T .C . Memo . 2009-5 0
Agency decision
Ask Donna
What actually matters in this document.
Text
T .C . Memo . 2009-5 0
UNITED STATES TAX COUR T
UNION CARBIDE CORPORATION AND SUBSIDIARIES, Petitioner v .
COMMISSIONER OF`INTERNAL REVENUE, Responden t
Docket No . 11119-99 .
Filed March 10, 2009 .
R determined deficiencies in P's Federal income
tax for 1994 and 1995 .• Pursuant to a negotiated
agreement, P was allowed research credits under sec .
41, I .R .C ., for 1994 and 1995 . In an amended petition
P now seeks-additional research credits for 106
projects conducted at its manufacturing plants . To
resolve this action expeditiously, P and R agreed to
try five of the largest projects underlying P's
research credit claim .
Held : Two ' of the five ;,prof ects constitute
qualified research under sec . 41(d), I .R .C .
Held , further , P has established that it included
all activities that were similar to the two qualified
research projects in its calculation of its base amount
under sec . 41(c)(4), I .R .C .
Held , further , P has established that it incurred
$1,045 of additional qualified research expenditure s
SERVED MAR 10 2009
-L(QREs) for wages paid to specific plant employees fo r
.qualified services performed during the two qualified
research projects . The remaining expenditures fo r
which P claims additional research credits are not QREs
because they were incurred in the production of good s
.for sale, not in the conduct of qualified research .
Held , further , P improperly included production
,costs in its base amount . However, because P's error
-caused P to overestimate its base amount, we find P's
error to be harmless and accept P's calculation of its
additional base period QREs with several adjustments .
Harold J . Heltzer ,
Alex E . Sadler ,
Robert L . Willmore ,
Pete r
B . Work , and Allen D . Madison , for petitioner .
Daniel A . Rosen ,
Jill A . Frisch ,
Lyle B . Press ,
Alex
Shlivko , and Jenny D . Boissonneault , for respondent .
CONTENT S
FINDINGS OF FACT
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
I . Overview
. . . . . . . .
A . Petitioner . . . . . .
B . Procedural History .
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
. . 9
. . 9
. 11
.
II . Claim Projects . . . . . . . . .
. .. . . . .
A . The Olefins Production Process .
.. . . . .
B . The Amoco Anticoking Project . . .
. . . .
1 . Overview of Coking
. .
. .
.
2 . The Coke Reduction Program and Amoco' s
Technology
. . . . .
. . . . . . . .
3 . The Amoco Anticoking Project
. . .
.
C . The Spuds Project
. . . . . . . . .. . . . . .
1 . Overview of the Spuds Project . . . . .
2 . Petitioner's Motion for Leave To Amen d
Its Petition
. . . .
. . . . . .
D . The Sodium Borohydride Project . .
. . .
1 . Overview of the Acid Gas Removal System
2 . The Sodium Borohydride Project
. . .. .
E . UOP GA-155 Project . . . . . . . . . . . . .
1 . Overview of Fouling in the C3 Column
2 . Overview of Inhibitors
. . . . . .
.
.
.
.
.
.
.
.
. .
.
. 15
. 16
. 20
20
.
.
.
.
.
.
.
.
.
.
.
.
. 22
. 25
. 32
. 32
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
. 9
37
38
38
41
48
48
50
- 3 52
. . . . . .
3 . The UOP GA-155 Project
60
F . The UCAT-J Project . . . . .
1 . Overview of Polyethylene Production . . . . . . 60
66
.
. . . . . .
. . . . .. . .
2 . UCAT-J . . .
.
70
. . .
. . .
3 . Overview of the UCAT-J Project
4 . Experimental Runs .Before,the Credit Years . . 79
79
5 . Experimental Runs During the Credit Years .
.
81
.
.
.
.
.
.
a . DJM-5265H (UCAT-J Run 1)
. . . . . 84
b . DJM-1810B (UCAT-J Runs 2 and 11 )
. 88
. .
C . DJM-1732H (UCAT-J Runs 3 and 15)
d . DJM-2419H, DJM-1810H, and DJM 2016H .
.
. . . . . . . 91
(UCAT-J Runs 4 Through 6)
. . . . . 95
.
DJM-1735H
(UCAT-J
Runs
7
and
16)
e
f . DJL-5264H and DJL-5280H (UCAT-J Runs 8, 9 ,
. .
. . . . . 98
. . . .
18, and 19
J Runs 10 an d
DJH-2580H and DJH-2950H (UCAT.
. 10 1
. .
. . . .
12)
. . . .
d
.
DJL-5420H
and
DJL-5143H
(UCAT-J
Runs
13
an
h
103
. . .
14)
. . . 10 4
i . DJM-1720H (UCAT-J Run 17) . .
. . .
. . . . .
III . Claimed Costs . . . . .
.
. . .
.
.
.
.
A . Cost Documentation Used
.
1 . PCDs and MASs
2 . CMAI Data for Ethylene Byproducts .
.
.
. . . . .
3 . Wage Information
.
.
.
.
.
.
.
.
.
R&D
Budgets
.
.
.
4
.Amoco
Anticoking
Project
B . Costs of the
. . .
. .
. . . .
1 . Supplies
2 . Wages . . . . . . . . . . . . . . .
.
C . Costs of the Spuds Project . . . .
.
. .
D . Costs of the .UOP GA-155 Project
. . . . . . . . . . . .
1 . Supplies
. .
. . . . . . . . .
2 . Wages . .
E . Costs .of the Sodium Borohydride Project
.
. . .
F . Costs of . the UCAT-J Project
. . . . . .
1 . Supplies
. . . .
2 . Wages . . . . . . . . . . . . . . .
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
. .
. .
. .
. .
. .
. .
. .
. .
. .
. .
.
.
.
.
. 106
. 10 6
. 106
107
. . 109
. . 10 9
. . 110
. . 110
. . 11 3
. . 114
. . 115
. . 115
. . 11 6
. . 116
. 117
. . 117
. . 11 8
.
.
.
. . . . . . . . 119
. . . .
IV . Base Period Projects . . . .
A ., Scope of the Trial . . . . . . . . . . . . . . . . . .119
1 . Organization of UCC's Manufacturing Operation s
. . . . . . . . . . . 120
During the Base Period
.
Acquisitions
and
Dispositions
Between the
2
. . . . . . 122
Period
.
Claim Years and the Base
. . . . . 122
. . . . . . . . .
a . Acquisitions
. . . . . . . . . . . . . . . 12 4
b . Dispositions
. . . . . . . 125
.3 . UCC/Shell Polypropylene Business
- 4 a . The Cooperative Undertaking . . . . . . . . 125 .
127
b . SPC . . . . . .
.
Petitioner's
Base
Amount
Recalculation
. 12 9
c
B . Base Period Projects . . .
130
1 . UCC's Focus on R&D During the Base Period and
Credit Years
. . . . . . . . . . . . . . . 13 0
2 . The Role of R&D and Engineering at UCC's
. . . . . . . . . . . . . 130
Manufacturing Plants
3 . Petitioner's Identification of Plant-Base d
Qualified Research Activities Conducted Durin g
the Base Period . . . . . . . . . . . . . . . . . 131
. . . . . . . . . . 131
a . Dr . Wadia's Assignment
b . Dr . Wadia's Methodology . . . . . . . . . . 133
c . Dr . Wadia's Conclusions . . . . . . . . . . 134
d . Petitioner's Concessions
. . .
. . . . 136
i . Nalco Inhibitor Antifouling Test (Ru n
816)
. . . .
136
ii . Wastewater Activity (Run 809)
. . . . . 137
iii . Rohm & Haas Runs (Runs 81 3
and
814)
138
e . Activities That Were Not Identified Base
Period Activities . . . . . . . . . . . . . 139
i . NOx . . . . .
. . . . . . .
.
. 139
ii . John Zink Co . Orders . . . . . . . . . 149
iii ' Star Pelleting
. . .
. . . . 149
iv .
Naphtha
Analysis
15 0
if . Duration and Quantities of Produc t
Produced
. . . . .
. . . . . . . . . . 150
i . Natural and Forced Draft Burner Test s
(Runs 1 through 11, 95, and 96)
. . . 153
ii . Nalco 5211 Tests (Run 15)
. . . . . . 157
iii ., Vinyl Acetate Catalyst Protectio n
Tests (Runs 47 and 48 and Runs 59 4
and 596)
.
.
. . . . . . . . . . 159
iv ., Butyl Acetate Capacity Increase Tes t
(Run 161) . . .
. . . . . . . . . . 161
v . MEK Production Test (Run 175) . . . . . 161
vi . Secondary Refining System Tes t
(Run 178)
. . . . . . . . . . . . . . 162
vii . Spanish Fermentation Ethanol Refining
Test (Run 180)
. . . . . . . . . . . 16 2
viii . Ethanol Tertiary Recovery Test (Ru n
181) .
. . . . . . . .
. . . . 162
ix . Mexican Fermentation Ethanol Refining
Test
(Run
184)
16 3
X.
Propionic Acid Hydrogen Peroxid e
Treatment Test (Run 190)
. . . .
. 163
- 5 xi . 'Adiabatic Hydrogenation Beds
Rearrangement . Test (Run 198
. .
xii . Butanol Refining Test (Run 202)
xiii . DIBK Recycle to Mixed Keytones
Converters Test .(Run 608)
. .
.
.
.
.
. 16 3
. 164
. 16 4
V . Base Period QREs
. . . .
.
. . .
164
A . Documentation
. . . . . . .
.
. . . . . . . . . 166
B . Ms . Toivonen's Costing Methodology . . . .
. . 16 7
1 . Identifying the Lead PCD
. . . . . . . . . . . 168
2 . Identifying the Materials .
. . . . . . 169
3 . Tracing the Materials . . .
. . . . 169
4 . Determining the Unit Costs of Materials . . . . 170
5 . Calculating Total Materials Costs . . . . . . . 172
6 . Calculating the Wage . Costs
. . . . . . . . . . . 173
7 . Calculating the Total Run Costs . . . . . . . . 175
8 . Exceptions to Ms . Toivonen's General Costin g
Methodology . .
. . . . . .
. . . . . . 175
C . Ms . Toi v'onen's Conclusions .
. . .
. . . . . 178
D . Disputed Calculations
.
. . . . .
. . . 178
.
1 . Acrolein Refining System Capacity Test (Run
128) . . . . . . .
.
179
.
. 179
2 .* Propyl Dipropasol Refining Test (Run 171)
3 . Isophorone Mids Conversion Test (Run 173) 180
4 . Secondary Refining System Test (Run 178)
. . . 180
5 .' Naphtha-Sulfur Injection Test (Run 807) . . . . 180
6 . Methylmercaptopropanal (MMP) Refrigeratio n
Tests (Run 810)
. . . . . . . . . . . . . . 18 1
OPINION
.
I . The Experts
.
.
.
.
.
.
.
.
.
Petitioner's Expert Witnesses
1 . Peter Spitz . . . .
. .
2 . Gilbert Froment . . . . .
. .
3 . Richard Martin
4 . Norman Brockmeier . . . . .
5 . Ms . Hinojosa
. . . . . .
6 . Dr . Wadia . . . . . . . .
7 . Ms . Toivonen
. . . . .
B . Respondent's Expert Witnesses
. . . . . .
1 . Roy T . Halle
2 . M . Julianne McClung .
.
3 . Gary Allen
. . .
. . .
.
.
.
.
.
.
.
.
.
.
.
.
.
A.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
. 18 6
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
. 187
. 187
. 187
. 188
. 188
. 188
. 189
. 18 9
. 189
. 189
. 190
. 19 0
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
182
II . Whether the Claim Projects Constitute Qualified Research 191
A . The Qualified Research Tests . . . . . .
. . . . . 19 1
1 . The Section 174 Test
. . . .
. .
. . . . .194
0
- 6 . . . . . . 197
2 . The Technological Information Test
3 . The Business Component Test . .
. .
. . . 198
4 . The Process of Experimentation Test . . . . . . 198
. 20 3
5 . Activities That Are Not Qualified Research
B . The Claim Projects . . . . . . . . . . . . . . . . . . 204
. . . . . . . . .
. . .. 204
1 . Plant-Based Research
2 . The Amoco Anticoking Project
. . . . . . . 20 7
a . The Section 174 Test
.
. . . . . . . . 208,
b . The Technological Information Test
. . . . 211
c . The Business Component Test . . .
. . . 212
d . Process of Experimentation Test . . . . . . 212
e . Funded Research . . . . . . . .
. . . . . 215
f . Research After Commercial Production
. . . 216
g . Data Collection and Routine Testing . . . . 217
h . Substantiation Requirement.
. . . . . . . . 21 9
. . . . . . . 220
3 . The Spuds Project . . . . . . .
. . . . . . . . . 221
a . The Section 174 Test
b . The Remaining Tests . . . .
. . . . . . 22 3
4 . The Sodium Borohydride Project
. . . . . . .223
a . The First Three Tests 224
b . The Process of Experimentation Test . . . . 22 4
5 . The UOP GA-155 Project . . . . . . . . . . . . . 227
a . The Section 174 Test
. . . . . . . . . . . 228
b.
The
Remaining
Tests
23 0
6 . The UCAT-J Project .
. . .
. .
. . . .
. .
a . The Section 174 Test
.i . Uncertainty . .
. . . . .
ii . Discovering Information
. . . .
b . The Technological Information Test
.
c . The Business Component Test . . . . .
d . The Process of Experimentation Test .
e . Research After Commercial Production
f . Substantiation Requirement
. . . .
. . 230
. . . 230
. . . . 23 2
. . . 235
. . . 238
. . . . 239
. . . 239
. . . 242
. 24 3
III .
Base
Period
Activities
244
A . Whether Petitioner Must Include Activities Conducte d
By the Entire Consolidated Group . . . . . . .
B . Acquisitions and Dispositions
. .
. . . .
C . Polypropylene Runs . . . . . . . . . . . . . . . .
D . Whether Petitioner Included All Activities Simila r
. 245
. 248
. 250
to the Claim Projects on Its List. of Identifie d
Runs . .
. . . . . . . . . . . . . .
. . . . . . 251
1 . Petitioner's Sources of Information
. . . . . . 251
a . Whether Petitioner Was Required To Us e
FOCRs To Identify Base Period Activities . 251
b . Whether Petitioner Was Required To Consider
Alternative Sources
. . . . . . . . . . . . 255
- 7 2 . Whether Petitioner Should Include Additional
Activities in Its Base Period Calculation . . . 256
a . NOx
. . . . . . . 257
b . John Zink Co . Products
. . . . . . . . . 257
C . Star Pelleting Line . . . . . .
. . . . . 257
d . Naphtha Analysis
. . . . .
. . . .
. 258
e . Dr . Wadia's Limitation of Duration
.
. 25 8
3 . Reliability of Dr . Wadia's Methodology
. . . 260
a . Reliability of Dr .Wadia's Methodology as
Expert Testimony
. . . . . . . . . . . . . 261
i . Whether the Methodology Can Be Tested . 263
ii . Whether the Methodology Is,Known o r
Accepted in the Community, Has Been,
Published, or Has Been Subjected to Peer
Review
. . . . . .
. . . . . 26 4
iii . . Whether the Methodology is Subject to
Known Rate of Error . . .
. . 264
b . Petitioner's Definition of "Qualifie d
Research"
. . . . ..
. . . . . . . . . 268
. 272
c . Whether Dr . Wadia Is Biased . . . . .
IV . Claimed Costs
.
.
. . .
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
. 273
V . Base Period QREs
. .
. .
. . . . . . . . . .
. . . . . 28 5
A . Alleged Flaws in Ms . Toivonen's Costin g
Methodology
. .
. .
. . . . . . . . .. . . . . . 285
B . Alleged Errors in Ms . Toivonen' s
Calculation sCalculations . .
. . . .288
C . Documents Ms . Toivonen Relied Upon
. . . . . . . . 291 .
D . Consistency Requirement
.
. . . .
. . . . 29 1
1 . In General
. . . .
. . . . . . . . . . . . . 293
. 294
2 . Base Case Costs . . .
. . . . . . . .
. . .
. 295
3 . Wage Costs
. . . . . . . . . . .
E . Whether Ms . Toivonen Calculated the Cost o f
. . .
. . . . . . 29 6
"Qualified Research " Activities
VI . Conclusion
.
.
.
.
..
.
.
..
.
.
.
.
.
.
.
. 29 6
MEMORANDUM FINDINGS OF FACT AND OPINIO N
GOEKE,
Judge : Respondent determined deficiencies in
petitioner's Federal income . tax of $20,481,520 and $140,732,25 4
for 1994 and 1995, respectively . In its petition, as amended,
El
- 8 petitioner alleges that it is entitled to additional research
credits under section 411 of approximately $3,656,091 and
$4,726,664'for 1994 and 1995, respectively (claimed credits) .2
The claimed credits,are based on 106 projects it conducted in
various units within six manufacturing plants during 1994 and
1995 (credit years) . . For purposes of resolving this action
expeditiously, the parties have agreed to try five of the largest
projects3 underlying petitioner's affirmative research credi t
claims (claim projects) . 4
The issue before the Court is whether petitioner is entitle d
to additional research credits under section 41 for 1994 or
1995 .5 Resolution of this issue requires us to determine : (1 )
'Unless otherwise indicated, all section references are to
the Internal Revenue Code in effect for the years at issue, and
all Rule references are to the Tax Court Rules of Practice and
Procedure .
?In its original petition, petitioner claimed as affirmative
adjustments additional research credits of $4,808,671 and
$5,851,619 for 1994 and 1995, respectively .
After amending its petition, petitioner has conceded that an
additional project does not satisfy the requirements of sec .
41(d) . This concession does not affect our discussion of
petitioner's claims and will be addressed in the parties' Rule
155 computations .
'The term "projects" is used for convenience .
4Petitioner withdrew a sixth project before trial .
5All other issues in this case were resolved'by agreement of
the parties or our previous Opinion in Union Carbide Foreign
Sales Corp . v . Commissioner , 115 T .C . 423 (2000) .
0
9 Whether any of the claim projects constitute qualified research
under section 41(d) ; (2) whether any of the- claim projects
constitute qualified research, whether petitioner included all
activities that were similar to the claim projects in it s
calculation of its base amount .under section' 41(c) (4) (3) if an y
of the claim projects constitute qualified research under section
41(d), whether the claimed costs of supplies and wages
attributable to those projects (claimed costs)-are qualified
research expenditures under section 41(b)- (QREs) ; and (4) if any
of the claimed costs are QREs,`whether petitioner included all
similar costs in its base amount calculation .
FINDINGS OF FAC T
I .
Overvie w
Some of the facts have'been stipulated and are so found .
The stipulated facts and the accompanying exhibits are
incorporated herein by this reference .- .A.
Petitione r
Union Carbide' `Corp . (UCC) was the `parent corporation of a~
.group of corporations
.(collectively, petitioner) that filed
consolidated Federal income tax returns for the'years ending
December 31, 1994 and 1995 . UCC-is`a corporation organized and
.
existing under the laws of the State .of New York . At the, .time
the petition was filed ; UCC maintained its principal corporate
office in Danbury, Connecticut . "
r
- 10 -
At, all relevant times petitioner was .a worldwid e
manufacturer and marketer of basics chemicals and plastics and
specialty and intermediate chemicals . Petitioner conducted its
operations at large-scale production facilities . throughout the
United States and abroad .
Petitioner's basic chemicals and plastics (C&P) operations
involved the processing of raw hydrocarbon feedstocks-principally ethane, propane, and naphtha--into basic buildingblock chemicals known as olefins . Ethylene and propylene .. were
the major olefins UCC produced and were key raw materials for
petitioner's olefins-chain C&P businesses .
Petitioner used process technologies . to convert manufactured
and purchased ethylene and polypropylene into first-line
derivatives such as : . (1) Polyethylene, which'is .used for highvolume applications such as food-containers, milk and water
bottles, grocery and trash bags, . pipes, and tubing ; (2)
polypropylene, which is used for similar high-volume
applications ; and (3) ethylene oxide/glycol and derivatives,
which are used for products such as automobile antifreeze,
polyester resin, and film and as raw materials for petitioner's
specialty and intermediates chemicals business .
Petitioner's specialty and . intermediates chemicals
operations involved the production of a, wide variety of specialty
chemical and polymer product lines, as well as solvents and
s
- 11 -
chemical intermediates . During the credit years petitioner also
licensed its key olefins-based process technologies, such as the
UNIPOL process for manufacturing, polyethylene, to third parties
in the oil and gas petrochemical industries .
During the credit years UCC maintained research and
development (R&D) technical centers in South Charleston, West
Virginia (South Charleston) ; Tarrytown, New York ; Bound Brook,
Edison, and Somerset, New Jersey ; and Cary, North Carolina . UCC
carried out process and design engineering at the technical
center in South Charleston .
On February 6, 2001, UCC merged into a wholly owne d
subsidiary of Dow Chemical Co . (Dow) .
B .
Procedural Histor y
UCC, . as the common parent of petitioner's consolidated
group, timely filed consolidated Federal income tax returns for
the years at issue on Forms 1120, U .S . Corporation Income Tax
Return .
On its 1994 and 1995 Federal income tax returns (returns),
petitioner claimed research credits of $14,100,887 and $4,053,901
for 1994 and 1995, respectively (original returns research
credits) . UCC elected the reduced research credit under section
280C(c)(3) on its 1995 return, but not on its 1994 return .
In computing the original returns research credits,
petitioner included the following amounts as QREs for 1984
12 through 1988 attributable to UCC,(UCC's original returns base
period QREs) :
Year
UCC's Original Return s
Base Period ORE S
1984
$68,503,72 2
1985
64,742,82 8
1986
48,107,16 9
1987
52,170,49 2
1988
70,499,62 2
Total
304,023,83 3
UCC's original returns base period QREs for 1984 through 1987
were drawn exclusively from UCC's R&D technical centers . 'UCC's
1988 original returns base period QREs were drawn from UCC's R&D
technical centers except for $1 .9 million attributable to UCC's
G-1750 reactor at its Seadrift facility in Texas (Seadrift) .
UCC's annual gross receipts for the base period were a s
follows :
i
Year
UCC's Annua l
Gross Receipt s
1984
$2,737,545,15 0
1985
2,440,721,12 6
1986
2,976,592,77 8
1987
3,547,163,93 8
1988
5,033,745,12 8
Total
16,735,768,120
13 UCC's annual gross receipts'for 1990 through 1994 were as
follows :
Year
UCC's Annua l
Gross Receipt s
1990
$4,010,083,91 3
1991
3,724,913,91 0
1992
3,608,486,05 4
1993
3,617,655,79 9
1994
3,789,545,36 1
On March 22, 1999, respondent timely mailed'a notice of
deficiency to petitioner determining income tax deficiencies of
$20,481,520 and $140,732,254 for 1994 and 1995, respectively .
The parties negotiated an agreement that resolved most of
the issues raised in the notice of deficiency . Respondent
allowed petitioner's original returns research credits as part of
the negotiated agreement .
Petitioner alleges in its petition, as amended, that it is
entitled to additional claimed credits of approximately
$3,656,091 and $4,726,'664 for 1994 and 1995, respectively
6
Petitioner's claimed credits are based on 106 projects it
conducted in various units within six manufacturing plants during
the claim years .
6These figures have not been adjusted to reflect the fact
that petitioner has conceded that some of the projects do not
satisfy the requirements of sec . 41(d) .
14 In computing the claimed credits, petitioner, claimed
$56,247,556 and $145,435,822 as additional QREs under section
41(b) for 1994 and 1995, respectively (claimed QREs) . The amount
of claimed QREs for 1995-isfthe full-year amount although
petitioner acknowledges that section 41 does not apply to any
amount paid or incurred after June 30, 1995, and before January
1, 1996, and petitioner will disregard such . .amounts in computing
the amount of additional research credits .to which it is
entitled . On its original 1994 and 1995 returns petitioner
reported the claimed QREs as costs of,goods sold ._ The supply,
items that are in dispute are raw materials used to produce goods
for sale .
For purposes of resolving this action expeditiously, the
parties have agreed to try five of the largest projects
underlying petitioner's affirmative research credit claims .' The
five claim projects are referred to as : (1) The Amoco anticoking
'The parties have not specified how they will proceed as to
the remaining credit year projects . The Court hopes that this
opinion will provide the parties with sufficient guidance to
determine whether additional research credits are available for
those projects . However, .. additional proceedings may be necessary
if the parties cannot agree-on the final disposition of the
remaining projects .
15 project ; (2) the spuds project ;' (3) the sodium borohydride
project ; (4) the UOP GA-155 project ; and (5) the UCAT-J project .
The Court held two special trial sessions in connection wit h
the petition claims . The first addressed the research credit
eligibility of the claim projects, and the second addressed
petitioner's section 41(c) base amount recomputation . Both
parties introduced fact testimony from former UCC employees (i n
some instances, current Dow employees) and opinion testimony from
expert witnesses .
II .
Claim Project s
UCC conducted the claim projects at the Taft Plant (Taft)
and the Star Plant (Star), both of~which were in Hahnville,
Louisiana .9 UCC conducted .. its olefins production at`Taft' s
hydrocarbons unit, which contained two -production,subunits
designated Olefins-land Olefins-2 . During the credit years Taft
was a manufacturing plant that included facilities for'the
conversion of raw hydrocarbon feedstocks such as ethane, propane,
and naphtha into basic olefins such as 'ethylene, propylene, and
butadiene . The Amoco anticoking, spuds, 'sodium bor'ohydride, an d
BPetitioner now concedes that the spuds project is not
qualified research .- However, for reasons discussed below, we
will make an independent determination as to whether the spuds
project constitutes qualified research .
9Following Dow's acquisition of UCC in 2001, Taft and Star
were integrated into a single petrochemical complex referred to
as St . Charles Operations .
16 UOP GA-155 projects .-related to the olefins production process and
were conducted at Taft .
UCC produced film and molding polyethylene resins using
petitioner's low pressure UNIPOL process technology at Star . The
UCAT-J project related to UCC's production of polyethylene resins
and was conducted at Star .
A.
The Olefins Production Proces s
A highly simplified description of the olefins production
process at Taft is that hydrocarbon feedstock is pumped from
storage into pyrolysis furnaces, preheated, and diluted with
steam and then is broken into lighter hydrocarbons through
thermal cracking . Hydrocarbons are any chemical compounds
consisting primarily of carbon and hydrogen . Hydrocarbons may
include 1 to more than 60 carbon atoms and can be gases, liquids,
or solids at normal temperatures depending on-the number of
carbon atoms in the compound . Hydrocarbons are found in
petroleum, coal, and natural gas . Hydrocarbons are significant
sources of fuel and raw materials for the production of basic
petrochemicals .and derivatives such as plastics, rubbers, and
specialty chemicals .
"Cracking" is the process whereby hydrocarbon molecules are
decomposed and recombined into lighter, commercially useful
molecules through the breaking of carbon-to-carbon or carbon-tohydrogen bonds . Cracking can be accomplished through a thermal
- 17 or a catalytic process . UCC's olefins production facilities
employed a thermal process called "steam__cracking",'whereby a
gaseous or liquid hydrocarbon feed is diluted with steam and
heated in a fire furnace . The steam cracking reaction requires
temperatures in the range of 1400 to 1650 degrees Fahrenheit and
ordinarily occurs for less than half a second before being
"quenched", or cooled rapidly, in a heat exchanger or by direct
contact with colder fluid . UCC's heat exchangers are typically
referred to by the acronym "TLE", which stands for "transfer line
exchanger" .' A TLE tubesheet is a flat, circular sheet
approximately 5 feet in diameter that manifolds together many
double concentric tubes each with an inner`diameter of about 1
inch . Water and steam flow through the concentric annulus of
each double concentric tube, and the very high temperature
effluent flows through the center tube . Heat is transferred from
the cracked gas, or "effluent", to the water and steam to quench
the ethylene furnace reaction products . TLEs use the extremely
hot effluent to boil water into high pressure steam that may be
used to power large steam turbine drivers in the product recovery
section of'the plant or for other purposes .
The steam cracking process requires the construction and
maintenance of large, capital intensive, and complex cracking
furnaces to supply the necessary heat . Most of the furnaces at
Olefins-1'and'2 were Lummus SRT (SRT'stands for "short residence
s
- 18 furnaces . A Lummus SRT furnace-consists of a rectangular
time" )
firebox with a row of vertical tubular coils, or "cracking sets",
located in the center plane between two radiating ceramic
refractory walls .
After the effluent is initially quenched in the furnace's
TLE to minimize secondary chemical reactions ,
it is further
quenched through-direct contact with water and / or oil in a quench
tower .
Heavier hydrocarbons, known as "pyrolysis fuel oil", are
separated from the effluent during the quenching process . Th e
cracking ,
quenching ,
and pyrolysis,fuel oil separation processes
occur in the hot section of UCC's olefins production units .
After quenching ,
the effluent enters the recovery section
(or cold section) of the olefins production units . The effluent
is first compressed in a multistage centrifugal compressor to the
pressure required for separation .
Acid gasses such as carbo n
dioxide and hydrogen . sulfide are removed in an acid gas removal
unit during the compression process .
Following compression and acid gas removal, the effluent is
dried, chilled ,
and partially condensed . It then proceeds
through a separations train whereby ethylene ,
butadiene ,
propylene,
and byproducts are fractionated and recovered in a
series of distillation columns and related equipment .
Distillation is performed in a column through the,
application of heat from a reboiler at the column's base and the
I
19 removal of components in a condenser at the column's top . The
lighter fraction inthe'column feed mixture (the fraction
containing the components of the mixture with the lower boiling
points) is separated according to the lower boiling points
relative to the other chemicals in the mixture and .recovered as
overhead vapor at the top of the column . The heavier fractions
in the column feed mixture exit as "bottoms" through the column's
base .
Olefins-1 and Olefins-2 each had several distillation
columns, including the demethanizer'(C1) column, which separated
methane from less volatile components ; the deethanizer
(CO
column, which separated ethylene and ethane from less volatile
components ; the depropanizer (C3) column,-which separated
propylene and propane from less volatile components ; and the
debutanizer (C4) column, which separated crude butadiene, butane,
and other four-carbon compounds from less volatile components .
The units also included an ethylene fractionator, which separated
ethylene from ethane, and a propylene fractionator, which
separated propylene from propane, as well as several other
columns .
-
Recovered methane and hydrogen were used primarily as fuel
gas . UCC typically supplied recovered ethylene, propylene, and
crude butadiene to third parties and/or one of UCC's dedicated
olefins-derivatives units . UCC also recovered and sold certain
20 -
byproducts of the olefins production process, such as acetylene,
dripolene (pygas), and fuel .oil . Ethane and propane recovered in
the process were, recycled through the process to extinction .
B . .
The Amoco Anticoking Project
1.
Overview of Cokin g
Coke is a heavy, hard, and relatively brittle form of carbon
that gradually forms on the interior walls of cracking set coils
during the cracking process . The cracking reaction produces two
types of coke, "catalytic" and "thermal" .10 Catalytic coking is
caused by the reaction between active metal sites on the inner
furnace tube walls and hydrocarbon, molecules in the cracked
furnace gas . Thermal coking gradually forms as a result of the
reaction between catalytic coke and the highly reactive products
in the cracked furnace gas . Time and temperature combine to
remove the hydrogen from the hydrocarbon molecules ; ., forming
thermal coke .
Coke buildup adversely .influences-furnace performance in a
number of ways . Coke insulates the furnace tubes . from the
inside, impeding effective heat transfer from the furnace walls
to the gas within the cracking sets . This gradually increases
the skin temperature of the coils to the mechanical limit,
approximately 2,000 degrees Fahrenheit . Coil coking also close s
"There are other coke formation theories that are not
relevant here .
-Y
21 off the flow cross'-section area within the cracking sets and
thereby causes the hydrocarbon partial pressure (the pressure
exerted by the hydrocarbons within the gas mixture) to increase .
Higher partial pressure in the coils reduces the desired ethylene
yield from the furnace .
Coke also accumulates in the TLEs, located immediately
downstream from the radiant section, and the accumulation can
lead to higher hydrocarbon partial pressures and TLE exit
temperatures . Higher pressure in the TLEs caused by coking also
reduces the desired ethylene yield from the furnace .
Because of these effects of coking on furnace operation, the
cracking sets must be decoked periodically . UCC generally
decoked the furnaces in Taft's hydrocarbons unit every 30 to 60
days through a process in which air and steam were fed into the
cracking sets at elevated temperatures (hot decokes) . After
approximately three to four hot decokes, UCC brought the furnaces
down for an extended "cold turnaround" in which damaged cracking
sets were replaced and coke was manually removed from the TLE
system . Hot decokes and cold turnarounds necessarily resulted in
maintenance costs and lost production . Inhibiting coke formation
could result in reduced maintenance, longer furnace run times,
longer equipment life, and increased productivity .
- 22 2 . .
The Coke Reduction Program and Amoco's Technolog y
Before and during the credit years UCC's hydrocarbons,R&D
group had in .,place a coke reduction program aimed at achieving
economic and productivity improvements by implementin g
technologies designed to reduce or eliminate coke in UCC's
ethylene_furnaces . . .Because-,of the inefficiencies .caused by coke,
finding ways to .reduc .e or eliminate coke was an important
objective of UCC's hydrocarbons business . The goal of the coke
reduction,program was to ; reduce the number of decokes per year by
50 percent and-increase productivity by 4 to 4 .5 percent per
year . If successful, .UCC estimated,that this would reduce its
decoking costs by $2 .4 million per . year and increase revenue b y
as much as .$20 million .
Many coke'mitigation technologies . have been proposed and
developed in laboratories over the years, but none have succeeded
commercially . Some, failed to mitigate coke or even made it
worse . UCC screened and commercially tested numerous anticoking
technologies in the mid-1980s and later . During the,credit years
.there was no known, generally accepted, commercial coke
mitigation technology,for pyrolysis furnaces . UCC considered at
least-four technologies during the credit years but tested only
technology developed by Amoco Chemical Corp . .(Amoco) during that
period .
i•
- 23 One of UCC's senior engineering scientists, David Milks,
approached Amoco regarding its anticoking technology in `January
1994 . Dr . Milks operated out of the South Charleston technical
center . On January 21,`1994, Amoco's anticoking technolog y
manager wrote to UCC'regarding an Amoco-developed furnace
anticoking technology that would mitigate coke formation and
extend furnace run times between decokings .' ,Amoco's technology
involved the' pretreatment of the interior walls of~the cracking
sets with a solution of dithiophosphoric acid derivative . Amoco .
claimed that the pretreatment bonded to the sites of the tube
walls that promote catalytic coke formation and "poisoned" these
sites for several furnace 'runs to-prevent coke buildup . Amoco,
told UCC that its anticoking technology had been successfully
tested in a-pilot plant and two commercial plants and that the
treatment had been shown to survive multiple decokes . After
reading about the science behind the technology, Dr . Milks
believed that it was theoretically sound but not yet proven .
Both Dr . Milks and Amoco were interested in'testing the
technology `on,UCC's facilities .
Several UCC employees formed the Amoco anticoking technology
test team to evaluate the technology on one of the furnaces at
Olefins-2'and to provide a recommendation as to whether UCC
should license the technology and implement it on all of its
furnaces atTaft and other UCC plants . William Hyde, an
24 operations improvement engineer, , at . Taft, was the team leader . As
the team leader, Mr . Hyde prepared a charter for the team,
evaluated the technology to . determine,whether it was worth
testing, and coordinated the testing of the technology .
Amoco's anticoking technology included the treating chemical,
and a specialized method of, application . Unlike prior decoking
technologies that,_UCC had tested, which involved the continuous
injection of an anticoking,chemical, Amoco's technology was a
pretreatment to be appliedto a clean furnace before introducing
the feed .
,
Because of the proprietary nature of the technology, Amoco
required the protection of a secrecy agreement before disclosing
its .process to UCC .I On or about November 23, 1994, UCC entered
into an agreement with Amoco . relating to Amoco's anticokin g
technology (the secrecy agreement) . . The secrecy, agreement was
the only agreement UCC entered into with Amoco regarding Amoco's
anticoking technology . 'According to,the secrecy agreement, UCC's
goal in conducting the Amoco anticoking project was to evaluate
the technical and economic feasibility of Amoco's process and
equipment for inhibiting coking in UCC's ethylene furnaces . UCC
also wanted to determine whether, it was interested in a-licensing
arrangement with Amoco . UCC's rights in Amoco's technology were
limited to these purposes . The secrecy agreement obligated UCC
to provide Amoco with a nonconfidential summary of,the Amoco
T
25 anticoking technology's performance no later than'3 months after
testing was completed . UCC gained'no rights in, or licenses to,
any Amoco patent, but'the secrecy agreement contemplated that the
parties could enter into a licensing agreement after the testing'•
was completed .
3 .
The Amoco 'Anti coking Projec t
At the beginning of the Amoco anticoking project UCC was
under the impression that the Amoco technology was fairly
established and beyond early developmental'stages but that it
would still require some testing before it was proven technology .
Except for the fact that UCC was testing the Amoco technology,
UCC intended to continue its ethylene production process as usual
without decreasing production during the Amoco anticoking
project .
UCC worked with Amoco to draft a test plan that specified
the number of test runs (runs), the run lengths what would be
measured, and the method of injecting the inhibitor . The run
lengths would be determined by "furnace cycles", the amount o f
time the furnace .would`run between hot decokes under norma l
operating conditions . The test plan called for the-collection of
data over four consecutive furnace cycles .- The testing would
begin on furnace 24 in Taft's Olefins-2'unit . The test plan
provided that Amoco would apply the inhibitor to four of the six
coils in the furnace so .that the coke formation could be compared
26 between the treated cracking, sets and the untreated cracking
sets . The test plan provided that treating four of the six coils
would ensure that the test results would not be affected .by
differences between furnaces or operating conditions .
The test plan called for the collection of various
measurements during decokes, including furnace coil skin
temperature, pressure drop across the coils, TLE inlet pressure,
carbon monoxide, carbon dioxide,,and .phosphine . Except for
phosphine, these measurements are affected by coke formation . .
Phosphine is a toxic substance that can be produced when
phosphorous-containing materials are used . as coke inhibitors .
To prepare for the test, Mr . .Hyde prepared a Facility
Operational Change Review (FOCR) for the project . An FOCR is a
document that is prepared by the operations personnel when a
significant .operational change is . to take place . It generally
addresses technical, quality, health, waste, and safety issues
that must be considered before the change .is implemented in order
to minimize any risks involved . Jason Tregre, a Taft hydrocarbon
R&D technology manager, participated in the prestartup safety
review on furnace 24 . As part of the test preparation UCC also
manufactured and installed nozzles according to design
specifications provided by Amoco . Among the other final test
preparations were several discussions with Amoco representatives
27 and a walkthrough at Taft on November 7, 1994, in which Amoco an d
UCC personnel reviewed the pretreatment application procedures .
On or about November,28, 1994, after a hot decoke, four of
the six cracking sets were treated . . Amoco personnel worked with
UCC's plant operators to apply the.treatment using Amoco' s
equipment . Amoco provided the treatment free of charge and
agreed to pay any overtime for additional time that UCC's
employees would be required . to work . The treatment was completed
on November 30, 1994 . After the pretreatment was complete, UCC's
plant personnel returned the furnace to normal operating
conditions .
UCC paid for the feedstocks .and fuel gases used during the
project as well as the normal wages of the UCC employees involved
in-the project . The supplies used for the project were the same
supplies that UCC used for normal operations, and UCC sold the
materials produced during the Amoco anti coking . project in the
ordinary course of its business . . The Amoco .anticoking project
did not disrupt UCC's normal manufacturing processes or products .
After-the pretreatment was applied, UCC's plant personnel
took various measurements, including the following, some of which
were not normally taken and others of which were not normally
taken as frequently :
I°
- 28 Measuremen t
Taken
Furnace coil
skin .
Frequenc y
During Test
Once per day
Normal
Frequenc y
Once every 1
to 3 day s
temperatur e
Radiant coil
pressure drop
At least once
per day
Not normally ,
measure d
TLE inlet
Continuously
Continuousl y
Carbon monoxide
Not specified
Not normall y
measure d
Carbon dioxide
During the
decoke
Not normall y
measure d
Hydrocarbon and
Every 6 minutes
Not specifie d
steam flows
for the first 7
pressur e
days, hourl y
thereafte r
Phosphine
Not specified
Not normall y
measure d
Some of these measurements were collected-on the Olefins-2 unit's
process computer, and others were collected manually .
UCC took measurements for approximately 45 days, then
performed a hot decoke of furnace 24 in January 1995 .
Throughout the project UCC continued to decoke furnace 24
according to the plant's, normal schedule . UCC restarted the
furnace on or about January 15, 1995, without retreating the
furnace and continued to take measurements for about 9 days
thereafter .
Dr . Hyde compiled these measurements and sent them to Dr .
Milks and Dr . Husebye, a researcher in the hydrocarbons R&D group
29 at the South Charleston technical center . Dr . Husebye
reformatted the data and analyzed them . Dr . Husebye did not
typically perform this type of analysis . UCC did not share the
data it collected with Amoco . "
Dr . Husebye and Dr . Milks documented the results of the
first Amoco pretreatment' in a report dated February 21, 1995 .
The report covered approximately 7 weeks of furnace 24' s
operation . The results showed that carbon monoxide 'in the
treated cracking sets was initially reduced, indicating
successful coke inhibition . However, after the first hot decoke
and restart of furnace 24, there was no statistically significant
difference in the amount of carbon monoxide in the treated versus
untreated cracking sets . Dr . Milks and Dr . Husebye hypothesize d
that the hot decoke that was performed before the Amoc o
pretreatment was applied might have been incomplete and the
pretreatment might not have survived the first hot decoke
following the pretreatment . The .results,from the other
measurements were either inconclusive or indicated no difference
between the treated and untreated cracking sets .
Because the results from the first pretreatment were
inconclusive, Dr . Milks and Dr . Husebye recommended a secon d
pretreatment with the Amoco technology 'after a thorough col d
"Respondent argues that UCC did share data it collected
with Amoco, and there is conflicting testimony on this point ;
However, this fact does not control our decision . .
I
30 turnaround . Amoco personnel applied the second pretreatment in
April 1995to four of the six cracking sets . UCC personnel
gathered the same data following the second pretreatment as they
had gathered following the first pretreatment, and Dr . Husebye
analyzed the data . While .. UCC did not retain its analysis of the
second pretreatment, it did retain archived computer records that
included data collected after the second pretreatment that could
be used to reconstruct the original analysis .
Following the second pretreatment, the initial carbon
monoxide levels in the treated cracking sets were again
significantly . lower than the carbon monoxide levels in the
untreated sets . However, after the hot decokes of furnace 24 in
May and June 1995,_the carbon monoxide levels in the treated and
untreated cracking sets were nearly identical . The results from
the second pretreatment, as a whole, indicated that the Amoco
technology did not . inhibit coke formation in furnace 24's treated
cracking sets during the runs conducted between April and midAugust 1995 .
On August 21, 1995, a furnace operator participating in a
cold turnaround of furnace 24 observed that the TLE cones
connected to the treated cracking sets had significantly greater
amounts of coke deposits than the TLE . cones connected to the
untreated cracking sets . This was unexpected, and UCC believed
- 31 that the pretreatment may have contributed to-the excess coke in
the TLE cones .
During-the cold turnaround UCC removed tube samples 'and coke
samples from furnace 24 to be - tested . UCC ' s corrosion and
machinery engineering department evaluated - the samples and
documented the results of its analysis in a formal project
report . This report included the results of several
performed on the samples ,
tests .
:
analyses'of those tests, and
recommendations for future tests of the Amoco technology . UCC
did not prepare any other formal project reports to specifically
document the results of the second pretreatment .
However, UC C
reported the results of the - two pretreatments in . several informal
reports and memoranda . '
UCC considered the Amoco anticoking project
to-be finished
in August 1995, and UCC never again tested the Amoco technology
in any of its ethylene furnaces :
UCC later'discovered that the
problem might have been caused by a mistake on Amoco's part in .
establishing the feed rate or the quantity of inhibitor to be fed
to the furnaces .
This indicated to UCC that - Amoco's technology
was more developmental than UCC originally believed it to be .
UCC never entered-into a licensing agreement with Amoco to us e
its technology .
UCC used the information gathered during the Amoc o
anticoking project primarily to determine that Amoco ' s technology
3,
32 did not effectively reduce coke formation in its commercial
facilities . UCC also learned about the operation of
thiophosphates (the active ingredients in the Amoco technology),
the relationship between sulfur and carbon monoxide levels, and
the effect of anticoking technology on the ceramic material on
TLE cones . UCC used this information in the course of its
business .
Mr . Hyde,spent 35,hours in 1994 and 10 hours in 1995 working
on the Amoco anticoking project . Mr . Tregre spent 5 hours
working on the Amoco anticoking project in 1994 .1 2
C.
The Spuds Projec t
1.
Overview of the Spuds Projec t
The spuds project involved replacing four-hole spuds with .
one-hole spuds . on . furnace 3 in,Olefins-1 at .Taf.t . The-one-hole
spuds-were installed on furnace 3 on or about January 13, 1995 .
A burner is a device that provides radiant heat in
a
pyrolysis furnace through controlled combustion . . . In a pyrolysis
furnace, combustion is intended to provide .a uniform temperature
to the fired radiant wall, allowing for even heat flu x
distribution to the cracking set coils . :
12Petitioner does not claim as QREs any wages paid to Dr .
Milks or Dr . Husebye, who operated out of the South Charleston
technical . center . Their wages would have been included in
,petitioner's original returns research credits .
33 The furnaces in Olefins - 1 each had 112 radiant wall burners .
The burners are mounted through the furnace radiant wall and
produced a thin, flat circular disk of flame adjacent to the
wall . The burners were equally spaced in a grid pattern and
radiated heat to the process tubes on the centerline of the
furnace . Each burner had a single spud . '
A spud is the orifice or port through which fuel gas flows
into the burner .
It resembles a bolt with one or more holes at
the end . Spuds are installed at the piping terminations of each
burner and affect fuel flow and pressure .
Spuds function to
equally divide the amount of fuel being injected to each burner
so that the heat released from ° the'burners is evenly and
predictably distributed throughout all of the burners in the
firebox .
The size and number of spud orifices determine the
pressure of the fuel gas just upstream of the orifice and the
exit velocity of the
fuel-gas from 'the orifice, parameters known
as "flow characteristics" .
Flow characteristics of the spuds
help determine the burner firing capacity, which is the British
Thermal Unit
( BTU) per hour heat output generated by a single
burner, flame stability, and fuel efficiency .
As fuel gas passes
through the spud it produces a high velocity gas jet, which
entrains combustion air and mixes it with the fuel . The amount
of air that mixes with the fuel is critical to the stability of
the flame .-
- 34- When it was first built in the 1960s, Olefins-1 used one
hole spuds until it was-moth-balled in the 1980s . When it was
restarted in-1989,,Olefins-1 switched to four-hole spuds in order
to reduce noise . The four-hole spuds were prone to plugging, and
UCC typically cleaned the spuds during furnace shutdowns by
poking them with pieces of wire . Plugging of spuds,may also be
improved or eliminated by cleaning the fuel gas system, removing
contaminants in the fuel gas, setting up a . regular maintenance
schedule for removing and cleaning the-spuds, or increasing the
size of the orifice(s) in the spuds . Some of these methods may
be .costly,and/or labor intensive, . : While replacing multihole
spuds with one-hole spuds without changing the-total area of the
holes was a known method of reducing plugging, one-hole spuds
cause significantly more noise than multihole spuds and therefore
cannot always be used .
The Taft hydrocarbons unit identified fuel efficiency as an
area .for operational improvement . In October 1994 the_John Zink
,Co . conducted a combustion survey of,Taft's hydrocarbons unit .,
.The John Zink Co . is a large ethylene burner manufacturer that
manufactured the burner used on furnace 3 . 'Burner manufacturers
generally use their test furnaces to evaluate new spud designs
because testing new-spuds in a commercial furnace can be
hazardous and the costs,are .unreasonably high . However, once a
spud design is proven, it generally performs better on commercial
35 furnaces than on test furnaces because the higher heat content in
a commercial furnace results in more stable flames .
Testing and
evaluating a new spud on a test furnace takes about a'day or
less .
Following the survey ,
the John Zink Co . recommended using
one-hole spuds instead of four-hole spuds in'the • Olefins-l
furnaces to reduce plugging .
UCC had been using one - hole spuds
in its Olefins - 2 furnaces since the late 1970s and noticed that
Olefins-2 had not experienced any plugging problems .
However ,
UCC was concerned about changing to one-hole spuds because the y
might create too much noise . Olefins-1 and 2 were physically
different ,
and noise was more of a concern at Olefins - l than at'
Olefins-2 .
However, noise was not a major concern because the
plant personnel already wore hearing protection .
UCC followed the John Zink Co .'s recommendation to try
switching from four - hole-spuds to spuds with one hole with the
same total hole area .
three furnaces ,
UCC decided to purchase enough spuds for
which would cost $3,400 to $3,700 per - furnace .
UCC believed that this was a relatively inexpensive way to solve
the plugging problem . UCC intended to test the' new spuds on one
furnace ; and if the test was successful ,
then UCC would
immediately begin replacing'the spuds on two other furnaces .
To test the new spuds ,
UCC planned to monitor performance
data such as : (1) The fuel - to-feed ratio
( BTUs of fuel per point
- 36 -
of feed), (2) excess oxygen in the fuel gas, (3), the amount o f
combustibles in the fuel gas, and (4) fuel pressure . UC C
intended to evaluate the fuel efficiency improvements b y
measuring BTUs in a process computer, measurements that were
available-regardless of whether a test was being performed . The
goals of the test were to determine whether the new spuds would :
(1) Stop or reduce plugging ; (2) increase efficiency, and if so
by how much ; and (3) .increase noise, and if so by how much . Mr .
Tregre was involved in this planning .
UCC did in fact take the above test data on furnace 3 fo r
about .90 days . Mr . James Gorenflo, a furnace technician, was
involved in testing furnace 3 . UCC monitored plugging by
checking fuel pressure gauges . The results showed that pressur e
was not increasing, which indicated-that the new spuds solved th e
plugging problem . UCC also evaluated fuel efficiency by
analyzing . measurements of fuel gravity and the fuel-to-feed
ratio . Mr . Tregre was .involved in this evaluation . The results
showed that fuel efficiency improved, although not as
dramatically as UCC had hoped .
Because the one-hole spuds solved the plugging problem, UCC
installed one-hole spuds on all of its . furnaces at Olefins-1
after the 90-day test period was over . While,UCC hoped that the
change would increase fuel efficiency more, the fact that the
- 37 .one-hole spuds solved the plugging problem was sufficient
justification for changing the spuds .
Mr .,'Tregre spent 70 hours in 1994 and 10 hours in 1995
working on the spuds project .- Mr . Gorenflo spent 10 hours in`
1995 working on the spuds project .
2 .
Petitioner's Motion for Leave To Amend Its Petition
On January 19, 2007,
petitioner filed a motion for leave to
amend its petition . If filed' the amended petition would have :
(1) Withdrawn petitioner's affirmative claim for additional
research credits under section 41 to the extent it was based on
the spuds project, (2) adjusted the claimed QREs to reflect the
withdrawal of the spuds project, and (3) applied the .correct'
credit rate for 1994 . Respondent opposed this motion because the
Court had already held a trial on'the"claim projects, including
the spuds project . Giver] the' substantial cost of litigation,
respondent argued that he would be prejudiced if the Court was,
prevented from rendering a decision on whether'the spuds project
satisfied the criteria for qualified research . In addition, to
the extent that'petitioner claimed additional research credit s
for projects similar to the spuds project :that were not litigated
in the claim year trial, respondent argued that he would be
prejudiced by the absence of a decision on whether the spudsproject constituted qualified research .
- 38 Following a . hearing on this motion on August 29, .2007, w e
denied petitioner's motion because we found that it would b e
unfair to allow petitioner to unilaterally alter its agreement
with respondent to hold a trial on the five claim projects .
D .
The Sodium Borohydride Projec t
1 .
Overview of the Acid Gas Removal Syste m
The sodium borohydride project involved the,injection .of a
sodium borohydride solution into .the Olefins-2 caustic scrubber .
The Olefins-land-Olefins-2 acid-gas removal systems remove,
carbon dioxide and hydrogen sulfide from cracked furnace gas .
Acid gases are impurities that .can cause operational problems in
downstream plant equipment . Acid gas removal is also necessary
to meet product specifications ..
The acid gas removal system consists of a regenerative
monoethanolamine (MEA) system followed by a . caustic scrubber .
Cracked furnace gas is fed into the MEA .system, .where it is
washed with a countercurrent flow of . amine solution that removes
the bulk of acid gases . As an incidental benefit the MEA system,
removes the impurity acetaldehyde from the•cracked furnace gas .
Acetaldehyde is .a highly reactive compound created in trace
quantities during the thermal cracking of hydrocarbons in the
presence of steam . It is formed in the furnaces through the
interaction of free radicals from steam and ethane or other raw
materials . Acetaldehyde can polymerize and foul plant equipment .
- 39 After being treated by the MEA system, the cracked furnace
gas passes through a two-stage causticscrubber for removal of
residual acid gases . The caustic scrubber is sized so that it
can reduce acid gases to specification levels even when the MEA
system is shut down .
The MEA systems . in both Olefins-1 and Olefins-2 had to be
periodically shut down and manually cleaned-because of'the
fouling of heat transfer surfaces partially caused-by
acetaldehyde polymerization . Fouling'is the-deposition of heavy
organic solids that were dissolved-in process fluid . When one o f
the MEA systems is down, the cracked furnace gas passes through
only the caustic scrubber for "acid-gas' removal . The causti c
scrubber,
however, does not remove acetaldehyde.
Taft's MEA
systems ordinarily ran-from-3 to 6 months between shutdowns ,
depending on the feedstocks used and furnace cracking conditions . .
Cleaning the MEA system` normally took about 14 days .
In the early 1990s UCC produced at its Taft plant'-a
hydrocarbon product called 'crude butadiene . Crude butadiene is
highly reactive and is'a major contributor to fouling in the
olefins process equipment . When'the MEA system was shut down and
only the caustic scrubber was used to remove acid gases, some .
acetaldehyde would 'leave-the process with the crude butadiene .
In 1994 Shell Oil Co . (Shell) was Taft's primary customer
for crude butadiene .' At'the time, Taft stored crude butadiene in
i
40 two storage tanks and transported it, in barges to Shell, which
operated a plant directly across .the Mississippi River from Taft .
Shell, had a product specification . limiting the amount of
acetaldehyde in Taft's crude butadiene to 100 parts per million
(ppm) because acetaldehyde would foul .Shell's processing
equipment . On one occasion in the summer of 1994, UCC
manufactured crude butadiene that did not meet Shell's
acetaldehyde specification . Shell refused to accept a barge
shipment of that crude butadiene and returned it to Taft .
When the MEA system, was in service, acetaldehyde levels in
Taft's crude butadiene were well below 100 ppm . However,
acetaldehyde levels reached between 5 0 0 and 800 ppm when the MEA
system was shut down . One method that UCC used to bring offspecification crude butadiene within specification levels was
called "blending" . UCC would store off-specification crude
butadiene and then blend it with on-specification crude butadiene
when the MEA system was restarted . ,
However, when the amount of off-specification crude
butadiene exceeded UCC's available storage capacity, UCC would
have to attempt to recycle the crude butadiene or find a
purchaser who would accept it as it was . Another problem of
.
blending was . that it was difficult to calculate the amount of onspecification product needed to,blend with the off-specification
product . UCC was also considering building a pipeline directly
41 -
from Taft to the Shell plant, which would reduce or eliminate the
need for storage tanks and make blending impractical . Therefore,
UCC did not view blending as a permanent solution to the problem
of off-specification crude butadiene .
2 .
The Sodium Borohydride Projec t
Because of the shortcomings of blending, UCC sought a way to
remove. acetaldehyde from crude butadiene during the periods that
the MEA system was shut down for maintenance . UCC decided that a
possible solution was to add sodium borohydride to the caustic
scrubber to remove acetaldehyde when the MEA system was shut down
for maintenance .
In February 1995 UCC considered using sodium borohydride
regularly to remove acetaldehyde if using sodium borohydride
.proved to be effective . UCC knew that sodium borohydride was
effective in removing aldehydes, including acetaldehyde, as UCC
had been testing sodium borohydride in laboratories for'such
purposes as early as 1961 . UCC and its competitors had
successfully used sodium borohydride in commercial processes to
remove acetaldehyde and other carbonyl compounds from products .
However, UCC did not know how effectively sodium borohydride
could remove acetaldehyde in the caustic scrubber . Liquid sodium
borohydride was often used to remove acetaldehyde from other
liquids, but in the caustic scrubber UCC would need to use liquid
sodium borohydride to remove acetaldehyde-from a gas . The
42 interaction of a liquid with a gas is much more difficult to
predict than the interaction of a liquid with other liquids .
UCC also knew that sodium bisulfate could be used to remove
acetaldehyde .
However, UCC would have had to use a 'higher
concentration of sodium bisulfate than sodium borohydride to
effectively remove acetaldehyde ,
and sodium bisulfate was more
difficult to work with than sodium borohydride .
On October 10, 1994, Mr .
George Brandon ,
a senior , production
specialist at Taft, initiated an FOCR for injecting sodium
borohydride into the caustic scrubber in Olefins - 2 . According to
the FOCR, the purpose of the project was to run a test to
determine whether sodium borohydride could be used to remove
acetaldehyde when the MEA . system was shut down .
An R&D report dated January 9 ., 1995, prepared by Robert
Manyik, a consultant in the hydrocarbons R&D group, was attached
to the FOCR .
In the R&D report Dr . Manyik proposed a plant test
to add sodium borohydride to the, caustic scrubber when the MEA
system was down in order to remove acetaldehyde to onspecification levels . UCC would use a,sodium borohydride
solution called VenPure , . sold by Morton Performance Chemicals
(Morton ) .
The R&D report addressed whether such a test was
feasible ,
identified potential . hazards that could arise during a
test, and provided the necessary technical information that would
be needed to conduct the test . The R&D report specified the
43
equipment that was available, how much sodium borohydride UCC
would purchase, the rate at which the sodium borohydride would be
added, and the benefits and .drawbacks of diluting the sodium
borohydride . The FOCR also included a diagram illustrating ho w
the sodium borohydride would be injected-and a memorandum setting
out, in question and answer format,-the duration of the test, the
controls that would` be monitored, whether the sodium borohydride
would be diluted, the physical configuration of the injection
equipment, operation temperatures and pressures for the injection
equipment, and UCC's plan to prevent the buildup of salt
precipitates .
One of the departments that reviewed .the FOCR was,Taft's
Environmental Pollution Department (EPD) . The EPD endorsed thesodium borohydride project provided that certain . conditions were
met . These conditions were that the EPD would sample and monitor
the plant's wastewater for the presence of boron 2 weeks before,
during, and 2 weeks after the test,` and the use of sodiu m
.borohydride would .be immediately terminated if'-the monitorin g
indicated that the wastewater quality was beginning t o
deteriorate . The EPD was concerned -that,large- amounts of boro n
might enter the wastewater system and disrupt the wastewater
treatment . Another condition that the EDP imposed was that the
injection rate would not exceed 5 pounds per hour ; and if the
- 44 -
plant was required to increase this ; rate, it would seek approval
from the EPD at that time .
Approval from UCC' s R&D department was also . necessary before
beginning the project because it involved the introduction of a
new chemical to the process . UCC wanted to .ensure that the
change was .safe and that there would be no adverse consequences
to the plant process from the injection of sodium borohydride .
The R&D department approved the sodium borohydride project on
January 13, 1995, and the engineering department approved the
sodium borohydride project on February 20, 1995 .
UCC believed that a plant test was necessary to determine
whether sodium borohydride would effectively remove acetaldehyde
in an actual caustic scrubber . UCC was uncertain how well the
sodium borohydride would mix with the acetaldehyde because of the
difficulty in modeling liquid-gas interactions . Therefore, while
it was known that sodium borohydride would react with
acetaldehyde in a laboratory or pilot plant setting, .UCC was not
sure how well sodium borohydride and acetaldehyde would react in
a full-scale plant given the plant' s size, .gas flow, and
configuration . Because cracked furnace gas travels quickly
through the caustic scrubber, UCC was unsure whether the
residence time of the sodium borohydride in the caustic scrubber
would give the sodium :borohydride sufficient time to react with
the acetaldehyde and bring the crude butadiene within
45 specification levels .' UCC was also unsure~of the appropriate
rate to inject the sodium borohydride and of the effect the
sodium borohydride would have on the boron concentration of the
wastewater . Because of these uncertainties as to how sodium
borohydride would interact with acetaldehyde, UCC referred to the
sodium borohydride project as a "test run" .
After injecting the sodium borohydride, UCC intended to
monitor the acetaldehyde content of crude butadiene extracted,
from the caustic scrubber . The EPD also planned to monitor the
wastewater for boron content .
The equipment for the sodium borohydride project was
initially installed at Olefins-1 on June 11, 1995,-but the crude
butadiene remained within specification levels when the Olefins-1
unit's MEA system was shut down for maintenance . Accordingly,
UCC moved the equipment to Olefins-2 and conducted the test
there . UCC had a limited amount of sodium borohydride and did
not want to waste it on crude butadiene that was already onspecification . The sodium borohydride project . began in the
Olefins-2 unit on or about June 12, 1995, and ran for
approximately 2 .weeks .
During the test, UCC injected the sodium borohydride
solution into the Olefins-2 caustic scrubber . To inject the,
sodium borohydride UCC used ,a small tote tank (owned- by Morton)
to hold the solution, a small metering pump to inject th e
k
- 46 -
solution, and tubing to connect the tank and the pump to the
process ." Morton recommended an amount for UCC to inject, and UCC
followed that recommendation initially but then made adjustments
as the project progressed . UCC did not regularly record . the .
amount of,sodium borohydride that was injected during the test .
Taft employees monitored the crude . butadiene production from
the Olefins-2 unit's C4 column during, the sodium borohydride
project . UCC measured the acetaldehyde content of the crude
butadiene every 12 hours . UCC normally took these measurements
about three times a week . To take the measurements, plant
operators took samples of,crude•butadiene toTaft's central
quality control laboratory for testing . In addition, Mr . Brandon
measured acetaldehyde levels in thecracked furnace gas entering
and, exiting the caustic scrubber . . To take these measurements,
Mr . Brandon used a device called .a "drager pump and tube system" .
The tubes would indicate how .many ppm of acetaldehyde the cracked
gas contained . Mr . Brandon took . these, measurements at least
daily .for-the duration of the- .project . Mr .-Brandon did not
normally take such measurements . As-planned, the EPD also
monitored the wastewater approximately every 12 hours . The EPD
normally monitored the wastewater weekly unless aspecial .test
was being run .
Mr . Brandon collected and recorded the-results of the crude
butadiene analyses and drager .tube tests and reported the results
47 to Terry Swindle, a Taft engineer assisting with the sodium
borohydride project . Mr . Brandon devoted approximately 200 hours
to the sodium borohydride project . The EPD collected and
recorded the results of the wastewater monitoring and,reported to
Mr . Swindle that the boron was within acceptable limits .
However, the data collected from the sodium borohydride project
were not documented in a final project report . UCC treated the
January 9, 1995, R&D report prepared by Dr . Manyik as the
functional equivalent of a project report even though the report
was prepared before the test of sodium borohydride occurred .
UCC considered the sodium borohydride project to be a
success because the sodium borohydride effectively kept the
acetaldehyde in the crude butadiene production below the 100 ppm
specification level . Accordingly, Taft began to use sodium
borohydride regularly to reduce acetaldehyde
levels when an MEA
system was shut down .
Several years later, UCC discovered that using sodium
borohydride to remove acetaldehyde caused unacceptably hig h
levels of . ethanol, a byproduct of the reaction, in the crud e
butadiene . During the credit years UCC believed that ethanol
would leave the system with the spent caustic and therefore did
not consider whether ethanol would be a problem and did not
measure it . However, the ethanol remained in the crude butadiene
and later caused it to fail Shell's new specifications .
.1
- 48 -
Therefore, UCC began using a new product to remove acetaldehyd e
instead of sodium borohydride .
E .
UOP GA-155 Projec t
1 .
Overview of Fouling . in the C3 Colum n
The UOP GA-155 project involved the injection of an
inhibitor, UOP GA-155, into the C3 column line at Olefins-l- in an
attempt to reduce . fouling, in the C3 column trays and reboilers .
Fouling is a major problem for petrochemical plants .
Consequences of fouling may .include declining performance,
frequent shutdowns of process equipment, loss of operation time,
and increased maintenance costs for cleaning or replacement o f
equipment . ,
Fouling is a particular problem in distillation column
services . Deposit buildup in distillation columns can reduc e
capacity and efficiency by blocking the flow .path and by impeding
the performance of heat exchangers . An ethylene unit can
experience polymer fouling in the CZ, C3, and C4 distillation
columns . . The C3 column typically has the worst fouling problem .
The main function of the . C3 'column was to separate the
propylene and propane (C3 molecules) and heavier hydrocarbons .
The liquid .hydrocarbon .steam entered the C3 column at the
column's midpoint and fell to the bottom where it .was heated by
one of the two reboilers mounted on the column's base . The
lighter C3 molecules were vaporized and captured,at the top of
49 the column, while the remaining heavier components exited the
bottom of the column and traveled on . to the C4 column . The C3
column contained approximately 40 trays that *held the liquid
hydrocarbon stream being processed"so that it could be exposed t o
the vapor generated by the reboiler .
Column .fouling is typically greatest within the reboiler and
also occurs in the trays . One cause of fouling in distillation
columns is the polymerization of reactive components in the
liquid phase of distillation . Polymerization is the linking mof
double bonds'to form long . chain :molecules . Most of the
polymerization is due to the reaction of diolefins and reactive
species such as styrenics .
In the mid-1990s Olefins-l- was experiencing high levels of
fouling in the C3 columns, reboilers, and internal trays caused
by the formation of polybutadiene polymer, a rubbery blac k
substance that adhered to the insides of the-column . `There were
two reboilers mounted to the base of the . C3 column, but only one
operated at a time . The polybutadiene polymer fouled the tubes
in-the operating reboiler and restricted the liquid ; flow . When
the reboiler fouled to .the point that it became inoperable, it
was taken out of service and cleaned, and the clean reboiler was
placed in service . Typically, it took about-2 weeks tto clean a
fouled reboiler and cost about $25,000 .
In 1994 and 1995 the
50 ideal . run time for a reboiler between cleanings was 2 to 3
months .
The polybutadiene polymer also accumulated on thetrays to
the point .-that the vapors rising from the bottom of the column
could not pass through the holes in-the tray . This foulin g
created a high differential pressure .in the column, causing the
column to flood with liquid and become inoperable . At this
point, plant employees would have to shut down the column and
clean it .- In 1994 and . 1995 the ideal run, time for a C3, column,
was approximately 3 years but, depending on the feedstock,
cracking,-and operating conditions, the column would not alway s
run that long . It would typically take about a month to clean a
fouled C3 column and cost about $5,0,000 . occasionally-the entire
olefins unit needed to be shut down when a column cleanin g
occurred .
2 .
Overview of Inhibitor s
An inhibitor is a chemical that is added to a chemical plant
to reduce fouling and increase the time that a particular piece
of equipment will operate before it .needs to be cleaned or shut
down . Olefins plants use two types of inhibitors (1 )
polymerization/oxidation inhibitors and (2) dispersants .
Polymerization/oxidation inhibitors are added to-stabilize
certain products that can polymerize or break down when exposed
to air . Dispersants are added to products to keep impurities
51 suspended in the liquid hydrocarbon stream from 'depositing on
plant surfaces and fouling- them .-An effective inhibitor will
improve column and reboiler run length times and will not cause
any additional problems in the plant .
UCC used about 12 different inhibitor s hibitors,in its-olefins
manufacturing processes at any particular time in the early
1990s . `In 1994 and 1995 UCC used-different`inhibitors in its
olefins manufacturing units because an inhibitor- that works well
in one olefins plant may not necessarily work well in another
olefins plant . Because equipment differs from plant to plant, an
inhibitor might have 'a different residence time or different
contact times in different columns . 'In addition, flow rates,
pressures, and temperatures, which all affect the operation of an
inhibitor, differ from' plant to' plant .
The vendors from whom UCC . purchased inhibitors-tested the
inhibitors in laboratories to verify ., that' they would in fact
inhibit-polymerization or oxidation . However,, UCC could not
determine how well the inhibitors'would work in one .-of its plant s
without testing them in theIplant .' -UCC generally gathered data
when using a new inhibitor and compared that data-to baseline
data to determine whether the inhibitor worked as expected . The
purpose of inhibitors is `to extend the time equipment can be used
before it must be shut down and cleaned . Therefore, one way to
know whether an inhibitor is effective is to compare the,run time
- 52 of a compressor, reboiler, or column operating with the inhibitor
against the preinhibitor run time of the same equipment .
UCC
believed that the test of a new inhibitor should last for about
as long as the vendor claims the equipment .will run with the use
of the inhibitor . UCC also generally used inhibitor tests t o
determine the proper dosage . While UCC believed it was important
to use enough of an inhibitor .for it to be effective, excessive
use of an inhibitor can have adverse effects on the production
process or on the plant's products . Furthermore, becaus e
inhibitors,are expensive, using a higher dosage than is necessary
will reduce the economic . benefit of using the inhibitor .
The hydrocarbons R&D group was generally involved in
decisions to test process inhibitors at UCC's plants because the
tests would involve the introduction of a new chemical into the
plant and could have environmental,,health, and safet y
consequences . R&D was familiar with the chemistries and
processes of the plants and could provide input on whether a new
inhibitor might be,effective in the plant, what dosage levels to
use, how to set up the test plan, and how to measure .the results
of the inhibitor use .
3 .
The UOP GA-155 Projec t
Dripolene was a byproduct of Taft's olefins production
process that flowed out the bottom of the C4 column, the final
column in the .olefins separations train . UCC could not ship
53 .dripolene unless it` was' stabilized with a certain amoun t
polymerization/oxidation inhibitor . Without the inhibitor, the
dripolene could react with oxygen and present an explosion
hazard .
Before undertaking the'UOP GA-155 project, Taft's
hydrocarbons unit had been injecting a stabilizer known as UOP-5
into the dripolene as it flowed out of the C4 column . The active
ingredient of UOP-5 was phenylenediamine . The dripolene from
Olefins-1 and 2 was blended and stored in the same tank, so the
Olefins-1 dripolene was stabilized by the inhibitor injected int o
the Olefins-2 dripolene .
Because cleaning the reboilers and shutting down the column s
was very expensive, UCC was always looking for ways to .-decrease
operating costs by reducing fouling . Mr . Brandon discussed the
problem with members of Taft's hydrocarbons R&D group to try t o
find ways to reduce fouling in the C3 column . Mr . Brandon
approached UOP, a supplier to the petrochemical industry,
t
.determine whether UOP had a product that could be fed directly
into the Olefins-1 C3 column to both reduce fouling and stabilize
the dripolene . UOP reviewed UCC's process stream, operation,
equipment, and operating conditions . On the basis of those
observations, UOP recommended that UCC use UOP GA-155, which
contains phenylenediamine ( .the active ingredient used in UOP-5)
as well as a dispersant . UOP told UCC the approximate
54 percentages of UOP-5 and . the, dispersant contained in U .OP GA-155 .
UOP maintained that UOP GA-155 would operate as an oxidation
inhibitor in the C3 column, the phenylenediamine .would_stabilize
the dripolene, and the dispersant would mitigate fouling in the .
C3 .column . UOPrepresented to UCC that UOP GA-155 ; was effectiv e
in extending process run .length .
.
UCC had not previously used UOP .GA-155 in any of its
facilities and was not aware of any other olefins plants in the
country that had used .UOP GA-155 . However, UOP told UCC that
some of the ingredients in UOP GA-155were industry-wide standard
materials that were being used in olefins plants . . UCC did . not
consider other possible inhibitors~or chemicals because their
cost,was excessive-because they were bundled . with the, purchase of
services that UCC did . not want . . .. .
UCC wanted .to test UOP-GA-155 in its plant because
successful laboratory tests do-not-guarantee that an inhibito r
will be effective .enough in a full-scale plant . to justify its
cost . While manufacturers often made representations .to UCC .
regarding the inhibitors that they were .selling, the inhibitor s
did not always work as represented . .
To test the UOP GA-l55, .UCC planned to inject UOP GA-155
into the C3 column feed instead- of into the dripolene product as
it had done with UOP-5 ., The UOP GA-155 would then flow out of
- 55 the bottom of the C3 column, flow into the C4 column feed, and
flow out of the C4 column and the plant with the-dripolene .
Mr . Brandon initiated an FOCR, numbered 94- .80 (FOCR 94-80),
for moving the equipment that was being used to inject UOP-5 into
the O1-efins-2 dripolene product over to Olefins-'l in order to
inject the,inhibitor into the C3 column feed . UCC hoped that
injecting the inhibitor into the C3 column feed instead of
injecting it into the dripolene as it flowed out of the C4 column
would inhibit fouling in the depropanizer system . Mr . Brandon
initiated another FOCR, numbered 94-61`(FOCR 94-61), for changing
the inhibitor from UOP-5 to UOP GA-155 and injecting UOP`GA-155
into the C3 column feed . FOCRs were generally required whe n
introducing new inhibitors because the introduction of a ne w
inhibitor is a process change . According to FOCR 94-61, the
purpose of the change was to reduce- fouling in the C3-and C4
columns and their'reboilers . The FOCR=listed as concerns thatneeded resolution (1) whether the customers would approve of the
change and (2) whether UCC had a pump that had a high enough
discharge pressure .
Mr . Brandon's supervisor instructed Mr . Brandon to keep the
UOP GA-155 project on hold until the necessary approvals had been
obtained from the hydrocarbons=R&D group, the EPD, and UCC' s
customers .- UCC informed its customers that UOP GA-155 would be
injected into Taft's Olefins-1 production process, and its
- 56 customers, did not object .-The FOCRs were finally approved on
September 22, 1994 .
While Mr . Brandon hoped, that UOP GA- .155 .would increase the
C3 column's run time, he was not certain how effective UOP GA-155 .
would be . Mr . Brandon was also concerned that UOP GA-155 could
actually harm UCC's production process . Specifically, he was
concerned that adding a dispersant to .the'column could cause
existing polymers to loosen from the column walls and trays and
plug the column . If .that .happened, UCC would have to shut down .
the column and possibly the entire, Olefins-1 unit . In addition,
Mr . Brandon was concerned abouttheS :effect that .UOP GA-155 might
have on Taft's commercial products because the UOP GA-155 would,
flow out with the crude dripolene . Because UOP GA-155 would be a
new ingredient in the product, it was possible that it could
adversely affect the downstream olefins . products or cause
problems when fed into customers' production processes .
The injection of UOP GA-155 into the C3 column feed line in .
Olefins-1 began soon after the final approvals were obtained for
FOCR 94-61 and FOCR 94-80 on September 22, 1994 . Th e
hydrocarbons R&D group asked the plant personnel to collect data
during the test . Accordingly, Mr . Brandon collected daily all of
the pertinent data that were regularly recorded on the process
computer system in the Olefins-1 control room, including
differential column pressure, feed flows, .throughput rate, steam
57 temperatures, and steam flows . Differential column pressure is
the measurement of the different pressures across the column
trays from top to bottom .' When polybutadiene polymer accumulate s
on the trays, 'the trays plug and the differential pressur e
increases . While UCC did not normally review ; these measurements'
daily, UCC did monitor reboiler chest pressure when there-were
problems . It was also typical in the industry to measure column
differential pressure when equipment is prone to fouling .
During the test Mr . Brandon also measured and recorde d
111
condensate pressure of'the'reboiler'every day . Neither Mr .
Brandon nor any of UCC's other employees had monitored the
condensate pressure daily before the'UOP GA-155 project . An
increase in condensate pressure is a primary indicator'of
reboiler fouling .
Mr . Brandon and other employees also took samples off'
dripolene and analyzed the inhibitor levels once-per 12-hour' .
shift . Before the'UOP GA-155 project,, UCC's employees had
analyzed the inhibitor levels in the dripolene once a week for
quality control . Mr . Brandon took measurements for approximately
90 days during the UOP-GA-155 project . . -Mr . Brandon also kept
track of reboiler run lengths'both before and during the test
period . Mr . Brandon spent approximately 200 hours in 1994 and
200 hours in 1995 working on the UOP GA-155 project .-
- .5 8
It would take approximately 3 years to determine whether UOP
GA-155 substantially extended the run length of the C3 column .
UCC could determine whether UOP GA-155 was reducing fouling in
the column by opening the column, . but that .was not practical .
Therefore, UCC relied on indicators such as differential column
pressure to determine whether UOP GA-155 was reducing fouling .-in
the column .
It would take at'least 3 .months for UCC to assess whether
UOP GA-155 would increase the, run length of the reboiler because
the normal run length of\a reboiler without the addition of an
inhibitor is about-2 to 3 months . UCC believed that a successful
inhibitor . could extend the run length of a reboiler to about 6
months . Therefore, while Mr . Brandon recorded data only for
about 90 days, UCC treated the project as beginning on September
22, 1994, and . lasting for 6 months . During this time the
Olefins- .1 unit operated normally except for the addition of the
activities described above . UCC sold the products produced
during the UOP GA-155 project in the ordinary course of its
business .
UGC considered the UOP GA-155 project to be a,success
because it reduced fouling and increased the run length of the
reboiler to 6 months .
Mr . Brandon recorded the results of the project and shared
them with Mr . Swindle . However, Mr . Brandon did not prepare a
- 59 -
formal project report after the project was completed or save th e
data for use when fouling of Olefins-2 was discovered in 1997 o r
1998 . However, the results of the project would have been
reported in the quarterly reports that the hydrocarbons R&D group
prepared . The results of the UOP GA-155 project were also
included in a memorandum prepared for a conference call to be
held on July 27, 1995 . The memorandum did not include data fro m
the project but reported the results as follows :
UOP Inhibitor'Project : Recall that in the beginning of
the second half last year, the UOP-5 inhibitor was
replaced with the UOP GA-155 inhibitor and it was
injected earlier in the system in order to reduce
fouling of the C3 Column Reboilers in Ole-l . In
January of this year, the east kettle [reboiler] had to
be taken out of service due to tube leaks which were
not caused by the inhibitor or fouling - it was due to
attack from carbonic acid in the steam condensate . The
newly purchased kettle, which was installed last
October, was then put in service and is still in
service . We feel that the success of the kettle - six
month life - is primarily due to the use of the new
inhibitor . In addition, the new inhibitor is now also
being used in Ole-2 .
UCC did not always prepare formal project reports when an
inhibitor test such as the UOP GA-155 project was performed .
Although it was preferable for a project report to be prepared to
summarize the results of an inhibitor test, this did not alway s
happen because it was not always a top priority .
On or about October 28, 1994, about a month after the UOP
GA-155 project began, Mr . Brandon began preparing an FOCR for a
project to begin using UOP GA-155 in Olefins-2 . On November 29,
60 1994, Mr . Swindle recommended that UOP GA-155 be used at Olefins2 . On or about June 14, 1995, after the completion of the UOP
GA-155 project, UCC began injecting UOP GA-155 into Olefins-2's
C2 column tail . The purpose of this change was to reduce fouling
in the C2, C3, and C4 columns in Olefins-2 and simultaneously
stabilize the dripolene . However, during a plant shutdown in
1997 or 1998, UCC discovered that the dispersant in UOP GA-155
caused severe fouling in the olefins-2 .
F .
The UCAT-J Projec t
1 .
Overview of Polyethylene Productio n
The UCAT-J project involved a series of runs using a new
polyethylene (PE) catalyst'referred to as UCAT-J conducted at
Star . PE is a plastic made by reacting ethylene with other
materials to form polymers, or molecular chains, of ethylene .
The PE production process generally involves a reaction between a
polymerization-initiating catalyst (as relevant here, M-1 or
UCAT-J13), a cocatalyst,
.a monomer (usually ethylene), a
comonomer (hexene or butene), triethylaluminum (TEAl), and
hydrogen ., Once polymerization begins, monomer molecules diffuse
to the growing polymer chains and resin is formed . Following
polymerization, the resin is discharged into a separate vessel
known as a product purge bin . Purging removes the residua l
13The UCAT-J and M-1 catalysts are described in greater
detail below .
- 61 hydrocarbons in the resin and deactivates the catalyst and
cocatalyst . The resin is then fed into a pelletizer, which
converts the resin into pellets . The pelleted PE resin is the
finished product . UCC typically . shipped pelleted PE in hopper
cars (which each hold about 185,000 pounds of PE resin) to
customers who used it to make items such as grocery and trash
bags, packaging, thin-walled containers, and industrial liners .
Star was dedicated to the commercial production of linear
low-density film and molding resins (LLDPE) and medium densit y
(MOPE) and high density (HDPE) molding resins using UCC's lowpressure UNIPOL process technology . "UNIPOL" is the trade name
for a low-pressure gas phase fluidized-bed process that UC C
developed and licensed to third parties . Star's Low Pressure 3
Unit (LP-3) operated two UNIPOL reactors : Reactor 1, which was
used primarily for HDPE molding resins, and Reactor 2, which was
used primarily for LLDPE film resins . Although used fo r
different purposes, the two reactors were physically and
technologically identical . Reactor 1 and Reactor 2 operated
continuously 24 hours a day except for limited downtime
maintenance, transitions, and unforeseen problems such as
electrical'outages .
In the early 19906 UCC began to plan the design of another
UNIPOL manufacturing facility, Low Pressure 6 Unit (LP-6) . 'LP-6
was designed to produce PE using UCAT-J as the catalyst, but UCC
62 decided to . install two different sets of catalyst feeders so that
M-1 could be used at the plant if UCC could not commercialize
UCAT-J by . the time LP-6 was complete .
. UCC believed that it was
likely that it would be able to use UCAT-J at LP-6 once it was
constructed, but also knew that beginning the design of LP-6
before UCAT-J was ready for commercial production was a risk .
UCC did not want to wait until UCAT-J was commercialized before
building,LP-6 because it takes years to design and build a
manufacturing facility and UCC wanted LP-6 to be completed close
to the time that UCAT-J was commercialized . LP-6 began producing
.PE in June of 1995 using UCAT-J .
A UNIPOL reactor is referred to as a "fluidized bed" becaus e
the circulating gas flow in the reactor causes the solid granular
resin to fluidize . . The catalyst is fed directly into the side of
the fluidized bed through an injection system . A cocatalyst is
also fed into the bottom of the UNIPOL reactor to activate the
catalyst and promote catalyst activity .
"Reactor operability" refers to a wide range of potential
reactor operating issues, including catalyst stability,
reproducibility (whether the reactor consistently produces the
same responses), reactor control, production rate control,
product discharge, and downstream equipment operation . Reactor
operability is affected by a number of factors such as the
history of the reactor since,it was last cleaned (i .e ., how often
I
- 63 it has been exposed to oxygen and moisture),"the mix of products
run on the reactor, the purity of the feed streams, and the
catalysts and cocatalysts used'on the reaction system .
A significant UNIPOL operability issue is the formation of
sheets and agglomerates caused by static in the reactor . Sheets
I
and agglomerates are often referred to as continuity problems
because they interrupt . the continuous operation of the reactors .
Sheets are formed when resin continues to react in a stagnant
zone (a zone with poor fluidization) next to the walls of the
reactor . Without fluidization to remove the heat of reaction ,
the resin fuses together and forms sheet-like blocks ranging from
paper thin to several inches in thickness and several feet-in
length . Agglomerates are formed when granular resin fuses
together forming solid or tightly adhered chunks ranging from
popcorn sized to several feet in diameter .
These chunks can be
caused by sheets folding or rolling in the fluidizing bed, poor
catalyst distribution ,
localized poor heat transfer, or areas of
poor fluidization on the reactor distributor plate . Sheets and
agglomerates interfere with fluidization and plug the product
purge bin valve, requiring UCC to shut down and clean the
reactors .
-
Another operability issue is the formation of small, dustlike particles called "fines " .
Fines can create static (which
T
- 64 can lead to sheeting), cause continuity problems in the reactor,
and foul the cycle gas system .
The occurrence of operability problems might require a
reactor to be "killed" . A reactor kill (or CO kill) is typically
accomplished by the injection of carbon monoxide into .the
reaction cycle gas to .either reduce the rate of reaction (a
minikill) or stop all reaction as quickly as possible .
PE material meeting all applicable product specifications is
referred to as "aim-grade" . PE material that does not meet al l
applicable product specifications is referred to as "off-grade" .
The production of off-grade material was not unusual, and UCC
sold both aim-grade and off-grade resin to third parties but at
different prices . Specific product properties of PE resins,
include the .average particle size
(APS), density (for solid
molded resin), bulk density .(for loose resin powder), film
appearance rating (FAR), hexane extractables (relating to the
stickiness of the resin), melt flow index, melt flow ratio (MFR),
and resin morphology .
The specific properties of the PE products made in a UNIPOL
reactor are determined by a variety of factors, including the
catalyst used and reactor operating conditions . The key reactor
operating conditions that determine .the properties of the PE
resin are reactor temperature, ethylene partial pressure,
- 65 -
hydrogen-to-ethylene . ratio, comonomer ratio, TEAl cocatalyst
ratio (Al/Ti) ,
and residence time .
Star's reactors made a .variety of PE base resins . UCC
identified base resins using a three-letter prefix followed by a
four-number code and either an "H" or a "B" . The prefix of all
base resins begins with a' I'D",
followed by a "J" if UCAT-J is
used as the catalyst or a' "G" if M-1 is used as the catalyst,
followed by an "H "M",'or "L" depending on the melt index
range . The four-number code identifies the density and melt
index designation . The final "H" or "B" identifies the comonomer
as hexene or butene, respectively .
A transition is the period when reactor conditions are
changed from one product's specifications to a new product's
specifications . A transition typically takes three to four bed
turnovers to complete, and each bed turnover lasts about 2 hours .
A bed turnover is the average amount of time material stays in
the reactor before flowing out of the product stream . The resin
made during transitions is either intermediate-grade material,
that can be recycled into aim-grade resin or off-grade material
sold for scrap uses such as picnic tables and barrels . Once a
reactor is transitioned into a new product it takes a number of
additional bed turnovers to "line out" the reactor . Lining ou t
r
the reactor involves increasing the production rate back to th e
normal level after slowing down for the transition and returning
r
66:
operation conditions back to their normal steady state . After a
transition from M-1 to UCAT-J, it takes at least 12 hours to line .
out the reactor .
2 .
UCAT- J
In a chemical reaction, a catalyst is a substance that
increases the rate of the reaction or causes the reaction to
occur under different conditions than otherwise possible .
Polymerization cannot occur in a UNIPOL reactor without a
.catalyst . The catalyst provides the site on which the polymer
chain grows . A PE : catalyst "precursor" refers to the catalyst
state before the incorporation of aluminum alkyl catalyst
modifying agents .
From Star's startup in 1981 through the beginning of the
UCAT-J runs at Star in 1992, Reactor 1 and Reactor 2 at the LP- 3
unit operated exclusively on a catalyst .called M-l . UCC
continued to use M-1 at Star during the credit years during
normal production runs occurring between UCAT-J runs . Despite
its extensive experience using M-1, UCC occasionally experienced
operability and continuity problems with M-1, particularly
sheeting .
UCC developed UCAT-J as a superior catalyst alternative to
M-1 . The primary advantage of UCAT-J is that UCAT-J is over four
times more "active" than M-1, meaning that the same amount o f
catalyst makes over four times as . much PE resin as can be made
67 with M-1 . This, in turn, . significantly reduces both capital
outlays for catalyst manufacturing facilities and the cost of
catalysts used in manufacturing PE . UCAT-J also requires less
hydrogen and TEAl than M-l, thereby reducing manufacturing costs
further, and improves some properties of PE resin such as FAR .
However, UCC used about the same amount of ethylene, hexene, and
butene regardless of whether it used M-1 or UCAT-J . Although UCC
had not commercialized UCAT-J during the credit years, UCC knew
of these advantages during the credit years and described them to
its licensees in anticipation of UCAT-J's commercialization .
M-1 and UCAT-J are both Ziegler-Natta catalysts, a genera l
category of PE catalysts made ' from a transition metal such as
titanium and requiring a cocatalyst to initiate polymerization .
Both catalysts
are based on a chemical solution of magnesium
chloride, titanium trichloride., and tetrahydrofuran, although the
proportions of these materials in M-l and UCAT-J are different .
Most significantly, UCAT-J has a higher titanium loading and
magnesium -to-titanium ratio than M-l, both of which give UCAT-J
superior activity . Both M-1 and UCAT-J use titanium to provide
the catalyst active site and TEAl as the co-catalyst .
To create M-1, a chemical solution is added'to small
particles of treated silica, which absorb the solution . Most of
the tetrahydrofuran is then evaporated to produce a free-flowing
solid, which is the M-1 precursor . The M-1 precursor is then
- 68 reduced with. aluminum alkyls, diethylaluminum chloride (DEAC) and
tri-n-hexylaluminum (TnHAl), to produce the M-1 catalyst .
Catalyst reduction refers to the,treatment of the catalyst
precursor, with aluminum alkyl modifying agents .t.o moderate
catalyst activity and ensure acceptable product properties such
as bulk density and particle size . The aluminum alkyl reduction
agents used for both M-1 and UCAT-J were DEAC and TnHA1 . In its .
final form, . M-1 is a dry powder resembling sand .
UCAT-J is spray dried instead of being silica based . The
chemical solution is transformed into a fine droplet spray, in a .
spray dryer . As these droplets pass through a drying chamber,
the tetrahydrofuran evaporates, leaving only the solid catalyst .
The catalyst is then added to mineral oil to create a slurry ( a
mixture of .liquid and insoluble solids) of UCAT-J precursor . The
UCAT-J precursor. is then reduced with aluminum alkyls . Although
Star made its own M-l catalyst precursor, UCC made UCAT-J
precursor, at a separate catalyst manufacturing facility in South
Charleston and shipped it to Star .
Because of the different methods by which they are made, M-1
and UCAT-J have different "catalyst morphology", a term used to
describe the size, shape, and surface texture of a catalyst :
particle . M-1 catalyst particles have a substantially larger APS
than those of UCAT-J . M-1 particles are typically rounder and
smoother than UCAT-J particles . UCAT .-J' .s morphology creates some
69 problems that were not present with M-l, particularly increased
fines and resin flowablity problems . These problems created
operating uncertainties that had not been resolved by the
beginning of 1994 . UCAT-J and M-1 also respond differently to
other chemicals present during polymerization, respond
differently to reactor conditions, and create differences in PE
product properties .
M-1 precursor is reduced in the catalyst'manufacturing unit
before the catalyst is delivered for use in the reactor . UCAT-J
precursor, in contrast, requires "in-line" catalyst reduction,
meaning that the DEAC'and TnHAl modifying agents are injected .
into the catalyst stream immediately before it is fed into the
UNIPOL reactor .
Before the first-UCAT-J-run at Star, which"occurred in May
1992, UCC_ installed new equipment at Star to allow the in-line .
reduction of UCAT-J precursor . The in-line precurso r
modification system was a new unit operation installed
specifically for use with UCAT-J . In this system, UCAT- J
precursor was placed into a slurry feed tank, agitated to
maintain good dispersion, and pumped at a controlled rate . . DEAC
and TnHA1 were pumped into the catalyst stream at a specific
ratio to the catalyst feed . Following the injection of the
aluminum' alkyls, the precursor flowed into a static mixer to
4
- 70 -
ensure adequate contacting and then into a residence time pot to
provide time for the in-line modification to occur :
The UCAT-J in-line-reduction system presented several
operating uncertainties not present with M-l . When, the system
was first used, it created catalyst consistency problem that were
due in part to the absence of static mixers and in part to the
fact that the original design contacted the UCAT-J precursor with
DEAC first and then with TnHA1, .as was customary . with M-l . UCC
later discovered that consistency improved when the order was
reversed . UCC also had difficulty controlling flow rates,
keeping control consistent and accurate, and injecting UCAT-J
because a slurry does not disburse as easily as a dry catalyst
like M-1 . These uncertainties were not resolved by 1994 .
3 .
Overview of the UCAT-J Projec t
The UCAT-J commercialization program involved the
development of UCAT-J to the point where it could be
commercialized . , UCC's UNIPOL licensing business wanted to
commercialize UCAT-J in order to : (1) Derive revenues from
selling UCAT-J to existing UNIPOL licensees ; (2) be able to tout
the superior qualifies of UCAT-J to prospective UNIPOL licensees ;
(3) avoid the capital costs associated with constructing plants
to manufacture the less-productive M-1 catalyst ; and (4) reduce
Star's manufacturing costs as a result of UCAT-J's superior
productivity . The UCAT-J commercialization program took place at
- 71 Star from 1992 to 1996 .
References to the "UCAT- J project" are
only to those runs that occurred during the credit years . .
Once UCC made the decision to commercialize UCAT-J, members
from process R&D, product R&D, and . catalyst - R&D formed an
interdisciplinary UCAT-J technology
task force .
The members me t
monthly or bimonthly, usually in person, to review the status o f
the commercialization effort and develop strategies for
overcoming problems with UCAT-J implementation . '
During 1993 through'r1995 UCC's
process R &D group conducte d
what it called " experimental runs" of UCAT - J on a small-scal e
UNIPOL reactor at a pilot plant at'the South Charleston technica l
center . UCC defined an experimental run as a run of a product
that UCC deemed noncommercial .14 During the credit years UCC's
manufacturing business required that a commercial facility
conduct at least two, but preferably three, objective-meeting
experimental runs of new PE products, including products made
with a new catalyst, for the products to be considere d
commercial . The successful completion of two to three . objectivemeeting runs would demonstrate the operability of a new
technology to the satisfaction of the UNIPOL R&D and
manufacturing organizations . A customer's qualification of a PE
resin depended on an independent inquiry related to th e
14 We use the term "experimental run" for convenience and
consistency with UCC's terminology .
-
72 -
suitability of the product, produced and did not establish that
the product could be produced consistently enough to be
considered commercial . UCC was not required to advise customers
that they were receiving base resins produced with UCAT-J unless
a specific contractual term required such a disclosure .
The South Charleston pilot plant's UNIPOL reactors were used
strictly for R&D purposes, and one reactor was dedicated to UCATJ . UCC ran UCAT-J on the pilot plant reactor to evaluate
catalyst performance, estimate optimal operating conditions for
the commercial reactors, .and make PE resin for evaluation by the
product R&D group in Bound Brook . After experimenting with new
technologies on the pilot plant, UCC generally experimented with
the technologies on its mid-size UNIPOL reactors at Seadrift
before experimenting with the technology on the . larger reactors,
at Star . However, UCC took some UCAT-J products from the pilot
plant . directly to Star or did not test them on smaller reactors
at all .
Successful commercialization of UCAT-J required UCC to
conduct experimental runs at UCC's commercial plants to evaluate
whether UCAT-J could be used with reactor operability and resin
properties at least equivalent to, and hopefully better than,
those achieved using M-1 . While UCC was often able to achieve at
least the same level of reactor operability and continuity usin g
UCAT-J as it had achieved with M-1 at pilot plants , commercial-
- 73 scale plant tests were also necessary because there were
significant differences between the pilot plants and commercial
reactors . For example, the bed volume of Star's commercial
reactors was about 825 times the size of the bed volume of the
pilot plant reactor . Because of this difference, UCC's pilot
plant and commercial reactors use different methods of
fluidization . These differences'affect the amount of sheeting
and static in a reactor .* Accordingly, a 'successful run at the
pilot plant did not indicate that sheeting and static would no t
cause significant problems when a similar run was conducted at a
commercial plant .
. The first commercial-scale run using UCAT-J was conducted on
UCC's smallest commercial-scale reactor, the G-1750 reactor at
Seadrift, in 1991 . UCC continued the UCAT-J commercialization
program at Star until 1996 . UCC did not consider UCAT-J fully
commercial before the program was completed because UCC did not
know with certainty how UCAT-J would affect reactor operabilit y
and continuity, how it would affect product quality and . how much
off-grade material it would produce, whether there would be
problems feeding the catalyst into the reactor, and how it would
respond to CO kills . UCC was also concerned about, reactor feed
stability, fines creation, production rate control, resin
properties, sheeting, and-agglomeration . Such reactor
operability and continuity issues could develop at any time
74 during an experimental run, . so process R&D representatives
remained on .site for the duration of the runs, even after the
reactor had been successfully transitioned into UCAT-J . Process
R&D preferred longer experimental runs because they afforded more
opportunities to evaluate reactor operability and continuity .
UCAT-J experimental runs were initiated by the completion of
an experimental run request by the appropriate business manager,
R&D group leader, inventory planning and control (IPAC) manager,
and plant department head . IPAC controlled the scheduling of the
experimental runs and the duration of each run . When scheduling
the runs, IPAC considered existing customer orders and the risk s
posed by experimental runs so that the experimental runs woul d
fit UCC's commercial requirements . Once an experimental run
request was .completed and the experimental run was scheduled,
representatives from process R&D in South Charleston would
prepare a strategic run plan with input from the UCAT-J
technology task force . The principal purpose of a strategic run
plan was .to communicate to all interested parties the run
objectives, key operating parameters, analytical requirements,
and run coverage . After receiving the strategic run plan, a Star
engineer would prepare a tactical run plan . The purpose of the
tactical run plan was to give detailed run instructions to the
plant operators responsible for reactor operation . Strategic run
plans and tactical run plans were not prepared for routine
75
commercial production runs . The operations improvement group
would also complete a "New Product Introduction/Commercialization
Procedure Checklist" showing°whether all required documentation
was in place .
The'function of process R&D representatives during
experimental runs was to evaluate what was happening in the
reactor, identify problems, create hypotheses . for how to solve
those issues or improve the process, and test those hypotheses by
conducting experiments .' Process R&D representatives conducted
experiments by adjusting operating ratios, modifying catalyst
properties, and introducing new reactor control technologies .
Process R&D generally did not address minor problems that-could
be solved by troubleshooting, which were addressed by the
production group at the plant .
During the UCAT-J project process R&D regularly collected
various measurements of reactor operability and continuity and
product properties . While many of these measurements wer e
collected during nonexperimental'runs, .process R&D
representatives collected some data that were not normally
collected and took other measurements more frequently than they
normally would . For example, process R&D measured residual
aluminum and titanium to monitor for TEAl .starvation during the
UCAT-J project but did not'normally take these measurements .
TEAl starvation occurs . when there is an inadequate amount of'TEAl
Q.
76 cocatalyst in the reactor . This lowers hydrogen and comonomer
response and catalyst productivity, which cause a loss of control
over .the reactor,and product properties . Process R&D also
measured hexane extractables more frequently than normal during
the UCAT-J project . The process R&D representatives recorded
their observations in .R&D notebooks . At least every other day
process R&D sent an e-mail update to the members of the UCAT-J
technology task force . and UCC's management . This was not done
for normal commercial . production runs . Process R&D
representatives were also called upon to address significant .
production problems with products made using the .M-1 catalyst
during the credit years ,
Representatives from catalyst R&D and product R&D, both
based in Bound Brook, were available as needed . Samples of PE
resins made during UCAT-J experimental runs were shipped to the
product R&D group for testing to ensure that the resin was
equivalent to or better than that made with M-1 . Any remaining
aim-grade resin made during the experimental runs was sold t o
UCC's customers . Product R&D did not : provide coverage or test
resin samples for routine commercial production runs with M-1 .
The run team, comprising representatives from process R&D
and Star's management and operations staff, met before each run
to discuss . the run objectives and transition into UCAT-J . The
run team also met regularly during the course of the UCAT-J runs
T
I
- 77 to assess the status of the run objectives and develop strategies
for resolving any operating problems that . had surfaced . At the
end of each run the run team met to discuss the extent to which
the run objectives had been met . The run team presented thes e
findings at meetings of the UCAT-J technology task force .
addition, process R&D,representatives prepared a run notebook for
each run containing the strategic run plan, the tactical run
plan, the R&D monthly report description of the run, the
presentation to the UCAT-J technology task force, e-mails and
other communications regarding the run, and lab data . Process
R&D also described the UCAT-J .runs in monthly reports issued by
the process R&D group, but these reports did not provide
technical details concerning the runs . Process R&D did not
generally mention normal production runs in these reports .
4 .
Experimental Runs Before the Credit Year s
UCC conducted nine UCAT-J run campaigns on reactor 2 at Star
from May 1992 to November 1993 . The UCAT-J runs conducted at
Star in 1992 and 1993 involved only hexene LLDPE film resins made
on reactor 2 . These were the principal products made at Star and
UNIPOL licensee plants and tended to have tighter product
requirements than molding resins . At the end of 1993 UCC had
conducted no UCAT-J runs on reactor 1 or on reactor 2 with either
molding or butene film resins .
78
About 6 percent of the PE resin UCC made at Star in 1993 wa s
made with UCAT-J . By the end of 1991,
UCC had resolved some
uncertainties related to UCAT-J such as an issue related to
catalyst particle size : The plant personnel at Star also . gained
experience operating the plants using UCAT-J and were at ease
using UCAT-J and in transitions . Furthermore, a number of UCAT-J
runs had produced no off-grade product .
However, the UCAT-J runs conducted at Star in 1992 and 1993
suffered,from numerous operability problems . Many were
unresolved as of the end of 1993, including : (1) Gas channeling
(resin becomes stagnant and nitrogen is channeled through the
resin instead of mixing with it, causing inadequate resin
purging) ; (2) TEAl starvation ; (3) sticky stretch'LLDPE resins
(resins that agglomerated and did not flow properly) ; (4)
sheeting ; and (5)
.poor control over product properties such as
melt index, density,'and hexane extractables caused by
differences in UCAT-J and M-1 catalyst morphology . UCC was
confident that many of these issues could be resolved but was
unsure when or how it would be able to resolve them .
Following a UCAT-J run campaign on LLDPE film resins in
November 1993, a moratorium was imposed on further experimental
runs on film resins to allow R&D to work out various problems,
some related to UCAT-J and others that were general plant
I
- 79 problems . UCC did not believe that UCAT-J was ready to be
commercialized by the end of 1993 .
5 .
Experimental Runs During the Credit Year s
At the beginning of 1994 some of the major outstanding
issues with UCAT-J were : (1) Obtaining acceptable product
properties in fractional melt index film resins ; (2) resolving
butene film bulk density problems ; (3) determining the cause of
and preventing resin stickiness ; (4) establishing operating
parameters for UCAT-J film resins ; (5) developing UCAT-J for
molding resins ; and (6) ensuring that UCAT-J met operational
requirements . UCC believed it needed to conduct additiona l
experimental runs to resolve these issues .
UCC seeks research credits for the expenses incurred in 19
UCAT-J runs (UCAT-J runs 1 through 19) conducted at Star during
the credit years . The base resins produced, types of resin
produced (low-density film . .or high-density molding), start and
end dates of the runs, and pounds of base resin produced
according to UCC's product cost detail reports (PCDs) . are
included in the chart below :
I
- 80 Aim-Grade
Resi n
Produced
Off-Grad e
Resi n
Produce d
End Date
(pounds)
(pounds )
Run
No .
Base
Resin
Resin Type
Start
Date '
1
DJM-5265H
HDPE .Molding
2/16/94
2/17/94
958,96 8
2
DJM-1810B
LLDPE Film
10/22/94
10/26/94
4,83 .2,092
771,35 0
3
DJM-1732H
LLDPE Film
11/14/94
11/15/94
1188,068
21,162,65 0
4
DJM-2419H
LLDPE Film
12/11/94
12/13/94
1,632,872
765,70 0
5
DJM-1810H
LLDPE Film
12/13/94
12/17/94
5,254,885
455,70 0
6
DJM-2016H
LLDPE Film
12/17/94
12/18/94
703,69 1
7
DJM-1725H
LLDPE Film
12/18/94
12/18/94
3731 , 731,842
4137 , 137,10 0
8
DJL-5264H
HDPE Molding
1/26/95
1/27/95
6,135,634
797,75 0
9
DJL-5280H
HDPE Molding
1/27/95
1/28/95
1,864,465
-
10
DJH-2580H
LLDPE Film
3/3/95
3/6/95
2,601,861
578,45 0
11
DJM-1810B
LLDPE Film
3/4/95
3/13/95
8,707,791
1,058,45 0
12
DJH-2950H
LLDPE Film
3/6/95
3/6/95
132,324
148,75 0
13
DJL-5420H
HDPE Molding
14
DJL-5143H
HDPE Molding
3/26/95
3/27/95
1,006,947.
15
DJM-1732H
LLDPE Film
5/16/95
5/22/95
54,091,446
62,430,70 0
16
DJM-1725H
LLDPE Film
5/22/95
5/26/95
3,653,813
966,35 0
17
DJM-1720H
LLDPE Film
5/26/95
5/27/95
886,625
520,10 0
3/25/95
3/26/95
696,18 1
8
19
DJL-5280H
HDPE Molding
6/.22/95
6/23/9 5
'This amount was found on a PCD for DJM-1734H . UCC could
not find a PCD for DJM-1732H, so it used the PCD for a similar
product .
2This amount was found on a PCD for DJM-1734H . UCC could
not find a PCD for DJM-1732H, so it used the PCD for a similar
product .
3This amount includes base resin produced during both run 7
and another experimental run that took place in November 1994 .
'This amount includes base resin produced during both run 7
and another experimental run that took place in November 1994 .
'This amount was found on a PCD for DJM-1734H . UCC could
not find a PCD for DJM-1732H, so it used the PCD for a similar
product .
81 6This amount was found on a PCD for DJM-1734H . UCC could
not find a PCD for DJM-1732H, so it used the PCD for a similar
product .
7The resin that petitioner claims UCC produced during run 18
is included in the amount of resin petitioner claims UCC produced
during run 8 .
'The resin that petitioner' claims UCC'produced during run 19
is included in the amount of resin petitioner claims UCC produced
during run 9 .
a .
DJM-5265H
(UCAT-J Run 1 )
UCAT-J run 1 was the first UCAT-J run at'Star with 'a molding
resin and the first UCAT-J run conducted on reactor 1 . The base
resin, DJM-5265H, was selected to be the first molding resin- made
with UCAT-J at Star because it was a basic Cornerstone product
that Star made in large quantities and UCC considered it to be a
low-risk product . UCC had made'aim-grade DJM-5265H at the pilot
plant using UCAT-J and found UCAT-J to be equivalent- to M-l with
respect to operability and continuity on that scale .
Before UCAT-J run .1, two short runs of DJM-5265H had been
conducted at the UNIPOL'facility of a licensee, Hanwa Chemical
Corp . (Hanwa), in Korea .` While the runs at Hanwa were generally
successful, they lasted only a few days, and the second run was
aborted when the second transition failed . These results were of
limited value to UCC because Hanwa's reactors were different from
Star's reactors : Hanwa's reactors were just over half'the size
of Star's reactors and so were less prone to static .
Furthermore, Hanwa's reactors had a purification system for ra w
materials that was considerably better than UCC's purification
- 82 system . As a result, Hanwa's reactor feed was much cleaner than
UCC's and the catalyst had better productivity .
The objectives of UCAT-J run 1 were to : (1) Successfull y
scale up production (adjust production to take into account the
differences in reactor size) of DJM-5265H from the South
Charleston pilot plant to reactor,l ; (2) produce aim-grade resin
for customer qualification ; and (3) establish reactor operability
and continuity on reactor 1 . As to the third objective, UCC was
not merely confirming that reactor operability and continuity
were as expected . UCC wanted to evaluate how well reactor 1
worked with UCAT .-J .
UCC's primary concerns before UCAT-J run-1 were that : (1)
The differences between the pilot plant and reactor 1 at Star
could cause the product to go off grade ; (2) TEAl starvation
could cause operability and continuity problems ; (3) .difficulties .
with CO kills could occur if any kills were necessary ; and (4)
resin clumpiness could cause operability and continuity problems .
As with all of the UCAT-J runs discussed below (although not
specifically mentioned below for brevity), representatives from
process R&D and product .R&D provided coverage for UCAT-J run 1
and process R&D collected data, some of which were not normally
collected or was not normally collected as frequently .
_
Additionally, samples of resin were collected during and
83 following the run and were sent to'product R&D in Bound Brook for
evaluation .
UCAT - J run 1 was aborted after 17 hours because of sheeting
caused by the use of M-1 before the transition to UCAT-J and the .
formation of a spongy material that resembled ` Styrofoam . `UCC
analyzed the spongy material and determined that it formed
because of the use of UCAT-J . But because the sheeting was
caused by M-1, UCC was unable to determine the extent to which
the use of UCAT - J contributed to the shutdown .
UCC also discovered a discrepancy between the Ti/A1 ratio
calculated by flow rate and the measured Ti ./Al ratio that
correlated with catalyst feed rate .
UCC was unable to explain
this discrepancy and was concerned about TEAl starvation . UCC
also discovered more fines ' than expected .
UCAT-J run 1 did not last long enough for UCC to draw any
conclusions from ' the run' . It remained . uncertain following th e
run whether UCAT-J could be used on reactor 1 with operability ,
continuity, and resin properties equivalent to those achievable
with M-l . Because of the formation of the spongy material, TEAl
starvation concerns, and increased fines, UCC had serious doubts
as to its ability to make further product . Therefore, it did not
attempt to make another molding resin run again until 1995 .
According to a PCD for DJM-5265H, UCC,produced 958,96 8
pounds of aim-grade base resin for customer evaluation during
84 UCAT-J run 1 .15 Petitioner claims as QREs costs associated with
producing 960,150 pounds of aim-grade base resin during UCAT-J
run 1 .
b.
DJM-1810B .(UCAT-J .Runs 2 and 11 )
UCAT-J run ,2 was the first,UCAT-J run . conducted at Sta r
using butene, as opposed to hexene, as the comonomer . UCC wanted
its plant operators to gain production experience using butene
comonomers in anticipation of the startup of LP-6 . There had
been successful runs of DJM-1810B at Seadrift, the pilot plant,
and a licensee's facility, which encouraged UCC to believe that
it would be able to use butene as a comonomer at Star . However,
process R&D had encountered significant difficulties producing
butene film resins using .UCAT-J with acceptable bulk. density
because of particle morphology differences between UCAT-J and
M-1 .
The principal objective for UCAT-J run 2 was to successfully
scale up UCAT-J on the butene film resin from the pilot plant to
Star . A successful scale-up would require that the run : (1 )
Demonstrate operability using UCAT-J equivalent to that
achievable using M-1 ; (2) reach aim-grade production within a
15As discussed below, PCDs were produced monthly and
annually, not for specific projects . . However, no base resin
produced with UCAT-J was made in more than one run in any given
month during the credit years . Accordingly, the PCD for the
month in which a UCAT-J run occurred would include information
only for that particular run .
- 85 specified period ; (3) produce no significant off-grade material
once the transition was complete ; and (4) produce resin with
acceptable bulk density . UCC was uncertain before the run
whether any of these requirements would be met or whether the
scale-up would be successful . UCC also hoped to produce 10 to 12
million pounds of aim-grade resin to sell to customers during
UCAT-J run 2 .
To achieve acceptable bulk density, process R&D planned to
change the catalyst reduction ratios and increase the amount of
isopentane in the reactor during the run . Process R&D regarded
.both changes as experimental and was uncertain whether they would
improve bulk density without adversely affecting reactor
productivity .
Additional objectives-of UCAT-J run 2 were to'demonstrate a
closed reactor restart . with UCAT-J following aCO kill on ,M-1 and
to demonstrate the ability to kill the reactor while it contained .
UCAT-J . UCC had never attempted a closed reactor restart at Star
with UCAT-J . UCC had had some experience with'CO kills using
UCAT-J, but the results had been mixed . In particular, minikills had been much less effective when using UCAT-J as compared
with M-1 .
UCC was also concerned about several other risks, including :
(1) TEA1 starvation ; (2) resin carryover (a negative effect of
I
- 86 low resin APS, which may result from steps taken to improve bulk
density) ; and (3) resin clumpiness .
UCAT-J Run 2 began well and met some of the objectives,
including the first successful reactor startup with UCAT-J, no
significant off-grade material produced, and unexpectedly high
bulk density . However, UCC, experienced operating problems a few
days into the run that required the reactor to be shut down and
the run aborted . The most significant of these problems were
unexplained production rate swings and the formation of "cue
balls" of PE resin that were about the size of softballs . . UCC
hypothesized that the cause of the cue balls was poor catalyst
dispersion, and accordingly it planned to change the injection
tube for the next run of DJM-1810B to improve catalyst dispersion
and determine whether that would solve the problem .
According to a PCD for DJM-1810B, UCC produced 4,832,092
pounds of aim-grade and 771,350 pounds of off-grade base resin
during .UCAT-J .run 2 . Petitioner claims as QREs costs associated
with producing 4,954,150 pounds of aim-grade and 771,350 pounds
of off-grade base resin during UCAT-J run 2 .
UCAT-J run 11 was the second run of DJM-1810B . UCC's
primary objective was to make. DJM-1810B without the problems
experienced in UCAT-J run 2 .
UCAT-J run 11 lasted from March 4 to 13, 1995, the longest
run for a single product during the UCAT-J project . A long run
- 87 -
is usually evidence that the run was successful . However, th e
transition to DJM-1810B was unusually long and difficult, and a
significant amount of off-grade resin was produced . Once UCAT-J
was introduced into the reactor, the resin bulk densit y
unexpectedly dropped significantly, causing the product purge bin
to plug. This resulted insignificant off-grade material and
required the production rate to be lowered . UCC did not
anticipate the bulk density problem because UCAT-J run 2-produced
resin with unexpectedly high bulk density . There were also
problems with'catalyst stability, sheeting, poor hydrogen
control, and melt index swings . These problems were all specific
to UCAT-J and were not anticipated before the run .
Because of the bulk density and operability problems, UCC
decided to .return the testing of'DJM-1810B to Seadrift . While
UCAT-J run ll"provided .valuable operating data, it did not
establish that reactor 1 at Star could produce UCAT-J butene
LLDPE film resins with operability and continuity equivalent to
that achieved using M-1 .
According to a PCD for DJM-1810B, UCC produced 8,707,791 .
pounds of aim-grade and 1,058,450 pounds of off-grade base resin
during UCAT-J run 11 . . Petitioner claims as QREs costs associated
with producing 8,941,350 pounds of aim-grade and 1,058,450 pounds
of off-grade base resin during UCAT-J run 11 .-
88 c .
DJM-1732H (UCAT-J Runs 3 and 15 )
UCAT-J run 3 produced DJM-1732H, a low-density, high-meltindex LLDPE film resin . UCAT-J run 3 was the first UCAT-J
experimental run of an LLDPE film resin with a hexene comonomer
conducted at . Star since November 1993 . . UCC experienced so many
problems during the November 1993 run and the run had such a
negative impact on manufacturing that R&D wanted .to do more work
on smaller reactors before attempting the run again at Star . UCC
had conducted runs of DJM-1732H at Star in January and March 1993
for 1 day each, but these runs were too short to establish that
the process could be used with sufficient operability and
continuity .
The objectives of UCAT-J run 3 were to : (1) Produce
sufficient product for customer qualification ; (2) run reactor 2
at normal Star rates with operability and continuity equivalent
to or better than M-1 ; (3) reach aim-grade production within a
specified period ; and (4) produce no significant off-grade
material . UCC was uncertain whether any of these objectives
could be met or whether the run would be successful .
Because low-density, high-melt-index LLDPE film resin is
sticky by design, resin flowability was a primary concern before
UCAT-J run 3 . UCC was also concerned about : (1) TEAL
starvation ; (2) resin carryover ; (3) difficulties with . CO kills,
if they were necessary ; and (4) resin clumpiness . . Resin
- 89 clumpiness had also been a problem when using M-1 to make DJM1732H but tended to be worse with UCAT-J .
UCAT-J run 3 had several successes : (1) UCC was able to use
CO mini-kills,' which produced a rapid and significant effect ; (2)
no fines were produced ; and (3) a hopper car of resin was
produced . However, the run as a whole was considered a failure
and several problems occurred : (1) There was extensive formation
of clumpy resin that plugged the product purge bin ; (2) there wa s
poor melt index control ; and (3) there was TEA1 starvation in the
reactor . Process R&D evaluated these problems, identified their
potential causes, and developed possible solutions for futur e
runs . UCC determined that the next run might be more successful
if it : (1) Lowered the ethylene partial pressure in the reactor
to reduce the amount of hexane ; (2) controlled the cycle ga s
composition and flow ratio ; and (3) doubled the TEAL feed into
the reactor for 20 minutes (known as giving the reactor a "TEAl
shot") periodically even if starvation was not expected and more
frequently during upset conditions . 'UCAT-J run 3 did not
establish that UCAT-J could be used with operability and
continuity equivalent to that achieved using M-1 .
According to a PCD for DJM-1734H, not DJM-1732H, UCC
produced 188,068 pounds of aim-grade and 1,162,650 pounds of offgrade DJM-1734H in 1994 . No PCD was available for DJM-1723H for
1994 . Petitioner claims as QREs costs associated with producing
I
- 90 188,850 pounds of aim-grade and 1,162,650 pounds of off-grade
base resin during UCAT-J run .3 . However, other postrun
documentation indicates that UCC produced 743,987 pounds of aimgrade base resin during UCAT-J run 3 .
In addition to the objectives stated for UCAT-J run 3, a
goal of UCAT-J run 15, the next run of DJM-1732H, was to
implement measures developed by process R&D to control resin
stickiness and TEAl levels and to demonstrate acceptable
operability and continuity using UCAT-J in reactor 2 . To control
resin stickiness, process R&D recommended that ethylene partial
pressure be lowered below 90 psi, which had never been done
before at Star with UCAT-J . This change to reactor conditions
was considered experimental and had two drawbacks : (1) Lowering
the ethylene partial pressure could lower the productivity of the
catalyst, which would lower resin APS and increase fines, causing
fouling ; and (2) if the reactor transitioned back to M-1, it
would be necessary to increase the ethylene partial pressure by a
greater amount . UCC also planned to give the reactor periodic
TEAl shots to minimize TEAL starvation, which UCC began using in
run 4 (discussed below) . However, UCC was unsure whether these
steps would be successful .
UCC hoped to produce 23'hopper cars of DJM-1732H for
customer qualification and consumption . Other run objectives
were to : (1) Run reactor 2 at normal production rates ; (2) reach
91 -
aim-grade production within a specified period ; and (3) produce
no significant off-grade material .
UCAT-J run 15 was generally successful . . UCC was able to
control resin stickiness by lowering the ethylene partial
pressure, and UCC was able to maintain good catalyst . productivity
even though it is more difficult to maintain at low ethylene
partial pressure . Overall, operability and continuity were good
throughout the run . However, while flowability improved, it was
still slightly worse than flowability that had been achieved
using M-l . Furthermore, there was some TEAL starvation due to
the TEAl feed system, though less than had occurred during
previous runs . Therefore, the information gained was valuable to
UCC but process R&D still had some concerns .
A PCD .for DJM-1734H, not DJM-1732H, shows that UCC produced
4,091,446 pounds of aim-grade DJM-1734H in 1995 . No PCD was
available for DJM-1732H for 1995 .- Petitioner claimed as QREs
costs associated with producing 4,108,850 pounds of aim-grade an d
2,430,700 pounds of off-grade base resin during UCAT-J run 15 .
d.
DJM-2419H, DJM-1810H, and DJM 2016H (UCAT-J
Runs 4 Through 6 )
UCAT-J runs 4 through 6 were all runs of hexene LLDPE film
resins . With the exception of DJM-1810H (UCAT-J run 5), which
had been used as an experimental bed resin for various types of
reactor testing, Star had limited experience with the UCAT-J
resins to be made in these runs .
92 UCC designed UCAT-J run 4 to make DJM-2419H, which UCC .had
previously made at Star only during a 1-day run in 1993 . . UCC
produced approximately 600,000 pounds of DJM-2419H in 1993 and
UCC's customers had accepted DJM-2419H made with UCAT-J .
However, UCC was still uncertain whether it would be able to
produce DJM- .2419H at Star consistently with satisfactory
operability .
UCC designed UCAT-J run 5 to make DJM-1810H . UCC had used
DJM-1810H as an experimental bed resin and had produced it in 11
runs at Star during 1992 and 1993 . UCC experienced significant
problems during the earlier runs . During the later runs UCC used
DJM-1810H as an experimental bed for catalyst reduction tests,
order of reduction tests, and similar tests . UCC made about 170
hopper cars of DJM-1810H in 1993 . DJM-1810H produced with UCAT-J
had already been accepted by customers . However, UCC still
considered DJM-1810H to be an experimental resin at this point,
primarily because it had flowability problems .
UCC designed UCAT-J run 6 to produce DJM-2016H, which UCC
had never made at Star . However, UCC had produced DJM-2016H at
other plants during earlier experimental runs and customers had
qualified resin produced during those runs . UCC expected results
similar to those that had been obtained during runs of DJM-1810H
(UCAT-J run 5) .
93 The overarching goal of these runs was to demonstrate
sustained operability of-UCAT-J with hexene LLDPE film resins .
The specific run objectives Tisted`on the strategic run plan were
to : (1) Produce sufficient product for customer qualification ;
(2) further commercial' experience through the extended production
run of DJM-2419H (UCAT-J run`4)' and DJM-1810H (UCAT-J run 5)
(among other runs not claimed) ; (3) run reactor 2 at normal Star
rates with operability equivalent to that achieved using M-1 ; (4)
reach aim-grade production within a"speci°fied period ; and (5)
produce no significant off-grade material outside product
transitions .
In response to a recommendation made at the UCAT-J
technology task force meeting following UCAT-J run 3, UCC decided
to''run reactor 2 at a lower than normal ethylene partial pressure
during UCAT-J runs 4 through 6 to improve resin flowability . UCC
considered this change to be an experiment because it was
uncertain whether the change would successfully eliminate
flowability problems and there was'a risk that the change could
significantly reduce catalyst productivity . UCC also decided to
use production rate control, which is'an automated system to
control the catalyst feed rate and the ethylene partial pressure
in the reactor . The goal of this system was to maximize
production rate by allowing production rate to run closer to th e
constraints of the reactor system .
- 94 Because of the problems with TEAl starvation in .UCAT-J run
3, UCC decided to experiment with TEAl shots during UCAT-J runs 4
through 6 . However, UCC was concerned that increasing the Ti/Al
ratio would also increase hexane extractables .
n addition to TEAl starvation, UCC identified several othe r
risks related to UCAT-J runs,4- .through,6 : (1) Resin carryover ;
(2) difficulties with CO kills, . if they were necessary ; and (3)
resin clumpiness .
Process R&D representatives evaluated the ethylene partial
pressure and TEAL shot experiments during UCAT-J-,runs 4 through 6
in addition to the support that R&D provided to all of the UCAT-J
runs .
UCAT-J runs 4 through 6 were generally successful . Reducing
the ethylene partial pressure and .using production rate control
reduced the stickiness problem and giving the reactor TEAl shots
reduced TEAl starvation .
.UCC viewed this as a substantial
achievement . The only significant problem was a decrease in FAR,
which'occurs when there are gels or foreign matter in the film .
UCC took samples of-the resin to,try to determine the potential
causes and solutions for the decreased FAR . UCC hypothesized
that the decrease in FAR was caused by the use of wet hexene .
Process R&D concluded that it had gained confidence that
Star could produce DJM-1810H (UCAT-J run 5) andDJM-2016H (UCAT-J
run 6) with sufficient operability and continuity . However, UCC
- 95 believed that additional experiments were necessary to reach this
conclusion with respect to DJM-2419H (UCAT-J `run 4) .
According to a PCD for DJM-2419H, UCC produced 1,632,872
pounds of aim-grade and 765,700 pounds of off-grade base resin
during UCAT-J run,4 . Petitioner claims'as QREs costs associated
with producing 1,640,950 pounds of aim-grade and 765,700 pounds
of off-grade base resin during UCAT-J run 4 .
According to a PCD for DJM-1810H, UCC produced 5,254,885
pounds of aim-grade and 455,700 pounds of off-grade base resin
during UCAT-J run 5 : Petitioner claims as QREs costs associated
with producing 5,270,050 pounds of aim-grade'and 455,700 pounds
of off-grade base resin during UCAT-J run 5 .` '
According to a PCD forDJM-2016H,*UCC produced 703,691
pounds of aim-grade base resin during'UCAT-J run 6 . Petitioner'
claims as QREs costs associated with producing 704,600 pounds of
aim-grade base resin during UCAT-J run 6 .
e:
DJM-1735H (UCAT-JRuns-7 and 16 )
UCAT-J run 7 was an experimental run of DJM-1725H, another
hexene LLDPE film resin that is very sticky and had shown poor
flowability . UCAT-J run 7 began and ended on December 18, 19 .94 ..
UCC also produced DJM-1725H in November 1994, but there were so
many problems with clumpy resin, melt index control,-and TEAl
starvation that UCC did not use that°resin for customerqualification .
96 .As in UCAT-J runs 4 through 6, the overarching objective of
UCAT-J run 7 was to demonstrate sustained operability of UCAT-J
with hexene LLDPE film resins . The specific run objectives were
to : (1) Produce sufficient product for customer qualification ;
(2) run reactor 2 at normal Star rates with operabilit y
equivalent to that achieved with M-l ; (3) reach aim-grade
production within a specified period ; and (4) produce no
significant off-grade material outside of product transitions .
UCC implemented the recommendation of the UCAT-J technolog y
task force to run reactor 2 at a lower than normal ethylene
partial pressure to improve resin flowability . UCC also gave the
reactor TEA1 shots to reduce TEAl starvation but was still
concerned that increasing the TEAl ratio would also increase
hexane extractables . In addition to the support R&D provided to
all of the UCAT-J runs, process R&D representatives evaluated the
ethylene partial pressure and TEAl shots experiments .
UCAT-J run 7 was generally successful . The only significant
problem was a decrease in FAR caused by gels or foreign matter in
the film, which had also occurred during UCAT-J runs 4 through 6 .
UCC took samples of the resin to try to determine the potential
causes and solutions for the decreased FAR . UCC believed that
additional experiments were necessary to gain confidence that it
could produce DJM-1725H with sufficient operability and
continuity .
97
According to the summary report of the UCAT-J experimenta l
runs conducted at Star, UCC produced 480,461 pounds of aim-grade
and 177,821 pounds of off-grade base resin during UCAT -J run 7 .
According to a PCD for DJM-1725H ,
UCC produced 541,866 pounds of
aim-grade and zero pounds of off-grade base resin . Petitioner
claims as QREs costs associated with producing 737,200 pounds of
aim-grade and 137,100 pounds of off-grade base resin, which
includes total production for 1994
(both UCAT- J run 7 and the run
that took place in November 1994) .
UCC produced DJM-1725H again in UCAT - J run 16 because UCAT-J
run 7 did not establish that DJM-1725H could be made without
continuity problems during longer runs . TEAl starvation remained
another significant operating issue .
In addition to the objectives for UCAT-J run 7, the goals of
UCAT-J Run 16 were to implement measures developed by process R&D
to control resin stickiness and TEAl levels and to demonstrat e
acceptable operability and continuity of UCAT-J in reactor 2 . As
in UCAT-J run .15, to control resin stickiness process R&D
recommended that ethylene partial pressure be lowered below 90
psi . UCC also planned to use periodic TEAl shots to minimize
TEAl starvation . However, UCC was unsure whether these steps
would be successful .
y
t
UCAT-J run 16 was generally successful . UCC controlled
resin stickiness by lowering the ethylene partial pressure below
- 98 90 psi, and UCC was able to maintain good catalyst productivity .
Overall, operability and continuity were good throughout the run .
However, while flowability, improved, it was still slightly worse
than the flowability that could be achieved using M-1 .
Furthermore, there was some TEA1 starvation due to the TEAl feed
system, though less than had occurred during previous runs .
Therefore, the information gained was valuable to-UCC but process
R&D still had some concerns .
According to a PCD for DJM-1725H, UCC produced 3,653,813
pounds of aim-grade and 966,350 pounds of off-grade base resin
during UCAT-J run 16 . Petitioner .claims as QREs costs associate d
with producing 3,665,,150 pounds of aim-grade and 966,350 pounds
of off-grade base resin during UCAT-J run 16 .
f.
DJL-5264H and DJL-5280H (UCAT-J Runs 8, 9,
18,and 1 9
UCAT-J runs 8 (DJL-5264H) and 9 (DJL-5280H) were the nex t
experimental runs of HDPE molding resins after UCAT-J run 1,
which UCC aborted before it could draw any meaningful
conclusions . Following UCAT-J run 1, process R&D took a year to
evaluate UCAT-J molding resins in the pilot plant before
conducting another experimental run at Star . UCC determined that
UCAT-J was equivalent to M-1 with respect to reactor operability
and continuity when making DJL-5264H .and DJL-5280H at its pilot
plant, but UCC was still uncertain whether UCAT-J would perform
as well at, Star . UCC had not yet determined that it could make
- 99
DJL-5264H or DJL-5280H consistently on'full-scale commercial
reactors before UCAT-J runs 8 and 9 .
The objectives of UCAT-J runs 8 and 9 were to : (1) Produce
sufficient product for customer qualification ; (2) run reactor 1
at normal Star rates with operability equivalent to that achieved
using M-1 ; (3) reach aim-grade production within a specified
period ; and (4) produce no significant off-grade materia l
The primary risks UCC identified for UCAT-J runs 8 and
9
were : (1) TEAL starvation ; (2) resin carryover ; and (3)
difficulties with CO kills, if they were . necessary . To reduce
the risk of TEAL starvation, UCC'measured aluminum and titanium
during the run and gave the reactor periodic TEAl .shots ._ Since
TEAl starvation had not, been a problem with M-1, these
measurements were not taken during commercial runs using M-1 .
Although resin carryover was listed as a risk on the strategic
run plan for UCAT-J runs 8 and 9, according=to the strategic run
plan UCC did not actually'expect resin carryover to be a problem .
UCAT-J runs 8 and 9 were generally successful . Reactor 1
demonstrated acceptable operability and continuity'and .all othe r
run objectives were met . There was some melt index variatio n
(resin in some hopper cars had a higher melt index than the resin
in others), but this . was not significant problem . Some TEAl
starvation also occurred, but it did not cause the resin to go
off grade ; and UCC determined that it could most likely fix the
a
100 problem by implementing a different TEAL system . Because UCAT-J
runs 8 and 9 each lasted only 1 day, UCC did not have time to
fully evaluate operability and continuity . However, the
information UCC gained was valuable, and-one or two more
successful experimental runs would establish, to UCC's
satisfaction that the process was ready for commercialization .
UCAT-J runs 18 and 19 were the next experimental runs of
DJL-5264H and DJL-5280H . The operability and continuity of
reactor 1 in making these products remained uncertain before
these runs, as only a few short HDPE molding resin runs had bee n
conducted up to this point with mixed results .
The primary objectives of UCAT-J run 18 were,to operate at
normal Star rates with operability equivalent to that achieved
using M-1-and to make a maximum of 250,000 pounds of off-grade
material .
UCAT-J run 18 yielded 825,000 pounds of off-grade material,
which indicated poor operability, particularly poor control of
the resin properties in the reactor . There were also problems
with the product purge bin, poor flowability, and poor melt index
control . However, UCAT-J run 19 was generally successful .
According to a PCD for DJL-5264H, UCC produced 6,135,634
pounds of aim-grade and 797,750 pounds of off-grade base resin
during 1995, including both UCAT-J runs 8 and 18 . Postrun
documentation indicates that UCC produced 933,000 pounds of aim-
- 101 grade base resin during run 8 and 5,313,000 pounds of aim-grade
and 825,000 pounds of off-grade base resin during UCAT-J run 18 .
Petitioner claims as QREs costs associated with producin g
6,143,300 pounds of aim-grade and 797,750 pounds of off-grade
resin during UCAT-J runs 8 and 18 combined .
According to a PCD for DJL-5280H, UCC produced 1,864,465
.pounds of aim-grade base resin in 1995, including both UCAT-J
runs 9 and 19 . Postrun documentation indicates that UCC produced
851,844 pounds . and 1,331,804 pounds of aim-grade base resin
during UC.AT-J runs 9 and 19, respectively . Petitioner claims as
QREs costs associated with producing 1,750,532 pounds of aimgrade base resin during UCAT-J runs 9 and 19 combined .
g .
DJH-2580H and DJH-2950H (UCAT-J Runs 10 and
12
UCC made DJH-2580H (UCAT-J run 10) in two short runs in 1992
and 1993 . The run in 1993 produced about 17 hopper cars of base
resin that customers accepted . However, the 1992 and 1993 runs
of DJH-2580H presented significant operability problems . DJH2950H (UCAT-J run 12) was a difficult product to run and had
never been made at Star .
The primary objectives of UCAT-J runs 10 and 12 were to
produce these resins with acceptable product properties,
particularly fractional melt index, and to demonstrate acceptable
reactor operability and continuity .
102 UCAT-J run 10 ran for 3 days and then transitioned to DJH2950H (UCAT-J run 12) . Significant sheeting problems developed
after the transition . The reactor was mini-killed and restarted, .
but the sheeting . continued and became worse . As a result ,
Reactor 2 had to be shut down so that the sheets could be
physically removed with a suction truck and chainsaws . Opening
the reactor to remove sheets exposes the reactor to oxygen and
can cause problems in subsequent runs . As a result of th e
sheeting, UCC aborted they runs and reactor 2 was restarted with
M-1 because resuming operation with UCAT-J was considered to be
too risky in the light of UCC's overall business considerations .
However, some aim-grade resin was produced during the runs and
was sold to customers .
Process R&D suspected that the sheeting that first developed
after the transition to DJH-2950H (UCAT-J run 12) was due to the
high molecular weight of the DJH-2950H resin, and the sheeting
that developed after the mini-kill was due to static . Because of
the significant sheeting problems experienced during these runs,
process R&D moved testing of DJH-2580H and DJH-2950 to Seadrift
before returning the testing to Star . UCC imposed a moratorium
restricting fractional melt index products from operation at
Star .
According to a PCD for DJH-2580H, UCC produced 2,601,86 1
pound of aim-grade and 578,450 pounds of off-grade base resin
103 during UCAT-J run 10 . Petitioner claims as QREs costs associated
with producing 2,668,500 pounds of aim-grade and 578,450 pounds
of off-grade base resin during UCAT-J run 10 .
According to a POD for DJH-2950H, .UCC produced 132,324
pounds of aim-grade and 148,750 pounds of off-grade base resin
during UCAT-J run 12 . Petitioner claims as QREs costs associated
with producing 132,800 pounds of aim-grade and 148,750 pounds of
off-grade base resin during UCAT-J run 12 .
h.
DJL-5420H and DJL-5143H (UCAT-J Runs 13 and
14
Although UCC had successfully produced high density molding
base resins in the pilot plant using UCAT-J, it had never made
DJL-5420H (UCAT-J run 13) or DJL-5143H (UCAT-J run 14) at Star
before these runs .
UCC's .objectives for UCAT-J runs 13 and 14 were to : (1)*
Produce requested quantities of each resin for customer
qualification (about four hopper cars for each product) ; (2) ru n
reactor 1 at normal Star rates with operability equivalent t o
that achieved using M-1 ; (3) reach aim-grade production within a
specified period ; and (4) produce no significant off-grade
material .
UCC was concerned about the risks of : (1) TEAl starvation ;
(2) resin carryover ; and (3 )
difficulties with CO kills, if they
were . necessary . UCC planned for both of these runs to be short
because of the risk associated with UCAT-J .
41
104 Several operability issues occurred during the runs,
particularly minor sheeting during UCAT-J run 13, cold bands
after .the transition to DJL-5143H, and the formation of spongy
agglomerates . A cold band is an area where . the reactor wall is
cold and it indicates that there is enough static to cause resin
to stick to the walls and create sheeting . The spongy
agglomerates that formed were similar to the substances that
formed during UCAT-J run 1 .
Despite these problems, UCC considered the runs to be a
success . However, because these were short runs, . UCC would need
to continue to evaluate the resins to determine whether
continuity issues would arise on longer runs .
According to a PCD for DJH-5420H, UCC produced 696,181
pounds of aim-grade base resin during UCAT-J run 13 . Petitioner
claims as QREs costs associated with producing 696,981 pounds of
base resin during UCAT-J run 13 .
According to a PCD for DJL-5143H, UCC produced 1,006,947
pounds of aim-grade base resin during UCAT-J run 14 . Petitioner
claims as QREs costs associated with producing 1,008,181 pounds
of aim-grade base resin during UCAT-J run 14 .
i .
DJM-1720H (UCAT-J Run 17 )
DJM-1720H had never been made at Star before UCAT-J run 17 .
Two of the goals of this run were to implement measures developed
by process R&D to control resin stickiness and TEAl levels (first
I
- 105 -
implemented in UCAT-J runs 15 and 16, discussed above) and 't o
demonstrate' acceptable operability and continuity of UCAT-J i n
reactor 2 with these products . The other run objective s
identified in pre.-run documentation were to : (1) Produce the
requested quantities of resin'for'customer qualification (fou r
hopper cars) ; (2) run reactor 2 at normal production rates ; (3)
reach aim-grade production within a specified'period ; and (4)
produce no significant off-gradematerial attributable to UCAT-J .
DJM-1720H is an LLDPE resin, which tends to be -very sticky
and had shown poor flowability in previous runs . TEAl starvatio n
remained another significant operating-issue . As in UCAT=J runs
15 and 16, to control resin stickiness process R&D recommended
that ethylene partial pressure be- lowered below 90 psi . UCC
still considered this change to reactor conditions to be
experimental. UCC also planned to give the reactor periodic TEAl
shots to minimize TEAL starvation .
UCAT-J run 17 was generally successful . UCC controlledresin stickiness through ethylene partial pressure, and UCC was
able to maintain good catalyst productivity . Overall,
operability and continuity were good throughout the run .
However, while flowability improved, it was still slightly worse
than the flowability achieved using M-1 . Furthermore, there was
some TEAl starvation due to the TEAL,feed system, though less
than during previous runs .- Therefore, the information gained was
- .106 valuable to UCC, but process R&D still had some . concerns .
Following UCAT-J runs 16 and 17 UCC planned to implement a new
TEAL feed system for all of Star . Ultimately this alleviated the
TEAL starvation issues . ..,
According to a PCD for DJM-1720H, UCC produced 866,625
pounds of,aim-grade and 520,100 pounds of off-grade base resi n
during UCAT-J run 17 . Petitioner claims as QREs the costs
associated with producing 895,700 pounds of aim-grade and 520,800
pounds of off-grade base resin .
III .
Claimed Cost s
One of petitioner's expert . witnesses, Wendi Hinojosa,16 was
responsible for costing the claim projects . Ms . Hinojosa was
qualified as an expert in the accounting systems and
documentation used by UCC in the credit years and the base
period . Petitioner claims as QREs .incurred by UCC in connection
with the claim projects $23,356,600 for 199 .4 and $32,114,800 for
1995 .
A.
Cost Documentation Used
1.
PCDs and MASs
.
The primary cost accounting records that Ms . Hinojosa used
to calculate the cost of . the supplies used in the claim projects
were PCDs and material accounting summary reports (MASs) . PCD s
"16Ms .' Hinojosa 's qualifications are set out in the Opinion
section, below .
107 and MASs were part of UCC's material accounting system used to
track variable costs (costs that .vary with production) such as
raw materials, catalysts, and other materials used in the
manufacturing process . UCC used the material accounting system
during both the credit years and the base period . There were no
significant differences in UCC's material accounting system and
related documentation during these two timeframes .
The PCD was UCC's official cost accounting record for
products that it manufactured . PCDs contained detailed cost
information for every product that UCC manufactured, including
the materials and quantities used in production . PCDs were
produced monthly and annually, not for particular projects . The
PCD for any given year consisted of approximately 3,000 pages .
MASs are inventory control reports containing a transaction
summary for every material UCC manufactured or purchased, each of
which was assigned a unique product code . Material production
and consumption information was contained in both PCDs and MASs .
However, PCDs were organized by manufactured product, whereas
MASs were organized in numerical order by product code and listed
all transactions for each product code by location .
2 .
CMAI Data for Ethylene Byproduct s
Additional products made during the manufacturing process of
the primary product were listed as byproducts on PCDs . UCC's
- 108 material accounting system treated the cost of byproducts as a
reduction in the cost of the primary product .
Taft's hydrocarbons unit made several ethylene byproducts
such as propylene, butadiene, dripolene, hydrogen, methane, and
acetylene . Because these, byproducts are made from the same
starting materials as ethylene, it is difficult to separately
allocate the supply costs, attributable to each byproduct . For
this reason, Ms . Hinojosa used historical 1994 and 1995 market
values of ethylene byproducts as a proxy for their supply costs .
These market values were provided by Chemical Market Associates,
Inc . (CMAI), a leading petrochemical industry consulting and
research firm .
Ms . Hinojosa used the byproduct values provided by CMAI to
calculate the supply costs incurred in conducting the UOP GA-155
project on the Olefins-1 unit's, C3 column, which produce d
ethylene byproducts (such as . propylene, butadiene, and dripolene)
as opposed to ethylene, which had already been separated off in
the C2 column . In addition, Ms . Hinojosa deducted these
byproduct values from Taft's total ethylene production cost, from
which she calculated the supply costs'for the Amoco anticoking
and sodium borohydride projects . This treatment of byproducts
avoided double-counting the supply costs incurred in conducting .
the claim projects .
- 109 3 .
Wage Informatio n
UCC's accounting system tracked budgeted and actual period
costs (fixed costs,' costs that do not fluctuate with production)
such as labor . . UCC's accounting system generated accounting
records known as account levels .' Account levels are the best
source of information for calculating wage costs . However,
account levels were not available for the credit years .
Therefore, for the claim projects conducted in Taft's
hydrocarbons unit-(the Amoco anticoking, spuds, UOP GA-155, and
sodium borohydride projects), Ms . Hinojosa used the annual
salaries found on Forms'W-2, Wage and Tax=Statement, for specific
employees involved in the projects . For the UCAT-J project, Ms .
Hinojosa used Star budget reports that provided the total wage
cost during the claim years and allocated that cost using the
percentage of PE pounds produced during the UCAT-J runs relative
to Star's total PE production during the same period . Wages
represented 1 percent of the total cost of all of the claim
projects .
4 .
R&D Budget s
Ms . Hinojosa did not refer to budgets prepared by UCC during
the credit years . UCC's hydrocarbons R&D department did not
prepare formal budget-proposals specific to individual projects,
but it did prepare an overall R&D budget that referenced variou s
projects that would occur during the year . The R&D budget
,4
110 generally included wages, laboratory materials, travel, and
extraordinary expenses . Plant materials were generally . included
in the plant budget, not the R&D budget . Accordingly, R&D did
not account for feedstock or fuel when estimating how much of its
budget would be allocated to projects conducted on commercial
plants . .
B .
Costs of the Amoco Anticoking Project
1 .
Supplie s
Ms . Hinojosa calculated the supply costs of the Amoco
anticoking, spuds, and sodium borohydride projects on the basis
of-the total ethylene manufacturing cost of Taft's hydrocarbons
unit in 1994 and 1995 . Ms . Hinojosa identified the materials as
material quantities used to manufacture ethylene at Taft from the
relevant PCDs and MASs .
In calculating Taft's total ethylene production cost for
1994 and 1995, Ms . Hinojosa included only major components of
supplies that were supported by available accounting records .
Specifically, Ms . Hinojosa included certain materials purchased
from third-party vendors and certain internally produced
materials .
Ms . Hinojosa did not include-any general plant utilities
such as electricity, treated water, nitrogen, or compressed air
in her calculations . However, Ms . Hinojosa,did include the cost
of the fuel gases (such as natural gas, methane, and hydrogen)
- 111 used to fire Taft's ethylene furnaces and the refrigeration used
in the cold section of the ethylene production process . Ms .
Hinojosa included these costs because itwas necessary to rapidly
reduce the temperature of the raw material-stream at various
points in the production process in order to maximize the
production of ethylene . To the extent that these costs are
considered utilities, Ms . Hinojosa considered them to be
extraordinary costs, different from general plant'utiIities,
because of the energy-intensive nature of the ethylene production
process relative to UCC's other manufacturing units .
Ms . Hinojosa used the-relevant pages from the 1994 and 1995
MASs to calculate UCC's actual per-unit cost for both
This text is long and has been trimmed here. Open the source document for the complete record.
This is a copy of a public record, reproduced as it was published. It is not legal advice, and it may not be the version a court would rely on. Check the official source before you cite it.