Petition for Writ of Certiorari — Atlantic Coast Pipeline, LLC, Petitioner v. Cowpasture River Preservation Association, et al.

Supreme Court briefJun 25, 2019

Ask Donna

What actually matters in this document.

Text

APPENDIX

TABLE OF APPENDICES

Appendix A

Opinion, United States Court of Appeals

for the Fourth Circuit, Cowpasture River

Preservation Association v. Forest Service,

No. 18-1144 (Dec. 13, 2018)......................... App-1

Appendix B

Order, United States Court of Appeals for

the Fourth Circuit, Cowpasture River

Preservation Association v. Forest Service,

No. 18-1144 (Feb. 25, 2019)....................... App-67

Appendix C

Record of Decision, United States

Department of Agriculture, Atlantic

Coast Pipeline Project Special Use

Permit/Land & Resource Management

Plan Amendment (Nov. 17, 2017) ............. App-69

Appendix D

Relevant Statutory Provisions ................ App-237

30 U.S.C. §185 ...................................... App-237

16 U.S.C. §1244 .................................... App-237

16 U.S.C. §1246 .................................... App-289

16 U.S.C. §521 ...................................... App-301

App-1

Appendix A

UNITED STATES COURT OF APPEALS

FOR THE FOURTH CIRCUIT

________________

No. 18-1144

________________

COWPASTURE RIVER PRESERVATION ASSOCIATION;

HIGHLANDERS FOR RESPONSIBLE DEVELOPMENT;

SHENANDOAH VALLEY BATTLEFIELDS FOUNDATION;

SHENANDOAH VALLEY NETWORK; SIERRA CLUB;

VIRGINIA WILDERNESS COMMITTEE;

WILD VIRGINIA, INC.,

v.

Petitioners,

FOREST SERVICE, an agency of the U.S. Department of

the Agriculture; KATHLEEN ATKINSON, in her official

capacity as Regional Forester of the Eastern Region;

KEN ARNEY, in his official capacity as Acting Regional

Forester of the Southern Region,

Respondents,

ATLANTIC COAST PIPELINE LLC,

Intervenor.

________________

On Petition for Review of a Decision of the

United States Forest Service

________________

Argued: Sept. 28, 2018

Decided: Dec. 13, 2018

________________

App-2

THACKER, Circuit Judge:

In this case, we address whether the United

States Forest Service (“Forest Service”) complied with

the National Forest Management Act (“NFMA”), the

National Environmental Policy Act (“NEPA”), and the

Mineral Leasing Act (“MLA”) in issuing a Special Use

Permit (“SUP”) and Record of Decision (“ROD”)

authorizing Atlantic Coast Pipeline, LLC (“Atlantic”),

the project developer, to construct the Atlantic Coast

Pipeline (“ACP” or “the pipeline”) through parts of the

George Washington and Monongahela National

Forests (“GWNF” and “MNF,” respectively) and

granting a right of way across the Appalachian

National Scenic Trail (“ANST”).

For the reasons more fully explained below, we

conclude that the Forest Service’s decisions violate the

NFMA and NEPA, and that the Forest Service lacked

statutory authority pursuant to the MLA to grant a

pipeline right of way across the ANST. Accordingly,

we grant the petition for review of the Forest Service’s

SUP and ROD, vacate those decisions, and remand to

the Forest Service for further proceedings consistent

with this opinion.

I.

A.

Background

The ACP is a proposed 604.5 mile, 42-inch

diameter natural gas pipeline that would stretch from

West Virginia to North Carolina. The ACP route

approved by the Federal Energy Regulatory

Commission (“FERC”)—and for which the Forest

Service issued the SUP, ROD, and right of way

App-3

challenged in this case—crosses 21 miles of national

forest land (about 16 miles in the GWNF and five

miles in the MNF) and crosses the ANST in the

GWNF. Construction would involve clearing trees and

other vegetation from a 125-foot right of way (reduced

to 75 feet in wetlands) through the national forests,

digging a trench to bury the pipeline, and blasting and

flattening ridgelines in mountainous terrains.

Following construction, the project requires

maintaining a 50-foot right of way (reduced to 30 feet

in wetlands) through the GWNF and MNF for the life

of the pipeline.

Pursuant to NEPA, when a federal agency

proposes to take a “major Federal action[] significantly

affecting the quality of the human environment,” the

agency must prepare a detailed environmental impact

statement (“EIS”) describing the likely environmental

effects, “adverse environmental effects which cannot

be avoided,” and potential alternatives to the proposal.

42 U.S.C. § 4332(C). On April 27, 2015, the Forest

Service provided scoping comments on FERC’s Notice

of Intent to prepare an EIS for the ACP project. The

scoping comments stated, among other concerns, that

the EIS must analyze alternative routes that do not

cross national forest land, and that the EIS must

address the Forest Service’s policy that restricts

special uses on national forest lands to those that

“cannot reasonably be accommodated on non-National

Forest System lands.” J.A. 3593; 1 see also Forest Serv.

Manual, Addendum to Pet’rs’ Br. 65-66. The Forest

Service’s comments further identified concerns about

1 Citations to the “J.A.” refer to the Corrected Deferred Joint

Appendix filed by the parties in this appeal.

App-4

landslides, slope failures, sedimentation, and impacts

to groundwater, soils, and threatened and endangered

species that it believed would result from the ACP

project.

On September 18, 2015, Atlantic filed its formal

application with FERC to construct, own, and operate

the pipeline. On November 12, 2015, Atlantic applied

for the SUP from the Forest Service to construct and

operate the pipeline across the MNF and GWNF. This

application was amended in June 2016.

B.

Review and Comment

As FERC prepared the EIS, the Forest Service

reviewed and commented on draft environmental

resource reports, construction designs, biologic

evaluations, and the first draft of Atlantic’s

Construction, Operation, and Maintenance (“COM”)

Plan filed with FERC. Additionally, in a letter to

Atlantic dated October 24, 2016, the Forest Service

requested ten site-specific stabilization designs for

selected areas of challenging terrain to demonstrate

the effectiveness of Atlantic’s proposed steep slope

stability program, which Atlantic called the “Best in

Class” (“BIC”) Steep Slopes Program. As the Forest

Service explained:

Both the [GWNF and MNF] contain Forest

Plan standards that limit activities in areas

that are at high risk for slope and soil

instability. To facilitate the acceptance of

ACP’s [SUP] application for further

processing, the Forests need to be able to

determine that the project is consistent or can

App-5

be made consistent with this Forest Plan

direction.

J.A. 3379. The letter further noted that the ten

selected sites were “merely representative sites that

have been selected to demonstrate whether stability

can be maintained for the purpose of making a

preliminary determination of Forest Plan consistency.

Should the ACP Project be permitted, multiple

additional high hazard areas will need to be addressed

on a site-specific basis.” Id.

In a meeting between Atlantic and the Forest

Service on November 21, 2016, Atlantic presented the

first two of these site-specific stabilization designs

(identified as MNF01 and GWNF02 in the October 24,

2016 letter). According to the meeting notes, the MNF

Forest Supervisor noted:

[W]hile the BIC program [Atlantic] is

proposing is laudable [the MNF Forest

Supervisor] is skeptical the techniques will

work; the Forest Service has seen slope

failures on lesser slopes and would be able to

provide examples. [Atlantic] needs to be able

to demonstrate that the techniques will work

in extreme conditions. . . . The [Forest

Service] wants to know beforehand that these

examples have a reasonable chance of

working.

J.A. 3319. Additionally, the Forest Service observed

that the MNF01 and GWNF02 “drawings are a step in

the right direction but more detail is needed for site

specific design, the Forest Service needs to see how

this lays out on the land.” Id. at 3320.

App-6

Thereafter, beginning in December 2016, Atlantic

circulated a timeline of “FERC and Forest Service

Reviews” to the Forest Service, which set the following

deadlines for the agency’s decisions (as proposed by

Atlantic): (1) FERC’s Draft Environmental Impact

Statement (“DEIS”) to be issued in December 2016; (2)

FERC’s Final Environmental Impact Statement

(“FEIS”) to be issued in June 2017; (3) the Forest

Service’s draft ROD to be issued also in June 2017; (4)

a “Federal Agency Decision Deadline” of September

2017 (for issuance of the FERC Certificate of

Convenience and Public Necessity and the Forest

Service’s SUP and ROD); (5) Forest Plan amendments

completed in October 2017; and (6) the pipeline in

service by 2019. See J.A. 3252-53.

In line with Atlantic’s deadlines for the agencies’

decisions, FERC issued the DEIS on December 30,

2016. Regarding its analysis of alternative routes, the

DEIS explicitly stated that the ACP was routed on

national forest lands in order to avoid the need for

congressional approval for the pipeline to cross the

ANST:

A significant factor in siting ACP was the

location at which the pipeline would cross the

ANST. In the general project area, the ANST

is located on lands managed by either the

[National Park Service (“NPS”)] or [the

Forest Service]. The NPS has indicated that

it does not have the authority to authorize a

pipeline crossing of the ANST on its lands.

Instead, legislation proposed by Congress and

signed into law by the President would be

necessary to allow the NPS the authority to

App-7

review, analyze, and approve a pipeline

crossing of the ANST on its lands. Because of

this legislative process, Atlantic considered

locations where the ANST was located on

lands acquired and administered by the

[Forest

Service],

which

significantly

constrained the pipeline route and severely

limits opportunities for avoiding and/or

minimizing the use of [National Forest

System] lands.

J.A. 3207-08 (emphasis supplied). Regarding the

environmental impact on forest resources, the DEIS

further stated:

[W]e acknowledge that a shorter pipeline

route could conceptually have significantly

greater qualitative impacts to sensitive

resources than a longer route, which could

make the longer route preferable. In this

instance, we have not identified or received

any information that suggests the shorter

pipeline route through the National Forests

has significantly greater impacts to sensitive

resources than the alternative, but

acknowledge that ground resource surveys

have not been conducted.

Id. at 3208 (emphasis supplied).

On February 17, 2017, Atlantic and the Forest

Service met again to discuss the ten requested sitespecific stabilization designs. During this meeting,

Atlantic informed the Forest Service that the two

earlier site designs were for demonstration purposes,

and the remaining eight sites were not currently being

designed. The Forest Service stated that it was “not

App-8

comfortable” with not seeing the remaining designs,

and that it was the Forest Service’s understanding

that specific designs for all ten sites were still needed.

J.A. 2939. Significantly, the Forest Service stated, it

“want[ed] to see actual information, including specs on

the actual controls and protocol on how they will be

installed, not conceptual drawings.” Id.

On April 6, 2017, the Forest Service provided

comments on FERC’s DEIS. In multiple places, the

Forest Service’s comments stated that FERC’s

conclusions in the DEIS were premature given the

incomplete information used to make them—this was

particularly the case regarding the extent of impacts

to national forest resources and the effectiveness of

mitigation techniques. See, e.g., J.A. 2444 (“This

statement [in the DEIS] acknowledges deficiencies in

information needed to conduct an appropriate effects

analysis for at least some sensitive species. Given this,

the [Forest Service] has serious reservations about the

conclusions of the analyses up to this point because

those conclusions have been reached prior to acquiring

the necessary information to substantiate what must

otherwise be presumed to represent judgments based

on incomplete information.”); id. at 2445 (“There will

be irreversible impacts to the soil and vegetation

resources from construction of the ACP pipeline on

[National Forest System] lands. No matter how

[Atlantic] plans to implement measures to reduce

these impacts, there will still be an unavoidable

irreversible dedication of the soil resource as defined

by NEPA . . . . The [COM] Plan is currently not

complete, and substantial work remains to develop

and refine measures to avoid, minimize, and mitigate

impacts to a variety of resources on [National Forest

App-9

System] lands, including steep slopes/sensitive soils;

threatened, endangered, and sensitive species; and

management indicator species.”).

Further, regarding the DEIS’s analysis of nonnational forest alternative routes, the Forest Service

commented:

No analysis of a National Forest Avoidance

Alternative has been conducted, and

environmental impacts of this alternative

have not been considered or compared to the

proposed action. Therefore, the Forest Service

cannot support the recommendation that the

National Forest Avoidance Alternative be

dropped from consideration. In our scoping

comments, we requested that all alternatives,

including a National Forest Avoidance

Alternative, be fully addressed in regard to

their feasibility and environmental effects. We

hereby reiterate that request.

J.A. 2454 (emphasis supplied).

The Forest Service’s comments on Atlantic’s draft

biologic evaluation, issued on April 24, 2017, paint a

similarly grim picture of the ACP project’s effects on

erosion and on threatened and endangered species.

For example, Atlantic’s draft biologic evaluation

contained the following statement: “Construction

activities may displace certain sensitive species from

within and areas adjacent to the right-of-way, but the

impact is expected to be short-term and limited to the

period of construction. After construction, Atlantic will

restore the right-of-way as near as practicable to

preconstruction contours and conditions . . . .” J.A.

2324. In response, the Forest Service stated:

App-10

Restoration will consist of erosion control,

some NNIS [non-native invasive species]

control, and some native plant reintroduction, so it will create habitat of some

sort, but the impact to sensitive species should

be expected to be long-term. Restoration

plantings will take many years to establish

and flourish, will in most cases consist of

different species than were present before,

and will in many cases not re-create the

conditions sensitive species need to survive.

NNIS introductions, given the current lack of

plans to conduct treatment along access

roads, likely will create long-term negative

impacts to the ecosystem, including

potentially to sensitive species.

Id. (emphasis supplied).

Additionally, in response to a statement in the

draft biologic evaluation that the loss of potential

roosting habitat for the little brown bat (caused by

construction of the pipeline and the resulting

permanent right of way) would be “offset,” since the

species could use the right of way as foraging habitat,

the Forest Service stated:

A potential increase in foraging habitat

(which is not really proven here) does not

offset the long-term loss of good roosting

habitat—they apply to different life history

needs and an increase in one does not offset

loss of the other. Also, the loss of forested

habitat would be a long-term impact given

the time period required for recovery.

App-11

J.A. 2333. The Forest Service further noted, “Bats

utilizing the more open areas (such as the [right of

way] and road corridors) for foraging are also more

vulnerable to predators. This offset is counteracted by

an increase in potential predation, which negates the

[right of way] and roads as potentially beneficial to the

bat.” Id. at 2332.

C.

Change of Course

Despite the Forest Service’s clearly stated

concerns regarding the adverse impacts of the ACP

project, as Atlantic’s deadlines for the agency’s

decisions drew closer, its tenor began to change. On

May 14, 2017, the Forest Service sent a letter to FERC

and Atlantic in which it stated—for the first time—

that it would not require the remaining eight sitespecific stabilization designs before authorizing the

project. Specifically, the letter stated: “If the ACP

project is authorized, the site-specific designs for the

remaining eight sites identified in our October 24,

2016 letter must be reviewed and approved by the

[Forest Service] before construction at those locations

could begin.” J.A. 2307. The letter did not acknowledge

that the agency was changing its position from its

original request for all ten site designs prior to

granting approval for the ACP nor did it provide any

further explanation regarding the reason for the

Forest Service’s change in position. On July 5, 2017,

the Forest Service sent a letter to Atlantic

“acknowledg[ing]”

that

the

two

site-specific

stabilization designs that had so far been provided

(MNF01 and GWNF02) and the subsequent

information about those sites provided by Atlantic

App-12

“w[ere] adequate for the purposes of disclosing the

environmental effects” associated with the ACP

project. Id. at 1881. The letter did not provide any

explanation as to why the two plans were “adequate.”

On July 21, 2017, FERC released the FEIS. On

the very same day, and in line with Atlantic’s timeline,

the Forest Service released its draft ROD proposing to

adopt the FEIS, grant the SUP, and exempt Atlantic

from several forest plan standards. The FEIS’s

“National Forest Avoidance Route Alternatives”

section, which the Forest Service commented on

previously (as explained above), is identical to the

DEIS. Regarding the alternatives analysis, the Forest

Service’s draft ROD states: “FERC’s evaluation

concluded that the major pipeline route alternatives

and variations do not offer a significant environmental

advantage when compared to the proposed route or

would not be economically practical.” Id. at 1411.

Regarding the COM Plan, on October 6, 2017, the

Forest Service sent a letter to Atlantic stating that

Atlantic’s June 30 responses to the Forest Service’s

second draft COM Plan comments “largely addressed

our comments except for a limited number of items

needing further explanation or clarification.” J.A. 847.

The letter requested an updated COM Plan

incorporating these responses. Atlantic filed this third

(and final) draft of the COM Plan on October 27, 2017.

FERC issued the Certificate of Convenience and

Public Necessity to ACP for construction of the

pipeline on October 13, 2017.

Shortly after, on October 27, 2017, the Forest

Service filed its responses to objections to the draft

ROD. In response to an objection regarding the range

App-13

of non-national forest route alternatives, the Forest

Service stated that FERC “adequate[ly] consider[ed]

the route across the National Forests” and “concluded

these alternatives would not provide a significant

environmental advantage over a shorter route that

passes through National Forests.” J.A. 676.

On November 16, 2017, the Forest Service sent a

letter to Atlantic regarding Atlantic’s updated biologic

evaluation, which had been filed on August 4, 2017.

That biologic evaluation stated that the ACP project

was likely to result in a “loss of viability” for three

Regional Forester Sensitive Species (“RFSS”) in the

MNF, a conclusion which, we note, was in line with

the Forest Service’s April 24, 2017 comments on the

draft biologic evaluation. Nonetheless, in an aboutface, the Forest Service’s letter amended the updated

biologic evaluation to conclude that, in fact, the project

was not likely to result in a loss of viability to the three

RFSS. This conclusion is significant, because the

Forest Service cannot authorize uses of national

forests that are likely to result in a loss of viability for

a species. See J.A. 64 (“Per [Forest Service Manual]

2670.32, activities or decisions on [National Forest

System] lands ‘must not result in a loss of species

viability or create significant trends towards federal

listing.’”). However, as noted above, the Forest Service

had already issued its draft ROD proposing to

authorize the SUP before the updated biologic

evaluation was filed.

The Forest Service issued its final ROD on

November 17, 2017, and it issued the SUP and

granted the right of way across the ANST on January

23, 2018. Cowpasture River Preservation Association,

App-14

Highlanders

for

Responsible

Development,

Shenandoah

Valley

Battlefields

Foundation,

Shenandoah Valley Network, Sierra Club, Virginia

Wilderness Committee, and Wild Virginia, Inc.

(collectively, “Petitioners”) filed this challenge on

February 5, 2018. We possess jurisdiction pursuant to

the Administrative Procedure Act (“APA”), 5 U.S.C.

§§ 701-06, and the Natural Gas Act, 15 U.S.C.

§ 717r(d)(1).

II.

We may “‘hold unlawful and set aside [a federal]

agency action’ for certain specified reasons, including

whenever the challenged act is ‘arbitrary, capricious,

an abuse of discretion, or otherwise not in accordance

with the law.’” Sierra Club, Inc. v. U.S. Forest Serv.,

897 F.3d 582, 589-90 (4th Cir. 2018) (quoting 5 U.S.C.

§ 706(2)(A)). An agency’s decision is arbitrary and

capricious if:

the agency relied on factors which Congress

has not intended it to consider, entirely failed

to consider an important aspect of the

problem, offered an explanation for its

decision that runs counter to the evidence

before the agency, or is so implausible that it

could not be ascribed to a difference in view

or the product of agency expertise.

Id. at 590 (quoting Defs. of Wildlife v. N.C. Dep’t of

Transp., 762 F.3d 374, 396 (4th Cir. 2014)).

III.

Petitioners assert that the Forest Service violated

three federal Acts in issuing the ROD and SUP: the

App-15

NFMA, NEPA, and the MLA. We address each of these

Acts and alleged violations in turn.

A.

National Forest Management Act

The NFMA sets forth substantive and procedural

standards that govern the management of national

forests. See 16 U.S.C. § 1604. As this court recently

explained in Sierra Club v. Forest Service, the NFMA

establishes a procedure for managing National Forest

System lands using “Forest Plans,” which “provide a

framework for where and how certain activities can

occur in national forests.” Sierra Club, Inc. v. U.S.

Forest Serv., 897 F.3d 582, 600 (4th Cir. 2018) (quoting

Am. Wild Horse Pres. Campaign v. Perdue, 873 F.3d

914, 919 (D.C. Cir. 2017); 16 U.S.C. § 1604(a)). First,

the NFMA directs the Forest Service to “develop,

maintain, and, as appropriate, revise” Forest Plans;

second, it directs the Forest Service to ensure that all

activities on national forest lands—specifically, all

“resource plans and permits, contracts, and other

instruments for the use and occupancy of National

Forest System lands”—are consistent with the Forest

Plans. Id. (quoting Perdue, 873 F.3d at 919; 16 U.S.C.

§ 1604(i)).

The NFMA also charges the Department of

Agriculture (through the Forest Service, see 36 C.F.R.

§ 200.3(b)) with “promulgating guidelines for Forest

Plans, which should, inter alia, ‘insure consideration

of the economic and environmental aspects of various

systems of renewable resource management’ and

‘provide for diversity of plant and animal communities

based on the suitability and capability of the specific

land area.’” Sierra Club, 897 F.3d at 600 (quoting 16

App-16

U.S.C. § 1604(g)(3)(A)-(B)). At issue in this case are

two Forest Service regulations issued pursuant to this

authority: the 2012 Planning Rule and the 2016

Amendment to the 2012 Planning Rule, both of which

deal with amendments to Forest Plans.

Petitioners assert that the Forest Service violated

the NFMA by: (1) determining that amendments to

the GWNF and MNF Plans’ standards to

accommodate the ACP were not “directly related” to

the 2012 Forest Planning Rule’s (“2012 Planning

Rule’s”) substantive requirements; (2) failing to meet

public participation requirements in amending forest

plans; and (3) failing to analyze whether the ACP

project’s needs could be reasonably met off of national

forest land.

1.

2012 Planning Rule

Petitioners assert that the Forest Service violated

the NFMA by failing to apply the substantive

requirements of the 2012 Planning Rule to the

amendments of the GNF and MNF Plans’ standards.

Specifically, Petitioners assert that the amendments

are directly related to the substantive requirements

both in their purpose and their effects.

a.

Background

In 2012, the Forest Service updated its Forest

Planning Rule, which superseded the 1982 rule and

set forth new, substantive requirements for Forest

Plans. See 2012 Planning Rule, 77 Fed. Reg. 21,162

(U.S. Dep’t of Agric. Apr. 9, 2012). The updated

substantive requirements in the 2012 Planning Rule

App-17

apply to Forest Plans developed under the 1982 rule

in certain circumstances. See 36 C.F.R. §§ 219.8219.11; Sierra Club, 897 F.3d at 600-01. Specifically,

as the 2016 Amendment to the 2012 Planning Rule

clarified, a substantive requirement from the 2012

Planning Rule applies to a Forest Plan amendment if

that requirement is “directly related to the plan

direction being added, modified, or removed by the

amendment.” Sierra Club, 897 F.3d at 601 (quoting 36

C.F.R. § 219.13(b)(5) (emphasis supplied in Sierra

Club)).

If the substantive requirement is directly related

to the amendment, then the responsible official must

“apply such requirement(s) within the scope and scale

of the amendment.” Sierra Club, 897 F.3d at 601

(quoting 36 C.F.R. § 219.13(b)(5)). Conversely, if the

substantive requirement from the 2012 Planning Rule

is not directly related to the amendment, the

responsible official is not required to apply it to the

amended Forest Plan. See id. Thus, Petitioners’

arguments on this point turn on whether the

requirements in the 2012 Planning Rule are directly

related to the Forest Service’s amendments to the

GWNF and MNF Plans.

A substantive requirement is directly related to

the amendment when the requirement “is associated

with either the purpose for the amendment or the

effects (beneficial or adverse) of the amendment.”

Sierra Club, 897 F.3d at 602 (quoting 2016

Amendment to 2012 Rule, 81 Fed. Reg. 90,723, 90,731

(U.S. Dep’t of Agric. Dec. 15, 2016)); see also 36 C.F.R.

§

219.13(b)(5)(i)

(“The

responsible

official’s

determination must be based on the purpose for the

App-18

amendment and the effects (beneficial or adverse) of

the amendment, and informed by the best available

scientific information, scoping, effects analysis,

monitoring data or other rationale.”). Further,

regarding the adverse effects of an amendment, “[t]he

responsible official must determine that a specific

substantive requirement is directly related to the

amendment when scoping or NEPA effects analysis

for the proposed amendment reveals substantial

adverse effects associated with that requirement, or

when the proposed amendment would substantially

lessen protections for a specific resource or use.” 36

C.F.R. § 219.13(b)(5)(ii).

b.

GWNF and MNF Plan Amendments:

Purpose Analysis

In its ROD, the Forest Service decided to apply

project-specific amendments to a total of 13 standards

in the GWNF and MNF Plans for the purpose of

construction and operation of the ACP. The

amendments exempt the ACP project from four MNF

Plan standards and nine GWNF Plan standards that

relate to soil, water, riparian, threatened and

endangered species, and recreational and visual

resources.

Petitioners assert that the Forest Service violated

the NFMA and the 2012 Planning Rule because it

skipped the “purpose” prong of the “directly related”

analysis. Consistent with our decision in Sierra Club,

we conclude that Petitioners are correct. 2 Although

2 Faced with a nearly identical situation in Sierra Club v.

Forest Service, we concluded that the Forest Service acted

App-19

the ROD states the rule correctly, see J.A. 36

(“[W]hether a planning regulation requirement is

directly related to an amendment is based upon the

amendment’s purpose or its effect (beneficial or

adverse).”), it fails to analyze the purpose of the

amendments and instead moves directly to analyzing

the amendments’ effects, see id. at 36-48. This

omission is particularly striking because the Forest

Service specifically identified the purpose and need for

the amendments in the ROD:

The purpose of the amendments are [sic] to

meet the requirements of the NFMA and its

implementing regulations that projects

authorized on [National Forest System] lands

must be consistent with the LRMP. Without

the MNF and GWNF project-specific Forest

Plan amendments the ACP project would not

be consistent with some Forest Plan

standards related to soil, riparian, threatened

and endangered species, utility corridors, the

ANST, an Eligible Recreational River Area,

and scenic integrity objectives.

Id. at 31.

Indeed, this purpose and need is repeated several

times throughout the ROD. See, e.g., J.A. 27 (“The

project-specific amendments to MNF and GWNF

LRMP’s [sic] approved by this decision are needed to

arbitrarily and capriciously by failing to analyze the purpose of

the amendment in its ROD (and instead focusing on only the

effects) when “the clear purpose of the amendment [was] to lessen

requirements protecting soil and riparian resources so that the

pipeline project could meet those requirements.” Sierra Club, 897

F.3d at 603.

App-20

allow the ACP Project to be consistent with LRMP

standards.”); id. at 37 (“[T]he purpose of the plan

amendments is to ensure consistency of the ACP

Project with the provisions of the two Forest Plans.”).

There would be no need to amend the Forest Plans to

“ensure consistency” if the ACP project could meet the

Forest Plan standards in the first place. In other

words, the ROD makes clear that the purpose of the

amendments was to lessen certain environmental

requirements in the GWNF and MNF Plans because

the ACP project could not meet those Plans’ existing

requirements.

Accordingly, by failing to analyze whether the

substantive requirements of the 2012 Planning Rule

are directly related to the purpose of the amendments,

the Forest Service “entirely failed to consider an

important aspect of the problem.” Defs. of Wildlife v.

N.C. Dep’t of Transp., 762 F.3d 374, 396 (4th Cir. 2014)

(quoting Motor Vehicle Mnfs. Ass’n v. State Farm Mut.

Auto. Ins. Co., 463 U.S. 29, 43 (1983)). This failure is

significant, because it is clear that the amendments

(intended to lessen protections for soils, riparian

areas, and threatened and endangered species in the

GWNF and MNF Plans) are directly related to the

2012 Planning Rule’s substantive requirements for

these same categories: “soil and soil productivity” (36

C.F.R. § 219.8(a)(2)(ii)); “water resources” (id.

§ 219.8(a)(2)(iv)); “ecological integrity of riparian

areas” (id. § 219.8(a)(3)(i)); “ecological integrity of

terrestrial . . . ecosystems”

(id.

§ 219.8(a)(1));

“appropriate placement and sustainable management

of . . . utility corridors” (id. § 219.10(a)(3)); and

“recovery of federally listed . . . species” (id.

§ 219.9(b)).

App-21

c.

Ex Post Facto Statements of Purpose

Notwithstanding the Forest Service’s statements

of purpose and need in the ROD, in its briefing and at

oral argument the Forest Service attempted to

recharacterize the purpose of the amendments as “to

relax thirteen planning standards just enough to

‘authorize [Atlantic] to use and occupy [National

Forest System] lands for the [ACP] Project’ consistent

with the forest plans.” Resp’t’s Br. 18. Meanwhile,

Atlantic asserts that the Forest Service did “explicitly

evaluate[] the purpose of the proposed amendments”

and determined that “the purpose of ACP is not

directly related to any of [the 2012 Planning Rule’s]

management guidelines.” Intervenor’s Br. 25. Instead,

according to Atlantic, “the purpose of ACP is to ‘serve

the growing energy needs of multiple public utilities

and local distribution companies, and Virginia and

North Carolina’ and the ‘purpose and need’ of the

‘proposed action’ is to ‘respond to Atlantic’s application

for a special use permit.’” Id. (quoting J.A. 10, 37).

Quite the contrary—the ROD does not analyze

whether the amendments’ purpose is directly related

to the 2012 Planning Rule’s substantive requirements.

Rather, the ROD lists the purpose and need of the

amendments but analyzes only the amendments’

effects. See J.A. 36-48. The Forest Service’s and

Atlantic’s attempts to recharacterize the purpose of

the amendments (despite the clear statements of the

amendments’ purpose in the ROD) are without merit.

First, the Forest Service asserts that the true

purpose of the amendments was just to authorize the

ACP project—not to lessen environmental protections

App-22

for certain resources—and that “not every amendment

with an effect on a particular resource has the purpose

of adjusting the forest plan’s direction for that

resource.” Resp’t’s Br. 18-19 (emphasis in original).

But this contradicts the Forest Service’s own

description of the amendments’ purpose in both the

ROD and in its brief, which begins with the phrase “to

relax thirteen planning standards.” Id. at 18.

Relaxing, lessening, loosening—regardless of the

Forest Service’s verb preference, the purpose of the

Forest Plan amendments is to reduce the Plans’

environmental protections for certain resources.

Further, this is not a situation where a proposed

project-specific amendment may have an incidental

effect on a Forest Plan standard; rather, the

amendments’ entire purpose is to weaken existing

environmental standards in order to accommodate the

ACP, which cannot meet the current standards. To say

that a 2012 Planning Rule requirement protecting

water resources (as one example) is not “directly

related” to a Forest Plan amendment specifically

relaxing protection for water resources is nonsense.

Meanwhile, Atlantic conflates the purpose of the

amendments to the Forest Plans with, first, the overall

purpose of the ACP project (to “serve the growing

energy needs of multiple public utilities and local

distribution companies, and Virginia and North

Carolina,” Intervenor’s Br. 25), and second, the Forest

Service’s reason for taking action at all (to “respond to

Atlantic’s application for a special use permit,” id.).

Both interpretations of “purpose” are facially incorrect

applications of the 2012 Planning Rule’s “directly

related” analysis, and neither address the Forest

App-23

Service’s purpose for amending the GWNF and MNF

Plans. First, the purpose of the plan amendment, not

the ACP project, is the focus of this analysis. Second,

the Forest Service’s need to respond to Atlantic’s

application for the SUP is overly broad and does not

address the need for amending the Forest Plans—

clearly, the Forest Service could have “responded” to

Atlantic’s application without the amendments.

Finally, both the Forest Service and Atlantic

suggest that only amendments changing a

management standard for the forest as a whole—and

not project-specific amendments—can trigger the

substantive requirements of the 2012 Planning Rule.

See Resp’t’s Br. 18-20 (“A substantive requirement is

directly related to the purpose for an amendment

when the amendment’s objective is to adjust the

management of the corresponding forest resource.”);

Intervenor’s Br. 26 (“[T]he proposed amendments for

ACP did not change any of the generally applicable

standards or guidelines in the forest plans.”). Neither

party offers authority to support this assertion, which

is contrary to the purpose of the 2012 Planning Rule:

to promote consistency in the protections for national

forest resources across Forest Plans. See 2012

Planning Rule, 77 Fed. Reg. at 21,162. If the Forest

Service could circumvent the requirements of the 2012

Planning Rule simply by passing project-specific

amendments on an ad hoc basis, both the substantive

requirements in the 2012 Planning Rule and the

NFMA’s Forest Plan consistency requirement would

be meaningless.

Accordingly, in line with our decision in Sierra

Club v. Forest Service, we conclude that the 2012

App-24

Planning Rule requirements for soil, riparian

resources, and threatened and endangered species are

directly related to the purpose of the Forest Plan

amendments. The Forest Service acted arbitrarily and

capriciously in concluding otherwise.

d.

Effects Analysis

Although we need not reach the “effects” prong of

the analysis in light of our conclusion that the purpose

of the amendments is directly related to the 2012

Planning Rule’s substantive requirements, the Forest

Service’s assertion that the Plan amendments will not

have substantial adverse effects warrants additional

discussion.

As noted above, a substantive requirement is

directly related to a Forest Plan amendment when the

requirement “is associated with . . . the effects

(beneficial or adverse) of the amendment.” Sierra

Club, 897 F.3d at 602 (quoting 2016 Amendment to

2012 Rule, 81 Fed. Reg. at 90,731); see also 36 C.F.R.

§ 219.13(b)(5)(i). The Forest Service asserts that an

adverse effect must be “substantial” in order to be

directly related to a substantive provision in the 2012

Planning Rule. 3 When asked at oral argument how the

It is not necessary for us to determine whether this

characterization of the regulations is accurate because, for the

reasons explained below, we conclude that the Forest Service’s

determination that the amendments will not have substantial

adverse effects was arbitrary and capricious. Nevertheless, we

note that the regulation at issue—36 C.F.R. § 219.13—does not

define “adverse effects” as including only substantial effects;

rather, it says that the applicable substantive requirement from

the 2012 Planning Rule must apply when the effects are

3

App-25

Forest Service defines “substantial adverse effects,”

counsel for the Forest Service responded:

COUNSEL: [T]he best guidance for that issue

can be found in the preamble to the 2012

[Planning] Rule where the Forest Service

says that rarely, if ever, will a project-specific

amendment rise to the level of having a

substantial adverse effect on these resources.

...

COURT: How can that be, rarely if ever will

something rise to have a substantial adverse

effect on the forest? How many trees do you

cut down before it is a substantial adverse

effect? Maybe not one. All of them?

COUNSEL: The way the Forest Service

stated it in the 2012 preamble to [the

Planning] Rule was that it was going to look

at the impact of the resource over the entire

forest.

Oral Argument at 22:55-24:04, Cowpasture River

Preservation Ass’n v. Forest Serv., No. 18-1144 (4th

Cir. Sept. 28, 2018), http://www.ca4.uscourts.gov/oralsubstantial. See 36 C.F.R. § 219.13(b)(5)(ii). Curiously, there is

no corresponding guidance for beneficial effects. In other words,

under the Forest Service’s interpretation of the regulation, only

“substantial” adverse effects could trigger application of a

substantive requirement, but any beneficial effect at all would

trigger the same substantive requirement. The Forest Service

does not explain why the regulations would intend to make it

easier to pass amendments that harm the environment (by not

requiring application of the substantive requirements, which aim

to protect the environment, unless that harm is substantial) but

more difficult to pass amendments that benefit the environment.

App-26

argument/listen-to-oral-arguments (hereinafter “Oral

Argument”).

It is nothing short of remarkable that the Forest

Service—the federal agency tasked with maintaining

and preserving the nation’s forest land—takes the

position that as a bright-line rule, a project-specific

amendment, no matter how large, will rarely, if ever,

cause a substantial adverse effect on a national forest.

And it is even more remarkable that the agency is

unable to say what would constitute a substantial

adverse effect on the forest.

Indeed, counsel’s response did not answer the

court’s question, and the Forest Service has never

explained (in its briefing nor at argument) what

makes an adverse effect “substantial.” Even more

telling, however, is that the “rarely, if ever” language

used by counsel is nowhere to be found in the preamble

to the 2012 Planning Rule, nor in any other Forest

Service guidance that the court could find. The closest

language to counsel’s assertion that the court could

identify is in the preamble to the 2016 Amendment to

the 2012 Planning Rule, which states, “[i]t is unlikely

that a change in land allocation for a small area would

have substantial adverse effects.” 2016 Amendment to

2012 Rule, 81 Fed. Reg. at 90,728. This language was

a response by the Forest Service to a public comment

which was concerned that the proposed rule (the 2016

Amendment) might impose a burden on small changes

to land allocation. The Forest Service’s full response

was as follows:

The 2012 rule did not require that every

resource or use be present in every area. The

Department clarifies in this final rule that

App-27

directly

related

specific

substantive

requirements within §§ 219.8 through 219.11

apply within the scope and scale of the

amendment. Changes in land allocation for a

small area would likely require a similarly

narrow application of the directly related

substantive requirements, depending on the

purpose and effects of the changes. It is

unlikely that a change in land allocation for a

small area would have substantial adverse

effects.

Id.

Even assuming that this language from the 2016

Amendment’s preamble is what counsel was referring

to during argument, it still does not provide any

support for the Forest Service’s interpretation of

“substantial adverse effects.” A “change in land

allocation for a small area” is plainly not the same as

generalizing to any project-specific amendment, and

“unlikely” is a far cry from “rarely, if ever.” Perhaps

this is why counsel struggled to define what “rarely, if

ever” would mean in this context.

Thus, we find no basis in the law for the Forest

Service’s assertion that “rarely, if ever, will a projectspecific amendment rise to the level of having a

substantial adverse effect” on the natural forests.

In any event, the Forest Service’s application of

the “effects” prong of the directly related test was still

flawed. In each instance in the ROD where the Forest

Service concluded that the 2012 Planning Rule’s

substantive requirements were not “directly related”

to the Plan amendments, the ROD states that the

amendment “will not cause substantial long-term

App-28

adverse effects.” J.A. 39, 41, 43 (emphasis supplied).

But nowhere do the regulations (nor does the ROD,

nor does the Forest Service’s brief) state that a

substantial adverse effect must be long term for the

substantive requirement in the 2012 Planning Rule to

be “directly related” to the amendment.

The Forest Service’s strained and implausible

interpretations of “substantial adverse effects” are

especially striking in light of the significant evidence

in the record that the GWNF and MNF Plan

amendments would cause substantial adverse effects

on the forests. See, e.g., J.A. 25 (“Sedimentation

modeling indicates annual soil loss will be 200 to 800

percent above baseline erosion during the first year of

construction, returning to pre-construction levels

within 5 years following restoration”); id. at 2320

(“Full recovery of forested sites would take many

decades.”); id. at 2351 (“It is unsubstantiated as to

how [erosion] increases of that magnitude are

considered moderate and impacts will be temporary

and minimal.”).

The lengths to which the Forest Service

apparently went to avoid applying the substantive

protections of the 2012 Planning Rule—its own

regulation intended to protect national forests—in

order to accommodate the ACP project through

national forest land on Atlantic’s timeline are striking,

and inexplicable.

Accordingly, we conclude that the Forest Service’s

determination that the GWNF and MNF Plan

amendments would not have substantial adverse

effects on the forests was arbitrary and capricious.

App-29

e.

Remand to the Forest Service

Because the 2012 Planning Rule requirements for

soil, riparian resources, and threatened and

endangered species are directly related to the purpose

and effect of the GWNF and MNF Forest Plan

amendments, the Forest Service must “apply [those]

requirement[s] within the scope and scale of the

amendment.” Sierra Club, 897 F.3d at 603 (quoting 36

C.F.R. § 219.13(b)(5) (alterations in Sierra Club)).

Accordingly, we remand to the Forest Service for

proper application of the Planning Rule requirements

for soil, riparian resources, and threatened and

endangered species to the Forest Plan amendments.

The Forest Service contends that remand is

unnecessary because the Plan amendments already

meet the substantive requirements of the 2012

Planning Rule. Thus, the Forest Service asserts, any

error in applying the 2012 Planning Rule was

harmless. We find no basis to support such a

conclusion. In fact, the ROD suggests just the opposite

is true: in its analysis of the amendments’ compliance

with the 2012 Planning Rule’s substantive

requirements, the Forest Service explicitly stated

when an amendment met the applicable substantive

requirement. For example, regarding the GWNF Plan

amendment for utility corridors, the ROD states:

The FEIS evaluated a variety of options to

transport natural gas and adequately

analyzed the appropriate placement and

sustainable management of the ACP.

Consequently, I find this amendment meets

the 36 CFR 219.10(a)(3) planning rule

App-30

requirement. Since the amendment meets the

rule requirement, there is no need to make a

further determination as to whether the rule

requirement is directly related to it.

J.A. 41-42 (emphasis supplied); see also id. at 44, 46,

47, 48 (similarly concluding that the Plan

amendments for the ANST, scenic integrity objectives,

road reconstruction, and management of old growth,

respectively, meet the 2012 Planning Rule’s

substantive requirements and thus “there is no need”

to determine whether the substantive requirement is

directly related to the amendment).

Yet, tellingly, the Forest Service specifically did

not conclude that the GWNF and MNF Plan

amendments for soils, riparian areas, and threatened

and endangered species met the applicable 2012

Planning Rule’s substantive requirement. Instead, it

concluded (incorrectly) that in each case, the

substantive requirements were not directly related to

the applicable Plan amendment. According to the

ROD, conducting the directly related analysis would

have been unnecessary if the amendment in fact

satisfied the substantive requirement: where “the

amendment meets the rule requirement, there is no

need to make a further determination as to whether the

rule requirement is directly related to it.” J.A. 41-42

(emphasis supplied)). Accordingly, the case must be

remanded.

2.

Public Participation Requirements

Petitioners further assert that the Forest Service

violated the NFMA because it provided no opportunity

for public comment for four of the amended forest plan

App-31

standards. Even assuming Petitioners are correct (a

point the Forest Service disputes), Petitioners do not

attempt to demonstrate “that the outcome of the

process would have differed in the slightest had notice

been at its meticulous best.” Friends of Iwo Jima v.

Nat’l Capital Planning Comm’n, 176 F.3d 768, 774

(4th Cir. 1999). Without even an allegation of

prejudice, Petitioners fail to carry their burden to

prove that any notice-related deficiency was

prejudicial. Accordingly, we reject this argument.

3.

Accommodation of the ACP Project on

Non-National Forest Land

Petitioners assert that the Forest Service violated

NEPA by failing to consider alternatives that avoid

national forest land. Relatedly, Petitioners argue that

the Forest Service violated the GWNF and MNF Plans

and the NFMA because it failed to demonstrate that

the ACP project’s needs could not be reasonably met

on non-national forest lands.

The

GWNF

Plan limits “Special Use

Authorizations” to “needs that cannot be reasonably

met on non-[National Forest System] lands or that

enhance programs and activities.” J.A. 4068

(emphasis supplied). Similarly, an MNF Plan goal

states: “[p]roposed special uses of [National Forest

System] lands . . . are considered that meet public

needs, are consistent with direction for other Forest

resources and management prescriptions, and cannot

be accommodated off the National Forest.” J.A. 4069

(emphasis supplied). Finally, the Forest Service’s

regulations state: “[a]n authorized officer shall reject

any proposal . . . if, upon further consideration, the

App-32

officer determines that: . . . the proposed use would

not be in the public interest.” 36 C.F.R.

§ 251.54(e)(5)(ii). The Forest Service Manual provides

further guidance on § 251.54(e)(5)(ii), directing that a

proposed use should be authorized as “in the public

interest” “only if . . . the proposed use cannot

reasonably be accommodated off of National Forest

System lands.” Forest Serv. Manual, Addendum to

Pet’rs’ Br. 65-66 (emphasis supplied). The Forest

Service Manual further directs, “[d]o not authorize the

use of National Forest System lands solely because it

affords the applicant a lower cost or less restrictive

location.” Id. at 66.

We agree that the Forest Service violated its

obligations under the NFMA and its own Forest Plans

because it failed to demonstrate that the ACP project’s

needs could not be reasonably met on non-national

forest lands. The Forest Service’s ROD adopted and

incorporated FERC’s alternative routes analysis in

the EIS, but the EIS applied a different standard than

the one imposed on the Forest Service by the NFMA

and its own Forest Plans. In the EIS, FERC considered

only whether a route alternative “confers a significant

environmental advantage over the proposed route.”

J.A. 1533. This is a significantly different standard

than whether the proposed use “cannot reasonably be

accommodated off of National Forest System lands.”

Forest Serv. Manual, Addendum to Pet’rs’ Br. 65-66

(emphasis supplied); cf. Sierra Club, 897 F.3d at 60405 (concluding that the Bureau of Land Management

violated its MLA obligations where it failed to analyze

whether

alternative

pipeline

routes

were

“impractical,” as required by the Bureau’s regulations,

and instead adopted an EIS that considered only

App-33

whether an alternative route offered a “significant

environmental advantage”).

Accordingly, adopting FERC’s EIS was not

sufficient for the Forest Service to fulfill its obligations

under the Forest Service Manual and its own Forest

Plans, and the Forest Service did not purport to

undertake this required analysis anywhere else in the

ROD.

The Forest Service asserts that it “determines

project consistency only ‘with respect to standards and

guidelines,’ not general forest planning ‘goals’ like

Monongahela LS17.” Resp’t’s Br. 24 (quoting 2012

Planning Rule, 77 Fed. Reg. at 21,241). As an initial

matter, the Forest Service regulations and the Forest

Service Manual apply to both the GWNF and the

MNF, so even if the court were to disregard the MNF

goal cited by Petitioners, the proposed use of national

forest land must still fit the Forest Service Manual’s

definition of “in the public use,” which contains

essentially the same requirement as the MNF goal:

that the proposed use cannot be reasonably

accommodated outside of the national forest. See

Forest Serv. Manual, Addendum to Pet’rs’ Br. 65-66.

However, the Forest Service’s assertion about

forest planning goals and objectives deserves

additional discussion. The regulatory guidance quoted

by the Forest Service—from the preamble to the 2012

Planning Rule, 77 Fed. Reg. at 21,241—is a response

by the Forest Service to a public comment regarding

the 2012 Planning Rule’s consistency requirement,

which states:

The Forest Service policy was that

consistency could only be determined with

App-34

respect to standards and guidelines, or just

standards, because an individual project

alone could almost never achieve objectives

and desired conditions. . . .

The Department continues to believe that the

consistency

requirement

cannot

be

interpreted to require achievement of the

desired conditions or objectives of a plan by

any single project or activity, but we believe

that we can provide direction for consistency

to move the plan area toward desired

conditions and objectives, or to not preclude

the eventual achievement of desired

conditions or objectives, as well as direction

for consistency with the other plan

components.

77 Fed. Reg. at 21,241 (emphasis supplied). In other

words, even if the Forest Service is not required to

conclude that an individual project alone meets a

forest planning goal, it is not free to disregard the goal

entirely—as the Forest Service apparently wishes to

do here.

The Forest Service was aware of its obligation to

determine that the ACP project could not be

reasonably accommodated on non-national forest land

from the beginning of the project. Indeed, the Forest

Service specifically cited to the Forest Service Manual

and Forest Plan requirements in its initial scoping

comments in response to FERC’s Notice of Intent to

Prepare an EIS. See J.A. 3593 (“[T]he analysis must

address Forest Service Manual direction that restricts

special uses to those that cannot reasonably be

accommodated on non-National Forest System lands

App-35

(FSM 2703.2).”); id. at 3593-94 (stating that the

GWNF Plan requires special use authorizations be

“[l]imit[ed] to needs that cannot be reasonably met on

non-[National Forest System] lands or that enhance

programs and activities”). The Forest Service’s failure

to undertake this analysis violated the NFMA.

Accordingly, we remand to the Forest Service for

proper analysis of whether the ACP project’s needs

can be reasonably met on non-national forest lands, in

compliance with the NFMA and the GWNF and MNF

Plans.

B.

National Environmental Policy Act

As this court recently explained in Sierra Club v.

Forest Service, Congress enacted NEPA “to reduce or

eliminate environmental damage.” 897 F.3d at 590

(quoting Dep’t of Transp. v. Pub. Citizen, 541 U.S. 752,

756 (2004)). “‘NEPA itself does not mandate particular

results in order to accomplish these ends,’ but rather,

‘imposes only procedural requirements on federal

agencies with a particular focus on requiring agencies

to undertake analyses of the environmental impact of

their proposals and actions.’” Id. (quoting Dep’t of

Transp., 541 U.S. at 756-57).

NEPA

requires

that

agencies

consider

alternatives to the proposed action, 40 C.F.R.

§ 1502.14, and “take a hard look at environmental

consequences,” Robertson v. Methow Valley Citizens

Council, 490 U.S. 332, 350 (1989) (internal quotation

marks omitted). To that end, whenever a federal

agency proposes to take a “major Federal action[]

significantly affecting the quality of the human

environment,” the agency must prepare a detailed EIS

App-36

describing the likely environmental effects of the

proposal, any unavoidable adverse environmental

effects, and potential alternatives. 42 U.S.C.

§ 4332(2)(C). Consideration of alternatives “is the

heart of the [EIS].” 40 C.F.R. § 1502.14.

In this case, FERC was the lead agency charged

with issuing the EIS, and the Forest Service acted as

a cooperating agency by assisting FERC to analyze the

environmental impacts to 430 acres of national forest

lands on the proposed ACP route. As a cooperating

agency, the Forest Service may adopt FERC’s EIS only

if it undertakes “an independent review of the [EIS]”

and “concludes that its comments and suggestions

have been satisfied.” 40 C.F.R. § 1506.3(c); see also

Sierra Club, 897 F.3d at 590. It must also ensure that

the EIS is “adequate” under NEPA regulations. 40

C.F.R. § 1506.3(a). In reviewing an EIS, the court’s

responsibility is to “determine whether the [agency]

has considered the relevant factors and articulated a

rational connection between the facts found and the

choice made.” Sierra Club, 897 F.3d at 594 (quoting

Balt. Gas & Elec. Co. v. Nat. Res. Def. Council, Inc.,

462 U.S. 87, 105 (1983)).

Petitioners assert that the Forest Service violated

NEPA by (1) failing to study alternative off-forest

routes, and (2) adopting a FEIS that failed to take a

hard look at landslide risks, erosion, and degradation

of water quality.

1.

Study of Alternative Off-Forest Routes

As noted above, an agency may only adopt an EIS

if it “meets the standards for an adequate statement”

App-37

under the applicable regulations. 40 C.F.R.

§ 1506.3(a). One applicable regulation provides:

If a [DEIS] is so inadequate as to preclude

meaningful analysis, the agency shall

prepare and circulate a revised draft of the

appropriate portion. The agency shall make

every effort to disclose and discuss at

appropriate points in the draft statement all

major points of view on the environmental

impacts of the alternatives including the

proposed action.

Id. § 1502.9(a) (emphasis supplied). Petitioners assert

that FERC’s FEIS was inadequate because it failed to

sufficiently study alternative pipeline routes for the

ACP that avoided national forest lands. According to

Petitioners, the Forest Service violated NEPA because

it adopted FERC’s inadequate EIS without

undertaking the required “independent review,” and

because the FEIS did not satisfy the Forest Service’s

earlier comments and suggestions on the DEIS. Id.

§ 1506.3(c).

In counter, the Forest Service asserts that once

FERC had issued the Certificate of Convenience and

Public Necessity, the choice before the Forest Service

was simple: either approve the pipeline route as it was

authorized by FERC or deny the right of way.

According to the Forest Service, since FERC was

responsible for analyzing alternative pipeline routes,

the Forest Service reasonably relied on that

alternatives analysis in adopting the FEIS.

The Forest Service frames Petitioners’ argument

as an impermissible collateral attack on FERC’s

actions, but that ignores the Forest Service’s

App-38

obligation to “independent[ly] review” the EIS and

ensure its comments and suggestions to the lead

agency were satisfied before adopting it. 40 C.F.R.

§ 1506.3(c). Neither the Forest Service nor Atlantic

points to evidence in the record to demonstrate that

the Forest Service undertook the required

independent review. To the contrary, the record

suggests that they did not. Instead, the record reflects

that at first the Forest Service strenuously objected to

the lack of non-national forest route alternatives in

the DEIS, but it eventually reversed course and

adopted the FEIS even though the analysis of nonnational forest alternatives was unchanged from the

DEIS—all in an effort to prevent Atlantic from having

to obtain congressional approval for the project to

cross the ANST.

From the beginning, the Forest Service made

clear through its comments to FERC and Atlantic that

the EIS would need to analyze non-national forest

alternative routes and justify the necessity of any

proposed route crossing of national forest lands. The

Forest Service’s scoping comments for the ACP project

noted:

It is . . . necessary to understand why any

proposed routes (preferred or alternative)

crossing [National Forest System] lands are

selected over those not crossing [National

Forest System] lands. Therefore, the EIS

should contain a comparison of project effects

for routes crossing [National Forest System]

lands versus routes not crossing [National

Forest System] lands. Discussions and other

relevant information should also be provided

App-39

to justify the necessity of any proposed route

crossing

[National

Forest

System]

lands. . . . Comparisons of the alternatives

should be based on analyses of site-specific

impacts to resources potentially affected by

the proposed project, which may not

necessarily be correlated with the footprint of

the proposed project.

J.A. 3593.

Then, FERC’s DEIS indicated that “[a] significant

factor in siting ACP was the location at which the

pipeline would cross the ANST.” J.A. 3207. As the

DEIS stated, crossing the ANST on NPS lands would

require congressional approval. “Because of this

legislative process”—that is, to avoid obtaining

congressional approval to cross the ANST on NPS

lands—“Atlantic considered locations where the

ANST was located on [Forest Service lands], which

significantly constrained the pipeline route and

severely limits opportunities for avoiding and/or

minimizing the use of [National Forest System]

lands.” Id. at 3207-08 (emphasis supplied). Because of

this, and even though ground resource surveys had

not been conducted, FERC concluded that it “ha[d] not

identified or received any information that suggests

the shorter pipeline route through the National

Forests has significantly greater impacts to sensitive

resources than the alternative” that avoided national

forest lands. Id. at 3208. In response to this analysis

of off-forest routes in the DEIS, the Forest Service

commented:

No analysis of a National Forest Avoidance

Alternative has been conducted, and

App-40

environmental impacts of this alternative

have not been considered or compared to the

proposed action. Therefore, the Forest Service

cannot support the recommendation that the

National Forest Avoidance Alternative be

dropped from consideration. In our scoping

comments, we requested that all alternatives,

including a National Forest Avoidance

Alternative, be fully addressed in regard to

their feasibility and environmental effects.

We hereby reiterate that request.

Id. at 2454. Further, in response to the DEIS’s

assertion that in general, as the length of a pipeline

route increases, the environmental impacts also

increase, the Forest Service commented: “Miles of line

do not necessarily equate to severity of the

environmental impact. The nature of the resources to

be impacted needs to be considered. The Forest

Service has previously requested that such

comparative information on impacts be obtained and

considered for alternatives to the proposed action.” Id.

at 2451.

Despite the Forest Service’s concerns regarding

the lack of study of off-forest alternatives, the

“National Forest Avoidance Route Alternatives”

section in the FEIS is identical to the DEIS.

Nevertheless, on the very same day that FERC issued

the FEIS, the Forest Service released its draft ROD,

which proposed adopting the FEIS (and, consequently,

the unchanged alternatives analysis). Without

explaining the Forest Service’s change of position from

the scoping comments or its comments on the DEIS,

the draft ROD states: “FERC’s evaluation concluded

App-41

that the major pipeline route alternatives and

variations do not offer a significant environmental

advantage when compared to the proposed route or

would not be economically practical.” J.A. 1411. The

Forest Service’s discussion on this point was

essentially identical in its response to objections filed

to the draft ROD and in its final ROD. 4

4 The Forest Service’s response to objections filed to the draft

ROD stated:

The Project Record shows consideration of alternatives

that avoid National Forests. One such alternative

would have increased the route by 43 miles to the

south and another would have increased the route by

15 miles to the north. The FERC noted, as a general

matter, environmental impacts increase as the length

of a pipeline route increases. Furthermore, the FERC

lacked information concluding a shorter overall route

through NFS lands would have significantly greater

impacts on sensitive resources . . . . Therefore, it was

concluded these alternatives would not provide a

significant environmental advantage over a shorter

route that passes through National Forests.

J.A. 676. Similarly, the final ROD stated:

The proposed crossing of the MNF and GWNF received

a considerable amount of comment and criticism from

stakeholders, and accordingly, resulted in a number of

evaluated route alternatives and variations. FERC

evaluated . . . several variations to avoid or minimize

crossing

of

[Forest

Service]

and

[NPS]

lands. . . . FERC’s evaluation concluded the major

pipeline route alternatives and variations do not offer

a significant environmental advantage when

compared to the proposed route or would not be

economically practical.

Id. at 48.

App-42

The Forest Service asserts, “Petitioners present

no record evidence that FERC did not” continue to

analyze non-national forest alternatives following the

Forest Service’s comments on the DEIS. Resp’t’s Br.

39. But no such analysis is apparent anywhere in the

record, and most tellingly, neither the Forest Service

nor Atlantic even attempt to identify evidence to

demonstrate that FERC did anything to address the

Forest Service’s concerns about off-forest alternative

routes. What is apparent from the record is that: (1)

the Forest Service repeatedly expressed concerns

about the need to analyze alternative pipeline routes

that avoided the national forests (particularly in the

scoping comments, comments on the draft resource

reports, and the DEIS); (2) FERC’s analysis of

alternative pipeline routes remained unchanged from

the DEIS to the FEIS, and there is no other evidence

apparent from the record that FERC addressed the

Forest Service’s concerns about off-forest alternative

routes; and (3) the Forest Service never explains, in

the ROD or elsewhere, how its concerns about offforest alternative routes were assuaged.

The chain of events surrounding the Forest

Service’s sudden acquiescence to the alternatives

analysis in the FEIS is similar to that in Sierra Club

v. Forest Service, where we determined that the Forest

Service had acted arbitrarily and capriciously in

adopting the sedimentation analysis in the FEIS for a

different pipeline project. See Sierra Club, 897 F.3d at

594-96. Here, like in Sierra Club, “[g]iven the

circumstances, we simply cannot conclude that the

Forest Service undertook an independent review and

determined that its comments and concerns were

satisfied” when it seemingly dropped its demand that

App-43

off-forest alternative routes be studied before the ACP

was authorized without any further analysis. Id. at

595. In light of this, and particularly considering the

Forest Service’s earlier skepticism that location

decisions for the ACP were made solely to avoid

congressional approval, 5 we hold that adopting the

unchanged alternatives analysis in the FEIS was

arbitrary and capricious.

2.

Analysis of Landslide Risks, Erosion, and

Degradation of Water Quality

Petitioners further contend that the Forest

Service’s deficient analysis of landslide risks, erosion

impacts, and water quality degradation from the ACP

project violated NEPA. Specifically, Petitioners assert

that the Forest Service abandoned its request for ten

site-specific stabilization designs prior to granting the

SUP, which it previously stated were necessary to

evaluate effects under NEPA, and instead accepted

the two that Atlantic provided as “adequate” without

explanation for this change in position. Additionally,

Petitioners assert that Atlantic’s erosion and

sedimentation mitigation plan had not been

determined at the time the FEIS and ROD were

issued. Thus, the Forest Service did not know if the

mitigation measures it relied on to approve the project

would actually be successful. As a result, Petitioners

argue that the FEIS does not provide “a thorough

5 See, e.g., J.A. 3661 (“[T]he report should . . . not base all of the

routing decisions for the [ANST] crossing on project timeline

issues with getting [c]ongressional approval. The proposed

location for crossing the [ANST] need[s] to be based on sound

resource and compelling public interest determinations.”).

App-44

investigation into the environmental impacts of [the]

agency’s action.” Pet’rs’ Reply Br. 29 (quoting Nat’l

Audubon Soc’y v. Dep’t of Navy, 422 F.3d 174, 185 (4th

Cir. 2005)). For its part, the Forest Service contends

that it thoroughly analyzed the impacts of the

proposed route on national forest lands, and that

NEPA does not require an agency to formulate and

adopt a complete mitigation plan before it can act.

As noted above, NEPA does not require the Forest

Service to ensure “environment-friendly outcomes.”

Nat’l Audubon Soc’y, 422 F.3d at 184. Rather, “an

agency decision is acceptable even if there will be

negative environmental impacts resulting from it, so

long as the agency considered these costs and still

decided that other benefits outweighed them. ‘NEPA

merely prohibits uninformed—rather than unwise—

agency action.’” Id. (quoting Robertson, 490 U.S. at

350-51 (citations omitted)). Nevertheless, an EIS must

still “contain a detailed discussion of possible

mitigation measures.” Robertson, 490 U.S. at 351.

Further, NEPA requires “particular care” “when the

environment that may be damaged is one that

Congress has specially designated for federal

protection,” such as national forests. Nat’l Audubon

Soc’y, 422 F.3d at 186-87.

We conclude that the Forest Service violated

NEPA by failing to take a hard look at the

environmental consequences of the ACP project. The

Forest Service expressed serious concerns that the

DEIS lacked necessary information to evaluate

landslide risks, erosion impacts, and degradation of

water quality, and it further lacked information about

App-45

the effectiveness of mitigation techniques to reduce

those risks.

Specifically, the record reflects that the Forest

Service voiced concerns about (1) authorizing the SUP

without ten site-specific stabilization designs to

demonstrate the effectiveness of Atlantic’s BIC

program; (2) the overly high efficiency rate of erosion

control devices used in the sedimentation analysis (96

percent); (3) relying on the use of water bars as a

mitigation technique, when Atlantic had not analyzed

whether water bars would mitigate or exacerbate

erosion effects during construction; and (4) Atlantic’s

use of averaged versus episodic sediment calculations

to analyze the water resource impacts from increases

in sedimentation due to the ACP project.

However, the FEIS did not address any of these

concerns; rather, it made clear that this incomplete

and/or inaccurate analysis in the DEIS remained

incomplete. The FEIS stated (among other examples):

“slope instability/landslide risk reduction measures

have not been completed or have not been adopted,”

J.A. 1615; “[Atlantic is] currently working to provide

documentation of the likelihood that their proposed

design features and mitigation measures would

minimize the risk of landslides in the project area,” id.

at 1616 (emphasis supplied); “specific [erosion] effects

are unknown” and “it is unclear if erosion control and

rehabilitation measures would meet the standards of

the Forest Plan[s],” id. at 1659; and “water resource

impacts from sedimentation are largely uncertain,” id.

at 1663.

Accordingly, the FEIS could not have satisfied the

Forest Service’s concerns that the DEIS lacked

App-46

necessary information to evaluate the environmental

consequences of the pipeline. Indeed, the FEIS

conceded that the Forest Service’s concerns remained

unresolved. Nevertheless, as Atlantic’s deadlines drew

near, the Forest Service disregarded these concerns

and adopted the FEIS—including its conclusions that

landslide risks, erosion impacts, and degradation of

water quality remained unknown—the very same day

FERC issued it. To support its decision to approve the

project and grant the SUP, the Forest Service relied

on the very mitigation measures it previously found

unreliable. This was insufficient to satisfy NEPA, and

did not constitute the necessary hard look at the

environmental consequences of the ACP project.

a.

Landslide Risks

The Forest Service clearly explained its concerns

about landslides, erosion, and pipeline safety and

stability in its October 24, 2016 letter requesting the

ten site-specific stabilization designs:

The route for the [ACP project] proposed by

[Atlantic] would cross some very challenging

terrain in the central Appalachians.

Potentially difficult situations include steep

slopes, presence of headwater streams,

geologic formations with high slippage

potential, highly erodible soils, and the

presence of high-value natural resources

downslope of high hazard areas. These

hazards are exacerbated by high annual rates

of precipitation and the potential for extreme

precipitation events.

App-47

Similar hazards on other smaller pipeline

projects in the central Appalachians have led

to slope failures, erosion and sedimentation

incidents, and damage to aquatic resources.

Therefore, the [Forest Service] is concerned

that crossing such challenging terrain with a

much larger pipeline could present a high risk

of failures that lead to resource damage.

J.A. 3379.

In addition to highlighting these concerns, the

Forest Service’s October 24, 2016 letter made clear

that the ten selected sites were “merely representative

sites,” required for the Forest Service to determine

whether the ACP project could be permitted in the

GWNF and MNF. J.A. 3379. In other words, the site

designs were needed to aid the Forest Service in its

decision whether to permit the pipeline at all.

Accordingly, the Forest Service’s later decision to only

require the designs prior to construction was not

simply a question of timing. It meant the Forest

Service approved the pipeline without information it

previously determined was necessary to making its

decision, and it did so without acknowledging, much

less explaining, its change in position.

The Forest Service’s reversal is particularly

puzzling considering the reason it requested the sitespecific stabilization designs in the first place: to

demonstrate that Atlantic’s BIC program could

actually work in particular conditions, rather than

simply being a “cookbook with generalities.” J.A. 2514.

The Forest Service also conducted a literature review

on Atlantic’s BIC incremental controls to attempt to

determine the effectiveness of these measures. Far

App-48

from proving the effectiveness of the BIC program, the

literature review concluded: “[T]he majority of these

BIC incremental controls are either too new to provide

any real insight to the effectiveness on erosion control,

especially on steep slopes, or there has not been any

research to prove the effectiveness of these

incremental controls for adequate erosion control.” Id.

at 3703.

Thus, despite its own well-documented concerns

with Atlantic’s mitigation plans, the Forest Service

abandoned its request for the eight site-specific

stabilization designs and adopted the FEIS, all

without science-based evidence of the BIC program’s

effectiveness. This falls far short of NEPA’s hard look

requirement, and the Forest Service’s brief, conclusory

letter stating that the information provided by

Atlantic was “adequate” is insufficient to show that

the Forest Service’s concerns had been addressed as

NEPA requires. J.A. 1881.

Perhaps nothing demonstrates the dangers of the

Forest Service’s insufficient analysis of landslide risks

clearer than the FEIS’s use of the Columbia Gas

Transmission pipeline as an example of an existing

pipeline in the Appalachian Mountains that safely

crosses karst terrain. See, e.g., J.A. 1589, 1609 (“There

are differences between ACP and corridor and the

Columbia pipeline project and corridor, and so, there

can be more potential for project-induced slope

failures in the ACP corridor. But the decades of slope

stability performance of the Columbia pipeline

corridor on slopes generally similar to those along the

ACP pipeline route is relevant information to

consider.”). Significantly, during the briefing of this

App-49

case, a landslide in Marshall County, West Virginia,

caused the Columbia pipeline—highlighted by the

Forest Service for its safety and stability—to rupture

and explode. 6 Clearly, the Forest Service’s concerns

about landslide risks and pipeline safety highlighted

in its October 24, 2016 letter deserve serious

consideration, for the protection of both the

environment and the public.

b.

Erosion Impacts and Degradation of Water Quality

In adopting the FEIS and approving the pipeline,

the Forest Service concluded that because of

“mitigation measures, impacts on groundwater and

surface waters will be effectively minimized or

mitigated.” J.A. 25. However, as explained above, the

Forest Service had previously expressed serious

concerns about the extensive erosion and

sedimentation that the ACP project could cause, and

it additionally questioned the mitigation techniques

that Atlantic relied on to reduce those impacts. This is

particularly true regarding the overly high efficiency

rate of erosion control devices used in the

sedimentation analysis (96 percent), the use of water

bars as a mitigation technique, and the use of

See, e.g., Anya Litvak, Landslide Caused West Virginia

Pipeline Explosion, TransCanada Reports, Pittsburgh PostGazette (July 11, 2018), http://www.post-gazette.com/business/

powersource/2018/07/11/Landslide-caused-pipeline-explosionColumbia-Gas-reported/stories/201807100176. We can take

judicial notice of this fact because it “is not subject to reasonable

dispute” and “can be accurately and readily determined from

sources whose accuracy cannot reasonably be questioned.” Fed.

R. Evid. 201(b).

6

App-50

averaged versus episodic sediment calculations to

analyze water resource impacts in the sedimentation

analysis. Despite these concerns, and the FEIS’s

conclusion that “specific [erosion] effects [remained]

unknown,” id. at 1659, the Forest Service nevertheless

relied on the incomplete analysis in the FEIS and

disregarded its concerns about the effectiveness of the

mitigation techniques.

For example, in the draft biologic evaluation,

Atlantic asserted that installation of erosion control

devices would “reduce erosion by about 96 percent.”

J.A. 2633. The Forest Service criticized this conclusion

in its March 10, 2017 comments to the draft biologic

evaluation, stating, “Use of lab testing and efficiency

rates are inappropriate for steep slope pipeline

construction. Update model with more conservative

assumptions

about

containment

efficiencies.

Document the literature references that apply to

efficiencies in the field, particularly mountainous

terrain in WV and VA.” Id. at 2357.

However, Atlantic did not comply with the Forest

Service’s request, and the 96 percent erosion control

efficiency rate remained in Atlantic’s August 2017 Soil

Erosion and Sedimentation Modeling Report. See J.A.

909 (“Installation of [erosion control devices] was

predicted to reduce erosion by about 96 percent.”). We

note that this report was issued five months after the

Forest Service directed Atlantic to update its erosion

efficiency rate, one month after the Forest Service

issued its draft ROD, just two months before the final

version of the COM Plan was issued, and only three

months before the Forest Service issued the final

ROD. Accordingly, we see no evidence in the record

App-51

that the Forest Service’s concerns regarding the 96

percent erosion control efficiency rate were ever

resolved; nonetheless, the Forest Service ultimately

relied on this figure to determine that Atlantic’s

proposed mitigation measures would effectively

reduce erosion and sedimentation impacts from the

ACP project.

During oral argument, Atlantic claimed that the

Forest Service’s concern about the 96 percent

efficiency rate was resolved because Atlantic agreed

not to use silt fences as a mitigation technique in

certain areas, which it claims were the cause of the

“overly optimistic” efficiency rate. Oral Argument at

37:50-39:41. As counsel for Atlantic stated:

The Forest Service never accepted the 96

percent efficiency. Indeed, that model was

predicated on a standard erosion and

sediment control device called the silt fence.

Instead of debating . . . over the percent

effectiveness of the silt fence, the Forest

Service made a much more direct and

compelling move, which was to prohibit the

use of silt fences in the areas over which it

had concern. . . Atlantic committed not to use

the silt fences that were the subject of the

overly optimistic erosion sediment model.

Id.

As an initial matter, we note that the Soil Erosion

and Sedimentation Modeling Report attributes the 96

percent erosion control efficiency rate to all erosion

control devices “such as silt fences, waterbars, and

mulch application,” not just silt fences. J.A. 929.

Additionally, the final draft of the COM Plan is riddled

App-52

with uses of silt fences as proposed mitigation

techniques. See, e.g., id. at 303, 409, 473, 475, 586,

587.

However, even if Atlantic is correct that it

committed not to use silt fences in certain areas, this

is beside the point. The use of silt fences was not the

problem. The problem, as the Forest Service itself

pointed out, was assuming that these devices would

function nearly perfectly to reduce erosion and

sediment, despite a wealth of evidence to the contrary.

This assumption remained in the August 2017 Soil

Erosion and Sedimentation Modeling Report. See J.A.

908 n.2 (“The effectiveness predicted by the model is

influenced by slope, soil, groundcover, and type of

erosion control device; the model assumes perfect

installation, soil retention, and maintenance.”

(emphasis supplied)). This assumption infected the

sedimentation model—the model that produced the

“200 to 800 percent above baseline erosion” estimate

cited in in the ROD. Id. at 25.

Crucially, we can identify no other more

conservative efficiency rate used to correct the

sedimentation model which drove the Forest Service’s

erosion and sedimentation analysis. Indeed, the use of

the 96 percent efficiency rate in the August 2017 Soil

Erosion and Sedimentation Modeling Report, which

was issued only three months before the Forest

Service’s final ROD, suggests that the Forest Service’s

concern with Atlantic’s overly high efficiency rate for

erosion control devices was never resolved. See J.A.

908-09 (“Installation of [erosion control devices] was

predicted to reduce erosion by about 96 percent.”).

App-53

Additionally, the FEIS relied on the use of water

bars as a mitigation technique that would reduce the

environmental impacts of the ACP project. See J.A.

1662 (“The use of water bars (i.e., slope breakers) was

assumed on long slopes . . . .”). The Forest Service had

previously stated in its comments on Atlantic’s

updated biologic evaluation that further analysis was

needed to determine whether water bars would be

effective: “Slope breaker locations relative to pertinent

habitat features need to be disclosed[.] It is important

to be sure that they are not potentially directing water

into habitats (in which case they would actually do

more harm than good).” Id. at 2337. Nevertheless, the

FEIS candidly acknowledged that this further

analysis was never done:

[W]ater bars create concentrated flows where

they discharge adjoining off right-of-way

areas. The [Forest Service] has stated that

Atlantic has not assessed how or whether the

adjoining areas can receive concentrated

flows, or whether measures would be

implemented to allow these areas to safely

receive and convey the concentrated flows. In

addition, the slopes to be encountered in the

MNF and GWNF would require several water

bars to be “stacked” along their length,

creating multiple points of discharge. The

[Forest Service] has stated the potential

impacts of multiple points of concentrated

discharges onto the adjoining areas has not

been assessed.

Id. at 1663 (emphasis supplied). Once again, the

Forest Service adopted the FEIS (including its use of

App-54

water bars as a mitigation technique), issued its ROD,

and granted the SUP based on an erosion and

sedimentation analysis using water bars as a

mitigation technique, despite the clear evidence in the

record that (1) the Forest Service had concerns with

this technique; (2) the Forest Service’s concerns were

not resolved in the FEIS; and (3) the effectiveness of

water bars for this project was never analyzed.

Finally, the record further reflects that the Forest

Service believed Atlantic used an incorrect calculation

to analyze how sedimentation from the ACP project

would impact aquatic species. In its draft biologic

evaluation, Atlantic analyzed the total sediment that

would erode a stream in a year divided by the volume

of water that would flow through the stream in a

year—to create an average sediment level over an

entire year—rather than analyzing sediment levels in

terms of discrete episodic events, where the sediment

levels vary based on precipitation events that cause

larger amounts of erosion to enter the stream. In other

words, Atlantic employed a simplistic (and unrealistic)

calculation that made in-stream sedimentation levels

look much lower than they would be during

construction. Of note, the Forest Service sharply

criticized this approach in its comments on the draft

biologic report:

This entire paragraph has false rationale and

needs to be deleted or modified extensively.

Erosion and sediment transport to streams

cannot be averaged evenly over a year, rather

it happens in discrete episodic events. It is not

appropriate to minimize impacts by making a

comparison of total load evenly spread over

App-55

time. The point of the load calculation is to

address impacts to sensitive aquatic species

which are impacted by flow and timing of

sediment during these erosion events.

J.A. 2358. However, despite the Forest Service’s

concerns with Atlantic’s calculations in the

sedimentation analysis, the record does not indicate

that Atlantic ever updated its calculation to reflect

actual conditions. Nevertheless, the Forest Service

adopted Atlantic’s updated biologic report and the

FEIS, and it concluded that erosion and sedimentation

from the ACP project would not substantially

adversely affect sensitive aquatic species.

The Forest Service argues—correctly—that

NEPA does not require a fully formed mitigation plan

to be in place. As this court has noted, “it would be

inconsistent with NEPA’s reliance on procedural

mechanisms—as opposed to substantive, result-based

standards—to demand the presence of a fully

developed plan that will mitigate environmental harm

before an agency can act.” Robertson, 490 U.S. at 353.

However, in this case, the Forest Service adopted the

FEIS and issued its draft ROD in reliance on a

mitigation plan that had not been established, and one

that, as demonstrated by the Forest Service’s own

concerns, had not been proven effective.

To satisfy NEPA in this case, the Forest Service

needed to resolve its own concerns with the EIS—

which, for the reasons we have explained, it did not

do—and it needed to have a reasonable basis for

concluding that the mitigation plan, once fully formed,

would be effective. Here, the Forest Service relied on

the generalities of the BIC program and other

App-56

techniques proposed by Atlantic to achieve particular

mitigating results, with neither actual site designs nor

science-based evidence demonstrating such results

were likely. This is precisely the sort of uninformed

agency action that NEPA prohibits. See Nat’l Audubon

Soc’y, 422 F.3d at 184.

Accordingly, we cannot conclude that the Forest

Service took a hard look at the environmental

consequences of its decision. Rather, the record before

us readily leads to the conclusion that the Forest

Service’s approval of the project “was a preordained

decision” and the Forest Service “‘reverse engineered’

the [ROD] to justify this outcome,” despite that the

Forest Service lacked necessary information about the

environmental impacts of the project. Nat’l Audubon

Soc’y, 422 F.3d at 183 (concluding that the U.S. Navy

“reverse engineered” its EIS to achieve a particular

outcome, and although “[t]he deficiencies in each area

of the Navy’s analysis would not, on their own, be

sufficient to invalidate the EIS,” “a review of the

various components of the EIS taken together

indicates that the Navy did not conduct the ‘hard look’

that NEPA requires.”).

Pursuant to NEPA, we conclude the Forest

Service acted arbitrarily and capriciously in adopting

the FEIS and granting the SUP. Upon remand, the

Forest Service should explain its decision that

receiving only two of the eight site-specific

stabilization designs was “adequate” to determine the

environmental effects of the ACP project, and it should

also explain how it took a “hard look” at the erosion,

sedimentation, and water quality issues discussed

here considering the Forest Service’s numerous

App-57

concerns that were not addressed in the FEIS. If

supplemental analysis is needed, particularly

regarding the effectiveness of mitigation strategies

relied on in the COM Plan, the Forest Service should

perform that analysis as well.

C.

Mineral Leasing Act

1.

The MLA authorizes the “Secretary of the Interior

or appropriate agency head” to grant gas pipeline

rights of way across “Federal lands.” 30 U.S.C.

§ 185(a). As relevant here, “Federal lands” means “all

lands owned by the United States except lands in the

National Park System.” 30 U.S.C. § 185(b)(1)

(emphasis supplied). Pursuant to the Park Service’s

Organic Act, land in the National Park System

includes “any area of land and water administered by

the Secretary [of the Interior]” through NPS. 54 U.S.C.

§ 100501.

Congress designated the ANST as a National

Scenic Trail administered by the Secretary of the

Interior, who delegated that duty to NPS. See 16

U.S.C. § 1244(a)(1). Accordingly, the ANST is land in

the National Park System. The parties are generally

in agreement about this; after NPS informed FERC

that “the entire [ANST] corridor [is] part of the ANST

park unit” and a “unit” of the National Park System,

J.A. 1849, 3186, FERC’s FEIS concluded that NPS is

“the lead federal agency for the administration of the

entire ANST” and that the ANST “is a ‘unit’ of the

national park system,” J.A. 1794. The parties also do

not dispute that NPS indicated it does not have

authority under the MLA to grant pipeline rights of

App-58

way across the ANST. However, the parties disagree

about whether the Forest Service has the authority to

grant such rights of way across the ANST. The FEIS

concluded:

The ANST is a unit of the National Park

system; however, the lands acquired and

administered by the [Forest Service] for the

ANST are [National Forest System] lands

and subject exclusively to [Forest Service]

regulations

and

management

authority. . . . [A]n authorization from the

NPS is not required for Atlantic’s proposed

ANST crossing on [National Forest System]

lands.”

Id. at 1489 (emphasis supplied).

The Forest Service asserts that the MLA

authorizes the Forest Service to grant pipeline rights

of way on Forest Service land traversed by the ANST.

Specifically, the Forest Service argues that the

National Trails System Act, which provides for the

administration of national trails like the ANST,

distinguishes between the “overall” administration of

the ANST (with which NPS is charged) and

administration of the ANST’s underlying lands (most

of which are under the jurisdiction of other agencies,

like the Forest Service). Pursuant to this reading of

the National Trails System Act, the Forest Service

asserts, the MLA authorizes the Forest Service to

grant pipeline rights of way on portions of the ANST

traversing lands administered by the Forest Service.

The Forest Service largely relies on the following

language from the National Trails System Act to

support this argument:

App-59

The Secretary of the Interior or the Secretary

of Agriculture as the case may be, may grant

easements and rights-of-way upon, over,

under, across, or along any component of the

national trails system in accordance with the

laws applicable to the national park system

and the national forest system, respectively:

Provided, That any conditions contained in

such easements and rights-of-way shall be

related to the policy and purposes of this

chapter.

16 U.S.C. § 1248(a) (emphasis supplied). The MLA,

the Forest Service asserts, prevents NPS from

authorizing pipeline rights of way across components

of the ANST on National Park System lands, but it

does not prevent the Forest System from authorizing

pipeline rights of way across components of the ANST

on National Forest System lands. In any event, the

Forest Service concedes that its position on this issue

is entitled to no judicial deference. See Resp’t’s

Surreply Br. 12-13.

The problem with the Forest Service’s argument

is it misreads both the MLA and the National Trails

System Act. The MLA specifically excludes lands in

the National Park System from the authority of the

Secretary of the Interior “or appropriate agency head”

to grant pipeline rights of way. See 30 U.S.C. §§ 185(a),

185(b)(1). In other words, the MLA concerns the land,

not the agency. The FEIS concluded, and the parties

agree, that the ANST is a unit of the National Park

System. Accordingly, even if the Forest Service were

the “appropriate agency head” in this instance, it could

not grant a pipeline right of way across the ANST

App-60

pursuant to the MLA. Interpreting the MLA as the

Forest Service argues would give the Forest Service

more authority than NPS on National Park System

land. This defies logic.

Further, the Forest Service is not the “appropriate

agency head” for the ANST. The Forest Service’s

arguments notwithstanding, the National Trails

System Act does not distinguish between various

levels of administration of the ANST (“overall” versus

by “jurisdiction”); rather, as NPS explained to FERC,

the Act is clear that the Secretary of the Interior

administers the entire ANST, while “other affected

State and Federal agencies,” like the Forest Service,

manage trail components under their jurisdiction. See

16 U.S.C. §§ 144(a), 1246(a). Indeed, 16 U.S.C.

§ 1246(a) clearly distinguishes between trail

administration and management:

The Secretary charged with the overall

administration of a trail pursuant to section

1244(a) of this title shall, in administering

and managing the trail, consult with the

heads of all other affected State and Federal

agencies. Nothing contained in this chapter

shall be deemed to transfer among Federal

agencies any management responsibilities

established under any other law for federally

administered lands which are components of

the National Trails System.

§ 1246(a)(1)(A) (emphasis supplied).

Section 1248(a) of the Act does not transfer

administration responsibilities of the ANST to the

Forest Service simply because the Forest Service

manages land underlying components of the ANST.

App-61

Although it is true that § 1248(a) does permit the

Secretary charged with overall administration of a

national trail—“[t]he Secretary of the Interior or the

Secretary of Agriculture as the case may be”—to grant

easements and rights of way in accordance with the

laws applicable to either the National Park System or

the National Forest System, in this case, the

applicable administrator is the Secretary of the

Interior, not the Secretary of Agriculture, and the

applicable laws are those of the National Park System.

See 16 U.S.C. § 1244(a)(1) (“The Appalachian Trail

shall be administered primarily as a footpath by the

Secretary of the Interior, in consultation with the

Secretary of Agriculture.”). Other national trails are

administered by the Secretary of Agriculture and are

subject to laws applicable to the National Forest

System—the ANST is simply not one of those trails.

See, e.g., § 1244(a)(2), (5), (13), (14), (27), (30) (charging

the

Secretary

of Agriculture

with overall

administration of the Pacific Crest Trail, the

Continental Divide National Scenic Trail, the Florida

National Scenic Trail, the Nez Perce National Historic

Trail, the Arizona National Scenic Trail, and the

Pacific Northwest National Scenic Trail).

The Forest Service’s arguments to the contrary

are unavailing, and the Forest Service does not have

statutory authority to grant pipeline rights of way

across the ANST pursuant the MLA. The Forest

Service’s ROD and SUP granting this right of way are,

accordingly, vacated.

2.

The Forest Service also argues that Petitioners

have no standing to bring this challenge because they

App-62

allege no harm traceable to the right of way grant. For

the reasons this court explained in Sierra Club v. U.S.

Department of the Interior, this standing argument

fails. See 899 F.3d 260, 282-85 (4th Cir. 2018).

Petitioners’ alleged injuries are fairly traceable to the

Forest Service because “without [the Forest Service’s]

grant of a right of way, the pipeline could not have

been authorized in its currently proposed form. It

therefore cannot be said that Petitioners’ injuries are

‘the result of the independent action of some third

party not before the court.’” Id. at 284 (quoting Bennett

v. Spear, 520 U.S. 154, 168-69 (1997)).

Furthermore, the Forest Service asserts that

Petitioners waived their argument that the Forest

Service lacks statutory authority to grant rights of

way across the ANST because Petitioners failed to

adequately raise that argument before the Forest

Service. In comments on the draft ROD, Petitioners

objected to the agency’s failure to consider nonnational forest routes for the pipeline and the viability

of Atlantic’s proposed method for crossing the ANST.

Petitioners did not challenge the Forest Service’s

authority to issue the right of way in the first instance.

Those challenging agency actions, such as

Petitioners here, are generally required to raise their

arguments to the agency during the administrative

review process and to exhaust their administrative

remedies before this Court may consider their

arguments. See 7 U.S.C. § 6912(e). Nonetheless, the

draft ROD—to which the Forest Service claims that

Petitioners should have lodged their MLA objection—

nowhere mentions that the Forest Service was

contemplating granting right of way through lands

App-63

administered by NPS, or the ANST, in particular. To

the contrary, the draft ROD characterizes the decision

to be made as “[W]hether to authorize the use and

occupancy of NFS lands for [Atlantic] to construct,

operate, maintain, and eventually decommission a

natural gas pipeline that crosses NFS lands

administered by the MNF and GWNF.” J.A. 1378

(emphasis added).

Because (1) the draft ROD purported to be

considering granting right of way through only Forest

Service “lands administered by the MNF and GWNF”

and (2) the FEIS, upon which the draft ROD relied,

stated that NPS “administered” the entire ANST and

that the entire ANST is a “unit” of the National Park

System, there was no reason for Petitioners, or any

other public commenter, to believe that the ROD or

the SUP would grant right of way across the ANST. To

be sure, Petitioners may have been on notice from the

FEIS that the pipeline would require a right of way

across the ANST from some agency at some point, but

Petitioners had no way to know that such right of way

would be granted by the Forest Service through the

ROD. Indeed, the plain language of the SUP

authorizes Atlantic “to use or occupy” only “National

Forest System lands in the [MNF] and the [GWNF] of

the National Forest System.” Put simply, the Forest

Service never notified the public that it intended to

grant Atlantic right of way through a unit of the

National Park System like the ANST.

Furthermore, and significantly, the draft ROD

nowhere mentions that the Forest Service intended to

rely on the MLA as the basis of its authority to grant

the right of way across the ANST. Indeed, regarding

App-64

the MLA, the FEIS stated only that separate,

congressional approval would be required if NPS were

the agency issuing the right of way. See, e.g., Bowen v.

City of New York, 476 U.S. 467, 482-87 (1986)

(refusing to enforce exhaustion requirement when

plaintiffs could not have been expected to

administratively “attack a policy they could not be

aware existed” (internal quotation marks omitted));

Beth V. v. Carroll, 87 F.3d 80, 83 (3d Cir. 1996)

(excepting plaintiff from statutory exhaustion

requirement when he “was given no prior notice or

opportunity to object” and requiring exhaustion would

be “futile”).

Moreover, the question of whether the MLA

authorized the Forest Service to issue the SUP is a

purely legal question that this Court may answer

without the benefit of the Forest Service’s expertise.

Our sister courts have recognized an exception to the

administrative exhaustion requirement for such legal

issues. See Bartlett v. U.S. Dep’t of Agric., 716 F.3d

464, 474 (8th Cir. 2013); Vt. Dep’t of Pub. Serv. v.

United States, 684 F.3d 149, 159-60 (D.C. Cir. 2012);

Beth V., 87 F.3d at 88. Under the legal question

exception, a party’s failure to exhaust administrative

remedies is excused if the issues “are legal questions

which are not suitable for administrative resolution

and are more properly resolved by the courts.”

Bartlett, 716 F.3d at 474 (citation omitted). This

exception is narrow. See id.; 7 West’s Fed. Admin.

Prac. § 8226 (2018) (“[C]ourts have plenary power over

questions of law, but usually legal questions must first

be presented to the agency.”). Nonetheless, when the

agency has no expertise in the issue, and no factual

disputes must be resolved, the question may be ripe

App-65

for judicial review notwithstanding a party’s failure to

exhaust its administrative remedies. See Ace Prop.

and Cas. Ins. Co. v. Fed. Crop Ins. Corp., 440 F.3d 992,

1001 (8th Cir. 2006); see also EEOC v. Seafarers Int’l

Union, 394 F.3d 197, 201 (4th Cir. 2005) (discussing

exhaustion exception for legal issues and stating that

“courts have limited it to issues that are

quintessentially legal and fail to implicate the

agency’s expertise in any meaningful manner”

(citation omitted)).

The issue of whether the Forest Service had

authority under the MLA to issue a right of way across

the ANST is a question of statutory interpretation.

Such a question is the peculiar province of the courts.

Indeed, “[t]he judiciary is the final authority on issues

of statutory construction . . . .” Chevron, U.S.A., Inc. v.

Nat. Res. Def. Council, Inc., 467 U.S. 837, 843 n.9

(1984). And the Forest Service has pointed to no

factual disputes that must otherwise be resolved

before the Court may determine the scope of the

agency’s authority under the MLA.

Accordingly, because (1) Petitioners were not put

on notice that the right of way across the ANST would

be granted by the Forest Service through the ROD; (2)

the Forest Service gave no hint of the legal authority

that it would claim in issuing the SUP during the

administrative review process; and (3) the Forest

Service’s authority to issue rights of way pursuant to

the MLA is a purely legal question, we decline to find

that Petitioners were required to exhaust their

administrative remedies in connection with their MLA

argument.

App-66

IV.

We trust the United States Forest Service to

“speak for the trees, for the trees have no tongues.” Dr.

Seuss, The Lorax (1971). A thorough review of the

record leads to the necessary conclusion that the

Forest Service abdicated its responsibility to preserve

national forest resources. This conclusion is

particularly informed by the Forest Service’s serious

environmental concerns that were suddenly, and

mysteriously, assuaged in time to meet a private

pipeline company’s deadlines. Accordingly, for the

reasons set forth herein, we grant the petition to

review the Forest Service’s Record of Decision and

Special Use Permit, vacate the Forest Service’s

decisions, and remand to the Forest Service for

proceedings consistent with this opinion.

PETITION FOR REVIEW GRANTED,

VACATED AND REMANDED

App-67

Appendix B

UNITED STATES COURT OF APPEALS

FOR THE FOURTH CIRCUIT

________________

No. 18-1144

________________

COWPASTURE RIVER PRESERVATION ASSOCIATION;

HIGHLANDERS FOR RESPONSIBLE DEVELOPMENT;

SHENANDOAH VALLEY BATTLEFIELDS FOUNDATION;

SHENANDOAH VALLEY NETWORK; SIERRA CLUB;

VIRGINIA WILDERNESS COMMITTEE;

WILD VIRGINIA, INC.,

v.

Petitioners,

FOREST SERVICE, an agency of the U.S. Department of

the Agriculture; KATHLEEN ATKINSON, in her official

capacity as Regional Forester of the Eastern Region;

KEN ARNEY, in his official capacity as Acting Regional

Forester of the Southern Region,

Respondents,

ATLANTIC COAST PIPELINE LLC,

Intervenor.

________________

Decided: Feb. 25, 2019

________________

ORDER

________________

Upon consideration of the petition for en banc

rehearing filed by Atlantic Coast Pipeline and the

App-68

petition for panel and en banc rehearing filed by the

federal respondents, and no judge having requested a

poll of the court on the petitions for en banc rehearing,

the court denies the petition for en banc rehearing and

the petition for panel and en banc rehearing.

Entered at the direction of the panel: Chief Judge

Gregory, Judge Wynn, and Judge Thacker.

For the Court

/s/ Patricia S. Conner, Clerk

App-69

Appendix C

UNITED STATES DEPARTMENT OF

AGRICULTURE

________________

ATLANTIC COAST PIPELINE PROJECT SPECIAL USE

PERMIT/LAND AND RESOURCE MANAGEMENT

PLAN AMENDMENTS

________________

Pocahontas County, West Virginia and Highland,

Bath, and Augusta Counties, Virginia

________________

Lead Agency: Federal Energy Regulatory

Commission

Cooperating Agency: U.S.D.A. Forest Service

________________

Dated: Nov. 17, 2017

________________

RECORD OF DECISION

________________

LIST OF ACRONYMS

ACP

Atlantic Coast Pipeline

ANST

Appalachian National Scenic Trail

ATWS

Additional Temporary Workspace

BA

Biological Assessment

BASI

Best Available Scientific

Information

BI

Beneficial Impact

BIC

Best in Class

App-70

BRP

Blue Ridge Parkway

BO

Biological Opinion

CFR

Code of Federal Regulations

CWA

Clean Water Act

COM

Construction, Operations, and

Maintenance

DEIS

Draft Environmental Impact

Statement

EPA

Environmental Protection Agency

ESA

Endangered Species Act

FEIS

Final Environmental Impact

Statement

FERC

Federal Energy Regulatory

Commission

FS

Forest Service

FWS

US Fish and Wildlife Service

FR

Federal Register

FR

Forest Road

GWNF

George Washington National Forest

HDD

Horizontal Directional Drilling

KOP

Key Observation Point

LRMP

Land and Resource Management

Plan

MNF

Monongahela National Forest

NEPA

National Environmental Policy Act

NFS

National Forest System

NFMA

National Forest Management Act

NOA

Notice of Availability

App-71

NOI

Notice of Intent

NRCS

Natural Resource Conservation

Service

NRHP

National Register of Historic Places

RACR

Roadless Area Conservation Rule

RFSS

Regional Forester Sensitive Species

ROD

Record of Decision

ROW

Rights of Way

RUSLE

Revised Universal Soil Loss

Equation

SHP

Supply Header Project

SHPO

State Historic Preservation Office

SIO

Scenic Integrity Objectives

SSURGO

Soil Survey Geographic Database

SUP

Special Use Permit

TEP

Threatened, Endangered, and

Proposed Species

U.S.C.

United States Code

USDA

United States Department of

Agriculture

VDCR-DNH

Virginia Department of Conservation

and Recreation–Division of Natural

Heritage

VIA

Visual Impact Analysis

WVDEP

West

Virginia

Department

Environmental Protection

of

App-72

INTRODUCTION

This record of decision (ROD) documents Forest

Service (FS) decisions and rationale for:

(1) Authorizing the use and occupancy of National

Forest System (NFS) land for Atlantic Coast

Pipeline, LLC (Atlantic) to construct, operate,

maintain, and eventually decommission a

natural gas pipeline that crosses NFS lands

administered by the Monongahela National

Forest (MNF) and George Washington

National Forest (GWNF); and

(2) Approving:

a.

a project-specific Forest Plan amendment

to the Monongahela National Forest’s

Land and Resource Management Plan1

(United

States

Department

of

Agriculture [USDA] Forest Service

2011), and

b.

a project-specific Forest Plan amendment

to the George Washington National

Forest’s LRMP (USDA Forest Service

2014).

Our decisions are based on the Final

Environmental Impact Statement (FEIS) prepared by

the Federal Energy Regulatory Commission (FERC)

for the Atlantic Coast Pipeline (ACP) Project and

Supply Header Project (SHP) (FERC 2017). In

accordance with the Natural Gas Act (Title 15 United

States Code [U.S.C.] § 717), the FERC is the lead

Federal agency for the environmental analysis of the

1 Hereafter referred to as the “LRMP” or “Forest Plan”

App-73

construction and operation of the ACP and SHP.

Federal agencies with a role in authorizing an

application for a natural gas pipeline are required by

law to cooperate in processing the application and to

comply with the processing schedule established by

FERC (Section 313 of Energy Policy Act of 2005). We

participated as a cooperating agency with the FERC

during the FEIS development. We have adopted the

environmental analysis conducted by FERC (in

accordance with 40 Code of Federal Regulations [CFR]

1506 (a) and (c)) to support this ROD.

Please note, while the pronoun “we” is used in this

document, the Regional Forester for the Eastern

Region (R9) is responsible for any decisions related to

the MNF and the Regional Forester for the Southern

Region (R8) is responsible for any decisions related to

the GWNF.

BACKGROUND

The ACP Project will involve the construction and

operation of 604.5 miles of an interstate natural gas

pipeline. Of the total ACP route miles, about 21 miles

are located on NFS lands. The SHP involves the

construction and operation of 37.5 miles of pipeline,

but since it will not impact NFS lands, it is not

addressed in this ROD. Figure 1-1 in the FEIS

provides an overview map of the two pipeline projects

analyzed in the FERC’s FEIS.

Section 1.0 (Introduction) of the FEIS describes

the background for the ACP Project. The ACP Project

on NFS lands includes the construction, operation,

and maintenance of a buried 42-inch diameter

interstate mainline natural gas pipeline that crosses

about 5 miles of lands managed by the MNF and 16

App-74

miles of lands managed by the GWNF. The pipeline

route will cross the Appalachian National Scenic Trail

(ANST) on the GWNF and the Blue Ridge Parkway

(BRP) on National Park Service land.

The construction corridor for the pipeline in most

instances will be 125 feet wide, but narrows to 75-feet

wide when crossing wetlands. The construction

corridor will be reclaimed to a final operational

corridor width of 50 feet. The pipeline will be buried so

that there will be three feet of cover in most areas, 18

inches of cover in consolidated rock and deeper when

crossing waterbodies. There will be no significant

above ground facilities located on either the MNF or

GWNF, although there will be minor equipment such

as test stations and line markers (size of a fence post).

The land use requirements of the project on NFS lands

is shown in Table 1:

Table 1 - Land Requirements of the Atlantic Coast

Pipeline on NFS Lands

App-75

If all approvals are in place, construction activity

to install the pipeline on NFS lands is scheduled to

begin in April 2018 and conclude in late 2019. Timber

removal would occur prior to pipeline installation

activity, but must occur between November 15 and

March 31 to avoid impacts to threatened and

endangered bats. Operation and maintenance within

the right-of-way (ROW) will begin shortly thereafter

and continue during the 30 year life of the special use

permit (SUP).

PURPOSE

ACTION

AND

NEED

AND

PROPOSED

Section 1.1 (Project Purpose and Need) of the

FEIS describes the purpose of the project is to serve

the growing energy needs of multiple public utilities

and local distribution companies in Virginia and

North Carolina. Atlantic states the ACP Project will

increase the reliability and security of natural gas

supplies in these two States, with the majority of the

gas supplied to be used to generate electricity for

industrial, commercial, and residential uses.

The purpose and need for the FS proposed action

is to respond to Atlantic’s application for a special use

permit that was submitted to the FS on June 16, 2016.

The proposed action by the FS is to authorize Atlantic

to use and occupy NFS lands for the ACP Project and

approve LRMP amendments to allow the project to be

consistent with the LRMPs. The FS decisions are

needed to meet our statutory obligations as a

cooperating agency in processing applications for

natural gas pipelines involving Federal land under

provisions Section 28 of the Mineral Leasing Act of

App-76

1920 (30 U.S.C. § 181) and the Energy Policy Act of

2005.

The Mineral Leasing Act of 1920 and federal

regulations at 36 CFR 251 Subpart B provide the FS

with authority to issue a SUP for construction and

operation of an oil and gas pipeline across these NFS

lands. The FS may include stipulations in the SUP it

deems necessary to protect Federal property and

otherwise protect the public interest.

Section 4.8.9 (“Federal Lands”) of the FEIS

describes the four MNF and nine GWNF Forest Plan

standards that will be modified and constitute the

amendment of each Forest LRMP. These amendments

allow the ACP Project to meet Forest Plan Standards

and minimize impacts to soil, water, riparian,

threatened and endangered species, recreational and

visual resources. Section 4.8.9.1 (“Forest Service”) of

the FEIS describes the function of Forest Plan

standards, as well as other types of management

direction that guide design of the ACP Project across

NFS lands. The National Forest Management Act

(NFMA) requires that proposed projects, including

third-party proposals subject to permits, be consistent

with the Forest Plan of the administrative unit where

the project will occur. The amendments are being

approved concurrently with our adoption and

use/occupancy decisions for the MNF and GWNF in

accordance with 36 CFR 219.15(c)(4).

DECISION TO BE MADE

are:

The decisions to be made by the Forest Service

(1) Whether to authorize the use and occupancy of

NFS land for Atlantic Coast Pipeline, LLC to

App-77

construct, operate, maintain, and eventually

decommission a natural gas pipeline that crosses

NFS lands administered by the MNF and GWNF;

and

(2) Whether to approve:

a.

A

project-specific

Forest

Plan

amendment to modify four standards in

the MNF’s Forest Plan, and

b.

A

project-specific

Forest

Plan

amendment to modify nine standards in

the GWNF’s Forest Plan.

We have reviewed those portions of the FEIS

directly related to NFS lands and the effects from the

ACP Project on those lands. We adopted the FEIS

because the analysis provides sufficient evidence to

support our decisions in compliance with Forest

Service regulations 36 CFR Part 219 (Planning), Part

220 (National Environmental Policy Act Compliance),

and Part 251 (Land Uses).

We have determined that the scope of the FEIS

analysis and this decision is limited to considering

authorizing use and occupancy and approving projectspecific plan amendments related to the ACP Project

on NFS lands. “Project-specific plan amendments”

means the amendments are applicable only to the ACP

Project and not to other current or future projects. We

have determined whether and how the four MNF and

nine GWNF modified Forest Plan standards are

directly related to the substantive requirements (36

CFR 219.8 through 219.11) of the Forest Service

planning regulations. The substantive requirements

address sustainability, diversity of plant and animal

communities, multiple use, and timber requirements

App-78

based on the NFMA. A forest plan amendment is

“directly related” to a substantive requirement if it has

one or more of the following relationships to a

substantive requirement:

•

•

•

•

the purpose for the amendment,

there would be a beneficial effect of the

amendment,

there would be a substantial adverse effect of

the amendment, or

there would be a substantial lessening of plan

protections by the amendment.

If a proposed amendment is determined to be

“directly related” to a substantive rule requirement,

we as the responsible officials must apply that

requirement within the scope and scale of the

proposed amendment and, if necessary, make

adjustments to the proposed amendment to meet the

substantive requirements. 36 CFR 219.13 (b)(5) and

(6); 81 Federal Register (FR) 90738 (Dec. 15, 2016).

Finally, mitigation for the ACP Project on NFS

lands is described in Section 2.3.1 (“Mitigation”) of the

FEIS. This section in the FEIS identifies the

construction and restoration plans that apply to the

ACP project as required both by FERC and by the FS.

Specifically, the Construction, Operation, and

Maintenance Plan (COM Plan) is a series of

construction plans, procedures, and mitigation

measures that will be implemented on NFS lands. The

COM Plan will be attached to and made a part of the

SUP issued by the FS. The SUP is the administrative

instrument that will implement this ROD.

App-79

CHANGES FROM DRAFT EIS (DEIS) TO FEIS

In the DEIS, the proposed Forest Plan

amendments consisted of one part with two potential

modified standards for the MNF and six parts with

eight proposed modified standards and three potential

modified standards for the GWNF. One part of the

GWNF amendment was proposed to be a “plan-level”

amendment; that is, it would have applied not only to

the ACP Project but also any future projects within the

area covered by the applicable modified standard. The

amendment proposals were based on the knowledge

and anticipated effects of the proposed project at that

time.

Since the DEIS, we reviewed additional

information, recent revisions to our planning

regulations, and comments from the public on the

DEIS. Our review resulted in determining that two of

the standards considered in the DEIS (FW-243 and

11-019 in the GWNF LRMP) do not need to be

modified for the project. However, the FEIS includes

modification of four standards (SW03 and TE07 in the

MNF LRMP; FW-8 and 11-003 in the GWNF LRMP)

that were not considered for modification in the DEIS.

Another change addressed in the FEIS was that we no

longer proposed to reallocate 104.2 acres of land on the

GWNF to Management Area 5C – Designated Utility

Corridor, but instead will exempt the ACP linear ROW

from being reallocated to the 5C management

prescription (See FW-244 in Table 3 below).

With one exception, the public was notified of the

aforementioned changes to the proposed Forest Plan

amendments through a notice that was published in

the Federal Register on June 5, 2017 (82 FR 25756).

App-80

One standard (TE07 in the MNF LRMP relating to

threatened and endangered species) was not included

in the DEIS nor in the June 5 FR Notice. TE07 is

identified in the FEIS as a standard that needs

modification based on results of biological surveys

completed since the DEIS.

The net result of the aforementioned changes is

that the FEIS evaluated proposed project-specific

amendments consisting of two parts modifying four

standards in the MNF LRMP (See Table 2 below) and

six parts modifying ten standards in the GWNF LRMP

(see Table 3 below.) The FEIS acknowledged that the

results of surveys completed after the release of the

FEIS would determine the need to modify two of the

standards identified (TE07 and FW-85). The

applicable surveys have now been completed and from

that information, it has been determined that TE07

(in the MNF’s LRMP) will need to be modified, but

FW-85 (in the GWNF’s LRMP) will not need to be

modified.

We also reviewed analyses from Atlantic and

worked with them to develop project design features

and mitigation measures that are designed to protect

resources including soil, riparian, special status

species habitat, visual, and recreational resources.

The additional mitigation measures or project design

features relating to the proposed amended standards

are discussed in the FEIS, Chapter 4 and in Atlantic’s

COM Plan. As described in the FEIS in Section 2.3.1.2

(“General Forest Service Mitigation”), our intent is to

avoid or minimize adverse impacts on NFS lands. The

COM Plan outlines mitigation measures that are

referenced throughout Chapter 4 in the FEIS

App-81

describing how the measures minimize impacts to

NFS resources. The COM Plan underwent a number

of changes from the DEIS to FEIS as described in

Section 4 of the FEIS. By adopting the FERC-prepared

FEIS, all design features and mitigation measures

applicable to NFS lands are made a part of this

decision. Atlantic submitted an updated COM plan in

October 2017 which addressed Forest Service

comments and includes additional details on

mitigation measures to minimize impacts. The COM

Plan will be a requirement of the SUPs the Forest

Service issues to implement the project.

The Federal Register on June 5, 2017 (82 FR

25756) also informed the public of a change to the

administrative review procedures for the ACP Project.

By not designating the ACP permit area as a

Management Area 5C Utility Corridor on the GWNF,

we are no longer considering a plan-level amendment

and the requisite administrative review process under

36 CFR 219 is no longer applicable. For this decision,

all of the modified standards were project-specific and

therefore the administrative review procedures of 36

CFR 218 were followed. (See the “Administrative

Review/Objections”

section

below

for

more

information.)

UPDATES SINCE DRAFT ROD RELEASE

This ROD reflects a number of updates since the

Draft ROD was published on July 21, 2017. The

completion of additional biological and cultural

resource surveys; updates to supporting documents,

reports, and plans; completion of our pre-decision

administrative review; and actions by other federal

agencies have helped shape the ROD. Discussed in

App-82

more detail throughout this document, the major

items influencing the ROD are summarized here:

Atlantic submitted an updated Biological

Evaluation (BE) report on August 4, 2017. The

BE

assesses

impacts

and

identifies

conservation measures for avoiding or

minimizing impacts on Regional Forester

Sensitive Species (RFSS). The updated report

incorporated the results of additional field

surveys and FS comments. On November 16,

2017, the Forest Service accepted the BE but

made different determinations for three RFSS.

• Atlantic completed a survey of old growth

areas that would be impacted by the ACP

Project and provided the results to the Forest

Service on September 8, 2017. Upon review of

survey results, the FS determined that the

GWNF’s old growth standard does not need to

be modified is addressed in this ROD.

• On October 13, 2017, FERC issued a Certificate

to Atlantic 2 for authorization to construct and

operate the ACP Project, subject to a number of

environmental conditions designed to mitigate

the environmental impacts associated with

construction and operation of the ACP Project.

The FERC’s Certificate will be referenced

throughout this ROD.

• The US Fish and Wildlife Service (FWS)

provided a biological opinion (BO) to FERC on

October 16, 2017, which contained the FWS

review of the effects of the ACP Project on eight

•

2 Hereafter referred to as the “FERC’s Certificate”

App-83

•

•

•

•

•

federally listed threatened and endangered

species. It also provided reasonable and

prudent measures which Atlantic must

implement to minimize harm as required by the

Endangered Species Act (ESA).

Atlantic submitted an updated COM Plan on

October 24,

2017 which incorporated

clarifications, additional information and

addressed FS comments. The updated COM

Plan is available at: http://elibrary.FERC.gov/

idmws/filelist.asp?accession_num=201710275240

On October 27, 2017, the FS completed its predecision administrative review of public

objections that were filed after the Draft ROD

was released. Objectors received a collective

response letter that addressed issues raised in

their objections.

Atlantic completed a Phase II cultural resource

survey on sites in the GWNF and on November

1, 2017, the FS notified the Virginia

Department of Historic Resources that the

tested sites were determined to not be eligible

for listing on the NRHP.

FERC requested a Conference Opinion from the

FWS on the candy darter on November 9, 2017.

The FWS had recently proposed the candy

darter for listing as a threatened species under

the ESA. FERC’s request asks FWS to confirm

its provisional finding that the ACP Project is

not likely to jeopardize the candy darter.

We recognize a need for the public to stay

informed as new information is obtained and

the project progresses on the National Forests.

App-84

We will meet this obligation by posting on the

GWNF website for the ACP Project relevant

plans,

documents,

weekly

inspection/

monitoring reports, photos, and links to other

websites

(FERC,

Dominion

Energy

Transmission,

Inc.,

etc…)

containing

information about the project.

DECISION

DECISION

AND

RATIONALE

FOR

THE

Authorization of the use and occupancy of NFS

land

Based on our review of the FEIS and project

record, we are authorizing Atlantic to use and occupy

NFS land to construct, operate, maintain, and

eventually decommission a natural gas pipeline, the

ACP Pipeline Project, on NFS lands administered by

the MNF and GWNF. The construction phase of the

project on NFS lands will disturb approximately 430.4

acres of land, including the pipeline construction

right-of-way, additional temporary workspaces

(ATWS), and access roads. Following construction, 214

acres of NFS lands will be maintained and operated

for long-term use. The long-term use will include

approximately 56 acres of lands associated with the

proposed 5.1 mile pipeline corridor and associated

access roads for the ACP Project that crosses the MNF

in Pocahontas County, West Virginia; and

approximately 158 acres and 15.9 miles of pipeline

corridor on the GWNF in Highland, Bath, and

Augusta Counties, Virginia. See Figure 1. More

detailed maps of the pipeline route are found in

Appendix B of the FEIS. This authorization will be

App-85

implemented through the FS issuing two SUPs: l)a

temporary SUP for the construction of the ACP; and

2) a SUP for use and maintenance of the ACP for a

term of 30 years with an option to renew in accordance

with 36 CFR 251.64.

Our decision allows Atlantic to implement the

ACP Project in a manner consistent with the terms

and conditions of this decision.

Approval of Forest Plan amendments

Based on our review of the FEIS and project

record, we amend the MNF's LRMP as displayed in

Table 2 and the GWNF's LRMP as displayed in Table

3. As the Tables show, the plan amendments modify

certain plan standards relating to: Utility Corridors,

Soil and Riparian, Threatened and Endangered

Species, Eligible Recreational River Access,

Appalachian National Scenic Trail Area, and Scenic

Integrity Objectives. Modified plan amendment

language is in "bold" text in column 2 of the tables.

App-86

Figure 1 - Atlantic Coast Pipeline Route on the MNF

and GWNF.

Table 2. MNF Revised Land and Resource

Management Plan Amendment Specific to the ACP

Project

MNF

Forest

Plan Standards

as

Standards Prior to Modified for the ACP

Modifying for the ACP Project

Project

Part One - Soils

Standard SW06: Severe

rutting resulting from

management activities

shall be confined to less

than 5 percent of an

activity area.

Standard SW06: Severe

rutting resulting from

management activities

shall be confined to less

than 5 percent of an

activity area with the

exception

of

the

App-87

construction

of

Atlantic

Coast

Pipeline, where the

applicable mitigation

measures identified

in the COM Plan and

SUP

must

be

implemented.

Standard SW07: Use of

wheeled and/or tracked

motorized

equipment

may be limited on soil

types that include the

following

soil/site

conditions:

Steep Slopes (40 to

50 percent) – Operations

on these slopes shall be

analyzed on a case-bycase basis to determine

the best method of

operation

while

maintaining

soil

stability

and

productivity. Very Steep

Slopes (more than 50

percent)

–

Use

is

prohibited

without

recommendations from

interdisciplinary team

review and line officer

approval.

Standard SW07: Use of

wheeled and/or tracked

motorized

equipment

may be limited on soil

types that include the

following

soil/site

conditions with the

exception

of

the

construction

of

Atlantic

Coast

Pipeline, where the

applicable mitigation

measures identified

in the COM Plan and

SUP

must

be

implemented:

Steep Slopes (40 to

50 percent) – Operations

on these slopes shall be

analyzed on a case-bycase basis to determine

the best method of

operation

while

maintaining

soil

stability

and

App-88

Susceptible

to

Landslides – Use on

slopes greater than 15

percent

with

soils

susceptible to downslope

movement when loaded,

excavated, or wet is

allowed

only

with

mitigation

measures

during periods of freezethaw and for one to

multiple days following

significant

rainfall

events. If the risk of

landslides during these

periods

cannot

be

mitigated, then use is

prohibited.

productivity. Very Steep

Slopes (more than 50

percent)

–

Use

is

prohibited

without

recommendations from

interdisciplinary team

review and line officer

approval.

Susceptible

to

Landslides – Use on

slopes greater than 15

percent

with

soils

susceptible to downslope

movement when loaded,

excavated, or wet is

allowed

only

with

mitigation

measures

during periods of freezethaw and for one to

multiple days following

significant

rainfall

events. If the risk of

landslides during these

periods

cannot

be

mitigated, then use is

prohibited.

Soils Commonly Wet

At or Near the Surface

During a Considerable

Part of the Year or Soils

Highly Susceptible to

Compaction. Equipment

use shall normally be

prohibited or mitigated

when soils are saturated

Soils Commonly Wet

or when freeze-thaw At or Near the Surface

cycles occur.

During a Considerable

Part of the Year or Soils

Highly Susceptible to

Compaction. Equipment

use shall normally be

App-89

prohibited or mitigated

when soils are saturated

or when freeze-thaw

cycles occur.

Standard

SW03:

Disturbed

soils

dedicated to growing

vegetation

shall

be

rehabilitated

by

fertilizing,

liming,

seeding, mulching, or

constructing structural

measures as soon as

possible, but generally

within 2 weeks after

project completion, or

prior to periods of

inactivity, or as specified

in

contracts.

Rip

compacted sites when

needed for vegetative

reestablishment

and

recovery

of

soil

productivity

and

hydrologic function.

Standard

SW03:

Disturbed

soils

dedicated to growing

vegetation

shall

be

rehabilitated

by

fertilizing,

liming,

seeding, mulching, or

constructing structural

measures as soon as

possible, but generally

within 2 weeks after

project completion, or

prior to periods of

inactivity, or as specified

in

contracts.

Rip

compacted sites when

needed for vegetative reestablishment

and

recovery

of

soil

productivity

and

hydrologic function with

the exception of the

construction,

restoration,

and

rehabilitation

activities associated

with

the

Atlantic

Coast Pipeline where

the

applicable

mitigation measures

App-90

identified in the COM

Plan and SUP must be

implemented.

Part 2 - Threatened and Endangered Species

Standard TE07: Special

use permits may be

authorized

in

TEP

[Threatened,

Endangered, Proposed]

species habitat if the

uses do not adversely

affect populations or

habitat. This standard

does not apply to Indiana

bat or running buffalo

clover. See special use

direction

for

these

species, [in the MNF

LRMP].

Standard TE07: Special

use permits may be

authorized

in

TEP

species habitat if the

uses do not adversely

affect populations or

habitat. However, this

requirement will not

apply to the Atlantic

Coast

Pipeline

Construction SUP for

the northern longeared bat and small

whorled

pogonia

where the applicable

mitigation measures

identified in the COM

Plan and SUP must be

implemented.

This

standard does not apply

to

Indiana

bat

or

running buffalo clover.

App-91

Table 3: GWNF Land and Resource Management Plan

Amendment Specific to the ACP Project

GWNF Forest Plan Standard as Modified

Standard Prior to for the ACP Project

Modification for the

ACP Project

Part 1 - Utility Corridors

Standard

FW-244:

Following evaluation of

the

above

criteria,

decisions

for

new

authorizations outside of

existing corridors and

designated

communication sites will

include an amendment

to the Forest Plan

designating them as

Prescription Area 5B or

5C

(Note: Use of the phrase

“above criteria” in this

standard

refers

to

criteria in other Plan

standards related to

utility corridors.)

Standard

FW

244:

Following evaluation of

the

above

criteria,

decisions

for

new

authorizations outside of

existing corridors and

designated

communication sites will

include an amendment

to the Forest Plan

designating them as

Prescription Area 5B or

5C with the exception

of the operational

right-of-way for the

Atlantic

Coast

Pipeline.

Part 2 - Soil and Riparian

Standard FW-5: On all

soils

dedicated

to

growing vegetation, the

organic layers, topsoil

and root mat will be left

Standard FW-5: On all

soils

dedicated

to

growing vegetation, the

organic layers, topsoil

and root mat will be left

App-92

in place over at least 85%

of the activity area and

revegetation

is

accomplished within 5

years.

in place over at least 85%

of the activity area and

revegetation

is

accomplished within 5

years,

with

the

exception

of

the

operational right-ofway

and

the

construction zone for

the Atlantic Coast

Pipeline, where the

applicable mitigation

measures identified

in the approved COM

Plan and SUP must be

implemented.

Standard FW-8: Water

saturated

in

areas

expected to produce

biomass

should

not

receive vehicle traffic or

livestock trampling to

prevent excessive soil

compaction.

Standard FW-8: Water

saturated

in

areas

expected to produce

biomass

should

not

receive vehicle traffic or

livestock trampling to

prevent excessive soil

compaction, with the

exception

of

the

operational right-ofway

and

the

construction zone for

the Atlantic Coast

Pipeline, where the

applicable mitigation

measures identified

in the approved COM

App-93

Plan and SUP must be

implemented.

Standard

FW-16:

Management activities

expose no more than 10%

mineral soil in the

channeled

ephemeral

zone.

Standard

FW-16:

Management activities

expose no more than 10%

mineral soil in the

channeled

ephemeral

zone,

with

the

exception

of

the

operational right-ofway

and

the

construction zone for

the Atlantic Coast

Pipeline, where the

applicable mitigation

measures identified

in the COM Plan and

SUP

must

be

implemented.

Standard FW-17: In

channeled

ephemeral

zones, up to 50% of the

basal area may be

removed down to a

minimum basal area of

50 square feet per acre.

Removal of additional

basal area is allowed on

a case-by-case basis

when needed to benefit

riparian

dependent

resources

Standard FW-17: Up to

50% of the basal area

may be removed, down to

a minimum basal area of

50 square feet per acre.

Removal of additional

basal area is allowed on

a case-by-case basis

when needed to benefit

riparian-dependent

resources, with the

exception

of

the

operational right-ofway

and

the

App-94

construction zone for

the Atlantic Coast

Pipeline, where the

applicable mitigation

measures identified

in the COM Plan and

SUP

must

be

implemented.

Standard

11-003:

Management activities

expose no more than 10

percent mineral soil

within the project area

riparian corridor

Standard

11-003:

Management activities

expose no more than 10

percent mineral soil

within the project area

riparian corridor, with

the exception of the

operational right-ofway

and

the

construction zone for

the Atlantic Coast

Pipeline, where the

applicable mitigation

measures identified

in the COM Plan and

SUP

must

be

implemented

Part 3 - Appalachian National Scenic Trial Crossing

Standard

4A-025:

Locate

new

public

utilities and rights-ofway in areas of this Rx

area

where

major

impacts already exist.

Limit linear utilities and

Standard 4A-025: Locate

new public utilities and

rights-of-way in areas of

this Rx area where major

impacts already exist,

with the exception of

the Atlantic Coast

App-95

rights-of-way to a single Pipeline right-of-way.

crossing of the Rx area Limit linear utilities and

rights-of-way to a single

per project.

crossing of the Rx area

per project.

Part 4 - Management Prescription 2C3 Eligible

Recreational River Area

2C3-015: Allow road

construction

or

reconstruction

to

improve

recreational

access, improve soil and

water, to salvage timber,

or to protect property or

public safety.

Standard 2C3-015: Allow

road construction or

reconstruction

to

improve

recreational

access, improve soil and

water, to salvage timber,

or to protect property or

public safety, and to

reconstruct FR 281 for

the Atlantic Coast

Pipeline, where the

applicable mitigation

measures identified

in the COM Plan and

SUP

must

be

implemented.

Part 5 - Scenic Integrity Objectives

Standard FW-182: The

Forest SIOs [Scenic

Integrity Objectives] are

met for all new projects

(including special uses).

Existing conditions may

not currently meet the

assigned SIO.

Standard FW-182: The

Forest SIOs are met for

all

new

projects

(including special uses),

with the exception of

the Atlantic Coast

Pipeline right-of-way.

The ACP ROW must

meet the established

App-96

SIOs within five years

after completion of

the

construction

phase of the project

for areas identified in

the COM Plan and

SUP, except for the

immediate

foreground of the

Shenandoah

Mountain

Trail

crossing where the

project must meet the

SIO of Low. Existing

conditions

may

not

currently

meet

the

assigned SIO.

Terms and Conditions

This decision will require compliance with the

following measures as special terms and conditions of

the special use permits:

1. Atlantic shall implement the ACP Project in

compliance with the October 2017 version of the

Construction, Operations and Maintenance Plan.

2. Atlantic shall comply with its proposal as described

in its submission to the Forest Service dated

October 17, 2017 regarding use of and

improvements to FR 281 (Campbell Hollow Road).

3. Atlantic shall implement the conservation

measures of the August 2017 version of the

Biological Evaluation

App-97

4. Atlantic shall comply with applicable provisions of

Appendix A – Environmental Conditions of FERC’s

Order Issuing Certificate; Docket Nos CP15-554000 and CP15- 554-001 (Issued October 13, 2017)

5. Atlantic shall not begin activities with the

potential to impact any eligible historic properties

on NFS lands until all signatories have signed the

Programmatic Agreement for compliance with the

National Historic Preservation Act for the ACP

Project and any required cultural resource

treatment plans for sites on NFS lands have been

completed.

6. Atlantic shall comply with applicable provisions of

the Reasonable and Prudent Measures and Terms

and Conditions of the USFWS Biological Opinion

(BO) for the ACP Project. In addition, Atlantic will

also comply with the BO’s Monitoring and

Reporting Requirements for the rusty patched

bumble bee and the Indiana bat to the extent

applicable to NFS land.

7. Atlantic shall not begin activity on NFS land that

may impact candy darter habitat until the USFWS

provides FERC with a non-jeopardy determination

for the species. The FS will not authorize activity

that could impact candy darter habitat until the

aforementioned condition is satisfied.

8. Atlantic shall obtain West Virginia and Virginia

Clean Water Act Section 401 Certifications (or

waivers thereof) before beginning activity on NFS

land that may impact waters of the U.S.

9. Atlantic shall obtain and comply with the Erosion

and Sediment Control Plan as approved by the

App-98

Virginia DEQ before beginning construction on

NFS land.

10. Atlantic shall obtain and comply with the

Stormwater Pollution Prevention Plan as approved

by the Virginia DEQ before beginning construction

on NFS land.

11. Atlantic shall obtain and comply with the Erosion

and Sediment Control Plan as approved by the

West Virginia DEP before beginning construction

on NFS land.

12. Where mechanical removal of timber products is

employed, merchantable material will be removed

from NFS lands in accordance with provisions of

Timber Sale Contract.

13. Atlantic shall provide a timber removal plan that

addresses access road improvements for Forest

Service approval prior to removing timber.

14. In addition to consideration of areas where safe

removal of timber is not reasonable, on the GWNF

merchantable timber will not be required to be

removed on lands that are less than or equal to site

index 40, slopes greater than 55%, and forest types

not equal to 48, 53, 56, and 81.

15. On the GWNF, forwarders and/or shovel loggers

may be utilized on slopes from 35% to 45%. Skyline

and/or helicopters may be used on slopes steeper

than 35%, but are required on slopes steeper than

45%.

16. Where windrows are necessary and do not conflict

with the COM Plan, windrowed slash shall be

limited to 8-foot-high, 20- foot-wide, and 100-footlong with 50-foot breaks between the windrows to

App-99

allow for movement

construction corridor.

of

wildlife

across

the

17. Atlantic will mitigate for the loss of habitat for

threatened, endangered, and sensitive bats on

MNF with a combination of tree-snagging and

installation of bat box (rocket box) clusters along

the edge of disturbance (within the temporary

workspace) following construction. These efforts

shall include suitable replacement habitat for the

loss of potential optimal roost trees (i.e., all

shagbark hickory greater than 5 inches DBH and

any snags cut within the construction right-ofway), shall be focused in those affected areas, and

specific locations guided by coordination with the

MNF. The installed boxes shall be monitored

annually for a minimum of three years to ensure

proper installation and assess efficacy in providing

roosting habitat in the impacted area.

18. No surface-disturbing activity would occur on NFs

lands as part of the crossing under the

Appalachian National Scenic Trail.

19. Wild brook trout activity timing restrictions of

October 1 to March 31 shall be applied to stream

crossings saua427p, saua428, and saua429.

20. Any adjustments to stream buffers must be

approved by the Forest Service prior to any work

in the area that is proposed for adjustment.

21. To reduce movement barriers to small animals,

protective barriers for wetlands shall substitute

filter stocks wherever silt fences would ordinarily

be used.

App-100

22. Atlantic shall employ the COM Plan feathering

vegetation clearing technique at the following

milepost locations to minimize impacts to visually

sensitive areas:

73.3-73.6

78.0-78.3

80.35-80.85

81.25-81.32

82.6-84.7

93.7-94.2

98.65-98.75

105.9-106.0

115.8-116.2

116.5-120.5

121.0-123.2

154.0-155.1

23. Atlantic shall identify trees to be retained for

feathering purposes and protected during

construction by clearly marking with flagging or

safety fencing.

24. Atlantic shall have a landscape architect onsite to

monitor for activities pertaining to scenery

including but not limited to feathered construction

right-of-way edges, and monitoring growth of

vegetation from a variety of viewpoints to assure

scenic integrity objectives are met within five

years.

25. Atlantic shall employ enhanced restoration

techniques of the permanent ROW at the

aforementioned mileposts to include a planting

configuration that transitions from the outside

edges to the center with small, shallow rooted

trees, then shrub species, then a minimum 10-foot

herbaceous strip centered over the pipe. Atlantic

shall coordinate with the FS on details of planting

prior to implementing restoration. The width and

frequency of mowing within the ROW will be

determined by the FS following completion of

planting.

App-101

26. Atlantic shall monitor herbaceous vegetation used

for stabilization at least quarterly for three years

after restoration is completed. Post-construction

and post-disturbance monitoring for tree and

shrub vegetation will be conducted annually for the

first five growing seasons following the initial

revegetation effort, and at five-year intervals

thereafter, for the life of the Project on the NFS

lands. Written reports, including photographs, will

be submitted to the Forest Service following each

monitoring cycle.

27. Any proposed substitutes for the ProGanics and

Flexterra soil supplements must be approved by

the Forest Service prior to use.

28. Atlantic shall conduct bleeder drain water quality

monitoring monthly to identify if there are

seasonal variability in parameters.

29. Atlantic shall install twelve-inch diameter (or

larger) compost filter socks at the outlet of slope

breakers to control sediment transport until

vegetation becomes established.

30. Atlantic shall employ standard industry standard

industry practices to ensure backfill, compaction,

and restoration activities occur only during

suitable soil moisture content conditions.

31. Atlantic shall submit Site Specific Designs (SSDs)

for the remaining eight steep slope sites identified

by the FS in its letter dated October 24, 2016. Each

respective SSD must be submitted to the FS a

minimum of 30 days in advance before beginning

work at the involved site. Each SSD will be

certified by a registered professional engineer or

engineering geologist with experience using

App-102

engineering geologic information in steep slope

design and construction of this type of facility.

Qualified professionals, including an engineering

geologist and a geotechnical engineer, will also

monitor construction activities at sites on NFS

lands to oversee implementation of design and

address unforeseen circumstances.

32. Prior to construction, Atlantic will provide FS with

all outstanding geotechnical studies and status of

Best in Class (BIC) program team analysis relating

to operations on NFS lands. At least 30 days prior

to the start of construction for a spread with slopes

greater than 30% and over 100 foot long, Atlantic

will notify FS. The notification will include the

anticipated start date, location based on mileposts,

and estimated duration of the construction

activities for that spread. The holder will

participate in pre-construction conference with FS.

33. Atlantic will immediately notify the FS of a slope

failure on NFS land during construction. Atlantic

shall use qualified professionals, including a

geotechnical engineer and an engineering

geologist, to assess the nature and extent of the

slope failure (including the potential for off-site

impacts) and to a develop remediation plan for

review and approval by the FS.

34. Atlantic shall provide access road designs for FS

review and approval at least 30 days prior to any

activity on the roads. In addition to construction

and improvements, designs shall also include plans

for deconstructing and restoring roads to their

prior maintenance standard within six months

after pipeline construction has been completed. No

App-103

use or improvement of roads shall occur until any

corrections required by the FS have been made and

FS approval of designs has been granted.

35. Atlantic shall provide legal access to the FS on any

roads that cross private land in the course of

accessing NFS land for purposes of administering

this project.

36. Atlantic

shall

inspect,

at

a

frequency

commensurate with weather conditions, temporary

erosion and sedimentation control features

installed within 250 feet of identified RFSS habitat

to ensure proper function of the feature.

37. Atlantic shall implement the following protections

for the potential hibernaculum near FR 1026:

a.

No trees shall be cut within 200’ of the

hibernaculum, except where public or worker

safety concerns require it;

b.

Explosives shall not be used within 200 feet of

the hibernaculum, unless the Forest Service

concurs that this activity will not have an

adverse effect on bat populations or habitat.

Explosives outside of these areas shall not be

used when such use has potential to damage

the cave or disturb the bats;

c.

Any road work (e.g., upgrades, maintenance)

within 200’ of the hibernaculum shall occur

outside the hibernacula period (Nov 15-March

31); and

d.

No entry into the cave is allowed. Ensure that

all personnel working on site are made aware

of this restriction.

App-104

38. If active northern goshawk nests are found in the

project area during tree clearing and other

construction activities, Atlantic shall notify the FS

for direction on appropriate course of action.

39. If active long-eared owl nests are found in the

project area during tree clearing and other

construction activities, Atlantic shall notify the FS

for direction on appropriate course of action.

40. Prior to construction, provide analysis of new

RFSS that were added to the MNF’s RFSS list in

October, 2017. Include effect determinations and

any avoidance, minimization, and mitigation

needed to meet Forest Plan direction.

41. Atlantic shall perform additional surveys in

suitable habitats near the project area for

populations of Roan Mountain sedge, Appalachian

oak fern, and white alumroot to improve size and

abundance data for the species.

Decision Rationale

Based on the analysis provided by FERC in the

FEIS, we are authorizing Atlantic to use and occupy

NFS lands for the ACP Project, and approve projectspecific amendments for the MNF and GWNF LRMPs

as described above, because our decision:

•

•

•

Can be implemented with limited adverse

impacts and will not impair the overall longterm productivity of NFS lands;

Meets the requirements of Forest Service

planning and special use regulations (36 CFR

Part 219 and Part 251 Subpart B);

Meets the purpose and need of the project to

transport natural gas to serve the growing

App-105

•

•

energy needs of multiple public utilities and

local distribution companies in Virginia and

North Carolina;

Has been developed through an extensive

public involvement and collaboration effort

with

our

publics,

partners,

adjacent

landowners, and other agencies; and

Is consistent with other Federal policy.

Rationale by Topic Area

Long-term productivity of NFS lands

The FERC analysis in the FEIS concludes that

implementation of the ACP Project will result in

limited adverse environmental impacts, noting an

increased potential for: project-induced landslides on

steep slopes; long term impacts related to slope

instability adjacent to waterbodies (impacting water

quality, stream channel geometry, and downstream

aquatic biota); creation of additional forest edge

habitat through fragmentation; and significant

impacts associated with karst, cave, subterranean

habitat, and the species associated with subterranean

habitat. (FEIS, Sections 4 and 5). We recognize that

the ACP Project will directly impact resources, though

mostly in the area disturbed by construction. The

extent of these impacts will occur within the 430-acre

construction phase footprint on the MNF and the

GWNF, which is a small percentage of their nearly two

million-acre total land base. The greatest potential for

impact will be during the estimated 18-month

construction phase, with impacts diminishing as

reclamation is completed. Because of the adverse

environmental impacts, we are requiring a broad

spectrum of mitigation measures for the ACP Project.

App-106

Therefore through application of mitigation and the

limited extent of the project, long-term productivity of

NFS lands will be maintained.

The SUPs issued by the FS will be subject to

required terms, conditions, and mitigation described

throughout the FEIS (particularly Sections 2.3.1. and

4.8.9 and the COM Plan) and highlighted in the

“Terms and Conditions” section of this ROD. Measures

to avoid or minimize environmental harm that are

incorporated in this decision include forestwide LRMP

standards and guidelines, which at a minimum meet

all requirements of applicable laws, regulations, State

standards, and additional standards and guidelines

for the affected NFS lands.

Adverse effects of pipeline construction will be

mitigated through measures proposed by Atlantic and

through measures required by FERC’s Certificate, the

FWS’s BO, and FS SUPs, as well as other agencies’

permits and plans. Singularly and collectively, they

avoid, rectify, reduce, or eliminate potential adverse

environmental impacts to NFS lands. The listing of

Construction and Restoration Plans that are

applicable to the ACP Project, taken from FEIS, Table

2.3.1-1, are displayed in Table 4 below. Readers should

note that there may be updates to the documents and

their associated website links shown in Table 4. Refer

to

FERC’s

eLibrary

webpage

(https://www.ferc.gov/docs-filing/elibrary.asp)

and

search by Docket Number CP15-554 for the latest

information if any of the links provided are no longer

valid.

App-107

Table 4: Construction and

Applicable to ACP Project

General Plan Name

Restoration

Plans

Location of Plan

Upland

Erosion The FERC Plan and

Control, Revegetation, Procedures can both be

and Maintenance Plan viewed on the FERC

Internet

website

at

Wetland and

https://www.ferc.gov/

Waterbody

industries/gas/enviro/

Construction and

guidelines.asp

Mitigation Procedures

Atlantic’s

proposed FERC

Accession

No.

modifications to FERC 20170526-5257. PDF file:

https://elibrary_ferc.

Plan and Procedures

gov/idmws/common/Open

Nat.asp?fileID=14598802

Restoration

and EIS Appendix F

Rehabilitation Plan

Construction,

EIS Appendix G

Operation,

and

Maintenance Plan

Horizontal Directional EIS Appendix H1

Drill Drilling Fluid

Monitoring, Operations,

and Contingency Plan

Contingency Plan for EIS Appendix H2

the Proposed Crossing

of the Appalachian

National Scenic Trial

and

Blue

Ridge

Parkway

App-108

Site-Specific

Crossing Plans

HDD EIS Appendix H3

Karst

Terrain EIS Appendix I

Assessment,

Construction,

Monitoring,

and

Mitigation Plan

Residential

Construction Plans

EIS Appendix J1

Site-Specific Crossing EIS Appendix J2

Plan for the James

River

Wildlife

Management Area

Spill

Prevention,

Control,

and

Countermeasures Plan

(SPCC Plan)

FERC

Accession

No.

20160718-5164. PDF file:

http://elibrary.ferc.gov/

idmws/common/OpenNat.

asp?fileID=14311323

Timber Removal Plan

FERC

Accession

No.

20160718-5164. PDF file:

http://elibrary.ferc.gov/

idmws/common/OpenNat.

asp?fileID=14311323

Stormwater Pollution

Prevention Plans (SHP;

AP-1 [WV]; AP-2 [NC];

remaining facility plans

are pending)

FERC

Accession

No.

20170609-5196. PDF file:

https://elibrary.ferc.gov/

idmws/file_list.asp?

accession_num=20170609

-5196

Contaminated

Plan

Media FERC

Accession

No.

20160718-5164. PDF file:

http://elibrary.ferc.gov/

App-109

idmws/common/OpenNat.

asp?fileID=14311323

Traffic

and FERC

Accession

No.

Transportation

20160718-5164. PDF file:

http://elibrary.ferc.gov/

Management Plan

idmws/common/OpenNat.

asp?fileID=14311323

Non-Native

Invasive FERC

Accession

No.

Plant

Species 20161115-5160. PDF file:

http://elibrary.ferc.gov/

Management Plan

idmws/common/OpenNat.

asp?fileID=14399112

Blasting Plan

FERC

Accession

No.

20161109-5138. PDF file:

http://elibrary.ferc.gov/

idmws/common/OpenNat.

asp?fileID=14395436

Slope Stability Policy FERC

Accession

No.

20170127-51202.

PDF

and Procedure

file:

http://elibrary.ferc.gov/

idmws/common/OpenNat.

asp?fileID=14475036

Winter

Plan

Construction FERC

Accession

No.

20170127-5202. PDF file:

http://elibrary.ferc.gov/

idmws/common/OpenNat.

asp?fileID=14475037

Plans for Unanticipated FERC

Accession

No.

Discovery of Historic 20160718-5164. PDF file:

Properties or Human http://elibrary.ferc.gov/

Remains

During

App-110

Construction

(ACP: idmws/common/OpenNat.

West Virginia, Virginia, asp?fileID=14311323

North Carolina, SHP:

West

Virginia,

Pennsylvania

Unanticipated

Discoveries Plans for

Cultural Resources and

Human Remains Policy

(MNF and GWNF)

FERC

Accession

No.

20170512-5163. PDF file:

http://elibrary.ferc.gov/

idmws/common/OpenNat.

asp?fileID=14588372

Migratory Bird Plan

FERC

Accession

No.

20170505-5036. PDF file:

http://elibrary.ferc.gov/

idmws/common/OpenNat.

asp?fileID=14582932

Fire Prevention

Suppression Plan

Open Burning Plan

and FERC

Accession

No.

20170127-5202. PDF file:

http://elibrary.ferc.gov/

idmws/common/OpenNat.

asp?fileID=14475038

FERC

Accession

No.

20160701-5255. PDF file:

http://elibrary.ferc.gov/

idmws/common/OpenNat.

asp?fileID=14295967

Fugitive Dust Control FERC

Accession

No.

20160718-5164. PDF file:

and Mitigation Plan

http://elibrary.ferc.gov/

idmws/common/OpenNat.

asp?fileID=14311323

Protected

Snake FERC

Accession

201607295-5256.

Conservation Plan

No.

PDF

App-111

file:

http://elibrary.ferc.gov/

idmws/common/OpenNat.

asp?fileID=14319660

Virginia

Relocation Plan

Fish FERC

Accession

No.

20160816-5051. PDF file:

http://elibrary.ferc.gov/

idmws/common/OpenNat.

asp?fileID=14330185

North Carolina Revised

Fish and Other Aquatic

Taxa Collection and

Relocation Protocol for

Instream Construction

Activities

FERC

Accession

No.

20170310-5157. PDF file:

http://elibrary.ferc.gov/

idmws/common/OpenNat.

asp?fileID=14515832

The following paragraphs and other sections of

this ROD discuss how impacts to Forest resources

would be mitigated to the extent practical. Impacts

and mitigation relating to Forest resources that are

the subject of the LRMP amendments are discussed in

the “Compliance with 36 CFR 219 Applicable

Substantive Provisions” section of this ROD.

Additional discussion of impacts and mitigation is also

contained in the “Findings Required by Other Laws,

Regulations, and Policy” section of this ROD.

Sustainability of surface and groundwater

resources was considered in our decision. Landslide

potential and slope instability concerns, soil erosion,

stream crossings, and karst topography are activities

associated with this project that could potentially

impact water quality. The ACP will be installed under

17 perennial, 28 intermittent, and 11 ephemeral

waterbodies on NFS lands. It will also cross about 2.4

App-112

miles of karst topography on the Forests.

Sedimentation modeling indicates annual soil loss will

be 200 to 800 percent above baseline erosion during

the first year of construction, returning to preconstruction levels within 5 years following

restoration. Water for hydrostatic testing of the

pipeline will not come from, or be discharged on, NFS

lands. Pipeline construction activities affecting

surface waters would be conducted in accordance with

Atlantic’s construction and restoration plans, along

with conditions that are part of other federal or state

water approvals. Atlantic will implement the Spill

Prevention, Control, and Countermeasure Plan and

the Karst Mitigation Plan to minimize impacts on

karst systems and protect groundwater quality. We

agree with the FERC’s conclusion that with these

measures, along with our additional recommended

mitigation measures, impacts on groundwater and

surface waters will be effectively minimized or

mitigated, and will be largely temporary in duration.

Restoration and revegetation of disturbed areas will

be completed in accordance with federal and

state/commonwealth permits, the FERC Plan and

Procedures, and the COM Plan that will be approved

and incorporated as a requirement into the SUPs.

Acknowledging that revegetation of steep slopes is

made more challenging due to soil erosion by water,

Section

5.6

of

Atlantic’s

Restoration

and

Rehabilitation Plan (FEIS Appendix F) describes the

methods that will be used to establish vegetation in

steep slope areas. Post-construction monitoring will

also be required to assure successful re-establishment

of vegetation and stability of upland soils and slopes

that drain to surface waters.

App-113

Sustainability of wildlife species and their

habitats was considered in our decision. The ACP

Project’s impacts to wildlife will vary depending on the

habitat requirements of each species and the existing

habitat present within the project area. The FEIS

concludes that despite the mitigation measures,

forested areas would experience long-term to

permanent significant impacts as a result of

fragmentation.

The

landscape

context

of

fragmentation is of particular concern to the FS. The

fragmentation of larger blocks, as is often the case on

NFS lands, may have an impact on habitat quality

potential of the entire patch thus affecting a much

larger amount of interior forest than a direct

measurement of acreage cleared. These effects will

diminish after construction, and some wildlife could

return to the newly disturbed areas and adjacent,

undisturbed habi

This text is long and has been trimmed here. Open the source document for the complete record.

This is a copy of a public record, reproduced as it was published. It is not legal advice, and it may not be the version a court would rely on. Check the official source before you cite it.

A word about cookies

We need a few to keep you signed in and the library working. The rest help us see which pages people use and where they get stuck. They stay off unless you say yes.

Petition for Writ of Certiorari — Atlantic Coast Pipeline, LLC, Petitioner v. Cowpasture River Preservation Association, et al. | Frix