Federal Register / Vol. 72, No. 17 / Friday, January 26, 2007 / Notices
The staff of the Federal Energy
Regulatory Commission (FERC or
Commission) will prepare an
environmental assessment (EA) that will
discuss the environmental impacts of
the St. Petersburg Relay Project,
involving construction and operation of
facilities by Florida Gas Transmission
Company (FGT).1
FGT proposes to replace a total of
about 6.6 miles of its St. Petersburg 12inch-diameter lateral pipeline in eastcentral Pinellas County, Florida. Testing
of the 12-inch St. Petersburg Lateral
identified stress erosion cracking
anomalies reflective of the age and
condition of the pipeline. Replacement
of the pipeline sections and valve
assemblies described below are
necessary to comply with United States
Department of Transportation
requirements for a high consequence
Class 3 area under Title 49 CFR,
Pipeline Integrity Management, Subpart
O (Section 192). The pipeline is located
in a highly developed, urbanized area
that includes residential subdivisions,
shopping malls and existing county and
Florida Department of Transportation
(FDOT) road rights-of-way.
The sections of pipeline to be
replaced are described as follows:
• Relay #1—3.6 miles of pipeline,
• Relay #2—0.09 mile of pipeline,
• Relay #3—0.40 mile of pipeline,
• Relay #4—2.1 miles of pipeline, and
• Relay #5—0.5 mile of pipeline.
FGT also proposes to install a 12-inch
pig launcher and receiver and replace
two 8-inch block valves with 10-inch
block valves to allow passage for a
pipeline integrity tool to be run after the
segments have been replaced. The
general location of the project is shown
on the map attached as Appendix 1.2
No change in the maximum allowable
operating pressure of the pipeline
would occur as a result of the proposed
replacements. Therefore, there would be
no impact to FGT’s peak day or annual
gas deliveries.
The proposed project would disturb
up to 63.6 acres of land, 14.5 acres of
which are within FGT’s permanent
easement and 49.1 acres of which are
proposed temporary workspace and
extra temporary workspace. Temporary
workspace and extra temporary
workspace would be required at public
road and waterbody crossings,
hydrostatic test locations, crossovers,
tie-ins, staging/fabrication of pipeline
sections, and drag sections.
If you are a landowner receiving this
notice, you may be contacted by a
pipeline company representative about
the acquisition of an easement to
construct, operate, and maintain the
proposed facilities. The pipeline
company would seek to negotiate a
mutually acceptable agreement.
However, if the project is approved by
the Commission, that approval conveys
with it the right of eminent domain.
Therefore, if easement negotiations fail
to produce an agreement, the pipeline
company could initiate condemnation
proceedings in accordance with state
law.
A fact sheet prepared by the FERC
entitled ‘‘An Interstate Natural Gas
Facility on My Land? What Do I Need
to Know?’’ addresses a number of
typically asked questions, including the
use of eminent domain and how to
1 FGT’s original proposal to construct the St.
Petersburg Lateral Replacement Project was filed as
a prior notice application under Section 157.208(b)
of the Commission’s regulations. It is now being
processed as an application for construction under
Section 7(c) of the Natural Gas Act due to the filing
of a protest that was not resolved.
2 The appendix referenced in this notice is not
being printed in the Federal Register. Copies of the
appendix (maps) are available from the
Commission’s Public Reference Room, 888 First
Street, NE., Washington, DC 20426, or call (202)
502–8371. Copies of the appendix will be sent to
all those receiving this notice in the mail.
Commission, such as orders, notices,
and rulemakings.
In addition, the Commission now
offers a free service called eSubscription
which allows you to keep track of all
formal issuances and submittals in
specific dockets. This can reduce the
amount of time you spend researching
proceedings by automatically providing
you with notification of these filings,
document summaries and direct links to
the documents. Go to http://
www.ferc.gov/esubscribenow.htm.
Finally, public meetings or site visits
will be posted on the Commission’s
calendar located at http://www.ferc.gov/
EventCalendar/EventsList.aspx along
with other related information.
Magalie R. Salas,
Secretary.
[FR Doc. E7–1134 Filed 1–25–07; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Docket No. CP06–429–000]
Florida Gas Transmission Company;
Notice of Intent To Prepare an
Environmental Assessment for the
Proposed St. Petersburg Relay
Replacement Project and Request for
Comments on Environmental Issues
sroberts on PROD1PC70 with NOTICES
January 19, 2007.
VerDate Aug<31>2005
17:19 Jan 25, 2007
Jkt 211001
PO 00000
Frm 00057
Fmt 4703
Sfmt 4703
3835
participate in the Commission’s
proceedings. It is available for viewing
on the FERC Internet Web site (http://
www.ferc.gov).
The EA Process
The National Environmental Policy
Act (NEPA) requires the Commission to
take into account the environmental
impacts that could result from an action
whenever it considers the issuance of a
Certificate of Public Convenience and
Necessity. NEPA also requires us to
discover and address concerns the
public may have about proposals. This
process is referred to as ‘‘scoping’’. The
main goal of the scoping process is to
focus the analysis in the EA on the
important environmental issues. By this
Notice of Intent, the Commission staff
requests public comments on the scope
of the issues to address in the EA. All
comments received will be considered
during the preparation of the EA.
The Commission’s staff will prepare
an EA that will describe the potential
environmental impacts that could result
from construction and operation of the
proposed project under the general
headings:
• Water resources, wetlands, and
waterbodies.
• Vegetation and wildlife.
• Threatened and endangered
species.
• Cultural resources.
• Geology and soils.
• Land use and residences.
• Air quality and noise.
• Reliability and safety.
Our independent analysis of the
issues will be presented in the EA. We
will also evaluate possible alternatives
to the proposed project or portions of
the project, and make recommendations
on how to lessen or avoid impacts on
the various resource areas.
Depending on the comments received
during the scoping process, the EA may
be published and mailed to Federal,
State, and local government agencies;
public interest groups; Native American
tribes; interested individuals; affected
landowners; newspapers; libraries; and
the Commission’s official service list for
this proceeding. A 30-day comment
period will be allotted for review if the
EA is published. We will consider all
comments submitted in any
Commission Order that is issued for the
project.
To ensure your comments are
considered, please carefully follow the
instructions in the public participation
section below.
Public Participation
You can make a difference by
providing us with your specific
E:\FR\FM\26JAN1.SGM
26JAN1
3836
Federal Register / Vol. 72, No. 17 / Friday, January 26, 2007 / Notices
comments or concerns about the project.
By becoming a commenter, your
concerns will be addressed in the EA
and considered by the Commission. The
more specific your comments, the more
useful they will be. Generally,
comments are submitted regarding the
potential environmental effects,
reasonable alternatives and measures to
avoid or lessen environmental impact.
This notice and request for
environmental comments is being sent
to affected landowners; Federal, State
and local government representatives
and agencies; environmental and public
interest groups; other interested parties
in this proceeding; and local libraries
and newspapers. We encourage
government representatives to notify
their constituents of this notice and to
encourage their comments concerning
this proposed project.
To ensure that your comments are
properly recorded, please mail them to
our office on or before February 19,
2007. When filing comments please:
• Send an original and two copies of
your letter to: Magalie R. Salas,
Secretary, Federal Energy Regulatory
Commission, 888 First St., NE., Room
1A, Washington, DC 20426.
• Label one copy of the comments for
the attention of Gas Branch 2; DG2E;
and Reference Docket No. CP06–429–
000 on the original and both copies.
Please note that the Commission
strongly encourages the electronic filing
(‘‘eFiling’’) of comments, interventions
or protests to this proceeding.
Instructions on how to ‘‘eFile’’
comments can be found on the
Commission’s Web site at http://
www.ferc.gov under the ‘‘Documents
and Filings’’ link.
sroberts on PROD1PC70 with NOTICES
Becoming an Intervenor
In addition to involvement in the EA
scoping process, you may want to
become an official party to the
proceeding known as an ‘‘intervenor’’.
Intervenors play a more formal role in
the process. Among other things,
intervenors have the right to receive
copies of case-related Commission
documents and filings by other
intervenors. Likewise, each intervenor
must send one electronic copy (using
the Commission’s e-Filing system) or 14
paper copies of its filings to the
Secretary of the Commission and must
send a copy of its filings to all other
parties on the Commission’s service list
for this proceeding. If you want to
become an intervenor you must file a
motion to intervene according to Rule
214 of the Commission’s Rules of
Practice and Procedure (18 CFR
385.214). Only intervenors have the
VerDate Aug<31>2005
17:19 Jan 25, 2007
Jkt 211001
right to seek rehearing of the
Commission’s decision.
Affected landowners and parties with
environmental concerns may be granted
intervenor status upon showing good
cause by stating that they have a clear
and direct interest in this proceeding
which would not be adequately
represented by any other parties. You do
not need intervenor status to have your
environmental comments considered.
Environmental Mailing List
Additional Information
Additional information about the
project is available from the
Commission’s Office of External Affairs
at 1–866–208 FERC (3372) or on the
FERC Internet Web site (http://
www.ferc.gov).
To access information via the FERC
Web site click on the ‘‘eLibrary’’ link
then click on ‘‘General Search’’ and
enter the docket number excluding the
last three digits in the Docket Number
field. Be sure you have selected an
appropriate date range. The ‘‘eLibrary’’
link provides access to the texts of
formal documents issued by the
Commission such as orders, notices, and
rulemakings. For assistance with
‘‘eLibrary’’, please contact FERC Online
Support at FERCOnlineSupport@
ferc.gov or call toll free at 1–866–208–
3676, or for TTY, contact (202) 502–
8659.
In addition, the Commission now
offers a free service called eSubscription
which allows you to keep track of all
formal issuances and submittals in
specific dockets. This can reduce the
amount of time you spend researching
proceedings by automatically providing
you with notification of these filings,
document summaries and direct links to
the documents. Go to http://
www.ferc.gov/esubscribenow.htm.
Public meetings and/or site visits
along with other Project related
information will be posted on the
Commission’s calendar located at
Frm 00058
Fmt 4703
Sfmt 4703
Magalie R. Salas,
Secretary.
[FR Doc. E7–1173 Filed 1–25–07; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[ Docket No. CP07–28–000]
This notice has been sent to all known
individuals, organizations, and
government entities interested in and/or
potentially affected by the proposed
project. This includes all landowners
who are potential right-of-way grantors,
whose property may be used
temporarily for project purposes, or who
own homes within distances defined in
the Commission’s regulations of certain
aboveground facilities.
PO 00000
http://www.ferc.gov/EventCalendar/
EventsList.aspx.
Southern Natural Gas Company;
Notice of Intent To Prepare an
Environmental Assessment for the
Proposed 2007 Alabama Abandonment
& Replacement Project and Request
for Comments on Environmental
Issues
January 17, 2007.
The staff of the Federal Energy
Regulatory Commission (FERC or
Commission) will prepare an
environmental assessment (EA) that will
discuss the environmental impacts of
the 2007 Alabama Abandonment &
Replacement Project. This proposal
involves abandonment, construction,
and operation of facilities along
approximately 10 miles of Southern
Natural Gas Company’s (Southern)
existing natural gas pipeline system in
Tuscaloosa County, Alabama.
This notice announces the opening of
the scoping period that will be used to
gather environmental input from the
public and interested agencies on the
project. Your input will help us (the
commission staff) determine which
issues need to be evaluated in the EA.
Please note that the scoping period will
close on February 16, 2007.
This notice is being sent to potentially
affected landowners; Federal, State, and
local government agencies; elected
officials; environmental and public
interest groups; Native American Tribes;
other interested parties; and local
libraries and newspapers. State and
local government representatives are
asked to notify their constituents of this
proposed project and encourage them to
comment on their areas of concern.
If you are a landowner receiving this
notice, you may be contacted by a
pipeline company representative about
the acquisition of an easement to
construct, operate, and maintain the
proposed facilities. The pipeline
company would seek to negotiate a
mutually acceptable agreement.
However, if the project is approved by
the Commission, that approval conveys
with it the right of eminent domain.
Therefore, if easement negotiations fail
E:\FR\FM\26JAN1.SGM