Petition for Writ of Certiorari — Delaware Riverkeeper Network, et al., Petitioners v. Secretary, Pennsylvania Department of Environmental Protection, et al.

Supreme Court briefJan 9, 2019

Ask Donna

What actually matters in this document.

Text

APPENDIX

i

APPENDIX

TABLE OF CONTENTS

Appendix A Opinion in the United States Court of

Appeals for the Third Circuit

(September 4, 2018) . . . . . . . . . . . App. 1

Appendix B Opinion and Order on the Termination

of the Above-Captioned Appeal in the

Commonwealth of Pennsylvania

Environmental Hearing Board

(June 2, 2017) . . . . . . . . . . . . . . . App. 27

Appendix C Opinion and Order on Request to

Dismiss in the Commonwealth of

Pennsylvania Environmental Hearing

Board

(May 10, 2017) . . . . . . . . . . . . . . App. 38

Appendix D Pennsylvania Bulletin, Vol. 46, No. 17,

Water Quality Certification under

Section, 401 of the Federal Clean

Water Act for the Atlantic Sunrise

Pipeline Project

(April 23, 2016) . . . . . . . . . . . . . App. 48

Appendix E Order Denying Petition for Rehearing

by the Panel Court En Banc in the

United States Court of Appeals for the

Third Circuit

(October 11, 2018) . . . . . . . . . . . App. 55

App. 1

APPENDIX A

PRECEDENTIAL

UNITED STATES COURT OF APPEALS

FOR THE THIRD CIRCUIT

Nos. 16-2211, 16-2212, 16-2218, 16-2400

[Filed September 4, 2018]

__________________________________________

DELAWARE RIVERKEEPER

)

NETWORK; DELAWARE RIVERKEEPER )

MAYA VAN ROSSUM,

)

Petitioners No. 16-2211

)

)

LANCASTER AGAINST PIPELINES,

)

Petitioner No. 16-2212

)

)

GERALDINE NESBITT,

)

Petitioner No. 16-2218

)

)

SIERRA CLUB,

)

Petitioner No. 16-2400

)

)

v.

)

)

SECRETARY PENNSYLVANIA

)

DEPARTMENT OF ENVIRONMENTAL

)

PROTECTION; PENNSYLVANIA

)

DEPARTMENT OF ENVIRONMENTAL

)

PROTECTION,

)

Respondents

)

)

App. 2

Transcontinental Gas Pipe Line

)

Company, LLC,

)

Intervenor Respondent

)

_________________________________________ )

On Petition for Review of an Order

of the Pennsylvania Department of

Environmental Protection

(FERC No. CP-15-138-000)

Argued November 7, 2017

Before: JORDAN, HARDIMAN, and SCIRICA,

Circuit Judges

(Filed: September 4, 2018)

Aaron J. Stemplewicz [Argued]

Delaware Riverkeeper Network

925 Canal Street, Suite 3701

Bristol, PA 19007

Attorney for Petitioners Delaware Riverkeeper

Network and Delaware Riverkeeper Maya Van

Rossum

Mark L. Freed [Argued]

Jordan B. Yeager

Curtin & Heefner

2005 South Easton Road, Suite 100

Doylestown, PA 18901

Attorneys for Petitioners Lancaster

Pipelines and Geraldine Nesbitt

Against

App. 3

Diana A. Csank

Zachary M. Fabish

Sierra Club Environmental Law Program

50 F Street NW, 8th Floor

Washington, DC 20001

Attorneys for Petitioner Sierra Club

Alexandra C. Chiaruttini

Margaret O. Murphy

Pennsylvania Department of Environmental Protection

400 Market Street, P.O. Box 8469

Harrisburg, PA 17105

Joseph S. Cigan, III [Argued]

Pennsylvania Department of Environmental Protection

2 Public Square

Wilkes-Barre, PA 18701

Curtis C. Sullivan

Pennsylvania Department of Environmental Protection

909 Elmerton Avenue, 3rd Floor

Harrisburg, PA 17110

Jesse C. Walker

Pennsylvania Office of Attorney General

Department of Environmental Resources

P.O. Box 8464

Harrisburg, PA 17105

Attorneys for Respondents

Andrew T. Bockis

Saul Ewing Arnstein & Lehr

2 North Second Street

Penn National Insurance Plaza, 7th Floor

Harrisburg, PA 17101

App. 4

Pamela S. Goodwin

Saul Ewing Arnstein & Lehr

650 College Road East, Suite 4000

Princeton, NJ 08540

Patrick F. Nugent

John F. Stoviak [Argued]

Saul Ewing Artnstein & Lehr

1500 Market Street

Centre Square West, 38th Floor

Philadelphia, PA 19102

Elizabeth U. Witmer

Saul Ewing Arnstein & Lehr

1200 Liberty Ridge Drive, Suite 200

Wayne, PA 19087

Attorneys for Intervenor Respondent

____________

OPINION OF THE COURT

____________

HARDIMAN, Circuit Judge.

These consolidated petitions for review concern the

Atlantic Sunrise Project, an expansion of the naturalgas distribution network owned by Intervenor

Transcontinental Gas Pipe Line Company (Transco). At

issue is a decision of the Pennsylvania Department of

Environmental Protection (PADEP or the Department)

granting Atlantic Sunrise a Water Quality Certification

under Section 401 of the Clean Water Act, 33 U.S.C.

§ 1341(a)(1).

In addition to their challenge to the merits of

PADEP’s decision to grant the Water Quality

Certification, Petitioners raise an important

App. 5

jurisdictional question we left open in Delaware

Riverkeeper Network v. Secretary of Pennsylvania

Department of Environmental Protection (Riverkeeper

II), 870 F.3d 171, 178 (3d Cir. 2017): whether our

exclusive jurisdiction under the judicial review

provisions of the Natural Gas Act, 15 U.S.C. § 717r(d),

requires finality and how such a requirement would

interact with Pennsylvania’s administrative scheme.

For the reasons that follow, we hold that we have

jurisdiction over the petitions and that Petitioners’

challenges fail on the merits.

I

A

We begin with a brief overview of the regulatory

background. The Natural Gas Act prohibits

construction or operation of a natural gas pipeline

without a Certificate of Public Convenience and

Necessity from the Federal Energy Regulatory

Commission (FERC). 15 U.S.C. § 717f(c)(1)(A). And

since many other federal laws and regulations apply to

pipeline projects, FERC often requires a showing of

compliance with those other mandates as part of its

permitting process. See id. § 717f(e) (authorizing FERC

to grant Certificates subject to “reasonable terms and

conditions”). FERC did so here, preventing Transco

from starting construction on Atlantic Sunrise until it

demonstrates “that it has received all applicable

authorizations required under federal law.”

Transcontinental Gas Pipe Line Co, LLC (Transco), 158

F.E.R.C. ¶ 61125, at App. C ¶ 10 (2017).

One such authorization is a discharge permit under

Section 404 of the Clean Water Act. 33 U.S.C.

App. 6

§ 1344(a). Because obtaining a Section 404 permit is a

federal requirement and the construction and operation

of Atlantic Sunrise “may result in a[] discharge into . . .

navigable waters,” Transco must also comply with

Section 401 of the Clean Water Act. Id. § 1341(a)(1).

Section 401 requires permit applicants to obtain “a

certification from the State in which the discharge . . .

will originate . . . that any such discharge will comply

with” that State’s water-quality standards. Id. Because

of these statutory requirements, Transco had to obtain

a Water Quality Certification from PADEP before

FERC would approve the pipeline project.

B

In an attempt to satisfy the obligations just

described, in the spring of 2015 Transco applied both to

FERC for a Certificate of Public Convenience and

Necessity and to PADEP for a Water Quality

Certification. Shortly thereafter, PADEP published

notice in the Pennsylvania Bulletin (Pennsylvania’s

answer to the Federal Register) of its intent to grant

Transco a Water Quality Certification. After a public

comment period, the Department certified in April

2016 that Atlantic Sunrise would comply with

Pennsylvania’s water-quality standards if it satisfied

certain conditions. Three of those conditions are

relevant here, requiring Transco to obtain the following

from PADEP:

1. a permit under the National Pollutant

Discharge Elimination System, 25 PA. CODE

§§ 92a.1–.104, covering the discharge of

water during hydrostatic pipeline testing;

App. 7

2. a permit under Chapter 102 of PADEP’s own

regulations, 25 PA. CODE §§ 102.1–.51,

covering erosion and sediment disturbance

associated with pipeline construction; and

3. a permit under Chapter 105 of the

Department’s regulations, 25 PA. CODE

§§ 105.1–.449, covering obstructions of and

encroachments on Pennsylvania waters.

In response to PADEP’s notice, Petitioners

immediately filed two parallel challenges to the

approved Water Quality Certification. First, they

sought relief directly from this Court under the

exclusive review provision of the Natural Gas Act, 15

U.S.C. § 717r(d)(1). Second, three of the petitioners also

appealed PADEP’s decision to the Pennsylvania

Environmental Hearing Board (EHB or the Board).1

The Board has stayed its proceedings pending our

jurisdictional ruling, so we turn to that issue now.

II

Under the Natural Gas Act, the courts of appeals

have “original and exclusive jurisdiction over any civil

action for the review” of a state administrative agency’s

“action” taken “pursuant to Federal law to issue . . .

any . . . concurrence” that federal law requires for the

construction of a natural-gas transportation facility. 15

U.S.C. § 717r(d)(1) (cross-referencing 15 U.S.C. § 717f).

We have previously held that when PADEP issues a

1

See Lancaster Against Pipelines v. Commonwealth, No. 2016-075L (Pa. Envtl. Hrg. Bd.); Nesbitt v. Commonwealth, No. 2016-076-L

(Pa. Envtl. Hrg. Bd.); Sierra Club v. Commonwealth, No. 2016-078L (Pa. Envtl. Hrg. Bd.).

App. 8

Water Quality Certification, it does so “pursuant to

federal law,” Del. Riverkeeper Network v. Sec’y Pa.

Dept. of Envtl. Prot. (Riverkeeper I), 833 F.3d 360, 370–

72 (3d Cir. 2016), and the parties do not dispute that

federal law requires the Department to concur before

construction on Atlantic Sunrise can move forward.

Nevertheless, Petitioners contend that we lack

jurisdiction to review their claims. Relying on the First

Circuit’s decision in Berkshire Environmental Action

Team, Inc. v. Tennessee Gas Pipeline Co., LLC, 851

F.3d 105 (1st Cir. 2017), they argue (1) that the

Natural Gas Act permits this Court to hear suits

challenging only a state agency’s final action, and

(2) that PADEP’s Water Quality Certification is nonfinal until the EHB rules on Petitioners’ administrative

appeal. We address both issues in turn.

A

Like the petitions here, Berkshire Environmental

involved the Natural Gas Act, the Clean Water Act,

and a state’s administrative procedures. In that case,

FERC granted a pipeline company a Certificate of

Public Convenience and Necessity subject to essentially

the same condition imposed here—the company would

have to demonstrate it had received all of its federal

permits in order to build its pipeline. Berkshire

Environmental, 851 F.3d at 107. The company

subsequently applied for and received a Water Quality

Certification from the Massachusetts Department of

Environmental Protection (MassDEP) after a noticeand-comment procedure. Id. at 107–08. Under

Massachusetts law, aggrieved parties then had 21 days

to “appeal” that initial decision by demanding a

hearing before MassDEP. Id. at 108, 112–13.

App. 9

Like Transco here, the pipeline company argued

that MassDEP had no authority to hear such an appeal

in light of the First Circuit’s original and exclusive

jurisdiction under the Natural Gas Act. Id. at 108. And

like Petitioners here, the challengers in Berkshire

Environmental asked for a declaration that the Water

Quality Certification would become final and

reviewable by the Court of Appeals only at the

conclusion of their state administrative appeals. Id.

The First Circuit agreed with the challengers on the

jurisdictional question, holding that the Natural Gas

Act permits review of only an agency’s final decisions.

Id. at 111.

Our sister court’s reasoning is straightforward and

persuasive: Although “[i]n a literal sense, state

agencies repeatedly take ‘action’ in connection with

applications for water quality certifications,” Congress

did not intend for us to “exercise immediate review over

[the many] . . . preliminary . . . steps that state

agencies may take in processing an application before

they actually act in the more relevant and

consequential sense of granting or denying it.” Id. at

108. To be sure, the Natural Gas Act’s reference to

state “action” does not expressly restrict our review to

an agency’s ultimate decisions, but there is a “wellsettled ‘strong presumption that judicial review will be

available only when agency action becomes final.’ To

say that silence on the subject implies no requirement

of finality would be to recognize this ‘strong

presumption’ only when it is of little benefit.” Id. at 109

(quoting Bell v. New Jersey, 461 U.S. 773, 778 (1983))

(citations and alterations omitted). We therefore join

the First Circuit in holding that the Natural Gas Act

provides jurisdiction to review only “final agency action

App. 10

of a type that is customarily subject to judicial review.”

Id. at 111.

In resisting that conclusion, PADEP and Transco

rely almost entirely on Tennessee Gas Pipeline Co. LLC

v. Delaware Riverkeeper Network, 921 F. Supp. 2d 381

(M.D. Pa. 2013), which held that the Natural Gas Act

gives this Court “an unqualified right of review” over

even non-final Water Quality Certifications. Id. at 391.

We reject that proposition. Tennessee Gas failed to

acknowledge our longstanding presumption that

Congress intends judicial review over only final

administrative action. Instead, it framed the issue as

whether to graft onto the Natural Gas Act a finality

requirement that the district court regarded as

“originating in state law.” Id. To be sure, deciding on a

PADEP decision’s finality requires reference to the

Pennsylvania procedures that produced it. But it

remains the case that the finality requirement itself,

along with the presumption that Congress intended us

to apply it, are creatures of federal, not state, law.

We are likewise unpersuaded by Tennessee Gas’s

analysis of the Second Circuit’s decisions in Islander

East Pipeline Co., LLC v. Connecticut Department of

Environmental Protection, 482 F.3d 79 (2d Cir. 2006),

and Islander East Pipeline Co., LLC v. McCarthy, 525

F.3d 141 (2d Cir. 2008). In both Islander cases, the

Second Circuit confronted a situation much like this

one and proceeded without analysis, “as if there were

no hurdles in appealing directly from the

determination of a state administrative body.”

Tennessee Gas, 921 F. Supp. 2d at 393. Implicit in that

course of action, the district court concluded, was a

“determination that it is not necessary for a state

App. 11

administrative quasi-judicial body to first review the

. . . issuance . . . of permits by a state administrative

agency before judicial review . . . may be sought.” Id.

Tennessee Gas incorrectly treated the Islander cases, in

which “jurisdiction [was] . . . assumed by the parties,

and assumed without discussion by the court,” as

authority on the question presented here. Goldman v.

Citigroup Glob. Mkts. Inc., 834 F.3d 242, 251 (3d Cir.

2016). Such “drive-by jurisdictional ruling[s]” would

have carried no precedential weight even had they been

decided by this Court. Id.

B

We turn next to whether the Department’s decision

is a conclusive agency action, such that a “civil action

for [its] review” is committed to our exclusive

jurisdiction under the Natural Gas Act. This is not the

first time we have considered the finality of a PADEP

Water Quality Certification issued for a federallyregulated pipeline. In Riverkeeper II, we held that such

an approval was final and reviewable because the time

to appeal to the EHB had already passed. 870 F.3d at

177. Noting the pendency of the petitions now before

us—in which most of the Petitioners had already taken

parallel protective appeals to the EHB—Riverkeeper II

expressly declined to consider whether the availability

of further state administrative review would render the

Department’s decision non-final. Id. at 178. We answer

that question now.

The standard for whether agency action is final is a

familiar one: “Final agency action ‘must mark the

consummation of the agency’s decisionmaking process,’

‘must not be of a merely tentative or interlocutory

nature,’ and ‘must be one by which rights or obligations

App. 12

have been determined, or from which legal

consequences will flow.’” Id. at 176 (quoting Bennett v.

Spear, 520 U.S. 154, 177–78 (1997)) (internal quotation

marks omitted); accord Berkshire Environmental, 851

F.3d at 111.2 Although the decisionmaking process we

are reviewing is defined by Pennsylvania law, we

nevertheless apply a federal finality standard to

determine whether Congress has made the results of

that process reviewable under the Natural Gas Act.

We begin by surveying Pennsylvania’s procedures

for obtaining and appealing a Water Quality

Certification. First, the applicant submits a request to

PADEP. PENNSYLVANIA DEPT. OF ENVTL. PROT. BUREAU

OF WATER QUALITY PROTECTION, NO. 362-2000-001,

P ERMITTING POLICY AND P ROCEDURE M ANUAL

[hereinafter PERMITTING MANUAL] § 400 at 6. The

Department places a notice in the Pennsylvania

Bulletin, beginning a 30-day comment period. Id.

PADEP then makes its decision, and “[t]he issuance or

denial of [the] Water Quality Certification[] . . .is

published in the Pennsylvania Bulletin as a final action

of the Department.” Id. Aggrieved parties have 30 days

from the date of publication to file an appeal to the

EHB. 25 PA. CODE § 1021.52(a)(1), 2(i).

2

We recognize that many (if not most) decisions addressing

administrative finality arise in the context of the Administrative

Procedure Act, see 5 U.S.C. § 704, rather than agency-specific

review provisions like the one we consider here. Nevertheless, we

think that the case law evaluating finality under the APA is

instructive, and see no reason why finality under the Natural Gas

Act should be evaluated any differently. We will therefore follow

Riverkeeper II’s approach of measuring finality in this context

against “the traditional hallmarks of final agency action.” 870 F.3d

at 178.

App. 13

The EHB is wholly separate from PADEP. The

Board is an “independent quasi-judicial agency,” 35 PA.

STAT. ANN. § 7513(a), and its members—full-time

administrative law judges—are appointed by the

Governor of Pennsylvania without any involvement by

either PADEP or the state’s Secretary of

Environmental Protection, id. § 7513(b). Final orders of

the EHB may be appealed to the Commonwealth Court.

42 PA. CONS. STAT. § 763(a)(1).

Two features of the Board’s review deserve special

mention. First, an appeal to the EHB does not prevent

PADEP’s decision from taking immediate legal effect.

The statute creating the Board expressly provides that

“[n]o appeal shall act as an automatic supersedeas,” 35

PA. STAT. ANN. § 7514(d)(1), and the EHB itself regards

it as “axiomatic that the mere pendency of litigation

before the Board . . . has no effect on the validity or

viability of the Department action being appealed . . . .

An appeal to the Board does not operate as a stay,”

M&M Stone Co. v. Commw. of Pa., Dept. of Envtl. Prot.,

EHB Docket No. 2007-098-L, 2009 WL 3159149, at *3

(Pa. Envtl. Hrg. Bd. Sept. 7, 2009) (citations omitted).

Second, the EHB’s review of PADEP decisions is

conducted largely de novo, with parties entitled to

introduce new evidence and otherwise alter the case

they made to the Department. While Pennsylvania law

refers to proceedings before the EHB as an “appeal,”

the Commonwealth Court has explained that the Board

is not an “appellate” tribunal in the ordinary sense of

that term. The Board does not have “a limited scope of

review attempting to determine if [PADEP]’s action can

be supported by the evidence received . . . [by PADEP].

Rather, the [Board’s] duty is to determine if [PADEP]’s

action can be sustained or supported by the evidence

App. 14

taken by the [Board].” Leatherwood, Inc. v. Commw.,

Dept. of Envtl. Prot., 819 A.2d 604, 611 (Pa. Commw.

Ct. 2003) (emphasis added) (citation omitted).

Once again relying heavily on Berkshire

Environmental, Petitioners claim we may not review

PADEP’s issuance of a Water Quality Certification

until the Board adjudicates their appeal. After holding

that its jurisdiction under the Natural Gas Act covered

only final action, the First Circuit concluded that the

Massachusetts Water Quality Certification then under

its review was non-final so long as the petitioners could

still appeal within MassDEP. Citing similarities

between the Massachusetts and Pennsylvania

procedures, Petitioners ask us to reach the same

conclusion here. We disagree, primarily because there

are important distinctions between the Massachusetts

and Pennsylvania schemes.

Two aspects of Pennsylvania’s system for issuing

Water Quality Certifications distinguish PADEP’s

decision from the non-final one in Berkshire

Environmental. First, the Department’s decision here

was immediately effective, notwithstanding Petitioners’

appeals to the EHB. The Department’s decision was

neither “tentative [n]or interlocutory” and was one

“from which legal consequences . . . flow[ed].”

Riverkeeper II, 870 F.3d at 176 (quoting Bennett, 520

U.S. at 177–78) (internal quotation marks omitted).

The First Circuit, by contrast, faced a Massachusetts

regulatory regime in which the agency’s initial decision

was ineffective until either the time to appeal expired

or a final decision on appeal issued. See 310 MASS.

CODE REGS. 9.09(1)(e); see also Berkshire Envtl., 851

F.3d at 108 (noting that the Water Quality

App. 15

Certification expressly forbade any work under its

auspices until “the expiration of the Appeal Period . . .

and any appeal proceedings”). Put another way,

Berkshire Environmental addressed a provisional order

that could become final in the absence of an appeal,

while we are presented with a final order that could be

overturned in the event of an appeal. In that regard,

PADEP’s order is no less final for the availability of

EHB review than a federal agency’s is for the

availability of review in this Court.

Second, unlike in Massachusetts, Pennsylvania law

does not “make[] clear that [Transco]’s application

seeking a . . . water quality certification initiated a

single, unitary proceeding” taking place within one

agency and yielding one final decision. Berkshire

Envtl., 851 F.3d at 112. Quite the opposite. The

Department and the Board are entirely independent

agencies. Each conducts a separate proceeding, under

separate rules, overseen by separately appointed

officers. Compare 25 PA. CODE. Part I (Department of

Environmental Protection), with 25 PA. CODE. Part IX

(Environmental Hearing Board). Both in formal terms,

see PERMITTING MANUAL, supra, § 400 at 6 (noting that

publication in the Pennsylvania Bulletin marks a “final

action of the Department”), and in the immediate

practical effect discussed above, PADEP’s issuance of

a Water Quality Certification is that agency’s final

action, leaving nothing for the Department to do other

than await the conclusion of any proceedings before the

Board.3

3

Petitioners emphasize another parallel between EHB review in

Pennsylvania and an adjudicatory hearing in Massachusetts: both

conduct de novo review without deference to the appealed decision.

App. 16

Whether state law permits further review by the

same agency that makes the initial decision or provides

for an appeal to a structurally-separate body is

probative of whether that decision is final. Finality, at

bottom, is “concerned with whether the initial

decisionmaker has arrived at a definitive position on

the issue,” and PADEP has said its piece regardless of

whether Pennsylvania law gives a different agency the

last word. Williamson Cty. Reg’l Planning Comm’n v.

Hamilton Bank of Johnson City, 473 U.S. 172, 193

(1985) (emphasis added). In that respect, finality is

“conceptually distinct” from the related issue of

exhaustion of administrative remedies. Id. at 192–93.

Here, Petitioners confine themselves to challenging the

finality of PADEP’s decision, and do not argue that we

lack jurisdiction because of a failure to exhaust an

appeal to the EHB.

Petitioners do not rest exclusively on the

comparison between this case and Berkshire

Environmental. Nevertheless, we find their other

arguments no more persuasive.

And to be sure, the First Circuit relied in part on the fact that “the

adjudicatory hearing [was] a review of [the pipeline company]’s

application, rather than a review of a prior agency decision.”

Berkshire Envtl., 851 F.3d at 112. But the court in Berkshire

Environmental did not rely on the fact of de novo review for its own

sake in finding the agency’s initial decision non-final. Rather, it

concluded that the decision was non-final because several features

of Massachusetts’s administrative scheme—de novo review among

them—combined to produce a “review” process that “continue[d]

more or less as though no decision ha[d] been rendered at all.” See

id. The same cannot be said of review by the EHB in Pennsylvania,

which takes place after a decision that has immediate legal effect.

App. 17

Petitioners are incorrect that the Department’s

decision is non-final for purposes of this Court’s review

because a Pennsylvania statute provides that “no

action of [PADEP] shall be final as to [a] person until

the person has had the opportunity to appeal the action

to the [EHB]” or the time to appeal has expired. 35 Pa.

Stat. Ann. § 7514(c). Despite this language,

Pennsylvania cannot declare when and how an agency

action taken pursuant to federal law is sufficiently final

to be reviewed in federal court. State law’s use of the

word “final” to characterize an agency’s decision is

irrelevant in that context, except so far as that

language is relevant to the substantive effect of the

order in question and the practical character of the

procedures surrounding it. Here, those underlying

realities indicate that PADEP has taken final action.

Nor does due process require that Petitioners have

an opportunity to present evidence at a hearing before

the EHB. “There are instances in which due process

requires that an agency afford an adversarial mode of

procedure and an evidentiary hearing,” but this “is not

such an instance.” See Nat’l Labor Relations Bd. v.

ARA Servs., Inc., 717 F.2d 57, 67 (3d Cir. 1983). The

essence of due process is notice and an opportunity to

be heard, and with respect to decisions like the one

under review here, the public comment period provided

Petitioners “with meaningful hearing rights sufficient

under the circumstances to protect [their] interests.”

See Bank of N. Shore v. Fed. Deposit Ins. Corp., 743

F.2d 1178, 1184 (7th Cir. 1984). Due process does not

entitle Petitioners to a de novo evidentiary hearing; the

opportunity to comment and to petition this Court for

review is enough.

App. 18

Notwithstanding the availability of an appeal to the

EHB, PADEP’s issuance of a Water Quality

Certification was final in precisely the most important

ways that the permit in Berkshire Environmental was

not. The Department’s action presents all the

“traditional hallmarks of final agency action,”

Riverkeeper II, 870 F.3d at 178, and we have exclusive

jurisdiction to hear any “civil action for the review” of

such a decision. We now turn to Petitioners’ challenges

to the merits of the Department’s decision.

III

Petitioners make four separate arguments on the

substance of their claims.4 First, they claim PADEP

failed to provide the public notice the Clean Water Act

requires prior to issuing a Water Quality Certification.

Second, they contend the Department acted arbitrarily

and capriciously by issuing a Water Quality

Certification that was immediately effective despite

being conditioned on Transco obtaining additional

permits in the future. Third, pointing out that

PADEP’s approval was necessary for Transco to begin

eminent domain proceedings under the Natural Gas

Act, Petitioners argue that the Department’s decision

deprived them of due process and violated the Fifth

Amendment’s Takings Clause. Finally, Petitioners

assert that the Department’s action violated its

obligation to safeguard the Commonwealth’s natural

resources under Article I, Section 27 of the

Pennsylvania Constitution. We address these

arguments seriatim.

4

Not every petitioner joins in every argument. For the sake of

simplicity we refer generically to “Petitioners.”

App. 19

A

The Clean Water Act obliges state agencies to

comply with a number of procedural requirements

before issuing a Water Quality Certification. As

relevant here, Section 401 requires PADEP to

“establish procedures for public notice in the case of all

applications for certification.” 33 U.S.C. § 1341(a)(1).

No party disputes that the Department has a

longstanding written policy, published in its Permitting

Manual, that when it “receives a request for Water

Quality Certification, a notice is published in the

Pennsylvania Bulletin for a 30-day comment period.”

PERMITTING MANUAL, supra, § 400 at 6. And no party

disputes that the Department followed that policy here.

Nevertheless, Petitioners claim it was insufficient to

satisfy Section 401. We disagree.

First, Petitioners cite several cases in which

“[c]ourts have found that Section 401(a)(1)’s notice

requirements are met where the state codifies the

notice requirements by statute or regulation.”

Riverkeeper Br. 25–26. But none of those decisions—

and nothing in the text of the Clean Water Act—

requires a State to establish its notice procedures by

way of regulation. The fact that formal rulemaking is

sufficient to satisfy the requirement of established

notice procedures does not mean it is necessary.

Second, Petitioners claim this Court has already

“held” that PADEP has “failed to ‘establish’ procedures

for public notice” under Section 401. Riverkeeper Br.

26–27. Petitioners’ only support for that claim is a

single clause in our decision in Riverkeeper I: “PADEP

has not published any procedures for issuing Water

Quality Certifications.” 833 F.3d at 385. Reading that

App. 20

clause in context, however, makes clear that it does not

refer to PADEP’s procedures for providing public notice

of Section 401 applications. Indeed, PADEP’s notice

procedures were not at issue in that case. Rather, we

considered PADEP’s procedures for processing such

applications—what information the agency would

gather and evaluate before issuing a Water Quality

Certification. Id. at 385–86. Contrary to Petitioners’

suggestion, we have never held anything with respect

to PADEP’s notice procedures.

Third, Petitioners suggest that “PADEP itself has

implicitly conceded” its failure to establish adequate

notice procedures by publishing a draft of new

procedures for considering Section 401 Certifications,

including notice procedures. Riverkeeper Br. 27–28. We

are unpersuaded. The Department has not conceded

that its existing notice procedures are legally

inadequate by moving to promulgate a single set of

rules governing the entire Water Quality Certification

process.

Finally, Petitioners contend that Section 401

required PADEP to immediately give full notice not

only of Transco’s application for a Water Quality

Certification, but also of the three substantive permits

on which the Department proposed to condition its

approval. That argument also fails. Notice need only be

adequate to allow interested parties to participate

meaningfully in the process that is actually pending,

and PADEP’s process for granting Water Quality

Certifications does not involve immediate consideration

of any substantive permits. This Court approved that

arrangement just two years ago, holding that when the

Department conditions a Certification on the later

App. 21

acquisition of other permits, the agency may issue the

Certification without engaging in the substantive

review that will eventually be required to grant the

permits. Riverkeeper I, 833 F.3d at 387–88. Since

PADEP is not required to conduct that review at this

stage, it would make little sense to require it to provide

notice of the same.

B

Petitioners also assert that the Department’s

decision to issue a Water Quality Certification now,

conditioned on Transco obtaining substantive permits

later, was arbitrary, capricious, or otherwise not in

accordance with law. Petitioners make two versions of

that argument. First, they claim PADEP’s decision was

arbitrary because it certified Atlantic Sunrise’s water

quality compliance based on a pledge that Transco

would demonstrate substantive compliance in a future

permit application rather than in the application for

the Water Quality Certification itself. Without that

present demonstration of compliance, Petitioners

argue, PADEP’s decision that Atlantic Sunrise would

comply with Pennsylvania water quality standards

could not have been based on anything but guesswork.

Second, Petitioners say the Department failed to follow

its own procedures, which they claim require the

agency to consider applications for Water Quality

Certifications simultaneously with any applicable

substantive permits.

Both of those arguments—which at bottom focus on

the timing rather than the substance of the

Department’s decision—are foreclosed by our decision

in Riverkeeper I. In that case, we held that PADEP’s

preferred procedure for considering Certifications along

App. 22

with other permits was not arbitrary or capricious

because—since no construction can begin before the

Department grants the substantive permits, and all

interested parties will have a full opportunity to weigh

in when PADEP considers applications for those

permits—the petitioners could not show they had been

harmed by the Department’s sequencing choice.

Riverkeeper I, 833 F.3d at 386–87. The same analysis

applies with equal force here. Petitioners attempt to

distinguish this case by arguing that they have been

harmed by the Department’s choice not to provide

notice of the substantive permits upon which it

conditioned the Water Quality Certification. But as we

discussed herein, Petitioners will suffer no harm from

PADEP’s decision to provide notice of those permits at

the time it actually considers them.

C

Petitioners next argue that PADEP’s issuance of a

conditional Water Quality Certification violates the

Takings Clause of the Fifth Amendment and the Due

Process Clause of the Fourteenth Amendment. Under

the Natural Gas Act, any natural gas company holding

a Certificate of Public Convenience and Necessity may

acquire a pipeline right-of-way through eminent

domain. 15 U.S.C. § 717f(h). The Certificate of Public

Convenience and Necessity establishes the legal right

to take property; in a condemnation proceeding under

the Natural Gas Act, the “only open issue [is] the

compensation the landowner defendant will receive in

return for the easement.” Columbia Gas Transmission,

LLC v. 1.01 Acres, More or Less in Penn Twp., York

Cty., Pa., Located on Tax ID #440002800150000000

Owned By Brown, 768 F.3d 300, 304 (3d Cir. 2014).

App. 23

Petitioners assert that PADEP violated the Fifth and

Fourteenth Amendments when it issued a conditional

Water Quality Certification—a condition precedent for

initiating eminent domain proceedings under Transco’s

Certificate of Public Convenience and Necessity—

based on a relatively restricted administrative process.

Regardless of its underlying merits, and setting

aside questions about whether the Clean Water Act

could ever provide a vehicle to raise a takings

argument, see Gunpowder Riverkeeper v. FERC, 807

F.3d 267, 274–75 (D.C. Cir. 2015) (concluding that “an

injury arising specifically by reason of eminent domain”

falls outside the zone of interests protected by the

statute), that claim cannot succeed because Petitioners

have presented it in the wrong forum. Their argument

does not challenge PADEP’s judgment that Transco

will comply with Pennsylvania’s water-quality

standards. Nor does it ask this Court to review the

Department’s reasoning, its procedures, or the facts on

which it based its decision. Rather, Petitioners’

eminent-domain argument is in substance a challenge

to FERC’s order granting a Certificate of Public

Convenience and Necessity. And that order may only

be challenged by a request for rehearing before FERC

itself, or by a petition for review by an appropriate

federal circuit court. See 15 U.S.C. § 717r(a)–(b);

Williams Nat. Gas Co. v. City of Okla. City, 890 F.2d

255, 264 (10th Cir. 1989). Petitioners respond, in

essence, that those avenues are inadequate because if

Petitioners took advantage of them, Transco would

resist and Petitioners might lose. That argument

refutes itself.

App. 24

D

Petitioners’ final argument—that PADEP failed to

comply with its obligations under the Pennsylvania

Constitution—also fails. Article I, Section 27 of the

Pennsylvania Constitution establishes a common right

to the Commonwealth’s natural resources and obligates

its government to hold those resources in trust.

Petitioners argue that PADEP failed to live up to that

obligation when it issued a Water Quality Certification

conditioned on Transco later obtaining certain

substantive permits.

Transco responds that a state constitutional claim

is not cognizable in this proceeding, arguing that by

vesting jurisdiction in this Court to review PADEP’s

Certification decision, the Natural Gas Act provides for

only a narrow scope of review that does not permit us

to hear state-law claims. Transco points to § 717r(d)(3)

of the Act, which states that if the reviewing court of

appeals finds that an agency’s action was “inconsistent

with the Federal law governing such permit and would

prevent the construction, expansion or operation of the

facility . . . , the Court shall remand the proceeding to

the agency.” 15 U.S.C. § 717r(d)(3) (emphasis added).

In Transco’s view, the statute’s requirement that we

remand to the agency when certain conditions are met

implies that remand is the only remedy available to us,

and then only under the conditions just quoted.

Therefore, Transco asserts, we may not reach the

merits of Petitioners’ claim under the Pennsylvania

Constitution. We cannot agree.

The provision of the Natural Gas Act that actually

grants us jurisdiction, 15 U.S.C. § 717r(d)(1), is quite

capacious. It empowers us to hear “any civil action”

App. 25

seeking “review” of federal permits required by

interstate pipelines. And ordinarily, when such agency

action is “made reviewable by statute,” 5 U.S.C. § 704,

the Administrative Procedure Act authorizes a broad

scope of review, without limiting courts to considering

only federal law, see id. § 706. Nothing in § 717r(d)(3)

says differently; it simply requires reviewing courts to

apply a particular remedy when certain conditions are

met. It says nothing about other circumstances, and we

will not imply from the statute’s silence that Congress

intended to restrict the language of its text. Congress

does not “hide elephants in mouseholes.” Whitman v.

Am. Trucking Ass’ns. Inc., 531 U.S. 457, 468 (2001).5

Nevertheless, Petitioners’ claim under the

Pennsylvania Constitution cannot succeed on the

merits. Petitioners essentially complain that PADEP

could not have met its obligation to safeguard

Pennsylvania’s natural resources because it granted a

Water Quality Certification before collecting the

environmental impact data that would be required to

issue the substantive permits on which it was

conditioned. That fails for the same reason that we

rejected Petitioners’ argument that PADEP’s decision

to grant a Water Quality Certification conditioned on

obtaining other permits was arbitrary and capricious.

See supra III.B. Because Transco will have to obtain

those substantive permits to begin construction—and

5

The United States Court of Appeals for the Fourth Circuit has

recently reached the same conclusion. Sierra Club v. U.S. Dep’t of

the Interior, — F.3d —, 2018 WL 3717067, at *25 (4th Cir. Aug. 6,

2018) (holding that when an agency’s action would not “prevent the

construction” of a pipeline, § 717r(d)(3) did not apply and “the

APA’s default rule” governed)

App. 26

PADEP will have to consider Article I, Section 27 in

deciding whether to grant or deny them—Petitioners

cannot show that they have been harmed by the

Department’s decision to issue a conditional Water

Quality Certification.

***

For the reasons stated, we will deny the petitions

for review.

App. 27

APPENDIX B

COMMONWEALTH OF PENNSYLVANIA

ENVIRONMENTAL HEARING BOARD

EHB Docket No. 2015-060-M

[Filed June 2, 2017]

__________________________________________

THE DELAWARE RIVERKEEPER

)

NETWORK AND MAYA K VAN ROSSUM, )

THE DELAWARE RIVERKEEPER

)

)

v.

)

)

COMMONWEALTH OF PENNSYLVANIA, )

DEPARTMENT OF ENVIRONMENTAL

)

PROTECTION and TRANSCONTINENTAL )

GAS PIPE LINE COMPANY, LLC

)

_________________________________________ )

Issued June 2, 2017

OPINION AND ORDER ON

THE TERMINATION OF THE

ABOVE-CAPTIONED APPEAL

By Richard P. Mather, Sr., Judge

Synopsis

The Board agrees to terminate Appellant’s appeal in

the above-captioned matter in light of the Appellant’s

March 24, 2017 letter and following a conference call

with the Parties on May 16, 2017. The Board

nonetheless notes that it did not decide to terminate

App. 28

the appeal for lack of jurisdiction. The Board believes

that it would have jurisdiction over this appeal.

OPINION

The above captioned appeal was filed by the

Delaware Riverkeeper Network and Maya K. Van

Rossum, the Delaware Riverkeeper (“Appellant”) on

May 5, 2015 in response to the Department’s grant of

two 401 Water Quality Certifications – Permits No. EA

40-013 and EA 45-002 – to Transcontinental Gas Pipe

Line Company, LLC (“Permittee”) on April 6, 2015.

On May 21, 2015, the Parties submitted a joint

request for a stay in this appeal, pending the Third

Circuit Court of Appeals’ review of its jurisdiction over

a petition for review filed by the Delaware Riverkeeper

Network. This petition for review concerns the same

Department decision as challenged here, which relates

to Transco’s Leidy Southeast Expansion Project.1 The

Board granted the request for an approximately

two-month stay, at which point the Parties were

required to submit a status report on or before July 28,

2015. As there were no new developments, the Board

continued to issue orders extending the stay and

requiring joint status reports. Status reports were due

1

See Delaware Riverkeeper Network v. Quigley, No. 15-2122 (3d.

Cir., filed May 5, 2015). On May 8, 2015, the Court of Appeals for

the Third Circuit issued an order requiring the parties to address

the Court’s authority over the petition within fourteen days of the

order. The parties in this matter requested that the appeal

pending before the Board be stayed for a reasonable duration so as

to give the Court of Appeals time to consider the submissions in

response to its order.

App. 29

on October 1, 2015, November 6, 2015, February 5,

2016, April 1, 2016, June 3, 2016, and August 1, 2016.

On August 8, 2016, the Court of Appeals for the

Third Circuit issued its opinion in Delaware

Riverkeeper Network v. Quigley, in which it held that

state action taken pursuant to the Clean Water Act in

permitting an interstate natural gas facility pursuant

to the Natural Gas Act “is subject to review exclusively

in the Court of Appeals.” Slip op. at 17-18. Permittee

filed a letter with the Board on August 8, 2016

requesting that the Board dismiss the appeal for lack

of jurisdiction, given the Court of Appeals’ ruling. The

Board issued an order on August 11, 2016 staying the

appeal and ordering the Appellant to file a status

report on or before September 12, 2016 indicating

whether they have an objection to Permittee’s request

to dismiss the appeal.

On September 15, 2016, the Appellant filed a status

report that alerted the Board to the Delaware

Riverkeeper Network’s request for a re-examination of

a number of issues ruled upon in the Third Circuit’s

decision. If granted, this request, while unrelated to

jurisdictional issues, would delay the Third Circuit’s

issuance of a mandate and could potentially modify the

Third Circuit’s August 8, 2016 Opinion. The Appellant

therefore requested that the Board extend its stay of

this appeal. On October 31, 2016, the Board granted

this request and stayed the matter until the Third

Circuit issued a mandate in Delaware Riverkeeper

Network v. Quigley.

On March 24, 2017, the Appellant submitted a

letter alerting the Board to the Third Circuit’s issuance

of an amended opinion on the same date. While the

App. 30

Third Circuit Court of Appeal’s adopted several

changes requested by the Delaware Riverkeeper, none

of those changes impacted the Court’s holding on

jurisdiction. In light of this, the Appellant had no

objection to the termination of its appeal before the

Board. However, in a footnote, Appellant also drew the

Board’s attention to a recent ruling out of the First

Circuit in which the Court dismissed a petition for

review under Section 19(d)(1) of the Natural Gas Act,

15 U.S.C. § 717r(d)(1). The Court determined that it

lacked subject matter jurisdiction over a Section 401

Water Quality Certificate because aggrieved parties

had the right to appeal the Certificate to the state

department of environmental protection before it could

be appropriately reviewed by the First Circuit of

Appeals.2

Prior to the Board addressing Appellant’s March 24,

2017 letter, Judge Labuskes issued an Opinion and

Order in Lancaster Against Pipelines, Geraldine Nesbitt

and Sierra Club v. DEP, EHB Docket No. 2016-075-L

(Opinion and Order, May 10, 2017). In this Opinion,

Judge Labuskes determined that the Board has

jurisdiction over appeals of Water Quality Certifications

pursuant to Section 401 of the Clean Water Act. In light

of this related matter, the Board scheduled a conference

call with all parties in the instant appeal on May 16,

2017 to confirm that Appellant had no objection to the

termination of its appeal before the Board. During the

call, the Appellant confirmed that it did not object to the

termination its appeal, and neither the Department nor

Permittee were opposed. Therefore, the Board will close

2

See Berkshire Environmental Action Team, Inc. v. Tennessee Gas

Pipeline Company, LLC, 851 F.3d 105 (1st Cir. 2017).

App. 31

and discontinue this docketed appeal. The Board

nonetheless feels that a brief discussion of its

jurisdiction over such appeals is useful because the issue

may arise in later appeals and was correctly decided by

Judge Labuskes in the pending related appeal.

Discussion

In Lancaster Against Pipelines, Geraldine Nesbitt

and Sierra Club v. DEP, Permittee Transcontinental

Gas Pipeline Company, LLC (“Permittee” or “Transco”)

requested that the Board dismiss the appeal regarding

the Department’s issuance of a Section 401 Water

Quality Certificate following the ruling by the Third

Circuit in Delaware Riverkeeper Network v. Secretary,

Pennsylvania Department of Environmental Protection

833 F.3d 360 (3d Cir. 2016). Transco argued that the

Board could not review the Department’s issuance of

the 401 Certification because the Third Circuit has

exclusive jurisdiction over that section. The

Department notified the Board that it would “abide by”

the Third Circuit’s ruling. The Appellants, however,

have asked the Third Circuit to dismiss their petitions

for review for lack of jurisdiction because the Board has

not yet acted on the appeals before it, thereby

rendering the petitions before the Third Circuit not yet

ripe for review. Appellants further argued that the

Board does have jurisdiction and should issue a stay in

Lancaster Against Pipelines v. DEP until the Third

Circuit rules on whether it has jurisdiction in the

pending parallel proceedings. The Board agreed with

the Appellants and determined that it had jurisdiction

under the Natural Gas Act, 15 U.S.C. §§ 717-717z.

Although the Natural Gas Act makes the regulation

of natural gas pipelines a federal function, it leaves

App. 32

open a limited role for states that have primacy to

implement the Clean Water Act. Lancaster Against

Pipelines, Geraldine Nesbitt and Sierra Club v. DEP,

EHB Docket No. 2016-075-L, slip op. at 3 (Opinion and

Order, May 10, 2017). Pennsylvania is such a state. In

these instances, the state retains the right to

determine whether the project complies with federal

and state water quality standards. Id. If the project is

in compliance, then the state will issue a 401

Certification. Id.

The jurisdictional issue involved here arises from

Section 19(d)(1) of the Natural Gas Act:

The United States Court of Appeals for the

circuit in which a facility subject to section 717b

of this title or section 717f of this title is

proposed to be constructed, expanded, or

operated shall have original and exclusive

jurisdiction over any civil action for the review of

an order or action of a Federal agency (other

than the Commission) or State administrative

agency acting pursuant to Federal law to issue,

condition, or deny any permit, license,

concurrence, or approval (hereinafter collectively

referred to as “permit”) required under Federal

law, other than the Coastal Zone Management

Act of 1972 (16 U.S.C. 1451 et seq.).

15 U.S.C. § 717r(d)(1). As Judge Labuskes stated, “the

Third Circuit’s opinion in the Delaware Riverkeeper

case is not particularly helpful” in resolving the

jurisdictional issue of concern to the Board. The

jurisdictional issue before the Third Circuit was both

broader and more general: whether the Department’s

issuance of a 401 Certification was the act of a state

App. 33

administrative agency acting “pursuant to Federal

law.” Delaware Riverkeeper, 833 F.3d at 370. This is

not the jurisdictional issue that is of concern to the

Board. Rather, the Board is faced with whether a final

state action is required before the Court of Appeals

may act upon a petition for review under Section

19(d)(1). If a final state action is required under Section

19(d)(1), then the follow-up question is whether a final

state action has occurred in a given matter.

The question of whether a final “state

administrative agency” action is required under Section

19(d)(1) is a question of federal law that is already

pending before the Third Circuit. Both the First and

Ninth Circuits have ruled that it is required. See

Berkshire Env. Action Team, Inc. v. Tenn. Gas Pipeline,

LLC, 851 F.3d 105 (1st Cir. 2017); Columbia

Riverkeeper v. U.S. Coast Guard, 761 F.3d 1084 (9th

Cir. 2014). The Middle District of Pennsylvania has

ruled that it is not required. Contra Tennessee Gas

Pipeline LLC v. Del. Riverkeeper Network, 921 F. Supp.

381 (M.D. Pa. 2013). The Board particularly finds the

First Circuit Court of Appeals’ position to be highly

persuasive. The First Circuit’s position was that there

was ample reason to continue to have the strong

presumption that judicial review is available only upon

a state agency action becoming final. Berkshire Env.

Action Team, 851 F.3d at 111 (citing Bell v. New Jersey,

461 U.S. 773, 778 (1973)).

Whether a state agency action is final is a question

of state law. As far as the Board is concerned, a

Department action only becomes final following an

opportunity to appeal the action to the Environmental

Hearing Board. Pennsylvania law is very clear on this

App. 34

point: “[N]o action of the department [of environmental

protection] adversely affecting a person shall be final as

to that person until the person has had an opportunity

to appeal the action to the [environmental hearing]

board. . . .” 35 P.S. § 7514(c). Courts in Pennsylvania

have long held “that a Department action is not final

until an adversely affected party has had an

opportunity to appeal the action to this Board.”

Lancaster Against Pipelines, EHB Docket No.

2016-075-L, slip op. at 5 (Opinion and Order, May 10,

2017), citing Fiore v. DER, 655 A.2d 1081, 1086 (Pa.

Cmwlth. 1995); Morcoal v. DER, 459 A.2d 1303, 1307

(Pa. Cmwlth. 1983).

This is very much like the Massachusetts

procedures that the First Circuit found were not final

until the adversely affected party had the opportunity

to go through the state’s hearing process. Berkshire,

851 F.3d at 111-14. Unless the Third Circuit holds that

a final action is not required, or that Pennsylvania’s

may be disregarded, the Board finds that it has

jurisdiction over appeals such as that found in

Lancaster Against Pipelines and the matter here.

Therefore, while we will close and terminate this

appeal because Appellant have no objection, we

maintain that we have jurisdiction over it.3

3

Aside from the statutory construction issue arising under Section

19(d)(1) regarding the need for a final state agency action, I believe

there is a more fundamental concern with Section 19(d)(1) that

arises under the Tenth Amendment of the United States

Constitution. U.S. CONST. amend. X. There is no question that

Congress has the authority to preempt state regulatory authority

regarding interstate pipelines subject to regulation by the Federal

Energy Regulatory Commission under the Natural Gas Act. 15

App. 35

U.S.C. §§ 717-717z. Section 19(d)(1) does not, however, preempt

state regulatory authority, but rather expressly recognizes a limited

state role for a “state administrative agency acting pursuant to

federal law . . .” Section 19(d)(1) does more than simply authorize a

limited state role, however. It commandeers state agency officials

and compels them to violate longstanding state administrative law.

Section 19(d)(1) purports to rewrite state laws by directing state

agency officials to litigate the state agency’s decisions before the

United States Court of Appeals for the circuit in which the facility

is located. It is a fundamental principle of law that Pennsylvania

state agencies are entities established by Pennsylvania state law,

and that they have only the authority given to them by the

Pennsylvania General Assembly. Small v. Horn, 722 A.2d 664, 669

(Pa. 1998). Congress’s attempt to commandeer the Department and

its officials and to compel them to defend their actions in federal

court rewrites longstanding state administrative law. 35 P.S. § 7514.

I believe that this attempt violates the Tenth Amendment and its

anti-commandeering principle. See New York v. United States, 505

U.S. 144 (1992) and Printz v. United States, 521 U.S. 898 (1997).

Congress may not simply commandeer state officials and agencies,

rewrite state laws, and direct that state agency officials defend state

agency decisions in federal court in violation of state laws enacted

by the Pennsylvania General Assembly. If the Third Circuit Court

of Appeals decides that a final state action is required under Section

19(d)(1) then the clear conflict with longstanding Pennsylvania state

law involving appeals of Department actions to the Environmental

Hearing Board will be addressed. However, the Pennsylvania

General Assembly has also directed that appeals from decisions of

the Pennsylvania Environmental Hearing Board go to the

Pennsylvania Commonwealth Court. 42 Pa. C.S.A. § 763. Therefore,

such a decision from the Third Circuit confirming the necessity of a

final state action could nonetheless still implicate constitutional

issues of commandeering by circumventing state laws directing such

appeals to the Commonwealth Court. See generally Josh Blackman,

Article: State Judicial Sovereignty, 2016 U. Ill. L. Rev. 2033 (2016)

(Discussing the constitutionality of exclusive federal jurisdiction as

it relates both to Article III of the Constitution and the

anti-commandeering principle of the Tenth Amendment).

App. 36

COMMONWEALTH OF PENNSYLVANIA

ENVIRONMENTAL HEARING BOARD

EHB Docket No. 2015-060-M

[Filed June 2, 2017]

__________________________________________

THE DELAWARE RIVERKEEPER

)

NETWORK AND MAYA K VAN ROSSUM, )

THE DELAWARE RIVERKEEPER

)

)

v.

)

)

COMMONWEALTH OF PENNSYLVANIA, )

DEPARTMENT OF ENVIRONMENTAL

)

PROTECTION and TRANSCONTINENTAL )

GAS PIPE LINE COMPANY, LLC

)

_________________________________________ )

ORDER

AND NOW, this 2nd day of June, 2017, in

consideration of the Permittee’s request to terminate

the appeal, the above-captioned matter will be marked

closed and discontinued in the docket.

ENVIRONMENTAL HEARING BOARD

s/ Richard P. Mather, Sr.

RICHARD P. MATHER, SR.

Judge

DATED: June 2, 2017

c: DEP, General Law Division:

Attention: Maria Tolentino

(via electronic mail)

App. 37

For the Commonwealth of PA, DEP:

Joseph S. Cigan III, Esquire

(via electronic filing system)

For Appellant:

Aaron Stemplewicz, Esquire

(via electronic filing system)

For Permittee:

Pamela S. Goodwin, Esquire

Andrew T. Bockis, Esquire

John F. Stoviak, Esquire

(via electronic filing system)

App. 38

APPENDIX C

COMMONWEALTH OF PENNSYLVANIA

ENVIRONMENTAL HEARING BOARD

EHB Docket No. 2016-075-L

(Consolidated with 2016-076-L and 2016-078-L)

[Filed May 10, 2017]

_____________________________________________

LANCASTER AGAINST PIPELINES

)

GERALDINE NESBITT AND SIERRA CLUB )

)

v.

)

)

COMMONWEALTH OF PENNSYLVANIA,

)

DEPARTMENT OF ENVIRONMENTAL

)

PROTECTION and TRANSCONTINENTAL

)

GAS PIPE LINE COMPANY, LLC, Permittee )

____________________________________________ )

Issued May 10, 2017

OPINION AND ORDER ON

REQUEST TO DISMISS

By Bernard A. Labuskes, Jr., Judge

Synopsis

The Environmental Hearing Board has jurisdiction

in an appeal from the Department of Environmental

Protection’s issuance of a Water Quality Certification

pursuant to Section 401 of the Clean Water Act.

App. 39

OPINION

On April 5, 2016, the Pennsylvania Department of

Environmental Protection (the “Department”) issued a

Water Quality Certification pursuant to Section 401 of

the Clean Water Act, 33 U.S.C. § 1341(a), to

Transcontinental Gas Pipe Line Company, LLC

(“Transco”). The Department certified among other

things that the construction, operation, and

maintenance of Transco’s Atlantic Sunrise Pipeline

Project complies with the Commonwealth’s water

quality standards, provided that Transco obtained and

complied with some yet-to-be-issued state permits.

Lancaster Against Pipelines, Geraldine Nesbitt, and

the Sierra Club filed these consolidated appeals from

the Department’s issuance of the 401 certification. The

Appellants also filed petitions with the Court of

Appeals for the Third Circuit seeking review of the

same Department action. Lancaster Against Pipelines

v. Quigley, No. 16-2212; Nesbitt v. Quigley, No.

16-2218; and Sierra Club v. Quigley, No. 16-2400. Soon

thereafter, the parties asked for and received a series

of stays in both our appeals and the Third Circuit

cases. The parties told us that they wished to await the

Third Circuit Court of Appeal’s decision in a case said

to involve similar issues, Delaware Riverkeeper

Network v. Secretary, Pennsylvania Department of

Environmental Protection, 833 F.3d 360 (3d Cir. 2016).

On August 8, 2016, Transco by letter informed us

that the Third Circuit had issued its Opinion in the

Delaware Riverkeeper case. Transco requested that we

dismiss the appeal. However, a petition for rehearing

was thereafter filed in the Delaware Riverkeeper case,

so the parties once again agreed to a continuing stay

App. 40

pending the ruling on that petition. The parties asked

us to issue an Order providing that, within fourteen

days of the Third Circuit’s mandate in the Delaware

Riverkeeper case, the parties could file written

responses addressing this Board’s authority to proceed

in this matter. We agreed and issued an appropriate

Order on September 13, 2016.

On March 13, 2017, the parties notified us that the

Third Circuit had issued its mandate in the Delaware

Riverkeeper case. They indicated that they would be

filing their respective jurisdictional statements as

contemplated in our Order, which they have now done.

Transco has renewed its “request” that the Board

dismiss these consolidated appeals for lack of

jurisdiction. It argues that this Board cannot review

the Department’s issuance of the 401 certification

because the Third Circuit has exclusive jurisdiction to

review that action. The Department sent us a short

letter indicating that it was willing to “abide by” the

Third Circuit’s ruling in Delaware Riverkeeper. The

Appellants tell us that they have asked the Third

Circuit to dismiss their own petitions for review for

lack of jurisdiction, arguing that the petitions are not

ripe for review because this Board has not yet acted on

their appeals before us. They tell the Court that,

because the Board has not yet acted on the appeal of

the 401 certification, there is no final state action for

the Court to review. Similarly, the Appellants argue

before us that we do indeed have jurisdiction, and that

at a minimum we should issue another stay until the

Third Circuit rules on its jurisdiction in the parallel

proceedings pending there.

App. 41

Although a challenge to our jurisdiction must

ordinarily take the form of a motion, 25 Pa. Code

§§ 1021.91 and 1021.94, we are willing to view

Transco’s request for dismissal together with the

parties’ jurisdictional statements as the functional

equivalent of a motion. Transco’s request is denied and

the Appellant’s request for a stay is granted because, in

our view, until the Third Circuit holds otherwise, this

Board does have jurisdiction to review the

Department’s action.

Ordinarily there would be no question that we have

jurisdiction to review the Department’s issuance of a

401 certification. See Solebury Twp. v. DEP, 928 A.2d

990 (Pa. 2007). The question arises here, however,

because the certification at issue involves an interstate

natural gas pipeline subject to regulation by the

Federal Energy Regulatory Commission (FERC) under

the Natural Gas Act, 15 U.S.C. §§ 717-717z. The

Natural Gas Act for the most part makes the

regulation of natural gas pipelines a federal function,

but it carves out a limited role for states such as

Pennsylvania that have primacy to implement the

Clean Water Act. The state retains the right to

determine whether the project complies with federal

and state water quality standards. If it does, the state

issues a 401 certification. The jurisdictional issue

arises because Section 19(d)(1) of the Natural Gas Act

provides:

The United States Court of Appeals for the

circuit in which a facility subject to section 717b

of this title or section 717f of this title is

proposed to be constructed, expanded, or

operated shall have original and exclusive

App. 42

jurisdiction over any civil action for the review of

an order or action of a Federal agency (other

than the Commission) or State administrative

agency acting pursuant to Federal law to issue,

condition, or deny any permit, license,

concurrence, or approval (hereinafter collectively

referred to as “permit”) required under Federal

law, other than the Coastal Zone Management

Act of 1972 (16 U.S.C. 1451 et seq.).

15 U.S.C. § 717r(d)(1).

We do not believe the Third Circuit’s Opinion in the

Delaware Riverkeeper case is particularly helpful. The

only jurisdictional issue before the Court was whether

the Department’s issuance of a 401 certification was

the act of a state administrative agency acting

“pursuant to Federal law.” Delaware Riverkeeper, 833

F.3d at 391. The Court held that it was, and it

proceeded to address the merits. The Court was not

faced with and did not address whether the state’s

action needed to be final and whether the Department’s

issuance of the certification was final. The precise

question presented in our case is not whether the

Department was acting pursuant to federal law; it is

whether a final action is required before the Court of

Appeals can act upon a petition for review, and

whether a final action has taken place in this case.

There is little point in us opining on the first

question. Whether a final action is required is a

question of federal law that is pending before the Court

in the Appellants’ petitions for review in the

proceedings parallel to this one. The First Circuit Court

of Appeals in what we believe to be a highly persuasive

decision that respects the state’s administrative

App. 43

process recently held that a final agency decision is

required. Berkshire Env. Action Team, Inc. v. Tenn.

Gas Pipeline, LLC, 851 F.3d 105 (1st Cir. 2017). See

also, Columbia Riverkeeper v. U.S. Coast Guard, 761

F.3d 1084 (9th Cir. 2014) (final action required).

Contra, Tennessee Gas Pipeline LLC v. Del. Riverkeeper

Network, 921 F.Supp. 381 (M.D. Pa. 2013) (final agency

action not required). The First Circuit said that there

was ample reason to stick with the strong presumption

that judicial review is only available when an agency

action becomes final. Id., 851 F.3d at 111 (citing Bell v.

New Jersey, 461 U.S. 773, 778 (1973)).

As to the second question, there is no doubt

whatsoever that the Department’s certification of

Transco’s project was not a final action. Pennsylvania

law is very clear on this point: “[N]o action of the

department [of environmental protection] adversely

affecting a person shall be final as to that person until

the person has had an opportunity to appeal the action

to the [environmental hearing] board…” 35 P.S.

§ 7514(c). Pennsylvania courts have long held that a

Departmental action is not final until an adversely

affected party has had an opportunity to appeal the

action to this Board. Fiore v. DER, 655 A.2d 1081, 1086

(Pa. Cmwlth. 1995); Morcoal v. DER, 459 A.2d 1303,

1307 (Pa. Cmwlth. 1983). Pennsylvania’s procedures

are nearly identical in substance to the Massachusetts

procedures that the First Circuit found not to be final

until the adversely affected party had an opportunity

to take advantage of that state’s hearing process.

Berkshire, 851 F.3d at 111-14. Unless the Third Circuit

holds that no final action is required, or that the one

that is required by Pennsylvania law may simply be

disregarded, the appeal before us may proceed.

App. 44

Accordingly, dismissal would be premature. We,

therefore, issue the Order that follows.

App. 45

COMMONWEALTH OF PENNSYLVANIA

ENVIRONMENTAL HEARING BOARD

EHB Docket No. 2016-075-L

(Consolidated with 2016-076-L and 2016-078-L)

[Filed May 10, 2017]

_____________________________________________

LANCASTER AGAINST PIPELINES

)

GERALDINE NESBITT AND SIERRA CLUB )

)

v.

)

)

COMMONWEALTH OF PENNSYLVANIA,

)

DEPARTMENT OF ENVIRONMENTAL

)

PROTECTION and TRANSCONTINENTAL

)

GAS PIPE LINE COMPANY, LLC, Permittee )

____________________________________________ )

ORDER

AND NOW, this 10th day of May, 2017, upon

consideration of the parties’ responses regarding this

Board’s jurisdiction over the above-captioned appeal

pursuant to the Board’s Order of March 21, 2017, it is

hereby ordered that:

1. This matter is stayed until the Third Circuit

rules upon its jurisdiction over the matters

docketed at Sierra Club v. Secretary,

Pennsylvania Department of Environmental

Protection, et al., No. 16-2400, Nesbitt v.

Secretary, Pennsylvania Department of

Environmental Protection, et al., No. 16-2218,

and Lancaster Against Pipelines v. Secretary,

Pennsylvania Department of Environmental

App. 46

Protection, et al., No. 16-2212 (“the pending

Third Circuit matters”).

2. The parties shall promptly notify the Board

upon the Third Circuit’s decision on jurisdiction

in the pending Third Circuit matters, or file a

collective status report by July 17, 2017,

whichever comes first.

ENVIRONMENTAL HEARING BOARD

s/ Bernard A. Labuskes, Jr.

BERNARD A. LABUSKES, JR.

Judge

DATED: May 10, 2017

c: DEP, General Law Division:

Attention: Maria Tolentino

(via electronic mail)

For the Commonwealth of PA, DEP:

Joseph S. Cigan, Esquire

Curtis C. Sullivan, Esquire

(via electronic filing system)

For Appellants, Lancaster Against Pipelines

and Geraldine Nesbitt:

Jordan B. Yeager, Esquire

Mark L. Freed, Esquire

Lauren M. Williams, Esquire

(via electronic filing system)

App. 47

For Appellant, Sierra Club:

Joanne Kilgour, Esquire

Diana A. Csank, Esquire

(via electronic filing system)

For Permittee:

John Stoviak, Esquire

Pamela S. Goodwin, Esquire

Andrew T. Bockis, Esquire

(via electronic filing system)

App. 48

APPENDIX D

PENNSYLVANIA BULLETIN,

VOL. 46, NO. 17, APRIL 23, 2016

Water Quality Certification under Section,

401 of the Federal Clean Water Act for the

Atlantic Sunrise Pipeline Project

Natural Gas Pipeline Project and Related

Mitigation; FERC Docket No. CP15-138-000;

PADEP File No. WQ02-001

Northeast Region: Waterways & Wetlands Program, 2

Public Square, Wilkes-Barre, PA 18711, Joseph

Buczynski, Program Manager 570-826-2511

On April 5, 2016, the DEP issued Section 401 Water

Quality Certification to Transcontinental Gas Pipe

Line Company, LLC for the Atlantic Sunrise Pipeline

Project. The Pennsylvania Department of

Environmental Protection (Department) certifies that

the construction, operation and maintenance of the

Project complies with the applicable provisions of

sections 301—303, 306 and 307 of the Federal Clean

Water Act (33 U.S.C.A. §§ 1311—1313, 1316 and 1317).

The Department further certifies that the construction,

operation and maintenance of the projects complies

with Commonwealth water quality standards and that

the construction, operation and maintenance of the

projects does not violate applicable Commonwealth

water quality standards provided that the construction,

operation and maintenance of the projects complies

App. 49

with the conditions for this certification, including the

criteria and conditions of the following permits:

1. Discharge Permit—Transcontinental Gas Pipe

Line Company, LLC shall obtain and comply with a

Department National Pollutant Discharge Elimination

System (NPDES) permit for the discharge of water

from the hydrostatic testing of the pipeline pursuant to

Pennsylvania’s Clean Streams Law (35 P.S.

§§ 691.1—691.1001) and all applicable implementing

regulations (25 Pa. Code Chapter 92a).

2. Erosion and Sediment Control Permit—

Transcontinental Gas Pipe Line Company, LLC shall

obtain and comply with the Department’s Chapter 102

Erosion and Sediment Control General Permit for

Earth Disturbance Associated with Oil and Gas

Exploration, Production, Processing or Treatment

issued pursuant to Pennsylvania’s Clean Streams Law

and Storm Water Management Act (32 P.S.

§§ 680.1—680.17) and all applicable implementing

regulations (25 Pa. Code Chapter 102).

3. Water Obstruction and Encroachment Permits—

Transcontinental Gas Pipe Line Company, LLC shall

obtain and comply with a Department Chapter 105

Water Obstruction and Encroachment Permits for the

construction, operation and maintenance of all water

obstructions and encroachments associated with the

project pursuant to Pennsylvania’s Clean Streams Law,

Dam Safety and Encroachments Act (32 P.S.

§§ 673.1—693.27), and Flood Plain Management Act

(32 P.S. §§ 679.101—679.601.) and all applicable

implementing regulations (25 Pa. Code Chapter 105).

App. 50

4. Water Quality Monitoring—The Department

retains the right to specify additional studies or

monitoring to ensure that the receiving water quality

is not adversely impacted by any operational and

construction process that may be employed by

Transcontinental Gas Pipe Line Company, LLC.

5. Operation—For each Project under this

certification, Transcontinental Gas Pipe Line

Company, LLC shall at all times properly operate and

maintain all Project facilities and systems of treatment

and control (and related appurtenances) which are

installed to achieve compliance with the terms and

conditions of this Certification and all required

permits. Proper operation and maintenance includes

adequate laboratory controls, appropriate quality

assurance procedures, and the operation of backup or

auxiliary facilities or similar systems installed by

Transcontinental Gas Pipe Line Company, LLC.

6. Inspection—The Projects, including all relevant

records, are subject to inspection at reasonable hours

and intervals by an authorized representative of the

Department to determine compliance with this

Certification, including all required permits required,

and Pennsylvania’s Water Quality Standards. A copy

of this Certification shall be available for inspection by

the Department during such inspections of the

Projects.

7. Transfer of Projects—If Transcontinental Gas

Pipe Line Company, LLC intends to transfer any legal

or equitable interest in the Projects which is affected by

this Certification, Transcontinental Gas Pipe Line

Company, LLC shall serve a copy of this Certification

upon the prospective transferee of the legal and

App. 51

equitable interest at least thirty (30) days prior to the

contemplated transfer and shall simultaneously inform

the Department Regional Office of such intent. Notice

to the Department shall include a transfer agreement

signed by the existing and new owner containing a

specific date for transfer of Certification responsibility,

coverage, and liability between them.

8. Correspondence—All correspondence with and

submittals to the Department concerning this

Certification shall be addressed to the Department of

Environmental Protection, Northeast Regional Office,

Waterways and Wetlands Program, 2 Public Square,

Wilkes-Barre, PA 18701-1915.

9. Reservation of Rights—The Department may

suspend or revoke this Certification if it determines

that Transcontinental Gas Pipe Line Company, LLC

has not complied with the terms and conditions of this

Certification. The Department may require additional

measures to achieve compliance with applicable law,

subject to Transcontinental Gas Pipe Line Company,

LLC’s applicable procedural and substantive rights.

10. Other Laws—Nothing in this Certification shall

be construed to preclude the institution of any legal

action or relieve Transcontinental Gas Pipe Line

Company, LLC from any responsibilities, liabilities, or

penalties established pursuant to any applicable

federal or state law or regulation.

11. Severability—The provisions of this Certification

are severable and should any provision of this

Certification be declared invalid or unenforceable, the

remainder of the Certification shall not be affected

thereby.

App. 52

Any person aggrieved by this action may appeal,

pursuant to Section 4 of the Environmental Hearing

Board Act, 35 P.S. § 7614, and the Administrative

Agency Law, 2 Pa.C.S. Chapter 5A, to the

Environmental Hearing Board, Second Floor Rachel

Carson State Office Building, 400 Market Street, PO

Box 8457, Harrisburg, PA 17105-8457, 717-787-3483.

TDD users may contact the Board through the

Pennsylvania AT&T Relay Service, 800-654-5984.

Appeals must be filed with the Environmental Hearing

Board within 30 days of receipt of written notice of this

action unless the appropriate statute provides a

different time period. Copies of the appeal form and the

Board’s rules of practice and procedure may be

obtained from the Board. The appeal form and the

Board’s rules of practice and procedure are also

available in braille or on audiotape from the Secretary

to the Board at 717-787-3483. This paragraph does not,

in and of itself, create any right of appeal beyond that

permitted by applicable statutes and decisional law.

If you want to challenge this action, your appeal

must reach the board within 30 days. You do not need

a lawyer to file an appeal with the board.

Important legal rights are at stake, however, so you

should show this document to a lawyer at once. If you

cannot afford a lawyer, you may qualify for free pro

bono representation. Call the secretary to the board

(717-787-3483) for more information.

App. 53

DAM SAFETY

Central Office: Bureau of Waterways Engineering

and Wetlands, Rachel Carson State Office Building,

Floor 3, 400 Market Street, P.O. Box 8460, Harrisburg,

PA 17105-8460

D51-012. East Park Reservoir Dam, Aramark

Tower, 2nd Floor, 1101 Market Street, Philadelphia,

PA 19103. Permit issued to modify, operate, and

maintain East Park Reservoir Dam within Schuylkill

River Watershed, for the purpose of meeting the

Commonwealth’s regulations (Philadelphia, PA

Quadrangle Latitude: 35.985833; Longitude:

-75.188333) in Philadelphia City, Philadelphia County.

EROSION AND SEDIMENT CONTROL

The following Erosion and Sediment Control

permits have been issued.

Persons aggrieved by an action may appeal that

action to the Environmental Hearing Board (Board)

under section 4 of the Environmental Hearing Board

Act and 2 Pa.C.S. §§ 501—508 and 701—704. The

appeal should be sent to the Environmental Hearing

Board, Second Floor, Rachel Carson State Office

Building, 400 Market Street, PO Box 8457, Harrisburg,

PA 17105-8457, (717) 787-3483. TDD users may

contact the Board through the Pennsylvania AT&T

Relay Service, (800) 654-5984. Appeals must be filed

with the Board within 30 days of publication of this

notice in the Pennsylvania Bulletin unless the

appropriate statute provides a different time period.

Copies of the appeal form and the Board’s rules of

practice and procedure may be obtained from the

Board. The appeal form and the Board’s rules of

App. 54

practice and procedure are also available in Braille or

on audiotape from the Secretary to the Board at (717)

787-3483. This paragraph does not, in and of itself,

create a right of appeal beyond that permitted by

applicable statutes and decisional law.

For individuals who wish to challenge an action, the

appeal must reach the Board within 30 days. A lawyer

is not needed to file an appeal with the Board.

Important legal rights are at stake, however, so

individuals should show this notice to a lawyer at once.

Persons who cannot afford a lawyer may qualify for

free pro bono representation. Call the Secretary to the

Board at (717) 787-3483 for more information.

Southwest Region: Waterways & Wetlands Program

Manager, 400 Waterfront Drive, Pittsburgh, PA 152224745.

App. 55

APPENDIX E

UNITED STATES COURT OF APPEALS

FOR THE THIRD CIRCUIT

Nos. 16-2211, 16-2212, 16-2218, 16-2400

[Filed October 11, 2018]

__________________________________________

DELAWARE RIVERKEEPER

)

NETWORK; DELAWARE RIVERKEEPER )

MAYA VAN ROSSUM,

)

Petitioners, No. 16-2211

)

)

LANCASTER AGAINST PIPELINES,

)

Petitioner, No. 16-2212

)

)

GERALDINE NESBITT,

)

Petitioner, No. 16-2218

)

)

SIERRA CLUB,

)

Petitioner, No. 16-2400

)

)

v.

)

)

SECRETARY PENNSYLVANIA

)

DEPARTMENT OF ENVIRONMENTAL

)

PROTECTION; PENNSYLVANIA

)

DEPARTMENT OF ENVIRONMENTAL

)

PROTECTION,

)

Respondents

)

)

TRANSCONTINENTAL GAS PIPE LINE

)

COMPANY, LLC,

)

App. 56

Intervenor Respondent

)

_________________________________________ )

SUR PETITION FOR REHEARING

Present: SMITH, Chief Judge, MCKEE, AMBRO,

CHAGARES, JORDAN, HARDIMAN, GREENAWAY,

JR., VANASKIE, SHWARTZ, KRAUSE, RESTREPO,

BIBAS, and SCIRICA,1 Circuit Judges.

The petition for rehearing filed by petitioners in

Nos. 16-2211, 16-2212 and 16-2400 having been

submitted to the judges who participated in the

decision of this Court and to all the other available

circuit judges of the circuit in regular active service,

and no judge who concurred in the decision having

asked for rehearing, and a majority of the judges of the

circuit in regular service not having voted for

rehearing, the petition for rehearing by the panel and

the Court en banc, is denied.

BY THE COURT,

s/ Thomas M. Hardiman

Circuit Judge

Dated: October 11, 2018

CJG/cc: All Counsel of Record

1

Judge Scirica’s vote is limited to panel rehearing.

This is a copy of a public record, reproduced as it was published. It is not legal advice, and it may not be the version a court would rely on. Check the official source before you cite it.

A word about cookies

We need a few to keep you signed in and the library working. The rest help us see which pages people use and where they get stuck. They stay off unless you say yes.