rwilkins on PROD1PC63 with NOTICES (2006)

Agency decision

Ask Donna

What actually matters in this document.

Text

rwilkins on PROD1PC63 with NOTICES

36330

Federal Register / Vol. 71, No. 122 / Monday, June 26, 2006 / Notices

the proposed project in accordance with

the National Environmental Policy Act.

DATES: Written comments are due to the

address below no later than: July 26,

2006. Comments may also be made at an

EIS scoping meeting to be held on July

11, 2006 at the address below.

ADDRESSES: Comments and suggestions

on the proposed scope of the Draft EIS,

and requests to be placed on the project

mailing list, may be mailed to

Bonneville Power Administration,

Public Affairs Office—DKC–7, P.O. Box

14428, Portland, OR, 97293–4428. Or,

you may fax them to (503) 230–3285;

submit them on-line at http://

www.bpa.gov/comment; or e-mail them

to comment@bpa.gov. You may also call

us toll-free with your comments at (800)

622–4519. Please reference the Lyle

Falls Fish Passage Project with your

comments.

On Tuesday, July 11, 2006, a scoping

meeting will be held from 7 p.m. to 9

p.m. at the Lyle Lions Community

Center, 5th Street and State Highway 14,

Lyle, Washington. At this meeting, we

will provide information about the

project, including maps, and have

members of the project team available to

answer questions. We look forward to

accepting oral and written comments

offered on the project.

We also invite interested parties to

attend a site visit that is planned for 3

p.m., Tuesday, July 11, 2006, to view

the proposed project site. To get to the

project site from State Highway 14 in

the town of Lyle, take Route 142 north

for about two miles, then turn west onto

Fishers Hill Road. Cross the Klickitat

River and follow the road for less than

one-fourth mile. Make a right onto an

unpaved road and proceed about seven

hundred feet. There will be signs

provided to help direct traffic.

FOR FURTHER INFORMATION, CONTACT: Carl

J. Keller, Environmental Project

Manager, Bonneville Power

Administration, KEC–4, P.O. Box 3621,

Portland, Oregon, 97208–3621; toll-free

telephone number (800) 622–4519; fax

number (503) 230–5699; e-mail address

cjkeller@bpa.gov.

SUPPLEMENTARY INFORMATION:

Background: BPA is a federal power

marketing agency that markets power

from many of the federal dams in the

Columbia River Basin, and has a duty to

protect, mitigate, and enhance fish

affected by the construction and

operation of those dams. The Yakama

Nation, through the Northwest Power

Planning and Conservation Council, has

proposed that BPA fund the

reconstruction of the existing fish

passage facility as part of those

mitigation responsibilities. The

VerDate Aug<31>2005

17:00 Jun 23, 2006

Jkt 208001

proposed project in on the Klickitat

River in Klickitat County, Washington

in T3N, R12E, west half of Section 25

and east half of Section 26. The location

is about two miles upriver of the

confluence of the Klickitat River with

the Columbia River. Currently the Lyle

Falls Fishway does not meet federal and

state fish passage criteria for migrating

adult salmon. Design flows in the

existing fishway result in poor attraction

flows throughout the year, and

significantly reduced attraction flows

during periods of low river discharge

(August—September). During these

periods of low flows the natural falls

become an even greater obstruction to

salmon and steelhead, resulting in

lowered passage above Lyle Falls.

Proposed Action: The proposed action

is to improve and expand the Lyle Falls

Fishway. The project would be designed

to safely and effectively allow adult fish

to move through the existing Lyle Falls

into the upper reaches of the Klickitat

River, and would improve the adult

trapping capabilities at the fishway.

Improvements would include

reconstructing and lengthening the

fishway and trash racks, upgrading the

adult trapping facility, and adding a

Passive Integrated Transponder (PIT) tag

detector and video monitor. The adult

trap would facilitate the collection of

fish for monitoring and broodstock

purposes.

Process to Date: The Yakama Nation

has proposed the project to support its

fish passage and fish conservation

initiatives. At a meeting held in March

2006, the Northwest Power and

Conservation Council recommended

that BPA fund the preparation of an EIS

to focus on fish passage and monitoring

at Lyle Falls.

Alternatives Proposed for

Consideration: BPA has identified two

alternatives for examination in the DEIS.

They are the proposed action, described

above, and no action. We will use the

no-action alternative to explore the

environmental impacts of not improving

the existing ladder and passage facilities

at Lyle Falls. We will also consider in

the Draft EIS other reasonable

alternatives presented to us during the

scoping process.

Public Participation and

Identification of Environmental Issues:

BPA has established a 30-day scoping

period during which interested and

affected landowners, concerned

citizens, tribes, special interest groups,

government agencies, and any other

interested parties are invited to

comment on the scope of the proposed

EIS. Scoping will help BPA ensure that

a full range of issues related to this

proposal is addressed in the EIS, and

PO 00000

Frm 00017

Fmt 4703

Sfmt 4703

also will help identify significant or

potentially significant impacts that may

result from the proposed project.

Environmental issues identified to date

include potential conflicts with the

Klickitat Wild and Scenic River

designation, use of explosives during

construction, impacts to archaeological

and historic resources, impacts to

threatened and endangered species, and

water quality impacts.

When completed, the Draft EIS will be

circulated for public and agency review

and comment; BPA will hold at least

one public comment meeting for the

Draft EIS. BPA will consider and

respond in the Final EIS to comments

received on the Draft EIS. BPA’s

subsequent decision will be

documented in a publicly available

Record of Decision.

Maps and further information are

available from BPA at the address

above.

Issued in Portland, Oregon, on June 20,

2006.

Stephen J. Wright,

Administrator and Chief Executive Officer.

[FR Doc. E6–9999 Filed 6–23–06; 8:45 am]

BILLING CODE 6450–01–P

DEPARTMENT OF ENERGY

Federal Energy Regulatory

Commission

Combined Notice of Filings #1

June 14, 2006.

Take notice that the Commission

received the following electric corporate

filings:

Docket Numbers: EC06–99–000.

Applicants: Tor Power, LLC; Tyr

Energy, LLC; Lincoln Generating

Facility, LLC; Green Country Energy,

LLC.

Description: Tyr Energy, LLC, Green

Country Energy, LLC et al. submit an

amendment to their application to

provide a description of their

reorganization.

Filed Date: 06/06/2006.

Accession Number: 20060609–0045.

Comment Date: 5 p.m. Eastern Time

on Friday, June 23, 2006.

Take notice that the Commission

received the following electric rate

filings:

Docket Numbers: ER02–298–003;

EL05–111–000.

Applicants: Thompson River Co-Gen,

LLC.

Description: Thompson River Co-Gen,

LLC submits its revised updated market

power analysis to include the generation

power market screens.

Filed Date: 05/30/2006.

E:\FR\FM\26JNN1.SGM

26JNN1

rwilkins on PROD1PC63 with NOTICES

Federal Register / Vol. 71, No. 122 / Monday, June 26, 2006 / Notices

Accession Number: 20060606–0453.

Comment Date: 5 p.m. Eastern Time

on Tuesday, June 20, 2006.

Docket Numbers: ER03–534–002.

Applicants: Ingenco Wholesale

Power, L.L.C.

Description: Ingenco Wholesale

Power, LLC submits its triennial market

power update analysis pursuant to

Commission order issued 3/24/03.

Filed Date: 04/27/2006.

Accession Number: 20060427–5031.

Comment Date: 5 p.m. Eastern Time

on Wednesday, June 21, 2006.

Docket Numbers: ER03–774–003.

Applicants: Eagle Energy Partners I,

L.P.

Description: Eagle Energy Partners I,

LP submits its updated power market

analysis pursuant to the Commission’s

order issued 6/11/03.

Filed Date: 06/12/2006.

Accession Number: 20060614–0110.

Comment Date: 5 p.m. Eastern Time

on Monday, July 3, 2006.

Docket Numbers: ER03–796–004.

Applicants: Katahdin Paper Company

LLC.

Description: Katahdin Paper Co LLC

submits its triennial market power

analysis in compliance with

Commission’s order.

Filed Date: 06/12/2006.

Accession Number: 20060614–0109.

Comment Date: 5 p.m. Eastern Time

on Monday, July 3, 2006.

Docket Numbers: ER04–805–005.

Applicants: Wabash Valley Power

Association, Inc.

Description: Wabash Valley Power

Association Inc submits its notice of

non-material change in status in

compliance with the requirements

adopted by FERC in Order 652.

Filed Date: 05/30/2006.

Accession Number: 20060602–0332.

Comment Date: 5 p.m. Eastern Time

on Tuesday, June 20, 2006.

Docket Numbers: ER05–1502–003.

Applicants: California Independent

System Operator Corporation.

Description: California Independent

System Operator Corp submits its

compliance filing pursuant to FERC’s 5/

12/06 Order.

Filed Date: 06/12/2006.

Accession Number: 20060614–0112.

Comment Date: 5 p.m. Eastern Time

on Monday, July 3, 2006.

Docket Numbers: ER06–436–001.

Applicants: Avista Corporation.

Description: Avista Corporation

submits Non-Conforming Agreements

under its OATT, Volume 8 consisting of

twelve Network Integration

Transmission Service Agreements with

Bonneville Power Administration.

VerDate Aug<31>2005

17:00 Jun 23, 2006

Jkt 208001

Filed Date: 06/09/2006.

Accession Number: 20060614–0080.

Comment Date: 5 p.m. Eastern Time

on Friday, June 30, 2006.

Docket Numbers: ER06–723–002.

Applicants: California Independent

System Operator Corporation.

Description: California Independent

System Operator Corp submits its

revised Interim Reliability Requirements

Program pursuant to FERC’s 5/12/06

Order.

Filed Date: 06/12/2006.

Accession Number: 20060614–0111.

Comment Date: 5 p.m. Eastern Time

on Monday, July 3, 2006.

Docket Numbers: ER06–731–002.

Applicants: Midwest Independent

Transmission System Operator, Inc.

Description: Midwest Independent

Transmission System Operator, Inc

submits revisions to Module D of its

OAT&EM Tariff.

Filed Date: 06/08/2006.

Accession Number: 20060612–0215.

Comment Date: 5 p.m. Eastern Time

on Thursday, June 29, 2006.

Docket Numbers: ER06–959–001.

Applicants: Vermont Electric

Cooperative, Inc.

Description: Vermont Electric

Cooperative, Inc. submits a letter

clarifying its 5/24/06 letter and a list of

the tariffs that should be withdrawn,

pursuant to Commission’s amendment

to section 201(f) of the Federal Power

Act.

Filed Date: 05/26/2006.

Accession Number: 20060526–5008.

Comment Date: 5 p.m. Eastern Time

on Wednesday, June 21, 2006.

Docket Numbers: ER06–1118–000.

Applicants: ECP Energy, LLC.

Description: ECP Energy, LLC submits

an application for order accepting initial

tariff, waiving regulations and granting

blanket approvals.

Filed Date: 06/08/2006.

Accession Number: 20060612–0216.

Comment Date: 5 p.m. Eastern Time

on Thursday, June 29, 2006.

Docket Numbers: ER06–1119–000.

Applicants: San Diego Gas & Electric

Company.

Description: San Diego Gas & Electric

Co submits First Revised Sheet 130 et al

to Rate Schedule FERC 14, Reliability

Must Run Service Agreement with

California Independent System Operator

Corp.

Filed Date: 06/08/2006.

Accession Number: 20060614–0071.

Comment Date: 5 p.m. Eastern Time

on Thursday, June 29, 2006.

Docket Numbers: ER06–1120–000.

Applicants: Midwest Independent

Transmission System Operator, Inc.

PO 00000

Frm 00018

Fmt 4703

Sfmt 4703

36331

Description: Midwest Independent

Transmission System Operator, Inc

supplements its 3/10/06 filing with

signature pages, Original Sheet Number

39.

Filed Date: 06/08/2006.

Accession Number: 20060614–0072.

Comment Date: 5 p.m. Eastern Time

on Thursday, June 29, 2006.

Docket Numbers: ER06–1121–000.

Applicants: American Electric Power

Service Corporation; Ohio Power

Company.

Description: Ohio Power Co submits

its notice of cancellation of its Amended

Interconnection Agreement and

Operation Agreement, Second Revised

Service Agreement 433, Electric Tariff

Third Revised Volume 6, with Lawrence

Energy Center, LLC.

Filed Date: 06/09/2006.

Accession Number: 20060614–0073.

Comment Date: 5 p.m. Eastern Time

on Friday, June 30, 2006.

Docket Numbers: ER06–1122–000.

Applicants: High Trail Wind Farm,

LLC.

Description: High Trail Wind Farm,

LLC submits a petition for order

accepting market-based rate schedule

for filing and granting waivers and

blanket approvals.

Filed Date: 06/09/2006.

Accession Number: 20060614–0074.

Comment Date: 5 p.m. Eastern Time

on Friday, June 30, 2006.

Docket Numbers: ER06–1123–000.

Applicants: American Electric Power

System; Ohio Power Company.

Description: Ohio Power Co submits

its notice of cancellation of its Amended

Interconnection Agreement and

Operation Agreement, Second Revised

Service Agreement 516, Electric Tariff

Third Revised Volume 6, with Lawrence

Energy Center, LLC.

Filed Date: 06/09/2006.

Accession Number: 20060614–0075.

Comment Date: 5 p.m. Eastern Time

on Friday, June 30, 2006.

Docket Numbers: ER06–1124–000.

Applicants: Kentucky Utilities

Company.

Description: Kentucky Utilities Co

submits a request for an extension of its

contract term for an Interconnection

Agreement with Eastern Kentucky

Power Cooperative.

Filed Date: 06/09/2006.

Accession Number: 20060614–0090.

Comment Date: 5 p.m. Eastern Time

on Friday, June 30, 2006.

Any person desiring to intervene or to

protest in any of the above proceedings

must file in accordance with Rules 211

and 214 of the Commission’s Rules of

Practice and Procedure (18 CFR 385.211

and 385.214) on or before 5 p.m. Eastern

E:\FR\FM\26JNN1.SGM

26JNN1

36332

Federal Register / Vol. 71, No. 122 / Monday, June 26, 2006 / Notices

Time on the specified comment date. It

is not necessary to separately intervene

again in a subdocket related to a

compliance filing if you have previously

intervened in the same docket. Protests

will be considered by the Commission

in determining the appropriate action to

be taken, but will not serve to make

protestants parties to the proceeding.

Anyone filing a motion to intervene or

protest must serve a copy of that

document on the Applicant. In reference

to filings initiating a new proceeding,

interventions or protests submitted on

or before the comment deadline need

not be served on persons other than the

Applicant.

The Commission encourages

electronic submission of protests and

interventions in lieu of paper, using the

FERC Online links at http://

www.ferc.gov. To facilitate electronic

service, persons with Internet access

who will eFile a document and/or be

listed as a contact for an intervenor

must create and validate an

eRegistration account using the

eRegistration link. Select the eFiling

link to log on and submit the

intervention or protests.

Persons unable to file electronically

should submit an original and 14 copies

of the intervention or protest to the

Federal Energy Regulatory Commission,

888 First St. NE., Washington, DC

20426.

The filings in the above proceedings

are accessible in the Commission’s

eLibrary system by clicking on the

appropriate link in the above list. They

are also available for review in the

Commission’s Public Reference Room in

Washington, DC. There is an

eSubscription link on the Web site that

enables subscribers to receive e-mail

notification when a document is added

to a subscribed dockets(s). For

assistance with any FERC Online

service, please e-mail

FERCOnlineSupport@ferc.gov. or call

(866) 208–3676 (toll free). For TTY, call

(202) 502–8659.

Magalie R. Salas,

Secretary.

[FR Doc. E6–9978 Filed 6–23–06; 8:45 am]

BILLING CODE 6717–01–P

DEPARTMENT OF ENERGY

rwilkins on PROD1PC63 with NOTICES

Western Area Power Administration

Desert Southwest Customer Service

Region-Rate Order No. WAPA–127

AGENCY: Western Area Power

Administration, DOE.

VerDate Aug<31>2005

17:00 Jun 23, 2006

Jkt 208001

ACTION: Notice of Order Concerning

Network Integration Transmission and

Ancillary Services Rates.

SUMMARY: The Deputy Secretary of

Energy confirmed and approved Rate

Order No. WAPA–127 and Rate

Schedules PD–NTS2 and INT–NTS2,

placing rates for Network Integration

Transmission Service (Network Service)

for the Parker-Davis Project (PDP) and

the Pacific Northwest-Pacific Southwest

Intertie Project (Intertie) of the Western

Area Power Administration (Western)

into effect on an interim basis. The

Deputy Secretary of Energy also

confirmed Rate Schedules DSW–SD2,

DSW–RS2, DSW–FR2, DSW–EI2, DSW–

SPR2, and DSW–SUR2, placing

ancillary services rates from the PDP,

Boulder Canyon Project (BCP), Central

Arizona Project (CAP), and that part of

the Colorado River Storage Project

(CRSP) located in the Western Area

Lower Colorado (WALC) Balancing

Authority and Transmission Operations

Area (BATO) into effect on an interim

basis. The provisional rates will be in

effect until the Federal Energy

Regulatory Commission (Commission)

confirms, approves, and places them

into effect on a final basis or until they

are replaced by other rates. The

provisional rates will provide sufficient

revenue to pay all annual costs,

including interest expense, and repay

power investment and irrigation aid,

within the allowable periods.

DATES: Rate Schedules DSW–SD2,

DSW–RS2, DSW–FR2, DSW–EI2, DSW–

SPR2, DSW–SUR2, PD–NTS2, and INT–

NTS2 will be placed into effect on an

interim basis on the first day of the first

full billing period beginning on or after

July 1, 2006, and will be in effect until

the Commission confirms, approves,

and places the rate schedules in effect

on a final basis through June 30, 2011,

or until the rate schedules are

superseded.

FOR FURTHER INFORMATION CONTACT: Mr.

Jack Murray, Rates Team Lead, Desert

Southwest Customer Service Region,

Western Area Power Administration,

P.O. Box 6457, Phoenix, AZ 85005–

6457; (602) 605–2442, e-mail

jmurray@wapa.gov.

SUPPLEMENTARY INFORMATION: The

Secretary of Energy approved Rate

Schedules DSW–SD1, DSW–RS1, DSW–

FR1, DSW–EI1, DSW–SPR1, DSW–

SUR1, PD–NTS1, and INT–NTS1 for the

Desert Southwest Region (DSWR)

network service for PDP and Intertie,

and ancillary services for the WALC

BATO on May 3, 1999 (Rate Order No.

WAPA–84, 64 FR 25323, May 11, 1999).

The Commission confirmed and

PO 00000

Frm 00019

Fmt 4703

Sfmt 4703

approved the rate schedules on January

20, 2000, in FERC Docket No. EF99–

5041–000, (90 FERC 62,032). Approval

for Rate Schedules DSW–SD1, DSW–

RS1, DSW–FR1, DSW–EI1, DSW–SPR1,

DSW–SUR1, PD–NTS1, and INT–NTS1

covered 5 years beginning on April 1,

1999, and ending on March 31, 2004.

These rate schedules were extended by

a series of Rate Orders through

September 30, 2006, with the most

recent Rate Order being Rate Order No.

WAPA–129 (71 FR 16572, April 3,

2006). The rate schedules were

extended to accommodate the Desert

Southwest Region (DSWR) MultiSystem Transmission Rate (MSTR)

process. An MSTR has not been

approved. However, Western plans to

seek approval of an MSTR for short-term

and non-firm transactions in the future.

The provisional formula for Network

Service in Rate Schedules PD–NTS2 and

INT–NTS2 will be the same as the

existing formula rates for Network

Service under Rate Schedules PD–NTS1

and INT–NTS1.

The existing transmission rates

include costs for Scheduling, System

Control, and Dispatch Services. The

transmission provisional formula rates

include the costs of these services.

Rate Schedules DSW–SD2, DSW–RS2,

DSW–FR2, DSW–EI2, DSW–SPR2, and

DSW–SUR2 supersede Rate Schedules

DSW–SD1, DSW–RS1, DSW–FR1,

DSW–EI1, DSW–SPR1, and DSW–SUR1,

respectively. Spinning Reserve and

Supplemental Reserve ancillary services

are being updated slightly to reflect

minor changes.

Under Schedule DSW–SD2,

Scheduling, System Control, and

Dispatch Service (Scheduling Service),

the rate is applied on a per tag basis.

The rate is calculated in two major

steps. First, the yearly costs associated

with capital improvements are

determined and divided by the number

of tags issued during the previous year.

Second, the average labor cost per tag is

determined and added to the capital

cost per tag. This methodology differs

from the previous methodology in that

it is based on tags rather than schedules

and a single rate is applied to all

transactions. These changes were made

because the tag was not used as a billing

unit when the rates under Rate Order

No. WAPA–84 were developed.

Under Schedule DSW–RS2, Reactive

Supply and Voltage Control Service

from Generation Sources (Voltage

Support Service), the rate is determined

by dividing the revenue requirement for

the service by the reservations for the

service. The revenue requirement for the

service is one minus the power factor

(1¥PF) times the combined generation

E:\FR\FM\26JNN1.SGM

26JNN1

This is a copy of a public record, reproduced as it was published. It is not legal advice, and it may not be the version a court would rely on. Check the official source before you cite it.

A word about cookies

We need a few to keep you signed in and the library working. The rest help us see which pages people use and where they get stuck. They stay off unless you say yes.