Petition for Writ of Certiorari — Columbia Falls Aluminum Company, LLC, Petitioner v. Atlantic Richfield Company
Supreme Court briefJun 12, 2023
Ask Donna
What actually matters in this document.
Text
No. ______
In the
Supreme Court of the United States
COLUMBIA FALLS ALUMINUM CO., LLC,
Petitioner,
V.
ATLANTIC RICHFIELD CO.,
Respondent.
ON PETITION FOR A WRIT OF CERTIORARI
TO THE UNITED STATES COURT OF APPEALS
FOR THE NINTH CIRCUIT
PETITION FOR A WRIT OF CERTIORARI
SAMIR DEGER-SEN
PETER TROMBLY*
LATHAM & WATKINS LLP
1271 Avenue of the
Americas
New York, NY 10020
GREGORY G. GARRE
Counsel of Record
LATHAM & WATKINS LLP
555 Eleventh Street, NW
Suite 1000
Washington, DC 20004
(202) 637-2207
gregory.garre@lw.com
Counsel for Petitioner
i
QUESTION PRESENTED
Whether a district court’s equitable allocation of
environmental response costs pursuant to Section
113(f)(1) of the Comprehensive Environmental
Response, Compensation, and Liability Act
(CERCLA), 42 U.S.C. § 9613(f)(1), is properly
reviewed on appeal only for clear error, as the Fourth,
Fifth, and Ninth Circuits have held, or for abuse of
discretion, as the First, Second, Third, Sixth,
Seventh, Tenth, and D.C. Circuits have held.
ii
CORPORATE DISCLOSURE STATEMENT
Petitioner Columbia Falls Aluminum Co., LLC is
a wholly owned, indirect subsidiary of Glencore plc, a
publicly held company.
iii
RELATED PROCEEDINGS
The following proceedings are directly related to
this petition:
Columbia Falls Aluminum Co., LLC v. Atlantic
Richfield Co., No. 21-36042, United States Court of
Appeals for the Ninth Circuit, judgment entered
January 31, 2023, rehearing denied March 14, 2023.
Columbia Falls Aluminum Co., LLC v. Atlantic
Richfield Co., No. 9:18-cv-0131, United States District
Court for the District of Montana, findings of fact and
conclusions of law entered, August 25, 2021,
judgment entered September 27, 2021, motion to
amend or correct granted in part, November 23, 2021,
amended judgment entered, November 23, 2021.
iv
TABLE OF CONTENTS
Page
QUESTION PRESENTED ......................................... i
CORPORATE DISCLOSURE STATEMENT ........... ii
RELATED PROCEEDINGS ..................................... iii
TABLE OF AUTHORITIES .................................... vii
OPINIONS BELOW ....................................................1
JURISDICTION ..........................................................1
STATUTORY PROVISIONS INVOLVED .................1
INTRODUCTION .......................................................2
STATEMENT OF THE CASE ....................................4
A. Statutory Background ..................................4
B. Factual Background .....................................6
C. Proceedings Below ........................................9
REASONS FOR GRANTING THE PETITION .......15
I.
The Courts Of Appeals Are Irreconcilably
Divided On The Question Presented ................16
II.
The Question Presented Is Exceptionally
Important ..........................................................23
III. The Ninth Circuit’s Rule Is Wrong ..................27
CONCLUSION ..........................................................36
v
TABLE OF CONTENTS—Continued
Page
APPENDIX
Opinion of the United States Court of Appeals
for the Ninth Circuit, Columbia Falls
Aluminum Company, LLC v. Atlantic
Richfield Company, No. 21-36042, 2023
WL 1281669 (9th Cir. Jan. 31, 2023), ECF
No. 48-1 ...............................................................1a
Findings of Fact and Conclusions of Law of the
United States District Court for the
District of Montana, Columbia Falls
Aluminum Company, LLC v. Atlantic
Richfield Company, No. CV 18-131, 2021
WL 3769886 (D. Mont. Aug. 25, 2021), ECF
No. 148 ................................................................7a
Order Granting Motion to Amend Judgment in
Limited Part, Columbia Falls Aluminum
Company, LLC v. Atlantic Richfield
Company, No. CV 18-131 (D. Mont. Nov.
23, 2021), ECF No. 167 ...................................154a
Amended
Judgment,
Columbia
Falls
Aluminum Company, LLC v. Atlantic
Richfield Company, No. CV 18-131 (D.
Mont. Nov. 23, 2021), ECF No. 168 ...............157a
Order Denying Petition for Rehearing,
Columbia Falls Aluminum Company,
LLC v. Atlantic Richfield Company,
No. 21-36042 (9th Cir. Mar. 14, 2023), ECF
No. 52 ..............................................................158a
42 U.S.C. § 9607(a)................................................160a
vi
TABLE OF CONTENTS—Continued
Page
42 U.S.C. § 9613(b), (f) ..........................................162a
vii
TABLE OF AUTHORITIES
Page(s)
CASES
Albemarle Paper Co. v. Moody,
422 U.S. 405 (1975) ..............................................30
Alston v. NCAA (In re NCAA Athletic
Grant-in-Aid Cap Antitrust
Litigation),
958 F.3d 1239 (9th Cir. 2020), aff’d,
141 S. Ct. 2141 (2021)..........................................17
American Cyanamid Co. v. Capuano,
381 F.3d 6 (1st Cir. 2004) ..............................18, 20
AmeriPride Services Inc. v. Texas
Eastern Overseas Inc.,
782 F.3d 474 (9th Cir. 2015)................................18
Amphibious Partners, LLC v. Redman,
534 F.3d 1357 (10th Cir. 2008)............................31
ASARCO LLC v. Atlantic Richfield Co.,
LLC,
975 F.3d 859 (9th Cir. 2020), cert.
dismissed, 141 S. Ct. 2843 (2021) .................17, 18
Astoria Federal Savings & Loan
Association v. Solimino,
501 U.S. 104 (1991) ..............................................29
Atlantic Research Corp. v. United
States,
459 F.3d 827 (8th Cir. 2006), aff’d,
551 U.S. 128 (2007) ..............................................26
viii
TABLE OF AUTHORITIES—Continued
Page(s)
Atlantic Richfield Co. v. Christian,
140 S. Ct. 1335 (2020)..........................................25
Baptist Health v. Smith,
536 F.3d 869 (8th Cir. 2008)................................31
Bedford Affiliates v. Sills,
156 F.3d 416 (2d Cir. 1998),
abrogated on other grounds by
Cooper Industries, Inc. v. Aviall
Services, Inc., 543 U.S. 157 (2004) ......................20
Biden v. Texas,
142 S. Ct. 2528 (2022)..........................................30
BladeRoom Group Ltd. v. Emerson
Electric Co.,
20 F.4th 1231 (9th Cir. 2021) ..............................32
Boeing Co. v. Cascade Corp.,
207 F.3d 1177 (9th Cir. 2000)............ 16, 17, 19, 22
Braxton v. United States,
500 U.S. 344 (1991) ..............................................16
Burlington Northern & Santa Fe
Railway Co. v. United States,
556 U.S. 599 (2009) .................................... 2, 19, 20
Burton v. Burton,
21 P. 847 (Cal. 1889) ............................................29
California Public Employees’ Retirement
System v. ANZ Securities, Inc.,
582 U.S. 497 (2017) ..............................................29
ix
TABLE OF AUTHORITIES—Continued
Page(s)
Cooper Industries, Inc. v. Aviall Services,
Inc.,
543 U.S. 157 (2004) ..............................................24
Cooter & Gell v. Hartmarx Corp.,
496 U.S. 384 (1990) ..............................................32
Cozard v. Cozard,
92 P. 935 (Wash. 1907) ........................................29
Curran v. Georgia Loan & Trust Co.,
30 S.E. 886 (Ga. 1898) .........................................29
eBay Inc. v. MercExchange, LLC,
547 U.S. 388 (2006) ..............................................28
Elementis Chromium L.P. v. Coastal
States Petroleum Co.,
450 F.3d 607 (5th Cir. 2006)................................22
Encino Motorcars, LLC v. Navarro,
579 U.S. 211 (2016) ..............................................31
Evans v. Secretary, Department of
Corrections,
703 F.3d 1316 (11th Cir.), cert.
denied, 569 U.S. 1008 (2013) ...............................24
FCC v. Fox Television Stations, Inc.,
556 U.S. 502 (2009) ........................................30, 31
Florida Power Corp. v. Ocklawaha
Reclamation Farms,
112 So. 616 (Fla. 1927) ........................................29
x
TABLE OF AUTHORITIES—Continued
Page(s)
Goodrich Corp. v. Town of Middlebury,
311 F.3d 154 (2d Cir. 2002), cert.
denied, 539 U.S. 937 (2003) ............... 18, 19, 20, 28
Halo Electronics, Inc. v. Pulse
Electronics, Inc.,
579 U.S. 93 (2016) ................................................31
Jackson v. Los Lunas Community
Program,
880 F.3d 1176 (10th Cir. 2018)............................32
Kenemer v. Kenemer,
26 Ind. 330 (1866) ................................................29
Key Tronic Corp. v. United States,
511 U.S. 809 (1994) ..............................................23
Krupski v. Costa Crociere S.p.A.,
560 U.S. 538 (2010) ..............................................27
Lamps Plus, Inc. v. Varela,
139 S. Ct. 1407 (2019)..........................................27
Lockheed Martin Corp. v. United States,
833 F.3d 225 (D.C. Cir. 2016) .................. 19, 20, 21
Lonchar v. Thomas,
517 U.S. 314 (1996) ..............................................30
McLane Co. v. EEOC,
581 U.S. 72 (2017) ...................................... 4, 25, 31
Metal Jeans, Inc. v. Metal Sport, Inc.,
987 F.3d 1242 (9th Cir. 2021)..............................31
xi
TABLE OF AUTHORITIES—Continued
Page(s)
Minerva Surgical, Inc. v. Hologic, Inc.,
141 S. Ct. 2298 (2021)..........................................29
Monasky v. Taglieri,
140 S. Ct. 719 (2020)............................................25
National Cable & Telecommunications
Association v. Brand X Internet
Services,
545 U.S. 967 (2005) ..............................................31
NCR Corp. v. George A. Whiting Paper
Co.,
768 F.3d 682 (7th Cir. 2014)..........................19, 21
New York v. Solvent Chemical Co.,
453 F. App’x 42 (2d Cir. 2011) .............................21
Niagara Mohawk Power Corp. v.
Chevron USA, Inc.,
596 F.3d 112 (2d Cir. 2010) .................................26
Nikko Materials USA, Inc. v. NavCom
Defense Electronics, Inc.,
291 F. App’x 67 (9th Cir. 2008) ...........................17
Old Chief v. United States,
519 U.S. 172 (1997) ..............................................27
PCS Nitrogen Inc. v. Ashley II of
Charleston LLC,
714 F.3d 161 (4th Cir.) ........................................22
Pierce v. Underwood,
487 U.S. 552 (1988) .................................. 27, 28, 29
xii
TABLE OF AUTHORITIES—Continued
Page(s)
Redwing Carriers, Inc. v. Saraland
Apartments,
94 F.3d 1489 (11th Cir. 1996)..............................20
SEC v. American Trailer Rentals Co.,
379 U.S. 594 (1965) ..............................................24
Smiley v. Citibank (South Dakota),
N.A.,
517 U.S. 735 (1996) ..............................................32
Spectrum Sports, Inc. v. McQuillan,
506 U.S. 447 (1993) ..............................................27
Spinks v. Raison,
139 S.W. 811 (Ky. 1911) ......................................29
State v. Norrell,
53 P. 610 (Utah 1898) ..........................................30
Taylor v. Baldwin,
10 Barb. 626 (N.Y. Gen. Term 1851)...................29
TDY Holdings, LLC v. United States,
885 F.3d 1142 (9th Cir. 2018)..............................18
Territory of Guam v. United States,
141 S. Ct. 1608 (2021)................................ 2, 23, 24
Teva Pharmaceuticals USA, Inc. v.
Sandoz, Inc.,
574 U.S. 318 (2015) ..............................................25
Thompson v. Keohane,
516 U.S. 99 (1995) ................................................24
xiii
TABLE OF AUTHORITIES—Continued
Page(s)
Tosco Corp. v. Koch Industries, Inc.,
216 F.3d 886 (10th Cir. 2000)..............................19
Trinity Industries, Inc. v. Greenlease
Holding Co.,
903 F.3d 333 (3d Cir. 2018) ...........................19, 21
U.S. Bank National Association ex rel.
CWCapital Asset Management LLC
v. Village at Lakeridge, LLC,
138 S. Ct. 960 (2018)................ 3, 25, 28, 31, 32, 33
United States v. Alcan Aluminum
Corp.,
990 F.2d 711 (2d Cir. 1993) .................................17
United States v. Atlantic Research
Corp.,
551 U.S. 128 (2007) .......................... 2, 5, 17, 24, 28
United States v. Brown,
453 F.3d 1024 (8th Cir. 2006)..............................32
United States v. Christensen,
828 F.3d 763 (9th Cir. 2015), as
amended (July 8, 2016), cert. denied,
580 U.S. 1049 (2017) ............................................13
United States v. Consolidation Coal Co.,
345 F.3d 409 (6th Cir. 2003)................................19
United States v. Hercules, Inc.,
247 F.3d 706 (8th Cir.), cert. denied,
534 U.S. 1065 (2001) ............................................19
xiv
TABLE OF AUTHORITIES—Continued
Page(s)
United States v. Oakland Cannabis
Buyers’ Co-operative,
532 U.S. 483 (2001) ..............................................28
United States v. R.W. Meyer, Inc.,
932 F.2d 568 (6th Cir. 1991)................................20
United States v. Shell Oil Co.,
294 F.3d 1045 (9th Cir. 2002), cert.
denied, 537 U.S. 1147 (2003) ...............................17
United States EPA v. Sequa Corp. (In re
Bell Petroleum Services, Inc.),
3 F.3d 889 (5th Cir. 1993)....................................17
Von Duprin LLC v. Major Holdings,
LLC,
12 F.4th 751 (7th Cir. 2021) ................................21
Westport Insurance Co. v. California
Casualty Management Co.,
916 F.3d 769 (9th Cir. 2019)................................31
STATUTES
28 U.S.C. § 1254(1)......................................................1
42 U.S.C. § 9607(a)(1) .................................................5
42 U.S.C. § 9607(a)(2) .................................................5
42 U.S.C. § 9607(a)(3) .................................................5
42 U.S.C. § 9607(a)(4) .................................................5
42 U.S.C. § 9613(b)....................................................25
xv
TABLE OF AUTHORITIES—Continued
Page(s)
42 U.S.C. § 9613(f) ......................................................5
42 U.S.C. § 9613(f)(1) .............................. 2, 5, 6, 27, 33
42 U.S.C. § 9613(f)(3)(b) ..............................................5
OTHER AUTHORITIES
Benjamin N. Cardozo, The Nature of the
Judicial Process (1921) ........................................24
EPA, National Priorities List (NPL)
Sites – by State (Apr. 5, 2023),
https://www.epa.gov/superfund/
national-priorities-list-npl-sites-state ...................4
EPA, Superfund Accomplishments Report
FY 2021 (2022),
https://semspub.epa.gov/work/HQ/
100003048.pdf ........................................................4
EPA, Superfund Remedy Decisions
Estimated to Cost $50 Million or More
(Aug. 11, 2021), https://perma.cc/954F5QUF ......................................................................5
Henry J. Friendly, Indiscretion About
Discretion, 31 Emory L.J. 747 (1982) ..................32
Owen W. Gallogly, Equity’s
Constitutional Source, 132 Yale L.J.
1213 (2023) ...........................................................29
H.R. Rep. No. 99-253, pt. 1 (1985) .............. 5, 6, 23, 26
xvi
TABLE OF AUTHORITIES—Continued
Page(s)
Justin R. Pidot & Dale Ratliff, The
Common Law of Liable Party CERCLA
Claims, 70 Stan. L. Rev. 191 (2018)....................23
Restatement (Second) of Torts (May 2023,
Westlaw)...............................................................28
Sup. Ct. R. 10(a) ........................................................23
Tod I. Zuckerman, et al., Environmental
Liability Allocation: Law & Practice
(Dec. 2022, Westlaw) ...........................................21
1
PETITION FOR A WRIT OF CERTIORARI
Petitioner Columbia Falls Aluminum Co., LLC
(CFAC), respectfully petitions this Court for a writ of
certiorari to review the judgment of the United States
Court of Appeals for the Ninth Circuit in this case.
OPINIONS BELOW
The opinion of the court of appeals (App. 1a-6a) is
available at 2023 WL 1281669. The court’s order
denying rehearing en banc (App. 158a-59a) is not
reported. The district court’s findings of fact and
conclusions of law (App. 7a-153a) are available at
2021 WL 3769886. The district court’s order granting
in part the motion to amend the judgment (App. 154a56a) is not reported.
JURISDICTION
The court of appeals entered its judgment on
January 31, 2023, and denied rehearing on March 14,
2023. This Court has jurisdiction under 28 U.S.C.
§ 1254(1).
STATUTORY PROVISIONS INVOLVED
Pertinent statutory provisions are reproduced at
App. 160a-63a.
2
INTRODUCTION
This petition presents a deep and acknowledged
circuit conflict over the standard of review for an
equitable allocation of costs under one of the nation’s
most important environmental statutes.
CERCLA addresses “the serious environmental
and health risks posed by industrial pollution,”
Burlington N. & Santa Fe Ry. Co. v. United States,
556 U.S. 599, 602 (2009), and the “crucial question” of
“[w]ho pays” for remediation, Territory of Guam v.
United States, 141 S. Ct. 1608, 1611 (2021). At the
heart of CERCLA is a contribution regime that
ensures that all parties responsible for pollution at a
Superfund site pay an “equitable” share of
remediation costs. United States v. Atlantic Research
Corp., 551 U.S. 128, 140 (2007); 42 U.S.C. § 9613(f)(1).
But the courts of appeals are intractably divided over
the role of an appellate court in reviewing a district
court’s equitable allocation of cleanup costs. While
seven circuits hold that a district court’s decisions are
subject to the abuse-of-discretion standard that
typically attends a lower court’s discretionary
balancing of equitable factors, three circuits—
including the Ninth Circuit below—hold that such
determinations are subject only to the clear-error
standard normally reserved for factual findings.
That acknowledged conflict warrants this Court’s
review. Applying the clear-error standard to an
equitable balancing decision deprives parties of
meaningful appellate review of an important
determination under CERCLA. Clear-error review in
this context has no basis in Section 113(f)(1)’s text, the
history of appellate practice, or common sense. As
this Court has explained, clear-error review puts “a
3
serious thumb on the scale” in favor of the district
court’s finding.
U.S. Bank Nat’l Ass’n ex rel.
CWCapital Asset Mgmt. LLC v. Village at Lakeridge,
LLC, 138 S. Ct. 960, 966 (2018). Moreover, applying
the
clear-error
standard
to
an
equitable
determination that requires a balancing of factors is
like putting a square peg in a round hole. And it not
only makes no sense, but has real consequences for
the administration of CERCLA. The clear-error
standard insulates allocations that are inconsistent,
irrational, and unexplained, so long as some evidence
supports the allocation. Not surprisingly, then,
equitable allocations are virtually always rubber
stamped under the clear-error standard.
The decision below starkly illustrates how the
clear-error standard can lead to perverse results in
this context. The district court found that Atlantic
Richfield Co. (ARCO) was primarily responsible for
groundwater contamination at the CERCLA site at
issue, and made nearly twice the profits at the Site as
CFAC. Yet the court allocated 65% of CERCLA
response costs to CFAC—and only 35% to ARCO—
reasoning that the parties’ Acquisition Agreement
shifted responsibility for these costs to CFAC. That
ruling not only defied the court’s finding that ARCO
was primarily responsible for contamination at the
Site, but rested on a fatal inconsistency. Earlier in its
opinion, the court expressly found that “neither the
language of the Agreement nor the . . . extrinsic
evidence” showed that the Agreement shifted
CERCLA liability. App. 43a. The court never
acknowledged, much less explained, this flagrant
contradiction. The court also failed to explain other
critical leaps in its decision that defied its own
findings. Yet, reviewing the district court’s “equitable
4
allocation” only for “clear error,” the Ninth Circuit
perfunctorily affirmed. App. 1a-6a.
This Court regularly intervenes when circuits
divide on the appropriate standard of review. See,
e.g., McLane Co. v. EEOC, 581 U.S. 72, 79 (2017).
Such intervention is needed here. The Ninth Circuit
is home to hundreds of CERCLA sites, more than all
but one other circuit. See EPA, National Priorities
List (NPL) Sites – by State, (Apr. 5, 2023),
https://www.epa.gov/superfund/national-prioritieslist-npl-sites-state.
The circuit with the most
CERCLA sites (the Third, id.) applies the abuse-ofdiscretion standard. The Ninth Circuit’s unsupported
and unworkable clear-error standard for allocation
determinations jeopardizes the proper functioning of
CERCLA’s contribution mechanism, on which billions
of dollars turn. And there is no sensible reason for the
scope of judicial review of cost allocation awards
under CERCLA to vary based simply on geography.
This Court’s intervention is warranted.
STATEMENT OF THE CASE
A. Statutory Background
CERCLA establishes a comprehensive framework
for cleaning up the Nation’s hazardous waste sites.
Cleaning up such Superfund sites is expensive.
Private and public parties have paid or committed to
pay over $48 billion in cleanup costs since CERCLA’s
inception.1 And between October 2017 and July 2021
alone, EPA ordered a final remedy expected to cost
over $50 million at 32 different sites across the
1
EPA, Superfund Accomplishments Report FY 2021 at 27
(2022), https://semspub.epa.gov/work/HQ/100003048.pdf.
5
country.2 CERCLA seeks to ensure that liability for
these costly cleanups is fairly allocated among all
responsible parties.
Section 107(a) of CERCLA “defines four categories
of” potentially responsible parties (PRPs), Atlantic
Research, 551 U.S. at 131-32 (citing 42 U.S.C.
§ 9607(a)(1)-(4)), including a site’s past or present
owners or operators, 42 U.S.C. § 9607(a)(1)-(2). In
1986, Congress added an express cause of action for
contribution in CERCLA Section 113(f), 42 U.S.C.
§ 9613(f). Under Section 113(f)(1), “[a]ny person may
seek contribution from any other person who is liable
or potentially liable under [Section 107(a)], during or
following any civil action under [Section 106] or
[Section 107(a)].”
Id. § 9613(f)(1); see also id.
§ 9613(f)(3)(B) (authorizing contribution claims
following settlement with a federal or state
government).
Section 113(f)(1) thus established a PRP’s “right to
collect from others responsible for the same tort after
the [PRP] has paid more than his or her proportionate
share.” Atlantic Research, 551 U.S. at 138 (citation
omitted). This provision was meant to “encourage
private party settlements and cleanups.” H.R. Rep.
No. 99-253, pt. 1 at 80 (1985). By “assur[ing] [PRPs]
that they can seek contribution from other[]” PRPs,
Section 113(f) sought to make “[p]rivate parties . . .
more willing to assume the financial responsibility for
some or all of [a] cleanup.” Id.
Section 113(f)(1) provides that, “[i]n resolving
contribution claims, the court may allocate response
2
EPA, Superfund Remedy Decisions Estimated to Cost
$50 Million or More (Aug. 11, 2021), https://perma.cc/954F5QUF.
6
costs among liable parties using such equitable
factors as the court determines are appropriate.” 42
U.S.C. § 9613(f)(1). Congress thus authorized “courts
. . . to resolve such claims on a case-by-case basis,
taking
into
account
relevant
equitable
considerations.” H.R. Rep. No. 99-253, pt. 1 at 80.
B. Factual Background
1. This case concerns the allocation of
potentially more than $50 million of CERCLA
liability for contamination over several decades at an
aluminum smelting facility in Columbia Falls,
Montana. ARCO owned and operated the Site from
1955 to 1985. During that period, ARCO produced
over 3.2 million tons of aluminum and generated $565
million in profits. App. 19a, 147a. This, in turn,
generated hazardous byproducts, including cyanide,
fluoride, and sodium.
Id. at 44a-45a.
These
contaminants seeped into the paste lining the steel
pots in which aluminum was heated, eventually
causing the pots’ lining to swell and fail. Id.
Contaminated “spent potliner” was then removed and
discarded. Id. From 1960 to 1980, ARCO disposed of
129,000 to 135,000 tons of toxic spent potliner in
unlined landfills, including 61,800 tons in the West
Landfill. Id. at 44a-45a, 57a.
As the district court found (and ARCO did not
contest on appeal), ARCO’s spent potliner is the
primary cause of groundwater contamination at the
Site. Id. at 138a-39a. Rainwater at the Site passed
through unlined landfills unimpeded, picking up
cyanide and fluoride present in the spent potliner and
depositing those contaminants into the Site’s
groundwater. Id. at 45a, 57a. Illustrating this
phenomenon, the area immediately downhill from the
7
unlined West Landfill not surprisingly displays the
highest
concentration
of
contaminants
in
groundwater at the Site. Id. at 57a-58a, 72a-75a.
3-ER-496.
2. By 1984, ARCO’s aluminum production
operation was “los[ing] money,” App. 147a-48a, and
ARCO had begun to explore selling or liquidating the
Site, id. at 32a. After struggling to find a buyer,
ARCO sold the Site to CFAC for $1 in 1985—a
transaction that saved ARCO over $7 million in
liquidation costs. Id.
The resulting Acquisition Agreement contained
cross-indemnification provisions. ARCO agreed to
indemnify CFAC “from and against . . . [a]ll damages
. . . caused by or arising out of obligations or liabilities
relating to the Smelter Business resulting from
events or conditions in existence prior to the Closing
Date [September 17, 1985].” Id. at 25a, 127a. CFAC
in turn agreed to indemnify ARCO “from and against
8
. . . [a]ll damages . . . arising out of . . . obligations or
liabilities, contingent or otherwise relating to the
operation of the Smelter Business after the Closing
Date, other than obligations or liabilities as to which
Seller is obligated to indemnify Buyer.” Id. at 25a.
ARCO was well aware of CERCLA at the time it
entered into the Agreement. By 1985, ARCO was “the
subject of several CERCLA lawsuits” and “deemed” a
PRP “at 24 sites by EPA and/or individual states.” Id.
at 43a. But, significantly, neither indemnification
provision referred to liability under CERCLA.
3. From 1985 to 2008, CFAC produced over 2.8
million tons of aluminum at the Site and gained $279
million in profits—about half of ARCO’s profits at the
Site. Id. at 20a, 147a-49a. But unlike ARCO, CFAC
never placed spent potliner in unlined landfills.
Instead, CFAC disposed of spent potliner in a lined
landfill from 1985 to 1990 and shipped spent potliner
offsite from 1990 onward, which seriously reduced
contamination at the Site. Id. at 45a.
Indeed, compared to ARCO’s disposal of spent
potliner, CFAC’s contribution to contamination was a
drop in the bucket. It was undisputed at trial that
ARCO contributed more than 50 times the amount of
cyanide and fluoride into the Site’s groundwater that
CFAC did. See id. at 76a-77a. Like ARCO before it,
CFAC occasionally disposed of leachate containing
trace amounts of contaminants in the Wet Scrubber
Sludge Pond, a landfill containing an inert substance.
Id. at 58a-60a. CFAC also deposited pot diggings—an
aluminum production byproduct—into the Wet
Scrubber Sludge Pond; but, upon learning that they
contained hazardous material, CFAC promptly
removed the pot diggings under the supervision of
state environmental authorities. Id. at 60a-62a.
9
CFAC discontinued aluminum production in 2009
and announced the facility’s permanent closure in
2015. Id. at 20a-22a. The same year, EPA invited
ARCO and CFAC, as PRPs for the Site, to “voluntarily
negotiate a consent order” providing for the Site’s
remediation. Id. at 82a-84a (citation omitted). ARCO
did not dispute that it was a PRP but simply “declined
to participate” in settlement talks. Id. at 83a-84a.
Rather than cooperate with environmental
authorities, “ARCO has fought tooth-and-nail” to
avoid paying cleanup costs. Id. at 143a-44a.
CFAC, by contrast, cooperated. It negotiated an
Administrative Order on Consent with EPA that
resolved CFAC’s liability for the costs of a Remedial
Investigation and Feasibility Study for the Site, as
well as future response costs associated with
implementing the agreement. Id. at 83a-84a. EPA
has not yet selected a final remedy for the Site.
C. Proceedings Below
Because ARCO had refused to assume any
responsibility for its contamination of the Site, CFAC
sued ARCO in 2018 for contribution under Section
113(f)(1) and cost recovery under Section 107(a).
After extensive discovery, the case proceeded to a
bench trial on the amount of recoverable costs CFAC
had incurred and the proper allocation of past and
future cleanup costs between ARCO and CFAC.
1. The district court found that ARCO was
“responsible for the lion’s share of the groundwater
contamination” that required remediation, App. 139a;
ARCO had earned more than twice the profits as
CFAC at the Site (almost $300 million more), id. at
147a, 149a; and, whereas CFAC had cooperated with
EPA throughout the remedial process, ARCO had
10
declined to cooperate with authorities, id. at 143a44a. Nevertheless, the district court ultimately made
an equitable allocation that assigned 65%
responsibility for past and future cleanup costs at the
Site to CFAC and just 35% to ARCO. Id. at 150a.
a. At the outset, the district court addressed
ARCO’s argument that the Acquisition Agreement
itself made CFAC responsible for the costs of ARCO’s
own environmental harm. After carefully reviewing
the text of the Agreement and extrinsic evidence, the
district court categorically rejected this argument,
holding that “neither the language of the Agreement
nor the parties’ intent as distilled from extrinsic
evidence shows that CFAC agreed to forego a
CERCLA claim related to environmental conditions.”
Id. at 43a; see also id. at 30a-31a. That ruling was the
crux of the initial part of the court’s analysis.
b. After determining which costs already
incurred by CFAC were recoverable, the district court
engaged in an equitable allocation under Section
113(f)(1). Id. at 129a-30a. In doing so, the court chose
to apply the so-called “Gore factors,” a common
framework for CERCLA contribution allocations that
considers:
(1) the ability of the parties to
demonstrate that their contribution to a
discharge, release or disposal of a
hazardous waste can be distinguished;
(2) the amount of the hazardous waste
involved;
(3) the degree of toxicity
hazardous waste involved;
of
the
(4) the degree of involvement by the
11
parties
in
the
generation,
transportation, treatment, storage, or
disposal of the hazardous waste;
(5) the degree of care exercised by the
parties with respect to the hazardous
waste concerned, taking into account the
characteristics of such hazardous waste;
and
(6) the degree of cooperation by the
parties with the Federal, State or local
officials to prevent any harm to the
public health or the environment.
See id. at 130a.
Taking the first four Gore factors together, the
district court assessed “the amount and nature of the
hazardous waste disposed of by the parties.” Id. at
138a. The court initially found that ARCO’s disposal
of spent potliner was the “primary driver” of
groundwater contamination. Id. at 138a-40a. But the
court nevertheless concluded that these factors did
not “weigh in favor of either party” because a proposed
final remedial measure—a slurry wall that would
divert the flow of clean groundwater around
contaminated areas—would encompass both the West
Landfill contaminated by ARCO and the Wet
Scrubber Sludge Pond contaminated by both parties.
Id. The court did not explain, however, how a
remedial measure addressing contamination “linked
to” a part of the Site used by both parties could
possibly cancel out ARCO’s responsibility for the
“lion’s share of the groundwater contamination.” Id.
at 139a-40a.
The lack of an explanation was
particularly jarring because the court’s reasoning on
this point was irreconcilable with its other findings:
12
ARCO’s disposal of spent potliner in the West Landfill
is the reason a remedy for groundwater
contamination is necessary at all. See id. at 80a. And
such a remedy needed to address the Wet Scrubber
Sludge Pond because the contaminated groundwater
beneath it had flowed downhill from the West
Landfill. See supra at 6-7; App. 73a-75a.
The district court held that the fifth and sixth Gore
factors balanced one another out. App. 140a-44a.
c. Finally, the district court considered two
additional factors. First, it revisited the parties’
contractual intent, which it now described as the
“most important” factor governing the allocation of
costs. Id. at 144a. Even though the court had already
held, in no uncertain terms, that the parties did not
intend the Acquisition Agreement to shift CERCLA
costs, the district court inexplicably reversed course
in its allocation decision and invoked the contract to
shift costs to CFAC on the premise that the
Agreement covered “the very environmental
liabilities that are the subject of this case.” Id. at
145a. The court did not acknowledge, much less
attempt to explain, this flat contradiction.
Next, the district court considered the parties’
relative economic benefits. The court found that
ARCO’s aluminum production profits at the Site
doubled CFAC’s. Id. at 147a-49a. And the court
rejected ARCO’s argument that its higher level of
capital investment than CFAC favored allocating
more costs to CFAC, noting that “the facility lacked
value as a going concern.” Id. at 148a. Nevertheless,
the court concluded that this factor was “neutral”
because CFAC bought property for $1 in 1985 that
would be worth an estimated $2.25 million after final
remediation. Id. at 149a-50a. The court did not
13
acknowledge that at least $50 million in spending
would be necessary before the Site reached a $2.25
million value. See id. at 89a. Nor did the court
explain how a potential economic benefit of $2.25
million could possibly cancel out ARCO’s $280 million
profits advantage.
Based on these allocation factors, the district court
deemed an allocation of 65% of response costs to
CFAC and 35% to ARCO a “fair and equitable”
result—again without any explanation as to how it
reached that relative distribution. Id. at 150a.
2. A panel of the Ninth Circuit affirmed.
a. In accordance with circuit precedent, the
panel reviewed the district court’s 65-35 equitable
allocation in ARCO’s favor only “for clear error.” App.
2a. The panel explained that “‘[a] finding of fact is
clearly erroneous only where it is “(1) illogical,
(2) implausible, or (3) without support in inferences
that may be drawn from the facts in the record.”’” Id.
(quoting United States v. Christensen, 828 F.3d 763,
779 (9th Cir. 2015), as amended (July 8, 2016), cert.
denied, 580 U.S. 1049 (2017)). And, the court noted,
“[i]f there are two reasonable interpretations” of the
underlying “evidence,” then “‘the factfinder’s choice
between them cannot be clearly erroneous.’” Id.
(citation omitted).
b. Applying that standard, the panel overlooked
the district court’s failure to acknowledge or explain
its contradictory contractual rulings. According to the
panel, the district court’s initial ruling that the
contract did not shift CERCLA liabilities “rested
solely” on the district court’s finding that the
Agreement’s text and extrinsic evidence were not
“sufficiently clear” to shift CERCLA liability under
14
Montana law. Id. at 3a (emphasis added). But this
reasoning is absent from the district court’s decision.
The district court did not find that the parties’ intent
as to CERCLA liability was not clear enough; rather,
it held that “neither the language of the Agreement
nor the parties’ intent as distilled from extrinsic
evidence shows that CFAC agreed to forego a
CERCLA claim” or shift CERCLA liability—period.
Id. at 43a. The panel also declined to grapple with the
district court’s about-face from saying that the
Agreement evinced no intent to shift CERCLA
liability to saying that it was the “most important”
factor for doing just that. Id. at 144a.
c. Next, the panel held that the district court did
not clearly err in assessing “the amount and nature of
hazardous waste” disposed of by the parties. Id. at
4a-5a.
Although ARCO was undisputedly the
“primary contributor” to contamination at the Site, id.
at 139a, the panel found no clear error in the district
court’s determination that this factor was “neutral”
because a slurry wall “was occasioned by both”
ARCO’s decades of spent potliner disposal and
CFAC’s handful of disposals of leachate and pot
diggings in the Wet Scrubber Sludge Pond, id. at 5a.
The panel acknowledged that the district court’s
explanation on this crucial point was lacking,
observing that, “[i]deally, the district court would
have explained more fully each party’s relative
contribution to the need for this joint remedial
measure.” Id. But instead of faulting the district
court for inadequately explaining this key point, the
panel simply held it could not “say based on the
evidence . . . that the district court clearly erred.” Id.
d. Finally, the panel upheld the district court’s
economic-benefit analysis. Id. at 6a. In doing so, the
15
panel emphasized ARCO’s expenditures on the Site
and the $1 purchase price as “other forms of economic
benefit” CFAC experienced. Id. But the panel did not
acknowledge, much less address, a blatant flaw in the
district court’s reasoning—its lack of explanation as
to how these considerations could possibly offset
ARCO’s $280 million profits advantage or be
reconciled with the court’s finding that CFAC
purchased a practically worthless Site. Instead,
under clear-error review, the panel simply stated that
“the district court did not err in concluding that the
totality of the economic picture was neutral.” Id.
3. CFAC petitioned for rehearing en banc,
arguing that the Ninth Circuit’s clear-error standard
for CERCLA contribution allocations conflicts with
other circuits’ abuse-of-discretion standard, and that
the
district
court’s
internally
inconsistent,
unexplained, and irrational decision could not stand
under the abuse-of-discretion standard. Reh’g Pet. 813, ECF No. 49; see also CA9 Appellant Br. 30 n.6,
ECF No. 20 (noting circuit split). The Ninth Circuit
denied rehearing. App. 158-59a.
REASONS FOR GRANTING THE PETITION
The Ninth Circuit’s decision implicates an
acknowledged circuit conflict on a recurring question
of undeniable importance to federal environmental
law. That conflict interferes with the administration
of CERCLA, and impacts the allocation of billions of
dollars of response costs among responsible parties.
The Ninth Circuit’s clear-error standard cannot be
reconciled with Section 113(f)(1)’s text, historical
practice, or common sense, all of which require review
for abuse of discretion. And this case is an ideal
vehicle to resolve this conflict. The Ninth Circuit
16
repeatedly invoked the clear-error standard to justify
affirmance of an inconsistent, irrational, and
unexplained allocation that could not withstand
genuine abuse-of-discretion review. The Court should
grant certiorari and resolve the entrenched division
in the circuits on this important question.
I. The Courts Of Appeals Are Irreconcilably
Divided On The Question Presented
An entrenched circuit split exists over the proper
standard of review for a district court’s ultimate
equitable allocation of contribution liability pursuant
to Section 113(f)(1). As this Court has noted many
times, its “primar[y]” responsibility is resolving
circuit conflicts “concerning the meaning of provisions
of federal law.” Braxton v. United States, 500 U.S.
344, 347-48 (1991). The Ninth Circuit’s adherence to
a clear-error standard in this case—over CFAC’s
petition for rehearing asking the Ninth Circuit to
reconsider its position on this issue—reinforces just
such a conflict and demands this Court’s intervention.
1. The decision below reviewed the district
court’s ultimate “equitable allocation . . . for clear
error.” App. 2a. In so doing, the panel followed the
standard adopted in Boeing Co. v. Cascade Corp., 207
F.3d 1177, 1187 (9th Cir. 2000).
There, in a
contribution action between two companies that
contaminated the same aquifer, the Ninth Circuit
observed that Section 113(f)(1)’s “language gives
district courts discretion to decide what factors ought
to be considered, as well as the duty to allocate costs
according to those factors.” Id. But the court
translated this statutory text into two separate
standards of review: (1) abuse of discretion for the
“select[ion]” of factors and (2) clear error for “the
17
allocation according to those factors.” Id.3 The court
did not ground the latter standard in the law of
contribution or equity practice. Rather, Boeing relied
on a decision holding that the “actual apportionment
of damages is a question of fact” in a cost recovery
action under a different provision—Section 107(a).
Id. at 1187 n.33 (citing U.S. EPA v. Sequa Corp. (In re
Bell Petroleum Servs., Inc.), 3 F.3d 889, 896 (5th Cir.
1993)).4
Clear-error review is sharply limited. As the
Ninth Circuit has itself observed, a finding is not
“clearly erroneous unless it ‘strike[s] [the panel] as
wrong with the force of a five-week-old,
unrefrigerated dead fish.’” Alston v. NCAA (In re
NCAA Athletic Grant-in-Aid Cap Antitrust Litig.),
958 F.3d 1239, 1253 (9th Cir. 2020), aff’d, 141 S. Ct.
2141 (2021) (first alteration in original) (citation
omitted). Under this standard, the Ninth Circuit lets
allocations stand even though a district court’s
“discussion of the nexus between its factual findings
3
The Ninth Circuit has routinely applied this standard.
See, e.g., United States v. Shell Oil Co., 294 F.3d 1045, 1060 (9th
Cir. 2002), cert. denied, 537 U.S. 1147 (2003); Nikko Materials
USA, Inc. v. NavCom Def. Elecs., Inc., 291 F. App’x 67, 70 (9th
Cir. 2008); ASARCO LLC v. Atlantic Richfield Co., LLC, 975
F.3d 859, 868 (9th Cir. 2020), cert. dismissed, 141 S. Ct. 2843
(2021).
4
Cost-recovery actions allow a PRP to seek costs it “has
itself incurred” to clean up a site. Atlantic Research, 551 U.S. at
139. Apportionment is a defense to joint and several liability for
cost-recovery damages, and requires proof that a harm is
“capable of division upon a reasonable and rational basis.” In re
Bell Petroleum, 3 F.3d at 895 (citation omitted). Courts view
apportionment as “an intensely factual determination.” United
States v. Alcan Aluminum Corp., 990 F.2d 711, 722 (2d Cir.
1993).
18
and the [selected equitable] factors” lacks clarity,
ASARCO LLC v. Atlantic Richfield Co., 975 F.3d 859,
869 (9th Cir. 2020) (rejecting ARCO’s challenge to
adequacy of district court’s explanation of allocation),
or, as here, “[i]deally . . . would have [been] explained
more fully,” App. 5a. Rather than looking for such
lapses, the Ninth Circuit’s standard emphasizes
quantity of factual findings. ASARCO, 975 F.3d at
869 (noting that district court’s “ninety-five page
order” included “extensive findings” about a site).
And when a district court identifies some evidence
implicating a PRP, the Ninth Circuit’s clear-error
standard makes any allocation of liability to that PRP
virtually unassailable on appeal.
Underscoring the limited nature of clear-error
review, the Ninth Circuit has apparently never
reversed a district court’s equitable allocation based
on inadequate consideration of a selected factor.5
2. In direct conflict with the Ninth Circuit, seven
other circuits review for abuse of discretion both a
district court’s selection of equitable factors and its
ultimate allocation of contribution liability under
Section 113(f)(1).
American Cyanamid Co. v.
Capuano, 381 F.3d 6, 19 (1st Cir. 2004); Goodrich
5
Instead, the Ninth Circuit has only reversed an
allocation under Section 113(f)(1) when reviewing the selection
of equitable factors for abuse of discretion—underscoring the
importance of the distinction between the two standards of
review. TDY Holdings, LLC v. United States, 885 F.3d 1142,
1149 (9th Cir. 2018) (reversing allocation of 100% of liability to
one party where district court misinterpreted precedent and
ignored relevant factors); AmeriPride Servs. Inc. v. Texas E.
Overseas Inc., 782 F.3d 474, 489 & n.9 (9th Cir. 2015) (reversing
where district court did not “explain the equitable factors it
considered” or how it arrived at allocation).
19
Corp. v. Town of Middlebury, 311 F.3d 154, 168-69,
171 (2d Cir. 2002), cert. denied, 539 U.S. 937 (2003);
Trinity Indus., Inc. v. Greenlease Holding Co., 903
F.3d 333, 356 (3d Cir. 2018); United States v.
Consolidation Coal Co., 345 F.3d 409, 412-13, 415
(6th Cir. 2003); NCR Corp. v. George A. Whiting Paper
Co., 768 F.3d 682, 700-01 (7th Cir. 2014); Tosco Corp.
v. Koch Indus., Inc., 216 F.3d 886, 894-95 (10th Cir.
2000); Lockheed Martin Corp. v. United States, 833
F.3d 225, 234-35 (D.C. Cir. 2016).
For example, in Goodrich, the Second Circuit
rejected a PRP’s argument that clear error
constituted the proper standard of review for a
CERCLA contribution allocation. 311 F.3d at 169-70.
Instead of viewing “the allocation of response costs
under § 113(f) [a]s a question of fact,” the Second
Circuit explained that “it is an equitable
determination based on the district court’s
discretionary selection of the appropriate equitable
factors in a given case.” Id. at 170. In so holding, the
Second Circuit expressly rejected the Ninth Circuit’s
decision in Boeing adopting the clear-error standard
as “unpersuasive” because it relied on the
“inapposite” standard for apportionment of damages
in a cost recovery action. Id. at 170 n.16 (citing
Boeing, 207 F.3d at 1187-88 & nn.33, 39).
Indeed, as the Second Circuit has explained, id.,
Boeing’s uncritical use of the apportionment standard
to review equitable allocations conflates “conceptually
distinct” inquiries, United States v. Hercules, Inc., 247
F.3d 706, 718 (8th Cir.), cert. denied, 534 U.S. 1065
(2001). Apportionment “looks to whether defendants
may avoid joint and several liability by establishing a
fixed amount of damage for which they are liable.”
Burlington N. & Santa Fe Ry. Co. v. United States,
20
556 U.S. 599, 615 n.9 (2009) (citation omitted).
“Equitable considerations play no role in [that]
analysis . . . .” Id. By contrast, equitable allocations
under Section 113(f) “allow . . . PRPs to recover from
each other on the basis of equitable considerations,”
id., and “[d]ivisibility of the harm . . . is not a
prerequisite to making [an] allocation,” Redwing
Carriers, Inc. v. Saraland Apartments, 94 F.3d 1489,
1514 (11th Cir. 1996). Thus, as the Second Circuit
has held, apportionment is “‘an intensely factual
determination’” that should be reviewed for clear
error, and allocation is an “equitable determination”
that should be reviewed for abuse of discretion.
Goodrich, 311 F.3d at 170 & n.16 (citation omitted).
Unlike the Ninth Circuit, the Second Circuit—and
the other courts that apply abuse of discretion—
derive the standard of review from Section 113(f)’s
text and its equitable underpinnings. See, e.g.,
Bedford Affiliates v. Sills, 156 F.3d 416, 429 (2d Cir.
1998), abrogated on other grounds by Cooper Indus.,
Inc. v. Aviall Servs., Inc., 543 U.S. 157 (2004). These
circuits have explained that Section 113(f)(1)’s
“expansive language” invests a district court with
“broad discretion to balance the equities in the
interests of justice.” Id.; see also American Cyanamid,
381 F.3d at 19 (similar). And courts have recognized
that Section 113(f)(1) “invoke[s] the tradition of equity
under which the court must construct a flexible
decree.” United States v. R.W. Meyer, Inc., 932 F.2d
568, 572-73 (6th Cir. 1991); see also Lockheed Martin,
833 F.3d at 234 (similar). Because Section 113(f)(1)
confers equitable discretion, these courts review
contribution allocations for abuse of discretion.
Accordingly, as commentators have recognized, these
circuits reject the Ninth Circuit’s clear-error
21
standard. See Tod I. Zuckerman, et al., Env’t Liab.
Allocation: L. & Prac. §§ 3:199-200 (Dec. 2022,
Westlaw).
Abuse-of-discretion review still affords significant
deference to the district court’s allocation. See, e.g.,
Lockheed Martin, 833 F.3d at 234-35. But it demands
not only evidentiary support for a cost allocation, but
a cogent explanation as well. Under an abuse-ofdiscretion standard, an allocation cannot stand where
“the reasons the court gave” for an allocation “do not
appear to be consistent with its stated rationale” or it
does “not explain why [a particular] fact was
important” for purposes of cost allocation. NCR, 768
F.3d at 703. And, importantly, even where a district
court writes “an admirably thorough opinion,”
Trinity, 903 F.3d at 347, a court reviewing for abuse
of discretion will “‘not simply “rubber stamp” a
district court’s equitable allocation,’” id. at 360-61
(quoting Lockheed Martin, 833 F.3d at 234). Instead,
when a district court’s allocation violates principles of
reasoned decision-making, these circuits reverse for
abuse of discretion6—a marked contrast from the
6
See, e.g., New York v. Solvent Chem. Co., 453 F. App’x 42,
49 (2d Cir. 2011) (vacating allocation where district court’s
“finding that the remedy was driven primarily by” chemical
produced by both PRPs “remove[d] the foundation” for allocation
of 94% of costs to one PRP and court offered insufficient
explanation); Trinity, 903 F.3d at 356, 361-62 (vacating
allocation where district court found lack of contractual intent to
allocate CERCLA liability but then awarded equitable deduction
based on contract); NCR, 768 F.3d at 701-03 (vacating allocation
where court did not explain prioritization of parties’ knowledge
as allocation factor or assessment of record evidence); Von
Duprin LLC v. Major Holdings, LLC, 12 F.4th 751, 768 (7th Cir.
2021) (vacating allocation where district court “mentioned
22
Ninth Circuit’s near universal affirmance rate in
applying its clear-error standard. Supra at 18.
3. Siding with the Ninth Circuit, two other
circuits part with the majority view and review
ultimate allocation determinations only for clear
error. But neither circuit has provided a reasoned
basis for adopting a clear-error standard.
Relying on Ninth Circuit precedent, the Fourth
Circuit reviews “a district court’s choice of factors for
abuse of discretion, and its ultimate allocations of
liability for clear error” in CERCLA contribution
claims. PCS Nitrogen Inc. v. Ashley II of Charleston
LLC, 714 F.3d 161, 186 (4th Cir.) (citing Boeing, 207
F.3d at 1187), cert. denied, 571 U.S. 990 (2013). In
PCS Nitrogen, the Fourth Circuit recognized that
Section 113(f)(1)’s “plain language grants a court
significant discretion to choose which factors to
consider in determining equitable allocation of
liability.” Id. Nevertheless, the court restricted its
bottom-line inquiry to whether “the [district] court
clearly erred by allocating too much liability” to
certain parties. Id.
The Fifth Circuit does the same. Where a party
challenges a percentage allocation of response costs,
the Fifth Circuit treats that determination as a
“finding[] of fact” reviewable “only for clear error.”
Elementis Chromium L.P. v. Coastal States Petroleum
Co., 450 F.3d 607, 613 (5th Cir. 2006).
Unsurprisingly, neither the Fourth or Fifth Circuits
appear to have ever reversed a district court’s decision
on the ground that its assessment of a selected factor
was irrational. These circuits’ adoption of the clearequitable factors that it considered” without explaining how it
allocated costs using those factors).
23
error standard deepens the divide and underscores
the need for this Court’s guidance.
This entrenched, 7-3 circuit conflict on the
standard of review for equitable allocations under
CERCLA warrants certiorari. Sup. Ct. R. 10(a).
II. The Question Presented Is Exceptionally
Important
The question presented is also frequently
recurring and tremendously important. As Congress
and this Court have recognized, Section 113(f)’s
contribution provision is critical to “encourag[ing]
private party settlements and cleanups.” H.R. Rep.
No. 99-253, pt. 1, at 80 (1985); Key Tronic Corp. v.
United States, 511 U.S. 809, 819 n.13 (1994)
(“CERCLA is designed to encourage private parties to
assume the financial responsibility of cleanup by
allowing them to seek recovery from others.”).
Allocations of CERCLA contribution liability affect
billions of dollars of remediation costs at sites across
the country. This case cleanly presents the question
regarding the appropriate standard for reviewing
such allocations, providing this Court with an
excellent vehicle to resolve the circuit conflict.
1. Section 113(f) is central to resolving “the
crucial question in a remedial action” under
CERCLA: “Who pays?” Territory of Guam v. United
States, 141 S. Ct. 1608, 1611 (2021). At a single
Superfund site, the answer can shift tens or hundreds
of millions of dollars of response costs from one party
to another. See Justin R. Pidot & Dale Ratliff, The
Common Law of Liable Party CERCLA Claims, 70
Stan. L. Rev. 191, 200 & nn.37, 40-41 (2018). These
stakes alone make proper review of allocations under
Section 113(f)(1) undeniably important.
24
In light of contribution’s crucial role in CERCLA’s
statutory scheme, this Court has repeatedly
intervened to clarify the proper interpretation of
Section 113(f) where circuits have split on its
meaning. See Guam, 141 S. Ct. at 1612 (resolving
circuit split); United States v. Atlantic Research Corp.,
551 U.S. 128, 131-33 (2007) (resolving circuit split);
Cooper Indus., 543 U.S. at 160-61 (granting review
without circuit split). This case presents a welldeveloped conflict regarding a critical feature of the
contribution provision that likewise warrants
resolution by this Court.
2. The fact that this conflict concerns the proper
standard of review further strengthens the case for
certiorari. As this Court has often noted, appellate
review is a vital bulwark against arbitrary decisionmaking, ensuring that “the same question” is not
decided “one way between one set of litigants and the
opposite way between another.” SEC v. American
Trailer Rentals Co., 379 U.S. 594, 620 (1965) (quoting
Benjamin N. Cardozo, The Nature of the Judicial
Process 33 (1921)). “Standards of review are critical
to the business of judging, and can often be outcome
determinative.” Evans v. Secretary, Dep’t of Corr.,
703 F.3d 1316, 1336 (11th Cir.) (en banc) (Jordan, J.,
concurring), cert. denied, 569 U.S. 1008 (2013). The
striking contrast in results under the majority and
minority positions on the standard of review at issue
here illustrates the standard’s importance. Supra at
17-18, 21-22 & n.6.
It is no surprise, then, that this Court routinely
intervenes to establish “uniformity among federal
courts” on standards of review.
Thompson v.
Keohane, 516 U.S. 99, 106 (1995) (resolving circuit
split on standard of review for state courts’ “in
25
custody” determinations); see also, e.g., Monasky v.
Taglieri, 140 S. Ct. 719, 726 (2020) (child’s habitual
residence under Hague Convention); U.S. Bank Nat’l
Ass’n ex rel. CWCapital Asset Mgmt. LLC v. Village at
Lakeridge, 138 S. Ct. 960, 965 (2018) (bankruptcy
court’s determination of non-statutory insider status);
McLane Co. v. EEOC, 581 U.S. 72, 79 (2017)
(enforcement of EEOC subpoena); Teva Pharms.
USA, Inc. v. Sandoz, Inc., 574 U.S. 318, 324 (2015)
(findings related to patent claim construction).
Here, it is especially “important to clarify the
standard of review” that appellate courts “must
apply” to CERCLA contribution allocations. Teva,
574 U.S. at 324. It is undeniable that, because of this
circuit conflict, some litigants benefit from
meaningful review of allocation decisions, and others
do not. Accordingly, a litigant’s choice between
seeking contribution in the “district in which the
release or damages occurred” or the district “in which
the defendant resides” could potentially alter the
standard of review. 42 U.S.C. § 9613(b). This Court’s
intervention is needed to ensure that the standard of
review for CERCLA contribution allocations does not
turn on geographic happenstance.
3. This conflict also has major ramifications for
the administration of CERCLA, because it impedes
the effective negotiation of settlements. As this Court
recently observed, “[s]ettlements are the heart of the
Superfund statute.”
Atlantic Richfield Co. v.
Christian, 140 S. Ct. 1335, 1355 (2020). Much of the
“cleanup work currently underway” is performed
pursuant to settlement agreements. Id. And EPA
prefers to proceed by settlement “instead of issuing an
order or paying for [a cleanup] and recovering the
cleanup costs later.” Id. (citation omitted).
26
Because CERCLA does not function without
settlements, “[c]ontribution is crucial to CERCLA’s
regulatory scheme.”
Atlantic Research Corp. v.
United States, 459 F.3d 827, 836 (8th Cir. 2006), aff’d,
551 U.S. 128 (2007). As courts have recognized, “the
statutory right to contribution in § 113(f)” exists “in
part to encourage settlements and further CERCLA’s
purpose as an impetus to efficient resolution of
environmental hazards.” Niagara Mohawk Power
Corp. v. Chevron USA, Inc., 596 F.3d 112, 138 (2d Cir.
2010). Indeed, Congress expressly anticipated that
“assur[ing]” parties who take on “financial
responsibility for some or all of the cleanup” that
“they can seek contribution from others” would
“encourage private party settlements and cleanups.”
H.R. Rep. No. 99-253, pt. 1, at 80. In other words, the
promise of fair contribution in the future makes PRPs
more inclined to settle now.
For PRPs to have confidence in CERCLA’s
contribution mechanism, however, appellate review
must provide a meaningful backstop against
irrational or unexplained allocations of liability. The
requirement for reasoned decision-making that the
abuse-of-discretion standard demands thus promotes
CERCLA’s goals of remediating contaminated sites
and making responsible parties pay, without
protracted litigation. At the same time, permitting
diverging interpretations of CERCLA’s contribution
provision to alter settlement incentives based on the
happenstance of geography is untenable.
4. This case is an excellent vehicle to address the
circuit conflict. The panel below expressly invoked
the Ninth Circuit’s clear-error standard in deciding
this appeal, and the Ninth Circuit declined to revisit
that standard by denying rehearing en banc.
27
Moreover, as explained below, the blatant
inconsistency and unexplained leaps at the heart of
the district court’s decision bear the hallmarks of an
abuse of discretion. Yet, under the clear-error
standard, the Ninth Circuit overlooked those flaws
and rubber stamped the district court’s allocation
decision in a summary opinion. This case thus
illustrates precisely why the standard of review
matters in reviewing equitable allocations under
CERCLA.7
III. The Ninth Circuit’s Rule Is Wrong
The Ninth Circuit’s position that equitable
allocations under CERCLA are reviewed only for clear
error also is indefensible on the merits.
1. The inquiry into the appropriate standard of
review starts with “the language and structure of the
governing statute.” Pierce v. Underwood, 487 U.S.
552, 559 (1988). Section 113(f)(1) provides that, “[i]n
resolving contribution claims, the court may allocate
response costs among liable parties using such
equitable factors as the court determines are
appropriate.” 42 U.S.C. § 9613(f)(1). This is an
“explicit statutory command” to exercise discretion,
7
The fact that the decision below is unpublished poses no
barrier to review because it applies a “line of” Ninth Circuit
precedent that “conflicts with holdings of courts in other
Circuits.” Spectrum Sports, Inc. v. McQuillan, 506 U.S. 447, 453
(1993) (reversing unpublished opinion); see also, e.g., Lamps
Plus, Inc. v. Varela, 139 S. Ct. 1407, 1413 (2019) (granting
certiorari to reverse unpublished opinion implicating “a conflict
among the Courts of Appeals”); Krupski v. Costa Crociere S.p.A.,
560 U.S. 538, 546 (2010) (same); Old Chief v. United States, 519
U.S. 172, 177 (1997) (same). CFAC pointed out this circuit
conflict in both its Ninth Circuit merits brief and its rehearing
petition.
28
which alone counsels strongly in favor of review for
abuse of that discretion. Pierce, 487 U.S. at 558.
Once the court decides the relevant factors, the
balancing of those factors requires the exercise of a
district court’s discretionary judgment. It is wellsettled that “an act of equitable discretion by the
district court” becomes “reviewable on appeal for
abuse of discretion.” eBay Inc. v. MercExchange, LLC,
547 U.S. 388, 391 (2006). This rule controls here.
“Contribution is a remedy that developed in equity,”
Restatement (Second) of Torts § 886A(2) cmt. c (May
2023, Westlaw), and Section 113(f)(1) incorporates
contribution’s “traditional” definition, Atlantic
Research, 551 U.S. at 138. To determine a tortfeasor’s
equitable share of liability, the district court must
exercise its “‘sound discretion,’” as “courts of equity
have” done “[f]or ‘several hundred years.”’ United
States v. Oakland Cannabis Buyers’ Co-op., 532 U.S.
483, 496 (2001) (citation omitted).
By contrast, nothing in Section 113(f)(1)’s text
suggests that an allocation of CERCLA contribution
liability should be construed as a finding of fact,
subject to clear-error review. The statute does not
simply ask a court to find “who did what, when or
where, how or why.” U.S. Bank, 138 S. Ct. at 966.
Rather, Section 113(f)(1) requires a judgment based
on a “discretionary” balancing of “equitable factors in
a given case.” Goodrich, 311 F.3d at 170. Clear-error
review is thus plainly “inapposite.” Id. at 170 n.16.
Indeed, it is hard to understand how any decision
striking a particular balance could be described as
“clear error”—unless it is based on erroneous factual
findings. But the text of Section 113(f)(1) plainly
contemplates review of a district court’s decision
beyond the underlying facts. A clear-error standard
29
is thus ultimately an incoherent fit for the type of
inquiry Section 113(f)(1) mandates.
2. A “long history of appellate practice”—against
which Congress enacted CERCLA—also favors
reviewing equitable determinations, such as
contribution allocations, for abuse of discretion.
Pierce, 487 U.S. at 558. And that history makes clear
that abuse-of-discretion review imposes meaningful
constraints on equitable decision-making. Absent a
statement to the contrary, Congress is presumed to
adopt such background principles. See, e.g., Minerva
Surgical, Inc. v. Hologic, Inc., 141 S. Ct. 2298, 2307
(2021) (citing Astoria Fed. Sav. & Loan Ass’n v.
Solimino, 501 U.S. 104, 108 (1991)) (assignor
estoppel); California Pub. Emps.’ Ret. Sys. v. ANZ
Sec., Inc., 582 U.S. 497, 507-08 (2017) (equitable
tolling).
A variety of equitable determinations have long
been reviewed for abuse of discretion. See, e.g.,
Burton v. Burton, 21 P. 847, 848 (Cal. 1889) (probate);
Florida Power Corp. v. Ocklawaha Reclamation
Farms, 112 So. 616, 616 (Fla. 1927) (per curiam)
(temporary restraining order); Curran v. Georgia
Loan & Tr. Co., 30 S.E. 886, 886-87 (Ga. 1898)
(interlocutory injunction); Kenemer v. Kenemer, 26
Ind. 330, 332 (1866) (alimony); Spinks v. Raison, 139
S.W. 811, 812 (Ky. 1911) (ordering resale of property);
Taylor v. Baldwin, 10 Barb. 626, 630-31 (N.Y. Gen.
Term 1851) (lien enforcement); Cozard v. Cozard, 92
P. 935, 936 (Wash. 1907) (division of community
property).
Just as courts’ power to exercise equitable
discretion is older than this Nation, so too are
constraints on that discretion. See Owen W. Gallogly,
Equity’s Constitutional Source, 132 Yale L.J. 1213,
30
1245-56
(2023)
(describing
English
equity
jurisprudence’s development of “a set of rules to
constrain [Chancellors’] discretion”). The abuse-ofdiscretion standard looks to whether a court’s
reasoning was not just supported by the record, but
internally consistent. See, e.g., State v. Norrell, 53 P.
610, 610 (Utah 1898) (explaining that, under the
abuse-of-discretion standard, “findings of fact,
conclusions of law, and decree must all stand
together, and be consistent with each other.”). And
apart from demanding consistency, the abuse-ofdiscretion
standard
requires
an
adequate
explanation. See, e.g., Biden v. Texas, 142 S. Ct. 2528,
2543-44 (2022) (explaining that an agency’s “exercise
of discretion within [a] statutory framework must be
reasonable and reasonably explained”); FCC v. Fox
Television Stations, Inc., 556 U.S. 502, 515 (2009)
(emphasizing “the requirement that an agency
provide reasoned explanation for its action”).
This Court also has explained that “when
Congress invokes” a court’s equitable powers, it
requires “the principled application of standards
consistent with [statutory] purposes.” Albemarle
Paper Co. v. Moody, 422 U.S. 405, 417 (1975); see also
Lonchar v. Thomas, 517 U.S. 314, 323 (1996)
(reviewing courts should protect against “arbitrary
and uncertain” rulings akin to “measuring distance by
the length of each chancellor’s foot”). Accordingly,
even where “the court’s discretion is equitable in
nature,” that “hardly means that [such discretion] is
unfettered by meaningful standards or shielded from
thorough appellate review.” Albemarle, 422 U.S. at
416. Such limits on equitable decision-making stand
in stark contrast to the “serious thumb on the scale”
31
given to “factual findings [that] are reviewable only
for clear error.” U.S. Bank, 138 S. Ct. at 966.
Contribution allocations outside of the CERCLA
context uniformly receive abuse-of-discretion review.
See, e.g., Baptist Health v. Smith, 536 F.3d 869, 872
(8th Cir. 2008); Amphibious Partners, LLC v.
Redman, 534 F.3d 1357, 1362 (10th Cir. 2008).
Indeed, the Ninth Circuit itself reviews for abuse of
discretion other equitable allocations, see Westport
Ins. Co. v. California Cas. Mgmt. Co., 916 F.3d 769,
778 (9th Cir. 2019), and a host of different equitable
determinations, see Metal Jeans, Inc. v. Metal Sport,
Inc., 987 F.3d 1242, 1244-45 (9th Cir. 2021). This
history firmly supports reviewing CERCLA
contribution allocations for abuse of discretion as
well.
3. Finally, “basic principles of institutional
capacity counsel in favor of” abuse-of-discretion
review. McLane Co., 581 U.S. at 81. Appellate courts
are well-situated to police the boundary between
“[d]iscretion” and “whim” by applying abuse-ofdiscretion review, and frequently do. Halo Elecs., Inc.
v. Pulse Elecs., Inc., 579 U.S. 93, 103 (2016)
(alteration in original) (citation omitted).
As this Court has repeatedly explained in
reviewing agency action, inconsistencies and the lack
of a “reasoned explanation” are the hallmarks of an
abuse of discretion.
Encino Motorcars, LLC v.
Navarro, 579 U.S. 211, 221-22 (2016); Fox, 556 U.S.
at 515-16 (“[A] reasoned explanation is needed for
disregarding facts and circumstances that underlay
or were engendered by the prior policy.”); National
Cable & Telecommc’ns Ass’n v. Brand X Internet
Servs., 545 U.S. 967, 981 (2005) (“Unexplained
inconsistency is . . . a reason for holding an
32
interpretation to be an arbitrary and capricious
change
from
agency
practice
under
the
Administrative Procedure Act.”); Smiley v. Citibank
(South Dakota), N.A., 517 U.S. 735, 742 (1996)
(“Sudden and unexplained change . . . may be
‘arbitrary, capricious [or] an abuse of discretion’”
(alteration in original) (citation omitted)).
Circuit courts likewise hold that a district court
decision that is internally inconsistent or
inadequately explained constitutes an abuse of
discretion. See, e.g., BladeRoom Grp. Ltd. v. Emerson
Elec. Co., 20 F.4th 1231, 1247-48 (9th Cir. 2021)
(holding that court abused discretion by “flipp[ing] its
reasoning twice without explaining why”); Jackson v.
Los Lunas Cmty. Program, 880 F.3d 1176, 1205 (10th
Cir. 2018) (holding that court abused discretion by
finding facts demonstrating changed circumstances
but “conclud[ing], without adequate explanation,” the
opposite); United States v. Brown, 453 F.3d 1024,
1026 (8th Cir. 2006) (holding that sentencing court
abused discretion based on “internally inconsistent”
reasoning regarding witness credibility); see also
Henry J. Friendly, Indiscretion About Discretion, 31
Emory L.J. 747, 778 (1982) (explaining that a
discretionary determination that fails to adhere to
“equitable principles” or “adequately articulate[] . . .
reasons” for its result should not “stand”).
To be sure, district courts are best-positioned to
find facts that bear on CERCLA contribution
allocations. U.S. Bank, 138 S. Ct. at 966. Such
subsidiary findings of fact therefore receive no less
deference under abuse-of-discretion review.
See
Cooter & Gell v. Hartmarx Corp., 496 U.S. 384, 399401 (1990) (explaining that abuse of discretion and
clear-error
standards
treat
historical
facts
33
identically). But reviewing ultimate allocations for
abuse of discretion recognizes that a CERCLA
contribution allocation is the product of a
discretionary balancing of factors.
42 U.S.C.
§ 9613(f)(1). In other words, a flexible, equitable
determination should not get the same significant
deference as a finding of “historical” fact about how
many tons of waste a party put in a landfill. U.S.
Bank, 138 S. Ct. at 966. And neither the Ninth
Circuit nor any other court has offered a considered
rationale for treating an equitable allocation as a
finding of fact. Supra at 16-17, 22.
4. The district court’s decision in this case
illustrates the shortcomings of the clear-error
standard in reviewing equitable allocations. Under
the clear-error standard, the Ninth Circuit
disregarded the blatant inconsistency infecting the
district court’s reliance on the parties’ contract in
shifting liability to CFAC and the district court’s
failure to explain key leaps in its decision.
First, the Ninth Circuit excused the district court’s
stark inconsistency on the applicability of the
Acquisition Agreement in shifting CERCLA liability.
At the outset of its analysis, the district court, in
rejecting ARCO’s threshold contractual argument,
held that the Agreement’s text “unambiguous[ly]” did
not make CFAC responsible for ARCO’s CERCLA
liability and that the parties’ “conduct” and “extensive
correspondence” reinforced this conclusion. App. 30a,
42a-43a. Yet, one hundred pages later, the district
court expressly relied on the Agreement as the “most
important factor” in allocating CFAC 65% of CERCLA
liability for the Site. Id. at 144a-46a, 150a. This
blatant inconsistency lay at the heart of the court’s
34
decision.
The district court did not directly
acknowledge or explain this about-face.
Instead of reviewing the district court’s reasoning
for an abuse of discretion, the Ninth Circuit panel
tried to paper over this inconsistency by
hypothesizing that the district court found that the
Agreement was “not sufficiently clear” to shift
CERCLA liability. Id. at 3a (emphasis added). But
that reasoning is refuted by what the district court
actually said. It did not find that the Agreement
suggested that CERCLA costs could be shifted, but
simply was not clear enough to meet some additional
hurdle under state law. Rather, the district court
concluded that the Agreement “unambiguously” did
not shift CERCLA liability. Id. at 30a-31a, 43a.
Second, the district court failed to explain its
bizarre finding that, even though ARCO was the
“primary contributor” to Site contamination—a huge
factor weighing in CFAC’s favor—the need to
construct a “slurry wall” around the Wet Scrubber
Sludge Pond to contain that contamination somehow
offset this critical finding. That made no sense. The
district court found that ARCO was the “primary
contributor” to contamination at the Site—period.
While CFAC contributed some contamination at the
Wet Scrubber Sludge Pond, that Pond was downhill
of the unlined landfill that ARCO contaminated, and
could not reasonably have canceled out ARCO’s
primary contamination of the Site, or the need to
remediate that contamination. Supra at 6-7. Even
the panel observed that “[i]deally, the district court
would have explained more fully each party’s relative
contribution to the need for” a slurry wall. App. 5a.
Yet it didn’t. That gaping lack of explanation on this
critical issue is a quintessential abuse of discretion.
35
Third, the district court also failed to explain its
head-scratching conclusion that a $2.25 million
benefit to CFAC (what it projected to be the postremediation value of the Site) somehow wiped out the
$280 million advantage in profits that ARCO enjoyed
at the Site—a 2-to-1 advantage over CFAC’s profits.
Once again, the district court utterly failed to explain
this nonsensical leap.
The panel, however,
disregarded the lack of any explanation of this key
point. Instead, the panel again tried to backfill the
reasoning by pointing to other underlying facts, such
as ARCO’s greater capital investment in “the facility’s
construction and upgrades to mitigate environmental
contamination,” CFAC’s purchase of the facility “for
$1.00,” and the “substantial profits earned by both
parties.” Id. at 6a. But the district court itself
rejected capital investment as a basis for offsetting
ARCO’s profits advantage and evaluating relative
benefit. Id. at 147a-48a. And, although CFAC
purchased the property for $1, ARCO saved $7 million
in liquidation costs from the sale. Once again,
therefore, the district court’s decision lacked the
critical requirement to survive abuse-of-discretion
review—reasoned decision-making. Yet this was
irrelevant under the Ninth Circuit’s clear-error test.
These are just a few examples of the obvious flaws
in the district court’s decision that would require
reversal under the abuse-of-discretion standard
applied by the strong majority of circuits. But none of
this mattered under the clear-error standard that the
Ninth Circuit applied in summarily affirming the
district court’s equitable allocation in this case. The
acknowledged conflict in the standard of review for
such allocations warrants this Court’s review.
36
CONCLUSION
The petition for a writ of certiorari should be
granted.
Respectfully submitted,
SAMIR DEGER-SEN
PETER TROMBLY*
LATHAM & WATKINS LLP
1271 Avenue of the
Americas
New York, NY 10020
GREGORY G. GARRE
Counsel of Record
LATHAM & WATKINS LLP
555 Eleventh Street, NW
Suite 1000
Washington, DC 20004
(202) 637-2207
gregory.garre@lw.com
Counsel for Petitioner
June 12, 2023
*
Admitted to practice in Virginia only.
APPENDIX
TABLE OF CONTENTS
Page
Opinion of the United States Court of Appeals
for the Ninth Circuit, Columbia Falls
Aluminum Company, LLC v. Atlantic
Richfield Company, No. 21-36042, 2023
WL 1281669 (9th Cir. Jan. 31, 2023), ECF
No. 48-1 ...............................................................1a
Findings of Fact and Conclusions of Law of the
United States District Court for the
District of Montana, Columbia Falls
Aluminum Company, LLC v. Atlantic
Richfield Company, No. CV 18-131, 2021
WL 3769886 (D. Mont. Aug. 25, 2021), ECF
No. 148 ................................................................7a
Order Granting Motion to Amend Judgment in
Limited Part, Columbia Falls Aluminum
Company, LLC v. Atlantic Richfield
Company, No. CV 18-131 (D. Mont. Nov.
23, 2021), ECF No. 167 ...................................154a
Amended
Judgment,
Columbia
Falls
Aluminum Company, LLC v. Atlantic
Richfield Company, No. CV 18-131 (D.
Mont. Nov. 23, 2021), ECF No. 168 ...............157a
Order Denying Petition for Rehearing,
Columbia Falls Aluminum Company,
LLC v. Atlantic Richfield Company,
No. 21-36042 (9th Cir. Mar. 14, 2023), ECF
No. 52 ..............................................................158a
42 U.S.C. § 9607(a)................................................160a
42 U.S.C. § 9613(b), (f) ..........................................162a
1a
[2023 WL 1281669]
FILED
JAN 31, 2023
MOLLY C. DWYER, CLERK
U.S. COURT OF APPEALS
NOT FOR PUBLICATION
UNITED STATES COURT OF APPEALS
FOR THE NINTH CIRCUIT
COLUMBIA FALLS
ALUMINUM COMPANY,
LLC,
Plaintiff-counterdefendant-Appellant,
No. 21-36042
D.C. No. 9:18-cv00131-DWM
MEMORANDUM*
v.
ATLANTIC RICHFIELD
COMPANY,
Defendant-counterclaimant-Appellee.
Appeal from the United States District Court
for the District of Montana
Donald W. Molloy, District Judge, Presiding
*
This disposition is not appropriate for publication and is not
precedent except as provided by Ninth Circuit Rule 36-3.
2a
Argued and Submitted December 5, 2022
San Francisco, California
Before: WATFORD and SANCHEZ, Circuit Judges,
and BENITEZ,** District Judge.
Appellant Columbia Falls Aluminum Co., LLC
(“CFAC”) appeals the district court’s equitable
allocation of environmental cleanup costs between
CFAC and Appellee Atlantic Richfield Co. (“ARCO”)
under the Comprehensive Environmental Response,
Compensation, and Liability Act (“CERCLA”). We
review the equitable factors considered for abuse of
discretion, and the equitable allocation of those
factors for clear error. TDY Holdings, LLC v. United
States, 885 F.3d 1142, 1146–47 (9th Cir. 2018). “A
finding of fact is clearly erroneous only where it is
‘(1) illogical, (2) implausible, or (3) without support in
inferences that may be drawn from the facts in the
record.’” United States v. Christensen, 828 F.3d 763,
779 (9th Cir. 2015) (quoting United States v. Pineda–
Doval, 692 F.3d 942, 944 (9th Cir. 2012)). If there are
two reasonable interpretations of the evidence, “the
factfinder’s choice between them cannot be clearly
erroneous.” Christensen, 828 F.3d at 779 (quoting
United States v. Working, 224 F.3d 1093, 1102 (9th
Cir. 2000) (en banc)). We affirm.
From 1955 to 1985, ARCO owned and operated an
aluminum smelting site in Columbia Falls, Montana
(the “Site”). In 1985, ARCO sold the Site to CFAC for
$1.00, and CFAC operated the Site until 2009. Both
** The Honorable Roger T. Benitez, United States District
Judge for the Southern District of California, sitting by
designation.
3a
ARCO and CFAC generated substantial profits in
their respective operations and over the years,
hazardous waste was disposed of throughout the Site,
resulting in environmental contamination.
The transfer of the Site from ARCO to CFAC was
governed by a written agreement (the “Agreement”)
containing cross-indemnity provisions.
1. The district court’s equitable allocation of
CERCLA costs and reliance on the Agreement is
consistent with its other findings. The district court
relied on the Agreement when allocating 65 percent
of CERCLA costs to CFAC versus 35 percent to
ARCO. The court found that the Agreement was not
drafted with the specificity required under Montana
law to effectuate a waiver of the right to sue under
statutes such as CERCLA. The court also found that
the extrinsic evidence of the parties’ intent was not
sufficiently clear to overcome the lack of specificity in
the Agreement’s text. Therefore, unlike in Trinity
Indus., Inc. v. Greenlease Holding Co., 903 F.3d 333,
361 (3d Cir. 2018), the district court’s refusal to
enforce the Agreement rested solely on the fact that
the high bar set by state law was not met.
Given the court’s finding that the parties did
intend the Agreement to cover non-statutory liability
for the very environmental conditions at issue in this
case, the court was within its discretion to consider
the Agreement for purposes of equitable allocation
under CERCLA. As the court noted, “[e]ven if the
indemnity provisions are not enforceable as a matter
of contract law to bar CFAC’s claims, the evidence
shows that the parties intended for CFAC alone to
have an indemnification obligation to ARCO after
August 31, 1990.” Accordingly, the district court did
not err in refusing to enforce the Agreement as a
4a
matter of law but considering it when equitably
allocating costs. See Cadillac Fairview/California,
Inc. v. Dow Chemical Co., 299 F.3d 1019, 1025 (9th
Cir. 2002) (equitably allocating 100 percent of
CERCLA cleanup costs to the government based on
an indemnity clause that was not enforceable as a
matter of law); Kerr-McGee Chem. Corp. v. Lefton Iron
& Metal Co., 14 F.3d 321, 326 (7th Cir. 1994) (holding
the district court erred in allocating cleanup costs by
not considering contractual arrangements, which
reflected an intent to indemnify).1
2. The district court did not err in applying the
Gore Factors focused on the amount and nature of
hazardous waste.2 Despite CFAC’s contention that
1
CFAC also challenges the district court’s 65-35 allocation as
arbitrary and speculative. However, the court found the Gore
Factors and respective economic benefits to be neutral, relying
on the Agreement to tip the scales in favor of ARCO. Because
courts “need not allocate response costs to a mathematical
certainty . . . ,” there is no error here. See ASARCO LLC v. Atl.
Richfield Co., LLC, 975 F.3d 859, 869 (9th Cir. 2020), cert.
dismissed sub nom. Atl. Richfield Co. v. Asarco LLC, 141 S. Ct.
2843 (2021); Nikko Materials USA, Inc. v. NavCom Def. Elecs.,
Inc., 291 F. App’x 67, 70 (9th Cir. 2008) (“The district court . . .
acted within its discretion in reducing the level of contribution
from sixty-six percent to sixty percent based on the contractual
relationship between the parties and . . . [the] aggressive
conduct during negotiations . . . .”).
2
These Gore Factors include: “(1) the ability of the parties to
demonstrate that their contribution to a discharge, release or
disposal of a hazardous waste can be distinguished; (2) the
amount of the hazardous waste involved; (3) the degree of
toxicity of the hazardous waste involved; [and] (4) the degree of
involvement by the parties in the generation, transportation,
treatment, storage, or disposal of the hazardous waste . . . .”
TDY Holdings, 885 F.3d at 1146 n.1 (quoting Kerr-McGee Chem.
Corp., 14 F.3d at 326 n.4).
5a
the district court was required to allocate costs based
on each party’s respective contamination of the Site,
the text of CERCLA clearly and unambiguously
states that “[i]n resolving contribution claims, the
court may allocate response costs among liable
parties using such equitable factors as the court
determines are appropriate.”
42 U.S.C.A.
§ 9613(f)(1). While the Gore factors are certainly
relevant and have been used by other courts, they are
“neither an exhaustive nor exclusive list.” Env’t
Transp. Sys., Inc. v. ENSCO, Inc., 969 F.2d 503, 509
(7th Cir. 1992). Here, the district court considered the
Gore Factors but found the first four to be neutral,
taking into consideration the practical effect of the
proposed remedial measure—a slurry wall that would
encompass the West Landfill and the Wet Scrubber
Sludge Pond (“WSSP”).
Considering CFAC’s contamination of the WSSP,
along with the fact that a large portion of the slurry
wall would contain the WSSP, the district court did
not err in considering the proposed remedial measure
alongside the Gore Factors. See Boeing Co. v. Cascade
Corp., 207 F.3d 1177, 1188 (9th Cir. 2000)
(illustrating how in certain circumstances where the
cost of remedial measures does not equate to the
volume of contamination, it would be inappropriate to
look to contamination alone). Ideally, the district
court would have explained more fully each party’s
relative contribution to the need for this joint
remedial measure. See Akzo Nobel Coatings, Inc. v.
Aigner Corp., 197 F.3d 302, 305 (7th Cir. 1999). But
we cannot say based on the evidence before us that
the district court clearly erred in finding that the
slurry wall was occasioned by both ARCO’s and
CFAC’s contamination.
6a
3. The district court did not err in its economic
benefits analysis. Both parties realized hundreds of
millions of dollars in profits during their respective
operations. Although ARCO earned more profit than
CFAC, ARCO expended over $1 billion dollars on the
Site—including the facility’s construction and
upgrades to mitigate environmental contamination—
while CFAC spent only $95 million on Site
improvements. The district court also considered that
CFAC received the facility and everything ARCO put
into it for $1.00. Recognizing these other forms of
economic benefit and the substantial profits earned
by both parties, the district court did not err in
concluding that the totality of the economic picture
was neutral. Cf. Lockheed Martin Corp. v. United
States, 35 F. Supp. 3d 92, 132 (D.D.C. 2014), aff’d, 833
F.3d 225 (D.C. Cir. 2016) (“Although LPC may not
have reaped large profits from its contracts with the
government, it helped its parent corporation
Lockheed Aircraft Corporation establish a foothold in
the rocket propulsion field, a position that Lockheed
retains to this day.”).
AFFIRMED.
7a
[2021 WL 3769886]
IN THE UNITED STATES DISTRICT COURT
FOR THE DISTRICT OF MONTANA
MISSOULA DIVISION
COLUMBIA FALLS
ALUMINUM COMPANY,
LLC,
Plaintiff,
vs.
CV 18-131-M-DWM
FINDINGS OF
FACT AND
CONCLUSIONS
OF LAW
ATLANTIC RICHFIELD
COMPANY,
Defendant.
The trial in this case arises out of a dispute
between Plaintiff Columbia Falls Aluminum
Company, LLC (“CFAC”) and Defendant Atlantic
Richfield Company (“ARCO”) over the parties’
respective environmental liabilities at an aluminum
smelter in Columbia Falls, Montana (“the Site”). In
July 2018, CFAC sued under the Comprehensive
Environmental Response, Compensation, and
Liability Act (“CERCLA”) and its state analog (the
Montana Comprehensive Environmental Cleanup
and Responsibility Act, or “CECRA”), seeking cost
recovery and contribution for its liability as the
current owner and operator of the Site. ARCO
counterclaimed and argues that the parties’ 1985
Acquisition Agreement bars suit and that, even if it
8a
did not, CFAC cannot recover under either CERCLA
or CECRA.
A 7-day bench trial took place in Missoula,
Montana beginning on June 28, 2021. CFAC
presented seven witnesses:
- Andrew Baris, remediation expert;
- David Batson, allocation expert;
- John Stroiazzo, a Glencore consultant at the
Columbia Falls facility;
- William Muno, cleanup cost expert;
- Andrew Otis, CFAC’s regulatory counsel;
- Jeffrey Dunn, rebuttal financial expert; and
- Kraig Kosena, rebuttal appraisal expert.
ARCO presented six witnesses:
- Brian Johnson, strategy manager for ARCO;
- Marcia Williams, industrial site closure expert;
- Peter Jewett, remediation expert;
- David Hall, financial expert;
- Thomas Stevens, appraisal expert; and
- Gayle Koch, cleanup cost expert.
The parties also presented deposition testimony of:
- Steven Wright, CFAC’s only employee and Site
Manager;
- Subodh Das, ARCO environmental manager in
the 1980s; and
- John R. Lucas, ARCO attorney involved in
1985 acquisition.
Notably, neither party deposed or called Brack Duker
as a witness in the case even though he was a critical
player in disposing of ARCO’s assets and negotiating
the 1985 Acquisition Agreement in favor of his new
company.
9a
Based on the evidence and testimony presented at
the trial, and further considering the applicable law
and the parties’ written submissions, the following
findings of fact and conclusions of law are made
pursuant to Federal Rule of Civil Procedure 52.
TABLE OF ACRONYMS
ARCO
Atlantic Richfield Company
CECRA
Comprehensive Environmental
Cleanup and Responsibility Act
CERCLA Comprehensive Environmental Response,
Compensation, and Liability Act
CFAC
Columbia Falls Aluminum Company,
LLC
EPA
United States Environmental
Protection Agency
MDEQ
Montana Department of
Environmental Quality
MDHES
Montana Department of Health and
Environmental Sciences
MPDES
Montana Pollutant Discharge
Elimination System
PAH
polyaromatic hydrocarbon
PCB
polychlorinated biphenyl
PRP
Potentially Responsible Party
RCRA
Resource Conservation and Recovery
Act
SPL
Spent Potliner
WSSP
Wet Scrubber Sludge Pond
10a
[Table of Contents omitted]
I. OPERATIONAL HISTORY
1.
Defendant Atlantic Richfield Company
(“ARCO”) is a corporation organized under the laws of
the state of Delaware, with its principal place of
business in Texas. (Agreed ¶ 1.)
2.
Plaintiff
Columbia
Falls
Aluminum
Company, LLC (“CFAC”) is a limited liability
company organized under the laws of the state of
Delaware, with its principal place of business in
Columbia Falls, Montana. (Agreed ¶ 2.)
3.
The former aluminum reduction facility
that CFAC owns, located near Columbia Falls,
Flathead County, Montana (“The Site”), is located at
2000 Aluminum Drive, two miles northeast of
Columbia Falls, Montana, and lies north of the
Flathead River, west of Teakettle Mountain, south of
Cedar Creek Reservoir, and east of Cedar Creek.
(Agreed ¶ 3.)
11a
(Ex. 260 at 9.)
4.
ARCO, including its corporate predecessors,
Anaconda Aluminum Company and Anaconda Copper
Mining Company (together “Anaconda”), owned real
property and/or conducted industrial operations at
the Site from 1955 to 1985. (Agreed ¶ 5.) ARCO is
now part of bp, or British Petroleum. (Johnson.)
5.
In 1955, Anaconda completed construction
of the aluminum reduction facility and began
12a
production of aluminum at the Site. (Agreed ¶ 7; see
also Ex. 230 at 6.)
(Ex. 230 at 118.)
6.
CFAC—through its corporate predecessors,
Montana Aluminum Investors Corp. and Columbia
Falls Aluminum Company, a Montana Corporation—
acquired the Site from ARCO in September 1985,
conducted industrial operations at the Site including
operating the aluminum reduction facility during the
period of 1985 to 2009, and currently owns the Site.
(Agreed ¶ 6.) Glencore is CFAC’s parent company.
(Stroiazzo.)
7.
The industrial ownership timeline for the
Site is as follows:
1951 to 1978:
Anaconda
1978 to 1985:
ARCO
13a
1985 to 1999:
Montana Aluminum Investors
Corp.
1999 to present:
CFAC
(Ex. 134 at 45.) References herein to ARCO include
actions and operations of Anaconda and references to
CFAC include the actions and operations of Montana
Aluminum Investors Corp.
8.
The operational area of the Site, commonly
known as the Anaconda Aluminum Co. Columbia
Falls Reduction Plant, occupied approximately 953
acres. (Ex. 26 at 8.) The following site features map
depicts the location of different Site operational areas
which are addressed in more detail below:
14a
(Agreed ¶ 4; Ex. 848 at 2; see also Ex. 134 at 304.)
15a
9.
Both ARCO and CFAC produced aluminum
at the Site using the Hall-Héroult process and vertical
stud Soderberg aluminum cell technology. In this
process, aluminum was produced in an aluminum
production “pot,” a steel vessel which was lined with
carbon paste, or “potliner.” Each pot was charged
with a mixture of powdered alumina (aluminum
oxide) and cryolite (sodium fluoride), to which a high
electric current was applied through an anode (made
of petroleum coke and pitch) at the top of the mixture.
The current passed from the anode through
alumina/cryolite bath to the potliner, which acted as
a cathode and completed a circuit. The application of
current also created high heat in each pot (1760° F
(960° C)). As a result, aluminum ions in alumina were
reduced to aluminum metal, forming molten
aluminum at the bottom of the pot. The molten
aluminum was periodically tapped from the pot and
transported to the Site’s Cast House, where it was
cast into ingots for offsite shipment. Over the years,
as part of the casting process, various alloys and
ingots were produced at the facility. (Agreed ¶ 8; Ex.
134 at 45.) Diagrams of the aluminum production
process are provided below:
16a
(Ex. 1278 at 7; Ex. 230 at 52.)
10.
Initially in 1955, ARCO built two potlines
with 120 pots in each potline and a nominal capacity
of 67,500 metric tonnes per year. A third potline of
17a
120 pots was added in 1965, and the fourth and fifth
potlines, also having 120 pots each, were added in
1968, increasing total aluminum production capacity
at the Site to 180,000 metric tonnes per year. (Ex. 134
at 45; Ex. 230.)
18a
(Ex. 1278 at 8.)
19a
11.
Prior to 1980, the average life of a
cathode/pot was short (3 to 4 years). (See Ex. 230 at
126; Ex. 294 at 9.) Technological improvements,
including the installation of “Sumitomo” technology
in the early 1980s, extended the lifespan of a potliner
to seven to nine years. (Ex. 294 at 9; Ex. 260 at 15.)
An image of the pot line from the Site is provided
below, (Ex. 230 at 126):
12.
ARCO
produced
an
estimated
7,104,464,396 lbs. (3,222,531 metric tonnes) of
aluminum between 1955 and September 1985, when
it sold the Site to CFAC. (Agreed ¶ 9; see also Exs.
283, 720.)
20a
13.
CFAC produced an estimated 6,319,833,296
lbs. (2,866,628 metric tonnes) of aluminum between
October 1985 and 2009, when it stopped producing
aluminum. (Agreed ¶ 10; see also Exs. 283, 720.)
14.
The aluminum production volumes (in lbs.)
are detailed below:
Atlantic Richfield
1955- Sep. 1985
CFAC
Oct. 1985-2009
Year
Production
(lbs.)
Year
Production
(lbs.)
1955
29,600,731
Oct.
1985Dec.
1985
91.525,427
1956
123,461,000
1986
367,594,000
1957
104,403,000
1987
371,200,000
1958
100,588,000
1988
366,104,000
1959
102,320,000
1989
369,366,000
1960
114,142,000
1990
370,264,000
1961
126,770,000
1991
370,292,000
1962
135,107,000
1992
374,864,000
1963
136,017,000
1993
284,475,420
1964
138,919,000
1994
279,758,900
1965
163,366,000
1995
331,606,716
1966
213,461,000
1996
372,290,190
1967
213,127,000
1997
377,474,544
21a
Year
Production
(lbs.)
Year
Production
(lbs.)
1968
211,694,000
1998
373,220,977
1969
356,485,000
1999
372,355,263
1970
358,877,000
2000
350,319,829
1971
346,610,000
2001
13,564,835
1972
357,304,000
2002
148,659,588
1973
304,064,000
2003
106,649,215
1974
342,028,000
2004
74,536,594
1975
257,660,000
2005
73,339,813
1976
294,011,000
2006
74,688,639
1977
309,641,000
2007
199,995,579
1978
309,420,000
2008
167,942,952
1979
315,462,000
2009
37,744,815
1980
332,043,000
Total
6,319,833,296
1981
335,830,000
1982
215,617,000
1983
170,990,000
1984
318,809,000
Jan. –
Sep.
1985
266,637,665
Total
7,104,464,396
(Agreed ¶ 11; Ex. 720.)
15.
Around 2001, CFAC temporarily ceased
aluminum production, shutting down the facility so it
22a
could instead sell electricity into the West Coast
wholesale electricity market. (See Ex. 283 at 99, 105.)
16.
CFAC announced the permanent closure of
the facility in 2015 and completed the
decommissioning and removal of the industrial
buildings and related structures in the third quarter
of 2019. (Agreed ¶ 12; Ex. 134 at 44.)
II. PARTY ARGUMENTS
A.
CFAC
17.
According to CFAC, from approximately
1960 through approximately 1980, ARCO alone
disposed of an estimated 129,000 to 135,000 tons of
spent potliners (“SPL”), a principal waste generated
by aluminum reduction which contained cyanide and
fluoride in two unlined landfills: the West Landfill
and the Center Landfill. ARCO alone also disposed of
another waste from its aluminum production
operations—sludge from wet scrubbers that was
composed of 80 percent calcium fluoride—in the Wet
Scrubber Sludge Pond (“WSSP”) from the beginning
of ARCO’s operations at the Site through
approximately 1979.
18.
These onsite SPL and fluoride disposals by
ARCO are primarily (if not in fact exclusively)
responsible for the elevated concentrations of cyanide
and fluoride observed in groundwater downgradient
from these disposal areas. The SPL and fluoride
disposals by ARCO, and the elevated groundwater
concentrations, led the United States Environmental
Protection Agency (“EPA”) to list the Site on the
CERCLA National Priorities List in September 2016.
The cyanide and fluoride leaching from the SPL
disposed of by ARCO, and calcium fluoride sludge
disposed of by ARCO, are the principal drivers for the
23a
need to select and implement a cleanup remedy at the
Site.
B.
ARCO
19.
According to ARCO, the present suit is
foreclosed by the parties’ 1985 Acquisition
Agreement. But even if it is not, CFAC seeks to
recover costs that are either not recoverable under
CERCLA or for which it agreed to indemnify ARCO.
Finally, to the extent any costs are recoverable, CFAC
should be allocated greater responsibility for those
costs based on the Acquisition Agreement, CFAC’s
failure to exercise due care in its operation and
closure of the facility, CFAC’s own discharges of
hazardous materials, and the economic benefit CFAC
realized or will realize from the Site.
III. CONTRACTUAL LIMITIONS ON SUIT
20.
As a threshold matter, the parties dispute
whether CFAC is contractually barred from bringing
this action against ARCO. Based on the evidence
presented at trial, the contractual bone of contention
is resolved in CFAC’s favor. Even so, the proof at trial
supports allocating a majority of the Site cleanup
costs to CFAC under CERCLA’s equitable allocation
process, which is discussed below.
21. State law “provide[s] the general content of
federal law on the validity of releases of claims of costrecovery under CERCLA.” Mardan Corp. v. C.G.C.
Music, Ltd., 804 F.2d 1454, 1460 (9th Cir. 1986).
Accordingly, Montana law governs the interpretation
of the parties’ agreements here.
24a
A.
The Agreements
22.
The parties entered into three agreements
in the 1980s: the 1985 Acquisition Agreement, the
1985 Supplemental Agreement, and the 1988
Settlement. While all three are discussed below, the
parties’ dispute focuses primarily on the 1985
Acquisition Agreement.
1. The Acquisition Agreement
23.
On September 10, 1985, ARCO and
Montana Aluminum Investors Corp., CFAC’s
predecessor, entered into the Acquisition Agreement.
(Ex. 1; Lucas.)
24.
Through the Agreement, ARCO transferred
to Montana Aluminum Investors Corp. the “Assets of
the Smelter Business,” as such term is defined in the
Acquisition Agreement and sold all stock to Montana
Aluminum Investors Corp. for the purchase price of
$1.00. (Ex. 1 at § 2(c).)
25.
The Acquisition Agreement defines “Assets
of the Smelter Business” as “those assets of Seller
relating to the Smelter Business wherever they may
be located,” but excluding certain assets not relevant
here, and explains “[a]s used herein, the phrase
‘relating to the Smelter Business’ when used with
respect to any asset or liability of Seller is intended to
designate those assets or liabilities that have been
used or are associated with the conduct of the Smelter
Business.” (Agreed ¶ 57; Ex. 1 § 1(a).)
26. The Acquisition Agreement contains
indemnity provisions in favor of both ARCO, as Seller,
and Montana Aluminum Investors Corp. (or CFAC),
as Buyer. (Ex. 1, Section 10.) ARCO insists that
pursuant to those provisions, CFAC agreed not to sue
ARCO for environmental conditions at the Site after
25a
1990 and/or assumed all environmental liability for
the Site as of 1990, foreclosing the present action. The
specific language of the indemnity provisions is
provided below.
27. The Acquisition Agreement required Seller
(ARCO) to “indemnity and hold Buyer harmless from
and against: . . . (iii) All damages, losses, and out-ofpocket expenses (including attorneys’ fees) caused by
or arising out of obligations or liabilities relating to
the Smelter Business resulting from events or
conditions in existence prior to the Closing Date.”
(Agreed ¶ 58; Ex. 1 § 10(a), (a)(iii).)
28.
The Acquisition Agreement requires Buyer
(CFAC) to “indemnify and hold Seller harmless from
and against . . . (iii) All damages, losses, and out-ofpocket expenses arising out of . . . obligations or
liabilities, contingent or otherwise, relating to the
operation of the Smelter Business after the Closing
Date, other than obligations or liabilities as to which
Seller is obligated to indemnify Buyer pursuant to
Section 10(a)(iii).” (Agreed ¶ 60; Ex. 1 § 10(b)(iii).)
29.
The
Acquisition
Agreement
further
provides: “Buyer’s obligation to indemnity Seller with
respect to the liabilities and obligations referred to in
clauses (ii) and (iii) of this Section 10(b) will be
continuing.” (Agreed ¶ 61; Ex. 1 § 10(b)(iii).) But
“Buyer may not make a claim with respect to . . . (B)
Seller’s indemnity referred to in clause (iii) of this
Section 10(a) at any time after August 31, 1990,
except with respect to any such claim relating to the
tax matters referred to in Article VIII . . . .” (Agreed
¶ 59; Ex. 1 § 10(a)(iii).)
26a
2. The Supplemental Agreement
30.
ARCO and Montana Aluminum Investors
Corp. also entered into a “Supplemental Agreement”
on September 10, 1985. Under the Supplemental
Agreement, ARCO agreed to pay $4 million into an
escrow account, which Montana Aluminum Investors
Corp. was authorized to draw upon for the purpose of
paying certain operating expenses or liquidating
expenses of the aluminum smelter facility for a period
not to exceed five years. (Ex. 2: Lucas.)
31.
If Montana Aluminum Investors Corp.
earned an aggregate amount of $10 million or more
from its operations of the facility during the ensuing
five-year period, the Supplemental Agreement
required it to repay to ARCO the $4 million deposited
into the escrow account out of Montana Aluminum
Investors Corp.’s subsequent earnings. (Ex. 2 at ¶ 4;
Lucas.)
32.
In approximately November 1988, Montana
Aluminum Investors Co. repaid the $4 million
because it had hit the $10 million benchmark (Ex. 9;
Lucas.)
3. 1988 Settlement
33.
On November 16, 1988, ARCO and
Montana Aluminum Investors Corp. entered into a
settlement agreement to “to compromise and settle
certain matters which were in dispute between the
two companies with respect to the operation of the
[1985] Acquisition Agreement . . . .” (Ex. 1216.)
34.
Among other things, the 1988 Settlement
addressed an asbestos encapsulation program
undertaken by Montana Aluminum Investors Corp.
at the Site. (Ex. 1216 at ¶ 2.) ARCO agreed to pay
one-half of the $310,000 expended by Montana
27a
Aluminum
Investors
Corp.
for
asbestos
encapsulation. In exchange for that $155,000
payment, Montana Aluminum Investors Corp. agreed
it would “continue to remain solely responsible for
compliance with all environmental, health, safety and
other regulations applicable to the operation of the
Columbia Falls smelter with reference to the presence
of asbestos containing materials.” (Ex. 1216 at ¶ 2.)
CFAC also agreed to “defend and hold ARCO
harmless against any claims which might be brought
by any person with respect to or arising out of, the
asbestos encapsulation program,” and “to waive and
hereby release[ ] ARCO from any and all claims which
Montana Aluminum Investors Corp. may presently
have, or may have in the future, with respect to the
presence of asbestos containing material at the
Columbia Falls smelter.” (Ex. 1216 at ¶ 2.)
35.
ARCO transmitted the check for $155,000
to CFAC on November 16, 1988. (Ex. 1216 at 1.)
36.
CFAC therefore waived and released ARCO
from any claims with respect to the presence of
asbestos containing materials at the Site, including
claims for costs associated with asbestos removal
from the plant buildings and any cleanup or capping
of the asbestos landfills at the Site. (See Ex. 1216.)
37.
Consequently, CFAC cannot recover
contribution for past costs of $2.85 million related to
asbestos abatement of the former Main Plant
Building nor future costs for remedial action related
to the Asbestos Landfills. Accordingly, ARCO’s Rule
52 motion is GRANTED as to CFAC’s asbestos costs.
B.
Section 10
38.
ARCO presents two defenses based on the
language contained in Section 10 of the Acquisition
28a
Agreement. ARCO first argues that Section 10(a) acts
as a covenant not to sue, barring CFAC’s claims for
contribution and recovery under CERCLA and
CECRA.1 Failing that, ARCO argues that Section
10(b) shifted liability for pre-closing environmental
conditions to CFAC at the time of the sale. These
arguments are discussed in turn.
1. Covenant Not to Sue
39.
Pursuant to Section 10(a), CFAC agreed
that it “may not make a claim with respect to . . .
(B) Seller’s indemnity referred to in clause (iii) of this
Section 10(a) at any time after August 31, 1990.” As
mentioned above, § 10(a)(iii) states that ARCO agreed
to “indemnify and hold [CFAC] harmless from and
against: . . . (iii) All damages, losses, and out-of-pocket
expenses (including attorneys’ fees) caused by or
arising out of obligations or liabilities relating to the
Smelter Business resulting from events or conditions
in existence prior to the Closing Date.”
40.
ARCO characterizes this provision as a
covenant not to sue, insisting that it applies to
existing environmental liabilities prior to closing.
(See Ex. 1 § 10(a)(iii); Doc. 128 at 10–13.) In response,
CFAC argues that the covenant—to the extent there
is one—is limited to CFAC’s contractual right to seek
indemnity, not its ability to pursue a statutory right
to recovery or contribution under CERCLA or
CECRA. CFAC has the better argument.
41.
In interpreting a contract under Montana
law, a court’s job “is simply to ascertain and declare
what is in the terms or substances contained therein,
not to insert what has been omitted or omit what
1
ARCO did not make this argument in its pretrial motion
for judgment on the pleadings. (See Doc. 128 at 8 n.3.)
29a
has been inserted.” Ohio Farmers Ins. Co. v. JEM
Contracting, Inc., 386 P.3d 613, 616 (Mont. 2016).
“The role of a court interpreting a contract provision
is to ascertain and effectuate the parties’ mutual
intentions[,]” which is reflected in “[t]he clear and
explicit language of the contract.” A.M. Welles, Inc. v.
Mont. Materials, Inc., 342 P.3d 987, 989 (Mont. 2015);
AWIN Real Estate, LLC v. Whitehead Homes, Inc.,
472 P.3d 165, 169 (Mont. 2020). “[A]n ambiguity
exists only if the language is susceptible to at least
two reasonable but conflicting meanings.” Mary J.
Baker Revocable Tr. v. Cenex Harvest Sts., Coops, Inc.,
164 P.3d 851, 857 (Mont. 2007). “[I]f the language of
a contract is ambiguous, a factual determination must
be made as to the parties’ intent in entering into the
contract.” Id. “[E]vidence of the circumstances under
which the contract was made and the matter to which
it relates may [also] be considered.” Id. “However,
such evidence . . . is not admissible to add to, vary, or
contradict the terms of the contract.” Id.
42.
The plain language of § 10(a) states that
CFAC will not make a claim “with respect to” ARCO’s
“indemnity” as defined under the Agreement. As both
sides agree, CFAC is not making a claim under the
indemnification provision here. (See Doc. 128 at 11.)
Rather, CFAC’s claims are based on independent
statutory obligations that could form the basis of suit
regardless of whether CFAC had a contractual right
of indemnity against ARCO. ARCO therefore argues
that “claim” covers any type of claim so long as it is
related to the matters covered by the indemnity
provision. CFAC, on the other hand, insists “claim” is
limited to an indemnification claim under the
Agreement. Because only CFAC’s interpretation is
30a
reasonable, the provision is not ambiguous and does
not foreclose the present suit.
43.
ARCO relies on several out of jurisdiction
authorities to argue that “with respect to” must be
broadly construed to include any related matter. (See
Doc. 128 at 10–12.) In doing so, however, ARCO
ignores the fact that it is essentially arguing that
CFAC waived its statutory right to bring a suit under
CERCLA. To be sure, statutory rights created for a
private benefit can be waived by contract. See
Collection Bureau Servs., Inc. v. Morrow, 87 P.3d
1024, 1028 (Mont. 2004); Mont. Code Ann. § 1–3–204.
But the waiver of statutory rights requires specificity
as “waiver is the intentional and voluntary
relinquishment of a known right, claim or privilege.”
Morrow, 87 P.3d at 1028–28.
44.
Thus, to bar CFAC’s claims, the language
“with respect to” must be read to specifically waive
independent statutory claims beyond those arising
from
the
indemnification
provision
itself.
Considering ARCO’s own argument that “with
respect to” broadens, rather than narrows, the scope
of contractual language, such a reading is not tenable.
45.
Because the broad waiver envisioned by
ARCO is not sufficiently pointed to effectuate a
waiver of CFAC’s right to sue for recovery or
contribution under CERCLA or CECRA under the
plain language of the provision, § 10(a) does not bar
the present lawsuit.
46.
Although
the
plain
language
is
unambiguous, even if the Agreement’s “with respect
to” language was sufficient to create an ambiguity,
the extrinsic evidence shows that CFAC did not waive
its statutory rights. The parties’ conduct shows that
31a
CFAC believed it needed to bring an indemnification
claim by 1990, not necessarily any claim.
47.
“Where an ambiguity in a contract exists,
the court may turn to extrinsic evidence to determine
the intent of the parties.” Ophus v. Fritz, 11 P.3d
1192, 1196 (Mont. 2000). At trial, the parties
presented evidence surrounding the Acquisition
Agreement. More specifically, ARCO presented
testimony of John Lucas, a former ARCO in-house
lawyer, and Subdoh Das, a former ARCO
environmental manager. CFAC did not present any
witnesses on this issue. Both parties offered several
documentary exhibits, including correspondence
leading up to the 1985 sale and following the
acquisition between 1985 and 1990. That evidence is
described below. As stated earlier, neither party
sought proof from a critical witness both as to the
CFAC acquisition and the contracts at issue, Brack
Duker.
i.
The Sale
48.
The signatories to the 1985 Acquisition
Agreement were Claude Goldsmith on behalf of
ARCO and Brack Duker on behalf of Montana
Aluminum Investors Corp. (Agreed ¶ 56; Ex. 1.)
Claude Goldsmith is deceased and no one remaining
at ARCO has personal knowledge of the Acquisition
Agreement. (Johnson.) While Duker is alive, (see
Doc. 42 at 29), he was not called as a witness at trial.
49.
Duker, who became a principal of Montana
Aluminum Investors Corp. and later CFAC, was in
charge of divesting the Columbia Falls smelter when
he worked at ARCO. (Das; Lucas.)
50.
At the time of the sale, there were other
companies potentially interested in acquiring the
32a
Site, such as Reynolds and Kaiser (other aluminum
smelters). (Das.) While Das did not have any direct
contact with Duker, Das got the impression that
Duker actively tried to discourage a third-party sale
in order to acquire the facility as a new going concern.
(Das.)
51.
That new concern included several existing
ARCO employees, such as Jerome Broussard, Thomas
Payne, Donald Ryan, and Ken Reick. (Compare Ex.
30 (details the organizational structure under ARCO)
with Ex. 1225 (details the organizational structure
under CFAC).)
52.
ARCO ultimately sold the facility to
Montana Aluminum Investors Corp., its former
employees, for $1.00. (See Exs. 241, 243, 244.)
53.
The sale was not without benefit to ARCO,
however, as the company had decided to “withdraw
from the primary aluminum business” and was going
to either sell or liquidate the facility. (See Exs. 244,
245.) Despite the sale price of $1.00, ARCO would
have lost more money liquidating the facility than
selling it to Montana Aluminum Investors Corp. (See
Ex. 112 at 5, 10 (projecting savings of $7 million).)
54.
Because the Agreement was between ARCO
and its own divestiture team, there is no basis for
construing the provisions at issue for or against a
particular party. AWIN Real Estate, LLC, 472 P.3d
at 171 (rejecting principle that contract should be
construed against drafter as an “absolute rule”).
ii. Subsequent Conduct
55.
Other than the above, much of the extrinsic
evidence presented at trial regards the parties’ postcontract conduct, that from 1985 to 1990. More
specifically, ARCO presented evidence that CFAC
33a
(1) sought to amend the Acquisition Agreement in
1986 and (2) made several environmentally related
indemnification demands prior to 1990.
56.
“Where the language of a contract is
doubtful and ambiguous, the conduct of the parties
under the contract is one of the best indications of
their true intent.” Waiters v. City of Billings, 451 P.3d
60, 67 (Mont. 2019) (cleaned up); see also Ophus, 11
P.3d at 1196 (“The practical interpretation of a
contract, which the parties placed upon it by their
course of conduct, is entitled to great, if not
controlling influence in ascertaining what they
understood by its terms.”).
57.
In this case, CFAC’s post-contract conduct
shows that while it believed it could not bring an
indemnification claim against ARCO after 1990, it did
not necessarily believe it was barred from bringing a
statutory claim.
58.
In 1986, CFAC sought to amend the
Acquisition Agreement to “waive ARCO’s August 31,
1990 deadline for [CFAC] making of claims under
§ 10(a)(iii) of the Agreement for all claims related to
environmental hazards,” among other things. (Ex. 3;
Lucas.)
59.
The proposed amendment also requested
that ARCO “acknowledge[ ] and accept[ ]” the
environmental claims CFAC had been attempting to
assert against ARCO under the terms of the
indemnification provision. (Ex. 3; Lucas.) The draft
amendment required ARCO to accept such claims
even if “the nature, scope and extent” of the claim was
not known by the August 31, 1990 deadline
and no actual claim had been made against CFAC
before August 31,1990. (Ex. 3; Lucas.) The proposed
34a
amendment specifically references government and
state ordered remediation, (see Ex. 3 at 4), but stops
short of addressing statutory obligations. To the
contrary, the references therein once again cite the
parties’ contractual indemnification obligations.
60.
Lucas, who received the draft amendment
from CFAC, testified that the proposed amendment
was “completely inconsistent with the fundamental
nature of the” Acquisition Agreement, which was that
ARCO’s liability ended on August 31, 1990. Thus,
ARCO did not agree to the amendment. (Lucas.)
61.
From 1985 through 1990, CFAC also made
a series of indemnification demands on ARCO,
specifically attempting to assert indemnity claims for
costs related to SPL in the landfills, cyanide and
fluoride in the groundwater, and other environmental
issues that are the subject of the current lawsuit.
(Lucas.)
62.
The primary person who responded to these
indemnification demands for ARCO was Lucas and
the primary persons who made these indemnification
demands for CFAC were Duker and Payne. (Lucas;
see Ex. 4.)
63.
On January 4, 1988, Payne, on behalf of
CFAC, sent a letter to ARCO, copying Lucas, advising
ARCO that EPA had visited the Site and discussed
“past practices and closed disposal practices” with
individuals at CFAC. (Ex. 5 (letter is misdated as
1987); Lucas.) Payne also stated that “per section
10(a)(iii), we will look to ARCO to indemnify
[Montana Aluminum Investors Corp.] and CFAC for
any expenses from this matter which result from
conditions in existence prior to September 10, 1985.”
(Ex. 5; Lucas.) In this letter, CFAC took the position
35a
that the Acquisition Agreement’s indemnification
obligations extended to pre-1985 environmental
liabilities. (Lucas.)
64.
On April 12, 1988, Payne, on behalf of
CFAC, sent a letter to ARCO, copying Lucas, stating
that it was “providing ARCO” with notice “concerning
potential Superfund cleanup requirements” at the
Site “[i]n accordance with the” Acquisition
Agreement. (Ex. 6; Lucas.) Specifically, the letter
advised that a consultant with EPA requested
information about CFAC’s “waste streams prior to
their ‘sampling [of] the plant’ ” and that EPA was
planning a site investigation. (Ex. 6; Lucas.)
65.
On April 18, 1988, Don Ryan of CFAC sent
a letter to EPA regarding the potential listing of the
Site on the National Priority List, stating, “Any
liability for these sites would be the responsibility of
ARCO.” (Ex. 7; Lucas.)
66.
On April 29, 1988, Lucas wrote to Payne to
dispute contentions CFAC had made to EPA that all
environmental liability for the Site would be ARCO’s
responsibility, stating that “[a]ny potential liability
on ARCO’s part will depend upon a combination of the
factual context as it evolves,” but that he did “not wish
to leave an impression that ARCO does not intend to
meet its contractual obligations to Montana
Aluminum Investors Corp. or that it is, at this point,
disclaiming all responsibility with respect to future
enforcement obligations which may be instituted with
respect to the Columbia Falls site.” (Ex. 8; Lucas.)
67.
On November 29,1988, Payne again wrote a
letter to ARCO, copying Lucas, advising it that
pursuant to the Acquisition Agreement, “[Montana
Aluminum Investors Corp.] is providing ARCO with
36a
notice of EPA activities regarding spent potliner
wastes” at the Site and that EPA had now listed SPL
from primary aluminum reduction as a hazardous
waste. (Ex. 10; Lucas.) Lucas testified that Payne
was “once again, giving notice of a possible indemnity
claim to [ARCO] based on the spent potliner that
[ARCO] may have disposed of at the site.”
68.
On August 24, 1990, days before the August
31, 1990 expiration of ARCO’s indemnity, Duker
copied Lucas on a letter to ARCO in which CFAC
stated it was “making a claim for damages, losses, and
out-of-pocket expenses (including attorneys’ fees)
caused by or arising out of the Columbia Falls
Aluminum Reduction Facility resulting from events
or conditions in existence prior to September 10, 1985
relating to environmental hazards which have been
identified at the plant site in Columbia Falls.” (Exs.
11, 12; Lucas.)
69.
After comparing the indemnity claims that
Duker made in his August 24, 1990 letter with
CFAC’s complaint in this case, Lucas confirmed that
many of the claims concerned the same
environmental issues, including cyanide and fluoride
in groundwater, cyanide and fluoride under the Wet
Scrubber Sludge Pond (“WSSP”), SPL in the West
Landfill, and contamination of the North and South
Percolation Ponds. (Lucas; compare Ex. 12 with Doc.
1 at ¶¶ 85–87, 99–100, 116–18, 108–12, 130.)
70.
On September 14, 1990, Floyd George, on
behalf of ARCO, wrote Duker a letter in response to
the August 24 indemnification demand. (Ex. 14.)
George was the individual tasked with keeping track
of divested assets that ARCO had sold in previous
years and he was monitoring the CFAC Agreement.
(Lucas.) Lucas assisted in drafting this letter for
37a
George’s signature. (Lucas.) In that letter, ARCO
explained that “[t]o be a claim under the Agreement,
it is necessary that by August 31, 1990, CFAC have
sustained damages, losses, or out-of-pocket expenses
caused by or arising out of an obligation or liability
relating to the smelter business resulting from
conditions existing as of the time of the sale.” (Ex. 14;
Lucas.) Because no such damages were listed in the
letter, ARCO asserted that CFAC had no valid claim.
(Ex. 14; Lucas.) The letter further explained that:
Such a potential, contingent environmental
risk or hazard, even if it were to occur in the
future, is not a claim covered within the
provisions of Section 10(a).
The indemnity sought by your letter is of an
entirely different type than that contained
in the [Acquisition] Agreement. Essentially,
CFAC is seeking indemnity for all liabilities
which might at any time arise out of conditions
existing at the site as of the date of sale. This
would be a continuing obligation of much
broader scope than that bargained for by the
parties. It would have required vastly different
language in the indemnifying clause. Instead,
what Montana Aluminum Investors Company
[sic] received was a limited indemnity designed
to protect it during the first five years of
operations against losses and other expenses
arising out of liabilities and obligations
resulting from conditions existing as of the time
of sale. This is entirely consistent with the
basic nature of the arrangement, whereby
ARCO sold the Columbia Falls assets for one
dollar. . . .
38a
The items identified in your letter do not
constitute claims within the meaning of the
Agreement and are not properly chargeable to
ARCO under the Agreement . . . .
(Ex. 14: Lucas.) This letter shows that ARCO did not
believe certain future environmental contingencies
were covered by the indemnification agreement.
71.
Nor did ARCO believe that CFAC was going
to honor the five-year expiration of the
indemnification terms. Das was the environmental
manager for ARCO when ARCO sold the CFAC plant
and was charged with assessing the potential
environmental liabilities that CFAC might assert
during the five-year period during which ARCO had
promised to indemnify CFAC. (Das.)
72.
Das’s conversations with his bosses during
this time (1988–89) indicated a concern that CFAC
would not take the five-year environmental
responsibility seriously but would continue to return
to ARCO for things it had agreed to forego. Das
therefore asked his coworkers to take copious notes
regarding all the facts and figures at that time. (Das;
see Ex. 76.)
73.
When ARCO’s indemnification obligation
expired on August 31, 1990, Das authored a
memorandum to ARCO’s management advising that:
“There should be a letter written by ARCO to [CFAC]
effectively giving notice that the five (5) year
obligation on environmental concerns has ended
effective August 31, 1990.” (Ex. 75; Das.) Based on
the proof presented at trial, no such letter was written
despite ARCO’s knowledge of CFAC’s contrary
understanding of its rights and obligations under the
Agreement.
39a
74.
And, unsurprisingly, CFAC continued to
make demands after 1990. On several occasions after
1990, CFAC sent letters to ARCO seeking
indemnification for environmental issues, for
example “the leaching of cyanide into the
groundwater from the spent pot liner placed in the
landfill.” (Ex. 274 (May 23, 1994); see also Ex. 269
(Apr. 8, 1993).) ARCO rejected these indemnification
demands for the same reasons articulated in the
September 14, 1990 letter. (See Exs. 1269, 1270.)
75.
Ultimately, however, CFAC did not assert a
right to sue ARCO under any theory other than for
indemnity under the Acquisition Agreement until the
run-up to this lawsuit. To the contrary, when the
parties discussed CERCLA or CECRA liability, it was
in the context of the non-transferrable liability that
the statute authorized regulators to impose rather
than a private-party claim. (See, e.g., Ex. 271, at
CFAC0442020; Ex. 269.)
iii. Knowledge
of
Environmental
Conditions
76.
In addition to the evidence discussed above,
documents related to the sale show that both sides
were equally aware of the outstanding environmental
conditions. For example, the following documents
were prepared by the ARCO Divestiture team, under
Duker:
a. A 1984 Offering Memorandum, which
stated: “Two waste landfills are currently on the
facility property. Spent pot linings from the
reduction process are the main waste disposed onsite. As a result of the Bevel [sic] Amendment, a
mining waste exemption from the Resource
Conservation and Recovery Act (RCRA), these
40a
spent pot linings are considered non-hazardous.”
(Ex. 231 at 15.)
b. A 1984 document titled “Columbia Falls
Divestiture Review: Environmental, Safety and
Health Summary” stated: “Two on-site landfills
are currently in operation: one is a sanitary
landfill for non-hazardous wastes; the second is for
the disposal of spent cathodes. (Spent cathode
materials are likely to receive future classification
as hazardous wastes by EPA.) Three closed on-site
landfills are present: the first was a sanitary
landfill; the second contains spent cathodes; and
the third is believed to have been used for the
disposal of all plant wastes, possibly including
hazardous wastes. An open, but inactive, calcium
fluoride sludge pond is also present.” (Ex. 1181.)
c. A 1984 Due Diligence Review Report of the
operations at the plant conducted by the ARCO
Divestiture team found: “One groundwater
monitoring well (#TW1) has elevated levels of
cyanide and fluoride . . . . Two on site landfills are
currently in operation . . . . The second is for the
disposal of spent cathodes from the potlines. This
material is currently classified as non-hazardous
but is expected to be reclassified as hazardous at
some future date . . . . There are three closed
landfills at the facility . . . the second contains
spent cathode materials.” (Ex. 71 at 7–8; Das.)
77.
Publicly available documents also described
the environmental issues at the Site. For example,
the August 10, 1984 public notice of the issuance of
the Montana Groundwater Pollution Control System
Permit for the Site stated: “The groundwater under
the facility may be somewhat contaminated with
41a
cyanide and fluoride from historic operations at the
site.” (See Ex. 1192 at 10.)
iv. Conclusion
78.
The plain language of the Agreement
cannot be read as broadly as ARCO insists because
waivers of statutory rights must be specific under
Montana law. As a result, “claims” as outlined in
§ 10(a) do not include independent, statutory claims.
79.
But even if ARCO’s reading were tenable,
making the provision ambiguous, the extrinsic
evidence shows only that while the parties were both
aware of the environmental conditions of the Site and
environmental conditions fell within the Agreement,
CFAC took every opportunity to attempt to hold
ARCO liable under the terms of the indemnification
provision for the existing environmental conditions at
the Site. That evidence does not show that either side
intended the Agreement to foreclose all future
statutory claims.
80.
As a result, ARCO’s claimed covenant not to
sue does not foreclose the present claims.
2. Assumption
of
Environmental
Liabilities
81.
ARCO’s second defense is that Section 10(b)
shifted liability for pre-closing environmental
conditions to CFAC at the time of the sale.
82.
In 2019, ARCO sought judgment on the
pleadings on the ground that CFAC assumed all
environmental liabilities at the Site once ARCO’s
indemnification obligation expired. (See Doc. 34
at 11.) While ARCO correctly argued that such an
assumption of liability was permissible under the law,
(see Doc. 49 at 5–6), it was previously determined that
the Agreement was ambiguous concerning whether
42a
its reference to costs “relating to the operation and
Smelter Business” included environmental liabilities
and whether CFAC assumed those liabilities after
ARCO’s indemnity obligation expired, (see id. at 12–
14). That finding meant that extrinsic evidence was
necessary to ascertain the intent of the parties. (Id.
at 15.)
83.
Under Montana law, an indemnity
agreement is interpreted like any other contract and
a court’s job “is simply to ascertain and declare what
is in terms or in substance contained therein, not to
insert what has been omitted or to omit what has been
inserted.” Ohio Farmers Ins. Co., 386 P.3d at 616
(quoting Mont. Code Ann. § 1-4-101). “To the extent
that there is ambiguity, indemnity clauses generally
should be liberally construed in favor of the party
intended to be indemnified.” A.M. Welles, Inc., 342
P.3d at 989 (internal quotation marks omitted).
84.
As shown above, the evidence confirms the
parties intended the indemnity provisions in Article
10 of the Acquisition Agreement to cover
environmental liabilities. The remaining question is
whether the parties also intended to shift all liability
for environmental conditions that existed at the time
of the sale but resulted in damages, losses, and outof-pocket expenses to CFAC after August 31, 1990.
85.
Neither ARCO nor CFAC presented
extrinsic evidence on this point. But, contrary to
ARCO’s position, that absence weighs in favor of
CFAC. As explained in this Court’s previous order,
despite Montana’s admonition to liberally construe
indemnification provisions, see A.M. Wells, Inc., 342
P.3d at 989, a party cannot assume CERCLA liability
passively; either the contract must specifically
provide for such an assumption or it must be so broad
43a
as to leave no question as to that assumption. This
Agreement does neither. To the contrary the evidence
shows that there was extensive correspondence
between ARCO and Montana Aluminum Investors
Corp. (via Duker) in 1985 that evaluated a variety of
costs, liabilities, and savings under both a
shutdown/liquidation scenario and the terms of
Duker’s offer; however, that correspondence made no
mention whatsoever of existing, future, or contingent
environmental liabilities. (See Exs. 112, 237, 238,
240, 241, 242, 243, 849.)
86.
Moreover, in 1985, ARCO was a
sophisticated party and the subject of several
CERCLA lawsuits, including at least one in Montana,
and had also been deemed a CERCLA potentially
responsible party (“PRP”) at 24 sites by EPA and/or
individual states. (See Ex. 1017 at ARC-0000565253.)
87.
While the evidence shows both parties were
aware of the environmental conditions at the Site,
neither the plain language of the Agreement nor the
parties’ conduct shows that they intended for CFAC
to assume all the environmental liabilities for the Site
as part of its post-closing operations.
3. Conclusion
88.
Because neither the language of the
Agreement nor the parties’ intent as distilled from
extrinsic evidence shows that CFAC agreed to
forego a CERCLA claim related to environmental
conditions or assumed all such liability, resolution
on the merits can proceed.
Nevertheless, the
circumstances surrounding the 1985 Agreement
support allocating the greater cleanup responsibility
to CFAC.
44a
IV.
SITE OVERVIEW
A.
Waste Streams
89.
Several different waste streams were
created during the course of aluminum production at
the Site. Approximately 40 chemicals were identified
as contaminants of potential concern. (Ex. 134 at
25.)2 Of primary concern here are cyanide and
fluoride in the groundwater, (Ex. 134 at 25–26), as
well as polycyclic hydrocarbons (“PAHs”) and
polychlorinated biphenyls (“PCBs”) in the soils, (Ex.
134 at 27–28). (See also Ex. 868 at 33–39.)
90.
Cyanide, fluoride, arsenic, and PAHs are
each “hazardous substances” pursuant to 42 U.S.C.
§ 9601(14). (Agreed COL ¶ 6.)
1. Spent Potliners (“SPL”)
91.
Over the lifetime of an aluminum pot,
sodium in the cryolite bath gradually penetrated the
potliner in the pots, causing the carbon to swell and
eventually fail. Periodically, a pot was taken out of
production and the spent potliner (“SPL”) was
removed from its steel shell and insulating brick layer
and replaced with a new carbon lining. (Agreed ¶ 13;
Ex. 134 at 45–46.)
92.
The SPL consisted of a thick layer of carbon
bonded to an insulating brick layer that had become
contaminated with cyanide, fluoride, sodium, and
aluminum by the time of its removal. The fluoride
and sodium in the SPL came from the sodium fluoride
2
At the time the parties filed their proposed findings of fact
and conclusions of law, the Final Feasibility Study had not yet
been approved. (See Ex. 868.) As a result, many of the citations
in their proposed findings are to the Remedial Investigation
Report. The findings in the two documents are, with minor
exception, consistent with one another.
45a
(cryolite) bath, and the cyanide formed in the cathode
as a side chemical reaction during aluminum
production. (Agreed ¶ 14; Ex. 134 at 45–46.) When
exposed to rainwater, the cyanide and fluoride in the
SPL can leach into the groundwater. (Baris.)
93.
EPA first proposed SPL for listing as a
hazardous waste pursuant to the federal Resource
Conservation and Recovery Act, 42 U.S.C. §§ 6901 et
seq. (“RCRA”) in 1980, but before that listing became
effective EPA suspended the listing of SPL because it
determined SPL was excluded from regulation under
the recently enacted Solid Waste Disposal Act
Amendments of 1980. (Ex. 855.) EPA then relisted
SPL as a hazardous waste in September 1988, (Ex.
1271), which became effective in Montana when the
State of Montana classified SPL as K088 hazardous
waste under RCRA, effective March 15,1991, (see Ex.
258). (Agreed ¶ 15.)
94.
Between approximately 1960 through
approximately 1980, ARCO disposed of between
129,000 and 135,000 tons of SPL in two unlined
landfills: the West and Center Landfills. (Baris; Ex.
90; Ex. 226 at 2.) Both ARCO and CFAC also disposed
of SPL in a lined landfill, the East Landfill, from 1980
to 1990. (See Ex. 275 at 2.) After 1990, SPL was
shipped off-Site for disposal. (Baris; Ex. 134 at 46; see
also Exs. 254, 255.)
95.
SPL at the Site was sampled at various
times. Samples taken during ARCO’s tenure in 1980
showed 36 milligrams per liter (mg/L) of cyanide in
pot bottoms from a landfill, 16 mg/L of cyanide in SPL
from a carbon pile face, and 0.42 mg/L of cyanide in
crushed pot bottom extract. (Ex. 126 at 67.) During
CFAC’s tenure, samples of “typical” SPL at the Site
were taken in January 1988 and March 1992 which
46a
were found to contain 0.1 percent cyanide and 16
percent fluoride. (Exs. 249, 261; Baris.)
2. Wet Scrubber Sludge
96.
Operations of the aluminum reduction pots
generated air emissions containing fluoride, PAHs,
and other contaminants.
For example, PAHs
associated with the electrolytic process would migrate
out from the potline building into the atmosphere.
From there, they would disperse across the Site and
be deposited on soil. ARCO controlled emissions from
potlines using wet scrubbers until the late 1970s,
when it replaced them with dry scrubbers. (Baris; Ex.
134 at 46.) Unlike with the wet scrubbers, residue
from the dry scrubbers was recycled back into the
aluminum reduction process. (Ex. 1177 at ARC00002803.)
97.
It is not possible to distinguish between
PAHs produced during either the ARCO or CFAC
period. (Baris).
98.
ARCO landfilled the sludge generated from
its wet scrubbers at the Wet Scrubber Sludge Pond
(“WSSP”). An analysis of the sludge indicated that it
contained approximately 80 percent calcium fluoride
on a dry-weight basis, and also contained calcium
oxide, magnesium oxide, sodium oxide, and iron
oxide. (Agreed ¶ 16; Ex. 134 at 46.) ARCO disposed
of sludge from approximately 1955 until 1977, when
the wet scrubbers were decommissioned. (Wright.)
ARCO did not dispose of SPL in the WSSP. (Wright.)
3. Soaking Pits
99.
Between approximately 1964 and 1977, as
part of its SPL removal process, ARCO constructed
pits at the Site at the northern end of the Main Plant
Area in which it placed spent pots and filled them
47a
with water to help loosen and release the SPL
(holding each pot for about 8 hours to also cool them).
Water used to release the liner, which became
contaminated with cyanide and fluoride, was drained
to the Northeast and Northwest Percolation Ponds
(“North Percolation Ponds”). (Exs. 122A, 122B, 814,
815, 827; see also Ex. 250 at 16.)
100. ARCO processed an estimated 1,800 pots
through the soaking pits, using about 100,000 gallons
of water for each pot. As a result, roughly 180 million
gallons of water passed through the soaking pits to
the North Percolation Ponds during their
approximately 14 years of operation. (Ex. 815; see
also Ex. 260 at 22.)
101. This water contained hazardous substances
including cyanide, fluoride, and PAHs. Given
attenuation and groundwater flows, however, the
water ARCO disposed of in the North Percolation
Ponds is no longer contributing cyanide and fluoride
to the groundwater today. (Baris; Otis.)
4. Other Wastes
102. Besides the SPL and the wet scrubber
sludge, operations at the Site resulted in the
generation of a variety of wastes which were disposed
of at different areas, including the North Percolation
Ponds, the Industrial Landfill, the Asbestos Landfills,
Soils North of Main Plant Building and immediately
adjacent to the landfills, and the South Percolation
Ponds. Additionally, drummed liquid wastes were
stored in the Former Drum Storage Area prior to
offsite shipment and disposal. (Agreed ¶ 17; Ex. 134
at 28–30.)
103. Liquid waste generated as a result of the
aluminum reduction process and stormwater were
48a
discharged to the North Percolation Ponds. (Agreed
¶ 18; Ex. 134 at 46.)
104. Throughout the Site’s operations, landfills
at the Site were used to dispose of plant wastes,
including aluminum dross, solvents, potliner
refractory wastes (non-hazardous)—likely the scrap
calcined petroleum coke, ore, cryolite (including
aluminum fluoride), brick, concrete, scrap metal,
wood, used oil, and plant trash and other municipal
solid waste. (Ex. 134 at 46.) Additionally, spills
sometimes occurred during the transportation and
transfer of industrial material for use at the facility,
and of waste products. (Williams; Batson.)
5. Technological Advancements
105. ARCO made several upgrades to the facility
between 1977 and 1981 that improved its
environmental performance.
106. In 1980, ARCO completed a major capital
expenditure program at the facility, at a cost of $32
million, to reduce fluoride emissions to meet revised
emissions standards, and it made an additional
capital expenditure of $5 million for the installation
of a dry scrubbing system to maintain compliance
with the standards. (Williams: Ex. 231.)
107. ARCO also completed the installation of
Sumitomo process technology at the aluminum
reduction plant in 1981 at a cost of approximately $42
million, which substantially reduced air emissions
and power consumption, improved materials
handling, and reduced the volume of SPL generated
by the facility. (Williams; Ex. 1177 at ARC-00002803;
Ex. 18 at 9; see also Exs. 221, 222, 224, 225, 228.)
49a
6. Permitted Discharges
108. During historical facility operations,
wastewater generated because of the aluminum
reduction process was discharged to several surface
impoundments at the Site, from which it then
discharged indirectly to groundwater.
These
discharges were undertaken in accordance with
several permits issued by the Montana Department of
Health and Environmental Sciences (“MDHES”),
subsequently renamed the Montana Department of
Environmental Quality (“MDEQ”). (Wright.)
109. ARCO applied for a groundwater discharge
permit sometime in or before May 1983. (See Ex. 825.)
MDHES inquired about the source of “elevated
cyanide and fluoride levels in some of the test wells,”
(Ex. 826), and was informed it was likely from the
“past practice” of discharging pot soaking to the North
Percolation Ponds, (Ex. 827).
110. On September 17, 1984, MDHES issued
Ground Water Pollution Control System Permit
Number MGWPCS-0005 to ARCO, allowing certain
discharges to the surface impoundments and
indirectly to groundwater, prohibiting degradation of
groundwater beyond the property boundary, and
requiring, among other things, submission of a
hydrogeologic report within one year that would
summarize groundwater conditions at the Site and
make recommendations regarding the existing
monitoring system and continuing management of
wastes present at the Site. (Ex. 1218; Ex. 134 at 46;
see also Ex. 250 at 16.) Related to this permit and
discussed in more detail below, both parties
discharged leachate onto the WSSP during their
respective tenures. ARCO did so twice, and CFAC did
so three times.
50a
111. In 1993, CFAC applied for a Montana
Pollutant Discharge Elimination System (“MPDES”)
permit for the groundwater contaminated by
historical SPL disposal practices, released via a seep
to the Flathead River. On May 1, 1994 MDHES
issued Permit No. MT-0030066, which authorized
process wastewater discharges to specified receiving
ponds and to groundwater. The permit included
specific conditions requiring CFAC to cap the West
Landfill and investigate Site hydrology to track the
cyanide concentrations in groundwater from the
landfill to the Flathead River. (Wright; Ex. 272; Ex.
134 at 46.) CFAC placed a synthetic cap on the West
Landfill
and
continued
to
track
cyanide
concentrations in groundwater. (Wright; Ex. 134 at
52; Ex. 275.)
112. Permit No. MT-0030066 was reissued in
1999, (Exs. 272, 273), and terminated in 2019,
(Wright; Ex. 285).
113. Related to the 1999 permit, in August 1991,
MDEQ performed a groundwater inspection at the
Site, which concluded that groundwater was
contaminated and that elevated levels of cyanide were
present in the seeps that were discharging from the
Site into the Flathead River, which MDEQ
determined was an unauthorized discharge of
pollutants by CFAC. (Ex 62 at 1; Wright.) While
CFAC agreed to increase monitoring and install new
sampling wells, those seeps remained active. As a
result, on December 4, 1996, EPA issued a Notice of
Violation to CFAC for violation of Section 301(a) of the
federal Clean Water Act for the unauthorized
discharge of cyanide-contaminated seepage from
the Site into the Flathead River. (Ex. 64; Wright.)
And, on January 13, 1997, MDEQ issued a Notice
51a
of Violation to CFAC for violation of the Montana
Water Quality Act, Mont. Code Ann. § 75-5-605,
for the unpermitted discharge of industrial waste
to the Flathead River. (Ex. 64; Wright.) Instead of
addressing the cyanide-contaminated seeps, CFAC
requested and obtained permission from MDEQ to
modify its MPDES permit to allow for a “mixing zone”
in the Flathead River, wherein MDEQ would allow
cyanide concentrations in the Flathead River to
exceed State water quality standards as a result of
the discharge of cyanide-contaminated seepage from
the CFAC Site. (Ex. 1242; Wright.)
114. On July 25, 2014, MDEQ issued a revised
MDPES permit to CFAC that effectively eliminated
the mixing zone that would have allowed CFAC’s
exceedances of the cyanide water quality standard
in the Flathead River to continue (Ex. 66 at ¶ 125–27;
Wright.)
CFAC appealed, but the permit was
terminated on April 17, 2019 because of the closure
of the facility. (Ex. 217; Wright.) However, the
discharge of cyanide-contaminated seepage from the
Site into the Flathead River continues today.
(Wright.)
B.
115.
Site
Area
West
Landfill
Site Conditions
There are eleven Site-specific areas at issue:
User:
Years of
Operation
ARCO:
approx.
1960-1980
Construction Use /
Type of
Waste
Unlined
Used for
bottom
disposal
Earthen cap
of: SPL
1981
(1960Clay cap 1992 1970)
52a
Site
Area
User:
Years of
Operation
Center
Landfill
ARCO:
approx.
1970-1980
East
Landfill
ARCO:
1980-1985
CFAC:
1985-1990
Wet
Scrubber
Sludge
Pond
(“WSSP”)
ARCO:
approx.
1955-1979;
discrete
disposal
events
between
1983-1984
CFAC:
discrete
disposal
events
Construction Use /
Type of
Waste
Synthetic cap Sanitary,
municipal
1994
solid waste
(steel, wood,
strapping,
scrap from
shops)
Unlined
Used for
bottom Clay
disposal of
SPL,
cap 1980
sanitary,
scrap from
shops
Clay liner
Used for
disposal of
bottom
SPL (1980Clay cap &
synthetic cap 1990)
1990
Unlined
User for
bottom
disposal of:
Earthen cap
calcium
fluoride wet
1981
scrubber
sludge
(approx.
1955-1979);
leachate
(1983, 1984,
1987, 1989,
1994); pot
diggings
53a
Site
Area
Former
Drum
Storage
Area
South
Percolation
Ponds
Northeast
Percolation
Ponds
User:
Years of
Operation
between
1987-1994
Construction Use /
Type of
Waste
(1993-1994,
partially
excavated
1998)
ARCO:
Earthen
Used as
approx.
unlined
storage
area for
1980-1985
storage pad
drums of
CFAC: 1985RCRAunknown
listed
(before
wastes for
1996)
shipment
offsite
ARCO:
Unlined
Used to
receive
1955-1985
bottom
wastewater
CFAC:
from:
1985-2009
sewage
treatment,
cooling of
equipment
ARCO:
Unlined
Used to
receive
1955-1985
bottom
wastewater
CFAC:
from
1985-2009
operations
in Main
Plant Area,
including
water from
SPL
54a
Site
Area
User:
Years of
Operation
Northwest
Percolation
Ponds
ARCO:
1970s-1985
CFAC:
1985-2009
Soils
North of
Main
Plant
Building
ARCO:
1955-1985
CFAC:
1985-2009
Industrial ARCO:
Landfill 1980-1985
CFAC:
1985-2009
Construction Use /
Type of
Waste
soaking
operations
(1964-1977)
Assumed
Used to
unlined
receive
wastewater
bottom
from
operations
in Main
Plant Area,
including
water
from SPL
soaking
operations
(1964-1977)
(Soils near
Used as
operations
facility
area; not an
operations
intended
area (no
disposal area) intentional
disposal)
Assumed
Used for
unlined
disposal of:
scrap
bottom
metal,
Closed 2009
wood,
municipal
solid
waste
55a
Site
Area
User:
Years of
Operation
Asbestos ARCO: late
Landfills 1970s-1985
(North
CFAC:
&
1985-2009
South)
Construction Use /
Type of
Waste
Assumed
Used for
unlined
disposal of:
bottom
asbestos
Closed 2009
(earthen cap)
(Ex. 868 at 76.) These individual areas are discussed
in more detail below.
1. West Landfill
116. The West Landfill is located in the northern
portion of the Site, north of and adjacent to the WSSP:
56a
(Agreed ¶ 27; Ex. 848 at 7; see also Ex. 134 at 304.)
57a
117. The West Landfill comprises approximately
7.8 acres, with areal dimensions of approximately 615
feet by 600 feet. (Agreed ¶ 28; Ex. 868 at 21.) The
landfill is unlined, extends approximately 15 to 22
feet below surrounding grade and rises approximately
13 to 20 feet above grade. (Ex. 868 at 21.) Impacted
soil beneath the landfill, however, could be as thick as
115 feet. (See Ex. 868 at 21.)
118. Groundwater levels around the West
Landfill range from approximately 36 feet to 87 feet
below surrounding grade. (Ex. 868 at 21.)
119. The West Landfill was used to dispose of
SPL and other wastes (sanitary, industrial, and
reportedly solvents) through 1980, (Agreed ¶ 29),
although SPL disposal reportedly ended in 1970, (Ex.
134 at 52). The landfill was closed in 1981 with a clay
cap and a synthetic cap was added in accordance with
CFAC’s MPDES Permit No. MT-0030066 in 1994.
(Baris; Ex. 134 at 52; Ex. 868 at 21; Ex. 272.)
120. By June 11, 1980, ARCO had disposed of
approximately 61,800 tons of SPL (carbon plus
refractory) in the West Landfill. (Baris; Ex. 226 at 2.)
And, as of July 1980, detectable amounts of cyanide
and fluoride had traveled from the SPL in the West
Landfill into underlying soils. (See Ex. 1081 at 44.)
121. By April 22, 1981, ARCO had disposed of
approximately 68,000 tons of “total material” in the
West Landfill, including 410 tons of cyanide and
13,000 tons of sodium fluoride. (Baris, Ex. 90.)
122. Although no soil or groundwater samples
have been collected beneath the West Landfill, the
long-term persistence of cyanide in groundwater
directly downgradient of the landfill coupled with a
low-permeability cap in place since 1994 indicates
58a
that impacted material likely extends into and
beneath the seasonal high-water table and is serving
as a continuing source of contamination. (Baris; Ex.
868 at 22.) This is discussed in more detail in the
“Groundwater” section.
123. EPA has indicated that it is not feasible to
either leave the West Landfill as is or simply upgrade
the cap. (Baris.) Rather, the Final Feasibility Study
Report recommends a range of alternatives from the
construction of a slurry wall to excavation of the
landfill with onsite consolidation. (Ex. 868 at 150.)
2. Wet
Scrubber
Sludge
Pond
(“WSSP”)
124. The WSSP is located directly south of and
adjacent to the West Landfill. (Agreed ¶ 30; Ex. 134
at 304.)
125. The WSSP is approximately 10.8 acres in
size with areal dimensions of approximately 750 feet
by 580 feet. (Agreed ¶ 31; Ex. 134 at 52.) The total
depth of the waste material is approximately 30 feet,
half of which is above grade. (Ex. 868 at 22.)
Groundwater levels beneath the WSSP range from 60
to 105 feet below grade. (Ex. 868 at 22.)
126. The WSSP received waste material from the
wet scrubbers under ARCO from 1955 to 1980, when
they were replaced with dry scrubbers that produced
less waste. (Baris; Otis; Wright; Ex. 134 at 139.)
During this period, ARCO disposed of an estimated
450,000 cubic yards of calcium fluoride sludge or wet
scrubber sludge in the WSSP. (Baris; Ex. 88 at 7.)
127. This calcium fluoride sludge contained
fluoride but did not contain cyanide. (Wright.)
Specifically, the sludge was approximately 80 percent
calcium fluoride (CaF2) on a dry weight basis, with
59a
small amounts of calcium oxide (CaO), magnesium
oxide (MgO), sodium oxide (Na2O), and iron oxide
(Fe2O3). (Ex. 134 at 139.)
128. The WSSP is unlined, (Baris), but was
capped with an earthen cap in 1981 and revegetated,
(Ex. 868 at 22).
129. Aside from the sludge disposed of by ARCO,
two other types of disposals into the WSSP implicate
future cleanup costs. First, both ARCO and CFAC
transferred leachate to the WSSP at discrete times
to prevent overflow of the Leachate Ponds. Second,
CFAC disposed of pot digging into the WSSP in 1993
or 1994. These discharges are discussed in more
detail below.
i. Leachate
130. SPL contains cyanide and fluoride, which,
when exposed to rainwater, can generate “leachate”
containing those constituents that can then migrate
into other surface or groundwater. (Baris.)
131. After construction and expansion of
the East Landfill and its associated Leachate Ponds
in 1980–82, ARCO discovered that, despite their
capacity of 900,000 gallons, heavy seasonal
precipitation could cause the Leachate Ponds
to overflow.
(Baris; Ex. 89 at 2.)
To avoid
contamination of the groundwater during an
overflow, transfer of the extra leachate to the WSSP
was viewed as a more environmentally sound option.
(Baris.)
132. Evidence suggests that ARCO disposed of
excess leachate this way at least twice, likely in 1983
and 1984. (Baris; Exs. 99, 102; see also Exs. 51, 840;
Ex. 89 at 2.) Documents conflict as to whether these
leachate disposal events totaled 800,000 gallons of
60a
leachate each time, (Ex. 99 at 12), or totaled 80,000
gallons on one occasion and 80,000 or 100,000 gallons
on the other, (Ex. 102). There is no trial witness
with personal knowledge of the 1983 or 1984 leachate
disposal events. (Wright.)
133. ARCO did not inform the State of Montana
about its leachate disposals. But CFAC disclosed
them to MDHES, in November 1985, approximately
two months after CFAC acquired the facility. (Ex. 99
at 1.)
134. CFAC disposed of excess leachate into
the WSSP on three occasions: 1987, 1989, and 1994.
The 1987 disposal involved approximately 400,000
gallons with a cyanide contamination level of
0.479 mg/L, (Exs. 52, 53), the 1989 disposal involved
approximately 150,000 gallons with a cyanide
contamination of 3 mg/L, (Ex. 56 at 1), and the 1994
disposal involved approximately 400-500,000 gallons
with a cyanide contamination of 0.44 mg/L, (Ex. 57 at
1). CFAC received MDEQ approval for all three
discharges. (Wright; but see Williams (opining that
1994 disposal was not properly authorized).)
135. Both ARCO and CFAC used methods to
reduce contamination, such as aeration, bleach, and
UV. (Williams; Wright.) Percolation of the leachate
through the calcium fluoride sludge was also effective
in reducing both cyanide and fluoride concentrations
in the leachate disposed of by both parties. (Baris; see
Ex. 54.)
ii. Pot Diggings
136. Around 1993 or 1994, CFAC conducted an
experiment to improve pot operation, which involved
opening approximately 120 of the facility’s 600 pots to
remove “muck” consisting of undissolved alumina ore
61a
and anode carbon dust. (Baris; Ex. 58 at 4.) CFAC
then planned to “reuse” material dug out from the
pots. (Baris.) Other than these specific pots, during
this period CFAC was sending its SPL off-Site for
disposal. (Wright.)
137. In this process, a backhoe was used to
remove the material from the pots and some of the pot
diggings material (clean cryolite bath) was recycled
back into the pots. Pot digging material that could
not be re-used at the time was transported to
the closed WSSP. (Ex. 58 at 4.) These materials,
however, were not supposed to contain SPL as pot
diggings are not generally considered hazardous.
CFAC did not put a liner under the pot diggings when
they were placed, nor did CFAC put a cover on the
diggings. (Wright.) This experiment was abandoned
after digging 120 pots when it was determined the
improvements in pot operations did not justify the
efforts. (Wright.)
138. On November 12, 1997, CFAC personnel
discovered pieces of carbon in the pot diggings
material, which upon closer inspection was found to
contain both anode carbon and cathode carbon. CFAC
investigated the origin of the carbon and concluded
that, although care was used when digging the pots,
the backhoe inadvertently removed pieces of cathode
carbon pot liner along with the muck. (Wright; Ex. 58
at 4.)
139. The next day, November 13, 1997, CFAC
reported its discovery of the cathode carbon to MDEQ.
(Ex. 58 at 5.) CFAC paid a fine and was given a
violation. (Wright.)
140. Sampling results indicated that total
cyanide content of the cathode carbon was below the
62a
detectable limit of 0.05 mg/L. CFAC estimated the
size of the total pot diggings material to be 1,800 cubic
yards. However, the carbon material deemed by
MDEQ to meet the definition of K088 SPL, a listed
hazardous waste, was estimated to have a volume of
between four and six cubic yards and a total weight of
14,340 lbs. (Baris; Wright; Ex. 58 at 5.)
141. On February 23, 1998, in coordination with
MDEQ, CFAC began excavating the carbon material
from the pot diggings, completing the excavation on
April 16, 1998, and notifying MDEQ of completion.
(Baris; Ex. 58 at 5.)
142. Results of cyanide sampling at the pot
diggings location around the time of the carbon
excavation ranged from a “non-detect” result to a
maximum of 2.1 milligrams per kilogram. (Baris;
Exs. 58, 59, 60.) These cyanide concentrations are
consistent with concentrations in soil across the Site
that did not have any contamination. (Baris.) MDEQ
did not request analysis of fluoride levels. (Baris.)
143. On
October
14,
1998,
MDEQ—in
correspondence copying EPA—notified CFAC and
EPA that “the State will require no further clean-up
action for the waste pile material or soil under the
pile.” (Ex. 60; Baris.)
3. Center Landfill
144. The Center Landfill is located east of the
West Landfill, south of the Sanitary Landfill, and
west of the East Landfill. (Agreed ¶ 32; Ex. 134 at
304.) The Center Landfill is unlined. (Baris.)
145. The Center Landfill is approximately 1.8
acres in area, in a circular shape, with a diameter of
approximately 330 feet. The Center Landfill was
historically referred to as the carbon mound or carbon
63a
pile. The landfill was constructed above grade and is
approximately 15 feet above surrounding grade. The
geophysical survey indicates an approximate
thickness between 15 and 30 feet of landfill material.
Groundwater levels around the Center Landfill range
from approximately 57 feet to 139 feet below
surrounding grade. (Ex. 868 at 22.)
146. By 1980, according to internal ARCO
records, ARCO had disposed of approximately 67,200
tons of SPL at the unlined, uncapped Center Landfill.
(Ex. 226 at 2; see also Ex. 90.)
147. Around 1980, concurrent with or shortly
after construction of the East Landfill, a clay cap was
placed on the Center Landfill, as was approximately
18 inches of till. (Agreed ¶ 33; Ex. 134 at 53.)
148. Although not a primary source, the Center
Landfill is considered a secondary source of cyanide
and fluoride contamination of the groundwater. (Ex.
134 at 30; Ex. 868 at 56.)
4. East Landfill
149. The East Landfill is located on the
northeastern border of the Superfund site, directly
East of the Cedar Creek Reservoir Overflow Ditch.
It was built along with, and sits between, the lined
North Leachate and South Leachate Ponds. (Agreed
¶ 38; Ex. 868 at 23.)
150. The
East
Landfill
encompasses
approximately 2.4 acres and is 330 feet by 730 feet.
(Ex. 868 at 23.) It is approximately 30 feet above
grade, with an approximated depth of 40 feet.
(Ex. 868 at 23.) Groundwater levels around the
East Landfill are approximately 109 to 130 feet below
grade. (Ex. 868 at 23.)
64a
151. The East Landfill was built with a clay liner
and capped with a 6-inch clay layer, a synthetic cap,
and an 18-inch vegetated cover. (Baris, Ex. 868 at 23.)
152. The East Landfill was operated from 1980
to 1990 for disposal of SPL. (Ex. 134 at 53.) Both
ARCO and CFAC each disposed of SPL at this
location for approximately five years and it is
estimated that the volume of SPL in the landfill
totaled approximately 65,042 tons. (Ex. 275 at 2.)
153. However, unlike the other two landfills
where SPL was historically disposed (the West and
Center Landfills), the East Landfill is not a
contributing source to cyanide and fluoride in
groundwater. (Baris.) The cyanide and fluoride
concentrations in groundwater to the east and
northeast of the West Landfill and WSSP, and
immediately downgradient of the East Landfill,
Leachate Ponds, and Sanitary Landfill, are generally
orders of magnitude lower than those downgradient
of the West Landfill and WSSP. (Agreed ¶ 39; Ex. 134
at 140.)
154. For example, the maximum cyanide and
fluoride concentrations in groundwater immediately
downgradient of the East Landfill were 203 μg/L3 and
736 (μg/L, respectively, both in monitoring well
CFMW-023. Immediately downgradient of the West
Landfill and WSSP, cyanide concentrations ranged
from 2,060 μg/L to 11,500 μg/L and fluoride
concentrations ranged from 4,110 μg/L to 55,300 μg/L.
(Ex. 134 at 140–41.)
155. The East Landfill was also built with two
lined leachate collection ponds. (Ex. 868 at 23.)
3
Micrograms per liter.
65a
156. The North Leachate Pond is approximately
0.6 acres in size and has a Hypalon liner. This pond
received stormwater runoff and leachate from the
East Landfill and was hydraulically connected to the
WSSP by a drainage pipe. The pond was aerated to
reduce concentrations of cyanide and then closed in
1994. (Ex. 868 at 23.)
157. The South Leachate Pond is approximately
0.9 acres in size and was also constructed to receive
stormwater runoff and leachate from the East
Landfill. It was also hydraulically connected to
the WSSP.
The pond was aerated to reduce
concentrations of cyanide and then emptied in 1990
and dried, capped, and closed in 1993. (Ex. 868 at 23.)
5. Industrial Landfill
158. The Industrial Landfill is an inactive,
uncovered landfill of unknown depth located in the
northern portion of the Site, northwest of the West
Landfill and North Asbestos Landfills. (Baris; Agreed
¶ 44.) It encompasses approximately 12.4 acres. (Ex.
868 at 23.)
159. Based on aerial photography, the Industrial
Landfill began operations in the 1980s and received
non-hazardous waste and debris until landfilling
operations ceased in October 2009. (Ex. 868 at 23.)
160. The Industrial Landfill is contaminated
with PAHs. (Ex. 134 at 141.) Although the Industrial
Landfill may potentially be contributing to the PAH
detections in groundwater at the Site, fluoride
and cyanide concentration levels immediately
downgradient of the Industrial Landfill indicate that
it is not a significant contributing source to the
cyanide and fluoride in groundwater at the Site.
(Baris; Ex. 134 at 141.)
66a
161. The Industrial Landfill has been identified
as a potential remediation location to place other onsite soils after excavation. (Baris.)
6. Asbestos Landfill
162. Two areas within the Site were identified as
being former asbestos landfills: one north of the West
Landfill and one south of the East Landfill. They
were constructed in the late 1970s or early 1980s and
were used from 1993 to 2009. There is evidence of an
engineered cap or liner. (Ex. 868 at 24.)
163. Superficial sampling of surface soils shows
“there is no potential exposure for asbestos by human
receptor activity in the area.” (Ex. 134 at 141.)
However, soil-disturbing activities may expose
asbestos. (Ex. 134 at 141.)
7. Former Drum Storage Area
164. The Former Drum Storage Area was 250
feet by 200 feet and located west of the WSSP.4 (Ex.
209 at 63.)
165. The Former Drum Storage Area was used
for the temporary storage of drums of RCRA-listed
hazardous substances, primarily spent solvents, for
shipment offsite beginning in 1980. (Agreed ¶ 42; Ex.
209 at 63.) There is no indication that SPL was ever
stored in this area. (Baris.) This area was no longer
used by 1996. (Agreed ¶ 43; Ex. 1251 at 20.)
166. The surface soil of the Former Drum
Storage Area is contaminated with PAHs, metals,
cyanide, and fluoride. (Agreed ¶ 41.) However, the
decrease in concentration with depth and the absence
4
A smaller size of 60 square feet was discussed at trial. (See
testimony of Williams). The discrepancy may be attributed to
the difference in size between the area overall and the size of the
paved asphalt pad.
67a
of any observed waste materials suggest that this
area is not a primary contributor to groundwater
contamination. (Ex 868 at 56; Baris.) The cyanide
concentration levels in the soil briefly peaks
approximately 0.5 to 2 feet below surface level before
dropping off. (Baris.)
167. Potential remediation would require only
the excavation and removal of soil to other onsite
locations, such as the Industrial Landfill. (Baris.)
8. Soil North of Main Plant Buildin
This text is long and has been trimmed here. Open the source document for the complete record.
This is a copy of a public record, reproduced as it was published. It is not legal advice, and it may not be the version a court would rely on. Check the official source before you cite it.