Petition for Writ of Certiorari — California Trout, et al., Petitioners v. Hoopa Valley Tribe, et al.

Supreme Court briefAug 26, 2019

Ask Donna

What actually matters in this document.

Text

1a

United States Court of Appeals

FOR THE DISTRICT OF COLUMBIA CIRCUIT

-----------------------------------------------------------------------

Argued October 1, 2018

Decided January 25, 2019

No. 14-1271

HOOPA VALLEY TRIBE,

PETITIONER

v.

FEDERAL ENERGY REGULATORY COMMISSION,

RESPONDENT

AMERICAN RIVERS, ET AL.,

INTERVENORS

-----------------------------------------------------------------------

On Petition for Review of Orders of the

Federal Energy Regulatory Commission

-----------------------------------------------------------------------

Thane D. Somerville argued the cause for petitioner. With him on the briefs was Thomas P. Schlosser.

Carol J. Banta, Attorney, Federal Energy Regulatory Commission, argued the cause for respondent. On

the brief were James P. Danly, General Counsel, Robert H. Solomon, Solicitor, Robert M. Kennedy, Senior

Attorney, and Ross R. Fulton, Attorney.

Richard Roos-Collins, Julie Gantenbein, Stuart

Sornach, Michael A. Swiger, and Sharon L. White were

on the briefs for intervenors American Rivers, et al. in

support of respondent.

2a

Michael A. Swiger and Sharon L. White were on

the brief for intervenor Pacificorp in support of respondent. Charles R. Sensiba entered an appearance.

George J. Mannina Jr. was on the brief for intervenor-respondent Siskiyou County, California. Ashley

Remillard and Paul S. Weiland entered appearances.

Robert W. Ferguson, Attorney General, Sonia A.

Wolfman, Assistant Attorney General, Office of the Attorney General for the State of Washington, Lawrence

G. Wasden, Attorney General, Office of the Attorney

General for the State of Idaho, Joseph A. Foster, Attorney General, Office of the Attorney General for the

State of New Hampshire, Douglas S. Chin, Attorney

General, Office of the Attorney General for the State of

Hawaii, Janet T. Mills, Attorney General, Office of the

Attorney General for the State of Maine, Peter K. Michael, Attorney General, Office of the Attorney General

for the State of Wyoming, Eric T. Schneiderman, Attorney General at the time the brief was filed, Office of the

Attorney General for the State of New York, and Sean

D. Reyes, Attorney General, Office of the Attorney General for the State of Utah, were on the brief for amici

curiae States of Washington, et al. in support of intervenors-respondents American Rivers, et al.

Kamala D. Harris, Attorney General at the time

the brief was filed, Office of the Attorney General for

the State of California, Robert W. Byrne, Senior Assistant Attorney General, Eric M. Katz, Supervising Deputy Attorney General, and Ross H. Hirsch and Adam

L. Levitan, Deputy Attorneys General, were on the

3a

brief for amicus curiae California State Water Resources Control Board in support of respondent.

Ellen F. Rosenblum, Attorney General, and Paul

Garrahan, Attorney-In-Charge, Office of the Attorney

General for the State of Oregon, were on the brief for

amicus curiae The State of Oregon in support of respondent.

Before: GRIFFITH and PILLARD, Circuit Judges, and

SENTELLE, Senior Circuit Judge.

Opinion for the Court filed by Senior Circuit Judge

SENTELLE.

SENTELLE, Senior Circuit Judge: Hoopa Valley

Tribe (“Hoopa”) petitions for review of Federal Energy

Regulatory Commission (“FERC”) orders, which found

(1) that California and Oregon had not waived their

water quality certification authority under Section 401

of the Clean Water Act (“CWA”) and (2) that PacifiCorp

had diligently prosecuted its relicensing application for

the Klamath Hydroelectric Project (“Project”). Whereas

statutory waiver is mandated after a request has been

pending for more than one year, the issue in this case

is whether states waive Section 401 authority by deferring review and agreeing with a licensee to treat repeatedly withdrawn and resubmitted water quality

certification requests as new requests. We conclude

that the withdrawal-and-resubmission of water quality certification requests does not trigger new statutory periods of review. Therefore, we grant the petition

and vacate the orders under review.

4a

I.

BACKGROUND

A. Statutory Background

Under Subchapter I of the Federal Power Act

(“FPA”), 16 U.S.C. §§ 791a-823g, Congress granted

FERC authority to regulate the licensing, conditioning,

and development of hydropower projects on navigable

waters. Under Section 401 of the CWA, any applicant

seeking a federal license for an activity that “may result in any discharge into the navigable waters” must

first seek water quality certifications from the controlling states. See 33 U.S.C. § 1341(a)(1). Thus, a state’s

water quality review serves as a precondition to any

federal hydropower license issued by FERC. The statute further provides that state certification requirements “shall be waived with respect to such Federal

application” if the state “fails or refuses to act on a request for certification, within a reasonable period of

time (which shall not exceed one year) after receipt of

such request.” See id. “[T]he purpose of the waiver provision is to prevent a State from indefinitely delaying

a federal licensing proceeding by failing to issue a

timely water quality certification under Section 401.”

Alcoa Power Generating Inc. v. FERC, 643 F.3d 963, 972

(D.C. Cir. 2011).

B. History of the Klamath Hydroelectric

Project

In this case, the hydropower project in question

consists of a series of dams along the Klamath River in

California and Oregon, which were originally licensed

5a

to a predecessor of PacifiCorp in 1954. Since the original license expired in 2006, PacifiCorp has continued

to operate the Project on annual interim licenses pending the broader licensing process. Due to the age of the

Project, the dams are not in compliance with modern

environmental standards. Since modernizing the dams

was presumably not cost-effective, PacifiCorp sought to

decommission the lower dams. In 2004, PacifiCorp filed

for relicensing with FERC, with a proposal to relicense

the upper dams and decommission the remainder. All

milestones for relicensing have been met except for the

states’ water quality certifications under Section 401.

In 2008, a consortium of parties—California, Oregon,

Native American tribes, farmers, ranchers, conservation groups, fishermen, and PacifiCorp—began settlement negotiations to resolve the procedures and the

risks associated with the dams’ decommissioning.

These negotiations culminated in a formal agreement

in 2010, the Klamath Hydroelectric Settlement Agreement (“KHSA” or the “Agreement”), imposing on PacifiCorp a series of interim environmental measures and

funding obligations, while targeting a 2020 decommission date. Under the KHSA, the states and PacifiCorp

agreed to defer the one-year statutory limit for Section

401 approval by annually withdrawing-and-resubmitting the water quality certification requests that serve

as a pre-requisite to FERC’s overarching review. The

Agreement explicitly required abeyance of all state

permitting reviews:

Within 30 days of the Effective Date, the

Parties, except ODEQ [Oregon Department of

6a

Environmental Quality], will request to the

California State Water Resources Control

Board and the Oregon Department of Environmental Quality that permitting and environmental review for PacifiCorp’s FERC

Project No. 2082 [Klamath Hydroelectric Project] licensing activities, including but not limited to water quality certifications under Section

401 of the CWA and review under CEQA [California Environmental Quality Act], will be

held in abeyance during the Interim Period

under this Settlement. PacifiCorp shall withdraw and re-file its applications for Section

401 certifications as necessary to avoid the

certifications being deemed waived under the

CWA during the Interim Period.

See KHSA at 42.

The parties to the KHSA agreed to a number of

preconditions for decommissioning, the most relevant

of which was the securing of federal funds, which

never occurred. Consequently, on April 6, 2016, a subset of parties from the original KHSA agreed to an

“Amended KHSA,” which created an alternative plan

for decommissioning that contemplated the transfer of

licensing to a company, Klamath River Renewal Corporation (“KRRC”), formed by the signatories of the

Amended KHSA in order to limit potential liability

that existing parties anticipated from decommissioning the dams. Of relevance, Hoopa—whose reservation

is downstream of the Project—was not a party to either

the KHSA or the Amended KHSA.

7a

On September 23, 2016, PacifiCorp filed for an

amended license to enable transfer of the dams to

KRRC. Having never previously considered the transfer of a license for the sole purpose of decommissioning,

and based on legal, technical, and financial concerns,

FERC chose to separately review the applications for

(1) amendment and (2) transfer. On March 15, 2018,

FERC approved splitting the lower dams to a separate

license, but has yet to approve transfer of that license.

PacifiCorp remains the licensee for both of these newly

split licenses.

C. Procedural History

On May 25, 2012, Hoopa petitioned FERC for a declaratory order that California and Oregon had waived

their Section 401 authority and that PacifiCorp had

correspondingly failed to diligently prosecute its licensing application for the Project. On June 19, 2014,

FERC denied that petition. On July 18, 2014, Hoopa

requested rehearing on its original petition, and FERC

denied that request on October 16, 2014. Subsequently,

on December 9, 2014, Hoopa petitioned this Court to

review FERC’s orders. This Court initially held the

case in abeyance once the Amended KHSA was in

place. But the decommissioning the agreement contemplated has yet to occur, and in light of Hoopa’s

pending petition, we removed the case from abeyance

on May 9, 2018.

8a

II.

DISCUSSION

We review FERC orders under the Administrative

Procedure Act (“APA”), which empowers the Court “to

reverse any agency action that is ‘arbitrary, capricious,

an abuse of discretion, or otherwise not in accordance

with law.’ ” See, e.g., Wisconsin Valley Improvement v.

FERC, 236 F.3d 738, 742 (D.C. Cir. 2001) (quoting 5

U.S.C. § 706(2)(A)). In conducting the review in this

case, because FERC is not the agency charged with administering the CWA, the Court owes no deference to

its interpretation of Section 401 or its conclusion regarding the states’ waiver. See Alcoa Power, 643 F.3d at

972.

A. Sovereign Immunity

The state of Oregon, an amicus curiae, has challenged this Court’s jurisdiction over the instant matter. Specifically, California and Oregon have exercised

their sovereign immunity under the Eleventh Amendment by refusing to intervene in this review. Oregon

avers a status as an indispensable party because this

review entails a potential finding of the states’ waiver

of their Section 401 authority. Thus, Oregon asserts

that this case must be dismissed, relying on Fed. R. Civ.

P. 19.

However, California and Oregon are not indispensable parties to the instant case. Contrary to Oregon’s

argument, Fed. R. Civ. P. 19 does not govern this joinder issue. See Int’l Union, United Auto. v. Scofield, 382

U.S. 205, 217 n.10 (1965). Rather, as an appellate court

9a

reviewing an agency action, we look to Fed. R. App.

P. 15. Rule 15 only requires the respondent federal

agency as a necessary party to a petition for review—

joinder of no other party is required. See Fed. R. App.

P. 15. With regard to sovereign immunity generally,

Oregon’s position is incompatible with the precepts of

federalism and this Court’s prior precedent. Hoopa’s

petition does not involve a state’s certification decision

or a state’s application of state law, but rather a federal

agency’s order, a matter explicitly within the purview

of this Court when petitioned by an aggrieved party.

See 16 U.S.C. § 825l(b). Indeed, FERC orders regarding

a state’s compliance are properly reviewed by federal

appeals courts whether or not the state is a party to

the review. See, e.g., City of Tacoma v. FERC, 460 F.3d

53 (D.C. Cir. 2006). This is especially true, in cases such

as this, when the dispositive issue on review is the interpretation of federal law. See U.S. Const. art. III, § 2,

cl. 1 (“The judicial Power shall extend to all Cases, in

Law and Equity, arising under this Constitution, the

Laws of the United States, and Treaties made, or which

shall be made, under their Authority. . . .”). Accordingly, this Court has jurisdiction over the instant matter, and we shall proceed to the merits of Hoopa’s

claims.

B. Waiver under Section 401

Hoopa’s petition presents three theories as bases

for relief: the states’ waiver of their Section 401 authority, PacifiCorp’s failure to diligently prosecute its

licensing application, and FERC’s abdication of its

10a

regulatory duty. However, all of Hoopa’s theories are

connected.

Resolution of this case requires us to answer a single issue: whether a state waives its Section 401 authority when, pursuant to an agreement between the

state and applicant, an applicant repeatedly withdraws-and-resubmits its request for water quality certification over a period of time greater than one year. If

this type of coordinated withdrawal-and-resubmission

scheme is a permissible manner for tolling a state’s

one-year waiver period, then (1) California and Oregon

did not waive their Section 401 authority; (2) PacifiCorp did not fail to diligently prosecute its application;

and (3) FERC did not abdicate its duty. However, if

such a scheme is ineffective, then the states’ and licensee’s actions were an unsuccessful attempt to circumvent FERC’s regulatory authority of whether and

when to issue a federal license.

Determining the effectiveness of such a withdrawaland-resubmission scheme is an undemanding inquiry

because Section 401’s text is clear.

If the State, interstate agency, or Administrator, as the case may be, fails or refuses to act

on a request for certification, within a reasonable period of time (which shall not exceed one

year) after receipt of such request, the certification requirements of this subsection shall

be waived with respect to such Federal application. No license or permit shall be granted

until the certification required by this section

11a

has been obtained or has been waived as provided in the preceding sentence.

See 33 U.S.C. § 1341(a)(1). The temporal element imposed by the statute is “within a reasonable period

of time,” followed by the conditional parenthetical,

“(which shall not exceed one year).” See id. Thus, while

a full year is the absolute maximum, it does not preclude a finding of waiver prior to the passage of a full

year. Indeed, the Environmental Protection Agency

(“EPA”)—the agency charged with administering the

CWA—generally finds a state’s waiver after only six

months. See 40 C.F.R. § 121.16.

The pendency of the requests for state certification

in this case has far exceeded the one-year maximum.

PacifiCorp first filed its requests with the California

Water Resources Control Board and the Oregon Department of Environmental Quality in 2006. Now,

more than a decade later, the states still have not rendered certification decisions. FERC “sympathizes” with

Hoopa, noting that the lengthy delay is “regrettable.”

According to FERC, it is now commonplace for states

to use Section 401 to hold federal licensing hostage. At

the time of briefing, twenty-seven of the forty-three licensing applications before FERC were awaiting a

state’s water quality certification, and four of those had

been pending for more than a decade.

Implicit in the statute’s reference “to act on a request for certification,” the provision applies to a specific request. See 33 U.S.C. § 1341(a)(1) (emphasis

added). This text cannot be reasonably interpreted to

12a

mean that the period of review for one request affects

that of any other request. In its decision, FERC used

this text to rescue the states from waiver. FERC found

that while PacifiCorp’s various resubmissions involved

the same Project, each resubmission was an independent request, subject to a new period of review. Thus,

FERC averred that the states had not failed to act. In

doing so, FERC acted arbitrarily and capriciously.

The record does not indicate that PacifiCorp withdrew its request and submitted a wholly new one in its

place, and therefore, we decline to resolve the legitimacy of such an arrangement. We likewise need not

determine how different a request must be to constitute a “new request” such that it restarts the one-year

clock. This case presents the set of facts in which a

licensee entered a written agreement with the reviewing states to delay water quality certification. PacifiCorp’s withdrawals-and-resubmissions were not just

similar requests, they were not new requests at all.

The KHSA makes clear that PacifiCorp never intended

to submit a “new request.” Indeed, as agreed, before

each calendar year had passed, PacifiCorp sent a letter

indicating withdrawal of its water quality certification

request and resubmission of the very same . . . in the

same one-page letter . . . for more than a decade. Such

an arrangement does not exploit a statutory loophole;

it serves to circumvent a congressionally granted authority over the licensing, conditioning, and developing

of a hydropower project.

While the statute does not define “failure to act” or

“refusal to act,” the states’ efforts, as dictated by the

13a

KHSA, constitute such failure and refusal within the

plain meaning of these phrases. Section 401 requires

state action within a reasonable period of time, not to

exceed one year. California and Oregon’s deliberate

and contractual idleness defies this requirement. By

shelving water quality certifications, the states usurp

FERC’s control over whether and when a federal license will issue. Thus, if allowed, the withdrawal-andresubmission scheme could be used to indefinitely

delay federal licensing proceedings and undermine

FERC’s jurisdiction to regulate such matters.

Congress intended Section 401 to curb a state’s

“dalliance or unreasonable delay.” See, e.g., 115 Cong.

Rec. 9264 (1969). This Court has repeatedly recognized

that the waiver provision was created “to prevent a

State from indefinitely delaying a federal licensing

proceeding.” See Alcoa Power, 643 F.3d at 972-73; Millennium Pipeline Co. v. Seggos, 860 F.3d 696, 701-02

(D.C. Cir. 2017).

While caselaw offers some guidance regarding a

state’s waiver, e.g., North Carolina v. FERC, 112 F.3d

1175, 1183-85 (D.C. Cir. 1997), this Court has never addressed the specific factual scenario presented in this

case, i.e., an applicant agreeing with the reviewing

states to exploit the withdrawal-and-resubmission of

water quality certification requests over a lengthy period of time. In its supplemental brief, FERC directs

the Court’s attention to a Second Circuit opinion which

suggested, in light of various practical difficulties, that

a state could “request that the applicant withdraw and

resubmit the application.” See New York State Dep’t of

14a

Envtl. Conservation v. FERC, 884 F.3d 450, 455-56 (2d

Cir. 2018) (citing Constitution Pipeline Co., LLC v. New

York State Dep’t of Envtl. Conservation, 868 F.3d 87, 94

(2d Cir. 2017)). That suggestion was not central to the

court’s holding. The dicta was offered to rebut the state

agency’s fears that a one-year review period could result in incomplete applications and premature decisions. See id. (identifying denial without prejudice as

another alternative).

While it is the role of the legislature, not the judiciary, to resolve such fears, those trepidations are inapplicable to the instant case. The record indicates

that PacifiCorp’s water quality certification request

has been complete and ready for review for more than

a decade. There is no legal basis for recognition of an

exception for an individual request made pursuant to

a coordinated withdrawal-and-resubmission scheme,

and we decline to recognize one that would so readily

consume Congress’s generally applicable statutory

limit. Accordingly, we conclude that California and Oregon have waived their Section 401 authority with regard to the Project.

C. Futility

FERC postulated that a finding of waiver would

require the agency to deny PacifiCorp’s license. As a

result, PacifiCorp would have to file a decommissioning

plan for the Klamath dams, and since decommissioning of the Project is an activity that itself would result

in a “discharge into the navigable waters,” that plan

15a

would be subject to its own set of the oft-delayed state

water quality certifications. Thus, in a futile sequence

of events, the Project would revert back to its present

state, only burdened with additional delays.

FERC may be correct that “[i]ndefinite delays in

processing [licensing] applications are . . . not in the

public interest.” See Georgia-Pacific Corp., 35 FERC

¶ 61120, 61248 n.8 (Apr. 25, 1986). However, such practical concerns do not trump express statutory directives. See supra Section II.B. Regardless, had FERC

properly interpreted Section 401 and found waiver

when it first manifested more than a decade ago, decommissioning of the Project might very well be underway.

Further, FERC possesses a critical role in protecting the public interest in hydropower projects. See 16

U.S.C. §§ 797(e), 803(a), 808(a). FERC solicits comments

from interested parties and holds public meetings.

See, e.g., U.S. Dep’t of Interior v. FERC, 952 F.2d 538,

540 (D.C. Cir. 1992). FERC may also “participate in

an advisory role in settlement discussions or review

proposed settlements” for the development or decommissioning of such projects. See Settlements in Hydropower Licensing Proceedings under Part I of the

Federal Power Act, 116 FERC ¶ 61270, 62086 (Sept. 1,

2006). Here, it did neither. Hoopa’s interests are not

protected directly as it is not a party to the KHSA

or Amended KHSA, nor are its interests protected indirectly through any participation by FERC in those

same settlement agreements. Therefore, we disagree that

a finding of waiver is futile because, at a minimum, it

16a

provides Hoopa and FERC an opportunity to rejoin the

bargaining table.

III. CONCLUSION

For the reasons set forth above, we vacate and remand the rulings under review. FERC shall proceed

with its review of, and licensing determination for, the

Klamath Hydroelectric Project.

17a

United States Court of Appeals

FOR THE DISTRICT OF COLUMBIA CIRCUIT

-----------------------------------------------------------------------

No. 14-1271

September Term, 2018

FERC-P-2082-61

Filed On: April 26, 2019

Hoopa Valley Tribe,

Petitioner

v.

Federal Energy Regulatory Commission,

Respondent

-----------------------American Rivers, et al.,

Intervenors

BEFORE: Griffith and Pillard, Circuit Judges;

Sentelle*, Senior Circuit Judge

ORDER

Upon consideration of the petition of respondentintervenors American Rivers, California Trout, and

Trout Unlimited for panel rehearing, and the response

thereto; the motions of the States of Oregon, et al.,

the California State Water Resources Control Board

(“California Board”), and the Karuk Tribe, et al., for

* Senior Circuit Judge Sentelle would deny the motions of

the States of Oregon, et al., and the California Board for invitation to file briefs amici curiae.

18a

invitation to file briefs amici curiae, and the lodged

briefs amici curiae; and the motion of respondentintervenor PacifiCorp for leave to file a response and

the lodged response, it is

ORDERED that the motions filed by the States of

Oregon, et al. and the California Board for invitation

to file briefs amici curiae be granted. The Clerk is directed to file the lodged briefs. It is

FURTHER ORDERED that the motion filed by

the Karuk Tribe, et al. for invitation to file brief amici

curiae be denied. The Clerk is directed to note the

docket accordingly. It is

FURTHER ORDERED that the motion of PacifiCorp for leave to file a response be granted. The Clerk

is directed to file the lodged response. It is

FURTHER ORDERED that the petition for

panel rehearing be denied.

Per Curiam

FOR THE COURT:

Mark J. Langer, Clerk

BY: /s/

Ken Meadows

Deputy Clerk

19a

United States Court of Appeals

FOR THE DISTRICT OF COLUMBIA CIRCUIT

-----------------------------------------------------------------------

No. 14-1271

September Term, 2018

FERC-P-2082-61

Filed On: April 26, 2019

Hoopa Valley Tribe,

Petitioner

v.

Federal Energy Regulatory Commission,

Respondent

-----------------------American Rivers, et al.,

Intervenors

BEFORE: Garland, Chief Judge; Henderson, Rogers, Tatel, Griffith, Srinivasan, Millett,

Pillard, Wilkins, Katsas, and Rao*, Circuit Judges; Sentelle**, Senior Circuit

Judge

ORDER

Upon consideration of the petition of respondentintervenors American Rivers, California Trout, and

* Circuit Judge Rao did not participate in this matter.

** Senior Circuit Judge Sentelle would deny the motions of

the States of Oregon, et al., and the California Board for invitation to file briefs amici curiae.

20a

Trout Unlimited for rehearing en banc, and the absence of a request by any member of the court for a

vote; and the motions of the States of Oregon, et al., the

California State Water Resources Control Board (“California Board”), and the Karuk Tribe, et al., for invitation to file briefs amici curiae, and the lodged briefs

amici curiae, it is

ORDERED that the motions of the States of Oregon, et al. and the California Board for invitation to file

briefs amici curiae be granted. The Clerk is directed to

file the lodged briefs. It is

FURTHER ORDERED that the motion of Karuk

Tribe, et al. for invitation to file brief amici curiae be

denied. The Clerk is directed to note the docket accordingly. It is

FURTHER ORDERED that the petition for rehearing en banc be denied.

Per Curiam

FOR THE COURT:

Mark J. Langer, Clerk

BY: /s/

Ken Meadows

Deputy Clerk

21a

2014 WL 2794387

FEDERAL ENERGY REGULATORY COMMISSION

Commission Opinions, Orders and Notices

Before Commissioners: Cheryl A. LaFleur, Acting

Chairman; Philip D. Moeller, John R. Norris, and Tony

Clark.

PacifiCorp

Project No., 2082-058

ORDER DENYING PETITION

FOR DECLARATORY ORDER

(Issued June 19, 2014)

1. The Hoopa Valley Tribe (Tribe) has filed a petition

for a declaratory order asking the Commission to find

that PacifiCorp, the licensee for the Klamath Hydroelectric Project No. 2082, has failed to diligently pursue

relicensing of the project, dismiss PacifiCorp’s relicense application, and direct PacifiCorp to file a plan

for decommissioning the project. In the alternative, the

Tribe asks the Commission to declare that the State of

California Water Resources Control Board (California

Water Board) and the Oregon Department of Environmental Quality (Oregon DEQ) have waived their

authority to issue water quality certification for the

project pursuant to the Clean Water Act. This order denies the petition.

22a

Background

2. The 169-megawatt Klamath Project is located

principally on the Klamath River in Klamath County,

Oregon and Siskiyou County, California.1 The project

includes seven hydroelectric developments and one

non-generating dam.2 The Commission’s predecessor,

the Federal Power Commission, issued a 50-year original license for the project in 1954. The license expired

in 2006 and the project has been operated under annual license since that time.3

3. On February 25, 2004, PacifiCorp filed with the

Commission an application for a new license for the

Klamath Project. The company proposed to relicense

five of the project’s generating developments and to decommission the other three developments, including

the non-generating development. In November 2007,

Commission staff issued a Final Environmental Impact Statement (EIS) in the relicensing proceeding.4

Staff recommended adopting PacifiCorp’s proposal,

with the addition of a number of environmental measures.

4. On March 5, 2010, PacifiCorp filed with the Commission the Klamath Hydroelectric Settlement Agreement

1

One development is located on Fall Creek, a tributary to

the Klamath.

2

See Final Environmental Impact Statement for Hydropower

License, Klamath Hydroelectric Project, Federal Energy Regulatory Commission, Office of Energy Projects (November 2007) at

xxxiii.

3

See 16 U.S.C. § 808(a)(1) (2012).

4

See n.2, infra.

23a

(Settlement Agreement). The Settlement Agreement,

which was signed by the Governors of the States of

California and Oregon, PacifiCorp, the U.S. Department of the Interior, the Department of Commerce’s

National Marine Fisheries Service, several Indian

tribes (not including the Hoopa Tribe), and a number

of local counties, irrigators, and conservation and fishing groups, provided for the future removal of PacifiCorp’s licensed Klamath River dams, with a target

date of 2020. The parties did not ask the Commission

to act on the agreement, the completion of which was

contingent on the passage of federal legislation and action by the Secretary of the Interior.

5. To date, no federal legislation regarding the Settlement Agreement has been enacted,5 and the parties

have not requested Commission action.

6. Under section 401(a)(1) of the Clean Water Act,6

the Commission may not issue a license authorizing

the construction or operation of a hydroelectric project

unless the state water quality certifying agency has either issued a Water Quality Certification for the project or has waived certification by failing to act on a

request for certification within a reasonable period of

time, not to exceed one year.

5

On May 21, 2014, Senator Wyden introduced S. 2379, entitled, “A bill to approve and implement the Klamath Basin agreements, to improve natural resource management, support economic

development, and sustain agricultural production in the Klamath

River Basin in the public interest and the interest of the United

States, and for other purposes.”

6

33 U.S.C. § 1341(a)(1) (2012).

24a

7. PacifiCorp filed a request for water quality certification with the California Water Board on March 29,

2006. Since then, the company has withdrawn and refiled its application eight times. Similarly, PacifiCorp

filed a request for certification with Oregon DEQ on

March 29, 2006, and has withdrawn and refiled its

application eight times. In refiling its applications,

PacifiCorp has noted that the Settlement Agreement

requires it to do so in order to avoid waiver by the water quality certifying agencies.7

8. On May 25, 2012, the Tribe filed a petition for a

declaratory order, asking the Commission to find that

PacifiCorp has failed to diligently pursue relicensing of

the project and accordingly require the company to file

a plan for decommissioning the project, or, in the alternative, find that California and Oregon have waived

water quality certification and issue a new license for

the project.

9. On June 25, 2012, PacifiCorp, on behalf of itself

and 16 other parties, filed an answer opposing the petition. Also on June 25, 2012, the County of Siskiyou

and Siskiyou County Flood Control and Water Conservation District filed an answer opposing project decommissioning but urging issuance of a license.

7

See, e.g., letter from Mark A. Sturtevant (PacifiCorp) to

Kimberly D. Bose (Commission Secretary), enclosing December 2,

2033 letter from PacifiCorp to Oregon Department of Water Quality (filed December 16, 2013).

25a

Discussion

10. The Tribe argues that PacifiCorp is not taking action to obtain water quality certification and thus is

not diligently pursuing its license application.8 The

Tribe therefore asks the Commission to dismiss the relicense application and require the company to file a

plan to decommission the project.9

11. We agree with the Tribe that the circumstances

of this case are far from ideal. As noted above, Commission staff issued the EIS in November 2007. The

Commission could act on PacifiCorp’s application but

for the absence of water quality certification.10 The

Klamath Project is operating under the terms of the

1954 license, and, as a result, the many environmental

benefits that could accrue under the new license have

not occurred.11 Under the express terms of the Clean

Water Act, however, the Commission cannot issue and

implement a new license until water quality certification has been issued.

8

Petition at 1-12.

Id. at 12-13.

10

There is also a need to conclude consultation under the National Historic Preservation Act, but such matters, as a rule, do

not delay license issuance.

11

While we cannot and do not consider the license application now, we note, as a general matter, that all licenses we have

issued in recent times contain substantially more environmental

measures than those issued 50 years ago, before any of the current environmental statutes were enacted and before the Federal

Power Act was amended to enhance consideration of environmental matters.

9

26a

12. We also agree with the Tribe that PacifiCorp has

been complicit with the parties to the Settlement

Agreement in agreeing to delay water quality certification, and that there is no apparent prospect of the federal legislation called for by the settlement being

passed or of the necessary actions by the Secretary of

the Interior taking place. Again, as the Tribe asserts,

infinite delays in licensing proceedings are not in the

public interest. Indeed, they are contrary to it.

13. Nonetheless, the remedy suggested by the Tribe

—requiring PacifiCorp to file a decommissioning plan

—would not resolve the impasse here. Any major decommissioning would likely result in some form of discharge into the navigable waters, meaning that the

Commission could not implement decommissioning

without a water quality certification.12 Given that we

would be acting contrary to the process envisioned by

all the parties to the settlement, including the two water quality certifying agencies, it appears unlikely that

the agencies would issue certification for a decommissioning process that did not comport with the terms of

the settlement to which they have agreed.13 It seems

12

See, e.g., Duke Energy Carolinas, LLC, 120 FERC ¶ 61,054

(2007) at PP 33-36 (stating that Commission could not accept license surrender, which included dam removal, without state water quality certification), reh’g denied, 123 FERC ¶ 61,069 at 1721) (2008), aff ’d, Jackson County v. FERC, 589 F.3d 1284 (D.C.

Cir. 2009).

13

Another likely outcome might be for PacifiCorp to file the

Settlement Agreement as its decommissioning plan, even though

the plan could not be implemented absent Congressional and executive department action.

27a

more probable that they would either deny certification, thereby precluding decommissioning, or work

with PacifiCorp and the other parties to repeatedly delay certification, as has already occurred in this case.

14. In addition, while we do have the authority to order a licensee to decommission a project,14 we have

done so only once in the absence of the licensee’s consent, upon a finding that the facts of the case required

that outcome.15 Here, we have not concluded based on

the record that decommissioning is required, and thus

lack a basis for imposing such a requirement.16 We are

also unsure how demanding that PacifiCorp file a decommissioning plan when it had already taken substantial steps in that direction in concert with a large

number of parties would yield a positive result. If we

had a viable way to require the parties to move forward, we would certainly consider it. We do not see

such an option before us.

15. The Tribe asks that, if we do not dismiss PacifiCorp’s license application for lack of diligence and require a decommissioning plan, we issue a license,

based on the conclusion that California and Oregon

have waived water quality certification by failing to act

14

See Edwards Manufacturing Company, Inc. and City of

Augusta, Maine, 81 FERC ¶ 61,255 at 62,207-09 (1997).

15

Id.

16

Without in any way prejudging the merits of the relicensing proceeding, we note that the EIS prepared by our staff recommended decommissioning only some of the project dams, consist

with PacifiCorp’s licensing proposal. We would at a minimum seriously consider staff ’s recommendation in acting in this case.

28a

by the deadline established by the Clean Water Act —

a reasonable period of time, not to exceed one year from

the filing of a request for certification.17 The Tribe contends that the states’ failure to act within one year and

their agreement with PacifiCorp not to do so amount

to waiver.18

16. Again, we have some sympathy with the Tribe’s

argument. Indefinite delays in licensing proceedings

do not comport with at least the spirit of the Clean Water Act and have the effect of preventing us from issuing new licenses that are best adapted to a current

comprehensive plan for improving or developing a waterway in the public interest.19 We have previously

stated that we “cannot endorse procedures that result

in undue extensions of the licensing process. . . . [Such

an] inordinate delay was hardly what Congress contemplated in crafting the one-year certification deadline.”20

17. In this case, however, we see little to be gained

from finding that the states have waived certification

and then issuing a license. It is clear that PacifiCorp

and the other settling parties are committed to the process envisioned in the Settlement Agreement. PacifiCorp states in its opposition to the petition that it is

endeavoring to implement the terms of the Settlement

17

See 33 U.S.C. § 1341(a) (2012).

Petition at 14-21.

19

See 16 U.S.C. § 808(a) (2012).

20

Central Vermont Public Service Corporation, 113 FERC

¶ 61,167, at P 16, n.14 (2005).

18

29a

Agreement, and will pursue relicensing if the agreement terminates. Given that we cannot require a licensee to accept a license, and that PacifiCorp views itself

as bound to follow the settlement, we see little point in

pursuing a course that would almost certainly leads

[sic] to protracted litigation and would be unlikely to

resolve the issues in this proceeding.

The Commission orders:

The petition for declaratory order filed by the Hoopa

Valley Tribe on May 25, 2012, is denied.

By the Commission.

(SEAL)

Kimberly D. Bose

Secretary

30a

2014 WL 5293211

FEDERAL ENERGY REGULATORY COMMISSION

Commission Opinions, Orders and Notices

Before Commissioners: Cheryl A. LaFleur, Chairman;

Philip D. Moeller, Tony Clark, and Norman C. Bay.

PacifiCorp

Project No., 2082-061

ORDER DENYING REHEARING

(Issued October 16, 2014)

1. The Hoopa Valley Tribe (Tribe) has requested rehearing of the Commission’s June 19, 2014, order1

denying the Tribe’s petition for a declaratory order either (1) finding that PacifiCorp, the licensee for the

Klamath Hydroelectric Project No. 2082, has failed

to diligently pursue relicensing of the project, dismissing PacifiCorp’s relicense application, and directing

PacifiCorp to file a plan for decommissioning the project, or (2) in the alternative, declaring that the State

of California Water Resources Control Board (California Water Board) and the Oregon Department of Environmental Quality (Oregon DEQ) have waived their

authority to issue water quality certification for the

project pursuant to the Clean Water Act. As discussed

below, we deny rehearing.

1

PacifiCorp, 147 FERC ¶ 61,216 (2014) (June 19 Order).

31a

Background

2. The 169-megawatt Klamath Project is located

principally on the Klamath River in Klamath County,

Oregon and Siskiyou County, California.2 The project

includes seven hydroelectric developments and one

non-generating dam.3 The Commission’s predecessor,

the Federal Power Commission, issued a 50-year original license for the project in 1954. The license expired

in 2006 and the project has been operated under annual license since that time.4

3. On February 25, 2004, PacifiCorp filed with the

Commission an application for a new license for the

Klamath Project. The company proposed to relicense

five of the project’s generating developments and to decommission the other three developments, including

the non-generating development. In November 2007,

Commission staff issued a Final Environmental Impact

Statement (EIS) in the relicensing proceeding.5 Staff

recommended adopting PacifiCorp’s proposal, with the

addition of a number of environmental measures.

4. On March 5, 2010, PacifiCorp filed with the Commission the Klamath Hydroelectric Settlement Agreement

(Settlement Agreement). The Settlement Agreement,

2

One development is located on Fall Creek, a tributary to

the Klamath.

3

See Final Environmental Impact Statement for Hydropower

License, Klamath Hydroelectric Project, Federal Energy Regulatory Commission, Office of Energy Projects (November 2007) at

xxxiii.

4

See 16 U.S.C. § 808(a)(1) (2012).

5

See n.2, infra.

32a

which was signed by the Governors of the States of

California and Oregon, PacifiCorp, the U.S. Department of the Interior, the Department of Commerce’s

National Marine Fisheries Service, several Indian

tribes (not including the Hoopa Tribe), and a number

of local counties, irrigators, and conservation and fishing groups, provided for the future removal of PacifiCorp’s licensed Klamath River dams, with a target

date of 2020. The parties did not ask the Commission

to act on the agreement, the completion of which is contingent on the passage of federal legislation and action

by the Secretary of the Interior.

5. To date, no federal legislation regarding the Settlement Agreement has been enacted,6 and the parties

have not requested Commission action.

6. Under section 401(a)(1) of the Clean Water Act,7

the Commission may not issue a license authorizing

the construction or operation of a hydroelectric project

unless the state water quality certifying agency has either issued a Water Quality Certification for the project or has waived certification by failing to act on a

request for certification within a reasonable period of

time, not to exceed one year.

6

On May 21, 2014, Senator Wyden introduced S. 2379, entitled,

“A bill to approve and implement the Klamath Basin agreements,

to improve natural resource management, support economic development, and sustain agricultural production in the Klamath

River Basin in the public interest and the interest of the United

States, and for other purposes.”

7

33 U.S.C. § 1341(a)(1) (2012).

33a

7. PacifiCorp filed a request for water quality certification with the California Water Board on March 29,

2006. Since then, the company has withdrawn and refiled its application eight times. Similarly, PacifiCorp

filed a request for certification with Oregon DEQ on

March 29, 2006, and has withdrawn and refiled its application eight times.

8. On May 25, 2012, the Tribe filed a petition for a

declaratory order, asking the Commission to find that

PacifiCorp has failed to diligently pursue relicensing of

the project and accordingly require the company to file

a plan for decommissioning the project, or, in the alternative, find that California and Oregon have waived

water quality certification and issue a new license for

the project.

9. In the June 19 order, the Commission denied the

Tribe’s petition. We explained that, while the circumstances of the Klamath project relicensing are far from

ideal, the Commission is barred by the Clean Water

Act from issuing a new license in the absence of water

quality certification from Oregon and California. We

further concluded that ordering PacifiCorp to file a decommissioning plan would be unlikely to resolve the

current impasse, given that the great majority of parties to the relicensing are pursuing implementation of

the settlement, and that decommissioning would probably require water quality certification, which the

states, as supporters of the settlement process, would

not likely issue.8 With respect to the Tribe’s assertion

8

June 19 Order, 147 FERC ¶ 61,216 at P 11.

34a

that we should find that California and Oregon have

waived water quality certification, we found that there

was little point in pursuing a course that would almost

certainly lead to protracted litigation and would be unlikely to resolve the issues in this proceeding.9

10. On July 18, 2014, the Tribe filed a timely request

for rehearing.

Discussion

A. Dismissal of the Relicensing Application

11. The Tribe reiterates its assertions that PacifiCorp

is diligently pursuing neither the issuance of a new

license nor water quality certification, and that delay

in relicensing is not in the public interest.10 It asserts

that our conclusion that a decommissioning plan would

require water quality certification that the states would

be unlikely to issue is unsupported by the record and

an insufficient basis for denying its petition.11 The

Tribe further argues that, if the Commission were to

grant the Tribe’s petition, decommissioning would be

the only appropriate course of action. It contends that

the Commission must not let the settlement process

9

Id. P 17.

Request for rehearing at 12-14. The Tribe notes that the

Commission has the authority to deny a new license to an applicant seeking relicensing. Id. at 14. While this is true, it does not

assist us in resolving this case. Denying a new license where no

party, other than the Tribe, seeks such a result, and, indeed,

where our staff in the Final EIS recommended issuing a new license, would be difficult to justify.

11

Id. at 14-17.

10

35a

play out, but should either dismiss PacifiCorp’s application for lack of prosecution or find that the states

have waived water quality certification.12

12. Given that neither the Federal Power Act nor our

regulations impose any requirements with respect to

situations such as that presented here, we have considerable discretion with respect to administering this

proceeding. Indeed, “the formulation of procedures [is]

basically to be left within the discretion of the agencies

to which Congress [has] confided the responsibility for

substantive judgments.”13 The Tribe points to nothing

in law, regulation, or precedent that requires us to find

that PacifiCorp’s application should be dismissed.

13. As we explained in the June 19 order, lengthy delays in licensing proceedings are contrary to the public

interest.14 At the same time, we see little to be gained

by taking steps that would likely result in further delay, litigation, and extensive expenditures of time and

money by the parties and the Commission. While it

is unfortunately the case that there are relicensing

proceedings that have been pending for many years

12

Id. at 17-20. The Tribe asserts that the fact that we have

not taken action on the Settlement Agreement is contrary to our

settlement policy. Id. at 5, n.8 (citing Settlements in Hydropower

Licensing Proceedings under Part I of the Federal Power Act, 116

FERC ¶ 61,270 (2006)). Nothing in our policy or practice requires

us to act on settlements where, as here, the parties explicitly file

an agreement for the Commission’s information only, and not for

Commission action.

13

Vermont Yankee Nuclear Power Corp. v. Natural Res. Def.

Council, 435 U.S. 519, 524-25 (1978).

14

June 19 Order, 147 FERC § 61, 216 at P 12.

36a

awaiting water quality certification,15 there has been

no such instance in which we have dismissed a relicense application for the licensee’s failure to diligently

pursue the application, in large part because of the

confusion such an action would cause and because we

have not seen a clear path to resolving the issues in

these cases.16

14. We disagree with the Tribe’s assertion that we

lacked a basis in the record for suggesting that California and Oregon would be no more likely to issue water

quality certification for a project decommissioning proceeding than they have been during the relicensing

proceeding.17 In the June 19 Order, we explained that

“[g]iven that we would be acting contrary to the process envisioned by all the parties to the settlement, including the two water quality certifying agencies, it

appears unlikely that the agencies would issue certification

for a decommissioning process that did not comport

with the terms of the settlement to which they have

15

For example, relicensing of the Hells Canyon Project No.

1971 and the Poe Project No. 2107 has been pending since 2003,

while the Upper North Fork Feather River relicensing has been

awaiting water quality certification since 2002, and the Waterbury Project No. 2090 has been pending since 1999. Of 43 pending

license applications regarding which our staff has completed its

environmental analysis, 29 (67 percent) area waiting water quality certification.

16

We continue to consider whether there are actions or incentives we can take that may be appropriate in individual proceedings to break these logjams.

17

Request for Rehearing at 16.

37a

agreed.”18 There is indeed no direct evidence in the record as to how the agencies would react were we to

grant the Tribe’s petition,19 but our experience, both in

this proceeding and generally, led us to conclude that

California and Oregon could not be expected to act

more promptly to authorize an outcome they do not

support20 than they have in the relicensing proceeding.

We continue to find this conclusion reasonable.

15. The Tribe is also incorrect in asserting that requiring a decommissioning plan would be the only alternative in the case of a dismissed application. We

could, for example, consider the project to be orphaned

and seek other applications,21 or we could issue PacifiCorp a non-power license for all or part of the project.22

16. In sum, the Tribe has shown no error in our decision to deny its request that we dismiss PacifiCorp’s

application and we deny rehearing on this matter.

18

June 19 Order, 147 FERC ¶ 61,216 at P 13.

It is difficult to envision what evidence there could be, absent a statement by the agencies as to what they would do in a

hypothetical situation.

20

As noted in the June 19 order, a number of parties, including PacifiCorp, Oregon DEQ, and the California Water Board, opposed the Tribes petition.

21

See 18 C.F.R. § 61.25 (2014). While this section explicitly

deals with instances in which a license [sic] fails to file a timely,

complete application, we believe that it would be applicable in the

case of an application that we elected to dismiss later in a proceeding.

22

See 16 U.S.C. § 808(f) (2012).

19

38a

B. Waiver of Water Quality Certification

The Tribe argues that we erred in not determining

that California and Oregon have waived water quality

certification. The Tribe notes that section 401(a)(1) of

the Clean Water Act provides that if a state “fails or

refuses to act on a request for certification, within a

reasonable time (which shall not exceed one year) after

receipt of such request, the certification . . . shall be

waived . . . ,”23 and states that the question whether

waiver has occurred is a federal question to be decided

by the Commission.24 The Tribe cites a number of

cases, as well as legislative history, for the proposition

that Congress intended the one-year deadline to avoid

undue state delay of the federal proceedings.25

18. We agree with the Tribe that continued delays in

completing the water quality certification are inconsistent with Congress’ intent. We further agree that, in

licensing proceedings before it, the Commission has

the obligation to determine whether a state has complied with the procedures required by the Clean Water

Act, including whether a state has waived certification.26

23

See 33 U.S.C. § 1341(a)(1) (2012).

Request for Rehearing at 20-21.

25

Id. at 22-23.

26

See, e.g., Alcoa Power Generating Inc. v. FERC, 643 F.3d

963 (D.C. Cir. 2011) (affirming, as a federal question, the Commission’s determination that a state had not waived certification);

City of Tacoma v. FERC, 460 F.3d 53 (D.C. Cir. 2006) (stating that

the Commission was obligated to inquire as to whether a state

satisfied the Clean Water Act’s notice requirements); Keating v.

24

39a

19. We part company with the Tribe on whether certification has been waived in this case. The Tribe carefully hedges its argument, maintaining that it “does

not ask the Commission to declare that the practice of

‘withdrawal and resubmission’ is unlawful in every instance,”27 but is so only under the facts of this case, including the states’ not acting within one year of the

initial certification requests, the passage of time since

the original requests, the delay in the relicensing proceeding, the states’ agreement with the licensee not to

move forward on certification, and the fact the licensee

continues to operate its project under the terms of its

existing license.28

20. We continue to be concerned that states and licensees that engage in repeated withdrawal and refiling of applications for water quality certification are

acting, in many cases, contrary to the public interest

by delaying the issuance of new licenses that better

meet current-day conditions than those issued many

decades ago, and that these entities are clearly violating the spirit of the Clean Water Act by failing to provide reasonably expeditious state decisions; however,

notwithstanding that concern, we do not conclude that

they have violated the letter of that statute. Section

401(a)(1) provides that a state waives certification

when it does not act on an application within one year.

FERC, 927 F.2d 616 (D.C. Cir. 1991) (holding that the Commission was obligated to determine the effectiveness of a state’s purported revocation of certification).

27

Request for Rehearing at 25.

28

Id. at 25-26.

40a

The Act therefore speaks solely to state action or in action, rather than the repeated withdrawal and refiling

of applications. By withdrawing its applications before

a year has passed, and presenting the states with new

applications, PacifiCorp has, albeit repeatedly, given

the states new deadlines. The record does not reveal

that either state has in any instance failed to act on an

application that has been before it for more than one

year. Again, while the Commission continues to be concerned that these entities are violating the spirit of the

Clean Water Act, the particular circumstances here, including the length of the delay, do not demand a different result because the Act speaks directly only to state

action within one year of a certification request. Accordingly, we find that California and Oregon have not

waived water quality certification in this case.

21. The Tribe’s reliance on Central Vermont Public

Service Corporation29 is unavailing. In that case, although the state and the licensee had agreed that the

licensee would withdraw and refile its water quality

certification application on an annual basis, the licensee ultimately failed to do so and the state did not act

on the then-pending application before the one-year

deadline. We held that the passage of the deadline resulted in waiver, regardless of the fact that the two parties had intended to continue the withdrawal and

refiling process: the governing fact was the expiration

of the one-year period.30 Here, whether for good or ill,

29

113 FERC ¶ 61,167 (2005) (Central Vermont). See Request

for Rehearing at 23-24.

30

See Central Vermont, 113 FERC ¶ 61,167 at PP 15-16.

41a

PacifiCorp has withdrawn and refiled its certification

applications numerous times. The Tribe does not assert that the states missed the one-year deadline with

respect to any single one of the company’s applications.

In essence, PacifiCorp and the states have avoided the

error that Vermont and the licensee in that proceeding

made. Accordingly, Central Vermont is inapposite here.

22. The Tribe goes on to argue that our decision not

to declare that California and Oregon have waived water quality certification is arbitrary, capricious, and an

abuse of discretion. The Tribe again asserts that our

conclusions that the parties to the settlement are committed to it is unsupported by the record and that the

public interest requires us to issue a new license or a

decommissioning order.31

31

Request for Rehearing at 26-30. The Tribe also objects to

what it asserts is the Commission’s “failure to reinitiate the licensing process [[because] it cannot require a licensee to accept a

license.” Id. at 29. In the June 19 Order, 147 FERC ¶ 61,216 at

P 17, we simply intended to indicate that the likely negative reaction to our issuing a license that ignored the wishes of the settling parties gave us little incentive to pursue untested legal

theories. We nonetheless fully agree with the Tribe that we must

issue licenses that satisfy the public interest standards established by the Federal Power Act, and we do not base licensing decisions on whether the applicant (or any other entity) will be

pleased by our actions. We further agree, as noted above, that a

new license would bring the project in line with current environmental standards. Were we to determine that water quality certification has been waived here, we would then issue a license that

we concluded met the public interest, as we have done in other

cases involving waiver. See, e.g., Central Vermont, supra; FPL

Energy Maine Hydro LLC, 139 FERC ¶ 61,215 (2012); Virginia

Electric Power Company d/b/a Dominion Virginia Power/Dominion

42a

23. As we have explained, it is the Clean Water Act

that prescribes when a state agency has waived certification; it is not an exercise of discretion vested in the

Commission. If our interpretation of the statute is incorrect, that would be for the courts to determine.32 As

to the adherence of the settling parties to their agreement, we have no way of knowing how firm their commitment is, but we think it a reasonable assumption

that entities will support an agreement which they

have voluntarily negotiated and signed.

The Commission orders:

The request for rehearing filed by the Hoopa Valley Tribe on July 18, 2014, is denied.

By the Commission.

(SEAL)

Kimberly D. Bose

Secretary

North Carolina Power, 110 FERC ¶ 61,241 (2005); Gustavus Electric Company, 109 FERC ¶ 61,105, reh’g denied, 110 FERC ¶ 61,334

(2004).

32

See Alabama Rivers Alliance v. FERC, 325 F.3d 290, 29697 (D.C.Cir.2003) (noting that the Commission’s interpretation of

Section 401 of the Clean Water Act is entitled to no deference by

the court because the Environmental Protection Agency, and not

the Commission, is charged with administering the Clean Water

Act, and that judicial review of the Commission’s interpretation

of Section 401 is de novo).

43a

TITLE 33—NAVIGATION AND

NAVIGABLE WATERS

SUBCHAPTER IV—PERMITS AND LICENSES

§ 1341. Certification

(a) Compliance with applicable requirements;

application; procedures; license suspension

(1) Any applicant for a Federal license or permit

to conduct any activity including, but not limited to,

the construction or operation of facilities, which may

result in any discharge into the navigable waters, shall

provide the licensing or permitting agency a certification from the State in which the discharge originates

or will originate, or, if appropriate, from the interstate

water pollution control agency having jurisdiction over

the navigable waters at the point where the discharge

originates or will originate, that any such discharge

will comply with the applicable provisions of sections

1311, 1312, 1313, 1316, and 1317 of this title. In the

case of any such activity for which there is not an applicable effluent limitation or other limitation under

sections 1311(b) and 1312 of this title, and there is

not an applicable standard under sections 1316 and

1317 of this title, the State shall so certify, except that

any such certification shall not be deemed to satisfy

section 1371(c) of this title. Such State or interstate

agency shall establish procedures for public notice in

the case of all applications for certification by it and, to

the extent it deems appropriate, procedures for public

hearings in connection with specific applications. In

any case where a State or interstate agency has no

44a

authority to give such a certification, such certification

shall be from the Administrator. If the State, interstate

agency, or Administrator, as the case may be, fails or

refuses to act on a request for certification, within a

reasonable period of time (which shall not exceed one

year) after receipt of such request, the certification requirements of this subsection shall be waived with respect to such Federal application. No license or permit

shall be granted until the certification required by this

section has been obtained or has been waived as provided in the preceding sentence. No license or permit

shall be granted if certification has been denied by the

State, interstate agency, or the Administrator, as the

case may be.

(2) Upon receipt of such application and certification the licensing or permitting agency shall immediately notify the Administrator of such application

and certification. Whenever such a discharge may affect, as determined by the Administrator, the quality of

the waters of any other State, the Administrator

within thirty days of the date of notice of application

for such Federal license or permit shall so notify such

other State, the licensing or permitting agency, and the

applicant. If, within sixty days after receipt of such notification, such other State determines that such discharge will affect the quality of its waters so as to

violate any water quality requirements in such State,

and within such sixty-day period notifies the Administrator and the licensing or permitting agency in writing of its objection to the issuance of such license or

permit and requests a public hearing on such objection,

45a

the licensing or permitting agency shall hold such a

hearing. The Administrator shall at such hearing submit his evaluation and recommendations with respect

to any such objection to the licensing or permitting

agency. Such agency, based upon the recommendations

of such State, the Administrator, and upon any additional evidence, if any, presented to the agency at the

hearing, shall condition such license or permit in such

manner as may be necessary to insure compliance with

applicable water quality requirements. If the imposition of conditions cannot insure such compliance such

agency shall not issue such license or permit.

(3) The certification obtained pursuant to paragraph (1) of this subsection with respect to the construction of any facility shall fulfill the requirements

of this subsection with respect to certification in connection with any other Federal license or permit required for the operation of such facility unless, after

notice to the certifying State, agency, or Administrator,

as the case may be, which shall be given by the Federal

agency to whom application is made for such operating

license or permit, the State, or if appropriate, the interstate agency or the Administrator, notifies such agency

within sixty days after receipt of such notice that there

is no longer reasonable assurance that there will be

compliance with the applicable provisions of sections

1311, 1312, 1313, 1316, and 1317 of this title because

of changes since the construction license or permit certification was issued in (A) the construction or operation of the facility, (B) the characteristics of the waters

into which such discharge is made, (C) the water

46a

quality criteria applicable to such waters or (D) applicable effluent limitations or other requirements. This

paragraph shall be inapplicable in any case where the

applicant for such operating license or permit has

failed to provide the certifying State, or, if appropriate,

the interstate agency or the Administrator, with notice

of any proposed changes in the construction or operation of the facility with respect to which a construction

license or permit has been granted, which changes may

result in violation of section 1311, 1312, 1313, 1316, or

1317 of this title.

(4) Prior to the initial operation of any federally

licensed or permitted facility or activity which may result in any discharge into the navigable waters and

with respect to which a certification has been obtained

pursuant to paragraph (1) of this subsection, which facility or activity is not subject to a Federal operating

license or permit, the licensee or permittee shall provide an opportunity for such certifying State, or, if appropriate, the interstate agency or the Administrator

to review the manner in which the facility or activity

shall be operated or conducted for the purposes of

assuring that applicable effluent limitations or other

limitations or other applicable water quality requirements will not be violated. Upon notification by the certifying State, or if appropriate, the interstate agency

or the Administrator that the operation of any such

federally licensed or permitted facility or activity will

violate applicable effluent limitations or other limitations or other water quality requirements such Federal

agency may, after public hearing, suspend such license

47a

or permit. If such license or permit is suspended, it

shall remain suspended until notification is received

from the certifying State, agency, or Administrator, as

the case may be, that there is reasonable assurance

that such facility or activity will not violate the applicable provisions of section 1311, 1312, 1313, 1316, or

1317 of this title.

(5) Any Federal license or permit with respect to

which a certification has been obtained under paragraph (1) of this subsection may be suspended or revoked by the Federal agency issuing such license or

permit upon the entering of a judgment under this

chapter that such facility or activity has been operated

in violation of the applicable provisions of section 1311,

1312, 1313, 1316, or 1317 of this title.

(6) Except with respect to a permit issued under

section 1342 of this title, in any case where actual construction of a facility has been lawfully commenced

prior to April 3, 1970, no certification shall be required

under this subsection for a license or permit issued after April 3, 1970, to operate such facility, except that

any such license or permit issued without certification

shall terminate April 3, 1973, unless prior to such termination date the person having such license or permit

submits to the Federal agency which issued such license or permit a certification and otherwise meets the

requirements of this section.

48a

(b) Compliance with other provisions of law

setting applicable water quality requirements

Nothing in this section shall be construed to limit

the authority of any department or agency pursuant to

any other provision of law to require compliance with

any applicable water quality requirements. The Administrator shall, upon the request of any Federal department or agency, or State or interstate agency, or

applicant, provide, for the purpose of this section, any

relevant information on applicable effluent limitations, or other limitations, standards, regulations, or

requirements, or water quality criteria, and shall,

when requested by any such department or agency or

State or interstate agency, or applicant, comment on

any methods to comply with such limitations, standards, regulations, requirements, or criteria.

(c) Authority of Secretary of the Army to permit use of spoil disposal areas by Federal

licensees or permittees

In order to implement the provisions of this section, the Secretary of the Army, acting through the

Chief of Engineers, is authorized, if he deems it to be

in the public interest, to permit the use of spoil disposal areas under his jurisdiction by Federal licensees

or permittees, and to make an appropriate charge for

such use. Moneys received from such licensees or permittees shall be deposited in the Treasury as miscellaneous receipts.

49a

(d) Limitations and monitoring requirements

of certification

Any certification provided under this section shall

set forth any effluent limitations and other limitations,

and monitoring requirements necessary to assure that

any applicant for a Federal license or permit will comply with any applicable effluent limitations and other

limitations, under section 1311 or 1312 of this title,

standard of performance under section 1316 of this title, or prohibition, effluent standard, or pretreatment

standard under section 1317 of this title, and with any

other appropriate requirement of State law set forth in

such certification, and shall become a condition on any

Federal license or permit subject to the provisions of

this section.

This is a copy of a public record, reproduced as it was published. It is not legal advice, and it may not be the version a court would rely on. Check the official source before you cite it.

A word about cookies

We need a few to keep you signed in and the library working. The rest help us see which pages people use and where they get stuck. They stay off unless you say yes.