Respondents Brief — Allco Finance Limited, Petitioner v. Robert J. Klee, Commissioner, Connecticut Department of Energy and Environmental Protection, et al.
Supreme Court briefDec 18, 2017
Ask Donna
What actually matters in this document.
Text
No. 17-737
================================================================
In The
Supreme Court of the United States
-----------------------------------------------------------------ALLCO FINANCE LIMITED,
Petitioner,
v.
ROBERT KLEE, in his Official Capacity as
Commissioner of the Connecticut Department of Energy
and Environmental Protection, KATHERINE S. DYKES,
JOHN W. BETKOSKI, III and MICHAEL CARON,
in their Official Capacities as Commissioners of the
Connecticut Public Utilities Regulatory Authority,
Respondents.
-----------------------------------------------------------------On Petition For A Writ Of Certiorari
To The United States Court Of Appeals
For The Second Circuit
-----------------------------------------------------------------BRIEF IN OPPOSITION TO
PETITION FOR WRIT OF CERTIORARI
-----------------------------------------------------------------GEORGE JEPSEN
Attorney General
of Connecticut
ROBERT D. SNOOK
Counsel of Record
Assistant Attorney General
OFFICE OF THE
ATTORNEY GENERAL
55 Elm Street, P.O. Box 120
Hartford, CT 06141-0120
Robert.Snook@ct.gov
(860) 808-5250
Counsel for Respondents
Dated: December, 2017
================================================================
COCKLE LEGAL BRIEFS (800) 225-6964
WWW.COCKLELEGALBRIEFS.COM
i
QUESTION PRESENTED
In order to meet important state environmental
and other public policy goals, the Connecticut
Commissioner of the Department of Energy and
Environmental
Protection
(“DEEP”
or
the
“Department”) issued a series of requests for proposals
(“RFPs”) seeking to procure new sources of renewable
energy. Allco, a developer of renewable energy, sued
claiming that the Federal Power Act, 16 U.S.C. § 824
et seq., granted exclusive jurisdiction over wholesale
energy rates to the Federal Energy Regulatory
Commission (“FERC”) and therefore that these state
procurement efforts intruded on this exclusive
authority and were preempted.
The Second Circuit, relying in large part on this
Court’s recent decision in Hughes v. Talen Energy
Marketing, LLC, 136 S. Ct. 1288 (2016), held that the
District Court properly dismissed the case because the
state renewable energy procurement programs did not
regulate wholesale energy sales and thus were outside
the scope of FERC’s jurisdiction under the Federal
Power Act.
The question presented is:
Did the Second Circuit correctly hold that
Connecticut’s competitive procurements do
not violate the Federal Power Act?
ii
TABLE OF CONTENTS
Page
QUESTION PRESENTED...................................
i
TABLE OF AUTHORITIES .................................
iii
INTRODUCTION ................................................
1
STATEMENT OF THE CASE..............................
3
A.
CONNECTICUT’S REGULATORY
SCHEME ...................................................
3
Renewable Energy Procurements .......
5
THE PROCEEDINGS BELOW .................
6
REASONS FOR DENYING THE PETITION ......
8
B.
I.
Connecticut’s RFPs Are A Straightforward
Application of Hughes and Are Not
Preempted ..................................................
9
A. The Commissioner’s Actions Are Within
His Authority ....................................... 11
B. Bilateral Contracts Do Not Violate
Hughes ................................................. 12
II.
Judicial Colloquy Is Not the Decision of
the Court .................................................... 15
CONCLUSION..................................................... 16
iii
TABLE OF AUTHORITIES
Page
CASES
Allco Renewable Energy Ltd., 154 FERC
¶ 61,007 (2016) ..........................................................7
Allco v. Klee, 805 F.3d 89 (2d Cir. 2015) ................. 6, 11
Allco v. Klee, No. 3:13-CV-1874-JBA, 2014 WL
7004024 (D. Conn. Dec. 10, 2014) .............................6
Entergy Nuclear Vermont Yankee, LLC v.
Shumlin, 733 F.3d 393 (2d Cir. 2013) ............... 11, 12
Hughes v. Talen Energy Marketing, LLC, 136
S. Ct. 1288 (2016) ............................................ passim
Morgan Stanley Capital Group Inc. v. Public
Util. Dist. No. 1 of Snohomish Cty., 554 U.S.
527 (2008) ................................................................13
Nantahala Power & Light Co. v. Thornburg, 476
U.S. 953 (1986) ........................................................11
New York v. FERC, 535 U.S. 1 (2002) .........................11
S. Cal. Edison Co. San Diego Gas & Elec. Co., 71
FERC P 61269 (June 2, 1995) .................................12
STATUTES
16 U.S.C. § 824 ..............................................................1
16 U.S.C. § 824a-3(h) ....................................................6
Conn. Gen. Stat. § 16-245a ...........................................3
Conn. Gen. Stat. § 16a-3a .............................................3
Conn. Gen. Stat. § 16a-3f .......................................... 4, 5
iv
TABLE OF AUTHORITIES—Continued
Page
Conn. Gen. Stat. § 16a-3j .......................................... 4, 5
Conn. Gen. Stat. § 22a-200a .........................................3
Conn. Gen. Stat. § 22a-200c .........................................3
REGULATIONS
P.A. 13-303 ................................................................ 4, 5
P.A. 15-107 ................................................................ 4, 5
RULES
Sup. Ct. R. 10 ............................................................ 8, 9
1
INTRODUCTION
As this Court has noted in its recent decision in
Hughes v. Talen Energy Marketing, LLC, 136 S.Ct.
1288 (2016) (“Hughes”), the Federal Power Act, 16
U.S.C. § 824 et seq. (“FPA”) is a careful and deliberate
exercise in federalism, dividing regulatory authority
over the generation and transmission of electric energy
between the Federal Energy Regulatory Commission
(“FERC”), for the federal government, and the states.
The FPA grants FERC full jurisdiction over interstate
wholesale rates and interstate transmission, but
reserves solely to the states regulatory authority over
retail rates and the sources of generation.
Connecticut has embarked on a broad and
transformative program of reducing carbon and
other air pollutant emissions while correspondingly
increasing its reliance on renewable energy. Consistent
with that goal, the Commissioner of the Connecticut
Department of Energy and Environmental Protection
(“Commissioner” or “Defendant”) has been granted
the authority by state law to procure new renewable
energy resources. Once the Commissioner has
reviewed bids for new projects, and determined which
projects best meet Connecticut’s program goals, the
Commissioner then directs the state’s regulated
utilities to enter into negotiations for binding
traditional bilateral contracts. Through these energy
procurements, the Commissioner directs the mix of
energy resources for the utilities under his authority
as permitted by the FPA. Nowhere in state law is the
Commissioner given any authority to set interstate
2
rates or otherwise intrude on FERC’s authority. All
rates established in the contracts are set by the
bidding developers.
Petitioner Allco Finance Limited (“Allco”), a
developer of solar energy, bid into one of the
Commissioner’s requests for proposal (“RFP”), but not
another. Allco sued in both cases claiming that the
state’s action in directing utilities to contract for
renewable energy is itself an intrusion into FERC’s
exclusive jurisdiction and thus preempted.1
This Court should reject Petitioner’s request. The
Connecticut RFPs are purely an exercise of the state’s
expressly reserved authority under the FPA over the
resource mix of its domestic utilities. The method
used by the state to procure new resources was the
traditional bilateral contract that this Court has
expressly approved in its recent FPA decision in
Hughes. The state did not, and cannot, set interstate
rates or otherwise intrude upon FERC’s exclusive
jurisdiction and there is nothing presented in this case
that should cause the Court to revisit Hughes.
For all of these reasons, as set forth more fully
below, the Court should deny the petition.
------------------------------------------------------------------
1
Allco also raised a dormant Commerce Clause claim
against the state’s renewable portfolio standard but has not
included that claim in its petition for writ of certiorari.
3
STATEMENT OF THE CASE
A. CONNECTICUT’S REGULATORY SCHEME
The Connecticut General Assembly has decided
that it is the policy of the state to encourage new
renewable energy generation in order to meet the
needs of environmental regulatory programs.2 These
programs in Connecticut include the Global Warming
Solutions Act3 and the Regional Greenhouse Gas
Initiative4 designed to address climate change and
the Integrated Resources Plan5 and Renewable
Portfolio Standard6 designed to meet other important
environmental and energy-related goals. In addition,
the state already has a federal mandatory obligation
to reduce Connecticut’s air quality problems.
Currently, the entire state of Connecticut is in
violation of the ozone limits established under the
federal Clean Air Act.7 In totality, these various
statutes and programs grant the Commissioner
authority to take actions to increase the state’s
reliance on renewable energy and offset carbon
emissions.
2
See Conn. Gen. Stat. § 22a-200c et seq. (setting forth
requirements to reduce greenhouse gas emissions).
3
Conn. Gen. Stat. § 22a-200a.
4
Conn. Gen. Stat. § 22a-200c.
5
Conn. Gen. Stat. § 16a-3a.
6
Conn. Gen. Stat. § 16-245a.
7
U.S. Environmental Protection Agency, 8-Hour Ozone
(2008) Designated Area/State Information, available at https://
www3.epa.gov/airquality/greenbook/hbtc.html.
4
In order to implement the state policy goals of
carbon reductions, air quality and renewable energy,
the Connecticut legislature passed two public acts. The
first was Public Act (P.A.) 13-303, “An Act Concerning
Connecticut’s Clean Energy Goals.” Public Act 13-303
authorized the Commissioner to solicit proposals from
providers of renewable energy sources and “[i]f the
commissioner finds such proposals to be in the interest
of ratepayers including, but not limited to, the
delivered price of such sources, and consistent with the
requirements to reduce greenhouse gas emissions . . .
and in accordance with the policy goals outlined in
the [2013 Comprehensive Energy Strategy] . . . the
commissioner may select proposals . . . to meet up
to four percent” of the state’s electric load. Public
Act No. 13-303, § 6 (2013) (codified at Conn. Gen.
Stat. § 16a-3f ). Pet. App. 70a-71a. The Act further
specifies that the “commissioner may direct the electric
distribution companies to enter into power purchase
agreements. . . .” Id. See Pet. App. 10a-11a.
Two years later in P.A. 15-107, using very similar
language, the Connecticut General Assembly directed
the Commissioner to solicit additional contracts for
large-scale renewable energy projects as well as
large-scale hydropower and natural gas capacity.
P.A. 15-107, § 1 (2015) (codified at Conn. Gen. Stat.
§ 16a-3j). Pet. App. 14a fn5. Under both public acts,
the Commissioner must determine if the projects
submitted in response to the solicitation are consistent
with state environmental and renewable energy goals
and if they are in the ratepayers’ interest. If so, the
5
Commissioner is authorized to direct utilities to enter
into such contracts. Conn. Gen. Stat. §§ 16a-3f, 16a-3j.
Connecticut law does not permit the Commissioner to
set wholesale electric energy rates.
Renewable Energy Procurements
The Commissioner issued several RFPs based
on the authority of P.A. 13-303 and P.A. 15-107. The
first was on July 8, 2013, when the Connecticut
Department of Energy and Environmental Protection
(“DEEP”) released a Notice of Request for Proposals
issued pursuant to P.A. 13-303 (“2013 Procurement”).
Pet. App. 11a. On July 22, 2013, Allco submitted
five solar power bid proposals alongside forty-two
other project submissions. After an extensive review
and consideration of the forty-seven bids, the
Commissioner directed the electric distribution
companies to negotiate possible purchase power
agreements (“PPAs”) with two selected projects, the
Fusion Solar Center, a 20 megawatt solar project,
and the Number Nine Wind Farm, a 250 megawatt
wind power project. Pet. App. 11a, 71a. None of
Plaintiff ’s projects were selected. Pet. App. 11a. The
Connecticut Public Utilities Regulatory Authority
(“PURA”), after a full hearing and review required
by statute, approved the two PPAs.8
8
Application for Approval of Class I Renewable Power
Purchase Agreements Resulting from Department of Energy
and Environmental Protection’s July 8, 2013 Requests for
Proposals pursuant to Section 6 of P.A. 13-303, Final Decision,
6
Subsequently, a three state renewable energy
procurement draft RFP was issued on February 26,
2015, and issued in final form on November 12, 2015
(“2015 RFP”) by the Commonwealth of Massachusetts,
and the States of Connecticut and Rhode Island. Pet.
App. 14a.
B. THE PROCEEDINGS BELOW
Allco brought several actions in district court.
The initial case, Allco Fin. Ltd. v. Klee, et al., No.
3:13-CV-1874 JBA, was brought by Allco against
the Defendant DEEP Commissioner regarding the
2013 energy procurement effort. Pet. App. 11a-12a.
The District Court (Arterton, J.) dismissed Allco’s
complaint, finding both a lack of standing and further
that the Commissioner did not set wholesale rates
and thus the procurement could not be barred as
preempted by the FPA. Allco I, No. 3:13-CV-1874 JBA,
2014 WL 7004024 (D. Conn. Dec. 10, 2014), A166-67.
Pet. App. 72a. The Second Circuit, Allco v. Klee, 805
F.3d 89, 93 (2d Cir. 2015) (Allco II), concluded that Allco
failed to exhaust its administrative remedies with the
FERC. Pet. App. 13a. Allco responded to the Court’s
ruling by filing an administrative implementation
challenge under the Public Utilities Regulatory
Policies Act of 1978, 16 U.S.C. §824a-3(h) (“PURPA”),
with the FERC. Allco Renewable Energy Ltd., FERC
Docket No. EL16-11-000 (filed Nov. 9, 2015). FERC
PURA Docket No. 13-09-19 (October 23, 2013), available at http://
www.ct.gov/pura/docketsearch.
7
responded in its January 8, 2016, Notice of Intent Not
to Act, declining to take action under PURPA. Allco
Renewable Energy Ltd., 154 FERC ¶ 61,007 (2016).
Pet. App. 128a-129a.
Subsequently, Allco brought another case, Allco
Fin. Ltd. v. Klee et al., No. 3:15-CV-608 CSH (Allco III),
filed on April 26, 2015, which is based largely upon
the legal theory advanced in Allco I against both
Defendants Klee and the PURA Commissioners. Pet.
App. 14a-15a. Allco then brought a very similar action
on March 30, 2016, against the same defendants and
including the same basic legal theory in Allco Fin. Ltd.
v. Klee, et al., No. 3:16-CV-508 CSH (Allco IV). Pet. App.
16a. Allco IV restates the essential allegations of Allco
I and Allco III, namely, that the 2013 RFP was in
violation of the Federal Power Act’s prohibition on
state regulation of wholesale electricity sales—subject
only to the limited exception for sales by statutorily
defined clean energy qualifying facilities (“QFs”),
such as Allco’s, under PURPA and that the 2015
Procurement should also be preempted. Specifically,
Allco shifted its theory somewhat from asserting
that the Commissioner could not set rates to the
broader theory that the Commissioner cannot direct or
“compel” utilities to enter into wholesale electric
contracts. Pet. App. 15a-17a. Allco asserts that any
such contract, directed by the Commissioner, is
prohibited by this Court’s decision in Hughes. Pet.
Cert. at 21. Allco IV also added a new count claiming
that the state’s Renewable Portfolio Standard violates
the dormant Commerce Clause because it does not
8
permit Allco to sell renewable energy certificates
generated in Georgia to Connecticut utilities. Pet. App.
40a. This count appears to have been abandoned.
Allco III and Allco IV were dismissed by the trial
court and appealed to the Second Circuit. Pet. App.
60a, 13a-14a. On appeal, Allco continued to press its
preemption claim, arguing that the Commissioner
violates the Federal Power Act if he “compels” utilities
to enter into contracts with generators and that the
state’s Renewable Portfolio Standard violates the
dormant Commerce Clause. The Second Circuit held
that Allco had failed to state a claim for preemption
because the Commissioner had directed the utilities
to enter into traditional bilateral contracts as was
precisely permitted by Hughes and, therefore this
case was outside of FERC’s exclusive jurisdiction. Pet.
App. 28a-40a. In addition, the court held that the
Commissioner’s actions were well within the state’s
authority under the FPA to regulate state utilities.
Pet. App. 34a.
------------------------------------------------------------------
REASONS FOR DENYING THE PETITION
Rule 10 of the Rules of the Supreme Court
describes the considerations governing the review of a
petition for writ of certiorari. Rule 10 notes that a
petition for writ of certiorari will be granted only for a
compelling reason and that the Court may consider
whether there is a conflict in the United States Courts
of Appeals, whether a state court of last resort has
9
decided a federal question in a way that conflicts with
another state or federal court, or if the petition raises
an important question of federal law that needs to be
settled by this Court. See Sup. Ct. R. 10.
There is no split in the Courts of Appeals in this
case. Furthermore, the case below was decided by a
federal court and therefore no state court of last resort
has issued a decision contrary to federal law. Finally,
the case below is a straightforward application of a
recent decision of this Court and therefore there is no
important issue of federal law that this Court has not
already decided.
Specifically, the Second Circuit correctly held
that Allco has failed to state a preemption claim
because the Commissioner acted wholly within the
authority the FPA preserved to the states with respect
to environmental and utility integrated resource
planning and has not intruded upon FERC’s exclusive
authority over wholesale electric rates.
I.
Connecticut’s RFPs Are A Straightforward
Application Of Hughes and Are Not
Preempted
Allco argues that Connecticut authorities
“compelled” utilities to enter into contracts for the
wholesale sale of electricity that are solely within the
jurisdiction of FERC. Allco asserts that “Connecticut’s
decision to force a utility to enter a wholesale power
contract constitutes regulation in the field of wholesale
10
energy sales, which is categorically field preempted.”
Pet. Cert. at 9.
Allco adds that the state’s actions in this case are
virtually identical to those struck down by this Court’s
decision in Hughes, which held that contracts tethered
to FERC markets are preempted by the FPA. Pet. Cert.
at 21. Finally, Allco repeatedly quotes a colloquy
between counsel and Justices Kagan and Alito during
oral argument for Hughes to the effect that if a
contract for the wholesale sale of electricity is subject
to FERC’s jurisdiction and any state action affecting
that contract is preempted. Pet. Cert. at 3, 20. Allco
concludes claiming that the Second Circuit decision,
if permitted to stand, would “create[ ] a massive
loophole” in FERC’s exclusive jurisdiction under the
FPA. Pet. Cert. at 13.
These claims lack merit because, as the Second
Circuit found, the state did not “compel” or obligate its
utilities to enter into contracts and it was possible that
utilities and bidders would not come to terms. Pet. App.
28a-30a. Connecticut did not set wholesale rates in
violation of the FPA or otherwise “tether” the planned
contracts to any FERC market and the bilateral
contracts entered into were of the type expressly
permitted under Hughes. Pet. App. 40a. Consequently,
there is no massive loophole in the FPA because the
state has carefully conducted its procurements in a
manner consistent with this Court’s rulings. Finally,
comments of one or more judges in the context of oral
argument are not the holding of the court and are not
law and Allco’s reliance upon them cannot advance its
argument.
11
A. The Commissioner’s Actions Are Within
His Authority
Federal law gives FERC authority over wholesale
electric rates but preserves the authority of states to
require regulated utilities to enter into bilateral
contracts with generators for clean renewable energy
and to direct the utilities mix of clean and other
resources. Pet. App. 5a; see Allco v. Klee, 805 F.3d 89,
91 (2d Cir. 2015) (Allco II); Entergy Nuclear Vermont
Yankee, LLC v. Shumlin, 733 F.3d 393, 432 (2d Cir.
2013) (quoting Nantahala Power & Light Co. v.
Thornburg, 476 U.S. 953, 966 (1986)). As the Second
Circuit noted, the 2013 and 2015 RFPs resulted
in straightforward, wholly unexceptional bilateral
contracts for clean energy between the utilities and
generators. Pet. App. 34a. The only action of the
Commissioner was to review the proposed contracts to
see if they met state policy goals, all of which was
clearly within the state’s authority to direct the
resource mix of regulated utilities. Pet. App. 10a.
This Court has explained that under the FPA,
states retain “authority over . . . administration of
integrated resource planning and . . . authority over
utility generation and resource portfolios. . . .” New
York v. FERC, 535 U.S. 1, 24 (2002) (emphasis added),
citing Order No. 888, at 31,782, n.544. Further, the
FPA clearly permits states to “direct the planning and
resource decisions of utilities under their jurisdiction.”
Entergy Nuclear Vermont Yankee, LLC v. Shumlin, 733
F.3d 393, 417 (2d Cir. 2013).
12
It is therefore beyond dispute that states may “order
utilities to build renewable generators themselves,
or . . . direct retail utilities to ‘purchase electricity
from an environmentally friendly power producer in
California or a cogeneration facility in Oklahoma, if
[they] so choose[ ].’ ” Entergy Nuclear Vermont Yankee,
LLC v. Shumlin, 733 F.3d 393, 417 (2d Cir. 2013), citing
S. Cal. Edison Co. San Diego Gas & Elec. Co., 71 FERC
P 61269 at *8 (June 2, 1995).
Thus, it is clear that state authorities retain full
jurisdiction over the resource portfolio planning of
regulated utilities and can direct utilities to purchase
clean (or other) energy as required.
B. Bilateral Contracts Do Not Violate
Hughes
Allco clams that “State-coerced bilateral
contracting” is inconsistent with Hughes. Pet. Cert.
at 2. The use of bilateral contracts is fully consistent
with Hughes.
As an initial matter, the claim that the state
“coerced” anyone is flatly untrue. As the court below
found, utilities were fully able to decline to sign
contracts if negotiations were unsuccessful. Pet. App.
29a-30a.
Beyond that, the record shows that the 2013 and
2015 RFPs resulted in standard bilateral contracts.
Both RFPs resulted in the Commissioner directing
state utilities to negotiate contracts with prospective
13
generators. Pet. App. 30a. These contracts, by and
between the utilities and generators, were clearly
traditional bilateral contracts for the purchase and
sale of electricity, as the court below found. Pet. App.
34a.
This Court’s decision in Hughes notes that the
FPA vests exclusive jurisdiction over wholesale
energy sales in the FERC. FERC, in turn, exercises
its jurisdiction in two ways:
Interstate
wholesale
transactions
in
deregulated markets typically occur through
two mechanisms. The first is bilateral
contracting: [load serving entities] sign
agreements with generators to purchase a
certain amount of electricity at a certain
rate over a certain period of time. After the
parties have agreed to contract terms, FERC
may review the rate for reasonableness. See
Morgan Stanley Capital Group Inc. v. Public
Util. Dist. No. 1 of Snohomish Cty., 554 U.S.
527, 546-548 (2008). . . . Second, [regional grid
operators] administer a number of competitive
wholesale auctions. . . .
Hughes, 136 S. Ct. at 1292-93 (emphasis added). Thus,
this Court ruled that traditional bilateral contracting
is permissible under the FPA and in fact went further
noting that bilateral contracts are arrangements
“which FERC has long accommodated. . . .” Id. at 1299.
The Second Circuit reviewed the record before it
and concluded that “the contracts . . . before us are the
kind of traditional bilateral contracts between utilities
14
and generators . . . [and] are . . . precisely what the
Hughes court placed outside its limited holding.” Pet.
App. 34a.
Allco then asserts that the state procurements are
“economically indistinguishable” to the prohibited
transactions in Hughes. Pet. Cert. at 21. In reality,
this Court explicitly differentiated the contracts for
differences in Hughes from the standard bilateral
contracts. Hughes, 136 S. Ct. at 1299. Specifically,
the Hughes contract “involve[d] the capacity auction
administered” by a regional grid operator. Id. at 1293.
This Court noted that the State of Maryland had, in
that case, required a generator to participate in the
regional auction, but at a different rate from the
FERC-approved market rate and thus “Maryland’s
program invades FERC’s regulatory turf.” Id. at 1297.
This Court noted that “the contract at issue here
differs from traditional bilateral contracts in this
significant respect: The contract for differences does
not transfer ownership of capacity from one to another
outside the auction. Instead, the contract for differences
operates within the auction. . . .” Id. at 1299.
This Court concluded:
So long as a State does not condition payment
of funds on capacity clearing the auction, the
State’s program would not suffer from the
fatal defect that renders Maryland’s program
unacceptable.
Id.
15
In its decision below, the Second Circuit applied
the reasoning of Hughes and found “important and
telling distinctions” between the Maryland and
Connecticut programs. The court found that the
Connecticut RFPs were not tethered to the market
and resulted in the actual purchase of electricity.
Pet. App. 34a. Thus, the court concluded that the
contracts at issue were not contracts for differences,
but rather traditional bilateral contracts. Id.
The Commissioner has issued a competitive
renewable energy RFP under state law to address state
environmental and resource adequacy needs. Nothing
in state law permits the Commissioner to change,
modify, or affect regional energy auction prices or in
any manner intrude upon FERC’s jurisdiction. The
contracts that resulted from the RFPs were traditional
bilateral contracts that were never forced upon any
utility and were not tethered to participation in any
FERC auction market. Therefore, the state’s actions
are not preempted by the Federal Power Act and Allco
cannot prevail on the merits of its case.
B. Judicial Colloquy Is Not the Decision of
the Court
Allco argues that the “permissibility of Statecoerced bilateral contracts was rejected out-of-hand at
oral argument” in Hughes. Pet. Cert. at 2, 20. Allco
quotes an excerpt from oral argument to the effect that
“at least two justices rejected” the claim that states
have the “right under the FPA to compel or direct its
16
utilities to enter into wholesale power contracts. . . .”
Pet. Cert. at 2.
The formal decision of a court is its published
decision. What a judge or judges say at oral argument
is not the ruling of the court.
------------------------------------------------------------------
CONCLUSION
For all of the reasons set forth herein, the petition
for a writ of certiorari should be denied.
Respectfully submitted,
GEORGE JEPSEN
Attorney General
of Connecticut
ROBERT D. SNOOK
Counsel of Record
Assistant Attorney General
OFFICE OF THE
ATTORNEY GENERAL
55 Elm Street, P.O. Box 120
Hartford, CT 06141-0120
Robert.Snook@ct.gov
(860) 808-5250
Counsel for Respondents
Dated: December, 2017
This is a copy of a public record, reproduced as it was published. It is not legal advice, and it may not be the version a court would rely on. Check the official source before you cite it.