Petition for Writ of Certiorari — Delaware Riverkeeper Network, et al., Petitioners v. Secretary, Pennsylvania Department of Environmental Protection, et al.
Supreme Court briefJan 9, 2019
Ask Donna
What actually matters in this document.
Text
NO.
In the Supreme Court of the United States
DELAWARE RIVERKEEPER NETWORK; DELAWARE
RIVERKEEPER, MAYA VAN ROSSUM, AND
LANCASTER AGAINST PIPELINES,
Petitioners,
v.
SECRETARY PENNSYLVANIA DEPARTMENT OF
ENVIRONMENTAL PROTECTION; PENNSYLVANIA
DEPARTMENT OF ENVIRONMENTAL PROTECTION;
AND TRANSCONTINENTAL GAS PIPE LINE
COMPANY, LLC,
Respondents.
On Petition for Writ of Certiorari to the
United States Court of Appeals for the Third Circuit
PETITION FOR WRIT OF CERTIORARI
AARON STEMPLEWICZ
Counsel of Record
DELAWARE RIVERKEEPER NETWORK
925 Canal Street
Suite 3701
Bristol, PA 19007
(215) 369-1188
Aaron@delawareriver
keeper.org
Counsel for Petitioners
Delaware Riverkeeper
Network and
The Delaware Riverkeeper
MARK L. FREED
CURTIN & HEEFNER
2005 South Easton Road
Suite 100
Doylestown, PA 18901
(267) 898-0570
Counsel for Petitioner
Lancaster Against
Pipelines
Becker Gallagher · Cincinnati, OH · Washington, D.C. · 800.890.5001
i
QUESTIONS PRESENTED
Section 401 of the Clean Water Act requires an
applicant for an interstate natural gas pipeline project
to obtain “a certification from the State in which the
discharge . . . will originate . . . that any such discharge
will comply with” that State’s water-quality standards.
33 U.S.C. § 1341(a)(1). The Clean Water Act leaves the
states with primary responsibility to regulate such
discharges based on the state’s individual water quality
standards. Each state has its own unique state defined
administrative process for the issuance and review of
any such water quality certifications. The Third Circuit
ruled that despite the fact that Pennsylvania’s
administrative review process was not complete, and
therefore not “final” pursuant to state law, Section
717r(d)(1) of the Natural Gas Act required an appeal of
a water quality certificate to be heard directly by the
Third Circuit Court of Appeals. In doing so, the Third
Circuit discarded Pennsylvania’s statutory definition of
finality, and instead inserted its own federal standard
of finality.
1. May a federal court preempt a state’s
administrative review process by substituting a federal
finality standard for a state finality standard, where
the state finality standard is clearly defined by state
law?
2. Whether the federal court’s preemption of the
Pennsylvania Environmental Hearing Board’s state
administrative review process violates the Tenth
Amendment?
ii
LIST OF PARTIES
Petitioners are the Delaware Riverkeeper Network
and the Delaware Riverkeeper, Maya van Rossum, and
Lancaster Against Pipelines. Respondents are the
Secretary of the Pennsylvania Department of
Environmental Protection and the Pennsylvania
Department of Environmental Protection. IntervenorRespondent is Transcontinental Gas Pipe Line
Company LLC.
CORPORATE DISCLOSURE
This Petition is not filed on behalf of a corporation.
iii
TABLE OF CONTENTS
QUESTIONS PRESENTED . . . . . . . . . . . . . . . . . . . i
LIST OF PARTIES . . . . . . . . . . . . . . . . . . . . . . . . . . ii
CORPORATE DISCLOSURE . . . . . . . . . . . . . . . . . . ii
TABLE OF AUTHORITIES . . . . . . . . . . . . . . . . . . vi
PETITION FOR A WRIT OF CERTIORARI . . . . . . 1
OPINIONS BELOW . . . . . . . . . . . . . . . . . . . . . . . . . 3
JURISDICTION . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3
CONSTITUTIONAL AND STATUTORY
PROVISIONS INVOLVED . . . . . . . . . . . . . . . . . . . . 3
STATEMENT OF THE CASE . . . . . . . . . . . . . . . . . 4
A. Statutory Background . . . . . . . . . . . . . . . . 4
B. Appeals Process . . . . . . . . . . . . . . . . . . . . . 5
1. Under The Natural Gas Act . . . . . . . . 5
2. Under State Law . . . . . . . . . . . . . . . . . 6
C. Procedural History . . . . . . . . . . . . . . . . . . 6
REASONS FOR ALLOWANCE OF THE WRIT . . . 8
I.
UNDER RULE 10(a) THIS COURT SHOULD
RESOLVE THE CIRCUIT SPLIT OVER
WHETHER STATE ADMINISTRATIVE LAW
PRO CED URES ARE PRESERVED
PURSUANT TO APPEALS TAKEN UNDER
SECTION 717r(d)(1) OF THE NATURAL
GAS ACT . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 8
iv
A. The Third Circuit’s Opinion In DRN
Irreconcilably Conflicts With The First
Circuit’s Opinion In Berkshire And The
Second Circuit’s Opinion In Murphy . . . . 8
1. The Third Circuit’s Finding Of
Finality In DRN Conflicts With The
First Circuit’s Holding In Berkshire . . 9
i. The Determination Of The Finality
Of A State Issued Permit Must
Respect State Law . . . . . . . . . . . . . 9
ii. The Substantive Functions Of The
Administrative Review Process
in DRN and Berkshire Are The
Same . . . . . . . . . . . . . . . . . . . . . . . 14
2. The Third Circuit’s Finding Of Finality
In DRN Conflicts With The Second
Circuit’s Holding In Murphy . . . . . . . 16
B. The Third Circuit’s DRN Decision Has
Resulted In An Intra-Circuit Split That
Preserved The Administrative Review
Process In New Jersey But Preempted
The Same Process In Pennsylvania . . . . 21
C. The Third Circuit’s Decision In DRN
Condemns The Third Circuit To
Reviewing Incomplete And Inadequate
Records In Section 717r(d)(1) Appeals
And Strips Aggrieved Parties Of Their
Due Process Rights . . . . . . . . . . . . . . . . . 27
v
III.
THE QUESTIONS PRESENTED ARE
EXCEPTIONALLY IMPORTANT AND
HAVE WIDE-RANGING IMPACT . . . . . . . 34
CONCLUSION . . . . . . . . . . . . . . . . . . . . . . . . . . . . 35
APPENDIX
Appendix A Opinion in the United States Court of
Appeals for the Third Circuit
(September 4, 2018) . . . . . . . . . . . App. 1
Appendix B Opinion and Order on the Termination
of the Above-Captioned Appeal in the
Commonwealth of Pennsylvania
Environmental Hearing Board
(June 2, 2017) . . . . . . . . . . . . . . . App. 27
Appendix C Opinion and Order on Request to
Dismiss in the Commonwealth of
Pennsylvania Environmental Hearing
Board
(May 10, 2017) . . . . . . . . . . . . . . App. 38
Appendix D Pennsylvania Bulletin, Vol. 46, No. 17,
Water Quality Certification under
Section, 401 of the Federal Clean
Water Act for the Atlantic Sunrise
Pipeline Project
(April 23, 2016) . . . . . . . . . . . . . App. 48
Appendix E Order Denying Petition for Rehearing
by the Panel Court En Banc in the
United States Court of Appeals for the
Third Circuit
(October 11, 2018) . . . . . . . . . . . App. 55
vi
TABLE OF AUTHORITIES
CASES
Alabama Rivers Alliance v. F.E.R.C.,
325 F.3d 290 (D.C. Cir. 2003) . . . . . . . . . . . 32, 33
Alcoa Power Generating Inc. v. FERC,
643 F.3d 963 (D.C. Cir. 2011) . . . . . . . . . . . . . . 20
Bell v. New Jersey,
461 U.S. 773 (1983) . . . . . . . . . . . . . . . . . . . . . . 10
Berkshire Environmental Action Team, Inc. v.
Tennessee Gas Pipeline, LLC,
851 F.3d 105 (1st Cir. 2017) . . . . . . . . . . . passim
Bradley and Amy Simon v. DEP,
EHB Docket No. 2017-019-L, 2017 WL 2399755
(May 25, 2017) . . . . . . . . . . . . . . . . . . . . . . . . . . 12
Camp v. Pitts,
411 U.S. 138 (1973) . . . . . . . . . . . . . . . . . . . . . . 30
Center for Coalfield Justice and Sierra Club v. DEP,
EHB Docket No. 2016-155-B, 2017 WL 663900
(February 1, 2017) . . . . . . . . . . . . . . . . . . . . 12, 13
Clifton Power v. FERC,
294 F.3d 108 (D.C. Cir. 2002) . . . . . . . . . . . . . . 20
Commonwealth v. Derry Township,
314 A.2d 868 (Pa. Cmwlth. 1973), modified,
351 A.2d 606 (Pa. 1976) . . . . . . . . . . . . . . . . . . . 27
Consol Pa. Coal Co. v. Dept. of Env’tl Prot.,
2011 WL 4943794 (Pa. Env. Hrg. Bd.,
Aug. 26, 2011) . . . . . . . . . . . . . . . . . . . . . . . . . . 31
vii
Darby v. Cisneros,
509 U.S. 137 (1993) . . . . . . . . . . . . . . . . . . . . . . 13
Devia v. NRC,
492 F.3d 421 (D.C. Cir. 2007) . . . . . . . . . . . . . . 20
Domiano v. Commonwealth, Department of
Environmental Resources,
713 A.2d 713 (Pa. Cmwlth. 1998) . . . . . . . . . . . 27
Energy Transfer Partners, LP v. FERC,
567 F.3d 134 (5th Cir. 2009) . . . . . . . . . . . . . . . 20
Fiore v. Department of Environmental Protection,
655 A.2d 1081 (Pa. Cmwlth. 1995)
modified, 351 A.2d 606 (Pa. 1976) . . . . . . . . . . 27
Global Tower Assets, LLC v. Town of Rome,
810 F.3d 77 (1st Cir. 2016) . . . . . . . . . . . . . . . . 13
Harman Coal Co. v. Com., Dept. of Environmental
Resources, 384 A.2d 289 (Pa. Cmwlth. 1978) . . 19
Hoehne v. County of San Benito,
870 F.2d 529 (9th Cir. 1989) . . . . . . . . . . . . . . . 18
Kiak v. Crown Equip. Corp.,
989 A.2d 385 (Pa. Super. Ct. 2010) . . . . . . . . . . 19
Kurtz v. Verizon New York, Inc.,
758 F.3d 506 (2d Cir. 2014) . . . . . . . . . . . . . . . . 17
Leatherwood, Inc. v. Com., Dept. of
Environmental Protection,
819 A.2d 604 (Pa. Cmwlth. 2003) . . . . . . . . 14, 28
Morcoal Company v. Dep’t of Envit. Resources,
459 A.2d 1303 (Pa. Cmwlth. 1983) . . . . . . . . . . 28
viii
Murphy v. Nat’l Collegiate Athletic Ass’n,
138 S. Ct. 1461 (2018) . . . . . . . . . . . . . . . . . . . . 33
Murphy v. New Milford Zoning Comm’n,
402 F.3d 342 (2d Cir. 2005) . . . . . . . . . . . . passim
New York v. United States,
505 U.S. 144 (1992) . . . . . . . . . . . . . . . . . . . . . . 34
Papago Tribal Utility Auth. v. FERC,
628 F.2d 235 . . . . . . . . . . . . . . . . . . . . . . . . . . . . 20
Rhode Island v. EPA,
378 F.3d 19 (1st Cir. 2004) . . . . . . . . . . . . . . . . 10
S. Ohio Coal Co. v. Office of Surface Mining,
Reclamation & Enf’t, Dep’t of Interior,
20 F.3d 1418 (6th Cir. 1994) . . . . . . . . . . . . . . . 11
Spence v. Zimmerman,
873 F.2d 256 (11th Cir. 1989) . . . . . . . . . . . . . . 18
State of Tex. v. U.S. Dept. of Energy,
764 F.2d 278 (5th Cir. 1985) . . . . . . . . . . . . . . . 19
Taylor Inv., Ltd. v. Upper Darby Tp.,
983 F.2d 1285 (3d Cir. 1993) . . . . . . . . . . . . . . . 18
Tire Jockey Serv., Inc. v. Dep’t of Envtl. Prot.,
915 A.2d 1165 (2007) . . . . . . . . . . . . . . . . . . . . . 15
Township of Bordentown, New Jersey v. Federal
Energy Regulatory Commission,
903 F.3d 234 (3d Cir. 2018) . . . . . 8, 21, 22, 23, 26
Transcontinental Gas Pipe Line Co, LLC,
158 F.E.R.C. ¶ 61125 (2017) . . . . . . . . . . . . . . . . 4
ix
United States v. Cooper,
482 F.3d 658 (4th Cir. 2007) . . . . . . . . . . . . . . . 11
Weaver’s Cove Energy, LLC v. State of Rhode
Island Dept. of Env’tl Management,
524 F.3d 1330 (D.C. Cir. 2008) . . . . . . . . . . . . . 32
Williamson Cly. Reg’l Planning Comm’n v.
Hamilton Bank of Johnson City,
473 U.S. 172 (1985) . . . . . . . . . . . . . . . . . . . 18, 19
CONSTITUTIONS AND STATUTES
U.S. Const. amend. X . . . . . . . . . . . . . . . . . . . 2, 3, 32
15 U.S.C. § 717b(d) . . . . . . . . . . . . . . . . . . . . . . . . . . 5
15 U.S.C. § 717f(c)(1)(A) . . . . . . . . . . . . . . . . . . . . . . 4
15 U.S.C. § 717f(e) . . . . . . . . . . . . . . . . . . . . . . . . . . . 4
15 U.S.C. § 717r(d)(1) . . . . . . . . . . . . . . . . . . . passim
15 U.S.C. § 717r(d)(2) . . . . . . . . . . . . . . . . . . . . . . . 32
15 U.S.C. § 717r(d)(3) . . . . . . . . . . . . . . . . . . . . . . . 32
28 U.S.C. § 1254(1) . . . . . . . . . . . . . . . . . . . . . . . . . . 3
33 U.S.C. § 1251(b) . . . . . . . . . . . . . . . . . . . . . . . . . . 1
33 U.S.C. § 1341(a) . . . . . . . . . . . . . . . . . . . . . passim
33 U.S.C. § 1341(a)(1) . . . . . . . . . . . . . . . . . . . . . 4, 33
310 CMR 1.01(5)(a) . . . . . . . . . . . . . . . . . . . . . . . . 15
310 CMR 1.01(5)(b) . . . . . . . . . . . . . . . . . . . . . . . . 15
310 CMR 1.01(12) . . . . . . . . . . . . . . . . . . . . . . . . . . 15
310 CMR 1.01(14)(f) . . . . . . . . . . . . . . . . . . . . . . . . 15
x
314 CMR 9.10(1) . . . . . . . . . . . . . . . . . . . . . . . . . . . 14
310 MCR § 1.01(c) . . . . . . . . . . . . . . . . . . . . . . . . . . 11
310 MASS. CODE REGS. 9.09(1)(e) . . . . . . . . . . . . 25
314 MCR § 9.10(1) . . . . . . . . . . . . . . . . . . . . . . . . . . 11
N.J.A.C. 7:7-28.3(b) . . . . . . . . . . . . . . . . . . . . . . . . . 25
N.J.A.C. 7:7A-21.3(b) . . . . . . . . . . . . . . . . . . . . . . . . 25
N.J.A.C. 7:14A-17.6 . . . . . . . . . . . . . . . . . . . . . . . . . 26
1 Pa. Code Chapters 31–35 . . . . . . . . . . . . . . . . . . . 28
1 Pa. Code Chapter 1021 . . . . . . . . . . . . . . . . . . . . . 28
25 Pa. Code § 92a . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5
25 Pa. Code § 102 . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5
25 Pa. Code § 105 . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5
25 Pa. Code § 1021.51 . . . . . . . . . . . . . . . . . . . . . . . 14
25 Pa. Code § 1021.52 . . . . . . . . . . . . . . . . . . . . . . 6, 7
25 Pa. Code §§ 1021.101-1021.134 . . . . . . . . . . . . . 28
25 Pa. Code § 1021.102 . . . . . . . . . . . . . . . . . . . . . . 15
25 Pa. Code § 1021.117 . . . . . . . . . . . . . . . . . . . . . . 15
25 Pa. Code § 1021.201 . . . . . . . . . . . . . . . . . . . . . . 15
2 PA. CONS. STAT. Ch. 5, Subchapter A . . . . . . . 28
42 Pa. C.S. § 723(a) . . . . . . . . . . . . . . . . . . . . . . . . . . 6
42 Pa. C.S. § 763(a) . . . . . . . . . . . . . . . . . . . . . . . . . . 6
32 P.S. § 673.1 et seq. . . . . . . . . . . . . . . . . . . . . . . . . 5
xi
32 P.S. § 679.101 et seq. . . . . . . . . . . . . . . . . . . . . . . . 5
32 P.S. § 680.1 et seq. . . . . . . . . . . . . . . . . . . . . . . . . 5
35 P.S. § 691.1 et seq. . . . . . . . . . . . . . . . . . . . . . 5, 29
35 P.S. § 7514 . . . . . . . . . . . . . . . . . . . . . . . . . . 14, 15
35 P.S. § 7514(a) . . . . . . . . . . . . . . . . . . . . . . . . . 7, 28
35 P.S. § 7514(b) . . . . . . . . . . . . . . . . . . . . . . . . . . . 28
35 P.S. § 7514(c) . . . . . . . . . . . . . . . . 12, 13, 14, 15, 28
35 P.S. § 7514(d) . . . . . . . . . . . . . . . . . . . . . . . . . . . 31
35 P.S. § 7514(d)(1) . . . . . . . . . . . . . . . . . . . . . . . . . 12
RULE
Sup. Ct. R. 10(a) . . . . . . . . . . . . . . . . . . . . . . . . . . . . 8
OTHER AUTHORITY
Channing Jones, “The Natural Gas Act, State
Environmental Policy, and the Jurisdiction of
the Federal Circuit Courts,” 42 Colum. J. Envtl.
L. 163 (2016) . . . . . . . . . . . . . . . . . . . . . . . . . . . . 23
1
PETITION FOR A WRIT OF CERTIORARI
Petitioners Delaware Riverkeeper Network, the
Delaware Riverkeeper, Maya van Rossum, and
Lancaster Against Pipelines petition for a writ of
certiorari to review the judgment of the United States
Court of Appeals for the Third Circuit.
This case strikes at the heart of our federal system.
State governments have traditionally played a central
role in regulating environmental impacts of various
types of construction projects. Congress’ intent to
maintain and reinforce this “cooperative federalism”
framework is explicitly stated in the Clean Water Act:
“It is the policy of the Congress to recognize, preserve,
and protect the primary responsibilities and rights of
States to prevent, reduce, and eliminate pollution,
[and] to plan the development and use . . . of land and
water resources.” 33 U.S.C. § 1251(b). Here, a federal
court decision has upended this balanced framework
and stripped Pennsylvania, and potentially many other
states, from discharging its statutory role in issuing
certifications based on state law.
Specifically, the Third Circuit in Delaware
Riverkeeper Network, et al. v. Secretary Pennsylvania
Department of Environmental Protection, et al., 903
F.3d 65 (3d Cir. 2018) (hereinafter “DRN”), supplanted
Pennsylvania’s definition of finality with regard to a
state issued certification and instead substituted a
federal standard. In doing so, the Third Circuit has
prematurely invoked the Natural Gas Act’s appeal
mechanism, which has wrought uncertainty as to
which states will have their administrative review
process preserved and which states will have them
preempted. Indeed, this uncertainty has already
2
materialized in the Third Circuit itself, whereby the
administrative review process in Pennsylvania is
preempted, while in neighboring New Jersey the same
administrative process is unchanged. Further, the
Third Circuit’s decision irreconcilably conflicts with the
way in which the First Circuit addressed the
preemptive effect of the Natural Gas Act. Furthermore,
the DRN decision commandeers Pennsylvania’s
legislative and administrative processes in violation of
the 10th Amendment.
Here, Petitioners Delaware Riverkeeper Network,
the Delaware Riverkeeper, and Lancaster Against
Pipelines’ challenged the issuance of a conditional
water quality certification pursuant to Section 401 of
the Clean Water Act, 33 U.S.C. § 1341(a) (“water
quality certification”). The Pennsylvania Department
of Environmental Protection (“Department”) issued the
Section 401 water quality certification to
Transcontinental Pipeline Company, LLC (“Transco”)
for the Atlantic Sunrise Pipeline Project (“Project”) on
or about April 5, 2016. The issuance was noticed in the
Pennsylvania Bulletin on April 23, 2016. The notice
directed any person aggrieved by the action to an
appeal with the Pennsylvania Environmental Hearing
Board (hereinafter “Board”). On or about May 5, 2016,
Petitioners filed the above-captioned action for review
of the Department’s decision to grant water quality
certification for the Project. On or about May 5, 2016,
Lancaster Against Pipelines also filed an
administrative appeal of the Department’s decision
with the Board.
There are no disputed issues of fact for the Court to
resolve. The issues are limited to matters of law.
3
Furthermore, the questions to be resolved by the Court
have industry wide import, as the this Court’s
resolution will determine the preemption or
preservation of state administrative review processes
for all appeals taken pursuant to Section 717r(d)(1) of
the Natural Gas Act in every state.
OPINIONS BELOW
The Court of Appeals opinion is reported at
Delaware Riverkeeper Network, et al. v. Secretary
Pennsylvania Department of Environmental Protection,
et al., 903 F.3d 65 (3d Cir. 2018). Petitioners’ Appendix
(“App.”) A.
JURISDICTION
The judgment of the Third Circuit was entered on
September 4, 2018. This Court’s jurisdiction is invoked
under 28 U.S.C. § 1254(1).
CONSTITUTIONAL AND STATUTORY
PROVISIONS INVOLVED
The Tenth Amendment to the United States
Constitution provides: “The powers not delegated to the
United States by the Constitution, nor prohibited by it
to the states, are reserved to the states respectively, or
to the people.”
15 U.S.C. § 717r(d)(1) of the Natural Gas Act states:
“The United States Court of Appeals for the circuit in
which a facility subject to section 717b of this title or
section 717f of this title is proposed to be constructed,
expanded, or operated shall have original and exclusive
jurisdiction over any civil action for the review of an
order or action of a . . . State administrative agency
4
acting pursuant to Federal law to issue, condition, or
deny any permit, license, concurrence, or approval . . .
required under Federal law . . . .”
STATEMENT OF THE CASE
A. Statutory Background
The Natural Gas Act prohibits construction or
operation of a natural gas pipeline without a
Certificate of Public Convenience and Necessity from
the Federal Energy Regulatory Commission
(“Commission”). 15 U.S.C. § 717f(c)(1)(A). The Natural
Gas Act further requires that, prior to issuing a
Certificate of Public Convenience and Necessity, the
applicant must demonstrate compliance with the many
other federal laws and regulations that apply to the
pipeline project. See id. § 717f(e) (authorizing the
Commission to grant Certificates subject to “reasonable
terms and conditions”). In the instant matter the
Commission found that Transco demonstrated such
compliance because “it has received all applicable
authorizations required under federal law.”
Transcontinental Gas Pipe Line Co, LLC, 158 F.E.R.C.
¶ 61125, at App. C ¶ 10 (2017).
One of the applicable authorizations is a water
quality certification issued under Section 401 of the
Clean Water Act. 33 U.S.C. § 1341(a)(1). Section 401
requires a permit applicant to obtain “a certification
from the State in which the discharge . . . will originate
[to ensure] that any such discharge will comply with”
that State’s water-quality standards. Id. Therefore, in
order to receive a Certificate of Public Convenience and
Necessity from the Commission, a pipeline company
must apply for and receive water quality certifications
5
from each of the affected states. Pennsylvania has
specific statutes, regulations, and administrative
procedures that relate to the process of obtaining a
water quality certification. See Pennsylvania Clean
Streams Law, 35 P.S. § 691.1 et seq., the Stormwater
Management Act, 32 P.S. § 680.1 et seq., the Dam
Safety and Encroachments Act, 32 P.S. § 673.1 et seq.,
and the Flood Plain Management Act, 32 P.S. § 679.101
et seq., and the regulations found in 25 Pa. Code §§ 92a,
102, 105.
B. Appeals Process
1. Under The Natural Gas Act
The Natural Gas Act provides:
The United States Court of Appeals for the
circuit in which a facility subject to section 717b
of this title or section 717f of this title is
proposed to be constructed, expanded, or
operated shall have original and exclusive
jurisdiction over any civil action for the review of
an order or action of a . . . State administrative
agency acting pursuant to Federal law to issue,
condition, or deny any permit, license,
concurrence, or approval . . . required under
Federal law . . . .
15 U.S.C. § 717r(d)(1) (hereafter, “§ 717r(d)(1)”). The
Natural Gas Act does not amend the Clean Water Act
by implication nor displace the primacy Congress
expressly assigned to state control of water pollution.
See 15 U.S.C. § 717b(d) (nothing in this chapter affects
the rights of States under . . . the [Clean Water Act]”).
6
2. Under State Law
In Pennsylvania, after the Pennsylvania
Department of Environmental Protection issues a
water quality certification, aggrieved parties are
afforded the right to appeal such a decision for
administrative review before the Pennsylvania
Environmental Hearing Board within 30 days. 25 Pa.
Code § 1021.52.
Decisions of the Board may be
appealed to the appropriate federal or state court. 42
Pa. C.S. §§ 763(a), 723(a).
C. Procedural History
In response to the requirements of the Natural Gas
Act and Clean Water Act, Transco was required to
obtain a water quality certification from the
Pennsylvania Department of Environmental Protection
for the Project. App.48-54. In 2015, Transco formally
applied both to the Commission for a Certificate of
Public Convenience and Necessity and to the
Department for a Section 401 water quality
certification. App.6. Shortly thereafter, the Department
published notice in the Pennsylvania Bulletin
(Pennsylvania’s analogue to the Federal Register) of its
intent to grant Transco a water quality certification.
App.48-54. In April 2016, the Department issued
Transco’s Water Quality Certification. App.6.
In response to the Department’s notice, the
Petitioners filed two parallel challenges to the issued
Water Quality Certification. First, Delaware
Riverkeeper Network, the Delaware Riverkeeper, Maya
van Rossum, and Lancaster Against Pipelines sought
relief directly from the Third Circuit Court of Appeals
under the exclusive review provision of the Natural
7
Gas Act, 15 U.S.C. § 717r(d)(1). Second, Lancaster
Against Pipelines appealed the Department’s decision
to the Pennsylvania Environmental Hearing Board.1
Pennsylvania law specifically vests the Board with
the exclusive “power and duty to hold hearings and
issue adjudications” on orders, permits, licenses and
decisions of the Department, including a Section 401
water quality certification. 35 P.S. § 7514(a); see also 25
Pa. Code § 1021.52. In fact, the Board has thrice
determined that it has jurisdiction over precisely this
type of appeal. App.43; App.33-34; Delaware
Riverkeeper Network v. Commonwealth of
Pennsylvania, Department of Environmental Protection,
EHB Docket No. 2012-196-M, 2013 WL 604393
(February 1, 2013).
Nevertheless, the Board stayed its proceedings
pending a jurisdictional ruling from the Third Circuit.
In the Third Circuit case, petitioners argued that the
Board has jurisdiction over the Department’s issuance
of Transco’s Water Quality Certification and must
provide finality by administratively reviewing the
proceeding before the Third Circuit hears any appeal
pursuant to Section 717r(d)(1). App.8. On September 4,
2018, the Third Circuit rejected Petitioners’ arguments,
and held that the Natural Gas Act preempted
Pennsylvania’s administrative review process at the
Board for the water quality certification. App.1-26.
1
See Lancaster Against Pipelines v. Commonwealth, No. 2016-075L (Pa. Envtl. Hrg. Bd.).
8
REASONS FOR ALLOWANCE OF THE WRIT
I.
UNDER RULE 10(a) THIS COURT SHOULD
RESOLVE THE CIRCUIT SPLIT OVER
WHETHER STATE ADMINISTRATIVE LAW
PROCEDURES ARE PRESERVED
PURSUANT TO APPEALS TAKEN UNDER
SECTION 717r(d)(1) OF THE NATURAL
GAS ACT
A. The Third Circuit’s Opinion In DRN
Irreconcilably Conflicts With The First
Circuit’s Opinion In Berkshire And The
Second Circuit’s Opinion In Murphy
The question raised in DRN was whether or not the
issuance of a Clean Water Act Section 401 water
quality certificate by the Department was a final action
subject to § 717r(d)(1) of the Natural Gas Act such that
the state administrative review process was entirely
preempted.
The Third Circuit’s resolution of that question
irreconcilably conflicts with the First Circuit’s handling
of precisely that same question in Berkshire
Environmental Action Team, Inc. v. Tennessee Gas
Pipeline, LLC, 851 F.3d 105 (1st Cir. 2017). It also
conflicts with the Second Circuit’s holding in Murphy
v. New Milford Zoning Comm’n, 402 F.3d 342 (2d Cir.
2005). Lastly, not only is the Third Circuit’s decision in
DRN at conflict with decisions of the First Circuit and
Second Circuit, but the decision cannot be reconciled
with the Third Circuit’s later decision in Township of
Bordentown, New Jersey v. Federal Energy Regulatory
Commission, 903 F.3d 234 (3d Cir. 2018).
9
1. The Third Circuit’s Finding Of
Finality In DRN Conflicts With The
First Circuit’s Holding In Berkshire
The First Circuit squarely addressed the scope of
the preemptive effect of Section 717r(d)(1) in Berkshire
Environmental Action Team, Inc. v. Tennessee Gas
Pipeline, LLC, 851 F.3d 105 (1st Cir. 2017) (hereinafter
“Berkshire”), where the court found that the state
administrative appeal process is preserved and must be
completed prior to United States Court of Appeals
review pursuant to Section 717r(d)(1). Here, the Third
Circuit came to the opposite conclusion when faced
with the same question.
i. The Determination Of The
Finality Of A State Issued Permit
Must Respect State Law
The lynchpin of the Third Circuit’s ruling in DRN,
is that the “finality requirement itself, along with the
presumption that Congress intended us to apply it, are
creatures of federal, not state, law.” App.10. The court
applied “a federal finality standard to determine
whether Congress has made the results of that process
reviewable under the Natural Gas Act.” App.12. This is
a crucial determination because to the extent state
law – and not federal law – informs the finality
determination for a state issued permit there is no
question that the Department’s action was not final.
The Third Circuit does not cite any authority
supporting its decision to disregard this aspect of
Pennsylvania law, and, in any case, the Third Circuit’s
conclusion expressly conflicts with the First Circuit’s
interpretation of finality in Berkshire. App.14-16. As
10
such, the Third Circuit prematurely invoked Section
717r(d)(1), prior to “final” agency action.
The Berkshire panel was faced with the question of
whether the federal circuit court had jurisdiction to
review a water quality certification issued by the
Massachusetts Department of Environmental
Protection (“MassDEP”) prior to the completion of a
state administrative appeal process. Berkshire, 851
F.3d at 108. The panel first noted that it is “a longstanding and well-settled ‘strong presumption . . . that
judicial review will be available only when agency
action becomes final.’” Id. at 109 (quoting Bell v. New
Jersey, 461 U.S. 773, 778 (1983)). “In a literal sense,
state agencies repeatedly take ‘action’ in connection
with applications for water quality certifications . . . we
see no reason, though, to think that Congress wanted
us to exercise immediate review over such preliminary
and numerous steps that state agencies may take in
processing an application before they actually act in
the more relevant and consequential sense of granting
or denying it.” Id. at 108. “An agency action is ‘final’
only where it ‘represents the culmination of the
agency’s decision making process and conclusively
determines the rights and obligations of the parties
with respect to the matters at issue.’” Id. at 111
(quoting Rhode Island v. EPA, 378 F.3d 19, 23 (1st Cir.
2004)).
To determine whether MassDEP’s action was final,
the First Circuit relied on the “substance of the
Massachusetts regulatory regime” to direct its decision.
Id. at 112. In doing so, the Berkshire panel examined
several provisions of the Massachusetts Code to come
to its conclusion on finality. Specifically, the panel
11
looked to portions of state law which mandate that only
after the administrative process is complete is there an
“issuance of a final decision.” Id. at 112 (citing 310
MCR § 1.01(c)); see also id. (citing 314 MCR § 9.10(1)).
Relying on these provisions, the Berkshire panel found
state law dictated that the “initial letter granting a
water quality certification . . . [was] not a final agency
action.” Id.
Additionally, the First Circuit concluded, “[w]e see
no indication that Congress otherwise intended to
dictate how (as opposed to how quickly) MassDEP
conducts its internal decision-making before finally
acting.” Id. at 113. The Berkshire panel’s reliance on
state law to determine finality respects the wellestablished “scheme of cooperative federalism” upon
which the Clean Water Act is built. United
States v. Cooper, 482 F.3d 658, 667 (4th Cir. 2007); see
also S. Ohio Coal Co. v. Office of Surface Mining,
Reclamation & Enf’t, Dep’t of Interior, 20 F.3d 1418,
1427 (6th Cir. 1994) (“[T]he CWA sets up a system of
‘cooperative federalism,’ in which states may choose to
be primarily responsible for running federally-approved
programs”).
Rather than respecting this system of cooperative
federalism, the Third Circuit, in DRN, discarded the
way in which Pennsylvania defined finality and
inserted its own federal standard, usurping the power
of administrative review from Pennsylvania’s longestablished state administrative review process.
App.10. Pennsylvania state law leaves no doubt on the
issue of finality, by expressly and unequivocally stating
that “no action of [the Department] adversely affecting
a person shall be final as to that person until the
12
person has had the opportunity to appeal the action to
the [B]oard . . . .” 35 P.S. § 7514(c). As further
explained by the Board:
As far as the [Board] is concerned, a
[Department] action only becomes final following
an opportunity to appeal the action to the
Environmental Hearing Board. Pennsylvania
law is very clear on this point: “[N]o action of
the department [of environmental protection]
adversely affecting a person shall be final as to
that person until the person has had an
opportunity to appeal the action to the
[environmental hearing] board. . . .” 35 P.S.
§ 7514(c). Courts in Pennsylvania have long
held “that a Department action is not final
until an adversely affected party has had
an opportunity to appeal the action to this
Board.”
App.33-34 (emphasis added). In this context, the Board
has stated that “[w]hether a state agency action is final
is a question of state law,” not federal law. App. 33.
As such, Pennsylvania law dictates that no action of
the Department is “culminated” or “conclusively
decided” unless and until a person has had the
opportunity for review by the Board. See 35 P.S.
§ 7514(c). Indeed, a proper appeal to the Board may
very well negate the Department’s initial certificate
approval by virtue of the Board’s power to grant a
supersedeas upon cause shown. 35 P.S. § 7514(d)(1); see
also Bradley and Amy Simon v. DEP, EHB Docket No.
2017-019-L, 2017 WL 2399755 (May 25, 2017); Center
for Coalfield Justice and Sierra Club v. DEP, EHB
Docket No. 2016-155-B, 2017 WL 663900 (February 1,
13
2017). Therefore, “there is no doubt whatsoever that
the Department’s certification of Transco’s project was
not a final action.” App.43.
Furthermore, this Court in Darby v. Cisneros, 509
U.S. 137 (1993), recognized that an agency may require
an initial administrative decision to be appealed
administratively before it may be deemed to be the
kind of “final” administrative action that may be
challenged in court. Id. at 153–54; see also Global
Tower Assets, LLC v. Town of Rome, 810 F.3d 77, 86
(1st Cir. 2016) (administrative review can “impose[] an
exhaustion requirement and make[] plain that the
underlying agency action is not a final one”) (internal
quotations omitted) (emphasis original). Here,
Pennsylvania has enacted a comprehensive regulatory
and administrative scheme for the protection of the
environment within the Commonwealth, and, pursuant
to this structure, the water quality certificate at issue
was not “final”. See 35 P.S. § 7514(c). This scheme
specifically dictates, in no uncertain terms, that
Department action is not final, and therefore subject to
Section 717r(d)(1) of the Natural Gas Act, until
aggrieved parties have had an opportunity to appeal
such action for administrative review to the Board.
Therefore, the Third Circuit’s dismissal of the way
in which state law addresses finality, and conjuring of
its own federal standard, conflicts with the reasoning
and statements of law in Berkshire and those
previously articulated by this Court.
14
ii. The Substantive Functions Of The
Administrative Review Process in
DRN and Berkshire Are The Same
Beyond the plain statement of finality in the
Pennsylvania Code, the substance and function of the
administrative process in Massachusetts parallels the
process in Pennsylvania. Indeed, the Board has
reviewed the procedures in Massachusetts, compared
it with its own procedures, and found that
“Pennsylvania’s procedures are nearly identical in
substance to the Massachusetts procedures that the
First Circuit found not to be final until the adversely
affected party had an opportunity to take advantage of
that state’s hearing process.” App.43 (emphasis added).
In all consequential forms, the Pennsylvania Code
and Massachusetts code function in the same manner.
This comes as no surprise, as the court in Berkshire
predicted that parallel review processes would likely be
found in numerous states noting, “the manner in which
Massachusetts has chosen to structure its internal
agency decision-making strikes us as hardly
unusual . . . .” Berkshire, 851 F.3d at 112. For example,
in both states the state agency action is not “final” until
opportunity for an administrative appeal. Compare 35
P. S. § 7514(c); with Berkshire, 851 F.3d at 112. In both
states agency action is subject to an administrative
appeal with an adjudicatory hearing. Compare 35 P. S.
§ 7514; 25 Pa. Code § 1021.51; with 314 CMR 9.10(1).
Both states have an administrative adjudication that
is de novo review of agency action. Compare
Leatherwood, Inc. v. Com., Dept. of Environmental
Protection, 819 A.2d 604, 611 (Pa. Cmwlth. 2003); with
Berkshire, 851 F.3d at 112. Both states’ adjudicatory
15
hearings can include witness testimony and other
evidence. Compare 25 Pa. Code § 1021.117; with 310
CMR 1.01(5)(a), (b). Both states allow for the
adjudication to include pre-hearing discovery. Compare
25 Pa. Code § 1021.102; with 310 CMR 1.01(12). And,
finally, in both states a party can appeal to the state
judiciary following a decision by an administrative law
judge. Compare 25 Pa. Code § 1021.201; with 310 CMR
1.01(14)(f).
Similar to the administrative process in Berkshire,
the Board does nothing more than provide the
administrative review of the Department’s actions. In
creating the Board, the Pennsylvania legislature
directed that “[t]he board shall continue to exercise the
powers to hold hearings and issue adjudications which
(powers) were vested in agencies listed in section 1901A of the act of April 9, 1929 (P.L.177, No.175), known
as The Administrative Code of 1929.” 35 P.S. § 7514(c).
In the judgment of the Pennsylvania Legislature, the
optimal administrative procedure for the
Commonwealth of Pennsylvania was to create the
Board to perform some of the duties of the Department,
including the administrative review process for
Department decisions. See 35 P.S. § 7514. Indeed, the
Pennsylvania Supreme Court characterized the
Department and the Board as together being part-andparcel of the governing environmental administrative
structure. See Tire Jockey Serv., Inc. v. Dep’t of Envtl.
Prot., 915 A.2d 1165, 1185 (2007) (describing “[t]he
administrative structure that governs environmental
regulation in Pennsylvania” as consisting of three
“inter-related branches” including the Environmental
Quality Board, the Department, and the Board). The
Board is, in essence, operating down the hall from,
16
instead of within the same office as, the Department.
As such, despite the fact that the Board is not within
the Department as it is in Berkshire, it is a superficial
distinction without a difference as the structural and
operational administrative processes in Pennsylvania
and Massachusetts are the same.
Considering the substantively matching provisions
governing administrative appellate review in DRN and
Berkshire, the conclusions of the First and Third
Circuits irreconcilably conflict.
2. The Third Circuit’s Finding Of
Finality In DRN Conflicts With The
Second Circuit’s Holding In Murphy
Similar to Berkshire, other Circuit Courts have
looked to state law to determine the finality of state
agency action in federal court proceedings. All of these
decisions are also now at conflict with the Third
Circuit’s decision in DRN.
For example, in Murphy v. New Milford Zoning
Comm’n, 402 F.3d 342 (2d Cir. 2005), the Second
Circuit relied on the way in which state law defined
finality to guide its decision with regard to a zoning
issue. There, homeowners were served by the local
zoning commission with a cease and desist order
related to large prayer meetings being held at their
home. Id. at 345. The homeowners brought an action in
federal court alleging, among other things, that their
First Amendment rights had been violated. Id. at 345346. The Second Circuit deferred judgement, accepting
the state’s definition of what constituted a “final”
decision and noting the importance of state
administrative procedures. Id. at 351 (looking to the
17
Connecticut General Statutes to determine whether a
cease and desist order was final). In this context, the
Second Circuit found “courts have recognized that
federalism principles also buttress the finality
requirement.” Murphy, 402 F.3d at 348; see also Kurtz
v. Verizon New York, Inc., 758 F.3d 506, 512 (2d Cir.
2014) (allowing the full record to be developed “gives
proper respect to principles of federalism”). Specifically,
the Murphy court held that:
The Zoning Board of Appeals possessed the
authority to review the cease and desist order de
novo to determine whether the zoning
regulations were properly applied. In fact, a
zoning board of appeals “is in the most
advantageous position to interpret its own
regulations and apply them to the situations
before it.” . . . For this reason, the Connecticut
Supreme Court recognized in Port Clinton that
a zoning board of appeals will typically be the
venue from which a final, definitive decision will
emanate. It thus stated: “In many instances a
final decision by the ‘initial decisionmaker,’
really means a decision by the zoning board of
appeals, when that body ... is exercising its
power to grant variances and exceptions.”
Id. at 352-53 (citations omitted). The Murphy court
found that the requirement that the homeowners
obtain a final definitive decision from the local zoning
authority as directed under Connecticut law ensures
that there will be a record of concrete and established
facts should the occasion of federal review arise. Id. at
352. Concluding that, “[u]ntil this variance and appeals
process is exhausted and a final, definitive decision
18
from local zoning authorities is rendered, this dispute
remains a matter of unique local import over which we
lack jurisdiction.” Murphy, 402 F.3d at 354. Further,
such a structure ensures “that federal review – should
the occasion eventually arise – is premised on concrete
and established facts” as proscribed by state law. Id. at
353.
A number of other US Court of Appeals have
followed the Second Circuit’s logic, including the Third
Circuit. See Taylor Inv., Ltd. v. Upper Darby Tp., 983
F.2d 1285, 1292 (3d Cir. 1993) (federal court relying on
the Pennsylvania Code to determine finality of a zoning
decision); Hoehne v. County of San Benito, 870 F.2d
529, 532 (9th Cir. 1989) (decision is not final until the
“government entity charged with implementing the
regulations has reached a final decision”); see also
Spence v. Zimmerman, 873 F.2d 256, 262 (11th Cir.
1989). While these decisions are largely zoning cases,
the underlying rationale regarding deference to state
finality standards when making decisions implicating
state law nevertheless applies with equal force.2
2
The singular case cited by the court in DRN to support its
holding, Williamson Cly. Reg’l Planning Comm’n v. Hamilton Bank
of Johnson City, 473 U.S. 172, 194, (1985) (hereinafter
“Williamson”), is inapposite. Williamson involved a developer’s
lawsuit against a planning commission for an alleged taking of
property. The court held that the takings claim was not ripe
because “the Commission’s denial of approval does not conclusively
determine whether respondent will be denied all reasonable
beneficial use of its property, and therefore is not a final,
reviewable decision.” Id. 473 U.S. at 194. While the court held that
“[t]he question whether administrative remedies must be
exhausted is conceptually distinct . . . from the question whether
an administrative action must be final before it is judicially
19
The finality of particular agency action must be
considered in light of the whole statutory scheme
within which the particular action is undertaken. State
of Tex. v. U.S. Dept. of Energy, 764 F.2d 278 (5th Cir.
1985). As noted by the DRN panel, the “Administrative
Procedure Act authorizes a broad scope of review,” and
specifically does not “limit[] courts to considering only
federal law.” App 25. “The presumption against federal
preemption of state law is one of ‘dual jurisdiction’
which results from reasons of comity and mutual
respect between the two judicial systems that form the
framework of our democracy.” Kiak v. Crown Equip.
Corp., 989 A.2d 385, 390 (Pa. Super. Ct. 2010) (internal
citation omitted). Nothing in case law, statutory law, or
the Third Circuit’s decision provides that a federal
court should disregard Pennsylvania law, with regard
to a state issued authorization, and instead adopt its
own definition of finality.
The proper presumption is that the federal courts
must respect Pennsylvania procedure. Pennsylvania, in
its wisdom, established the Board as an administrative
body with special expertise in reviewing actions of the
Department and tasked with establishing the record
for those Department actions, and, therefore, its
review. See Harman Coal Co. v. Com., Dept. of
Environmental Resources, 384 A.2d 289, 292 (Pa.
Cmwlth. 1978) (finding that “members of the [Board]
and its staff workers have an expertise in the scientific
and technical aspects of environmental protection not
possessed by this Court”) (citations omitted). As such,
reviewable,” the Williamson court did not, in any way, hold that a
state’s definition of finality in its regulatory scheme may be
disregarded by the courts. Id. 473 U.S. at 192.
20
the Board is uniquely qualified, and in the most
advantageous position to interpret and apply
Pennsylvania environmental law to Department
actions. Absent a final determination by the Board, as
required by state law, any later judicial review would
proceed without: (1) development of a full record, (2) a
precise demonstration of how the state specific
regulations should be applied to particular project, and
(3) thus would risk premature interference in complex
environmental matters of local concern more aptly
suited for resolution by a body specifically designed to
address precisely these issues.3
3
Ironically, the Natural Gas Act requires the Federal Energy
Regulatory Commission to complete its administrative process
prior to judicial review of its actions, despite the fact that the
Commission’s issuance of a Certificate of Public Convenience and
Necessity immediately imbues a possessor of the Certificate with
a number of concrete rights, including eminent domain rights.
Papago Tribal Utility Auth. v. FERC, 628 F.2d 235, 238-39 & n.11
(D.C. Cir. 1980) (explaining that a party must complete the
administrative appeals process before it may file a petition for
review, and that the order denying the requests for rehearing is
the final, reviewable agency order); see also Energy Transfer
Partners, LP v. FERC, 567 F.3d 134, 141 (5th Cir. 2009). “There is
good reason to prohibit any litigant from pressing its cause
concurrently against both the judicial and the administrative
fronts: a favorable decision from the agency might yet obviate the
need for review by the court,” or the agency appeals process might
alter the issues ultimately presented for review, “mak[ing] the case
moot and [the court’s] efforts supererogatory.” Clifton Power v.
FERC, 294 F.3d 108, 111-12 (D.C. Cir. 2002)(citations omitted).
See also Alcoa Power Generating Inc. v. FERC, 643 F.3d 963, 967
(D.C. Cir. 2011) (citing Devia v. NRC, 492 F.3d 421, 424 (D.C. Cir.
2007) (claim may be unripe because the court may never need to
decide it)). The same logic applies here.
21
B. The Third Circuit’s DRN Decision Has
Resulted In An Intra-Circuit Split That
Preserved The Administrative Review
Process In New Jersey But Preempted
The Same Process In Pennsylvania
The question of the preemptive scope and reach of
Section 717r(d)(1) has implications far beyond this
case. Each state has different statutory schemes
regarding the way in which the state reviews and
approves water quality certifications – and other
related state permits issued for Commission
jurisdictional projects. The Third Circuit’s DRN opinion
sows uncertainty as to how, and in what forum, an
appeal of a state water quality certification, or any
other state approval required pursuant to a
Commission jurisdictional project, occurs.
This uncertainty has already manifested within the
Third Circuit, as the Third Circuit’s decision
engendered an intra-circuit split regarding how the
administrative appeals process is preserved in New
Jersey, yet, preempted in neighboring Pennsylvania. A
day after the DRN decision, the Third Circuit panel in
Township of Bordentown, New Jersey v. Federal Energy
Regulatory Commission, 903 F.3d 234 (3d Cir. 2018)
(hereinafter “Bordentown”), held that the Natural Gas
Act “leaves untouched the state’s internal
administrative review process, which may continue to
operate as it would in the ordinary course under state
law.” Bordentown, 903 F.3d at 268.
In Bordentown, Transco planned a separate upgrade
of its natural gas pipeline system in New Jersey and
applied to both the Commission for a Certificate of
Public Convenience and Necessity and to the New
22
Jersey Department of Environmental Protection (“New
Jersey”) for a Section 401 water quality certification.
Id. at 244. In 2015, the Commission granted the
Certificate of Public Convenience and Necessity
contingent on Transco’s compliance with all other
required authorizations. Id. at 245. On March 13, 2017,
New Jersey issued the water quality certification,
among other approvals. Id. In accordance with New
Jersey administrative procedures, the petitioners
timely sought an administrative hearing with regard to
New Jersey’s issuance of the permits. Id. at 243. New
Jersey denied the petitioners’ request for an
administrative hearing because it believed that its
administrative procedures were preempted by the
Natural Gas Act. Id.
Yet, the Third Circuit Bordentown panel found that
“the only plausible” conclusion to draw from the text of
the Natural Gas Act is “that § 717r(d)(1) does not
preempt state administrative review of interstate
pipeline permitting decisions.” Id. at 269 (emphasis
added). In finding this, the Bordentown panel closely
analyzed the language of the Natural Gas Act and held
that a state’s administrative proceedings are not “civil
actions” over which the Third Circuit has exclusive
jurisdiction:
…§ 717r(d)(1)—which is titled “Judicial
review”— grants “original and exclusive
jurisdiction over any civil action for the
review of an order or action of a ... or State
administrative agency.” [emphasis in original].
Congress therefore clearly understood the
difference between establishing direct judicial
“review” over agency action (supplanting any
23
alternative intra-agency process) and creating
an exclusive judicial forum in the federal Courts
of Appeals for a “civil action” challenging an
agency’s decision-making (separate from the
agency’s own internal review process). As
opposed to affirmatively installing federal
courts to oversee the administrative
process, as it did in § 717r(b) by placing the
“review” of all FERC action in the Courts of
Appeals, Congress did not interject federal
courts into the internal workings of state
administrative agencies.
Id. at 268 (emphasis added).
The Bordentown panel took pains to discuss how, if
it had accepted Transco’s arguments, the Natural Gas
Act would “cut off any state review other than the
initial decision,” making all initial state administrative
decisions by default final decisions. Id. at 269. Finding
that, if all initial decisions are final decisions, then the
state administrative review of pipeline permitting
decisions provided for in the Natural Gas Act would be
eviscerated.4 Specifically, the Bordentown panel
concluded that,
viewed in light of both federal and New Jersey
authority, and barring any specific statutory
language to the contrary, a hearing before an
administrative body is not a “civil action.”
Accordingly, such hearings are not impacted by
4
For a detailed discussion of state’s rights in this context, see
Channing Jones, “The Natural Gas Act, State Environmental
Policy, and the Jurisdiction of the Federal Circuit Courts,” 42
Colum. J. Envtl. L. 163 (2016).
24
§ 717r(d)(1)’s assignment to the federal Courts of
Appeals the exclusive jurisdiction over civil
actions challenging a state agency’s permitting
decision made pursuant to federal law. Because,
as relevant here, the NGA explicitly permits
states “to participate in environmental
regulation of [interstate natural gas]
facilities” under the CWA, Delaware I, 833
F.3d at 368, and only removes from the
states the right for their courts to hear civil
actions seeking review of interstate
pipeline–related state agency orders made
pursuant thereto, the NGA leaves
untouched the state’s internal
administrative review process, which may
continue to operate as it would in the
ordinary course under state law.
Id. at 268 (citations omitted)(emphasis added). The
Natural Gas Act “only removes from the states the
right for their courts to hear civil actions seeking
review of interstate pipeline–related state agency
orders made pursuant thereto . . .” Id. (emphasis
added). In other words, the primary question is
whether the proceeding is one before an administrative
agency and therefore not a “civil action” over which the
Third Circuit has exclusive jurisdiction. Therefore, it is
without dispute that the proceeding before the Board is
one before an administrative agency.
In contrast, the DRN panel cut off state
administrative review after the initial decision of the
Department. App.10-13. The DRN panel held that the
decision of the Department was the final decision
despite Pennsylvania administrative procedure that
25
provides for a hearing before the Board. App.10-13.
DRN and Bordentown are therefore in conflict, and
future petitioners and state administrative agencies
are left to wonder how to proceed.
Additionally, in DRN, the panel found significant
the fact that that the Department’s decision “was
immediately effective.”App.14. The DRN panel noted
the “First Circuit, by contrast, faced a Massachusetts
regulatory regime in which the agency’s initial decision
was ineffective until either the time to appeal expired
or a final decision on appeal issued.” App.14 (citing 310
MASS. CODE REGS. 9.09(1)(e)). The DRN court
further clarified that:
Put another way, Berkshire Environmental
addressed a provisional order that could become
final in the absence of an appeal, while we are
presented with a final order that could be
overturned in the event of an appeal. In that
regard, PADEP’s order is no less final for the
availability of EHB review than a federal
agency’s is for the availability of review in this
Court.
App. 15.
However, like the Board, the administrative appeals
process in the state of New Jersey is also “immediately
effective.” See, e.g., Freshwater Wetlands Protection
Act Rules, N.J.A.C. 7:7A-21.3(b), (“the operation of the
permit or authorization is not automatically stayed” by
a request for an adjudicatory hearing); Coastal Zone
Management Rules, N.J.A.C. 7:7-28.3(b) (“the
operation of the permit or authorization is not
automatically stayed” by a request for an adjudicatory
26
hearing); and the New Jersey Pollutant Discharge
Elimination System, N.J.A.C. 7:14A-17.6 (“The
Department’s grant of a request for an adjudicatory
hearing shall not automatically stay any contested
permit condition(s)”). As such, the primary reason the
DRN panel distinguished the Berkshire decision is
undercut by Bordentown.
If this Court were to allow the decisions in DRN and
Bordentown to remain, there would be conflicting and
inequitable standards intact in the Third Circuit.
Under the DRN rationale, the Department action was
final, Pennsylvania state administrative procedures
were preempted, and the Third Circuit had exclusive
jurisdiction over petitioners’ objections to the
Department’s action. Under the Bordentown rationale,
the Department action is final but Pennsylvania
administrative procedures are not subject to
preemption by the Third Circuit and may continue to
operate as they would in the ordinary course under
state law. These holdings are not reconcilable.
The fact is that the DRN panel’s decision has
already wrought uncertainty to state agencies under
the Third Circuit’s own jurisdiction – as evinced by
New Jersey’s initial denial of the administrative review
hearing based on jurisdiction. This foretells even
greater confusion outside of the Third Circuit as
various courts must attempt to juggle the positions and
interpretations of finality and the uncertain
preemptive force of Section 717r(d)(1).
27
C. The Third Circuit’s Decision In DRN
Condemns The Third Circuit To
Reviewing Incomplete And Inadequate
Records In Section 717r(d)(1) Appeals
And Strips Aggrieved Parties Of Their
Due Process Rights
The Third Circuit’s usurpation of Pennsylvania’s
clearly defined and well-established administrative
review process has significant consequences for both
the quality of the Third Circuit’s review of future
appeals, and the due process rights of aggrieved
parties; as the rationale in the DRN decision dictates
that any future rulings with regard to 717r(d)(1)
challenges of state issued permits will rely on
piecemeal administrative records.
In Pennsylvania, appeals to the Environmental
Hearing Board are the means by which the record of a
Department action is developed and “[a] party’s due
process rights are protected . . . .” Fiore v. Department
of Environmental Protection, 655 A.2d 1081 (Pa.
Cmwlth. 1995) modified, 351 A.2d 606 (Pa. 1976))
(citing Commonwealth v. Derry Township, 314 A.2d 868
(Pa. Cmwlth. 1973), modified, 351 A.2d 606 (Pa. 1976));
see also Domiano v. Commonwealth, Department of
Environmental Resources, 713 A.2d 713, 717 (Pa.
Cmwlth. 1998) (The Board exercises its primary
jurisdiction so that, inter alia, “a record can be fully
developed . . . .”). Specifically, the Pennsylvania
Department of Environmental Protection does not have
internal hearing examiners and, therefore, does not
prepare formal written findings, a formal
administrative record, or issue adjudications as part of
its permit application review process. Rather, the
28
Department – by express statutory design – is
specifically exempt from these record-keeping and
record-developing requirements. See 35 P.S. § 7514(a)(c), 2 PA. CONS. STAT. Ch. 5, Subchapter A, and the
regulations thereunder at 1 Pa.Code Chapters 31–35,
1021. As such, the supposed record produced by the
Department, and later relied upon by the Third Circuit
in reviewing the agency’s action cannot resemble a
traditional administrative record.
Pennsylvania’s laws and regulations mandate that
the record be compiled during the state administrative
review process, so it is the Board that is charged with
creation of the administrative record. Indeed, the
Board’s administrative review is a de novo review and
requires pre-hearing discovery, an evidentiary hearing,
and post-hearing submissions. 25 Pa. Code
§§ 1021.101-1021.134; see also Leatherwood, Inc. v.
Com., Dept. of Environmental Protection, 819 A.2d 604,
611 (Pa. Cmwlth. 2003). This process is key because it
is by virtue of an appeal to the Board that the
Department and aggrieved parties develop the record
that the Third Circuit can later review under the
arbitrary and capricious standard. See, e.g., Morcoal
Company v. Dep’t of Envit. Resources, 459 A.2d 1303
(Pa. Cmwlth. 1983) (an appeal to the Board protects
important constitutional due process right of
appellants). It is axiomatic that bad facts make bad
law, and, without a full record to review, the Third
Circuit relegates itself to deciding complex state law
environmental issues on incomplete records. This is
contrary to the holdings it other circuits as, it is
precisely this concern of creating a complete factual
record which undergirds the decisions in Murphy and
its progeny, allowing aggrieved parties to complete the
29
state administrative process prior to judicial review.
See Murphy, 402 F.3d at 352-53.
Furthermore, the DRN decision strips the due
process rights of Pennsylvania citizens aggrieved by
the issuance of the substantive permits issued
pursuant to the water quality certifications by limiting
the record of review and opportunity for participation
in the process. For example, three underlying
substantive state permits comprise Pennsylvania’s
water quality certificate. App.48-49. One of these
permits is a National Pollutant Discharge Elimination
System (“NPDES”) permit for the discharge of water
pursuant to Pennsylvania’s Clean Streams Law (35
P.S. §§ 691.1 – 691.1001). App.49. Like appeals of the
water quality certification itself, an appeal of the
underlying NPDES permit is also taken pursuant to
Section 717r(d)(1). However, unlike water quality
certification, the Department does not provide any
opportunity for comment or notice prior to the
Department approving a NPDES permit. See
Transcript of Oral Argument page number 44, lines 2023, Delaware Riverkeeper Network, et al. v.
Pennsylvania Department of Environmental Protection,
et al., Third Circuit Court of Appeals, Docket No. 162211, Oral Argument (November 7, 2017) (Department
admitting that, “[t]here is no comment period. There is
no notice in the Pennsylvania Bulletin of receipt for a
request and notice of intent to use an [NPDES] general
permit”).
The Department does not publish notice of an
NPDES general permit application in the Pennsylvania
Bulletin, does not provide public notice in public
newspapers, does not provide public notice anywhere
30
else, and does not accept comments on the NPDES
general permit. Indeed, the Department simply does
not have a process for a party to comment on this type
of NPDES permit. This may not be a problem if an
aggrieved party has the right to challenge the NPDES
permit and develop a record de novo before the Board;
however, the Third Circuit’s decision eliminates this
opportunity. Thus, an aggrieved party is left without
notice and an opportunity to comment on an NPDES
permit application, and without an opportunity to
create a meaningful record before the Board. The DRN
panel itself noted that “[t]he essence of due process is
notice and an opportunity to be heard,” and that
“opportunity to comment and to petition this Court for
review is enough” to satisfy due process concerns.
App.17. Yet, the court’s ruling in DRN strips aggrieved
parties of the very same opportunity for notice and
comment that it recognized as providing due process.
Moreover, under the Third Circuit’s scheme
articulated in DRN, a challenge to a NPDES permit in
a federal circuit court pursuant to Section 717r(d)(1) –
without administrative review by the Board – would
be a futile effort as the record for such an appeal would
be strictly limited to the record that was before the
agency at the time that it rendered its decision. See
Camp v. Pitts, 411 U.S. 138, 142 (1973) (holding that
“the focal point for judicial review should be the
administrative record already in existence, not some
new record made initially in the reviewing court”).
Because aggrieved parties have no ability to create a
meaningful record, they cannot cite or rely on any
evidence challenging or questioning the Department’s
decision in any subsequent judicial proceeding before
the Third Circuit.
31
Finally, it is not surprising that the Department
lacks notice and comment procedures for the NPDES
permits because the Department’s review and approval
process was never contemplated to be reviewed in a
case where original jurisdiction is the US Court of
Appeals for the Third Circuit. Rather, the permits
issued by the Department have always been heard de
novo by the Board. Indeed, as described above, Board
review is an integral part of Pennsylvania
environmental permitting and cannot be truncated
without affecting the finality of a permit and causing
serious due process problems. See 35 P.S. § 7514(d);
Consol Pa. Coal Co. v. Dept. of Env’tl Prot., 2011 WL
4943794, at *3 (Pa. Env. Hrg. Bd., Aug. 26, 2011).
As a result of the Third Circuit’s decision, a
landowner with a stream running through her back
yard has no opportunity to engage with the
Department regarding the issuance of a NPDES permit
prior to the Department’s authorization of a potential
withdrawal from or discharge to that landowner’s
stream. Aggrieved parties have no notice of when a
project applicant submits an application, what was in
the application, when the Department considered the
application complete, and therefore whether the
application met the substantive criteria for coverage
under the NPDES general permit and governing
technical standards. Based on the DRN decision, such
an aggrieved party would have no opportunity to build
or otherwise challenge the record prior to judicial
review by a federal appellate court. This is not how
Section 717r(d)(1) was designed to operate, as such a
draconian interpretation not only reduces the quality
of the record the Third Circuit must rely on when
deciding whether the Department’s action was in
32
conformance with law, but also fatally undercuts an
aggrieved party’s ability to challenge the permit.5
II.
THE
THIRD
CIRCUIT
COURT’S
PREEMPTION OF BOARD REVIEW
VIOLATES THE 10TH AMENDMENT
The Tenth Amendment to the United States
Constitution provides: “The powers not delegated to the
United States by the Constitution, nor prohibited by it
to the states, are reserved to the states respectively, or
to the people.” As set forth supra, the Natural Gas Act
and the Clean Water Act do not preempt state
regulatory authority. To the contrary, they expressly
recognize a role for the states in the regulatory process.
The Clean Water Act provides that any person
applying for a federal license or permit for any project
“which may result in any discharge into the navigable
waters,” must receive a certification from the state in
which the project is located certifying that the expected
discharge into navigable waters will comply with
applicable provisions of the Clean Water Act and state
water quality standards. See Alabama Rivers Alliance
5
To the extent there is concern that a Board proceeding would
cause undue delay to a Commission jurisdictional Project, the
Natural Gas Act accounts for this concern. The Natural Gas Act
specifically provides project applicants with the ability to seek
relief from agency delay in the U.S. Court of Appeals for the
District of Columbia, which has the ability to “set a reasonable
schedule and deadline for the agency to act on remand.” 15 U.S.C.
§ 717r(d)(2)-(3). See also Weaver’s Cove Energy, LLC v. State of
Rhode Island Dept. of Env’tl Management, 524 F.3d 1330 (D.C. Cir.
2008) (considering appeal by company under Section 717r(d)(2) of
the Natural Gas Act to an action on appeal to state administrative
agency).
33
v. F.E.R.C., 325 F.3d 290, 297 (D.C. Cir. 2003) (citing
33 U.S.C. § 1341(a)(1)). Since the federal government
has not preempted the state’s role in approvals for
natural gas pipelines but, to the contrary, has
specifically given the states a role in this process, on
what authority does the federal government then
disregard the very administrative procedure that the
state has developed to comply with the federal
requirements?
As the Honorable Richard P. Mather of the Board
has stated:
Congress may not simply commandeer state
officials and agencies, rewrite state laws, and
direct that state agency officials defend state
agency decisions in federal court in violation of
state laws enacted by the Pennsylvania General
Assembly.
App.34. The federal government does not have the
power to issue a direct order to the government of a
state thereby “conscript[ting] state governments as its
agents” and may not dictate “what a state legislature
may and may not do.” Murphy v. Nat’l Collegiate
Athletic Ass’n, 138 S. Ct. 1461, 1476, 1477, 1478 (2018).
This is exactly what the Third Circuit has done in DRN
by commandeering Pennsylvania’s legislative and
administrative processes.
In usurping Pennsylvania law, the Third Circuit is,
in effect, forcing the Commonwealth to legislate its
administrative scheme to conform to the structure
preferred by the Third Circuit. If the Commonwealth
wants its preferred scheme for review of Department
actions and its definition of finality to be respected, the
34
Commonwealth will be required to dissolve the Board
and move its functions back within the Department.
This is unconstitutional. Further, such a change would
be nothing but a shuffling of furniture down the hall.
Functionally, there would be absolutely no change in
Pennsylvania’s administrative process; the only change
would be the roof under which that process occurs.
“While Congress has substantial powers to govern
the Nation directly, including in areas of intimate
concern to the States, the Constitution has never been
understood to confer upon Congress the ability to
require the States to govern according to Congress’
instructions.” New York v. United States, 505 U.S. 144,
162 (1992).
III.
THE QUESTIONS PRESENTED
EXCEPTIONALLY IMPORTANT
HAVE WIDE-RANGING IMPACT
ARE
AND
If left intact, federal courts bound by the First and
Third Circuits will be forced to apply conflicting and
amorphous standards to determine whether individual
state’s administrative review processes are preserved
or preempted by Section 717r(d)(1). The unclear timing
for invoking Section 717r(d)(1) creates enormous
uncertainty for the regulated community, aggrieved
parties, and state agencies implementing their water
quality certification programs. Therefore, it is critical
that this Court create a unified standard that not only
protects the due process rights of aggrieved parties, but
also respects the well-developed and long-relied upon
regulatory schemes of the states who are responsible
for issuing the water quality certifications.
35
This Court should grant certiorari to resolve the
conflicts to which the decision below contributes, and
return the Natural Gas Act to its intended scope.
CONCLUSION
For the foregoing reasons, this Court should grant
the petition for certiorari.
Respectfully submitted,
AARON STEMPLEWICZ
Counsel of Record
DELAWARE RIVERKEEPER
NETWORK
925 Canal Street
Suite 3701
Bristol, PA 19007
(215) 369-1188
Aaron@delawareriver
keeper.org
Counsel for Petitioners
Delaware Riverkeeper
Network and
The Delaware Riverkeeper
January 9, 2019
MARK L. FREED
CURTIN & HEEFNER
2005 South Easton Road
Suite 100
Doylestown, PA 18901
(267) 898-0570
Counsel for Petitioner
Lancaster Against
Pipelines
This is a copy of a public record, reproduced as it was published. It is not legal advice, and it may not be the version a court would rely on. Check the official source before you cite it.