Petition for Writ of Certiorari — Joslyn Manufacturing Company, LLC, et al., Petitioners v. Valbruna Slater Steel Corporation, et al.
Supreme Court briefJan 21, 2020
Ask Donna
What actually matters in this document.
Text
No. 19IN THE
Supreme Court of the United States
___________
JOSLYN MANUFACTURING CO., LLC AND JOSLYN CORP.,
Petitioners,
v.
VALBRUNA SLATER STEEL CORP. AND FORT WAYNE
STEEL CORP.,
Respondents.
___________
On Petition for a Writ of Certiorari
to the United States Court of Appeals
for the Seventh Circuit
___________
PETITION FOR A WRIT OF CERTIORARI
___________
JOSHUA G. VINCENT
HINSHAW & CULBERTSON
151 N. Franklin St., #2500
Chicago, Illinois 60606
(312) 704-3463
STEPHEN D. DAVIS
STEVE DAVIS LAW, P.C.
1333 Burr Ridge Parkway
Burr Ridge Illinois 60527
(630) 756-3042
CARTER G. PHILLIPS *
TIMOTHY K. WEBSTER
JENNIFER J. CLARK
SIDLEY AUSTIN LLP
1501 K Street, N.W.
Washington, D.C. 20005
(202) 736-8000
cphillips@sidley.com
Counsel for Petitioner
January 21, 2020
* Counsel of Record
QUESTION PRESENTED
The Comprehensive Environmental Response,
Compensation, and Liability Act (CERCLA), contains
two different statutes of limitations for suits to recover environmental clean-up costs: (1) a three-year limitations period for suits to recover “removal” costs;
and (2) a six-year period for suits to recover “remedial” costs. See 42 U.S.C. § 9613(g)(2)(A), (B). The
three-year period to seek removal costs starts when
the removal work is completed; the six-year period to
seek remedial costs starts when physical on-site remedial construction begins.
The terms “removal” and “remedial” are defined
terms under CERCLA. See 42 U.S.C. § 9601(23), (24).
“Removal” activity generally consists of clean-up
measures taken in response to immediate threats to
public health and safety; “remedial” activity means
“actions consistent with [a] permanent remedy.” 42
U.S.C. § 9601(24).
The question presented is:
Whether the six-year statute of limitations for “remedial” work is triggered, as the court of appeals held
below, only when the construction of a permanent solution for environmental contamination meets a
threshold level of comprehensiveness.
(i)
ii
PARTIES TO THE PROCEEDING AND RULE
29.6 STATEMENT
Petitioners Joslyn Manufacturing Company, LLC
and Joslyn Corporation were the defendantsappellants in the court below. Respondents Valbruna
Slater Steel Corporation and Fort Wayne Steel Corporation were the plaintiffs-appellees in the court below.
Petitioner Joslyn Manufacturing Company, LLC is
a Delaware limited liability company. Joslyn Company, also a Delaware limited liability company, owns
100% of Joslyn Manufacturing Company, LLC. Danaher Corporation, a publicly held company, owns
100% of Joslyn Company. Petitioner Joslyn Corporation was a Delaware corporation that ceased to exist
in 1997.
RELATED PROCEEDINGS
There are no proceedings in state or federal courts
that are directly related to this case.
TABLE OF CONTENTS
Page
QUESTION PRESENTED ...................................
i
PARTIES TO THE PROCEEDING AND RULE
29.6 STATEMENT ............................................
ii
RELATED PROCEEDINGS.................................
ii
TABLE OF AUTHORITIES .................................
v
OPINIONS BELOW .............................................
1
JURISDICTION....................................................
1
STATUTORY PROVISIONS INVOLVED ...........
1
INTRODUCTION .................................................
1
STATEMENT OF THE CASE..............................
4
A. Statutory and Regulatory Background ....
4
B. Factual and Procedural Background .......
5
REASONS FOR GRANTING THE PETITION ...
8
I. THE CIRCUITS HAVE ADOPTED DISPARATE TESTS FOR TRIGGERING
CERCLA’S SIX-YEAR STATUTE OF LIMITATIONS FOR ACTIONS TO RECOVER
COSTS OF REMEDIATION. .......................
9
II. THE DECISION BELOW IS CONTRARY
TO THE STATUTORY LANGUAGE AND
RISKS ELIMINATING THE STATUTE OF
LIMITATIONS ALTOGETHER ...................
12
III. THIS CASE INVOLVES A RECURRING
ISSUE OF NATIONAL IMPORTANCE
AND IS AN EXCELLENT VEHICLE TO
RESOLVE THE ACKNOWLEDGED SPLIT
AMONG THE COURTS OF APPEALS .......
15
CONCLUSION ....................................................
17
(iii)
iv
TABLE OF CONTENTS—continued
Page
APPENDICES
APPENDIX A: Valbruna Slater Steel Corp. v.
Joslyn Mfg. Co., 934 F.3d 553 (7th Cir.
2019) ...................................................................
1a
APPENDIX B: Entry of Final Judgment, Valbruna Slater Steel Corp. v. Joslyn Mfg. Co.,
No. 1:10-CV-044-JD (N.D. Ind. July 20,
2018) ................................................................... 23a
APPENDIX C: Opinion and Order, Valbruna
Slater Steel Corp. v. Joslyn Mfg. Co., No. 1:10CV-44 (N.D. Ind. June 5, 2013) ......................... 25a
APPENDIX D: Opinion and Order, Valbruna
Slater Steel Corp. v. Joslyn Mfg. Co., No. 1:10CV-044 JD (N.D. Ind. Mar. 21, 2013) ............... 32a
APPENDIX E: Order Denying Rehearing, Valbruna Slater Steel Corp. v. Joslyn Mfg. Co.,
Nos. 18-2633 & 18-2738 (7th Cir. Sept. 6,
2019) ................................................................... 60a
APPENDIX F: Statutory Provisions Involved .... 61a
42 U.S.C. § 9601 (excerpts) ............................. 61a
42 U.S.C. § 9613 (excerpts) ............................. 63a
v
CASES
TABLE OF AUTHORITIES
Page
California ex rel. Cal. Dep’t of Toxic
Substances Control v. Neville Chem. Co.,
358 F.3d 661 (9th Cir. 2004) .......... 3, 10, 11, 15
Commander Oil Corp. v. Barlo Equip.
Corp., 215 F.3d 321 (2d Cir. 2000) ............
4
GenCorp, Inc. v. Olin Corp., 390 F.3d 433
(6th Cir. 2004) ............................................
10
Geraghty & Miller, Inc. v. Conoco Inc., 234
F.3d 917 (5th Cir. 2000), abrogated on
other grounds by Vine Street LLC v. Borg
Warner Corp., 776 F.3d 312 (5th Cir.
2015) ........................................................... 3, 10
Schaefer v. Town of Victor, 457 F.3d 188 (2d
Cir. 2006) .............................................. 3, 10, 15
United States v. Kubrick, 444 U.S. 111
(1979) ..........................................................
14
United States v. Navistar Int’l Transp.
Corp.,
152
F.3d
702
(7th
Cir.
1998) ............................................. 10, 13, 14, 15
United States v. Raytheon Co., 334 F. Supp.
3d 519 (D. Mass. 2018)............................. 11, 15
Valbruna Slater Steel Corp. v. Joslyn Mfg.
Co., 934 F.3d 553 (7th Cir. 2019) .............. 1, 15
STATUTES AND REGULATION
42 U.S.C. § 6901 et seq. .................................
5
§ 9601(23) ......................................
1
§ 9601(24) .......................... 1, 2, 3, 6, 12
§ 9607(a) ........................................
4
§ 9613(g)(2) .................................... 1, 12
§ 9613(g)(2)(A) ............................... 2, 4
§ 9613(g)(2)(B) ............................. 2, 3, 4
40 C.F.R. § 300.5 ...........................................
6
PETITION FOR A WRIT OF CERTIORARI
OPINIONS BELOW
The opinion of the court of appeals is reported at
934 F.3d 553 (7th Cir. 2019). Pet. App. 1a-22a. The
district court’s unpublished decisions striking the
statute of limitations defense and denying summary
judgment are reproduced at Pet. App. 25a-31a and
32a-59a.
JURISDICTION
The court of appeals entered judgment on August 8,
2019, and denied a timely petition for rehearing en
banc by order dated September 6, 2019. Pet. App.
60a. This Court extended the time to file a petition
for a writ of certiorari to January 20, 2020. This petition is timely filed on January 21, 2020 due to the
federal holiday on January 20, 2020. This Court has
jurisdiction pursuant to 28 U.S.C. § 1254(1).
STATUTORY PROVISIONS INVOLVED
The statutory provisions involved are set forth in
the appendix to this petition: 42 U.S.C. § 9613(g)(2)
(providing a three-year statute of limitations for actions to recover removal costs and a six-year statute
of limitations for actions to recover remediation
costs); 42 U.S.C. § 9601(23) (defining “removal”); 42
U.S.C. § 9601(24) (defining “remedy” or “remedial action”). Pet. App. 61a-64a.
INTRODUCTION
The courts of appeals are in disarray over the correct application of CERCLA’s limitations period for
actions to recover clean-up costs. Multiple courts of
appeals have adopted disparate tests for what constitutes initiation of remedial action that triggers CER-
2
CLA’s six-year limitations period for recovery of “remediation” costs as opposed to the three-year period
for “removal” costs. This Court’s guidance is warranted to clarify this confusion and enable parties to
know with greater certainty when a cause of action
for cost recovery accrues and, more importantly,
when a claim has expired.
Under CERCLA, “removal” actions are generally
short-term actions to address an immediate threat to
public health or the environment from the release or
threatened release of hazardous materials. CERCLA
requires suits to recover costs of removal actions to be
filed within three years of the completion of the work.
42 U.S.C. § 9613(g)(2)(A). This encourages parties to
address the threat to public health or the environment first and sue for costs afterwards.
Remedial actions, by contrast, are longer-term and
indeed can go on for decades. The remedial work at
issue here has been ongoing since 1981. Timely actions and finality would be impossible if the limitations period did not commence until remediation was
completed. Accordingly, Congress provided a limitations period that commences, not with the completion
of the work, but instead with the “initiation of physical on-site construction” “consistent with” a “permanent” remedy. 42 U.S.C. §§ 9613(g)(2)(B), 9601(24)
(emphasis added). Suits must be filed within six
years of the initiation of that type of clean-up effort.
The Seventh Circuit’s decision—that otherwise
permanent remedial work is merely “removal” if it
resolves only a portion of the contamination at a
site—does violence to the plain language of the statute and runs counter to Congress’ intent. The decision below delays the accrual of actions to recover the
cost of remedial activity until remedial work meets
an amorphous level of comprehensiveness. This is the
3
exact opposite of what the statute says: “‘remedial action’ means those actions consistent with permanent
remedy,” and an action to recover remedial costs
must be brought within six years after remediation
begins. 42 U.S.C. §§ 9601(24), 9613(g)(2)(B).
The Seventh Circuit’s decision also brings further
confusion into the disagreement among the courts of
appeals over whether the permanent containment or
disposal of contamination at its source must be part
of a “comprehensive” remedial action plan before it
can trigger the statute of limitations for “remedial”
activity. The Ninth and Fifth Circuits hold that the
statute of limitations for “remedial” cost recovery is
not triggered until a final remedial action plan has
been adopted. See California ex rel. Cal. Dep’t of Toxic Substances Control v. Neville Chem. Co., 358 F.3d
661, 667 (9th Cir. 2004); Geraghty & Miller, Inc. v.
Conoco Inc., 234 F.3d 917, 927 (5th Cir. 2000), abrogated on other grounds by Vine Street LLC v. Borg
Warner Corp., 776 F.3d 312 (5th Cir. 2015). The Second Circuit has rejected that approach and holds that
a permanent fix undertaken before adoption of a remedial action plan can trigger the six-year statute of
limitations for “remedial” costs if it is consistent with
a permanent remedy. Schaefer v. Town of Victor, 457
F.3d 188, 207 (2d Cir. 2006). Like the Second Circuit,
the Seventh Circuit has rejected the Ninth Circuit’s
requirement of a ratified action plan. But, in the decision below, the court created yet a third test for starting the remedial statute of limitations, requiring that
to qualify as remedial, the clean-up work, no matter
how permanent, must be “meant to substantially resolve the bulk of the site’s ongoing pollution problems.” Pet. App. 17a.
This Court should grant certiorari to resolve the
split of authority over the statutory meaning of “re-
4
medial” clean-up activity, to ensure the statutory text
is enforced as written and thereby provide parties
with notice that their exposure to clean-up costs has
ended.
STATEMENT OF THE CASE
A. Statutory and Regulatory Background
CERCLA establishes “a regime of broad-ranging liability, permitting the government to recover its remediation expenses directly from parties responsible
for pollution and authorizing private parties to pursue contribution or indemnification from potentially
responsible parties for expenses incurred responding
to environmental threats.” Commander Oil Corp. v.
Barlo Equip. Corp., 215 F.3d 321, 326 (2d Cir. 2000)
(citation omitted). Among other provisions, section
107(a) of CERCLA authorizes the government and
certain private parties to bring suit against any of
four categories of potentially responsible parties to
recover costs of clean-up and prevention of future pollution at contaminated sites. 42 U.S.C. § 9607(a).
Section 113 of CERCLA distinguishes between removal, which “generally refers to a shortterm action
taken to halt risks posed by hazardous wastes immediately,” and remedial actions which “are longer
term, more permanent responses.” Pet. App. 15a.
CERCLA provides different statutes of limitations
for recovery of removal costs and remediation costs.
Actions to recover costs related to “removal actions”
must be brought within three years after the completion of the removal action. 42 U.S.C. § 9613(g)(2)(A).
Actions to recover costs related to “remediation,” by
contrast, must be brought within six years of the initiation of physical on-site construction of the remediation. Id. § 9613(g)(2)(B).
5
B. Factual and Procedural Background
From 1928 to 1981, petitioners and their predecessors (collectively “Joslyn”) owned and operated a steel
production business in Fort Wayne, Indiana (the
“Site”). Pet. App. 2a. The Site was sold to Slater
Steels Corporation (“Slater”) in 1981. Id.
At that time, the Site was an Interim Status
Treatment Disposal and Storage Facility under the
Resource Conservation and Recovery Act of 1976, 42
U.S.C. § 6901 et seq. (“RCRA”). Pet. App. 2a There
were three hazardous waste storage units at the Site
that required RCRA compliance: a waste pile; a drum
storage area; and a former surface impoundment,
which contained sludge generated in the steelmaking process. Slater immediately began incurring
environmental response costs to clean up and officially close these units in an effort to reduce its overall
environmental costs and liability. Id. at 2a-3a.
Closing the impoundment required the most work.
From 1981 to 1987, Slater conducted a series of excavations to dig up contaminated material and dispose
of it offsite for the purpose of closing the impoundment. After each effort, Slater thought it had done
enough to satisfy RCRA; each time, however, Indiana’s regulatory agency wanted more excavated. Pet.
App. 2a, 37a. In 1988, Slater entered into a Consent
Decree with the U.S. Environmental Protection
Agency (“EPA”), which provided in relevant part that
if the impoundment could not be “closed by removal,”
it would be “closed by landfill.” Id. at 2a; ECF No. 467, at 8-9.1 Stated more plainly, Slater would construct
a cap over the former impoundment to contain the
1 All “ECF No.” citations refer to the district court docket:
Valbruna Slater Steel Corp. v. Joslyn Mfg. Co., No. 1:10-cv00044-JD (N.D. Ind.).
6
residual contamination in place. Pet. App. 2a. The
cap would prevent rainwater from percolating
through the residual contamination and spreading it
farther, falling squarely within the statutory definition of “remedial action.” See 42 U.S.C. § 9601(24)
(“[T]hose actions consistent with permanent remedy . . . to prevent or minimize the release of hazardous substances so that they do not migrate to cause
substantial danger to present or future public health
or welfare or to the environment.”).
A reinforced concrete cap was constructed over the
former impoundment in November 1991. Pet. App.
2a. A groundwater monitoring system was built
around the impoundment in 1992. Id. at 3a. After
monitoring results showed the cap was containing the
contamination, the Indiana Department of Environmental Management (“IDEM”) certified closure of the
impoundment in 1999 on the condition that the other
sources of contamination at the Site would be addressed. Id. Thus, the impoundment’s “closure by
landfill” met the definition of a CERCLA “operable
unit,” i.e., “a discrete action that comprises an incremental step toward comprehensively addressing site
problems.” 40 C.F.R. § 300.5.
On March 22, 2000, Indiana issued a Covenant Not
to Sue for the project. (ECF No. 42-7, at 4-5.) The
Certificate of Completion for the Voluntary Remediation Program and the Covenant were both conditioned on Slater addressing the other sources of contamination at the Site. (ECF No. 42-7, at 12, 5 ¶ 7.)
On March 25, 2002, Slater entered into an Agreed
Order with IDEM to do the other work. Pet. App. 36a37a.
By 2003, however, Slater was bankrupt. Respondents acquired the Site at a bankruptcy auction in
2004. Pet. App. 4a. In 2005, respondents undertook
7
treatment of trichloroethylene (TCE) contamination
at the Site, and, in 2008, respondents entered the
Site in Indiana’s Voluntary Remediation program to
address other sources of contamination. Respondents’
2012 Work Remediation Plan submitted to Indiana’s
environmental authorities described Slater’s 1991
closure of the former impoundment as a “key component[]” of the Site’s overall remedial strategy. (ECF
No. 101-11, § 3.0, ¶ 1.)
Respondents brought this CERCLA action against
Joslyn in 2010 to recover past and future clean-up
costs. Pet. App. 4a. Joslyn moved for summary judgment, asserting the action was untimely under 42
U.S.C. § 9613(g)(2)(B). Joslyn argued that Slater initiated physical construction of the remedial action at
the former surface impoundment either in 1981
(when excavation began), or at the latest in 1991
(when the concrete cap was poured), both of which
occurred more than six years before respondents’
2010 suit was filed. Id. at 5a.
The district court denied Joslyn’s motion, entered
summary judgment for respondents on the issue of
liability, and held a trial limited to the issue of damages and contribution. Pet. App. 5a. Ultimately, the
district court awarded respondents $1,410,767.20 in
past response costs and a declaratory judgment that
Joslyn is responsible for 75% of respondents’ future
response costs. Id. at 5a-6a.
Joslyn appealed the rejection of its statute of limitations defense. The Seventh Circuit affirmed. It held
that the reinforced concrete cap Slater constructed on
the surface impoundment in 1991 did not trigger the
six-year limitations period for recovery of the costs of
remedial action because the cap constituted removal
action, not remedial action. The court reasoned that
treating the permanent concrete cap constructed on
8
the impoundment as “remedial” would “prioritize[]
form (the cap’s makeup) over function (the cap’s purpose and effect),” because “[t]he concrete cap covered
just one area” and was not “meant to substantially
resolve the bulk of the site’s ongoing pollution problems.” Pet. App. 17a.
REASONS FOR GRANTING THE PETITION
The decision below exacerbates an acknowledged
circuit split about the nature of clean-up work required to trigger CERCLA’s six-year statute of limitations for actions to recover costs of “remediation.” The
Ninth and Fifth Circuits hold that the statute for remedial action is not triggered by clean-up work conducted before the adoption of a comprehensive remedial action plan. The Second Circuit rejects this requirement and requires only that clean-up work be
consistent with a permanent remedy to trigger the
six-year limitations period. The Seventh Circuit’s decision below adopts yet a third test, requiring that
permanent clean-up work meet a threshold level of
comprehensiveness to trigger the six-year statute of
limitations. This disagreement among the courts of
appeals matters. The court below held that the costrecovery action was timely; under the Second Circuit’s approach in Schaefer, the action would be timebarred.
The Seventh Circuit’s decision runs counter to the
statutory language and fails to provide parties with
clarity and predictability over when a cost-recovery
action accrues and ignores the practical reality of
CERCLA clean-up efforts. The test adopted by the
court below also improperly extends the statute of
limitations, possibly indefinitely, which severely interferes with the ability of all potentially responsible
parties to be able to determine their liability risks.
9
This case presents an excellent vehicle to resolve
the disagreement among the lower courts. The relevant facts are typical of CERCLA cost-recovery actions and are not in dispute. The Seventh Circuit’s
published opinion squarely addresses the question,
and published decisions from other circuits present
opposing views. This Court should grant certiorari
and provide uniformity on this important and recurring question.
I. THE CIRCUITS HAVE ADOPTED DISPARATE TESTS FOR TRIGGERING CERCLA’S
SIX-YEAR STATUTE OF LIMITATIONS
FOR ACTIONS TO RECOVER COSTS OF
REMEDIATION.
The decision below exacerbated an acknowledged
circuit split about the nature of clean-up work required to trigger CERCLA’s six-year statute of limitations for actions to recover costs of “remedial” work.
The Ninth and Fifth Circuits on the one hand and the
Second Circuit on the other have adopted directly
contradictory tests. The Seventh Circuit has expressly rejected the Ninth Circuit’s approach and, in the
decision below, created yet a third approach for deciding when a permanent containment effort should be
classified as “remediation” and thereby trigger the
six-year limitations period. These disparate approaches to the statute of limitations mean that
whether a given cost-recovery action is timely turns
on the happenstance of geography. Cost recovery may
be barred in New York, but not in Chicago. That is
precisely the situation in which this Court should intervene.
The Ninth Circuit has adopted a bright-line rule
that remedial action starts when a final remedial action plan is adopted, and therefore even permanent
containment efforts must be treated as “removal” un-
10
til a final remedial plan is agreed upon. Neville, 358
F.3d at 666-67. The Ninth Circuit reasoned that the
statute defines remedial as actions “consistent with
permanent remedy,” and “[f]or an action to be ‘consistent with permanent remedy,’ a permanent remedy [i.e., a final remedial action plan] must already
have been adopted.” Id. at 667. The Fifth Circuit has
similarly held a clean-up program was not remedial
prior to the state’s approval of the final remediation
plan. See Geraghty & Miller, Inc., 234 F.3d at 927.
The Second Circuit has expressly rejected the
Ninth Circuit’s approach. The Second Circuit explained that the “plain language of the statute”
makes no mention of a “final remedial action plan,”
and requires only that remedial activity be “consistent with permanent remedy.” Schaefer, 457 F.3d
at 207 (emphasis omitted). The Second Circuit held
that using a crane to spread topsoil, sand, and gravel
over a landfill was “consistent with permanent remedy” and thus triggered the six-year limitations period.
Id. at 204.2
The Seventh Circuit has likewise rejected the requirement that a final remedial action plan be approved before clean-up efforts can be classified as remedial. United States v. Navistar Int’l Transp. Corp.,
152 F.3d 702, 712 (7th Cir. 1998) (“The statute is devoid of any reference that would lead us to conclude
from its plain language that Congress intended to incorporate this specific aspect of the administrative
process in establishing the actions that would trigger
2 The Sixth Circuit has also held that remedial action begins
when construction is initiated if it is “consistent with” a “permanent remedy” but has declined to reach the question whether a
final remediation plan is also required. See GenCorp, Inc. v. Olin
Corp., 390 F.3d 433, 444 (6th Cir. 2004).
11
the limitations period.”). But in the decision below,
the Seventh Circuit created a new, additional requirement. It held that the concrete cap and the containment of the surface impoundment at the Site was
permanent, but not remedial, because it did not address any other areas of contamination at the Site
and therefore was not sufficiently comprehensive.
Pet. App. 17a.
Curiously and notwithstanding the Seventh Circuit’s rejection of the Ninth Circuit’s precise approach, the action would likely have been untimely
under the Ninth Circuit’s test. Although there was no
final remedial action plan approved for this Site
when the cap was built over the impoundment in
1991, a 1988 consent decree between Slater and the
EPA provided that the impoundment would be
“closed by landfill” if it could not be “closed by removal.” This agreement on the means of remediation
would likely satisfy the Ninth Circuit’s requirement
of an agreed action plan that would make the concrete cap qualify as initiation of remediation. See Neville, 358 F.3d at 671 (explaining that the result in
Navistar would be the same under the Ninth Circuit
test because the clay cap occurred after the EPA determined that “the landfill needed to be covered with
a permanent clay cap to isolate the hazardous materials from the rest of the environment”). And because
the containment system was plainly consistent with a
permanent remedy (indeed, it is still in place and has
since been incorporated into respondents’ final remedial action plan), this cost-recovery action would be
untimely under the Second Circuit’s approach in
Schaefer.
The disagreement among the courts of appeals also
sows confusion among district courts in circuits that
have not yet addressed the question. See, e.g., United
12
States v. Raytheon Co., 334 F. Supp. 3d 519, 526 (D.
Mass. 2018) (noting absence of First Circuit guidance
and disagreeing with another district court on the
proper test). The circuit split also creates uncertainty
for environmental enforcement agencies, businesses,
and insurers.
This Court should grant the petition for a writ of
certiorari to resolve the confusion among the lower
courts regarding the nature of clean-up work required to trigger CERCLA’s six-year statute of limitations for cost-recovery actions. This Court’s guidance
is warranted to clarify this important—and often dispositive—threshold legal question.
II. THE DECISION BELOW IS CONTRARY TO
THE STATUTORY LANGUAGE AND RISKS
ELIMINATING THE STATUTE OF LIMITATIONS ALTOGETHER.
The Seventh Circuit’s test cannot be reconciled with
the relevant statutory language. CERCLA defines
remedial work as “actions consistent with permanent
remedy . . . to prevent or minimize the release of hazardous substances so that they do not migrate to
cause substantial danger to present or future public
health or welfare or the environment.” 42 U.S.C.
§ 9601(24) (emphasis added). And it provides that
suits for recovery of remediation costs must be
brought “within 6 years after initiation of physical
on-site construction of the remedial action.” Id.
§ 9613(g)(2) (emphasis added). It says nothing about
“substantially resolv[ing] the bulk of the site’s ongoing pollution problems,” as the court below required.
Pet. App. 17a. The Seventh Circuit’s test effectively
reads out of the statute the phrases “consistent with
permanent remedy” and “initiation of . . . construction of the remedial action.” It requires instead that
the clean-up work constitute the entirety of the per-
13
manent remedy and does not allow for phased initiation of clean-up efforts. The result is that the court
below found that the cost-recovery action was timely
filed 18 years after installation of a permanent concrete cap and groundwater monitoring system to prevent the release of hazardous substances. There is no
way to reconcile that outcome with the plain language and intent of CERCLA’s two-part limitations
scheme.
As the Seventh Circuit itself recognized in Navistar, “‘remedial action’ is a term broadly defined by the
statute—a fact of which Congress was no doubt well
aware when it incorporated that term in the statute
of limitations.” 152 F.3d at 712. If Congress had intended to require a “comprehensive” remedy that addressed the “bulk” of the contamination at a site before the limitations period could begin, it “surely
would have provided [the courts] with a more explicit
direction to that effect.” Id.
The decision below sows uncertainty for the timely
commencement of cost recovery-actions and ignores
the practical reality of the mine-run of CERCLA
clean-up efforts. The Seventh Circuit’s approach
dates the limitations period from a point that cannot
be calibrated with any degree of certainty. When does
otherwise permanent clean-up work become sufficiently “comprehensive” to be considered remedial?
When it affects 25% of the contamination at a site?
40%? 50? More? What if there are different forms of
contamination at the site (e.g., soil, sediment,
groundwater) that are not amenable to quantitative
comparison? The problems with this approach are obvious. It permits the commencement of the statute of
limitations to become a wholly discretionary determination of when “enough” permanent clean-up work
has been done to make it “remedial” and thus invites
14
widely disparate accrual dates across jurisdictions. It
would also encourage strategic behavior to preclude
the limitations period from ever accruing, thereby effectively eliminating the statute of limitations and
imposing potentially indefinite liability. There is no
possibility of repose embedded in the Seventh Circuit’s approach to determining when the limitations
period begins to run.
One of the primary functions of a limitations period, especially with regard to regulatory matters, is to
ensure an intelligible record for review. Statutes of
limitations “protect defendants and the courts from
having to deal with cases in which the search for
truth may be seriously impaired by the loss of evidence, whether by death or disappearance of witnesses, fading memories, disappearance of documents, or
otherwise.” United States v. Kubrick, 444 U.S. 111,
117 (1979). The rule the Seventh Circuit adopted in
this case has all of these risks. And it defeats the
purpose of a statute of limitations which, above all
else, is supposed to provide certainty for both the party seeking relief and the party who may be liable. See
Navistar, 152 F.3d at 707-08 (Congress enacted 42
U.S.C. § 9613(g)(2)(B) to “serve the important purpose of encouraging the prompt filing of claims and
by doing so of enhancing the likelihood of accurate
determinations and removing debilitating uncertainty about legal liabilities”).
The Seventh Circuit’s test also fails to account for
the practical realities of CERCLA clean-up efforts.
The clean-up of large, contaminated industrial sites
necessarily occurs in phases, and permanent fixes often commence before a complete remedial action plan
is in place. It is time-consuming, expensive work. The
fact that otherwise permanent remedial work frequently occurs on a piecemeal basis does not trans-
15
form that work into “removal” activity that delays indefinitely the start of the limitations period for the
recovery of remedial costs.
Congress provided a statute of limitations for
CERCLA cost-recovery actions to promote timely
claims and accurate determinations, and to provide
finality to potentially responsible parties. It pursued
these purposes by requiring initial suits for remedial
costs to be filed within six years after the initiation of
physical on-site construction “consistent with permanent remedy.” It did not require comprehensiveness.
The Seventh Circuit erred by finding physical construction consistent with a permanent remedy not to
trigger the statute of limitations.
III. THIS CASE INVOLVES A RECURRING ISSUE OF NATIONAL IMPORTANCE AND IS
AN EXCELLENT VEHICLE TO RESOLVE
THE ACKNOWLEDGED SPLIT AMONG
THE COURTS OF APPEALS.
CERCLA applies nationwide, and the issue of what
activities trigger the start of CERCLA’s six-year statute of limitations for recovery of remediation costs
arises frequently, as evidenced by the multiple district court and court of appeals decisions addressing
the issue. E.g., Navistar, 152 F.3d 702; Neville, 358
F.3d 661; Schaefer, 457 F.3d 188; Valbruna, 934 F.3d
553; Raytheon Co., 334 F. Supp. 3d 519. This Court’s
guidance on this important question of statutory interpretation would provide much-needed national
uniformity.
This case is an excellent vehicle with which to resolve this question. The relevant facts are typical of
CERCLA cost-recovery actions. This case involves a
large industrial site that was in use for more than a
century with multiple owners. The facts concerning
16
who caused the contamination of the Site are not in
dispute, nor is there any dispute over the clean-up
work that was performed, when it was performed,
how it was performed, or by whom. The permanent
remedy that was constructed—a concrete cap and
groundwater monitoring system—is also a commonly
used method for the disposal and containment of contamination. State environmental enforcement agencies were involved as early as 1982 and at various
times reviewed and approved the remediation efforts
at the Site. As such, the instant case contains all of
the facts that are characteristic of those that were at
issue in the cases that have divided the circuits over
how to interpret CERCLA’s limitations period for
suits to recover remedial costs.
In addition, this Court now has the benefit of the
views of multiple courts of appeals. The Seventh Circuit’s published opinion squarely addresses the question, and published decisions from other circuits present opposing views with significant analysis.
A decision by this Court on this record will resolve
the circuit split and provide the certainty that is essential to the proper operation of the statute of limitations.
17
CONCLUSION
For the foregoing reasons, the petition for a writ of
certiorari should be granted.
Respectfully submitted,
JOSHUA G. VINCENT
HINSHAW & CULBERTSON
151 N. Franklin St., #2500
Chicago, Illinois 60606
(312) 704-3463
STEPHEN D. DAVIS
STEVE DAVIS LAW, P.C.
1333 Burr Ridge Parkway
Burr Ridge Illinois 60527
(630) 756-3042
CARTER G. PHILLIPS *
TIMOTHY K. WEBSTER
JENNIFER J. CLARK
SIDLEY AUSTIN LLP
1501 K Street, N.W.
Washington, D.C. 20005
(202) 736-8000
cphillips@sidley.com
Counsel for Petitioner
January 21, 2020
* Counsel of Record
This is a copy of a public record, reproduced as it was published. It is not legal advice, and it may not be the version a court would rely on. Check the official source before you cite it.