Petition for Writ of Certiorari — North Carolina Utilities Commission, Petitioner v. Federal Energy Regulatory Commission
Supreme Court briefJul 2, 2019
Ask Donna
What actually matters in this document.
Text
No. ___
IN THE
Supreme Court of the United States
————
NORTH CAROLINA UTILITIES COMMISSION,
Petitioner,
v.
FEDERAL ENERGY REGULATORY COMMISSION,
Respondent.
————
On Petition for a Writ of Certiorari to the
United States Court of Appeals for the
District of Columbia Circuit
————
PETITION FOR A WRIT OF CERTIORARI
————
KATHLEEN L. MAZURE
Counsel of Record
JASON T. GRAY
DUNCAN & ALLEN
1730 Rhode Island Avenue, NW
Suite 700
Washington, DC 20036
(202) 289-8400
klm@duncanallen.com
jtg@duncanallen.com
Counsel for Petitioner
July 2, 2019
WILSON-EPES PRINTING CO., INC. – (202) 789-0096 – WASHINGTON, D. C. 20002
QUESTION PRESENTED
The Natural Gas Act provides States and State
regulatory commissions procedural rights to challenge
Federal Energy Regulatory Commission orders in
order to protect States’ interests. 15 U.S.C. § 717r(a),
(b). This Court’s opinion in Massachusetts v. Environmental Protection Association, 549 U.S. 497, 518-520
(2007) held that States are entitled to special solicitude in courts’ standing analyses because they are not
normal litigants for purposes of invoking federal
jurisdiction. While courts of appeals have offered
varying views of Massachusetts’ scope, in this case,
the District of Columbia Circuit did not address
Massachusetts. Instead, it held a State litigant had
not demonstrated injury-in-fact and, therefore, lacked
standing to challenge Federal Energy Regulatory
Commission orders that authorized construction of
interstate pipeline facilities that will be located within
the State’s borders and that were marketed to serve
the State’s ratepayers.
The questions presented are:
1. If a court of appeals finds a State litigant failed
to demonstrate injury-in-fact that is traceable to the
challenged action and redressable by the court, must
it separately consider whether the State litigant has
standing under Massachusetts to challenge orders by
a federal agency that implicate the State’s quasisovereign and parens patriae interests?
2. If a federal statute affords a State litigant procedural rights to challenge agency actions that affect
the State’s quasi-sovereign and parens patriae interests, do Massachusetts and Lujan v. Defenders of
Wildlife, 504 U.S. 555, 572 n.7 (1992) require the State
to demonstrate injury-in-fact that is traceable to the
(i)
ii
challenged action and redressable by the court in order
to establish Article III standing?
iii
PARTIES TO THE PROCEEDING
Petitioner appearing in this Court is the North
Carolina Utilities Commission. Petitioner was the
appellant in the court of appeals. Petitioner is a
governmental entity that is not required to file a Rule
29.6 statement.
Respondent is the Federal Energy Regulatory
Commission. Respondent was the appellee in the
court of appeals.
The following entities were intervenors in the court
of appeals: (1) Transcontinental Gas Pipe Line
Company, LLC; (2) The New York State Public Service
Commission; and (3) Oglethorpe Power Corporation.
TABLE OF CONTENTS
Page
QUESTION PRESENTED ..................................
i
PARTIES TO THE PROCEEDING ....................
iii
TABLE OF AUTHORITIES ................................
vii
OPINIONS BELOW ............................................
1
STATEMENT OF JURISDICTION ....................
1
STATUTORY AND REGULATORY
PROVISIONS INVOLVED ..............................
1
STATEMENT OF THE CASE ............................
2
A.
Legal Framework ......................................
3
B.
Procedural Background ............................
5
REASONS FOR GRANTING THE PETITION..
7
A.
The United States Court of Appeals for
the District of Columbia Circuit Decision
Conflicts with the Supreme Court’s Decisions in Massachusetts and Lujan ...........
8
In Reversing the District of Columbia
Circuit’s Dismissal of the North Carolina
Commission’s Appeal, the Court Should
Address the Split Among the Circuits
and Affirm the Scope and Durability of
Massachusetts’ Special Solicitude Doctrine for State Litigants ............................
12
CONCLUSION ....................................................
15
B.
APPENDIX
APPENDIX A: JUDGMENT, U.S. Court of
Appeals for the District of Columbia Circuit
(April 3, 2019) ..................................................
(v)
1a
vi
TABLE OF CONTENTS—Continued
Page
APPENDIX B: ORDER ISSUING CERTIFICATE, U.S. Federal Energy Regulatory
Commission (August 3, 2016) ..........................
5a
APPENDIX C: ORDER DENYING REHEARING, U.S. Federal Energy Regulatory
Commission (November 21, 2017) ...................
81a
APPENDIX D: ORDER ISSUING CERTIFICATE, U.S. Federal Energy Regulatory
Commission (July 7, 2016)...............................
91a
APPENDIX E: ORDER DENYING REHEARING, U.S. Federal Energy Regulatory
Commission (November 21, 2017) ................... 130a
APPENDIX F: ORDER ISSUING CERTIFICATE, U.S. Federal Energy Regulatory
Commission (February 3, 2017) ...................... 136a
APPENDIX G: ORDER ON REHEARING,
U.S. Federal Energy Regulatory Commission
(December 6, 2017) .......................................... 274a
APPENDIX H: 15 U.S.C.S. § 717a .................. 345a
APPENDIX I: 15 U.S.C.S. § 717r .................... 347a
APPENDIX J: N.C. Gen. Stat. § 62-2.............. 351a
APPENDIX K: N.C Gen. Stat. § 62-32 ............ 357a
APPENDIX L: N.C Gen. Stat. § 62-36.01 ....... 358a
APPENDIX M: N.C Gen. Stat. § 62-48 ........... 360a
APPENDIX N: N.C Gen. Stat. § 62-133.4 ....... 362a
APPENDIX O: 18 C.F.R. § 385.214 ................. 364a
vii
TABLE OF AUTHORITIES
CASES
Page(s)
Ark. Elec. Coop. Corp. v. Ark. Pub.
Serv. Comm’n,
461 U.S. 375 (1983) ................................... 3, 7, 9
Arpaio v. Obama,
797 F.3d 11 (D.C. Cir. 2015) .....................
13
Center for Biological Diversity v.
Department of Interior,
563 F.3d 466 (D.C. Cir. 2009) ................... 12, 13
Connecticut v. Am. Elec. Power Co.,
582 F.3d 309 (2d Cir. 2009), juris.
aff’d by an equally divided court,
131 S. Ct. 2527 (2011) ........................... 8, 13, 14
Gvt. Province of Manitoba v.
David Bernhardt,
D.C. Cir. Case No. No. 17-5242
(May 3, 2019)....................................... 7-8, 13-14
Lujan v. Defenders of Wildlife,
504 U.S. 555 (1992) ..................................passim
Md. People’s Counsel v. FERC,
760 F.2d 318 (D.C. Cir. 1985) ...................
4
Massachusetts v. EPA,
549 U.S. 497 (2007) ..................................passim
N. Carolina Utilities Comm’n v. F.E.R.C.,
No. 18-1018 (D.C. Cir. April 3, 2019) ......passim
Texas v. United States,
809 F.3d 134 (5th Cir. 2015), aff’d
by an equally divided Court,
136 S. Ct. 2271 (2016) ...................... 8, 12-13, 14
viii
TABLE OF AUTHORITIES—Continued
ADMINISTRATIVE CASES
Page(s)
Transcontinental Gas Pipe Line Co., LLC,
156 FERC ¶ 61,022 (2016), on reh’g,
161 FERC ¶ 61,212 (2017) ........................
1
Transcontinental Gas Pipe Line Co., LLC,
156 FERC ¶ 61,092 (2016), on reh’g,
161 FERC ¶ 61,211 (2017) ........................
1
Transcontinental Gas Pipe Line Co., LLC,
158 FERC ¶ 61,125, on reh’g,
161 FERC ¶ 61,250 (2017) ........................
1
CONSTITUTION
U.S. Const. art. I, § 8, cl. 3 ...........................
3
U.S. Const. art. III ...................................... 4, 8, 13
STATUTES
15 U.S.C. § 717(a) .........................................
3
15 U.S.C. § 717(b) .........................................
3
15 U.S.C. § 717a(6) .......................................
5
15 U.S.C. § 717f(c) ........................................
3, 5
15 U.S.C. § 717f(e) ........................................
3
15 U.S.C. § 717n(e) ....................................... 4, 5-6
15 U.S.C. § 717r(a) ......................................passim
15 U.S.C. § 717r(b) ......................................passim
28 U.S.C. § 1254(l) ........................................
1
N.C. Gen. Stat. § 62-48(a) .......................... 2, 5, 11
ix
TABLE OF AUTHORITIES—Continued
REGULATIONS
Page(s)
18 C.F.R. § 385.214(a)(2) .............................. 4, 11
RULES
Fed. R. App. P. 36 .........................................
1
OPINIONS BELOW
Pursuant to D.C. Circuit Rule 36, the judgement
below was not published. The judgement was issued
on April 3, 2019 in North Carolina Utilities Commission v. F.E.R.C., D.C. Circuit Case No. 18-1018. Pet.
Appendix-A at 1a-4a.
The orders of the Federal Energy Regulatory
Commission that were on appeal below are reported
at: (1) 156 FERC ¶ 61,092 (2016), Pet. Appendix-B at
5a-80a; (2) 161 FERC ¶ 61,211 (2017), Pet. AppendixC at 81a-90a; (3) 156 FERC ¶ 61,022 (2016), Pet.
Appendix-D at 91a-129a; (4) 161 FERC ¶ 61,212
(2017), Pet. Appendix-E at 130a-135a; (5) 158 FERC
¶ 61,125 (2017), Pet. Appendix-F at 136a-273a; and
(6) 161 FERC ¶ 61,250 (2017), Pet. Appendix-G at
274a-344a.
STATEMENT OF JURISDICTION
The judgement of the court of appeals was entered
on April 3, 2019. The jurisdiction of this Court is
invoked under 28 U.S.C. § 1254(1).
STATUTORY AND REGULATORY
PROVISIONS INVOLVED
In pertinent part, 15 U.S.C. § 717r(a) provides that
a “State commission aggrieved by an order issued by
the [Federal Energy Regulatory] Commission in a
proceeding under this chapter to which such . . . State
commission is a party may apply for a rehearing
within thirty days after the issuance of such order.”
Pet Appendix-I at 347a.
In pertinent part, 15 U.S.C. § 717r(b) provides:
Any party to a proceeding under this chapter
aggrieved by an order issued by the [Federal
Energy Regulatory] Commission in such
2
proceeding may obtain a review of such order
in the court of appeals of the United States for
any circuit wherein the natural-gas company
to which the order relates is located or has its
principal place of business, or in the United
States Court of Appeals for the District of
Columbia, by filing in such court, within sixty
days after the order of the Commission upon
the application for rehearing, a written petition praying that the order of the Commission
be modified or set aside in whole or in part.
Pet. Appendix-I at 348-349a.
Other relevant statutes and regulations are contained
in the appendix.
STATEMENT OF THE CASE
This case presents a recurring question of exceptional importance that circuit courts have grappled
with—the scope and durability of this Court’s holding
in Massachusetts v. EPA, 549 U.S. 497 (2007) regarding the special solicitude afforded to State litigants
that challenge federal agency actions affecting the
State’s interests. Petitioner in the case below, the
North Carolina Utilities Commission (“North Carolina
Commission”), “is authorized and empowered to initiate and appear before federal and State courts and
agencies as in its opinion may be necessary to secure
for the users of public utility service in [North
Carolina] just and reasonable rates and service” (N.C.
Gen. Stat. § 62-48(a), Pet. Appendix-M at 360a). The
North Carolina Commission sought judicial review of
Federal Energy Regulatory Commission (“FERC”) orders
that authorized construction of interstate pipeline
facilities that were marketed to the State’s citizens
and that will be constructed and operated within the
State’s borders. The North Carolina Commission
3
asserted that Massachusetts entitled it to special
solicitude in the court’s standing analysis. Petitioner
Initial Brief at 32-34; Petitioner Reply Brief at 19-21.
Without addressing Massachusetts, the District of
Columbia Circuit dismissed the appeal on the grounds
that the North Carolina Commission failed to demonstrate injury-in-fact and, therefore, lacks standing.
Pet. Appendix-A at 1a-4a. This finding conflicts
directly with this Court’s holding in Massachusetts;
ignores the procedural rights the Natural Gas Act
affords State litigants to challenge FERC orders (15
U.S.C. § 717r(a), (b), Pet. Appendix-I at 347a-349a);
and deprives North Carolina of the ability to protect
its quasi-sovereign and parens patriae interests in
interstate pipeline facilities that will be constructed
and operated within North Carolina’s borders and the
rates paid by North Carolina citizens for service on
those facilities.
A. Legal Framework
1. Congress vested the authority to regulate interstate commerce solely in the federal government. US
Const. Art. I, Sec. 8, Cl. 3. The Natural Gas Act vested
the power to regulate interstate transportation of
natural gas to FERC’s predecessor, the Federal Power
Commission. 15 U.S.C. § 717(a), (b). FERC’s regulatory powers include the authority to determine
whether construction and operation of interstate
pipeline facilities is in the public interest. 15 U.S.C.
§ 717f(c), (e).
2. “[T]he regulation of utilities is one of the most
important of the functions traditionally associated
with the police power of the States.” Ark. Elec. Coop.
Corp. v. Ark. Pub. Serv. Comm’n, 461 U.S. 375, 377
(1983). If a State had not joined the Union, it would
have the sovereign right to regulate public utilities
4
that construct facilities located within its borders and
that serve its citizens. By joining the Union, however,
States relinquished that right to the extent those
public utilities engage in interstate commerce. States
must rely on the federal government to protect their
interests when interstate pipelines impact the State
and its citizens.
3. Though the Natural Gas Act vested FERC
with authority to regulate interstate transportation
of natural gas, it recognized States’ special status
concerning matters over which FERC has jurisdiction.
The Natural Gas Act expressly recognizes States and
State commissions as “parties” that may participate in
FERC proceedings. 15 U.S.C. § 717n(e); cf. 18 C.F.R.
§ 385.214(a)(2) (unlike other parties that must seek
leave to intervene, FERC’s regulations authorize State
commissions to intervene in proceedings as a matter
of right, without motion), Pet. Appendix-O at 364a365a. “The special solicitude for states and state
agencies is also reflected in the provision governing
those who may apply for rehearing, which is a prerequisite for judicial review.” Md. People’s Counsel v.
FERC, 760 F.2d 318, 320-21 (D.C. Cir. 1985) (discussing 15 U.S.C. § 717r(a), Pet. Appendix-I at 347a). In
addition, the Natural Gas Act provides a procedural
right to seek relief from federal courts if they are
“aggrieved” by FERC orders. 15 U.S.C. § 717r(b), Pet.
Appendix-I at 348a-349a.
4. To establish Article III standing, a litigant must
demonstrate injury-in-fact that is traceable to the
challenged action and redressable by the court. Lujan
v. Defenders of Wildlife, 504 U.S. 555, 559-61(1992).
However, a litigant “who has been accorded a procedural right to protect his concrete interests can
assert that right without meeting all the normal
5
standards of redressability and immediacy.” Id., at
572, n.7. This Court’s Massachusetts decision requires
courts to afford State litigants special solicitude when
analyzing standing, especially where Congress has
provided the State litigant a concomitant procedural
right to challenge actions by federal agencies that
negatively impact the State’s once-sovereign prerogatives. Massachusetts, 549 U.S. at 518-20.
B. Procedural Background
5. Transcontinental Gas Pipe Line Company, LLC
(“Transco”) is a natural gas pipeline company as
defined by Natural Gas Act section 2(6). 15 U.S.C.
§ 717a(6), Pet. Appendix-H at 345a. In March 2015,
Transco initiated the three FERC proceedings that
give rise to this Petition by seeking authorization
under 15 U.S.C. § 717f(c) to construct and operate
interstate pipeline facilities. Pet. Appendix-B at 5a8a; Pet. Appendix-D at 91a-93a; Pet. Appendix-F at
136a-140a. Those facilities were marketed to serve
North Carolina residents and, in part, be constructed
within North Carolina’s borders. Pet. Appendix-B at
5a-7a; Pet. Appendix-D at 93a, 126a; Pet. Appendix-F
at 136a-140a.
6. North Carolina law authorizes and empowers
the North Carolina Commission “to . . . appear before
federal . . . courts and agencies as in its opinion
may be necessary to secure for the users of public
utility service in [North Carolina] just and reasonable
rates and service.” N.C. Gen. Stat. § 62-48(a), Pet.
Appendix-M at 360a. Given that Transco’s proposed
facilities implicated North Carolina’s quasi-sovereign
and parens patriae interests in interstate natural gas
pipeline facilities that will be constructed and operated in North Carolina and the rates paid by North
Carolina ratepayers for service on those facilities, the
6
North Carolina Commission became “party” to those
FERC proceedings as the Natural Gas Act defines that
term (15 U.S.C. § 717n(e)). Pet. Appendix-B at 10a;
Pet. Appendix-D at 94a-95a; Pet. Appendix-F at 144a.
The North Carolina Commission raised substantive
concerns with Transco’s proposals, arguing that they
negatively impacted North Carolina’s interests. Pet.
Appendix-B at 10a; Pet. Appendix-D at 94a-96a; Pet.
Appendix-F at 144a-145a. Aggrieved by the manner
in which FERC’s orders impacted North Carolina’s
interests, the North Carolina Commission sought
rehearing and judicial review of FERC’s orders under
15 U.S.C. § 717r(a), (b). Pet. Appendix-C at 81a-82a;
Pet. Appendix-E at 130a-131a; Pet. Appendix-G at
275a-282a.
7. On appeal before the District of Columbia
Circuit, the North Carolina Commission asserted that
FERC’s orders resulted in an injury-in-fact to North
Carolina’s interests that was traceable to the orders
and redressable by the court. Petitioner Initial Brief
at 29-32; see also Petitioner Reply Brief at 5-19. The
North Carolina Commission also asserted that the
District of Columbia Circuit must afford the North
Carolina Commission special solicitude when analyzing standing under Massachusetts. Petitioner Initial
Brief at 32-34; see also Petitioner Reply Brief at 19-21.
8. On April 3, 2019, the District of Columbia
Circuit dismissed the appeal on the grounds that the
North Carolina Commission did not demonstrate
injury-in-fact. Pet. Appendix-A at 1a-4a. The District
of Columbia Circuit did not address Massachusetts or
acknowledge North Carolina’s special status as a
State litigant with a concomitant procedural right to
challenge FERC orders.
7
REASONS FOR GRANTING THE PETITION
The Court should grant this Petition because the
District of Columbia’s standing analysis is in direct
conflict with this Court’s decision in Massachusetts.
Massachusetts requires courts to afford State litigants
special solicitude when analyzing questions of standing, especially when Congress has provided the State
a concomitant procedural right to challenge federal
agency actions that negatively impact the State’s oncesovereign prerogatives and interests of its citizens.
Massachusetts, 549 U.S. 518-20. In that regard, the
District of Columbia’s standing analysis is also in
direct conflict with this Court’s holding in Lujan that
a litigant “who has been accorded a procedural right
to protect his concrete interests can assert that
right without meeting all the normal standards of
redressability and immediacy.” Lujan, 504 at 572, n.7.
“The regulation of utilities is one of the most important
of the functions traditionally associated with the police
power of the States.” Ark. Elec. Coop., 461 U.S. at 377.
Because the Natural Gas Act vests FERC with jurisdiction over interstate pipeline matters that affect
North Carolina’s quasi-sovereign and parens patriae
interests, the District of Columbia Circuit’s failure
to follow Massachusetts and Lujan deprives North
Carolina of the ability to protect those interests with
regard to interstate pipeline facilities that are constructed and operated within North Carolina’s borders
and rates paid by North Carolina citizens for service
on those facilities.
The Court should grant this Petition because it
presents an opportunity to address questions of exceptional importance—the scope and durability of Massachusetts. Circuit courts have grappled with interpreting Massachusetts’ scope and meaning. See Gvt.
8
Province of Manitoba v. David Bernhardt, D.C. Cir.
Case No. No. 17-5242, Slip Op. at 13 (May 3, 2019)
(“Massachusetts v. EPA is not a parens patriae case.
There is some confusion on this score most possibly
caused by the opinion’s discussion of quasi-sovereign
interests.”); see also Connecticut v. Am. Elec. Power
Co., 582 F.3d 309, 337 (2d Cir. 2009) (“the Massachusetts Court . . . arguably muddled state proprietary and
parens patriae standing”), aff’d by an equally divided
Court; see also id. at 338 (“The question is whether
Massachusetts’ discussion of state standing has an
impact on the analysis of parens patriae standing[.]
That is, what is the role of the Article III parens
patriae standing in relation to the test set out in
Lujan?”); Texas v. United States, 809 F.3d 134 (5th Cir.
2015) (affording special solicitude doctrine relying on
parens patriae standing), aff’d by an equally divided
Court, 136 S. Ct. 2271, 2272 (2016).
A. The United States Court of Appeals for the
District of Columbia Circuit Decision
Conflicts with the Supreme Court’s Decisions in Massachusetts and Lujan.
On appeal before the District of Columbia Circuit,
the North Carolina Commission submitted that it met
the traditional, three-part standing test for establishing Article III standing. Petitioner Initial Brief at 2732; Petitioner Reply Brief at 5-19. However, the North
Carolina Commission also expressly relied on its
special status as a State litigant to establish standing
under Massachusetts. Petitioner Initial Brief at
32-34; Petitioner Reply Brief at 19-21. The District
of Columbia Circuit dismissed the North Carolina
Commission’s appeal without acknowledging that argument or addressing Massachusetts. Pet. Appendix-A
9
at 1a-4a. That decision is in direct conflict with this
Court’s holding in Massachusetts.
Massachusetts held that “States are not normal
litigants for the purposes of invoking federal jurisdiction.” Massachusetts, 549 U.S. at 518. “It is of
considerable relevance that the party seeking review
here is a sovereign state and not, as it was in Lujan,
a private individual.” Id. The distinction between
State and private litigants is based on the fact that
States “surrender[ed] certain sovereign prerogatives”
when they entered the Union. Id. at 518-19. “These
sovereign prerogatives are now lodged in the Federal
Government” and, as such, states have standing to
protect their parens patriae interests where federal
law preempts them from exercising their once-sovereign abilities to protect the interests of their citizens.
Id. at 519, n.17. As such, Massachusetts requires that
courts afford State litigants special solicitude when
analyzing questions of standing. Id., at 518-20.
Like the petitioner in Massachusetts, North Carolina is a sovereign State that surrendered certain
sovereign prerogatives when it joined the Union, i.e.,
the ability to regulate the rates for, and construction
and operation of, pipeline facilities that are in North
Carolina but that are engaged in interstate commerce.
This Court recognizes that “the regulation of utilities
is one of the most important of the functions traditionally associated with the police power of the States.”
Ark. Elec. Coop. Corp. v. Ark. Pub. Serv. Comm’n, 461
U.S. 375, 377 (1983). By surrendering this important
function to the federal government, it is imperative
that North Carolina be afforded access to federal
courts to challenge FERC actions that harm North
Carolina’s quasi-sovereign and parens patriae interests in interstate natural gas pipeline facilities con-
10
structed and operated within its borders and rates
that North Carolina citizens pay for service on those
facilities.
In discussing the special solicitude to which State
litigants are entitled, Massachusetts emphasized that
the State litigant in that proceeding was afforded
a special procedural right to challenge the federal
agency action at issue there:
Given that procedural right [under the Clean
Air Act to challenge the rejection of a rulemaking petition as arbitrary and capricious]
and Massachusetts’ stake in protecting its
quasi-sovereign interests, the Commonwealth
is entitled to special solicitude in our standing
analysis . . . . [T]here is a critical difference
between allowing a State ‘to protect her
citizens from the operation of federal statutes’
(which is what Mellon prohibits) and allowing
a State to assert its rights under federal law
(which it has standing to do).
Id. at 520, n.17. Similarly, in Lujan, a case addressed
by Massachusetts, the Court discussed the important
role of procedural rights in standing inquiries.
There is this much truth to the assertion that
“procedural rights” are special: The person
who has been accorded a procedural right
to protect his concrete interests can assert
that right without meeting all the normal
standards for redressability and immediacy.
Lujan, 504 U.S. at n.7.
The Clean Air Act’s procedural right to challenge
unlawful agency action is substantially similar to the
procedural rights the Natural Gas Act affords to
11
States and State commissions to challenge FERC’s
actions. Under FERC’s implementing regulations,
State commissions are distinct from parties that must
seek, and be granted, leave before they can become a
party to FERC proceedings. See 18 C.F.R. § 385.214(a)(2)
(permitting State Commissions to intervene in proceedings as a matter of right, without motion), Pet.
Appendix-O at 364a-365a. Given its authority under
State law “to . . . appear before federal . . . courts and
agencies as in its opinion may be necessary to secure
for the users of public utility service in [North
Carolina] just and reasonable rates and service” (N.C.
Gen. Stat. § 62-48(a), Pet. Appendix-M at 360a), the
North Carolina Commission exercised this right and
intervened in the underlying certificate proceedings,
which implicated North Carolina’s quasi-sovereign and
parens patriae interests in interstate natural gas
pipeline facilities constructed and operated within its
borders and rates paid by North Carolina ratepayers
for service on those facilities. Pet. Appendix-B at 10a;
Pet. Appendix-D at 94a-95a; Pet. Appendix-F at 144a.
The Natural Gas Act also provides States procedural rights to challenge FERC orders. 15 U.S.C.
§§ 717r(a), (b), Pet. Appendix-I at 347a-349a. The
North Carolina Commission raised substantive concerns
with Transco’s proposals, arguing that they negatively
impacted North Carolina. Pet. Appendix-B at 10a18a; Pet. Appendix-D at 94a-96a; Pet. Appendix-F at
144a-145a. Aggrieved by the manner in which FERC’s
orders dismissed those challenges, the North Carolina
Commission invoked its procedural rights by seeking
rehearing and judicial review under 15 U.S.C. § 717r(a),
(b). Pet. Appendix-C at 81a-82a; Pet. Appendix-E at
130a-131a; Pet. Appendix-G at 275-282a.
12
The District of Columbia Circuit dismissed the North
Carolina Commission’s appeal without acknowledging
that argument or addressing Massachusetts’ and
Lujan’s discussion of the importance of concomitant
procedural rights. Pet. Appendix-A at 1a-4a. As such,
its decision is in direct conflict with Massachusetts
and Lujan. The effect of that erroneous decision is
significant. It deprives a State litigant of access to
federal courts to challenge federal agency actions that
impact the State’s quasi-sovereign and parens patriae
interests in interstate natural gas pipeline facilities
constructed and operated within its borders and rates
paid by North Carolina ratepayers for service on such
facilities.
B. In Reversing the District of Columbia
Circuit’s Dismissal of the North Carolina
Commission’s Appeal, the Court Should
Address the Split Among the Circuits
and Affirm the Scope and Durability of
Massachusetts’ Special Solicitude Doctrine
for State Litigants.
The courts of appeals interpret Massachusetts differently. For example, despite ignoring Massachusetts
altogether in the case below, the District of Columbia
Circuit narrowly construed Massachusetts in Center
for Biological Diversity v. Department of Interior,
563 F.3d 466, 476 (D.C. Cir. 2009), emphasizing
the “uniqueness” of Massachusetts. According to the
District of Columbia Circuit, Massachusetts “stands
only for the limited proposition that, where a harm is
widely shared, a sovereign, suing in its individual
interest, has standing to sue where that sovereign’s
individual interests are harmed, wholly apart from the
alleged general harm.” Id. at 477. In stark contrast,
the Fifth Circuit found it “obvious that being a state
13
greatly matters in the standing inquiry, and it makes
no difference . . . whether [that] means that states are
afforded a relaxed standing inquiry by virtue of their
statehood or whether their statehood, in [and] of itself,
helps confer standing.” Texas v. United States, 809
F.3d 134, n.26 (5th Cir. 2015), aff’d by an equally
divided Court, 136 S. Ct. 2271, 2272 (2016) (internal
quotations omitted).
Similar to the Fifth Circuit’s interpretation, but in
contrast to the District of Columbia Circuit’s narrow
interpretation in Centers for Biological Diversity,
District of Columbia Circuit Judge Brown opined that
“[S]tate litigants” are afforded “laxity” in the standing
analysis because “the [Supreme] Court lowered the
bar [in Massachusetts], ruling that state litigants were
‘entitled to special solicitude’” that “likely does not
extend to non-state litigants . . . who must clear the
ordinary hurdles to standing.” Arpaio v. Obama, 797
F.3d 11, 27 (D.C. Cir. 2015) (Brown, J., concurring).
The Second Circuit has grappled with how to interpret and apply Massachusetts. For example, it suggested that “the Massachusetts Court . . . arguably
muddled state proprietary and parens patriae standing.” Connecticut v. Am. Elec. Power Co., 582 F.3d 309,
337 (2d Cir. 2009), juris. aff’d by an equally divided
court, 131 S. Ct. 2527, 2535 (2011); see also id. at 338
(“The question is whether Massachusetts’ discussion of
state standing has an impact on the analysis of parens
patriae standing[.] That is, what is the role of
the Article III parens patriae standing in relation to
the test set out in Lujan?”). Despite acknowledging
“confusion” on Massachusetts’ impact on the analysis
of parens patriae standing, the District of Columbia
Circuit purports to know the answers to these
questions. See Gvt. Province of Manitoba v. David
14
Bernhardt, D.C. Cir. Case No. No. 17-5242, Slip Op.
at 13 (May 3, 2019) (“Massachusetts v. EPA is not a
parens patriae case.”). Notably, the Fifth Circuit’s
Texas v. United States decision did not rely on parens
patriae standing in affording special solicitude to the
State litigant.
As demonstrated above, this Petition raises a question of exceptional importance. Indeed, the Court has
twice granted petitions for certiorari that addressed
Massachusetts, splitting four-to-four both times. Texas
v. United States, 136 S. Ct. at 2272; Connecticut v.
Am. Elec. Power Co., 131 S. Ct. at 2535. This Petition
represents a unique opportunity to address this exceptional issue and provide critical clarity to State
litigants that may be denied access to federal courts in
circuits that construe Massachusetts narrowly. In that
regard, had the North Carolina Commission’s appeal
been addressed by the Fifth Circuit, instead of the
District of Columbia Circuit, it is likely that North
Carolina would not have been denied the ability
to challenge FERC orders that directly impact its
quasi-sovereign and parens patriae interests. Thus, in
addition to the importance of granting this Petition
and allowing North Carolina the ability to ensure
the federal government protects its interests, the
Court should grant this Petition to clarify and affirm
the scope and durability of Massachusetts’ special
solicitude doctrine for all State litigants.
15
CONCLUSION
The Petition for a writ of certiorari should be
granted for the foregoing reasons.
Respectfully submitted,
KATHLEEN L. MAZURE
Counsel of Record
JASON T. GRAY
DUNCAN & ALLEN
1730 Rhode Island Avenue, NW
Suite 700
Washington, DC 20036
(202) 289-8400
klm@duncanallen.com
jtg@duncanallen.com
Counsel for Petitioner
July 2, 2019
APPENDIX
1a
APPENDIX A
UNITED STATES COURT OF APPEALS
FOR THE DISTRICT OF COLUMBIA CIRCUIT
[Filed: April 3, 2019]
————
No. 18-1018
————
NORTH CAROLINA UTILITIES COMMISSION,
Petitioner,
v.
FEDERAL ENERGY REGULATORY COMMISSION,
Respondent,
PUBLIC SERVICE COMMISSION OF THE STATE OF
NEW YORK AND TRANSCONTINENTAL
GAS PIPE LINE COMPANY, LLC,
Intervenors.
————
Consolidated with 18-1019, 18-1020
————
On Petitions for Review of Orders of the
Federal Energy Regulatory Commission
————
September Term, 2018
————
Before: GARLAND, Chief Judge, and GRIFFITH and
WILKINS, Circuit Judges.
————
2a
JUDGMENT
This appeal was considered on the record from the
Federal Energy Regulatory Commission (“FERC”) and
on the briefs of the parties and oral arguments of
counsel. The court has accorded the issues full consideration and has determined that they do not warrant
a published opinion. See D.C. CIR. R. 36(d). For the
reasons stated below, it is
ORDERED and ADJUDGED that the petition for
review be DISMISSED for lack of jurisdiction.
Petitioner North Carolina Utilities Commission
(“NCUC”) and Intervenor New York State Public
Service Commission (“NYSPSC”) ask this Court to
set aside three FERC orders granting certificates
to Transcontinental Gas Pipe Line Company, LLC
(“Transco”) to construct and operate interstate natural gas pipeline projects – the Virginia Southside
Expansion Project, the Dalton Expansion Project, and
the Atlantic Sunrise Project – in the Eastern United
States. NCUC and NYSPSC contend that the recourse
rate used in FERC’s certification orders relies on
an outdated and inflated pre-tax return. Thus, they
argue, the agreed-upon negotiated rate is tainted,
given FERC’s intention for recourse rates to constrain
a company’s ability to exercise market power during
rate negotiations.
The Natural Gas Act instructs that only “aggrieved”
persons may seek judicial review of a FERC order. 15
U.S.C. § 717r(b). “A party is aggrieved only ‘if it
can establish both the constitutional and prudential
requirements for standing.’” PNGTS Shipper’s Grp. v.
FERC, 592 F.3d 132, 136 (D.C. Cir. 2010) (quoting
Exxon Mobil Corp. v. FERC, 571 F.3d 1208, 1219 (D.C.
Cir. 2009)). The “irreducible constitutional minimum”
3a
of standing requires that a petitioner allege an “an
injury in fact” that is “concrete and particularized” and
“actual or imminent, not conjectural or hypothetical.”
Lujan v. Defenders of Wildlife, 504 U.S. 555, 559-61
(1992). These standing requirements apply equally
to intervenors. Alabama Mun. Distributors Group. v.
FERC, 300 F.3d 877, 879 n.2 (D.C. Cir. 2002) (per
curiam).
Petitioner and Intervenor lack standing because
they have failed to provide sufficient evidence to
establish injury in fact. NCUC “assume[s]” that ratepayers in its state will use the facilities certificated
on the Atlantic Sunrise Project. Appellant’s Br. 31.
NYSPSC, through declaration from the Deputy
Director for Natural Gas and Water within the Office
of Electricity, Gas, and Water at the New York State
Department of Public Service, insists that the Atlantic
Sunrise’s project shippers will “almost certainly exercise
their contractual rights to use the expansion capacity
to ship at least some of their gas to New York.”
McCarran Declaration 7-8. But neither NCUC nor
NYSPSC has shown a “substantial probability” that
any capacity from the Atlantic Sunrise project will
flow into their respective states, nor have they shown
that any end-users in their states will pay higher rates
as a result of the project. Kansas Corp. Comm’n v.
FERC, 881 F.3d 924, 930 (D.C. Cir. 2018). Indeed, with
respect to the Dalton Expansion or Virginia Southside
Expansion Projects, they offer no evidence of injury.
Any harm is therefore either non-existent or “conjectural or hypothetical,” which does not suffice to
demonstrate injury in fact. Id.
Pursuant to D.C. Circuit Rule 36, this disposition
will not be published. The Clerk is directed to withhold
issuance of the mandate herein until seven days after
4a
resolution of any timely petition for rehearing or
petition for rehearing en banc. See FED. R. APP. P.
41(b); D.C. CIR. R. 41.
Per Curiam
FOR THE COURT:
Mark J. Langer, Clerk
BY:
/s/
Scott H. Atchue
Deputy Clerk
5a
APPENDIX B
156 FERC ¶ 61,092
UNITED STATES OF AMERICA
FEDERAL ENERGY REGULATORY COMMISSION
Docket No. CP15-117-000
Before Commissioners: Norman C. Bay, Chairman;
Cheryl A. LaFleur, Tony Clark,
and Colette D. Honorable.
Transcontinental Gas Pipe Line Company, LLC
ORDER ISSUING CERTIFICATE
(Issued August 3, 2016)
1. On March 19, 2015, Transcontinental Gas Pipe
Line Company, LLC (Transco) filed an application
pursuant to section 7(c) of the Natural Gas Act (NGA)1
and Part 157 of the Commission’s regulations for a
certificate of public convenience and necessity authorizing it to construct, lease, and operate pipeline,
compression, metering, and appurtenant facilities in
Virginia, North Carolina, and Georgia (Dalton Expansion
Project). As discussed below, the Commission will grant
the requested authorizations, subject to conditions.
I. Background and Proposal
A. Construction of Facilities
2. Transco is a natural gas company, as defined by
section 2(6) of the NGA,2 which transports natural gas
in interstate commerce. Transco’s natural gas transmission system extends through Texas, Louisiana, the
offshore Gulf of Mexico area, Mississippi, Alabama,
1
15 U.S.C. § 717f(c) (2012).
2
Id. § 717a(6).
6a
Georgia, South Carolina, North Carolina, Virginia,
Maryland, Pennsylvania, and New Jersey, to its
termini in the New York City metropolitan area.
3. Transco proposes to construct and operate
approximately 114.99 miles of 30-, 24-, 20-, and 16inch diameter pipeline (Dalton Lateral), three meter
stations, and one compressor station (Compressor
Station 116) in Georgia, as well as valves, yard piping,
and other appurtenant facilities in Virginia and North
Carolina. Specifically, Transco proposes to construct
and operate:
• Dalton Lateral Segment 1 – Approximately 7.6
miles of 30-inch-diameter pipeline in Coweta
and Carroll Counties, Georgia, from the discharge of the existing Compressor Station 115
to the proposed Compressor Station 116;
• Dalton Lateral Segment 2 – Approximately 51.3
miles of 24-inch-diameter pipeline in Carroll,
Douglas, Paulding, and Bartow Counties, Georgia,
from the discharge of proposed Compressor
Station 116 to the proposed Beasley Road Meter
Station;
• Dalton Lateral Segment 3 – Approximately 53.8
miles of 20-inch-diameter pipeline in Bartow,
Gordon, Murray, and Whitfield Counties, Georgia,
from the proposed Beasley Road Meter Station
to the proposed Looper Bridge Road Meter
Station;
• AGL Spur Lateral – Approximately 2.0 miles of
16-inch-diameter pipeline in Murray County,
Georgia, from milepost (MP) 105.2 of the Dalton
Lateral to the proposed Murray Meter Station;
7a
• Beasley Road Meter Station (formally known
as the AGL-Bartow Meter Station) – a new
190,000 dekatherms (Dth) per day meter
station in Bartow County, Georgia;
• Looper Bridge Road Meter Station (formally
known as the Oglethorpe-Smith Meter Station) – a new 208,000 Dth per day meter station
in Murray County, Georgia;
• Murray Meter Station (formally known as the
AGL-Murray Meter Station) – a new 50,000 Dth
per day meter station in Murray County,
Georgia;
• Compressor Station 116 – a new 21,830 horsepower compressor station in Carroll County,
Georgia, with two Solar Taurus 70 gas turbine
driven compressor units near MP 7.6 on the
Dalton Lateral;
• Valves and yard piping for south flow compression at Compressor Stations 165 in Pittsylvania
County, Virginia, and 180 in Prince William
County, Virginia;
• Odor masking/deodorization of valves at valve
sites between Compressor Stations 160 in
Rockingham County, North Carolina, and 165
in Pittsylvania County, Virginia;
• Odor detection and supplemental odorization
at 20 delivery meters on the South Virginia
Lateral and between Compressor Stations 160
and 165 in Rockingham, Northampton and
Hertford Counties, North Carolina, and
Pittsylvania, Brunswick, Mecklenburg, Halifax,
and Greensville Counties, Virginia;
8a
• Valve site masking/deodorization at Compressor
Station 167 in Mecklenburg County, Virginia;
and
• Related appurtenant underground and aboveground facilities.
4. Transco states that the proposed project will
enable it to provide 448,000 Dth per day of incremental firm transportation service from a receipt point in
Zone 6 on its mainline in Mercer County, New Jersey,
for delivery to an interconnection with Gulf South
Pipeline Company, LP in Pike County, Mississippi,
and to interconnections in northwest Georgia through
the proposed Dalton Lateral.
5. Transco held an open season from May 30
through June 28, 2012. As a result of the open season,
Transco executed binding precedent agreements with
Atlanta Gas Light Company (Atlanta Gas Light or
AGL) and Oglethorpe Power Corporation (Oglethorpe)
for 240,000 and 208,000 Dth per day of firm transportation service, respectively, for 25 years. This
represents all of the capacity associated with the
proposed Dalton Expansion Project.
6. The project’s estimated cost is approximately
$471.9 million. Transco states that it will undertake
permanent financing at a later date as part of its
overall, long-term financing program. Transco has proposed an incremental recourse reservation rate for
firm transportation service on the project facilities,
as described in more detail below. Atlanta Gas Light
and Oglethorpe have agreed to pay a negotiated rate.
Transco will provide service under the terms and
conditions of its existing Rate Schedule FT.
9a
B. Lease of Facilities
7. Transco and Dogwood Enterprise Holdings, Inc.
(Dogwood) will jointly own the Dalton Lateral, as
tenants in common, with each holding a 50 percent
undivided ownership interest.3 Dogwood will hold its
50 percent ownership interest as a “passive owner” of
the lateral. On the in-service date of the Dalton
Lateral, Dogwood will lease its ownership interest in
the lateral, including its share of the capacity rights,
to Transco, which will have full possessory, operational, and capacity rights.
8. The lease agreement provides that Dogwood and
Transco will jointly fund the cost to construct the
Dalton Lateral facilities in proportion to their respective ownership interests. Transco is the sole applicant
for the NGA section 7(c) certificate to construct and
operate the Dalton Lateral, as Dogwood is not currently an NGA jurisdictional entity and does not
intend to become one as part of the Dalton Lateral
ownership structure.
II. Notice, Interventions, and Procedural Issues
9. Notice of Transco’s application was published in
the Federal Register on April 10, 2015 (80 Fed. Reg.
19,312). The parties listed in Appendix A filed timely,
unopposed motions to intervene.4
10. The parties listed in Appendix B filed late
motions to intervene. We will grant the late-filed
motions to intervene, since to do so at this stage of the
3
Dogwood is an affiliate of AGL Resources, the parent
company of Atlanta Gas Light.
4
Timely, unopposed motions to intervene are granted by
operation of Rule 214 of the Commission’s Rules of Practice and
Procedure. See 18 C.F.R. § 385.214 (2015).
10a
proceeding will not delay, disrupt, or unfairly prejudice the proceeding or other parties.5
11. The North Carolina Utilities Commission and
the New York State Public Service Commission (State
Commissions) filed a joint protest to Transco’s application. Transco filed an answer to the State Commissions’
protest and the State Commissions filed an answer to
Transco’s answer. Although the Commission’s Rules of
Practice and Procedure do not permit answers to
protests or answers to answers, the Commission finds
good cause to waive its rules and accept the answers
because they provide information that has assisted in
our decision making process.6
12. The Bartow County School System and Bartow
County Board of Education (Bartow), the 1460
Partnership, LLLP (1460 Partnership), and the
State Commissions request an evidentiary hearing.
Specifically, Bartow seeks a hearing on issues regarding the route of the Dalton Lateral, claiming that the
pipeline is proposed to be located at an unsafe distance
from two elementary schools and that the pipeline’s
proposed location will interfere with its ability to
expand the schools on land that it specifically acquired
for that purpose. The 1460 Partnership seeks a
hearing on the route of the lateral across the Pole Cat
Creek Farms, over which it has a fee simple property
interest.7 The State Commissions seek a hearing on
(1) Transco’s use of a 15.34 percent pre-tax rate of
5
See 18 C.F.R. § 385.214(c)(2) (2015).
6
Id. § 385.213(a)(2).
7
The Pole Cat Creek Farms is an undeveloped tract of land,
consisting of 360 acres of forest wetland, freshwater lake, and
field meadow. The 1460 Partnership states that the tract is home
to more than 50 types of plants and 150 types of animals.
11a
return in developing its proposed recourse rates and
(2) whether the project is being subsidized by prior
expansions that created southbound capacity on Transco’s
mainline. The State Commissions also request that we
partially consolidate this proceeding with Transco’s
proposals to construct and operate the Virginia
Southside Expansion Project II8 and the Atlantic
Sunrise Project9 in order to address issues about
Transco’s pre-tax rate of return.
13. Although our regulations provide for a hearing,
neither section 7 of the NGA nor our regulations
require that such hearing be a trial-type evidentiary
hearing.10 When, as is usually the case, the written
record provides a sufficient basis for resolving the
relevant issues, it is our practice to provide for a paper
hearing.11 That is the case here. We have reviewed the
8
In the Virginia Southside Expansion Project II, Transco was
authorized to construct and operate approximately 4.33 miles of
pipeline and compression facilities. See Transcontinental Gas
Pipeline Co., LLC, 156 FERC ¶ 61,022 (2016).
9
In the Atlantic Sunrise Project, Docket No. CP15-138-000,
Transco proposes to construct and operate approximately 57.3
miles of 30-inch-diameter pipeline and 125.2 miles of 42-inchdiameter pipeline in Pennsylvania.
10
See Minisink Residents for Environmental Preservation
and Safety v. FERC, 762 F.3d 97, 114 (D.C. Cir. 2014) (“FERC’s
choice whether to hold an evidentiary hearing is generally
discretionary.”).
11
See NE Hub Partners, L.P., 83 FERC ¶ 61,043, at 61,192
(1998), reh’g denied, 90 FERC ¶ 61,142 (2000); Pine Needle LNG
Co., LLC, 77 FERC ¶ 61,229, at 61,916 (1996). Moreover, courts
have recognized that even where there are disputed issues the
Commission need not conduct an evidentiary hearing if the
disputed issues “may be adequately resolved on the written
record.” Minisink Residents, 762 F.3d at 114 (quoting Cajun Elec.
Power Coop., Inc. v. FERC, 28 F.3d 173, 177 (D.C. Cir. 1994)).
12a
requests for an evidentiary hearing by Bartow, the
1460 Partnership, and the State Commissions and
conclude that all issues of material fact relating to
Transco’s proposal are capable of being resolved on the
basis of the written record. Accordingly, we will deny
the requests for a formal hearing. As to the State
Commissions’ request for partial consolidation, the
Commission’s policy is to consolidate matters only if a
trial-type evidentiary hearing is required to resolve
common issues of law and fact and consolidation will
ultimately result in greater administrative efficiency.12
Since there is no need for an evidentiary hearing in
this proceeding, we will deny the State Commissions’
request for partial consolidation.
14. The Natural Gas Supply Association, Atlanta
Gas Light, and Oglethorpe filed comments supporting
the project. Numerous other parties filed comments
regarding the routing of the Dalton Lateral, safety,
sufficiency of information, and potential aesthetic,
economic, and environmental impacts of the proposal.
The concerns raised in the State Commissions’ protest
and in the comments by the other parties are addressed
below or in the Environmental Assessment (EA).
III. Discussion
15. Since Transco proposes to construct and operate
facilities used to transport natural gas in interstate
commerce subject to the jurisdiction of the Commission,
12
See Columbia Gulf Transmission Co., 139 FERC ¶ 61,236, at
P 20 (2012); Midcontinent Express Pipeline LLC, 124 FERC
¶ 61,089, at P 27 (2008); Startrans IO, L.L.C., 122 FERC ¶ 61,253,
at P 25 (2008); see also Mobil Oil Explor. & Prod. Serv. v. United
Distrib. Cos., 498 U.S. 211, 230-31 (1991) (agencies “enjoy[] broad
discretion” in determining how best to order its proceedings).
13a
the proposal is subject to the requirements of subsections (c) and (e) of section 7 of the NGA.13
A. Certificate Policy Statement
16. The Certificate Policy Statement provides guidance for evaluating proposals for new construction.14
The Certificate Policy Statement establishes criteria
for determining whether there is a need for a proposed
project and whether the proposed project will serve
the public interest. The Certificate Policy Statement
explains that in deciding whether to authorize the
construction of major new natural gas facilities, the
Commission balances the public benefits against the
potential adverse consequences. The Commission’s
goal is to give appropriate consideration to the enhancement of competitive transportation alternatives, the
possibility of overbuilding, subsidization by existing
customers, the applicant’s responsibility for unsubscribed capacity, the avoidance of unnecessary disruptions of the environment, and the unneeded exercise of
eminent domain in evaluating new pipeline construction.
17. Under this policy, the threshold requirement for
pipelines proposing new projects is that the pipeline
must be prepared to financially support the project
without relying on subsidization from existing customers. The next step is to determine whether the
applicant has made efforts to eliminate or minimize
any adverse effects the project might have on the
applicant’s existing customers, existing pipelines in
13
14
15 U.S.C. §§ 717f(c) and (e) (2012).
Certification of New Interstate Natural Gas Pipeline Facilities, 88 FERC ¶ 61,227 (1999), clarified, 90 FERC ¶ 61,128,
further clarified, 92 FERC ¶ 61,094 (2000) (Certificate Policy
Statement).
14a
the market and their captive customers, or landowners and communities affected by the construction. If
residual adverse effects on these interest groups are
identified after efforts have been made to minimize
them, the Commission will evaluate the project by
balancing the evidence of public benefits to be
achieved against the residual adverse effects. This is
essentially an economic test. Only when the benefits
outweigh the adverse effects on economic interests will
the Commission proceed to complete the environmental analysis where other interests are considered.
18. As discussed above, the threshold requirement
for a new project is that the applicant must be
prepared to financially support the project without
relying on subsidization from its existing customers.
The Commission has determined that, in general,
where a pipeline proposes an incremental recourse
rate for the project – as Transco does here – the
pipeline satisfies the threshold requirement that the
project will not be subsidized by existing shippers.15
Because Transco proposes to charge an incremental
rate for the services proposed in this proceeding that,
as discussed below, exceeds the existing applicable
system rate, we find that the threshold no-subsidy
requirement under the Certificate Policy Statement
has been met.
19. The State Commissions assert that Transco has
not addressed the possibility that the proposed project
will be subsidized by shippers on Transco’s recentlyapproved Leidy Southeast Project in Pennsylvania,
which has a higher recourse rate than the incremental
recourse rate proposed for this project. The bulk of the
15
See, e.g., Dominion Transmission, Inc., 155 FERC ¶ 61,106
(2016).
15a
Leidy Southeast facilities are upstream of the proposed Dalton facilities and transport gas from receipt
points on Transco’s Leidy Line to Transco’s mainline.
We find that the Leidy Southeast facilities are not
integral to the provision of the proposed Dalton
Expansion Project services. The two projects’ transportation paths and facilities are too dissimilar for
subsidization to be a concern. Thus we find that
existing Leidy Southeast Project shippers will not
subsidize the Dalton Expansion Project shippers.
20. Transco has designed the Dalton Expansion
Project to ensure that there will not be any adverse
impacts on its existing shippers. With respect to other
pipeline’s customers, there will be no adverse impact
on other pipelines in the region or their captive
customers because the Project is not intended to
replace service on other pipelines. Also, no pipeline
company or their captive customers have protested
Transco’s application.
21. Regarding effects on landowners and communities, the proposed Dalton Expansion Project will disturb approximately 1,764 acres of land during construction and about 746.3 acres during operation.
To minimize impacts on landowners, Transco will
collocate approximately 49 percent of the proposed
pipeline facilities with existing rights-of-way and on
previously disturbed property. The modifications to
existing compressor stations will take place within the
fence lines of those existing facilities. Accordingly, we
find that Transco has designed the project to minimize
adverse impacts on landowners and surrounding
communities.
22. Transco has entered into binding precedent
agreements for 25 years with Atlanta Gas Light and
Oglethorpe, which fully subscribe the project. Based
16a
on the benefits the project will provide16 and the
minimal adverse impacts on existing shippers, other
pipelines and their captive customers, and landowners
and surrounding communities, we find, consistent
with the Certificate Policy Statement and NGA section
7(c), that the public convenience and necessity
requires approval of Transco’s proposal, subject to the
conditions discussed below.
B. Rates
1. Pre-tax Rate of Return
23. In their protest, the State Commissions take
issue with Transco’s proposed use of a pre-tax return
of 15.34 percent in calculating its proposed incremental recourse rates in its applications for its Dalton
Expansion Project proposal in this proceeding, as
well as in its recently approved Virginia Southside
Expansion II Project in Docket No. CP15-118-000, and
its proposed Atlantic Sunrise Project in Docket No.
CP15-138-000. The State Commissions acknowledge
that Transco’s use of the specified pre-tax return most
recently approved in a section 4 rate case is consistent
with Commission policy, but they emphasize that
that rate case was fifteen years ago. They argue the
incremental recourse rates approved in the current
proceedings should take into account the significant
changes in financial markets since then.17 The State
16
The shippers state that Commission approval of Transco’s
application will provide more diversified natural gas supply
options (Oglethorpe intervention at 2 and comments in support
of the EA at 2) and enable Atlanta Gas Light to meet growing
customer demands in Georgia (Atlanta Gas Light intervention at
2 and June 10, 2016 support letter at 2).
17
Transco’s last section 4 rate case in which a specified rate of
return was used in calculating Commission-approved rates was
in Docket No. RP01-245-000, et al. A letter order issued in that
17a
Commissions assert that the pre-tax return of 15.34
percent accounts for approximately half of Transco’s
proposed cost of service in these proceedings,18 and
their comments included a discounted cash flow (DCF)
analysis, which they contend reflects current market
conditions and reflects a median rate of return on
equity (ROE) of 10.95 percent for natural gas pipelines.19 They request partial consolidation of these
proceedings to consider the appropriate pre-tax return
in a full evidentiary hearing.
24. As the State Commissions argued in the recent
proceeding regarding Transco’s Virginia Southside
Expansion II Project,20 recent Commission orders
provide valuable perspective indicating that Transco’s
proposed 15.34 percent pre-tax return is not reasonable. They reference the 2015 order where the Commission relied on a DCF analysis for a proxy group of
pipelines based on a six-month period ending March
31, 2011, to limit Portland Natural Gas Transmission
System’s ROE to 11.59 percent, the top of the range of
reasonable returns for which the median ROE was
10.28 percent.21 The State Commissions also point to
docket on July 23, 2002, accepted a partial settlement resolving
cost classification, cost allocation, and rate design subject to
certain reservations and adjustments, and revising Transco’s
generally applicable rates. Transcontinental Gas Pipe Line Corp.,
100 FERC ¶ 61,085, at P 2 (2002).
18
State Commissions’ April 22, 2015 Protest in Docket No.
CP15-117-000, et al.
19
Preliminary Pipeline DCF Analysis Exhibit to State Commissions’ Protest.
20
Transcontinental Gas Pipeline Co., LLC, 156 FERC ¶ 61,022,
at PP 23-26 (2016).
21
Portland Natural Gas Transmission System, Opinion No.
524-A, 150 FERC ¶ 61,107, at P 195 (2015).
18a
the Commission’s 2013 orders that limited the ROEs
for El Paso Natural Gas Company, L.L.C. and Kern
River Gas Transmission Company to 10.5 percent and
11.55 percent, respectively.22
25. Transco’s answer emphasizes that this proceeding and the proceedings on its proposed Virginia
Southside Expansion II and Atlantic Sunrise projects
are section 7 certificate proceedings, not section 4 rate
cases, and that its proposed recourse rates in these
certificate proceedings will be initial section 7 rates for
incremental services using new expansion capacity.
Transco further asserts its proposed initial section 7
recourse rates are consistent with Commission policy
in section 7 proceedings, in that they are appropriately
designed to recover each project’s incremental cost of
service.23 In the State Commissions’ answer to Transco’s
answer, they contend that when the Commission grants
a pipeline negotiated rate authority, it relies on the
availability of cost-based recourse rates to prevent the
pipeline from exercising market power by ensuring
that shippers will have the option of choosing to pay
cost-based recourse rates for expansion capacity that
becomes available on either an interruptible or firm
22
El Paso Natural Gas Co., L.L.C., Opinion No. 528, 145
FERC ¶ 61,040, at P 686 (2013); Kern River Gas Transmission
Co., Opinion No. 486-F, 142 FERC ¶ 61,132, at P 263 (2013).
23
Transco cites the Commission’s order that certificated its
Rock Springs Lateral and additional mainline compression to
provide service for another new electric generating plant. In that
order, the Commission approved Transco’s proposed incremental
recourse rate for that expansion capacity, which was calculated
using the pre-tax return of 15.34 percent from its settlement
rates in Docket No. RP01-245. Transcontinental Gas Pipe Line
Co., LLC, 150 FERC ¶ 61,205, at P 17 (2015).
19a
basis. Therefore, the State Commissions assert that
even if a pipeline has negotiated rate agreements for
all of the expansion capacity proposed in a certificate
proceeding, the recourse rates nevertheless need to be
properly designed and based on a reasonable estimate
of the actual costs to construct and operate the
expansion capacity.
24
26. The State Commissions are correct that “the
predicate for permitting a pipeline to charge a negotiated rate is that capacity is available at the recourse
rate,”25 and the Commission therefore requires that
shippers have the option of choosing to pay a costbased recourse rate for expansion capacity that
becomes available. However, as the State Commissions acknowledge, the Commission’s consistent policy
in section 7 certificate proceedings is to require that a
pipeline’s cost-based recourse rates for incrementallypriced expansion capacity be designed using the rate
of return from its most recent general rate case
approved by the Commission under section 4 of the
NGA in which a specified rate of return was used to
calculate the rates.26 Transco’s proposed incremental
24
State Commissions’ May 27, 2015 Answer at 2 (citing
Alternatives to Traditional Cost-of-Service Ratemaking, 74 FERC
¶ 61,076).
25
Columbia Gas Transmission Corp., 97 FERC ¶ 61,221, at
62,004 (2001) (citing Alternatives to Traditional Cost-of-Service
Ratemaking for Natural Gas Pipelines; Regulation of Negotiated
Transportation Services of Natural Gas Pipelines, 74 FERC
¶ 61,076).
26
See, e.g., Trunkline Gas Co., LLC, 135 FERC ¶ 61,019, at
P 33 (2011); Florida Gas Transmission Co., LLC, 132 FERC
¶ 61,040, at P 35 & n.12 (2010); Northwest Pipeline Corp., 98
FERC ¶ 61,352, at 62,499 (2002); and Mojave Pipeline Co., 69
FERC ¶ 61,244, at 61,925 (1994). See also Dominion Cove Point
LNG, LP, 115 FERC ¶ 61,337, at P 132 (2006), order on reh’g, 118
20a
recourse rate for the Dalton Expansion Project is
based on the specified pre-tax return of 15.34 percent
underlying the design of its approved settlement rates
in Docket No. RP01-245-000, et al.27 Since Transco’s
most recently approved general section 4 rate case
settlements in Docket Nos. RP12-993-000, et al.28 and
RP06-569-004, et al.29 were both “black box” settle-
FERC ¶ 61,007, at PP 120 & 122-123 (2007) (allowing, on
rehearing, Dominion Cove Point LNG to recalculate incremental
rates using the rates of return ultimately approved in its pending
rate case, as opposed to its proposed rates of return). If a
pipeline’s most recent general section 4 rate case involved a
settlement that did not specify a rate of return or pre-tax return,
the Commission’s policy requires that incremental rates in the
pipeline’s certificate proceedings be calculated using the rate of
return or pre-tax return from its most recent general section 4
rate case (or rate case settlement) in which a specified return
component was used to calculate the approved rates. See, e.g.,
Equitrans, L.P., 117 FERC ¶ 61,184, at P 38 (2006). This policy
applies even if a pipeline calculated its proposed incremental
rates for expansion capacity using a rate of return lower than the
most recently approved specified rate of return. Id. (rejecting
Equitrans’ proposed use of 14.25 percent ROE component for
incremental rates for mainline extension and requiring
recalculation using the specified pre-tax rate of return of 15
percent that was approved in its rate case).
27
Transcontinental Gas Pipe Line Corp., 100 FERC ¶ 61,085.
28
Transcontinental Gas Pipe Line Co., LLC, 144 FERC
¶ 63,029, at P 13 (2013) (certifying to the Commission an
uncontested settlement in which, “[w]ith the exception of certain
expressly designated items, the cost of service agreement was
reached on a ‘black box’ basis”); Transcontinental Gas Pipeline
Co., LLC, 145 FERC ¶ 61,205 (2013) (approving and accepting
tariff records to implement rate case settlement).
29
Transcontinental Gas Pipe Line Corp., 122 FERC ¶ 61,213
(2008) (approving and accepting tariff records to implement rate
case settlement); Transcontinental Gas Pipe Line Co., LLC, 147
FERC ¶ 61,102, at P 53 (2014) (explaining that the settlement
21a
ments that did not specify the rate of return or most
other cost of service components used to calculate
the settlement rates, Transco calculated its proposed
incremental rates in this certificate proceeding consistent with Commission policy by using the last
Commission-approved specified pre-tax return of
15.34 percent from its prior rate proceeding in Docket
No. RP01-245.
27. Further, in section 7 certificate proceedings the
Commission reviews initial rates for service using
proposed new pipeline capacity under the public convenience and necessity standard, which is a less
rigorous standard than the just and reasonable standard under NGA sections 4 and 5.30 The Commission
reached in Docket No. RP06-569 was a “black box” settlement
that did not specify a rate of return).
30
Atlantic Refining Co. v. Public Serv. Comm’n of New York,
360 U.S. 378 (1959) (CATCO). In CATCO, the Court contrasted
the Commission’s authority under sections 4 and 5 of the NGA to
approve changes to existing rates using existing facilities and its
authority under section 7 to approve initial rates for new services
and services using new facilities. The Court recognized “the
inordinate delay” that can be associated with a full-evidentiary
rate proceeding and concluded that was the reason why, unlike
sections 4 and 5, section 7 does not require the Commission to
make a determination that an applicant’s proposed initial rates
are or will be just and reasonable before the Commission
certificates new facilities, expansion capacity, and/or services. Id.
at 390. The Court stressed that in deciding under section 7(c)
whether proposed new facilities or services are required by the
public convenience and necessity, the Commission is required to
“evaluate all factors bearing on the public interest,” and an
applicant’s proposed initial rates are not “the only factor bearing
on the public convenience and necessity.” Id. at 391. Thus, as
explained by the Court, “[t]he Congress, in § 7(e), has authorized
the Commission to condition certificates in such manner as
the public convenience and necessity may require when the
Commission exercises authority under section 7,” id., and the
22a
develops the recourse rate for expansion capacity
based on the pipeline’s estimated cost of service. As
discussed above, the State Commissions’ protest
included a DCF analysis for natural gas pipelines,
which they contend reflects current market conditions
and a median ROE of 10.95 percent. However, the
Commission does not believe that conducting DCF
analysis in individual certificate proceedings would be
the most effective or efficient way for determining the
appropriate ROEs for proposed pipeline expansions.
While parties have the opportunity in section 4 rate
proceedings to file and examine testimony with regard
to the composition of the proxy group to use in the DCF
analysis, the growth rates used in the analysis, and
the pipeline’s position within the zone of reasonableness with regard to risk, it would be difficult, if
not impossible, to complete this type of analysis in
section 7 certificate proceedings in a timely manner
and attempting to do so would unnecessarily delay
proposed projects with time sensitive in-service schedules. The Commission’s current policy of calculating
incremental rates for expansion capacity using the
Commission-approved ROEs underling pipelines’ existing rates is an appropriate exercise of its discretion
in section 7 certificate proceedings to approve initial
rates that will “hold the line” until just and reasonable
rates are adjudicated under section 4 or 5 of the NGA.
28. Here, Transco is required to file an NGA general
section 4 rate case by August 31, 2018, pursuant to the
comeback provision in Article 6 of the settlement in
Commission therefore has the discretion in section 7 certificate
proceedings to approve initial rates that will “hold the line” and
“ensure that the consuming public may be protected” while
awaiting adjudication of just and reasonable rates under the
more time-consuming ratemaking sections of the NGA. Id. at 392.
23a
Docket No. RP12-993. Parties in that future rate case
will have an opportunity to review Transco’s pre-tax
return and other cost of service components. In
addition, given the possibility that that rate case could
result in another settlement for rates that are not
based on a specified rate of return and, as discussed
above, the Commission’s policy in section 7 certificate
proceedings is to require that a pipeline’s initial
rates for expansion capacity be designed using a
Commission-approved, specified rate of return, the
Commission would advise that parties in the rate case
use that opportunity to address issues of concern
relating to the rate of return that should be used in
calculating initial rates in Transco’s future certificate
proceedings.32
31
29. For the reasons discussed above, and consistent
with the rate of return accepted for the Virginia
Southside Expansion II Project,33 the Commission
finds that it is appropriate to apply its general policy
and accepts Transco’s use of a pre-tax return of 15.34
percent to calculate Transco’s initial recourse rate in
this proceeding. Parties should raise, in Transco’s
upcoming general rate case, any issues and concerns
they have regarding the rate of return or other cost of
service components to be used in calculating Transco’s
recourse rates in subsequent certificate proceedings.
31
Transcontinental Gas Pipe Line Co., LLC, 144 FERC
¶ 63,029.
32
See, e.g., Eastern Shore Natural Gas Co., 138 FERC ¶ 61,050
(2012) (approving settlement that established rates on “black
box” basis but provided a specified pre-tax rate of return).
33
Transcontinental Gas Pipeline Co., 156 FERC ¶ 61,022 at
P 26.
24a
2. Initial Rates
30. Transco proposes an initial incremental recourse
reservation charge of $0.50580 per Dth/day under its
existing Rate Schedule FT for service on the project.
In support of the proposed initial rates, Transco submitted an incremental cost of service and rate design
study showing the derivation of the recourse rate
under the project based on a total first year cost of
service of $82,708,551 and billing determinants of
448,000 Dth/day.34 The proposed cost of service is
based on a pre-tax rate of return of 15.34 percent, and
Transco’s system depreciation rates of 2.61 percent
for onshore transmission facilities, including negative
salvage, and 4.97 percent for solar turbines.35 The
proposed cost of service also includes the lease payments to Dogwood at an annualized amount equal to
approximately $25,691,000.
31. On October 29, 2015, the Commission issued a
data request directing Transco to provide a breakdown
of its Operation and Maintenance (O&M) expenses by
FERC account number and labor and non-labor costs
for the project. In response, Transco identified a total
of $357,883 in non-labor O&M costs in Account Nos.
853 and 864.36 These non-labor costs are classified as
variable costs, and section 284.7(e) of the Commission’s regulations does not allow variable costs to be
recovered through the reservation charge.37 Therefore,
34
See Transco’s Application at Exhibit P.
35
See Transcontinental Gas Pipe Line Co., LLC, 145 FERC
¶ 61,205, which established the current system depreciation rate
and the current negative salvage rate.
36
Transco’s November 2, 2015 Data Response, Response No. 1
and Schedule 1.
37
18 C.F.R. § 284.7(e) (2015).
25a
Transco must recalculate its incremental recourse
reservation rate to reflect the removal of variable costs.
32. Transco’s proposed incremental reservation charge
of $0.50590 per Dth/day is higher than the currently
applicable Rate Schedule FT Zone 6-4 reservation
charge of $0.41704 per Dth/day. We do not expect
that recalculation of the proposed rate to remove the
variable costs identified above will result in an incremental rate that is lower than the existing system
rate. Accordingly, because an appropriately calculated
incremental reservation charge will be higher than the
currently applicable Rate Schedule FT reservation
charge, the Commission will require use of the recalculated incremental reservation charge as the initial
recourse reservation charge for firm service using the
expansion capacity.38
33. Transco did not propose an incremental usage
charge since its initial filing included no variable costs.
An incremental usage charge calculated to recover
the $357,883 in variable costs would be lower than
the currently applicable Rate Schedule FT Zone 6-4
usage charge of $0.02375 per Dth. Therefore, the
Commission will require Transco to charge its currently applicable Rate Schedule FT usage charge for
the project.
34. Transco’s application does not address recourse
rates for interruptible service using the expansion
capacity. Consistent with Commission policy, the Commission will require Transco to charge its currently
38
Under the Certificate Policy Statement there is a presumption that incremental rates should be charged for proposed
expansion capacity if the incremental rate will exceed the
maximum system-wide rate. Certificate Policy Statement, 88
FERC at 61,745.
26a
effective system interruptible rates for interruptible
service using the expansion capacity.39
35. Transco states that Atlanta Gas Light Company
and Oglethorpe have elected to enter into negotiated
rate agreements for their capacity. Transco states that
it will file the negotiated rate agreements prior to the
commencement of service as required by Commission
policy.40
3. Fuel Retention and Electric Power Rates
36. Transco proposes to charge its generally applicable system fuel retention and electric power rates for
service on the project. Transco states that the project
facilities will reduce overall system fuel use (gas fuel
consumption plus the gas equivalent of electric power
consumption) to the benefit of non-project shippers.41
Transco’s fuel study shows that the project impact
of fuel consumption will result in a 30.53 percent
reduction in system fuel use attributable to existing
shippers.42 In view of this, we will approve Transco’s
proposal to charge its generally applicable system gas
39
See, e.g., Trunkline Gas Co., LLC, 153 FERC ¶ 61,300, at
P 62 (2015).
40
Pipelines are required to file any service agreement containing non-conforming provisions and to disclose and identify any
transportation term or agreement in a precedent agreement that
survives the execution of the service agreement. See, e.g., Texas
Eastern Transmission, LP, 149 FERC ¶ 61,198, at P 33 (2014).
41
42
See Transco’s Application at 11, Exhibit Z-1.
Transco’s study was based on ten representative days
between November 1, 2013 and October 31, 2014. Transco states
that the system was modeled with and without the incremental
project facilities and transportation volumes. See Transco’s
Application at Exhibit Z-1.
27a
fuel and electric power rates for service using the
expansion capacity.
4. Inexpensive Expansibility
37. The State Commissions assert that Transco’s
application appears to be deficient because it fails to
address the issue of inexpensive expansibility (i.e.,
whether it was possible to construct the Dalton Expansion Project at a lower cost because of the previous
construction of the Leidy Southeast Project). The State
Commissions claim that the Dalton Expansion Project
allows shippers to transport gas on Transco’s mainline
from New Jersey to Mississippi, but not pay for any
major facilities north of Georgia, which they contend
raises the question of whether this project will be
subsidized by shippers on prior expansions that created southbound capacity on Transco’s mainline. The
State Commissions note that the proposed $0.50580
recourse rate for the Dalton Expansion Project is
significantly lower than the estimated recourse rate of
$0.67393 for Leidy Southeast Project, which will
enable shippers to transport gas from receipt points
on Transco’s Leidy Line in Pennsylvania to various
delivery points along Transco’s mainline as far south
as Transco’s existing Station 85 Zone 4 and 4A pooling
points in Choctaw County, Alabama. Thus, the State
Commissions argue the new Dalton Expansion Project
will allow shippers to transport gas further south on
Transco’s mainline at a lower recourse rate than the
Leidy Southeast Project shippers.
38. Transco states that the inexpensive expansibility doctrine has no application to the Dalton and Leidy
Southeast Projects. Transco states that the Leidy
Southeast Project involves construction of extensive
looping and compression on Transco’s Leidy Line. In
contrast, the Dalton Expansion Project principally
28a
involves the construction of a new, 111-mile lateral
off the Transco mainline in Georgia. Transco states
that the bulk of the Leidy Southeast Project costs are
for facilities upstream of the point where the Dalton
capacity commences, and include pipeline looping
and compressor station horsepower additions on the
Leidy Line necessary to transport gas from the Leidy
Southeast receipt points on the Leidy Line to the
point of interconnection between the Leidy Line and
Transco’s mainline. Thus, Transco asserts that the
Leidy Southeast Project facilities do not beneficially
affect the facility costs underlying the Dalton Expansion
Project. Transco concludes that the primary firm capacity
paths and facilities under the two projects are too dissimilar to consider a roll-in of the costs of the projects.
39. The Commission disagrees with the State
Commissions that the Dalton Expansion Project is a
result of inexpensive expansibility made possible by
the Leidy Southeast Project. As Transco correctly
stated, the bulk of the Leidy Southeast Project are
facilities upstream of the point where the Dalton
capacity commences and were constructed to enable
delivery of gas from Transco’s Leidy Line to Transco’s
mainline. Conversely, the Dalton Expansion Project
transports gas from Transco’s Station 210 Zone 6
Pooling Point in Mercer County, New Jersey, and
transportation of the volumes entering this pool are
not dependent on the Leidy Southeast Project being
constructed. Due to the nature of pipeline construction, service on almost all incremental expansions use
some part of the existing pipeline system to provide
service, since expansion volumes can often be delivered by constructing discrete facilities in key areas to
alleviate bottlenecks or increasing throughput by
adding looping or compression. Thus, as we have here,
the Commission addresses concerns about potential
29a
subsidization by comparing the rate calculated to
recover the costs associated with the proposed expansion capacity to the applicable existing system rate for
the project service and requiring pipelines to use the
higher of the two as the recourse rate for project
service. Given the lack of interdependence between
the Dalton Expansion Project and the Leidy Southeast
Project, there is no basis for basing our subsidization
determination on a comparison, instead, of the rates of
the two expansion projects, as suggested by the State
Commissions.
5. Reporting Incremental Costs
40. Section 154.309 of the Commission’s regulations43
includes bookkeeping and accounting requirements
applicable to all expansions for which incremental
rates are approved to ensure that costs are properly
allocated between pipelines’ existing shippers and
incremental expansion shippers. Therefore, Transco
must keep separate books and accounting of costs and
revenues attributable to Dalton Lateral capacity and
incremental services using that capacity as required
by section 154.309. The books should be maintained
with applicable cross-references. This information
must be in sufficient detail so that the data can be
identified in Statements G, I, and J in any future NGA
section 4 or 5 rate case, and the information must be
provided consistent with Order No. 710.44
43
44
18 C.F.R. § 154.309 (2015).
Revisions to Forms, Statements, and Reporting Requirements
for Natural Gas Pipelines, Order No. 710, FERC Stats. & Regs.
¶ 31,267, at P 23 (2008).
30a
6. Lease Agreement
41. The Dalton Lateral will be jointly owned and
jointly funded by Transco and Dogwood, with each
party holding a 50 percent undivided joint ownership
interest. Dogwood will hold its 50 percent ownership
interest as a “passive owner” of the Lateral. On the inservice date of the project, Dogwood will lease its 50
percent ownership interest to Transco for a primary
term of 25 years. Transco asserts that during the lease
term it will have full possessory and operational rights
to the lateral and will have 100 percent of the capacity
rights on the lateral.
42. The Construction and Ownership Agreement
provides that Dogwood and Transco will jointly fund
the cost to construct the Dalton Lateral facilities in
proportion to their respective ownership interests.
Because Dogwood will be a passive owner, Transco
asserts that the Commission should find that Dogwood
does not require a certificate in connection with the
project. Accordingly, Transco requests that the certificate authority requested herein be granted solely to
Transco and pertain to 100 percent of the Dalton
Lateral facilities.
43. Transco asserts that it will utilize the capacity
rights under the lease, in conjunction with the
capacity to be created by the other project facilities, to
provide transportation services under its Tariff.
Transco further asserts that during the proposed
lease, all operating and maintenance expenses will be
Transco’s responsibility. Transco states that the Lease
Agreement includes a mechanism for Transco and
Dogwood to share maintenance capital expenditures
incurred by Transco to repair or replace the Dalton
Lateral facilities.
31a
44. The Lease Agreement provides for a primary
term of 25 years and may be extended, at Transco’s
option, for two successive five-year terms. Subject to
Transco’s right to extend the term of the Lease
Agreement, the Lease Agreement will continue in
effect for successive one-year extensions until prior
written notice to terminate is provided by Transco to
Dogwood. Transco asserts that at the termination of
the Lease Agreement, possessory and operational
rights to the leased facilities will revert to Dogwood,
subject to the receipt of the necessary authorizations
from the Commission.
45. The Lease Agreement provides that Transco
will pay to Dogwood a fixed monthly payment of
$2,140,916.70 for the 25-year primary term. The
monthly lease charge during each term extension will
be determined in accordance with a formula detailed
in Exhibit A of the Lease Agreement, reflecting an
adjusted annual cost of service for the Dalton Lateral
and a monthly unsubscribed capacity sharing factor,
if any. In addition, Transco will pay Dogwood a
maintenance capital surcharge in the form of a
monthly cost of service payment based on the amount
of maintenance capital expenditures, if any, reimbursed by Dogwood to Transco. Transco asserts that
its annual lease payments to Dogwood under the
Lease Agreement are less than the equivalent cost of
service that would apply if Transco directly owned 100
percent of the Dalton Lateral facilities (i.e., if Transco
constructed Dogwood’s 50 percent ownership share of
the Dalton Lateral instead of leasing Dogwood’s 50
percent ownership share).
46. Consistent with Commission regulations, Transco
proposes to record the lease as a capital lease in
Account 101.1, Property under Capital Leases, and the
32a
related obligation in Account 243, Obligations under
Capital Leases – Current, and Account 227, Obligations under Capital Leases – Noncurrent. Transco
contends that the lease qualifies as a capital lease
because the present value at the beginning of the lease
term of the minimum lease payments exceeds 90
percent of the fair value of the leased property to the
lessor at the inception of the lease. Transco states that
the costs and revenues associated with the project’s
leased facilities will be accounted for separately and
segregated from its other system costs.
47. Historically, the Commission views lease arrangements differently from transportation services under
rate contracts. The Commission views a lease of
interstate pipeline capacity as an acquisition of a
property interest that the lessee acquires in the
capacity of the lessor’s pipeline.45 To enter into a lease
agreement, the lessee generally is required to be a
natural gas company under the NGA and requires
section 7(c) certificate authorization to acquire the
capacity. Once acquired, the lessee in essence owns
that capacity and the capacity is subject to the lessee’s
tariff. The leased capacity is allocated for use by the
lessee’s customers. The lessor, while it may remain the
operator of the pipeline system, no longer has any
rights to use the leased capacity.46
48. The Commission’s practice has been to approve
a lease if it finds that: (1) there are benefits from using
a lease arrangement; (2) the lease payments are less
than, or equal to, the lessor’s firm transportation rates
45
Texas Eastern Transmission Corp., 94 FERC ¶ 61,139, at
61,530 (2001).
46
Texas Gas Transmission, LLC, 113 FERC ¶ 61,185, at P 10
(2005).
33a
for comparable service over the terms of the lease on a
net present value basis; and (3) the lease arrangement
does not adversely affect existing customers.47 We find
that the proposed lease agreement between Transco
and Dogwood satisfies these requirements.48
49. The Commission has found that capacity leases
in general have several potential benefits. Leases
can promote efficient use of existing facilities, avoid
construction of duplicative facilities, reduce the risk of
overbuilding, reduce costs, and minimize environmental impacts.49 In addition, leases can result in
administrative efficiencies for shippers.50
50. The annual amount Transco would pay Dogwood
under the lease is less than what it would cost if
Transco constructed and owned the facilities being
leased from Dogwood; thus, shippers will benefit from
the lease arrangement. During the 25 year primary
term of the Lease Agreement, Transco will pay
47
Midcontinent Express Pipeline LLC, 124 FERC ¶ 61,089
(2008), order on reh’g, 127 FERC ¶ 61,164 (2009), order on
remand, 134 FERC ¶ 61,155 (2011); Colorado Interstate Gas Co.,
122 FERC ¶ 61,256, at P 30 (2008); Gulf South Pipeline Co., L.P.,
119 FERC ¶ 61,281, at P 37 (2007).
48
The second criterion, that “the lease payments [be] less than,
or equal to, the lessor’s firm transportation rates for comparable
service of the terms of the lease on a net present value basis,” is
not applicable to the circumstances here, as Dogwood does not
provide transportation services and thus, has no firm transportation rates to which the lease payments may be compared.
49
See, e.g., Dominion Transmission, Inc., 104 FERC ¶ 61,267,
at P 21 (2003) (Dominion); Texas Gas Transmission, LLC, 113
FERC ¶ 61,185 at P 9; Islander East Pipeline Co., L.L.C., 100
FERC ¶ 61,276, at P 70 (2002).
50
Wyoming Interstate Co., Ltd., 84 FERC ¶ 61,007, at 61,027
(1998), reh’g denied, 87 FERC ¶ 61,011 (1999).
34a
Dogwood a fixed lease payment of $2,140,916.70 per
month for Dogwood’s ownership interest in the Dalton
Lateral. The annualized amount of such lease charge
is $25,691,000,51 which is then compared to the estimated annual cost of service of $46,445,747, assuming
Transco constructed and owned Dogwood’s share of
the Dalton Lateral.52 Since the annual amount to be
paid under the lease is less than the comparable cost
of service if Transco had constructed the facilities,
approval of this lease agreement will reduce Transco’s
costs associated with the project and thus the amount
shippers will pay under the recourse rate by an
estimated $20,754,747 per year.53
51. The State Commissions argue that Transco has
not demonstrated that its annual lease payments will
be less than the equivalent cost of service that would
apply if Transco directly owned 100 percent of the
facilities. The State Commissions assert that Transco’s
analysis of its annual lease payments is deficient,
because while the project lease has a 25-year primary
term, Exhibit N only analyzes one year of the lease.
Therefore, Transco’s analysis does not take into account
the impact of depreciation of the leased facilities on the
cost of service. As the leased facilities are depreciated
over time, the cost of service should decrease due to
the decrease in rate base. The State Commissions
contend that by limiting its analysis to one year,
Transco has failed to show that the lease payments
51
See Exhibit N, Line 14. The annualized amount of such lease
charge was calculated as follows: $2,140,916.70 times 12 equals
approximately $25,691,000.
52
See Exhibit N, Line 13 reflecting an estimated incremental
total cost of service to construct Dogwood’s ownership share of the
Dalton Lateral.
53
See Exhibit N, Line 15.
35a
over the life of the lease will be less than the equivalent cost of service that would apply if Transco directly
owned the facilities.
52. Transco states that it has included in its certificate application an analysis that includes a comparison
of the annual lease charges to an incremental annual
cost of service that would apply if Transco constructed
and owned 100 percent of the project facilities. Transco
states that its analysis used the first year of the lease
arrangement consistent with section 157.14(a)(18) of
the Commission’s regulations, which Transco states
requires Transco to calculate its initial recourse rates
for the project using a cost of service for the first
calendar year of operation after the proposed facilities
are placed in service. Thus, Transco argues that when
comparing Transco’s annual lease payments under the
lease arrangement to the estimated annual cost of
service assuming Transco constructed and owned
Dogwood’s share of the corresponding project facilities,
Transco appropriately used a first-year cost of service
analysis.
53. Transco’s analysis using the first year of the lease
arrangement is consistent with section 157.14(a)(18)
of the Commission’s regulations,54 and our approval
of the lease agreement is consistent with previous
Commission orders in which the Commission approved
the leasing of new capacity being constructed as part
54
Section 157.14(a)(18)(c)(ii)(a) of the Commission’s regulations provides in relevant part that “[w]hen new rates . . . are
proposed . . . [a statement explaining the basis used in arriving
at the proposed rate] shall be accompanied by supporting data
showing . . . system cost of service for the first calendar year of
operation after the proposed facilities are placed in service.”
36a
of a project based on the costs of that capacity.55 With
the lease agreement in place, Transco’s recourse rates
are lower than if Transco had constructed the capacity
itself, because Transco’s cost of service is lower under
the lease. The State Commissions are correct that,
assuming Transco constructed and owned 100 percent
of the facilities, its cost of service should decrease over
time. But, as stated above, rates are based on a first
year cost of service, and the pipeline is under no
obligation to reduce those rates over time. Therefore,
the lease arrangement provides lower rates and a
benefit to shippers.
54. In addition, we find that the lease arrangement
will not adversely affect Transco’s existing customers.
Transco proposes an incremental recourse rate designed
to recover the cost of service attributable to the project
facilities, including the payments under the Lease
Agreement. Therefore, existing shippers will not
subsidize the lease arrangement. In addition, Transco
has agreed to separately account for the costs and
revenues associated with the leased facilities and to
segregate those costs and revenues from its other
system costs during the term of the Lease Agreement.
Accordingly, the lease arrangement will not result in
adverse effects to Transco’s existing customers or on
any other pipelines or its customers.
55. The State Commissions are concerned that at
the termination of the lease agreement, possessory
and operational rights to the leased facilities will
revert to Dogwood, arguing that the use of the lease
ownership structure should not be allowed to evade or
55
See, e.g., Constitution Pipeline Co., 149 FERC ¶ 61,199
(2014); Tennessee Gas Pipeline Co., L.L.C. and National Fuel Gas
Supply Corp., 150 FERC ¶ 61,160 (2015).
37a
weaken the certificate holder’s obligations regarding
continuity of service. Specifically, the State Commissions assert that Transco has not fully fleshed out
the impact of its request that Dogwood, the co-owner
of the leased capacity, be exempt from any certificate
obligations with regard to the leased facilities. The
State Commissions recognize that the reversion at the
end of the term of the lease is subject to the receipt of
the necessary authorization from the Commission;
however, despite that qualification they are concerned
that approval of the lease, including the provision
regarding what occurs at the termination of the lease,
should not prejudge any issues regarding continuity of
service, or any other issue, at the end of the lease.56
The State Commissions assert that the Commission’s
long-standing policy is that when examining proposals
to abandon service, it weighs all relevant factors,
but considers “continuity and stability of existing
services . . . the primary considerations in assessing
whether the public convenience and necessity permit
abandonment.” Accordingly, the State Commissions
request that, in the event the Commission approves
the lease, it should clarify that nothing therein prejudges any issues as to the status of the leased
facilities, or the service provided on those facilities, at
the end of the lease.
56. Transco asserts that it is not requesting pregranted abandonment authority at the end of the
lease term. Transco further asserts that while the
passive owner lessor under the lease arrangement is
not required to apply for certificate authority, any
certificate authority granted will attach to 100 percent
56
State Commission’s Protest at 17 (citing Northern Natural
Gas Co., 142 FERC ¶ 61,120, at PP 10-11 (2013) and El Paso
Natural Gas Co., 136 FERC ¶ 61,180, at P 22 (2011)).
38a
of the project’s facilities and not just to Transco’s
ownership interest. Transco states that if at the end of
the lease the lessor desires to use the facilities for a
purpose other than that authorized by the certificate,
then Transco and the lessor will be required to obtain
the necessary abandonment authority under NGA
section 7(b) and interested parties will have ample
opportunity to participate in the section 7(b) proceeding for such abandonment.
57. The Commission clarifies that upon termination
of the lease at the end of its term or otherwise, Transco
must continue to provide jurisdictional service on the
Dalton Lateral until it requests and is authorized to
abandon the capacity under NGA section 7(b). Similarly,
if Transco files for authorization to abandon the leased
capacity, Dogwood or any other entity seeking to use
the capacity for jurisdictional service will need to file
for and receive the requisite certification authorizations under NGA section 7(c).
C. Environment
58. On April 25, 2014, the Commission staff began
its environmental review of the Dalton Expansion
Project by granting Transco’s request to use the prefiling process and assigning Docket No. PF14-10-000.57
57
Natural Resources Group, LLC (NRG) was selected at that
time as third-party contractor to assist Commission staff in the
development of the environmental assessment for the Dalton
Expansion Project. In September 2014, Environmental Resources
Group (ERM) acquired NRG. Subsequently, ERM notified
Commission staff of a possible conflict of interest, as ERM had
previously been engaged by Transco to provide air permitting
support and air dispersion analyses for inclusion in Transco’s
Dalton Expansion Project application; ERM included updated
Organizational Conflict of Interest forms with its notification. As
mitigation for the potential conflict, ERM proposed to establish
39a
As part of the pre-filing review, staff participated in
open houses sponsored by Transco in Newnan,
Carrollton, Dallas, Cartersville, Calhoun, and Dalton,
Georgia between June 9 and September 25, 2014, to
explain our environmental review process to interested stakeholders.
59. On October 21, 2014, the Commission issued
a Notice of Intent to Prepare an Environmental
Assessment for the Proposed Dalton Expansion Project,
Request for Comments on Environmental Issues, and
Notice of Public Scoping Meetings (NOI). The NOI
was published in the Federal Register58 and mailed
to interested parties including federal, state, and
local officials; elected officials; agency representatives;
environmental and public interest groups; Native
American tribes; local libraries and newspapers; and
affected property owners. FERC environmental staff
conducted three scoping meetings on November 3, 4,
and 5, 2014, in Dalton, Carrollton, and Cartersville,
Georgia to receive verbal scoping comments on the
an internal corporate firewall to isolate NRG and ERM project
and client teams for the duration of the respective third-party
contractor engagements. This mitigation was found to be acceptable. Though wholly-owned by ERM, NRG operated as a separate
entity until after its work for the Commission on the Dalton
Expansion Project was completed. Further, while NRG did review
the analyses done by ERM for Transco, the air dispersion analyses were also independently reviewed by Commission staff and
the conclusions on this modeling presented in the environmental
assessment are those of staff. Moreover, the air permitting
support provided by ERM was also independently reviewed by
the Georgia Department of Natural Resources - Environmental
Protection Division, which issued air quality permits on for
Compressor Station 116 and the Looper Bridge Road Meter
Station on March 11, 2015 and July 10, 2015, respectively.
58
79 Fed. Reg. 64186 (October 28, 2014).
40a
project. On November 14, 2014, the Commission
issued a Supplemental Notice of Intent to Prepare an
Environmental Assessment for the Planned Dalton
Expansion Project and Request for Comments on
Environmental Issues. This notice was also published
in the Federal Register59 and was mailed to over 1,100
interested parties and property owners affected by
the project facilities, notifying them that the scoping
period was extended through December 20, 2014.
60. As a result of concerns raised during the prefiling process by the Georgia Department of Natural
Resources (GADNR), the U.S. Fish and Wildlife
Service (FWS), and the Nature Conservancy, Transco
revised its planned route to avoid and minimize
potential environmental impacts on the biologically
sensitive Raccoon Creek Watershed. Accordingly, on
February 13, 2015, the Commission issued a second
Supplemental Notice of Intent to Prepare an Environmental Assessment for the Planned Dalton Expansion
Project and Request for Comments on Environmental
Issues. This notice was published in the Federal
Register60 and was mailed to over 1,270 interested
parties, including landowners that could be affected by
the route variation. Transco held a public open house
on February 24, 2015, in Dallas, Georgia to introduce
the project to landowners potentially affected by
the newly-developed route. Our environmental staff
held a fourth scoping meeting in Dallas, Georgia on
March 4, 2015, to receive verbal scoping comments
from stakeholders about the adjusted route. Eighteen
people spoke at the meeting. This newly-developed
route, referred to as the Raccoon Creek Alternative,
59
79 Fed. Reg. 69455 (Nov. 21, 2014).
60
80 Fed. Reg. 9710 (Feb. 24, 2015).
41a
was subsequently incorporated into the application for
the project on July 15, 2015.
61. In addition, as noted above, Bartow indicated
concern in its motion to intervene that the proposed
location of the Dalton Lateral would interfere with its
ability to expand two of its elementary schools on land
that it specifically acquired for that purpose. In a
response to those comments filed on October 21, 2015,
Transco stated it had incorporated Route Variation
AK as part of the Dalton Lateral – Segment 3, moving
the pipeline to a location slightly over 1000 feet from
the Taylorsville Elementary School, such that the route
no longer bisects the school property. The modified
route was reflected in Transco’s July 15, 2015 filing
and reviewed in the EA. Regarding the location of the
pipeline in the vicinity of the second school, Kingston
Elementary School, the pipeline follows an existing
overhead powerline, paralleling a corridor located
about 1,500 feet west of the school.
62. To satisfy the requirements of the National
Environmental Policy Act of 1969 (NEPA), our
staff prepared an environmental assessment (EA) for
Transco’s proposal. The analysis in the EA addresses
geology, soils, water resources, wetlands, vegetation,
fisheries, wildlife, threatened and endangered species,
land use, recreation, visual resources, cultural resources,
air quality, noise, safety, socioeconomics, cumulative
impacts, and alternatives. The EA addressed all substantive comments raised during the scoping period.
63. The EA was issued for a 30-day comment period
and placed into the public record on March 31, 2016.
The Commission received several comment letters
on the EA from individual stakeholders, the U.S.
Environmental Protection Agency (EPA), and the
Coosa River Basin Initiative (CRBI) regarding the
42a
impacts on the Etowah River, construction techniques,
potential impacts on water supply, effects of blasting,
cultural resources, cumulative effects, erosion and
production and end-user emissions.
1. April 2016 Modifications
64. On April 13, 2016, Transco filed 27 proposed
modifications to its project and on May 19 and 25,
2016, it filed additional information pertaining to
these modifications. Transco’s proposed modifications
would affect a total of 43 landowners, two of whom
were not previously affected by the project. Since
these proposals were made after the issuance of the
EA, while we will address them in this order, we will
consider them under the criteria established in
Environmental Condition 5. Environmental Condition
5 contemplates that there might be changes, such as
route realignments, facility relocations, new staging
areas, or access roads, identified after a project has
been certificated. Requests for such modifications
must include, among other information, documentation of affected-landowner approval and information
regarding potentially affected cultural resources,
endangered species, and environmentally sensitive
areas. As detailed below and consistent with the
criteria of Environmental Condition 5, we will only
grant approval for the modifications for which Transco
has both obtained landowner agreements and completed environmental surveys. For the remaining
proposed modifications, we will allow Transco to
present the required additional information and/or
justifications for the changes as required by Environmental Condition 5 of this order.
65. While Transco’s proposed modifications would
increase the pipeline length by 0.2 mile and total land
disturbance by 5.3 acres, the modifications would
43a
decrease the amount of forested wetlands impacted by
0.9 acre and eliminate four waterbody crossings.
Based on its May 19, 2016 filing, Transco has agreements with 25 of the 43 landowners impacted by the
modifications (covering 11 of the 27 modifications).
Transco continues to negotiate with the other 18
landowners. Transco has conducted environmental
surveys along 20 of the 27 proposed modifications. We
have reviewed the available survey reports for the
modifications and determined that the modifications
approved herein will not significantly increase impacts
on sensitive resources.
66. Transco proposed relocation of eight of its
mainline valves (MLV). Transco has completed environmental surveys and obtained landowner agreements
for the following six modifications: relocation of MLV
3 (from MP 34.5 to MP 34.3), MLV 6 (from MP 67.8 to
MP 64.2), and MLV 7 (from MP 77.9 to MP 78.2);
shifting MLV 8 at MP 85.3 (no change in MP), and
MLV 10 at MP 98.7 (no change in MP); and adding a
new MLV at MP 71.8. Having reviewed the submitted
information, we approve these modifications.
67. Transco has not completed environmental surveys
and has not obtained landowner agreements for the
property affected by the relocation of MLV 1 at MP
20.4 (no change in MP). Also, Transco has not obtained
landowner agreement for the relocation of MLV 9
(from MP 92.2 to MP 92.3). Accordingly, we will not
approve these modifications at this time.
68. Transco has completed environmental surveys
and obtained landowner agreements for two modifications along the Dalton Lateral: the addition of extra
workspace on the north and south sides of a railroad
crossing near MP 58.2 and a reroute of the Dalton
44a
Lateral between MPs 71.2 and 71.4 to avoid impacts
on Green Pond. We approve these modifications.
69. Transco has not completed environmental
surveys and/or obtained landowner agreement for the
following eight proposed modifications to the Dalton
Lateral: (1) a reroute between MPs 35.9 and 36.4 to
the west based on a landowner request; (2) shifting
the crossing of Highway 278 to the west between MPs
40.4 and 40.8 and the addition of two access roads;
(3) addition of a cathodic protection site at MP 51.0;
(4) reroute to the east between MPs 54.5 and 55.4 to
avoid crossing GADNR-owned lands and addition of a
new temporary access road; (5) reroute of an access
road near MP 56.5; (6) addition of extra workspace at
the Highway 278 crossing; (7) reroute and reduction of
the bore length at the Interstate 75 crossing between
MPs 76.6 and 77.9; and (8) reroute between MPs 95.7
and 96.9 to avoid multiple crossings of Polecat Creek.
We do not approve these modifications.
70. Transco also proposes to: (1) added a new access
road from the existing Compressor Station 115 to the
Dalton Lateral right-of-way; (2) relocate the Beasley
Road Meter Station (now called the Lucas Road Meter
Station) and add a new tap site and pipeline spur from
the Dalton Lateral at MP 53.2 to the new meter station
site; and (3) modify the portage path, which will be
used to move boats and kayaks around the construction area, on the southern side of the Etowah River.
Transco has not completed the environmental surveys
of the first of these modifications and has not obtained
landowner agreements for all the properties affected
by the second and third of these modifications.
Therefore, we do not approve these modifications.
71. Transco proposes five modifications that would
include locating workspace within streams. Because
45a
each of these changes will require modifications to
the project’s Wetland and Waterbody Construction
and Mitigation Procedures (Transco’s Procedures;
Appendix E of the EA), we will require additional
information to evaluate the feasibility of an alternative workspace layout or if additional protection
measures can be used to adequately protect the
streams. Accordingly, we do not approve these modifications at this time.
72. Finally, Transco proposes to reroute a portion of
the Dalton Lateral between MPs 30.3 and 30.4 to the
west to avoid impacts on a cemetery and to maintain
a 30-foot-wide no-disturbance buffer, as requested by
the Georgia State Historic Preservation Office. Transco
has neither completed the environmental surveys nor
obtained landowner agreements for all the properties
affected by this proposed reroute. Therefore, we will
not approve this modification. Further, the workspace
for this reroute would be located approximately 10 feet
from a house that was previously 400 feet from the
workspace. Additional information is needed for us to
evaluate Transco’s request and assess the feasibility of
an alternative route or crossing method to avoid
impacts on that residence.
73. To summarize, we approve incorporation of
eight of Transco’s requested modifications, as described
above, into the route authorized with this order. The
other 19 modifications are not approved. Transco may
present the required additional information and/or
justifications for these changes with its Implementation Plan and in accordance with Environmental
Condition 5 of this order. This condition requires
Transco to demonstrate compliance with Section 106
of the National Historic Preservation Act and Section
46a
7 of the Endangered Species Act prior to receiving
approval of any of the requested modifications.
2. Comments from the U.S. Environmental
Protection Agency
74. In its May 2, 2016 comment letter, the EPA
provided several recommendations and requested that
the Commission issue a supplemental EA to address
deficiencies identified in staff’s EA and to include
additional analysis addressing the 27 route modifications proposed after the EA was issued. In response,
we address the various comments from EPA in this
order and conclude that a supplemental EA for the
Dalton Expansion Project is not warranted.
75. First, the EPA recommends we address the
project’s potential to cause acid rock drainage during
construction. Acid-producing rocks are known to
occur in Georgia, and typically include graphitic
schist, phyllite, slate, coal, and carbonaceous shales,
which often contain pyrite. Counties that are crossed
by the Project in Georgia where these rocks are known
to occur include Paulding, Bartow, and Gordon. Acidproducing rocks are generally recognizable in the field
with an overall color of black or very-dark gray. Pyrite
has a gold metallic appearance.
76. In response to the EPA’s recommendation,
Transco agrees to evaluate the potential presence of
acid-producing rock or acidic soil along the project
route through review of U.S. Geologic Survey geologic
maps, U.S. Department of Agriculture – Natural
Resources Conservation Service Soil Surveys, and the
Soil Survey Geographic database, and to conduct field
47a
testing. Transco states that it will file with the
Commission, prior to construction, the results of its
desktop analysis identifying areas with the potential
for acid-producing rock or acidic soils, and a detailed
mitigation plan that outlines the procedures for field
verification and the mitigation measures that will be
implemented during construction.
61
77. Transco will also include a discussion on acidproducing rock and acidic soils in the environmental
training that will be required for environmental
inspectors before construction begins to familiarize the
environmental inspectors with the specific conditions
and issues associated with acid-producing rock and
acidic soils. We conclude that Transco’s proposed
measures are sufficient to address the EPA concerns.
78. The EPA also recommends that we address
karst areas of concern identified through desktop review
(topographic maps, aerial photographs, and LiDAR) in
Bartow and Murray Counties, Georgia. Transco has
conducted geophysical investigations at eight locations to gather additional information about these
features.62 Based on anomalies that were identified
during the geophysical investigations, soil borings
were performed at two locations to further define the
features and to determine if mitigation measures may
be needed during construction. The results of the soil
borings indicated that the conditions at the investigated locations should support the proposed pipeline
construction without karst mitigation measures. Three
61
See Transco’s Response to our November 13, 2015 Environmental Data Request, stating it will file the test borings before
commencing construction.
62
See Transco’s Report of Geophysical Services Karst Evaluation filed on August 13, 2015 in this proceeding.
48a
additional areas have been identified for soil borings
once access is available prior to construction in order
to determine if karst mitigation measures will be
required. The pipeline was re-routed away from three
of the eight locations where anomalies were identified;
therefore soil borings were not performed at those
locations. Environmental Condition 12 requires that
Transco file a revised Karst Mitigation Plan prior to
construction that includes the results of geotechnical
borings to determine the nature and extent of the
anomalies detected during the electric resistivity
imaging investigations as well as site-specific mitigation measures (e.g., route adjustment) for any karst
features identified. With this additional study, the
Commission’s review of the results, and Environmental Condition 12, we find the EPA’s concerns are
adequately addressed.
79. The EPA recommends that we address potential
scouring, erosion of river banks, and associated sediment discharges that could impact habitat for federally listed mussels where waterbodies are crossed via
dry-ditch and/or wet open crossings. On May 12, 2016,
the FWS filed with the Commission its biological
opinion (BO) on the project’s potential impacts on
aquatic species (see Threatened and Endangered
Species discussion below).63 The FWS states that
federally listed freshwater mussels are not known to
occur in the Oostanaula, Coosawattee, and Conasauga
River tributaries that the pipeline will cross, with the
exception of Holly Creek, where mussel populations
occur well upstream of the proposed crossing location.
The FWS also states that direct impacts on listed
63
See FWS’s Biological Opinion detailing potential impacts of
Transco’s proposed Dalton Expansion Project on aquatic species,
filed on May 12, 2016 in this proceeding.
49a
mussels are not anticipated but that erosion and
excessive sediment transport from these tributaries
due to pipeline construction and right-of-way could
impact listed mussels and their designated critical
habitat. However, the BO states that as proposed, the
project is not likely to jeopardize the continued existence of federally listed freshwater mussels identified
as potentially occurring in the project area and is not
likely to destroy or adversely modify critical habitat.
Based on analysis in the EA and the findings of the
FWS’ BO, we conclude that additional scour analysis
as recommended by the EPA is not warranted.
80. The EPA requests that we assess the cumulative effects of collocating pipeline rights-of-way with
existing rights-of-way, and that we evaluate the impacts
on sensitive ecosystems crossed by the proposed route.
As discussed in section B.3.c of the EA, although the
project may contribute to forest fragmentation, collocation and construction in previously disturbed areas
will minimize the effects of forest fragmentation and
forest edge effect caused by construction of the pipeline.64 In addition, Transco has deviated from existing
rights-of-way in areas where expanding the existing
right-of-way would affect sensitive habitats (e.g.,
portions of the Raccoon Creek watershed, Green Pond,
and Drummond Swamp). Further, as noted in the EA,
the presence of similar habitat types within the vicinity
of the project area will help ensure that the project
does not result in population-level or significant
64
EA at 54, see also EA at 52-53 (noting that much of the
woodland in the project area has already been fragmented
by agricultural land, managed timber operations, and other
developments).
50a
measurable negative impacts on birds of conservation
concern or other migratory birds.65
81. The EPA identifies concerns related to the
transfer of hydrostatic test water between watersheds
and expresses concerns about water withdrawals. The
EPA asserts that the associated aquatic ecosystems
should be assessed, particularly for drought conditions, the hydrostatic-testing frequency needed for
operations/maintenance, and impacts on federally
listed mussel species.
82. Transco states in its May 17, 2016 response
that surface water used for project construction and
operations will be removed from and returned to the
same watershed (8-digit hydrologic unit code) and that
no hydrostatic testing will be performed during
operations/maintenance.66 As stated in section B.2.b of
the EA, Transco will be required to obtain authorization from the GADNR prior to any water withdrawals
and to comply with all conditions set by the GADNR.67
Further, Transco will implement the measures outlined
in its Procedures (subject to Commission review and
modification as necessary) to minimize impacts on
waterbodies during withdrawals including maintaining adequate flow rates to protect aquatic life, provide
for all waterbody uses, and provide for downstream
withdrawals of water by existing users.68 We conclude
that Transco’s measures address the concerns expressed
by the EPA.
65
EA at 54-55.
66
Transco’s May 17, 2016 Response to the EPA’s Comments on
the EA.
67
EA at 40.
68
Id.; see also Environmental Condition 14.
51a
83. The EPA recommends that the EA address the
depth of the pipeline to mitigate the potential effects
of severe flooding events such as a 500-year flood that
could compromise the pipeline due to flood-water
scouring of the stream bottom, and cites as an example
the weakening and rupture of the Enterprise Product
Pipeline that was buried to a depth of 20 feet beneath
the Missouri River bed.
84. The Missouri River is the longest river in the
United States and has a drainage area of more than
half a million square miles. There is no waterbody
crossed by the project that is comparable. Moreover,
most of the larger waterbodies crossed by the project
will be crossed using the horizontal direction drill (HDD)
method, resulting in the pipeline being installed more
than 30 feet below the streambed. Additionally, the
pipeline will be constructed in accordance with Transco’s
Procedures and be subject to post-construction monitoring to identify areas of exposure as discussed in
section A.7.e and Appendix E of the EA.
85. The EPA identifies concerns related to the crossing of three major waterbodies: an unnamed tributary
to Jones Branch, an unnamed tributary to Crane
Eater Creek, and Pole Cat Creek. Transco states in its
May 17, 2016 response that the unnamed tributary to
Jones Branch is a man-made intermittent pond that
will be crossed using dry crossing methods. The unnamed
tributary to Crane Eater Creek is an agricultural stock
pond that will be drained under permission of the
owner. Finally, the referenced crossing of Pole Cat
Creek is no longer part of the proposed project. As
outlined in its Procedures, Transco will file detailed,
site-specific construction plans and scaled drawings
identifying all areas to be disturbed by construction for
each major waterbody crossing for the review and
52a
written approval (and additional mitigation measures
if warranted) by the Director of the Office of Energy
Projects prior to construction.
86. The EPA questions the number of streams
described in the EA. To clarify, the EA states that the
project will cross 55 coldwater fishery streams; 41 of
which will be crossed using a dry crossing method and
one will be crossed using the HDD method. The
remaining coldwater fisheries streams are within the
proposed construction workspace but will not be
crossed by the pipeline. Based on Transco’s April 2016
Supplemental Filing, two additional coldwater fisheries streams will be crossed. Therefore, the current
project, as modified, will cross 57 coldwater fisheries,
43 of which will be crossed using a dry crossing
method, one will be crossed using the HDD method,
and 13 that are within the proposed construction
workspace but will not be crossed by the pipeline.
87. The EPA identifies concerns related to the
crossing of a conservation easement associated with
Snake Creek. This conservation easement was avoided
by a route variation that was adopted in July 2015 and
was considered in the EA.
88. The EPA identifies concerns related to the
future conversion of the proposed pipeline from
natural gas transportation to the transportation of
natural gas liquids or petroleum products. Transco
states that it does not have any plans to abandon or
convert the pipeline to natural gas liquids or
petroleum products. Prior to any abandonment of the
pipeline, Transco would be required to obtain an
approval from the Commission under section 7(b) of
the NGA.
53a
89. The EPA identifies concerns related to the
storage of tert‐butyl mercaptan, the odorant used to
assist in the detection of pipeline leaks. Transco
indicates that odorization facilities are not proposed
for any component of the project. The supplemental
odorization control proposed by Transco will analyze
the gas composition and mercaptan levels in the gas
stream and signal the existing odorization stations to
inject less mercaptan or to supplement up to the
established level. The net effect will be the same
amount of mercaptan by volume in the delivered gas
stream to the customer. Transco anticipates that the
usage of the existing odorization facilities will be
reduced.69
90. The EPA recommends that the Commission
provide an estimate of both the production emissions,
including production-related fugitive emissions, and
end-user GHG emissions associated with the proposed
action in a supplemental NEPA document. As identified by Transco, gas transported by the project will be
delivered to the Oglethorpe Power – Chattahoochee
Energy Facility and to Atlanta Gas Light. We have
determined that there is no pending construction
or air quality permit application pending for the
Oglethorpe Power – Chattahoochee Energy Facility.
The project would deliver approximately 208 million
cubic feet per day to the facility, which may be used for
either future expansion or to displace current natural
gas supply. Should the gas be used for expansion,
there would be an increase in greenhouse gas emissions (GHGs) as well as criteria pollutants. If the
natural gas is displacing an existing gas supply, there
would be no change in emissions. If the gas is used to
69
Transco’s May 17, 2016 Response to the EPA’s Comments on
the EA.
54a
displace another fuel, such as oil or coal, then GHGs
would most likely be reduced. Regardless, changes in
the air permit would require approval by the Georgia
Department of Environmental Protection.
91. The remaining 240 million cubic feet per day
would be delivered to the Atlanta Gas Light, a local
distribution company (LDC). The LDC could distribute
the gas to residential, commercial, or industrial customers. Each of these end use scenarios result in very
different lifecyle GHG or criteria pollutant emissions.
We do not believe the potential increase of emissions
associated with the production and combustion of
natural gas is causally related to our action in approving this project, nor are the potential environmental
effects reasonably foreseeable as contemplated by the
Council on Environmental Quality’s (CEQ) regulations. Moreover, as the Commission has previously
stated, there is no standard method for determining
fugitive methane emissions for pipelines and the level
of fugitive methane releases during the lifecycle of
natural gas are highly debated. Therefore, it is difficult
to accurately quantify fugitive emissions of methane.70
Further, the EA explains that there is no standard
methodology to determine how a project’s incremental
contribution to GHG emissions would result in physical effects on the environment, either locally or
globally.71 We concur.72 Even if we determined that a
lifecycle GHG analysis was warranted, uncertainties
regarding both the LDC end uses, as well as numerous
70
See Transcontinental Gas Pipe Line Co. LLC, 149 FERC ¶
61,258, at P 109 (2014).
71
72
EA at 122.
See, e.g., Sabine Pass Liquefaction Expansion, LLC, 151
FERC ¶ 61,012 at P 97, reh’g denied, 151 FERC ¶ 61,253 (2015).
55a
production/upstream variables (gas source, pipeline
lengths, processing facilities, etc.) would make the
analysis too speculative to permit any meaningful consideration. In addition, given that potential production
areas are far removed from the geographic scope of the
project, identifying emissions of criteria pollutants
from production/upstream is even more speculative.
Speculative estimates of the end use and production/
upstream GHG emissions would not meaningfully
inform the Commission’s decision. There are no
thresholds for significance, nor is there a meaningful
method to determine the local or regional incremental
impacts on ongoing climate change.
92. The EPA expressed concerns about impacts on
carbon sequestration. Currently there are no federal
or state regulations regarding carbon sequestration.
According to the EPA, carbon sequestration is the
process through which plant life removes carbon
dioxide from the atmosphere and stores it in biomass.
The project will affect approximately 796 acres of
forested land, with 400 acres allowed to revert to forest
over time. While there will be a long-term effect of
reduced carbon sequestration due to removal of trees
from the permanent right-of-way, areas of temporary
disturbance will be allowed to revert to pre-existing
conditions. The young vegetation of the restored temporary right-of-way will continue to perform the
carbon sequestration process. The carbon sequestration ability of the permanent right-of-way will be
reduced; however, we conclude that the project will not
significantly impact cumulative carbon sequestration
in the United States. We also do not believe that the
potential reduction of greenhouse gas sinks will
significantly exacerbate ongoing climate change.
56a
3. Etowah River Crossing
93. The Commission received multiple comments
regarding the proposed Etowah River Crossing, including comments from the EPA, the Coosa River Basin
Initiative (CRBI), Darrel Cagle, and Troy Harris.
94. The EPA recommends that the EA evaluate
blasting impacts on karst terrain, specifically the
effects of blasting through karst during the crossing of
the Etowah River, and recommends that we address
sensitive ecosystem impacts.
95. The only waterbody for which blasting is currently proposed is the Etowah River. As discussed in
section B.2.b of the EA, Transco conducted a geotechnical investigation of the Etowah River crossing.
Given the degree of karst found during Transco’s
geophysical investigation, trenching for an open-cut
crossing of the Etowah River will be through karst
bedrock, which is likely to be conducive to techniques
such as rock sawing and hammering. If conditions
encountered are as expected, then blasting will not be
necessary. However, if blasting becomes necessary,
Transco will follow the pre-blasting monitoring requirements and post-blasting mitigation measures
contained in its project blasting plan, which includes
the development of site-specific mitigation measures.
Moreover, Environmental Condition 12 requires that
Transco file – for review and approval by the Commission – a revised Karst Mitigation Plan prior to
construction that will include site-specific mitigation
measures for any karst features identified.
96. The EPA requests information regarding compensatory mitigation related to the Etowah River
crossing. Compensatory mitigation will be addressed
by the U.S. Army Corps of Engineers (COE) during
57a
the COE permitting process for the Etowah River
crossing.73
97. The CRBI questions whether the EA fully
evaluated alternative crossing methods and requests
that the Commission independently review the feasibility of an HDD crossing of the river. Additionally,
the EPA commented that the EA did not include a
detailed analysis of the impacts associated with the
proposed crossing and requests that turbidity modeling be used to determine impacts. Furthermore, the
CRBI and Troy Harris question the reliability of the
borings collected within the river and request the
results of electric resistivity imaging testing near the
river. Lastly, the CRBI, EPA, Darrel Cagle, and Troy
Harris express concern regarding blasting and trenching and the resulting turbidity impacts. Troy Harris
questions the efficacy of turbidity curtains used during
construction, impacts associated with the installation
of the curtains, and potential downstream impacts
including stream bank erosion and sedimentation
affecting a sensitive cultural resource site identified as
the Indian Fish Weir.
98. As discussed in the EA, the information provided in Transco’s application and supplemental
filings is adequate to support the conclusion that the
use of the HDD crossing method is not appropriate at
this location. Environmental Condition 13 requires
that Transco provide, prior to construction, quantitative modeling results of turbidity and sedimentation,
including the duration, extent, and magnitude of
elevated turbidity levels and sedimentation due to
trenching, backfilling, and blasting (should it be
73
See Transco’s May 17, 2016 Response to the EPA’s Comments on the EA.
58a
required). The condition also requires Transco to file
its final Etowah River Turbidity Control and Monitoring
Plan, which was developed in coordination with the
GADNR and was provided to the FWS and COE for
review. The analysis already included in the EA, as
supplemented by the environmental conditions, is
sufficient to assess the impacts.
99. The CRBI questions the appropriateness of the
use of COE Nationwide Permit 12. The COE will make
the final determination on which type of permit the
project requires.
100. The CRBI requests that the Commission consider an alternative crossing location of the Etowah
River that will avoid a wet trench crossing. As
indicated in the EA, based on available U.S. Geological
Survey data and the results of the field investigations,
similar geologic conditions are expected within reasonable proximity to the proposed Etowah River crossing
location.74 Consequently, the alternative route identified by the CRBI would likely encounter similar
geology as the proposed location, which would preclude the use of an HDD crossing method. In addition,
the CRBI’s alternative route is approximately 3 miles
longer than the proposed route, which would result in
additional terrestrial impacts.
101. The CRBI comments that the EA did not
consider impacts on recreational use of the Etowah
River. Impacts on recreational use of the Etowah River
are addressed in section B.5.a of the EA. Transco’s
Draft Aid to Navigation Plan includes a plan identify74
See EA at 24. Environmental Condition 12 requires that,
before commencing construction, Transco must file a revised
Karst Mitigation Plan that includes site-specific mitigation
measures for any karst features identified.
59a
ing portage locations to be used by recreational users
during construction and a detailed signage plan to
inform recreational users of access limitations and
portage locations.
4. Alternatives
102. The Commission received several comments on
the EA regarding alternatives to the proposed pipeline
route, including comments from 1460 Partnership;
Evans & Rhodes, LLC; and the First Baptist Church
of Atlanta. The 1460 Partnership, LLLP provided a
map identifying three specific alternatives that
avoided their property. Evans & Rhodes, LLC did not
identify a specific alternative route but referenced an
alternative route on an adjacent undeveloped property. Based on our review of available information, we
determined that these alternatives are similar in
length or longer and would cross the same sensitive
resources (e.g., forest land) as the corresponding
segment of the proposed route without conferring an
obvious environmental advantage over the proposed
route. Further, these alternatives would require moving the route onto other landowners. For these reasons,
we are not authorizing these alternative routes.
103. The First Baptist Church of Atlanta identified
an alternative that would follow the church property
line, which is located adjacent to an existing powerline
right-of-way. Based on a preliminary review of the
alternative route, it appears to be feasible and remains
on the church property. We agree in this case that colocating along the power line right-of-way at the edge
of the property is preferable to bisecting the property.
Therefore, Environmental Condition 24 requires Transco
to either modify the pipeline route as requested by the
First Baptist Church of Atlanta, provide additional
justification why the alternative route cannot be incor-
60a
porated, or document landowner concurrence with the
currently proposed route.
104. David Shumaker identifies an alternative
route that would follow the existing access road to
Compressor Station 115 then head east along the
northern edge of Mr. Shumaker’s property where it
would connect with the proposed pipeline route. Based
on a preliminary review of the alternative route, it
appears to be feasible without impacting additional
landowners. Environmental Condition 24 requires
Transco to either modify the pipeline route as discussed above, provide additional justification why the
alternative route cannot be incorporated, or document
landowner concurrence with the currently proposed
route.
5. Threatened and Endangered Species
105. The Commission received several comments
on the EA regarding federally and state-listed species,
including comments from the EPA and 1460 Partnership. Section B.4. of the EA determines that constructing and operating the project will result in no effect on
13 threatened and endangered species; may affect, but
is not likely to adversely affect five threatened and
endangered species; and will not contribute to the
listing of one candidate species.
106. On April 5, 2016, the FWS filed a letter with
the Commission stating that it did not concur with
some of our staff’s determinations, based largely on
the possibility of erosion and sedimentation within
affected watersheds. However, the EA does include
measures to avoid and minimize potential erosion,
turbidity, and sedimentation impacts, as well as effects
attributable to hydrostatic test water withdrawals.
Based on our past experience with natural gas pipeline
61a
construction, the EA concludes that these measures
provide adequate protection for all resources that are
directly affected and substantially limits the potential
for any indirect impacts. However, in deference to the
opinions of the FWS, we adopted the FWS determinations in a letter to the FWS dated April 28, 2016. On
May 2, 2016, the FWS concurred with our revised
determinations. With receipt of the FWS concurrence,
and the subsequent BO addressing terrestrial species
dated May 9, 2016, the Endangered Species Act
Consultation process is complete and, as a result, EA
recommendation no. 19 is not included as a condition
of this order.
107. In a letter filed on April 28, 2016, Troy Harris
identifies concerns about the project’s potential impacts on an active bald eagle nest along the Etowah
River at Hardin Bridge. Because the closest construction areas are about 1.5 miles from the nest, construction
or operation of the project is not likely to affect it.75
108. Concerns regarding state-listed species are
adequately addressed in section B.4.b of the EA, which
concludes that the project is expected to have no
impact on 54 of the 58 state-listed species that are not
also federally listed and will have temporary and
minor impacts on four species.
6. Water Resources
109. On May 2, 2016, the CRBI filed a letter
identifying several Clean Water Act section 303(d)listed impaired waterbodies crossed by the proposed
pipeline route that were not specifically discussed in
75
As indicated on page 54 of the EA, Table B.3c-2, our environmental staff completed consultation with the FWS for the bald
eagle as part of the Birds of Conservation Concern, which is a
subset of the Migratory Bird Treaty Act.
62a
the EA. Based on Transco’s proposed construction
techniques and the implementation of minimization
and mitigation measures as outlined in section B.2.b
and Appendix E of the EA, we do not anticipate any
impact on the impairment criteria for these waterbodies during construction or operation of the project.
7. Land Use
110. Evans & Rhodes, LLC questions the use of
Wahoo Overlook Trail as an access road, noting such
use could block access to residents along the road.
Transco states that it no longer proposes to use this
road.76 If Transco proposes to use this road, it must file
a written request for our environmental staff’s review
and approval.
8. Environmental Conclusions
111. Based on the analysis in the EA, as supplemented herein, we conclude that if constructed in
accordance with Transco’s application and supplement(s),
and in compliance with the environmental conditions
in the appendix to this order, our approval of this
proposal would not constitute a major federal action
significantly affecting the quality of the human
environment.
112. Any state or local permits issued with respect
to the jurisdictional facilities authorized herein must
be consistent with the conditions of this certificate. We
encourage cooperation between interstate pipelines
and local authorities. However, this does not mean
that state and local agencies, through application of
state or local laws, may prohibit or unreasonably delay
76
EA Environmental Condition 4.
63a
the construction or operation of facilities approved by
this Commission.77
IV. Conclusion
113. The Commission on its own motion received
and made a part of the record in this proceeding all
evidence, including the application, and exhibits
thereto, and all comments and upon consideration of
the record,
The Commission orders:
(A) A certificate of public convenience and necessity
is issued to Transco authorizing it to construct and
operate the Dalton Expansion Project, as described
and conditioned herein, and as more fully described in
the application.
(B) The certificate authority granted in Ordering
Paragraph (A) is conditioned on Transco’s:
(1) completion of construction of the proposed
facilities and making them available for service
within two years of the issuance of this order
pursuant to section 157.20(b) of the Commission’s
regulations;
(2) compliance with all applicable Commission
regulations under the NGA including, but not
77
See 15 U.S.C. § 717r(d) (state or federal agency’s failure to
act on a permit considered to be inconsistent with Federal law);
see also Schneidewind v. ANR Pipeline Co., 485 U.S. 293, 310
(1988) (state regulation that interferes with FERC’s regulatory
authority over the transportation of natural gas is preempted)
and Dominion Transmission, Inc. v. Summers, 723 F.3d 238,
245 (D.C. Cir. 2013) (noting that state and local regulation is
preempted by the NGA to the extent it conflicts with federal
regulation, or would delay the construction and operation of
facilities approved by the Commission).
64a
limited to Parts 154, 157, and 284, and paragraphs
(a), (c), (e), and (f) of section 157.20 of the
Commission’s regulations;
(3) compliance with the environmental conditions
in Appendix C to this order; and
(4) execution, prior to commencement of construction, of a firm contracts for the volumes and service
terms equivalent to those in its precedent agreement.
(C) A certificate of public convenience and necessity
is issued under section 7(c) of the NGA authorizing
Transco to lease capacity from Dogwood, as described
herein and in the application.
(D) Transco’s initial incremental reservation charge
under Rate Schedule FT as recalculated for the project
to reflect the removal of variable costs is approved, as
discussed above.
(E) Transco shall file actual tariff records with the
recalculated base reservation charge no earlier than
60 days and no later than 30 days, prior to the date the
project goes into service.
(F) As described in this order, not less than 30 days
and not more than 60 days prior to the commencement
of service using the authorized expansion capacity,
Transco must file an executed copy of any nonconforming service agreement associated with the
project as part of its tariff, disclosing and reflecting all
non-conforming language, and a tariff record identifying each such agreement as a non-conforming agreement
consistent with section 154.112 of the Commission’s
regulations.
(G) As described in the body of this order, Transco
must file any negotiated rate agreement or tariff record
setting forth the essential terms of the agreement
65a
associated with the project at least 30 days, but not
more than 60 days before the proposed effective date
of such rates.
(H) Transco shall keep separate books and accounting of costs attributable to the incremental services
using the expansion capacity created by the project, as
discussed herein.
(I) Transco shall notify the Commission’s environmental staff by telephone, e-mail, and/or facsimile of
any environmental noncompliance identified by other
federal, state or local agencies on the same day that
such agency notifies Transco. Transco shall file written
confirmation of such notification with the Secretary of
the Commission (Secretary) within 24 hours.
(J) The State Commissions’ protest and request for
partial consolidation and evidentiary hearing is denied.
(K) The late motions to intervene are granted.
By the Commission.
(SEAL)
Nathaniel J. Davis, Sr.,
Deputy Secretary.
66a
Appendix A
Timely Motions to Intervene
Alabama Gas Corporation
Atlanta Gas Light Company
Atmos Energy Marketing, LLC
Bartow County School System and
Bartow County Board of Education
City of Cartersville, Georgia
Conoco Phillips Company
Consolidated Edison Company of New York, Inc.
and Philadelphia Gas Works
Duke Energy Carolinas, LLC
Municipal Gas Authority of Georgia78 and
Transco Municipal Group79
78
The Gas Authority consists, inter alia, of the following
municipalities which are served directly by Transco: the Georgia
municipalities of Bowman, Buford, Commerce, Covington, Elberton,
Hartwell, Lawrenceville, Madison, Monroe, Royston, Social
Circle, Sugar Hill, Toccoa, Winder, and Tri-County Natural Gas
Company (consisting of Crawfordville, Greensboro and Union
Point); the East Central Alabama Gas District, Alabama; the
towns of Wadley and Rockford, Alabama; the Utilities Board of
the City of Roanoke, Alabama; Wedowee Water, Sewer & Gas
Board, Wedowee, Alabama; and the Maplesville Waterworks and
Gas Board, Maplesville, Alabama.
79
The members of TMG include the Cities of Alexander City
and Sylacauga, Alabama; the Commissions of Public Works of
Greenwood, Greer, and Laurens, South Carolina; the Cities of
Fountain Inn and Union, South Carolina; the Patriots Energy
Group (consisting of the Natural Gas Authorities of Chester,
Lancaster and York Counties, South Carolina); and the cities of
67a
National Grid Gas Delivery Companies
New Jersey Natural Gas Company
NJR Energy Services Company
North Carolina Utilities Commission and New York
State Public Service
Commission
Oglethorpe Power Corporation
Piedmont Natural Gas Company, Inc.
PSEG Energy Resources & Trade LLC
SCE & GPSC of North Carolina
UGI Distribution Company
Bessemer City, Greenville, Kings Mountain, Lexington, Monroe,
Rocky Mount, Shelby, and Wilson, North Carolina.
68a
Appendix B
Late Motions to Intervene
1460 Partnership, LLLP
Coosa River Basin Initiative
David L. Shumaker
Handy Land and Timber, LLC
Ivan Goldenberg and Christine Cali Snellgrove Glenn
Paul Corley
Scott & Judy Mullis, Donna Gordon, Aimee and Phillip
Hutzelman, Kathleen and Michael Rossi, Darlos and
William Biossat, and Cynthia Schiller Jackson
Southern Company Services, Inc.
Virginia Corley Casey, Douglas Van Corley, Edward
Daniel Corley, Wanda Corley Haight, and Mary Corley
White
69a
Appendix C
Environmental Conditions
As recommended in the environmental assessment
(EA) this authorization includes the following
conditions:
1. Transcontinental Gas Pipe Line Company, LLC
(Transco) shall follow the construction procedures and
mitigation measures described in its application,
supplemental filings (including responses to staff data
requests), and as identified in the EA, unless modified
by the Order. Transco must:
a. request any modification to these procedures,
measures, or conditions in a filing with the Secretary
of the Commission (Secretary);
b. justify each modification relative to sitespecific conditions;
c. explain how that modification provides an
equal or greater level of environmental protection
than the original measure; and
d. receive approval in writing from the Director of
the Office of Energy Projects (Director of OEP)
before using that modification.
2. The Director of OEP has delegated authority to
take whatever steps are necessary to ensure the
protection of all environmental resources during construction and operation of the project. This authority
shall allow:
a. the modification of conditions of the Order; and
b. the design and implementation of any additional measures deemed necessary (including stopwork authority) to ensure continued compliance
with the intent of the environmental conditions as
70a
well as the avoidance or mitigation of adverse
environmental impact resulting from construction
and operation of the project.
3. Prior to any construction of the facilities, Transco
shall file an affirmative statement with the Secretary,
certified by a senior company official, that all company
personnel, environmental inspectors (EIs), and contractor personnel will be informed of the EIs’ authority
and have been or will be trained on the implementation
of the environmental mitigation measures appropriate
to their jobs before becoming involved with construction and restoration activities for the project.
4. The authorized facility locations shall be as
shown in the EA, as supplemented by filed alignment
sheets. As soon as they are available and before the
start of construction, Transco shall file with the Secretary
any revised detailed survey alignment maps/sheets for
the project at a scale not smaller than 1:6,000 with
station positions for all facilities approved by the
Order. All requests for modifications of environmental
conditions of the Order or site-specific clearances must
be written and must reference locations designated on
these alignment maps/sheets.
Transco’s exercise of eminent domain authority
granted under NGA section 7(h) in any condemnation
proceedings related to the Order must be consistent
with these authorized facilities and locations. Transco’s
right of eminent domain granted under NGA section
7(h) does not authorize it to increase the size of its
natural gas facilities to accommodate future needs or
to acquire a right-of-way for a pipeline to transport a
commodity other than natural gas.
5. Transco shall file with the Secretary detailed
alignment maps/sheets and aerial photographs at a
71a
scale not smaller than 1:6,000 identifying all route
realignments or facility relocations, and staging areas,
pipe storage and ware yards, new access roads, and
other areas for the project that would be used or
disturbed and have not been previously identified in
filings with the Secretary. Approval for each of these
areas must be explicitly requested in writing. For each
area, the request must include a description of the
existing land use/cover type, documentation of landowner approval, whether any cultural resources or
federally listed threatened or endangered species would
be affected, and whether any other environmentally
sensitive areas are within or abutting the area. All
areas shall be clearly identified on the maps/sheets/
aerial photographs. Each area must be approved in
writing by the Director of OEP before construction in
or near that area.
This requirement does not apply to extra workspace
allowed by Transco’s Plan and/or minor field realignments per landowner needs and requirements that do
not affect other landowners or sensitive environmental
areas such as wetlands.
Examples of alterations requiring approval include
all route realignments and facility location changes
resulting from:
(i) implementation of cultural resources mitigation measures;
(ii) implementation of endangered, threatened, or
special concern species mitigation measures;
(iii) recommendations by state regulatory authorities; and
72a
(iv) agreements with individual landowners that
affect other landowners or could affect sensitive
environmental areas.
6. Within 60 days of the acceptance of the
Certificate and before construction begins, Transco
shall file an Implementation Plan for the project for
review and written approval by the Director of OEP.
Transco must file revisions to the plan as schedules
change. The plan shall identify:
a. how Transco will implement the construction
procedures and mitigation measures described in its
application and supplements (including responses to
staff data requests), identified in the EA, and
required by the Order;
b. how Transco will incorporate these requirements into the contract bid documents, construction
contracts (especially penalty clauses and specifications), and construction drawings so that the
mitigation required at each site is clear to on-site
construction and inspection personnel;
c. the number of EIs assigned per spread, and
how Transco will ensure that sufficient personnel
are available to implement the environmental
mitigation;
d. company personnel, including EIs and contractors, who will receive copies of the appropriate
material;
e. the location and dates of the environmental
compliance training and instructions Transco will
give to all personnel involved with construction and
restoration (initial and refresher training as the
project progresses and personnel changes), with the
73a
opportunity for OEP staff to participate in the
training session;
f. the company personnel (if known) and specific
portion of Transco’s organization having responsibility for compliance;
g. the procedures (including use of contract penalties) Transco will follow if noncompliance occurs;
and
h. for each discrete facility, a Gantt chart (or
similar project scheduling diagram), and dates for:
i. the completion of all required surveys and
reports;
ii. the environmental compliance training of
on-site personnel;
iii. the start of construction; and
iv. the start and completion of restoration.
7. Transco shall employ one or more EIs per
construction spread. The EIs shall be:
a. responsible for monitoring and ensuring compliance with all mitigation measures required by the
Order and other grants, permits, certificates, or
other authorizing documents;
b. responsible for evaluating the construction
contractor’s implementation of the environmental
mitigation measures required in the contract (see
condition 6 above) and any other authorizing
document;
c. empowered to order correction of acts that
violate the environmental conditions of the Order,
and any other authorizing document;
74a
d. a full-time position, separate from all other
activity inspectors;
e. responsible for documenting compliance with
the environmental conditions of the Order, as well
as any environmental conditions/permit requirements imposed by other federal, state, or local
agencies; and
f. responsible for maintaining status reports.
8. Beginning with the filing of its Implementation
Plan, Transco shall file updated status reports on a
weekly basis for the project until all construction and
restoration activities are complete. On request, these
status reports will also be provided to other federal
and state agencies with permitting responsibilities.
Status reports shall include:
a. an update of Transco’s efforts to obtain the
necessary federal authorizations;
b. the current construction status of each spread
of the project, work planned for the following
reporting period, and any schedule changes for
stream crossings or work in other environmentally
sensitive areas;
c. a listing of all problems encountered and each
instance of noncompliance observed by the EI(s)
during the reporting period (both for the conditions
imposed by the Commission and any environmental
conditions/permit requirements imposed by other
federal, state, or local agencies);
d. a description of the corrective actions implemented in response to all instances of noncompliance,
and their cost;
e. the effectiveness of all corrective actions
implemented;
75a
f. a description of any landowner/resident complaints that may relate to compliance with the
requirements of the Order, and the measures taken
to satisfy their concerns; and
g. copies of any correspondence received by
Transco from other federal, state, or local permitting
agencies concerning instances of noncompliance,
and Transco’s response.
9. Prior to receiving written authorization from the
Director of OEP to commence construction of any
project facilities, Transco shall file with the Secretary
documentation that it has received all applicable
authorizations required under federal law (or evidence
of waiver thereof).
10. Transco must receive written authorization
from the Director of OEP before commencing service
on each discrete facility of the project. Such authorization will only be granted following a determination
that rehabilitation and restoration of the right-of-way
and other areas affected by the project are proceeding
satisfactorily.
11. Within 30 days of placing the authorized
facilities for the project into service, Transco shall file
an affirmative statement, certified by a senior
company official:
a. that the facilities have been constructed in
compliance with all applicable conditions, and that
continuing activities will be consistent with all
applicable conditions; or
b. identifying which of the Certificate conditions
Transco has complied with or will comply with. This
statement shall also identify any areas affected by
the project where compliance measures were not
76a
properly implemented, if not previously identified in
filed status reports, and the reason for noncompliance.
12. Prior to construction, Transco shall file with the
Secretary, for review and approval by the Director of
the OEP, a revised Karst Mitigation Plan that
includes a comprehensive karst report providing a
complete discussion of the desktop reviews and field
surveys that were conducted to identify potential karst
features along the route. The report shall:
a. provide the results of geotechnical borings to
determine the nature and extent of the anomalies
detected during the electric resistivity imaging
investigations;
b. provide site-specific mitigation measures for
any karst features identified (e.g., route adjustment); and
c. provide an analysis to determine the pipeline’s
intrinsic ability to span subsidence features and
provide documentation showing where these data
can be found.
13. Prior to any construction within the Etowah
River, Transco shall file with the Secretary, for review
and approval by the Director of OEP, quantitative
modeling results of the turbidity and sedimentation
associated with construction across the Etowah River.
The modeling shall consider blasting activities; trench
excavation and backfilling; and the installation and
removal of the riprap, equipment bridges, and
turbidity curtains. The results of the analysis shall
illustrate the duration, extent, and magnitude of
elevated turbidity levels and sedimentation. In
addition, Transco shall provide its final Etowah River
Turbidity Control and Monitoring Plan.
77a
14. Prior to construction, Transco shall file with the
Secretary, for review and written approval by the
Director OEP, an updated version of its Procedures
that complies entirely with section IV.A.1.d of the
FERC Procedures.
15. Prior to construction, Transco shall file with the
Secretary further site-specific justification for or
modify its proposed workspaces related to waterbodies
noted as “without sufficient justification” in Appendix
L of the EA and file updated alignment sheets, as
appropriate, for review and written approval by the
Director of OEP.
16. Prior to construction, Transco shall file with the
Secretary further site-specific justification for or
modify its proposed workspaces related to wetlands
noted as “without sufficient justification” in Appendix
L of the EA and file updated alignment sheets, as
appropriate, for review and written approval by the
Director of OEP.
17. Prior to construction, Transco shall file with the
Secretary a copy of its final wetland mitigation plan
and documentation of COE approval of the plan.
18. Prior to construction, Transco shall file with the
Secretary a plan describing the feasibility of incorporating plant seeds that support pollinators into
the seed mixes used for restoration of construction
workspaces. These plans shall also describe Transco’s
consultations with the relevant federal and/or state
agencies.
19. Transco shall not begin implementation of any
treatment plans/measures (including archaeological
data recovery); construction of facilities; or use staging
storage, or temporary work areas and new or to-beimproved access roads until:
78a
a. Transco files with the Secretary:
i. all cultural resources survey reports, including special studies such as ground penetrating
radar, evaluation reports, avoidance plans and
treatment plans;
ii. comments on survey reports, special studies,
evaluation reports, avoidance plans and treatment plans from the State Historic Preservation
Office, as well as any comments from federally
recognized Indian tribes;
iii. the Advisory Council on Historic Preservation is afforded an opportunity to comment on the
undertaking if historic properties would be
adversely affected; and
b. the FERC staff reviews and the Director of
OEP approves all cultural resources reports and
plans, and notifies Transco in writing that treatment plans/mitigation measures may be implemented
and/or construction may proceed.
All material filed with the Commission that contains location, character, and ownership information
about cultural resources must have the cover and any
relevant pages therein clearly labeled in bold lettering
“CONTAINS PRIVILEGED INFORMATION – DO
NOT RELEASE.”
20. If changes to the project construction schedule
occur that would materially impact the amount of NOX
emissions generated in a calendar year, Transco shall
file, in its weekly status report, revised construction
emissions estimates prior to implementing the schedule modification with the Secretary demonstrating
that the annual NOX emissions resulting from the
79a
revised construction schedule do not exceed general
conformity applicability thresholds.
21. Prior to construction of the I-20, Highway 120,
and Joe Frank Harris Parkway locations, Transco
shall file with the Secretary, for review and written
approval by the Director of OEP, an horizontal
directional drill noise mitigation plan to reduce the
projected noise level attributable to the proposed
drilling operations at noise-sensitive areas (NSAs)
with predicted noise levels above 55 decibels on the
A-weighted frequency scale (dBA). During drilling
operations, Transco shall implement the approved
plan, monitor noise levels, and make all reasonable
efforts to restrict the noise attributable to the drilling
operations to no more than an day-night averaged
sound level (Ldn) of 55 dBA at the NSAs.
22. Transco shall file a noise survey with the
Secretary no later than 60 days after placing
Compressor Station 116 into service. If a full load
condition noise survey is not possible, Transco shall
provide an interim survey at the maximum possible
power load and provide the full power load survey
within 6 months. If the noise attributable to the
operation of all of the equipment at any compressor
station at interim or full power load conditions exceeds
55 dBA Ldn at any nearby NSAs, Transco shall file a
report on what changes are needed and shall install
additional noise controls to meet the level within 1
year of the in-service date. Transco shall confirm
compliance with the above requirement by filing a
second noise survey with the Secretary no later than
60 days after it installs the additional noise controls.
23. Transco shall file a noise survey with the
Secretary no later than 60 days after placing the
Murray Meter Station in service. If the noise
80a
attributable to the operation of the meter station at
maximum flow exceeds an Ldn of 55 dBA at any nearby
NSAs, Transco
This text is long and has been trimmed here. Open the source document for the complete record.
This is a copy of a public record, reproduced as it was published. It is not legal advice, and it may not be the version a court would rely on. Check the official source before you cite it.