UNITED STATES TAX COURT
Agency decision
Ask Donna
What actually matters in this document.
Text
SERVICE
T.C. Memo. 2005-208
UNITED STATES TAX COURT
FPL GROUP, INC. AND SUBSIDIARIES, Petitioner v.
COMMISSIONER OF INTERNAL REVENUE, Respondent
Docket No. 5271-96.
Filed August 31,
2005.
Robert T. Carney, Paul S. Manning, and Christopher
Faiferlick, for petitioner.
Beniamin A. DeLuna, James F. Kearney, Robert Dillard, and
Donald Burkhart,
for respondent.
SERVED .AUG 3 1 2005
2 CONTENTS
MEMORANDUM FINDINGS OF FACT AND OPINION .
FINDINGS OF FACT
.
.
.
.
.
.
.
.
.
.
.
4
. . . . . . . . . . . . . . . . . . . . . . . 5
A.
Nuclear Fuel Assemblies . . . . . . . . . . . . . . . . . . 8
B.
Miscellaneous Nuclear Property . . . . . .
1. Main Steam Isolation Valve (MSIV) Air
.
.
.
.
.
.
.
14
Accumulation System. . . . . . . . . . . . . . . .
2.
042 14
.
.
.
.
.
.
16
3.
Reactor Vessel Probes
4.
Raceway Protection System
.
.
.
.·.
.
.
.
.
.
6.
7.
Area Radiation Monitoring System .
Nuclear Fuel Transfer System . . .
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
25
27
. . . . . . . . . . . . . . . . .
29
5.
C.
Surveillance System for Heat Exchangers
Spent Fuel Rack Systems
Environmental Property
1.
. . . . . . . . . . . . . . .
.
.
.
18
19
. . . . . . . . . . . . . .
.
.
Wastewater Neutralization Treatment System .
21
.
.
.
.
29
.
.
.
2. .PCB Transformers . . . . . . . . . . . . . . . . . .
D.
Simulator and Training Buildings .
.
36
E.
Load Management System . . . . . . . . . . . . . . . . .
41
F.
St. Lucie Backfit Construction . .
1.
Underwater. Intrusion System .
2.
Condensate Polisher Tie Line .
.
.
.
48
49
52
. . . . . . . . . .
56
3.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
33
.
.
.
.
.
.
.
.
.
.
.
.
Instrument Air Upgrade . . . . . . . . . . . . . . .
54
G.
St. John's River Power Park (SJRPP)
H.
The Southern Company Contracts .
.
.
.
.
.
.
.
.
.
.
66
I.
Integrated Transmission Line Systems .
.
.
.
.
.
.
.
.
.
74
J.
Distribution and Transmission Substations
.
.
.
.
.
.
.
80
K.
Regional Planning
. . . .. . . . . . . . . . . . . . . .
82
OPINION . . . . ... . . . - ·. . . . . . . . . . . . . . . . .
87
A.
The Statutory Landscape . . . . . . . . . . . . . . . . .
87
B.
TRA Section 204 (a) (3)--Supply or Service Contracts
92
.
.
.
.
.
- 3 1.
Property Purchase.d and/or Installed Pursuant
to the Tariff . . . . . . . . . . . . . . . . . . .
2.
3.
The Tariff Is Not a Contract for
Purposes of.TRA Section 204 (a) (3)
. . .
b. .
The Tariff Does Not Readily Identify the
Property in Issue . . . . . . . . . . .
c.
Documents Incorporated by Reference Into
the Supply or Service Contract . . . .
d.
Property Readily Identifiable From the
Related Documents
. . . . . . . . . . .
e.
Class Life of Nuclear Fuel Assemblies
Pursuant to TRA Section 203(b) (2)
. . .
Are the Southern Company Contracts TRA Section
204 (a) (3) Supply or Service Contracts? . . . .
Are the DRI Documents TRA Section 204 (a) (3)
94
a.
.
.
95
.
. 101
.
. 102
.
. 106
.
. 124
.
. 128
Supply Contracts? . . . . . . . . . . . . . . . . . 134
C.
TRA Section 203 (b) (1) (A)--The "Binding Contract" Rule
1. Nuclear Fuel Transfer System . . . . . . . . . .
2.' Southern Interchange Contract
. . . . . . . . .
3.
LMS Equipment Under A.B. Chance Contract . . . .
4.
St. John's River Power Park (SJRPP)
. . . . . .
D.
TRA Section 203(b) (1) (B)--"Self-Constructed Property" . . 152
1.
"Wrap Up" Work and "Enhancements and
Deficiencies" Work at the SJRPP . . . . . . . . . . 158
2.
Distribution and Transmission Substations . . . . . 165
3. . Transmission Line Systems
. . . . . . . . . ... . 169
4.
"Backfit" Items at St. Lucie . . . . . . . . . . . 176
a.
Underwater Intrusion System .. . . . . . . . 177
b.
Condensate Polisher Tie Line . . . . . . . . 179
c.
Instrument Air Upgrade . . . . . . . . . - :. 181
5.
Spent Fuel Rack Systems . . . . . . . . . . . . . . 184
E.
TRA Section 203(b) (1) (C)--"Plant Facility Rule"
1.
"Backfit" Items at St. Lucie . . . . . . .
2.
"Wrap up" Work and "Enhancements and
Deficiencies" Work at the SJRPP . . . . . .
a.
Written Specific Plan . . . . . . .
b.
Costs Committed or Incurred . . . .
3.
Distribution and Transmission Substations
a.
Written Specific Plan . . . . . . .
b.
Commencement of the Construction . .
c.
Costs Committed or Incurred . . . .
-
.
.
.
.
.
.
.
.
.
.
136
138
140
144
147
.
.
.
.
.
.
. 187
. 189
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
191
192
194
196
197
199
202
Conclusion . . . . . . . . ". . . . . . . . . . . . . . . . . 204
Appendix A:
Equipment Installed at Substations .
Appendix B:
DRI Project
.
.
.
.
.
. 205
. . . . . . . . ;... . . . . . . . . 208
MEMORANDUM FINDINGS OF FACT AND OPINION
RUWE, Judoe:
Respondent determined the following
deficiencies in pet=itioner's Federal income taxes:
Year
Deficiency
1988
1989
1990
1991
1992
$922,601
15,183,930
5,228,640
1,788,565
5,867,463
Petitioner did not make any claim for investment tax.credits
(ITCs)
in its original returns for the taxable years 1988,
and 1990.
1989,
On the same date that respondent issued the notice of
deficiency, petitioner filed Forms 1120X, Amended U.S.
Corporation Income Tax Returns
years 1988, 1989, and 1990.
(amended returns),
for its taxable
In the amended returns, petitioner
claimed additional ITCs1 as follows:
Year
1988
1989
1990
Amount
.
$33,308,287
44,336,798
55,760,749
On March 21, 1996, petitioner filed its petition in this
case listing these same amounts.
In its first.and second amended
1 In the amended returns, petitioner claimed refunds.
- 5 petitions, petitioner reduced its claim for additional ITCs as
follows:
Year
Amount
1988
1989
1990
$31, 737, 038
41,553,822
51, 973, 051
.
.
On January 14, 2002, petitioner submitted its trial
memorandum in which it further reduced' the additional ITCs
clairäed as follows:
Year
Amount
1988
1989
1990
$7, 681, 335.
7,862,335
13, 320, 9.79
The issue addressed in this opinion is whetl3er FPL Group,
Inc., & Subsidiaries (FPL) is entitled to ITCs for certain
property and equipment it placed in service during. the taxable
years 1988, 1989, and 1990.2
Resolution of this issue requires
us to explore the strictures of the Tax Reform Act of 1986 (TRA),
Pub. L. 99-514, 100 Stat. 2058, which repealed the ITC and
provided relief from the ITC repeal iri transitional rules.
FINDINGS OF FACT
Some of the facts have been stipulated and are so found.
The stipulation of facts, the first, second, third, and fourth
supplemental stipulations of facts, and "the accómpanying exhibits
2 This case involves multiple issues. The ITC issue
addressed in the opinion was tried and briefed separately.
- 6 are incorporated herein by this reference.
Petitioner's
principal place of business was in North Palm Beach, Florida,
when its petition was filed.
Petitioner is the parent corporation of a publicly traded
holding company that filed consolidated Federal income tax
returns on a·calendar year basis for its 1988 through 1992
taxable years.
FPL is a first-tier, wholly owned subsidiary of
petitioner with operations throughout most of the east and lower
west coasts of the State of Florida and is a member of the
consolidated group.
As a public utility, FPL is subject to
regulation by various State and Federal agencies, including the
Florida Public Service Commission (FPSC), the Federal Energy
Regulatory Commission (FERC), and the Nuclear Regulatory
Commission
(NRC).
To generate electricity, FPL operates nuclear and nonnuclear
power plants.
FPL owned and operated four nuclear electric
generating units, named:
St. Lucie Unit 1, which was operational
commencing in 1976; St. Lucie Unit 2, which was operational
commencing in 1983; Turkey Point Unit 3, which was operational
commencing in 1972; and Turkey Point Unit 4, which was
operational commencing in 1973.
During the years at issue, FPL was under the jurisdiction of
the FPSC, which regulated and supervised the rates charged by and
the services provided.by FPL to its customers.3
.FPL's charges to
its customers for their use of electricity were based upon a
tariff.
A tariff is a document,that contains the terms,
conditions, rates, and charges that a company may charge and a
customer must pay.for the,service offered by a utility.
According to the tariff, "Service under the tariff is subject to
orders of governmental bodies having.jurisdiction and to the
currently effective 'General Rules and Regulations for Electric
Service' on file with the Florida Public Servïce Commission."
From time to time, FPL could, and did, request adjustments to the
tariff rates, terms, and conditions.4
FPL's customers did not
3 Michael Wilson, FPL's vice president of government
relations and a former FPSC commissioner, testified:
The Public Service Commissioner provided economic
regulation of those utilities which the legislature put
in their charge or their jurisdiction which entailed
setting rates for various classes of customers,
determining the investment level that companies had,
quality of service regulation, hearings on a number of
different issues regarding service and rates.
4 Mr. Wilson testified:
a company which decides that it is not receiving a
reasonable return on its investment or costs have.gone
up would apply to the Public Service Commission for a
rate increase.
* * *
Those would be the subject of hearings.and
testimony by public counsel, by intervenors, large,
industrial customers * * *
Claude Villard was a nuclear.fuel witness for FPL before the
FPSC from 1995 to 1997.
He testified:
(continued...)
sign the tariff.
Under the tariff, a customer may obtain service
from FPL by ipplying in writing, by telephone, or in person.
The
tariff included a Èuel clause, whiah calculated the cost of fuel
and of purchased power in aácordance with a formula "to reflect
the cost of fóssil and nuclear fuels and purchased.power for ·each
kilowatt-hour deliver'ed".
A.
Nuclear Fuel Assemblies
FPL claims ITCs for nuclear fuel assemblies in the 1988,
1989, and 1990 taxable years.
Gene'rally, to generate electricity
at a pbwer plant, a heat source heats water to form steam, which
drives a turbine of an electric generator.
At a nuclear power
plant, the heat source is a nuclear fission reaction in a nuclear
reactor.
The nuclear fission reaction occurs in the "core" of
the reactor where an arrangement of nuclear fuel assemblie.s (fuel
assemblies or nuclear fuel) is located.
Essentially, a fuel
assembly is loaded with nuclear fuel rods, which house enriched
uranium pellets.
Fuel fabrication refers to the process of
making the pellets, putting those pellets into a fuel rod, and
bundling these rods together into different support cogponents to
make a fuel assembly.
4 (...continued)
under [F]PSC rules, every six months Florida Power and
Light has to submit to the [F]PSC the costs that it
intends to recover from the customer. And it has to
have it approved by the [F]PSC * * *...
- 9 Nuclear fuel must be replaced because.it wastes over time
and from use.
During the years at issue, FPL's nuclear reactor
units used an 18-month reloading cycle; it replaced one-third of
the fuel assemblies in the reactor core with new fuel assemblies
every 18 months.5
In 1988, 1989, and 1990, petitioner
depreciated the nuclear fuel over 5 years for tax purposes.
The fabrication of fuel assembli^es is a multistep process.
The first step in the process is the acquisition of uranium from
the mines.
The second step is to convert the uranium to uranium
hexafluoride .(UF6), a gaseous compound.
The third step is the
enrichment process, which.is accomplished by.increasing the
amount of uranium 235 in the gas.
The fourth step is to convert
the gas into U2, a uranium oxide powder.
The uranium oxide
powder is pressed into pellets, which are then loaded into tubes
or rods.
The rods are then bundled together to form a fuel
assembly.
The design of the fuel assemblies is specific to the
type of reactor used.'
5 Mr. Villard testified that the reload took about 1 week to
complete, during which time the power plant was shut down.
6 FOr example, One Of FPLfs nuclear power plants, the St.
Lucie Unit 1 reactor, is a 14 by 14 array of fuel rods, whereas
another of FPL's nuclear power plants, Turkey Point Units 3 and
4, uses a 15 by 15 array.
- 10 FPL entered into a series of long-term contracts.to meet its
expected fuel assemblies needs.'
In 1979, FPL.entered into an
.
agreement of settlement with Westinghouse Electric Corp.
(Westinghouse)
to supply FPL. with uranium;
Under the agreement,
Westinghouse agreed to supply FPL with uranium at a rate of
135,000 pounds per year beginning in 1987 and continuing for 7
years, through. and including 1994, or a total of 1,080,000
pounds. - The agreement gave FPL the. option to terminate the
agreement upon~ 6 months' prior written notice to Westinghouse
with no consequences.
.
Additionally, FPL could cancel the
agreement if Westinghouse failed -to meet specific delivery
deadlines.
Similarly, on July 25, 1978, FPL, entered into a sales
agreement with International Minerals & Chemical Corp.
(IMC) to
deliver a minimum of 400,000 pounds of "uranium concentrates" per
year for 13 years.
IMC and FPL entered into a.seconds sales
agreement on October 4, 1978, under which FPL purchased uranium
concentrate.
On September 9, ·1974, Potomac Elec.tric Power Co.
(PEPCO) and
Kerr-McGee Nuclear Corp. executed a contract to.chemically
process uranium.
This agreement called for the conversion of
Mr. Villard testified that to change to another NRCapproved supplier, it would take at least 3 to 4 years before
actually getting the first new full ba.tch to be delivered. The
process of changing to a supplier not approved by the NRC took 5
to 10 years.
- 11 10,190,700 pounds of uran.ium concentrates.into UF6 from 1978
through 1990.
to FPL.
On Febru.ary 10, 1978, this agreement was assigned
T.he contract was never. terminated.
On October 23, 1984, FPL entered into a contract with the
Department of Energy (DOE) under which the DOE agreed to provide
FPL with a minimum of 70 percent of FPL's enrichment services.8
The term of th.e contract was the lesser of the life of the
nuclear power facility or 30 years.
FPL could terminate the
contract at no cost with.10 years' advance notice.· On April 29,
1985, FPL and the DOE entered into an amendment to the contract
to provide additional supply.
On February 11,
1985, _FPL entered
into a contract for sale with AGIP URANIO' S.p.A. for certain.
uranium enrichment services.
The contract was terminated as of
September 30, 1987.
On November 5, 1979, FPL entered into a contract with
Westinghouse for the purchase of services to design- and fabricate
fuel assemblies for Turkey} Point Units' 3 and 4.
FPL could
terminate the contract "only if Turkey' Point 3, or Turkey Point 4
is permanently shut down for any reason whatsoever."
On January 30, 1982, ÝPL entered into a contract with Exxon
Nuclear Co. for thë 'supply and delivery of fuel assemblies.
According to the contract, "FPL may terminate Reload Regions
The contract provided that FPL had no obligation to
.purchase enrichment services from the DOE in the fiscal years
1984, 1987, and 1988.
- 12 -
other than [Region] XN-1 for convenience by giving Seller notice
of such termination no later than seventeen (17) months prior to
the * * * [preliminary scheduled delivery date] that is to be
terminated."
FPL budgeted the costs associated for each step in the fuel
assembly process.
Carl R. Bible, Jr., an FPL engineering
manager, testified that "Budget items are used to authorize funds
to be expended on various activities."
A 1986 Capital
Expenditures Budget Item (budget item or BI) No. 562 lists the
gross cost of.~expenses to convert uranium concentrates to UF6 as
$1,925,000.9
A 1986 BI No. 563 lists the gross cost of
enrichment services as $21,-397,000.1°
A 1986 BI No. 564 for
fabrication of nuclear fuel for St. Lucie Unit 1 (including
engineering and design work) lists the gross cost as $600,000."
9 The budget item breaks down the expenditure as $1,717,000
in gross property additions and $208,000 for an allowance of
funds during construction. This budget item was approved on Oct..
14, 1985, and contemplated a projected 5-year schedule for
conversion as follows: $1,717,000 for 1986; $2,282,000 for 1987;
$2,794,000 for 1988; $4,097,000 for 1989; and $3,673,000 for
1990.
1° The budget item breaks down the expenditure. as
$19,266,000 in gross property additions and $2,131,000 for an
allowance of funds during construction. This budget item was
approved on Oct. 14, 1985, and contemplated a pro'jected 5-year
schedule for enrichment as follows: .$19,266,000 for 1986;
$20,318,000 for 1987; $43,826,000 for 1988; $29,544,000 for 1989;
and $33,786,000 for 1990.
The date that this budget item was approved is illegible
on the Court's copy. The budget item contemplated a projected 5(continued...)
A 1986 BI No. 565 for fabrication of nuclear fuel for St. Lucie
Unit 2 (including ehgineering and design work) lists the gross
cost as $2,151,000."
A 1986 BI No. 566 for fabrication of
nuclear fuel for Turkey Point Unit 3 lists the gross cost.as
$4,640,000."
A 1986 BI No. 567 for fabrication of.nuclear fuel
for Turkey Point Unit 4 lists the gross cost as $760,000."
A
1986 BI No. 561 for uranium purchases for Turkey Point Units 3
(...continued)
year schedule for fabrication expenses as follows: $600,000 for
1986; $9,921,000 for 1987; $9,775,000 for 1988; zero for 1989;
and $10,940,000 for 1990.
" The budget item breaks down the expenditure as $1,651,000
in gross property additions and $500,000 for an allowance of
funds during construction. This budget item was approved on Oct.
14',·1985, and contemplates a projected 5-year schedule for
fabrication expenses as follows: $1,651,000 for 1986;
$10,932,000 for 1987; $9,.310,000 for 1988; $3,984,000 for 1989;
and $12,009,000 for 1990.
The.budget item breaks down the expenditure as $4,433,000
in gross property additions and $207,000 for an allowance of
funds during construction.
This budget item was approved on Oct.
14, 1985, and contemplates a projected 5-year schedule for
fabrication expenses as follows: $4,433,000 for 1986; $1,337,000
for 1987; $3,593,000 for 1988; $4,556,000 for 1989; and
$2,450,000 for 1990.
" The budget item breaks down the expenditure as $355,000
in gross property additions and $405,000 for an allowance of
funds during construction. This budget item was approved on Oct.
14, 1985, and contemplates a projected 5-year schedule for
fabrication expenses as follows: $355,000 for 1986; $4,320,000
for 1987; $3,097,000 for 1988; $2,258,000 for 1989; and
$5,253,000 for 1990.
- 14 -
and 4 and St Lucie -Units 1-and 2 lists the gross cost as
$44,545,000.15
FPL placed fuel assemblies in service with total capitalized
costs (tax basis) of $51,684,173, $70,782,440, and $133,263,604
in the.1988, 1989) and 1990 taxable years, respectively.
B.
Miscellaneous Nuclear Property
1.
Main Steam Isolation Valve (MSIV) Air Accumulation
System
The MSIV air accumulation system is a safety item, required
by the NRC, that shuts down a nuclear power plant. and protects
the reactor core in an emergency.
FPL claims ITCs for_the MSIV
air accumulation system in the 1989 and 1990 taxable years.
On July 29, 1985, FPL issued a licensee event report
(licensee event report)," in which its engineering department
determined that the valves ät Turkey Point Units 3 and 4 were
unable to close the MSIV in accordance with its originäl
" The budget'item breaks down the expenditure as
$36,836,000 in gross property,additions and $7,709,000 for an
allowance of funds during construction.
This budget item was
approved on Oct. 14, 1985, and contemplates a projected 5-year.
schedule for fabrication expenses as follows: $36,836,000 for
1986; $42,633,000 for -1987; $50,889,000 for 1988; $63,267,000 for
1989;.and $54,725,000 for 1990.
" A licensee event report is a document required to be
written and submitted to the NRC. When.something at the plant
does not meet design requirements, the report.describes the
problem and the corrective action taken.
- 15 design."
The licensee event report indicates that the design of
the valves will be upgraded to ensure that each valve meets the
final safety analysis report.
An FPL engineering study, issued
in July 1985, "recommended that design modifications be
implemented on an expedited basis" and that continued operation
was warranted.
.
.
A 1987 BI No. 155 includes, inter alia, Main Stream
Isolation.
The budget item contains an October 13, 1986, date
underneath "APPROVED BY - CORPORATE OFFICER".
FPL issued an
expenditure requisition (ER)18 No. 4573 to "Install a low
pressure alr accumulator system".
The ER also states:
"This
emergency ER is being prepared due to the length·of time it takes
to obtain ER approval.
The work is currently scheduled for the
1988 Refueling Outage.
We anticipate this ER to be revised by
October 1988."
The earliest date on the ER is October 1, 1988,
".Mr. Bible testified that in the licensee event report,
FPL committed to the NRC to resolve the valve problem.
18 Richard Engstrom, FPL's supervisor of power plant
accounting, testified as to the distinction between an ER and a
work order as follows:
A work order is basically * * * issued to capture and
record costs associated with a specific project at a
specific location. An ER which stands for expenditure
requisition, it basically identifies the type of work
order such as a transmission work order, distribution
work order, a.specific work order. However, sometimes
they are used interchangeably, particularly when it
comes to a specific work o.rder.
* * *
- '16 which is under a "received" ·stamp.
Additionally,- the ER bears an
October 3, 1988, date underneath a stamp that reads
"Authorization Certified Accounting Department".
The ER,was
revised in early 1989 "to reflect a definitive construction
estimate" and again in early '1991.
With respect to the installation of the MSIV air
accumulation system, petitioner incurred capitalized costs (tax
basis) of $2,846,306 and $126,666, for equipment placed in
service in the 1989 and 1990 taxable years, respectively.
2.
Surveillance System for Heat Exchangers
The surveillan'ce system for heat exchangers (surveillance
system) consisted of temperature and flow instruments to- ensure
that the heat exchanger, which is designed to remove heat,
performed properly.
FPL claims ITCs for the surveillance system
in the 1989 and 1990 taxable years.
On April 15, 1985, FPL responded to a notice of violation
issued by the NRC with respect to its nuclear generating facility
at Turkey Point.
One of the corrective steps articulated in the
letter; was the "development of a surveillance.program".19
19 Mr. Bible testified that this letter was FPL's
"commitment to the NRC to perform these modifications and. put
this system in place.
It's a written commitment from the
officers of our company to the NRC, requiring us to perform these
actions."
- 17 FPL developed or established an action item2o to oversee. the
development of a surveillance.program, which is a system that
monitors the heat exchangers.21, In a request for engineering
assistance, dated November 5, 1985, Turkey Point requested a
modification of its plant.22
ER No. 3811, dated March 1988, and supplemented in October
1988, discussed upgrading the surveillance system at Turkey Point
Unit 3.
Similarly, ER No. 3854, dated:April 1988, with
supplements dated October.1988 and May 1991, discussed- the same
scope of work with respect to Turkey Point Unit 4.
With respect to the acquisition and. installation of the.
surveillance system, petitioner.incurred capitalized costs (tax
basis) of $123,742 and $324,668 for equipment placed in service
during the 1989 and 1990 taxable. years, respectively.
20 An action item is the method by which FPL tracks its
commitments to the NRC.
21 Mr. Bible testified that sthere is typically a 3-year lag
time to comply with the NRC requirements.
22 Mr. Bible testified that a "Request for engineering
assistance is how engineering gets a turn on to perform a project
here." He explained:
What will happen is engineering will produce a
design package, which is how you install things.
It
will show drawings, specifications from buying
equipment, instructions from the field as.to how to
install that equipment and update all the associated
designs for the power 042plant.
- 18 3.
Reactor Vessel Probes
A reactor vessel probe measures the water level in a nuclear
reactor core.
A reactor :vessel probe is custom made and takes up
to 45 weeks to obtain.
FPL claims ITCs for the reactor vessel
probes in the 1988 taxable year.23
As a result of an accident at the Three Mile Island nuclear
facility (TMI), 4 the NRC imposed "Action Plan Requirements",
known as "NUREG-0737", to prevent similar accidents at.other
nuclear plants.
One of the regulatory guidelines2s that resulted
from the TMI a.ccident was the requirement that nuclear plants
monitor'coolant inventory.
FPL's nuclear plants were designed
before this guideline and didt not have reactor vessel probes; as
a result, FPL installed reactor vessel level monitoring
instrumentation.
On July 18, 1.986, FPL sent a letter to the
Office of Nuclear Reactor Regulation, which detailed the
technical specifications concerning its proposed reactor vessel
monitoring system.
On December 5, 1986, the NRC sent FPL a
..23 In -the taxable years 1989 and 1990, petitioner claims
reductions in the amount of the ITC, which resulted from
reductions in the amount of the qualified costs (tax basis) of
the property.
24 The TMI nuclear plant failed to maintain the proper water
level in the nuclear reactor, which resulted in a partial
meltdown in its core.
25 Many of the guidelines were embodied in Regulatory
Guideline 1.97, Instrumentation for Light-Water-Cooled Nuclear
Power Plants 041to
Assess Plant and Environs Conditions During and
Following an Accident, issued by the lHlC and dated May 1983.
- 19 letter detailing,modifications to FPL's próposed changes.
On
July 28, 1987, the NRC sent a letter to FPL advising it that the
technical specifications as modified were approved.
ER No. 9302 details the purchase of two spare reactor vessel
level probes -in the authorized amount of $348,000.
date on the ER is November 1, 1985.
The earliest
The ER was revised to
account for an increase in;cost of the project to $798,223, which
was approved in late 1989.
With respect to the acquisition of the reactor véssel
probes, petitioner incurred capitalized costs (tax basis) of
$862,757, -$126,353,26 and -$12,983 for'equipment placed in
service during the 1988, 1989, and 1990 taxable years,
respectively.
4.
Raceway Protection System
A "raceway" is a system of metal conduits or trays that is
used to transport electric cables from one place to ano'ther
throughout a facility and protects the cables from fire hazards.
FPL claims ITCs for the raceway protection system in the 1989 and
1990 taxable years.
Appendix R--Fire Protection Program for Nuclear Power
Facilities Operating Prior to January 1, 1979, 45 Fed. Reg. 76611
26 Mrl Engstrom testified that negative numbers were a
result of FPL's debit/credit accounting system. On brief,
petitioner explained that the amount of qualified costs (tax
basis) was reduced in the taxable years .1989 and 1990; as a
result, the ITC must be reduced in thóse years.
- 20 (Nov. 19, 1980), contains general and specific redluirements for+
protecting electfic cables from fire hazards.
The specific
requirements section of"appendix R provides detailed requirements
for "separation of cables and .equipment" and "enclosure of cable
and equipment".
In a letter dated October 11, 1985, FPL
explained to the Office of Nuclear Reactor Regulation that
[FPL] notified the 'NRC ·in late Augus't 1985 concerning
an additional scope of work identified relating to * *
* Appendix R requirements at our Turkey Point Nuclear
facility.
The additional scope of Appendix R work was
identified as a result of an evaluation of the original
Appendix R Safe Shutdown analysis, and was completed in
September 1985. In Auguht 1985, based on preliminary
results of the evaluation, FPL committed to provide a
report detailing the additional scope of work and a
proposed schedule for completion of the modifications.
With respect to the St. Lucie plant, a 1984 BI .No. 147 Rev.
2 budgeted $19 million to meet the requirements of appendix R and
was approved on February 21, 1984 .
FPL revised this BI several
times to increase the budgeted amount to $26 million for the St.
Lucie plant.
A 1984 BI No. 933 Rev. 3, approved on March 23, 1984,
budgeted $45 million to "Upgrade the present fire protection
capabilities at Turkey Point Units #3 and #4 to meet * * *
appendix 'R'" requirements.
FPL. revised this BI several times,
and the ultimate authorization was approved in August 1.986 for
$87 million.
- 21 ER No. 4276, approved in 1988, authorized $1.8 million for
fire protection'modifications to the raceway protection for
Turkey Point.
This ER wasv revised'in 1989 to decrease the amount
authorized for the. expenditure to $1,081,459.. 'Similarly, ER;No.
6256, approved in 1989, authorized $10 for the raceway protection
for Turkey Point, which was revised in late,1989 to $358,000, and
revised again in early 1991 to decreabe the amount authorized to
$263,722..With respect to the installation of the raceway protection
systém, petitioner incurred capitalized costs; (tax basis) of
$969,676 and $239,161 for equipment placed in service in the 1989
and 1990 taxable years, respectively.
5.
Spent Fuel Rack Systems
FPL's use of nuclear fuel to generate electricity requires
it to repl,ace one-third of the, fuel assemblies every 18 months.
FPL uses spent fuel racks to store its used nuclear fuel.
FPL
claims ITCs for the spent fuel rack systems in the 1988, 1989,
and 1990 taxable years.
Under the Nuclear Waste Policy Act of 1982,. Pub. L. 97-425,
sec. 302, 96 Stat.. 2257
(nuclear wa 541te=act),
the Federal
Government was required, in e 576change
for fees paid by electric
utilities, to handle the disposal and permanent storaye of.spent
or u^sed fuel beginning in 1998.
The purpose of the nuclear waste
act was to develop repositories for disposing of high-level
- 22 _.radioactive waste and spent nuclear.fuel.
The nuclear waste act
provided that pérsons owning and operating civilian nuclear power
reactors were primarily responsible for providing interim storage
of spent nuclear fuel.
.
Accordingly, FPL was required to store spent nuclear fuel
until 1998; as a.result, FPL needed to expand its on_-site spent
fuel rack system at each. of its nuclear generating plants.
As of
January 7, 1983, the enactment date of the nuclear waste act, FPL
knew the amount' of spent fuel it would need to store and the .
design of the expanded.spent fuel rack systems at St. Lucie and
Turkey Point.
.
FPL removed spent nuclear fuel from.the reactor and
transferred it via the .fuel transfer system to a containment
building, using a series of underwater tunnels.
The spent^fuel
was then transferred from the containment;building to the fuel
handling building.
The spent fuel.rack system at each,of FPL's nuclear
generating plants consisted of two large pools of water,
approximately 40 feet deep, with metal storage racks at the
bottom.
Each·pool and sys.tem of racks was located proximately to
one of the two nuclear.reactors, which were located side.by side.
Because FPL had additional space,in-the pools, it expanded its
storage facilities by increasing the number of storage racks in
the pool.
FPL designed its system so.that each pool could
.
- 23 accommodate the spent fuel of either reactor; in the past, FPL
had obtained licenses to transfer spent fuel from one pool to the
other.
A 1982 BI No. 139, approved on August 30, 1982, budgeted
$300,000 to procure and install spent fuel storage racks to
increase capacity at Turkey Point Unit 3.
A section of the BI
labeled "purpose and necessity" states:
The original design for Turkey Point Unit #3 had a
spent fuel storage capacity of 217 as.semblies.
In 1977
the original racks were.replaced with high density
stainless steel racks which provided a capacity. of 621
assemblies. The capacity was increased due to the lack
of off-site spent fuel reprocessing facilities.
The BI went through several revisions.
Similarly, FPL began expansion of the spent fuel facility at
St. Lucie Unit 1 in 1982.
A 1982 BI No..177, approved on July
13, 1982, budgeted $46 million for various projects at St. Lucie,
including spent fuel storage racks.
series of revisions.
This BI also underwent a
ER No. 9304, dated December 1985,
authorized $1.5 million for "phase I" of the project for design
engineering, to remove the existing spent fuel racks, and to
install new high density racks."
This ER was revised in late
1986 and processed in March 1987 to include construction and
material costs, increasing the amount authorized by about $9.5
This ER was associated with BI No. 190, approved in late
1985, which budgeted $1.5 million for engineering costs for the
St. Lucie Unit 1 spent fuel storage rack project.
- 24 million'to $11 million.
This- ER was again revised in late
1988/early 1989 to decrease the amount of- the authorization by
$2,067,000 to the "present estimate" of $8,933,000.
ER No. 1760, dated late 1986/early 1987, authorized the
expenditure of $12 million to procure and install spent fuel
storage racks for Turkey Point Unit 4.
FPL revised this ER in
late 1988/early 1989 to decrease the amount authorized by $4
million.
A 1986 BI'No. 190, approved in ·late 1985, budgeted $1.5
million to remove the existing spent fuel storage racks at St.
Lucie Unit 1 and install new high density spent fuel storage
racks.
The allotted amount was authorized for engineering with a
total estimated cost of $10.3 million.28
A 1987 BI No. 19829 budgeted $12 million for Turkey Point
.
Unit 4 to "Procure and install spent fuel storage racks to
increase capacity from 614 assemblies to provide sufficient
storage capacity through the end of licensed operation in
2007."3°
28 Mr. Bible testified on cross-examination that this
document showed that no costs were incurred before January 1986.
29 The date that BI No. 198.was approved is illegible.
3° Mr. Bible testified that, according to the document, n.o
construction costs were incurred before January 1987, and only $1
million was scheduled to be incurred in 1987 and.$11, million
thereafter.
- 25 With respect to the acquisition and installation of the
spent fuel.rack system, petitioner incurred capitalized costs
(tax basis) of $6,713,729, $532,892, and $6,646,960 for equipment
placed in service in the 1988, 1989, and 1990 taxable years,
respectively.
6.
Area Radiation Monitorina System
An area radiation monitoring ·system measures the radiation
throughout a nuclear.electric generating plant.
·The system
consists of a local monitor that measures radiation and cabling
to the control room where readouts from all the monitors are
displayed.
FPL claims an ITC for the area radiation monitoring.
system in the 1990 taxable year.
NUREG 0737 and Supplement 1 to NUREG 0737, dated December
17, 1982
provide regulatory guidelines for radiation
mo.nitoring."
On February 23, 1984, the NRC issued an order
confirming FPL's commitments to.comply with Supplement 1 to NUREG
0737 with respect to Turkey Point Units 3 and 4..
J
A 1988 BI No. 145, approved on August 20, 1987, budgeted
$1.9 million to replace the area radiation ·monitoring system.
section of the BI labeled "purpose and- necessity" states:
" According to.these regulatory guidelines:
It is our intent that the guidance documents themselves
* * * are not to be.used as requirements, but rather
they are to be used as sources of guidance for NRC
reviewers and licensees regarding acceptable means for
meeting the basic requirements.
A
- 26 The existing equipment has high maintenance due to
equipment age and unavailability of parts. The
egúipment is obsolete. The replacement of the
equipment is a Nuclear Regulatory Commission (NRC)
Requirement to,meet the recommendat.ions of Regulatory
Guideline 1.97. The full scope of work has not been
defined.
Phase I
- Engineering and Procurement $1,900,000
Phase II - Construction
The total cost of the project is estimated to be
$3,800,000 to $12,500,000 depending on which
alternative is implemented. · The expected completion
date of Phase II is December, 1990.
This BI was revised twice in 1989, decreasing the amount budgeted
for phase I of the project to $550,000.
ER No. 5339, processed on March 3, 1989, authorized $950,000
for an area radiation monitoring system.
The ER states:
This project is to replace the entire existing
Area Radiation Monitoring System with new state of the
art components for Turkey Point.
Purpose and Necessity:
The existing Area Radiation Monitoring ·System
,
regulres very high maintenance, also the equipment is
obsolete. Replacement of the Area Radiation Monitoring
System has been committed to the NRC under compliance
of R.G.- 1.97 Rev. 3.
This is a phased ER:
Phase I
- Engineering= & Procurement
Phase II - Construction
This ER is for engi'neering and procurement only.
The ER will be revised later to include construction.
Removal costs and property retirements will be
addressed when the ER is revised for Phase II. The
authorized amount is included in the 1989 Capital
Budget.
- 27 As indicated above, the ER was revised in late 1990/early 1991 to
increase the amount authorized to $1,350,000.
With respect to the acquisition and installation of the area
radiation monitoring system, petitioner incurred capitalized cost
(tax basis) of.$657,253 for equipment placed in service in the
1990 taxable year.
7.
Nuclear Fuel Transfer System
A nuclear fuel transfer system is an underwater system
consisting of motors and equipment that transports spent nuclear
fuel from the reactor to the spent fuel pool.
FPL reconstructed
its nuclear fuel transfer system at Turkey Point.
The
reconstruction modernized the system by installing a two-cable
hoist, changing a number of monitors that measured the load, and
changing a number of drive motors and associated equipment.
FPL
claims ITCs for the nuclear fuel transfer system in the 1988,
1989, and 1990 taxable years.
A 1984 BI No. 569, approved on October 24, 1983, budgeted
$1,178,000 for the fuel transfer system upgrade for Turkey Point
Units 3 and 4.
The BI describes the work to be performed as: ·
Upgrade the nuclear fuel transfer system on Unit
#3 & #4, with out [sic] of water electric drive motor
(replaces underwater air drive motor), counter weights
on the upenders, winch load monitors for the upenders,
quick opening transfer tube closures, dual cables and
hoist load monitors for the.spent fuel pit bridge crane
hoists.
I.
- 28 BI No. 569 appears to be a revision of BI No. 934, which
originally authorized $831,000 in 1982.
This budget item was
also revised in'late 1984 and- late 1985.ER No. 7031 authorized $417,879 to upgrade the fuel transfer
system for Turkey*Point Unit 4.
This ER was revised in 1989 to c
increase the amount authorized by $712,217.
The ER includes a '
description that states that the modifications were designed by
Stearns Catalytic Corp.
(Stearns Catalytic) .
Effective December
17, 1984, FPL issued a purchabe order"to Stearns Catalytic)
authorizing $663, 975 to 'provide labor and materiåls for - the
transfer upgrade modification of 'I'urkey Point Units 3 and 4.,
A
nuclear safety change order was'issued to Stearns Catalytic, with
an effective date of December 19, 1985, to reopen, clarify, and
revise the purchase order.
ER No. 4133, approved and processed in 1988, authorized
042
$200,000 for modification to convert a- single cable hoist to a
dual cable hoist, and for the- installation of a new hoist load
indicator system for Turkey Point Unit 4.
With respect to the acquisition and installation of the fuel
transfer system, petitioner incurred capitalized costs. (tax
- 29 basis) of $430,432, $391,294, and $662 for equipment placed in
service in the 1988, 1989, and 1990 taxable years, respectively.
C.
Environmental Property
-
As a utility company, FPL is subject to environmental
regulations by Þederal, State, and local governmental agencles,
including the Environmental Protection Agency (EPA), U.S. Coast
Guard, and the Florida Depa-rtment of Environmental Protection.
Environmental regulations applicable to FPL relate to several
natural resources, including air, water, waste, animals, and
plants.
The purpose of envirdnmental regulati'ons, as applicable
to FPL, is to ensure that FPL generates, transmits, and
distributes elèctricity in1 a mannër that will protect human
health and the environment.
1.
Wastewater Neùtralization Treatment System
..
A wastewater neutralization treatment system treats the
wastewater.coming from th.e mineralizer regenerate.
The
mineralizer water i's ultrapure water that is placed into the
boiler to generate the steam, which ultimately drives the
generator to create electricity.
corrosivity.
Wastewater is ha.zardous for
FPL claims ITCs for the wastewater neutralization
treatment system in the 1988 and 1990 taxable years.
FPL received temporary'operating permits (TOPs) from·the
State of Florida, Department of Environmental Regulation,
for its
- 30 Martin County and Port Everglades plants."
The TOPs were .issued
pursuant to the Resource Conservation Recovery Act.
On May 7, 198.5, the Department of Environmental. Regulation
issued permit.Nos. HT 43-068555 and HT 06-068527, each of which
allowed FPL "to operate .two.hazardous waste surface impoundments
for the treatment of corrosive wastes (D002). by
neutralization"."
According to the TOPs, FPL was required to
"inspect and/or certify the surface impoundment, dikes, liners
and other associated structural and monitoring equipment as
required by *.* *
règulations.
[Florida statute] and in accordance" with EPA
Additionally, the TOPs state:
Within 30 ·days issuance of this permit, .the permittee
[FPL] shall submit to the department for approval a
schedule for closure of the existing. surface
The.parties each requested that we find as fact that FPL
received TOPs for each' of its nine fossil fuel power plants.
However, the documentary evidence reflects TOPs issued were for
FPL's Martin County and Port Everglades plants.
Each of the TOPs
in the record had an effective date of May 1985, and one permit
expired on July 15, 1986, and' the other had an expiration date of
May 15, 1987.
Ray Butts, FPL's manager for strategic and regulatory
planning, testified that the TOPs required FPL to install new
wastewater neutralization treatment systems at its fossil plants.
He further testified that FPL was required to install:
new tanks for the actual treatment of the water, the
ancillary piping that goes with that, as well as the
various pieces of equipment to support that activity
including monitoring equipment such as pH meters or
water level meters.
It also included the maintenance
of the existing basins to ensure that they had liners
that did not leak as well as embankments or retaining
walls that would prevent any over-topping of water.
- 31 impoundment(s) with a binding committment [sic] to
construct and have operational an elementary
neutralization unit or total enclosed treatment
facility. This binding committment [sic] shall include
the authorization to commit funds by F P & L for the
engineering, des'ign, and construction of said units.
The elementary neutralization unit or total enclosed
system shall be constructed and operational within
fifty (50) weeks from issuance of this permit.
* * *
If FPL failed to provide a binding commitment, it then had:
90 days to submit a groundwater monitoring plan:
(1)
(2) 30 days from
the approval of the groundwater monitoring.plan to install the
necessary monitoring wells;
(3) within 15 days after completion
of the installation of the monitoring wells, to submit a
certification of the well construction by the engineer of record
for approval; and (4) 15 days from approval of well construction
and certification, to begin sampling the.groundwater monitoring
well.
A 1986 BI No. 951,- approved on October 15,
1985, budgeted
$1.4 million to "Design and construct neutralization tanks for
fossil fuel power plants" that controlled the pH level of water
discharged from the plant.
A section of the BI labeled "purpose
and. necessity" states:
Existing and pending state and federal
environmental regulations require the control of the pH
range of water discharged from water treatment
facilities at power plants.
* * * State and federal
regulatory agencies no longer recognize the present
means of using existing open neutralization basins to
be in compliance with regulations.
Installation of neutralization tanks is the most
cost effective means of regulatory compliance.
* * *
- 32 Another alternative considered~was to obtain new
permits for the water treatment plants to operate as
hazardous waste treatment facilities.
To continue.operating without modification or
obtaining a new permit to operate as a hazardous wäste
treatment facility would not meet federal and state
statutory requïresents.
* * *
ER No. 9956, processed on December 5, 1988, authori 576ed
$93,603 for the purchase and installation of neutralization basin
lihers at the Port Everglades'plant.
A section of the ER labeled
"purpose and necessity" étates:
The existing liner is approaching the end of its
serviceable life. These basins are now regulated by
State and Federal law. Any breech [sic] of the liner
must be reported to State regulatory authorities.
Excess reportïng of leaks could bring about enforcement
action. The existing liners will not be removed; the
new liner will be placed on top of the existing liners.
ER No. 2286, processed on September 4, 1987, authorized the
expenditure of $70,290 to install a neutralization tank for FPL's
Riviera fossil plant.
ER No. 3068" authorized 'the purchase and
installation of a pH meter fo'r the neutralizatio'n tank at FPL's
Fort Myers fossil plant.
ER No. 8831, processed on September 6,
1985, authorized $19,440 to "Construct in pl·ace a concrete block
retention wall around' the Water.Treatment Plant neutralization
basin" at the Turkey Point fossil plant.
Because of the quality'of the copy in the record, neither
the date nor the. amount can be determined.
Mr. Butts testifi.ed that FPL purchased all the ,property
(continued...)
- 33 With respect to the installation of wastewater
neutralization treatment system, petitioner incurred capitalized
costs (tax basis) of $241,469 and $233,742 for equipment placed
in service in the 1988 and 1989 taxable. years, respectively.
2.
PCB'Transformers
Polychlorinated biphenyls (PCBs) are a hydrocarbon that has
been chlorinated.
PCBs have been idehtified by environmental
regulators as a potentia,1 risk to human health and the
environment.
The Toxic Substance Control Act of 1976, Pub. L.
94-469, 90 Stat. 2003, current version at 15 U.S.C. sec. 2605
(2000), prohibits the manufacture, process1ng, or distribution in
commerce or use of PCBs in any manner other than in a totally
enclosed manner.
.FPL previously used PCBs in its fossil fuel
power plant transformers.. FPL claims ITCs for the replacement of
PCB transformers in the 1988, 1989, and 1990 taxable years.
In 1982, the EPA promulgated a rule, 40 C.F.R. sec. 761
(1982)
(the PCB rule), that regulates the use of PCBs.
rule, inter alia:
(1) "P'rohibits the use of PCB Transformers and
PCB-filled electromagnets
greater)
The PCB
(with a PCB concentration of 500 ppm or
* * * after October 1, 1985, and requires a weekly
inspection of this equipment for leaks of dielectric fluid until
that date";
(2) "Authorizes the use of all other PCB Transformers
35(...COntinued)
according to the specific conditions of the TOPs.
- 34.for the.remainder of their useful lives, and requires a quarterly
inspection of this equipment for leaks of dielectric fluid"; and·
(3) "Prohibits the use of all other large PCB Capacitors after
October 1, 1988".
According to the PCB rule:
If a PCB Transformer is found to have a leak which
results in.any quantity of PCBs running off or about to
run off the external surface of the transformer, then
the transformer must be repaired or replaced to
eliminate the source of the leak. In all cases any
leaking material must be cleaned up and properly
disposed of * * * in no case later than 48 hours of its
discovery.
* * *
In response to the PCB rule, FPL commenced a program to remove
PCBs from its electrical equipment, including all power
transformers at its power plants."
A 1986 BI No. 895, approved in October 1985, budgeted $16.4
million to "Replace all PCB filled distribution capacitors" over
a 6-year period "to conform with new EPA regulations, and
commenced in the first quarter of 1983 and are to be completed in
the third quarter, 1988."
A section of the BI labeled "purpose
and necessity" states that "Recent EPA regulations released
August 25, 1982 prohibit the use of all large PCB-filled
capacitors after October 1, 1988."
A 1986 BI No. 904, approved in October 1985, budgeted $13
million to "Replace all PCB filled distribution transformers"
over a 3-year period to commence in the first quarter of 1984 and
M Mr. Butts testified that a PCB leak was a "reportable
event" to the EPA.
- 35 to be completed ïn the fourth quarter of 1986.
A section of the
BI labeled "purpose and necessity" states that "Recent concerns
with PCB fluids and by-products of PCB's resulting from fire have
made it advantageous to replace these transformers before end of
life."
The record contains copies of ER Nos. 1997, 3042, 3043,
3331, 3337, 3498, 3567, 3568, 4210, 4211, 4213, 3971, and 4455,
which authorized the expenditure of funds to "replace the
existing generator grounding transformer (containing PCB
contaminants.) with a PCB free transformer"" at FPL's power
plants."
Similarly, ER No. 4440, processed on December 8, 1988,
authorized $341,396 to "replace Pressurizer He.ater P.C.B. oil
filled transformers with Non-P.C.B. dry type" at St. Lucie Unit
2.
A section of the ER labeled "purpose and necessity" states
that."Having transformers on site filled with this oil containing
P.C.B.'s in this Regulatory, Environmental, and litigious climate
is a liability" for FPL."
With respect to the replacement of PCB, transformers,
petitioner incurred capitalized costs (tax basis) of $886,616,
Although not all of these ER's contain the exact.quoted
language, they each contain similar language.
Mr. Butts testified that these ERs were the result of the
PCB rule.
39 Mr. Butts testified that this ER was the result of the
PCB rule.
- 36 $748,411, and $36,053 for equipment placed in service in the
1988, 1989, and 1990 taxable years, respectively.
D.
Sïmulator and Trainino Buildinos
At some point, the NRC and FPL's management held various
management and enforcement conferences concerning Turkey Point.4°
In February 1984, FPL presented a performance enhancement program
for Turkèy Point to the NRC."
Part of the performance
enhancement prbgram was to establish on-site training facilities
and to obtain plant reference' simulators.
FPL claims ITCs for
the simulator.-and training buildings in the 1988, 1989, and 1.990
taxable years.
On July 13, 1984, the NRC sent a letter to FPL,· which-states
in part:
Based on recent NRC inspection activities and the
enforcement history of the Turkey Point Facility, we
conclude that * * * [FPL] has not given sufficient
management attention to ensuring adherence to
regulatory requirements.
* * *
The NRC included a confirmatory order with the letter, which
states in part:
4° Thomas J. DePlonty, FPL's project. manager, testified that
during this period Turkey Point was placed on a "watch- list" and
was considered one of the 10 worst nuclear plants operating at
that tike.
" The performance enhancement program stated: "This
document is specific to Turkey Point Plant however, where
appropriate, the results and lessons learned will be applied to
the St. Lucie Plant."
- 37 -
Because of NRC concerns regarding the extent of
problems at the Turkey Point Plant, FPL presented
information on January 13, 1984 describing management
actions taken to improve operational performance at the
site. A more comprehensive FPL program was developed
and presented to the NRC on February 17, 1984.
* * *
Accordingly, on July 11,
1984, the NRC ordered FPL to, inter
alia, "implement the Turkey Point Performance Enhancement
Program".
.
A 1983 BI No. 543, approved in late 1982, budgeted $100,000
to "Purchase and install a plant control room specific simulator
at Turkey Point and St. Lucie Plants."
divided in two phases.
The budget item was
Phase I provided for the development of
simulator technical specifications, and phase II provided for
simulator procurement and installation.42
FPL'revised BI 543 in
1984, authorizing $21,980,000 (which was apparently "phase II")
to "Provide control room specific simulators for the Turkey Point
and St. Lucie nuclear power plants."
This revision referenced a
third phase to the project, which "will include construction of
the buildings and simulator installation.
estimated at $2,800,000."
These costs are
This BI 543 was revised in March 1984
to increase the amount budgeted for all three phases to $32
million.
This revis1on envisioned training centers as p.art of
phase III, which had an estimated cost of $10,020,000.
42 BI No. 543 only dealt with phase I.
In late
- -38 1984/early 1985, FPL= revised this BI to increase the overall
budgeted amount to $35. million.
ER No. 7172, referencing BI No. 543, was processed in 1984
and approved $10,675,000 to design, fabricate, and install a
control room specific simulator for the St. Lucie power plant.
This ER was revised in late 1988/early 1989 to increase the
amount approved to $13,150,000 and revised again in 1991 to
increase the amount approved to $14,520,000.
ER No. 8223,
referencing BI No. 543, was processed in 1985, and authorized
$375,000 to provide detailed design and engineering necessary to
construct the training facility at the St. Lucie nuclear power
plant.
FPL revised this ER in 1986 to increase the amount
approved to $5.5 million, and again in 1988 to increase the
amount approved to $7,050,000.
ER No. 7173, referencing BI No.
543 and approved in 1984, authorized $10,780,000 to design,
fabricate, and install a cont ol room specific simulator for
Turkey Point.
This ER was revised in late 1988/early 1989 to
increase the amount approved to $11,550,000.
A 1987 BI No. 103, approved in 1986, budgeted $2,437,000 to
"provide the capital additions necessary to equip the
Training/Simulator [at the St. Lucie nuclear power plant] with
state of the art tooling, mockups, and equipment."
ER No.. 1817,
which references BI No. 103 and was approved in early 1987,
authorized $330,000 to purchase mockup equipment and plant
- 39 specific training aids for, the St. Lucie. nuclear power plant.
ER
No. 1818, which also references BI No.. 103 and was approved in
early 1987, authorized $628,000 to purchase equipment for the
simulator at the St. Lucie,plant.
ER No. 1819, which references
BI No. 103 and was approved in early 1987, approved $521,000 to
purchase a security system and other equipment for the St. Lucie
plant simulator project.
ER No. 1820^, which references BI No.
103 and was approved in early.1987, authorized $917,000 for the
purchase o.f equipment and training aids for the St. Lucie nuclear
power plant simulator project.
This ER was reprocessed in late
1990, and was reestimated to decrease the amount approved to
$614,989.
A 1989 BI No. 482, approved in late 1988, budgeted $786,000
for the necessary additional equipment for the training/simulator
building.
ER No. 5448; referencing BI No. 482 and approved in
1989, authorized $300,000 to purchase "NIS Pack mockup that
duplicates plant equipment to conduct training" for Turkey Point.
This ER was revised in 1990 to increase the amount authorized to
$382,262.
A 1987 BI No. 483, approved in late 1986, budgeted
,
$1,807,.000 to "provide capital funds necessary to equip the
Training/Simulator Building [at Turkey Point] with state of the
art mockups equipment and tooling."
ER No. 2374, referencing BI
No. 483 and approved in 1987, authorized $95,000 to purchase
Turkey Point specific training aids and mockups.
ER No. 2442,
referencing BI No. 483 and approved in 1987,. authorized $35,000
to "Purchase a test/training cabinet that·will duplicate the
equipment associated with the [Turkey Póint] plant's process and
area radiation monitoring systems."
ER No. 2486, referencing BI
No. 483 and approved in 1987, authorized.$682,000 to purchase
shop equipment and training aids for Turkey Point.
A 1988 BI No.. 558, approved in late 1987, budgeted
$1,467,000 to provide "THE CAPITAL -FUNDS NECESSARY TO EQUIP THE
TRAINING/SIMULATOR BUILDING."43 * ER No.
3381,
referencing BI No.
558 and approved in 1988, authorized $275,000 for the purchase of
a "See-Through Power Plant Operational Model" for Turkey Point.
ER No. 5447, referencing BI No. 577 and approved in. early
1989, authorized $200,000 for a "Flux Map System Training Model"
for Turkey Point.
This ER was revised in June 1989 to increase
the amount authorized to $270,000.
ER No. 8224, referencing BI No. 543 and approved in early
1985, authorized $325,000 to provide detailed design and
engineering necessary to construct the training facility at
Turkey Point.
This ER was revised in 1986 to increase the amount
43 This BI did not specify for which site, Turkey Point or
St..Lucie, these funds were budgeted.
- 41 authorized to $4.7 million for the construction of the simulator
training facility at Turkey Point.44
With respect to the construction of the simulator training
buildings, petitioner incurred capitalized costs
(tax basis) of
$1,486,050, $1,458,213, and $345,914 for equipment placed in
service in the 1988, 1989, and 1990 taxable years, respectively.
E.
Load Management System
A load management system (LMS) is a group of components that
control appliances in customers' homes to reduce peak demand for
electricity.
Peak demand is the time during the day with the
highest demand for. electricity.
In reducing the demand during
peak times, load management reduces FPL's need to construct
additional facilities to provide electricity.
Load management
reduces peak demand by remotely turning on and off certain
appliances in customers' homes.
Customers voluntarily
participate in the LMS, and FPL gives its customers rebates in
exchange for their participation.
FPL claims.·ITCs for the LMS in
the 1988, 1989, and 1990 taxable years.
The three major components of the LMS are the central
computer, the substation control equipment, and the transponders
located at customers' homes.
Telephone and power lines connect
44 Mr.. DePlonty testified that physical construction of the
St. Lucie plant training facility did not start until after April
1986. However, Mr. DePlonty testified that development of the
simulator, a training aid, began before the construction of the
building that housed the simulator.
- 42 these components. to each other.
The central computer is a
mainframe type of computer, issuing commands through telephone
lines to substation equipment, and is fully redundant, meaning
that FPL purchased two central computers, one of which was used
and one of which served as a backup.
When FPL purchased the
central computer at the beginning of the LMS implementation, the
system could handle 600,000 to 700,000 customer locations
(transponders) and the corresponding substation equipment.
When
FPL purchased the central computer it also purchased related
software,45 and its software license was perpetual.
The substation control equipment received commands from the
cen·tral computer, translated those commands, and sent the
commands through power lines to transponders in customers' homes.
Substation control equipment includes the control receiving unit,
the outbound modulation unit, the modulation transformer unit,
the inbound processing unit, and the associated equipment.
Transponders are installed at customers' homes, the transponders
accept commands that are sent from the substation equipment, and
they act on the commands by turning appliances on or off at
customers' homes.
Although the components of the LMS function in
an integrated manner, each transponder, once installed, was
45 According to a document entitled "SOFTWARE PRODUCTS
LICENSE AGREEMENT", the software was licensed from A.B. Chance
Load Management Systems (A.B. Chance), effective on Oct. 4, 1985.
- 43 operated and placed in service independent of any other
transponder.
FPL began placing transponders in service during
the beginning of 1985 and continued to do so through the date of
trial.
On September 17, 1980, the FPSC ,issued an order proposing
rules.
According to the general goals listed in the order, "The
Florida Energy Efficiency and Conservation Act requires
increasing the efficiency of the electric * * * systems of
Florida".
The order also called for a public hearing on the
proposed rules.
During 1980-81,
FPL prepared1the "Energy Management Plan for
the '80s" (the plan) .and submitted it to the FPSC."
The
articulated objective of the plan was to "Reduce use of home
appliances at times of FPL system peak, thereby reducing peak
demand."
The plan called for a load management system.
The plan
document states that "FPL has recently obtained * * * [FPSC]
approval to implement a two year test on 1,000 residential
customers beginning in the fall of 1980".
In January 1983, FPL published a bidirectional communication
system requirements study that outlined "FPL's future load
" Armando Garcia, an engineer at FPL, testified that FPL
submitted·the energy management plan to the FPSC in response to
the FPSC order and that the FPSC approved the plan. Mr. Garcia
explained that the FPSC had to approve the energy management plan
"Because we do recover the costs and any costs that, money we
collect on our customers has to be approved by the" FPSC.
management and energy conservation programs designed to meet the
FPSC mandated goals.""
The study recommended, inter alia, that
FPL procure and install a bidirectional communication system to
implement load control.
In addition to the study, FPL published
a technical report- that detailed the project expenditures by
.
year.
In November 1983, FPL prepared a technical specification
that detailed how the LMS was"supposed to work, its properties,
.
and its requirements."
FPL ubed the technical specification to
secure bids from vendors to build the LMS.
On October 4, 1985, FPL entered into an agreement (the LMS
contract) with A.B. Chance Load Management Systems (A.B.
Chance)."
An FPL purchase order incorporated into the LMS
contract acted as' A.B. Chance's authority to "furnish the Phase I
For example, the FPSC's Sept. 17, 1980, o.rder proposing
rules included goals to "reduce the average annual growth of
kilowatt demand * * *.
The specific goals for the 1980-85 period
are to reduce growth rates so that the total KW demand in 1985
does not exceed that of 1984 by more than 2.212%".
The technical specifications included a ",tentative
delivery schedule" for the years 1985 through and including 1992.
Mr. Garcia testified:
'
we knew that we were going to go long term with the
system and that, because of the nature of it, you had
to go with one vendor. This is what the vendor was
told and he'was given the" scope of the project and the
values that we were talking about in order to submit an
accurate bid.
49 gg.·GarCia testified that FPL's technical specifications
were incorporated into the LMS contract.
- 45 Load Management System" to FPL for a total'price of $11,477,432.
One of the terms included in the LMS contract was a price
guarantee:
Prices for all parts of the Work shall remain firm
throughout Phase I except as otherwise indicated in
Base Bid Schedule Appendix I.
It- is FPL's intent to competitively bid its
requirements for Phases II and III.
However, Contractor
agrees that the maximum. price it* will charge FPL during
Phases II and III will be the lowest price the Contractor
then currently charges its other customers of Contractor's
load management system equipment of the same model, type,
system size, quantity purchase and similar contractual
terms.
* * * °1
Under the LMS contract, FPL purchased an entire system, including
hardware, software, etc."
The LMS contract contemplated the
purchase of, inter alia, 10,000 plug-in transponders, 2,000
surface mount transponders, central computers, software licenses,
50 Concerning the LMS contract, Mr. Garcia testified:
There.was no commitment to the work on FPL's part
at that time to purchase any equipment beyond what is
described here as Phase I.
* * * [However, it] was made clear to the vendor
throughout the.document that·our intention was to do
the whole LMS project.
*.* *
" The LMS contract refers to "phase I" but apparently that
term is not defined within the body of the voluminous.contract.
Given the description of the items to be provided by A.B. Chance
and those which are described in FPL's budget items, see infra,
we assume that "phase I",for the LMS contract is the same as
"phase I" for budget item purposes.
etc."
The LMS contract contained a termination clause for
convenience that provides:
upon 15 days Written Notice to Contractor, FPL may at
its sole discretion and without prejudice to any other
right or remedy, terminate ·this Contract.
* * *
Upon such termination, FPL shall pay such amount as
Contractor and FPL may agree is to be paid by reason of
such termination, but in event of failure to.agree upon
the amount to be paid by reason of such termination,
FPL shall pay the Contractor and.Contractor agrees to
accept in full payment of all FPL's obligations to the
Contractor under this Contract, an amount consisting
of:
.
1.
All amounts which are due to the Contractor
as a result of Contractor satisfactorily
reaching payment milestones in accordance
with * * * [the LMS contract] which FPL has
not yet paid Contractor, plus
2.
An amount equal to 10% of the progress
payment for any Contract milestone not
started and for which no preparatory or
startup costs have been incurred by Contract
at the time of termination, plus
3.
If a portion of a Contract milestone is
terminated, an amount equal to the costs
which Contractor is unable to mitigate * * *
and 10% of the progress payment determined by
multiplying the percentage of such Work which
Although the terms of the LMS contract were for "phase
I," Mr. Garcia testified that "once we made the commitment [to
the LMS), it was a huge investment and we would continue with
that vendor unless there was a catastrophic event." He.further
testified:
the contract was always envisioned as a single contract
and all the purchases have been made under the same
contract.
Phase I, Phase II and {Phase] III were
designations given in order to better manage the
contract.
You would not get a contract for 10 or 20
years originally.
It just doesn't make sense.
- 47 has not been completed times the progress
payment of such uncompleted milestones being
terminated.
A 1986 BI No. 897 budgeted $-15 million to purchase:
12,000
load control transponders; 1,050 metering transponders; and 500
surface mount load survey t.ransponders, communication equ.ipment
for substations, test equipment, and computer hardware and
software.
The budget item states th,at work was to begin in 1985
and was to be completed in 1988..
It further states that a load
management communications system is necessary to meet the demand
and energy goals of the FPSC and FPL's·energy management plan.
This budget item permitted FPL to implement phase, I of the LMS:
Initially, the Load Management System will be sized for
10,000 load control points and 1,000 TOU [Time-of-Use]
meter points, and 500 load survey points. After Phase
I is thoroughly tested and ·results are satisfactory,
the system will be expanded to support 388,000 load
control points and 220,000 TOU Rate customers by 1994.
BI No. 897 was revised in 1989 to increase the amount budgeted
for phase I to $20 million.
The budget item states:
Phase II of the program is covered under Budget item
868 which calls for.the System to be expanded to
support 250,000 load control points by 1993.
Total Prooram Capital ($000)
Phase I
$ 20,000
Phase II 90,000
All future
Phases
95,000
Total
$205,000
A 1989 BI No. 868 budgeted $90 million for phase II of the
LMS.
The budget item states that work was to begin in 1989 and
was to be completed in 1993.
It also explains that phase II will
inc.rease the LMS from 10,000 to 250,000 load control points and
from 15 to 183 substations.
According to"a summary of exhibits submitted at trial
relating to the cost of the LMS equipment purchased from A.B.
Ch.ance in l'988; 1989, and 1990, FPL·instal-led transponders with a
total cosi'of $18,061,148, substation equipment with a total cost
of $6,044,979., and* master station equipment with a total cost of
$7,478,426 for a total cost of $31,584,553."
With respect to the' installation of the LMS, petitioner
incurred capitalized costs (tax basis) of $362,837, .315,156,624,
and $39,351,031 for equipmënt placed in' service in the 1988,
1989, and 1990 taxable years, respect-ively.
F.
St. Lucie Backfit Construction
St. Lucie Unit 1 was operational in 1976, and St. Lucie Unit
2 was operational in 1983.
items:
(1)
There are two categories of backfit
Items that are the part of the plan completed after
commercial operation, and (2) items developed after commercial
operation, resulting from regulatory requirements or performance
problems.
.
Mr. Garcia testified that all the equipment purchased
from A.B. Chance was purchased under the same contract.
He also
testified that as of the day of trial, FPL was still purchasing
equipment from A.B. Chance.
- 49 -
1.
Underwater Intrusion System
An.underwater intrusion system protects a power plant using
a barrier system.54
Mr. Paduano testified that "The system
consists of a bridge across the intake canal with a suspension of
a barrier, and underwater and surface detection devices."·
FPL
claims an ITC regarding the underwater intrusion detection system
for the 1990 taxable year.
On October 25, 1984, the NRC sent a letter to FPL concerning
St. Lucie's physical security plan.
The letter stated in
pertinent part:
Other changes which were in response to NRR's
letter of June 5, 1984, relative to the Underwater
Intrusion Detection System (UIDS), are in need of
additional clarification. However, this additional
information request does not delay the acceptance of
your proposed UIDS.
You should commence implementation
of that system upon receipt of this letter.I"1
In response to an FPL letter and a meeting regarding the
intake canal barrier and intrusion detection system, on November
14, 1985, the. NRC sent a letter to FPL concerning St. Lucie Units
1 and 2 physical security plan.
The letter stated in part:
We have determined that the proposal presented by
Florida Power and Light Company * * * is technically
insufficient in that the underwater portion does not
satisfy the requirements of 10 CFR 73.55(c) (4) * * *
54 Harry Paduano, a former manager with FPL, testified that
the underwater intrusion system was required by the NRC.
Mr. Paduano testified that this letter in effect required
FPL to modify the underwater intrusion system.
.
*
- 50 -
*
*
*
*
*
*
You should take whatever steps are necessary to have
this matter resolved and the system installed by the
date committed to in your security plan.
On December 21, 1989, FPL sent a letter to the NRC ·
concerning St. Lucie's intrusion detection system.
The letter
státed in part:
The NRC found in its December 7, 1989 letter, that the
system currently installed at St. Lucie Plant does not
meet regulatory requirements or guidance for detection
capability.
* * *
*
*
*
*
*
*
*
FPL's plan [sic] to meet with the NRC in February 1990
to update the Staff on its approach to resolution of
this issue.
On May 1, 1990, the NRC sent' a letter to FPL concerning its
conceptual design of the intrusion detection system's intake
canal.
In that letter, the NRC "determined that your conceptual
design is consistent with" regulatory requirements.
However, the
letter cautioned that approval of the conceptual de ign does not
constitute final approval.
ER No. 6475, processed on October 24, 1983, authorized
$2,188,000 to "perform work after the commercial operation of St.
Lucie Unit No. 2 in. order to meet regulatory requirements, comply
with technical specifications, achieve full operating capability
and increase plant availability'."
The ER specified that "Backfit
Item No. 166, Underwater Intrusion Detection" was to be completed
and in service by March 31,. 1984.
In 1986, the amount authorized
- 51 was increased to $5.9 million.
The ER included a report of
construction action prepared on May 9, 1984, which is associated
with ER No. 64,75.
;The report of construction action stated that
construction work star.ted on May 1, 1984."
Another report of
construction action prepared on February 27, 1987, stated that
the underwater intrusion detection was completed on February 25,
1987.
ER No. 4866, approved in late 1988/earl.y 1989, authorized
$360,000 for the St. Lucie underwater intrusion detection system.
The ER stated in pertinent part:
[FPL] is' committed to the * * * [NRC] for the
development of an underwater intrusion detection system
for the intake canal. This is a security measure.
* * *
This ER is necessary as.the present,1y installed system
does not satisfy the requirements of the [NRC). 042 This
has caused an extensive effort in research and
development of this specialty system. This research
has identified the need to:
Install an additionál
sonar head and a.surface detection system. These
additional requirements have made it necessary to fund
and perform these modifications.4"1
With respect to the modification and construction of the
underwater intrusion system, petitioner incurred capitalized
costs (tax basis) of $338,665 for equipment placed in service in
the 1990 taxable year.
56 Mr. Paduano testified that the construction work on the
.underwater intrusion system began before 1986.
Mr. Paduano testified that this ER "added additional
detection capabilities."
- 52 2.
Condensate Polisher Tie Line
A condensate polisher purifies.the feedwater that enters the
steam generator to protect the generator from corrosion.
The
design for each of the reactors at the St. Lucie= plant included a
condensate polisher.
FPL claims ITCs for the condensate polisher
tie line in the 1989 and 1990 taxable years.
Apparently, in 1982 there was a plan change or modification
for. St. Lucie Unit 1.
An engineering study, datedrNovember 13,
1985,'recommended the use of cross-tie piping to protect the
generator from corrosion.
The recommended system,would purify
the feedwater in the second unit by using the polishers at the
first unit.
The system uses the cross-tie lines :to purify the
feedwater by passing the water discharged from the condensate
pumps at St. Lucie Unit 2 to the condensate polishers at·St.
Lucie Unit 1.
After passing through the:condensate polisher, the
water returns to the condensate system at St. Lucie Unit 2 via
the cross-tie lines, and then the water feeds through the steam
generators.58
ER No. 6195,' processed.on June 22, 1983, authorized the
expenditure of $15,243,000 as part of the "backfit program"' on
St. Lucie Unit;2.
The ER states:
58 In a letter dated Jan. 9, 1986, Mr. Paduano recommended
the installation of the cross-tie option for St. Lucie Unit 2.
The record contains numerous letters describing the design
process for going forward with the condensate polisher cross-tie
line for St. Lucie Unit 2.
.
- 53·It is necessary to perform work after commercial
operation of St. Lucie Unit No. 2 in order to meet
regulatory requirements, comply with technical
specifications, achieve full operating capability and
increase plant availability.
.
According to the ER, work was to, be completed and in service by
May 31, 1985."
February 8,
A revision to ER No. 6195 was processed on
1984, to.increase the amount,authorized to
$18,288,000.
FPL revised the ER again in 1986 and 1987 to
decrease the amount authorized:to $3,830,000.
The decrease was
explained as follows:
The previous scope of work included the installation. of
a complete full flow condensate polisher at Unit 2. An
examination of the steam generators.during,the recent
refueling outage resulted in an engineering
determination that the existing.>condensate polisher at
Unit 1 could serve the needs of both units. The scope
of work is being reduced to a condensate tie line
between the two units.
After the decrease, the ER was again revised to increase the
amount authorized to $4,828,000 to account for extensive
modifications.
With respect to the installation of the condensate polisher
tie line at the St. Lucie nuclear power plant, petitioner
incurred capitalized costs
(tax basis) of $3,826,317 and $388,906
for equipment placed in service in the 1989 and 1990 taxable
years, respectively.
Mr. Paduano testifïed that the construction related to
the condensate polisher at- St. Lucie Unit 2 commenced before
1986.
- 54 3.
Instrument Air Upgrade
At a power plant, an instrument air system operates the
valves located throughout the plant.
The instrument air system
provides the force that changes the positions of the valves in
the plants.
FPL claims ITCs for the instrument air upgrade for
the 1988, 1989, and 1990 taxable years.
Apparently, the instrument air system at St. Lucie Unit 1
experienced problems, and FPL initiated a study to determine, the
cause of the problems.6°
The study culminated in a
recommendation. on June 22, 1983, to remove existing equipment and
replace it with new equipment.
A letter dated October 22,
1984,
states that FPL held a meeting in May 1984 to discuss the
problems and potential solutions for the instrument,air systems
for both units at St. Lucie.
In that letter, FPL expressed its
intent to solicit bids to acquire four new compressors and two
new dryers.
According to a letter dated December 28, 1984, FPL
anticipated that it would complete the bid review and provide an
engineering schedule by January 18, 1985.
ER No. 9009, processed on October 23, 1985, authorized
$75,000 to upgrade the instrument air system at St. Lucie Unit 1.
The ER stated:
The present instrumënt air systems are not capable
of suppling [sic) the total plant needs for instrument
6° Mr. Paduano testified that the instrument air upgrade was
a type 1 backfit item.
-.55 air. Additional air stations are needed to be
installed in order to provide the equipment with the
necessary instrument air.. Two new.addit.ional air
compressors will be installed, and the air dryer will
be replaced.
The present air compressors. are operating
continuously indicating insufficient air capacity. The
system suffers from a lack of adequate pressure for the
main steam isolation valves * * *. The existing dryer
is not properly drying air at the.present system flow
rates.
ER No. 9009 estimated that the upgrade would be completed by
November 30, 1986.
In late 1985, t e amount authorized was
increased to $692,000.
In late 1988/early 1989, the ER was
increased to $1,765,000 "due.to schedule duration increase and a
growth in scope."
The duration increase was due to "rescheduling
of Engineering and a Plant Operations requirement that some work
be accomplished during a plant outage."
According to a report of
construction action, the constructi'on began on Óctober 26, 1985.
According to another report of construction action, construction.
stopped to await a consÊruction package needed to complete the
work, and the work was to resume during the summer of 1987.
ER No. 9303, processed on February 26, 1986, authorized
$692,000 to upgrade the instrument air system on St. Lucie Unit
2.
ER No. 9303 essentially listed the same need for the upgrade
as described in ER No. 9009.
In late 1988/early 1989, FPL
increased the amount authorized to $1,464,000 because of growth
in the scope of the project.
According to a report of
construction action, construction started.on the instrument air
- 56 system upgrade on May 12, 1986.
According to another report, of
construction action, the instrument air system upgrade was put in
service on April 27, 1989.
With respect to the installation of the instrument air
upgrade, petitioner incurred capitalized costs (taxi basis). of
$1, 541, 741, $1, 717, 941, and $316, 912 for equipment placed in
service in the 1988, 1 89, and 1990 taxable years, respectively.
G.
St. John's River Power Park (SJRPP)
The Jacksonville Electric Authority (JEA) and FPL entered
into an agreement, dat~ed April 2, 1982, to jointly own and
operate the St. John'_s River Power Park (SJRPP) .
FPL owns 'a 20-
percent interest, and the JEA owns an 80-percent interest of the
SJRPP as tenants in 'common.
FPL claims ITCs for the SJRPP
equipment in the 1988, 1989, and 1990 taxable years.
The SJRPP burns coal to generate steam to turn the turbines
that generate electricity.
include:
The major components of the SJRPP
Hyperbolic cooling towers, bore houses, turbine houses,
steam generators, switcher, precipitators, scrubbers, chimney,
and coal facilities.
SJRPP Units 1 and 2 each had their own
boiler, turbine, and control panel.
The SJRPP includes a water-
borne coal terminal, which is connected to the main part of the
- 57 -
facility by conveyor systems located on a piece of land that is
approximately 3.5 miles long by'100 feet wide.
.
Buildings at* the SJRPP serve' a support function to the
elec.trïcal power generation components.
The buildings are not
significant compared to the other parts of the SJRPP facilities
in terms of size and cost
In operation, Units 1 and 2 both'use coal from..the SJRPP's
coal yard and coal-unloading facilities (train and ship).
SJRPP's conveyor s*ystem serves both Units 1 and 2.
the SJRPP work on both Units 1 and 2.
The
Employees of
Both these units use the
SJRPP's inventory, storage, and tool. rooms.
The SJRPP includes
other facilities common to both Units 1 and 2, such as the switch
yard, waste water treatment, limestone handling, shipment
handling, and rotary coal dumper.
Unit 1 is capable of
supporting the critical systems of Unit 2 and vice versa.
These
critical systems are "cross connected" to support one another,
and include the ins.trument air/service units, condensate systems,
cooling water systems, and auxiliary steam systems.
The SJRPP Unit 1 and the common facilities were placed in
service in 1987, and Unit 2 was placed in service in 1988.
After
Unit 1,· the common faci,lities, and Unit 2 were placed in service,
certain consËruÊtion completfon work remained, including "wrap
up" work and "enhancements and deficiencies" work.
"Wrap up"
work included predominantl.y contract closeout work related to
- 58 construction contracts with unrelated parties.
"Wrap up" work
was within the original design of the SJRPP.·
The SJRPP agreement defi:ned the physical facilities to .
include:
(1) Two coal-fired electric generating units, . along .
with all of their necessary equipment;
(2) a coal handling
system, including coal storage facilities;61 and (3) a
switchyard.6?
The same building' contains the generators for
Units 1 and 2. ' Both units use them same coal yard. - The control
room houses control .panels for both Units 1 and 2.
61 The. SJRPP agreement also stated: ""Currently being
studied is the conceptual design for and feasibility of a
facility to provide for the'waterborne delivery and transfer of
fuel.
62 John P. Reid, business manager for the SJRPP, testified
that it was always intended that the SJRPP would include two coal
fire units.
- 59 The SJRPP agreement states in pertinent part:
5.9 Commitments on Behalf of Co-Owner.
5.9.1 Authority of Agents to Commit.
JEA shall
have the authority to act as agent on behalf of
FPL (i) to the extent actions are authorized
According to a final cost report, as of September 30, 1993,
the final cost totaled $860,703,589.96 for Unit 1,
$510,248,946.56 for Unit 2, and $60,227,555.61 for the coal
terminal.
Numerous third parties contracted to provide materials,
services, and other aspects of the construction of the SJRPP.
Excavation for the construction of the SJRPP commenced in
December 1982, and the first concrete was poured in 1983.
The
parties submitted into evidence a summary of third-party
Mr. Reid explained his understanding of this provision
as:
.
[the] JEA is the leading manager of the construction
operation and maintenance and long term ownership of
the facility and because of their contracting
requirements was the lead manager of the facility of
the construction and operation of the facility. This
.section under the JOA states that [the] JEA,.from * * *
[FPL's] perspective, [the] JEA will have the authority
to act as agent on behalf of * * * [FPL) in all those
* * * issues.
Additionally, Mr. Reid testified that the JEA and FPL managed the
SJRPP project by committee, with two representatives from each
owner serving as representatives.
Mr. Reid testified that the cost of Unit 1 far exceeded
the cost of Unit 2 because the common facilities had to be
erected in time to support the first unit built.
- 60 construction contracts related to the SJRPP.
The- summary lists
the major contracts for the SJRPP Units 1 and 2, the base award
values of the contracts, the effective dates, and the subject
matter.
The part.ies stipulated that, except for one contract,
each contract identified in'the summary contained an introductory
paragraph, of which the following is representative:
This Agreement, Executed. this ___ day of ___ in the
A.D. ___ by and between JACKSONVILLE ELECTRIC
AUTHORITY, Jacksonville, Florida, hereinafter OWNER,
and ___, hereinafter called CONTRACTOR.
The parties stipulated that each contract identified in the
summary contained a clause defining "Owner", of which the
following is representative:
Owner "means the [Jacksonville Electric] Authority
and any person, firm, partnership, joint venture,
company, corporation or other entity obtaining an
ownership interest or ownership participation in the
Project.
The Authority shall represent all entities
comprising Owner with regard to all relations between
the Owner and.Contractor under this Contract."
The parties stipulated that each contract identified in the
summary contained a termination clause, of which the following is
representative:
" The excepted contract contained the following language:
This Agreement, Executed the 11* day of September in
the A.D. 1985 by and between Jacksonville Electric
Authority on its behalf and agent for Florida Power and
Light, hereinafter Owner and Johnson Control, Inc.,
hereinafter Contractor.
- 61 44.0 Termination for Convenience
.1 At any time after the acceptance of this
Contract, Owner shall have the absolute
right to terminate the entire Contract.
In the event of termination, Contractor
shall be paid for all disbursements.and
expenses which Contractor has incurred
or becomes obligated for prior t.o the
date of Contractor's receipt of the
notice of termination plus costs
incurred in compliance with Section 44.2
below, less the reasonable resale value
of Equipment which shall have been
ordered, obtained or fabricated in
connection with this Contract plus a sum
as profit bearing the same ratio to the
profit that Contractor would have
received upon completing this Contract
as the value of the Work completed as of
the date of receipt of the notice of
termination bears to the Contract Price.
44..2 Upon receipt of such notice of termination,
Contractor shall:
44.2.1 Stop the performance of the Work
hereunder except as may be
. .
necessary to carry out such
termination.
44.2.2 Take any other action toward
termination of the Work which
Owner may reasonablely [sic]
direct, including all reasonable
efforts to provide for a prompt
and efficient transition as
directed by Owner.
44.3 All payments made by Owner against the
Contract Price prior to termination shall be
credited to the amount, if any, due
Contractor as provided in Section 44.1.
44.4 Except for amounts due pursuant to
Section 44.1, upon termination as
provided in Section 44.1 Owner will have
no liability to Contractor for any cause
- 62 whatsoever arising out of or in
connection with such termination.
44.5 If the sum of all previous payments and
credits made by Owner exceeds the sum
payable under Section 44.1, such excess
shall be refunded by Contractor to Owner
immediately upon determination of such
excess by the Parties.I")
According to an. actual cost report, as of December 31, 1985,
the total amount expended on the SJRPP was $703,407,644."
According to that ·report, as of December 31, 1985, FPL's
obligation was $140,681,529.
Apparently a retention account was
created," which totaled $31,.259,567 as of December 31, 1985.
" Mr. Reid testified that, as of Dec. 31, 1985, it was 100
percent likely that FPL and the JEA would continue with the
existing contractors, and that there was a zero percent
likelihood that the JEA or FPL would terminate these contracts.
Furthermore, Mr. Reid testified that neither the JEA nor FPL
exercised the termination clause.
Mr. Reid testified that, as of Dec. 31, 1985, the SJRPP
was between 60- and 65-percent complete. According to Mr. Reid's
testimony and the stipulated summary of the SJRPP contracts, as
of Dec. 31, 1985, FPL and the JEA were "committed" to spend
$810,902,712. Mr. Reid testified that this sum "represents cash
out the door."
" As Mr. Reid testified:
Retention is monies withheld from the contractors
invoice pending overall óompletion, successful
completion of the contract of work and/or performance
testing acceptance, monies withheld from the
contractors invoice on a monthly basis.
However,. Mr. Reid also testified that the retained amounts were
owed to the contractors.
- 63 Additionally, as of December 31, 1985, there was an unpaid
liability of $5,569,907.6
According to an actual cost report dated January 31, 1986,
the total expenditures to date were $726,985,585.
1986, $23,964,311 was expended on the SJRPP.
During January
This amount paid in
January 1986, covered contract work performed during November and
December of 1985.'°
According to the actual cost report, as·of
January 31, 1986, FPL's obligation was $145,477,686.
A 1986 BI No. 148 Rev. 4 budgeted $239,087,000 "To
participate with * * * [the JEA]
in the joint.construction of. the
first of two coal-fired steam generating units."
The BI
explained that this amount was predicated upon FPL's owning 20
percent of the unit's capital·cost.
This BI stated that work
started in 1979 and would be completed in April 1987.
FPL
approved this BI in late 1985 with only the construction of phase
III yet to ,be completed.
BI No. 148 Rev. 5, approved on October
13, 1986, decreased the amount budgeted to $231 millión.
According to the revlslon, the estimated completion date of
construction was April 15, 1987.
Approved on August 20,
1987, BI
69 Mr. Reid testified that the unpaid liability was for
purchase orders that were amounts outside or above and beyond
contractor expenditures.
° Mr. Reid testified that FPL and the JEA were liable to
the contractors in January 1986 for work performed in November
and December of 1985. This amount, however, did not include the
amounts retained from contractors.
- 64 No. 148 Rev. 6 decreased the amount budgeted to $216 million.
BI
No. 14.8 Rev. 7, approved in late 1988, again decreased the amount
budgeted to the SJRPP project to $204 million.
Finally, BI No.
148 Rev. 8 increased the amount budgeted to $207 million in late
1989.
A 1986 BI No. 149 Rev. 4, approved in late'1985, authorized
$166,453,000 to participate in the construction of Unit 2.
BI
No. 149 Rev. 5 decreased the amount budgeted to this project to
$148 million.
BI No. 149 Rev. 6 decreased the amount budgeted to
$124 million.
BI No. 149 Rev. 7 again reduced the amount
budgeted to $121 million.
ER No. 5736, approved in late 1982/early 1983, authorized
the expenditure of $228,116,000 for the SJRPP Unit 1 "To
participate with * * * [the JEA]
in the joint construction of the
first of two coal-fired steam generating units."
The estimated
date of completion of construction, startup, and initial
operation of the plant was April 1, 1987.
The amount authorized
was decreased to $214,535,000 in late 1986/early 1987.
In late
1987/early 1988, the amount authorized was decreased again to.
$202,637,000.
The revision stated that the unit was operational
at the time of the revision.
On June 30, 1988, ER No. 5736 was
closed "To meet both regulatory and corporate accounting
requirements".
The amount authorized in that revision was
apparently again decreased to $179,979,000.
In late 1988/early
- 65 1989, ER No
5736 was reestimated to $181,990,000.,
1991, FPL increased the ER to $196,666,000.
In early ·
This revision was
increased "to incorporate [the] JEA owners and FPL owners costs
from ER's 5737 and 4290 respectively, and also costs accumulated
to this ER prior to opening ER 4110 (SJRPP Unit 1 Construction
Wrap-Up)."
ER No. 4110, which authorized the expenditure of $22.6
million for the SJRPP-Unit 1 wrap up work," was initiated "to
specifically cover the project costs (excluding the JEA and FPL
owner's costs) beyond June 30, 1988.""
In late 1988/early 1989
the amount authorized under ER No. 4110 was decreased to
$8,736,000.
This ER was again revised-in 1989 to decrease the
amount authorized to $8,016,400.
A few months later, at the end
of 1989, the ER was rev-ised and the amount authorized was
decreased to $7,354,900.
Finally, in 1991, FPL revised the ER to
decrease the amount authorized to $6,575,000.
The parties
-
" Mr. Reid defined "wrap up" work as:
the work that was completed after both units went
commercial.
It's typical of a job this size that
you're going to have punch list type items after.the
units both went commercial.
Included into that is
examples whereas, as I stated, was contract close.out,
retention releases, * * * insurance settlements and
enhancements.
" Mr. Reid testified that the "wrap up" work authorized in
ER No. 4110 was within the original"design of the SJRPP.
He
explained that -"The wrap up was predominantly the construction
and close out of those large dollar contracts and the associated
expense with those."
s
- 66 stipulated that a series of ERs were used by FPL to authorize
amounts to be spent on the SJRPP.
With respect to the installation.of equipment at.the SJRPP,
petitioner incurred capitalized costs (tax basis) of $1,702,649,
$2,376,238, and ($360,804) for equipment placed in service in the
1988, 1989, and 1990 taxable years, respectively.
H.
The Southern Company Contracts
On October 18, 1979, FRL entered into an interchange
contract with an affiliated group of corporations providing
electric power in several southeastern.States, including Georgia
(collectively referred to as the.Southern companies).
The
interchange contract enabled. FPL to acquire coal-fired power from
the Southern companies.
An "interconnection" between power
companies links the two companies' systems to enable them to
purchâse, sell,- and exchange power.
Before 1979, FPL did not
have any interconnections with the Southern companies.
042
For simplicity, the following list identifies these ERs
and the respective amounts authorized:
(1) ER No. 6473, $1,900;
(2) ER No. 6477, $7,300; (3), ER No. 6483, $105,400; (4) ER No.
6487, $96,500; (5) ER No. 6609, $22,400; (6) ER No. 6638,
$35,000; (7) ER No. 6631, $8,900; (8) ER No. 6640, $14,600; (9)
ER No. 6627, $3,100; (10). ER No. 6629, $1,000; (11) ER No. 6645,
$4,400; (12) ER No. 6623, $2,500; (13) ER No. 6633, $14,300; (14)
ER No. 6637, $8,800; (15) ER No. 6639, $38,400; (16) ER No. 6642,
$16,800; (17) ER No. 6651, $9,800; (18) ER No. 6653, $11,200,
revised to $116,000; (19) ER No. 6611, $21,800; (20) ER No. 6654,
$2,200; (21) ER No. 6722, $9,600; (22) ER No. 6716, $2,500; (23)
ER No. 6728, $6,600; (24) ER No. 6730, $11,700; and _(25) ER No.
6644, $9.,200.
a
- 67 The interchange contract specifically required FPL to
construct a 230-kV transmission line from its Duval substation
near Baldwin, Florida, to a point on the Florida-Georgia State
line."
FPL completed the 230-kV transmission line required by
the interchange contract between November 1979 and January 1980.
In addition, the contract required FPL to provide communications,
telemetering, and automatic generation control equipment,
together with such other facilities as may be required for load
dispatching purposes and for control of power flow and reactive
plan.
FPL claims ITCs for the acquisition and construction of
equipment associated with the Southern company supply contract in
the 1988, 1989, and 1990 taxable years.
Subsequent to establishing the interconnection with the
Southern companies under the interchange contract, FPL was
interested in buying more power from the Southern companies.
Effective February·19, 1981, the Southern companies and FPL
entered into a unit power sales agreement (power agreement) under
which the Southern companies sold power to FPL.
agreement continued until May 31,
The power
1995, "or such extended period
agreed to by the parties under the provisions" of the contract.
Also, on Febr,uary 19,.1981, the Southern companies and FPL
entered into amendment. No. 1 to the interchange contract.
The Southern companies were required to construct a 230kV transmission line on their side of the Florida-Georgia State
line to deliver the power.
.
- 68 Amendment No. 1 required both the Southern companies and FPL to
establish two additional interconnections (500-kV transmission
lines) with specific reference to the point of origin and
destination.
Both the Southern companies and FPL were also
required to provide, install, operate, and maintain such
associated terminal and other facilities as may be necessary to
permit effective use of such interconnection.
Each of the
transmission lines required under amendment No. 1 was completed
by December 31, 1982.
On July 23, 1981, FPL and the Southern companies entered
into amendment No. 2 to the interchange contract.
This amendment
accelerated the effective date listed in amendment No. 1 to the
interchange contract (December 31, 1982) to a date before August
1, 1982.
On February 18, 1982, the Southern companies and FPL entered
into an amended and restated unit power sales agreement (amended.
power agreement).
Under the amended power agreement, the
Southern companies agreed to sell more power to FPL, and FPL
agreed to acquire more power from the Southern companies.
The
amended power agreement recognized that FPL would construct
certain internal transmission lines to allow FPL to increase its
purchases of unit power capacity during the contract period,
which began on January 1,
were:
1985.
The contemplated facilities
(i). A 500-kV transmission line from its Duval substation
- 69 -
.
to its Ri'áe s'ubstation continuing to its Poinsett substation;
(ii) a separate 500-kV trafisñiission line from its^Duval
substaÊion 'to îts' Poinsett ' substdt ioh; 'and. (iii) a· 500-kV
transmí ssìõff line f rom'lts1Poinsètt- sûbstation r to- its Martin
plant.
FPL covenaÊÚed ̯o -"use [its] bèst efforts consistent with
Prudérit Utility Practiães' to(comþlete' s'uch facilities by the time
such facilities'are needed·to purchas"e the increased unit power
capacity -on Janua y 1, 1985.
FPL~completed each of the
transmisÃion lines requirea undér thelamended power agreement by
January 1, 1985.
As of Septeinberl.1985, -FPL had developed a
transmission expansiòn. progräm for the yéars 1985 through 1990.
A 1983 BI No. .273'budcjeted $9,670,000 to construct
approximately;13 'inilesl of 240 kV line from the Corbett substation
to th 'RaÈch; substatioñ; extefid' the Orange River-Ranch 240-kV
linè into the Corbett substati'on;
reconductoh" the.240-kV line
from the Cedar substation to the Ranch substation;-install two
240-kV terniinals fbr
he
orbett 1
es
and upgradh the Òedar
- 70,terminal in the Ranch substation."
FPL r.evised this budget ·item
in 1985.to decrease this project's budget to $7 million.
A 1983 BI No. 274. bud.geted $28.4 million as a conceptual
estimate to construct a new 500-240-kV transmission substation,
the Corbett substation, ·consisting of four 500 MVA
autotransformers, one 500-kV line terminal and four 240-kV line
terminals.
According to the budget item, the work was to begin
in November 1985 and was to be completed in May 1987.
A 1985 BI No. 272 budgeted $24.2 million as a conceptual
estimate to construct approximately 33 miles of 500-kV
transmission line between the Corbett- substation and the Martin
plant."
It also states FPL's plan to construct a 500-kV
terminal at the Martin plant switchyard."
The budget item _
scheduled work to commence in May 1986 and to be completed in May
1987.
ER No. 1248, which refers to BI No. 272 and was processed .
" Thomas Sanders, an engineer employed by FPL, testified:
042
This is the construction of 13 miles of new 230 KV
line.
There are two miles of 230 KV line. Between the
two constructions, they basically integrate the 500 KV
Corbett substation with the existing 230 KV·system
that's in the area.. There is also a reconductoring of
the 230 KV line from Cedar to Ranch and the two 240 KV
terminals for the.Corbett lines and the upgrade of the
Cedar and the ranch terminal.
BI No. 272 was originally authorized in 1983 for $23
million.
Mr. Sanders testified that, .according to this budget
item, this work was needed "to reliably transfer contracted
foreign power purchases from the Southern [Companies]."
- 71 in 1986, authorized the expenditure of $15,294,000 to "Construct
33 miles of 500 KV transmission line from proposed Corbett
Substation to Martin Plant."'8
ER No. 1224, approved in 1986, authorized $16,599,430 to
construct ,the Corbett substation, a "500/230, kV air insulated
substation".
ER No. 1249, approved in 1986, authorized the
expenditure of $4,412,159 to construct approximately 11 miles of
double circuit 230-kV transmission line.79
ER No. 2383, approved
in 1987, authorized ·the expenditure of $896,375 to construct
approximately 2.5 miles of double circuit 230-kV transmission
line looping the Orange River-Ranch 230-kV line into the Corbett
substation.
ER No. 1984, approved in 1987, authorized the
expenditure of $113,550 to, inter alia, "Convert the Ranch No. 2,
230kV line to Corbe.tt 230kV line." ; ER No. '1479, approved in
1986, authorized the expenditure of $94,840 for the Orange River
subrelaying equipment for the Corbett 230-kV line.
ER No. 1778,
approved in early 1987, authorized the expenditure of $593,620 to
upgrade a portion of the "230 kV yard at Ranch Substation * * *
to accommodate the Corbett No. 1 and No. 2, 230 kV lines."
'8 Mr. Sanders testified that this expenditure requisition
was approved in 1986, and construction began after such approval.
He also testified that FPL started receiving power under the
Southern company contracts before the construction of the
property.
79 Mr. Sanders testified that the Southern company contracts
did not specifically identify the property listed in ER No. 1249.
- 72 A 1987 BI No. 304, entitled "Transmission.Plant-Systemwide--Miscellaneous--1987", approved in 1986, budgeted $9.8
million for transmission lines, substations, relay projects, and
miscellaneous projects.
ER No. 3276, approved in late 1987/early
1988, authorized the expenditure of $738,140 to replace five 230kV transmission breakers -at the St. Lucie plant.
On the basis of
a study by the systém planning department, the ER states that the
then-existing breakers would become overstressed because of the
500-kV transmission expansion.
A 1989 BI No. 267, entitled
"Transmission.-Plant--Systemwide--Miscellaneous--1989", approved
in 1988, budgeted $23,456,000 to, inter alia, ·upgrade an'd replace
various transmission' lines.
ER No. 5334, approved in late
1988/early 1989, authorized the expenditure of $1,192,967 -to
install one 500-kV bus tie breaker at the Poinsett substation.
ER No. 1776, approved in 1987, authorized the expenditure of
$3,401,908 to install a 500-kV 2 breaker terminal.8°
A 1988 BI
No. 264, approved on October 15, 1987, entitled "Transmission
Plant Systemwide Miscellaneous--1988", budgeted $12,045,000 to,
inter alia, install. high voltage switched capacitor banks at
three locations.
ER No. 3216, approved in late 1987/early 1988,
authorized the expenditure of $1,257,310 to add two 230-kV MVAR
8° Mr. Sanders testified that this expenditure was "an
integral part of the 500 KV transmi'ssion system thãt we built."
.
- 73 capacitor banks to the Poinsett substation.
A section of the ER
labeled "purpose and necessity" states, in part:
an increased load demand coincident with the nuclear
units at Turkey Point out of service and insufficient
reactive support will reduce the transfer capability of
the FPL ties with Southern to scheduled firm
interchanges in the 1988 to 1990 time frame.
* * *
Installation of these capacitor banks and
asso.ciated equipment * * * will provide an increase in
transfer capability of the ties with Southern * * *.
ER No. 3623, approved in early 1988, authorized the expenditure
of $992,000 to add a second 230-kV capacitor bank to the Levee
substation."
ER No. 3219,.approved in 1988,.authorized the
expenditure of $1,182,715 to add two 88 MVAR 230-kV capacitor
banks to the Duval substation.
A 1986 BI No. 129, approved in 1985, budgeted $13.1 million
to install high initial response exciters.82
ER No. 9327,
approved in 1986, authorized the expenditure of $1,225,000 to
install a high initial response excitation system at Turkey Point
Unit 2.
ER No. 9334, approved in 1986, authorized the
expenditure of $740,000 to install a high initial response
The purpose and necessity stated in this ER is very
similar to that stated in ER No. 3216.
82 Mr. Sanders testified that the installation or
construction of the high initial response exciters was required
by the interchange contract to effectively utilize the interface.
excitation system at Martin Unit No. 1.
ER No. 9337, approved in
1986, authorized the expenditure of $1,215,000 to install a high
initial response excitation system at Port Everglades Unit No. 4.
ER No. 9329, approved in 1986, authorized the expenditure of
$970,000 to install a high initial response excitation system at
Turkey Point Unit 4.
ER No. 9326, approved in 1986, authorized
the expenditure of $1,185,000 to install a high initial response
excitation system at Turkey Point Unit 1.
With respect to the equipment relating to the Southern
company supply. contract and the interchange contract, petitioner
incurred capitalized costs (tax basis) of $39,605,571,
$2,648,789, and $1,169,866 for equipment placed in service in the
1988, 1989, and 1990 taxable years, respectively.
I.
Integrated Transmission Line Systems
FPL claims ITCs for components added to the Midway-Jensen-
Crane transmission line system in the 1989 and 1990 taxable
years.
FPL also claims ITCs for components added to the
Andytown-Lauderdale transmission line system in the 1988, 1989,
and 1990 taxable years.
In 1983, FPL filed an application for corridor certification
under the Florida Transmission Line Siting Act proposing the
Midway-Jensen-Crane 230-kV transmission line.
The transmission
line supported the entire load in this particular area of
- 75 Florida."
FPL had a reliability problem.because a single
transmission line fed several substations in the area.
As a
result, if the transmission line lost service at one end, all of
the substations would experience an outage.
FPL planned to break
that line into two segments, including the new Midway-Jensen-
Crane line.
To reliably serve the load in that.area, the plan
also called for additional distributi'on substations to the west.
A 1982 BI No. 244, approved in late 1981, budgeted $1.5
million to:
(1) Acquire 16 miles of 15-foot-wide right-of-way
from Jensen substation to Midway substation;
(2) acquire a 10-
acre substation site for a distributïon/switching station from
Turnpike substation; and (3) acquire 7.5 miles of 15-foot-wide
right-of-way from the Turnpike substation to the Crane
substation.
According to the BI, the work was to be started in
January 1982 and was to be completed in December 1985.
FPL
revised BI No. 244 in late.1982 to increase the amount authorized
.by $200,000 to acquire an additional 1.5 acres at the Jensen
substation for its expansion.
In early 1982, ER No. 5058, which
references BI No. 244, authorized the expenditure of $200,000 to
purchase approximately 10 acres of land as a site for the
purposed Turnpike substation.
Mr. Sanders testified that the Midway-Turnpike-Jensen
transmission line system operated as an integrated unit, and that
FPL viewed the system as one integrated piece of equipment.
- 76 A 1986 BI No. 330, approved in 1985, budgeted $1.2 million
to construct a 230-23-kV one-transformer two-feeder distribution
substation.84
The BI states:
The City of Port St. Lucie has experienced an estimated
67% increase in population from 1980 to 1983.
* * *
Economic studies have indicated that the addition of
Turnpike Substation with its two feeders connected to
the proposed Midway-Sandpiper 230 kV line is the most
cost effective method of addressing this load growth.
ER No. 8476, which references BI No. 330 and. was approved in
early 1985, authorized the expenditure of $1,856,836 to construct
the Turnpike substation.
A 1988 BI No. 206, approved in 1987, budgeted $2.3 million
as a conceptual estimate to construct approximately 7.7 miles of
single pole concrete 230-kV line from the Turnpike substation to
the proposed Crane substation.
The stated reason for budgeting
this amount was:
The area adjacent to Palm City and Martin Downs is
presently being subjected to expansive residential,
commercial, and industrial development. * * *
* * * It is proposed to construct Crane Substation
and the associated Crane-Turnpike 230 kV line to
address the expected load growth and service
reliability to the area.
This line extension will be utilized in the
development of the Turnpike-Crane-Bridge-Plumosus
future circuit.
84 Mr. Sanders testified that BI No. 330 was to build the
Turnpike substation.
- 77 -
ER No. 5366, which referenced BI No. 206 and was processed
in late 1988/early 1989, authorized the expenditure of $2,226,922
to construct approximately 7.7 miles of 230-kV single circuit
transmission line from the existing Turnpike substation to the
proposed Crane substation.. The ER explained that the "ER will
provide service for the expected load growth and improve service
reliability to the area."
A 1988 BI No. 307, approved in.1987, budgeted $1,530,000 to
construct the Crane substation, which consists of a 230-23-kV
line, one transformer, and a two feeder distribution substation.
FPL approved this BI because "The.area adjacent to Palm City and
Martin Downs is presently being subjected to expansive
residential, commercial, and industrial development."
ER No. 4512, approved in 1988, authorized the expenditure of
$111,245 to install a third regulated feeder position to the
Turnpike substation.
The ER anticipated that construction would
begin on March 1, 1989.
ER No. 5056, approved in late 1988/early
1989, authòrized the expenditure of $240,928 to add a third 230kV line terminal to the Turnpike substation.
The ER stated that
"The present 138kV network * * * will become inadequate to serve
load in 1989.
A 1986 BI No. 246,. approved in 1985, budgeted $5,860,000 for
a conceptual estimate to construct approximately 16 miles of
single pole concrete 230-kV line from the Andytown substation to
the Trace substation.
The BI stated that "Extensive development
is presently occurring in the Southwest Broward County area".
Apparently, FPL anticipated that one development project in this
area would have an ultimate peak demand of 270 MVA.
New
substations were anticipated to be built, and FPL proposed to
construct a fourth Andytown-Lauderdale plant 230-kV line to serve
the new substations.85
.
.
ER No. 1333, which referenced BI No. 246 and was approved in
late 1986, authorized .the expenditure of $2,.502,710 to construct
approximately .9.5 miles of single pole concrete 230-kV
transmission line from the Andytown substation to the Trace
substation.
ER No. 1645, which referenced BI No. 246 and was
processed in late 1986/early 1987, authorized the expenditure of
$962,036 to install equipment at the Andytown7substation.
ER No.
1676, which references BI No. 246, authorized the expenditure of
$152,090 to install equipment at the Andytown substation.
A 1986 BI ·No. 253, approved in late 1985, budgeted $1.1
million to construct approximately 3.5 miles of single circuit,
single pole concrete 230-kV line to serve the Trace substation.
The BI states that the project was initially authorized in 1984,
and that the project was completed in May 1985.
The reason for
the BI was "to construct Trace Substation by the summer of 1985
11
85 Mr. Sanders testified that "This line was constructed to
serve the load growth in western Broward County."
- 79 to serve new customers in Bona.Venture Estates and Arvida's
Weston development"."
A 1986 BI No. 254, approved in late 1985,.budgeted $900,000
to construct approximately 2.5 miles of single circuit, single
pole concrete.230-kV _transmission line.
The BI stated that it
was initially authorized for $600,000 in 1984 and that, at that
time, the.line.was under construction.
The BI·stated that this
expenditure was needed because of ,growth in.the area from new
development and increased demand for electricity.", ER No. 1332,
which references BI No. 254, authorized the expenditure of
$2,265,570 to construct approximately 7.5 miles of single pole
concrete 230-kV transmission line from the Hiatus substation to
the Melaleuca substation.
With respect to the installation of the,Midway-Jensen-Crane
transmission line system, petitioner incurred capitalized costs
(tax basis) of. $119,911 and $3,109,573 for equipment placed in
service in the 1989.and 1990 taxable years, respectively.
With
respect to the-installation of the Andytown-Lauderdale
transmission line, petitioner incurred capitalized costs
(tax
basis) of $6,436,912,.$545,188, and $16,707 for equipment placed
Mr. Sanders testified that this BI was for the MelaleucaTrace section of the Andytown-Lauderdale line.
Mr. Sanders testified that "This is another section of
the Andytown-Lauderdale number four line, the Hiatus Springtree
section."
in service in the' 1988, 1989, and 1990 taxable years,
respectively.
J.
Distribution and Transmission Substations
A distribution substation ·transforms transmission voltage of
electricity from high voltage/lower current to low voltage/higher
current; i.e., to "distribution voltage".
The distribution
voltage is distributed through feeder wire (either overhead or
underground), then through either aerial or pad-mounted
transformers, and then to utility customers (residential or
commercial).
A transmission substation either.consolidates
transmission lines or transforms voltage from one ·voltage to
another.
FPL used similar procedures for designing and
constructing distribution substations to those it used for
transmission substations.
Typically, FPL builds a distribution
substation on approximately 5 acres of proper'ty, with
approximately 1.acre in the middle of the property developed for
the substation.
FPL claims ITCs for the distribution and
transmission substation components in the 1988, 1989, and 1990
taxable years.
The most important components of a distribution substation
are the "power transformers" (transformers) because this
equipment transforms the voltage from transmission voltage to
distribution voltage.
Also, the transformers are significantly
more expensive than the other items in the substation.
.A
.
- 81 distribution substation contains other necessary and related
electrical and structural components, including pull-off
structures, switches, bús' work,· feeders, voltage regulators,
equi'pment contained within a "relay vault" (a concrete block
enclosure for electrical equipment),^ wire, cable, control panels,
fencing,· concrete, and steel.
Regulations require that a chain
lin]c fence enclose distribution and· t^ransmission substations.
FPL viewed each' distribution and transmission substation as a
single facility.88
FPL planned a distribution substation typically 5 years in
advance.
The planning process included an analysis of the number
of transformers required.
Substations are built according to
more than 100 structural and electrical plans.
The plans.
graphically illustrate the location of the transformers and
feeder positions:
To build a substation, FPL.was. required to
obtain permits from local, State,' and sometimes Federal agencies.
To allocate funds to'the project, FPL prepared a budget item
the year before a substation was constructed.
After the budget
item ·received approval, an engineer prepared an expenditure
requisition to authorize the payment for the project against the
budget item.
Once the budget item and the expenditure
requisition received approval, FPL prepared detailed drawings for
88 Ken Veronee, an employee. of FPL, testified that each
distribution and transmission substation was a self-contained
unit.
- 82 the substation.
three phases:
Finally, construction would begin, typically in
Site prep work .(clearing trees and vegetation on
the property); substatìon construction; and installation and
testing of equipment.
FPL individually named each distribution
and transmission substation, normally on the basis of geography.
A plot plan was essentially FPL's overall layout of the
substation on the piece of property.
The plot plan graphically
illustrated the general orientation of the high voltage bus work,
location and number of transformers, location of the relay vault,
and all low voltage distribution substation equipment.
FPL
created the plot plan when it prepared the substation's first
budget item because the budget! was based upon the plot plan.
FPL claims an ITC for equipment installed at numerous
substations, including transformers and feeders.
.In the interest
of brevity and ease of explanation, a table has been prepared to
illustrate FPL's claims that is attached as appendix A.
With respect to the distribution and transmission
substations, petitioner incurred capitalized costs
(tax basis) of
$3, 264, 386, $8, 09.1, 517, . and $4, 413., 670 for equipment placed in
service in 1988,
K.
1989, and 1990 taxable years, respectively.
Regional Planning
FPL had a distribution planning group that planned and
provided for an orderly, cost effective expansion of FPL's
electrical distribution system over the long term.
The
- 83 distribution planning group provided extensive analysis.
Annually, this group collected data related to electrical power
needs from residential customers, small businesses,
commercial/industrial customers,.large customers, and
governmental customers.
involved:
system;
The distribution planning process
(i) .Evaluation of load demands on the distribution
(ii) analysis of alternatives for providing electrical
service to customers, currently and over the long term;
(iii)
.evaluating the cost and reliability of alternatives against any
risk associated with the alternative; and (iv) selection of the
best alternative.
Load" is.the demand for electricity from customers.
The
distribution.planning group made projections of "load growth"
over the short, medium, and long terms.". To project load
growth, the distribution planning group,conducted an extensive
analysis of, inter alia, historical load growth and anticipated
land uses in relevant areas.
The distribution planning group's
expertise in analyzing load growth allowed.FPL to determine the
" Michael H. Hernandez, FPL's operations support,
supervisor, testified:
Distribution planning will go ahead and first
measure how much of our actual loading we have on our
existing equipment.
We will review that loading.
We
will go ahead and forecast loads into the future and
determine if there are any future weaknesses, either
current or future, and plan for alternatives of how to
go ahead and deal with.those projected weaknesses.
size and number of distribution substations that FPL needs for
its distribution system.
A development of regional impact (DRI) project is a large
development project that has an impact beyond a particular
municipality and becomes subject to the requirements of the
Florida Administrative Code.
Examples of DRI projects include
large housing developments and commercial construction projects
(regional malls and stadiums).
Regional planning councils
throughout the State of Florida review DRI projects.
FPL claims
ITCs for the acquisition and construction of property related to
the DRI projects in the 1988, 1989, and 1990 taxable years.
Before a developer of a DRI project is permitted to commence
construction, the developer must submit an application for
development approval to the appropriate regional planning
council.
.
The application for development approval requires,
inter alia, a statement or letter from the offsite source of
electricity indicating its ability to provide electric service at
all times during and after the development.9°
To fulfill a
90 Mr. Hernandez explained how FPL responded when a
developer requested power:
We review it to see what work is going to be required
in order to serve the project. We establish a file on
the project. We go ahead and determine an a.rea of
study including the project. We look at the existing
facilities we have within the area. We look at the
demand on those existing facilities. We look at what
other additional projects are coming on in service in
(continued...)
.
requirement of the application for development approval, a
developer submits a letter of inquiry to the offsite source of
electricity, in this case FPL, as to whether it can meet the
developer's électricity needs for his proposed development.91
The letter from FPL to·the developers generally stated that FPL
was ready and able to provide the needed electrical services to
serve the development project.
For example, the record contains an application for
development approval for the Palm Beach International Airport.·
This application.was made according to section ·380.06(6) of the
Florida Statutes to the Bureau of Land and Water Management,
Division of State Planning, Department of Administration, State
of Florida·.
The Palm Beach County Department of Airports made
the application to undertake a DRI project.
Included with the
9°(...continued)
that area, also what additional vacant land is in that
same area, and then look at alternative ways of serving
it, whether it can be served from existing facilities,
whether it requires new facilities, and what new
facilities it requires..
* * *
" Mr. Hernandez testified as follows:
Q:
And what does the special process require of
the developer?
A:
As I said, the developer has to make an
application, and prior to making that
application they must first apply. to Florida
Power and Light a request for service. They
must enumerate how much energy they are going
to use * * * and they have to show how much
load or demand they are going to have * * *
application is a letter from the developer to FPL concerning its
load needs for the DRI project.92
On June 1, 1981, FPL wrote a
letter to the Palm Beach County Department of Planning, Zoning &.
Building stating that it ·anticipated "no problem in providing
electric service" for the DRI project, the Palm Beach
International Airport.
The record contains a portion of the
Treasure Coast Regional Planning Council's DRI update which
lists, inter alia, the Palm Beach International Airport
project.93
The document is in table format with columns and rows
detailing the specifics of each project.
One of the columns is
titled "Effective Date"., which was February 16, 1982, for the
Palm Beach International Airport project.94
The Palm Beach International Airport project 1s
representative of the many DRI ·projects in the record for which
FPL claims ITCs.
Petitioner introduced work orders for the
92 Mr. Hernandez was asked and answered as follows:
Q:
A:
At the time FPL issues the response letter,
is it possible to know exactly how much cable
and trench will be required?
No, it wouldn't because the developer hasn't
finalized his plans; and, therefore, we don't
know the exact routes of these cables.
93 Mr. Hernandez testified:
"This document establishes the
status of the project and shows that the project has been given
permission to go ahead."
94 jvfr. Hernandez testified that "The effective date is the
date that the project has permission to move ahead."
r
various DRI projects for which it claims ITC.s.
Because of the
large numbër of DRI projects and in the interest of brevity, we
will detail in appendix B the information from the work orders
that petitioner cites on brief to support its claimed ITCs.
With respect to equipment related to the DRI projects,
petitioner incurred capitalized costs (tax basis) of $1,464,901,
$3,609,855, and $4,832,205 for equipment placed in service in the
1988, 1989,.and 1990 taxable years, respectively.
OPINION
A.
The Statutory Landscape
Before 1986, _section 38 (a)" of the Internal Revenue Code of
1954 provided businesses with an investment tax credit
(ITC), and
section 46(a) determined the amount of the ITC available to
taxpayers.
Section 49(a) eliminated the ITC for all property
placed in service after December 31, 1985.96
However, section 49
" Unless otherwise indicated, all section references·are to
the Internal Revenue Code for the years at issue, and all Rule
references are to the Tax Court Rules of Practice and Procedure.
" Sec. 49(a), which was added to the Internal Revenue Code
by the Tax Reform Act of 1986 (TRA), Pub. L. 99-514, sec. 211,
100 Stat. 2166, provides:
SEC. 49. TERMINATION OF REGULAR PERCENTAGE.
(a) General Rule.--For purposes of determining the
amount of the investment tax credit. determined under
section 46, the regular percentage shall not apply to
any property placed in service after December 31, 1985.
- 88
'
contained transitional rules that excepted "transition property"
from the repeal of the ITC.97
Sec. 49(b).
Section 49(e) defined
"transition property" as:
SEC. 49 (e) . Transition Property.--For purposes of
this section--
(1) Transition property.--The term
"transition property" means any property placed. in
service after December 31, 1985, and to which the
amendments made by section 201* of the Tax·
Reform Act of 1986 do not apply, except that in
making such determination-(A) section 203 (a) (1) (A) of such Act
shall be applied by substituting "1985" for
"1986",
(B) sections 203 (b) (1)· and 204 (a) (3) of
such Act shall be applied by substituting
"December 31, 1985" for "March 1, 1986",
(C) in the case of transition property
with a class life of less than 7 years--
97 The transitional rules were intended to provide relief to
taxpayers who may have committed to post-1985 investments in
qualifying property in reliance on the availability of the
credit.
See Newhouse Broad. Corp. v. Commissioner, T.C. Memo.
2000-270.
The House Ways and Means Committee made the following
observation with respect to the repeal of the ITC:
The committee is aware that commitments have
already been made on the basis of present law capital
cost recovery rules. The committee bill provides for
equitable transition rules in such cases, which are
estimated 'to cover more than 50 percent of the new .
personal property to be placed in service in the first
year the bill is effective.
H. Conf. Rept. 99-426, at 146 (.1985), 1986-3 C.B.
146.
(Vol. 2) 1,
98 TRA sec. 201, 100 Stat. 2121, amended sec. 168, which
relates to the accelerated cost recovery system.
- 89 (i) section 203(b) (2) of such Act
shall apply, and
. ,
(ii) in the case of property with a
class life-(I) of less than 5 years, the
applicable date shall be July 1,
1986, and
(II) at least 5 years, but
less than 7 years, the applicable
date shall be January 1, 1987,
* * *
The pertinent portions of TRA section 203, 100 Stat. 2143,
provide:99
SEC. 203. EFFECTIVE DATES;.GENERAL TRANSITIONAL RULES.
(a) Gèneral Effective Dates.--
(1) Section 201.-(A) In general.--Except as provid'ed in
this section, section 204, and section
251(d), the amendments made by section 201
shall apply to property placed im service
after December 31, [1985] 1996, in taxable
years ending after such date.
(b) General Transitional Rule.-.(1) In general.--The amendments made by
section 201 shall not apply to-(A) any property which.is constructed,
reconstructed, or acquired by·the taxpayer
99 pggggggt to see. 49(e), date changes have been made in
TRA secs. 203 and 204. The stricken portions are the original
dates, unmodified by sec. 49(e). The inserted dates are those
which were modified by sec. 49(e) (1) (A) and (B) and applicable to
this case.
- 90 pursuant to a written contract which was
binding on [December 31, .1985] March-17-1-9&6,
(B) property which is constructed or
reconstructed by the taxpayer if-(i) the lesser of (I) $1,000,000,
or (II) 5 percent of the cost of such
property has been incurred or committed
by [December 31, 1985] Mareh-17-+996,
and
(ii) the construction or
reconstruction of such property began by
such date, or
(C) an equipped building or plant
facility if construction has commenced as of
[December 31, 1985) March-tr-1-946, pursuant
to a written specific plan and more than onehalf of the cost of such equipped building or
facility has been incurred or committed by
such date.
(2) Requirement That Certain Property Be
Placed In Service Before Certain Date.--
(A) In general.--Paragraph (1) and
section 204 (.a) (other than paragraph (8) or
(12) thereof) shall not .apply to any property
unless such property has a class life of at
least 7 years and is placed in service before
the applicable date determined under the
following table:
In the case of property
with a class life of:
The applicable
date is:
At least 7 but less than 20 years...January 1, 1989
20 years or more....................January 1, 1991
(B) Residential rental and
nonresidential real property.--In the case of
residential rental property and
nonresidential real property, the applicable
date is January 1, 1991.
- 91 (C) Class lives.--For purposes of
subparagraph (A)--
(i) the class life of property to
which section 168 (g) (3) (B) of the
Internal Revenue Code of 1986 (as added
by section 201) shall be the class life
in effect on January 1, 1986, except
that computer-based telephone central
office switching equipment described in
section 168 (e) (3) (B) (iii) of such Code
shall be treated as having a class life
of 6 years,
(ii) property described in section
204 (a) shall be treated as having a
class life of 20 years, and
(iii) property with no class life
shall be treated as having a class life
of 12 years.
(D) Substitution of applicable dates.-If any provision of this Act substitutes a
date for an applicable date, this paragraph
shall be applied by using such date.
The pertinent portion of TRA section 204, 100 Stat. 2146,
pròvides:
SEC. 204. ADDI·TIONAL TRANSITIONAL RULES.
(a) Other Transitional Rules.--
*
*
*
*
*
*
*
(3) Supply or service contracts . --The
amendments made by section 201 shall not apply to
any property which is readily identifiable with
and necessary to carry out a written supply or
service contract, or agreement to lease, which was
binding on * * * [December 31, 1985) Maüli 1,
+9%.
We note that "provisions granting special tax exemptions are
to be strictly construed."
Helvering v. Nw. Steel Rolling Mills,
- 92 311 U.S. 46, 49 (1940).
This rule of interpretation applies
equally to transitional rules.
United States v. Commonwealth
Energy Sys . , 235 F . 3d 11, 16 (1st Cir . 2000 ) ; see Apache Bend
Apartments, Ltd. v. United States,
987 F.2d 1174, 1175
(5th Cir.
1993); United States v. Kiellstrom, 916 F. Supp. 902, 905 (W.D.
Wis.. 1996), affd. 100 F.3d 482 (7th Cir. 1996).
As the Court of
Appeals for the First Circuit explained:
The transition rules were enacted to provide relief "to
a very, very few specified favored taxpayers," * * *
and although we must extend them to all qualifying
taxpayers, * * * we need not broaden our interpretation
so that entities that did not detrimentally rely on the
old rule benefit from the transition exemption * * *
[Citations omitted.]
United States v. Commonwealth Energy Sys., supra at 16.
The
taxpayer bears the burden of proving that it qualifies for the
transitional rules.
Rule 142(a); Pavless Cashways, Inc. v.
Commissioner, 114 T.C. 72, 80 (2000).
B.
TRA Section 204 (a) (3)--Supply or Service Contracts
Petitioner argues that it is entitled to ITCs for property
FPL placed in service during the years at issue because FPL
purchased and/or installed the property pursuant to binding,
written supply contracts within the meaning of TRA section
204 (a) (3) .
According to petitioner, the following contracts
constitute binding, written supply contracts:
(1) The tariff;
(2) the Southern company contracts; and (3) the documents
exchanged with respect to the DRIs.
Respondent argues that
- 93 petitioner "did rnot enter into any written supply contracts that
were binding on December 31, 1985."
Pursuant to TRA section 2.04 (a) (3), property qualifies for
relief ~from. the ITC repeal only when it is "readily identifiable
with' and necessary.to carry.out a wrïtten supply or serv.ice
contract,.* * * which was binding on" December 31, 1985.
also sec. 49(e) (1).
See
Many courts havè grappled with interpreting
this language and have looked to legislative history for
guidance.
See United States v. Commonwealth Energy Sys., supra;
Bell Atl.. Corp. v. United States, 224 F.3d;220
(3d Cir. 2000),
affg. 82 AFTR 2d 7375, 99-1 USTC par. 50,119 (E.D. Pa. 1998);
Maine Yankee Atomic Power Co. v. Commissioner, T.C. Memo. 2002176.
As the Court of Appeals for the First Circuit exþlained:
"Still it is possible to think that there are ambiguities
inherent in the clause 'readily identifiable with and necessary
to carry out,' ,and that the level of specificity. required as to
both 'readily identifiable' and 'necessary' is not selfdefining."
16.
United States 'v. Commonwealth Eneray Sys., supra at
The conference report explains:
This transitional rule is applicable only where
the specifications and amount of the property are
readily ascertainable froà the terms of -the contract,
or from related documents. A supply or service
contract or agreement to lease must·satisfy the
requirements of a binding contract * * *.
H. Conf. Rept. 99-841 (Vol. LI), at II-60 (1986), 1986-3. C.B.
(Vol. 4) 1, 60.
We glean from· this· that the specifications and amount of
property must be readily or "easily" ascertainable from the. terms
of the source documents, which consist of the contract and
related documents .
United States v. Commonwealth Energy Sys . ,
supra at 16; Bell Atl. Corp. v. United States, supra at 224.
Because the specifications and amount of the property must be
readily ascertainable, this rule requires a "specific, although
not exact", inquiry.
United States v. Commonwealth Energy Sys.,
supra.
1.
Property Purchased and/or Installed Pursuant to the
Tariff
Petitioner argues that "FPL and its customers, through the
* * * [FPSC], entered into a binding written supply or service
contract in the form of a Tariff in 1984."
Petitioner further
contends that the tariff is a contract under Florida law;
therefore,
it is a binding contract for Federal tax purposes.
Accordingly, petitioner asserts that it acquired, installed, and
constructed and/or reconstructed property that was readily
identifiable within the tariff and/or related documents, and that
this property was necessary to carry out FPL's supply obligations
to its customers under the tariff.
Petitioner seeks ITCs for the
- 95 tariff related equipment that was placed in service during 1988,
1989, and 1990.1°°
a.
The Tariff Is Not a Contract for Purposes of
TRA Section 204 (a) (3)
In support of its argument, petitioner cites cases that
generally state that a tariff is a contract.
For example, in
Life Sciences, Inc. v. Emery Air Freight Corp., 341 So. 2d 272
(Fla. Ct. App. 1977), a shipper brought suit against an air
carrier to recover damages to its cargo.
Apparently, a tariff
filed by the freight forwarder contained a 1-year property damage
1°° Petitioner argues that the following equipment is readily
identifiable with the tariff and incorporated documents:
(1) The
nuclear fuel assemblies; (2) the nuclear plant property (MSIV air
accumulation system, surveillance system for heat exchangers,
reactor vessel probes, raceway protection, spent fuel rack
equipment, and area radiation monitoring system equipment); (3)
environmental property (PCB transformers and wastewater
neutralization treatment system); (4) simulator and training
buildings; and (5) the LMS. The tax bases of. the property for
which petitioner seeks ITCs are as follows:
Property
Nuclear fuel assemblies
MSIV air accumulation
system
Surveillance system for
heat exchangers
Reactor vessel probes
Raceway protection
Spent fuel rack equipment
Area radiation monitoring
system equipment
PCB transformers
Wastewater neutralization
treatment system
Simulator and training
buildings
LMS
1988
1989
1990
$51, 684, 173
--
$70, 782, 440
2,846,306
$133, 263, 604
126,666
--
123,742
324,668
826,767
-6, 713, 729
--
(126,353)
969,676
532, 892
--
(12,983)
239,161
6, 646, 960
657,253
886,616
241,469
748,411
--
36,053
233,742
1,486,050
1,458,213
354,914
362,837
15,156,624
39,351,031
claims limitation based upon a Florida statute.
The
freight forwarder argued that the limitation period stated in the
tariff was invalid as such power could only be granted by Federal
law.
In holding against the freight forwarder, the court stated
that "The tariff filed by * * * [a freight forwarder] constituted
part of the contract of carriage between it and its customer".
Id. at 273; see also Bd.·of Water, Lioht and Sinking Fund Commrs.
v. FERC, 294 F.3d 1317, 1319 n.2 (11th Cir. 2002); Atlanta Gas
Light Co. v. FERC, 140 F.3d 1392, 1395 n.1 (11th Cir. 1998)
("A
tariff is the.'contract which governs a pipeline's service to its
customers.'"); ANR Pipeline Co. v. FERC, 931 F.2d 88, 90 n.1
-
(D.-C. -Cir. 1991); Bell S. Telecomm., Inc. v. Jacobs, 834 So. 2d
855, 859 (Fla. 2002); Bella Boutique Corp. v. Venezolana
Internacional de Aviacion, S.A., 459 So. 2d 440, 441
App. 1984)
(Fla. Ct.
("A validly filed tariff constitutes the contract of
carriage between the parties and conclusively and exclusively.
governs the rights and liabilities between the parties.").
In Bell Atl. Corp. v. United States, 82 AFTR 2d 7375,
99-1
USTC par. 50,119 (E.D. Pa. 1998), the District Court discussed
this issue at length.
That court examined whether TRA section
204 (a) (3) entitled the taxpayer to an ITC based upon, inter alia,
a tariff.
As that court stated:
"A contract is·'a promise or
set of promises for the breach of.which the law gives a remedy,
or the performance of which the law in some way recognizes as a
.
- 97 duty.'"
Id. at 7379, -99-1 USTC par. at 87,037
(quoting 1
Restatement, Contracts 2d, sec. 1 (1981); Black's Law Dictionary
322 (6th ed. 1990)).
The District Court then explained:
A tariff is "a public document setting forth
services of a common carrier being offered, rates and
charges with respect to services and governing rules,
regulations and practices relating to those services."
Black's Law Dict. 6th ed. (1990) at 1456-57.
* * *
Tariffs set forth a description of the services
that a particular regulated public utility provides,
including the prices that customers may be charged for
these services. Tariffs are reviewed and may be
challenged by the regulating authority and consumers.
Once effective, tariffs bind the customer and the
utility to the tariffs [sic] terms.
* * *
Id. at 7381, 99-1 USTC par. 50,119, at 87,039.
The court looked
at the broad terms of the tariffs and concluded that the tariffs
were not TRA section 204 (a) (3) service or supply. contracts.
court reasoned as follows:
First, the court does not find that the tariffs
are contracts under the normal definition of that term.
However, even accepting arguendo that the tariffs are
contracts, the court finds that these tariffs are not
the type of contracts Congress contemplated under the
ITC. The tariffs are. descriptions of services offered
and prices to be charged. They are terminable at will
by the customers and * * * [the taxpayer) can.modify
them by filing a new tariff.
The regulating
authorities can revoke the certifications and levy
.fines. The tariffs are merely the rules with which
* * * [the taxpayer] must conform if it chooses to
conduct business in the particular jurisdiction.
* * *
[The taxpayer] may decide that it does not agree with
the terms and may decide not [to] apply to provide its
service in a particular jurisdiction.
It would not be
bound to do so. None of the tariffs require the
purchase of property. None of the tariffs or related
documents alone or together identify the property to
the "contracts" or necessitate the purchase of the
The
- 98 property. The court finds that. the property for which
* * * [the taxpayer] claims the ITC was not "readily
identifiable with and necessary to carry out" these
"contracts."
Id. at 7382, 99-1 USTC par. 50,119, at 87,040.
We find the District Court's reasoning in Bell Atl. Corp.
persuasive.
Indeed, the tariff that petitioner argues is a TRA
section 204 (a) (3) contract is strikingly similar in its broad
description of rights and duties to the tariff described by the
District Court in Bell Atl. Corp."1
The tariff at issue sets
forth the rates to be charged and the general service commitments
to which FPL had to adhere if it wanted to provide electrical
service to customers under the jurisdiction of the FPSC.
Cus.tomers could discontinue service at will and without penalty.
The price for electrical service was not permanently fixed; from
time to time, FPL could (and did) petition to change the price
term in the tariff.
The term establishing the fee that customers
must pay for electrical service was not fixed.
"that the tariffs are [not]
. of that term."
Id.
Thus, we agree
contracts under the normal definition
Rather, the tariff is more akin to a set of
operating rules imposed on petitioner by the State that
1 In Bell Atl. Corp. v. United.States, 224 F.3d 220 (3d
Cir. 2000), the.Court of Appeals for the Third Circuit affirmed
the District Court's holding, which denied the taxpayer's claimed
ITC.
In affirming the District Court, the Court of Appeals did
not find it necessarÿ to decide whether Bell Atlantic's tariffs
franchises, and contracts with.other telephone companies are
written service contracts' within the meaning of the Act." Id.
at 223.
4
petitioner must follow if it wishes to'provide services to
customers.
The tariff does not obligate customers to continue
the purchase of electrical services, and the price for future
services can be adjusted by the State.
Petitioner also argues that respondent has taken the
position in published guidance that a tariff is a contract.
Petitioner cites Rev. Rul. 68-109, 19'68-1 C.B. 10, which
addressed "whether switchboards installed in furnishing
communications services to tax-exempt organizations or government
units qualify as
'section 38 property.'"
Id.
In the revenue
ruling, the investment tax credit would not have been available
had the property.been owned by or leased to the tax-exempt
organizations or. government units.
The taxpayer installed
equipment pursuant to contracts between it and its bustomers that
were tax-exempt organizations or government units.
Under the
terms of the contracts, the taxpayer retained all ownership and
control of the equipment, and the customers paid the installation
charges and provided an operator for the equipment.
of these factors, the ruling concludes:
On the basis
"Hence, the agreement
entered into.between the taxpayer and the customer is not a sale
or lease but a service contract."
Id.
After holding that the
agreement was a service contract, the revenue ruling stated:
Furthermore, the services furnished by the taxpayer [a
regulated utility] and the manner in which they must be
furnished are described in tariffs on file with the
Federal Communications Commission * * *. These tariffs
- 100 constitute a public offering by the utility which, when
accepted by the subscribers,·creates a contract
embodying the terms and conditions of that tariff.
* * *
Id.; see also Rev. Rul. 72-49, 1972-1 C.B. 125.
In Rev. Rul. 68-109, supra, there was a service contract
independent of the tariff.
The conclusion of the revenue ruling,
that there was a service contract, is based upon the agreement
entered into between the utility and its customers.
After
determining that such service contract existed, the revenue
ruling found that "Furthermore" the provisions of the tariff also
bound the parties.
The instant case is distinguishable because there was no
binding contract independent of the tariff.
The service
agreement between the utility and its customers was the
determining.factor in the ruling..
It was in this context that
the ruling stated that the tariff was a contract.
The revenue
ruling does not address TRA section 204 (a) (3), nor does it state
that the tariff is a binding supply or service contract.
Here,
we must determine whether the tariff constitutes a binding supply
or service contract for purposes of TRA section 204 (a) (3).
We do
not think this revenue ruling supports a finding that the tariff
is a binding supply or service contract for purposes of TRA
section 204 (a) (3).
- 101 b.
The Tariff Does Not Readily Identify the
Property in Issue
Even assuming for the sake of argument that the tariff is
the type of contract which Congress contemplated when it drafted
TRA section 204 (a) (3), we do not believe the property for which
petitioner seeks an ITC was "readily identifiable" in that
tariff.
The link between the tariff and the property for which
petitioner seeks ITCs is "too attenuated" to be considered
"readily.identifiable" under TRA section 204 (a) (3).
See United
States v. Commonwealth Energy Sys., 235 F.3d at 17; Bell Atl.
Corp. v. United States, 224 F.3d at 224.
Indeed, "Congress added
the word 'readily' to imply a more immediate link between the
terms of the contract and the property at issue."
United States
v. Commonwealth Energy Sys., 235 F.3d at 17; see Bell Atl. Corp.
v. United States, 224 F.3d at' 224; S. Multi-Media Commcns., Inc.
v. Commissioner, 113 T.C. 412
(1999); United States v. Zeigler
Coal Holding Co., 934 F. Supp. 292, 294-295 (S.D. Ill. 1996).
"Congress did not want to extend ITC to all property that was
identifiable and -necessary to carry out a service contract."
Bell Atl. Corp. v. United States, 224 F.3d at 24.
As in Bell Atl. Corp., the tariff at issue does not specify
any of the property for which petitioner seeks an ITC.
Under
petitioner's construction of TRA·section 204 (a) (3), any property
used.in the generation of electricity or in supplying customers
with electrical service would be considered readily identifiable.
- 102 The tariff is not concerned with the "hows" or the "whats" of
generating electricity; it merely sets forth the expected
services FPL will provide to its customers.
We do not think this
is what Congress intended when it drafted the transitional relief
to the repeal of the ITC.
c.
Documents Incorporated by Reference Into the
Supply or Service Contract
Petitioner .also argues that the documents incorporated into
the tariff readily identify the specifications and amount of
property for which it claimed ITCs.
Petitioner contends that it
is irrelevant that the tariff does not reference the other
documents because "'referencing' is not the test for a 'related
document'."
The supply or service contract rule requires.that property
is readily identifiable from the terms of the contract or related
documents.
TRA sec. 204 (a) (3); H. Conf. Rept. 99-841 (Vol. II),
supra at II-60, 1986-3 C.B.
(Vol. 4) at 60.
When a contract
specifically incorporates another document by reference, the
referenced document constitutes a "related document".
See Maine
Yankee Atomic Power Co. v. Commissioner, T.C. Memo. 2002-176.
Language within a contract that generally refers to industry
standards and the applicable law, without specifically referring
.
- 103 to a document, fails..to incorporate by reference those documents
created.according to the industry.standards and applicable laws.
See id.
For the documents to qualify as "related documents.", the
supply contract must adequately incorporate the documents by
reference.
In Maine Yankee Atomic Power Co., the taxpayer
claimed an ITC under TRA section 204 (a) (3) with, respect to
nuclear fuel assemblies.
The parties stipulated that the .power
contracts and amendments as of December 31, 1985, qualified as
binding written supply or service contracts under TRA,section
204 (a) .
Id.
Ho.wever, the parties disputed whether the nuclear
fuel assemblies were readily identifiable with the power
contracts.
Id.
While the taxpayer conceded that.the power
contract faile.d to list the specifications of the fuel
assemblies, it argued that the operating license, and amendments
and appendices of the power contract constituted "related
documents".
Id.
The taxpayer argued that the following language
incorporated the "related. documents".by reference:
Maine .Yankee * * * will operate and maintain the
Unit * * *. in accordance with good utility practice
under the cïrcumstances and all applicable law,
including the applicable provisions of the Atomic
Energy Act of 1954, as amended, and of any licenses
issued thereunder to Maine Yankee."
[Emphasis added in
original.]
.
Id.
.
-'
I!
- 104 . This Court found that the operating licenses and their
amendments were not "related documents" because the power
contract contained only a general reference and failed to
specifically refer to these documents.
I
ldm ·"This general
.
standard of operation and maintenance, without more, does not
incorporate the operating license, or amendments or appendices
thereto, into the power contracts."
Id.
In this case, petitioner argues:
The Tariff incorporated by reference applicable órders,
rules and regulations of various governmental bodies,
including, for example, the Nuclear Regulatory
Commission ("NRC"), the Environmental Protection Agency.
("EPA"), the Florida Department of Environmental
Protection ("FDEP") , the FPSC and others .
FPL was
required under the Tariff to comply with these orders,
rules and regulations.
According to Mr. Wilson's testimony and the citations contained
in petitioner's proposed findings of fact, the relevant language
in the tariff states:
RULES AND. REGULATIONS
Service under this schedule is subject to orders
of governmental bodies having jurisdiction and to the
currently effective 'General Rules and Regulations for
Electric Service' on file with the Florida Public
Service Commission.
In case of conflict between any
provision of this schedule and said 'General Rules and
Regulations for Electric Service' the· provision of this
schedule shall apply.
Mr. Wilson testified:
The Commission had rules and regulations itself
that concerned the quality of service, how companies
were to treat deposits for service for customers, the
complaint procedure, things like that.
And this was
.
-.105 '
-intended to.incorporate, to refer to-·that,. so that
anyone looking at this tariff sheet would see that
there were other conditions that apply.
Neither TRA section 204 (a) (3) nor the conference report
articulates a standard for identifying "related documents."
Maine Yankee Atomic Power Co. indicated that a supply or service
contract must incorporate an item by reference for it to
constitute a "relate^d document."
In ^11ght of Helvering v.- Nw.
Steel Rollina Mills, 311:U.S. at- 49, we agree with the
interpretation of the supply·or service contract rule in.Maine
Yankee Atomic Power Co.' bebause it.strictly construed the ITC transitional rule, a provision which grants- a special tax
exemption.
Petitioner's' position would expand the supply or
service contract rulè beyond its proper scope because property
could be identified from documents that have not been referred to
in the supply or service contract. . Therefore, we find that the
languaye in the tafiff must incorporate by reference' the alleged
"related documents".
The general language lof the power contract in Maine Yankee
Atomic Power Co. is analogous to the language petitioner relies
upon in the4tár'iff.
The 't'axpayer in.Maine Yankee Atomic Power
Co. asserted that the power contract incorporated "relatéd
documents" by providing that its power plant will operate "in
accordance with good utility practice under the circumstances and
all applicable law, including the applicable provisions of the
- 106 Atomic Energy Act of 1954, as amended, and of any licenses issued
thereunder to Maine Yankee."
Maine Yankee Atomic Power Co. v.
Commissioner, T.C.. Memo. 2002-176.
Both the Maine Yankee Atomic Power Co. power contract and
petitioner's tariff contain general references to the authorities
that govern service quality and standards.
Each fails to refer
to any specific document. · The general statements referring to
service standards and regulatory orders lack the details
necessary to identify which documents constitute related
documents.
See Mainè Yankee Atomic Power Co. v. Commissioner,
supra ("This general standard of operation and maintenance,
.
.
.
without more, does not incorporate the operating license, or
amendments or appendices thereto, into the power contracts.") .
Because petitioner's. tariff contains only a general statement
identifying "orders of governmental. bodies having jurisdiction
and to the currently effective 'General Rules. and Regulations for
Electric Service' on file with the Florida Public Service
Commission", we hold that the tariff .fails to incorporate by
reference the alleged "related documents".
d.
.
Property Readily Identifiable From the Related
Documents
Assuming arguendo that the tariff qualifies as a contract
and the documents cited·by petitioner qualify as "rélated
documents", the property in issue must be readily identifiable
from the terms of these "related documents".
TRA sec. 204 (a) (3) .
- 107 The conference report states that TRA section 204 (a) (3) applies
only when the specifications and amount of the property.are
readily ascertainable from the terms of the contract and related
documents.
H. Conf. Rept. 99-841 (Vol. II), supra at II-60,
1986-3 C.B.
(Vol. 4) at 60.
i. ,
Statutess·and Regulatory Materials
Petitioner argues that statutes and regulatory guidelines
are "related documents" that readily identify the property it
installed pursuant to the tariff. , Specifically, petitioner
contends that the following statutes and regulatory materials are
"related documents":
(1) The U.S. Nuclear Regulatory Commission,
Office of Nuclear Reactor Regulation, Clarification of TMI Action
Plan Requirements, NUREG-0737
(NUREG 0737);
(2) a letter from the
U.S. Nuclear Regulatory Commission, to all licensees of operating
reactors, applicants for operating.licenses, and holders of
construction permits, Supplement 1 to NUREG-0737 (December 17,
1982)
(Generic Letter 82-33);
(3) the U.S. Nuclear Regulatory
Commission, Office of Nuclear Regulatory Research, Regulatory
Guide 1.97, Rev. 3 (1983)
(Regulatory Guide 1.97,.Rev. 3);
C.F.R. sec. 50, App. R (1992)
(appendix R);
(4) 10
(5) the Nuclear Waste
Policy Act of.1982, Pub. L. 97-425, 96 Stat. 2201 (Nuclear Waste
Policy Act of 1982);
94-469,
(6) the Toxic Substance Control Act, .Pub. L.
sec. 6(e), 15 U.S.C. sec. 2605 (1976)
(TSCA sec. 6(e));
and (7) the Environmental Protection Agency, Polychlorinate
- 108 Biphenyls (PCBs) Manufacturing, Processing, Distribution in
Commerce and Use Prohibitions; Use in Electrical Equipment, 47
Fed. Reg. 37,342 (Aug. 25, 1982)
(codified at 40 C.F.R. pt. 761).
We find that these statutes and regulatory materials fail to
provide the specifications and amount of property for which
petitioner seeks ITCs.
.TRA section 204 (a) (3).requires that the
terms of the supply contract and related documents readily
identify the specifications and amount of the property.
These
regulatory materials provide guidelines that are generally
applicable; however, they do not specifically refer to
petitioner's property.
Petitioner's reliance on regulatory guidance.to readily
identify its property is 'similar to that of the taxpayer in Bell
Atl. Corp. v. United States, 224 F.3d at 221, which relied on
service quality standards in its utility franchises, tariffs, and
contracts with other telephone companies to identify property for
purposes of TRA section 204 (a) (3).
In Bell Atl. Corp., the court .
found that the terms of the utility franchise, tariffs, and
contracts with other telephone companies did not readily identify
the taxpayer's property because "these alleged 'contracts'
speak
only of service quality standards, never mentioning property of
any sort."
Id. at 224.
- 109 The.franchises, tariffs, and contracts in Bell Atl. Corp.
failed to specifically refer to the taxpayer's property.
The
statutes and regulatöry guidance petitioner relies on also fail
to specifically.identify any of FPL's property.
These regulatory
materials establish quality and service standards and lack
references or descriptions that specifically relate to
petitioner's property.
We find that the documents lack. the
specifications and amounts necessary to readily identify
petitioner's property for purposes of TRA section 204 (a) (3)..
ii.
Corre.spondence
In addition to the statutes and regulatory guidance,
petitioner asserts that numerous.items óf correspondence are
"related documents" that readily identify the property in issue.
Particularly, petitioner relies on:
(1) Letter, No. L-85-385,
dated October 11, 1985, from FPL to the Office of Nuclear Reactor
Regulation;
(2) a letter dated July 18, 1986, from FPL to the
Office of Nuclear Reactor Regulation;
This text is long and has been trimmed here. Open the source document for the complete record.
This is a copy of a public record, reproduced as it was published. It is not legal advice, and it may not be the version a court would rely on. Check the official source before you cite it.