction

dredge mining did add pollutants, those pollutants are

“dredged” or “fill” material regulated exclusively

under Section 404 (not Section 402) of the CWA and

therefore did not require an NPDES permit.2 This

Memorandum Decision and Order confronts these

Within its September 30, 2019 Memorandum Decision and

Order denying Defendant Shannon Poe’s Motion to Dismiss, the

Court generally discussed the characteristics of the South Fork

Clearwater River; recreational suction dredge mining and

National Pollutant Discharge Elimination System (“NPDES”)

permit requirements under the Clean Water Act (“CWA”);

Idaho’s permitting requirements for suction dredging; Mr. Poe’s

suction dredge activity on the South Fork Clearwater River

without an NPDES permit in 2014, 2015, and 2018; and Plaintiff

Idaho Conservation League’s (“ICL”) correspondence to Mr. Poe

in 2016, 2017, and 2018 advising him of its intention to initiate

a CWA citizen suit against him if he continued to suction dredge

in Idaho without an NPDES permit. See generally 9/30/19 MDO,

pp. 1–8 (Dkt. 26). This backdrop, while important for context, will

not be repeated here.

1

Mr. Poe further argues that any discharges from his suction

dredge mining are only “incidental fallback,” making them

exempt from Section 404 of the CWA in any event.

2

63a

positions, resolving the question of whether Mr. Poe’s

suction dredge mining is governed under Section 402

or Section 404 of the CWA.

II. LEGAL STANDARD

Summary judgment requires a showing that, as to

any claim or defense, “there is no genuine dispute as

to any material fact and the movant is entitled to

judgment as a matter of law.” Fed. R. Civ. P. 56(a). A

principal purpose of summary judgment “is to isolate

and dispose of factually unsupported claims . . . .”

Celotex Corp. v. Catrett, 477 U.S. 317, 323 (1986). It is

“not a disfavored procedural shortcut”; rather, it is the

“principal tool[ ] by which factually insufficient claims

or defenses [can] be isolated and prevented from going

to trial with the attendant unwarranted consumption

of public and private resources.” Id. at 327. “[T]he

mere existence of some alleged factual dispute

between the parties will not defeat an otherwise

properly supported motion for summary judgment.”

Anderson v. Liberty Lobby, Inc., 477 U.S. 242, 247–48

(1986). There must be a genuine dispute as to any

material fact—a fact “that may affect the outcome of

the case.” Id. at 248.

The evidence must be viewed in the light most

favorable to the non-moving party, and the court must

not make credibility findings. See id. at 255. Direct

testimony of the non-movant, however implausible,

must be believed. See Leslie v. Grupo ICA, 198 F.3d

1152, 1159 (9th Cir. 1999). However, the court is not

required to adopt unreasonable inferences from

circumstantial evidence. See McLaughlin v. Liu, 849

F.2d 1205, 1208 (9th Cir. 1988).

64a

In deciding cross-motions for summary judgment,

the court considers each party’s evidence. See Las

Vegas Sands, LLC v. Nehme, 632 F.3d 526, 532 (9th

Cir. 2011); see also Fair Hous. Council of Riverside

Cnty., Inc. v. Riverside Two, 249 F.3d 1132, 1134 (9th

Cir. 2001) (“[W]hen simultaneous cross-motions for

summary judgment on the same claim are before the

court, the court must consider the appropriate

evidentiary material identified, and submitted in

support of both motions, and in opposition to both

motions, before ruling on each of them.”). The court

must independently search the record for factual

disputes. See Fair Hous. Council of Riverside Cnty.,

Inc. v. Riverside Two, 249 F.3d 1132, 1134 (9th Cir.

2001). Even though the filing of cross-motions for

summary judgment means that both parties

essentially assert that there are no material factual

disputes, the Court nonetheless must decide whether

disputes as to material fact are present. See id.

The moving party bears the initial burden of

demonstrating the absence of a genuine dispute as to

material fact

This text is long and has been trimmed here. Open the source document for the complete record.

This is a copy of a public record, reproduced as it was published. It is not legal advice, and it may not be the version a court would rely on. Check the official source before you cite it.

A word about cookies

We need a few to keep you signed in and the library working. The rest help us see which pages people use and where they get stuck. They stay off unless you say yes.