Federal Energy Regulatory Commission

Agency decision

Ask Donna

What actually matters in this document.

Text

Thursday,

March 15, 2007

Part II

Department of

Energy

Federal Energy Regulatory Commission

sroberts on PROD1PC70 with RULES

18 CFR Parts 35 and 37

Preventing Undue Discrimination and

Preference in Transmission Service; Final

Rule

VerDate Aug<31>2005

18:17 Mar 14, 2007

Jkt 211001

PO 00000

Frm 00001

Fmt 4717

Sfmt 4717

E:\FR\FM\15MRR2.SGM

15MRR2

12266

Federal Register / Vol. 72, No. 50 / Thursday, March 15, 2007 / Rules and Regulations

DEPARTMENT OF ENERGY

Federal Energy Regulatory

Commission

18 CFR Parts 35 and 37

[Docket Nos. RM05–17–000 and RM05–25–

000; Order No. 890]

Preventing Undue Discrimination and

Preference in Transmission Service

Issued February 16, 2007.

AGENCY: Federal Energy Regulatory

Commission, DOE.

ACTION: Final rule.

SUMMARY: The Federal Energy

Regulatory Commission is amending the

regulations and the pro forma open

access transmission tariff adopted in

Order Nos. 888 and 889 to ensure that

transmission services are provided on a

basis that is just, reasonable and not

unduly discriminatory or preferential.

The final rule is designed to: Strengthen

the pro forma open-access transmission

tariff, or OATT, to ensure that it

achieves its original purpose of

remedying undue discrimination;

provide greater specificity to reduce

opportunities for undue discrimination

and facilitate the Commission’s

enforcement; and increase transparency

in the rules applicable to planning and

use of the transmission system.

EFFECTIVE DATE: This rule will become

effective May 14, 2007.

FOR FURTHER INFORMATION CONTACT:

Daniel Hedberg (Technical Information),

Office of Energy Markets and Reliability,

Federal Energy Regulatory Commission,

888 First Street, NE., Washington, DC

20426, (202) 502–6243.

W. Mason Emnett (Legal Information),

Office of the General Counsel—Energy

Markets, Federal Energy Regulatory

Commission, 888 First Street, NE.,

Washington, DC 20426, (202) 502–6540.

Kathleen Barrón (Legal Information),

Office of the General Counsel—Energy

Markets, Federal Energy Regulatory

Commission, 888 First Street, NE.,

Washington, DC 20426, (202) 502–6461.

SUPPLEMENTARY INFORMATION:

Paragraph

Nos.

sroberts on PROD1PC70 with RULES

Table of Contents

I. Introduction ...........................................................................................................................................................................................

II. Background ...........................................................................................................................................................................................

A. Historical Antecedent ..................................................................................................................................................................

B. Order No. 888 and Subsequent Reforms .....................................................................................................................................

C. EPAct 2005 and Recent Developments .......................................................................................................................................

III. Need for Reform of Order No. 888 ....................................................................................................................................................

A. Opportunities for Undue Discrimination Continue to Exist .....................................................................................................

B. Lack of Transparency Undermines Confidence in Open Access and Impedes Enforcement of Open Access Requirements

C. Congestion and Inadequate Infrastructure Development Impede Customers’ Use of the Grid ...............................................

D. A Consistent Method of Measuring ATC Is Needed ..................................................................................................................

E. Discriminatory Pricing of Imbalances ..........................................................................................................................................

F. Redispatch/Conditional Firm .......................................................................................................................................................

G. EPAct 2005 Emphasized Certain Policies and Priorities for the Commission .........................................................................

IV. Summary, Scope and Applicability of the Final Rule .....................................................................................................................

A. Summary of Reforms ....................................................................................................................................................................

B. Core Elements of Order No. 888 That Are Retained ..................................................................................................................

1. Federal/State Jurisdiction ......................................................................................................................................................

2. Native Load Protection ..........................................................................................................................................................

3. The Types of Transmission Services Offered ......................................................................................................................

4. Functional Unbundling .........................................................................................................................................................

C. Applicability of the Final Rule ....................................................................................................................................................

1. Non-ISO/RTO Public Utility Transmission Providers .........................................................................................................

2. ISO and RTO Public Utility Transmission Providers and Transmission Owner Members of ISOs and RTOs ...............

3. Non-Public Utility Transmission Providers/Reciprocity .....................................................................................................

V. Reforms of the OATT ..........................................................................................................................................................................

A. Consistency and Transparency of ATC Calculations .................................................................................................................

B. Coordinated, Open and Transparent Planning ...........................................................................................................................

C. Transmission Pricing ....................................................................................................................................................................

1. General ....................................................................................................................................................................................

2. Energy and Generation Imbalances .......................................................................................................................................

3. Credits for Network Customers .............................................................................................................................................

4. Capacity Reassignment ..........................................................................................................................................................

5. ‘‘Operational’’ Penalties .........................................................................................................................................................

a. Unreserved Use Penalties ...............................................................................................................................................

b. Distribution of Operational Penalties ............................................................................................................................

c. Applicability of Operational Penalties Proposal to RTOs and Other Independent or Non-Profit Entities ...............

6. ‘‘Higher of’’ Pricing Policy ....................................................................................................................................................

7. Other Ancillary Services .......................................................................................................................................................

D. Non-Rate Terms and Conditions .................................................................................................................................................

1. Modifications to Long-Term Firm Point-to-Point Service ...................................................................................................

a. Planning Redispatch and Conditional Firm Options ...................................................................................................

b. Proposals for Transparent Redispatch ...........................................................................................................................

c. Other Requested Service Modifications ........................................................................................................................

2. Hourly Firm Service ..............................................................................................................................................................

3. Rollover Rights .......................................................................................................................................................................

4. Modification of Receipt or Delivery Points ..........................................................................................................................

5. Acquisition of Transmission Service ....................................................................................................................................

a. Processing of Service Requests ......................................................................................................................................

b. Reservation Priority ........................................................................................................................................................

6. Designation of Network Resources .......................................................................................................................................

a. Qualification as a Network Resource .............................................................................................................................

VerDate Aug<31>2005

18:17 Mar 14, 2007

Jkt 211001

PO 00000

Frm 00002

Fmt 4701

Sfmt 4700

E:\FR\FM\15MRR2.SGM

15MRR2

1

9

9

14

22

26

26

44

52

62

70

73

79

82

83

91

92

95

110

117

124

124

143

162

193

193

418

603

603

627

729

778

826

826

850

866

870

886

901

901

901

1095

1165

1177

1214

1268

1296

1296

1394

1432

1432

Federal Register / Vol. 72, No. 50 / Thursday, March 15, 2007 / Rules and Regulations

Paragraph

Nos.

Table of Contents

b. Documentation for Network Resources .........................................................................................................................

c. Undesignation of Network Resources ............................................................................................................................

7. Clarifications Related to Network Service ............................................................................................................................

a. Secondary Network Service ...........................................................................................................................................

b. Behind the Meter Generation .........................................................................................................................................

8. Transmission Curtailments ....................................................................................................................................................

9. Standardization of Rules and Practices ................................................................................................................................

a. Business Practices ...........................................................................................................................................................

b. Liability and Indemnification ........................................................................................................................................

10. OATT Definitions ................................................................................................................................................................

E. Enforcement ..................................................................................................................................................................................

1. General Policy ........................................................................................................................................................................

2. Civil Penalties ........................................................................................................................................................................

VI. Information Collection Statement ......................................................................................................................................................

VII. Environmental Analysis ....................................................................................................................................................................

VIII. Regulatory Flexibility Act Analysis ................................................................................................................................................

IX. Document Availability .......................................................................................................................................................................

X. Effective Date and Congressional Notification ...................................................................................................................................

Appendix A: Summary of Compliance Filing Requirements

Appendix B: Commenting Party Acronyms

Appendix C: Pro Forma Open Access Transmission Tariff

Before Commissioners: Joseph T.

Kelliher, Chairman; Suedeen G.

Kelly, Marc Spitzer, Philip D.

Moeller, and Jon Wellinghoff.

I. Introduction

sroberts on PROD1PC70 with RULES

1. This Final Rule addresses and

remedies opportunities for undue

discrimination under the pro forma

Open Access Transmission Tariff

(OATT) adopted in 1996 by Order No.

888.1 This landmark rulemaking

fostered greater competition in

wholesale power markets by reducing

barriers to entry in the provision of

transmission service. In the ten years

since Order No. 888, however, the

Commission has found that the OATT

contains flaws that undermine realizing

its core objective of remedying undue

discrimination. In the Notice of

Proposed Rulemaking (NOPR) issued on

May 19, 2006, the Commission

proposed to remedy those flaws.2 After

receiving approximately 6,500 pages of

comments from close to 300 parties, we

now take final action. We highlight

below the most critical reforms being

adopted today.

1 Promoting Wholesale Competition Through

Open Access Non-discriminatory Transmission

Services by Public Utilities; Recovery of Stranded

Costs by Public Utilities and Transmitting Utilities,

Order No. 888, 61 FR 21540 (May 10, 1996), FERC

Stats. & Regs. § 31,036 (1996), order on reh’g, Order

No. 888–A, 62 FR 12274 (Mar. 14, 1997), FERC

Stats. & Regs. § 31,048 (1997), order on reh’g, Order

No. 888–B, 81 FERC § 61,248 (1997), order on reh’g,

Order No. 888–C, 82 FERC § 61,046 (1998), aff’d in

relevant part sub nom. Transmission Access Policy

Study Group v. FERC, 225 F.3d 667 (D.C. Cir. 2000)

(TAPS v. FERC), aff’d sub nom. New York v. FERC,

535 U.S. 1 (2002).

2 Preventing Undue Discrimination and

Preference in Transmission Service, Notice of

Proposed Rulemaking, 71 FR 32,636 (Jun. 6, 2006),

FERC Stats. & Regs. § 32,603 (2006).

VerDate Aug<31>2005

18:17 Mar 14, 2007

Jkt 211001

2. First, the Final Rule will increase

nondiscriminatory access to the grid by

eliminating the wide discretion that

transmission providers currently have

in calculating available transfer

capability (ATC).3 The calculation of

ATC is one of the most critical functions

under the OATT because it determines

whether transmission customers can

access alternative power supplies.

Despite this, the existing OATT does not

prescribe how ATC should be calculated

because the Commission sought to rely

on voluntary efforts by the industry to

develop consistent methods of ATC

calculation. This voluntary industry

effort has not proven successful. The

Commission therefore acts today to

require public utilities, working through

the North American Electric Reliability

Corporation (NERC), to develop

consistent methodologies for ATC

calculation and to publish those

methodologies to increase transparency.

This important reform will eliminate the

wide discretion that exists today in

calculating ATC and ensure that

customers are treated fairly in seeking

alternative power supplies.

3. Second, the Final Rule will

increase the ability of customers to

access new generating resources and

promote efficient utilization of

transmission by requiring an open,

transparent, and coordinated

transmission planning process.

Transmission planning is a critical

3 The Commission used the term ‘‘Available

Transmission Capability’’ in Order No. 888 to

describe the amount of additional capability

available in the transmission network to

accommodate additional requests for transmission

services. To be consistent with the term generally

accepted throughout the industry, the Commission

revises the pro forma OATT to adopt the term

‘‘Available Transfer Capability.’’

PO 00000

Frm 00003

Fmt 4701

Sfmt 4700

12267

1507

1534

1592

1592

1614

1620

1633

1633

1662

1678

1714

1715

1724

1752

1758

1759

1760

1763

function under the pro forma OATT

because it is the means by which

customers consider and access new

sources of energy and have an

opportunity to explore the feasibility of

non-transmission alternatives. Despite

this, the existing pro forma OATT

provides limited guidance regarding

how transmission customers are treated

in the planning process and provides

them very little information on how

transmission plans are developed. These

deficiencies are serious, given the

substantial need for new infrastructure

in this Nation.4 We act today to remedy

these deficiencies by requiring

transmission providers to open their

transmission planning process to

customers, coordinate with customers

regarding future system plans, and share

necessary planning information with

customers.

4. Third, the Final Rule will also

increase the efficient utilization of

4 Congress placed special emphasis on the

development of transmission infrastructure,

including the consideration of advanced

transmission technologies, in the Energy Policy Act

of 2005 (EPAct 2005). See Pub. L. 109–58, 119 Stat.

594 (to be codified in scattered titles of the U.S.C.).

The Commission has taken steps to implement that

goal in numerous contexts, including recent

rulemaking proceedings that address the promotion

of transmission investment through pricing reform

and the siting of certain transmission facilities. See

Promoting Transmission Investment through

Pricing Reform, Order No. 679, 71 FR 43294 (Jul.

31, 2006), FERC Stats. & Regs. § 31,222 (2006), order

on reh’g, Order No. 679–A, 72 FR 1152 (Jan. 10,

2007), FERC Stats. & Regs. § 31,236 (2007), reh’g

pending; Regulations for Filing Applications for

Permits to Site Interstate Electric Transmission

Facilities, Order No. 689, 71 FR 69440 (Dec. 1,

2006), FERC Stats. & Regs. § 31,234 (2006), reh’g

pending. As discussed herein, several actions taken

in this Final Rule also relate to the need for

investments in transmission infrastructure and are

consistent with the Commission’s responsibilities

under EPAct 2005.

E:\FR\FM\15MRR2.SGM

15MRR2

sroberts on PROD1PC70 with RULES

12268

Federal Register / Vol. 72, No. 50 / Thursday, March 15, 2007 / Rules and Regulations

transmission by eliminating artificial

barriers to use of the grid. The existing

pro forma OATT allows a transmission

provider to deny a request for long-term

point-to-point service if the request

cannot be satisfied in only one hour of

the requested term. This practice

discourages the efficient use of the

existing grid and precludes access to

alternative power supplies. We reform

this practice by requiring that a

conditional firm option be offered to

customers seeking long-term point-topoint service, i.e., conditional firm

service. We also modify the redispatch

obligations of transmission providers to

increase the efficient utilization of the

grid, while also ensuring that reliability

to native load customers is maintained.

5. Fourth, by adopting these and other

reforms, the Final Rule facilitates the

use of clean energy resources such as

wind power. Conditional firm service is

particularly important to wind resources

that can provide significant economic

and environmental value even if

curtailed under limited circumstances.

Open and coordinated transmission

planning will enhance the ability of

customers to access clean energy

resources as part of their future resource

portfolio. The Final Rule also benefits

clean energy resources by reforming

energy and generator imbalance charges.

These reforms are particularly important

to intermittent resources such as wind

power because these resources have

limited ability to control their output

and, hence, must be assured that

imbalance charges are no more than

required to provide appropriate

incentives for prudent behavior.

6. Fifth, the Final Rule will strengthen

compliance and enforcement efforts. We

are increasing the transparency of pro

forma OATT administration, thereby

increasing the ability of customers and

our Office of Enforcement to detect

undue discrimination. We are adopting

operational penalties for clear violations

of an OATT, thereby enhancing

compliance while also reducing the

burdens on our Office of Enforcement.

We are also increasing the clarity of

many other OATT requirements,

thereby facilitating compliance by

transmission providers with our

regulations. This Final Rule thus reflects

the close integration of our Office of

Enforcement into policy development at

the Commission. Several of the reforms

we adopt today are informed by our

experience with OATT administration

through oversight, audits, and

investigations performed by the Office

of Enforcement.

7. Finally, we modify and improve

several provisions of the pro forma

OATT using our experience over the

VerDate Aug<31>2005

18:17 Mar 14, 2007

Jkt 211001

past ten years and clarify others that

have proven ambiguous. For example,

we reform our rollover rights policy to

ensure that the rights and obligations of

rollover customers are consistent with

the resulting obligations of transmission

providers to plan and upgrade the

system to accommodate rollovers. We

remove the price cap on reassigned

capacity because it is not necessary to

remedy market power and doing so will

otherwise increase the efficient use of

existing capacity. We increase the

efficient use of existing capacity by

providing a priority to certain ‘‘preconfirmed’’ requests for service. We

increase certainty by providing greater

clarity regarding the wholesale contracts

that qualify as network resources. We

also adopt numerous clarifications that

should assist transmission providers

and customers in implementing and

using the pro forma OATT

8. Our actions in this proceeding have

been informed to a great extent by the

comments received in response to our

notices of inquiry in the abovecaptioned dockets and the subsequent

NOPR.5 We appreciate the time and

thoughtfulness of all sectors of the

industry in preparing comments. We

have found them very informative and

useful in reaching our decisions in this

Final Rule.

II. Background

A. Historical Antecedent

9. In the NOPR, the Commission

explained the historical background that

led up to the issuance of Order No. 888,

and the initiation of this rulemaking

proceeding. We repeat that history here

to place in context the actions we take

today.

10. In the first few decades after

enactment of the Federal Power Act

(FPA) in 1935, the industry was

characterized mostly by self-sufficient,

vertically integrated electric utilities, in

which generation, transmission, and

distribution facilities were owned by a

single entity and sold as part of a

bundled service to wholesale and retail

customers. Most electric utilities built

their own power plants and

transmission systems, entered into

interconnection and coordination

arrangements with neighboring utilities,

and entered into long-term contracts to

make wholesale requirements sales

(bundled sales of generation and

transmission) to municipal, cooperative,

5 Preventing Undue Discrimination and

Preference in Transmission Services, Notice of

Inquiry, 112 FERC ¶ 61,299 (2005) (NOI);

Information Requirements for Available Transfer

Capability, Notice of Inquiry, 111 FERC ¶ 61,274

(2005) (ATC NOI).

PO 00000

Frm 00004

Fmt 4701

Sfmt 4700

and investor-owned utilities connected

to each utility’s transmission system.

Each system covered a limited service

area, which was defined by the retail

franchise decisions of State regulatory

agencies. This structure of separate

systems arose naturally primarily due to

cost and the technological limitations

on the distance over which electricity

could be transmitted.

11. A number of statutory, economic,

and technological developments in the

1970s led to an increase in coordinated

operations and competition. Among

those was the passage of the Public

Utility Regulatory Policies Act of 1978

(PURPA),6 which was designed to

lessen dependence on foreign fossil

fuels by encouraging the development of

alternative generation sources and

imposing a mandatory purchase

obligation on utilities for generation

from such sources. PURPA also enabled

the Commission to order wheeling of

electricity under limited

circumstances.7 The rapid expansion

and performance of the independent

power industry following the enactment

of PURPA demonstrated that traditional,

vertically integrated public utilities

need not be the only sources of reliable

power. During this period, the profile of

generation investment began to change,

and a market for non-traditional power

supply beyond the purchases required

by PURPA began to emerge. The

economic and technological changes in

the transmission and generation sectors

helped encourage many new entrants in

the generating markets that could sell

electric energy profitably with smaller

scale technology at a lower price than

many utilities selling from their existing

generation facilities at rates reflecting

cost. However, it became increasingly

clear that the potential consumer

benefits that could be derived from

these technological advances could be

realized only if more efficient generating

plants could obtain access to the

regional transmission grids. Because

many traditional vertically integrated

utilities still did not provide open

access to third parties and favored their

own generation if and when they

6 Pub. L. 95–617, 92 Stat. 3117 (1978) (codified

in U.S.C. titles 15, 16, 26, 30, 42, and 43).

7 Section 211 of the FPA, 16 U.S.C. 824j. In earlier

years, a few customers were able to obtain access

as a result of litigation, beginning with the U.S.

Supreme Court’s decision in Otter Tail Power

Company v. United States, 410 U.S. 366 (1973).

Additionally, some customers gained access by

virtue of Nuclear Regulatory Commission license

conditions and voluntary preference power

transmission arrangements associated with Federal

power marketing agencies. See, e.g., Consumers

Power Co., 6 NRC 887, 1036–44 (1977); Toledo

Edison Co., 10 NRC 265, 327–34 (1979); Florida

Municipal Power Agency v. Florida Power and Light

Co., 839 F. Supp. 1563 (M.D. Fla. 1993).

E:\FR\FM\15MRR2.SGM

15MRR2

Federal Register / Vol. 72, No. 50 / Thursday, March 15, 2007 / Rules and Regulations

sroberts on PROD1PC70 with RULES

provided transmission access to third

parties, access to cheaper, more efficient

generation sources remained limited.

12. The Commission encouraged the

development of independent power

producers (IPPs), as well as emerging

power marketers, by authorizing marketbased rates for their power sales on a

case-by-case basis, and by encouraging

more widely available transmission

access on a case-by-case basis. Marketbased rates helped to develop

competitive bulk power markets by

allowing generating utilities to move

more quickly and flexibly to take

advantage of short-term or even longterm market opportunities than those

utilities operating under traditional

cost-of-service tariffs. In approving these

market-based rates, the Commission

required that the seller and its affiliates

lack market power or mitigate any

market power that they may have had.8

The major concern of the Commission

was whether the seller or its affiliates

could limit competition and thereby

drive up prices. A key inquiry became

whether the seller or its affiliates owned

or controlled transmission facilities in

the relevant service area and therefore,

by denying access or imposing

discriminatory terms or conditions on

transmission service, could foreclose

other generators from competing.

Beginning in the late 1980s, in order to

mitigate their market power to meet the

Commission’s conditions, public

utilities seeking Commission

authorization for blanket approval of

market-based rates for generation

services under section 205 of the FPA

filed ‘‘open access’’ transmission tariffs

of general applicability.9 The

Commission also approved proposed

mergers under section 203 of the FPA

on the condition that the merging

companies remedy anticompetitive

effects potentially caused by the merger

by filing ‘‘open access’’ tariffs. The early

tariffs submitted in market-based rate

proceedings under section 205 and

merger proceedings under section 203

did not, however, provide access to the

transmission system that was

comparable to the service the

transmission providers used for their

own purposes. Rather, they typically

made available only point-to-point

transmission service, i.e., service from a

single point of receipt to a single point

8 See, e.g., Dartmouth Power Associates Limited

Partnership, 53 FERC ¶ 61,117 (1990);

Commonwealth Atlantic Limited Partnership, 51

FERC ¶ 61,368 (1990); Doswell Limited Partnership,

50 FERC ¶ 61,251 (1990); Citizens Power & Light

Co., 48 FERC ¶ 61,210 (1989); Ocean State Power,

44 FERC ¶ 61,261 (1988); and Orange and Rockland

Utilities, Inc., 42 FERC ¶ 61,012 (1988).

9 See Order No. 888 at 31,644 n.52.

VerDate Aug<31>2005

18:17 Mar 14, 2007

Jkt 211001

12269

B. Order No. 888 and Subsequent

Reforms

14. In April 1996, as part of its

statutory obligation under sections 205

and 206 of the FPA to remedy undue

discrimination, the Commission

adopted Order No. 888 prohibiting

public utilities from using their

monopoly power over transmission to

unduly discriminate against others. In

that order, the Commission required all

public utilities that own, control or

operate facilities used for transmitting

electric energy in interstate commerce to

file open access non-discriminatory

transmission tariffs that contained

minimum terms and conditions of nondiscriminatory service. It also obligated

such public utilities to ‘‘functionally

unbundle’’ their generation and

transmission services. This meant

public utilities had to take transmission

service (including ancillary services) for

their own new wholesale sales and

purchases of electric energy under the

open access tariffs, and to separately

state their rates for wholesale

generation, transmission and ancillary

services.13 Each public utility was

required to file the pro forma OATT

included in Order No. 888 without any

deviation (except a limited number of

terms and conditions that reflect

regional practices).14 After the

effectiveness of their OATTs, public

utilities were allowed to file, pursuant

to section 205 of the FPA, deviations

that were consistent with or superior to

the pro forma OATT’s terms and

conditions. Because certain owners,

controllers or operators of interstate

transmission facilities were not subject

to the Commission’s jurisdiction under

sections 205 and 206 and thus were not

subject to Order No. 888, the

Commission adopted a reciprocity

provision in the pro forma OATT that

conditions the use by a non-public

utility of a public utility’s open access

services on an agreement to offer nondiscriminatory transmission services in

return.

15. In addition to imposing the

functional unbundling requirement, the

Commission also encouraged broader

reforms through the formation of

independent system operators (ISOs).

The Commission stated that ISOs can

provide significant benefits such as

enhancing regional efficiencies and

further remedying undue

discrimination.15 While the

Commission declined to mandate ISOs,

it set forth eleven principles for

assessing ISO proposals submitted to

the Commission.16

16. Order No. 888 also clarified the

Commission’s interpretation of the

Federal and State jurisdictional

boundaries over transmission and local

distribution. While Order No. 888

reaffirmed that the Commission has

exclusive jurisdiction over the rates,

10 Pub. L. 102–486, 106 Stat. 2776 (1992)

(codified at, among other places, 15 U.S.C. 79z–5a

and 16 U.S.C. 796 (22–25), 824j–l).

11 15 U.S.C. 79a, repealed by EPAct 2005 sec.

1263; see Repeal of the Public Utility Holding

Company Act of 1935 and Enactment of the Public

Utility Holding Company Act of 2005, Order No.

667, 70 FR 75592 (Dec. 20, 2005), FERC Stats. &

Regs. ¶ 31,197 (2005), order on reh’g, Order No.

667–A, 71 FR 28446 (May 16, 2006), FERC Stats.

& Regs. ¶ 31,213 (2006), order on reh’g, Order No.

667–B, 71 FERC 42750 (Jul. 28, 2006), FERC Stats.

& Regs. ¶ 31,224 (2006), reh’g pending.

12 16 U.S.C. 824j (authorizing the Commission to

require transmission utilities to provide service in

certain circumstances); 16 U.S.C. 824k (establishing

rates for service provided pursuant to an order

under section 211).

13 This is known as ‘‘functional unbundling’’

because the transmission element of a wholesale

sale is separated or unbundled from the generation

element of that sale, although the public utility may

provide both functions. See infra section IV.B.4 of

this Final Rule.

14 See Order No. 888 at 31,769–70 (noting that the

pro forma OATT expressly identified certain nonrate terms and conditions, such as the time

deadlines for determining available transfer

capability in section 18.4 or scheduling changes in

sections 13.8 and 14.6, that may be modified to

account for regional practices if such practices are

reasonable, generally accepted in the region, and

consistently adhered to by the transmission

provider).

15 Order No. 888 at 31,655.

16 Id. at 31,730–32.

of delivery. As these early tariffs were

offered only by transmission providers

that volunteered to provide service to

third parties, they resulted in a

patchwork of open access that was not

sufficient to facilitate wholesale

generation markets.

13. In response to the competitive

developments following PURPA, and

the fact that limited transmission access

and significant regulatory barriers

continued to constrain the development

of generation by independent power

producers, Congress enacted Title VII of

the Energy Policy Act of 1992 (EPAct

1992).10 EPAct 1992 reduced regulatory

barriers to entry by creating a class of

‘‘Exempt Wholesale Generators’’ that

were exempt from the requirements of

the Public Utility Holding Company Act

of 1935.11 EPAct 1992 also expanded

the Commission’s authority to approve

applications for transmission services

under sections 211 and 212 of the

FPA.12 Though the Commission

aggressively implemented expanded

section 211, it ultimately concluded that

the procedural limitations in section

211 thwarted the Commission’s ability

to effectively eliminate undue

discrimination in the provision of

transmission service.

PO 00000

Frm 00005

Fmt 4701

Sfmt 4700

E:\FR\FM\15MRR2.SGM

15MRR2

12270

Federal Register / Vol. 72, No. 50 / Thursday, March 15, 2007 / Rules and Regulations

terms, and conditions of unbundled

retail transmission in interstate

commerce by public utilities, it

nevertheless recognized the legitimate

concerns of State regulatory authorities

regarding the transmission component

of bundled retail sales. The Commission

therefore declined to extend its

unbundling requirement to the

transmission component of bundled

retail sales. On appeal, the U.S.

Supreme Court affirmed this element of

Order No. 888, finding that the

Commission made a statutorily

permissible choice.17

17. The same day it issued Order No.

888, the Commission issued a

companion order, Order No. 889,18

addressing the separation of vertically

integrated utilities’ transmission and

merchant functions, the information

transmission providers were required to

make public, and the electronic means

they were required to use to do so.

Order No. 889 imposed Standards of

Conduct governing the separation of,

and communications between, the

utility’s transmission and wholesale

power functions, to prevent the utility

from giving its merchant arm

preferential access to transmission

information. All public utilities that

owned, controlled or operated facilities

used in the transmission of electric

energy in interstate commerce were

required to create or participate in an

Open Access Same-Time Information

System (OASIS) that was to provide

existing and potential transmission

customers the same access to

transmission information.

18. Among the information public

utilities were required to post on their

OASIS was the transmission provider’s

calculation of ATC. Though the

Commission acknowledged that beforethe-fact measurement of the availability

of transmission service is ‘‘difficult,’’ it

concluded that it was important to give

potential transmission customers ‘‘an

easy-to-understand indicator of service

availability.’’ 19 Because formal methods

did not then exist to calculate ATC and

total transfer capability (TTC), the

Commission encouraged industry efforts

to develop consistent methods for

calculating ATC and TTC.20 Order No.

889 ultimately required transmission

providers to base their calculations on

sroberts on PROD1PC70 with RULES

17 New York v. FERC, 535 U.S. 1 (2002).

18 Open Access Same-Time Information System

(Formerly Real-Time Information Networks) and

Standards of Conduct, Order No. 889, 61 FR 21737

(May 10, 1996), FERC Stats. & Regs. ¶ 31,035 (1996),

order on reh’g, Order No. 889–A, FERC Stats. &

Regs. ¶ 31,049 (1997), order on reh’g, Order No.

889–B, 81 FERC ¶ 61,253 (1997).

19 Order No. 889 at 31,605.

20 Id. at 31,607.

VerDate Aug<31>2005

18:17 Mar 14, 2007

Jkt 211001

‘‘current industry practices, standards

and criteria’’ and to describe their

methodology in their tariffs.21 The

Commission noted that the requirement

that transmission providers purchase

only ATC that is posted as available

‘‘should create an adequate incentive for

them to calculate ATC and TTC as

accurately and as uniformly as

possible.’’ 22

19. The electric industry continued to

undergo economic and regulatory

changes in the years following the

issuance of Order No. 888. Retail access

was adopted by approximately 25 states

in the late 1990s.23 This State

restructuring activity spurred significant

changes at the wholesale level as well

by encouraging or requiring the

divestiture of generation plants by

traditional electric utilities and the

development of ISOs that could manage

short-term energy markets necessary to

support retail access. At the same time,

there was a significant increase in the

number of mergers between traditional

electric utilities and between electric

utilities and gas pipeline companies,

and large increases in the number of

power marketers and independent

generation facility developers entering

the marketplace. Trade in bulk power

markets increased significantly and the

Nation’s transmission grid was used

more heavily and in new ways as

customers took advantage of the pro

forma OATT and purchased power from

competitive sellers.

20. In the wake of these changes, in

December 1999, the Commission

adopted Order No. 2000.24 That

rulemaking recognized that Order No.

888 set the foundation upon which

competitive electric markets could

develop, but did not eliminate the

potential to engage in undue

discrimination and preference in the

provision of transmission service.25 The

rulemaking also recognized that Order

No. 888 did not address the regional

nature of the grid, including the

treatment of parallel flows, pancaked

rates, and congestion management.

Thus, the Commission encouraged the

creation of RTOs to address important

operational and reliability issues and

21 Id.

22 Id.

23 See Energy Information Administration, Retail

Unbundling—U.S. Summary (2005), http://www.

eia.doe.gov/oil_gas/natural_gas/restructure/state/

us.html.

24 Regional Transmission Organizations, Order

No. 2000, 65 FR 809 (Jan. 6, 2000), FERC Stats. &

Regs. ¶ 31,089 (1999), order on reh’g, Order No.

2000–A, 65 FR 12088 (Mar. 8, 2000), FERC Stats.

& Regs. ¶ 31,092 (2000), aff’d sub nom. Public

Utility District No. 1 of Snohomish County,

Washington v. FERC, 272 F.3d 607 (D.C. Cir. 2001).

25 Order No. 2000 at 31,015.

PO 00000

Frm 00006

Fmt 4701

Sfmt 4700

eliminate any residual discrimination in

transmission services that can occur

when the operation of the transmission

system remains in the control of a

vertically integrated utility. The

Commission found that RTOs would

increase the efficiency of wholesale

markets by eliminating pancaked rates,

internalizing parallel flow, managing

congestion efficiently, and operating

markets for energy, capacity and

ancillary services. The Commission

established an open, collaborative

process that relied on voluntary regional

participation to design RTOs tailored to

the specific needs of each region. The

Commission noted, however, that ‘‘[i]f

the industry fails to form RTOs under

this approach, the Commission will

reconsider what further regulatory steps

are in the public interest.’’26

21. Following Order No. 2000, RTOs

were approved in several regions of the

country including the Northeast (PJM;

ISO New England),27 the Midwest

(MISO) and the South (SPP). In most

cases, RTOs have assumed

responsibility for calculating ATC

across the footprint of the RTO, as well

as the planning and expansion of the

transmission grid, at least for facilities

necessary for maintaining system

reliability. However, large areas of the

Nation have not developed RTOs using

the voluntary structure adopted by the

Commission in Order No. 2000.

Moreover, transmission customers have

complained that even in RTO markets

there are instances when comparable

transmission service is not provided,

particularly in the area of transmission

planning.

C. EPAct 2005 and Recent

Developments

22. Enacted on August 8, 2005, EPAct

added a number of new authorities and

priorities for the Commission and

emphasized certain of its existing

obligations. Among other things, EPAct

2005 recognized the importance of

adequate transmission infrastructure

development and its role in facilitating

the development of competitive

wholesale markets. The Congressional

directives in EPAct 2005 are intended to

reverse the decline in transmission

infrastructure investment. For example,

Congress required the Commission to

adopt a rule establishing incentive

ratemaking for transmission

infrastructure to help promote reliability

and reduce congestion.28 Congress also

26 Id. at 30,993.

27 A list of commenter acronyms can be found in

Appendix B.

28 EPAct 2005 sec. 1241 (to be codified at section

219 of the FPA, 16 U.S.C. 824s).

E:\FR\FM\15MRR2.SGM

15MRR2

Federal Register / Vol. 72, No. 50 / Thursday, March 15, 2007 / Rules and Regulations

sroberts on PROD1PC70 with RULES

directed the Commission to encourage

the deployment of advanced

technologies.29 Congress further

directed the Commission to ‘‘exercise its

authority’’ under EPAct 2005 ‘‘in a

manner that facilitates the planning and

expansion of transmission facilities to

meet the reasonable needs of loadserving entities.’’30 Congress also gave

the Commission certain ‘‘backstop’’

transmission siting authority, and

authorized the creation of interstate

compacts establishing transmission

siting agencies.31 EPAct 2005 also

authorized the Commission to require

unregulated transmitting utilities

(except for certain small entities) to

provide access to their transmission

facilities on a comparable basis.32

Congress further ordered the

Department of Energy (DOE) to study

the benefits of economic dispatch and

required the Commission to convene

regional joint boards to develop a report

to Congress containing

recommendations for the use of security

constrained economic dispatch within

each region.33 Congress also directed the

Commission to facilitate price

transparency in markets for the sale and

transmission of electric energy in

interstate commerce, having due regard

for the public interest, the integrity of

those markets, fair competition, and the

protection of consumers, and it

authorized the Commission to prescribe

rules to provide for the dissemination of

information about the availability and

price of wholesale electric energy and

transmission service.34 Finally,

Congress emphasized compliance with

the Commission’s regulations, adopting

and increasing the civil and criminal

penalties for violations of Commissionadministered statutes and regulations.35

29 EPAct 2005 sec. 1223 (to be codified at 42

U.S.C. 16422). Indeed, Congress provided specific

guidance as to the types of advanced technologies

that should be encouraged in infrastructure

improvements to include, among others, optimized

transmission line configurations (including

multiple phased transmission lines), controllable

load, distributed generation (including PV, fuel

cells, and microturbines), and enhanced power

device monitoring. Id.

30 EPAct 2005 sec. 1233(a) (to be codified at

section 217(b)(4) of the FPA, 16 U.S.C. 824q).

31 EPAct 2005 sec. 1221(a) (to be codified at

section 216 of the FPA, 16 U.S.C. 824p).

32 EPAct 2005 sec. 1231 (to be codified at section

211A of the FPA, 16 U.S.C. 824j–1)

33 EPAct 2005 sec. 1234 (to be codified at 42

U.S.C. 16432); EPAct 2005 sec. 1298 (to be codified

at section 223 of the FPA, 16 U.S.C. 824w). EPAct

2005 sec. 1234(b) defined economic dispatch as

‘‘the operation of generation facilities to produce

energy at the lowest cost to reliably serve

consumers, recognizing any operational limits of

generation and transmission facilities.’’

34 EPAct 2005 sec. 1281 (to be codified at section

220 of the FPA, 16 U.S.C. 824t).

35 EPAct 2005 sec. 1284(d) (to be codified at

section 316 of the FPA, 16 U.S.C. 825o); EPAct 2005

VerDate Aug<31>2005

18:17 Mar 14, 2007

Jkt 211001

23. Recognizing the need for reform of

Order No. 888 in light of the

Commission’s continuing concern

regarding whether the pro forma OATT

adequately remedies undue

discrimination, the Commission issued

an NOI on September 16, 2005 36

seeking comments on appropriate

reforms of the Order No. 888 pro forma

OATT. In the NOI, the Commission

expressed its preliminary view that

reforms to the pro forma OATT and

public utilities’ OATTs are necessary to

avoid undue discrimination or

preference in the provision of

transmission service. The NOI sought

comments on how best to accomplish

the Commission’s goals, specifically

with respect to enhancements that are

needed to (1) Remedy any unduly

discriminatory or preferential

application of the pro forma OATT or

(2) improve the clarity of the Order No.

888 pro forma OATT and the individual

public utility tariffs in order to more

readily identify violations and facilitate

compliance.

24. The Commission received over

4,000 pages of initial and reply

comments on the NOI. Based on these

comments, the comments submitted in

response to the ATC NOI,37 our

experience in implementing Order No.

888, and the changes in the industry

since we adopted it, the Commission

proposed to reform the pro forma OATT

in a number of ways. The Commission

issued the NOPR on May 19, 2006

proposing a number of reforms aimed at

remedying undue discrimination in the

provision of open access transmission

service and improving the clarity of the

pro forma OATT and the individual

tariffs of transmission providers in order

to more readily identify violations and

facilitate compliance. The Commission

received over 5,700 pages of initial and

reply comments in response. In

response to comments on the particular

issue of redispatch and conditional firm

service (discussed in more detail

below), the Commission issued a Notice

of Request for Supplemental Comments

on November 15, 2006,38 that resulted

in receipt of an additional 750 pages of

comments.

25. Based on this voluminous record,

the Commission concludes that reform

of the pro forma OATT and associated

amendments to its regulations are

necessary to reduce the potential for

undue discrimination and provide

sec. 1284(e) (to be codified at section 316A of the

FPA, 16 U.S.C. 825o–1).

36 See supra note 5.

37 Id.

38 Preventing Undue Discrimination and

Preference in Transmission Service, 117 FERC

¶ 61,185 (2006).

PO 00000

Frm 00007

Fmt 4701

Sfmt 4700

12271

clarity in the obligations of transmission

providers and customers alike. We turn

next to a more complete explanation of

this need for reform.

III. Need for Reform of Order No. 888

A. Opportunities for Undue

Discrimination Continue To Exist

26. Although Order No. 888 has been

successful in many important respects,

the need for reform of the Order No. 888

pro forma OATT has been apparent for

some time. In 1999, the Commission

held, in adopting Order No. 2000, that

the pro forma OATT could not fully

remedy undue discrimination because

transmission providers retained both the

incentive and the ability to discriminate

against third parties, particularly in

areas where the pro forma OATT left the

transmission provider with significant

discretion.39 The Commission made a

similar finding in Order No. 2003,40

holding that opportunities for undue

discrimination continue to exist in areas

where the pro forma OATT leaves

transmission providers with substantial

discretion.41 The NOPR reaffirmed these

findings, preliminarily concluding that

opportunities for undue discrimination

continue to exist in the provision of

open access transmission service. The

Commission therefore proposed a

number of reforms to the pro forma

OATT to address the opportunities and

incentives transmission providers have

to unduly discriminate.

Comments

27. Many commenters agree with the

Commission that reforms to the pro

forma OATT are needed because there

continue to be both the opportunity and

incentive for transmission providers to

engage in undue discrimination.42

28. Several commenters offered

examples of their experiences with

transmission providers, where they

believe transmission providers have

acted in an unduly discriminatory

39 Order No. 2000 at 31,105.

40 See Standardization of Generator

Interconnection Agreements and Procedures, Order

No. 2003, 68 FR 49845 (Aug. 19, 2003), FERC Stats.

& Regs. ¶ 31,146 at P 11–12 (2003), order on reh’g,

Order No. 2003–A, 69 FR 15932 (Mar. 26, 2004),

FERC Stats. & Regs. ¶ 31,160 (2004), order on reh’g,

Order No. 2003–B, 70 FR 265 (Jan. 4, 2005), FERC

Stats. & Regs. ¶ 31,171 (2004), order on reh’g, Order

No. 2003–C, 70 FR 37,661 (Jun. 30, 2005), FERC

Stats. & Regs. ¶ 31,190 (2005), aff’d sub nom.

National Association of Regulatory Utility

Commissioners v. FERC, No. 04–1148, 2007 U.S.

App. LEXIS 626 (D.C. Cir. Jan. 12, 2007).

41 Order No. 2003 at P 11–12.

42 E.g., APPA, EPSA, East Texas Cooperatives,

Fayetteville, NRG, Occidental, TAPS, TDU Systems,

Williams, Entegra Reply, and NRECA Reply.

E:\FR\FM\15MRR2.SGM

15MRR2

sroberts on PROD1PC70 with RULES

12272

Federal Register / Vol. 72, No. 50 / Thursday, March 15, 2007 / Rules and Regulations

fashion.43 Constellation claims that on

multiple occasions it has been denied a

transmission request when the

transmission provider’s OASIS indicates

that ATC is available, but Constellation

had no effective and timely way to

challenge that determination because of

the ATC ‘‘black box.’’ Constellation

states that given that its needs for

transmission service are often near-term

or immediate—e.g., to facilitate a loadserving obligation or wholesale

transaction that must be consummated

quickly—seeking redress at the

Commission for improperly denied

service generally is not time- or costeffective. Instead, Constellation asserts,

it is often forced to accept the

determination of the transmission

provider that ATC is not available (even

though its OASIS may indicate

otherwise) and seek alternate

transmission paths and/or products to

consummate its transaction.

29. Powerex also describes instances

where a transmission provider has

granted short-term firm point-to-point

transmission service requests to

transmission customers who have been

allowed to remain in the queue, even

when zero ATC is posted, in the hopes

that a transmission provider’s OASIS

site wrongly indicates zero ATC or will

soon be updated. Powerex asserts that

such practices clog the short-term pointto-point transmission queue with

multiple requests and result in

duplicative requests for service that

reflect customers’ attempts to secure

service, rather than the actual quantity

of service needed. Moreover, Powerex

argues, transmission provider discretion

in this area and the lack of transparency

raise customer concerns about

preferential treatment.

30. Occidental claims that it has firsthand experience with a vertically

integrated transmission provider that,

despite having an OATT, appears to

have persistently used its transmission

system to preferentially benefit its

merchant function. Similarly, Williams

alleges that its interests have been

consistently and significantly

compromised by the discretion afforded

transmission providers in the

interpretation of the OATT and the lack

of transparency in requesting,

scheduling and interrupting of

transmission service.

31. Other commenters, however,

argue that the Commission’s proposed

reforms are based on unsupported

allegations of undue discrimination. EEI

maintains that any opportunities to

engage in undue discrimination have

43 See, e.g., Dow, Fayetteville, Occidental, and

Williams.

VerDate Aug<31>2005

18:17 Mar 14, 2007

Jkt 211001

been largely mitigated by current

regulatory policies and changes in the

industry. EEI explains that, unlike the

situation that existed when the

Commission enacted Order No. 888,

much of the country’s transmission

facilities are now under the control of

RTOs and ISOs. In addition, EEI states,

other transmission providers have

transferred (or are in the process of

transferring) the administration of their

OATTs and OASIS functions to

independent transmission service

coordinators. Even among the

transmission providers who have taken

neither of those steps, EEI argues that

the open access requirements of Order

No. 888 and the Standards of Conduct

of Order Nos. 889 and 2004 have largely

eliminated the ability of transmission

providers to engage in undue

discrimination in the provision of

transmission service.44 In addition, EEI

states, the Commission’s expanded civil

penalty authority added to the FPA by

EPAct 2005 gives the Commission a

powerful tool that will further eliminate

any remaining incentive of transmission

providers to engage in undue

discrimination in the provision of

transmission service. Therefore, EEI

asserts, any modifications to the OATT

should be narrowly tailored to address

the perceptions of residual undue

discrimination. To the extent that such

perceptions exist, however, Community

Power Alliance states that, in the

absence of concrete record evidence,

they are just that—perceptions.

32. Although Duke strongly supports,

as a policy matter, OATT reforms that

will eliminate the perception that undue

discrimination is possible and/or likely,

Duke argues that the FPA does not

provide the Commission the authority to

remedy mere ‘‘opportunities’’ to

discriminate. Duke states that, in some

cases, the Commission is attempting to

remedy an opportunity for undue

discrimination that does not exist or is

proposing to impose a remedy that does

not actually remedy the perceived

opportunity. Duke notes, however, that

some OATT terms and conditions are

subject to multiple interpretations and

argues that the Commission can, and

should, justify the OATT reforms

proposed in the NOPR as reforms

needed to provide clarity to existing

policies.

33. With regard to specific allegations

made by commenters, several

transmission providers respond that the

examples given by transmission

customers do not illustrate instances of

undue discrimination. Rather, they

assert, these examples demonstrate the

44 See also Southern Reply.

PO 00000

Frm 00008

Fmt 4701

Sfmt 4700

transmission customers’ lack of

understanding of the OATT

requirements, and the data available on

OASIS.45

34. New Mexico Attorney General

argues that the traditional Stateregulated, vertically-integrated cost-ofservice world is not in need of reform.

Contrary to the ‘‘conspiracy theorists’’

who argue that utilities have an

incentive to engage in undue

discrimination and preference in

transmission services, New Mexico

Attorney General asserts that utilities

have an incentive to maximize

throughput and revenue between Statelevel rate cases because incremental

transmission revenue is not deducted

from the State-jurisdictional retail

revenues between rate cases. Similarly,

Southern, in its reply comments, asserts

that broad claims of undue

discrimination fail to take into

consideration that vertically-integrated

utilities have more of an incentive to act

appropriately than do independent

utilities because the former have more

to lose (e.g., loss of market-based rates,

state prudence reviews of costs, etc.) if

they are found to have engaged in

wrong-doing. Southern states that any

OATT revisions ultimately adopted by

the Commission must be reasonably

tailored to address an identified

problem or to provide a specific

improvement.

35. Other commenters argue that the

Commission’s focus should be on

transmission providers in non-organized

markets, arguing that remaining

concerns about undue discrimination

have already been addressed in the

world of ISOs and RTOs.46 According to

ISO/RTO Council, this proceeding

provides an opportunity for the

Commission to harmonize the worlds of

organized and non-organized markets in

a manner that encourages competition,

promotes non-discriminatory access,

and maximizes the flow of electricity

across various ISO/RTO and non-ISO/

RTO regions. ISO/RTO Council states

that, in the existing regulatory

environment, a utility that is not a

member of an ISO or RTO can sell into,

or purchase from, an ISO or RTO market

even though the non-ISO/RTO utility

operates under tariff rules that are less

open and transparent, particularly in

terms of access to generation resources

and pricing/system information, than

their competitors that belong to an ISO

or RTO. Such asymmetry, ISO/RTO

Council argues, operates as an

45 See, e.g., Entergy Reply, Progress Energy Reply,

and Southern Reply.

46 E.g., Indicated New York Transmission

Owners, ISO/RTO Council, and Northeast Utilities.

E:\FR\FM\15MRR2.SGM

15MRR2

Federal Register / Vol. 72, No. 50 / Thursday, March 15, 2007 / Rules and Regulations

sroberts on PROD1PC70 with RULES

impediment to fair and nondiscriminatory transmission access and

management of grid congestion.

36. ISO/RTO Council states that its

members do not seek to impose their

market designs on the rest of the nation.

At the same time, ISO/RTO Council

argues that meaningful reform should

ensure a level of transparency (of both

price and the dispatch utilized by nonISO/RTO vertically-integrated entities)

in regions without an ISO or RTO that

can assist the flow of electricity and

enhance reliability and planning in both

ISO/RTO and non-ISO/RTO regions.

37. Exelon urges the Commission to

hold the transmission providers outside

ISOs or RTOs to the same standard of

non-discrimination that exists within

those organizations. Further, MISO/PJM

States argue that in order to achieve

some level of independence in non-RTO

regions, non-independent transmission

providers should be encouraged to turn

over operational control of their

transmission systems to an independent

coordinator of transmission whose

functions would include security

coordination, determination of ATC,

granting of transmission service and

oversight for transmission planning.

38. Finally, EPSA suggests that the

Commission establish a one-year review

period for the reformed pro forma

OATT. EPSA urges the Commission to

revisit this Final Rule after one year of

operation under the reformed pro forma

OATT to ensure that the revisions

adopted here do, in fact, protect against

non-discriminatory or preferential

behavior by transmission providers.

NRECA responds that, after this

comprehensive rulemaking process,

there is simply no need for another

major look at the OATT in one year.

Moreover, NRECA states, one year is

likely too short a period for the

Commission and industry participants

to fully appreciate all of the

consequences of those elements of

OATT reform resulting from this

proceeding. At the same time, NRECA

agrees that the Commission should

carefully monitor implementation of the

reformed OATT. This monitoring,

NRECA states, must be an ongoing

process and cannot wait a year to begin.

Commission Determination

39. The Commission concludes that

reforms are needed to address

deficiencies in the pro forma OATT that

have become apparent since 1996, by

limiting remaining opportunities for

undue discrimination. As the

Commission found in Order No. 888, it

is in the economic self-interest of

transmission monopolists, particularly

those with high-cost generation assets,

VerDate Aug<31>2005

18:17 Mar 14, 2007

Jkt 211001

to deny transmission or to offer

transmission on a basis that is inferior

to that which they provide to

themselves.47 Such an incentive can

lead to unduly discriminatory behavior

against third parties, particularly if

public utilities have unnecessarily

broad discretion in the application of

their tariffs. This discretion also can

create problems for transmission

providers seeking to comply with our

regulations in good faith because so

many issues are left for their

interpretation, thereby increasing the

possibility of disputes with

transmission customers and

enforcement actions by the

Commission.48 Transmission customers

also have found ways to use the tariffs

to their own advantage, particularly in

the scheduling and queuing processes.49

40. As some commenters note,

opportunities for undue discrimination

persist, particularly in areas where the

pro forma OATT leaves the

transmission provider with substantial

discretion. The Commission has a

responsibility under section 206 of the

FPA to remedy undue discrimination.

Indeed, the court concluded in

Associated Gas Distributors v. FERC,50

that, like the Natural Gas Act,51 the FPA

‘‘fairly bristles’’ with concern over

undue discrimination. Based on AGD,

the Commission determined in Order

No. 888 that:

The Commission has a mandate under

sections 205 and 206 of the FPA to ensure

that, with respect to any transmission in

interstate commerce or any sale of electric

energy for resale in interstate commerce by

a public utility, no person is subject to any

undue prejudice or disadvantage. We must

determine whether any rule, regulation,

practice or contract affecting rates for such

transmission or sale for resale is unduly

discriminatory or preferential, and must

prevent those contracts and practices that do

not meet this standard. * * * AGD

demonstrates that our remedial power is very

broad and includes the ability to order

industry-wide non-discriminatory open

access as a remedy for undue discrimination.

47 Order No. 888 at 31,682.

48 See, e.g., Order No. 2003 at P 11–12.

49 See, e.g., Potomac Economics, Ltd., 2004 State

of the Market Report: Midwest ISO at 30–31, 34–35

(Jun. 2005), http://www.midwestmarket.org/

publish/Document/2b8a32_103ef711180_-7bf20a

48324a/2004%20MISO%20SOM%20Report.pdf?

action=download&_property=Attachment

(explaining that the queuing process, by giving

customers the opportunity to submit multiple

requests for service, provides a low- or no-cost

option that restricts other customers’ access to

congested interfaces, and the scheduling process, by

allowing customers to leave transmission requests

unconfirmed, provides a free option that may invite

hoarding or result in underutilized capacity).

50 824 F.2d 981 (D.C. Cir. 1987) (AGD).

51 15 U.S.C. 717.

PO 00000

Frm 00009

Fmt 4701

Sfmt 4700

12273

Order No. 888 at 31,669. Through this

Final Rule, the Commission exercises

that remedial authority again to limit

further opportunities for undue

discrimination, by minimizing areas of

discretion, addressing ambiguities and

clarifying various aspects of the pro

forma OATT.

41. We disagree with commenters

who assert that the Commission is

relying on unsubstantiated allegations of

discriminatory conduct to justify OATT

reform. The courts have made clear that

the Commission need not make specific

factual findings of discrimination in

order to promulgate a generic rule to

eliminate undue discrimination.52 In

AGD, the court explained that the

promulgation of generic rate criteria

involves the determination of policy

goals and the selection of the means to

achieve them and that courts do not

insist on empirical data for every

proposition upon which the selection

depends: ‘‘[a]gencies do not need to

conduct experiments in order to rely on

the prediction that an unsupported

stone will fall.’’ 53 During this multi-year

proceeding, the Commission has

received many comments arguing that

commenters have either experienced or

perceived that they have experienced

unduly discriminatory conduct by

transmission providers. Even

transmission providers have

acknowledged that there is a continuing

perception that there is the opportunity

for them to unduly discriminate against

their competitors and, accordingly, they

state their support for our reform

effort.54 Moreover, it is undisputed that

the existing pro forma OATT provides

wide discretion in implementing some

of its basic requirements, such as the

assessment of whether sufficient ATC

exists to grant third party access to the

grid and the manner in which new

facilities are planned to satisfy third

party needs. This wide discretion, when

coupled with a transmission provider’s

incentive to discriminate, creates

opportunities for discrimination under

the pro forma OATT. We have an

obligation under section 206 to remedy

that discrimination.

42. It is thus clear to us that,

notwithstanding the Commission’s

efforts in Order No. 888, opportunities

to engage in undue discrimination can

and will persist unless the existing pro

forma OATT is reformed. We therefore

exercise our broad remedial authority

today to limit these remaining

52 TAPS v. FERC, 225 F.3d at 667, 688; National

Fuel Gas Supply Corp. v. FERC, 468 F.3d 831 (D.C.

Cir. 2006) (National Fuel).

53 824 F.2d at 1008.

54 See, e.g., Duke and EEI.

E:\FR\FM\15MRR2.SGM

15MRR2

12274

Federal Register / Vol. 72, No. 50 / Thursday, March 15, 2007 / Rules and Regulations

sroberts on PROD1PC70 with RULES

opportunities for undue discrimination.

The Commission concludes that any

additional costs incurred by

transmission providers to implement

the reforms required in this Final Rule

are fully justified by the need to ensure

open, transparent and nondiscriminatory access to transmission

service. We also believe it is appropriate

to adopt these reforms by rulemaking,

rather than rely on complaints filed by

transmission customers or other parties.

Case-by-case application of the reforms

adopted in this Final Rule would be

inappropriate since the most

fundamental problems addressed here

arise from deficiencies in the pro forma

OATT itself, not simply the

implementation of the pro forma OATT

by a few transmission providers. Also,

we decline to establish a one-year

review period for the reformed pro

forma OATT, as EPSA recommends.

The Commission will continue to

actively monitor compliance with its

orders and, as necessary, institute

further proceedings to meet its statutory

obligation to remedy undue

discrimination.

43. The Commission will not catalog

each and every basis for its reform of the

pro forma OATT in this section. Rather,

we identify the bases for some of the

most fundamental reforms herein and,

in addition, we explain in each

individual section of the Final Rule the

inadequacies of the existing pro forma

OATT provisions being addressed there

and the reasons why our reforms are

necessary to remedy undue

discrimination or otherwise provide for

rates, terms and conditions of service

under the pro forma OATT that are just

and reasonable.

B. Lack of Transparency Undermines

Confidence in Open Access and

Impedes Enforcement of Open Access

Requirements

44. Following the issuance of the NOI,

the Commission received a number of

comments asserting that increased

transparency would aid transmission

customers in their participation in the

wholesale market. A common theme in

the comments was that a lack of

transparency could lead to claims of

discrimination and could make such

claims more difficult to resolve.

Commenters urged the Commission to

improve transparency in a number of

areas, particularly the evaluation of ATC

and the planning of the transmission

system, as well as the processing of

transmission service requests and

studies.

45. In the NOPR, the Commission

agreed that a lack of transparency both

increases the potential for undue

VerDate Aug<31>2005

18:17 Mar 14, 2007

Jkt 211001

discrimination and makes it more

difficult to detect. The Commission

reasoned that this lack of sufficient

transparency was caused in part by

inadequate compliance with the existing

OASIS regulations and in part by

inadequate transparency requirements.

The Commission stated that the

proposed reforms were intended to

address both elements of the problem in

an effort to increase confidence in open

access tariffs and to facilitate

compliance with the Commission’s

regulations and its enforcement of them.

Comments

46. Williams states that its interests

have been consistently and significantly

compromised by the discretion afforded

transmission providers in the

interpretation of the OATT and the lack

of transparency in requesting,

scheduling and interrupting of

transmission service. According to

Williams, simply being told that service

is being curtailed for reliability

purposes under opaque local

procedures, in the absence of a NERC

Transmission Loading Relief (TLR)

event, leaves market participants

suffering the consequences without

knowing on what basis the decision was

reached, and without assurance that the

decision was made in a nondiscriminatory manner. Ultimately,

Williams adds, the lack of transparency

and latitude taken by the transmission

provider to determine which requests

for service are confirmed or denied and

which are curtailed or interrupted in

real time frustrates the Commission’s

goal of preventing undue discrimination

and preference in the provision of

transmission service. Furthermore,

Williams states, the same lack of

transparency exists around the opaque

processes utilized, assumptions made,

and basis on which the results of

transmission planning studies are

conducted to grant or deny requests for

service.

47. APPA agrees that additional

transparency in the administration of

public utility transmission providers’

OATTs will be of material assistance to

both the Commission and transmission

customers. However, APPA argues that

the Commission must go beyond

increasing transparency in the

administration of public utility

transmission providers’ OATTs.

According to APPA, more transparency

will not change the basic industry

paradigm with transmission customers

depending on monopoly transmission

providers for service. In APPA’s view,

customers are often reluctant to file

complaints or bring problems to the

Commission’s attention because they

PO 00000

Frm 00010

Fmt 4701

Sfmt 4700

depend on their transmission providers’

systems for the vital services they need

to serve their loads. APPA argues that

the Commission not only has an

obligation to act to remedy undue

discrimination when it sees it, but also

has an affirmative duty to look for it.

According to APPA, the Commission

must continue to actively regulate the

transmission services that public utility

transmission providers offer, even if full

transparency is achieved through the

revisions to the OATT implemented in

the instant docket.

48. EPSA agrees that greater

transparency will help enable market

participants and the Commission to

monitor and audit the behavior of

transmission providers. EPSA states that

the several ‘‘black boxes’’ shielding

discriminatory transmission service

over the past ten years must be opened.

However, EPSA argues, there must be

meaningful clarity and obligations set

out in the rules and OATT

requirements—transparency simply for

the sake of knowing why transmission

service has been denied only

illuminates a ‘‘bridge to nowhere’’ and

fails to satisfy the Federal Power Act.

49. Entergy also supports the

Commission’s efforts to provide greater

clarity in the rights and obligations of

transmission providers and

transmission customers under the

OATT. According to Entergy, many of

the improvements proposed by the

Commission will reduce the likelihood

of disputes and promote greater

confidence on the part of customers that

they are being treated fairly. Entergy

states that, while it recognizes that the

lack of clarity makes it difficult for the

Commission to detect instances of noncompliance by transmission providers,

Entergy also believes that this lack of

clarity often makes it easier for

transmission customers to convert every

practice or policy into a claim of

discrimination or other misconduct.

50. Although not convinced that there

is a compelling need for increased

transparency since transmission

providers are already required to

disclose voluminous amounts of

information, Southern states that it

recognizes that some reforms in the

availability of information may be

advantageous. However, Southern

asserts, providing additional

transparency must not simply impose

additional reporting requirements; any

such transparency-related reforms

should be made after taking into

consideration the extent and type of

data and information that is already

provided.

E:\FR\FM\15MRR2.SGM

15MRR2

Federal Register / Vol. 72, No. 50 / Thursday, March 15, 2007 / Rules and Regulations

Commission Determination

51. The Commission concludes that

inadequate transparency requirements,

combined with inadequate compliance

with existing OASIS regulations,

increases the opportunities for undue

discrimination under the pro forma

OATT and makes instances of undue

discrimination more difficult to detect.

We find that the reforms we adopt in

this Final Rule will improve

transparency in the OATT, reduce

opportunities for undue discrimination,

and increase our ability to detect undue

discrimination.

C. Congestion and Inadequate

Infrastructure Development Impede

Customers’ Use of the Grid

52. The Commission noted in the

NOPR that the ability and incentive to

discriminate increases as the

transmission system becomes more

congested. The Commission observed

that the pro forma OATT contained only

minimal requirements regarding

transmission planning, which have

proven to be inadequate as the Nation

faces insufficient transmission

investment in many areas. The

Commission preliminarily concluded

that the inadequacy of the existing

obligation to conduct transmission

system planning, coupled with the lack

of transparency surrounding system

planning generally, required reform of

the pro forma OATT to ensure that

transmission infrastructure is

constructed on a nondiscriminatory

basis and is otherwise sufficient to

support reliable and economic service to

all eligible customers. The Commission

therefore proposed to require public

utilities to engage in an open and

transparent planning process at both the

local and regional levels.

sroberts on PROD1PC70 with RULES

Comments

53. APPA agrees that the lack of

adequate transmission infrastructure is

one of the core problems facing the

electric utility industry. APPA supports

revisions to the pro forma OATT to

enhance and improve transmission

planning on both an individual system

and regional basis. Several commenters

go further, arguing that the proposed

reforms are insufficient and urging the

Commission to more strongly encourage

infrastructure development. EPSA

asserts that successful implementation

of the Congressional policy in favor of

wholesale competition and State

policies in favor of competitive

procurement is frustrated by the lack of

sufficient open access to the

transmission grid. According to EPSA,

new power plant investment is highly

VerDate Aug<31>2005

18:17 Mar 14, 2007

Jkt 211001

unlikely to occur, except by the

transmission provider or its affiliate on

a ‘‘sole source’’ or ‘‘no bid’’ basis

(despite Federal and State policies to

the contrary), if unaffiliated suppliers

cannot effectively and efficiently obtain

transmission service. EPSA argues that

failure to boldly reform the

Commission’s open access transmission

rules at this critical juncture would

effectively hand an undeserved victory

to the very transmission providers who,

by the Commission’s own findings, have

the motive and the opportunity to

discriminate. International

Transmission argues that tariff reform is

no substitute for prudent investment in

the transmission infrastructure needed

to increase the underlying physical

capability of the transmission system.

54. On the other hand, some

commenters dispute the Commission’s

assertion in the NOPR that verticallyintegrated utilities operating in nonRTO regions have an incentive to

discriminate and, therefore, are not

adequately expanding the transmission

grid to accommodate new entry by more

efficient competitors. New Mexico

Attorney General argues that verticallyintegrated utilities operating under the

traditional rate-base, rate-of-return

model of regulation in fact have been

historically criticized for having

incentives to overbuild. New Mexico

Attorney General asserts that most

transmission projects are in reality

derailed by strong ‘‘NIMBY’’ opposition

to the actual siting of transmission lines.

Another countervailing factor to the

utility’s incentive to overbuild, in New

Mexico Attorney General’s view, is the

fact that State regulators attempt to limit

capacity investment to reasonable levels

only necessary to serve native load.

55. Southern states that the

Commission’s assertion in the NOPR

that vertically-integrated utilities do not

have an incentive to expand the grid

overlooks the fact that many such

utilities are under State legal duties to

procure generation supplies through

open, non-discriminatory requests for

proposals, with the winners of those

requests for proposals often being

competitors of the vertically-integrated

utility. Southern maintains that the

winning competitive generation is then

integrated into the host utility’s

transmission system and dispatch, and

the transmission system is expanded to

ensure the deliverability of this

competitive generation. Furthermore,

Southern states, a competitive generator

can also have the output of its generator

planned into the transmission

provider’s system if it takes long-term

firm service under the OATT, with the

transmission provider then being under

PO 00000

Frm 00011

Fmt 4701

Sfmt 4700

12275

a legal duty to expand its transmission

system accordingly. Southern notes that

it alone has invested $3.2 billion in

transmission over the past decade and

plans to invest another $2.8 billion over

the next five years (2006–2010).

56. Community Power Alliance also

argues that the Commission’s own June

2005 ‘‘State of the Markets Report’’

contradicts the Commission’s assertion

that vertically-integrated utilities do not

have the proper incentives to expand

the grid. Community Power Alliance

contends that this report shows that the

amount of transmission investments

made in the non-RTO regions, where

vertically-integrated utilities typically

operate, substantially exceeds the

amount of transmission investments

made in RTO regions.

Commission Determination

57. The Commission concludes that

reforms are needed to ensure that

transmission infrastructure is evaluated,

and if needed, constructed on a

nondiscriminatory basis and is

otherwise sufficient to support reliable

and economic service to all eligible

customers. As noted above, verticallyintegrated utilities do not have an

incentive to expand the grid to

accommodate new entries or to facilitate

the dispatch of more efficient

competitors. Despite this, the existing

pro forma OATT contains very few

requirements regarding how

transmission planning should be

conducted to ensure that undue

discrimination does not occur.

58. Our concern over this flaw is

heightened by the critical need for new

transmission infrastructure in this

Nation. As the Commission explained in

the NOPR, transmission capacity is

being constructed at a much slower rate

than the rate of increase in customer

demand, with transmission capacity per

MW of peak demand declining at an

average rate of 2.1 percent per year

during the period 1992 to 2002.55 The

projections suggest that this trend will

continue through 2012.56 As a result,

there has been a significant decrease in

transmission capacity relative to load in

every NERC region.57 In light of this

trend, there is a compelling need to

build new transmission and respond to

increasing demand through other

55 Eric Hirst, U.S. Transmission Capacity: Present

Status and Future Prospects (Aug. 2004), http://

www.eei.org/industry_issues/energy_infrastructure/

transmission/USTransCapacity10–18–04.pdf

(Present Status and Future Prospects).

56 Present Status and Future Prospects at v.

57 Brendan Kirby (Oak Ridge National Laboratory,

U.S. Department of Energy), Barriers to

Transmission Investment, Technical Conference

Presentation, (Docket No. AD05–5–000) (April 22,

2005).

E:\FR\FM\15MRR2.SGM

15MRR2

12276

Federal Register / Vol. 72, No. 50 / Thursday, March 15, 2007 / Rules and Regulations

sroberts on PROD1PC70 with RULES

means. EEI estimates that capital

spending must increase by 25 percent,

from $4 billion annually to $5 billion

annually, to ensure system reliability

and to accommodate wholesale electric

markets.58 The legacy systems

constructed by vertically-integrated

utilities prior to the adoption of Order

No. 888 support ‘‘only limited amounts

of inter-regional power flows and

transactions. Thus, existing systems

cannot fully support all of society’s

goals for a modern electric-power

system.’’ 59

59. Expansion of the transmission

system, as well as more efficient use of

the grid, will alleviate the growth of

congestion in most regions of the

country. Transmission congestion has

created fairly small local load pockets in

primarily urban areas, e.g., New York

City, Long Island, Boston, parts of

Connecticut, and the San Francisco Bay

Area. Other load pocket concerns have

arisen in parts of northern Virginia, and

various load centers in SPP. Still other

constraints are more regional in scope:

from the Midwest to the Mid-Atlantic,

from the Midwest to TVA, into and

within California, from TVA and

Southern into Entergy, from MidAmerica Interconnected Network into

Wisconsin-Upper Michigan Systems,

and into Florida.

60. Transmission congestion can have

significant cost impacts on consumers.

In 2002, DOE issued a study estimating

the costs of congestion in four U.S.

regions: California, PJM, New York and

New England.60 DOE found that, despite

58 Energy Policy Act of 2005: Hearings before the

Subcommittee on Energy and Air Quality of the

House Committee on Energy and Commerce, 109th

Congress, First Sess. (2005) (Prepared statement of

Thomas R. Kuhn, President of EEI).

59 Present Status and Future Prospects at v.

60 U.S. Department of Energy, National

Transmission Grid Study at 11, 16–17 (May 2002),

available at http://www.ferc.gov/industries/electric/

indus-act/transmission-grid.pdf. To conduct this

study, DOE estimated the benefits of interregional

wholesale power markets using the Policy Office

Electricity Modeling System (POEMS). POEMS is a

national energy model designed specifically to

examine the impacts of electricity restructuring.

The model includes economic, regional, and

temporal detail that is needed to analyze the

economics of interregional trade. In the first step of

the study, DOE used POEMS to examine the cost

reductions that would occur if increased electricity

transfers across congested paths were allowed in

these four regions, assuming generators bid their

marginal costs. Under this assumption, consumer

costs declined by $157 million per year. In the

second step, DOE calculated the increase in

congestion costs under the assumption that

generators bid above their marginal operating costs

when supplies are tight and additional electricity

cannot be imported. The price spikes were assumed

to occur during hours when at least one

transmission link into a sub-region was congested

and demand was greater than 90 percent of peak

demand. When prices spike an additional $50 per

MWh (above the price predicted when generators

VerDate Aug<31>2005

18:17 Mar 14, 2007

Jkt 211001

the overall savings of wholesale

electricity markets that lowered

consumers’ electricity bills by nearly

$13 billion annually, interregional

transmission congestion cost consumers

hundreds of millions of dollars

annually. DOE concluded that relieving

bottlenecks in these four regions alone

could save consumers about $500

million annually.61 In 2006, DOE

released another study identifying two

areas of the country with severe existing

or growing congestion problems: the

Atlantic coastal area from metropolitan

New York southward through Northern

Virginia, and Southern California.62

61. The decline in transmission

investment and increase in transmission

congestion underscore our concerns

over inadequate planning provisions of

the existing pro forma OATT. The

existing pro forma OATT, as indicated

above, contains very little specificity

regarding how transmission planning

should be conducted, how customers’

needs are incorporated into that process,

and what information is publicly

available regarding the transmission

providers’ assumptions, criteria and

data used in the planning process.

These inadequacies are sufficiently

severe, standing alone, to merit reform

of the OATT. However, they are of even

greater concern given the current state

of the transmission grid. With

inadequate levels of investment in the

grid and increasing transmission

congestion, customers’ ability to access

alternatives to the transmission

provider’s resources is limited. It is

therefore imperative for the Commission

to ensure that the planning process

under each transmission provider’s

OATT is sufficient to prevent undue

discrimination and transparent enough

to detect any remaining instances of

undue discrimination. We have done so

in the reforms adopted and explained in

section V.B.

D. A Consistent Method of Measuring

ATC Is Needed

62. Another area in which

transmission providers have significant

discretion under the pro forma OATT is

the calculation of ATC. While Order No.

888 obligated each public utility to

calculate the amount of transfer

capability on its system available for

sale to third parties, the Commission

bid their marginal operating cost) during these

periods, congestion costs nearly double to $300

million.

61 Id. at xi and ii.

62 U.S. Department of Energy, National Electric

Transmission Congestion Study, Executive

Summary at 2 (August 2006), available at http://

www.ferc.gov/industries/electric/indus-act/doecongestion-study-2006.pdf.

PO 00000

Frm 00012

Fmt 4701

Sfmt 4700

did not standardize the methodology for

calculating ATC, nor did it impose any

specific requirements regarding the

disclosure of the methodologies used by

each transmission provider.63 As a

result, there are a variety of ATC

calculation methodologies in use today

and very few clear rules governing their

use. Moreover, there is often very little

transparency about the nature of these

calculations, given that many

transmission providers have filed only

summary explanations of their ATC

methodologies in Attachment C to their

OATTs.

63. In the NOPR, the Commission

noted that, although the industry has

sought to pursue greater consistency in

ATC calculations through existing

NERC processes, these efforts to date

have been largely unsuccessful. The

Commission expressed its preliminary

determination that the lack of a

consistent, industry-wide methodology

for calculating ATC gives transmission

providers the ability and the

opportunity to unduly discriminate

against third parties. The Commission

therefore proposed a number of reforms

to the process of calculating ATC to

provide clarity and transparency to

users of the grid.

Comments

64. As discussed further in section

V.A below, most commenters support

the Commission’s goal of requiring

greater consistency in the manner in

which ATC is calculated and additional

transparency of ATC calculations.

Commenters generally favor the

Commission’s proposal to increase

consistency in the calculation of ATC,

including consistent definitions of its

components, data inputs, modeling

assumptions, and data exchange and

coordination protocols. For example,

Exelon argues that each ATC component

should be used in the same manner for

all purposes (e.g., granting transmission

service to third parties or for the

transmission provider’s own network

load). Some commenters assert that

industry-wide standardization of ATC

calculation might not be possible and

that the Commission should consider

interconnection-wide, regional or even

sub-regional standardization. Others

suggest allowing flexibility in order to

capture differences in system operation,

usage, market operations and topology.

65. At the technical conference

organized in this proceeding on October

12, 2006 (October 12 Technical

Conference), the entire panel agreed that

definitions must be consistent and a

panelist representing Constellation

63 Order No. 888 at 31,794 n.610.

E:\FR\FM\15MRR2.SGM

15MRR2

Federal Register / Vol. 72, No. 50 / Thursday, March 15, 2007 / Rules and Regulations

asserted that broad differences in the

core definitions of the ATC calculation

are neither rational nor explainable.64

NERC, however, recognized that the

goal of achieving consistency may not

mean that a single ATC methodology is

required.65 NERC explained that

consistency can be achieved with a

limited number of methodologies if the

requirements of those methodologies are

properly coordinated and

communicated.

66. Numerous commenters support

the Commission’s proposals to increase

transparency in the manner in which

transmission providers derive ATC,

including greater OASIS posting.

Commenters opposing the transparencyrelated reforms focus on the

Commission’s proposal to require the

posting of narratives on OASIS

explaining reasons for changes in

monthly and yearly ATC values on

constrained paths. They argue that such

a requirement would be too burdensome

and would not provide customers with

any significant new information.

67. Several commenters believe that

making substantial ATC calculation and

modeling data transparent will

compromise Critical Energy

Infrastructure Information (CEII) but

provide suggestions for resolving the

issue. Others express concern that the

data required for posting on OASIS is

not CEII but commercially sensitive.

Finally, commenters provide

suggestions regarding the requirement to

post metrics on OASIS related to the

provision of transmission service under

the pro forma OATT, including various

additional metrics the Commission

should consider. Others state that this

information is already available on

OASIS.

sroberts on PROD1PC70 with RULES

Commission Determination

68. We find that the lack of a

consistent and transparent methodology

for calculating ATC gives transmission

providers the ability and opportunity to

unduly discriminate in the provision of

open access transmission service. There

are few clear rules respecting ATC

calculation, and transmission providers

retain unnecessarily broad discretion in

this area. This resulting discretion is a

significant problem because calculation

of ATC, which varies greatly depending

on the criteria and assumptions used,

may allow the transmission provider to

discriminate in subtle ways against its

competitors. On systems where

64 Transcript of October 12 Technical Conference

at 149–50, available at Preventing Undue

Discrimination and Preference in Transmission

Service, Technical Conference (Docket No. RM05–

25–000).

65 Id. at 125–50.

VerDate Aug<31>2005

18:17 Mar 14, 2007

Jkt 211001

transmission capacity is congested, this

lack of consistency, coupled with a lack

of transparency, is of heightened

importance and has led to recurring

disputes over whether the transmission

provider is exercising its discretion to

discriminate against its competitors.

This discretion also hampers the

detection of undue discrimination and,

thereby, undermines the Commission’s

ability to enforce the general

requirement in Order No. 888 that

transmission service be provided on a

not unduly discriminatory basis.

69. As discussed more fully below in

section V.AIII.D, this Final Rule adopts

a number of reforms that address the

potential for remaining undue

discrimination in the determination of

ATC by requiring consistency in how

ATC is evaluated, as well as providing

greater transparency about how a

transmission provider calculates and

allocates ATC.

E. Discriminatory Pricing of Imbalances

70. Order No. 888 focused primarily

on the adoption of non-rate terms and

conditions of service, rather than

instituting broad reform of the

Commission’s transmission pricing

policies. Consistent with this focus, the

Commission did not propose broad

transmission pricing reform in the

NOPR, but rather focused on instances

where current pricing practices under

the pro forma OATT may no longer be

sufficient to remedy undue

discrimination or ensure just and

reasonable rates. One significant reform

proposed in the NOPR related to charges

for imbalance energy. The Commission

preliminarily found that the existing

policies provide wide discretion in the

development of these charges and hence

the potential for undue discrimination.

The Commission therefore proposed

certain principles to remedy that

potential and sought comment on

whether a specific imbalance pricing

method would be appropriate.

Comments

71. In general, transmission customers

complain about the level and scope of

energy and generator imbalance charges

that are levied under the pro forma

OATT and under individual

interconnection agreements.66

Customers complain that energy

imbalance charges are excessive and not

66 Energy imbalance charges, including penalties

on some systems, are imposed on a transmission

customer when the amount of energy scheduled for

delivery to the transmission grid does not equal the

amount of energy withdrawn by that customer.

Generator imbalance charges are levied on

generators for deviations between the amount of

energy they schedule and the amount they actually

deliver to the grid.

PO 00000

Frm 00013

Fmt 4701

Sfmt 4700

12277

related to the actual costs incurred by

transmission providers. They also argue

that the inconsistency between these

charges in different control areas is

unnecessary, and that other means of

compensating the transmission

provider, such as return-in-kind, should

be considered. Generators likewise

complain that generator imbalance

charges are excessive, that transmission

providers refuse to credit generators

with the revenues resulting from

imbalance penalties that are collected,

and that transmission providers prevent

unaffiliated generators from purchasing

or self-supplying generator imbalance

services. In addition, owners of

intermittent resources complain that

generator imbalance charges, which are

imposed to provide an incentive for

generators to schedule accurately, are

inappropriate given their lack of control

and ability to cure deviations.

Commission Determination

72. The Commission agrees that

imbalance charges should provide

appropriate incentives to keep

schedules accurate without being

excessive. We also find that consistency

in imbalance charges, both between and

among energy and generator imbalances,

is preferable to the wide variety of

imbalance provisions in place today. All

imbalances have the same net effect on

the transmission system in that they

require other generation to be ramped

up or down to compensate for the

imbalance. As such, the Commission

adopts two pro forma OATT provisions

(Schedule 4 for energy imbalances and

Schedule 9 for generator imbalances)

based on a tiered structure similar to the

imbalance provision used by

Bonneville, as described further below.

Such an approach recognizes the link

between escalating deviations and

potential reliability impacts on the

system while keeping imbalance charges

closely related to incremental costs. The

Commission finds, however, that

intermittent resources should be exempt

from the highest-tier deviation band. We

also require transmission providers to

credit to all non-offending transmission

customers the revenues they collect in

excess of incremental costs.

F. Redispatch/Conditional Firm

73. In the NOPR, the Commission

examined whether existing methods for

evaluating requests for long-term firm

point-to-point service continue to be

just and reasonable. When a

transmission provider considers a new

resource to serve native load, the

transmission provider does not

eliminate an otherwise economic option

because the resource may not be

E:\FR\FM\15MRR2.SGM

15MRR2

12278

Federal Register / Vol. 72, No. 50 / Thursday, March 15, 2007 / Rules and Regulations

deliverable during a few hours of the

year. For transmission customers,

however, the transmission provider

evaluates whether service can be

granted in every hour of the year that is

modeled and, if not, it informs the

customer that service cannot be

provided out of existing transfer

capability. Only if the transmission

customer agrees to pay for facilities

studies does the transmission provider

evaluate redispatch options, including

whether they are less expensive than the

upgrade costs. The Commission

therefore proposed to reform the

existing pro forma OATT planning

redispatch 67 obligation, or, in the

alternative, to add a conditional firm

service to the pro forma OATT. As

proposed by the Commission,

conditional firm would have been a

long-term service allowing the

transmission provider to give a lower

curtailment priority than firm to the

transmission customer during a prespecified number of hours.

sroberts on PROD1PC70 with RULES

Comments

74. Some commenters support the

inclusion of both a modified planning

redispatch obligation and a conditional

firm service in the pro forma OATT,

stating that both are required to remedy

undue discrimination and provide for

comparable transmission service. These

commenters urge the Commission to

require transmission providers to offer

planning redispatch and conditional

firm service and allow customers to

choose the option that best suits their

physical, commercial and economic

circumstances.

75. Others opine that conditional firm

service may be simpler and less costly

to implement. These commenters prefer

the development of conditional firm

service over the modifications to the

planning redispatch service because of

the complexities surrounding redispatch

costs and protocols. For example,

Entergy believes conditional firm

service can provide benefits to

transmission customers without unfairly

socializing costs to native load and

network customers of the transmission

provider.

76. On the other hand, many

commenters argue that the Commission

should not require either option because

the services are unnecessary,

operationally unworkable, and legally

unjustified, or because they would harm

reliability and the quality of existing

67 Although pro forma OATT section 13.5 refers

to ‘‘redispatch,’’ we refer to it here as ‘‘planning

redispatch’’ to distinguish it from the reliability

redispatch provisions in the network integration

transmission service sections of the pro forma

OATT. See infra notes 552 and 557.

VerDate Aug<31>2005

18:17 Mar 14, 2007

Jkt 211001

network service and provide

disincentives for transmission

investment. Several commenters state

that these services would make

curtailments of existing firm service

more likely and limit opportunities for

use of secondary network service,

thereby harming native load protections

and reducing reliability, contrary to FPA

sections 215 and 217 respectively.

While it recognizes that conditional firm

service has been successful in parts of

the Western Interconnection, NRECA

contends that a mandate would

undermine responsible planning and

expansion of the transmission grid by

harnessing the transmission provider’s

planning and dispatch functions to

frame elaborate service conditions for

conditional firm service.

77. Several commenters argue that, if

the services are required, the

Commission should ensure that

reliability is not adversely affected.

Others urge the Commission to make the

new services an interim option until

transmission upgrades are in place to

provide firm service. Some commenters

believe planning redispatch and

conditional firm customers should bear

the actual costs of the services received,

including costs associated with system

operational changes needed to

accommodate the services. A few

commenters believe that the

Commission should allow for regional

differences in development of the new

services.

Commission Determination

78. The Commission believes it is

necessary to modify the manner in

which transmission providers assess

point-to-point service requests to

eliminate the potential for undue

discrimination in transmission service.

We find that both techniques—planning

redispatch and conditional firm

service—are currently used under

certain circumstances by transmission

providers to serve native load and,

therefore, that transmission customers

should have comparable services in

order to avoid undue discrimination,

facilitate the provision of long-term

transmission service and provide

customers with greater flexibility in

choosing resources to meet their needs.

We expect that both options will help

integrate new generation more quickly.

This can be particularly beneficial to

renewable generation resources, such as

wind, that can be constructed more

quickly than the transmission upgrades

necessary to deliver their power on a

firm basis over the long-run.

PO 00000

Frm 00014

Fmt 4701

Sfmt 4700

G. EPAct 2005 Emphasized Certain

Policies and Priorities for the

Commission

79. Finally, we note that the reforms

adopted in this proceeding are

consistent with the policies and

priorities embodied in EPAct 2005, in

which Congress emphasized many of

the same principles reflected in this

Final Rule. First, in EPAct 2005,

Congress placed special emphasis on

the development of transmission

infrastructure. Congress required the

Commission to adopt a rule establishing

incentive-based rates for new

transmission infrastructure investment.

The stated purpose of new FPA section

219 is to benefit ‘‘consumers by

ensuring reliability and reducing the

cost of delivered power by reducing

transmission congestion.’’ 68 Among

other steps, FPA section 219 requires

the Commission to ‘‘(1) Promote reliable

and economically efficient transmission

and generation of electricity by

promoting capital investment in the

enlargement, improvement,

maintenance, and operation of all

facilities for the transmission of electric

energy in interstate commerce,

regardless of the ownership of the

facilities; (2) provide a return on equity

that attracts new investment in

transmission facilities (including related

transmission technologies); [and] (3)

encourage deployment of transmission

technologies and other measures to

increase the capacity and efficiency of

existing transmission facilities and

improve the operation of the

facilities.’’ 69 In addition, Congress

directed the Commission to encourage

the deployment of advanced

transmission technologies.70 Congress

also gave the Commission certain

‘‘backstop’’ transmission siting

authority, and authorized the creation of

interstate compacts establishing

transmission siting agencies.71 Finally,

the Commission was directed to

exercise its authority under EPAct 2005

‘‘in a manner that facilitates the

planning and expansion of transmission

facilities to meet the reasonable needs of

load-serving entities to satisfy the

68 EPAct 2005 sec. 1241 (to be codified at section

219 of the FPA, 16 U.S.C. 824s). The Commission

has issued a Final Rule implementing such an

incentive rate program. See Order Nos. 679 and

679–A.

69 FPA Sec. 219(b)(1).

70 EPAct 2005 sec. 1223 (to be codified at 42

U.S.C. 16442).

71 EPAct 2005 sec. 1221(a) (to be codified at

section 216 of the FPA, 16 U.S.C. 824p). The

Commission implemented new regulations in

accordance with this section to establish filing

requirements and procedures for entities seeking to

construct electric transmission facilities in Order

No. 689.

E:\FR\FM\15MRR2.SGM

15MRR2

Federal Register / Vol. 72, No. 50 / Thursday, March 15, 2007 / Rules and Regulations

sroberts on PROD1PC70 with RULES

service obligations of the load-serving

entities, and enables load-serving

entities to secure firm transmission

rights * * * on a long-term basis for

long-term power supply arrangements

made, or planned, to meet such

needs.’’ 72 Although these provisions

have been, or will be, addressed

primarily in other proceedings, we

conclude that the Final Rule is

consistent with these provisions

because it supports improvements in

infrastructure by reforming the

transmission planning process to ensure

that it is open, transparent and

nondiscriminatory.

80. Second, Congress emphasized the

need for greater transparency in

electricity markets, including

transmission service. EPAct 2005 added

section 220 to the FPA, which requires

the Commission to facilitate ‘‘price

transparency in markets for the sale and

transmission of electric energy in

interstate commerce, having due regard

for the public interest, the integrity of

[that market], fair competition, and the

protection of consumers.’’ 73 The

Commission was authorized to

‘‘prescribe such rules as the

Commission determines necessary and

appropriate to carry out the purposes

of’’ FPA section 220. Those rules ‘‘shall

provide for the dissemination, on a

timely basis, of information about the

availability and prices of wholesale

electric energy and transmission service

to the Commission, State commissions,

buyers and sellers of wholesale electric

energy, users of transmission services,

and the public.’’ This Final Rule

similarly will promote greater

transparency in the provision of

transmission service in many important

areas, including ATC calculation and

transmission planning.

81. Finally, Congress emphasized

compliance with the Commission’s

regulations, increasing the civil and

criminal penalties for violations of

Commission-administered statutes and

regulations.74 This new authority

buttresses the Commission’s efforts to

enforce public utility OATTs and the

regulations requiring transmission

information to be posted on OASIS. As

we explained in the Policy Statement on

Enforcement, however, this new

72 EPAct 2005 sec. 1233(a) (to be codified at

section 217(b)(4) of the FPA, 16 U.S.C. 824q). The

Commission implemented FPA section 217(b)(4) in

Long-Term Firm Transmission Rights in Organized

Electricity Markets, Order No. 681, 71 FR 43564

(Aug. 1, 2006), FERC Stats. & Regs. ¶ 31,226 (2006),

order on reh’g, Order No. 681–A, 117 FERC ¶ 61,201

(2006), reh’g pending.

73 EPAct 2005 sec. 1281 (to be codified at 16

U.S.C. 824t).

74 EPAct 2005 sec. 1284(e)(1) (to be codified at

section 316(A) of the FPA, 16 U.S.C. 825o–1).

VerDate Aug<31>2005

18:17 Mar 14, 2007

Jkt 211001

authority carries with it the

responsibility to ensure that

enforcement is firm but fair and that our

rules are as clear as practicable to

facilitate compliance.75 We conclude

that this Final Rule is fully consistent

with these principles because it clarifies

our rules, in many areas, which will

facilitate compliance by transmission

providers.

IV. Summary, Scope and Applicability

of the Final Rule

82. This section provides a summary

of the major components of the Final

Rule, a description of the core elements

of Order No. 888 that we retain, and a

discussion of the applicability of the

proposed rule to various entities.

A. Summary of Reforms

83. Consistency and transparency of

ATC calculations. The Commission

affirms the finding in the NOPR that the

lack of a consistent, industry-wide

methodology for calculating ATC, and

the lack of adequate transparency in

ATC calculations, increases the

potential for undue discrimination and

also makes undue discrimination more

difficult to detect. The lack of consistent

standards can facilitate undue

discrimination by giving a transmission

provider the discretion, and hence the

ability and opportunity, to favor itself

and its affiliates over third parties in

how it calculates and allocates ATC. In

this Final Rule, we give the industry

specific guidance regarding the

calculation of ATC and establish a firm

deadline to develop certain

requirements to make more consistent

the ATC calculation process and the

process of exchanging data between

transmission providers about ATC. In

addition, we amend pro forma OATT

requirements as well as our OASIS

regulations to increase the transparency

in how ATC is calculated.

84. Requirement for coordinated,

open and transparent transmission

planning. The Commission also affirms

the finding in the NOPR that Order No.

888 does not contain sufficient

protections to guard against undue

discrimination in transmission system

planning. Without adequate

coordination and open participation,

market participants have minimal input

or insight into whether a particular

transmission plan treats all loads and

generators comparably. To ensure that

truly comparable transmission service is

provided by all public utility

transmission providers, including RTOs

75 Enforcement of Statutes, Orders, Rules and

Regulations, Policy Statement on Enforcement, 113

FERC ¶ 61,068 (2005) (Policy Statement on

Enforcement).

PO 00000

Frm 00015

Fmt 4701

Sfmt 4700

12279

and ISOs, we amend the pro forma

OATT to require coordinated, open, and

transparent transmission planning on

both a sub-regional and regional level.

To implement this remedy, we adopt

the eight planning principles proposed

in the NOPR, as well as one additional

principle, that each public utility

transmission provider will be required

to follow. We recognize that many

regions have made significant progress

in recent years in creating greater

openness and transparency in

transmission planning and believe our

proposed reforms will build upon,

strengthen, and improve this progress to

reform transmission planning.

85. Transmission Pricing Reforms.

Consistent with the focus of Order No.

888 on the non-rate terms and

conditions of open access, the

Commission does not initiate broad

reform of transmission pricing policy

through this Final Rule. However, we

have identified several pricing rules that

are part and parcel of OATT service that

merit reform.

• Energy and Generator Imbalance

Charges. We find that energy and

generator imbalance charges we have

previously accepted are excessive, too

varied, and otherwise unrelated to the

cost of providing the service and,

therefore, we reform energy and

generator imbalance pricing. We adopt

tiered pro forma OATT energy and

generator imbalance provisions similar

to those in use by Bonneville and

exempt intermittent resources from the

highest deviation band. In these new

provisions, imbalance charges are based

on incremental cost and escalate as the

imbalance increases. Any deviations

from these provisions must be

consistent with or superior to the pro

forma OATT as modified by this Final

Rule and must meet the following

criteria: the charges must (1) Be related

to the cost of correcting the imbalance,

(2) be tailored to encourage accurate

scheduling behavior, such as by

increasing the percentage of the adder as

the deviations become larger, and (3)

account for the special circumstances

presented by intermittent generators,

such as by waiving the higher ends of

the deviation penalties.

• Capacity Reassignment Pricing. We

find that the existing cap on the

reassignment of point-to-point service is

no longer just and reasonable and,

therefore, we eliminate the cap. We

believe that removing the cap will

eliminate an unnecessary impediment

to the resale of capacity, which in turn

should increase utilization of the grid

and otherwise ensure that point-to-point

service is just, reasonable, and not

unduly discriminatory.

E:\FR\FM\15MRR2.SGM

15MRR2

sroberts on PROD1PC70 with RULES

12280

Federal Register / Vol. 72, No. 50 / Thursday, March 15, 2007 / Rules and Regulations

• Crediting of Customer-Owned

Facilities. We retain most elements of

our existing policy respecting the

crediting of customer-owned facilities,

including the requirement that such

facilities meet the integration standard.

However, we eliminate the requirement

that new facilities can receive credits

only if they are ‘‘jointly planned’’

because this requirement provides a

disincentive to coordinated planning.

Rather, we provide that such new

facilities are eligible for credits if such

facilities are integrated into the

operations of the transmission

provider’s facilities. Customer-owned

facilities shall be presumed to be

integrated if those facilities, if owned by

the transmission provider, would be

eligible for inclusion in the transmission

provider’s annual transmission revenue

requirement.

86. Improvements to Point-to-Point

Service. The Commission concludes that

the existing methods for evaluating

requests for long-term firm point-topoint service are no longer just,

reasonable, and not unduly

discriminatory. The existing pro forma

OATT allows the transmission provider

to deny a request for long-term point-topoint service if that service is not

available in a single hour of the period

studied. We find that this approach is

not comparable because, when a

transmission provider considers a new

resource to serve native load, the

transmission provider does not

eliminate an otherwise economic option

because the resource may not be

deliverable in a few hours of the year.

To remedy this problem, the

Commission adopts a ‘‘conditional

firm’’ component to long-term point-topoint service that addresses the

situation where firm service can be

provided for most, but not all, hours of

the period requested. We also reform the

existing requirements for the provision

of redispatch service to ensure that they

are of greater use to transmission

customers and more consistent with

reliability planning and operation of the

system.

87. Reform of rollover rights. The

Commission concludes that section 2.2

of the pro forma OATT, which grants an

ongoing right to transmission customers

to renew or ‘‘roll over’’ their contracts,

should be reformed. The current

rollover rights do not provide

consistency between the rights of

rollover customers and the resulting

obligations of transmission providers to

plan and upgrade the system to

accommodate rollovers. The

Commission therefore amends section

2.2 to ensure greater consistency with

transmission planning and construction

VerDate Aug<31>2005

18:17 Mar 14, 2007

Jkt 211001

timelines and modifies the minimum

term of the rollover rights to five years,

rather than the current minimum term

of one year. The Commission also

requires that a transmission customer

eligible for rollover rights provide notice

of whether or not it will exercise its

right of first refusal to renew the

contract no less than one year before the

expiration date of the transmission

service agreement, rather than within

the current 60-day period.

88. Increases in transparency to

lessen the opportunities to discriminate

and reduce transaction costs. In

addition to the increased transparency

we require regarding the calculation of

ATC and transmission planning, we

increase the transparency of

transmission service provided under the

pro forma OATT in several other

respects. For example, we require

transmission providers and their

network customers to use the

transmission providers’ OASIS to

request designation of a new network

resource and to terminate the

designation of an existing network

resource. In addition, we require

transmission providers to modify their

OASIS so that requests to designate and

terminate a network resource can be

queried, allowing all parties access to

such information. We also require

transmission providers to post a list of

their current designated network

resources and all network customers’

current designated network resources on

their OASIS. Finally, we require

transmission providers to post on

OASIS all their business rules, practices

and standards that relate to transmission

services provided under the pro forma

OATT.

89. Strengthening enforcement of the

pro forma OATT. The reforms adopted

in this Final Rule provide greater clarity

in the terms and conditions of the pro

forma OATT, resolving ambiguities in

the existing pro forma OATT that have

made undue discrimination easier to

accomplish and more difficult to detect.

Our new civil penalty authority under

EPAct 2005 gives us ample power to

remedy tariff violations, but it also

places upon us an increased

responsibility to make the rules as clear

as possible. We fulfill that responsibility

in the Final Rule by providing greater

clarity where appropriate to several

critical OATT provisions. We also adopt

a number of posting and reporting

requirements that will provide the

Commission and market participants

with information about each

transmission provider’s performance of

pro forma OATT obligations. For

example, we require transmission

providers to post specific performance

PO 00000

Frm 00016

Fmt 4701

Sfmt 4700

metrics related to their completion of

studies required under the pro forma

OATT. We note that the Commission

will continue to audit compliance with

the pro forma OATT, and toward that

end require transmission information

kept on OASIS to be retained for audit

purposes for five years. Finally, we

adopt a number of reforms to

operational penalties assessed under the

pro forma OATT, including so-called

‘‘over-use’’ penalties and the treatment

of operational penalty revenues

collected from transmission providers

and their affiliates.

90. Miscellaneous OATT

improvements. Finally, we implement a

number of improvements to the terms

and conditions of the pro forma OATT

to incorporate the lessons learned over

the past ten years. We briefly note these

below:

• Designation of network resources.

We provide clarification regarding the

types of agreements that may be

designated as network resources, the

process for verifying whether

agreements meet the requirements in the

pro forma OATT, and the requirement

for transmission providers to designate

and undesignate network resources. We

also require customers to submit an

attestation with each application to

designate a new network resource.

• Reservation priorities. We change

the priority rules to give certain priority

to pre-confirmed transmission service

requests submitted in the same time

period. We also add price as a tiebreaker in determining reservation

queue priority when the transmission

provider is willing to discount

transmission service.

• Clarifications related to network

service. We provide clarification related

to use of network service on an ‘‘as

available basis’’ and to ‘‘redirects’’ of

network service.

B. Core Elements of Order No. 888 That

Are Retained

91. Although we are adopting many

important reforms to Order No. 888 and

the pro forma OATT in this Final Rule,

we emphasize that many of the core

elements of Order No. 888 are retained.

As the Commission noted in the NOPR,

many of these core elements enjoy broad

support from many sectors of the

industry. A variety of commenters—in

response to the NOI issued earlier in

this proceeding and again in response to

the NOPR—have urged the Commission

to focus on meaningful incremental

reforms to the pro forma OATT, rather

than on industry restructuring. We share

the view that Order No. 888 can be

strengthened without discarding its

fundamental structure. We discuss

E:\FR\FM\15MRR2.SGM

15MRR2

Federal Register / Vol. 72, No. 50 / Thursday, March 15, 2007 / Rules and Regulations

below the core elements that are being

retained and the comments received on

these points.

1. Federal/State Jurisdiction

92. In Order No. 888, the Commission

stated that it has exclusive jurisdiction

over the rates, terms, and conditions of

unbundled retail transmission in

interstate commerce.76 Though the

Commission adopted a test for

determining what constitute

Commission-jurisdictional transmission

facilities and what constitute Statejurisdictional local distribution facilities

in situations involving unbundled

wholesale wheeling and unbundled

retail wheeling,77 the Commission

stated that it generally would defer to

determinations by State regulatory

authorities concerning where to draw

the jurisdictional line under that test.78

The Commission declined to assert

jurisdiction over bundled retail

transmission, reasoning that ‘‘when

transmission is sold at retail as part and

parcel of the delivered product called

electric energy, the transaction is a sale

of electric energy at retail.’’ 79 The U.S.

Supreme Court affirmed the

Commission’s decision to assert

jurisdiction over unbundled but not

bundled retail transmission, finding that

the Commission made a statutorily

permissible choice.80 In the NOPR, the

Commission proposed to retain the

jurisdictional divide established in

Order No. 888.

Comments

93. Several commenters support the

Commission’s proposal to retain the

existing jurisdictional divide.81 Though

APPA concludes that the most politic

course at this juncture is to leave the

current jurisdictional boundaries in

place and develop cooperative

mechanisms in each region to

coordinate Federal policy

implementation with the relevant State

regulators, APPA notes that there is

disagreement among its members about

whether the current jurisdictional lines

are properly drawn. APPA explains that

a substantial number of its members

believe that all interstate transmission

services (both retail and wholesale)

should be provided under one

consistent set of tariff terms and

conditions. Other APPA members,

however, believe that the Commission

made the proper jurisdictional call in

sroberts on PROD1PC70 with RULES

76 Order No. 888 at 31,781.

Order No. 888. NARUC urges the

Commission to clarify that its planning

proposals will not reopen or attempt to

change the jurisdictional split over

transmission facilities delineated in

Order No. 888.

Commission Determination

94. The Commission will retain the

existing jurisdictional divide that was

established in Order No. 888, which has

been affirmed by the U.S. Supreme

Court and accepted by the industry and

State regulatory authorities.82 We also

reiterate our recognition of the need for

heightened cooperation between Federal

and State regulators in areas where there

are overlapping Federal and State policy

concerns. As explained in greater detail

in the planning section below, and in

response to NARUC’s concern, the

planning reforms adopted in the Final

Rule contemplate coordinated and open

transmission planning, but do not

reopen or otherwise change the existing

jurisdictional divide for transmission

facilities.

2. Native Load Protection

95. In Order No. 888, the Commission

did not require transmission providers

to unbundle transmission service to

their retail native load. The Commission

also did not require that bundled retail

service be taken under the terms of the

pro forma OATT.83 Moreover, the

Commission allowed a transmission

provider to reserve, in its calculation of

ATC, transmission capacity necessary to

accommodate native load growth

reasonably forecasted in its planning

horizon.84 Order No. 888 also granted a

rollover right to existing firm service

customers,85 but allowed transmission

providers to restrict that rollover right if

the capacity was reasonably forecasted

as needed to serve native load

customers, as long as that restriction

was set forth in the customer’s initial

service contract.86

96. Congress, in section 1233 of EPAct

2005, added section 217 to the FPA,

entitled ‘‘Native Load Service

Obligation,’’ which addresses

transmission rights held by load-serving

entities (LSEs). FPA section 217 allows

LSEs to use their own and contractedfor transmission capacity to deliver

energy as required to meet their service

obligations, without being subject to

charges of unlawful discrimination. The

provision makes clear, however, that

this requirement does not abrogate any

77 Id. at 31,771 (setting forth the seven-factor test).

78 Id. at 31,781.

82 See New York v. FERC, 535 U.S. at 28.

79 Id.

83 Order No. 888 at 31,745.

80 See New York v. FERC, 535 U.S. at 28.

84 Id. at 31,694.

81 E.g., Ameren, APPA, North Carolina

85 Id.; see pro forma OATT section 2.2.

Commission Reply, PNM–TNMP, and Southern.

VerDate Aug<31>2005

18:17 Mar 14, 2007

Jkt 211001

86 Order No. 888–A at 30,198.

PO 00000

Frm 00017

Fmt 4701

Sfmt 4700

12281

contract or service agreement for firm

transmission service or rights in effect

as of the date of enactment of EPAct

2005.87 In the NOPR, the Commission

concluded that the protection of native

load embodied in Order No. 888 is

consistent with FPA section 217, and

reaffirmed its commitment to the

protection of native load.

Comments

97. Several commenters agree with

the Commission’s preliminary

conclusion that the protection of native

load embodied in Order No. 888 is

consistent with FPA section 217 and

support the Commission’s continued

commitment to the protection of native

load.88 While APPA 89 and TAPS

generally agree with the Commission

that the overall OATT regime is

consistent with section 217, they urge

the Commission to maintain and

reinforce the comparability requirement.

APPA urges the Commission to broaden

its preliminary conclusion in the NOPR

and conclude instead that the protection

of native load and the provision of fully

comparable transmission service to

other LSEs with long-term service

obligations, as embodied in Order No.

888, are consistent with FPA section

217. TAPS also supports the

Commission’s reading of FPA section

217 as consistent with the Order No.

888 pro forma OATT’s ‘‘native load’’

priority, recognizing that FPA section

217 reinforces the OATT’s commitment

to comparable treatment of all LSEs—

e.g., transmission providers and

network customers.

98. Other commenters dispute the

Commission’s preliminary conclusion

that the native load protection

embodied in Order No. 888 is consistent

with FPA section 217.90 Many

commenters argue that FPA section 217

protects all load, not just native load.91

Constellation states that the

Commission must recognize that there

are other market participants besides the

transmission providers themselves that

are LSEs under FPA section 217. Under

the definition of LSEs in FPA section

87 16 U.S.C. 217(f).

88 E.g., Ameren, E.ON, Tacoma, Arkansas

Commission, EPSA, Southern, and TAPS.

89 APPA argues that the proposed definition of

native load customers in section 1.21 is not

technically consistent with FPA section 217

because FPA section 217 does not distinguish

among the types of power supply arrangements that

an LSE must have to enjoy the protection of FPA

section 217. Nevertheless, APPA states that it

would not be fruitful to reopen the entire OATT

framework to address this technical (but very

important) definitional difference.

90 E.g., Arkansas Municipal, Constellation, Duke,

Salt River, and South Carolina E&G.

91 E.g., Constellation, EPSA, and South Carolina

E&G.

E:\FR\FM\15MRR2.SGM

15MRR2

sroberts on PROD1PC70 with RULES

12282

Federal Register / Vol. 72, No. 50 / Thursday, March 15, 2007 / Rules and Regulations

217, EPSA argues that many entities

other than traditional, verticallyintegrated utilities are in the business of

serving load. The statute, EPSA asserts,

applies to any native load service

obligation, whether that obligation is

served by a competitive supplier, an

affiliate of the transmission provider, or

by the transmission provider itself. Salt

River contends that FPA section 217 is

self-implementing, though it urges the

Commission to act to remove

impediments to the full exercise of

rights granted to LSEs.

99. Constellation argues that the

Commission should require native load

and OATT customers to take service

under the same terms and conditions

because experience has proven that

discrimination has occurred as a result

of having two different sets of rules

applicable to transmission customers.

EPSA urges the Commission to further

clarify that the transmission provider

has an affirmative obligation to serve

native load in a non-discriminatory

manner. According to EPSA, section 217

supports the Commission’s paramount

statutory mission of ensuring nondiscrimination and makes clear that a

transmission provider, when utilizing

transmission capacity or rights reserved

to serve native load, must ‘‘put its

blinders on’’ to ensure that the load’s

needs are being met in the most

economical way available, whether that

decision means the deployment of its

own affiliated generation, or the

deployment of available non-utility

alternatives.

100. Arkansas Municipal asserts that

FPA section 217 recognizes the need to

give priority to LSEs in certain

situations, such as when the

transmission grid may be constrained

and one group of customers may be

denied service at the expense of other

customers. Arkansas Municipal states

that a priority list could be instituted in

this reform proceeding that places LSEs

at the top of the list in competing

requests for transmission service when

not all requests could be granted or

honored by the transmission provider.

101. New Mexico Attorney General

argues that native load is fundamentally

different than merchant load and

therefore, in the planning process, the

needs of merchants should not be

treated comparably with the needs of

New Mexico utilities’ native loads. New

Mexico Attorney General asserts that

New Mexico utilities have a statutory

obligation to serve retail load while

merchants are free to come and go with

cycles inherent in wholesale markets.

According to New Mexico Attorney

General, the transmission requirements

of the utilities’ native loads amount to

VerDate Aug<31>2005

18:17 Mar 14, 2007

Jkt 211001

an ongoing long-term firm contract,

while the transmission needs of

merchants are, by comparison, shortterm and speculative.

102. Several commenters urge the

Commission to revisit various aspects of

the reforms proposed in the NOPR in

order to enhance the protection of

native load. For example, some

commenters urge the Commission to

modify the rollover proposal in the

NOPR. Salt River argues that the

Commission’s regulations must include

a clear provision for a transmission

owner anticipating, or unexpectedly

facing, load growth to recapture

capacity temporarily made available to

the wholesale market. Arkansas

Commission disagrees with the

Commission’s proposal to require a

transmission provider to compete for

transmission capacity rather than

reclaim it through its rights to reserve

capacity for future load growth. The

proposal is inequitable, Arkansas

Commission argues, because native load

customers have historically paid for

most of the transmission providers’

assets and will continue to do so in the

future. Because of this, Arkansas

Commission asserts, native load

customers should be given preference in

the reservation of transmission capacity.

In response to Arkansas Commission’s

position, MDEA urges the Commission

to make clear, consistent with the

comparability principle adopted in

Order No. 888 and reaffirmed in the

NOPR, and with FPA section 217, that

any reservation of rights or preference

available to a transmission provider’s

native load customers must be available

to network customer loads as well.

South Carolina E&G argues that the

Commission’s interpretation of

‘‘reasonably forecasted’’ capacity under

section 2.2 of the pro forma OATT has

been effectively impossible to meet and,

therefore, the Commission should now

provide clear standards for evaluation of

native load protecting rollover

restrictions. A clear standard, South

Carolina E&G states, would have the

Commission consider rollover

restrictions in light of a utility’s

transmission planning process. On

reply, Progress Energy supports South

Carolina E&G’s comments. Progress

Energy urges the Commission to revisit

the rollover rights policy to develop a

policy by which an LSE may be assured

of future transmission service for

reasonably forecasted native load

growth.

103. South Carolina E&G also asks the

Commission to revise section 13.6 of the

pro forma OATT, regarding curtailment

of firm point-to-point transmission

service. South Carolina E&G urges the

PO 00000

Frm 00018

Fmt 4701

Sfmt 4700

Commission to comply with the

mandate of Northern States Power Co. v.

FERC,92 which South Carolina E&G

asserts held that the Commission had

exceeded its authority in rejecting a

vertically-integrated transmission

provider’s proposal to modify section

13.6 of the OATT to give a higher

curtailment priority to native load.

According to South Carolina E&G, the

Commission has responded by applying

the court’s decision narrowly, but FPA

section 217 requires the Commission to

change that position and recognize the

primacy of service to native load in

section 13.6 of the OATT. In its reply

comments, Progress Energy supports the

comments of South Carolina E&G and

states that the Commission must

affirmatively recognize the priority of

service to LSEs in the application of the

curtailment priorities in section 13.6 of

the OATT.

104. Duke argues that several of the

Commission’s proposed reforms—such

as hourly firm service, redispatch, and

conditional firm service—actually

reduce the protection afforded native/

network load. Salt River suggests that

the Commission should modify its ATC

proposal to bring the Commission’s

native load priority policies in line with

FPA section 217. Salt River asserts that,

in calculating ATC, the transmission

provider must be able to exercise

reasonable professional judgment as to

the amount of transmission that must be

reserved to meet native load service

obligations; the Commission should not

get into the business of dictating

forecasting methodology. Salt River

proposes that a native load forecast that

is used by an LSE as the basis for

committing capital for generation

expansion or procurement should be

presumed to be valid for purposes of

establishing available capacity. EPSA,

however, argues that, unless and until

the Commission mandates a hard and

enforceable definition of ATC,

transmission-owning utilities that also

own affiliated generation will continue

to hide behind the native load service

obligation as an excuse for being unable

to find ATC for any but self-serving

purposes.

105. EPSA also argues that the

Commission must ensure that

transmission owners’ planning

accommodates all supply options. EPSA

urges the Commission to clarify that

transmission capacity reserved for

native load is to be made available

(including for study and other purposes)

to competitive suppliers who wish to

92 176 F.3d 1090, 1096 (8th Cir. 1999), cert.

denied sub nom. Enron Power Marketing, Inc. v.

Northern States Power Co., 528 U.S. 1182 (2000).

E:\FR\FM\15MRR2.SGM

15MRR2

Federal Register / Vol. 72, No. 50 / Thursday, March 15, 2007 / Rules and Regulations

sroberts on PROD1PC70 with RULES

serve native load as allowed by State

law. According to EPSA, all generation

assets ultimately serve load and the pro

forma OATT should be clarified to

ensure that the transmission system is

available on a non-discriminatory basis

now and in the future to ensure that

load is optimally served—regardless of

which generation resources are serving

that load. In its reply comments, EPSA

also challenges the initial comments of

New Mexico Attorney General, which

EPSA argues incorrectly interpret FPA

section 217 as drawing a distinction

between the types of generation that

serve load. EPSA argues that the statute

protects the customer load that all

suppliers would seek to serve regardless

of the source.

106. APPA agrees with the

Commission’s response in the NOPR to

Metropolitan Water District that the

specific issues related to an RTO’s

provision of long-term transmission

rights are better left to the rulemaking in

Docket Nos. RM06–8–000 and AD05–7–

000, and the proceedings in each RTO

region to implement the Final Rule

issued in those dockets on July 20, 2006.

APPA notes, however, that the

Commission has not proposed in this

docket to exempt RTOs from the

provisions of the NOPR. Rather, APPA

notes, departures from the pro forma

OATT, including departures in RTO

OATTs, must be justified under the

‘‘consistent with or superior to’’

standard. APPA argues that the

Commission should apply this standard

to long-term transmission rights, as well

as to the other terms and conditions of

OATT transmission service that RTOs

provide.

Commission Determination

107. In Order No. 888, the

Commission gave public utilities the

right to reserve existing transmission

capacity needed for native load growth

reasonably forecasted within the

utility’s current planning horizon. The

Commission also allowed transmission

providers to restrict rollover rights

based on reasonably forecasted need at

the time the contract is executed. We

continue to believe these protections for

native load are appropriate and do not

eliminate them in this Final Rule, as

suggested by some commenters. We also

believe that the protection of native load

embodied in Order No. 888, as

enhanced by the reforms adopted in this

Final Rule, is consistent with FPA

section 217, which protects the

transmission rights of entities with

service obligations to end-users or a

distribution utility, to the extent

required to meet their service

obligations. The additional reforms

VerDate Aug<31>2005

18:17 Mar 14, 2007

Jkt 211001

proposed by commenters are not

necessary at this time to remedy undue

discrimination. We conclude that the

native load priority established in Order

No. 888 continues to strike the

appropriate balance between the

transmission provider’s need to meet its

native load obligations and the need of

other entities to obtain service from the

transmission provider to meet their own

obligations.

108. In response to comments

regarding reforms needed to ATC

calculation and transmission planning

to bring the native load priority policies

in line with FPA section 217, we believe

that the Commission’s reforms in this

Final Rule appropriately reflect the

transmission provider’s obligation to

serve native load. As discussed more

fully in the ATC and planning sections

below, the processes we adopt herein

are open, transparent and nondiscriminatory and assume that the

transmission provider is meeting its

obligations, including its native load

service obligation. We disagree with

Duke’s assertion that the reforms

proposed in the NOPR will result in a

reduction of the protection afforded

native or network load. Not only have

we reaffirmed the fundamental

protections for native load contained in

Order No. 888, but we have modified,

where appropriate, the pro forma OATT

to ensure that a transmission provider’s

obligations can be met consistent with

maintaining the reliability to existing

customers, including native load. For

example, we are eliminating the current

requirement to provide planning

redispatch over long periods of time

(e.g., 10–30 years) because it is

unnecessary to remedy undue

discrimination and can create problems

in forecasting system conditions

consistent with maintaining reliability

to native load customers.93

109. With regard to APPA’s comments

regarding long-term transmission rights

in organized markets, we note that the

Commission has issued its Final Rule in

Docket Nos. RM06–8–000 and AD05–7–

000.94 As discussed more fully in the

applicability section of this rulemaking,

and in response to APPA’s comments,

we reiterate that any departures from

the pro forma OATT proposed by an

ISO or an RTO must be ‘‘consistent with

or superior to’’ the pro forma OATT in

this Final Rule.

93 Proposals related to other reforms, such as

curtailments and rollovers, are discussed in the

sections below dealing with each of those issues.

94 See supra note 72.

PO 00000

Frm 00019

Fmt 4701

Sfmt 4700

12283

3. The Types of Transmission Services

Offered

110. In Order No. 888, the

Commission required all public utilities

to offer, on a non-discriminatory, openaccess basis, firm network service and

firm and non-firm point-to-point

service. In the NOPR, the Commission

proposed to retain these services and

did not propose to require transmission

providers to adopt a network contract

demand service, either as a replacement

for network or point-to-point service or

as a third category of service under the

OATT.

Comments

111. Several commenters support the

Commission’s proposal to retain the

current services in the pro forma OATT

and to not adopt contract demand

service.95 While APPA supports the

Commission’s proposal, it states that the

Commission should remain open to

individual public utility transmission

provider’s proposals to add ‘‘hybrid’’

service to the base network and pointto-point services.

112. Other commenters, such as AMPOhio and Nevada Companies, argue that

the Commission should require all

transmission providers to offer network

contract demand service. Nevada

Companies argue that the Commission’s

network designation process can

substantially interfere with State

jurisdiction over resource acquisition,

especially for transmission providers

that are required to purchase substantial

amounts of power to serve their retail

customers instead of relying primarily

on their own generation. Nevada

Companies reason that allowing

transmission providers to move to a

contract demand-based network service

would remove them from the dilemma

of being forced to make resource

procurement decisions that are

inconsistent with State requirements.

On reply, MidAmerican, Newmont

Mining, and Utah Municipals oppose

the suggestion that the contract demand

service should be made a mandatory

service offering in the pro forma OATT.

In its reply comments, Newmont Mining

states that, if the Commission is

inclined to provide some relief to allow

Nevada Companies to comply with both

the pro forma OATT and their Stateapproved resource plans, that relief

should come only after an investigation

of how similar problems are handled on

other systems and should be a narrowly

and carefully monitored exception to

the resource designation requirements.

95 E.g., MISO/PJM States, TVA, and Southern.

E:\FR\FM\15MRR2.SGM

15MRR2

12284

Federal Register / Vol. 72, No. 50 / Thursday, March 15, 2007 / Rules and Regulations

sroberts on PROD1PC70 with RULES

113. Alberta Intervenors argue that

undue discrimination is most likely to

occur in situations where there is a

single or dominant network customer

and that customer either has a dual

mandate for serving the network

customers or that customer has a ‘‘free

option’’ for procuring transmission.96

Alberta Intervenors recommend that the

Commission implement standardized

rules with respect to the ‘‘free option’’

concept while offering regional

flexibility to ensure the objectives of

open access and the absence of undue

discrimination continue to be advanced.

Alberta Intervenors also argue that,

despite the Commission’s proposal to

address undue discrimination against

transmission customers in attempting to

redirect to new receipt and delivery

points, undue discrimination remains a

concern since network customers retain

a flexibility of receipt and delivery

points that is not granted to third party

point-to-point customers. This

flexibility provided to the network

customer allows the use of the system

for activities known as ‘‘parking’’ 97 and

‘‘hubbing.’’ 98 Alberta Intervenors urge

the Commission to eliminate this unfair

competitive advantage under the OATT

by making a common service available

to all participants rather than differing

service for network customers, or

alternatively, by restricting the use of

96 Alberta Intervenors assert that the purchase of

point-to-point service by dominant network

customers results in an equal and offsetting

reduction to the network customer’s network

charges, resulting in a net cost of zero. They state

that point-to-point service is a net cost to all

competitors except the dominant network customer.

Thus, they argue, a dominant network customer can

buy point-to-point service for an extended period

and use this service for a limited number of hours

at little (or no) net cost compared to not purchasing

point-to-point service for an extended period. In

Alberta Intervenors’ view, this ‘‘free option’’

provides network customers with a competitive

advantage when reserving point-to-point service

because it enables the network customers to overconsume or buy excess point-to-point service than

they would if the true net cost were reflected.

Alberta Intervenors contend that such overconsumption reduces access to point-to-point

service for other customers.

97 Alberta Intervenors define ‘‘parking’’ as a

network customer reserving point-to-point service

using a network load point of delivery to purchase

energy that it intends to sell but where no buyer has

been identified at the time of the reservation. The

energy notionally reduces network load. Once a

buyer is found, the network customer completes the

sale by delivering the energy from freed-up

generation at a generation point of receipt to a

buyer’s point of delivery.

98 Alberta Intervenors define ‘‘hubbing’’ as a

practice very similar to ‘‘parking,’’ but involving

multiple buyers and sellers. The network customer

can reserve point-to-point transmission to purchase

energy from multiple sellers and to sell energy to

multiple buyers by creating a hub within its

network load. Alberta Intervenors explain that this

allows the network customer to organize purchases

and sales by physically matching the requirements

of multiple buyers and sellers.

VerDate Aug<31>2005

18:17 Mar 14, 2007

Jkt 211001

point-to-point services by the network

customer to exclude its use for

‘‘parking’’ and ‘‘hubbing.’’

114. MidAmerican states that in the

Western Interconnection, a utility’s

loads are not necessarily located within

a confined geographical boundary

served by a single transmission owner.

In these cases, MidAmerican argues,

neither network nor point-to-point

service under the current pro forma

OATT is suitable to serve those loads.

To remedy these shortcomings in

standard OATT service, MidAmerican

states that the Commission should

require the incorporation of dynamic

scheduling and long-term, seasonallyshaped, firm point-to-point as new

service offerings under the pro forma

OATT.

Commission Determination

115. The Commission will not alter

the types of services that we required in

Order No. 888. We continue to believe

that network and point-to-point services

are the appropriate base-line service

offerings in the OATT, and we will not

mandate that transmission providers

adopt new service offerings such as

network contract demand service.

Although the Commission has accepted

forms of network contract demand

service proposed by individual

transmission providers, and the service

may provide benefits to certain

customers, we do not believe the service

is necessary to remedy undue

discrimination. For example, the service

would require a departure from full

load-ratio pricing for network

customers, which may not be warranted

to the extent the transmission provider

plans its system to serve all native load.

However, while the Commission

concludes that it will not require all

transmission providers to offer this

service, in response to the arguments

raised by commenters such as AMPOhio and Nevada Companies, we

reiterate that the Commission already

has accepted forms of network contract

demand service and will continue to

entertain such proposals on a voluntary

basis from transmission providers.

116. The Commission also is not

persuaded by Alberta Intervenors’ and

MidAmerican’s arguments in support of

further alternative services under the

pro forma OATT. As with network

contract demand service, transmission

providers may propose such services if

appropriate for their region. We do not

believe mandating that such services be

provided by all transmission providers

is necessary at this time to prevent

undue discrimination.

PO 00000

Frm 00020

Fmt 4701

Sfmt 4700

4. Functional Unbundling

117. In Order No. 888, the

Commission chose to mandate

functional, rather than corporate (in

which a public utility’s transmission

and generation assets would be placed

in separate corporate entities),

unbundling of transmission and

generation services. The Commission

explained that functional unbundling

has three components:

1. A public utility must take

transmission services (including

ancillary services) for all of its new

wholesale sales and purchases of energy

under the same tariff of general

applicability as do others;

2. A public utility must state separate

rates for wholesale generation,

transmission, and ancillary services;

3. A public utility must rely on the

same electronic information network

that its transmission customers rely on

to obtain information about its

transmission system when buying or

selling power.99

118. In the years following Order No.

888, a number of public utilities

nonetheless underwent corporate

unbundling. Many of these entities did

so as a result of State-mandated

restructuring laws. Others did so for

corporate or tax reasons. Some entities

divested all of their generation assets to

a non-affiliate, while others simply

restructured internally to place the

generation assets in a different corporate

subsidiary than the transmission assets.

There remain, however, a significant

number of vertically-integrated public

utilities that operate under the

functional unbundling approach.

119. In the NOPR, we proposed to

preserve the functional unbundling

approach adopted in Order No. 888,

rather than impose a corporate or

structural unbundling requirement.

While the Commission expressed its

continued support for voluntary efforts

to adopt structural changes (such as

transmission-only companies, RTOs, or

other reforms), the Commission found

that the more intrusive and costly

corporate unbundling was not necessary

at this time. The Commission also

declined to mandate an independent

transmission coordinator for all

transmission providers. Though the

Commission has previously found that

such entities may be appropriate in

certain circumstances and we support

voluntary efforts to rely on them,100 the

99 Order No. 888 at 31,654.

100 See Duke Power, 113 FERC ¶ 61,288 (2005);

MidAmerican Energy Co., 113 FERC ¶ 61,274

(2005); see also Entergy Services, Inc., 110 FERC

61,295 (2005), order on clarification, 111 FERC

¶ 61,222 (2005), order conditionally approving

filing, 115 FERC ¶ 61,095 (2006).

E:\FR\FM\15MRR2.SGM

15MRR2

Federal Register / Vol. 72, No. 50 / Thursday, March 15, 2007 / Rules and Regulations

Commission concluded that there was

not a sufficient basis for requiring them

as a generic remedy for undue

discrimination.

Comments

120. Commenters generally support

the Commission’s proposal to retain

functional unbundling.101 APPA also

supports the Commission’s decision not

to mandate an independent

transmission coordinator for all public

utility transmission providers.

Similarly, Tacoma supports the

Commission’s decision to continue to

view participation in an RTO or ISO as

voluntary actions. While PJM and EPSA

would prefer a structural remedy, they

generally support the Commission’s

proposal to retain functional

unbundling. However, EPSA states that

given the Commission’s proposal to

continue to rely on functional

unbundling, it is critical, particularly in

those areas without organized markets,

that OATT rules regarding unbundled

transmission service be clear,

transparent, consistent, and rigorously

enforced. APPA states that it will be

vital to obtain the cooperation of State

regulators in each region where the

OATT reforms will be implemented to

ensure that the current functional

unbundling regime in fact is sufficient

to do the job.

121. E.ON and TVA express concern

that the Commission may yet choose a

structural remedy. E.ON urges the

Commission to look at the full depth

and breadth of its existing powers to

monitor and fully redress any abuses in

the allocation of transmission services

before considering structural

unbundling. Similarly, TVA notes that

the Commission already has the option

to impose a structural remedy on a caseby-case basis.102

Commission Determination

sroberts on PROD1PC70 with RULES

122. The Commission will, as

proposed in the NOPR, continue to

require functional—rather than

corporate or structural—unbundling. As

explained in the NOPR, for public

utilities that keep transmission and

generation assets in the same corporate

entity, the Commission has strict

Standards of Conduct that require the

separation of the utilities’ transmission

system operations and wholesale

101 E.g., Santee Cooper, LPPC, TVA, Tacoma,

Southern, MISO Transmission Owners, and E.ON.

102 Some commenters argue that adoption of the

‘‘open dispatch’’ proposals raised by commenters

such as Chandley-Hogan and PJM would constitute

a departure from functional unbundling. We

discuss the ‘‘open dispatch’’ and similar proposals

in section V.C below.

VerDate Aug<31>2005

18:17 Mar 14, 2007

Jkt 211001

marketing functions.103 These rules

require that employees engaged in

transmission functions operate

separately from employees of energy

affiliates and marketing affiliates. A

number of information sharing

restrictions also apply, which prohibit

transmission providers from allowing

employees of their energy and

marketing affiliates to obtain access to

transmission or customer information,

except via OASIS.

123. The Commission aggressively

enforces the Standards of Conduct and,

as referenced by APPA, cooperates with

State regulators to ensure that the

functional unbundling regime is

sufficient to prevent undue

discrimination. The Commission’s

Office of Enforcement is well-suited to

investigate potential violations of the

Standards of Conduct and to propose

remedies, including structural remedies

if necessary, to ensure that the

separation of functions and information

restrictions are fully implemented. We

believe that the increased clarity and

transparency adopted in other parts of

this Final Rule, when coupled with the

Standards of Conduct rules and our

rigorous enforcement program, will

ensure that the functional unbundling

requirement will serve its original

purpose.

C. Applicability of the Final Rule

1. Non-ISO/RTO Public Utility

Transmission Providers

124. In the NOPR, the Commission

proposed to apply the Final Rule to all

public utility transmission providers,

including those that are approved ISOs

and RTOs. With respect to non-ISO/

RTO transmission providers, the

Commission proposed to require all

103 The rules were first established in Order No.

889. See Order No. 889 at 31,595. The Standards

of Conduct rules were later replaced by a broader

set of rules adopted in Order No. 2004, which were

subsequently vacated in part by the United States

Court of Appeals pending remand proceedings

before the Commission. See Standards of Conduct

for Transmission Providers, Order No. 2004, 68 FR

69134 (Dec. 11, 2003), FERC Stats. & Regs. ¶ 31,155

(2003), order on reh’g, Order No. 2004–A, 69 FR

23562 (Apr. 29, 2004), FERC Stats. & Regs. ¶ 31,161

(2004), order on reh’g, Order No. 2004–B, 69 FR

48371 (Aug. 10, 2004), FERC Stats. & Regs. ¶ 31,166

(2004), order on reh’g, Order No. 2004–C, 70 FR 284

(Jan. 4, 2005), FERC Stats. & Regs. ¶ 31,172 (2005),

order on reh’g, Order No. 2004–D, 110 FERC

¶ 61,320 (2005), vacated, National Fuel, 468 F.3d

831. The Commission has issued an interim rule

promulgating temporary regulations consistent with

the Court’s decision and initiated a further

rulemaking to propose permanent regulations. See

Standards of Conduct for Transmission Providers,

Order No. 690, 72 FR 2427 (Jan. 19, 2007), FERC

Stats. & Regs. ¶ 31,327 (2007); Standards of Conduct

for Transmission Providers, Notice of Proposed

Rulemaking, 72 FR 3958 (Jan. 29, 2007), FERC Stats.

& Regs. ¶ 32,611 (2007) (Standards of Conduct

NOPR).

PO 00000

Frm 00021

Fmt 4701

Sfmt 4700

12285

such transmission providers to submit

FPA section 206 compliance filings,

within 60 days after the publication of

the Final Rule in the Federal Register,

that contain the non-rate terms and

conditions set forth in the Final Rule.

The Commission also acknowledged

that certain non-rate terms and

conditions, such as Attachment C

(relating to the transmission provider’s

ATC calculation methodology) and

Attachment K (relating to the

transmission provider’s transmission

planning process), may require more

than 60 days to prepare and sought

comment on an appropriate time period

in which to require the submission of

these attachments.

125. Following their FPA section 206

compliance filings, the Commission

proposed that transmission providers

could submit filings under FPA section

205 proposing rates for the services

provided for in the tariff, as well as nonrate terms and conditions that differ

from those set forth in the Final Rule if

those provisions are ‘‘consistent with or

superior to’’ the pro forma OATT.

Comments

126. Several commenters ask the

Commission to clarify and/or revise the

proposal for dealing with previouslyapproved provisions that depart from

the existing (Order No. 888) pro forma

OATT. APPA contends that after this

multi-phase rulemaking (NOI/NOPR/

Final Rule) to revise the OATT, the

Commission should hold those public

utility transmission providers that

propose non-rate terms and conditions

differing from the new pro forma OATT

to a high standard of proof under the

‘‘consi

This text is long and has been trimmed here. Open the source document for the complete record.

This is a copy of a public record, reproduced as it was published. It is not legal advice, and it may not be the version a court would rely on. Check the official source before you cite it.

A word about cookies

We need a few to keep you signed in and the library working. The rest help us see which pages people use and where they get stuck. They stay off unless you say yes.

Federal Energy Regulatory Commission | Frix