Petition for Writ of Certiorari — Constitution Pipeline Company, LLC, Petitioner v. New York State Department of Environmental Conservation, et al.
Supreme Court briefJan 16, 2018
Ask Donna
What actually matters in this document.
Text
No. 17In the
Supreme Court of the United States
CONSTITUTION PIPELINE COMPANY, LLC,
Petitioner,
v.
NEW YORK STATE DEPARTMENT OF ENVIRONMENTAL
CONSERVATION; BASIL SEGGOS, COMMISSIONER, NEW
YORK STATE DEPARTMENT OF ENVIRONMENTAL
CONSERVATION; JOHN FERGUSON, CHIEF PERMIT
ADMINISTRATOR, NEW YORK STATE DEPARTMENT
OF ENVIRONMENTAL CONSERVATION,
Respondents.
On Petition for a Writ of Certiorari to the United
States Court of A ppeals for the Second Circuit
PETITION FOR A WRIT OF CERTIORARI
Philip C. Bobbitt
Herbert Wechsler Professor of
Federal Jurisprudence and
Director for the Center for
National Security
Columbia Law School
Jerome Greene Hall, Room 720
435 West 116th Street
New York, NY 10027
Elizabeth U. Witmer
Saul Ewing A rnstein
& Lehr LLP
1200 Liberty Ridge Drive,
Suite 200
Wayne, PA 19087
John F. Stoviak
Counsel of Record
Patrick F. Nugent
Saul Ewing A rnstein
& Lehr LLP
Centre Square West
1500 Market Street,
38th Floor
Philadelphia, PA 19102
(215) 972-1095
john.stoviak@saul.com
A ndrew T. Bockis
Saul Ewing A rnstein
& Lehr LLP
Two North 2nd Street,
7th Floor
Harrisburg, PA 17101
Counsel for Petitioner
January 16, 2018
277774
i
QUESTION PRESENTED
The Energy Policy Act of 2005, amending the Natural
Gas Act of 1938 (“NGA”), reaffirms Congress’ clear intent
to federalize the approval and regulation of interstate
natural gas pipelines by providing for the comprehensive
federal regulation of the transportation and sale of
natural gas in interstate commerce by the Federal
Energy Regulatory Commission (“FERC”). See Islander
E. Pipeline Co., LLC v. Conn. Dep’t of Envtl. Prot., 482
F.3d 79, 84 (2d Cir. 2006); see also Schneidewind v. ANR
Pipeline Co., 485 U.S. 293, 300–01 (1988). “Congress
placed authority regarding the location of interstate
pipelines . . . in the FERC, a federal body that can make
choices in the interests of energy consumers nationally
. . . .” Nat’l Fuel Gas Supply Corp. v. Pub. Serv. Comm’n,
894 F.2d 571, 579 (2d Cir. 1990).
The NGA preempts state permitting and licensing
requirements, see Islander E. Pipeline Co., LLC v.
McCarthy, 525 F.3d 141, 143 (2d Cir. 2008), expressly
limiting narrowly tailored authority for states to
administer three federal regulatory statutes. One of these
is the Clean Water Act (“CWA”). See 15 U.S.C. § 717b(d)
(3). Under Section 401 of the CWA (“Section 401”), any
applicant seeking a federal permit for an activity that
“may result in any discharge into the navigable waters”
must obtain “a certification from the State in which the
discharge originates or will originate . . . that any such
discharge will comply with” the state’s federally-approved
water quality standards. 33 U.S.C. § 1341(a)(1). No
applicable federal license or permit will be granted unless
the certification required by Section 401 has been obtained,
or the reviewing state body waives the requirement by
ii
failing to act on an application for certification within a
reasonable period of time, not to exceed one year. Id.
This narrowly tailored authority does not allow a
state to frustrate principles of federal supremacy and
impede interstate commerce because it disagrees with
the FERC-approved route and location of an interstate
natural gas pipeline.
The question presented is:
Whether a state’s denial of a federally-approved
interstate natural gas pipeline’s request for certification
under Section 401 of the CWA on the basis of purportedly
receiving insufficient information regarding alternative
routes for the interstate natural gas pipeline exceeds
the state’s limited authority under the Energy Policy
Act of 2005 and the Natural Gas Act of 1938, interferes
with FERC’s exclusive jurisdiction over the routing of
interstate natural gas pipelines when consideration of
alternative routes is explicitly not part of the state’s
federally-approved water quality standards, and violates
fundamental principles of federal supremacy arising from
the Constitution’s Supremacy Clause?
iii
PARTIES TO THE PROCEEDING AND RULE 29.6
CORPORATE DISCLOSURE STATEMENT
The petitioner below was Constitution Pipeline
Company, LLC. The respondents below were: the New
York State Department of Environmental Conservation;
Basil Seggos, then Acting Commissioner of the New
York State Department of Environmental Conservation
(and now its Commissioner); and John Ferguson, Chief
Permit Administrator of the New York State Department
of Environmental Conser vation. The inter venors
below, supporting the respondents, were: Stop the
Pipeline; Catskill Mountainkeeper, Inc.; Sierra Club; and
Riverkeeper, Inc.
Constitution Pipeline Company, LLC is a limited
liability natural gas pipeline company organized and
existing under the laws of the State of Delaware. The
members of Constitution include Williams Partners
Operating LLC (41 percent), Cabot Pipeline Holdings,
LLC (25 percent), Piedmont Constitution Pipeline
Company, LLC (24 percent), and WGL Midstream CP,
LLC (10 percent). The respective members’ direct and
indirect parents are Williams Partners Operating LLC,
Williams Partners L.P., The Williams Companies, Inc.,
WGL Midstream, Inc., WGL Holdings, Inc., Washington
Gas Resources Corp., Duke Energy Pipeline Holding
Company, LLC, and Duke Energy Corporation. The
following publicly-held corporations directly or indirectly
own a 10% or more interest in Constitution Pipeline
Company, LLC: Williams Partners L.P., The Williams
Companies, Inc., Duke Energy Corporation, and WGL
Holdings, Inc. Cabot Oil & Gas Corporation is an indirect,
beneficial owner of a 25% membership interest through
iv
its wholly-owned subsidiary, Cabot Pipeline Holdings,
LLC. In addition, The Williams Companies Inc. owns
10% or more of the publicly-held limited partner interest
in Williams Partners, L.P. Duke Energy Corporation
is an indirect owner of Duke Energy Pipeline Holding
Company, LLC.
v
TABLE OF CONTENTS
Page
QUESTION PRESENTED . . . . . . . . . . . . . . . . . . . . . . . . i
PA RTIES TO THE PROCEEDING A ND
RULE 29.6 CORPORATE DISCLOSURE
STATEMENT . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . iii
TABLE OF CONTENTS . . . . . . . . . . . . . . . . . . . . . . . . . v
TABLE OF APPENDICES . . . . . . . . . . . . . . . . . . . . . viii
TABLE OF CITED AUTHORITIES . . . . . . . . . . . . . . ix
OPINION BELOW . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1
JURISDICTION . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1
STATUTORY PROVISIONS INVOLVED . . . . . . . . . . 2
INTRODUCTION . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 4
STATEMENT OF THE CASE . . . . . . . . . . . . . . . . . . . 10
I.
The Interstate Project . . . . . . . . . . . . . . . . . . . . . 10
II. FERC’s Comprehensive Review and
Approval of the Interstate Project . . . . . . . . . . . 11
III. NYSDEC’s Denial of the Section 401
Certification . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 13
vi
Table of Contents
Page
IV. The Second Circuit Denies Constitution’s
Petition for Review of NYSDEC’s Denial of
the Section 401 Certification . . . . . . . . . . . . . . . . 15
REASONS FOR GRANTING THE PETITION . . . . 16
I.
The Second Circuit’s Decision Conflicts
With the Decisions of This Court and
Other Courts of Appeals on an Important
Question of Federal Law That Has Profound
Implications for the Development of Critical
National Energ y Infrastructure and
U.S. National Security . . . . . . . . . . . . . . . . . . . . . 16
A. Cong ress Gave FERC Exclusive
A ut hor it y t o R out e I nt e r st at e
Natural Gas Pipelines . . . . . . . . . . . . . . . . . 17
B. States’ Limited Authority Under Section
401 of the CWA Does Not Include Routing
of Interstate Natural Gas Pipelines . . . . . 19
vii
Table of Contents
Page
C. Allowing States to Act Beyond the
Limits of Their Authority Under Section
401 of the CWA and in an Area Reserved
Exclusively for Federal Regulation
Frustrates Fundamental Principles
A r ising f rom the Constitution’s
Supremacy Clause in A rticle VI
and the Commitment to Congress
of the Reg ulation of Commerce
Among the Several States and with
Foreign Nations in Article II . . . . . . . . . . . 21
CONCLUSION . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 25
viii
TABLE OF APPENDICES
Page
A P P E N DI X A — O P I N ION O F T H E
UNITED STATES COURT OF APPEALS
FOR THE SECOND CIRCUIT, DATED
AUGUST 18, 2017 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1a
APPENDIX B — THE NEW YORK STATE
DEPARTMENT OF ENVIRONMENTAL
C ONS ERVA T ION ’ S A PR I L 2 2 , 2 016
DENIAL OF CONSTITUTION PIPELINE
COMPANY, LLC’S A PPLICATION FOR
A WATER QUALIT Y CERTIFICATION
UNDER SECTION 401 OF THE CLEAN
WATER ACT FOR THE CONSTITUTION
PIPELINE PROJECT . . . . . . . . . . . . . . . . . . . . . . . 35a
APPENDIX C — DENIAL OF REHEARING
OF THE UNITED STATES COURT OF
APPEALS FOR THE SECOND CIRCUIT,
DATED OCTOBER 19, 2017 . . . . . . . . . . . . . . . . . . . . 66a
ix
TABLE OF CITED AUTHORITIES
Page
CASES
Constitution Pipeline Co., LLC v.
N.Y. State Dep’t of Envtl. Conservation,
868 F.3d 87 (2d Cir. 2017) . . . . . . . . . . . . . . . . . . passim
Gibbons v. Ogden,
22 U.S. (9 Wheat.) 1 (1824) . . . . . . . . . . . . . . . . . . . . . 23
Islander E. Pipeline Co., LLC v.
Conn. Dep’t of Envtl. Prot.,
482 F.3d 79 (2d Cir. 2006) . . . . . . . . . . . . . . . . . . . . . . 24
Islander E. Pipeline Co., LLC v. McCarthy,
525 F.3d 141 (2d Cir. 2008) . . . . . . . . . . . . . . . . . . 16, 18
Milk Control Bd. v. Eisenberg Farm Prods.,
306 U.S. 346 (1939) . . . . . . . . . . . . . . . . . . . . . . . . . . . 22
Millennium Pipeline Co., L.L.C. v. Seggos,
No. 117CV1197MADCFH,
2017 WL 6397742 (N.D.N.Y. Dec. 13, 2017) . . . . 19-20
N. Nat. Gas Co. v. State Corp. Comm’n,
372 U.S. 84 (1963) . . . . . . . . . . . . . . . . . . . . . . . . . . . . 17
Nat’l Fuel Gas Supply Corp. v.
Pub. Serv. Comm’n,
894 F.2d 571 (2d Cir. 1990) . . . . . . . . . . . . . . . . . passim
x
Cited Authorities
Page
Niagara Mohawk Power Corp. v.
N.Y. State Dep’t of Envtl. Conservation,
592 N.Y.S.2d 141 (N.Y. App. Div. 1993), aff’d,
624 N.E.2d 146 (N.Y. 1993), cert. denied,
511 U.S. 1141 (1994) . . . . . . . . . . . . . . . . . . . . . . . . . . . 20
Pennsylvania v. Wheeling & Belmont Bridge Co.,
59 U.S. 421 (1855) . . . . . . . . . . . . . . . . . . . . . . . . . . . . 22
Schneidewind v. ANR Pipeline Co.,
485 U.S. 293 (1988) . . . . . . . . . . . . . . . . . . . . . . . passim
Steward Machine Co. v. Davis,
301 U.S. 548 (1937) . . . . . . . . . . . . . . . . . . . . . . . . . . . . 9
Weaver’s Cove Energy, LLC v.
R.I. Coastal Res. Mgmt. Council,
589 F.3d 458 (1st Cir. 2009) . . . . . . . . . . 8, 16-17, 18, 19
STATUTES AND OTHER AUTHORITIES
U.S. Const. amend. XXI, § 2 . . . . . . . . . . . . . . . . . . . . . . 23
15 U.S.C. § 717(a) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2, 22
15 U.S.C. § 717(b) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 22
15 U.S.C. § 717b(d) . . . . . . . . . . . . . . . . . . . . . . . 3, 5, 18, 22
15 U.S.C. § 717f(c)(1)(A) . . . . . . . . . . . . . . . . . . . . . . . . . . 11
xi
Cited Authorities
Page
15 U.S.C. § 717f(e) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 11
15 U.S.C. § 717r(d)(1) . . . . . . . . . . . . . . . . . . . . . . . . . . 1, 15
28 U.S.C. § 1254(1) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1
28 U.S.C. § 2101(c) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1
33 U.S.C. § 1341(a)(1) . . . . . . . . . . . . . . . . . . . . . . . 4, 14, 19
33 U.S.C. § 1344(a) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 13
6 N.Y.C.R.R. §§ 700-706 . . . . . . . . . . . . . . . . . . . . . . . . . . 20
David Biello, Can U.S. Fracked Gas Save Ukraine?,
Scientific A merican, Mar. 11, 2014 . . . . . . . . . . . . . 17
Dr. David Gordon, et al., Energy, Economic
Growth, and U.S. National Security, Ctr .
for a New A m Sec. (Nov. 13, 2017) . . . . . . . . . . . . . 6, 7
Elizabeth Rosenberg, Energy Rush: Shale
Production and U.S. National Security, Ctr.
for a New A m. Sec., (Feb. 2014) . . . . . . . . . . . . . . . . . 6
Elizabeth Rosenberg, et al., The New Great Game
– Changing Global Energy Markets, The ReEmergent Strategic Triangle, and U.S. Policy,
Ctr. for a New A m. Sec. (June 15, 2016) . . . . . . . . . . 7
George L. Haskins, John Marshall and the
xii
Cited Authorities
Page
Commerce Clause of the Constitution,
104 U. Pa. L. Rev. 23 (1955) . . . . . . . . . . . . . . . . . . . . 23
P r e s i d e n t i a l D e c i s i o n D i r e c t i ve 6 3 o n
Cr itical Infrastr ucture Protection,
63 Fed. Reg. 41804-01 (Aug. 5, 1998) . . . . . . . . . . . . 21
Project Benefits, Const. Pipeline . . . . . . . . . . . . . . . . . . 10
S. Rep. No. 109-78 (2005) . . . . . . . . . . . . . . . . . . . . . . . . . . 6
Sup. Ct. R. 13.1 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1
Sup. Ct. R. 13.3 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1
1
Petitioner Constitution Pipeline Company, LLC
(“Constitution”) respectfully petitions this Court for a writ
of certiorari to review the judgment of the United States
Court of Appeals for the Second Circuit.
OPINION BELOW
The opinion of the United States Court of Appeals for
the Second Circuit (App. 1a-34a)1 is reported at 868 F.3d
87. The New York State Department of Environmental
Conservation’s letter denying Constitution’s application
for a water quality certification under Section 401 of the
Clean Water Act is reproduced at App. 35a-65a.
JURISDICTION
The United States Court of Appeals for the Second
Circuit issued its opinion and entered judgment in this
case on August 18, 2017. App. 1a. Constitution filed a
petition for panel rehearing and/or rehearing en banc
on September 1, 2017. The Court of Appeals denied
Constitution’s rehearing petition on October 19, 2017.
App. 66a-67a. This petition is timely under 28 U.S.C.
§ 2101(c) and Supreme Court Rules 13.1 and 13.3 because
it is being filed within 90 days of the date of the denial
of rehearing. This Court has jurisdiction to review the
Court of Appeals’ judgment under 28 U.S.C. § 1254(1).
Constitution originally invoked federal jurisdiction in
the Second Circuit under the Natural Gas Act, 15 U.S.C.
§ 717r(d)(1).
1. “App.” refers to the pages of the Appendices accompanying
this Petition for a Writ of Certiorari.
2
STATUTORY PROVISIONS INVOLVED
Section 717 of the Natural Gas Act (“NGA”) provides,
in relevant part:
(a) Necessity of regulation in public interest
As disclosed in reports of the Federal Trade
Commission made pursuant to S.Res. 83
(Seventieth Congress, first session) and other
reports made pursuant to the authority of
Congress, it is declared that the business of
transporting and selling natural gas for ultimate
distribution to the public is affected with a
public interest, and that Federal regulation
in matters relating to the transportation of
natural gas and the sale thereof in interstate
and foreign commerce is necessary in the public
interest.
15 U.S.C. § 717(a).
Section 717b of the NGA provides, in relevant part:
(d) Construction with other laws
Except as specifically provided in this chapter,
nothing in this chapter affects the rights of
States under—
(1) the Coastal Zone Management Act of 1972
(16 U.S.C. 1451 et seq.);
(2) the Clean Air Act (42 U.S.C. 7401 et seq.); or
3
(3) the Federal Water Pollution Control Act (33
U.S.C. 1251 et seq.).
15 U.S.C. § 717b(d).
Section 401 of the Clean Water Act (“CWA”) provides,
in relevant part:
(a) Compliance with applicable requirements;
application; procedures; license suspension
(1) Any applicant for a Federal license or permit
to conduct any activity including, but not limited
to, the construction or operation of facilities,
which may result in any discharge into the
navigable waters, shall provide the licensing
or permitting agency a certification from
the State in which the discharge originates
or will originate, or, if appropriate, from the
interstate water pollution control agency
having jurisdiction over the navigable waters
at the point where the discharge originates
or will originate, that any such discharge
will comply with the applicable provisions of
sections 1311, 1312, 1313, 1316, and 1317 of this
title. In the case of any such activity for which
there is not an applicable effluent limitation
or other limitation under sections 1311(b) and
1312 of this title, and there is not an applicable
standard under sections 1316 and 1317 of this
title, the State shall so certify, except that
any such certification shall not be deemed to
satisfy section 1371(c) of this title. Such State
or interstate agency shall establish procedures
4
for public notice in the case of all applications
for certification by it and, to the extent it deems
appropriate, procedures for public hearings in
connection with specific applications. In any
case where a State or interstate agency has
no authority to give such a certification, such
certification shall be from the Administrator. If
the State, interstate agency, or Administrator,
as the case may be, fails or refuses to act on a
request for certification, within a reasonable
period of time (which shall not exceed one year)
after receipt of such request, the certification
requirements of this subsection shall be waived
with respect to such Federal application. No
license or permit shall be granted until the
certification required by this section has been
obtained or has been waived as provided in
the preceding sentence. No license or permit
shall be granted if certification has been
denied by the State, interstate agency, or the
Administrator, as the case may be.
33 U.S.C. § 1341(a)(1).
INTRODUCTION
Consistent with the express intent of the NGA
to federalize the regulation of interstate natural gas
pipelines, the Federal Energy Regulatory Commission
(“FERC”) conducted a comprehensive thirty-one
month review process that included consideration of
nine separate letters submitted by the New York State
Department of Environmental Conservation (“NYSDEC”)
addressing in detail NYSDEC’s objections to the proposed
5
route for Constitution’s proposed interstate natural
gas pipeline project (“Interstate Project”). FERC then
issued a Certificate of Public Convenience and Necessity
(“Certificate Order”) determining that Constitution’s
Interstate Project was in the national public interest.
It is noteworthy that NYSDEC did not file an appeal
challenging FERC’s issuance of the Certificate Order.
Instead, NYSDEC attempted to bootstrap its limited
authority to review interstate natural gas projects
for compliance with federally-approved water quality
standards under Section 401 of the CWA by denying a
water quality certification (“Section 401 Certification”).
Although a state is within its authority to deny a Section
401 Certification when its denial is timely and based
on federally-approved water quality standards, here
NYSDEC notably delayed issuing a denial until Earth
Day (April 22, 2016), justifying its ultimate denial (the
“Denial”) on, inter alia, an alleged failure to provide
NYSDEC sufficient information about an alternative route
for the Interstate Project—an issue over which FERC has
exclusive authority. It is undisputed that the basis for this
denial is not limited to an application of federally-approved
water quality standards. Nor is it disputed that Congress
provided FERC with exclusive authority over the routing
of interstate natural gas pipelines.
The NGA federalizes the regulation of interstate
natural gas pipelines, though it employs narrowly tailored
state determinations as part of the federally-mandated
process. These determinations are linked to specific state
findings under the CWA, the Coastal Zone Management
Act, and the Clean Air Act. See 15 U.S.C. § 717b(d). By
overstepping their carefully circumscribed roles under
6
the NGA in order to block interstate pipelines, states,
like New York here, would frustrate Congress’ express
intent in passing the Energy Policy Act of 2005, which was
to “provide a comprehensive national energy policy that
balances domestic energy production with conservation
and efficiency efforts to enhance the security of the United
States and decrease dependence on foreign sources of
fuel,” S. Rep. No. 109-78, at 1 (2005).
The last point can scarcely be overstated. Domestic
energy development and a robust energy supply with
reliable transportation infrastructure (including
interstate natural gas pipelines) are vitally important to
our national security interests. At this very time, “[t]he
United States is currently taking a major step forward in
energy production as a result of the shale energy boom, a
development that will contribute to . . . energy security.” 2
“The return of the United States as a major global energy
producer and exporter . . . open[s] global energy markets
. . . [and] provid[es] greater resilience to those markets,
which adds to the security of supply. This has already
led to concrete national security benefits for the United
States.” 3 “[G]reater resilience undermines would-be
regional hegemons who seek to use energy as a coercive
2. Elizabeth Rosenberg, Energy Rush: Shale Production
and U.S. National Security, Ctr . for a New A m. Sec., (Feb.
2014), https://www.cnas.org/publications/reports/energy-rush-shaleproduction-and-u-s-national-security (follow “Download PDF”
hyperlink).
3. Dr. David Gordon, et al., Energy, Economic Growth,
and U.S. National Security, Ctr. for a New A m Sec. (Nov. 13,
2017), https://www.cnas.org/publications/reports/energy-economicgrowth-and-u-s-national-security-the-case-for-an-open-trade-andinvestment-regime (follow “Download PDF” hyperlink).
7
tool against the United States and its allies by limiting
their ability to control access to their energy resources.”4
Additionally, “supporting and encouraging a strong
U.S. energy production and export capability . . . can
be a powerful lever to check adversaries or unwelcome
aggression on the international stage.”5
The affirmance of this Denial by the Second Circuit
ultimately turned on its acceptance of NYSDEC’s
maneuver. The “single cognizable rationale” identified by
the Second Circuit was the issue of alternative routes: “A
state’s consideration of a possible alternative route that
would result in less substantial impact on its waterbodies is
plainly within the state’s authority.” Constitution Pipeline
Co., LLC v. N.Y. State Dep’t of Envtl. Conservation, 868
F.3d 87, 101 (2d Cir. 2017), App. 29a.
If not corrected, this decision will have far-reaching
implications for all NGA infrastructure projects. Left
unchecked, states like New York, with an intent to
superimpose their political, parochial interests over
the interests of the nation, will use the Second Circuit’s
expanded reading of their narrowly tailored rights under
Section 401 of the CWA to undermine FERC’s routing
determinations by requiring applicants to consider
“a possible alternative route that would result in less
4. Id.
5. Elizabeth Rosenberg, et al., The New Great Game –
Changing Global Energy Markets, The Re-Emergent Strategic
Triangle, and U.S. Policy, Ctr. for a New A m. Sec. (June 15,
2016), https://www.cnas.org/publications/reports/the-new-greatgame-changing-global-energy-markets-the-re-emergent-strategictriangle-and-u-s-policy (follow “Download PDF” hyperlink).
8
substantial impact,” Constitution Pipeline, 868 F.3d at
101, App. 29a. This would effectively allow states to block
federally reviewed and approved interstate natural gas
pipelines for reasons entirely unrelated to the limited role
Congress has provided to states in the NGA’s regulatory
scheme. Indeed, NYSDEC has effectively instituted a
blockade of FERC-approved natural gas pipelines as
evidenced by its recent denials of Section 401 water quality
certifications for the Interstate Project and two other
projects (Millennium Pipeline Company’s Valley Lateral
Project and National Fuel Gas Supply Corporation’s and
Empire Pipeline, Inc.’s Northern Access Project).
The Second Circuit’s decision eviscerates the
carefully delineated boundaries of cooperative federalism
established by Congress in the NGA, as amended by the
Energy Policy Act of 2005, and presents a profound threat
to our national security by allowing states to intrude
upon FERC’s exclusive jurisdiction in an effort to prevent
development of critical natural gas energy infrastructure,
which, in turn, will impair the development of United
States energy resources, a key priority for our nation’s
national security.
The Court should grant this petition because the
Second Circuit’s decision conflicts with the decisions of this
Court and other federal Courts of Appeals on an important
question of federal law that has profound implications for
the development of critical energy infrastructure and
national security. See Schneidewind v. ANR Pipeline
Company, 485 U.S. 293, 300-01, 305 (1988); Nat’l Fuel Gas
Supply Corp. v. Pub. Serv. Comm’n, 894 F.2d 571, 579 (2d
Cir. 1990); Weaver’s Cove Energy, LLC v. R.I. Coastal Res.
Mgmt. Council, 589 F.3d 458, 472 (1st Cir. 2009). FERC
9
alone has authority to determine the routes of interstate
natural gas pipelines whose environmental impact is to
be assessed by the states strictly according to federal
guidelines. States should not be permitted to effectively
negate FERC’s determinations by maneuvers that are in
effect routing assessments disguised as the exercise of
their limited CWA Section 401 authority. Allowing states
to do so would conflict with the Supremacy jurisprudence of
two centuries of Supreme Court precedent and eviscerate
the NGA and amendments thereto in the Energy Policy
Act of 2005. Absent a ruling from this Court, state officials
will be emboldened by the Second Circuit’s ruling to
transform their CWA Section 401 authority into the power
to block pipelines at the expense of national interests that
FERC is charged to balance and protect. In essence, it
would elevate the Not-In-My-Backyard temptations and
pressures on state officials to an irresistible level by
removing the national check on those pressures carefully
crafted by Congress. Of course the problem of locating
energy pipelines is not the only public policy issue whose
solution cannot be thwarted by individual state action,6 but
6. Justice Cardozo discussed these so-called “collective
action” problems in his opinion for the Court in Steward Machine
Co. v. Davis, 301 U.S. 548 (1937):
Two consequences ensued. One was that the freedom
of a state to contribute its fair share to the solution
of a national problem was paralyzed by fear. The
other was that in so far as there was failure by the
states to contribute relief according to the measure
of their capacity, a disproportionate burden, and a
mountainous one, was laid upon the resources of the
Government of the nation.
Id. at 588.
10
it must be a paradigm case. How could a national critical
infrastructure ever come into being if the permitting
process were localized and held hostage to the political
vagaries of the various states and localities?
Here, Congress has spoken unmistakably: action by
the state must be part of a narrowly tailored process that
does not frustrate the routing plans determined by FERC.
STATEMENT OF THE CASE
I.
The Interstate Project
This case concerns NYSDEC’s Denial of Constitution’s
application for a Section 401 Certification for a 124-mile
interstate natural gas pipeline project from Pennsylvania
to New York.7 The Interstate Project is designed to
provide up to 650,000 dekatherms per day of cleanburning natural gas and its capacity is fully subscribed.
JA1667, JA1670. 8 The Interstate Project will transport
enough natural gas to serve over 3 million homes,9 and
is designed to transport domestically-sourced gas from
Pennsylvania to markets in New England and New York.
Certificate Order ¶ 25, JA1674.
7. Approximately 99 miles of the Interstate Project are
located in New York State; 25 miles are located in Pennsylvania.
Pennsylvania issued a Section 401 Certification on September 5,
2014.
8. “JA” refers to the Joint Appendix filed in the Second
Circuit proceeding.
9. Project Benefits, Const. Pipeline, http://constitutionpipeline.
com/about-the-project/project-benefits/ (last visited Jan. 11, 2018).
11
II. FERC’s Comprehensive Review and Approval of
the Interstate Project
Pursuant to Section 7 of the NGA, a natural gas
company must obtain from FERC a “certificate of public
convenience and necessity” before it constructs, extends,
acquires, or operates any facility for the transportation
or sale of natural gas in interstate commerce. 15 U.S.C.
§ 717f(c)(1)(A). FERC is required to issue a certificate
of public convenience and necessity if it finds that the
proposed project “is or will be required by the present
or future public convenience and necessity,” and FERC
may attach “to the issuance of the certificate . . . such
reasonable terms and conditions as the public convenience
and necessity may require.” Id. § 717f(e).
On June 13, 2013, Constitution filed an application
with FERC for a certificate of public convenience and
necessity authorizing construction and operation of the
Interstate Project. As the lead federal agency under the
National Environmental Policy Act (“NEPA”), FERC
considered extensive environmental data on the Interstate
Project’s potential impacts as part of the environmental
impact statement process. As a consequence of this
review, FERC issued a 400-page Draft Environmental
Impact Statement on February 12, 2014, on which it
received extensive comments (including four letters
from NYSDEC), and thereafter issued a 450-page Final
Environmental Impact Statement (“FEIS”) on October 24,
2014. The FEIS concluded that any adverse environmental
impacts that would result from the Interstate Project
“would be reduced to less than significant levels with the
implementation of Constitution’s . . . proposed mitigation
and the additional measures recommended by staff in
12
the final EIS.” FEIS at 1, JA1006. It is important to note
that as a part of its review, FERC’s Final Environmental
Impact Statement also considered alternative routes for
the Interstate Project, as well as the anticipated impact
on a host of environmental resources. See generally FEIS,
JA1005-JA1469.
NYSDEC actively participated in FERC’s review
proceedings by submitting nine separate comment letters
to FERC between November 2012 and May 2014.10 In its
comment letters to FERC, NYSDEC twice expressed
the commitment that it “intends to rely upon the federal
environmental review prepared pursuant to [NEPA] to
determine if the Project will comply with the applicable
New York standards.” JA75-JA76, JA164. NYSDEC also
expressed a strong preference for an alternative route,
referred to as Alternative M, that would have moved
the proposed pipeline route to a location parallel to New
York Interstate 88 for a substantial portion of the route.
JA223-JA224, JA496-JA515.
FERC specifically rejected NYSDEC’s proposed
alternative route (see FEIS, Volume 3, Appendix S,
Part 2, SA4-2, JA1641-JA1642), expressly articulating
why it did not find Alternative M to be preferable to
the proposed route, and noting that FERC “completed
numerous in-field reviews of the topographical constraints
associated with Alternative M on foot, by car along
I-88, and by helicopter.” Id. FERC’s analysis was
buttressed by an explicit comparison of the impact
10. JA75-JA80, JA81-JA88, JA89-JA127, JA164-JA206,
JA223-JA224, JA486-JA488, JA496-JA515, JA844-JA846, JA853JA855.
13
on waterbodies and wetlands. This comparison “was
one of several environmental parameters supporting
[FERC’s] conclusion that the Alternative M segments
were not preferable to the proposed route segments.”
Id. at SA4-3, JA1643. Additionally, both the New York
State Department of Transportation and the Federal
Highway Administration strongly voiced their safety and
operational concerns regarding the Alternative M routing
advocated by NYSDEC. See JA225-JA293.
After conducting an extensive review for more than
two years and seven months, FERC issued a Certificate
of Public Convenience and Necessity on December 2, 2014
approving the Interstate Project subject to conditions,
including Constitution’s obtaining necessary federal
authorizations. Certificate Order at 45, 51 (Environmental
Condition 8), JA1711, JA1717.
NYSDEC chose not to file an appeal challenging
FERC’s Certificate of Public Convenience and Necessity,
which set the route for the Interstate Project.
III. NYSDEC’s Denial of the Section 401 Certification
Following pre-application consultations with NYSDEC
in 2012 and 2013, Constitution submitted its Section 401
Certification application to NYSDEC on August 22, 2013,
the same day it submitted its application to the United
States Army Corps of Engineers (“U.S. Army Corps”)
for a permit under Section 404 of the CWA, 33 U.S.C.
§ 1344(a). Under Section 401, any applicant for a Section
404 permit to construct or operate a facility that may
result in a discharge must provide the U.S. Army Corps
with “a certification from the State in which the discharge
14
originates . . . that any such discharge will comply with”
federally-approved state water quality standards. 33
U.S.C. § 1341(a)(1).
On Earth Day, two years and eight months after
Constitution submitted its application to NYSDEC, and
following a multitude of detailed technical submissions
to NYSDEC, including a comprehensive summary
responding to over 15,000 public comments related to
Constitution’s application, NYSDEC denied Constitution’s
application on grounds that it purportedly did not contain
sufficient information to determine whether Constitution’s
proposed activities demonstrate compliance w ith
New York’s water quality standards. JA2870-JA2883.
NYSDEC denied Constitution’s application for lack of
sufficient information, notwithstanding that it twice
publicly acknowledged that Constitution had submitted
a complete application. JA1725-JA1732, JA2074-JA2075.
It should not be overlooked that NYSDEC prepared
a twenty-one page draft Section 401 Certification with
extensive conditions that it sent to the U.S. Army Corps
for comment on July 20, 2015, seeking its prompt review
and comment in light of the apparent imminence for
issuance of the Section 401 Certification. JA75-JA76,
JA164, JA2219-JA2241. Nevertheless, NYSDEC shut
down substantive communications with Constitution
regarding the draft Section 401 Certification and made
no request for additional information regarding routing
of the pipeline or any of the subjects on which it would
ultimately base its denial for lack of sufficient information
during the eight month period leading up to the 2016 Earth
Day denial by NYSDEC.
15
It would appear that this silence with the applicant
was not inadvertent, but was an essential element in
NYSDEC’s finding that “Constitution’s unwillingness to
adequately explore the Alternative M route alternative
. . . means that the Department is unable to determine
whether an alternative route is actually more protective
of water quality standards.” Denial at 11, SPA11.11 This
is particularly significant in light of the Second Circuit’s
decision to uphold the Denial.
IV. The Second Circuit Denies Constitution’s Petition
for Review of NYSDEC’s Denial of the Section 401
Certification
On May 16, 2016, Constitution filed a petition for
review of NYSDEC’s Denial with the United States Court
of Appeals for the Second Circuit pursuant to Section
19(d)(1) of the NGA, 15 U.S.C. § 717r(d)(1). Constitution
raised three primary arguments in support of its
petition: (1) NYSDEC waived the Section 401 certification
requirement by failing to act on Constitution’s application
within a reasonable period of time; (2) NYSDEC exceeded
its narrow authority under Section 401 of the CWA,
and intruded upon FERC’s exclusive jurisdiction, by
considering alternative routes for the Interstate Project;
and (3) NYSDEC acted arbitrarily and capriciously in
denying Constitution’s application.
The Second Circuit denied Constitution’s petition for
review and upheld NYSDEC’s Denial. First, the Second
Circuit decided that it lacked jurisdiction to consider
11. “SPA” refers to the Special Appendix filed in the Second
Circuit proceeding.
16
Constitution’s waiver argument. Constitution Pipeline
Co., LLC v. N.Y. State Dep’t of Envtl. Conservation, 868
F.3d 87, 100 (2d Cir. 2017), App. 26a. Turning to the merits,
the Second Circuit rejected the bulk of Constitution’s
arguments out of hand: “We need not address all of these
contentions. . . . [W]here an agency decision is sufficiently
supported by even as little as a single cognizable rationale,
that rationale, ‘by itself, warrants our denial of [a] petition’
for review under the arbitrary-and-capricious standard
of review.” Id. at 101-02 (quoting Islander E. Pipeline
Co., LLC v. McCarthy, 525 F.3d 141, 158 (2d Cir. 2008)),
App. 29a. The “single cognizable rationale” identified by
the Second Circuit was the issue of alternative routes: “A
state’s consideration of a possible alternative route that
would result in less substantial impact on its waterbodies
is plainly within the state’s authority.” Id. at 101, App. 29a.
REASONS FOR GRANTING THE PETITION
I.
The Second Circuit’s Decision Conflicts With the
Decisions of This Court and Other Courts of Appeals
on an Important Question of Federal Law That
Has Profound Implications for the Development of
Critical National Energy Infrastructure and U.S.
National Security
The Second Circuit’s decision conflicts with the
decisions of this Court and federal Courts of Appeals on
an important question of federal law that has material
implications for the development of critical energy
infrastructure in this nation. See Schneidewind v. ANR
Pipeline Co., 485 U.S. 293, 300-01, 305 (1988); Nat’l Fuel
Gas Supply Corp. v. Pub. Serv. Comm’n, 894 F.2d 571,
579 (2d Cir. 1990); Weaver’s Cove Energy, LLC v. R.I.
17
Coastal Res. Mgmt. Council, 589 F.3d 458, 472 (1st Cir.
2009). Without a ruling from this Court, there is a serious
risk that states will use the Second Circuit’s ruling
below to abuse their narrowly tailored CWA Section 401
authority in their efforts to frustrate interstate natural
gas pipeline development at the expense of vital national
interests, including the development of energy security
by the United States and the impact on energy prices
worldwide—with all the implications for the geopolitical
position of the U.S. and other countries—such as Iran
and Russia.12
A.
Congress Gave FERC Exclusive Authority to
Route Interstate Natural Gas Pipelines
“The NGA confers upon FERC exclusive [jurisdiction]
over the transportation and sale of natural gas in interstate
commerce for resale.” Schneidewind, 485 U.S. at 300-01
(citing N. Nat. Gas Co. v. State Corp. Comm’n, 372 U.S. 84,
89 (1963)); see also id. at 305 (“Congress occupied the field
of matters relating to wholesale sales and transportation
of natural gas in interstate commerce.”). This Court has
long held that “facilities of natural gas companies are”
one of “the things over which FERC has comprehensive
authority.” Id. at 308; see also Nat’l Fuel Gas Supply, 894
F.2d at 579 (“Congress placed authority regarding the
location of interstate pipelines . . . in the FERC, a federal
body that can make choices in the interests of energy
consumers nationally . . . .”). The Second Circuit’s holding
that “[a] state’s consideration of a possible alternative
12. See, e.g., David Biello, Can U.S. Fracked Gas Save
Ukraine?, S cientific A merican, Mar. 11, 2014, https://www.
scientificamerican.com/article/can-us-fracked-gas-save-ukraine/.
18
route that would result in less substantial impact on
its waterbodies is plainly within the state’s authority,”
Constitution Pipeline, 868 F.3d at 101, App. 29a, squarely
conflicts with this Court’s decision in Schneidewind, as
well as the Second Circuit’s decision in National Fuel and
the First Circuit’s decision in Weaver’s Cove,13 all of which
recognize FERC’s exclusive authority over the siting of
natural gas facilities.
The Second Circuit cites its previous decision in
Islander East Pipeline Co., LLC v. McCarthy, 525
F.3d 141, 151-52 (2d Cir. 2008) (“Islander East II”) as
support for its ruling that a state may second-guess
FERC’s routing determination, but Islander East II says
nothing to support a departure from its prior precedent
in National Fuel. In Islander East II, the Connecticut
Department of Environmental Protection (“CTDEP”)
made an affirmative determination that the FERCapproved route—not an alternative route preferred
by CTDEP—“would adversely affect shellfish habitat
and cause the loss of an existing and designated use,
i.e., shellfishing, over an unacceptably large area” and,
therefore, would not comply with state water quality
standards. Id. at 152. Nowhere did the Court in Islander
East II suggest—much less hold—that a state agency
may insist on the consideration of an alternative route
13. Weaver’s Cove involved the regulation of a proposed
liquefied natural gas (“LNG”) terminal under the Coastal Zone
Management Act—one of the three statutes pursuant to which
states may regulate NGA-governed projects. See 15 U.S.C.
§ 717b(d). The differences between that case and this one are
immaterial. Under the NGA, FERC possesses exclusive authority
over the siting of facilities. That remains true irrespective of
whether the proposed facilities are for a natural gas pipeline or
an LNG terminal.
19
or reject a Section 401 Certification because it prefers
a different route over the route FERC approved. The
Second Circuit’s endorsement of NYSDEC’s improper
efforts to re-evaluate alternative routes rejected by FERC
is a fundamental error of law that poses a serious threat
to development of interstate natural gas facilities. The
Second Circuit’s ruling below creates untenable conflicts
within the Second Circuit and with the First Circuit’s
decision in Weaver’s Cove,14 presenting a serious risk
that Courts of Appeals will continue to reach different
outcomes on an issue that should be uniformly decided
under the federal statutory scheme.
B. States’ Limited Authority Under Section 401
of the CWA Does Not Include Routing of
Interstate Natural Gas Pipelines
Section 401 of the CWA explicitly circumscribes the
states’ role in reviewing projects for compliance with
federally-approved water quality standards. 33 U.S.C.
§ 1341(a)(1)15; see also Millennium Pipeline Co., L.L.C.
14. See note 13, supra.
15. Sections 1311, 1312, 1316, and 1317 establish, and
allow the Environmental Protection Agency (“EPA”)
to establish, standards governing numerous aspects of
water quality; and § 1313 allows states to develop their
own water quality standards and submit them to the
EPA for approval. If the EPA approves a state’s water
quality standards, it publishes a notice of approval
and they become the state’s EPA-approved standards,
regulating water quality in that state. See 33 U.S.C.
§§ 1313(a), (c).
Constitution Pipeline, 868 F.3d at 101, App. 27a-28a.
20
v. Seggos, No. 117CV1197MADCFH, 2017 WL 6397742,
at *2 (N.D.N.Y. Dec. 13, 2017) (“In reviewing applications
for Section 401 certification, states may apply their own
EPA-approved state water quality standards.”). However,
“[r]eview by State agencies that would overlap or
duplicate the Federal purview and prerogatives was
not contemplated and would infringe on and potentially
conflict with an area of the law dominated by the nationally
uniform Federal statutory scheme.” Niagara Mohawk
Power Corp. v. N.Y. State Dep’t of Envtl. Conservation,
624 N.E.2d 146, 148 (N.Y. 1993), cert. denied, 511 U.S.
1141 (1994).
“Section 401 of the Clean Water Act . . . serves as
the conduit for the incorporation of relevant State water
quality standards in this otherwise Federally filled
universe.” Niagara Mohawk, 624 N.E.2d at 149; see also
Niagara Mohawk Power Corp. v. N.Y. State Dep’t of
Envtl. Conservation, 592 N.Y.S.2d 141, 143 (N.Y. App. Div.
1993), aff’d, 624 N.E.2d 146 (N.Y. 1993) (“[E]nvironmental
and conservation factors of concern to a State are to be
weighed at the Federal level; to allow them to serve as a
predicate for a State ‘veto’ of the project is indefensible for
it would effectively undermine the intent of Congress.”).
The routing of interstate natural gas pipelines falls
within the exclusive province of FERC and is scarcely a
federally-approved water quality standard. See Section
I.A., supra; 6 N.Y.C.R.R. §§ 700-706. The Second Circuit’s
ruling upholding NYSDEC’s Denial on the issue of
alternative routes is precisely the type of intrusion upon
“an area of the law dominated by the nationally uniform
Federal statutory scheme,” Niagara Mohawk, 624 N.E.2d
at 148, that is not permitted under a state’s narrowly
21
tailored Section 401 authority, particularly when FERC
rejected NYSDEC’s routing comments during the NEPA
review process and NYSDEC did not challenge the route
chosen in FERC’s Certificate of Public Convenience and
Necessity for the Interstate Project.
C.
Allowing States to Act Beyond the Limits
of Their Authority Under Section 401 of the
CWA and in an Area Reserved Exclusively for
Federal Regulation Frustrates Fundamental
Principles Arising from the Constitution’s
Supremacy Clause in Article VI and the
Commitment to Congress of the Regulation
of Commerce Among the Several States and
with Foreign Nations in Article II
NYSDEC’s denial of the Section 401 Certification for
the Interstate Project on grounds outside of its limited
authority under Section 401 of the CWA unlawfully
frustrates principles of federal supremacy, impedes
interstate commerce, deprives other states of the benefits of
clean-burning and inexpensive natural gas to satisfy their
energy needs, and threatens national security interests in
domestic energy development and a robust energy supply
with reliable and secure infrastructure.16 In the NGA,
Congress declared that “the business of transporting and
selling natural gas for ultimate distribution to the public is
affected with a public interest, and that Federal regulation
in matters relating to the transportation of natural gas
16. See Presidential Decision Directive 63 on Critical
Infrastructure Protection, 63 Fed. Reg. 41804-01 (Aug. 5, 1998)
(defining the nation’s “critical infrastructure” to include energy
infrastructure, which includes pipelines).
22
and the sale thereof in interstate and foreign commerce
is necessary in the public interest.” 15 U.S.C. § 717(a); see
also id. § 717(b) (Congress drafted the NGA to, among
other things, “apply to the transportation of natural gas
in interstate commerce”). Allowing an individual state
to unilaterally accord its interests dispositive weight
manipulates the balance of national interests with respect
to commerce among the states and with foreign nations, of
which Congress is the arbiter, and destroys the uniformity
that is essential to the success of the interstate system of
natural gas transportation.
Protecting interstate and foreign commerce is one
of the most basic and essential functions of our national
government. “The United States could not exist as a nation
if each of them were to have the power to forbid imports
from another state, to sanction the rights of citizens to
transport their goods interstate, or to discriminate as
between neighboring states in admitting articles produced
therein.” Milk Control Bd. v. Eisenberg Farm Prods., 306
U.S. 346, 351 (1939). Congress may choose to authorize state
actions that impede free trade and interstate commerce,
but without Congressional legislation authorizing such
actions, they are prohibited under the Commerce Clause.
See Pennsylvania v. Wheeling & Belmont Bridge Co.,
59 U.S. 421, 422 (1855). Here, Congress has established
a clear delineation of federal and state authority in the
regulation of interstate natural gas pipelines. The NGA,
as amended by the Energy Policy Act of 2005, allows
states a limited and narrowly circumscribed authority to
participate in the regulatory process by means of three
statutes, one of which is the CWA. See 15 U.S.C. § 717b(d).
In all other matters, interstate natural gas pipelines are
regulated at the federal level.
23
It is easy to confuse a federal regulatory scheme
that leaves state options intact—like Section 2 of the
Constitution’s XXI Amendment17—with one in which
a federal statute uses a state determination, carefully
circumscribed by Congress, as an element in a federal
agency’s overall final determination. But the two
regulatory schemes are not the same. Treating the latter
regulatory method as if it were the former permits the
state “tail” to wag the federal “dog”. It is not surprising
that in such a politically fraught area as pipeline location,
states have found this confusion very tempting indeed.
The threat to interstate commerce presented by
NYSDEC’s Denial and the Second Circuit’s decision is
reminiscent of Gibbons v. Ogden, 22 U.S. (9 Wheat.) 1
(1824). “Gibbons v. Ogden was the needed guarantee
that interstate rail, telephone and telegraph, oil and gas
pipe lines might be built across state lines without the
threat of local interference from state action.” George
L. Haskins, John Marshall and the Commerce Clause of
the Constitution, 104 U. Pa. L. Rev. 23, 28 (1955). “The
question before the Court was whether the commerce
clause invalidated the act of a state purporting to grant
an exclusive right to navigate the waters of that state.” Id.
at 24. The Court “held that, under the commerce clause,
an act of Congress dealing with the subject matter of the
clause is superior to a state statute inconsistent therewith
and dealing with the same subject matter.” Id. at 25 (citing
Gibbons, 22 U.S. (9 Wheat.) at 221). Similar to Gibbons,
17. “Section 2. The transportation or importation into any
State, Territory, or possession of the United States for delivery or
use therein of intoxicating liquors, in violation of the laws thereof,
is hereby prohibited.” U.S. Const. amend. XXI, § 2.
24
here, New York is regulating subject matter Congress
reserved exclusively for federal regulation by FERC. The
supremacy of the essential federal prerogative must be
preserved.
The Second Circuit’s decision below poses a serious
threat to interstate and foreign commerce by allowing
states to wield power that Congress has not given them
to block development of interstate energy infrastructure.
The NGA thoroughly federalizes regulation of interstate
natural gas pipelines. “The NGA confers upon FERC
exclusive jurisdiction over the transportation and
sale of natural gas in interstate commerce for resale.”
Schneidewind, 485 U.S. at 300-01; see also Islander E.
Pipeline, 482 F.3d at 90 (“Congress wholly preempted and
completely federalized the area of natural gas regulation
by enacting [the NGA]”). States have no authority to act
beyond the limits of CWA Section 401 to second-guess
FERC’s determinations and regulate issues over which
only FERC has power to regulate. See Nat’l Fuel Gas
Supply, 894 F.2d at 579 (“Because FERC has authority to
consider environmental issues, states may not engage in
concurrent site-specific environmental review.”). To hold
otherwise would allow “all the sites and all the specifics to
be regulated by agencies with only local constituencies,”
and “would delay or prevent construction that has won
approval after federal consideration of environmental
factors and interstate need, with the increased costs
or lack of gas to be borne by utility consumers in other
states.” Id. That is precisely what is happening in New
York right now with NYSDEC’s recent trilogy of Section
401 Certification denials, and which may happen elsewhere
as states are emboldened by the Second Circuit’s ruling
that states may block FERC-approved interstate natural
25
gas pipelines if they disagree with FERC’s routing
determinations.
CONCLUSION
For each of the foregoing reasons, the Court should
grant the petition.
Respectfully submitted,
Philip C. Bobbitt
Herbert Wechsler Professor of
Federal Jurisprudence and
Director for the Center for
National Security
Columbia Law School
Jerome Greene Hall, Room 720
435 West 116th Street
New York, NY 10027
Elizabeth U. Witmer
Saul Ewing A rnstein
& Lehr LLP
1200 Liberty Ridge Drive,
Suite 200
Wayne, PA 19087
John F. Stoviak
Counsel of Record
Patrick F. Nugent
Saul Ewing A rnstein
& Lehr LLP
Centre Square West
1500 Market Street,
38th Floor
Philadelphia, PA 19102
(215) 972-1095
john.stoviak@saul.com
A ndrew T. Bockis
Saul Ewing A rnstein
& Lehr LLP
Two North 2nd Street,
7th Floor
Harrisburg, PA 17101
Counsel for Petitioner
January 16, 2018
APPENDIX
1a
APPENDIX A — Appendix
OPINIONAOF THE UNITED
STATES COURT OF APPEALS FOR THE SECOND
CIRCUIT, DATED AUGUST 18, 2017
UNITED STATES COURT OF APPEALS
FOR THE SECOND CIRCUIT
November 16, 2016, Argued; August 18, 2017, Decided
Docket No. 16-1568
CONSTITUTION PIPELINE COMPANY, LLC,
Petitioner,
- v. NEW YORK STATE DEPARTMENT OF
ENVIRONMENTAL CONSERVATION;
BASIL SEGGOS, ACTING COMMISSIONER,
NEW YORK STATE DEPARTMENT OF
ENVIRONMENTAL CONSERVATION; JOHN
FERGUSON, CHIEF PERMIT ADMINISTRATOR,
NEW YORK STATE DEPARTMENT OF
ENVIRONMENTAL CONSERVATION,
Respondents,
STOP THE PIPELINE, CATSKILL
MOUNTAINKEEPER, INC., SIERRA CLUB,
RIVERKEEPER, INC.,
Intervenors.*
*
The Clerk of Court is directed to amend the official caption to
conform with the above.
2a
Appendix A
Before: kearSe, weSley, and droney, Circuit Judges.
Petition for review of respondents’ decision denying
application for certification pursuant to § 401 of the Clean
Water Act, 33 U.S.C. § 1341, that petitioner’s proposed
interstate natural gas pipeline would comply with New
York State water quality standards (“§ 401 certification”).
Respondents denied the application on the ground that
petitioner had not complied with requests for relevant
information. Petitioner contends (1) that respondents
exceeded the statutory time limitations for the State’s
review of the application and that they must therefore
be ordered to notify the United States Army Corps of
Engineers (“USACE”) that the State waives its right to
issue or deny § 401 certification, thereby allowing USACE
to issue a permit to petitioner under § 404 of the Clean
Water Act, see 33 U.S.C. § 1344(a); and (2) alternatively,
that respondents’ decision should be vacated on the ground
that the denial of the application was arbitrary, capricious,
and ultra vires, and that respondents should be ordered
to grant the requested § 401 certification. To the extent
that petitioner challenges the timeliness of respondents’
decision, we conclude that we lack jurisdiction over that
challenge. As to the merits, we conclude that respondents’
actions were within their statutory authority and that the
decision was not arbitrary or capricious.
Petition dismissed in part and denied in part.
3a
Appendix A
KEARSE, Circuit Judge:
Petitioner Constitution Pipeline Company, LLC
(“Constitution”), petitions pursuant to 15 U.S.C. § 717r(d)
(1) for review of an April 22, 2016 decision of the New
York State Department of Environmental Conservation
(“NYSDEC” or the “Department”) denying Constitution’s
application for certification pursuant to § 401 of the
Federal Water Pollution Control Act, more commonly
known as the Clean Water Act (or “CWA”), 33 U.S.C.
§ 1341 (“§ 401 certification”), that Constitution’s proposed
interstate natural gas pipeline would comply with New
York State (or “State”) water quality standards (or
“WQS”). NYSDEC denied the application on the ground
that Constitution had not provided sufficient information.
In its petition, Constitution contends principally (1) that
NYSDEC exceeded the § 401(a) time limitations for
the State’s review of the application and that NYSDEC
must therefore be ordered to notify the United States
Army Corps of Engineers (“USACE” or “Army Corps of
Engineers” or “Army Corps”) that the State has waived
its right to act upon Constitution’s § 401 certification
application, thereby allowing USACE to issue a permit
to petitioner under § 404 of the Clean Water Act, see 33
U.S.C. § 1344(a); and (2) alternatively, that Constitution
submitted sufficient information and that NYSDEC’s
decision should be vacated on the ground that its denial
of the application was arbitrary, capricious, and ultra
vires, and that NYSDEC should be ordered to grant
the requested § 401 certification. To the extent that
Constitution challenges the timeliness of the NYSDEC
decision, we dismiss the petition for lack of jurisdiction.
4a
Appendix A
As to the merits, we conclude that NYSDEC’s actions
were within its statutory authority and that its decision
was not arbitrary or capricious, and we deny the petition.
I. BACKGROUND
Constitution proposes to construct a 121-mile
interstate natural gas pipeline in Pennsylvania and New
York, approximately 98 miles of which would be in New
York. In connection with this project (the “Project”),
Constitution applied for, to the extent pertinent here, a
“certificate of public convenience and necessity” from the
Federal Energy Regulatory Commission (“FERC”), 15
U.S.C. § 717f(c), a CWA § 401 water quality certification
(or “WQC”) from New York State that the Project
would comply with State water quality standards (see 6
N.Y.C.R.R. parts 701 to 704), and a CWA § 404 permit
from the Army Corps of Engineers to allow discharges
into United States navigable waters.
A. Proceedings Before FERC
In September 2012, FERC announced that it would
prepare an environmental impact statement (“EIS”) for
Constitution’s Project and asked Constitution to submit a
feasibility study explaining how it would install the pipeline
across waterbodies (generally using that term to refer to
streams but not wetlands). For such installations, there
is a trenched method--a dry open-cut crossing--which
involves diverting a stream, digging a trench through
the banks and stream bed, installing and burying the
pipeline, and then allowing the stream to resume flowing
in the stream bed. (See, e.g., FERC Final Environmental
5a
Appendix A
Impact Statement (“FEIS”) pages 2-21 to 2-22.) There are
also trenchless crossing methods--including Horizontal
Directional Drill (or “HDD”), Direct Pipe (or “DP”), and
conventional bore--which involve digging pits on either
side of a waterbody and boring or drilling underneath the
stream. FERC asked Constitution to provide information
with regard to trenchless construction methods for
crossing several categories of streams, including those
classified by the states as sensitive or high quality and
those greater than 30 feet wide where a dry construction
method would not be feasible.
1.
Constitution’s Trenchless Feasibility Study
Constitution submitted to FERC a study discussing
trenchless crossing methods. (See Constitution,
Feasibility Study: Trenchless Construction Methods
for Sensitive Environmental Resource Crossings (Nov.
2013) (“Constitution 2013 Feasibility Study” or “Study”)
pages 1-3 to 1-5.) Trenchless methods do not disturb soil
or organisms in the stream banks, stream bed, or in the
stream itself, but require disturbing surrounding areas
to clear space for installation pits; there are also risks of
mid-project drill breakage, with leakage of drill fluid into
the waterbody. (See Constitution 2013 Feasibility Study
page 2-3; FEIS page 2-24.) Use of the trenched method
does not require as much installation space or present the
risk of drill failure; but it requires stream diversion and
digging into the stream bed and banks. (See, e.g., FEIS
pages 2-21 to 2-22.)
The Constitution feasibility study dealt principally
with locations where the waterbody was designated by
6a
Appendix A
New York or Pennsylvania as sensitive or high quality.
(See Constitution 2013 Feasibility Study pages 2-2 to 2-3.)
As a result, Constitution eliminated from consideration
for trenchless crossings all but 89 of the 251 New York
waterbodies that would be crossed by the pipeline or
affected by pipeline construction.
The remaining 89 locations were addressed in three
phases. The Study’s “Phase I[] Desktop Analysis” (id.
pt. 1.0 page 1-1) further reduced the number of New York
waterbodies considered by Constitution for trenchless
crossings from 89 to 26, in part by eliminating streams
less than 30 feet wide, even if they were classified by
New York as sensitive or high-quality (see id. pages 2-1,
2-3). Constitution stated that trenchless crossings for
such narrower waterbodies would potentially require
workspace requirements significantly greater than those
generally needed for a conventional dry crossing method.
(See id. page 2-3.) Thus, unless such a waterbody was
immediately associated with a larger wetland and/or
waterway complex crossed by the Project or was located
in the immediate vicinity of a proposed rail or roadway
crossing, “Constitution did not evaluate waterbody
crossings less than 30 feet in width” (id.).
Phase II was a “Cost/Time/Construction Workspace
Impact Analysis.” (Id. page 3-1; see also id. pt. 1.0 page 1-1
(“Trenchless construction methods are limited” not only by
such matters as “underlying geology, available workspace,
[and] available time,” but also by “available finances
budgeted for a capital project.”).) This phase eliminated
waterways from trenchless-crossing consideration largely
7a
Appendix A
on the basis of expense; as a result, there remained only 13
waterbody crossings in New York for which Constitution
planned to investigate a “formal trenchless construction
design.” (Id. pages 3-2 to 3-4 & tbl.3.2-1.) The Study stated
that Phase III, a “geotechnical field analysis” of each of the
13 locations, was in progress. (Id. page 5-1.) Constitution
thus planned to use the trenched method for 238 of the
251 New York waterbodies to be crossed.
2.
NYSDEC Comments and the FEIS
In connection with FERC’s announcement of a planned
EIS for the Constitution pipeline--and its subsequent draft
EIS (“DEIS”)--NYSDEC submitted numerous letters
to FERC. The first noted that NYSDEC’s preferred
method for crossing waterbodies is a trenchless method,
in particular
Horizontal Directional Drilling (HDD) because
it has the advantages of minimizing land
disturbance, avoiding the need for dewatering
of th e stream , l eav in g th e imm edi a t e
stream bed and banks intact, and reducing
erosion, sedimentation and Project-induced
watercourse instabilities.
(November 7, 2012 Letter from NYSDEC to FERC
at 3 (emphasis added).) Stating that the DEIS should
identify the New York classification of each stream the
proposed pipeline would cross, NYSDEC urged FERC to
“evaluate cases where other methods are proposed” and
have Constitution “explain why HDD will not work or is
8a
Appendix A
not practical for that specific crossing.” (Id. (emphasis
added).)
A May 2013 letter again stated that “NYSDEC’s
preferred methodology for all stream crossings is . . .
(HDD)”; that letter also stated that “[w]ithin stream
crossings, pipelines should be buried at least 6' below a
stream bottom. Minimum cover depth is not subject to
variance based on field conditions.” (May 28, 2013 Letter
from NYSDEC to FERC (“NYSDEC May 2013 Letter”)
at 1-2 (emphasis added).)
In September 2013, NYSDEC wrote to join a request
by the Army Corps for additional analysis of whether
the Constitution pipeline could be routed along a certain
interstate highway, a route referred to as “Alternative
M.” (September 25, 2013 Letter from NYSDEC to FERC
at 1.) Constitution responded by arguing that Alternative
M would have greater environmental impact than
Constitution’s proposed route and noting likely difficulties
in obtaining highway agencies’ approvals. (See October
22, 2013 Letter from Constitution to NYSDEC at 2-4.)
In 2014, FERC issued its DEIS, which drew criticism
from several sources including NYSDEC. (See, e.g.,
March 24, 2014 Letter from NYSDEC to FERC and
Army Corps at 1-2 (urging a revised DEIS to include
“geotechnical feasibility studies for all trenchless crossing
locations,” as well as “site specific blasting plans that
include protocols for in-water blasting and the protection
of aquatic resources and habitats” (emphasis added));
April 7, 2014 Letter from NYSDEC to FERC and Army
9a
Appendix A
Corps (“NYSDEC April 2014 Letter”) at 1-5 (adding
additional comments and requesting additional analysis
of Alternative M which, in NYSDEC’s view, would reduce
the amount of disturbance of higher-quality waterbodies).)
FERC issued its FEIS in 2014 without significantly
expanding on several aspects of the DEIS. It did not
address NYSDEC’s concern that Constitution had not
developed site-specific blasting plans. (See FEIS pages
4-15 to 4-16; DEIS page 4-16.) The FEIS added discussion
of two new versions of Alternative M proposed by NYSDEC
(see FEIS pages 3-46 to 3-47), but rejected them without
analyzing disturbances to high-quality waterbodies
(compare id. pages 3-32 to 3-47 with NYSDEC April
2014 Letter at 3-4). And the FEIS stated that the pipeline
would be buried 60 inches below streams in normal soil
conditions and 24 inches in areas of “consolidated rock”
(FEIS page 2-16), as contrasted with the NYSDEC May
2013 Letter’s statement that the pipe needed to be buried
“at least 6' below a stream bottom” (NYSDEC May 2013
Letter at 2).
The FEIS expanded on the DEIS’s waterbody
crossing information but repeated DEIS explanations
for why relatively few crossings were slated to be
crossed by trenchless techniques, stating, inter alia, that
“[a]ccording to Constitution, trenchless crossing methods
are not practical [except in limited circumstances] for
waterbody crossings less than 30 feet in width” and that
“Constitution indicated that such crossings would be
impractical due to minimum length requirements, depth
of pipeline considerations, and workspace requirements,”
10a
Appendix A
and describing the areas that would be required for
trenchless crossing “[a]ccording to Constitution” (FEIS
page 4-50). The FEIS stated that
[t]he potential impacts on waterbodies
associated with the use of conventional bore
or Direct Pipe trenchless crossing methods
are considered minimal when compared to
other crossing methods. The waterbody and
its banks, and typically the entire immediate
riparian zone, would not be disturbed by
clearing or trenching; rather, the pipe would
be installed below the feature.
(Id. page 4-56 (emphasis added).) FERC added:
We concur with Constitution’s assessment that
it is not practicable to use trenchless crossing
methods where waterbodies were listed as
ephemeral or intermittent (because these
waterbodies are likely to be dry at the time of
crossing) or for waterbodies less than 30 feet
in width (as extra workspaces needed would
offset potential benefits). . . .
(FEIS, App’x S, page S-52 (emphases added).) The FEIS
noted that Constitution had completed geotechnical
feasibility studies at only two New York sites. (See FEIS
page 4-4.)
11a
Appendix A
B. Proceedings Before NYSDEC
While its application to FERC for a certificate of public
convenience and necessity was pending, Constitution
submitted an application to the Army Corps for a CWA
§ 404 permit for the discharge of dredged or fill material
while constructing the pipeline and to NYSDEC for a
CWA § 401 certification that the Project would comply
with State water quality standards. In December 2014,
NYSDEC issued a notice that Constitution’s application
was complete; but on December 31, it asked Constitution
for more information about stream crossings. In JanuaryMarch 2015, Constitution submitted more information
to NYSDEC, and on April 27, 2015, at NYSDEC’s
request, Constitution withdrew and resubmitted its
§ 401 application. (Constitution had also withdrawn and
resubmitted its § 401 application at NYSDEC’s request
in May 2014.)
1.
Stream-Crossing Information Requests by
NYSDEC
On January 23, 2015, staff from Constitution and
NYSDEC met to discuss trenchless stream-crossing
methods (see January 14, 2015 email from NYSDEC
Project Manager Stephen M. Tomasik to Constitution
engineering consultant Keith Silliman; January 27, 2015
email from Tomasik to Constitution Environmental
Project Mananger Lynda Schubring (“NYSDEC January
27, 2015 email”)). Prior to that meeting, Constitution wrote
to NYSDEC stating that it had
12a
Appendix A
conducted subsurface geotechnical
investigations at the majority of the proposed . . .
(HDD) and . . . (DP) trenchless locations. Results
of the subsurface geotechnical investigations
revealed crossing locations that present a high
risk of failure if a trenchless method is used.
As a result, trenchless crossing locations with
a high risk of failure are not feasible and have
been modified to a dry open cut design. Since
the last . . . submissions to the USACE, three (3)
HDD or DP locations affecting six (6) wetlands
or waterbodies have changed to an open cut
construction method . . . .
(January 22, 2015 Letter from Schubring to Tomasik
at 1.) Constitution also stated that six other originally
proposed trenchless crossings would be crossed by a
trenched method, “to address various concerns raised
by [state and local] authorities relative to the trenchless
crossings of specific public roadways and associated
infrastructure.” (Id . at 2.) A fter the January 23
meeting, NYSDEC requested additional documents that
Constitution personnel had said informed its decision to
use the trenched crossing method at two locations, as well
as “information about stream crossings that we requested
on 12/31/2014.” (NYSDEC January 27, 2015 email).
In response, Constitution submitted feasibility
evaluations based on geotechnical studies for four
locations: two wetlands crossings and two waterbody
crossings. One of the waterbody feasibility evaluations
concluded that using either HDD or DP was infeasible due
13a
Appendix A
to subsurface soil conditions; the other did not address
the feasibility of trenchless crossing methods, and instead
discussed only a contingency open-cut crossing to be used
if the proposed DP crossing failed.
In Febr uar y 2015, Constitution submitted to
NYSDEC a document titled “Draft Trenchless Feasibility
Study Edits” (“Constitution 2015 Feasibility Draft”) that
appears to be a version of part of the 2013 trenchless
feasibility study that Constitution had submitted to FERC,
merely expanding on the manner in which each trenchless
method operates. Again there was no discussion of stream
crossings site-by-site. The Constitution 2015 Feasibility
Draft stated that
Constitution recognizes that, in general,
performing . . . (HDD) for streams less than 30
feet in width causes greater net environmental
impacts than a dry open cut method and this
threshold is an industry recognized standard.
Constitution has not identified any NYSDEC
regulation, formally adopted policy or guidance
document that would warrant deviating from
this standard.
(Id. at 1 (emphases added).) It also discussed the Direct
Pipe method, stating that “it is likely that additional
forest will require clearing to perform DP for most of the
protected stream crossings,” and that “[m]any” streams
are in valleys whose slopes make the DP method infeasible.
(Id. at 2-3 (emphases added).) In addition, the Constitution
2015 Feasibility Draft stated that DP technology is of
14a
Appendix A
“limited availability,” leading Constitution to conclude that
using “DP technology for . . . streams less than 30 feet
in width is not a realistic or viable expectation within a
reasonable period of time.” (Id. at 3 (emphasis added).)
In March 2015, NYSDEC sent Constitution a list of
20 waterbody locations that NYSDEC “wants crossed
via HDD,” stating that NYSDEC “is still expecting
an evaluation as to whether an HDD is technically
feasible for each of these streams.” (March 17, 2015 email
from NYSDEC Major Project Management Unit Chief
Christopher M. Hogan to Silliman (emphasis added).) In
April 2015, as indicated above, Constitution withdrew and
resubmitted its § 401 WQC request.
2.
Subsequent Discussions
In May 2015, NYSDEC noted that it had agreed to
“eliminate” four streams from “further consideration for
trenchless crossing methods.” (May 22, 2015 email from
Tomasik to Schubring, Silliman, et al.)
In July 2015, a member of NYSDEC’s staff emailed
to certain Army Corps staff members a “Confidential”
message attaching a “VERY PRELIMINARY version
of a Constitution permit” (July 20, 2015 email from
Tomasik to Kevin J. Bruce et al., Army Corps), which
included a table of 19 locations that “shall be crossed
using a trenchless construction method”--unless an
“experienced and qualified engineer” concludes that
the techniques are “not constructible or not feasible”
(Confidential Draft NYSDEC Certification Conditions
15a
Appendix A
at 17). The draft, however, required Constitution,
“[p]rior to beginning construction of any trenchless
stream crossing,” to “submit a[] . . . ‘Trenchless Crossing
Plan’ for each trenchless stream crossing,” including
“detailed engineering plans” for each location. (Id. at 18
(emphases added).)
In September 2015, Constitution submitted to
N YSDEC an Env i ronmental Constr uction Plan,
attached to which was a Blasting Plan. (See Constitution,
Environmental Construction Plan 50 (Aug. 2015).) This
plan listed 253 “[a]reas of shallow depth to bedrock
crossed by the [pipeline]” in New York, but stated that
“[a] final determination on the need for blasting will be
made at the time of construction.” (Constitution, Blasting
Plan (Aug. 2015) (“Blasting Plan”) pages 1-1, 1-2 & tbl.1.22, 4-1.) The Blasting Plan identified regulations and a
permit that would govern blasting in Pennsylvania, but
stated that “[a]ll blasting operations in New York will
be conducted in accordance with an in-stream b[l]asting
protocol to be prepared by Constitution.” (Id. page 4-1
(emphasis added).)
C. NYSDEC’s Decision Denying § 401 Certification
In a 14-page letter to Constitution dated April 22,
2016, NYSDEC denied Constitution’s application for CWA
§ 401 certification (“NYSDEC Decision” or “Decision”),
stating that “the Application fails in a meaningful way to
address the significant water resource impacts that could
occur from this Project and has failed to provide sufficient
information to demonstrate compliance with New York
16a
Appendix A
State water quality standards,” NYSDEC Decision at 1.
Although also noting the lack of adequate information as
to such issues as the feasibility of the Alternative M route,
blasting information, pipe burial depth, and wetlands
crossings, see, e.g., id. at 11-14, the Decision focused
principally on Constitution’s failure to provide information
with respect to stream crossings.
NYSDEC noted that Constitution’s Project “would
disturb a total of 251 streams . . . , 87 of which support
trout or trout spawning,” and that “[c]umulatively,
construction would disturb a total of 3,161 linear feet
of streams and result in a combined total of 5.09 acres
of temporary stream disturbance impacts.” NYSDEC
Decision at 8. It stated that although
[f]rom inception of its review of the Application,
NYSDEC directed Constitution to demonstrate
compliance with State water quality standards
and required site-specific information for each
of the 251 streams impacted by the Project
[, and] NYSDEC informed Constitution that
all 251 stream crossings must be evaluated
for environmental impacts and that trenchless
technology was the preferred method for
stream crossing[, and that t]his information
was conveyed to Constitution and FERC on
numerous occasions since November 2012[,]
. . . Constitution has not supplied the Department
with the necessary information for decision
making.
Id. (emphasis in original).
17a
Appendix A
The Decision stated that because some form of
trenchless technology is the “most protective method for
stream crossings,”
NYSDEC directed Constitution to determine
whet he r a t r enc h le s s t e c h nolog y w a s
constructible for each stream crossing. On a
number of occasions NYSDEC identified the
need to provide information so that it could
evaluate trenchless stream installation methods
(see Table 2, below); however, Constitution has
not provided sufficient information . . . .
Id. (footnote omitted) (emphasis added).
Table 2 in the Decision principally chronicled
NYSDEC’s requests of Constitution--both directly
and indirectly in its submissions to FERC--and noted
Constitution’s resistance, including the following:
• In June 2012, “NYSDEC stated in a letter to
Constitution that for protected streams and
wetlands, trenchless technology is the preferred
method for crossing and should be considered for
all such crossings (emphasis added).”
• On November 7, 2012, “[i]n comments to FERC,
NYSDEC stated that for streams and wetlands
the preferred method for crossing is trenchless
technology,” and that as to each crossing where
another method is proposed “Constitution should
explain why trenchless crossing technology
18a
Appendix A
will not work or is not practical for that specific
crossing.”
• On April 9, 2013, “FERC[] . . . directed Constitution
to address all of the comments filed in the public
record by other agencies . . . including all
comments from the NYSDEC.”
• On May 28, 2013, at a “[m]eeting” of “Constitution
and NYSDEC staff . . . NYSDEC reiterate[d]
that acceptable trenchless technology was the
preferred installation method and that stream
crossings should be reviewed for feasibility of
using those technologies.”
• In July and August 2013, on “[f]ield visits of
proposed stream crossings prior to permit
applications to the Department[, a]t each crossing,
NYSDEC emphasized to Constitution staff
that trenchless technology is preferred/most
protective.”
• In its November 2013 Trenchless Feasibility
Study, Constitution “arbitrarily eliminated
from any consideration for trenchless crossing
methods” “all streams less than 30' wide.”
• On December 31, 2014, at a meeting w ith
Constitution staff, “NYSDEC indicated that the
Trenchless Feasibility Study was inadequate, e.g.
provided insufficient justification and removed all
streams less than 30 feet in width from analysis.”
19a
Appendix A
NYSDEC gave Constitution “an informational
request table including required technical
information.”
• On January 13, 2015, an “Army Corps of Engineers
letter reiterate[d] a request for a feasibility
analysis of trenchless crossings.”
• At a January 23, 2015 “[m]eeting between
Constitution and NYSDEC staff . . . Constitution
s t at e d it wa s u n a ble t o c omplet e t he
[informational request] table [it received from
NYSDEC] on December 31, 2014[]. NYSDEC staff
indicated that the justification for stream crossing
methods was insufficient and that appropriate site
specific information must be provided.”
• In a January 28, 2015 “[c]onference call[,] NYSDEC
reiterated its request for a site specific analysis
of trenchless stream crossings for all streams
including those under 30 feet wide.”
• On February 5, 2015, “Constitution provided an
updated example of a trenchless feasibility study
but that example continued to exclude streams
up to 30 feet wide from analysis and did not
provide detailed information of the majority of
streams.”
NYSDEC Decision at 9-10 (emphases added).
Although the Decision’s Table 2 ended with the
February 2015 entry, the Decision noted that Constitution’s
20a
Appendix A
“unwillingness to provide a complete and thorough[]
Trenchless Feasibility Study” persisted:
[I]n May 2015, Constitution provided detailed
project plans for 25 potential trenchless
crossings, but only two of those plans were
based on full geotechnical borings that are
necessary to evaluate the potential success
of a trenchless design. Detailed project plans
including full geotechnical borings for the
remaining stream crossings have not been
provided to the Department.
Id. at 11 (emphasis added). The NYSDEC Decision stated
that
[d]ue to the lack of detailed project plans,
including geotechnical borings, the Department
has determined to deny Constitution’s WQC
Application because the supporting materials
supplied by Constitution do not provide
sufficient information for each stream crossing
to demonstrate compliance with applicable
narrative water quality standards for turbidity
and preservation of best usages of affected
water bodies. Specifically, the Application lacks
sufficient information to demonstrate that
the Project will result in no increase that will
cause a substantial visible contrast to natural
conditions.10
Furthermore, the Application remains deficient
in that it does not contain sufficient information
21a
Appendix A
to demonstrate compliance with 6 NYCRR Part
701 setting forth conditions applying to best
usages of all water classifications. Specifically,
“the discharge of sewage, industrial waste or
other wastes shall not cause impairment of the
best usages of the receiving water as specified
by the water classifications at the location of
the discharge and at other locations that may
be affected by such discharge.”11
10
6 NYCRR § 703.2.
11
6 NYCRR § 701.1.
NYSDEC Decision at 12 & nn.10-11. The Decision added
that
[c]umulatively, impacts to both small and large
streams from the construction and operation of
the Project can be profound and include loss of
available habitat, changes in thermal conditions,
increased erosion, creation of stream instability
and turbidity, impairment of best usages, as
well as watershed-wide impacts resulting from
placement of the pipeline across water bodies in
remote and rural areas (See Project Description
and Environmental Impacts Section, above).
Because the Department’s review concludes
that Constitution did not provide sufficient
detailed information including site specific
project plans regarding stream crossings
(e.g. geotechnical borings) the Department
22a
Appendix A
has determined to deny Constitution’s WQC
Application for failure to provide reasonable
assurance that each stream crossing will be
conducted in compliance with 6 NYCRR §608.9.
NYSDEC Decision at 12; see 6 N.Y.C.R.R. § 608.9(a)
(2) (“The applicant” for a CWA § 401 certification “must
demonstrate compliance with sections 301-303, 306
and 307 of the Federal Water Pollution Control Act, as
implemented by . . . water quality standards and thermal
discharge criteria set forth in Parts 701, 702, 703 and 704
of this Title . . . .”).
II. DISCUSSION
In its petition for review (or “Petition”), Constitution
contends principally (1) that NYSDEC failed to issue
its Decision within a reasonable time as required by
§ 401 and thus must be required to inform USACE that
NYSDEC has waived its right to rule on Constitution’s
application for a WQC, thereby enabling the Army Corps
to grant Constitution a permit for its pipeline Project, or
(2) alternatively, that Constitution submitted sufficient
information and that NYSDEC’s decision should be
vacated on the ground that its denial of the application
was arbitrary, capricious, and ultra vires, and that
NYSDEC should be ordered to grant the requested § 401
certification. For the reasons that follow, we (1) conclude
that Constitution’s first contention, which would have
us treat NYSDEC’s Decision as an act that is void, lies
beyond the jurisdiction of this Court, and (2) conclude
that NYSDEC’s Decision was not ultra vires, arbitrary,
or capricious.
23a
Appendix A
A. Constitution’s Argument that NYSDEC Waived Its
§ 401 Authority
The Natural Gas Act (or “NGA”), 15 U.S.C. §§ 717717z, sets out provisions with respect to, inter alia, the
construction of transportation facilities for natural gas,
see id. § 717f. Such projects are also subject to restrictions
under other federal statutes, including provisions of the
Clean Water Act, see, e.g., id. § 717b(d)(3). Section 401 of
the CWA requires an applicant for a federal permit to
conduct any activity that “may result in any discharge
into the navigable waters” of the United States to obtain
“a certification from the State in which the discharge . . .
will originate . . . that any such discharge will comply
with,” inter alia, the state’s water quality standards. 33
U.S.C. § 1341(a)(1).
As to petitions for review relating to such applications,
§ 717r of the NGA divides jurisdiction between the Circuit
in which the facility is proposed to be constructed and
the United States Court of Appeals for the District of
Columbia Circuit. It states, in pertinent part, as follows:
(1) In general
The United States Court of Appeals for the
circuit in which a facility subject to . . . section
717f of this title is proposed to be constructed . . .
shall have original and exclusive jurisdiction
over any civil action for the review of an order
or action of a Federal agency (other than
[FERC]) or State administrative agency acting
24a
Appendix A
pursuant to Federal law to issue, condition,
or deny any permit, license, concurrence, or
approval (hereinafter collectively referred to
as “permit”) required under Federal law . . . .
(2) Agency delay
The United States Court of Appeals for the
District of Columbia shall have original and
exclusive jurisdiction over any civil action
for the review of an alleged failure to act by a
Federal agency (other than [FERC]) or State
administrative agency acting pursuant to
Federal law to issue, condition, or deny any
permit required under Federal law . . . .
15 U.S.C. §§ 717r(d)(1)-(2) (emphases added). We regard
subsection (2)--titled “Agency delay”--as encompassing
not only “an alleged failure to act” but also an allegation
that a failure to act within a mandated time period
should be treated as a failure to act. This is the nature of
Constitution’s first argument.
Constitution points out that CWA § 401 provides that
“[i]f” a “State . . . agency” from which an applicant for
a federal permit has sought a water quality certification
“fails or refuses to act on [the] request for certification,
within a reasonable period of time (which shall not
exceed one year) after receipt of such request, the
certification requirements of this subsection shall be
waived with respect to such Federal application.” 33 U.S.C.
§ 1341(a)(1). Constitution argues that NYSDEC did not
25a
Appendix A
issue its Decision until 32 months after Constitution
submitted its initial application, 16 months after NYSDEC
issued notice that that initial application was complete,
15 months after the deadline imposed by FERC, nearly
a year (“359 days”) after Constitution’s 2015 withdrawaland-resubmission of its application--and eight months
after Constitution claims it was advised by NYSDEC that
NYSDEC “had everything it needed to issue a Section 401
Certification.” (Constitution brief in support of Petition
at 28-29.) Constitution argues that NYSDEC “waived its
right” to rule on the certification application and must be
required to so notify the Army Corps. (Id. at 37.)
We note first that there is nothing in the administrative
record to show that NYSDEC received the information
it had consistently and explicitly requested over the
course of several years--much less anything to support
Constitution’s claim that NYSDEC said “it had” all of
the information it required “to issue” the requested
certification (id. at 29). Although Constitution proffered
in this Court non-record declarations from certain of its
personnel, those “outside-the-record declarations and
associated portions of [Constitution]’s brief” were stricken.
Constitution Pipeline Co., LLC v. Seggos, No. 16-1568,
2016 U.S. App. LEXIS 23831 (2d Cir. Oct. 3, 2016).
Second, Constitution’s “waive[r]” argument is that the
NYSDEC Decision must be treated as a nullity by reason
of NYSDEC’s “failing to act within the prescribed time
period under the CWA” (Constitution brief in support of
Petition at 37 (emphasis added)). Such a failure-to-act
claim is one over which the District of Columbia Circuit
would have “exclusive” jurisdiction, 15 U.S.C. § 717r(d)
26a
Appendix A
(2). See generally Weaver’s Cove Energy, LLC v. Rhode
Island Department of Environmental Management,
524 F.3d 1330, 1332, 381 U.S. App. D.C. 17 (D.C. Cir.
2008). Accordingly, we dismiss Constitution’s timeliness
argument for lack of jurisdiction.
B. Constitution’s Challenge to the Merits of NYSDEC’s
Decision
Judicial review of an administrative agency’s denial
of a CWA § 401 certificate is limited to grounds set forth
in the Administrative Procedure Act, 5 U.S.C. §§ 701-706.
We review the agency’s interpretation of federal law de
novo; if the agency correctly interpreted federal law, we
review its factual determinations under the arbitraryand-capricious standard, see id. § 706(2)(A); Islander
East Pipeline Co. v. McCarthy, 525 F.3d 141, 150 (2d Cir.
2008) (“Islander East II”); Islander East Pipeline Co. v.
Connecticut Department of Environmental Protection,
482 F.3d 79, 94 (2d Cir. 2006) (“Islander East I”).
1.
Federal Law
Constitution argues that as a matter of law, NYSDEC’s
“jurisdiction to review”--and “in effect, veto”--FERC
determinations is preempted by FERC’s performance of
its obligations under the National Environmental Policy
Act (“NEPA”), 42 U.S.C. §§ 4321-4370h, to prepare a DEIS
and a FEIS. (Constitution brief in support of Petition at 37,
39.) We disagree that NYSDEC’s action was preempted.
Although NEPA requires federal-agency review of
virtually any possible environmental effect that a proposed
27a
Appendix A
action may have, see generally 40 C.F.R. § 1502.16, it
does not impose substantive standards. See Robertson
v. Methow Valley Citizens Council, 490 U.S. 332, 350,
109 S. Ct. 1835, 104 L. Ed. 2d 351 (1989). “[T]hrough a
set of action-forcing procedures,” NEPA “require[s] that
agencies take a hard look at environmental consequences,”
but it is “well settled that NEPA itself does not mandate
particular results[; it] simply prescribes the necessary
process.” Id. (internal quotation marks omitted). Thus,
NEPA states, in pertinent part, that “[n]othing in section
4332 or 4333 of this title shall in any way affect the specific
statutory obligations of any Federal agency . . . to act, or
refrain from acting contingent upon the recommendations
or certification of any . . . State agency.” 42 U.S.C. § 4334.
We note also that while the Natural Gas Act generally
preempts state laws, it states that “[e]xcept as specifically
provided[,] . . . nothing” in the NGA “affects the rights
of States under . . . the [CWA] (33 U.S.C. § 1251 et seq.),”
15 U.S.C. § 717b(d). CWA § 511, in turn, preserves the
states’ authority to determine issues of a planned project’s
effect on water quality. See 33 U.S.C. § 1371(c)(2)(A). CWA
§ 401(a)(1) requires that an entity such as Constitution,
proposing to construct an interstate pipeline, obtain
from each state in which the pipeline is to be constructed
a certification that “any . . . discharge” from a proposed
activity “will comply with the applicable provisions of
[33 U.S.C. §§] 1311, 1312, 1313, 1316, and 1317.” 33 U.S.C.
§ 1341(a)(1). Sections 1311, 1312, 1316, and 1317 establish,
and allow the Environmental Protection Agency (“EPA”)
to establish, standards governing numerous aspects of
water quality; and § 1313 allows states to develop their
own water quality standards and submit them to the EPA
28a
Appendix A
for approval. If the EPA approves a state’s water quality
standards, it publishes a notice of approval and they
become the state’s EPA-approved standards, regulating
water quality in that state. See 33 U.S.C. §§ 1313(a), (c).
The New York State water quality standards, approved
by the EPA, see generally 42 Fed. Reg. 56,786, 56,790 (Oct.
28, 1977), are found in 6 N.Y.C.R.R. parts 701 to 704, and
were invoked by the NYSDEC Decision, which stated that
“[d]enial of a WQC may occur when an application fails to
contain sufficient information to determine whether the
application demonstrates compliance with the above stated
State water quality standards and other applicable State
statutes and regulations due to insufficient information.”
NYSDEC Decision at 7; see also id. at 12 nn.10-11 and
accompanying text (quoted in Part I.C. above). The State
standards classify waterbodies in terms of, inter alia,
potability and their suitability for various activities such
as swimming and fishing, see 6 N.Y.C.R.R. pt. 701; they
set standards for characteristics such as water odor, color,
and turbidity, see id. pt. 703; and they regulate thermal
discharges into waterbodies, see id. pt. 704.
Thus, the relevant federal statutes entitled NYSDEC
to conduct its own review of the Constitution Project’s
likely effects on New York waterbodies and whether
those effects would comply with the State’s water quality
standards.
CWA § 401(a)(1), as pertinent here, states that “[n]o
license or permit shall be granted if [a § 401] certification
has been denied by the State,” 33 U.S.C. § 1341(a)(1).
Thus, we have indeed referred to § 401 as “a statutory
29a
Appendix A
scheme whereby a single state agency effectively vetoes
an energy pipeline that has secured approval from a host
of other federal and state agencies.” Islander East II, 525
F.3d at 164 (emphases added); accord Keating v. FERC,
927 F.2d 616, 622, 288 U.S. App. D.C. 344 (D.C. Cir. 1991)
(“Through [the § 401 certification] requirement, Congress
intended that the states would retain the power to block,
for environmental reasons, local water projects that
might otherwise win federal approval.” (emphasis added)).
Constitution also argues that NYSDEC’s demands
for information with regard to, e.g., possible alternative
routes for the planned pipeline (see, e.g., NYSDEC
Decision at 3 (NYSDEC “asked Constitution to analyze
alternative routes that could have avoided or minimized
impacts to an extensive group of water resources”)), as
well as Constitution’s planned blasting sites and the depth
at which the pipe would be buried, exceeded NYSDEC’s
authority (Constitution brief in support of Petition at 38).
We need not address all of these contentions. A state’s
consideration of a possible alternative route that would
result in less substantial impact on its waterbodies is
plainly within the state’s authority. See, e.g., Islander
East II, 525 F.3d at 151-52. And where an agency decision
is sufficiently supported by even as little as a single
cognizable rationale, that rationale, “by itself, warrants
our denial of [a] petition” for review under the arbitraryand-capricious standard of review. See, e.g., id. at 158.
30a
Appendix A
2.
Application of the Arbitrary-and-Capricious
Standard
Under the arbitrary-and-capricious standard, “[a]
reviewing court may not itself weigh the evidence or
substitute its judgment for that of the agency.” Islander
East II, 525 F.3d at 150. “Rather,” we “consider[] whether
the agency ‘relied on factors which Congress has not
intended it to consider, entirely failed to consider an
important aspect of the problem, offered an explanation
for its decision that runs counter to the evidence before the
agency, or is so implausible that it could not be ascribed to
a difference in view or the product of agency expertise.’”
Id. at 150-51 (quoting Motor Vehicle Manufacturers
Ass’n of the United States, Inc. v. State Farm Mutual
Automobile Insurance Co., 463 U.S. 29, 43, 103 S. Ct.
2856, 77 L. Ed. 2d 443 (1983) (“State Farm”)).
[W]ithin the prescribed narrow sphere, judicial
inquiry must be searching and careful. . . .
Notably, a court must be satisfied from the
record that the agency . . . examine[d] the
relevant data and articulate[d] a satisfactory
explanation for its action. . . . Further, the
agency’s decision must reveal a rational
connection between the facts found and the
choice made.
Islander East II, 525 F.3d at 151 (internal quotation marks
omitted). If there is “sufficient evidence in the record
to provide rational support for the choice made by the
agency,” we must uphold its decision. Id. at 152.
31a
Appendix A
Usually, the agency’s choice concerns whether
the applicant’s submission of the relevant information
warrants the granting of the application. In the present
case, as summarized in Part I.C. above, NYSDEC denied
Constitution’s application because Constitution refused
to provide information that NYSDEC had repeatedly
requested with regard to, inter alia, issues such as
those just discussed in Part II.B.1. above, and issues as
to the feasibility, site-by-site, of trenchless methods for
most of the 251 stream crossings planned in New York.
Constitution does not contend that those requests were not
made. Indeed, in its own brief in this Court, Constitution
acknowledges that the NYSDEC Decision (the “Denial”)
explained that NYSDEC had requested but had not
received sufficient information with regard to:
♦ construction methods and site-specific project
plans for stream crossings (Denial at 8-11 . . . );
♦ alternative routes (Id. at 11 . . . );
♦ pipeline burial depth in stream beds (Id. at
12-13 . . . );
♦ procedures and safety measures Constitution
would follow in the event that blasting is
required (Id. at 13 . . . );
♦ Constitution’s plans to avoid, minimize, or
mitigate discharges to navigable waters and
wetlands (Id. at 13-14 . . . ); and
♦ cumulative impacts (Id. at 3, 5, 7, 14 . . . ).
32a
Appendix A
(Constitution brief in support of Petition at 21-22.)
Nowhere does Constitution claim to have provided the
above categories of information; rather, it insists that it
provided NYSDEC with “sufficient” information (id. at 5262) because use of trenchless crossing methods for streams
less than 30 feet wide is not “an industry recognized
standard” (Constitution 2015 Feasibility Draft at 1).
However, in order to show that an agency’s decision-or its request for additional information as to alternative
methods--is arbitrary and capricious, “it is not enough that
the regulated industry has eschewed a given [technology].”
State Farm, 463 U.S. at 49. Industry preferences do not
circumscribe environmental relevance.
In Marsh v. Oregon Natural Resources Council, 490
U.S. 360, 109 S. Ct. 1851, 104 L. Ed. 2d 377 (1989), the
Supreme Court considered whether a federal agency,
presented with new evidence, should have been required to
file a new supplemental environmental impact statement;
the Court stated that the matter of whether additional
information is “significant” is “a classic example of
a factual dispute the resolution of which implicates
substantial agency expertise,” as to which the courts
“must defer to the informed discretion of the responsible
. . . agencies,” id. at 376-77 (internal quotation marks
omitted). We cannot conclude that any less deference is
due an agency’s determination that it should not grant a
permit application where it has already determined that
additional information is needed, and the applicant refuses
to supply it. Cf. University of Iowa Hospitals & Clinics v.
Shalala, 180 F.3d 943, 955 (8th Cir. 1999) (where agency
33a
Appendix A
regulations required substantiation of costs for which
reimbursement was sought, denial of reimbursement
based on inadequate documentation was not arbitrary
and capricious); Mendoza v. Secretary, DHS, 851 F.3d
1348, 1356 (11th Cir. 2017) (denial of visa application
where applicants declined to answer relevant questions
relating to eligibility was not arbitrary and capricious; the
applicants “were free to refuse to answer [the agency’s]
questions . . . but they did so at their own peril”).
Indeed, an agency’s decision may be found “arbitrary
and capricious” for “issuing a permit with insufficient
information.” Utahns For Better Transportation v. United
States Department of Transportation, 305 F.3d 1152, 1192
(10th Cir. 2002) (emphasis added).
Here, the record amply shows, inter alia, that
Constitution persistently refused to provide information
as to possible alternative routes for its proposed pipeline
or site-by-site information as to the feasibility of trenchless
crossing methods for streams less than 30 feet wide--i.e.,
for the vast majority of the 251 New York waterbodies to be
crossed by its pipeline--and that it provided geotechnical
data for only two of the waterbodies.
In sum, NYSDEC is responsible for evaluating the
environmental impacts of a proposed pipeline on New York
waterbodies in light of the State’s water quality standards.
Applying the arbitrary-and-capricious standard of review,
we defer to NYSDEC’s expertise as to the significance
of the information requested from Constitution, given
the record evidence supporting the relevance of that
information to NYSDEC’s certification determination.
34a
Appendix A
We conclude that the denial of the § 401 certification after
Constitution refused to provide relevant information,
despite repeated NYSDEC requests, was not arbitrary
or capricious.
CONCLUSION
We have considered all of Constitution’s arguments
and have found in them no basis for granting the petition
for review. Insofar as the petition contends that the
NYSDEC Decision is a nullity on the ground that it was
untimely, the petition is dismissed for lack of jurisdiction;
to the extent that the petition challenges the NYSDEC
Decision on the merits, the petition is denied.
35a
B YORK STATE
APPENDIX B —Appendix
THE NEW
DEPARTMENT OF ENVIRONMENTAL
CONSERVATION’S APRIL 22, 2016 DENIAL
OF CONSTITUTION PIPELINE COMPANY,
LLC’S APPLICATION FOR A WATER QUALITY
CERTIFICATION UNDER SECTION 401 OF THE
CLEAN WATER ACT FOR THE CONSTITUTION
PIPELINE PROJECT
NEW YORK STATE DEPARTMENT OF
ENVIRONMENTAL CONSERVATION
Division of Environmental Permits & Pollution Prevention
625 Broadway, 4th Floor, Albany, New York 12233-1750
P: (518) 402-9167 | F: (518) 402-9168
deppermitting@dec.ny.gov
www.dec.ny.gov
April 22, 2016
Lynda Schubring, PMP
Environmental Project Manager
Constitution Pipeline Company, LLC
2800 Post Oak Boulevard
P.O. Box 1396
Houston, Texas 77251-1396
Re: Joint Application: DEC Permit # 0 -9999 00181/00024 Water Quality Certification/Notice of Denial
Dear Ms. Schubring,
On April 27, 2015, Constitution Pipeline Company, LLC
(Constitution) submitted to the New York State Department
of Environmental Conservation (NYSDEC or Department)
36a
Appendix B
a Joint Application (Application)1 to obtain a Clean Water
Act2 Section 401 Water Quality Certification (WQC) for
the proposed Project and New York State Environmental
Conservation law (ECL) Article 15, Title 5 (Protection
of Waters) and Article 24, Title 23 Freshwater Wetlands
permits. Based on a thorough evaluation of the Application
as well as supplemental submissions, the Department hereby
provides notice to Constitution that in accordance with Title
6 New York Codes Rules and Regulation (NYCRR) Part
621, the Application fails in a meaningful way to address the
significant water resource impacts that could occur from
this Project and has failed to provide sufficient information
to demonstrate compliance with New York State water
quality standards. Constitution’s failure to adequately
address these concerns limited the Department’s ability
to assess the impacts and conclude that the Project will
comply water quality standards. Accordingly, Constitution’s
request for a WQC is denied.3 As required by 6 NYCRR
§621.10, a statement of the NYSDEC’s rationale for denial
is provided below.
1. New York State and U.S. Army Corps of Engineers Joint
Application, Constitution Pipeline, August, 2013. Constitution
initially submitted its WQC application on August 28, 2013. With
the Department’s concurrence Constitution subsequently withdrew
and re-submitted the WQC application on May 9, 2014 and April 27,
2015, each time extending the period for the Department to review
the application by up to one year.
2. See 33 U.S.C.A. Section 1341.
3. The other permits sought by Constitution in the Joint
Application remain pending before the Department and are not the
subject of this letter.
37a
Appendix B
BACKGROUND
The Federal Energ y Reg ulatory Commission
(FERC) issued a certificate approving construction
and operation of the pipeline on December 2, 2014,
conditioning its approval on Constitution first obtaining
all other necessary approvals. Accordingly, Constitution’s
Application for a WQC pending with the Department
must be approved before construction may commence.
Constitution’s Application was reviewed by NYSDEC in
accordance with ECL Article 70 (Uniform Procedures Act
or UPA) and its implementing regulations at 6 NYCRR
Part 621, which provide a review process for applications
received by NYSDEC.
Despit e FERC cond it ion i ng it s approva l on
Constitution’s need to obtain a WQC, the Department has
received reports that tree felling has already occurred in
New York on the Project’s right of way. This tree cutting,
both clear cutting and selective cutting, has occurred
notwithstanding the fact that Constitution has right-ofway agreements with the property owners where this
cutting has occurred. The tree felling was conducted
near streams and directly on the banks of some streams,
and in one instance has resulted in trees and brush being
deposited directly in a stream, partially damming it.
As described below, this type of activity, if not properly
controlled, can severely impact the best usages of the
water resource.
38a
Appendix B
Concurrent with its review, the Department received
a Clean Air Act Title V application 4 for the Wright
Compressor Station (Wright Compressor Station) from
Iroquois Gas Transmission System, Inc. Additionally,
Constitution is obligated to obtain coverage from
NYSDEC under the SPDES Stormwater General Permit
for Construction Activities (GP-0-15-002) and prepare a
Stormwater Pollution Prevention Plan (SWPPP) prior to
Project construction.
Proposed Project Description and Environmental Impacts
Constitution proposes construction of approximately
124.14 miles of new interstate natural gas transmission
originating in northeastern Pennsylvania, proceeding into
New York State through Broome, Chenango, Delaware,
and Schoharie Counties, terminating at the existing
Wright Compressor Station in Schoharie County. In
New York State, the Project, rather than co-locating a
significant portion of the pipeline on an existing New
York State Department of Transportation (NYSDOT)
Interstate 1-88 access area 5 , proposes to include new
4. Minor Source Air Permit Modification, Wright Compressor
Station, Town of Wright, Schoharie County, NY, Iroquois Gas
Transmission System, July 26, 2013.
5. On September 25, 2013, NYSDEC provided FERC with
comments on Constitution’s Environmental Report dated June 13,
2013, supplemented in July, 2013 that concurred with the United
States Army Corps of Engineers’ (ACOE) comments and supported
ACOE’s requcst to FERC for additional details and documentation
to support the reasons why all or some of the Project route could not
be routed with the New York State Department of Transportation
39a
Appendix B
right-of-way (ROW) construction of approximately 99
miles of new 30-inch diameter pipeline, temporary and
permanent access roads and additional ancillary facilities.
A lthough t he Depa r tment repeat ed ly a sked
Constitution to analyze alternative routes that could
have avoided or minimized impacts to an extensive
group of water resources, as well as to address other
potential impacts to these resources, Constitution failed
to substantively address these concerns. Constitution’s
failure to adequately address these concerns limited
the Department’s ability to assess the impacts and
conclude that the Project will comply with water quality
standards. Project construction would impact a total of
251 streams, 87 of which support trout or trout spawning.
Cumulatively, construction would include disturbance to
3,161 linear feet of streams resulting in a total of 5.09
acres of stream disturbance impacts. Furthermore,
proposed Project construction would cumulatively impact
(NYSDOT) Interstate 1-88 control of access area. On April 7, 2014,
the Department provided FERC with preliminary comments on
the DEIS whieh extensively analyzed the environmental benefits
of utilizing Interstate 1-88 (also referred to as Alternative “M”)
regarding stream, wetland, and interior forest habitats.
In June 2014, Constitution provided information about
Alternative M which Department Staff found did not contain sufficient
analysis to determine whcther Alternative M would generate
fewer impacts than Constitution’s preferred route. However, using
Constitution’s information, as well as publicly available information,
Department Staff conducted a review that found that Alternative
M could reduce overall impacts to water bodies and wetlands when
compared to Constitution’s preferred route.
40a
Appendix B
85.5 acres of freshwater wetlands and result in impacts to
regulated wetland adjacent areas totaling 4,768 feet for
crossings, 9.70 acres for construction and 4.08 for acres
for Project operation. Due to the large amount of new
ROW construction, the Project would also directly impact
almost 500 acres of valuable interior forest. Cumulatively,
within such areas, as well as the ROW generally, impacts
to both small and large streams from the construction
and operation of the Project can be profound and could
include loss of available water body habitat, changes in
thermal conditions, increased erosion, and creation of
stream instability and turbidity.
The individual quality and integrity of streams
form the primary trophic levels that support many
aquatic organisms and enable the provision of stream
ecosystems at large. Under the Project’s proposal, many
of the streams to be crossed present unique and sensitive
ecological conditions that may be significantly impacted
by construction and jeopardize best usages. For a number
of reasons, streams that support trout and other cold
water aquatic species are typically the most sensitive. The
physical features of these streams include dense riparian
vegetation often composed of old-growth trees which are
free of invasive species and that shade and cool streams
while also maintaining the integrity of adjacent banks or
hillslopes. Undisturbed spring seeps provide clean, cold
water and stable yet sensitive channel forms maintain the
integrity of the stream itself and further preserve water
quality. Biologically, these streams are vital in providing
complex habitat for foraging, spawning and nursery
protection by wild reproducing trout.
41a
Appendix B
Impacts to these streams are exacerbated as the
cumulative negative effects of multiple crossings are
added. Demonstrating this, the trout stream Clapper
Hollow Creek and its tributaries would be crossed 11 times
by the project. Likewise, Ouleout Creek and its tributaries
will be crossed 28 times. Many of these streams are
part of tributary networks that are dependent upon the
contributing quality of connected streams to supply and
support the physical and biological needs of a system.
This is especially true in supporting the viability of wild
trout populations.
Initially, 100 per cent loss of stream and riparian
habitat will occur within the ROW as it is cleared and
the pipeline trenched across streams. The trenching of
streams will destroy all in-stream habitat in the shorter
term and in some cases could destroy and degrade specific
habitat areas for years following active construction. For
example, highly sensitive groundwater discharge areas
within streams could be disturbed, resulting in loss or
degradation to critical spawning and nursery habitat. In
addition, physical barriers will temporarily prevent the
movement of aquatic species during active construction
and changes to the stream channel will persist beyond
the active construction period, creating physical and
behavioral barriers to aquatic organism passage.
Changes to thermal conditions will also likely occur
due to clearing of riparian vegetation. Because of the need
to maintain an accessible ROW, subsequent revegetation
will take considerable time to replace what was lost,
notably long-lived, slow growing forest trees. Loss of
42a
Appendix B
riparian vegetation that shades streams from the warming
effects of the sun will likely increase water temperatures,
further limiting habitat suitability for cold-water aquatic
species such as brook trout. The loss of shade provided
by mature riparian vegetation may be exacerbated in the
long term by climate change and thus be more significant
since small changes in the thermal loading of cold water
trout streams could result in the long term loss of trout
populations.
NYSDEC Staff’s extensive experience and technical
reviews have shown that destabilization of steep hillslopes
and stream banks will likely occur and may result in
erosion and failure of banks, causing turbid inputs to
waterbodies. Specifically, Project construction would
include approximately 24 miles of steep slope or side slope
construction. Cumulatively, this would account for roughly
24 percent of the new cleared right-of-way. Exposed
hillslopes can become less stable and, when appropriate
stormwater controls are not properly implemented,
erosion can result in increased sediment inputs to streams
and wetlands. If these events occur they can affect the
water quality and habitat quality of these streams.
Trenching of streams can also destabilize the stream
bed and such conditions can temporarily cause an
exceedance of water quality standards, notably turbidity.
Turbidity and sediment transport caused as a result
of construction can negatively impact immediate and
downstream habitat, can smother or kill sensitive aquatic
life stages and reduce feeding potential of all aquatic
organisms. More specifically, visual predators such as
43a
Appendix B
brook trout find food using visual cues. Thus, reductions
in clear water conditions may reduce feeding success
that can ultimately result in impacts on aquatic species’
propagation and survival and corresponding reductions
in the attainment of the waters’ best usages.
As a result of chronic erosion from disturbed stream
banks and hill slopes, consistent degradation of water
quality may occur. Changes in rain runoff along ROW
may change flooding intensity and alter stream channel
morphology. Disturbed stream channels are at much
greater risk of future instability, even if the actual work
is conducted under dry conditions; long ranging stream
erosion may occur up and downstream of disturbed stream
crossings well beyond the time of active construction.
This longer term instability and erosion can result in
the degradation of spawning beds and a decrease in egg
development. The loss of spawning potential in some
cold headwater streams may significantly reduce the
long-term viability of these streams to support trout.
Constitution proposes to cross 50 known trout spawning
streams which will likely result in cumulative impacts on
the trout populations in these streams. More specifically,
and by way of an example of cumulative impacts to a water
body, Constitution proposes to cross Ouleout Creek and its
tributaries a total of 28 times with 15 of these crossings
occurring in trout spawning areas.
Finally, at the landscape level, impacts to streams from
the ROW construction are analogous to the cumulative
impacts from roads. There is an established negative
correlation between road miles per watershed area and
44a
Appendix B
stream quality. Thus, increases in the crossings of streams
by linear features such as roads and the pipeline ROW can
have cumulative impacts beyond the individual crossings.
In the case of the 1 mile corridor surrounding the proposed
Constitution pipeline, the pre-construction crossing/area
ratio for the New York section is 2.28 crossings/square
mile. However, the post-construction ratio will increase 44
per cent to 3.29 crossings/square mile. In specific basins
this ratio will be higher and may cause a permanent
degradation in stream habitat quality and likewise affect
associated natural resources, including aquatic species’
propagation and survival.
NYSDEC Application Reviews
On August 21, 2013, Constitution submitted the
Application to obtain a CWA §401 WQC and NYSECL
Article 15 and Article 24 permits to the Department.
Due to insufficient information, NYSDEC issued a
Notice of Incomplete Application on September 12,
2013, indicating that the Application was not complete
for commencing review. On May 9, 2014, Constitution
simultaneously withdrew and resubmitted its WQC
request to the NYSDEC. Constitution supplemented
the Application a number of times in 2014. A Notice of
Complete Application for public review was published by
NYSDEC in the Environmental Notice Bulletin (ENB)
and local newspapers on December 24, 2014.
This notice commenced a public comment period
ending on January 30, 2015 which was subsequently
extended to February 27, 2015. To afford the Applicant
45a
Appendix B
time to respond to NYSDEC’s requests for information
based on thousands of public comments, and to extend
the time period by which NYSDEC was required to
issue the WOC and associated permits, Constitution
submitted its second request to withdraw and resubmit
the WOC on April 27, 2015. This resubmission initiated
an additional UPA comment period until May 21, 2015. A
total of 15,035 individual comments were received during
the two comment periods. Most of these comments related
to issues surrounding the Project applications; a relative
handful were related to issues specific to the Compressor
Station application.
Since August 21, 2013, Constitution supplemented
its Application numerous times in response to additional
information requests by the Department; Table 1 below
provides an easy reference of the requests and submittals·
associated with the Application over the past several
years.
Table 1
Prepared by
Date
Summary
DEC
June 21, 2012
Summary of PreApplication Meeting
DEC
May 30, 2013
Sample Matrix for
Linear Projects
Constitution
August 28,
2013
401 WQC and
related NYS Joint
Permit application/
documentation
received by DEC
46a
Appendix B
DEC
September
12, 2013
Notice of Incomplete
Application
Constitution
November 27, Joint Permit Application
2013
- Supplemental
Information
Constitution
May 9, 2014
401 WQC Application
Withdrawal and Resubmittal
DEC
July 3, 2014
DEC Recommendations
for Revised Joint
Application
Constitution
August 13,
2014
Joint Permit
Application Supplemental
Information #2
Constitution
November 17, Additional Information
2014
Submittal
Constitution
November 17, Responses to Wetland
2014
Mitigation Plan
Deficiencies
Constitution
November
24, 2014
Updated and Revised
Information
Constitution
December 1,
2014
Response to Request
for Additional
Clarification of
Wetland Impacts
DEC
December
24, 2014
Notice of Complete
Application
47a
Appendix B
DEC
December 31, NY Stream Crossing
2014
Feasibility Analysis
Information Request
Constitution
January 22,
2015
Summary of Changes
Trenchless Locations
Constitution
February 2,
2015
Revised Wetland
Mitigation Plan
Constitution
February 6,
2015
Phase I Stream
Analysis/Open Cut
DEC
February 19,
2015
DEC Proposed
Wetland Re-route
Constitution
March 27,
2015
Joint Permit
Application Supplemental
Information
Constitution
April 24,
2015
Response to DEC
Preferred List of
Trenchless Stream
Crossings
Constitution
April 27, 2015 401 WQC Application
Withdrawal and Resubmittal
DEC
April 27, 2015 Notice of Complete
Application - WQC
Withdrawal and Resubmittal
48a
Appendix B
Constitution
May 13, 2015
Wetland Mitigation
Area - Application for
Pesticide Permit
Constitution
May 20, 2015
Supplemental
Information Trenchless Crossings
DEC
June 1, 2015
Notice of Incomplete
Application - Pesticide
Permit
Constitution
June 19, 2015
Canadarago Lake
Mitigation Area
Update
Constitution
June 30, 2015
Updated Trenchless
Crossing Matrix
Constitution
July 8, 2015
Joint Permit
Application Supplemental
Information - Wetland
Re-route
Constitution
July 14, 2015
Additional Information
Submittal - Wetland
Impacts and Mitigation
Constitution
August 5,
2015
Response to Notice of
Incomplete Application
- Pesticide Permit
49a
Appendix B
Constitution
September
15, 2015
Joint Permit
Application Supplemental
Information
DEC
October 2,
2015
Acknowledgement of
NOI - SPDES MS GP Contractor Yard 5B
Constitution
January 6,
2016
Wetland Mitigation
Area - Application
for Pesticide Permit Betty Brook
DEC
February 26,
2016
Acknowledgement of
NOT - SPDES MS GP
- Contractor Yard 5B
STATEMENT OF REASONS FOR DENIAL
The Department, in accordance with CWA §401,
is required to certify that a facility meets State water
quality standards prior to a federal agency issuing a
federal license or permit in conjunction with its proposed
operation. An applicant for a water quality certification
must provide the Department sufficient information to
demonstrate compliance with the water quality regulations
found at 6 NYCRR Section 608.9 ( Water Quality
Certifications). Pursuant to this regulation, the Applicant
must demonstrate compliance with §§301, 302, 303, 306
and 307 of the Federal Water Pollution Control Act, as
implemented, by applicable water quality standards and
thermal discharge criteria set forth in 6 NYCRR Parts
50a
Appendix B
701,702,703,704 and 750, and State statutes, regulations
and criteria otherwise applicable to such activities. 6
Denial of a WQC may occur when an application fails to
contain sufficient information to determine whether the
application demonstrates compliance with the above stated
State water quality standards and other applicable State
statutes and regulations due to insufficient information.
The Department is guided by statute to take into account
the cumulative impact upon all resources in making a
determination in connection with any license, order,
permit or certification, which in this case includes being
able to evaluate the cumulative water quality impacts of
ROW construction and operation on the numerous water
bodies mentioned in this letter.7
As noted above, Constitution supplemented its
Application in response to information requests issued
to it by the Department but has not supplied sufficient
information for the Department to be reasonably assured
that the State’s water quality standards would be met
during construction and operation of the proposed
pipeline. As a result the Department cannot be assured
that the aforementioned adverse impacts to water quality
and associated resources will be avoided or adequately
minimized and mitigated so as not to materially interfere
with or jeopardize the best usages of affected water bodies.
The following are the Department’s reasons for denial of
Constitution’s Application based on applicable sections of
the New York State environmental laws, regulations or
standards related to water quality.
6. 6 NYCRR §608.9 (2) and (6).
7. ECL 3-0301(1)(b).
51a
Appendix B
Stream Crossings
Project construction would disturb a total of 251
streams under New York State’s jurisdiction, 87 of
which support trout or trout spawning. Cumulatively,
construction would disturb a total of 3,161 linear feet of
streams and result in a combined total of 5.09 acres of
temporary stream disturbance impacts. From inception
of its review of the Application, NYSDEC directed
Constitution to demonstrate compliance with State water
quality standards and required site-specific information
for each of the 251 streams impacted by the Project.
NYSDEC informed Constitution that all 251 stream
crossings must be evaluated for environmental impacts
and that trenchless technology was the preferred method
for stream crossing. This information was conveyed to
Constitution and FERC on numerous occasions since
November 2012; however, Constitution has not supplied the
Department with the necessary information for decision
making.
Deficient Trenchless Stream Crossings Information
and Lack of Specific Stream Crossings Details
Staff’s review of the Application includes an analysis
of adverse stream crossing impacts, specifically the
suitability of open trenching versus trenchless techniques
or subsurface boring methods. Open trenching is a highly
impactful construction technique involving significant
disturbance of the existing stream bed and potential
long-term stream flow disruption, destruction of riparian
vegetation and establishment of a permanently cleared
52a
Appendix B
corridor. Comparatively, trench less methods present
significantly fewer environmental impacts to the regulated
resource. Because alternative trench less techniques exist
for this Project, the Department requested additional
information from Constitution to evaluate their feasibility
and to determine if the Application provides enough
information to demonstrate compliance with water quality
standards.
Since NYSDEC’s most protective method for stream
crossings is some form of a trenchless technology,
NYSDEC directed Constitution to determine whether a
trenchless technology was constructible for each stream
crossing. 8 On a number of occasions NYSDEC identified
the need to provide information so that it could evaluate
trenchless stream installation methods (see Table 2,
below); however, Constitution has not provided sufficient
information to enable the Department to determine if the
Application demonstrates compliance with 6 NYCRR Part
703, including, but not limited to, standards for turbidity
and thermal impacts (6 NYCRR §703.2), and 6 NYCRR
Part 701 (best usages).
8. NYSDEC Comments to FERC, November 7, 2012.
Date
June 21, 2012
November 7,
2012
Prepared by
NYSDEC
NYSDEC
In comments to FERC, NYSDEC stated that for
streams and wetlands the preferred method for
crossing is trenchless technology. The draft EIS
should evaluate cases where other methods are
proposed and Constitution should explain why
trenchless crossing technology will not work or is
not practical for that specific crossing.
In a summary of the initial pre-application meeting
with Constitution, which took place on June 7, 2012,
NYSDEC stated in a letter to Constitution that
for protected streams and wetlands, trenchless
technology is the preferred method for crossing
and should be considered for all such crossings
(emphasis added).
Summary
Table 2
53a
Appendix B
April 9, 2013
May 28, 2013
July 17, 2013
FERC
NYSDEC
NYSDEC
NYSDEC comments to FERC reiterates that
trenchless technology is preferred method for
stream crossings. The DEIS should evaluate cases
where other methods are proposed and the Project
Sponsor should explain why trenchless technology
will not work or is not practical for that specific
crossing.
Meeting with Constitution and NYSDEC staff at
the DEC Region 4 office to review stream crossings.
NYSDEC reiterates that acceptable trench less
technology was the preferred installation method
and that stream crossings should be reviewed for
feasibility of using those technologies.
FERC’s Environmental Information Request (EIR)
directed Constitution to address all of the comments
filed in the public record by other agencies
regarding the draft Resource Reports including all
comments from the NYSDEC.
54a
Appendix B
July - August
2013
November
2013
December 31,
2014
NYSDEC
and
Constitution
staff
Constitution
NYSDEC
and
Constitution
staff
Meeting conducted with Constitution staff in which
NYSDEC indicated that the Trenchless Feasibility
Study was inadequate, e.g. provided insufficient
justification and removed all streams less than 30
feet in width from analysis.
Trenchless Feasibility Study provided by
Constitution that described its choices of stream
crossing techniques. Upon review, document and
justifications found insufficient and all streams less
than 30’ wide were arbitrarily eliminated from any
consideration for trenchless crossing methods.
Field visits of proposed stream crossings prior to
permit applications to the Department. At staff each
crossing, NYSDEC emphasized to Constitution
staff that trench less technology is preferred/most
protective.
55a
Appendix B
To aid in an appropriate review of stream crossing
techniques and compliance with water quality
standards, an informational request table including
required technical information was developed by
NYSDEC and provided to Constitution.
U.S. Army Corps of Engineers letter reiterates
a request for a feasibility analysis of trenchless
crossings.
Meeting between Constitution and NYSDEC
staff wherein Constitution stated it was unable to
complete the table (described above on December
31, 2014). NYSDEC staff indicated that the
justification for stream crossing methods was
insufficient and that appropriate site specific
information must be provided.
Conference call: NYSDEC reiterated its request for
a site specific analysis of trenchless stream crossings
for all streams including those under 30 feet wide.
December 31,
2014
January 13,
2015
January 23,
2015
January 28,
2015
NYSDEC
US Army
Corps of
EnQineers
Constitution
and
NYSDEC
Constitution
and
NYSDEC
56a
Appendix B
Constitution
Februaey 5,
2015
Constitution provided an updated example of
a trench less feasibility study but that example
continued to exclude streams up to 30 feet wide from
analysis and did not provide detailed information of
the majority of streams.
57a
Appendix B
58a
Appendix B
Constitution submitted a Trenchless Feasibility
Study (Study) to FERC in November of 2013 which the
Department has analyzed for the purpose of reviewing
Constitution’s WQC application. This Study did not include
the information that FERC directed Constitution to supply
to NYSDEC (and others) in its April 9, 2013 EIR, which
incorporated NYSDEC’s information requests, including
NYSDEC’s request to Constitution dated November 7,
2012. Moreover, the Study did not include information
that NYSDEC specifically requested in meetings and
site visits with Constitution throughout 2013 and did not
provide a reasoned analysis to enable the Department to
determine if the Project demonstrates compliance with
water quality standards.
Of the 251 streams to be impacted by the Project,
Constitution’s Study evaluated only 87 streams, in
addition to the Schoharie Creek, as part of the Phase I
desktop analysis9 which Constitution used to determine
if surface installation methods warranted consideration
for a trenchless design. Of the 87 streams reviewed,
Constitution automatically eliminated 41 streams from
consideration f9r trench less crossing because those
streams were 30 feet wide or less. Constitution further
eliminated 10 more streams from the Study because
although they were in the proposed ROW, they would
not be crossed by the Project. Accordingly, a total of 24
streams were subsequently analyzed in the Study’s Phase
9. Constitution described the Phase I analysis as “a general
evaluation of Project locations meeting the basic criteria for trench
less construction methods such as crossing distances, feature
classifications and potential associated impacts.”
59a
Appendix B
II analysis which evaluated construction limiting factors
including available workspace, construction schedules
and finances. Using its review criteria, Constitution’s
Study finally concluded that only 11 stream crossings of
the 251 displayed preliminary evidence in support of a
potentially successful trenchless design and were chosen
for the Phase III geotechnical field analysis. Department
staff consistently told Constitution that its November
2013 Trenchless Feasibility Study was incomplete and
inadequate (See Table 2).
Constitution’s continued unwillingness to provide
a complete and thorough, Trenchless Feasibility Study
required Department staff to engage in a dialogue
with Constitution on potential trenchless crossings
for a limited number of streams. On April 24, 2015,
Constitution’s consultant produced a revised draft list
of 29 trenchless stream crossings and an example of
plans that would be provided for each crossing on the
proposed list. Subsequently, in May 2015, Constitution
provided detailed project plans for 25 potential trenchless
crossings, but only two of those plans were based on
full geotechnical borings that are necessary to evaluate
the potential success of a trenchless design. Detailed
project plans including full geotechnical borings for the
remaining stream crossings have not been provided to the
Department. From May through August 2015, NYSDEC
engaged in a dialogue with Constitution on potential
trenchless methods for 19 streams, although NYSDEC
did not form a conclusion on a crossing method for the
remaining streams, including the vast majority of trout
and trout spawning streams. Furthermore, as noted
60a
Appendix B
above, Constitution’s unwillingness to adequately explore
the Alternative M route alternative, with the prospect
of potentially fewer overall impacts to water bodies and
wetlands when compared to Constitution’s preferred
route, means that the Department is unable to determine
whether an alternative route is actually more protective of
water quality standards. The Department therefore does
not have adequate information to assure that sufficient
impact avoidance, minimization or mitigation measures
were considered as to each of the more than 200 streams
proposed for trenched crossings.
Due to the lack of detailed project plans, including
geotechnical borings, the Department has determined
to deny Constitution’s WQC Application because the
supporting materials supplied by Constitution do not
provide sufficient information for each stream crossing
to demonstrate compliance with applicable narrative
water quality standards for turbidity and preservation
of best usages of affected water bodies. Specifically, the
Application lacks sufficient information to demonstrate
that the Project will result in no increase that will cause
a substantial visible contrast to natural conditions.10
Furthermore, the Application remains deficient in that
it does not contain sufficient information to demonstrate
compliance with 6 NYCRR Part 701 setting forth conditions
applying to best usages of all water classifications.
Specifically, “the discharge of sewage, industrial waste
or other wastes shall not cause impairment of the best
10. 6 NYCRR §703.2.
61a
Appendix B
usages of the receiving water as specified by the water
classifications at the location of the discharge and at other
locations that may be affected by such discharge.”11
Cumulatively, impacts to both small and large streams
from the construction and operation of the Project can be
profound and include loss of available habitat, changes in
thermal conditions, increased erosion, creation of stream
instability and turbidity, impairment of best usages, as
well as watershed-wide impacts resulting from placement
of the pipeline across water bodies in remote and rural
areas (See Project Description and Environmental
Impacts Section, above). Because the Department’s review
concludes that Constitution did not provide sufficient
detailed information including site specific project plans
regarding stream crossings (e.g. geotechnical borings) the
Department has determined to deny Constitution’s WQC
Application for failure to provide reasonable assurance
that each stream crossing will be conducted in compliance
with 6 NYCRR §608.9.
In addition, the Application lacks required sitespecific information for each of the 251 stream crossings
including, but not limited to the specific location of access
roads, definite location of temporary stream crossing
bridges, details of temporary bridges including depth of
abutments in stream banks, details of proposed blasting
and the location of temporary coffer dams for stream
crossings. Absent this information and the information
described above, the Department cannot determine
whether additional water quality impact avoidance,
11. 6 NYCRR §701.1.
62a
Appendix B
minimization or mitigation measures must be taken to
ensure compliance with water quality standards in water
bodies associated with this infrastructure.
Insufficient Site-Specific Information on Depth of Pipe
NYSDEC received numerous public comments
regarding the necessary depth for pipeline burial in
stream beds that would prevent inadvertent exposure
of the pipe. Historically, Department staff has observed
numerous and extensive vertical movements of streams
in New York State that have led to pipe exposure and
subsequent remedial projects to rebury the pipe and
armor the stream channel. These subsequent corrective
actions caused severe negative impacts on water quality
and seriously impacted the stability and ecology of the
stream that could have been avoided with a deeper pipe.
Department staff requested that Constitution provide
a comprehensive and site-specific analysis of depth for
pipeline burial, but Constitution provided only a limited
analysis of burial depth for 21 of the 251 New York
streams.12 Without a site-specific analysis of the potential
for vertical movement of each steam crossing to justify a
burial depth, NYSDEC is unable to determine whether the
depth of pipe is protective of State water quality standards
and applicable State statutes and standards.
In addition to impacts to water quality described
above and without proper site-specific evaluations, future
12. See, Trout Stream Restoration Report, dated August
2014.
63a
Appendix B
high flow events could expose the pipeline, resulting in
risks to the health, safety, and welfare of the people of New
York State. Pipe exposure would require more extensive
stabilization measures and in stream disturbances
resulting in addition degradation to environmental
quality. We note that flooding conditions from extreme
precipitation events are projected to increase on the
operational span of the pipeline due to climate change.
Deficient Blasting Information
Constitution’s Blasting Plan, dated August, 2014,
outlines the procedures and safety measures to which
Constitution would adhere in the event that blasting is
required for Project installation. The Blasting Plan does
not provide site-specific information where blasting will
occur but instead provides a list of potential blasting
locations based on the presence of shallow bedrock. In
New York alone, Constitution identifies 42.77 total miles
where shallow bedrock occurs, or approximately 44 per
cent of the route, involving 84 wetlands crossings and 27
waterbody crossings. Constitution indicates that a final
determination on the need for blasting will be made at
the time of construction in waterbodies and wetlands.
Due to the lack of specific blasting information needed for
review with respect to associated water bodies, NYSDEC
is unable to determine whether this Plan is protective of
State water quality standards and in compliance with
applicable State statutes and standards.
64a
Appendix B
Wetlands Crossings
Wetlands provide valuable water quality protection by
retaining and cleansing surface runoff to water bodies.
Constitution’s Application does not demonstrate that
wetland crossings will be performed in a manner that
will avoid or minimize discharges to navigable waters
that would violate water quality standards, including
turbidity. Absent detailed information for each wetland
crossing that demonstrates Constitution properly avoided,
minimized and mitigated impacts to wetland and adjacent
areas, the Application does not supply the Department
with adequate information to assure that streams and
water bodies will not be subject to discharges that do not
comply with applicable water quality standards.
NYSDEC Denial
Constitution was required to submit an Application
providing sufficient information to demonstrate compliance
with the regulations found at 6 NYCRR §608.9, Water
Quality Certifications. Pursuant to this regulation, an
Applicant must demonstrate compliance with §§301, 302,
303, 306 and 307 of the Federal Water Pollution Control
Act, as implemented, by applicable water quality standards
and thermal discharge criteria set forth in 6 NYCRR Parts
701,702,703,704 and 750, and State statutes, regulations
and criteria otherwise applicable to such activities.13 The
Department must also take into account the cumulative
impact to water quality of the full complement of
13. 6 NYCRR §608.9 (2) and (6).
65a
Appendix B
affected water resources in making any determination in
connection with any license, order, permit or certification.14
For the reasons articulated above, the Department hereby
denies Constitution’s WQC Application because it does
not supply adequate information to determine whether
the Application demonstrates compliance with the above
stated State water quality standards and other applicable
State statutes and regulations.
This notice of denial serves as the Department’s
final determination. Should Constitution wish to address
the above deficiencies, a new WQC application must be
submitted pursuant to 6 NYCRR §608.9 and 6 NYCRR
Part 621. Uniform Procedures Regulations, 6 NYCRR
§621.10 provide that that an applicant has a right to a
public hearing on the denial of a permit, including a §401
WQC. A request for hearing must be made in writing to
me within 30 days of the date of this letter.
Sincerely,
/s/
John Ferguson
Chief Permit Administrator
14. ECl 3-0301 (1)(b).
66a
Appendix
C
APPENDIX C — DENIAL
OF REHEARING
OF THE
UNITED STATES COURT OF APPEALS FOR THE
SECOND CIRCUIT, DATED OCTOBER 19, 2017
UNITED STATES COURT OF APPEALS
FOR THE SECOND CIRCUIT
Docket No: 16-1568
At a stated term of the United States Court of Appeals for
the Second Circuit, held at the Thurgood Marshall United
States Courthouse, 40 Foley Square, in the City of New
York, on the 19th day of October, two thousand seventeen.
CONSTITUTION PIPELINE COMPANY, LLC,
Petitioner,
v.
NEW YORK STATE DEPARTMENT OF
ENVIRONMENTAL CONSERVATION, BASIL
SEGGOS, ACTING COMMISSIONER, NEW YORK
STATE DEPARTMENT OF ENVIRONMENTAL
CONSERVATION, JOHN FERGUSON, CHIEF
PERMIT ADMINISTRATOR, NEW YORK
STATE DEPARTMENT OF ENVIRONMENTAL
CONSERVATION,
Respondents,
67a
Appendix C
STOP THE PIPELINE, CATSKILL
MOUNTAINKEEPER, INC., SIERRA CLUB,
RIVERKEEPER, INC.,
Intervenors.
ORDER
Petitioner, Constitution Pipeline Company, LLC, filed
a petition for panel rehearing, or, in the alternative, for
rehearing en banc. The panel that determined the appeal
has considered the request for panel rehearing, and the
active members of the Court have considered the request
for rehearing en banc.
IT IS HEREBY ORDERED that the petition is
denied.
FOR THE COURT:
/s/
Catherine O’Hagan Wolfe, Clerk
This is a copy of a public record, reproduced as it was published. It is not legal advice, and it may not be the version a court would rely on. Check the official source before you cite it.