Federal Register / Vol. 72, No. 60 / Thursday, March 29, 2007 / Notices

Agency decision

Ask Donna

What actually matters in this document.

Text

14800

Federal Register / Vol. 72, No. 60 / Thursday, March 29, 2007 / Notices

the original and the number of copies

provided by the Commission’s

regulations to: The Secretary, Federal

Energy Regulatory Commission, 888

First Street, NE., Washington, DC 20426.

A copy of any motion to intervene must

also be served upon each representative

of the Applicant specified in the

particular application.

t. Agency Comments—Federal, state,

and local agencies are invited to file

comments on the described application.

A copy of the application may be

obtained by agencies directly from the

Applicant. If an agency does not file

comments within the time specified for

filing comments, it will be presumed to

have no comments. One copy of an

agency’s comments must also be sent to

the Applicant’s representatives.

Philis J. Posey,

Acting Secretary.

[FR Doc. E7–5766 Filed 3–28–07; 8:45 am]

BILLING CODE 6717–01–P

DEPARTMENT OF ENERGY

Federal Energy Regulatory

Commission

Notice of Intent To File License

Application, Filing of Pre-Application

Document, and Approval of Use of the

Traditional Licensing Process

jlentini on PROD1PC65 with NOTICES

March 23, 2007.

a. Type of Filing: Notice of Intent to

File License Application and Request to

Use the Traditional Licensing Process.

b. Project No.: 12771–000.

c. Dated Filed: February 5, 2007.

d. Submitted By: Great Bear

Hydropower, Inc.

e. Name of Project: Upper Falls

Hydroelectric Project.

f. Location: The project would be

located at the existing Riverside and

Kendrick-Davis Dams on the Mascoma

River in Grafton County, New

Hampshire. The project would not

occupy United States lands.

g. Filed Pursuant to: 18 CFR 5.3 of the

Commission’s regulations.

h. Applicant Contact: Mr. Terry

McDonnell, President, Great Bear

Hydropower, Inc., 15 Brigham Hill

Road, Norwich, VT 05055, (802) 649–

9099.

i. FERC Contact: John Ramer, (202)

502–8969 or john.ramer@ferc.gov.

j. Great Bear Hydropower, Inc. filed

its request to use the Traditional

Licensing Process on February 5, 2007.

Great Bear Hydropower, Inc. filed

public notice of its request on February

20, 2007. In a letter dated March 16,

2007, the Director of the Office of

Energy Projects approved Great Bear

VerDate Aug<31>2005

17:20 Mar 28, 2007

Jkt 211001

Hydropower, Inc.’s request to use the

Traditional Licensing Process.

k. With this notice, we are initiating

informal consultation with: (a) The U.S.

Fish and Wildlife Service under section

7 of the Endangered Species Act; and (b)

the New Hampshire State Historic

Preservation Officer, as required by

section 106, National Historical

Preservation Act, and the implementing

regulations of the Advisory Council on

Historic Preservation at 36 CFR 800.2.

l. Great Bear Hydropower, Inc. filed a

Pre-Application Document (PAD;

including a proposed process plan and

schedule) with the Commission,

pursuant to 18 CFR 5.6 of the

Commission’s regulations.

m. A copy of the PAD is available for

review at the Commission in the Public

Reference Room or may be viewed on

the Commission’s Web site (http://

www.ferc.gov), using the ‘‘eLibrary’’

link. Enter the docket number,

excluding the last three digits in the

docket number field to access the

document. For assistance, contact FERC

Online Support at

FERCONlineSupport@ferc.gov or toll

free at 1–866–208–3676, or for TTY,

(202) 502–8659. A copy is also available

for inspection and reproduction at the

address in paragraph h.

Register online at http://ferc.gov/docsfiling/esubscription.asp to be notified

via e-mail of new filing and issuances

related to this or other pending projects.

For assistance, contact FERC Online

Support.

Philis Posey,

Acting Secretary.

[FR Doc. E7–5767 Filed 3–28–07; 8:45 am]

BILLING CODE 6717–01–P

DEPARTMENT OF ENERGY

Federal Energy Regulatory

Commission

Notice of Termination of License by

Implied Surrender and Soliciting

Comments, Protests, and Motions To

Intervene

March 23, 2007.

Take notice that the following

hydroelectric proceeding has been

initiated by the Commission:

a. Type of Proceeding: Termination of

license by implied surrender.

b. Project No.: 9300–017.

c. Date Initiated: March 21, 2007.

d. Licensee: The licensee is James

Lichoulas Jr.

e. Name and Location of Project: The

constructed 346-kilowatt Appleton

Trust Project is located on the Hamilton

PO 00000

Frm 00034

Fmt 4703

Sfmt 4703

Canal in Middlesex County,

Massachusetts.

f. Filed Pursuant to: 18 CFR 6.4.

g. Licensee Contact Information: Mr.

James Lichoulas, Jr., 57 Mill Street,

Woburn, MA 01801.

h. FERC Contact: Tom Papsidero,

(202) 502–6002.

i. Deadline for filing comments,

protests, and motions to intervene: April

23, 2007.

All documents (original and eight

copies) should be filed with Philis J.

Posey, Acting Secretary, Federal Energy

Regulatory Commission, 888 First

Street, NE., Washington, DC 20426.

Comments, protests and interventions

may be filed electronically via the

Internet in lieu of paper; see 18 CFR

385.2001(a)(1)(iii) and the instructions

on the Commission’s Web site under the

‘‘e-Filing’’ link. The Commission

strongly encourages electronic filings.

Please include the project number (P–

9300–017) on any documents or

motions filed.

The Commission’s Rules of Practice

and Procedure require all intervenors

filing documents with the Commission

to serve a copy of that document on

each person in the official service list

for the project. Further, if an intervenor

files comments or documents with the

Commission relating to the merits of an

issue that may affect the responsibilities

of a particular resource agency, they

must also serve a copy of the document

on that resource agency.

j. Description of Existing Facilities:

The constructed project consists of the

following existing facilities: (1) An

intake off the Hamilton Canal; (2) two

11-foot-wide and 160-foot-long open

masonry flumes; (3) an 11-foot-wide and

20-foot-long steel penstock which

funnels the water into; (4) an existing

turbine chamber which contains two

turbine-generators with an installed

capacity of 346 kW; (5) two stone

masonry tailraces; (6) 480-volt generator

leads; (7) a 0.48/13.8-kV transformer; (8)

a 300-foot-long, 480-volt underground

cable; and (9) appurtenant facilities.

k. Description of Proceeding: 18 CFR

6.4 of the Commission’s regulations

provides, among other things, that it is

deemed to be the intent of a licensee to

surrender a license, if the licensee

abandons a project for a period of three

years.

A license for the Appleton Trust

Project was issued by Order Issuing

License (Minor Project) on July 18, 1986

(36 FERC ¶ 62,047). The project has not

operated regularly since November 1994

and the licensee, James Lichoulas, Jr.,

has not made necessary repairs to

resume operations. By letter of March

17, 2003, the Commission’s Division of

E:\FR\FM\29MRN1.SGM

29MRN1

jlentini on PROD1PC65 with NOTICES

Federal Register / Vol. 72, No. 60 / Thursday, March 29, 2007 / Notices

Dam Safety and Inspections, New York

Regional Office directed the licensee to

resume project operation by May 30,

2003, and to provide a status report to

that office by June 15, 2003. The

licensee did not comply. By letter of

September 23, 2004, Commission staff

informed the licensee that the project

was considered abandoned and that the

Commission may terminate the license

for the project under an implied

surrender proceeding. In this letter, the

licensee was given the opportunity to

voluntarily surrender the license.

On December 6, 2004, the licensee

filed a response to Commission staff’s

September 23, 2004 letter, stating that

the reason repairs had not been done at

the project was that the Appleton Mills

area had been undergoing a major

selective demolition of 400,000 of its

600,000 square feet and that an asbestos

removal and clean up process had gone

on for several years. In the December 6,

2004 filing, the licensee stated that

necessary planning was underway for

the reconstruction of the equipment and

wheelhouse. The licensee further stated

that it was his plan to develop a full

scope of work by early March 2005 and

that he would forward an outline of the

scope with a full timeline projection to

the Commission. However, a scope of

work was never filed. On July 26, 2006,

the City of Lowell, Massachusetts (City)

filed a letter with the Commission

stating that the City had acquired the

parcel of land on which the licensed

Appleton Trust Project is located.

To date, the licensee has not made the

necessary repairs to resume operations

at the project and the project is hereby

considered abandoned.

l. Location of the Order: A copy of the

order is available for inspection and

reproduction at the Commission in the

Public Reference Room or may be

viewed on the Commission’s Web site at

http://www.ferc.gov using the

‘‘eLibrary’’ link. Enter the docket

number excluding the last three digits in

the docket number field to access the

document. For assistance, call toll-free

1–866–208–3676 or e-mail

FERCOnlineSupport@ferc.gov. For TTY,

call (202) 502–8659.

m. Individuals desiring to be included

on the Commission’s mailing list should

so indicate by writing to the Secretary

of the Commission.

n. Comments, Protests, or Motions to

Intervene—Anyone may submit

comments, a protest, or a motion to

intervene in accordance with the

requirements of Rules of Practice and

Procedure, 18 CFR 385.210, 385.211,

385.214. In determining the appropriate

action to take, the Commission will

consider all protests or other comments

VerDate Aug<31>2005

17:20 Mar 28, 2007

Jkt 211001

filed, but only those who file a motion

to intervene in accordance with the

Commission’s Rules may become a

party to the proceeding. Any comments,

protests, or motions to intervene must

be received on or before the specified

comment date for the proceeding.

Comments, protests and interventions

may be filed electronically via the

Internet in lieu of paper; See 18 CFR

385.2001 (a)(1)(iii) and the instructions

on the Commission’s Web site under ‘‘efiling’’ link. The Commission strongly

encourages electronic filing.

o. Filing and Service of Responsive

Documents—Any filings must bear in

all capital letters the title

‘‘COMMENTS’’, ‘‘PROTEST’’, or

‘‘MOTION TO INTERVENE’’, and

‘‘RECOMMENDATIONS FOR TERMS

AND CONDITIONS’’, as applicable, and

the Project Number of the proceeding.

Any of the above-named documents

must be filed by providing the original

and the number of copies provided by

the Commission’s regulations to: The

Secretary, Federal Energy Regulatory

Commission, 888 First Street, NE.,

Washington, DC 20426. An additional

copy must be sent to Director, Division

of Hydropower Administration and

Compliance, Federal Energy Regulatory

Commission, at the above-mentioned

address.

p. Agency Comments—Federal, state,

and local agencies are invited to file

comments on the described proceeding.

If an agency does not file comments

within the time specified for filing

comments, it will be presumed to have

no comments.

Philis J. Posey,

Acting Secretary.

[FR Doc. E7–5771 Filed 3–28–07; 8:45 am]

BILLING CODE 6717–01–P

14801

Commission Meeting Room. All

interested persons are invited to attend.

A further notice with a detailed agenda

will be issued in advance of the

conference.

Transcripts of the conference will be

immediately available from Ace

Reporting Company (202–347–3700 or

1–800–336–6646) for a fee. They will be

available for the public on the

Commission’s eLibrary system seven

calendar days after FERC receives the

transcript.

A free webcast of this event will be

available through www.ferc.gov. Anyone

with Internet access who desires to view

this event can do so by navigating to

www.ferc.gov’s Calendar of Events and

locating this event in the Calendar. The

event will contain a link to its webcast.

The Capitol Connection provides

technical support for the free webcasts.

It also offers access to this event via

television in the DC area and via phone

bridge for a fee. If you have any

questions, visit http://

www.CapitolConnection.org or contact

Danelle Perkowski or David Reininger at

703–993–3100.

Commission conferences are

accessible under section 508 of the

Rehabilitation Act of 1973. For

accessibility accommodations please

send an e-mail to accessibility@ferc.gov

or call toll free 1–866–208–3372 (voice)

or 202–208–1659 (TTY), or send a fax to

202–208–2106 with the required

accommodations.

For more information about this

conference, please contact: Clara

Brooks, Office of Energy Markets and

Reliability, Federal Energy Regulatory

Commission, 888 First Street, NE.,

Washington, DC 20426, (202) 502–8357,

Clara.Brooks@ferc.gov.

Philis J. Posey,

Acting Secretary.

[FR Doc. E7–5755 Filed 3–28–07; 8:45 am]

DEPARTMENT OF ENERGY

BILLING CODE 6717–01–P

Federal Energy Regulatory

Commission

ENVIRONMENTAL PROTECTION

AGENCY

[Docket No. AD07–7–000]

Conference on Competition in

Wholesale Power Markets; Notice of

Conference

March 23, 2007.

Take notice that on May 8, 2007, a

second conference will be held at the

Federal Energy Regulatory Commission

(Commission or FERC) to examine the

state of competition in wholesale power

markets. This second conference will be

held from 9 a.m. to 4 p.m. (EST) at the

Federal Energy Regulatory

Commission’s offices, 888 First Street,

NE., Washington, DC 20426, in the

PO 00000

Frm 00035

Fmt 4703

Sfmt 4703

[FRL–8293–5]

Proposed Consent Decree, Clean Air

Act Citizen Suit

AGENCY: Environmental Protection

Agency (EPA).

ACTION: Notice of Proposed Consent

Decree; Request for Public Comment.

SUMMARY: In accordance with section

113(g) of the Clean Air Act, as amended

(‘‘CAA’’ or ‘‘Act’’), 42 U.S.C. 7413(g),

notice is hereby given of a proposed

consent decree to address a lawsuit filed

E:\FR\FM\29MRN1.SGM

29MRN1